I PEKERJAAN LANTAI
1 Urugan Pasir t = 30 cm PT.08 M3 93.68 237,080.00 22,208,943.16
2 Lantai Kerja Beton Camp. 1:3:5 , t = 5cm P.PBB.01 M3 12.20 1,034,350.00 12,619,070.00
- Pembesian Ø 8 mm P.BB.03 Kg 171.77 25,839.00 4,438,238.94
3 Pekerjaan Keramik Lantai Uk. 40x40 Polos P.LD.09 M2 200.00 236,242.20 47,248,440.00
86,514,692.10
II PEKERJAAN PEMASANGAN BATAKO
1 Pekerjaan Pemasangan Batako P.Dnd.01 M2 360.03 131,749.00 47,433,987.72
47,433,987.72
III PEKERJAAN PLESTERAN DINDING
1 Pekerjaan Plaster t=1,5cm P.Pls.11 M2 720.07 62,753.80 45,186,877.75
45,186,877.75
IV PEKERJAAN TOILET
1 Balok Sloof 20x35cm
- Cor Beton Camp. 1 : 2 : 3 P.BB.02 M3 0.68 1,512,990.00 1,022,781.24
- Pembesian Ø 12 mm P.BB.03 Kg 48.22 25,839.00 1,246,037.28
- Pembesian Beugel Ø 8-15cm P.BB.03 Kg 33.80 25,839.00 873,361.14
- Bekesting P.BB.05 M2 9.46 166,407.50 1,574,880.58
2 Kolom 15x15 cm
- Cor Beton Camp. 1 : 2 : 3 P.BB.02 M3 0.60 1,512,990.00 907,794.00
- Pembesian Ø 12 mm P.BB.03 Kg 122.16 25,839.00 3,156,383.10
- Pembesian Beugel Ø 8-15cm P.BB.09 Kg 64.13 25,839.00 1,657,058.65
- Bekesting P.BB.06 M2 14.40 248,687.50 3,581,100.00
- Plesteran P.Pls.11 M2 9.60 62,753.80 602,436.48
3 Ring Balok 20x15cm
- Cor Beton Camp. 1 : 2 : 3 P.BB.02 M3 0.20 1,512,990.00 306,834.37
- Pembesian Ø 12 mm P.BB.03 Kg 49.93 25,839.00 1,290,079.84
- Pembesian Beugel Ø 8-15cm P.BB.09 Kg 20.10 25,839.00 519,335.13
- Bekesting P.BB.10 M2 4.73 15,997.40 75,699.70
- Plesteran P.Pls.11 M2 4.73 62,753.80 296,950.98
4 Atap Dak Beton, t= 10cm
- Cor Beton Camp. 1 : 2 : 3 P.BB.02 M3 1.06 1,512,990.00 1,600,743.42
- Pembesian Ø 8 mm (Double) P.BB.03 Kg 37.88 25,839.00 978,723.44
- Bekesting P.BB.09 M2 4.83 37,565.60 181,441.85
5 Keramik Lantai 20x20cm P.LD.07 M2 8.00 225,267.20 1,802,137.60
6 Pemasangan Floordrain P.Snt.16 Unit 3.00 74,502.50 223,507.50
7 Pemasangan kran Ø 3/4 atau 1/2 P.Snt.15 Unit 4.00 31,127.50 124,510.00
8 Instalasi Air Kotor, Pipa Ø4 P.Snt.14 M1 11.50 83,064.00 955,236.00
9 Pemasangan Kloset Jongkok P.Snt.02 Unit 3.00 195,000.00 585,000.00
10 Pemasangan Wastafel P.Snt.03 Unit 1.00 849,110.00 849,110.00
24,411,142.29
V PEKERJAAN SELASAR

1 Balok Sloof 20x35cm


- Cor Beton Camp. 1 : 2 : 3 P.BB.02 M3 5.23 1,512,990.00 7,915,963.68
- Pembesian Ø 12 mm P.BB.03 Kg 372.01 25,839.00 9,612,287.59
- Pembesian Beugel Ø 8-15cm P.BB.03 Kg 259.47 25,839.00 6,704,500.25
- Bekesting P.BB.05 M2 73.25 166,407.50 12,189,016.56
2 Kolom 15x15 cm
- Cor Beton Camp. 1 : 2 : 3 P.BB.02 M3 1.26 1,512,990.00 1,906,367.40
- Pembesian Ø 12 mm P.BB.03 Kg 427.55 25,839.00 11,047,340.84
- Pembesian Beugel Ø 8-15cm P.BB.09 Kg 67.24 25,839.00 1,737,505.97
- Bekesting P.BB.06 M2 33.60 248,687.50 8,355,900.00
- Plesteran P.Pls.11 M2 33.60 62,753.80 2,108,527.68
3 Ring Balok 20x15cm
- Cor Beton Camp. 1 : 2 : 3 P.BB.02 M3 0.81 1,512,990.00 1,225,521.90
- Pembesian Ø 12 mm P.BB.03 Kg 49.93 25,839.00 1,290,079.84
- Pembesian Beugel Ø 8-15cm P.BB.09 Kg 20.10 25,839.00 519,335.13
- Bekesting P.BB.10 M2 18.90 15,997.40 302,350.86
- Plesteran P.Pls.11 M2 18.90 62,753.80 1,186,046.82
4 Atap Dak Beton, t= 10cm
- Cor Beton Camp. 1 : 2 : 3 P.BB.02 M3 5.20 1,512,990.00 7,867,548.00
- Pembesian Ø 8 mm (Double) P.BB.03 Kg 113.63 25,839.00 2,936,170.32
- Bekesting P.BB.09 M2 25.26 37,565.60 948,907.06
5 Keramik Lantai 30x30cm P.LD.08 M2 40.00 228,967.20 9,158,688.00
87,012,057.89
VI PEKERJAAN TERAS DEPAN

1 Balok Sloof 20x35cm


- Cor Beton Camp. 1 : 2 : 3 P.BB.02 M3 0.60 1,512,990.00 907,794.00
- Pembesian Ø 12 mm P.BB.03 Kg 42.83 25,839.00 1,106,569.19
- Pembesian Beugel Ø 8-15cm P.PKK.04 Kg 30.04 25,839.00 776,250.03
- Bekesting P.BB.05 M2 8.40 166,407.50 1,397,823.00
2 Kolom 20x20 cm
- Cor Beton Camp. 1 : 2 : 3 P.BB.02 M3 0.32 1,512,990.00 484,156.80
- Pembesian Ø 12 mm P.BB.03 Kg 61.08 25,839.00 1,578,191.55
- Pembesian Beugel Ø 8-15cm P.PKK.09 Kg 13.97 25,839.00 361,040.20
- Bekesting P.Snt.02 M2 6.40 529,610.00 3,389,504.00
- Plesteran P.Pls.11 M2 6.40 62,753.80 401,624.32
- Finishing Kolom - Ls 1.00 2,000,000.00 2,000,000.00
3 Ring Balok 20x15cm
- Cor Beton Camp. 1 : 2 : 3 P.BB.02 M3 0.18 1,512,990.00 272,338.20
- Pembesian Ø 12 mm P.BB.03 Kg 42.83 25,839.00 1,106,569.19
- Pembesian Beugel Ø 8-15cm P.PKK.09 Kg 17.26 25,839.00 445,930.87
- Bekesting P.BB.10 M2 4.20 15,997.40 67,189.08
- Plesteran P.Pls.11 M2 4.20 62,753.80 263,565.96
4 Atap Dak Beton, t= 10cm
- Cor Beton Camp. 1 : 2 : 3 P.BB.02 M3 0.36 1,512,990.00 544,676.40
- Pembesian Ø 8 mm (Double) P.BB.03 Kg 66.29 25,839.00 1,712,766.02
- Bekesting P.BB.09 M2 11.46 37,565.60 430,501.78
5 Pekerjaan Atap
Kuda-kuda Blk Nok + Gapit + Skoor PK.25 M3 0.36 4,565,410.00 1,643,985.88
Gording + Ikatan Angin Kayu Kls II PK.27 M3 0.37 5,578,650.00 2,040,112.31
Atap Seng Metal P.PA.16 M2 17.51 99,382.50 1,740,455.91
Perabung Papan Lapis Seng Plat BJLS 0.30 P.PA.13 M1 7.67 56,165.60 430,790.15
List Plank Papan Kayu Kls I PK.37 M1 11.32 80,360.00 909,675.20
6 Keramik Lantai 30x30cm P.LD.08 M2 16.00 228,967.20 3,663,475.20
27,674,985.23
VII PEKERJAAN KUSEN PINTU
1 Pintu Panel Kayu Klas I PK.15 M2 15.69 694,240.00 10,894,014.08
2 Jendela Kaca Jungkit Kayu Klas I PK.15 M2 24.96 694,240.00 17,328,230.40
3 Ventilasi Ram Kayu Klas II PK.22 M2 35.32 210,241.50 7,424,678.57
4 Kunci 2 Slaag P.PKK.02 Unit 4.00 264,250.00 1,057,000.00
5 Kait Angin P.PKK.06 Unit 12.00 10,574.00 126,888.00
6 Handle Jendela P.PKK.09 Unit 12.00 19,587.50 235,050.00
7 Kunci Sloot Pintu P.PKK.07 Unit 8.00 19,587.50 156,700.00
8 Kunci Sloot Jendela P.PKK.08 Unit 24.00 15,587.50 374,100.00
9 Engsel Pintu 4" P.PKK.04 Unit 12.00 47,662.50 571,950.00
10 Engsel Jendela 3" P.PKK.05 Unit 36.00 42,662.50 1,535,850.00
39,704,461.05
VIII PEKERJAAN PLAFOND
1 Plafond GRC + Rangka Kayu Kls II P.Pf.01 M2 264.00 169,680.50 44,795,652.00
44,795,652.00
IX PEKERJAAN PENGECATAN
1 Cat Tembok P.Ct.11 M2 769.67 22,003.00 16,934,961.00
2 Cat Kilat P.Ct.04 M2 126.06 42,293.00 5,331,337.16
22,266,298.16
REKAPITULASI
RENCANA ANGGARAN BIAYA

Program :-
Kegiatan :-
Pekerjaan :-
Lokasi :-
Tahun Anggaran : 2017

URAIAN JUMLAH HARGA


NO.
JENIS PEKERJAAN (Rp.)
1 2 3

I. PEKERJAAN LANTAI 86,514,692.10


II. PEKERJAAN PEMASANGAN BATAKO 47,433,987.72
III. PEKERJAAN PLESTERAN DINDING 45,186,877.75
IV. PEKERJAAN TOILET 24,411,142.29
V. PEKERJAAN SELASAR 87,012,057.89
VI. PEKERJAAN TERAS DEPAN 27,674,985.23
VII. PEKERJAAN KUSEN PINTU 39,704,461.05
VIII. PEKERJAAN PLAFOND 44,795,652.00
IX. PEKERJAAN PENGECATAN 22,266,298.16

A. JUMLAH 425,000,154.18
B. DIBULATKAN 425,000,000.00

Terbilang :-

aaaaaa, ………………….2017
DIBUAT OLEH :
KEPALA SEKOLAH
SDN NO.02 BENUA MARTINUS

ELIAS, S.Pd.SD
NIP.197304111996061001
WILAYAH PUTUSSIBAU DAN SEKITARNYA
(Meliputi: Kec. Putussibau Utara, Putussibau Selatan, Kalis, Bika, Mentebah, Boyan Tanjung, Bunut
Hulu, Pengkadan, Hulu Gurung, Embaloh Hulu, dll)

PROPENSI : KALIMANTAN BARAT


KOTA / KABUPATEN : KAPUAS HULU

UPAH UPAH
NO URAIAN TENAGA KERJA KODE
(Rp / Hari) (Rp / Jam) KETERANGAN

A B C D E F
1 Mandor Lapangan L.061 150,000.00 21,428.57
2 Mekanik L.071 150,000.00 21,428.57
3 Mekanik Pembantu L.072 125,000.00 17,857.14
4 Kepala Tukang L.073 150,000.00 21,428.57
5 Tukang L.079 125,000.00 17,857.14
6 Operator ** L.081 150,000.00 21,428.57
7 Pembantu Operator *** L.089 105,000.00 15,000.00
8 Supir Truck Material L.091 125,000.00 17,857.14
9 Pembantu Supir L.099 100,000.00 14,285.71
10 Buruh Lapangan Tidak Terlatih/Pekerja L.101 100,000.00 14,285.71

CATATAN :
*) Tenaga Kerja Dihitung 7 (Tujuh) Jam Kerja / Hari
n*) Operator yang sudah biasa dan terampil mengoperasikan jenis peralatan untuk melayani pekerjaan berat.
Misal : Buldozer, Grader, Whell Loader, Asphalt Finisher, dll.
n') Operator yang mengoperasikan peralatan untuk melayani pekerjaan berat yang agak ringan.
Misal : Steel Wheeled Roller, Stamper, Mechanical Rammer, Concrete Mixer / Mesin Pengaduk.

HARGA SATUAN
NO URAIAN BAHAN / MATERIAL KODE SATUAN KETERANGAN
(Rp)

A B C D E F
BAHAN PENGISI
1 Batu Gunung Quary M_010 m3 340,000.00
2 Batu Gunung Quary M_010.a m3 232,000.00
3 Batu Gunung Quary M_010.b m3 194,000.00
4 Kerikil dari galian bukit M_011 m3 280,000.00
5 Kerikil Sungai ( Leveransir ) M_012 m3 197,000.00
6 Kerikil Sungai ( Royality ) M_013 m3 80,000.00
7 Batu kali M_014 m3 222,000.00
8 Kerikil sungai ayak tanpa pasir (1-2 cm) M_015 m3 207,000.00
9 Kerikil sungai ayak tanpa pasir (2-3 cm) M_015.a m3 192,000.00
10 Batu pecah gunung (10 - 15 cm) M_021 m3 450,000.00
11 Batu pecah gunung (7 - 10 cm) M_022 m3 575,000.00
12 Batu pecah gunung (5 - 7 cm.) M_023 m3 675,000.00
13 Batu pecah gunung (3 - 5 cm.) M_024 m3 725,000.00
14 Batu pecah gunung (2 - 3 cm.) M_025 m3 775,000.00
15 Batu pecah gunung (1 - 2 cm.) M_026 m3 825,000.00
16 Batu pecah gunung (0,5 - 1 cm.) M_027 m3 975,000.00
17 Batu pecah sungai (3 - 5 cm.) M_028 m3 625,000.00
18 Batu pecah sungai (2 - 3 cm.) M_029 m3 675,000.00
19 Batu pecah sungai (1 - 2 cm.) M_030 m3 725,000.00
20 Batu pecah sungai (0,5 - 1 cm.) M_031 m3 825,000.00
21 Pasir urug / timbun M_040 m3 172,000.00
22 Pasir ayak untuk beton M_041 m3 187,000.00
23 Sirtu Sungai ( Leveransir ) M_042 m3 187,000.00
24 Sirtu Sungai ( Royality ) M_043 m3 80,000.00
25 Bahan timbunan pilihan (laterit) Leveransir M_050 m3 137,000.00
26 Bahan timbunan pilihan (laterit) Setempat M_051 m3 40,000.00
27 Timbunan setempat ( tanah biasa) M_052 m3 10,000.00
28 Aspal Bitument M_061 Kg. 10,800.00
29 Semen Portlant ( PC ) M_080 50 Kg. 127,000.00
30 Semen Portlant ( PC ) M_080.a Kg 2,540.00
31 Semen Warna (Oker) M_080.b Kg 15,040.00
32 Paving blok M_082 BH 3,200.00
33 Bataco Ukuran 15 x 30 x 7 cm M_239 Buah 2,700.00
34 Bataco Ukuran 20 x 40 x 7 cm M_239.a Buah 3,200.00
35 Bataco Ukuran 20 x 40 x 9 cm M_239.b Buah 3,450.00
36 Alat - alat bantu * M_171 Set 125,000.00
37 Alat - alat bantu ** M_172 Set 205,000.00
38 Alat - alat bantu pek. Latasir *** M_173 Set 235,000.00
39 Gerobak + kuali aspal M_174 Set 6,250,000.00
BAHAN MINYAK
40 Minyak Tanah M_065 Ltr. 7,600.00
41 Minyak Diesel M_183 Ltr. 13,700.00
42 Premium / Bensin M_184 Ltr. 11,600.00
43 Minyak Pelumas M_185 Ltr. 30,600.00
44 Minyak Thinner M - 203 Ltr 20,500.00
45 Minyak Bekesting / Cetakan M - 203.a Ltr 7,300.00
HARGA SATUAN
NO URAIAN BAHAN / MATERIAL KODE SATUAN KETERANGAN
(Rp)

A B C D E F
BAHAN CAT
46 Cat Jembatan M_090 Kg 120,500.00
47 Cat Dasar M_187 Kg. 45,600.00
48 Alkali - Kg 54,300.00
49 Teer M_188 Kg. 10,600.00
50 Cat Kilap M_193 Kg. 55,600.00
51 Cat Galvanis M - 202 Kg 51,000.00
52 Dempul M_230 Kg 35,100.00
53 Plamur M_231 Kg 35,100.00
54 Amplas M_232 Lbr 3,100.00
55 Cat Tembok Kualitas Biasa M_233 Kg 10,100.00
56 Cat Tembok Kualitas Sedang M_233.a Kg 17,325.00
57 Cat Tembok Weather Shield M_233.b Kg 110,100.00
58 Cat Vernis M_233.a Liter 50,100.00
59 Cat Melamic M_233.b Kg 60,100.00
60 Cat Meni Besi M_233.c Kg 27,100.00
61 Cat Meni Atap M_233.d Kg 30,100.00
62 Cat Tembok Interior M_233.e Kg 100,100.00
63 Cat Tembok Eksterior (Anti Jamur) M_233.f Kg 110,100.00
64 Cat Water Proofing M_233.g Kg 55,100.00
65 Soda Api M_234 Kg 41,100.00
66 Sabun M_235 Kg 5,100.00
67 Kuas Cat M_236 Buah 20,100.00
BAHAN BESI & BAJA
68 Baja Tralis M_161 Kg. 20,600.00
69 Kawat Bronjong Galvanis uk. 2.0 x 1.0 x 0.5 dia. 3 mm M_162 Unit 646,000.00
70 Kawat Bronjong Galvanis M_162. a Kg. 35,600.00
71 Kawat Bronjong Galvanis Lapis PVC M_162. b Kg. 70,600.00
72 Kawat las M_162 c Kg. 33,000.00
73 Kawat Las Listrik M_162 d Kg 32,000.00
74 Paku Jembatan M_166 Kg. 30,600.00
75 Baut Baja M_163 Kg. 36,000.00
76 Besi Galvanis sandaran jembatan M_164 btg 626,000.00
77 Baja Konstruksi (rangka baja Jembatan) M_165 Kg. 36,000.00
78 Baja Beton U.24 Tulangan Polos dan Ulir M_167 Kg. 22,600.00
79 Baja Beton U.32 Tulangan Polos dan Ulir M_167. a Kg. 23,600.00
80 Wire Mash M5 M_167. b Kg. 28,900.00
81 Wire Mash M6 M_167. c Kg. 37,700.00
82 Kawat Bindrat / Kawat Ikat M_170 Kg. 25,600.00
83 Beugel tebal plat 5 mm M_186 Bh. 25,600.00
84 Baut Panjang (15 - 30 cm) M_189 Btg. 8,100.00
85 Paku Baut 15 cm M. 189.A Btg. 5,600.00
86 Baut Pendek (4 - 12 cm) M_190 Btg. 2,600.00
87 Klem spore plank M_194 Btg. 30,600.00
88 Pipa baja tiang pancang M_197 Kg. 27,000.00
89 Sepatu besi untuk pancang kayu M_198 Bh 256,000.00
90 Baja konstruksi WF berbagai Ukuran: M - 199 Kg 36,000.00
91 Besi plat Uk berbagai Ukuran M - 200 Kg 36,000.00
92 Baja Kanal ( C ) Berbagai ukuran M - 201 Kg 36,000.00
93 Besi Profil CNP 125.50.20.3,2 M - 201 Kg 48,900.00
94 Besi Profil Siku - Kg 39,000.00
95 Besi Profil Hollow - Kg 38,000.00
96 Kusen Alumunium Uk. 5/5 cm Warna Silver - m1 149,000.00
97 Kusen Alumunium Uk. 4/8 cm Warna Silver - m1 121,000.00
98 Kusen Alumunium Uk. 5/10 cm Warna Silver - m1 161,000.00
99 Kusen Alumunium Uk. 5/12 cm Warna Silver - m1 143,500.00
100 Kusen Alumunium Ambang Uk. 3,5/5 cm Warna Silver - m1 141,850.00
101 Sunscreen Alumunium Lebar 7,5 cm - m2 1,206,000.00
102 Sunscreen Alumunium Lebar 13,5 cm - m2 1,876,000.00
103 Kawat Simpai M_237 Kg 17,200.00
104 Kawat Waring Kualitas Baik M_237.a m1 7,200.00
105 Kawat Waring Kualitas Biasa M_237.b m1 5,200.00
106 Kawat Duri M_238 Kg 20,200.00
107 Paku Campuran M_241 Kg 25,200.00
108 Paku Triplek M_241.a Kg 40,200.00
109 Paku Seng / Belian M_241.b Kg 30,200.00
110 Sekrup M_242 Kg 8,200.00
111 Sekrup Fixer - Buah 1,200.00
112 Sealant - Tube 45,200.00
113 Besi Strip M_243 Btg 17,000.00
114 Kabel / Seling 1" M_245 m1 83,000.00
115 Kabel / Seling 1/2" M_245.a m1 22,500.00
116 Kabel / Seling 1/4" M_245.b m1 11,000.00
HARGA SATUAN
NO URAIAN BAHAN / MATERIAL KODE SATUAN KETERANGAN
(Rp)

