BILL OF QUANTITY (REKAPITULASI)

PEKERJAAN : RELOKASI GUDANG 02 DARI PEKAN BARU KE PERAWANG


LOKASI : PELABUHAN PERAWANG
TAHUN : INVESTASI 2018

JUMLAH HARGA (Rp.)


NO URAIAN
UPAH BAHAN ALAT JUMLAH
1 2 3 4 5 6 = 3+4+5

I Pekerjaan Persiapan 9,574,927.46 48,600,347.76 25,000,000.00 83,175,275.22

II Pekerjaan Tanah 5,915,225.39 249,991,266.56 14,266,125.20 270,172,617.14

III Pekerjaan Struktur Gudang CFS 720,362,224.99 2,129,435,471.76 299,382,446.26 3,149,180,143.01

IV Pekerjaan Lain-lain 13,000,000.00 2,000,000.00 4,545,337.00 19,545,337.00

JUMLAH 3,522,073,372.37
PPN(10%) 352,207,337.24
TOTAL BIAYA 3,874,280,709.61
DIBULATKAN ###

Terbilang : Tiga Milyar Delapan Ratus Tujuh Puluh Empat Juta Dua Ratus Delapan Puluh Ribu Tujuh Ratus
Sembilan Rupiah

Medan, 16 April 2018


PT. TISA LESTARI

HIDAYATULLAH
Direktur
BILL OF QUANTITY (RINCIAN HARGA)
PEKERJAAN : RELOKASI GUDANG 02 DARI PEKAN BARU KE PERAWANG
LOKASI : PELABUHAN PERAWANG
TAHUN : INVESTASI 2018

KONTRAK
NO URAIAN SAT HARGA SATUAN (Rp)
VOL
UPAH BAHAN ALAT JUMLAH
1 2 3 4 5 6 7 8
I Pekerjaan Persiapan
1 Mobilisasi dan Demobilisasi ls 1.00 25,000,000.00 25,000,000.00
2 Pembuatan Direksi Kit dan Gudang m2 40.00 200,000.00 1,000,000.00 1,200,000.00
3 Rambu-rambu Keselamatan & PMK 3 ls 1.00 3,000,000.00 3,000,000.00
4 Pengukuran awal dan akhir Pekerjaan m' 67.00 23,506.38 83,587.28 107,093.66
Jumlah I

II Pekerjaan Tanah
1 Penimbunan dan pemadatan sertu m3 455.00 9,957.07 353,669.21 21,452.82 385,079.10
2 Penimbunan dan pemadatan Base A m3 210.00 6,594.09 424,151.32 21,452.82 452,198.23
Jumlah II

III Pekerjaan Struktur Gudang CFS


A Pekerjaan Pondasi
1 Pengangkatan tiang pancang ke titik pancang m' 880.00 9,307.35 300,000.00 29,878.90 339,186.25
2 Pemancangan tiang pancang beton kotak 25x25 cm m' 880.00 28,508.78 56,247.65 84,756.42
3 Penyambungan tiang pancang ttk 44.00 8,142.48 4,628.40 97,817.34 110,588.22
4 Pemotongan kepala tiang pancang ttk 44.00 11,617.74 232,817.34 244,435.08
5 Pekerjaan galian tanah untuk pondasi m3 47.03 67,858.90 67,858.90
6 Urugkan pasir dibawah pondasi m3 1.24 181,844.94 151,032.00 332,876.94
7 Pengecoran lantai kerja beton 1:3:5 m3 1.24 202,261.68 532,306.60 734,568.28
8 Pile cap
Beton K 300 m3 18.78 31,617.21 1,707,438.15 239,582.45 1,978,637.81
Pembesian kg 2,294.46 2,790.27 11,264.06 14,054.33
Bekisting m2 114.27 73,417.00 305,657.10 379,074.10
Urugan Kembali (Back Fill) m3 28.22 40,715.34 40,715.34
B Pekerjaan Drainase
1 Galian tanah m3 81.28 67,858.90 67,858.90
2 Pengecoran lantai kerja beton 1 : 3 : 5 m3 5.08 202,261.68 532,306.60 734,568.28
3 Pekerjaan Drainase
Beton K 300 m3 37.59 31,617.21 1,707,438.15 239,582.45 1,978,637.81
Pembesian kg 4,286.71 2,790.27 11,264.06 14,054.33
Bekisting m2 395.24 75,352.00 318,811.50 394,163.50
C Pekerjaan Sloop dan Lantai
1 Sloop 30x50
Beton K 300 m3 16.50 31,617.21 1,707,438.15 239,582.45 1,978,637.81
Pembesian kg 1,460.73 2,790.27 11,264.06 14,054.33
Pengecoran lantai kerja beton 1 : 3 : 5 m3 2.75 202,261.68 532,306.60 734,568.28
Bekisting m2 176.00 64,033.02 202,350.40 266,383.42
2 Beton penahan tanah 50 x 70
Beton K 300 m3 38.50 31,617.21 1,707,438.15 239,582.45 1,978,637.81
Pembesian kg 3,078.39 2,790.27 11,264.06 14,054.33
Urugan pasir m3 7.70 181,844.94 151,032.00 332,876.94
Pengecoran lantai kerja beton 1 : 3 : 5 m3 3.85 202,261.68 532,306.60 734,568.28
Bekisting m2 264.00 75,352.00 365,745.10 441,097.10
3 Lantai Gudang
Beton K 300 m3 150.00 31,617.21 1,707,438.15 239,582.45 1,978,637.81
Pembesian kg 14,808.00 2,790.27 11,264.06 14,054.33
Urugan pasir m3 60.80 181,844.94 151,032.00 332,876.94
Urugan tanah m3 120.00 30,812.94 151,032.00 181,844.94
Bekisting m2 27.50 75,352.00 365,745.10 441,097.10
4 Ram dari Apron ke gudang
Beton K 300 m3 64.80 31,617.21 1,707,438.15 239,582.45 1,978,637.81
Pembesian kg 3,607.96 2,790.27 11,264.06 14,054.33
Bekisting m2 286.20 75,352.00 365,745.10 441,097.10
D Pekerjaan Struktur Baja Gudang CFS
1 Pembongkaran dinding bata gudang lama m3 33.00 513,549.00 513,549.00
2 Pembongkaran struktur baja lama kg 23,535.40 4,108.39 4,108.39
3 Pengangkutan struktur baja dari Pekanbaru ke Perawang kg 23,535.40 6.06 5,561.81 5,567.87
4 Pemasangan kembali Besi WF 250.125.6.9 kg 21,460.00 7,345.41 7,345.41
5 Besi CNP 150.65.20.2,3 kg 5,324.00 7,345.41 28,566.16 35,911.57
6 Plat 10 mm kg 1,163.37 7,345.41 20,423.60 27,769.01
7 Plat 8 mm kg 398.62 7,345.41 20,423.60 27,769.01
8 Plat 4 mm kg 146.27 7,345.41 20,423.60 27,769.01
9 Pas. Ikatan Angin dia.16 kg 2,050.07 1,425.60 16,830.00 18,255.60
10 Pas. Trekstang gording dia 12 mm kg 500.19 1,425.60 16,830.00 18,255.60
11 Tracker bh 36.00 50,000.00 50,000.00
12 Baut 3/4" bh 528.00 6,084.00 8,000.00 14,084.00
13 Baut 5/8" bh 1,074.00 6,084.00 7,514.84 13,598.84
14 Baut 1/2" bh 1,428.00 6,084.00 3,113.18 9,197.18
15 Angkur baut 1"-60cm bh 66.00 23,688.00 40,705.39 64,393.39
16 Pipa 4" untuk buangan air m' 35.80 26,193.24 147,250.00 173,443.24
17 Pasang kembali kisi-kisi m' 80.00 150,000.00 150,000.00
18 Pengecatan m2 2,252.66 8,142.48 3,962.56 12,105.04
E Pekerjaan Atap
1 Atap spandek 0,35 mm m2 932.80 33,777.36 103,404.20 137,181.56
2 Rabung atap m' 44.00 45,590.15 78,614.20 124,204.35
3 List plank m2 69.00 37,399.68 39,570.20 76,969.88
4 Talang m' 88.00 65,629.40 139,422.06 205,051.46
F Pekerjaan dinding
1 Pasangan bata m2 220.00 45,983.34 51,249.38 97,232.72
2 Plesteran dinding m2 440.00 53,175.35 11,254.32 64,429.67
3 Pengecatan dinding m2 440.00 19,990.87 15,325.24 35,316.11

G Pekerjaan pintu
1 Pek.Pas. Pintu gudang(dlm 2.5m x 5m x 4) m2 48.70 152,731.87 1,200,000.00 1,352,731.87

H Pekerjaan Instalasi
1 Instalasi listrik + panel ls 1.00 50,000,000.00 50,000,000.00
2 Instalasi air + panel ls 1.00 12,000,000.00 12,000,000.00

