Program : -
Kegiatan : -
Pekerjaan : -
Lokasi : -
Tahun Anggaran : 2017
I PEKERJAAN LANTAI
1 Urugan Pasir t = 30 cm PT.08 M3 93.68 237,080.00 22,208,943.16
2 Lantai Kerja Beton Camp. 1:3:5 , t = 5cm P.PBB.01 M3 12.20 1,034,350.00 12,619,070.00
- Pembesian Ø 8 mm P.BB.03 Kg 171.77 25,839.00 4,438,238.94
3 Pekerjaan Keramik Lantai Uk. 40x40 Polos P.LD.09 M2 200.00 236,242.20 47,248,440.00
86,514,692.10
II PEKERJAAN PEMASANGAN BATAKO
1 Pekerjaan Pemasangan Batako P.Dnd.01 M2 360.03 131,749.00 47,433,987.72
47,433,987.72
III PEKERJAAN PLESTERAN DINDING
1 Pekerjaan Plaster t=1,5cm P.Pls.11 M2 720.07 62,753.80 45,186,877.75
45,186,877.75
IV PEKERJAAN TOILET
1 Balok Sloof 20x35cm
- Cor Beton Camp. 1 : 2 : 3 P.BB.02 M3 0.68 1,512,990.00 1,022,781.24
- Pembesian Ø 12 mm P.BB.03 Kg 48.22 25,839.00 1,246,037.28
- Pembesian Beugel Ø 8-15cm P.BB.03 Kg 33.80 25,839.00 873,361.14
- Bekesting P.BB.05 M2 9.46 166,407.50 1,574,880.58
2 Kolom 15x15 cm
- Cor Beton Camp. 1 : 2 : 3 P.BB.02 M3 0.60 1,512,990.00 907,794.00
- Pembesian Ø 12 mm P.BB.03 Kg 122.16 25,839.00 3,156,383.10
- Pembesian Beugel Ø 8-15cm P.BB.09 Kg 64.13 25,839.00 1,657,058.65
- Bekesting P.BB.06 M2 14.40 248,687.50 3,581,100.00
- Plesteran P.Pls.11 M2 9.60 62,753.80 602,436.48
3 Ring Balok 20x15cm
- Cor Beton Camp. 1 : 2 : 3 P.BB.02 M3 0.20 1,512,990.00 306,834.37
- Pembesian Ø 12 mm P.BB.03 Kg 49.93 25,839.00 1,290,079.84
- Pembesian Beugel Ø 8-15cm P.BB.09 Kg 20.10 25,839.00 519,335.13
- Bekesting P.BB.10 M2 4.73 15,997.40 75,699.70
- Plesteran P.Pls.11 M2 4.73 62,753.80 296,950.98
4 Atap Dak Beton, t= 10cm
- Cor Beton Camp. 1 : 2 : 3 P.BB.02 M3 1.06 1,512,990.00 1,600,743.42
- Pembesian Ø 8 mm (Double) P.BB.03 Kg 37.88 25,839.00 978,723.44
- Bekesting P.BB.09 M2 4.83 37,565.60 181,441.85
5 Keramik Lantai 20x20cm P.LD.07 M2 8.00 225,267.20 1,802,137.60
6 Pemasangan Floordrain P.Snt.16 Unit 3.00 74,502.50 223,507.50
7 Pemasangan kran Ø 3/4 atau 1/2 P.Snt.15 Unit 4.00 31,127.50 124,510.00
8 Instalasi Air Kotor, Pipa Ø4 P.Snt.14 M1 11.50 83,064.00 955,236.00
9 Pemasangan Kloset Jongkok P.Snt.02 Unit 3.00 195,000.00 585,000.00
10 Pemasangan Wastafel P.Snt.03 Unit 1.00 849,110.00 849,110.00
24,411,142.29
V PEKERJAAN SELASAR
Program :-
Kegiatan :-
Pekerjaan :-
Lokasi :-
Tahun Anggaran : 2017
A. JUMLAH 425,000,154.18
B. DIBULATKAN 425,000,000.00
Terbilang :-
aaaaaa, ………………….2017
DIBUAT OLEH :
KEPALA SEKOLAH
SDN NO.02 BENUA MARTINUS
ELIAS, S.Pd.SD
NIP.197304111996061001
WILAYAH PUTUSSIBAU DAN SEKITARNYA
(Meliputi: Kec. Putussibau Utara, Putussibau Selatan, Kalis, Bika, Mentebah, Boyan Tanjung, Bunut
Hulu, Pengkadan, Hulu Gurung, Embaloh Hulu, dll)
UPAH UPAH
NO URAIAN TENAGA KERJA KODE
(Rp / Hari) (Rp / Jam) KETERANGAN
A B C D E F
1 Mandor Lapangan L.061 150,000.00 21,428.57
2 Mekanik L.071 150,000.00 21,428.57
3 Mekanik Pembantu L.072 125,000.00 17,857.14
4 Kepala Tukang L.073 150,000.00 21,428.57
5 Tukang L.079 125,000.00 17,857.14
6 Operator ** L.081 150,000.00 21,428.57
7 Pembantu Operator *** L.089 105,000.00 15,000.00
8 Supir Truck Material L.091 125,000.00 17,857.14
9 Pembantu Supir L.099 100,000.00 14,285.71
10 Buruh Lapangan Tidak Terlatih/Pekerja L.101 100,000.00 14,285.71
CATATAN :
*) Tenaga Kerja Dihitung 7 (Tujuh) Jam Kerja / Hari
n*) Operator yang sudah biasa dan terampil mengoperasikan jenis peralatan untuk melayani pekerjaan berat.
Misal : Buldozer, Grader, Whell Loader, Asphalt Finisher, dll.
n') Operator yang mengoperasikan peralatan untuk melayani pekerjaan berat yang agak ringan.
Misal : Steel Wheeled Roller, Stamper, Mechanical Rammer, Concrete Mixer / Mesin Pengaduk.
HARGA SATUAN
NO URAIAN BAHAN / MATERIAL KODE SATUAN KETERANGAN
(Rp)
A B C D E F
BAHAN PENGISI
1 Batu Gunung Quary M_010 m3 340,000.00
2 Batu Gunung Quary M_010.a m3 232,000.00
3 Batu Gunung Quary M_010.b m3 194,000.00
4 Kerikil dari galian bukit M_011 m3 280,000.00
5 Kerikil Sungai ( Leveransir ) M_012 m3 197,000.00
6 Kerikil Sungai ( Royality ) M_013 m3 80,000.00
7 Batu kali M_014 m3 222,000.00
8 Kerikil sungai ayak tanpa pasir (1-2 cm) M_015 m3 207,000.00
9 Kerikil sungai ayak tanpa pasir (2-3 cm) M_015.a m3 192,000.00
10 Batu pecah gunung (10 - 15 cm) M_021 m3 450,000.00
11 Batu pecah gunung (7 - 10 cm) M_022 m3 575,000.00
12 Batu pecah gunung (5 - 7 cm.) M_023 m3 675,000.00
13 Batu pecah gunung (3 - 5 cm.) M_024 m3 725,000.00
14 Batu pecah gunung (2 - 3 cm.) M_025 m3 775,000.00
15 Batu pecah gunung (1 - 2 cm.) M_026 m3 825,000.00
16 Batu pecah gunung (0,5 - 1 cm.) M_027 m3 975,000.00
17 Batu pecah sungai (3 - 5 cm.) M_028 m3 625,000.00
18 Batu pecah sungai (2 - 3 cm.) M_029 m3 675,000.00
19 Batu pecah sungai (1 - 2 cm.) M_030 m3 725,000.00
20 Batu pecah sungai (0,5 - 1 cm.) M_031 m3 825,000.00
21 Pasir urug / timbun M_040 m3 172,000.00
22 Pasir ayak untuk beton M_041 m3 187,000.00
23 Sirtu Sungai ( Leveransir ) M_042 m3 187,000.00
24 Sirtu Sungai ( Royality ) M_043 m3 80,000.00
25 Bahan timbunan pilihan (laterit) Leveransir M_050 m3 137,000.00
26 Bahan timbunan pilihan (laterit) Setempat M_051 m3 40,000.00
27 Timbunan setempat ( tanah biasa) M_052 m3 10,000.00
28 Aspal Bitument M_061 Kg. 10,800.00
29 Semen Portlant ( PC ) M_080 50 Kg. 127,000.00
30 Semen Portlant ( PC ) M_080.a Kg 2,540.00
31 Semen Warna (Oker) M_080.b Kg 15,040.00
32 Paving blok M_082 BH 3,200.00
33 Bataco Ukuran 15 x 30 x 7 cm M_239 Buah 2,700.00
34 Bataco Ukuran 20 x 40 x 7 cm M_239.a Buah 3,200.00
35 Bataco Ukuran 20 x 40 x 9 cm M_239.b Buah 3,450.00
36 Alat - alat bantu * M_171 Set 125,000.00
37 Alat - alat bantu ** M_172 Set 205,000.00
38 Alat - alat bantu pek. Latasir *** M_173 Set 235,000.00
39 Gerobak + kuali aspal M_174 Set 6,250,000.00
BAHAN MINYAK
40 Minyak Tanah M_065 Ltr. 7,600.00
41 Minyak Diesel M_183 Ltr. 13,700.00
42 Premium / Bensin M_184 Ltr. 11,600.00
43 Minyak Pelumas M_185 Ltr. 30,600.00
44 Minyak Thinner M - 203 Ltr 20,500.00
45 Minyak Bekesting / Cetakan M - 203.a Ltr 7,300.00
HARGA SATUAN
NO URAIAN BAHAN / MATERIAL KODE SATUAN KETERANGAN
(Rp)
A B C D E F
BAHAN CAT
46 Cat Jembatan M_090 Kg 120,500.00
47 Cat Dasar M_187 Kg. 45,600.00
48 Alkali - Kg 54,300.00
49 Teer M_188 Kg. 10,600.00
50 Cat Kilap M_193 Kg. 55,600.00
51 Cat Galvanis M - 202 Kg 51,000.00
52 Dempul M_230 Kg 35,100.00
53 Plamur M_231 Kg 35,100.00
54 Amplas M_232 Lbr 3,100.00
55 Cat Tembok Kualitas Biasa M_233 Kg 10,100.00
56 Cat Tembok Kualitas Sedang M_233.a Kg 17,325.00
57 Cat Tembok Weather Shield M_233.b Kg 110,100.00
58 Cat Vernis M_233.a Liter 50,100.00
59 Cat Melamic M_233.b Kg 60,100.00
60 Cat Meni Besi M_233.c Kg 27,100.00
61 Cat Meni Atap M_233.d Kg 30,100.00
62 Cat Tembok Interior M_233.e Kg 100,100.00
63 Cat Tembok Eksterior (Anti Jamur) M_233.f Kg 110,100.00
64 Cat Water Proofing M_233.g Kg 55,100.00
65 Soda Api M_234 Kg 41,100.00
66 Sabun M_235 Kg 5,100.00
67 Kuas Cat M_236 Buah 20,100.00
BAHAN BESI & BAJA
68 Baja Tralis M_161 Kg. 20,600.00
69 Kawat Bronjong Galvanis uk. 2.0 x 1.0 x 0.5 dia. 3 mm M_162 Unit 646,000.00
70 Kawat Bronjong Galvanis M_162. a Kg. 35,600.00
71 Kawat Bronjong Galvanis Lapis PVC M_162. b Kg. 70,600.00
72 Kawat las M_162 c Kg. 33,000.00
73 Kawat Las Listrik M_162 d Kg 32,000.00
74 Paku Jembatan M_166 Kg. 30,600.00
75 Baut Baja M_163 Kg. 36,000.00
76 Besi Galvanis sandaran jembatan M_164 btg 626,000.00
77 Baja Konstruksi (rangka baja Jembatan) M_165 Kg. 36,000.00
78 Baja Beton U.24 Tulangan Polos dan Ulir M_167 Kg. 22,600.00
79 Baja Beton U.32 Tulangan Polos dan Ulir M_167. a Kg. 23,600.00
80 Wire Mash M5 M_167. b Kg. 28,900.00
81 Wire Mash M6 M_167. c Kg. 37,700.00
82 Kawat Bindrat / Kawat Ikat M_170 Kg. 25,600.00
83 Beugel tebal plat 5 mm M_186 Bh. 25,600.00
84 Baut Panjang (15 - 30 cm) M_189 Btg. 8,100.00
85 Paku Baut 15 cm M. 189.A Btg. 5,600.00
86 Baut Pendek (4 - 12 cm) M_190 Btg. 2,600.00
87 Klem spore plank M_194 Btg. 30,600.00
88 Pipa baja tiang pancang M_197 Kg. 27,000.00
89 Sepatu besi untuk pancang kayu M_198 Bh 256,000.00
90 Baja konstruksi WF berbagai Ukuran: M - 199 Kg 36,000.00
91 Besi plat Uk berbagai Ukuran M - 200 Kg 36,000.00
92 Baja Kanal ( C ) Berbagai ukuran M - 201 Kg 36,000.00
93 Besi Profil CNP 125.50.20.3,2 M - 201 Kg 48,900.00
94 Besi Profil Siku - Kg 39,000.00
95 Besi Profil Hollow - Kg 38,000.00
96 Kusen Alumunium Uk. 5/5 cm Warna Silver - m1 149,000.00
97 Kusen Alumunium Uk. 4/8 cm Warna Silver - m1 121,000.00
98 Kusen Alumunium Uk. 5/10 cm Warna Silver - m1 161,000.00
99 Kusen Alumunium Uk. 5/12 cm Warna Silver - m1 143,500.00
100 Kusen Alumunium Ambang Uk. 3,5/5 cm Warna Silver - m1 141,850.00
101 Sunscreen Alumunium Lebar 7,5 cm - m2 1,206,000.00
102 Sunscreen Alumunium Lebar 13,5 cm - m2 1,876,000.00
103 Kawat Simpai M_237 Kg 17,200.00
104 Kawat Waring Kualitas Baik M_237.a m1 7,200.00
105 Kawat Waring Kualitas Biasa M_237.b m1 5,200.00
106 Kawat Duri M_238 Kg 20,200.00
107 Paku Campuran M_241 Kg 25,200.00
108 Paku Triplek M_241.a Kg 40,200.00
109 Paku Seng / Belian M_241.b Kg 30,200.00
110 Sekrup M_242 Kg 8,200.00
111 Sekrup Fixer - Buah 1,200.00
112 Sealant - Tube 45,200.00
113 Besi Strip M_243 Btg 17,000.00
114 Kabel / Seling 1" M_245 m1 83,000.00
115 Kabel / Seling 1/2" M_245.a m1 22,500.00
116 Kabel / Seling 1/4" M_245.b m1 11,000.00
HARGA SATUAN
NO URAIAN BAHAN / MATERIAL KODE SATUAN KETERANGAN
(Rp)
A B C D E F
117 Kabel Baja Pengaku dia. 19 mm M - 246 m1 40,500.00
118 Seling BaJa Dia. 1,5 " M - 247 m1 193,000.00
119 Seling Baja Dia. 2,5 " M - 247.a m1 203,000.00
120 Katrol M - 248 Set 1,770,000.00
121 Warfel 2" M - 249 Buah 655,000.00
122 Warfel 1/2" M - 249.a Buah 22,500.00
123 Warfel 19 mm M - 249.b Buah 35,500.00
124 Cekak 1,5" - Buah 47,000.00
125 Cekak 1" M - 250 Buah 22,000.00
126 Cekak 1/2" M - 250.a Buah 7,000.00
127 Cekak 1/4" M - 250.b Buah 5,250.00
128 Cekak seling 19 mm M - 251 Buah 13,000.00
129 Accesoris Plat Penggantung - Buah 58,100.00
BAHAN KAYU
130 Kayu Bakar M_070 m3 235,000.00
131 Kayu bulat untuk turap panjang 2 m M_175 Btg 7,500.00
132 Kayu Bulat Untuk Turap Panjang 4 - 4,5 m M_176 Btg 13,100.00
133 Kayu untuk Perancah M_180 m3 955,000.00
134 Kayu Konstruksi Jembatan (Kayu Belian Uk. 15/15 cm) M_181 m3 10,051,500.00
135 Kayu Konstruksi Jembatan (Kayu Kelas I Uk. 15/15 cm) M_191 m3 4,848,500.00
136 Papan Lantai Jembatan Kelas I Uk. 4/18-4,20 m M_191.g m3 4,386,500.00
137 Papan Lantai Jembatan Kelas I Uk. 4/18-3,60 m M_191.h m3 4,386,500.00
138 Kayu Tembesu M_195 m3 4,278,500.00
139 Kayu Belian Panjang ≥ 2,5 m (Ketam) M_181.a m3 11,214,500.00
140 Kayu Belian Panjang ≥ 2,5 m (Tidak Ketam) M_181.b m3 11,017,500.00
141 Kayu Belian Panjang < 2,5 m (Ketam) M_181.c m3 9,755,500.00
142 Kayu Belian Panjang < 2,5 m (Tidak Ketam) M_181.d m3 9,406,500.00
143 Kayu Klas I Tekam (Ketam) M_191.a m3 3,737,500.00
144 Kayu Klas I Tekam (Tidak Ketam) M_191.b m3 3,536,500.00
145 Kayu Klas I Selain Tekam (Ketam) M_191.c m3 3,334,500.00
146 Kayu Klas I Selain Tekam (Tidak Ketam) M_191.d m3 3,137,500.00
147 Kayu Klas II, Kawi Danau (Ketam) M_192.c m3 2,528,500.00
148 Kayu Klas II, Kawi Danau(Tidak Ketam) M_192.d m3 2,327,500.00
149 Kayu Klas II, Selain Kawi Danau (Ketam) M_192 m3 2,326,500.00
150 Kayu Klas II. Selain Kawi Danau (Tidak Ketam) M_192.a m3 2,125,500.00
151 Kayu Klas III (Ketam) M_213 m3 2,088,500.00
152 Kayu Klas III (Tidak Ketam) M_213.a m3 2,021,500.00
153 Papan Kayu Belian (Ketam) M_181.c m3 11,628,500.00
154 Papan Kayu Belian (Tidak Ketam) M_181.d m3 11,028,500.00
155 Papan Kayu Klas I, Tekam (Ketam) M_191.e m3 6,348,500.00
