Tanggal : 3/19/2021
NO JENIS STRUKTUR SATUAN RENCANA REALISASI SISA
1 Box Culvert Buah 17.00 17.00
2 Dinding Penahan Tanah m3 -
3 Saluran m3 -
4 Bronjong m3 -
5 Patok Pengarah Buah -
6 Patok KM Buah -
7 Rambu Engineer Grade Buah -
8 Rambu High Intensity Grade Buah -
9 Guard Rail m -
A BOX CULVERT
B BETON FC 10
C BETON FC 30
D BEKISTING
3 PLAT INJAK
Lantai bawah 5.00 0.20 1.00 2.00 2.00 8.00 16.00
0.40 0.20 0.08 2.00 0.16 8.00 1.28
Lantai Atas 5.00 0.20 1.00 2.00 2.00 12.00 24.00
3.30 0.20 0.66 2.00 1.32 12.00 15.84
Pier Head 12.00 0.48 5.76 1.00 5.76 2.00 11.52
0.06 2.00 0.12 2.00 0.24
JUMLAH 68.88
E BESI
Kode Diameter Panjang Tekukan ( m ) Jml panj. Jml Tul. Keb. Btg 12 M Pjg. Sisa Rekap Keb. Btg 12 M Berat Tot. Berat (Kg)
No Gambar / Sket Pemakian sisa
Tulangan
Jarak a b c d e f g (m) ( Potong ) ( btg ) (m) ( btg ) P10 P12 P16 P19 ( Kg /m') Terpasang Pengadaan
b
e
d
c
2. Tulangan Pokok (14/0.2)x2
b 1A2 ∅ 12 - 20 0.05 1.29 0.12 1.29 0.12 0.05 2.92 140 35 0.32 35 - 35 - - 0.89 362.75 372.69
f
e a c
d
B Memanjang
(1.34/0.2)x2x2
1B1 ∅ 10 - 20 7.40 7.40 28 28 4.60 28 28 - - - 0.62 127.68 207.05
a b 1B2 ∅ 10 - 20 7.40 7.40 28 28 4.6 28.0 28 - - - 0.62 127.68 207.05
e c
d
B Memanjang
(1.84/0.2)x2x2
2B1 ∅ 10 - 20 7.40 7.40 40 40 4.60 40 40 - - - 0.62 182.40 295.79
3 Koperan
A Melintang
b
1. Tulangan Pokok (1.34/0.2)x2
a f
3A1 ∅ 10 - 20 0.05 0.35 0.92 0.35 0.92 0.05 2.64 14 4 1.44 4 4 - - - 0.62 22.78 29.58
e c
d
B Memanjang
1. Tulangan Bagi 8x2
3B1 ∅ 10 1.29 1.29 16 2 0.39 2 2 - - - 0.62 12.72 14.79
a
4 Kerb
A Melintang
1. Tulangan Pokok (4.97/0.2)x2
4A1 ∅ 10 - 20 0.05 0.15 0.45 0.25 0.16 0.29 0.05 1.40 50 4 0.80 4 5B2.5A1.4B1 (29) 4 - - - 0.62 43.14 29.58
a g
f
c
e
d
B Memanjang
1. Tulangan Bagi 7x2
4B1 ∅ 10 4.97 4.97 14 2.06 - 1B1 - - - - 0.62 42.88 -
a
5 Wingwall
1. Tulangan Vertikal b (1.84/0.2)x4
a f 5A1 ∅ 10 - 20 0.05 0.15 2.19 0.15 2.19 0.05 4.78 40 2.44 - 1B1,1B3 - - - - 0.62 117.82 -
e c
d
2. Tulangan Horizontal (2.21/0.2)x4
5A2 ∅ 10 - 20 0.05 1.90 0.15 1.9 0.2 0.1 4.20 48 3.60 - 2B1, 2B3 - - - - 0.62 124.23 -
f b
e a c
d
