A.

PEKERJAAN PERSIAPAN

1 m2 Pagar Sementara Kayu (T=2M) (RSNI: T-12-2002-6.1)


1 Dolken dia 5 s/d 7 cm p. 4 m 1.250 btg 13,144 16,430
2 Semen PC (50 Kg) 0.110 zak 63,500 6,985
3 Pasir Beton 0.005 m3 145,000 725
4 Batu Split Pecah Mesin 2/3 0.009 m3 145,000 1,305
5 Kaso kelas III 0.072 m3 2,387,000 171,864
6 Paku 4 s/d 7 cm 0.060 kg 36,000 2,160
7 Minyak Pelumas 0.400 Ltr 35,000 14,000
a Tukang Kayu Halus 0.200 Org/Hari 80,000 16,000
b Pekerja 0.400 Org/Hari 60,000 24,000
c Kepala Tukang 0.020 Org/Hari 80,000 1,600
d Mandor 0.020 Org/Hari 95,000 1,900
JUMLAH 256,969

1 m2 Pagar Sementara Seng Gelombang (T=2M) (RSNI: T-12-2002-6.2)


1 Dolken dia 5 s/d 7 cm p. 4 m 1.250 btg 13,144 16,430
2 Semen PC (50 Kg) 2.500 zak 63,500 158,750
3 Seng Gelombang BJLS 0,3 1.200 lbr 100,100 120,120
4 Pasir Beton 0.005 m3 145,000 725
5 Batu Split Pecah Mesin 2/3 0.009 m3 145,000 1,305
6 Kaso kelas III 0.072 m3 2,387,000 171,864
7 Paku 1 s/d 3 cm 0.060 kg 20,020 1,201
8 Cat Dasar / meni besi 0.450 Kg 28,336 12,751
a Tukang Kayu Halus 0.200 Org/Hari 80,000 16,000
b Pekerja 0.400 Org/Hari 60,000 24,000
c Kepala Tukang 0.020 Org/Hari 80,000 1,600
d Mandor 0.020 Org/Hari 95,000 1,900
JUMLAH 526,646

1 m2 Pagar Sementara Kawat Duri (T=1,8M) (RSNI: T-12-2002-6.3)


1 Dolken dia 5 s/d 7 cm p. 4 m 1.250 btg 13,144 16,430
2 Semen PC (50 Kg) 2.000 zak 63,500 127,000
3 Kawat Duri 1.200 m2 27,500 33,000
4 Pasir Beton 0.005 m3 145,000 725
5 Batu Split Pecah Mesin 2/3 0.009 m3 145,000 1,305
6 Paku 4 s/d 7 cm 0.060 kg 36,000 2,160
a Tukang Kayu Halus 0.200 Org/Hari 80,000 16,000
b Pekerja 0.300 Org/Hari 60,000 18,000
c Kepala Tukang 0.020 Org/Hari 80,000 1,600
d Mandor 0.020 Org/Hari 95,000 1,900
JUMLAH 218,120

1 m1 Pengukuran & Pemasangan Bowplank (RSNI: T-12-2002-6.4)


1 Kaso kelas III 0.012 m3 2,387,000 28,644
2 Paku 4 s/d 7 cm 0.020 kg 36,000 720
3 Balok kelas III 0.007 m3 2,387,000 16,709
a Tukang Kayu Kasar 0.100 Org/Hari 80,000 8,000
b Pekerja 0.100 Org/Hari 60,000 6,000
c Kepala Tukang 0.010 Org/Hari 80,000 800
d Mandor 0.005 Org/Hari 95,000 475
JUMLAH 61,348
1 m2 Pembuatan Kantor Proyek Sementara (RSNI: T-12-2002-6.5)
1 Dolken dia 5 s/d 7 cm p. 4 m 1.250 btg 13,144 16,430
2 Kayu Kuat klas III 0.180 m3 2,335,667 420,420
3 Paku 8 s/d 12 cm 0.850 kg 36,000 30,600
4 Besi Plat rata2 1 s/d 5 mm 1.100 Kg 19,717 21,689
5 Semen PC (50 Kg) 0.700 zak 63,500 44,450
6 Pasir Pasang 0.150 m3 135,000 20,250
7 Pasir Beton 0.100 m3 145,000 14,500
8 Batu Split Pecah Mesin 2/3 0.150 m3 145,000 21,750
9 Bata Merah 30.000 bh 600 18,000
10 Seng Plat BJLS 0,30 0.250 m' 84,700 21,175
11 Kaca nako polos 5 mm 0.200 daun 215,000 43,000
12 Kaca Polos 5 mm 0.080 m2 95,000 7,600
13 Triplex t. 4 mm 0.150 lbr 54,000 8,100
14 Handel + Kunci bulat 0.060 bh 125,000 7,500
a Tukang Kayu Kasar 2.000 Org/Hari 80,000 160,000
b Pekerja 1.000 Org/Hari 60,000 60,000
c Kepala Tukang 0.300 Org/Hari 80,000 24,000
d Mandor 0.050 Org/Hari 95,000 4,750
JUMLAH 944,214

1 m2 Pembuatan Gudang Poyek


1 Dolken dia 5 s/d 7 cm p. 4 m 1.700 btg 13,144 22,345
2 Kayu Kuat klas III 0.210 m3 2,335,667 490,490
3 Paku 8 s/d 12 cm 0.300 kg 36,000 10,800
4 Semen PC (50 Kg) 0.210 zak 63,500 13,335
5 Pasir Pasang 0.030 m3 135,000 4,050
6 Pasir Beton 0.050 m3 145,000 7,250
7 Seng Gelombang BJLS 0,3 1.500 lbr 100,100 150,150
a Tukang Kayu Kasar 2.000 Org/Hari 80,000 160,000
b Pekerja 1.000 Org/Hari 60,000 60,000
c Kepala Tukang 0.200 Org/Hari 80,000 16,000
d Mandor 0.050 Org/Hari 95,000 4,750
JUMLAH 939,170

1 m2 Pembuatan Rumah Jaga Sementara Konstruksi Kayu


1 Dolken dia 5 s/d 7 cm p. 4 m 3.000 btg 13,144 39,432
2 Kayu Kuat klas III 0.276 m3 2,335,667 644,644
3 Paku 8 s/d 12 cm 0.700 kg 36,000 25,200
4 Seng Gelombang BJLS 0,3 1.500 lbr 100,100 150,150
a Tukang Kayu Kasar 1.500 Org/Hari 80,000 120,000
b Pekerja 1.000 Org/Hari 60,000 60,000
c Kepala Tukang 0.150 Org/Hari 80,000 12,000
d Mandor 0.050 Org/Hari 95,000 4,750
JUMLAH 1,056,176

1 m2 Membersihkan Lokasi Proyek


a Pekerja 0.100 Org/Hari 60,000 6,000
b Mandor 0.005 Org/Hari 95,000 475
JUMLAH 6,475
1 m2 Pembuatan Bedeng Buruh
1 Dolken dia 5 s/d 7 cm p. 4 m 1.250 btg 13,144 16,430
2 Kayu Kuat klas III 0.186 m3 2,335,667 434,434
3 Paku 8 s/d 12 cm 0.300 kg 36,000 10,800
4 Semen PC (50 Kg) 0.360 zak 63,500 22,860
5 Pasir Beton 0.030 m3 145,000 4,350
6 Batu Split Pecah Mesin 2/3 0.050 m3 145,000 7,250
7 Seng Gelombang BJLS 0,3 1.500 lbr 100,100 150,150
8 Triplex t. 4 mm 1.500 lbr 54,000 81,000
a Tukang Kayu Kasar 2.000 Org/Hari 80,000 160,000
b Pekerja 1.000 Org/Hari 60,000 60,000
c Kepala Tukang 0.200 Org/Hari 80,000 16,000
d Mandor 0.050 Org/Hari 95,000 4,750
JUMLAH 968,024

1 m2 Pembuatan Bak Adukan


1 Kaso kelas III 0.036 m3 2,387,000 85,932
2 Paku 4 s/d 7 cm 0.080 kg 36,000 2,880
3 Balok kelas III 0.014 m3 2,387,000 33,418
a Tukang Kayu Kasar 0.300 Org/Hari 80,000 24,000
JUMLAH 146,230

1 m2 Pembuatan Stegger
1 Kaso kelas III 0.028 m3 2,387,000 66,836
2 Paku 4 s/d 7 cm 0.125 kg 36,000 4,500
a Tukang Kayu Kasar 0.250 Org/Hari 80,000 20,000
b Pekerja 0.002 Org/Hari 60,000 120
c Kepala Tukang 0.013 Org/Hari 80,000 1,040
d Mandor 0.017 Org/Hari 95,000 1,615
JUMLAH 94,111

1 m2 Membersihkan Puing-puing/ Membersihkan tanaman, stripping/ Mecabut pohon


a Pekerja 0.050 Org/Hari 60,000 3,000
b Mandor 0.005 Org/Hari 95,000 475
JUMLAH 3,475

1 m2 Pembuatan Jalan Masuk Proyek Sementara


1 Batu Belah Pondasi 0.150 m3 228,571 34,286
2 Batu Split Pecah Mesin 5/7 0.090 m3 145,000 13,050
3 Pasir Pasang 1.010 m3 135,000 136,350
a Pekerja 1.000 Org/Hari 60,000 60,000
b Mandor 0.050 Org/Hari 95,000 4,750
JUMLAH 248,436

1 m3 Pembongkaran Beton
a Pekerja 6.667 Org/Hari 60,000 400,020
b Mandor 0.333 Org/Hari 95,000 31,635
JUMLAH 431,655

1 m3 Pembongkaran Dinding Bata


a Pekerja 6.667 Org/Hari 60,000 400,020
b Mandor 0.333 Org/Hari 95,000 31,635
JUMLAH 431,655
B.PEKERJAAN TANAH SNI 2835:2008

1 m3 Galian Tanah Sedalam <1m (SNI:2835:2008-6.1)


a Pekerja 0.750 Org/Hari 60,000 45,000
b Mandor 0.025 Org/Hari 95,000 2,375
JUMLAH 47,375

1 m3 Galian Tanah Sedalam 2m (SNI:2835:2008-6.2)


a Pekerja 0.900 Org/Hari 60,000 54,000
b Mandor 0.045 Org/Hari 95,000 4,275
JUMLAH 58,275

1 m3 Galian Tanah Sedalam 3m (SNI:2835:2008-6.3)


a Pekerja 1.050 Org/Hari 60,000 63,000
b Mandor 0.067 Org/Hari 95,000 6,365
JUMLAH 69,365

1 m3 Galian Tanah Keras Sedalam 1m (SNI:2835:2008-6.4)


a Pekerja 1.000 Org/Hari 60,000 60,000
b Mandor 0.032 Org/Hari 95,000 3,040
JUMLAH 63,040

1 m3 Pekerjaan Pengupasan Tanah Cadas Sedalam 1m (SNI:2835:2008-6.5)


a Pekerja 1.500 Org/Hari 60,000 90,000
b Mandor 0.060 Org/Hari 95,000 5,700
JUMLAH 95,700

1 m3 Pekerjaan Pengupasan Tanah Lumpur Sedalam 1m (SNI:2835:2008-6.6)


a Pekerja 1.200 Org/Hari 60,000 72,000
b Mandor 0.450 Org/Hari 95,000 42,750
JUMLAH 114,750

1 m2 Pekerjaan Stripping Tebing Setinggi 1m (SNI:2835:2008-6.7)


a Pekerja 0.050 Org/Hari 60,000 3,000
b Mandor 0.005 Org/Hari 95,000 475
JUMLAH 3,475

1 m3 Pembuangan Tanah Sejauh 15m (SNI:2835:2008-6.8)


a Pekerja 0.330 Org/Hari 60,000 19,800
b Mandor 0.010 Org/Hari 95,000 950
JUMLAH 20,750

(SNI:2835:2008-6.9)
1 m3 Urugan Kembali semua indeks sejumlah 1/3 dari indeks tiap jenis pekerjaan

1 m3 Pemadatan Tanah (per 20cm) (SNI:2835:2008-6.10)


a Pekerja 0.500 Org/Hari 60,000 30,000
b Mandor 0.050 Org/Hari 95,000 4,750
JUMLAH 34,750

1 m3 Urugan Tanah (SNI:2835:2008-6.10)


a Pekerja 0.250 Org/Hari 60,000 15,000
b Mandor 0.025 Org/Hari 95,000 2,375
JUMLAH 17,375
1 m3 Urugan Pasir (SNI:2835:2008-6.11)
1 Pasir Urug 1.050 m3 100,000 105,000
a Pekerja 0.300 Org/Hari 60,000 18,000
b Mandor 0.010 Org/Hari 95,000 950
JUMLAH 123,950

1 m2 Memasang lapisan ijuk t=10cm (utk resapan) (SNI:2835:2008-6.14)


1 Pasir Urug 6.000 kg 100,000 600,000
a Pekerja 0.150 Org/Hari 60,000 9,000
b Mandor 0.015 Org/Hari 95,000 1,425
JUMLAH 10,425

1 m3 Urugan Sirtu (SNI:2835:2008-6.15)


1 Pasir Urug 1.200 m3 100,000 120,000
a Pekerja 0.250 Org/Hari 60,000 15,000
b Mandor 0.025 Org/Hari 95,000 2,375
JUMLAH 137,375

C.PEKERJAAN PONDASI SNI 2836:2008

1 m3 Pasang Pondasi BT Belah 1 Pc : 3 Ps (SNI:2836:2008-6.1)


1 Batu Belah Pondasi 1.200 m3 228,571 274,286
2 Semen PC (50 Kg) 4.040 zak 63,500 256,540
3 Pasir Pasang 0.485 m3 135,000 65,475
a Pekerja 1.500 Org/Hari 60,000 90,000
b Tukang Batu Kasar 0.750 Org/Hari 80,000 60,000
c Kepala Tukang 0.075 Org/Hari 80,000 6,000
d Mandor 0.075 Org/Hari 95,000 7,125
JUMLAH 759,426

1 m3 Pasang Pondasi BT Belah 1 Pc : 4 Ps (SNI:2836:2008-6.2)


1 Batu Belah Pondasi 1.200 m3 228,571 274,286
2 Semen PC (50 Kg) 3.260 zak 63,500 207,010
3 Pasir Pasang 0.520 m3 135,000 70,200
a Pekerja 1.500 Org/Hari 60,000 90,000
b Tukang Batu Kasar 0.750 Org/Hari 80,000 60,000
c Kepala Tukang 0.075 Org/Hari 80,000 6,000
d Mandor 0.075 Org/Hari 95,000 7,125
JUMLAH 714,621

1 m3 Pasang Pondasi BT Belah 1 Pc : 5 Ps (SNI:2836:2008-6.3)


1 Batu Belah Pondasi 1.200 m3 228,571 274,286
2 Semen PC (50 Kg) 2.720 zak 63,500 172,720
3 Pasir Pasang 0.544 m3 135,000 73,440
a Pekerja 1.500 Org/Hari 60,000 90,000
b Tukang Batu Kasar 0.750 Org/Hari 80,000 60,000
c Kepala Tukang 0.075 Org/Hari 80,000 6,000
d Mandor 0.075 Org/Hari 95,000 7,125
JUMLAH 683,571

1 m3 Pasang Pondasi BT Belah 1 Pc : 6 Ps (SNI:2836:2008-6.4)


1 Batu Belah Pondasi 1.200 m3 228,571 274,286
2 Semen PC (50 Kg) 2.340 zak 63,500 148,590
3 Pasir Pasang 0.561 m3 135,000 75,735
a Pekerja 1.500 Org/Hari 60,000 90,000
b Tukang Batu Kasar 0.750 Org/Hari 80,000 60,000
c Kepala Tukang 0.075 Org/Hari 80,000 6,000
d Mandor 0.075 Org/Hari 95,000 7,125
JUMLAH 661,736
1 m3 Pasang Pondasi BT Belah 1 Pc : 8 Ps (SNI:2836:2008-6.5)
1 Batu Belah Pondasi 1.200 m3 228,571 274,286
2 Semen PC (50 Kg) 1.820 zak 63,500 115,570
3 Pasir Pasang 0.584 m3 135,000 78,840
a Pekerja 1.500 Org/Hari 60,000 90,000
b Tukang Batu Kasar 0.750 Org/Hari 80,000 60,000
c Kepala Tukang 0.075 Org/Hari 80,000 6,000
d Mandor 0.075 Org/Hari 95,000 7,125
JUMLAH 631,821

1 m3 Pasang Pondasi BT Kosong (Aanstamping) (SNI:2836:2008-6.9)


1 Batu Belah Pondasi 1.200 m3 228,571 274,286
2 Pasir Urug 0.432 m3 100,000 43,200
a Pekerja 0.780 Org/Hari 60,000 46,800
b Tukang Batu Kasar 0.390 Org/Hari 80,000 31,200
c Kepala Tukang 0.039 Org/Hari 80,000 3,120
d Mandor 0.039 Org/Hari 95,000 3,705
JUMLAH 402,311

1 m3 Pasang Pondasi BT Kali (SNI:2836:2008-6.9)


1 Batu kali 1.200 bh 227,500 273,000
2 Pasir Urug 0.432 m3 100,000 43,200
a Pekerja 0.780 Org/Hari 60,000 46,800
b Tukang Batu Kasar 0.390 Org/Hari 80,000 31,200
c Kepala Tukang 0.039 Org/Hari 80,000 3,120
d Mandor 0.039 Org/Hari 95,000 3,705
JUMLAH 401,025

1 m3 Pondasi Sumuran d=100cm (SNI:2836:2008-6.11)


1 Batu Belah Pondasi 0.450 m3 228,571 102,857
2 Semen PC (50 Kg) 3.880 zak 63,500 246,380
3 Pasir Beton 0.312 m3 145,000 45,240
4 Batu Split Pecah Mesin 2/3 0.468 m3 145,000 67,860
a Pekerja 2.400 Org/Hari 60,000 144,000
b Tukang Batu Kasar 0.800 Org/Hari 80,000 64,000
c Kepala Tukang 0.080 Org/Hari 80,000 6,400
d Mandor 1.119 Org/Hari 95,000 106,305
JUMLAH 783,042

1 m3 Adukan Beton Untuk Pondasi 1Pc : 2 Ps : 3 Kr


a Semen PC (50 Kg) 6.72 zak 63,500 426,720
b Pasir Beton 0.54 m3 145,000 78,300
c Batu Split Pecah Mesin 1/2 0.81 m3 145,000 117,450
d Pekerja 2.00 Org/Hari 60,000 120,000
e Tukang Batu Kasar 0.35 Org/Hari 80,000 28,000
JUMLAH 770,470

1 1 KG Penulangan Beton Pondasi


a Besi Beton rata-rata 1.05 Kg 1,721 1,807
b Kawat Beton Hitam 0.02 kg 27,000 540
c Pekerja 0.01 Org/Hari 60,000 600
d Tukang Batu Kasar 0.01 Org/Hari 80,000 800
JUMLAH 3,747

1 m2 Pekerjaan Bekisting untuk Pondasi


a Kayu Kuat klas III 0.04 m3 2,335,667 93,427
b Paku 4 s/d 7 cm 0.30 kg 36,000 10,800
c Minyak Pelumas 0.10 Ltr 35,000 3,500
d Pekerja 0.30 Org/Hari 60,000 18,000
e Tukang Kayu Kasar 0.26 Org/Hari 80,000 20,800
JUMLAH 146,527
1 m1 Pondasi Tiang Beton Bertulang uk.40x40cm
a Pasir Beton 0.10 m3 145,000 14,500
b Batu Split Pecah Mesin 2/3 0.15 m3 145,000 21,750
c Semen PC (50 Kg) 1.21 zak 63,500 76,835
d Besi Beton rata-rata 45.00 Kg 1,721 77,442
e Kawat Beton Hitam 0.90 kg 27,000 24,300
f Kaso kelas III 0.03 m3 2,387,000 71,610
g Papan kelas III 0.10 m3 2,233,000 223,300
h Paku 4 s/d 7 cm 0.12 kg 36,000 4,320
I Terpentin 0.09 Ltr 7,500 675
j Cat Dasar / meni besi 0.24 Kg 28,336 6,801
k Pekerja 1.00 Org/Hari 60,000 60,000
l Tukang Kayu Kasar 0.67 Org/Hari 80,000 53,600
JUMLAH 635,133

1 m1 Pondasi Tiang Beton Bertulang uk.35x35cm


a Pasir Beton 0.08 m3 145,000 11,600
b Batu Split Pecah Mesin 2/3 0.13 m3 145,000 18,850
c Semen PC (50 Kg) 0.98 zak 63,500 62,230
d Besi Beton rata-rata 34.50 Kg 1,721 59,372
e Kawat Beton Hitam 0.70 kg 27,000 18,900
f Kaso kelas III 0.03 m3 2,387,000 71,610
g Papan kelas III 0.01 m3 2,233,000 22,330
h Paku 4 s/d 7 cm 0.12 kg 36,000 4,320
I Terpentin 0.09 Ltr 7,500 675
j Cat Dasar / meni besi 0.20 Kg 28,336 5,667
k Pekerja 0.80 Org/Hari 60,000 48,000
l Tukang Kayu Kasar 0.50 Org/Hari 80,000 40,000
JUMLAH 363,555

1 m1 Pondasi Tiang Beton Bertulang uk.25x25cm


a Pasir Beton 0.06 m3 145,000 8,700
b Batu Split Pecah Mesin 2/3 0.11 m3 145,000 15,950
c Semen PC (50 Kg) 0.82 zak 63,500 52,070
d Besi Beton rata-rata 34.50 Kg 1,721 59,372
e Kawat Beton Hitam 0.60 kg 27,000 16,200
f Kaso kelas III 0.03 m3 2,387,000 71,610
g Papan kelas III 0.01 m3 2,233,000 22,330
h Paku 4 s/d 7 cm 0.11 kg 36,000 3,960
I Terpentin 0.08 Ltr 7,500 600
j Cat Dasar / meni besi 0.20 Kg 28,336 5,667
k Pekerja 0.80 Org/Hari 60,000 48,000
l Tukang Kayu Kasar 0.50 Org/Hari 80,000 40,000
JUMLAH 344,460

1 m3 Pondasi Plat Beton (Pembesian 125kg + bekisting papan)


1 Papan kelas III 0.20 m3 2,233,000 446,600
2 Paku 4 s/d 7 cm 1.50 kg 36,000 54,000
3 Minyak Pelumas 0.40 Ltr 35,000 14,000
4 Besi Beton rata-rata 125.00 Kg 1,721 215,117
5 Kawat Beton Hitam 2.25 kg 27,000 60,750
6 Semen PC (50 Kg) 6.46 zak 63,500 410,210
7 Pasir Beton 0.52 m3 145,000 75,400
8 Batu Split Pecah Mesin 2/3 0.78 m3 145,000 113,100
a Pekerja 3.90 Org/Hari 60,000 234,000
b Tukang Batu Kasar 0.35 Org/Hari 80,000 28,000
c Tukang Kayu Kasar 1.04 Org/Hari 80,000 83,200
d Tukang Besi Tulangan 1.05 Org/Hari 80,000 84,000
JUMLAH 1,818,377
1 m3 Pondasi Plat Beton (Pembesian 150kg + bekisting papan)
1 Papan kelas III 0.20 m3 2,233,000 446,600
2 Paku 4 s/d 7 cm 1.50 kg 36,000 54,000
3 Minyak Pelumas 0.40 Ltr 35,000 14,000
4 Besi Beton rata-rata 150.00 Kg 1,721 258,141
5 Kawat Beton Hitam 2.25 kg 27,000 60,750
6 Semen PC (50 Kg) 6.46 zak 63,500 410,210
7 Pasir Beton 0.52 m3 145,000 75,400
8 Batu Split Pecah Mesin 2/3 0.78 m3 145,000 113,100
a Pekerja 4.00 Org/Hari 60,000 240,000
b Tukang Batu Kasar 0.40 Org/Hari 80,000 32,000
c Tukang Kayu Kasar 1.00 Org/Hari 80,000 80,000
d Tukang Besi Tulangan 1.00 Org/Hari 80,000 80,000
JUMLAH 1,864,201

1 m3 Pondasi Beton Borepile (Pembesian 125kg)


1 Besi Beton rata-rata 125.00 Kg 1,721 215,117
2 Kawat Beton Hitam 2.10 kg 27,000 56,700
3 Semen PC (50 Kg) 6.46 zak 63,500 410,210
4 Pasir Beton 0.52 m3 145,000 75,400
5 Batu Split Pecah Mesin 2/3 0.78 m3 145,000 113,100
a Pekerja 3.90 Org/Hari 60,000 234,000
b Tukang Batu Kasar 0.35 Org/Hari 80,000 28,000
c Tukang Kayu Kasar 1.00 Org/Hari 80,000 80,000
d Tukang Besi Tulangan 1.00 Org/Hari 80,000 80,000
JUMLAH 1,292,527

1 m3 Pondasi Beton Borepile (Pembesian 150kg)


1 Besi Beton rata-rata 150.00 Kg 1,721 258,141
2 Kawat Beton Hitam 0.08 kg 27,000 2,160
3 Semen PC (50 Kg) 6.46 zak 63,500 410,210
4 Pasir Beton 0.52 m3 145,000 75,400
5 Batu Split Pecah Mesin 2/3 0.78 m3 145,000 113,100
a Pekerja 4.00 Org/Hari 60,000 240,000
b Tukang Batu Kasar 0.40 Org/Hari 80,000 32,000
c Tukang Kayu Kasar 1.00 Org/Hari 80,000 80,000
d Tukang Besi Tulangan 1.00 Org/Hari 80,000 80,000
JUMLAH 1,291,011

D.PEKERJAAN BETON STRUKTUR & NON STR


D1. PEKERJAAN BETON
1 m3 Pembuatan Beton Non Struktur (1 Pc : 3 Ps : 5 Split)
1 Semen PC (50 Kg) 4.36 zak 63,500 276,860
2 Pasir Beton 0.52 m3 145,000 75,400
3 Batu Split Pecah Mesin 2/3 0.87 m3 145,000 126,150
a Pekerja 2.00 Org/Hari 60,000 120,000
b Tukang Batu Kasar 0.35 Org/Hari 80,000 28,000
JUMLAH 626,410

1 m3 Pembuatan Beton Struktur (1 Pc : 2 Ps : 4 Split)


1 Semen PC (50 Kg) 4.64 zak 63,500 294,640
2 Pasir Beton 0.52 m3 145,000 75,400
3 Batu Split Pecah Mesin 2/3 0.78 m3 145,000 113,100
a Pekerja 2.00 Org/Hari 60,000 120,000
b Tukang Batu Kasar 0.35 Org/Hari 80,000 28,000
JUMLAH 631,140
1 m3 Pembuatan Beton Struktur (1 Pc : 2 Ps : 3 Split)
1 Semen PC (50 Kg) 6.72 zak 63,500 426,720
2 Pasir Beton 0.54 m3 145,000 78,300
3 Batu Split Pecah Mesin 2/3 0.81 m3 145,000 117,450
a Pekerja 2.00 Org/Hari 60,000 120,000
b Tukang Batu Kasar 0.35 Org/Hari 80,000 28,000
JUMLAH 770,470
1 m3 Pembuatan Beton mutu K=100 (SNI:7394:2008-6.1)
1 Semen PC (50 Kg) 1.568 zak 63,500 99,584
2 Pasir Beton 0.644 m3 145,000 93,337
3 Batu Split Pecah Mesin 2/3 0.714 m3 145,000 103,468
4 Air 215.000 liter 34 7,267
a Pekerja 1.650 Org/Hari 60,000 99,000
b Tukang Batu Kasar 0.275 Org/Hari 80,000 22,000
c Kepala Tukang 0.028 Org/Hari 80,000 2,240
d Mandor 0.083 Org/Hari 95,000 7,885
JUMLAH 434,781

1 m3 Pembuatan Beton mutu K=125 (SNI:7394:2008-6.2)


1 Semen PC (50 Kg) 1.752 zak 63,500 111,276
2 Pasir Beton 0.613 m3 145,000 88,933
3 Batu Split Pecah Mesin 2/3 0.723 m3 145,000 104,814
4 Air 215.000 liter 34 7,267
a Pekerja 1.650 Org/Hari 60,000 99,000
b Tukang Batu Kasar 0.275 Org/Hari 80,000 22,000
c Kepala Tukang 0.028 Org/Hari 80,000 2,240
d Mandor 0.083 Org/Hari 95,000 7,885
JUMLAH 443,416

1 m3 Pembuatan Beton mutu K=150 (SNI:7394:2008-6.3)


1 Semen PC (50 Kg) 1.898 zak 63,500 120,549
2 Pasir Beton 0.592 m3 145,000 85,819
3 Batu Split Pecah Mesin 2/3 0.726 m3 145,000 105,332
4 Air 215.000 liter 34 7,267
a Pekerja 1.650 Org/Hari 60,000 99,000
b Tukang Batu Kasar 0.275 Org/Hari 80,000 22,000
c Kepala Tukang 0.028 Org/Hari 80,000 2,240
d Mandor 0.083 Org/Hari 95,000 7,885
JUMLAH 450,092

1 m3 Pembuatan Lantai Kerja Beton K=100 (SNI:7394:2008-6.4)


1 Semen PC (50 Kg) 1.460 zak 63,500 92,730
2 Pasir Beton 0.661 m3 145,000 95,915
3 Batu Split Pecah Mesin 2/3 0.734 m3 145,000 106,368
4 Air 200.000 liter 34 6,760
a Pekerja 1.200 Org/Hari 60,000 72,000
b Tukang Batu Kasar 0.200 Org/Hari 80,000 16,000
c Kepala Tukang 0.020 Org/Hari 80,000 1,600
d Mandor 0.060 Org/Hari 95,000 5,700
JUMLAH 397,073

1 m3 Pembuatan Beton mutu K=175 (SNI:7394:2008-6.5)


1 Semen PC (50 Kg) 2.070 zak 63,500 131,435
2 Pasir Beton 0.563 m3 145,000 81,630
3 Batu Split Pecah Mesin 2/3 0.735 m3 145,000 106,575
4 Air 215.000 liter 34 7,267
a Pekerja 1.650 Org/Hari 60,000 99,000
b Tukang Batu Kasar 0.275 Org/Hari 80,000 22,000
c Kepala Tukang 0.028 Org/Hari 80,000 2,240
d Mandor 0.083 Org/Hari 95,000 7,885
JUMLAH 458,032
1 m3 Pembuatan Beton mutu K=200 (SNI:7394:2008-6.6)
1 Semen PC (50 Kg) 2.235 zak 63,500 141,917
2 Pasir Beton 0.541 m3 145,000 78,515
3 Batu Split Pecah Mesin 2/3 0.736 m3 145,000 106,782
4 Air 215.000 liter 34 7,267
a Pekerja 1.650 Org/Hari 60,000 99,000
b Tukang Batu Kasar 0.275 Org/Hari 80,000 22,000
c Kepala Tukang 0.028 Org/Hari 80,000 2,240
d Mandor 0.083 Org/Hari 95,000 7,885
JUMLAH 465,606

1 m3 Pembuatan Beton mutu K=225 (SNI:7394:2008-6.7)


1 Semen PC (50 Kg) 2.356 zak 63,500 149,578
2 Pasir Beton 0.517 m3 145,000 74,970
3 Batu Split Pecah Mesin 2/3 0.748 m3 145,000 108,439
4 Air 215.000 liter 34 7,267
a Pekerja 1.650 Org/Hari 60,000 99,000
b Tukang Batu Kasar 0.275 Org/Hari 80,000 22,000
c Kepala Tukang 0.028 Org/Hari 80,000 2,240
d Mandor 0.083 Org/Hari 95,000 7,885
JUMLAH 471,379

1 m3 Pembuatan Beton mutu K=250 (SNI:7394:2008-6.8)


1 Semen PC (50 Kg) 2.438 zak 63,500 154,819
2 Pasir Beton 0.513 m3 145,000 74,326
3 Batu Split Pecah Mesin 2/3 0.742 m3 145,000 107,611
4 Air 215.000 liter 34 7,267
a Pekerja 1.650 Org/Hari 60,000 99,000
b Tukang Batu Kasar 0.275 Org/Hari 80,000 22,000
c Kepala Tukang 0.028 Org/Hari 80,000 2,240
d Mandor 0.083 Org/Hari 95,000 7,885
JUMLAH 475,148

1 m3 Pembuatan Beton mutu K=275 (SNI:7394:2008-6.9)


1 Semen PC (50 Kg) 2.578 zak 63,500 163,689
2 Pasir Beton 0.507 m3 145,000 73,467
3 Batu Split Pecah Mesin 2/3 0.733 m3 145,000 106,264
4 Air 215.000 liter 34 7,267
a Pekerja 1.650 Org/Hari 60,000 99,000
b Tukang Batu Kasar 0.275 Org/Hari 80,000 22,000
c Kepala Tukang 0.028 Org/Hari 80,000 2,240
d Mandor 0.083 Org/Hari 95,000 7,885
JUMLAH 481,812

1 m3 Pembuatan Beton mutu K=300 (SNI:7394:2008-6.10)


1 Semen PC (50 Kg) 2.622 zak 63,500 166,511
2 Pasir Beton 0.010 m3 145,000 1,463
3 Batu Split Pecah Mesin 2/3 0.015 m3 145,000 2,115
4 Air 215.000 liter 34 7,267
a Pekerja 1.650 Org/Hari 60,000 99,000
b Tukang Batu Kasar 0.275 Org/Hari 80,000 22,000
c Kepala Tukang 0.028 Org/Hari 80,000 2,240
d Mandor 0.083 Org/Hari 95,000 7,885
JUMLAH 308,481
1 m3 Pembuatan Beton mutu K=325 (SNI:7394:2008-6.11)
1 Semen PC (50 Kg) 2.787 zak 63,500 176,994
2 Pasir Beton 0.496 m3 145,000 71,963
3 Batu Split Pecah Mesin 2/3 0.719 m3 145,000 104,193
4 Air 215.000 liter 34 7,267
a Pekerja 2.100 Org/Hari 60,000 126,000
b Tukang Batu Kasar 0.350 Org/Hari 80,000 28,000
c Kepala Tukang 0.035 Org/Hari 80,000 2,800
d Mandor 0.105 Org/Hari 95,000 9,975
JUMLAH 527,191

1 m3 Pembuatan Beton mutu K=350 (SNI:7394:2008-6.12)


1 Semen PC (50 Kg) 2.844 zak 63,500 180,622
2 Pasir Beton 0.494 m3 145,000 71,641
3 Batu Split Pecah Mesin 2/3 0.714 m3 145,000 103,571
4 Air 215.000 liter 34 7,267
a Pekerja 2.100 Org/Hari 60,000 126,000
b Tukang Batu Kasar 0.350 Org/Hari 80,000 28,000
c Kepala Tukang 0.035 Org/Hari 80,000 2,800
d Mandor 0.105 Org/Hari 95,000 9,975
JUMLAH 529,876

1 m3 Pembuatan Cor Beton K-250 Readymix (SNI DT-91-0008-6.9-2007)


1 Beton K-250 Readymix Slum 12 cm 1.100 m3 2,168,516 2,385,368
2 Vibrator 1.000 unt 300,000 300,000
3 Sewa Pompa 1.000 unt 3,250,000 3,250,000
a Pekerja 1.650 Org/Hari 60,000 99,000
b Tukang Batu Kasar 0.275 Org/Hari 80,000 22,000
c Kepala Tukang 0.028 Org/Hari 80,000 2,240
d Mandor 0.083 Org/Hari 95,000 7,885
JUMLAH 6,066,493

1 m3 Pembuatan Cor Beton K-300 Readymix (SNI DT-91-0008-6.9-2007)


1 Beton K-300 Readymix Slum 12 cm 1.100 m3 2,400,000 2,640,000
2 Vibrator 1.000 unt 300,000 300,000
3 Sewa Pompa 1.000 unt 3,250,000 3,250,000
a Pekerja 1.650 Org/Hari 60,000 99,000
b Tukang Batu Kasar 0.275 Org/Hari 80,000 22,000
c Kepala Tukang 0.028 Org/Hari 80,000 2,240
d Mandor 0.083 Org/Hari 95,000 7,885
JUMLAH 6,321,125

1 m3 Pembuatan Cor Beton K-350 Readymix (SNI DT-91-0008-6.9-2007)


1 Beton K-300 Readymix Slum 12 cm 1.100 m3 2,710,645 2,981,710
2 Vibrator 1.000 unt 300,000 300,000
3 Sewa Pompa 1.000 unt 3,250,000 3,250,000
a Pekerja 1.650 Org/Hari 60,000 99,000
b Tukang Batu Kasar 0.275 Org/Hari 80,000 22,000
c Kepala Tukang 0.028 Org/Hari 80,000 2,240
d Mandor 0.083 Org/Hari 95,000 7,885
JUMLAH 6,662,835
D2. PEKERJAAN PEMBESIAN
1 1kg Penulangan Beton Pembesian Besi dia. 6mm
1 Besi beton Ø6 1.0500 Kg 10,526 11,053
b Kawat Beton Hitam 0.0150 kg 27,000 405
a Pekerja 0.0070 Org/Hari 60,000 420
b Tukang Batu Kasar 0.0070 Org/Hari 80,000 560
c Kepala Tukang 0.0007 Org/Hari 80,000 56
d Mandor 0.0004 Org/Hari 95,000 38
JUMLAH 12,532

1 1kg Penulangan Beton Pembesian Besi dia. 8mm


1 Besi beton Ø8 1.0500 Kg 14,531 15,258
b Kawat Beton Hitam 0.0150 kg 27,000 405
a Pekerja 0.0070 Org/Hari 60,000 420
b Tukang Batu Kasar 0.0070 Org/Hari 80,000 560
c Kepala Tukang 0.0007 Org/Hari 80,000 56
d Mandor 0.0004 Org/Hari 95,000 38
JUMLAH 16,737

1 1kg Penulangan Beton Pembesian Besi dia. 10mm


1 Besi beton Ø10 1.0500 Kg 9,324 9,791
b Kawat Beton Hitam 0.0150 kg 27,000 405
a Pekerja 0.0070 Org/Hari 60,000 420
b Tukang Batu Kasar 0.0070 Org/Hari 80,000 560
c Kepala Tukang 0.0007 Org/Hari 80,000 56
d Mandor 0.0004 Org/Hari 95,000 38
JUMLAH 11,270

1 1kg Penulangan Beton Pembesian Besi dia. 13mm


1 Besi beton Ø13 1.0500 Kg 8,974 9,423
b Kawat Beton Hitam 0.0150 kg 27,000 405
a Pekerja 0.0070 Org/Hari 60,000 420
b Tukang Batu Kasar 0.0070 Org/Hari 80,000 560
c Kepala Tukang 0.0007 Org/Hari 80,000 56
d Mandor 0.0004 Org/Hari 95,000 38
JUMLAH 10,902

1 1kg Penulangan Beton Pembesian Besi Polos


1 Besi Beton rata-rata 1.0500 Kg 1,721 1,807
b Kawat Beton Hitam 0.0150 kg 27,000 405
a Pekerja 0.0070 Org/Hari 60,000 420
b Tukang Batu Kasar 0.0070 Org/Hari 80,000 560
c Kepala Tukang 0.0007 Org/Hari 80,000 56
d Mandor 0.0004 Org/Hari 95,000 38
JUMLAH 3,286

1 1kg Penulangan Beton Pembesian Besi Ulir


1 Besi Beton rata-rata 1.0500 Kg 1,721 1,807
b Kawat Beton Hitam 0.0150 kg 27,000 405
a Pekerja 0.0070 Org/Hari 60,000 420
b Tukang Batu Kasar 0.0070 Org/Hari 80,000 560
c Kepala Tukang 0.0007 Org/Hari 80,000 56
d Mandor 0.0004 Org/Hari 95,000 38
JUMLAH 3,286
1 1kg Penulangan Besi Beton U-24 & U-39
1 Besi Beton rata-rata 1.0500 Kg 1,721 1,807
b Kawat Beton Hitam 0.0150 kg 27,000 405
a Pekerja 0.0070 Org/Hari 60,000 420
b Tukang Batu Kasar 0.0070 Org/Hari 80,000 560
c Kepala Tukang 0.0007 Org/Hari 80,000 56
d Mandor 0.0004 Org/Hari 95,000 38
JUMLAH 3,286

1 1kg Memasang Besi Kabel Prestressed Polos/Strand


1 Besi Beton rata-rata 1.0500 Kg 1,721 1,807
b Kawat Beton Hitam 0.0150 kg 27,000 405
a Pekerja 0.0050 Org/Hari 60,000 300
b Tukang Batu Kasar 0.0050 Org/Hari 80,000 400
c Kepala Tukang 0.0005 Org/Hari 80,000 40
d Mandor 0.0003 Org/Hari 95,000 29
JUMLAH 2,980

1 1m2 Memasang Wiremesh M5


1 Wiremesh M5 U50 SNI 1.0500 m2 19,577 20,556
b Kawat Beton Hitam 0.0050 kg 27,000 135
a Pekerja 0.0030 Org/Hari 60,000 180
b Tukang Batu Kasar 0.0030 Org/Hari 80,000 240
c Kepala Tukang 0.0030 Org/Hari 80,000 240
d Mandor 0.0001 Org/Hari 95,000 10
JUMLAH 21,360

1 1m2 Memasang Wiremesh M8


1 Wiremesh M8 rata-rata 1.0500 m2 68,318 71,734
b Kawat Beton Hitam 0.0050 kg 27,000 135
a Pekerja 0.0030 Org/Hari 60,000 180
b Tukang Batu Kasar 0.0030 Org/Hari 80,000 240
c Kepala Tukang 0.0030 Org/Hari 80,000 240
d Mandor 0.0001 Org/Hari 95,000 10
JUMLAH 72,538

1 1m2 Memasang Wiremesh M6


1 Wiremesh M6 rata-rata 1.0500 m2 74,750 78,488
2 Kawat Beton Hitam 0.0050 kg 27,000 135
a Pekerja 0.0030 Org/Hari 60,000 180
b Tukang Batu Kasar 0.0030 Org/Hari 80,000 240
c Kepala Tukang 0.0030 Org/Hari 80,000 240
d Mandor 0.0001 Org/Hari 95,000 10
JUMLAH 79,292

D3. PEKERJAAN BEKISTING


1 m2 Pembuatan Bekisiting untuk Pondasi (SNI:7394:2008-6.20)
1 Kayu Kuat klas III 0.0400 m3 2,335,667 93,427
2 Paku 8 s/d 12 cm 0.3000 kg 36,000 10,800
3 Minyak Pelumas 0.1000 Ltr 35,000 3,500
a Pekerja 0.5200 Org/Hari 60,000 31,200
b Tukang Batu Kasar 0.2600 Org/Hari 80,000 20,800
c Kepala Tukang 0.0260 Org/Hari 80,000 2,080
d Mandor 0.0260 Org/Hari 95,000 2,470
JUMLAH 164,277
1 m2 Pembuatan Bekisiting Pondasi Buis Beton Sumuran
1 Buis Beton 2.0000 Bh 71,500 143,000
2 Alat Bantu 1.0000 ls 2,500 2,500
a Pekerja 1.0000 Org/Hari 60,000 60,000
b Mandor 0.0520 Org/Hari 95,000 4,940
JUMLAH 210,440

1 m2 Pembuatan Bekisiting untuk Sloof (SNI:7394:2008-6.21)


1 Kayu Kuat klas III 0.0450 m3 2,335,667 105,105
2 Paku 8 s/d 12 cm 0.3000 kg 36,000 10,800
3 Minyak Pelumas 0.1000 Ltr 35,000 3,500
a Pekerja 0.5200 Org/Hari 60,000 31,200
b Tukang Batu Kasar 0.2600 Org/Hari 80,000 20,800
c Kepala Tukang 0.0260 Org/Hari 80,000 2,080
d Mandor 0.0260 Org/Hari 95,000 2,470
JUMLAH 175,955

1 m2 Pembuatan Bekisiting untuk Kolom (SNI:7394:2008-6.22)


1 Kayu Kuat klas III 0.0400 m3 2,335,667 93,427
2 Paku 8 s/d 12 cm 0.4000 kg 36,000 14,400
3 Minyak Pelumas 0.2000 Ltr 35,000 7,000
4 Kayu Kuat klas II 0.0150 m3 9,500,000 142,500
5 Multiplex t. 9 mm 0.3500 lbr 100,000 35,000
6 Dolken dia 8 s/d 10 cm p. 4 m 2.0000 btg 15,000 30,000
a Pekerja 0.6600 Org/Hari 60,000 39,600
b Tukang Batu Kasar 0.3300 Org/Hari 80,000 26,400
c Kepala Tukang 0.0330 Org/Hari 80,000 2,640
d Mandor 0.0330 Org/Hari 95,000 3,135
JUMLAH 394,102

1 m2 Pembuatan Bekisiting untuk Balok (SNI:7394:2008-6.23)


1 Kayu Kuat klas III 0.0400 m3 2,335,667 93,427
2 Paku 8 s/d 12 cm 0.4000 kg 36,000 14,400
3 Minyak Pelumas 0.2000 Ltr 35,000 7,000
4 Kayu Kuat klas II 0.0180 m3 9,500,000 171,000
5 Multiplex t. 9 mm 0.3500 lbr 100,000 35,000
6 Dolken dia 8 s/d 10 cm p. 4 m 2.0000 btg 15,000 30,000
a Pekerja 0.6600 Org/Hari 60,000 39,600
b Tukang Batu Kasar 0.3300 Org/Hari 80,000 26,400
c Kepala Tukang 0.0330 Org/Hari 80,000 2,640
d Mandor 0.0330 Org/Hari 95,000 3,135
JUMLAH 422,602

1 m2 Pembuatan Bekisiting untuk Plat Lantai (SNI:7394:2008-6.24)


1 Kayu Kuat klas III 0.0400 m3 2,335,667 93,427
2 Paku 8 s/d 12 cm 0.4000 kg 36,000 14,400
3 Minyak Pelumas 0.2000 Ltr 35,000 7,000
4 Kayu Kuat klas II 0.0150 m3 9,500,000 142,500
5 Multiplex t. 9 mm 0.3500 lbr 100,000 35,000
6 Dolken dia 8 s/d 10 cm p. 4 m 6.0000 btg 15,000 90,000
a Pekerja 0.6600 Org/Hari 60,000 39,600
b Tukang Batu Kasar 0.3300 Org/Hari 80,000 26,400
c Kepala Tukang 0.0330 Org/Hari 80,000 2,640
d Mandor 0.0330 Org/Hari 95,000 3,135
JUMLAH 454,102
1 m2 Pembuatan Bekisiting untuk Dinding (SNI:7394:2008-6.25)
1 Kayu Kuat klas III 0.0300 m3 2,335,667 70,070
2 Paku 8 s/d 12 cm 0.4000 kg 36,000 14,400
3 Minyak Pelumas 0.2000 Ltr 35,000 7,000
4 Kayu Kuat klas II 0.0200 m3 9,500,000 190,000
5 Multiplex t. 9 mm 0.3500 lbr 100,000 35,000
6 Dolken dia 8 s/d 10 cm p. 4 m 3.0000 btg 15,000 45,000
7 Formiten/spacer bekisting 4.0000 Bh 14,300 57,200
a Pekerja 0.6600 Org/Hari 60,000 39,600
b Tukang Batu Kasar 0.3300 Org/Hari 80,000 26,400
c Kepala Tukang 0.0330 Org/Hari 80,000 2,640
d Mandor 0.0330 Org/Hari 95,000 3,135
JUMLAH 490,445

1 m2 Pembuatan Bekisiting untuk Tangga (SNI:7394:2008-6.26)


1 Kayu Kuat klas III 0.0300 m3 2,335,667 70,070
2 Paku 8 s/d 12 cm 0.4000 kg 36,000 14,400
3 Minyak Pelumas 0.1500 Ltr 35,000 5,250
4 Kayu Kuat klas II 0.0150 m3 9,500,000 142,500
5 Multiplex t. 9 mm 0.3500 lbr 100,000 35,000
6 Dolken dia 8 s/d 10 cm p. 4 m 2.0000 btg 15,000 30,000
a Pekerja 0.6600 Org/Hari 60,000 39,600
b Tukang Batu Kasar 0.3300 Org/Hari 80,000 26,400
c Kepala Tukang 0.0330 Org/Hari 80,000 2,640
d Mandor 0.0330 Org/Hari 95,000 3,135
JUMLAH 368,995