A B C D E F
117 Kabel Baja Pengaku dia. 19 mm M - 246 m1 40,500.00
118 Seling BaJa Dia. 1,5 " M - 247 m1 193,000.00
119 Seling Baja Dia. 2,5 " M - 247.a m1 203,000.00
120 Katrol M - 248 Set 1,770,000.00
121 Warfel 2" M - 249 Buah 655,000.00
122 Warfel 1/2" M - 249.a Buah 22,500.00
123 Warfel 19 mm M - 249.b Buah 35,500.00
124 Cekak 1,5" - Buah 47,000.00
125 Cekak 1" M - 250 Buah 22,000.00
126 Cekak 1/2" M - 250.a Buah 7,000.00
127 Cekak 1/4" M - 250.b Buah 5,250.00
128 Cekak seling 19 mm M - 251 Buah 13,000.00
129 Accesoris Plat Penggantung - Buah 58,100.00
BAHAN KAYU
130 Kayu Bakar M_070 m3 235,000.00
131 Kayu bulat untuk turap panjang 2 m M_175 Btg 7,500.00
132 Kayu Bulat Untuk Turap Panjang 4 - 4,5 m M_176 Btg 13,100.00
133 Kayu untuk Perancah M_180 m3 955,000.00
134 Kayu Konstruksi Jembatan (Kayu Belian Uk. 15/15 cm) M_181 m3 10,051,500.00
135 Kayu Konstruksi Jembatan (Kayu Kelas I Uk. 15/15 cm) M_191 m3 4,848,500.00
136 Papan Lantai Jembatan Kelas I Uk. 4/18-4,20 m M_191.g m3 4,386,500.00
137 Papan Lantai Jembatan Kelas I Uk. 4/18-3,60 m M_191.h m3 4,386,500.00
138 Kayu Tembesu M_195 m3 4,278,500.00
139 Kayu Belian Panjang ≥ 2,5 m (Ketam) M_181.a m3 11,214,500.00
140 Kayu Belian Panjang ≥ 2,5 m (Tidak Ketam) M_181.b m3 11,017,500.00
141 Kayu Belian Panjang < 2,5 m (Ketam) M_181.c m3 9,755,500.00
142 Kayu Belian Panjang < 2,5 m (Tidak Ketam) M_181.d m3 9,406,500.00
143 Kayu Klas I Tekam (Ketam) M_191.a m3 3,737,500.00
144 Kayu Klas I Tekam (Tidak Ketam) M_191.b m3 3,536,500.00
145 Kayu Klas I Selain Tekam (Ketam) M_191.c m3 3,334,500.00
146 Kayu Klas I Selain Tekam (Tidak Ketam) M_191.d m3 3,137,500.00
147 Kayu Klas II, Kawi Danau (Ketam) M_192.c m3 2,528,500.00
148 Kayu Klas II, Kawi Danau(Tidak Ketam) M_192.d m3 2,327,500.00
149 Kayu Klas II, Selain Kawi Danau (Ketam) M_192 m3 2,326,500.00
150 Kayu Klas II. Selain Kawi Danau (Tidak Ketam) M_192.a m3 2,125,500.00
151 Kayu Klas III (Ketam) M_213 m3 2,088,500.00
152 Kayu Klas III (Tidak Ketam) M_213.a m3 2,021,500.00
153 Papan Kayu Belian (Ketam) M_181.c m3 11,628,500.00
154 Papan Kayu Belian (Tidak Ketam) M_181.d m3 11,028,500.00
155 Papan Kayu Klas I, Tekam (Ketam) M_191.e m3 6,348,500.00
156 Papan Kayu Klas I, Tekam (Tidak Ketam) M_191.f m3 5,918,500.00
157 Papan Kayu Klas I, Selain Tekam (Ketam) M_191.g m3 5,918,500.00
158 Papan Kayu Klas I, Selain Tekam (Tidak Ketam) M_191.h m3 5,488,500.00
159 Papan Kayu Klas II, Kawi (Ketam) M_192.e m3 4,414,500.00
160 Papan Kayu Klas II Kawi (Tidak Ketam) M_192.f m3 3,984,500.00
161 Papan Kayu Klas II Selain Kawi (Ketam) M_192.g m3 3,355,500.00
162 Papan Kayu Klas II Selain Kawi (Tidak Ketam) M_192.h m3 2,925,500.00
163 Papan Kayu Klas III (Campuran) M_213.b m3 1,966,500.00
164 Tiang Tongkat Kayu Belian Uk. 9/9 - 4,20 M M_181.g Btg 335,000.00
165 Tiang Tongkat Kayu Belian Uk. 9/9 - 3,60 M M_181.h Btg 325,000.00
166 Tiang Tongkat Kayu Belian Uk. 9/9 - 3,20 M M_181.i Btg 300,000.00
167 Tiang Tongkat Kayu Belian Uk. 9/9 - 2,70 M M_181.j Btg 250,000.00
168 Tiang Tongkat Kayu Belian Uk. 9/9 - 2,50 M M_181.k Btg 235,200.00
169 Tiang Tongkat Kayu Belian Uk. 9/9 - 2,20 M M_181.l Btg 192,000.00
170 Tiang Tongkat Kayu Belian Uk. 9/9 - 2,10 M M_181.m Btg 184,400.00
171 Tiang Tongkat Kayu Belian Uk. 9/9 - 1,80 M M_181.n Btg 150,000.00
172 Tiang Tongkat Kayu Belian Uk. 9/9 - 1,50 M M_181.o Btg 95,200.00
173 Renglat M_215 Btg 9,300.00
174 Laci Kayu Belian 5/10 - 80 cm M_181.e Btg 9,600.00
175 Laci Kayu Belian 9/9 - 80 cm M_181.f Btg 15,500.00
176 Laci Kayu Belian 4/8 - 60 cm M_181.g Btg 8,800.00
177 Alas Kayu Hutan M_216 Btg 6,800.00
178 Alas Laci Kayu Belian 4/8-60 cm M_216.a Btg 8,800.00
179 Konsul Kayu Klas I M_217 Buah 95,000.00
180 Triplek 3 mm M_218 Lbr 60,300.00
181 Triplek 3 mm M_218.a m2 20,256.65
182 Triplek 6 mm M_218.b Lbr 145,300.00
183 Triplek 9 mm M_218.c Lbr 243,000.00
184 Triplek 12 mm M_218.d Lbr 303,000.00
185 Plywood 4' x 8' x 4 mm M_218.e Lbr 79,000.00
186 Lem Kayu M_219 ltr 40,500.00
187 Lem Kuning M_219.a ltr 47,500.00
188 List Kayu Profil M_220 m' 12,500.00
189 Kayu Profil List Plafond M_221 m' 7,000.00
HARGA SATUAN
NO URAIAN BAHAN / MATERIAL KODE SATUAN KETERANGAN
(Rp)

A B C D E F
190 Gypsum Profil List Plafond / Cornice - m1 30,500.00
191 Gypsum Board Tebal 4 mm M_222 Lbr 87,000.00
192 GRC Board Tebal 4 mm M_223 Lbr 76,500.00
193 Aklirik Tebal 6 mm Uk. 120 x 240 cm - Lbr 932,000.00
194 Papan Profil /Lambriziring - m3 4,504,000.00
195 Papan Lambrizing Tebal 9 mm - Lbr 166,000.00
196 Sungkai Tebal 3 mm, Uk. 120 x 240 cm - m2 82,000.00
197 List Plafond Ukiran Kayu Kelas I Lebar 70 cm - m1 551,000.00
BAHAN SANITASI
198 Talang Gantung & Talang Tegak M_229 m1 95,500.00
199 Pipa Suling Dia. 3/4" M - 253 Buah 20,100.00
200 Pipa Galvanis Dia. 2" M - 253.a m' 156,500.00
201 Pipa Galvanis Dia. 4" M - 253.b m' 560,500.00
202 Pipa Galvanis Dia. 6" M - 253.c m' 839,500.00
203 Pipa Spiral Dia. 4 - m' 425,000.00
205 Kloset Duduk M - 254 Buah 1,405,000.00
205 Kloset Jongkok M - 254.a Buah 195,000.00
206 Urinoir M - 255 Buah 577,900.00
207 Wastafel M - 256 Buah 670,000.00
208 Seal Tape Gypsum M - 257 Buah 30,100.00
209 Floor Drain M - 258 Buah 65,300.00
210 Kran Air Kualitas Biasa M - 259 Buah 15,300.00
211 Kran Air Kualitas Baik M - 259. a Buah 40,300.00
212 Kran Air Stainless Ø 1/2" M - 259. a Buah 47,300.00
213 Penguras Bak Air Ø 3/4" - Buah 15,300.00
214 Seal Tape Kran M - 260 Buah 3,100.00
215 Tempat Sabun Porcelain (Keramik) Terpasang - Buah 60,100.00
216 Centong Air Kualitas Biasa - Buah 15,100.00
217 Centong Air Kualitas Baik - Buah 25,100.00
218 Bak Air Fiber Glass 0,50 M3 M - 261 Buah 1,250,000.00
219 Bak Air Fiber Glass 0,75 M3 M - 261.a Buah 1,550,000.00
220 Bak Air Fiber Glass 0,80 M3 M - 261.b Buah 1,650,000.00
221 Bak Air Fiber Glass 1 M3 M - 261.c Buah 2,050,000.00
222 Bak Air Fiber Glass 2 M3 M - 261.d Buah 2,725,000.00
223 Bak Air Fiber Glass 1,5 M3 M - 261.e Buah 3,450,000.00
224 Bak Air Fiber Glass 3 M3 M - 261.f Buah 4,250,000.00
225 Bak Air Fiber Glass 5 M3 M - 261.g Buah 5,100,000.00
226 Septic Tank Type ST24 0,75 M3 - Buah 3,510,000.00
227 Septic Tank Type ST46 1,30 M3 - Buah 4,610,000.00
228 Septic Tank Type ST68 1,55 M3 - Buah 5,490,000.00
BAHAN ATAP
229 Seng Gelombang BJLS 0,20 M_224 Lbr 42,500.00
230 Seng Gelombang BJLS 0,20 M_224.a m2 33,203.13
231 Seng Gelombang BJLS 0,30 M_224.b Lbr 65,500.00
232 Seng Gelombang BJLS 0,30 M_224.c m2 51,171.88
233 Seng Gelombang Warna BJLS 0,25 M_224.d Lbr 55,500.00
234 Plat Aluminium Warna BJLS 0,25 - Lbr 65,500.00
235 Genteng Metal Type PRIMA 0,35 M_225 Lbr 37,500.00
236 Genteng Metal Type ROYAL 0,35 M_225.a Lbr 37,500.00
237 Genteng Metal Type CLASSIC 0,35 M_225.b Lbr 37,500.00
238 Zincalume BJLS 0,3 Polos M_225.d m2 95,500.00
239 Zincalume BJLS 0,3 Color M_225.e m2 105,500.00
240 Zincalume BJLS 0,35 Polos M_225.f m2 160,700.00
241 Zincalume BJLS 0,35 Color M_225.g m2 175,000.00
242 Zincalume BJLS 0,4 Polos M_225.h m2 165,500.00
243 Zincalume BJLS 0,4 Color M_225.i m2 178,500.00
244 Seng Datar Colour BJLS 0,35 M_227 Lbr 48,500.00
245 Seng Datar Polos BJLS 0,30 M_227.a Lbr 48,000.00
246 Zincalume Plat BJLS 0,3 Polos M_227.b Lbr 132,000.00
247 Zincalume Plat BJLS 0,3 Color M_227.c Lbr 146,300.00
248 Zincalume Plat BJLS 0,35 Polos M_227.d Lbr 160,700.00
249 Zincalume Plat BJLS 0,35 Color M_227.e Lbr 175,500.00
250 Nok / Bubungan Genteng Metal 1/2 Lingkaran 0,35 M_228 Buah 48,500.00
251 Roof Light Fiberglass - m2 362,500.00
252 Roof Light Polycarbonat - m2 356,500.00
BAHAN KERAMIK
253 Keramik 10 x 20 cm Polos M_240 Buah 1,850.00
254 Keramik 10 x 33 cm Polos M_240.a Buah 2,600.00
255 Keramik 20 x 20 cm Polos M_240.b Buah 2,900.00
256 Keramik 20 x 25 cm Polos M_240.c Buah 3,850.00
257 Keramik 30 x 30 cm Polos M_240.d Buah 6,350.00
258 Keramik 30 x 30 cm Artistik M_240.e Buah 6,400.00
259 Keramik 30 x 30 cm Unpolished M_240.f Buah 6,400.00
260 Keramik 40 x 40 cm Polos M_240.g Buah 15,900.00
261 Keramik 40 x 40 cm Anti Gores M_240.h Buah 20,100.00
262 Keramik 40 x 40 cm Unpolished M_240.i Buah 16,600.00
HARGA SATUAN
NO URAIAN BAHAN / MATERIAL KODE SATUAN KETERANGAN
(Rp)

A B C D E F
263 Keramik 60 x 60 cm Anti Gores (Polysed) M_240.j Buah 139,100.00
264 Keramik 10 x 10 cm Anti Gores (Polysed) M_240.k Buah 10,100.00
265 Keramik List Dinding 10 x 20 cm (Polysed) M_240.l Buah 6,100.00
266 Batu Granit - m2 1,200,100.00
267 Batu Teraso - m2 200,100.00
268 Batu Tempel Hitam (Batu Alam) - m2 230,100.00
269 Batu Andesit - m2 550,100.00
BAHAN KACA
270 Kaca Polos Tebal 3 mm M_244 m2 153,000.00
271 Kaca Polos Tebal 5 mm M_244.a m2 173,000.00
272 Kaca Polos Tebal 8 mm M_244.b m2 333,000.00
273 Kaca Polos Tebal 12 mm M_244.c m2 415,000.00
274 Kaca Rayben Tebal 5 mm M_244.d m2 203,000.00
275 Kaca Cermin Tebal 5 mm M_244.e m2 278,000.00
276 Kaca Buram Tebal 5 mm M_244.f m2 173,500.00
277 Kaca Setara Asahi Drak Blue Tebal 5 mm (Stopsol) M_244.g m2 333,000.00
278 Kaca Setara Asahi Drak Blue Tebal 6 mm (Stopsol) M_244.h m2 683,000.00
279 Kaca Setara Asahi Drak Blue Tebal 8 mm (Stopsol) M_244.i m2 768,000.00
280 Kaca Setara Asahi Drak Blue Tebal 12 mm (Stopsol) M_244.j m2 966,000.00
BAHAN LISTRIK
281 Saklar Ganda Kualitas Biasa M - 262 Buah 10,050.00
282 Saklar Ganda Kualitas Baik M - 262.a Buah 25,050.00
283 Saklar Tunggal Kualitas Biasa M - 262.b Buah 9,050.00
284 Saklar Tunggal Kualitas Baik M - 262.c Set 20,050.00
285 Stop Kontak Kualitas Biasa M - 263 Set 10,050.00
286 Stop Kontak Kualitas Baik M - 263.a Set 17,050.00
287 Sekring Box / MCB M - 264 Set 120,100.00
288 Lampu Pijar 40 Watt M - 265.a Set 25,050.00
289 Lampu XL 20 Watt M - 265.b Set 45,050.00
290 Lampu TL 20 Watt M - 266.c Set 45,050.00
291 Lampu LED 5 Watt M - 266.d Buah 50,050.00
292 Lampu LED 5 Watt M - 266.e Buah 110,050.00
293 Lampu LED 5 Watt M - 266.f Buah 125,050.00
294 Instalasi Titik Lampu - Titik 225,500.00
BAHAN PENGUNCI & PENGGANTUNG
295 Engsel Pintu M - 267 Buah 25,050.00
296 Engsel Jendela M - 267.a Buah 20,050.00
297 Engsel Pintu Pivot (Tanam) Kualitas Baik Terpasang M - 267.a Buah 975,350.00
298 Handle Pintu M - 268 Buah 80,050.00
299 Handle Pintu Stainless Steel Panjang 30 cm M - 268.a Buah 150,050.00
300 Handle Jendela M - 268.a Buah 13,050.00
301 Slot Pintu M - 269 Buah 12,050.00
302 Slot Pintu Tanam - Buah 105,050.00
303 Slot Jendela M - 269.a Buah 8,050.00
304 Kait Angin M - 270 Buah 6,050.00
305 Kunci 2 Slaag M - 271 Buah 198,500.00
306 Kunci Pintu Tanam M - 271.a Buah 160,500.00
307 Kunci Pintu Tanam 2 Slaag M - 271.a Buah 198,500.00
308 Pintu Folding Gate + Pemasangan M - 272 m2 590,000.00
309 Pintu Gulungan Besi (Rolling Door) M - 272.a m2 590,000.00
310 Door Closer M - 273 Buah 230,500.00
311 Engsel Sendok - Buah 15,500.00
BAHAN PERPIPAAN
312 Pipa Ø 1/2 " PVC M - 280.a m' 5,300.00
313 Pipa Ø 3/4 " PVC M - 281.a m' 8,150.00
314 Pipa Ø 1 " PVC M - 282.a m' 10,300.00
315 Pipa Ø 1,5 " PVC M - 283.a m' 17,050.00
316 Pipa Ø 2 " PVC M - 284.a m' 21,700.00
317 Pipa Ø 2,5 " PVC M - 285.a m' 30,900.00
318 Pipa Ø 3 " PVC M - 286.a m' 43,000.00
319 Pipa Ø 4 " PVC M - 287.a m' 71,050.00
320 Pipa Ø 6 " PVC M - 288.a m' 161,350.00
321 Pipa Ø 8 " PVC M - 289.a m' 278,500.00
322 Pipa Ø 1,5 " PVC M - 290.b m' 11,200.00
323 Pipa Ø 2 " PVC M - 291.b m' 14,800.00
324 Pipa Ø 2,5 " PVC M - 292.b m' 20,050.00
325 Pipa Ø 3 " PVC M - 293.b m' 26,600.00
326 Pipa Ø 4 " PVC M - 294.b m' 42,200.00
327 Pipa Ø 6 " PVC M - 295.b m' 111,300.00
328 Pipa Ø 8 " PVC M - 296.b m' 165,950.00
327 Water Meter 1/2" M - 440 Buah 347,565.00
328 Water Meter 50 mm M - 441 Buah 1,215,000.00
329 Water Meter 75 mm M - 442 Buah 1,988,000.00
330 Water Meter 100 mm M - 443 Buah 3,108,000.00
331 Water Meter 150 mm M - 444 Buah 3,328,000.00
332 Water Meter 200 mm M - 445 Buah 4,476,000.00
WILAYAH PUTUSSIBAU DAN SEKITARNYA
(Meliputi: Kec. Putussibau Utara, Putussibau Selatan, Kalis, Bika, Mentebah, Boyan Tanjung, Bunut
Hulu, Pengkadan, Hulu Gurung, Embaloh Hulu, dll)
K.9

Propinsi Kalimantan Barat : 61


Kabupaten Kapuas Hulu : 06
UPAH UPAH
NO. TENAGA KERJA KODE TENAGA KERJA TENAGA KERJA KETERANGAN
( Rp / Hari ) ( Rp / Jam )*
1 Mandor Lapangan L.061 150,000.00 21,428.57
2 Mekanik L.071 150,000.00 21,428.57
3 Mekanik Pembantu L.072 125,000.00 17,857.14
4 Kepala Tukang L.073 150,000.00 21,428.57
5 Tukang L.079 125,000.00 17,857.14
6 Operator ** L.081 150,000.00 21,428.57
7 Pembantu Operator *** L.089 105,000.00 15,000.00
8 Supir Truck Material L.091 125,000.00 17,857.14
9 Pembantu Supir L.099 100,000.00 14,285.71
10 Buruh Lapangan Tidak Terlatih/Pekerja L.101 100,000.00 14,285.71
* Tenaga Kerja Dihitung 7 (Tujuh) Jam Kerja / Hari

Dengan Pertimbangan kondisi lokasi - lokasi yang bervariasi pada Kabupaten Kapuas Hulu, maka harga dasar dikelompokkan Dalam 6 wilayah sebagai berikut, lokasi yang diluar 6 wilayah
tersebut mengikuti standar harga dasar (Harga Putussibau dan Sekitarnya).
* Wilayah Pts&Sekitarnya : Adalah Wilayah yang meliputi Kec. Putussibau Utara, Putussibau Selatan, Kalis, Bika, Mentebah, Boyan Tanjung, Bunut Hulu, Pengkadan,
Hulu Gurung, Embaloh Hulu, dll)
* Wilayah I Meliputi : Adalah Wilayah Dimana Harga Dasar Material Quarry ( Batu,Pasir,dll ) dan Harga Angkut (Jalur Darat) Bahan Pabrikan (Semen,Besi Tulangan,dll)
dinaikan, Wilayah ini sesuai dengan kondisi daerah seperti : Empanang, Badau, Batang Lupar, Puring Kencana dll
* Wilayah II Meliputi : Adalah Wilayah Dimana Harga Dasar Material Quarry ( Batu,Pasir,dll ) tetap, dan Harga Angkut (Jalur Air) Bahan Pabrikan (Semen,Besi Tulangan,dll)
dinaikan, Wilayah ini sesuai dengan kondisi daerah seperti : Mendalam, Kensurai, Na. Lebangan, dll.
* Wilayah III Meliputi : Adalah Wilayah Dimana Harga Dasar Material Quarry ( Batu,Pasir,dll ) dan Harga Angkut (Jalur Air) Bahan Pabrikan (Semen,Besi Tulangan,dll)
dinaikan, Wilayah ini sesuai dengan kondisi daerah seperti : Kecamatan Embaloh Hilir, Bunut Hilir, Jongkong, dll.
* Wilayah IV Meliputi : Adalah Wilayah Dimana Harga Dasar Material Quarry ( Batu,Pasir,dll ) Tetap, dan Harga Angkut (Jalur Darat) Bahan Pabrikan
(Semen,Besi Tulangan,dll) diturunkan, Wilayah ini sesuai dengan kondisi daerah seperti : Kec Sejiram, Semitau, Suhaid, Selimbau, Silat Hilir, Silat Hulu dll.
* Wilayah Khusus Meliputi: Adalah Wilayah Diluar Wilayah I - IV (Kondisi Transportasi Sulit).
Wilayah ini sesuai dengan kondisi daerah seperti : Tanjung Lokang, Beberuk, Sepan padang, Sauk, Semalah, Tempurau, Rantau Bumbun dll.

