Pemakaian Material

Blok D.17 Blok D.18


No Tanggal Jenis Material Sat VOL VOL
Harga Jumlah
Terpakai Terpakai
1 8/21/2018 Bendrat kg 0.5 18,000 9,000 1
2 8/21/2018 Benang nilon (kenur) ikat 1.0 4,000 4,000 1
3 8/21/2018 paku 5" kg 0.8 16,500 12,375 1
4 8/21/2018 paku 7" kg 0.8 16,500 12,375 1
5 8/21/2018 kaso usuk speck glugu biji 16.0 20,000 320,000 15
1 8/29/2018 Batu kali/belah rit 1
2 8/29/2018 semen holcim sak 4
3 8/30/2018 Pasir rit 1
4 8/30/2018 semen holcim sak 2
5 8/31/2018 kaso usuk biji 3
6 8/31/2018 pasir rit 0.5 325,000 162,500
7 8/31/2018 pasir rit 1
8 8/31/2018 batu belah (dump) rit 0.5 750,000 375,000
9 8/31/2018 batu belah (dump) rit 1.0 750,000 750,000
10 8/31/2018 begel 8 x12 (20 kg) kg 13
11 8/31/2018 besi beton 8" biji 22
12 8/31/2018 semen holcim sak 6.0 42,000 252,000 2
13 1/9/2018 Batu koral rit 1
14 9/1/2018 kawat bendrat kg 3
15 9/1/2018 pasir rit 2.0 325,000 650,000
16 9/1/2018 papan cor lbr 20
17 9/1/2018 semen holcim sak 5.0 42,000 210,000
18 9/1/2018 begel 8 x12 (20 kg) kg 6.6 70,076 462,500
19 9/2/2018 semen holcim sak 5
20 9/2/2018 begel 8 x 10 (25kg) kg 13
21 9/2/2018 besi beton 8" biji 22.0 46,000 1,012,000 10
22 9/2/2018 kawat bendrat kg 2.5 18,000 45,000
23 9/3/2018 semen holcim sak 1
24 9/3/2018 besi beton 8" biji 6.0 46,000 276,000
25 9/3/2018 begel 8 x 10 (25kg) kg 5.0 18,516 92,581
1 9/4/2018 Begel 8x10 Kg 10.0 18,516 185,161
2 9/4/2018 Semen Holcim Sak 6.0 42,000 252,000
3 9/4/2018 Paku 5" Kg 1.0 16,500 16,500
4 9/4/2018 Besi Beton 8" Biji 9.0 46,000 414,000
5 9/4/2018 Papan Cor Biji 20.0 6,500 130,000
6 9/6/2018 Besi Beton 8" Biji 12
7 9/6/2018 Paku 7" Kg 1.0 16,500 16,500
8 9/6/2018 Semen Holcim Sak 5
9 9/6/2018 Tanah Urug Rit 1
10 9/6/2018 Mortar Sak 7
11 9/6/2018 Pasir rit 1
12 9/6/2018 Bata Ringan m3 5
13 9/7/2018 Mortar Sak 2.0 60,000 120,000
14 9/7/2018 Batu Koral (L300) Rit 1
15 9/7/2018 Begel 8x12 Kg 6
16 9/7/2018 Semen Holcim Sak 6.0 42,000 252,000
17 9/7/2018 Besi Beton 8" Biji 12
18 9/7/2018 Pasir Rit 0.5 325,000 162,500
19 9/7/2018 Bata Ringan m3 5.0 580,000 2,900,000
20 9/8/2018 Besi Beton 8" Biji 8
21 9/8/2018 Semen Holcim Sak 2.0 42,000 84,000
22 9/8/2018 Begel 8x12 Kg 6
23 9/8/2018 Batu Koral (L300) Rit 0.5 350,000 175,000
24 9/8/2018 Mortar Sak 5.0 60,000 300,000
25 9/8/2018 Bata Ringan m3 4.0 580,000 2,320,000
26 9/8/2018 Kawat Bendrat Kg 3

TOTAL (Periode 1 : s/d tgl 08 sept) 11,972,992

1 10/09/2018 tanah urug rit 2


2 10/09/2018 kaso biji 4.0 20,000 80,000
3 12/09/2018 tanah urug rit 2.0 230,000 460,000
4 9/13/2018 tanah urug rit 1.0 230,000 230,000
5 9/13/2018 bambu biji 1
6 9/14/2018 mortar sak 2
7 9/14/2018 tanah urug dump 1.0 230,000 230,000

TOTAL (Periode 2 : 10-15 sept) 1,000,000

1 9/17/2018 Semen Gresik sak 1


2 9/17/2018 paku 5 kg 2
3 9/17/2018 tanah urug rit 1
4 9/17/2018 mortar sak 2
5 9/17/2018 papan cor biji 20
6 9/18/2018 mortar sak 2.0 60,000 120,000 1
7 9/18/2018 bambu biji 6.0 20,000 120,000
8 9/18/2018 kawat bendrat kg 1.0 18,000 18,000 1
9 9/18/2018 besi 8 biji 2
10 9/18/2018 Semen Gresik sak 1
11 9/18/2018 bata ringan m3 10.8 580,000 6,264,000 11
12 9/20/2018 mortar sak 3.0 60,000 180,000
13 9/19/2018 bambu biji 6
14 9/20/2018 Semen Gresik sak 1.0 48,500 48,500 1
15 9/20/2018 paku 5 kg 1.5 16,500 24,750
16 9/20/2018 kawat bendrat kg 1.0 18,000 18,000
17 9/20/2018 papan cor lbr 10
18 9/20/2018 besi 8 biji 5.0 46,000 230,000 6
19 9/20/2018 begel 8 x 10 (20kg) kg 10.0 18,516 185,161
20 9/21/2018 papan cor lbr 6
21 9/21/2018 bambu biji 4
22 9/21/2018 Triplex 9 mm lbr 1
23 9/21/2018 Semen Holcim sak 1
24 9/22/2018 bambu ljr 4.0 20,000 80,000
25 9/22/2018 Semen Holcim sak 1.0 48,500 48,500 2
26 9/22/2018 kawat bendrat kg 1.0 18,000 18,000
27 9/22/2018 paku 7 kg 1.0 16,500 16,500 1
28 9/22/2018 Triplex 9mm lbr 2
29 9/22/2018 besi 8 biji 5