Kode Diameter Panjang Tekukan ( m ) Jml panj. Jml Tul. Keb. Btg 12 M Pjg. Sisa Rekap Keb. Btg 12 M Berat Tot. Berat (Kg)
No Gambar / Sket Pemakian sisa
Tulangan
Jarak a b c d e f g (m) ( Potong ) ( btg ) (m) ( btg ) P10 P12 P16 P19 ( Kg /m') Terpasang Pengadaan
b
e
d
c
2. Tulangan Pokok (14/0.2)x4
b 1A2 ∅ 12 - 20 0.05 2.44 0.19 2.44 0.19 0.05 5.36 280 140 1.28 140 - 140 - - 0.89 1,331.76 1,490.77
f
e a c
d
B Memanjang
(2.5/0.2)x2x4
1B1 ∅ 10 - 20 7.40 7.40 104 104 4.60 104 104 - - - 0.62 474.25 769.05
a b 1B2 ∅ 10 - 20 7.40 7.40 104 104 4.60 104 104 - - - 0.62 474.25 769.05
3 Koperan
A Melintang
b
1. Tulangan Pokok (2.5/0.2)x2
a f
3A1 ∅ 10 - 20 0.05 0.35 0.92 0.35 0.92 0.05 2.64 26 1.44 - 1B1 - - - - 0.62 42.30 -
e c
d
B Memanjang
1. Tulangan Bagi 8x2
3B1 ∅ 10 2.45 2.45 16 2.20 - 1B1 - - - - 0.62 24.16 -
a
4 Kerb
A Melintang
1. Tulangan Pokok (7.5/0.2)x2
4A1 ∅ 10 - 20 0.05 0.15 0.45 0.25 0.16 0.29 0.05 1.40 76 0.80 - 1B2 - - - - 0.62 65.57 -
a g
f
c
e
d
B Memanjang
1. Tulangan Bagi 7x2
4B1 ∅ 10 7.45 7.45 14 14 4.55 14 14 - - - 0.62 64.27 103.53
a
5 Wingwall
1. Tulangan Vertikal b (2.5/0.2)x4
a f 5A1 ∅ 16 - 20 0.05 0.15 2.93 0.15 2.93 0.05 6.26 52 52 5.74 52 - - 52 - 1.58 513.52 984.38
e c
d
2. Tulangan Horizontal (2.95/0.2)x4
5A2 ∅ 16 - 20 0.05 2.60 0.15 2.60 0.15 0.05 5.60 60 5 0.80 5 5A1 (50) - - 5 - 1.58 530.05 94.65
f b
e a c
d
Kode Diameter Panjang Tekukan ( m ) Jml panj. Jml Tul. Keb. Btg 12 M Pjg. Sisa Rekap Keb. Btg 12 M Berat Tot. Berat (Kg)
No Gambar / Sket Pemakian sisa
Tulangan
Jarak a b c d e f g (m) ( Potong ) ( btg ) (m) ( btg ) P10 P12 P16 P19 ( Kg /m') Terpasang Pengadaan
JUMLAH BATANG 233 140 57 70 5,388.79 6,161.41
BOX CULVERT (TIPE 1.0 X 1.5) P = 14 m
b
e
d
c
2. Tulangan Pokok
f b 1A2 ∅ 12 -### 0.05 1.29 0.12 1.29 0.12 0.05
e a c
d
3. Tulangan Siku
a 1A3 ∅ 10 -### 0.43
B Memanjang
2. Tulangan Pokok
b 2A2 ∅ 12 -### 0.05 0.12 1.79 0.12 1.79 0.05
a f
e c
d
B Memanjang
3 Koperan
A Melintang
b
1. Tulangan Pokok
a f
3A1 ∅ 10 -### 0.05 0.35 0.92 0.35 0.92 0.05
e c
d
B Memanjang
1. Tulangan Bagi
3B1 ∅ 10 1.29
a
4 Kerb
A Melintang
1. Tulangan Pokok
4A1 ∅ 10 -### 0.05 0.15 0.45 0.25 0.16 0.29 0.05
a g
f
c
e
d
B Memanjang