Jumlah III
IV Pekerjaan Lain-lain
1 Laporan, Dokumentasi dan Administrasi ls 1.00 7,000,000.00 2,000,000.00 9,000,000.00
2 Pembersihan Akhir ls 1.00 6,000,000.00 4,545,337.00 10,545,337.00
Jumlah IV

JUMLAH
PPN(10%)
TOTAL BIAYA
DIBULATKAN
TRAK
JUMLAH HARGA (Rp)
JUMLAH (Rp)
UPAH BAHAN ALAT
9 10 11 12

25,000,000.00 25,000,000.00
8,000,000.00 40,000,000.00 48,000,000.00
3,000,000.00 3,000,000.00
1,574,927.46 5,600,347.76 7,175,275.22
9,574,927.46 48,600,347.76 25,000,000.00 83,175,275.22

4,530,467.20 160,919,488.41 9,761,033.03 175,210,988.64


1,384,758.19 89,071,778.15 4,505,092.17 94,961,628.50
5,915,225.39 249,991,266.56 14,266,125.20 270,172,617.14

8,190,468.00 264,000,000.00 26,293,428.89 298,483,896.89


25,087,724.61 49,497,927.66 74,585,652.27
358,269.12 203,649.60 4,303,962.84 4,865,881.56
511,180.56 10,243,962.84 10,755,143.40
3,191,064.87 3,191,064.87
225,487.73 187,279.68 412,767.41
250,804.48 660,060.18 910,864.67

593,644.77 32,058,858.76 4,498,400.04 37,150,903.57


6,402,162.90 25,844,944.29 32,247,107.19
8,389,360.13 34,927,436.82 43,316,796.95
1,148,783.35 1,148,783.35

5,515,571.55 5,515,571.55
1,027,489.33 2,704,117.53 3,731,606.86

1,188,490.99 64,182,600.17 9,005,904.22 74,376,995.38


11,961,078.31 48,285,775.79 60,246,854.10
29,782,122.90 126,007,057.26 155,789,180.16

521,683.99 28,172,729.53 3,953,110.39 32,647,523.91


4,075,831.10 16,453,756.21 20,529,587.30
556,219.62 1,463,843.15 2,020,062.77
11,269,811.52 35,613,670.40 46,883,481.92

1,217,262.65 65,736,368.89 9,223,924.25 76,177,555.79


8,589,539.27 34,675,181.98 43,264,721.24
1,400,206.04 1,162,946.40 2,563,152.44
778,707.47 2,049,380.41 2,828,087.88
19,892,926.94 96,556,706.40 116,449,633.34
4,742,581.76 256,115,722.96 35,937,367.20 296,795,671.92
41,318,318.16 166,798,259.71 208,116,577.87
11,056,172.35 9,182,745.60 20,238,917.95
3,697,552.80 18,123,840.00 21,821,392.80
2,072,179.89 10,057,990.25 12,130,170.14

2,048,795.32 110,641,992.32 15,524,942.63 128,215,730.27


10,067,182.55 40,640,292.35 50,707,474.90
21,565,741.26 104,676,247.62 126,241,988.88

16,947,117.00 16,947,117.00
96,692,649.08 96,692,649.08
142,649.59 130,899,515.29 131,042,164.88
157,632,601.61 157,632,601.61
39,106,988.40 152,086,235.84 191,193,224.24
8,545,435.22 23,760,203.53 32,305,638.75
2,928,029.25 8,141,255.43 11,069,284.68
1,074,413.82 2,987,359.97 4,061,773.79
2,922,579.79 34,502,678.10 37,425,257.89
713,070.86 8,418,197.70 9,131,268.56
1,800,000.00 1,800,000.00
3,212,352.00 4,224,000.00 7,436,352.00
6,534,216.00 8,070,938.16 14,605,154.16
8,687,952.00 4,445,621.04 13,133,573.04
1,563,408.00 2,686,555.74 4,249,963.74
937,718.12 5,271,550.00 6,209,268.12
12,000,000.00 12,000,000.00
18,342,239.00 8,926,300.41 27,268,539.41

31,507,521.41 96,455,437.76 127,962,959.17


2,005,966.51 3,459,024.80 5,464,991.31
2,580,577.92 2,730,343.80 5,310,921.72
5,775,386.76 12,269,141.28 18,044,528.04
10,116,334.80 11,274,863.60 21,391,198.40
23,397,153.12 4,951,900.80 28,349,053.92
8,795,983.68 6,743,105.60 15,539,089.28

7,438,042.17 58,440,000.00 65,878,042.17

50,000,000.00 50,000,000.00
12,000,000.00 12,000,000.00

718,294,802.39 2,120,828,167.82 299,382,446.26 3,138,505,416.47


7,000,000.00 2,000,000.00 9,000,000.00
6,000,000.00 4,545,337.00 10,545,337.00
13,000,000.00 2,000,000.00 4,545,337.00 19,545,337.00

3,511,398,645.83
351,139,864.58
3,862,538,510.41
3,862,538,510.00

Medan, 16 April 2018


PT. TISA LESTARI

HIDAYATULLAH
Direktur
DAFTAR HARGA BAHAN, UPAH DAN ALAT

PEKERJAAN RELOKASI GUDANG 02 DARI PEKAN BARU KE PERAWANG

LOKASI : PROPINSI RIAU


TAHUN : 2018

NO. BAHAN SATUAN

1 Panel beton pracetak uk. 240 x 45 x 5 cm, K.225 lbr


2 Kayu dolken btg
3 Kayu cerucuk (dolken Ø 3", pjg = 300 cm) m'
4 Multiplek tbl. 6 mm lbr
5 Besi beton polos kg
6 Besi beton ulir kg
7 Besi profil kg
8 Al. Composite Panel (Alucopan) m2
9 Kawat beton kg
10 Kawat las kg
11 Kolom beton pracetak U. 225 cm btg
12 Batu Bata bh
13 Batu pecah 2/3 ( split ) m3
14 Pasir timbun/Tanah Timbun m3
15 Pasir beton m3
16 Pasir pasang m3
17 Krikil beton m3
18 Cat dasar meni kg
19 Cat tembok kg
20 Cat penutup kg
21 Minyak cat ltr
22 Thinner ltr
23 Kuas roll bh
24 Kuas ukuran 3,5" bh
25 Kayu Kelas III m3
26 Papan cetakan m3
27 Semen (Portland Cement ) kg
28 Paku biasa kg
29 Minyak Bekisting ltr
NO. BAHAN SATUAN
NO. BAHAN SATUAN

1 Tukang kayu hari


2 Tukang batu hari
3 Tukang besi hari
4 Tukang las hari
5 Tukang cat hari
6 Kepala tukang hari
7 Pekerja hari
8 Mandor hari
6 Operator terlatih hari

Medan, 16 April 2018


PT. TISA LESTARI

HIDAYATULLAH
Direktur
FTAR HARGA BAHAN, UPAH DAN ALAT

DANG 02 DARI PEKAN BARU KE PERAWANG

HARGA SATUAN
(Rp.)

154,280.00
15,022.00
15,428.00
77,546.00
7,389.20
7,714.00
23,223.20
243,600.00
12,017.60
46,284.00
300,440.00
454.72
231,420.00
125,860.00
125,860.00
125,860.00
288,260.00
37,758.00
33,698.00
33,698.00
27,608.00
28,420.00
32,480.00
18,676.00
4,384,800.00
4,384,800.00
1,218.00
13,804.00
8,932.00
HARGA SATUAN
(Rp.)
HARGA SATUAN
(Rp.)
119,196.00
119,196.00
119,196.00
119,196.00
119,196.00
131,580.00
96,750.00
119,196.00
123,840.00
ANALISA BIAYA KONSTRUKSI
RELOKASI GUDANG 02 DARI PEKAN BARU KE PER

PA 6.4. Pengukuran dan Pemasangan bouplank


6.4.1. Bahan
Kayu 5/7 sembarang
Paku biasa 2" - 5"
Kayu papan sembarang 3/20

6.4.2. Tenaga
Tukang kayu
Pekerja
Kepala tukang
Mandor

PA 6.14. 1m³ Bongkaran dinding tembok bata merah


6.14.1 Tenaga
Pekerja
Mandor

PA 6.15. 100 kg Bongkaran struktur rangka/atap baja


6.15.1 Tenaga
Pekerja
Mandor

BERSAMBUNG : ……ABK PEKERJAAN TANAH

PT 6.4. 1 m³ Galian tanah keras sedalam 1 meter


6.4. Tenaga
Pekerja
Mandor

PT 6.11 a 1 m³ Urugan Tanah


Bahan
Tanah urug

Upah
Pekerja
Mandor

PT 6.11. 1 m³ Urugan pasir


6.11.1. Bahan
Pasir urug

6.11.2. Tenaga
Pekerja
Mandor
BERSAMBUNG : …………….ABK PEKERJAAN PONDASI.

PP Taksir 1 M' Pembuatan tiang pancang (20 x 20) Cm, beton bertulang
Taksir Bahan
Semen
Pasir pasang
Split 2/3
Besi beton
Kawat beton
Kayu SK
Paku
Tie Rod
Minyak bekisting