TOTAL (Periode 3 : 17-23 sept) 7,371,411

1 24/09/2018 Semen Holcim sak 2.0 43,000 86,000 1


2 24/09/2018 papan cor biji 10.0 6,500 65,000
3 24/09/2018 kawat bendrat kg 1.0 18,000 18,000
4 24/09/2018 besi 8 biji 10.0 46,000 460,000 5
5 24/09/2018 Triplex 9mm lbr 2.0 96,000 192,000
6 25/09/2018 paku 5 kg 1
7 25/09/2018 Semen Holcim sak 2
8 9/26/2018 papan cor lbr 6.0 6,500 39,000
9 9/26/2018 semen sak 4.0 43,000 172,000 3
10 9/26/2018 paku 5 kg 1.0 16,500 16,500
11 9/26/2018 paku 7 kg 1.0 16,500 16,500
12 9/26/2018 bambu biji 5.0 20,000 100,000
13 9/26/2018 besi 8 biji 10.0 46,000 460,000
14 9/26/2018 mortar sak 2
15 9/27/2018 Semen Holcim sak 1.0 43,000 43,000
16 9/27/2018 pasir rit 1.0 325,000 325,000 1
17 9/27/2018 papan cor lbr 8.0 6,500 52,000
18 9/27/2018 batu koral rit 0.5 350,000 175,000
19 9/27/2018 batu koral rit 0.5 350,000 175,000 1
20 9/28/2018 kawat bendrat kg 1.0 18,000 18,000 1
21 9/28/2018 besi 8 biji 15
22 9/28/2018 bambu biji 6
23 9/28/2018 begel 8 x 10 kg 5.0 18,516 92,581
24 9/28/2018 paku 5 kg 1.0 16,500 16,500
25 9/28/2018 papan cor biji 10.0 6,500 65,000 10
26 9/28/2018 begel 8 x12 kg 13
27 9/28/2018 Semen Holcim kg 1
28 9/29/2018 Semen Holcim kg 2.0 43,000 86,000
29 9/29/2018 besi 8 biji 10.0 46,000 460,000
TOTAL (Periode 4 : 24-29 sept) 3,133,081

1 10/1/2018 Semen Holcim sak 2.0 43,000 86,000 2


2 10/1/2018 besi 8 biji 5.0 46,000 230,000
3 10/1/2018 besi 8 biji 5.0 46,000 230,000 4
4 10/1/2018 kawat bendrat kg 1.0 18,000 18,000 1
5 10/1/2018 begel 8 x 12 kg 10.0 70,076 700,758
6 10/1/2018 mortar sak 2.0 60,000 120,000
7 10/2/2018 paku uk 5 kg - 1
8 10/2/2018 kawat bendrat kg 1.0 18,000 18,000
9 10/2/2018 papan cor biji 10.0 6,500 65,000
10 10/2/2018 paku 7 kg 1.0 16,500 16,500
11 10/2/2018 besi 8 biji 10.0 46,000 460,000
12 10/2/2018 Semen Holcim sak 3.0 43,000 129,000 2
13 10/2/2018 papan cor biji 10
14 10/3/2018 Semen Holcim sak 2
15 10/4/2018 Semen Holcim sak 2.0 43,000 86,000
16 10/4/2018 besi 8 biji 6
17 10/5/2018 paku 5 kg 1.0 16,500 16,500
18 10/5/2018 Semen Holcim sak 4.0 43,000 172,000 2
19 10/6/2018 mortar sak 1
20 10/6/2018 kawat bendrat kg 1
21 10/6/2018 Semen Holcim sak 4.0 43,000 172,000 3
22 10/6/2018 besi 8 biji 5.0 46,000 230,000
23 10/6/2018 begel 8 x 12 kg 5.0 70,076 350,379

TOTAL (Periode 5 : 01-06 okt) 3,100,136

24 10/8/2018 pasir rit 1.0 325,000 325,000 1


25 10/8/2018 semen (merah putih) sak 4.0 42,000 168,000 4
26 10/9/2018 semen (merah putih) sak 4.0 42,000 168,000 2
27 10/9/2018 besi 8 biji 2.0 46,000 92,000
28 10/9/2018 kawat bendrat kg 1.0 18,000 18,000
29 10/10/2018 semen (merah putih) sak 2.0 42,000 84,000 4
30 10/10/2018 besi 8 biji 1.0 46,000 46,000 2
31 10/11/2018 semen Holcim sak 3.0 45,000 135,000 2
32 10/12/2018 semen Holcim sak 4.0 45,000 180,000 2
33 10/12/2018 genteng flat biji 500.0 4,000 2,000,000 500
34 10/12/2018 stop ending biji 10.0 5,500 55,000 10
35 10/12/2018 bumbungan (wuwung) biji 50.0 6,500 325,000 50
36 10/12/2018 kanal 0,75 biji 22.0 82,000 1,804,000 21
37 10/12/2018 drilling sds 12x20 biji 500.0 135 67,500 500
38 10/12/2018 reng 0,45 biji 0.5 35,000 17,500 1
39 10/13/2018 dynabolt biji 20.0 1,500 30,000 20
40 10/13/2018 reng 0,45 biji 18.0 35,000 630,000 18
41 10/13/2018 Drilling sds 8 x 13 biji 500.0 135 67,500 500
42 10/13/2018 semen Holcim sak 2

TOTAL (Periode 6 : 08-13 Okt) 6,212,500

43 10/15/2018 semen Holcim sak 4.0 45,000 180,000


44 10/15/2018 benang nylon (kenur) ikat 1.0 4,000 4,000
45 10/15/2018 kanal 0,75 biji 4.0 82,000 328,000 5
46 10/15/2018 reng 0,45 biji 12.0 35,000 420,000 12
47 10/15/2018 mortar sak - 1
48 10/15/2018 bambu biji - 4
49 10/16/2018 drywall 6 x 2" (600biji) biji 100.0 80 8,000 100
50 10/16/2018 wall angel biji 5.0 8,500 42,500 5
51 10/16/2018 listplank biji 4.0 50,000 200,000 4
52 10/16/2018 drywall 6 x 2" (600biji) biji 250.0 80 20,000 250
53 10/16/2018 talang seng meter 3.8 41,000 155,800 4
54 10/16/2018 driiling sds 8 x 13 biji 500.0 135 67,500 500
55 10/16/2018 kanal 0,75 biji 1.0 82,000 82,000 1
56 10/16/2018 pasir rit 1.0 325,000 325,000
57 10/16/2018 besi 8 biji 4.0 46,000 184,000
58 10/16/2018 begel 8 x 10 kg 2.5 18,516 46,290
59 10/16/2018 semen holcim sak 4.0 45,000 180,000
60 10/17/2018 reng 0,45 biji 19.5 35,000 682,500 20
61 10/17/2018 kanal 0,75 biji 3.0 82,000 246,000 3
62 10/17/2018 semen sak 3.0 45,000 135,000 3
63 10/17/2018 pasir rit - 1
64 10/18/2018 kanal 0,75 biji 3.5 82,000 287,000 4
65 10/18/2018 reng 0,45 biji 10.0 35,000 350,000 10
66 10/18/2018 driiling sds 8 x 13 biji 250.0 135 33,750 250
67 10/19/2018 wall angel biji 5.0 8,500 42,500 5
68 10/19/2018 list plank biji 4.0 50,000 200,000 3
69 10/19/2018 list plank biji 1
70 10/19/2018 talang galvalum meter 3.6 28,000 100,800 4
71 10/19/2018 bis beton biji 3.0 80,000 240,000 3
72 10/19/2018 tutup bis beton biji 2.0 50,000 100,000 2
73 10/20/2018 semen sak 2.0 45,000 90,000
74 10/20/2018 benang nylon (kenur) ikat 1.0 4,000 4,000