156 Papan Kayu Klas I, Tekam (Tidak Ketam) M_191.f m3 5,918,500.00
157 Papan Kayu Klas I, Selain Tekam (Ketam) M_191.g m3 5,918,500.00
158 Papan Kayu Klas I, Selain Tekam (Tidak Ketam) M_191.h m3 5,488,500.00
159 Papan Kayu Klas II, Kawi (Ketam) M_192.e m3 4,414,500.00
160 Papan Kayu Klas II Kawi (Tidak Ketam) M_192.f m3 3,984,500.00
161 Papan Kayu Klas II Selain Kawi (Ketam) M_192.g m3 3,355,500.00
162 Papan Kayu Klas II Selain Kawi (Tidak Ketam) M_192.h m3 2,925,500.00
163 Papan Kayu Klas III (Campuran) M_213.b m3 1,966,500.00
164 Tiang Tongkat Kayu Belian Uk. 9/9 - 4,20 M M_181.g Btg 335,000.00
165 Tiang Tongkat Kayu Belian Uk. 9/9 - 3,60 M M_181.h Btg 325,000.00
166 Tiang Tongkat Kayu Belian Uk. 9/9 - 3,20 M M_181.i Btg 300,000.00
167 Tiang Tongkat Kayu Belian Uk. 9/9 - 2,70 M M_181.j Btg 250,000.00
168 Tiang Tongkat Kayu Belian Uk. 9/9 - 2,50 M M_181.k Btg 235,200.00
169 Tiang Tongkat Kayu Belian Uk. 9/9 - 2,20 M M_181.l Btg 192,000.00
170 Tiang Tongkat Kayu Belian Uk. 9/9 - 2,10 M M_181.m Btg 184,400.00
171 Tiang Tongkat Kayu Belian Uk. 9/9 - 1,80 M M_181.n Btg 150,000.00
172 Tiang Tongkat Kayu Belian Uk. 9/9 - 1,50 M M_181.o Btg 95,200.00
173 Renglat M_215 Btg 9,300.00
174 Laci Kayu Belian 5/10 - 80 cm M_181.e Btg 9,600.00
175 Laci Kayu Belian 9/9 - 80 cm M_181.f Btg 15,500.00
176 Laci Kayu Belian 4/8 - 60 cm M_181.g Btg 8,800.00
177 Alas Kayu Hutan M_216 Btg 6,800.00
178 Alas Laci Kayu Belian 4/8-60 cm M_216.a Btg 8,800.00
179 Konsul Kayu Klas I M_217 Buah 95,000.00
180 Triplek 3 mm M_218 Lbr 60,300.00
181 Triplek 3 mm M_218.a m2 20,256.65
182 Triplek 6 mm M_218.b Lbr 145,300.00
183 Triplek 9 mm M_218.c Lbr 243,000.00
184 Triplek 12 mm M_218.d Lbr 303,000.00
185 Plywood 4' x 8' x 4 mm M_218.e Lbr 79,000.00
186 Lem Kayu M_219 ltr 40,500.00
187 Lem Kuning M_219.a ltr 47,500.00
188 List Kayu Profil M_220 m' 12,500.00
189 Kayu Profil List Plafond M_221 m' 7,000.00
HARGA SATUAN
NO URAIAN BAHAN / MATERIAL KODE SATUAN KETERANGAN
(Rp)
A B C D E F
190 Gypsum Profil List Plafond / Cornice - m1 30,500.00
191 Gypsum Board Tebal 4 mm M_222 Lbr 87,000.00
192 GRC Board Tebal 4 mm M_223 Lbr 76,500.00
193 Aklirik Tebal 6 mm Uk. 120 x 240 cm - Lbr 932,000.00
194 Papan Profil /Lambriziring - m3 4,504,000.00
195 Papan Lambrizing Tebal 9 mm - Lbr 166,000.00
196 Sungkai Tebal 3 mm, Uk. 120 x 240 cm - m2 82,000.00
197 List Plafond Ukiran Kayu Kelas I Lebar 70 cm - m1 551,000.00
BAHAN SANITASI
198 Talang Gantung & Talang Tegak M_229 m1 95,500.00
199 Pipa Suling Dia. 3/4" M - 253 Buah 20,100.00
200 Pipa Galvanis Dia. 2" M - 253.a m' 156,500.00
201 Pipa Galvanis Dia. 4" M - 253.b m' 560,500.00
202 Pipa Galvanis Dia. 6" M - 253.c m' 839,500.00
203 Pipa Spiral Dia. 4 - m' 425,000.00
205 Kloset Duduk M - 254 Buah 1,405,000.00
205 Kloset Jongkok M - 254.a Buah 195,000.00
206 Urinoir M - 255 Buah 577,900.00
207 Wastafel M - 256 Buah 670,000.00
208 Seal Tape Gypsum M - 257 Buah 30,100.00
209 Floor Drain M - 258 Buah 65,300.00
210 Kran Air Kualitas Biasa M - 259 Buah 15,300.00
211 Kran Air Kualitas Baik M - 259. a Buah 40,300.00
212 Kran Air Stainless Ø 1/2" M - 259. a Buah 47,300.00
213 Penguras Bak Air Ø 3/4" - Buah 15,300.00
214 Seal Tape Kran M - 260 Buah 3,100.00
215 Tempat Sabun Porcelain (Keramik) Terpasang - Buah 60,100.00
216 Centong Air Kualitas Biasa - Buah 15,100.00
217 Centong Air Kualitas Baik - Buah 25,100.00
218 Bak Air Fiber Glass 0,50 M3 M - 261 Buah 1,250,000.00
219 Bak Air Fiber Glass 0,75 M3 M - 261.a Buah 1,550,000.00
220 Bak Air Fiber Glass 0,80 M3 M - 261.b Buah 1,650,000.00
221 Bak Air Fiber Glass 1 M3 M - 261.c Buah 2,050,000.00
222 Bak Air Fiber Glass 2 M3 M - 261.d Buah 2,725,000.00
223 Bak Air Fiber Glass 1,5 M3 M - 261.e Buah 3,450,000.00
224 Bak Air Fiber Glass 3 M3 M - 261.f Buah 4,250,000.00
225 Bak Air Fiber Glass 5 M3 M - 261.g Buah 5,100,000.00
226 Septic Tank Type ST24 0,75 M3 - Buah 3,510,000.00
227 Septic Tank Type ST46 1,30 M3 - Buah 4,610,000.00
228 Septic Tank Type ST68 1,55 M3 - Buah 5,490,000.00
BAHAN ATAP
229 Seng Gelombang BJLS 0,20 M_224 Lbr 42,500.00
230 Seng Gelombang BJLS 0,20 M_224.a m2 33,203.13
231 Seng Gelombang BJLS 0,30 M_224.b Lbr 65,500.00
232 Seng Gelombang BJLS 0,30 M_224.c m2 51,171.88
233 Seng Gelombang Warna BJLS 0,25 M_224.d Lbr 55,500.00
234 Plat Aluminium Warna BJLS 0,25 - Lbr 65,500.00
235 Genteng Metal Type PRIMA 0,35 M_225 Lbr 37,500.00
236 Genteng Metal Type ROYAL 0,35 M_225.a Lbr 37,500.00
237 Genteng Metal Type CLASSIC 0,35 M_225.b Lbr 37,500.00
238 Zincalume BJLS 0,3 Polos M_225.d m2 95,500.00
239 Zincalume BJLS 0,3 Color M_225.e m2 105,500.00
240 Zincalume BJLS 0,35 Polos M_225.f m2 160,700.00
241 Zincalume BJLS 0,35 Color M_225.g m2 175,000.00
242 Zincalume BJLS 0,4 Polos M_225.h m2 165,500.00
243 Zincalume BJLS 0,4 Color M_225.i m2 178,500.00
244 Seng Datar Colour BJLS 0,35 M_227 Lbr 48,500.00
245 Seng Datar Polos BJLS 0,30 M_227.a Lbr 48,000.00
246 Zincalume Plat BJLS 0,3 Polos M_227.b Lbr 132,000.00
247 Zincalume Plat BJLS 0,3 Color M_227.c Lbr 146,300.00
248 Zincalume Plat BJLS 0,35 Polos M_227.d Lbr 160,700.00
249 Zincalume Plat BJLS 0,35 Color M_227.e Lbr 175,500.00
250 Nok / Bubungan Genteng Metal 1/2 Lingkaran 0,35 M_228 Buah 48,500.00
251 Roof Light Fiberglass - m2 362,500.00
252 Roof Light Polycarbonat - m2 356,500.00
BAHAN KERAMIK
253 Keramik 10 x 20 cm Polos M_240 Buah 1,850.00
254 Keramik 10 x 33 cm Polos M_240.a Buah 2,600.00
255 Keramik 20 x 20 cm Polos M_240.b Buah 2,900.00
256 Keramik 20 x 25 cm Polos M_240.c Buah 3,850.00
257 Keramik 30 x 30 cm Polos M_240.d Buah 6,350.00
258 Keramik 30 x 30 cm Artistik M_240.e Buah 6,400.00
259 Keramik 30 x 30 cm Unpolished M_240.f Buah 6,400.00
260 Keramik 40 x 40 cm Polos M_240.g Buah 15,900.00
261 Keramik 40 x 40 cm Anti Gores M_240.h Buah 20,100.00
262 Keramik 40 x 40 cm Unpolished M_240.i Buah 16,600.00
HARGA SATUAN
NO URAIAN BAHAN / MATERIAL KODE SATUAN KETERANGAN
(Rp)
A B C D E F
263 Keramik 60 x 60 cm Anti Gores (Polysed) M_240.j Buah 139,100.00
264 Keramik 10 x 10 cm Anti Gores (Polysed) M_240.k Buah 10,100.00
265 Keramik List Dinding 10 x 20 cm (Polysed) M_240.l Buah 6,100.00
266 Batu Granit - m2 1,200,100.00
267 Batu Teraso - m2 200,100.00
268 Batu Tempel Hitam (Batu Alam) - m2 230,100.00
269 Batu Andesit - m2 550,100.00
BAHAN KACA
270 Kaca Polos Tebal 3 mm M_244 m2 153,000.00
271 Kaca Polos Tebal 5 mm M_244.a m2 173,000.00
272 Kaca Polos Tebal 8 mm M_244.b m2 333,000.00
273 Kaca Polos Tebal 12 mm M_244.c m2 415,000.00
274 Kaca Rayben Tebal 5 mm M_244.d m2 203,000.00
275 Kaca Cermin Tebal 5 mm M_244.e m2 278,000.00
276 Kaca Buram Tebal 5 mm M_244.f m2 173,500.00
277 Kaca Setara Asahi Drak Blue Tebal 5 mm (Stopsol) M_244.g m2 333,000.00
278 Kaca Setara Asahi Drak Blue Tebal 6 mm (Stopsol) M_244.h m2 683,000.00
279 Kaca Setara Asahi Drak Blue Tebal 8 mm (Stopsol) M_244.i m2 768,000.00
280 Kaca Setara Asahi Drak Blue Tebal 12 mm (Stopsol) M_244.j m2 966,000.00
BAHAN LISTRIK
281 Saklar Ganda Kualitas Biasa M - 262 Buah 10,050.00
282 Saklar Ganda Kualitas Baik M - 262.a Buah 25,050.00
283 Saklar Tunggal Kualitas Biasa M - 262.b Buah 9,050.00
284 Saklar Tunggal Kualitas Baik M - 262.c Set 20,050.00
285 Stop Kontak Kualitas Biasa M - 263 Set 10,050.00
286 Stop Kontak Kualitas Baik M - 263.a Set 17,050.00
287 Sekring Box / MCB M - 264 Set 120,100.00
288 Lampu Pijar 40 Watt M - 265.a Set 25,050.00
289 Lampu XL 20 Watt M - 265.b Set 45,050.00
290 Lampu TL 20 Watt M - 266.c Set 45,050.00
291 Lampu LED 5 Watt M - 266.d Buah 50,050.00
292 Lampu LED 5 Watt M - 266.e Buah 110,050.00
293 Lampu LED 5 Watt M - 266.f Buah 125,050.00
294 Instalasi Titik Lampu - Titik 225,500.00
BAHAN PENGUNCI & PENGGANTUNG
295 Engsel Pintu M - 267 Buah 25,050.00
296 Engsel Jendela M - 267.a Buah 20,050.00
297 Engsel Pintu Pivot (Tanam) Kualitas Baik Terpasang M - 267.a Buah 975,350.00
298 Handle Pintu M - 268 Buah 80,050.00
299 Handle Pintu Stainless Steel Panjang 30 cm M - 268.a Buah 150,050.00
300 Handle Jendela M - 268.a Buah 13,050.00
301 Slot Pintu M - 269 Buah 12,050.00
302 Slot Pintu Tanam - Buah 105,050.00
303 Slot Jendela M - 269.a Buah 8,050.00
304 Kait Angin M - 270 Buah 6,050.00
305 Kunci 2 Slaag M - 271 Buah 198,500.00
306 Kunci Pintu Tanam M - 271.a Buah 160,500.00
307 Kunci Pintu Tanam 2 Slaag M - 271.a Buah 198,500.00
308 Pintu Folding Gate + Pemasangan M - 272 m2 590,000.00
309 Pintu Gulungan Besi (Rolling Door) M - 272.a m2 590,000.00
310 Door Closer M - 273 Buah 230,500.00
311 Engsel Sendok - Buah 15,500.00
BAHAN PERPIPAAN
312 Pipa Ø 1/2 " PVC M - 280.a m' 5,300.00
313 Pipa Ø 3/4 " PVC M - 281.a m' 8,150.00
314 Pipa Ø 1 " PVC M - 282.a m' 10,300.00
315 Pipa Ø 1,5 " PVC M - 283.a m' 17,050.00
316 Pipa Ø 2 " PVC M - 284.a m' 21,700.00
317 Pipa Ø 2,5 " PVC M - 285.a m' 30,900.00
318 Pipa Ø 3 " PVC M - 286.a m' 43,000.00
319 Pipa Ø 4 " PVC M - 287.a m' 71,050.00
320 Pipa Ø 6 " PVC M - 288.a m' 161,350.00
321 Pipa Ø 8 " PVC M - 289.a m' 278,500.00
322 Pipa Ø 1,5 " PVC M - 290.b m' 11,200.00
323 Pipa Ø 2 " PVC M - 291.b m' 14,800.00
324 Pipa Ø 2,5 " PVC M - 292.b m' 20,050.00
325 Pipa Ø 3 " PVC M - 293.b m' 26,600.00
326 Pipa Ø 4 " PVC M - 294.b m' 42,200.00
327 Pipa Ø 6 " PVC M - 295.b m' 111,300.00
328 Pipa Ø 8 " PVC M - 296.b m' 165,950.00
327 Water Meter 1/2" M - 440 Buah 347,565.00
328 Water Meter 50 mm M - 441 Buah 1,215,000.00
329 Water Meter 75 mm M - 442 Buah 1,988,000.00
330 Water Meter 100 mm M - 443 Buah 3,108,000.00
331 Water Meter 150 mm M - 444 Buah 3,328,000.00
332 Water Meter 200 mm M - 445 Buah 4,476,000.00
WILAYAH PUTUSSIBAU DAN SEKITARNYA
(Meliputi: Kec. Putussibau Utara, Putussibau Selatan, Kalis, Bika, Mentebah, Boyan Tanjung, Bunut
Hulu, Pengkadan, Hulu Gurung, Embaloh Hulu, dll)
K.9
Dengan Pertimbangan kondisi lokasi - lokasi yang bervariasi pada Kabupaten Kapuas Hulu, maka harga dasar dikelompokkan Dalam 6 wilayah sebagai berikut, lokasi yang diluar 6 wilayah
tersebut mengikuti standar harga dasar (Harga Putussibau dan Sekitarnya).
* Wilayah Pts&Sekitarnya : Adalah Wilayah yang meliputi Kec. Putussibau Utara, Putussibau Selatan, Kalis, Bika, Mentebah, Boyan Tanjung, Bunut Hulu, Pengkadan,
Hulu Gurung, Embaloh Hulu, dll)
* Wilayah I Meliputi : Adalah Wilayah Dimana Harga Dasar Material Quarry ( Batu,Pasir,dll ) dan Harga Angkut (Jalur Darat) Bahan Pabrikan (Semen,Besi Tulangan,dll)
dinaikan, Wilayah ini sesuai dengan kondisi daerah seperti : Empanang, Badau, Batang Lupar, Puring Kencana dll
* Wilayah II Meliputi : Adalah Wilayah Dimana Harga Dasar Material Quarry ( Batu,Pasir,dll ) tetap, dan Harga Angkut (Jalur Air) Bahan Pabrikan (Semen,Besi Tulangan,dll)
dinaikan, Wilayah ini sesuai dengan kondisi daerah seperti : Mendalam, Kensurai, Na. Lebangan, dll.
* Wilayah III Meliputi : Adalah Wilayah Dimana Harga Dasar Material Quarry ( Batu,Pasir,dll ) dan Harga Angkut (Jalur Air) Bahan Pabrikan (Semen,Besi Tulangan,dll)
dinaikan, Wilayah ini sesuai dengan kondisi daerah seperti : Kecamatan Embaloh Hilir, Bunut Hilir, Jongkong, dll.
* Wilayah IV Meliputi : Adalah Wilayah Dimana Harga Dasar Material Quarry ( Batu,Pasir,dll ) Tetap, dan Harga Angkut (Jalur Darat) Bahan Pabrikan
(Semen,Besi Tulangan,dll) diturunkan, Wilayah ini sesuai dengan kondisi daerah seperti : Kec Sejiram, Semitau, Suhaid, Selimbau, Silat Hilir, Silat Hulu dll.
* Wilayah Khusus Meliputi: Adalah Wilayah Diluar Wilayah I - IV (Kondisi Transportasi Sulit).
Wilayah ini sesuai dengan kondisi daerah seperti : Tanjung Lokang, Beberuk, Sepan padang, Sauk, Semalah, Tempurau, Rantau Bumbun dll.