D4. PEKERJAAN BETON BERTULANG


1 m3 Pekerjaan Pondasi Beton (Besi 150kg + bekisting) (SNI:7394:2008-6.28)
1 Kayu Kuat klas III 0.2000 m3 2,335,667 467,133
2 Paku 8 s/d 12 cm 1.5000 kg 36,000 54,000
3 Minyak Pelumas 0.4000 Ltr 35,000 14,000
4 Besi Beton rata-rata 157.5000 Kg 1,721 271,048
5 Kawat Beton Hitam 2.2500 kg 27,000 60,750
6 Semen PC (50 Kg) 6.7200 zak 63,500 426,720
7 Pasir Beton 0.5400 m3 145,000 78,300
8 Batu Split Pecah Mesin 2/3 0.8100 m3 145,000 117,450
a Pekerja 5.3000 Org/Hari 60,000 318,000
b Tukang Batu Kasar 0.2750 Org/Hari 80,000 22,000
c Tukang Kayu Kasar 1.3000 Org/Hari 80,000 104,000
d Tukang Besi Tulangan 1.0500 Org/Hari 80,000 84,000
e Kepala Tukang 0.2620 Org/Hari 80,000 20,960
f Mandor 0.2650 Org/Hari 95,000 25,175
JUMLAH 2,063,536

1 m3 Pekerjaan Sloof Beton (Besi 200kg + bekisting) (SNI:7394:2008-6.29)


1 Kayu Kuat klas III 0.2700 m3 2,335,667 630,630
2 Paku 8 s/d 12 cm 2.0000 kg 36,000 72,000
3 Minyak Pelumas 0.6000 Ltr 35,000 21,000
4 Besi Beton rata-rata 210.0000 Kg 1,721 361,397
5 Kawat Beton Hitam 3.0000 kg 27,000 81,000
6 Semen PC (50 Kg) 6.7200 zak 63,500 426,720
7 Pasir Beton 0.5400 m3 145,000 78,300
8 Batu Split Pecah Mesin 2/3 0.8100 m3 145,000 117,450
a Pekerja 0.5650 Org/Hari 60,000 33,900
b Tukang Batu Kasar 0.2750 Org/Hari 80,000 22,000
c Tukang Kayu Kasar 1.5600 Org/Hari 80,000 124,800
d Tukang Besi Tulangan 1.4000 Org/Hari 80,000 112,000
e Kepala Tukang 0.3230 Org/Hari 80,000 25,840
f Mandor 0.2830 Org/Hari 95,000 26,885
JUMLAH 2,133,922
1 m3 Pekerjaan Kolom Beton (Besi 300kg + bekisting) (SNI:7394:2008-6.30)
1 Kayu Kuat klas III 0.4000 m3 2,335,667 934,267
2 Paku 8 s/d 12 cm 4.0000 kg 36,000 144,000
3 Minyak Pelumas 2.0000 Ltr 35,000 70,000
4 Besi Beton rata-rata 315.0000 Kg 1,721 542,095
5 Kawat Beton Hitam 4.5000 kg 27,000 121,500
6 Semen PC (50 Kg) 6.7200 zak 63,500 426,720
7 Pasir Beton 0.5400 m3 145,000 78,300
8 Batu Split Pecah Mesin 2/3 0.8100 m3 145,000 117,450
9 Kayu Kuat klas II 0.1500 m3 9,500,000 1,425,000
10 Multiplex t. 9 mm 3.5000 lbr 100,000 350,000
11 Dolken dia 8 s/d 10 cm p. 4 m 20.0000 btg 15,000 300,000
a Pekerja 7.0500 Org/Hari 60,000 423,000
b Tukang Batu Kasar 0.2750 Org/Hari 80,000 22,000
c Tukang Kayu Kasar 1.6500 Org/Hari 80,000 132,000
d Tukang Besi Tulangan 2.1000 Org/Hari 80,000 168,000
e Kepala Tukang 0.4030 Org/Hari 80,000 32,240
f Mandor 0.3530 Org/Hari 95,000 33,535
JUMLAH 5,320,107

1 m3 Pekerjaan Balok Beton (Besi 200kg + bekisting) (SNI:7394:2008-6.31)


1 Kayu Kuat klas III 0.3200 m3 2,335,667 747,413
2 Paku 8 s/d 12 cm 3.2000 kg 36,000 115,200
3 Minyak Pelumas 1.6000 Ltr 35,000 56,000
4 Besi Beton rata-rata 210.0000 Kg 1,721 361,397
5 Kawat Beton Hitam 3.0000 kg 27,000 81,000
6 Semen PC (50 Kg) 6.7200 zak 63,500 426,720
7 Pasir Beton 0.5400 m3 145,000 78,300
8 Batu Split Pecah Mesin 2/3 0.8100 m3 145,000 117,450
9 Kayu Kuat klas II 0.1400 m3 9,500,000 1,330,000
10 Multiplex t. 9 mm 2.8000 lbr 100,000 280,000
11 Dolken dia 8 s/d 10 cm p. 4 m 16.0000 btg 15,000 240,000
a Pekerja 6.3500 Org/Hari 60,000 381,000
b Tukang Batu Kasar 0.2750 Org/Hari 80,000 22,000
c Tukang Kayu Kasar 1.6500 Org/Hari 80,000 132,000
d Tukang Besi Tulangan 1.4000 Org/Hari 80,000 112,000
e Kepala Tukang 0.3330 Org/Hari 80,000 26,640
f Mandor 0.3180 Org/Hari 95,000 30,210
JUMLAH 4,537,330

1 m3 Pekerjaan Plat Beton (Besi 150kg + bekisting) (SNI:7394:2008-6.32)


1 Kayu Kuat klas III 0.3200 m3 2,335,667 747,413
2 Paku 8 s/d 12 cm 3.2000 kg 36,000 115,200
3 Minyak Pelumas 1.6000 Ltr 35,000 56,000
4 Besi Beton rata-rata 157.5000 Kg 1,721 271,048
5 Kawat Beton Hitam 2.2500 kg 27,000 60,750
6 Semen PC (50 Kg) 6.7200 zak 63,500 426,720
7 Pasir Beton 0.5400 m3 145,000 78,300
8 Batu Split Pecah Mesin 2/3 0.8100 m3 145,000 117,450
9 Kayu Kuat klas II 0.1200 m3 9,500,000 1,140,000
10 Multiplex t. 9 mm 2.8000 lbr 100,000 280,000
11 Dolken dia 8 s/d 10 cm p. 4 m 32.0000 btg 15,000 480,000
a Pekerja 5.3000 Org/Hari 60,000 318,000
b Tukang Batu Kasar 0.2750 Org/Hari 80,000 22,000
c Tukang Kayu Kasar 1.3000 Org/Hari 80,000 104,000
d Tukang Besi Tulangan 1.0500 Org/Hari 80,000 84,000
e Kepala Tukang 0.2650 Org/Hari 80,000 21,200
f Mandor 0.2650 Org/Hari 95,000 25,175
JUMLAH 4,347,256
1 m3 Pekerjaan Dinding Beton (Besi 150kg + bekisting) (SNI:7394:2008-6.33)
1 Kayu Kuat klas III 0.2400 m3 2,335,667 560,560
2 Paku 8 s/d 12 cm 3.2000 kg 36,000 115,200
3 Minyak Pelumas 1.6000 Ltr 35,000 56,000
4 Besi Beton rata-rata 157.5000 Kg 1,721 271,048
5 Kawat Beton Hitam 2.2500 kg 27,000 60,750
6 Semen PC (50 Kg) 6.7200 zak 63,500 426,720
7 Pasir Beton 0.5400 m3 145,000 78,300
8 Batu Split Pecah Mesin 2/3 0.8100 m3 145,000 117,450
9 Kayu Kuat klas II 0.1600 m3 9,500,000 1,520,000
10 Multiplex t. 9 mm 2.8000 lbr 100,000 280,000
11 Dolken dia 8 s/d 10 cm p. 4 m 24.0000 btg 15,000 360,000
a Pekerja 5.3000 Org/Hari 60,000 318,000
b Tukang Batu Kasar 0.2750 Org/Hari 80,000 22,000
c Tukang Kayu Kasar 1.3000 Org/Hari 80,000 104,000
d Tukang Besi Tulangan 1.0500 Org/Hari 80,000 84,000
e Kepala Tukang 0.2620 Org/Hari 80,000 20,960
f Mandor 0.2650 Org/Hari 95,000 25,175
JUMLAH 4,420,163

1 m3 Pekerjaan Dinding Beton (Besi 200kg + bekisting) (SNI:7394:2008-6.34)


1 Kayu Kuat klas III 0.2400 m3 2,335,667 560,560
2 Paku 8 s/d 12 cm 3.2000 kg 36,000 115,200
3 Minyak Pelumas 1.6000 Ltr 35,000 56,000
4 Besi Beton rata-rata 210.0000 Kg 1,721 361,397
5 Kawat Beton Hitam 3.0000 kg 27,000 81,000
6 Semen PC (50 Kg) 6.7200 zak 63,500 426,720
7 Pasir Beton 0.5400 m3 145,000 78,300
8 Batu Split Pecah Mesin 2/3 0.8100 m3 145,000 117,450
9 Kayu Kuat klas II 0.1050 m3 9,500,000 997,500
10 Multiplex t. 9 mm 2.5000 lbr 100,000 250,000
11 Dolken dia 8 s/d 10 cm p. 4 m 14.0000 btg 15,000 210,000
a Pekerja 5.6500 Org/Hari 60,000 339,000
b Tukang Batu Kasar 0.2750 Org/Hari 80,000 22,000
c Tukang Kayu Kasar 1.5600 Org/Hari 80,000 124,800
d Tukang Besi Tulangan 1.4000 Org/Hari 80,000 112,000
e Kepala Tukang 0.3230 Org/Hari 80,000 25,840
f Mandor 0.2830 Org/Hari 95,000 26,885
JUMLAH 3,904,652

1 m1 Pekerjaan Kolom Praktis Beton (11x11cm) (SNI:7394:2008-6.35)


1 Kayu Kuat klas III 0.0020 m3 2,335,667 4,671
2 Paku 8 s/d 12 cm 0.0100 kg 36,000 360
3 Besi Beton rata-rata 3.0000 Kg 1,721 5,163
4 Kawat Beton Hitam 0.0450 kg 27,000 1,215
5 Semen PC (50 Kg) 0.0800 zak 63,500 5,080
6 Pasir Beton 0.0050 m3 145,000 725
7 Batu Split Pecah Mesin 2/3 0.0060 m3 145,000 870
a Pekerja 0.1800 Org/Hari 60,000 10,800
b Tukang Batu Kasar 0.0200 Org/Hari 80,000 1,600
c Tukang Kayu Kasar 0.0200 Org/Hari 80,000 1,600
d Tukang Besi Tulangan 0.0200 Org/Hari 80,000 1,600
e Kepala Tukang 0.0060 Org/Hari 80,000 480
f Mandor 0.0090 Org/Hari 95,000 855
JUMLAH 35,019
1 m1 Pekerjaan Ring Balok Beton (10x15cm) (SNI:7394:2008-6.36)
1 Kayu Kuat klas III 0.0030 m3 2,335,667 7,007
2 Paku 8 s/d 12 cm 0.0200 kg 36,000 720
3 Besi Beton rata-rata 3.6000 Kg 1,721 6,195
4 Kawat Beton Hitam 0.0500 kg 27,000 1,350
5 Semen PC (50 Kg) 0.1100 zak 63,500 6,985
6 Pasir Beton 0.0090 m3 145,000 1,305
7 Batu Split Pecah Mesin 2/3 0.0150 m3 145,000 2,175
a Pekerja 0.2970 Org/Hari 60,000 17,820
b Tukang Batu Kasar 0.0330 Org/Hari 80,000 2,640
c Tukang Kayu Kasar 0.0330 Org/Hari 80,000 2,640
d Tukang Besi Tulangan 0.0330 Org/Hari 80,000 2,640
e Kepala Tukang 0.0100 Org/Hari 80,000 800
f Mandor 0.0150 Org/Hari 95,000 1,425
JUMLAH 53,702

E.PEKERJAAN DINDING (SNI 6897:2008)

1 m2 Pasangan Bata Merah 1Bt (1 pc : 2 Ps) (SNI:6897:2008-6.1)


1 Bata Merah 140.0000 bh 600 84,000
2 Semen PC (50 Kg) 0.8700 zak 63,500 55,245
3 Pasir Pasang 0.0800 m3 135,000 10,800
a Pekerja 0.6000 Org/Hari 60,000 36,000
b Tukang Batu Kasar 0.2000 Org/Hari 80,000 16,000
c Kepala Tukang 0.0200 Org/Hari 80,000 1,600
d Mandor 0.0300 Org/Hari 95,000 2,850
JUMLAH 206,495

1 m2 Pasangan Bata Merah 1Bt (1 pc : 3 Ps) (SNI:6897:2008-6.2)


1 Bata Merah 140.0000 bh 600 84,000
2 Semen PC (50 Kg) 0.6590 zak 63,500 41,847
3 Pasir Pasang 0.0910 m3 135,000 12,285
a Pekerja 0.6000 Org/Hari 60,000 36,000
b Tukang Batu Kasar 0.2000 Org/Hari 80,000 16,000
c Kepala Tukang 0.0200 Org/Hari 80,000 1,600
d Mandor 0.0300 Org/Hari 95,000 2,850
JUMLAH 194,582

1 m2 Pasangan Bata Merah 1Bt (1 pc : 4 Ps) (SNI:6897:2008-6.3)


1 Bata Merah 140.0000 bh 600 84,000
2 Semen PC (50 Kg) 0.5310 zak 63,500 33,719
3 Pasir Pasang 0.0930 m3 135,000 12,555
a Pekerja 0.6000 Org/Hari 60,000 36,000
b Tukang Batu Kasar 0.2000 Org/Hari 80,000 16,000
c Kepala Tukang 0.0200 Org/Hari 80,000 1,600
d Mandor 0.0300 Org/Hari 95,000 2,850
JUMLAH 186,724

1 m2 Pasangan Bata Merah 1Bt (1 pc : 5 Ps) (SNI:6897:2008-6.4)


1 Bata Merah 140.0000 bh 600 84,000
2 Semen PC (50 Kg) 0.4440 zak 63,500 28,194
3 Pasir Pasang 0.1020 m3 135,000 13,770
a Pekerja 0.6000 Org/Hari 60,000 36,000
b Tukang Batu Kasar 0.2000 Org/Hari 80,000 16,000
c Kepala Tukang 0.0200 Org/Hari 80,000 1,600
d Mandor 0.0300 Org/Hari 95,000 2,850
JUMLAH 182,414
1 m2 Pasangan Bata Merah 1Bt (1 pc : 6 Ps) (SNI:6897:2008-6.5)
1 Bata Merah 140.0000 bh 600 84,000
2 Semen PC (50 Kg) 0.3700 zak 63,500 23,495
3 Pasir Pasang 0.1220 m3 135,000 16,470
a Pekerja 0.6000 Org/Hari 60,000 36,000
b Tukang Batu Kasar 0.2000 Org/Hari 80,000 16,000
c Kepala Tukang 0.0200 Org/Hari 80,000 1,600
d Mandor 0.0300 Org/Hari 95,000 2,850
JUMLAH 180,415

1 m2 Pasangan Bata Merah 1/2 Bt (1 pc : 2 Ps) (SNI:6897:2008-6.7)


1 Bata Merah 70.0000 bh 600 42,000
2 Semen PC (50 Kg) 0.3790 zak 63,500 24,067
3 Pasir Pasang 0.0380 m3 135,000 5,130
a Pekerja 0.3000 Org/Hari 60,000 18,000
b Tukang Batu Kasar 0.1000 Org/Hari 80,000 8,000
c Kepala Tukang 0.0100 Org/Hari 80,000 800
d Mandor 0.0150 Org/Hari 95,000 1,425
JUMLAH 99,422

1 m2 Pasangan Bata Merah 1/2 Bt (1 pc : 3 Ps) (SNI:6897:2008-6.8)


1 Bata Merah 70.0000 bh 600 42,000
2 Semen PC (50 Kg) 0.2874 zak 63,500 18,250
3 Pasir Pasang 0.0400 m3 135,000 5,400
a Pekerja 0.3000 Org/Hari 60,000 18,000
b Tukang Batu Kasar 0.1000 Org/Hari 80,000 8,000
c Kepala Tukang 0.0100 Org/Hari 80,000 800
d Mandor 0.0150 Org/Hari 95,000 1,425
JUMLAH 93,875

1 m2 Pasangan Bata Merah 1/2 Bt (1 pc : 4 Ps) (SNI:6897:2008-6.9)


1 Bata Merah 70.0000 bh 600 42,000
2 Semen PC (50 Kg) 0.2300 zak 63,500 14,605
3 Pasir Pasang 0.0430 m3 135,000 5,805
a Pekerja 0.3000 Org/Hari 60,000 18,000
b Tukang Batu Kasar 0.1000 Org/Hari 80,000 8,000
c Kepala Tukang 0.0100 Org/Hari 80,000 800
d Mandor 0.0150 Org/Hari 95,000 1,425
JUMLAH 90,635

1 m2 Pasangan Bata Merah 1/2 Bt (1 pc : 5 Ps) (SNI:6897:2008-6.10)


1 Bata Merah 70.0000 bh 600 42,000
2 Semen PC (50 Kg) 0.1936 zak 63,500 12,294
3 Pasir Pasang 0.0450 m3 135,000 6,075
a Pekerja 0.3000 Org/Hari 60,000 18,000
b Tukang Batu Kasar 0.1000 Org/Hari 80,000 8,000
c Kepala Tukang 0.0100 Org/Hari 80,000 800
d Mandor 0.0150 Org/Hari 95,000 1,425
JUMLAH 88,594

1 m2 Pasangan Bata Merah 1/2 Bt (1 pc : 6 Ps) (SNI:6897:2008-6.11)


1 Bata Merah 70.0000 bh 600 42,000
2 Semen PC (50 Kg) 0.1664 zak 63,500 10,566
3 Pasir Pasang 0.0490 m3 135,000 6,615
a Pekerja 0.3000 Org/Hari 60,000 18,000
b Tukang Batu Kasar 0.1000 Org/Hari 80,000 8,000
c Kepala Tukang 0.0100 Org/Hari 80,000 800
d Mandor 0.0150 Org/Hari 95,000 1,425
JUMLAH 87,406
1 m2 Pasangan Batako (1 pc : 3 Ps) t-20cm (SNI:6897:2008-6.16)
1 Batako 12.5000 bh 2,400 30,000
2 Semen PC (50 Kg) 0.6064 zak 63,500 38,506
3 Pasir Pasang 0.7280 m3 135,000 98,280
4 Besi Beton rata-rata 0.0280 Kg 1,721 48
a Pekerja 0.3500 Org/Hari 60,000 21,000
b Tukang Batu Kasar 0.1500 Org/Hari 80,000 12,000
c Kepala Tukang 0.0150 Org/Hari 80,000 1,200
d Mandor 0.0180 Org/Hari 95,000 1,710
JUMLAH 202,745

1 m2 Pasangan Conblock (1 pc : 3 Ps) t-20cm (SNI:6897:2008-6.16)


1 Bata Conblock 12.5000 bh 2,400 30,000
2 Semen PC (50 Kg) 0.6064 zak 63,500 38,506
3 Pasir Pasang 0.7280 m3 135,000 98,280
4 Besi Beton rata-rata 0.0280 Kg 1,721 48
a Pekerja 0.3500 Org/Hari 60,000 21,000
b Tukang Batu Kasar 0.1500 Org/Hari 80,000 12,000
c Kepala Tukang 0.0150 Org/Hari 80,000 1,200
d Mandor 0.0180 Org/Hari 95,000 1,710
JUMLAH 202,745

1 m2 Pasangan Batako (1 pc : 4 Ps) t-20cm (SNI:6897:2008-6.17)


1 Bata Conblock 12.5000 bh 2,400 30,000
2 Semen PC (50 Kg) 0.4852 zak 63,500 30,810
3 Pasir Pasang 0.7720 m3 135,000 104,220
4 Besi Beton rata-rata 0.0280 Kg 1,721 48
a Pekerja 0.3500 Org/Hari 60,000 21,000
b Tukang Batu Kasar 0.1500 Org/Hari 80,000 12,000
c Kepala Tukang 0.0150 Org/Hari 80,000 1,200
d Mandor 0.0180 Org/Hari 95,000 1,710
JUMLAH 200,988

1 m2 Pasangan Batako (1 pc : 3 Ps) t-15 cm (SNI:6897:2008-6.18)


1 Batako 12.5000 bh 2,400 30,000
2 Semen PC (50 Kg) 0.4548 zak 63,500 28,880
3 Pasir Pasang 0.5500 m3 135,000 74,250
4 Besi Beton rata-rata 0.0280 Kg 1,721 48
a Pekerja 0.3200 Org/Hari 60,000 19,200
b Tukang Batu Kasar 0.1200 Org/Hari 80,000 9,600
c Kepala Tukang 0.0120 Org/Hari 80,000 960
d Mandor 0.0160 Org/Hari 95,000 1,520
JUMLAH 164,458

1 m2 Pasangan Conblok (1 pc : 3 Ps) t-15 cm (SNI:6897:2008-6.18)


1 Bata Conblock 12.5000 bh 2,400 30,000
2 Semen PC (50 Kg) 0.4548 zak 63,500 28,880
3 Pasir Pasang 0.5500 m3 135,000 74,250
4 Besi Beton rata-rata 0.0280 Kg 1,721 48
a Pekerja 0.3200 Org/Hari 60,000 19,200
b Tukang Batu Kasar 0.1200 Org/Hari 80,000 9,600
c Kepala Tukang 0.0120 Org/Hari 80,000 960
d Mandor 0.0160 Org/Hari 95,000 1,520
JUMLAH 164,458
1 m2 Pasangan Batako (1 pc : 4 Ps) t-15 cm (SNI:6897:2008-6.19)
1 Batako 12.5000 bh 2,400 30,000
2 Semen PC (50 Kg) 0.3640 zak 63,500 23,114
3 Pasir Pasang 0.5820 m3 135,000 78,570
4 Besi Beton rata-rata 0.0280 Kg 1,721 48
a Pekerja 0.3200 Org/Hari 60,000 19,200
b Tukang Batu Kasar 0.1200 Org/Hari 80,000 9,600
c Kepala Tukang 0.0120 Org/Hari 80,000 960
d Mandor 0.0160 Org/Hari 95,000 1,520
JUMLAH 163,012

1 m2 Pasangan Conblok (1 pc : 4 Ps) t-15 cm (SNI:6897:2008-6.19)


1 Bata Conblock 12.5000 bh 2,400 30,000
2 Semen PC (50 Kg) 0.3640 zak 63,500 23,114
3 Pasir Pasang 0.5820 m3 135,000 78,570
4 Besi Beton rata-rata 0.0280 Kg 1,721 48
a Pekerja 0.3200 Org/Hari 60,000 19,200
b Tukang Batu Kasar 0.1200 Org/Hari 80,000 9,600
c Kepala Tukang 0.0120 Org/Hari 80,000 960
d Mandor 0.0160 Org/Hari 95,000 1,520
JUMLAH 163,012

1 m2 Pasangan Batako (1 pc : 3 Ps) t-10 cm (SNI:6897:2008-6.20)


1 Batako 12.5000 bh 2,400 30,000
2 Semen PC (50 Kg) 0.3032 zak 63,500 19,253
3 Pasir Pasang 0.3640 m3 135,000 49,140
4 Besi Beton rata-rata 0.0280 Kg 1,721 48
a Pekerja 0.3000 Org/Hari 60,000 18,000
b Tukang Batu Kasar 0.1000 Org/Hari 80,000 8,000
c Kepala Tukang 0.0100 Org/Hari 80,000 800
d Mandor 0.0150 Org/Hari 95,000 1,425
JUMLAH 126,666

1 m2 Pasangan Conblok (1 pc : 3 Ps) t-10 cm (SNI:6897:2008-6.20)


1 Bata Conblock 12.5000 bh 2,400 30,000
2 Semen PC (50 Kg) 0.3032 zak 63,500 19,253
3 Pasir Pasang 0.3640 m3 135,000 49,140
4 Besi Beton rata-rata 0.0280 Kg 1,721 48
a Pekerja 0.3000 Org/Hari 60,000 18,000
b Tukang Batu Kasar 0.1000 Org/Hari 80,000 8,000
c Kepala Tukang 0.0100 Org/Hari 80,000 800
d Mandor 0.0150 Org/Hari 95,000 1,425
JUMLAH 126,666

1 m2 Pasangan Batako (1 pc : 4 Ps) t-10 cm (SNI:6897:2008-6.21)


1 Batako 12.5000 bh 2,400 30,000
2 Semen PC (50 Kg) 0.2426 zak 63,500 15,405
3 Pasir Pasang 0.3880 m3 135,000 52,380
4 Besi Beton rata-rata 0.0280 Kg 1,721 48
a Pekerja 0.3000 Org/Hari 60,000 18,000
b Tukang Batu Kasar 0.1000 Org/Hari 80,000 8,000
c Kepala Tukang 0.0100 Org/Hari 80,000 800
d Mandor 0.0150 Org/Hari 95,000 1,425
JUMLAH 126,058
1 m2 Pasangan Conblok (1 pc : 4 Ps) t-10 cm (SNI:6897:2008-6.21)
1 Bata Conblock 12.5000 bh 2,400 30,000
2 Semen PC (50 Kg) 0.2426 zak 63,500 15,405
3 Pasir Pasang 0.3880 m3 135,000 52,380
4 Besi Beton rata-rata 0.0280 Kg 1,721 48
a Pekerja 0.3000 Org/Hari 60,000 18,000
b Tukang Batu Kasar 0.1000 Org/Hari 80,000 8,000
c Kepala Tukang 0.0100 Org/Hari 80,000 800
d Mandor 0.0150 Org/Hari 95,000 1,425
JUMLAH 126,058

1 m2 Pasangan Bata Roster (1 pc : 3 Ps) u.12x11x24 cm (SNI:6897:2008-6.22)


1 Bata Roster 30.0000 bh 7,000 210,000
2 Semen PC (50 Kg) 0.2800 zak 63,500 17,780
3 Pasir Pasang 0.0320 m3 135,000 4,320
a Pekerja 0.3000 Org/Hari 60,000 18,000
b Tukang Batu Kasar 0.1000 Org/Hari 80,000 8,000
c Kepala Tukang 0.0100 Org/Hari 80,000 800
d Mandor 0.0150 Org/Hari 95,000 1,425
JUMLAH 260,325

1 m2 Pasangan Bata Roster (1 pc : 4 Ps) u.12x11x24 cm (SNI:6897:2008-6.23)


1 Bata Roster 30.0000 bh 7,000 210,000
2 Semen PC (50 Kg) 0.2200 zak 63,500 13,970
3 Pasir Pasang 0.0350 m3 135,000 4,725
a Pekerja 0.3000 Org/Hari 60,000 18,000
b Tukang Batu Kasar 0.1000 Org/Hari 80,000 8,000
c Kepala Tukang 0.0100 Org/Hari 80,000 800
d Mandor 0.0150 Org/Hari 95,000 1,425
JUMLAH 256,920

F.PEKERJAAN Plesteran & Aci (SNI 2837:2008)

1 m2 Plesteran tebal= 1,5 (1 pc : 1 Ps) (SNI:2837:2008-6.1)


1 Semen PC (50 Kg) 0.3101 zak 63,500 19,690
2 Pasir Pasang 0.0160 m3 135,000 2,160
a Pekerja 0.3000 Org/Hari 60,000 18,000
b Tukang Batu Kasar 0.1500 Org/Hari 80,000 12,000
c Kepala Tukang 0.0150 Org/Hari 80,000 1,200
d Mandor 0.0150 Org/Hari 95,000 1,425
JUMLAH 54,475

1 m2 Plesteran tebal= 1,5 (1 pc : 2 Ps) (SNI:2837:2008-6.2)


1 Semen PC (50 Kg) 0.2045 zak 63,500 12,984
2 Pasir Pasang 0.0200 m3 135,000 2,700
a Pekerja 0.3000 Org/Hari 60,000 18,000
b Tukang Batu Kasar 0.1500 Org/Hari 80,000 12,000
c Kepala Tukang 0.0150 Org/Hari 80,000 1,200
d Mandor 0.0150 Org/Hari 95,000 1,425
JUMLAH 48,309

1 m2 Plesteran tebal= 1,5 (1 pc : 3 Ps) (SNI:2837:2008-6.3)


1 Semen PC (50 Kg) 0.1555 zak 63,500 9,876
2 Pasir Pasang 0.0230 m3 135,000 3,105
a Pekerja 0.3000 Org/Hari 60,000 18,000
b Tukang Batu Kasar 0.1500 Org/Hari 80,000 12,000
c Kepala Tukang 0.0150 Org/Hari 80,000 1,200
d Mandor 0.0150 Org/Hari 95,000 1,425
JUMLAH 45,606
1 m2 Plesteran tebal= 1,5 (1 pc : 4 Ps) (SNI:2837:2008-6.4)
1 Semen PC (50 Kg) 0.1248 zak 63,500 7,925
2 Pasir Pasang 0.0240 m3 135,000 3,240
a Pekerja 0.3000 Org/Hari 60,000 18,000
b Tukang Batu Kasar 0.1500 Org/Hari 80,000 12,000
c Kepala Tukang 0.0150 Org/Hari 80,000 1,200
d Mandor 0.0150 Org/Hari 95,000 1,425
JUMLAH 43,790

1 m2 Plesteran tebal= 1,5 (1 pc : 5 Ps) (SNI:2837:2008-6.5)


1 Semen PC (50 Kg) 0.1037 zak 63,500 6,584
2 Pasir Pasang 0.0260 m3 135,000 3,510
a Pekerja 0.3000 Org/Hari 60,000 18,000
b Tukang Batu Kasar 0.1500 Org/Hari 80,000 12,000
c Kepala Tukang 0.0150 Org/Hari 80,000 1,200
d Mandor 0.0150 Org/Hari 95,000 1,425
JUMLAH 42,719

1 m2 Plesteran tebal= 1,5 (1 pc : 6 Ps) (SNI:2837:2008-6.6)


1 Semen PC (50 Kg) 0.0883 zak 63,500 5,608
2 Pasir Pasang 0.0270 m3 135,000 3,645
a Pekerja 0.3000 Org/Hari 60,000 18,000
b Tukang Batu Kasar 0.1500 Org/Hari 80,000 12,000
c Kepala Tukang 0.0150 Org/Hari 80,000 1,200
d Mandor 0.0150 Org/Hari 95,000 1,425
JUMLAH 41,878

1 m2 Plesteran tebal= 2cm (1 pc : 2 Ps) (SNI:2837:2008-6.13)


1 Semen PC (50 Kg) 0.2726 zak 63,500 17,313
2 Pasir Pasang 0.0270 m3 135,000 3,645
a Pekerja 0.4000 Org/Hari 60,000 24,000
b Tukang Batu Kasar 0.2000 Org/Hari 80,000 16,000
c Kepala Tukang 0.0200 Org/Hari 80,000 1,600
d Mandor 0.0220 Org/Hari 95,000 2,090
JUMLAH 64,648

1 m2 Plesteran tebal= 2cm (1 pc : 3 Ps) (SNI:2837:2008-6.14)


1 Semen PC (50 Kg) 0.2074 zak 63,500 13,167
2 Pasir Pasang 0.0310 m3 135,000 4,185
a Pekerja 0.4000 Org/Hari 60,000 24,000
b Tukang Batu Kasar 0.2000 Org/Hari 80,000 16,000
c Kepala Tukang 0.0200 Org/Hari 80,000 1,600
d Mandor 0.0220 Org/Hari 95,000 2,090
JUMLAH 61,042

1 m2 Plesteran tebal= 2cm (1 pc : 4 Ps) (SNI:2837:2008-6.15)


1 Semen PC (50 Kg) 0.1664 zak 63,500 10,566
2 Pasir Pasang 0.0320 m3 135,000 4,320
a Pekerja 0.4000 Org/Hari 60,000 24,000
b Tukang Batu Kasar 0.2000 Org/Hari 80,000 16,000
c Kepala Tukang 0.0200 Org/Hari 80,000 1,600
d Mandor 0.0220 Org/Hari 95,000 2,090
JUMLAH 58,576
1 m2 Plesteran tebal= 2cm (1 pc : 5 Ps) (SNI:2837:2008-6.16)
1 Semen PC (50 Kg) 0.1382 zak 63,500 8,778
2 Pasir Pasang 0.0350 m3 135,000 4,725
a Pekerja 0.4000 Org/Hari 60,000 24,000
b Tukang Batu Kasar 0.2000 Org/Hari 80,000 16,000
c Kepala Tukang 0.0200 Org/Hari 80,000 1,600
d Mandor 0.0220 Org/Hari 95,000 2,090
JUMLAH 57,193

1 m1 Plesteran Sekoning 10mm (1 pc : 2 Ps) (SNI:2837:2008-6.20)


1 Semen PC (50 Kg) 0.0100 zak 63,500 635
2 Pasir Pasang 0.0130 m3 135,000 1,755
a Pekerja 0.0800 Org/Hari 60,000 4,800
b Tukang Batu Kasar 0.4000 Org/Hari 80,000 32,000
c Kepala Tukang 0.0400 Org/Hari 80,000 3,200
d Mandor 0.0040 Org/Hari 95,000 380
JUMLAH 42,770

1 m2 Plesteran Granit t=10mm (1 pc : 2 Ps) (SNI:2837:2008-6.21)


1 Semen PC (50 Kg) 0.2000 zak 63,500 12,700
2 Batu granit tumbuk 15.0000 Kg 12,000 180,000
a Pekerja 0.4500 Org/Hari 60,000 27,000
b Tukang Batu Kasar 0.2250 Org/Hari 80,000 18,000
c Kepala Tukang 0.0230 Org/Hari 80,000 1,840
d Mandor 0.0230 Org/Hari 95,000 2,185
JUMLAH 241,725

1 m2 Plesteran Teraso t=10mm (1 pc : 2 Ps) (SNI:2837:2008-6.22)


1 Semen PC (50 Kg) 0.2000 zak 63,500 12,700
2 Batu teraso tumbuk 15.0000 Kg 7,000 105,000
a Pekerja 0.4500 Org/Hari 60,000 27,000
b Tukang Batu Kasar 0.2250 Org/Hari 80,000 18,000
c Kepala Tukang 0.0230 Org/Hari 80,000 1,840
d Mandor 0.0230 Org/Hari 95,000 2,185
JUMLAH 166,725

1 m2 Plesteran Teraso Kamprot (1 pc : 2 Ps) (SNI:2837:2008-6.23)


1 Semen PC (50 Kg) 0.0864 zak 63,500 5,486
2 Pasir Pasang 0.0060 m3 135,000 810
a Pekerja 0.3000 Org/Hari 60,000 18,000
b Tukang Batu Kasar 0.1000 Org/Hari 80,000 8,000
c Kepala Tukang 0.0100 Org/Hari 80,000 800
d Mandor 0.0150 Org/Hari 95,000 1,425
JUMLAH 34,521

1 m2 Finishing siar bata merah (SNI:2837:2008-6.24)


1 Semen PC (50 Kg) 0.0622 zak 63,500 3,947
a Pekerja 0.1500 Org/Hari 60,000 9,000
b Tukang Batu Kasar 0.0750 Org/Hari 80,000 6,000
c Kepala Tukang 0.0080 Org/Hari 80,000 640
d Mandor 0.0080 Org/Hari 95,000 760
JUMLAH 20,347

1 m2 Finishing siar batako/bata conblok (SNI:2837:2008-6.25)


1 Semen PC (50 Kg) 0.0320 zak 63,500 2,032
a Pekerja 0.0700 Org/Hari 60,000 4,200
b Tukang Batu Kasar 0.0350 Org/Hari 80,000 2,800
c Kepala Tukang 0.0040 Org/Hari 80,000 320
d Mandor 0.0040 Org/Hari 95,000 380
JUMLAH 9,732
1 m2 Finishing siar pasangan batu kali ekspos (1PC:2PS) (SNI:2837:2008-6.26)
1 Semen PC (50 Kg) 0.1268 zak 63,500 8,052
2 Pasir Pasang 0.0120 m3 135,000 1,620
a Pekerja 0.3000 Org/Hari 60,000 18,000
b Tukang Batu Kasar 0.1500 Org/Hari 80,000 12,000
c Kepala Tukang 0.0150 Org/Hari 80,000 1,200
d Mandor 0.0150 Org/Hari 95,000 1,425
JUMLAH 42,297

1 m2 Acian (SNI:2837:2008-6.27)
1 Semen PC (50 Kg) 0.0650 zak 63,500 4,128
a Pekerja 0.2000 Org/Hari 60,000 12,000
b Tukang Batu Kasar 0.1000 Org/Hari 80,000 8,000
c Kepala Tukang 0.0100 Org/Hari 80,000 800
d Mandor 0.1000 Org/Hari 95,000 9,500
JUMLAH 34,428

G.PEKERJAAN FINISHING Lantai (SNI 7395:2008)

1 m2 Lantai Ubin PC abu-abu uk. 40X 40 cm (SNI:7395:2008-6.1)


2 Semen PC (50 Kg) 0.1960 zak 63,500 12,446
3 Pasir Pasang 0.0450 m3 135,000 6,075
a Pekerja 0.2500 Org/Hari 60,000 15,000
b Tukang Batu Kasar 0.1250 Org/Hari 80,000 10,000
c Kepala Tukang 0.0130 Org/Hari 80,000 1,040
d Mandor 0.0130 Org/Hari 95,000 1,235
JUMLAH 77,620

NOTE: Analisa harga diatas berlaku untuk material disebut dibawah ini ukuran 40 x 40cm
Ubin PC warna (SNI:7395:2008-6.4)

Ubin warna (SNI:7395:2008-6.7)

Ubin teraso (SNI:7395:2008-6.9)

Ubin granit (SNI:7395:2008-6.11)

Ubin teralux marmer (SNI:7395:2008-6.14)

1 m2 Lantai Keramik (uk. = 20x20 cm) (SNI:7395:2008-6.36)


1 Keramik Lantai 20/20 cm Unpolished 1.0600 m2 65,000 68,900
2 Semen PC (50 Kg) 0.2080 zak 90,000 18,720
3 Pasir Pasang 0.0450 m3 153,000 6,885
4 Semen Warna 1.5000 kg 8,000 12,000
a Pekerja 0.7000 Org/Hari 75,000 52,500
b Tukang Batu Kasar 0.3500 Org/Hari 100,000 35,000
c Kepala Tukang 0.0350 Org/Hari 115,000 4,025
d Mandor 0.0350 Org/Hari 115,000 4,025
JUMLAH 202,055

1 m2 Lantai Keramik (uk. = 30x30 cm)


1 Keramik Lantai 60/60 cm Unpolished 1.0683 m2 200,000 213,660
2 Semen PC (50 Kg) 0.2000 zak 63,500 12,700
3 Pasir Pasang 0.0450 m3 135,000 6,075
4 Semen Warna 1.5000 kg 12,500 18,750
a Pekerja 0.7000 Org/Hari 60,000 42,000
b Tukang Batu Kasar 0.3500 Org/Hari 80,000 28,000
c Kepala Tukang 0.0350 Org/Hari 80,000 2,800
d Mandor 0.0350 Org/Hari 95,000 3,325
JUMLAH 327,310
1 m2 Lantai Keramik (uk. = 33x33 cm) (SNI:7395:2008-6.34)
1 Keramik Lantai 60/60 cm Unpolished 1.0890 m2 75,000 81,675
2 Semen PC (50 Kg) 0.1638 zak 90,000 14,742
3 Pasir Pasang 0.0450 m3 153,000 6,885
4 Semen Warna 1.5000 kg 8,000 12,000
a Pekerja 0.7000 Org/Hari 75,000 52,500
b Tukang Batu Kasar 0.3500 Org/Hari 100,000 35,000
c Kepala Tukang 0.0350 Org/Hari 115,000 4,025
d Mandor 0.0350 Org/Hari 115,000 4,025
JUMLAH 210,852

1 m2 Lantai Keramik (uk. = 40x40 cm) (dihitung)


1 Keramik Lantai 40/40 cm Polished 1.1000 m2 90,000 99,000
2 Semen PC (50 Kg) 0.1960 zak 90,000 17,640
3 Pasir Pasang 0.0450 m3 153,000 6,885
4 Semen Warna 1.3000 kg 8,000 10,400
a Pekerja 0.7000 Org/Hari 75,000 52,500
b Tukang Batu Kasar 0.3500 Org/Hari 100,000 35,000
c Kepala Tukang 0.0350 Org/Hari 115,000 4,025
d Mandor 0.0350 Org/Hari 115,000 4,025
JUMLAH 229,475

1 m2 Lantai Keramik (uk. = 50x50 cm) (dihitung)


1 Keramik Lantai 50/50 cm Polished 1.1050 m2 51,500 56,908
2 Semen PC (50 Kg) 0.1940 zak 90,000 17,460
3 Pasir Pasang 0.0450 m3 153,000 6,885
4 Semen Warna 1.5000 kg 8,000 12,000
a Pekerja 0.7000 Org/Hari 75,000 52,500
b Tukang Batu Kasar 0.3500 Org/Hari 100,000 35,000
c Kepala Tukang 0.0350 Org/Hari 115,000 4,025
d Mandor 0.0350 Org/Hari 115,000 4,025
JUMLAH 188,803

1 m2 Lantai Keramik (uk. = 60x60 cm) (dihitung)


1 Keramik Lantai 60/60 cm Polished 1.1160 m2 75,000 83,700
2 Semen PC (50 Kg) 0.1920 zak 90,000 17,280
3 Pasir Pasang 0.0450 m3 153,000 6,885
4 Semen Warna 1.5000 kg 8,000 12,000
a Pekerja 0.7000 Org/Hari 75,000 52,500
b Tukang Batu Kasar 0.3500 Org/Hari 100,000 35,000
c Kepala Tukang 0.0350 Org/Hari 115,000 4,025
d Mandor 0.0350 Org/Hari 115,000 4,025
JUMLAH 215,415

1 m2 Lantai Keramik Border (uk. = 10x33cm) bo - NI:7395:2008-6.37)


1 Keramik Lantai 33/33 cm Polished 1.0890 m2 44,400 48,352
2 Semen PC (50 Kg) 0.1960 zak 90,000 17,640
3 Pasir Pasang 0.0450 m3 153,000 6,885
4 Semen Warna 4.3700 kg 8,000 34,960
a Pekerja 1.0500 Org/Hari 75,000 78,750
b Tukang Batu Kasar 0.5250 Org/Hari 100,000 52,500
c Kepala Tukang 0.0530 Org/Hari 115,000 6,095
d Mandor 0.0530 Org/Hari 115,000 6,095
JUMLAH 251,277
`
1 m2 Lantai Keramik Mozaik (uk. = 30x30 cm) mozaik (SNI:7395:2008-6.38)
1 Keramik Lantai 30/30 cm Polished 1.0683 m2 80,000 85,464
2 Semen PC (50 Kg) 0.2830 zak 90,000 25,470
3 Pasir Pasang 0.0390 m3 153,000 5,967
4 Semen Warna 2.0000 kg 8,000 16,000
a Pekerja 0.7000 Org/Hari 75,000 52,500
b Tukang Batu Kasar 0.3500 Org/Hari 100,000 35,000
c Kepala Tukang 0.0350 Org/Hari 115,000 4,025
d Mandor 0.0350 Org/Hari 115,000 4,025
JUMLAH 228,451
DIBULATKAN 228,400
`
1 m1 Plint Lantai Keramik (uk. = 10x20 cm) (SNI:7395:2008-6.39)
1 Keramik Lantai 20/20 cm Polished 0.1060 m2 65,000 6,890
2 Semen PC (50 Kg) 0.0228 zak 90,000 2,052
3 Pasir Pasang 0.0030 m3 153,000 459
4 Semen Warna 0.0250 kg 8,000 200
a Pekerja 0.0900 Org/Hari 75,000 6,750
b Tukang Batu Kasar 0.0900 Org/Hari 100,000 9,000
c Kepala Tukang 0.0090 Org/Hari 115,000 1,035
d Mandor 0.0050 Org/Hari 115,000 575
JUMLAH 26,961

1 m1 Plint Lantai Keramik (uk. = 10x10 cm) (SNI:7395:2008-6.40)


1 Keramik Lantai 20/20 cm Polished 0.1060 m2 65,000 6,890
2 Semen PC (50 Kg) 0.0228 zak 90,000 2,052
3 Pasir Pasang 0.0030 m3 153,000 459
4 Semen Warna 0.0500 kg 8,000 400
a Pekerja 0.0900 Org/Hari 75,000 6,750
b Tukang Batu Kasar 0.0900 Org/Hari 100,000 9,000
c Kepala Tukang 0.0090 Org/Hari 115,000 1,035
d Mandor 0.0050 Org/Hari 115,000 575
JUMLAH 27,161
`
1 m1 Plint Lantai Keramik (uk. = 5X20 cm) (SNI:7395:2008-6.41)
1 Keramik Lantai 20/20 cm Polished 0.0530 m2 65,000 3,445
2 Semen PC (50 Kg) 0.0114 zak 90,000 1,026
3 Pasir Pasang 0.0015 m3 153,000 230
4 Semen Warna 0.0130 kg 8,000 104
a Pekerja 0.0900 Org/Hari 75,000 6,750
b Tukang Batu Kasar 0.0900 Org/Hari 100,000 9,000
c Kepala Tukang 0.0090 Org/Hari 115,000 1,035
d Mandor 0.0050 Org/Hari 115,000 575
JUMLAH 22,165
`
1 m1 Plint Lantai Keramik (uk. = 10x30 cm) (dihitung)
1 Keramik Lantai 30/30 cm Polished 0.1050 m2 80,000 8,400
2 Semen PC (50 Kg) 0.0228 zak 90,000 2,052
3 Pasir Pasang 0.0030 m3 153,000 459
4 Semen Warna 0.0250 kg 8,000 200
a Pekerja 0.0900 Org/Hari 75,000 6,750
b Tukang Batu Kasar 0.0900 Org/Hari 100,000 9,000
c Kepala Tukang 0.0090 Org/Hari 115,000 1,035
d Mandor 0.0050 Org/Hari 115,000 575
JUMLAH 28,471
`
1 m1 Plint Lantai Keramik (uk. = 10x33 cm) (dihitung)
1 Keramik Lantai 33/33 cm Polished 0.1056 m2 44,400 4,689
2 Semen PC (50 Kg) 0.0228 zak 90,000 2,052
3 Pasir Pasang 0.0030 m3 153,000 459
4 Semen Warna 0.0250 kg 8,000 200
a Pekerja 0.0900 Org/Hari 75,000 6,750
b Tukang Batu Kasar 0.0900 Org/Hari 100,000 9,000
c Kepala Tukang 0.0090 Org/Hari 115,000 1,035
d Mandor 0.0050 Org/Hari 115,000 575
JUMLAH 24,760

1 m1 Plint Lantai Keramik (uk. = 10x40 cm) (dihitung)