TOTAL (Periode 7 : 15-20 Okt) 4,754,640

1 10/22/2018 mortar sak 1


2 10/22/2018 besi 8 biji 4
3 10/22/2018 begel 8 x 10 kg 3
4 10/22/2018 kawat bendrat kg 1
5 10/22/2018 semen holcim sak 3.0 45,000 135,000
6 10/22/2018 pasir rit 1.0 325,000 325,000
7 10/23/2018 semen holcim sak 2
8 10/24/2018 semen holcim sa 3
9 10/24/2018 mortar sak 1
10 10/24/2018 besi 8 biji 4
11 10/24/2018 begel 8x10 kg 3
12 10/24/2018 bata merah biji 1,000
13 10/25/2018 semen holcim sak 3.0 45,000 135,000 3
14 10/26/2018 besi 8" biji 1
15 10/26/2018 begel 8 x 10 biji 2
16 10/26/2018 pasir rit
17 10/26/2018 genteng flat biji 100.0 4,000 400,000 100
18 10/27/2018 pasir rit 2
19 10/27/2018 semen holcim sak 2.0 45,000 90,000 2

TOTAL (Periode 8 : 22-27 okt) 1,085,000

1 10/29/2018 genteng flat biji 25.0 4,000 100,000 25


2 10/29/2018 semen sak 1.0 45,000 45,000 1
3 10/30/2018 keni 3 biji 1.0 7,000 7,000 1
4 10/30/2018 keni 4 biji 1.0 12,500 12,500 1
5 10/30/2018 pvc 4 biji 1.0 147,000 147,000 1
6 10/30/2018 pvc 3 biji 1.0 105,000 105,000 1
7 10/30/2018 semen holcim sak 3.0 45,000 135,000 3
8 10/31/2018 pvc 3 biji 4.0 105,000 420,000 4
9 10/31/2018 mortar sak 1.0 60,000 60,000
10 11/1/2018 semen sak 1.0 45,000 45,000 1
11 11/1/2018 keni 3 biji 1.0 7,000 7,000 1
12 11/2/2018 semen sak 2.0 45,000 90,000 2

TOTAL (Periode 9 : 29 Okt-02 Nov) 1,173,500

1 11/3/2018 kalsium kuda sak 1.0 30,000 30,000


2 11/3/2018 kawat bendrat kg 1.0 20,000 20,000
3 11/5/2018 semen holcim sak 1.0 45,000 45,000
4 11/6/2018 semen holcim sak 2.0 45,000 90,000 1
5 11/6/2018 kalsium sak 1
6 11/6/2018 NYA 1 X 2,5 KUNING 100M ROLL 1.0 294,000 294,000
7 11/6/2018 NYA 1 X 2,5 BIRU 100M ROLL 1.0 294,000 294,000
8 11/6/2018 NYA 1 X 2,5 MERAH 100M ROLL 1.0 294,000 294,000
9 11/6/2018 embodus BIJI 11.0 2,600 28,600 10
10 11/6/2018 BOX MCB BIJI 1.0 19,000 19,000 1
11 11/6/2018 PIPA 5/8 BIJI 7.0 6,000 42,000 7
12 11/7/2018 semen hocim sak 1
13 11/8/2018 NYY 3 X4 MM METER 10.5 24,000 252,000
14 11/8/2018 NYM 3 X 2,5 METER 13.5 9,200 124,200
15 11/8/2018 ARDE 11 MM BIJI 1.0 11,500 11,500
16 11/8/2018 ISOLASI NATIONAL BIJI 1.0 4,500 4,500
17 11/8/2018 NYM 2 X 2,5 METER 31.0 6,840 212,040
18 11/8/2018 BATA MERAH BIJI 1,000.0 450 450,000
19 11/9/2018 lem pvc klg 1

TOTAL (Periode 10 : 03-09 Nov) 2,210,840


Jumlah Update -per 10 Nov 2018 42,014,101

1 11/12/2018 kalsium biji 2.0 30,000 60,000 2


2 11/12/2018 semen holcim sak 2.0 45,000 90,000 2
3 11/13/2018 besi 8 biji 2.0 48,500 97,000 2
4 11/13/2018 gypsum knouf biji 9.0 58,000 522,000
5 14/11/2018 hollow 4 x4 biji 15.0 32,500 487,500
6 14/11/2018 driwall 6 x 1 biji 1,000.0 80 80,000
7 14/11/2018 wall angel lipat biji 12.0 8,500 102,000
8 14/11/2018 hollow 2 x 4 biji 25.0 24,000 600,000
9 14/11/2018 paku 5 kg 1.0 16,500 16,500
10 15/11/2018 gypsum knouf biji 6.0 58,000 348,000
11 15/11/2018 wall angel lipat biji 10.0 8,500 85,000
12 15/11/2018 Compound A plus sak 1.0 65,000 65,000
13 15/11/2018 perban gypsum biji 2.0 10,000 20,000
14 15/11/2018 lem rajawali biji 5.0 12,750 63,750
15 15/11/2018 cat sanlex gln - 1
16 16/11/2018 hollow 4 x 4 biji - 15
17 16/11/2018 driwall 6 x 1 biji - 1000
18 16/11/2018 perban gypsum biji - 2
19 16/11/2018 kompund A plus sak - 1
20 16/11/2018 wall angel lipat biji - 10
21 16/11/2018 wall angel lipat biji - 15
22 16/11/2018 hollow 2 x 4 biji - 30
23 16/11/2018 gypsum knouf biji - 10
24 16/11/2018 driwall 6 x 2 biji - 200
25 16/11/2018 semen holcim sak 2.0 45,000 90,000
26 16/11/2018 kalsium dsgm sak 1.0 47,000 47,000
27 17/11/2018 semen holcim sak 2.0 45,000 90,000