BAHAN PENGISI
1 Batu Gunung Quary m3 M_010 140,000.00 < 30 200,000.00 340,000.00 0.00 0.00 340,000.00
2 Batu Gunung Quary m3 M_010.a 140,000.00 < 20 92,000.00 232,000.00 0.00 0.00 232,000.00
3 Batu Gunung Quary m3 M_010.b 140,000.00 < 10 54,000.00 194,000.00 0.00 0.00 194,000.00
4 Kerikil dari galian bukit m3 M_011 80,000.00 < 30 200,000.00 280,000.00 0.00 0.00 280,000.00
5 Kerikil Sungai ( Leveransir ) m3 M_012 105,000.00 < 20 92,000.00 197,000.00 0.00 0.00 197,000.00
6 Kerikil Sungai ( Royality ) m3 M_013 80,000.00 - - 80,000.00 0.00 0.00 80,000.00
7 Batu kali m3 M_014 130,000.00 < 20 92,000.00 222,000.00 0.00 0.00 222,000.00
8 Kerikil sungai ayak tanpa pasir (1-2 cm) m3 M_015 115,000.00 < 20 92,000.00 207,000.00 0.00 0.00 207,000.00
9 Kerikil sungai ayak tanpa pasir (2-3 cm) m3 M_015.a 100,000.00 < 20 92,000.00 192,000.00 0.00 0.00 192,000.00
10 Batu pecah gunung (10 - 15 cm) m3 M_021 250,000.00 < 30 200,000.00 450,000.00 0.00 0.00 450,000.00
11 Batu pecah gunung (7 - 10 cm) m3 M_022 375,000.00 < 30 200,000.00 575,000.00 0.00 0.00 575,000.00
12 Batu pecah gunung (5 - 7 cm.) m3 M_023 475,000.00 < 30 200,000.00 675,000.00 0.00 0.00 675,000.00
13 Batu pecah gunung (3 - 5 cm.) m3 M_024 525,000.00 < 30 200,000.00 725,000.00 0.00 0.00 725,000.00
14 Batu pecah gunung (2 - 3 cm.) m3 M_025 575,000.00 < 30 200,000.00 775,000.00 0.00 0.00 775,000.00
15 Batu pecah gunung (1 - 2 cm.) m3 M_026 625,000.00 < 30 200,000.00 825,000.00 0.00 0.00 825,000.00
16 Batu pecah gunung (0,5 - 1 cm.) m3 M_027 775,000.00 < 30 200,000.00 975,000.00 0.00 0.00 975,000.00
17 Batu pecah sungai (3 - 5 cm.) m3 M_028 425,000.00 < 30 200,000.00 625,000.00 0.00 0.00 625,000.00
18 Batu pecah sungai (2 - 3 cm.) m3 M_029 475,000.00 < 30 200,000.00 675,000.00 0.00 0.00 675,000.00
19 Batu pecah sungai (1 - 2 cm.) m3 M_030 525,000.00 < 30 200,000.00 725,000.00 0.00 0.00 725,000.00
20 Batu pecah sungai (0,5 - 1 cm.) m3 M_031 625,000.00 < 30 200,000.00 825,000.00 0.00 0.00 825,000.00
21 Pasir urug / timbun m3 M_040 80,000.00 < 20 92,000.00 172,000.00 0.00 0.00 172,000.00
22 Pasir ayak untuk beton m3 M_041 95,000.00 < 20 92,000.00 187,000.00 0.00 0.00 187,000.00
23 Sirtu Sungai ( Leveransir ) m3 M_042 95,000.00 < 10 92,000.00 187,000.00 0.00 0.00 187,000.00
24 Sirtu Sungai ( Royality ) m3 M_043 80,000.00 - - 80,000.00 0.00 0.00 80,000.00
25 Bahan timbunan pilihan (laterit) Leveransir m3 M_050 45,000.00 < 20 92,000.00 137,000.00 0.00 0.00 137,000.00
26 Bahan timbunan pilihan (laterit) Setempat m3 M_051 40,000.00 - - 40,000.00 0.00 0.00 40,000.00
27 Timbunan setempat ( tanah biasa) m3 M_052 10,000.00 - - 10,000.00 0.00 0.00 10,000.00
28 Aspal Bitument Kg. M_061 10,000.00 >100 800.00 10,800.00 0.00 0.00 10,800.00
29 Semen Portlant ( PC ) 50 Kg. M_080 125,000.00 < 10 2,000.00 127,000.00 0.00 0.00 127,000.00
30 Semen Portlant ( PC ) Kg M_080.a 2,500.00 < 10 40.00 2,540.00 0.00 0.00 2,540.00
31 Semen Warna (Oker) Kg M_080.b 15,000.00 100 40.00 15,040.00 0.00 0.00 15,040.00
32 Paving blok BH M_082 3,000.00 < 10 200.00 3,200.00 0.00 0.00 3,200.00
33 Bataco Ukuran 15 x 30 x 7 cm Buah M_239 2,500.00 < 10 200.00 2,700.00 0.00 0.00 2,700.00
34 Bataco Ukuran 20 x 40 x 7 cm Buah M_239.a 3,000.00 < 10 200.00 3,200.00 0.00 0.00 3,200.00
35 Bataco Ukuran 20 x 40 x 9 cm Buah M_239.b 3,250.00 < 10 200.00 3,450.00 0.00 0.00 3,450.00
36 Alat - alat bantu * Set M_171 120,000.00 < 10 5,000.00 125,000.00 0.00 0.00 125,000.00
37 Alat - alat bantu ** Set M_172 200,000.00 < 10 5,000.00 205,000.00 0.00 0.00 205,000.00
38 Alat - alat bantu pek. Latasir *** Set M_173 230,000.00 < 10 5,000.00 235,000.00 0.00 0.00 235,000.00
HARGA DI SUM- JARAK ONGKOS JUMLAH PAJAK JUMLAH HARGA
BER/QUARY ANGKUT ANGKUT HARGA Profit 10 % GALIAN - C TERMASUK
NO MATERIAL UNIT KODE
(TANPA PAJAK) RATA-RATA PER UNIT TANPA PAJAK ( Rp ) ( 10 % ) PAJAK
( Rp ) ( Km ) ( Rp ) ( Rp ) ( Rp ) ( Rp )
39 Gerobak + kuali aspal Set M_174 6,000,000.00 < 10 250,000.00 6,250,000.00 0.00 0.00 6,250,000.00
HARGA DI SUM- JARAK ONGKOS JUMLAH PAJAK JUMLAH HARGA
BER/QUARY ANGKUT ANGKUT HARGA Profit 10 % GALIAN - C TERMASUK
NO MATERIAL UNIT KODE
(TANPA PAJAK) RATA-RATA PER UNIT TANPA PAJAK ( Rp ) ( 10 % ) PAJAK
( Rp ) ( Km ) ( Rp ) ( Rp ) ( Rp ) ( Rp )
BAHAN MINYAK
40 Minyak Tanah Ltr. M_065 7,000.00 >100 600.00 7,600.00 0.00 0.00 7,600.00
41 Minyak Diesel Ltr. M_183 13,100.00 >100 600.00 13,700.00 0.00 0.00 13,700.00
42 Premium / Bensin Ltr. M_184 11,000.00 >100 600.00 11,600.00 0.00 0.00 11,600.00
43 Minyak Pelumas Ltr. M_185 30,000.00 >100 600.00 30,600.00 0.00 0.00 30,600.00
44 Minyak Thinner Ltr M - 203 20,000.00 > 100 500.00 20,500.00 0.00 0.00 20,500.00
45 Minyak Bekesting / Cetakan Ltr M - 203.a 7,000.00 >100 300.00 7,300.00 0.00 0.00 7,300.00
BAHAN CAT
46 Cat Jembatan Kg M_090 120,000.00 10 500.00 120,500.00 0.00 0.00 120,500.00
47 Cat Dasar Kg. M_187 45,000.00 10 600.00 45,600.00 0.00 0.00 45,600.00
48 Alkali Kg - 54,000.00 10 300.00 54,300.00 0.00 0.00 54,300.00
49 Teer Kg. M_188 10,000.00 10 600.00 10,600.00 0.00 0.00 10,600.00
50 Cat Kilap Kg. M_193 55,000.00 10 600.00 55,600.00 0.00 0.00 55,600.00
51 Cat Galvanis Kg M - 202 45,000.00 > 100 6,000.00 51,000.00 0.00 0.00 51,000.00
52 Dempul Kg M_230 35,000.00 10 100.00 35,100.00 0.00 0.00 35,100.00
53 Plamur Kg M_231 35,000.00 10 100.00 35,100.00 0.00 0.00 35,100.00
54 Amplas Lbr M_232 3,000.00 10 100.00 3,100.00 0.00 0.00 3,100.00
55 Cat Tembok Kualitas Biasa Kg M_233 10,000.00 10 100.00 10,100.00 0.00 0.00 10,100.00
56 Cat Tembok Kualitas Sedang Kg M_233.a 17,225.00 10 100.00 17,325.00 0.00 0.00 17,325.00
57 Cat Tembok Weather Shield Kg M_233.b 110,000.00 10 100.00 110,100.00 0.00 0.00 110,100.00
58 Cat Vernis Liter M_233.a 50,000.00 10 100.00 50,100.00 0.00 0.00 50,100.00
59 Cat Melamic Kg M_233.b 60,000.00 10 100.00 60,100.00 0.00 0.00 60,100.00
60 Cat Meni Besi Kg M_233.c 27,000.00 10 100.00 27,100.00 0.00 0.00 27,100.00
61 Cat Meni Atap Kg M_233.d 30,000.00 10 100.00 30,100.00 0.00 0.00 30,100.00
62 Cat Tembok Interior Kg M_233.e 100,000.00 10 100.00 100,100.00 0.00 0.00 100,100.00
63 Cat Tembok Eksterior (Anti Jamur) Kg M_233.f 110,000.00 10 100.00 110,100.00 0.00 0.00 110,100.00
64 Cat Water Proofing Kg M_233.g 55,000.00 10 100.00 55,100.00 0.00 0.00 55,100.00
65 Soda Api Kg M_234 41,000.00 10 100.00 41,100.00 0.00 0.00 41,100.00
66 Sabun Kg M_235 5,000.00 10 100.00 5,100.00 0.00 0.00 5,100.00
67 Kuas Cat Buah M_236 20,000.00 10 100.00 20,100.00 0.00 0.00 20,100.00
BAHAN BESI & BAJA
68 Baja Tralis Kg. M_161 20,000.00 10 600.00 20,600.00 0.00 0.00 20,600.00
69 Kawat Bronjong Galvanis uk. 2.0 x 1.0 x 0.5 dia. 3 mm Unit M_162 640,000.00 >100 6,000.00 646,000.00 0.00 0.00 646,000.00
70 Kawat Bronjong Galvanis Kg. M_162. a 35,000.00 >100 600.00 35,600.00 0.00 0.00 35,600.00
71 Kawat Bronjong Galvanis Lapis PVC Kg. M_162. b 70,000.00 >100 600.00 70,600.00 0.00 0.00 70,600.00
72 Kawat las Kg. M_162 c 27,000.00 100 6,000.00 33,000.00 0.00 0.00 33,000.00
73 Kawat Las Listrik Kg M_162 d 26,000.00 100 6,000.00 32,000.00 0.00 0.00 32,000.00
74 Paku Jembatan Kg. M_166 30,000.00 100 600.00 30,600.00 0.00 0.00 30,600.00
75 Baut Baja Kg. M_163 30,000.00 >100 6,000.00 36,000.00 0.00 0.00 36,000.00
76 Besi Galvanis sandaran jembatan btg M_164 620,000.00 100 6,000.00 626,000.00 0.00 0.00 626,000.00
77 Baja Konstruksi (rangka baja Jembatan) Kg. M_165 30,000.00 >100 6,000.00 36,000.00 0.00 0.00 36,000.00
78 Baja Beton U.24 Tulangan Polos dan Ulir Kg. M_167 22,000.00 100 600.00 22,600.00 0.00 0.00 22,600.00
79 Baja Beton U.32 Tulangan Polos dan Ulir Kg. M_167. a 23,000.00 100 600.00 23,600.00 0.00 0.00 23,600.00
80 Wire Mash M5 Kg. M_167. b 28,300.00 100 600.00 28,900.00 0.00 0.00 28,900.00
81 Wire Mash M6 Kg. M_167. c 37,100.00 100 600.00 37,700.00 0.00 0.00 37,700.00
82 Kawat Bindrat / Kawat Ikat Kg. M_170 25,000.00 100 600.00 25,600.00 0.00 0.00 25,600.00
83 Beugel tebal plat 5 mm Bh. M_186 25,000.00 10 600.00 25,600.00 0.00 0.00 25,600.00
84 Baut Panjang (15 - 30 cm) Btg. M_189 7,500.00 10 600.00 8,100.00 0.00 0.00 8,100.00
85 Paku Baut 15 cm Btg. M. 189.A 5,000.00 10 600.00 5,600.00 0.00 0.00 5,600.00
86 Baut Pendek (4 - 12 cm) Btg. M_190 2,000.00 10 600.00 2,600.00 0.00 0.00 2,600.00
87 Klem spore plank Btg. M_194 30,000.00 10 600.00 30,600.00 0.00 0.00 30,600.00
88 Pipa baja tiang pancang Kg. M_197 21,000.00 100 6,000.00 27,000.00 0.00 0.00 27,000.00
89 Sepatu besi untuk pancang kayu Bh M_198 250,000.00 6,000.00 256,000.00 0.00 0.00 256,000.00
90 Baja konstruksi WF berbagai Ukuran: Kg M - 199 30,000.00 > 100 6,000.00 36,000.00 0.00 0.00 36,000.00
91 Besi plat Uk berbagai Ukuran Kg M - 200 30,000.00 > 100 6,000.00 36,000.00 0.00 0.00 36,000.00
92 Baja Kanal ( C ) Berbagai ukuran Kg M - 201 30,000.00 > 100 6,000.00 36,000.00 0.00 0.00 36,000.00
93 Besi Profil CNP 125.50.20.3,2 Kg M - 201 42,900.00 > 100 6,000.00 48,900.00 0.00 0.00 48,900.00
94 Besi Profil Siku Kg - 33,000.00 > 100 6,000.00 39,000.00 0.00 0.00 39,000.00
95 Besi Profil Hollow Kg - 32,000.00 > 100 6,000.00 38,000.00 0.00 0.00 38,000.00
96 Kusen Alumunium Uk. 5/5 cm Warna Silver m1 - 143,000.00 > 100 6,000.00 149,000.00 0.00 0.00 149,000.00
97 Kusen Alumunium Uk. 4/8 cm Warna Silver m1 - 115,000.00 > 100 6,000.00 121,000.00 0.00 0.00 121,000.00
98 Kusen Alumunium Uk. 5/10 cm Warna Silver m1 - 155,000.00 > 100 6,000.00 161,000.00 0.00 0.00 161,000.00
99 Kusen Alumunium Uk. 5/12 cm Warna Silver m1 - 137,500.00 > 100 6,000.00 143,500.00 0.00 0.00 143,500.00
100 Kusen Alumunium Ambang Uk. 3,5/5 cm Warna Silver m1 - 135,850.00 > 100 6,000.00 141,850.00 0.00 0.00 141,850.00
101 Sunscreen Alumunium Lebar 7,5 cm m2 - 1,200,000.00 > 100 6,000.00 1,206,000.00 0.00 0.00 1,206,000.00
102 Sunscreen Alumunium Lebar 13,5 cm m2 - 1,870,000.00 > 100 6,000.00 1,876,000.00 0.00 0.00 1,876,000.00
103 Kawat Simpai Kg M_237 17,000.00 10 200.00 17,200.00 0.00 0.00 17,200.00
104 Kawat Waring Kualitas Baik m1 M_237.a 7,000.00 10 200.00 7,200.00 0.00 0.00 7,200.00
105 Kawat Waring Kualitas Biasa m1 M_237.b 5,000.00 10 200.00 5,200.00 0.00 0.00 5,200.00
106 Kawat Duri Kg M_238 20,000.00 10 200.00 20,200.00 0.00 0.00 20,200.00
107 Paku Campuran Kg M_241 25,000.00 10 200.00 25,200.00 0.00 0.00 25,200.00
108 Paku Triplek Kg M_241.a 40,000.00 10 200.00 40,200.00 0.00 0.00 40,200.00
109 Paku Seng / Belian Kg M_241.b 30,000.00 10 200.00 30,200.00 0.00 0.00 30,200.00
HARGA DI SUM- JARAK ONGKOS JUMLAH PAJAK JUMLAH HARGA
BER/QUARY ANGKUT ANGKUT HARGA Profit 10 % GALIAN - C TERMASUK
NO MATERIAL UNIT KODE
(TANPA PAJAK) RATA-RATA PER UNIT TANPA PAJAK ( Rp ) ( 10 % ) PAJAK
( Rp ) ( Km ) ( Rp ) ( Rp ) ( Rp ) ( Rp )
110 Sekrup Kg M_242 8,000.00 10 200.00 8,200.00 0.00 0.00 8,200.00
111 Sekrup Fixer Buah - 1,000.00 10 200.00 1,200.00 0.00 0.00 1,200.00
112 Sealant Tube - 45,000.00 10 200.00 45,200.00 0.00 0.00 45,200.00
113 Besi Strip Btg M_243 15,000.00 10 2,000.00 17,000.00 0.00 0.00 17,000.00
HARGA DI SUM- JARAK ONGKOS JUMLAH PAJAK JUMLAH HARGA
BER/QUARY ANGKUT ANGKUT HARGA Profit 10 % GALIAN - C TERMASUK
NO MATERIAL UNIT KODE
(TANPA PAJAK) RATA-RATA PER UNIT TANPA PAJAK ( Rp ) ( 10 % ) PAJAK
( Rp ) ( Km ) ( Rp ) ( Rp ) ( Rp ) ( Rp )
114 Kabel / Seling 1" m1 M_245 80,000.00 > 100 3,000.00 83,000.00 0.00 0.00 83,000.00
115 Kabel / Seling 1/2" m1 M_245.a 19,500.00 > 100 3,000.00 22,500.00 0.00 0.00 22,500.00
116 Kabel / Seling 1/4" m1 M_245.b 10,000.00 > 100 1,000.00 11,000.00 0.00 0.00 11,000.00
117 Kabel Baja Pengaku dia. 19 mm m1 M - 246 37,500.00 > 100 3,000.00 40,500.00 0.00 0.00 40,500.00