Taksir Tenaga
Mandor
K. Tukang
Tukang Batu
Pekerja
Alat bantu

BERSAMBUNG : ……. ABK PEKERJAAN DINDING

PD 6.11. 1 m² Pasangan bata merah tebal 1/2 bata, 1Pc : 4 Ps


6.11.1. Bahan
Bata merah 5 x 10 x 20 cm
Semen portland
Pasir pasang

6.11.2. Tenaga
Pekerja
Tukang batu
Kepala tukang
Mandor

BERSAMBUNG : ……………… PEKERJAAN PELESTERAN

PPL 6.30. 1 M² Plesteran Beton 1 Pc : 3 Ps, tebal 15 mm


6.30.1. Bahan
Semen Portland
Pasir pasang

6.30.2. Tenaga
Pekerja
Tukang batu
Kepala tukang
Mandor

BERSAMBUNG : …………….ABK PEKERJAAN KAYU

PK 6.47. 1 M´ Pasang lisplang ukuran (3 x 20) cm, kayu sembarang keras :


6.47.1. Bahan
Kayu sembarang keras, papan
Paku biasa 2" - 5"

6.47.2. Tenaga
Pekerja
Tukang kayu
Kepala tukang
Mandor
BERSAMBUNG : ………………ABK PEKERJAAN BETON

PB 6.1. 1 M³ Membuat beton tumbuk, 1 Pc : 3 Ps : 5 Kr


6.1.1 Bahan
Semen portland
Pasir beton
Batu Pecah 2/3

6.1.2. Tenaga
Pekerja
Tukang batu
Kepala tukang
Mandor

PB 6.25. 1 Kg Pembesian dengan besi polos


6.25.1. Bahan
Besi beton polos
Kawat beton

6.25.2. Tenaga
Pekerja
Tukang besi
Kepala tukang
Mandor

PB 6.29. 1 M² Pasang bekisting untuk Sloof


6.29.1. Bahan
Kayu Sembarang
Paku biasa 2' - 5"
Minyak bekisting

6.29.2. Tenaga
Pekerja
Tukang kayu
Kepala tukang
Mandor

PB 6.30. 1 M² Pasang bekisting untuk Kolom/Pile Cap


6.30.1. Bahan
Kayu Sembarang
Paku biasa 2' - 5"
Minyak bekisting
Balok Kayu sembarang
Plywood tebal 9 mm
Kayu dolken/laut Ø 3'-4'/4 m

6.30.2. Tenaga
Pekerja
Tukang kayu
Kepala tukang
Mandor
PB 6.31. 1 M² Pasang bekisting untuk Balok/Drainase
6.31.1. Bahan
Kayu Sembarang
Paku biasa 2' - 5"
Minyak bekisting
Balok Kayu sembarang
Plywood tebal 9 mm
Kayu dolken/laut Ø 3'-4'/4 m

6.31.2. Tenaga
Pekerja
Tukang kayu
Kepala tukang
Mandor

PB 6.32. 1 M² Pasang bekisting untuk Lantai /Ramp


6.32.1. Bahan
Kayu Sembarang
Paku biasa 2' - 5"
Minyak bekisting
Balok Kayu sembarang
Plywood tebal 9 mm
Kayu dolken/laut Ø 3'-4'/4 m

6.32.2. Tenaga
Pekerja
Tukang kayu
Kepala tukang
Mandor

BERSAMBUNG : ………………ABK PEKERJAAN PENUTUP ATAP

PPA 6.32. 1 M² Pasang atap Spandek


6.32.1. Bahan
Atap Spandek
Paku biasa 2" - 5"

6.32.2. Tenaga
Pekerja
Tukang Kayu
Kepala Tukang
Mandor

PPA 6.36. 1 M' Pasang Rabung


6.36.1. Bahan
Rabung Atap
Paku biasa ½" - 1"

6.36.2. Tenaga
Pekerja
Tukang Kayu
Kepala Tukang
Mandor

BERSAMBUNG : ……………ABK PEKERJAAN LANGIT - LANGIT


BERSAMBUNG : ………...

PS 6.32. Memasang 1 m' pipa PVC tipe AW diameter 4"


6.32.1. Bahan
Pipa PVC
Perlengkapan 0.35

6.32.2. Tenaga
Pekerja
Tukang batu
Kepala tukang
Mandor

BERSAMBUNG : ……….

PBA 6.1. 1 Kg Pasang rangka atap baja


6.1.1. Bahan
Besi profil WF/profil C
Meni besi

6.1.2. Tenaga
Tukang besi
Pekerja
Kepala tukang
Mandor

PBA 6.1A. 1 Kg Pasang plat baja untuk atap


6.1A.1. Bahan
Besi plat
Meni besi

6.1A.2. Tenaga
Tukang besi
Pekerja
Kepala tukang
Mandor

PBA 6.2. 1 M² Pasang pintu besi baja


6.2.1. Bahan
Pintu besi baja

6.2.2. Tenaga
Tukang besi konstruksi
Pekerja
Kepala tukang
Mandor

PBA 6.18. 1 M' Pasang talang datar, seng bjls 35


6.18.1. Bahan
Seng plat 3' x 6' bjls 35
Paku biasa ½" - 1" atau skrup
Kayu Sembarang Keras
Flincote / meni besi

6.18.2. Tenaga
Pekerja
Tukang kayu
Kepala tukang
Mandor
BERSAMBUNG : …………….ABK PEKERJAAN PENUTUP LANTAI DAN DINDING

BERSAMBUNG : ……..ABK PEKERJAAN PENGECATAN

PC 6.14 1M² Pengecatan tembok baru (1 lapis plamir,1 lapis cat dasar,2 lapis cat penutup)
6.14.1 Bahan
Plamir
Cat dasar
Cat Tembok 2 x

6.14.2 Tenaga
Pekerja
Tukang cat
Kepala tukang
Mandor

PC 6.20 1M² Pengecatan permukaan baja dengan meni besi


6.20.1 Bahan
Meni besi
Kuas

6.20.2 Tenaga
Pekerja
Tukang cat
Kepala tukang
Mandor

BERSAMBUNG : ……………ABK PEKERJAAN PINTU DAN JENDELA

PEKERJAAN LISTRIK

PEKERJAAN TIANG PANCANG

1 titik Pengelasan Sambungan Tiang Pancang


Bahan
Kawat Las

Tenaga
Pekerja
Tukang las
Kepala tukang
Mandor

Alat
Welding Set

1 titik Pemotongan Kepala Tiang Pancang


Bahan

Tenaga
Pekerja
Tukang Batu
Kepala tukang
Mandor

Alat
Welding Set
Alat Bantu

Medan, 16 April 2018


PT. TISA LESTARI

HIDAYATULLAH
Direktur
NSTRUKSI
AN BARU KE PERAWANG

0.012 M3 x Rp 4,384,800 = Rp 52,617.60


0.020 Kg x Rp 13,804 = Rp 276.08
0.007 M3 x Rp 4,384,800 = Rp 30,693.60
Jumlah (1) = Rp 83,587.28

0.100 Oh x Rp 119,196 = Rp 11,919.60


0.100 Oh x Rp 96,750 = Rp 9,675.00
0.010 Oh x Rp 131,580 = Rp 1,315.80
0.005 Oh x Rp 119,196 = Rp 595.98
Jumlah (2) = Rp 23,506.38
Jumlah (1) + (2) = Rp 107,093.66

5.000 Oh x Rp 96,750 = Rp 483,750.00


0.250 Oh x Rp 119,196 = Rp 29,799.00
Jumlah = Rp 513,549.00

4.000 Oh x Rp 96,750 = Rp 387,000.00


0.200 Oh x Rp 119,196 = Rp 23,839.20
Jumlah = Rp 410,839.20
untuk 1 kg 4,108.39

0.625 Oh x Rp. 96,750 = Rp. 60,468.75


0.062 Oh x Rp. 119,196 = Rp. 7,390.15
Jumlah = Rp. 67,858.90

1.200 M³ x Rp. 125,860 = Rp. 151,032.00


Jumlah (1) = Rp. 151,032.00
0.300 OH x Rp. 96,750 = Rp. 29,025.00
0.015 OH x Rp. 119,196 = Rp. 1,787.94

Jumlah (2) = Rp. 30,812.94


Jumlah (1) + (2) = Rp. 181,844.94

1.200 M³ x Rp. 125,860 = Rp. 151,032.00


Jumlah (1) = Rp. 151,032.00

0.300 Oh x Rp. 96,750 = Rp. 29,025.00


0.015 Oh x Rp. 119,196 = Rp. 1,787.94
Jumlah (2) = Rp. 30,812.94
Jumlah (1) + (2) = Rp. 181,844.94
10.000 Kg x Rp. 1,423.13 = Rp. 14,231.30
0.020 m3 x Rp. 49,018.75 = Rp. 980.38
0.035 m3 x Rp. 616,280.00 = Rp. 21,569.80
25.875 kg x Rp. 19,800.00 = Rp. 512,325.00
0.700 kg x Rp. 22,000.00 = Rp. 15,400.00
0.030 m3 x Rp. 4,680,500.00 = Rp. 140,415.00
0.200 m3 x Rp. 13,804.00 = Rp. 2,760.80
0.100 bh x Rp. 20,000.00 = Rp. 2,000.00
0.050 ltr x Rp. 7,956.85 = Rp. 397.84
Jumlah (1) = Rp. 710,080.12