1. Tulangan Bagi
4B1 ∅ 10 4.97
a
5 Wingwall
1. Tulangan Vertikal b
a f 5A1 ∅ 10 -### 0.05 0.15 2.19 0.15 2.19 0.05
e c
d
2. Tulangan Horizontal
5A2 ∅ 10 -### 0.05 1.90 0.15 1.9 0.2 0.1
f b
e a c
d
b
e
d
c
2. Tulangan Pokok
b 1A2 ∅ 12 - 20 0.05 2.44 0.19 2.44 0.19 0.05
f
e a c
d
3. Tulangan Siku
1A3 ∅ 10 - 20 0.65
a
B Memanjang
a b 1B1 ∅ 10 - 20 7.40
1B2 ∅ 10 - 20 7.40
3 Koperan b
A Melintang a f
1. Tulangan Pokok
3A1 ∅ 10 - 20 0.05 0.35 0.92 0.35 0.92 0.05
e c
d
B Memanjang
a
1. Tulangan Bagi
3B1 ∅ 10 2.45
4 Kerb
A Melintang
a g
1. Tulangan Pokok f
4A1 ∅ 10 - 20 0.05 0.15 0.45 0.25 0.16 0.29 0.05
c
e
d
B Memanjang
1. Tulangan Bagi a
4B1 ∅ 10 7.45
5 Wingwall
1. Tulangan Vertikal b
a f 5A1 ∅ 16 - 20 0.05 0.15 2.93 0.15 2.93 0.05
e c
d
2. Tulangan Horizontal
5A2 ∅ 16 - 20 0.05 2.60 0.15 2.60 0.15 0.05
f b
e a c
d
Kode Diameter Panjang Tekukan ( m ) Jml panj. Jml Tul. Keb. Btg 12 M Pjg. Sisa Rekap Keb. Btg 12 M Berat Tot. Berat (Kg)
No Gambar / Sket Pemakian sisa
Tulangan
Jarak a b c d e f g (m) ( Potong ) ( btg ) (m) ( btg ) P10 P12 P16 P19 ( Kg /m') Terpasang Pengadaan
1 Lantai Bawah
A Melintang
1. Tulangan Pokok (10/0.2)x4
b 1A1 ∅ 12 - 20 0.05 0.35 0.15 0.35 0.15 0.05 1.10 200 20 1.00 20 - 20 - - 0.89 195.22 212.97
f
e a c
d
B Memanjang
1. Tulangan Pembagi
(0.4/0.15)x2x4
1B1 ∅ 10 - 15 5.40 5.40 22 11 1.20 11 11 - - - 0.62 73.21 81.34
a b 1B2 ∅ 10 - 15 5.40 5.40 22 11 1.2 11.0 11 - - - 0.62 73.21 81.34
2 Lantai Atas
A Melintang
1. Tulangan Pokok (10/0.2)x6
b 2A1 ∅ 12 - 20 0.05 3.25 0.15 3.25 0.15 0.05 6.90 300 300 5.10 300 2B1 - 300 - - 0.89 1,836.84 3,194.51
f
e a c
d
B Memanjang
1. Tulangan Pembagi
(3.3/0.15)x2x6
2B1 ∅ 10 - 15 5.40 5.40 264 - 1.20 - - - - - 0.62 878.49 -
a b 2B2 ∅ 10 - 15 5.40 5.40 264 132 1.2 132.0 132 - - - 0.62 878.49 976.10
3 Pier Head
A Melintang b
1. Tulangan Pokok
a c (12/0.2)x2
3A1 ∅ 12 - 20 0.16 0.32 0.16 0.45 1.09 120 11 0.01 11 2B1 - 11 - - 0.89 116.07 117.13
d
B Memanjang
1. Tulangan Pembagi
4x2
3B1 ∅ 10 - 15 7.40 7.40 8 8 4.60 8 8 - - - 0.62 36.48 59.16
a b 3B2 ∅ 10 - 15 7.40 7.40 8 8 4.6 8.0 8 - - - 0.62 36.48 59.16
Jumlah 2,350.15
Volume Rencana 2,400.00