118 Seling BaJa Dia. 1,5 " m1 M - 247 190,000.00 > 100 3,000.00 193,000.00 0.00 0.00 193,000.00
119 Seling Baja Dia. 2,5 " m1 M - 247.a 200,000.00 > 100 3,000.00 203,000.00 0.00 0.00 203,000.00
120 Katrol Set M - 248 1,750,000.00 > 100 20,000.00 1,770,000.00 0.00 0.00 1,770,000.00
121 Warfel 2" Buah M - 249 650,000.00 > 100 5,000.00 655,000.00 0.00 0.00 655,000.00
122 Warfel 1/2" Buah M - 249.a 17,500.00 > 100 5,000.00 22,500.00 0.00 0.00 22,500.00
123 Warfel 19 mm Buah M - 249.b 30,500.00 > 100 5,000.00 35,500.00 0.00 0.00 35,500.00
124 Cekak 1,5" Buah - 45,000.00 > 100 2,000.00 47,000.00 0.00 0.00 47,000.00
125 Cekak 1" Buah M - 250 20,000.00 > 100 2,000.00 22,000.00 0.00 0.00 22,000.00
126 Cekak 1/2" Buah M - 250.a 5,000.00 > 100 2,000.00 7,000.00 0.00 0.00 7,000.00
127 Cekak 1/4" Buah M - 250.b 4,500.00 > 100 750.00 5,250.00 0.00 0.00 5,250.00
128 Cekak seling 19 mm Buah M - 251 11,000.00 > 100 2,000.00 13,000.00 0.00 0.00 13,000.00
129 Accesoris Plat Penggantung Buah - 57,500.00 10 600.00 58,100.00 0.00 0.00 58,100.00
BAHAN KAYU
130 Kayu Bakar m3 M_070 80,000.00 10 155,000.00 235,000.00 0.00 0.00 235,000.00
131 Kayu bulat untuk turap panjang 2 m Btg M_175 7,000.00 10 500.00 7,500.00 0.00 0.00 7,500.00
132 Kayu Bulat Untuk Turap Panjang 4 - 4,5 m Btg M_176 12,000.00 10 1,100.00 13,100.00 0.00 0.00 13,100.00
133 Kayu untuk Perancah m3 M_180 800,000.00 10 155,000.00 955,000.00 0.00 0.00 955,000.00
134 Kayu Konstruksi Jembatan (Kayu Belian Uk. 15/15 cm) m3 M_181 9,523,000.00 > 100 528,500.00 10,051,500.00 0.00 0.00 10,051,500.00
135 Kayu Konstruksi Jembatan (Kayu Kelas I Uk. 15/15 cm) m3 M_191 4,320,000.00 > 100 528,500.00 4,848,500.00 0.00 0.00 4,848,500.00
136 Papan Lantai Jembatan Kelas I Uk. 4/18-4,20 m m3 M_191.g 3,858,000.00 > 100 528,500.00 4,386,500.00 0.00 0.00 4,386,500.00
137 Papan Lantai Jembatan Kelas I Uk. 4/18-3,60 m m3 M_191.h 3,858,000.00 > 100 528,500.00 4,386,500.00 0.00 0.00 4,386,500.00
138 Kayu Tembesu m3 M_195 3,750,000.00 > 100 528,500.00 4,278,500.00 0.00 0.00 4,278,500.00
139 Kayu Belian Panjang ≥ 2,5 m (Ketam) m3 M_181.a 10,686,000.00 > 100 528,500.00 11,214,500.00 0.00 0.00 11,214,500.00
140 Kayu Belian Panjang ≥ 2,5 m (Tidak Ketam) m3 M_181.b 10,489,000.00 > 100 528,500.00 11,017,500.00 0.00 0.00 11,017,500.00
141 Kayu Belian Panjang < 2,5 m (Ketam) m3 M_181.c 9,227,000.00 > 100 528,500.00 9,755,500.00 0.00 0.00 9,755,500.00
142 Kayu Belian Panjang < 2,5 m (Tidak Ketam) m3 M_181.d 8,878,000.00 > 100 528,500.00 9,406,500.00 0.00 0.00 9,406,500.00
143 Kayu Klas I Tekam (Ketam) m3 M_191.a 3,209,000.00 > 100 528,500.00 3,737,500.00 0.00 0.00 3,737,500.00
144 Kayu Klas I Tekam (Tidak Ketam) m3 M_191.b 3,008,000.00 > 100 528,500.00 3,536,500.00 0.00 0.00 3,536,500.00
145 Kayu Klas I Selain Tekam (Ketam) m3 M_191.c 2,806,000.00 > 100 528,500.00 3,334,500.00 0.00 0.00 3,334,500.00
146 Kayu Klas I Selain Tekam (Tidak Ketam) m3 M_191.d 2,609,000.00 > 100 528,500.00 3,137,500.00 0.00 0.00 3,137,500.00
147 Kayu Klas II, Kawi Danau (Ketam) m3 M_192.c 2,000,000.00 > 100 528,500.00 2,528,500.00 0.00 0.00 2,528,500.00
148 Kayu Klas II, Kawi Danau(Tidak Ketam) m3 M_192.d 1,799,000.00 > 100 528,500.00 2,327,500.00 0.00 0.00 2,327,500.00
149 Kayu Klas II, Selain Kawi Danau (Ketam) m3 M_192 1,798,000.00 > 100 528,500.00 2,326,500.00 0.00 0.00 2,326,500.00
150 Kayu Klas II. Selain Kawi Danau (Tidak Ketam) m3 M_192.a 1,597,000.00 > 100 528,500.00 2,125,500.00 0.00 0.00 2,125,500.00
151 Kayu Klas III (Ketam) m3 M_213 1,560,000.00 > 100 528,500.00 2,088,500.00 0.00 0.00 2,088,500.00
152 Kayu Klas III (Tidak Ketam) m3 M_213.a 1,493,000.00 > 100 528,500.00 2,021,500.00 0.00 0.00 2,021,500.00
153 Papan Kayu Belian (Ketam) m3 M_181.c 11,100,000.00 > 100 528,500.00 11,628,500.00 0.00 0.00 11,628,500.00
154 Papan Kayu Belian (Tidak Ketam) m3 M_181.d 10,500,000.00 > 100 528,500.00 11,028,500.00 0.00 0.00 11,028,500.00
155 Papan Kayu Klas I, Tekam (Ketam) m3 M_191.e 5,770,000.00 > 100 578,500.00 6,348,500.00 0.00 0.00 6,348,500.00
156 Papan Kayu Klas I, Tekam (Tidak Ketam) m3 M_191.f 5,340,000.00 > 100 578,500.00 5,918,500.00 0.00 0.00 5,918,500.00
157 Papan Kayu Klas I, Selain Tekam (Ketam) m3 M_191.g 5,340,000.00 > 100 578,500.00 5,918,500.00 0.00 0.00 5,918,500.00
158 Papan Kayu Klas I, Selain Tekam (Tidak Ketam) m3 M_191.h 4,910,000.00 > 100 578,500.00 5,488,500.00 0.00 0.00 5,488,500.00
159 Papan Kayu Klas II, Kawi (Ketam) m3 M_192.e 3,836,000.00 10 578,500.00 4,414,500.00 0.00 0.00 4,414,500.00
160 Papan Kayu Klas II Kawi (Tidak Ketam) m3 M_192.f 3,406,000.00 10 578,500.00 3,984,500.00 0.00 0.00 3,984,500.00
161 Papan Kayu Klas II Selain Kawi (Ketam) m3 M_192.g 2,777,000.00 10 578,500.00 3,355,500.00 0.00 0.00 3,355,500.00
162 Papan Kayu Klas II Selain Kawi (Tidak Ketam) m3 M_192.h 2,347,000.00 10 578,500.00 2,925,500.00 0.00 0.00 2,925,500.00
163 Papan Kayu Klas III (Campuran) m3 M_213.b 1,388,000.00 10 578,500.00 1,966,500.00 0.00 0.00 1,966,500.00
164 Tiang Tongkat Kayu Belian Uk. 9/9 - 4,20 M Btg M_181.g 320,000.00 <10 15,000.00 335,000.00 0.00 0.00 335,000.00
165 Tiang Tongkat Kayu Belian Uk. 9/9 - 3,60 M Btg M_181.h 312,000.00 <10 13,000.00 325,000.00 0.00 0.00 325,000.00
166 Tiang Tongkat Kayu Belian Uk. 9/9 - 3,20 M Btg M_181.i 289,000.00 <10 11,000.00 300,000.00 0.00 0.00 300,000.00
167 Tiang Tongkat Kayu Belian Uk. 9/9 - 2,70 M Btg M_181.j 240,500.00 <10 9,500.00 250,000.00 0.00 0.00 250,000.00
168 Tiang Tongkat Kayu Belian Uk. 9/9 - 2,50 M Btg M_181.k 226,500.00 <10 8,700.00 235,200.00 0.00 0.00 235,200.00
169 Tiang Tongkat Kayu Belian Uk. 9/9 - 2,20 M Btg M_181.l 184,300.00 <10 7,700.00 192,000.00 0.00 0.00 192,000.00
170 Tiang Tongkat Kayu Belian Uk. 9/9 - 2,10 M Btg M_181.m 177,000.00 <10 7,400.00 184,400.00 0.00 0.00 184,400.00
171 Tiang Tongkat Kayu Belian Uk. 9/9 - 1,80 M Btg M_181.n 143,700.00 <10 6,300.00 150,000.00 0.00 0.00 150,000.00
172 Tiang Tongkat Kayu Belian Uk. 9/9 - 1,50 M Btg M_181.o 89,900.00 <10 5,300.00 95,200.00 0.00 0.00 95,200.00
173 Renglat Btg M_215 9,000.00 10 300.00 9,300.00 0.00 0.00 9,300.00
174 Laci Kayu Belian 5/10 - 80 cm Btg M_181.e 9,300.00 10 300.00 9,600.00 0.00 0.00 9,600.00
175 Laci Kayu Belian 9/9 - 80 cm Btg M_181.f 14,500.00 10 1,000.00 15,500.00 0.00 0.00 15,500.00
176 Laci Kayu Belian 4/8 - 60 cm Btg M_181.g 8,500.00 10 300.00 8,800.00 0.00 0.00 8,800.00
177 Alas Kayu Hutan Btg M_216 6,500.00 10 300.00 6,800.00 0.00 0.00 6,800.00
178 Alas Laci Kayu Belian 4/8-60 cm Btg M_216.a 8,500.00 10 300.00 8,800.00 0.00 0.00 8,800.00
179 Konsul Kayu Klas I Buah M_217 85,000.00 10 10,000.00 95,000.00 0.00 0.00 95,000.00
180 Triplek 3 mm Lbr M_218 60,000.00 10 300.00 60,300.00 0.00 0.00 60,300.00
181 Triplek 3 mm m2 M_218.a 20,155.87 10 100.78 20,256.65 0.00 0.00 20,256.65
182 Triplek 6 mm Lbr M_218.b 145,000.00 10 300.00 145,300.00 0.00 0.00 145,300.00
183 Triplek 9 mm Lbr M_218.c 240,000.00 10 3,000.00 243,000.00 0.00 0.00 243,000.00
184 Triplek 12 mm Lbr M_218.d 300,000.00 10 3,000.00 303,000.00 0.00 0.00 303,000.00
185 Plywood 4' x 8' x 4 mm Lbr M_218.e 76,000.00 10 3,000.00 79,000.00 0.00 0.00 79,000.00
HARGA DI SUM- JARAK ONGKOS JUMLAH PAJAK JUMLAH HARGA
BER/QUARY ANGKUT ANGKUT HARGA Profit 10 % GALIAN - C TERMASUK
NO MATERIAL UNIT KODE
(TANPA PAJAK) RATA-RATA PER UNIT TANPA PAJAK ( Rp ) ( 10 % ) PAJAK
( Rp ) ( Km ) ( Rp ) ( Rp ) ( Rp ) ( Rp )
186 Lem Kayu ltr M_219 40,000.00 10 500.00 40,500.00 0.00 0.00 40,500.00
187 Lem Kuning ltr M_219.a 47,000.00 10 500.00 47,500.00 0.00 0.00 47,500.00
188 List Kayu Profil m' M_220 12,000.00 10 500.00 12,500.00 0.00 0.00 12,500.00
HARGA DI SUM- JARAK ONGKOS JUMLAH PAJAK JUMLAH HARGA
BER/QUARY ANGKUT ANGKUT HARGA Profit 10 % GALIAN - C TERMASUK
NO MATERIAL UNIT KODE
(TANPA PAJAK) RATA-RATA PER UNIT TANPA PAJAK ( Rp ) ( 10 % ) PAJAK
( Rp ) ( Km ) ( Rp ) ( Rp ) ( Rp ) ( Rp )
189 Kayu Profil List Plafond m' M_221 6,500.00 10 500.00 7,000.00 0.00 0.00 7,000.00
190 Gypsum Profil List Plafond / Cornice m1 - 30,000.00 10 500.00 30,500.00 0.00 0.00 30,500.00
191 Gypsum Board Tebal 4 mm Lbr M_222 84,000.00 10 3,000.00 87,000.00 0.00 0.00 87,000.00
192 GRC Board Tebal 4 mm Lbr M_223 74,000.00 10 2,500.00 76,500.00 0.00 0.00 76,500.00
193 Aklirik Tebal 6 mm Uk. 120 x 240 cm Lbr - 929,500.00 10 2,500.00 932,000.00 0.00 0.00 932,000.00
194 Papan Profil /Lambriziring m3 - 4,004,000.00 10 500,000.00 4,504,000.00 0.00 0.00 4,504,000.00
195 Papan Lambrizing Tebal 9 mm Lbr - 163,000.00 10 3,000.00 166,000.00 0.00 0.00 166,000.00
196 Sungkai Tebal 3 mm, Uk. 120 x 240 cm m2 - 81,500.00 10 500.00 82,000.00 0.00 0.00 82,000.00
197 List Plafond Ukiran Kayu Kelas I Lebar 70 cm m1 - 550,500.00 10 500.00 551,000.00 0.00 0.00 551,000.00
BAHAN SANITASI
198 Talang Gantung & Talang Tegak m1 M_229 95,000.00 10 500.00 95,500.00 0.00 0.00 95,500.00
199 Pipa Suling Dia. 3/4" Buah M - 253 20,000.00 10 100.00 20,100.00 0.00 0.00 20,100.00
200 Pipa Galvanis Dia. 2" m' M - 253.a 155,000.00 > 100 1,500.00 156,500.00 0.00 0.00 156,500.00
201 Pipa Galvanis Dia. 4" m' M - 253.b 550,500.00 > 100 10,000.00 560,500.00 0.00 0.00 560,500.00
202 Pipa Galvanis Dia. 6" m' M - 253.c 829,500.00 > 100 10,000.00 839,500.00 0.00 0.00 839,500.00
203 Pipa Spiral Dia. 4 m' - 415,000.00 > 100 10,000.00 425,000.00 0.00 0.00 425,000.00
204 Kloset Duduk Buah M - 254 1,375,000.00 > 100 30,000.00 1,405,000.00 0.00 0.00 1,405,000.00
205 Kloset Jongkok Buah M - 254.a 180,000.00 10 15,000.00 195,000.00 0.00 0.00 195,000.00
206 Urinoir Buah M - 255 552,900.00 > 100 25,000.00 577,900.00 0.00 0.00 577,900.00
207 Wastafel Buah M - 256 650,000.00 > 100 20,000.00 670,000.00 0.00 0.00 670,000.00
208 Seal Tape Gypsum Buah M - 257 30,000.00 10 100.00 30,100.00 0.00 0.00 30,100.00
209 Floor Drain Buah M - 258 65,000.00 10 300.00 65,300.00 0.00 0.00 65,300.00
210 Kran Air Kualitas Biasa Buah M - 259 15,000.00 10 300.00 15,300.00 0.00 0.00 15,300.00
211 Kran Air Kualitas Baik Buah M - 259. a 40,000.00 10 300.00 40,300.00 0.00 0.00 40,300.00
212 Kran Air Stainless Ø 1/2" Buah M - 259. a 47,000.00 10 300.00 47,300.00 0.00 0.00 47,300.00
213 Penguras Bak Air Ø 3/4" Buah - 15,000.00 10 300.00 15,300.00 0.00 0.00 15,300.00
214 Seal Tape Kran Buah M - 260 3,000.00 10 100.00 3,100.00 0.00 0.00 3,100.00
215 Tempat Sabun Porcelain (Keramik) Terpasang Buah - 60,000.00 10 100.00 60,100.00 0.00 0.00 60,100.00
216 Centong Air Kualitas Biasa Buah - 15,000.00 10 100.00 15,100.00 0.00 0.00 15,100.00
217 Centong Air Kualitas Baik Buah - 25,000.00 10 100.00 25,100.00 0.00 0.00 25,100.00
218 Bak Air Fiber Glass 0,50 M3 Buah M - 261 1,200,000.00 > 100 50,000.00 1,250,000.00 0.00 0.00 1,250,000.00
219 Bak Air Fiber Glass 0,75 M3 Buah M - 261.a 1,500,000.00 > 100 50,000.00 1,550,000.00 0.00 0.00 1,550,000.00
220 Bak Air Fiber Glass 0,80 M3 Buah M - 261.b 1,600,000.00 > 100 50,000.00 1,650,000.00 0.00 0.00 1,650,000.00
221 Bak Air Fiber Glass 1 M3 Buah M - 261.c 2,000,000.00 > 100 50,000.00 2,050,000.00 0.00 0.00 2,050,000.00
222 Bak Air Fiber Glass 2 M3 Buah M - 261.d 2,650,000.00 > 100 75,000.00 2,725,000.00 0.00 0.00 2,725,000.00
223 Bak Air Fiber Glass 1,5 M3 Buah M - 261.e 3,350,000.00 > 100 100,000.00 3,450,000.00 0.00 0.00 3,450,000.00
224 Bak Air Fiber Glass 3 M3 Buah M - 261.f 4,150,000.00 > 100 100,000.00 4,250,000.00 0.00 0.00 4,250,000.00
225 Bak Air Fiber Glass 5 M3 Buah M - 261.g 5,000,000.00 > 100 100,000.00 5,100,000.00 0.00 0.00 5,100,000.00
