Anda di halaman 1dari 61

DAFTAR KESEPAKATAN HARGA SATUAN BAHAN / MATERIAL DAN UPAH SEMESTER 2

DINAS BINA MARGA, DINAS PENGELOLAAN SUMBER DAYA AIR & PERTAMBANGAN
DAN DINAS CIPTA KARYA & TATA RUANG
KABUPATEN CIREBON
TAHUN ANGGARAN 2014

NO URAIAN BAHAN/MATERIAL SAT. HARGA KET


KESEPAKATAN
A. BAHAN :
I. BATU
1 Abu Batu m3 172,500.00
2 Atras ( tanah urug ) m3 125,000.00
3 Base course A m3 175,000.00
4 Base course B m3 165,800.00
5 Batu apung kg 4,300.00
6 Batu belah 10/15 cm m3 135,000.00
7 Batu belah 15/20 cm m3 135,000.00
8 Batu pecah mesin 0.5-1 cm m3 180,000.00
9 Batu pecah mesin 1-2 cm m3 180,000.00
10 Batu pecah mesin 2-3 cm m3 180,000.00
11 Batu tempel Palimanan 10 X 20 bh 1,500.00
12 Batu tempel kapur tekstur tidak rata bh 2,000.00
13 Kapur bakar m3 70,000.00
14 Kapur Sirih kg 2,000.00
15 Kerikil m3 65,000.00

II. PASIR
1 Pasir beton m3 150,000.00
2 Pasir aspal m3 150,000.00
3 Pasir pasang m3 143,000.00
4 Pasir urug m3 110,000.00
5 Sirtu m3 110,000.00
6 Sirtu tersaring m3 115,000.00
7 Tanah urug pilhan m3 125,000.00
8 Tanah urug biasa m3 100,000.00
III. BESI / PIPA / KAWAT
1 Besi WF/Besi Profil kg 11,250.00
2 Besi strip kg 11,250.00
3 Besi beton kg 11,000.00
4 Besi stainless dia. 0,5" m' 38,000.00
5 Besi stainless dia. 1" m' 60,000.00
6 Besi stainless dia. 1,5" m' 75,000.00
7 Besi stainless dia. 2" m' 80,000.00
8 Besi stainless dia. 2,5" m' 125,000.00
9 Besi stainless dia. 3" m' 152,000.00
10 Besi galvanis dia. 0.5" m' 25,000.00
11 Besi galvanis dia. 1" m' 27,000.00
12 Besi galvanis dia. 1.5" m' 45,000.00
13 Besi galvanis dia. 2" m' 57,000.00
14 Besi galvanis dia. 2.5" m' 80,500.00
15 Besi galvanis dia. 3" m' 96,000.00
16 Besi biasa dia. 2" btg 250,000.00
17 Besi biasa dia. 3" btg 310,000.00
18 Dop besi Ø 3 " bh 60,000.00
19 Kawat beton / Kawat tali kg 18,000.00
20 Kawat bronjong dia. 4 mm kg 20,000.00
21 Kawat galvanis dia. 4 mm kg 20,000.00
22 Kawat galvanis dia. 6 mm kg 24,000.00
23 Kawat duri m' 20,000.00
24 Pipa besi galvanis 2" btg 324,000.00
25 Pipa besi galvanis 3" btg/6m' 600,000.00
26 Pipa PVC Ø 2" S-12,5 ( 8 - 10 bar ) m' 26,300.00
27 Pipa PVC Ø 3" S-12,5 ( 8 - 10 bar ) m' 53,600.00
28 Pipa PVC / paralon 2 inch btg 50,600.00
29 Pipa PVC / paralon 3 inch btg 75,000.00
30 Pipa Reducer PVC Ø 3"-4" bh 5,800.00
31 Pipa Knee/bend PVC Ø 3" bh 5,800.00
32 Plat baja tebal 5 mm - 20 mm kg 12,650.00
33 Ram kawat harmonika m2 23,200.00
34 Socket besi O 3 " bh 45,000.00
NO URAIAN BAHAN/MATERIAL SAT. HARGA KET
KESEPAKATAN

IV. PABRIKAN / TOKO


1 Alumunium foil m2 9,000.00
2 Alumunium pelapis pintu KM lbr 130,000.00
3 Asbes gelombang 1500 x 1050 x 4 mm lbr 35,000.00
4 Asbes gelombang 1800 x 920 x 4 mm lbr 42,500.00
5 Asbes gelombang 2100 x 1050 x 4 mm lbr 57,000.00
6 Asbes gelombang 2400 x 1050 x 4 mm lbr 65,000.00
7 Asbes gelombang 2700 x 1050 x 4 mm lbr 75,000.00
8 Asbes gelombang 3000 x 1050 x 4 mm lbr 85,000.00
9 Bak mandi keramik volume 0,3 m3 bh 185,000.00
10 Bak mandi fiber 120 L bh 220,000.00
11 Batu apung kg 4,300.00
12 Baut 3/4 " bh 3,000.00
13 Baut 5/8 " bh 3,800.00
14 Baut 1/2 " bh 6,000.00
15 Baut 1/2 " panjang 30 cm bh 8,550.00
16 Baut lawa-lawa bh 9,900.00
17 Beading penurunan ( PC ) gypsum m' 10,000.00
18 Beading horison gypsum m' 10,000.00
19 Cat Menie kg 20,000.00
20 Cat genteng kg 48,000.00
21 Cat penutup kayu kg 49,000.00
22 Cat penutup tembok kg 23,000.00
23 Cat penutup besi kg 45,000.00
24 Cat Sinkromat kg 80,000.00
25 Closet duduk ( mono block ) porselen merk INA bh 1,237,000.00
26 Closet duduk ( siram ) porselen merk INA bh 545,000.00
27 Closet jongkok porselen merk INA/KIA bh 140,000.00
28 Dempul kayu kg 18,000.00
29 Dinding keramik uk. 10 x 20 cm bh 950.00
30 Dinding keramik uk. 20 x 20 cm bh 1,850.00
31 Dinding keramik uk. 20 x 25 cm bh 2,200.00
32 Dinding keramik uk. 30 x 30 cm bh 3,300.00
33 Door closer bh 158,125.00
34 Daun pintu alumunium lengkap warna natural/coklat dop bh 900,000.00
35 Daun pintu alumunium lengkap warna coklat kilap bh 1,300,000.00
36 Daun jendela alumunium lengkap warna natural/coklat dop bh 350,000.00
37 Daun jendela alumunium lengkap warna coklat kilap bh 400,000.00
38 Elastomer 30x30x5 bh 550,000.00
39 Engsel jendela set 12,000.00
40 Engsel pintu set 15,000.00
41 Engsel meubeler bh 3,800.00
42 Eternit tebal 4 mm uk. 1 m x 1 m lbr 6,800.00
43 Eternit tebal 4 mm uk. 1 m x 0,5 m lbr 3,400.00
44 Flincote ltr 22,000.00
45 Glass beat kg 20,000.00
46 Glass Block bh 17,500.00
47 Gas elpiji kg 8,800.00
48 Grendel pintu / jendela bh 5,500.00
49 Gypsum board lbr 50,000.00
50 GRC tebal 4 mm lbr 53,000.00
51 Hampelas lbr 4,000.00
52 Kaca nako tebal 5 mm berikut teralis bh 11,400.00
53 Kaca polos tebal 3 mm m2 63,250.00
54 Kaca polos tebal 5 mm m2 75,000.00
55 Kait angin bh 9,500.00
56 Kunci gembok bh 17,000.00
57 Kunci pintu ukuran besar bh 125,000.00
58 Kunci pintu ukuran sedang bh 85,000.00
59 Kunci dan daun pintu dari fiber bh 350,000.00
60 Kusen Alumunium 3" warna natural m' 55,000.00
61 Kusen Alumunium 3" warna coklat dop m' 60,000.00
62 Kusen Alumunium 3" warna coklat kilap m' 75,000.00
63 Kusen Alumunium 4" warna natural m' 60,000.00
64 Kusen Alumunium 4" warna coklat dop m' 65,000.00
65 Kusen Alumunium 4" warna coklat kilap m' 85,000.00
66 Langko - langko kuda - kuda bh 18,000.00
67 Lantai granit 40 x 40 cm ex. Essenza bh 43,500.00
68 Lantai granit 40 x 40 cm ex. Granito bh 42,000.00
69 Lantai granit 60 x 60 cm ex. Granito bh 46,800.00
70 Lantai keramik uk. 10 x 20 cm bh 950.00
71 Lantai keramik uk. 20 x 20 cm bh 1,650.00
72 Lantai keramik uk. 30 x 30 cm bh 3,650.00
73 Lantai keramik uk. 40 x 40 cm ( putih polos ) bh 6,900.00
74 Lantai terakota 20 x 5 cm bh 4,400.00
NO URAIAN BAHAN/MATERIAL SAT. HARGA KET
KESEPAKATAN
75 Lem kayu ltr 30,000.00
76 Lemkra/zat addictive kg 15,000.00
77 Lemkra Just Do It kg 4,500.00
78 Lemkra FS Nat kg 15,850.00
79 List kayu B.3 ( lebar sisi 3 cm ) m' 4,400.00
80 List kayu B.4 ( lebar sisi 4 cm ) m' 4,800.00
81 List keliling gypsum lebar 7 cm m' 6,250.00
82 List keliling gypsum lebar 10 cm m' 7,250.00
83 List keliling gypsum lebar 12 cm m' 8,750.00
84 List drop m' 8,900.00
85 Melamin / folywood lbr 88,500.00
86 Mozaik uk. 20 x 20 cm bh 1,900.00
87 Multiplex tebal 15 mm m2 272,000.00
88 Paku biasa 1/2" - 1" kg 15,000.00
89 Paku biasa 2" - 5" kg 12,500.00
90 Paku pancing 60 x 230 bh 825.00
91 Paku sekrup 3" - 5 " bh 400.00
92 Paku ulir bh 150.00
93 Plamir kayu / kualitas 1 kg 17,500.00
94 Plamir tembok kg 25,000.00
95 Plester Mutiara kg 8,700.00
96 Polycarbonate m2 115,000.00
97 Plywood lbr 92,250.00
98 Portland Cement ( PC ) zak 61,000.00
99 Rubber joint 25x10x5 bh 175,000.00
100 Roster / batu kerawang bh 2,600.00
101 Semen portland kg 1,220.00
102 Semen warna kg 11,000.00
103 Seng BJLS 30 L. 90 cm m2 32,500.00
104 Seng gelombang 3' - 6 " BJLS 30 lbr 42,000.00
105 Sirlak kg 19,500.00
106 Spirtus ltr 11,000.00
107 Skim Coat kg 4,400.00
108 Taekwood 4 mm 1200 x 2400 mm lbr 90,000.00
109 Taekwood 4 mm 900 x 2400 mm lbr 75,000.00
110 Ter kayu kg 14,500.00
111 Thermoplastic Glass beat kg 23,000.00
112 Tiner / minyak cat ltr 9,200.00
113 Triplek 3 mm lbr 45,000.00
114 Triplek 4 mm lbr 55,000.00
115 Triplek 6 mm lbr 75,000.00
116 Triplek 9 mm lbr 95,000.00
117 Triplek 12 mm lbr 200,000.00
118 TG 302 kg 46,500.00
119 Ubin abu2 kepala basah 20 x 20 cm bh 2,000.00
120 Ubin abu2 kepala basah 30 x 30 cm bh 2,500.00
121 Ubin wafel ukuran 20 x 20 cm bh 2,000.00
122 Ubin warna 20 x 20 cm bh 2,300.00
123 Ubin warna 30 x 30 cm bh 2,900.00
124 Washtafel bh 686,000.00
125 Woodplank bh 59,500.00
126 Zincalume m2 70,000.00
127 Rangka plafon memakai Hollow dengan penutup GRC tebal 4 mm + pengecatan m2 88,200.00
128 Rangka atap baja ringan
a. Atap Baja Ringan memakai Genteng Keramik/Plentong ( jarak reng 22-28 cm)
- Atap Baja Ringan Pelana Bentang < 9 m Zinc-Alumunium G.550 m2 165,000.00
- Atap Baja Ringan Perisai Bentang < 9 m Zinc-Alumunium G.550 m2 175,000.00
- Atap Baja Ringan Joglo Bentang < 9 m Zinc-Alumunium G.550 m2 185,000.00
- Atap Baja Ringan Pelana Bentang 10-12 m Zinc-Alumunium G.550 m2 175,000.00
- Atap Baja Ringan Perisai Bentang 10-12 m Zinc-Alumunium G.550 m2 190,000.00
- Atap Baja Ringan Joglo Bentang 10-12 m Zinc-Alumunium G.550 m2 200,000.00
- Atap Baja Ringan Pelana Bentang > 12 m Zinc-Alumunium G.550 m2 190,000.00
- Atap Baja Ringan Perisai Bentang > 12 m Zinc-Alumunium G.550 m2 200,000.00
- Atap Baja Ringan Joglo Bentang > 12 m Zinc-Alumunium G.550 m2 210,000.00
b. Atap Baja Ringan Genteng Metal/Spandek ( jarak reng 37,5-90 cm)
- Atap Baja Ringan Pelana Bentang < 9 m Zinc-Alumunium G.550 m2 155,000.00
- Atap Baja Ringan Perisai Bentang < 9 m Zinc-Alumunium G.550 m2 162,500.00
- Atap Baja Ringan Joglo Bentang < 9 m Zinc-Alumunium G.550 m2 170,000.00
- Atap Baja Ringan Pelana Bentang 10-12 m Zinc-Alumunium G.550 m2 160,000.00
- Atap Baja Ringan Perisai Bentang 10-12 m Zinc-Alumunium G.550 m2 175,000.00
- Atap Baja Ringan Joglo Bentang 10-12 m Zinc-Alumunium G.550 m2 185,000.00
- Atap Baja Ringan Pelana Bentang > 12 m Zinc-Alumunium G.550 m2 170,000.00
- Atap Baja Ringan Perisai Bentang > 12 m Zinc-Alumunium G.550 m2 180,000.00
- Atap Baja Ringan Joglo Bentang > 12 m Zinc-Alumunium G.550 m2 190,000.00
NO URAIAN BAHAN/MATERIAL SAT. HARGA KET
KESEPAKATAN
129 Pintu Air Sorong
- Pintu Air Sorong Baja B = 0.40-0.60 ( 1 drat stang tanpa roda gigi ) Unit 8,497,000.00
- Pintu Air Sorong Baja B = 0.70-0.80 ( 1 drat stang tanpa roda gigi ) Unit 9,639,000.00
- Pintu Air Sorong Baja B = 0.90-1.00 ( 1 drat stang tanpa roda gigi ) Unit 13,500,000.00
- Pintu Air Sorong Baja B = 0.70-1.00 ( 1 drat stang + roda gigi ) Unit 11,414,000.00
- Pintu Air Sorong Baja B = 1.00-1.10 ( 2 drat stang + roda gigi ) Unit 25,366,000.00
- Pintu Air Sorong Baja B = 1.50-1.80 ( 2 drat stang + roda gigi ) Unit 38,049,000.00
- Pintu Air Sorong Baja B = 2.00-2.50 ( 2 drat stang + roda gigi ) Unit 50,732,000.00
130 Gigi Payung / Jantung Besar bh 1,250,000.00
131 Gigi Payung / Jantung Sedang bh 1,100,000.00
132 Gigi Piring Besar bh 2,930,000.00
133 Gigi Piring Sedang bh 1,903,000.00
134 Blok Laher bh 1,750,000.00
135 Bron mur drat 5 " bh 3,250,000.00
136 Bron mur drat 3 " bh 2,150,000.00
137 Drat stang 2" x 100 bh 2,500,000.00
138 Drat stang 3/4" x 100 bh 1,750,000.00
139 Drat stang 1,5" x 100 bh 1,550,000.00
140 Dudukan as horisontal bh 1,850,000.00
141 As Horisontal bh 1,850,000.00
142 Karet sel 8 x 3 cm bh 1,500,000.00
143 As Pemutar bh 750,000.00
144 Laher/Bearing bh 350,000.00
145 Engkel Kemudi Sedang bh 450,000.00
146 Daun Pintu B.50, H.50 bh 1,000,000.00
147 Pintu Klep B=0,5 m unit 1,750,000.00
148 Pintu Klep B=1,0 m unit 3,000,000.00
149 Pintu Klep B=1,5 m unit 4,500,000.00

V. ASPAL
1 Aspal kemasan kg 10,785.00
2 Aspal curah kg 9,930.00

VI. MINYAK
1 Premium liter 4,500.00
2 Premium (non subsidi) liter 9,950.00
3 Solar liter 4,500.00
4 Solar (non subsidi) liter 8,500.00
5 Minyak tanah liter 9,000.00
6 Olie SAE 20, 40, 60, 80 dan 120 liter 35,000.00
7 Pelumas bekisting liter 10,000.00
8 Stempet kg 25,000.00

VII.CETAKAN
1 Bata merah bh 600.00
2 Bata berongga bh 2,250.00
3 Genteng glazuur turbo ex Jatiwangi bh 2,500.00
4 Genteng nok/bubung diglazuur ex Jatiwangi bh 3,500.00
5 Genteng nok/bubung press mesin ex Jatiwangi bh 2,200.00
6 Genteng nok/bubung press tangan ex Jatiwangi bh 2,000.00
7 Genteng nok/bubung morando diglazuur bh 4,500.00
8 Genteng nok/bubung morando bh 4,000.00
9 Genteng press diglazuur ex Jatiwangi bh 2,000.00
10 Genteng press mesin ex Jatiwangi bh 1,900.00
11 Genteng press tangan ex Jatiwangi bh 1,400.00
12 Genteng Type Viktoria bh 9,000.00
13 Genteng nok/bubung Type Viktoria bh 12,500.00
14 Genteng nok/bubung ujung Type Viktoria bh 20,000.00
15 Genteng nok/bubung ujung pertigaan Type Viktoria bh 25,000.00
16 Genteng beton bh 5,000.00
17 Genteng metal m2 75,000.00
18 Gorong-gorong buis beton dia. 100 cm bh/0,5 m' 120,000.00
19 Gorong-gorong buis beton dia. 80 cm bh/0,5 m' 100,000.00
20 Gorong-gorong buis beton dia. 60 cm bh/m' 70,000.00
21 Gorong-gorong buis beton dia. 40 cm bh/m' 60,000.00
22 Gorong-gorong buis beton dia. 30 cm bh/m' 50,000.00
23 Gorong-gorong buis beton dia. 20 cm bh/m' 40,000.00
24 Gravel dia. 60 cm bh 38,000.00
25 Gravel dia. 40 cm bh 35,000.00
26 Gravel dia. 20 cm bh 20,000.00
27 Nok steel gelombang 1050 x 5 mm m' 23,000.00
28 Nok steel gelombang 920 x 5 mm m' 22,500.00
29 Nok / bubung genteng beton bh 6,000.00
30 Paving Block K.175 Segi Enam bh 1,500.00
31 Paving Block K.175 Persegi bh 2,000.00
32 Paving Block K.125 Segi Enam bh 1,250.00
NO URAIAN BAHAN/MATERIAL SAT. HARGA KET
KESEPAKATAN
33 Paving Block K.125 Persegi bh 1,600.00
34 Digital printing m2 25,000.00
NO URAIAN BAHAN/MATERIAL SAT. HARGA KET
KESEPAKATAN
VIII. KAYU
1 Bambu Ø6 - Ø8 / 6 m btg 14,000.00
2 Kayu deplank 8/20 - 4 m (Jati Jateng) m3 8,000,000.00
3 Kayu deplank 8/20 - 4 m (Balau) m3 7,500,000.00
4 Kayu deplank 8/20 - 4 m (Borneo) m3 4,500,000.00
5 Kayu dolken O 8 - 10 /4 m btg 57,000.00
6 Kayu dolken O 12 - 15 /4 m btg 60,000.00
7 Kayu dolken O 5 /3 m btg 35,000.00
8 Kayu hutan/kayu perancah acuan m3 4,255,000.00
9 Kayu kamper m3 8,200,000.00
10 Kayu kaso 5/7 meranti m3 5,000,000.00
11 Kayu kaso 5/7 meranti btg 79,000.00
12 Kayu kruing m3 7,274,000.00
13 Kayu lanan m3 6,546,000.00
14 Kayu meranti m3 5,000,000.00
15 Kayu jati Jabar m3 7,500,000.00
16 Kayu Balau m3 7,500,000.00
17 Kayu Borneo m3 4,500,000.00
18 Kayu bakar m3 90,000.00
19 Reng kayu borneo ukuran 2/3 cm btg 54,000.00
20 Tali Ijuk kg 9,000.00

