3.

PEK PELAPISAN DINDING DI AREA TANGGA


NO. URAIAN PEKERJAAN Volume / Harga Satuan. Jumlah Harga Total Material Total upah kerja
Satuan ( Rp.) ( Rp.) ( Rp.) ( Rp.)

kayu ulin 17.500.000 /m³


4 Kebutuhan balok batang untuk dinding 1.7800 m³ 17,500,000 31,150,000 31,150,000
5 Upah serut, coak, belah, pinggul 1.7800 m³ 2,150,000 3,827,000 3,827,000
6 Kebutuhan balok 3/4 untuk bantalan 33.00 btng 158,960 5,245,680 5,245,680

8 Fisher S 8 6.0 box 22,000 132,000 132,000


9 Skrup 10 x 5 320.0 pcs 667 213,440 213,440
10 Skrup SDD 8 x 38 2,185.0 pcs 383 836,855 836,855
11 Ring D 6 x 20 734.0 pcs 315 231,210 231,210
12 Paku F 30 1.300 box 57,000 74,100 74,100
13 Paku F 50 1.000 box 122,700 122,700 122,700
14 Upah pemasangan 39.30 m² 196,000 7,702,800 7,702,800
15 Strager 4.00 set 387,600 1,550,400 1,550,400

38,005,985 13,080,200
51,086,185

Harga / meter 1,299,902.93 51,086,185


fee kontraktor fee 15 % 7,662,928
fee arsitek fee 5 % 2,554,309
61,303,422