Volume Sisa 49.85
B Rencana Sisa A p n V
1 Sta 23+800 ka 1.78 46.60 1.00 82.95
2 Sta 23+800
82.95 (33.10)
C HITUNGAN
Lebar
No STA SISI t A P V 595.31
Atas Bawah
1 18+045 61.81
Kiri 1 A1 0.35 0.85 1.00 0.60
A2 0.35 1.10 1.50 1.09
0.84 18.90 15.95
Kiri 2 A1 0.35 1.09 1.48 1.07
A2 0.35 0.80 0.89 0.51
0.79 17.40 13.72
Kanan 1 A1 0.35 0.79 0.88 0.50
A2 0.35 1.22 1.73 1.36
0.93 16.50 15.34
kanan 2 A1 0.35 1.32 1.94 1.62
A2 0.35 0.70 0.69 0.36
0.99 16.95 16.80
2 18+610 61.81
Kiri 1 A1 0.35 0.85 1.00 0.60
A2 0.35 1.10 1.50 1.09
0.84 18.90 15.95
Kiri 2 A1 0.35 1.09 1.48 1.07
A2 0.35 0.80 0.89 0.51
0.79 17.40 13.72
Kanan 1 A1 0.35 0.79 0.88 0.50
A2 0.35 1.22 1.73 1.36
0.93 16.50 15.34
kanan 2 A1 0.35 1.32 1.94 1.62
A2 0.35 0.70 0.69 0.36
0.99 16.95 16.80
1 STA 12+400
KI 1 A1 0.35 0.68 1.35 0.69
A2 0.35 0.55 1.10 0.50
0.59 13.00 7.71
KI 2 A1 0.35 - -
A2 0.35 - -
- -
KA 1 A1 0.35 0.45 0.90 0.36
A2 0.35 0.65 1.30 0.65
0.51 10.70 5.40
KA 2 A1 0.35 0.44 0.88 0.35
Page 15
A2 0.35 0.60 1.20 0.57
0.46 15.10 6.93
38.80 20.05
2 STA 13+176
KI 1 A1 0.35 0.40 0.80 0.30
A2 0.35 0.80 1.60 0.92
0.61 25.60 15.62
KI 2 A1 0.35 0.38 0.75 0.27
A2 0.35 0.65 1.30 0.65
0.46 23.60 10.88
KA 1 A1 0.35 0.35 0.70 0.25
A2 0.35 0.70 1.40 0.74
0.49 24.60 12.05
KA 2 A1 0.35 0.48 0.95 0.39
A2 0.35 0.75 1.50 0.83
0.61 24.00 14.60
97.80 53.15
3 STA 19+100
KI 1 A1 0.35 0.75 1.50 0.83
A2 0.35 0.90 1.80 1.13
0.98 13.30 12.97
AΔ 1.00 0.34 0.17 0.35 0.06
KI 2 A1 0.35 0.57 1.13 0.52
A2 0.35 1.05 2.10 1.47
0.99 22.24 22.10
AΔ 1.00 0.50 0.25 0.35 0.09
KA 1 A1 0.35 0.60 1.20 0.57
A2 0.35 1.40 2.80 2.45
1.51 26.50 40.02
AΔ 1.50 0.55 0.41 0.35 0.14
KA 2 A1 0.35 0.60 1.20 0.57
A2 0.35 1.20 2.40 1.86
1.22 18.50 22.48
AΔ 1.10 0.50 0.28 0.35 0.10
81.94 97.94
4 STA 21+200
KI 1 A1 0.35 0.75 1.50 0.83
A2 0.35 0.90 1.80 1.13
A3 0.35 0.90 1.80 1.13
1.03 20.00 20.50
20.00 20.50
5 STA 21+900
KA 1 A1 0.35 0.55 1.10 0.50
A2 0.35 0.75 1.50 0.83
A3 0.35 0.70 1.40 0.74
0.69 28.60 19.59
28.60 19.59
6 STA 22+700
KI 1 A1 0.35 0.60 1.20 0.57
A2 0.35 0.70 1.40 0.74
A3 0.35 0.60 1.20 0.57
0.63 26.70 16.69
KA 1 A1 0.35 0.55 1.10 0.50
A2 0.35 0.75 1.50 0.83