B. UPAH
1 Mandor /hari 70,000.00
2 Kepala tukang /hari 65,000.00
3 Tukang kayu / besi /hari 60,000.00
4 Tukang batu /hari 60,000.00
5 Pembantu tukang /hari 50,000.00
6 Operator terlatih /hari 60,000.00
7 Operator kurang terlatih /hari 55,000.00
8 Pembantu operator /hari 50,000.00
9 Supir truk /hari 55,000.00
10 Pembantu supir /hari 50,000.00
11 Buruh lapangan terlatih /hari 55,000.00
12 Buruh lapangan kurang terlatih /hari 50,000.00
13 Buruh lapangan tak terlatih / pekerja /hari 50,000.00

DINAS BINA MARGA DINAS PENGELOLAAN SUMBER DAYA AIR


KABUPATEN CIREBON DINAS CIPTA KARYA DAN TATA RUANG DAN PERTAMBANGAN KAB.CIREBON
KABUPATEN CIREBON Kepala Seksi Perencanaan Teknik
Kepala Seksi Desain Teknik
Jalan dan Jembatan Kepala Seksi Bangunan Gedung

SUPARMAN,S.Sos, ST Ir. DAWUD


NIP. 19721230 199901 1 001 NIP. 19640525 199303 1 007
YEDI ADHI PRIATNA, BAE, S.Sos
NIP. 19660815 199803 1 004
Kepala Bidang Bina Teknik Kepala Bidang Bina Teknik
Kepala Bidang Bangunan Gedung, Perumahan dan
Permukiman

RACHMAT S, BE AGUNG GUMILANG, SS., M.si


NIP. 19571008 198709 1 001 Ir. FELLYANTO TAMZIL, MM NIP. 19711224 199803 1 004
NIP. 19620428 199003 1 006
Kepala Dinas Bina Marga Kepala Dinas Pengelolaan Sumber Daya Air
Kabupaten Cirebon dan Pertambangan Kabupaten Cirebon
Kepala Dinas Cipta Karya dan Tata Ruang
Kabupaten Cirebon

Ir. AVIP SUHERDIAN, MT DEDI NURUL SUDJUDI A


NIP. 19640827 199303 1 006 NIP. 19590721 198303 1 009
Ir. H. ARIEF BUDI PRAYITNO
NIP. 19620428 199003 1 006
DAFTAR KESEPAKATAN HARGA SATUAN BAHAN / MATERIAL DAN UPAH
DINAS BINA MARGA, DINAS PENGELOLAAN SUMBER DAYA AIR & PERTAMBANGAN
DAN DINAS CIPTA KARYA & TATA RUANG
KABUPATEN CIREBON
TAHUN ANGGARAN 2014

NO URAIAN BAHAN/MATERIAL SAT. HARGA KET


KESEPAKATAN
A. BAHAN :
I. BATU
1 Abu Batu m3 172,500.00
2 Agregat kasar m3 203,000.00
3 Agregat halus m3 203,000.00
4 Atras ( tanah urug ) m3 125,000.00
5 Base course A m3 175,000.00
6 Base course B m3 165,800.00
7 Batu apung kg 4,300.00
8 Batu belah 10/15 cm m3 153,000.00
9 Batu belah 15/20 cm m3 153,000.00
10 Batu pecah mesin 0.5-1 cm m3 180,000.00
11 Batu pecah mesin 1-2 cm m3 180,000.00
12 Batu pecah mesin 2-3 cm m3 190,000.00
13 Batu tempel Palimanan 10 X 20 bh 1,500.00
14 Batu tempel kapur tekstur tidak rata bh 2,000.00
15 Chipping m3 203,000.00
16 Filler kg 90.00
17 Kapur bakar m3 70,000.00
18 Kapur Sirih kg 2,000.00
19 Kerikil m3 65,000.00

II. PASIR
1 Pasir beton m3 178,000.00
2 Pasir aspal m3 150,000.00
3 Pasir pasang m3 145,000.00
4 Pasir urug m3 140,000.00
5 Sirtu m3 140,000.00
6 Sirtu tersaring m3 145,000.00
7 Tanah urug pilhan m3 125,000.00
8 Tanah urug biasa m3 100,000.00
III. BESI / PIPA / KAWAT
1 Besi WF/Besi Profil kg 12,500.00
2 Besi strip kg 12,500.00
3 Besi beton kg 11,000.00
4 Besi stainless dia. 0,5" m' 38,000.00
5 Besi stainless dia. 1" m' 60,000.00
6 Besi stainless dia. 1,5" m' 75,000.00
7 Besi stainless dia. 2" m' 80,000.00
8 Besi stainless dia. 2,5" m' 125,000.00
9 Besi stainless dia. 3" m' 152,000.00
10 Besi galvanis dia. 0.5" m' 25,000.00
11 Besi galvanis dia. 1" m' 27,000.00
12 Besi galvanis dia. 1.5" m' 45,000.00
13 Besi galvanis dia. 2" m' 57,000.00
14 Besi galvanis dia. 2.5" m' 80,500.00
15 Besi galvanis dia. 3" m' 96,000.00
16 Besi biasa dia. 2" btg 250,000.00
17 Besi biasa dia. 3" btg 310,000.00
18 Dop besi Ø 3 " bh 60,000.00
19 Kawat beton / Kawat tali kg 18,000.00
20 Kawat bronjong dia. 4 mm kg 20,000.00
21 Kawat galvanis dia. 4 mm kg 20,000.00
22 Kawat galvanis dia. 6 mm kg 24,000.00
23 Kawat duri m' 14,000.00
24 Pipa besi galvanis 2" btg 324,000.00
25 Pipa besi galvanis 3" btg/6m' 500,000.00
26 Pipa PVC Ø 2" S-12,5 ( 8 - 10 bar ) m' 26,300.00
27 Pipa PVC Ø 3" S-12,5 ( 8 - 10 bar ) m' 53,600.00
28 Pipa PVC / paralon 2 inch btg 65,000.00
29 Pipa PVC / paralon 3 inch btg 90,000.00
30 Pipa Reducer PVC Ø 3"-4" bh 6,000.00
NO URAIAN BAHAN/MATERIAL SAT. HARGA KET
KESEPAKATAN
31 Pipa Knee/bend PVC Ø 3" bh 6,000.00
32 Plat baja tebal 5 mm - 20 mm kg 12,650.00
33 Ram kawat harmonika m2 23,000.00
34 Socket besi O 3 " bh 45,000.00
35 Toren Penguin 250 lt bh 525,000.00
36 Toren 500 lt bh 860,000.00
37 Toren 1000 lt bh 1,450,000.00

IV. PABRIKAN / TOKO


1 Alumunium foil m2 9,000.00
2 Alumunium pelapis pintu KM Tebal 0.2 lbr 35,000.00
3 Alumunium pelapis pintu KM Tebal 0.3 lbr 50,000.00
4 Alumunium pelapis pintu KM Tebal 0.4 lbr 70,000.00
5 Asbes gelombang 1500 x 1050 x 4 mm lbr 42,500.00
6 Asbes gelombang 1800 x 920 x 4 mm lbr 32,000.00
7 Asbes gelombang 2100 x 1050 x 4 mm lbr 57,000.00
8 Asbes gelombang 2400 x 1050 x 4 mm lbr 65,000.00
9 Asbes gelombang 2700 x 1050 x 4 mm lbr 75,000.00
10 Asbes gelombang 3000 x 1050 x 4 mm lbr 85,000.00
11 Ampelas lbr 3,000.00
12 Bak mandi keramik volume 0,3 m3 bh 185,000.00
13 Bak mandi fiber 120 L bh 220,000.00
14 Batu apung kg 4,300.00
15 Baut 3/4 " bh 8,500.00
16 Baut 5/8 " bh 3,800.00
17 Baut 1/2 " bh 6,000.00
18 Baut 1/2 " panjang 30 cm bh 8,550.00
19 Beading penurunan ( PC ) gypsum m' 10,000.00
20 Beading horison gypsum m' 10,000.00
21 Cat Menie kg 20,000.00
22 Cat genteng Matex kg 48,000.00
23 Cat genteng maxilite kg 50,000.00
24 Cat penutup kayu Bee brand kg 49,000.00
25 Cat penutup kayu Vim kg 25,000.00
26 Cat penutup kayu Ftalit kg 46,000.00
27 Cat penutup kayu Avian kg 48,000.00
28 Cat penutup tembok Vinilex kg 23,000.00
29 Cat penutup tembok Metrolit kg 23,000.00
30 Cat penutup tembok catylac kg 18,600.00
31 Cat penutup tembok Q Luc kg 10,000.00
32 Cat penutup tembok Property kg 9,500.00
33 Cat penutup besi kg 45,000.00
34 Cat Sinkromat kg 80,000.00
35 Closet duduk ( mono block ) porselen merk INA bh 1,237,000.00
36 Closet duduk ( siram ) porselen merk INA bh 545,000.00
37 Closet jongkok porselen merk INA/KIA bh 140,000.00
38 Closet jongkok porselen merk Avena bh 100,000.00
39 Dempul kayu kg 18,500.00
40 Dinding keramik uk. 10 x 20 cm bh 1,000.00
41 Dinding keramik uk. 20 x 20 cm bh 2,000.00
42 Dinding keramik uk. 20 x 25 cm bh 2,200.00
43 Dinding keramik uk. 30 x 30 cm bh 4,500.00
44 Door closer bh 160,000.00
45 Daun pintu alumunium lengkap warna natural/coklat dop bh 900,000.00
46 Daun pintu alumunium lengkap warna coklat kilap bh 1,300,000.00
47 Daun jendela alumunium lengkap warna natural/coklat dop bh 350,000.00
48 Daun jendela alumunium lengkap warna coklat kilap bh 400,000.00
49 Elastomer 30x30x5 bh 550,000.00
50 Engsel jendela set 12,000.00
51 Engsel pintu set 19,000.00
52 Engsel meubeler bh 3,800.00
53 Eternit tebal 4 mm uk. 1 m x 1 m lbr 6,900.00
54 Eternit tebal 4 mm uk. 1 m x 0,5 m lbr 3,450.00
55 Flincote ltr 22,000.00
56 Loster Jati bh 25,000.00
57 Glass beat kg 20,000.00
58 Glass Block bh 17,500.00
59 Gas elpiji kg 8,800.00
60 Grendel pintu / jendela bh 5,500.00
61 Gypsum board lbr 52,500.00
62 GRC tebal 4 mm lbr 52,500.00
63 Fiber Gelombang 180 x80 lbr 40,000.00
64 Kaca nako tebal 5 mm berikut teralis bh 11,400.00
65 Kaca polos tebal 3 mm m2 63,250.00
66 Kaca polos tebal 5 mm m2 75,000.00
67 Kaca polos tebal 5 mm ryben m2 80,000.00
68 Kait angin bh 7,500.00
69 Kran air Onda bh 12,000.00
70 Kunci gembok bh 20,000.00
NO URAIAN BAHAN/MATERIAL SAT. HARGA KET
KESEPAKATAN
71 Kunci pintu ukuran besar bh 125,000.00
72 Kunci pintu ukuran sedang bh 85,000.00
73 Kunci dan daun pintu dari fiber bh 350,000.00
74 Kusen Alumunium 3" warna natural m' 60,000.00
75 Kusen Alumunium 3" warna coklat dop m' 65,000.00
76 Kusen Alumunium 3" warna coklat kilap m' 70,000.00
77 Kusen Alumunium 4" warna natural m' 65,000.00
78 Kusen Alumunium 4" warna coklat dop m' 70,000.00
79 Kusen Alumunium 4" warna coklat kilap m' 75,000.00
80 Kusen Alumunium 3" YKK m' 100,000.00
81 Kusen Alumunium 4" YKK m' 1,300,000.00
82 Langko - langko kuda - kuda bh 18,000.00
83 Lantai granit 60 x 60 cm ex. Granito corak bh 57,600.00
84 Lantai granit 60 x 60 cm ex. Granito polos bh 84,600.00
85 Lantai granit 40 x 40 cm ex. Essenza bh 43,500.00
86 Lantai granit 40 x 40 cm ex. Granito bh 42,000.00
87 Lantai granit 60 x 60 cm ex. Granito bh 46,800.00
88 Lantai keramik uk. 10 x 20 cm bh 1,000.00
89 Lantai keramik uk. 20 x 20 cm bh 2,000.00
90 Lantai keramik uk. 30 x 30 cm bh 2,200.00
91 Lantai keramik uk. 40 x 40 cm ( putih polos ) bh 4,500.00
92 Lantai terakota 20 x 5 cm bh 4,400.00
93 Lem kayu ltr 30,000.00
94 Lemkra/zat addictive kg 15,000.00
95 Lemkra Just Do It kg 4,500.00
96 Lemkra FS Nat kg 15,850.00
97 List kayu B.3 ( lebar sisi 3 cm ) m' 4,400.00
98 List kayu B.4 ( lebar sisi 4 cm ) m' 4,800.00
99 List keliling gypsum lebar 7 cm m' 14,000.00
100 List keliling gypsum lebar 10 cm m' 16,000.00
101 List keliling gypsum lebar 12 cm m' 18,000.00
102 List drop m' 8,900.00
103 Melamin / folywood lbr 88,500.00
104 Mozaik uk. 20 x 20 cm bh 1,900.00
105 Multiplex tebal 12 mm lbr 175,000.00
106 Multiplex tebal 15 mm lbr 275,000.00
107 Paku biasa 1/2" - 1" kg 16,000.00
108 Paku biasa 2" - 5" kg 13,000.00
109 Paku pancing 60 x 230 bh 825.00
110 Paku sekrup 3" - 5 " bh 400.00
111 Paku ulir bh 150.00
112 Plamir kayu / kualitas 1 kg 18,500.00
113 Plamir tembok kg 20,000.00
114 Plester Mutiara kg 8,000.00
115 Pintu kamer mandi fiber polos Daimaru bh 175,000.00
116 Pintu kamer mandi fiber Kaca Daimaru bh 245,000.00
117 Pintu kamer mandi Almunium Kettler bh 700,000.00
118 Polycarbonate m2 115,000.00
119 Plywood lbr 92,250.00
120 Portland Cement ( PC ) tiga roda zak 63,000.00
121 Portland Cement ( PC ) holcim zak 62,500.00
122 Portland Cement ( PC ) gresik zak 61,000.00
123 Rubber joint 25x10x5 bh 175,000.00
124 Roster / batu kerawang bh 4,000.00
125 Semen portland kg 1,260.00
126 Semen warna kg 6,000.00
127 Seng BJLS 30 L. 90 cm m2 38,000.00
128 Seng gelombang 3' - 6 " BJLS 30 lbr 42,000.00
129 Sirlak kg 19,500.00
130 Spirtus ltr 9,000.00
131 Skim Coat kg 4,400.00
132 Taekwood 4 mm 1200 x 2400 mm lbr 80,000.00
133 Taekwood 4 mm 900 x 2400 mm lbr 65,000.00
134 Ter kayu kg 14,500.00
135 Thermoplastic Glass beat kg 23,000.00
136 Tiner / minyak cat ltr 6,000.00
137 Triplek 3 mm lbr 45,000.00
138 Triplek 4 mm lbr 55,000.00
139 Triplek 6 mm lbr 75,000.00
140 Triplek 9 mm lbr 102,500.00
141 Triplek 12 mm lbr 200,000.00
142 Tempat cuci piring Beleza bh 400,000.00
143 Tempat cuci piring Benoti bh 175,000.00
144 Tempat cuci piring Royal bh 160,000.00
145 TG 302 kg 43,600.00
146 Washtafel bh 686,000.00
147 Woodplank corak 4 m lbr 60,000.00
148 Woodplank polos 2 m lbr 32,500.00
NO URAIAN BAHAN/MATERIAL SAT. HARGA KET
KESEPAKATAN
149 Ubin abu2 kepala basah 20 x 20 cm bh 2,000.00
150 Ubin abu2 kepala basah 30 x 30 cm bh 2,500.00
151 Ubin wafel ukuran 20 x 20 cm bh 2,000.00
152 Ubin warna 20 x 20 cm bh 2,300.00
153 Ubin warna 30 x 30 cm bh 2,900.00
154 Washtafel bh 686,000.00
155 Woodplank corak 4 m lbr 60,000.00
156 Woodplank polos 2 m lbr 32,500.00
157 Zincalume m2 75,000.00
158 Rangka plafon memakai Hollow dengan penutup GRC tebal 4 mm + pengec m2 88,200.00
159 Rangka atap baja ringan
a. Atap Baja Ringan memakai Genteng Keramik/Plentong ( jarak reng 22-28 cm)
- Atap Baja Ringan Pelana Bentang < 9 m Zinc-Alumunium G.550 m2 165,000.00
- Atap Baja Ringan Perisai Bentang < 9 m Zinc-Alumunium G.550 m2 175,000.00
- Atap Baja Ringan Joglo Bentang < 9 m Zinc-Alumunium G.550 m2 185,000.00
- Atap Baja Ringan Pelana Bentang 10-12 m Zinc-Alumunium G.550 m2 175,000.00
- Atap Baja Ringan Perisai Bentang 10-12 m Zinc-Alumunium G.550 m2 190,000.00
- Atap Baja Ringan Joglo Bentang 10-12 m Zinc-Alumunium G.550 m2 200,000.00
- Atap Baja Ringan Pelana Bentang > 12 m Zinc-Alumunium G.550 m2 190,000.00
- Atap Baja Ringan Perisai Bentang > 12 m Zinc-Alumunium G.550 m2 200,000.00
- Atap Baja Ringan Joglo Bentang > 12 m Zinc-Alumunium G.550 m2 210,000.00
b. Atap Baja Ringan Genteng Metal/Spandek ( jarak reng 37,5-90 cm)
- Atap Baja Ringan Pelana Bentang < 9 m Zinc-Alumunium G.550 m2 155,000.00
- Atap Baja Ringan Perisai Bentang < 9 m Zinc-Alumunium G.550 m2 162,500.00
- Atap Baja Ringan Joglo Bentang < 9 m Zinc-Alumunium G.550 m2 170,000.00
- Atap Baja Ringan Pelana Bentang 10-12 m Zinc-Alumunium G.550 m2 160,000.00
- Atap Baja Ringan Perisai Bentang 10-12 m Zinc-Alumunium G.550 m2 175,000.00
- Atap Baja Ringan Joglo Bentang 10-12 m Zinc-Alumunium G.550 m2 185,000.00
- Atap Baja Ringan Pelana Bentang > 12 m Zinc-Alumunium G.550 m2 170,000.00
- Atap Baja Ringan Perisai Bentang > 12 m Zinc-Alumunium G.550 m2 180,000.00
- Atap Baja Ringan Joglo Bentang > 12 m Zinc-Alumunium G.550 m2 190,000.00