TOTAL (Periode 11 : 12-17 Nov) 2,863,750


Jumlah Update -per 17 Nov 2018 44,877,851

1 19/11/2018 tee 3/4 biji 2.0 3,000 6,000 2


2 19/11/2018 keni 3/4 biji 1.0 3,500 3,500
3 19/11/2018 pvc 3/4 biji 3.0 33,000 99,000
4 19/11/2018 shock 3/4 biji 2.0 3,500 7,000
5 20/11/2018 arde 11mm biji - 1
6 20/11/2018 nyy 3 x 4 meter - 9.5
7 21/11/2018 keni 3/4 biji - 3
8 21/11/2018 t 3/4 biji - 2
9 21/11/2018 pvc 3/4 biji - 3
10 21/11/2018 cat plafon paragon gln 1.0 100,000 100,000
11 21/11/2018 shock 3/4 biasa biji - 2
12 21/11/2018 amplas 8 biji - 4
13 21/11/2018 wall angel lipat biji - 5
14 21/11/2018 gypsumkonuf biji 4.0 58,000 232,000 4
15 21/11/2018 nya 1 x 2.5 kuning meter - 100
16 21/11/2018 nym daifu 2 x2.5 meter - 50
17 21/11/2018 paku 5 kg 0.5 16,500 8,250
18 22/11/2018 lem rajawali biji 5.0 12,750 63,750
19 22/11/2018 kalsium dsgm biji 2.0 47,000 94,000
20 22/11/2018 gypsum knouf biji - 4
21 23/11/2018 semen holcim sak 2.0 45,000 90,000
22 23/11/2018 lem rajawali biji - 2
23 23/11/2018 kalsium dsgm sak - 1
24 24/11/2018 semen holcim sak 4.0 45,000 180,000
25 24/11/2018 pasir rit 1.0 350,000 350,000
26 24/11/2018 lem rajawali biji 4.0 12,750 51,000
27 24/11/2018 kalsium dsgm sak 1.0 47,000 47,000

TOTAL (Periode 12 : 19-24 Nov) 1,331,500


Jumlah Update -per 24 Nov 2018 46,209,351

1 11/26/2018 kalsium dsgm SAK 3


2 11/26/2018 lem rajawali biji 12
3 11/27/2018 kalsium SAK 2
4 11/27/2018 pasir engkel RIT 1
5 11/29/2018 semen holcim sak 2.0 45,000 90,000
6 11/29/2018 semen putih sak 1.0 86,000 86,000
7 11/29/2018 semen holcim SAK 6
8 11/29/2018 semen putih sak 1
9 11/30/2018 wall angel lipat BIJI 2
10 11/30/2018 driwall 6 x 1 PROFIT BIJI 100
11 11/30/2018 isolasi national BIJI 1
12 11/30/2018 kalsium dsgm sak 3.0 47,000 141,000
13 11/30/2018 lem rajawali biji 19.0 12,750 242,250
14 12/1/2018 MCB sneider BIJI 2
15 12/1/2018 MCB sneider BIJI 2.0 43,500 87,000
16 12/4/2018 bata ringan 60 x 20 x 10 M3 1.5 630,000 945,000
17 12/7/2018 casting a plus sak 1.0 40,000 40,000
TOTAL (Periode 13 : 26-07 Des ) 1,631,250
Jumlah Update -per 07 Des 2018 47,840,601
makaian Material
Blok D.18 Blok C 19 Sisa
VOL Barang Keterangan
Harga Jumlah Harga Jumlah
Terpakai di Gudang
18,000 9,000
4,000 4,000 1.00 4,000 4,000
16,500 12,375
16,500 12,375
20,000 300,000 5.00 20,000 100,000
750,000 375,000
42,000 168,000
325,000 162,500
42,000 84,000
20,000 60,000

325,000 325,000

70,076 939,015
46,000 1,012,000
42,000 84,000
350,000 175,000
18,000 45,000

6,500 130,000

Rp. 462,500/dus
42,000 210,000

46,000 460,000

42,000 42,000

Rp. 340,000/dus

46,000 552,000

42,000 210,000
230,000 230,000
60,000 420,000
325,000 162,500
580,000 2,900,000

350,000 175,000
70,076 437,973

46,000 552,000

46,000 368,000

70,076 437,973

18,000 54,000

11,108,712 104,000

230,000 460,000

20,000 20,000
60,000 120,000

600,000

48,500 48,500 Semen Gresik


16,500 24,750
230,000 230,000
60,000 120,000
6,500 130,000
60,000 60,000

18,000 18,000
46,000 92,000
48,500 48,500
580,000 6,264,000

20,000 120,000
48,500 48,500 Semen Gresik

6,500 65,000
46,000 276,000

6,500 39,000
20,000 80,000
96,000 96,000
43,000 43,000

43,000 86,000

16,500 16,500
96,000 192,000
46,000 230,000

8,327,750

43,000 43,000

46,000 230,000

16,500 16,500
43,000 86,000

43,000 129,000

60,000 120,000

325,000 325,000

350,000 175,000
18,000 18,000
46,000 690,000
20,000 120,000

6,500 65,000
70,076 875,947
43,000 43,000
2,936,447

43,000 86,000

46,000 184,000
18,000 18,000

16,500 16,500

43,000 86,000
6,500 65,000
43,000 86,000

46,000 276,000

43,000 86,000
60,000 60,000
18,000 18,000
43,000 129,000

1,110,500

325,000 325,000
42,000 168,000 Semen Merah putih
42,000 84,000 Semen Merah putih

42,000 168,000
46,000 92,000
45,000 90,000 Naik Rp. 2,000/zak
45,000 90,000
4,000 2,000,000
5,500 55,000
6,500 325,000
82,000 1,722,000
135 67,500
35,000 17,500
1,500 30,000
35,000 630,000
135 67,500
45,000 90,000

6,021,500

82,000 410,000
35,000 420,000
60,000 60,000
20,000 80,000
80 8,000
8,500 42,500
50,000 200,000
80 20,000
41,000 155,800
135 67,500
82,000 82,000

35,000 682,500
82,000 246,000
45,000 135,000
325,000 325,000
82,000 287,000
35,000 350,000
135 33,750
8,500 42,500
50,000 150,000
50,000 50,000
28,000 100,800
80,000 240,000
50,000 100,000

4,288,350

60,000 60,000
48,000 192,000
17,000 42,500
20,000 20,000
45,000 90,000
45,000 135,000
60,000 60,000
48,000 192,000
17,000 42,500
475 475,000
45,000 135,000
48,000 48,000
17,000 34,000

4,000 400,000
325,000 650,000
45,000 90,000

2,666,000

4,000 100,000
45,000 45,000
7,000 7,000
12,500 12,500
147,000 147,000
105,000 105,000
45,000 135,000
105,000 420,000