A3 0.35 0.50 1.00 0.43
0.58 37.00 21.52
63.70 38.21
Tanggal 27-08-2018
7 STA 19+275
KI 1 A1 0.35 0.95 1.90 1.24
A2 0.35 0.72 1.43 0.76
1.00 8.67 8.65
KA 1 A1 0.35 0.67 1.33 0.67
A2 0.35 0.64 1.28 0.63
0.65 4.44 2.91
13.11 11.56
8 STA 19+875
KI 1 A1 0.35 0.90 1.80 1.13
A2 0.35 1.05 2.10 1.47
1.30 4.55 5.90
KI kerb 0.35 1.66 0.58 2.38 1.38
KI 2 A1 0.35 0.78 1.55 0.87
A2 0.35 1.10 2.20 1.60
1.23 28.80 35.52
KA 1 A1 0.35 0.55 1.10 0.50
A2 0.35 0.72 1.43 0.76
0.63 4.10 2.58
KA kerb 0.35 0.97 0.34 2.45 0.83
KA 2 A1 0.35 0.45 0.90 0.36
A2 0.35 0.65 1.30 0.65
0.51 4.80 2.42
47.08 48.64
9 STA 23+650
KA 2 sambungan A1 0.35 0.50 1.00 0.43
A2 0.35 0.65 1.30 0.65
0.54 20.00 10.75
20.00 10.75
10 STA 13+625
KI 1 A1 0.35 0.48 0.95 0.39
A2 0.35 1.00 2.00 1.35
0.87 44.35 38.68
KI 2 A1 0.35 0.50 1.00 0.43
A2 0.35 0.93 1.85 1.18
0.80 34.30 27.59
KA 1 A1 0.35 0.55 1.10 0.50
A2 0.35 0.80 1.60 0.92
0.71 46.30 32.76
124.95 99.03
Tanggal 08-09-2018 (Pak Nur)
11 STA 12+500
KI 2 A1 0.35 0.40 0.80 0.30
A2 0.35 0.63 1.25 0.61
0.46 17.80 8.12
17.80 8.12
12 STA 19+275
KI 2 A1 0.35 - - -
A2 0.35 0.95 1.90 1.24
0.62 11.67 7.21
KA 2 A1 0.35 0.64 1.27 0.63
A2 0.35 0.70 1.40 0.74
0.68 4.40 3.00
Page 16
AΔ1 0.35 - - -
AΔ2 0.35 0.20 0.40 0.11
0.06 3.30 0.18
19.37 10.39
13 STA 19+400
KI A1 0.35 0.80 1.60 0.92
A2 0.35 0.85 1.70 1.02
A3 0.35 0.75 1.50 0.83
0.92 24.65 22.72
24.65 22.72
14 STA 19+650
KA 1 A1 0.35 0.60 1.20 0.57
A2 0.35 1.10 2.20 1.60
A3 0.35 0.70 1.40 0.74
0.97 14.80 14.31
14.80 14.31
15 STA 29+050
KA 1 A1 0.35 0.55 1.10 0.50
A2 0.35 0.97 1.94 1.28
0.89 19.80 17.58
KA 2 A1 0.35 0.15 0.30 0.08
A2 0.35 0.35 0.70 0.25
0.16 7.30
Page 17
27.10 17.58
16 STA 13+625
KA 2 A1 0.35 0.34 0.68 0.23
A2 0.35 0.48 0.95 0.39
A3 0.35 0.80 1.60 0.92
0.52 35.90 18.53
35.90 18.53
1 STA
KI 1 A1 0.35 - -
A2 0.35 - -
A3 0.35 - -
- -
KI 2 A1 0.35 - -
A2 0.35 - -
A3 0.35 - -
- -
KA 1 A1 0.35 - -
A2 0.35 - -
A3 0.35 - -
- -
KA 2 A1 0.35 - -
A2 0.35 - -
A3 0.35 - -
- -
Page 18
43 27+100
KI 1 A1 0.35 1.00 1.90 1.28
A2 0.35 1.00 1.90 1.28
1.28 2.10 2.69
KI 2 A1 0.35 1.00 1.50 1.01
A2 0.35 1.00 1.50 1.01
1.01 3.15 3.19
5.88