160 Pintu Air Sorong


- Pintu Air Sorong Baja B = 0.40-0.60 ( 1 drat stang tanpa roda gigi ) Unit 8,497,000.00
- Pintu Air Sorong Baja B = 0.70-0.80 ( 1 drat stang tanpa roda gigi ) Unit 9,639,000.00
- Pintu Air Sorong Baja B = 0.90-1.00 ( 1 drat stang tanpa roda gigi ) Unit 13,500,000.00
- Pintu Air Sorong Baja B = 0.70-1.00 ( 1 drat stang + roda gigi ) Unit 11,414,000.00
- Pintu Air Sorong Baja B = 1.00-1.10 ( 2 drat stang + roda gigi ) Unit 25,366,000.00
- Pintu Air Sorong Baja B = 1.50-1.80 ( 2 drat stang + roda gigi ) Unit 38,049,000.00
- Pintu Air Sorong Baja B = 2.00-2.50 ( 2 drat stang + roda gigi ) Unit 50,732,000.00
161 Gigi Payung / Jantung Besar bh 1,250,000.00
162 Gigi Payung / Jantung Sedang bh 1,100,000.00
163 Gigi Piring Besar bh 2,930,000.00
164 Gigi Piring Sedang bh 1,903,000.00
165 Blok Laher bh 1,750,000.00
166 Bron mur drat 5 " bh 3,250,000.00
167 Bron mur drat 3 " bh 2,150,000.00
168 Drat stang 2" x 100 bh 2,500,000.00
169 Drat stang 3/4" x 100 bh 1,750,000.00
170 Drat stang 1,5" x 100 bh 1,550,000.00
171 Dudukan as horisontal bh 1,850,000.00
172 As Horisontal bh 1,850,000.00
173 Karet sel 8 x 3 cm bh 1,500,000.00
174 As Pemutar bh 750,000.00
175 Laher/Bearing bh 350,000.00
176 Engkel Kemudi Sedang bh 450,000.00
177 Daun Pintu B.50, H.50 bh 1,000,000.00
178 Pintu Klep B=0,5 m unit 1,750,000.00
179 Pintu Klep B=1,0 m unit 3,000,000.00
180 Pintu Klep B=1,5 m unit 4,500,000.00

V. ASPAL
1 Aspal kemasan kg 11,300.00
2 Aspal curah kg 11,100.00

VI. MINYAK
1 Premium liter 6,500.00
2 Premium (non subsidi) liter 9,600.00
3 Solar liter 6,500.00
4 Solar (non subsidi) liter 10,400.00
5 Minyak tanah liter 10,300.00
6 Olie SAE 20, 40, 60, 80 dan 120 liter 35,000.00
7 Pelumas bekisting liter 10,000.00
8 Stempet kg 25,000.00
NO URAIAN BAHAN/MATERIAL SAT. HARGA KET
KESEPAKATAN
VII.CETAKAN
1 Bata merah bh 650.00
2 Bata berongga bh 2,400.00
3 Batako bh 3,200.00
4 Genteng glazuur turbo ex Jatiwangi bh 2,500.00
5 Genteng nok/bubung diglazuur ex Jatiwangi bh 3,500.00
6 Genteng nok/bubung press mesin ex Jatiwangi bh 2,200.00
7 Genteng nok/bubung press tangan ex Jatiwangi bh 2,000.00
8 Genteng nok/bubung morando diglazuur bh 4,500.00
9 Genteng morando bh 3,500.00
10 Genteng nok/bubung morando bh 4,000.00
11 Genteng press diglazuur ex Jatiwangi bh 2,500.00
12 Genteng press mesin ex Jatiwangi bh 1,900.00
13 Genteng press tangan ex Jatiwangi bh 1,400.00
14 Genteng Type Viktoria bh 9,000.00
15 Genteng nok/bubung Type Viktoria bh 12,500.00
16 Genteng nok/bubung ujung Type Viktoria bh 20,000.00
17 Genteng nok/bubung ujung pertigaan Type Viktoria bh 25,000.00
18 Genteng beton bh 5,000.00
19 Genteng metal 70 x 80 cm lbr 48,000.00
20 Gorong-gorong buis beton dia. 100 cm bh/0,5 m' 120,000.00
21 Gorong-gorong buis beton dia. 80 cm bh/0,5 m' 100,000.00
22 Gorong-gorong buis beton dia. 60 cm bh/m' 80,000.00
23 Gorong-gorong buis beton dia. 40 cm bh/m' 60,000.00
24 Gorong-gorong buis beton dia. 30 cm bh/m' 50,000.00
25 Gorong-gorong buis beton dia. 20 cm bh/m' 40,000.00
26 Gravel dia. 60 cm bh 40,000.00
27 Gravel dia. 40 cm bh 35,000.00
28 Gravel dia. 20 cm bh 25,000.00
29 Nok steel gelombang 1050 x 5 mm m' 29,000.00
30 Nok steel gelombang 920 x 5 mm m' 22,500.00
31 Nok / bubung genteng beton bh 6,000.00
32 Paving Block K.175 Segi Enam Netural tebal 8 cm m2 62,000.00
33 Paving Block K.175 Segi Enam motif tebal 8 cm m2 64,000.00
34 Paving Block K.175 Segi Enam warna tebal 8 cm m2 69,000.00
35 Paving Block K.175 Segi Enam Netural tebal 7 cm m2 55,000.00
36 Paving Block K.175 Segi Enam motif tebal 7 cm m2 58,000.00
37 Paving Block K.175 Segi Enam warna tebal 7 cm m2 64,000.00
38 Paving Block K.175 Segi Enam Netural tebal 6 cm m2 50,000.00
39 Paving Block K.175 Segi Enam motif tebal 6 cm m2 53,000.00
40 Paving Block K.175 Segi Enam warna tebal 6 cm m2 57,000.00
41 Paving Block K.125 Segi Enam Netural tebal 6 cm bh 43,000.00
42 Paving Block K.125 Segi Enam warna tebal 6 cm bh 47,000.00
43 Digital printing m2 25,000.00
VIII. KAYU
1 Bambu Ø6 - Ø8 / 6 m btg 17,000.00
2 Kayu deplank 8/20 - 4 m (Jati Jateng) m3 8,000,000.00
3 Kayu deplank 8/20 - 4 m (Balau) m3 9,500,000.00
4 Kayu deplank 8/20 - 4 m (Borneo) m3 5,000,000.00
5 Kayu dolken O 8 - 10 /4 m btg 60,000.00
6 Kayu dolken O 12 - 15 /4 m btg 68,000.00
7 Kayu dolken O 5 /3 m btg 12,500.00
8 Kayu hutan/kayu perancah acuan m3 4,255,000.00
9 Kayu kamper m3 8,200,000.00
10 Kayu kaso 5/7 meranti m3 6,000,000.00
11 Kayu kaso 5/7 meranti btg 79,000.00
12 Kayu kruing m3 7,274,000.00
13 Kayu lanan m3 6,546,000.00
14 Kayu meranti m3 6,000,000.00
15 Kayu jati Jabar m3 8,200,000.00
16 Kayu Balau m3 9,500,000.00
17 Kayu Borneo m3 5,000,000.00
18 Kayu bakar m3 90,000.00
19 Reng kayu borneo ukuran 2/3 cm btg 54,000.00
20 Tali Ijuk kg 9,000.00
NO URAIAN BAHAN/MATERIAL SAT. HARGA KET
KESEPAKATAN
B. UPAH
1 Mandor /hari 85,000.00
2 Kepala tukang /hari 75,000.00
3 Tukang kayu / besi /hari 70,000.00
4 Tukang batu /hari 70,000.00
5 Pembantu tukang /hari 55,000.00
6 Operator terlatih /hari 100,000.00
7 Operator kurang terlatih /hari 55,000.00
8 Pembantu operator /hari 50,000.00
9 Supir truk /hari 55,000.00
10 Pembantu supir /hari 50,000.00
11 Mekanik /hari 55,000.00
12 Pembantu mekanik /hari 50,000.00
13 Buruh lapangan terlatih /hari 55,000.00
14 Buruh lapangan kurang terlatih /hari 50,000.00
15 Buruh lapangan tak terlatih / pekerja /hari 55,000.00

DINAS BINA MARGA DINAS CIPTA KARYA DAN TATA RUANG DINAS PENGELOLAAN SUMBER DAYA AIR
KABUPATEN CIREBON KABUPATEN CIREBON DAN PERTAMBANGAN KAB.CIREBON
Kepala Seksi Perencanaan Teknik
Kepala Seksi Desain Teknik Kepala Seksi Bangunan Gedung
Jalan dan Jembatan

SUPARMAN,S.Sos, ST YEDI ADHI PRIATNA, BAE, S.Sos Ir. DAWUD


NIP. 19721230 199901 1 001 NIP. 19660815 199803 1 004 NIP. 19640525 199303 1 007

Kepala Bidang Bina Teknik Kepala Bidang Bangunan Gedung, Perumahan dan Kepala Bidang Bina Teknik
Permukiman

RACHMAT S, BE Ir. FELLYANTO TAMZIL, MM AGUNG GUMILANG, SS., M.si


NIP. 19571008 198709 1 001 NIP. 19620428 199003 1 006 NIP. 19711224 199803 1 004

Kepala Dinas Bina Marga Kepala Dinas Cipta Karya dan Tata Ruang Kepala Dinas Pengelolaan Sumber Daya Air
Kabupaten Cirebon Kabupaten Cirebon dan Pertambangan Kabupaten Cirebon

Ir. AVIP SUHERDIAN, MT Ir. H. ARIEF BUDI PRAYITNO DEDI NURUL SUDJUDI A
NIP. 19640827 199303 1 006 NIP. 19620428 199003 1 006 NIP. 19590721 198303 1 009
DAFTAR KESEPAKATAN HARGA SATUAN BAHAN / MATERIAL DAN UPAH
DINAS BINA MARGA, DINAS PENGELOLAAN SUMBER DAYA AIR & PERTAMBANGAN
DAN DINAS CIPTA KARYA & TATA RUANG
KABUPATEN CIREBON
HARGA TERTINGGI TAHUN ANGGARAN 2015

kesimpulan
NO URAIAN BAHAN/MATERIAL SAT. HARGA TERTINGGI 2015 HARGA TERTINGGI 2015 harga survay
HARGA DASAR + 10 % tertinggi
A. BAHAN :
I. BATU
1 Abu Batu m3 185,850.00 204,400.00
2 Atras ( tanah urug ) m3 125,000.00 137,500.00
3 Base course A m3
4 Base course B m3
5 Batu apung kg 4,300.00 4,700.00
6 Batu belah 10/15 cm m3 175,000.00 192,500.00
7 Batu belah 15/20 cm (Krakal) m3 175,000.00 192,500.00
8 Batu pecah mesin 0.5-1 cm m3 200,000.00 220,000.00
9 Batu pecah mesin 1-2 cm m3 200,000.00 220,000.00
10 Batu pecah mesin 2-3 cm m3 200,000.00 220,000.00
11 Batu pecah mesin 3-5 cm 182,000.00 200,200.00
12 Batu tempel Palimanan 10 X 20 bh 1,500.00 1,650.00
13 Batu tempel kapur tekstur tidak rata bh 2,000.00 2,200.00
14 Chipping m3 245,300.00 269,800.00
15 Filler kg 100.00 100.00
16 Kapur bakar m3 70,000.00 77,000.00
17 Kapur Sirih kg 2,000.00 2,200.00
18 Kerikil m3 65,000.00 71,500.00

II. PASIR
1 Pasir beton m3 179,000.00 196,900.00
2 Pasir aspal m3 175,000.00 192,500.00
3 Pasir pasang m3 162,000.00 178,200.00
4 Pasir urug m3 150,000.00 165,000.00
5 Sirtu m3 145,000.00 159,500.00
6 Sirtu tersaring m3 147,000.00 161,700.00
7 Tanah urug pilhan m3 125,000.00 137,500.00
8 Tanah urug biasa m3 100,000.00 110,000.00
Tanah merah m3 112,500.00 123,750.00
III. BESI / PIPA / KAWAT
1 Besi WF/Besi Profil kg 13,750.00 15,125.00
2 Besi strip kg 13,750.00 15,125.00
3 Besi beton kg 13,000.00 14,300.00
4 Besi stainless dia. 0,5" m' 38,000.00 41,800.00
5 Besi stainless dia. 1" m' 60,000.00 66,000.00
6 Besi stainless dia. 1,5" m' 75,000.00 82,500.00
7 Besi stainless dia. 2" m' 80,000.00 88,000.00
8 Besi stainless dia. 2,5" m' 125,000.00 137,500.00
9 Besi stainless dia. 3" m' 152,000.00 167,200.00
10 Besi galvanis dia. 0.5" m' 25,000.00 27,500.00
11 Besi galvanis dia. 1" m' 27,000.00 29,700.00
12 Besi galvanis dia. 1.5" m' 45,000.00 49,500.00
13 Besi galvanis dia. 2" m' 57,000.00 62,700.00
14 Besi galvanis dia. 2.5" m' 80,500.00 88,550.00
15 Besi galvanis dia. 3" m' 84,000.00 92,400.00
16 Besi biasa dia. 2" btg 250,000.00 275,000.00
17 Besi biasa dia. 3" btg 310,000.00 341,000.00
18 Dop besi Ø 3 " bh 60,000.00 66,000.00
19 Kawat beton / Kawat tali kg 18,000.00 19,800.00
20 Kawat bronjong pabrikan dia. 3 mm (uk 2x1x0.5) unit 388,080.00 426,888.00
21 Kawat bronjong dia. 4 mm kg 20,000.00 22,000.00
22 Kawat galvanis dia. 4 mm kg 20,000.00 22,000.00
23 Kawat galvanis dia. 6 mm kg 24,000.00 26,400.00
24 Kawat duri m' 14,000.00 15,400.00
25 Pipa besi galvanis 2" btg/6m' 324,000.00 356,400.00
26 Pipa besi galvanis 3" btg/6m' 500,000.00 550,000.00
27 Pipa PVC Ø 2" S-12,5 ( 8 - 10 bar ) m' 26,300.00 28,900.00
28 Pipa PVC Ø 3" S-12,5 ( 8 - 10 bar ) m' 53,600.00 58,900.00
29 Pipa PVC / paralon 2 inch btg 69,000.00 75,900.00
30 Pipa PVC / paralon 3 inch btg 90,000.00 99,000.00
31 Pipa Reducer PVC Ø 3"-4" bh 6,000.00 6,600.00
kesimpulan
NO URAIAN BAHAN/MATERIAL SAT. HARGA TERTINGGI 2015 HARGA TERTINGGI 2015 harga survay
HARGA DASAR + 10 % tertinggi
32 Pipa Knee/bend PVC Ø 3" bh 6,000.00 6,600.00
33 Plat baja tebal 5 mm - 20 mm kg 13,000.00 14,300.00
34 Ram kawat harmonika m2 25,000.00 27,500.00
35 Socket besi O 3 " bh 45,000.00 49,500.00
36 Toren Penguin 250 lt bh 525,000.00 577,500.00
37 Toren 500 lt bh 860,000.00 946,000.00
38 Toren 1000 lt bh 1,450,000.00 1,595,000.00
39 Sling Ø 32 mm m 300,000.00 330,000.00
40 Sling Ø 16 mm m 175,000.00 192,500.00
41 Klem sling Ø 32 mm set 250,000.00 275,000.00
42 Warfel / jarum keras Ø 32 mm bh 200,000.00 220,000.00
43 Causen sling Ø 32 mm bh 85,000.00 93,500.00
44 Klem kokat sling Ø 32 mm bh 210,000.00 231,000.00
45 Segel sling Ø 32 mm bh 250,000.00 275,000.00
46 Warfel sling Ø 16 mm bh 135,000.00 148,500.00
47 Segel sling Ø 16 mm bh 140,000.00 154,000.00
48 Klem kokat sling Ø 16 mm bh 35,000.00 38,500.00
49 Causen sling Ø 16 mm bh 50,000.00 55,000.00
50 Jarum keras Ø 16 mm bh 75,000.00 82,500.00

