BILL OF QUANTITY (BOQ) TOTAL REKAP

KEGIATAN : PEMBANGUNAN, REHABILITASI DAN RENOVASI SARANA PRASARANA INFRASTRUKTUR PERGURUAN TINGGI NEGERI
PEKERJAAN : PEMBANGUNAN GEDUNG AKUNTANSI, TEKNIK INFORMASI, TEKNIK SIPIL POLITEKNIK NEGERI SAMARINDA
LOKASI : KOTA SAMARINDA

NO URAIAN PEKERJAAN HARGA PEKERJAAN (Rp) JUMLAH HARGA (Rp)

1 2 3 4
BAGIAN I GEDUNG AKUTANSI
I PEKERJAAN PENDAHULUAN 92,040,000.00
KESELAMATAN DAN KESEHATAN KERJA (K3) 92,040,000.00
II PEKERJAAN ARSITEKTUR 162,277,251,325.40
A PEKERJAAN PASANGAN DINDING 160,555,595,854.00
B PEKERJAAN PINTU/ JENDELA -
C PEKERJAAN LANTAI 834,223,940.00
D PEKERJAAN PLAFOND 58,294,668.00
E PEKERJAAN FINISHING -
F PEKERJAAN ATAP KANOPI -
G PEKERJAAN SANITAIR 10,400,740.00
H PEKERJAAN HALAMAN 818,736,123.40
III PEKERJAAN MEKANIKAL 7,696,920.00
A PEKERJAAN INSTALASI AIR BERSIH -
B PEK. INSTALASI AIR BUANGAN, AIR KOTOR & AIR HUJAN -
C PEKERJAAN INSTALASI AIR CONDITIONING (AC) -
D PEKERJAAN INSTALASI EXHAUST FAN -
E PEKERJAAN INSTALASI APAR (PEMADAM KEBAKARAN) -
F PEKERJAAN RESAPAN AIR BEKAS 7,696,920.00
IV PEKERJAAN ELEKTRIKAL -
A PEKERJAAN LANTAI - 2 (elevasi + 4,77) -
B PEKERJAAN LANTAI - 3 (Elevasi + 8,77) -
C PEKERJAAN LANTAI ATAP/ RL Elevasi + 12,77 -
TOTAL GEDUNG AKUTANSI 162,376,988,245.40
BAGIAN II GEDUNG TEKNIK SIPIL
I PEKERJAAN PENDAHULUAN - -
II PEK. PEMATANGAN LAHAN DAN TURAP 270,096,163.20 270,096,163.20
III PEKERJAAN SUB STRUKTUR. 645,680,142.40 645,680,142.40
IV PEKERJAAN UPPER STRUKTUR 3,396,981,681.00 3,396,981,681.00
V PEKERJAAN RANGKA KUDA - KUDA DAN ATAP - -
VI PEKERJAAN ARSITEKTUR 3,575,060,754.80
A PEKERJAAN PASANGAN DINDING 2,427,289,397.00
B PEKERJAAN PINTU/ JENDELA -
C PEKERJAAN LANTAI 1,146,490,288.80
D PEKERJAAN PLAFOND -
E PEKERJAAN FINISHING -
F PEKERJAAN SANITAIR 1,281,069.00
VII PEKERJAAN JEMBATAN PENGHUBUNG 472,168,812.63
A PEKERJAAN SUB STRUKTUR. 986,572.80
B PEKERJAAN UPPER STRUKTUR 328,943,319.83
C PEKERJAAN PASANGAN DINDING 75,527,320.00
D PEKERJAAN LANTAI 66,711,600.00
E PEKERJAAN FINISHING -
VIII PEKERJAAN HALAMAN DAN TAMAN 296,824,412.80 296,824,412.80
IX PEKERJAAN MEKANIKAL 260,040.00
A PEKERJAAN INSTALASI AIR BERSIH -
B PEK. INSTALASI AIR BUANGAN, AIR KOTOR & AIR HUJAN 260,040.00
C PEKERJAAN INSTALASI AIR CONDITIONING (AC) -
D PEKERJAAN INSTALASI APAR (PEMADAM KEBAKARAN) -
E PEKERJAAN INSTALASI EXHAUST FAN -
F PEKERJAAN INSTALASI FIRE ALARM -
X PEKERJAAN ELEKTRIKAL -
A PEKERJAAN LANTAI 1 (Elev. - 4.00) -
B PEKERJAAN LANTAI 2 (Elev. ± 0.00) -
C PEKERJAAN LANTAI - 3 (Elev. ± 4.00) -
D PEKERJAAN LANTAI ATAP /PETIR -
XI KESELAMATAN DAN KESEHATAN KERJA (K3) - -

TOTAL GEDUNG SIPIL 8,657,072,006.83


NO URAIAN PEKERJAAN HARGA PEKERJAAN (Rp) JUMLAH HARGA (Rp)

1 2 3 4
BAGIAN III GEDUNG TEKNIK INFORMASI (TI)
A PEKERJAAN PERSIAPAN (K3) 91,315,000.00
KESELAMATAN DAN KESEHATAN KERJA (K3) 91,315,000.00
B PEKERJAAN STRUKTUR CORE LIFT 153,526,395.40
I Pekerjaan Galian dan Urugan 914,732.00
II Pekerjaan Struktur Pondasi, Beton dan Baja 152,611,663.40
III Pekerjaan Rangka Atap & Talang -
C PEKERJAAN ARSITEKTUR
I PEKERJAAN PASANGAN & DINDING 572,670,168.00
I.1 Pekerjaan Lantai - 1 1,727,460.00
I.2 Pekerjaan Lantai - 2 15,130,629.00
I.3 Pekerjaan Lantai - 3 189,506,026.00
I.4 Pekerjaan Lantai - 4 254,610,273.00
I.5 Pekerjaan Lantai - RL 111,695,780.00
II PEKERJAAN KUSEN, PINTU & JENDELA ALUMINIUM -
II.1 Pekerjaan Lantai - 1 -
II.2 Pekerjaan Lantai - 2 -
II.3 Pekerjaan Lantai - 3 -
II.4 Pekerjaan Lantai - 4 -
II.5 Pekerjaan Lantai - RL -
III PEKERJAAN LANTAI 157,215,859.00
III.1 Pekerjaan Lantai - 1 20,165,202.00
III.2 Pekerjaan Lantai - 2 14,523,799.00
III.3 Pekerjaan Lantai - 3 61,263,429.00
III.4 Pekerjaan Lantai - 4. 61,263,429.00
III.5 Pekerjaan Lantai - RL. -
IV PEKERJAAN PLAFOND 13,462,496.00
IV.1 Pekerjaan Lantai - 1 -
IV.2 Pekerjaan Lantai - 2 6,731,248.00
IV.3 Pekerjaan Lantai - 3 -
IV.4 Pekerjaan Lantai - 4 6,731,248.00
V PEKERJAAN SANITAIR -
V.1 Pekerjaan Lantai - 1 -
V.2 Pekerjaan Lantai - 2 -
V.3 Pekerjaan Lantai - 3 -
V.4 Pekerjaan Lantai - 4 -
V.5 Pekerjaan Lantai - RL. -
VI PEKERJAAN PENGECATAN / FINISHING -
VI.1 Pekerjaan Lantai - 1 -
VI.2 Pekerjaan Lantai - 2 -
VI.3 Pekerjaan Lantai - 3 -
VI.4 Pekerjaan Lantai - 4 -
VI.5 Pekerjaan Lantai - RL. -
VII PEKERJAAN ATAP - -
VIII PEKERJAAN RAILLING 32,777,868.00 32,777,868.00
IX PEKERJAAN LAIN - LAIN 4,324,847.00 4,324,847.00
X PEKERJAAN BANGUNAN LIFT 60,642,508.00 60,642,508.00
XI PEKERJAAN GROUND TANK, RUMAH GENSET DAN RUANG POMPA 119,541,587.60
XI.1 Pekerjaan Ground Tank 29,014,920.80
XI.2 Pekerjaan Rumah Genset dan Ruang Pompa 90,526,666.80
D PEKERJAAN ELEKTRIKAL
I PEKERJAAN ELEKTRIKAL GEDUNG -
I.1 Pekerjaan Lantai - 1 -
I.2 Pekerjaan Lantai - 2 -
I.3 Pekerjaan Lantai - 3 -
I.4 Pekerjaan Lantai - 4 -
I.5 Pekerjaan Lantai - RL. -
II PEKERJAAN PENANGKAL PETIR - -
III PEKERJAAN JARINGAN LAN -
III.1 Pekerjaan Lantai - 1 -
III.2 Pekerjaan Lantai - 2 -
III.3 Pekerjaan Lantai - 3 -
III.4 Pekerjaan Lantai - 4 -
NO URAIAN PEKERJAAN HARGA PEKERJAAN (Rp) JUMLAH HARGA (Rp)

1 2 3 4
E PEKERJAAN MEKANIKAL
I INSTALASI AIR BERSIH -
I.1 Pekerjaan Lantai - 1 -
I.2 Pekerjaan Lantai - 2 -
I.3 Pekerjaan Lantai - 3 -
I.4 Pekerjaan Lantai - 4 -
I.5 Pekerjaan Lantai -Atap dan Shaft -
II INSTALASI AIR KOTOR 29,498,208.00
II.1 Pekerjaan Lantai - 1 29,498,208.00
II.2 Pekerjaan Lantai - 2 -
II.3 Pekerjaan Lantai - 3 -
II.4 Pekerjaan Lantai - 4 -
II.5 Pekerjaan Lantai - RL. -
III PEKERJAAN TATA UDARA -
III.2 Pekerjaan Lantai - 2 -
III.3 Pekerjaan Lantai - 3 -
III.4 Pekerjaan Lantai - 4 -
IV PEKERJAAN PEMADAM KEBAKARAN - -
V PEKERJAAN LIFT ELEVATOR - -

TOTAL GEDUNG TEKNIK INFORMASI 1,234,974,937.00

JUMLAH GEDUNG AKUNTANSI, TEKNIK INFORMASI, TEKNIK SIPIL 172,269,035,189.23

PPN 10% 17,226,903,518.92

JUMLAH TOTAL GEDUNG AKUNTANSI, TEKNIK INFORMASI, TEKNIK SIPIL 189,495,938,708.16

PEMBULATAN 189,495,938,000.00

Terbilang : Seratus Delapan Puluh Sembilan Milyar Empat Ratus Sembilan Puluh Lima Juta Sembilan Ratus Tiga Puluh Delapan Ribu Rupiah

Jakarta, 15 November 2019


Penawar,
PT. JUMINDO INDAH PERKASA

JUNAIDIN
Direktur
BILL OF QUANTITY (BOQ) SUB REKAP
GEDUNG AKUNTANSI

KEGIATAN : PEMBANGUNAN, REHABILITASI DAN RENOVASI SARANA PRASARANA INFRASTRUKTUR PERGURUAN TINGGI NEGERI
PEKERJAAN : PEMBANGUNAN GEDUNG AKUNTANSI, TEKNIK INFORMASI, TEKNIK SIPIL POLITEKNIK NEGERI SAMARINDA
LOKASI : KOTA SAMARINDA

HARGA PEKERJAAN
NO URAIAN PEKERJAAN JUMLAH HARGA (Rp)
(Rp)
1 2 3 4

BAGIAN I GEDUNG AKUTANSI


I PEKERJAAN PENDAHULUAN 92,040,000.00
KESELAMATAN DAN KESEHATAN KERJA (K3) 92,040,000.00
II PEKERJAAN ARSITEKTUR 162,277,251,325.40
A PEKERJAAN PASANGAN DINDING 160,555,595,854.00
B PEKERJAAN PINTU/ JENDELA -
C PEKERJAAN LANTAI 834,223,940.00
D PEKERJAAN PLAFOND 58,294,668.00
E PEKERJAAN FINISHING -
F PEKERJAAN ATAP KANOPI -
G PEKERJAAN SANITAIR 10,400,740.00
H PEKERJAAN HALAMAN 818,736,123.40
III PEKERJAAN MEKANIKAL 7,696,920.00
A PEKERJAAN INSTALASI AIR BERSIH -
B PEK. INSTALASI AIR BUANGAN, AIR KOTOR & AIR HUJAN -
C PEKERJAAN INSTALASI AIR CONDITIONING (AC) -
D PEKERJAAN INSTALASI EXHAUST FAN -
E PEKERJAAN INSTALASI APAR (PEMADAM KEBAKARAN) -
F PEKERJAAN RESAPAN AIR BEKAS 7,696,920.00
IV PEKERJAAN ELEKTRIKAL -
A PEKERJAAN LANTAI - 2 (elevasi + 4,77) -
B PEKERJAAN LANTAI - 3 (Elevasi + 8,77) -
C PEKERJAAN LANTAI ATAP/ RL Elevasi + 12,77 -

TOTAL GEDUNG AKUTANSI 162,376,988,245.40


BILL OF QUANTITY (BOQ)
GEDUNG AKUNTANSI
KEGIATAN : PEMBANGUNAN, REHABILITASI DAN RENOVASI SARANA PRASARANA INFRASTRUKTUR PERGURUAN TINGGI NEGERI
PEKERJAAN : PEMBANGUNAN GEDUNG AKUNTANSI, TEKNIK INFORMASI, TEKNIK SIPIL POLITEKNIK NEGERI SAMARINDA
LOKASI : KOTA SAMARINDA

PERHITUNGAN BIAYA KESELAMATAN DAN KESEHATAN KERJA


NO ITEM PEKERJAAN UNIT VOLUME HARGA SATUAN (Rp) TOTAL HARGA (Rp)

1 2 3 4 6 7

I PEKERJAAN PENDAHULUAN
1 Penyiapan RK3K Terdiri atas
a Pembuatan manual prosedur, instruksi kerja
dan ijin kerja Ls 1.00 1,000,000.00 1,000,000.00
b Pembuatan Kartu Identitas Pekerja (KIP) Org 30.00 5,000.00 150,000.00
2 Sosialisasidan Promosi K3 terdiri atas : -
a Spanduk (banner) Lb 1.00 100,000.00 100,000.00
b Poster Lb 1.00 100,000.00 100,000.00
c Papan Informasi K3 Bh 1.00 100,000.00 100,000.00
3 Alat Pelindung Kerja terdiri atas : -
a Jaring Pengaman + Pemasangan ls 1.00 2,500,000.00 2,500,000.00
b Tali Keselamatan (lifeline) + Acesories Ls 1.00 3,000,000.00 3,000,000.00
c Pagar Pengaman (guard railling) Ls 1.00 15,000,000.00 15,000,000.00
d Pembatas Area Ls 1.00 1,500,000.00 1,500,000.00
4 Alat Pelindung Diri terdiri atas : -
a Topi Perlindungan Bh 30.00 40,000.00 1,200,000.00
b Pelindung Mata Psg 30.00 15,000.00 450,000.00
c Pelindung Pernapasan dan Mulut (Masker) Psg 30.00 5,000.00 150,000.00
d Sarung Tangan (Kulit, Katun dan Karet) Psg 30.00 8,000.00 240,000.00
e Sepatu Keselamatan Psg 30.00 125,000.00 3,750,000.00
f Rompi Keselamatan (Safety Vest) Psg 30.00 50,000.00 1,500,000.00
5 Asuransi dan Perijinan terdiri atas : -
a BPJS Ketenaga Kerjaandan esehatan Kerja, -
(Berdasarkan Kepmenaker No. Kep. 196/MEN/ -
1999, untuk Tenaga harian proyek Ls 1.00 4,750,000.00 4,750,000.00
6 Personil K3 terdiri atas : -
a Ahli K3 OB 4.00 7,550,000.00 30,200,000.00
c Petugas P3K Ob 4.00 3,500,000.00 14,000,000.00
7 Pasilitas sarana Kesehatan -
a Peralatan P3K (Kotak P3K , Tandu, Tabung Ls 1.00 5,000,000.00 5,000,000.00
Oksigen, Obat Luka, Perban dll. -
8 Rambu - Rambu terdiri atas : -
a Rambu Petunjuk Bh 2.00 650,000.00 1,300,000.00
b RambuLarangan Bh 2.00 650,000.00 1,300,000.00
c Rambu Peringatan Bh 2.00 650,000.00 1,300,000.00
d Rambu Kewajiban Bh 2.00 650,000.00 1,300,000.00
e Rambu Informasi Bh 2.00 650,000.00 1,300,000.00
9 Lain -Lain Terkait Pengendalian ResikoK3 -
a Bendera K3 Bh 1.00 650,000.00 650,000.00
b APAR Bh 1.00 200,000.00 200,000.00
TOTAL 92,040,000.00
BILL OF QUANTITY
GEDUNG AKUNTANSI

KEGIATAN : PEMBANGUNAN, REHABILITASI DAN RENOVASI SARANA PRASARANA INFRASTRUKTUR PERGURUAN TINGGI NEGERI
PEKERJAAN : PEMBANGUNAN GEDUNG AKUNTANSI, TEKNIK INFORMASI, TEKNIK SIPIL POLITEKNIK NEGERI SAMARINDA
LOKASI : KOTA SAMARINDA

NO URAIAN PEKERJAAN SAT. VOLUME HARGA SATUAN (Rp) JUMLAH HARGA (Rp) TOTAL HARGA (Rp)

1 2 3 4 5 6 7
II PEKERJAAN ARSITEKTUR
A. PEKERJAAN PASANGAN DINDING
- Lantai Besment (Elevasi - 3,23)
1 Railing Tangga Stainless Steel M' 12.00 - -
Jumlah -

- Lantai 1 (Elevasi + 0, 77)


1 Pemasangan Acian M² 507.13 56,300.00 28,551,419.00
2 Railing Tangga Stainless Steel M' 45.00 - -
Jumlah 28,551,419.00
- Lantai 2 (Elevasi + 4, 77)
1 Pemasangan Acian Batu Bata M² 1,792.53 56,300.00 100,919,439.00
2 Pemasangan Acian Bata Ringan M² 140.28 - -
3 Kolom Praktis 11/11 M' 10.00 71,100.00 711,000.00
4 Balok Latai 11/15 M' 100.20 98,600.00 9,879,720.00
5 Pemasangan dinding HB10 campuran 1PC:4PP M² 70.14 371,000.00 26,021,940.00
6 Pemasangan plesteran 1PC:4PP tebal 10 mm M² 140.28 88,700.00 12,442,836.00
7 Pek. Pipa Stainless Steel Ø 2,5" M' 50.10 - -
8 Railing Tangga Stainless Steel M' 54.00 - -
Jumlah 149,974,935.00
- Lantai 3 (Elevasi + 8, 77)
1 Kolom Praktis 11/11 M' 464.00 71,100.00 5,055,210,000.00
2 Balok Latai 11/15 M' 105.75 98,600.00 9,721,960,000.00
3 Pemasangan dinding HB10 campuran 1PC:4PP M² 1,114.99 371,000.00 137,641,000,000.00
4 Pemasangan plesteran 1PC:4PP tebal 10 mm M² 2,229.99 88,700.00 7,867,690,000.00
5 Pemasangan Acian Bata Ringan M² 2,291.99 - -
7 Railing Tangga Stainless Steel M' 54.00 - -
Jumlah 160,285,860,000.00
- RL.1 roof tank (Elevasi +12,77)
1 Kolom Praktis 11/11 M' 7.00 71,100.00 497,700.00
2 Balok Latai 11/15 M' 19.00 98,600.00 1,873,400.00
3 Pemasangan dinding HB10 campuran 1PC:3PP M² 134.40 371,000.00 49,862,400.00
4 Pemasangan plesteran 1PC:4PP tebal 20 mm M² 268.80 88,700.00 23,842,560.00
5 Pemasangan Acian M² 268.80 56,300.00 15,133,440.00
Jumlah 91,209,500.00
TOTAL : II.A. PEKERJAAN PASANGAN 160,555,595,854.00
B PEKERJAAN PINTU/ JENDELA
- Lantai 1 (Elevasi + 0, 77)
1 PEK. PINTU TYPE P9. uk 85 x 190 CM
- Pekerjaan Kusen Alumunium M' 4.65 - -
- Daun Pintu Type P9 Spandrell aluminium M² 1.62 - -
- Kunci Pintu Bh 1.00 - -
- Engsel Pintu Bh 3.00 - -
Jumlah -
- Lantai 2 (Elevasi + 4, 77)
1 PEK. PINTU TYPE P2.UK.155 x 250 CM ( 2 unit)
- Pekerjaan Kusen Alumunium M' 16.84 - -
- Daun Pintu Alumunium + Kaca 5 mm M² 6.13 - -
- Kaca 5 mm M² 1.58 - -
- Kunci Pintu Bh 2.00 - -
- Engsel Pintu Bh 12.00 - -
- Espagnollete Tanam Bh 2.00 - -
- Finis Duco Milamin M² 12.26 - -
- Door Closer Bh 4.00 - -
NO URAIAN PEKERJAAN SAT. VOLUME HARGA SATUAN (Rp) JUMLAH HARGA (Rp) TOTAL HARGA (Rp)

1 2 3 4 5 6 7

2 PEK. PINTU TYPE P4. uk 130 x 250 CM (9 Unit)


- Pekerjaan Kusen Alumunium M' 71.10 - -
- Daun Pintu Double Teakwood M² 20.88 - -
- Kaca 5 mm M² 5.98 - -
- Kunci Pintu Bh 9.00 - -
- Engsel Pintu Bh 54.00 - -
- Espagnollete Tanam Bh 9.00 - -
- Finis Duco Milamin M² 41.76 - -
- Door Closer Bh 18.00 - -

3 PEK. PINTU TYPE P7. uk 85 x 205 CM (6 Unit)


- Pekerjaan Kusen Alumunium M' 28.80 - -
- Daun Pintu Double Teakwood M² 9.60 - -
- Kunci Pintu Bh 6.00 - -
- Engsel Pintu Bh 18.00 - -
- Finis Duco Milamin M² 19.20 - -

4 PEK. PINTU TYPE P9. uk 85 x 190 CM (9 unit)


- Pekerjaan Kusen Alumunium M' 41.85 - -
- Daun Pintu Type P9 Spandrell aluminium M² 14.54 - -
- Kunci Pintu Bh 9.00 - -
- Engsel Pintu Bh 27.00 - -

5 PEK. PINTU TYPE PS. Uk 75 x 110 CM (3 unit)


- Pekerjaan Kusen Alumunium M' 11.10 - -
- Daun Pintu Type P9 Spandrell aluminium M² 2.48 - -
- Kunci Pintu Bh 3.00 - -
- Engsel Pintu Bh 6.00 - -

6 PEK. PINTU TYPE PJ3. uk 325 x260 CM (1 unit)


- Pekerjaan Kusen Alumunium M' 20.70 - -
- Daun Pintu Double Teakwood M² 2.32 - -
- Kaca 5 mm M² 4.51 - -
- Espagnollete Tanam Bh 1.00 - -
- Kunci Pintu Bh 1.00 - -
- Engsel Pintu Bh 6.00 - -
- Finis Duco Milamin M² 4.64 - -
- Door Closer Bh 1.00 - -

7 PEK. JENDELA TYPE J1a. Uk 180 x 180 CM (32 Unit)


- Pekerjaan Kusen Alumunium M' 460.80 - -
- Jendela Type Alumunium + Kaca 5 mm M² 30.72 - -
- Kaca 5 mm M² 56.32 - -
- Engsel Jendela Bh 128.00 - -
- Handle Jendela Bh 64.00 - -
- Kaitan Angin Bh 128.00 - -
- Grendel Jendela Bh 128.00 - -

8 PEK. JENDELA TYPE J3. Uk 70 x 150 CM (2 Unit)


- Pekerjaan Kusen Alumunium M' 11.20 - -
- Jendela Type Alumunium + Kaca 5 mm M² 1.68 - -
- Kaca 5 mm M² 0.56 - -
- Engsel Jendela Bh 4.00 - -
- Handle Jendela Bh 4.00 - -
- Kaitan Angin Bh 4.00 - -
- Grendel Jendela Bh 4.00 - -

8 PEK. JENDELA TYPE J4. Uk 200 x 195 CM (2 unit)


- Pekerjaan Kusen Alumunium M' 23.40 - -
- Kaca 5 mm M² 6.66 - -
NO URAIAN PEKERJAAN SAT. VOLUME HARGA SATUAN (Rp) JUMLAH HARGA (Rp) TOTAL HARGA (Rp)

1 2 3 4 5 6 7
9 PEK. JENDELA TYPE J5a. Uk 200 x 120 CM (1 unit)
- Pekerjaan Kusen Alumunium M' 9.95 - -
- Kaca 5 mm M² 1.44 - -

10 PEK. JENDELA TYPE J5b. Uk 265 x 120 CM (1 unit)


- Pekerjaan Kusen Alumunium M' 12.95 - -
- Kaca 5 mm M² 1.92 - -

11 PEK. JENDELA TYPE J6. Uk 265 x 135 CM (3 unit)


- Pekerjaan Kusen Alumunium M' 34.65 - -
- Kaca 5 mm M² 2.25 - -

12 PEK. JENDELA TYPE J8. Uk 176 x 120 CM (2 Unit)


- Pekerjaan Kusen Alumunium M' 13.64 - -
- Kaca 5 mm Rayband M² 3.52 - -

13 PEK. JENDELA TYPE J9'. Uk 40 x 130 CM (2 Unit)


- Pekerjaan Kusen Alumunium M' 6.40 - -
- Kaca 5 mm Rayband M² 0.72 - -

14 PEK. JENDELA TYPE J10. Uk 60 x 130 CM (2 Unit)


- Pekerjaan Kusen Alumunium M' 31.00 - -
- Kaca 5 mm Rayband M² 6.23 - -

15 PEK. JENDELA TYPE BV. uk 60 x 50 CM (18 Unit)


- Pekerjaan Kusen Alumunium M' 36.00 - -
- Kaca 5 mm M² 3.15 - -

16 PEK. JENDELA TYPE BV1. UK 60 X 70 CM (6 Unit)


- Pekerjaan Kusen Alumunium M' 14.76 - -
- Kaca 5 mm M² 1.59 - -
17 PEK. JENDELA TYPE BV2. uk 200 x 50 CM (24 Unit)
- Pekerjaan Kusen Alumunium M' 134.40 - -
- Kaca 5 mm M² 5.76 - -

Jumlah -
- Lantai 3 (Elevasi + 8, 77)
1 PEK. PINTU TYPE P1a. 155 x 220 CM (1 Unit)
- Daun Pintu Kaca Tempered 12mm M² 3.41 - -
- Floor Hinge Bh 2.00 - -
- Pull Handle Bh 2.00 - -
- Patch Fitting Bh 1.00 - -
- Bottom pivot patch Bh 2.00 - -
- Top pivot patch Bh 2.00 - -

2 PEK. PINTU TYPE P2.UK.155 x 250 CM (1 Unit)


- Pekerjaan Kusen Alumunium M' 8.42 - -
- Daun Pintu Alumunium + Kaca 5 mm M² 3.05 - -
- Kaca 5 mm M² 0.79 - -
- Kunci Pintu Bh 1.00 - -
- Engsel Pintu Bh 6.00 - -
- Espagnollete Tanam Bh 1.00 - -
- Door Closer Bh 2.00 - -

3 PEK. PINTU TYPE P2a. uk 156 x 250 CM (2 Unit)


- Pekerjaan Kusen Alumunium M' 16.84 - -
- Daun Pintu Double Teakwood M² 5.29 - -
- Kaca 5 mm M² 1.92 - -
- Kunci Pintu Bh 2.00 - -
- Engsel Pintu Bh 12.00 - -
- Espagnollete Tanam Bh 2.00 - -
- Finis Duco Milamin M² 10.58 - -
- Door Closer Bh 4.00 - -
NO URAIAN PEKERJAAN SAT. VOLUME HARGA SATUAN (Rp) JUMLAH HARGA (Rp) TOTAL HARGA (Rp)

1 2 3 4 5 6 7
4 PEK. PINTU TYPE P3. uk 200 x 240 CM (2 Unit)
- Pekerjaan Kusen Alumunium M' 15.00 - -
- Daun Pintu Panel M² 11.20 - -
- Kaca 5 mm M² 1.18 - -
- Kunci Pintu Bh 2.00 - -
- Engsel tanam Bh 8.00 - -
- Espagnollete Tanam Bh 4.00 - -
- Finis Duco Milamin M² 22.40 - -
- Door Closer Bh 4.00 - -

5 PEK. PINTU TYPE P3a. uk 100 x 240 CM (2 Unit)


- Pekerjaan Kusen Alumunium M' 13.00 - -
- Daun Pintu Panel M² 5.01 - -
- Kaca 5 mm M² 0.59 - -
- Kunci Pintu Bh 2.00 - -
- Engsel tanam Bh 4.00 - -
- Espagnollete Tanam Bh 2.00 - -
- Finis Duco Milamin M² 10.02 - -
- Door Closer Bh 2.00 - -

6 PEK. PINTU TYPE P4. uk 130 x 250 CM (1 Unit)


- Pekerjaan Kusen Alumunium M' 7.90 - -
- Daun Pintu Double Teakwood M² 2.32 - -
- Kaca 5 mm M² 0.66 - -
- Kunci Pintu Bh 1.00 - -
- Engsel Pintu Bh 6.00 - -
- Espagnollete Tanam Bh 1.00 - -
- Finis Duco Milamin M² 4.64 - -
- Door Closer Bh 1.00 - -

7 PEK. PINTU TYPE P5. uk 130 x 215 CM (1 Unit)


- Pekerjaan Kusen Alumunium M' 5.60 - -
- Daun Pintu Double Teakwood M² 0.66 - -
- Kaca 5 mm M² 0.20 - -
- Kunci Pintu Bh 1.00 - -
- Engsel Pintu Bh 6.00 - -
- Espagnollete Tanam Bh 1.00 - -
- Finis Duco Milamin M² 1.33 - -
- Door Closer Bh 1.00 - -

8 PEK. PINTU TYPE P7. uk 85 x 205 CM (8 Unit)


- Pekerjaan Kusen Alumunium M' 38.40 - -
- Daun Pintu Double Teakwood M² 12.80 - -
- Kunci Pintu Bh 8.00 - -
- Engsel Pintu Bh 24.00 - -
- Finis Duco Milamin M² 25.60 - -

9 PEK. PINTU TYPE P9. uk 85 x 190 CM (8 Unit)


- Pekerjaan Kusen Alumunium M' 37.20 - -
- Daun Pintu Type P9 Spandrell aluminium M² 12.92 - -
- Kunci Pintu Bh 8.00 - -
- Engsel Pintu Bh 24.00 - -

10 PEK. PINTU TYPE PS. Uk 75 x 110 CM (3 Unit)


- Pekerjaan Kusen Alumunium M' 11.10 - -
- Daun Pintu Type P9 Spandrell aluminium M² 2.48 - -
- Kunci Pintu Bh 3.00 - -
- Engsel Pintu Bh 6.00 - -
NO URAIAN PEKERJAAN SAT. VOLUME HARGA SATUAN (Rp) JUMLAH HARGA (Rp) TOTAL HARGA (Rp)

1 2 3 4 5 6 7
11 PEK. PINTU TYPE PJ3. uk 325 x260 CM (2 Unit)
- Pekerjaan Kusen Alumunium M' 41.40 - -
- Daun Pintu Double Teakwood M² 5.04 - -
- Kaca 5 mm M² 9.02 - -
- Espagnollete Tanam Bh 2.00 - -
- Kunci Pintu Bh 2.00 - -
- Engsel Pintu Bh 12.00 - -
- Lapisan Sunblast M² 5.04 - -
- Finis Duco Milamin M² 10.08 - -
- Door Closer Bh 2.00 - -

12 PEK. PINTU TYPE PJ4. uk 195 x 260 CM (4 Unit)


- Pekerjaan Kusen Alumunium M' 51.60 - -
- Daun Pintu Double Teakwood M² 9.28 - -
- Kaca 5 mm M² 18.84 - -
- Espagnollete Tanam Bh 4.00 - -
- Kunci Pintu Bh 4.00 - -
- Engsel Pintu Bh 24.00 - -
- Lapisan Sunblast M² 3.36 - -
- Finis Duco Milamin M² 18.56 - -
- Door Closer Bh 4.00 - -

13 PEK. PINTU TYPE PJ5. uk 122 x 220 CM (1 Unit)


- Pekerjaan Kusen Alumunium M' 10.33 - -
- Daun Pintu Kaca Tempered 12mm M² 1.80 - -
- Floor Hinge Bh 2.00 - -
- Pull Handle Bh 1.00 - -
- Patch Fitting Bh 2.00 - -
- Kaca 5 mm M² 0.39 - -

14 PEK. JENDELA TYPE J1b. Uk 180 x 106 CM (10 Unit)


- Pekerjaan Kusen Alumunium M' 96.40 - -
- Jendela Type Alumunium + Kaca 5 mm M² 6.00 - -
- Kaca 5 mm M² 9.20 - -
- Engsel Jendela Bh 40.00 - -
- Handle Jendela Bh 20.00 - -
- Kaitan Angin Bh 40.00 - -
- Grendel Jendela Bh 40.00 - -

15 PEK. JENDELA TYPE J1c. Uk 180 x 150 CM (28 Unit)


- Pekerjaan Kusen Alumunium M' 341.60 - -
- Jendela Type Alumunium + Kaca 5 mm M² 33.60 - -
- Kaca 5 mm M² 34.44 - -
- Engsel Jendela Bh 112.00 - -
- Handle Jendela Bh 56.00 - -
- Kaitan Angin Bh 112.00 - -
- Grendel Jendela Bh 112.00 - -

16 PEK. JENDELA TYPE J2a. Uk 135 x 180 CM (8 Unit)


- Pekerjaan Kusen Alumunium M' 57.60 - -
- Jendela Type Alumunium + Kaca 5 mm M² 9.60 - -
- Kaca 5 mm M² 3.84 - -
- Engsel Jendela Bh 32.00 - -
- Handle Jendela Bh 16.00 - -
- Kaitan Angin Bh 32.00 - -
- Grendel Jendela Bh 32.00 - -
NO URAIAN PEKERJAAN SAT. VOLUME HARGA SATUAN (Rp) JUMLAH HARGA (Rp) TOTAL HARGA (Rp)

1 2 3 4 5 6 7
17 PEK. JENDELA TYPE J3a. Uk 80 x 155 CM (2 Unit)
- Pekerjaan Kusen Alumunium M' 9.60 - -
- Jendela Type Alumunium + Kaca 5 mm M² 1.20 - -
- Kaca 5 mm M² 0.48 - -
- Engsel Jendela Bh 4.00 - -
- Handle Jendela Bh 2.00 - -
- Kaitan Angin Bh 4.00 - -
- Grendel Jendela Bh 4.00 - -

18 PEK. JENDELA TYPE J4. Uk 200 x 195 CM (14 Unit)


- Pekerjaan Kusen Alumunium M' 163.80 - -
- Kaca 5 mm M² 46.62 - -
- Lapisan Sunblast M² 11.76 - -

19 PEK. JENDELA TYPE J9'. Uk 40 x 130 CM (4 Unit)


- Pekerjaan Kusen Alumunium M' 12.80 - -
- Kaca 5 mm Rayband M² 1.44 - -

20 PEK. JENDELA TYPE J10. Uk 80 x 140 CM (2 Unit)


- Pekerjaan Kusen Alumunium M' 31.00 - -
- Kaca 5 mm Rayband M² 6.23 - -

21 PEK. JENDELA TYPE J11. Uk 120 x 120 CM (6 Unit)


- Pekerjaan Kusen Alumunium M' 27.60 - -
- Kaca 5 mm Rayband M² 6.72 - -

22 PEK. JENDELA TYPE BV. uk 60 x 50 CM (18 Unit)


- Pekerjaan Kusen Alumunium M' 36.00 - -
- Kaca 5 mmRayband M² 3.15 - -

23 PEK. JENDELA CURTAINWALL. Uk 8.05 x 5.75 CM (1 Unit)


- Pekerjaan Kusen Alumunium M' 96.10 - -
- Kaca 8 mm M² 14.75 - -

Jumlah -
- RL.1 Roof Tank (Elevasi + 12,77)
1 PEK. PINTU TYPE P4. uk 130x250 CM (2 Unit)
- Pekerjaan Kusen Alumunium M' 15.80 - -
- Daun Pintu Double Teakwood M² 5.20 - -
- Kaca 5 m M² 0.93 - -
- Kunci Pintu Bh 2.00 - -
- Engsel Pintu Bh 12.00 - -
- Espagnollete Tanam Bh 2.00 - -
- Finis Duco Milamin M² 10.40 - -
- Door Closer Bh 4.00 - -
Jumlah -
TOTAL : II. B. PEKERJAAN PINTU & JENDELA -
C. PEKERJAAN LANTAI
- Lantai Besment (Elevasi - 3,23)
1 Keramik Tangga 30/60 + (Granite Tile) M² 24.00 341,200.00 8,188,800.00
Jumlah 8,188,800.00
- Lantai 1 (Elevasi + 0, 77)
1 Keramik Tangga 30/60 + (Granite Tile) M² 41.19 341,200.00 14,054,028.00
Jumlah 14,054,028.00
NO URAIAN PEKERJAAN SAT. VOLUME HARGA SATUAN (Rp) JUMLAH HARGA (Rp) TOTAL HARGA (Rp)

1 2 3 4 5 6 7
- Lantai 2 (Elevasi + 4, 77)
1 Keramik Lantai 60/60 (Homogenus Tile) M² 843.06 411,800.00 347,172,108.00
2 Keramik Lantai 30/30 Km/Wc M² 69.53 282,100.00 19,614,413.00
3 Keramik Dinding Km/Wc M² 168.68 - -
4 Keramik Tangga 30/60 + (Granite Tile) M² 41.19 341,200.00 14,054,028.00
Jumlah 380,840,549.00
- Lantai 3 (Elevasi + 8, 77)
1 Keramik Lantai 60/60 (Homogenus Tile) M² 871.90 411,800.00 359,048,420.00
2 Keramik Lantai 30/30 Km/Wc M² 59.63 282,100.00 16,821,623.00
3 Keramik Dinding 20/25 Km/Wc M² 132.02 343,600.00 45,362,072.00
4 Keramik Tangga 30/60 + (Granite Tile) M² 29.04 341,200.00 9,908,448.00
Jumlah 431,140,563.00
TOTAL : II.C. PEKERJAAN LANTAI 834,223,940.00
D. PEKERJAAN PLAFOND
- Lantai Besment (Elevasi - 3,23)
1 Pas. Plafond Gypsum t 9 mm M² 58.05 - -
2 Pas. List Profil Gypsum Standart Lebar Sampai 5-10cm M' 38.00 32,600.00 1,238,800.00
Jumlah 1,238,800.00
- Lantai 2 (Elevasi + 4, 77)
1 Pas. Rangka Plafond Hollow M² 912.58 - -
2 Pas. Plafond Gypsum t 9 mm M² 693.06 - -
3 Plafond Calsiboard 4.5 mm M² 69.53 - -
4 List Plafond Gipsum Standart M' 781.78 32,600.00 25,486,028.00
Jumlah 25,486,028.00
- Lantai 3 (Elevasi + 8, 77)
1 Pas. Rangka Plafond Hollow M² 1,156.73 - -
2 Pas. Plafond Gypsum t 9 mm M² 870.74 - -
3 Plafond Calsiboard 4.5 mm M² 285.99 - -
4 List Plafond Gypsum Standart M' 901.40 32,600.00 29,385,640.00
Jumlah 29,385,640.00
- RL.1 Roof Tank (Elevasi + 12,77)
1 Pas. Rangka Plafond Hollow M² 252.90 - -
2 Plafond Calsiboard 4.5 mm M² 252.90 - -
3 List Plafond Kayu Profil M² 67.00 32,600.00 2,184,200.00
Jumlah 2,184,200.00
TOTAL : II.D. PEKERJAAN PLAFOND 58,294,668.00
E. PEKERJAAN FINISHING
- Lantai Besment (Elevasi - 3,23)
1 Cat Tembok Luar M² 207.71 - -
2 Cat Plafond M² 58.05 - -
Jumlah -
- Lantai 1 (Elevasi + 0, 77)
1 Cat Tembok Luar M² 507.13 - -
Jumlah -
- Lantai 2 (Elevasi + 4, 77)
1 Cat Tembok Luar M² 552.34 - -
2 Cat Tembok Dalam M² 1,190.19 - -
3 Cat Plafond M² 912.58 - -
Jumlah -
- Lantai 3 (Elevasi + 8, 77)
1 Cat Tembok Luar M² 428.00 - -
2 Cat Tembok Dalam M² 1,863.99 - -
3 Cat Plafond M² 1,156.73 - -
Jumlah -
- RL.1 roof tank (Elevasi +12,77)
1 Cat Tembok Luar M² 92.98 - -
2 Cat Tembok Dalam M² 175.77 - -
3 Cat Plafond M² 252.90 - -
4 Cat Listplank M² 71.63 - -
Jumlah -
TOTAL : II. E. PEKERJAAN FINISHING -
NO URAIAN PEKERJAAN SAT. VOLUME HARGA SATUAN (Rp) JUMLAH HARGA (Rp) TOTAL HARGA (Rp)

1 2 3 4 5 6 7
PEKERJAAN ATAP KANOPI
F.
- Lantai 1 (Elevasi + 0, 77)
1 Rangka Atap Besi Kotak 5/10 dan 5/5 M² 28.62 - -
2 Atap Spandek M² 28.62 - -
Jumlah -
TOTAL : II. F. PEKERJAAN ATAP KANOPI -
G. PEKERJAAN SANITAIR
- Lantai 1 (Elevasi + 0, 77)
1 Railing Disabilitas (besi stainless Steel Ø 2 " ) M' 6.20 - -
2 Dinding Partisi (rangka Hollow, GRC 9 mm) M² 4.80 - -
Jumlah -
- Lantai 2 (Elevasi + 4, 77)
1 Kloset Duduk Unit 5.00 - -
2 kloset Jongkok Unit 4.00 - -
3 Meja Wastafel Beton
- Pembesian kg 53.87 7,600.00 409,412.00
- begesting M² 5.99 418,100.00 2,504,419.00
- Plat Beton K175 Tbl 10 cm M³ 0.60 994,600.00 596,760.00
- Pas. Keramik 30x30 M² 5.99 282,100.00 1,689,779.00
4 Satu Wastafel+Kran+Instalasi Unit 1.00 - -
5 Dua Wastafel+Kran+Instalasi Unit 4.00 - -
6 Cermin 5 mm M² 3.78 - -
7 Kran air Jet washer + acsesories bh 9.00 - -
8 Kran Air bh 9.00 - -
9 Urinoir Unit 6.00 - -
10 Penyekat Urinoir bh 4.00 - -
11 Pemasangan Floor Drain bh 16.00 - -
Jumlah 5,200,370.00
- Lantai 3 (Elevasi + 8, 77)
1 Kloset Duduk Unit 4.00 - -
2 Kloset Jongkok Unit 4.00 - -
3 Meja Wastafel Beton
- Pembesian kg 53.87 7,600.00 409,412.00
- begesting M² 5.99 418,100.00 2,504,419.00
- Plat Beton K175 Tbl 10 cm M³ 0.60 994,600.00 596,760.00
- Pas. Keramik 30x30 M² 5.99 282,100.00 1,689,779.00
4 Satu Wastafel+Kran+Instalasi Unit 1.00 - -
5 Dua Wastafel+Kran+Instalasi Unit 4.00 - -
6 Cermin 5 mm M² 3.78 - -
7 Kran air Jet washer + acsesories bh 8.00 - -
8 Kran Air bh 8.00 - -
9 Urinoir Unit 6.00 - -
10 Penyekat Urinoir bh 4.00 - -
11 Pemasangan Floor Drain bh 13.00 - -
Jumlah 5,200,370.00
TOTAL : II. G. PEKERJAAN SANITAIR 10,400,740.00
H. PEKERJAAN HALAMAN
- Lantai 1 (Elevasi ± 0, 00)
1 Pekerjaan Selasar
- Galian Tanah M³ 2.91 85,640.00 249,212.40
- Pasangan Batu Gunung penahan tanah M³ 3.24 - -
- Pasangan Batu Bata 1 : 2 (selsara Gedung) M² 15.60 310,000.00 4,836,000.00
- Plesteran Pasangan M² 22.35 93,600.00 2,091,960.00
- Cor Rabat Selasar mutu fc 14,5 Mpa (K175) M³ 10.28 994,600.00 10,224,488.00
2 Pekerjaan Pengecoran Halaman
- Galian Tanah + Pembuangan M³ 40.86 142,340.00 5,816,012.40
- Pembesian kg 1,958.38 7,600.00 14,883,688.00
- Begesting M² 6.11 418,100.00 2,554,591.00
- Cor beton mutu fc 21,75 Mpa (K. 250) M³ 34.86 1,065,700.00 37,150,302.00
3 Pekerjaan Saluran Gedung
- Galian Tanah M³ 2.40 85,640.00 205,536.00
- Pasangan Batu Bata 1 : 2 (selsara Gedung) M² 12.00 310,000.00 3,720,000.00
- Plesteran Pasangan M² 12.00 93,600.00 1,123,200.00
- Cor Rabat Selasar mutu fc 14,5 Mpa (K175) M³ 0.63 994,600.00 626,598.00
- Pipa Pvc 4" M' 4.00 - -
NO URAIAN PEKERJAAN SAT. VOLUME HARGA SATUAN (Rp) JUMLAH HARGA (Rp) TOTAL HARGA (Rp)

1 2 3 4 5 6 7
4 Pembuatan Ramp Disabilitas
- Pembesian kg 75.60 7,600.00 574,560.00
- Begesting M² 4.00 418,100.00 1,672,400.00
- Cor Beton mutu fc 14,5 Mpa (K175) M³ 1.26 994,600.00 1,253,196.00
- Keramik Lantai 60/60 (unpolish Tile) M² 8.40 411,800.00 3,459,120.00
- Pasangan Guiding block M² 1.53 - -
- Railling Tangga Stainless Steel (disabilitas) M' 13.80 - -
Jumlah 90,440,863.80
- Lantai Besment (Elevasi - 3,23)
1 Pekerjaan Selasar
- Galian Tanah M³ 3.40 85,640.00 291,176.00
- Pasangan Batu Bata 1 : 2 (selasar Gedung) M² 34.00 310,000.00 10,540,000.00
- Plesteran Pasangan M² 34.00 93,600.00 3,182,400.00
- Cor Rabat Selasar mutu fc 14,5 Mpa (K175) M³ 8.50 994,600.00 8,454,100.00
2 Pekerjaan Saluran Gedung
- Galian Tanah M³ 7.84 85,640.00 671,417.60
- Pasangan Batu Bata 1 : 2 (selsara Gedung) M² 39.20 310,000.00 12,152,000.00
- Plesteran Pasangan M² 39.20 93,600.00 3,669,120.00
- Cor Beton Saluran mutu fc 14,5 Mpa (K175) M³ 6.86 994,600.00 6,822,956.00
3 Pekerjaan Halaman Parkir
- Urugan pasir t = 5cm M³ 49.61 174,400.00 8,651,984.00
- Cor Lantai Kerja mutu fc 7,4 Mpa (K100) t = 5 cm M³ 49.61 897,300.00 44,515,053.00
- Pembesian Kg 20,005.62 7,600.00 152,042,712.00
- Bekesting M² 505.20 418,100.00 211,224,120.00
- Cor beton mutu fc 26,4 Mpa (K300) M³ 218.99 1,100,800.00 241,064,192.00
- Kanstin Beton M' 104.53 239,300.00 25,014,029.00
Jumlah 728,295,259.60
TOTAL : II. H. PEKERJAAN HALAMAN 818,736,123.40
TOTAL : RAB ARSITEKTUR AKUTANSI 162,277,251,325.40

III. PEKERJAAN MEKANIKAL


A. PEKERJAAN INSTALASI AIR BERSIH
A.1 - Pekerjaan Intalasi Air Bersih Lantai 2 (Elev. ± 4.77)
1 Pipa PVC AW :
a. Pipa tegak PVC ø 3/4"(ke km/wc) m 29.40 - -
b. Pipa tegak PVC ø 1" mm (ke roof tank) m 88.00 - -
2 Fitting & aksesoris pipa GSP medium class ls 1.00 - -
Jumlah -
A.2 - Pekerjaan Intalasi Air Bersih Lantai 3 (Elev. ± 8,77)
1 Pipa PVC AW :
a. Pipa tegak PVC ø 3/4"(ke km/wc) m 29.40 - -
b. Pipa tegak PVC ø 1" mm (ke roof tank) m 84.00 - -
2 Fitting & aksesoris pipa GSP medium class ls 1.00 - -
Jumlah -
A.3 - Pekerjaan Instalasi Air Bersih Lantai RL (Elev. ± 12.77)
1 Pekerjaan instalasi tanki air (roof tank) :
a. Tanki air (roof tank) : unit 1.00 - -
Tipe/material
Kapasitas
b. Pipa venting tanki air :
- Pipa PVC AW class ø 40 mm, lengkap dengan insect screen m 1.50 - -
c. Mesin Pompa Air/Swage Pump (Komplit) unit 2.00 - -
Voltek : 1 x 220 kapaisitas 50 liter/detik daya dorong 36 m kw :
0,83
d. Fitting & aksesoris pipa PVC AW class ls 1.00 - -
2 Pipa PVC AW :
a. Pipa PVC AW ø 1,5" (bak penampungan ke Rppftank) m 71.00 - -
3 Fitting & aksesoris pipa GSP medium class ls 1.00 - -
Jumlah -
TOTAL : III. A. PEKERJAAN INSTALASI AIR BERSIH -
NO URAIAN PEKERJAAN SAT. VOLUME HARGA SATUAN (Rp) JUMLAH HARGA (Rp) TOTAL HARGA (Rp)

1 2 3 4 5 6 7

B. PEK. INSTALASI AIR BUANGAN, AIR KOTOR & AIR HUJAN


Pengadaan dan pemasangan instalasi air bekas, air kotor, air
hujan,
dan pipa ventilasinya dalam gedung berikut fixtures, fittings,
aksesoris, hanger & support dan perlengkapannya
beserta pengetesan sistem dan instalasi.
B.1 - Pekerjaan Inatalsi Air Buangan Lantai 2 (Elev. ± 4.77)
1 Pekerjaan instalasi air bekas :
a. Pipa uPVC class AW :
- Pipa uPVC class AW ø 2" m 52.00 - -
b. Fitting & aksesoris pipa uPVC class AW ls 1.00 - -
c. Fixture unit :
- Floor clean out :
~ Floor clean out ø 100 mm pcs 1.00 - -
2 Pekerjaan instalasi air kotor :
a. Pipa uPVC class AW :
- Pipa uPVC class AW ø 100 mm m 52.00 - -
b. Fitting & aksesoris pipa uPVC class AW ls 1.00 - -
Jumlah -

B.2 - Pekerjaan Intalasi Air Buangan Lantai 3 (Elev. ± 8.77)


1 Pekerjaan instalasi air bekas :
a. Pipa uPVC class AW :
- Pipa uPVC class AW ø 2" m 44.00 - -
b. Fitting & aksesoris pipa uPVC class AW ls 1.00 - -
c. Fixture unit :
- Floor clean out :
~ Floor clean out ø 100 mm pcs 1.00 - -
2 Pekerjaan instalasi air kotor :
a. Pipa uPVC class AW :
- Pipa uPVC class AW ø 100 mm m 44.00 - -
b. Fitting & aksesoris pipa uPVC class AW ls 1.00 - -
Jumlah -
TOTAL : III. B. PEKERJAAN INSTALASI AIR BUANGAN -

C. PEKERJAAN INSTALASI AIR CONDITIONING (AC)


Pengadaan dan pemasangan air conditioning (AC) lengkap dengan
kabel daya, refrigerant berisolasi, pipa drain (kondensat)
dan perlengkapannya beserta pengetesan sistem dan instalasi.
C.1 PEKERJAAN INSTALASI AIR CONDITIONING (AC)LT 2 DAN 3
1 AC wall mounted, single split system : 22.500 BTUH
Instalasi Air Conditioning (AC) Lt 2 dan Lt 3
a. Unit air conditioning (AC) : unit 5.00 - -
- Fan coil unit (FCU) : wall mounted, single split system
Tipe : 22.500 BTUH
Kapasitas : Ruang Senat Jurusan
Servis : FCU.1-01
Kode unit : lantai 2 dan lantai 3
Lokasi
- Condensing unit : 1100 W / 220 V / 1 Ph / 50 Hz
Konsumsi daya : CU.1-01
Kode unit : outdoor lantai 1
Lokasi
a. Pipa refrigerant m 300.00 - -
b. Instalasi kabel daya : NYM 3 x 2,5 mm2 m 768.00 - -
c. Instalasi pipa drain/kondensat AC :
- Pipa drain/kondensat AC ø 20 mm m 14.00 - -
d. Fitting & aksesoris pipa drain/kondensat AC ls 1.00 - -
NO URAIAN PEKERJAAN SAT. VOLUME HARGA SATUAN (Rp) JUMLAH HARGA (Rp) TOTAL HARGA (Rp)

1 2 3 4 5 6 7
2 AC wall mounted, single split system : 18.000 BTUH
Instalasi Air Conditioning (AC) Lt 2 dan Lt 3
a. Unit air conditioning (AC) : unit 28.00 - -
- Fan coil unit (FCU) : wall mounted, single split system
Tipe : 18.000 BTUH
Kapasitas : Ruang Senat Jurusan
Servis : FCU.1-02
Kode unit : lantai 2 dan lantai 3
Lokasi
- Condensing uni : 1100 W / 220 V / 1 Ph / 50 Hz
Konsumsi daya : CU.1-02
Kode unit : outdoor lantai 1
Lokasi
a. Pipa refrigerant m 30.00 - -
b. Instalasi kabel daya : NYM 3 x 2,5 mm2 m 68.00 - -
c. Instalasi pipa drain/kondensat AC :
- Pipa drain/kondensat AC ø 20 mm m 14.00 - -
d. Fitting & aksesoris pipa drain/kondensat AC ls 1.00 - -

3 AC wall mounted, single split system : 9.000 BTUH


Instalasi Air Conditioning (AC) Lt 2 dan Lt 3
a. Unit air conditioning (AC) : unit 4.00 - -
- Fan coil unit (FCU) : wall mounted, single split system
Tipe : 9.000 BTUH (2.200 Kcal)
Kapasitas : Ruang Sekretaris
Servis : FCU.1-03
Kode unit : lantai 1
Lokasi
- Condensing unit : 825 W / 220 V / 1 Ph / 50 Hz
Konsumsi daya : CU.1-03
Kode unit : outdoor lantai 1
Lokasi
a. Pipa refrigerant m 30.00 - -
b. Instalasi kabel daya : NYM 3 x 2,5 mm2 m 145.00 - -
c. Instalasi pipa drain/kondensat AC :
- Pipa drain/kondensat AC ø 20 mm m 50.00 - -
d. Fitting & aksesoris pipa drain/kondensat AC ls 1.00 - -
4 Testing & commissioning instalasi air conditioning (AC) lot 1.00 - -
TOTAL : III. C. PEKERJAAN INSTALASI AIR CONDITIONING (AC) -

D. PEKERJAAN INSTALASI EXHAUST FAN


Pengadaan dan pemasangan exhaust fan lengkap dengan kabel
daya
dan perlengkapannya beserta pengetesan sistem dan instalasi.

D.1 Pekerjaan Instalasi Exhaust Fan Lt.2


a. Unit exhaust fan : EFT-1.01A & 01B unit 13.00 0 -
Tipe : Propeller Wall Mounted
Kapasitas : 200 CMH
Static pressure : 5 Pa
Konsumsi daya : 55 W/ 220V/ 1 Ph / 50 Hz
Putaran : rpm
Servis : ruang toilet (as. Y-14' - Y-15')
Kode unit : EFT-1.01A & EFT-1.01B
b. Instalasi kabel daya : NYM 3 x 2,5 mm2 m 28.00 - -

D.2 Pekerjaan Instalasi Exhaust Fan Lt.3


a. Unit exhaust fan : EFT-1.03A & 03B unit 12.00 - -
Tipe : Propeller Wall Mounted
Kapasitas : 200 CMH
Static pressure : 5 Pa
Konsumsi daya : 55 W/ 220V/ 1 Ph / 50 Hz
Putaran : rpm
Servis : ruang toilet (as. Y-3' - Y-4')
Kode unit : EFT-1.03A & EFT-1.03B
b. Instalasi kabel daya : NYM 3 x 2,5 mm2 m 28.00 - -
D.3 Testing & commissioning instalasi ventilasi mekanik lot 1.00 - -
TOTAL : III. D. PEKERJAAN INSTALASI EXHAUFAN -
NO URAIAN PEKERJAAN SAT. VOLUME HARGA SATUAN (Rp) JUMLAH HARGA (Rp) TOTAL HARGA (Rp)

1 2 3 4 5 6 7

E. PEKERJAAN INSTALASI APAR (PEMADAM KEBAKARAN)


Pengadaan dan pemasangan Apar lengkap dengan
Tabung, Penggantung, serta MSDS (material safety data sheets)
dan perlengkapannya beserta pengetesan sistem dan instalasi.
E.1 - Lantai Basement (Elevasi - 3,23)
Jenis Apar Carbon dioxide/ C02 unit 4.00 - -
Tipe : Carbon Dioxide (CO2) Portable
Model : SV – 230 C
Berat : 2 kg
Kelas : BC (Minyak, Solar, Bensin, Elektronik dan Listrik)
E.2 - Lantai 1 (Elevasi + 0, 77)
Jenis Apar Carbon dioxide/ C02 unit 6.00 - -
Tipe : Carbon Dioxide (CO2) Portable
Model : SV – 230 C
Berat : 2,3 kg
Kelas : BC (Minyak, Solar, Bensin, Elektronik dan Listrik)
E.3 - Lantai 2 (Elevasi + 4, 77)
Jenis Apar Carbon dioxide/ C02 unit 6.00 - -
Tipe : Carbon Dioxide (CO2) Portable
Model : SV – 230 C
Berat : 2,3 kg
Kelas : BC (Minyak, Solar, Bensin, Elektronik dan Listrik)
E.4 - Lantai 3 (Elevasi + 8, 77)
Jenis Apar Carbon dioxide/ C02 unit 6.00 - -
Tipe : Carbon Dioxide (CO2) Portable
Model : SV – 230 C
Berat : 2,3 kg
Kelas : BC (Minyak, Solar, Bensin, Elektronik dan Listrik)
TOTAL : III. E. PEKERJAAN INSTALASI APAR (PEMADAM KEBAKARAN) -

F. PEKERJAAN RESAPAN AIR BEKAS


1 Galian tanah M³ 3.00 85,640.00 256,920.00
2 Pas. Batu Bata 1 : 2 M² 24.00 310,000.00 7,440,000.00
3 Plesteran Pas. Batu 1 : 2 M² 24.00 - -
4 Pekerjaan Grill Besi Ø 16 - l = 30 cm M' 25.50 - -
5 Instalsi pipa
- Pipa uPVC class AW ø 50 mm M' 18.00 - -
- Pipa uPVC class AW ø 100 mm + Saringan M' 12.00 - -
6 Material peresapan
- Pasir Pasang M³ 0.60 - -
- Koral M³ 0.60 - -
- Ijuk kg 9.00 - -
TOTAL : III. F. PEKERJAAN RESAPAN AIR BEKAS 7,696,920.00
TOTAL : RAB MEKANIKAL AKUTANSI 7,696,920.00

IV. PEKERJAAN ELEKTRIKAL


A. PEKERJAAN LANTAI - 2 (elevasi + 4,77)
1 Kabel Feeder
- dari PSD ke P-2, NYY 4x6 mm2 m 12.00 - -
2 Panel Hubung Bagi
- Panel P-3 unit 1.00 - -
- Panel AC unit 1.00 - -
3 Pencahayaan
- Lampu RM 300 Led 2 x 10 Watt Mirror Louvere bh 60.00 - -
- Lampu GMS TP Led 1 x 10 Watt Acrylic Cover bh 2.00 - -
- Lampu Down Light RD 145 E27 Led 1 x 5 Watt bh 48.00 - -
- Lampu Down Light RD 125 E27 Led 1 x 3 Watt bh 21.00 - -
- Lampu Keluar/Exit TL. 1x10 Watt. ACR. 2MK + NICAB bh 2.00 - -
- Saklar Tunggal 10A 250 VAC bh 12.00 - -
- Saklar Ganda 10A 250 VAC bh 28.00 - -
- Instalasi Penerangan Kabel Dalam Pipa Kondui uPVC titik 173.00 - -
NO URAIAN PEKERJAAN SAT. VOLUME HARGA SATUAN (Rp) JUMLAH HARGA (Rp) TOTAL HARGA (Rp)

1 2 3 4 5 6 7
4 Kotak Kontak
- Kotak Kontak Biasa 1 Fasa 15 A, 250 VAC bh 46.00 - -
- Kotak Kontak Ceiling1 Fasa 15 A, 250 VAC bh 8.00 - -
- Instalasi Penerangan Kabel Dalam Pipa Kondui uPVC titik 54.00 - -
5 LD PROYEKTOR
- LCD Proyectore (XGA 1024x 768 - 3000 lumean) bh 8.00 - -
- Tiang Penggantung LCD Otomatis unit 8.00 - -
- Instalasi Penerangan Kabel Dalam Pipa Kondul uPVC ttk 8.00 - -
- Kotak Kontak 1 Fasa 15 A 250 VAC bh 8.00 - -
- Kabel Data HDMI m 120.00 - -
- Autlet Data bh 8.00 - -
6 Test commisioning lantai - 2 (elevasi + 4,77) ls 1.00 - -
TOTAL : IV. A. PEKERJAAN LANTAI 2 -

B. PEKERJAAN LANTAI - 3 (Elevasi + 8,77)


1 Kabel Feeder
- dari PSD ke P-2, NYY 4x6 mm2 m 12.00 - -
2 Panel Hubung Bagi
;- Panel P-4 unit 1.00 - -
- Panel AC unit 1.00 - -
3 Pencahayaan
- Lampu RM 300 Led 2 x 10 Watt Mirror Louvere bh 61.00 - -
- Lampu GMS TP Led 1 x 10 Watt Acrylic Cover bh 23.00 - -
- Lampu Down Light RD 145 E27 Led 1 x 5 Watt bh 60.00 - -
- Lampu Down Light RD 125 E27 Led 1 x 3 Watt bh 22.00 - -
- Lampu Keluar/Exit TL. 1x10 Watt. ACR. 2MK + NICAB bh 2.00 - -
- Saklar Tunggal 10A 250 VAC bh 4.00 - -
- Saklar Ganda 10A 250 VAC bh 8.00 - -
- Instalasi penerangan kabel dalam pipa konducit uPVC titik 180.00 - -
4 Kotak Kontak
- Kotak Kontak Biasa 1 Fasa 15 A, 250 VAC bh 141.00 - -
- Kotak Kontak Ceiling1 Fasa 15 A, 250 VAC bh 5.00 - -
- Instalasi Penerangan Kabel Dalam Pipa Kondui uPVC titik 146.00 - -
5 LD PROYEKTOR
- LCD Proyectore (XGA 1024x 768 - 3000 lumean) bh 5.00 - -
- Tiang Penggantung LCD Otomatis unit 5.00 - -
- Kotak Kontak 1 Fasa 15 A 250 VAC bh 5.00 - -
- Instalasi Penerangan Kabel Dalam Pipa Kondul uPVC ttk 5.00 - -
- Kabel Data HDMI m 80.00 - -
- Autlet Data bh 5.00 - -
6 Test commisioning lantai - 3 (Elevasi + 8,77) ls 1.00 - -
TOTAL : IV. B. PEKERJAAN LANTAI 3 -

C. PEKERJAAN LANTAI ATAP/ RL Elevasi + 12,77


1 Kabel Feeder
- dari PSD ke P-2, NYY 4x6 mm2 m 12.00 - -
2 Pencahayaan
- Lampu Down Light RD 145 E27 Led 1 x 5 Watt bh 6.00 - -
- Saklar Ganda 10A 250 VAC bh 2.00 - -
- Instalasi penerangan kabel dalam pipa konducit uPVC titik 8.00 - -
3 Kotak Kontak
- Kotak Kontak Biasa 1 Fasa 15 A, 250 VAC bh 2.00 - -
- Instalasi Penerangan Kabel Dalam Pipa Kondui uPVC titik 2.00 - -
4 Test commisioning lantai - RL (Elevasi + 12,77) ls 1.00 - -
TOTAL : IV. C. PEKERJAAN LANTAI ATAP/RL -
TOTAL : RAB ELEKTRIKAL AKUTANSI -
BILL OF QUANTITY (BOQ) SUB REKAP
GEDUNG TEKNIK SIPIL

KEGIATAN : PEMBANGUNAN, REHABILITASI DAN RENOVASI SARANA PRASARANA INFRASTRUKTUR PERGURUAN TINGGI NEGERI
PEKERJAAN : PEMBANGUNAN GEDUNG AKUNTANSI, TEKNIK INFORMASI, TEKNIK SIPIL POLITEKNIK NEGERI SAMARINDA
LOKASI : KOTA SAMARINDA

NO URAIAN PEKERJAAN HARGA PEKERJAAN (Rp) JUMLAH HARGA (Rp)


1 2 3 4

I PEKERJAAN PENDAHULUAN - -

II PEK. PEMATANGAN LAHAN DAN TURAP 270,096,163.20 270,096,163.20

III PEKERJAAN SUB STRUKTUR 645,680,142.40 645,680,142.40

IV PEKERJAAN UPPER STRUKTUR 3,396,981,681.00


- Lantai 1 (Elv. - 4.00) 939,959,446.00
- Lantai 2 (Elevasi ± 0.00) 910,324,988.00
- Lantai 3 (Elevasi ± 4.00) 1,241,210,398.00
- RL. (Elevasi +7,80) 152,207,605.00
- RL.2 (Elevasi +9.51) 153,279,244.00