1 Keramik Lantai 40/40 cm Polished 0.1052 m2 90,000 9,468
2 Semen PC (50 Kg) 0.0228 zak 90,000 2,052
3 Pasir Pasang 0.0030 m3 153,000 459
4 Semen Warna 0.0250 kg 8,000 200
a Pekerja 0.0900 Org/Hari 75,000 6,750
b Tukang Batu Kasar 0.0900 Org/Hari 100,000 9,000
c Kepala Tukang 0.0090 Org/Hari 115,000 1,035
d Mandor 0.0050 Org/Hari 115,000 575
JUMLAH 29,539
`
1 m1 Plint Lantai Keramik (uk. = 10x50 cm) (dihitung)
1 Keramik Lantai 50/50 cm Polished 0.1050 m2 51,500 5,408
2 Semen PC (50 Kg) 0.0228 zak 90,000 2,052
3 Pasir Pasang 0.0030 m3 153,000 459
4 Semen Warna 0.0250 kg 8,000 200
a Pekerja 0.0900 Org/Hari 75,000 6,750
b Tukang Batu Kasar 0.0900 Org/Hari 100,000 9,000
c Kepala Tukang 0.0090 Org/Hari 115,000 1,035
d Mandor 0.0050 Org/Hari 115,000 575
JUMLAH 25,479
`
1 m1 Plint Lantai Keramik (uk. = 10x60 cm) (dihitung)
1 Keramik Lantai 60/60 cm Polished 0.1050 m2 75,000 7,875
2 Semen PC (50 Kg) 0.0228 zak 90,000 2,052
3 Pasir Pasang 0.0030 m3 153,000 459
4 Semen Warna 0.0250 kg 8,000 200
a Pekerja 0.0900 Org/Hari 75,000 6,750
b Tukang Batu Kasar 0.0900 Org/Hari 100,000 9,000
c Kepala Tukang 0.0090 Org/Hari 115,000 1,035
d Mandor 0.0050 Org/Hari 115,000 575
JUMLAH 27,946
`
1 m1 Plint Lantai Internal Cove (SNI:2837:2008-6.42)
1 Internal Cove (Plint) 1.0500 m1 27,500 28,875
2 Semen PC (50 Kg) 0.0228 zak 63,500 1,448
3 Pasir Pasang 0.0030 m3 135,000 405
4 Semen Warna 0.1000 kg 12,500 1,250
a Pekerja 0.0750 Org/Hari 60,000 4,500
b Tukang Batu Kasar 0.0750 Org/Hari 80,000 6,000
c Kepala Tukang 0.0075 Org/Hari 80,000 600
d Mandor 0.0038 Org/Hari 95,000 361
JUMLAH 43,439
`
1 m2 Lantai Marmer (uk. =100x100 cm) (SNI:2837:2008-6.43)
1 Lantai Marmer 1.0600 m2 190,000 201,400
2 Semen PC (50 Kg) 0.1638 zak 63,500 10,401
3 Pasir Pasang 0.0450 m3 135,000 6,075
4 Semen Warna 0.6500 kg 12,500 8,125
a Pekerja 0.7000 Org/Hari 60,000 42,000
b Tukang Batu Kasar 0.3500 Org/Hari 80,000 28,000
c Kepala Tukang 0.0350 Org/Hari 80,000 2,800
d Mandor 0.0350 Org/Hari 95,000 3,325
JUMLAH 302,126
`
1 m2 Lantai Batu Andesit (uk. =100x100 cm)
1 Batu Andesit 30x30 1.0600 m2 150,000 159,000
2 Semen PC (50 Kg) 0.1638 zak 63,500 10,401
3 Pasir Pasang 0.0450 m3 135,000 6,075
4 Semen Warna 0.6500 kg 12,500 8,125
a Pekerja 0.7000 Org/Hari 60,000 42,000
b Tukang Batu Kasar 0.3500 Org/Hari 80,000 28,000
c Kepala Tukang 0.0350 Org/Hari 80,000 2,800
d Mandor 0.0350 Org/Hari 95,000 3,325
JUMLAH 259,726
`
1 m2 Lantai Karpet (SNI:2837:2008-6.44)
1 Karpet Lantai Roll 1.0500 m2 76,000 79,800
2 Lem Karpet 0.3500 Kg 27,500 9,625
a Pekerja 0.1700 Org/Hari 60,000 10,200
b Tukang Batu Kasar 0.1700 Org/Hari 80,000 13,600
c Kepala Tukang 0.0170 Org/Hari 80,000 1,360
d Mandor 0.0090 Org/Hari 95,000 855
JUMLAH 115,440
`
1 m2 Pelapis bawah / Underlayer (SNI:2837:2008-6.45)
1 Underlayer/rubber corrugated 1.0500 m2 12,000 12,600
2 Lem Karpet 0.3500 Kg 27,500 9,625
a Pekerja 0.1200 Org/Hari 60,000 7,200
b Tukang Batu Kasar 0.1200 Org/Hari 80,000 9,600
c Kepala Tukang 0.0120 Org/Hari 80,000 960
d Mandor 0.0060 Org/Hari 95,000 570
JUMLAH 40,555
`
1 m2 Lantai Parquette Kayu (SNI:2837:2008-6.46)
1 Lantai Parquette Laminated 1.0500 m2 176,000 184,800
2 Lem Kayu 0.6000 Kg 62,500 37,500
a Pekerja 0.7000 Org/Hari 60,000 42,000
b Tukang Batu Kasar 0.3500 Org/Hari 80,000 28,000
c Kepala Tukang 0.0350 Org/Hari 80,000 2,800
d Mandor 0.0350 Org/Hari 95,000 3,325
JUMLAH 298,425
`
1 m2 Lantai Kayu Gymfloor (SNI:2837:2008-6.47)
1 Lantai Parquette 1.0500 m2 600,000 630,000
2 Lem Kayu 0.6000 Kg 62,500 37,500
a Pekerja 0.7000 Org/Hari 60,000 42,000
b Tukang Batu Kasar 0.3500 Org/Hari 80,000 28,000
c Kepala Tukang 0.0350 Org/Hari 80,000 2,800
d Mandor 0.0350 Org/Hari 95,000 3,325
JUMLAH 743,625
1 m2 Lantai Vinyl (SNI:2837:2008-6.59)
1 Lantai Vinyl Roll 1.0500 m2 35,000 36,750
2 Lem Vinyl 0.3500 Kg 15,000 5,250
a Pekerja 0.1500 Org/Hari 60,000 9,000
b Tukang Batu Kasar 0.1500 Org/Hari 80,000 12,000
c Kepala Tukang 0.0150 Org/Hari 80,000 1,200
d Mandor 0.0080 Org/Hari 95,000 760
JUMLAH 64,960

1 m1 Plint Lantai Vinyl (SNI:2837:2008-6.62)


1 Plint Lantai Vinyl 1.0500 m1 15,000 15,750
2 Lem Vinyl 0.3500 Kg 15,000 5,250
a Pekerja 0.0800 Org/Hari 60,000 4,800
b Tukang Batu Kasar 0.0800 Org/Hari 80,000 6,400
c Kepala Tukang 0.0080 Org/Hari 80,000 640
d Mandor 0.0040 Org/Hari 95,000 380
JUMLAH 33,220

1 m1 Plint Lantai Kayu (tinggi =10 cm, tebal =0.9 – 1,2 cm) (SNI:2837:2008-6.63)
1 Kayu Kuat klas II 0.0013 m3 9,500,000 11,970
2 Paku 1 s/d 3 cm 0.0500 kg 20,020 1,001
a Pekerja 0.1200 Org/Hari 60,000 7,200
b Tukang Batu Kasar 0.1200 Org/Hari 80,000 9,600
c Kepala Tukang 0.0120 Org/Hari 80,000 960
d Mandor 0.0060 Org/Hari 95,000 570
JUMLAH 31,301

1 m2 Lantai floor hardener (SNI:2837:2008-6.61)


1 Floor Hardener 5.0000 Kg 4,480 22,400
a Pekerja 0.1200 Org/Hari 60,000 7,200
b Tukang Batu Kasar 0.1200 Org/Hari 80,000 9,600
c Kepala Tukang 0.0120 Org/Hari 80,000 960
d Mandor 0.0060 Org/Hari 95,000 570
JUMLAH 40,730

1 m2 Lantai Koral Sikat (SNI:2837:2008-6.61)


1 Batu koral sikat terpasang 1.0000 m2 325,000 325,000
a Pekerja 0.1200 Org/Hari 60,000 7,200
b Tukang Batu Kasar 0.1200 Org/Hari 80,000 9,600
c Kepala Tukang 0.0120 Org/Hari 80,000 960
d Mandor 0.0060 Org/Hari 95,000 570
JUMLAH 343,330

H.PEKERJAAN FINISHING DINDING (SNI 7395:2008)

1 m2 Dinding Porselen (uk. = 11x11 cm)P (SNI:7395:2008-6.48)


1 Dinding Porselen 11/11 cm 1.0406 m2 25,000 26,015
2 Semen PC (50 Kg) 0.1860 zak 90,000 16,740
3 Pasir Pasang 0.0180 m3 153,000 2,754
4 Semen Warna 1.5000 kg 8,000 12,000
a Pekerja 0.1000 Org/Hari 75,000 7,500
b Tukang Batu Kasar 0.0500 Org/Hari 100,000 5,000
c Kepala Tukang 0.0050 Org/Hari 115,000 575
d Mandor 0.0050 Org/Hari 115,000 575
JUMLAH 71,159
1 m2 Dinding Porselen (uk. = 10x20 cm)P (SNI:7395:2008-6.49)
1 Dinding Porselen 10/20 cm 1.0600 m2 28,000 29,680
2 Semen PC (50 Kg) 0.1860 zak 90,000 16,740
3 Pasir Pasang 0.0180 m3 153,000 2,754
4 Semen Warna 2.7500 kg 8,000 22,000
a Pekerja 0.0900 Org/Hari 75,000 6,750
b Tukang Batu Kasar 0.0450 Org/Hari 100,000 4,500
c Kepala Tukang 0.0045 Org/Hari 115,000 518
d Mandor 0.0045 Org/Hari 115,000 518
JUMLAH 83,459

1 m2 Dinding Keramik (uk. = 20x20 cm)K (SNI:7395:2008-6.54)


1 Keramik Dinding 20/20 cm Polished 1.0600 m2 100,000 106,000
2 Semen PC (50 Kg) 0.1860 zak 90,000 16,740
3 Pasir Pasang 0.0180 m3 153,000 2,754
4 Semen Warna 1.9400 kg 8,000 15,520
a Pekerja 0.6000 Org/Hari 75,000 45,000
b Tukang Batu Kasar 0.4500 Org/Hari 100,000 45,000
c Kepala Tukang 0.0450 Org/Hari 115,000 5,175
d Mandor 0.0350 Org/Hari 115,000 4,025
JUMLAH 240,214

1 m2 Dinding Keramik Artistik (uk. = 10x20 cm)KA (SNI:7395:2008-6.51)


1 Keramik Dinding Artistik 10/20 cm Polished 1.0600 m2 200,000 212,000
2 Semen PC (50 Kg) 0.1860 zak 90,000 16,740
3 Pasir Pasang 0.0180 m3 153,000 2,754
4 Semen Warna 2.7500 kg 8,000 22,000
a Pekerja 0.0900 Org/Hari 75,000 6,750
b Tukang Batu Kasar 0.0450 Org/Hari 100,000 4,500
c Kepala Tukang 0.0045 Org/Hari 115,000 518
d Mandor 0.0045 Org/Hari 115,000 518
JUMLAH 265,779

1 m2 Dinding Keramik Artistik (uk. = 5x20 cm)KA (SNI:7395:2008-6.52)


1 Keramik Dinding Artistik 5/20 cm Polished 1.0600 m2 240,000 254,400
2 Semen PC (50 Kg) 0.1860 zak 90,000 16,740
3 Pasir Pasang 0.1800 m3 153,000 27,540
4 Semen Warna 2.9000 kg 8,000 23,200
a Pekerja 0.0900 Org/Hari 75,000 6,750
b Tukang Batu Kasar 0.0450 Org/Hari 100,000 4,500
c Kepala Tukang 0.0045 Org/Hari 115,000 518
d Mandor 0.0045 Org/Hari 115,000 518
JUMLAH 334,165

1 m2 Dinding Keramik (uk. = 10x20 cm)K (SNI:7395:2008-6.53)


1 Dinding Porselen 20/20 cm 1.0600 m2 29,500 31,270
2 Semen PC (50 Kg) 0.1860 zak 90,000 16,740
3 Pasir Pasang 0.0180 m3 153,000 2,754
4 Semen Warna 2.7500 kg 8,000 22,000
a Pekerja 0.0900 Org/Hari 75,000 6,750
b Tukang Batu Kasar 0.0450 Org/Hari 100,000 4,500
c Kepala Tukang 0.0045 Org/Hari 115,000 518
115,000 518
JUMLAH 85,049
1 m2 Dinding Keramik (uk. = 20x20 cm)K (SNI:7395:2008-6.54)
1 Keramik Dinding 20/20 cm Polished 1.0600 m2 100,000 106,000
2 Semen PC (50 Kg) 0.1860 zak 90,000 16,740
3 Pasir Pasang 0.0180 m3 153,000 2,754
4 Semen Warna 1.9400 kg 8,000 15,520
a Pekerja 0.6000 Org/Hari 75,000 45,000
b Tukang Batu Kasar 0.4500 Org/Hari 100,000 45,000
c Kepala Tukang 0.0450 Org/Hari 115,000 5,175
d Mandor 0.0350 Org/Hari 115,000 4,025
JUMLAH 240,214
0
1 m2 Dinding Keramik (uk. = 20x25 cm)K (SNI:7395:2008-6.54)R
1 Keramik Dinding 20/25 cm Polished 1.0600 m2 90,000 95,400
2 Semen PC (50 Kg) 0.1860 zak 90,000 16,740
3 Pasir Pasang 0.0180 m3 153,000 2,754
4 Semen Warna 1.9400 kg 8,000 15,520
a Pekerja 0.0900 Org/Hari 75,000 6,750
b Tukang Batu Kasar 0.0450 Org/Hari 100,000 4,500
c Kepala Tukang 0.0045 Org/Hari 115,000 518
d Mandor 0.0045 Org/Hari 115,000 518
JUMLAH 142,699

1 m2 Dinding Keramik (uk. = 20x25 cm)K (SNI:7395:2008-6.54)R


1 Keramik Dinding 20/25 cm Polished 1.0600 m2 90,000 95,400
2 Semen PC (50 Kg) 0.1860 zak 90,000 16,740
3 Pasir Pasang 0.0180 m3 153,000 2,754
4 Semen Warna 1.9400 kg 8,000 15,520
a Pekerja 0.0900 Org/Hari 75,000 6,750
b Tukang Batu Kasar 0.0450 Org/Hari 100,000 4,500
c Kepala Tukang 0.0045 Org/Hari 115,000 518
d Mandor 0.0045 Org/Hari 115,000 518
JUMLAH 142,699
0
1 m2 Dinding Keramik (uk. = 30x30 cm)K (SNI:7395:2008-6.54)R
1 Keramik Dinding 30/30 cm Polished 1.0600 m2 90,000 95,400
2 Semen PC (50 Kg) 0.1860 zak 90,000 16,740
3 Pasir Pasang 0.0180 m3 153,000 2,754
4 Semen Warna 1.5000 kg 8,000 12,000
a Pekerja 0.0900 Org/Hari 75,000 6,750
b Tukang Batu Kasar 0.0450 Org/Hari 100,000 4,500
c Kepala Tukang 0.0045 Org/Hari 115,000 518
d Mandor 0.0045 Org/Hari 115,000 518
JUMLAH 139,179

1 m2 Dinding Marmer (uk. = 100x100 cm) (SNI:2835:2008-6.55)


1 Dinding Marmer 100/100 cm 1.0600 m2 280,800 297,648
2 Paku 8 s/d 12 cm 0.0375 kg 36,000 1,351
3 Semen PC (50 Kg) 0.2488 zak 63,500 15,799
4 Pasir Pasang 0.0250 m3 135,000 3,375
5 Semen Warna 0.6500 kg 12,500 8,125
a Pekerja 1.3000 Org/Hari 60,000 78,000
b Tukang Batu Kasar 0.6500 Org/Hari 80,000 52,000
c Kepala Tukang 0.0650 Org/Hari 80,000 5,200
d Mandor 0.0650 Org/Hari 95,000 6,175
JUMLAH 467,673
1 m2 Dinding Batu Bata Pelapis (3x7x24 cm) (SNI:2835:2008-6.56)
1 Bata pelapis (3x7x24cm) 1.0600 m2 117,000 124,020
2 Semen PC (50 Kg) 0.2488 zak 63,500 15,799
3 Pasir Pasang 0.0250 m3 135,000 3,375
4 Semen Warna 2.7500 kg 12,500 34,375
a Pekerja 1.0000 Org/Hari 60,000 60,000
b Tukang Batu Kasar 0.5000 Org/Hari 80,000 40,000
c Kepala Tukang 0.0500 Org/Hari 80,000 4,000
d Mandor 0.0500 Org/Hari 95,000 4,750
JUMLAH 286,319

1 m2 Dinding Batu Paras (SNI:2835:2008-6.57)


1 Batu paras tempel 1.0600 m2 162,500 172,250
2 Semen PC (50 Kg) 0.2350 zak 63,500 14,923
3 Pasir Pasang 0.0350 m3 135,000 4,725
a Pekerja 0.7000 Org/Hari 60,000 42,000
b Tukang Batu Kasar 0.3500 Org/Hari 80,000 28,000
c Kepala Tukang 0.0350 Org/Hari 80,000 2,800
d Mandor 0.0350 Org/Hari 95,000 3,325
JUMLAH 268,023

1 m2 Dinding Batu Tempel (SNI:2835:2008-6.58)


1 Batu Andesit 30x30 1.0600 m2 150,000 159,000
2 Semen PC (50 Kg) 0.2488 zak 63,500 15,799
3 Pasir Pasang 0.0250 m3 135,000 3,375
a Pekerja 1.0000 Org/Hari 60,000 60,000
b Tukang Batu Kasar 0.5000 Org/Hari 80,000 40,000
c Kepala Tukang 0.0500 Org/Hari 80,000 4,000
d Mandor 0.0500 Org/Hari 95,000 4,750
JUMLAH 286,924

1 m2 Wallpaper lebar 50cm (SNI:2835:2008-6.60)


1 Wallpaper artistik 0.4400 roll 123,500 54,340
2 Lem Wallpaper 0.2500 Kg 9,000 2,250
a Pekerja 0.3500 Org/Hari 60,000 21,000
b Tukang Batu Kasar 0.1750 Org/Hari 80,000 14,000
c Kepala Tukang 0.0170 Org/Hari 80,000 1,360
d Mandor 0.0020 Org/Hari 95,000 190
JUMLAH 93,140

1 m2 Dinding Glassblock 20x20 cm (SNI:2835:2008-6.58)


1 Glass Block 25.0000 bh 3,000 75,000
2 Semen PC (50 Kg) 0.2200 zak 63,500 13,970
3 Pasir Pasang 0.0350 m3 135,000 4,725
4 Sealant Kaca 0.2488 kg 45,000 11,196
a Pekerja 0.3000 Org/Hari 60,000 18,000
b Tukang Batu Kasar 0.1000 Org/Hari 80,000 8,000
c Kepala Tukang 0.0100 Org/Hari 80,000 800
d Mandor 0.0150 Org/Hari 95,000 1,425
JUMLAH 133,116
I.PEKERJAAN KAYU (SNI 3434:2008)
I.1. PEKERJAAN KUSEN, PINTU & JENDELA
1 m3 Membuat & memasang kusen pintu & jendela Kayu kelas I (SNI:3434:2008-6.1)
1 Kayu Kuat klas I 1.1000 m3 16,000,000 17,600,000
2 Paku 8 s/d 12 cm 1.2500 kg 36,000 45,000
3 Lem Kayu 1.0000 Kg 62,500 62,500
a Pekerja 7.0000 Org/Hari 60,000 420,000
b Tukang Kayu Halus 21.0000 Org/Hari 80,000 1,680,000
c Kepala Tukang 2.1000 Org/Hari 80,000 168,000
d Mandor 0.3500 Org/Hari 95,000 33,250
JUMLAH 20,008,750

1 m3 Membuat & memasang kusen pintu & jendela Kayu kelas II (SNI:3434:2008-6.2)
1 Kayu Kuat klas II 1.2000 m3 9,500,000 11,400,000
2 Paku 8 s/d 12 cm 1.2500 kg 36,000 45,000
3 Lem Kayu 1.0000 Kg 62,500 62,500
a Pekerja 6.0000 Org/Hari 60,000 360,000
b Tukang Kayu Halus 18.0000 Org/Hari 80,000 1,440,000
c Kepala Tukang 1.8000 Org/Hari 80,000 144,000
d Mandor 0.3000 Org/Hari 95,000 28,500
JUMLAH 13,480,000

1 m2 Membuat & memasang daun pintu Klamp Kayu kelas II (SNI:3434:2008-6.3)


1 Kayu Kuat klas II 0.0400 m3 9,500,000 380,000
2 Paku 4 s/d 7 cm 0.0500 kg 36,000 1,800
a Pekerja 0.3500 Org/Hari 60,000 21,000
b Tukang Kayu Halus 1.0500 Org/Hari 80,000 84,000
c Kepala Tukang 0.1050 Org/Hari 80,000 8,400
d Mandor 0.0180 Org/Hari 95,000 1,710
JUMLAH 496,910

1 m2 Membuat & memasang daun pintu Klamp Kayu kelas III (SNI:3434:2008-6.4)
1 Kayu Kuat klas III 0.0400 m3 2,335,667 93,427
2 Paku 4 s/d 7 cm 0.0500 kg 36,000 1,800
a Pekerja 0.3500 Org/Hari 60,000 21,000
b Tukang Kayu Halus 1.0500 Org/Hari 80,000 84,000
c Kepala Tukang 0.1050 Org/Hari 80,000 8,400
d Mandor 0.0180 Org/Hari 95,000 1,710
JUMLAH 210,337

1 m2 Membuat & memasang daun pintu Panel Kayu kelas I (SNI:3434:2008-6.5)


1 Kayu Kuat klas I 0.0400 m3 16,000,000 640,000
2 Lem Kayu 0.0500 Kg 62,500 3,125
a Pekerja 1.0000 Org/Hari 60,000 60,000
b Tukang Kayu Halus 3.0000 Org/Hari 80,000 240,000
c Kepala Tukang 0.3000 Org/Hari 80,000 24,000
d Mandor 0.0500 Org/Hari 95,000 4,750
JUMLAH 971,875

1 m2 Membuat & memasang daun pintu & jendela kaca Kayu kelas I (SNI:3434:2008-6.6)
1 Kayu Kuat klas I 0.0240 m3 16,000,000 384,000
2 Lem Kayu 0.5000 Kg 62,500 31,250
a Pekerja 0.8000 Org/Hari 60,000 48,000
b Tukang Kayu Halus 2.4000 Org/Hari 80,000 192,000
c Kepala Tukang 0.2400 Org/Hari 80,000 19,200
d Mandor 0.0400 Org/Hari 95,000 3,800
JUMLAH 678,250
1 m2 Membuat & memasang daun pintu & jendela jalusi Kayu kelas I (SNI:3434:2008-6.7)
1 Kayu Kuat klas I 0.0640 m3 16,000,000 1,024,000
2 Lem Kayu 0.5000 Kg 62,500 31,250
a Pekerja 1.0000 Org/Hari 60,000 60,000
b Tukang Kayu Halus 3.0000 Org/Hari 80,000 240,000
c Kepala Tukang 0.3000 Org/Hari 80,000 24,000
d Mandor 0.0500 Org/Hari 95,000 4,750
JUMLAH 1,384,000

1 m2 Membuat & memasang daun pintu dobel Plywood, Rangka kelas II (SNI:3434:2008-6.8)
1 Kayu Kuat klas II 0.0250 m3 9,500,000 237,500
2 Paku 1 s/d 3 cm 0.0300 kg 20,020 601
3 Lem Kayu 0.5000 Kg 62,500 31,250
4 Triplex t. 4 mm 1.0000 lbr 54,000 54,000
a Pekerja 0.7000 Org/Hari 60,000 42,000
b Tukang Kayu Halus 2.1000 Org/Hari 80,000 168,000
c Kepala Tukang 0.2100 Org/Hari 80,000 16,800
d Mandor 0.0350 Org/Hari 95,000 3,325
JUMLAH 553,476

1 m2 Membuat & memasang daun pintu dobel Plywood, Rangka Expose kelas II (SNI:3434:2008-6.9)
1 Kayu Kuat klas II 0.0256 m3 9,500,000 243,200
2 Paku 1 s/d 3 cm 0.0300 kg 20,020 601
3 Lem Kayu 0.5000 Kg 62,500 31,250
4 Triplex t. 4 mm 1.0000 lbr 54,000 54,000
a Pekerja 0.8000 Org/Hari 60,000 48,000
b Tukang Kayu Halus 2.4000 Org/Hari 80,000 192,000
c Kepala Tukang 0.2400 Org/Hari 80,000 19,200
d Mandor 0.0400 Org/Hari 95,000 3,800
JUMLAH 592,051

1 m2 Membuat & memasang kusen jalusi Kayu kelas I (SNI:3434:2008-6.10)


1 Kayu Kuat klas I 0.0600 m3 16,000,000 960,000
2 Paku 1 s/d 3 cm 0.1500 kg 20,020 3,003
a Pekerja 0.6700 Org/Hari 60,000 40,200
b Tukang Kayu Halus 2.0000 Org/Hari 80,000 160,000
c Kepala Tukang 0.2000 Org/Hari 80,000 16,000
d Mandor 0.3350 Org/Hari 95,000 31,825
JUMLAH 1,211,028

1 m2 Membuat & memasang Teakwood rangkap, rangka expose Kayu kelas I (SNI:3434:2008-6.11)
1 Kayu Kuat klas II 0.0250 m3 9,500,000 237,500
2 Paku 1 s/d 3 cm 0.0300 kg 20,020 601
3 Lem Kayu 0.3000 Kg 62,500 18,750
4 Teakwood t. 6 mm 1.0000 lbr 60,000 60,000
a Pekerja 0.8000 Org/Hari 60,000 48,000
b Tukang Kayu Halus 2.4000 Org/Hari 80,000 192,000
c Kepala Tukang 0.2400 Org/Hari 80,000 19,200
d Mandor 0.0400 Org/Hari 95,000 3,800
JUMLAH 579,851
1 m2 Membuat & memasang Teakwood rangkap lapis HPL, rangka expose Kayu kelas I (SNI:3434:2008-6.12)
1 Kayu Kuat klas II 0.0250 m3 9,500,000 237,500
2 Paku 1 s/d 3 cm 0.0300 kg 20,020 601
3 Lem Kayu 0.8000 Kg 62,500 50,000
4 Teakwood t. 3 mm 1.0000 lbr 78,000 78,000
5 Finish Melamik 0.5000 m2 110,500 55,250
a Pekerja 0.8500 Org/Hari 60,000 51,000
b Tukang Kayu Halus 2.5500 Org/Hari 80,000 204,000
c Kepala Tukang 0.2550 Org/Hari 80,000 20,400
d Mandor 0.0430 Org/Hari 95,000 4,085
JUMLAH 700,836

I.2. PEKERJAAN ATAP

1 m3 Membuat & memasang Konstruksi kuda-kuda Kayu bentang s/d 6M (SNI:3434:2008-6.13)


1 Kayu Kuat klas II 1.1000 m3 9,500,000 10,450,000
2 Plat Strip 15.0000 Kg 14,690 220,345
3 Paku 8 s/d 12 cm 5.6000 kg 36,000 201,600
a Pekerja 4.0000 Org/Hari 60,000 240,000
b Tukang Kayu Halus 12.0000 Org/Hari 80,000 960,000
c Kepala Tukang 1.2000 Org/Hari 80,000 96,000
d Mandor 0.2000 Org/Hari 95,000 19,000
JUMLAH 12,186,945

1 m3 Membuat & memasang Konstruksi kuda-kuda Kayu Ekspose (SNI:3434:2008-6.14)


1 Kayu Kuat klas I 1.2000 m3 16,000,000 19,200,000
2 Plat Strip 15.0000 Kg 14,690 220,345
3 Paku 8 s/d 12 cm 5.6000 kg 36,000 201,600
a Pekerja 6.7000 Org/Hari 60,000 402,000
b Tukang Kayu Halus 20.1000 Org/Hari 80,000 1,608,000
c Kepala Tukang 2.0100 Org/Hari 80,000 160,800
d Mandor 0.3350 Org/Hari 95,000 31,825
JUMLAH 21,824,570

1 m3 Membuat & memasang Gordeng, Kayu kelas II (SNI:3434:2008-6.15)


1 Kayu Kuat klas II 1.1000 m3 9,500,000 10,450,000
2 Plat Strip 15.0000 Kg 14,690 220,345
3 Paku 8 s/d 12 cm 3.0000 kg 36,000 108,000
a Pekerja 2.4000 Org/Hari 60,000 144,000
b Tukang Kayu Halus 7.2000 Org/Hari 80,000 576,000
c Kepala Tukang 0.7200 Org/Hari 80,000 57,600
d Mandor 0.1200 Org/Hari 95,000 11,400
JUMLAH 11,567,345

1 m2 Membuat & memasang rangka atap genteng Keramik, kayu kelas II (SNI:3434:2008-6.16)
1 Kaso kelas II 0.0140 m3 9,500,000 133,000
2 Kayu Reng 3/4 Kamper Samarinda 0.0036 m3 9,500,000 34,200
3 Paku 4 s/d 7 cm 0.2500 kg 36,000 9,000
a Pekerja 0.1000 Org/Hari 60,000 6,000
b Tukang Kayu Halus 0.1000 Org/Hari 80,000 8,000
c Kepala Tukang 0.0100 Org/Hari 80,000 800
d Mandor 0.0050 Org/Hari 95,000 475
JUMLAH 191,475
1 m2 Membuat & memasang rangka atap genteng Beton, kayu kelas II (SNI:3434:2008-6.17)
1 Kaso kelas II 0.0140 m3 9,500,000 133,000
2 Kayu Reng 3/4 Kamper Samarinda 0.0072 m3 9,500,000 68,400
3 Paku 4 s/d 7 cm 0.2500 kg 36,000 9,000
a Pekerja 0.1000 Org/Hari 60,000 6,000
b Tukang Kayu Halus 0.1000 Org/Hari 80,000 8,000
c Kepala Tukang 0.0100 Org/Hari 80,000 800
d Mandor 0.0050 Org/Hari 95,000 475
JUMLAH 225,675

1 m2 Membuat & memasang rangka atap Sirap, kayu kelas II (SNI:3434:2008-6.18)


1 Kaso kelas II 0.1650 m3 9,500,000 1,567,500
2 Paku 4 s/d 7 cm 0.2000 kg 36,000 7,200
a Pekerja 0.1200 Org/Hari 60,000 7,200
b Tukang Kayu Halus 0.1200 Org/Hari 80,000 9,600
c Kepala Tukang 0.0120 Org/Hari 80,000 960
d Mandor 0.0060 Org/Hari 95,000 570
JUMLAH 1,593,030

1 m1 Membuat & memasang Lisplank (3x20cm), Kayu kelas II (SNI:3434:2008-6.21)


1 Papan kelas II 0.0108 m3 9,500,000 102,600
2 Paku 4 s/d 7 cm 0.1000 kg 36,000 3,600
a Pekerja 0.1000 Org/Hari 60,000 6,000
b Tukang Kayu Halus 0.2000 Org/Hari 80,000 16,000
c Kepala Tukang 0.0200 Org/Hari 80,000 1,600
d Mandor 0.0050 Org/Hari 95,000 475
JUMLAH 130,275

1 m1 Membuat & memasang Lisplank (3x30cm), Kayu kelas II (SNI:3434:2008-6.22)


1 Papan kelas II 0.0110 m3 9,500,000 104,500
2 Paku 4 s/d 7 cm 0.0500 kg 36,000 1,800
a Pekerja 0.1000 Org/Hari 60,000 6,000
b Tukang Kayu Halus 0.2000 Org/Hari 80,000 16,000
c Kepala Tukang 0.0200 Org/Hari 80,000 1,600
d Mandor 0.0050 Org/Hari 95,000 475
JUMLAH 130,375

I.3. PEKERJAAN RANGKA PLAFOND

1 m2 Membuat & memasang rangka plafond (50x100cm), Kayu kelas II (SNI:3434:2008-6.19)


1 Kaso kelas II 0.0154 m3 9,500,000 146,300
2 Paku 4 s/d 7 cm 0.2000 kg 36,000 7,200
a Pekerja 0.1500 Org/Hari 60,000 9,000
b Tukang Kayu Halus 0.3000 Org/Hari 80,000 24,000
c Kepala Tukang 0.0300 Org/Hari 80,000 2,400
d Mandor 0.0750 Org/Hari 95,000 7,125
JUMLAH 196,025

1 m2 Membuat & memasang rangka plafond (60x60cm), Kayu kelas II (SNI:3434:2008-6.20)


1 Kaso kelas II 0.0154 m3 9,500,000 146,300
2 Paku 4 s/d 7 cm 0.2000 kg 36,000 7,200
a Pekerja 0.1500 Org/Hari 60,000 9,000
b Tukang Kayu Halus 0.3000 Org/Hari 80,000 24,000
c Kepala Tukang 0.0300 Org/Hari 80,000 2,400
d Mandor 0.0750 Org/Hari 95,000 7,125
JUMLAH 196,025
I.4. PEKERJAAN RANGKA DINDING

1 m2 Membuat & memasang rangka dinding partisi (60x120cm), Kayu kelas II (SNI:3434:2008-6.23)
1 Kaso kelas II 0.0280 m3 9,500,000 266,000
2 Paku 4 s/d 7 cm 0.1500 kg 36,000 5,400
a Pekerja 0.1500 Org/Hari 60,000 9,000
b Tukang Kayu Halus 0.4500 Org/Hari 80,000 36,000
c Kepala Tukang 0.0450 Org/Hari 80,000 3,600
d Mandor 0.0080 Org/Hari 95,000 760
JUMLAH 320,760

1 m2 Membuat & memasang rangka dinding partisi dobel teakwood, Kayu kelas II (SNI:3434:2008-6.24)
1 Balok kelas II 0.0280 m3 9,500,000 266,000
2 Paku 4 s/d 7 cm 0.1500 kg 36,000 5,400
3 Lem Kayu 0.5600 Kg 62,500 35,000
4 Teakwood t. 6 mm 0.8600 lbr 60,000 51,600
a Pekerja 0.1500 Org/Hari 60,000 9,000
b Tukang Kayu Halus 0.4500 Org/Hari 80,000 36,000
c Kepala Tukang 0.0450 Org/Hari 80,000 3,600
d Mandor 0.0080 Org/Hari 95,000 760
JUMLAH 407,360

1 m2 Membuat & memasang rangka dinding partisi dobel Plywood, Kayu kelas II (SNI:3434:2008-6.25)
1 Balok kelas II 0.0280 m3 9,500,000 266,000
2 Paku 4 s/d 7 cm 0.1500 kg 36,000 5,400
3 Lem Kayu 0.5600 Kg 62,500 35,000
4 Plywood 0.8600 lbr 120,000 103,200
a Pekerja 0.2000 Org/Hari 60,000 12,000
b Tukang Kayu Halus 0.6000 Org/Hari 80,000 48,000
c Kepala Tukang 0.0600 Org/Hari 80,000 4,800
d Mandor 0.0100 Org/Hari 95,000 950
JUMLAH 475,350

1 m2 Membuat & memasang rangka dinding Lambisering, Kayu kelas I (SNI:3434:2008-6.26)


1 Kayu Kuat klas I 0.0070 m3 16,000,000 112,000
2 Paku 4 s/d 7 cm 0.1000 kg 36,000 3,600
3 Paku Skrup 0.1500 Kg 20,000 3,000
a Pekerja 0.6000 Org/Hari 60,000 36,000
b Tukang Kayu Halus 1.8000 Org/Hari 80,000 144,000
c Kepala Tukang 0.1800 Org/Hari 80,000 14,400
d Mandor 0.0300 Org/Hari 95,000 2,850
JUMLAH 315,850

1 m2 Membuat & memasang rangka dinding Lambisering Plywood ukuran (120x240)cm (SNI:3434:2008-6.27)
1 Plywood 0.4000 lbr 120,000 48,000
2 Paku 1 s/d 3 cm 0.0500 kg 20,020 1,001
a Pekerja 0.0250 Org/Hari 60,000 1,500
b Tukang Kayu Halus 0.0750 Org/Hari 80,000 6,000
c Kepala Tukang 0.0080 Org/Hari 80,000 640
d Mandor 0.0010 Org/Hari 95,000 95
JUMLAH 57,236
1 m2 Membuat & memasang dinding bilik, Kayu kelas III (SNI:3434:2008-6.28)
1 Bilik bambu 1.5000 m2 6,500 9,750
2 Kaso kelas III 0.0140 m3 2,387,000 33,418
3 Paku 4 s/d 7 cm 0.0120 kg 36,000 432
4 List Kayu 2/4 0.0030 m3 7,500,000 22,500
a Pekerja 0.1000 Org/Hari 60,000 6,000
b Tukang Kayu Halus 0.0500 Org/Hari 80,000 4,000
c Kepala Tukang 0.0050 Org/Hari 80,000 400
d Mandor 0.0050 Org/Hari 95,000 475
JUMLAH 76,975

J.PEKERJAAN BESI, ALUMUNIUM, PINTU dan DEKORASI (SNI 7393:2008)

1 kg Membuat & memasang besi profil (SNI:7393:2008-6.1)


1 Besi Profil 1.1500 Kg 20,000 23,000
a Pekerja 0.0600 Org/Hari 60,000 3,600
b Tukang Kayu Halus 0.0600 Org/Hari 80,000 4,800
c Kepala Tukang 0.0060 Org/Hari 80,000 480
d Mandor 0.0030 Org/Hari 95,000 285
JUMLAH 32,165

1 kg Memasang rangka kuda-kuda baja ringan (SNI:7393:2008-6.2)


1 Roof botton 5.1000 m' 8,500 43,350
a Mobilisasi 1.0000 Ls 9,000 9,000
b Rangka atap baja ringan 1.0000 #N/A 160,000 160,000
c Self Drilling Screw dia. 6x20 mm 25.0000 bh 375 9,375
d Self Drilling Screw dia. 4x16 mm 35.0000 bh 350 12,250
e Dynabolt 1.0000 bh 1,500 1,500
f Tukang Besi Tulangan 0.0600 Org/Hari 80,000 4,800
g Kepala Tukang 0.0060 Org/Hari 80,000 480
h Mandor 0.0030 Org/Hari 95,000 285
i Pekerja 0.0600 Org/Hari 60,000 3,600
j Tukang Besi Tulangan 0.0600 Org/Hari 80,000 4,800
k Kepala Tukang 0.0060 Org/Hari 80,000 480
l Mandor 0.0030 Org/Hari 95,000 285
JUMLAH 250,205

1 kg Mengerjakan 100kg pekerjaan perkaitan (SNI:7393:2008-6.3)


1 Solar 1.0000 Ltr 5,500 5,500
2 Minyak Pelumas 0.1000 Ltr 35,000 3,500
3 Sewa Alat 0.8000 jam 57,000 45,600
a Pekerja 0.1000 Org/Hari 60,000 6,000
b Tukang Kayu Halus 0.1000 Org/Hari 80,000 8,000
c Kepala Tukang 0.0010 Org/Hari 80,000 80
d Mandor 0.0050 Org/Hari 95,000 475
JUMLAH 69,155

1 m2 Membuat pintu besi plat dobel t=2mm, rangka besi siku (SNI:7393:2008-6.4)
1 Besi Siku Rata-rata 15.0000 Kg 13,840 207,600
2 Besi Plat rata2 1 s/d 5 mm 32.8000 Kg 19,717 646,720
3 Kawat las listrik 0.0500 kg 25,000 1,250
a Pekerja 1.0500 Org/Hari 60,000 63,000
b Tukang Kayu Halus 1.0500 Org/Hari 80,000 84,000
c Kepala Tukang 0.1050 Org/Hari 80,000 8,400
d Mandor 0.0520 Org/Hari 95,000 4,940
JUMLAH 1,015,910
1 cm Mengerjakan 10 cm pengelasan dengan las listrik (SNI:7393:2008-6.5)
1 Kawat las listrik 0.4000 kg 25,000 10,000
2 Solar 0.3000 Ltr 5,500 1,650
3 Minyak Pelumas 0.0400 Ltr 35,000 1,400
4 Sewa Alat Las 0.1700 jam 20,000 3,400
a Pekerja 0.0400 Org/Hari 60,000 2,400
b Tukang Kayu Halus 0.0200 Org/Hari 80,000 1,600
c Kepala Tukang 0.0020 Org/Hari 80,000 160
d Mandor 0.0020 Org/Hari 95,000 190
JUMLAH 20,800

1 m2 Membuat rangka jendela besi Square Tube (25x5)cm (SNI:7393:2008-6.6)


1 Besi Square Tube 0.4000 Kg 20,001 8,000
2 Besi List Kaca 0.3000 Kg 20,002 6,001
3 Pengelasan 0.0400 cm 40 2
a Pekerja 0.0400 Org/Hari 60,000 2,400
b Tukang Kayu Halus 0.0200 Org/Hari 80,000 1,600
c Kepala Tukang 0.0020 Org/Hari 80,000 160
d Mandor 0.0020 Org/Hari 95,000 190
JUMLAH 18,353

1 m2 Pengadaan dan pemasangan pintu rolling door besi (SNI:7393:2008-6.7)


1 Rolling door Plat Besi 1.0000 m2 1,300,000 1,300,000
a Pekerja 1.2000 Org/Hari 60,000 72,000
b Tukang Kayu Halus 1.2000 Org/Hari 80,000 96,000
c Kepala Tukang 0.1200 Org/Hari 80,000 9,600
d Mandor 0.0060 Org/Hari 95,000 570
JUMLAH 1,478,170

1 m2 Pengadaan dan pemasangan pintu lipat plastik/PVC (folding door) (SNI:7393:2008-6.8)


1 Folding Door PVC 1.0000 m2 592,800 592,800
a Pekerja 0.4400 Org/Hari 60,000 26,400
b Tukang Kayu Halus 0.4400 Org/Hari 80,000 35,200
c Kepala Tukang 0.0440 Org/Hari 80,000 3,520
d Mandor 0.0220 Org/Hari 95,000 2,090
JUMLAH 660,010

1 m2 Pengadaan dan pemasangan sunscreen alumunium (SNI:7393:2008-6.9)


1 Sunscreen Alumunium 1.0000 m2 592,800 592,800
a Pekerja 0.0800 Org/Hari 60,000 4,800
b Tukang Kayu Halus 0.8000 Org/Hari 80,000 64,000
c Kepala Tukang 0.0800 Org/Hari 80,000 6,400
d Mandor 0.0040 Org/Hari 95,000 380
JUMLAH 668,380

1 m2 Pengadaan dan pemasangan rolling door alumunium (SNI:7393:2008-6.10)


1 Rolling door Zinkalume/Alumunium 1.0000 m2 1,300,000 1,300,000
a Pekerja 1.0000 Org/Hari 60,000 60,000
b Tukang Kayu Halus 1.0000 Org/Hari 80,000 80,000
c Kepala Tukang 0.1000 Org/Hari 80,000 8,000
d Mandor 0.0500 Org/Hari 95,000 4,750
JUMLAH 1,452,750
1 m2 Pengadaan dan pemasangan kusen pintu alumunium (SNI:7393:2008-6.11)
1 Kusen Alm. 4" CA 1.1000 m' 175,000 192,500
2 Skrup 2.0000 bh 334 667
3 Sealant clear neutral (300 ml) 0.0600 tb 35,000 2,100
a Pekerja 0.0430 Org/Hari 60,000 2,580
b Tukang Kayu Halus 0.0430 Org/Hari 80,000 3,440
c Kepala Tukang 0.0043 Org/Hari 80,000 344
d Mandor 0.0021 Org/Hari 95,000 200
JUMLAH 201,831

1 m2 Pengadaan dan pemasangan daun pintu alumunium strip (SNI:7393:2008-6.12)


1 Kusen Alm. 4" CA 4.4000 m' 175,000 770,000
2 Alumunium Strip 14.6000 m' 45,500 664,300
a Pekerja 0.0850 Org/Hari 60,000 5,100
b Tukang Kayu Halus 0.0850 Org/Hari 80,000 6,800
c Kepala Tukang 0.0085 Org/Hari 80,000 680
d Mandor 0.0042 Org/Hari 95,000 399
JUMLAH 1,447,279

1 m2 Pengadaan dan pemasangan daun pintu kaca rangka alumunium (SNI:7393:2008-6.13)


1 Kusen Alm. 4" CA 4.4000 m' 175,000 770,000
2 Kaca Polos 6 mm 4.5000 m2 125,000 562,500
3 Sealant clear neutral (300 ml) 0.2700 tb 35,000 9,450
a Pekerja 0.0850 Org/Hari 60,000 5,100
b Tukang Kayu Halus 0.0850 Org/Hari 80,000 6,800
c Kepala Tukang 0.0090 Org/Hari 80,000 720
d Mandor 0.0050 Org/Hari 95,000 475
JUMLAH 1,355,045

1 m2 Pengadaan dan pemasangan venetian, horisontal atau vertical blind (SNI:7393:2008-6.14)


1 Vertical Blind 1.0000 m2 123,500 123,500
a Pekerja 0.3500 Org/Hari 60,000 21,000
b Tukang Kayu Halus 0.3500 Org/Hari 80,000 28,000
c Kepala Tukang 0.0350 Org/Hari 80,000 2,800
d Mandor 0.0180 Org/Hari 95,000 1,710
JUMLAH 177,010

1 m2 Pengadaan dan pemasangan teralis besi strip (2x30)mm (SNI:7393:2008-6.15)


1 Plat Strip 6.1770 Kg 14,690 90,738
2 Pengelasan 27.0800 cm 40 1,080
a Pekerja 1.6700 Org/Hari 60,000 100,200
b Tukang Kayu Halus 1.6700 Org/Hari 80,000 133,600
c Kepala Tukang 0.1670 Org/Hari 80,000 13,360
d Mandor 0.0830 Org/Hari 95,000 7,885
JUMLAH 346,863

1 m2 Pengadaan dan pemasangan kawat nyamuk (SNI:7393:2008-6.16)


1 Kawat Nyamuk 1.1000 m2 3,250 3,575
2 Pengelasan 11.1100 cm 40 443
2 Plat Strip 1.7160 Kg 14,690 25,207
a Pekerja 0.1000 Org/Hari 60,000 6,000
b Tukang Kayu Halus 0.1000 Org/Hari 80,000 8,000
c Kepala Tukang 0.0100 Org/Hari 80,000 800
d Mandor 0.0050 Org/Hari 95,000 475
JUMLAH 44,501
1 m2 Pengadaan dan pemasangan jendela nako & tralis (SNI:7393:2008-6.17)
1 Kaca nako t.6 mm + rangka 1.1000 m2 75,000 82,500
2 Paku Skrup 0.1000 Kg 20,000 2,000
2 Plat Strip 7.0000 Kg 14,690 102,828
a Pekerja 0.2000 Org/Hari 60,000 12,000
b Tukang Kayu Halus 0.2000 Org/Hari 80,000 16,000
c Kepala Tukang 0.0200 Org/Hari 80,000 1,600
d Mandor 0.0010 Org/Hari 95,000 95
JUMLAH 217,023

1 m1 Pengadaan dan pemasangan talang datar/jurai Seng BJLS 28 lebar=90cm (SNI:7393:2008-6.18)


1 Seng Plat BJLS 0,30 1.0500 m' 84,700 88,935
2 Paku 1 s/d 3 cm 0.0150 kg 20,020 300
2 Papan kelas III 0.0190 m3 2,233,000 42,427
a Pekerja 0.2000 Org/Hari 60,000 12,000
b Tukang Kayu Halus 0.4000 Org/Hari 80,000 32,000
c Kepala Tukang 0.0250 Org/Hari 80,000 2,000
d Mandor 0.0010 Org/Hari 95,000 95
JUMLAH 177,757

1 m1 Pengadaan dan pemasangan talang 1/2 lingkaran Seng BJLS 30 lebar=45cm (SNI:7393:2008-6.19)
1 Seng Plat BJLS 0,30 1.0500 m' 84,700 88,935
2 Paku 1 s/d 3 cm 0.0100 kg 20,020 200
2 Plat Strip 0.5000 Kg 14,690 7,345
a Pekerja 0.1500 Org/Hari 60,000 9,000
b Tukang Kayu Halus 0.3000 Org/Hari 80,000 24,000
c Kepala Tukang 0.0300 Org/Hari 80,000 2,400
d Mandor 0.0080 Org/Hari 95,000 760
JUMLAH 132,640

K. Pekerjaan Plafond, Gypsum dan Partisi Gypsum (SNI 2839:2008)

1 m2 Pengadaan dan pemasangan plafond Kalsiboard/GRC t= 4mm, 5mm dan 6mm (SNI:2839:2008-6.1)
1 Plafon GRC Tiles 1.1000 lbr 180,000 198,000
2 Paku Skrup 0.0100 Kg 20,000 200
a Pekerja 0.0300 Org/Hari 60,000 1,800
b Tukang Kayu Halus 0.0700 Org/Hari 80,000 5,600
c Kepala Tukang 0.0070 Org/Hari 80,000 560
d Mandor 0.0040 Org/Hari 95,000 380
JUMLAH 206,540

1 m2 Pengadaan dan pemasangan plafond akustik (uk. =30x30 cm) (SNI:2839:2008-6.2)


1 Plafond akustik 30x30cm 12.0000 lbr 70,000 840,000
2 Paku Skrup 0.0500 Kg 20,000 1,000
a Pekerja 0.1200 Org/Hari 60,000 7,200
b Tukang Kayu Halus 0.1200 Org/Hari 80,000 9,600
c Kepala Tukang 0.0120 Org/Hari 80,000 960
d Mandor 0.0060 Org/Hari 95,000 570
JUMLAH 859,330