HARGA DI SUM- JARAK ONGKOS JUMLAH PAJAK JUMLAH HARGA


BER/QUARY ANGKUT ANGKUT HARGA Profit 10 % GALIAN - C TERMASUK
NO MATERIAL UNIT KODE
(TANPA PAJAK) RATA-RATA PER UNIT TANPA PAJAK ( Rp ) ( 10 % ) PAJAK
( Rp ) ( Km ) ( Rp ) ( Rp ) ( Rp ) ( Rp )

BAHAN PENGISI
1 Batu Gunung Quary m3 M_010 140,000.00 < 30 200,000.00 340,000.00 0.00 0.00 340,000.00
2 Batu Gunung Quary m3 M_010.a 140,000.00 < 20 92,000.00 232,000.00 0.00 0.00 232,000.00
3 Batu Gunung Quary m3 M_010.b 140,000.00 < 10 54,000.00 194,000.00 0.00 0.00 194,000.00
4 Kerikil dari galian bukit m3 M_011 80,000.00 < 30 200,000.00 280,000.00 0.00 0.00 280,000.00
5 Kerikil Sungai ( Leveransir ) m3 M_012 105,000.00 < 20 92,000.00 197,000.00 0.00 0.00 197,000.00
6 Kerikil Sungai ( Royality ) m3 M_013 80,000.00 - - 80,000.00 0.00 0.00 80,000.00
7 Batu kali m3 M_014 130,000.00 < 20 92,000.00 222,000.00 0.00 0.00 222,000.00
8 Kerikil sungai ayak tanpa pasir (1-2 cm) m3 M_015 115,000.00 < 20 92,000.00 207,000.00 0.00 0.00 207,000.00
9 Kerikil sungai ayak tanpa pasir (2-3 cm) m3 M_015.a 100,000.00 < 20 92,000.00 192,000.00 0.00 0.00 192,000.00
10 Batu pecah gunung (10 - 15 cm) m3 M_021 250,000.00 < 30 200,000.00 450,000.00 0.00 0.00 450,000.00
11 Batu pecah gunung (7 - 10 cm) m3 M_022 375,000.00 < 30 200,000.00 575,000.00 0.00 0.00 575,000.00
12 Batu pecah gunung (5 - 7 cm.) m3 M_023 475,000.00 < 30 200,000.00 675,000.00 0.00 0.00 675,000.00
13 Batu pecah gunung (3 - 5 cm.) m3 M_024 525,000.00 < 30 200,000.00 725,000.00 0.00 0.00 725,000.00
14 Batu pecah gunung (2 - 3 cm.) m3 M_025 575,000.00 < 30 200,000.00 775,000.00 0.00 0.00 775,000.00
15 Batu pecah gunung (1 - 2 cm.) m3 M_026 625,000.00 < 30 200,000.00 825,000.00 0.00 0.00 825,000.00
16 Batu pecah gunung (0,5 - 1 cm.) m3 M_027 775,000.00 < 30 200,000.00 975,000.00 0.00 0.00 975,000.00
17 Batu pecah sungai (3 - 5 cm.) m3 M_028 425,000.00 < 30 200,000.00 625,000.00 0.00 0.00 625,000.00
18 Batu pecah sungai (2 - 3 cm.) m3 M_029 475,000.00 < 30 200,000.00 675,000.00 0.00 0.00 675,000.00
19 Batu pecah sungai (1 - 2 cm.) m3 M_030 525,000.00 < 30 200,000.00 725,000.00 0.00 0.00 725,000.00
20 Batu pecah sungai (0,5 - 1 cm.) m3 M_031 625,000.00 < 30 200,000.00 825,000.00 0.00 0.00 825,000.00
21 Pasir urug / timbun m3 M_040 80,000.00 < 20 92,000.00 172,000.00 0.00 0.00 172,000.00
22 Pasir ayak untuk beton m3 M_041 95,000.00 < 20 92,000.00 187,000.00 0.00 0.00 187,000.00
23 Sirtu Sungai ( Leveransir ) m3 M_042 95,000.00 < 10 92,000.00 187,000.00 0.00 0.00 187,000.00
24 Sirtu Sungai ( Royality ) m3 M_043 80,000.00 - - 80,000.00 0.00 0.00 80,000.00
25 Bahan timbunan pilihan (laterit) Leveransir m3 M_050 45,000.00 < 20 92,000.00 137,000.00 0.00 0.00 137,000.00
26 Bahan timbunan pilihan (laterit) Setempat m3 M_051 40,000.00 - - 40,000.00 0.00 0.00 40,000.00
27 Timbunan setempat ( tanah biasa) m3 M_052 10,000.00 - - 10,000.00 0.00 0.00 10,000.00
28 Aspal Bitument Kg. M_061 10,000.00 >100 800.00 10,800.00 0.00 0.00 10,800.00
29 Semen Portlant ( PC ) 50 Kg. M_080 125,000.00 < 10 2,000.00 127,000.00 0.00 0.00 127,000.00
30 Semen Portlant ( PC ) Kg M_080.a 2,500.00 < 10 40.00 2,540.00 0.00 0.00 2,540.00
31 Semen Warna (Oker) Kg M_080.b 15,000.00 100 40.00 15,040.00 0.00 0.00 15,040.00
32 Paving blok BH M_082 3,000.00 < 10 200.00 3,200.00 0.00 0.00 3,200.00
33 Bataco Ukuran 15 x 30 x 7 cm Buah M_239 2,500.00 < 10 200.00 2,700.00 0.00 0.00 2,700.00
34 Bataco Ukuran 20 x 40 x 7 cm Buah M_239.a 3,000.00 < 10 200.00 3,200.00 0.00 0.00 3,200.00
35 Bataco Ukuran 20 x 40 x 9 cm Buah M_239.b 3,250.00 < 10 200.00 3,450.00 0.00 0.00 3,450.00
36 Alat - alat bantu * Set M_171 120,000.00 < 10 5,000.00 125,000.00 0.00 0.00 125,000.00
37 Alat - alat bantu ** Set M_172 200,000.00 < 10 5,000.00 205,000.00 0.00 0.00 205,000.00
38 Alat - alat bantu pek. Latasir *** Set M_173 230,000.00 < 10 5,000.00 235,000.00 0.00 0.00 235,000.00
HARGA DI SUM- JARAK ONGKOS JUMLAH PAJAK JUMLAH HARGA
BER/QUARY ANGKUT ANGKUT HARGA Profit 10 % GALIAN - C TERMASUK
NO MATERIAL UNIT KODE
(TANPA PAJAK) RATA-RATA PER UNIT TANPA PAJAK ( Rp ) ( 10 % ) PAJAK
( Rp ) ( Km ) ( Rp ) ( Rp ) ( Rp ) ( Rp )
39 Gerobak + kuali aspal Set M_174 6,000,000.00 < 10 250,000.00 6,250,000.00 0.00 0.00 6,250,000.00
HARGA DI SUM- JARAK ONGKOS JUMLAH PAJAK JUMLAH HARGA
BER/QUARY ANGKUT ANGKUT HARGA Profit 10 % GALIAN - C TERMASUK
NO MATERIAL UNIT KODE
(TANPA PAJAK) RATA-RATA PER UNIT TANPA PAJAK ( Rp ) ( 10 % ) PAJAK
( Rp ) ( Km ) ( Rp ) ( Rp ) ( Rp ) ( Rp )

