Satuan Harga (Rp) (Rp) A TENAGA Pekerja L.01 OH 0.24 165,000 39,600 Tukang Batu L.02 OH 0.12 180,000 21,600 Kepala tukang L.03 OH 0.012 190,000 2,280 Mandor L.04 OH 0.012 200,000 2,400 JUMLAH TENAGA KERJA 65,880 B BAHAN Keramik 60x60 Bh 3.1 57,000 176,700 Semen Portland Kg 10 1,300 13,000 Pasir pasang m3 0.045 148,400 6,678 Semen warna Kg 1.5 5,000 7,500 JUMLAH HARGA BAHAN 203,878 C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) 269,758
E Overhead & Profit (15%) 15% x D 40,464 F Harga Satuan Pekerjaan (D+E) 310,222