REKAP RAB

NAMA PEKERJAAN : Pekerjaan Landscape Forest House


LOKASI : Sukabumi
LUAS LAHAN : 3000 m2
TAHUN 2024

NO JENIS PEKERJAAN BIAYA PEKERJAAN

A PEKERJAAN PERSIAPAN 122.326.880,00


B PEKERJAAN WELCOME AREA (ENTRANCE 1) 506.787.242,00
C PEKERJAAN WELCOME AREA (ENTRANCE 2) 408.452.072,00
D PEKERJAAN ZONA TAMAN CAFE, PLAZA DAN SEATING AREA 1.111.577.588,00
E PEKERJAAN ZONA HUTAN PINUS 629.912.667,00
F PEKERJAAN ZONA KEBUN BUAH 866.653.220,00
TOTAL 3.645.709.669,00
Fee Desain 2,5% 91.142.741,73

GRANDTOTAL 3.736.852.410,73

Bogor, 01 April 2024


Hendra Witama
Landscape Architect
& Pekerjaan Sipil
RENCANA ANGGARAN BIAYA

NAMA PEKERJAAN : Pekerjaan Landscape Forest House


LOKASI : Sukabumi
LUAS LAHAN : 3000 M2
TAHUN : 2024

NO JENIS PEKERJAAN SAT VOL HARGA (Rp) JUMLAH (Rp)

A PEKERJAAN PERSIAPAN

1 Pekerjaan pematokan dan pengukuran ulang site (alat: Total Station) m2 2.250,00 3.900,00 8.775.000,00
2 Pekerjaan Direksi Keet (Gudang sementara) m2 16,00 1.771.680,00 28.346.880,00
3 Pekerjaan pembersihan dan pematangan lahan area landscape m2 2.250,00 12.240,00 27.540.000,00
4 Pekerjaan mobilisasi dan demobilisasi alat ls 1,00 18.820.000,00 18.820.000,00
5 Pekerjaan pembongkaran bangunan eksisting m2 126,00 120.000,00 15.120.000,00
6 Pekerjaan buangan sampah dan bongkaran ls 1,00 17.500.000,00 17.500.000,00
7 Pekerjaan air dan listrik sementara & rumah pompa ls 1,00 6.225.000,00 6.225.000,00

Total Pekerjaan A 122.326.880,00


RENCANA ANGGARAN BIAYA

NAMA PEKERJAAN : Pekerjaan Landscape Forest House


LOKASI : Sukabumi
LUAS LAHAN : 3000 M2
TAHUN : 2024

NO JENIS PEKERJAAN SAT VOL HARGA (Rp) JUMLAH (Rp)

B PEKERJAAN WELCOME AREA (ENTRANCE 1)

1 Pekerjaan Perkerasan Aspal Jalan m2 138,00 384.000,00 52.992.000,00


2 Pekerjaan Pintu Gerbang Entrance 1 m2 12,50 4.255.200,00 53.190.000,00
3 Pekerjaan Edging Penjepit, pasangan 1/2 bata tinggi 15 cm + fin.cat m' 58,00 439.440,00 25.487.520,00
4 Pemasangan Lampu Taman t.3-4m
Pek. lampu taman t. 3m incl.instalasi set 8,00 9.505.555,00 76.044.440,00
(Body Steel Plate fin.powder coating, cover acliric, Lamp Prevaled Sky
48 W, Tiang pipa galvanis 2.5 inch)
Pek. Pondasi lampu taman titik 8,00 603.750,00 4.830.000,00
Pek. penyambungan panel dan akesoris ls 1,00 5.664.000,00 5.664.000,00
5 Pemasangan Lampu Tree Uplight incl. instalasi bh 6,00 1.443.600,00 8.661.600,00
6 Pemasangan Kran penyiraman outdoor incl.instalasi bh 2,00 1.049.040,00 2.098.080,00
7 Bangunan Pendopo 3x4m m2 12,00 6.216.000,00 74.592.000,00
8 Pekerjaan Penanaman
Urugan Tanah Subur (Top soil) m3 15,15 521.880,00 7.906.482,00
Pemupukan dan obat hama ls 1,00 4.340.000,00 4.340.000,00
Ki damar (Agathis dammara) t=3-4m, dia.btg 5-8cm pohon 7,00 1.058.760,00 7.411.320,00
Ketapang kencana (Terminalia mantally) t=3-4m, dia.btg 5-8cm pohon 7,00 2.066.400,00 14.464.800,00
Pulai (Alstonia schrolaris) t=5-6m ,dia.btg 30-50cm pohon 1,00 50.500.000,00 50.500.000,00
Kapuk randu t=3-5m, dia.btg.30-50cm pohon 1,00 47.500.000,00 47.500.000,00
Trembesi (Samanea saman) t=4-5m, dia.btg 5-8cm pohon 7,00 2.375.000,00 16.625.000,00
Rumput gajah mini (Axonopus dwarf) m2 280,00 66.000,00 18.480.000,00
Semak dan groundcover kombinasi variasi jenis m2 20,00 1.800.000,00 36.000.000,00

