BIDANG PEMBANGUNAN APBDES ALOKASI BIAYA DD TA 2018

DESA : Pupus
KEC : Lembeyan
KAB : Magetan

NO JENIS KEGIATAN LOKASI VOLUME

1 Rabat Beton Dk Marokan RT 001/002 72mx2.5mx0.10 - 60mx2.0x0.10


2 Rabat Beton Dk Duduk RT 002/003 134mx2.5mx0.10
3 Rabat Beton Dk Pandeyan RT 003/005 120mx2.5mx0.10
4 Rabat Beton Dk Grumbul Malang RT 001/011 107mx3.00mx0.12
5 Pembangunan Talud/saluran RT 001/007 Panjang 28.5 m
6 Pembangunan Talud/saluran RT 002/002 Panjang 28m
7 Pembangunan Talud Jalan RT 003/001 Panjang 55 m
8 Pembangunan Talud Jalan RT 006/001 Panjang 48 m
9 Pembangunan Talud Jalan RT 002/003 Panjang 39 m
10 Pembangunan Talud Jalan RT 001/005 Panjang 28 m
11 Pembangunan Talud Jalan RT 002/012 Panjang 22 m
12 Pembangunan Talud Jalan Jomblang P 65 L 0.30 T 0.60
13 Pambuatan jalan dan saluran Blok Barat Panjang 130 m Lebar 5 m
14 Rehabilitasi Pasar Desa Blok Paron Kios 3x4 = ( 4 Unit )
15 Pembangunan Jembatan Jomblang Blok Jomblang P 3.0 m, L 4.40 m
16 Pengembangan Sumur Pamsimas Pupus
17 RTLH Sepintu
18 Cat Gapuro
19 Saluran Grumbul Malang
20 Lapen Pupus
21 Rehab Ruang PKK

TOTAL
PROSENTASE
BAHAN ALAT UPAH BIAYA UMUM TOTAL BIAYA RAB UPAH DAN BIAYA
TOTAL
1 2 3 4 5'=1+2+3+4 6=3/5

23,833,300.00 386,700.00 3,780,000.00 2,000,000.00 30,000,000.00 12.60%


27,013,400.00 410,300.00 4,020,000.00 2,056,500.00 33,500,200.00 12.00%
23,833,300.00 386,700.00 3,780,000.00 2,000,000.00 30,000,000.00 12.60%
30,977,300.00 386,700.00 4,840,000.00 2,296,000.00 38,500,000.00 12.57%
10,795,100.00 184,900.00 4,820,000.00 1,200,000.00 17,000,000.00 28.35%
9,271,850.00 189,400.00 4,500,000.00 1,040,000.00 15,001,250.00 30.00%
13,286,350.00 184,400.00 5,180,000.00 1,350,000.00 20,000,750.00 25.90%
9,806,400.00 206,250.00 3,960,000.00 1,027,500.00 15,000,150.00 26.40%
9,814,850.00 205,400.00 4,120,000.00 860,000.00 15,000,250.00 27.47%
12,234,050.00 226,250.00 5,340,000.00 1,200,000.00 19,000,300.00 28.10%
9,589,750.00 162,050.00 4,240,000.00 1,008,200.00 15,000,000.00 28.27%
7,522,200.00 223,000.00 3,460,000.00 795,000.00 12,000,200.00 28.83%
269,311.50 8,859,299.54 2,300,000.00 571,430.55 12,000,041.59 19.17%
47,579,389.77 1,940,600.00 38,560,000.00 6,428,579.77 94,508,569.54 40.80%
31,138,159.53 1,380,050.00 2,720,000.00 1,761,912.28 37,000,121.81 7.35%
0.00 0.00 70,000,000.00 0.00 70,000,000.00 100.00%
6,000,000.00 0.00 2,695,000.00 0.00 8,695,000.00 30.99%

272,964,710.80 15,331,999.54 168,315,000.00 25,595,122.60 482,206,833


TOTAL BIAYA RAB 482,206,833
TOTAL BIAYA UPAH 168,315,000
PROSENTASE UPAH TERHADAP TOTAL BIAYA RAB 0.35
PAGU 30% UPAH HOK PADAT KARYA TUNAI 144,662,050
KEKURANGAN UPAH UNTUK MENCAPAI 30% (23,652,950)

Mengetahui
Kepala Desa Pupus

TUMIRAN
KETERANGAN

DBHPRD Rp. 40,491,600