IV. PABRIKAN / TOKO


1 Alumunium foil m2 9,000.00 9,900.00
2 Alumunium pelapis pintu KM Tebal 0.2 lbr 35,000.00 38,500.00
3 Alumunium pelapis pintu KM Tebal 0.3 lbr 50,000.00 55,000.00
4 Alumunium pelapis pintu KM Tebal 0.4 lbr 70,000.00 77,000.00
5 Asbes gelombang 1500 x 1050 x 4 mm lbr 42,500.00 46,750.00
6 Asbes gelombang 1800 x 920 x 4 mm lbr 32,000.00 35,200.00
7 Asbes gelombang 2100 x 1050 x 4 mm lbr 57,000.00 62,700.00
8 Asbes gelombang 2400 x 1050 x 4 mm lbr 65,000.00 71,500.00
9 Asbes gelombang 2700 x 1050 x 4 mm lbr 75,000.00 82,500.00
10 Asbes gelombang 3000 x 1050 x 4 mm lbr 85,000.00 93,500.00
11 Ampelas lbr 3,000.00 3,300.00
12 Bak mandi keramik volume 0,3 m3 bh 185,000.00 203,500.00
13 Bak mandi fiber 120 L bh 220,000.00 242,000.00
14 Batu apung kg 4,300.00 4,700.00
15 Baut 3/4 " bh 6,700.00 7,300.00
16 Baut 5/8 " bh 6,700.00 7,300.00
17 Baut 1/2 " bh 6,000.00 6,600.00
18 Baut 1/2 " panjang 30 cm bh 8,550.00 9,400.00
19 Baut lawa-lawa 12 cm 13,000.00 14,300.00
20 Beading penurunan ( PC ) gypsum m' 10,000.00 11,000.00
21 Beading horison gypsum m' 10,000.00 11,000.00
22 Cat Menie kg 25,000.00 27,500.00
23 Cat genteng Matex kg 48,000.00 52,800.00
24 Cat genteng maxilite kg 50,000.00 55,000.00
25 Cat penutup kayu Bee brand kg 49,000.00 53,900.00
26 Cat penutup kayu Vim kg 25,000.00 27,500.00
27 Cat penutup kayu Ftalit kg 46,000.00 50,600.00
28 Cat penutup kayu Avian kg 48,000.00 52,800.00
29 Cat penutup tembok Vinilex kg 25,000.00 27,500.00
30 Cat penutup tembok Metrolit kg 23,000.00 25,300.00
31 Cat penutup tembok catylac kg 18,600.00 20,400.00
32 Cat penutup tembok Q Luc kg 10,000.00 11,000.00
33 Cat penutup tembok Property kg 9,500.00 10,450.00
34 Cat penutup besi kg 52,000.00 57,200.00
35 Cat Sinkromat kg 90,000.00 99,000.00
36 Closet duduk ( mono block ) porselen merk INA bh 1,237,000.00 1,360,700.00
37 Closet duduk ( siram ) porselen merk INA bh 545,000.00 599,500.00
38 Closet jongkok porselen merk INA/KIA bh 140,000.00 154,000.00
39 Closet jongkok porselen merk Avena bh 100,000.00 110,000.00
40 Dempul kayu kg 18,500.00 20,350.00
41 Dinding keramik uk. 10 x 20 cm bh 1,000.00 1,100.00
42 Dinding keramik uk. 20 x 20 cm bh 2,000.00 2,200.00
43 Dinding keramik uk. 20 x 25 cm bh 2,200.00 2,400.00
44 Dinding keramik uk. 30 x 30 cm bh 4,500.00 4,950.00
45 Door closer bh 160,000.00 176,000.00
46 Daun pintu alumunium lengkap warna natural/coklat dop bh 900,000.00 990,000.00
47 Daun pintu alumunium lengkap warna coklat kilap bh 1,300,000.00 1,430,000.00
48 Daun jendela alumunium lengkap warna natural/coklat do bh 350,000.00 385,000.00
49 Daun jendela alumunium lengkap warna coklat kilap bh 400,000.00 440,000.00
50 Elastomer 30x30x5 bh 632,500.00 695,750.00
51 Engsel jendela set 12,000.00 13,200.00
52 Engsel pintu set 19,000.00 20,900.00
53 Engsel meubeler bh 3,800.00 4,200.00
54 Eternit tebal 4 mm uk. 1 m x 1 m lbr 6,900.00 7,600.00
55 Eternit tebal 4 mm uk. 1 m x 0,5 m lbr 3,450.00 3,800.00
56 Flincote ltr 22,000.00 24,200.00
57 Loster Jati bh 25,000.00 27,500.00
58 Glass beat kg 25,000.00 27,500.00
59 Glass Block bh 17,500.00 19,250.00
60 Gas elpiji kg 8,800.00 9,700.00
61 Grendel pintu / jendela bh 5,500.00 6,000.00
62 Gypsum board lbr 52,500.00 57,750.00
63 GRC tebal 4 mm lbr 52,500.00 57,750.00
64 Fiber Gelombang 180 x80 lbr 40,000.00 44,000.00
65 Kaca nako tebal 5 mm berikut teralis bh 11,400.00 12,500.00
66 Kaca polos tebal 3 mm m2 63,250.00 69,575.00
67 Kaca polos tebal 5 mm m2 75,000.00 82,500.00
68 Kaca polos tebal 5 mm ryben m2 80,000.00 88,000.00
69 Kait angin bh 7,500.00 8,250.00
70 Kran air Onda bh 12,000.00 13,200.00
71 Kunci gembok bh 20,000.00 22,000.00
kesimpulan
NO URAIAN BAHAN/MATERIAL SAT. HARGA TERTINGGI 2015 HARGA TERTINGGI 2015 harga survay
HARGA DASAR + 10 % tertinggi
72 Kunci pintu ukuran besar bh 125,000.00 137,500.00
73 Kunci pintu ukuran sedang bh 85,000.00 93,500.00
74 Kunci dan daun pintu dari fiber bh 350,000.00 385,000.00
75 Kusen Alumunium 3" warna natural m' 60,000.00 66,000.00
76 Kusen Alumunium 3" warna coklat dop m' 65,000.00 71,500.00
77 Kusen Alumunium 3" warna coklat kilap m' 70,000.00 77,000.00
78 Kusen Alumunium 4" warna natural m' 65,000.00 71,500.00
79 Kusen Alumunium 4" warna coklat dop m' 70,000.00 77,000.00
80 Kusen Alumunium 4" warna coklat kilap m' 75,000.00 82,500.00
81 Kusen Alumunium 3" YKK m' 100,000.00 110,000.00
82 Kusen Alumunium 4" YKK m' 1,300,000.00 1,430,000.00
83 Langko - langko kuda - kuda bh 18,000.00 19,800.00
84 Lantai granit 60 x 60 cm ex. Granito corak bh 57,600.00 63,400.00
85 Lantai granit 60 x 60 cm ex. Granito polos bh 84,600.00 93,000.00
86 Lantai granit 40 x 40 cm ex. Essenza bh 43,500.00 47,850.00
87 Lantai granit 40 x 40 cm ex. Granito bh 42,000.00 46,200.00
88 Lantai granit 60 x 60 cm ex. Granito bh 46,800.00 51,500.00
89 Lantai keramik uk. 10 x 20 cm bh 1,000.00 1,100.00
90 Lantai keramik uk. 20 x 20 cm bh 2,000.00 2,200.00
91 Lantai keramik uk. 30 x 30 cm bh 2,200.00 2,400.00
92 Lantai keramik uk. 40 x 40 cm ( putih polos ) bh 4,500.00 4,950.00
93 Lantai terakota 20 x 5 cm bh 4,400.00 4,800.00
94 Lem kayu ltr 30,000.00 33,000.00
95 Lemkra/zat addictive kg 15,000.00 16,500.00
96 Lemkra Just Do It kg 4,500.00 4,950.00
97 Lemkra FS Nat kg 15,850.00 17,400.00
98 List kayu B.3 ( lebar sisi 3 cm ) m' 4,400.00 4,800.00
99 List kayu B.4 ( lebar sisi 4 cm ) m' 4,800.00 5,300.00
100 List keliling gypsum lebar 7 cm m' 14,000.00 15,400.00
101 List keliling gypsum lebar 10 cm m' 16,000.00 17,600.00
102 List keliling gypsum lebar 12 cm m' 18,000.00 19,800.00
103 List drop m' 8,900.00 9,800.00
104 Melamin / folywood lbr 88,500.00 97,350.00
105 Mozaik uk. 20 x 20 cm bh 1,900.00 2,100.00
106 Multiplex tebal 12 mm lbr 175,000.00 192,500.00
107 Multiplex tebal 15 mm lbr 275,000.00 302,500.00
108 Paku biasa 1/2" - 1" kg 18,500.00 20,350.00
109 Paku biasa 2" - 5" kg 20,000.00 22,000.00
110 Paku pancing 60 x 230 bh 825.00 900.00
111 Paku sekrup 3" - 5 " bh 400.00 450.00
112 Paku ulir bh 150.00 200.00
113 Plamir kayu / kualitas 1 kg 20,000.00 22,000.00
114 Plamir tembok kg 23,000.00 25,300.00
115 Plester Mutiara kg 8,000.00 8,800.00
116 Pintu kamer mandi fiber polos Daimaru bh 175,000.00 192,500.00
117 Pintu kamer mandi fiber Kaca Daimaru bh 245,000.00 269,500.00
118 Pintu kamer mandi Almunium Kettler bh 700,000.00 770,000.00
119 Polycarbonate m2 115,000.00 126,500.00
120 Plywood lbr 92,250.00 101,475.00
121 Portland Cement ( PC ) tiga roda zak 68,000.00 68,000.00
122 Portland Cement ( PC ) holcim zak 67,000.00 67,000.00
123 Portland Cement ( PC ) gresik zak 66,000.00 66,000.00
124 Rubber joint 25x10x5 bh 192,500.00 211,750.00
125 Joint Sealent kg 42,900.00 47,200.00
126 Expansion Cap m2 7,600.00 8,400.00
127 Polytene 125 mikron kg 27,500.00 30,250.00
128 Curing Compound Ltr 4,400.00 4,850.00
129 Roster / batu kerawang bh 4,000.00 4,400.00
130 Semen portland kg 1,360.00 1,360.00
131 Semen warna kg 6,000.00 6,000.00
132 Seng BJLS 30 L. 90 cm m2 38,000.00 41,800.00
133 Seng gelombang 3' - 6 " BJLS 30 lbr 51,000.00 56,100.00
134 Sirlak kg 19,500.00 21,450.00
135 Spirtus ltr 9,000.00 9,900.00
136 Skim Coat kg 4,400.00 4,850.00
137 Taekwood 4 mm 1200 x 2400 mm lbr 80,000.00 88,000.00
138 Taekwood 4 mm 900 x 2400 mm lbr 65,000.00 71,500.00
139 Ter kayu kg 14,500.00 15,950.00
140 Thermoplastic Glass beat kg 25,000.00 27,500.00
141 Tiner / minyak cat ltr 11,500.00 12,650.00
142 Triplek 3 mm lbr 52,000.00 57,200.00
143 Triplek 4 mm lbr 55,000.00 60,500.00
144 Triplek 6 mm lbr 83,000.00 91,300.00
145 Triplek 9 mm lbr 102,500.00 112,750.00
146 Triplek 12 mm lbr 200,000.00 220,000.00
147 Tempat cuci piring Beleza bh 400,000.00 440,000.00
148 Tempat cuci piring Benoti bh 175,000.00 192,500.00
149 Tempat cuci piring Royal bh 160,000.00 176,000.00
150 TG 302 kg 43,600.00 47,950.00
151 Washtafel bh 686,000.00 754,600.00
152 Woodplank corak 4 m lbr 60,000.00 66,000.00
153 Woodplank polos 2 m lbr 32,500.00 35,750.00
kesimpulan
NO URAIAN BAHAN/MATERIAL SAT. HARGA TERTINGGI 2015 HARGA TERTINGGI 2015 harga survay
HARGA DASAR + 10 % tertinggi
154 Ubin abu2 kepala basah 20 x 20 cm bh 2,000.00 2,200.00
155 Ubin abu2 kepala basah 30 x 30 cm bh 2,500.00 2,750.00
156 Ubin wafel ukuran 20 x 20 cm bh 2,000.00 2,200.00
157 Ubin warna 20 x 20 cm bh 2,300.00 2,550.00
158 Ubin warna 30 x 30 cm bh 2,900.00 3,200.00
159 Washtafel bh 686,000.00 754,600.00
160 Woodplank corak 4 m lbr 60,000.00 66,000.00
161 Woodplank polos 2 m lbr 32,500.00 35,750.00
162 Zincalume m2 75,000.00 82,500.00
163 Rangka plafon memakai Hollow dengan penutup GRC teb m2 88,200.00 97,000.00
164 Rangka atap baja ringan
a. Atap Baja Ringan memakai Genteng Keramik/Plentong ( jarak reng 22-28 cm)
- Atap Baja Ringan Pelana Bentang < 9 m Zinc-Alumuni m2 165,000.00 181,500.00
- Atap Baja Ringan Perisai Bentang < 9 m Zinc-Alumuni m2 175,000.00 192,500.00
- Atap Baja Ringan Joglo Bentang < 9 m Zinc-Alumuniu m2 185,000.00 203,500.00
- Atap Baja Ringan Pelana Bentang 10-12 m Zinc-Alumu m2 175,000.00 192,500.00
- Atap Baja Ringan Perisai Bentang 10-12 m Zinc-Alum m2 190,000.00 209,000.00
- Atap Baja Ringan Joglo Bentang 10-12 m Zinc-Alumun m2 200,000.00 220,000.00
- Atap Baja Ringan Pelana Bentang > 12 m Zinc-Alumun m2 190,000.00 209,000.00
- Atap Baja Ringan Perisai Bentang > 12 m Zinc-Alumun m2 200,000.00 220,000.00
- Atap Baja Ringan Joglo Bentang > 12 m Zinc-Alumuni m2 210,000.00 231,000.00
b. Atap Baja Ringan Genteng Metal/Spandek ( jarak reng 37,5-90 cm)
- Atap Baja Ringan Pelana Bentang < 9 m Zinc-Alumuni m2 155,000.00 170,500.00
- Atap Baja Ringan Perisai Bentang < 9 m Zinc-Alumuni m2 162,500.00 178,750.00
- Atap Baja Ringan Joglo Bentang < 9 m Zinc-Alumuniu m2 170,000.00 187,000.00
- Atap Baja Ringan Pelana Bentang 10-12 m Zinc-Alumu m2 160,000.00 176,000.00
- Atap Baja Ringan Perisai Bentang 10-12 m Zinc-Alum m2 175,000.00 192,500.00
- Atap Baja Ringan Joglo Bentang 10-12 m Zinc-Alumun m2 185,000.00 203,500.00
- Atap Baja Ringan Pelana Bentang > 12 m Zinc-Alumun m2 170,000.00 187,000.00
- Atap Baja Ringan Perisai Bentang > 12 m Zinc-Alumun m2 180,000.00 198,000.00
- Atap Baja Ringan Joglo Bentang > 12 m Zinc-Alumuni m2 190,000.00 209,000.00

165 Pintu Air Sorong


- Pintu Air Sorong Baja B = 0.40-0.60 ( 1 drat stang tanpa Unit 8,497,000.00 9,346,700.00
- Pintu Air Sorong Baja B = 0.70-0.80 ( 1 drat stang tanpa Unit 9,639,000.00 10,602,900.00
- Pintu Air Sorong Baja B = 0.90-1.00 ( 1 drat stang tanpa Unit 13,500,000.00 14,850,000.00
- Pintu Air Sorong Baja B = 0.70-1.00 ( 1 drat stang + roda Unit 11,414,000.00 12,555,400.00
- Pintu Air Sorong Baja B = 1.00-1.10 ( 2 drat stang + roda Unit 25,366,000.00 27,902,600.00
- Pintu Air Sorong Baja B = 1.50-1.80 ( 2 drat stang + roda Unit 38,049,000.00 41,853,900.00
- Pintu Air Sorong Baja B = 2.00-2.50 ( 2 drat stang + roda Unit 50,732,000.00 55,805,200.00
166 Gigi Payung / Jantung Besar bh 1,250,000.00 1,375,000.00
167 Gigi Payung / Jantung Sedang bh 1,100,000.00 1,210,000.00
168 Gigi Piring Besar bh 2,930,000.00 3,223,000.00
169 Gigi Piring Sedang bh 1,903,000.00 2,093,300.00
170 Blok Laher bh 1,750,000.00 1,925,000.00
171 Bron mur drat 5 " bh 3,250,000.00 3,575,000.00
172 Bron mur drat 3 " bh 2,150,000.00 2,365,000.00
173 Drat stang 2" x 100 bh 2,500,000.00 2,750,000.00
174 Drat stang 3/4" x 100 bh 1,750,000.00 1,925,000.00
175 Drat stang 1,5" x 100 bh 1,550,000.00 1,705,000.00
176 Dudukan as horisontal bh 1,850,000.00 2,035,000.00
177 As Horisontal bh 1,850,000.00 2,035,000.00
178 Karet sel 8 x 3 cm bh 1,500,000.00 1,650,000.00
179 As Pemutar bh 750,000.00 825,000.00
180 Laher/Bearing bh 350,000.00 385,000.00
181 Engkel Kemudi Sedang bh 450,000.00 495,000.00
182 Daun Pintu B.50, H.50 bh 1,000,000.00 1,100,000.00
183 Pintu Klep B=0,5 m unit 1,750,000.00 1,925,000.00
184 Pintu Klep B=1,0 m unit 3,000,000.00 3,300,000.00
185 Pintu Klep B=1,5 m unit 4,500,000.00 4,950,000.00

V. ASPAL
1 Aspal kemasan kg 12,100.00 12,100.00
2 Aspal curah kg 11,600.00 11,600.00
3 Aspal Emulsi ltr 10,500.00 10,500.00