0.040 Oh x Rp. 119,196.00 = Rp. 4,767.84


0.020 Oh x Rp. 131,580.00 = Rp. 2,631.60
0.200 Oh x Rp. 119,196.00 = Rp. 23,839.20
0.800 Oh x Rp. 96,750.00 = Rp. 77,400.00
1.000 Ls x Rp. 137,500.00 = Rp. 137,500.00
Jumlah (2) = Rp. 246,138.64
Jumlah (1) +(2) = Rp. 956,218.76

70.000 Bh x Rp. 454.72 = Rp 31,830.40


11.500 Kg x Rp. 1,218.00 = Rp 14,007.00
0.043 M³ x Rp. 125,860.00 = Rp 5,411.98
Jumlah (1) = Rp 51,249.38

0.320 Oh x Rp. 96,750 = Rp 30,960.00


0.100 Oh x Rp. 119,196 = Rp 11,919.60
0.010 Oh x Rp. 131,580 = Rp 1,315.80
0.015 Oh x Rp. 119,196 = Rp 1,787.94
Jumlah (2) = Rp 45,983.34
Jumlah (1) + (2) = Rp 97,232.72
7.070 Kg x Rp. 1,218 = Rp. 8,611.26
0.021 M³ x Rp. 125,860 = Rp. 2,643.06
Jumlah (1) = Rp. 11,254.32

0.260 Oh x Rp. 96,750 = Rp. 25,155.00


0.200 Oh x Rp. 119,196 = Rp. 23,839.20
0.020 Oh x Rp. 131,580 = Rp. 2,631.60
0.013 Oh x Rp. 119,196 = Rp. 1,549.55
Jumlah (2) = Rp. 53,175.35
Jumlah (1) + (2) = Rp. 64,429.67

0.0072 M³ x Rp. 5,400,000.00 = Rp. 38,880.00


0.050 Kg x Rp. 13,804.00 = Rp. 690.20
Jumlah (1) = Rp. 39,570.20

0.100 Oh x Rp. 96,750.00 = Rp. 9,675.00


0.200 Oh x Rp. 119,196.00 = Rp. 23,839.20
0.025 Oh x Rp. 131,580.00 = Rp. 3,289.50
0.005 Oh x Rp. 119,196.00 = Rp. 595.98
Jumlah (2) = Rp. 37,399.68
Jumlah (1) +(2) = Rp. 76,969.88
218.000 Kg x Rp. 1,218 = Rp. 265,524.00
0.520 M³ x Rp. 125,860 = Rp. 65,447.20
0.870 M³ x Rp. 231,420 = Rp. 201,335.40
Jumlah (1) = Rp. 532,306.60

1.650 Oh x Rp. 96,750 = Rp. 159,637.50


0.250 Oh x Rp. 119,196 = Rp. 29,799.00
0.025 Oh x Rp. 131,580 = Rp. 3,289.50
0.080 Oh x Rp. 119,196 = Rp. 9,535.68
Jumlah (2) = Rp. 202,261.68
Jumlah (1) + (2) = Rp. 734,568.28

1.500 Kg x Rp. 7,389 = Rp. 11,083.80


0.015 Kg x Rp. 12,018 = Rp. 180.26
Jumlah (1) = Rp. 11,264.06

0.007 Oh x Rp. 96,750 = Rp. 677.25


0.007 Oh x Rp. 119,196 = Rp. 834.37
0.007 Oh x Rp. 131,580 = Rp. 921.06
0.003 Oh x Rp. 119,196 = Rp. 357.59
Jumlah (2) = Rp. 2,790.27
Jumlah (1) + (2) = Rp. 14,054.33

0.045 M³ x Rp. 4,384,800 = Rp. 197,316.00


0.300 Kg x Rp. 13,804 = Rp. 4,141.20
0.100 Ltr x Rp. 8,932 = Rp. 893.20
Jumlah (1) = Rp. 202,350.40

0.300 Oh x Rp. 96,750 = Rp. 29,025.00


0.260 Oh x Rp. 119,196 = Rp. 30,990.96
0.026 Oh x Rp. 131,580 = Rp. 3,421.08
0.005 Oh x Rp. 119,196 = Rp. 595.98
Jumlah (2) = Rp. 64,033.02
Jumlah (1) + (2) = Rp. 266,383.42
0.040 M³ x Rp. 4,384,800 = Rp. 175,392.00
0.400 Kg x Rp. 13,804 = Rp. 5,521.60
0.200 Ltr x Rp. 8,932 = Rp. 1,786.40
0.015 M³ x Rp. 4,384,800 = Rp. 65,772.00
0.350 Lbr x Rp. 77,546 = Rp. 27,141.10
2.000 Btg x Rp. 15,022 = Rp. 30,044.00
Jumlah (1) = Rp. 305,657.10

0.300 Oh x Rp. 96,750 = Rp. 29,025.00


0.330 Oh x Rp. 119,196 = Rp. 39,334.68
0.033 Oh x Rp. 131,580 = Rp. 4,342.14
0.006 Oh x Rp. 119,196 = Rp. 715.18
Jumlah (2) = Rp. 73,417.00
Jumlah (1) + (2) = Rp. 379,074.10
0.040 M³ x Rp. 4,384,800 = Rp. 175,392.00
0.400 Kg x Rp. 13,804 = Rp. 5,521.60
0.200 Ltr x Rp. 8,932 = Rp. 1,786.40
0.018 M³ x Rp. 4,384,800 = Rp. 78,926.40
0.350 Lbr x Rp. 77,546 = Rp. 27,141.10
2.000 Btg x Rp. 15,022 = Rp. 30,044.00
Jumlah (1) = Rp. 318,811.50

0.320 Oh x Rp. 96,750 = Rp. 30,960.00


0.330 Oh x Rp. 119,196 = Rp. 39,334.68
0.033 Oh x Rp. 131,580 = Rp. 4,342.14
0.006 Oh x Rp. 119,196 = Rp. 715.18
Jumlah (2) = Rp. 75,352.00
Jumlah (1) + (2) = Rp. 394,163.50

0.040 M³ x Rp. 4,384,800 = Rp. 175,392.00


0.400 Kg x Rp. 13,804 = Rp. 5,521.60
0.200 Ltr x Rp. 8,932 = Rp. 1,786.40
0.015 M³ x Rp. 4,384,800 = Rp. 65,772.00
0.350 Lbr x Rp. 77,546 = Rp. 27,141.10
6.000 Btg x Rp. 15,022 = Rp. 90,132.00
Jumlah (1) = Rp. 365,745.10

0.320 Oh x Rp. 96,750 = Rp. 30,960.00


0.330 Oh x Rp. 119,196 = Rp. 39,334.68
0.033 Oh x Rp. 131,580 = Rp. 4,342.14
0.006 Oh x Rp. 119,196 = Rp. 715.18
Jumlah (2) = Rp. 75,352.00
Jumlah (1) + (2) = Rp. 441,097.10

1.02 Lbr x Rp. 98,670 = Rp. 100,643.40


0.200 Kg x Rp. 13,804 = Rp. 2,760.80
Jumlah (1) = Rp. 103,404.20

0.200 Oh x Rp. 96,750 = Rp. 19,350.00


0.100 Oh x Rp. 119,196 = Rp. 11,919.60
0.010 Oh x Rp. 131,580 = Rp. 1,315.80
0.010 Oh x Rp. 119,196 = Rp. 1,191.96
Jumlah (2) = Rp. 33,777.36
Jumlah (1) + (2) = Rp. 137,181.56

1.10 Bh x Rp. 70,840 = Rp. 77,924.00


0.050 Kg x Rp. 13,804 = Rp. 690.20
Jumlah (1) = Rp. 78,614.20

0.250 Oh x Rp. 96,750 = Rp. 24,187.50


0.150 Oh x Rp. 119,196 = Rp. 17,879.40
0.015 Oh x Rp. 131,580 = Rp. 1,973.70
0.013 Oh x Rp. 119,196 = Rp. 1,549.55
Jumlah (2) = Rp. 45,590.15
Jumlah (1) + (2) = Rp. 124,204.35
ABK PEKERJAAN SANITASI