1 m2 Pengadaan dan pemasangan plafond akustik (uk. =30x60 cm) (SNI:2839:2008-6.3)


1 Plafond akustik 30x60cm 5.8000 lbr 70,000 406,000
2 Paku Skrup 0.0500 Kg 20,000 1,000
a Pekerja 0.1000 Org/Hari 60,000 6,000
b Tukang Kayu Halus 0.1000 Org/Hari 80,000 8,000
c Kepala Tukang 0.0100 Org/Hari 80,000 800
d Mandor 0.0050 Org/Hari 95,000 475
JUMLAH 422,275
1 m2 Pengadaan dan pemasangan plafond akustik (uk. =60x120 cm) (SNI:2839:2008-6.4)
1 Plafond akustik 60x120cm 1.5000 lbr 30,000 45,000
2 Paku Skrup 0.0500 Kg 20,000 1,000
a Pekerja 0.1000 Org/Hari 60,000 6,000
b Tukang Kayu Halus 0.1000 Org/Hari 80,000 8,000
c Kepala Tukang 0.0100 Org/Hari 80,000 800
d Mandor 0.0050 Org/Hari 95,000 475
JUMLAH 61,275

1 m2 Pengadaan dan pemasangan plafond triplek (uk. =120x240 cm), t=3mm, 4mm, 6mm (SNI:2839:2008-6.5)
1 Triplex t. 6 mm 0.3750 lbr 69,000 25,875
2 Paku Skrup 0.0300 Kg 20,000 600
a Pekerja 0.1000 Org/Hari 60,000 6,000
b Tukang Kayu Halus 0.1000 Org/Hari 80,000 8,000
c Kepala Tukang 0.0100 Org/Hari 80,000 800
d Mandor 0.0050 Org/Hari 95,000 475
JUMLAH 41,750

1 m2 Pengadaan dan pemasangan plafond lambisering kayu t=9mm (SNI:2839:2008-6.6)


1 Papan kelas II 0.0150 m3 9,500,000 142,500
2 Paku Skrup 0.0100 Kg 20,000 200
a Pekerja 0.8000 Org/Hari 60,000 48,000
b Tukang Kayu Halus 0.8000 Org/Hari 80,000 64,000
c Kepala Tukang 0.0800 Org/Hari 80,000 6,400
d Mandor 0.0400 Org/Hari 95,000 3,800
JUMLAH 264,900

1 m2 Pengadaan dan pemasangan plafond gypsumboard t=9mm (SNI:2839:2008-6.7)


1 Gypsumboard t.9 mm 0.3640 lbr 62,980 22,925
2 Paku Skrup 0.1100 Kg 20,000 2,200
a Pekerja 0.1000 Org/Hari 60,000 6,000
b Tukang Kayu Halus 0.0500 Org/Hari 80,000 4,000
c Kepala Tukang 0.0050 Org/Hari 80,000 400
d Mandor 0.0050 Org/Hari 95,000 475
JUMLAH 36,000

1 m2 Pengadaan dan pemasangan list plafond gypsum profil 10cm (SNI:2839:2008-6.8)


1 List Profil 10 cm Gypsum 1.0500 m1 15,700 16,485
2 Paku Skrup 0.1500 Kg 20,000 3,000
a Pekerja 0.0600 Org/Hari 60,000 3,600
b Tukang Kayu Halus 0.0600 Org/Hari 80,000 4,800
c Kepala Tukang 0.0060 Org/Hari 80,000 480
d Mandor 0.0030 Org/Hari 95,000 285
JUMLAH 28,650

1 m2 Pengadaan dan pemasangan Plafond Akustik + rangka (SNI:2839:2008-6.9)


1 Profil Alumunium “T” 3.6000 m1 19,500 70,200
2 Kawat galvanized 0.1500 m' 130,000 19,500
3 Ramset 1.0500 Bh 11,000 11,550
4 Plafond akustik 60x120cm 1.5000 lbr 30,000 45,000
a Pekerja 0.5000 Org/Hari 60,000 30,000
b Tukang Kayu Halus 0.5000 Org/Hari 80,000 40,000
c Kepala Tukang 0.0500 Org/Hari 80,000 4,000
d Mandor 0.0250 Org/Hari 95,000 2,375
JUMLAH 222,625
1 m2 Pengadaan dan pemasangan list plafond kayu profil (SNI:2839:2008-6.10)
1 List Profil 5 cm Kayu 1.0500 m1 7,500 7,875
2 Paku 1 s/d 3 cm 0.0100 kg 20,020 200
a Pekerja 0.0500 Org/Hari 60,000 3,000
b Tukang Kayu Halus 0.0500 Org/Hari 80,000 4,000
c Kepala Tukang 0.0050 Org/Hari 80,000 400
d Mandor 0.0030 Org/Hari 95,000 285
JUMLAH 15,760

1 m2 Pengadaan dan pemasangan rangka plafond besi hollow 40x40mm & 20x40mm (dihitung)
1 Besi Hollow 40x40mm (Sinchromated) 0.2775 btg 41,600 11,544
2 Besi Hollow 20x40mm (Sinchromated) 0.4681 btg 20,800 9,736
3 Suspension rod 1.2350 Bh 4,550 5,619
a Pekerja 0.1500 Org/Hari 60,000 9,000
b Tukang Kayu Halus 0.3000 Org/Hari 80,000 24,000
c Kepala Tukang 0.0500 Org/Hari 80,000 4,000
d Mandor 0.0100 Org/Hari 95,000 950
JUMLAH 64,850

1 m2 Pengadaan dan pemasangan rangka plafond besi hollow 40x40mm & 40x40mm (dihitung)
1 Besi Hollow 40x40mm (Sinchromated) 0.2775 btg 41,600 11,544
2 Besi Hollow 40x40mm (Sinchromated) 0.4681 btg 41,600 19,473
3 Suspension rod 1.2350 Bh 4,550 5,619
a Pekerja 0.1500 Org/Hari 60,000 9,000
b Tukang Kayu Halus 0.2500 Org/Hari 80,000 20,000
c Kepala Tukang 0.0500 Org/Hari 80,000 4,000
d Mandor 0.0100 Org/Hari 95,000 950
JUMLAH 70,586

1 m2 Pengadaan dan pemasangan rangka plafond besi hollow 60x40mm & 40x40mm (dihitung)
1 Rangka Plafond Akustik 60 x 60 cm 0.2775 m2 124,861 34,649
2 Besi Hollow 40x40mm (Sinchromated) 0.4681 btg 41,600 19,473
3 Suspension rod 1.2350 Bh 4,550 5,619
a Pekerja 0.1500 Org/Hari 60,000 9,000
b Tukang Kayu Halus 0.2500 Org/Hari 80,000 20,000
c Kepala Tukang 0.0500 Org/Hari 80,000 4,000
d Mandor 0.0100 Org/Hari 95,000 950
JUMLAH 93,691

1 m2 Pengadaan dan pemasangan rangka plafond besi hollow 100x50mm (dihitung)


1 Besi Hollow 50x100mm (galvanized) t.0.5mm 0.2775 btg 1,170,000 324,675
2 Besi Hollow 40x60mm (Sinchromated) 0.4681 btg 62,400 29,209
3 Suspension rod 1.2350 Bh 4,550 5,619
a Pekerja 0.1500 Org/Hari 60,000 9,000
b Tukang Kayu Halus 0.2500 Org/Hari 80,000 20,000
c Kepala Tukang 0.0500 Org/Hari 80,000 4,000
d Mandor 0.0100 Org/Hari 95,000 950
JUMLAH 393,454

1 m2 Pengadaan dan pemasangan rangka pipa besi hollow diameter 8cm (dihitung)
1 Besi Hollow 50x100mm (galvanized) t.0.5mm 0.2775 btg 1,170,000 324,675
2 Besi Hollow 40x60mm (Sinchromated) 0.4681 btg 62,400 29,209
3 Suspension rod 1.2350 Bh 4,550 5,619
a Pekerja 0.1500 Org/Hari 60,000 9,000
b Tukang Kayu Halus 0.2500 Org/Hari 80,000 20,000
c Kepala Tukang 0.0500 Org/Hari 80,000 4,000
d Mandor 0.0100 Org/Hari 95,000 950
JUMLAH 393,454
J.PEKERJAAN PENGECATAN & FINISHING DINDING (Pt T-38-2000-C)

1 m2 Mendempul dan Menggosok Kayu


1 Dempul Kayu 0.0800 Kg 24,640 1,971
2 Cat Kayu 0.0200 Kg 30,800 616
3 Batu apung 0.0100 Kg 6,000 60
a Pekerja 0.0400 Org/Hari 60,000 2,400
b Tukang Cat Biasa 0.0400 Org/Hari 80,000 3,200
c Kepala Tukang 0.0040 Org/Hari 80,000 320
d Mandor 0.0025 Org/Hari 95,000 238
JUMLAH 8,805

1 m2 Mengecatan Bidang Kayu Baru ( 1 Lapis Plamir ), 1 Lapis Cat Dasar, 3 Lapis Cat Penutup
1 Cat Dasar / meni kayu 0.2000 Kg 28,336 5,667
2 Plamir Kayu 0.1500 Kg 17,890 2,684
3 Dempul Kayu 0.1700 Kg 24,640 4,189
4 Cat Kayu 0.3500 Kg 30,800 10,780
a Pekerja 0.0700 Org/Hari 60,000 4,200
b Tukang Cat Biasa 0.1050 Org/Hari 80,000 8,400
c Kepala Tukang 0.0040 Org/Hari 80,000 320
d Mandor 0.0025 Org/Hari 95,000 238
JUMLAH 30,810

1 m2 Pelaburan Bidang Kayu dengan Teak Oil


1 Teak Oil 0.3600 Ltr 15,000 5,400
a Pekerja 0.0400 Org/Hari 60,000 2,400
b Tukang Cat Biasa 0.0630 Org/Hari 80,000 5,040
c Kepala Tukang 0.0630 Org/Hari 80,000 5,040
d Mandor 0.0025 Org/Hari 95,000 238
JUMLAH 18,118

1 m2 Pelaburan Bidang Kayu dengan Pelitur


1 Politur 0.1500 Ltr 7,000 1,050
2 Politur 0.3720 Ltr 7,000 2,604
3 Amplas Kayu / Besi 2.0000 Lbr 8,624 17,248
a Pekerja 0.0400 Org/Hari 60,000 2,400
b Tukang Cat Biasa 0.0630 Org/Hari 80,000 5,040
c Kepala Tukang 0.0630 Org/Hari 80,000 5,040
d Mandor 0.0025 Org/Hari 95,000 238
JUMLAH 33,620

1 m2 Pelaburan Bidang Kayu dengan Vernis


1 Vernis Kayu 0.1500 Ltr 11,500 1,725
2 Dempul Kayu 0.0500 Kg 24,640 1,232
3 Amplas Kayu / Besi 0.1000 Lbr 8,624 862
4 Kuas Cat rata2 0.0100 Bh 11,211 112
a Pekerja 0.1600 Org/Hari 60,000 9,600
b Tukang Cat Biasa 0.1600 Org/Hari 80,000 12,800
c Kepala Tukang 0.0160 Org/Hari 80,000 1,280
d Mandor 0.0025 Org/Hari 95,000 238
JUMLAH 26,124
1 m2 Pengecatan Tembok Baru ( 1 Plamir, 1 Lapis Cat Dasar, 2 Lapis Cat Penutup )
1 Plamur Tembok 0.1000 kg 52,000 5,200
2 Cat Tembok (25 kg) 0.1400 kg 22,100 3,094
3 Cat akhir emulsion 0.3640 Ltr 62,500 22,750
4 Amplas Kayu / Besi 0.2000 Lbr 8,624 1,725
a Pekerja 0.0200 Org/Hari 60,000 1,200
b Tukang Cat Biasa 0.0630 Org/Hari 80,000 5,040
c Kepala Tukang 0.0063 Org/Hari 80,000 504
d Mandor 0.0025 Org/Hari 95,000 238
JUMLAH 39,750

1 m2 Pengecatan Tembok Baru ( 1 Plamir, 1 Lapis Cat Dasar, 2 Lapis Cat Penutup Wheather shield )
1 Plamur Tembok 0.1000 kg 52,000 5,200
2 Cat akhir Wheathersield 0.1400 Ltr 100,000 14,000
3 Cat akhir Wheathersield 0.3640 Ltr 100,000 36,400
4 Amplas Kayu / Besi 0.2000 Lbr 8,624 1,725
a Pekerja 0.0200 Org/Hari 60,000 1,200
b Tukang Cat Biasa 0.0630 Org/Hari 80,000 5,040
c Kepala Tukang 0.0063 Org/Hari 80,000 504
d Mandor 0.0025 Org/Hari 95,000 238
JUMLAH 64,306

1 m2 Pengecatan Permukaan Besi/Baja dengan Meni Besi


1 Cat Dasar / meni besi 0.1000 Kg 28,336 2,834
2 Kuas Cat rata2 0.0100 Bh 11,211 112
a Pekerja 0.0200 Org/Hari 60,000 1,200
b Tukang Cat Biasa 0.2000 Org/Hari 80,000 16,000
c Kepala Tukang 0.0200 Org/Hari 80,000 1,600
d Mandor 0.0100 Org/Hari 95,000 950
JUMLAH 22,696

1 m2 Pengecatan Permukaan Besi/Baja dengan Meni Besi (semprot/spray)


1 Cat Dasar / meni besi 0.1000 Kg 28,336 2,834
a Pekerja 0.4000 Org/Hari 60,000 24,000
b Tukang Cat Biasa 0.7000 Org/Hari 80,000 56,000
c Kepala Tukang 0.2000 Org/Hari 80,000 16,000
d Mandor 0.2000 Org/Hari 95,000 19,000
JUMLAH 117,834

1 m2 Pengecatan Permukaan Besi/Baja dengan Meni Besi dengan perancah


1 Cat Dasar / meni besi 0.1000 Kg 28,336 2,834
2 Kuas Cat rata2 0.0100 Bh 11,211 112
3 Kayu Kuat klas III 0.0020 m3 2,335,667 4,671
a Pekerja 0.2500 Org/Hari 60,000 15,000
b Tukang Cat Biasa 0.2250 Org/Hari 80,000 18,000
c Kepala Tukang 0.0225 Org/Hari 80,000 1,800
d Mandor 0.0075 Org/Hari 95,000 713
JUMLAH 43,130

1 m2 Pengecatan Permukaan Besi/Baja dengan Meni Besi dengan perancah (semprot/spray)


1 Cat Dasar / meni besi 0.1000 Kg 28,336 2,834
2 Kayu Kuat klas III 0.0020 m3 2,335,667 4,671
a Pekerja 0.4000 Org/Hari 60,000 24,000
b Tukang Cat Biasa 0.7000 Org/Hari 80,000 56,000
c Kepala Tukang 0.2000 Org/Hari 80,000 16,000
d Mandor 0.2000 Org/Hari 95,000 19,000
JUMLAH 122,505
1 m2 Pengecatan Permukaan Besi/Baja dengan Cat Besi
1 Cat Besi 0.1000 Kg 30,800 3,080
2 Kuas Cat rata2 0.0100 Bh 11,211 112
a Pekerja 0.0200 Org/Hari 60,000 1,200
b Tukang Cat Biasa 0.2000 Org/Hari 80,000 16,000
c Kepala Tukang 0.0200 Org/Hari 80,000 1,600
d Mandor 0.0100 Org/Hari 95,000 950
JUMLAH 22,942

1 m2 Pengecatan Permukaan Besi/Baja dengan Cat Besi dengan perancah


1 Cat Besi 0.1000 Kg 30,800 3,080
2 Kuas Cat rata2 0.0100 Bh 11,211 112
3 Kayu Kuat klas III 0.0020 m3 2,335,667 4,671
a Pekerja 0.2500 Org/Hari 60,000 15,000
b Tukang Cat Biasa 0.2250 Org/Hari 80,000 18,000
c Kepala Tukang 0.0225 Org/Hari 80,000 1,800
d Mandor 0.0075 Org/Hari 95,000 713
JUMLAH 43,376

1 m2 Pengecatan Permukaan Besi/Baja dengan Cat Besi (semprot/spray)


1 Cat Besi 0.3000 Kg 30,800 9,240
a Pekerja 0.4000 Org/Hari 60,000 24,000
b Tukang Cat Biasa 0.7000 Org/Hari 80,000 56,000
c Kepala Tukang 0.2000 Org/Hari 80,000 16,000
d Mandor 0.2000 Org/Hari 95,000 19,000
JUMLAH 124,240

1 m2 Pengecatan Permukaan Besi/Baja Meni & Cat Besi


m2 Pengecatan Permukaan Besi/Baja dengan Meni Besi 22,696
m2 Pengecatan Permukaan Besi/Baja dengan Cat Besi 22,942
JUMLAH 45,638

1 m2 Pengecatan Permukaan Besi/Baja Meni & Cat Besi (semprot/spray)


m2 Pengecatan Permukaan Besi/Baja dengan Meni Besi (semprot/spray) 117,834
m2 Pengecatan Permukaan Besi/Baja dengan Cat Besi (semprot/spray) 124,240
JUMLAH 242,074

K. PEKERJAAN ATAP (xxxxxxxxxx))

1 m2 Pengadaan dan pemasangan Atap Genteng Palentong Kecil


1 Genteng Palentong Kecil 25.0000 Bh 3,500 87,500
a Pekerja 0.1500 Org/Hari 60,000 9,000
b Tukang Kayu Kasar 0.0750 Org/Hari 80,000 6,000
c Kepala Tukang 0.0080 Org/Hari 80,000 640
d Mandor 0.0080 Org/Hari 95,000 760
JUMLAH 103,900

1 m2 Pengadaan dan pemasangan Atap Genteng Kodok/Glazzur


1 Genteng Kodok 25.0000 Bh 4,700 117,500
a Pekerja 0.1500 Org/Hari 60,000 9,000
b Tukang Kayu Kasar 0.0750 Org/Hari 80,000 6,000
c Kepala Tukang 0.0080 Org/Hari 80,000 640
d Mandor 0.0080 Org/Hari 95,000 760
JUMLAH 133,900
1 m2 Pengadaan dan pemasangan Atap Genteng Palentong Super/besar
1 Genteng Palentong Super 12.0000 Bh 11,000 132,000
a Pekerja 0.1500 Org/Hari 60,000 9,000
b Tukang Kayu Kasar 0.0600 Org/Hari 80,000 4,800
c Kepala Tukang 0.0060 Org/Hari 80,000 480
d Mandor 0.0080 Org/Hari 95,000 760
JUMLAH 147,040

1 m1 Pengadaan dan pemasangan Bubung Palentong Kecil


1 Bubungan Genteng Palentong 5.0000 Bh 4,300 21,500
2 Semen PC (50 Kg) 0.1600 zak 63,500 10,160
3 Pasir Pasang 0.0320 m3 135,000 4,320
a Pekerja 0.4000 Org/Hari 60,000 24,000
b Tukang Kayu Kasar 0.2000 Org/Hari 80,000 16,000
c Kepala Tukang 0.0200 Org/Hari 80,000 1,600
d Mandor 0.0020 Org/Hari 95,000 190
JUMLAH 77,770

1 m1 Pengadaan dan pemasangan Bubung Kodok Glazzur


1 Bubungan Genteng Kodok 5.0000 Bh 5,200 26,000
2 Semen PC (50 Kg) 0.1600 zak 63,500 10,160
3 Pasir Pasang 0.0320 m3 135,000 4,320
a Pekerja 0.4000 Org/Hari 60,000 24,000
b Tukang Kayu Kasar 0.2000 Org/Hari 80,000 16,000
c Kepala Tukang 0.0200 Org/Hari 80,000 1,600
d Mandor 0.0020 Org/Hari 95,000 190
JUMLAH 82,270

1 m1 Pengadaan dan pemasangan Bubung Palentong Besar


1 Bubungan Palentong Super 4.0000 Bh 13,400 53,600
2 Semen PC (50 Kg) 0.1600 zak 63,500 10,160
3 Pasir Pasang 0.0320 m3 135,000 4,320
a Pekerja 0.4000 Org/Hari 60,000 24,000
b Tukang Kayu Kasar 0.2000 Org/Hari 80,000 16,000
c Kepala Tukang 0.0200 Org/Hari 80,000 1,600
d Mandor 0.0020 Org/Hari 95,000 190
JUMLAH 109,870

1 m1 Pengadaan dan pemasangan Rooflight Fiberglass


1 Atap Fiberglass 0.6000 Lbr 170,000 102,000
2 Paku Skrup 0.0500 Kg 20,000 1,000
a Pekerja 0.1400 Org/Hari 60,000 8,400
b Tukang Kayu Kasar 0.6700 Org/Hari 80,000 53,600
c Kepala Tukang 0.0070 Org/Hari 80,000 560
d Mandor 0.0070 Org/Hari 95,000 665
JUMLAH 166,225

1 m1 Pengadaan dan pemasangan Asbes gelombang (2.5Mx0.92M) t=5mm


1 Asbes/Harflex gelombang uk. 2500X920x5 mm 0.5000 lbr 49,250 24,625
2 Paku payung 0.1200 bh 500 60
a Pekerja 0.1400 Org/Hari 60,000 8,400
b Tukang Kayu Kasar 0.0750 Org/Hari 80,000 6,000
c Kepala Tukang 0.0080 Org/Hari 80,000 640
d Mandor 0.0080 Org/Hari 95,000 760
JUMLAH 40,485
1 m1 Pengadaan dan pemasangan Asbes gelombang (2.25Mx0.92M) t=5mm
1 Asbes/Harflex gelombang uk. 2250X920x5 mm 0.6000 lbr 36,450 21,870
2 Paku Pancing 0.1200 Kg 18,700 2,244
a Pekerja 0.1400 Org/Hari 60,000 8,400
b Tukang Kayu Kasar 0.0750 Org/Hari 80,000 6,000
c Kepala Tukang 0.0080 Org/Hari 80,000 640
d Mandor 0.0080 Org/Hari 95,000 760
JUMLAH 39,914

1 m1 Pengadaan dan pemasangan Asbes gelombang (2Mx0.92M) t=5mm


1 Asbes/Harflex gelombang uk. 2000X920x5 mm 0.6000 lbr 32,350 19,410
2 Paku Pancing 0.1200 Kg 18,700 2,244
a Pekerja 0.1400 Org/Hari 60,000 8,400
b Tukang Kayu Kasar 0.0700 Org/Hari 80,000 5,600
c Kepala Tukang 0.0070 Org/Hari 80,000 560
d Mandor 0.0070 Org/Hari 95,000 665
JUMLAH 36,879

1 m1 Pengadaan dan pemasangan Asbes gelombang (1.8Mx0.92M) t=5mm


1 Asbes/Harflex gelombang uk. 1800x1080x5 mm 0.7500 lbr 59,150 44,363
2 Paku Pancing 0.1200 Kg 18,700 2,244
a Pekerja 0.1400 Org/Hari 60,000 8,400
b Tukang Kayu Kasar 0.0700 Org/Hari 80,000 5,600
c Kepala Tukang 0.0070 Org/Hari 80,000 560
d Mandor 0.0070 Org/Hari 95,000 665
JUMLAH 61,832

1 m1 Pengadaan dan pemasangan Asbes gelombang (3Mx1.05M) t=4mm


1 Asbes/Harflex gelombang uk. 3000X1050x4 mm 0.3500 lbr 73,000 25,550
2 Paku Pancing 0.1200 Kg 18,700 2,244
a Pekerja 0.1400 Org/Hari 60,000 8,400
b Tukang Kayu Kasar 0.0700 Org/Hari 80,000 5,600
c Kepala Tukang 0.0070 Org/Hari 80,000 560
d Mandor 0.0070 Org/Hari 95,000 665
JUMLAH 43,019

1 m1 Pengadaan dan pemasangan Asbes gelombang (2.7Mx1.05M) t=4mm


1 Asbes/Harflex gelombang uk. 2700X1050x4 mm 0.4200 lbr 65,750 27,615
2 Paku Pancing 0.1200 Kg 18,700 2,244
a Pekerja 0.1400 Org/Hari 60,000 8,400
b Tukang Kayu Kasar 0.0700 Org/Hari 80,000 5,600
c Kepala Tukang 0.0070 Org/Hari 80,000 560
d Mandor 0.0070 Org/Hari 95,000 665
JUMLAH 45,084

1 m1 Pengadaan dan pemasangan Asbes gelombang (2.4Mx1.05M) t=4mm


1 Asbes/Harflex gelombang uk. 2400X1050x4 mm 0.4400 lbr 58,450 25,718
2 Paku Pancing 0.1200 Kg 18,700 2,244
a Pekerja 0.1400 Org/Hari 60,000 8,400
b Tukang Kayu Kasar 0.0670 Org/Hari 80,000 5,360
c Kepala Tukang 0.0070 Org/Hari 80,000 560
d Mandor 0.0070 Org/Hari 95,000 665
JUMLAH 42,947
1 m1 Pengadaan dan pemasangan Asbes gelombang (2.1Mx1.05M) t=4mm
1 Asbes/Harflex gelombang uk. 2100X1050x4 mm 0.5100 lbr 58,450 29,810
2 Paku Pancing 0.1200 Kg 18,700 2,244
a Pekerja 0.1400 Org/Hari 60,000 8,400
b Tukang Kayu Kasar 0.0670 Org/Hari 80,000 5,360
c Kepala Tukang 0.0070 Org/Hari 80,000 560
d Mandor 0.0070 Org/Hari 95,000 665
JUMLAH 47,039

1 m1 Pengadaan dan pemasangan Asbes gelombang (1.5Mx1.05M) t=4mm


1 Asbes/Harflex gelombang uk. 1500X1050x4 mm 0.8000 lbr 36,800 29,440
2 Paku Pancing 0.1200 Kg 18,700 2,244
a Pekerja 0.1400 Org/Hari 60,000 8,400
b Tukang Kayu Kasar 0.0670 Org/Hari 80,000 5,360
c Kepala Tukang 0.0070 Org/Hari 80,000 560
d Mandor 0.0070 Org/Hari 95,000 665
JUMLAH 46,669

1 m1 Pengadaan dan pemasangan Asbes gelombang (3Mx1.08M) t=6mm


1 Asbes/Harflex gelombang uk. 3000X1080x6 mm 0.3700 lbr 116,500 43,105
2 Paku Pancing 0.1200 Kg 18,700 2,244
a Pekerja 0.1400 Org/Hari 60,000 8,400
b Tukang Kayu Kasar 0.0670 Org/Hari 80,000 5,360
c Kepala Tukang 0.0070 Org/Hari 80,000 560
d Mandor 0.0070 Org/Hari 95,000 665
JUMLAH 60,334

1 m1 Pengadaan dan pemasangan Asbes gelombang (2.7Mx1.08M) t=6mm


1 Asbes/Harflex gelombang uk. 2700X1080x6 mm 0.3800 lbr 104,850 39,843
2 Paku Pancing 0.1200 Kg 18,700 2,244
a Pekerja 0.1400 Org/Hari 60,000 8,400
b Tukang Kayu Kasar 0.0670 Org/Hari 80,000 5,360
c Kepala Tukang 0.0070 Org/Hari 80,000 560
d Mandor 0.0070 Org/Hari 95,000 665
JUMLAH 57,072

1 m1 Pengadaan dan pemasangan Asbes gelombang (2.4Mx1.08M) t=6mm


1 Asbes/Harflex gelombang uk. 2400X1080x6 mm 0.4600 lbr 93,250 42,895
2 Paku Pancing 0.1200 Kg 18,700 2,244
a Pekerja 0.1400 Org/Hari 60,000 8,400
b Tukang Kayu Kasar 0.0670 Org/Hari 80,000 5,360
c Kepala Tukang 0.0070 Org/Hari 80,000 560
d Mandor 0.0070 Org/Hari 95,000 665
JUMLAH 60,124

1 m1 Pengadaan dan pemasangan Asbes gelombang (2.1Mx1.08M) t=6mm


1 Asbes/Harflex gelombang uk. 2100X1080x6 mm 0.4900 lbr 93,250 45,693
2 Paku Pancing 0.1200 Kg 18,700 2,244
a Pekerja 0.1400 Org/Hari 60,000 8,400
b Tukang Kayu Kasar 0.0670 Org/Hari 80,000 5,360
c Kepala Tukang 0.0070 Org/Hari 80,000 560
d Mandor 0.0070 Org/Hari 95,000 665
JUMLAH 62,922
1 m1 Pengadaan dan pemasangan Asbes gelombang (1.8Mx1.08M) t=6mm
1 Asbes/Harflex gelombang uk. 1800X1080x6 mm 0.5700 lbr 69,900 39,843
2 Paku Pancing 0.1200 Kg 18,700 2,244
a Pekerja 0.1400 Org/Hari 60,000 8,400
b Tukang Kayu Kasar 0.0670 Org/Hari 80,000 5,360
c Kepala Tukang 0.0070 Org/Hari 80,000 560
d Mandor 0.0070 Org/Hari 95,000 665
JUMLAH 57,072

1 m1 Pengadaan dan pemasangan Bubung Stel Gelombang 0.92m


1 Bubungan stel gelombang 920 mm 2.4000 lbr 7,100 17,040
2 Paku payung 6.0000 bh 500 3,000
a Pekerja 0.0840 Org/Hari 60,000 5,040
b Tukang Kayu Kasar 0.1250 Org/Hari 80,000 10,000
c Kepala Tukang 0.0130 Org/Hari 80,000 1,040
d Mandor 0.0040 Org/Hari 95,000 380
JUMLAH 36,500

1 m1 Pengadaan dan pemasangan Nok Stel Gelombang 0.92m


1 Nok stel gelombang 1050 mm 2.4000 lbr 25,100 60,240
2 Paku payung 6.0000 bh 500 3,000
a Pekerja 0.0840 Org/Hari 60,000 5,040
b Tukang Kayu Kasar 0.1250 Org/Hari 80,000 10,000
c Kepala Tukang 0.0130 Org/Hari 80,000 1,040
d Mandor 0.0040 Org/Hari 95,000 380
JUMLAH 79,700

1 m1 Pengadaan dan pemasangan Nok Stel Gelombang 0.92m


1 Nok stel gelombang 1050 mm 2.4000 lbr 25,100 60,240
2 Paku payung 6.0000 bh 500 3,000
a Pekerja 0.0840 Org/Hari 60,000 5,040
b Tukang Kayu Kasar 0.1250 Org/Hari 80,000 10,000
c Kepala Tukang 0.0130 Org/Hari 80,000 1,040
d Mandor 0.0040 Org/Hari 95,000 380
JUMLAH 79,700

1 m1 Pengadaan dan pemasangan Nok Stel Gelombang 1.05m


1 Nok stel gelombang 1050 mm 2.1000 lbr 25,100 52,710
2 Paku payung 6.0000 bh 500 3,000
a Pekerja 0.0840 Org/Hari 60,000 5,040
b Tukang Kayu Kasar 0.1250 Org/Hari 80,000 10,000
c Kepala Tukang 0.0130 Org/Hari 80,000 1,040
d Mandor 0.0040 Org/Hari 95,000 380
JUMLAH 72,170

1 m1 Pengadaan dan pemasangan Nok Stel Gelombang 1.08m


1 Nok stel gelombang 1080 mm 2.1000 lbr 44,700 93,870
2 Paku payung 6.0000 bh 500 3,000
a Pekerja 0.0840 Org/Hari 60,000 5,040
b Tukang Kayu Kasar 0.1250 Org/Hari 80,000 10,000
c Kepala Tukang 0.0130 Org/Hari 80,000 1,040
d Mandor 0.0040 Org/Hari 95,000 380
JUMLAH 113,330
1 m1 Pengadaan dan pemasangan Atap Genteng Beton
1 Genteng Beton 11.0000 Bh 4,680 51,480
2 Paku 4 s/d 7 cm 0.0300 kg 36,000 1,080
a Pekerja 0.2000 Org/Hari 60,000 12,000
b Tukang Kayu Kasar 0.1000 Org/Hari 80,000 8,000
c Kepala Tukang 0.0100 Org/Hari 80,000 800
d Mandor 0.0100 Org/Hari 95,000 950
JUMLAH 74,310

1 m1 Pengadaan dan pemasangan Nok Atap Genteng Beton


1 Nok Genteng Beton 3.5000 Bh 4,681 16,385
2 Paku 4 s/d 7 cm 0.0500 kg 36,000 1,800
3 Semen PC (50 Kg) 0.2160 zak 63,500 13,716
4 Pasir Pasang 0.0320 m3 135,000 4,320
5 Semen Warna 1.0000 kg 12,500 12,500
a Pekerja 0.4000 Org/Hari 60,000 24,000
b Tukang Kayu Kasar 0.2000 Org/Hari 80,000 16,000
c Kepala Tukang 0.0200 Org/Hari 80,000 1,600
d Mandor 0.0200 Org/Hari 95,000 1,900
JUMLAH 92,221

1 m1 Pengadaan dan pemasangan Atap Genteng Aspal


1 Genteng Aspal 6.9000 Bh 3,602 24,854
2 Triplex t. 4 mm 0.3500 lbr 54,000 18,900
3 Paku 4 s/d 7 cm 0.0300 kg 36,000 1,080
4 Plastic Aerator 0.5000 Bh 3,000 1,500
a Pekerja 0.2000 Org/Hari 60,000 12,000
b Tukang Kayu Kasar 0.3000 Org/Hari 80,000 24,000
c Kepala Tukang 0.0030 Org/Hari 80,000 240
d Mandor 0.0100 Org/Hari 95,000 950
JUMLAH 83,524

1 m1 Pengadaan dan pemasangan Nok Atap Genteng Aspal


1 Nok Genteng aspal 2.0000 Bh 3,603 7,206
2 Paku 1 s/d 3 cm 0.0500 kg 20,020 1,001
3 Kayu Kuat klas III 0.0035 m3 2,335,667 8,175
a Pekerja 0.1250 Org/Hari 60,000 7,500
b Tukang Kayu Kasar 0.2500 Org/Hari 80,000 20,000
c Kepala Tukang 0.0250 Org/Hari 80,000 2,000
d Mandor 0.0060 Org/Hari 95,000 570
JUMLAH 46,452

1 m1 Pengadaan dan pemasangan Atap Genteng Metal


1 Genteng Metal stone chip 1.0200 m2 143,000 145,860
2 Paku 4 s/d 7 cm 0.2000 kg 36,000 7,200
a Pekerja 0.2000 Org/Hari 60,000 12,000
b Tukang Kayu Kasar 0.1000 Org/Hari 80,000 8,000
c Kepala Tukang 0.0100 Org/Hari 80,000 800
d Mandor 0.0100 Org/Hari 95,000 950
JUMLAH 174,810

1 m1 Pengadaan dan pemasangan Nok Atap Genteng Metal


1 Nok Genteng Metal 1.1000 Lbr 65,000 71,500
2 Paku 4 s/d 7 cm 0.0500 kg 36,000 1,800
a Pekerja 0.2500 Org/Hari 60,000 15,000
b Tukang Kayu Kasar 0.1500 Org/Hari 80,000 12,000
c Kepala Tukang 0.0150 Org/Hari 80,000 1,200
d Mandor 0.0130 Org/Hari 95,000 1,235
JUMLAH 102,735
1 m1 Pengadaan dan pemasangan Atap Sirap
1 Atap Sirap 60.0000 Bh 3,606 216,360
2 Triplex t. 4 mm 0.3500 lbr 54,000 18,900
3 Paku 4 s/d 7 cm 0.0300 kg 36,000 1,080
4 Plastic Aerator 0.5000 Bh 3,000 1,500
a Pekerja 0.1660 Org/Hari 60,000 9,960
b Tukang Kayu Kasar 0.2500 Org/Hari 80,000 20,000
c Kepala Tukang 0.0250 Org/Hari 80,000 2,000
d Mandor 0.0080 Org/Hari 95,000 760
JUMLAH 270,560

1 m1 Pengadaan dan pemasangan Nok Atap Sirap


1 Nok Atap Sirap 1.0200 m1 3,607 3,679
2 Paku 1 s/d 3 cm 0.0600 kg 20,020 1,201
3 Paku 4 s/d 7 cm 0.0500 kg 36,000 1,800
4 Papan kelas II 0.0040 m3 9,500,000 38,000
a Pekerja 0.1250 Org/Hari 60,000 7,500
b Tukang Kayu Kasar 0.2500 Org/Hari 80,000 20,000
c Kepala Tukang 0.0250 Org/Hari 80,000 2,000
d Mandor 0.0060 Org/Hari 95,000 570
JUMLAH 74,750

1 m1 Pengadaan dan pemasangan Seng Gelombang


1 Seng Gelombang BJLS 0,3 0.7000 lbr 100,100 70,070
2 Paku 1 s/d 3 cm 0.0200 kg 20,020 400
a Pekerja 0.1200 Org/Hari 60,000 7,200
b Tukang Kayu Kasar 0.0600 Org/Hari 80,000 4,800
c Kepala Tukang 0.0060 Org/Hari 80,000 480
d Mandor 0.0060 Org/Hari 95,000 570
JUMLAH 83,520

1 m1 Pengadaan dan pemasangan Nok Seng Gelombang


1 Seng Gelombang BJLS 0,3 0.3000 lbr 100,100 30,030
2 Paku 1 s/d 3 cm 0.0400 kg 20,020 801
a Pekerja 0.0150 Org/Hari 60,000 900
b Tukang Kayu Kasar 0.0700 Org/Hari 80,000 5,600
c Kepala Tukang 0.0080 Org/Hari 80,000 640
d Mandor 0.0060 Org/Hari 95,000 570
JUMLAH 38,541

1 m1 Pengadaan dan pemasangan Atap Zincalumn


1 Steel Corregouted Zincalum t. 0,45 mm Colorcoa 1.0500 m2 152,100 159,705
2 Paku Skrup 0.0200 Kg 20,000 400
a Pekerja 0.0150 Org/Hari 60,000 900
b Tukang Kayu Kasar 0.0750 Org/Hari 80,000 6,000
c Kepala Tukang 0.0080 Org/Hari 80,000 640
d Mandor 0.0060 Org/Hari 95,000 570
JUMLAH 168,215

1 m1 Pengadaan dan pemasangan Nok Atap Zincalumn


1 Nok Steel Sheet Zincalum t. 0,45 mm Colorcoat 1.2000 m' 109,850 131,820
2 Paku Skrup 0.0400 Kg 20,000 800
a Pekerja 0.1000 Org/Hari 60,000 6,000
b Tukang Kayu Kasar 1.0000 Org/Hari 80,000 80,000
c Kepala Tukang 0.0100 Org/Hari 80,000 800
d Mandor 0.0100 Org/Hari 95,000 950
JUMLAH 220,370
1 m1 Pengadaan dan pemasangan Alumunium Foil/Insulation
1 Alumunium Foil 1.2000 m2 6,000 7,200
2 Paku Skrup 0.0800 Kg 20,000 1,600
3 Ram Kawat Ayam 1.0200 m2 36,000 36,720
a Pekerja 0.1000 Org/Hari 60,000 6,000
b Tukang Kayu Kasar 1.0000 Org/Hari 80,000 80,000
c Kepala Tukang 0.0100 Org/Hari 80,000 800
d Mandor 0.0100 Org/Hari 95,000 950
JUMLAH 133,270

1 m2 Pengadaan dan pemasangan Railing


1 Cat Besi 1.0000 m2 28,900 28,900
2 Pipa Stainless Steel Ø 1" 0.0800 Btg 240,000 19,200
3 Pipa Stainless Steel Ø 1,5 " 0.0800 Btg 320,000 25,600
4 Pipa Stainless Steel Ø 2" 0.0800 Btg 400,000 32,000
a Pekerja 0.0600 Org/Hari 60,000 3,600
b Tukang Besi Tulangan 0.0600 Org/Hari 80,000 4,800
c Kepala Tukang 0.0060 Org/Hari 80,000 480
d Mandor 0.0030 Org/Hari 95,000 285
JUMLAH 114,865

1 m2 Pengadaan dan pemasangan Listplank Kayu kelas II


1 Cat Besi 1.0000 m2 28,900 28,900
2 Pipa Stainless Steel Ø 1" 0.0800 Btg 240,000 19,200
3 Pipa Stainless Steel Ø 1,5 " 0.0800 Btg 320,000 25,600
4 Pipa Stainless Steel Ø 2" 0.0800 Btg 400,000 32,000
a Pekerja 0.0600 Org/Hari 60,000 3,600
b Tukang Besi Tulangan 0.0600 Org/Hari 80,000 4,800
c Kepala Tukang 0.0060 Org/Hari 80,000 480
d Mandor 0.0030 Org/Hari 95,000 285
JUMLAH 114,865

1 kg Memasang rangka kuda2 baja IWF (SNI:7393:2008-6.2)


1 Besi Profil 1.1500 Kg 20,000 23,000
a Pekerja 0.0600 Org/Hari 60,000 3,600
b Tukang Kayu Halus 0.0600 Org/Hari 80,000 4,800
c Kepala Tukang 0.0060 Org/Hari 80,000 480
d Mandor 0.0030 Org/Hari 95,000 285
JUMLAH 32,165
DIBULATKAN 32,100

1 Pemasangan Kayu Dolken


1 Dolken dia 5 s/d 7 cm p. 4 m 1.0000 btg 13,144 13,144
a Pekerja 0.0600 Org/Hari 75,000 4,500
b Tukang Batu 0.0600 Org/Hari 100,000 6,000
c Kepala Tukang 0.0060 Org/Hari 115,000 690
d Mandor 0.0030 Org/Hari 115,000 345
JUMLAH 24,679

1 m' Pekerjaan Tangga Monyet


a Besi beton Ø13 1.05 Kg 8,974 9,423
c Pekerja 0.01 Org/Hari 60,000 600
d Tukang Batu Kasar 0.01 Org/Hari 80,000 800
JUMLAH 10,823
JUMLAH 21,646

1 m2 Pengadaan dan pemasangan kaca tempered 6mm laminated (SNI:7393:2008-6.17)


1 Kaca Tempered 6 mm 1.1000 m2 250,000 275,000
2 Sealant clear neutral (300 ml) 0.2700 tb 35,000 9,450
a Pekerja 0.2000 Org/Hari 60,000 12,000
b Tukang Kayu Halus 0.2000 Org/Hari 80,000 16,000
c Kepala Tukang 0.0200 Org/Hari 80,000 1,600
d Mandor 0.0010 Org/Hari 95,000 95
JUMLAH 314,145
1 m2 Pengadaan dan pemasangan kaca tempered 10mm laminated (SNI:7393:2008-6.17)
1 Kaca Tempered 10 mm 1.1000 m2 400,000 440,000
2 Sealant clear neutral (300 ml) 0.2700 tb 35,000 9,450
a Pekerja 0.2000 Org/Hari 60,000 12,000
b Tukang Kayu Halus 0.2000 Org/Hari 80,000 16,000
c Kepala Tukang 0.0200 Org/Hari 80,000 1,600
d Mandor 0.0010 Org/Hari 95,000 95
JUMLAH 479,145

1 m2 Pengadaan dan pemasangan rangka pipa stainless 4" (dihitung)


1 Pipa Stainless Steel Ø 4" 0.2500 Btg 585,000 146,250
a Pekerja 0.1500 Org/Hari 60,000 9,000
b Tukang Kayu Halus 0.2500 Org/Hari 80,000 20,000
c Kepala Tukang 0.0500 Org/Hari 80,000 4,000
d Mandor 0.0100 Org/Hari 95,000 950
JUMLAH 180,200

1 m2 Pengadaan dan pemasangan rangka pipa stainless 3" (dihitung)


1 Pipa Stainless Steel Ø 3" 0.2500 Btg 480,000 120,000
a Pekerja 0.1500 Org/Hari 60,000 9,000
b Tukang Kayu Halus 0.2500 Org/Hari 80,000 20,000
c Kepala Tukang 0.0500 Org/Hari 80,000 4,000
d Mandor 0.0100 Org/Hari 95,000 950
JUMLAH 153,950

1 m2 Pekeraan Gutter Lantai (uk. = 40x40 cm) (dihitung)


1 Keramik Lantai 40/40 cm Polished 1.1 m2 90,000 99,000
2 Semen PC (50 Kg) 0.196 zak 90,000 17,640
3 Pasir Pasang 0.045 m3 153,000 6,885
4 Semen warna 1.3 kg 8,000 10,400
a Pekerja 0.7 Org/Hari 75,000 52,500
b Tukang Batu Kasar 0.35 Org/Hari 100,000 35,000
c Kepala Tukang 0.035 Org/Hari 115,000 4,025
d Mandor 0.035 Org/Hari 115,000 4,025
JUMLAH 229,475
Analisa u/
Berat per Breakdown
BERAT BESI Batang (x0,105)

1 Besi Beton :
Besi beton ø 6 mm - 12 m 2.66 kg 2.793 kg
Besi beton ø 8 mm - 12 m 3.20 kg 3.36 kg
Besi beton ø 10 mm - 12 m 7.40 kg 7.77 kg
Besi beton ø 12 mm - 12 m 10.66 kg 11.193 kg
Besi beton ø 13 mm - 12 m 12.48 kg 13.104 kg
Besi beton ø 16 mm - 12 m 18.96 kg 19.908 kg
Besi beton ø 19 mm - 12 m 26.76 kg 28.098 kg
Besi beton ø 22 mm - 12 m 35.76 kg 37.548 kg

2 Besi Bordes Plat :


Plat 4" x 8" tebal 2.3 mm 59.00 kg
Plat 4" x 8" tebal 3.0 mm 75.00 kg
Plat 4" x 8" tebal 3.2 mm 79.60 kg
Plat 4" x 8" tebal 4.5 mm 110.00 kg
Plat 4" x 8" tebal 6.0 mm 145.00 kg
Plat 4" x 8" tebal 8.0 mm 192.00 kg
Plat 4" x 8" tebal 9.0 mm 215.00 kg

3 Besi Kanal "C" / Lip Channel "C"


60 x 30 x 10 x 1.6 mm - 6 M 9.76 kg
75 x 35 x 15 x 1.6 mm - 6 M 12.40 kg
75 x 45 x 15 x 1.6 mm - 6 M 13.93 kg
75 x 45 x 15 x 2.3 mm - 6 M 19.50 kg
100 x 50 x 20 x 1.6 mm - 6 M 17.50 kg
100 x 50 x 20 x 2.3 mm - 6 M 24.40 kg
100 x 50 x 20 x 3.2 mm - 6 M 33.00 kg
125 X 50 X 20 X 2.3 mm - 6 M 27.10 kg
125 X 50 X 20 X 3.2 mm - 6 M 36.80 kg
150 x 50 x 20 x 2.3 mm - 6 M 29.80 kg
150 x 50 x 20 x 3.2 mm - 6 M 40.60 kg
150 x 65 x 20 x 2.3 mm - 6 M 33.00 kg
150 x 65 x 20 x 3.2 mm - 6 M 45.10 kg
200 x 75 x 20 x 3.2 mm - 6 M 55.62 kg

4 Besi Siku / Angle Bars


20 x 20 x 3 mm - 6 M 5.31 kg
25 x 25 x 3 mm - 6 M 6.72 kg
20 x 20 x 5 mm - 6 M 10.60 kg
30 x 30 x 3 mm - 6 M 8.16 kg
40 x 40 x 3 mm - 6 M 11.00 kg
40 x 40 x 4 mm - 6 M 14.50 kg
40 x 40 x 5 mm - 6 M 18.00 kg
45 x 45 x 4 mm - 6 M 16.44 kg
45 x 45 x 5 mm - 6 M 20.50 kg
50 x 50 x 4 mm - 6 M 18.40 kg
50 x 50 x 5 mm - 6 M 22.50 kg
50 x 50 x 6 mm - 6 M 27.58 kg
60 x 60 x 5 mm - 6 M 27.30 kg
60 x 60 x 6 mm - 6 M 32.52 kg
65 x 65 x 6 mm - 6 M 35.46 kg
70 x 70 x 6 mm - 6 M 38.28 kg
70 x 70 x 7 mm - 6 M 44.28 kg
75 x 75 x 6 mm - 6 M 41.22 kg
75 x 75 x 7 mm - 6 M 45.00 kg
75 x 75 x 8 mm - 6 M 54.18 kg
75 x 75 x 9 mm - 6 M 59.80 kg
80 x 80 x 8 mm - 6 M 57.96 kg
90 x 90 x 6.6 mm - 6 M 57.54 kg
90 x 90 x 7 mm - 6 M 57.54 kg
90 x 90 x 9 mm - 6 M 73.20 kg
90 x 90 x 10 mm - 6 M 79.80 kg
100 x 100 x 7 mm - 6 M 64.25 kg
100 x 100 x 10 mm - 6 M 90.60 kg
120 x 120 x 11 mm - 6 M 119.40 kg
120 x 120 x 12 mm - 6 M 130.00 kg
125 x 125 x 12 mm - 6 M 140.00 kg
130 x 130 x 9 mm - 6 M 107.10 kg
130 x 130 x 12 mm - 6 M 140.10 kg
150 x 150 x 12 mm - 6 M 164.00 kg
150 x 150 x 15 mm - 6 M 202.00 kg