BAHAN MINYAK
40 Minyak Tanah Ltr. M_065 7,000.00 >100 600.00 7,600.00 0.00 0.00 7,600.00
41 Minyak Diesel Ltr. M_183 13,100.00 >100 600.00 13,700.00 0.00 0.00 13,700.00
42 Premium / Bensin Ltr. M_184 11,000.00 >100 600.00 11,600.00 0.00 0.00 11,600.00
43 Minyak Pelumas Ltr. M_185 30,000.00 >100 600.00 30,600.00 0.00 0.00 30,600.00
44 Minyak Thinner Ltr M - 203 20,000.00 > 100 500.00 20,500.00 0.00 0.00 20,500.00
45 Minyak Bekesting / Cetakan Ltr M - 203.a 7,000.00 >100 300.00 7,300.00 0.00 0.00 7,300.00
BAHAN CAT
46 Cat Jembatan Kg M_090 120,000.00 10 500.00 120,500.00 0.00 0.00 120,500.00
47 Cat Dasar Kg. M_187 45,000.00 10 600.00 45,600.00 0.00 0.00 45,600.00
48 Alkali Kg - 54,000.00 10 300.00 54,300.00 0.00 0.00 54,300.00
49 Teer Kg. M_188 10,000.00 10 600.00 10,600.00 0.00 0.00 10,600.00
50 Cat Kilap Kg. M_193 55,000.00 10 600.00 55,600.00 0.00 0.00 55,600.00
51 Cat Galvanis Kg M - 202 45,000.00 > 100 6,000.00 51,000.00 0.00 0.00 51,000.00
52 Dempul Kg M_230 35,000.00 10 100.00 35,100.00 0.00 0.00 35,100.00
53 Plamur Kg M_231 35,000.00 10 100.00 35,100.00 0.00 0.00 35,100.00
54 Amplas Lbr M_232 3,000.00 10 100.00 3,100.00 0.00 0.00 3,100.00
55 Cat Tembok Kualitas Biasa Kg M_233 10,000.00 10 100.00 10,100.00 0.00 0.00 10,100.00
56 Cat Tembok Kualitas Sedang Kg M_233.a 17,225.00 10 100.00 17,325.00 0.00 0.00 17,325.00
57 Cat Tembok Weather Shield Kg M_233.b 110,000.00 10 100.00 110,100.00 0.00 0.00 110,100.00
58 Cat Vernis Liter M_233.a 50,000.00 10 100.00 50,100.00 0.00 0.00 50,100.00
59 Cat Melamic Kg M_233.b 60,000.00 10 100.00 60,100.00 0.00 0.00 60,100.00
60 Cat Meni Besi Kg M_233.c 27,000.00 10 100.00 27,100.00 0.00 0.00 27,100.00
61 Cat Meni Atap Kg M_233.d 30,000.00 10 100.00 30,100.00 0.00 0.00 30,100.00
62 Cat Tembok Interior Kg M_233.e 100,000.00 10 100.00 100,100.00 0.00 0.00 100,100.00
63 Cat Tembok Eksterior (Anti Jamur) Kg M_233.f 110,000.00 10 100.00 110,100.00 0.00 0.00 110,100.00
64 Cat Water Proofing Kg M_233.g 55,000.00 10 100.00 55,100.00 0.00 0.00 55,100.00
65 Soda Api Kg M_234 41,000.00 10 100.00 41,100.00 0.00 0.00 41,100.00
66 Sabun Kg M_235 5,000.00 10 100.00 5,100.00 0.00 0.00 5,100.00
67 Kuas Cat Buah M_236 20,000.00 10 100.00 20,100.00 0.00 0.00 20,100.00
BAHAN BESI & BAJA
68 Baja Tralis Kg. M_161 20,000.00 10 600.00 20,600.00 0.00 0.00 20,600.00
69 Kawat Bronjong Galvanis uk. 2.0 x 1.0 x 0.5 dia. 3 mm Unit M_162 640,000.00 >100 6,000.00 646,000.00 0.00 0.00 646,000.00
70 Kawat Bronjong Galvanis Kg. M_162. a 35,000.00 >100 600.00 35,600.00 0.00 0.00 35,600.00
71 Kawat Bronjong Galvanis Lapis PVC Kg. M_162. b 70,000.00 >100 600.00 70,600.00 0.00 0.00 70,600.00
72 Kawat las Kg. M_162 c 27,000.00 100 6,000.00 33,000.00 0.00 0.00 33,000.00
73 Kawat Las Listrik Kg M_162 d 26,000.00 100 6,000.00 32,000.00 0.00 0.00 32,000.00
74 Paku Jembatan Kg. M_166 30,000.00 100 600.00 30,600.00 0.00 0.00 30,600.00
75 Baut Baja Kg. M_163 30,000.00 >100 6,000.00 36,000.00 0.00 0.00 36,000.00
76 Besi Galvanis sandaran jembatan btg M_164 620,000.00 100 6,000.00 626,000.00 0.00 0.00 626,000.00
77 Baja Konstruksi (rangka baja Jembatan) Kg. M_165 30,000.00 >100 6,000.00 36,000.00 0.00 0.00 36,000.00
78 Baja Beton U.24 Tulangan Polos dan Ulir Kg. M_167 22,000.00 100 600.00 22,600.00 0.00 0.00 22,600.00
79 Baja Beton U.32 Tulangan Polos dan Ulir Kg. M_167. a 23,000.00 100 600.00 23,600.00 0.00 0.00 23,600.00
80 Wire Mash M5 Kg. M_167. b 28,300.00 100 600.00 28,900.00 0.00 0.00 28,900.00
81 Wire Mash M6 Kg. M_167. c 37,100.00 100 600.00 37,700.00 0.00 0.00 37,700.00
82 Kawat Bindrat / Kawat Ikat Kg. M_170 25,000.00 100 600.00 25,600.00 0.00 0.00 25,600.00
83 Beugel tebal plat 5 mm Bh. M_186 25,000.00 10 600.00 25,600.00 0.00 0.00 25,600.00
84 Baut Panjang (15 - 30 cm) Btg. M_189 7,500.00 10 600.00 8,100.00 0.00 0.00 8,100.00
85 Paku Baut 15 cm Btg. M. 189.A 5,000.00 10 600.00 5,600.00 0.00 0.00 5,600.00
86 Baut Pendek (4 - 12 cm) Btg. M_190 2,000.00 10 600.00 2,600.00 0.00 0.00 2,600.00
87 Klem spore plank Btg. M_194 30,000.00 10 600.00 30,600.00 0.00 0.00 30,600.00
88 Pipa baja tiang pancang Kg. M_197 21,000.00 100 6,000.00 27,000.00 0.00 0.00 27,000.00
89 Sepatu besi untuk pancang kayu Bh M_198 250,000.00 6,000.00 256,000.00 0.00 0.00 256,000.00
90 Baja konstruksi WF berbagai Ukuran: Kg M - 199 30,000.00 > 100 6,000.00 36,000.00 0.00 0.00 36,000.00
91 Besi plat Uk berbagai Ukuran Kg M - 200 30,000.00 > 100 6,000.00 36,000.00 0.00 0.00 36,000.00
92 Baja Kanal ( C ) Berbagai ukuran Kg M - 201 30,000.00 > 100 6,000.00 36,000.00 0.00 0.00 36,000.00
93 Besi Profil CNP 125.50.20.3,2 Kg M - 201 42,900.00 > 100 6,000.00 48,900.00 0.00 0.00 48,900.00
94 Besi Profil Siku Kg - 33,000.00 > 100 6,000.00 39,000.00 0.00 0.00 39,000.00
95 Besi Profil Hollow Kg - 32,000.00 > 100 6,000.00 38,000.00 0.00 0.00 38,000.00
96 Kusen Alumunium Uk. 5/5 cm Warna Silver m1 - 143,000.00 > 100 6,000.00 149,000.00 0.00 0.00 149,000.00
97 Kusen Alumunium Uk. 4/8 cm Warna Silver m1 - 115,000.00 > 100 6,000.00 121,000.00 0.00 0.00 121,000.00
98 Kusen Alumunium Uk. 5/10 cm Warna Silver m1 - 155,000.00 > 100 6,000.00 161,000.00 0.00 0.00 161,000.00
99 Kusen Alumunium Uk. 5/12 cm Warna Silver m1 - 137,500.00 > 100 6,000.00 143,500.00 0.00 0.00 143,500.00
100 Kusen Alumunium Ambang Uk. 3,5/5 cm Warna Silver m1 - 135,850.00 > 100 6,000.00 141,850.00 0.00 0.00 141,850.00
101 Sunscreen Alumunium Lebar 7,5 cm m2 - 1,200,000.00 > 100 6,000.00 1,206,000.00 0.00 0.00 1,206,000.00
102 Sunscreen Alumunium Lebar 13,5 cm m2 - 1,870,000.00 > 100 6,000.00 1,876,000.00 0.00 0.00 1,876,000.00
103 Kawat Simpai Kg M_237 17,000.00 10 200.00 17,200.00 0.00 0.00 17,200.00
104 Kawat Waring Kualitas Baik m1 M_237.a 7,000.00 10 200.00 7,200.00 0.00 0.00 7,200.00
105 Kawat Waring Kualitas Biasa m1 M_237.b 5,000.00 10 200.00 5,200.00 0.00 0.00 5,200.00
106 Kawat Duri Kg M_238 20,000.00 10 200.00 20,200.00 0.00 0.00 20,200.00
107 Paku Campuran Kg M_241 25,000.00 10 200.00 25,200.00 0.00 0.00 25,200.00
108 Paku Triplek Kg M_241.a 40,000.00 10 200.00 40,200.00 0.00 0.00 40,200.00
109 Paku Seng / Belian Kg M_241.b 30,000.00 10 200.00 30,200.00 0.00 0.00 30,200.00
HARGA DI SUM- JARAK ONGKOS JUMLAH PAJAK JUMLAH HARGA
BER/QUARY ANGKUT ANGKUT HARGA Profit 10 % GALIAN - C TERMASUK
NO MATERIAL UNIT KODE
(TANPA PAJAK) RATA-RATA PER UNIT TANPA PAJAK ( Rp ) ( 10 % ) PAJAK
( Rp ) ( Km ) ( Rp ) ( Rp ) ( Rp ) ( Rp )
110 Sekrup Kg M_242 8,000.00 10 200.00 8,200.00 0.00 0.00 8,200.00
111 Sekrup Fixer Buah - 1,000.00 10 200.00 1,200.00 0.00 0.00 1,200.00
112 Sealant Tube - 45,000.00 10 200.00 45,200.00 0.00 0.00 45,200.00
113 Besi Strip Btg M_243 15,000.00 10 2,000.00 17,000.00 0.00 0.00 17,000.00
HARGA DI SUM- JARAK ONGKOS JUMLAH PAJAK JUMLAH HARGA
BER/QUARY ANGKUT ANGKUT HARGA Profit 10 % GALIAN - C TERMASUK
NO MATERIAL UNIT KODE
(TANPA PAJAK) RATA-RATA PER UNIT TANPA PAJAK ( Rp ) ( 10 % ) PAJAK
( Rp ) ( Km ) ( Rp ) ( Rp ) ( Rp ) ( Rp )
114 Kabel / Seling 1" m1 M_245 80,000.00 > 100 3,000.00 83,000.00 0.00 0.00 83,000.00
115 Kabel / Seling 1/2" m1 M_245.a 19,500.00 > 100 3,000.00 22,500.00 0.00 0.00 22,500.00
116 Kabel / Seling 1/4" m1 M_245.b 10,000.00 > 100 1,000.00 11,000.00 0.00 0.00 11,000.00
117 Kabel Baja Pengaku dia. 19 mm m1 M - 246 37,500.00 > 100 3,000.00 40,500.00 0.00 0.00 40,500.00
118 Seling BaJa Dia. 1,5 " m1 M - 247 190,000.00 > 100 3,000.00 193,000.00 0.00 0.00 193,000.00
119 Seling Baja Dia. 2,5 " m1 M - 247.a 200,000.00 > 100 3,000.00 203,000.00 0.00 0.00 203,000.00
120 Katrol Set M - 248 1,750,000.00 > 100 20,000.00 1,770,000.00 0.00 0.00 1,770,000.00
121 Warfel 2" Buah M - 249 650,000.00 > 100 5,000.00 655,000.00 0.00 0.00 655,000.00
122 Warfel 1/2" Buah M - 249.a 17,500.00 > 100 5,000.00 22,500.00 0.00 0.00 22,500.00
123 Warfel 19 mm Buah M - 249.b 30,500.00 > 100 5,000.00 35,500.00 0.00 0.00 35,500.00
124 Cekak 1,5" Buah - 45,000.00 > 100 2,000.00 47,000.00 0.00 0.00 47,000.00
125 Cekak 1" Buah M - 250 20,000.00 > 100 2,000.00 22,000.00 0.00 0.00 22,000.00
126 Cekak 1/2" Buah M - 250.a 5,000.00 > 100 2,000.00 7,000.00 0.00 0.00 7,000.00
127 Cekak 1/4" Buah M - 250.b 4,500.00 > 100 750.00 5,250.00 0.00 0.00 5,250.00
128 Cekak seling 19 mm Buah M - 251 11,000.00 > 100 2,000.00 13,000.00 0.00 0.00 13,000.00
129 Accesoris Plat Penggantung Buah - 57,500.00 10 600.00 58,100.00 0.00 0.00 58,100.00
BAHAN KAYU
130 Kayu Bakar m3 M_070 80,000.00 10 155,000.00 235,000.00 0.00 0.00 235,000.00
131 Kayu bulat untuk turap panjang 2 m Btg M_175 7,000.00 10 500.00 7,500.00 0.00 0.00 7,500.00
132 Kayu Bulat Untuk Turap Panjang 4 - 4,5 m Btg M_176 12,000.00 10 1,100.00 13,100.00 0.00 0.00 13,100.00
133 Kayu untuk Perancah m3 M_180 800,000.00 10 155,000.00 955,000.00 0.00 0.00 955,000.00
134 Kayu Konstruksi Jembatan (Kayu Belian Uk. 15/15 cm) m3 M_181 9,523,000.00 > 100 528,500.00 10,051,500.00 0.00 0.00 10,051,500.00
135 Kayu Konstruksi Jembatan (Kayu Kelas I Uk. 15/15 cm) m3 M_191 4,320,000.00 > 100 528,500.00 4,848,500.00 0.00 0.00 4,848,500.00
136 Papan Lantai Jembatan Kelas I Uk. 4/18-4,20 m m3 M_191.g 3,858,000.00 > 100 528,500.00 4,386,500.00 0.00 0.00 4,386,500.00
137 Papan Lantai Jembatan Kelas I Uk. 4/18-3,60 m m3 M_191.h 3,858,000.00 > 100 528,500.00 4,386,500.00 0.00 0.00 4,386,500.00
138 Kayu Tembesu m3 M_195 3,750,000.00 > 100 528,500.00 4,278,500.00 0.00 0.00 4,278,500.00
139 Kayu Belian Panjang ≥ 2,5 m (Ketam) m3 M_181.a 10,686,000.00 > 100 528,500.00 11,214,500.00 0.00 0.00 11,214,500.00
140 Kayu Belian Panjang ≥ 2,5 m (Tidak Ketam) m3 M_181.b 10,489,000.00 > 100 528,500.00 11,017,500.00 0.00 0.00 11,017,500.00
141 Kayu Belian Panjang < 2,5 m (Ketam) m3 M_181.c 9,227,000.00 > 100 528,500.00 9,755,500.00 0.00 0.00 9,755,500.00
142 Kayu Belian Panjang < 2,5 m (Tidak Ketam) m3 M_181.d 8,878,000.00 > 100 528,500.00 9,406,500.00 0.00 0.00 9,406,500.00
143 Kayu Klas I Tekam (Ketam) m3 M_191.a 3,209,000.00 > 100 528,500.00 3,737,500.00 0.00 0.00 3,737,500.00
144 Kayu Klas I Tekam (Tidak Ketam) m3 M_191.b 3,008,000.00 > 100 528,500.00 3,536,500.00 0.00 0.00 3,536,500.00
145 Kayu Klas I Selain Tekam (Ketam) m3 M_191.c 2,806,000.00 > 100 528,500.00 3,334,500.00 0.00 0.00 3,334,500.00
146 Kayu Klas I Selain Tekam (Tidak Ketam) m3 M_191.d 2,609,000.00 > 100 528,500.00 3,137,500.00 0.00 0.00 3,137,500.00
147 Kayu Klas II, Kawi Danau (Ketam) m3 M_192.c 2,000,000.00 > 100 528,500.00 2,528,500.00 0.00 0.00 2,528,500.00
148 Kayu Klas II, Kawi Danau(Tidak Ketam) m3 M_192.d 1,799,000.00 > 100 528,500.00 2,327,500.00 0.00 0.00 2,327,500.00
149 Kayu Klas II, Selain Kawi Danau (Ketam) m3 M_192 1,798,000.00 > 100 528,500.00 2,326,500.00 0.00 0.00 2,326,500.00
150 Kayu Klas II. Selain Kawi Danau (Tidak Ketam) m3 M_192.a 1,597,000.00 > 100 528,500.00 2,125,500.00 0.00 0.00 2,125,500.00
151 Kayu Klas III (Ketam) m3 M_213 1,560,000.00 > 100 528,500.00 2,088,500.00 0.00 0.00 2,088,500.00
152 Kayu Klas III (Tidak Ketam) m3 M_213.a 1,493,000.00 > 100 528,500.00 2,021,500.00 0.00 0.00 2,021,500.00
153 Papan Kayu Belian (Ketam) m3 M_181.c 11,100,000.00 > 100 528,500.00 11,628,500.00 0.00 0.00 11,628,500.00
154 Papan Kayu Belian (Tidak Ketam) m3 M_181.d 10,500,000.00 > 100 528,500.00 11,028,500.00 0.00 0.00 11,028,500.00
155 Papan Kayu Klas I, Tekam (Ketam) m3 M_191.e 5,770,000.00 > 100 578,500.00 6,348,500.00 0.00 0.00 6,348,500.00
156 Papan Kayu Klas I, Tekam (Tidak Ketam) m3 M_191.f 5,340,000.00 > 100 578,500.00 5,918,500.00 0.00 0.00 5,918,500.00
157 Papan Kayu Klas I, Selain Tekam (Ketam) m3 M_191.g 5,340,000.00 > 100 578,500.00 5,918,500.00 0.00 0.00 5,918,500.00
158 Papan Kayu Klas I, Selain Tekam (Tidak Ketam) m3 M_191.h 4,910,000.00 > 100 578,500.00 5,488,500.00 0.00 0.00 5,488,500.00
159 Papan Kayu Klas II, Kawi (Ketam) m3 M_192.e 3,836,000.00 10 578,500.00 4,414,500.00 0.00 0.00 4,414,500.00
160 Papan Kayu Klas II Kawi (Tidak Ketam) m3 M_192.f 3,406,000.00 10 578,500.00 3,984,500.00 0.00 0.00 3,984,500.00
161 Papan Kayu Klas II Selain Kawi (Ketam) m3 M_192.g 2,777,000.00 10 578,500.00 3,355,500.00 0.00 0.00 3,355,500.00
162 Papan Kayu Klas II Selain Kawi (Tidak Ketam) m3 M_192.h 2,347,000.00 10 578,500.00 2,925,500.00 0.00 0.00 2,925,500.00
163 Papan Kayu Klas III (Campuran) m3 M_213.b 1,388,000.00 10 578,500.00 1,966,500.00 0.00 0.00 1,966,500.00
164 Tiang Tongkat Kayu Belian Uk. 9/9 - 4,20 M Btg M_181.g 320,000.00 <10 15,000.00 335,000.00 0.00 0.00 335,000.00
165 Tiang Tongkat Kayu Belian Uk. 9/9 - 3,60 M Btg M_181.h 312,000.00 <10 13,000.00 325,000.00 0.00 0.00 325,000.00
166 Tiang Tongkat Kayu Belian Uk. 9/9 - 3,20 M Btg M_181.i 289,000.00 <10 11,000.00 300,000.00 0.00 0.00 300,000.00
167 Tiang Tongkat Kayu Belian Uk. 9/9 - 2,70 M Btg M_181.j 240,500.00 <10 9,500.00 250,000.00 0.00 0.00 250,000.00
168 Tiang Tongkat Kayu Belian Uk. 9/9 - 2,50 M Btg M_181.k 226,500.00 <10 8,700.00 235,200.00 0.00 0.00 235,200.00
169 Tiang Tongkat Kayu Belian Uk. 9/9 - 2,20 M Btg M_181.l 184,300.00 <10 7,700.00 192,000.00 0.00 0.00 192,000.00
170 Tiang Tongkat Kayu Belian Uk. 9/9 - 2,10 M Btg M_181.m 177,000.00 <10 7,400.00 184,400.00 0.00 0.00 184,400.00
171 Tiang Tongkat Kayu Belian Uk. 9/9 - 1,80 M Btg M_181.n 143,700.00 <10 6,300.00 150,000.00 0.00 0.00 150,000.00
172 Tiang Tongkat Kayu Belian Uk. 9/9 - 1,50 M Btg M_181.o 89,900.00 <10 5,300.00 95,200.00 0.00 0.00 95,200.00
173 Renglat Btg M_215 9,000.00 10 300.00 9,300.00 0.00 0.00 9,300.00
174 Laci Kayu Belian 5/10 - 80 cm Btg M_181.e 9,300.00 10 300.00 9,600.00 0.00 0.00 9,600.00
175 Laci Kayu Belian 9/9 - 80 cm Btg M_181.f 14,500.00 10 1,000.00 15,500.00 0.00 0.00 15,500.00
176 Laci Kayu Belian 4/8 - 60 cm Btg M_181.g 8,500.00 10 300.00 8,800.00 0.00 0.00 8,800.00
177 Alas Kayu Hutan Btg M_216 6,500.00 10 300.00 6,800.00 0.00 0.00 6,800.00
178 Alas Laci Kayu Belian 4/8-60 cm Btg M_216.a 8,500.00 10 300.00 8,800.00 0.00 0.00 8,800.00
179 Konsul Kayu Klas I Buah M_217 85,000.00 10 10,000.00 95,000.00 0.00 0.00 95,000.00
180 Triplek 3 mm Lbr M_218 60,000.00 10 300.00 60,300.00 0.00 0.00 60,300.00
181 Triplek 3 mm m2 M_218.a 20,155.87 10 100.78 20,256.65 0.00 0.00 20,256.65
182 Triplek 6 mm Lbr M_218.b 145,000.00 10 300.00 145,300.00 0.00 0.00 145,300.00
183 Triplek 9 mm Lbr M_218.c 240,000.00 10 3,000.00 243,000.00 0.00 0.00 243,000.00
184 Triplek 12 mm Lbr M_218.d 300,000.00 10 3,000.00 303,000.00 0.00 0.00 303,000.00
185 Plywood 4' x 8' x 4 mm Lbr M_218.e 76,000.00 10 3,000.00 79,000.00 0.00 0.00 79,000.00
HARGA DI SUM- JARAK ONGKOS JUMLAH PAJAK JUMLAH HARGA
BER/QUARY ANGKUT ANGKUT HARGA Profit 10 % GALIAN - C TERMASUK
NO MATERIAL UNIT KODE
(TANPA PAJAK) RATA-RATA PER UNIT TANPA PAJAK ( Rp ) ( 10 % ) PAJAK
( Rp ) ( Km ) ( Rp ) ( Rp ) ( Rp ) ( Rp )
186 Lem Kayu ltr M_219 40,000.00 10 500.00 40,500.00 0.00 0.00 40,500.00
187 Lem Kuning ltr M_219.a 47,000.00 10 500.00 47,500.00 0.00 0.00 47,500.00
188 List Kayu Profil m' M_220 12,000.00 10 500.00 12,500.00 0.00 0.00 12,500.00
HARGA DI SUM- JARAK ONGKOS JUMLAH PAJAK JUMLAH HARGA
BER/QUARY ANGKUT ANGKUT HARGA Profit 10 % GALIAN - C TERMASUK
NO MATERIAL UNIT KODE
(TANPA PAJAK) RATA-RATA PER UNIT TANPA PAJAK ( Rp ) ( 10 % ) PAJAK
( Rp ) ( Km ) ( Rp ) ( Rp ) ( Rp ) ( Rp )
189 Kayu Profil List Plafond m' M_221 6,500.00 10 500.00 7,000.00 0.00 0.00 7,000.00
190 Gypsum Profil List Plafond / Cornice m1 - 30,000.00 10 500.00 30,500.00 0.00 0.00 30,500.00
191 Gypsum Board Tebal 4 mm Lbr M_222 84,000.00 10 3,000.00 87,000.00 0.00 0.00 87,000.00
192 GRC Board Tebal 4 mm Lbr M_223 74,000.00 10 2,500.00 76,500.00 0.00 0.00 76,500.00
193 Aklirik Tebal 6 mm Uk. 120 x 240 cm Lbr - 929,500.00 10 2,500.00 932,000.00 0.00 0.00 932,000.00
194 Papan Profil /Lambriziring m3 - 4,004,000.00 10 500,000.00 4,504,000.00 0.00 0.00 4,504,000.00
195 Papan Lambrizing Tebal 9 mm Lbr - 163,000.00 10 3,000.00 166,000.00 0.00 0.00 166,000.00
196 Sungkai Tebal 3 mm, Uk. 120 x 240 cm m2 - 81,500.00 10 500.00 82,000.00 0.00 0.00 82,000.00
197 List Plafond Ukiran Kayu Kelas I Lebar 70 cm m1 - 550,500.00 10 500.00 551,000.00 0.00 0.00 551,000.00
BAHAN SANITASI
198 Talang Gantung & Talang Tegak m1 M_229 95,000.00 10 500.00 95,500.00 0.00 0.00 95,500.00
199 Pipa Suling Dia. 3/4" Buah M - 253 20,000.00 10 100.00 20,100.00 0.00 0.00 20,100.00
200 Pipa Galvanis Dia. 2" m' M - 253.a 155,000.00 > 100 1,500.00 156,500.00 0.00 0.00 156,500.00
201 Pipa Galvanis Dia. 4" m' M - 253.b 550,500.00 > 100 10,000.00 560,500.00 0.00 0.00 560,500.00
202 Pipa Galvanis Dia. 6" m' M - 253.c 829,500.00 > 100 10,000.00 839,500.00 0.00 0.00 839,500.00
203 Pipa Spiral Dia. 4 m' - 415,000.00 > 100 10,000.00 425,000.00 0.00 0.00 425,000.00
204 Kloset Duduk Buah M - 254 1,375,000.00 > 100 30,000.00 1,405,000.00 0.00 0.00 1,405,000.00
205 Kloset Jongkok Buah M - 254.a 180,000.00 10 15,000.00 195,000.00 0.00 0.00 195,000.00
206 Urinoir Buah M - 255 552,900.00 > 100 25,000.00 577,900.00 0.00 0.00 577,900.00
207 Wastafel Buah M - 256 650,000.00 > 100 20,000.00 670,000.00 0.00 0.00 670,000.00
208 Seal Tape Gypsum Buah M - 257 30,000.00 10 100.00 30,100.00 0.00 0.00 30,100.00
209 Floor Drain Buah M - 258 65,000.00 10 300.00 65,300.00 0.00 0.00 65,300.00
210 Kran Air Kualitas Biasa Buah M - 259 15,000.00 10 300.00 15,300.00 0.00 0.00 15,300.00
211 Kran Air Kualitas Baik Buah M - 259. a 40,000.00 10 300.00 40,300.00 0.00 0.00 40,300.00
212 Kran Air Stainless Ø 1/2" Buah M - 259. a 47,000.00 10 300.00 47,300.00 0.00 0.00 47,300.00
213 Penguras Bak Air Ø 3/4" Buah - 15,000.00 10 300.00 15,300.00 0.00 0.00 15,300.00
214 Seal Tape Kran Buah M - 260 3,000.00 10 100.00 3,100.00 0.00 0.00 3,100.00
215 Tempat Sabun Porcelain (Keramik) Terpasang Buah - 60,000.00 10 100.00 60,100.00 0.00 0.00 60,100.00
216 Centong Air Kualitas Biasa Buah - 15,000.00 10 100.00 15,100.00 0.00 0.00 15,100.00
217 Centong Air Kualitas Baik Buah - 25,000.00 10 100.00 25,100.00 0.00 0.00 25,100.00
218 Bak Air Fiber Glass 0,50 M3 Buah M - 261 1,200,000.00 > 100 50,000.00 1,250,000.00 0.00 0.00 1,250,000.00
219 Bak Air Fiber Glass 0,75 M3 Buah M - 261.a 1,500,000.00 > 100 50,000.00 1,550,000.00 0.00 0.00 1,550,000.00
220 Bak Air Fiber Glass 0,80 M3 Buah M - 261.b 1,600,000.00 > 100 50,000.00 1,650,000.00 0.00 0.00 1,650,000.00
221 Bak Air Fiber Glass 1 M3 Buah M - 261.c 2,000,000.00 > 100 50,000.00 2,050,000.00 0.00 0.00 2,050,000.00
222 Bak Air Fiber Glass 2 M3 Buah M - 261.d 2,650,000.00 > 100 75,000.00 2,725,000.00 0.00 0.00 2,725,000.00
223 Bak Air Fiber Glass 1,5 M3 Buah M - 261.e 3,350,000.00 > 100 100,000.00 3,450,000.00 0.00 0.00 3,450,000.00
224 Bak Air Fiber Glass 3 M3 Buah M - 261.f 4,150,000.00 > 100 100,000.00 4,250,000.00 0.00 0.00 4,250,000.00
225 Bak Air Fiber Glass 5 M3 Buah M - 261.g 5,000,000.00 > 100 100,000.00 5,100,000.00 0.00 0.00 5,100,000.00
226 Septic Tank Type ST24 0,75 M3 Buah - 3,410,000.00 > 100 100,000.00 3,510,000.00 0.00 0.00 3,510,000.00
227 Septic Tank Type ST46 1,30 M3 Buah - 4,510,000.00 > 100 100,000.00 4,610,000.00 0.00 0.00 4,610,000.00
228 Septic Tank Type ST68 1,55 M3 Buah - 5,390,000.00 > 100 100,000.00 5,490,000.00 0.00 0.00 5,490,000.00
BAHAN ATAP
229 Seng Gelombang BJLS 0,20 Lbr M_224 42,000.00 10 500.00 42,500.00 0.00 0.00 42,500.00
230 Seng Gelombang BJLS 0,20 m2 M_224.a 32,812.50 10 390.63 33,203.13 0.00 0.00 33,203.13
231 Seng Gelombang BJLS 0,30 Lbr M_224.b 65,000.00 10 500.00 65,500.00 0.00 0.00 65,500.00
232 Seng Gelombang BJLS 0,30 m2 M_224.c 50,781.25 10 390.63 51,171.88 0.00 0.00 51,171.88
233 Seng Gelombang Warna BJLS 0,25 Lbr M_224.d 55,000.00 10 500.00 55,500.00 0.00 0.00 55,500.00
234 Plat Aluminium Warna BJLS 0,25 Lbr - 65,000.00 10 500.00 65,500.00 0.00 0.00 65,500.00
235 Genteng Metal Type PRIMA 0,35 Lbr M_225 37,000.00 10 500.00 37,500.00 0.00 0.00 37,500.00
236 Genteng Metal Type ROYAL 0,35 Lbr M_225.a 37,000.00 10 500.00 37,500.00 0.00 0.00 37,500.00
237 Genteng Metal Type CLASSIC 0,35 Lbr M_225.b 37,000.00 10 500.00 37,500.00 0.00 0.00 37,500.00
238 Zincalume BJLS 0,3 Polos m2 M_225.d 95,000.00 10 500.00 95,500.00 0.00 0.00 95,500.00
239 Zincalume BJLS 0,3 Color m2 M_225.e 105,000.00 10 500.00 105,500.00 0.00 0.00 105,500.00
240 Zincalume BJLS 0,35 Polos m2 M_225.f 160,200.00 10 500.00 160,700.00 0.00 0.00 160,700.00
241 Zincalume BJLS 0,35 Color m2 M_225.g 174,500.00 10 500.00 175,000.00 0.00 0.00 175,000.00
242 Zincalume BJLS 0,4 Polos m2 M_225.h 165,000.00 10 500.00 165,500.00 0.00 0.00 165,500.00
243 Zincalume BJLS 0,4 Color m2 M_225.i 178,000.00 10 500.00 178,500.00 0.00 0.00 178,500.00
244 Seng Datar Colour BJLS 0,35 Lbr M_227 48,000.00 10 500.00 48,500.00 0.00 0.00 48,500.00
245 Seng Datar Polos BJLS 0,30 Lbr M_227.a 47,500.00 10 500.00 48,000.00 0.00 0.00 48,000.00
246 Zincalume Plat BJLS 0,3 Polos Lbr M_227.b 131,500.00 10 500.00 132,000.00 0.00 0.00 132,000.00
247 Zincalume Plat BJLS 0,3 Color Lbr M_227.c 145,800.00 10 500.00 146,300.00 0.00 0.00 146,300.00
248 Zincalume Plat BJLS 0,35 Polos Lbr M_227.d 160,200.00 10 500.00 160,700.00 0.00 0.00 160,700.00
249 Zincalume Plat BJLS 0,35 Color Lbr M_227.e 175,000.00 10 500.00 175,500.00 0.00 0.00 175,500.00
250 Nok / Bubungan Genteng Metal 1/2 Lingkaran 0,35 Buah M_228 48,000.00 10 500.00 48,500.00 0.00 0.00 48,500.00
251 Roof Light Fiberglass m2 - 362,000.00 10 500.00 362,500.00 0.00 0.00 362,500.00
252 Roof Light Polycarbonat m2 - 356,000.00 10 500.00 356,500.00 0.00 356,500.00
BAHAN KERAMIK
253 Keramik 10 x 20 cm Polos Buah M_240 1,750.00 10 100.00 1,850.00 0.00 0.00 1,850.00
254 Keramik 10 x 33 cm Polos Buah M_240.a 2,500.00 10 100.00 2,600.00 0.00 0.00 2,600.00
255 Keramik 20 x 20 cm Polos Buah M_240.b 2,800.00 10 100.00 2,900.00 0.00 0.00 2,900.00
256 Keramik 20 x 25 cm Polos Buah M_240.c 3,750.00 10 100.00 3,850.00 0.00 0.00 3,850.00
257 Keramik 30 x 30 cm Polos Buah M_240.d 6,250.00 10 100.00 6,350.00 0.00 0.00 6,350.00
258 Keramik 30 x 30 cm Artistik Buah M_240.e 6,300.00 10 100.00 6,400.00 0.00 0.00 6,400.00
HARGA DI SUM- JARAK ONGKOS JUMLAH PAJAK JUMLAH HARGA
BER/QUARY ANGKUT ANGKUT HARGA Profit 10 % GALIAN - C TERMASUK
NO MATERIAL UNIT KODE
(TANPA PAJAK) RATA-RATA PER UNIT TANPA PAJAK ( Rp ) ( 10 % ) PAJAK
( Rp ) ( Km ) ( Rp ) ( Rp ) ( Rp ) ( Rp )
259 Keramik 30 x 30 cm Unpolished Buah M_240.f 6,300.00 10 100.00 6,400.00 0.00 0.00 6,400.00
HARGA DI SUM- JARAK ONGKOS JUMLAH PAJAK JUMLAH HARGA
BER/QUARY ANGKUT ANGKUT HARGA Profit 10 % GALIAN - C TERMASUK
NO MATERIAL UNIT KODE
(TANPA PAJAK) RATA-RATA PER UNIT TANPA PAJAK ( Rp ) ( 10 % ) PAJAK
( Rp ) ( Km ) ( Rp ) ( Rp ) ( Rp ) ( Rp )
260 Keramik 40 x 40 cm Polos Buah M_240.g 15,800.00 10 100.00 15,900.00 0.00 0.00 15,900.00
261 Keramik 40 x 40 cm Anti Gores Buah M_240.h 20,000.00 10 100.00 20,100.00 0.00 0.00 20,100.00
262 Keramik 40 x 40 cm Unpolished Buah M_240.i 16,500.00 10 100.00 16,600.00 0.00 0.00 16,600.00
263 Keramik 60 x 60 cm Anti Gores (Polysed) Buah M_240.j 139,000.00 10 100.00 139,100.00 0.00 0.00 139,100.00
264 Keramik 10 x 10 cm Anti Gores (Polysed) Buah M_240.k 10,000.00 10 100.00 10,100.00 0.00 0.00 10,100.00
265 Keramik List Dinding 10 x 20 cm (Polysed) Buah M_240.l 6,000.00 10 100.00 6,100.00 0.00 0.00 6,100.00
266 Batu Granit m2 - 1,200,000.00 10 100.00 1,200,100.00 0.00 0.00 1,200,100.00
267 Batu Teraso m2 - 200,000.00 10 100.00 200,100.00 0.00 0.00 200,100.00
268 Batu Tempel Hitam (Batu Alam) m2 - 230,000.00 10 100.00 230,100.00 0.00 0.00 230,100.00
269 Batu Andesit m2 - 550,000.00 10 100.00 550,100.00 0.00 0.00 550,100.00
BAHAN KACA
270 Kaca Polos Tebal 3 mm m2 M_244 150,000.00 10 3,000.00 153,000.00 0.00 0.00 153,000.00
271 Kaca Polos Tebal 5 mm m2 M_244.a 170,000.00 10 3,000.00 173,000.00 0.00 0.00 173,000.00
272 Kaca Polos Tebal 8 mm m2 M_244.b 330,000.00 10 3,000.00 333,000.00 0.00 0.00 333,000.00
273 Kaca Polos Tebal 12 mm m2 M_244.c 412,000.00 10 3,000.00 415,000.00 0.00 0.00 415,000.00
274 Kaca Rayben Tebal 5 mm m2 M_244.d 200,000.00 10 3,000.00 203,000.00 0.00 0.00 203,000.00
275 Kaca Cermin Tebal 5 mm m2 M_244.e 275,000.00 10 3,000.00 278,000.00 0.00 0.00 278,000.00
276 Kaca Buram Tebal 5 mm m2 M_244.f 170,500.00 10 3,000.00 173,500.00 0.00 0.00 173,500.00
277 Kaca Setara Asahi Drak Blue Tebal 5 mm (Stopsol) m2 M_244.g 330,000.00 10 3,000.00 333,000.00 0.00 0.00 333,000.00
278 Kaca Setara Asahi Drak Blue Tebal 6 mm (Stopsol) m2 M_244.h 680,000.00 10 3,000.00 683,000.00 0.00 0.00 683,000.00
279 Kaca Setara Asahi Drak Blue Tebal 8 mm (Stopsol) m2 M_244.i 765,000.00 10 3,000.00 768,000.00 0.00 0.00 768,000.00
280 Kaca Setara Asahi Drak Blue Tebal 12 mm (Stopsol) m2 M_244.j 963,000.00 10 3,000.00 966,000.00 0.00 0.00 966,000.00
BAHAN LISTRIK
281 Saklar Ganda Kualitas Biasa Buah M - 262 10,000.00 10 50.00 10,050.00 0.00 0.00 10,050.00
282 Saklar Ganda Kualitas Baik Buah M - 262.a 25,000.00 10 50.00 25,050.00 0.00 0.00 25,050.00
283 Saklar Tunggal Kualitas Biasa Buah M - 262.b 9,000.00 10 50.00 9,050.00 0.00 0.00 9,050.00
284 Saklar Tunggal Kualitas Baik Set M - 262.c 20,000.00 10 50.00 20,050.00 0.00 0.00 20,050.00
285 Stop Kontak Kualitas Biasa Set M - 263 10,000.00 10 50.00 10,050.00 0.00 0.00 10,050.00
286 Stop Kontak Kualitas Baik Set M - 263.a 17,000.00 10 50.00 17,050.00 0.00 0.00 17,050.00
287 Sekring Box / MCB Set M - 264 120,000.00 10 100.00 120,100.00 0.00 0.00 120,100.00
288 Lampu Pijar 40 Watt Set M - 265.a 25,000.00 10 50.00 25,050.00 0.00 0.00 25,050.00
289 Lampu XL 20 Watt Set M - 265.b 45,000.00 10 50.00 45,050.00 0.00 0.00 45,050.00
290 Lampu TL 20 Watt Set M - 266.c 45,000.00 10 50.00 45,050.00 0.00 0.00 45,050.00
291 Lampu LED 5 Watt Buah M - 266.d 50,000.00 10 50.00 50,050.00 0.00 0.00 50,050.00
292 Lampu LED 5 Watt Buah M - 266.e 110,000.00 10 50.00 110,050.00 0.00 0.00 110,050.00
293 Lampu LED 5 Watt Buah M - 266.f 125,000.00 10 50.00 125,050.00 0.00 0.00 125,050.00
294 Instalasi Titik Lampu Titik - 225,000.00 10 500.00 225,500.00 0.00 0.00 225,500.00
BAHAN PENGUNCI & PENGGANTUNG
295 Engsel Pintu Buah M - 267 25,000.00 10 50.00 25,050.00 0.00 0.00 25,050.00
296 Engsel Jendela Buah M - 267.a 20,000.00 10 50.00 20,050.00 0.00 0.00 20,050.00
297 Engsel Pintu Pivot (Tanam) Kualitas Baik Terpasang Buah M - 267.a 975,300.00 10 50.00 975,350.00 0.00 0.00 975,350.00
298 Handle Pintu Buah M - 268 80,000.00 10 50.00 80,050.00 0.00 0.00 80,050.00
299 Handle Pintu Stainless Steel Panjang 30 cm Buah M - 268.a 150,000.00 10 50.00 150,050.00 0.00 0.00 150,050.00
300 Handle Jendela Buah M - 268.a 13,000.00 10 50.00 13,050.00 0.00 0.00 13,050.00
301 Slot Pintu Buah M - 269 12,000.00 10 50.00 12,050.00 0.00 0.00 12,050.00
302 Slot Pintu Tanam Buah - 105,000.00 10 50.00 105,050.00 0.00 0.00 105,050.00
303 Slot Jendela Buah M - 269.a 8,000.00 10 50.00 8,050.00 0.00 0.00 8,050.00
304 Kait Angin Buah M - 270 6,000.00 10 50.00 6,050.00 0.00 0.00 6,050.00
305 Kunci 2 Slaag Buah M - 271 198,000.00 10 500.00 198,500.00 0.00 0.00 198,500.00
306 Kunci Pintu Tanam Buah M - 271.a 160,000.00 10 500.00 160,500.00 0.00 0.00 160,500.00
307 Kunci Pintu Tanam 2 Slaag Buah M - 271.a 198,000.00 10 500.00 198,500.00 0.00 0.00 198,500.00
308 Pintu Folding Gate + Pemasangan m2 M - 272 350,000.00 > 100 240,000.00 590,000.00 0.00 0.00 590,000.00
309 Pintu Gulungan Besi (Rolling Door) m2 M - 272.a 350,000.00 > 100 240,000.00 590,000.00 0.00 0.00 590,000.00
310 Door Closer Buah M - 273 230,000.00 10 500.00 230,500.00 0.00 0.00 230,500.00
311 Engsel Sendok Buah - 15,000.00 10 500.00 15,500.00 0.00 0.00 15,500.00
BAHAN PERPIPAAN
312 Pipa Ø 1/2 " PVC Type AW m' M - 280.a 4,300.00 > 600 1,000.00 5,300.00 0.00 0.00 5,300.00
313 Pipa Ø 3/4 " PVC Type AW m' M - 281.a 6,650.00 > 600 1,500.00 8,150.00 0.00 0.00 8,150.00
314 Pipa Ø 1 " PVC Type AW m' M - 282.a 8,300.00 > 600 2,000.00 10,300.00 0.00 0.00 10,300.00
315 Pipa Ø 1,5 " PVC Type AW m' M - 283.a 14,550.00 > 600 2,500.00 17,050.00 0.00 0.00 17,050.00
316 Pipa Ø 2 " PVC Type AW m' M - 284.a 18,700.00 > 600 3,000.00 21,700.00 0.00 0.00 21,700.00
317 Pipa Ø 2,5 " PVC Type AW m' M - 285.a 26,900.00 > 600 4,000.00 30,900.00 0.00 0.00 30,900.00
318 Pipa Ø 3 " PVC Type AW m' M - 286.a 37,000.00 > 600 6,000.00 43,000.00 0.00 0.00 43,000.00
319 Pipa Ø 4 " PVC Type AW m' M - 287.a 61,050.00 > 600 10,000.00 71,050.00 0.00 0.00 71,050.00
320 Pipa Ø 6 " PVC Type AW m' M - 288.a 136,350.00 > 600 25,000.00 161,350.00 0.00 0.00 161,350.00
321 Pipa Ø 8 " PVC Type AW m' M - 289.a 233,500.00 > 600 45,000.00 278,500.00 0.00 0.00 278,500.00
322 Pipa Ø 1,5 " PVC Type D m' M - 290.b 8,700.00 > 600 2,500.00 11,200.00 0.00 0.00 11,200.00
323 Pipa Ø 2 " PVC Type D m' M - 291.b 11,800.00 > 600 3,000.00 14,800.00 0.00 0.00 14,800.00
324 Pipa Ø 2,5 " PVC Type D m' M - 292.b 16,050.00 > 600 4,000.00 20,050.00 0.00 0.00 20,050.00
325 Pipa Ø 3 " PVC Type D m' M - 293.b 20,600.00 > 600 6,000.00 26,600.00 0.00 0.00 26,600.00
326 Pipa Ø 4 " PVC Type D m' M - 294.b 32,200.00 > 600 10,000.00 42,200.00 0.00 0.00 42,200.00
327 Pipa Ø 6 " PVC Type D m' M - 295.b 86,300.00 > 600 25,000.00 111,300.00 0.00 0.00 111,300.00
328 Pipa Ø 8 " PVC Type D m' M - 296.b 120,950.00 > 600 45,000.00 165,950.00 0.00 0.00 165,950.00
DAFTAR ANALISA HARGA SATUAN PEKERJAAN
PEKERJAAN : -
LOKASI : -
TAHUN ANGGARAN : 2017