1.200 M´ x Rp. 95,000 = Rp. 114,000.00


harga pipa x Rp. 95,000 = Rp. 33,250.00
Jumlah (1) = Rp. 147,250.00

0.081 Oh x Rp. 96,750 = Rp. 7,836.75


0.135 Oh x Rp. 119,196 = Rp. 16,091.46
0.0135 Oh x Rp. 131,580 = Rp. 1,776.33
0.0041 Oh x Rp. 119,196 = Rp. 488.70
Jumlah (2) = Rp. 26,193.24
Jumlah (1) +(2) = Rp. 173,443.24

ABK PEKERJAAN BESI DAN ALUMINIUM

1.100 Kg x Rp. 23,223 = Rp. 25,545.52


0.080 Kg x Rp. 37,758 = Rp. 3,020.64
Jumlah (1) = Rp. 28,566.16

0.006 Oh x Rp. 119,196 = Rp. 715.18


0.060 Oh x Rp. 96,750 = Rp. 5,805.00
0.006 Oh x Rp. 131,580 = Rp. 789.48
0.0003 Oh x Rp. 119,196 = Rp. 35.76
Jumlah (2) = Rp. 7,345.41
Jumlah (1) +(2) = Rp. 35,911.57

1.100 Kg x Rp. 16,500 = Rp. 18,150.00


0.080 Kg x Rp. 28,420 = Rp. 2,273.60
Jumlah (1) = Rp. 20,423.60

0.006 Oh x Rp. 119,196 = Rp. 715.18


0.060 Oh x Rp. 96,750 = Rp. 5,805.00
0.006 Oh x Rp. 131,580 = Rp. 789.48
0.0003 Oh x Rp. 119,196 = Rp. 35.76
Jumlah (2) = Rp. 7,345.41
Jumlah (1) +(2) = Rp. 27,769.01
1.000 M² x Rp. 1,200,000 = Rp. 1,200,000.00
Jumlah (1) = Rp. 1,200,000.00

0.650 Oh x Rp. 119,196 = Rp. 77,477.40


0.650 Oh x Rp. 96,750 = Rp. 62,887.50
0.065 Oh x Rp. 131,580 = Rp. 8,552.70
0.032 Oh x Rp. 119,196 = Rp. 3,814.27
Jumlah (2) = Rp. 152,731.87
Jumlah (1) +(2) = Rp. 1,352,731.87

0.500 Lbr x Rp. 165,000 = Rp. 82,500.00


0.015 Kg x Rp. 13,804 = Rp. 207.06
0.0096 M³ x Rp. 5,400,000 = Rp. 51,840.00
0.250 Kg x Rp. 19,500 = Rp. 4,875.00
Jumlah (1) = Rp. 139,422.06

0.150 Oh x Rp. 96,750 = Rp. 14,512.50


0.400 Oh x Rp. 119,196 = Rp. 47,678.40
0.025 Oh x Rp. 131,580 = Rp. 3,289.50
0.00125 Oh x Rp. 119,196 = Rp. 149.00
Jumlah (2) = Rp. 65,629.40
Jumlah (1) +(2) = Rp. 205,051.46
cat penutup)

0.120 Kg x Rp. 21,000 = Rp. 2,520.00


0.120 Kg x Rp. 33,698 = Rp. 4,043.76
0.260 Kg x Rp. 33,698 = Rp. 8,761.48
Jumlah (1) = Rp. 15,325.24

0.040 Oh x Rp. 96,750 = Rp. 3,870.00


0.120 Oh x Rp. 119,196 = Rp. 14,303.52
0.0120 Oh x Rp. 131,580 = Rp. 1,578.96
0.002 Oh x Rp. 119,196 = Rp. 238.39
Jumlah (2) = Rp. 19,990.87
Jumlah (1) + (2) = Rp. 35,316.11

0.100 Kg x Rp. 37,758 = Rp. 3,775.80


0.010 Bh x Rp. 18,676 = Rp. 186.76
Jumlah (1) = Rp. 3,962.56

0.020 Oh x Rp. 96,750 = Rp. 1,935.00


0.020 Oh x Rp. 119,196 = Rp. 2,383.92
0.02 Oh x Rp. 131,580 = Rp. 2,631.60
0.01 Oh x Rp. 119,196 = Rp. 1,191.96
Jumlah (2) = Rp. 8,142.48
Jumlah (1) + (2) = Rp. 12,105.04

0.100 Kg x Rp. 46,284 = Rp. 4,628.40


Jumlah (1) = Rp. 4,628.40
0.020 Oh x Rp. 96,750 = Rp. 1,935.00
0.020 Oh x Rp. 119,196 = Rp. 2,383.92
0.02 Oh x Rp. 131,580 = Rp. 2,631.60
0.01 Oh x Rp. 119,196 = Rp. 1,191.96
Jumlah (2) = Rp. 8,142.48

1 set x Rp. 97,817 = Rp. 97,817.34


x Rp. = Rp. 0.00
Jumlah (3) = Rp. 97,817.34
Jumlah (1) + (2) + (3) = Rp. 110,588.22

x Rp. 0 = Rp. 0.00


Jumlah (1) = Rp. 0.00

0.030 Oh x Rp. 96,750 = Rp. 2,902.50


0.030 Oh x Rp. 119,196 = Rp. 3,575.88
0.03 Oh x Rp. 131,580 = Rp. 3,947.40
0.01 Oh x Rp. 119,196 = Rp. 1,191.96
Jumlah (2) = Rp. 11,617.74

1 set x Rp. 97,817 = Rp. 97,817.34


1 set x Rp. 135,000 = Rp. 135,000.00
Jumlah (3) = Rp. 232,817.34
Jumlah (1) + (2) + (3) = Rp. 244,435.08
PROGRES MINGGUAN
PEKERJAAN : RELOKASI GUDANG 02 DARI PEKAN BARU KE PERAWANG
LOKASI : PELABUHAN PERAWANG MINGGU KE : 31
TAHUN : INVESTASI 2018 PERIODE : 7 Desember s/d 14 Desember 2018

KONTRAK CCO PROGRES FISIK (%) BOBOT PROGRES (%)


BOBOT CCO
NO URAIAN SAT (%) s.d Minggu s.d Minggu s.d Minggu
VOL VOL Lalu
Minggu Ini s.d Minggu ini
Lalu
Minggu Ini ini

1 2 3 4
I Pekerjaan Persiapan
1 Mobilisasi dan Demobilisasi ls 1.00 1.00 0.70 50.00 50.00 0.35 - 0.35
2 Pembuatan Direksi Kit dan Gudang m2 40.00 40.00 1.36 100.00 100.00 1.36 - 1.36
3 Rambu-rambu Keselamatan & PMK 3 ls 1.00 1.00 0.08 100.00 100.00 0.08 - 0.08
4 Pengukuran awal dan akhir Pekerjaan m' 67.00 67.00 0.20 75.00 25.00 100.00 0.15 0.05 0.20
Jumlah I 2.35 1.95 0.05 2.00

II Pekerjaan Tanah
1 Penimbunan dan pemadatan sertu m3 455.00 - - - - - -
2 Penimbunan dan pemadatan Base A m3 210.00 - - - - - -
Jumlah II - - - -

III Pekerjaan Struktur Gudang CFS


A Pekerjaan Pondasi
1 Pengangkatan tiang pancang ke titik pancang m' 880.00 792.00 7.63 100.00 100.00 7.63 7.63
2 Pemancangan tiang pancang beton kotak 25x25 cm m' 880.00 792.00 1.89 100.00 100.00 1.89 - 1.89
3 Penyambungan tiang pancang ttk 44.00 44.00 0.14 100.00 100.00 0.14 - 0.14
4 Pemotongan kepala tiang pancang ttk 44.00 44.00 0.30 100.00 100.00 0.30 - 0.30
5 Pekerjaan galian tanah untuk pondasi m3 47.03 19.80 0.04 100.00 100.00 0.04 - 0.04
6 Urugkan pasir dibawah pondasi m3 1.24 1.24 0.01 100.00 100.00 0.01 - 0.01
7 Pengecoran lantai kerja beton 1:3:5 m3 1.24 1.24 0.03 100.00 100.00 0.03 - 0.03
8 Pile cap
Beton K 300 m3 18.78 15.96 0.89 100.00 100.00 0.89 - 0.89
Pembesian kg 2,294.46 1,868.73 0.74 100.00 100.00 0.74 - 0.74
Bekisting m2 142.43 114.27 1.22 100.00 100.00 1.22 - 1.22
Urugan Kembali (Back Fill) m3 28.22 8.79 0.01 100.00 100.00 0.01 - 0.01

B Pekerjaan Drainase
1 Galian tanah m3 81.28 80.22 0.15 100.00 100.00 0.15 - 0.15
2 Pengecoran lantai kerja beton 1 : 3 : 5 m3 5.08 10.40 0.22 75.00 25.00 100.00 0.16 0.05 0.22
3 Pekerjaan Drainase
Beton K 300 m3 37.59 58.10 3.26 75.00 25.00 100.00 2.45 0.82 3.26
Pembesian kg 4,286.71 7,342.67 2.93 50.00 50.00 100.00 1.47 1.47 2.93
Bekisting m2 395.24 450.00 3.92 25.00 75.00 100.00 0.98 2.94 3.92
Penimbunan - - -
besi siku
KONTRAK CCO PROGRES FISIK (%) BOBOT PROGRES (%)
BOBOT CCO
NO URAIAN SAT (%) s.d Minggu s.d Minggu s.d Minggu
VOL VOL Lalu
Minggu Ini s.d Minggu ini
Lalu
Minggu Ini ini