226 Septic Tank Type ST24 0,75 M3 Buah - 3,410,000.00 > 100 100,000.00 3,510,000.00 0.00 0.00 3,510,000.00
227 Septic Tank Type ST46 1,30 M3 Buah - 4,510,000.00 > 100 100,000.00 4,610,000.00 0.00 0.00 4,610,000.00
228 Septic Tank Type ST68 1,55 M3 Buah - 5,390,000.00 > 100 100,000.00 5,490,000.00 0.00 0.00 5,490,000.00
BAHAN ATAP
229 Seng Gelombang BJLS 0,20 Lbr M_224 42,000.00 10 500.00 42,500.00 0.00 0.00 42,500.00
230 Seng Gelombang BJLS 0,20 m2 M_224.a 32,812.50 10 390.63 33,203.13 0.00 0.00 33,203.13
231 Seng Gelombang BJLS 0,30 Lbr M_224.b 65,000.00 10 500.00 65,500.00 0.00 0.00 65,500.00
232 Seng Gelombang BJLS 0,30 m2 M_224.c 50,781.25 10 390.63 51,171.88 0.00 0.00 51,171.88
233 Seng Gelombang Warna BJLS 0,25 Lbr M_224.d 55,000.00 10 500.00 55,500.00 0.00 0.00 55,500.00
234 Plat Aluminium Warna BJLS 0,25 Lbr - 65,000.00 10 500.00 65,500.00 0.00 0.00 65,500.00
235 Genteng Metal Type PRIMA 0,35 Lbr M_225 37,000.00 10 500.00 37,500.00 0.00 0.00 37,500.00
236 Genteng Metal Type ROYAL 0,35 Lbr M_225.a 37,000.00 10 500.00 37,500.00 0.00 0.00 37,500.00
237 Genteng Metal Type CLASSIC 0,35 Lbr M_225.b 37,000.00 10 500.00 37,500.00 0.00 0.00 37,500.00
238 Zincalume BJLS 0,3 Polos m2 M_225.d 95,000.00 10 500.00 95,500.00 0.00 0.00 95,500.00
239 Zincalume BJLS 0,3 Color m2 M_225.e 105,000.00 10 500.00 105,500.00 0.00 0.00 105,500.00
240 Zincalume BJLS 0,35 Polos m2 M_225.f 160,200.00 10 500.00 160,700.00 0.00 0.00 160,700.00
241 Zincalume BJLS 0,35 Color m2 M_225.g 174,500.00 10 500.00 175,000.00 0.00 0.00 175,000.00
242 Zincalume BJLS 0,4 Polos m2 M_225.h 165,000.00 10 500.00 165,500.00 0.00 0.00 165,500.00
243 Zincalume BJLS 0,4 Color m2 M_225.i 178,000.00 10 500.00 178,500.00 0.00 0.00 178,500.00
244 Seng Datar Colour BJLS 0,35 Lbr M_227 48,000.00 10 500.00 48,500.00 0.00 0.00 48,500.00
245 Seng Datar Polos BJLS 0,30 Lbr M_227.a 47,500.00 10 500.00 48,000.00 0.00 0.00 48,000.00
246 Zincalume Plat BJLS 0,3 Polos Lbr M_227.b 131,500.00 10 500.00 132,000.00 0.00 0.00 132,000.00
247 Zincalume Plat BJLS 0,3 Color Lbr M_227.c 145,800.00 10 500.00 146,300.00 0.00 0.00 146,300.00
248 Zincalume Plat BJLS 0,35 Polos Lbr M_227.d 160,200.00 10 500.00 160,700.00 0.00 0.00 160,700.00
249 Zincalume Plat BJLS 0,35 Color Lbr M_227.e 175,000.00 10 500.00 175,500.00 0.00 0.00 175,500.00
250 Nok / Bubungan Genteng Metal 1/2 Lingkaran 0,35 Buah M_228 48,000.00 10 500.00 48,500.00 0.00 0.00 48,500.00
251 Roof Light Fiberglass m2 - 362,000.00 10 500.00 362,500.00 0.00 0.00 362,500.00
252 Roof Light Polycarbonat m2 - 356,000.00 10 500.00 356,500.00 0.00 356,500.00
BAHAN KERAMIK
253 Keramik 10 x 20 cm Polos Buah M_240 1,750.00 10 100.00 1,850.00 0.00 0.00 1,850.00
254 Keramik 10 x 33 cm Polos Buah M_240.a 2,500.00 10 100.00 2,600.00 0.00 0.00 2,600.00
255 Keramik 20 x 20 cm Polos Buah M_240.b 2,800.00 10 100.00 2,900.00 0.00 0.00 2,900.00
256 Keramik 20 x 25 cm Polos Buah M_240.c 3,750.00 10 100.00 3,850.00 0.00 0.00 3,850.00
257 Keramik 30 x 30 cm Polos Buah M_240.d 6,250.00 10 100.00 6,350.00 0.00 0.00 6,350.00
258 Keramik 30 x 30 cm Artistik Buah M_240.e 6,300.00 10 100.00 6,400.00 0.00 0.00 6,400.00
HARGA DI SUM- JARAK ONGKOS JUMLAH PAJAK JUMLAH HARGA
BER/QUARY ANGKUT ANGKUT HARGA Profit 10 % GALIAN - C TERMASUK
NO MATERIAL UNIT KODE
(TANPA PAJAK) RATA-RATA PER UNIT TANPA PAJAK ( Rp ) ( 10 % ) PAJAK
( Rp ) ( Km ) ( Rp ) ( Rp ) ( Rp ) ( Rp )
259 Keramik 30 x 30 cm Unpolished Buah M_240.f 6,300.00 10 100.00 6,400.00 0.00 0.00 6,400.00
HARGA DI SUM- JARAK ONGKOS JUMLAH PAJAK JUMLAH HARGA
BER/QUARY ANGKUT ANGKUT HARGA Profit 10 % GALIAN - C TERMASUK
NO MATERIAL UNIT KODE
(TANPA PAJAK) RATA-RATA PER UNIT TANPA PAJAK ( Rp ) ( 10 % ) PAJAK
( Rp ) ( Km ) ( Rp ) ( Rp ) ( Rp ) ( Rp )
260 Keramik 40 x 40 cm Polos Buah M_240.g 15,800.00 10 100.00 15,900.00 0.00 0.00 15,900.00
261 Keramik 40 x 40 cm Anti Gores Buah M_240.h 20,000.00 10 100.00 20,100.00 0.00 0.00 20,100.00
262 Keramik 40 x 40 cm Unpolished Buah M_240.i 16,500.00 10 100.00 16,600.00 0.00 0.00 16,600.00
263 Keramik 60 x 60 cm Anti Gores (Polysed) Buah M_240.j 139,000.00 10 100.00 139,100.00 0.00 0.00 139,100.00
264 Keramik 10 x 10 cm Anti Gores (Polysed) Buah M_240.k 10,000.00 10 100.00 10,100.00 0.00 0.00 10,100.00
265 Keramik List Dinding 10 x 20 cm (Polysed) Buah M_240.l 6,000.00 10 100.00 6,100.00 0.00 0.00 6,100.00
266 Batu Granit m2 - 1,200,000.00 10 100.00 1,200,100.00 0.00 0.00 1,200,100.00
267 Batu Teraso m2 - 200,000.00 10 100.00 200,100.00 0.00 0.00 200,100.00
268 Batu Tempel Hitam (Batu Alam) m2 - 230,000.00 10 100.00 230,100.00 0.00 0.00 230,100.00
269 Batu Andesit m2 - 550,000.00 10 100.00 550,100.00 0.00 0.00 550,100.00
BAHAN KACA
270 Kaca Polos Tebal 3 mm m2 M_244 150,000.00 10 3,000.00 153,000.00 0.00 0.00 153,000.00
271 Kaca Polos Tebal 5 mm m2 M_244.a 170,000.00 10 3,000.00 173,000.00 0.00 0.00 173,000.00
272 Kaca Polos Tebal 8 mm m2 M_244.b 330,000.00 10 3,000.00 333,000.00 0.00 0.00 333,000.00
273 Kaca Polos Tebal 12 mm m2 M_244.c 412,000.00 10 3,000.00 415,000.00 0.00 0.00 415,000.00
274 Kaca Rayben Tebal 5 mm m2 M_244.d 200,000.00 10 3,000.00 203,000.00 0.00 0.00 203,000.00
275 Kaca Cermin Tebal 5 mm m2 M_244.e 275,000.00 10 3,000.00 278,000.00 0.00 0.00 278,000.00
276 Kaca Buram Tebal 5 mm m2 M_244.f 170,500.00 10 3,000.00 173,500.00 0.00 0.00 173,500.00
277 Kaca Setara Asahi Drak Blue Tebal 5 mm (Stopsol) m2 M_244.g 330,000.00 10 3,000.00 333,000.00 0.00 0.00 333,000.00
278 Kaca Setara Asahi Drak Blue Tebal 6 mm (Stopsol) m2 M_244.h 680,000.00 10 3,000.00 683,000.00 0.00 0.00 683,000.00
279 Kaca Setara Asahi Drak Blue Tebal 8 mm (Stopsol) m2 M_244.i 765,000.00 10 3,000.00 768,000.00 0.00 0.00 768,000.00
280 Kaca Setara Asahi Drak Blue Tebal 12 mm (Stopsol) m2 M_244.j 963,000.00 10 3,000.00 966,000.00 0.00 0.00 966,000.00
BAHAN LISTRIK
281 Saklar Ganda Kualitas Biasa Buah M - 262 10,000.00 10 50.00 10,050.00 0.00 0.00 10,050.00
282 Saklar Ganda Kualitas Baik Buah M - 262.a 25,000.00 10 50.00 25,050.00 0.00 0.00 25,050.00
283 Saklar Tunggal Kualitas Biasa Buah M - 262.b 9,000.00 10 50.00 9,050.00 0.00 0.00 9,050.00
284 Saklar Tunggal Kualitas Baik Set M - 262.c 20,000.00 10 50.00 20,050.00 0.00 0.00 20,050.00
285 Stop Kontak Kualitas Biasa Set M - 263 10,000.00 10 50.00 10,050.00 0.00 0.00 10,050.00
286 Stop Kontak Kualitas Baik Set M - 263.a 17,000.00 10 50.00 17,050.00 0.00 0.00 17,050.00
287 Sekring Box / MCB Set M - 264 120,000.00 10 100.00 120,100.00 0.00 0.00 120,100.00
288 Lampu Pijar 40 Watt Set M - 265.a 25,000.00 10 50.00 25,050.00 0.00 0.00 25,050.00
289 Lampu XL 20 Watt Set M - 265.b 45,000.00 10 50.00 45,050.00 0.00 0.00 45,050.00
290 Lampu TL 20 Watt Set M - 266.c 45,000.00 10 50.00 45,050.00 0.00 0.00 45,050.00
291 Lampu LED 5 Watt Buah M - 266.d 50,000.00 10 50.00 50,050.00 0.00 0.00 50,050.00
292 Lampu LED 5 Watt Buah M - 266.e 110,000.00 10 50.00 110,050.00 0.00 0.00 110,050.00
293 Lampu LED 5 Watt Buah M - 266.f 125,000.00 10 50.00 125,050.00 0.00 0.00 125,050.00
294 Instalasi Titik Lampu Titik - 225,000.00 10 500.00 225,500.00 0.00 0.00 225,500.00
BAHAN PENGUNCI & PENGGANTUNG
295 Engsel Pintu Buah M - 267 25,000.00 10 50.00 25,050.00 0.00 0.00 25,050.00
296 Engsel Jendela Buah M - 267.a 20,000.00 10 50.00 20,050.00 0.00 0.00 20,050.00
297 Engsel Pintu Pivot (Tanam) Kualitas Baik Terpasang Buah M - 267.a 975,300.00 10 50.00 975,350.00 0.00 0.00 975,350.00
298 Handle Pintu Buah M - 268 80,000.00 10 50.00 80,050.00 0.00 0.00 80,050.00
299 Handle Pintu Stainless Steel Panjang 30 cm Buah M - 268.a 150,000.00 10 50.00 150,050.00 0.00 0.00 150,050.00
300 Handle Jendela Buah M - 268.a 13,000.00 10 50.00 13,050.00 0.00 0.00 13,050.00
301 Slot Pintu Buah M - 269 12,000.00 10 50.00 12,050.00 0.00 0.00 12,050.00
302 Slot Pintu Tanam Buah - 105,000.00 10 50.00 105,050.00 0.00 0.00 105,050.00
303 Slot Jendela Buah M - 269.a 8,000.00 10 50.00 8,050.00 0.00 0.00 8,050.00
304 Kait Angin Buah M - 270 6,000.00 10 50.00 6,050.00 0.00 0.00 6,050.00
305 Kunci 2 Slaag Buah M - 271 198,000.00 10 500.00 198,500.00 0.00 0.00 198,500.00
306 Kunci Pintu Tanam Buah M - 271.a 160,000.00 10 500.00 160,500.00 0.00 0.00 160,500.00
307 Kunci Pintu Tanam 2 Slaag Buah M - 271.a 198,000.00 10 500.00 198,500.00 0.00 0.00 198,500.00
308 Pintu Folding Gate + Pemasangan m2 M - 272 350,000.00 > 100 240,000.00 590,000.00 0.00 0.00 590,000.00
309 Pintu Gulungan Besi (Rolling Door) m2 M - 272.a 350,000.00 > 100 240,000.00 590,000.00 0.00 0.00 590,000.00
310 Door Closer Buah M - 273 230,000.00 10 500.00 230,500.00 0.00 0.00 230,500.00
311 Engsel Sendok Buah - 15,000.00 10 500.00 15,500.00 0.00 0.00 15,500.00
BAHAN PERPIPAAN
312 Pipa Ø 1/2 " PVC Type AW m' M - 280.a 4,300.00 > 600 1,000.00 5,300.00 0.00 0.00 5,300.00
313 Pipa Ø 3/4 " PVC Type AW m' M - 281.a 6,650.00 > 600 1,500.00 8,150.00 0.00 0.00 8,150.00
314 Pipa Ø 1 " PVC Type AW m' M - 282.a 8,300.00 > 600 2,000.00 10,300.00 0.00 0.00 10,300.00
315 Pipa Ø 1,5 " PVC Type AW m' M - 283.a 14,550.00 > 600 2,500.00 17,050.00 0.00 0.00 17,050.00
316 Pipa Ø 2 " PVC Type AW m' M - 284.a 18,700.00 > 600 3,000.00 21,700.00 0.00 0.00 21,700.00
317 Pipa Ø 2,5 " PVC Type AW m' M - 285.a 26,900.00 > 600 4,000.00 30,900.00 0.00 0.00 30,900.00
318 Pipa Ø 3 " PVC Type AW m' M - 286.a 37,000.00 > 600 6,000.00 43,000.00 0.00 0.00 43,000.00
319 Pipa Ø 4 " PVC Type AW m' M - 287.a 61,050.00 > 600 10,000.00 71,050.00 0.00 0.00 71,050.00
320 Pipa Ø 6 " PVC Type AW m' M - 288.a 136,350.00 > 600 25,000.00 161,350.00 0.00 0.00 161,350.00
321 Pipa Ø 8 " PVC Type AW m' M - 289.a 233,500.00 > 600 45,000.00 278,500.00 0.00 0.00 278,500.00
322 Pipa Ø 1,5 " PVC Type D m' M - 290.b 8,700.00 > 600 2,500.00 11,200.00 0.00 0.00 11,200.00
323 Pipa Ø 2 " PVC Type D m' M - 291.b 11,800.00 > 600 3,000.00 14,800.00 0.00 0.00 14,800.00
324 Pipa Ø 2,5 " PVC Type D m' M - 292.b 16,050.00 > 600 4,000.00 20,050.00 0.00 0.00 20,050.00
325 Pipa Ø 3 " PVC Type D m' M - 293.b 20,600.00 > 600 6,000.00 26,600.00 0.00 0.00 26,600.00
326 Pipa Ø 4 " PVC Type D m' M - 294.b 32,200.00 > 600 10,000.00 42,200.00 0.00 0.00 42,200.00
327 Pipa Ø 6 " PVC Type D m' M - 295.b 86,300.00 > 600 25,000.00 111,300.00 0.00 0.00 111,300.00
328 Pipa Ø 8 " PVC Type D m' M - 296.b 120,950.00 > 600 45,000.00 165,950.00 0.00 0.00 165,950.00
DAFTAR ANALISA HARGA SATUAN PEKERJAAN
PEKERJAAN : -
LOKASI : -
TAHUN ANGGARAN : 2017
Harga Biaya
No. Uraian Satuan Satuan Kuantitas Satuan
( Rp ) ( Rp )
A TENAGA KERJA
1 Pekerja Hari/Orang 100,000.00 0.1920 19,200.00
2 Mandor Hari/Orang 150,000.00 0.0192 2,880.00
Jumlah 22,080.00
B BAHAN
1 Pasir Urug M3 172,000.00 1.2500 215,000.00
Jumlah 215,000.00
C Jumlah A + B 237,080.00
D Biaya Umum = % x C 0.00
E Harga Satuan = ( C + D ) 237,080.00
Harga Biaya
No. Uraian Satuan Satuan Kuantitas Satuan
( Rp ) ( Rp )
A TENAGA KERJA
1 Tukang Batu Hari/Orang 125,000.00 0.2500 31,250.00
2 Kepala Tukang Batu Hari/Orang 150,000.00 0.0250 3,750.00
3 Pekerja Hari/Orang 100,000.00 1.6500 165,000.00
4 Mandor Hari/Orang 150,000.00 0.0800 12,000.00
Jumlah 212,000.00
B BAHAN
1 Pasir Ayak / Pasir Beton M3 187,000.00 0.5200 97,240.00
2 Semen Kg 2,540.00 218.0000 553,720.00
3 Kerikil Sungai M3 197,000.00 0.8700 171,390.00
Jumlah 822,350.00
C Jumlah A + B 1,034,350.00
D Biaya Umum = % x C 0.00
E Harga Satuan = ( C + D ) 1,034,350.00
REKAPITULASI ANALISA HARGA SATUAN
BALOK SLOOF WC
BALOK SLOOF VOLUME BETON
Lebar Tinggi PANJANG Volume Jlh / titik
20 x 35 0.20 0.25 13.52 0.676 1
RING BALOK WC