VI. MINYAK
1 Premium liter 6,500.00 6,500.00
2 Premium (non subsidi) liter 11,400.00 11,400.00
3 Solar liter 5,500.00 5,500.00
4 Solar (non subsidi) liter 11,900.00 11,900.00
5 Minyak tanah liter 12,500.00 12,500.00
6 Olie SAE 20, 40, 60, 80 dan 120 liter 42,000.00 42,000.00
7 Pelumas bekisting liter 10,000.00 10,000.00
8 Stempet kg 25,000.00 25,000.00
kesimpulan
NO URAIAN BAHAN/MATERIAL SAT. HARGA TERTINGGI 2015 HARGA TERTINGGI 2015 harga survay
HARGA DASAR + 10 % tertinggi
VII.CETAKAN
1 Bata merah bh 800.00 900.00
2 Bata berongga bh 2,400.00 2,650.00
3 Batako bh 3,200.00 3,500.00
4 Genteng glazuur turbo ex Jatiwangi bh 3,500.00 3,850.00
5 Genteng nok/bubung diglazuur ex Jatiwangi bh 4,000.00 4,400.00
6 Genteng nok/bubung press mesin ex Jatiwangi bh 2,500.00 2,750.00
7 Genteng nok/bubung press tangan ex Jatiwangi bh 2,000.00 2,200.00
8 Genteng nok/bubung morando diglazuur bh 4,500.00 4,950.00
9 Genteng morando bh 3,500.00 3,850.00
10 Genteng nok/bubung morando bh 4,000.00 4,400.00
11 Genteng press diglazuur ex Jatiwangi bh 2,500.00 2,750.00
12 Genteng press mesin ex Jatiwangi bh 1,900.00 2,100.00
13 Genteng press tangan ex Jatiwangi bh 1,400.00 1,550.00
14 Genteng Type Viktoria bh 9,000.00 9,900.00
15 Genteng nok/bubung Type Viktoria bh 12,500.00 13,750.00
16 Genteng nok/bubung ujung Type Viktoria bh 20,000.00 22,000.00
17 Genteng nok/bubung ujung pertigaan Type Viktoria bh 25,000.00 27,500.00
18 Genteng beton bh 5,000.00 5,500.00
19 Genteng metal 70 x 80 cm lbr 48,000.00 52,800.00
20 Gorong-gorong buis beton dia. 100 cm bh/0,5 m' 150,000.00 165,000.00
21 Gorong-gorong buis beton dia. 80 cm bh/0,5 m' 130,000.00 143,000.00
22 Gorong-gorong buis beton dia. 60 cm bh/m' 140,000.00 154,000.00
23 Gorong-gorong buis beton dia. 40 cm bh/m' 100,000.00 110,000.00
24 Gorong-gorong buis beton dia. 30 cm bh/m' 80,000.00 88,000.00
25 Gorong-gorong buis beton dia. 20 cm bh/m' 60,000.00 66,000.00
26 Kansten Cetak 82,500.00 90,750.00
27 Gravel dia. 60 cm bh 75,000.00 82,500.00
28 Gravel dia. 40 cm bh 45,000.00 49,500.00
29 Gravel dia. 20 cm bh 35,000.00 38,500.00
30 Nok steel gelombang 1050 x 5 mm m' 29,000.00 31,900.00
31 Nok steel gelombang 920 x 5 mm m' 22,500.00 24,750.00
32 Nok / bubung genteng beton bh 6,000.00 6,600.00
33 Paving Block K.175 Segi Enam Netural tebal 8 cm m2 62,000.00 68,200.00
34 Paving Block K.175 Segi Enam motif tebal 8 cm m2 64,000.00 70,400.00
35 Paving Block K.175 Segi Enam warna tebal 8 cm m2 69,000.00 75,900.00
36 Paving Block K.175 Segi Enam Netural tebal 7 cm m2 55,000.00 60,500.00
37 Paving Block K.175 Segi Enam motif tebal 7 cm m2 58,000.00 63,800.00
38 Paving Block K.175 Segi Enam warna tebal 7 cm m2 64,000.00 70,400.00
39 Paving Block K.175 Segi Enam Netural tebal 6 cm m2 50,000.00 55,000.00
40 Paving Block K.175 Segi Enam motif tebal 6 cm m2 53,000.00 58,300.00
41 Paving Block K.175 Segi Enam warna tebal 6 cm m2 57,000.00 62,700.00
42 Paving Block K.125 Segi Enam Netural tebal 6 cm bh 43,000.00 47,300.00
43 Paving Block K.125 Segi Enam warna tebal 6 cm bh 47,000.00 51,700.00
44 Tiang pancang beton Pratekan m3 4,600,000.00 5,060,000.00
45 Digital printing m2 25,000.00 27,500.00
VIII. KAYU
1 Bambu Ø6 - Ø8 / 6 m btg 17,000.00 18,700.00
2 Kayu deplank 8/20 - 4 m (Jati Jateng) m3 9,800,000.00 10,780,000.00
3 Kayu deplank 8/20 - 4 m (Balau) m3 9,500,000.00 10,450,000.00
4 Kayu deplank 8/20 - 4 m (Borneo) m3 5,000,000.00 5,500,000.00
5 Kayu dolken O 8 - 10 /4 m btg 60,000.00 66,000.00
6 Kayu dolken O 12 - 15 /4 m btg 68,000.00 74,800.00
7 Kayu dolken O 5 /3 m btg 12,500.00 13,750.00
8 Kayu hutan/kayu perancah acuan m3 4,700,000.00 5,170,000.00
9 Kayu kamper m3 8,200,000.00 9,020,000.00
10 Kayu kaso 5/7 meranti m3 6,000,000.00 6,600,000.00
11 Kayu kaso 5/7 meranti btg 79,000.00 86,900.00
12 Kayu kruing m3 7,274,000.00 8,001,400.00
13 Kayu lanan m3 6,546,000.00 7,200,600.00
14 Kayu meranti m3 6,000,000.00 6,600,000.00
15 Kayu jati Jabar m3 8,200,000.00 9,020,000.00
16 Kayu Balau m3 9,500,000.00 10,450,000.00
17 Kayu Borneo m3 5,000,000.00 5,500,000.00
18 Kayu bakar m3 90,000.00 99,000.00
19 Reng kayu borneo ukuran 2/3 cm btg 54,000.00 59,400.00
20 Tali Ijuk kg 9,000.00 9,900.00
kesimpulan
NO URAIAN BAHAN/MATERIAL SAT. HARGA TERTINGGI 2015 HARGA TERTINGGI 2015 harga survay
HARGA DASAR + 10 % tertinggi
B. UPAH
1 Mandor /hari 85,000.00 85,000.00
2 Kepala tukang /hari 75,000.00 75,000.00
3 Tukang kayu / besi /hari 70,000.00 70,000.00
4 Tukang batu /hari 70,000.00 70,000.00
5 Pembantu tukang /hari 55,000.00 55,000.00
6 Operator terlatih /hari 100,000.00 100,000.00
7 Operator kurang terlatih /hari 55,000.00 55,000.00
8 Pembantu operator /hari 50,000.00 50,000.00
9 Supir truk /hari 55,000.00 55,000.00
10 Pembantu supir /hari 50,000.00 50,000.00
11 Mekanik /hari 55,000.00 55,000.00
12 Pembantu mekanik /hari 50,000.00 50,000.00
13 Buruh lapangan terlatih /hari 55,000.00 55,000.00
14 Buruh lapangan kurang terlatih /hari 50,000.00 50,000.00
15 Buruh lapangan tak terlatih / pekerja /hari 55,000.00 55,000.00

DINAS CIPTA KARYA DAN TATA


RUANG
DINAS BINA MARGA DINAS PENGELOLAAN SUMBER DAYA AIR
KABUPATEN CIREBON
KABUPATEN CIREBON DAN PERTAMBANGAN KAB.CIREBON
Kepala Seksi Bangunan Gedung Kepala Seksi Perencanaan Teknik
Kepala Seksi Desain Teknik
Jalan dan Jembatan

YEDI ADHI PRIATNA, BAE,


SUPARMAN,S.Sos, ST Ir. DAWUD
S.Sos
NIP. 19721230 199901 1 001 NIP. 19640525 199303 1 007
NIP. 19660815 199803 1 004
Kepala Bidang Bina Teknik Kepala Bidang Bina Teknik
Kepala Bidang Bangunan Gedung,
Perumahan dan Permukiman

Ir. TETI MEIRAWATI AGUNG GUMILANG, SS., M.si


Ir. FELLYANTO TAMZIL, MM
NIP. 19670502 199703 2 004 NIP. 19711224 199803 1 004
NIP. 19620428 199003 1 006
Kepala Dinas Bina Marga Kepala Dinas Pengelolaan Sumber Daya Air
Kepala Dinas Cipta Karya dan Tata
Kabupaten Cirebon dan Pertambangan Kabupaten Cirebon
Ruang
Kabupaten Cirebon

Ir. AVIP SUHERDIAN, MT DEDI NURUL SUDJUDI A


NIP. 19640827 199303 1 006 NIP. 19590721 198303 1 009
Ir. H. ARIEF BUDI PRAYITNO
NIP. 19620428 199003 1 006
HARGA PERKIRAAN SENDIRI (HPS)
RENCANA ANGGARAN BIAYA
DAK SLBM (SANITASI LINGKUNGAN BERBASIS MASYARAKAT)

TAHUN : 2019
PESANTREN : ASSA'IDIYYAH
DESA : ENDER
KECAMATAN : PANGENAN
KABUPATEN : CIREBON

HARGA
JUMLAH
NO JENIS PEKERJAAN ANALISA VOLUME SATUAN
Rp Rp
1 2 3 4 5 6

A PEKERJAAN PEMBUATAN BAK SEPTICTANK KOMUNAL


DIMENSI (6,80 x 3,00 x 2,75)
I PEKERJAAN PERSIAPAN
1 Pengukuran dan pemasangan bouwplank A.2.2.1.4 12.99 m' 63,435.20 824,023.25
2 Tembok penahan penahan tanah sementara - 1.00 ls 2,000,000.00 2,000,000.00
2,824,023.25
II PEKERJAAN GALIAN/URUGAN
1 Galian tanah A.2.3.1.1 67.02 m3 63,000.00 4,222,260.00
2 Pek. Urugan pasir T. 10 cm A.2.3.1.11 2.04 m3
257,640.00 525,585.60
3 Pek. Adukan beton ad. 1 PC : 2PS : 3Krl u/ lantai T. 10 cm ABK.300.19 2.04 m3 841,400.00 1,716,456.00
6,464,301.60

III PEKERJAAN BETON/PEMBESIAN


1 Pekerjaan Balok 20/30
Tul 6 Ø 10 mm, Begel Ø 8 - 150 mm
a Pembesian A.4.1.1.17 220.08 kg 15,412.00 3,391,872.96
b Adukan beton ad. 1 PC : 2PS : 3Krl ABK.300.19 1.18 m3 841,400.00 989,486.40
4,381,359.36
2 Pekerjaan Kolom 20/30
Tul 6 Ø 10 mm, Begel Ø 8 - 150 mm
a Pembesian A.4.1.1.17 59.48 kg 15,412.00 916,767.41
b Adukan beton ad. 1 PC : 2PS : 3Krl ABK.300.19 0.35 m3 841,400.00 292,807.20
1,209,574.61
3 Pekerjaan Balok Tutup 15/25
Tul 6 Ø 10 mm, Begel Ø 8 - 150 mm
a Pembesian A.4.1.1.17 51.38 kg 15,412.00 791,883.97
b Bekisting A.4.1.1.21 0.91 m2 240,940.00 219,255.40
c Adukan beton ad. 1 PC : 2PS : 3Krl ABK.300.19 0.10 m3
841,400.00 82,036.50
1,093,175.87
4 Pekerjaan Dinding T = 20 cm
Tul Ø 10 - 150 mm
a Pembesian A.4.1.1.17 361.09 kg 15,412.00 5,565,088.26
b Bekisting A.4.1.1.21 10.78 m2 240,940.00 2,597,333.20
c Adukan beton ad. 1 PC : 2PS : 3Krl ABK.300.19 7.91 m3 841,400.00 6,657,156.80
14,819,578.26
5 Pekerjaan Tutup Dak Beton T = 15 cm
Tul Ø 10 - 150 mm
a Pembesian A.4.1.1.17 271.06 kg 15,412.00 4,177,638.37
b Bekisting A.4.1.1.21 2.70 m2 240,940.00 651,019.88
c Adukan beton ad. 1 PC : 2PS : 3Krl ABK.300.19 2.03 m3 841,400.00 1,705,097.10
6,533,755.35
JUMLAH III : 28,037,443.44
1 2 3 4 5 6

IV PEKERJAAN PLESTERAN
1 Acian Tutup Septictang A.4.4.2.27 18.44 m2 33,950.00 626,038.00
626,038.00

V PEKERJAAN LAIN-LAIN
1 Pek. Pengadaan Ipal Komunal Pabrikasi Volume 20 m3 - 1.00 unit 130,000,000.00 130,000,000.00
2 Pek. Pasangan Manhole (Plat baja) Uk. 70/70 - 4.00 unit 1,500,000.00 6,000,000.00
136,000,000.00

A PEKERJAAN PEMBUATAN BAK SEPTICTANK KOMUNAL


I PEKERJAAN PERSIAPAN 2,824,023.25
II PEKERJAAN GALIAN/URUGAN 6,464,301.60
III PEKERJAAN BETON/PEMBESIAN 28,037,443.44
IV PEKERJAAN PLESTERAN 626,038.00
V PEKERJAAN LAIN-LAIN 136,000,000.00
JUMLAH A : 173,951,806.29
1 2 3 4 5 6

B PENGADAAN DAN PEMASANGAN PIPA PVC 16.00 13.00


1 Pengadaan Pipa PVC AW Ø 6 Inchi - 15.00 m' 119,900.00 1,798,500.00
2 Pengadaan Pipa PVC AW Ø 3 Inchi - 60.00 m' 69,000.00 4,140,000.00
3 Galian tanah untuk pemasangan pipa A.2.3.1.1 12.00 m3 63,435.20 761,222.40
4 Urugan kembali bekas galian pipa A.2.3.1.9. 11.33 m3 46,000.00 520,950.00
JUMLAH B : 7,220,672.40
C PEMBUATAN BAK KONTROL
1 Pek. Pasangan Bak Kontrol Utama 70 x 70
Tul Ø 10 - 150 mm 25.00
- Pembesian A.4.1.1.17 10.60 kg 15,412.00 163,398.02
- Bekisting A.4.1.1.21 1.30 m2 240,940.00 313,222.00
- Adukan beton ad. 1 PC : 2PS : 3Krl ABK.300.19 0.16 m3 841,400.00 130,417.00
- Pek. Pasangan Manhole (Plat baja) Uk. 60/60 - 1.00 unit 1,200,000.00 1,200,000.00
1.00 1,807,037.02
1 unit = 1,807,037.02

2 Pek. Pasangan Bak Penangkap Lemak/Non Lemak 70 x 70


Tul Ø 10 - 150 mm 25.00
- Pembesian A.4.1.1.17 10.60 kg 15,412.00 163,398.02
- Bekisting A.4.1.1.21 1.30 m2 240,940.00 313,222.00
- Adukan beton ad. 1 PC : 2PS : 3Krl ABK.300.19 0.16 m3 841,400.00 130,417.00
- Pek. Pasangan Manhole (Plat baja) Uk. 60/60 - 1.00 unit 1,200,000.00 1,200,000.00
2.00 1,807,037.02
2 unit = 3,614,074.05
JUMLAH C : 5,421,111.07

D PEMBANGUNAN MCK 27.00


I PEKERJAAN PERSIAPAN
1 Pengukuran & pemasangan bouwplank/profil A.2.2.1.4 31.51 m' 63,435.20 1,998,843.15
1,998,843.15

II PEKERJAAN GALIAN & URUGAN


1 Galian tanah pondasi menerus A.2.3.1.1 41.53 m3 63,000.00 2,616,138.00
2 Urugan pasir dibawah pondasi menerus A.2.3.1.11. 3.08 m3 257,640.00 792,500.64
3,408,638.64
III PEKERJAAN PONDASI
1 Pasangan batu kosong A.3.2.1.9 6.92 m3 558,338.40 3,864,260.07
2 Pasangan batu kali ad. 1PC : 5PS A.3.2.1.3 55.37 m3 876,300.00 48,518,978.40
52,383,238.47

IV PEKERJAAN BETON/PEMBESIAN
1 Sloof 15/25
Tul. Utama 4 Ø 12 mm, Begel Ø 8 - 150 mm
a Pembesian A.4.1.1.17 497.47 kg 15,412.00 7,666,976.82
b Bekisting A.4.1.1.21 9.25 m2 240,940.00 2,228,695.00
c Adukan beton ad. 1PC : 2PS : 3KR ABK.300.19 3.47 m3 841,400.00 2,918,606.25
12,814,278.07
2 Kolom 20/20
Tul. Utama 4 Ø 12 mm, Begel Ø 8 - 150 mm
a Pembesian A.4.1.1.17 309.64 kg 15,412.00 4,772,171.68
b Bekisting A.4.1.1.21 5.70 m2 240,940.00 1,373,358.00
c Adukan beton ad. 1PC : 2PS : 3KR ABK.300.19 2.28 m3 841,400.00 1,918,392.00
8,063,921.68
3 Kolom Praktis 15/15
Tul. Utama 4 Ø 10 mm, Begel Ø 8 - 150 mm
a Pembesian A.4.1.1.17 202.39 kg 15,412.00 3,119,203.86
1 2 3 4 5 6
b Bekisting A.4.1.1.21 3.25 m2 240,940.00 782,814.06
c Adukan beton ad. 1PC : 2PS : 3KR ABK.300.19 2.03 m3 841,400.00 1,703,835.00
5,605,852.92

4 Balok 15/25
Tul. Utama 4 Ø 12 mm, Begel Ø 8 - 150 mm
1 Pembesian A.4.1.1.17 393.57 kg 15,412.00 6,065,731.66
2 Bekisting A.4.1.1.21 4.00 m2 240,940.00 963,470.87
3 Adukan beton ad. 1PC : 2PS : 3KR ABK.300.19 1.50 m3 841,400.00 1,261,721.37
8,290,923.91
5 Balok 15/20
Tul. Utama 4 Ø 10 mm, Begel Ø 8 - 150 mm
1 Pembesian A.4.1.1.17 134.14 kg 15,412.00 2,067,304.03
2 Bekisting A.4.1.1.21 1.10 m2 240,940.00 265,997.76
3 Adukan beton ad. 1PC : 2PS : 3KR ABK.300.19 0.33 m3 841,400.00 278,671.68
2,611,973.47
1 2 3 4 5 6

6 Pekerjaan Atap Dak Beton, T = 12 cm


Tul Ø 8 - 150 mm
a Pembesian A.4.1.1.17 369.14 kg 15,412.00 5,689,108.62
b Bondek - 71.10 m2 99,000.00 7,038,900.00
c Adukan beton ad. 1PC : 2PS : 3KR ABK.300.19 8.53 m3 841,400.00 7,178,824.80
19,906,833.42
57,293,783.46

V PEKERJAAN PASANGAN DINDING BATA


1 Pasangan 1/2 bata ad. 1 PC : 5 PS A.4.4.1.10 204.30 m2 116,270.75 23,753,672.40
2 Plesteran ad. 1 PC : 5 PS A.4.4.2.5 347.09 m2
56,395.10 19,574,310.61
3 Pasangan dinding keramik uk. 25 x 50 cm t. 1,00 m A.4.4.3.54 61.50 m2 213,447.50 13,127,021.25
56,455,004.25

VI PEKERJAAN KUSEN PINTU & JENDELA


Pasangan Pintu
1 Pasangan pintu KM (spandrel) + aksesoris warna silver - 12.00 unit 990,000.00 11,880,000.00
11,880,000.00
Bouvenlee
1 Kusen aluminium 3'' - 34.56 m' 73,600.00 2,543,616.00
2 Pas. Kaca 5 mm A.4.6.2.17 4.80 m2 104,196.00 499,640.66
3,043,256.66
14,923,256.66

VII PEKERJAAN LANTAI


1 Urugan tanah atras padat A.2.3.1.14.a 17.30 m3 173,000.00 2,992,447.10
SNI 03-7395:2008
2 Pasang lantai keramik uk. 40 x 40 cm tekstur 35.88 m2 96,273.75 3,454,302.15
N0.6.9
SNI 03-7395:2008
3 Pasang lantai keramik uk. 25 x 25 cm tekstur 31.20 m2 96,273.75 3,003,741.00
N0.6.9
9,450,490.25

VIII PEKERJAAN BESI/LAIN-LAIN


1 Closet jongkok porselen A.5.1.1 2. 12.00 bh 432,537.50 5,190,450.00
2 Instalasi air bersih/perpipaan berikut kran air - 1.00 ls 1,000,000.00 1,000,000.00
3 Pekerjaan pasangan MCB Box - 1.00 ttk 50,600.00 50,600.00
4 Pek. Pengadaan Kabel 2 x 1,5 mm - 2.00 roll 300,000.00 600,000.00
5 Pek. Pengadaan Kabel 3 x 2,5 mm - 1.00 roll 425,000.00 425,000.00
6 Mangkok + Pipa listrik - 20.00 bh 30,000.00 600,000.00
7 Pasang stop kontak - 2.00 bh 33,600.00 67,200.00
8 Pasang saklar ganda - 5.00 bh 57,200.00 286,000.00
9 Pasang saklar tunggal - 13.00 bh 54,200.00 704,600.00
10 Pasang lampu LED 5 watt + Downlight - 23.00 bh 135,600.00 3,118,800.00
12,042,650.00

IX PEKERJAAN MENGECAT
1 Pengecatan tembok baru (1 lps plamir +1 lps cat dasar + 2 lps A.4.7.1.10. 173.55 m2 25,646.00 4,450,765.85
cat penutup)
JUMLAH D : 212,406,670.73
JUMLAH TOTAL 399,000,260.49

R E K A P I T U LA S I
A PEKERJAAN PEMBUATAN BAK SEPTICTANK KOMUNAL Rp 173,951,806.29
B PENGADAAN DAN PEMASANGAN PIPA PVC Rp 7,220,672.40
C PEMBUATAN BAK KONTROL Rp 5,421,111.07
D PEMBANGUNAN MCK Rp 212,406,670.73
JUMLAH 399,000,260.49
1 2 3 4 5 6

DIBULATKAN Rp 399,000,000.00

Terbilang ( Tiga Ratus Sembilan Puluh Sembilan Juta Rupiah )

Cirebon, 22 April 2018


Diperiksa Oleh : Dibuat Oleh :
Fasilitator Teknik Kelompok Swadaya Masyarakat
Pondok Pesantren Assaidiyyah

MOCH ZULKARNAEN ST
Ketua
HARGA PERKIRAAN SENDIRI (HPS)
RENCANA ANGGARAN BIAYA
DAK SLBM (SANITASI LINGKUNGAN BERBASIS MASYARAKAT)

TAHUN : 2019
PESANTREN : ASSA'IDIYYAH
DESA : ENDER
KECAMATAN : PANGENAN
KABUPATEN : CIREBON

HARGA
JUMLAH
NO JENIS PEKERJAAN ANALISA VOLUME SATUAN
Rp Rp
1 2 3 4 5 6

A PEKERJAAN PEMBUATAN BAK SEPTICTANK KOMUNAL


DIMENSI (6,25 x 2,65 x 2,5)
I PEKERJAAN PERSIAPAN
1 Pengukuran dan pemasangan bouwplank A.2.2.1.4 m2 63,435.20 -
2 Steiger / Alat bantu penahan tanah - ls 2,500,000.00 -
3 Jasa pengukuran beda tinggi dengan alat theodolit - ls -
-
II PEKERJAAN GALIAN/URUGAN
1 Galian tanah A.2.3.1.3 m3 92,040.00 -
2 Pek. Urugan pasir T. 10 cm A.2.3.1.11 m3 257,640.00 -
3 Pek. Rabat beton K. 100 untuk lantai T. 10 cm A.4.1.1.1 m3 #REF! #REF!
#REF!