V PEKERJAAN RANGKA KUDA - KUDA DAN ATAP - -

VI PEKERJAAN ARSITEKTUR
A PEKERJAAN PASANGAN DINDING 2,427,289,397.00
- Lantai 1 (Elv. - 4.00) 740,164,766.00
- Lantai 2 (Elevasi ± 0.00) 794,174,889.00
- Lantai 3 (Elevasi ± 4.00) 806,000,922.00
- RL.1 (Elevasi +8,8.000) 86,948,820.00
B PEKERJAAN PINTU/ JENDELA -
- Lantai 1 (Elv. - 4.00) -
- Lantai 2 (Elevasi ± 0.00) -
- Lantai 3 (Elevasi ± 4.00) -
C PEKERJAAN LANTAI 1,146,490,288.80
- Lantai 1 (Elv. - 4.00) 426,044,685.60
- Lantai 2 (Elevasi ± 0.00) 364,294,149.60
- Lantai 3 (Elevasi ± 4.00) 356,151,453.60
D PEKERJAAN PLAFOND -
- Lantai 1 (Elv. - 4.00) -
- Lantai 2 (Elevasi ± 0.00) -
- Lantai 3 (Elevasi ± 4.00) -
- RL.1 (Elevasi +8,8.000) -
E PEKERJAAN FINISHING -
- Lantai 1 (Elv. - 4.00) -
- Lantai 2 (Elevasi ± 0.00) -
- Lantai 3 (Elevasi ± 4.00) -
- RL.1 (Elevasi +8,8.000) -
F PEKERJAAN SANITAIR 1,281,069.00
- Lantai 1 (Elv. - 4.00) 427,023.00
- Lantai 2 (Elevasi ± 0.00) 427,023.00
- Lantai 3 (Elevasi ± 4.00) 427,023.00
NO URAIAN PEKERJAAN HARGA PEKERJAAN (Rp) JUMLAH HARGA (Rp)
1 2 3 4

VII PEKERJAAN JEMBATAN PENGHUBUNG 472,168,812.63


A PEKERJAAN SUB STRUKTUR. 986,572.80
B PEKERJAAN UPPER STRUKTUR 328,943,319.83
C PEKERJAAN PASANGAN DINDING 75,527,320.00
D PEKERJAAN LANTAI 66,711,600.00
E PEKERJAAN FINISHING -

VIII PEKERJAAN HALAMAN DAN TAMAN 296,824,412.80


A Pekerjaan Halaman/Jalan 275,340,973.00
B Pekerjaan Ramp Disabilitas 18,824,703.00
D Pekerjaan Tangga Darurat 2,658,736.80

IX PEKERJAAN MEKANIKAL
A PEKERJAAN INSTALASI AIR BERSIH -
- Toilet Lantai - 1 ( Elevasi - 4.00) -
- Toilet Lantai - 2 ( Elevasi ±0.00 ) -
- Toilet Lantai - 3 ( Elevasi ± 4.00 ) -
- Pek. Intalasi Air Bersih Lantai RL -
B PEK. INSTALASI AIR BUANGAN, AIR KOTOR & AIR HUJAN 260,040.00
- Toilet Lantai - 1( Elev.± -4.00) 260,040.00
- Toilet Lantai - 2 ( Elev.± 0.00) -
- Toilet Lantai - 3 ( Elev.± 4.00) -
C PEKERJAAN INSTALASI AIR CONDITIONING (AC) - -
D PEKERJAAN INSTALASI APAR (PEMADAM KEBAKARAN) - -
E PEKERJAAN INSTALASI EXHAUST FAN - -
F PEKERJAAN INSTALASI FIRE ALARM - -

X PEKERJAAN ELEKTRIKAL -
A PEKERJAAN LANTAI - 1 (Elev. - 4.00) -
B PEKERJAAN LANTAI - 2 (Elev. ± 0.00) -
C PEKERJAAN LANTAI - 3 (Elev. ± 4.00) -
D PEKERJAAN LANTAI ATAP/PETIR -

XI KESELAMATAN DAN KESEHATAN KERJA (K3) - -

JUMLAH 8,657,072,006.83
BILL OF QUANTITY (BOQ) GEDUNG
GEDUNG TEKNIK SIPIL
KEGIATAN : PEMBANGUNAN, REHABILITASI DAN RENOVASI SARANA PRASARANA INFRASTRUKTUR PERGURUAN TINGGI NEGERI
PEKERJAAN : PEMBANGUNAN GEDUNG AKUNTANSI, TEKNIK INFORMASI, TEKNIK SIPIL POLITEKNIK NEGERI SAMARINDA
LOKASI : KOTA SAMARINDA

PERHITUNGAN BIAYA KESELAMATAN DAN KESEHATAN KERJA

NO URAIAN PEKERJAAN SAT. VOLUME HARGA SATUAN JUMLAH HARGA

1 2 3 4 5 6
Keselamatan dan Kesehatan Kerja
1
- Penyiapan RK3K Terdiri atas
a Pembuatan manual prosedur, instruksi kerja
dan ijin kerja Ls 1.00 - -
b Pembuatan Kartu Identitas Pekerja (KIP) Org 30.00 - -
- Sosialisasidan Promosi K3 terdiri atas :
a Spanduk (banner) Lb 4.00 - -
b Poster Lb 2.00 - -
c Papan Informasi K3 Bh 2.00 - -
- Alat Pelindung Kerja terdiri atas :
a Jaring Pengaman Ls 1.00 - -
b Tali Keselamatan (lifeline) Ls 1.00 - -
c Pagar Pengaman (guard railling) Ls 1.00 - -
d Pembatas Area Ls 1.00 - -
- Alat Pelindung Diri terdiri atas :
a Helm Sefety Bh 25.00 - -
b Pelindung Mata Psg 60.00 - -
c Pelindung Pernapasan dan Mulut (Masker) Psg 60.00 - -
d Sarung Tangan (Kulit, Katun dan Karet) Psg 60.00 - -
e Sepatu Keselamatan Psg 60.00 - -
f Rompi Keselamatan (safety Vest) Psg 15.00 - -
- Asuransi dan Perijinan terdiri atas :
a BPJS Ketenaga Kerjaandan esehatan Kerja,
(Berdasarkan Kepmenaker No. Kep. 196/MEN/ -
1999, untuk Tenaga harian proyek Ls 1.00 - -
- Personil K3 terdiri atas :
a Ahli K3 OB 4.00 - -
b Petugas Tanggap Darurat OB 4.00 - -
c PetugasK3 OB 4.00 - -
- Pasilitas sarana Kesehatan
a Peralatan P3K (Kotak P3K , Tandu, Tabung Ls 1.00 - -
Oksigen, Obat Luka, Perban dll.
- Rambu - Rambu terdiri atas :
a Rambu Petunjuk Bh 4.00 - -
b RambuLarangan Bh 4.00 - -
c Rambu Peringatan Bh 4.00 - -
d Rambu Kewajiban Bh 4.00 - -
e Rambu Informasi Bh 4.00 - -
- Lain -Lain Terkait Pengendalian ResikoK3
a Alat Pemadam ApiRingan (Apar); 3,3 kg Bh 1.00 - -
b Bendera K3 Bh 4.00 - -
c Pelaporan dan Penyelidikan Insiden Ls 1.00 - -

Jumlah -
BILL OF QUANTITY (BOQ)
GEDUNG TEKNIK SIPIL

KEGIATAN : PEMBANGUNAN, REHABILITASI DAN RENOVASI SARANA PRASARANA INFRASTRUKTUR PERGURUAN TINGGI NEGERI
PEKERJAAN : PEMBANGUNAN GEDUNG AKUNTANSI, TEKNIK INFORMASI, TEKNIK SIPIL POLITEKNIK NEGERI SAMARINDA
LOKASI : KOTA SAMARINDA

JUMLAH HARGA TOTAL HARGA


NO URAIAN PEKERJAAN SAT. VOLUME HARGA SATUAN (Rp)
( Rp ) ( Rp )

1 2 3 4 5 6 7
I PEKERJAAN PENDAHULUAN
2 Bowplank + Pengukuran lokasi + Pematokan M' 175.00 - -
3 Pembersihan Lahan/Stripping M² 346.50 - -
4 Mobilisasi/Demobilisasi Ls 1.00 - -

TOTAL : I. PEKERJAAN PENDAHULUAN -

II. PEK. PEMATANGAN LAHAN DAN TURAP


1 Lahan
- Galian Tanah biasa/Pematangan Lahan M' 735.68 169,840.00 124,947,891.20

2 Pondasi Turap Batu Gunung


- Pancang ulin 10/10 h : 2 m Ttk 248.00 250,500.00 62,124,000.00
- Pas. Aanstamping Batu Gunung M³ 65.39 - -
- Pasangan Batu Gunung 1 : 4 M³ 492.42 - -
- Plesteran Siar Mata Sapi M² 634.92 - -
- Pipa Drainase PVC ø 2" h + sumbat Ijuk Bh 420.00 - -

3 Pekerjaan Parit Induk


- Galian tanah Parit M³ 101.20 85,640.00 8,666,768.00
- Kolom+Balok Praktis 13/13 M' 49.23 - -
- Balok Latai 13/13 dan sloof M' 389.80 - -
- Pas. Batu Bata 1 : 2 M³ 72.11 310,000.00 22,354,100.00
- Plester 1 : 2 M² 407.52 - -
- Cor Lantai Parit t.10 cm M³ 11.51 - -
- Pekerjaan Grill Besi Ø 16 - l = 30 cm M' 29.30 - -

4 Pekerjaan Parit Bangunan Keliling Bangunan


- Galian tanah Parit M³ 35.15 85,640.00 3,010,246.00
- Pas. Batu Bata 1 : 2 M³ 131.81 310,000.00 40,861,100.00
- Plester 1 : 2 M² 132.91 - -
- Cor Lantai Parit t.10 cm M³ 5.86 897,300.00 5,258,178.00

5 Pekerjaan Terap Tangga dari Halaman ke Teras


- Pasangan Batu Gunung 1 : 4 M³ 4.50 - -
- Pas. Rolag 1 Bata 1 : 4 M² 32.40 88,700.00 2,873,880.00
- Cor Terap Tangga M³ 2.03 - -
- Pas Batu Andesit Terap Tangga M² 27.90 - -
- Plester 1 :4 M² 6.00 - -

TOTAL : II. PEKERJAAN PEMATANGAN LAHAN DAN TURAP 270,096,163.20

III. PEKERJAAN SUB STRUKTUR.


1 Pancang Bore pile Ø 30 K300 dlm 14 m M' 1,890.00 250,500.00 473,445,000.00
2 Pemotongan Kepala Tiang Pancang Ttk 150.00 75,000.00 11,250,000.00
4 Galian Pondasi M³ 172.96 85,640.00 14,812,294.40
5 Urugan Pasir Bawah Poer Plat dan Sloof = 5cm M³ 6.04 174,400.00 1,053,376.00
6 Cor lantai Kerja Bawah Poer Plat dan Sloof = 5cm M³ 6.04 897,300.00 5,419,692.00
7 Urugan Tanah Bawah Lantai + Pemadatan M³ 364.50 258,600.00 94,259,700.00
8 Urugan Pasir Bawah Lantai t = 5 cm M³ 42.40 174,400.00 7,394,560.00
9 Cor Lantai Kerja Bawah Lantai t = 5cm M³ 42.40 897,300.00 38,045,520.00

TOTAL : III. PEKERJAAN SUB STRUKTUR 645,680,142.40

IV. PEKERJAAN UPPER STRUKTUR


- Lantai 1 (Elv. - 4.00)
1 Pondasi Type A 230x 160 x 50 cm K 300
Pembesian Ulir Kg 6,318.65 7,600.00 48,021,740.00
Bekesting / Cetakan Untuk Pondasi M² 50.70 418,100.00 21,197,670.00
Beton fc 26,4 Mpa M³ 23.92 1,100,800.00 26,331,136.00
JUMLAH HARGA TOTAL HARGA
NO URAIAN PEKERJAAN SAT. VOLUME HARGA SATUAN (Rp)
( Rp ) ( Rp )

1 2 3 4 5 6 7
2 Pondasi Type B 160x 160 x 50 cm fc' 26,4 Mpa
Pembesian Ulir Kg 6,232.41 7,600.00 47,366,316.00
Bekesting / Cetakan Untuk Pondasi M² 60.80 418,100.00 25,420,480.00
Beton fc 26,4 Mpa M³ 24.32 1,100,800.00 26,771,456.00
3 Pondasi Type C 155x 155 x 50 cm fc' 26,4 MPa
Pembesian Ulir Kg 734.22 7,600.00 5,580,072.00
Bekesting / Cetakan Untuk Pondasi M² 9.30 418,100.00 3,888,330.00
Beton fc 26,4 Mpa M³ 3.60 1,100,800.00 3,962,880.00
4 Pondasi Type D 155x 155 x 50 cm fc' 26,4 MPa
Pembesian Ulir Kg 1,122.07 7,600.00 8,527,732.00
Bekesting / Cetakan Untuk Pondasi M² 9.92 418,100.00 4,147,552.00
Beton fc 26,4 Mpa M³ 3.84 1,100,800.00 4,227,072.00
5 Pondasi Type E110 x 110 x 40 cm fc' 26,4 MPa
Pembesian Ulir Kg 114.42 7,600.00 869,592.00
Bekesting / Cetakan Untuk Pondasi M² 1.76 418,100.00 735,856.00
Beton fc 26,4 Mpa M³ 0.48 1,100,800.00 528,384.00
6 Pondasi Type F120 x 120 x 40 cm fc' 26,4 MPa
Pembesian Ulir Kg 1,094.70 7,600.00 8,319,720.00
Bekesting / Cetakan Untuk Pondasi M² 19.20 418,100.00 8,027,520.00
Beton fc 26,4 Mpa M³ 5.76 1,100,800.00 6,340,608.00
7 Kolom K1 35x50 fc' 26,4 MPa
Pembesian Ulir Kg 893.33 7,600.00 6,789,308.00
Pembesian Polos Kg 138.24 7,600.00 1,050,624.00
Bekesting / Cetakan Untuk Kolom M² 34.00 418,100.00 14,215,400.00
Beton fc 26,4 Mpa M³ 3.68 1,100,800.00 4,050,944.00
8 Kolom K2 40x40 fc' 26,4 MPa
Pembesian Ulir Kg 6,485.60 7,600.00 49,290,560.00
Pembesian Polos Kg 1,227.60 7,600.00 9,329,760.00
Bekesting / Cetakan Untuk Kolom M² 309.76 308,100.00 95,437,056.00
Beton fc 26,4 Mpa M³ 30.98 1,100,800.00 34,102,784.00
9 Kolom K3 35x35 fc' 26,4 MPa
Pembesian Ulir Kg 170.28 7,600.00 1,294,128.00
Pembesian Polos Kg 48.36 7,600.00 367,536.00
Bekesting / Cetakan Untuk Kolom M² 12.40 308,100.00 3,820,440.00
Beton fc' 26,4 MPa M³ 1.09 1,100,800.00 1,199,872.00
10 Balok Tee Bim 25x40 fc' 26,4 MPa
Pembesian Ulir Kg 6,099.64 7,600.00 46,357,264.00
Besi Polos Kg 1,953.60 7,600.00 14,847,360.00
Bekesting / Cetakan Untuk Sloof M² 318.24 223,400.00 71,094,816.00
Beton fc' 26,4 MPa M³ 47.74 1,100,800.00 52,552,192.00
11 Balok Tee Bim 20x30 fc' 26,4 MPa
Pembesian Ulir Kg 205.77 7,600.00 1,563,852.00
Pembesian Polos Kg 56.88 7,600.00 432,288.00
Bekesting / Cetakan Untuk Sloof M² 7.02 223,400.00 1,568,268.00
Beton fc' 26,4 MPa M³ 0.70 1,100,800.00 770,560.00
12 Plat Lantai Dasar t= 12 cm fc' 26,4 MPa
Pembesian Polos Kg 13,824.54 7,600.00 105,066,504.00
Bekisting/Perancah Lantai M² 21.82 418,100.00 9,122,942.00
Beton fc' 26,4 MPa M³ 102.75 1,100,800.00 113,107,200.00
13
Pek. Beton Tangga t = 15 cm
Pembesian Ulir Kg 591.44 7,600.00 4,494,944.00
Pembesian Polos Kg 583.42 7,600.00 4,433,992.00
Bekesting / Cetakan Untuk Tangga M² 46.54 418,100.00 19,458,374.00
Beton fc' 26,4 MPa M³ 6.03 1,100,800.00 6,637,824.00
14 Cor Lantai Selasar Gedung
Pembesian Polos Kg 730.79 7,600.00 5,554,004.00
Bekesting / Cetakan Untuk Sloof M² 11.75 223,400.00 2,624,950.00
Beton fc' 26,4 MPa M³ 8.23 1,100,800.00 9,059,584.00
Jumlah 939,959,446.00

- Lantai 2 (Elevasi ± 0.00)


1 Balok 1 dan balok 2 30x50 fc' 26,4 MPa
Pembesian Ulir Kg 3,577.59 7,600.00 27,189,684.00
Pembesian Polos Kg 1,611.00 7,600.00 12,243,600.00
Bekesting / Cetakan Untuk Balok M² 181.80 311,000.00 56,539,800.00
Beton fc' 26,4 MPa M³ 27.27 1,100,800.00 30,018,816.00
2 Balok 3 dan balok 4 25x40 fc' 26,4 MPa
Pembesian Ulir Kg 5,362.90 7,600.00 40,758,040.00
Pembesian Polos Kg 1,640.88 7,600.00 12,470,688.00
JUMLAH HARGA TOTAL HARGA
NO URAIAN PEKERJAAN SAT. VOLUME HARGA SATUAN (Rp)
( Rp ) ( Rp )

1 2 3 4 5 6 7
Bekesting / Cetakan Untuk Balok M² 249.04 311,000.00 77,451,440.00
Beton fc' 26,4 MPa M³ 37.36 1,100,800.00 41,125,888.00
3 Balok 5 20x30 fc' 26,4 MPa
Pembesian Ulir Kg 142.90 7,600.00 1,086,040.00
Pembesian Polos Kg 2.16 7,600.00 16,416.00
Bekesting / Cetakan Untuk Balok M² 6.12 311,000.00 1,903,320.00
Beton fc' 26,4 MPa M³ 0.61 1,100,800.00 671,488.00
4 Balok 6 15x20 fc' 26,4 Mpa
Pembesian Ulir Kg 211.45 7,600.00 1,607,020.00
Pembesian Polos Kg 35.55 7,600.00 270,180.00
Bekesting / Cetakan Untuk Sloof M² 32.77 223,400.00 7,320,818.00
Beton fc' 26,4 MPa M³ 2.46 1,100,800.00 2,707,968.00
5 Pek. Plat Lantai t = 12 cm fc' 26,4 MPa
Pembesian Polos Kg 8,816.94 7,600.00 67,008,744.00
Bekisting/Perancah Lantai M² 549.37 7,600.00 4,175,212.00
Beton fc' 26,4 MPa M³ 64.15 1,100,800.00 70,616,320.00
6 Pek. Plat Lantai tribun minit = 12 cm fc' 26,4 MPa
Pembesian Ulir Kg 4,715.80 7,600.00 35,840,080.00
Pembesian Polos Kg 1,347.84 7,600.00 10,243,584.00
Bekisting/Perancah Lantai M² 129.60 418,100.00 54,185,760.00
Beton fc' 26,4 MPa M³ 15.55 1,100,800.00 17,117,440.00
7 Pek. Plat Kanopi t = 10 cm fc' 26,4 MPa
Pembesian Polos Kg 1,069.64 7,600.00 8,129,264.00
Bekisting/Perancah Lantai M² 67.50 418,100.00 28,221,750.00
Beton fc' 26,4 MPa M³ 15.69 1,100,800.00 17,271,552.00
8 Kolom K1 35x50 fc' 26,4 MPa
Pembesian Ulir Kg 1,179.20 7,600.00 8,961,920.00
Pembesian Polos Kg 178.56 7,600.00 1,357,056.00
Bekesting / Cetakan Untuk Kolom M² 45.90 308,100.00 14,141,790.00
Beton fc' 26,4 MPa M³ 4.73 1,100,800.00 5,206,784.00
9 Kolom K2 40x40 fc' 26,4 MPa
Pembesian Ulir Kg 6,485.60 7,600.00 49,290,560.00
Pembesian Polos Kg 1,227.60 7,600.00 9,329,760.00
Bekesting / Cetakan Untuk Kolom M² 309.76 308,100.00 95,437,056.00
Beton fc' 26,4 MPa M³ 30.98 1,100,800.00 34,102,784.00
10 Kolom K3 35x35 fc' 26,4 MPa
Pembesian Ulir Kg 196.53 7,600.00 1,493,628.00
Pembesian Polos Kg 48.36 7,600.00 367,536.00
Bekesting / Cetakan Untuk Kolom M² 12.32 308,100.00 3,795,792.00
Beton fc' 26,4 MPa M³ 1.08 1,100,800.00 1,188,864.00
11 Kolom KP1 10x18 fc' 26,4 MPa
Pembesian Polos Kg 1,159.93 7,600.00 8,815,468.00
Bekesting / Cetakan Untuk Kolom M² 38.80 308,100.00 11,954,280.00
Beton fc' 26,4 MPa M³ 3.33 1,100,800.00 3,665,664.00
12 Pek. Beton Tangga t = 15 cm
Pembesian Ulir Kg 591.44 7,600.00 4,494,944.00
Pembesian Polos Kg 583.42 7,600.00 4,433,992.00
Bekesting / Cetakan Untuk Tangga M² 46.54 418,100.00 19,458,374.00
Beton fc' 26,4 MPa M³ 6.03 1,100,800.00 6,637,824.00
13 Pekerjaan Waterproofing M² 131.00 - -
Jumlah 910,324,988.00
- Lantai 3 (Elevasi ± 4.00)
1 Balok 30x50 fc' 26,4 MPa
Pembesian Ulir Kg 4,257.56 7,600.00 32,357,456.00
Pembesian Polos Kg 1,891.80 7,600.00 14,377,680.00
Bekesting / Cetakan Untuk Balok M² 225.00 311,000.00 69,975,000.00
Beton fc' 26,4 MPa M³ 33.75 1,100,800.00 37,152,000.00
2 Balok 25x40 fc' 26,4 MPa
Pembesian Ulir Kg 4,209.52 7,600.00 31,992,352.00
Pembesian Polos Kg 1,300.68 7,600.00 9,885,168.00
Bekesting / Cetakan Untuk Balok M² 245.52 311,000.00 76,356,720.00
Beton fc' 26,4 MPa M³ 36.83 1,100,800.00 40,542,464.00
JUMLAH HARGA TOTAL HARGA
NO URAIAN PEKERJAAN SAT. VOLUME HARGA SATUAN (Rp)
( Rp ) ( Rp )

1 2 3 4 5 6 7
3 Balok 5 20x30 fc' 26,4 MPa
Pembesian Ulir Kg 836.37 7,600.00 6,356,412.00
Pembesian Polos Kg 253.88 7,600.00 1,929,488.00
Bekesting / Cetakan Untuk Balok M² 42.06 311,000.00 13,080,660.00
Beton fc' 26,4 MPa M³ 4.21 1,100,800.00 4,634,368.00
3 Pek. Plat Lantai t = 12 cm fc' 26,4 MPa
Pembesian Polos Kg 16,598.10 7,600.00 126,145,560.00
Bekisting/Perancah Lantai M² 829.18 418,100.00 346,680,158.00
Beton fc' 26,4 MPa M³ 97.14 1,100,800.00 106,931,712.00
4 Pek. Plat Atap Kanopi t = 10 cm fc' 26,4 MPa
Pembesian Polos Kg 1,190.60 7,600.00 9,048,560.00
Bekisting/Perancah Lantai M² 152.88 418,100.00 63,919,128.00
Beton fc' 26,4 MPa M³ 13.89 1,100,800.00 15,290,112.00
5 Kolom K2 40x40 fc' 26,4 MPa
Pembesian Ulir Kg 6,485.60 7,600.00 49,290,560.00
Pembesian Polos Kg 1,227.60 7,600.00 9,329,760.00
Bekesting / Cetakan Untuk Kolom M² 309.76 308,100.00 95,437,056.00
Beton fc' 26,4 MPa M³ 30.98 1,100,800.00 34,102,784.00
6 Kolom K3 35x35 fc' 26,4 MPa
Pembesian Ulir Kg 196.53 7,600.00 1,493,628.00
Pembesian Polos Kg 48.36 7,600.00 367,536.00
Bekesting / Cetakan Untuk Kolom M² 12.32 308,100.00 3,795,792.00
Beton fc' 26,4 MPa M³ 1.08 1,100,800.00 1,188,864.00
7 Kolom K1 35x50 fc' 26,4 MPa
Pembesian Ulir Kg 1,572.27 7,600.00 11,949,252.00
Pembesian Polos Kg 238.08 7,600.00 1,809,408.00
Bekesting / Cetakan Untuk Kolom M² 61.20 308,100.00 18,855,720.00
Beton fc' 26,4 MPa M³ 6.30 1,100,800.00 6,935,040.00
8 Pekerjaan Waterproofing M² 138.88 - -
Jumlah 1,241,210,398.00
- RL. (Elevasi +7,80)
1 Balok 15x20 cm fc' 18.67 MPa
Pembesian Ulir Kg 238.62 7,600.00 1,813,512.00
Pembesian Polos Kg 72.72 7,600.00 552,672.00
Bekesting / Cetakan Untuk Balok M² 77.22 311,000.00 24,015,420.00
Beton fc' 26,4 MPa M³ 4.21 1,100,800.00 4,634,368.00
2 Balok 20x30 cm fc' 26,4 MPa
Pembesian Ulir Kg 593.80 7,600.00 4,512,880.00
Pembesian Polos Kg 97.20 7,600.00 738,720.00
Bekesting / Cetakan Untuk Balok M² 16.00 311,000.00 4,976,000.00
Beton fc' 26,4 MPa M³ 1.20 1,100,800.00 1,320,960.00
3 Pek. Plat Dak t = 12 cm fc' 26,4 MPa
Pembesian Polos Kg 499.88 7,600.00 3,799,088.00
Bekisting/Perancah Lantai M² 22.37 418,100.00 9,352,897.00
Beton fc' 26,4 MPa M³ 2.42 1,100,800.00 2,663,936.00
4 Pek. Plat Kanopi t = 10 cm fc' 26,4 MPa
Pembesian Ulir Kg 3,105.84 7,600.00 23,604,384.00
Bekisting/Perancah Lantai M² 135.52 418,100.00 56,660,912.00
Beton fc' 26,4 MPa M³ 12.32 1,100,800.00 13,561,856.00
5 Pekerjaan Waterproofing M² 143.36 - -
Jumlah 152,207,605.00
- RL.2 (Elevasi +9.51)
1 Balok 20x30 cm fc' 26,4 MPa
Pembesian Ulir Kg 3,958.61 7,600.00 30,085,436.00
Pembesian Polos Kg 1,150.92 7,600.00 8,746,992.00
Bekesting / Cetakan Untuk Balok M² 255.60 311,000.00 79,491,600.00
Beton fc' 26,4 MPa M³ 19.17 1,100,800.00 21,102,336.00
2 Balok 25x40 fc' 26,4 MPa
Pembesian Ulir Kg 388.96 7,600.00 2,956,096.00
Pembesian Polos Kg 126.00 7,600.00 957,600.00
Bekesting / Cetakan Untuk Balok M² 20.88 311,000.00 6,493,680.00
Beton fc' 26,4 MPa M³ 3.13 1,100,800.00 3,445,504.00
Jumlah 153,279,244.00

TOTAL : IV. PEKERJAAN UPPER STRUKTUR 3,396,981,681.00


JUMLAH HARGA TOTAL HARGA
NO URAIAN PEKERJAAN SAT. VOLUME HARGA SATUAN (Rp)
( Rp ) ( Rp )

1 2 3 4 5 6 7
V. PEKERJAAN RANGKA KUDA - KUDA DAN ATAP
1 Pek. Kuda - kuda Baja Siku Kg 47,562.28 - -
2 Pek. Gording Kanal C Kg 8,728.82 - -
3 Pek. Tie Rod/Ikatan Angin Kg 117.70 - -
4 Pek. Plat Simpul Kg 4,322.75 - -
5 Pas .Baut Ø 16 mm bh 4,838.00 - -
6 Pas. Angkur Ø 22 - h. 50 cm bh 148.00 - -
7 Pek. Pas. Rangka Atap genteng metal (Baja Ringan) M² 897.50 - -
8 Pek. Pas. Atap Metal M² 897.50 - -
9 Pek. Talang Jurai dalam M' 21.80 - -
10 Pek. Bubungan Atap M' 97.50 - -
11 Pas.LisplanK GRC 9/30 CM M' 135.50 - -

TOTAL : V. PEKERJAAN RANGKA KUDA - KUDA DAN ATAP -


VI. PEKERJAAN ARSITEKTUR
A. PEKERJAAN PASANGAN DINDING
- Lantai 1 (Elv. - 4.00)
1 Kolom+Balok Praktis 13/13 M' 343.00 308,100.00 105,678,300.00
2 Balok Latai 13/13 M' 44.80 - -
3 Pemasangan dinding HB10 campuran 1PC:4PP M² 919.70 371,000.00 341,208,700.00
4 Pemasangan plesteran 1PC:4PP tebal 10 mm M² 1,839.40 88,700.00 163,154,780.00
5 Plesteran Kolom 1 : 4 M² 252.84 - -
6 Pemasangan acian M² 2,092.00 56,300.00 117,779,600.00
7 Pas. Dinding Keramik Les Pintu M² 12.63 341,200.00 4,309,356.00
8 Pas. Sancren Aliminium t. 90 cm M² 59.62 - -
9 Cor Rabat Keliling Bangunan t. 10 cm Beton fc' 19,3 Mpa M³ 7.65 1,050,200.00 8,034,030.00
10 Relling Tangga (pipa standlistel Ø 2,5 ) M' 64.38 - -
Jumlah 740,164,766.00
- Lantai 2 (Elevasi ± 0.00)
1 Kolom Praktis 13/13 M' 325.00 308,100.00 100,132,500.00
2 Balok Latai M' 68.30 - -
3 Pemasangan dinding HB10 campuran 1PC:4PP M² 1,027.50 371,000.00 381,202,500.00
4 Pemasangan plesteran 1PC:4PP tebal 10 mm M² 2,055.00 88,700.00 182,278,500.00
5 Plesteran Kolom 1 : 4 M² 264.04 - -
6 Pemasangan acian M² 2,319.03 56,300.00 130,561,389.00
Jumlah 794,174,889.00
- Lantai 3 (Elevasi ± 4.00)
1 Kolom Praktis 13/13 M' 318.50 308,100.00 98,129,850.00
2 Balok Latai 13/20 M' 198.00 - -
3 Pemasangan dinding HB10 campuran 1PC:4PP M² 1,048.42 371,000.00 388,963,820.00
4 Pemasangan plesteran 1PC:4PP tebal 10 mm M² 2,096.84 88,700.00 185,989,708.00
5 Plesteran Kolom 1 : 4 M² 264.04 - -
6 Pemasangan acian M² 2,360.88 56,300.00 132,917,544.00
7 Pas. Sancren Aliminium t. 90 cm M² 130.90 - -
8 Relling Tangga (pipa standlistel Ø 2,5 ) M' 64.38 - -
Jumlah 806,000,922.00
- RL.1 (Elevasi +8,8.000)
1 Pemasangan dinding HB10 campuran 1PC:4PP M² 158.55 371,000.00 58,822,050.00
2 Pemasangan plesteran 1PC:4PP tebal 20 mm M² 317.10 88,700.00 28,126,770.00
3 Tangga Besi Ke Tandon Air M' 12.00 - -
Jumlah 86,948,820.00

TOTAL : VI.A. PEKERJAAN PASANGAN DINDING 2,427,289,397.00


B PEKERJAAN PINTU/ JENDELA
- Lantai 1 (Elv. - 4.00)
1 PEK. PINTU TYPE PU.uk 395 x 450 CM (1 Unit)
- Kusen Pintu Allumunium M' 47.00 - -
- Daun Pintu Kaca Tempered 12 mm M² 4.25 - -
- Kaca t = 5 mm M² 6.57 - -
- Engsel Pintu + Aksesories Bh 1.00 - -
- Kunci Pintu + Aksesories Bh 1.00 - -
- Handle Pintu Bh 2.00 - -
JUMLAH HARGA TOTAL HARGA
NO URAIAN PEKERJAAN SAT. VOLUME HARGA SATUAN (Rp)
( Rp ) ( Rp )

1 2 3 4 5 6 7

2 PEK. PINTU TYPE PS.uk 170 x 255 CM (2 Unit)


- Kusen Pintu Allumunium M' 50.32 - -
- Daun Pintu Kaca Tempered 12 mm M² 8.66 - -
- Kaca t = 5 mm M² 5.64 - -
- Engsel Pintu + Aksesories Bh 2.00 - -
- Kunci Pintu + Aksesories Bh 2.00 - -

3 PEK. PINTU TYPE P1. uk 170 x 250 CM (9 Unit)


- Kusen Pintu Allumunium M' 60.30 - -
-Frame Daun Pintu Allumunium M² 120.60 - -
- Kaca t = 5 mm M² 21.60 - -
- Engsel Pintu Bh 54.00 - -
- Kunci Pintu Bh 9.00 - -
- Espagnollette Tanam Bh 9.00 - -
- Door Closer Bh 18.00 - -

4 PEK. PINTU TYPE P3. uk 83 x 220 CM (6 Unit)


- Kusen Pintu Allumunium M' 40.80 - -
- Frame Daun Pintu Allumunium M' 40.50 - -
- Spandrill Plafond Alumunium M² 7.98 - -
- Engsel Pintu Bh 18.00 - -
- Kunci Pintu Bh 6.00 - -

5 PEK. PINTU TYPE P4. uk 83 x 220 CM (2 Unit)


- Kusen Pintu Allumunium M' 13.60 - -
- Frame Daun Pintu Allumunium M' 15.30 - -
- Spandrill Plafond Alumunium M² 3.14 - -
- Engsel Pintu Bh 6.00 - -
- Kunci Pintu Bh 2.00 - -

6 PEK. PINTU TYPE PV. uk 170 x 250 CM (1 Unit)


- Kusen Pintu Allumunium M' 6.60 - -
- Frame Daun Pintu Allumunium M' 15.60 - -
- Kaca t = 5 mm M² 2.34 - -
- Engsel Pintu Bh 6.00 - -
- Kunci Pintu Bh 1.00 - -
- Espagnollette Tanam Bh 1.00 - -
- Door Closer Bh 2.00 - -

7 PEK. JENDELA TYPE J1A. Uk 193 x 311 CM (8 Unit)


- Kusen Jendela Allumunium M' 80.64 - -
- Frame Daun Jendela Allumunium M' 172.00 - -
- Kaca t = 5 mm M² 38.08 - -
- Engsel Jendela Bh 80.00 - -
- Handle Jendela Bh 40.00 - -

8 PEK. JENDELA TYPE J1B. Uk 206 x 193 CM (7 Unit)


- Kusen Jendela Allumunium M' 55.65 - -
- Frame Daun Jendela Allumunium M' 150.50 - -
- Kaca t = 5 mm M² 23.80 - -
- Engsel Jendela Bh 70.00 - -
- Handle Jendela Bh 35.00 - -

9 PEK. JENDELA TYPE J2. Uk 77 x 211 CM (1 Unit)


- Kusen Jendela Allumunium M' 7.99 - -
- Frame Daun Jendela Allumunium M' 8.84 - -
- Kaca t = 5 mm M² 1.36 - -
- Engsel Jendela Bh 4.00 - -
- Handle Jendela Bh 2.00 - -

10 PEK. JENDELA TYPE J3. Uk 56 x 150 CM (36 Unit)


- Kusen Jendela Allumunium M' 220.32 - -
- Frame Daun Jendela Allumunium M' 237.60 - -
- Kaca t = 5 mm M² 19.80 - -
- Engsel Jendela Bh 288.00 - -
- Handle Jendela Bh 144.00 - -
JUMLAH HARGA TOTAL HARGA
NO URAIAN PEKERJAAN SAT. VOLUME HARGA SATUAN (Rp)
( Rp ) ( Rp )

1 2 3 4 5 6 7

12 PEK. JENDELA TYPE BV1. Uk 54 x 65 CM (8 Unit)


- Kusen Jendela Allumunium M' 15.84 - -
- Pipa Hollow 4x4 cm M' 13.44 - -

13 PEK. JENDELA TYPE BV3. Uk 34 x 185 CM (12 Unit)


- Kusen Jendela Allumunium M' 55.92 - -
- Kaca t = 5 mm M² 4.68 - -

14 PEK. JENDELA TYPE BV4. Uk 34 x 65 CM (2 Unit)


- Kusen Jendela Allumunium M' 3.56 - -
- Kaca t = 5 mm M² 0.26 - -

15 PEK. JENDELA TYPE SH1. Uk 44 x 70 CM (1 Unit)


- Kusen Jendela Allumunium M' 2.28 - -
- Daun Jendela Allumunium M² 0.31 - -
- Kunci Jendela Bh 1.00 - -

16 PEK. JENDELA TYPE SH1. Uk 40 x 70 CM (1 Unit)


- Kusen Jendela Allumunium M' 2.20 - -
- Daun Jendela Allumunium M² 0.28 - -
- Kunci Jendela Bh 1.00 - -

Jumlah -

- Lantai 2 (Elevasi ± 0.00)


1 PEK. PINTU TYPE PH1. 170 x 280 CM (1 Unit)
- Kusen Pintu Allumunium M' 34.90 - -
- Daun Pintu Kaca Tempered 12 mm M² 4.08 - -
- Kaca t = 5 mm M² 4.33 - -
- Engsel Pintu + Aksesories Bh 1.00 - -
- Kunci Pintu + Aksesories Bh 1.00 - -
- Handle Pintu Bh 2.00 - -

2 PEK. PINTU TYPE PS.uk 170 x 255 CM (1 Unit)


- Kusen Pintu Allumunium M' 25.16 - -
- Daun Pintu Kaca Tempered 12 mm M² 4.33 - -
- Kaca t = 5 mm M² 2.82 - -
- Engsel Pintu + Aksesories Bh 1.00 - -
- Kunci Pintu + Aksesories Bh 1.00 - -

3 PEK. PINTU TYPE PH2.UK.280 x 400 CM (1 Unit)


- Kusen Pintu Allumunium M' 26.94 - -
- Frame Daun Pintu Allumunium M' 11.60 - -
- Kaca t = 5 mm M² 5.56 - -
- Engsel Pintu Bh 6.00 - -
- Kunci Pintu Bh 1.00 - -
- Espagnollette Tanam Bh 1.00 - -
- Door Closer Bh 2.00 - -

4 PEK. PINTU TYPE P1. uk 170 x 250 CM (6 Unit)


- Kusen Pintu Allumunium M' 40.20 - -
- Frame Daun Pintu Allumunium M' 80.40 - -
- Kaca t = 5 mm M² 14.40 - -
- Engsel Pintu Bh 36.00 - -
- Kunci Pintu Bh 6.00 - -
- Espagnollette Tanam Bh 6.00 - -
- Door Closer Bh 12.00 - -

5 PEK. PINTU TYPE P2. uk 138 x 220 CM (2 Unit)


- Kusen Pintu Allumunium M' 11.36 - -
- Frame Daun Pintu Allumunium M' 22.40 - -
- Kaca t = 5 mm M² 3.08 - -
- Engsel Pintu Bh 12.00 - -
- Kunci Pintu Bh 2.00 - -
- Espagnollette Tanam Bh 2.00 - -
- Door Closer Bh 4.00 - -
JUMLAH HARGA TOTAL HARGA
NO URAIAN PEKERJAAN SAT. VOLUME HARGA SATUAN (Rp)
( Rp ) ( Rp )

1 2 3 4 5 6 7

6 PEK. PINTU TYPE P3. uk 83 x 220 CM (3 Unit)


- Kusen Pintu Allumunium M' 20.40 - -
- Frame Daun Pintu Allumunium M' 20.25 - -
- Spandrill Plafond Alumunium M² 3.99 - -
- Engsel Pintu Bh 9.00 - -
- Kunci Pintu Bh 3.00 - -

7 PEK. PINTU TYPE PA.uk 170 x 255 CM (2 Unit)


- Kusen Pintu Allumunium M' 30.54 - -
- Daun Pintu Kaca Tempered 12 mm M² 8.66 - -
- Kaca t = 5 mm M² 3.58 - -
- Engsel Pintu + Aksesories Bh 2.00 - -
- Kunci Pintu + Aksesories Bh 2.00 - -

8 PEK. JENDELA TYPE J3. Uk 56 x 150 CM (44 Unit)


- Kusen Jendela Allumunium M' 269.28 - -
- Frame Daun Jendela Allumunium M' 290.40 - -
- Kaca t = 5 mm M² 24.20 - -
- Engsel Jendela Bh 352.00 - -
- Handle Jendela Bh 176.00 - -

9 PEK. JENDELA TYPE J4. Uk 56 x 110 CM (3 Unit)


- Kusen Jendela Allumunium M' 13.26 - -
- Frame Daun Jendela Allumunium M' 17.16 - -
- Kaca t = 5 mm M² 1.08 - -
- Engsel Jendela Bh 12.00 - -
- Handle Jendela Bh 6.00 - -

10 PEK. JENDELA TYPE BV1. Uk 54 x 65 CM (6 Unit)


- Kusen Jendela Allumunium M' 11.88 - -
- Pipa Hollow 4x4 cm M' 10.08 - -

11 PEK. JENDELA TYPE BV2. Uk 34 x 244 CM (2 Unit)


- Kusen Jendela Allumunium M' 12.16 - -
- Kaca t = 5 mm M' 1.04 - -

12 PEK. JENDELA TYPE BV3. Uk 34 x 185 CM (19 Unit)


- Kusen Jendela Allumunium M' 88.54 - -
- Kaca t = 5 mm M² 7.41 - -

13 PEK. JENDELA TYPE SH1. Uk 44 x 70 CM (1 Unit)


- Kusen Jendela Allumunium M' 2.28 - -
- Daun Jendela Allumunium M² 0.31 - -
- Kunci Jendela Bh 1.00 - -

14 PEK. JENDELA TYPE SH1. Uk 40 x 70 CM (1 Unit)


- Kusen Jendela Allumunium M' 2.20 - -
- Daun Jendela Allumunium M² 0.28 - -
- Kunci Jendela Bh 1.00 - -

Jumlah -
- Lantai 3 (Elevasi ± 4.00)
1 PEK. PINTU TYPE PH1. 170 x 280 CM (1 Unit)
- Kusen Pintu Allumunium M' 34.90 - -
- Daun Pintu Kaca Tempered 12 mm M² 4.08 - -
- Kaca t = 5 mm M² 4.33 - -
- Engsel Pintu + Aksesories Bh 1.00 - -
- Kunci Pintu + Aksesories Bh 1.00 - -
- Handle Pintu Bh 2.00 - -
JUMLAH HARGA TOTAL HARGA
NO URAIAN PEKERJAAN SAT. VOLUME HARGA SATUAN (Rp)
( Rp ) ( Rp )

1 2 3 4 5 6 7

2 PEK. PINTU TYPE PH2.UK.280 x 400 CM (1 Unit)


- Kusen Pintu Allumunium M' 26.94 - -
- Frame Daun Pintu Allumunium M' 11.60 - -
- Kaca t = 5 mm M² 5.56 - -
- Engsel Pintu Bh 6.00 - -
- Kunci Pintu Bh 1.00 - -
- Espagnollette Tanam Bh 1.00 - -
- Door Closer Bh 2.00 - -

3 PEK. PINTU TYPE PS.uk 170 x 255 CM (1 Unit)


- Kusen Pintu Allumunium M' 25.16 - -
- Daun Pintu Kaca Tempered 12 mm M² 4.33 - -
- Kaca t = 5 mm M² 2.82 - -
- Engsel Pintu + Aksesories Bh 1.00 - -
- Kunci Pintu + Aksesories Bh 1.00 - -

4 PEK. PINTU TYPE PV. uk 170 x 250 CM (1 Unit)


- Kusen Pintu Allumunium M' 6.60 - -
- Frame Daun Pintu Allumunium M' 15.60 - -
- Kaca t = 5 mm M² 2.34 - -
- Engsel Pintu Bh 6.00 - -
- Kunci Pintu Bh 1.00 - -
- Espagnollette Tanam Bh 1.00 - -
- Door Closer Bh 2.00 - -

5 PEK. PINTU TYPE P1. uk 170 x 250 CM (8 Unit)


- Kusen Pintu Allumunium M' 53.60 - -
- Frame Daun Pintu Allumunium M' 107.20 - -
- Kaca t = 5 mm M² 19.20 - -
- Engsel Pintu Bh 48.00 - -
- Kunci Pintu Bh 8.00 - -
- Espagnollette Tanam Bh 8.00 - -
- Door Closer Bh 16.00 - -

6 PEK. PINTU TYPE P3. uk 83 x 220 CM (3 Unit)


- Kusen Pintu Allumunium M' 20.40 - -
- Frame Daun Pintu Allumunium M' 20.25 - -
- Spandrill Plafond Alumunium M² 3.99 - -
- Engsel Pintu Bh 9.00 - -
- Kunci Pintu Bh 3.00 - -

7 PEK. JENDELA TYPE J1B. Uk 206 x 193 CM (2 Unit)


- Kusen Jendela Allumunium M' 15.90 - -
- Frame Daun Jendela Allumunium M' 43.00 - -
- Kaca t = 5 mm M² 6.80 - -
- Engsel Jendela Bh 20.00 - -
- Handle Jendela Bh 10.00 - -

8 PEK. JENDELA TYPE J3. Uk 56 x 150 CM (51 Unit)


- Kusen Jendela Allumunium M' 312.12 - -
- Frame Daun Jendela Allumunium M' 336.60 - -
- Kaca t = 5 mm M² 28.05 - -
- Engsel Jendela Bh 408.00 - -
- Handle Jendela Bh 204.00 - -

9 PEK. JENDELA TYPE J4. Uk 56 x 110 CM (2 Unit)


- Kusen Jendela Allumunium M' 8.84 - -
- Frame Daun Jendela Allumunium M' 11.44 - -
- Kaca t = 5 mm M² 0.72 - -
- Engsel Jendela Bh 8.00 - -
- Handle Jendela Bh 4.00 - -
JUMLAH HARGA TOTAL HARGA
NO URAIAN PEKERJAAN SAT. VOLUME HARGA SATUAN (Rp)
( Rp ) ( Rp )

1 2 3 4 5 6 7

10 PEK. JENDELA TYPE BV1. Uk 54 x 65 CM (5 Unit)


- Kusen Jendela Allumunium M' 9.90 - -
- Pipa Hollow 4x4 cm M' 8.40 - -

11 PEK. JENDELA TYPE BV3. Uk 34 x 185 CM (16 Unit)


- Kusen Jendela Allumunium M' 74.56 - -
- Kaca t = 5 mm M² 6.24 - -

12 PEK. JENDELA TYPE SH1. Uk 44 x 70 CM (1 Unit)


- Kusen Jendela Allumunium M' 2.28 - -
- Daun Jendela Allumunium M² 0.31 - -
- Kunci Jendela Bh 1.00 - -

13 PEK. JENDELA TYPE SH1. Uk 40 x 70 CM (1 Unit)


- Kusen Jendela Allumunium M' 2.20 - -
- Daun Jendela Allumunium M² 0.28 - -
- Kunci Jendela Bh 1.00 - -

Jumlah -

TOTAL : VI.B. PEKERJAAN PINTU/JENDELA -


C. PEKERJAAN LANTAI
- Lantai 1 (Elv. - 4.00)
1 Keramik Lantai 60/60 (Homogenus Tile) M² 911.94 411,800.00 375,536,892.00
2 Keramik Lantai 25/25 Km/Wc M² 22.05 270,400.00 5,962,320.00
3 Keramik Dinding 25 x 40 cm Km/Wc M² 55.50 412,320.00 22,883,760.00
4 Keramik Tangga M² 34.56 288,300.00 9,963,648.00
5 Keramik Step Noushing M' 46.80 117,100.00 5,480,280.00
6 Pas. Dinding Keramik Les Pintu 25X 40 M² 15.08 412,320.00 6,217,785.60
Jumlah 426,044,685.60
- Lantai 2 (Elevasi ± 0.00)
1 Keramik Lantai 60/60 (Homogenus Tile) M² 749.70 411,800.00 308,726,460.00
2 Keramik Lantai 25/25 Km/Wc M² 29.25 270,400.00 7,909,200.00
3 Keramik Dinding 25 x 40 cm Km/Wc M² 73.10 412,320.00 30,140,592.00
4 Keramik Tangga M' 34.56 288,300.00 9,963,648.00
5 Keramik Step Noushing M' 46.80 117,100.00 5,480,280.00
6 Pas. Dinding Keramik Les Pintu 25X 40 M² 5.03 412,320.00 2,073,969.60
Jumlah 364,294,149.60
- Lantai 3 (Elevasi ± 4.00)
1 Keramik Lantai 60/60 (Homogenus Tile) M² 789.78 411,800.00 325,231,404.00
2 Keramik Lantai 25/25 Km/Wc M² 22.05 270,400.00 5,962,320.00
3 Keramik Dinding 25 x 40 cm Km/Wc M² 55.50 412,320.00 22,883,760.00
4 Pas. Dinding Keramik Les Pintu 25X 40 M² 5.03 412,320.00 2,073,969.60
Jumlah 356,151,453.60

TOTAL : VI. C. PEKERJAAN LANTAI 1,146,490,288.80

D. PEKERJAAN PLAFOND
- Lantai 1 (Elv. - 4.00)
1 Pas. Rangka Plapond Hollow M² 651.20 - -
2 Pas. Plapond Gypsum t 9 mm M² 629.15 - -
3 Plafond Kalsibord 4.5 mm M² 22.05 - -
5 Pas. List Profil Gipsum Standart Lebar Sampai 5-10cm M' 453.10 - -
Jumlah -
- Lantai 2 (Elevasi ± 0.00)
1 Pas. Rangka Plapond Hollow M² 616.95 - -
2 Pas. Plapond Gypsum t 9 mm M² 749.70 - -
3 Plafond Kalsibord 4.5 mm M² 29.25 - -
5 Pas. List Profil Gipsum Standart Lebar Sampai 5-10cm M' 363.70 - -
Jumlah -
- Lantai 3 (Elevasi ± 4.00)
1 Pas. Rangka Plapond Hollow M² 872.58 - -
2 Pas. Plapond Gypsum t 9 mm M² 850.53 - -
3 Plafond Kalsibord 4.5 mm M² 22.05 - -
4 List Plafond Gipsum Standart M' 454.00 - -
Jumlah -
JUMLAH HARGA TOTAL HARGA
NO URAIAN PEKERJAAN SAT. VOLUME HARGA SATUAN (Rp)
( Rp ) ( Rp )

1 2 3 4 5 6 7
- RL.1 (Elevasi +8,8.000)
1 Pas. Rangka Plapond Hollow M² 108.00 - -
2 Plafond Kalsibord 4.5 mm M² 108.00 - -
3 List Plafond Gipsum Standart M' 230.00 - -
Jumlah -
TOTAL : VI.D. PEKERJAAN PLAFOND -

E. PEKERJAAN FINISHING
- Lantai 1 (Elv. - 4.00)
1 Cat Tembok Luar M² 656.54 - -
2 Cat Tembok Dalam M² 1,275.35 - -
3 Cat Plafond M² 716.00 - -
Jumlah -
- Lantai 2 (Elevasi ± 0.00)
1 Cat Tembok Luar M² 822.00 - -
2 Cat Tembok Dalam M² 1,227.53 - -
3 Cat Plafond M² 616.95 - -
Jumlah -
- Lantai 3 (Elevasi ± 4.00)
1 Cat Tembok Luar M² 545.79 - -
2 Cat Tembok Dalam M² 1,329.66 - -
3 Cat Plafond M² 872.58 - -
Jumlah -
- RL.1 (Elevasi +8,8.000)
1 Cat Tembok Luar M² 158.55 - -
2 Cat Plafond M² 108.00 - -
3 Cat lis plapond M² 13.50 - -
4 Cat Listplang M² 40.50 - -
Jumlah -

TOTAL : VI.E. PEKERJAAN FINISHING -

F. PEKERJAAN SANITAIR
- Lantai 1 (Elv. - 4.00)
1 Klosed Jongkok Unit 2.00 - -
2 Klosed Duduk Unit 2.00 - -
3 Bak Air Fibber glass kap.0,30m3 Unit 1.00 - -
4 Bioseptic tank (kapasitas 7 m3) Unit 1.00 - -
5 Urinoir Unit 2.00 - -
6 Penyekat Urinoir Unit 1.00 - -
7 Meja Wastafel Beton
- Pembesian kg 19.44 7,600.00 147,744.00
- begesting M² 1.44 - -
- Plat Beton K150 Tbl 10 cm M³ 0.36 - -
- Pas. Keramik 30x30 M² 0.99 282,100.00 279,279.00
8 Satu Wastafel+Kran+Instalas Unit 1.00 - -
9 Dua Wastafel+Kran+Instalasi Unit 1.00 - -
10 Bak Cuci Piring Stainlessteel Unit 1.00 - -
11 Pasanga Kaca Cermin 5 mm M² 2.52 - -
12 Kran air Jet washer + acsesories bh 2.00 - -
13 Kran Air bh 4.00 - -
14 Flour drain bh 6.00 - -
15 Reling Tangga Disabilitas M' 3.50 - -
Jumlah 427,023.00
- Lantai 2 (Elevasi ± 0.00)
1 Klosed Duduk Unit 2.00 - -
2 Klosed Jongkok Unit 1.00 - -
3 Bak Air Fibber glass kap.0,30m3 Unit 1.00 - -
4 Meja Wastafel Beton
- Pembesian kg 19.44 7,600.00 147,744.00
- begesting M² 1.44 - -
- Plat Beton K150 Tbl 10 cm M³ 0.36 - -
- Pas. Keramik 30x30 M² 0.99 282,100.00 279,279.00
5 Satu Wastafel+Kran+Instalasi+Meja Beton Unit 1.00 - -
6 Dua Wastafel+Kran+Instalasi+Meja Beton Unit 1.00 - -
7 Pasanga Kaca Cermin 5 mm M² 2.52 - -
8 Kran air Jet washer + acsesories bh 2.00 - -
9 Kran Air bh 7.00 - -
10 Flour drain bh 7.00 - -
11 Reling Tangga Disabilitas M' 6.00 - -
Jumlah 427,023.00
JUMLAH HARGA TOTAL HARGA
NO URAIAN PEKERJAAN SAT. VOLUME HARGA SATUAN (Rp)
( Rp ) ( Rp )

1 2 3 4 5 6 7
- Lantai 3 (Elevasi ± 4.00)
1 Klosed Duduk Unit 2.00 - -
2 Klosed Jongkok Unit 1.00 - -
3 Bak Air Fibber glass kap.0,30m3 Unit 1.00 - -
4 Meja Wastafel Beton
- Pembesian kg 19.44 7,600.00 147,744.00
- begesting M² 1.44 - -
- Plat Beton K150 Tbl 10 cm M³ 0.36 - -
- Pas. Keramik 30x30 M² 0.99 282,100.00 279,279.00
5 Satu Wastafel+Kran+Instalasi+Meja Beton Unit 1.00 - -
6 Dua Wastafel+Kran+Instalasi+Meja Beton Unit 1.00 - -
7 Kran air Jet washer + acsesories bh 2.00 - -
8 Pasangan Kaca Cermin 5 mm M² 2.52 - -
9 Kran Air bh 3.00 - -
10 Urinoir Unit 2.00 - -
11 Penyekat Urinoir bh 1.00 - -
12 Flour drain bh 5.00 - -
Jumlah 427,023.00

TOTAL : VI.F. PEKERJAAN SANITER 1,281,069.00


VII PEKERJAAN JEMBATAN PENGHUBUNG
A. PEKERJAAN SUB STRUKTUR.
1 Pancang Bor File Ø 30 K300 dlm 14 m M' 112.00 - -
2 Galian Pondasi M³ 11.52 85,640.00 986,572.80
3 Urugan Pasir Bawah Poer Plat dan Sloof = 5cm M³ 1.15 - -
4 Cor lantai Kerja Bawah Poer Plat dan Sloof = 5cm M³ 0.58 - -
Jumlah 986,572.80
B. PEKERJAAN UPPER STRUKTUR
- Lantai 1 (Elv. - 4.00)
1 Pondasi Type F120 x 120 x 40 cm fc' 26,4 MPa
Pembesian Ulir Kg 875.76 7,600.00 6,655,776.00
Bekesting / Cetakan Untuk Pondasi M² 3.84 71,905.16 276,115.83
Beton fc 26,4 Mpa M³ 4.61 1,100,800.00 5,074,688.00
2 Balok Tee Bim 25x40 fc' 26,4 MPa
Pembesian Ulir Kg 201.96 7,600.00 1,534,896.00
Pembesian Polos Kg 66.24 7,600.00 503,424.00
Bekesting / Cetakan Untuk Sloof M² 10.80 223,400.00 2,412,720.00
Beton fc' 26,4 MPa M³ 1.35 1,100,800.00 1,486,080.00
3 Kolom K1 35x50 fc' 26,4 MPa
Pembesian Ulir Kg 771.84 7,600.00 5,865,984.00
Pembesian Polos Kg 120.96 7,600.00 919,296.00
Bekesting / Cetakan Untuk Kolom M² 26.52 308,100.00 8,170,812.00
Beton fc' 26,4 MPa M³ 2.73 1,100,800.00 3,005,184.00

- Lantai 2 (Elevasi ± 0.00)


1 Balok 1 dan balok 2 30x50 fc' 26,4 MPa
Pembesian Ulir Kg 717.39 7,600.00 5,452,164.00
Pembesian Polos Kg 324.90 7,600.00 2,469,240.00
Bekesting / Cetakan Untuk Balok M² 36.00 311,000.00 11,196,000.00
Beton fc' 26,4 MPa M³ 2.16 1,100,800.00 2,377,728.00
2 Balok 3 dan balok 4 25x40 fc' 26,4 MPa
Pembesian Kg 1,381.68 7,600.00 10,500,768.00
Bekesting / Cetakan Untuk Balok M² 97.72 311,000.00 30,390,920.00
Beton fc' 26,4 MPa M³ 11.66 1,100,800.00 12,835,328.00
3 Balok 5 20x30 fc' 26,4 MPa
Pembesian Kg 1,572.27 7,600.00 11,949,252.00
Bekesting / Cetakan Untuk Balok M² 54.40 311,000.00 16,918,400.00
Beton fc' 26,4 MPa M³ 5.60 1,100,800.00 6,164,480.00

4 Pek. Plat Lantai t = 12 cm fc' 26,4 MPa


Pembesian Polos Kg 416.58 7,600.00 3,166,008.00
Bekisting/Perancah Lantai M² 49.14 418,100.00 20,545,434.00
Beton fc' 26,4 MPa M³ 5.90 1,100,800.00 6,494,720.00

- Lantai 3 (Elevasi ± 4.00)


1 Balok 1 dan balok 2 30x50 fc' 26,4 MPa
Pembesian Ulir Kg 717.39 7,600.00 5,452,164.00
Pembesian Polos Kg 324.90 7,600.00 2,469,240.00
Bekesting / Cetakan Untuk Balok M² 36.00 311,000.00 11,196,000.00
Beton fc' 26,4 MPa M³ 2.16 1,100,800.00 2,377,728.00
JUMLAH HARGA TOTAL HARGA
NO URAIAN PEKERJAAN SAT. VOLUME HARGA SATUAN (Rp)
( Rp ) ( Rp )

1 2 3 4 5 6 7
2 Pek. Plat Lantai t = 12 cm fc' 26,4 MPa
Pembesian Polos Kg 1,381.68 7,600.00 10,500,768.00
Bekisting/Perancah Lantai M² 97.72 418,100.00 40,856,732.00
Beton fc' 26,4 MPa M³ 11.66 1,100,800.00 12,835,328.00
3 Kolom K1 35x50 fc' 26,4 MPa
Pembesian Ulir Kg 1,572.27 7,600.00 11,949,252.00
Pembesian Polos Kg 238.08 7,600.00 1,809,408.00
Bekesting / Cetakan Untuk Kolom M² 54.40 308,100.00 16,760,640.00
Beton fc' 26,4 MPa M³ 5.60 1,100,800.00 6,164,480.00
4 Pek. Plat Atap Kanopi t = 10 cm fc' 26,4 MPa
Pembesian Polos Kg 416.58 7,600.00 3,166,008.00
Bekisting/Perancah Lantai M² 49.14 418,100.00 20,545,434.00
Beton fc' 26,4 MPa M³ 5.90 1,100,800.00 6,494,720.00
5 Pekerjaan Waterproofing M² 117.00 - -
Jumlah 328,943,319.83

C. PEKERJAAN PASANGAN DINDING


- Lantai 2 (Elevasi ± 0.00)
1 Kolom Praktis 13/13 M' 8.00 308,100.00 2,464,800.00
2 Balok Latai M' 36.00 473,100.00 17,031,600.00
3 Pemasangan dinding HB10 campuran 1PC:4PP M² 23.82 371,000.00 8,837,220.00
4 Pemasangan plesteran 1PC:4PP tebal 10 mm M² 47.64 88,700.00 4,225,668.00
5 Plesteran Kolom 1 : 4 M² 44.80 - -
6 Pemasangan acian M² 92.44 56,300.00 5,204,372.00
7 Pas. Sancren Aliminium t. 90 cm M² 36.60 - -
8 Relling Tangga (pipa standlistel Ø 2,5 ) M' 33.60 - -

- Lantai 3 (Elevasi ± 4.00)


1 Kolom Praktis 13/13 M' 8.00 308,100.00 2,464,800.00
2 Balok Latai M' 36.00 473,100.00 17,031,600.00
3 Pemasangan dinding HB10 campuran 1PC:4PP M² 23.82 371,000.00 8,837,220.00
4 Pemasangan plesteran 1PC:4PP tebal 10 mm M² 47.64 88,700.00 4,225,668.00
5 Plesteran Kolom 1 : 4 M² 44.80 - -
6 Pemasangan acian M² 92.44 56,300.00 5,204,372.00
7 Pas. Sancren Aliminium t. 90 cm M' 36.60 - -
8 Relling Tangga (pipa standlistel Ø 2,5 ) M' 33.60 - -
Jumlah 75,527,320.00
D. PEKERJAAN LANTAI
- Lantai 2 (Elevasi ± 0.00)
1 Keramik Lantai 60/60 (Homogenus Tile) M² 81.00 411,800.00 33,355,800.00

- Lantai 3 (Elevasi ± 4.00)


1 Keramik Lantai 60/60 (Homogenus Tile) M² 81.00 411,800.00 33,355,800.00
Jumlah 66,711,600.00
E. PEKERJAAN FINISHING
- Lantai 1 (Elv. - 4.00)
1 Cat Tembok Luar M² 106.60 - -

- Lantai 2 (Elevasi ± 0.00)


1 Cat Tembok Luar M² 225.80 - -

- Lantai 3 (Elevasi ± 4.00)


1 Cat Tembok Luar M² 225.80 - -
Jumlah -

TOTAL : VII. PEKERJAAN JEMBATAN PENHUBUNG 472,168,812.63


VIII PEKERJAAN HALAMAN DAN TAMAN
A Pekerjaan Halaman/Jalan
1 Urugan pasir t = 5cm M³ 31.47 174,400.00 5,488,368.00
2 Cor Lantai Kerja t = 5 cm M³ 31.47 897,300.00 28,238,031.00
3 Besi Tulangan Pokok Ø 10 -15 cm Kg 11,266.90 8,380.00 94,416,622.00
4 Bekesting M² 66.28 418,100.00 27,711,668.00
5 Cor beton fc: 26,4 Mpa t = 20 cm M³ 112.12 1,065,700.00 119,486,284.00
Jumlah 275,340,973.00
JUMLAH HARGA TOTAL HARGA
NO URAIAN PEKERJAAN SAT. VOLUME HARGA SATUAN (Rp)
( Rp ) ( Rp )

1 2 3 4 5 6 7
B. Pekerjaan Ramp Disabilitas
1 Galian Tanah M³ 1.67 85,640.00 143,018.80
2 Pas. Pondasi Batu Gunung M³ 2.14 - -
3 Urungan Pasir t = 5 cm M³ 1.43 174,400.00 249,392.00
4 Besi Beton Ø 10 - 15 cm kg 262.64 8,380.00 2,200,923.20
5 Begesting M² 5.00 418,100.00 2,090,500.00
6 Cor beton mutu fc 16,9 Mpa M³ 1.63 1,026,300.00 1,672,869.00
7 Keramik Lantai 60/60 (unpolish Tile) M² 22.50 411,800.00 9,265,500.00
8 Pasangan Guiding block M² 7.50 427,000.00 3,202,500.00
9 Relling Tangga Standlisteel (disabilitas) M' 50.00 - -
Jumlah 18,824,703.00
C. Pekerjaan Tangga Darurat
1 Galian Tanah M³ 1.67 85,640.00 143,018.80
2 Pek. Pacang Ulin 10/10 - 2 m titik 4.00 250,500.00 1,002,000.00
3 Pas. Pondasi Batu Gunung M³ 2.14 - -
4 Pekerjaan Beton Sloof 20/25
- Pembesian Polos kg 34.48 7,600.00 262,048.00
- Bekesting / Cetakan Untuk Sloof M² 2.50 223,400.00 558,500.00
- Beton fc' 26,4 MPa M³ 0.35 1,100,800.00 385,280.00
5 Cor Beton Lantai t = 10 cm mutu fc 16,9 Mpa M³ 0.30 1,026,300.00 307,890.00
6 Pekerjaan Baja
- Baja INP 160 (160 x 74 x 6,5 x 9,5 x 3,8 ) kg 2,741.43 - -
- Plat Siku L 70.70.7 kg 8.86 - -
- Plat Siku L 60.60.6 kg 86.72 - -
- Plat Baja t = 1 cm kg 2,289.06 - -
- Baut Ø 3/4" bh 8.00 - -
- Baut Ø 1/2" bh 384.00 - -
7 Reling tangga Besi Kotak 4x4 dan 2x4 M² 37.68 - -
Jumlah 2,658,736.80

TOTAL : VII. PEKERJAAN HALAMAN 296,824,412.80

TOTAL RAB GEDUNG SIPIL 8,656,811,966.83

IX PEKERJAAN MEKANIKAL

A. PEKERJAAN INSTALASI AIR BERSIH


Pengadaan dan pemasangan peralatan air bersih dan instalasi pipa air bersih
dalam gedung berikut fixtures, fittings, aksesoris, hanger & support
dan perlengkapannya beserta pengetesan sistem dan instalasi.
A.1 - Toilet Lantai 1 ( Elevasi - 4.00)
1 Pipa PVC AW ::
a. Pipa PVC AW ø 3/4" m 10.50 - -
b. Pipa PVC AW ø 1" (dari pipa induk Ke gedung) m 16.00 - -
2 Fitting & aksesoris pipa GSP medium class ls 1.00 - -
Jumlah Instalasi Air Bersih Lantai 1 (Elevasi -4.00) Jumlah : -

A.2 - Toilet Lantai -2 ( Elevasi ±0.00 )


1 Pipa PVC AW :
a. Pipa PVC AW ø 3/4" m 8.00 - -
b. Pipa tegak PVC ø 1" m 12.00 - -
2 Fitting & aksesoris pipa GSP medium class ls 1.00 - -
Jumlah Instalasi Air Bersih Lantai 2 (Elevasi ±0.00) Jumlah : -

A.3 - Toilet Lantai - 3 ( Elevasi ± 4.00 )


1 Pipa PVC AW :
a. Pipa PVC AW ø 3/4" m 12.00 - -
b. Pipa tegak PVC ø 1" m 8.00 - -
2 Fitting & aksesoris pipa GSP medium class ls 1.00 - -
Jumlah Instalasi Air Bersih Lantai 3 (Elevasi ±4.00) Jumlah : -

A.4 - Pek. Intalasi Air Bersih Lantai RL


1 Pekerjaan instalasi tanki air (roof tank) :
a. Tanki air (roof tank) : unit 3.00 - -
Tipe/material : GS-2000 / Fibre Glass
Kapasitas : 2.000 liter
Ketebalan : 0,7 mm
Diameter : 990 mm
Tinggi : 1,450 mm
Kode : RT - 01 A/B
JUMLAH HARGA TOTAL HARGA
NO URAIAN PEKERJAAN SAT. VOLUME HARGA SATUAN (Rp)
( Rp ) ( Rp )

1 2 3 4 5 6 7
b. Pipa venting tanki air :
- Pipa PVC AW class ø 40 mm, lengkap dengan insect screen m 3.00 - -
c. Mesin Pompa Air/Swage Pump (Komplit) unit 1.00 - -
d. Fitting & aksesoris pipa PVC AW class ls 1.00 - -
2 Pipa PVC AW :
a. Pipa tegak PVC AW ø 3/4* (Rooftank) m 18.00 - -
b. Pipa PVC AW ø 1,5" (ke lantai 1 & taman) m 34.76 - -
c. Pipa PVC AW ø 2" (drain & overflow) m 21.36 - -
3 Fitting & aksesoris pipa GSP medium class ls 1.00 - -
Jumlah Instalasi Air Bersih - RL Jumlah : -
JUMLAH - A. PEKERJAAN INSTALASI AIR BERSIH : -
B PEK. INSTALASI AIR BUANGAN, AIR KOTOR & AIR HUJAN
Pengadaan dan pemasangan instalasi air bekas, air kotor, air hujan,
dan pipa ventilasinya dalam gedung berikut fixtures, fittings,
aksesoris, hanger & support dan perlengkapannya
beserta pengetesan sistem dan instalasi.
B.1 - Toilet Lantai - 1( Elev. ± -4.00)
1 Pekerjaan instalasi air bekas :
a. Pipa uPVC class AW :
- Pipa uPVC class AW ø 50 mm m 2.50 - -
b. Fitting & aksesoris pipa uPVC class AW ls 1.00 - -
2 Pekerjaan instalasi air kotor :
a. Pipa uPVC class AW :
- Pipa uPVC class AW ø 100 mm m 8.00 - -
b. Fitting & aksesoris pipa uPVC class AW ls 1.00 - -
3 Galian tanah dan urugan kembali jalur pipa m 1.00 260,040.00 260,040.00
Jumlah 260,040.00

B.2 - Toilet Lantai - 2 ( Elev. ± 0.00)


1 Pekerjaan instalasi air bekas :
a. Pipa uPVC class AW :
- Pipa uPVC class AW ø 50 mm m 16.50 - -
b. Fitting & aksesoris pipa uPVC class AW ls 1.00 - -
2 Pekerjaan instalasi air kotor :
a. Pipa uPVC class AW :
- Pipa uPVC class AW ø 100 mm m 12.00 - -
b. Fitting & aksesoris pipa uPVC class AW ls 1.00 - -
Jumlah -

B.3 - Toilet Lantai - 3 ( Elev. ± 4.00)


1 Pekerjaan instalasi air bekas :
a. Pipa uPVC class AW :
- Pipa uPVC class AW ø 50 mm m 26.50 - -
b. Fitting & aksesoris pipa uPVC class AW ls 1.00 - -
2 Pekerjaan instalasi air kotor :
a. Pipa uPVC class AW :
- Pipa uPVC class AW ø 100 mm m 28.00 - -
b. Fitting & aksesoris pipa uPVC class AW ls 1.00 - -
Jumlah -

SUB JUMLAH - B PEK. INSTALASI AIR BUANGAN, AIR KOTOR & AIR HUJAN : 260,040.00

C. PEKERJAAN INSTALASI AIR CONDITIONING (AC)


Pengadaan dan pemasangan air conditioning (AC) lengkap dengan
kabel daya, refrigerant berisolasi, pipa drain (kondensat)
dan perlengkapannya beserta pengetesan sistem dan instalasi.
C.1 Pek. Instalasi Air Conditioning (AC) Lantai 1
1 Instalasi Air Conditioning (AC)
a. Unit air conditioning (AC) : unit 15.00 - -
- Fan coil unit (FCU)
Tipe : wall mounted, single split system
Kapasitas : 18.000 BTUH
Servis : Ruang Sidang, AD, Prodi, Dosen
Kode unit : FCU.1-01
Lokasi : lantai Ground
- Condensing unit
Konsumsi daya : 825 W / 220 V / 1 Ph / 50 Hz
Kode unit : CU.1-01
Lokasi : outdoor lantai 1
JUMLAH HARGA TOTAL HARGA
NO URAIAN PEKERJAAN SAT. VOLUME HARGA SATUAN (Rp)
( Rp ) ( Rp )

1 2 3 4 5 6 7
b. Pipa refrigerant m 50.25 - -
c. Instalasi kabel daya : NYM 3 x 2,5 mm2 m 120.00 - -
d. Instalasi pipa drain/kondensat AC :
- Pipa drain/kondensat AC ø 20 mm m 45.00 - -
e. Fitting & aksesoris pipa drain/kondensat AC ls 1.00 - -

C.2 Pek. Instalasi Air Conditioning (AC) Lantai 2


1 Instalasi Air Conditioning (AC)
a. Unit air conditioning (AC) : unit 18.00 - -
- Fan coil unit (FCU)
Tipe : wall mounted, single split system
Kapasitas : 18.000 BTUH
Servis : Ruang VIP
Kode unit : FCU.1-01
Lokasi : lantai 1
- Condensing unit
Konsumsi daya : 2000 W / 220 V / 1 Ph / 50 Hz
Kode unit : CU.1-01
Lokasi : outdoor lantai 1
b. Pipa refrigerant m 60.30 - -
c. Instalasi kabel daya : NYM 3 x 2,5 mm2 m 144.00 - -
d. Instalasi pipa drain/kondensat AC :
- Pipa drain/kondensat AC ø 20 mm m 54.00 - -
e. Fitting & aksesoris pipa drain/kondensat AC ls 1.00 - -

C.3 Pek. Instalasi Air Conditioning (AC) Lantai 3


1 Instalasi Air Conditioning (AC)
a. Unit air conditioning (AC) : unit 13.00 - -
- Fan coil unit (FCU)
Tipe : wall mounted, single split system
Kapasitas : 18.000 BTUH
Servis : Ruang Sekretaris
Kode unit : FCU.1-01
Lokasi : lantai 1
- Condensing unit
Konsumsi daya : 825 W / 220 V / 1 Ph / 50 Hz
Kode unit : CU.1-01
Lokasi : outdoor lantai 1
b. Pipa refrigerant m 43.29 - -
c. Instalasi kabel daya : NYM 3 x 2,5 mm2 m 104.00 - -
d. Instalasi pipa drain/kondensat AC :
- Pipa drain/kondensat AC ø 20 mm m 39.00 - -
e. Fitting & aksesoris pipa drain/kondensat AC ls 1.00 - -

SUB JUMLAH - C. PEKERJAAN INSTALASI AIR CONDITIONING (AC) : -

D. PEKERJAAN INSTALASI APAR (PEMADAM KEBAKARAN)


Pengadaan dan pemasangan Apar lengkap dengan
Tabung, Penggantung, serta MSDS (material safety data sheets)
dan perlengkapannya beserta pengetesan sistem dan instalasi.
D.1 Lantai - 1 ( Elev. ± -4.00)
Jenis Apar Carbon dioxide/ C02 unit 3.00 - -
Tipe : Carbon Dioxide (CO2) Portable
Model : SV – 230 C
Berat : 3 kg
Kelas : BC (Minyak, Solar, Bensin, Elektronik dan Listrik)
D.2 Lantai - 2 ( Elev. ± 0.00)
Jenis Apar Carbon dioxide/ C02 unit 3.00 - -
Tipe : Carbon Dioxide (CO2) Portable
Model : SV – 230 C
Berat : 3 kg
Kelas : BC (Minyak, Solar, Bensin, Elektronik dan Listrik)
D.3 Lantai - 3 ( Elev. ± 4.00)
Jenis Apar Carbon dioxide/ C02
Tipe : Carbon Dioxide (CO2) Portable unit 3.00 - -
Model : SV – 230 C
Berat : 3 kg
Kelas : BC (Minyak, Solar, Bensin, Elektronik dan Listrik)

SUB JUMLAH - D. PEKERJAAN INSTALASI APAR (PEMADAM KEBAKARAN) : -


JUMLAH HARGA TOTAL HARGA
NO URAIAN PEKERJAAN SAT. VOLUME HARGA SATUAN (Rp)
( Rp ) ( Rp )

1 2 3 4 5 6 7
E. PEKERJAAN INSTALASI EXHAUST FAN
Pengadaan dan pemasangan exhaust fan lengkap dengan kabel daya
dan perlengkapannya beserta pengetesan sistem dan instalasi.