Pekerjaan Pengurukan Pasir dibawah Lantai ( PT.08 / M3 )

Harga Biaya
No. Uraian Satuan Satuan Kuantitas Satuan
( Rp ) ( Rp )
A TENAGA KERJA
1 Pekerja Hari/Orang 100,000.00 0.1920 19,200.00
2 Mandor Hari/Orang 150,000.00 0.0192 2,880.00
Jumlah 22,080.00
B BAHAN
1 Pasir Urug M3 172,000.00 1.2500 215,000.00
Jumlah 215,000.00
C Jumlah A + B 237,080.00
D Biaya Umum = % x C 0.00
E Harga Satuan = ( C + D ) 237,080.00

Pekerjaan Beton Tumbuk Camp 1 Pc : 3Psr : 5 (P.BB.01/M3)

Harga Biaya
No. Uraian Satuan Satuan Kuantitas Satuan
( Rp ) ( Rp )
A TENAGA KERJA
1 Tukang Batu Hari/Orang 125,000.00 0.2500 31,250.00
2 Kepala Tukang Batu Hari/Orang 150,000.00 0.0250 3,750.00
3 Pekerja Hari/Orang 100,000.00 1.6500 165,000.00
4 Mandor Hari/Orang 150,000.00 0.0800 12,000.00
Jumlah 212,000.00
B BAHAN
1 Pasir Ayak / Pasir Beton M3 187,000.00 0.5200 97,240.00
2 Semen Kg 2,540.00 218.0000 553,720.00
3 Kerikil Sungai M3 197,000.00 0.8700 171,390.00
Jumlah 822,350.00
C Jumlah A + B 1,034,350.00
D Biaya Umum = % x C 0.00
E Harga Satuan = ( C + D ) 1,034,350.00
REKAPITULASI ANALISA HARGA SATUAN

NO. PEKERJAAN SATUAN HARGA


1 Pekerjaan pengukuran dan Pemasangan Bouwplank (P.Ps.02/1M') PT.08 237,080.00
2 Pekerjaan Beton Tumbuk Camp 1 Pc : 3Psr : 5 (P.BB.01/M3) P.BB.01 1,034,350.00
3 Pekerjaan Lantai Keramik uk. 40 x 40 cm Polos (P.LD.09 / M2) P.LD.09 236,242.20
4 Pekerjaan Dinding Batako Uk. 15 x 30 x 7 ( P.Dnd.01/ M2) P.Dnd.01 131,749.00
5 Pekerjaan Plesteran dan Acian Tebal 1,5 cm Camp. 1Pc :2 Psr ( P.Pls.11 / M2) P.Pls.11 62,753.80
6 Pekerjaan Lantai Keramik uk. 20 x 20 cm Polos (P.LD.07 / M2) P.LD.07 225,267.20
7 Pekerjaan Beton Bertulang Camp 1 Pc : 2 Psr : 3 (P.BB.02 / M3) P.BB.02 1,512,990.00
8 Pekerjaan Pembesian Besi ulir atau Polos ( P.BB.03 / 1 Kg) P.BB.03 25,839.00
9 Pekerjaan Bekisting Untuk Sloof ( P.BB.05 / M2 ) P.BB.05 166,407.50
10 Pekerjaan Bekisting Untuk Kolom ( P.BB.06 / M2 ) P.BB.06 248,687.50
11 Pekerjaan Bekisting Untuk Kolom ( P.BB.06.a / M2 ) P.BB.06.a 193,500.00
12 Pekerjaan Bekisting Untuk Balok ( P.BB.07 / M2 ) P.BB.07 250,294.00
13 Pekerjaan Bekisting Untuk Lantai ( P.BB.08 / M2 ) P.BB.08 246,401.90
14 Pekerjaan Bekisting Untuk Lantai Cor Gantung ( P.BB.09 / M2 ) P.BB.09 37,565.60
15 Pekerjaan Bekisting Untuk Balok Ring ( P.BB.10 / M2 ) P.BB.10 15,997.40
16 Pekerjaan Lantai Keramik uk. 30 x 30 cm Polos (P.LD.08 / M2) P.LD.08 228,967.20
17 Pekerjaan Atap Seng Gelombang BJLS 0.20 (P.PA.12.a / M2) P.PA.12.a 55,107.13
18 Pekerjaan Bumbungan Atap seng Plat (P.PA.13 / 10 M') P.PA.13 56,165.60
19 Pekerjaan Atap Seng Metal (P.PA.16 / M2) P.PA.16 99,382.50
20 Pekerjaan Pintu Panel Kayu Klas I (PK. 15 / M2) PK.15 694,240.00
21 Pekerjaan Ventilasi Jalusi / Ram Kayu Klas II (PK.22 / m2) PK.22 210,241.50
22 Pekerjaan Kuda-kuda Konstruksi Kayu Klas II (PK.25/M3) PK.25 4,565,410.00
23 Pekerjaan gording + Blk Angin Kayu Klas II (PK.27 / M3) PK.27 5,578,650.00
24 Pekerjaan Reng dan Kasau Kayu Klas II (PK.30 / M2) PK.30 60,412.50
25 Pekerjaan Rangka Langit-langit 30 x 60 Kayu Klas II (PK.32 / M2) PK.32 116,166.50
26 Pekerjaan Lisplank Papan Kayu Klas I 2 x (2 x 18) (PK.37 / M1) PK.37 80,360.00
27 Pekerjaan Pemasangan Kunci 2 slaag ( P.KK.02 Bh ) P.PKK.02 264,250.00
28 Pekerjaan Pemasangan engsel Pintu ( P.KK.04 / Bh ) P.PKK.04 47,662.50
29 Pekerjaan Pemasangan engsel Jendela ( P.KK.05 / Bh ) P.PKK.05 42,662.50
30 Pekerjaan Pemasangan Kait angin ( P.KK.06 / Bh ) P.PKK.06 10,574.00
31 Pekerjaan Pemasangan Slot Pintu ( P.KK.07 / Bh ) P.PKK.07 19,587.50
32 Pekerjaan Pemasangan Slot Jendela ( P.KK.08 / Bh ) P.PKK.08 15,587.50
33 Pekerjaan Pemasangan Handle Jendela ( P.KK.09/ Bh ) P.PKK.09 20,587.50
34 Pekerjaan Pemasangan Handle Pintu ( P.KK.10/ Bh ) P.PKK.10 95,125.00
35 Pekerjaan Pemasangan kloset Jongkok (P.Snt.02 / Bh) P.Snt.02 529,610.00
36 Pekerjaan Pemasangan Wastefel (P.Snt.03 / Bh) P.Snt.03 849,110.00
37 Pekerjaan Pemasangan Pipa PVC Tipe AW Ø 4" (P.Snt.14 / M') P.Snt.14 83,064.00
38 Pekerjaan Memasang Kran air Ø 3/4" atau Ø 1/2" (P.Snt.15 / Bh) P.Snt.15 31,127.50
39 Pekerjaan Memasang Floor Drain (P.Snt.16 / Bh) P.Snt.16 74,502.50
40 Pekerjaan Langit - Langit GRC t = 4 mm + Rangka Kayu (P.Pf.01 / M2) P.Pf.01 169,680.50
41 Pekerjaan Pengecatan Bidang kayu Baru ( 1 Lapis plamir, 1 lapis cat dasar, 2 lapis cat penutup ) (P Ct. 04 / 1 M2) P.Ct.04 42,293.00
42 Pekerjaan Pengecatan Tembok Baru ( 1 Lapis plamur, 1 lapis cat dasar, 2 lapis cat penutup ) (P Ct. 11 / M2) P.Ct.11 22,003.00
BALOK SLOOF SELASAR
BALOK SLOOF VOLUME BETON
Lebar Tinggi PANJANG Volume Jlh / titik
20 x 35 0.20 0.25 52.32 2.616 2

Panjang Jumlah Pj Tulangan Jumlah


Tulangan Balok Balok + tekuk 5 d Tulangan
(meter) (buah) (meter) (buah)
Tlng. Memanjang 52.32 2 52.38 4

Tul Beugel D 8 mm - 15 cm 52.32 2 0.94 350


JUMLAH

BALOK SLOOF TERAS


BALOK SLOOF VOLUME BETON
Lebar Tinggi PANJANG Volume Jlh / titik
20 x 35 0.20 0.25 12 0.6 1

Panjang Jumlah Pj Tulangan Jumlah


Tulangan Balok Balok + tekuk 5 d Tulangan
(meter) (buah) (meter) (buah)
Tlng. Memanjang 12 1 12.06 4

Tul Beugel D 8 mm - 150 mm 12 1 0.94 81


JUMLAH

BALOK SLOOF WC
BALOK SLOOF VOLUME BETON
Lebar Tinggi PANJANG Volume Jlh / titik
20 x 35 0.20 0.25 13.52 0.676 1

Panjang Jumlah Pj Tulangan Jumlah


Tulangan Balok Balok + tekuk 5 d Tulangan
(meter) (buah) (meter) (buah)
Tlng. Memanjang 13.52 1 13.58 4

Tul Beugel D 8 mm - 15 cm 13.52 1 0.94 91


JUMLAH

RING BALOK SELASAR


BALOK SLOOF VOLUME BETON
Lebar Tinggi PANJANG Volume Jlh / titik
15 x 20 0.15 0.1 54 0.81 1

Panjang Jumlah Pj Tulangan Jumlah


Tulangan Balok Balok + tekuk 5 d Tulangan
Tulangan
(meter) (buah) (meter) (buah)
Tlng. Memanjang 14 1 14.06 4

Tul Beugel D 8 mm - 15 cm 14 1 0.54 94


JUMLAH

RING BALOK TERAS


BALOK SLOOF VOLUME BETON
Lebar Tinggi PANJANG Volume Jlh / titik
15 x 20 0.15 0.1 12 0.18 1

Panjang Jumlah Pj Tulangan Jumlah


Tulangan Balok Balok + tekuk 5 d Tulangan
(meter) (buah) (meter) (buah)
Tlng. Memanjang 12 1 12.06 4

Tul Beugel D 8 mm - 15 cm 12 1 0.54 81


JUMLAH

RING BALOK WC
BALOK SLOOF VOLUME BETON
Lebar Tinggi PANJANG Volume Jlh / titik
15 x 20 0.15 0.1 13.52 0.2028 1

Panjang Jumlah Pj Tulangan Jumlah


Tulangan Balok Balok + tekuk 5 d Tulangan
(meter) (buah) (meter) (buah)
Tlng. Memanjang 14 1 14.06 4

Tul Beugel D 8 mm - 15 cm 14 1 0.54 94


JUMLAH

KOLOM SELASAR
KOLOM VOLUME BETON
Lebar Tinggi PANJANG Volume Jlh / titik
15 x 15 0.15 0.15 4 0.09 14

Pj Tulangan
Panjang Jumlah
Jlh Balok + tekuk 5 d
Tulangan Balok Tulangan
+1,5M
(meter) (buah) (meter) (buah)
Tulangan Tegak 4 14 4.3 8

Tul Beugel D 8 mm - 150 mm 4 14 0.44 28


JUMLAH

KOLOM TERAS
KOLOM VOLUME BETON
Lebar Tinggi PANJANG Volume Jlh / titik
20 x 20 0.20 0.2 4 0.16 2

Pj Tulangan
Panjang Jumlah
Jlh Balok + tekuk 5 d
Tulangan Balok Tulangan
+1,5M
(meter) (buah) (meter) (buah)
Tulangan Tegak 4 2 4.3 8

Tul Beugel D 8 mm - 150 mm 4 2 0.64 28


JUMLAH

KOLOM WC
KOLOM VOLUME BETON
Lebar Tinggi PANJANG Volume Jlh / titik
15 x 15 0.15 0.15 4 0.09 4

Pj Tulangan
Panjang Jumlah
Jlh Balok + tekuk 5 d
Tulangan Balok Tulangan
+1,5M
(meter) (buah) (meter) (buah)
Tulangan Tegak 4 4 4.3 8

Tul Beugel D 8 mm - 150 mm 4 4 0.44 28


JUMLAH

KOLOM PRAKTIS WC
KOLOM VOLUME BETON
Lebar Tinggi PANJANG Volume Jlh / titik
10 x 10 0.10 0.1 4 0.04 6

Pj Tulangan
Panjang Jumlah
Jlh Balok + tekuk 5 d
Tulangan Balok Tulangan
+1,5M
(meter) (buah) (meter) (buah)
Tulangan Tegak 4 6 4.3 4
Tul Beugel D 8 mm - 200 mm 4 6 0.22 14
JUMLAH