44 31+400
KI 1 A1 0.35 0.61 0.88 0.42
A2 0.35 0.74 1.12 0.61
0.52 16.14 8.33
KI 2 A1 0.35 0.73 1.15 0.62
A2 0.35 0.68 1.00 0.52
0.57 16.20 9.20
KA 1 A1 0.35 0.60 0.60 0.29
A2 0.35 0.65 0.90 0.45
0.37 9.96 3.66
KA 2 A1 0.35 0.68 1.06 0.55
A2 0.35 0.56 0.65 0.30
0.42 14.78 6.22
27.42
45 31+700
KI 1 A1 0.35 0.59 0.89 0.42
A2 0.35 0.70 1.07 0.56
0.49 22.70 11.12
KI 2 A1 0.35 0.73 1.11 0.60
A2 0.35 0.71 1.10 0.58
0.59 22.70 13.42
KA 1 A1 0.35 0.61 0.75 0.36
A2 0.35 0.82 1.50 0.88
0.62 23.10 14.29
KA 2 A1 0.35 0.82 1.35 0.79
A2 0.35 0.70 0.90 0.47
0.63 19.18 12.10
50.94
Page 19
A SALURAN MORTAR
Jumlah -
Volume Rencana 1,135.00
Volume Sisa 1,135.00 1,518.39 m
1,509.39
A BRONJONG
Panjang Volume
No STA Sisi Tingkat Unit Tanggal Opname Keterangan
m m3
Jumlah -
Volume Rencana 370.00
Volume Sisa 370.00
Catatan
1 QUARRY 18 9.00 m3
A PATOK PENGARAH
Catatan REKAP
* Kap.prod. 12 btg/hari/org Rencana 880.00 buah
* Hilang 1 18+000 Pengadaan 884.00 buah
3 20+537 (4.00) buah
Sisa
4.00 buah (Hilang)
824.00
B KEBUTUHAN CAT
1 Kg Cat Putih 14.00 bh 4.52 m2
1 Kg Cat Hitam 24.00 bh 4.32 m2
Putih 0.32 m2
Luas
Hitam 0.18 m2
1 -10+450 ka TKL 96 PLK 130 TBT 11 1.00 1.00 10/15/2019 V TKL = TENGKILING
2 -09+450 ka TKL 97 PLK 131 TBT 10 1.00 1.00 10/15/2019 V
3 -08+450 ka TKL 98 PLK 132 TBT 9 1.00 1.00 10/15/2019 V TBT = TUMBANG TELAKEN
4 -07+450 ka TKL 99 PLK 133 TBT 8 1.00 1.00 10/15/2019 V
5 -06+450 ka TKL 100 PLK 134 TBT 7 1.00 1.00 10/15/2019 V TBJ = TUMBANG JUTUH
6 -05+450 ka TKL 101 PLK 135 TBT 6 1.00 1.00 10/15/2019 V
7 -04+450 ka TKL 102 PLK 136 TBT 5 1.00 1.00 10/15/2019 V PLK = PALANGKA RAYA
8 -03+450 ka TKL 103 PLK 137 TBT 4 1.00 1.00 10/15/2019 V
9 -02+450 ka TKL 104 PLK 138 TBT 3 1.00 1.00 10/15/2019 V
10 -01+450 ka TKL 105 PLK 139 TBT 2 1.00 1.00 10/15/2019 V
11 -00+450 ka TKL 106 PLK 140 TBT 1 1.00 1.00 10/15/2019 V digeser 7 m
12 00+550 ka TBT 1 PLK 141 TBJ 36 1.00 1.00 10/15/2019 V digeser
13 01+550 ka TBT 2 PLK 142 TBJ 35 1.00 1.00 10/15/2019 V
14 02+550 ka TBT 3 PLK 143 TBJ 34 1.00 1.00 10/15/2019 V
15 03+550 ka TBT 4 PLK 144 TBJ 33 1.00 1.00 10/15/2019 V
16 04+550 ka TBT 5 PLK 145 TBJ 32 1.00 1.00 10/15/2019 V