III PEKERJAAN BETON/PEMBESIAN


1 Pekerjaan Balok Bawah 20/30
Tul 6 Ø 10 mm, Begel Ø 8 - 150 mm
a Pembesian A.4.1.1.17 kg 15,412.00 -
b Bekisting A.4.1.1.21 m2 240,940.00 -
c Adukan beton ad. 1 PC : 2PS : 3Krl ABK.300.19 m3 841,400.00 -
-
2 Pekerjaan Kolom 20/30
Tul 6 Ø 10 mm, Begel Ø 8 - 150 mm
a Pembesian A.4.1.1.17 kg 15,412.00 -
b Bekisting A.4.1.1.21 m2 240,940.00 -
c Adukan beton ad. 1 PC : 2PS : 3Krl ABK.300.19 m3 841,400.00 -
-

3 Pekerjaan Balok Atas 20/30


Tul 6 Ø 10 mm, Begel Ø 8 - 150 mm
a Pembesian A.4.1.1.17 kg 15,412.00 -
b Bekisting A.4.1.1.21 m2 240,940.00 -
c Adukan beton ad. 1 PC : 2PS : 3Krl ABK.300.19 m3 841,400.00 -
-
4 Pekerjaan Dinding T = 20 cm
Tul Ø 10 - 150 mm
a Pembesian A.4.1.1.17 kg 15,412.00 -
b Bekisting A.4.1.1.21 m2 240,940.00 -
c Adukan beton ad. 1 PC : 2PS : 3Krl ABK.300.19 m3 841,400.00 -
-
5 Pekerjaan Tutup Bak Beton T = 15 cm
Tul Ø 10 - 150 mm
a Pembesian A.4.1.1.17 kg 15,412.00 -
b Bekisting A.4.1.1.21 m2 240,940.00 -
c Adukan beton ad. 1 PC : 2PS : 3Krl ABK.300.19 m3 841,400.00 -
-
JUMLAH III : -

IV PEKERJAAN PLESTERAN
1 Acian Tutup Bak Septictang A.4.4.2.27 m2 33,950.00 -
-
1 2 3 4 5 6

V PEKERJAAN LAIN-LAIN
1 Pek. Pengadaan Ipal Komunal Pabrikasi Volume 15 m3 - pkt 130,000,000.00 -
2 Pek. Pengadaan Manhole (Plat baja) Uk. 70/70 - unit 1,500,000.00 -
-

A PEKERJAAN PEMBUATAN BAK SEPTICTANK KOMUNAL


I PEKERJAAN PERSIAPAN -
II PEKERJAAN GALIAN/URUGAN #REF!
III PEKERJAAN BETON/PEMBESIAN -
IV PEKERJAAN PLESTERAN -
V PEKERJAAN LAIN-LAIN -
JUMLAH A : #REF!

B PENGADAAN DAN PEMASANGAN PIPA PVC DAN ACC 13.00


1 Pengadaan Lite Pipa PVC SDR 41 Ø 6 Inchi - m' 119,900.00 -
2 Pengadaan Pipa PVC AW Ø 3 Inchi - m' 69,000.00 -
3 ACC Pipa - unit -
4 Galian tanah keras untuk pemasangan pipa A.2.3.1.4. m3 83,840.00 -
5 Urugan kembali bekas galian pipa A.2.3.1.9. m 3 46,000.00 -
JUMLAH B : -
C PEMBUATAN BAK KONTROL
1 Pek. Pasangan Bak Kontrol Utama 70 x 70
Tul Ø 10 - 150 mm
- Pembesian A.4.1.1.17 kg 15,412.00 -
- Bekisting A.4.1.1.21 m2 240,940.00 -
- Adukan beton ad. 1 PC : 2PS : 3Krl ABK.300.19 m3 841,400.00 -
- Penutup Manhole (Cor Plat) Uk. 60/60 - unit 1,200,000.00 -
2.00 -
2 unit = -

2 Pek. Pasangan Bak Penangkap Lemak 130 x 70


Tul Ø 10 - 150 mm
- Pembesian A.4.1.1.17 kg 15,412.00 -
- Bekisting A.4.1.1.21 m2 240,940.00 -
- Adukan beton ad. 1 PC : 2PS : 3Krl ABK.300.19 m3 841,400.00 -
- Penutup Manhole (Plat Acer t. 2 mm) Uk. 120/60 - unit 360,000.00 -
3.00 -
3 unit = -
JUMLAH C : -

D PEMBANGUNAN MCK
I PEKERJAAN PERSIAPAN
1 Perataan dan pembersihan lahan A.2.2.1.9 m2 14,000.00 -
2 Pengukuran & pemasangan bouwplank/profil A.2.2.1.4 m2 63,435.20 -
-

II PEKERJAAN GALIAN & URUGAN


1 Galian tanah pondasi menerus A.2.3.1.1 m3 63,000.00 -
2 Galian tanah pondasi rollag A.2.3.1.1 m3 63,000.00 -
3 Urugan pasir dibawah pondasi menerus A.2.3.1.11 m3 257,640.00 -
-
III PEKERJAAN PONDASI
1 Pasangan batu kosong A.3.2.1.9 m3 558,338.40 -
2 Pasangan batu kali ad. 1PC : 5PS A.3.2.1.3 m3 876,300.00 -
-

IV PEKERJAAN BETON/PEMBESIAN
1 Sloof 15/20
Tul. Utama 4 Ø 10 mm, Begel Ø 8 - 150 mm
a Pembesian A.4.1.1.17 kg 15,412.00 -
b Bekisting A.4.1.1.21 m2 240,940.00 -
c Adukan beton ad. 1PC : 2PS : 3KR ABK.300.19 m3 841,400.00 -
-
2 Kolom Praktis 15/15
Tul. Utama 4 Ø 12 mm, Begel Ø 8 - 150 mm
a Pembesian A.4.1.1.17 kg 15,412.00 -
1 2 3 4 5 6
b Bekisting A.4.1.1.21 m2 240,940.00 -
c Adukan beton ad. 1PC : 2PS : 3KR ABK.300.19 m3 841,400.00 -
-
1 2 3 4 5 6

3 Kolom 20/20
Tul. Utama 4 Ø 10 mm, Begel Ø 8 - 150 mm
a Pembesian A.4.1.1.17 kg 15,412.00 -
b Bekisting A.4.1.1.21 m2 240,940.00 -
c Adukan beton ad. 1PC : 2PS : 3KR ABK.300.19 m3 841,400.00 -
-
4 Balok 15/25
Tul. Utama 5 Ø 10 mm, Begel Ø 8 - 150 mm
1 Pembesian A.4.1.1.17 kg 15,412.00 -
2 Bekisting A.4.1.1.21 m2 240,940.00 -
3 Adukan beton ad. 1PC : 2PS : 3KR ABK.300.19 m3 841,400.00 -
-
5 Balok Litel 15/15
Tul. Utama 4 Ø 10 mm, Begel Ø 8 - 150 mm
1 Pembesian A.4.1.1.17 kg 15,412.00 -
2 Bekisting A.4.1.1.21 m2 240,940.00 -
3 Adukan beton ad. 1PC : 2PS : 3KR ABK.300.19 m3 841,400.00 -
-
6 Ring Balok 15/20
Tul. Utama 4 Ø 10 mm, Begel Ø 8 - 150 mm
1 Pembesian A.4.1.1.17 kg 15,412.00 -
2 Bekisting A.4.1.1.21 m2 240,940.00 -
3 Adukan beton ad. 1PC : 2PS : 3KR ABK.300.19 m3 841,400.00 -
-
-

V PEKERJAAN PASANGAN DINDING BATA


1 Pasangan 1/2 bata ad. 1 PC : 5 PS A.4.4.1.10 m2 116,270.75 -
2 Plesteran ad. 1 PC : 5 PS A.4.4.2.5 m2 56,395.10 -
3 Acian kolom, balok beton A.4.4.2.27 m 2
33,950.00 -
4 Pasangan dinding keramik uk. 20 x 25 cm t. 1,00 m A.4.4.3.54 m2 213,447.50 -
-

VI PEKERJAAN KUSEN PINTU & JENDELA


Pasangan Pintu P1 (1 BH)
1 Kusen aluminium 3'' warna silver - m' 73,600.00 -
2 Pasangan Aluminium warna silver + aksesoris - unit 1,210,000.00 -
3 Pas. Kaca 5 mm A.4.6.2.17 m2 104,196.00 -
-
Pasangan Pintu P2 (4 BH)
1 Pasangan pintu KM (spandrel) + aksesoris warna silver - unit 990,000.00 -
-
Pasangan (Rolling Door)
1 Pasangan Rolling Door + aksesoris A.4.2.1.10. m2 588,000.00 -
-
Pasangan Jendela J1 (1 BH)
1 Kusen aluminium 3'' warna silver - m' 73,600.00 -
2 Daun jendela aluminium warna silver lengkap aksesoris - bh 715,000.00 -
3 Pas. Kaca 5 mm A.4.6.2.17 m2 104,196.00 -
-
Bouvenli
1 Kusen aluminium 3'' warna silver - m' 73,600.00 -
2 Daun jendela aluminium warna silver lengkap aksesoris - bh 715,000.00 -
3 Pas. Kaca 5 mm A.4.6.2.17 m2 104,196.00 -
-
-
VII PEKERJAAN KUDA-KUDA/ATAP
1 Pasangan rangka atap baja ringan profil Uk. ZINC-Aluminium - m2 165,000.00 -
G.550
2 Pemasangan atap genteng pelentong kecil A.4.5.2.1. m2 44,610.00 -
3 Pasangan nok bubung pelentong kecil A.4.5.2.4 m' 84,040.00 -
4 Pasangan plafond GRC - m2 100,410.00 -

5 List plafond gypsum SNI 2839:2008 N0.6.8 m' 34,155.00 -


1 2 3 4 5 6

6 Pasangan Papan Lisplank woodplank SNI 2839:2008 N0.6.8 m' 49,000.00 -


-

VIII PEKERJAAN LANTAI


1 Urugan tanah atras padat A.2.3.1.14.a m3 173,000.00 -
SNI 03-7395:2008
2 Pasang lantai keramik uk. 40 x 40 cm rata m2
96,273.75 -
N0.6.9
SNI 03-7395:2008
3 Pasang lantai keramik uk. 40 x 40 cm tekstur m2 96,273.75 -
N0.6.9
-
1 2 3 4 5 6

IX PEKERJAAN BESI/LAIN-LAIN
1 Bak mandi vibreglass 0,3 m3 A.5.1.1 10. bh 327,100.00 -
2 Closet jongkok porselen A.5.1.1 2. bh 432,537.50 -
3 Loster jati uk. 20 x 20 cm - bh 25,000.00 -
4 Pek. Sumur Bor - unit 2,000,000.00 -
5 Pek. Tower + Tandon 1000 ltr - unit 5,500,000.00 -
6 Penyediaan pompa + instalasi air bersih/perpipaan berikut kran - unit 1,658,000.00 -
air
7 Pemasangan Listrik 900 watt - ttk 1,500,000.00 -
8 Pekerjaan pasangan MCB Box - ttk 50,600.00 -
9 Pek. Pemasangan titik lampu + stop kontak - ttk 153,440.00 -
10 Pasang stop kontak - bh 33,600.00 -
11 Pasang saklar ganda - bh 57,200.00 -
12 Pasang saklar tunggal - bh 54,200.00 -
13 Pasang lampu LED 5 watt + Downlight - bh 135,600.00 -
-

X PEKERJAAN MENGECAT
1 Pengecatan tembok & plafond (1 lps plamir +1 lps cat dasar + 2 A.4.7.1.10. m2 25,646.00 -
lps cat penutup)
JUMLAH D : -
#REF!

R E K A P I T U LA S I
A PEKERJAAN PEMBUATAN BAK SEPTICTANK KOMUNAL Rp #REF!
B PENGADAAN DAN PEMASANGAN PIPA PVC DAN ACC Rp -
C PEMBUATAN BAK KONTROL Rp -
D PEMBANGUNAN MCK Rp -
JUMLAH #REF!

DIBULATKAN Rp #REF!

Cirebon, 18 April 2018


Diperiksa Oleh : Dibuat Oleh :
Fasilitator Teknik Kelompok Swadaya Masyarakat
Pondok Pesantren Ulumuddin

SANUSI ASYIKIN ST Dra. Hj. MAS'UDAH AL MAHMUDY SPD.I.


Ketua
DAFTAR ANALISA HARGA SATUAN

A.2.2.1 HARGA SATUAN PEKERJAAN PERSIAPAN


A. 2.2.1.4. Pengukuran dan pemasangan 1 m’ Bouwplank
44.50
Harga Satuan (Rp) Jumlah Harga (Rp)
No Uraian Kode Satuan Koefisien
A TENAGA
Pekerja L.01 OH 4.45 0.100 80,000.00 8,000.00
Tukang kayu L.02 OH 4.45 0.100 110,000.00 11,000.00
Kepala tukang L.03 OH 0.445 0.010 120,000.00 1,200.00
Mandor L.04 OH 0.2225 0.005 120,000.00 600.00
JUMLAH TENAGA KERJA 20,800.00
B BAHAN
Kayu kelas III m3 0.534 0.012 3,500,000.00 42,000.00
Paku 2''-3'' Kg 0.89 0.020 20,000.00 400.00
Kayu papan 3/20 m3 0.3115 0.007 33,600.00 235.20
JUMLAH HARGA BAHAN 42,635.20
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 63,435.20


E Overhead & Profit 0.00% -
F Harga Satuan Pekerjaan (D+E) 63,435.20

A.2.3.1 HARGA SATUAN PEKERJAAN TANAH


A.2.3.1.1. Penggalian 1 m3 tanah biasa sedalam 1 m
120.55

No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)

A TENAGA
Pekerja L.01 OH 90.41 0.750 80,000.00 60,000.00
Mandor L.04 OH 3.01 0.025 120,000.00 3,000.00
JUMLAH TENAGA KERJA 63,000.00
B BAHAN

JUMLAH HARGA BAHAN -


C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 63,000.00
E Overhead & Profit 0.00% -
F Harga Satuan Pekerjaan (D+E) 63,000.00

A.2.3.1.9. Pengurugan kembali 1 m3 galian tanah


11.33
Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga

(Rp) (Rp)

A TENAGA

Pekerja L.01 OH 5.6625 0.500 80,000.00 40,000.00

Mandor L.04 OH 0.56625 0.050 120,000.00 6,000.00

JUMLAH TENAGA KERJA 46,000.00


B BAHAN

JUMLAH HARGA BAHAN -


C PERALATAN
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 46,000.00
E Overhead & Profit 0.00% -
F Harga Satuan Pekerjaan (D+E) 46,000.00

A.2.3.1.11. Pengurugan 1 m3 dengan pasir urug


5.12
Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 1.5348 0.300 80,000.00 24,000.00
Mandor L.04 OH 0.05116 0.010 120,000.00 1,200.00
JUMLAH TENAGA KERJA 25,200.00
B BAHAN
Pasir urug 6.1392 1.200 193,700.00 232,440.00
JUMLAH HARGA BAHAN 232,440.00
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 257,640.00
E Overhead & Profit 0.00% -
F Harga Satuan Pekerjaan (D+E) 257,640.00

A.2.3.1.14.a Pengurugan 1 m3 Tanah atras


17.2973821
Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 4.32 0.250 80,000.00 20,000.00
Mandor L.04 OH 0.43 0.025 120,000.00 3,000.00
JUMLAH TENAGA KERJA 23,000.00
B BAHAN
Tanah atras m3 20.76 1.200 125,000.00 150,000.00
JUMLAH HARGA BAHAN 150,000.00
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 173,000.00


E Overhead & Profit 0.00% -
F Harga Satuan Pekerjaan (D+E) 173,000.00

A.3.2.1 HARGA SATUAN PEKERJAAN PONDASI


A.3.2.1.3 Pemasangan 1 m3 pondasi batu belah campuran 1SP : 5PP
55.368
Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 83.052 1.500 80,000.00 120,000.00
Tukang batu L.02 OH 41.526 0.750 110,000.00 82,500.00
Kepala tukang L.03 OH 4.153 0.075 120,000.00 9,000.00
Mandor L.04 OH 4.153 0.075 120,000.00 9,000.00
JUMLAH TENAGA KERJA 220,500.00
B BAHAN
Batu belah m3 66.442 1.200 300,000.00 360,000.00
Semen Portland Kg 7,530.048 136.000 1,400.00 190,400.00
Pasir pasang m3 30.120 0.544 193,750.00 105,400.00
JUMLAH HARGA BAHAN 655,800.00
C PERALATAN
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 876,300.00
E Overhead & Profit 0.00% -
F Harga Satuan Pekerjaan (D+E) 876,300.00

A.3.2.1.9. (K3) Pemasangan 1 m3 batu kosong (anstamping)


6.921
Harga Satuan (Rp) Jumlah Harga (Rp)
No Uraian Kode Satuan Koefisien
A TENAGA
Pekerja L.01 OH 5.398 0.780 80,000.00 62,400.00
Tukang batu L.02 OH 2.699 0.390 110,000.00 42,900.00
Kepala tukang L.03 OH 0.270 0.039 120,000.00 4,680.00
Mandor L.04 OH 0.270 0.039 120,000.00 4,680.00
JUMLAH TENAGA KERJA 114,660.00
B BAHAN
Batu belah m3 8.305 1.200 300,000.00 360,000.00
Pasir urug m3 2.990 0.432 193,700.00 83,678.40
JUMLAH HARGA BAHAN 443,678.40
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 558,338.40


E Overhead & Profit 0.00% -
F Harga Satuan Pekerjaan (D+E) 558,338.40

A.4.1.1 HARGA SATUAN PEKERJAAN BETON


A.4.1.1.17 Pembesian 10 kg dengan besi polos atau besi ulir
2,901.24
Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 20.31 0.070 80,000.00 5,600.00
Tukang besi L.02 OH 20.31 0.070 110,000.00 7,700.00
Kepala tukang L.03 OH 2.03 0.007 120,000.00 840.00
Mandor L.04 OH 1.16 0.004 120,000.00 480.00
JUMLAH TENAGA KERJA 14,620.00
B BAHAN
Besi beton kg 3,046.30 10.500 13,000.00 136,500.00
(polos/ulir)
Kawat beton kg 43.52 0.150 20,000.00 3,000.00
JUMLAH HARGA BAHAN 139,500.00
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 154,120.00