Total Pekerjaan B 506.787.242,00


RENCANA ANGGARAN BIAYA

NAMA PEKERJAAN : Pekerjaan Landscape Forest House


LOKASI : Sukabumi
LUAS LAHAN : 3000 M2
TAHUN : 2024

NO JENIS PEKERJAAN SAT VOL HARGA (Rp) JUMLAH (Rp)

C PEKERJAAN WELCOME AREA (ENTRANCE 2)

1 Pekerjaan Perkerasan Aspal Jalan m2 130,00 384.000,00 49.920.000,00


2 Pekerjaan Pagar (beton precast) m2 26,00 1.482.000,00 38.532.000,00
3 Pekerjaan Pintu Gerbang Entrance 1 m2 12,50 4.255.200,00 53.190.000,00
4 Pekerjaan Turap/ Retaining Wall m2 16,50 3.704.880,00 61.130.520,00
5 Pekerjaan Edging Penjepit, pasangan 1/2 bata tinggi 15 cm + fin.cat m' 63,00 439.440,00 27.684.720,00
6 Pemasangan Lampu Taman t.3-4m
Pek. lampu taman t. 3m incl.instalasi set 4,00 9.505.555,00 38.022.220,00
(Body Steel Plate fin.powder coating, cover acliric, Lamp Prevaled Sky
48 W, Tiang pipa galvanis 2.5 inch)
Pek. Pondasi lampu taman titik 8,00 603.750,00 4.830.000,00
Pek. penyambungan panel dan akesoris ls 1,00 5.664.000,00 5.664.000,00
7 Pemasangan Lampu Tree Uplight incl. instalasi bh 4,00 1.443.600,00 5.774.400,00
8 Pemasangan Kran penyiraman outdoor incl.instalasi bh 2,00 1.049.040,00 2.098.080,00
9 Pekerjaan Penanaman
Urugan Tanah Subur (Top soil) m3 15,90 521.880,00 8.297.892,00
Pemupukan dan obat hama ls 1,00 3.340.000,00 3.340.000,00
Ki damar (Agathis dammara) t=3-4m, dia.btg 5-8cm pohon 14,00 1.058.760,00 14.822.640,00
Ketapang kencana (Terminalia mantally) t=3-4m, dia.btg 5-8cm pohon 4,00 2.066.400,00 8.265.600,00
Rumput gajah mini (Axonopus dwarf) m2 280,00 66.000,00 18.480.000,00
Semak dan groundcover kombinasi variasi jenis m2 38,00 1.800.000,00 68.400.000,00

Total Pekerjaan B 408.452.072,00


RENCANA ANGGARAN BIAYA

NAMA PEKERJAAN : Pekerjaan Landscape Forest House


LOKASI : Sukabumi
LUAS LAHAN : 3000 M2
TAHUN : 2024

NO JENIS PEKERJAAN SAT VOL HARGA (Rp) JUMLAH (Rp)