E.1 Lantai - 1 ( Elev. ± -4.00)


a. Unit exhaust fan : EFT-1.01A & 01B unit 3.00 - -
Tipe : Propeller Wall Mounted
Kapasitas : 200 CMH
Static pressure : 5 Pa
Konsumsi daya : 55 W/ 220V/ 1 Ph / 50 Hz
Putaran : rpm
Servis : ruang toilet (as. Y-14' - Y-15')
Kode unit : EFT-1.01A & EFT-1.01B
b. Instalasi kabel daya : NYM 3 x 2,5 mm2 m 9.00 - -

E.2 Lantai - 2 ( Elev. ± 0.00)


a. Unit exhaust fan : EFT-1.03A & 03B unit 3.00 - -
Tipe : Propeller Wall Mounted
Kapasitas : 200 CMH
Static pressure : 5 Pa
Konsumsi daya : 55 W/ 220V/ 1 Ph / 50 Hz
Putaran : rpm
Servis : ruang toilet (as. Y-3' - Y-4')
Kode unit : EFT-1.03A & EFT-1.03B
b. Instalasi kabel daya : NYM 3 x 2,5 mm2 m 9.00 - -

E.3 Lantai - 3 ( Elev. ± 4.00)


a. Unit exhaust fan : EFT-1.03A & 03B unit 3.00 - -
Tipe : Propeller Wall Mounted
Kapasitas : 200 CMH
Static
: 5 Pa
pressure
Konsumsi
: 55 W/ 220V/ 1 Ph / 50 Hz
daya
Putaran : rpm
Servis : ruang toilet (as. Y-3' - Y-4')
Kode unit : EFT-1.03A & EFT-1.03B
b. Instalasi kabel daya : NYM 3 x 2,5 mm2 m 9.00 - -

SUB JUMLAH - E. PEKERJAAN INSTALASI EXHAUST FAN : -

F. PEKERJAAN INSTALASI FIRE ALARM


Pengadaan dan pemasangan FIRE ALARM
dan perlengkapannya beserta pengetesan sistem dan instalasi.
Master/Main CONTROL Fire Alarm (MCFA)
Type Semi Addressible 2 loop c/w BackUp Battery unit 1.00 - -
F.1 Lantai - 1 ( Elev. ± -4.00)
a. Kabel distribusi MCFA ke terminal Box m 20.00 - -
b. Grounding lot 1.00 - -
c. Monitor modul set 1.00 - -
d. Control modul set 1.00 - -
e. Zone modul set 1.00 - -
f. Instalasi Detector titik 38.00 - -
g. MCP titik 1.00 - -
h. Alarm Bel titik 1.00 - -
i. Smoke Detektor bh 2.00 - -
j. Heat Detektor (ROR) bh 34.00 - -
k. Heat Detektor (Fixed) bh 2.00 - -

F.2 Lantai - 2 ( Elev. ± 0.00)


a. Kabel distribusi MCFA ke terminal Box m 40.00 - -
b. Grounding lot 1.00 - -
c. Monitor modul set 1.00 - -
d. Control modul set 1.00 - -
e. Zone modul set 1.00 - -
f. Instalasi Detector titik 29.00 - -
g. MCP titik 1.00 - -
h. Alarm Bel titik 1.00 - -
i. Smoke Detektor bh 6.00 - -
j. Heat Detektor (ROR) bh 23.00 - -
JUMLAH HARGA TOTAL HARGA
NO URAIAN PEKERJAAN SAT. VOLUME HARGA SATUAN (Rp)
( Rp ) ( Rp )

1 2 3 4 5 6 7

F.3 Lantai - 3 ( Elev. ± 4.00)


a. Kabel distribusi MCFA ke terminal Box m 60.00 - -
b. Grounding lot 1.00 - -
c. Monitor modul set 1.00 - -
d. Control modul set 1.00 - -
e. Zone modul set 1.00 - -
f. Instalasi Detector titik 26.00 - -
g. MCP titik 1.00 - -
h. Alarm Bel titik 1.00 - -
i. Heat Detektor (ROR) bh 26.00 - -

SUB JUMLAH - F. PEKERJAAN INSTALASI FIRE ALARM : -

TOTAL PEKERJAAN MEKANIKAL 260,040.00

X PEKERJAAN ELEKTRIKAL
A PEKERJAAN LANTAI 1 (Elev. - 4.00)
1 Kabel Feeder
- dari PLN ke PUTR, NYY 4x70 mm2 m 50.00 - -
- dari PUTR ke PSD, NYFGbY 4x50 mm 2 m 15.00 - -
- dari PUTR ke P-AB, NYFGbY 4x4 mm 2 m 10.00 - -
- dari PSD ke P-1, NYY 4x6 mm 2 m 8.00 - -
- dari PSD ke PAC-1, NYY 4x16 mm 2 m 12.00 - -
2 Panel Hubung Bagi
- Panel LVMDP unit 1.00 - -
- Panel P 1 unit 1.00 - -
- Pembumian Pengaman ttk 1.00 - -
3 Pencahayaan
- Lampu RM 300 Led 2 x 18 Wat Mirror Louvere bh 24.00 - -
- Lampu RM 300 Led 2 x 36 Wat Mirror Reflector bh 14.00 - -
- Lampu RM 300 Led 2 x 36 Watt Open Type/TKI bh 47.00 - -
- Lampu RM Down Light 18 Wat bh 40.00 - -
- Saklar Tunggal 10A 250 VAC bh 3.00 - -
- Saklar Ganda 10A 250 VAC bh 27.00 - -
- Instalasi Penerangan Kabel Dalam Pipa Kondui uPVC titik 246.00 - -
4 Kotak Kontak
- Kotak Kontak 1 Fasa 15 A, 250 VAC bh 56.00 - -
- Instalasi Penerangan Kabel Dalam Pipa Kondui uPVC titik 56.00 - -
5 LD PROYEKTOR
- Tiang Penggantung LCD Otomatis unit 3.00 - -
- Instalasi Daya 2 x 2.5 mm ttk 3.00 - -
- Kotak Kontak 1 Fasa 15 A 250 VAC bh 3.00 - -
- Instalasi Penerangan Kabel Dalam Pipa Kondul uPVC ttk 3.00 - -
- Kabel Data HDMI m 36.00 - -
- Autlet Data bh 1.00 - -
Jumlah -

B PEKERJAAN LANTAI 2 (Elev. ± 0.00)


1 Kabel Feeder
- dari PSD ke P-2, NYY 4x6 mm2 m 26.00 - -
2 Panel Hubung Bagi
- Panel P-2 unit 1.00 - -
- Panel AC unit 1.00 - -
3 Pencahayaan
- Lampu RM 300 Led 2 x 36 Wat Mirror Louvere bh 28.00 - -
- Lampu RM 300 Led 2 x 36 Wat Mirror Reflector bh 44.00 - -
- Lampu RM 300 Led 2 x 18 Wat Flucrescent Light bh 16.00 - -
- Lampu RM Down Light 18 Wat bh 57.00 - -
- Lampu GMS T 8 ACR-SCR 1 X 18 Wat bh 102.00 - -
- Saklar Tunggal 10A 250 VAC bh 2.00 - -
- Saklar Ganda 10A 250 VAC bh 15.00 - -
- Instalasi Penerangan Kabel Dalam Pipa Kondui uPVC titik 145.00 - -
4 Kotak Kontak
- Kotak Kontak Biasa 1 Fasa 15 A, 250 VAC bh 38.00 - -
- Instalasi Penerangan Kabel Dalam Pipa Kondui uPVC titik 38.00 - -
JUMLAH HARGA TOTAL HARGA
NO URAIAN PEKERJAAN SAT. VOLUME HARGA SATUAN (Rp)
( Rp ) ( Rp )

1 2 3 4 5 6 7
5 LD PROYEKTOR
- Tiang Penggantung LCD Otomatis unit 1.00 - -
- Instalasi Daya 2 x 2.5 mm ttk 1.00 - -
- Kotak Kontak 1 Fasa 15 A 250 VAC bh 1.00 - -
- Instalasi Penerangan Kabel Dalam Pipa Kondul uPVC ttk 1.00 - -
- Kabel Data HDMI m 16.00 - -
- Autlet Data bh 1.00 - -
Jumlah -

C PEKERJAAN LANTAI - 3 (Elev. ± 4.00)


1 Kabel Feeder
- dari PSD ke P-2, NYY 4x6 mm 2 m 10.00 - -
2 Panel Hubung Bagi
- Panel P-3 unit 1.00 - -
- Panel AC unit 1.00 - -
3 Pencahayaan
- Lampu RM 300 Led 2 x 36 Wat Mirror Louvere bh 48.00 - -
- Lampu RM 300 Led 2 x 36 Wat Mirror Reflector bh 28.00 - -
- Lampu RM Down Light 18 Wat bh 56.00 - -
- Saklar Tunggal 10A 250 VAC bh 1.00 - -
- Saklar Ganda 10A 250 VAC bh 22.00 - -
- Instalasi Penerangan Kabel Dalam Pipa Kondui uPVC titik 132.00 - -
4 Kotak Kontak
- Kotak Kontak Biasa 1 Fasa 15 A, 250 VAC bh 57.00 - -
- Instalasi Penerangan Kabel Dalam Pipa Kondui uPVC titik 57.00 - -
5 LD PROYEKTOR
- Tiang Penggantung LCD Otomatis unit 4.00 - -
- Instalasi Daya 2 x 2.5 mm ttk 4.00 - -
- Kotak Kontak 1 Fasa 15 A 250 VAC bh 4.00 - -
- Instalasi Penerangan Kabel Dalam Pipa Kondul uPVC ttk 4.00 - -
- Kabel Data HDMI m 48.00 - -
- Autlet Data bh 1.00 - -
Jumlah -

D PEKERJAAN LANTAI ATAP /PETIR


1 Proteksi Petir
- terminal udara Flash vectron type FV. 6 radius 150 m unit 1.00 - -
- Tiang Penyangga Terminal Udara (PVC) tinggi 1 meter m 5.00 - -
- Batang tembaga Ø 15 mm (tahanan pembumian) m 6.00 - -
- fiber full solid (connecting sleeve Ø 50 mm) bh 1.00 - -
- elektroda pembumian tembaga pejal bh 3.00 - -
- bak kontrol batu - bata 600 x 600 x 600 mm bh 1.00 - -
- kabel BC 1x70 mm2 dalam pipa uPVC AW Ø 32mm m 40.00 - -
- kabel NYM 3x2,5 mm2 dalam pipa konduit uPVC Ø 20 mm m 40.00 - -
Jumlah : -

TOTAL PEKERJAAN ELEKTRIKAL -


BILL OF QUANTITY (BOQ) SUB REKAP
GEDUNG TEKNIK INFORMASI

KEGIATAN : PEMBANGUNAN, REHABILITASI DAN RENOVASI SARANA PRASARANA INFRASTRUKTUR PERGURUAN TINGGI NEGERI
PEKERJAAN : PEMBANGUNAN GEDUNG AKUNTANSI, TEKNIK INFORMASI, TEKNIK SIPIL POLITEKNIK NEGERI SAMARINDA
LOKASI : KOTA SAMARINDA

HARGA TOTAL HARGA


NO URAIAN PEKERJAAN
( Rp ) ( Rp )
1 2 3 4

A PEKERJAAN PERSIAPAN (K3) 91,315,000.00 91,315,000.00

B PEKERJAAN STRUKTUR CORE LIFT 153,526,395.40


I PEKERJAAN GALIAN DAN URUGAN 914,732.00
II PEKERJAAN STRUKTUR PONDASI, BETON DAN BAJA 152,611,663.40
III PEKERJAAN RANGKA ATAP & TALANG -

C PEKERJAAN ARSITEKTUR
I PEKERJAAN PASANGAN & DINDING 572,670,168.00
I.1 Pekerjaan Lantai - 1 1,727,460.00
I.2 Pekerjaan Lantai - 2 15,130,629.00
I.3 Pekerjaan Lantai - 3 189,506,026.00
I.4 Pekerjaan Lantai - 4 254,610,273.00
I.5 Pekerjaan Lantai - Atas 111,695,780.00

II PEKERJAAN KUSEN, PINTU & JENDELA ALUMINIUM -


II.1 Pekerjaan Lantai - 1 -
II.2 Pekerjaan Lantai - 2 -
II.3 Pekerjaan Lantai - 3 -
II.4 Pekerjaan Lantai - 4 -
II.5 Pekerjaan Lantai - Atap -

III PEKERJAAN LANTAI 157,215,859.00


III.1 Pekerjaan Lantai - 1 20,165,202.00
III.2 Pekerjaan Lantai - 2 14,523,799.00
III.3 Pekerjaan Lantai - 3 61,263,429.00
III.4 Pekerjaan Lantai - 4. 61,263,429.00
III.5 Pekerjaan Lantai - RL. -

IV PEKERJAAN PLAFOND 13,462,496.00


IV.1 Pekerjaan Lantai - 1 -
IV.2 Pekerjaan Lantai - 2 6,731,248.00
IV.3 Pekerjaan Lantai - 3 -
IV.4 Pekerjaan Lantai - 4 6,731,248.00
HARGA TOTAL HARGA
NO URAIAN PEKERJAAN
( Rp ) ( Rp )
1 2 3 4

V PEKERJAAN SANITAIR -
V.1 Pekerjaan Lantai - 1 -
V.2 Pekerjaan Lantai - 2 -
V.3 Pekerjaan Lantai - 3 -
V.4 Pekerjaan Lantai - 4 -
V.5 Pekerjaan Lantai - RL. -

VI PEKERJAAN PENGECATAN / FINISHING -


VI.1 Pekerjaan Lantai - 1 -
VI.2 Pekerjaan Lantai - 2 -
VI.3 Pekerjaan Lantai - 3 -
VI.4 Pekerjaan Lantai - 4 -
VI.5 Pekerjaan Lantai - ATAP -

VII PEKERJAAN ATAP - -

VIII PEKERJAAN RAILLING 32,777,868.00 32,777,868.00

IX PEKERJAAN LAIN - LAIN 4,324,847.00 4,324,847.00

X PEKERJAAN BANGUNAN LIFT 60,642,508.00 60,642,508.00

XI PEKERJAAN GROUND TANK, RUMAH GENSET DAN RUANG POMPA 119,541,587.60


XI.1 Pekerjaan Ground Tank 29,014,920.80
XI.2 Pekerjaan Rumah Genset dan Ruang Pompa 90,526,666.80

D PEKERJAAN ELEKTRIKAL
I PEKERJAAN ELEKTRIKAL GEDUNG -
I.1 Pekerjaan Lantai - 1 -
I.2 Pekerjaan Lantai - 2 -
I.3 Pekerjaan Lantai - 3 -
I.4 Pekerjaan Lantai - 4 -
I.5 Pekerjaan Lantai - Top -

II PEKERJAAN PENANGKAL PETIR - -

III PEKERJAAN JARINGAN LAN -


III.1 Pekerjaan Lantai - 1 -
III.2 Pekerjaan Lantai - 2 -
III.3 Pekerjaan Lantai - 3 -
III.4 Pekerjaan Lantai - 4 -

E PEKERJAAN MEKANIKAL
I INSTALASI AIR BERSIH -
I.1 Pekerjaan Lantai -1 -
I.2 Pekerjaan Lantai -2 -
I.3 Pekerjaan Lantai -3 -
I.4 Pekerjaan Lantai -4 -
I.5 Pekerjaan Lantai -Atap dan Shaft -
HARGA TOTAL HARGA
NO URAIAN PEKERJAAN
( Rp ) ( Rp )
1 2 3 4

II INSTALASI AIR KOTOR 29,498,208.00


II.1 Pekerjaan Lantai -1 29,498,208.00
II.2 Pekerjaan Lantai -2 -
II.3 Pekerjaan Lantai -3 -
II.4 Pekerjaan Lantai -4 -
II.5 Pekerjaan Lantai -Atap -

III PEKERJAAN TATA UDARA -


III.2 Pekerjaan Lantai - 2 -
III.3 Pekerjaan Lantai - 3 -
III.4 Pekerjaan Lantai - 4 -

IV PEKERJAAN PEMADAM KEBAKARAN - -

V PEKERJAAN LIFT ELEVATOR - -

TOTAL 1,234,974,937.00
BILL OF QUANTITY (BOQ)
GEDUNG TEKNIK INFORMASI

KEGIATAN : PEMBANGUNAN, REHABILITASI DAN RENOVASI SARANA PRASARANA INFRASTRUKTUR PERGURUAN TINGGI NEGERI
PEKERJAAN : PEMBANGUNAN GEDUNG AKUNTANSI, TEKNIK INFORMASI, TEKNIK SIPIL POLITEKNIK NEGERI SAMARINDA
LOKASI : KOTA SAMARINDA

PERHITUNGAN BIAYA KESELAMATAN DAN KESEHATAN KERJA

HARGA SATUAN
NO ITEM PEKERJAAN UNIT VOLUME TOTAL HARGA (Rp)
(Rp)
1 2 3 4 5 6

A PEKERJAAN PERSIAPAN (K3)


1 Penyiapan RK3K Terdiri atas
a Pembuatan manual prosedur, instruksi kerja
dan ijin kerja Ls 1.00 1,000,000.00 1,000,000.00
2 Sosialisasidan Promosi K3 terdiri atas :
a Spanduk (banner) Lb 2.00 100,000.00 200,000.00
b Poster Lb 2.00 100,000.00 200,000.00
c Papan Informasi K3 Bh 2.00 100,000.00 200,000.00
3 Alat Pelindung Kerja terdiri atas :
a Jaring Pengaman + Pemasangan ls 1.00 2,500,000.00 2,500,000.00
b Tali Keselamatan (lifeline) + Acesories Ls 1.00 3,000,000.00 3,000,000.00
c Pagar Pengaman (guard railling) Ls 1.00 15,000,000.00 15,000,000.00
d Pembatas Area Ls 1.00 1,500,000.00 1,500,000.00
4 Alat Pelindung Diri terdiri atas :
a Helm Sefety Bh 15.00 40,000.00 600,000.00
b Pelindung Mata Psg 30.00 15,000.00 450,000.00
c Pelindung Pernapasan dan Mulut (Masker) Psg 30.00 5,000.00 150,000.00
d Sarung Tangan (Kulit, Katun dan Karet) Psg 30.00 8,000.00 240,000.00
e Sepatu Keselamatan Psg 15.00 125,000.00 1,875,000.00
f Rompi Lapangan Psg 15.00 50,000.00 750,000.00
5 Asuransi dan Perijinan terdiri atas :
a BPJS Ketenaga Kerjaandan esehatan Kerja,
(Berdasarkan Kepmenaker No. Kep. 196/MEN/
1999, untuk Tenaga harian proyek Ls 1.00 4,750,000.00 4,750,000.00
6 Personil K3 terdiri atas :
a Ahli K3 OB 4.00 7,550,000.00 30,200,000.00
b PetugasK3 OB 4.00 3,500,000.00 14,000,000.00
7 Pasilitas sarana Kesehatan -
a Peralatan P3K (Kotak P3K , Tandu, Tabung Ls 1.00 5,000,000.00 5,000,000.00
Oksigen, Obat Luka, Perban dll.
8 Rambu - Rambu terdiri atas :
a Rambu Petunjuk Bh 2.00 650,000.00 1,300,000.00
b RambuLarangan Bh 2.00 650,000.00 1,300,000.00
c Rambu Peringatan Bh 2.00 650,000.00 1,300,000.00
d Rambu Kewajiban Bh 2.00 650,000.00 1,300,000.00
e Rambu Informasi Bh 2.00 650,000.00 1,300,000.00
9 Lain -Lain Terkait Pengendalian Resiko K3 -
a Bendera K3 Bh 2.00 650,000.00 1,300,000.00
b Pelaporan dan Penyelidikan Insiden Ls 1.00 1,500,000.00 1,500,000.00
c Appar / Pemadam Kebakaran Bh 2.00 200,000.00 400,000.00

TOTAL 91,315,000.00
BILL OF QUANTITY (BOQ)
GEDUNG TEKNIK INFORMASI

KEGIATAN : PEMBANGUNAN, REHABILITASI DAN RENOVASI SARANA PRASARANA INFRASTRUKTUR PERGURUAN TINGGI NEGERI
PEKERJAAN : PEMBANGUNAN GEDUNG AKUNTANSI, TEKNIK INFORMASI, TEKNIK SIPIL POLITEKNIK NEGERI SAMARINDA
LOKASI : KOTA SAMARINDA

HARGA SATUAN JUMLAH HARGA TOTAL HARGA


NO URAIAN PEKERJAAN SAT. VOLUME
( Rp ) ( Rp ) ( Rp )
1 2 3 4 5 6 7

B PEKERJAAN STRUKTUR CORE LIFT


I PEKERJAAN GALIAN DAN URUGAN
1 Galian M
3 9.50 85,640.00 813,580.00
2 Urugan M
3 0.58 174,400.00 101,152.00
TOTAL II.1.I PEKERJAAN GALIAN DAN URUGAN 914,732.00
II PEKERJAAN STRUKTUR PONDASI, BETON DAN BAJA
II.1 Pit Lift
1 Pekerjaan pondasi bor pile dia 30 cm M
1 80.00 253,500.00 20,280,000.00
beton ready mix fc ' = 29,4 Mpa
2 Pekerjaan lantai kerja t = 5 cm
- Lantai kerja dibawah pondasi pile cap M
3 0.19 253,500.00 48,165.00
- Lantai kerja dibawah sloof M
3 0.15 994,600.00 149,190.00
- Lantai kerja dibawah plat M
3 0.30 994,600.00 298,380.00
3 Pekerjaan pondasi pile cap
- Pile cap
- Pembesian Kg 356.67 7,600.00 2,710,692.00
- Bekesting / Cetakan Untuk Pondasi M² 14.08 8,380.00 117,990.40
- Beton fc 26,4 Mpa M³ 3.07 1,100,800.00 3,379,456.00
4 Pekerjaan Tie Beam
Tie Beam TB 30 x 50 cm
- Pembesian Kg 83.72 7,600.00 636,272.00
- Bekesting / Cetakan Untuk Balok M² 5.76 311,000.00 1,791,360.00
- Beton fc' 26,4 MPa M³ 1.44 1,100,800.00 1,585,152.00
5 Kolom pedestal 60 x 60 cm
- Pembesian Kg 377.46 7,600.00 2,868,696.00
- Bekesting / Cetakan Untuk Kolom M² 9.80 308,100.00 3,019,380.00
- Beton fc' 26,4 MPa M³ 0.86 1,100,800.00 946,688.00
6 Angkur Ø dia 16 mm L.50 cm bh 24.00 - -
7 Base Plate 350.350.20 kg 76.93 - -
8 Dinding Pit Lift (shear wall)
- Bekisting M² 16.80 418,100.00 7,024,080.00
- Pembesian Kg 403.20 7,600.00 3,064,320.00
- Beton fc 26,4 Mpa M
3 2.02 1,100,800.00 2,223,616.00
9 Pekerjaan Baja (kolom dan balok)
- Kolom Utama WF. 250.250.9.14 Kg 5,915.88 - -
- Balok Utama WF. 200.100.5,5.8 Kg 1,203.36 - -
- Balok Anak WF. 150.75.5.7 Kg 536.93 - -
- Ringbalk WF.179.90.5.8 Kg 86.11 - -
10 Plat Sambung dan baut
Kolom - Balok Utama (melintang&memanjang)
- Baut HTB M-22 ASTM A.325 Bh 56.00 - -
- Plat Sambung Kg 300.84 - -
Kolom - Balok Anak (melintang&memanjang)
- Baut HTB M-22 ASTM A.325 Bh 32.00 - -
- Plat Sambung Kg 134.23 - -
Balok Utama - Ringbalk Anak
- Baut HTB M-22 ASTM A.325 Bh 16.00 - -
- Plat Sambung Kg 21.53 - -
11 Pekerjaan Beton
Selimut Beton (Kolom dan Balok)
- Selimut kolom 50 x 50 cm beton fc 26,4 M
3 9.95 1,100,800.00 10,952,960.00
- Selimut balok utama 30x20 cm beton fc 26,4 M
3 3.35 1,100,800.00 3,687,680.00
- Selimut balok anak 25x20 cm beton fc 26,4 M
3 1.87 1,100,800.00 2,058,496.00
HARGA SATUAN JUMLAH HARGA TOTAL HARGA
NO URAIAN PEKERJAAN SAT. VOLUME
( Rp ) ( Rp ) ( Rp )
1 2 3 4 5 6 7

- Selimut balok anak 30x20 cm beton fc 26,4 3


M 0.28 1,100,800.00 308,224.00
Begisting
- Begisting Kolom 2
M 115.20 308,100.00 35,493,120.00
- Begisting Balok 30 x 20 2
M 46.08 311,000.00 14,330,880.00
- Begisting Balok 25 x 20 2
M 26.88 311,000.00 8,359,680.00
- Begisting Balok 30 x 20 2
M 31.68 311,000.00 9,852,480.00

Pekerjaan cor lantai t = 10 cm, f'c = 14,5 Mpa 3


M 0.52 994,600.00 517,192.00
Beton Plat lantai Pit, Elv. -2.05
- Beton fc 26,4 3
M 1.80 1,100,800.00 1,981,440.00
- Pembesian Kg 196.94 7,600.00 1,496,744.00
Beton Plat lantai 2,3 & 4
- Beton fc 26,4 3
M 1.86 1,100,800.00 2,047,488.00
- Pembesian Kg 72.52 7,600.00 551,152.00
- Bondeck 2
M 15.54 - -
Beton Plat lantai Mesin, Elv. +16.045
- Beton fc 26,4 3
M 1.04 1,100,800.00 1,144,832.00
- Pembesian Kg 93.24 7,600.00 708,624.00
- Begesting 2
M 5.18 418,100.00 2,165,758.00
Beton Plat lantai dak, Elv. +18.090
- Beton fc 26,4 3
M 1.30 1,100,800.00 1,431,040.00
- Pembesian Kg 113.81 7,600.00 864,956.00
- Begesting 2
M 10.80 418,100.00 4,515,480.00
TOTAL II.1.II PEKERJAAN STRUKTUR PONDASI, BETON DAN BAJA 152,611,663.40

III PEKERJAAN RANGKA ATAP & TALANG


1 Tiang Rangka pipa dia. 5,5" , tebal 3,6 mm Kg 291.81 - -
2 Rangka pipa dia. 42 mm, tebal 2,3 mm ( Atap ) Kg 348.50 - -
3 Rangka pipa dia. 34 mm, tebal 2,3 mm ( Atap ) Kg 111.80 - -
4 Rangka pipa dia. 34 mm, tebal 2,3 mm ( Talang ) Kg 177.20 - -
TOTAL II.1.III PEKERJAAN RANGKA ATAP & TALANG -
TOTAL B. (I+II+III+IV) PEKERJAAN STRUKTUR 153,526,395.40

C PEKERJAAN ARSITEKTUR
I PEKERJAAN PASANGAN & DINDING
I.1 Pekerjaan Lantai - 1
1 Pemasangan dinding HB20 campuran 1PC:4PP M² 3.15 371,000.00 1,168,650.00
2 Pemasangan plesteran 1PC:4PP tebal 10 mm M² 6.30 88,700.00 558,810.00
3 Acian Dinding Pas Bata Ringan M² 125.66 - -
4 Dinding keramik 20/45 (toilet) M² 54.39 - -
5 Dinding keramik 40/40 (Lift) M² 4.20 - -
6 Pas. Batu Alam (Palimanan) M² 73.00 - -
7 Cubicle Toilet 1
M 19.28 - -
Sub Total - Pekerjaan Lantai - 1 1,727,460.00
I.2 Pekerjaan Lantai - 2
1 Pemasangan dinding HB20 campuran 1PC:4PP M² 4.55 371,000.00 1,688,050.00
2 Pemasangan plesteran 1PC:4PP tebal 10 mm M² 9.10 88,700.00 807,170.00
3 Acian Dinding M² 194.53 56,300.00 10,952,039.00
4 Acian Kolom M² 29.90 56,300.00 1,683,370.00
5 Dinding keramik 20/45 (toilet) M² 54.39 - -
6 Dinding keramik 40/40 (Lift) M² 4.20 - -
7 Cubicle Toilet 1
M 19.28 - -
Sub Total - Pekerjaan Lantai - 2 15,130,629.00
HARGA SATUAN JUMLAH HARGA TOTAL HARGA
NO URAIAN PEKERJAAN SAT. VOLUME
( Rp ) ( Rp ) ( Rp )
1 2 3 4 5 6 7

I.3 Pekerjaan Lantai - 3


1 Pemasangan dinding HB20 campuran 1PC:4PP M² 271.15 371,000.00 100,596,650.00
2 Pemasangan plesteran 1PC:4PP tebal 10 mm M² 542.30 88,700.00 48,102,010.00
3 Acian Dinding M² 487.91 56,300.00 27,469,333.00
4 Acian Kolom M² 236.91 56,300.00 13,338,033.00
5 Dinding keramik 20/45 (toilet) M² 54.39 - -
6 Dinding keramik 40/40 (Lift) M² 4.20 - -
7 Kolom praktis beton bertulang (11 x 11) cm 1
M 175.00 - -
8 Balok Latei beton bertulang (11 x 15) cm 1
M 56.00 - -
9 Cubicle Toilet 1
M 19.28 - -
Sub Total - Lantai 3 189,506,026.00
I.4 Pekerjaan Lantai - 4
1 Pemasangan dinding HB20 campuran 1PC:4PP M² 376.94 371,000.00 139,844,740.00
2 Pemasangan plesteran 1PC:4PP tebal 10 mm M² 699.50 88,700.00 62,045,650.00
3 Acian Dinding M² 699.50 56,300.00 39,381,850.00
4 Acian Kolom M² 236.91 56,300.00 13,338,033.00
5 Dinding keramik 20/45 (toilet) M² 54.39 - -
6 Dinding keramik 40/40 (Lift) M² 4.20 - -
7 Kolom praktis beton bertulang (11 x 11) cm 1
M 175.00 - -
8 Balok Latei beton bertulang (11 x 15) cm 1
M 56.00 - -
9 Cubicle Toilet 1
M 19.28 - -
Sub Total - Lantai 4 254,610,273.00
I.5 Pekerjaan Lantai - Atas
1 Pemasangan dinding HB20 campuran 1PC:4PP M² 168.98 371,000.00 62,691,580.00
2 Pemasangan plesteran 1PC:4PP tebal 10 mm M² 337.96 88,700.00 29,977,052.00
3 Acian Dinding M² 337.96 56,300.00 19,027,148.00
4 Kolom praktis beton bertulang (11 x 11) cm 1
M 54.00 - -
5 Ringbalk beton bertulang (11 x 11) cm 1
M 56.00 - -

Sub Total - Lantai Atas 111,695,780.00


TOTAL C.I - PEKERJAAN PASANGAN & DINDING 572,670,168.00

II PEKERJAAN KUSEN, PINTU & JENDELA ALUMINIUM


(Lengkap dengan Kunci, Engsel + Kaca & Accessories) terpasang
II.1 Pekerjaan Lantai - 1
1 Kusen pintu Type P2 (4 Unit)
-Kusen Pintu Allumunium uk 4" x 1 3/4" m' 22.00 - -
-Frame Daun Pintu Alluminium m' 28.20 - -
-Spandril plapond aluminium m² 4.28 - -
-Engsel Pintu bh 12.00 - -
-Kunci Pintu bh 4.00 - -
2 Kusen pintu Type P2a (8 Unit)
-Kusen Pintu Allumunium uk 4" x 1 3/4" m' 40.80 - -
-Frame Daun Pintu Alluminium m' 43.20 - -
-Spandril plapond aluminium m² 8.00 - -
-Engsel Pintu bh 24.00 - -
-Kunci Pintu bh 8.00 - -
3 Kusen jendela Type BV (10 Unit)
-Kusen aluminium 4" YKK YS1 m' 9.40 - -
-Frame Daun Jendela Allumunium m' 6.00 - -
-Kaca Panasap 5 mm m2 1.06 - -
-Engsel Casement 10" Deksson psg 20.00 - -
-Rambuncis bh 10.00 - -
Sub Total - Lantai 1 -
II.2 Pekerjaan Lantai - 2
1 Kusen pintu Type P1 (6 Unit)
-Kusen Pintu Allumunium uk 4" x 1 3/4" m' 35.40 - -
-Frame Daun Pintu Alluminium m' 74.10 - -
-Kaca t = 5 mm m² 4.01 - -
-Engsel Pintu bh 36.00 - -
HARGA SATUAN JUMLAH HARGA TOTAL HARGA
NO URAIAN PEKERJAAN SAT. VOLUME
( Rp ) ( Rp ) ( Rp )
1 2 3 4 5 6 7

-Kunci Pintu bh 6.00 - -


-Espagnollete Tanam psg 6.00 - -
-Door Closer Fino 457 12FB SAS bh 12.00 - -

2 Kusen pintu Type P1a (9 Unit)


-Kusen Pintu Allumunium uk 4" x 1 3/4" m' 47.70 - -
-Frame Daun Pintu Alluminium m' 54.81 - -
-Kaca t = 5 mm m² 9.65 - -
-Engsel Pintu bh 27.00 - -
-Kunci Pintu bh 9.00 - -
-Door Closer Fino 457 12FB SAS bh 9.00 - -

3 Kusen pintu Type P2 (4 Unit)


-Kusen Pintu Allumunium uk 4" x 1 3/4" m' 22.00 - -
-Frame Daun Pintu Alluminium m' 28.20 - -
-Spandril plapond aluminium m² 4.28 - -
-Engsel Pintu bh 12.00 - -
-Kunci Pintu bh 4.00 - -

4 Kusen pintu Type P2a (8 Unit)


-Kusen Pintu Allumunium uk 4" x 1 3/4" m' 40.80 - -
-Frame Daun Pintu Alluminium m' 43.20 - -
-Spandril plapond aluminium m² 8.00 - -
-Engsel Pintu bh 24.00 - -
-Kunci Pintu bh 8.00 - -

5 Kusen jendela Type J1 (26 Unit)


-Kusen aluminium 4" YKK YS1 m' 115.28 - -
-Frame Jendela Allumunium m² 235.56 - -
-Kaca Panasap 5 mm m² 31.20 - -
-Engsel Casement 10" Deksson psg 156.00 - -

6 Kusen jendela Type J3 (9 Unit)


-Kusen aluminium 4" YKK YS1 m' 63.00 - -
-Kaca Panasap 5 mm m² 34.20 - -

7 Kusen jendela Type BV (10 Unit)


-Kusen aluminium 4" YKK YS1 m' 9.40 - -
-Frame Jendela Allumunium m' 16.80 - -
-Kaca Panasap 5 mm m2 1.06 - -
-Engsel Casement 10" Deksson psg 20.00 - -
- Rambuncis bh 10.00 - -

8 Dinding partisi gypsum rangka baja ringan M2 157.22 - -


Sub Total - Lantai 2 -
II.3 Pekerjaan Lantai - 3
1 Kusen pintu Type P1 (6 Unit)
-Kusen Pintu Allumunium uk 4" x 1 3/4" m' 35.40 - -
-Frame Daun Pintu Alluminium m' 74.10 - -
-Kaca t = 5 mm m² 4.01 - -
-Engsel Pintu bh 36.00 - -
-Kunci Pintu bh 6.00 - -
-Espagnollete Tanam psg 6.00 - -
-Door Closer Fino 457 12FB SAS bh 12.00 - -
HARGA SATUAN JUMLAH HARGA TOTAL HARGA
NO URAIAN PEKERJAAN SAT. VOLUME
( Rp ) ( Rp ) ( Rp )
1 2 3 4 5 6 7

2 Kusen pintu Type P1a (9 Unit)


-Kusen Pintu Allumunium uk 4" x 1 3/4" m' 47.70 - -
-Frame Daun Pintu Alluminium m' 54.81 - -
-Kaca t = 5 mm m² 9.65 - -
-Engsel Pintu bh 27.00 - -
-Kunci Pintu bh 9.00 - -
-Door Closer Fino 457 12FB SAS bh 9.00 - -

3 Kusen pintu Type P2 (4 Unit)


-Kusen Pintu Allumunium uk 4" x 1 3/4" m' 22.00 - -
-Frame Daun Pintu Alluminium m' 28.20 - -
-Spandril plapond aluminium m² 4.28 - -
-Engsel Pintu bh 12.00 - -
-Kunci Pintu bh 4.00 - -

4 Kusen pintu Type P2a (8 Unit)


-Kusen Pintu Allumunium uk 4" x 1 3/4" m' 40.80 - -
-Frame Daun Pintu Alluminium m' 43.20 - -
-Spandril plapond aluminium m² 8.00 - -
-Engsel Pintu bh 24.00 - -
-Kunci Pintu bh 8.00 - -

5 Kusen jendela Type J1 (26 Unit)


-Kusen aluminium 4" YKK YS1 m' 115.28 - -
-Frame Jendela Allumunium m² 235.56 - -
-Kaca Panasap 5 mm m² 31.20 - -
-Engsel Casement 10" Deksson psg 156.00 - -
-Rambuncis bh 78.00 - -

6 Kusen jendela Type J3 (9 Unit)


-Kusen aluminium 4" YKK YS1 m' 63.00 - -
-Kaca Panasap 5 mm m² 34.20 - -

7 Kusen jendela Type BV (10 Unit)


-Kusen aluminium 4" YKK YS1 m' 9.40 - -
-Frame Jendela Allumunium m' 16.80 - -
-Kaca Panasap 5 mm m2 1.06 - -
-Engsel Casement 10" Deksson psg 20.00 - -
- Rambuncis bh 10.00 - -

8 Dinding partisi gypsum rangka baja ringan M2 157.22 - -


Sub Total - Lantai 3 -
II.4 Pekerjaan Lantai - 4
1 Kusen pintu Type P1 (6 Unit)
-Kusen Pintu Allumunium uk 4" x 1 3/4" m' 35.40 - -
-Frame Daun Pintu Alluminium m' 74.10 - -
-Kaca t = 5 mm m² 4.01 - -
-Engsel Pintu bh 36.00 - -
-Kunci Pintu bh 6.00 - -
-Espagnollete Tanam psg 6.00 - -
-Door Closer Fino 457 12FB SAS bh 12.00 - -

2 Kusen pintu Type P1a (9 Unit)


-Kusen Pintu Allumunium uk 4" x 1 3/4" m' 47.70 - -
-Frame Daun Pintu Alluminium m' 54.81 - -
-Kaca t = 5 mm m² 9.65 - -
-Engsel Pintu bh 27.00 - -
-Kunci Pintu bh 9.00 - -
-Door Closer Fino 457 12FB SAS bh 9.00 - -
HARGA SATUAN JUMLAH HARGA TOTAL HARGA
NO URAIAN PEKERJAAN SAT. VOLUME
( Rp ) ( Rp ) ( Rp )
1 2 3 4 5 6 7

3 Kusen pintu Type P2 (4 Unit)


-Kusen Pintu Allumunium uk 4" x 1 3/4" m' 22.00 - -
-Frame Daun Pintu Alluminium m' 28.20 - -
-Spandril plapond aluminium m² 4.28 - -
-Engsel Pintu bh 12.00 - -
-Kunci Pintu bh 4.00 - -

4 Kusen pintu Type P2a (8 Unit)


-Kusen Pintu Allumunium uk 4" x 1 3/4" m' 40.80 - -
-Frame Daun Pintu Alluminium m' 43.20 - -
-Spandril plapond aluminium m² 8.00 - -
-Engsel Pintu bh 24.00 - -
-Kunci Pintu bh 8.00 - -

5 Kusen pintu Type P4 (Pintu Besi Teralis) (1 Unit) m² 1.68 - -

6 Kusen jendela Type J1 (26 Unit)


-Kusen aluminium 4" YKK YS1 m' 115.28 - -
-Frame Jendela Allumunium m² 235.56 - -
-Kaca Panasap 5 mm m² 31.20 - -
-Engsel Casement 10" Deksson psg 156.00 - -
-Rambuncis bh 78.00 - -

7 Kusen jendela Type J3 (9 Unit)


-Kusen aluminium 4" YKK YS1 m' 63.00 - -
-Kaca Panasap 5 mm m² 34.20 - -

8 Kusen jendela Type BV (10 Unit)


-Kusen aluminium 4" YKK YS1 m' 9.40 - -
-Frame Jendela Allumunium m' 16.80 - -
-Kaca Panasap 5 mm m2 1.06 - -
-Engsel Casement 10" Deksson psg 20.00 - -
- Rambuncis bh 10.00 - -

9 Dinding partisi gypsum rangka baja ringan M2 157.22 - -


Sub Total - Lantai 4 -
II.5 Pekerjaan Lantai - Atap
1 Kusen pintu Type P1 (1 Unit)
-Kusen Pintu Allumunium uk 4" x 1 3/4" m' 5.90 - -
-Frame Daun Pintu Alluminium m' 12.35 - -
-Kaca t = 5 mm m² 0.67 - -
-Engsel Pintu bh 6.00 - -
-Kunci Pintu bh 1.00 - -
-Espagnollete Tanam psg 1.00 - -
-Door Closer Fino 457 12FB SAS bh 2.00 - -

2 Kusen pintu Type P2 (1 Unit)


-Kusen Pintu Allumunium uk 4" x 1 3/4" m' 5.50 - -
-Frame Daun Pintu Alluminium m' 7.05 - -
-Spandril plapond aluminium m² 1.85 - -
-Engsel Pintu bh 3.00 - -
-Kunci Pintu bh 1.00 - -

3 Kusen jendela Type J1 ( 1 Unit)


-Kusen aluminium 4" YKK YS1 m' 8.28 - -
-Frame Jendela Allumunium m² 9.06 - -
-Kaca Panasap 5 mm m² 1.20 - -
-Engsel Casement 10" Deksson psg 6.00 - -
-Rambuncis bh 3.00 - -
HARGA SATUAN JUMLAH HARGA TOTAL HARGA
NO URAIAN PEKERJAAN SAT. VOLUME
( Rp ) ( Rp ) ( Rp )
1 2 3 4 5 6 7

4 Kusen jendela Type J2 (16 Unit)


- Kusen aluminium 4" YKK YS1 m' 28.80 - -
- Frame Jendela Allumunium m² 38.40 - -
- Kaca Panasap 5 mm m² 4.32 - -
- Engsel Casement 10" Deksson psg 32.00 - -
- Rambuncis bh 32.00 - -

5 Kusen jendela Type BV (2 Unit)


-Kusen aluminium 4" YKK YS1 m' 4.40 - -
-Frame Jendela Allumunium m' 3.36 - -
-Kaca Panasap 5 mm m2 0.21 - -
-Engsel Casement 10" Deksson psg 4.00 - -
- Rambuncis bh 2.00 - -

6 Dinding partisi kalsiboard rangka baja ringan M2 74.72 - -


Sub Total - Lantai Atap -
TOTAL .C.II PEKERJAAN KUSEN, PINTU & JENDELA ALUMINIUM -

III PEKERJAAN LANTAI


III.1 Pekerjaan Lantai - 1
1 Lantai Keramik 400x400 ( Nonslip ) M² 39.55 307,700.00 12,169,535.00
2 Lantai Keramik 400x400 ( Tangga ) M² 15.71 307,700.00 4,833,967.00
3 Pas. Stepnoshing keramik 1
M 27.00 117,100.00 3,161,700.00
4 Waterproofing & Screed beton Pit Lift M² 42.72 - -
Sub Total - Lantai 1 20,165,202.00
III.2 Pekerjaan Lantai - 2
1 Lantai Keramik 400x400 M² 112.35 - -
2 Lantai vynil ukuran 0,8 cm x 20 cm x 120 cm M² 376.74 - -
3 Lantai Keramik 400x400 ( Nonslip ) M² 39.55 - -
4 Pas.Plint Keramik 10 x 40 1
M 147.03 44,400.00 6,528,132.00
5 Lantai Keramik 400x400 ( Tangga ) M² 15.71 307,700.00 4,833,967.00
6 Pas.nosing keramik 1
M 27.00 117,100.00 3,161,700.00
7 Waterproofing & Screed dak beton M² 39.43 - -
Sub Total - Lantai 2 14,523,799.00
III.3 Pekerjaan Lantai - 3
1 Lantai Keramik 400x400 M² 112.35 307,700.00 34,570,095.00
2 Lantai vynil ukuran 0,8 cm x 20 cm x 120 cm M² 376.74 - -
3 Lantai Keramik 400x400 ( Nonslip ) M² 39.55 307,700.00 12,169,535.00
4 Pas.Plint Keramik 10 x 40 1
M 147.03 44,400.00 6,528,132.00
5 Lantai Keramik 400x400 ( Tangga ) M² 15.71 307,700.00 4,833,967.00
6 Pas.nosing keramik 1
M 27.00 117,100.00 3,161,700.00
7 Waterproofing & Screed dak beton M² 39.43 - -
Sub Total - Lantai 3 61,263,429.00
III.4 Pekerjaan Lantai - 4.
1 Lantai Keramik 400x400 M² 112.35 307,700.00 34,570,095.00
2 Lantai vynil ukuran 0,8 cm x 20 cm x 120 cm M² 376.74 - -
3 Lantai Keramik 400x400 ( Nonslip ) M² 39.55 307,700.00 12,169,535.00
4 Pas.Plint Keramik 10 x 40 1
M 147.03 44,400.00 6,528,132.00
5 Lantai Keramik 400x400 ( Tangga ) M² 15.71 307,700.00 4,833,967.00
6 Pas.nosing keramik 1
M 27.00 117,100.00 3,161,700.00
7 Waterproofing & Screed dak beton M² 39.43 - -
Sub Total - Lantai 4 61,263,429.00
III.5 Pekerjaan Lantai - RL.
1 Screed Lantai ( Tebal 3 cm ) M² 258.21 - -
2 Waterproofing M² 56.63 - -
Sub Total - Lantai RL -
TOTAL C.III PEKERJAAN LANTAI : 157,215,859.00
HARGA SATUAN JUMLAH HARGA TOTAL HARGA
NO URAIAN PEKERJAAN SAT. VOLUME
( Rp ) ( Rp ) ( Rp )
1 2 3 4 5 6 7

IV PEKERJAAN PLAFOND
IV.1 Pekerjaan Lantai - 1
1 Pas.Plafond Calsiboard 4,5 mm M² 39.55 - -
2 Rangka Plafond Besi Hollow Modul 60x60 cm M² 39.55 - -
3 List kayu + fin.cat 1
M 44.96 - -
Sub Total - Lantai 1 -
IV.2 Pekerjaan Lantai - 2
1 Plafond Gypsum board t = 9 mm M² 376.74 - -
2 Rangka Plafond Besi Hollow Modul 60x60 cm M² 376.74 - -
3 Pas.Plafond Calsiboard 4,5 mm M² 151.90 - -
4 Rangka Plafond Besi Hollow Modul 60x60 cm M² 151.90 - -
5 Pas.Cornice Gypsum / List Gypsum Standart 1
M 206.48 32,600.00 6,731,248.00
6 List kayu + fin.cat 1
M 44.96 - -
Sub Total - Lantai 2 6,731,248.00
IV.3 Pekerjaan Lantai - 3
1 Plafond Gypsum board t = 9 mm M² 376.74 - -
2 Rangka Plafond Besi Hollow Modul 60x60 cm M² 376.74 - -
3 Pas.Plafond Calsiboard 4,5 mm M² 151.90 - -
4 Rangka Plafond Besi Hollow Modul 60x60 cm M² 151.90 - -
5 Pas.Cornice Gypsum / List Gypsum 1
M 206.48 - -
6 List kayu + fin.cat 1
M 44.96 - -
Sub Total - Lantai 3 -
IV.4 Pekerjaan Lantai - 4
1 Plafond Gypsum board t = 9 mm M² 376.74 - -
2 Rangka Plafond Besi Hollow Modul 60x60 cm M² 376.74 - -
3 Pas.Plafond Calsiboard 4,5 mm M² 151.90 - -
4 Rangka Plafond Besi Hollow Modul 60x60 cm M² 151.90 - -
5 Pas.Cornice Gypsum / List Gypsum 1
M 206.48 32,600.00 6,731,248.00
6 List kayu + fin.cat 1
M 44.96 - -
Sub Total - Lantai 4 6,731,248.00
TOTAL C.IV PEKERJAAN PLAFOND 13,462,496.00

V PEKERJAAN SANITAIR
V.1 Pekerjaan Lantai - 1
1 Closet duduk Unit 8.00 - -
2 Wastafel Unit 4.00 - -
3 Meja Wastafel Unit 2.00 - -
4 Dinding Sekat Urinoir Unit 3.00 - -
5 Cermin 600x900 Unit 2.00 - -
6 Urinoir Unit 3.00 - -
7 Jet Washer Unit 8.00 - -
8 Kran dinding Unit 4.00 - -
9 Floor drain Unit 12.00 - -
Sub Total - Lantai 1 -
V.2 Pekerjaan Lantai - 2
1 Closet duduk Unit 8.00 - -
2 Wastafel Unit 4.00 - -
3 Meja Wastafel Unit 2.00 - -
4 Dinding Sekat Urinoir Unit 3.00 - -
5 Cermin 600x900 Unit 2.00 - -
6 Urinoir Unit 3.00 - -
7 Jet Washer Unit 8.00 - -
8 Kran dinding Unit 4.00 - -
9 Floor drain Unit 12.00 - -
Sub Total - Lantai 2 -
V.3 Pekerjaan Lantai - 3
1 Closet duduk Unit 8.00 - -
2 Wastafel Unit 4.00 - -
3 Meja Wastafel Unit 2.00 - -
HARGA SATUAN JUMLAH HARGA TOTAL HARGA
NO URAIAN PEKERJAAN SAT. VOLUME
( Rp ) ( Rp ) ( Rp )
1 2 3 4 5 6 7

4 Dinding Sekat Urinoir Unit 3.00 - -


5 Cermin 600x900 Unit 2.00 - -
6 Urinoir Unit 3.00 - -
7 Jet Washer Unit 8.00 - -
8 Kran dinding Unit 4.00 - -
9 Floor drain Unit 12.00 - -
Sub Total - Lantai 3 -
V.4 Pekerjaan Lantai - 4
1 Closet duduk Unit 8.00 - -
2 Wastafel Unit 4.00 - -
3 Meja Wastafel Unit 2.00 - -
4 Dinding Sekat Urinoir Unit 3.00 - -
5 Cermin 600x900 Unit 2.00 - -
6 Urinoir Unit 3.00 - -
7 Jet Washer Unit 8.00 - -
8 Kran dinding Unit 4.00 - -
9 Floor drain Unit 12.00 - -
Sub Total - Lantai 4 -
V.5 Pekerjaan Lantai - RL.
1 Roof drain Bh 6.00 - -
Sub Total - Lantai RL -
TOTAL C.V PEKERJAAN SANITAIR : -

VI PEKERJAAN PENGECATAN / FINISHING


VI.1 Pekerjaan Lantai - 1
1 Pengecatan dinding Luar M² 131.96 - -
2 Pengecatan dinding Dalam M² 43.60 - -
3 Pengecatan Kolom M² 10.08 - -
Sub Total - Lantai 1 -
VI.2 Pekerjaan Lantai - 2
1 Pengecatan dinding Luar M² 543.56 - -
2 Pengecatan dinding Dalam M² 715.99 - -
3 Pengecatan plafond M² 528.64 - -
4 Pengecatan Kolom M² 93.38 - -
Sub Total - Lantai 2 -
VI.3 Pekerjaan Lantai - 3
1 Pengecatan dinding M² 543.56 - -
2 Pengecatan dinding Dalam M² 715.99 - -
3 Pengecatan plafond M² 528.64 - -
4 Pengecatan Kolom M² 93.38 - -
Sub Total - Lantai 3 -
VI.4 Pekerjaan Lantai - 4
1 Pengecatan dinding M² 543.56 - -
2 Pengecatan dinding Dalam M² 715.99 - -
3 Pengecatan plafond M² 528.64 - -
4 Pengecatan Kolom M² 93.38 - -
Sub Total - Lantai 4 -
VI.5 Pekerjaan Lantai - ATAP
1 Pengecatan dinding M² 168.98 - -
2 Pengecatan dinding Dalam M² 243.70 - -
Sub Total - Lantai ATAP -
TOTAL - VI. PEKERJAAN PENGECATAN / FINISHING -

VII PEKERJAAN ATAP


1 Atap ex Alcobond/colourbond - ACP M² 1,189.70 - -
2 Pengecatan Konstruksi atap (rangka pipa) M² 317.75 - -
TOTAL C.VII. PEKERJAAN ATAP -

VIII PEKERJAAN RAILLING


1 Railling Tangga 1
M 61.60 - -
HARGA SATUAN JUMLAH HARGA TOTAL HARGA
NO URAIAN PEKERJAAN SAT. VOLUME
( Rp ) ( Rp ) ( Rp )
1 2 3 4 5 6 7

2 Railling Pagar Selasar 1


M 143.10 - -
3 Pemasangan dinding HB20 campuran 1PC:4PP M² 59.77 371,000.00 22,174,670.00
4 Pemasangan plesteran 1PC:4PP tebal 10 mm M² 119.54 88,700.00 10,603,198.00
5 Acian Dinding Pas Bata Ringan M² 119.54 - -
6 Ringbalk beton bertulang (11 x 11) cm M´ 127.17 - -
TOTAL C.VIII PEKERJAAN RAILLING 32,777,868.00

IX PEKERJAAN LAIN - LAIN


1 Pekerjaan rabat keliling t = 5 cm, f'c = 14,5 Mpa 3
M 4.42 - -
2 Bak kontrol 45 cm x 45 cm bh 4.00 - -
3 Saluran 1/2 dia.30 cm 1
M 34.00 - -
4 Pek. Curtain Wall Tempered ( Tangga / Top Floor ) M² 533.41 - -
(Kaca , t = 8 mm, rangka aluminium)
5 Dinding ACP M² 697.71 - -
6 Beton Penutup Listplank Uk. ( 10 cm x 20 cm ) 1
M 127.17 - -
7 Reling Disabilitas Toilet (pipa standlees Ø 2 " ) 1
M 20.00 - -
8 Pekerjaan Grill Besi ( Ruang Shaft ) 1
M 10.44 - -
9 Pembuatan Ramp Disabilitas
- Pemasangan dinding HB20 campuran 1PC:4PP M² 9.15 371,000.00 3,394,650.00
- Pemasangan plesteran 1PC:4PP tebal 10 mm M² 9.15 88,700.00 811,605.00
- Timbunan Tanah 3
M 1.68 - -
- Urugan Pasir 3
M 0.68 174,400.00 118,592.00
- Besi Beton Ø 10 - 15 cm kg 72.33 - -
- Begesting M² 11.06 - -
- Cor beton mutu fc 16,9 Mpa M³ 1.02 - -
- Keramik Lantai 40/40 (non slip) M² 8.16 - -
- Relling Standlisteel M' 12.75 - -
TOTAL C.IX PEKERJAAN LAIN - LAIN 4,324,847.00

X PEKERJAAN BANGUNAN LIFT


1 Pemasangan dinding HB20 campuran 1PC:4PP M² 94.20 371,000.00 34,948,200.00
2 Pemasangan plesteran 1PC:4PP tebal 10 mm M² 188.40 88,700.00 16,711,080.00
3 Acian Dinding + Balok M² 103.56 56,300.00 5,830,428.00
4 Acian Kolom M² 56.00 56,300.00 3,152,800.00
5 Pengecatan dinding + Balok M² 103.56 - -
6 Pengecatan Kolom M² 56.00 - -
TOTAL 3.X PEKERJAAN BANGUNAN LIFT 60,642,508.00

XI PEKERJAAN GROUND TANK, RUMAH GENSET DAN RUANG POMPA


XI.1 Pekerjaan Ground Tank
XI.1a Pekerjaan Galian dan Urugan
1 Galian 3
M 103.32 85,640.00 8,848,324.80
2 Urugan pasir dibawah lantai 3
M 2.10 174,400.00 366,240.00
3 Pemadatan tanah dasar dibawah lantai M² 42.00 - -
Sub Total - Pekerjaan Galian dan Urugan 9,214,564.80
XI.1b Pekerjaan Struktur
Ground Structure
1 Pekerjaan sloof
Sloof type S1 30 x 50 cm (bawah)
- Pembesian Kg 218.83 7,600.00 1,663,108.00
- Bekesting / Cetakan Untuk Sloof M² 20.80 - -
- Beton fc' 26,4 MPa M³ 3.12 - -
2 Ringbalk 30 x 50 cm
- Pembesian Kg 218.83 7,600.00 1,663,108.00
- Bekesting / Cetakan Untuk Sloof M² 27.04 - -
- Beton fc' 26,4 MPa M³ 3.12 - -
3 Dinding Ground Structure
- Bekisting M² 54.08 - -
- Pembesian Kg 620.62 7,600.00 4,716,712.00
- Beton fc 26,4 Mpa 3
M 4.06 - -
HARGA SATUAN JUMLAH HARGA TOTAL HARGA
NO URAIAN PEKERJAAN SAT. VOLUME
( Rp ) ( Rp ) ( Rp )
1 2 3 4 5 6 7

