Anda di halaman 1dari 3

ANALISA EXCAVATOR : - KAPASITAS PRODUKSI = 300M3/ Hari 25

- JUMLAH SOLAR/ JAM = 14,22Ltr/ Jam


- JAM KERJA = 12Jam/ Hari
- JUMLAH SOLAR/ HARI = 170,64Ltr/ Hari
- JUMLAH SOLAR TOTAL = ( 18.595,49) Ltr

DATA KONTRAK : VOLUME GALIAN TOTAL = ( 32.692,50) M3


JUMLAH HARI SESUAI AN = 108,975Hari

DATA LAPANGAN : VOLUME TERLAKSANA SESUAI BACKUP DATA = ( 41.132,49) M3


TGL MULAI KERJA = 9/11/2014
TGL BERAKHIR KERJA = 11/29/2014
JUMLAH HARI KERJA = 49 Hari

PERMASALAHAN : BERDASARKAN ANALISA BERARTI DALAM 49 HARI KERJA DIDAPATKAN VOLUME :


= 300 x 49
= 14.700 M3

ARTINYA ADA KEKURANGAN VOLUME = ( 17.992,50) M3

RATA - RATA PEKERJAAN BERDASARKAN ANALISA 56 M/ HARI


REAL RATA - RATA PEKERJAAN DI LAPANGAN 125 M/ HARI

PEKERJAAN 11 SEPTEMBER 2014 s.d 28 NOPEMBER 2014