45,000 45,000
7,000 7,000
45,000 90,000

1,113,500

45,000 45,000
30,000 30,000

2,600 26,000
19,000 19,000
6,000 42,000
45,000 45,000
40,000 40,000

247,000
38,419,759

30,000 60,000
45,000 90,000
48,500 97,000
-
-
-
-
-
-
-
-
-
-
-
170,000 170,000
32,500 487,500
80 80,000
10,000 20,000
65,000 65,000
8,500 85,000
8,500 127,500
24,000 720,000
58,000 580,000
125 25,000

2,607,000
41,026,759

3,000 6,000
-
-
-
11,500 11,500
24,000 228,000
2,000 6,000
4,000 8,000
33,000 99,000
-
3,000 6,000
4,000 16,000
8,500 42,500
58,000 232,000
2,940 294,000
6,840 342,000
-
-
-
58,000 232,000
-
12,750 25,500
47,000 47,000

1,595,500
42,622,259

94,000 282,000
35,063 420,750
90,000 180,000
350,000 350,000

157,500 945,000
86,000 86,000
140,250 280,500
110 11,000
4,500 4,500

43,500 87,000
2,646,750
45,269,009
1,600,000
15,699,161
6,069,528
#REF!
Pemakaian Material
Blok C13 Sisa
No Tanggal Jenis Material Sat VOL Barang
Harga Jumlah
Terpakai di Gudang
1 11/1/2018 kaso usuk biji 10 20,000 200,000
2 11/1/2018 benang nylon ikat 2 4,000 8,000
3 11/1/2018 paku 7" kg 1 16,500 16,500

TOTAL (Periode : s/d 02 Nov) 224,500

4 11/5/2018 pasir (engkel) rit 2 230,000 460,000


5 11/6/2018 paku 5 kg 1 16,500 16,500
5 11/6/2018 batu gebal engkel) rit 2 294,000 588,000
6 11/6/2018 benang nilon ikat 1 19,000 19,000
7 11/7/2018 BESI 8 biji 25 294,000 7,350,000
8 11/7/2018 batu gebal engkel) rit 1 294,000 294,000
9 11/7/2018 kawat bendrat kg 2 294,000 588,000
10 11/7/2018 semen holcim sak 6 48,500 291,000
11 11/8/2018 pasir (engkel) RIT 2 350,000 700,000
12 11/8/2018 batu gebal engkel) RIT 1 500,000 500,000
13 11/9/2018 begel 8 x 10 (20kg) kg 20 340,000 6,800,000
14 11/9/2018 batu koral engkel rit 1 350,000 350,000
15 11/9/2018 keni 3 biji 3 7,000 21,000
16 11/9/2018 t3 biji 1 8,000 8,000
17 11/9/2018 keni 4 " biji 2 12,500 25,000
18 11/9/2018 pvc 4 wafin biji 2 147,000 294,000
19 11/10/2018 besi 8 biji 25 48,500 1,212,500
20 11/10/2018 paku 5 kg 1 16,500 16,500
21 11/10/2018 t3 bji 1 8,000 8,000

TOTAL (Periode : 05-10 Nov) 19,541,500


Jumlah Update -per 10 Nov 2018 19,766,000

1 11/12/2018 semen holcim sak 10 45,000 450,000


2 11/12/2018 pvc 3 wafin biji 6 105,000 630,000
3 11/13/2018 mortar biji 10 60,000 600,000
4 11/13/2018 besi 8 biji 12 48,500 582,000
5 11/13/2018 bata ringan m3 8.5 640,000 5,440,000
6 14/11/2018 keni 3/4 biji 3 2,000 6,000
7 14/11/2018 pvc 3/4 biji 3 30,000 90,000
8 15/11/2018 tanah urug rit 2 230,000 460,000
9 17/11/2018 paku 5 kg 1 16,500 16,500

TOTAL (Periode 10 : 12-17 Nov) 8,274,500


Jumlah Update -per 17 Nov 2018 28,040,500
1 20/11/2018 semen holcim sak 2 45,000 90,000
2 20/11/2018 papan cor biji 10 6,500 65,000
3 21/11/2018 besi 8 biji 9 48,500 436,500
4 21/11/2018 begel 8 x 15 biji 2 17,000 34,000
5 21/11/2018 paku 5 kg 1 16,500 16,500
6 22/11/2018 papan cor biji 5 6,500 32,500
7 23/11/2018 papan cor biji 10 6,500 65,000
8 23/11/2018 paku 5 kg 1.5 16,500 24,750
9 23/11/2018 kawat bendrat kg 1 20,000 20,000
10 24/11/2018 tanah urug rit 1 230,000 230,000
11 24/11/2018 triplex biji 6 97,500 585,000
12 24/11/2018 semen holcim sak 10 45,000 450,000
13 24/11/2018 pasir rit 1 350,000 350,000
14 24/11/2018 nym 2 x 2.5 meter 9 6,840 61,560
15 24/11/2018 kawat bendrat kg 1 20,000 20,000
16 24/11/2018 paku 7 kg 1 16,500 16,500
17 24/11/2018 paku 5 kg 1 16,500 16,500
18 11/27/2018 begel 8 x 12 KG 10 17,000 170,000
19 11/27/2018 besi 8 new BIJI 47 48,500 2,279,500
20 11/28/2018 bambu BIJI 5 20,000 100,000
21 11/28/2018 kawat bendrat KG 5 20,000 100,000
22 11/28/2018 paku 5 - B KG 0 16,000 -
23 11/28/2018 papan cor BIJI 55 6,500 357,500
24 11/28/2018 kaso usuk 3m biji 10 15,000 150,000
25 11/29/2018 batu koral (l 300) RIT 1 350,000 350,000
26 11/29/2018 begel 8 x 10 KG 5 17,000 85,000
27 11/29/2018 semen holcim SAK 25 45,000 1,125,000
28 11/30/2018 triplek (9MM) LBR 4 97,500 390,000
29 12/1/2018 Buis beton A BIJI 3 80,000 240,000
30 12/1/2018 Buis beton B biji 3 75,000 225,000
31 12/1/2018 tutup bis beton biji 2 60,000 120,000
32 12/1/2018 tutup bis beton BIJI 2 50,000 100,000
33 12/3/2018 kaso usuk BIJI 14 20,000 280,000
34 12/3/2018 mortar SAK 3 60,000 180,000
35 12/4/2018 bata merah BIJI 1000 450 450,000
36 12/4/2018 paku 5 - A kg 3 16,500 49,500