4 Lantai Ground Structure


- Pembesian Kg 929.74 7,600.00 7,066,024.00
- Beton fc 26,4 Mpa 3
M 11.83 - -
5 Balok 20 x 30 cm
- Pembesian Kg 47.34 7,600.00 359,784.00
- Bekesting / Cetakan Untuk Balok M² 3.76 - -
- Beton fc' 26,4 MPa M³ 0.28 - -
6 Waterproofing & Screed M² 68.39 - -
7 Lantai Penutup Ground Structure
- Bekisting M² 33.39 - -
- Pembesian Kg 396.76 7,600.00 3,015,376.00
- Beton fc 26,4 Mpa 3
M 4.01 - -
8 Kolom 30 x 30 cm
- Bekisting M² 9.60 - -
- Pembesian Kg 128.02 7,600.00 972,952.00
- Beton fc 26,4 Mpa 3
M 0.72 - -
9 Pekerjaan dudukan genset
- Pembesian Kg 45.17 7,600.00 343,292.00
- Bekesting / Cetakan Untuk Sloof M² 2.38 - -
- Beton fc' 26,4 MPa 3
M 0.35 - -
10 Penutup Lubang Kontrol (Besi) M2 0.49 - -
11 Tangga service (pipa stainles steel)Ø 1,5 " M1 7.20 - -
Sub Total - Pekerjaan Struktur Pondasi, Beton dan Baja 19,800,356.00
TOTAL PEKERJAAN GROUND TANK 29,014,920.80
XI.2 Pekerjaan Rumah Genset dan Ruang Pompa
1 Pengukuran dan pemasangan bouwplank 1
M 28.00 - -
2 Pas. Batu Gunung camp. 1 pc : 4 ps 3
M 5.88 - -
3 Timbunan tanah 3
M 22.85 - -
4 Pemadatan timbunan 3
M 22.85 - -
5 Pekerjaan cor lantai t = 10 cm, f'c = 14,5 Mpa 3
M 2.20 - -
6 Pekerjaan rabat keliling t = 5 cm, f'c = 14,5 Mpa 3
M 1.19 - -
7 Pemasangan dinding HB20 campuran 1PC:4PP M² 86.46 371,000.00 32,076,660.00
8 Pemasangan plesteran 1PC:4PP tebal 10 mm M² 172.91 88,700.00 15,337,117.00
9 Acian Dinding M² 172.91 56,300.00 9,734,833.00
10 Sloof 15x20
- Beton fc 26,4 3
M 0.87 - -
- Pembesian Kg 233.66 7,600.00 1,775,816.00
- Begesting Sloof M² 8.74 - -
11 Kolom 15x15
- Beton fc 26,4 3
M 0.63 - -
- Pembesian Kg 166.29 7,600.00 1,263,804.00
- Begesting Kolom M² 16.80 - -
12 Ringbalk 15x15
- Beton fc 26,4 3
M 0.55 - -
- Pembesian Kg 146.61 7,600.00 1,114,236.00
- Begesting Ringbalk M² 12.04 - -
13 Pekerjaan Kusen dan Pintu
- Pintu Besi Unit 1.00 - -
- Jendela Jalusi Besi Unit 3.00 - -
14 Pekerjaan Plafond
- Plafond Gypsum board t = 9 mm + rangka hollow M² 24.00 - -
- Rangka Plafond Besi Hollow Modul 60x60 cm M² 24.00 - -
- Pas.Plafond Calsiboard 6 mm + rangka hollow M² 14.28 - -
15 - Rangka Plafond Besi Hollow Modul 60x60 cm M² 14.28 - -
Pekerjaan Lantai
- Urugan pasir 3
M 1.20 174,400.00 209,280.00
- Beton fc 26,4 lantai 3
M 2.40 - -
- Beton fc 26,4 pondasi genset 3
M 0.36 - -
16 Pekerjaan Grill Besi Penutup Kabel M1 3.73 - -
17 Pekerjaan Pengecatan M² 172.91 - -
HARGA SATUAN JUMLAH HARGA TOTAL HARGA
NO URAIAN PEKERJAAN SAT. VOLUME
( Rp ) ( Rp ) ( Rp )
1 2 3 4 5 6 7

18 Pekerjaan Atap
- Rangka Atap Baja Ringan M² 34.10 - -
- Penutup Atap M² 34.10 - -
- Pas. Lisplank M1 26.00 - -
19 Lampu Downlight 18 W (LED) bh 3.00 - -
17 Stop kontak bh 2.00 - -
18 Saklar tunggal bh 1.00 - -
19 Saklar ganda bh 2.00 - -
20 Instalasi lampu dalam pipa conduit 20 mm2 ttk 3.00 - -
21 Instalasi Stop kontak dinding dalam pipa conduit 20 mm2 ttk 2.00 - -
Sub Total - Pekerjaan Rumah Genset dan Ruang Pompa 61,511,746.00
TOTAL C.XI GROUND TANK, RUMAH POMPA DAN RUANG GENSET 90,526,666.80
TOTAL C (I+II+III+IV+V+VI+VII+VIII+IX+X+XI) PEKERJAAN ARSITEKTUR BANGUNAN 931,620,412.80

D PEKERJAAN ELEKTRIKAL
I PEKERJAAN ELEKTRIKAL GEDUNG
I.1 Pekerjaan Lantai - 1
2 Lampu Downlight 13 W (LED) bh 12.00 - -
4 Exhaust ceiling Fan bh 8.00 - -
9 Instalasi lampu dalam pipa conduit 20 mm2 ttk 12.00 - -
10 Instalasi Exhaust ceiling Fan ttk 8.00 - -
12 Panel LP-1 unit 1.00 - -
13 Panel AC-1 unit 1.00 - -
14 Panel Pompa Transfer unit 1.00 - -
15 Panel LVMDP+Kapasitor bank unit 1.00 - -
16 Panel ATS + AMF unit 1.00 - -
17 Kabel Power NYFGBY 4x95 mm2 m' 380.00 - -
18 Kabel Power NYY 4x16 mm2 m' 140.00 - -
19 Kabel Power NYY 4x6 mm2 m' 384.40 - -
20 Kabel Tray 200 x 100 m' 83.00 - -
21 Grounding tahanan 2 ohm lot 1.00 - -
22 Support dan material bantu ls 1.00 - -
Sub Total Pekerjaan Elektrikal Lantai - 1 -

I.2 Pekerjaan Lantai - 2


1 Lampu Downlight 18 W (LED) bh 59.00 - -
2 Lampu Downlight 13 W (LED) bh 12.00 - -
3 Lampu GMS 1x18 W (LED) bh 2.00 - -
4 Exhaust ceiling Fan bh 8.00 - -
5 Stop kontak bh 27.00 - -
6 Stop kontak Lantai bh 18.00 - -
7 Saklar tunggal bh 5.00 - -
8 Saklar ganda bh 14.00 - -
9 Instalasi lampu dalam pipa conduit 20 mm2 ttk 73.00 - -
10 Instalasi Exhaust ceiling Fan ttk 8.00 - -
11 Instalasi Stop kontak dinding dalam pipa conduit 20 mm2 ttk 27.00 - -
12 Instalasi Stop kontak lantai dalam kabel duct ttk 18.00 - -
13 Panel LP-2 unit 1.00 - -
14 Panel AC-2 unit 1.00 - -
15 Kabel Power NYY 4x16 mm2 m' 140.00 - -
16 Kabel Power NYY 4x6 mm2 m' 666.15 - -
17 Kabel Tray 200 x 100 m' 83.00 - -
18 Grounding lot 1.00 - -
19 Support dan material bantu ls 1.00 - -
Sub Total Pekerjaan Elektrikal Lantai - 2 -

I.3 Pekerjaan Lantai - 3


1 Lampu Downlight 18 W (LED) bh 59.00 - -
2 Lampu Downlight 13 W (LED) bh 12.00 - -
3 Lampu GMS 1x18 W (LED) bh 2.00 - -
HARGA SATUAN JUMLAH HARGA TOTAL HARGA
NO URAIAN PEKERJAAN SAT. VOLUME
( Rp ) ( Rp ) ( Rp )
1 2 3 4 5 6 7

4 Exhaust ceiling Fan bh 8.00 - -


5 Stop kontak bh 27.00 - -
6 Stop kontak lantai bh 18.00 - -
7 Saklar tunggal bh 5.00 - -
8 Saklar ganda bh 14.00 - -
9 Instalasi lampu dalam pipa conduit 20 mm2 ttk 73.00 - -
10 Instalasi Exhaust ceiling Fan ttk 8.00 - -
11 Instalasi Stop kontak dinding dalam pipa conduit 20 mm2 ttk 27.00 - -
12 Instalasi Stop kontak lantai dalam kabel duct ttk 18.00 - -
13 Panel LP-3 unit 1.00 - -
14 Panel AC-3 unit 1.00 - -
15 Kabel Power NYY 4x16 mm2 m' 140.00 - -
16 Kabel Power NYY 4x6 mm2 m' 666.15 - -
17 Kabel Tray 200 x 100 m' 83.00 - -
18 Grounding lot 1.00 - -
19 Support dan material bantu ls 1.00 - -
Sub Total Pekerjaan Elektrikal Lantai - 3 -

I.4 Pekerjaan Lantai - 4


1 Lampu Downlight 18 W (LED) bh 59.00 - -
2 Lampu Downlight 13 W (LED) bh 12.00 - -
3 Lampu GMS 1x18 W (LED) bh 2.00 - -
4 Exhaust ceiling Fan bh 8.00 - -
5 Stop kontak bh 27.00 - -
6 Stop kontak lantai bh 18.00 - -
7 Saklar tunggal bh 5.00 - -
8 Saklar ganda bh 14.00 - -
9 Instalasi lampu dalam pipa conduit 20 mm2 ttk 73.00 - -
10 Instalasi Exhaust ceiling Fan ttk 8.00 - -
11 Instalasi Stop kontak dinding dalam pipa conduit 20 mm2 ttk 27.00 - -
12 Instalasi Stop kontak lantai dalam kabel duct ttk 18.00 - -
13 Panel LP-4 unit 1.00 - -
14 Panel AC-4 unit 1.00 - -
15 Panel Lift unit 1.00 - -
16 Kabel Power NYY 4x16 mm2 m' 140.00 - -
17 Kabel Power NYY 4x6 mm2 m' 666.15 - -
18 Kabel Tray 200 x 100 m' 83.00 - -
19 Grounding lot 1.00 - -
20 Support dan material bantu ls 1.00 - -
Sub Total Pekerjaan Elektrikal Lantai - 4 -

I.5 Pekerjaan Lantai - Top


1 Lampu Downlight 18 W (LED) bh 21.00 - -
2 Stop kontak bh 12.00 - -
3 Saklar tunggal bh 1.00 - -
4 Saklar ganda bh 2.00 - -
5 Instalasi lampu dalam pipa conduit 20 mm2 ttk 21.00 - -
6 Instalasi Stop kontak dinding dalam pipa conduit 20 mm2 ttk 12.00 - -
7 Grounding lot 1.00 - -
8 Support dan material bantu ls 1.00 - -
Sub Total Pekerjaan Elektrikal Lantai - Top -
TOTAL D.I PEKERJAAN ELEKTRIKAL GEDUNG -

II PEKERJAAN PENANGKAL PETIR


1 Head Spitzen Penangkal petir non radio aktif unit 1.00 - -
2 Tiang penyangga dan dudukan unit 1.00 - -
3 Kabel NYY 1x50 mm2 m' 87.00 - -
4 Grounding tahanan 5 ohm lot 1.00 - -
5 Bak kontrol lot 1.00 - -
6 Material bantu ls 1.00 - -
HARGA SATUAN JUMLAH HARGA TOTAL HARGA
NO URAIAN PEKERJAAN SAT. VOLUME
( Rp ) ( Rp ) ( Rp )
1 2 3 4 5 6 7

7 Biaya perijinan Penangkal petir ls 1.00 - -


TOTAL D.II PEKERJAAN ELEKTRIKAL GEDUNG -

III PEKERJAAN JARINGAN LAN


III.1 Pekerjaan Lantai - 1
1 Instalasi data dengan kabel UTP Cat 6 dalam konduit ttk 64.00 - -
2 2 gang outlet data Rj 45 dinding bh 44.00 - -
3 2 gang outlet data Rj 45 lantai bh 20.00 - -
4 Switch hub 24 porth bh 1.00 - -
5 Wall Mount Rack unit 3.00 - -
PERALATAN UTAMA
6 Main Switch Router & Fire Wall unit 1.00 - -
7 Grounding tahanan 0.1 ohm lot 1.00 - -
8 Server : Xeon dual core. Ram 1Gb. 250 Gb SS Sata unit 1.00 - -
Sub Total Pekerjaan LAN Lantai - 1 -
III.2 Pekerjaan Lantai - 2
1 Instalasi data dengan kabel UTP Cat 6 dalam konduit ttk 64.00 - -
2 2 gang outlet data Rj 45 dinding bh 44.00 - -
3 2 gang outlet data Rj 45 lantai bh 20.00 - -
4 Switch hub 24 porth bh 3.00 - -
5 Wall Mount Rack unit 1.00 - -
Sub Total Pekerjaan LAN Lantai - 2 -
III.3 Pekerjaan Lantai - 3
1 Instalasi data dengan kabel UTP Cat 6 dalam konduit ttk 64.00 - -
2 2 gang outlet data Rj 45 dinding bh 44.00 - -
3 2 gang outlet data Rj 45 lantai bh 20.00 - -
4 Switch hub 24 porth bh 3.00 - -
5 Wall Mount Rack unit 1.00 - -
Sub Total Pekerjaan LAN Lantai - 3 -
III.4 Pekerjaan Lantai - 4
1 Instalasi data dengan kabel UTP Cat 6 dalam konduit ttk 64.00 - -
2 2 gang outlet data Rj 45 dinding bh 44.00 - -
3 2 gang outlet data Rj 45 lantai bh 20.00 - -
4 Switch hub 24 porth bh 3.00 - -
5 Wall Mount Rack unit 1.00 - -
Sub Total Pekerjaan LAN Lantai - 4 -
TOTAL D.III PEKERJAAN JARINGAN LAN -
TOTAL D.(I+II+III) ELEKTRIKAL -

E PEKERJAAN MEKANIKAL
I INSTALASI AIR BERSIH
I.1 Pekerjaan Lantai -1
1 Pipa PVC AW Ø 1" m' 80.00 - -
2 Pipa PVC AW Ø 3/4" m' 65.00 - -
3 Pipa PVC AW Ø 1" (external) m' 125.00 - -
4 Gate Valve Ø 1" bh 2.00 - -
5 Support , Fitting dan material bantu ls 1.00 - -
6 Pompa Transfer kap. 350ltr/mnt, head 40mtr bh 2.00 - -
7 Instalasi Pompa Transfer dan perlengkapanya ls 1.00 - -
8 Testing dan Comissioning ls 1.00 - -
Sub Total Pekerjaan Instalasi Air Bersih Lantai - 1 -

I.2 Pekerjaan Lantai -2


1 Pipa PVC AW Ø 1" m' 20.00 - -
2 Pipa PVC AW Ø 3/4" m' 65.00 - -
3 Gate Valve Ø 1" bh 2.00 - -
4 Support , Fitting dan material bantu ls 1.00 - -
5 Testing dan Comissioning ls 1.00 - -
Sub Total Pekerjaan Instalasi Air Bersih Lantai - 2 -
HARGA SATUAN JUMLAH HARGA TOTAL HARGA
NO URAIAN PEKERJAAN SAT. VOLUME
( Rp ) ( Rp ) ( Rp )
1 2 3 4 5 6 7

I.3 Pekerjaan Lantai -3


1 Pipa PVC AW Ø 1" m' 20.00 - -
2 Pipa PVC AW Ø 3/4" m' 65.00 - -
3 Gate Valve Ø 1" bh 2.00 - -
4 Support , Fitting dan material bantu ls 1.00 - -
5 Testing dan Comissioning ls 1.00 - -
Sub Total Pekerjaan Instalasi Air Bersih Lantai - 3 -

I.4 Pekerjaan Lantai -4


1 Pipa PVC AW Ø 1" m' 20.00 - -
2 Pipa PVC AW Ø 3/4" m' 65.00 - -
3 Gate Valve Ø 1" bh 2.00 - -
4 Support , Fitting dan material bantu ls 1.00 - -
5 Testing dan Comissioning ls 1.00 - -
Sub Total Pekerjaan Instalasi Air Bersih Lantai - 4 -

I.5 Pekerjaan Lantai -Atap dan Shaft


1 Pipa PVC AW Ø 1" m' 42.00 - -
2 Gate Valve Ø 1" bh 4.00 - -
3 Support , Fitting dan material bantu ls 1.00 - -
4 Roof tank 2.000ltr bh 2.00 - -
5 Pompa Boster berikut kelengkapanya bh 2.00 - -
6 Testing dan Comissioning lot 1.00 - -
Sub Total Pekerjaan Mekanikal Lantai - Atap dan Shaft -
TOTAL E. I PEKERJAAN INSTALASI AIR BERSIH -

II INSTALASI AIR KOTOR


II.1 Pekerjaan Lantai -1
1 Pipa PVC AW Ø 6" m' 18.00 - -
2 Pipa PVC AW Ø 4" m' 88.00 - -
3 Clean Out Ø 4" bh 2.00 - -
4 Clean Out Ø 3" bh 2.00 - -
5 Support , Fitting dan material bantu lot 1.00 - -
6 Biotech Kapasitas 15 m3 bh 2.00 - -
7 Galian Tanah m3 46.00 85,640.00 3,939,440.00
8 Pasir Urug m3 14.60 - -
9 Pondasi Batu Gunung m3 2.59 - -
10 Pemasangan dinding HB20 campuran 1PC:4PP m2 65.60 371,000.00 24,337,600.00
11 Cor Beton Penutup Atas m3 2.74 - -
12 Pembesian kg 160.68 7,600.00 1,221,168.00
13 Testing dan Comissioning lot 1.00 - -
Sub Total Pekerjaan Instalasi Air Kotor Lantai - 1 29,498,208.00

II.2 Pekerjaan Lantai -2


1 Pipa PVC AW Ø 4" m' 68.00 - -
3 Clean Out Ø 4" bh 2.00 - -
4 Clean Out Ø 3" bh 2.00 - -
5 Support , Fitting dan material bantu lot 1.00 - -
6 Testing dan Comissioning lot 1.00 - -
Sub Total Pekerjaan Instalasi Air Kotor Lantai - 2 -

II.3 Pekerjaan Lantai -3


1 Pipa PVC AW Ø 4" m' 68.00 - -
3 Clean Out Ø 4" bh 2.00 - -
4 Clean Out Ø 3" bh 2.00 - -
5 Support , Fitting dan material bantu lot 1.00 - -
6 Testing dan Comissioning lot 1.00 - -
Sub Total Pekerjaan Instalasi Air Kotor Lantai - 3 -

II.4 Pekerjaan Lantai -4


HARGA SATUAN JUMLAH HARGA TOTAL HARGA
NO URAIAN PEKERJAAN SAT. VOLUME
( Rp ) ( Rp ) ( Rp )
1 2 3 4 5 6 7

1 Pipa PVC AW Ø 4" m' 68.00 - -


3 Clean Out Ø 4" bh 2.00 - -
4 Clean Out Ø 3" bh 2.00 - -
5 Support , Fitting dan material bantu lot 1.00 - -
6 Testing dan Comissioning lot 1.00 - -
Sub Total Pekerjaan Instalasi Air Kotor Lantai - 4 -

II.5 Pekerjaan Lantai -Atap


1 Pipa PVC AW Ø 4" m' 169.20 - -
2 Support , Fitting dan material bantu lot 1.00 - -
Sub Total Pekerjaan Instalasi Air Kotor Lantai - Atap -
TOTAL E. II PEKERJAAN INSTALASI AIR KOTOR 29,498,208.00

III PEKERJAAN TATA UDARA


Pengadaan dan pemasangan air conditioning (AC) lengkap dengan
kabel daya, refrigerant berisolasi, pipa drain (kondensat)
dan perlengkapannya beserta pengetesan sistem dan instalasi.

III.1 Pekerjaan Lantai -2


1 Instalasi Air Conditioning (AC) 2,5 PK
a. Unit air conditioning (AC) : unit 8.00 - -
- Fan coil unit (FCU)
Tipe : wall mounted, single split system
Kapasitas : 22.500 BTUH
Servis: Ruang Kelas
Lokasi : lantai 2
- Condensing unit
Lokasi : outdoor lantai 2
a. Pipa refrigerant m 120.00 - -
b. Instalasi kabel daya : NYM 3 x 2,5 mm2 m 58.00 - -
c. Instalasi pipa drain/kondensat AC :
- Pipa drain/kondensat AC ø 20 mm m 25.00 - -
d. Fitting & aksesoris pipa drain/kondensat AC ls 1.00 - -
Testing & commissioning instalasi air conditioning (AC) lot 1.00 - -
Sub Total Pekerjaan Tata Udara Lantai - 2 -
III.2 Pekerjaan Lantai -3
1 Instalasi Air Conditioning (AC) 2,5 PK
a. Unit air conditioning (AC) : unit 8.00 - -
- Fan coil unit (FCU)
Tipe : wall mounted, single split system
Kapasitas : 22.500 BTUH
Servis : Ruang Kelas
Lokasi : lantai 3
- Condensing unit
Lokasi : outdoor lantai 3
a. Pipa refrigerant m 120.00 - -
b. Instalasi kabel daya : NYM 3 x 2,5 mm2 m 58.00 - -
c. Instalasi pipa drain/kondensat AC :
- Pipa drain/kondensat AC ø 20 mm m 25.00 - -
d. Fitting & aksesoris pipa drain/kondensat AC ls 1.00 - -
Testing & commissioning instalasi air conditioning (AC) lot 1.00 - -
Sub Total Pekerjaan Tata Udara Lantai - 3 -
III.3 Pekerjaan Lantai -4
1 Instalasi Air Conditioning (AC) 2,5 PK
a. Unit air conditioning (AC) : unit 8.00 - -
- Fan coil unit (FCU)
Tipe : wall mounted, single split system
Kapasitas : 22.500 BTUH
Servis : Ruang Kelas
Lokasi : lantai 4
HARGA SATUAN JUMLAH HARGA TOTAL HARGA
NO URAIAN PEKERJAAN SAT. VOLUME
( Rp ) ( Rp ) ( Rp )
1 2 3 4 5 6 7

- Condensing unit
Lokasi : outdoor lantai 4
a. Pipa refrigerant m 120.00 - -
b. Instalasi kabel daya : NYM 3 x 2,5 mm2 m 58.00 - -
c. Instalasi pipa drain/kondensat AC :
- Pipa drain/kondensat AC ø 20 mm m 25.00 - -
d. Fitting & aksesoris pipa drain/kondensat AC ls 1.00 - -
Testing & commissioning instalasi air conditioning (AC) lot 1.00 - -
Sub Total Pekerjaan Tata Udara Lantai -4 -
TOTAL E.III PEKERJAAN TATA UDARA -

IV PEKERJAAN PEMADAM KEBAKARAN


Pengadaan dan pemasangan Apar lengkap dengan
Tabung, Penggantung, serta MSDS (material safety data sheets)
dan perlengkapannya beserta pengetesan sistem dan instalasi.
IV.1 Pekerjaan Lantai 1
Jenis Apar Carbon dioxide/ C02 Unit 4.00 - -
Tipe : Carbon Dioxide (CO2) Portable
Model : SV – 230 C
Berat : 2 kg
Kelas : BC (Minyak, Solar, Bensin,Elektronik dan Listrik)

IV.2 Pekerjaan Lantai 2


Jenis Apar Carbon dioxide/ C02 Unit 4.00 - -
Tipe : Carbon Dioxide (CO2) Portable
Model : SV – 230 C
Berat : 2,3 kg
Kelas : BC (Minyak, Solar, Bensin,Elektronik dan Listrik)

IV.3 Pekerjaan Lantai 3


Jenis Apar Carbon dioxide/ C02 Unit 4.00 - -
Tipe : Carbon Dioxide (CO2) Portable
Model : SV – 230 C
Berat : 2,3 kg
Kelas : BC (Minyak, Solar, Bensin,Elektronik dan Listrik)

IV.4 Pekerjaan Lantai 4


Jenis Apar Carbon dioxide/ C02 Unit 4.00 - -
Tipe : Carbon Dioxide (CO2) Portable
Model : SV – 230 C
Berat : 2,3 kg
Kelas : BC (Minyak, Solar, Bensin,Elektronik dan Listrik)

TOTAL E.IV PEKERJAAN PEMADAM KEBAKARAN -

V PEKERJAAN LIFT ELEVATOR


Pengadaan lift unit 1.00 - -
Type : Lift Penumpang Type Standard
Fungsi : Passanger
Kapasitas : 1300 kg
Kecepatan : 60 mpm
Penggerak Kontrol : AC - VVF (Variable Voltage, Variable Freq)
Lantai yang dilayani : sesuai gambar
Tipe Pintu : Centre Opening
Sumber tenaga : AC 7,5 Kw,3phase,220/380V, 50 Hz
Sumber penerangan : : AC 1 Phase 220 v
Aplication Code : BS, ANSI code A17.1, JIS
Matrials & Wiring : BS, ANSI code A17.1, JIS

Pekerjaan Pendukung
HARGA SATUAN JUMLAH HARGA TOTAL HARGA
NO URAIAN PEKERJAAN SAT. VOLUME
( Rp ) ( Rp ) ( Rp )
1 2 3 4 5 6 7

separator beam IWF 200 ( berat per M minimal 20 kg ) kg 1,440.00 - -


kolom H Beam dudukan rel hoist way H Beam 100 ( per M min 14 Kg) kg 2,016.00 - -
Struktur besi untuk pintu Siku 60.60.4 kg 314.00 - -
Pasang AC 1/2 PK smart inverter panasonic Low Wattage unit 1.00 - -

Test Comisioning Ls 1.00 - -

TOTAL E.V PEKERJAAN LIFT ELEVATOR -

TOTAL E. (I+II+III+IV+V) MEKANIKAL 29,498,208.00


NO. URAIAN PEKERJAAN KODE SATUAN KOEF HARGA STUAN SUB. JUMLAH JUMLAH
1 2 3 4 5 6 7 8
A PEKERJAAN TANAH
1 m³ Galian Tanah Biasa s/d 1 m
Tenaga Kerja
Pekerja L.01 org/hr 0.550 Rp 137,242.34 Rp 75,483.29
Mandor L.04 org/hr 0.015 Rp 157,828.69 Rp 2,367.43
` Jumlah : Rp 77,850.72
Keuntungan 10% : Rp 7,785.07
Jumlah : Rp 85,635.79
Dibulatkan : Rp 85,640.00
1 m³ Galian Tanah Biasa s/d 2 m
Tenaga Kerja
Pekerja L.01 org/hr 0.700 Rp 137,242.34 Rp 96,069.64
Mandor L.04 org/hr 0.035 Rp 157,828.69 Rp 5,524.00
Jumlah : Rp 101,593.64
Keuntungan 10% : Rp 10,159.36
Jumlah : Rp 111,753.01
Dibulatkan : Rp 111,800.00
Mengurug Kembali 1 M³ Galian
Tenaga Kerja
Pekerja L.01 org/hr 0.500 Rp 137,242.34 Rp 68,621.17
Mandor L.04 org/hr 0.050 Rp 157,828.69 Rp 7,891.43
Jumlah : Rp 76,512.60
Keuntungan 10% : Rp 7,651.26
Jumlah : Rp 84,163.87
Dibulatkan : Rp 84,200.00
1 m³ Memadatkan Tanah Per 20 cm
Tenaga Kerja
Pekerja L.01 org/hr 0.500 Rp 137,242.34 Rp 68,621.17
Mandor L.04 org/hr 0.050 Rp 157,828.69 Rp 7,891.43
Jumlah : Rp 76,512.60
Keuntungan 10% : Rp 7,651.26
Jumlah : Rp 84,163.87
Dibulatkan : Rp 84,200.00
PENGURUGAN 1 M3 DENGAN PASIR URUG
Bahan Rp 115,823.45
Pasir urug m³ 1.200 Rp 96,519.54 Rp 115,823.45
Tenaga Kerja Rp 42,750.99
Pekerja L.01 org/hr 0.300 Rp 137,242.34 Rp 41,172.70
Mandor L.04 org/hr 0.010 Rp 157,828.69 Rp 1,578.29
Jumlah : Rp 158,574.44
Keuntungan 10% : Rp 15,857.44
Jumlah : Rp 174,431.88
Dibulatkan : Rp 174,400.00
1m3 Buangan tanah kearea site dengan jarak 100 m
Pekerja org 0.363 Rp 137,242.34 Rp 49,818.97
Mandor org 0.011 Rp 157,828.69 Rp 1,736.12
Jumlah : Rp 51,555.09
Keuntungan 10% : Rp 5,155.51
Jumlah : Rp 56,710.59
Dibulatkan : Rp 56,700.00
Pemadatan 1 m3 Tanah (Per 20 Cm)
Pekerja org 0.500 Rp 137,242.34 Rp 68,621.17
Mandor org 0.050 Rp 157,828.69 Rp 7,891.43
Jumlah : Rp 76,512.60
Keuntungan 10% : Rp 7,651.26
Jumlah : Rp 84,163.87
Dibulatkan : Rp 84,200.00
MEMANCANG 1 M3 ULIN 10/10 KEDALAMAN SAMPAI 2 M
Bahan Rp 185,000.00
Pemancangan m1 1.000 Rp 170,000.00 Rp 170,000.00
Handling tiang di lokasi proyek m1 1.000 Rp 15,000.00 Rp 15,000.00
Tenaga Kerja Rp 42,750.99
Pekerja org/hr 0.300 Rp 137,242.34 Rp 41,172.70
Mandor org/hr 0.010 Rp 157,828.69 Rp 1,578.29
Jumlah : Rp 227,750.99
Keuntungan 10% : Rp 22,775.10
Jumlah : Rp 250,526.09
Dibulatkan : Rp 250,500.00
NO. URAIAN KODE SATUAN KOEF HARGA STUAN SUB. JUMLAH JUMLAH
1 2 3 4 5 6 7 8

Pemasangan 1 m3 pondasi batu belah campuran 1SP : 3PP


Bahan Rp 441,481.86
Batu Belah 15 cm / 20 cm m³ 1.200 Rp 125,475.40 Rp 150,570.48
PC/Semen Kg 202.000 Rp 1,220.00 Rp 246,440.00
Pasir pasang m³ 0.485 Rp 91,693.56 Rp 44,471.38
Tenaga Kerja
Pekerja L.01 org/hr 1.500 Rp 137,242.34 Rp 205,863.51 Rp 354,085.24
Tukang Batu L.02 org/hr 0.750 Rp 166,063.23 Rp 124,547.42
Kepala Tukang L.03 org/hr 0.075 Rp 157,828.69 Rp 11,837.15
Mandor L.04 org/hr 0.075 Rp 157,828.69 Rp 11,837.15
Jumlah : Rp 795,567.10
Keuntungan 10% : Rp 79,556.71
Jumlah : Rp 875,123.81
Dibulatkan : Rp 875,100.00
A.3.2.1.2 Pemasangan 1 m3 pondasi batu belah campuran 1SP : 4PP
Bahan Rp 397,111.13
Batu Belah 15 cm / 20 cm m³ 1.200 Rp 125,475.40 Rp 150,570.48
PC/Semen Kg 163.00 Rp 1,220.00 Rp 198,860.00
Pasir pasang m³ 0.520 Rp 91,693.56 Rp 47,680.65
Tenaga Kerja
Pekerja L.01 org/hr 1.500 Rp 137,242.34 Rp 205,863.51 Rp 354,085.24
Tukang Batu L.02 org/hr 0.750 Rp 166,063.23 Rp 124,547.42
Kepala Tukang L.03 org/hr 0.075 Rp 157,828.69 Rp 11,837.15
Mandor L.04 org/hr 0.075 Rp 157,828.69 Rp 11,837.15
Jumlah : Rp 751,196.37
Keuntungan 10% : Rp 75,119.64
Jumlah : Rp 826,316.01
Dibulatkan : Rp 826,300.00
A.3.2.1.9 (K3) Pemasangan 1 m3 batu kosong (anstamping)
Bahan Rp 192,266.92
Batu Belah 15 cm / 20 cm m³ 1.200 Rp 125,475.40 Rp 150,570.48
Pasir urug m³ 0.432 Rp 96,519.54 Rp 41,696.44
Tenaga Kerja Rp 184,124.32
Pekerja L.01 org/hr 0.780 Rp 137,242.34 Rp 107,049.03
Tukang Batu L.02 org/hr 0.390 Rp 166,063.23 Rp 64,764.66
Kepala Tukang L.03 org/hr 0.039 Rp 157,828.69 Rp 6,155.32
Mandor L.04 org/hr 0.039 Rp 157,828.69 Rp 6,155.32
Jumlah : Rp 376,391.25
Keuntungan 10% : Rp 37,639.12
Jumlah : Rp 414,030.37
Dibulatkan : Rp 414,000.00

ANALISIS HARGA SATUAN PEKERJAAN BIDANG PEKERJAAN UMUMNOMOR : 28/PRT/M/2016


NO. URAIAN KODE SATUAN KOEF HARGA STUAN SUB. JUMLAH JUMLAH
1 2 3 4 5 6 7 8

PEKERJAAN 1 M1 BORE PILE Ø 300 MM DAN PENGECORAN K-250


Bahan Rp 227,962.63
Beton K-250 m3 0.071 Rp 472,837.29 Rp 33,429.60
Baja Tulangan Kg 10.603 Rp 4,880.20 Rp 51,744.29
Papan perancah m2 0.943 Rp 151,500.00 Rp 142,788.75
ALAT Rp 5,800.04
Bore Pile Jam 0.002 Rp 216,200.00 Rp 367.54
Concr. Pump Jam 0.011 Rp 512,500.00 Rp 5,432.50
Tenaga Kerja Rp 2,457.32
Pekerja L.01 org/hr 0.010 Rp 137,242.34 Rp 1,358.70
Tukang Batu L.02 org/hr 0.005 Rp 166,063.23 Rp 830.32
Mandor L.04 org/hr 0.002 Rp 157,828.69 Rp 268.31
Jumlah : Rp 230,419.96
Keuntungan 10% : Rp 23,042.00
Jumlah : Rp 253,461.95
Dibulatkan : Rp 253,500.00

ANALISIS HARGA SATUAN PEKERJAAN BIDANG PEKERJAAN UMUMNOMOR : 28/PRT/M/2016


NO. URAIAN KOEF SATUAN HARGA STUAN SUB. Jumlah : JUMLAH
1 2 2 3 4 5 6

1 1 m³ Membuat beton mutu fc=7,4 Mpa (K 100), slum (12 ± 2) cm, w/c = 0.87
Bahan Rp 526,085.99
Portland Cement 247.000 kg Rp 1,220.00 Rp 301,340.00
Pasir Beton 0.869 m3 Rp 108,584.48 Rp 94,359.91
Kerikil (maksimum 30 mm) 0.999 m3 Rp 130,301.38 Rp 130,171.08
Air 0.215 Liter Rp 1,000.00 Rp 215.00
Tenaga Kerja Rp 289,636.24
Pekerja 1.650 org/hr Rp 137,242.34 Rp 226,449.86
Tukang Batu 0.275 org/hr Rp 166,063.23 Rp 45,667.39
Kepala Tukang 0.028 org/hr Rp 157,828.69 Rp 4,419.20
Mandor 0.083 org/hr Rp 157,828.69 Rp 13,099.78
Jumlah : Rp 815,722.23
Keuntungan : Rp 81,572.22
Jumlah : Rp 897,294.45
Dibulatkan : Rp 897,300.00

ANALISIS HARGA SATUAN PEKERJAAN BIDANG PEKERJAAN UMUMNOMOR : 28/PRT/M/2016


NO. URAIAN KOEF SATUAN HARGA STUAN SUB. Jumlah : JUMLAH
1 2 2 3 4 5 6
2 1 m³ Membuat beton mutu fc=9.8 Mpa (K 125), slum (12 ± 2) cm, w/c = 0.76
Bahan Rp 558,707.94
Portland Cement 276.000 kg Rp 1,220.00 Rp 336,720.00
Pasir Beton 0.828 m3 Rp 108,584.48 Rp 89,907.95
Kerikil (maksimum 30 mm) 1.012 m3 Rp 130,301.38 Rp 131,864.99
Air 0.215 Liter Rp 1,000.00 Rp 215.00
Tenaga Kerja Rp 327,201.10
Pekerja 1.650 org/hr Rp 157,643.00 Rp 260,110.95
Tukang Batu 0.275 org/hr Rp 166,729.00 Rp 45,850.48
Kepala Tukang 0.028 org/hr Rp 182,676.00 Rp 5,114.93
Mandor 0.083 org/hr Rp 194,274.00 Rp 16,124.74
Jumlah : Rp 885,909.04
Keuntungan : Rp 88,590.90
Jumlah : Rp 974,499.94
Dibulatkan : Rp 974,500.00
3 1 m³ Membuat beton mutu fc=12.2 Mpa (K 150), slum (12 ± 2) cm, w/c = 0.72
Bahan Rp 584,270.50
Portland Cement 299.000 kg Rp 1,220.00 Rp 364,780.00
Pasir Beton 0.799 m3 Rp 108,584.48 Rp 86,759.00
Kerikil (maksimum 30 mm) 1.017 m3 Rp 130,301.38 Rp 132,516.50
Air 0.215 Liter Rp 1,000.00 Rp 215.00
Tenaga Kerja Rp 289,636.24
Pekerja 1.650 org/hr Rp 137,242.34 Rp 226,449.86
Tukang Batu 0.275 org/hr Rp 166,063.23 Rp 45,667.39
Kepala Tukang 0.028 org/hr Rp 157,828.69 Rp 4,419.20
Mandor 0.083 org/hr Rp 157,828.69 Rp 13,099.78
Jumlah : Rp 873,906.74
Keuntungan : Rp 87,390.67
Jumlah : Rp 961,297.41
Dibulatkan : Rp 961,300.00
4 1 m³ Membuat beton mutu fc=14.5 Mpa (K 175), slum (12 ± 2) cm, w/c = 0.66
Bahan Rp 614,539.32
Portland Cement 326.000 kg Rp 1,220.00 Rp 397,720.00
Pasir Beton 0.760 m3 Rp 108,584.48 Rp 82,524.21
Kerikil (maksimum 30 mm) 1.029 m3 Rp 130,301.38 Rp 134,080.12
Air 0.215 Liter Rp 1,000.00 Rp 215.00
Tenaga Kerja Rp 289,636.24
Pekerja 1.650 org/hr Rp 137,242.34 Rp 226,449.86
Tukang Batu 0.275 org/hr Rp 166,063.23 Rp 45,667.39
Kepala Tukang 0.028 org/hr Rp 157,828.69 Rp 4,419.20
Mandor 0.083 org/hr Rp 157,828.69 Rp 13,099.78
Jumlah : Rp 904,175.56
Keuntungan : Rp 90,417.56
Jumlah : Rp 994,593.11
Dibulatkan : Rp 994,600.00

ANALISIS HARGA SATUAN PEKERJAAN BIDANG PEKERJAAN UMUMNOMOR : 28/PRT/M/2016


NO. URAIAN KOEF SATUAN HARGA STUAN SUB. Jumlah : JUMLAH
1 2 2 3 4 5 6
5 1 m³ Membuat beton mutu fc=16.9 Mpa (K 200), slum (12 ± 2) cm, w/c = 0.61
Bahan Rp 643,370.98
Portland Cement 352.000 kg Rp 1,220.00 Rp 429,440.00
Pasir Beton 0.731 m3 Rp 108,584.48 Rp 79,375.26
Kerikil (maksimum 30 mm) 1.031 m3 Rp 130,301.38 Rp 134,340.72
Air 0.215 Liter Rp 1,000.00 Rp 215.00
Tenaga Kerja Rp 289,636.24
Pekerja 1.650 org/hr Rp 137,242.34 Rp 226,449.86
Tukang Batu 0.275 org/hr Rp 166,063.23 Rp 45,667.39
Kepala Tukang 0.028 org/hr Rp 157,828.69 Rp 4,419.20
Mandor 0.083 org/hr Rp 157,828.69 Rp 13,099.78
Jumlah : Rp 933,007.21
Keuntungan : Rp 93,300.72
Jumlah : Rp 1,026,307.93
Dibulatkan : Rp 1,026,300.00
6 1 m³ Membuat beton mutu fc=19.3 Mpa (K 225), slum (12 ± 2) cm, w/c = 0.58
Bahan Rp 665,052.51
Portland Cement 371.000 kg Rp 1,220.00 Rp 452,620.00
Pasir Beton 0.698 m3 Rp 108,584.48 Rp 75,791.97
Kerikil (maksimum 30 mm) 1.047 m3 Rp 130,301.38 Rp 136,425.54
Air 0.215 Liter Rp 1,000.00 Rp 215.00
Tenaga Kerja Rp 289,636.24
Pekerja 1.650 org/hr Rp 137,242.34 Rp 226,449.86
Tukang Batu 0.275 org/hr Rp 166,063.23 Rp 45,667.39
Kepala Tukang 0.028 org/hr Rp 157,828.69 Rp 4,419.20
Mandor 0.083 org/hr Rp 157,828.69 Rp 13,099.78
Jumlah : Rp 954,688.75
Keuntungan : Rp 95,468.87
Jumlah : Rp 1,050,157.62
Dibulatkan : Rp 1,050,200.00
7 1 m³ Membuat beton mutu fc=21.7 Mpa (K 250), slum (12 ± 2) cm, w/c = 0.56
Bahan Rp 679,218.59
Portland Cement 384.000 kg Rp 1,220.00 Rp 468,480.00
Pasir Beton 0.692 m3 Rp 108,584.48 Rp 75,140.46
Kerikil (maksimum 30 mm) 1.039 m3 Rp 130,301.38 Rp 135,383.13
Air 0.215 Liter Rp 1,000.00 Rp 215.00
Tenaga Kerja Rp 289,636.24
Pekerja 1.650 org/hr Rp 137,242.34 Rp 226,449.86
Tukang Batu 0.275 org/hr Rp 166,063.23 Rp 45,667.39
Kepala Tukang 0.028 org/hr Rp 157,828.69 Rp 4,419.20
Mandor 0.083 org/hr Rp 157,828.69 Rp 13,099.78
Jumlah : Rp 968,854.83
Keuntungan : Rp 96,885.48
Jumlah : Rp 1,065,740.31
Dibulatkan : Rp 1,065,700.00
8 1 m³ Membuat beton mutu fc=24.0 Mpa (K 275), slum (12 ± 2) cm, w/c = 0.53
Bahan Rp 703,496.00
Portland Cement 406.000 kg Rp 1,220.00 Rp 495,320.00
Pasir Beton 0.684 m3 Rp 108,584.48 Rp 74,271.79
Kerikil (maksimum 30 mm) 1.026 m3 Rp 130,301.38 Rp 133,689.21
Air 0.215 Liter Rp 1,000.00 Rp 215.00
Tenaga Kerja Rp 289,636.24
Pekerja 1.650 org/hr Rp 137,242.34 Rp 226,449.86
Tukang Batu 0.275 org/hr Rp 166,063.23 Rp 45,667.39
Kepala Tukang 0.028 org/hr Rp 157,828.69 Rp 4,419.20
Mandor 0.083 org/hr Rp 157,828.69 Rp 13,099.78
Jumlah : Rp 993,132.23
Keuntungan : Rp 99,313.22
Jumlah : Rp 1,092,445.46
Dibulatkan : Rp 1,092,400.00
9 1 m³ Membuat beton mutu fc=26.4 Mpa (K 300), slum (12 ± 2) cm, w/c = 0.52
Bahan Rp 711,058.74
Portland Cement 413.000 kg Rp 1,220.00 Rp 503,860.00
Pasir Beton 0.681 m3 Rp 108,584.48 Rp 73,946.03
Kerikil (maksimum 30 mm) 1.021 m3 Rp 130,301.38 Rp 133,037.71
Air 0.215 Liter Rp 1,000.00 Rp 215.00
Tenaga Kerja Rp 289,636.24
Pekerja 1.650 org/hr Rp 137,242.34 Rp 226,449.86
Tukang Batu 0.275 org/hr Rp 166,063.23 Rp 45,667.39
Kepala Tukang 0.028 org/hr Rp 157,828.69 Rp 4,419.20
Mandor 0.083 org/hr Rp 157,828.69 Rp 13,099.78
Jumlah : Rp 1,000,694.97
Keuntungan : Rp 100,069.50
Jumlah : Rp 1,100,764.47
Dibulatkan : Rp 1,100,800.00
10 1 m³ B Membuat beton mutu fc=28.8 Mpa (K 325), slum (12 ± 2) cm, w/c = 0.49
Bahan Rp 739,629.79
Portland Cement 439.000 kg Rp 1,220.00 Rp 535,580.00
Pasir Beton 0.670 m3 Rp 108,584.48 Rp 72,751.60
Kerikil (maksimum 30 mm) 1.006 m3 Rp 130,301.38 Rp 131,083.19
Air 0.215 Liter Rp 1,000.00 Rp 215.00
Tenaga Kerja Rp 368,427.06
Pekerja 2.100 org/hr Rp 137,242.34 Rp 288,208.92
Tukang Batu 0.350 org/hr Rp 166,063.23 Rp 58,122.13
Kepala Tukang 0.035 org/hr Rp 157,828.69 Rp 5,524.00

ANALISIS HARGA SATUAN PEKERJAAN BIDANG PEKERJAAN UMUMNOMOR : 28/PRT/M/2016


NO. URAIAN KOEF SATUAN HARGA STUAN SUB. Jumlah : JUMLAH
1 2 2 3 4 5 6
Mandor 0.105 org/hr Rp 157,828.69 Rp 16,572.01
Jumlah : Rp 1,108,056.85
Keuntungan : Rp 110,805.69
Jumlah : Rp 1,218,862.54
Dibulatkan : Rp 1,218,900.00
11 1 m³ B Membuat beton mutu fc=31.2 Mpa (K 350), slum (12 ± 2) cm, w/c = 0.48
Bahan Rp 749,502.23
Portland Cement 448.000 kg Rp 1,220.00 Rp 546,560.00
Pasir Beton 0.667 m3 Rp 108,584.48 Rp 72,425.85
Kerikil (maksimum 30 mm) 1.000 m3 Rp 130,301.38 Rp 130,301.38
Air 0.215 Liter Rp 1,000.00 Rp 215.00
Tenaga Kerja Rp 368,427.06
Pekerja 2.100 org/hr Rp 137,242.34 Rp 288,208.92
Tukang Batu 0.350 org/hr Rp 166,063.23 Rp 58,122.13
Kepala Tukang 0.035 org/hr Rp 157,828.69 Rp 5,524.00
Mandor 0.105 org/hr Rp 157,828.69 Rp 16,572.01
Jumlah : Rp 1,117,929.29
Keuntungan : Rp 111,792.93
Jumlah : Rp 1,229,722.22
Dibulatkan : Rp 1,229,700.00
CATATAN
Bobot isi pasir = 1.400 kg/m3, Bobot isi kerikil = 1.800 kg/m3, Buckling factor pasir = 20 %

ANALISIS HARGA SATUAN PEKERJAAN BIDANG PEKERJAAN UMUMNOMOR : 28/PRT/M/2016


NO. URAIAN KOEF SATUAN HARGA STUAN SUB. Jumlah : JUMLAH
1 2 2 3 4 5 6
12 Pembesian 10 kg Dengan Besi polos/Ulir
Bahan Rp 53,194.20
Besi Beton (Polos/Ulir) 10.500 kg Rp 4,880.20 Rp 51,242.11
Kawat Beton 0.150 kg Rp 13,013.87 Rp 1,952.08
Tenaga Kerja Rp 22,967.51
Pekerja 0.070 org/hr Rp 137,242.34 Rp 9,606.96
Tukang Besi 0.070 org/hr Rp 166,063.23 Rp 11,624.43
Kepala Tukang 0.007 org/hr Rp 157,828.69 Rp 1,104.80
Mandor 0.004 org/hr Rp 157,828.69 Rp 631.31
Jumlah : Rp 76,161.70
Keuntungan : Rp 7,616.17
Jumlah : Rp 83,777.87
Tiap 10 kg Dibulatkan : Rp 83,800.00
Tiap 1 kg Jumlah : Rp 8,380.00
13 10 kg Kabel Presstressed Polos
Bahan Rp 52,543.50
Besi Beton (Polos/Ulir) 10.500 kg Rp 4,880.20 Rp 51,242.11
Kawat Beton 0.100 kg Rp 13,013.87 Rp 1,301.39
Tenaga Kerja Rp 16,427.91
Pekerja 0.050 org/hr Rp 137,242.34 Rp 6,862.12
Tukang Besi 0.050 org/hr Rp 166,063.23 Rp 8,303.16
Kepala Tukang 0.005 org/hr Rp 157,828.69 Rp 789.14
Mandor 0.003 org/hr Rp 157,828.69 Rp 473.49
Jumlah : Rp 68,971.41
Keuntungan : Rp 6,897.14
Jumlah : per 10 kg : Rp 75,868.55
Jumlah : per kg : Rp 7,586.86
Dibulatkan : Rp 7,600.00
A.4.1.1.20 1 m² Memasang Bekisting Untuk Pondasi
Bahan Rp 71,905.16
Kayu Kelas III 0.040 m³ Rp 1,689,091.93 Rp 67,563.68
Paku 5 cm - 10 cm 0.300 kg Rp 12,471.63 Rp 3,741.49
Minyak Bekisting 0.100 liter Rp 6,000.00 Rp 600.00
Tenaga Kerja Rp 122,749.55
Pekerja 0.520 org/hr Rp 137,242.34 Rp 71,366.02
Tukang Kayu 0.260 org/hr Rp 166,063.23 Rp 43,176.44
Kepala Tukang 0.026 org/hr Rp 157,828.69 Rp 4,103.55
Mandor 0.026 org/hr Rp 157,828.69 Rp 4,103.55
Jumlah : Rp 194,654.71
Keuntungan : Rp 19,465.47
Jumlah : Rp 214,120.19
Dibulatkan : Rp 214,100.00
A.4.1.1.21 1 m² Memasang Bekisting sloof
Bahan Rp 80,350.62
Kayu Kelas III / Bekisting 0.045 m³ Rp 1,689,091.93 Rp 76,009.14
Paku 5 cm - 10 cm 0.300 kg Rp 12,471.63 Rp 3,741.49
Minyak Bekisting 0.100 liter Rp 6,000.00 Rp 600.00
Tenaga Kerja Rp 122,749.55
Pekerja 0.520 org/hr Rp 137,242.34 Rp 71,366.02
Tukang Kayu 0.260 org/hr Rp 166,063.23 Rp 43,176.44
Kepala Tukang 0.026 org/hr Rp 157,828.69 Rp 4,103.55
Mandor 0.026 org/hr Rp 157,828.69 Rp 4,103.55
Jumlah : Rp 203,100.17
Keuntungan : Rp 20,310.02
Jumlah : Rp 223,410.19
Dibulatkan : Rp 223,400.00

ANALISIS HARGA SATUAN PEKERJAAN BIDANG PEKERJAAN UMUMNOMOR : 28/PRT/M/2016


NO. URAIAN KOEF SATUAN HARGA STUAN SUB. Jumlah : JUMLAH
1 2 2 3 4 5 6
A.4.1.1.22 1 m² Memasang Bekisting Untuk Kolom
Bahan Rp 124,314.47
Kayu Kelas III ( kayu lokal ) 0.020 m³ Rp 1,689,091.93 Rp 33,781.84
Paku 5 cm - 12 cm 0.400 kg Rp 12,471.63 Rp 4,988.65
Minyak Bekisting 0.200 liter Rp 6,000.00 Rp 1,200.00
Balok Kayu Kelas III ( kayu lokal )---2 0.008 m³ Rp 1,718,530.39 Rp 12,888.98
Plywood Tebal 9 mm---2 x pakai 0.175 lbr Rp 122,600.00 Rp 21,455.00
Dolken Kayu Galam. Dia (8-10) cm Pa 2.000 Batang Rp 25,000.00 Rp 50,000.00
Tenaga Kerja Rp 155,797.51
Pekerja 0.660 org/hr Rp 137,242.34 Rp 90,579.94
Tukang Kayu 0.330 org/hr Rp 166,063.23 Rp 54,800.87
Kepala Tukang 0.033 org/hr Rp 157,828.69 Rp 5,208.35
Mandor 0.033 org/hr Rp 157,828.69 Rp 5,208.35
Jumlah : Rp 280,111.97
Keuntungan : Rp 28,011.20
Jumlah : Rp 308,123.17
Dibulatkan : Rp 308,100.00
A.4.1.1.23 1 m² Memasang Bekisting Untuk Balok
Bahan Rp 126,892.26
Kayu Kelas III ( kayu lokal )---2 x paka 0.020 m³ Rp 1,689,091.93 Rp 33,781.84
Paku 5 cm - 12 cm 0.400 kg Rp 12,471.63 Rp 4,988.65
Minyak Bekisting 0.200 liter Rp 6,000.00 Rp 1,200.00
Balok Kayu Kelas III ( kayu lokal )---2 0.009 m³ Rp 1,718,530.39 Rp 15,466.77
Plywood Tebal 9 mm---2 x pakai 0.175 lbr Rp 122,600.00 Rp 21,455.00
Dolken Kayu Galam. Dia (8-10) cm Pa 2.000 Batang Rp 25,000.00 Rp 50,000.00
Tenaga Kerja Rp 155,797.51
Pekerja 0.660 org/hr Rp 137,242.34 Rp 90,579.94
Tukang Kayu 0.330 org/hr Rp 166,063.23 Rp 54,800.87
Kepala Tukang 0.033 org/hr Rp 157,828.69 Rp 5,208.35
Mandor 0.033 org/hr Rp 157,828.69 Rp 5,208.35
Jumlah : Rp 282,689.77
Keuntungan : Rp 28,268.98
Jumlah : Rp 310,958.74
Dibulatkan : Rp 311,000.00

A.4.1.1.24 1 m² Memasang Bekisting Untuk plat lantai ( 2 x pakai )


Bahan Rp 224,314.47
Kayu Kelas III ( kayu lokal )---2 x paka 0.020 m³ Rp 1,689,091.93 Rp 33,781.84
Paku 5 cm - 12 cm 0.400 kg Rp 12,471.63 Rp 4,988.65
Minyak Bekisting 0.200 liter Rp 6,000.00 Rp 1,200.00
Balok Kayu Kelas III ( kayu lokal )---2 0.008 m³ Rp 1,718,530.39 Rp 12,888.98
Plywood Tebal 9 mm---2 x pakai 0.175 lbr Rp 122,600.00 Rp 21,455.00
Dolken Kayu Galam. Dia (8-10) cm Pa 6.000 Batang Rp 25,000.00 Rp 150,000.00
Tenaga Kerja Rp 155,797.51
Pekerja 0.660 org/hr Rp 137,242.34 Rp 90,579.94
Tukang Kayu 0.330 org/hr Rp 166,063.23 Rp 54,800.87
Kepala Tukang 0.033 org/hr Rp 157,828.69 Rp 5,208.35
Mandor 0.033 org/hr Rp 157,828.69 Rp 5,208.35
Jumlah : Rp 380,111.97
Keuntungan : Rp 38,011.20
Jumlah : Rp 418,123.17
Dibulatkan : Rp 418,100.00
A.4.1.1.24 1 m² PEMASANGAN 1M2 BEKESTING UNTUK BALOK LATAI/RING BALK
Bahan Rp 274,314.47
Kayu Kelas III ( kayu lokal )---2 x paka 0.020 m³ Rp 1,689,091.93 Rp 33,781.84
Paku 5 cm - 12 cm 0.400 kg Rp 12,471.63 Rp 4,988.65
Minyak Bekisting 0.200 liter Rp 6,000.00 Rp 1,200.00
Balok Kayu Kelas III ( kayu lokal )---2 0.008 m³ Rp 1,718,530.39 Rp 12,888.98
Plywood Tebal 9 mm---2 x pakai 0.175 lbr Rp 122,600.00 Rp 21,455.00
Dolken Kayu Galam. Dia (8-10) cm Pa 8.000 Batang Rp 25,000.00 Rp 200,000.00
Tenaga Kerja Rp 155,797.51
Pekerja 0.660 org/hr Rp 137,242.34 Rp 90,579.94
Tukang Kayu 0.330 org/hr Rp 166,063.23 Rp 54,800.87
Kepala Tukang 0.033 org/hr Rp 157,828.69 Rp 5,208.35
Mandor 0.033 org/hr Rp 157,828.69 Rp 5,208.35
Jumlah : Rp 430,111.97
Keuntungan : Rp 43,011.20
Jumlah : Rp 473,123.17
Dibulatkan : Rp 473,100.00

ANALISIS HARGA SATUAN PEKERJAAN BIDANG PEKERJAAN UMUMNOMOR : 28/PRT/M/2016


NO. URAIAN KOEF SATUAN HARGA STUAN SUB. Jumlah : JUMLAH
1 2 2 3 4 5 6
A.4.1.1.25 1 m² Memasang Bekisting Untuk Dinding ( 2 x pakai )
Bahan Rp 205,165.33
Kayu Kelas III ( kayu lokal )---2 x paka 0.015 m³ Rp 1,689,091.93 Rp 25,336.38
Paku 5 cm - 12 cm 0.400 kg Rp 12,471.63 Rp 4,988.65
Minyak Bekisting 0.200 liter Rp 6,000.00 Rp 1,200.00
Balok Kayu Kelas III ( kayu lokal )---2 0.010 m³ Rp 1,718,530.39 Rp 17,185.30
Plywood Tebal 9 mm---2 x pakai 0.175 lbr Rp 122,600.00 Rp 21,455.00
Dolken Kayu Galam. Dia (8-10) cm Pa 3.000 Batang Rp 25,000.00 Rp 75,000.00
Formite/Penjaga Jarak Bekisting 4.000 Buah Rp 15,000.00 Rp 60,000.00
Tenaga Kerja Rp 155,797.51
Pekerja 0.660 org/hr Rp 137,242.34 Rp 90,579.94
Tukang Kayu 0.330 org/hr Rp 166,063.23 Rp 54,800.87
Kepala Tukang 0.033 org/hr Rp 157,828.69 Rp 5,208.35
Mandor 0.033 org/hr Rp 157,828.69 Rp 5,208.35
Jumlah : Rp 360,962.84
Keuntungan : Rp 36,096.28
Jumlah : Rp 397,059.12
Dibulatkan : Rp 397,100.00
A.4.1.1.26 1 m² PEMASANGAN 1M2 BEKESTING UNTUK PLAT KANOPI
Bahan Rp 92,071.63
Kayu Kelas III ( kayu lokal )---2 x paka 0.015 m³ Rp 122,600.00 Rp 1,839.00
Paku 5 cm - 12 cm 0.400 kg Rp 12,471.63 Rp 4,988.65
Minyak Bekisting 0.150 liter Rp 6,000.00 Rp 900.00
Balok Kayu Kelas III ( kayu lokal )---2 0.008 m³ Rp 1,718,530.39 Rp 12,888.98
Plywood Tebal 9 mm---2 x pakai 0.175 lbr Rp 122,600.00 Rp 21,455.00
Dolken Kayu Galam. Dia (8-10) cm Pa 2.000 Batang Rp 25,000.00 Rp 50,000.00
Tenaga Kerja Rp 155,797.51
Pekerja 0.660 org/hr Rp 137,242.34 Rp 90,579.94
Tukang Kayu 0.330 org/hr Rp 166,063.23 Rp 54,800.87
Kepala Tukang 0.033 org/hr Rp 157,828.69 Rp 5,208.35
Mandor 0.033 org/hr Rp 157,828.69 Rp 5,208.35
Jumlah : Rp 247,869.13
Keuntungan : Rp 24,786.91
Jumlah : Rp 272,656.05
Dibulatkan : Rp 272,700.00
1 M' KOLOM PRAKTIS BETON BERTULANG (11X11)CM
Bahan Rp 27,570.98
Kayu Kelas III 0.002 m³ Rp 122,600.00 Rp 245.20
Paku 5 cm - 12 cm 0.010 kg Rp 12,471.63 Rp 124.72
Besi Beton Polos 3.000 kg Rp 4,880.20 Rp 14,640.60
Kawat Beton 0.450 kg Rp 13,013.87 Rp 5,856.24
Portlan Cement 4.000 kg Rp 1,220.00 Rp 4,880.00
Pasir Beton 0.006 m³ Rp 108,584.48 Rp 651.51
Kerikil 0.009 m³ Rp 130,301.38 Rp 1,172.71
Tenaga Kerja Rp 37,034.85
Pekerja 0.180 org/hr Rp 137,242.34 Rp 24,703.62
Tukang Batu 0.020 org/hr Rp 166,063.23 Rp 3,321.26
Tukang Kayu 0.020 org/hr Rp 166,063.23 Rp 3,321.26
Tukang Besi 0.020 org/hr Rp 166,063.23 Rp 3,321.26
Kepala Tukang 0.006 org/hr Rp 157,828.69 Rp 946.97
Mandor 0.009 org/hr Rp 157,828.69 Rp 1,420.46
Jumlah : Rp 64,605.83
Keuntungan : Rp 6,460.58
Jumlah : Rp 71,066.41
Dibulatkan : Rp 71,100.00
1 m' Ring Balok Beton Bertulang (10 x 15) cm
Bahan Rp 28,478.43
Kayu Kelas III 0.003 m³ Rp 122,600.00 Rp 367.80
Paku 5 cm - 12 cm 0.020 kg Rp 12,471.63 Rp 249.43
Besi Beton Polos 3.600 kg Rp 4,880.20 Rp 17,568.73
Kawat Beton 0.050 kg Rp 13,013.87 Rp 650.69
Portlan Cement 5.500 kg Rp 1,220.00 Rp 6,710.00
Pasir Beton 0.009 m³ Rp 108,584.48 Rp 977.26
Kerikil 0.015 m³ Rp 130,301.38 Rp 1,954.52

ANALISIS HARGA SATUAN PEKERJAAN BIDANG PEKERJAAN UMUMNOMOR : 28/PRT/M/2016


NO. URAIAN KOEF SATUAN HARGA STUAN SUB. Jumlah : JUMLAH
1 2 2 3 4 5 6
Tenaga Kerja Rp 61,146.95
Pekerja 0.297 org/hr Rp 137,242.34 Rp 40,760.98
Tukang Batu 0.033 org/hr Rp 166,063.23 Rp 5,480.09
Tukang Kayu 0.033 org/hr Rp 166,063.23 Rp 5,480.09
Tukang Besi 0.033 org/hr Rp 166,063.23 Rp 5,480.09
Kepala Tukang 0.010 org/hr Rp 157,828.69 Rp 1,578.29
Mandor 0.015 org/hr Rp 157,828.69 Rp 2,367.43
Jumlah : Rp 89,625.38
Keuntungan : Rp 8,962.54
Jumlah : Rp 98,587.92
Dibulatkan : Rp 98,600.00
PEMASANGAN 1 M KANSTIN 60X14X30CM
Pek. Analisa sebelum keuntungan Rp 8,513.42
Galian Tanah 0.070 m³ Rp 77,850.72 Rp 5,449.55
Urugan pasir 0.008 m³ Rp 158,574.44 Rp 1,189.31
Mengurug Kembali 0.025 m³ Rp 76,512.60 Rp 1,874.56
Bahan Rp 162,622.00
kansteen 2.500 m³ Rp 65,000.00 Rp 162,500.00
Semen untuk pengikat 0.100 kg Rp 1,220.00 Rp 122.00
Tenaga Kerja Rp 46,422.22
Pekerja 0.200 org/hr Rp 137,242.34 Rp 27,448.47
Tukang Batu 0.100 org/hr Rp 166,063.23 Rp 16,606.32
Kepala Tukang 0.010 org/hr Rp 157,828.69 Rp 1,578.29
Mandor 0.005 org/hr Rp 157,828.69 Rp 789.14
Jumlah : Rp 217,557.64
Keuntungan : Rp 21,755.76
Jumlah : Rp 239,313.40
Dibulatkan : Rp 239,300.00
PEMASANGAN 1 M KANSTIN 50X20X40CM
Pek. Analisa sebelum keuntungan Rp 8,513.42
Galian Tanah 0.070 m³ Rp 77,850.72 Rp 5,449.55
Urugan pasir 0.008 m³ Rp 158,574.44 Rp 1,189.31
Mengurug Kembali 0.025 m³ Rp 76,512.60 Rp 1,874.56
Bahan Rp 106,372.00
kansteen 2.500 m³ Rp 42,500.00 Rp 106,250.00
Semen untuk pengikat 0.100 kg Rp 1,220.00 Rp 122.00
Tenaga Kerja Rp 46,422.22
Pekerja 0.200 org/hr Rp 137,242.34 Rp 27,448.47
Tukang Batu 0.100 org/hr Rp 166,063.23 Rp 16,606.32
Kepala Tukang 0.010 org/hr Rp 157,828.69 Rp 1,578.29
Mandor 0.005 org/hr Rp 157,828.69 Rp 789.14
Jumlah : Rp 161,307.64
Keuntungan : Rp 16,130.76
Jumlah : Rp 177,438.40
Dibulatkan : Rp 177,400.00

ANALISIS HARGA SATUAN PEKERJAAN BIDANG PEKERJAAN UMUMNOMOR : 28/PRT/M/2016


NO. URAIAN KOEF SATUAN HARGA STUAN SUB. JUMLAH JUMLAH
1 2 3 4 5 6 7
G PENETAPAN INDEKS HARGA SATUAN PEKERJAAN BESI DAN ALUMUNIUM