E Overhead & Profit 0.00% -
F Harga Satuan Pekerjaan (D+E) 154,120.00

A.4.1.1.21 (K3) Pemasangan 1 m2 bekisting untuk sloof kolom biasa


41.59
Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 21.63 0.520 80,000.00 41,600.00
Tukang kayu L.02 OH 10.81 0.260 110,000.00 28,600.00
Kepala tukang L.03 OH 1.08 0.026 120,000.00 3,120.00
Mandor L.04 OH 1.08 0.026 120,000.00 3,120.00
JUMLAH TENAGA KERJA 76,440.00
B BAHAN
Kayu kelas III m3 1.87 0.045 3,500,000.00 157,500.00
Paku 5 cm – 10 cm kg 12.48 0.300 20,000.00 6,000.00
Minyak bekisting Liter 4.16 0.100 10,000.00 1,000.00
JUMLAH HARGA BAHAN 164,500.00
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 240,940.00


E Overhead & Profit 0.00% -
F Harga Satuan Pekerjaan (D+E) 240,940.00

A.4.4.1 HARGA SATUAN PEKERJAAN PASANGAN BATA


DAFTAR ANALISA HARGA SATUAN

A.2.2.1 HARGA SATUAN PEKERJAAN PERSIAPAN


A. 2.2.1.4. Pengukuran dan pemasangan 1 m’ Bouwplank

Harga Satuan (Rp) Jumlah Harga (Rp)


No Uraian Kode Satuan Koefisien

A TENAGA
Pekerja L.01 OH 0.100 80,000.00 8,000.00
Tukang kayu L.02 OH 0.100 110,000.00 11,000.00
Kepala tukang L.03 OH 0.010 120,000.00 1,200.00
Mandor L.04 OH 0.005 120,000.00 600.00
JUMLAH TENAGA KERJA 20,800.00
B BAHAN
Kayu balok 5/7 m3 0.012 3,500,000.00 42,000.00
Paku 2''-3'' Kg 0.020 20,000.00 400.00
Kayu papan 3/20 m3 0.007 33,600.00 235.20
JUMLAH HARGA BAHAN 42,635.20
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 63,435.20


E Overhead & Profit 0.00% -
F Harga Satuan Pekerjaan (D+E) 63,435.20

A.2.3.1 HARGA SATUAN PEKERJAAN TANAH


A.2.3.1.1. Penggalian 1 m3 tanah biasa sedalam 1 m

No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)

A TENAGA
Pekerja L.01 OH 0.750 80,000.00 60,000.00
Mandor L.04 OH 0.025 120,000.00 3,000.00
JUMLAH TENAGA KERJA 63,000.00
B BAHAN

JUMLAH HARGA BAHAN -


C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 63,000.00
E Overhead & Profit 0.00% -
F Harga Satuan Pekerjaan (D+E) 63,000.00

A.2.3.1.9. Pengurugan kembali 1 m3 galian tanah

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga

(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.500 80,000.00 40,000.00
Mandor L.04 OH 0.050 120,000.00 6,000.00
JUMLAH TENAGA KERJA 46,000.00
B BAHAN

JUMLAH HARGA BAHAN -


C PERALATAN
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 46,000.00
E Overhead & Profit 0.00% -
F Harga Satuan Pekerjaan (D+E) 46,000.00
A.2.3.1.11. Pengurugan 1 m3 dengan pasir urug

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga

(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.300 80,000.00 24,000.00
Mandor L.04 OH 0.010 120,000.00 1,200.00
JUMLAH TENAGA KERJA 25,200.00
B BAHAN
Pasir urug 1.200 193,700.00 232,440.00
JUMLAH HARGA BAHAN 232,440.00
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 257,640.00
E Overhead & Profit 0.00% -
F Harga Satuan Pekerjaan (D+E) 257,640.00

A.2.3.1.14.a Pengurugan 1 m3 Tanah atras

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga

(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.250 80,000.00 20,000.00
Mandor L.04 OH 0.025 120,000.00 3,000.00
JUMLAH TENAGA KERJA 23,000.00
B BAHAN
Tanah atras m3 1.200 125,000.00 150,000.00
JUMLAH HARGA BAHAN 150,000.00
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 173,000.00


E Overhead & Profit 0.00% -
F Harga Satuan Pekerjaan (D+E) 173,000.00

A.3.2.1 HARGA SATUAN PEKERJAAN PONDASI


A.3.2.1.3 Pemasangan 1 m3 pondasi batu belah campuran 1SP : 5PP

Harga Jumlah
No Uraian Kode Satuan Satuan Harga
Koefisien

(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 1.500 80,000.00 120,000.00
Tukang batu L.02 OH 0.750 110,000.00 82,500.00
Kepala tukang L.03 OH 0.075 120,000.00 9,000.00
Mandor L.04 OH 0.075 120,000.00 9,000.00
JUMLAH TENAGA KERJA 220,500.00
B BAHAN
Batu belah m3 1.200 300,000.00 360,000.00
Semen Portland Kg 136.000 1,400.00 190,400.00
Pasir pasang m3 0.544 193,750.00 105,400.00
JUMLAH HARGA BAHAN 655,800.00
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 876,300.00
E Overhead & Profit 0.00% -
F Harga Satuan Pekerjaan (D+E) 876,300.00
A.3.2.1.9. (K3) Pemasangan 1 m3 batu kosong (anstamping)

Harga Satuan (Rp) Jumlah Harga (Rp)


No Uraian Kode Satuan Koefisien

A TENAGA
Pekerja L.01 OH 0.780 80,000.00 62,400.00
Tukang batu L.02 OH 0.390 110,000.00 42,900.00
Kepala tukang L.03 OH 0.039 120,000.00 4,680.00
Mandor L.04 OH 0.039 120,000.00 4,680.00
JUMLAH TENAGA KERJA 114,660.00
B BAHAN
Batu belah m3 1.200 300,000.00 360,000.00
Pasir urug m3 0.432 193,700.00 83,678.40
JUMLAH HARGA BAHAN 443,678.40
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 558,338.40


E Overhead & Profit 0.00% -
F Harga Satuan Pekerjaan (D+E) 558,338.40

A.4.1.1 HARGA SATUAN PEKERJAAN BETON


A.4.1.1.17 Pembesian 10 kg dengan besi polos atau besi ulir

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga

(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.070 80,000.00 5,600.00
Tukang besi L.02 OH 0.070 110,000.00 7,700.00
Kepala tukang L.03 OH 0.007 120,000.00 840.00
Mandor L.04 OH 0.004 120,000.00 480.00
JUMLAH TENAGA KERJA 14,620.00
B BAHAN
Besi beton kg 10.500 13,000.00 136,500.00
(polos/ulir)
Kawat beton kg 0.150 20,000.00 3,000.00
JUMLAH HARGA BAHAN 139,500.00
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 154,120.00


E Overhead & Profit 0.00% -
F Harga Satuan Pekerjaan (D+E) 154,120.00

A.4.1.1.21 (K3) Pemasangan 1 m2 bekisting untuk sloof

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga

(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.520 80,000.00 41,600.00
Tukang kayu L.02 OH 0.260 110,000.00 28,600.00
Kepala tukang L.03 OH 0.026 120,000.00 3,120.00
Mandor L.04 OH 0.026 120,000.00 3,120.00
JUMLAH TENAGA KERJA 76,440.00
B BAHAN
Kayu kelas III m3 0.045 3,500,000.00 157,500.00
Paku 5 cm – 10 cm kg 0.300 20,000.00 6,000.00
Minyak bekisting Liter 0.100 10,000.00 1,000.00
JUMLAH HARGA BAHAN 164,500.00
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 240,940.00


E Overhead & Profit 0.00% -
F Harga Satuan Pekerjaan (D+E) 240,940.00
A.4.4.1 HARGA SATUAN PEKERJAAN PASANGAN DINDING
A. 4.4.1.10 Pemasangan 1m2 dinding bata merah (5x11x22) cm tebal ½ batu campuran 1SP :5PP

No Uraian Kode Satuan Koefisien Harga Jumlah


Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.300 80,000.00 24,000.00
Tukang batu L.02 OH 0.100 110,000.00 11,000.00
Kepala tukang L.03 OH 0.010 120,000.00 1,200.00
Mandor L.04 OH 0.015 120,000.00 1,800.00
JUMLAH TENAGA KERJA 38,000.00
B BAHAN
Bata merah buah 70.000 800.00 56,000.00
Semen Portland Kg 9.680 1,400.00 13,552.00
Pasir pasang m3 0.045 193,750.00 8,718.75
JUMLAH HARGA BAHAN 78,270.75
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 116,270.75


E Overhead & Profit 0.00% -
F Harga Satuan Pekerjaan (D+E) 116,270.75

A.4.4.2 HARGA SATUAN PEKERJAAN PLESTERAN


A.4.4.2.5. Pemasangan 1 m2 plesteran 1SP : 5PP tebal 15 mm

No Uraian Kode Satuan Koefisien Harga Jumlah


Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.300 80,000.00 24,000.00
Tukang batu L.03 OH 0.150 110,000.00 16,500.00
Kepala tukang L.03 OH 0.015 120,000.00 1,800.00
Mandor L.04 OH 0.015 120,000.00 1,800.00
JUMLAH TENAGA KERJA 44,100.00
B BAHAN
PC Kg 5.184 1,400.00 7,257.60
PP m3 0.026 193,750.00 5,037.50
JUMLAH HARGA BAHAN 12,295.10
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 56,395.10


E Overhead & Profit 0.00% -
F Harga Satuan Pekerjaan (D+E) 56,395.10

A.4.4.2.7. Pemasangan 1 m2 plesteran 1SP : 7PP tebal 15 mm

No Uraian Kode Satuan Koefisien Harga Jumlah


Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.300 80,000.00 24,000.00
Tukang batu L.03 OH 0.150 110,000.00 16,500.00
Kepala tukang L.03 OH 0.015 120,000.00 1,800.00
Mandor L.04 OH 0.015 120,000.00 1,800.00
JUMLAH TENAGA KERJA 44,100.00
B BAHAN
PC Kg 3.936 1,400.00 5,510.40
PP m3 0.028 193,750.00 5,425.00
JUMLAH HARGA BAHAN 10,935.40
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 55,035.40


E Overhead & Profit 0.00% -
F Harga Satuan Pekerjaan (D+E) 55,035.40
A.4.4.2.27. Pemasangan 1 m2 acian

No Uraian Kode Satuan Koefisien Harga Jumlah


Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.200 80,000.00 16,000.00
Tukang batu L.03 OH 0.100 110,000.00 11,000.00
Kepala tukang L.03 OH 0.010 120,000.00 1,200.00
Mandor L.04 OH 0.010 120,000.00 1,200.00
JUMLAH TENAGA KERJA 29,400.00
B BAHAN
Semen PC Kg 3.250 1,400.00 4,550.00
JUMLAH HARGA BAHAN 4,550.00
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 33,950.00


E Overhead & Profit 0.00% -
F Harga Satuan Pekerjaan (D+E) 33,950.00

A.4.4.3 HARGA SATUAN PEKERJAAN PENUTUP LANTAI DAN PENUTUP DINDING


A.4.4.3.54. Pemasangan 1 m2 dinding keramik 20 cm x 20 cm

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.900 80,000.00 72,000.00
Tukang batu L.02 OH 0.450 110,000.00 49,500.00
Kepala tukang L.03 OH 0.045 120,000.00 5,400.00
Mandor L.04 OH 0.045 120,000.00 5,400.00
JUMLAH TENAGA KERJA 132,300.00
B BAHAN
Keramik artistik buah 26.500 2,000.00 53,000.00
Semen Portland Kg 9.300 1,400.00 13,020.00
Pasir pasang M3 0.018 193,750.00 3,487.50
Semen warna Kg 1.940 6,000.00 11,640.00
JUMLAH HARGA BAHAN 81,147.50
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 213,447.50


E Overhead & Profit 0.00% -
F Harga Satuan Pekerjaan (D+E) 213,447.50

A.4.6.2 HARGA SATUAN PEKERJAAN KUNCI DAN KACA


A.4.6.2.17. Pemasangan 1 m2 kaca tebal 5 mm

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.015 80,000.00 1,200.00
Tukang kayu L.02 OH 0.150 110,000.00 16,500.00
Kepala tukang L.03 OH 0.015 120,000.00 1,800.00
Mandor L.04 OH 0.001 120,000.00 96.00
JUMLAH TENAGA KERJA 19,596.00
B BAHAN
Kaca tebal 5 mm m2 1.100 75,000.00 82,500.00
Sealant Kg 0.050 42,000.00 2,100.00
JUMLAH HARGA BAHAN 84,600.00
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 104,196.00


E Overhead & Profit 0.00% -
F Harga Satuan Pekerjaan (D+E) 104,196.00
A.4.7.1 HARGA SATUAN PEKERJAAN PENGECATAN
A.4.7.1.10. Pengecatan 1 m2 tembok baru (1 lapis plamuur, 1 lapis cat dasar, 2 lapis cat penutup)

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.020 80,000.00 1,600.00
Tukang cat L.02 OH 0.063 110,000.00 6,930.00
Kepala tukang L.03 OH 0.006 120,000.00 756.00
Mandor L.04 OH 0.003 120,000.00 360.00
JUMLAH TENAGA KERJA 9,646.00
B BAHAN
Plamuur Kg 0.100 70,000.00 7,000.00
Cat dasar Kg 0.100 25,000.00 2,500.00
Cat penutup Kg 0.260 25,000.00 6,500.00
JUMLAH HARGA BAHAN 16,000.00
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 25,646.00


E Overhead & Profit 0.00% -
F Harga Satuan Pekerjaan (D+E) 25,646.00

A.5.1.1 HARGA SATUAN PEKERJAAN SANITASI DALAM GEDUNG


A.5.1.1 2. Pemasangan 1 buah closet jongkok porselen

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
TENAGA
Pekerja L.01 OH 1.000 80,000.00 80,000.00
Tukang batu L.02 OH 1.500 110,000.00 165,000.00
Kepala tukang L.03 OH 0.150 120,000.00 18,000.00
Mandor L.04 OH 0.160 120,000.00 19,200.00
JUMLAH TENAGA KERJA 282,200.00
B BAHAN
Closet jongkok Unit 1.000 140,000.00 140,000.00
Semen Portland Kg 6.000 1,400.00 8,400.00
Pasir pasang M3 0.010 193,750.00 1,937.50
JUMLAH HARGA BAHAN 150,337.50
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 432,537.50


E Overhead & Profit 0.00% -
F Harga Satuan Pekerjaan (D+E) 432,537.50

TAMBAHAN / LAIN-LAIN
SNI 03-7395:2008 N0.6.9 Memasang 1 m2 lantai keramik ukuran 40 x 40

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pembantu tukang oh 0.250 80,000.00 20,000.00
Tukang batu oh 0.120 110,000.00 13,200.00
Kepala tukang oh 0.012 120,000.00 1,440.00
Mandor oh 0.013 120,000.00 1,560.00
JUMLAH TENAGA KERJA 36,200.00
B BAHAN
keramik 40 x 40 bh 6.630 4,500.00 29,835.00
portland cement kg 9.800 1,400.00 13,720.00
pasir pasang m3 0.045 193,750.00 8,718.75
semen warna kg 1.300 6,000.00 7,800.00
JUMLAH HARGA BAHAN 60,073.75
C PERALATAN -
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 96,273.75


E Overhead & Profit 0.00% -
F Harga Satuan Pekerjaan (D+E) 96,273.75
ABK.300.19 1 m3 Beton Bertulang AD. 1:2:3

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A BAHAN
Semen portland kg 232 1,400.00 324,800.00
Pasir beton m3 0.52 212,500.00 110,500.00
Spleet 2/3 cm m3 0.78 300,000.00 234,000.00
JUMLAH HARGA BAHAN 669,300.00
B TENAGA
Pekerja Oh 1.65 80,000.00 132,000.00
Tukang batu Oh 0.25 110,000.00 27,500.00
Kepala tukang Oh 0.025 120,000.00 3,000.00
Mandor Oh 0.08 120,000.00 9,600.00
JUMLAH TENAGA KERJA 172,100.00
C PERALATAN
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 841,400.00


E Overhead & Profit 0.00% -
F Harga Satuan Pekerjaan (D+E) 841,400.00

- 1 Bh Pekerjaan Stop Kontak

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
BAHAN
Stop Kontak bh 1.000 13,000.00 13,000.00
JUMLAH HARGA BAHAN 13,000.00
TENAGA
Pembantu tukang Listrik Oh 0.2 80,000.00 16,000.00
Tukang Listrik Oh 0.02 110,000.00 2,200.00
Kepala tukang Listrik Oh 0.02 120,000.00 2,400.00
JUMLAH TENAGA KERJA 20,600.00
C PERALATAN
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 33,600.00


E Overhead & Profit 0.00% -
F Harga Satuan Pekerjaan (D+E) 33,600.00

- 1 Bh Pekerjaan Lampu led 5 Watt + Downlight

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
BAHAN
Lampu led 5 Watt + Downlight bh 1.000 115,000.00 115,000.00
JUMLAH HARGA BAHAN 115,000.00
TENAGA
Pembantu tukang Listrik Oh 0.2 80,000.00 16,000.00
Tukang Listrik Oh 0.02 110,000.00 2,200.00
Kepala tukang Listrik 0 0.02 120,000.00 2,400.00
JUMLAH TENAGA KERJA 20,600.00
C PERALATAN
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 135,600.00


E Overhead & Profit 0.00% -
F Harga Satuan Pekerjaan (D+E) 135,600.00
- 1 Bh Pekerjaan MCB Box

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
BAHAN
MCB BOX bh 1.000 30,000.00 30,000.00
JUMLAH HARGA BAHAN 30,000.00
TENAGA
Pembantu tukang Listrik Oh 0.2 80,000.00 16,000.00
Tukang Listrik Oh 0.02 110,000.00 2,200.00
Kepala tukang Listrik Oh 0.02 120,000.00 2,400.00
JUMLAH TENAGA KERJA 20,600.00
C PERALATAN
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 50,600.00


E Overhead & Profit 0.00% -
F Harga Satuan Pekerjaan (D+E) 50,600.00

- 1 Bh Pekerjaan Saklar Ganda

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
BAHAN
Saklar Ganda bh 1.000 16,000.00 16,000.00
JUMLAH HARGA BAHAN 16,000.00
TENAGA
Pembantu tukang Listrik Oh 0.4 80,000.00 32,000.00
Tukang Listrik Oh 0.04 110,000.00 4,400.00
Kepala tukang Listrik Oh 0.04 120,000.00 4,800.00
JUMLAH TENAGA KERJA 41,200.00
C PERALATAN
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 57,200.00