TOTAL (Periode 10 : 19 Nov-04 Des) 9,265,310


Jumlah Update -per 07 Des 2018 37,305,810
Keterangan
Pemakaian Material
Blok C1 Sisa
No Tanggal Jenis Material Sat VOL Barang
Harga Jumlah
Terpakai di Gudang
1 10/19/2018 kaso usuk biji 12 20,000 240,000
2 10/19/2018 paku 7 kg 1 16,500 16,500
3 10/20/2018 paku 5 kg 0.5 16,500 8,250
4 10/20/2018 paku 7 kg 0.5 16,500 8,250
5 10/20/2018 benang nylon (kenur) ikat 1 4,000 4,000
6 10/22/2018 bata ringan rit 10.8 630,000 6,804,000
7 10/23/2018 begel 8 x 12 kg 20 17,000 340,000
8 10/24/2018 mortar sak 10 60,000 600,000
9 10/24/2018 begel 8 x 10 kg 20 17,000 340,000
10 10/24/2018 kawat bendart kg 5 20,000 100,000
11 10/24/2018 besi 8 biji 50 48,000 2,400,000
12 10/24/2018 pasir rit 3 350,000 1,050,000
13 10/24/2018 batu gebal (engkel) rit 3 750,000 2,250,000
14 10/25/2018 semen holcim sak 5 45,000 225,000
15 10/25/2018 besi 8 '' biji 20 48,000 960,000
16 10/25/2018 begel 8 x 10 kg 17.5 17,000 297,500
17 10/25/2018 batu gebal (engkel) rit 2 750,000 1,500,000
18 10/25/2018 pasir rit 1 350,000 350,000
19 10/26/2018 pvc 4 '' wafin biji 2 147,000 294,000
20 10/26/2018 batu gebal (engkel) rit 1 750,000 750,000
21 10/26/2018 batu koral (l300) rit 1 350,000 350,000
22 10/27/2018 pcv 3/4 biji 1 31,000 31,000
23 10/27/2018 begel 8 x 12 kg 4 17,000 68,000
24 10/27/2018 lem pvc biji 1 40,000 40,000

TOTAL (Periode : 19-28 okt) 19,026,500

1 10/29/2018 pasir rit 2 350,000 700,000


2 10/29/2018 papan cor biji 50 6,500 325,000
3 10/29/2018 kawat bendrat kg 1 20,000 20,000
4 10/29/2018 semen sak 6 45,000 270,000
5 10/29/2018 paku 5" kg 2 16,500 33,000
6 10/31/2018 tanah urug rit 2 230,000 460,000
7 10/31/2018 pvc 3 biji 6 105,000 630,000
8 10/31/2018 paku 8" kg 1 16,500 16,500
9 10/31/2018 keni 3 biji 2 7,000 14,000
10 10/31/2018 keni 4 biji 2 12,500 25,000
11 10/31/2018 pvc 4 biji 3 147,000 441,000
12 11/1/2018 tanah urug rit 1 230,000 230,000
13 11/1/2018 semen holcim sak 5 45,000 225,000
14 11/1/2018 paku dudur kg 2 16,500 33,000
15 11/1/2018 paku 5" kg 1 16,500 16,500

TOTAL (Periode : 29 okt-02 nov) 3,439,000

1 11/3/2018 kawat bendrat kg 1 20,000 20,000


2 11/5/2018 paku 7 kg 2 16,500 33,000
3 11/5/2018 triplek biji 2 500,000 1,000,000
4 11/5/2018 kawat bendrat kg 1 20,000 20,000
5 11/5/2018 paku 5 kg 2.5 16,500 41,250
6 11/5/2018 BESI 8 biji 12 630,000 7,560,000
7 11/5/2018 kabel nym 2 x 2,5 meter 7 340,000 2,380,000
8 11/6/2018 BESI 8 BIJI 8 630,000 5,040,000
9 11/6/2018 NYM 2X 2,5 METER 4 340,000 1,360,000
10 11/6/2018 paku 5 kg 2 16,500 33,000
11 11/7/2018 triplek tebal 6mm biji 1 500,000 500,000
12 11/7/2018 bata ringan m3 10.8 17,000 183,600
13 11/7/2018 semen hocim sak 5 45,000 225,000
14 11/7/2018 kaso usuk biji 3 20,000 60,000
15 11/7/2018 begel 8 x 10 (20kg) kg 20 17,000 340,000
16 11/8/2018 pasir (engkel) RIT 2 350,000 700,000
17 11/9/2018 triplek biji 2 97,500 195,000
18 11/9/2018 kaso usuk biji 20 22,000 440,000
19 11/9/2018 nym 2 x 2,5 meter 8 6,840 54,720
20 11/10/2018 triplex biji 1 97,500 97,500

TOTAL (Periode : 03-10 Nov) 20,283,070


Jumlah Update -per 10 Nov 2018 42,748,570

1 11/12/2018 keni 3/4 biji 8 3,500 28,000


2 11/12/2018 semen holcim sak 5 45,000 225,000
3 11/12/2018 pvc 3/4 maspion biji 8 33,000 264,000
4 11/12/2018 tee 4 biji 1 15,000 15,000
5 11/12/2018 keni 4 biji 1 12,500 12,500
6 11/12/2018 t 3/4 rucika biji 6 4,000 24,000
7 11/13/2018 PVC 1 1/2 WAFIN BIJI 1 42,500 42,500
8 11/13/2018 KENI 1 1/2 BIJI 3 3,000 9,000
9 11/13/2018 keni 3" biji 1 7,000 7,000
10 11/13/2018 besi 8 biji 6 48,500 291,000
11 11/13/2018 besi 8 biji 4 48,500 194,000
12 13/11/2018 paku 7 kg 1 16,500 16,500
13 14/11/2018 keni 3/4 biji 3 2,000 6,000
14 14/11/2018 papan cor biji 10 6,500 65,000
15 14/11/2018 triplek biji 1 97,500 97,500
16 14/11/2018 kaso usuk biji 20 20,000 400,000
17 15/11/2018 kawat bendrat kg 2 20,000 40,000
18 15/11/2018 triplek biji 5 97,500 487,500
19 15/11/2018 paku 7 kg 1 16,500 16,500
20 15/11/2018 papan cor biji 20 6,500 130,000
21 16/11/2018 besi 8 biji 10 48,500 485,000
22 16/11/2018 papan cor bii 10 6,500 65,000
23 16/11/2018 paku 7 kg 1 16,500 16,500
24 16/11/2018 paku 5 kg 2 16,500 33,000
25 16/11/2018 semen holcim sak 10 45,000 450,000
26 17/11/2018 papan cor biji 10 6,500 65,000