1 1 kg Memasang besi profil


Bahan Rp 9,975.00
Besi Profil 1.0500 kg Rp 9,500.00 Rp 9,975.00
Tenaga Kerja Rp 19,618.79
Pekerja 0.0600 org/hr Rp 137,242.34 Rp 8,234.54
Tukang Las 0.0600 org/hr Rp 166,063.23 Rp 9,963.79
Kepala Tukang 0.0060 org/hr Rp 157,828.69 Rp 946.97
Mandor 0.0030 org/hr Rp 157,828.69 Rp 473.49
Jumlah 29,593.79
Keuntungan 10% : Rp 2,959.38
Jumlah : Rp 32,553.17
Dibulatkan : Rp 32,600.00
2 1 kg Memasang Plat Baja t=……
Bahan Rp 9,975.00
Plat Baja t=….. 1.0500 kg Rp 9,500.00 Rp 9,975.00
Tenaga Kerja Rp 19,618.79
Pekerja 0.0600 org/hr Rp 137,242.34 Rp 8,234.54
Tukang Las 0.0600 org/hr Rp 166,063.23 Rp 9,963.79
Kepala Tukang 0.0060 org/hr Rp 157,828.69 Rp 946.97
Mandor 0.0030 org/hr Rp 157,828.69 Rp 473.49
Jumlah Rp 29,593.79
Keuntungan 10% : Rp 2,959.38
Jumlah : Rp 32,553.17
Dibulatkan : Rp 32,600.00
3 1 m² Membuat Pintu Besi Plat Baja Tebal 2 mm Rangkap. Rangka Baja Siku
Bahan Rp 458,350.00
Besi Siku L 30.30.3 15.0000 kg Rp 9,500.00 Rp 142,500.00
Besi Plat Baja 32.8000 kg Rp 9,500.00 Rp 311,600.00
Kawat Las 0.0500 kg Rp 85,000.00 Rp 4,250.00
Tenaga Kerja Rp 343,249.96
Pekerja 1.0500 org/hr Rp 137,242.34 Rp 144,104.46
Tukang las 1.0500 org/hr Rp 166,063.23 Rp 174,366.39
Kepala Tukang 0.1050 org/hr Rp 157,828.69 Rp 16,572.01
Mandor 0.0520 org/hr Rp 157,828.69 Rp 8,207.09
Jumlah Rp 801,599.96
Keuntungan 10% : Rp 80,160.00
Jumlah : Rp 881,759.95
Dibulatkan : Rp 881,800.00

ANALISIS HARGA SATUAN PEKERJAAN BIDANG PEKERJAAN UMUMNOMOR : 28/PRT/M/2016


NO. URAIAN KOEF SATUAN HARGA STUAN SUB. JUMLAH JUMLAH
1 2 3 4 5 6 7
G PENETAPAN INDEKS HARGA SATUAN PEKERJAAN BESI DAN ALUMUNIUM
4 10 cm Mengerjakan Pengelasan Dengan Las Listrik
Bahan Rp 39,050.00
Kawat Las Listrik 0.4000 kg Rp 85,000.00 Rp 34,000.00
Solar 0.3000 liter Rp 9,500.00 Rp 2,850.00
Minyak Pelumas 0.0400 liter Rp 55,000.00 Rp 2,200.00
Tenaga Kerja Rp 9,442.27
Pekerja 0.0400 org/hr Rp 137,242.34 Rp 5,489.69
Tukang las 0.0200 org/hr Rp 166,063.23 Rp 3,321.26
Kepala Tukang 0.0020 org/hr Rp 157,828.69 Rp 315.66
Mandor 0.0020 org/hr Rp 157,828.69 Rp 315.66
Alat
Sewa Alat 0.1700 jam Rp 93,500.00 Rp 15,895.00 Rp 15,895.00
Jumlah Rp 64,387.27
Keuntungan 10% : Rp 6,438.73
Jumlah : Rp 70,826.00
Dibulatkan : Rp 70,800.00
5 1 m1 Memasang Kusen Pintu Alumunium
Bahan Rp 65,939.84
Bahan kusen Alluminium 1.1000 m Rp 55,308.95 Rp 60,839.84
Skrup Fixer 2.0000 buah Rp 1,200.00 Rp 2,400.00
Sealant 0.0600 tube Rp 45,000.00 Rp 2,700.00
Tenaga Kerja Rp 14,052.24
Pekerja 0.0430 org/hr Rp 137,242.34 Rp 5,901.42
Tukang khusus alumunium 0.0430 org/hr Rp 166,063.23 Rp
7,140.72
Kepala Tukang 0.0043 org/hr Rp 157,828.69 Rp
678.66
Mandor 0.0021 org/hr Rp 157,828.69 Rp
331.44
Jumlah Rp 79,992.09
Keuntungan 10% : Rp 7,999.21
Jumlah : Rp 87,991.30
Dibulatkan : Rp 88,000.00
6 1 m1 Memasang Kusen Pintu Alumunium 4" tebal 1.35mm Warna EX. ALEXINDO
Bahan Rp 122,800.00
Bahan kusen Alluminium ex.
1.1000 m Rp 107,000.00 Rp 117,700.00
Alexindo 4 " ( silver / natural )
Skrup Fixer 2.0000 buah Rp 1,200.00 Rp 2,400.00
Sealant 0.0600 tube Rp 45,000.00 Rp 2,700.00
Tenaga Kerja Rp 14,052.24
Pekerja 0.0430 org/hr Rp 137,242.34 Rp 5,901.42
Tukang khusus alumunium 0.0430 org/hr Rp 166,063.23 Rp 7,140.72
Kepala Tukang 0.0043 org/hr Rp 157,828.69 Rp 678.66
Mandor 0.0021 org/hr Rp 157,828.69 Rp 331.44
Jumlah Rp 136,852.24
Keuntungan 10% : Rp 13,685.22
Jumlah : Rp 150,537.47
Dibulatkan : Rp 150,500.00
7 1 m² Memasang Pintu Kaca Rangka Alumunium
Bahan Rp 278,909.38
Profil Alumunium 4.4000 m Rp 55,308.95 Rp 243,359.38
List Kaca karet L 1 cm 4.5000 m Rp 5,200.00 Rp 23,400.00
Sealant 0.2700 tube Rp 45,000.00 Rp 12,150.00
Tenaga Kerja Rp 27,990.58
Pekerja 0.0850 org/hr Rp 137,242.34 Rp 11,665.60
Tukang Besi 0.0850 org/hr Rp 166,063.23 Rp 14,115.37
Kepala Tukang 0.0090 org/hr Rp 157,828.69 Rp 1,420.46
Mandor 0.0050 org/hr Rp 157,828.69 Rp 789.14
Jumlah Rp 306,899.95
Keuntungan 10% : Rp 30,690.00
Jumlah : Rp 337,589.95
Dibulatkan : Rp 337,600.00
A.4.2.1.9 1 m² Memasang Sunscreen Alumunium
Bahan Rp 860,000.00
Jalusi Alumunium t=2mm 2.0000 m² Rp 430,000.00 Rp 860,000.00
Tenaga Kerja Rp 157,087.58
Pekerja 0.0800 org/hr Rp 137,242.34 Rp 10,979.39
Tukang khusus alumunium 0.8000 org/hr Rp 166,063.23 Rp 132,850.59
Kepala Tukang 0.0800 org/hr Rp 157,828.69 Rp 12,626.30
Mandor 0.0040 org/hr Rp 157,828.69 Rp 631.31
Jumlah Rp 1,017,087.58
Keuntungan 10% : Rp 101,708.76
Jumlah : Rp 1,118,796.34
Dibulatkan : Rp 1,118,800.00

ANALISIS HARGA SATUAN PEKERJAAN BIDANG PEKERJAAN UMUMNOMOR : 28/PRT/M/2016


NO. URAIAN KOEF SATUAN HARGA STUAN SUB. JUMLAH JUMLAH
1 2 2 3 4 5 6

1 1 m² Pasangan Dinding Bata Merah kelas 1 Uk.(5x11x22)cm Tebal 1 Bata. Campuran Spesi 1PC : 2PP
Bahan Rp 158,405.48
Bata Merah kelas 1 140.000 Buah Rp 700.00 Rp 98,000.00
PC 43.500 kg Rp 1,220.00 Rp 53,070.00
PP 0.080 m³ Rp 91,693.56 Rp 7,335.48
Tenaga Kerja Rp 123,449.49
Pekerja 0.600 org/hr Rp 137,242.34 Rp 82,345.40
Tukang Batu 0.200 org/hr Rp 166,063.23 Rp 33,212.65
Kepala Tukang 0.020 org/hr Rp 157,828.69 Rp 3,156.57
Mandor 0.030 org/hr Rp 157,828.69 Rp 4,734.86
Jumlah : Rp 281,854.97
Keuntungan 10% : Rp 28,185.50
Jumlah : Rp 310,040.47
Dibulatkan : Rp 310,000.00
2 1 m² Pasangan Dinding Bata Merah kelas 1 Uk.(5x11x22)cm Tebal 1 Bata. Campuran Spesi 1PC : 4PP
Bahan Rp 138,918.50
Bata Merah kelas 1 140.000 Buah Rp 700.00 Rp 98,000.00
PC 26.550 kg Rp 1,220.00 Rp 32,391.00
PP 0.093 m³ Rp 91,693.56 Rp 8,527.50
Tenaga Kerja Rp 123,449.49
Pekerja 0.600 org/hr Rp 137,242.34 Rp 82,345.40
Tukang Batu 0.200 org/hr Rp 166,063.23 Rp 33,212.65
Kepala Tukang 0.020 org/hr Rp 157,828.69 Rp 3,156.57
Mandor 0.030 org/hr Rp 157,828.69 Rp 4,734.86
Jumlah : Rp 262,367.99
Keuntungan 10% : Rp 26,236.80
Jumlah : Rp 288,604.79
Dibulatkan : Rp 288,600.00
3 1 m² Pasangan Dinding Bata Merah kelas 1 Uk.(5x11x22)cm Tebal 1/2 Bata. Campuran Spesi 1PC : 2PP
Bahan Rp 75,603.36
Bata Merah kelas 1 70.000 Buah Rp 700.00 Rp 49,000.00
PC 18.950 kg Rp 1,220.00 Rp 23,119.00
PP 0.038 m³ Rp 91,693.56 Rp 3,484.36
Tenaga Kerja Rp 61,724.74
Pekerja 0.300 org/hr Rp 137,242.34 Rp 41,172.70
Tukang Batu 0.100 org/hr Rp 166,063.23 Rp 16,606.32
Kepala Tukang 0.010 org/hr Rp 157,828.69 Rp 1,578.29
Mandor 0.015 org/hr Rp 157,828.69 Rp 2,367.43
Jumlah : Rp 137,328.10
Keuntungan 10% : Rp 13,732.81
Jumlah : Rp 151,060.91
Dibulatkan : Rp 151,100.00
17 1 m² Pasangan Dinding HB/CB 20.Campuran Spesi 1PC :4PP
Bahan Rp 259,154.63
HB 20 12.500 bh Rp 12,500.00 Rp 156,250.00
PC 24.260 kg Rp 1,220.00 Rp 29,597.20
PP 0.772 m³ Rp 91,693.56 Rp 70,787.43
Besi Angkur Diameter 8 mm 0.280 kg Rp 9,000.00 Rp 2,520.00
Tenaga Kerja 78152.65091975
Pekerja 0.350 org/hr Rp 137,242.34 Rp 48,034.82
Tukang Batu 0.150 org/hr Rp 166,063.23 Rp 24,909.48
Kepala Tukang 0.015 org/hr Rp 157,828.69 Rp 2,367.43
Mandor 0.018 org/hr Rp 157,828.69 Rp 2,840.92
Jumlah : Rp 337,307.28
Keuntungan 10% : Rp 33,730.73
Jumlah : Rp 371,038.01
Dibulatkan : Rp 371,000.00

ANALISIS HARGA SATUAN PEKERJAAN BIDANG PEKERJAAN UMUMNOMOR : 28/PRT/M/2016


NO. URAIAN KOEF SATUAN HARGA STUAN SUB. JUMLAH JUMLAH
1 2 2 3 4 5 6

PEKERJAAN PLESTERAN

A.4.4.2.1 1 m² Plesteran 1 : 1 Tebal 15 mm


Bahan Rp 20,381.98
Portland Cement 15.504 Kg Rp 1,220.00 Rp 18,914.88
Pasir Pasang 0.016 m³ Rp 91,693.56 Rp 1,467.10
Tenaga Kerja Rp 70,817.05
Pekerja 0.300 org/hr Rp 137,242.34 Rp 41,172.70
Tukang Batu 0.150 org/hr Rp 166,063.23 Rp 24,909.48
Kepala Tukang 0.015 org/hr Rp 157,828.69 Rp 2,367.43
Mandor 0.015 org/hr Rp 157,828.69 Rp 2,367.43
Jumlah Rp 91,199.02
Keuntungan 10% : Rp 9,119.90
Jumlah : Rp 100,318.93
Dibulatkan : Rp 100,300.00

A.4.4.2.2 1 m² Plesteran 1 : 2 Tebal 15 mm


Bahan Rp 14,307.15
Portland Cement 10.224 Kg Rp 1,220.00 Rp 12,473.28
Pasir Pasang 0.020 m³ Rp 91,693.56 Rp 1,833.87
Tenaga Kerja Rp 70,817.05
Pekerja 0.300 org/hr Rp 137,242.34 Rp 41,172.70
Tukang Batu 0.150 org/hr Rp 166,063.23 Rp 24,909.48
Kepala Tukang 0.015 org/hr Rp 157,828.69 Rp 2,367.43
Mandor 0.015 org/hr Rp 157,828.69 Rp 2,367.43
Jumlah Rp 85,124.20
Keuntungan 10% : Rp 8,512.42
Jumlah : Rp 93,636.62
Dibulatkan : Rp 93,600.00
A.4.4.2.4 1 m² Plesteran 1 : 4 Tebal 15 mm
Bahan Rp 9,813.45
Portland Cement 6.240 Kg Rp 1,220.00 Rp 7,612.80
Pasir Pasang 0.024 m³ Rp 91,693.56 Rp 2,200.65
Tenaga Kerja Rp 70,817.05
Pekerja 0.300 org/hr Rp 137,242.34 Rp 41,172.70
Tukang Batu 0.150 org/hr Rp 166,063.23 Rp 24,909.48
Kepala Tukang 0.015 org/hr Rp 157,828.69 Rp 2,367.43
Mandor 0.015 org/hr Rp 157,828.69 Rp 2,367.43
Jumlah Rp 80,630.49
Keuntungan 10% : Rp 8,063.05
Jumlah : Rp 88,693.54
Dibulatkan : Rp 88,700.00
NO. URAIAN KOEF SATUAN HARGA STUAN SUB. JUMLAH JUMLAH
1 2 2 3 4 5 6

PEKERJAAN PLESTERAN
#VALUE! 1 m² Plesteran 1PC : 1/2KP : 3PP Tebal 15 mm
Bahan Rp -
Portland Cement 5.760 Kg Rp 1,220.00
Kapur 0.003 m³ Rp -
Pasir Pasang 0.013 m³ Rp 91,693.56
Tenaga Kerja Rp -
Pekerja 0.360 org/hr Rp 137,242.34
Tukang Batu 0.120 org/hr Rp 166,063.23
Kepala Tukang 0.012 org/hr Rp 157,828.69
Mandor 0.018 org/hr Rp 157,828.69
Jumlah Rp -
Keuntungan 10% : Rp -
Jumlah : Rp -
Dibulatkan : Rp -
#VALUE! 1 m² Plesteran 1PC : 2KP : 8PP Tebal 15 mm
Bahan Rp -
Portland Cement 3.000 Kg Rp 1,220.00
Kapur 0.005 m³ Rp -
Pasir Pasang 0.020 m³ Rp 91,693.56
Tenaga Kerja Rp -
Pekerja 0.360 org/hr Rp 137,242.34
Tukang Batu 0.120 org/hr Rp 166,063.23
Kepala Tukang 0.012 org/hr Rp 157,828.69
Mandor 0.018 org/hr Rp 157,828.69
Jumlah Rp -
Keuntungan 10% : Rp -
Jumlah : Rp -
Dibulatkan : Rp -
#VALUE! 1 m² Plesteran 1SM : 1KP : 1PP Tebal 15 mm
Bahan Rp -
SM 0.009 Kg Rp -
Kapur 0.009 m³ Rp -
Pasir Pasang 0.009 m³ Rp 91,693.56
Tenaga Kerja Rp -
Pekerja 0.360 org/hr Rp 137,242.34
Tukang Batu 0.120 org/hr Rp 166,063.23
Kepala Tukang 0.012 org/hr Rp 157,828.69
Mandor 0.018 org/hr Rp 157,828.69
Rp -
Keuntungan 10% : Rp -
Jumlah : Rp -
Dibulatkan : Rp -
#VALUE! 1 m² Plesteran 1SM : 1KP : 2PP Tebal 15 mm
Bahan Rp -
SM 0.007 Kg Rp -
Kapur 0.007 m³ Rp -
Pasir Pasang 0.015 m³ Rp 91,693.56
Tenaga Kerja Rp -
Pekerja 0.360 org/hr Rp 137,242.34
Tukang Batu 0.120 org/hr Rp 166,063.23
Kepala Tukang 0.012 org/hr Rp 157,828.69
Mandor 0.018 org/hr Rp 157,828.69
Jumlah Rp -
Keuntungan 10% : Rp -
Jumlah : Rp -
Dibulatkan : Rp -
A.4.4.2.13 1 m² Plesteran 1 : 1 Tebal 20 mm
Bahan Rp 19,106.77
Portland Cement 13.632 Kg Rp 1,220.00 Rp 16,631.04
Pasir Pasang 0.027 m³ Rp 91,693.56 Rp 2,475.73
Tenaga Kerja Rp 94,738.39
Pekerja 0.400 org/hr Rp 137,242.34 Rp 54,896.94
Tukang Batu 0.200 org/hr Rp 166,063.23 Rp 33,212.65
Kepala Tukang 0.020 org/hr Rp 157,828.69 Rp 3,156.57
Mandor 0.022 org/hr Rp 157,828.69 Rp 3,472.23
Jumlah Rp 113,845.15
Keuntungan 10% : Rp 11,384.52
Jumlah : Rp 125,229.67
Dibulatkan : Rp 125,200.00
A.4.4.2.14 1 m² Plesteran 1 : 3 Tebal 20 mm
Bahan Rp 15,491.46
Portland Cement 10.368 Kg Rp 1,220.00 Rp 12,648.96
Pasir Pasang 0.031 m³ Rp 91,693.56 Rp 2,842.50
Tenaga Kerja Rp 94,738.39
Pekerja 0.400 org/hr Rp 137,242.34 Rp 54,896.94
Tukang Batu 0.200 org/hr Rp 166,063.23 Rp 33,212.65
Kepala Tukang 0.020 org/hr Rp 157,828.69 Rp 3,156.57
Mandor 0.022 org/hr Rp 157,828.69 Rp 3,472.23
Jumlah Rp 110,229.85
Keuntungan 10% : Rp 11,022.98
Jumlah : Rp 121,252.83
Dibulatkan : Rp 121,300.00
A.4.4.2.15 1 m² Plesteran 1 : 4 Tebal 20 mm
Bahan Rp 13,084.59
NO. URAIAN KOEF SATUAN HARGA STUAN SUB. JUMLAH JUMLAH
1 2 2 3 4 5 6

PEKERJAAN PLESTERAN
Portland Cement 8.320 Kg Rp 1,220.00 Rp 10,150.40
Pasir Pasang 0.032 m³ Rp 91,693.56 Rp 2,934.19
Tenaga Kerja Rp 94,738.39
Pekerja 0.400 org/hr Rp 137,242.34 Rp 54,896.94
Tukang Batu 0.200 org/hr Rp 166,063.23 Rp 33,212.65
Kepala Tukang 0.020 org/hr Rp 157,828.69 Rp 3,156.57
Mandor 0.022 org/hr Rp 157,828.69 Rp 3,472.23
Jumlah Rp 107,822.98
Keuntungan 10% : Rp 10,782.30
Jumlah : Rp 118,605.28
Dibulatkan : Rp 118,600.00
NO. URAIAN KOEF SATUAN HARGA STUAN SUB. JUMLAH JUMLAH
1 2 2 3 4 5 6

PEKERJAAN PLESTERAN
1 m² PEMASANGAN 1M2 PLESTERAN BATA RINGAN TEBAL 1CM
Bahan Rp 10,150.40
Portland Cement 8.320 Kg Rp 1,220.00 Rp 10,150.40
Pasir Pasang 0.032 m³ Rp - Rp -
Tenaga Kerja Rp 94,738.39
Pekerja 0.400 org/hr Rp 137,242.34 Rp 54,896.94
Tukang Batu 0.200 org/hr Rp 166,063.23 Rp 33,212.65
Kepala Tukang 0.020 org/hr Rp 157,828.69 Rp 3,156.57
Mandor 0.022 org/hr Rp 157,828.69 Rp 3,472.23
Jumlah Rp 104,888.79
Keuntungan 10% : Rp 10,488.88
Jumlah : Rp 115,377.67
Dibulatkan : Rp 115,400.00
#VALUE! 1 m' Plesteran Granit 1PC : 2Teraso Tebal 10 mm
Bahan Rp 49,700.00
Portland Cement 10.000 Kg Rp 1,220.00 Rp 12,200.00
Batu Teraso 15.000 Kg Rp 2,500.00 Rp 37,500.00
Tenaga Kerja Rp 106,383.40
Pekerja 0.450 org/hr Rp 137,242.34 Rp 61,759.05
Tukang Batu 0.225 org/hr Rp 166,063.23 Rp 37,364.23
Kepala Tukang 0.023 org/hr Rp 157,828.69 Rp 3,630.06
Mandor 0.023 org/hr Rp 157,828.69 Rp 3,630.06
Jumlah Rp 156,083.40
Keuntungan 10% : Rp 15,608.34
Jumlah : Rp 171,691.74
Dibulatkan : Rp 171,700.00
NO. URAIAN KOEF SATUAN HARGA STUAN SUB. JUMLAH JUMLAH
1 2 2 3 4 5 6

PEKERJAAN PLESTERAN

A.4.4.2.27 1 m² Finishing Acian


Bahan Rp 3,965.00
Portland Cement 3.250 Kg Rp 1,220.00 Rp 3,965.00
Tenaga Kerja Rp 47,211.37
Pekerja 0.200 org/hr Rp 137,242.34 Rp 27,448.47
Tukang Batu 0.100 org/hr Rp 166,063.23 Rp 16,606.32
Kepala Tukang 0.010 org/hr Rp 157,828.69 Rp 1,578.29
Mandor 0.010 org/hr Rp 157,828.69 Rp 1,578.29
Jumlah Rp 51,176.37
Keuntungan 10% : Rp 5,117.64
Jumlah : Rp 56,294.00
Dibulatkan : Rp 56,300.00
A.4.4.2.28 1 m² Flesteran + Acian (Pakai perekat jenis mortar)
Bahan Rp 36,042.86
Sement / mortal ( MU -301) untuk plesteran 19.048 Kg Rp 1,425.00 Rp 27,142.86
Sement / mortal ( MU -200) untuk acian 2.000 Kg Rp 4,450.00 Rp 8,900.00
Tenaga Kerja Rp 58,027.78
Pekerja 0.250 org/hr Rp 137,242.34 Rp 34,310.59
Tukang Batu 0.125 org/hr Rp 166,063.23 Rp 20,757.90
Kepala Tukang 0.013 org/hr Rp 157,828.69 Rp 1,972.86
Mandor 0.006 org/hr Rp 157,828.69 Rp 986.43
Jumlah Rp 94,070.63
Keuntungan 10% : Rp 9,407.06
Jumlah : Rp 103,477.70
Dibulatkan : Rp 103,500.00
NO. URAIAN KOEF SATUAN HARGA STUAN SUB. JUMLAH JUMLAH
1 2 3 4 5 6 7
PEKERJAAN LANTAI

1 1 m² Pasang Lantai keramik Ukuran (33 x 33) cm---Polished


Bahan Rp 94,302.94
Keramik uk. 33x33cm Polished/Glazed 1.089 M2 Rp 63,550.00 Rp 69,205.95
PC 8.140 kg Rp 1,220.00 Rp 9,930.80
PP 0.045 M³ Rp 103,026.47 Rp 4,636.19
Semen Warna 1.620 kg Rp 6,500.00 Rp 10,530.00
Tenaga Kerja Rp 181,898.50
Pekerja 0.700 0rg/hr Rp 157,643.00 Rp 110,350.10
Tukang Batu 0.350 0rg/hr Rp 166,729.00 Rp 58,355.15
Kepala Tukang 0.035 0rg/hr Rp 182,676.00 Rp 6,393.66
Mandor 0.035 0rg/hr Rp 194,274.00 Rp 6,799.59
Jumlah Rp 276,201.44
Keuntungan 10% : Rp 27,620.14
Jumlah : Rp 303,821.59
Dibulatkan : Rp 303,800.00
A.4.4.3.34.a 1 m² Pasang Lantai keramik Ukuran (33 x 33) cm---Unpolished
Bahan Rp 100,330.56
Keramik uk. 33x33cm Unpolished/Anti slip 1.089 M2 Rp 69,085.00 Rp 75,233.57
PC 8.140 kg Rp 1,220.00 Rp 9,930.80
PP 0.045 M³ Rp 103,026.47 Rp 4,636.19
Semen Warna 1.620 kg Rp 6,500.00 Rp 10,530.00
Tenaga Kerja Rp 181,898.50
Pekerja 0.700 0rg/hr Rp 157,643.00 Rp 110,350.10
Tukang Batu 0.350 0rg/hr Rp 166,729.00 Rp 58,355.15
Kepala Tukang 0.035 0rg/hr Rp 182,676.00 Rp 6,393.66
Mandor 0.035 0rg/hr Rp 194,274.00 Rp 6,799.59
Jumlah Rp 282,229.06
Keuntungan 10% : Rp 28,222.91
Jumlah : Rp 310,451.96
Dibulatkan : Rp 310,500.00
A.4.4.3.35 1 m² Pasang Lantai Keramik Ukuran (30 x 30) cm---Polished setara DN
Bahan Rp 91,176.21
Keramik uk. 30x30cm polished/Glazed 1.050 M2 Rp 62,000.00 Rp 65,100.00
PC 10.000 kg Rp 1,220.00 Rp 12,200.00
PP 0.045 M³ Rp 91,693.56 Rp 4,126.21
Semen Warna 1.500 kg Rp 6,500.00 Rp 9,750.00
Tenaga Kerja Rp 165,239.78
Pekerja 0.700 0rg/hr Rp 137,242.34 Rp 96,069.64
Tukang Batu 0.350 0rg/hr Rp 166,063.23 Rp 58,122.13
Kepala Tukang 0.035 0rg/hr Rp 157,828.69 Rp 5,524.00
Mandor 0.035 0rg/hr Rp 157,828.69 Rp 5,524.00
Jumlah Rp 256,415.99
Keuntungan 10% : Rp 25,641.60
Jumlah : Rp 282,057.59
Dibulatkan : Rp 282,100.00
A.4.4.3.35a 1 m² Pasang Lantai Keramik Ukuran (30 x 30) cm---Unpolished setara DN
Bahan Rp 96,846.21
Keramik uk. 30x30cm Unpolished/Anti slip 1.050 M2 Rp 67,400.00 Rp 70,770.00
PC 10.000 kg Rp 1,220.00 Rp 12,200.00
PP 0.045 M³ Rp 91,693.56 Rp 4,126.21
Semen Warna 1.500 kg Rp 6,500.00 Rp 9,750.00
Tenaga Kerja Rp 165,239.78
Pekerja 0.700 0rg/hr Rp 137,242.34 Rp 96,069.64
Tukang Batu 0.350 0rg/hr Rp 166,063.23 Rp 58,122.13
Kepala Tukang 0.035 0rg/hr Rp 157,828.69 Rp 5,524.00
Mandor 0.035 0rg/hr Rp 157,828.69 Rp 5,524.00
Jumlah Rp 262,085.99
Keuntungan 10% : Rp 26,208.60
Jumlah : Rp 288,294.59
Dibulatkan : Rp 288,300.00
A.4.4.3.35b 1 m² Pasang Lantai Keramik Ukuran (30 x 30) cm---Polished setara Roman Gol. C
Bahan Rp 122,978.30
Keramik uk. 30x30cm polished/Glazed 1.050 M2 Rp 91,802.01 Rp 96,392.11
PC 10.000 kg Rp 1,220.00 Rp 12,200.00
PP 0.045 M³ Rp 103,026.47 Rp 4,636.19
Semen Warna 1.500 kg Rp 6,500.00 Rp 9,750.00
Tenaga Kerja Rp 181,898.50
Pekerja 0.700 0rg/hr Rp 157,643.00 Rp 110,350.10
Tukang Batu 0.350 0rg/hr Rp 166,729.00 Rp 58,355.15
Kepala Tukang 0.035 0rg/hr Rp 182,676.00 Rp 6,393.66
Mandor 0.035 0rg/hr Rp 194,274.00 Rp 6,799.59
Jumlah Rp 304,876.80
Keuntungan 10% : Rp 30,487.68
Jumlah : Rp 335,364.48
Dibulatkan : Rp 335,400.00
A.4.4.3.35c 1 m² Pasang Lantai Keramik Ukuran (30 x 30) cm---Unpolished setara Roman Gol. B
Bahan Rp 94,339.65
Keramik uk. 30x30cm Unpolished/Anti slip 1.050 M2 Rp 64,527.11 Rp 67,753.46
PC 10.000 kg Rp 1,220.00 Rp 12,200.00
PP 0.045 M³ Rp 103,026.47 Rp 4,636.19
Semen Warna 1.500 kg Rp 6,500.00 Rp 9,750.00
Tenaga Kerja Rp 181,898.50
Pekerja 0.700 0rg/hr Rp 157,643.00 Rp 110,350.10
Tukang Batu 0.350 0rg/hr Rp 166,729.00 Rp 58,355.15
Kepala Tukang 0.035 0rg/hr Rp 182,676.00 Rp 6,393.66
Mandor 0.035 0rg/hr Rp 194,274.00 Rp 6,799.59
Jumlah Rp 276,238.15
Keuntungan 10% : Rp 27,623.82
Jumlah : Rp 303,861.97
Dibulatkan : Rp 303,900.00
A.4.4.3.35d 1 m² Pasang Lantai Homogenous Ukuran (30 x 30) cm setra Niro Granit
Bahan Rp 285,936.19
Homogenous Ukuran (30 x 30) cm 1.050 M2 Rp 247,000.00 Rp 259,350.00
PC 10.000 kg Rp 1,220.00 Rp 12,200.00
PP 0.045 M³ Rp 103,026.47 Rp 4,636.19
Semen Warna 1.500 kg Rp 6,500.00 Rp 9,750.00
Tenaga Kerja Rp 181,898.50
ANALISIS HARGA SATUAN PEKERJAAN BIDANG PEKERJAAN UMUMNOMOR : 28/PRT/M/2016
NO. URAIAN KOEF SATUAN HARGA STUAN SUB. JUMLAH JUMLAH
1 2 3 4 5 6 7
PEKERJAAN LANTAI
Pekerja 0.700 0rg/hr Rp 157,643.00 Rp 110,350.10
Tukang Batu 0.350 0rg/hr Rp 166,729.00 Rp 58,355.15
Kepala Tukang 0.035 0rg/hr Rp 182,676.00 Rp 6,393.66
Mandor 0.035 0rg/hr Rp 194,274.00 Rp 6,799.59
Jumlah Rp 467,834.69
Keuntungan 10% : Rp 46,783.47
Jumlah : Rp 514,618.16
Dibulatkan : Rp 514,600.00
A.4.4.3.36. 1 m² Pasang Lantai Keramik Ukuran (20 x 20) cm --- Polished/Glazed setara DN
Bahan Rp 80,544.21
Keramik uk. 20x20cm Polished/Glazed 1.050 M2 Rp 57,600.00 Rp 60,480.00
PC 10.400 kg Rp 1,220.00 Rp 12,688.00
PP 0.045 M³ Rp 91,693.56 Rp 4,126.21
Semen Warna 0.500 kg Rp 6,500.00 Rp 3,250.00
Tenaga Kerja Rp 165,239.78
Pekerja 0.700 0rg/hr Rp 137,242.34 Rp 96,069.64
Tukang Batu 0.350 0rg/hr Rp 166,063.23 Rp 58,122.13
Kepala Tukang 0.035 0rg/hr Rp 157,828.69 Rp 5,524.00
Mandor 0.035 0rg/hr Rp 157,828.69 Rp 5,524.00
Jumlah Rp 245,783.99
Keuntungan 10% : Rp 24,578.40
Jumlah : Rp 270,362.39
Dibulatkan : Rp 270,400.00
A.4.4.3.36a 1 m² Pasang Lantai Keramik Ukuran (30 x 30) cm wx. Roman KW,1
Bahan Rp 77,324.19
Keramik uk. 30x30cm 10.000 bh Rp 6,000.00 Rp 60,000.00
PC 10.400 kg Rp 1,220.00 Rp 12,688.00
PP 0.045 M³ Rp 103,026.47 Rp 4,636.19
Tenaga Kerja Rp 125,814.85
Pekerja 0.450 0rg/hr Rp 157,643.00 Rp 70,939.35
Tukang Batu 0.250 0rg/hr Rp 166,729.00 Rp 41,682.25
Kepala Tukang 0.035 0rg/hr Rp 182,676.00 Rp 6,393.66
Mandor 0.035 0rg/hr Rp 194,274.00 Rp 6,799.59
Jumlah Rp 203,139.04
Keuntungan 10% : Rp 20,313.90
Jumlah : Rp 223,452.95
Dibulatkan : Rp 223,000.00
#VALUE! 1 m² Pasang Lantai Keramik Ukuran (10 x 33) cm. variasi/border
Bahan Rp -
Keramik uk. 10x33cm 33.000 buah Rp 3,250.00
PC 9.800 kg Rp 1,220.00
PP 0.045 M³ Rp 103,026.47
Semen Warna 4.370 kg Rp 6,500.00
Tenaga Kerja Rp -
Pekerja 1.050 0rg/hr Rp 157,643.00
Tukang Batu 0.525 0rg/hr Rp 166,729.00
Kepala Tukang 0.053 0rg/hr Rp 182,676.00
Mandor 0.053 0rg/hr Rp 194,274.00
Jumlah Rp -
Keuntungan 10% : Rp -
Jumlah : Rp -
Dibulatkan : Rp -
#VALUE! 1 m² Pasang Lantai Mosaik Ukuran (30 x 30) cm. Campuran Spesi 1 PC : 3 PP
Bahan Rp -
Mosaik 11.870 buah
PC 14.150 kg
PP 0.039 M³
Semen Warna 2.000 kg
Tenaga Kerja Rp -
Pekerja 0.700 0rg/hr
Tukang Batu 0.350 0rg/hr
Kepala Tukang 0.035 0rg/hr
Mandor 0.035 0rg/hr
Jumlah Rp -
Keuntungan 10% : Rp -
Jumlah : Rp -
Dibulatkan : Rp -
A.4.4.3.36b 1 m² Pasang Lantai Keramik Ukuran (20 x 20) cm --- Polished/Glazed setara Roman Gol. B
Bahan Rp 96,868.01
Keramik uk. 20x20cm Polished/Glazed 1.050 M2 Rp 72,660.78 Rp 76,293.82
PC 10.400 kg Rp 1,220.00 Rp 12,688.00
PP 0.045 M³ Rp 103,026.47 Rp 4,636.19
Semen Warna 0.500 kg Rp 6,500.00 Rp 3,250.00
Tenaga Kerja Rp 181,898.50
Pekerja 0.700 0rg/hr Rp 157,643.00 Rp 110,350.10
Tukang Batu 0.350 0rg/hr Rp 166,729.00 Rp 58,355.15
Kepala Tukang 0.035 0rg/hr Rp 182,676.00 Rp 6,393.66
Mandor 0.035 0rg/hr Rp 194,274.00 Rp 6,799.59
Jumlah Rp 278,766.51
Keuntungan 10% : Rp 27,876.65
Jumlah : Rp 306,643.16
Dibulatkan : Rp 306,600.00

ANALISIS HARGA SATUAN PEKERJAAN BIDANG PEKERJAAN UMUMNOMOR : 28/PRT/M/2016


NO. URAIAN KOEF SATUAN HARGA STUAN SUB. JUMLAH JUMLAH
1 2 3 4 5 6 7
PEKERJAAN LANTAI
A.4.4.3.36c 1 m² Pasang Lantai Keramik Ukuran (20 x 20) cm --- Unpolished/Anti slip setara Roman Gol. B
Bahan Rp 90,035.72
Keramik uk. 20x20cm Anpolished/Anti slip 1.050 M2 Rp 66,153.84 Rp 69,461.53
PC 10.400 kg Rp 1,220.00 Rp 12,688.00
PP 0.045 M³ Rp 103,026.47 Rp 4,636.19
Semen Warna 0.500 kg Rp 6,500.00 Rp 3,250.00
Tenaga Kerja Rp 181,898.50
Pekerja 0.700 0rg/hr Rp 157,643.00 Rp 110,350.10
Tukang Batu 0.350 0rg/hr Rp 166,729.00 Rp 58,355.15
Kepala Tukang 0.035 0rg/hr Rp 182,676.00 Rp 6,393.66
Mandor 0.035 0rg/hr Rp 194,274.00 Rp 6,799.59
Jumlah Rp 271,934.22
Keuntungan 10% : Rp 27,193.42
Jumlah : Rp 299,127.65
Dibulatkan : Rp 299,100.00
A.4.4.3.39 1 m' Pasang Plint Keramik Ukuran (10 x 20) cm
Bahan Rp 9,017.38
Plint Keramik 10x20 cm 5.300 buah Rp 1,350.00 Rp 7,155.00
PC 1.140 kg Rp 1,220.00 Rp 1,390.80
PP 0.003 M³ Rp 103,026.47 Rp 309.08
Semen Warna 0.025 kg Rp 6,500.00 Rp 162.50
Tenaga Kerja Rp 36,558.51
Pekerja 0.090 0rg/hr Rp 157,643.00 Rp 14,187.87
Tukang Batu 0.090 0rg/hr Rp 166,729.00 Rp 15,005.61
Kepala Tukang 0.035 0rg/hr Rp 182,676.00 Rp 6,393.66
Mandor 0.005 0rg/hr Rp 194,274.00 Rp 971.37
Jumlah Rp 45,575.89
Keuntungan 10% : Rp 4,557.59
Jumlah : Rp 50,133.48
Dibulatkan : Rp 50,100.00
A.4.4.3.39a 1 m' Pasang Plint Keramik Ukuran (10 x 30) cm
Bahan Rp 12,695.71
Plint Keramik 10 x 30 3.333 buah Rp 3,250.00 Rp 10,833.33
PC 1.140 kg Rp 1,220.00 Rp 1,390.80
PP 0.003 M³ Rp 103,026.47 Rp 309.08
Semen Warna 0.025 kg Rp 6,500.00 Rp 162.50
Tenaga Kerja Rp 31,808.93
Pekerja 0.090 0rg/hr Rp 157,643.00 Rp 14,187.87
Tukang Batu 0.090 0rg/hr Rp 166,729.00 Rp 15,005.61
Kepala Tukang 0.009 0rg/hr Rp 182,676.00 Rp 1,644.08
Mandor 0.005 0rg/hr Rp 194,274.00 Rp 971.37
Jumlah Rp 44,504.65
Keuntungan 10% : Rp 4,450.46
Jumlah : Rp 48,955.11
Dibulatkan : Rp 49,000.00
1 1 m' Pasang Plint Keramik Ukuran (10 x 40) cm
Bahan Rp 10,828.38
Plint Keramik 10 x 40 2.500 buah Rp 3,600.00 Rp 9,000.00
PC 1.140 kg Rp 1,220.00 Rp 1,390.80
PP 0.003 M³ Rp 91,693.56 Rp 275.08
Semen Warna 0.025 kg Rp 6,500.00 Rp 162.50
Tenaga Kerja Rp 29,507.10
Pekerja 0.090 0rg/hr Rp 137,242.34 Rp 12,351.81
Tukang Batu 0.090 0rg/hr Rp 166,063.23 Rp 14,945.69
Kepala Tukang 0.009 0rg/hr Rp 157,828.69 Rp 1,420.46
Mandor 0.005 0rg/hr Rp 157,828.69 Rp 789.14
Jumlah Rp 40,335.48
Keuntungan 10% : Rp 4,033.55
Jumlah : Rp 44,369.03
Dibulatkan : Rp 44,400.00
A.4.4.3.39c 1 m' Pasang Plint Keramik Ukuran (10 x 60) cm
Bahan Rp 12,695.71
Plint Keramik 10 x 40 1.667 buah Rp 6,500.00 Rp 10,833.33
PC 1.140 kg Rp 1,220.00 Rp 1,390.80
PP 0.003 M³ Rp 103,026.47 Rp 309.08
Semen Warna 0.025 kg Rp 6,500.00 Rp 162.50
Tenaga Kerja Rp 31,808.93
Pekerja 0.090 0rg/hr Rp 157,643.00 Rp 14,187.87
Tukang Batu 0.090 0rg/hr Rp 166,729.00 Rp 15,005.61
Kepala Tukang 0.009 0rg/hr Rp 182,676.00 Rp 1,644.08
Mandor 0.005 0rg/hr Rp 194,274.00 Rp 971.37
Jumlah Rp 44,504.65
Keuntungan 10% : Rp 4,450.46
Jumlah : Rp 48,955.11
Dibulatkan : Rp 49,000.00
A.4.4.3.39d 1 m' Pasang Plint Homogeneus Ukuran (10 x 30) cm
Bahan Rp 85,195.71
Plint Homogeneus 10 x 30 3.333 buah Rp 25,000.00 Rp 83,333.33
PC 1.140 kg Rp 1,220.00 Rp 1,390.80
PP 0.003 M³ Rp 103,026.47 Rp 309.08
Semen Warna 0.025 kg Rp 6,500.00 Rp 162.50
Tenaga Kerja Rp 31,808.93
Pekerja 0.090 0rg/hr Rp 157,643.00 Rp 14,187.87
Tukang Batu 0.090 0rg/hr Rp 166,729.00 Rp 15,005.61
Kepala Tukang 0.009 0rg/hr Rp 182,676.00 Rp 1,644.08
Mandor 0.005 0rg/hr Rp 194,274.00 Rp 971.37
Jumlah Rp 117,004.65
Keuntungan 10% : Rp 11,700.46
Jumlah : Rp 128,705.11
Dibulatkan : Rp 128,700.00

ANALISIS HARGA SATUAN PEKERJAAN BIDANG PEKERJAAN UMUMNOMOR : 28/PRT/M/2016


NO. URAIAN KOEF SATUAN HARGA STUAN SUB. JUMLAH JUMLAH
1 2 3 4 5 6 7
PEKERJAAN LANTAI
A.4.4.3.39e 1 m' Pasang Plint Homogeneus Ukuran (10 x 40) cm
Bahan Rp 74,612.38
Plint Homogeneus 10 x 40 2.500 buah Rp 29,100.00 Rp 72,750.00
PC 1.140 kg Rp 1,220.00 Rp 1,390.80
PP 0.003 M³ Rp 103,026.47 Rp 309.08
Semen Warna 0.025 kg Rp 6,500.00 Rp 162.50
Tenaga Kerja Rp 31,808.93
Pekerja 0.090 0rg/hr Rp 157,643.00 Rp 14,187.87
Tukang Batu 0.090 0rg/hr Rp 166,729.00 Rp 15,005.61
Kepala Tukang 0.009 0rg/hr Rp 182,676.00 Rp 1,644.08
Mandor 0.005 0rg/hr Rp 194,274.00 Rp 971.37
Jumlah Rp 106,421.31
Keuntungan 10% : Rp 10,642.13
Jumlah : Rp 117,063.44
Dibulatkan : Rp 117,100.00
A.4.4.3.39f 1 m' Pasang Plint Homogeneus Ukuran (10 x 60) cm ex. Roman
Bahan Rp 21,199.88
Plint Homogeneus 10 x 60 0.650 buah Rp 30,000.00 Rp 19,500.00
PC 1.140 kg Rp 1,220.00 Rp 1,390.80
PP 0.003 M³ Rp 103,026.47 Rp 309.08
Tenaga Kerja Rp 31,808.93
Pekerja 0.090 0rg/hr Rp 157,643.00 Rp 14,187.87
Tukang Batu 0.090 0rg/hr Rp 166,729.00 Rp 15,005.61
Kepala Tukang 0.009 0rg/hr Rp 182,676.00 Rp 1,644.08
Mandor 0.005 0rg/hr Rp 194,274.00 Rp 971.37
Jumlah Rp 53,008.81
Keuntungan 10% : Rp 5,300.88
Jumlah : Rp 58,309.69
Dibulatkan : Rp 58,300.00
#VALUE! 1 m' Pasang Border Keramik Ukuran (8 x 20) cm
Bahan Rp 1,862.38
Border Keramik Ukuran (8 x 20) cm 5.000 buah Rp - Rp -
PC 1.140 kg Rp 1,220.00 Rp 1,390.80
PP 0.003 M³ Rp 103,026.47 Rp 309.08
Semen Warna 0.025 kg Rp 6,500.00 Rp 162.50
Tenaga Kerja Rp 31,808.93
Pekerja 0.090 0rg/hr Rp 157,643.00 Rp 14,187.87
Tukang Batu 0.090 0rg/hr Rp 166,729.00 Rp 15,005.61
Kepala Tukang 0.009 0rg/hr Rp 182,676.00 Rp 1,644.08
Mandor 0.005 0rg/hr Rp 194,274.00 Rp 971.37
Jumlah Rp 33,671.31
Keuntungan 10% : Rp 3,367.13
Jumlah : Rp 37,038.44
Dibulatkan : Rp 37,000.00
#VALUE! 1 m' Pasang Border Keramik Ukuran (8 x 25) cm
Bahan Rp 1,862.38
Border Keramik Ukuran (8 x 25) cm 4.000 buah Rp - Rp -
PC 1.140 kg Rp 1,220.00 Rp 1,390.80
PP 0.003 M³ Rp 103,026.47 Rp 309.08
Semen Warna 0.025 kg Rp 6,500.00 Rp 162.50
Tenaga Kerja Rp 31,808.93
Pekerja 0.090 0rg/hr Rp 157,643.00 Rp 14,187.87
Tukang Batu 0.090 0rg/hr Rp 166,729.00 Rp 15,005.61
Kepala Tukang 0.009 0rg/hr Rp 182,676.00 Rp 1,644.08
Mandor 0.005 0rg/hr Rp 194,274.00 Rp 971.37
Jumlah Rp 33,671.31
Keuntungan 10% : Rp 3,367.13
Jumlah : Rp 37,038.44
Dibulatkan : Rp 37,000.00
#VALUE! 1 m' Pasang Border Keramik Ukuran (8 x 30) cm
Bahan Rp 1,862.38
Border Keramik Ukuran (8 x 30) cm 3.333 buah Rp - Rp -
PC 1.140 kg Rp 1,220.00 Rp 1,390.80
PP 0.003 M³ Rp 103,026.47 Rp 309.08
Semen Warna 0.025 kg Rp 6,500.00 Rp 162.50
Tenaga Kerja Rp 31,808.93
Pekerja 0.090 0rg/hr Rp 157,643.00 Rp 14,187.87
Tukang Batu 0.090 0rg/hr Rp 166,729.00 Rp 15,005.61
Kepala Tukang 0.009 0rg/hr Rp 182,676.00 Rp 1,644.08
Mandor 0.005 0rg/hr Rp 194,274.00 Rp 971.37
Jumlah Rp 33,671.31
Keuntungan 10% : Rp 3,367.13
Jumlah : Rp 37,038.44
Dibulatkan : Rp 37,000.00
A.4.4.3.39g 1 m' Pasang Stair nozing Keramik Ukuran (10 x 20) cm
Bahan Rp 64,362.38
Stair nozing Keramik Ukuran (10 x 20) cm 5.000 buah Rp 12,500.00 Rp 62,500.00
PC 1.140 kg Rp 1,220.00 Rp 1,390.80
PP 0.003 M³ Rp 103,026.47 Rp 309.08
Semen Warna 0.025 kg Rp 6,500.00 Rp 162.50
Tenaga Kerja Rp 31,808.93
Pekerja 0.090 0rg/hr Rp 157,643.00 Rp 14,187.87
Tukang Batu 0.090 0rg/hr Rp 166,729.00 Rp 15,005.61
Kepala Tukang 0.009 0rg/hr Rp 182,676.00 Rp 1,644.08
Mandor 0.005 0rg/hr Rp 194,274.00 Rp 971.37
Jumlah Rp 96,171.31
Keuntungan 10% : Rp 9,617.13
Jumlah : Rp 105,788.44
Dibulatkan : Rp 105,800.00
A.4.4.3.39h 1 m' Pasang Stair nozing Keramik Ukuran (10 x 30) cm
Bahan Rp 71,862.38
Stair nozing Keramik Ukuran (10 x 30) cm 3.333 buah Rp 21,000.00 Rp 70,000.00
PC 1.140 kg Rp 1,220.00 Rp 1,390.80
PP 0.003 M³ Rp 103,026.47 Rp 309.08
Semen Warna 0.025 kg Rp 6,500.00 Rp 162.50
Tenaga Kerja Rp 31,808.93
Pekerja 0.090 0rg/hr Rp 157,643.00 Rp 14,187.87
Tukang Batu 0.090 0rg/hr Rp 166,729.00 Rp 15,005.61
ANALISIS HARGA SATUAN PEKERJAAN BIDANG PEKERJAAN UMUMNOMOR : 28/PRT/M/2016
NO. URAIAN KOEF SATUAN HARGA STUAN SUB. JUMLAH JUMLAH
1 2 3 4 5 6 7
PEKERJAAN LANTAI
Kepala Tukang 0.009 0rg/hr Rp 182,676.00 Rp 1,644.08
Mandor 0.005 0rg/hr Rp 194,274.00 Rp 971.37
Jumlah Rp 103,671.31
Keuntungan 10% : Rp 10,367.13
Jumlah : Rp 114,038.44
Dibulatkan : Rp 114,000.00
A.4.4.3.39i 1 m' Pasang Stair nozing Keramik Ukuran (10 x 40 ) cm
Bahan Rp 76,862.38
Stair nozing Keramik Ukuran (10 x 40) cm 2.500 buah Rp 30,000.00 Rp 75,000.00
PC 1.140 kg Rp 1,220.00 Rp 1,390.80
PP 0.003 M³ Rp 103,026.47 Rp 309.08
Semen Warna 0.025 kg Rp 6,500.00 Rp 162.50
Tenaga Kerja Rp 31,808.93
Pekerja 0.090 0rg/hr Rp 157,643.00 Rp 14,187.87
Tukang Batu 0.090 0rg/hr Rp 166,729.00 Rp 15,005.61
Kepala Tukang 0.009 0rg/hr Rp 182,676.00 Rp 1,644.08
Mandor 0.005 0rg/hr Rp 194,274.00 Rp 971.37
Jumlah Rp 108,671.31
Keuntungan 10% : Rp 10,867.13
Jumlah : Rp 119,538.44
Dibulatkan : Rp 119,500.00
#VALUE! 1 m' Pasang Plint Keramik Ukuran (10 x 10) cm
Bahan Rp -
Plint Keramik Artistik 10.600 buah
PC 1.140 kg
PP 0.003 M³
Semen Warna 0.005 kg
Tenaga Kerja Rp -
Pekerja 0.090 0rg/hr
Tukang Batu 0.090 0rg/hr
Kepala Tukang 0.009 0rg/hr
Mandor 0.005 0rg/hr
Jumlah Rp -
Keuntungan 10% : Rp -
Jumlah : Rp -
Dibulatkan : Rp -
#VALUE! 1 m' Pasang Plint Keramik Ukuran (5 x 20) cm
Bahan Rp -
Plint Keramik Artistik 5.300 buah
PC 0.570 kg
PP 0.002 M³
Semen Warna 0.013 kg
Tenaga Kerja Rp -
Pekerja 0.090 0rg/hr
Tukang Batu 0.090 0rg/hr
Kepala Tukang 0.009 0rg/hr
Mandor 0.005 0rg/hr
Jumlah Rp -
Keuntungan 10% : Rp -
Jumlah : Rp -
Dibulatkan : Rp -
#VALUE! 1 m' Pasang Plint Internal Cove Artistik Ukuran (5 x 5 x 20) cm
Bahan Rp -
Internal Cove 5.300 buah
PC 1.140 kg
PP 0.003 M³
Semen Warna 0.100 kg
Tenaga Kerja Rp -
Pekerja 0.750 0rg/hr
Tukang Batu 0.450 0rg/hr
Kepala Tukang 0.045 0rg/hr
Mandor 0.038 0rg/hr
Jumlah Rp -
Keuntungan 10% : Rp -
Jumlah : Rp -
Dibulatkan : Rp -
#VALUE! 1 m2 Pasang lantai Marmer Ukuran (100x100) cm
Bahan Rp 1,608,852.99
Marmer setara Ujung Pandang 1.060 buah Rp 1,500,000.00 Rp 1,590,000.00
PC 8.190 kg Rp 1,220.00 Rp 9,991.80
PP 0.045 M³ Rp 103,026.47 Rp 4,636.19
Semen Warna 0.650 kg Rp 6,500.00 Rp 4,225.00
Tenaga Kerja Rp 181,898.50
Pekerja 0.700 0rg/hr Rp 157,643.00 Rp 110,350.10
Tukang Batu 0.350 0rg/hr Rp 166,729.00 Rp 58,355.15
Kepala Tukang 0.035 0rg/hr Rp 182,676.00 Rp 6,393.66
Mandor 0.035 0rg/hr Rp 194,274.00 Rp 6,799.59
Jumlah Rp 1,790,751.49
Keuntungan 10% : Rp 179,075.15
Jumlah : Rp 1,969,826.64
Dibulatkan : Rp 1,969,800.00

ANALISIS HARGA SATUAN PEKERJAAN BIDANG PEKERJAAN UMUMNOMOR : 28/PRT/M/2016


NO. URAIAN KOEF SATUAN HARGA STUAN SUB. JUMLAH JUMLAH
1 2 3 4 5 6 7
PEKERJAAN LANTAI
1 m2 Pasang lantai Marmer Ukuran (60x60) cm
Bahan Rp 209,143.01
Marmer setara Ujung Pandang 1.060 buah Rp 180,000.00 Rp 190,800.00
PC 8.190 kg Rp 1,220.00 Rp 9,991.80
PP 0.045 M³ Rp 91,693.56 Rp 4,126.21
Semen Warna 0.650 kg Rp 6,500.00 Rp 4,225.00
Tenaga Kerja Rp 165,239.78
Pekerja 0.700 0rg/hr Rp 137,242.34 Rp 96,069.64
Tukang Batu 0.350 0rg/hr Rp 166,063.23 Rp 58,122.13
Kepala Tukang 0.035 0rg/hr Rp 157,828.69 Rp 5,524.00
Mandor 0.035 0rg/hr Rp 157,828.69 Rp 5,524.00
Jumlah Rp 374,382.79
Keuntungan 10% : Rp 37,438.28
Jumlah : Rp 411,821.07
Dibulatkan : Rp 411,800.00
1 1 m2 Pasang lantai Marmer Ukuran (40x40) cm
Bahan Rp 177,852.99
Marmer setara Ujung Pandang 1.060 buah Rp 150,000.00 Rp 159,000.00
PC 8.190 kg Rp 1,220.00 Rp 9,991.80
PP 0.045 M³ Rp 103,026.47 Rp 4,636.19
Semen Warna 0.650 kg Rp 6,500.00 Rp 4,225.00
Tenaga Kerja Rp 181,898.50
Pekerja 0.700 0rg/hr Rp 157,643.00 Rp 110,350.10
Tukang Batu 0.350 0rg/hr Rp 166,729.00 Rp 58,355.15
Kepala Tukang 0.035 0rg/hr Rp 182,676.00 Rp 6,393.66
Mandor 0.035 0rg/hr Rp 194,274.00 Rp 6,799.59
Jumlah Rp 359,751.49
Keuntungan 10% : Rp 35,975.15
Jumlah : Rp 395,726.64
Dibulatkan : Rp 395,700.00
2 1 m2 Pasang lantai Granit alam solid
Bahan Rp 197,992.99
Granit alam ex. Cina 1.060 buah Rp 169,000.00 Rp 179,140.00
PC 8.190 kg Rp 1,220.00 Rp 9,991.80
PP 0.045 M³ Rp 103,026.47 Rp 4,636.19
Semen Warna 0.650 kg Rp 6,500.00 Rp 4,225.00
Tenaga Kerja Rp 181,898.50
Pekerja 0.700 0rg/hr Rp 157,643.00 Rp 110,350.10
Tukang Batu 0.350 0rg/hr Rp 166,729.00 Rp 58,355.15
Kepala Tukang 0.035 0rg/hr Rp 182,676.00 Rp 6,393.66
Mandor 0.035 0rg/hr Rp 194,274.00 Rp 6,799.59
Jumlah Rp 379,891.49
Keuntungan 10% : Rp 37,989.15
Jumlah : Rp 417,880.64
Dibulatkan : Rp 417,900.00
3 1 m² Pasang Lantai Karpet
Bahan Rp 19,250.00
Karpet Feltex 80% wool, 20% nylon 1.050 M² - Rp -
Lem 0.350 kg 55,000.00 Rp 19,250.00
Tenaga Kerja Rp 59,997.20
Pekerja 0.170 0rg/hr Rp 157,643.00 Rp 26,799.31
Tukang 0.170 0rg/hr Rp 166,729.00 Rp 28,343.93
Kepala Tukang 0.017 0rg/hr Rp 182,676.00 Rp 3,105.49
Mandor 0.009 0rg/hr Rp 194,274.00 Rp 1,748.47
Jumlah Rp 79,247.20
Keuntungan 10% : Rp 7,924.72
Jumlah : Rp 87,171.92
Dibulatkan : Rp 87,200.00
4 1 m² Pasang underlayer / Pelapis bawah karpet Karpet
Bahan Rp 45,500.00
Underlayer / rubber corrugated 1.050 M² 25,000.00 Rp 26,250.00
Lem 0.350 kg 55,000.00 Rp 19,250.00
Tenaga Kerja Rp 42,282.40
Pekerja 0.120 0rg/hr Rp 157,643.00 Rp 18,917.16
Tukang 0.120 0rg/hr Rp 166,729.00 Rp 20,007.48
Kepala Tukang 0.012 0rg/hr Rp 182,676.00 Rp 2,192.11
Mandor 0.006 0rg/hr Rp 194,274.00 Rp 1,165.64
Jumlah Rp 87,782.40
Keuntungan 10% : Rp 8,778.24
Jumlah : Rp 96,560.64
Dibulatkan : Rp 96,600.00
5 1 m² Pasang Lantai Parquet kayu Jati
Bahan Rp 33,000.00
Lantai parquet kayu jati 1.050 M² - Rp -
Lem 0.600 kg 55,000.00 Rp 33,000.00
Tenaga Kerja Rp 181,898.50
Pekerja 0.700 0rg/hr Rp 157,643.00 Rp 110,350.10
Tukang Batu 0.350 0rg/hr Rp 166,729.00 Rp 58,355.15
Kepala Tukang 0.035 0rg/hr Rp 182,676.00 Rp 6,393.66
Mandor 0.035 0rg/hr Rp 194,274.00 Rp 6,799.59
Jumlah Rp 214,898.50
Keuntungan 10% : Rp 21,489.85
Jumlah : Rp 236,388.35
Dibulatkan : Rp 236,400.00
6 1 m² Pasang Lantai kayu ( Gym floor )
Bahan Rp 33,000.00
Gym floor 1.050 M² -Rp -
Lem 0.600 kg 55,000.00 Rp 33,000.00
Tenaga Kerja Rp 181,898.50
Pekerja 0.700 0rg/hr Rp 157,643.00 Rp 110,350.10
Tukang Batu 0.350 0rg/hr Rp 166,729.00 Rp 58,355.15
Kepala Tukang 0.035 0rg/hr Rp 182,676.00 Rp 6,393.66
Mandor 0.035 0rg/hr Rp 194,274.00 Rp 6,799.59
Jumlah Rp 214,898.50
Keuntungan 10% : Rp 21,489.85
Jumlah : Rp 236,388.35
Dibulatkan : Rp 236,400.00

ANALISIS HARGA SATUAN PEKERJAAN BIDANG PEKERJAAN UMUMNOMOR : 28/PRT/M/2016


NO. URAIAN KOEF SATUAN HARGA STUAN SUB. JUMLAH JUMLAH
1 2 3 4 5 6 7
PEKERJAAN LANTAI
7 1 m² Pasang Dinding Porselin Ukuran (11 x 11) cm
Bahan Rp -
Porselin 53.000 buah
PC 9.300 kg
PP 0.018 M³
Semen Warna 2.750 kg
Tenaga Kerja Rp -
Pekerja 1.000 0rg/hr
Tukang Batu 0.500 0rg/hr
Kepala Tukang 0.050 0rg/hr
Mandor 0.050 0rg/hr
Jumlah Rp -
Keuntungan 10% : Rp -
Jumlah : Rp -
Dibulatkan : Rp -
8 1 m² Pasang Dinding Porselin Ukuran (10 x 20) cm
Bahan Rp -
Porselin 53.000 buah
PC 9.300 kg
PP 0.018 M³
Semen Warna 2.750 kg
Tenaga Kerja Rp -
Pekerja 0.125 0rg/hr
Tukang Batu 0.251 0rg/hr
Kepala Tukang 0.050 0rg/hr
Mandor 0.010 0rg/hr
Jumlah Rp -
Keuntungan 10% : Rp -
Jumlah : Rp -
Dibulatkan : Rp -
9 1 m² Pasang Dinding Porselin Ukuran (20 x 20) cm
Bahan Rp -
Porselin 26.000 buah Rp -
PC 9.300 kg Rp -
PP 0.018 M³ Rp -
Semen Warna 1.940 kg Rp -
Tenaga Kerja Rp -
Pekerja 0.125 0rg/hr Rp -
Tukang Batu 0.251 0rg/hr Rp -
Kepala Tukang 0.050 0rg/hr Rp -
Mandor 0.010 0rg/hr Rp -
Jumlah Rp -
Keuntungan 10% : Rp -
Jumlah : Rp -
Dibulatkan : Rp -
10 1 m² Pasang Dinding Keramik artistik Ukuran (10 x 20) cm
Bahan Rp -
Keramik artistik Ukuran (10 x 20) cm 53.000 buah Rp -
PC 9.300 kg Rp -
PP 0.018 M³ Rp -
Semen Warna 2.750 kg Rp -
Tenaga Kerja Rp -
Pekerja 0.900 0rg/hr Rp -
Tukang Batu 0.450 0rg/hr Rp -
Kepala Tukang 0.045 0rg/hr Rp -
Mandor 0.045 0rg/hr Rp -
Jumlah Rp -
Keuntungan 10% : Rp -
Jumlah : Rp -
Dibulatkan : Rp -
11 1 m² Pasang Dinding Keramik artistik Ukuran (5 x 20) cm
Bahan Rp -
Keramik artistik Ukuran (5 x 20) cm 53.000 buah Rp -
PC 9.300 kg Rp -
PP 0.018 M³ Rp -
Semen Warna 2.750 kg Rp -
Tenaga Kerja Rp -
Pekerja 0.900 0rg/hr Rp -
Tukang Batu 0.450 0rg/hr Rp -
Kepala Tukang 0.045 0rg/hr Rp -
Mandor 0.045 0rg/hr Rp -
Jumlah Rp -
Keuntungan 10% : Rp -
Jumlah : Rp -
Dibulatkan : Rp -
12 1 m² Pasang Dinding Keramik Ukuran (10 x 20) cm
Bahan Rp -
Keramik Ukuran (10 x 20) cm 1.040 M2 Rp -
PC 9.300 kg Rp -
PP 0.045 M³ Rp -
Semen Warna 1.940 kg Rp -
Tenaga Kerja Rp -
Pekerja 0.900 0rg/hr Rp -
Tukang Batu 0.450 0rg/hr Rp -
Kepala Tukang 0.045 0rg/hr Rp -
Mandor 0.045 0rg/hr Rp -
Jumlah Rp -
Keuntungan 10% : Rp -
Jumlah : Rp -
Dibulatkan : Rp -
A.4.4.3.54 1 m² Pasang Dinding Keramik Ukuran (20 x 20) cm---Polished setara DN
Bahan Rp 96,685.48
Keramik Ukuran (20 x 20) cm 1.050 M2 Rp 67,500.00 Rp 70,875.00
PC 9.300 kg Rp 1,220.00 Rp 11,346.00
PP 0.018 M³ Rp 103,026.47 Rp 1,854.48
Semen Warna 1.940 kg Rp 6,500.00 Rp 12,610.00
Tenaga Kerja Rp 233,869.50