5 Besi Wide Flange ex. Jepang


100 x 50 x 5 x 7 mm - 12 M 112.00 kg
125 x 60 x 6 x 8 mm - 12 M 158.40 kg
150 x 75 x 5 x 7 mm - 12 M 168.00 kg
175 x 90 x 5 x 8 mm - 12 M 217.20 kg
200 x 100 x 3.2 x 4.5 mm - 12 M 143.00 kg
200 x 100 x 5.5 x 8 mm - 12 M 256.00 kg
250 x 125 x 6 x 9 mm - 12 M 355.20 kg
300 x 150 x 6.5 x 9 mm - 12 M 440.40 kg
400 x 200 x 8 x 13 mm - 12 M 792.00 kg
400 x 250 x 12 x 19 mm - 12 M 1317.40 kg
450 x 200 x 9 x 14 mm - 12 M 912.00 kg
500 x 200 x 10 x 16 mm - 12 M 1075.00 kg
600 x 200 x 11 x 17 mm - 12 M 1272.00 kg
700 x 300 x 13 x 24 mm - 12 M 2220.00 kg
800 x 300 x 14 x 26 mm - 12 M 2520.00 kg

6 Besi H Beam
100 x 100 x 6 x 8 mm - 12 M 206.00 kg
125 x 125 x 5 x 7 mm - 12 M 222.00 kg
125 x 125 x 6.5 x 9 mm - 12 M 286.00 kg
150 x 150 x 7 x 10 mm - 12 M 378.00 kg
175 x 175 x 7 x 11 mm - 12 M 482.00 kg
200 x 200 x 8 x 12 mm - 12 M 599.00 kg
250 x 250 x 9 x 14 mm - 12 M 869.00 kg
300 x 300 x 10 x 15 mm - 12 M 1128.00 kg
350 x 350 x 12 x 19 mm - 12 M 1644.00 kg
400 x 400 x 13 x 21 mm - 12 M 2064.00 kg

7 Pipa Hitam STK 41


Dia 2 1/2" tebal 2.8 mm - 6 M 30.48 kg
Dia 2 1/2" tebal 3.2 mm - 6 M 34.62 kg
Dia 3" tebal 3.2 mm - 6 M 40.68 kg
Dia 4" tebal 3.5 mm - 6 M 57.36 kg
Dia 4" tebal 4.5 mm - 6 M 73.20 kg
Dia 5" tebal 4.5 mm - 6 M 90.00 kg
Dia 5" tebal 6.0 mm - 6 M 118.80 kg
Dia 6" tebal 4.5 mm - 6 M 106.80 kg
Dia 6" tebal 5.0 mm - 6 M 118.00 kg
Dia 6" tebal 6.0 mm - 6 M 141.60 kg
Dia 7" tebal 5.3 mm - 6 M 145.20 kg
Dia 8" tebal 5.8 mm - 6 M 180.60 kg
Dia 8" tebal 8.2 mm - 6 M 252.60 kg
Dia 10" tebal 6.6 mm - 6 M 254.40 kg
J.PEKERJAAN PIPA dan SANITER (Pt T-38-2000-C)

1 Bh Pengadaan dan Pemasangan Kloset Duduk / Monoblok (Pt T-38-2000-C) 6.1


1 Kloset Duduk Porselen 1.0000 unt 2,000,000 2,000,000
2 Perlengkapan 0.0600 persen 2,000,000 120,000
a Pekerja 3.3000 Org/Hari 60,000 198,000
b Tukang Batu Halus 1.1000 Org/Hari 80,000 88,000
c Kepala Tukang 0.0010 Org/Hari 80,000 80
d Mandor 0.1600 Org/Hari 95,000 15,200
JUMLAH 2,406,080

1 Bh Pengadaan dan Pemasangan Kloset Type CW 421 J dihitung


1 Kloset Duduk Toto CW 421 J 1.0000 unt 3,616,600 3,616,600
2 Perlengkapan 0.0600 persen 3,616,600 216,996
a Pekerja 3.3000 Org/Hari 60,000 198,000
b Tukang Batu Halus 1.1000 Org/Hari 80,000 88,000
c Kepala Tukang 0.0010 Org/Hari 80,000 80
d Mandor 0.1600 Org/Hari 95,000 15,200
JUMLAH 4,119,676

1 Bh Pengadaan dan Pemasangan Kloset Jongkok Porselen (Pt T-38-2000-C) 6.2


1 Kloset Jongkok Porselen Putih 1.0000 unt 450,000 450,000
2 Semen PC (50 Kg) 0.1200 zak 63,500 7,620
3 Pasir Pasang 0.0100 m3 135,000 1,350
a Pekerja 1.0000 Org/Hari 60,000 60,000
b Tukang Batu Halus 1.5000 Org/Hari 80,000 120,000
c Kepala Tukang 0.1500 Org/Hari 80,000 12,000
d Mandor 0.1600 Org/Hari 95,000 15,200
JUMLAH 650,970

1 Bh Pengadaan dan Pemasangan Kloset Jongkok Keramik (Pt T-38-2000-C) 6.3


1 Kloset Jongkok Keramik 1.0000 unt 425,000 425,000
2 Bata Merah 8.2600 bh 600 4,956
3 Semen PC (50 Kg) 0.1200 zak 63,500 7,620
4 Pasir Pasang 0.0100 m3 135,000 1,350
a Pekerja 1.0000 Org/Hari 60,000 60,000
b Tukang Batu Halus 1.5000 Org/Hari 80,000 120,000
c Kepala Tukang 0.3000 Org/Hari 80,000 24,000
d Mandor 0.1100 Org/Hari 95,000 10,450
JUMLAH 642,926

1 Bh Pengadaan dan Pemasangan Urinoir (Pt T-38-2000-C) 6.4


1 Urinoir keramik komplit acc 1.0000 unt 2,120,000 2,120,000
2 Perlengkapan 0.3000 persen 2,120,000 636,000
3 Semen PC (50 Kg) 0.1200 zak 63,500 7,620
4 Pasir Pasang 0.0100 m3 135,000 1,350
a Pekerja 1.0000 Org/Hari 60,000 60,000
b Tukang Batu Halus 1.0000 Org/Hari 80,000 80,000
c Kepala Tukang 0.1000 Org/Hari 80,000 8,000
d Mandor 0.1000 Org/Hari 95,000 9,500
JUMLAH 2,912,970
1 Bh Pengadaan dan Pemasangan Washtafel (Pt T-38-2000-C) 6.5
1 Washtafel Keramik (lengkap) 1.0000 unt 750,000 750,000
2 Perlengkapan 0.1200 persen 750,000 90,000
3 Semen Warna 6.0000 kg 12,500 75,000
4 Pasir Pasang 0.0100 m3 135,000 1,350
a Pekerja 1.2000 Org/Hari 60,000 72,000
b Tukang Batu Halus 1.4500 Org/Hari 80,000 116,000
c Kepala Tukang 0.1500 Org/Hari 80,000 12,000
d Mandor 0.1000 Org/Hari 95,000 9,500
JUMLAH 1,116,350

1 bh Pengadaan dan Pemasangan Bak Mandi Teraso (Pt T-38-2000-C) 6.6


1 Bak mandi Teraso 1.0000 set 650,000 650,000
2 Semen PC (50 Kg) 0.1200 zak 63,500 7,620
3 Pasir Pasang 0.0100 m3 135,000 1,350
a Pekerja 2.1000 Org/Hari 60,000 126,000
b Tukang Batu Halus 0.7500 Org/Hari 80,000 60,000
c Kepala Tukang 0.0700 Org/Hari 80,000 5,600
d Mandor 0.1100 Org/Hari 95,000 10,450
JUMLAH 861,020

1 bh Pengadaan dan Pemasangan Bak Mandi Fiberglass vol 0,3 m3 (Pt T-38-2000-C) 6.7
1 Bak air fibreglass uk. 55x55x60 cm 1.0000 bh 916,000 916,000
2 Perlengkapan 0.1800 persen 916,000 164,880
a Pekerja 1.8000 Org/Hari 60,000 108,000
b Tukang Batu Halus 2.7000 Org/Hari 80,000 216,000
c Kepala Tukang 0.0500 Org/Hari 80,000 4,000
d Mandor 0.0100 Org/Hari 95,000 950
JUMLAH 1,409,830

1 bh Pengadaan dan Pemasangan Bak Mandi Batu Bata vol 0,3 m3 (Pt T-38-2000-C) 6.8
1 Bata Merah 330.4000 bh 600 198,240
2 Semen PC (50 Kg) 2.4000 zak 63,500 152,400
3 Pasir Pasang 0.3000 m3 135,000 40,500
4 Dinding Porselen 11/11 cm 3.6000 m2 32,500 117,000
5 Semen Putih 6.0000 kg 2,000 12,000
a Pekerja 6.0000 Org/Hari 60,000 360,000
b Tukang Batu Halus 3.0000 Org/Hari 80,000 240,000
c Kepala Tukang 0.3000 Org/Hari 80,000 24,000
d Mandor 0.3000 Org/Hari 95,000 28,500
JUMLAH 1,172,640

1 bh Pengadaan dan Pemasangan Bakdip Porselen (Pt T-38-2000-C) 6.9


1 Bakdip 1.0000 Bh 1,950,000 1,950,000
2 Perlengkapan 0.2000 persen 1,950,000 390,000
a Tukang Batu Halus 0.0750 Org/Hari 80,000 6,000
b Kepala Tukang 0.7500 Org/Hari 80,000 60,000
c Mandor 0.2500 Org/Hari 95,000 23,750
JUMLAH 2,429,750
1 bh Pengadaan dan Pemasangan Bak Beton Vol 1 m3 air (Pt T-38-2000-C) 6.10
1 Beton 0.9000 m3 2,600,000 2,340,000
2 Pembersih 180.0000 kg 4,500 810,000
3 Kayu cetakan 8.0000 m3 2,340,000 18,720,000
4 Dinding Porselen 11/11 cm 5.0000 m2 32,500 162,500
5 Perlengkapan 0.1000 ls 22,032,500 2,203,250
a Pekerja 3.5000 Org/Hari 60,000 210,000
b Tukang Batu Halus 4.5000 Org/Hari 80,000 360,000
c Kepala Tukang 0.9000 Org/Hari 80,000 72,000
d Mandor 0.9000 Org/Hari 95,000 85,500
JUMLAH 24,963,250

1 bh Pengadaan dan Pemasangan Bak Mandi Fiberglass vol 1m3 (Pt T-38-2000-C) 6.11
1 Bak air fibreglass uk. 55x55x60 cm 1.0000 bh 523,900 523,900
2 Perlengkapan 0.1200 persen 523,900 62,868
a Pekerja 3.0000 Org/Hari 60,000 180,000
b Tukang Batu Halus 4.5000 Org/Hari 80,000 360,000
c Kepala Tukang 0.9000 Org/Hari 80,000 72,000
d Mandor 0.9000 Org/Hari 95,000 85,500
JUMLAH 1,284,268

1 m Pengadaan dan Pemasangan Pipa Penyalur Air Limbah Jenis Pipa Tanah d=20 cm (Pt T-38-2000-C) 6.12
1 Pipa PVC 1.6000 bh 65,000 104,000
2 Semen PC (50 Kg) 0.0136 zak 63,500 864
3 Pasir Pasang 0.0130 m3 135,000 1,755
4 Pasir Urug 0.1100 m3 100,000 11,000
a Pekerja 0.0600 Org/Hari 60,000 3,600
b Tukang Batu Halus 0.0300 Org/Hari 80,000 2,400
c Kepala Tukang 0.0030 Org/Hari 80,000 240
d Mandor 0.0025 Org/Hari 95,000 238
JUMLAH 124,096

1 m3 Pengadaan dan Pemasangan Pipa Penyalur Air Limbah Jenis Pipa Tanah d=15 cm (Pt T-38-2000-C) 6.13
1 Pipa PVC 1.6000 bh 65,000 104,000
2 Semen PC (50 Kg) 0.0174 zak 63,500 1,105
3 Pasir Pasang 0.0140 m3 135,000 1,890
4 Pasir Urug 0.0140 m3 100,000 1,400
a Pekerja 0.0800 Org/Hari 60,000 4,800
b Tukang Batu Halus 0.0400 Org/Hari 80,000 3,200
c Kepala Tukang 0.0040 Org/Hari 80,000 320
d Mandor 0.0070 Org/Hari 95,000 665
JUMLAH 117,380

1 m3 Pengadaan dan Pemasangan Pipa Beton d= 15-20 cm (Pt T-38-2000-C) 6.14


1 Pipa PVC 1.1000 bh 65,000 71,500
2 Bata Merah 22.3020 bh 600 13,381
3 Semen PC (50 Kg) 0.0784 zak 63,500 4,978
4 Pasir Pasang 0.0560 m3 135,000 7,560
5 Pasir Urug 0.0240 m3 100,000 2,400
a Pekerja 0.1400 Org/Hari 60,000 8,400
b Tukang Batu Halus 0.0700 Org/Hari 80,000 5,600
c Kepala Tukang 0.0070 Org/Hari 80,000 560
d Mandor 0.0070 Org/Hari 95,000 665
JUMLAH 115,045

1 m3 Pengadaan dan Pemasangan Pipa Beton d= 30-100 cm (Pt T-38-2000-C) 6.15


1 Pipa PVC 1.1000 bh 65,000 71,500
2 Bata Merah 454.3000 bh 600 272,580
3 Semen PC (50 Kg) 0.2060 zak 63,500 13,081
4 Pasir Pasang 0.0610 m3 135,000 8,235
5 Pasir Urug 0.0690 m3 100,000 6,900
a Pekerja 0.3800 Org/Hari 60,000 22,800
b Tukang Batu Halus 0.1900 Org/Hari 80,000 15,200
c Kepala Tukang 0.0190 Org/Hari 80,000 1,520
d Mandor 0.0190 Org/Hari 95,000 1,805
JUMLAH 413,621
1 bh Pengadaan dan Pemasangan Bak Kontrol pasangan batu bata uk. 30x30x50 cm (Pt T-38-2000-C) 6.16
1 Bata Merah 119.7700 bh 600 71,862
2 Semen PC (50 Kg) 0.8800 zak 63,500 55,880
3 Pasir Pasang 0.0700 m3 135,000 9,450
4 Batu Split Pecah Mesin 1/2 0.0700 m3 145,000 10,150
5 Besi Beton rata-rata 2.6000 Kg 1,721 4,474
6 Pasir Beton 0.0900 m3 145,000 13,050
a Pekerja 1.4200 Org/Hari 60,000 85,200
b Tukang Batu Halus 0.4730 Org/Hari 80,000 37,840
c Kepala Tukang 0.0470 Org/Hari 80,000 3,760
d Mandor 0.0710 Org/Hari 95,000 6,745
JUMLAH 298,411

1 bh Pengadaan dan Pemasangan Bak Kontrol pasangan batu bata uk. 45x45x50 cm (Pt T-38-2000-C) 6.17
1 Bata Merah 206.5000 bh 600 123,900
2 Semen PC (50 Kg) 1.5400 zak 63,500 97,790
3 Pasir Pasang 0.1300 m3 135,000 17,550
4 Batu Split Pecah Mesin 1/2 0.0200 m3 145,000 2,900
5 Besi Beton rata-rata 2.6000 Kg 1,721 4,474
6 Pasir Beton 0.0900 m3 145,000 13,050
a Pekerja 1.4200 Org/Hari 60,000 85,200
b Tukang Batu Halus 0.4730 Org/Hari 80,000 37,840
c Kepala Tukang 0.0470 Org/Hari 80,000 3,760
d Mandor 0.0710 Org/Hari 95,000 6,745
JUMLAH 393,209

1 bh Pengadaan dan Pemasangan Bak Kontrol pasangan batu bata uk. 60x60x65 cm (Pt T-38-2000-C) 6.18
1 Bata Merah 306.4460 bh 600 183,868
2 Semen PC (50 Kg) 2.2800 zak 63,500 144,780
3 Pasir Pasang 0.1840 m3 135,000 24,840
4 Batu Split Pecah Mesin 1/2 0.0330 m3 145,000 4,785
5 Besi Beton rata-rata 4.8500 Kg 1,721 8,347
6 Pasir Beton 0.1200 m3 145,000 17,400
a Pekerja 2.1600 Org/Hari 60,000 129,600
b Tukang Batu Halus 0.7200 Org/Hari 80,000 57,600
c Kepala Tukang 0.0720 Org/Hari 80,000 5,760
d Mandor 0.1080 Org/Hari 95,000 10,260
e Tukang Gali 0.1000 Org/Hari 75,000 7,500
JUMLAH 587,239

1 m3 Pengadaan dan Pemasangan Pipa Galvanis d = 1/2 " (Pt T-38-2000-C) 6.19
1 Pipa Galvanis d=1/2 " 1.2000 m1 130,000 156,000
2 Perlengkapan 0.3500 persen 130,000 45,500
a Pekerja 0.5400 Org/Hari 60,000 32,400
b Tukang Batu Halus 0.0900 Org/Hari 80,000 7,200
c Kepala Tukang 0.0090 Org/Hari 80,000 720
d Mandor 0.0270 Org/Hari 95,000 2,565
JUMLAH 244,385

1 m3 Pengadaan dan Pemasangan Pipa Galvanis d = 3/4 " (Pt T-38-2000-C) 6.20
1 Pipa Galvanis d=3/4 " 1.2000 m1 260,000 312,000
2 Perlengkapan 0.3500 persen 260,000 91,000
a Pekerja 0.5400 Org/Hari 60,000 32,400
b Tukang Batu Halus 0.0900 Org/Hari 80,000 7,200
c Kepala Tukang 0.0090 Org/Hari 80,000 720
d Mandor 0.0270 Org/Hari 95,000 2,565
JUMLAH 445,885

1 m3 Pengadaan dan Pemasangan Pipa Galvanis d = 1" (Pt T-38-2000-C) 6.21


1 Pipa Galvanis d= 1 " 1.2000 m1 325,000 390,000
2 Perlengkapan 0.3500 persen 325,000 113,750
a Pekerja 0.5400 Org/Hari 60,000 32,400
b Tukang Batu Halus 0.0900 Org/Hari 80,000 7,200
c Kepala Tukang 0.0090 Org/Hari 80,000 720
d Mandor 0.0270 Org/Hari 95,000 2,565
JUMLAH 546,635

1 m3 Pengadaan dan Pemasangan Pipa Galvanis d = 1 1/2" (Pt T-38-2000-C) 6.22


1 Pipa Galvanis d=1 1/2 " 1.2000 m1 390,000 468,000
2 Perlengkapan 0.3500 persen 390,000 136,500
a Pekerja 0.1080 Org/Hari 60,000 6,480
b Tukang Batu Halus 0.1800 Org/Hari 80,000 14,400
c Kepala Tukang 0.0180 Org/Hari 80,000 1,440
d Mandor 0.0054 Org/Hari 95,000 513
JUMLAH 627,333
1 m3 Pengadaan dan Pemasangan Pipa Galvanis d = 3" (Pt T-38-2000-C) 6.23
1 Pipa Galvanis d=1 1/2 " 1.2000 m1 390,000 468,000
2 Perlengkapan 0.3500 persen 390,000 136,500
a Pekerja 0.1080 Org/Hari 60,000 6,480
b Tukang Batu Halus 0.1800 Org/Hari 80,000 14,400
c Kepala Tukang 0.0180 Org/Hari 80,000 1,440
d Mandor 0.0054 Org/Hari 95,000 513
JUMLAH 627,333

1 m3 Pengadaan dan Pemasangan Pipa Galvanis d = 4" (Pt T-38-2000-C) 6.24


1 Pipa Galvanis d=4 " 1.2000 m1 455,000 546,000
2 Perlengkapan 0.3500 persen 455,000 159,250
a Pekerja 0.1350 Org/Hari 60,000 8,100
b Tukang Batu Halus 0.2250 Org/Hari 80,000 18,000
c Kepala Tukang 0.0225 Org/Hari 80,000 1,800
d Mandor 0.0068 Org/Hari 95,000 646
JUMLAH 733,796

1 m3 Pengadaan dan Pemasangan Pipa PVC tipe AW d = 1/2" (Pt T-38-2000-C) 6.25
1 Pipa PVC d=1/2 " 1.2000 m1 455,000 546,000
2 Perlengkapan 0.3500 persen 455,000 159,250
a Pekerja 0.0360 Org/Hari 60,000 2,160
b Tukang Batu Halus 0.0600 Org/Hari 80,000 4,800
c Kepala Tukang 0.0060 Org/Hari 80,000 480
d Mandor 0.0018 Org/Hari 95,000 171
JUMLAH 712,861

1 m3 Pengadaan dan Pemasangan Pipa PVC tipe AW d = 3/4" (Pt T-38-2000-C) 6.26
1 Pipa PVC d=3/4 " 1.2000 m1 455,000 546,000
2 Perlengkapan 0.3500 persen 455,000 159,250
a Pekerja 0.0360 Org/Hari 60,000 2,160
b Tukang Batu Halus 0.0600 Org/Hari 80,000 4,800
c Kepala Tukang 0.0060 Org/Hari 80,000 480
d Mandor 0.0018 Org/Hari 95,000 171
JUMLAH 712,861

1 m3 Pengadaan dan Pemasangan Pipa PVC tipe AW d = 1" (Pt T-38-2000-C) 6.27
1 Pipa PVC d= 1 " 1.2000 m1 455,000 546,000
2 Perlengkapan 0.3500 persen 455,000 159,250
a Pekerja 0.0360 Org/Hari 60,000 2,160
b Tukang Batu Halus 0.0600 Org/Hari 80,000 4,800
c Kepala Tukang 0.0060 Org/Hari 80,000 480
d Mandor 0.0018 Org/Hari 95,000 171
JUMLAH 712,861

1 m3 Pengadaan dan Pemasangan Pipa PVC tipe AW d = 1 1/2" (Pt T-38-2000-C) 6.28
1 Pipa PVC d= 1 1/2 " 1.2000 m1 455,000 546,000
2 Perlengkapan 0.3500 persen 455,000 159,250
a Pekerja 0.0360 Org/Hari 60,000 2,160
b Tukang Batu Halus 0.0600 Org/Hari 80,000 4,800
c Kepala Tukang 0.0060 Org/Hari 80,000 480
d Mandor 0.0018 Org/Hari 95,000 171
JUMLAH 712,861

1 m3 Pengadaan dan Pemasangan Pipa PVC tipe AW d = 2" (Pt T-38-2000-C) 6.29
1 Pipa PVC d= 2 " 1.2000 m1 455,000 546,000
2 Perlengkapan 0.3500 persen 455,000 159,250
a Pekerja 0.0540 Org/Hari 60,000 3,240
b Tukang Batu Halus 0.0900 Org/Hari 80,000 7,200
c Kepala Tukang 0.0090 Org/Hari 80,000 720
d Mandor 0.0027 Org/Hari 95,000 257
JUMLAH 716,667

1 m3 Pengadaan dan Pemasangan Pipa PVC tipe AW d = 2 1/2" (Pt T-38-2000-C) 6.30
1 Pipa PVC d= 2 1/2 " 1.2000 m1 455,000 546,000
2 Perlengkapan 0.3500 persen 455,000 159,250
a Pekerja 0.0360 Org/Hari 60,000 2,160
b Tukang Batu Halus 0.0600 Org/Hari 80,000 4,800
c Kepala Tukang 0.0060 Org/Hari 80,000 480
d Mandor 0.0018 Org/Hari 95,000 171
JUMLAH 712,861
1 m3 Pengadaan dan Pemasangan Pipa PVC tipe AW d = 3" (Pt T-38-2000-C) 6.31
1 Pipa PVC d= 3 " 1.2000 m1 455,000 546,000
2 Perlengkapan 0.3500 persen 455,000 159,250
a Pekerja 0.0810 Org/Hari 60,000 4,860
b Tukang Batu Halus 0.1350 Org/Hari 80,000 10,800
c Kepala Tukang 0.1350 Org/Hari 80,000 10,800
d Mandor 0.0041 Org/Hari 95,000 390
JUMLAH 732,100

1 m3 Pengadaan dan Pemasangan Pipa PVC tipe AW d = 4" (Pt T-38-2000-C) 6.32
1 Pipa PVC d= 4 " 1.2000 m1 455,000 546,000
2 Perlengkapan 0.3500 persen 455,000 159,250
a Pekerja 0.0810 Org/Hari 60,000 4,860
b Tukang Batu Halus 0.1350 Org/Hari 80,000 10,800
c Kepala Tukang 0.1350 Org/Hari 80,000 10,800
d Mandor 0.0041 Org/Hari 95,000 390
JUMLAH 732,100

1 Bh Pengadaan dan Pemasangan Bak Cuci Piring Stainless Steel (Pt T-38-2000-C) 6.33
1 Kitchenzink stainless steel 1 lubang 1.0000 unt 17,500 17,500
2 Water drain+aksesoris 1.0000 set 195,000 195,000
a Tukang Batu Halus 0.3000 Org/Hari 80,000 24,000
b Kepala Tukang 0.0300 Org/Hari 80,000 2,400
JUMLAH 238,900

1 Bh Pengadaan dan Pemasangan Bak Cuci Piring Teraso (Pt T-38-2000-C) 6.34
1 Kitchenzink teraso 1 lubang 1.0000 bh 130,000 130,000
2 Water drain+aksesoris 1.0000 set 195,000 195,000
3 Semen PC (50 Kg) 0.4000 zak 63,500 25,400
4 Pasir Pasang 0.0500 m3 135,000 6,750
a Tukang Batu Halus 0.5000 Org/Hari 80,000 40,000
b Kepala Tukang 0.0500 Org/Hari 80,000 4,000
JUMLAH 401,150
1 Bh Pengadaan dan Pemasangan Kran Air diameter 3/4" atau 1/2 " (Pt T-38-2000-C) 6.35
1 Kran dinding 4 jari 1.0000 bh 188,000 188,000
2 Seal tape 0.0250 roll 314,000 7,850
a Tukang Batu Halus 0.1000 Org/Hari 80,000 8,000
b Kepala Tukang 0.0100 Org/Hari 80,000 800
JUMLAH 204,650

1 Bh Pengadaan dan Pemasangan Floor Drain (Pt T-38-2000-C) 6.36


1 Floordrain 1.0000 unt 367,000 367,000
a Tukang Batu Halus 0.1000 Org/Hari 80,000 8,000
b Kepala Tukang 0.0100 Org/Hari 80,000 800
JUMLAH 375,800

1 Bh Pengadaan dan Pemasangan Jetwasher (dihitung) 6.35


1 Water drain+aksesoris 1.0000 set 195,000 195,000
2 Seal tape 0.0250 roll 25,000 625
a Tukang Batu Halus 0.1000 Org/Hari 80,000 8,000
b Kepala Tukang 0.0100 Org/Hari 80,000 800
JUMLAH 204,425

1 Bh Pengadaan dan Pemasangan Toilet Paper Holder (dihitung) 6.35


1 Tempat Tissue Inbow 1.0000 unt 509,600 509,600
2 Seal tape 0.0250 roll 25,000 625
a Tukang Batu Halus 0.1000 Org/Hari 80,000 8,000
b Kepala Tukang 0.0100 Org/Hari 80,000 800
JUMLAH 519,025

1 Bh Pengadaan dan Pemasangan Kran Sink (Pt T-38-2000-C) 6.35


1 Kran Air 3/4" 1.0000 bh 78,000 78,000
2 Seal tape 0.0250 roll 161,500 4,038
a Tukang Batu Halus 0.1000 Org/Hari 80,000 8,000
b Kepala Tukang 0.0100 Org/Hari 80,000 800
JUMLAH 90,838
1 Bh Pengadaan dan Pemasangan Roof Drain (Pt T-38-2000-C) 6.36
1 Roof drain 1.0000 bh 234,000 234,000
a Tukang Batu Halus 0.1000 Org/Hari 80,000 8,000
b Kepala Tukang 0.0100 Org/Hari 80,000 800
JUMLAH 242,800
1 Bh Pengadaan dan Pemasangan Divider (Pt T-38-2000-C) 6.5
1 Urinoir Partisi Keramik 1.0000 unt 961,000 961,000
2 Perlengkapan 0.1200 persen 961,000 115,320
3 Semen Warna 6.0000 kg 12,500 75,000
4 Pasir Pasang 0.0100 m3 135,000 1,350
a Pekerja 1.2000 Org/Hari 60,000 72,000
b Tukang Batu Halus 1.4500 Org/Hari 80,000 116,000
c Kepala Tukang 0.1500 Org/Hari 80,000 12,000
d Mandor 0.1000 Org/Hari 95,000 9,500
JUMLAH 1,352,670

1 Bh Pengadaan dan Pemasangan Shower (Pt T-38-2000-C) 6.35


1 Shower 1.0000 bh 245,000 245,000
2 Seal tape 0.0250 roll 39,470 987
a Tukang Batu Halus 0.1000 Org/Hari 80,000 8,000
b Kepala Tukang 0.0100 Org/Hari 80,000 800
JUMLAH 254,787
PEKERJAAN KUNCI,ALAT GANTUNGAN dan KACA (SNI 2002)

1 Bh Pengadaan dan Pemasangan Kunci Silinder (SNI 2002) No.1


1 Kunci Silinder 1.0000 bh 13,000 13,000
a Pekerja 0.0050 Org/Hari 60,000 300
b Tukang Kayu Halus 0.5000 Org/Hari 80,000 40,000
c Kepala Tukang 0.0050 Org/Hari 80,000 400
d Mandor 0.0003 Org/Hari 95,000 24
JUMLAH 53,700

1 Bh Pengadaan dan Pemasangan Engsel Pintu (SNI 2002) No.2


1 Engsel 3" 1.0000 bh 22,500 22,500
a Pekerja 0.0150 Org/Hari 60,000 900
b Tukang Kayu Halus 0.1500 Org/Hari 80,000 12,000
c Kepala Tukang 0.0150 Org/Hari 80,000 1,200
d Mandor 0.0008 Org/Hari 95,000 71
JUMLAH 36,600

1 Bh Pengadaan dan Pemasangan Engsel Jendela Kupu-kupu (SNI 2002) No.3


1 Engsel 3" 1.0000 bh 22,500 22,500
a Pekerja 0.0100 Org/Hari 60,000 600
b Tukang Kayu Halus 0.1000 Org/Hari 80,000 8,000
c Kepala Tukang 0.0100 Org/Hari 80,000 800
d Mandor 0.0005 Org/Hari 95,000 48
JUMLAH 31,900

1 Bh Pengadaan dan Pemasangan Engsel Angin (SNI 2002) No.4


1 Engsel 3" 1.0000 bh 22,500 22,500
a Pekerja 0.0200 Org/Hari 60,000 1,200
b Tukang Kayu Halus 0.2000 Org/Hari 80,000 16,000
c Kepala Tukang 0.0200 Org/Hari 80,000 1,600
d Mandor 0.0100 Org/Hari 95,000 950
JUMLAH 41,300

1 Bh Pengadaan dan Pemasangan Spring Knip (SNI 2002) No.5


1 Spring Knip 1.0000 bh 15,600 15,600
a Pekerja 0.0150 Org/Hari 60,000 900
b Tukang Kayu Halus 0.1500 Org/Hari 80,000 12,000
c Kepala Tukang 0.0150 Org/Hari 80,000 1,200
d Mandor 0.0008 Org/Hari 95,000 71
JUMLAH 29,700

1 Bh Pengadaan dan Pemasangan Kait Angin (SNI 2002) No.6


1 Hak Angin 1.0000 Pas 6,160 6,160
a Pekerja 0.0150 Org/Hari 60,000 900
b Tukang Kayu Halus 0.1500 Org/Hari 80,000 12,000
c Kepala Tukang 0.0150 Org/Hari 80,000 1,200
d Mandor 0.0008 Org/Hari 95,000 71
JUMLAH 20,260

1 Bh Pengadaan dan Pemasangan Door Closer (SNI 2002) No.7


1 Door Closer 1.0000 bh 13,000 13,000
a Pekerja 0.0500 Org/Hari 60,000 3,000
b Tukang Kayu Halus 0.5000 Org/Hari 80,000 40,000
c Kepala Tukang 0.0500 Org/Hari 80,000 4,000
d Mandor 0.0025 Org/Hari 95,000 238
JUMLAH 60,000
1 Bh Pengadaan dan Pemasangan Kunci Selot (SNI 2002) No.8
1 Slot Tanam 1.0000 bh 45,500 45,500
a Pekerja 0.0200 Org/Hari 60,000 1,200
b Tukang Kayu Halus 0.2000 Org/Hari 80,000 16,000
c Kepala Tukang 0.0200 Org/Hari 80,000 1,600
d Mandor 0.0010 Org/Hari 95,000 95
JUMLAH 64,300

1 Bh Pengadaan dan Pemasangan Door Holder / Pegangan Pintu (SNI 2002) No.9
1 Handle Pintu ex Solid 1.0000 bh 125,000 125,000
a Pekerja 0.0500 Org/Hari 60,000 3,000
b Tukang Kayu Halus 0.5000 Org/Hari 80,000 40,000
c Kepala Tukang 0.0500 Org/Hari 80,000 4,000
d Mandor 0.0025 Org/Hari 95,000 238
JUMLAH 172,000

1 Bh Pengadaan dan Pemasangan Door Stop (SNI 2002) No.10


1 Door Stop 1.0000 bh 19,500 19,500
a Pekerja 0.0100 Org/Hari 60,000 600
b Tukang Kayu Halus 0.1000 Org/Hari 80,000 8,000
c Kepala Tukang 0.0100 Org/Hari 80,000 800
d Mandor 0.0005 Org/Hari 95,000 48
JUMLAH 28,900

1 Bh Pengadaan dan Pemasangan Rel Pintu Dorong (SNI 2002) No.11


1 Rel Pintu Dorong 1.0000 set 513,500 513,500
a Pekerja 0.0600 Org/Hari 60,000 3,600
b Tukang Kayu Halus 0.6000 Org/Hari 80,000 48,000
c Kepala Tukang 0.0600 Org/Hari 80,000 4,800
d Mandor 0.0030 Org/Hari 95,000 285
JUMLAH 569,900

1 Bh Pengadaan dan Pemasangan Kunci Lemari (SNI 2002) No.12


1 Kunci Silinder 1.0000 bh 13,000 13,000
a Pekerja 0.0250 Org/Hari 60,000 1,500
b Tukang Kayu Halus 0.2500 Org/Hari 80,000 20,000
c Kepala Tukang 0.0250 Org/Hari 80,000 2,000
d Mandor 0.0013 Org/Hari 95,000 119
JUMLAH 36,500

1 Bh Pengadaan dan Pemasangan Kaca, tebal 3 mm (SNI 2002) No.13


1 Kaca Polos 3 mm 1.1000 m2 70,000 77,000
a Pekerja 0.0150 Org/Hari 60,000 900
b Tukang Kayu Halus 0.1500 Org/Hari 80,000 12,000
c Kepala Tukang 0.0150 Org/Hari 80,000 1,200
d Mandor 0.0008 Org/Hari 95,000 71
JUMLAH 91,100

1 Bh Pengadaan dan Pemasangan Kaca, tebal 5 mm (SNI 2002) No.14


1 Kaca Polos 5 mm 1.1000 m2 95,000 104,500
a Pekerja 0.0150 Org/Hari 60,000 900
b Tukang Kayu Halus 0.1500 Org/Hari 80,000 12,000
c Kepala Tukang 0.0150 Org/Hari 80,000 1,200
d Mandor 0.0008 Org/Hari 95,000 71
JUMLAH 118,600

1 Bh Pengadaan dan Pemasangan Kaca, tebal 8 mm (SNI 2002) No.15


1 Kaca Polos 8 mm 1.1000 m2 180,000 198,000
a Pekerja 0.0165 Org/Hari 60,000 990
b Tukang Kayu Halus 0.1650 Org/Hari 80,000 13,200
c Kepala Tukang 0.0165 Org/Hari 80,000 1,320
d Mandor 0.0008 Org/Hari 95,000 76
JUMLAH 213,510

1 Bh Pengadaan dan Pemasangan Kaca Buram, tebal 12 mm (SNI 2002) No.16


1 Kaca Buram 12mm 1.1000 m2 390,000 429,000
2 Sealant clear neutral (300 ml) 0.0500 tb 35,000 1,750
a Pekerja 0.0250 Org/Hari 60,000 1,500
b Tukang Kayu Halus 0.2500 Org/Hari 80,000 20,000
c Kepala Tukang 0.0250 Org/Hari 80,000 2,000
d Mandor 0.0001 Org/Hari 95,000 12
JUMLAH 454,250

1 Bh Pengadaan dan Pemasangan Kaca Cermin, tebal 5 mm (SNI 2002) No.17


1 Kaca Cermin 5 mm 1.1000 m2 - -
a Pekerja 0.0250 Org/Hari 60,000 1,500
b Tukang Kayu Halus 0.2500 Org/Hari 80,000 20,000
c Kepala Tukang 0.0250 Org/Hari 80,000 2,000
d Mandor 0.0001 Org/Hari 95,000 12
JUMLAH 23,500

1 Bh Pengadaan dan Pemasangan Kaca Cermin, tebal 6 mm (SNI 2002) No.18


1 KacaCermin 6 mm 1.1000 m2 266,500 293,150
a Pekerja 0.0150 Org/Hari 60,000 900
b Tukang Kayu Halus 0.1500 Org/Hari 80,000 12,000
c Kepala Tukang 0.0150 Org/Hari 80,000 1,200
d Mandor 0.0008 Org/Hari 95,000 71
JUMLAH 307,250
NO HARGA MATERIAL SATUAN HARGA SATUAN UPDATED

I. BATA, BATU DAN PASIR --------------------


1 Bata Merah biasa bh 600 Int – 22 may 2013
2 Bata Tela bh 1,350 sorong jan-juni 2013
3 Bata Merah Press bh 750 Int – 22 may 2013
4 Bata Merah Bojonghaur bh 900 Int – 22 may 2013
5 Batako Kecil bh 600 Int – 22 may 2013
6 Batako Lubang bh 4,000 Int – 22 may 2013
7 Conblock
8 Bata Conblock Standar (lubang 2) bh 2,400 Int – 22 may 2013
9 Bata Conblock Standar (lubang 3) bh 2,800 Boy – 22 may 2013
10 Bata Conblock Super (lubang 2) bh 3,000 Boy – 22 may 2013
11 Bata Conblock Super (lubang 3) bh 3,500 Boy – 22 may 2013
12 Bata Conblock Decoratif bh 6,000 Boy – 22 may 2013
Roster
13 Roster Beton 20x20 bh 7,000 Boy – 22 may 2013
14 Roster Beton 30x15 bh 10,000 Boy – 22 may 2013
15 Roster Beton 40x20 (wind flow) bh 14,000 Boy – 22 may 2013
16 Roster Beton 25x15 bh 8,000 Boy – 22 may 2013
17 Roster Beton 38x38 bh 25,000 Boy – 22 may 2013
18 Roster Beton Kotak Kosong 24x12 bh 7,000 Boy – 22 may 2013
19 Roster Beton Kotak Kosong 30x15 bh 10,000 Boy – 22 may 2013
20 Roster Beton Kotak Kosong 40x15 bh 14,000 Boy – 22 may 2013
21 Roster Beton Kotak Kosong 45x15 bh 17,500 Boy – 22 may 2013
22 Roster Beton Motih Madina 25x25 bh 12,500 Boy – 22 may 2013
23 Bata Roster 20x20 bh 6,500 Int – 22 may 2013
24 Bata Roster 10x20 bh 3,000 Int – 22 may 2013
25 Batu Belah Pondasi m3 228,571 Boy – 28 may 2013
26 Batu granit tumbuk Kg 12,000
27 Batu teraso tumbuk Kg 7,000
28 Batu Split Pecah Mesin 1/2 m3 145,000 Int – 22 may 2013
29 Batu Split Pecah Mesin 2/3 m3 145,000 Int – 22 may 2013
30 Batu Split Pecah Mesin 3/5 m3 145,000 Int – 22 may 2013
31 Batu Split Pecah Mesin 5/7 m3 145,000 Int – 22 may 2013
32 Abu batu 5mm m3 125,000 Int – 22 may 2013
33 Sirtu m3 125,000 Int – 22 may 2013
34 Pasir Beton m3 145,000 Int – 22 may 2013
35 Pasir Pasang m3 135,000 Int – 22 may 2013
36 Pasir Urug m3 100,000 Int – 22 may 2013
37 Pasir putih m3 195,000 Int – 22 may 2013
38 Tanah Urug m3 92,400
39 Pasir Plester m3 135,000 sorong jan-juni 2013
40 Air liter 34 Boy – 22 may 2013
41 Batu apung Kg 6,000
42 Bata berongga bh 1,500 sorong jan-juni 2013
43 Glass Block bh 3,000 sorong jan-juni 2013
44 HollowB lock (HB.20) bh 1,500 sorong jan-juni 2013
45 Batu kali bh 227,500
46 Batu koral sikat terpasang m2 325,000
47 Agregat kasar m3 254,800
48 Agregat halus m3 201,500

II BAHAN PEREKAT ----------------------------


45 Semen PC (50 Kg) zak 63,500 Int – 22 may 2013
46 Semen PC (40 Kg) zak 53,000 Int – 22 may 2013
47 Semen Putih kg 2,000 Int – 22 may 2013
48 Semen Warna kg 12,500 Int – 22 may 2013
49 Beton K-250 Readymix Slum 12 cm m3 2,168,516 sorong jan-juni 2013
50 Beton K-300 Readymix Slum 12 cm m3 2,710,645 sorong jan-juni 2013
AM 50 + Micro 1kg White kg 12,350
51 Beton m3 2,600,000

III TIANG PANCANG ---------------------------


52 Triangle 28 m 234,910 Boy – 22 may 2013
53 Triangle 32 m 302,510 Boy – 22 may 2013
54 Square 20 m 260,260 Boy – 22 may 2013
55 Square 25 m 385,320 Boy – 22 may 2013
56 Bulat dia. 30 m Boy – 22 may 2013
57 SPUN Pile Bulat dia. 30 m 370,000 Boy – 22 may 2013
56 Pemasangan m 253,500 Boy – 22 may 2013
57 Pemotongan bh 126,750 Boy – 22 may 2013
58 Penyambungan bh 253,500 Boy – 22 may 2013
59 Sewa Pompa unt 3,250,000 Boy – 22 may 2013
IV PIPA BETON---------------------------------
60 U - Ditch 300/400 p.1,20 m Bh
61 U - Ditch 400/600 p.1,20 m Bh
62 U - Ditch 300/500 p.1,20 m Bh 70,000 Boy – 22 may 2013
63 U - Ditch 400/500 p.1,20 m Bh 90,000 Boy – 22 may 2013
64 Box culvert BC 400x400 LD p. 1,00 m Bh
65 Greffel U20 p. 1,00 m Bh 24,000 Boy – 22 may 2013
66 Greffel U30 p. 1,00 m Bh 30,000 Boy – 22 may 2013
67 Greffel U40 p. 1,00 m Bh 40,000 Boy – 22 may 2013
68 Greffel U50 p. 1,00 m Bh 65,000 Boy – 22 may 2013
69 Buis Beton 200x1000 Bh 45,000 Boy – 22 may 2013
70 Buis Beton 300x1000 Bh 55,000 Boy – 22 may 2013
71 Buis Beton 400x1000 Bh 75,000 Boy – 22 may 2013
72 Buis Beton 500x1000 Bh 100,000 Boy – 22 may 2013
73 Buis Beton 600x500 Bh 80,000 Boy – 22 may 2013
74 Buis Beton 600x1000 Bh 140,000 Boy – 22 may 2013
75 Buis Beton 700x500 Bh 130,000 Boy – 22 may 2013
76 Buis Beton 800x500 Bh 150,000 Boy – 22 may 2013
77 Buis Beton 1000x500 Bh 210,000 Boy – 22 may 2013
78 Tutup Buis D700 Bh 70,000 Boy – 22 may 2013
79 Tutup Buis D1000 Bh 100,000 Boy – 22 may 2013
80 Tutup Buis D1200 Bh 120,000 Boy – 22 may 2013
81 Buis Beton Bh 71,500
82 Pipa PVC bh 65,000
83 Pipa Galvanis d=1/2 " m1 130,000
84 Pipa Galvanis d=3/4 " m1 260,000
85 Pipa Galvanis d=1 1/2 " m1 390,000
86 Pipa Galvanis d= 1 " m1 325,000
87 Pipa Galvanis d=3 " m1 455,000
88 Pipa Galvanis d=4 " m1 455,000
89 Pipa PVC d=1/2 " m1 455,000
90 Pipa PVC d=3/4 " m1 455,000
91 Pipa PVC d= 1 1/2 " m1 455,000
92 Pipa PVC d= 1 " m1 455,000
93 Pipa PVC d= 2 " m1 455,000
94 Pipa PVC d= 2 1/2 " m1 455,000
95 Pipa PVC d= 3 " m1 455,000
96 Pipa PVC d= 4 " m1 455,000
97 Pipa PVC 3/4" Btg 30,000 sorong jan-juni 2013
98 Pipa PVC 2,5" Btg 125,000 sorong jan-juni 2013
99 Pipa PVC 3" Btg 135,000 sorong jan-juni 2013
100 Pipa PVC 4" Btg 230,000 sorong jan-juni 2013
101 ID. 1/2" - 4m' Btg 20,000 sorong jan-juni 2013
102 ID. 3/4" - 4m' Btg 30,000 sorong jan-juni 2013
103 ID. 1" - 4m' Btg 40,000 sorong jan-juni 2013
104 ID. 3" - 4m' Btg 120,000 sorong jan-juni 2013
105 ID. 4" - 4m' Btg 190,000 sorong jan-juni 2013
106 ID. 5" - 4m' Btg 215,000 sorong jan-juni 2013
107 ID. 6" - 4m' Btg 450,000 sorong jan-juni 2013
108 Talang PVC 4-6" - 4m' Btg 90,000 sorong jan-juni 2013
109 Talang PVC 4-8" - 4m' Btg 325,000 sorong jan-juni 2013
110 Pipa GIP Kelas Medium Btg 110,000 sorong jan-juni 2013
111 ID. 1/2" - 6m' Btg 125,000 sorong jan-juni 2013
112 ID. 1" - 6m' Btg 250,000 sorong jan-juni 2013
113 ID. 1,5" - 6m' Btg 350,000 sorong jan-juni 2013
114 ID. 2" - 6m' Btg 370,000 sorong jan-juni 2013
115 ID. 3" - 6m' Btg 600,000 sorong jan-juni 2013
116 ID. 4" - 6m' Btg 800,000 sorong jan-juni 2013
117 ID. 5" - 6m' Btg 1,200,000 sorong jan-juni 2013
118 ID. 6" - 6m' Btg 1,524,900 sorong jan-juni 2013
119 Pipa Besi Listrik Ø 3/8" Btg 200,000 sorong jan-juni 2013
120 Pipa Besi Listrik Ø 5/8" Btg 400,000 sorong jan-juni 2013
121 Pipa Stainless Steel Ø 1" Btg 240,000 sorong jan-juni 2013
122 Pipa Stainless Steel Ø 4" Btg 585,000 sorong jan-juni 2013
123 Pipa Stainless Steel Ø 1,5 " Btg 320,000 Int – 11 June 2013
124 Pipa Stainless Steel Ø 2" Btg 400,000 sorong jan-juni 2013
125 Pipa Stainless Steel Ø 3" Btg 480,000 sorong jan-juni 2013
126 Reservoir Fiberglass Cap. 1 m3 bh 1,800,000 sorong jan-juni 2013
127 Pompa Dragon bh 500,000 sorong jan-juni 2013
128 Pompa Sanyo Kecil bh 475,000 sorong jan-juni 2013
129 Pompa Sanyo Besar bh 1,275,000 sorong jan-juni 2013
130 Pompa Air Honda bh 3,500,000 sorong jan-juni 2013
V BAHAN BAJA :
131 Besi Beton rata-rata Kg 1,721 Boy – 22 may 2013
Besi beton Ø6 biasa Kg 6,767 Boy – 22 may 2013
Besi beton Ø6 Kg 10,526 Boy – 22 may 2013
Besi beton Ø8 biasa Kg 11,875 Boy – 22 may 2013
Besi beton Ø8 Kg 14,531 Boy – 22 may 2013
Besi beton Ø10 biasa Kg 7,568 Boy – 22 may 2013
Besi beton Ø10 Kg 9,324 Boy – 22 may 2013
Besi beton Ø12 biasa Kg 7,505 Boy – 22 may 2013
Besi beton Ø12 Kg 8,912 Boy – 22 may 2013
Besi beton Ø13 Kg 8,974 Boy – 22 may 2013
Besi beton Ø16 biasa Kg 8,228 Boy – 22 may 2013
Besi beton Ø16 Kg 9,124 link E92
132 Besi Full 8 mm Kg 14,531 Boy – 22 may 2013
133 Besi Full 10 mm Kg 9,324 Boy – 22 may 2013
134 Besi Full 12 mm Kg 8,912 Boy – 22 may 2013
135 Besi Polos 16 mm Kg 9,124 Boy – 22 may 2013
136 Besi Ulir 15 mm Kg 10,000 sorong jan-juni 2013
137 Besi Ulir 16 mm Kg 9,124 Boy – 22 may 2013
138 Besi beton Ø6 biasa kg 6,767 Boy – 22 may 2013
139 Besi beton Ø6 kg 10,526 Boy – 22 may 2013
140 Besi beton Ø13 kg 8,974 Boy – 22 may 2013
1 Cakar Ayam Besi Beton Kg 8,974 link E92
141 Wiremesh M6 rata-rata m2 74,750
142 Wiremesh M8 rata-rata m2 68,318
143 Wiremesh M10 rata-rata m2 73,800
144 Wiremesh M4 U50 SNI m2 13,139 Boy – 22 may 2013
145 Wiremesh M5 U50 SNI m2 19,577 Boy – 22 may 2013
146 Wiremesh M6 U50 SNI m2 27,513 Boy – 22 may 2013
147 Wiremesh M7 U50 SNI m2 37,478 Boy – 22 may 2013
148 Wiremesh M8 U50 SNI m2 48,942 Boy – 22 may 2013
149 Wiremesh M9 U50 SNI m2 63,492 Boy – 22 may 2013
150 Wiremesh M10 U50 SNI m2 78,307 Boy – 22 may 2013
151 Wiremesh M12 U50 SNI m2 114,021 Boy – 22 may 2013
152 Wiremesh M4 standar m2 11,905 Boy – 22 may 2013
153 Wiremesh M5 standar m2 15,520 Boy – 22 may 2013
Wiremesh M6 standar m2 24,868 Boy – 22 may 2013
154 Wiremesh M7 standar m2 32,275 Boy – 22 may 2013
155 Wiremesh M12 standar m2 45,326 Boy – 22 may 2013
156 Besi Siku Rata-rata Kg 13,840 Boy – 22 may 2013
157 Besi IWF Rata-rata Kg 14,690 Boy – 22 may 2013
158 Besi UNP Rata-rata Kg 14,690 Boy – 22 may 2013
159 Besi C Rata-rata Kg 14,690 Boy – 22 may 2013
160 Besi Plat rata2 1 s/d 5 mm Kg 19,717 Boy – 22 may 2013
161 Besi Plat rata2 6 s/d 10 mm Kg 19,717 Boy – 22 may 2013
162 Besi Plat rata2 11 s/d 16 mm Kg 19,717 Boy – 22 may 2013
163 Plat Strip Kg 14,690 Boy – 22 may 2013
164 Plat Bordes t=3 mm Kg
165 Besi Profil Kg 20,000
166 Besi Square Tube Kg 20,001
167 Besi List Kaca Kg 20,002
168 Pengelasan cm 40
169 Besi siku 50x50x5 btg 160,000