BALOK SLOOF VOLUME BETON
Lebar Tinggi PANJANG Volume Jlh / titik
15 x 20 0.15 0.1 13.52 0.2028 1
KOLOM SELASAR
KOLOM VOLUME BETON
Lebar Tinggi PANJANG Volume Jlh / titik
15 x 15 0.15 0.15 4 0.09 14
Pj Tulangan
Panjang Jumlah
Jlh Balok + tekuk 5 d
Tulangan Balok Tulangan
+1,5M
(meter) (buah) (meter) (buah)
Tulangan Tegak 4 14 4.3 8
KOLOM TERAS
KOLOM VOLUME BETON
Lebar Tinggi PANJANG Volume Jlh / titik
20 x 20 0.20 0.2 4 0.16 2
Pj Tulangan
Panjang Jumlah
Jlh Balok + tekuk 5 d
Tulangan Balok Tulangan
+1,5M
(meter) (buah) (meter) (buah)
Tulangan Tegak 4 2 4.3 8
KOLOM WC
KOLOM VOLUME BETON
Lebar Tinggi PANJANG Volume Jlh / titik
15 x 15 0.15 0.15 4 0.09 4
Pj Tulangan
Panjang Jumlah
Jlh Balok + tekuk 5 d
Tulangan Balok Tulangan
+1,5M
(meter) (buah) (meter) (buah)
Tulangan Tegak 4 4 4.3 8
KOLOM PRAKTIS WC
KOLOM VOLUME BETON
Lebar Tinggi PANJANG Volume Jlh / titik
10 x 10 0.10 0.1 4 0.04 6
Pj Tulangan
Panjang Jumlah
Jlh Balok + tekuk 5 d
Tulangan Balok Tulangan
+1,5M
(meter) (buah) (meter) (buah)
Tulangan Tegak 4 6 4.3 4
Tul Beugel D 8 mm - 200 mm 4 6 0.22 14
JUMLAH
Jumlah 0.36 M3
Jumlah
Diameter Panjang Jlh Dak
TULANGAN Tulangan
Tulangan
(meter) (Buah) (Buah)
Tulangan Atas 8 12.00 1 81.00
8 0.30 1 3.00
Tulangan Bawah 8 12.00 1 81.00
8 0.30 1 3.00
JUMLAH
Jumlah 1.06 M3
Jumlah
Diameter Panjang Jlh Dak
TULANGAN Tulangan
Tulangan
(meter) (Buah) (Buah)
Tulangan Atas 8 4.60 1 31.67
8 2.30 1 16.33
Tulangan Bawah 8 4.60 1 31.67
8 2.30 1 16.33
JUMLAH
LANTAI KERJA
VOLUME BETON
LEBAR PANJANG Tebal Volume Jlh / titik T.volume
20.00 10.00 0.05 10 1 10.00 M3
2.00 4.00 0.05 0.4 1 0.40 M3
4.00 4.00 0.05 0.8 1 0.80 M3
20.00 1.00 0.05 1 2 2.00 M3
46.00 19 JUMLAH 12.2
Jumlah
Diameter Panjang Jlh Dak
TULANGAN Tulangan
Tulangan
(meter) (Buah) (Buah)
Tulangan Bawah 8 19.00 1 127.67
8 46.00 1 307.67
JUMLAH
BETON VOLUME BEKESTING
T.volume Lebar Panjang Sisi Jlh / titik T.volume
0.25 2
5.232 M3 52.32 2 73.248 M2
0.20 1
Berat = 427.55 Kg
D 8 170 M' 15 Btg 67.24 Kg
Berat = 67.24 Kg
BETON VOLUME BEKESTING
T.volume Lebar Panjang Sisi Jlh / titik T.volume
0.2 2
0.32 M3 4 2 6.4 M2
0.20 2
Berat = 61.08 Kg
D 8 35 M' 3 Btg 13.97 Kg
Berat = 13.97 Kg
Berat = 122.16 Kg
D 8 49 M' 4 Btg 19.21 Kg
Berat = 19.21 Kg
VOLUME BAKESTING
Panjang Lebar Volume Jlh / titik T.volume
20.00 1.30 26 1 26 M2
0.13 2 0.26 M2
2.00 1 2 M2
Jumlah 28.26 M2
Pengurangan Balok Jumlah 3 M2
Jumlah 25.26 M2
VOLUME BAKESTING
Panjang Lebar Volume Jlh / titik T.volume
12.00 1 12 1 12 M2
0.03 2 0.06 M2
1.20 1 1.2 M2
Jumlah 13.26 M2
Pengurangan Balok Jumlah 1.8 M2
Jumlah 11.46 M2
VOLUME BAKESTING
Panjang Lebar Volume Jlh / titik T.volume
4.60 1 4.6 1 4.6 M2
0.23 2 0.46 M2
0.46 1 0.46 M2
Jumlah 5.52 M2
Pengurangan Balok Jumlah 0.69 M2
Jumlah 4.83 M2
JUMLAH
JUMLAH
JUMLAH
BAKESTIN TULANGA TULANGA
BETON
G N UTAMA N BEUGEL
0.81 18.90 49.93 20.10
JUMLAH
BAKESTIN TULANGA TULANGA
BETON
G N UTAMA N BEUGEL
JUMLAH
JUMLAH
JUMLAH
JUMLAH
BAKESTIN TULANGA
BETON
G N UTAMA
JUMLAH
BAKESTIN TULANGA
BETON
G N UTAMA
5.20 25.26 113.63
JUMLAH
BAKESTIN TULANGA
BETON
G N UTAMA
JUMLAH
BAKESTIN TULANGA
BETON
G N UTAMA
Harga Biaya
No. Uraian Satuan Satuan Kuantitas Satuan
( Rp ) ( Rp )
A TENAGA KERJA
1 Tukang Kayu Hari/Orang 125,000.00 0.1000 12,500.00
2 Kepala Tukang Kayu Hari/Orang 150,000.00 0.0100 1,500.00
3 Pekerja Hari/Orang 100,000.00 0.1000 10,000.00
4 Mandor Hari/Orang 150,000.00 0.0050 750.00
Jumlah 24,750.00
B BAHAN
1 Papan klas. III Campuran M3 1,966,500.00 0.0070 13,765.50
2 Cerucuk dia. 8 cm - 2 m Btg 7,500.00 1.0000 7,500.00
3 Paku Campuran Kg 25,200.00 0.0200 504.00
Jumlah 21,769.50
C Jumlah A + B 46,519.50
D Biaya Umum = % x C 0.00
E Harga Satuan = ( C + D ) 46,519.50
Harga Biaya
No. Uraian Satuan Satuan Kuantitas Satuan
( Rp ) ( Rp )
A TENAGA KERJA
1 Pekerja Hari/Orang 100,000.00 0.1000 10,000.00
2 Mandor Hari/Orang 150,000.00 0.0050 750.00
Jumlah 10,750.00
B BAHAN
Jumlah
C Jumlah A + B 10,750.00
D Biaya Umum = % x C 0.00
E Harga Satuan = ( C + D ) 10,750.00
Harga Biaya
No. Uraian Satuan Satuan Kuantitas Satuan
( Rp ) ( Rp )
A TENAGA KERJA
1 Pekerja Hari/Orang 100,000.00 0.4000 40,000.00
2 Mandor Hari/Orang 150,000.00 0.0400 6,000.00
Jumlah 46,000.00
B BAHAN
Jumlah
C Jumlah A + B 46,000.00
D Biaya Umum = % x C 0.00
E Harga Satuan = ( C + D ) 46,000.00
Harga Biaya
No. Uraian Satuan Satuan Kuantitas Satuan
( Rp ) ( Rp )
A TENAGA KERJA
1 Pekerja Hari/Orang 100,000.00 0.1920 19,200.00
2 Mandor Hari/Orang 150,000.00 0.0192 2,880.00
Jumlah 22,080.00
B BAHAN
Jumlah
C Jumlah A + B 22,080.00
D Biaya Umum = % x C 0.00
E Harga Satuan = ( C + D ) 22,080.00
Pekerjaan Balok Keef, Gelegar dll, Kayu Belian 9/9 (PK.01/M3)
Harga Biaya
No. Uraian Satuan Satuan Kuantitas Satuan
( Rp ) ( Rp )
A TENAGA KERJA
1 Tukang Kayu Hari/Orang 125,000.00 24.0000 3,000,000.00
2 Kepala Tukang Kayu Hari/Orang 150,000.00 2.4000 360,000.00
3 Pekerja Hari/Orang 100,000.00 8.0000 800,000.00
4 Mandor Hari/Orang 150,000.00 0.4000 60,000.00
Jumlah 4,220,000.00
B BAHAN
1 Kayu Belian (tak Ketam) M3 11,017,500.00 1.1000 12,119,250.00
2 Paku Belian / Beton Kg 30,200.00 3.0000 90,600.00
Jumlah 12,209,850.00
C Jumlah A + B 16,429,850.00
D Biaya Umum = % x C 0.00
E Harga Satuan = ( C + D ) 16,429,850.00
Pekerjaan Balok Keef, Gelegar dll, Kayu Klas I 5/9, 9/9 (PK.01.a/M3)
Harga Biaya
No. Uraian Satuan Satuan Kuantitas Satuan
( Rp ) ( Rp )
A TENAGA KERJA
1 Tukang Kayu Hari/Orang 125,000.00 24.0000 3,000,000.00
2 Kepala Tukang Kayu Hari/Orang 150,000.00 2.4000 360,000.00
3 Pekerja Hari/Orang 100,000.00 8.0000 800,000.00
4 Mandor Hari/Orang 150,000.00 0.4000 60,000.00
Jumlah 4,220,000.00
B BAHAN
1 Kayu Klas I (tak ketam) M3 3,137,500.00 1.1000 3,451,250.00
2 Paku Campuran Kg 25,200.00 3.0000 75,600.00
Jumlah 3,526,850.00
C Jumlah A + B 7,746,850.00
D Biaya Umum = % x C 0.00
E Harga Satuan = ( C + D ) 7,746,850.00
Harga Biaya
No. Uraian Satuan Satuan Kuantitas Satuan
( Rp ) ( Rp )
A TENAGA KERJA
1 Tukang Kayu Hari/Orang 125,000.00 36.0000 4,500,000.00
2 Kepala Tukang Kayu Hari/Orang 150,000.00 3.6000 540,000.00
3 Pekerja Hari/Orang 100,000.00 12.0000 1,200,000.00
4 Mandor Hari/Orang 150,000.00 0.6000 90,000.00
Jumlah 6,330,000.00
B BAHAN
1 Kayu Belian 8/8 (ketam) M3 11,214,500.00 1.1000 12,335,950.00
2 Paku Belian / Beton Kg 30,200.00 6.0000 181,200.00
Jumlah 12,517,150.00
C Jumlah A + B 18,847,150.00
D Biaya Umum = % x C 0.00
E Harga Satuan = ( C + D ) 18,847,150.00
Harga Biaya
No. Uraian Satuan Satuan Kuantitas Satuan
( Rp ) ( Rp )
A TENAGA KERJA
1 Tukang Kayu Hari/Orang 125,000.00 24.0000 3,000,000.00
2 Kepala Tukang Kayu Hari/Orang 150,000.00 2.4000 360,000.00
3 Pekerja Hari/Orang 100,000.00 8.0000 800,000.00
4 Mandor Hari/Orang 150,000.00 0.4000 60,000.00
Jumlah 4,220,000.00
B BAHAN
1 Kayu Klas I 8/8 (ketam) M3 3,334,500.00 1.1000 3,667,950.00
2 Paku Campuran Kg 25,200.00 6.0000 151,200.00
Jumlah 3,819,150.00
C Jumlah A + B 8,039,150.00
D Biaya Umum = % x C 0.00
E Harga Satuan = ( C + D ) 8,039,150.00
Pekerjaan Rangka Badan Kayu Klas II 8/8 (PK.08.a / M3)
Harga Biaya
No. Uraian Satuan Satuan Kuantitas Satuan
( Rp ) ( Rp )
A TENAGA KERJA
1 Tukang Kayu Hari/Orang 125,000.00 24.0000 3,000,000.00
2 Kepala Tukang Kayu Hari/Orang 150,000.00 2.4000 360,000.00
3 Pekerja Hari/Orang 100,000.00 8.0000 800,000.00
4 Mandor Hari/Orang 150,000.00 0.4000 60,000.00
Jumlah 4,220,000.00
B BAHAN
1 Kayu Klas II 8/8 (ketam) M3 2,326,500.00 1.1000 2,559,150.00
2 Paku Campuran Kg 25,200.00 6.0000 151,200.00
Jumlah 2,710,350.00
C Jumlah A + B 6,930,350.00
D Biaya Umum = % x C 0.00
E Harga Satuan = ( C + D ) 6,930,350.00
Harga Biaya
No. Uraian Satuan Satuan Kuantitas Satuan
( Rp ) ( Rp )
A TENAGA KERJA
1 Tukang Kayu Hari/Orang 125,000.00 0.2500 31,250.00
2 Kepala Tukang kayu Hari/Orang 150,000.00 0.0250 3,750.00
3 Pekerja Hari/Orang 100,000.00 0.1000 10,000.00
4 Mandor Hari/Orang 150,000.00 0.0050 750.00
Jumlah 45,750.00
Upah Diambil 25 % 11,437.50
B BAHAN
Jumlah
C Jumlah A + B 11,437.50
D Biaya Umum = % x C 0.00
E Harga Satuan = ( C + D ) 11,437.50
Harga Biaya
No. Uraian Satuan Satuan Kuantitas Satuan
( Rp ) ( Rp )
A TENAGA KERJA
1 Tukang Kayu Hari/Orang 125,000.00 0.6000 75,000.00
2 Kepala Tukang kayu Hari/Orang 150,000.00 0.0600 9,000.00
Jumlah 84,000.00
Upah Diambil 60 % 50,400.00
B BAHAN
Jumlah
C Jumlah A + B 50,400.00
D Biaya Umum = % x C 0.00
E Harga Satuan = ( C + D ) 50,400.00
Harga Biaya
No. Uraian Satuan Satuan Kuantitas Satuan
( Rp ) ( Rp )
A TENAGA KERJA
1 Tukang Kayu Hari/Orang 125,000.00 0.0400 5,000.00
2 Kepala Tukang Kayu Hari/Orang 150,000.00 0.0040 600.00
3 Pekerja Hari/Orang 100,000.00 1.8000 180,000.00
4 Mandor Hari/Orang 150,000.00 0.0430 6,450.00
Jumlah 192,050.00
Upah Diambil 25 % 48,012.50
B BAHAN
Jumlah
C Jumlah A + B 48,012.50
D Biaya Umum = % x C 0.00
E Harga Satuan = ( C + D ) 48,012.50
Pekerjaan Pintu Panel Kayu Belian (PK.14 / M2)
Harga Biaya
No. Uraian Satuan Satuan Kuantitas Satuan
( Rp ) ( Rp )
A TENAGA KERJA
1 Tukang Kayu Hari/Orang 125,000.00 2.5000 312,500.00
2 Kepala Tukang Kayu Hari/Orang 150,000.00 0.2500 37,500.00
3 Pekerja Hari/Orang 100,000.00 1.0000 100,000.00
4 Mandor Hari/Orang 150,000.00 0.0500 7,500.00
Jumlah 457,500.00
B BAHAN
1 Papan Kayu Belian (Ketam) M3 11,628,500.00 0.0400 465,140.00
Jumlah 465,140.00
C Jumlah A + B 922,640.00
D Biaya Umum = % x C 0.00
E Harga Satuan = ( C + D ) 922,640.00
Harga Biaya
No. Uraian Satuan Satuan Kuantitas Satuan
( Rp ) ( Rp )
A TENAGA KERJA
1 Tukang Kayu Hari/Orang 125,000.00 2.5000 312,500.00
2 Kepala Tukang Kayu Hari/Orang 150,000.00 0.2500 37,500.00
3 Pekerja Hari/Orang 100,000.00 1.0000 100,000.00
4 Mandor Hari/Orang 150,000.00 0.0500 7,500.00
Jumlah 457,500.00
B BAHAN
1 Papan Kayu Klas I (ketam) M3 5,918,500.00 0.0400 236,740.00
Jumlah 236,740.00
C Jumlah A + B 694,240.00
D Biaya Umum = % x C 0.00
E Harga Satuan = ( C + D ) 694,240.00
Harga Biaya
No. Uraian Satuan Satuan Kuantitas Satuan
( Rp ) ( Rp )
A TENAGA KERJA
1 Tukang Kayu Hari/Orang 125,000.00 2.0000 250,000.00
2 Kepala Tukang Kayu Hari/Orang 150,000.00 0.2000 30,000.00
3 Pekerja Hari/Orang 100,000.00 0.8000 80,000.00
4 Mandor Hari/Orang 150,000.00 0.0400 6,000.00
Jumlah 366,000.00
B BAHAN
1 Kayu Klas I (ketam) M3 3,334,500.00 0.0350 116,707.50
2 Kaca Bening 5 mm M2 173,000.00 0.7500 129,750.00
Jumlah 246,457.50
C Jumlah A + B 612,457.50
D Biaya Umum = % x C 0.00
E Harga Satuan = ( C + D ) 612,457.50
Harga Biaya
No. Uraian Satuan Satuan Kuantitas Satuan
( Rp ) ( Rp )
A TENAGA KERJA
1 Tukang Kayu Hari/Orang 125,000.00 1.5000 187,500.00
2 Kepala Tukang Kayu Hari/Orang 150,000.00 0.1500 22,500.00
3 Pekerja Hari/Orang 100,000.00 0.5000 50,000.00
4 Mandor Hari/Orang 150,000.00 0.0250 3,750.00
Jumlah diambil 25% 65,937.50
B BAHAN
1 Kayu Klas II M3 2,125,500.00 0.0039 8,289.45
2 Triplek M2 20,256.65 2.0000 40,513.30
3 Paku Triplek Kg 40,200.00 0.0500 2,010.00
Jumlah 50,812.75
C Jumlah A + B 116,750.25
D Biaya Umum = % x C 0.00
E Harga Satuan = ( C + D ) 116,750.25
Pekerjaan Ventilasi Jalusi / Ram Kayu Klas II (PK.22 / m2)
Harga Biaya
No. Uraian Satuan Satuan Kuantitas Satuan
( Rp ) ( Rp )
A TENAGA KERJA
1 Tukang Kayu Hari/Orang 125,000.00 0.8000 100,000.00
2 Kepala Tukang Kayu Hari/Orang 150,000.00 0.0800 12,000.00
3 Pekerja Hari/Orang 100,000.00 0.5000 50,000.00
4 Mandor Hari/Orang 150,000.00 0.0140 2,100.00
Jumlah 164,100.00
B BAHAN
1 Papan Kayu Klas II (ketam) M3 3,355,500.00 0.0130 43,621.50
2 Paku Campuran Kg 25,200.00 0.1000 2,520.00
Jumlah 46,141.50
C Jumlah A + B 210,241.50
D Biaya Umum = % x C 0.00
