JADWAL WAKTU PELAKSANAAN

PROGRAM : REHABILITASI GEDUNG KANTOR


LOKASI :
TAHUN ANGGARAN : 2019

BOBOT JANGKA WAKTU PELAKSANAAN 90 HARI KALENDER


NO URAIAN PEKERJAAN MINGGU KE I MINGGU KE II MINGGU KE III MINGGU KE IV
(%) 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4

1 PEKERJAAN PERSIAPAN 0,072 0,072


2 REHAB TERAS DAN PINTU UTAMA 10,406 2,602 2,602 2,602 2,602
3 REHAB LANTAI 35,522 7,104 7,104 7,104 7,104 7,104
4 REHAB JENDELA 16,558 4,139 4,139 4,139 4,139
5 PEKERJAAN PLAFOND, PARTISI DAN INSTALASI LISTRIK 14,252 3,563 3,563 3,563 3,563
6 PEKERJAAN BATU ALAM DAN PENGECATAN DINDING 23,189 5,797 5,797 5,797 5,797

KEMAJUAN FISIK PEKERJAAN TIAP MINGGU 0,072 2,602 2,602 2,602 9,706 7,104 11,244 11,244 14,807 7,703 3,563 3,563 5,797 5,797 5,797 5,797
KEMAJUAN FISIK PEKERJAAN TIAP BULAN 0,072 2,674 5,275 7,877 17,583 24,687 35,931 47,175 61,982 69,685 73,248 76,811 82,608 88,405 94,203 100,000
JUMLAH BOBOT PEKERJAAN 100,0

CV. PILAR UTAMA

ARKY NUGRAHA
TEAM LEADER