ANALISIS HARGA SATUAN PEKERJAAN BIDANG PEKERJAAN UMUMNOMOR : 28/PRT/M/2016


NO. URAIAN KOEF SATUAN HARGA STUAN SUB. JUMLAH JUMLAH
1 2 3 4 5 6 7
PEKERJAAN LANTAI
Pekerja 0.900 0rg/hr Rp 157,643.00 Rp 141,878.70
Tukang Batu 0.450 0rg/hr Rp 166,729.00 Rp 75,028.05
Kepala Tukang 0.045 0rg/hr Rp 182,676.00 Rp 8,220.42
Mandor 0.045 0rg/hr Rp 194,274.00 Rp 8,742.33
Jumlah Rp 330,554.98
Keuntungan 10% : Rp 33,055.50
Jumlah : Rp 363,610.47
Dibulatkan : Rp 363,600.00
A.4.4.3.54a 1 m² Pasang Dinding Keramik Ukuran (20 x 20) cm---Unpolished setara DN
Bahan Rp 91,225.48
Keramik Ukuran (20 x 20) cm 1.050 M2 Rp 62,300.00 Rp 65,415.00
PC 9.300 kg Rp 1,220.00 Rp 11,346.00
PP 0.018 M³ Rp 103,026.47 Rp 1,854.48
Semen Warna 1.940 kg Rp 6,500.00 Rp 12,610.00
Tenaga Kerja Rp 233,869.50
Pekerja 0.900 0rg/hr Rp 157,643.00 Rp 141,878.70
Tukang Batu 0.450 0rg/hr Rp 166,729.00 Rp 75,028.05
Kepala Tukang 0.045 0rg/hr Rp 182,676.00 Rp 8,220.42
Mandor 0.045 0rg/hr Rp 194,274.00 Rp 8,742.33
Jumlah Rp 325,094.98
Keuntungan 10% : Rp 32,509.50
Jumlah : Rp 357,604.47
Dibulatkan : Rp 357,600.00
A.4.4.3.54b 1 m² Pasang Dinding Keramik Ukuran (20 x 20) cm---Polished setara Roman Gol. B
Bahan Rp 167,455.48
Keramik Ukuran (20 x 20) cm Roman 1.050 M2 Rp 134,900.00 Rp 141,645.00
PC 9.300 kg Rp 1,220.00 Rp 11,346.00
PP 0.018 M³ Rp 103,026.47 Rp 1,854.48
Semen Warna 1.940 kg Rp 6,500.00 Rp 12,610.00
Tenaga Kerja Rp 233,869.50
Pekerja 0.900 0rg/hr Rp 157,643.00 Rp 141,878.70
Tukang Batu 0.450 0rg/hr Rp 166,729.00 Rp 75,028.05
Kepala Tukang 0.045 0rg/hr Rp 182,676.00 Rp 8,220.42
Mandor 0.045 0rg/hr Rp 194,274.00 Rp 8,742.33
Jumlah Rp 401,324.98
Keuntungan 10% : Rp 40,132.50
Jumlah : Rp 441,457.47
Dibulatkan : Rp 441,500.00
A.4.4.3.54c 1 m² Pasang Dinding Keramik Ukuran (20 x 20) cm---Unpolished setara Roman Gol. B
Bahan Rp 95,613.62
Keramik Ukuran (20 x 20) cm Roman 1.050 M2 Rp 66,479.19 Rp 69,803.15
PC 9.300 kg Rp 1,220.00 Rp 11,346.00
PP 0.018 M³ Rp 103,026.47 Rp 1,854.48
Semen Warna 1.940 kg Rp 6,500.00 Rp 12,610.00
Tenaga Kerja Rp 233,869.50
Pekerja 0.900 0rg/hr Rp 157,643.00 Rp 141,878.70
Tukang Batu 0.450 0rg/hr Rp 166,729.00 Rp 75,028.05
Kepala Tukang 0.045 0rg/hr Rp 182,676.00 Rp 8,220.42
Mandor 0.045 0rg/hr Rp 194,274.00 Rp 8,742.33
Jumlah Rp 329,483.12
Keuntungan 10% : Rp 32,948.31
Jumlah : Rp 362,431.44
Dibulatkan : Rp 362,400.00
A.4.4.3.54d 1 m² Pasang Dinding Keramik Ukuran (20 x 25) cm ---Polished setara DN
Bahan Rp 99,902.21
Keramik Ukuran (20 x 25) cm 1.050 M2 Rp 68,400.00 Rp 71,820.00
PC 9.300 kg Rp 1,220.00 Rp 11,346.00
PP 0.045 M³ Rp 91,693.56 Rp 4,126.21
Semen Warna 1.940 kg Rp 6,500.00 Rp 12,610.00
Tenaga Kerja Rp 212,451.14
Pekerja 0.900 0rg/hr Rp 137,242.34 Rp 123,518.11
Tukang Batu 0.450 0rg/hr Rp 166,063.23 Rp 74,728.45
Kepala Tukang 0.045 0rg/hr Rp 157,828.69 Rp 7,102.29
Mandor 0.045 0rg/hr Rp 157,828.69 Rp 7,102.29
Jumlah Rp 312,353.35
Keuntungan 10% : Rp 31,235.34
Jumlah : Rp 343,588.69
Dibulatkan : Rp 343,600.00
A.4.4.3.54e 1 m² Pasang Dinding Keramik Ukuran (20 x 25) cm ---Unpolished setara DN
Bahan Rp 100,412.19
Keramik Ukuran (20 x 25) cm 1.050 M2 Rp 68,400.00 Rp 71,820.00
PC 9.300 kg Rp 1,220.00 Rp 11,346.00
PP 0.045 M³ Rp 103,026.47 Rp 4,636.19
Semen Warna 1.940 kg Rp 6,500.00 Rp 12,610.00
Tenaga Kerja Rp 233,869.50
Pekerja 0.900 0rg/hr Rp 157,643.00 Rp 141,878.70
Tukang Batu 0.450 0rg/hr Rp 166,729.00 Rp 75,028.05
Kepala Tukang 0.045 0rg/hr Rp 182,676.00 Rp 8,220.42
Mandor 0.045 0rg/hr Rp 194,274.00 Rp 8,742.33
Jumlah Rp 334,281.69
Keuntungan 10% : Rp 33,428.17
Jumlah : Rp 367,709.86
Dibulatkan : Rp 367,700.00
A.4.4.3.54f 1 m² Pasang Dinding Keramik Ukuran (20 x 25) cm ---Polished setara Roman Gol. B
Bahan Rp 149,762.19
Keramik Ukuran (20 x 25) cm Roman 1.050 M2 Rp 115,400.00 Rp 121,170.00
PC 9.300 kg Rp 1,220.00 Rp 11,346.00
PP 0.045 M³ Rp 103,026.47 Rp 4,636.19
Semen Warna 1.940 kg Rp 6,500.00 Rp 12,610.00
Tenaga Kerja Rp 233,869.50
Pekerja 0.900 0rg/hr Rp 157,643.00 Rp 141,878.70
Tukang Batu 0.450 0rg/hr Rp 166,729.00 Rp 75,028.05
Kepala Tukang 0.045 0rg/hr Rp 182,676.00 Rp 8,220.42
Mandor 0.045 0rg/hr Rp 194,274.00 Rp 8,742.33
Jumlah Rp 383,631.69
Keuntungan 10% : Rp 38,363.17
Jumlah : Rp 421,994.86
ANALISIS HARGA SATUAN PEKERJAAN BIDANG PEKERJAAN UMUMNOMOR : 28/PRT/M/2016
NO. URAIAN KOEF SATUAN HARGA STUAN SUB. JUMLAH JUMLAH
1 2 3 4 5 6 7
PEKERJAAN LANTAI
Dibulatkan : Rp 422,000.00
A.4.4.3.54g 1 m² Pasang Dinding Keramik Ukuran (20 x 25) cm ---Unpolished setara Roman Gol. A
Bahan Rp 157,322.19
Keramik Ukuran (20 x 25) cm Roman 1.050 M2 Rp 122,600.00 Rp 128,730.00
PC 9.300 kg Rp 1,220.00 Rp 11,346.00
PP 0.045 M³ Rp 103,026.47 Rp 4,636.19
Semen Warna 1.940 kg Rp 6,500.00 Rp 12,610.00
Tenaga Kerja Rp 233,869.50
Pekerja 0.900 0rg/hr Rp 157,643.00 Rp 141,878.70
Tukang Batu 0.450 0rg/hr Rp 166,729.00 Rp 75,028.05
Kepala Tukang 0.045 0rg/hr Rp 182,676.00 Rp 8,220.42
Mandor 0.045 0rg/hr Rp 194,274.00 Rp 8,742.33
Jumlah Rp 391,191.69
Keuntungan 10% : Rp 39,119.17
Jumlah : Rp 430,310.86
Dibulatkan : Rp 430,300.00
A.4.4.3.54h 1 m² Pasang Dinding Keramik Ukuran (30 x 60) cm Roman
Bahan Rp 135,982.19
Keramik Ukuran (20 x 40) cm, Roman 6.000 BH Rp 20,000.00 Rp 120,000.00
PC 9.300 kg Rp 1,220.00 Rp 11,346.00
PP 0.045 M³ Rp 103,026.47 Rp 4,636.19
Tenaga Kerja Rp 138,481.41
Pekerja 0.500 0rg/hr Rp 157,643.00 Rp 78,821.50
Tukang Batu 0.290 0rg/hr Rp 166,729.00 Rp 48,351.41
Kepala Tukang 0.030 0rg/hr Rp 182,676.00 Rp 5,480.28
Mandor 0.030 0rg/hr Rp 194,274.00 Rp 5,828.22
Jumlah Rp 274,463.60
Keuntungan 10% : Rp 27,446.36
Jumlah : Rp 301,909.96
Dibulatkan : Rp 301,900.00
A.4.4.3.54i 1 m² Pasang Dinding Keramik Ukuran (20 x 25) cm---Unpolished setara Roman Gol. B
Bahan Rp 100,412.19
Keramik Ukuran (20 x 25) cm, Roman 1.050 M2 Rp 68,400.00 Rp 71,820.00
PC 9.300 kg Rp 1,220.00 Rp 11,346.00
PP 0.045 M³ Rp 103,026.47 Rp 4,636.19
Semen Warna 1.940 kg Rp 6,500.00 Rp 12,610.00
Tenaga Kerja Rp 233,869.50
Pekerja 0.900 0rg/hr Rp 157,643.00 Rp 141,878.70
Tukang Batu 0.450 0rg/hr Rp 166,729.00 Rp 75,028.05
Kepala Tukang 0.045 0rg/hr Rp 182,676.00 Rp 8,220.42
Mandor 0.045 0rg/hr Rp 194,274.00 Rp 8,742.33
Jumlah Rp 334,281.69
Keuntungan 10% : Rp 33,428.17
Jumlah : Rp 367,709.86
Dibulatkan : Rp 367,700.00
A.4.4.3.54j 1 m² Pasang Dinding Keramik Ukuran (30 x 30 ) cm ---Polished setara DN
Bahan Rp 104,192.19
Keramik Ukuran (30 x 30) cm 1.050 M2 Rp 72,000.00 Rp 75,600.00
PC 9.300 kg Rp 1,220.00 Rp 11,346.00
PP 0.045 M³ Rp 103,026.47 Rp 4,636.19
Semen Warna 1.940 kg Rp 6,500.00 Rp 12,610.00
Tenaga Kerja Rp 233,869.50
Pekerja 0.900 0rg/hr Rp 157,643.00 Rp 141,878.70
Tukang Batu 0.450 0rg/hr Rp 166,729.00 Rp 75,028.05
Kepala Tukang 0.045 0rg/hr Rp 182,676.00 Rp 8,220.42
Mandor 0.045 0rg/hr Rp 194,274.00 Rp 8,742.33
Jumlah Rp 338,061.69
Keuntungan 10% : Rp 33,806.17
Jumlah : Rp 371,867.86
Dibulatkan : Rp 371,900.00
A.4.4.3.54k 1 m² Pasang Dinding Keramik Ukuran (30 x 30 ) cm ---Unpolished setara DN
Bahan Rp 99,362.19
Keramik Ukuran (30 x 30) cm 1.050 M2 Rp 67,400.00 Rp 70,770.00
PC 9.300 kg Rp 1,220.00 Rp 11,346.00
PP 0.045 M³ Rp 103,026.47 Rp 4,636.19
Semen Warna 1.940 kg Rp 6,500.00 Rp 12,610.00
Tenaga Kerja Rp 233,869.50
Pekerja 0.900 0rg/hr Rp 157,643.00 Rp 141,878.70
Tukang Batu 0.450 0rg/hr Rp 166,729.00 Rp 75,028.05
Kepala Tukang 0.045 0rg/hr Rp 182,676.00 Rp 8,220.42
Mandor 0.045 0rg/hr Rp 194,274.00 Rp 8,742.33
Jumlah Rp 333,231.69
Keuntungan 10% : Rp 33,323.17
Jumlah : Rp 366,554.86
Dibulatkan : Rp 366,600.00
A.4.4.3.54l 1 m² Pasang Dinding Keramik Ukuran (30 x 30 ) cm ---Polished setara Roman Gol. C
Bahan Rp 104,192.19
Keramik Ukuran (30 x 30) cm Roman 1.050 M2 Rp 72,000.00 Rp 75,600.00
PC 9.300 kg Rp 1,220.00 Rp 11,346.00
PP 0.045 M³ Rp 103,026.47 Rp 4,636.19
Semen Warna 1.940 kg Rp 6,500.00 Rp 12,610.00
Tenaga Kerja Rp 233,869.50
Pekerja 0.900 0rg/hr Rp 157,643.00 Rp 141,878.70
Tukang Batu 0.450 0rg/hr Rp 166,729.00 Rp 75,028.05
Kepala Tukang 0.045 0rg/hr Rp 182,676.00 Rp 8,220.42
Mandor 0.045 0rg/hr Rp 194,274.00 Rp 8,742.33
Jumlah Rp 338,061.69
Keuntungan 10% : Rp 33,806.17
Jumlah : Rp 371,867.86
Dibulatkan : Rp 371,900.00
54.d 1 m² Pasang Dinding Homogeneus tile Ukuran (30 x 30 ) cm
Bahan Rp 962,792.19
Homogeneus tile Ukuran (30 x 30) cm ex. 1.080 M2 Rp 865,000.00 Rp 934,200.00
PC 9.300 kg Rp 1,220.00 Rp 11,346.00
PP 0.045 M³ Rp 103,026.47 Rp 4,636.19
Semen Warna 1.940 kg Rp 6,500.00 Rp 12,610.00
Tenaga Kerja Rp 233,869.50
Pekerja 0.900 0rg/hr Rp 157,643.00 Rp 141,878.70
ANALISIS HARGA SATUAN PEKERJAAN BIDANG PEKERJAAN UMUMNOMOR : 28/PRT/M/2016
NO. URAIAN KOEF SATUAN HARGA STUAN SUB. JUMLAH JUMLAH
1 2 3 4 5 6 7
PEKERJAAN LANTAI
Tukang Batu 0.450 0rg/hr Rp 166,729.00 Rp 75,028.05
Kepala Tukang 0.045 0rg/hr Rp 182,676.00 Rp 8,220.42
Mandor 0.045 0rg/hr Rp 194,274.00 Rp 8,742.33
Jumlah Rp 1,196,661.69
Keuntungan 10% : Rp 119,666.17
Jumlah : Rp 1,316,327.86
Dibulatkan : Rp 1,316,300.00
54.e 1 m² Pasang Dinding Homogenous Ukuran (30 x 60 ) cm
Bahan Rp 98,281.47
Homogenous Ukuran (30 x 60 ) cm 1.080 M2 Rp 64,527.11 Rp 69,689.28
PC 9.300 kg Rp 1,220.00 Rp 11,346.00
PP 0.045 M³ Rp 103,026.47 Rp 4,636.19
Semen Warna 1.940 kg Rp 6,500.00 Rp 12,610.00
Tenaga Kerja Rp 233,869.50
Pekerja 0.900 0rg/hr Rp 157,643.00 Rp 141,878.70
Tukang Batu 0.450 0rg/hr Rp 166,729.00 Rp 75,028.05
Kepala Tukang 0.045 0rg/hr Rp 182,676.00 Rp 8,220.42
Mandor 0.045 0rg/hr Rp 194,274.00 Rp 8,742.33
Jumlah Rp 332,150.97
Keuntungan 10% : Rp 33,215.10
Jumlah : Rp 365,366.06
Dibulatkan : Rp 365,400.00

ANALISIS HARGA SATUAN PEKERJAAN BIDANG PEKERJAAN UMUMNOMOR : 28/PRT/M/2016


NO. URAIAN KOEF SATUAN HARGA STUAN SUB. JUMLAH JUMLAH
1 2 3 4 5 6 7
PEKERJAAN LANTAI
54.f 1 m² Pasang Dinding Homogenous Ukuran (30 x 30 ) cm
Bahan Rp 962,792.19
Homogenous Ukuran (30 x 30 ) cm 1.080 M2 Rp 865,000.00 Rp 934,200.00
PC 9.300 kg Rp 1,220.00 Rp 11,346.00
PP 0.045 M³ Rp 103,026.47 Rp 4,636.19
Semen Warna 1.940 kg Rp 6,500.00 Rp 12,610.00
Tenaga Kerja Rp 233,869.50
Pekerja 0.900 0rg/hr Rp 157,643.00 Rp 141,878.70
Tukang Batu 0.450 0rg/hr Rp 166,729.00 Rp 75,028.05
Kepala Tukang 0.045 0rg/hr Rp 182,676.00 Rp 8,220.42
Mandor 0.045 0rg/hr Rp 194,274.00 Rp 8,742.33
Jumlah Rp 1,196,661.69
Keuntungan 10% : Rp 119,666.17
Jumlah : Rp 1,316,327.86
Dibulatkan : Rp 1,316,300.00
1 1 m' Pasang dinding Marmer Ukuran (100x100) cm
Bahan Rp 1,613,475.55
Marmer setara Ujung Pandang 1.060 buah Rp 1,500,000.00 Rp 1,590,000.00
Paku 12 cm 3.003 buah Rp 498.87 Rp 1,498.09
PC 12.440 kg Rp 1,220.00 Rp 15,176.80
PP 0.025 M³ Rp 103,026.47 Rp 2,575.66
Semen Warna 0.650 kg Rp 6,500.00 Rp 4,225.00
Tenaga Kerja Rp 337,811.50
Pekerja 1.300 0rg/hr Rp 157,643.00 Rp 204,935.90
Tukang Batu 0.650 0rg/hr Rp 166,729.00 Rp 108,373.85
Kepala Tukang 0.065 0rg/hr Rp 182,676.00 Rp 11,873.94
Mandor 0.065 0rg/hr Rp 194,274.00 Rp 12,627.81
Jumlah Rp 1,951,287.05
Keuntungan 10% : Rp 195,128.71
Jumlah : Rp 2,146,415.76
Dibulatkan : Rp 2,146,400.00
55.a 1 m' Pasang dinding Marmer Ukuran (60x60) cm
Bahan Rp 1,613,475.55
Marmer setara Ujung Pandang 1.060 buah Rp 1,500,000.00 Rp 1,590,000.00
Paku 12 cm 3.003 buah Rp 498.87 Rp 1,498.09
PC 12.440 kg Rp 1,220.00 Rp 15,176.80
PP 0.025 M³ Rp 103,026.47 Rp 2,575.66
Semen Warna 0.650 kg Rp 6,500.00 Rp 4,225.00
Tenaga Kerja Rp 337,811.50
Pekerja 1.300 0rg/hr Rp 157,643.00 Rp 204,935.90
Tukang Batu 0.650 0rg/hr Rp 166,729.00 Rp 108,373.85
Kepala Tukang 0.065 0rg/hr Rp 182,676.00 Rp 11,873.94
Mandor 0.065 0rg/hr Rp 194,274.00 Rp 12,627.81
Jumlah Rp 1,951,287.05
Keuntungan 10% : Rp 195,128.71
Jumlah : Rp 2,146,415.76
Dibulatkan : Rp 2,146,400.00
55.b 1 m' Pasang dinding Marmer Ukuran (40x40) cm
Bahan Rp 1,613,475.55
Marmer setara Ujung Pandang 1.060 buah Rp 1,500,000.00 Rp 1,590,000.00
Paku 12 cm 3.003 buah Rp 498.87 Rp 1,498.09
PC 12.440 kg Rp 1,220.00 Rp 15,176.80
PP 0.025 M³ Rp 103,026.47 Rp 2,575.66
Semen Warna 0.650 kg Rp 6,500.00 Rp 4,225.00
Tenaga Kerja Rp 337,811.50
Pekerja 1.300 0rg/hr Rp 157,643.00 Rp 204,935.90
Tukang Batu 0.650 0rg/hr Rp 166,729.00 Rp 108,373.85
Kepala Tukang 0.065 0rg/hr Rp 182,676.00 Rp 11,873.94
Mandor 0.065 0rg/hr Rp 194,274.00 Rp 12,627.81
Jumlah Rp 1,951,287.05
Keuntungan 10% : Rp 195,128.71
Jumlah : Rp 2,146,415.76
Dibulatkan : Rp 2,146,400.00
#VALUE! 1 m' Pasang dinding Granit alam
Bahan Rp 202,615.55
Granit alam ex. Cina 1.060 buah Rp 169,000.00 Rp 179,140.00
Paku 12 cm 3.003 buah Rp 498.87 Rp 1,498.09
PC 12.440 kg Rp 1,220.00 Rp 15,176.80
PP 0.025 M³ Rp 103,026.47 Rp 2,575.66
Semen Warna 0.650 kg Rp 6,500.00 Rp 4,225.00
Tenaga Kerja Rp 337,811.50
Pekerja 1.300 0rg/hr Rp 157,643.00 Rp 204,935.90
Tukang Batu 0.650 0rg/hr Rp 166,729.00 Rp 108,373.85
Kepala Tukang 0.065 0rg/hr Rp 182,676.00 Rp 11,873.94
Mandor 0.065 0rg/hr Rp 194,274.00 Rp 12,627.81
Jumlah Rp 540,427.05
Keuntungan 10% : Rp 54,042.71
Jumlah : Rp 594,469.76
Dibulatkan : Rp 594,500.00

ANALISIS HARGA SATUAN PEKERJAAN BIDANG PEKERJAAN UMUMNOMOR : 28/PRT/M/2016


NO. URAIAN KOEF SATUAN HARGA STUAN SUB. JUMLAH JUMLAH
1 2 3 4 5 6 7
PEKERJAAN LANTAI
2 1 m2 Pasang dinding bata pelapis ukuran (3x7x24) cm
Bahan Rp 193,127.46
Bata pelapis ukuran (3x7x24) cm 63.000 buah Rp 2,500.00 Rp 157,500.00
PC 12.440 kg Rp 1,220.00 Rp 15,176.80
PP 0.025 M³ Rp 103,026.47 Rp 2,575.66
Semen Warna 2.750 kg Rp 6,500.00 Rp 17,875.00
Tenaga Kerja Rp 259,855.00
Pekerja 1.000 0rg/hr Rp 157,643.00 Rp 157,643.00
Tukang Batu 0.500 0rg/hr Rp 166,729.00 Rp 83,364.50
Kepala Tukang 0.050 0rg/hr Rp 182,676.00 Rp 9,133.80
Mandor 0.050 0rg/hr Rp 194,274.00 Rp 9,713.70
Jumlah Rp 452,982.46
Keuntungan 10% : Rp 45,298.25
Jumlah : Rp 498,280.71
Dibulatkan : Rp 498,300.00
A.4.4.3.54m 1 m² Pasang Dinding Keramik Ukuran (30 x 30 ) cm ---Unpolished setara Roman Gol. B
Bahan Rp 99,362.19
Keramik Ukuran (30 x 30) cm Roman 1.050 M2 Rp 67,400.00 Rp 70,770.00
PC 9.300 kg Rp 1,220.00 Rp 11,346.00
PP 0.045 M³ Rp 103,026.47 Rp 4,636.19
Semen Warna 1.940 kg Rp 6,500.00 Rp 12,610.00
Tenaga Kerja Rp 233,869.50
Pekerja 0.900 0rg/hr Rp 157,643.00 Rp 141,878.70
Tukang Batu 0.450 0rg/hr Rp 166,729.00 Rp 75,028.05
Kepala Tukang 0.045 0rg/hr Rp 182,676.00 Rp 8,220.42
Mandor 0.045 0rg/hr Rp 194,274.00 Rp 8,742.33
Jumlah Rp 333,231.69
Keuntungan 10% : Rp 33,323.17
Jumlah : Rp 366,554.86
Dibulatkan : Rp 366,600.00
54.d 1 m² Pasang Dinding Homogeneus tile Ukuran (30 x 30 ) cm
Bahan Rp 295,352.19
Homogeneus tile Ukuran (30 x 30) cm ex. 1.080 M2 Rp 247,000.00 Rp 266,760.00
PC 9.300 kg Rp 1,220.00 Rp 11,346.00
PP 0.045 M³ Rp 103,026.47 Rp 4,636.19
Semen Warna 1.940 kg Rp 6,500.00 Rp 12,610.00
Tenaga Kerja Rp 233,869.50
Pekerja 0.900 0rg/hr Rp 157,643.00 Rp 141,878.70
Tukang Batu 0.450 0rg/hr Rp 166,729.00 Rp 75,028.05
Kepala Tukang 0.045 0rg/hr Rp 182,676.00 Rp 8,220.42
Mandor 0.045 0rg/hr Rp 194,274.00 Rp 8,742.33
Jumlah Rp 529,221.69
Keuntungan 10% : Rp 52,922.17
Jumlah : Rp 582,143.86
Dibulatkan : Rp 582,100.00
54.e 1 m² Pasang Dinding Homogenous Ukuran (30 x 60 ) cm
Bahan Rp 97,771.49
Homogenous Ukuran (30 x 60 ) cm 1.080 M2 Rp 64,527.11 Rp 69,689.28
PC 9.300 kg Rp 1,220.00 Rp 11,346.00
PP 0.045 M³ Rp 91,693.56 Rp 4,126.21
Semen Warna 1.940 kg Rp 6,500.00 Rp 12,610.00
Tenaga Kerja Rp 212,451.14
Pekerja 0.900 0rg/hr Rp 137,242.34 Rp 123,518.11
Tukang Batu 0.450 0rg/hr Rp 166,063.23 Rp 74,728.45
Kepala Tukang 0.045 0rg/hr Rp 157,828.69 Rp 7,102.29
Mandor 0.045 0rg/hr Rp 157,828.69 Rp 7,102.29
Jumlah Rp 310,222.63
Keuntungan 10% : Rp 31,022.26
Jumlah : Rp 341,244.89
Dibulatkan : Rp 341,200.00
54.f 1 m² Pasang Dinding Homogenous Ukuran (30 x 30 ) cm
Bahan Rp 295,352.19
Homogenous Ukuran (30 x 30 ) cm 1.080 M2 Rp 247,000.00 Rp 266,760.00
PC 9.300 kg Rp 1,220.00 Rp 11,346.00
PP 0.045 M³ Rp 103,026.47 Rp 4,636.19
Semen Warna 1.940 kg Rp 6,500.00 Rp 12,610.00
Tenaga Kerja Rp 233,869.50
Pekerja 0.900 0rg/hr Rp 157,643.00 Rp 141,878.70
Tukang Batu 0.450 0rg/hr Rp 166,729.00 Rp 75,028.05
Kepala Tukang 0.045 0rg/hr Rp 182,676.00 Rp 8,220.42
Mandor 0.045 0rg/hr Rp 194,274.00 Rp 8,742.33
Jumlah Rp 529,221.69
Keuntungan 10% : Rp 52,922.17
Jumlah : Rp 582,143.86
Dibulatkan : Rp 582,100.00
#VALUE! 1 m' Pasang dinding Marmer Ukuran (100x100) cm
Bahan Rp 1,613,475.55
Marmer setara Ujung Pandang 1.060 buah Rp 1,500,000.00 Rp 1,590,000.00
Paku 12 cm 3.003 buah Rp 498.87 Rp 1,498.09
PC 12.440 kg Rp 1,220.00 Rp 15,176.80
PP 0.025 M³ Rp 103,026.47 Rp 2,575.66
Semen Warna 0.650 kg Rp 6,500.00 Rp 4,225.00
Tenaga Kerja Rp 337,811.50
Pekerja 1.300 0rg/hr Rp 157,643.00 Rp 204,935.90
Tukang Batu 0.650 0rg/hr Rp 166,729.00 Rp 108,373.85
Kepala Tukang 0.065 0rg/hr Rp 182,676.00 Rp 11,873.94
Mandor 0.065 0rg/hr Rp 194,274.00 Rp 12,627.81
Jumlah Rp 1,951,287.05
Keuntungan 10% : Rp 195,128.71
Jumlah : Rp 2,146,415.76
Dibulatkan : Rp 2,146,400.00
55.a 1 m' Pasang dinding Marmer Ukuran (60x60) cm
Bahan Rp 214,275.55
Marmer setara Ujung Pandang 1.060 buah Rp 180,000.00 Rp 190,800.00
Paku 12 cm 3.003 buah Rp 498.87 Rp 1,498.09
PC 12.440 kg Rp 1,220.00 Rp 15,176.80
PP 0.025 M³ Rp 103,026.47 Rp 2,575.66
Semen Warna 0.650 kg Rp 6,500.00 Rp 4,225.00
ANALISIS HARGA SATUAN PEKERJAAN BIDANG PEKERJAAN UMUMNOMOR : 28/PRT/M/2016
NO. URAIAN KOEF SATUAN HARGA STUAN SUB. JUMLAH JUMLAH
1 2 3 4 5 6 7
PEKERJAAN LANTAI
Tenaga Kerja Rp 337,811.50
Pekerja 1.300 0rg/hr Rp 157,643.00 Rp 204,935.90
Tukang Batu 0.650 0rg/hr Rp 166,729.00 Rp 108,373.85
Kepala Tukang 0.065 0rg/hr Rp 182,676.00 Rp 11,873.94
Mandor 0.065 0rg/hr Rp 194,274.00 Rp 12,627.81
Jumlah Rp 552,087.05
Keuntungan 10% : Rp 55,208.71
Jumlah : Rp 607,295.76
Dibulatkan : Rp 607,300.00
55.b 1 m' Pasang dinding Marmer Ukuran (40x40) cm
Bahan Rp 182,475.55
Marmer setara Ujung Pandang 1.060 buah Rp 150,000.00 Rp 159,000.00
Paku 12 cm 3.003 buah Rp 498.87 Rp 1,498.09
PC 12.440 kg Rp 1,220.00 Rp 15,176.80
PP 0.025 M³ Rp 103,026.47 Rp 2,575.66
Semen Warna 0.650 kg Rp 6,500.00 Rp 4,225.00
Tenaga Kerja Rp 337,811.50
Pekerja 1.300 0rg/hr Rp 157,643.00 Rp 204,935.90
Tukang Batu 0.650 0rg/hr Rp 166,729.00 Rp 108,373.85
Kepala Tukang 0.065 0rg/hr Rp 182,676.00 Rp 11,873.94
Mandor 0.065 0rg/hr Rp 194,274.00 Rp 12,627.81
Jumlah Rp 520,287.05
Keuntungan 10% : Rp 52,028.71
Jumlah : Rp 572,315.76
Dibulatkan : Rp 572,300.00
#VALUE! 1 m' Pasang dinding Granit alam
Bahan Rp 202,615.55
Granit alam ex. Cina 1.060 buah Rp 169,000.00 Rp 179,140.00
Paku 12 cm 3.003 buah Rp 498.87 Rp 1,498.09
PC 12.440 kg Rp 1,220.00 Rp 15,176.80
PP 0.025 M³ Rp 103,026.47 Rp 2,575.66
Semen Warna 0.650 kg Rp 6,500.00 Rp 4,225.00
Tenaga Kerja Rp 337,811.50
Pekerja 1.300 0rg/hr Rp 157,643.00 Rp 204,935.90
Tukang Batu 0.650 0rg/hr Rp 166,729.00 Rp 108,373.85
Kepala Tukang 0.065 0rg/hr Rp 182,676.00 Rp 11,873.94
Mandor 0.065 0rg/hr Rp 194,274.00 Rp 12,627.81
Jumlah Rp 540,427.05
Keuntungan 10% : Rp 54,042.71
Jumlah : Rp 594,469.76
Dibulatkan : Rp 594,500.00
#VALUE! 1 m2 Pasang dinding bata pelapis ukuran (3x7x24) cm
Bahan Rp 193,127.46
Bata pelapis ukuran (3x7x24) cm 63.000 buah Rp 2,500.00 Rp 157,500.00
PC 12.440 kg Rp 1,220.00 Rp 15,176.80
PP 0.025 M³ Rp 103,026.47 Rp 2,575.66
Semen Warna 2.750 kg Rp 6,500.00 Rp 17,875.00
Tenaga Kerja Rp 259,855.00
Pekerja 1.000 0rg/hr Rp 157,643.00 Rp 157,643.00
Tukang Batu 0.500 0rg/hr Rp 166,729.00 Rp 83,364.50
Kepala Tukang 0.050 0rg/hr Rp 182,676.00 Rp 9,133.80
Mandor 0.050 0rg/hr Rp 194,274.00 Rp 9,713.70
Jumlah Rp 452,982.46
Keuntungan 10% : Rp 45,298.25
Jumlah : Rp 498,280.71
Dibulatkan : Rp 498,300.00
A.4.4.3.57 1 m2 Pasang dinding batu paras
Bahan Rp 176,780.64
Batu paras Bali 1.100 M2 Rp 144,399.74 Rp 158,839.71
PC 11.750 kg Rp 1,220.00 Rp 14,335.00
PP 0.035 M³ Rp 103,026.47 Rp 3,605.93
Tenaga Kerja Rp 181,898.50
Pekerja 0.700 0rg/hr Rp 157,643.00 Rp 110,350.10
Tukang Batu 0.350 0rg/hr Rp 166,729.00 Rp 58,355.15
Kepala Tukang 0.035 0rg/hr Rp 182,676.00 Rp 6,393.66
Mandor 0.035 0rg/hr Rp 194,274.00 Rp 6,799.59
Jumlah Rp 358,679.14
Keuntungan 10% : Rp 35,867.91
Jumlah : Rp 394,547.05
Dibulatkan : Rp 394,500.00
A.4.4.3.58 1 m2 Pasang dinding batu tempel hitam
Bahan Rp 156,521.57
Batu tempel andesit 1.100 M2 Rp 126,342.99 Rp 138,977.29
PC 11.750 kg Rp 1,220.00 Rp 14,335.00
PP 0.035 M³ Rp 91,693.56 Rp 3,209.27
Tenaga Kerja Rp 165,239.78
Pekerja 0.700 0rg/hr Rp 137,242.34 Rp 96,069.64
Tukang Batu 0.350 0rg/hr Rp 166,063.23 Rp 58,122.13
Kepala Tukang 0.035 0rg/hr Rp 157,828.69 Rp 5,524.00
Mandor 0.035 0rg/hr Rp 157,828.69 Rp 5,524.00
Jumlah Rp 321,761.34
Keuntungan 10% : Rp 32,176.13
Jumlah : Rp 353,937.48
Dibulatkan : Rp 353,900.00
A.4.4.3.58a 1 m2 Pasang dinding batu Candi
Bahan Rp 193,302.83
Batu Candi 1.100 M2 Rp 159,419.91 Rp 175,361.90
PC 11.750 kg Rp 1,220.00 Rp 14,335.00
PP 0.035 M³ Rp 103,026.47 Rp 3,605.93
Tenaga Kerja Rp 181,898.50
Pekerja 0.700 0rg/hr Rp 157,643.00 Rp 110,350.10
Tukang Batu 0.350 0rg/hr Rp 166,729.00 Rp 58,355.15
Kepala Tukang 0.035 0rg/hr Rp 182,676.00 Rp 6,393.66
Mandor 0.035 0rg/hr Rp 194,274.00 Rp 6,799.59
Jumlah Rp 375,201.33
Keuntungan 10% : Rp 37,520.13
Jumlah : Rp 412,721.46
Dibulatkan : Rp 412,700.00
ANALISIS HARGA SATUAN PEKERJAAN BIDANG PEKERJAAN UMUMNOMOR : 28/PRT/M/2016
NO. URAIAN KOEF SATUAN HARGA STUAN SUB. JUMLAH JUMLAH
1 2 3 4 5 6 7
PEKERJAAN LANTAI
#VALUE! 1 m2 Pasang lantai vinyl ukuran ( 30 x 30 ) cm
Bahan Rp 136,763.00
Vinyl ukuran ( 30 x 30 ) cm 1.068 M2 Rp 110,000.00 Rp 117,513.00
Lem vinyl 0.350 kg Rp 55,000.00 Rp 19,250.00
Tenaga Kerja Rp 49,125.90
Pekerja 0.150 0rg/hr Rp 137,242.34 Rp 20,586.35
Tukang Batu 0.150 0rg/hr Rp 166,063.23 Rp 24,909.48
Kepala Tukang 0.015 0rg/hr Rp 157,828.69 Rp 2,367.43
Mandor 0.008 0rg/hr Rp 157,828.69 Rp 1,262.63
Jumlah Rp 185,888.90
Keuntungan 10% : Rp 18,588.89
Jumlah : Rp 204,477.79
Dibulatkan : Rp 204,500.00
A.4.4.3.60 1 m2 Pasang wall paper, lebar 50cm
Bahan Rp 68,750.00
Wall paper 2.200 M' Rp 25,000.00 Rp 55,000.00
Lem 0.250 kg Rp 55,000.00 Rp 13,750.00
Tenaga Kerja Rp - Rp 87,846.67
Pekerja 0.350 0rg/hr Rp 157,643.00 Rp 55,175.05
Tukang Batu 0.175 0rg/hr Rp 166,729.00 Rp 29,177.58
Kepala Tukang 0.017 0rg/hr Rp 182,676.00 Rp 3,105.49
Mandor 0.002 0rg/hr Rp 194,274.00 Rp 388.55
Jumlah Rp 156,596.67
Keuntungan 10% : Rp 15,659.67
Jumlah : Rp 172,256.33
Dibulatkan : Rp 172,300.00
A.4.4.3.61 1 m2 Pasang Floor hardener natural ex. Sika
Bahan Rp 28,586.25
Floor Hardener 5.000 kg Rp 4,235.00 Rp 21,175.00
Material penunjang dan alat bantu 1.000 ls Rp 7,411.25 Rp 7,411.25
Tenaga Kerja Rp 42,282.40
Pekerja 0.120 0rg/hr Rp 157,643.00 Rp 18,917.16
Tukang Batu 0.120 0rg/hr Rp 166,729.00 Rp 20,007.48
Kepala Tukang 0.012 0rg/hr Rp 182,676.00 Rp 2,192.11
Mandor 0.006 0rg/hr Rp 194,274.00 Rp 1,165.64
Jumlah Rp 70,868.65
Keuntungan 10% : Rp 7,086.86
Jumlah : Rp 77,955.51
Dibulatkan : Rp 78,000.00
A.4.4.3.61a 1 m2 Pasang Floor hardener warna ex. Sika
Bahan Rp 34,303.50
Floor Hardener 5.000 kg Rp 5,082.00 Rp 25,410.00
Material penunjang dan alat bantu 1.000 ls Rp 8,893.50 Rp 8,893.50
Tenaga Kerja Rp 87,846.67
Pekerja 0.350 0rg/hr Rp 157,643.00 Rp 55,175.05
Tukang Batu 0.175 0rg/hr Rp 166,729.00 Rp 29,177.58
Kepala Tukang 0.017 0rg/hr Rp 182,676.00 Rp 3,105.49
Mandor 0.002 0rg/hr Rp 194,274.00 Rp 388.55
Jumlah Rp 122,150.17
Keuntungan 10% : Rp 12,215.02
Jumlah : Rp 134,365.18
Dibulatkan : Rp 134,400.00
#VALUE! 1 m' Pasang plin vinyl karet ukuran ( 15 x 30 ) cm dengan perekat
Bahan Rp 198,000.00
Vinyl karet ukuran ( 15 x 30 ) cm 1.760 bh Rp 110,000.00 Rp 193,600.00
Lem vinyl 0.080 kg Rp 55,000.00 Rp 4,400.00
Tenaga Kerja Rp 28,188.26
Pekerja 0.080 0rg/hr Rp 157,643.00 Rp 12,611.44
Tukang Batu 0.080 0rg/hr Rp 166,729.00 Rp 13,338.32
Kepala Tukang 0.008 0rg/hr Rp 182,676.00 Rp 1,461.41
Mandor 0.004 0rg/hr Rp 194,274.00 Rp 777.10
Jumlah Rp 226,188.26
Keuntungan 10% : Rp 22,618.83
Jumlah : Rp 248,807.09
Dibulatkan : Rp 248,800.00
#VALUE! 1 m' Pasang plin plin kayu Kamper Samarinda ukuran ( t=2cm x l=10 )
Bahan Rp 10,656.73
Papan kayu Kamper Samarinda 0.003 M3 Rp 3,348,902.65 Rp 10,046.71
Sekrup+piser 0.050 kg Rp 12,200.50 Rp 610.03
Tenaga Kerja Rp 42,282.40
Pekerja 0.120 0rg/hr Rp 157,643.00 Rp 18,917.16
Tukang Batu 0.120 0rg/hr Rp 166,729.00 Rp 20,007.48
Kepala Tukang 0.012 0rg/hr Rp 182,676.00 Rp 2,192.11
Mandor 0.006 0rg/hr Rp 194,274.00 Rp 1,165.64
Jumlah Rp 52,939.13
Keuntungan 10% : Rp 5,293.91
Jumlah : Rp 58,233.04
Dibulatkan : Rp 58,200.00
J.40 1 m² Pasang Lantai keramik Ukuran (40 x 40) cm---Polished setra DN
Bahan Rp 114,443.01
Keramik uk. 40x40cm polished/Glazed 1.040 M2 Rp 86,400.00 Rp 89,856.00
PC 8.140 kg Rp 1,220.00 Rp 9,930.80
PP 0.045 M³ Rp 91,693.56 Rp 4,126.21
Semen Warna 1.620 kg Rp 6,500.00 Rp 10,530.00
Tenaga Kerja Rp 165,239.78
Pekerja 0.700 0rg/hr Rp 137,242.34 Rp 96,069.64
Tukang Batu 0.350 0rg/hr Rp 166,063.23 Rp 58,122.13
Kepala Tukang 0.035 0rg/hr Rp 157,828.69 Rp 5,524.00
Mandor 0.035 0rg/hr Rp 157,828.69 Rp 5,524.00
Jumlah Rp 279,682.79
Keuntungan 10% : Rp 27,968.28
Jumlah : Rp 307,651.07
Dibulatkan : Rp 307,700.00
J.41 1 m² Pasang Lantai keramaik Ukuran (40 x 40) cm---Unpolished setara DN
Bahan Rp 115,784.99
Keramik uk. 40x40cm Unpolished/Anti slip 1.040 M2 Rp 87,200.00 Rp 90,688.00
PC 8.140 kg Rp 1,220.00 Rp 9,930.80
PP 0.045 M³ Rp 103,026.47 Rp 4,636.19
ANALISIS HARGA SATUAN PEKERJAAN BIDANG PEKERJAAN UMUMNOMOR : 28/PRT/M/2016
NO. URAIAN KOEF SATUAN HARGA STUAN SUB. JUMLAH JUMLAH
1 2 3 4 5 6 7
PEKERJAAN LANTAI
Semen Warna 1.620 kg Rp 6,500.00 Rp 10,530.00
Tenaga Kerja Rp 181,898.50
Pekerja 0.700 0rg/hr Rp 157,643.00 Rp 110,350.10
Tukang Batu 0.350 0rg/hr Rp 166,729.00 Rp 58,355.15
Kepala Tukang 0.035 0rg/hr Rp 182,676.00 Rp 6,393.66
Mandor 0.035 0rg/hr Rp 194,274.00 Rp 6,799.59
Jumlah Rp 297,683.49
Keuntungan 10% : Rp 29,768.35
Jumlah : Rp 327,451.84
Dibulatkan : Rp 327,500.00
J.42 1 m² Pasang Lantai keramaik Ukuran (40 x 40) cm---Polished setara Roman Gol. B
Bahan Rp 99,141.58
Keramik uk. 40x40cm polished/Glazed 1.040 M2 Rp 71,196.72 Rp 74,044.58
PC 8.140 kg Rp 1,220.00 Rp 9,930.80
PP 0.045 M³ Rp 103,026.47 Rp 4,636.19
Semen Warna 1.620 kg Rp 6,500.00 Rp 10,530.00
Tenaga Kerja Rp 181,898.50
Pekerja 0.700 0rg/hr Rp 157,643.00 Rp 110,350.10
Tukang Batu 0.350 0rg/hr Rp 166,729.00 Rp 58,355.15
Kepala Tukang 0.035 0rg/hr Rp 182,676.00 Rp 6,393.66
Mandor 0.035 0rg/hr Rp 194,274.00 Rp 6,799.59
Jumlah Rp 281,040.08
Keuntungan 10% : Rp 28,104.01
Jumlah : Rp 309,144.08
Dibulatkan : Rp 309,100.00
J.43 1 m² Pasang Lantai keramaik Ukuran (40 x 40) cm---Unpolished setara Roman Gol . A
Bahan Rp 104,668.13
Keramik uk. 40x40cm Unpolished/Anti slip 1.040 M2 Rp 76,510.71 Rp 79,571.14
PC 8.140 kg Rp 1,220.00 Rp 9,930.80
PP 0.045 M³ Rp 103,026.47 Rp 4,636.19
Semen Warna 1.620 kg Rp 6,500.00 Rp 10,530.00
Tenaga Kerja Rp 181,898.50
Pekerja 0.700 0rg/hr Rp 157,643.00 Rp 110,350.10
Tukang Batu 0.350 0rg/hr Rp 166,729.00 Rp 58,355.15
Kepala Tukang 0.035 0rg/hr Rp 182,676.00 Rp 6,393.66
Mandor 0.035 0rg/hr Rp 194,274.00 Rp 6,799.59
Jumlah Rp 286,566.63
Keuntungan 10% : Rp 28,656.66
Jumlah : Rp 315,223.30
Dibulatkan : Rp 315,200.00
J.44 1 m² Pasang Lantai Homogenous Ukuran (40 x 40) cm---Polished setara Niro Granit
Bahan Rp 376,824.99
Homogenous Ukuran (40 x 40) cm 1.040 M2 Rp 338,200.00 Rp 351,728.00
PC 8.140 kg Rp 1,220.00 Rp 9,930.80
PP 0.045 M³ Rp 103,026.47 Rp 4,636.19
Semen Warna 1.620 kg Rp 6,500.00 Rp 10,530.00
Tenaga Kerja Rp 181,898.50
Pekerja 0.700 0rg/hr Rp 157,643.00 Rp 110,350.10
Tukang Batu 0.350 0rg/hr Rp 166,729.00 Rp 58,355.15
Kepala Tukang 0.035 0rg/hr Rp 182,676.00 Rp 6,393.66
Mandor 0.035 0rg/hr Rp 194,274.00 Rp 6,799.59
Jumlah Rp 558,723.49
Keuntungan 10% : Rp 55,872.35
Jumlah : Rp 614,595.84
Dibulatkan : Rp 614,600.00

ANALISIS HARGA SATUAN PEKERJAAN BIDANG PEKERJAAN UMUMNOMOR : 28/PRT/M/2016


NO. URAIAN KOEF SATUAN HARGA STUAN SUB. JUMLAH JUMLAH
1 2 3 4 5 6 7
PEKERJAAN LANTAI
J.45 1 m² Pasang Lantai Homogeneus Ukuran (60 x 60) cm Homogeneus Tile ex Roman
Bahan Rp 123,015.91
Keramik uk. 60x60cm 1.000 M2 Rp 108,448.92 Rp 108,448.92
PC 8.140 kg Rp 1,220.00 Rp 9,930.80
PP 0.045 M³ Rp 103,026.47 Rp 4,636.19
Tenaga Kerja Rp 124,711.35
Pekerja 0.443 0rg/hr Rp 157,643.00 Rp 69,835.85
Tukang Batu 0.250 0rg/hr Rp 166,729.00 Rp 41,682.25
Kepala Tukang 0.035 0rg/hr Rp 182,676.00 Rp 6,393.66
Mandor 0.035 0rg/hr Rp 194,274.00 Rp 6,799.59
Jumlah Rp 247,727.26
Keuntungan 10% : Rp 24,772.73
Jumlah : Rp 272,499.99
Dibulatkan : Rp 272,000.00
J.46 1 m² Pasang Lantai keramaik Ukuran (60 x 60) cm---Polished setara Roman
Bahan Rp 158,976.32
Keramik uk. 60x60cm polished/Glazed 1.080 M2 Rp 123,035.30 Rp 132,878.12
PC 9.600 kg Rp 1,220.00 Rp 11,712.00
PP 0.045 M³ Rp 103,026.47 Rp 4,636.19
Semen Warna 1.500 kg Rp 6,500.00 Rp 9,750.00
Tenaga Kerja Rp 62,365.20
Pekerja 0.240 0rg/hr Rp 157,643.00 Rp 37,834.32
Tukang Batu 0.120 0rg/hr Rp 166,729.00 Rp 20,007.48
Kepala Tukang 0.012 0rg/hr Rp 182,676.00 Rp 2,192.11
Mandor 0.012 0rg/hr Rp 194,274.00 Rp 2,331.29
Jumlah Rp 221,341.52
Keuntungan 10% : Rp 22,134.15
Jumlah : Rp 243,475.67
Dibulatkan : Rp 243,500.00
J.47 1 m² Pasang Lantai keramaik Ukuran (60 x 60) cm---Unpolished setara Roman
Bahan Rp 143,393.07
Keramik uk. 60x60cm Unpolished/Anti slip 1.080 M2 Rp 109,533.41 Rp 118,296.08
PC 8.140 kg Rp 1,220.00 Rp 9,930.80
PP 0.045 M³ Rp 103,026.47 Rp 4,636.19
Semen Warna 1.620 kg Rp 6,500.00 Rp 10,530.00
Tenaga Kerja Rp 181,898.50
Pekerja 0.700 0rg/hr Rp 157,643.00 Rp 110,350.10
Tukang Batu 0.350 0rg/hr Rp 166,729.00 Rp 58,355.15
Kepala Tukang 0.035 0rg/hr Rp 182,676.00 Rp 6,393.66
Mandor 0.035 0rg/hr Rp 194,274.00 Rp 6,799.59
Jumlah Rp 325,291.57
Keuntungan 10% : Rp 32,529.16
Jumlah : Rp 357,820.73
Dibulatkan : Rp 357,800.00
J.48 1 m² Pasang Lantai Homogenous Ukuran (60 x 60) cm---Polished setara Niro Granit
Bahan Rp 551,704.99
Homogenous Ukuran (60 x 60) cm 1.080 M2 Rp 487,600.00 Rp 526,608.00
PC 8.140 kg Rp 1,220.00 Rp 9,930.80
PP 0.045 M³ Rp 103,026.47 Rp 4,636.19
Semen Warna 1.620 kg Rp 6,500.00 Rp 10,530.00
Tenaga Kerja Rp 181,898.50
Pekerja 0.700 0rg/hr Rp 157,643.00 Rp 110,350.10
Tukang Batu 0.350 0rg/hr Rp 166,729.00 Rp 58,355.15
Kepala Tukang 0.035 0rg/hr Rp 182,676.00 Rp 6,393.66
Mandor 0.035 0rg/hr Rp 194,274.00 Rp 6,799.59
Jumlah Rp 733,603.49
Keuntungan 10% : Rp 73,360.35
Jumlah : Rp 806,963.84
Dibulatkan : Rp 807,000.00
J.49 1 m² Pasang Lantai Homogenous Ukuran (60 x 60) cm---Unpolished setara Niro Granit
Bahan Rp 447,592.99
Homogenous Ukuran (60 x 60) cm 1.080 M2 Rp 391,200.00 Rp 422,496.00
PC 8.140 kg Rp 1,220.00 Rp 9,930.80
PP 0.045 M³ Rp 103,026.47 Rp 4,636.19
Semen Warna 1.620 kg Rp 6,500.00 Rp 10,530.00
Tenaga Kerja Rp 181,898.50
Pekerja 0.700 0rg/hr Rp 157,643.00 Rp 110,350.10
Tukang Batu 0.350 0rg/hr Rp 166,729.00 Rp 58,355.15
Kepala Tukang 0.035 0rg/hr Rp 182,676.00 Rp 6,393.66
Mandor 0.035 0rg/hr Rp 194,274.00 Rp 6,799.59
Jumlah Rp 629,491.49
Keuntungan 10% : Rp 62,949.15
Jumlah : Rp 692,440.64
Dibulatkan : Rp 692,400.00
J.54 1 m² Pasang Lantai Homogenous Ukuran (60 x 60) cm ex valentino
Bahan Rp 187,096.99
Homogenous Ukuran (60 x 60) cm 1.080 M2 Rp 150,000.00 Rp 162,000.00
PC 8.140 kg Rp 1,220.00 Rp 9,930.80
PP 0.045 M³ Rp 103,026.47 Rp 4,636.19
Semen Warna 1.620 kg Rp 6,500.00 Rp 10,530.00
Tenaga Kerja Rp 181,898.50
Pekerja 0.700 0rg/hr Rp 157,643.00 Rp 110,350.10
Tukang Batu 0.350 0rg/hr Rp 166,729.00 Rp 58,355.15
Kepala Tukang 0.035 0rg/hr Rp 182,676.00 Rp 6,393.66
Mandor 0.035 0rg/hr Rp 194,274.00 Rp 6,799.59
Jumlah Rp 368,995.49
Keuntungan 10% : Rp 36,899.55
Jumlah : Rp 405,895.04
Dibulatkan : Rp 405,900.00
J.51 1 m² Pasang Lantai Homogenous Ukuran (60 x 60) cm---Polished setara Garuda granit
Bahan Rp 137,308.99
Homogenous Ukuran (60 x 60) cm 1.080 M2 Rp 103,900.00 Rp 112,212.00
PC 8.140 kg Rp 1,220.00 Rp 9,930.80
PP 0.045 M³ Rp 103,026.47 Rp 4,636.19
Semen Warna 1.620 kg Rp 6,500.00 Rp 10,530.00
Tenaga Kerja Rp 181,898.50
Pekerja 0.700 0rg/hr Rp 157,643.00 Rp 110,350.10
ANALISIS HARGA SATUAN PEKERJAAN BIDANG PEKERJAAN UMUMNOMOR : 28/PRT/M/2016
NO. URAIAN KOEF SATUAN HARGA STUAN SUB. JUMLAH JUMLAH
1 2 3 4 5 6 7
PEKERJAAN LANTAI
Tukang Batu 0.350 0rg/hr Rp 166,729.00 Rp 58,355.15
Kepala Tukang 0.035 0rg/hr Rp 182,676.00 Rp 6,393.66
Mandor 0.035 0rg/hr Rp 194,274.00 Rp 6,799.59
Jumlah Rp 319,207.49
Keuntungan 10% : Rp 31,920.75
Jumlah : Rp 351,128.24
Dibulatkan : Rp 351,100.00
J.52 1m Pemasangan Paving 6 Cm
Bahan Rp 184,801.07
Pasir Urug 5 Cm 0.0600 m³ Rp 108,448.92 Rp 6,506.94
Paving Block 50.0000 bh Rp 3,500.00 Rp 175,000.00
Pasir beton utk. Pengisian 0.0270 m³ Rp 122,005.04 Rp 3,294.14
Tenaga Kerja Rp 71,176.26
Tukang Batu 0.2400 org/hr Rp 166,729.00 Rp 40,014.96
Kepala Tukang Batu 0.0240 org/hr Rp 182,676.00 Rp 4,384.22
Pekerja 0.1600 org/hr Rp 157,643.00 Rp 25,222.88
Mandor 0.0080 org/hr Rp 194,274.00 Rp 1,554.19
Jumlah Rp 255,977.33
Keuntungan 10% : Rp 25,597.73
Jumlah : Rp 281,575.06
Dibulatkan : Rp 281,600.00
J.53 1 m² Pemasangan Paving 8 Cm
Bahan Rp 235,624.61
Pasir Urug 5 Cm 0.0600 m³ Rp 108,448.92 Rp 6,506.94
Paving Block t = 8 cm 50.0000 bh Rp 4,500.00 Rp 225,000.00
Pasir beton utk. Pengisian 0.0338 m³ Rp 122,005.04 Rp 4,117.67
Tenaga Kerja Rp 71,176.26
Tukang Batu 0.2400 org/hr Rp 166,729.00 Rp 40,014.96
Kepala Tukang Batu 0.0240 org/hr Rp 182,676.00 Rp 4,384.22
Pekerja 0.1600 org/hr Rp 157,643.00 Rp 25,222.88
Mandor 0.0080 org/hr Rp 194,274.00 Rp 1,554.19
Jumlah Rp 306,800.86
Keuntungan 10% : Rp 30,680.09
Jumlah : Rp 337,480.95
Dibulatkan : Rp 337,500.00
J.54 1 M² Screeding tebal 3 cm
Bahan Rp 22,326.20
Semen 0.288 zak Rp 61,000.00 Rp 17,568.00
Pasir beton 0.039 m³ Rp 122,005.04 Rp 4,758.20
Tenaga Kerja Rp 51,971.00
Tukang Batu 0.100 org/hr Rp 166,729.00 Rp 16,672.90
Kepala Tukang 0.010 org/hr Rp 182,676.00 Rp 1,826.76
Pekerja 0.200 org/hr Rp 157,643.00 Rp 31,528.60
Mandor 0.010 org/hr Rp 194,274.00 Rp 1,942.74
Jumlah Rp 74,297.20
Keuntungan 10% : Rp 7,429.72
Jumlah : Rp 81,726.92
Dibulatkan : Rp 81,700.00
J.55 1 M² Water profing ex. Sika Top 107 Seal (untuk Toilet dan Area basah)
Bahan Rp 60,925.00
Pre treatment/cleaning 1.050 m² Rp 2,500.00 Rp 2,625.00
Curbing sudut 0.400 m' Rp 2,000.00 Rp 800.00
Water profing ex. Sika Top 107 Seal ( 3 kali 3.000 kg Rp 18,000.00 Rp 54,000.00
Kuas 0.200 bh Rp 17,500.00 Rp 3,500.00
Tenaga Kerja Rp 54,706.36
Tukang Batu 0.200 org/hr Rp 166,729.00 Rp 33,345.80
Kepala Tukang 0.020 org/hr Rp 182,676.00 Rp 3,653.52
Pekerja 0.100 org/hr Rp 157,643.00 Rp 15,764.30
Mandor 0.010 org/hr Rp 194,274.00 Rp 1,942.74
Jumlah Rp 115,631.36
Keuntungan 10% : Rp 11,563.14
Jumlah : Rp 127,194.50
Dibulatkan : Rp 127,200.00

ANALISIS HARGA SATUAN PEKERJAAN BIDANG PEKERJAAN UMUMNOMOR : 28/PRT/M/2016


NO. URAIAN KOEF SATUAN HARGA STUAN SUB. JUMLAH JUMLAH
1 2 3 4 5 6 7
PEKERJAAN LANTAI
J.56 1 M² Water profing ex. Sika Rain Tile untuk atap dak beton
Bahan Rp 100,150.00
Pre treatment/cleaning 1.050 m² Rp 3,000.00 Rp 3,150.00
Curbing sudut 0.400 m' Rp 2,500.00 Rp 1,000.00
Waterproofing Coating ex. Sika Rain Tile ( 3 2.400 kg Rp 40,000.00 Rp 96,000.00
Tenaga Kerja Rp 134,337.48
Tukang Batu 0.500 org/hr Rp 166,729.00 Rp 83,364.50
Kepala Tukang 0.050 org/hr Rp 182,676.00 Rp 9,133.80
Pekerja 0.250 org/hr Rp 157,643.00 Rp 39,410.75
Mandor 0.013 org/hr Rp 194,274.00 Rp 2,428.43
Jumlah Rp 234,487.48
Keuntungan 10% : Rp 23,448.75
Jumlah : Rp 257,936.22
Dibulatkan : Rp 257,900.00
J.57 1 M² Pekerjaan meja beton wastafel finish. Keramik 20 x 20 cm ex. Roman
Terpasang :
- Beton 1:2:3 0.100 m3 Rp 981,774.02 Rp 98,177.40
- Besi 10.000 kg Rp 7,795.61 Rp 77,956.06
- Bekisting 12.500 m² Rp 401,338.99 Rp 5,016,737.41
- Pasang keramik 20 x 20 cm meja 1.100 m² Rp 330,554.98 Rp 363,610.47
- Pas Bata merah 0.960 m² Rp 134,152.46 Rp 128,786.36
- Plesteran 1.920 m² Rp 69,366.77 Rp 133,184.20
Jumlah Rp 5,818,451.91
Keuntungan 10% : Rp 581,845.19
Jumlah : Rp 6,400,297.10
Dibulatkan : Rp 6,400,300.00
J.57 1 M² Pekerjaan meja beton pantry finish. Keramik 20 x 20 cm berikut dinding
Terpasang :
- Beton 1:2:3 0.100 m3 Rp 981,774.02 Rp 98,177.40
- Besi 10.000 kg Rp 7,795.61 Rp 77,956.06
- Bekisting 12.500 m² Rp 401,338.99 Rp 5,016,737.41
- Pasang keramik 20 x 20 cm meja + dind 2.428 m² Rp 330,554.98 Rp 802,587.48
- Pas Bata merah 0.960 m² Rp 134,152.46 Rp 128,786.36
- Plesteran 1.920 m² Rp 69,366.77 Rp 133,184.20
Jumlah Rp 6,257,428.92
Keuntungan 10% : Rp 625,742.89
Jumlah : Rp 6,883,171.81
Dibulatkan : Rp 6,883,200.00
J.58 1 m2 Lantai beton sikat ( Pearl stone )
a. Bahan: Rp 224,149.65
- Batu sikat 15.0000 kg Rp 13,556.12 Rp 203,341.73
- Sement / PC kwalitas 3 Roda 0.2820 zk Rp 61,000.00 Rp 17,202.00
- Pasir pasang 0.0350 m3 Rp 103,026.47 Rp 3,605.93
b. Upah: Rp 198,545.45
- Pekerja 0.0350 hari Rp 157,643.00 Rp 5,517.51
- Tukang 0.3500 hari Rp 166,729.00 Rp 58,355.15
- Kepala tukang 0.7000 hari Rp 182,676.00 Rp 127,873.20
- Mandor 0.0350 hari Rp 194,274.00 Rp 6,799.59
Jumlah Rp 422,695.10
Keuntungan 10% : Rp 42,269.51
Jumlah : Rp 464,964.61
Dibulatkan : Rp 465,000.00
A.4.7.1.6 1 m2 Epoxy floor lining 2000 um ( 2mm )
a. Terpasang :
Material : Dongyang Epoxy Primer EP 1.0500 M2 Rp 150,000.00 Rp 157,500.00
118, Dongyang Scraping Material,
Dongyang Epoxy finish ET 5635 -
Selfleveling type.
Jumlah Rp 157,500.00
Keuntungan 10% : Rp 15,750.00
Jumlah : Rp 173,250.00
Dibulatkan : Rp 173,300.00
#VALUE! 1 m2 Epoxy floor lining 3000 um ( 3mm )
a. Terpasang :
Material : Dongyang Epoxy Primer EP 1.0500 M2 Rp 220,000.00 Rp 231,000.00
118, Dongyang Scraping Material,
Dongyang Epoxy finish ET 5635 -
Selfleveling type.
Jumlah Rp 231,000.00
Keuntungan 10% : Rp 23,100.00
Jumlah : Rp 254,100.00
Dibulatkan : Rp 254,100.00
#VALUE! 1 M² Pekerjaan meja beton wastafel finish. Batu granit alam
Terpasang :
- Beton 1:2:3 0.100 m3 Rp 981,774.02
- Besi 10.000 kg Rp 7,795.61
- Bekisting 12.500 m² Rp 401,338.99
- Pasang batu granit alam 1.100 m² Rp 379,891.49
- Pas Bata merah 0.960 m² Rp 134,152.46
- Plesteran 1.920 m² Rp 69,366.77 Rp 133,184.20
Jumlah Rp 133,184.20
Keuntungan 10% : Rp 13,318.42
Jumlah : Rp 146,502.61
Dibulatkan : Rp 146,500.00

1 m2 PEMASANGAN 1 M2 LANTAI GUIDING BLOCK UKURAN 30CM X 30 CM


a. Bahan: Rp 323,449.25
- Ubin granit 1.1870 buah Rp 247,000.00 Rp 293,189.00
- Portland cement 10.0000 kg Rp 1,220.00 Rp 12,200.00
- Pasir pasang 0.0450 m3 Rp 401,338.99 Rp 18,060.25
- Semen warna 1.5000 m3 Rp 6,500.00
b. Upah: Rp 64,696.04
- Pekerja 0.2600 hari Rp 137,242.34 Rp 35,683.01
- Tukang 0.1500 hari Rp 166,063.23 Rp 24,909.48
- Kepala tukang 0.0130 hari Rp 157,828.69 Rp 2,051.77
- Mandor 0.0130 hari Rp 157,828.69 Rp 2,051.77
Jumlah Rp 388,145.29
Keuntungan 10% : Rp 38,814.53
Jumlah : Rp 426,959.82
Dibulatkan : Rp 427,000.00
ANALISIS HARGA SATUAN PEKERJAAN BIDANG PEKERJAAN UMUMNOMOR : 28/PRT/M/2016
NO. URAIAN KOEF SATUAN HARGA STUAN SUB. JUMLAH JUMLAH
1 2 3 4 5 6 7
Persyaratan teknis dalam perhitungan harga satuan pekerjaan :
a. Pelaksanaan perhitungan satuan pekerjaan harus didasarkan pada gambar teknis dan rencana kerja syarat-syarat (RKS).
b. Pelaksanaan Koefisien bahan telah ditambahkan toleransi sebesar 5% - 20%, dimana didalamnya termasuk angka susut, yang
besarnya tergantung dari jenis bahan dan komposisi adukan.
c. Jam kerja efektif untuk tenaga kerja diperhitungkan 5 jam per hari.

D SNI-2839-2008 PENETAPAN INDEKS HARGA SATUAN PEKERJAAN LANGIT-LANGIT

1 1 m² Pasang Langit-langit Asbes Semen Tebal 4 mm

2 1 m² Pasang Langit-langit Akustik 30 x 30 cm

3 1 m² Pasang Langit-langit Akustik 30 x 60 cm

4 1 m² Pasang Langit-langit Akustik 60 x 120 cm

5 1 m² Pasang Langit-langit Tripleks 120 x 240 cm. Tebal 3. 4. 6 mm

A.4.5.1.7 1 m² Pasang Langit-langit Gypsum Board 120 x 240 x 9 mm. Tebal 9 mm


Bahan Rp 19,815.25
Gypsum Board t=9mm Jayaboard 0.364 Lembar Rp 46,090.79 Rp 16,777.05
Drywall Screw 25mmX083 12.153 pc(s) Rp 250.00 Rp 3,038.20
Jointing Compound UB-10/20/888/CCL 20kg/b 0.019 bag(s) Rp 71,600.00 Rp 1,360.40
UB Tape 75m/roll(s) 0.016 roll(s) Rp 39,600.00 Rp 633.60
Tenaga Kerja Rp 23,605.68
Pekerja 0.100 org/hr Rp 137,242.34 Rp 13,724.23
Tukang 0.050 org/hr Rp 166,063.23 Rp 8,303.16
Kepala Tukang 0.005 org/hr Rp 157,828.69 Rp 789.14
Mandor 0.005 org/hr Rp 157,828.69 Rp 789.14
Jumlah Rp 43,420.93
Keuntungan 10% : Rp 4,342.09
Jumlah : Rp 47,763.02
Dibulatkan : Rp 47,800.00

A.4.5.1.7 1 m² Pasang Langit-langit calcium cilicate Board 120 x 240 Tebal 4 mm


Bahan Rp 24,671.21
Calcium cilicate t=6mm GRC 0.364 Lembar Rp 53,953.34 Rp 19,639.01
Drywall Screw 25mmX083 12.153 pc(s) Rp 250.00 Rp 3,038.20
Jointing Compound UB-10/20/888/CCL 20kg/b 0.019 bag(s) Rp 71,600.00 Rp 1,360.40
UB Tape 75m/roll(s) 0.016 roll(s) Rp 39,600.00 Rp 633.60
Tenaga Kerja Rp 25,985.50
Pekerja 0.100 org/hr Rp 157,643.00 Rp 15,764.30
Tukang 0.050 org/hr Rp 166,729.00 Rp 8,336.45
Kepala Tukang 0.005 org/hr Rp 182,676.00 Rp 913.38
Mandor 0.005 org/hr Rp 194,274.00 Rp 971.37
Jumlah Rp 50,656.71
Keuntungan 10% : Rp 5,065.67
Jumlah : Rp 55,722.39
Dibulatkan : Rp 55,700.00

A.4.5.1.7 1 m² Pasang Langit-langit Gypsum water prof 120 x 240 Tebal 9 mm


Bahan Rp 51,415.80
Gyfsum Board water prof Tebal 9 mm 0.364 Lembar Rp 127,427.48 Rp 46,383.60
Drywall Screw 25mmX083 12.153 pc(s) Rp 250.00 Rp 3,038.20
Jointing Compound UB-10/20/888/CCL 20kg/b 0.019 bag(s) Rp 71,600.00 Rp 1,360.40
UB Tape 75m/roll(s) 0.016 roll(s) Rp 39,600.00 Rp 633.60
Tenaga Kerja Rp 25,985.50
Pekerja 0.100 org/hr Rp 157,643.00 Rp 15,764.30
Tukang 0.050 org/hr Rp 166,729.00 Rp 8,336.45
Kepala Tukang 0.005 org/hr Rp 182,676.00 Rp 913.38
Mandor 0.005 org/hr Rp 194,274.00 Rp 971.37
Jumlah Rp 77,401.30
Keuntungan 10% : Rp 7,740.13
Jumlah : Rp 85,141.43
Dibulatkan : Rp 85,100.00
D.4 1 m² Pasang Ceiling Panel tile 9mm (600mmx1200mm)
Bahan Rp -
Ceiling Panel tile 9mm (600mmx1200mm) 1.500 Lembar Rp - Rp -
Tenaga Kerja Rp 25,985.50
Pekerja 0.100 org/hr Rp 157,643.00 Rp 15,764.30
Tukang 0.050 org/hr Rp 166,729.00 Rp 8,336.45
Kepala Tukang 0.005 org/hr Rp 182,676.00 Rp 913.38
Mandor 0.005 org/hr Rp 194,274.00 Rp 971.37
Jumlah Rp 25,985.50
Keuntungan 10% : Rp 2,598.55
Jumlah : Rp 28,584.05
Dibulatkan : Rp 28,600.00
NO. URAIAN KOEF SATUAN HARGA STUAN SUB. JUMLAH JUMLAH
1 2 3 4 5 6 7
Persyaratan teknis dalam perhitungan harga satuan pekerjaan :
a. Pelaksanaan perhitungan satuan pekerjaan harus didasarkan pada gambar teknis dan rencana kerja syarat-syarat (RKS).
b. Pelaksanaan Koefisien bahan telah ditambahkan toleransi sebesar 5% - 20%, dimana didalamnya termasuk angka susut, yang
besarnya tergantung dari jenis bahan dan komposisi adukan.
c. Jam kerja efektif untuk tenaga kerja diperhitungkan 5 jam per hari.