PLAT DAK BETON SELASAR


VOLUME BETON
Lebar PANJANG Tebal Volume Jlh / titik T.volume
1.30 20.00 0.1 2.6 2 5.20 M3
Jumlah 5.20 M3
Jumlah
Diameter Panjang Jlh Dak
TULANGAN Tulangan
Tulangan
(meter) (Buah) (Buah)
Tulangan Atas 8 20.00 2 134.33
8 1.30 2 9.67
Tulangan Bawah 8 20.00 2 134.33
8 1.30 2 9.67
JUMLAH

PLAT DAK BETON TERAS


VOLUME BETON
Lebar PANJANG Tebal Volume Jlh / titik T.volume
0.30 12 0.1 0.36 1 0.36 M3

Jumlah 0.36 M3
Jumlah
Diameter Panjang Jlh Dak
TULANGAN Tulangan
Tulangan
(meter) (Buah) (Buah)
Tulangan Atas 8 12.00 1 81.00
8 0.30 1 3.00
Tulangan Bawah 8 12.00 1 81.00
8 0.30 1 3.00
JUMLAH

PLAT DAK BETON WC


VOLUME BETON
Lebar PANJANG Tebal Volume Jlh / titik T.volume
2.30 4.6 0.1 1.058 1 1.06 M3

Jumlah 1.06 M3
Jumlah
Diameter Panjang Jlh Dak
TULANGAN Tulangan
Tulangan
(meter) (Buah) (Buah)
Tulangan Atas 8 4.60 1 31.67
8 2.30 1 16.33
Tulangan Bawah 8 4.60 1 31.67
8 2.30 1 16.33
JUMLAH
LANTAI KERJA
VOLUME BETON
LEBAR PANJANG Tebal Volume Jlh / titik T.volume
20.00 10.00 0.05 10 1 10.00 M3
2.00 4.00 0.05 0.4 1 0.40 M3
4.00 4.00 0.05 0.8 1 0.80 M3
20.00 1.00 0.05 1 2 2.00 M3
46.00 19 JUMLAH 12.2

Jumlah
Diameter Panjang Jlh Dak
TULANGAN Tulangan
Tulangan
(meter) (Buah) (Buah)
Tulangan Bawah 8 19.00 1 127.67
8 46.00 1 307.67
JUMLAH
BETON VOLUME BEKESTING
T.volume Lebar Panjang Sisi Jlh / titik T.volume
0.25 2
5.232 M3 52.32 2 73.248 M2
0.20 1

Kebutuhan besi tulangan Berat Besi Tulangan


Diameter Tulangan Jumlah Panjang Besi
(batang) (Kg)

D 12 419.04 M' 38 Btg 372.01 Kg


Berat = 372.01 Kg
D 8 657.624 M' 60 Btg 259.47 Kg
Berat = 259.47 Kg

BETON VOLUME BEKESTING


T.volume Lebar Panjang Sisi Jlh / titik T.volume
0.25 2
0.6 M3 12 1 8.4 M2
0.20 1

Kebutuhan besi tulangan Berat Besi Tulangan


Diameter Tulangan Jumlah Panjang Besi
(batang) (Kg)

D 12 48.24 M' 4 Btg 42.83 Kg


Berat = 42.83 Kg
D 8 76.14 M' 7 Btg 30.04 Kg
Berat = 30.04 Kg

BETON VOLUME BEKESTING


T.volume Lebar Panjang Sisi Jlh / titik T.volume
0.25 2
0.676 M3 13.52 1 9.464 M2
0.20 1

Kebutuhan besi tulangan Berat Besi Tulangan


Diameter Tulangan Jumlah Panjang Besi
(batang) (Kg)

D 12 54.32 M' 5 Btg 48.22 Kg


Berat = 48.22 Kg
D 8 85.67 M' 8 Btg 33.80 Kg
Berat = 33.80 Kg

BETON VOLUME BEKESTING


T.volume Lebar Panjang Sisi Jlh / titik T.volume
0.1 2
0.81 M3 54 1 18.9 M2
0.15 1

Kebutuhan besi tulangan Berat Besi Tulangan


Diameter Tulangan Jumlah Panjang Besi
(batang) (Kg)
Kebutuhan besi tulangan Berat Besi Tulangan
Diameter Tulangan Jumlah Panjang Besi
(batang) (Kg)

D 12 56.24 M' 5 Btg 49.93 Kg


Berat = 49.93 Kg
D 8 50.94 M' 5 Btg 20.10 Kg
Berat = 20.10 Kg

BETON VOLUME BEKESTING


T.volume Lebar Panjang Sisi Jlh / titik T.volume
0.1 2
0.18 M3 12 1 4.2 M2
0.15 1

Kebutuhan besi tulangan Berat Besi Tulangan


Diameter Tulangan Jumlah Panjang Besi
(batang) (Kg)

D 12 48.24 M' 4 Btg 42.83 Kg


Berat = 42.83 Kg
D 8 43.74 M' 4 Btg 17.26 Kg
Berat = 17.26 Kg

BETON VOLUME BEKESTING


T.volume Lebar Panjang Sisi Jlh / titik T.volume
0.1 2
0.2028 M3 13.52 1 4.732 M2
0.15 1

Kebutuhan besi tulangan Berat Besi Tulangan


Diameter Tulangan Jumlah Panjang Besi
(batang) (Kg)

D 12 56.24 M' 5 Btg 49.93 Kg


Berat = 49.93 Kg
D 8 50.94 M' 5 Btg 20.10 Kg
Berat = 20.10 Kg

BETON VOLUME BEKESTING


T.volume Lebar Panjang Sisi Jlh / titik T.volume
0.15 2
1.26 M3 4 14 33.6 M2
0.15 2

Kebutuhan besi tulangan Berat Besi Tulangan


Diameter Tulangan Jumlah Panjang Besi
(batang) (Kg)

D 12 481.6 M' 44 Btg 427.55 Kg

Berat = 427.55 Kg
D 8 170 M' 15 Btg 67.24 Kg
Berat = 67.24 Kg
BETON VOLUME BEKESTING
T.volume Lebar Panjang Sisi Jlh / titik T.volume
0.2 2
0.32 M3 4 2 6.4 M2
0.20 2

Kebutuhan besi tulangan Berat Besi Tulangan


Diameter Tulangan Jumlah Panjang Besi
(batang) (Kg)

D 12 68.8 M' 6 Btg 61.08 Kg

Berat = 61.08 Kg
D 8 35 M' 3 Btg 13.97 Kg
Berat = 13.97 Kg

BETON VOLUME BEKESTING


T.volume Lebar Panjang Sisi Jlh / titik T.volume
0.15 2
0.36 M3 4 4 9.6 M2
0.15 2

Kebutuhan besi tulangan Berat Besi Tulangan


Diameter Tulangan Jumlah Panjang Besi
(batang) (Kg)

D 12 137.6 M' 13 Btg 122.16 Kg

Berat = 122.16 Kg
D 8 49 M' 4 Btg 19.21 Kg
Berat = 19.21 Kg

BETON VOLUME BEKESTING


T.volume Lebar Panjang Sisi Jlh / titik T.volume
0.1 1
0.24 M3 4 6 4.8 M2
0.10 1

Kebutuhan besi tulangan Berat Besi Tulangan


Diameter Tulangan Jumlah Panjang Besi
(batang) (Kg)

D 8 103.2 M' 9 Btg 40.72 Kg


D 6 18.92 M' 2 Btg 4.20 Kg
Berat = 44.92 Kg

VOLUME BAKESTING
Panjang Lebar Volume Jlh / titik T.volume
20.00 1.30 26 1 26 M2
0.13 2 0.26 M2
2.00 1 2 M2
Jumlah 28.26 M2
Pengurangan Balok Jumlah 3 M2
Jumlah 25.26 M2

JUMBLAH PANJANG Kebutuhan besi tulangan Berat Besi Tulangan


BESI (batang) (Kg)

268.67 M' 24.42 btg 53.00 Kg


19.33 M' 1.76 btg 3.81 Kg
268.67 M' 24.42 btg 53.00 Kg
19.33 M' 1.76 btg 3.81 Kg
Berat = 113.63 Kg

VOLUME BAKESTING
Panjang Lebar Volume Jlh / titik T.volume
12.00 1 12 1 12 M2
0.03 2 0.06 M2
1.20 1 1.2 M2
Jumlah 13.26 M2
Pengurangan Balok Jumlah 1.8 M2
Jumlah 11.46 M2

JUMBLAH PANJANG Kebutuhan besi tulangan Berat Besi Tulangan


BESI (batang) (Kg)

81.00 M' 7.36 btg 31.96 Kg


3.00 M' 0.27 btg 1.18 Kg
81.00 M' 7.36 btg 31.96 Kg
3.00 M' 0.27 btg 1.18 Kg
Berat = 66.29 Kg

VOLUME BAKESTING
Panjang Lebar Volume Jlh / titik T.volume
4.60 1 4.6 1 4.6 M2
0.23 2 0.46 M2
0.46 1 0.46 M2
Jumlah 5.52 M2
Pengurangan Balok Jumlah 0.69 M2
Jumlah 4.83 M2

JUMBLAH PANJANG Kebutuhan besi tulangan Berat Besi Tulangan


BESI (batang) (Kg)

31.67 M' 2.88 btg 12.49 Kg


16.33 M' 1.48 btg 6.44 Kg
31.67 M' 2.88 btg 12.49 Kg
16.33 M' 1.48 btg 6.44 Kg
Berat = 37.88 Kg
JUMLAH
TULANGA
BETON
N UTAMA

JUMLAH VOL BETON 12.2

JUMBLAH PANJANG Kebutuhan besi tulangan Berat Besi Tulangan


BESI (batang) (Kg)

127.67 M' 11.61 btg 50.37 Kg


307.67 M' 27.97 btg 121.39 Kg
Berat = 171.77 Kg 12.20 171.77
JUMLAH

BAKESTIN TULANGA TULANGA


BETON
G N UTAMA N BEUGEL

5.23 73.25 372.01 259.47

JUMLAH

BAKESTIN TULANGA TULANGA


BETON
G N UTAMA N BEUGEL

0.60 8.40 42.83 30.04

JUMLAH

BAKESTIN TULANGA TULANGA


BETON
G N UTAMA N BEUGEL

0.68 9.46 48.22 33.80

JUMLAH
BAKESTIN TULANGA TULANGA
BETON
G N UTAMA N BEUGEL
0.81 18.90 49.93 20.10

JUMLAH
BAKESTIN TULANGA TULANGA
BETON
G N UTAMA N BEUGEL

0.18 4.20 42.83 17.26

JUMLAH

BAKESTIN TULANGA TULANGA


BETON
G N UTAMA N BEUGEL

0.20 4.73 49.93 20.10

JUMLAH

BAKESTIN TULANGA TULANGA


BETON
G N UTAMA N BEUGEL

1.26 33.60 427.55 67.24


JUMLAH

BAKESTIN TULANGA TULANGA


BETON
G N UTAMA N BEUGEL

0.32 6.40 61.08 13.97

JUMLAH

BAKESTIN TULANGA TULANGA


BETON
G N UTAMA N BEUGEL

0.36 9.60 122.16 19.21

JUMLAH
BAKESTIN TULANGA
BETON
G N UTAMA

0.24 4.80 44.92

JUMLAH
BAKESTIN TULANGA
BETON
G N UTAMA
5.20 25.26 113.63

JUMLAH
BAKESTIN TULANGA
BETON
G N UTAMA

0.36 11.46 66.29

JUMLAH
BAKESTIN TULANGA
BETON
G N UTAMA

1.06 4.83 37.88


Banyak Kuda-kuda 2.00 2.00 4.000
1/2 Panjang Miring Kuda 2.00
Tinggi Tg Kuda 1.15
Panjang Nok 8.01
Panjang Bgn 4.00
Lebar Bangunan 4.00

kuda - kuda Sokong Tiang kuda Balok Tarik Balok Nok


0.08 0.11 0.02 0.08 0.08 0.36
Gording Ik. Angin
0.29 0.07 0.37
DAFTAR ANALISA HARGA SATUAN PEKERJAAN
PEKERJAAN : -
LOKASI : -
TAHUN ANGGARAN : 2017

Pekerjaan pengukuran dan Pemasangan Bouwplank (P.Ps.02/1M')

Harga Biaya
No. Uraian Satuan Satuan Kuantitas Satuan
( Rp ) ( Rp )
A TENAGA KERJA
1 Tukang Kayu Hari/Orang 125,000.00 0.1000 12,500.00
2 Kepala Tukang Kayu Hari/Orang 150,000.00 0.0100 1,500.00
3 Pekerja Hari/Orang 100,000.00 0.1000 10,000.00
4 Mandor Hari/Orang 150,000.00 0.0050 750.00
Jumlah 24,750.00
B BAHAN
1 Papan klas. III Campuran M3 1,966,500.00 0.0070 13,765.50
2 Cerucuk dia. 8 cm - 2 m Btg 7,500.00 1.0000 7,500.00
3 Paku Campuran Kg 25,200.00 0.0200 504.00
Jumlah 21,769.50
C Jumlah A + B 46,519.50
D Biaya Umum = % x C 0.00
E Harga Satuan = ( C + D ) 46,519.50

Pekerjaan Pembersihan Lapangan dan Perataan ( P.Ps.03 / 1 M2 )

Harga Biaya
No. Uraian Satuan Satuan Kuantitas Satuan
( Rp ) ( Rp )
A TENAGA KERJA
1 Pekerja Hari/Orang 100,000.00 0.1000 10,000.00
2 Mandor Hari/Orang 150,000.00 0.0050 750.00
Jumlah 10,750.00
B BAHAN
Jumlah
C Jumlah A + B 10,750.00
D Biaya Umum = % x C 0.00
E Harga Satuan = ( C + D ) 10,750.00

Pekerjaan Galian Tanah Biasa Sedalam 1 M' ( PT.01 / M3 )

Harga Biaya
No. Uraian Satuan Satuan Kuantitas Satuan
( Rp ) ( Rp )
A TENAGA KERJA
1 Pekerja Hari/Orang 100,000.00 0.4000 40,000.00
2 Mandor Hari/Orang 150,000.00 0.0400 6,000.00
Jumlah 46,000.00
B BAHAN
Jumlah
C Jumlah A + B 46,000.00
D Biaya Umum = % x C 0.00
E Harga Satuan = ( C + D ) 46,000.00

Pekerjaan Mengisi Bekas Galian Tanah ( PT.06 / M3 )

Harga Biaya
No. Uraian Satuan Satuan Kuantitas Satuan
( Rp ) ( Rp )
A TENAGA KERJA
1 Pekerja Hari/Orang 100,000.00 0.1920 19,200.00
2 Mandor Hari/Orang 150,000.00 0.0192 2,880.00
Jumlah 22,080.00
B BAHAN
Jumlah
C Jumlah A + B 22,080.00
D Biaya Umum = % x C 0.00
E Harga Satuan = ( C + D ) 22,080.00
Pekerjaan Balok Keef, Gelegar dll, Kayu Belian 9/9 (PK.01/M3)

Harga Biaya
No. Uraian Satuan Satuan Kuantitas Satuan
( Rp ) ( Rp )
A TENAGA KERJA
1 Tukang Kayu Hari/Orang 125,000.00 24.0000 3,000,000.00
2 Kepala Tukang Kayu Hari/Orang 150,000.00 2.4000 360,000.00
3 Pekerja Hari/Orang 100,000.00 8.0000 800,000.00
4 Mandor Hari/Orang 150,000.00 0.4000 60,000.00
Jumlah 4,220,000.00
B BAHAN
1 Kayu Belian (tak Ketam) M3 11,017,500.00 1.1000 12,119,250.00
2 Paku Belian / Beton Kg 30,200.00 3.0000 90,600.00
Jumlah 12,209,850.00
C Jumlah A + B 16,429,850.00
D Biaya Umum = % x C 0.00
E Harga Satuan = ( C + D ) 16,429,850.00

Pekerjaan Balok Keef, Gelegar dll, Kayu Klas I 5/9, 9/9 (PK.01.a/M3)

Harga Biaya
No. Uraian Satuan Satuan Kuantitas Satuan
( Rp ) ( Rp )
A TENAGA KERJA
1 Tukang Kayu Hari/Orang 125,000.00 24.0000 3,000,000.00
2 Kepala Tukang Kayu Hari/Orang 150,000.00 2.4000 360,000.00
3 Pekerja Hari/Orang 100,000.00 8.0000 800,000.00
4 Mandor Hari/Orang 150,000.00 0.4000 60,000.00
Jumlah 4,220,000.00
B BAHAN
1 Kayu Klas I (tak ketam) M3 3,137,500.00 1.1000 3,451,250.00
2 Paku Campuran Kg 25,200.00 3.0000 75,600.00
Jumlah 3,526,850.00
C Jumlah A + B 7,746,850.00
D Biaya Umum = % x C 0.00
E Harga Satuan = ( C + D ) 7,746,850.00

Pekerjaan Rangka Badan Kayu Belian 8/8 (PK.06 / M3)

Harga Biaya
No. Uraian Satuan Satuan Kuantitas Satuan
( Rp ) ( Rp )
A TENAGA KERJA
1 Tukang Kayu Hari/Orang 125,000.00 36.0000 4,500,000.00
2 Kepala Tukang Kayu Hari/Orang 150,000.00 3.6000 540,000.00
3 Pekerja Hari/Orang 100,000.00 12.0000 1,200,000.00
4 Mandor Hari/Orang 150,000.00 0.6000 90,000.00
Jumlah 6,330,000.00
B BAHAN
1 Kayu Belian 8/8 (ketam) M3 11,214,500.00 1.1000 12,335,950.00
2 Paku Belian / Beton Kg 30,200.00 6.0000 181,200.00
Jumlah 12,517,150.00
C Jumlah A + B 18,847,150.00
D Biaya Umum = % x C 0.00
E Harga Satuan = ( C + D ) 18,847,150.00

Pekerjaan Rangka Badan Kayu Klas I 8/8 (PK.08 / M3)

Harga Biaya
No. Uraian Satuan Satuan Kuantitas Satuan
( Rp ) ( Rp )
A TENAGA KERJA
1 Tukang Kayu Hari/Orang 125,000.00 24.0000 3,000,000.00
2 Kepala Tukang Kayu Hari/Orang 150,000.00 2.4000 360,000.00
3 Pekerja Hari/Orang 100,000.00 8.0000 800,000.00
4 Mandor Hari/Orang 150,000.00 0.4000 60,000.00
Jumlah 4,220,000.00
B BAHAN
1 Kayu Klas I 8/8 (ketam) M3 3,334,500.00 1.1000 3,667,950.00
2 Paku Campuran Kg 25,200.00 6.0000 151,200.00
Jumlah 3,819,150.00
C Jumlah A + B 8,039,150.00
D Biaya Umum = % x C 0.00
E Harga Satuan = ( C + D ) 8,039,150.00
Pekerjaan Rangka Badan Kayu Klas II 8/8 (PK.08.a / M3)

Harga Biaya
No. Uraian Satuan Satuan Kuantitas Satuan
( Rp ) ( Rp )
A TENAGA KERJA
1 Tukang Kayu Hari/Orang 125,000.00 24.0000 3,000,000.00
2 Kepala Tukang Kayu Hari/Orang 150,000.00 2.4000 360,000.00
3 Pekerja Hari/Orang 100,000.00 8.0000 800,000.00
4 Mandor Hari/Orang 150,000.00 0.4000 60,000.00
Jumlah 4,220,000.00
B BAHAN
1 Kayu Klas II 8/8 (ketam) M3 2,326,500.00 1.1000 2,559,150.00
2 Paku Campuran Kg 25,200.00 6.0000 151,200.00
Jumlah 2,710,350.00
C Jumlah A + B 6,930,350.00
D Biaya Umum = % x C 0.00
E Harga Satuan = ( C + D ) 6,930,350.00

Pekerjaan Melancip/Meruncing Tiang (PK.09/Btg)

Harga Biaya
No. Uraian Satuan Satuan Kuantitas Satuan
( Rp ) ( Rp )
A TENAGA KERJA
1 Tukang Kayu Hari/Orang 125,000.00 0.2500 31,250.00
2 Kepala Tukang kayu Hari/Orang 150,000.00 0.0250 3,750.00
3 Pekerja Hari/Orang 100,000.00 0.1000 10,000.00
4 Mandor Hari/Orang 150,000.00 0.0050 750.00
Jumlah 45,750.00
Upah Diambil 25 % 11,437.50
B BAHAN
Jumlah
C Jumlah A + B 11,437.50
D Biaya Umum = % x C 0.00
E Harga Satuan = ( C + D ) 11,437.50

Pekerjaan Membuat Pen dan Lubang (PK.10 / Psg)

Harga Biaya
No. Uraian Satuan Satuan Kuantitas Satuan
( Rp ) ( Rp )
A TENAGA KERJA
1 Tukang Kayu Hari/Orang 125,000.00 0.6000 75,000.00
2 Kepala Tukang kayu Hari/Orang 150,000.00 0.0600 9,000.00
Jumlah 84,000.00
Upah Diambil 60 % 50,400.00
B BAHAN
Jumlah
C Jumlah A + B 50,400.00
D Biaya Umum = % x C 0.00
E Harga Satuan = ( C + D ) 50,400.00

Pekerjaan Memancang Tiang Kedalam Tanah (PK.11 / M1)

Harga Biaya
No. Uraian Satuan Satuan Kuantitas Satuan
( Rp ) ( Rp )
A TENAGA KERJA
1 Tukang Kayu Hari/Orang 125,000.00 0.0400 5,000.00
2 Kepala Tukang Kayu Hari/Orang 150,000.00 0.0040 600.00
3 Pekerja Hari/Orang 100,000.00 1.8000 180,000.00
4 Mandor Hari/Orang 150,000.00 0.0430 6,450.00
Jumlah 192,050.00
Upah Diambil 25 % 48,012.50
B BAHAN
Jumlah
C Jumlah A + B 48,012.50
D Biaya Umum = % x C 0.00
E Harga Satuan = ( C + D ) 48,012.50
Pekerjaan Pintu Panel Kayu Belian (PK.14 / M2)

