b
1 DIVISI 1. UMUM
Mobilisasi
Bouwplank
Galian tanah
Pembesian D13
Pembesian Ø10
Pembesian D13
Pembesian Ø10
Beton Site Mix 1:2:3 (K225)
Bekisting 2x Pakai
Balok B3 (25x25 cm)
Pembesian D13
Pembesian Ø10
Bekisting 2x Pakai
Pembesian D13
Pembesian Ø10
Bekisting 2x Pakai
Pembesian Ø10
Pembesian Ø8
Bekisting 2x Pakai
BOBOT
dibuat oleh :
HARGA SATUAN
SAT KUANTITAS JUMLAH HARGA (RUPIAH) BOBOT
(RUPIAH)
c d e f = (d x e)
LS 1 Rp 30,000,000 4.95%
LS 1.00
LS 1.00
Bln 5.00
M1 40.00
LS Rp 10,968,000 1.81%
M3 By GAM By GAM
M3 By GAM By GAM
M3 226.80 25,000 Rp 5,670,000 0.94%
M3 0.00 By GAM
M3 120.00 20,000 Rp 2,400,000 0.40%
LS Rp 293,252,946 48.36%
kg -
kg - 9,750
kg 208.00 9,750 2,028,000.00 0.33%
LS 59,134,000.00 9.75%
LS 1 61,735,018.20 10.18%
LS 1 4,015,000.00 0.66%
M1 3.00 -
LS 1 15,250,000.00 2.52%
set 1.00 -
Rp 606,347,129 100.00%
Diperiksa oleh :
PT.BANTI INDONESIA
ABDUL RACHMAN
PJO
MBORONG
ASJID KM. 12
2.47% 15,000,000.00
#REF! #REF! -
#REF! #REF! -
#REF! #REF! -
#REF! #REF! -
0.90% 5,484,000.00
22.86% 138,591,879.38
1.89% 11,446,800.00
Total Penerimaan :
Dibayarkan :
dibulatkan
S/D BULAN INI
BOBOT JUMLAH
2.47% 15,000,000.00
2.47% 15,000,000.00
0.90% 5,484,000.00
0.47% 2,835,000.00
0.24% 1,449,000.00
0.20% 1,200,000.00
22.86% 138,591,879.38
0.45% 2,730,021.84
0.23% 1,377,788.80
0.33% 2,015,520.00
0.62% 3,746,800.00
0.62% 3,773,853.72
0.28% 1,683,126.40
0.77% 4,649,062.50
0.21% 1,284,716.16
0.11% 648,371.20
0.00% -
0.27% 1,653,000.00
0.28% 1,712,954.88
0.09% 572,979.20
0.00% -
0.27% 1,653,000.00
0.11% 642,229.40
0.05% 287,695.28
0.00% -
0.26% 1,552,442.50
0.92% 5,607,027.74
1.05% 6,395,400.00
0.08% 487,350.00
1.74% 10,537,000.30
2.21% 13,376,000.00
0.20% 1,216,000.00
0.19% 1,155,000.00
8.86% 53,718,876.51
2.66% 16,115,662.95
1.89% 11,446,800.00
1.89% 11,446,800.00
0.21% 4,140,000.00
0.05% 315,000.00
0.07% 405,000.00
0.09% 570,000.00
0.10% 600,000.00
0.37% 2,250,000.00
174,662,679.38
Rp 174,662,679
Rp 8,733,134
Rp 165,929,545
Rp 165,929,545
Rp 165,929,545
Rp 165,929,000