1 2 3 4
C Pekerjaan Sloop dan Lantai
1 Sloop 30x50
Beton K 300 m3 16.50 15.05 0.84 100.00 100.00 0.84 - 0.84
Pembesian kg 1,460.73 1,220.96 0.48 100.00 100.00 0.48 - 0.48
Pengecoran lantai kerja beton 1 : 3 : 5 m3 2.75 - -
Bekisting m2 176.00 110.00 0.83 100.00 100.00 0.83 - 0.83
2 Beton penahan tanah 50 x 70
Beton K 300 m3 38.50 -
Pembesian kg 3,078.39 -
Urugan pasir m3 7.70 -
Pengecoran lantai kerja beton 1 : 3 : 5 m3 3.85 -
Bekisting m2 264.00 -
- Beton penahan tanah 50 x 90
Beton K-300 m3 49.50 2.78 100.00 100.00 2.78 - 2.78
Pembesian kg 3,183.69 1.26 100.00 100.00 1.26 - 1.26
Urugan pasir m3 7.70 0.07 100.00 100.00 0.07 - 0.07
Pengecoran lantai kerja beton 1:3:5 m3 3.85 0.08 100.00 100.00 0.08 - 0.08
Bekisting m2 198.00 2.48 100.00 100.00 2.48 - 2.48
Pemasangan Rolag m2 39.16 0.12 100.00 100.00 0.12 - 0.12
3 Lantai Gudang
Beton K 300 m3 150.00 150.00 8.43 - - -
Pembesian kg 14,808.00 14,808.00 5.91 - - -
Urugan pasir m3 60.80 30.00 0.28 - - - -
Lantai Kerja m3 - - - -
Urugan tanah m3 120.00 1,280.69 6.62 80.00 10.00 90.00 5.30 0.66 5.96
Bekisting m2 27.50 17.50 0.22 30.00 30.00 - 0.07 0.07
4 Ram dari Apron ke gudang
Pengadaan Cerucuk 5" - 4 m Btg 160.00 50.00 50.00 - - -
Pemancangan Cerucuk 5" - 4 m Btg 160.00 - - - -
Beton K 300 m3 64.80 34.85 1.94 - - - -
Pembesian kg 3,607.96 4,866.00 1.94 30.00 30.00 - 0.58 0.58
Bekisting m2 286.20 245.00 3.07 30.00 30.00 - 0.92 0.92
pengangkatan tiang pancang ke titik pancang m' 108.00 1.04 100.00 100.00 1.04 1.04
pemancangan tiang pancang beton kotak 25x25 cm m' 108.00 0.26 100.00 100.00 0.26 0.26
Penyambungan tiang pancang ttk 9.00 0.04 100.00 100.00 0.04 0.04
pemotongan kepala tiang pancang ttk 9.00 0.07 100.00 100.00 0.07 0.07

D Pekerjaan Struktur Baja Gudang CFS


1 Pembongkaran dinding bata gudang lama m3 33.00 33.00 0.48 100.00 100.00 0.48 - 0.48
2 Pembongkaran struktur baja lama kg 23,535.40 23,535.40 2.75 100.00 100.00 2.75 - 2.75
3 Pengangkutan struktur baja dari Pekanbaru ke Perawang kg 23,535.40 23,535.40 3.72 100.00 100.00 3.72 - 3.72
4 Pemasangan kembali Besi WF 250.125.6.9 kg 21,460.00 21,460.00 4.48 100.00 100.00 4.48 - 4.48
5 Besi CNP 150.65.20.2,3 kg 5,324.00 6,050.00 6.91 22.00 78.00 100.00 1.52 5.39 6.91
6 Plat 10 mm kg 1,163.37 1,163.37 0.91 100.00 100.00 - 0.91 0.91
KONTRAK CCO PROGRES FISIK (%) BOBOT PROGRES (%)
BOBOT CCO
NO URAIAN SAT (%) s.d Minggu s.d Minggu s.d Minggu
VOL VOL Lalu
Minggu Ini s.d Minggu ini
Lalu
Minggu Ini ini

1 2 3 4
7 Plat 8 mm kg 398.62 398.62 0.31 100.00 100.00 - 0.31 0.31
8 Plat 4 mm kg 146.27 146.27 0.11 100.00 100.00 - 0.11 0.11
9 Pas. Ikatan Angin dia.16 kg 2,050.07 2,050.07 1.06 100.00 100.00 - 1.06 1.06
10 Pas. Trekstang gording dia 12 mm kg 500.19 500.19 0.26 25.00 25.00 0.06 - 0.06
11 Tracker bh 36.00 36.00 0.05 100.00 100.00 - 0.05 0.05
12 Baut 3/4" bh 528.00 528.00 0.21 100.00 100.00 - 0.21 0.21
13 Baut 5/8" bh 1,074.00 1,074.00 0.41 100.00 100.00 - 0.41 0.41
14 Baut 1/2" bh 1,428.00 1,428.00 0.37 100.00 100.00 - 0.37 0.37
15 Angkur baut 1"-60cm bh 66.00 66.00 0.12 100.00 100.00 0.12 - 0.12
16 Pipa 4" untuk buangan air m' 35.80 - -
17 Pipa 4" pipa baja untuk buangan air m' 33.00 0.38 - - - -
18 Pasang kembali kisi-kisi m' 80.00 80.00 0.34 100.00 100.00 - 0.34 0.34
19 Pengecatan m2 2,252.66 2,252.66 0.77 70.00 30.00 100.00 0.54 0.23 0.77

E Pekerjaan Atap
1 Atap spandek 0,35 mm m2 932.80 976.80 3.80 - - - -
2 Rabung atap m' 44.00 44.00 0.15 - - - -
3 List plank m2 69.00 88.40 0.19 - - - -
4 Talang m' 88.00 88.00 0.51 - - - -

F Pekerjaan dinding
1 Pasangan bata m2 220.00 290.00 0.79 35.00 30.00 65.00 0.28 0.24 0.52
2 Plesteran dinding m2 440.00 580.00 1.05 40.00 40.00 - 0.42 0.42
3 Pengecatan dinding m2 440.00 580.00 0.58 - - - -
4 Penutup Dinding Spandek m2 318.00 1.23 - - - -
5 Rangka Penutup dinding CNP 100.50.20.2,3 kg 648.10 0.65 - - - -

G Pekerjaan pintu
1 Pek.Pas. Pintu gudang(dlm 2.5m x 5m x 4) m2 48.70 48.70 0.39 - - - -

H Pekerjaan Instalasi
1 Instalasi listrik + panel ls 1.00 1.00 1.42 - - - -
2 Instalasi air + panel ls 1.00 1.00 0.34 - - - -

Jumlah III 96.88 46.29 18.97 65.25


KONTRAK CCO PROGRES FISIK (%) BOBOT PROGRES (%)
BOBOT CCO
NO URAIAN SAT (%) s.d Minggu s.d Minggu s.d Minggu
VOL VOL Lalu
Minggu Ini s.d Minggu ini
Lalu
Minggu Ini ini

1 2 3 4
IV Pekerjaan Lain-lain
1 Laporan, Dokumentasi dan Administrasi ls 1.00 1.00 0.25 50.00 20.00 70.00 0.13 0.05 0.18
2 Pembersihan Akhir ls 1.00 1.00 0.30 - - - -
Jumlah IV 0.56 0.13 0.05 0.18

99.80 48.36 19.07 67.43

Perawang, 05 November 2018


Diperiksa Oleh Tim Pengawas : Dibuat Oleh
ASMEN FASILISTAS PT. TISA LESTARI
1. RANDY MAMIN : SITE MENEJER

2. AHMAD THOHIR RAMBE :

MORGANDA 3. MARIO DOVAN : ADI EFENDI


PEKERJAAN PERSIAPAN
panjang lebar Volume (m')
Pengukuran dan bouwplank 45 22 67

PEKERJAAN TANAH
luas
Penimbunan dan pemadatan sirtu 1035 m2
Cor lantai beton 1035 m2
Base A

PEKERJAAN PONDASI
Pengadaan tiang pancang 25 x 25
Pengangkatan tiang pancang ke titik pancang
Pemancangan tiang pancang
Penyambungan tiang pancang
Pemotongan kepala tiang pancang
Pekerjaan Galian Tanah Untuk Pondasi

Pile cap
Volume beton
jumlah pile cap
lean concrete
sand beddng
bekisting

total beton
total lean concrete
total sand beddng
total tulangan D16
total tulangan D10
total bekisting
total urugan kembali