Harga Biaya
No. Uraian Satuan Satuan Kuantitas Satuan
( Rp ) ( Rp )
A TENAGA KERJA
1 Tukang Kayu Hari/Orang 125,000.00 2.5000 312,500.00
2 Kepala Tukang Kayu Hari/Orang 150,000.00 0.2500 37,500.00
3 Pekerja Hari/Orang 100,000.00 1.0000 100,000.00
4 Mandor Hari/Orang 150,000.00 0.0500 7,500.00
Jumlah 457,500.00
B BAHAN
1 Papan Kayu Belian (Ketam) M3 11,628,500.00 0.0400 465,140.00
Jumlah 465,140.00
C Jumlah A + B 922,640.00
D Biaya Umum = % x C 0.00
E Harga Satuan = ( C + D ) 922,640.00

Pekerjaan Pintu Panel Kayu Klas I (PK. 15 / M2)

Harga Biaya
No. Uraian Satuan Satuan Kuantitas Satuan
( Rp ) ( Rp )
A TENAGA KERJA
1 Tukang Kayu Hari/Orang 125,000.00 2.5000 312,500.00
2 Kepala Tukang Kayu Hari/Orang 150,000.00 0.2500 37,500.00
3 Pekerja Hari/Orang 100,000.00 1.0000 100,000.00
4 Mandor Hari/Orang 150,000.00 0.0500 7,500.00
Jumlah 457,500.00
B BAHAN
1 Papan Kayu Klas I (ketam) M3 5,918,500.00 0.0400 236,740.00
Jumlah 236,740.00
C Jumlah A + B 694,240.00
D Biaya Umum = % x C 0.00
E Harga Satuan = ( C + D ) 694,240.00

Pekerjaan Pintu atau Jendela Kaca (PK.17 / M2)

Harga Biaya
No. Uraian Satuan Satuan Kuantitas Satuan
( Rp ) ( Rp )
A TENAGA KERJA
1 Tukang Kayu Hari/Orang 125,000.00 2.0000 250,000.00
2 Kepala Tukang Kayu Hari/Orang 150,000.00 0.2000 30,000.00
3 Pekerja Hari/Orang 100,000.00 0.8000 80,000.00
4 Mandor Hari/Orang 150,000.00 0.0400 6,000.00
Jumlah 366,000.00
B BAHAN
1 Kayu Klas I (ketam) M3 3,334,500.00 0.0350 116,707.50
2 Kaca Bening 5 mm M2 173,000.00 0.7500 129,750.00
Jumlah 246,457.50
C Jumlah A + B 612,457.50
D Biaya Umum = % x C 0.00
E Harga Satuan = ( C + D ) 612,457.50

Pekerjaan Pintu Double Triplek Kayu Klas II (PK.18 / M2)

Harga Biaya
No. Uraian Satuan Satuan Kuantitas Satuan
( Rp ) ( Rp )
A TENAGA KERJA
1 Tukang Kayu Hari/Orang 125,000.00 1.5000 187,500.00
2 Kepala Tukang Kayu Hari/Orang 150,000.00 0.1500 22,500.00
3 Pekerja Hari/Orang 100,000.00 0.5000 50,000.00
4 Mandor Hari/Orang 150,000.00 0.0250 3,750.00
Jumlah diambil 25% 65,937.50
B BAHAN
1 Kayu Klas II M3 2,125,500.00 0.0039 8,289.45
2 Triplek M2 20,256.65 2.0000 40,513.30
3 Paku Triplek Kg 40,200.00 0.0500 2,010.00
Jumlah 50,812.75
C Jumlah A + B 116,750.25
D Biaya Umum = % x C 0.00
E Harga Satuan = ( C + D ) 116,750.25
Pekerjaan Ventilasi Jalusi / Ram Kayu Klas II (PK.22 / m2)

Harga Biaya
No. Uraian Satuan Satuan Kuantitas Satuan
( Rp ) ( Rp )
A TENAGA KERJA
1 Tukang Kayu Hari/Orang 125,000.00 0.8000 100,000.00
2 Kepala Tukang Kayu Hari/Orang 150,000.00 0.0800 12,000.00
3 Pekerja Hari/Orang 100,000.00 0.5000 50,000.00
4 Mandor Hari/Orang 150,000.00 0.0140 2,100.00
Jumlah 164,100.00
B BAHAN
1 Papan Kayu Klas II (ketam) M3 3,355,500.00 0.0130 43,621.50
2 Paku Campuran Kg 25,200.00 0.1000 2,520.00
Jumlah 46,141.50
C Jumlah A + B 210,241.50
D Biaya Umum = % x C 0.00
E Harga Satuan = ( C + D ) 210,241.50

Pekerjaan Kuda-kuda Konstruksi Kayu Klas II (PK.25/M3)

Harga Biaya
No. Uraian Satuan Satuan Kuantitas Satuan
( Rp ) ( Rp )
A TENAGA KERJA
1 Tukang Kayu Hari/Orang 125,000.00 12.0000 1,500,000.00
2 Kepala Tukang Kayu Hari/Orang 150,000.00 1.2000 180,000.00
3 Pekerja Hari/Orang 100,000.00 4.0000 400,000.00
4 Mandor Hari/Orang 150,000.00 0.2000 30,000.00
Jumlah 2,110,000.00
B BAHAN
1 Kayu Klas II (tak ketam) M3 2,125,500.00 1.1000 2,338,050.00
2 Baut Btg 8,100.00 12.0000 97,200.00
3 Paku Campuran Kg 25,200.00 0.8000 20,160.00
Jumlah 2,455,410.00
C Jumlah A + B 4,565,410.00
D Biaya Umum = % x C 0.00
E Harga Satuan = ( C + D ) 4,565,410.00

Pekerjaan gording + Blk Angin Kayu Klas II (PK.27 / M3)

Harga Biaya
No. Uraian Satuan Satuan Kuantitas Satuan
( Rp ) ( Rp )
A TENAGA KERJA
1 Tukang Kayu Hari/Orang 125,000.00 18.0000 2,250,000.00
2 Kepala Tukang Kayu Hari/Orang 150,000.00 1.8000 270,000.00
3 Pekerja Hari/Orang 100,000.00 6.0000 600,000.00
4 Mandor Hari/Orang 150,000.00 0.3000 45,000.00
Jumlah 3,165,000.00
B BAHAN
1 Kayu Klas II (tak ketam) M3 2,125,500.00 1.1000 2,338,050.00
2 Paku Campuran Kg 25,200.00 3.0000 75,600.00
Jumlah 2,413,650.00
C Jumlah A + B 5,578,650.00
D Biaya Umum = % x C 0.00
E Harga Satuan = ( C + D ) 5,578,650.00

Pekerjaan Reng dan Kasau Kayu Klas II (PK.30 / M2)

Harga Biaya
No. Uraian Satuan Satuan Kuantitas Satuan
( Rp ) ( Rp )
A TENAGA KERJA
1 Tukang Kayu Hari/Orang 125,000.00 0.100 12,500.00
2 Kepala Tukang Kayu Hari/Orang 150,000.00 0.010 1,500.00
3 Pekerja Hari/Orang 100,000.00 0.100 10,000.00
4 Mandor Hari/Orang 150,000.00 0.005 750.00
Jumlah 24,750.00
B BAHAN
1 Kayu Klas II (Tidak Ketam) M3 2,125,500.00 0.0150 31,882.50
2 Paku Campuran Kg 25,200.00 0.1500 3,780.00
Jumlah 35,662.50
C Jumlah A + B 60,412.50
D Biaya Umum = % x C 0.00
E Harga Satuan = ( C + D ) 60,412.50
Pekerjaan Rangka Langit-langit 30 x 60 Kayu Klas II (PK.32 / M2)

Harga Biaya
No. Uraian Satuan Satuan Kuantitas Satuan
( Rp ) ( Rp )
A TENAGA KERJA
1 Tukang Kayu Hari/Orang 125,000.00 0.3000 37,500.00
2 Kepala Tukang Kayu Hari/Orang 150,000.00 0.0300 4,500.00
3 Pekerja Hari/Orang 100,000.00 0.2000 20,000.00
4 Mandor Hari/Orang 150,000.00 0.0100 1,500.00
Jumlah 63,500.00
B BAHAN
1 Paku Campuran Kg 25,200.00 0.1500 3,780.00
2 Kayu Klas II (tak ketam) M3 2,125,500.00 0.0230 48,886.50
Jumlah 52,666.50
C Jumlah A + B 116,166.50
D Biaya Umum = % x C 0.00
E Harga Satuan = ( C + D ) 116,166.50

Pekerjaan Lisplank Papan Kayu Klas I 2 x (2 x 18) (PK.37 / M1)

Harga Biaya
No. Uraian Satuan Satuan Kuantitas Satuan
( Rp ) ( Rp )
A TENAGA KERJA
1 Tukang Kayu Hari/Orang 125,000.00 0.1000 12,500.00
2 Kepala Tukang Kayu Hari/Orang 150,000.00 0.0100 1,500.00
3 Pekerja Hari/Orang 100,000.00 0.1000 10,000.00
4 Mandor Hari/Orang 150,000.00 0.0500 7,500.00
Jumlah 31,500.00
B BAHAN
1 Papan Klas I (ketam) M3 5,918,500.00 0.0080 47,348.00
2 Paku Campuran Kg 25,200.00 0.0600 1,512.00
Jumlah 48,860.00
C Jumlah A + B 80,360.00
D Biaya Umum = % x C 0.00
E Harga Satuan = ( C + D ) 80,360.00

Pekerjaan Lisplank Papan Kayu Klas II 2 x (2 x 18) (PK.37.a / M1)

Harga Biaya
No. Uraian Satuan Satuan Kuantitas Satuan
( Rp ) ( Rp )
A TENAGA KERJA
1 Tukang Kayu Hari/Orang 125,000.00 0.1000 12,500.00
2 Kepala Tukang Kayu Hari/Orang 150,000.00 0.0100 1,500.00
3 Pekerja Hari/Orang 100,000.00 0.1000 10,000.00
4 Mandor Hari/Orang 150,000.00 0.0500 7,500.00
Jumlah 31,500.00
B BAHAN
1 Papan Kayu Klas II (ketam) M3 3,355,500.00 0.0080 26,844.00
2 Paku Campuran Kg 25,200.00 0.0600 1,512.00
Jumlah 28,356.00
C Jumlah A + B 59,856.00
D Biaya Umum = % x C 0.00
E Harga Satuan = ( C + D ) 59,856.00

Pekerjaan Lantai Papan Kayu Klas I (PK.38/ M2)

Harga Biaya
No. Uraian Satuan Satuan Kuantitas Satuan
( Rp ) ( Rp )
A TENAGA KERJA
1 Tukang Kayu Hari/Orang 125,000.00 1.8000 225,000.00
2 Kepala Tukang Kayu Hari/Orang 150,000.00 0.1800 27,000.00
3 Pekerja Hari/Orang 100,000.00 0.6000 60,000.00
4 Mandor Hari/Orang 150,000.00 0.0300 4,500.00
Jumlah 316,500.00
Upah diambil 50 % 158,250.00
B BAHAN
1 Papan Kayu Klas I (ketam) M3 5,918,500.00 0.0240 142,044.00
2 Paku Campuran Kg 25,200.00 0.2000 5,040.00
Jumlah 147,084.00
C Jumlah A + B 305,334.00
D Biaya Umum = % x C 0.00
E Harga Satuan = ( C + D ) 305,334.00
Pekerjaan Lantai Papan Kayu Klas II (PK.38.a/ M2)

Harga Biaya
No. Uraian Satuan Satuan Kuantitas Satuan
( Rp ) ( Rp )
A TENAGA KERJA
1 Tukang Kayu Hari/Orang 125,000.00 1.8000 225,000.00
2 Kepala Tukang Kayu Hari/Orang 150,000.00 0.1800 27,000.00
3 Pekerja Hari/Orang 100,000.00 0.6000 60,000.00
4 Mandor Hari/Orang 150,000.00 0.0300 4,500.00
Jumlah 316,500.00
Upah diambil 50 % 158,250.00
B BAHAN
1 Papan Kayu Klas II (ketam) M3 3,355,500.00 0.0240 80,532.00
2 Paku Campuran Kg 25,200.00 0.2000 5,040.00
Jumlah 85,572.00
C Jumlah A + B 243,822.00
D Biaya Umum = % x C 0.00
E Harga Satuan = ( C + D ) 243,822.00

Pekerjaan Atap Seng Gelombang BJLS 0.20 (P.PA.12.a / M2)

Harga Biaya
No. Uraian Satuan Satuan Kuantitas Satuan
( Rp ) ( Rp )
A TENAGA KERJA
1 Tukang Seng Hari/Orang 125,000.00 0.0600 7,500.00
2 Kepala Tukang Hari/Orang 150,000.00 0.0060 900.00
3 Pekerja Hari/Orang 100,000.00 0.1200 12,000.00
4 Mandor Hari/Orang 150,000.00 0.0060 900.00
Jumlah 21,300.00
B BAHAN
1 Seng Gelombang BJLS 0.20 M2 33,203.13 1.0000 33,203.13
2 Paku Seng Kg 30,200.00 0.0200 604.00
Jumlah 33,807.13
C Jumlah A + B 55,107.13
D Biaya Umum = % x C 0.00
E Harga Satuan = ( C + D ) 55,107.13

Pekerjaan Atap Seng Metal (P.PA.16 / M2)

Harga Biaya
No. Uraian Satuan Satuan Kuantitas Satuan
( Rp ) ( Rp )
A TENAGA KERJA
1 Tukang Seng Hari/Orang 125,000.00 0.1000 12,500.00
2 Kepala Tukang Hari/Orang 150,000.00 0.0100 1,500.00
3 Pekerja Hari/Orang 100,000.00 0.2000 20,000.00
4 Mandor Hari/Orang 150,000.00 0.0100 1,500.00
Jumlah 35,500.00
B BAHAN
1 Seng Metal Lembar 37,500.00 1.6230 60,862.50
2 Paku Seng Kg 30,200.00 0.1000 3,020.00
Jumlah 63,882.50
C Jumlah A + B 99,382.50
D Biaya Umum = % x C 0.00
E Harga Satuan = ( C + D ) 99,382.50

Pekerjaan Bumbungan Atap seng Plat (P.PA.13 / 10 M')

Harga Biaya
No. Uraian Satuan Satuan Kuantitas Satuan
( Rp ) ( Rp )
A TENAGA KERJA
1 Tukang Seng Hari/Orang 125,000.00 0.2500 31,250.00
2 Kepala Tukang Hari/Orang 150,000.00 0.0250 3,750.00
3 Pekerja Hari/Orang 100,000.00 0.2500 25,000.00
Jumlah 60,000.00
B BAHAN
1 Seng Plat BJLS 0.30 Lembar 48,000.00 6.0000 288,000.00
2 Paku Seng Kg 30,200.00 0.1000 3,020.00
3 Papan Klas II ( Tidak Ketam ) M3 2,925,500.00 0.0720 210,636.00
Jumlah 501,656.00
C Jumlah A + B 561,656.00
D Biaya Umum = % x C 0.00
E Harga Satuan = ( C + D ) 561,656.00
Untuk 1 M' 56,165.60
Pekerjaan Langit - Langit GRC t = 4 mm + Rangka Kayu (P.Pf.01 / M2)

Harga Biaya
No. Uraian Satuan Satuan Kuantitas Satuan
( Rp ) ( Rp )
A TENAGA KERJA
1 Tukang Hari/Orang 125,000.00 0.4000 50,000.00
2 Kepala Tukang Hari/Orang 150,000.00 0.0400 6,000.00
3 Pekerja Hari/Orang 100,000.00 0.2700 27,000.00
4 Mandor Hari/Orang 150,000.00 0.0135 2,025.00
Jumlah 85,025.00
B BAHAN
1 GRC Board Lbr 76,500.00 0.3900 29,835.00
2 Paku GRC Kg 40,200.00 0.1100 4,422.00
3 Kayu Klas II (tidak ketam) M3 2,125,500.00 0.0230 48,886.50
4 Paku Campuran Kg 25,200.00 0.0600 1,512.00
Jumlah 84,655.50
C Jumlah A + B 169,680.50
D Biaya Umum = % x C 0.00
E Harga Satuan = ( C + D ) 169,680.50

Pekerjaan Plafond Reng Lat Kayu Kls II (P.Pf.03 / M2)

Harga Biaya
No. Uraian Satuan Satuan Kuantitas Satuan
( Rp ) ( Rp )
A TENAGA KERJA
1 Tukang Kayu Hari/Orang 125,000.00 0.8000 100,000.00
2 Kepala Tukang Hari/Orang 150,000.00 0.0800 12,000.00
3 Pekerja Hari/Orang 100,000.00 0.2800 28,000.00
4 Mandor Hari/Orang 150,000.00 0.0140 2,100.00
Jumlah 142,100.00
B BAHAN
1 Kayu Kls II (tdk ketam) M3 2,125,500.00 0.0080 17,004.00
2 Papan Kayu Kls II (ketam) Kg 3,355,500.00 0.0090 30,199.50
3 Paku Campur Kg 25,200.00 0.0100 252.00
Jumlah 47,455.50
C Jumlah A + B 189,555.50
D Biaya Umum = % x C 0.00
E Harga Satuan = ( C + D ) 189,555.50

Pekerjaan mengikis / Mengorek Permukaan Cat Tembok Lama (P Ct.01 / 1 M2)

Harga Biaya
No. Uraian Satuan Satuan Kuantitas Satuan
( Rp ) ( Rp )
A TENAGA KERJA
3 Pekerja Hari/Orang 100,000.00 0.1500 15,000.00
4 Mandor Hari/Orang 150,000.00 0.0025 375.00
Jumlah 15,375.00
B BAHAN
1 Soda Api Kg 41,100.00 1.0000 41,100.00
Jumlah 41,100.00
C Jumlah A + B 56,475.00
D Biaya Umum = % x C 0.00
E Harga Satuan = ( C + D ) 56,475.00

Pekerjaan Pengecatan bidang Kayu Lama (P Ct.03 / 1 M2)

Harga Biaya
No. Uraian Satuan Satuan Kuantitas Satuan
( Rp ) ( Rp )
A TENAGA KERJA
1 Tukang Cat Hari/Orang 125,000.00 0.0750 9,375.00
2 Kepala Tukang Cat Hari/Orang 150,000.00 0.0075 1,125.00
3 Pekerja Hari/Orang 100,000.00 0.0700 7,000.00
4 Mandor Hari/Orang 150,000.00 0.0025 375.00
Jumlah 17,875.00
B BAHAN
1 Plamur Kg 35,100.00 0.1500 5,265.00
2 Cat Dasar Kg 45,600.00 0.0075 342.00
3 Cat Penutup Cat Kilat Kg 55,600.00 0.0025 139.00
Jumlah 5,746.00
C Jumlah A + B 23,621.00
D Biaya Umum = % x C 0.00
E Harga Satuan = ( C + D ) 23,621.00
Pekerjaan Pengecatan Bidang kayu Baru ( 1 Lapis plamir, 1 lapis cat dasar, 2 lapis cat penutup ) (P Ct. 04 / 1 M2)

Harga Biaya
No. Uraian Satuan Satuan Kuantitas Satuan
( Rp ) ( Rp )
A TENAGA KERJA
1 Tukang Cat Hari/Orang 125,000.00 0.0090 1,125.00
2 Kepala Tukang Cat Hari/Orang 150,000.00 0.0060 900.00
3 Pekerja Hari/Orang 100,000.00 0.0700 7,000.00
4 Mandor Hari/Orang 150,000.00 0.0025 375.00
Jumlah 9,400.00
B BAHAN
1 Cat Meni Kg 27,100.00 0.2000 5,420.00
2 Plamur Kg 35,100.00 0.1500 5,265.00
3 Cat dasar Kg 45,600.00 0.1700 7,752.00
4 Cat Penutup / Kilat 2 Kali Kg 55,600.00 0.2600 14,456.00
Jumlah 32,893.00
C Jumlah A + B 42,293.00
D Biaya Umum = % x C 0.00
E Harga Satuan = ( C + D ) 42,293.00

Pekerjaan Pengecatan Bidang kayu Baru ( 1 Lapis plamir, 1 lapis cat dasar, 3 lapis cat penutup ) (P Ct. 05 / 1 M2)

Harga Biaya
No. Uraian Satuan Satuan Kuantitas Satuan
( Rp ) ( Rp )
A TENAGA KERJA
1 Tukang Cat Hari/Orang 125,000.00 0.1050 13,125.00
2 Kepala Tukang Cat Hari/Orang 150,000.00 0.0040 600.00
3 Pekerja Hari/Orang 100,000.00 0.0700 7,000.00
4 Mandor Hari/Orang 150,000.00 0.0025 375.00
Jumlah 21,100.00
B BAHAN
1 Cat Meni Kg 27,100.00 0.2000 5,420.00
2 Plamur Kg 35,100.00 0.1500 5,265.00
3 Cat dasar Kg 45,600.00 0.1700 7,752.00
4 Cat Penutup / Kilat 3 Kali Kg 55,600.00 0.3500 19,460.00
Jumlah 37,897.00
C Jumlah A + B 58,997.00
D Biaya Umum = % x C 0.00
E Harga Satuan = ( C + D ) 58,997.00

Pekerjaan Pengecatan Atap Seng ( 1 lapis cat penutup ) (P Ct. 04.a / 1 M2)

Harga Biaya
No. Uraian Satuan Satuan Kuantitas Satuan
( Rp ) ( Rp )
A TENAGA KERJA
1 Tukang Cat Hari/Orang 125,000.00 0.0090 1,125.00
2 Kepala Tukang Cat Hari/Orang 150,000.00 0.0060 900.00
3 Pekerja Hari/Orang 100,000.00 0.0700 7,000.00
4 Mandor Hari/Orang 150,000.00 0.0025 375.00
Jumlah 9,400.00
Upah di ambil 50% 4,700.00
B BAHAN
4 Cat Seng / 1 Kali Kg 55,600.00 0.1300 7,228.00
Jumlah 7,228.00
C Jumlah A + B 11,928.00
D Biaya Umum = % x C 0.00
E Harga Satuan = ( C + D ) 11,928.00