TOTAL (Periode 10 : 12-17 Nov) 3,485,500


Jumlah Update -per 17 Nov 2018 46,234,070

1 19/11/2018 papan cor biji 20 6,500 130,000


2 19/11/2018 kawat bendrat kg 1 20,000 20,000
3 19/11/2018 triplek biji 1 97,500 97,500
4 19/11/2018 besi 8 biji 20 48,500 970,000
5 20/11/2018 paku 5 kg 2 16,500 33,000
6 20/11/2018 paku 7 kg 1 16,500 16,500
7 20/11/2018 semen holcim sak 10 45,000 450,000
8 20/11/2018 kaso usuk biji 6 20,000 120,000
9 21/11/2018 papan cor biji 5 6,500 32,500
10 22/11/2018 paku 7 kg 1 16,500 16,500
11 22/11/2018 papan cor biji 20 6,500 130,000
12 22/11/2018 kawat bendrat kg 1 20,000 20,000
13 22/11/2018 bata merah biji 500 450 225,000
14 22/11/2018 bambu biji 10 20,000 200,000
15 23/11/2018 semen holcim sak 5 45,000 225,000
16 23/11/2018 paku 7 kg 1 16,500 16,500
17 23/11/2018 besi 8 biji 15 48,500 727,500
18 23/11/2018 bambu biji 6 20,000 120,000
19 24/11/2018 paku 5 kg 1 16,500 16,500
20 11/30/2018 bambu BIJI 5 20,000 100,000
21 11/29/2018 drilling sds 8x13 BIJI 3000 135 405,000
22 12/7/2018 driwall 6 x 1 BIJI 1000 80 80,000
23 11/27/2018 dynabolt BIJI 20 1,500 30,000
24 11/27/2018 kanal 0,75 BIJI 5 82,000 410,000
25 11/27/2018 kanal 0,75 biji 50 81,000 4,050,000
26 12/7/2018 kasiplank 20cm BIJI 10 50,000 500,000
27 11/26/2018 mortar SAK 10 60,000 600,000
28 12/3/2018 paku 7 KG 1 16,500 16,500
29 11/30/2018 papan cor BIJI 26 6,500 169,000
30 11/26/2018 pasir engkel RIT 2 350,000 700,000
31 11/27/2018 reng 0,45 BIJI 111 35,000 3,885,000
32 11/26/2018 semen holcim SAK 26 45,000 1,170,000
33 12/7/2018 wall angel lipat BIJI 20 8,500 170,000
34 11/28/2018 paku 7 beton dus 2 20,000 40,000
35 12/1/2018 bis beton biji 3 75,000 225,000
36 12/1/2018 tutup bis beton biji 2 50,000 100,000

TOTAL (Periode 10 : 19 Nov-31 Des) 16,217,000


Jumlah Update -per 07 Des 2018 62,451,070
Keterangan
Pemakaian Material
Blok C21 Sisa
No Tanggal Jenis Material Sat VOL Barang
Harga Jumlah
Terpakai di Gudang
1 10/20/2018 kaso usuk 4/6 biji 10 20,000 200,000
2 10/23/2018 benang nylon ikat 2 4,000 8,000
3 10/23/2018 batu gebal (dump) rit 1 750,000 750,000
4 10/24/2018 besi 8 '' biji 10 48,000 480,000
5 10/25/2018 besi 8 '' biji 10 48,000 480,000
6 10/25/2018 batu koral ( L 300 ) rit 1 350,000 350,000
7 10/26/2018 kawat bendrat kg 1 20,000 20,000
8 10/26/2018 semen holcim sak 2 45,000 90,000
9 10/26/2018 pasir rit 2 350,000 700,000
10 10/27/2018 bata ringan 60x20x10 m3 8 630,000 5,040,000
11 10/27/2018 batu gebal m3 2 500,000 1,000,000
12 10/29/2018 besi 10" biji 6 75,000 450,000
13 10/29/2018 papan cor biji 30 6,500 195,000
14 10/29/2018 begel 8 x 25 kg 30 -
15 10/29/2018 kawat bendrat kg 4 20,000 80,000
16 10/29/2018 besi 10 " biji 36 75,000 2,700,000
17 10/30/2018 besi 8 " biji 25 48,000 1,200,000
18 10/30/2018 besi 10" biji 2 75,000 150,000
19 10/30/2018 besi 8 " biji 13 48,000 624,000
20 10/30/2018 begel 8 x 12 kg 36 -
21 10/31/2018 semen sak 12 45,000 540,000
22 10/31/2018 begel 8 x10 kg 18 -
23 10/31/2018 kawat bendrat kg 2 20,000 40,000
24 11/1/2018 benang nylon ikat 1 4,000 4,000
25 11/1/2018 semen holcim sak 5 45,000 225,000
26 11/2/2018 semen sak 5 45,000 225,000
27 11/2/2018 pasir rit 3 350,000 1,050,000

TOTAL (Periode : 19 okt-02 nov) 16,601,000

1 11/3/2018 paku 7" kg 3 4,000 10,000


2 11/3/2018 besi 8 " biji 5 630,000 3,150,000
3 11/3/2018 kawat bendrat kg 2 20,000 40,000
4 11/5/2018 kawat bendrat kg 1 20,000 20,000
5 11/5/2018 paku 5 kg 2 4,000 8,000
6 11/5/2018 semen holcim sak 5 45,000 225,000
7 11/5/2018 tanah urug dump rit 1 48,500 48,500
8 11/5/2018 papan cor biji 50 6,840 342,000
9 11/6/2018 semen holcim sak 2 45,000 90,000
10 11/6/2018 pvc 2,5 wafin biji 3 16,500 49,500
11 11/6/2018 pvc 3/4 maspion biji 2 48,500 97,000
12 11/6/2018 keni 3/4 rucika biji 2 97,500 195,000
13 11/6/2018 keni 2,5 '' biji 3 17,000 51,000
14 11/7/2018 paku 5 kg 2 4,000 8,000
15 11/7/2018 begel 8x12 kg 20 20,000 400,000
16 11/7/2018 mortar sak 10 45,000 450,000
17 11/7/2018 kawat bendrat kg 2 9,200 18,400
18 11/8/2018 bata ringan M3 11 630,000 6,804,000
19 11/8/2018 MORTAR SAK 10 60,000 600,000
20 11/9/2018 triplek biji 1 97,500 97,500
21 11/9/2018 besi 8 biji 10 48,500 485,000
22 11/9/2018 pasir (engkel) rit 2 350,000 700,000
23 11/10/2018 keni 3/4 rucika biji 10 3,500 35,000
24 11/10/2018 paku 5 kg 2 16,500 33,000
25 11/10/2018 pvc 2,5 wafin biji 8 80,000 640,000
26 11/10/2018 pvc 3/4 maspion biji 8 33,000 264,000
27 11/10/2018 pvc 4 wafin biji 2 147,000 294,000
28 11/10/2018 keni 4 biji 1 12,500 12,500
29 11/10/2018 keni 2,5 '' biji 7 5,000 35,000
30 11/10/2018 t 3/4 biji 3 3,500 10,500
31 11/10/2018 shock 3/4rucika biji 6 3,500 21,000