Tulangan Pile Cap


Dimensi pile cap Diameter tulangan Panjang tulangan
0.55 x 1.3 x 0.5 0.016 m 1.3
0.01 m 1.8

0.44 x 0.44 x 1.9 0.016 m 1.9


0.01 m 1.46

PEKERJAAN DRAINASE
Panjang drainase
p1 p2 p
43 20.5 127 m 43 44 87
tutup drainase 0.5 0.1 0.05

Penampang saluran A (m2) Volume beton (m3)


0.296 37.592 22.19 m3

Galian tanah Volume galian (m3)


81.28 24.36 m3

Lean concrete Volume beton (m3)


5.08

Tulangan
jumlah panjang berat per m Total berat
D10 36 87 0.617 1932.444 kg
D8 580.00 4.3829 0.395 1004.122 kg

Total tulangan 2936.5664 kg

Bekisting
Keliling 311.213 cm 2.51 m'
3.11213 m
Luas 395.2405 m2 218.54 m2

PEKERJAAN SLOOF DAN LANTAI


Sloof 30 x 50

Volume
Sloof 30 x 50 lebar tinggi panjang (per meter) Volume per meter
0.3 0.5 1 0.15 m3

Dimensi sloof Diameter tulangan Panjang tulangan


0.3 x 0.5 x 1 0.012 m 1
0.01 m 1.6

total panjang 110 m 9.68 100.32 m'

D13 890.8416 kg
D10 330.1197 kg

Total beton 16.5 m3 15.05 m3

Lean concrete 2.75 m3


Sand bedding 5.5 m3
CCO
Bekisting 176 m2 110.00 m2

Lantai Gudang

Luas lantai panjang lebar tebal Volume


40 15 0.25 150

Beton lantai 150 m3

Dimensi slab Diameter tulangan Panjang tulangan


lx (m) ly (m) lx (m)
5x 5x 0.25 0.01 0.01 5

Total berat tulangan


D13 14808 kg

p l
Urugan tanah 120 m3 40 15
40 17
Urugan pasir 60.8 m3 40 15

Lantai Kerja 40 15

Bekisting 27.5 m2

Ram

Volume beton 64.8 m3 56.92 m3


lean concrete 6.475 m3 2.37 m3
sand beddng 12.95 m3 2.37 m3
bekisting 286.2 m2

total tulangan D16 2319.66 m3


total tulangan D10 1288.296 m3

Tulangan Ram
Dimensi ram Diameter tulangan Panjang tulangan
36 x 2x 0.9 0.01 m 5.8
0.016 m 73.5

Ram Revisi

Volume beton 34.85 m3


- Telapak 0.30 0.50 48.00 1.00 7.20
- Plat Lantai 0.20 2.10 40.00 1.00 16.80
- DPT 0.20 1.55 35.00 1.00 10.85
lean concrete 5.00 m3
0.05 0.50 48.00 1.00 1.20
0.05 1.90 40.00 1.00 3.80

sand beddng 5.00 m3

bekisting 245.00 m2
- Plat vertikal (DPT) 1.75 35.00 2.00 245.00

Pemasangan Cerucuk 5" - 4m 160.00 btg

Tulangan Ram Diameter


tulangan Panjang tulangan
- Telapak 48.00 x 0.3 x 0.5 0.01 m 1.60
0.016 m 48.0
- Plat Lantai 40.00 x 2.1 x 0.2 0.01 m 4.60
0.01 m 80.3
- Dinding Penahan Tanah 35.00 x 2x 0.2 0.01 m 4.40
0.01 m 70.3

Beton Penahan Tanah

Volume
50 x 70 lebar tinggi panjang (per meter) Volume per meter
0.5 0.7 1 0.35 m3

Dimensi Diameter tulangan Panjang tulangan


0.5 x 0.7 x 1 0.016 m 1
0.01 m 2.2

total panjang 110 m

D16 2082.96 kg
D10 995.4267 kg

Total beton 38.5 m3

Lean concrete 3.85 m3


Sand bedding 7.7 m3

Bekisting 264 m2

Beton Penahan Tanah

Volume
50 x 90 lebar tinggi panjang (per meter) Volume per meter
0.5 0.9 1 0.45 m3

Dimensi Diameter tulangan Panjang tulangan


0.5 x 0.9 x 1 0.016 m 1
0.01 m 1
0.01 m 2.6

total panjang 110 m

D16 1735.8 kg
D10 271.48 kg
D10 1176.413 kg

Total beton 49.5 m3

Lean concrete 3.85 m3


Sand bedding 7.7 m3

Bekisting 198 m2

Rolag Bata
p l t jmlh volume
4.45 0.5 8 17.8
4.45 0.3 8 10.68
4.45 0.4 6 10.68
39.16

PEKERJAAN STRUKTUR BAJA


total panjang
Baja WF 250x125x6x9 725 m
Besi CNP 150.65.20.2,3 968 m

PLAT 10 mm
panjang lebar tebal volume (m3berat baja (kg/m3)
0.52 0.125 0.01 0.00065 7850

PLAT 8 mm
panjang lebar tebal volume (m3berat baja (kg/m3)
0.232 0.12 0.008 0.000223 7850

PLAT 4 mm
unt luas brt/m2 v
utk Gording 94.5 0.01 32.39583 30.61406
utk Gording 357 0.01 32.39583 115.6531
146.2672

Baut 5/8"
unt
I 1074

Besi 16
unt p brt/m2 v
utk Gording 16 9.01 14.22081 2050.072

Besi 12
unt p brt/m2 v
Scrod 220 1.6 1.421 500.192

Baut 3/4"
unt
I 528

Baut 1/2"
unt
I 1428

Anchor bolt 1"-60 cm


unt unit jmlh
I 66 4 22

Pengecatan
total luas 2252.657 76.4976 2329.154

Pipa 4" untuk buangan air


p
35.8 m

Pembongkaran struktur baja gudang lama

WF.250.125.6.9 unt p brt/m v


tiang 22 7 29.6 4558.4
kuda2 22 22 29.6 14326.4
voute 11 1.2548 29.6 408.5629
voute apron 9 1.3434 29.6 357.8818
balok kelilin 3 110.0000 29.6 9768
29419.24

PEKERJAAN ATAP
Atap Spandek 0,35 mm 932.8 m2
Rabung Atap 44 m
List plank 69 m2
Talang 88 m

PEKERJAAN DINDING
Pasangan Bata
Plesteran dinding
Pengecatan dinding

PEKERJAAN PINTU
Panjang (mUnit Volume (m')
Kusen alumunium 4.87 4 19.48

Luas (m2) Unit Volume (m2)


Pintu alumunium 24.35 2 48.7

Pipa buangan Air (pipa baja dia 4")


3.3 10 33 m'

#REF!
tebal volume
0.5 m 517.5 m3 40 15 2
0.3 m 310.5 m3
40 15 2

880 m
880 m
880 m
44 ea
44 ea
24.75 m3 19.80 m3

0.72534 m3
22 ea
0.05625 m3
0.05625 m3
5.194 m2

15.95748 m3
1.2375 m3
1.2375 m3
1345.5922 kg
523.14196 kg 1868.734
114.268 m2
8.79 m3

Panjang tulangan Jumlah tulangan Berat besi Total panjang Total berat
m 9 1.578 kg/m 11.7 m 36.9252 kg
m 6 0.617 kg/m 10.8 m 6.6636 kg

m 6 1.578 kg/m 11.4 m 17.9892 kg


m 19 0.617 kg/m 28 m 17.11558 kg
78.69358
Panjang tulangan Jumlah tulangan Berat besi Total panjang Total berat
m 10 0.89 kg/m 10.00 m 8.88
m 3.333 0.62 kg/m 5.33 m 3.29
12.170667
Panjang tulangan Jumlah tulangan Berat besi Total berat Jumlah slab
ly (m) lx ly lx ly lx ly
5 50 50 0.62 0.617 308.5 308.5 24

CCO
lbr ramp t
2 1.40 945.00 m3
2 0.45 335.69 m3
0.05 30.00 m3

0.05 30.00 m3

17.50 m2

Panjang tulangan Jumlah tulangan Berat besi Total panjang Total berat
m 360 0.62 kg/m 2088 m 1288.296
m 20 1.58 kg/m 1470 m 2319.66
Jumlah tulangan Jmlh Unit
Panjang tulangan Berat besi Total panjang Total berat
m 320 1 0.62 kg/m 512.00 m 315.90
m 8 1 1.58 kg/m 384.10 m 606.11
m 400 1 0.62 kg/m 1,840.00 m 1,135.28
m 20 1 0.62 kg/m 1,606.10 m 990.96
m 350 1 0.62 kg/m 1,540.00 m 950.18
m 20 1 0.62 kg/m 1,406.10 m 867.56
4,866.00

Panjang tulangan Jumlah tulangan Berat besi Total panjang Total berat
m 12 1.58 kg/m 12 m 18.936
m 6.667 0.62 kg/m 14.666667 m 9.0493333
27.985333
Panjang tulangan Jumlah tulangan Berat besi Total panjang Total berat
m 10 1.58 kg/m 10 m 15.78
m 4 0.62 kg/m 4m 2.468
m 6.667 0.62 kg/m 17.333333 m 10.694667
28.942667

berat per m total berat luas (m2)