Pekerjaan Pengecatan Tembok Baru ( 1 Lapis plamur, 1 lapis cat dasar, 2 lapis cat penutup ) (P Ct. 11 / M2)

Harga Biaya
No. Uraian Satuan Satuan Kuantitas Satuan
( Rp ) ( Rp )
A TENAGA KERJA
1 Tukang Cat Hari/Orang 125,000.00 0.0630 7,875.00
2 Kepala Tukang Cat Hari/Orang 150,000.00 0.0063 945.00
3 Pekerja Hari/Orang 100,000.00 0.0200 2,000.00
4 Mandor Hari/Orang 150,000.00 0.0025 375.00
Jumlah 11,195.00
B BAHAN
1 Cat Meni Kg 27,100.00 0.1000 2,710.00
2 Car dasar Kg 45,600.00 0.1200 5,472.00
3 Cat tembok Kg 10,100.00 0.2600 2,626.00
Jumlah 10,808.00
C Jumlah A + B 22,003.00
D Biaya Umum = % x C 0.00
E Harga Satuan = ( C + D ) 22,003.00
Pekerjaan Pengecatan Tembok Lama (1 lapis plamir, 2 lapis cat penutup) (P.Ct.12)

Harga Biaya
No. Uraian Satuan Satuan Kuantitas Satuan
( Rp ) ( Rp )
A TENAGA KERJA
1 Tukang Cat Hari/Orang 125,000.00 0.0420 5,250.00
2 Kepala Tukang Cat Hari/Orang 150,000.00 0.0042 630.00
3 Pekerja Hari/Orang 100,000.00 0.0280 2,800.00
4 Mandor Hari/Orang 150,000.00 0.0025 375.00
Jumlah 9,055.00
B BAHAN
2 Car dasar Kg 45,600.00 0.1200 5,472.00
3 Cat tembok Kg 10,100.00 0.1800 1,818.00
Jumlah 7,290.00
C Jumlah A + B 16,345.00
D Biaya Umum = % x C 0.00
E Harga Satuan = ( C + D ) 16,345.00

Pekerjaan Beton Tumbuk Camp 1 Pc : 3Psr : 5 Kr (P.BB.01/M3)

Harga Biaya
No. Uraian Satuan Satuan Kuantitas Satuan
( Rp ) ( Rp )
A TENAGA KERJA
1 Tukang Batu Hari/Orang 125,000.00 0.2500 31,250.00
2 Kepala Tukang Batu Hari/Orang 150,000.00 0.0250 3,750.00
3 Pekerja Hari/Orang 100,000.00 1.6500 165,000.00
4 Mandor Hari/Orang 150,000.00 0.0800 12,000.00
Jumlah 212,000.00
B BAHAN
1 Pasir Ayak / Pasir Beton M3 187,000.00 0.5200 97,240.00
2 Semen Kg 2,540.00 218.0000 553,720.00
3 Kerikil sungai M3 197,000.00 0.8700 171,390.00
Jumlah 822,350.00
C Jumlah A + B 1,034,350.00
D Biaya Umum = % x C 0.00
E Harga Satuan = ( C + D ) 1,034,350.00

Pekerjaan Beton Bertulang Camp 1 Pc : 2 Psr : 3 Kr (P.BB.02 / M3)

Harga Biaya
No. Uraian Satuan Satuan Kuantitas Satuan
( Rp ) ( Rp )
A TENAGA KERJA
1 Tukang Batu Hari/Orang 125,000.00 0.3500 43,750.00
2 Kepala Tukang Batu Hari/Orang 150,000.00 0.0350 5,250.00
3 Pekerja Hari/Orang 100,000.00 2.0000 200,000.00
4 Mandor Hari/Orang 150,000.00 1.0000 150,000.00
Jumlah 399,000.00
B BAHAN
1 Pasir M3 187,000.00 0.5400 100,980.00
2 Semen Kg 2,540.00 336.0000 853,440.00
3 Batu Belah 1,5 - 1 cm / Krikil M3 197,000.00 0.8100 159,570.00
Jumlah 1,113,990.00
C Jumlah A + B 1,512,990.00
D Biaya Umum = % x C 0.00
E Harga Satuan = ( C + D ) 1,512,990.00

Pekerjaan Pembesian Besi ulir atau Polos ( P.BB.03 / 1 Kg)

Harga Biaya
No. Uraian Satuan Satuan Kuantitas Satuan
( Rp ) ( Rp )
A TENAGA KERJA
1 Tukang Besi Hari/Orang 125,000.00 0.0070 875.00
2 Kepala Tukang Hari/Orang 150,000.00 0.0007 105.00
3 Pekerja Hari/Orang 100,000.00 0.0070 700.00
4 Mandor Hari/Orang 150,000.00 0.0003 45.00
Jumlah 1,725.00
B BAHAN
1 Besi Beton Kg 22,600.00 1.0500 23,730.00
2 Kawat Beton / Bendrat Kg 25,600.00 0.0150 384.00
Jumlah 24,114.00
C Jumlah A + B 25,839.00
D Biaya Umum = % x C 0.00
E Harga Satuan = ( C + D ) 25,839.00
Pekerjaan Bekisting Untuk Lantai Cor Gantung ( P.BB.09 / M2 )

Harga Biaya
No. Uraian Satuan Satuan Kuantitas Satuan
( Rp ) ( Rp )
A TENAGA KERJA
1 Tukang Kayu Hari/Orang 125,000.00 0.3300 41,250.00
2 Kepala Tukang Kayu Hari/Orang 150,000.00 0.0330 4,950.00
3 Pekerja Hari/Orang 100,000.00 0.3200 32,000.00
4 Mandor Hari/Orang 150,000.00 0.0060 900.00
Upah 25 % 19,775.00
B BAHAN
1 Kayu campuran M3 2,021,500.00 0.0048 9,703.20
2 Paku campuran Kg 25,200.00 0.0400 1,008.00
3 Papan Kayu Klas III / Papan Mal M3 1,966,500.00 0.0036 7,079.40
Jumlah 17,790.60
C Jumlah A + B 37,565.60
D Biaya Umum = % x C 0.00
E Harga Satuan = ( C + D ) 37,565.60

Pekerjaan Plesteran dan Acian Tebal 1,5 cm Camp. 1Pc :2 Psr ( P.Pls.11 / M2)

Harga Biaya
No. Uraian Satuan Satuan Kuantitas Satuan
( Rp ) ( Rp )
A TENAGA KERJA
1 Tukang Hari/Orang 125,000.00 0.1650 20,625.00
2 Kepala Tukang Hari/Orang 150,000.00 0.0165 2,475.00
3 Pekerja Hari/Orang 100,000.00 0.3300 33,000.00
4 Mandor Hari/Orang 150,000.00 0.0165 2,475.00
Jumlah 58,575.00
B BAHAN
1 Portland Cement Kg 2,540.00 0.3200 812.80
2 Pasir Beton M3 187,000.00 0.0180 3,366.00
Jumlah 4,178.80
C Jumlah A + B 62,753.80
D Biaya Umum = % x C 0.00
E Harga Satuan = ( C + D ) 62,753.80

Pekerjaan Dinding Simpai ,Camp. 1 Pc : 3 Psr ( P.Dnd.02/ M2)

Harga Biaya
No. Uraian Satuan Satuan Kuantitas Satuan
( Rp ) ( Rp )
A TENAGA KERJA
1 Tukang Batu Hari/Orang 125,000.00 0.4000 50,000.00
2 Kepala Tukang Batu Hari/Orang 150,000.00 0.0400 6,000.00
3 Pekerja Hari/Orang 100,000.00 0.8000 80,000.00
4 Mandor Hari/Orang 150,000.00 0.0400 6,000.00
Jumlah 142,000.00
B BAHAN
1 Portland Cement Zak 127,000.00 0.2610 33,147.00
2 Pasir Beton M3 187,000.00 0.0390 7,293.00
3 Kawat Simpai Kg 17,200.00 0.6500 11,180.00
4 Papan Mal M3 1,966,500.00 0.0100 19,665.00
5 Paku Campuran Kg 25,200.00 0.1000 2,520.00
Jumlah 73,805.00
C Jumlah A + B 215,805.00
D Biaya Umum = % x C 0.00
E Harga Satuan = ( C + D ) 215,805.00

Pekerjaan Lantai Keramik uk. 20 x 20 cm Polos (P.LD.07 / M2)

Harga Biaya
No. Uraian Satuan Satuan Kuantitas Satuan
( Rp ) ( Rp )
A TENAGA KERJA
1 Tukang Semen Hari/Orang 125,000.00 0.3500 43,750.00
2 Kepala Tukang Semen Hari/Orang 150,000.00 0.0350 5,250.00
3 Pekerja Hari/Orang 100,000.00 0.6200 62,000.00
4 Mandor Hari/Orang 150,000.00 0.0300 4,500.00
Jumlah 115,500.00
B BAHAN
1 Keramik 20 x 20 Bh 2,900.00 25.0000 72,500.00
2 Portland cement Kg 2,540.00 11.3800 28,905.20
3 Semen Putih Pengisi Nat Kg 2,540.00 0.2000 508.00
4 Pasir Beton M3 187,000.00 0.0420 7,854.00
Jumlah 109,767.20
C Jumlah A + B 225,267.20
D Biaya Umum = % x C 0.00
E Harga Satuan = ( C + D ) 225,267.20
Pekerjaan Lantai Keramik uk. 30 x 30 cm Polos (P.LD.08 / M2)

Harga Biaya
No. Uraian Satuan Satuan Kuantitas Satuan
( Rp ) ( Rp )
A TENAGA KERJA
1 Tukang Semen Hari/Orang 125,000.00 0.3500 43,750.00
2 Kepala Tukang Semen Hari/Orang 150,000.00 0.0350 5,250.00
3 Pekerja Hari/Orang 100,000.00 0.6200 62,000.00
4 Mandor Hari/Orang 150,000.00 0.0300 4,500.00
Jumlah 115,500.00
B BAHAN
1 Keramik 30 x 30 Bh 6,350.00 12.0000 76,200.00
2 Portland cement Kg 2,540.00 11.3800 28,905.20
3 Semen Putih Pengisi Nat Kg 2,540.00 0.2000 508.00
4 Pasir Beton M3 187,000.00 0.0420 7,854.00
Jumlah 113,467.20
C Jumlah A + B 228,967.20
D Biaya Umum = % x C 0.00
E Harga Satuan = ( C + D ) 228,967.20

Pekerjaan Pemasangan kloset Jongkok (P.Snt.02 / Bh)

Harga Biaya
No. Uraian Satuan Satuan Kuantitas Satuan
( Rp ) ( Rp )
A TENAGA KERJA
1 Tukang Batu Hari/Orang 125,000.00 1.5000 187,500.00
2 Kepala Tukang Batu Hari/Orang 150,000.00 0.1500 22,500.00
3 Pekerja Hari/Orang 100,000.00 1.0000 100,000.00
4 Mandor Hari/Orang 150,000.00 0.0500 7,500.00
Jumlah 317,500.00
B BAHAN
1 Kloset Jongkok Bh 195,000.00 1.0000 195,000.00
2 Portland Cement Kg 25,200.00 6.0000 151,200.00
3 Pasir Beton Kg 187,000.00 0.0100 1,870.00
Jumlah 348,070.00
C Jumlah A + B 665,570.00
D Biaya Umum = % x C 0.00
E Harga Satuan = ( C + D ) 665,570.00

Pekerjaan Pemasangan Wastefel (P.Snt.03 / Bh)

Harga Biaya
No. Uraian Satuan Satuan Kuantitas Satuan
( Rp ) ( Rp )
A TENAGA KERJA
1 Tukang Batu Hari/Orang 125,000.00 0.1500 18,750.00
2 Kepala Tukang Batu Hari/Orang 150,000.00 0.1450 21,750.00
3 Pekerja Hari/Orang 100,000.00 1.2000 120,000.00
4 Mandor Hari/Orang 150,000.00 0.0100 1,500.00
Jumlah 162,000.00
B BAHAN
1 Wastefel Bh 670,000.00 1.0000 670,000.00
2 Portland Cement Kg 25,200.00 6.0000 151,200.00
3 Pasir Beton Kg 187,000.00 0.0100 1,870.00
Jumlah 823,070.00
C Jumlah A + B 985,070.00
D Biaya Umum = % x C 0.00
E Harga Satuan = ( C + D ) 985,070.00

Pekerjaan Pemasangan Pipa PVC Tipe AW Ø 4" (P.Snt.14 / M')

Harga Biaya
No. Uraian Satuan Satuan Kuantitas Satuan
( Rp ) ( Rp )
A TENAGA KERJA
1 Tukang Hari/Orang 125,000.00 0.0600 7,500.00
2 Kepala Tukang Hari/Orang 150,000.00 0.0060 900.00
3 Pekerja Hari/Orang 100,000.00 0.0360 3,600.00
4 Mandor Hari/Orang 150,000.00 0.0180 2,700.00
Jumlah 14,700.00
B BAHAN
1 Pipa PVC Ø 4" M1 42,200.00 1.2000 50,640.00
2 Perlengkapan Ls 35 % X Harga Pipa 17,724.00
Jumlah 68,364.00
C Jumlah A + B 83,064.00
D Biaya Umum = % x C 0.00
E Harga Satuan = ( C + D ) 83,064.00
Pekerjaan Memasang Kran air Ø 3/4" atau Ø 1/2" (P.Snt.15 / Bh)

Harga Biaya
No. Uraian Satuan Satuan Kuantitas Satuan
( Rp ) ( Rp )
A TENAGA KERJA
1 Tukang Batu Hari/Orang 125,000.00 0.1000 12,500.00
2 Kepala Tukang Batu Hari/Orang 150,000.00 0.0100 1,500.00
3 Pekerja Hari/Orang 100,000.00 0.0100 1,000.00
4 Mandor Hari/Orang 150,000.00 0.0050 750.00
Jumlah 15,750.00
B BAHAN
1 Kran air Bh 15,300.00 1.0000 15,300.00
2 Seal Tape Set 3,100.00 0.0250 77.50
Jumlah 15,377.50
C Jumlah A + B 31,127.50
D Biaya Umum = % x C 0.00
E Harga Satuan = ( C + D ) 31,127.50

Pekerjaan Memasang Floor Drain (P.Snt.16 / Bh)

Harga Biaya
No. Uraian Satuan Satuan Kuantitas Satuan
( Rp ) ( Rp )
A TENAGA KERJA
1 Tukang Hari/Orang 125,000.00 0.0900 11,250.00
2 Kepala Tukang Hari/Orang 150,000.00 0.0090 1,350.00
3 Pekerja Hari/Orang 100,000.00 0.0540 5,400.00
4 Mandor Hari/Orang 150,000.00 0.0027 405.00
Jumlah 18,405.00
Upah diambil 50 % 9,202.50
B BAHAN
1 Floor Drain Bh 65,300.00 1.0000 65,300.00
Jumlah 65,300.00
C Jumlah A + B 74,502.50
D Biaya Umum = % x C 0.00
E Harga Satuan = ( C + D ) 74,502.50

Pekerjaan Pemasangan Kunci 2 slaag ( P.KK.02 Bh )

Harga Biaya
No. Uraian Satuan Satuan Kuantitas Satuan
( Rp ) ( Rp )
A TENAGA KERJA
1 Tukang Kayu Hari/Orang 125,000.00 0.5000 62,500.00
2 Kepala Tukang Kayu Hari/Orang 150,000.00 0.0100 1,500.00
3 Pekerja Hari/Orang 100,000.00 0.0100 1,000.00
4 Mandor Hari/Orang 150,000.00 0.0050 750.00
Jumlah 65,750.00
B BAHAN
1 Kunci 2 slaag Bh 198,500.00 1.0000 198,500.00
Jumlah 198,500.00
C Jumlah A + B 264,250.00
D Biaya Umum = % x C 0.00
E Harga Satuan = ( C + D ) 264,250.00

Pekerjaan Pemasangan engsel Pintu ( P.KK.04 / Bh )

Harga Biaya
No. Uraian Satuan Satuan Kuantitas Satuan
( Rp ) ( Rp )
A TENAGA KERJA
1 Tukang Kayu Hari/Orang 125,000.00 0.1500 18,750.00
2 Kepala Tukang Kayu Hari/Orang 150,000.00 0.0150 2,250.00
3 Pekerja Hari/Orang 100,000.00 0.0150 1,500.00
4 Mandor Hari/Orang 150,000.00 0.00075 112.50
Jumlah 22,612.50
B BAHAN
1 Engsel Pintu Bh 25,050.00 1.0000 25,050.00
Jumlah 25,050.00
C Jumlah A + B 47,662.50
D Biaya Umum = % x C 0.00
E Harga Satuan = ( C + D ) 47,662.50
Pekerjaan Pemasangan engsel Jendela ( P.KK.05 / Bh )

Harga Biaya
No. Uraian Satuan Satuan Kuantitas Satuan
( Rp ) ( Rp )
A TENAGA KERJA
1 Tukang Kayu Hari/Orang 125,000.00 0.1500 18,750.00
2 Kepala Tukang Kayu Hari/Orang 150,000.00 0.0150 2,250.00
3 Pekerja Hari/Orang 100,000.00 0.0150 1,500.00
4 Mandor Hari/Orang 150,000.00 0.00075 112.50
Jumlah 22,612.50
B BAHAN
1 Engsel Jendela Bh 20,050.00 1.0000 20,050.00
Jumlah 20,050.00
C Jumlah A + B 42,662.50
D Biaya Umum = % x C 0.00
E Harga Satuan = ( C + D ) 42,662.50

Pekerjaan Pemasangan Kait angin ( P.KK.06 / Bh )

Harga Biaya
No. Uraian Satuan Satuan Kuantitas Satuan
( Rp ) ( Rp )
A TENAGA KERJA
1 Tukang Kayu Hari/Orang 125,000.00 0.1500 18,750.00
2 Kepala Tukang Kayu Hari/Orang 150,000.00 0.0150 2,250.00
3 Pekerja Hari/Orang 100,000.00 0.0150 1,500.00
4 Mandor Hari/Orang 150,000.00 0.00080 120.00
Jumlah 22,620.00
Upah Diambil 25 % 4,524.00
B BAHAN
1 Kait Angin Bh 6,050.00 1.0000 6,050.00
Jumlah 6,050.00
C Jumlah A + B 10,574.00
D Biaya Umum = % x C 0.00
E Harga Satuan = ( C + D ) 10,574.00

Pekerjaan Pemasangan Slot Pintu ( P.KK.07 / Bh )

Harga Biaya
No. Uraian Satuan Satuan Kuantitas Satuan
( Rp ) ( Rp )
A TENAGA KERJA
1 Tukang Kayu Hari/Orang 125,000.00 0.2000 25,000.00
2 Kepala Tukang Kayu Hari/Orang 150,000.00 0.0200 3,000.00
3 Pekerja Hari/Orang 100,000.00 0.0200 2,000.00
4 Mandor Hari/Orang 150,000.00 0.0010 150.00
Jumlah 30,150.00
Upah diambil 25 % 7,537.50
B BAHAN
1 Slot Pintu Bh 12,050.00 1.0000 12,050.00
Jumlah 12,050.00
C Jumlah A + B 19,587.50
D Biaya Umum = % x C 0.00
E Harga Satuan = ( C + D ) 19,587.50

Pekerjaan Pemasangan Slot Jendela ( P.KK.08 / Bh )

Harga Biaya
No. Uraian Satuan Satuan Kuantitas Satuan
( Rp ) ( Rp )
A TENAGA KERJA
1 Tukang Kayu Hari/Orang 125,000.00 0.2000 25,000.00
2 Kepala Tukang Hari/Orang 150,000.00 0.0200 3,000.00
3 Pekerja Hari/Orang 100,000.00 0.0200 2,000.00
4 Mandor Hari/Orang 150,000.00 0.0010 150.00
Jumlah 30,150.00
Upah diambil 25 % 7,537.50
B BAHAN
1 Slot Jendela Bh 8,050.00 1.0000 8,050.00
Jumlah 8,050.00
C Jumlah A + B 15,587.50
D Biaya Umum = % x C 0.00
E Harga Satuan = ( C + D ) 15,587.50
Pekerjaan Pemasangan Handle Jendela ( P.KK.09/ Bh )

Harga Biaya
No. Uraian Satuan Satuan Kuantitas Satuan
( Rp ) ( Rp )
A TENAGA KERJA
1 Tukang Kayu Hari/Orang 125,000.00 0.2000 25,000.00
2 Kepala Tukang Hari/Orang 150,000.00 0.0200 3,000.00
3 Pekerja Hari/Orang 100,000.00 0.0200 2,000.00
4 Mandor Hari/Orang 150,000.00 0.0010 150.00
Jumlah 30,150.00
Upah diambil 25 % 7,537.50
B BAHAN
1 Handle Jendela Bh 13,050.00 1.0000 13,050.00
Jumlah 13,050.00
C Jumlah A + B 20,587.50
D Biaya Umum = % x C 0.00
E Harga Satuan = ( C + D ) 20,587.50

Pekerjaan Pemasangan Handle Pintu ( P.KK.10/ Bh )

Harga Biaya
No. Uraian Satuan Satuan Kuantitas Satuan
( Rp ) ( Rp )
A TENAGA KERJA
1 Tukang Kayu Hari/Orang 125,000.00 0.2000 25,000.00
2 Kepala Tukang Hari/Orang 150,000.00 0.0200 3,000.00
3 Pekerja Hari/Orang 100,000.00 0.0200 2,000.00
4 Mandor Hari/Orang 150,000.00 0.0010 150.00
Jumlah 30,150.00
Upah diambil 50 % 15,075.00
B BAHAN
1 Handle Pintu Bh 80,050.00 1.0000 80,050.00
Jumlah 80,050.00
C Jumlah A + B 95,125.00
D Biaya Umum = % x C 0.00
E Harga Satuan = ( C + D ) 95,125.00