E Harga Satuan = ( C + D ) 210,241.50
Harga Biaya
No. Uraian Satuan Satuan Kuantitas Satuan
( Rp ) ( Rp )
A TENAGA KERJA
1 Tukang Kayu Hari/Orang 125,000.00 12.0000 1,500,000.00
2 Kepala Tukang Kayu Hari/Orang 150,000.00 1.2000 180,000.00
3 Pekerja Hari/Orang 100,000.00 4.0000 400,000.00
4 Mandor Hari/Orang 150,000.00 0.2000 30,000.00
Jumlah 2,110,000.00
B BAHAN
1 Kayu Klas II (tak ketam) M3 2,125,500.00 1.1000 2,338,050.00
2 Baut Btg 8,100.00 12.0000 97,200.00
3 Paku Campuran Kg 25,200.00 0.8000 20,160.00
Jumlah 2,455,410.00
C Jumlah A + B 4,565,410.00
D Biaya Umum = % x C 0.00
E Harga Satuan = ( C + D ) 4,565,410.00
Harga Biaya
No. Uraian Satuan Satuan Kuantitas Satuan
( Rp ) ( Rp )
A TENAGA KERJA
1 Tukang Kayu Hari/Orang 125,000.00 18.0000 2,250,000.00
2 Kepala Tukang Kayu Hari/Orang 150,000.00 1.8000 270,000.00
3 Pekerja Hari/Orang 100,000.00 6.0000 600,000.00
4 Mandor Hari/Orang 150,000.00 0.3000 45,000.00
Jumlah 3,165,000.00
B BAHAN
1 Kayu Klas II (tak ketam) M3 2,125,500.00 1.1000 2,338,050.00
2 Paku Campuran Kg 25,200.00 3.0000 75,600.00
Jumlah 2,413,650.00
C Jumlah A + B 5,578,650.00
D Biaya Umum = % x C 0.00
E Harga Satuan = ( C + D ) 5,578,650.00
Harga Biaya
No. Uraian Satuan Satuan Kuantitas Satuan
( Rp ) ( Rp )
A TENAGA KERJA
1 Tukang Kayu Hari/Orang 125,000.00 0.100 12,500.00
2 Kepala Tukang Kayu Hari/Orang 150,000.00 0.010 1,500.00
3 Pekerja Hari/Orang 100,000.00 0.100 10,000.00
4 Mandor Hari/Orang 150,000.00 0.005 750.00
Jumlah 24,750.00
B BAHAN
1 Kayu Klas II (Tidak Ketam) M3 2,125,500.00 0.0150 31,882.50
2 Paku Campuran Kg 25,200.00 0.1500 3,780.00
Jumlah 35,662.50
C Jumlah A + B 60,412.50
D Biaya Umum = % x C 0.00
E Harga Satuan = ( C + D ) 60,412.50
Pekerjaan Rangka Langit-langit 30 x 60 Kayu Klas II (PK.32 / M2)
Harga Biaya
No. Uraian Satuan Satuan Kuantitas Satuan
( Rp ) ( Rp )
A TENAGA KERJA
1 Tukang Kayu Hari/Orang 125,000.00 0.3000 37,500.00
2 Kepala Tukang Kayu Hari/Orang 150,000.00 0.0300 4,500.00
3 Pekerja Hari/Orang 100,000.00 0.2000 20,000.00
4 Mandor Hari/Orang 150,000.00 0.0100 1,500.00
Jumlah 63,500.00
B BAHAN
1 Paku Campuran Kg 25,200.00 0.1500 3,780.00
2 Kayu Klas II (tak ketam) M3 2,125,500.00 0.0230 48,886.50
Jumlah 52,666.50
C Jumlah A + B 116,166.50
D Biaya Umum = % x C 0.00
E Harga Satuan = ( C + D ) 116,166.50
Harga Biaya
No. Uraian Satuan Satuan Kuantitas Satuan
( Rp ) ( Rp )
A TENAGA KERJA
1 Tukang Kayu Hari/Orang 125,000.00 0.1000 12,500.00
2 Kepala Tukang Kayu Hari/Orang 150,000.00 0.0100 1,500.00
3 Pekerja Hari/Orang 100,000.00 0.1000 10,000.00
4 Mandor Hari/Orang 150,000.00 0.0500 7,500.00
Jumlah 31,500.00
B BAHAN
1 Papan Klas I (ketam) M3 5,918,500.00 0.0080 47,348.00
2 Paku Campuran Kg 25,200.00 0.0600 1,512.00
Jumlah 48,860.00
C Jumlah A + B 80,360.00
D Biaya Umum = % x C 0.00
E Harga Satuan = ( C + D ) 80,360.00
Harga Biaya
No. Uraian Satuan Satuan Kuantitas Satuan
( Rp ) ( Rp )
A TENAGA KERJA
1 Tukang Kayu Hari/Orang 125,000.00 0.1000 12,500.00
2 Kepala Tukang Kayu Hari/Orang 150,000.00 0.0100 1,500.00
3 Pekerja Hari/Orang 100,000.00 0.1000 10,000.00
4 Mandor Hari/Orang 150,000.00 0.0500 7,500.00
Jumlah 31,500.00
B BAHAN
1 Papan Kayu Klas II (ketam) M3 3,355,500.00 0.0080 26,844.00
2 Paku Campuran Kg 25,200.00 0.0600 1,512.00
Jumlah 28,356.00
C Jumlah A + B 59,856.00
D Biaya Umum = % x C 0.00
E Harga Satuan = ( C + D ) 59,856.00
Harga Biaya
No. Uraian Satuan Satuan Kuantitas Satuan
( Rp ) ( Rp )
A TENAGA KERJA
1 Tukang Kayu Hari/Orang 125,000.00 1.8000 225,000.00
2 Kepala Tukang Kayu Hari/Orang 150,000.00 0.1800 27,000.00
3 Pekerja Hari/Orang 100,000.00 0.6000 60,000.00
4 Mandor Hari/Orang 150,000.00 0.0300 4,500.00
Jumlah 316,500.00
Upah diambil 50 % 158,250.00
B BAHAN
1 Papan Kayu Klas I (ketam) M3 5,918,500.00 0.0240 142,044.00
2 Paku Campuran Kg 25,200.00 0.2000 5,040.00
Jumlah 147,084.00
C Jumlah A + B 305,334.00
D Biaya Umum = % x C 0.00
E Harga Satuan = ( C + D ) 305,334.00
Pekerjaan Lantai Papan Kayu Klas II (PK.38.a/ M2)
Harga Biaya
No. Uraian Satuan Satuan Kuantitas Satuan
( Rp ) ( Rp )
A TENAGA KERJA
1 Tukang Kayu Hari/Orang 125,000.00 1.8000 225,000.00
2 Kepala Tukang Kayu Hari/Orang 150,000.00 0.1800 27,000.00
3 Pekerja Hari/Orang 100,000.00 0.6000 60,000.00
4 Mandor Hari/Orang 150,000.00 0.0300 4,500.00
Jumlah 316,500.00
Upah diambil 50 % 158,250.00
B BAHAN
1 Papan Kayu Klas II (ketam) M3 3,355,500.00 0.0240 80,532.00
2 Paku Campuran Kg 25,200.00 0.2000 5,040.00
Jumlah 85,572.00
C Jumlah A + B 243,822.00
D Biaya Umum = % x C 0.00
E Harga Satuan = ( C + D ) 243,822.00
Harga Biaya
No. Uraian Satuan Satuan Kuantitas Satuan
( Rp ) ( Rp )
A TENAGA KERJA
1 Tukang Seng Hari/Orang 125,000.00 0.0600 7,500.00
2 Kepala Tukang Hari/Orang 150,000.00 0.0060 900.00
3 Pekerja Hari/Orang 100,000.00 0.1200 12,000.00
4 Mandor Hari/Orang 150,000.00 0.0060 900.00
Jumlah 21,300.00
B BAHAN
1 Seng Gelombang BJLS 0.20 M2 33,203.13 1.0000 33,203.13
2 Paku Seng Kg 30,200.00 0.0200 604.00
Jumlah 33,807.13
C Jumlah A + B 55,107.13
D Biaya Umum = % x C 0.00
E Harga Satuan = ( C + D ) 55,107.13
Harga Biaya
No. Uraian Satuan Satuan Kuantitas Satuan
( Rp ) ( Rp )
A TENAGA KERJA
1 Tukang Seng Hari/Orang 125,000.00 0.1000 12,500.00
2 Kepala Tukang Hari/Orang 150,000.00 0.0100 1,500.00
3 Pekerja Hari/Orang 100,000.00 0.2000 20,000.00
4 Mandor Hari/Orang 150,000.00 0.0100 1,500.00
Jumlah 35,500.00
B BAHAN
1 Seng Metal Lembar 37,500.00 1.6230 60,862.50
2 Paku Seng Kg 30,200.00 0.1000 3,020.00
Jumlah 63,882.50
C Jumlah A + B 99,382.50
D Biaya Umum = % x C 0.00
E Harga Satuan = ( C + D ) 99,382.50
Harga Biaya
No. Uraian Satuan Satuan Kuantitas Satuan
( Rp ) ( Rp )
A TENAGA KERJA
1 Tukang Seng Hari/Orang 125,000.00 0.2500 31,250.00
2 Kepala Tukang Hari/Orang 150,000.00 0.0250 3,750.00
3 Pekerja Hari/Orang 100,000.00 0.2500 25,000.00
Jumlah 60,000.00
B BAHAN
1 Seng Plat BJLS 0.30 Lembar 48,000.00 6.0000 288,000.00
2 Paku Seng Kg 30,200.00 0.1000 3,020.00
3 Papan Klas II ( Tidak Ketam ) M3 2,925,500.00 0.0720 210,636.00
Jumlah 501,656.00
C Jumlah A + B 561,656.00
D Biaya Umum = % x C 0.00
E Harga Satuan = ( C + D ) 561,656.00
Untuk 1 M' 56,165.60
Pekerjaan Langit - Langit GRC t = 4 mm + Rangka Kayu (P.Pf.01 / M2)
Harga Biaya
No. Uraian Satuan Satuan Kuantitas Satuan
( Rp ) ( Rp )
A TENAGA KERJA
1 Tukang Hari/Orang 125,000.00 0.4000 50,000.00
2 Kepala Tukang Hari/Orang 150,000.00 0.0400 6,000.00
3 Pekerja Hari/Orang 100,000.00 0.2700 27,000.00
4 Mandor Hari/Orang 150,000.00 0.0135 2,025.00
Jumlah 85,025.00
B BAHAN
1 GRC Board Lbr 76,500.00 0.3900 29,835.00
2 Paku GRC Kg 40,200.00 0.1100 4,422.00
3 Kayu Klas II (tidak ketam) M3 2,125,500.00 0.0230 48,886.50
4 Paku Campuran Kg 25,200.00 0.0600 1,512.00
Jumlah 84,655.50
C Jumlah A + B 169,680.50
D Biaya Umum = % x C 0.00
E Harga Satuan = ( C + D ) 169,680.50
Harga Biaya
No. Uraian Satuan Satuan Kuantitas Satuan
( Rp ) ( Rp )
A TENAGA KERJA
1 Tukang Kayu Hari/Orang 125,000.00 0.8000 100,000.00
2 Kepala Tukang Hari/Orang 150,000.00 0.0800 12,000.00
3 Pekerja Hari/Orang 100,000.00 0.2800 28,000.00
4 Mandor Hari/Orang 150,000.00 0.0140 2,100.00
Jumlah 142,100.00
B BAHAN
1 Kayu Kls II (tdk ketam) M3 2,125,500.00 0.0080 17,004.00
2 Papan Kayu Kls II (ketam) Kg 3,355,500.00 0.0090 30,199.50
3 Paku Campur Kg 25,200.00 0.0100 252.00
Jumlah 47,455.50
C Jumlah A + B 189,555.50
D Biaya Umum = % x C 0.00
E Harga Satuan = ( C + D ) 189,555.50
Harga Biaya
No. Uraian Satuan Satuan Kuantitas Satuan
( Rp ) ( Rp )
A TENAGA KERJA
3 Pekerja Hari/Orang 100,000.00 0.1500 15,000.00
4 Mandor Hari/Orang 150,000.00 0.0025 375.00
Jumlah 15,375.00
B BAHAN
1 Soda Api Kg 41,100.00 1.0000 41,100.00
Jumlah 41,100.00
C Jumlah A + B 56,475.00
D Biaya Umum = % x C 0.00
E Harga Satuan = ( C + D ) 56,475.00
Harga Biaya
No. Uraian Satuan Satuan Kuantitas Satuan
( Rp ) ( Rp )
A TENAGA KERJA
1 Tukang Cat Hari/Orang 125,000.00 0.0750 9,375.00
2 Kepala Tukang Cat Hari/Orang 150,000.00 0.0075 1,125.00
3 Pekerja Hari/Orang 100,000.00 0.0700 7,000.00
4 Mandor Hari/Orang 150,000.00 0.0025 375.00
Jumlah 17,875.00
B BAHAN
1 Plamur Kg 35,100.00 0.1500 5,265.00
2 Cat Dasar Kg 45,600.00 0.0075 342.00
3 Cat Penutup Cat Kilat Kg 55,600.00 0.0025 139.00
Jumlah 5,746.00
C Jumlah A + B 23,621.00
D Biaya Umum = % x C 0.00
E Harga Satuan = ( C + D ) 23,621.00
Pekerjaan Pengecatan Bidang kayu Baru ( 1 Lapis plamir, 1 lapis cat dasar, 2 lapis cat penutup ) (P Ct. 04 / 1 M2)
Harga Biaya
No. Uraian Satuan Satuan Kuantitas Satuan
( Rp ) ( Rp )
A TENAGA KERJA
1 Tukang Cat Hari/Orang 125,000.00 0.0090 1,125.00
2 Kepala Tukang Cat Hari/Orang 150,000.00 0.0060 900.00
3 Pekerja Hari/Orang 100,000.00 0.0700 7,000.00
4 Mandor Hari/Orang 150,000.00 0.0025 375.00
Jumlah 9,400.00
B BAHAN
1 Cat Meni Kg 27,100.00 0.2000 5,420.00
2 Plamur Kg 35,100.00 0.1500 5,265.00
3 Cat dasar Kg 45,600.00 0.1700 7,752.00
4 Cat Penutup / Kilat 2 Kali Kg 55,600.00 0.2600 14,456.00
Jumlah 32,893.00
C Jumlah A + B 42,293.00
D Biaya Umum = % x C 0.00
E Harga Satuan = ( C + D ) 42,293.00
Pekerjaan Pengecatan Bidang kayu Baru ( 1 Lapis plamir, 1 lapis cat dasar, 3 lapis cat penutup ) (P Ct. 05 / 1 M2)
Harga Biaya
No. Uraian Satuan Satuan Kuantitas Satuan
( Rp ) ( Rp )
A TENAGA KERJA
1 Tukang Cat Hari/Orang 125,000.00 0.1050 13,125.00
2 Kepala Tukang Cat Hari/Orang 150,000.00 0.0040 600.00
3 Pekerja Hari/Orang 100,000.00 0.0700 7,000.00
4 Mandor Hari/Orang 150,000.00 0.0025 375.00
Jumlah 21,100.00
B BAHAN
1 Cat Meni Kg 27,100.00 0.2000 5,420.00
2 Plamur Kg 35,100.00 0.1500 5,265.00
3 Cat dasar Kg 45,600.00 0.1700 7,752.00
4 Cat Penutup / Kilat 3 Kali Kg 55,600.00 0.3500 19,460.00
Jumlah 37,897.00
C Jumlah A + B 58,997.00
D Biaya Umum = % x C 0.00
E Harga Satuan = ( C + D ) 58,997.00
Pekerjaan Pengecatan Atap Seng ( 1 lapis cat penutup ) (P Ct. 04.a / 1 M2)
Harga Biaya
No. Uraian Satuan Satuan Kuantitas Satuan
( Rp ) ( Rp )
A TENAGA KERJA
1 Tukang Cat Hari/Orang 125,000.00 0.0090 1,125.00
2 Kepala Tukang Cat Hari/Orang 150,000.00 0.0060 900.00
3 Pekerja Hari/Orang 100,000.00 0.0700 7,000.00
4 Mandor Hari/Orang 150,000.00 0.0025 375.00
Jumlah 9,400.00
Upah di ambil 50% 4,700.00
B BAHAN
4 Cat Seng / 1 Kali Kg 55,600.00 0.1300 7,228.00
Jumlah 7,228.00
C Jumlah A + B 11,928.00
D Biaya Umum = % x C 0.00
E Harga Satuan = ( C + D ) 11,928.00
Pekerjaan Pengecatan Tembok Baru ( 1 Lapis plamur, 1 lapis cat dasar, 2 lapis cat penutup ) (P Ct. 11 / M2)
Harga Biaya
No. Uraian Satuan Satuan Kuantitas Satuan
( Rp ) ( Rp )
A TENAGA KERJA
1 Tukang Cat Hari/Orang 125,000.00 0.0630 7,875.00
2 Kepala Tukang Cat Hari/Orang 150,000.00 0.0063 945.00
3 Pekerja Hari/Orang 100,000.00 0.0200 2,000.00
4 Mandor Hari/Orang 150,000.00 0.0025 375.00
Jumlah 11,195.00
B BAHAN
1 Cat Meni Kg 27,100.00 0.1000 2,710.00
2 Car dasar Kg 45,600.00 0.1200 5,472.00
3 Cat tembok Kg 10,100.00 0.2600 2,626.00
Jumlah 10,808.00
C Jumlah A + B 22,003.00
D Biaya Umum = % x C 0.00
E Harga Satuan = ( C + D ) 22,003.00
Pekerjaan Pengecatan Tembok Lama (1 lapis plamir, 2 lapis cat penutup) (P.Ct.12)
Harga Biaya
No. Uraian Satuan Satuan Kuantitas Satuan
( Rp ) ( Rp )
A TENAGA KERJA
1 Tukang Cat Hari/Orang 125,000.00 0.0420 5,250.00
2 Kepala Tukang Cat Hari/Orang 150,000.00 0.0042 630.00
3 Pekerja Hari/Orang 100,000.00 0.0280 2,800.00
4 Mandor Hari/Orang 150,000.00 0.0025 375.00
Jumlah 9,055.00
B BAHAN
2 Car dasar Kg 45,600.00 0.1200 5,472.00
3 Cat tembok Kg 10,100.00 0.1800 1,818.00
Jumlah 7,290.00
C Jumlah A + B 16,345.00
D Biaya Umum = % x C 0.00
E Harga Satuan = ( C + D ) 16,345.00
Harga Biaya