29.6 kg/m 21460 kg 716.3
5.5 kg/m 5324 kg 606.1616

berat per plat (kg) jumlah plat Total berat plat luas (m2)
5.1025 228 1163.37 kg 597.36

berat per plat (kg) jumlah plat Total berat plat


1.748352 228 398.624256 kg 328.32

0.945
3.57
7850
0.000201

0.000113

108
144
32
48
24 404
48

vol
88

4 kg/m2 3731.2 kg 44 22.2


44
44 44.4
44 2

220 m2
0 - m3

0 - m3

Jumlah pondasi Total berat


22 812.3544 kg
22 146.5992 kg

22 395.7624 kg 2.56 533.2378


22 376.54276 kg 1345.592 1868.734
108.492 kg/m3 523.142
kg
kg
kg
81.137778 kg/m3
total berat (kg)

7404 7404
98.72 kg/m3

kg
kg
55.678333
kg
kg
kg
kg
kg
kg

kg
kg
kg
79.958095 kg/m3
kg
kg
kg
kg
64.317037 kg/m3

total panjan volume kg

1,100.00 6,050.00
14.22081

1.420503

976.8
44
88.4
88
PEK. DRAINASE SISI IKPP 7 SISI RABANA
PANJANG SALURAN UTARA = 152 M - Galian 55.86
PANJANG SALURAN BARAT = M - Lantai Kerja 5.32
TOTAL PANJANG SALURAN = 152 M

A BETON SALURAN UTARA (IKPP)

VOLUME BETON A =
ket P L T Volume
1 dinding parit sisi ikpp 0.6 0.15 152 13.68 m3
2 Lantai Parit 0.3 0.15 152 6.84 m3
3 Dinding parit sisi timbunan 0.6 0.15 152 13.68 m3

Total Vol 34.20 m3


B BETON SALURAN BARAT

ket P L T l vol
dinding 0 1 0.15 2 0
lantai 0 0.4 0.15 2 0

0 M3

C PEMBESIAN
SALURAN UTARA
unt p brt/kg v
Dinding parit sisi IKPP Ø 12 10 152 0.8917 1355.3333
Ø8 608 1.3 0.395 312.208
1667.5413

Dinding parit sisi timbunan Ø 12 10 152 0.8917 1355.3333


Ø8 608 1.3 0.395 312.208
1667.5413

Lantai Parit Ø 12 4 152 0.8917 542.13333


Ø8 608 1.3 0.395 312.208
854.34133
Total Vol 4,189.42 kg

SALURAN BARAT
dnding unt p brt/kg v
Ø 12 12 0 0.8917 0
Ø8 0 1.5 0.395 0
0 kg

lantai unt p brt/kg v


Ø 12 4 0 0.8917 0
Ø8 0 1.5 0.395 0
0 kg

Total Vol - kg
D BEKISTING
SALURAN UTARA
p l Luas
dinding 152 1.2 182.4
152 0.8 121.6

101.33 m2

SALURAN BARAT
p l Luas
0 0.6 0
0 0.6 0
0 0.4 0
0.00 m2

E PEKERJAAN BETON PENGUNCI

1 BETON (Jarak 2 meter)

P L T JMLH V

0.15 0.15 0.3 76 1.71 SAL UTARA


Total Vol 1.71 m3

2 PEMBESIAN

unt p brt/kg jmlh v


Ø 12 4 0.6 0.892 76 162.64
Ø8 3 0.6 0.395 76 54.036

Total Vol 216.68

3 BEKISTING
p l Luas jml
0.45 0.3 0.405 76 30.78

Total Vol 30.78 m2


m3
m3
SAL UTARA

SAL
UTARA

Kg
DRAFT CCO
PEKERJAAN
LOKASI
TAHUN

BULAN 1 BULAN 2 BULAN 3 BULAN 4 BULAN 5 BULAN 6 BULAN 7 BULAN 8


BOBOT CCO
NO URAIAN (%) MINGGU 1 MINGGU 2 MINGGU 3 MINGGU 4 MINGGU 5 MINGGU 6 MINGGU 7 MINGGU 8 MINGGU 9 MINGGU 10 MINGGU 11 MINGGU 12 MINGGU 13 MINGGU 14 MINGGU 15 MINGGU 16 MINGGU 17 MINGGU 18 MINGGU 19 MINGGU 20 MINGGU 21 MINGGU 22 MINGGU 23 MINGGU 24 MINGGU 25 MINGGU 26 MINGGU 27 MINGGU 28 MINGGU 29 MINGGU 30 MINGGU 31 MINGGU 32 MINGGU 33
18 Mei - 20 Mei 21 Mei - 27 Mei 28 Mei - 03 Juni 04 Juni - 10 Juni 11 Juni - 17 Juni 18 Juni - 24 Juni 25 Juni - 01 Juli 02 Juli - 08 Juli 09 Juli - 15 Juli 16 Juli - 22 Juli 23 Juli - 29 Juli 30 Juli - 05 Agus 06 Agus-12 Agus 13 Agus-19 Agus 20 Agus-26 Agus 27 Agus-02 Sept 03 Sept - 09 Sept 10 Sept - 16 Sept 17 Sept - 23 Sept 24 Sept - 30 Sept 01 Okt - 07 Okt 08 Okt - 14 Okt 15 Okt - 21 Okt 22 Okt - 28 Okt 29 Okt - 04 Nov 05 Nov - 14 Nov
1 2
I Pekerjaan Persiapan 2.36 0.09 0.09 0.09 0.09 0.09 0.09 0.09 0.09 0.09 0.09 0.09 0.09 0.09 0.09 0.09 0.09 0.09 0.09 0.09 0.09 0.09 0.09 0.09 0.09 0.09 0.09 0.05 0.05 0.05 0.05 0.05 0.05 0.05

II Pekerjaan Tanah

III Pekerjaan Struktur Gudang CFS


A Pekerjaan Pondasi 12.93 1.62 1.62 1.62 1.62 1.62 1.62 1.62 1.62
RENCANA ADDENDUM

B Pekerjaan Drainase 10.49 1.05 1.05 1.05 1.05 1.05 1.05 1.05 1.05 1.05 1.05 1.75 1.75 1.75 1.75 1.75 1.75

C Pekerjaan Sloop dan Lantai 38.36 3.20 3.20 3.20 3.20 3.20 3.20 3.20 3.20 3.20 3.20 3.20 3.20 4.40 4.40 4.40 4.40

D Pekerjaan Struktur Baja Gudang CFS 22.93 3.82 3.82 3.82 3.82 3.82 3.82 4.17 4.17 4.17 4.17

E Pekerjaan Atap 4.67 1.56 1.56 1.56 1.56 1.56 1.56

F Pekerjaan dinding 4.07 1.36 1.36 1.36 1.02 1.02 1.02 1.02

G Pekerjaan pintu 1.87 0.94 0.94 0.94 0.94

H Pekerjaan Instalasi 1.76 0.35 0.35 0.35 0.35 0.35 0.44 0.44 0.44 0.44

IV Pekerjaan Lain-lain 0.55 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.42

JUMLAH 100.00
TOTAL RENCANA 0.11 5.55 5.55 5.55 1.73 1.73 1.73 4.93 4.93 4.36 4.36 4.36 4.36 4.36 4.36 4.36 4.36 4.36 4.36 3.93 4.29 5.84 4.31 4.31 1.82 0.11
TOTAL RENCANA KUMULATIF 0.11 5.66 11.21 16.77 18.49 20.22 21.95 26.88 31.80 36.16 40.52 44.88 49.23 53.59 57.95 62.31 66.66 71.02 75.38 79.31 83.60 89.44 93.75 98.07 99.89 100.00
TOTAL PROGRESS AKTUAL - - 1.39 1.39 1.39 1.39 1.39 1.49 1.49 1.49 1.49 1.49 1.49 1.49 1.49 1.49 1.49 2.28 2.28 2.28 2.28 2.28 2.28 2.28 2.28 2.28
TOTAL PROGRESS AKTUAL KUMULATIF - - 1.39 2.78 4.17 5.56 6.95 8.44 9.94 11.43 12.92 14.42 15.91 17.41 18.90 20.39 21.89 24.17 26.45 28.74 31.02 33.30 35.59 37.87 40.15 42.43
DEVIASI PROGRESS TERHADAP HD RENCANA
Rencana Kemajuan Addenum Pekerjaan 6.19 6.19 10.81 11.83 9.92 9.92 3.05
Rencana Komulatif Kemajuan Addendum Pekerjaan ### 48.63 54.82 65.63 77.46 87.38 97.30 100.35
AKTUAL KEMAJUAN ADDENDUM PEKERJAAN
AKTUAL KEMAJUAN ADDENDUM PEKERJAAN KUMULATIF