D PEKERJAAN ZONA TAMAN CAFE, PLAZA DAN SEATING AREA

2 Pekerjaan Pagar (beton precast) m2 28,50 1.482.000,00 42.237.000,00


4 Pekerjaan Turap/ Retaining Wall m2 28,50 3.704.880,00 105.589.080,00
1 Pekerjaan Edging Penjepit, pasangan 1/2 bata tinggi 15 cm + fin.cat m' 153,00 439.440,00 67.234.320,00
2 Pekerjaan Stepping Stone WPC outdoor m2 16,00 1.272.500,00 20.360.000,00
3 Pekerjaan Blumbak t= 80cm
Pek. galian tanah m3 5,60 164.160,00 919.296,00
Pek. pondasi batu belah 1PC:4PP m3 0,90 1.537.896,00 1.384.106,40
Pek. pasangan bata m2 7,68 450.360,00 3.458.764,80
Pek. angkur besi kg 12,00 30.600,00 367.200,00
Pek. fin.batu alam palimanan m2 7,68 566.760,00 4.352.716,80
4 Pekerjaan lantai batu split (area cafe) m2 54,00 425.640,00 22.984.560,00
5 Pekerjaan Lantai Stamp/Pattern Concrete
Pek.galian tanah m3 38,00 164.160,00 6.238.080,00
Pek.urugan sirtu dan pemadatan tb.10cm m3 19,00 399.264,00 7.586.016,00
Pek. cor beton K 250 tb.8 cm m3 15,20 1.697.760,00 25.805.952,00
Pembesian wiremesh M6 single layer m2 190,00 162.344,00 30.845.360,00
Pek. Decorative/ Pattern Concrete (variasi pola & warna custom) m2 190,00 802.687,50 152.510.625,00
(Colour hardener, ex. Germany, Semigloss Solvent based Acrylic
Concrete Selaer)
6 Pemasangan Lampu Taman t.3-4m
Pek. lampu taman t. 3m incl.instalasi set 10,00 9.505.555,00 95.055.550,00
(Body Steel Plate fin.powder coating, cover acliric, Lamp Prevaled Sky
48 W, Tiang pipa galvanis 2.5 inch)
Pek. Pondasi lampu taman titik 10,00 603.750,00 6.037.500,00
Pek. penyambungan panel dan akesoris ls 1,00 8.720.000,00 8.720.000,00
7 Pemasangan Lampu Tree Uplight incl. instalasi bh 11,00 1.443.600,00 15.879.600,00
8 Pemasangan Kran penyiraman outdoor incl.instalasi bh 3,00 1.049.040,00 3.147.120,00
9 Bangku meja panjang taman outdoor set 2,00 7.333.000,00 14.666.000,00
10 Bangku meja payung patio set 4,00 6.536.000,00 26.144.000,00
11 Pekerjaan kandang aviary burung merak set 1,00 22.430.000,00 22.430.000,00
11 Pekerjaan Penanaman
Urugan Tanah Subur (Top soil) m3 29,35 580.860,00 17.048.241,00
Pemupukan dan obat hama ls 1,00 6.400.000,00 6.400.000,00
Pulai (Alstonia schrolaris) t=5-6m ,dia.btg 30-50cm pohon 1,00 50.500.000,00 50.500.000,00
Kapuk randu t=3-5m, dia.btg.30-50cm pohon 1,00 47.500.000,00 47.500.000,00
Baobab t=3-5m, dia.btg.30-50cm pohon 1,00 87.700.000,00 87.700.000,00
Selobium/Pakis brazil (Shzolobium parahyba) t=3-4m, dia.btg 5-8cm pohon 7,00 3.275.000,00 22.925.000,00
Karet kebo kuning (Ficus spp) t=3-4m, dia.btg 5-8cm pohon 3,00 3.722.300,00 11.166.900,00
Pakis monyet t=2-3m, dia.btg 5-8cm pohon 2,00 3.754.500,00 7.509.000,00
Kayu putih (Melaluca sp.) t=3-4m dia.btg 5-8cm pohon 4,00 2.887.000,00 11.548.000,00
Jacaranda sp. t=3-4m dia.btg 5-8cm pohon 4,00 2.832.000,00 11.328.000,00
Sikat botol (Calllistemon sp.) t=3-4m, dia.btg 5-8cm pohon 4,00 2.850.000,00 11.400.000,00
Trembesi (Samanea saman) t=4-5m, dia.btg 5-8cm pohon 6,00 2.375.000,00 14.250.000,00
Ketapang kencana (Terminalia mantally) t=3-4m, dia.btg 5-8cm pohon 9,00 2.066.400,00 18.597.600,00
Rumput gajah mini (Axonopus dwarf) m2 587,00 66.000,00 38.742.000,00
Semak dan groundcover kombinasi variasi jenis m2 75,00 946.800,00 71.010.000,00

Total Pekerjaan C 1.111.577.588,00


RENCANA ANGGARAN BIAYA

NAMA PEKERJAAN : Pekerjaan Landscape Forest House


LOKASI : Sukabumi
LUAS LAHAN : 3000 M2
TAHUN : 2024

NO JENIS PEKERJAAN SAT VOL HARGA (Rp) JUMLAH (Rp)