D SNI-2839-2008 PENETAPAN INDEKS HARGA SATUAN PEKERJAAN LANGIT-LANGIT


D.5 1 m1 Pasang List plafon gyfsum profil
Bahan Rp 9,987.00
gyfsum profil l=7cm 1.050 m' Rp 9,000.00 Rp 9,450.00
Tepung gyfsum 0.150 Kg Rp 3,580.00 Rp 537.00
Tenaga Kerja Rp 19,618.79
Pekerja 0.060 org/hr Rp 137,242.34 Rp 8,234.54
Tukang 0.060 org/hr Rp 166,063.23 Rp 9,963.79
Kepala Tukang 0.006 org/hr Rp 157,828.69 Rp 946.97
Mandor 0.003 org/hr Rp 157,828.69 Rp 473.49
Jumlah Rp 29,605.79
Keuntungan 10% : Rp 2,960.58
Jumlah : Rp 32,566.37
Dibulatkan : Rp 32,600.00

D.6 1 m' Pasang List Langit-langit Kayu Profil


Bahan Rp 36,874.72
List Kayu Profil 1.050 m' Rp 35,000.00 Rp 36,750.00
Paku 0.010 Kg Rp 12,471.63 Rp 124.72
Tenaga Kerja Rp 16,427.91
Pekerja 0.050 org/hr Rp 137,242.34 Rp 6,862.12
Tukang 0.050 org/hr Rp 166,063.23 Rp 8,303.16
Kepala Tukang 0.005 org/hr Rp 157,828.69 Rp 789.14
Mandor 0.003 org/hr Rp 157,828.69 Rp 473.49
Jumlah
Rp 53,302.62
Keuntungan 10% : Rp 5,330.26
Jumlah : Rp 58,632.89
Dibulatkan : Rp 58,600.00

D.7 1 m² Pasang rangka hollow Metal Furing uk. gypsum / calcium cilicate
Bahan Rp 79,344.58
Metal Furing 4 x 4 cm 0.5000 btg Rp 73,203.02 Rp 36,601.51
Metal Furig 2 x 4 cm 0.3333 btg Rp 110,000.00 Rp 36,666.67
Drywall Screw 25mmX083 24.306 pc(s) Rp 250.00 Rp 6,076.40
Tenaga Kerja Rp 70,470.66
Tukang 0.2000 org/hr Rp 166,729.00 Rp 33,345.80
Pekerja 0.2000 org/hr Rp 157,643.00 Rp 31,528.60
Kepala Tukang 0.0200 org/hr Rp 182,676.00 Rp 3,653.52
Mandor 0.0100 org/hr Rp 194,274.00 Rp 1,942.74
JumlahRp 149,815.24
Keuntungan 10% : Rp 14,981.52
Jumlah : Rp 164,796.76
Dibulatkan : Rp 164,800.00

D.8 1 m² Pasang plafond gyfsum board t=9mm berikut rangka Metal Furing
Pasang rangka hollow Metal Furing uk.
A.4.5.1.7 1 m2 Rp 149,815.24 Rp 149,815.24
gypsum / calcium cilicate
Pasang Langit-langit Gypsum Board 120 x
D.7 1 m2 Rp 43,420.93 Rp 43,420.93
240 x 9 mm. Tebal 9 mm
Jumlah Rp 193,236.17
Dibulatkan : Rp 193,200.00
D.9 1 m² Pasang plafond calcium cilicate GRC t=6mm berikut rangka hollow galvanises
Pasang rangka hollow Metal Furing uk.
A.4.5.1.7 1 m2 Rp 149,815.24 Rp 149,815.24
gypsum / calcium cilicate
Pasang Langit-langit calcium cilicate Board
A.4.5.1.7 1 m2 Rp 50,656.71 Rp 50,656.71
120 x 240 Tebal 4 mm
Jumlah Rp 200,471.95
Dibulatkan : Rp 200,500.00
D.10 1 m² Pasang plafond gyfsum tile 600 x 1200 t=6mm berikut rangka metal furing BMSys
Pasang rangka metal furing BMSys ( Untuk
1 m2 Rp 70,470.66 Rp 70,470.66
ceilling
Pasangpanel 600 x 1200
Langit-langit ) tile 600 x
gyfsum
8 1 m2 Rp 25,985.50 Rp 25,985.50
1200mm
Jumlah Rp 96,456.16
Dibulatkan : Rp 96,500.00

D.11 1 m² Pek. Plafon Sunda Plafond t= 6mm + Rangka Hollow


A.4.5.1.7 Pasang rangka hollow Metal Furing uk.
gypsum / calcium cilicate 1 m2 Rp 157,000.00 Rp 157,000.00
A.4.5.1.7 Pasang Langit-langit Gypsum water prof
120 x 240 Tebal 6 mm 1 m2 Rp 123,000.00 Rp 123,000.00
Jumlah Rp 280,000.00
Dibulatkan : Rp 280,000.00
NO. URAIAN KOEF SATUAN HARGA STUAN SUB. JUMLAH JUMLAH
1 2 3 4 5 6 7
Persyaratan teknis dalam perhitungan harga satuan pekerjaan :
a. Pelaksanaan perhitungan satuan pekerjaan harus didasarkan pada gambar teknis dan rencana kerja syarat-syarat (RKS).
b. Pelaksanaan Koefisien bahan telah ditambahkan toleransi sebesar 5% - 20%, dimana didalamnya termasuk angka susut, yang
besarnya tergantung dari jenis bahan dan komposisi adukan.
c. Jam kerja efektif untuk tenaga kerja diperhitungkan 5 jam per hari.

D SNI-2839-2008 PENETAPAN INDEKS HARGA SATUAN PEKERJAAN LANGIT-LANGIT


D.12 1 m² Dinding Partisi Gypsum 12 mm + Rangka Metal BMSys
Bahan Rp 86,936.21
Metal Wall Stud 0.570 pc(s) Rp 41,300.00 Rp 23,541.00
Metal Wall Track 0.222 pc(s) Rp 41,300.00 Rp 9,176.86
Jointing Compound UB-10/20/888/CCL 20kg/b 0.038 bag(s) Rp 71,600.00 Rp 2,720.80
UB Tape 75m/roll(s) 0.032 roll(s) Rp 39,600.00 Rp 1,267.20
Drywall Screw 25mmX083 24.306 pc(s) Rp 500.00 Rp 12,152.80
Jaya Sealant 580ml 0.291 pc(s) Rp 20,000.00 Rp 5,814.00
Gypsum 2.4 x 1.2 t= 9 mm Jayaboard 0.700 lembar Rp 46,090.79 Rp 32,263.55
Tenaga Kerja Rp 117,807.21
Tukang gypsum 0.300 org/hr Rp 166,729.00 Rp 50,018.70
Tukang allumunium 0.200 org/hr Rp 166,729.00 Rp 33,345.80
Pekerja 0.200 org/hr Rp 157,643.00 Rp 31,528.60
Mandor 0.015 org/hr Rp 194,274.00 Rp 2,914.11
Jumlah Rp 204,743.42
Keuntungan 10% : Rp 20,474.34
Jumlah : Rp 225,217.77
Dibulatkan : Rp 225,200.00
D.13 1 m² Dinding Partisi Double Kalsiboard 6 mm + + Rangka Metal BMSys
Bahan Rp 93,084.35
Metal Wall Stud 0.570 m2 Rp 41,300.00 Rp 23,541.00
Metal Wall Track 0.222 m2 Rp 41,300.00 Rp 9,176.86
Jointing Compound UB-10/20/888/CCL 20kg/b 0.038 m2 Rp 71,600.00 Rp 2,720.80
UB Tape 75m/roll(s) 0.032 m2 Rp 39,600.00 Rp 1,267.20
Drywall Screw 25mmX083 24.306 bh Rp 500.00 Rp 12,152.80
Jaya Sealant 580ml 0.291 bh Rp 20,000.00 Rp 5,814.00
Skrup kalsiboard 0.150 bh Rp 500.00 Rp 75.00
Calcium cilicate t=6mm setara GRC 0.700 Lembar Rp 54,766.70 Rp 38,336.69
Tenaga Kerja Rp 117,807.21
Tukang 0.300 org/hr Rp 166,729.00 Rp 50,018.70
Tukang allumunium 0.200 org/hr Rp 166,729.00 Rp 33,345.80
Pekerja 0.200 org/hr Rp 157,643.00 Rp 31,528.60
Mandor 0.015 org/hr Rp 194,274.00 Rp 2,914.11
Jumlah Rp 210,891.56
Keuntungan 10% : Rp 21,089.16
Jumlah : Rp 231,980.72
Dibulatkan : Rp 232,000.00

A.4.5.1.7 1 m² Pasang Langit-langit Gypsum Board 120 x 240 x 9 mm. Tebal 9 mm


Bahan Rp 270,586.36
Shunda Plafond 1.000 m2 Rp 158,438.00 Rp 158,438.00
Rangka hollow 4x4 cm 1.130 btg Rp 87,843.63 Rp 99,263.30
Alat Bantu 5% * Rp 12,885.06
Tenaga Kerja Rp 23,605.68
Pekerja 0.100 org/hr Rp 137,242.34 Rp 13,724.23
Tukang 0.050 org/hr Rp 166,063.23 Rp 8,303.16
Kepala Tukang 0.005 org/hr Rp 157,828.69 Rp 789.14
Mandor 0.005 org/hr Rp 157,828.69 Rp 789.14
Jumlah Rp 294,192.04
Keuntungan 10% : Rp 29,419.20
Jumlah : Rp 323,611.25
Dibulatkan : Rp 323,600.00
NO. URAIAN KOEF SATUAN HARGA STUAN SUB. JUMLAH JUMLAH
1 2 2 3 4 5 6
Persyaratan teknis dalam perhitungan harga satuan pekerjaan :
a. Pelaksanaan perhitungan satuan pekerjaan harus didasarkan pada gambar teknis dan rencana kerja syarat-syarat (RKS).
b. Pelaksanaan Koefisien bahan telah ditambahkan toleransi sebesar 5% - 20%, dimana didalamnya termasuk angka susut,
yang besarnya tergantung dari jenis bahan dan komposisi adukan.
c. Jam kerja efektif untuk tenaga kerja diperhitungkan 5 jam per hari.

I PENETAPAN INDEKS HARGA SATUAN PEKERJAAN PENUTUP ATAP

I.1 1 m2 Atap Kanopy Twinlight + Rangka Hollow

a. Bahan: 296,296.04
- Polycarbonat t 6 mm setara twinlate/Impral 1.1000 m2 107,400.00 118,140.00
- Sekroof 42.0000 bh 250.00 10,500.00
- Rangka hollow 40.40.1.6 5.0000 m1 29,281.21 146,406.04
- Kawat las 0.2500 kg 85,000.00 21,250.00
b. Upah: 102,124.80
- Pekerja 0.4000 hari 157,643.00 63,057.20
- Tukang las 0.2000 hari 157,643.00 31,528.60
- Kepala Tukang 0.0200 bh 182,676.00 3,653.52
- Mandor 0.0200 hari 194,274.00 3,885.48

Jumlah Rp 398,420.84
Keuntungan 10% : Rp 39,842.08
Jumlah : Rp 438,262.93
Dibulatkan : Rp 438,300.00
I.1a 1 m2 Atap Kanopy Twinlight

a. Bahan: 128,640.00
- Polycarbonat t 6 mm setara twinlate/Impral 1.1000 m2 107,400.00 118,140.00
- Sekroof 42.0000 bh 250.00 10,500.00
- Rangka hollow 40.40.1.6 5.0000 m1 852.33
- Kawat las 0.2500 kg 6,500.00
b. Upah: 102,124.80
- Pekerja 0.4000 hari 157,643.00 63,057.20
- Tukang las 0.2000 hari 157,643.00 31,528.60
- Kepala Tukang 0.0200 bh 182,676.00 3,653.52
- Mandor 0.0200 hari 194,274.00 3,885.48

Jumlah Rp 230,764.80
Keuntungan 10% : Rp 23,076.48
Jumlah : Rp 253,841.28
Dibulatkan : Rp 253,800.00
I.2 1 m2 Glass wool WM6

a. Bahan: 27,300.00
- WM6 1.0500 m2 26,000.00 27,300.00
b. Upah: 42,216.59
- Pekerja 0.1500 hari 157,643.00 23,646.45
- Tukang 0.0500 hari 157,643.00 7,882.15
- Kepala tukang 0.0500 hari 182,676.00 9,133.80
- Mandor 0.0080 hari 194,274.00 1,554.19

Jumlah Rp 69,516.59
Keuntungan 10% : Rp 6,951.66
Jumlah : Rp 76,468.25
Dibulatkan : Rp 76,500.00
A.4.5.2.1 1 m2 Pasang atap genteng palentong biasa
1 Bahan 50,000.00
Genteng palentong 25.000 bh 2,000.00 50,000.00
2 Tenaga 38,393.94
Pekerja 0.150 oh 157,643.00 23,646.45
Tukang kayu 0.075 oh 157,643.00 11,823.23
Kepala tukang 0.008 oh 182,676.00 1,370.07
Mandor 0.008 oh 194,274.00 1,554.19

Jumlah Rp 88,393.94
Keuntungan 10% : Rp 8,839.39
Jumlah : Rp 97,233.33
Dibulatkan : Rp 97,200.00

ANALISIS HARGA SATUAN PEKERJAAN BIDANG PEKERJAAN UMUMNOMOR : 28/PRT/M/2016


NO. URAIAN KOEF SATUAN HARGA STUAN SUB. JUMLAH JUMLAH
1 2 2 3 4 5 6
Persyaratan teknis dalam perhitungan harga satuan pekerjaan :
a. Pelaksanaan perhitungan satuan pekerjaan harus didasarkan pada gambar teknis dan rencana kerja syarat-syarat (RKS).
b. Pelaksanaan Koefisien bahan telah ditambahkan toleransi sebesar 5% - 20%, dimana didalamnya termasuk angka susut,
yang besarnya tergantung dari jenis bahan dan komposisi adukan.
c. Jam kerja efektif untuk tenaga kerja diperhitungkan 5 jam per hari.

I PENETAPAN INDEKS HARGA SATUAN PEKERJAAN PENUTUP ATAP


A.4.5.2.4 1 m' Pasang bubung genteng palentong biasa
1 Bahan 55,556.85
Genteng bubung morando 5.000 bh 8,500.00 42,500.00
Semen portland 0.160 zak 61,000.00 9,760.00
Pasir pasang 0.032 m3 103,026.47 3,296.85
2 Tenaga 98,627.87
Pekerja 0.400 oh 157,643.00 63,057.20
Tukang kayu 0.200 oh 157,643.00 31,528.60
Kepala tukang 0.020 oh 182,676.00 3,653.52
Mandor 0.002 oh 194,274.00 388.55

Jumlah Rp 154,184.72
Keuntungan 10% : Rp 15,418.47
Jumlah : Rp 169,603.19
Dibulatkan : Rp 169,600.00
I.5 1 m2 Pasang atap genteng morando
1 Bahan 58,000.00
Genteng morando 20.000 bh 2,900.00 58,000.00
2 Tenaga 35,755.28
Pekerja 0.150 oh 157,643.00 23,646.45
Tukang kayu 0.060 oh 157,643.00 9,458.58
Kepala tukang 0.006 oh 182,676.00 1,096.06
Mandor 0.008 oh 194,274.00 1,554.19

Jumlah Rp 93,755.28
Keuntungan 10% : Rp 9,375.53
Jumlah : Rp 103,130.81
Dibulatkan : Rp 103,100.00
I.6 1 m' Pasang genteng bubung morando
1 Bahan 58,056.85
Genteng bubung morando 5.000 bh 9,000.00 45,000.00
Semen portland 0.160 zak 61,000.00 9,760.00
Pasir pasang 0.032 m3 103,026.47 3,296.85
2 Tenaga 98,627.87
Pekerja 0.400 oh 157,643.00 63,057.20
Tukang kayu 0.200 oh 157,643.00 31,528.60
Kepala tukang 0.020 oh 182,676.00 3,653.52
Mandor 0.002 oh 194,274.00 388.55

Jumlah Rp 156,684.72
Keuntungan 10% : Rp 15,668.47
Jumlah : Rp 172,353.19
Dibulatkan : Rp 172,400.00
I.7 1 m' Pasang genteng samping penutup lisplang morando
1 Bahan 80,056.85
Genteng samping penutup lisplang morando 5.000 bh 13,400.00 67,000.00
Semen portland 0.160 zak 61,000.00 9,760.00
Pasir pasang 0.032 m3 103,026.47 3,296.85
2 Tenaga 98,627.87
Pekerja 0.400 oh 157,643.00 63,057.20
Tukang kayu 0.200 oh 157,643.00 31,528.60
Kepala tukang 0.020 oh 182,676.00 3,653.52
Mandor 0.002 oh 194,274.00 388.55

Jumlah Rp 178,684.72
Keuntungan 10% : Rp 17,868.47
Jumlah : Rp 196,553.19
Dibulatkan : Rp 196,600.00

ANALISIS HARGA SATUAN PEKERJAAN BIDANG PEKERJAAN UMUMNOMOR : 28/PRT/M/2016


NO. URAIAN KOEF SATUAN HARGA STUAN SUB. JUMLAH JUMLAH
1 2 2 3 4 5 6
Persyaratan teknis dalam perhitungan harga satuan pekerjaan :
a. Pelaksanaan perhitungan satuan pekerjaan harus didasarkan pada gambar teknis dan rencana kerja syarat-syarat (RKS).
b. Pelaksanaan Koefisien bahan telah ditambahkan toleransi sebesar 5% - 20%, dimana didalamnya termasuk angka susut,
yang besarnya tergantung dari jenis bahan dan komposisi adukan.
c. Jam kerja efektif untuk tenaga kerja diperhitungkan 5 jam per hari.

I PENETAPAN INDEKS HARGA SATUAN PEKERJAAN PENUTUP ATAP


A.4.5.2.3 1 m2 Pasang Atap Genteng Palentong Besar Ex. Jatiwangi Glazur
1 Bahan 80,400.00
Genteng Glazur Ex. Jatiwangi 12.000 bh 6,700.00 80,400.00
2 Tenaga 38,485.28
Pekerja 0.150 oh 157,643.00 23,646.45
Tukang kayu 0.075 oh 157,643.00 11,823.23
Kepala tukang 0.008 oh 182,676.00 1,461.41
Mandor 0.008 oh 194,274.00 1,554.19

Jumlah Rp 118,885.28
Keuntungan 10% : Rp 11,888.53
Jumlah : Rp 130,773.80
Dibulatkan : Rp 130,800.00
A.4.5.2.6 1 m' Pasang Bubungan Palentong Besar Ex. Jatiwangi Glazur
1 Bahan 540,496.85
Bubungan Genteng Glazur Ex. Jatiwangi 4.000 bh 12,300.00 49,200.00
Semen portland 8.000 zak 61,000.00 488,000.00
Pasir pasang 0.032 m3 103,026.47 3,296.85
2 Tenaga 98,627.87
Pekerja 0.400 oh 157,643.00 63,057.20
Tukang kayu 0.200 oh 157,643.00 31,528.60
Kepala tukang 0.020 oh 182,676.00 3,653.52
Mandor 0.002 oh 194,274.00 388.55

Jumlah Rp 639,124.72
Keuntungan 10% : Rp 63,912.47
Jumlah : Rp 703,037.19
Dibulatkan : Rp 703,000.00
I.10 1 m2 Pasang Atap Genteng Keramik Glazur Ex. Kanmuri
1 Bahan 204,000.00
Genteng Keramik Glazur Ex. Kanmuri 20.000 bh 10,200.00 204,000.00
2 Tenaga 35,755.28
Pekerja 0.150 oh 157,643.00 23,646.45
Tukang kayu 0.060 oh 157,643.00 9,458.58
Kepala tukang 0.006 oh 182,676.00 1,096.06
Mandor 0.008 oh 194,274.00 1,554.19

Jumlah Rp 239,755.28
Keuntungan 10% : Rp 23,975.53
Jumlah : Rp 263,730.81
Dibulatkan : Rp 263,700.00
I.11 1 m' Pasang Bubungan Keramik Glazur Ex. Kanmuri
1 Bahan 99,056.85
Bubungan Genteng Keramik Glazur Ex. Kanmu 5.000 bh 17,200.00 86,000.00
Semen portland 0.160 zak 61,000.00 9,760.00
Pasir pasang 0.032 m3 103,026.47 3,296.85
2 Tenaga 98,627.87
Pekerja 0.400 oh 157,643.00 63,057.20
Tukang kayu 0.200 oh 157,643.00 31,528.60
Kepala tukang 0.020 oh 182,676.00 3,653.52
Mandor 0.002 oh 194,274.00 388.55

Jumlah Rp 197,684.72
Keuntungan 10% : Rp 19,768.47
Jumlah : Rp 217,453.19
Dibulatkan : Rp 217,500.00

ANALISIS HARGA SATUAN PEKERJAAN BIDANG PEKERJAAN UMUMNOMOR : 28/PRT/M/2016


NO. URAIAN KOEF SATUAN HARGA STUAN SUB. JUMLAH JUMLAH
1 2 2 3 4 5 6
Persyaratan teknis dalam perhitungan harga satuan pekerjaan :
a. Pelaksanaan perhitungan satuan pekerjaan harus didasarkan pada gambar teknis dan rencana kerja syarat-syarat (RKS).
b. Pelaksanaan Koefisien bahan telah ditambahkan toleransi sebesar 5% - 20%, dimana didalamnya termasuk angka susut,
yang besarnya tergantung dari jenis bahan dan komposisi adukan.
c. Jam kerja efektif untuk tenaga kerja diperhitungkan 5 jam per hari.

I PENETAPAN INDEKS HARGA SATUAN PEKERJAAN PENUTUP ATAP


A.4.5.2.30 1 m2 Pasang atap genteng beton
1 Bahan 170,874.15
Genteng beton 11.000 bh 15,500.00 170,500.00
Paku biasa 2" - 5" 0.030 kg 12,471.63 374.15
2 Tenaga 51,062.40
Pekerja 0.200 oh 157,643.00 31,528.60
Tukang kayu 0.100 oh 157,643.00 15,764.30
Kepala tukang 0.010 oh 182,676.00 1,826.76
Mandor 0.010 oh 194,274.00 1,942.74

Jumlah Rp 221,936.55
Keuntungan 10% : Rp 22,193.65
Jumlah : Rp 244,130.20
Dibulatkan : Rp 244,100.00
A.4.5.2.35 1 m' Pasang nok genteng beton
1 Bahan 91,496.43
Nok genteng beton 3.500 bh 19,400.00 67,900.00
Paku biasa 2" x 5" 0.050 kg 12,471.63 623.58
Semen abu-abu 10.800 kg 1,220.00 13,176.00
Pasir pasang 0.032 m3 103,026.47 3,296.85
Semen warna 1.000 kg 6,500.00 6,500.00
2 Tenaga 102,124.80
Pekerja 0.400 oh 157,643.00 63,057.20
Tukang kayu 0.200 oh 157,643.00 31,528.60
Kepala tukang 0.020 oh 182,676.00 3,653.52
Mandor 0.020 oh 194,274.00 3,885.48

Jumlah Rp 193,621.23
Keuntungan 10% : Rp 19,362.12
Jumlah : Rp 212,983.35
Dibulatkan : Rp 213,000.00
I.14 1 m2 Pasang atap Bitumen 400x1060 mm/Onduvila
1 Bahan 91,500.00
Atap Bitumen Casa Ex. Gutta uk. 3x500x105 2.610 bh 30,000.00 78,300.00
Paku Sekrup 12.000 kg 1,100.00 13,200.00
2 Tenaga 51,062.40
Pekerja 0.200 oh 157,643.00 31,528.60
Tukang kayu 0.100 oh 157,643.00 15,764.30
Kepala tukang 0.010 oh 182,676.00 1,826.76
Mandor 0.010 oh 194,274.00 1,942.74

Jumlah Rp 142,562.40
Keuntungan 10% : Rp 14,256.24
Jumlah : Rp 156,818.64
Dibulatkan : Rp 156,800.00
A.4.5.2.39 1 m1 Pasang Nok Atap Bitumen Ukuran l: 800 mm/Onduvila
1 Bahan 66,000.00
Nok Atap Bitumen Casa Ex. Gutta uk 1.100 bh 50,000.00 55,000.00
Paku Sekrup 10.000 kg 1,100.00 11,000.00
2 Tenaga 68,322.90
Pekerja 0.250 oh 157,643.00 39,410.75
Tukang kayu 0.150 oh 157,643.00 23,646.45
Kepala tukang 0.015 oh 182,676.00 2,740.14
Mandor 0.013 oh 194,274.00 2,525.56

Jumlah Rp 134,322.90
Keuntungan 10% : Rp 13,432.29
Jumlah : Rp 147,755.19
Dibulatkan : Rp 147,800.00

ANALISIS HARGA SATUAN PEKERJAAN BIDANG PEKERJAAN UMUMNOMOR : 28/PRT/M/2016


NO. URAIAN KOEF SATUAN HARGA STUAN SUB. JUMLAH JUMLAH
1 2 2 3 4 5 6
Persyaratan teknis dalam perhitungan harga satuan pekerjaan :
a. Pelaksanaan perhitungan satuan pekerjaan harus didasarkan pada gambar teknis dan rencana kerja syarat-syarat (RKS).
b. Pelaksanaan Koefisien bahan telah ditambahkan toleransi sebesar 5% - 20%, dimana didalamnya termasuk angka susut,
yang besarnya tergantung dari jenis bahan dan komposisi adukan.
c. Jam kerja efektif untuk tenaga kerja diperhitungkan 5 jam per hari.

I PENETAPAN INDEKS HARGA SATUAN PEKERJAAN PENUTUP ATAP


A.4.5.2.39 1 m2 Pasang atap seng gelombang
1 Bahan 31,744.01
Seng gelombang 3" x 6" bkls 28 0.700 lbr 45,000.00 31,500.00
Paku payung + karet 2" 0.020 kg 12,200.50 244.01
2 Tenaga 30,637.44
Pekerja 0.120 oh 157,643.00 18,917.16
Tukang kayu 0.060 oh 157,643.00 9,458.58
Kepala tukang 0.006 oh 182,676.00 1,096.06
Mandor 0.006 oh 194,274.00 1,165.64

Jumlah Rp 62,381.45
Keuntungan 10% : Rp 6,238.15
Jumlah : Rp 68,619.60
Dibulatkan : Rp 68,600.00
A.4.5.2.40 1 m2 Pasang atap nok seng
1 Bahan 14,898.87
Nok Seng plat 3" x 6" bjls 28 0.300 lbr 48,000.00 14,400.00
Paku biasa 1/2" - 1" 0.040 kg 12,471.63 498.87
2 Tenaga 37,308.51
Pekerja 0.150 oh 157,643.00 23,646.45
Tukang kayu 0.070 oh 157,643.00 11,035.01
Kepala tukang 0.008 oh 182,676.00 1,461.41
Mandor 0.006 oh 194,274.00 1,165.64

Jumlah Rp 52,207.38
Keuntungan 10% : Rp 5,220.74
Jumlah : Rp 57,428.11
Dibulatkan : Rp 57,400.00
I.17 1 m2 Pasang atap Zinc - Allumunium Prepainted TCT 0.45mm
a. Bahan: 142,259.83
- Union Pesona TCT 0.45mm lebar 990mm c 1.0500 m2 133,110.00 139,765.50
- Paku hak panjang 15 cm 0.2000 kg 12,471.63 2,494.33
b. Upah: 55,818.67
- Kepala Tukang las 0.0100 hari 157,643.00 1,576.43
- Tukang las 0.1000 hari 157,643.00 15,764.30
- Pekerja 0.2000 hari 182,676.00 36,535.20
- Mandor 0.0100 hari 194,274.00 1,942.74

Jumlah Rp 198,078.50
Keuntungan 10% : Rp 19,807.85
Jumlah : Rp 217,886.34
Dibulatkan : Rp 217,900.00
#VALUE! 1 m2 Pasang atap Zinc - Allumunium Standing seam TCT 0.50 mm
1 Bahan 249.43
Zinc - Allumunium Standing seam TCT 0.50 1.050 m3 0.00 -
Paku hak panjang 15 cm 0.020 kg 12,471.63 249.43
2 Tenaga 144,505.75
Pekerja 0.150 oh 157,643.00 23,646.45
Tukang kayu 0.750 oh 157,643.00 118,232.25
Kepala tukang 0.008 oh 182,676.00 1,461.41
Mandor 0.006 oh 194,274.00 1,165.64

Jumlah Rp 144,755.18
Keuntungan 10% : Rp 14,475.52
Jumlah : Rp 159,230.70
Dibulatkan : Rp 159,200.00
A.4.5.2.52 1 m1 Pasang nok Zincalume t=0.45mm
1 Bahan 63,543.87
- Nok Standar untuk sudut atap curam 1.200 m1 52,537.50 63,045.00
Paku hak panjang 15 cm 0.040 kg 12,471.63 498.87
2 Tenaga 209,270.75
Pekerja 1.000 oh 157,643.00 157,643.00
Tukang kayu 0.150 oh 157,643.00 23,646.45
Kepala tukang 0.100 oh 182,676.00 18,267.60
Mandor 0.050 oh 194,274.00 9,713.70

Jumlah Rp 272,814.62
Keuntungan 10% : Rp 27,281.46
Jumlah : Rp 300,096.08
Dibulatkan : Rp 300,100.00
A.4.5.2.53 1 m1 Pasang Lisplank GRC
1 Bahan 25,360.03
GRC 0.330 Lbr 75,000.00 24,750.00
Paku GRC 0.050 kg 12,200.50 610.03
2 Tenaga 51,917.79
Pekerja 0.100 oh 157,643.00 15,764.30
Tukang kayu 0.200 oh 157,643.00 31,528.60
Kepala tukang 0.020 oh 182,676.00 3,653.52
Mandor 0.005 oh 194,274.00 971.37
ANALISIS HARGA SATUAN PEKERJAAN BIDANG PEKERJAAN UMUMNOMOR : 28/PRT/M/2016
NO. URAIAN KOEF SATUAN HARGA STUAN SUB. JUMLAH JUMLAH
1 2 2 3 4 5 6
Persyaratan teknis dalam perhitungan harga satuan pekerjaan :
a. Pelaksanaan perhitungan satuan pekerjaan harus didasarkan pada gambar teknis dan rencana kerja syarat-syarat (RKS).
b. Pelaksanaan Koefisien bahan telah ditambahkan toleransi sebesar 5% - 20%, dimana didalamnya termasuk angka susut,
yang besarnya tergantung dari jenis bahan dan komposisi adukan.
c. Jam kerja efektif untuk tenaga kerja diperhitungkan 5 jam per hari.

I PENETAPAN INDEKS HARGA SATUAN PEKERJAAN PENUTUP ATAP

Jumlah Rp 77,277.82
Keuntungan 10% : Rp 7,727.78
Jumlah : Rp 85,005.60
Dibulatkan : Rp 85,000.00
#VALUE! 1 m1 Pasang atap arah melintang ( Transvarsa pascia capping ) TCT 0.45mm
1 Bahan -
- Penutup atap arah memanjang 1.100 m1 26,055.00
Paku hak panjang 15 cm 0.040 kg 12,200.50
2 Tenaga -
Pekerja 0.250 oh 157,643.00
Tukang kayu 0.150 oh 157,643.00
Kepala tukang 0.015 oh 182,676.00
Mandor 0.013 oh 194,274.00

Jumlah Rp -
Keuntungan 10% : Rp -
Jumlah : Rp -
Dibulatkan : Rp -

ANALISIS HARGA SATUAN PEKERJAAN BIDANG PEKERJAAN UMUMNOMOR : 28/PRT/M/2016


NO. URAIAN KOEF SATUAN HARGA STUAN SUB. JUMLAH JUMLAH
1 2 2 3 4 5 6
Persyaratan teknis dalam perhitungan harga satuan pekerjaan :
a. Pelaksanaan perhitungan satuan pekerjaan harus didasarkan pada gambar teknis dan rencana kerja syarat-syarat (RKS).
b. Pelaksanaan Koefisien bahan telah ditambahkan toleransi sebesar 5% - 20%, dimana didalamnya termasuk angka susut,
yang besarnya tergantung dari jenis bahan dan komposisi adukan.
c. Jam kerja efektif untuk tenaga kerja diperhitungkan 5 jam per hari.

I PENETAPAN INDEKS HARGA SATUAN PEKERJAAN PENUTUP ATAP


I.20 1 m2 Pasang Alumunium foil Setara Primary Smart - Foam 6.5 mm
1 Bahan 48,300.00
Alumunium foil Setara Primary Smart - Foa 1.050 m2 46,000.00 48,300.00
2 Tenaga 26,114.02
Pekerja 0.100 oh 157,643.00 15,764.30
Tukang kayu 0.050 oh 157,643.00 7,882.15
Kepala tukang 0.005 oh 182,676.00 913.38
Mandor 0.008 oh 194,274.00 1,554.19

Jumlah Rp 74,414.02
Keuntungan 10% : Rp 7,441.40
Jumlah : Rp 81,855.42
Dibulatkan : Rp 81,900.00
I.21 1 m' Pasang talang gantung
1 Bahan 126,787.50
Talang alumunium 1.050 m' 120,750.00 126,787.50
2 Tenaga 26,114.02
Pekerja 0.100 oh 157,643.00 15,764.30
Tukang kayu 0.050 oh 157,643.00 7,882.15
Kepala tukang 0.005 oh 182,676.00 913.38
Mandor 0.008 oh 194,274.00 1,554.19

Jumlah Rp 152,901.52
Keuntungan 10% : Rp 15,290.15
Jumlah : Rp 168,191.67
Dibulatkan : Rp 168,200.00
I.22 1 m' Talang jurai atau datar zincalume

a. Bahan: 107,250.00
- Zincalume Plat L = 90 CM t=0.45mm 1.100 m1 97,500.00 107,250.00
b. Upah: 48,950.48
Pekerja 0.100 oh 157,643.00 15,764.30
Tukang 0.150 hari 157,643.00 23,646.45
Kepala tukang 0.015 oh 182,676.00 2,740.14
Mandor 0.035 hari 194,274.00 6,799.59

Jumlah Rp 156,200.48
Keuntungan 10% : Rp 15,620.05
Jumlah : Rp 171,820.53
Dibulatkan : Rp 171,800.00
#VALUE! 1 m1 Talang Vertikal Pralon D 1 1/2"

a. Bahan: -
- Pralon Ø 1 1/2" setara AW 0.2750 btg 14,650.00
- Sambungan Pelengkap (10% harga pralon) 0.1000 ls 1,465.00
- Lem PVC 0.0200 kg 84,000.00
b. Upah: -
- Tukang pipa 0.0750 hari 157,643.00
- Mandor 0.0100 hari 194,274.00

Jumlah Rp -
Keuntungan 10% : Rp -
Jumlah : Rp -
Dibulatkan : Rp -
#VALUE! 1 m1 Talang Vertikal Pralon D 2"

a. Bahan: -
- Pralon Ø 2" setara AW 0.2750 btg 19,275.00
- Sambungan Pelengkap (10% harga pralon) 0.1000 ls 1,927.50
- Lem PVC 0.0200 kg 84,000.00
b. Upah: -
- Tukang pipa 0.0750 hari 157,643.00
- Mandor 0.0100 hari 194,274.00

Jumlah Rp -
Keuntungan 10% : Rp -
Jumlah : Rp -
Dibulatkan : Rp -
#VALUE! 1 m1 Talang Vertikal Pralon D 2 1/2"

a. Bahan: -
- Pralon Ø 2 1/2" setara AW 0.2750 btg 31,750.00
- Sambungan Pelengkap (10% harga pralon) 0.1000 ls 3,175.00
- Lem PVC 0.0200 kg 84,000.00
b. Upah: -
- Tukang pipa 0.0750 hari 157,643.00
- Mandor 0.0100 hari 194,274.00

Jumlah Rp -
ANALISIS HARGA SATUAN PEKERJAAN BIDANG PEKERJAAN UMUMNOMOR : 28/PRT/M/2016
NO. URAIAN KOEF SATUAN HARGA STUAN SUB. JUMLAH JUMLAH
1 2 2 3 4 5 6
Persyaratan teknis dalam perhitungan harga satuan pekerjaan :
a. Pelaksanaan perhitungan satuan pekerjaan harus didasarkan pada gambar teknis dan rencana kerja syarat-syarat (RKS).
b. Pelaksanaan Koefisien bahan telah ditambahkan toleransi sebesar 5% - 20%, dimana didalamnya termasuk angka susut,
yang besarnya tergantung dari jenis bahan dan komposisi adukan.
c. Jam kerja efektif untuk tenaga kerja diperhitungkan 5 jam per hari.

I PENETAPAN INDEKS HARGA SATUAN PEKERJAAN PENUTUP ATAP


Keuntungan 10% : Rp -
Jumlah : Rp -
Dibulatkan : Rp -
I.23 1 m1 Talang Vertikal Pralon D 3"

a. Bahan: 12,367.50
- Pralon Ø 3" setara AW 0.2750 btg 37,500.00 10,312.50
- Sambungan Pelengkap (10% harga pralon) 0.1000 ls 3,750.00 375.00
- Lem PVC 0.0200 kg 84,000.00 1,680.00
b. Upah: 13,765.97
- Tukang pipa 0.0750 hari 157,643.00 11,823.23
- Mandor 0.0100 hari 194,274.00 1,942.74

Jumlah Rp 26,133.47
Keuntungan 10% : Rp 2,613.35
Jumlah : Rp 28,746.81
Dibulatkan : Rp 28,700.00

ANALISIS HARGA SATUAN PEKERJAAN BIDANG PEKERJAAN UMUMNOMOR : 28/PRT/M/2016


NO. URAIAN KOEF SATUAN HARGA STUAN SUB. JUMLAH JUMLAH
1 2 2 3 4 5 6
Persyaratan teknis dalam perhitungan harga satuan pekerjaan :
a. Pelaksanaan perhitungan satuan pekerjaan harus didasarkan pada gambar teknis dan rencana kerja syarat-syarat (RKS).
b. Pelaksanaan Koefisien bahan telah ditambahkan toleransi sebesar 5% - 20%, dimana didalamnya termasuk angka susut,
yang besarnya tergantung dari jenis bahan dan komposisi adukan.
c. Jam kerja efektif untuk tenaga kerja diperhitungkan 5 jam per hari.

I PENETAPAN INDEKS HARGA SATUAN PEKERJAAN PENUTUP ATAP


I.24 1 m1 Talang Vertikal Pralon d 4"

a. Bahan: 19,428.38
- Pralon Ø 4" setara AW 0.2750 btg 62,275.00 17,125.63
- Sambungan Pelengkap (10% harga pralon) 0.1000 ls 6,227.50 622.75
- Lem PVC 0.0200 kg 84,000.00 1,680.00
b. Upah: 13,765.97
- Tukang pipa 0.0750 hari 157,643.00 11,823.23
- Mandor 0.0100 hari 194,274.00 1,942.74

Jumlah Rp 33,194.34
Keuntungan 10% : Rp 3,319.43
Jumlah : Rp 36,513.77
Dibulatkan : Rp 36,500.00
#VALUE! 1 m1 Sparing Pralon d 1 1/2"

a. Bahan: -
- Pralon Ø 1 1/2" setara AW 0.0750 btg 14,650.00
- Lem PVC 0.0010 kg 84,000.00
b. Upah: -
- Tukang pipa 0.0125 hari 157,643.00
- Mandor 0.0006 hari 194,274.00

Jumlah Rp -
Keuntungan 10% : Rp -
Jumlah : Rp -
Dibulatkan : Rp -
#VALUE! 1 m1 Sparing Pralon d 2"

a. Bahan: -
- Pralon Ø 2" setara AW 0.0750 btg 19,275.00
- Lem PVC 0.0010 kg 84,000.00
b. Upah: -
- Tukang pipa 0.0125 hari 157,643.00
- Mandor 0.0006 hari 194,274.00

Jumlah Rp -
Keuntungan 10% : Rp -
Jumlah : Rp -
Dibulatkan : Rp -
#VALUE! 1 m1 Sparing Pralon d 2 1/2"

a. Bahan: -
- Pralon Ø 2 1/2" setara AW 0.0750 btg 31,750.00
- Lem PVC 0.0010 kg 84,000.00
b. Upah: -
- Tukang pipa 0.0125 hari 157,643.00
- Mandor 0.0006 hari 194,274.00

Jumlah Rp -
Keuntungan 10% : Rp -
Jumlah : Rp -
Dibulatkan : Rp -
I.25 1 m1 Sparing Pralon d 3"

a. Bahan: 2,896.50
- Pralon f 3" setara AW 0.0750 btg 37,500.00 2,812.50
- Lem PVC 0.0010 kg 84,000.00 84.00
b. Upah: 2,091.96
- Tukang pipa 0.0125 hari 157,643.00 1,970.54
- Mandor 0.0006 hari 194,274.00 121.42

Jumlah Rp 4,988.46
Keuntungan 10% : Rp 498.85
Jumlah : Rp 5,487.30
Dibulatkan : Rp 5,500.00
I.26 1 m1 Sparing Pralon d 4"

a. Bahan: 4,754.63
- Pralon f 3" setara AW 0.0750 btg 62,275.00 4,670.63
- Lem PVC 0.0010 kg 84,000.00 84.00
b. Upah: 2,091.96
- Tukang pipa 0.0125 hari 157,643.00 1,970.54
- Mandor 0.0006 hari 194,274.00 121.42

Jumlah Rp 6,846.58
Keuntungan 10% : Rp 684.66
Jumlah : Rp 7,531.24
Dibulatkan : Rp 7,500.00
ANALISIS HARGA SATUAN PEKERJAAN BIDANG PEKERJAAN UMUMNOMOR : 28/PRT/M/2016
NO. URAIAN KOEF SATUAN HARGA STUAN SUB. JUMLAH JUMLAH
1 2 2 3 4 5 6
Persyaratan teknis dalam perhitungan harga satuan pekerjaan :
a. Pelaksanaan perhitungan satuan pekerjaan harus didasarkan pada gambar teknis dan rencana kerja syarat-syarat (RKS).
b. Pelaksanaan Koefisien bahan telah ditambahkan toleransi sebesar 5% - 20%, dimana didalamnya termasuk angka susut,
yang besarnya tergantung dari jenis bahan dan komposisi adukan.
c. Jam kerja efektif untuk tenaga kerja diperhitungkan 5 jam per hari.

I PENETAPAN INDEKS HARGA SATUAN PEKERJAAN PENUTUP ATAP


I.27 1 m1 Talang Flasing jurai atau datar BJLS

a. Bahan: 49,500.00
- Flashing, seng BJLS 28 1.1000 m2 45,000.00 49,500.00
b. Upah: 30,446.04
- Tukang 0.1500 hari 157,643.00 23,646.45
- Mandor 0.0350 hari 194,274.00 6,799.59

Jumlah Rp 79,946.04
Keuntungan 10% : Rp 7,994.60
Jumlah : Rp 87,940.64
Dibulatkan : Rp 87,900.00
I.28 1 m1 Pasang Talang Flasing jurai atau datar Bitumen Casa Ex. Gutta
1 Bahan 92,800.00
Flasing Atap Bitumen Casa Ex. Gutta uk 1.050 bh 80,000.00 84,000.00
Paku Sekrup 8.000 kg 1,100.00 8,800.00
2 Tenaga 36,099.27
Pekerja 0.084 oh 157,643.00 13,242.01
Tukang kayu 0.125 oh 157,643.00 19,705.38
Kepala tukang 0.013 oh 182,676.00 2,374.79
Mandor 0.004 oh 194,274.00 777.10

Jumlah Rp 128,899.27
Keuntungan 10% : Rp 12,889.93
Jumlah : Rp 141,789.20
Dibulatkan : Rp 141,800.00

ANALISIS HARGA SATUAN PEKERJAAN BIDANG PEKERJAAN UMUMNOMOR : 28/PRT/M/2016


REKAP ANALISA
NO. URAIAN ANALISA HARGA

1 2 3

HARGA SATUAN PEKERJAAN PERSIAPAN DAN PENDAHULUAN


1 MOBILISASI PROYEK
2 PENGUKURAN DAN PEMASANGAN 1 M' BOUWPLANK -
3 PEMBERSIHAN 1 M2 LAPANGAN DAN PERATAAN -

HARGA SATUAN PEKERJAAN TANAH


1 PENGGALIAN 1 M3 TANAH BIASA SEDALAM 1 M 85,640.00
2 Pemadatan 1 m3 Tanah (Per 20 Cm) 84,200.00
3 PENGURUGAN KEMBALI 1 M3 GALIAN TANAH 84,200.00
4 PENGURUGAN 1 M3 DENGAN PASIR URUG 174,400.00
5 MEMANCANG 1 M3 ULIN 10/10 KEDALAMAN SAMPAI 2 M 250,500.00

HARGA SATUAN PEKERJAAN PONDASI


1 PEMASANGAN 1 M3 PONDASI BATU BELAH CAMPURAN 1SP : 3PP 875,100.00
2 PEMASANGAN 1 M3 PONDASI BATU BELAH CAMPURAN 1SP : 4PP 826,300.00
3 PEMASANGAN 1 M3 BATU KOSONG (ANSTAMPING) 414,000.00
4 PEKERJAAN 1 M1 BORE PILE Ø 300 MM DAN PENGECORAN 253,500.00
5 PEMOTONGAN 1 TTK TIANG PANCANG 20 X 20 , K.500 75,000.00

HARGA SATUAN PEKERJAAN BETON


1 MEMBUAT 1M3 BETON MUTU F'c =7,4 Mpa (K100), SLUMP (12 ± 2)CM, W/C=0,87 897,300.00
2 MEMBUAT 1M3 BETON MUTU f'c =9,8 Mpa (K125), SLUMP (12 ± 2)CM, W/C=0,87 974,500.00
3 MEMBUAT 1M3 BETON MUTU f'c =12,2 Mpa (K150), SLUMP (12 ± 2)CM, W/C=0,72 961,300.00
4 MEMBUAT 1M3 BETON MUTU f'c =14,5 Mpa (K175), SLUMP (12 ± 2)CM, W/C=0,66 994,600.00
5 MEMBUAT 1 m3 BETON MUTU fc 16,9 MPa 1,026,300.00
6 MEMBUAT 1M3 BETON MUTU F'c =19,3 Mpa (K225), SLUMP (12 ± 2)CM, W/C=0,58 1,050,200.00
7 MEMBUAT 1M3 BETON MUTU F'c =21,75 Mpa (K250), SLUMP (12 ± 2)CM, W/C=0,87 1,065,700.00
8 READYMIX 1M3 BETON MUTU F'c =26,4 Mpa (K300), SLUMP (12 ± 2)CM, W/C=0,52 1,100,800.00
9 READYMIX 1M3 BETON MUTU F'c =30 Mpa (K350), SLUMP (12 ± 2)CM, W/C=0,52 1,229,700.00
10 Pembesian 10 kg dengan besi polos atau ulir 8,380.00
11 PEMBESIAN 10 KG DENGAN BESI POLOS 7,600.00
12 PEMBESIAN 1 KG DENGAN BESI ULIR 7,600.00
13 PEMASANGAN 1M2 BEKESTING UNTUK PONDASI 71,905.16
14 PEMASANGAN 1M2 BEKESTING UNTUK SLOOF 223,400.00
15 PEMASANGAN 1M2 BEKESTING UNTUK KOLOM 308,100.00
16 PEMASANGAN 1M2 BEKESTING UNTUK BALOK 311,000.00
17 PEMASANGAN 1M2 BEKESTING UNTUK BALOK LATAI/RING BALK 473,100.00
18 PEMASANGAN 1M2 BEKESTING UNTUK LANTAI 418,100.00
19 Pemasangan 1 m2 bekisting untuk dinding 397,100.00
20 PEMASANGAN 1M2 BEKESTING UNTUK PLAT KANOPI 272,700.00
21 MEMBUAT 1 M' KOLOM PRAKTIS BETON BERTULANG (11X11)CM 71,100.00
22 MEMBUAT 1 M' RING BALOK BETON BERTULANG (10X15)CM 98,600.00
23 PEMASANGAN 1 M KANSTIN 60X14X30CM 239,300.00
24 PEMASANGAN 1 M KANSTIN 50X20X40CM 177,400.00
NO. URAIAN ANALISA HARGA

1 2 3

HARGA SATUAN PEKERJAAN BESI DAN ALUMINIUM


1 PEMASANGAN 1 KG BESI PROFIL 32,600.00
2 Pekerjaan Angkur Ø 16 mm -
3 PEMASANGAN 1 KG BESI PLAT BAJA 32,600.00
4 PEMASANGAN 1 KG BESI SIKU 881,800.00
5 PEMASANGAN 1M' TANGGA PIPA GALVANIS -
6 PEKERJAAN 1 M' RELING TANGGA -
7 MEMBUAT 1 M2 RANGKA BESI SCUARE TUBE (BESI KOTAK) -
8 PEKERJAAN PENGELASAN 1 CM DENGA MENGGUNAKAN LAS LISTRIK 70,800.00
9 PEMASANGAN 1 M' KUSEN ALUMINIUM 150,500.00
10 PEMASANGAN 1 M' FRAME PINTU / JENDELA ALUMINIUM 337,600.00
11 PEMASANGAN 1 M' GRILL BESI Ø 16 Lbr = 30 cm -
12 Pemasangan 1 m2 rangka besi hollow 1x40.40.2mm, modul 60 x 60 cm, plafond -
13 Pemasangan 1 m2 ACP + Rangak Besi Hollow 50x50x5 mm -
14 PEMASANGAN 1 M2 RANGKA BESI HOLLOW 40X40X2MM, MODUL 60 X120 CM DINDING PARTISI -

HARGA SATUAN PEKERJAAN PASANGAN DINDING


1 PEMASANGAN 1M2 DINDING BATA MERAH (5X11X22) CM TEBAL 1 BATU CAMPURAN 1SP : 2PP 310,000.00
2 PEMASANGAN 1M2 DINDING BATA MERAH (5X11X22) CM TEBAL 1 BATU CAMPURAN 1SP : 4PP 288,600.00
3 PEMASANGAN 1M2 DINDING BATA MERAH (5X11X22) CM TEBAL 1/2 BATU CAMPURAN 1SP : 2PP 151,100.00
4 PEMASANGAN 1 M2 DINDING BATA RINGAN HB20 CAMPURAN 1SM : 4PP 371,000.00
5 PEMASANGAN 1 M2 SUNSCREEN ALUMUNIUM 1,118,800.00

HARGA SATUAN PEKERJAAN PLESTERAN


1 PEMASANGAN 1M2 PLESTERAN 1SP : 1PP TEBAL 15 MM 100,300.00
2 PEMASANGAN 1M2 PLESTERAN 1SP : 2PP TEBAL 15 MM 93,600.00
3 PEMASANGAN 1 M2 PLESTERAN 1SP : 4PP TEBAL 15MM. 88,700.00
4 PEMASANGAN 1M2 PLESTERAN BATA RINGAN TEBAL 1CM -
5 Pemasangan plesteran teraso 1PC:2 teraso tebal 10 mm 171,700.00
6 PEKERJAAN 1 M2 ACIAN DINDING 56,300.00
7 PEKERJAAN 1 M2 ACIAN DINDING PAS. BATA RINGAN -

HARGA SATUAN PEKERJAAN PENUTUP LANTAI DAN PENUTUP DINDING


1 Pemasangan 1 m’ plint keramik ukuran 10cm x 40cm 44,400.00
2 Pemasangan 1 m2 lantai keramik ukuran 40cm x 40cm 307,700.00
3 Pemasangan 1 m2 lantai keramik ukuran 20cm x 20cm 270,400.00
4 PEMASANGAN 1M2 LANTAI KERAMIK UKURAN 60CM X 60CM 411,800.00
5 PEMASANGAN 1M2 LANTAI KERAMIK UKURAN 30CM X 30CM 282,100.00
6 PEMASANGAN 1 M2 LANTAI GUIDING BLOCK UKURAN 30CM X 30 CM 427,000.00
7 PEMASANGAN 1 M1 LANTAI GRANIT TILE STEP TANGGA UKURAN 60 CM X 30 CM 341,200.00
8 PEMASANGAN 1 M1 STOP NUSING PLINT KERAMIK UKURAN 10CM X 40 CM 117,100.00
9 PEMASANGAN 1 M2 DINDING KERAMIK 20CM X 25CM 343,600.00
10 Pemasangan 1 m2 Dinding Keramik 20cm X 45cm 412,320.00
11 PEMASANGAN 1M2 DINDING BATU ANDESIT BAKAR 353,900.00
12 Pemasangan 1 m2 lantai vynil ukuran 30cm x 30cm 204,500.00
13 Pemasangan 1 m2 keramik tangga ukuran 30cm x 30cm 288,300.00

SATUAN PEKERJAAN LANGIT-LANGIT (PLAFOND)


1 PEMASANGAN 1 M2 LANGIT-LANGIT GYPSUM BOARD UKURAN (120X240X9) MM, TEBAL 9 MM 323,600.00
2 PEMASANGAN 1 M' LANGIT-LANGIT LIST KAYU PROFIL 58,600.00
3 PEMASANGAN 1 M' LANGIT - LANGIT LIST GYPSUM 32,600.00
4 PEMASANGAN 1 M2 LANGIT-LANGIT CALSI BOARD UKURAN (120X240X9) MM, TEBAL 3,5 MM 47,800.00
5 PEMASANGAN 1 M2 RANGKA BESI HOLLOW 1x40.40.2MM, MODUL 60x60cm, PLAFOND 280,000.00

SATUAN PEKERJAAN PENUTUP ATAP


1 PEMASANGAN 1 M' BUBUNG STEL GELOMBANG 0.92 M -
2 PEMASANGAN 1 M2 GENTENG METAL -
3 PEKERJAAN 1 M2 ATAP SENG GELOMBANG (SETARA DENGAN SPANDEK) -
4 PEKERJAAN 1 m2 RANGKA ATAP BAJA RINGAN -
5 PEKERJAAN 1 m2 RANGKA ATAP BAJA KOTAK -
NO. URAIAN ANALISA HARGA

1 2 3

PEKERJAAN PINTU DAN JENDELA ALUMUNIUM


1 PEMASANGAN 1 M' KUSEN ALUMUNIUM -
2 PEMASANGAN 1 M' FRAME PINTU / JENDELA ALUMINIUM -
3 PEMASANGAN 1 M2 PINTU ALUMINIUM SPANDRILL -
4 PEMASANGAN 1 M2 PINTU ALUMINIUM -
5 PEMASANGAN 1 M2 PINTU PANEL -
6 PEMASANGAN 1 M2 PINTU PANEL ALUMUNIUM -
7 PEMASANGAN 1 M2 KACA TEBAL 5 mm -
8 PEMASANGAN 1 M2 KACA TEBAL 5 mm RAYBAND -
9 PEMASANGAN 1 M2 KACA TEBAL 8 mm -
10 PEMASANGAN 1M2 KACA TEMPRED TEBAL 12 mm -
11 PEMASANGAN 1 BH FLOOR HINGE -
12 PEMASANGAN 1 BH ENGSEL PINTU -
13 PEMASANGAN 1 BH ENGSEL TANAM -
14 PEMASANGAN 1 BH ENGSEL JENDELA -
15 PEMASANGAN 1 BH ESPAGNOLLEETE TANAM -
16 PEMASANGAN 1 BH DOOR CLOSER -
17 PEMASANGAN 1 BH GRENDEL JENDELA -
18 PEMASANGAN 1 BH HAK ANGIN -
19 PEMASANGAN 1 BH HENDEL JENDELA -
20 PEMASANGAN 1 BH KUNCI PINTU -
21 PEMASANGAN 1 BH PATCH FITTING -
22 PEMASANGAN 1 BH PULL HANDLE -
23 PEMASANGAN 1 BH BOTTOM PIVOT PATCH -
24 PEMASANGAN 1 BH TOP PIVOT PATCH -
25 PEMASANGAN 1 BUAH ENGSEL PINTU + AKSESORIS -
26 PEMASANGAN 1 BUAH KUNCI SILINDER -
27
HARGA SATUAN PEKERJAAN KAYU
1 PEMBUATAN 1 M2 PINTU PLYWOOD RANGKAP, RANGKA EXPOSE KAYU KELAS I ATAU II -

PEKERJAAN KACA
1 PEMASANGAN 1 M2 KACA CERMIN TEBAL 5 MM -

PEKERJAAN PENGECATAN
1 1 M2 PENGECATAN BIDANG KAYU BARU (1 LAPIS PLAMUR, 1 LAPIS CAT DASAR, 2 LAPIS CAT PENUTUP) -
2 PENGECATAN 1 M2 TEMBOK BARU INTERIOR ( 1 LAPIS PLAMIR, 1 LAPIS CAT DASAR, 2 LAPIS CAT PENUTUP) -
3 PENGECATAN 1 M2 TEMBOK BARU EXTERIOR ( 1LAPIS PLAMUUR, 1 LAPIS CAT DASAR, 2 LAPIS CATPENUTUP) -
4 PENGECATAN 1 M2 PLAFOND -
5 Pengecatan 1 m2 permukaan baja galvanis secara manual sistem 1 lapis cat mutakhir -
6 PEKERJAAN 1 M2 WATERPROOFING -
7 PELABURAN 1 M2 BIDANG KAYU DENGAN VERNIS -

HARGA SATUAN PEKERJAAN SANITASI DALAM GEDUNG


1 PEMASANGAN 1 BUAH KLOSET DUDUK -
2 PEMASANGAN 1 BUAH KLOSET JONGKOK -
3 PEMASANGAN 1 BUAH URINOIR -
4 PEMASANGAN 1 BUAH PARTISI URINOIR -
5 PEMASANGAN 1 BUAH WASTAFEL -
6 PEMASANGAN 2 BUAH WASTAFEL -
7 Pemasangan 1 buah bak kontrol pasangan bata 30x30 tinggi 35 cm -
8 Pemasangan 1 buah bak kontrol pasangan bata 45cm x45cm tinggi 50 cm -
9 PEMASANGAN 1 BUAH BAK FIBREGLASS VOL 1 M3 -
10 PEMASANGAN 1 BUAH BAK CUCI PIRING STAINLESSSTEEL -
NO. URAIAN ANALISA HARGA

1 2 3

11 PEMASANGAN 1 BUAH FLOOR DRAIN -


12 PEMASANGAN 1 BUAH ROOF DRAIN -
13 PEMASANGAN 1 BUAH KRAN AIR 1/2" ATAU 3/4" -
14 PEMASANGAN 1 BUAH KRAN AIR JET WASHER -
15 PEMASANGAN 1 M’ PIPA PVC TIPE AW DIAMETER 3/4” -
16 PEMASANGAN 1 M’ PIPA PVC TIPE AW DIAMETER 1” -
17 PEMASANGAN 1 M’ PIPA PVC TIPE AW DIAMETER 1.5” -
18 PEMASANGAN 1 M’ PIPA PVC TIPE AW DIAMETER 2” -
19 PEMASANGAN 1 M’ PIPA PVC TIPE AW DIAMETER 4” -
20 PEMASANGAN 1 BH BIOSEPTIC TANK -
21 PEMASANGAN TANGKI AIR ROOF TANK -

HARGA SATUAN PEKERJAAN PEMASANGAN PIPA


1 PEMASANGAN 1 M PIPA STAINLESS STEEL Ø 1,5" -
2 PEMASANGAN 1 M PIPA STAINLESS STEEL Ø 2" -
3 PEMASANGAN 1 M PIPA STAINLESS STEEL Ø 2,5" -

PEKERJAAAN MEKANIKAL
1 Pipa uPVC class AW ø 3/4" -
2 Pipa uPVC class AW ø 1" -
3 Pipa uPVC class AW ø 1,5" -
4 Pipa uPVC class AW ø 2" -
5 Pipa uPVC class AW ø 4" -
6 Pipa uPVC class AW ø 6" -
7 Pipa Baja Galvanis mediun class Gate valve, JIS 10K ø 25 mm -
8 Floor Clean out ø 80 mm -
9 Floor Clean out ø 100 mm -
10 Tangki Air Fiberglass -
11 Pompa Transfer kap. 350ltr/mnt, head 40mtr -
12 POMPA BOOSTER (PACKAGE BOOSTER PUMP) -
13 Pompa Air Transper 50 liter/menit -
14 Pompa Transper 8 m3/Jam -
15 Exhaust Fan : 200 CMH -
16 AC wall mounted, single split system : 4.500 BTUH -
17 AC wall mounted, single split system : 9.000 BTUH -
18 AC wall mounted, single split system : 18.000 BTUH -
19 AC wall mounted, single split system : 24.000 BTUH -
20 Refrigerant AC wall mounted, single split system : 4. 500 BTUH -
21 Refrigerant AC wall mounted, single split system : 9. 000 BTUH -
22 Refrigerant AC wall mounted, single split system : 18. 000 BTUH -
23 Refrigerant AC wall mounted, single split system : 24. 000 BTUH -
24 Drain/kondensat AC ø 20 mm -
25 Portable fire extinguisher karbon dioksida agent (CO.2.0.) : 2 kg -
26 Portable fire extinguisher karbon dioksida agent (CO.2.0.) : 3 kg -
27 Kabel NYM : 3 x 2,5 mm2 -
28 Instalasi Detektor/titik -

PEKERJAAAN ELEKTRIKAL
1 PEMASANGAN/INSTALASI KABEL 4 x 4 mm² -
2 PEMASANGAN/INSTALASI KABEL 4 x 6 mm² -
3 PEMASANGAN/INSTALASI KABEL 4 x 16 mm² -
4 PEMASANGAN/INSTALASI KABEL 4 x 70 mm² -
5 PEMASANGAN/INSTALASI KABEL NYFGbY 4 x 50 mm² -
6 PEMASANGAN/INSTALASI KABEL NYFGbY 4 x 95 mm² -
7 PEMASANGAN/ INSTALASI KABEL DATA HDMI -
NO. URAIAN ANALISA HARGA

1 2 3

8 ELEKTRODA PEMBUMIAN -
9 PANEL PUTR (Box uk. 1.800 x 600 x 400 mm ) + Komponen -
10 PANEL P-1 (Box Panel ukuran 800 x 600 x 250 mm) + Komponen -
11 PANEL P - 3 (Box Panel ukuran 800 x 600 x 250 mm) + Komponen -
12 PANEL PAC - 1 ( Box Panel ukuran 700 x 500 x 250 mm) + Komponen -
13 LAMPU RM 300 LED 2 x 10 WATT MIRROR LOUVERE -
14 LAMPU RM 300 Led 2 x 18 Wat Mirror Louvere -
15 LAMPU RM 300 Led 2 x 36 Wat Mirror Reflector -
16 LAMPU RM 300 Led 2 x 36 Watt Open Type/TKI -
17 LAMPU RM DOWN LIGHT 13 Wat -
18 LAMPU RM DOWN LIGHT 18 Wat -
19 LAMPU GMS T 8 ACR-SCR 1 X 18 Wat -
20 LAMPU DOWN LIGHT RD 125 E27 Led 1 x 3 Watt -
21 LAMPU GMS GMS TP LED 1 x 10 WATT ACRYLIC COVER -
22 LAMPU GMS GMS TP LED 1 x 18 WATT ACRYLIC COVER -
23 LAMPU KELUAR/EXIT, TL -D 1x10 W -
24 SAKLAR TUNGGAL, 10 A, 250 VAC -
25 SAKLAR GANDA, 10 A, 250 VAC -
26 SAKLAR CELING, 15 A, 250 VAC -
27 INSTALASI PENERANGAN KABEL DALAM PIPA KONDUCIT uPVC -
28 KONTAK - KONTAK BIASA 1 FASE, 15 A, 250 VAC -
29 KABEL TRAY 200 x 100 -
30 KABEL TELPON ITC (STELL-K011) 30 x 2 x 0,6 mm² -
31 INSTALASI LAN UTP cat 6 -
32 OUTLET DATA Rj 45 DINDING 2 GANG -
33 OUTLET DATA Rj 45 LANTAI 2 GANG -
34 SWITCH HUB 24 porth -
35 WALL MOUNT RACK -
36 SERVER : Xeon dual core. Ram 1Gb. 250 Gb SS Sata -
37 MAIN SWITCH ROUTER & FIRE WALL -
38 TIANG PENGGANTUNG LCD -
118