VI BAHAN KAYU
169 Kayu Kuat klas IV -
170 Kaso kelas IV m3
171 Balok kelas IV m3
172 Papan kelas IV m3
173 Kayu Kuat klas III m3 2,335,667
174 Kaso kelas III m3 2,387,000
175 Balok kelas III m3 2,387,000
176 Papan kelas III m3 2,233,000
177 Kayu Kuat klas II m3 9,500,000
178 Kaso kelas II m3 9,500,000
179 Balok kelas II m3 9,500,000
180 Papan kelas II m3 9,500,000
181 Kayu Kuat klas I m3 16,000,000
182 Kaso kelas I m3 16,000,000
183 Balok kelas I m3 16,000,000
184 Balok kelas I m3 16,000,000
185 Papan kelas I m3 16,000,000
186 Dolken dia 5 s/d 7 cm p. 4 m btg 13,144
187 Dolken dia 8 s/d 10 cm p. 4 m btg 15,000
188 Bambu dia 5 s/d 7 cm p. 4 m btg 6,500
189 Bilik bambu m2 6,500
190 Kayu Reng 3/4 Kamper Samarinda m3 9,500,000
191 List Kayu 2/4 m3 7,500,000
192 Kayu cetakan m3 2,340,000
193 Kayu Bakar/Kayu Putih m3 1,500,000 sorong jan-juni 2013
VII BAHAN ALMUNIUM & PINTU2, JENDELA & BLIND
194 Kusen Alm. 4" CA m' 175,000 Int – 22 may 2013
195 Kusen Alm. 3" CA m' 145,000 Int – 22 may 2013
196 Kusen Alm. 4" PC m' 283,000 Int – 22 may 2013
197 Kusen Alm. 3" PC m' 220,000 Int – 22 may 2013
198 Kusen Alm. 12 x 6 x 3 m' 27,000 sorong jan-juni 2013
199 Bingkai Pintu Alumunium bh 375,000 sorong jan-juni 2013
200 Rangka Pintu Alm. CA ex Indal m'
201 Rangka Jendela Alm. CA ex Indal m'
202 Almunium frame ex Indal m' 65,000 Int – 19 Juni 2013
203 Almunium Hollow 300x500 mm ex Indal m'
204 Alumunium Strip m' 45,500
205 Pintu PVC uk. Standart unt 1,235,000 Int – 19 Juni 2013
206 Rolling door Plat Besi m2 1,300,000
207 Rolling door Zinkalume/Alumunium m2 1,300,000
208 Folding Door PVC m2 592,800
209 Sunscreen Alumunium m2 592,800
210 Horisontal Blind Metal Strip m2 110,500
211 Horisontal Wooden Blind m2 240,500
212 Vertical Blind m2 123,500
213 Venetian Blind m2 182,000
214 Kawat Nyamuk m2 3,250
Kawat Galvanis m' 130,000
215 Kusen Alm. 3" (CA silver) m' 50,000 Int – 22 may 2013
216 Kusen Alm. 3" (CA brown) m' 55,000 Int – 22 may 2013
217 Kusen Alm. 3" (PC) m' 75,000 Int – 22 may 2013
218 Kusen Alm. 4" (CA silver) m' 60,000 Int – 22 may 2013
219 Kusen Alm. 4” (CA brown) m' 65,000 Int – 22 may 2013
220 Kusen Alm. 4" (PC) m' 80,000 Int – 22 may 2013
Alexindo
221 Kusen Alm. 3" (CA silver) m' 50,000 Int – 22 may 2013
222 Kusen Alm. 3" (CA brown/black) m' 65,000 Int – 22 may 2013
222 Kusen Alm. 3" (PC) m' 85,000 Int – 22 may 2013
223 Kusen Alm. 4" (CA silver) m' 65,000 Int – 22 may 2013
223 Kusen Alm. 4” (CA brownblack) m' 75,000 Int – 22 may 2013
224 Kusen Alm. 4" (PC) m' 95,000 Int – 22 may 2013
Superex
225 Kusen Alm. 3" (CA silver) m' 70,000 Int – 22 may 2013
226 Kusen Alm. 3" (CA brown/black) m' 80,000 Int – 22 may 2013
226 Kusen Alm. 3" (PC) m' 100,000 Int – 22 may 2013
227 Kusen Alm. 4" (CA silver) m' 80,000 Int – 22 may 2013
227 Kusen Alm. 4” (CA brownblack) m' 90,000 Int – 22 may 2013
228 Kusen Alm. 4" (PC) m' 105,000 Int – 22 may 2013
YKK
229 Kusen Alm. 3" (CA silver) m' 90,000 Int – 22 may 2013
230 Kusen Alm. 3" (CA brown/black) m' 110,000 Int – 22 may 2013
230 Kusen Alm. 3" (PC) m' 135,000 Int – 22 may 2013
231 Kusen Alm. 4" (CA silver) m' 110,000 Int – 22 may 2013
231 Kusen Alm. 4” (CA brownblack) m' 150,000 Int – 22 may 2013
232 Kusen Alm. 4" (PC) m' 185,000 Int – 22 may 2013
232 Jendela Casement 3” (60x120cm) unit 450,000 Int – 22 may 2013
233 Rangka Jendela Alm. CA ex Indal m'
233 Almunium frame ex Indal m'
234 Almunium Hollow 300x500 mm ex Indal m'
234 Alumunium Strip m' 35,000
235 Pintu PVC uk. Standart unt
235 Rolling door Plat Besi t=0,4mm m2 227,500 Int – 22 may 2013
236 Rolling door Zinkalume/Alumunium t=0,8mm m2 357,500 Int – 22 may 2013
236 Rolling door Zinkalume/Alumunium t=1mm m2 422,500 Int – 22 may 2013
237 Folding Door PVC m2 592,800 Int – 22 may 2013
237 Folding Door Gate t=0,5mm m2 520,000 Int – 22 may 2013
238 Folding Door Gate t=0,8mm m2 715,000 Int – 22 may 2013
238 Folding Door Gate t=1mm m2 1,560,000 Int – 22 may 2013
239 Folding Door Gate t=1,2mm m2 1,820,000 Int – 22 may 2013
239 Sunscreen Alumunium m2 592,800
240 Horisontal Blind Metal Strip m2 126,100 Int – 22 may 2013
240 Horisontal Blind Metal Strip (Perforated) m2 150,800 Int – 22 may 2013
241 Horisontal Wooden Blind 27 m2 354,835 Int – 22 may 2013
241 Horisontal Wooden Blind 35 m2 413,400 Int – 22 may 2013
242 Horisontal Wooden Blind 50 m2 440,960 Int – 22 may 2013
242 Horisontal Bamboo Blind 25 m2 413,400 Int – 22 may 2013
243 Horisontal Bamboo Blind 50 m2 586,300 Int – 22 may 2013
243 Horisontal Blind Metal Strip Gold Series m2 181,350 Int – 22 may 2013
244 Horisontal Blind Metal Strip (Perforated) Gold Series m2 224,250 Int – 22 may 2013
244 Horisontal Wooden Blind Gold Series m2 248,950 Int – 22 may 2013
245 Roller Blind (standar) m2 204,100 Int – 22 may 2013
245 Roller Blind (semi black out) m2 217,100 Int – 22 may 2013
246 Roller Blind (black out) m2 283,400 Int – 22 may 2013
246 Vertical Blind (standar) m2 152,100 Int – 22 may 2013
247 Vertical Blind (semi black out) m2 165,100 Int – 22 may 2013
247 Vertical Blind (black out) m2 205,400 Int – 22 may 2013
248 Venetian Blind (Deluxe) m2 143,000 Int – 22 may 2013
248 Venetian Blind (Perforated) m2 166,400 Int – 22 may 2013
249 Venetian Blind (Wood Motif) m2 172,250 Int – 22 may 2013
249 Kawat Nyamuk m2 221,000 Int – 22 may 2013
250 Kawat Nyamuk + magnet m2 377,000 Int – 22 may 2013
Profil 1,5 x 3 Frame m2 54,167 Huge

VIII IRONMONGERIES
251 Engsel 3" bh 22,500
252 Engsel 4" bh 38,500
253 Lockcase Kunci ex SES bh
254 Cylinder Doble Slag ex SES bh
255 Engsel Pintu Pas 35,000 sorong jan-juni 2013
256 Engsel Lokal Pas 16,000 sorong jan-juni 2013
257 Engsel H Jendela Pas 15,000 sorong jan-juni 2013
258 Engsel H Pintu Pas 15,000 sorong jan-juni 2013
259 Engsel Kupu2 Ring Nylon Pintu Pas 20,000 sorong jan-juni 2013
260 Engsel Kupu2 Ring Nylon Jendela Pas 15,000 sorong jan-juni 2013
261 Door Closer bh 13,000
262 Door Stop bh 19,500
263 Handle Pintu ex Solid bh 520,000
270 Slot Tanam bh 45,500 Int – 07 Jun 2013
271 Hak Angin Biasa Pas 6,160 sorong jan-juni 2013
272 Hak Angin Lipat Pas 25,000 sorong jan-juni 2013
273 Kait Angin bh 30,000 sorong jan-juni 2013
274 Handel + Kunci bulat bh 125,000 ex setara Alfa
275 Pull Handle Pintu set
276 Slot Besi bh 10,780 Int – 22 may 2006
277 Tarikan jendela bh 7,700 Int – 22 may 2007
278 Engsel sendok lurus bh 18,000 Int – 22 may 2008
279 Engsel sendok lurus 1.5 HUK bh 50,000 Int – 22 may 2009
280 Gembok kecil bh 19,000 Int – 22 may 2010
281 Rel laci D soen bh 24,000 Int – 22 may 2011
282 Magnet lemari bh 2,000 Int – 22 may 2012
283 Kunci bh 160,000 Int – 22 may 2013
278 Kunci Silinder bh 13,000
279 Spring Knip bh 15,600
280 Rel Pintu Dorong set 513,500 Int-19 Juni 2013
281 Kunci Gembok Globe bh 40,000 sorong jan-juni 2013
282 Kunci Gembok Royal bh 50,000 sorong jan-juni 2013
283 Kunci Tanam 1 Slag bh 90,000 sorong jan-juni 2013
284 Kunci Terbang 2 Slag bh 175,000 sorong jan-juni 2013
285 Kunci Yale 2 Slag bh 140,000 sorong jan-juni 2013
286 Kunci Royal Besar bh 175,000 sorong jan-juni 2013
287 Kunci Royal Kecil bh 90,000 sorong jan-juni 2013
288 Grendel Jendela (Kilip) bh 10,000 sorong jan-juni 2013
289 Grendel Lokal bh 10,000 sorong jan-juni 2013
290 Grendel Kecil bh 10,000 sorong jan-juni 2013
291 Grendel Sedang bh 25,000 sorong jan-juni 2013
292 Grendel Besar bh 45,000 sorong jan-juni 2013
293 Gembok kecil bh

IX BAHAN PELAPIS :
294 Triplex t. 3 mm lbr 43,000 Int – 22 may 2013
295 Triplex t. 4 mm lbr 54,000 Int – 22 may 2013
296 Triplex t. 6 mm lbr 69,000 Int – 22 may 2013
297 Triplex t. 9 mm lbr 98,000 Int – 22 may 2013
298 Triplex t. 12 mm lbr 143,000 Int – 22 may 2013
299 Multiplex t. 16 mm lbr 175,000 Int – 22 may 2013
300 Multiplex t. 18 mm lbr 195,000 Int – 22 may 2013
301 Blockboard lbr 198,000 Int – 22 may 2013
302 Teakwood t. 3 mm lbr 78,000 Int – 22 may 2013
303 Teakwood t. 6 mm lbr 60,000 Int – 18 okt 2013
304 Multiplex t. 4 mm lbr 75,000 sorong jan-juni 2013
305 Multiplex t. 9 mm lbr 100,000 sorong jan-juni 2013
306 Multiplex t. 12 mm lbr 200,000 sorong jan-juni 2013
307 Multiplex t. 18 mm lbr 312,000 Int – 22 may 2013
308 Teakblock t.18 mm lbr 240,000 Int – 22 may 2013
308 HPL lbr 145,000 Int – 22 may 2013
309 HPL motif serat 185,000 Int – 22 may 2013
310 Melaminto Doff lbr 95,000 Int – 22 may 2013
311 Melaminto Gloss lbr 85,000 Int – 22 may 2013
312 Plywood lbr 120,000 sorong jan-juni 2013

X BAHAN LANTAI & DINDING


A LANTAI
313 Keramik Lantai 20/20 cm Polished m2 87,000 Int – 22 may 2013
314 Keramik Lantai 20/20 cm Unpolished m2 90,000 Int – 22 may 2013
315 Keramik Lantai 30/30 cm Polished m2 87,000 Int – 22 may 2013
316 Keramik Lantai 30/30 cm Unpolished m2 90,000 Int – 22 may 2013
317 Keramik Lantai 33/33 cm Polished m2 87,000 Int – 22 may 2013
318 Keramik Lantai 33/33 cm Unpolished m2 137,000 Int – 22 may 2013
319 Keramik Lantai 40/40 cm Polished m2 105,000 Int – 22 may 2013
320 Keramik Lantai 40/40 cm Unpolished m2 112,000 Int – 22 may 2013
321 Keramik Lantai 50/50 cm Polished m2 123,500 Int – 22 may 2013
322 Keramik Lantai 50/50 cm Unpolished m2 150,500 Int – 22 may 2013
323 Keramik Lantai 60/60 cm Polished m2 155,000 Int – 22 may 2013
324 Keramik Lantai 60/60 cm Unpolished m2 200,000 Int – 22 may 2013
Keramik 30/30 IMP Rocky Black m2 48,000
325 Grassblok t. 8 cm (40x40 cm ) Natural bh
326 Marmer Putih 30/30 bh 165,000 sorong jan-juni 2013
327 Marmer Putih 40/60 bh 200,000 sorong jan-juni 2013
328 Marmer Hitam 40/60 bh 300,000 sorong jan-juni 2013
329 Marmer Hitam 40/90 bh 900,000 sorong jan-juni 2013
330 Stepnosing Keramik 10/30 bh 16,000 sorong jan-juni 2013
331 Ubin Porselin 20/20 m2 65,000 sorong jan-juni 2013
332 Ubin Porselin 30/30 m2 85,000 sorong jan-juni 2013
333 Ubin Porselin 40/40 m2 90,000 sorong jan-juni 2013
334 Plint Warna bh 20,000 sorong jan-juni 2013
335 Plint PC 10/20 bh 37,000 sorong jan-juni 2013
ROMAN
336 Roman 20 x 20 Golongan A m2 87,000 Int – 22 may 2013
337 Roman 20 x 20 Golongan B m2 90,000 Int – 22 may 2013
338 Roman 20 x 20 Golongan D m2 100,000 Int – 22 may 2013
339 Roman 30 x 30 Golongan B m2 87,000 Int – 22 may 2013
340 Roman 30 x 30 Golongan C m2 91,000 Int – 22 may 2013
341 Roman 33.3 x 33.3 Golongan A m2 97,000 Int – 22 may 2013
342 Roman 33.3 x 33.3 Golongan C m2 137,500 Int – 22 may 2013
343 Roman 40 x 40 Golongan A m2 97,000 Int – 22 may 2013
344 Roman 40 x 40 Golongan B m2 105,000 Int – 22 may 2013
345 Roman 40 x 40 Golongan C m2 107,000 Int – 22 may 2013
346 Roman 40 x 40 Golongan D m2 112,000 Int – 22 may 2013
347 Roman 45 x 45 Golongan A m2 107,000 Int – 22 may 2013
348 Roman 45 x 45 Golongan B m2 113,000 Int – 22 may 2013
349 Roman 45 x 45 Golongan E m2 150,000 Int – 22 may 2013
350 Roman 50 x 50 Golongan A m2 123,500 Int – 22 may 2013
351 Roman 50 x 50 Golongan B m2 132,500 Int – 22 may 2013
352 Roman 50 x 50 Golongan C m2 150,500 Int – 22 may 2013
353 Roman 60 x 60 Golongan A m2 155,000 Int – 22 may 2013
354 Roman 60 x 60 Golongan B m2 175,000 Int – 22 may 2013
355 Roman 60 x 60 Golongan C m2 200,000 Int – 22 may 2013
356 Roman 16.5 x 66.6 Golongan A m2 192,000 Int – 22 may 2013
357 Roman 33.3 x 66.6 Golongan A m2 172,500 Int – 22 may 2013
358 Roman 33.3 x 66.6 Golongan B m2 193,000 Int – 22 may 2013
359 Roman 33.3 x 66.6 Golongan C m2 212,500 Int – 22 may 2013
360 Roman 8 x 30 Hospital Skirting m2 474,000 Int – 22 may 2013
361 Roman 10 x 20 Step Nosing m2 515,000 Int – 22 may 2013
362 Roman 10 x 30 Step Nosing Golongan A m2 521,400 Int – 22 may 2013
363 Ubin PC abu2 Bh 4,800
364 Ubin PC warna Bh 5,120
365 Ubin warna Bh 5,760
366 Ubin teraso Bh 4,000
367 Ubin granit Bh 4,480
368 Internal Cove (Plint) m1 27,500
369 Lantai Marmer m2 190,000
370 Karpet Lantai Roll m2 76,000
371 Karpet Lantai Tile m2 97,000
372 Underlayer/rubber corrugated m2 12,000
373 Lantai Parquette Laminated m2 176,000
374 Lantai Vynil Tile m2 65,000
375 Lantai Vinyl Roll m2 35,000
376 Plint Lantai Kayu Jati m1 45,000
377 Plint Lantai Vinyl m1 15,000
378 Floor Hardener Kg 4,480
379 Lantai Tegel Polos m2 55,000 Boy – 22 may 2013
380 Lantai Tegel Warna m2 60,000 Boy – 22 may 2013
381 Paving, Grass & Kanstein Block
382 Paving Block (M) t.6cm Natural m2 45,000 Boy – 22 may 2013
383 Paving Block (M) t.6cm Warna m2 50,000 Boy – 22 may 2013
384 Paving Block KW 2 t.6cm Natural m2 70,000 Boy – 22 may 2013
385 Paving Block KW 2 t.6cm Warna m2 80,000 Boy – 22 may 2013
386 Paving Block KW 2 t.8cm Natural m2 80,000 Boy – 22 may 2013
387 Paving Block KW 2 t.8cm Warna m2 90,000 Boy – 22 may 2013
388 Paving Block KW 1 t.6cm Natural m2 87,000 Boy – 22 may 2013
389 Paving Block KW 1 t.6cm Warna m2 97,000 Boy – 22 may 2013
390 Paving Block KW 1 t.8cm Natural m2 102,000 Boy – 22 may 2013
391 Paving Block KW 1 t.8cm Warna m2 112,000 Boy – 22 may 2013
392 Grass Block (M) t.6cm m2 50,000 Boy – 22 may 2013
393 Grass Block (M) t.7cm m2 60,000 Boy – 22 may 2013
394 Grass Block (M) t.8cm m2 65,000 Boy – 22 may 2013
395 Grass Block KW 2 t.6cm m2 70,000 Boy – 22 may 2013
396 Grass Block KW 2 t.8cm m2 80,000 Boy – 22 may 2013
397 Kanstein Taman 40x15x5/6 Bh 7,000 Boy – 22 may 2013
398 Kanstein Taman 40x17x5/9 Bh 10,000 Boy – 22 may 2013
399 Kanstein Taman 40x17x5/10 Bh 12,000 Boy – 22 may 2013
400 Kanstein Type K3 40x18x5/15 Bh 15,000 Boy – 22 may 2013
401 Kanstein Type K4 40x25x8/13 Bh 18,000 Boy – 22 may 2013
402 Kanstein Type K28 60x28x12/16 Bh 27,000 Boy – 22 may 2013
403 Kanstein Type K28 1/2 60x20x12/16 Bh 17,000 Boy – 22 may 2013
404 Kanstein Type K30 1/2 60x30x22/25 Bh 32,000 Boy – 22 may 2013
405 Kanstein Type K40 1/2 60x40x12/16 Bh 37,000 Boy – 22 may 2013
406 Kanstein Type KS (spoon) 1/2 50x30x10x15 Bh 23,000 Boy – 22 may 2013
407 Marmer slab m2
408 Ubin PC abu2 Bh 4,800
409 Ubin PC warna Bh 5,120
410 Ubin warna Bh 5,760
411 Ubin teraso Bh 4,000
412 Ubin granit Bh 4,480
413 Internal Cove (Plint) m1 27,500
414 Lantai Marmer m2 190,000
415 Karpet Lantai Roll m2 76,000
416 Karpet Lantai Tile m2 97,000
417 Underlayer/rubber corrugated m2 12,000
418 Lantai Parquette m2 176,000
419 Lantai Vynil Tile m2 65,000
420 Lantai Vinyl Roll m2 35,000
421 Plint Lantai Vinyl m1 15,000
422 Floor Hardener Kg 4,480

B DINDING
423 Keramik Dinding 20/20 cm Polished m2 87,000 Int – 22 may 2013
424 Keramik Dinding 20/25 cm Polished m2 90,000 Int – 22 may 2013
425 Keramik Dinding 30/30 cm Polished m2 118,000 Int – 22 may 2013
426 Skirting Keramik 8/30 cm bh -
427 Dinding Porselen 11/11 cm m2 32,500
428 Dinding Porselen 10/20 cm m2 36,400
429 Dinding Porselen 20/20 cm m2 38,350
430 Keramik Dinding Artistik 10/20 cm Polished m2 260,000
431 Keramik Dinding Artistik 5/20 cm Polished m2 312,000
432 Dinding Marmer 100/100 cm m2 280,800
433 Dinding Marmer Travertine Cream m2 2,314,000
434 Bata pelapis (3x7x24cm) m2 117,000
435 Batu paras tempel m2 162,500
436 Batu tempel m2 45,500
437 Wallpaper standar roll 71,500
438 Wallpaper artistik roll 123,500
439 Wallpaper tebal roll 189,800
440 Ornamen Tempel Minimalis 400x200 (garis Besar) m2 71,500 Boy – 22 may 2013
441 Ornamen Tempel Minimalis 300x150 (garis Sedang) m2 71,500 Boy – 22 may 2013
442 Ornamen Tempel Minimalis 400x200 (garis Kecil) m2 71,500 Boy – 22 may 2013
443 Plint Warna bh 20,000 sorong jan-juni 2013
444 Plint PC 10/20 bh 37,000 sorong jan-juni 2013
445 ROMAN
446 Roman 20 x 20 Golongan A m2 84,000 Int – 22 may 2013
447 Roman 20 x 20 Golongan B m2 90,000 Int – 22 may 2013
448 Roman 20 x 25 Golongan A m2 84,000 Int – 22 may 2013
449 Roman 20 x 25 Golongan B m2 90,000 Int – 22 may 2013
450 Roman 20 x 25 Golongan C m2 93,500 Int – 22 may 2013
451 Roman 25 x 25 Golongan A m2 85,000 Int – 22 may 2013
452 Roman 25 x 25 Golongan B m2 91,500 Int – 22 may 2013
453 Roman 25 x 25 Golongan C m2 103,000 Int – 22 may 2013
454 Roman 30 x 30 Golongan B (match 20 x 60) m2 118,000 Int – 22 may 2013
455 Roman 30 x 30 Golongan C (match 20 x 60) m2 128,000 Int – 22 may 2013
456 Roman 30 x 30 Golongan D (match 20 x 60) m2 143,000 Int – 22 may 2013
457 Roman 30 x 30 Golongan A (match 30 x 60) m2 113,000 Int – 22 may 2013
458 Roman 30 x 30 Golongan B (match 30 x 60) m2 118,000 Int – 22 may 2013
459 Roman 30 x 30 Golongan C (match 30 x 60) m2 128,000 Int – 22 may 2013
460 Roman 30 x 30 Golongan D (match 30 x 60) m2 143,000 Int – 22 may 2013
461 Roman 25 x 33.3 Golongan A m2 84,000 Int – 22 may 2013
462 Roman 25 x 33.3 Golongan B m2 90,000 Int – 22 may 2013
463 Roman 25 x 33.3 Golongan C m2 93,500 Int – 22 may 2013
464 Roman 20 x 40 Golongan A m2 84,000 Int – 22 may 2013
465 Roman 20 x 40 Golongan B m2 90,000 Int – 22 may 2013
466 Roman 25 x 45 Golongan A m2 92,500 Int – 22 may 2013
467 Roman 25 x 45 Golongan B m2 103,500 Int – 22 may 2013
468 Roman 25 x 45 Golongan D m2 122,500 Int – 22 may 2013
469 Roman 32.5 x 32.5 Golongan A match 32.5 x 65.6 m2 126,000 Int – 22 may 2013
470 Roman 32.5 x 32.5 Golongan B match 32.5 x 65.6 m2 131,000 Int – 22 may 2013
471 Roman 32.5 x 32.5 Golongan A match 32.5 x 97.5 m2 126,000 Int – 22 may 2013
472 Roman 20 x 60 Golongan A m2 128,500 Int – 22 may 2013
473 Roman 20 x 60 Golongan B m2 140,000 Int – 22 may 2013
474 Roman 20 x 60 Golongan C m2 155,000 Int – 22 may 2013
475 Roman 20 x 60 Golongan D m2 175,000 Int – 22 may 2013
476 Roman 30 x 60 Golongan A m2 128,500 Int – 22 may 2013
477 Roman 30 x 60 Golongan B m2 140,000 Int – 22 may 2013
478 Roman 30 x 60 Golongan C m2 155,000 Int – 22 may 2013
479 Roman 30 x 60 Golongan D m2 175,000 Int – 22 may 2013
480 Roman 30 x 60 Golongan E m2 185,000 Int – 22 may 2013
481 Roman 32.5 x 65.6 Golongan A Rectified m2 191,500 Int – 22 may 2013
482 Roman 32.5 x 65.6 Golongan B Rectified m2 207,000 Int – 22 may 2013
483 Roman 32.5 x 65.6 Golongan C Rectified m2 226,000 Int – 22 may 2013
484 Roman 32.5 x 97.5 Golongan A Rectified m2 283,000 Int – 22 may 2013
485 Roman 32.5 x 97.5 Golongan B Rectified m2 323,000 Int – 22 may 2013
445 Skirting Keramik 8/30 cm bh -
446 Dinding Porselen 11/11 cm m2 25,000
447 Dinding Porselen 10/20 cm m2 28,000
448 Dinding Porselen 20/20 cm m2 29,500
449 Keramik Dinding Artistik 10/20 cm Polished m2 112,000
450 Keramik Dinding Artistik 5/20 cm Polished m2 123,500
451 Dinding Marmer 30/60 cm m2 190,000
452 Bata pelapis (3x7x24cm) m2 90,000
453 Batu paras tempel m2 125,000
454 Batu tempel m2 35,000
455 Wallpaper standar roll 55,000
456 Wallpaper artistik roll 95,000
457 Wallpaper tebal roll 146,000
458 Ornamen Tempel Minimalis 400x200 (garis Besar) m2 55,000 Boy – 22 may 2013
459 Ornamen Tempel Minimalis 300x150 (garis Sedang) m2 55,000 Boy – 22 may 2013
460 Ornamen Tempel Minimalis 400x200 (garis Kecil) m2 55,000 Boy – 22 may 2013

XI BAHAN PENUTUP ATAP


461 Steel Corregouted Zincalum t. 0,45 mm Colorcoat m2 152,100
462 Genteng Metal stone chip m2 169,000
463 Nok Metal stone chip bh 71,000
464 Nok Steel Sheet Zincalum t. 0,45 mm Colorcoat m' 109,850
465 Skrup 12 x 45 HWTG bh
466 Zincoated BJLS 30 m2
467 Seng Plat BJLS 0,30 m' 84,700
468 Seng Plat BJLS 0,20 m' 60,060
469 Seng Gelombang BJLS 0,3 lbr 100,100
470 Seng Gelombang BJLS 0,2 lbr 56,210
471 Nok Seng Gelombang Lbr 15,000
472 Metal deck m2 295,750
473 Seng Plat BJLS 0,30 m' 70,000 sorong jan-juni 2013
474 Seng Plat BJLS 0,20 m' 57,000 sorong jan-juni 2013
475 Seng Gelombang BJLS 0,3 lbr 59,000 sorong jan-juni 2013
476 Seng Gelombang BJLS 0,3 lbr 67,000 sorong jan-juni 2013
477 Seng Gelombang BJLS 0,2 lbr 36,000 sorong jan-juni 2013
478 Seng Gelombang BJLS 0,2 lbr 42,000 sorong jan-juni 2013
479 Seng Gelombang BJLS 0,2 lbr 50,000 sorong jan-juni 2013
480 Seng Talang BJLS 0,3 lbr 50,000 sorong jan-juni 2013
Seng Gajah Mas
481 Seng Datar BJLS 30 uk (0,.90 x 1.00) lbr 31,500 Int – 22 may 2013
482 Seng Gelombang BJLS (180 x 80) lbr 41,100 Int – 22 may 2013
482 Seng Gelombang BJLS (120 x 80) lbr 47,700 Int – 22 may 2013
483 Seng Gelombang BJLS (240x 80) lbr 54,300 Int – 22 may 2013
483 Seng Gelombang BJLS (300 x 80) lbr 67,500 Int – 22 may 2013
484 Seng Plat BJLS 30 L = 0,45 M M1 34,800 Int – 22 may 2013
484 Seng Plat BJLS 30 L = 0,60 M M1 39,600 Int – 22 may 2013
485 Seng Plat BJLS 30 L = 0,90 M M1 49,800 Int – 22 may 2013
485 Seng Plat BJLS 28 (90 x 180) cm lbr 83,100 Int – 22 may 2013
486 Bubung Seng Gelombang lbr 93,600 Int – 22 may 2013
T=3.5 mm
487 Asbes/Harflex gelombang uk. 3000X800x3.5 mm lbr 54,700 Int – 22 may 2013
488 Asbes/Harflex gelombang uk. 2700X800x3.5 mm lbr 49,250 Int – 22 may 2013
488 Asbes/Harflex gelombang uk. 2400X800x3.5 mm lbr 36,450 Int – 22 may 2013
489 Asbes/Harflex gelombang uk. 2000X800x3.5 mm lbr 32,350 Int – 22 may 2013
489 Asbes/Harflex gelombang uk. 1800X800x3.5 mm lbr 27,450 Int – 22 may 2013
490 Asbes/Harflex gelombang uk. 1500X800x3.5 mm lbr 23,050 Int – 22 may 2013
T=4 mm
491 Asbes/Harflex gelombang uk. 3000x1050x4 mm lbr 73,000 Int – 22 may 2013
492 Asbes/Harflex gelombang uk. 2700x1050x4 mm lbr 65,750 Int – 22 may 2013
492 Asbes/Harflex gelombang uk. 2400x1050x4 mm lbr 58,450 Int – 22 may 2013
493 Asbes/Harflex gelombang uk. 2000x1050x4 mm lbr 51,150 Int – 22 may 2013
493 Asbes/Harflex gelombang uk. 1800x1050x4 mm lbr 43,850 Int – 22 may 2013
494 Asbes/Harflex gelombang uk. 1500x1050x4 mm lbr 36,800 Int – 22 may 2013
T=5 mm
495 Asbes/Harflex gelombang uk. 3000x1080x5 mm lbr 98,550 Int – 22 may 2013
496 Asbes/Harflex gelombang uk. 2700x1080x5 mm lbr 88,700 Int – 22 may 2013
497 Asbes/Harflex gelombang uk. 2400x1080x5 mm lbr 78,850 Int – 22 may 2013
498 Asbes/Harflex gelombang uk. 2000x1080x5 mm lbr 69,000 Int – 22 may 2013
499 Asbes/Harflex gelombang uk. 1800x1080x5 mm lbr 59,150 Int – 22 may 2013
500 Asbes/Harflex gelombang uk. 1500x1080x5 mm lbr 49,300 Int – 22 may 2013
T=6 mm
501 Asbes/Harflex gelombang uk. 3000x1080x6 mm lbr 116,500 Int – 22 may 2013
502 Asbes/Harflex gelombang uk. 2700x1080x6 mm lbr 104,850 Int – 22 may 2013
503 Asbes/Harflex gelombang uk. 2400x1080x6 mm lbr 93,250 Int – 22 may 2013
504 Asbes/Harflex gelombang uk. 2000x1080x6 mm lbr 81,600 Int – 22 may 2013
505 Asbes/Harflex gelombang uk. 1800x1080x6 mm lbr 69,900 Int – 22 may 2013
506 Asbes/Harflex gelombang uk. 1500x1080x6 mm lbr 58,300 Int – 22 may 2013
Aksesoris
507 Bubungan stel gelombang 920 mm lbr 7,100
508 Nok stel gelombang 800 mm lbr 19,000 Int – 22 may 2013
508 Nok stel gelombang 1050 mm lbr 25,100 Int – 22 may 2013
509 Nok stel gelombang 1080 mm lbr 44,700 Int – 22 may 2013
509 Nok gel besar l.102 cm pcs 25,000
510 Nok gel kecil l.102 cm pcs 23,000
510 Rangka atap baja ringan m2 180,000 Int – 28 may 2013
511 Polycarbonate Celar t. 8 mm m2
511 Bubungan stel gelombang 920 mm lbr 9,230
512 Nok stel gelombang 0.92 mm lbr 8,450
512 Nok stel gelombang 1050 mm lbr 8,450
513 Nok stel gelombang 1080 mm lbr 8,710
513 Nok gel besar l.102 cm pcs 32,500
514 Nok gel kecil l.102 cm pcs 29,900
515 Rangka atap baja ringan m2 182,000
516 Polycarbonate Celar t. 8 mm m2 103,048
517 Genteng Palentong Kecil Bh 3,500
518 Genteng Kodok Bh 4,700
519 Genteng Palentong Super Bh 11,000
520 Bubungan Genteng Palentong Bh 4,300
521 Bubungan Genteng Kodok Bh 5,200
522 Bubungan Palentong Super Bh 13,400
523 Atap Fiberglass Lbr 170,000
Genteng Beton Motif Natural Bh 6,000 Boy – 22 may 2013
Genteng Beton Motif Warna Bh 6,500 Boy – 22 may 2013
Genteng Beton Gelombang Natural Bh 5,000 Boy – 22 may 2013
Genteng Beton Gelombang Warna Bh 5,500 Boy – 22 may 2013
Nok Genteng Beton Motif Natural Bh 7,000 Boy – 22 may 2013
Nok Genteng Beton Motif Warna Bh 7,500 Boy – 22 may 2013
Nok Genteng Beton Gelombang Natural Bh 6,000 Boy – 22 may 2013
Nok Genteng Beton Gelombang Warna Bh 6,500 Boy – 22 may 2013
524 Genteng Beton Bh 4,680 sorong jan-juni 2013
525 Nok Genteng Beton Bh 4,681 sorong jan-juni 2013
526 Genteng Aspal Bh 3,602
527 Nok Genteng aspal Bh 3,603
528 Plastic Aerator Bh 3,000
529 Genteng Metal Lbr 78,000
530 Nok Genteng Metal Lbr 65,000
531 Atap Sirap Bh 3,606
532 Nok Atap Sirap m1 3,607
533 besi m2 7,800 sorong jan-juni 2013
534 Atap Plastik Gelombang Besar lbr 55,000 sorong jan-juni 2013
535 Atap Ardek Gelombang Kecil lbr 55,000 sorong jan-juni 2013
536 Atap Ardek Gelombang Besar lbr 52,000 sorong jan-juni 2013
537 Atep Sakura Roof 2 Susun lbr 36,000 sorong jan-juni 2013
538 Atep Sakura Roof 3 Susun bh 50,000 sorong jan-juni 2013
539 Nok Atap Sakura Roof bh 27,500 sorong jan-juni 2013
540 Genteng Plentong Super bh 3,000 sorong jan-juni 2013
541 Nok Genteng Plentong bh 3,000 sorong jan-juni 2013
542 Nok Genteng Kodok bh 2,800 sorong jan-juni 2013
543 Nok Plentong Super bh 3,400 sorong jan-juni 2013
544 Roof Fiberglass 6K bh 35,000 sorong jan-juni 2013
545 Roof Fiberglass 7K lbr 40,000 sorong jan-juni 2013
546 Roof Fiberglass 8K lbr 50,000 sorong jan-juni 2013
547 Nok Atap Alumunium lbr 30,000 sorong jan-juni 2013
548 Alumunium Bondex lbr 140,000 sorong jan-juni 2013
549 Alumunium Sirip m2 175,000 sorong jan-juni 2013
550 Alumunium Foil m2 6,000 sorong jan-juni 2013
551 Listplank m1 78,000 Int-17 Jun 2013
552 Roof Botton R33 Btg 35,750
553 Self Drilling Screw

XII BAHAN PERLINDUNGAN


551 Waterproofing Coating m2 125,000
552 Adukan perekat FK101 kg
553 Adukan perekat FK111 kg
554 Pengisi Nat FS NAT kg
555 Hardener kg 10,140

XIII KAWAT / MESH


556 Kawat Beton Hitam kg 27,000
557 Kawat Galvanisir Kg 32,000
558 Ram Kawat Ayam m2 36,000
559 Kawat Bronjong Galvanisir kg 22,000 sorong jan-juni 2013
560 Kawat Duri m2 27,500
561 Kawat Harmoni m' 85,000 sorong jan-juni 2013
562 Kawat Nyamuk Plastik m' 10,000 sorong jan-juni 2013
563 Kawat Nyamuk Besi m' 28,000 sorong jan-juni 2013
564 Kawat Las 2,6 Kg 27,500
565 Pagar Kawat Jaring Galv. Glg 210,000 sorong jan-juni 2013

XIV BAHAN KACA :


566 Kaca Polos 3 mm m2 70,000 Int – 22 may 2013
567 Kaca Polos 5 mm m2 95,000 Int – 22 may 2013
568 Kaca Polos 6 mm m2 125,000 Int – 22 may 2013
569 Kaca Polos 8 mm m2 180,000 Int – 22 may 2013
570 Kaca Polos 10 mm m2 260,000 Int – 22 may 2013
571 Kaca Polos 12 mm m2 290,000 Int – 22 may 2013
572 Kaca Polos 15 mm m2 1,300,000 Int – 22 may 2013
573 Kaca Polos 19 mm m2 1,600,000 Int – 22 may 2013
574 Kaca Rayben 3 mm lbr 133,000 sorong jan-juni 2013
575 Kaca Rayben 5 mm lbr 210,000 sorong jan-juni 2013
576 Kaca Tempered 5 mm m2 200,000 Int – 22 may 2013
577 Kaca Tempered 6 mm m2 250,000 Int – 22 may 2013
578 Kaca Tempered 8 mm m2 375,000 Int – 22 may 2013
579 Kaca Tempered 10 mm m2 400,000 Int – 22 may 2013
580 Kaca Tempered 12 mm m2 450,000 Int – 22 may 2013
581 Kaca Tempered 15 mm m2 1,950,000 Int – 22 may 2013
582 Kaca Tempered 19 mm m2 2,450,000 Int – 22 may 2013
583 Kaca nako polos 5 mm daun 215,000
584 Kaca nako rayben 5 mm daun 192,500
585 Rangka nako daun 18,000
586 Besi nako m
587 Kaca nako t.6 mm + rangka m2 75,000
588 Kaca Cermin 5 mm m2 162,500 Int – 07 Juni 2013
589 KacaCermin 6 mm m2 266,500
590 Kaca Buram 12mm m2 390,000
591 Kaca nako dengan Trali 6 klip Set 195,000 sorong jan-juni 2013
592 Kaca nako dengan Trali 7 klip Set 220,000 sorong jan-juni 2013
593 Kaca nako dengan Trali 8 klip Set 240,000 sorong jan-juni 2013
594 Kaca nako dengan Trali 9 klip Set 270,000 sorong jan-juni 2013
595 Kaca nako dengan Trali 10 klip Set 290,000 sorong jan-juni 2013
596 Stang Lovers 5 klip Pas 75,000 sorong jan-juni 2013
597 Stang Lovers 6 klip Pas 115,000 sorong jan-juni 2013
598 Stang Lovers 7 klip Pas 105,000 sorong jan-juni 2013
599 Stang Lovers 8 klip Pas 120,000 sorong jan-juni 2013
600 Stang Lovers 9 klip Pas 135,000 sorong jan-juni 2013
601 Stang Lovers 10 klip Pas 150,000 sorong jan-juni 2013
602 Besi tralis nako bh 22,000 sorong jan-juni 2013
603 Kaca Lover Bening lbr 12,000 sorong jan-juni 2013
604 Kaca Lover Buram lbr 23,000 sorong jan-juni 2013
605 Kaca Lover Rayben lbr 15,000 sorong jan-juni 2013

XV BAHAN PAKU DAN MUR BAUT :


606 Paku 1 s/d 3 cm kg 20,020
607 Paku 4 s/d 7 cm kg 36,000
608 Paku 8 s/d 12 cm kg 36,000
609 Paku payung bh 500
610 Besi Begel Kuda-kuda kg
611 Duk angker kg
612 Angker Mur Bout 19 mm p. 90 cm bh
613 Mur Baut HTB dia 16 s/d 19 mm p. 5 cm bh
614 Mur Baut Biasa dia 16 s/d 19 mm p. 5 cm bh
615 Wartermur 12 mm bh
616 Klem Alm bh -
617 Skrup bh 334
618 Paku Skrup Kg 20,000
619 Paku Pancing Kg 18,700
620 Paku Biasa kg 15,000 sorong jan-juni 2013
621 Paku Seng kg 25,000 sorong jan-juni 2013
622 Paku Triplex kg 22,500 sorong jan-juni 2013
623 Paku Persegi kg 22,500 sorong jan-juni 2013
624 Paku Ardex kg 25,000 sorong jan-juni 2013
625 Paku Asbes kg 25,000 sorong jan-juni 2013
626 Paku Tembok 7-10 cm kg 25,000 sorong jan-juni 2013
627 Paku Jembatan kg 25,000 sorong jan-juni 2013
628 Mur Baut ID.3/8" - 7" s/d 14" bh 10,000 sorong jan-juni 2013
629 Skrup bh 500 sorong jan-juni 2013

XVI BAHAN FINISHING :


A. Besi:
630 Dempul Besi Kg 24,640 sorong jan-juni 2013
631 Cat Dasar / meni besi Kg 28,336 sorong jan-juni 2013
632 Cat Besi Kg 30,800 sorong jan-juni 2013
633 Thinner Ltr 27,720 sorong jan-juni 2013
634 Terpentin Ltr 7,500 sorong jan-juni 2013

B Kayu :
633 Dempul Kayu Kg 24,640
634 Cat Dasar / meni kayu Kg 28,336
635 Cat Kayu Kg 30,800
636 Plamir Kayu Kg 17,890
637 Teak Oil Ltr 15,000
638 Politur Ltr 7,000
639 Politur Dasar Ltr 5,000
640 Vernis Kayu Ltr 11,500
Edging ED 300L2/2 450,000
641 Cat Alumunium Kg 46,000 sorong jan-juni 2013
642 Cat Atap Ardex Kg 108,000 sorong jan-juni 2013
643 Meni Kayu Kg 28,000 sorong jan-juni 2013
644 Sirlak kg 175,000 sorong jan-juni 2013
645 Plamur Besi kg 78,000
646 Plamur Tembok kg 52,000
647 Plamur Kayu kg 7,800
648 Meni Besi Ltr 36,400
649 Meni Kayu kg 36,400
650 Thinner kg 36,400
651 Residu Ltr 78,000

C. Tembok
645 Cat dasar emulsion Ltr 46,550 Int – 25 may 2013
646 Cat akhir emulsion Ltr 62,500 Int – 25 may 2013
647 Cat akhir Wheathersield Ltr 100,000 Int – 25 may 2013
648 Cat Dasar Alkali Resistant Primer Kg 60,410 Int – 25 may 2013
649 Plamir Tembok Kg 30,940 Int – 25 may 2013
650 Soligneum Kg
651 Finish Melamik m2 110,500 Int – 19 Juni 2013
652 Cat Tembok (25 kg) kg 22,100 sorong jan-juni 2013
PRODUK NIPPON PAINT
652 MATEX PUTTY Ltr 6,190 Int – 25 may 2013
653 VINILEX 5180WALL SEALER Ltr 14,229 Int – 25 may 2013
653 NIPPON ALKALI PRIMER 3 IN 1 Kg 46,200 Int – 25 may 2013
CAT INTERIOR
654 Q-LUC Ltr 5,714 Int – 25 may 2013
655 MATEX Ltr 9,200 Int – 25 may 2013
655 VINILEX 5000 Ltr 12,371 Int – 25 may 2013
656 SUPER VINILEX 5000 Ltr 14,229 Int – 25 may 2013
CAT EXTERIOR
657 KIMEX WEATHERBOND Ltr 7,971 Int – 25 may 2013