E PEKERJAAN ZONA HUTAN PINUS

1 Pekerjaan Turap/ Retaining Wall m2 29,40 3.704.880,00 108.923.472,00


2 Pekerjaan Tangga m2 12,00 2.266.550,00 27.198.600,00
3 Pekerjaan Jalan setapak m2 142,00 1.027.875,00 145.958.250,00
4 Pemasangan Lampu Taman t.3-4m
Pek. lampu taman t. 3m incl.instalasi set 11,00 9.505.555,00 104.561.105,00
(Body Steel Plate fin.powder coating, cover acliric, Lamp Prevaled Sky
48 W, Tiang pipa galvanis 2.5 inch)
Pek. Pondasi lampu taman titik 11,00 603.750,00 6.641.250,00
Pek. penyambungan panel dan akesoris ls 1,00 8.715.000,00 8.715.000,00
5 Pemasangan Lampu Tree Uplight incl. instalasi bh 11,00 1.443.600,00 15.879.600,00
6 Pemasangan Kran penyiraman outdoor incl.instalasi bh 4,00 1.049.040,00 4.196.160,00
7 Pekerjaan Penanaman
Urugan Tanah Subur (Top soil) m3 30,50 580.860,00 17.716.230,00
Pemupukan dan obat hama ls 1,00 5.350.000,00 5.350.000,00
Pinus merkusii t=3-4m pohon 65,00 1.285.000,00 83.525.000,00
Rumput gajah mini (Axonopus dwarf) m2 608,00 66.000,00 40.128.000,00
Semak dan groundcover kombinasi variasi jenis m2 32,00 1.910.000,00 61.120.000,00

Total Pekerjaan D 629.912.667,00


RENCANA ANGGARAN BIAYA

NAMA PEKERJAAN : Pekerjaan Landscape Forest House


LOKASI : Sukabumi
LUAS LAHAN : 3000 M2
TAHUN : 2024

NO JENIS PEKERJAAN SAT VOL HARGA (Rp) JUMLAH (Rp)

F PEKERJAAN ZONA KEBUN BUAH

1 Pekerjaan Turap/ Retaining Wall m2 21,00 3.704.880,00 77.802.480,00


2 Pekerjaan Tangga & ramp m2 36,00 2.684.500,00 96.642.000,00
3 Pekerjaan pagar pembatas hunian privat m2 81,00 1.853.000,00 150.093.000,00
4 Pekerjaan Green House & Gudang Penyimpanan m2 12,00 6.725.700,00 80.708.400,00
5 Pekerjaan Jalan setapak m2 83,00 1.027.875,00 85.313.625,00
6 Pemasangan Lampu Taman t.3-4m
Pek. lampu taman t. 3m incl.instalasi set 13,00 9.505.555,00 123.572.215,00
(Body Steel Plate fin.powder coating, cover acliric, Lamp Prevaled Sky
48 W, Tiang pipa galvanis 2.5 inch)
Pek. Pondasi lampu taman titik 13,00 603.750,00 7.848.750,00
Pek. penyambungan panel dan akesoris ls 1,00 8.005.000,00 8.005.000,00
7 Pemasangan Kran penyiraman outdoor incl.instalasi bh 6,00 1.049.040,00 6.294.240,00
8 Pekerjaan Penanaman
Urugan Tanah Subur (Top soil) m3 28,50 580.860,00 16.554.510,00
Pemupukan dan obat hama ls 1,00 8.750.000,00 8.750.000,00
Rambutan t=2,5-3m pohon 8,00 2.725.000,00 21.800.000,00
Mangga t=1,5-2,5m pohon 14,00 2.244.200,00 31.418.800,00
Sawo manila t=1,5-2m pohon 8,00 2.282.550,00 18.260.400,00
Jeruk siam t=1-1,5m pohon 8,00 1.852.500,00 14.820.000,00
Jambu air t=1,5-2m pohon 8,00 2.803.500,00 22.428.000,00
Sukun t=2-2,5m pohon 4,00 2.764.500,00 11.058.000,00
Delima t=1-1,5m pohon 4,00 2.774.300,00 11.097.200,00
Srikaya t=1-1,5m pohon 8,00 2.843.000,00 22.744.000,00
Buah tin t=80-150cm pohon 6,00 1.854.700,00 11.128.200,00
Rumput gajah mini (Axonopus dwarf) m2 402,00 66.000,00 26.532.000,00
Semak dan perdu tanaman obat m2 8,00 1.722.800,00 13.782.400,00

Total Pekerjaan E 866.653.220,00