17 05+550 ka TBT 6 PLK 146 TBJ 31 1.00 1.00 10/15/2019 V
18 06+550 ka TBT 7 PLK 147 TBJ 30 1.00 1.00 10/15/2019 V
19 07+550 ka TBT 8 PLK 148 TBJ 29 1.00 1.00 10/15/2019 V
20 08+550 ka TBT 9 PLK 149 TBJ 28 1.00 1.00 10/15/2019 V
21 09+550 ka TBT 10 PLK 150 TBJ 27 1.00 1.00 10/15/2019 V
22 10+550 ka TBT 11 PLK 151 TBJ 26 1.00 1.00 10/15/2019 V
23 11+550 ka TBT 12 PLK 152 TBJ 25 1.00 1.00 10/15/2019 V digeser
24 12+550 ka TBT 13 PLK 153 TBJ 24 1.00 1.00 10/15/2019 V
25 13+550 ka TBT 14 PLK 154 TBJ 23 1.00 1.00 10/15/2019 V
26 14+550 ka TBT 15 PLK 155 TBJ 22 1.00 1.00 10/15/2019 V
27 15+550 ka TBT 16 PLK 156 TBJ 21 1.00 1.00 10/15/2019 V
28 16+550 ka TBT 17 PLK 157 TBJ 20 1.00 1.00 10/15/2019 V digeser
29 17+550 ka TBT 18 PLK 158 TBJ 19 1.00 1.00 10/15/2019 V digeser
30 18+550 ka TBT 19 PLK 159 TBJ 18 1.00 1.00 10/15/2019 V
31 19+550 ka TBT 20 PLK 160 TBJ 17 1.00 1.00 10/15/2019 V
32 20+550 ka TBT 21 PLK 161 TBJ 16 1.00 1.00 10/31/2019 V
33 21+550 ka TBT 22 PLK 162 TBJ 15 1.00 1.00 10/31/2019 V
34 22+550 ka TBT 23 PLK 163 TBJ 14 1.00 1.00 10/31/2019 V
35 23+550 ka TBT 24 PLK 164 TBJ 13 1.00 1.00 10/31/2019 V
36 24+550 ka TBT 25 PLK 165 TBJ 12 1.00 1.00 10/31/2019 V
37 25+550 ka TBT 26 PLK 166 TBJ 11 1.00 1.00 10/31/2019 V
38 26+550 ka TBT 27 PLK 167 TBJ 10 1.00 1.00 11/15/2019 V
39 27+550 ka TBT 28 PLK 168 TBJ 9 1.00 1.00 10/31/2019 V
40 28+550 ka TBT 29 PLK 169 TBJ 8 1.00 1.00 10/31/2019 V
41 29+550 ka TBT 30 PLK 170 TBJ 7 1.00 1.00 10/31/2019 V
42 30+550 ka TBT 31 PLK 171 TBJ 6 1.00 1.00 10/31/2019 V
43 31+550 ka TBT 32 PLK 172 TBJ 5 1.00 1.00 10/31/2019 V
44 32+550 ka TBT 33 PLK 173 TBJ 4 1.00 1.00 10/31/2019 V
45 33+550 ka TBT 34 PLK 174 TBJ 3 1.00 1.00 11/15/2019 V
46 34+550 ka TBT 35 PLK 175 TBJ 2 1.00 1.00 11/15/2019 V
47 35+550 ka TBT 36 PLK 176 TBJ 1 1.00 1.00 11/15/2019 V
Total 47.00 - 47.00
Sisa -
Catatan REKAP
* Stok di gudang 5 bh Rencana 47.00 buah
* Patah 1 bh Pengadaan 48.00 buah
(1.00) buah
Sisa
1.00 buah (patah)
B KEBUTUHAN CAT
1 Kg Cat Kuning 2.00 bh 4.02 m2
1 Kg Cat Putih 26.00 bh 4.38 m2
Kuning 2.01 m2
Luas
Putih 0.17 m2
Kuning 23.50 kg
Kebut.