658 NIPPONWEATHERBOND Ltr 53,500 Int – 25 may 2013


(warna Briliant White)
PRODUK DULUX
659 Dulux Weathershield Pro (std) Ltr 87,750 Int – 25 may 2013
660 Dulux Weathershield Pro (spc) Ltr 95,000 Int – 25 may 2013
660 Dulux Weathershield Max (std) Ltr 95,000 Int – 25 may 2013
661 Dulux Weathershield Max (spc) Ltr 103,750 Int – 25 may 2013
661 Dulux Weathershield Max (new) Ltr 131,500 Int – 25 may 2013
662 Dulux Pentalite (std) Ltr 54,900 Int – 25 may 2013
662 Dulux Pentalite (spc) Ltr 62,250 Int – 25 may 2013
663 Dulux Easy Clean (std) Ltr 37,000 Int – 25 may 2013
663 Dulux Easy Clean (spc) Ltr 53,350 Int – 25 may 2013
664 Dulux Pearl Glo Ltr 69,100 Int – 25 may 2013
664 Dulux Wallfiller Kg 21,250 Int – 25 may 2013
665 Dulux Alkali Killer Ltr 60,800 Int – 25 may 2013
665 Dulux Alkali Killer Ltr 53,250 Int – 25 may 2013
666 Dulux Alkali Resisting Primer Ltr 43,150 Int – 25 may 2013
666 Dulux Weathershield Putty Kg 21,250 Int – 25 may 2013
667 Dulux Weathershield Primer Ltr 49,600 Int – 25 may 2013
667 Dulux Weathershield Primer Ltr 46,550 Int – 25 may 2013
PRODUK MOWILEX
668 Mowilex Emulsion (standar) Ltr 49,200 Int – 25 may 2013
669 Mowilex Emulsion (khusus) Ltr 73,200 Int – 25 may 2013
669 Mowilex Emulsion (pastel) Ltr 51,600 Int – 25 may 2013
670 Mowilex Emulsion (VIP) Ltr 51,200 Int – 25 may 2013
670 Mowilex Weathercoat Ltr 75,200 Int – 25 may 2013

671 Mowilex Elastomeric Ltr 76,400 Int – 25 may 2013


Wall coating

D BAHAN PEMBANTU 6,000


672 Amplas Kayu / Besi Lbr 8,624
673 Kuas Cat rata2 Bh 11,211
674 Kuas Cat 2" Bh 7,000 sorong jan-juni 2013
675 Kuas Cat 3" Bh 12,000 sorong jan-juni 2013
676 Roll Cat Bh 20,713 sorong jan-juni 2013
677 Lem Kayu Kg 62,500
678 Lem Karpet Kg 27,500 sorong jan-juni 2013
679 Lem Vinyl Kg 15,000 sorong jan-juni 2013
680 Lem Wallpaper Kg 9,000
681 Sealant Kaca kg 45,000 sorong jan-juni 2013
XVII BAHAN SANITARI
Kloset duduk TOTO CST412MF unt 6,712,695 Int – 25 nov 2013
682 Kloset Duduk Porselen unt 2,000,000 sorong jan-juni 2013
683 Kloset Jongkok Porselen Putih unt 450,000 sorong jan-juni 2013
684 Kloset Jongkok Keramik unt 425,000 sorong jan-juni 2013
685 Kloset Duduk; Toilet bowl; komplit acc unt 2,140,000 Int – 25 may 2013
686 Kloset Duduk; Single Toilet bowl; komplit acc unt 2,500,000 Int – 25 may 2013
687 Kloset Duduk; Single Toilet bowl; 'Euro" komplit acc unt 2,140,000 Int – 25 may 2013
688 Kloset Duduk; Toilet bowl; komplit acc unt 3,295,500 Int – 25 may 2013
689 Kloset Duduk; Single Toilet bowl; komplit acc unt 5,695,300 Int – 25 may 2013
690 Kloset Duduk; Single Toilet bowl; 'Euro" komplit acc unt 3,295,500 Int – 25 may 2013
691 Kloset Duduk Toto CW 421 J unt 3,616,600 Int – 25 may 2013
692 Washlet unt 794,300 Int – 25 may 2013
693 Kloset Jongkok 440x550x280 unt 392,000 Int – 25 may 2013
694 Kloset Jongkok 400x500x200 unt 215,000 Int – 25 may 2013
695 Kloset Jongkok + instalasi Flush unt 2,840,000 Int – 25 may 2013
696 Kloset Jongkok unt 599,950 Int – 25 may 2013
697 Urinoir keramik komplit acc unt 2,120,000 Int – 25 may 2013
698 Urinoir Partisi Keramik unt 961,000 Int – 25 may 2013
699 Wastafel Dinding komplit acc; uk. 430x435 mm unt 189,280 Int – 25 may 2013
700 Wastafel Console komplit acc; uk. Dia. 430 mm unt 5,468,840 Int – 25 may 2013
701 Wastafel Topcounter Self Rumming; uk 445x365 mm unt 2,256,150 Int – 25 may 2013
702 Wastafel Topcounter Semi Recessed; uk 415x485 mm unt 4,765,410 Int – 25 may 2013
703 Wastafel Undercounter; uk 630x345 mm unt 3,699,410 Int – 25 may 2013
704 Washtafel Pedestal; uk. 500x350 mm unt 916,000
705 Washtafel Keramik (lengkap) unt 750,000 sorong jan-juni 2013
706 Bak air fibreglass uk. 55x55x60 cm bh 523,900 Int – 25 may 2013
707 Kran dinding acrilyc bulat bh 196,000 Int – 25 may 2013
708 Kran dinding 4 jari bh 188,000 Int – 25 may 2013
709 Kran dinding bh Int – 25 may 2013
710 Kran zink lever handle bh 314,000 Int – 25 may 2013
711 Kran Air 1/2" bh 17,500 sorong jan-juni 2013
712 Kran Air 3/4" bh 35,000 sorong jan-juni 2013
713 Kitchenzink stainless steel 1 lubang unt 450,000 sorong jan-juni 2013
714 Kitchenzink stainless steel 2 lubang unt 600,000 sorong jan-juni 2013
715 Kitchenzink teraso 1 lubang bh 130,000 Int – 25 may 2013
716 Floordrain unt 367,000 Int – 25 may 2013
717 Shower bh 245,000 sorong jan-juni 2013
718 Bath Tube fibreglass unt 6,100,000
719 Shower head bh 457,990
720 Mix Shower Set unt 1,499,030
721 Toilet Shower unt 326,000 Int – 25 may 2013
722 Toilet Shower unt 267,000 Int – 25 may 2013
723 Tempat Tissue Inbow unt 209,000 Int – 25 may 2013

724 Tempat Tissue SST outbow TX720ACRB 314,000


unt
725 Tempat Sabun dinding (Kecil) unt 61,000 Int – 25 may 2013
Tempat Sabun dinding (Panjang) unt 87,000 Int – 25 may 2013
726 Tempat Sabun wastavel unt 211,250 sorong jan-juni 2013
727 Gantungan baju doble bh 375,000 Int – 25 may 2013
728 Towel ring unt 304,200 sorong jan-juni 2013
729 Tissue Paper Bh 1,604,937 sorong jan-juni 2013
730 Bakdip Bh 1,950,000
731 Water drain+aksesoris set 195,000
732 Bak mandi Teraso set 650,000
Jet washer bh 347,100 Int – 07 Jun 2013
Roof drain bh 234,000 Int – 11 Jun 2013
Toilet Partition unt 8,190,000 Int – 07 Jun 2013
Kran dan Hand Shower unt 1,275,300
1 Shower tray 745,000
2 Jet washer THX20NB unt 212,000
3 Roof drain 250,000

XVIII BAHAN PARTISI DINDING /PLAFOND


733 Gypsumboard t.9 mm lbr 62,980 Int – 24 may 2013
734 Gypsumboard t.12 mm lbr 78,000 Int – 24 may 2013
735 Gypsumboard t.9 mm WR lbr 105,000 Int – 24 may 2013
736 Gypsumboard t.13 mm WA lbr 158,600 Int – 24 may 2013
737 Gypsumboard t.13 mm FS lbr 154,000 Int – 24 may 2013
738 Gypsumboard t.16 mm FS lbr 161,500 Int – 24 may 2013
739 Kalsium Silikat t. 4,5 mm lbr 111,540 Int – 24 may 2013
740 Plafon GRC Tiles lbr 180,000 sorong jan-juni 2013
List
741 List Profil 5 cm Gypsum m1
742 List Profil 7 cm Gypsum m1 12,000
742 List Profil 10 cm Gypsum m1 15,700
743 List Profil 5 cm Kayu m1 7,500
Cement& & Silika Board
744 Papan Kalsium Silikat t. 4,5 mm lbr 70,160 Int – 24 may 2013
745 Papan Kalsium Silikat t. 6 mm lbr 100,120 Int – 24 may 2013
746 Papan Kalsium Silikat t. 8 mm lbr 141,000 Int – 24 may 2013
747 KalsiBoard Ling 3.5® lbr 50,350 Int – 24 may 2013
748 KalsiBoard Ling 4.5® lbr 70,160 Int – 24 may 2013
749 KalsiBoard Ling 6® lbr 100,120 Int – 24 may 2013
750 KalsiBoard Ling 6-R1® lbr 102,740 Int – 24 may 2013
751 KalsiBoard Ling 6-R2® lbr 103,770 Int – 24 may 2013
752 KalsiBoard Part 8® lbr 136,180 Int – 24 may 2013
753 KalsiBoard Part 8® R-2 lbr 139,640 Int – 24 may 2013
754 KalsiBoard Part 8® R-4 lbr 140,100 Int – 24 may 2013
755 KalsiBoard Clad 10® lbr 171,850 Int – 24 may 2013
756 KalsiBoard Clad 12® lbr 208,200 Int – 24 may 2013
757 KalsiPlank 8® lbr 26,220 Int – 24 may 2013
758 KalsiPlank 8® Jati lbr 27,500 Int – 24 may 2013
759 KalsiPlank 12® lbr 39,470 Int – 24 may 2013
GRC
760 GRC Board 6 mm (122x244) lbr 95.000 Int – 24 may 2013
761 GRC Fiber Flat 4 mm (122x244) lbr 50.000 Int – 24 may 2013
762 GRC Fiber Lux 5 mm (122x244) lbr 70.000 Int – 24 may 2013
763 Super Panel 9 mm (122x244) lbr 200.000 Int – 24 may 2013
764 Superplank 100 9 mm (10x244) lbr 30.000 Int – 24 may 2013
765 Superplank 200 9 mm (20x244) lbr 46.000 Int – 24 may 2013
766 Superplank 300 9 mm (30x244) lbr 60.000 Int – 24 may 2013
767 Elephant Big Flat 4 mm (122x244) lbr 44,500 Int – 24 may 2013
768 Elephant Big Flat 6 mm (122x244) lbr 72,000 Int – 24 may 2013
769 Elephant Big Flat 8 mm (122x244) lbr 98,000 Int – 24 may 2013
770 Elephant Wood Plank 8 mm (100x4.050) lbr 50,000 Int – 24 may 2013
771 Elephant Wood Plank 8 mm (200x4.050) lbr 65,000 Int – 24 may 2013
772 Elephant Wood Plank 10 mm (300x4.050) lbr 70,000 Int – 24 may 2013
Akustik
773 Plafond akustik 60x60cm lbr 17,000 Int – 24 may 2013
774 Plafond akustik 60x120cm lbr 30,000 Int – 24 may 2013
775 Plafond Gyptile tipe Deko 60x60cm lbr 9,000 Int – 24 may 2013
776 Plafond Gyptile tipe Deko 120x60cm lbr 18,000 Int – 24 may 2013
777 Plafond Gyptile tipe Teksture 60x60cm lbr 10,000 Int – 24 may 2013
778 Plafond Gyptile tipe Teksture 120x60cm lbr 20,000 Int – 24 may 2013
779 Plafond Gyptile tipe Dura 60x60cm lbr 14,000 Int – 24 may 2013
780 Plafond Gyptile tipe Dura 120x60cm lbr 27,500 Int – 24 may 2013
781 Plafond Gyptile tipe Akustik 60x60cm lbr 14,500 Int – 24 may 2013
782 Plafond Gyptile tipe Akustik 120x60cm lbr 28,500 Int – 24 may 2013

XIX FRAME
783 Atap onduline m2 143,000
784 Rangka Plafond Metal furing l. 4 cm; 60 x 60 cm m2 92,950 sorong jan-juni 2013
785 Rangka Partisi Metal furing l. 4 cm; 60 x 60 cm m2 83,132 Int – 24 may 2013
786 Rangka hollow galvanis t. 0,35 m2 84,500 sorong jan-juni 2013
787 Profil Alumunium “T” m1 19,500
788 Besi Hollow 20x40mm (Sinchromated) btg 20,800
789 Besi Hollow 40x40mm (Sinchromated) btg 41,600
790 Besi Hollow 40x60mm (Sinchromated) btg 62,400
791 Besi Hollow 20x40mm (Galvanized) btg 21,450
792 Besi Hollow 40x40mm (Galvanized) btg 25,350
793 Besi Hollow 40x60mm (Galvanized) btg 47,450
794 Suspension rod Bh 4,550
795 Rangka Plafond Akustik 60 x 60 cm m2 124,861 Int – 24 may 2013
796 Rangka Plafond Akustik 60 x 120 cm m2 85,417 Int – 24 may 2013
797 Rangka Plafond Hollow 40x40cm m2 73,132 Int – 24 may 2013
798 Rangka Partisi Hollow 40x40cm m2 86,400 Int – 24 may 2013
799 Rangka Partisi Metal Stud m2 87,900 Int – 24 may 2013
Metal Furring
800 Top Cross btg 34,300 Int – 24 may 2013
801 Furring Channel btg 34,900 Int – 24 may 2013
801 Ceiling Batten / C section btg 52,100 Int – 24 may 2013
802 Wal Angle btg 9,300 Int – 24 may 2013
802 Top Cross Clip Bh 4,500 Int – 24 may 2013
803 Suspension rod Bh 9,600 Int – 24 may 2013
Akustik
804 Cross T 60 btg 5,000 Int – 24 may 2013
805 Cross T 120 btg 7,500 Int – 24 may 2013
805 Main T btg 25,000 Int – 24 may 2013
806 Wal Angle btg 14,000 Int – 24 may 2013
806 PN Clip Bh 2,900 Int – 24 may 2013
807 Suspension Rod PN Bh 3,800 Int – 24 may 2013
Hollow
808 Besi Hollow 20x40mm t.0.35mm btg 16,500 Int – 24 may 2013
809 Besi Hollow 20x40mm t.0.4mm btg 19,500 Int – 24 may 2013
810 Besi Hollow 20x40mm t.0.5mm btg 22,000 Int – 24 may 2013
811 Besi Hollow 40x40mm t.0.35mm btg 21,500 Int – 24 may 2013
812 Besi Hollow 40x40mm t.0.4mm btg 24,500 Int – 24 may 2013
813 Besi Hollow 40x40mm t.0.5mm btg 28,500 Int – 24 may 2013
814 Besi Hollow 40x60mm t.0.6mm btg 85,000 Int – 24 may 2013
815 Besi Hollow 20x40mm (galvanized) t.0.35mm btg 19,500 Int – 24 may 2013
816 Besi Hollow 20x40mm (galvanized) t.0.4mm btg 23,500 Int – 24 may 2013
817 Besi Hollow 20x40mm (galvanized) t.0.5mm btg 27,000 Int – 24 may 2013
818 Besi Hollow 20x40mm (galvanized) t.0.6mm btg 29,500 Int – 24 may 2013
819 Besi Hollow 40x40mm (galvanized) t.0.35mm btg 24,500 Int – 24 may 2013
820 Besi Hollow 40x40mm (galvanized) t.0.4mm btg 28,500 Int – 24 may 2013
821 Besi Hollow 40x40mm (galvanized) t.0.5mm btg 32,500 Int – 24 may 2013
822 Besi Hollow 40x40mm (galvanized) t.0.6mm btg 35,500 Int – 24 may 2013
Metal Stud
823 Metal Stud 51 t.0.45mm btg
824 Metal Stud 76 t.0.45mm btg
825 Metal Stud 100 t.0.45mm btg
826 Metal Track/Runner 51 t.0.45mm btg
827 Metal Track/Runner 76 t.0.45mm btg
828 Metal Track/Runner 100 t.0.45mm btg
Besi Hollow 50x100mm (galvanized) t.0.5mm btg 1,170,000
Pipa si hollow 8cm btg

XX BAHAN SALURAN AIR


829 Greffel U20 p. 1,00 m m' 46,475 sorong jan-juni 2013
830 Kanstien 40x9x19 cm ex Ubin Alpen bh 7,605 sorong jan-juni 2013

XXI PERALATAN / LAIN-LAIN


1 Kikir Nicholson 2 Kikir Lurus Besar bh 225,000
2 Kikir Nicholson 1.5 HUK bh 275,000
3 Kikir Nicholson Gergaji kecil bh 25,000
831 Sewa Alat Las jam 20,000 sorong jan-juni 2013
832 Sewa Stamper jam 32,500 sorong jan-juni 2013
833 Sewa Alat jam 57,000
834 Instalasi Listrik Sementara ttk 97,500 sorong jan-juni 2013
835 Lampu TL bh 97,500 sorong jan-juni 2013
836 Biaya Pemakaian Listrik bln 195,000 sorong jan-juni 2013
837 Excavatot kap. 0,5 m3 jam 500,000
838 Dumptruck kap 3-4 m3 jam 500,000
839 Solar Ltr 5,500 sorong jan-juni 2013
840 Bensin Ltr 6,500 sorong jan-juni 2013
841 Minyak Pelumas Ltr 35,000
842 Minyak Bekisting Ltr 3,000 sorong jan-juni 2013
843 Minyak Panas Ltr 4,500 sorong jan-juni 2013
844 Steiger ls
845 Kawat las listrik kg 25,000
846 Sealant clear neutral (300 ml) tb 35,000
847 Seal tape roll 10,000 sorong jan-juni 2013
848 Lem pipa tb 42,250
849 Formiten/spacer bekisting Bh 14,300
850 Ramset Bh 11,000
851 Pembersih kg 4,500
852 Stempet Pail 480,000 sorong jan-juni 2013
853 Teak Oil kg 35,000 sorong jan-juni 2013
854 Sikat Besi bh 15,000 sorong jan-juni 2013
855 Aquistic Arm Strong Lbr 105,000 sorong jan-juni 2013
856 Panel beton Pra Cetak Lbr 65,000 sorong jan-juni 2013
857 Kolom beton Pra Cetak Btg 44,000 sorong jan-juni 2013
858 Water Stop 150 mm m' 60,000 sorong jan-juni 2013
859 Water Stop 200 mm m' 93,600 sorong jan-juni 2013
860 Vibrator unt 300,000 Int-11 Jun 2013
861 Hager Box MCB Bh 985,500
862 Stop kontak Panasonic AC Bh 28,000
863 Steker Panasonic AC Bh 11,000
864 Kabel 3x1.5 Prima roll 320,000
865 Tarikan Oxford 128-4057 25,000

XXII ELEKTRIKAL
860 Tiang Galvanis Oktagonal 8 m 1 Mikro Btg 3,150,000 sorong jan-juni 2013
861 Tiang Besi Galvanis Oktagonal 8 m 2 Mikro Btg 4,250,000 sorong jan-juni 2013
862 Tiang Galvanis Biasa 8 m 1 Mikro Btg 2,900,000 sorong jan-juni 2013
863 Tiang Galvanis Biasa 8 m 2 Mikro Btg 3,200,000 sorong jan-juni 2013
864 MCB 32A 1 Ph MG bh 95,000 sorong jan-juni 2013
865 MCB 6A 1 Ph MG bh 75,000 sorong jan-juni 2013
866 MCB 32A 3 Ph MG bh 350,000 sorong jan-juni 2013
867 MCB 50A MG bh 350,000 sorong jan-juni 2013
868 Time Switch Legran 30A bh 550,000 sorong jan-juni 2013
869 Kontaktor 3 P 80A LCID50M7 bh 700,000 sorong jan-juni 2013
870 Kontaktor 1 P 40A LCID25M7 bh 550,000 sorong jan-juni 2013
871 Foto Cell Seleon AS 10A bh 200,000 sorong jan-juni 2013
872 Foto Cell Seleon AS 6A bh 175,000 sorong jan-juni 2013
873 Bola Lampu SON T 250 W bh 220,000 sorong jan-juni 2013
874 Bola Lampu SON H 400 W bh 295,000 sorong jan-juni 2013
875 Trafo Philips 250 W bh 300,000 sorong jan-juni 2013
876 Trafo Philips 400 W bh 450,000 sorong jan-juni 2013
877 Lampu TL 20 Watt bh 90,000 sorong jan-juni 2013
878 Lampu TL 2x20 Watt bh 110,000 sorong jan-juni 2013
879 Lampu TL 1x40 Watt bh 100,000 sorong jan-juni 2013
880 Lampu TL 2x40 Watt bh 150,000 sorong jan-juni 2013
881 Lampu Pijar 60 Watt (S) bh 7,000 sorong jan-juni 2013
882 Lampu Pijar 100 Watt bh 9,000 sorong jan-juni 2013
883 Lampu Pijar 25 Watt bh 5,500 sorong jan-juni 2013
884 Lampu Pijar 40 Watt bh 6,000 sorong jan-juni 2013
885 Lampu Pijar 75 Watt bh 8,000 sorong jan-juni 2013
886 Lampu SL 25 Watt bh 61,000 sorong jan-juni 2013
887 Lampu SL 50 Watt bh 135,000 sorong jan-juni 2013
888 Lampu SL 65 Watt bh 150,000 sorong jan-juni 2013
889 Lampu SL 85 Watt bh 180,000 sorong jan-juni 2013
890 Sekring Otomat bh 20,000 sorong jan-juni 2013
891 Stop Kontak (kontak) bh 25,000 sorong jan-juni 2013
892 Saklar Engkel Tanam bh 20,000 sorong jan-juni 2013
893 Saklar Double Tanam bh 25,000 sorong jan-juni 2013
894 Box Sekring Otomat 1 Group bh 22,000 sorong jan-juni 2013
895 Box Sekring Otomat 2 Group bh 45,000 sorong jan-juni 2013
896 Box Sekring Otomat 4 Group bh 50,000 sorong jan-juni 2013
897 Fitting DC bh 55,000 sorong jan-juni 2013
898 Flaser Fire Work Lamp bh 2,000,000 sorong jan-juni 2013
899 Kabel Tanah NYFGBY 4x6mm M' 45,000 sorong jan-juni 2013
900 Kabel SR M' 15,000 sorong jan-juni 2013
901 Lampu Son H 250 W Komplit bh 2,300,000 sorong jan-juni 2013
902 Lampu Son T 400 W Komplit bh 2,500,000 sorong jan-juni 2013
903 Panel Box 30x40x20 cm bh 327,000 sorong jan-juni 2013
904 Kabel Instalasi Listrik 2,5mm 100m' Roll 280,000 sorong jan-juni 2013
905 Kabel NYY 4x4 mm M' 30,000 sorong jan-juni 2013
906 Kabel NYM 2x1,5 mm M' 10,000 sorong jan-juni 2013
907 Kabel NYM 3x1,5 mm M' 15,000 sorong jan-juni 2013
908 Kabel NYM 2x2,5 mm M' 10,000 sorong jan-juni 2013
909 Kabel NYM 3x2,5 mm M' 16,000 sorong jan-juni 2013
910 Kabel NYM 4x3 mm M' 28,000 sorong jan-juni 2013
911 Isolasi Ban Roll 15,000 sorong jan-juni 2013
912 Klem Tarik bh 15,000 sorong jan-juni 2013
913 Konektor bh 10,000 sorong jan-juni 2013
914 Box Meteran Set 80,000 sorong jan-juni 2013
915 Baut ID. 14" s/d 24" bh 10,000 sorong jan-juni 2013
916 Trafo Distribusi 20 KV, 50 KVA, Outdoor Unit sorong jan-juni 2013
917 Cut Out 20 KV ....kA, Outdoor bh 1,400,000 sorong jan-juni 2013
918 Fuse Link 20 KV, 5A bh 50,000 sorong jan-juni 2013
919 Aresster 20 KV bh 1,200,000 sorong jan-juni 2013
920 Kawat AAAC 70 mm2 M' 20,000 sorong jan-juni 2013
921 Kabel NYY 1x70mm2, TR, untuk OG Trafo M' 175,000 sorong jan-juni 2013
922 Travers untuk dudukan CO & LA bh 325,000 sorong jan-juni 2013
923 Beugels 4" Komplit Mur Baut & Ring bh 40,000 sorong jan-juni 2013
924 Parallel Group 25/150 mm2 u/ Penyambungan bh 35,000 sorong jan-juni 2013
925 Kabel Schoen AL 70 mm untuk CO & LA M' 27,000 sorong jan-juni 2013
926 Kabel Schoen CU 90 mm Untuk Kabel Incoming M' 30,000 sorong jan-juni 2013
927 Pipa Kabel 3" u/ pelindung Kabel Outgoing Btg 175,000 sorong jan-juni 2013
928 Elbow (Knee) pipa 3" bh 20,000 sorong jan-juni 2013
929 Elbow (Knee) pipa 4" bh 53,000 sorong jan-juni 2013
930 Klem Beugels 5"/8" x 3" u/ dudukan pipa kabel bh 30,000 sorong jan-juni 2013
931 Klem Beugels , D 4", 8"x 1" u/ dudukan pipa pelindung Set 57,000 sorong jan-juni 2013
932 Klem Selang D 3/4" bh 53,000 sorong jan-juni 2013
933 Peti Pembagi 220/380 volt 100 A, 4 Group Unit 9,500,000 sorong jan-juni 2013
934 Travers UNP 10 x 2000mm2 u/ dudukan Trafo bh 300,000 sorong jan-juni 2013
935 Beugels 8" Komplit Mur Baut & Ring bh sorong jan-juni 2013
936 Mur Baut 5/8", 150mm Komplit Ring bh 10,000 sorong jan-juni 2013
937 Kabel Schoen CU 50mm Untuk Kabel Arde M' 15,000 sorong jan-juni 2013
938 Kabel BC Draad 50mm2 M' 70,000 sorong jan-juni 2013
939 Pipa Besi 1" untuk pelindung Btg 135,000 sorong jan-juni 2013
940 Patok Arde Komplit Baut Set 130,000 sorong jan-juni 2013
941 Twisted Cable 3x70mm2 + 1 x 50mm M' 70,000 sorong jan-juni 2013
942 Tension Bracket (klem pemegang) bh 55,000 sorong jan-juni 2013
943 Wedge Type Strain Clamb (klem jepit kbel) Set 15,000 sorong jan-juni 2013
944 Stainless Steel Strip 20x0,7 mm2 (klem pengikat) M' 12,000 sorong jan-juni 2013
945 Stopping Bukle Stainless Steel bh 20,000 sorong jan-juni 2013
946 Plastic Strap R12 (Pengikat TC) bh 2,000 sorong jan-juni 2013
947 Trap Connector 35-070/35-70mm bh sorong jan-juni 2013
948 Suspension Bracket (klem pemegang) bh 80,000 sorong jan-juni 2013
949 Kabel Twisted 2x10mm M' 18,000 sorong jan-juni 2013
950 MCB 1 Phasa, 220V, 1 s/d 35 A bh 250,000 sorong jan-juni 2013
951 KWH Meter 1 Phasa, 4 W, 220V, 5/20 A bh sorong jan-juni 2013
952 Kotak APP. OK bh 75,000 sorong jan-juni 2013
953 Piercing (TAP) Connector,/.mm2 bh 13,000 sorong jan-juni 2013
954 Two Way Pole Bracket bh 20,000 sorong jan-juni 2013
955 Mobilisasi Ls 15,600
956 Paket pekerjaan hotmix 2cm m2 160,550
957 Plastik Cor m2 6,500
958 Harga Torn Air Stainless 2500 ltr unt 7,800,000
959 Holder Kaca bh 25,000
960 Batu Andesit 30x30 m2 150,000
961 Buis beton 1/2 m1 71,500
962 Plat bondek m2 139,100
KETERANGAN

###
###
###
###
###
###

lokal, lubang 2, uk. 40X9x20


lokal, lubang 3, uk. 40X10x20
lokal, lubang 2, uk. 40X9x20
lokal, lubang 3, uk. 40X10x20
lokal, permukaan motif uk. 40X10x20

lokal
lokal
lokal
lokal
lokal
lokal
lokal
lokal
lokal
lokal
###
###
lokal JKT
###
###
###
###
###
###
###
###
###
###
###
###
###
###
harga PDAM bdg per mobil 500 liter
###
###
20x20 cm
###
###
###
###
###

ex.Tiga Roda
ex.Tiga Roda
ex.Tiga Roda 1 zak = 40 kg
ex.Lemkra, daya sebar 8-10m2/kg
###
###

###

Concrete Quality : K-450


Steel Quality : U-39
Spiral Reinforcement : Ø 5mm with 0.2mm tolerance
Standard Connection : Welded steel plate
Installation System : Drop Hammer & Jacked Pile
###
###
###
###
###
lokal bdg
lokal bdg

lokal bdg
lokal bdg
lokal bdg
lokal bdg
lokal bdg
lokal bdg
lokal bdg
lokal bdg
lokal bdg
lokal bdg
lokal bdg
lokal bdg
lokal bdg
lokal bdg
lokal bdg
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
Biasa
SNI, full, 12 meter
biasa, ukuran banci
SNI, full, 12 meter
biasa, ukuran banci
SNI, full, 12 meter
biasa, ukuran banci
SNI, full, 12 meter
SNI, full, 12 meter, ulir
biasa, ukuran banci
SNI, full, 12 meter, ulir
###
###
###
###
###
###
Biasa
SNI, full, 12 meter
SNI, full, 12 meter, ulir

###
###
###
ex.BRC, U50 spc 15x15cm, 1 lbr uk.2,1x5.4m, 1 roll 155 kg/54m
ex.BRC, U50 spc 15x15cm, 1 lbr uk.2,1x5.4m, 1 roll 242 kg/54m
ex.BRC, U50 spc 15x15cm, 1 lbr uk.2,1x5.4m, 1 roll 347.6bkg/54m
ex.BRC, U50 spc 15x15cm, 1 lbr uk.2,1x5.4m, 1 roll 473.1 kg/54m
ex.BRC, U50 spc 15x15cm, 1 lbr uk.2,1x5.4m, 1 roll 617.9 kg/54m
ex.BRC, U50 spc 15x15cm, 1 lbr uk.2,1x5.4m, 1 roll 782.1 kg/54m
ex.BRC, U50 spc 15x15cm, 1 lbr uk.2,1x5.4m, 1 roll 965.5 kg/54m
ex.BRC, U50 spc 15x15cm, 1 lbr uk.2,1x5.4m, 1 roll 1155.7 kg/54m
ex.BRC, spc 15x15cm, 1 lbr uk.2,1x5.4m, 1 roll 155 kg/54m
ex.BRC, spc 15x15cm, 1 lbr uk.2,1x5.4m, 1 roll 242 kg/54m
ex.BRC, spc 15x15cm, 1 lbr uk.2,1x5.4m, 1 roll 347.6bkg/54m
ex.BRC, spc 15x15cm, 1 lbr uk.2,1x5.4m, 1 roll 473.1 kg/54m
ex.BRC, spc 15x15cm, 1 lbr uk.2,1x5.4m, 1 roll 1155.7 kg/54m
###
###
###
###
###
###
###
###
###
###
###
###
###
###

###
uk. 5/7 & 5/10 panjang 3,80 m'

uk. 3/20 & 3/30 panjang 3,80 m'


###
uk. 5/7 & 5/10 panjang 3,80 m'
###
uk. 3/20 & 3/30 panjang 3,80 m'
###
uk. 5/7 & 5/10 panjang 3,80 m'
uk. 6/12, 6/15, 8/12 & 8/15 panjang 3,80 m'
uk. 3/20 & 3/30 panjang 3,80 m'
###
###
###
###
###
###
###
###
###
###
###
###
###
setara Indal
setara Indal
setara Indal
setara Indal
###
###

###

###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###

###
###
###
###
###
###

###
###
###
###
###
###

###
###
###
###
###
###
###

###

###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###

lokal
lokal

###
###
###
###
###
###
###
###
###
###
###
###
###
ex setara Alfa

###
###
Ferrari
Ferrari

paloma
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###

Uk 120x240 cm
Uk 120x240 cm
###
###
###
Uk 122x244 cm
Uk 122x244 cm
Uk 122x244 cm
Uk 120x240 cm
###
Uk 120x240 cm
Uk 120x240 cm
Uk 120x240 cm
Uk 120x240 cm
Uk 122x244 cm
###
ex.Violam
Uk 122x244 cm
Uk 122x244 cm
###

setara Roman
setara Roman
setara Roman
setara Roman
###
###
setara Roman
setara Roman
###
###
setara Roman
setara Roman

###
###
###
###
###
###
###
###
###
###

1 m2 = (25/dos)
1 m2 = (25/dos)
1 m2 = (20/dos)
1 m2 = (11/dos)
1 m2 = (11/dos)
1 m2 = (9/dos)
1 m2 = (9/dos)
1 m2 = (6/dos)
1 m2 = (6/dos)
1 m2 = (6/dos)
1 m2 = (6/dos)
1 m2 = (5/dos)
1 m2 = (5/dos)
1 m2 = (5/dos)
1 m2 = (4/dos)
1 m2 = (4/dos)
1 m2 = (4/dos)
1 m2 = (3/dos)
1 m2 = (3/dos)
1 m2 = (3/dos)
1 m2 = (10/dos)
1 m2 = (5/dos)
1 m2 = (5/dos)
1 m2 = (5/dos)
1 m2 = (30/dos)
1 m2 = (50/dos)
1 m2 = (33/dos)
###
###
###
###
###
###
###
###
###
###
###
###
###

###
###
lokal bdg
lokal bdg

lokal, press manual


lokal, press manual
lokal, press hidraulik, setara K-200
lokal, press hidraulik, setara K-200
lokal, press hidraulik, setara K-250
lokal, press hidraulik, setara K-250
lokal, press hidraulik, setara K-300
lokal, press hidraulik, setara K-300
lokal, press hidraulik, setara K-300
lokal, press hidraulik, setara K-300
lokal, press manual, uk.45x30
lokal, press manual, uk.33x33
lokal, press manual, uk.30x30
lokal, press hidraulik, setara K-250
lokal, press hidraulik, setara K-250
lokal, ukuran standar PU
lokal, ukuran standar PU
lokal, ukuran standar PU
lokal, ukuran standar PU
lokal, ukuran standar PU
lokal, ukuran standar PU
lokal, ukuran standar PU
lokal, ukuran standar PU
lokal, ukuran standar PU
lokal, ukuran standar PU
setara Citatah
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###

setara Roman
setara Roman
setara Roman
setara Roman
###
###
###
###
###
###

###
###
###
###
###
###
lokal bdg
lokal bdg
lokal bdg
###
###

1 m2 = (25/dos)
1 m2 = (25/dos)
1 m2 = (20/dos)
1 m2 = (20/dos)
1 m2 = (20/dos)
1 m2 = (16/dos)
1 m2 = (16/dos)
1 m2 = (16/dos)
1 m2 = (11/dos)
1 m2 = (11/dos)
1 m2 = (11/dos)
1 m2 = (11/dos)
1 m2 = (11/dos)
1 m2 = (11/dos)
1 m2 = (11/dos)
1 m2 = (12/dos)
1 m2 = (12/dos)
1 m2 = (12/dos)
1 m2 = (12/dos)
1 m2 = (12/dos)
1 m2 = (9/dos)
1 m2 = (9/dos)
1 m2 = (9/dos)
1 m2 = (9/dos)
1 m2 = (9/dos)
1 m2 = (9/dos)
1 m2 = (8/dos)
1 m2 = (8/dos)
1 m2 = (8/dos)
1 m2 = (8/dos)
1 m2 = (6/dos)
1 m2 = (6/dos)
1 m2 = (6/dos)
1 m2 = (6/dos)
1 m2 = (6/dos)
1 m2 = (5/dos)
1 m2 = (5/dos)
1 m2 = (5/dos)
1 m2 = (5/dos)
1 m2 = (5/dos)
setara Roman

lokal bdg
lokal bdg
lokal bdg

setara Bluescope
setara Surya roof
setara Surya roof
setara Bluescope

L. 90 cm
###
Uk. 80 x 180 cm
###
###
###
L. 90 cm
(0,2 x 0,45 m')
6" (0,6 x 1,80 m')
7" (0,7 x 1,80 m')
6" (0,6 x 1,80 m')
7" (0,6 x 1,80 m')
8" (0,6 x 1,80 m')
L. 30 cm

ex.Gajah Mas atau setara


ex.Gajah Mas atau setara
ex.Gajah Mas atau setara
ex.Gajah Mas atau setara
ex.Gajah Mas atau setara
ex.Gajah Mas atau setara
ex.Gajah Mas atau setara
ex.Gajah Mas atau setara
ex.Gajah Mas atau setara
ex.Gajah Mas atau setara

setara Jabesmen/Harflex non asbes (harga 2011)


setara Jabesmen/Harflex non asbes (harga 2011)
setara Jabesmen/Harflex non asbes (harga 2011)
setara Jabesmen/Harflex non asbes (harga 2011)
setara Jabesmen/Harflex non asbes (harga 2011)
setara Jabesmen/Harflex non asbes (harga 2011)

setara Jabesmen/Harflex non asbes (harga 2011)


setara Jabesmen/Harflex non asbes (harga 2011)
setara Jabesmen/Harflex non asbes (harga 2011)
setara Jabesmen/Harflex non asbes (harga 2011)
setara Jabesmen/Harflex non asbes (harga 2011)
setara Jabesmen/Harflex non asbes (harga 2011)

setara Jabesmen/Harflex non asbes (harga 2011)


setara Jabesmen/Harflex non asbes (harga 2011)
setara Jabesmen/Harflex non asbes (harga 2011)
setara Jabesmen/Harflex non asbes (harga 2011)
setara Jabesmen/Harflex non asbes (harga 2011)
setara Jabesmen/Harflex non asbes (harga 2011)

setara Jabesmen/Harflex non asbes (harga 2011)


setara Jabesmen/Harflex non asbes (harga 2011)
setara Jabesmen/Harflex non asbes (harga 2011)
setara Jabesmen/Harflex non asbes (harga 2011)
setara Jabesmen/Harflex non asbes (harga 2011)
setara Jabesmen/Harflex non asbes (harga 2011)

###
setara Jabesmen/Harflex non asbes (harga 2011)
setara Jabesmen/Harflex non asbes (harga 2011)
setara Jabesmen/Harflex non asbes (harga 2011)
setara Djabesnok
setara Djabesnok
setara Blue Scope
setara Solartuff
###
###
###
###
setara Djabesnok
setara Djabesnok
setara Sakura roof
setara Solartuff
###
###
###
###
###
###
###
lokal bdg
lokal bdg
lokal bdg
lokal bdg
lokal bdg
lokal bdg
lokal bdg
lokal bdg
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###

setara Lemkra
setara Lemkra
setara Lemkra

setara Sika
###
###
###
###
###
###
###
###
###
###

1,22 x 1,82 m'


1,22 x 1,82 m'
ex.Asahimas (harga 2012)
ex.Asahimas (harga 2012)
ex.Asahimas (harga 2012)
ex.Asahimas (harga 2012)
ex.Asahimas (harga 2012)
ex.Asahimas (harga 2012)
###
###
ex.Asahimas (harga 2012)
ex.Asahimas (harga 2012)
ex.Asahimas (harga 2012)
ex.Asahimas (harga 2012)
ex.Asahimas (harga 2012)
ex.Asahimas (harga 2012)
ex.Asahimas (harga 2012)
###
###
setara Globe

###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###

###
###
###
###

###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
setara Seiv
###
###

setara Vinilex
setara Vinilex
setara Vinilex
###
###
###
###
###

###
###
###
###
###
###
###
###
###
###
###

setara Vinilex
setara Vinilex
setara Vinilex
###
setara Sanlex

###
###
ex.Nipponpaint
ex.Nipponpaint
ex.Nipponpaint
###
ex.Nipponpaint
ex.Nipponpaint
ex.Nipponpaint
ex.Nipponpaint
###
ex.Nipponpaint
ex.Nipponpaint

###

ex.Dulux
ex.Dulux
ex.Dulux
ex.Dulux
ex.Dulux
ex.Dulux
ex.Dulux
ex.Dulux
ex.Dulux
ex.Dulux
ex.Dulux
ex.Dulux
ex.Dulux
ex.Dulux
ex.Dulux
ex.Dulux
ex.Dulux
###
ex.Mowilex
ex.Mowilex
ex.Mowilex
ex.Mowilex
ex.Mowilex
ex.Mowilex

###

###
###
###
###
###
###
###
###
###
###
Ex. Kia
###
###
CW702J/SW784JP ex.Toto
CW660J/SW660J ex.Toto
CW 420 J/SW 420 JP
CW 705/TV 150 NSV7
CW 660 J
ex KIA
TGB 500 AZRV24
CE 6 ex Toto
CE 7 ex Toto
CE 9/TV150NWV12J ex.Toto
CE 6 ex Toto
###
A 100 ex Toto
L 529 V1 / T 205 MCB
LW 523 J / TX 116 LE
LW 565 / TX 109 LD
LW 642 CJ / TX 115 LESN
LW 549 J / TX 108 LJ
LW 240 CJ / LW 240 HFJ
###
###
T 23 B13V7NB ex Toto
T 23 B13 ex Toto
T 205 MC
T 30 ARQ13N ex Toto
###
###
Hwaco 1L
Hwaco 2L
###
TX 1B ex Toto
###
###
TX 438 SZ
TR 309 S ex Toto
TX 403 S PIV ex Toto
TX 403 SMCR ex Toto
TX 720 ACR
TS 116 R

###

TS 126 AR

TS 118 WS
TS 115 SB
###
###
###
###
Toto THX20MCRB
 H0 1-4' SAN-EI
###
###
###
Filippo
White

uk 120 x 240 cm
uk 120 x 240 cm
ex.Jaya Board, tipe Wet Area
ex.Jaya Board, tipe Fire Stop
ex.Jaya Board, tipe Fire Stop
###
###
###

###
###
###
###
ex.Kalsiboard atau setara
ex.Kalsiboard atau setara
ex.Kalsiboard atau setara
ex.Kalsiboard uk.3.5 x 1200 x 2400
ex.Kalsiboard uk.4.5 x 1200 x 2400
ex.Kalsiboard uk.6 x 1200 x 2400
ex.Kalsiboard uk.6 x 1200 x 2400, resesed 2 sisi
ex.Kalsiboard uk.6 x 1200 x 2400, resesed 4 sisi
ex.Kalsiboard uk.8 x 1200 x 2400
ex.Kalsiboard uk.8 x 1200 x 2400, resesed 2 sisi
ex.Kalsiboard uk.8 x 1200 x 2400, resesed 4 sisi
ex.Kalsiboard uk.10 x 1200 x 2400
ex.Kalsiboard uk.12 x 1200 x 2400
ex.Kalsiboard uk.8 x 200 x 2400
ex.Kalsiboard uk.8 x 200 x 2400, motif jati
ex.Kalsiboard uk.12 x 200 x 2400, motif jati
###
ex.GRC (harga 2011)
ex.GRC (harga 2011)
ex.GRC (harga 2011)
ex.GRC (harga 2011)
ex.GRC (harga 2011)
ex.GRC (harga 2011)
ex.GRC (harga 2011)
ex.Elephant (harga 2011)
ex.Elephant (harga 2011)
ex.Elephant (harga 2011)
ex.Elephant (harga 2011)
ex.Elephant (harga 2011)
ex.Elephant (harga 2011)
###
ex.Jayaboard atau setara, t=9mm
ex.Jayaboard atau setara, t=12mm
ex. Jayaboard, t=9mm, polos
ex. Jayaboard, t=12mm, polos
ex. Jayaboard, t=9mm, motif bintik
ex. Jayaboard, t=12mm, motif bintik
ex. Jayaboard, t=9mm, motif teksture
ex. Jayaboard, t=12mm, motif moyif teksture
ex. Jayaboard, t=9mm, motif grid
ex. Jayaboard, t=12mm, motif grid
###

###
###
###
###
###
###
###
###
###
###
###
ex.Jayaboard atau setara
ex.Jayaboard atau setara
ex.Jayaboard atau setara
ex.Jayaboard atau setara
ex.Jayaboard atau setara
###
ex.Jayaboard atau setara, panjang 3.6 m
ex.Jayaboard atau setara, panjang 4.8 m
ex.Jayaboard atau setara, panjang 4.8 m
ex.Jayaboard atau setara, panjang 3 m
ex.Jayaboard atau setara
ex.Jayaboard atau setara, panjang 3.6 m
###
ex.Jayaboard atau setara, panjang 60 cm
ex.Jayaboard atau setara, panjang 1,2 m
ex.Jayaboard atau setara, panjang 3.6 m
ex.Jayaboard atau setara, panjang 3 m
ex.Jayaboard atau setara
ex.Jayaboard atau setara, panjang 2.4 m
###
ex.lokal, panjang 4m, belum dimeni
ex.lokal, panjang 4m, belum dimeni
ex.lokal, panjang 4m, belum dimeni
ex.lokal, panjang 4m, belum dimeni
ex.lokal, panjang 4m, belum dimeni
ex.lokal, panjang 4m, belum dimeni
ex.lokal, panjang 4m
ex.lokal, panjang 4m
ex.lokal, panjang 4m
ex.lokal, panjang 4m
ex.lokal, panjang 4m
ex.lokal, panjang 4m
ex.lokal, panjang 4m
ex.lokal, panjang 4m
ex.lokal, panjang 4m
###
uk.51x35x10
uk.76x35x10
uk.100x35x10
uk.51x35
uk.76x35
uk.100x35

###

###
###

Ferrari
Ferrari

###
###
###
###
###
###
###
###
###
###
###
###
###

###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###

###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###

###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###

###
###
###
###
###
###
###
###
###
###
###

###
###
###

###
###
###
###
###
###
###
NO HARGA MATERIAL SATUAN HARGA SATUAN KETERANGAN
XXIII UPAH PEKERJA :
A Pengukuran :
1 Juru Ukur Org/Hari

2 Pembantu Juru Ukur Org/Hari

B Pembesian :
3 Tukang Besi Konstruksi Org/Hari 80,000
4 Tukang Besi Tulangan Org/Hari 80,000
5 Kepala Tukang Besi Org/Hari 95,000

C Kayu
6 Tukang Kayu Kasar Org/Hari 80,000 (Plafond , Kuda/Gording, R.Atap)
7 Tukang Kayu Halus Org/Hari 80,000 (Kusen)
8 Kepala Tukang Kayu Org/Hari 95,000

D Tembok / batu
9 Tukang Batu Kasar Org/Hari 80,000 Tukang Batu Kasar
10 Tukang Batu Halus Org/Hari 80,000 Tukang Batu Halus (Bata,Plester,Acian list2)
11 Kepala Tukang Batu Org/Hari 95,000

E Cat:

12 Tukang Cat Biasa Org/Hari 80,000


13 Tukang Cat Duco Org/Hari 80,000
14 Kepala Tukang Cat Org/Hari 95,000

F Lain-Lain :
15 Pekerja Org/Hari 60,000
16 Kepala Tukang Org/Hari 80,000
17 Tukang Gali Org/Hari 75,000

18 Mandor Org/Hari 95,000


19 Penjaga Malam Org/Hari 121,000
20 Pengemudi Org/Hari 135,828
21 Operator Org/Hari 155,232
22 Pembantu Operator Org/Hari 121,968
23 Operator Alat Berat Org/Hari 155,232
24 Mekanik Org/Hari 152,888
25 Pembantu Operator Org/Hari 121,968
26 Operator Alat Berat Org/Hari 152,888
27 Mekanik Org/Hari 152,888
18,000 btg
28,000 btg
38,000 btg
46,500 btg
56,000 btg
69,000 btg
80,000 btg
95,000 btg
112,000 btg
156,000 btg