No. Uraian Satuan Satuan Kuantitas Satuan
( Rp ) ( Rp )
A TENAGA KERJA
1 Tukang Batu Hari/Orang 125,000.00 0.2500 31,250.00
2 Kepala Tukang Batu Hari/Orang 150,000.00 0.0250 3,750.00
3 Pekerja Hari/Orang 100,000.00 1.6500 165,000.00
4 Mandor Hari/Orang 150,000.00 0.0800 12,000.00
Jumlah 212,000.00
B BAHAN
1 Pasir Ayak / Pasir Beton M3 187,000.00 0.5200 97,240.00
2 Semen Kg 2,540.00 218.0000 553,720.00
3 Kerikil sungai M3 197,000.00 0.8700 171,390.00
Jumlah 822,350.00
C Jumlah A + B 1,034,350.00
D Biaya Umum = % x C 0.00
E Harga Satuan = ( C + D ) 1,034,350.00
Harga Biaya
No. Uraian Satuan Satuan Kuantitas Satuan
( Rp ) ( Rp )
A TENAGA KERJA
1 Tukang Batu Hari/Orang 125,000.00 0.3500 43,750.00
2 Kepala Tukang Batu Hari/Orang 150,000.00 0.0350 5,250.00
3 Pekerja Hari/Orang 100,000.00 2.0000 200,000.00
4 Mandor Hari/Orang 150,000.00 1.0000 150,000.00
Jumlah 399,000.00
B BAHAN
1 Pasir M3 187,000.00 0.5400 100,980.00
2 Semen Kg 2,540.00 336.0000 853,440.00
3 Batu Belah 1,5 - 1 cm / Krikil M3 197,000.00 0.8100 159,570.00
Jumlah 1,113,990.00
C Jumlah A + B 1,512,990.00
D Biaya Umum = % x C 0.00
E Harga Satuan = ( C + D ) 1,512,990.00
Harga Biaya
No. Uraian Satuan Satuan Kuantitas Satuan
( Rp ) ( Rp )
A TENAGA KERJA
1 Tukang Besi Hari/Orang 125,000.00 0.0070 875.00
2 Kepala Tukang Hari/Orang 150,000.00 0.0007 105.00
3 Pekerja Hari/Orang 100,000.00 0.0070 700.00
4 Mandor Hari/Orang 150,000.00 0.0003 45.00
Jumlah 1,725.00
B BAHAN
1 Besi Beton Kg 22,600.00 1.0500 23,730.00
2 Kawat Beton / Bendrat Kg 25,600.00 0.0150 384.00
Jumlah 24,114.00
C Jumlah A + B 25,839.00
D Biaya Umum = % x C 0.00
E Harga Satuan = ( C + D ) 25,839.00
Pekerjaan Bekisting Untuk Lantai Cor Gantung ( P.BB.09 / M2 )
Harga Biaya
No. Uraian Satuan Satuan Kuantitas Satuan
( Rp ) ( Rp )
A TENAGA KERJA
1 Tukang Kayu Hari/Orang 125,000.00 0.3300 41,250.00
2 Kepala Tukang Kayu Hari/Orang 150,000.00 0.0330 4,950.00
3 Pekerja Hari/Orang 100,000.00 0.3200 32,000.00
4 Mandor Hari/Orang 150,000.00 0.0060 900.00
Upah 25 % 19,775.00
B BAHAN
1 Kayu campuran M3 2,021,500.00 0.0048 9,703.20
2 Paku campuran Kg 25,200.00 0.0400 1,008.00
3 Papan Kayu Klas III / Papan Mal M3 1,966,500.00 0.0036 7,079.40
Jumlah 17,790.60
C Jumlah A + B 37,565.60
D Biaya Umum = % x C 0.00
E Harga Satuan = ( C + D ) 37,565.60
Pekerjaan Plesteran dan Acian Tebal 1,5 cm Camp. 1Pc :2 Psr ( P.Pls.11 / M2)
Harga Biaya
No. Uraian Satuan Satuan Kuantitas Satuan
( Rp ) ( Rp )
A TENAGA KERJA
1 Tukang Hari/Orang 125,000.00 0.1650 20,625.00
2 Kepala Tukang Hari/Orang 150,000.00 0.0165 2,475.00
3 Pekerja Hari/Orang 100,000.00 0.3300 33,000.00
4 Mandor Hari/Orang 150,000.00 0.0165 2,475.00
Jumlah 58,575.00
B BAHAN
1 Portland Cement Kg 2,540.00 0.3200 812.80
2 Pasir Beton M3 187,000.00 0.0180 3,366.00
Jumlah 4,178.80
C Jumlah A + B 62,753.80
D Biaya Umum = % x C 0.00
E Harga Satuan = ( C + D ) 62,753.80
Harga Biaya
No. Uraian Satuan Satuan Kuantitas Satuan
( Rp ) ( Rp )
A TENAGA KERJA
1 Tukang Batu Hari/Orang 125,000.00 0.4000 50,000.00
2 Kepala Tukang Batu Hari/Orang 150,000.00 0.0400 6,000.00
3 Pekerja Hari/Orang 100,000.00 0.8000 80,000.00
4 Mandor Hari/Orang 150,000.00 0.0400 6,000.00
Jumlah 142,000.00
B BAHAN
1 Portland Cement Zak 127,000.00 0.2610 33,147.00
2 Pasir Beton M3 187,000.00 0.0390 7,293.00
3 Kawat Simpai Kg 17,200.00 0.6500 11,180.00
4 Papan Mal M3 1,966,500.00 0.0100 19,665.00
5 Paku Campuran Kg 25,200.00 0.1000 2,520.00
Jumlah 73,805.00
C Jumlah A + B 215,805.00
D Biaya Umum = % x C 0.00
E Harga Satuan = ( C + D ) 215,805.00
Harga Biaya
No. Uraian Satuan Satuan Kuantitas Satuan
( Rp ) ( Rp )
A TENAGA KERJA
1 Tukang Semen Hari/Orang 125,000.00 0.3500 43,750.00
2 Kepala Tukang Semen Hari/Orang 150,000.00 0.0350 5,250.00
3 Pekerja Hari/Orang 100,000.00 0.6200 62,000.00
4 Mandor Hari/Orang 150,000.00 0.0300 4,500.00
Jumlah 115,500.00
B BAHAN
1 Keramik 20 x 20 Bh 2,900.00 25.0000 72,500.00
2 Portland cement Kg 2,540.00 11.3800 28,905.20
3 Semen Putih Pengisi Nat Kg 2,540.00 0.2000 508.00
4 Pasir Beton M3 187,000.00 0.0420 7,854.00
Jumlah 109,767.20
C Jumlah A + B 225,267.20
D Biaya Umum = % x C 0.00
E Harga Satuan = ( C + D ) 225,267.20
Pekerjaan Lantai Keramik uk. 30 x 30 cm Polos (P.LD.08 / M2)
Harga Biaya
No. Uraian Satuan Satuan Kuantitas Satuan
( Rp ) ( Rp )
A TENAGA KERJA
1 Tukang Semen Hari/Orang 125,000.00 0.3500 43,750.00
2 Kepala Tukang Semen Hari/Orang 150,000.00 0.0350 5,250.00
3 Pekerja Hari/Orang 100,000.00 0.6200 62,000.00
4 Mandor Hari/Orang 150,000.00 0.0300 4,500.00
Jumlah 115,500.00
B BAHAN
1 Keramik 30 x 30 Bh 6,350.00 12.0000 76,200.00
2 Portland cement Kg 2,540.00 11.3800 28,905.20
3 Semen Putih Pengisi Nat Kg 2,540.00 0.2000 508.00
4 Pasir Beton M3 187,000.00 0.0420 7,854.00
Jumlah 113,467.20
C Jumlah A + B 228,967.20
D Biaya Umum = % x C 0.00
E Harga Satuan = ( C + D ) 228,967.20
Harga Biaya
No. Uraian Satuan Satuan Kuantitas Satuan
( Rp ) ( Rp )
A TENAGA KERJA
1 Tukang Batu Hari/Orang 125,000.00 1.5000 187,500.00
2 Kepala Tukang Batu Hari/Orang 150,000.00 0.1500 22,500.00
3 Pekerja Hari/Orang 100,000.00 1.0000 100,000.00
4 Mandor Hari/Orang 150,000.00 0.0500 7,500.00
Jumlah 317,500.00
B BAHAN
1 Kloset Jongkok Bh 195,000.00 1.0000 195,000.00
2 Portland Cement Kg 25,200.00 6.0000 151,200.00
3 Pasir Beton Kg 187,000.00 0.0100 1,870.00
Jumlah 348,070.00
C Jumlah A + B 665,570.00
D Biaya Umum = % x C 0.00
E Harga Satuan = ( C + D ) 665,570.00
Harga Biaya
No. Uraian Satuan Satuan Kuantitas Satuan
( Rp ) ( Rp )
A TENAGA KERJA
1 Tukang Batu Hari/Orang 125,000.00 0.1500 18,750.00
2 Kepala Tukang Batu Hari/Orang 150,000.00 0.1450 21,750.00
3 Pekerja Hari/Orang 100,000.00 1.2000 120,000.00
4 Mandor Hari/Orang 150,000.00 0.0100 1,500.00
Jumlah 162,000.00
B BAHAN
1 Wastefel Bh 670,000.00 1.0000 670,000.00
2 Portland Cement Kg 25,200.00 6.0000 151,200.00
3 Pasir Beton Kg 187,000.00 0.0100 1,870.00
Jumlah 823,070.00
C Jumlah A + B 985,070.00
D Biaya Umum = % x C 0.00
E Harga Satuan = ( C + D ) 985,070.00
Harga Biaya
No. Uraian Satuan Satuan Kuantitas Satuan
( Rp ) ( Rp )
A TENAGA KERJA
1 Tukang Hari/Orang 125,000.00 0.0600 7,500.00
2 Kepala Tukang Hari/Orang 150,000.00 0.0060 900.00
3 Pekerja Hari/Orang 100,000.00 0.0360 3,600.00
4 Mandor Hari/Orang 150,000.00 0.0180 2,700.00
Jumlah 14,700.00
B BAHAN
1 Pipa PVC Ø 4" M1 42,200.00 1.2000 50,640.00
2 Perlengkapan Ls 35 % X Harga Pipa 17,724.00
Jumlah 68,364.00
C Jumlah A + B 83,064.00
D Biaya Umum = % x C 0.00
E Harga Satuan = ( C + D ) 83,064.00
Pekerjaan Memasang Kran air Ø 3/4" atau Ø 1/2" (P.Snt.15 / Bh)
Harga Biaya
No. Uraian Satuan Satuan Kuantitas Satuan
( Rp ) ( Rp )
A TENAGA KERJA
1 Tukang Batu Hari/Orang 125,000.00 0.1000 12,500.00
2 Kepala Tukang Batu Hari/Orang 150,000.00 0.0100 1,500.00
3 Pekerja Hari/Orang 100,000.00 0.0100 1,000.00
4 Mandor Hari/Orang 150,000.00 0.0050 750.00
Jumlah 15,750.00
B BAHAN
1 Kran air Bh 15,300.00 1.0000 15,300.00
2 Seal Tape Set 3,100.00 0.0250 77.50
Jumlah 15,377.50
C Jumlah A + B 31,127.50
D Biaya Umum = % x C 0.00
E Harga Satuan = ( C + D ) 31,127.50
Harga Biaya
No. Uraian Satuan Satuan Kuantitas Satuan
( Rp ) ( Rp )
A TENAGA KERJA
1 Tukang Hari/Orang 125,000.00 0.0900 11,250.00
2 Kepala Tukang Hari/Orang 150,000.00 0.0090 1,350.00
3 Pekerja Hari/Orang 100,000.00 0.0540 5,400.00
4 Mandor Hari/Orang 150,000.00 0.0027 405.00
Jumlah 18,405.00
Upah diambil 50 % 9,202.50
B BAHAN
1 Floor Drain Bh 65,300.00 1.0000 65,300.00
Jumlah 65,300.00
C Jumlah A + B 74,502.50
D Biaya Umum = % x C 0.00
E Harga Satuan = ( C + D ) 74,502.50
Harga Biaya
No. Uraian Satuan Satuan Kuantitas Satuan
( Rp ) ( Rp )
A TENAGA KERJA
1 Tukang Kayu Hari/Orang 125,000.00 0.5000 62,500.00
2 Kepala Tukang Kayu Hari/Orang 150,000.00 0.0100 1,500.00
3 Pekerja Hari/Orang 100,000.00 0.0100 1,000.00
4 Mandor Hari/Orang 150,000.00 0.0050 750.00
Jumlah 65,750.00
B BAHAN
1 Kunci 2 slaag Bh 198,500.00 1.0000 198,500.00
Jumlah 198,500.00
C Jumlah A + B 264,250.00
D Biaya Umum = % x C 0.00
E Harga Satuan = ( C + D ) 264,250.00
Harga Biaya
No. Uraian Satuan Satuan Kuantitas Satuan
( Rp ) ( Rp )
A TENAGA KERJA
1 Tukang Kayu Hari/Orang 125,000.00 0.1500 18,750.00
2 Kepala Tukang Kayu Hari/Orang 150,000.00 0.0150 2,250.00
3 Pekerja Hari/Orang 100,000.00 0.0150 1,500.00
4 Mandor Hari/Orang 150,000.00 0.00075 112.50
Jumlah 22,612.50
B BAHAN
1 Engsel Pintu Bh 25,050.00 1.0000 25,050.00
Jumlah 25,050.00
C Jumlah A + B 47,662.50
D Biaya Umum = % x C 0.00
E Harga Satuan = ( C + D ) 47,662.50
Pekerjaan Pemasangan engsel Jendela ( P.KK.05 / Bh )
Harga Biaya
No. Uraian Satuan Satuan Kuantitas Satuan
( Rp ) ( Rp )
A TENAGA KERJA
1 Tukang Kayu Hari/Orang 125,000.00 0.1500 18,750.00
2 Kepala Tukang Kayu Hari/Orang 150,000.00 0.0150 2,250.00
3 Pekerja Hari/Orang 100,000.00 0.0150 1,500.00
4 Mandor Hari/Orang 150,000.00 0.00075 112.50
Jumlah 22,612.50
B BAHAN
1 Engsel Jendela Bh 20,050.00 1.0000 20,050.00
Jumlah 20,050.00
C Jumlah A + B 42,662.50
D Biaya Umum = % x C 0.00
E Harga Satuan = ( C + D ) 42,662.50
Harga Biaya
No. Uraian Satuan Satuan Kuantitas Satuan
( Rp ) ( Rp )
A TENAGA KERJA
1 Tukang Kayu Hari/Orang 125,000.00 0.1500 18,750.00
2 Kepala Tukang Kayu Hari/Orang 150,000.00 0.0150 2,250.00
3 Pekerja Hari/Orang 100,000.00 0.0150 1,500.00
4 Mandor Hari/Orang 150,000.00 0.00080 120.00
Jumlah 22,620.00
Upah Diambil 25 % 4,524.00
B BAHAN
1 Kait Angin Bh 6,050.00 1.0000 6,050.00
Jumlah 6,050.00
C Jumlah A + B 10,574.00
D Biaya Umum = % x C 0.00
E Harga Satuan = ( C + D ) 10,574.00
Harga Biaya
No. Uraian Satuan Satuan Kuantitas Satuan
( Rp ) ( Rp )
A TENAGA KERJA
1 Tukang Kayu Hari/Orang 125,000.00 0.2000 25,000.00
2 Kepala Tukang Kayu Hari/Orang 150,000.00 0.0200 3,000.00
3 Pekerja Hari/Orang 100,000.00 0.0200 2,000.00
4 Mandor Hari/Orang 150,000.00 0.0010 150.00
Jumlah 30,150.00
Upah diambil 25 % 7,537.50
B BAHAN
1 Slot Pintu Bh 12,050.00 1.0000 12,050.00
Jumlah 12,050.00
C Jumlah A + B 19,587.50
D Biaya Umum = % x C 0.00
E Harga Satuan = ( C + D ) 19,587.50
Harga Biaya
No. Uraian Satuan Satuan Kuantitas Satuan
( Rp ) ( Rp )
A TENAGA KERJA
1 Tukang Kayu Hari/Orang 125,000.00 0.2000 25,000.00
2 Kepala Tukang Hari/Orang 150,000.00 0.0200 3,000.00
3 Pekerja Hari/Orang 100,000.00 0.0200 2,000.00
4 Mandor Hari/Orang 150,000.00 0.0010 150.00
Jumlah 30,150.00
Upah diambil 25 % 7,537.50
B BAHAN
1 Slot Jendela Bh 8,050.00 1.0000 8,050.00
Jumlah 8,050.00
C Jumlah A + B 15,587.50
D Biaya Umum = % x C 0.00
E Harga Satuan = ( C + D ) 15,587.50
Pekerjaan Pemasangan Handle Jendela ( P.KK.09/ Bh )
Harga Biaya
No. Uraian Satuan Satuan Kuantitas Satuan
( Rp ) ( Rp )
A TENAGA KERJA
1 Tukang Kayu Hari/Orang 125,000.00 0.2000 25,000.00
2 Kepala Tukang Hari/Orang 150,000.00 0.0200 3,000.00
3 Pekerja Hari/Orang 100,000.00 0.0200 2,000.00
4 Mandor Hari/Orang 150,000.00 0.0010 150.00
Jumlah 30,150.00
Upah diambil 25 % 7,537.50
B BAHAN
1 Handle Jendela Bh 13,050.00 1.0000 13,050.00
Jumlah 13,050.00
C Jumlah A + B 20,587.50
D Biaya Umum = % x C 0.00
E Harga Satuan = ( C + D ) 20,587.50
Harga Biaya
No. Uraian Satuan Satuan Kuantitas Satuan
( Rp ) ( Rp )
A TENAGA KERJA
1 Tukang Kayu Hari/Orang 125,000.00 0.2000 25,000.00
2 Kepala Tukang Hari/Orang 150,000.00 0.0200 3,000.00
3 Pekerja Hari/Orang 100,000.00 0.0200 2,000.00
4 Mandor Hari/Orang 150,000.00 0.0010 150.00
Jumlah 30,150.00
Upah diambil 50 % 15,075.00
B BAHAN
1 Handle Pintu Bh 80,050.00 1.0000 80,050.00
Jumlah 80,050.00
C Jumlah A + B 95,125.00
D Biaya Umum = % x C 0.00
E Harga Satuan = ( C + D ) 95,125.00