E Overhead & Profit 0.00% -
F Harga Satuan Pekerjaan (D+E) 57,200.00

- 1 Bh Pekerjaan Saklar Tunggal

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
BAHAN
Saklar tunggal bh 1.000 13,000.00 13,000.00
JUMLAH HARGA BAHAN 13,000.00
TENAGA
Pembantu tukang Listrik Oh 0.4 80,000.00 32,000.00
Tukang Listrik Oh 0.04 110,000.00 4,400.00
Kepala tukang Listrik Oh 0.04 120,000.00 4,800.00
JUMLAH TENAGA KERJA 41,200.00
C PERALATAN
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 54,200.00
E Overhead & Profit 0.00% -
F Harga Satuan Pekerjaan (D+E) 54,200.00
DAFTAR HARGA SATUAN BAHAN, UPAH DAN ALAT
DAK SLBM (SANITASI LINGKUNGAN BERBASIS MASYARAKAT)

HARGA
NO URAIAN BAHAN/UPAH/ALAT KODE SAT. SATUAN KET.
Rp
A. UPAH
1 Pekerja 559.07 /hari 80,000.00 44,725,512.20
2 Tukang 228.80 /hari 110,000.00 25,168,375.94
3 Kepala tukang 24.00 /hari 120,000.00 2,879,561.01
4 Mandor 28.07 /hari 120,000.00 3,367,897.55
B. BAHAN :
1 Kayu Kelas III 2.40 m3 3,500,000.00 8,402,523.50
2 Paku 2''-3'' 13.37 kg 20,000.00 267,362.80
3 Kayu papan 3/20 0.31 m3 33,600.00 10,466.40
4 Atras ( tanah urug ) 20.76 m3 125,000.00 2,594,607.32
5 Batu belah 10/15 cm 74.75 m3 300,000.00 22,424,040.00
6 Batu pecah mesin 2-3 cm 25.12 m3 300,000.00 7,535,151.00
7 Pasir beton 16.74 m3 212,500.00 3,558,265.75
8 Pasir pasang 52.58 m3 193,750.00 10,188,057.66
9 Pasir urug 9.13 m3 193,700.00 1,768,301.25
10 Besi beton 3,046.30 kg 13,000.00 39,601,953.30
11 Kawat beton / Kawat tali 43.52 kg 20,000.00 870,372.60
12 Plamir tembok 17.35 kg 44,000.00 763,603.28
13 Cat tembok Vinilex 62.48 kg 25,000.00 1,561,915.80
14 Closet jongkok porselen merk INA/KIA 12.00 bh 140,000.00 1,680,000.00
15 Semen Portland 20,138.97 kg 1,400.00 28,194,563.90
16 Minyak bekisting 4.16 ltr 10,000.00 41,593.80
17 Bata merah 14,300.73 bh 800.00 11,440,587.20
18 Keramik dinding 25/50 584.25 bh 5,578.95 3,259,500.00
19 Semen warna 206.51 kg 6,000.00 1,239,084.00
20 Kaca tebal 5 mm 5.27 m2 75,000.00 395,604.00
21 Sealant 0.24 kg 42,000.00 10,069.92
22 Keramik 40 x 40 444.74 bh 4,500.00 2,001,331.80
23 Stop Kontak 2.00 bh 13,000.00 26,000.00
24 Saklar ganda 5.00 bh 16,000.00 80,000.00
25 Saklar tunggal 13.00 bh 13,000.00 169,000.00
26 Lampu LED 5 watt + Downlight 23.00 bh 135,600.00 3,118,800.00
27 MCB BOX 1.00 bh 30,000.00 30,000.00
28 Pek. Pengadaan Kabel 2 x 1,5 mm 2.00 roll 300,000.00 600,000.00
29 Pek. Pengadaan Kabel 3 x 2,5 mm 1.00 roll 425,000.00 425,000.00
30 Mangkok + Pipa listrik 20.00 bh 30,000.00 600,000.00
31 Instalasi air bersih/perpipaan berikut kran air 1.00 ls 1,000,000.00 1,000,000.00
32 Kusen aluminium 3'' 34.56 m' 73,600.00 2,543,616.00
33 Pasangan pintu KM (spandrel) + aksesoris warna silver 12.00 unit 990,000.00 11,880,000.00
34 Bondek 71.10 m2 99,000.00 7,038,900.00
35 Manhole (Plat baja) Uk. 60/60 3.00 unit 1,200,000.00 3,600,000.00
36 Pengadaan Pipa PVC AW Ø 6 Inchi 15.00 m' 119,900.00 1,798,500.00
37 Pengadaan Pipa PVC AW Ø 3 Inchi 60.00 m' 69,000.00 4,140,000.00
38 Pek. Pengadaan Ipal Komunal Pabrikasi Volume 20 m3 1.00 unit 130,000,000.00 130,000,000.00
39 Pek. Pasangan Manhole (Plat baja) Uk. 70/70 4.00 unit 1,500,000.00 6,000,000.00
40 Tembok penahan penahan tanah sementara 1.00 ls 2,000,000.00 2,000,000.00
JUMLAH 399,000,117.97
DIBULATKAN 399,000,000.00

Sumber, 2019
DAFTAR SATUAN ANALISA

HARGA SATUAN
NO KODE ANALISA SATUAN PEKERJAAN KET
Rp

A.2.2.1 HARGA SATUAN PEKERJAAN PERSIAPAN


1 A. 2.2.1.4. Pengukuran dan pemasangan 1 m’ Bouwplank 63,435.20 63,435.20
A.2.3.1 HARGA SATUAN PEKERJAAN TANAH
1 A.2.3.1.1. Penggalian 1 m3 tanah biasa sedalam 1 m 63,000.00 63,000.00
2 A.2.3.1.9. Pengurugan kembali 1 m3 galian tanah 46,000.00 46,000.00
3 A.2.3.1.11. Pengurugan 1 m3 dengan pasir urug 257,640.00 257,640.00
A.2.3.1.14.a Pengurugan 1 m3 Tanah atras 173,000.00 173,000.00
A.3.2.1 HARGA SATUAN PEKERJAAN PONDASI
1 A.3.2.1.3 Pemasangan 1 m3 pondasi batu belah campuran 1SP : 5PP 876,300.00 876,300.00
2 A.3.2.1.9. (K3) Pemasangan 1 m3 batu kosong (anstamping) 558,338.40 558,338.40
A.4.1.1 HARGA SATUAN PEKERJAAN BETON
1 A.4.1.1.17 Pembesian 10 kg dengan besi polos atau besi ulir 154,120.00 154,120.00
2 A.4.1.1.21 (K3) Pemasangan 1 m2 bekisting untuk sloof 240,940.00 240,940.00
A.4.4.1 HARGA SATUAN PEKERJAAN PASANGAN DINDING
1 A. 4.4.1.10 Pemasangan 1m2 dinding bata merah (5x11x22) cm tebal ½ batu campuran 1SP :5PP 116,270.75 116,270.75
A.4.4.2 HARGA SATUAN PEKERJAAN PLESTERAN
1 A.4.4.2.5. Pemasangan 1 m2 plesteran 1SP : 5PP tebal 15 mm 56,395.10 56,395.10
2 A.4.4.2.27. Pemasangan 1 m2 acian 33,950.00 33,950.00
A.4.4.3 HARGA SATUAN PEKERJAAN PENUTUP LANTAI DAN PENUTUP DINDING
1 A.4.4.3.54. Pemasangan 1 m2 dinding keramik 20 cm x 20 cm 213,447.50 213,447.50
A.4.6.2 HARGA SATUAN PEKERJAAN KUNCI DAN KACA
1 A.4.6.2.17. Pemasangan 1 m2 kaca tebal 5 mm 104,196.00 104,196.00
A.4.7.1 HARGA SATUAN PEKERJAAN PENGECATAN
1 A.4.7.1.10. Pengecatan 1 m2 tembok baru (1 lapis plamuur, 1 lapis cat dasar, 2 lapis cat penutup) 25,646.00 25,646.00
2 A.5.1.1 2. Pemasangan 1 buah closet jongkok porselen 432,537.50 432,537.50
- TAMBAHAN / LAIN-LAIN
1 SNI 03-7395:2008 N0.6.9 Memasang 1 m2 lantai keramik ukuran 40 x 40 96,273.75 96,273.75 2 granit 60 x 60
2 ABK.300.19 1 m3 Beton Bertulang AD. 1:2:3 841,400.00 841,400.00
3 - 1 Bh Pekerjaan Stop Kontak 33,600.00 33,600.00
4 - 1 Bh Pekerjaan Lampu led 5 Watt + Downlight 135,600.00 135,600.00
5 - 1 Bh Pekerjaan MCB Box 50,600.00 50,600.00
6 - 1 Bh Pekerjaan Saklar Ganda 57,200.00 57,200.00 Kepala
7 - 1 Bh Pekerjaan Saklar Tunggal 54,200.00 54,200.00 Dinas
Perumahan
, Kawasan
Permukima
nSumber,
Dan
Sumber, 2019
Pertanahan
Kabupaten
Cirebon
HARGA SATUAN
NO KODE ANALISA SATUAN PEKERJAAN KET
Rp

H. SUKMA NUG
NIP. 19610301 19
Sumber, 2017
H. SUKMA NUGRAHA, SH.,MM.
NIP. 19610301 198603 1 012
RENCANA PENGGUNAAN DANA TERMIN I
DAK SLBM (SANITASI LINGKUNGAN BERBASIS MASYARAKAT) TAHUN 2019
DESA ENDER KECAMATAN PANGENAN

VOLUME
Unit/Satu
NO URAIAN KEBUTUHAN Real s/d Tahap Pengajuan jumlah Harga Satuan Jumlah
an
Lalu sekarang Komulatif
1 2 3 5 6 7 8 9 10

A. BAHAN :
1 Semen 20,138.97 2,400.00 2,400.00 kg 1,400.00 3,360,000.00
2 Batu belah 10/15 cm 74.75 22.43 22.43 m3 300,000.00 6,729,000.00
3 Batu pecah mesin 2-3 cm 25.12 4.80 4.80 m3 300,000.00 1,440,000.00
4 Pasir beton 16.74 4.80 4.80 m3 212,500.00 1,020,000.00
5 Pasir pasang 52.58 4.80 4.80 m3 193,750.00 930,000.00
6 Pasir urug 9.13 2.74 2.74 m3 193,700.00 530,738.00
7 Besi beton 3,046.30 890.00 890.00 kg 13,000.00 11,570,000.00
8 Kawat beton / Kawat tali 43.52 13.06 13.06 kg 20,000.00 261,200.00
9 Bata merah 14,300.73 2,100.00 2,100.00 bh 800.00 1,680,000.00
10 Kayu kelas III/Bekisting' 2.40 0.14 0.14 m3 3,500,000.00 490,000.00
-
B. UPAH -
1 Mandor 28.07 0.60 0.60 /hari 120,000.00 72,000.00
2 Kepala tukang 24.00 0.60 0.60 /hari 120,000.00 72,000.00
3 Tukang 228.80 14.40 14.40 /hari 110,000.00 1,584,000.00
4 Pekerja 559.07 21.60 21.60 /hari 80,000.00 1,728,000.00

C. PELATIHAN DAN BOP KPM


1 Pelatihan 1.00 - - pkt - -
2 BOP KPM 1.00 - - pkt - -
TOTAL PENGAJUAN 31,466,938.00
DIBULATKAN 31,500,000.00

Sumber, 2019
Mengetahui Diperiksa Oleh Dibuat Oleh
Pejabat Pembuat Komitmen Fasilitator Teknik Kelompok Swadaya Masyarakat
Pondok Pesantren Assaidiyyah
ASEP DJAMALUDIN MALIK, ST. MOCH ZULKARNAEN ST H. RUDIN, SE. M,Si
NIP : 19680607 199703 1 005
DAFTAR HARGA SATUAN BAHAN, UPAH DAN ALAT

HARGA SATUAN
NO URAIAN BAHAN/UPAH/ALAT KODE SAT. KET.
Rp

A. BAHAN :
I. BATU
1 Atras ( tanah urug ) m3 125,000.00
2 Batu belah 10/15 cm m3 300,000.00
3 Batu pecah mesin 2-3 cm m3 300,000.00

II. PASIR
1 Pasir beton m3 212,500.00
2 Pasir pasang m3 193,750.00
3 Pasir urug m3 193,700.00

III. BESI / PIPA / KAWAT


1 Besi beton kg 13,000.00
2 Kawat beton / Kawat tali kg 20,000.00
3 Bak mandi fiber 120 L bh 220,000.00
4 Cat Menie kg 44,000.00
5 Cat penutup tembok Vinilex kg 25,000.00
6 Closet jongkok porselen merk INA/KIA bh 140,000.00
7 Dempul kayu kg 18,500.00
8 Dinding keramik uk. 20 x 20 cm bh 2,000.00
9 Jendela Alumunium + Kaca (uk.120 cm x 60 cm) warna silver unit 715,000.00
10 Pintu Allumunium + Kaca (uk.210 cm x 90 cm) warna silver unit 1,210,000.00
11 Pintu Kamar Mandi (Spandrel) uk. 200 cm x 70 cm warna silver unit 990,000.00
12 Loster Jati bh 25,000.00
13 GRC tebal 4 mm lbr 68,000.00
14 Kaca polos tebal 5 mm m2 75,000.00
15 Kusen Alumunium 3" warna natural/silver + accessories (terpasang) m' 73,600.00
16 Lantai keramik uk. 40 x 40 cm ( putih polos ) bh 4,500.00
17 List keliling gypsum lebar 12 cm m' 18,000.00
18 Paku biasa 2" - 5" kg 20,000.00
19 Plamir tembok kg 70,000.00
20 Joint Sealent kg 42,000.00
21 Semen portland kg 1,400.00
22 Semen warna kg 6,000.00
23 Woodplank corak 4 m lbr 60,000.00
24 Pasangan pintu KM (spandrel) + aksesoris warna silver unit
25 Lite Pipa PVC SDR 41 Ø 6 Inchi m'
26 Pipa PVC AW Ø 3 Inchi m'
27 Ipal Komunal Pabrikasi Volume 15 m3 unit
28 Manhole (Plat baja) Uk. 70/70 unit
29 Manhole (Cor Plat) Uk. 60/60 unit
30 Manhole (Plat Acer t. 2 mm) Uk. 120/60 unit
31 ACC Pipa ls
Rangka atap baja ringan
HARGA SATUAN
NO URAIAN BAHAN/UPAH/ALAT KODE SAT. KET.
Rp

a. Atap Baja Ringan memakai Genteng Keramik/Plentong


( jarak reng 22-28 cm)
1 - Atap Baja Ringan Pelana Bentang < 9 m Zinc-Alumunium G.550 m2 165,000.00

IV. MINYAK
1 Pelumas bekisting liter 10,000.00

V. CETAKAN
1 Bata merah bh 800.00
2 Genteng nok/bubung press tangan ex Jatiwangi bh 2,000.00
3 Kayu hutan/kayu perancah acuan (kayu kelas III) m3 3,500,000.00
VI. LAIN-LAIN
1 Air L 50.00
2 Rolling door alluminium m2 400,000.00
3 genteng palentong kecil bh 900.00
4 Saklar tunggal bh 13,000.00
5 Saklar ganda bh 16,000.00
6 MCB bh 30,000.00
8 Stop kontak broco standard bh 13,000.00
9 Holo 4/4 meni btg 12,100.00
10 Holo 2/4 meni btg 11,000.00
11 Kawat Bwg 12 kg 10,000.00
12 Paku screw 2.5 cm bh 50.00
13 Adhesive kg 6,000.00
14 Kain kasa m' 400.00
15 Cat penutup 2 kali kg -
16 Paku beton bh 175.00
17 Kabel Listrik NYA 3 x 2,5 mm m' 6,500.00
18 Steiger / Alat bantu penahan tanah 1.00 ls 29,500.00
19 Jasa pengukuran beda tinggi dengan alat theodolit 1.00 ls -

B. UPAH
1 Mandor /hari 120,000.00
2 Kepala tukang /hari 120,000.00
3 Tukang kayu / besi /hari 110,000.00
4 Tukang batu /hari 110,000.00
5 Pembantu tukang/Pekerja /hari 80,000.00

Sumber, 2019
DAFTAR SATUAN ANALISA
DINAS PERUMAHAN KAWASAN PERMUKIMAN DAN PERTANAHAN
KABUPATEN CIREBON
TAHUN ANGGARAN 2017

HARGA SATUAN
NO KODE ANALISA SATUAN PEKERJAAN
Rp

1 A.3.2.1.3 Pemasangan 1 m3 pondasi batu belah campuran 1SP : 5PP 876,300.00


2 #REF! #REF! #REF!
3 #REF! #REF! #REF!
4 #REF! #REF! #REF!
5 #REF! #REF! #REF!
6 #REF! #REF! #REF!
7 #REF! #REF! #REF!
8 #REF! #REF! #REF!
9 #REF! #REF! #REF!
#REF! #REF!
426 #REF! #REF! #REF!
427 #REF! #REF! #REF!
- TAMBAHAN / LAIN-LAIN
428 #REF! #REF! #REF!
429 #REF! #REF! #REF!
430 SNI 03-7395:2008 N0.6.9
Memasang 1 m2 lantai keramik ukuran 40 x 40 96,273.75
431 #REF! #REF! #REF!
432 SNI 2839:2008 N0.6.8Memasang 1 m' List Plafond Gypsum Profil 34,155.00
433 SNI 2839:2008 N0.6.81 m' Pasang Listplank Woodplank 49,000.00
434 #REF! #REF! #REF!
435 #REF! #REF! #REF!
436 #REF! #REF! #REF!
437 #REF! #REF! #REF!
438 #REF! #REF! #REF!
439 #REF! #REF! #REF!
440 ABK.300.19 1 m3 Beton Bertulang AD. 1:2:3 841,400.00
441 - 1m2 Pasang Plafond Rangka Holo dan Dengan Penutup GRC Berikut Pengecatan 100,410.00
442 - 1 Titik Pekerjaan Instalasi Lampu dan Stop Kontak 153,440.00
443 - 1 Bh Pekerjaan Stop Kontak 33,600.00
444 - 1 Bh Pekerjaan Lampu led 5 Watt + Downlight 135,600.00
445 - #REF! 50,600.00
446 - 1 Bh Pekerjaan MCB Box 50,600.00
447 - #REF! #REF!
448 - 1 Bh Pekerjaan Saklar Ganda 57,200.00
449 - 1 Bh Pekerjaan Saklar Tunggal 54,200.00
JALAN LINGKUNGAN
450 Analisa EI-311a #REF! #REF!
451 Analisa EI-321.rob #REF! #REF!
452 Analisa EI-322.rob #REF! #REF!
453 Analisa EI-331.rob #REF! #REF!
454 Analisa EI-611a #REF! #REF!
455 Analisa EI-612a #REF! #REF!
456 Analisa EI-621 #REF! #REF!
457 Analisa EI-631.rob #REF! #REF!
458 Analisa EI-632.rob #REF! #REF!
459 Analisa EI-661 #REF! #REF!
460 Analisa EI-662 #REF! #REF!
461 Analisa EI-814 #REF! #REF!
462 Analisa EI-817 #REF! #REF!

Sumber, 2017

Kepala Dinas Perumahan, Kawasan Permukiman Dan Pertanahan Kabupaten Cirebon


HARGA SATUAN
NO KODE ANALISA SATUAN PEKERJAAN
Rp

H. SUKMA NUGRAHA, SH.,MM.


NIP. 19610301 198603 1 012

Anda mungkin juga menyukai