TOTAL (Periode : 03 nov-10 nov) 15,233,900


Jumlah Update -per 10 Nov 2018 31,834,900

1 11/12/2018 papan cor biji 10 6,500 65,000


2 11/12/2018 besi 8 biji 12 48,500 582,000
3 11/12/2018 paku 5 kg 2 16,500 33,000
4 11/12/2018 begel 8 x 10 kg 20 17,000 340,000
5 11/12/2018 pvc 2,5 " biji 1 80,000 80,000
6 11/13/2018 besi 8 biji 10 48,500 485,000
7 14/11/2018 pvc 5/8 biji 1 6,000 6,000
8 14/11/2018 besi 8 biji 14 48,500 679,000
9 14/11/2018 begel 8 x 25 biji 10 13,000 130,000
10 14/11/2018 paku 7 kg 2 16,500 33,000
11 14/11/2018 triplek biji 1 97,500 97,500
12 14/11/2018 paku 5 kg 2 16,500 33,000
13 14/11/2018 semen holcim sak 5 45,000 225,000
14 14/11/2018 besi beton 10 biji 8 70,000 560,000
15 15/11/2018 kaso usuk biji 10 20,000 200,000
16 15/11/2018 kawat bendrat kg 5 20,000 100,000
17 15/11/2018 begel 8 x 25 kg 15 17,000 255,000
18 15/11/2018 besi 8 biji 6 48,500 291,000
19 15/11/2018 papan cor biji 10 6,500 65,000
20 16/11/2018 besi 8 biji 10 48,500 485,000
21 16/11/2018 semen holcim sak 6 45,000 270,000
22 16/11/2018 besi beton 10 biji 12 70,000 840,000
23 17/11/2018 kasoo usuk biji 21 20,000 420,000
24 17/11/2018 pasir engkel rit 2 350,000 700,000
25 17/11/2018 paku 5 kg 2 16,500 33,000
26 17/11/2018 paku kg 2 16,500 33,000
27 17/11/2018 triplek biji 1 97,500 97,500
28 17/11/2018 papan cor biji 20 6,500 130,000
29 17/11/2018 besi 8 biji 1 48,500 48,500

TOTAL (Periode 10 : 12-17 Nov) 7,316,500


Jumlah Update -per 17 Nov 2018 39,151,400

1 11/19/2018 paku 7 kg 1 16,500 16,500


2 19/11/2018 kawat bendrat kg 1 20,000 20,000
3 19/11/2018 nym 2 x 2.5 meter 41 6,840 280,440
4 19/11/2018 paku 7 kg 1 16,500 16,500
5 21/11/2018 kawat bendrat biji 2 20,000 40,000
6 21/11/2018 besi8 biji 10 48,500 485,000
7 22/11/2018 paku 7 kg 2 16,500 33,000
8 22/11/2018 papan cor biji 10 6,500 65,000
9 22/11/2018 bata merah biji 500 450 225,000
10 23/11/2018 semen holcim sak 10 45,000 450,000
11 23/11/2018 reng kayu biji 50 3,400 170,000
12 23/11/2018 papan cor biji 20 6,500 130,000
13 23/11/2018 paku 7 kg 1 16,500 16,500
14 23/11/2018 kaso usuk biji 20 20,000 400,000
15 23/11/2018 bambu biji 10 20,000 200,000
16 24/11/2018 tanah urug rit 1 230,000 230,000
17 24/11/2018 t 2.5 biji 1 7,000 7,000
18 24/11/2018 pvc 3/4 biji 1 33,000 33,000
19 24/11/2018 pvc 2.5 biji 3 80,000 240,000
20 24/11/2018 paku reng pring kg 1 16,500 16,500
21 24/11/2018 paku 7 kg 2 16,500 33,000
22 24/11/2018 keni 3/4 r biji 6 3,500 21,000
23 24/11/2018 kaso usuk biji 10 20,000 200,000
24 24/11/2018 bambu biji 20 20,000 400,000
25 24/11/2018 keni 2.5 biji 9 5,000 45,000

TOTAL (Periode 10 : 19-24 Nov) 3,773,440


Jumlah Update -per 24 Nov 2018 42,924,840

1 24/11/2018 bambu BIJI 25 20,000 500,000


2 11/26/2018 kaso usuk BIJI 24 20,000 480,000
3 11/26/2018 kawat bendrat KG 17 20,000 340,000
4 11/26/2018 paku 7 KG 2 16,000 32,000
5 11/26/2018 paku reng pring kg 4 16,500 66,000
6 11/27/2018 triplek (9MM) LBR 13 97,500 1,267,500
7 11/28/2018 paku 8 KG 3 16,500 49,500
8 11/28/2018 papan cor BIJI 30 6,500 195,000
9 11/28/2018 reng kayu biji 50 3,400 170,000
10 11/28/2018 kaso usuk 3m biji 20 15,000 300,000
11 11/29/2018 batu koral (l 300) RIT 2 350,000 700,000
12 11/29/2018 begel 8 x 10 KG 25 17,000 425,000
13 11/29/2018 benang NILON / kenur IKAT 4 4,000 16,000
14 11/29/2018 abu batu engkel rit 4 350,000 1,400,000
15 11/30/2018 begel 8 x 25 kg 3 17,000 51,000
16 11/30/2018 besi 8 new BIJI 125 48,500 6,062,500
17 11/30/2018 besi 6 biji 5 28,000 140,000
18 11/30/2018 besi 12 biji 8 105,000 840,000
19 12/1/2018 bis beton biji 3 75,000 225,000
20 12/3/2018 tutup bis beton biji 2 50,000 100,000
21 12/3/2018 Blandar glugu biji 12 70,000 840,000
22 12/3/2018 NYM 3 x 25 mm METER 25 9,200 230,000
23 12/3/2018 NYM daifu 2 x 2,5 METER 30 6,900 207,000
24 12/4/2018 semen holcim SAK 46 45,000 2,070,000
25 12/6/2018 paku 7 kg 11 16,500 181,500
26 12/7/2018 begel 8 x 12 KG 8 17,000 136,000
27 12/7/2018 paku 5 KG 2 16,500 33,000

TOTAL (Periode 10 : 19-24 Nov) 17,057,000


Jumlah Update -per 07 Des 2018 60,381,840