AHSP 2
AHSP 2
5 PEKERJAAN DINDING
P14 Pemasangan Dinding Batu Bata M2 3.3 Rp 109,380.90
70.000 Batu Bata Merah MT15 Buah Rp 700.00 Rp 49,000.00
0.194 Semen Portland 50 Kg MT16 Zak Rp 61,100.00 Rp 11,853.40
0.045 Pasir Pasang MT07 M3 Rp 169,100.00 Rp 7,609.50
0.300 Pekerja TK01 Or/Hari Rp 85,500.00 Rp 25,650.00
0.100 Tukang Batu TK04 Or/Hari Rp 109,300.00 Rp 10,930.00
0.010 Kepala Tukang TK03 Or/Hari Rp 136,800.00 Rp 1,368.00
0.015 Mandor TK02 Or/Hari Rp 198,000.00 Rp 2,970.00