Putih 1.81 kg
SCHEDULE SISA PEKERJAAN STRUKTUR
No Uraian Pekerjaan Sisi Satuan Volume Desember Januari Februari Maret April Mei Juni Juli Agustus Keterangan
23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31
DPT
1 DPT STA 31+675 (BC) KI + KA
2 DPT STA 31+400 (BC) KI + KA
Timbunan Oprit
Galian
Pemasangan Batu
3 Makam Rabambang KI 50
Galian
Pemasangan Batu
4 Bank BRI
Galian
Pemasangan Batu
5 DPT STA -09+825 (BC) KI + KA
Galian
Pemasangan Batu
BRONJONG
1 Bronjong STA 12+750 - 12+775 KI+Ka
Galian
Pemasangan Batu
2 Bronjong STA 27 KI
Galian
Pemasangan Batu
SALURAN
6 Saluran STA 21+811 - 21+913
Galian
Pemasangan Batu
7 Saluran STA 22+225 - 22+275
Galian
Pemasangan Batu
8 Saluran STA 23+282 - 23+421
Galian
Pemasangan Batu
9 Saluran STA 23+703 - 23+948
Galian
Pemasangan Batu
Gunung Mas,
Dari Ke POSISI
N0 - PANJANG KETERANGAN
STA STA KIRI KANAN
1 00+975 - 01+025 50 √
2 01+175 - 01+225 50 √
3 02+625 - 02+725 100 √
4 05+275 - 05+325 50 √
5 16+200 - 16+300 100 √
6 21+675 - 21+725 50 √
7 21+875 - 21+925 50 √
8 23+800 - 23+850 50 √
TOTAL 500
Sudut Quantity
No Posisi STA Pjg (m) (Decimal Ket
Degree) W-Beam Section Steel Block Steel Post End Block Hexagonal Bolt Fastener Splice Bolt (1) Splice Bolt (2)
40.075 10 21 21 2 42 21 88 21 44
2 03+085 03+135 116.440
14.075 4 9 9 2 18 9 40 9
62.075 16 33 33 2 66 33 136 33 72
6.075 2 5 5 2 10 5 24 5
4.075 1 3 3 2 6 3 16 3 44
38.075 10 21 21 2 42 21 88 21
24.075 6 13 13 2 26 13 56 13 48
10.075 3 7 7 2 14 7 32 7
42.037 11 23 23 2 46 23 96 23 84
8 28+842 28+920 134.24
34.075 9 19 19 2 38 19 80 19
534.387 552 138 292 292 32 584 292 1232 292 Real Lapangn
500 125 251 251 ~ 502 251 1008 251 Sesuai Addendum 03 (500m)
A GUARDRAIL
Panjang Quantity
Tanggal Tanggal
No Posisi STA CAT
Rencana (m) Realisasi (m) W-Beam Section Steel Block Steel Post End Block Hexagonal Bolt Splice Bolt (1) Splice Bolt (2) Fastener Opname Opname