120,000.00

173,000 btg
135,000.00
Tabel I.1 Analisa Harga Satuan Pekerjaan Persiapan

1 m2 Membersihkan Lokasi Proyek


a Pekerja 0.100 Org/Hari 60,000 6,000
b Mandor 0.005 Org/Hari 95,000 475
JUMLAH 6,475
1 m1 Pengukuran & Pemasangan Bowplank (RSNI: T-12-2002-6.4)
1 Kaso kelas III 0.012 m3 2,387,000 28,644
2 Paku 4 s/d 7 cm 0.020 kg 36,000 720
3 Balok kelas III 0.007 m3 2,387,000 16,709
a Tukang Kayu Kasar 0.100 Org/Hari 80,000 8,000
b Pekerja 0.100 Org/Hari 60,000 6,000
c Kepala Tukang 0.010 Org/Hari 80,000 800
d Mandor 0.005 Org/Hari 95,000 475
JUMLAH 61,348
1 m2 Pembuatan Bedeng Buruh
1 Dolken dia 5 s/d 7 cm p. 4 m 1.250 btg 13,144 16,430
2 Kayu Kuat klas III 0.186 m3 2,335,667 434,434
3 Paku 8 s/d 12 cm 0.300 kg 36,000 10,800
4 Semen PC (50 Kg) 0.360 zak 63,500 22,860
5 Pasir Beton 0.030 m3 145,000 4,350
6 Batu Split Pecah Mesin 2/3 0.050 m3 145,000 7,250
7 Seng Gelombang BJLS 0,3 1.500 lbr 100,100 150,150
8 Triplex t. 4 mm 1.500 lbr 54,000 81,000
a Tukang Kayu Kasar 2.000 Org/Hari 80,000 160,000
b Pekerja 1.000 Org/Hari 60,000 60,000
c Kepala Tukang 0.200 Org/Hari 80,000 16,000
d Mandor 0.050 Org/Hari 95,000 4,750
JUMLAH 968,024
1 m2 Pembuatan Gudang Proyek
1 Dolken dia 5 s/d 7 cm p. 4 m 1.700 btg13,144 22,345
2 Kayu Kuat klas III 0.210 m3
2,335,667 490,490
3 Paku 8 s/d 12 cm 0.300 kg36,000 10,800
4 Semen PC (50 Kg) 0.210 zak63,500 13,335
5 Pasir Pasang 0.030 m3135,000 4,050
6 Pasir Beton 0.050 m3145,000 7,250
7 Seng Gelombang BJLS 0,3 1.500 lbr
100,100 150,150
a Tukang Kayu Kasar 2.000 Org/Hari
80,000 160,000
b Pekerja 1.000 Org/Hari
60,000 60,000
c Kepala Tukang 0.200 Org/Hari
80,000 16,000
d Mandor 0.050 Org/Hari
95,000 4,750
JUMLAH 939,170
1 m2 Pagar Sementara Seng Gelombang (T=2M) (RSNI: T-12-2002-6.2)
1 Dolken dia 5 s/d 7 cm p. 4 m 1.250 btg 13,144 16,430
2 Semen PC (50 Kg) 2.500 zak 63,500 158,750
3 Seng Gelombang BJLS 0,3 1.200 lbr 100,100 120,120
4 Pasir Beton 0.005 m3 145,000 725
5 Batu Split Pecah Mesin 2/3 0.009 m3 145,000 1,305
6 Kaso kelas III 0.072 m3 2,387,000 171,864
7 Paku 1 s/d 3 cm 0.060 kg 20,020 1,201
8 Cat Dasar / meni besi 0.450 Kg 28,336 12,751
a Tukang Kayu Halus 0.200 Org/Hari 80,000 16,000
b Pekerja 0.400 Org/Hari 60,000 24,000
c Kepala Tukang 0.020 Org/Hari 80,000 1,600
d Mandor 0.020 Org/Hari 95,000 1,900
JUMLAH 526,646
JUMLAH BAHAN DAN UPAH DI AHS BAB I 2,501,663
JUMLAH BAHAN DAN UPAH DI RAB BAB I 2,501,663
KONTROL OK
Tabel 1.2 Volume Pekerjaan Persiapan

1 Membersihkan Lokasi Proyek


Panjang (m) Lebar (m) Volume (m2)
16 7 112

2 Pengukuran & Pemasangan Bowplank


VERTIKAL HORIZONTA
85 49
134

3 Pembuatan Bedeng Buruh


Panjang (m) Lebar (m) Volume (m2)
4 3 12
Tabel I.3 Rencana Anggaran Biaya Pekerjaan Persiapan

Harga Satuan Jumlah Harga Jumlah


No. Uraian Jenis Pekerjaan Sat. Vol.
Bahan Upah Bahan Upah Bahan + Upah
A B C D E F G=DxE H=DxF I=G+H
1 Membersihkan Lokasi Proyek m2 112 - 6,475 - 725,200 725,200
2 Pengukuran & Pemasangan Bowplank m1 134 46,073 15,275 6173782 2,046,850 8,220,632
3 Pembuatan Bedeng Buruh m2 12 727,274 240,750 8,727,288 2,889,000 11,616,288
4 Pembuatan Gudang Proyek m2 9 698,420 240,750 6,285,778 2,166,750 8,452,528
5 Pagar Sementara Seng Gelombang (T=2M) m2 44 483,146 43,500 21,258,442 1,914,000 23,172,442
Jumlah Total 42,445,290 9,741,800 52,187,090
Persentase (%) 81% 19% 100%
Tabel II.1 Analisa Harga Satuan Pekerjaan Tanah dan Pondasi

1 m3 Galian Tanah Sedalam <1m (SNI:2835:2008-6.1)


a Pekerja 0.750 Org/Hari 60,000 45,000
b Mandor 0.025 Org/Hari 95,000 2,375
JUMLAH 47,375
1 m3 Urugan Pasir (SNI:2835:2008-6.11)
1 Pasir Urug 1.050 m3 100,000 105,000
a Pekerja 0.300 Org/Hari 60,000 18,000
b Mandor 0.010 Org/Hari 95,000 950
JUMLAH 123,950
1 m3 Pasang Pondasi BT Kosong (Aanstamping) (SNI:2836:2008-6.9)
1 Batu Belah Pondasi 1.200 m3 228,571 274,286
2 Pasir Urug 0.432 m3 100,000 43,200
a Pekerja 0.780 Org/Hari 60,000 46,800
b Tukang Batu Kasar 0.390 Org/Hari 80,000 31,200
c Kepala Tukang 0.039 Org/Hari 80,000 3,120
d Mandor 0.039 Org/Hari 95,000 3,705
JUMLAH 402,311
1 m3 Pasang Pondasi BT Kali (SNI:2836:2008-6.9)
1 Batu kali 1.200 bh 227,500 273,000
2 Pasir Urug 0.432 m3 100,000 43,200
a Pekerja 0.780 Org/Hari 60,000 46,800
b Tukang Batu Kasar 0.390 Org/Hari 80,000 31,200
c Kepala Tukang 0.039 Org/Hari 80,000 3,120
d Mandor 0.039 Org/Hari 95,000 3,705
JUMLAH 401,025
1 m3 Urugan Tanah (SNI:2835:2008-6.10)
a Pekerja 0.250 Org/Hari 60,000 15,000
b Mandor 0.025 Org/Hari 95,000 2,375
JUMLAH 17,375
JUMLAH BAHAN DAN UPAH DI AHS BAB II 992,036
JUMLAH BAHAN DAN UPAH DI RAB BAB II 992,036
KONTROL OK
Tabel II.3 Rencana Anggaran Biaya Pekerjaan Tanah dan Pondasi

Harga Satuan Jumlah Harga Jumlah


No. Uraian Jenis Pekerjaan Sat. Vol.
Bahan Upah Bahan Upah Bahan + Upah
A B C D E F G=DxE H=DxF I=G+H
1 Galian Tanah Sedalam <1m m3 26.400 - 47,375 - 1,250,700 1,250,700
2 Urugan Pasir m3 1.111 105,000 18,950 116,655 21,053 137,708
3 Pasang Pondasi BT Kosong (Aanstamping) m3 3.465 317,486 84,825 1,100,088 293,919 1,394,007
4 Pasang Pondasi BT Kali m3 9.240 316,200 84,825 2,921,688 783,783 3,705,471
5 Urugan Tanah m3 12.584 - 17,375 - 218,647 218,647
Jumlah Total 4,138,431 2,568,102 6,706,533
Persentase (%) 62% 38% 100%
Tabel II.2 Volume Pekerjaan Tanah dan Pondasi

1 Galian Tanah Sedalam <1m


Kedalaman Lebar (m) Panjang Pondasi
Volume (m3)
(m) Atas Bawah Vertikal Horizontal
A B C D =Ax B x C
1.000 1.400 1.000 16.000 6.000 26.400
Galian Tanah Sedalam <1m 26.400

2 Urugan Pasir
Kedalaman Lebar (m) Panjang Pondasi
Volume (m3)
(m) Atas Bawah Vertikal Horizontal
A B C D =Ax B x C
0.050 1.020 1.000 16.000 6.000 1.111
Urugan Pasir 1.111
3 Pasang Pondasi BT Kosong (Aanstamping)
Kedalaman Lebar (m) Panjang Pondasi
Volume (m3)
(m) Bawah Atas Vertikal Horizontal
A B C D =Ax B x C
0.150 1.020 1.080 16.000 6.000 3.465
Pasang Pondasi BT Kosong (Aanstamping) 3.465

4 Pasang Pondasi BT Kali


Kedalaman Lebar (m) Panjang Pondasi
Volume (m3)
(m) Bawah Atas Vertikal Horizontal
A B C D =Ax B x C
0.800 0.800 0.250 16.000 6.000 9.240
Pasang Pondasi BT Kali 9.240

5 Urugan Tanah
Volume
Galian Tanah Batu
Urugan Pasir Batu Kali Volume (m3)
(m3) Kosong
A B C D E = (A-B-C-D)
26.400 1.111 3.465 9.240 12.584
Urugan Tanah 12.584
1 m2 Pembuatan Bekisiting untuk Sloof
1 Kayu Kuat klas III 0.0450 m3
2 Paku 8 s/d 12 cm 0.3000 kg
3 Minyak Pelumas 0.1000 Ltr
a Pekerja 0.5200 Org/Hari
b Tukang Batu Kasar 0.2600 Org/Hari
c Kepala Tukang 0.0260 Org/Hari
d Mandor 0.0260 Org/Hari

2 m2 Pembuatan Bekisiting untuk Kolom


1 Kayu Kuat klas III 0.0400 m3
2 Paku 8 s/d 12 cm 0.4000 kg
3 Minyak Pelumas 0.2000 Ltr
4 Kayu Kuat klas II 0.0150 m3
5 Multiplex t. 9 mm 0.3500 lbr
6 Dolken dia 8 s/d 10 cm p. 4 m 2.0000 btg
a Pekerja 0.6600 Org/Hari
b Tukang Batu Kasar 0.3300 Org/Hari
c Kepala Tukang 0.0330 Org/Hari
d Mandor 0.0330 Org/Hari

3 m2 Pembuatan Bekisiting untuk Balok


1 Kayu Kuat klas III 0.0400 m3
2 Paku 8 s/d 12 cm 0.4000 kg
3 Minyak Pelumas 0.2000 Ltr
4 Kayu Kuat klas II 0.0180 m3
5 Multiplex t. 9 mm 0.3500 lbr
6 Dolken dia 8 s/d 10 cm p. 4 m 2.0000 btg
a Pekerja 0.6600 Org/Hari
b Tukang Batu Kasar 0.3300 Org/Hari
c Kepala Tukang 0.0330 Org/Hari
d Mandor 0.0330 Org/Hari

4 m2 Pembuatan Bekisiting untuk Plat Lantai


1 Kayu Kuat klas III 0.0400 m3
2 Paku 8 s/d 12 cm 0.4000 kg
3 Minyak Pelumas 0.2000 Ltr
4 Kayu Kuat klas II 0.0150 m3
5 Multiplex t. 9 mm 0.3500 lbr
6 Dolken dia 8 s/d 10 cm p. 4 m 6.0000 btg
a Pekerja 0.6600 Org/Hari
b Tukang Batu Kasar 0.3300 Org/Hari
c Kepala Tukang 0.0330 Org/Hari
d Mandor 0.0330 Org/Hari

5 m2 Pembuatan Bekisiting untuk Tangga


1 Kayu Kuat klas III 0.0300 m3
2 Paku 8 s/d 12 cm 0.4000 kg
3 Minyak Pelumas 0.1500 Ltr
4 Kayu Kuat klas II 0.0150 m3
5 Multiplex t. 9 mm 0.3500 lbr
6 Dolken dia 8 s/d 10 cm p. 4 m 2.0000 btg
a Pekerja 0.6600 Org/Hari
b Tukang Batu Kasar 0.3300 Org/Hari
c Kepala Tukang 0.0330 Org/Hari
d Mandor 0.0330 Org/Hari

6 m3 Pekerjaan Sloof Beton (Besi 200kg + bekisting)


1 Kayu Kuat klas III 0.2700 m3
2 Paku 8 s/d 12 cm 2.0000 kg
3 Minyak Pelumas 0.6000 Ltr
4 Besi Beton rata-rata 210.0000 Kg
5 Kawat Beton Hitam 3.0000 kg
6 Semen PC (50 Kg) 6.7200 zak
7 Pasir Beton 0.5400 m3
8 Batu Split Pecah Mesin 2/3 0.8100 m3
a Pekerja 0.5650 Org/Hari
b Tukang Batu Kasar 0.2750 Org/Hari
c Tukang Kayu Kasar 1.5600 Org/Hari
d Tukang Besi Tulangan 1.4000 Org/Hari
e Kepala Tukang 0.3230 Org/Hari
f Mandor 0.2830 Org/Hari

7 m3 Pekerjaan Kolom Beton (Besi 300kg + bekisting)


1 Kayu Kuat klas III 0.4000 m3
2 Paku 8 s/d 12 cm 4.0000 kg
3 Minyak Pelumas 2.0000 Ltr
4 Besi Beton rata-rata 315.0000 Kg
5 Kawat Beton Hitam 4.5000 kg
6 Semen PC (50 Kg) 6.7200 zak
7 Pasir Beton 0.5400 m3
8 Batu Split Pecah Mesin 2/3 0.8100 m3
9 Kayu Kuat klas II 0.1500 m3
10 Multiplex t. 9 mm 3.5000 lbr
11 Dolken dia 8 s/d 10 cm p. 4 m 20.0000 btg
a Pekerja 7.0500 Org/Hari
b Tukang Batu Kasar 0.2750 Org/Hari
c Tukang Kayu Kasar 1.6500 Org/Hari
d Tukang Besi Tulangan 2.1000 Org/Hari
e Kepala Tukang 0.4030 Org/Hari
f Mandor 0.3530 Org/Hari

8 m3 Pekerjaan Balok Beton (Besi 200kg + bekisting)


1 Kayu Kuat klas III 0.3200 m3
2 Paku 8 s/d 12 cm 3.2000 kg
3 Minyak Pelumas 1.6000 Ltr
4 Besi Beton rata-rata 210.0000 Kg
5 Kawat Beton Hitam 3.0000 kg
6 Semen PC (50 Kg) 6.7200 zak
7 Pasir Beton 0.5400 m3
8 Batu Split Pecah Mesin 2/3 0.8100 m3
9 Kayu Kuat klas II 0.1400 m3
10 Multiplex t. 9 mm 2.8000 lbr
11 Dolken dia 8 s/d 10 cm p. 4 m 16.0000 btg
a Pekerja 6.3500 Org/Hari
b Tukang Batu Kasar 0.2750 Org/Hari
c Tukang Kayu Kasar 1.6500 Org/Hari
d Tukang Besi Tulangan 1.4000 Org/Hari
e Kepala Tukang 0.3330 Org/Hari
f Mandor 0.3180 Org/Hari

9 m3 Pekerjaan Plat Beton (Besi 150kg + bekisting)


1 Kayu Kuat klas III 0.3200 m3
2 Paku 8 s/d 12 cm 3.2000 kg
3 Minyak Pelumas 1.6000 Ltr
4 Besi Beton rata-rata 157.5000 Kg
5 Kawat Beton Hitam 2.2500 kg
6 Semen PC (50 Kg) 6.7200 zak
7 Pasir Beton 0.5400 m3
8 Batu Split Pecah Mesin 2/3 0.8100 m3
9 Kayu Kuat klas II 0.1200 m3
10 Multiplex t. 9 mm 2.8000 lbr
11 Dolken dia 8 s/d 10 cm p. 4 m 32.0000 btg
a Pekerja 5.3000 Org/Hari
b Tukang Batu Kasar 0.2750 Org/Hari
c Tukang Kayu Kasar 1.3000 Org/Hari
d Tukang Besi Tulangan 1.0500 Org/Hari
e Kepala Tukang 0.2650 Org/Hari
f Mandor 0.2650 Org/Hari

10 m1 Pekerjaan Ring Balok Beton (10x15cm)


1 Kayu Kuat klas III 0.0030 m3
2 Paku 8 s/d 12 cm 0.0200 kg
3 Besi Beton rata-rata 3.6000 Kg
4 Kawat Beton Hitam 0.0500 kg
5 Semen PC (50 Kg) 0.1100 zak
6 Pasir Beton 0.0090 m3
7 Batu Split Pecah Mesin 2/3 0.0150 m3
a Pekerja 0.2970 Org/Hari
b Tukang Batu Kasar 0.0330 Org/Hari
c Tukang Kayu Kasar 0.0330 Org/Hari
d Tukang Besi Tulangan 0.0330 Org/Hari
e Kepala Tukang 0.0100 Org/Hari
f Mandor 0.0150 Org/Hari
(SNI:7394:2008-6.21)
2,335,667 105,105
36,000 10,800
35,000 3,500
60,000 31,200
80,000 20,800
80,000 2,080
95,000 2,470
JUMLAH 175,955

(SNI:7394:2008-6.22)
2,335,667 93,427
36,000 14,400
35,000 7,000
9,500,000 142,500
100,000 35,000
15,000 30,000
60,000 39,600
80,000 26,400
80,000 2,640
95,000 3,135
JUMLAH 394,102

(SNI:7394:2008-6.23)
2,335,667 93,427
36,000 14,400
35,000 7,000
9,500,000 171,000
100,000 35,000
15,000 30,000
60,000 39,600
80,000 26,400
80,000 2,640
95,000 3,135
JUMLAH 422,602

(SNI:7394:2008-6.24)
2,335,667 93,427
36,000 14,400
35,000 7,000
9,500,000 142,500
100,000 35,000
15,000 90,000
60,000 39,600
80,000 26,400
80,000 2,640
95,000 3,135
JUMLAH 454,102
(SNI:7394:2008-6.26)
2,335,667 70,070
36,000 14,400
35,000 5,250
9,500,000 142,500
100,000 35,000
15,000 30,000
60,000 39,600
80,000 26,400
80,000 2,640
95,000 3,135
JUMLAH 368,995
(SNI:7394:2008-6.29)
2,335,667 630,630
36,000 72,000
35,000 21,000
1,721 361,397
27,000 81,000
63,500 426,720
145,000 78,300
145,000 117,450
60,000 33,900
80,000 22,000
80,000 124,800
80,000 112,000
80,000 25,840
95,000 26,885
JUMLAH 2,133,922

(SNI:7394:2008-6.30)
2,335,667 934,267
36,000 144,000
35,000 70,000
1,721 542,095
27,000 121,500
63,500 426,720
145,000 78,300
145,000 117,450
9,500,000 1,425,000
100,000 350,000
15,000 300,000
60,000 423,000
80,000 22,000
80,000 132,000
80,000 168,000
80,000 32,240
95,000 33,535
JUMLAH 5,320,107

(SNI:7394:2008-6.31)
2,335,667 747,413
36,000 115,200
35,000 56,000
1,721 361,397
27,000 81,000
63,500 426,720
145,000 78,300
145,000 117,450
9,500,000 1,330,000
100,000 280,000
15,000 240,000
60,000 381,000
80,000 22,000
80,000 132,000
80,000 112,000
80,000 26,640
95,000 30,210
JUMLAH 4,537,330

(SNI:7394:2008-6.32)
2,335,667 747,413
36,000 115,200
35,000 56,000
1,721 271,048
27,000 60,750
63,500 426,720
145,000 78,300
145,000 117,450
9,500,000 1,140,000
100,000 280,000
15,000 480,000
60,000 318,000
80,000 22,000
80,000 104,000
80,000 84,000
80,000 21,200
95,000 25,175
JUMLAH 4,347,256
(SNI:7394:2008-6.36)
2,335,667 7,007
36,000 720
1,721 6,195
27,000 1,350
63,500 6,985
145,000 1,305
145,000 2,175
60,000 17,820
80,000 2,640
80,000 2,640
80,000 2,640
80,000 800
95,000 1,425
JUMLAH 53,702
BETON

1. SLOOF T L P VOLUME BEGISTING


0.3 0.2 134 8.04

2. KOLOM T L P VOLUME BEGISTING


0.3 0.2 96 5.76

3. BALOK & RING BALOK T L P VOLUME BEGISTING


0.3 0.2 134 8.04

4. PLATE BETON P L T VOLUME BEGISTING


10 6 0.15 9

5. TANGGA P L T VOLUME BEGISTING


5.1 1 0.3 1.53
T L P VOLUME
0.3 0.02 269.5 1.617

T L P VOLUME
0.3 0.02 384 2.304

T L P VOLUME
0.3 0.02 269.5 1.617

T L P VOLUME PLATE BETON + TANGGA


0.3 0.02 53.1 0.3186 10.53

T L P VOLUME
0.3 0.02 4.8 0.0288
Tabel IV.1 Analisa Harga Satuan Pekerjaan Dinding

1 m2 Pasangan Bata Merah 1Bt (1 pc : 4 Ps) (SNI:6897:2008-6.3)


1 Bata Merah 140.0000 bh 600 84,000
2 Semen PC (50 Kg) 0.5310 zak 63,500 33,719
3 Pasir Pasang 0.0930 m3 135,000 12,555
a Pekerja 0.6000 Org/Hari 60,000 36,000
b Tukang Batu Kasar 0.2000 Org/Hari 80,000 16,000
c Kepala Tukang 0.0200 Org/Hari 80,000 1,600
d Mandor 0.0300 Org/Hari 95,000 2,850
JUMLAH 186,724
1 m2 Pasangan Bata Merah 1Bt (1 pc : 5 Ps) (SNI:6897:2008-6.4)
1 Bata Merah 140.0000 bh 600 84,000
2 Semen PC (50 Kg) 0.4440 zak 63,500 28,194
3 Pasir Pasang 0.1020 m3 135,000 13,770
a Pekerja 0.6000 Org/Hari 60,000 36,000
b Tukang Batu Kasar 0.2000 Org/Hari 80,000 16,000
c Kepala Tukang 0.0200 Org/Hari 80,000 1,600
d Mandor 0.0300 Org/Hari 95,000 2,850
JUMLAH 182,414
1 m2 Dinding Keramik (uk. = 20x20 cm)K (SNI:7395:2008-6.54)
1 Keramik Dinding 20/20 cm Polished 1.0600 m2 87,000 92,220
2 Semen PC (50 Kg) 0.1860 zak 63,500 11,811
3 Pasir Pasang 0.0180 m3 135,000 2,430
4 Semen Warna 1.9400 kg 12,500 24,250
a Pekerja 0.6000 Org/Hari 60,000 36,000
b Tukang Batu Kasar 0.4500 Org/Hari 80,000 36,000
c Kepala Tukang 0.0450 Org/Hari 80,000 3,600
d Mandor 0.0350 Org/Hari 95,000 3,325
JUMLAH 209,636
1 m2 Dinding Keramik (uk. = 20x25 cm)K (SNI:7395:2008-6.54)R
1 Keramik Dinding 20/25 cm Polished 1.0600 m2 90,000 95,400
2 Semen PC (50 Kg) 0.1860 zak 63,500 11,811
3 Pasir Pasang 0.0180 m3 135,000 2,430
4 Semen Warna 1.9400 kg 12,500 24,250
a Pekerja 0.0900 Org/Hari 60,000 5,400
b Tukang Batu Kasar 0.0450 Org/Hari 80,000 3,600
c Kepala Tukang 0.0045 Org/Hari 80,000 360
d Mandor 0.0045 Org/Hari 95,000 428
JUMLAH 143,679
1 m2 Plesteran tebal= 2cm (1 pc : 4 Ps) (SNI:2837:2008-6.15)
1 Semen PC (50 Kg) 0.1664 zak 63,500 10,566
2 Pasir Pasang 0.0320 m3 135,000 4,320
a Pekerja 0.4000 Org/Hari 60,000 24,000
b Tukang Batu Kasar 0.2000 Org/Hari 80,000 16,000
c Kepala Tukang 0.0200 Org/Hari 80,000 1,600
d Mandor 0.0220 Org/Hari 95,000 2,090
JUMLAH 58,576
1 m2 Plesteran tebal= 2cm (1 pc : 5 Ps) (SNI:2837:2008-6.16)
1 Semen PC (50 Kg) 0.1382 zak 63,500 8,778
2 Pasir Pasang 0.0350 m3 135,000 4,725
a Pekerja 0.4000 Org/Hari 60,000 24,000
b Tukang Batu Kasar 0.2000 Org/Hari 80,000 16,000
c Kepala Tukang 0.0200 Org/Hari 80,000 1,600
d Mandor 0.0220 Org/Hari 95,000 2,090
JUMLAH 57,193
1 m2 Acian (SNI:2837:2008-6.27)
1 Semen PC (50 Kg) 0.0650 zak 63,500 4,128
a Pekerja 0.2000 Org/Hari 60,000 12,000
b Tukang Batu Kasar 0.1000 Org/Hari 80,000 8,000
c Kepala Tukang 0.0100 Org/Hari 80,000 800
d Mandor 0.1000 Org/Hari 95,000 9,500
JUMLAH 34,428
JUMLAH BAHAN DAN UPAH DI AHS BAB IV 872,649
JUMLAH BAHAN DAN UPAH DI RAB BAB IV 872,649
KONTROL OK
Harga Satuan
No. Uraian Jenis Pekerjaan Sat. Vol.
Bahan
A B C D E
1 Pembuatan Bekisiting untuk Sloof m2 26.400 119,405
2 Pembuatan Bekisiting untuk Kolom m2 2.304 322,327
3 Pembuatan Bekisiting untuk Balok m2 1.617 350,827
4 Pembuatan Bekisiting untuk Plat Lantai m2 0.319 382,327
5 Pembuatan Bekisiting untuk Tangga m2 0.029 297,220
6 Pekerjaan Sloof Beton (Besi 200kg + bekisting) m3 8.040 1,788,497
7 Pekerjaan Kolom Beton (Besi 300kg + bekisting) m3 5.760 4,509,332
8 Pekerjaan Balok Beton (Besi 200kg + bekisting) m3 8.040 3,833,480
9 Pekerjaan Plat Beton (Besi 150kg + bekisting) m3 10.530 3,772,881
10 Pekerjaan Ring Balok Beton (10x15cm) m1 8.040 25,737
Jumlah Total
Persentase (%)
Harga Satuan Jumlah Harga Jumlah
Upah Bahan Upah Bahan + Upah
F G=DxE H=DxF I=G+H
56,550 3,152,292 1,492,920 4,645,212
71,775 742,641 165,370 908,010
71,775 567,287 116,060 683,347
71,775 121,809 22,868 144,677
71,775 8,560 2,067 10,627
345,425 14,379,516 2,777,217 17,156,733
810,775 25,973,753 4,670,064 30,643,817
703,850 30,821,182 5,658,954 36,480,136
574,375 39,728,438 6,048,169 45,776,606
27,965 206,929 224,839 431,767
115,702,405 21,178,527 136,880,932
85% 15% 100%
Tabel IV.2 Volume Pekerjaan Dinding

1 Pasangan Bata Merah 1Bt (1 pc : 4 Ps)


Tinggi Panjang (m) Bukaan (m)
Volume (m2)
Dinding (m) Vertikal Kolom Pintu Rooster Jendela
A B C D= (AxB) - C
3.000 2.700 - - - 0.135 J2 = 2 0.700 7.265
3.000 1.350 - P3 1.720 - - - 2.330
3.000 1.350 - P3 1.720 - - - 2.330
3.000 1.350 - - - - - - 4.050
3.000 1.350 - - - 0.068 J2 = 1 0.350 3.632
3.000 1.850 - - - - - - 5.550
3.000 0.850 - - - - - - 2.550
Tinggi Panjang (m) Bukaan (m)
Dinding (m) Horizontal Kolom Pintu Rooster Jendela
A B C
3.000 1.350 - - - - - - 4.050
3.000 1.850 - - - - - - 5.550
3.000 2.550 - - - - - - 7.650
3.000 1.850 - P3 1.720 - - - 3.830
3.000 2.700 - - - - - - 8.100
3.000 2.850 - - 0.135 J1 1.553 6.862
Pasangan Bata Merah 1Bt (1 pc : 4 Ps) 63.750

2 Pasangan Bata Merah 1Bt (1 pc : 5 Ps)


Tinggi Panjang (m) Bukaan (m)
Volume (m2)
Dinding (m) Vertikal Kolom Pintu Rooster Jendela
A B C D= (AxB) - C
3.000 2.850 - - - 0.135 J1 1.553 6.862
3.000 2.350 - - - 0.068 J3 0.805 6.177
3.000 2.850 - P2 1.935 0.068 - - 6.547
3.000 3.700 - P2 1.935 0.068 - - 9.097
3.000 1.700 - P2 1.935 0.068 - - 3.097
3.000 3.050 - - - - - - 9.150
3.000 3.050 - - - - - - 9.150
3.000 0.850 - - - - - - 2.550
3.000 2.850 - - - 0.068 J3 0.805 7.677
3.000 1.850 - - - - - - 5.550
Tinggi Panjang (m) Bukaan (m)
Dinding (m) Horizontal Kolom Pintu Rooster Jendela
A B C
3.000 9.475 - - - - - - 28.425
3.000 2.850 - - - - - - 8.550
3.000 0.850 - - - - - - 2.550
3.000 0.850 - - - - - - 2.550
3.000 5.700 - - - 0.270 J1 3.105 13.725
3.000 2.850 - - - 0.135 J1 1.553 6.862
3.000 3.350 - KP5 2.795 0.338 KP5 3.413 3.505
3.000 2.350 - - - - - - 7.050
3.000 4.350 - 0.203 J4 2.300 10.547
Pasangan Bata Merah 1Bt (1 pc : 5 Ps) 149.623

3 Dinding Keramik 20x20


Tinggi Panjang (m) Bukaan (m)
Volume (m2)
Dinding (m) Vertikal Kolom Pintu Rooster Jendela
A B C D= (AxB) - C
3.000 1.350 - - - 0.068 B 0.350 3.632
3.000 1.350 - - - 0.068 B 0.350 3.632
3.000 1.350 - P3 1.720 - - - 2.330
3.000 1.350 - P3 1.720 - - - 2.330
3.000 1.350 - - - - - - 4.050
3.000 1.350 - - - 0.068 B 0.350 3.632
Tinggi Panjang (m) Bukaan (m)
Dinding (m) Horizontal Kolom Pintu Rooster Jendela
A B C
3.000 1.850 - - - - - - 5.550
3.000 1.700 - - - - - - 5.100
3.000 1.350 - - - - - - 4.050
3.000 1.850 - P3 1.720 - - - 3.830
3.000 1.850 - - - - - - 5.550
Dinding Keramik 20x20 43.687
4 Dinding Keramik 20x25
Tinggi Panjang (m) Bukaan (m)
Volume (m2)
Dinding (m) Vertikal Kolom Pintu Rooster Jendela
A B C D= (AxB) - C
2.150 0.925 - - - - - - 1.989
2.150 0.925 - - - - - - 1.989
Tinggi Panjang (m) Bukaan (m)
Dinding (m) Horizontal Kolom Pintu Rooster Jendela
A B C
2.150 2.850 - - - 0.135 J1 1.553 4.440
Dinding Keramik 20x25 8.417
Tabel IV.3 Rencana Anggaran Biaya Pekerjaan Dinding

Harga Satuan Jumlah Harga Jumlah


No. Uraian Jenis Pekerjaan Sat. Vol.
Bahan Upah Bahan Upah Bahan + Upah
A B C D E F G=DxE H=DxF I=G+H
1 Pasangan Bata Merah 1Bt (1 pc : 4 Ps) m2 63.750 130,274 56,450 8,304,870 3,598,659 11,903,530
2 Pasangan Bata Merah 1Bt (1 pc : 5 Ps) m2 149.623 125,964 56,450 18,847,099 8,446,213 27,293,312
3 Dinding Keramik 20x20 m2 43.687 130,711 78,925 5,710,398 3,448,012 9,158,410
4 Dinding Keramik 20x25 m2 8.417 133,891 9,788 1,127,001 82,384 1,209,385
5 Plesteran tebal= 2cm (1 pc : 4 Ps) m2 75.395 14,886 43,690 1,122,353 3,293,986 4,416,338
6 Plesteran tebal= 2cm (1 pc : 5 Ps) m2 299.246 13,503 43,690 4,040,788 13,074,049 17,114,837
7 Acian m2 374.640 4,128 30,300 1,546,328 11,351,601 12,897,929
Jumlah Total 40,698,836 43,294,904 83,993,741
Persentase (%) 48% 52% 100%
Tabel V.1 Analisa Harga Satuan Pekerjaan Penutup Lantai

1 m2 Lantai Ubin Granit (uk. = 40x40 cm)


1 Ubin Granit 6.630 bh
2 Semen PC (50 Kg) 9.800 zak
3 Pasir Pasang 0.045 m3
4 Semen Warna 10 kg
a Pekerja 0.250 Org/Hari
b Tukang Batu Kasar 0.125 Org/Hari
c Kepala Tukang 0.013 Org/Hari
d Mandor 0.013 Org/Hari

1 m2 Lantai Ubin Tralux Marmer (uk. = 40x40 cm)


1 Ubin Marmer 6.630 bh
2 Semen PC (50 Kg) 9.800 zak
3 Pasir Pasang 0.045 m3
4 Semen Warna 10 kg
a Pekerja 0.250 Org/Hari
b Tukang Batu Kasar 0.125 Org/Hari
c Kepala Tukang 0.013 Org/Hari
d Mandor 0.013 Org/Hari

1 m2 Lantai Keramik Mozaik (uk. = 30x30 cm) mozaik


1 Keramik Lantai 30/30 cm Polished 1.068 m2
2 Semen PC (50 Kg) 0.283 zak
3 Pasir Pasang 0.039 m3
4 Semen Warna 2.000 kg
a Pekerja 0.700 Org/Hari
b Tukang Batu Kasar 0.350 Org/Hari
c Kepala Tukang 0.035 Org/Hari
d Mandor 0.035 Org/Hari

1 m3 Urugan Pasir
1 Pasir Urug 1.050 m3
a Pekerja 0.300 Org/Hari
b Mandor 0.010 Org/Hari

1 m2 Lantai Kayu Gymfloor


1 Lantai Parquette 1.050 m2
2 Lem Kayu 0.600 Kg
a Pekerja 0.700 Org/Hari
b Tukang Batu Kasar 0.350 Org/Hari
c Kepala Tukang 0.035 Org/Hari
d Mandor 0.035 Org/Hari

JUMLAH BAHAN DAN UPAH DI


JUMLAH BAHAN DAN UPAH DI
rjaan Penutup Lantai

249,000 1,650,870
63,500 622,300
135,000 6,075
12,500 125,000
60,000 15,000
80,000 10,000
80,000 1,040
95,000 1,235
JUMLAH 2,431,520

200,000 1,326,000
63,500 622,300
135,000 6,075
12,500 125,000
60,000 15,000
80,000 10,000
80,000 1,040
95,000 1,235
JUMLAH 2,106,650

cm) mozaik (SNI:7395:2008-6.38)


80,000 85,464
63,500 17,971
135,000 5,265
12,500 25,000
60,000 42,000
80,000 28,000
80,000 2,800
95,000 3,325
JUMLAH 209,825

(SNI:2835:2008-6.11)
100,000 105,000
60,000 18,000
95,000 950
JUMLAH 123,950

(SNI:2837:2008-6.47)
600,000 630,000
62,500 37,500
60,000 42,000
80,000 28,000
80,000 2,800
95,000 3,325
JUMLAH 743,625
AH BAHAN DAN UPAH DI AHS BAB V 5,615,570
AH BAHAN DAN UPAH DI RAB BAB V 4,871,945
KONTROL NO
Tabel V.2 Volume Pekerjaan Penutup Lantai

No Lokasi Jenis Penutup Lantai Panjang (m)

1 WC 1 Lantai Keramik Mozaik 1.5


2 WC 2 Lantai Keramik Mozaik 1.5
3 WC 3 Lantai Keramik Mozaik 1.3
4 Teras 1 Lantai Ubin Tralux Marmer 3.8
5 Teras 2 Lantai Ubin Tralux Marmer 1.5
7 Balkon 1 Lantai Ubin Granit 3
8 R. Tidur 1 Lantai Ubin Granit 3
9 R. Tidur 2 Lantai Ubin Granit 4
10 R. Tidur 3 Lantai Ubin Granit 2.93

11 R. Makan Lantai Ubin Granit 5.9

12 R. tamu Lantai Ubin Granit 3


13

Jumlah Volume Keseluruhan Penutup Lantai

Volume Penutup Lantai (m3) Tinggi Urugan Pasir (m)


82.011 0.05
Pekerjaan Penutup Lantai

Jumlah Volume Per-


Lebar (m) Volume (m2)
Jenis Penutup Lantai
1.5 2.25
4.5
1.5 2.25
2 2.6
4 15.2 19.3
1 1.5
1 3
4 12
4 16
2.7 7.911
58.211
2 11.8

2.5 7.5

ntai 82.011

Tinggi Urugan Pasir (m) Volume Urugan Pasir


0.05 4.10055
Tabel V.3 Rencana Anggaran Biaya Pekerjaan Penutup Lantai

Harga Satuan
No. Uraian Jenis Pekerjaan Sat. Vol.
Bahan Upah
A B C D E F
1 Lantai Ubin Granit m2 91.200 2,404,245 27,275
2 Lantai Ubin Tralux Marmer m2 8.650 2,079,375 27,275
3 Lantai Keramik Mozaik m2 4.500 133,700 76,125
5 Urugan Pasir m2 4.101 105,000 18,950
Jumlah Total
Persentase (%)
Penutup Lantai

Jumlah Harga Jumlah


Bahan Upah Bahan + Upah
G=DxE H=DxF I=G+H
219,267,144 2,487,480 221,754,624
17,986,594 235,929 18,222,523
601,648 342,563 944,210
430,558 77,705 508,263
238,285,943 3,143,677 241,429,620
99% 1% 100%
Tabel VI.1 Analisa Harga Satuan Pekerjaan Kusen

1 m3 Membuat & memasang kusen pintu & jendela Kayu kelas I (SNI:3434:2008-
1 Kayu Kuat klas I 1.100 m3 16,000,000
2 Paku 8 s/d 12 cm 1.250 kg 36,000
3 Lem Kayu 1.000 Kg 62,500
a Pekerja 7.000 Org/Hari 60,000
b Tukang Kayu Halus 21.000 Org/Hari 80,000
c Kepala Tukang 2.100 Org/Hari 80,000
d Mandor 0.350 Org/Hari 95,000
JUMLAH
1 m2 Membuat & memasang daun pintu Panel Kayu kelas I (SNI:3434:2008-
1 Kayu Kuat klas I 0.0400 m3 16,000,000
2 Lem Kayu 0.5000 Kg 62,500
a Pekerja 1.0000 Org/Hari 60,000
b Tukang Kayu Halus 3.0000 Org/Hari 80,000
c Kepala Tukang 0.3000 Org/Hari 80,000
d Mandor 0.0500 Org/Hari 95,000
JUMLAH
1 m2 Pengadaan dan pemasangan jendela nako & tralis (SNI:7393:2008-6
1 Kaca nako t.6 mm + rangka 1.1000 m2 75,000
2 Paku Skrup 0.1000 Kg 20,000
2 Plat Strip 7.0000 Kg 14,690
a Pekerja 0.2000 Org/Hari 60,000
b Tukang Kayu Halus 0.2000 Org/Hari 80,000
c Kepala Tukang 0.0200 Org/Hari 80,000
d Mandor 0.0010 Org/Hari 95,000
JUMLAH
1 m2 Pengadaan dan pemasangan pintu lipat plastik/PVC (folding door) (SNI:7393:2008-
1 Folding Door PVC 1.0000 m2 592,800
a Pekerja 0.4400 Org/Hari 60,000
b Tukang Kayu Halus 0.4400 Org/Hari 80,000
c Kepala Tukang 0.0440 Org/Hari 80,000
d Mandor 0.0220 Org/Hari 95,000
JUMLAH
(SNI:3434:2008-6.1)
17,600,000
45,000
62,500
420,000
1,680,000
168,000
33,250
20,008,750
(SNI:3434:2008-6.5)
640,000
31,250
60,000
240,000
24,000
4,750
1,000,000
(SNI:7393:2008-6.17)
82,500
2,000
102,828
12,000
16,000
1,600
95
217,023
(SNI:7393:2008-6.8)
592,800
26,400
35,200
3,520
2,090
660,010
Tabel VI.2 Volume Pekerjaan Penutup Lantai

VOLUME KUSEN PINTU DAN JENDELA

No Kode Jenis Pintu dan Jendela Tokasi Tinggi Tebal


A B C D E F

1 P1 PINTU UTAMA (PINTU DOUBLE) RUANG TAMU 5.4 0.05

R.TIDUR(3) R.MAKAN(1)
2 P2 PINTU KAMAR DAPUR(1) DAN 5.4 0.05
GUDANG(1)
3 J JENDELA RUANG TAMU RUANG TAMU 9.15 0.05
R.S,G (1) R.TIDUR(3)
4 J1 JENDELA BOUBLE 6.55 0.05
DAPUR(1)
5 J2 BOVENLIGT KM/CW 2.8 0.05
6 J3 JENDELA SINGLE R.TIDUR(2) 4.1 0.05
7 J4 JENDELA TRIPEL R.MAKAN 9 0.05
No Kode ROSSTER Tokasi Tinggi Tebal
A B C D E F
1 P1 PINTU UTAMA (PINTU DOUBLE) RUANG TAMU 1.04 0.05
R.TIDUR(3) R.MAKAN(1)
2 P2 PINTU KAMAR DAPUR(1) DAN 1.04 0.05
GUDANG(1)
3 J JENDELA RUANG TAMU RUANG TAMU 1.04 0.05
R.S,G (1) R.TIDUR(3)
4 J1 JENDELA BOUBLE 1.04 0.05
DAPUR(1)
5 J3 JENDELA SINGLE R.TIDUR(2) 1.04 0.05
6 J4 JENDELA TRIPEL R.MAKAN 1.04 0.05
JUMLAH VOLUME KUSEN

8 P3 PVC KM/CW 3.000

VOLUME DAUN PINTU

No Kode Jenis Pintu Tokasi Tinggi Lebar


A B C D E F
1 P1 PINTU UTAMA (PINTU DOUBLE) RUANG TAMU 2.11 1.22
R.TIDUR(3) R.MAKAN(1)
2 P2 PINTU KAMAR DAPUR(1) DAN 2.11 0.82
GUDANG(1)
JUMLAH VOLUME DAUN PINTU
No Kode Jenis Jendela Tokasi Tinggi Lebar
A B C D E G
1 J JENDELA RUANG TAMU RUANG TAMU 1.65 1.8
R.S,G (1) R.TIDUR(3)
2 J1 JENDELA BOUBLE 1.05 1.2
DAPUR(1)
3 J2 BOVENLIGT KM/CW 0.4 0.6
4 J3 JENDELA SINGLE R.TIDUR(2) 1.05 0.5
5 J4 JENDELA TRIPEL R.MAKAN 1.05 1.8
JUMLAH VOLUME
tup Lantai

Lebar Jumlah VOLUME


G H I=E*F*G*H

0.15 1 0.041

0.15 6 0.243

0.15 1 0.069

0.15 5 0.246

0.15 3 0.063
0.15 2 0.062
0.15 1 0.068
Lebar Jumlah VOLUME
G H I=E*F*G*H
0.15 4 0.031

0.15 24 0.187

0.15 3 0.023
0.15 10 0.078
0.15 2 0.016
0.15 3 0.023
1.149

Jumlah VOLUME
G H=E*F*G
1 2.574

6 10.381

12.955
Jumlah VOLUME
H H=E*F*G
1 2.970
5 6.300
3 0.720
2 1.050
1 1.890
12.930
No. Uraian Jenis Pekerjaan Sat. Vol.
A B C D
1 Membuat & memasang kusen pintu & jendela Kayu kelas I m3 1.149
2 Membuat & memasang daun pintu Panel Kayu kelas I m2 12.955
3 Pengadaan dan pemasangan jendela nako & tralis m2 12.930
4 Pengadaan dan pemasangan pintu lipat plastik/PVC (folding door) m2 3.000
Jumlah Total
Persentase (%)
Harga Satuan Jumlah Harga Jumlah
Bahan Upah Bahan Upah Bahan + Upah
E F G=DxE H=DxF I=G+H
17,707,500 2,301,250 20,337,949 2,643,101 22,981,050
671,250 328,750 8,696,312 4,259,088 12,955,400
187,328 29,695 2,422,146 383,956 2,806,102
592,800 67,210 1,778,400 201,630 1,980,030
33,234,807 7,487,775 40,722,582
82% 18% 100%
I.3. PEKERJAAN RANGKA PLAFOND

1 m2 Membuat & memasang rangka plafond (50x100cm), Kayu kelas II


1 Kaso kelas II 0.0154 m3
2 Paku 4 s/d 7 cm 0.2000 kg
a Pekerja 0.1500 Org/Hari
b Tukang Kayu Halus 0.3000 Org/Hari
c Kepala Tukang 0.0300 Org/Hari
d Mandor 0.0750 Org/Hari

2 m2 Membuat & memasang rangka plafond (60x60cm), Kayu kelas II


1 Kaso kelas II 0.0154 m3
2 Paku 4 s/d 7 cm 0.2000 kg
a Pekerja 0.1500 Org/Hari
b Tukang Kayu Halus 0.3000 Org/Hari
c Kepala Tukang 0.0300 Org/Hari
d Mandor 0.0750 Org/Hari
00cm), Kayu kelas II (SNI:3434:2008-6.19)
9,500,000 146,300
36,000 7,200
60,000 9,000
80,000 24,000
80,000 2,400
95,000 7,125
JUMLAH 196,025

0cm), Kayu kelas II (SNI:3434:2008-6.20)


9,500,000 146,300
36,000 7,200
60,000 9,000
80,000 24,000
80,000 2,400
95,000 7,125
JUMLAH 196,025
No Lokasi Panjang (m) Lebar (m) Volume (m2)
1 WC 1 1.5 1.5 2.25
2 WC 2 1.5 1.5 2.25
3 Teras 1 1 3 3
4 Teras 2 1.5 1 1.5
5 Balkon 1 4.15 4.15
7 Dapur 2 1.5 3
8 R. Tidur 1 3 3 9
9 R. Tidur 2 3 2.5 7.5
10 R. Tidur 3 3 2.5 7.5
11 R. Tidur 4 3 3 9
R. Keluarga 1 3.5 5.85 20.475
11 R. Keluarga 2 3.5 5.85 20.475
11 R. Makan 1.5 3.5 5.25
12 R. Tamu 3 3 9

Jumlah Volume Keseluruhan Penutup Lantai 104.35


No. Uraian Jenis Pekerjaan Sat.
A B C
1 Membuat & memasang rangka plafond (50x100cm), Kayu kelas II m2
2 Membuat & memasang rangka plafond (60x60cm), Kayu kelas II m2
Jumlah Total
Persentase (%)
Harga Satuan Jumlah Harga
Vol.
Bahan Upah Bahan Upah
D E F G=DxE H=DxF
104.350 153,500 42,525 16,017,725 4,437,484
104.350 153,500 42,525 16,017,725 4,437,484
32,035,450 8,874,968
) 78% 22%
Jumlah
Bahan + Upah
I=G+H
20,455,209
20,455,209
40,910,418
100%
1 m2 Pengadaan dan pemasangan Atap Genteng Palentong Super/besar
1 Genteng Palentong Super 12.0000 Bh 11,000
a Pekerja 0.1500 Org/Hari 60,000
b Tukang Kayu Kasar 0.0600 Org/Hari 80,000
c Kepala Tukang 0.0060 Org/Hari 80,000
d Mandor 0.0080 Org/Hari 95,000
JUMLAH
uper/besar
132,000
9,000
4,800
480
760
147,040
VOLUME ATAP

P L V
5.5 10 110
No. Uraian Jenis Pekerjaan Sat. Vol.
A B C D
1 Pengadaan dan pemasangan Atap Genteng Palentong Super/besar m2 110.000
Jumlah Total
Persentase (%)
Harga Satuan Jumlah Harga
Bahan Upah Bahan Upah
E F G=DxE H=DxF
132,000 15,040 14,520,000 1,654,400
14,520,000 1,654,400
90% 10%
Jumlah
Bahan + Upah
I=G+H
16,174,400