DAFTAR HARGA SATUAN UPAH DAN BAHAN


KOTA BOGOR
TAHUN ANGGARAN 2019

UPAH
NO KEAHLIAN SAT
Rp.
I. PEKERJA.
1 Tenaga/ Pekerja 137,242 /Org/Hr
2 Tukang Aspal 166,063 /Org/Hr
3 Tukang Batu 166,063 /Org/Hr
4 Tukang Besi 166,063 /Org/Hr
5 Tukang Cat 166,063 /Org/Hr
6 Tukang Gypsum 166,063 /Org/Hr
7 Tukang Kayu 166,063 /Org/Hr
8 Tukang Las 166,063 /Org/Hr
9 Tukang Listrik 166,063 /Org/Hr
10 Tukang Taman 166,063 /Org/Hr
11 Tukang Cat Melamik 166,063 /Org/Hr
12 Tukang Pipa 166,063 /Org/Hr
13 Tukang Aluminium 166,063 /Org/Hr
14 Kepala Tukang 157,829 /Org/Hr
15 Operator 166,063 /Org/Hr
16 Mandor 157,829 /Org/Hr

HARGA SATUAN UPAH DAN BAHAN138


119

II. BAHAN.
HARGA
NO JENIS MATERIAL SAT
Rp.
A BAHAN DASAR
1 Pasir Beton 108,584 m3
2 Pasir Pasang 91,694 m3
3 Pasir Urug 96,520 m3
4 Batu Belah / Batu Kali / Batu Gunung 125,475 m3
5 Batu Split 1x2 130,301 m3
6 Batu Split 2x3 130,301 m3
7 Batu lime stone 91,694 m3
8 Sirtu (Pasir Batu) 91,694 m3
9 Tanah Urug setempat 96,520 m3
10 Tanah Subur 33,782 m3
11 Tanah Urug pilihan - Material Jalan 96,520 m3
12 Bata Merah bakar Kelas 1 700 bh
13 Batako 2,600 bh
14 Hollow Block 20 12,500 bh
15 Beton ringan ( Celcon block ) 10,241 Bh
16 Roaster Kembang biasa uk. 22x220x15 cm 12,500 bh
17 Roaster beton uk. 12x30x15 cm 18,100 bh
18 Terawang Beton Grc Cetak Ornamen Betawi 238,588 m2
19 Glass block Lokal 20 x 20 cm ex. Mulya 30,300 bh
20 Semen PC type I @ 50 kg Tiga Roda 61,000 Zak
21 Semen putih @50 kg Tiga Roda 116,000 Zak
22 Semen Mortar Instant ( MU -100) 65,000 kg
23 Semen Warna untuk nat kemasan plastik 6,500 kg
24 Semen Grouting 4,584,678 m3
25 Sement / mortal ( MU -300) 1,425 kg
26 Sement / mortal ( MU -200) 4,450 kg
27 Air 1,000 liter
27 Semen PC type I @ 1 kg Tiga Roda 1,300 kg

B BETON
B.1 BETON READY MIX
1 Readymix Mutu Beton K-175 450,063 m3
2 Readymix Mutu Beton K-225 461,450 m3
3 Readymix Mutu Beton K-250 472,837 m3
4 Readymix Mutu Beton K-300 492,900 m3
6 Sewa pompa beton 256,048 jam
7 Sewa vibrator 100,857 jam

B.3 PRECAST AND PRESTRESS CONCRETE


1 Pagar beton ex. Beton
- Panel 240.40.5 155,900 lbr
Kolom ( H-BEAM )
- 260 248,600 bt
- 300 286,000 bt
- 340 382,800 bt
- 360 404,800 bt
- 380 427,900 bt
- 420 483,000 bt
1 Kansteen ex. Beton
- K.03.1 ( 15.18.40 ) 35,000 bh
- K.03.2 ( 15.18.20 ) 40,000 bh
- K.03.3 ( 15.18.40 ) 42,500 bh
- K.04.1 ( 15.28.60 ) 65,000 bh
- K.04.2 ( 15.28.20 ) 19,140 bh
- K.04.3 ( 15.28.60 ) 47,740 bh

C BAHAN BESI
1 Besi beton polos 4,880 kg
2 Besi beton ulir 4,880 kg
3 Kawat beton 13,014 kg
4 Paku rata-rata 12,472 kg
5 Sekruf 12,201 kg
6 Paku hak panjang / paku kait 12,201 kg
7 Skruf gyp 12,201 kg
8 Skruf plafond 12,201 kg
9 Drywall Screw 25mmX083 250 bh
10 Skrup Fixer 1,200 bh
11 Skrup atap bitumen 1,100 bh
11 WM - M5-150 2,1 x 5,4 m 26,000 m2
12 WM - M6-150 2,1 x 5,4 m 36,000 m2
13 WM - M8-150 2,1 x 5,4 m 48,000 m2
14 WM - M9-150 2,1 x 5,4 m 66,000 m2
15 WM - M10-150 2,1 x 5,4 m 110,000 m2
16 Skruf + fiser untuk kusen alumunium 3,500 bh
17 Baja HB & IWF 9,500 kg
18 Siku 9,500 kg
19 Jenis CNP 9,500 kg
20 Jenis UNP 9,500 kg
21 Jenis Lips Canal 9,500 kg
22 Jenis plat ukuran 4' x 8' berlaku untuk semua ketebalan 9,500 kg
23 Besi hollow kotak 40/40 mm t.1,6mm pj=6m 87,844 btg
24 Besi kotak hollow 40/20 mm t.1,6mm pj=6m 66,696 btg
25 Besi hollow kotak 20/80 mm t.1,6mm pj=6m 104,111 btg
26 Besi kotak 20/20 mm (untuk rangka plafond) pj=4m 43,000 btg

HARGA SATUAN UPAH DAN BAHAN138


120

II. BAHAN.
HARGA
NO JENIS MATERIAL SAT
Rp.
27 Besi kotak 20/40 mm (untuk rangka plafond) pj=4m 66,696 btg
28 Besi kotak 40/40 mm (untuk rangka plafond) pj=6m 87,844 btg
29 Besi hollow kotak 40/60 mm t.1,6mm pj=6m 78,625 btg
30 Besi hollow galvanis 40/40 mm t= 0.35mm 73,203 btg
31 Besi hollow galvanis 20/40 mm t= 0.35mm 110,000 btg
32 Besi Strips 10,500 kg
33 Kawat las 85,000 kg
33 Angker dia 8 9,000 bh
34 Angker dia 12 13,920 bh
35 Angker dia 16 18,120 bh
36 Angker dia 19 21,889 bh
37 Angker dia 20 23,150 bh
38 Angker dia 22 A 327 25,465 bh
39 Angker dia 32 37,040 bh
40 Baut HTB M12 - panjang 60 mm 2,557 bh
41 Baut HTB M16 - panjang 60 mm 4,759 bh
42 Baut HTB M20 - panjang 60 mm 8,457 bh
43 Baut HTB M22 - panjang 70 mm 14,330 bh
44 Baut HTB M25 - panjang 70 mm 22,400 bh
44 Baut HTB M27 - panjang 70 mm 32,872 bh
45 Walter mur 16 42,000 bh
46 Kawat harmonika 29,000 m2
47 Kawat nyamuk 21,000 m2
48 Kawat kassa 21,400 m2
49 Kawat duri 1,580 m'
50 Kawat bronjong 27,000 m2
50 Jaring pengaman plastik 6,500 bh
51 Plat Boundex 0.75 mm 125,000 m2
52 Turnbuckle M-16 45,000 bh
-
D TIANG PANCANG - K 500 -
1 Tiang Pancang 20x20 P. 6 ( Single joint) 170,000 m1
2 Tiang pancang 20x20 P. 6 ( Double joint) 250,000 m1
3 Tiang pancang30x30 P. 6 ( Double joint) 315,000 m1
4 Joint plate 25x25 ( Sudah termasuk pada tiang pancang ) - joint
5 Mob/Demob tiang pancang -
- Crane pancang + Hidrolik hammer 7 Ton ( 1 unit ) 35,000,000
- Crane service 5,000,000
6 Biaya lain - lain untuk pemancangan : - LS
- Keamanan alat 10,000,000 LS
- Perlengkapan safety 5,000,000 LS
- Akomodasi & transfortasi Crew 10,000,000 LS
- Asuransi Jamsostek 1,000,000 LS
11 Biaya pemotongan tiang pancang tiang pancang 45x45cm - joint
12 Biaya pemotongan tiang pancang tiang pancang 20x20cm 75,000 joint
13 Biaya pemotongan tiang pancang tiang pancang spun pile Ø 50 cm 115,000 joint
14 Biaya penyambungan tiang pancang 45x45cm ( Las AWS E6013 ) 165,000 joint
15 Biaya penyambungan tiang pancang 20x20cm ( Las AWS E6013 ) 110,000 joint
16 Biaya pemancangan tiang pancang 45x45cm 85,000 m1
17 Biaya pemancangan tiang pancang 20x20cm 70,000 m1
18 Biaya pemancangan tiang pancang spun pile Ø 50 cm - m1
19 Handling tiang pancang 15,000 m1

D KAYU
1 Kayu Kelas I, (Kayu Kamper dan sejenisnya) :
- Jenis Papan 2,980,523 m3
- Jenis Balok 4,639,694 m3
2 Kayu Kelas II, (Kayu Meranti dan sejenisnya)
- Jenis Papan 2,524,469 m3
- Jenis Balok 2,094,474 m3
3 Kayu Kelas III (Borneo dan sejenisnya)
- Jenis Papan 2,094,474 m3
- Jenis Balok 1,718,530 m3
- Kayu lokal kelas III 1,689,092 m3
4 Kayu lokal kelas IV (Kayu Albasia dan sejenisnya)
- Jenis Papan 1,557,825 m3
- Jenis Balok 1,450,206 m3
- Kayu lokal kelas III 1,689,092 m3
5 Dolken Ø 8-10cm panjang 4m - 5m 25,000 bt
6 Multiplek 18 mm phenolic 2 muka - lbr
7 Multiplek 18 mm - lbr
8 Multiplek 15 mm - lbr
9 Multiplek 12 mm phenolic 2 muka 122,600 lbr
6 Multiplek 12 mm 151,500 lbr
7 Multiplek 9 mm 122,600 lbr
8 Multiplek 6 mm 87,600 lbr
9 Multiplek 4 mm 69,100 lbr
10 Multiplek 3 mm 58,800 lbr
11 Teak wood ukuran normal ( Jati ) 3mm 91,600 lbr
12 Teak wood ukuran normal ( Jati ) 4mm 119,900 lbr
13 Formika uk. Besar 120 x 240 warna putih 200,000 lbr
14 Formika uk. Besar 120 x 240 warna 230,000 lbr
15 Melaminto uk. 120 x 240 ( Triplek lapis ) 150,000 lbr
16 Profil kayu jati Jabar 35,000 m1

HARGA SATUAN UPAH DAN BAHAN138


121

II. BAHAN.
HARGA
NO JENIS MATERIAL SAT
Rp.
E BAHAN LANGIT - LANGIT
1 Silicate uk. 120 x 240 t=4mm ex. GRC 53,953 lbr
2 Silicate uk. 120 x 240 t=6mm ex. GRC 54,767 lbr
3 Gypsum water prof 2.4 x 1.2 t= 9 mm 127,427 lbr
4 Gypsum 2.4 x 1.2 t= 9 mm DN setara Jayaboard 46,091 lbr
5 Gypsum 2.4 x 1.2 t= 12 mm 65,069 lbr
6 List Gypsum T. 8 - 10 cm 10,000 m1
7 List Plafond Gypsum T, 5 - 7 cm 9,000 m1
8 Tepung Gypsum @ 20 kg 71,600 zak
9 Plafond Akustik 67,000 lbr
10 Textile tape 39,600 roll
11 Kalsiplank uk. 8 x 300 x 3000 setara ex. Kalsiboard 75,000 lbr
12 Rangka Metal BMSys ( untuk partisi gyfsum )
- Wall Track 41,300 pc(s)
- Wall Stud 45,800 pc(s)
- Jointing Compound UB-10/20/888/CCL 20kg/bag(s) 71,600 bag(s)
- UB Tape 75m/roll(s) 39,600 roll(s)
- Drywall Screw 25mmX083 500 pc(s)
- Jaya Sealant 580ml 20,000 pc(s)

F BAHAN FINISHING LANTAI & DINDING


F.1 Keramik & Granit ex. Roman
1 Keramik lantai 20 x 20 type Polised setara DN 57,600 m2
2 Keramik lantai 30 x 30 Brand impresso KW1 relief batu 6,000 BH
3 Keramik lantai 20 x 20 type Polised setara Roman Gol. B 72,661 m2
4 Keramik lantai 20 x 20 type Unpolised setara Roman Gol. B 66,154 m2
5 Keramik lantai 25 x 25 type Polised setara Roman Gol. B 67,509 m2
6 Keramik lantai 25 x 25 type Unpolised setara Roman Gol. B 124,500 m2
7 Keramik lantai 30 x 30 type Polised Setara DN 62,000 m2
8 Keramik lantai 30 x 30 type Unpolised Setara DN 67,400 m2
9 Keramik lantai 30 x 30 type Polised Setara Roman Gol. C 91,802 m2
10 Keramik lantai 30 x 60 type Unpolised Setara Roman Gol. C 64,527 m2
9 Keramik lantai 40 x 40 type Polised Setara DN 86,400 m2
10 Keramik lantai 40 x 40 type Unpolised Setara DN 87,200 m2
11 Keramik lantai 40 x 40 type Polised Setara Roman Gol. B 71,197 m2
12 Keramik lantai 40 x 40 type Unpolised Setara Roman Gol. B 76,511 m2
12 Keramik lantai 60 x 60 type Homogeneus Tile 108,449 m2
13 Keramik lantai 60 x 60 type Polised Setara Roman Gol. B 123,035 m2
14 Keramik lantai 60 x 60 type Polised Setara Roman Gol. C 139,574 m2
15 Keramik lantai 60 x 60 type Unpolised Setara Roman Gol. B 109,533 m2
16 Keramik Dinding 20 x 20 Polised setara DN 67,500 m2
17 Keramik Dinding 20 x 20 Unpolised setara DN 62,300 m2
18 Keramik Dinding 20 x 20 Polised setara Roman Gol. B 134,900 m2
19 Keramik Dinding 20 x 20 Unpolised setara Roman Gol. B 66,479 m2
20 Keramik Dinding 20 x 25 Polised setara DN 68,400 m2
21 Keramik Dinding 20 x 25 Unpolised setara DN 68,400 m2
22 Keramik Dinding 20 x 25 Polised setara Roman. Gol B 115,400 m2
23 Keramik Dinding 20 x 25 Unpolised setara Roman Gol. B 122,600 m2
24 Pasang Dinding Keramik Ukuran (30 x 60) cm Roman Blink Wall White W.632 20,000 BH
25 Keramik dinding 20 x 40 Unpolised setara Roman Gol. B 122,600 m2
26 Keramik dinding 30 x 30 Polised setara DN 72,000 m2
27 Keramik dinding 30 x 30 Unpolised setara DN 67,400 m2
28 Keramik dinding 30 x 30 Polised setara Roman Gol. C 91,802 m2
29 Keramik dinding 30 x 30 Unpolised setara Roman Gol. C 91,802 m2
30 Plint keramik 10 x 30 cm polised setara lantai 3,250 bh
31 Plint keramik 10 x 40 cm polised setara lantai 3,600 bh
32 Plint keramik 10 x 60 cm polised setara lantai 6,500 bh
33 Stair nozing krmk 10 x 30 unpolised 21,000 bh
34 Stair nozing krmk 10 x 20 unpolised 12,500 bh

HARGA SATUAN UPAH DAN BAHAN138


122

II. BAHAN.
HARGA
NO JENIS MATERIAL SAT
Rp.
F.2 Granit ex.
1 Homogeneus 30 x 30 type Polised Setara Niro granit 247,000 m2
2 Homogeneus 40 x 40 type Polised Setara Niro granit 338,200 m2
3 Homogeneus 40 x 40 type Unpolised Setara Niro granit 257,600 m2
4 Homogeneus 60 x 60 type Polised Setara Niro granit 487,600 m2
5 Homogeneus 60 x 60 type Unpolised Setara Niro granit 391,200 m2
6 Homogeneus tile 60 x 60 type Polised Ex. Valentino gress super white 150,000 m2
7 Homogeneus 60 x 60 type polised Setara Garuda 103,900 m2
8 Plint Homogeneus 10 x 30 cm polised Setara lantai 25,000 bh
9 Plint Homogeneus 10 x 40 cm polised setara lantai 29,100 bh
10 Plint Homogeneus 10 x 60 cm polised setara lantai 30,000 bh
11 Stair nozing Homogeneus 10 x 30 unpolised 25,000 bh
12 Stair nozing Homogeneus 10 x 40 unpolised 30,000 bh
13 Stair nozing Homogeneus 10 x 20 unpolised 17,000 bh
14 Stair nozing Homogeneus 6 x 20 unpolised 15,000 bh

F.3 Marmer, Garnit & batu alam berikut material jalan


1 Marmer 40 x 40 type Polised Setara ex. Ujung Pandang 150,000 m2
2 Marmer 60 x 60 type Polised Setara ex. Ujung Pandang 180,000 m2
3 Marmer Solid type Polised Setara ex. Ujung Pandang 1,500,000 m2
4 Granit macam-macam corak setara Cina 169,000 m2
5 Granit macam-macam corak setara Italia 189,000 m2
6 batu Teraso 2,500 kg
1 Batu andesit bakar macam ukuran 126,343 m2
2 Batu sikat 13,556 kg
3 Batu paras 144,400 m2
4 Batu candi 159,420 m2
F.4 Parquit,viny, karpet & Epoxy
1 Lem Vinyl 55,000 kg
2 Wall Paper 25,000 m2
3 Lapisan HPL 145,000 m2
1 Epoxy floor lining 2000um ( 2mm ) --- terpasang 150,000 m2
Material : Dongyang Epoxy Primer EP 118, Dongyang Scraping Material,
Dongyang Epoxy finish ET 5635 - Selfleveling type. 82,000
2 Epoxy floor lining 3000 um ( 3mm ) --- terpasang 220,000 m2
Material : Dongyang Epoxy Primer EP 118, Dongyang Scraping Material,
Dongyang Epoxy finish ET 5635 - Selfleveling type. 82,000
F.5 Paving block
1 Paving block press 6 cm natural 3,500 bh
2 Paving block press 6 cm warna 3,200 bh
3 Paving block press 8 cm natural 4,500 bh
4 Paving block press 8 cm warna 4,700 bh
5 Grassblock 30x45 6 cm 9,500 bh
6 Grassblock 30x45 8 cm 11,500 bh

G BAHAN PENUTUP ATAP


1 Genteng Morando natural 2,900 bh
2 Genteng Morando Glazur 5,000 bh
3 Bubung Morando Natural 9,000 bh
4 Bubung Morando Glazur 9,000 bh
5 Genteng samping penutup lisplang morando 13,400 bh
6 Genteng palentong biasa 2,000 bh
7 Bubungan Palentong biasa 8,500 bh
8 Genteng Palentong Ex Jatiwangi glazur 6,700 bh
9 Bubungan Genteng Jatiwangi Glazur 12,300 bh
10 Genteng Keramik Glazur standar Setara kanmuri 10,200 bh
11 Bubungan Genteng Glazur setara Kanmuri 17,200 bh
12 Genteng beton setara cisangkan 15,500 bh
13 Bubungan Genteng Beton 19,400 bh
14 Genteng Bitumen Casa, tebal 3mm 30,000 lbr
15 Nok Atap Bitumen Casa, tebal 3mm 50,000 lbr
16 Flasing Atap Bitumen Casa 80,000 lbr
17 Atap metal berpasir (harga terpasang) 90,500 m2
18 Bubungan Atap Metal Berpasir (harga terpasang) 35,000 m1
19 Seng gelombang 3" x 6" bjls 28 45,000 lbr
20 Nok seng Seng plat 3" x 6" bjls 28 48,000 lbr
21 Atap alumunium gelombang tebal 0,55 45,000 m2
22 Nok strandar 40 cm 18, swg 22 alumunium 63,940 m1
23 Talang alumunium 120,750 m1
24 Expanded metal besi 1015 135,000 m1

HARGA SATUAN UPAH DAN BAHAN138


123

II. BAHAN.
HARGA
NO JENIS MATERIAL SAT
Rp.
25 Zincalume Hi- Tensile G 550 Union :
- Zinc - Allumunium Union Clip Panel 121,840 m2
- Prepainted Zinc - Allumunium Union 156,492 m2
- Zincalume Plat L = 90 CM t=0.45mm 97,500 m1
- Union Pesona TCT 0.45mm lebar 990mm Colorbond 133,110 m2
- Nok Standar untuk sudut atap curam 52,538 m1
- Nok Standar untuk sudut atap kurang dari 5⁰ 52,538 m1
26 Alumunium foil Setara Primary Smart - Foam 5 mm 46,000 m2
27 Polycarbonat t 6 mm setara twinlate/Impralon 107,400 m2
28 Rangka atap baja ringan ( Harga terpasang ) 165,000 m2
29 Alumunium Composite Panel forporated ex Alucomp type 03 326,700 m2
30 Alumunium Composite Panel ex Alucomp type 03 267,300 m2
31 Rangka alumunium hollow 33x38x1mm, MF, bracket besi hollow 40x40x4
zincromate + silicone sealant dan accessories 250,000 m2

H ALLUMUNIUM & KACA


1 Bahan kusen Alluminium ex. Alexindo 4 " ( warna / coklat, hitam ) 55,309 m1
2 Bahan kusen Alluminium ex. Alexindo 4 " ( silver / natural ) 107,000 m1
3 Bahan kusen Alluminium ex. Alexindo 3 " ( silver / natural ) 93,000 m1
4 Bahan kusen Alluminium ex. Alexindo 3 " ( warna / coklat, hitam ) 103,000 m1
5 Bahan kusen Alluminium ex. YKK 4 " ( silver / natural ) 125,000 m1
6 Bahan kusen Alluminium ex. YKK 4 " ( warna / coklat, hitam ) 132,000 m1
7 Bahan kusen Alluminium ex. YKK 3 " ( silver / natural ) 112,000 m1
8 Bahan kusen Alluminium ex. YKK 3 " ( warna / coklat, hitam ) 117,000 m1
9 Pintu Swing Poder coating 200x90 tanpa kaca 380,000 m2
10 Sunscreen alumunium 430,000 m2
11 Profil Alumunium jendela 2" ex. YKK ( silver / natural ) 104,500 m1
12 Profil Alumunium jendela 2" ex. YKK ( warna / coklat, hitam ) 114,000 m1
13 Profil Alumunium Pintu 3" ex. YKK ( warna / coklat, hitam ) 118,000 m1
14 List Kaca karet L 1 cm 5,200 m'
15 List aluminium L 1 cm 3,300 m'
16 List aluminium L 1 x 2 cm 9,500 m'
17 Alumunium Strip 12,000 m'
18 Folding Gate t=0.8mm 550,000 m2
19 Rolling Door t=0.8mm + Motor penggerak ( Harga terpasang ) 1,000,000 m2
20 Rangka plafond allum (lay in) merk BORAL 32,000 m2
21 Venetions Blinds dan Vertical Blinds 73,000 m'
22 Kaca nako + rangka 81,000 unit
23 Kaca polos 3mm 95,000 m2
24 Kaca polos 5mm 127,000 m2
25 Kaca Buram/kaca S 5mm 130,000 m2
26 Kaca warna 5mm 130,000 m2
27 Kaca Cermin 5mm 190,000 m2
28 Kaca polos 8mm 140,000 m2
29 Kaca warna 8mm 470,000 m2
30 Kaca Tinted 8 mm 470,000 m2
31 Kaca polos 12mm 865,000 m2
32 Kaca warna 12mm 865,000 m2
33 Kaca tempered 12mm 865,000 m2
34 Plat alumunium t = 2mm 160,000 m2
35 Plat alumunium t = 3mm 212,000 m2
36 Plat alumunium L = 90cm 50,200 m1

HARGA SATUAN UPAH DAN BAHAN138


124

II. BAHAN.
HARGA
NO JENIS MATERIAL SAT
Rp.
I JENIS CAT
1 Cat Tembok Dalam Setara Catilax ICI 45,000 Kg
2 Cat Tembok Dalam Setara Vinilex 55,000 Kg
3 Cat Tembok Dalam ex Nipponpaint 59,600 Kg
4 Cat Tembok Dalam ex Mowilex Type Acrylic Emulsion paint 62,000 Kg
5 Cat Tembok Dalam ex DULUX Type Acrylic Emulsion paint 65,000 Kg
6 Cat Tembok Dalam ex JOTUN Premium 62,000 Kg
7 Cat Tembok Luar ex Nipponpaint Type Weatherbond 106,000 Kg
8 Cat Tembok Luar ex Mowilex Type Weathercoat 95,000 Kg
9 Cat Tembok Luar ex DULUX Type Weathersheild 95,000 Kg
10 Cat Tembok Luar ex JOTUN Type Jotasheild 102,000 Kg
11 Cat Dasar Interior setara mutu tinggi 42,000 Kg
12 Cat Dasar Exterior setara mutu tinggi 46,000 Kg
12 Cat Kayu dan Besi setara mutu Seiv 55,000 kg
13 Cat Kayu dan Besi setara ICI. Dulux 55,000 ltr
14 Minyak cat standard biasa 15,000 Lt
15 Thiner ( minyak cat A spesial ) 35,000 Lt
16 Wood filer setara mutu tinggi 43,000 kg
17 Wood stand setara Impra 43,000 kg
18 Sanding Sealer setara Impra 39,000 Itr
19 Clear Melamic Setara Impra 45,000 kg
20 Meni kayu setara mutu menengah 55,000 kg
21 Meni besi setara mutu menengah 30,000 Lt
22 Plitur Impra 59,000 kg
23 Dempul kayu setara mutu menengah 20,000 kg
24 Dempul duko setara mutu tinggi 40,000 kg
25 Kwas setara Makita 17,500 bh
26 Rool cat 25,000 bh
27 Ampelas tembok 3,200 bh
28 Ampelas kayu & besi 3,200 bh
29 PlamIr tembok setara mutu ICI. Dulux 21,000 kg
30 Minyak bekisting 6,000 Lt
31 Ram kawat ayam 10,500 m2
32 Coating Primer 19,000 m2
33 Water Proofing Produck Sika :
- Sika rain Tite ( Untuk atap beton ) 40,000 kg
- Sika top 107 Seal ( Untuk toilet, balkon & area basah ) 18,000 kg

HARGA SATUAN UPAH DAN BAHAN138


125

II. BAHAN.
HARGA
NO JENIS MATERIAL SAT
Rp.
- Sikafloor Epolem Module ( Water cistern & rain water tank ) 96,000 kg
- Sikagard 81 Epolem ( Water cistern & rain water tank ) 26,000 kg
- Sikagard 720 Epolem ( Water cistern & rain water tank ) 25,000 kg
- Sikagard 62 ( Water cistern & rain water tank ) 361,000 kg
- Sika Chapdur ( Floor hardener ) Natural 4,235 kg
- Sika Chapdur ( Floor hardener ) warna 5,082 kg

J JENIS PELEKAT / LEM & IJUK


1 Sealent (penjepit kaca) dari karet 5,600 m1
2 Sealent setara mutu menengah 45,000 tube
3 Lem kuning setara mutu menengah 17,500 kg
4 Lem Kayu putih setara mutu menengah 34,000 kg
5 Ijuk 21,200 kg

K SALURAN AIR
K.1 Saluran pipa air kotor
1 Buis beton 1/2 Ø 20 cm 60,000 bh
2 Buis beton 1/2 Ø 30 cm 80,000 bh
3 Buis beton Ø 20 cm panjang 1M 105,000 bh
4 Buis beton Ø 30 cm panjang 1M 140,000 bh
5 Buis beton Ø 40 cm panjang 1M 200,000 bh
6 Buis beton Ø 50 cm panjang 1M 310,000 bh
K.2 PVC
1 Pipa PVC Ø 1/2" setara standard AW 4,425 Meter
2 Pipa PVC Ø 3/4" setara standard AW 5,000 Meter
3 Pipa PVC Ø 1" setara standard AW 8,300 Meter
4 Pipa PVC Ø 1 1/4" setara standard AW 12,225 Meter
5 Pipa PVC Ø 1 1/2" setara standard AW 14,650 Meter
6 Pipa PVC Ø 2" setara standard AW 19,275 Meter
7 Pipa PVC Ø 2 1/2" setara standard AW 31,750 Meter
8 Pipa PVC Ø 3" setara standard AW 37,500 Meter
9 Pipa PVC Ø 4" setara standard AW 62,275 Meter
10 Pipa PVC Ø 5" setara standard AW 99,850 Meter
11 Pipa PVC Ø 6" setara standard AW 139,075 Meter
12 Pipa PVC Ø 8" setara standard AW 216,500 Meter
13 Pipa PVC Ø 10" setara standard AW 343,500 Meter
14 Lem PVC 84,000 kg
15 Gergaji besi 15,000 bh
14 BSP 15mm - Meter
15 BSP 25mm - Meter
16 BSP 32mm - Meter
17 BSP 40mm - Meter
18 BSP 50mm - Meter
19 BSP 65mm - Meter
20 BSP 80mm - Meter
21 BSP 100mm - Meter
22 BSP 125mm - Meter
23 BSP 150mm - Meter
24 BSP 200mm - Meter
P.5 POMPA
EX.VERSA
1 Pompa horisontal single stage 4,025,000 paket
2 Pompa transfer air bersih (2x 320 l/m) 3 phase, head 42 m paket
3 Pompa transfer air olahan (2x 320 l/m) 3 phase, head 42 m paket
4 Pompa booster air bersih (2x 150 l/m) 3 phase, head 10 m paket
5 Pompa sewage pit (2x 300 l/m) 3 phase, head 25 m paket
6 Pompa transfer air bersih (2x 500 l/m) 3 phase, head 60 m paket
7 Pompa transfer air olahan (2x 420 l/m) 3 phase, head 60 m paket
8 Pompa filter STP (300 l/m) 3 phase, head 25 m paket
9 Pompa filter air hujan (400 l/m) 3 phase, head 25 m paket
10 Pompa sumur dalam (150 l/m) 3 phase, head 100 m paket
11 Pompa booster air bersih (2x 120 l/m) 3 phase, head 10 m paket
12 Pompa booster air bersih (2x 110 l/m) 3 phase, head 10 m paket
13 Pompa bak kontrol (2x 100 l/m) 3 phase, head 20 m paket
14 Pompa grease trap (2x 100 l/m) 3 phase, head 15 m paket
15 Pompa pit basement (2x 300 l/m) 3 phase, head 15 m paket
16 Pompa pit ruang pompa (100 l/m) 3 phase, head 10 m paket
17 Pompa filter STP (300 l/m) 3 phase, head 15 m paket
18 Pompa filter air hujan (400 l/m) 3 phase, head 15 m paket
19 Pompa filter sumur (150 l/m) 3 phase, head 15 m paket

L SANITARY ACCESSORIES
1 1 Unit Closet duduk lengkap setara INA 1,183,000 unit
2 1 Unit Closet duduk setara Standart dengan tangki 1,800,000 unit
3 1 Unit Closet duduk porselin LUX dengan tangki 1,900,000 unit

4 1 Unit Closet duduk setara TOTO CW 705ELNJ TV150NSV7J 5,950,000 unit


- C 421 J closet body
- SW420JP low tank
- TR 407 HV3 Tank trim + stop valve
- TC 262 NV1 Seat & coper
- T 53 P100 Seal Garket & Flange
- T 53 DSR Screws & Cap / set
5 1 UNIT MONO BLOCK TOTO Type CW 661 JT1/SW 661 JP 3,150,000 unit
- CW 661 JT1 closet body
- SW 661 JP low tank
- SW 661 CRJP Tank cover for SW 661 JP
- TX212CWS Dual flush tank trim W/O stop valve for SW420, SW660J (6/3 liters)
- TC280 Duroplast seat & cover W/Metal Hinges
- TX212CWS Insulation fitting set for CW660J, CW661JT1, CW668J

HARGA SATUAN UPAH DAN BAHAN138


126

II. BAHAN.
HARGA
NO JENIS MATERIAL SAT
Rp.
6 Closet jongkok unit
- CE 7 250,000 bh
- CE 6 567,200 bh
7 Urinal U 370 M 5,250,000 unit
8 Urinal U 57 M 1,500,000 unit
9 Urinal partition unit
- Urinal partition w/fittings tipe A100 1,150,000 unit
7 Washtafel Standart INA 1,016,000 unit
8 Washtafel Lux INA 1,200,000 unit
9 WASTAFEL L 521 V1A 1,332,500 unit
- L 521 V1A 525,000 bh
- T 205 MCB 199,500 bh
- TX 709-AN 318,000 bh
- TS 251 FT2N 165,000 bh
- TS 126 AR 125,000 bh
10 WASTAFEL L 237 V1B 1,456,000 unit
- L 237 V1B - bh
- T 205 MCB - bh
- T6 PV1 - bh
- TS 251 F - bh
- TS 126 AR - bh
11 WASTAFEL TOTO Type LW 535 J SHEET 2,581,000 unit
Lw 535 J bh
- T 205 QN bh
- TX 709 AV4N bh
- TS 251 FT2N bh
- TL 220 D bh
9 WASTAFEL L529 VI LENGKAP 1,655,000 unit
10 WASTAFEL L 38 V1 SHEET - unit
L 38 V1 bh
- T 205 MCB bh
- TX 709 AN bh
- TS 251 FT2N bh
- TS 126 AR & T 9 R, T 8 C bh
11 Wastafel pedestal ex. TOTO Tipe Vision LW 825 CJ komplit 1,408,000 unit
12 Wastafel dinding ex. TOTO Tipe LW 825 J komplit 4,058,000 unit
13 Bak mandi teraso volume air 0.30 m3 282,150 unit
14 Bak mandi fiberglass volume air 0.30 m3 183,750 unit
15 Bak mandi fiberglass volume air 1 m3 1,320,000 unit
16 Bath tube ex. Toto 3,750,000 unit
11 Kitchen zink setara 1 lobang stinless lengkap 385,000 unit
12 Meja beton untuk pantry 125x50 295,000 bh
15 Kran Air Biasa 69,000 unit
16 Belokan knee 1 inch 1,200 bh
Percabangan pipa 1 inch
Percabangan pipa 2 inch
17 Shower Spray TX 403 S N5 + TS 251 F 328,000 unit
18 Floor drain TX 1 AN 119,000 unit
19 Floor drain biasa 15,000 unit
20 Soap holder/Tempat sabun colour 29,000 unit
21 Kran dinding T 23B 13V7N 187,000 unit
22 Kran dinding T 30 AR13 V7N 299,000 unit
23 Kran dinding Toto tipe T 26-13 ( kran taman ) 725,000 unit
24 Kran dinding ex SUN-EI Type TY 20 JNR 195,000 unit
25 Hand shower set THX 17ZB/ TX 402 XZ 512,000 bh
26 Hand shower set THX 18ZB/ TX 402 XZ 622,000 bh
27 Hand shower set THX 19ZB/ TX 402 XZ 842,000 bh
28 Hand shower set TX 423 SZ/sink tap 591,000 bh
29 Gate valve 2 inch 525,000 bh
30 Pipa galvanised I inch 54,208 m
31 Pipa galvanised 2 inch 101,708 m
30 Hand shower B250 298,000 bh
31 Fixed Shower Head TX 422 S - Valve: TX 419 SCN 1,240,000 unit
32 Fixed shower head TB 18 D (Luxury shower head) 2,720,000 unit
33 Fixed shower head TX422SC - Valve: TX 419 SCN (Curio fixed shower head - 3 1,240,000 unit
34 Fixed shower head TX435SZ (3S Massage) 601,000 unit
35 Fixed shower head TX439SZ (3S Massage) 872,000 unit
36 Head shower ex. TOTO tipe TX422S + TX452SF + TGB 9 MZN 510,850 unit
37 Paper Holder ex. Toto :
- Paper Holder TS 116 R 209,000 bh
- Paper Holder TOTO TX 703 AC 268,000 bh
- Paper Holder TOTO TX11B 209,000 bh
38 Soap holder/Tempat sabun ex. Toto tipe :
- S 6N colour 61,000 unit
- S 11N colour 47,000 unit
- S 156N colour 61,000 unit
- S 160V1 colour 205,000 unit
- S 161 colour 294,000 unit
- Soap Dispencer TS 125 R 232,000 bh
- Soap Basket ex TOTO Type TX 2 BV1B 234,000 unit

HARGA SATUAN UPAH DAN BAHAN138


127

II. BAHAN.
HARGA
NO JENIS MATERIAL SAT
Rp.
38 Tissue Dispencer ex. Toto tipe TX 8 374,400 unit
39 Grab Bar ex. Toto tipe :
- TX3A1 Grab Bar (Panjang 350 mm) 488,000 bh
- TX3A2 Grab Bar (Panjang 500 mm) 592,000 bh
- TX3A3 Grab Bar (Panjang 800 mm) 723,000 bh
40 Double Robe Hook TOTO Type TS 118 WS 92,000 bh
41 Towel bar ex. Toto tipe :
- Towel bar TX 5 B (L=660 mm) 449,000 bh
- Towel bar TX 5A2 (L=660 mm) 420,000 bh
- Towel bar TX 5A1 (L=558 mm) 383,000 bh
42 - Towel Ring TS 115 S 153,600 bh

21 Jet Washer ex. TOTO tipe THX30CRB 265,000 Unit

M ACCESSORIES PINTU
Ex. setara Griff
1 Lockcase :
- Kenobset WC setara Griff 170,978 set
- Lockcase setara Griff ( untuk pintu dobel ) 223,125 bh
- Lockcase setara Griff ( untuk pintu singel ) 204,850 bh
- Lockcase setara Griff ( untuk pintu geser ) 236,725 bh
- Lockase KM ex setara Griff (untuk KM/WC) 252,450 bh
- Kunci Tanam besar 36,000 bh
- Kunci Tanam Kecil 29,000 bh
2 Lever Handle :
- Lever Handle setara Griff 72,450 psg
3 Double Cylinder :
- Double Cylinder 60mm normal setara setara Griff (untuk toilet) 273,000 bh
- Double Cylinder 60mm normal setara setara Griff Type 3301.60 157,000 bh
4 Tubular Pull Handle :
- Tubular Pull Handle setara Griff ( pintu kaca & alumunium ) 404,300 psg
- Tubular Pull Handle setara Griff ( pintu kayu ) 379,000 psg
- Tubular Pull Handle setara Griff ( pintu kayu & kaca ) 539,200 psg
- Tubular Pull Handle setara Griff ( pintu kaca ) 843,700 psg
- Pull Handle on Backplate 84,000 psg
5 Engsel pintu :
- Engsel setara Griff (4"x3"x2,5) washer 98,000 bh
- Engsel setara Griff (4"x3"x2,5) with ball beering 104,100 bh
6 Floor hinge setara setara Griff 952,000 set
7 Sliding track huskey 100 ex. setara Griff ( untuk pintu geser ) panjang 3 m 1,515,000 set
8 Engsel jendela :
- Friction stay setara Griff tipe 1909-SS-8" ( untuk boven jungkit ) 120,400 psg
9 Slot tarikan jendela alumunium :
- Rambuncis ex. setara Griff 51,000 bh
10 Fush Plate ( untuk pintu geser ) tipe :
- setara Griff 138,600 bh
13 Fushbolt : 126,500 bh
- Fushbolt tanam atas bawah 8+12" ex. setara Griff 210,500 psg
- Fushbolt ex setara Griff (untuk pintu Rangka) 175,000 psg
- Door Viewer ( untuk dudukan Fushbolt bawah ) 64,800 bh
14 Panicbar ( untuk pintu baja ) 2,915,000 bh
15 Floor hinge setara setara Griff , lengkap ( untuk pintu alumunium ) 1,320,000 bh
16 Top Fact fiting setara setara Griff ( untuk pintu kaca engsel atas ) 660,000 bh
17 Over & side panel Fact ex. setara Griff (untuk pasangan Top Pact - kaca ke ka 970,000 bh
18 Bottom Fact fiting setara setara Griff ( untuk pintu kaca engsel bawah ) 660,000 bh
19 Corner Lock setara setara Griff ( untuk kunci bawah pintu kaca ) 870,000 bh
20 Escutcheon ex. setara Griff 76,500 set
21 Door closer ex setara Griff 662,000 set
22 Sliding track huskey 100 ex. setara Griff ( untuk pintu geser ) panjang 2 m 827,000 set
23 Roda bulat Ø100mm 23,750 bh

HARGA SATUAN UPAH DAN BAHAN138


128

II. BAHAN.
HARGA
NO JENIS MATERIAL SAT
Rp.
P TANAMAN
1 Angsana (2 s/d 3m) 178,000 btg
2 Bambu Jepang (2 s/d 3m) 105,300 m2
3 Bambu Kuning (2 s/d 3m) 126,000 m2
4 Rumput Gajah 6,000 m2
5 Rumput jepang 18,500 m2
6 Rumput peking 6,500 m2
7 Rumput bermuda ( terpasang belum PPN + keuntungan ) 92,800 m2
8 Pohon Kiara payung T= 1 - 2 m 40,000 btg
9 Pohon Nangka tinggi 40cm 12,500 btg
10 Lili Paris 3,000 btg
11 Klame of Irian 29,850 btg
12 Tanaman heloconia 8,900 btg
13 Pohon kecapi tinggi 40cm 11,500 btg
14 Pohon manggis t=2 - 4 m 75,000 btg
15 Pohon ceremai tinggi 40cm 47,500 btg
16 Dadap Merah t=2 - 4 m 228,000 btg
17 Pohon semak ekor tupai 32,500 btg
18 Pohon kaca piring tinggi 40cm 29,000 btg
19 Pohon trembesi t = 2,50 m - 3,00 m 397,500 btg
20 Palem botol (2 s/d 3m) 858,000 btg
21 Palem Raja t=2 - 4 m 214,500 btg
22 Pohon semak mahkota duri 14,000 btg
23 Pohon pisang - pisangan 12,000 btg
24 Pohon semak hias taiwan beuty 12,500 btg
25 Pohon hias bougenville t = 50 cm 35,500 btg
26 Pohon hias bougenville ping t = 50 cm 45,000 btg
27 Pohon hias bougenville ungu t = 50 cm 45,000 btg
28 Teh-Tehan ( Duranta) 3,250 btg
29 Perdu Oleander 23,500 btg
30 Pohon Sukun t=1,5 - 2 m 75,000 btg
31 Pohon Kelengkeng t=1 m 150,000 btg
32 Pohon Tabebuya Caraiba ` 134,400 btg
33 Pohon pucuk merah t=1 m 70,000 btg
34 Pohon bungur t=1,5 -3 m 95,000 btg
35 Pohon BarosT= 2,5 - 3 m 75,000 btg
36 Pohon Pinus t= 2,5 - 3 m 90,000 btg
37 Pohon Mahoni t= 2,5 - 3 m 115,000 btg
38 Pohon Kamboja t= 2,5 - 4 m 225,000 btg
39 Pohon Ketapang laut t= 2 - 4 m 145,000 btg
40 Pohon Ketapang kencana t= 2 - 4 m 185,000 btg
41 Pohon Biola cantik t=1 - 2 m 65,000 btg
42 Pohon Jabon t= 2,5 - 3 m 150,000 btg
43 Pohon Tanjung t= 2,5 - 3 m 65,000 btg
44 Pohon Kasia kuning t=1 m 50,000 btg
45 Pohon bunga kupu-kupu t= 1,5 - 3 m 65,000 btg
46 Aires polybeg 20 ( 1 Rumpun=1m2 ---25 pohon ) 1,500 btg
47 Lantana polybeg 20 ( 1 Rumpun=1m2 ---25 pohon ) 2,500 btg
48 Tegetes polybeg 20 ( 1 Rumpun=1m2 ---25 pohon ) 2,500 btg

N PAGAR
PAGAR PANEL BRC :
1 Ukuran 175x240 dia 8mm Elektroplating Galvanized 521,000 lbr
2 Ukuran 175x240 dia 8mm Hot dip Galvanized 693,000 lbr
3 Ukuran 175x240 dia 7mm Elektroplating Galvanized 398,000 lbr
4 Ukuran 175x240 dia 7mm Hot dip Galvanized 548,000 lbr
5 Ukuran 175x240 dia 6mm Elektroplating Galvanized 311,000 lbr
6 Ukuran 175x240 dia 6mm Hot dip Galvanized 413,000 lbr
1 Ukuran 190x240 dia 8mm Elektroplating Galvanized 549,000 lbr
2 Ukuran 190x240 dia 8mm Hot dip Galvanized 742,000 lbr
3 Ukuran 190x240 dia 7mm Elektroplating Galvanized 430,000 lbr
4 Ukuran 190x240 dia 7mm Hot dip Galvanized 588,000 lbr
5 Ukuran 190x240 dia 6mm Elektroplating Galvanized 326,000 lbr
6 Ukuran 190x240 dia 6mm Hot dip Galvanized 435,000 lbr
1 Ukuran 240x240 dia 8mm Elektroplating Galvanized 632,000 lbr
2 Ukuran 240x240 dia 8mm Hot dip Galvanized 856,000 lbr
3 Ukuran 240x240 dia 7mm Elektroplating Galvanized 493,000 lbr
4 Ukuran 240x240 dia 7mm Hot dip Galvanized 665,000 lbr
TIANG BRC :
1 Ukuran tinggi 175 dia 2" Elektroplating Galvanized 101,200 bh
2 Ukuran tinggi 175 dia 2" Hot dip Galvanized 122,100 bh
3 Ukuran tinggi 200 dia 2" Elektroplating Galvanized 118,800 bh
4 Ukuran tinggi 200 dia 2" Hot dip Galvanized 143,000 bh
5 Ukuran tinggi 220 dia 2" Elektroplating Galvanized 138,600 bh
6 Ukuran tinggi 220 dia 2" Hot dip Galvanized 159,500 bh
7 Ukuran tinggi 240 dia 2" Elektroplating Galvanized 158,500 bh
8 Ukuran tinggi 240 dia 2" Hot dip Galvanized 174,000 bh
9 Ukuran tinggi 300 dia 2" Elektroplating Galvanized 178,000 bh
10 Ukuran tinggi300 dia 2" Hot dip Galvanized 214,500 bh
Harga tianga diaatas sudah termasuk accessories ( tutup tiang, angkur dan U-Clip )
U. Atap
Komponen space frame : pipa Od 2,5"-16", balljoint T 84 - 300 M 16 / 42,
1 m2
base plate t=25mm + angkur M32-500 1,676,167.43
Komponen gording : dudukan gording, gording primer ∅3"t=2.8"(STK41),
2 m2
skunder ∅2" t=2.8mm(STK41), klem gording primer & sekunder 148,804.80
Komponen catwalk : dudukan catwalk ∅3" t=3mm, rangka baja CNP 125,
3 m2
siku 40.40.4, railling BSP Ø1" & expanded metal 604,103.80
Komponen Penutup atap geas Zipdeck : Standing seam (tapered)
4 m2
Colorbond TCT = 0,50mm (BMT), Alumunium Halter, Halter path 370,685.38
Lisplank Bulnose-Zinc Alum rangka pipa Ø2", hollow 40x40x2mm, hollow
5 m2
20x40x1,6mm + dudukan gording & ACPt=4mm 812,195.12
Komponen talang datar : Dudukan talang siku 50.50.5, pipa ∅ 2" t=2mm
6 STK 41, metal zincalume t=6mm, flshing zincalume t=6mm & corong
talang Od 12" 1,355,625.69 m2
- Harga per m2 atap space frame 2,416,490.94 bh

V. Pelat beton Prestressed Precast ( By Specialis PCI ) :


- Tipe. 1 Ukuran 350 x 100cm + sandaran lantai l=35cm 2,416,490.94 bh
- Tipe. 1A Ukuran 300 x 220cm + sandaran lantai l=35cm 3,429,955.62 bh
- Tipe. 1B Ukuran 300 x 220cm + sandaran lantai l=35cm 3,429,955.62 bh
- Tipe. 1C Ukuran 460 x 100cm + sandaran lantai l=35cm 2,874,002.95 bh
- Tipe. 1D Ukuran 350 x 100cm + sandaran lantai l=35cm 2,416,490.94 bh
- Tipe. 2 Ukuran 350 x 100cm + sandaran lantai l=40cm 2,331,308.98 bh
- Tipe. 2A Ukuran 350 x 200cm + sandaran lantai l=40cm 3,420,684.54 bh
- Tipe. 2B Ukuran 350 x 180cm + sandaran lantai l=40cm 3,151,414.63 bh
- Tipe. 3 Ukuran 350 x 100cm + sandaran lantai l=45cm 2,405,688.74 bh
- Tipe. 3A Ukuran 360 x 200cm + sandaran lantai l=45cm 3,526,376.49 bh
- Tipe. 3B Ukuran 360 x 170cm + sandaran lantai l=45cm 3,217,849.18 bh
- Tipe. 3C Ukuran 350 x 100cm + sandaran lantai l=45cm 2,454,155.34 bh
- Tipe. 4 Ukuran 350 x 100cm + sandaran lantai l=90cm 4,212,622.05 bh
- Tipe. 5 Ukuran 350 x 100cm + sandaran lantai l=35cm 4,525,105.13 bh
- Tipe. 3D Ukuran 380 x 100cm + sandaran lantai l=45cm 4,573,703.94 bh
- Tipe. 6 Ukuran 370 x 145cm - 180 x 150cm 9,707,084.81 bh
- Tipe. 7 Ukuran 380 x 100cm + sandaran lantai l=70cm 5,031,074.33 bh

O LISTRIK
1 Kabel, NYM 3 x 2,5 mm2 13,500 M'
2 Pipa Conduit 8,000 M'
3 Socket Pipa 600 Bh
4 Tee Doos 5,100 Bh
5 Klem Pipa 600 Bh
6 Fhiser 3,600 Bh
7 Las Doop 4,358 Bh
8 Isolasi ban 10,000 Bh
9 Saklar Tunggal Single OB 11,000 Bh
10 Saklar Ganda ob 15,000 Bh
11 Stop Kontak In Bow 12,800 Bh
12 Lampu Philips LED 7 W 87,500 Bh
13 Lampu Philips LED 13 W 175,300 Bh
14 Lampu Philips LED 36 W 175,000 Bh
15 Lampu Philips PL 11 W 45,000 Bh
16 Lampu Flood light 250,000 Bh
17 Lampu Philips PL 18 W 49,500 Bh
18 Armateur Roseet Plafond 15,000 Bh
19 Armateur Downlight 4" 25,000 Bh
20 Armateur Downlight Outbow 4" 25,000 Bh
21 Lampu Baret TL 18 watt +Armateur Lampu Baret 30,000 Bh
22 Lampu Industrial Lampu Philips HPI-BU 250 watt + Cover 350,000 BH
23 Lampu Cold Storage 100 Watt + Cover 850,000 BH
24 Exhaust Fan 12" 210,000 Bh
25 Lampu LED Philips 2x 36 W + Armateur RM 650,000 Bh
26 Lampu LED Philips 2x 18 W + Armateur RM 450,000 Bh
27 MCCB 25 A, 3 P, 10 kA 253,000 Bh
28 7 x MCB 6 A, 1 P, 6 kA 205,000 Bh
29 fuse 2 A + fuse holder 9,500 Bh
30 3 x pilot lamp 74,000 Bh
31 1 lot busbar 40 A full neutral, 5 bus 110,900 Bh
32 1 lot internal wiring + aksesori 314,000 Bh
33 1 lot panel 50 (L) x 25 (D) x 60 (T) cm 470,000 Bh
34 1 lot instalasi kabel grounding 3,000,000 Bh
35 NYFGbY 2 x 120 sqmm 225,000 Bh
36 Alesis RA150 Stereo Power Amplifier 1,600,000 Bh
37 CCTV 16 chanel 12,000,000 pkt
38 AC split 2.5 PK 6,815,000 unit
39 Exhaust fan blower 70cm 400,000 bh

O LAIN LAIN
1 Solar 9,500
MinyakPelumas 55,000

HARGA SATUAN UPAH DAN BAHAN138


DAFTAR HARGA SEWA PERALATAN PER JAM
BIAYA
NO ALAT KO HP KAP. SEWA KET.
DE ALAT/JAM
(di luar PPN)

1 ASPHALT MIXING PLANT E01 220.0 50.00 T/Jam 8,250,000.00


2 ASPHALT FINISHER E02 50.0 5.00 Ton 500,000.00
3 ASPHALT SPRAYER E03 15.0 300.00 Liter 100,000.00
4 BULLDOZER 100-150 HP E04 155.0 400,000.00
5 COMPRESSOR 4000-6500 L\M E05 80.0 5,000.00 CPM/(L/m) 175,000.00
6 CONCRETE MIXER 0.3-0.6 M3 E06 15.0 300.00 Liter 85,000.00
7 DUMP TRUCK 3.5 TON E09 100.0 3.50 Ton 200,000.00
8 DUMP TRUCK 10 TON E09 190.0 10.00 Ton 350,000.00
9 EXCAVATOR 80-140 HP E10 133.0 0.93 M3 350,000.00
10 FLAT BED TRUCK 3-4 M3 E11 190.0 10.00 ton 350,000.00
11 GENERATOR SET E12 180.0 135.00 KVA 250,000.00
12 MOTOR GRADER >100 HP E13 135.0 135.00 HP 350,000.00
13 WHEEL LOADER 1.0-1.6 M3 E15 125.0 1.50 M3 350,000.00
14 THREE WHEEL ROLLER 6-8 T E16 60.0 8.00 Ton 250,000.00
15 TANDEM ROLLER 6-8 T. E17 60.0 8.00 Ton 350,000.00
16 TIRE ROLLER 8-10 T. E18 60.0 10.00 Ton 350,000.00
17 VIBRATORY ROLLER 5-8 T. E19 82.0 7.05 Ton 350,000.00
18 CONCRETE VIBRATOR E20 5.5 25.00 - 45,000.00
19 WATER TANKER 3000-4500 L. E23 125.0 4,000.00 Liter 155,000.00
20 TAMPER E25 5.0 0.20 Ton 45,000.00
21 JACK HAMMER E26 3.00 60.00 - 45,000.00
22 CONCRETE PUMP 28 26 -50 m³ 512,500.00
23 ASPHALT LIQUID MIXER E34 5.0 1,000.00 Liter 200,000.00
24 CONDRETE MIXER (350) E47 20.0 350.00 liter 85,000.00
25 BAR BENDER E53 3.0 2.00 HP 15,000.00
26 BAR CUTTER E54 3.0 2.00 HP 15,000.00
27 BORE PILE 3.0 2.00 HP 216,200.00
DAFTAR HARGA SATUAN UPAH

NO URAIAN SATUAN UPAH (Rp.)

A DAFTAR UPAH
1 Mandor Org/hr Rp 150,270.00
2 Kepala Tukang Batu Org/hr Rp 135,243.00
3 Kepala Tukang Kayu Org/hr Rp 135,243.00
4 Kepala Tukang Besi Org/hr Rp 135,243.00
5 Kepala Tukang Cat Org/hr Rp 135,243.00
6 Kepala Tukang Listrik Org/hr Rp 135,243.00
7 Kepala Tukang Org/hr Rp 135,243.00
8 Tukang Batu Org/hr Rp 100,180.00
9 Tukang Kayu Org/hr Rp 100,180.00
10 Tukang Besi/Baja Org/hr Rp 100,180.00
11 Tukang Cat Org/hr Rp 100,180.00
12 Tukang Listrik Org/hr Rp 100,180.00
13 Tukang Pipa Org/hr Rp 100,180.00
14 Tukang Plitur Org/hr Rp 100,180.00
15 Tukang Taman Org/hr Rp 100,180.00
16 Tukang Org/hr Rp 100,180.00
17 Pembantu Tukang Org/hr Rp 80,144.00
18 Pekerja Biasa Org/hr Rp 80,144.00

B BAHAN PASANGAN DAN BESI


1 Pasir Urug m3 175,100.40
2 Tanah Urug Pilihan m3 102,141.90
3 Sirtu m3 157,590.36
4 Pasir Pasang Kali m3 214,011.60
5 Pasir Beton m3 233,467.20
6 Batu Pecah Mesin 2/3 m3 263,592.00
7 Batu Pecah Mesin 3/5 m3 280,328.00
8 Batu Belah Pondasi m3 282,420.00
9 Paving Blok Natural 8 cm buah 4,707.00
10 Paving Blok Natural 6 cm buah 3,138.00
11 Bata Merah Bakar kelas I bh 627.60
12 Semen PC /50 kg Kg 1,464.40
13 Semen Putih zak 90,176.71
14 Semen Warna kg 15,272.65
15 Air ltr 627.60
16 Aggregat Halus Untuk Pondasi Klas A m3 360,870.00
17 Aggregat Halus Untuk Pondasi Klas B m3 319,030.00
18 Kanstein ukuran 60 X 15 X 30 cm bh 71,620.93
19 Aspal Kg 6,589.80
20 Saluran U-Ditch 40 X 60 cm m' 657,567.90
21 Saluran U-Ditch 50 X 70 cm m' 940,615.50
22 Saluran gorong - gorong diameter 30 cm m' 274,575.00
23 Grill Besi Lebar = 40 cm m' 457,625.00
24 Water Profing Bithuthene Sheet m2 156,900.00
B LABURAN,PENGISI DAN ALATNYA
1 Plamir Tembok kg 23,012.00
2 Cat Tembok Interior ( Plafon Dan Dinding ) lt 47,070.00
3 Cat Tembok Eksterior ( Plafon Dan Dinding ) lt 62,760.00
4 Cat Dasar Interior kg 26,150.00
5 Cat Dasar Eksterior kg 29,288.00
6 Water Profing Emulsion ml 68,094.60
7 Rool Cat Tembok bh 31,615.35
8 Ampelas lbr 4,863.90
9 Meni Kayu / Besi kg 29,572.51
10 Cat Kayu Sieve lt 40,564.93
11 Thinner lt 26,150.00
11 Kuas Cat bh 20,920.00
C BAHAN KAYU BERIKUT BAHAN JADINYA
1 Bambu 7 s.d 10 bt 24,319.50
2 Kayu Papan Borneo Super m3 3,526,066.00
3 Dolken 7 s/d 10 bt 31,380.00
4 List Profil Kamper 1 cm m1 8,657.74
5 List Profil Kamper 4 cm m1 13,910.75
6 Kayu Kaso 4/6 m3 2,876,500.00
7 Kayu Kaso 5/7 m3 3,265,427.90
8 Kayu Reng 2/3 Borneo Super m1 2,431.95
9 Kayu Reng 2/3 Kamper Banjar m1 3,210.17
10 Kayu Papan Terentang m3 3,033,400.00
11 Kayu Balok Terentang m3 2,298,062.00
12 Tali Ijuk kg 22,763.05
D BAHAN PENUTUP RANGKA PLAFOND
1 Gypsum 120 x 240 t= 9 mm lbr 73,220.00
2 Kalsiplank uk. 3000 x 300 x 9 mm lbr 63,230.70
3 Cotton Plester bh 14,591.70
4 GRC (120 x 240) cm, t = 4 mm lbr 99,370.00
5 Cornice Coumpound zak 72,958.50
E BAHAN KAYU LAPIS
1 Wall paper m2 54,183.85
2 MultiPlek 9 mm 120 x 240 lbr 141,210.00
F BAHAN LANTAI DAN PELAPIS DINDING
1 Keramik 10 x 20 dan 20 x 20 m2 44,747.88
2 Keramik 20 x 20 (Lantai Kamar Mandi) m2 71,128.00
3 Keramik 20 x 25 Dinding KM m2 70,186.60
4 Keramik 30 x 30 m2 58,576.00
5 Keramik 30 x 30 (Anti Slip) m2 70,186.60
6 Keramik 40 x 40 m2 76,358.00
7 Keramik 40 x 40 (Anti Slip) m2 67,990.00
8 Keramik 10 x 20 m' 9,704.79
9 Keramik 10 x 30 m' 11,087.60
10 Keramik 10 x 40 m' 12,865.80
G BAHAN LOGAM DAN BAHAN JADINYA
1 Besi Beton U-24 Rata-rata kg 9,937.00
2 Kawat Beton kg 25,417.80
3 Ram nyamuk Alumunium m2 71,169.84
4 Plat Srip Ø 2 x 30 mm ( 6 m1 ) bt 32,101.74
5 Plat Srip Ø 3 x 30 mm ( 6 m1 ) bt 32,199.02
6 Kusen Alumunium Natural 1.3 mm t= 1,3 mm ( m1 62,760.00
7 Frame Pintu Kaca Alumunium Natural 1.3 m m1 135,980.00
8 Frame Jendela Kaca Alumunium Natural 1.3 m1 94,140.00
9 Daun Jendela Alumunium Natural ( tanpa kac m2 96,110.66
10 Jalusi Alluminium m' 34,047.30
11 Lem Fox kg 23,249.44
12 Profil kaca m' 7,845.00
13 Skrup fixer bh 313.80
14 Sealent tube 39,225.00
15 Besi Hallow ( 2 x 4 x 4) cm (400cm) btg 21,984.83
16 Besi Hallow ( 4 x 4) cm (400 cm) btg 28,405.18
I BAHAN KACA
1 Kaca Polos 5 mm m2 107,978.58
2 Kaca Polos 6 mm m2 115,060.00
3 Kaca Polos 8 mm m2 183,050.00
4 Kaca Es 5 mm m2 162,130.00
5 Sealant tube 52,300.00
J BAHAN PAKU DAN MUR BAUT
1 Paku 1/2" s/d 2" kg 25,627.00
2 Paku 2" s/d 5" kg 25,627.00
3 Ramset / Dinabolt bh 7,004.02
4 Baut Besar bh 583.67
5 Paku GRC kg 34,047.30
6 Paku gypsum kg 17,023.65
K BAHAN PERPIPAAN
1 Pipa PVC RUCIKA type AW 2 1/2" bt 183,660.86
2 Pipa PVC RUCIKA type AW 3" bt 133,659.97
3 Pipa PVC RUCIKA type AW 4" bt 398,839.80
4 Solatip Ledeng gl 4,085.68
5 Pipa PVC 4" Berlobang Jenis AW m1 35,701.03
L BAHAN SANITAIR
1 Stop Kran 3/4" KIT bh 101,071.84
2 Stop Kran 1" KIT bh 120,819.28
3 Saringan Air Lt. KM Stainless Steel bh 64,787.15
4 Kran Tembok Sun Eui dia. 1/2" bh 143,302.00
5 Kran Tembok ITAP dia. 1/2" bh 101,462.00
6 Wastafel Lengkap unit 985,134.31
7 Wastafel unit 680,848.72
8 Closet Jongkok Standard unit 371,330.00
9 Closet Jongkok Lengkap Sistem Jet unit 1,977,564.46
M BAHAN PENUTUP ATAP
1 Genteng Metal m2 115,060.00
2 Insulasi Aluminium Foil m2 47,070.00
3 Ram kawat m2 26,150.00
4 Nok Genteng Metal lbr 43,775.10
5 Atap Seng Gelombang 80 cm x 180 cm x 3 lbr 61,187.86
6 Talang air zinkalum m' 67,990.00
N BAHAN MEKANIKAL
1 Hydrant Box dlm Gedung ( Lengkap ) unit 6,667,823.23
O BAHAN ALAT DAUN PINTU, PENGANTUNG DAN KUNCI
1 Kunci 2 Slaag Kuda Terbang bh 91,927.71
2 Lever Handle set 171,962.40
3 Pull Handle set 219,660.00
4 Cylinder unit 103,135.60
5 Mortise Lock unit 194,974.40
6 Espangolet ps 50,195.45
7 Grendel 5 cm bh 5,350.29
8 Hak Angin Kait Jendela Biasa ps 6,906.74
9 Engsel pintu 4" ps 14,591.70
10 Friction Stay Jendela bh 102,508.00
11 Window handle bh 47,070.00
12 Daun pintu engineering lapis HPL uk. 80 x 21 unit 993,700.00
13 Daun pintu engineering lapis HPL uk. 75 x 21 unit 941,400.00
14 Daun pintu engineering lapis HPL uk. 70 x 21 unit 920,480.00
15 Kusen + Daun pintu lengkap hardware uk. 2 unit 7,845,000.00
16 Alumunium plat m2 151,670.00
P BAHAN BAKAR DAN PELUMAS
1 Minyak Bekisting ltr 39,397.59
2 minyak tanah ltr 5,753.00
Q ALAT BERAT
1 Dump truck 3-4 ton bh 183,050.00
2 Excavator jam 307,262.50
3 Motor Grader jam 470,700.00
4 Pneumatic Tire Roller jam 294,187.50
5 Vibro Roller jam 298,110.00
6 Water Tank Truck jam 261,500.00
7 Wheel Loader jam 444,550.00
8 Asphalt finisher jam 1,255,200.00
9 Tandem roller jam 404,802.00
10 Asphalt Mixing Plant jam 6,288,552.00
11 Wheel Loader jam 614,002.00
12 Asphalt Spray jam 62,446.20
13 Compressor jam 206,689.60
14 jam 0.00
DAFTAR HARGA BAHAN DAN UPAH ELEKTRIKAL
LANJUTAN PEMBANGUNAN IPWL
DI KABUPATEN TAKALAR SULAWESI SELATAN

NO URAIAN HARGA SATUAN


A. DAFTAR UPAH
1 Pekerja Rp 80,144 hari
2 Tukang pipa Rp 100,180 hari
3 Tukang listrik Rp 100,180 hari
4 Tukang AC Rp 100,180 hari
5 Kepala tukang AC Rp 100,180 hari
6 Kepala tukang listrik Rp 135,243 hari
7 Kepala tukang pipa Rp 135,243 hari
8 Mandor Rp 150,270 hari

B. PEKERJAAN ELEKTRIKAL
1 Kabel NYM 3x2,5 mm2 Rp 14,950 m¹
2 Kabel NYY 4x25 mm2 Rp 135,000 m¹
3 Kabel NYY 4x4 mm2 Rp 34,500 m¹
4 Kabel NYY 4x6 mm2 Rp 42,000 m¹
5 Kabel NYY 4x10 mm2 Rp 74,000 m¹
6 Kabel NYY 4x50 mm2 Rp 264,000 m¹
7 Lampu Down Light LED 10 W Rp 224,250 bh
8 Lampu TL 36 Watt Rp 628,000 bh
9 Lampu SL 18 Watt Rp 85,000 bh
10 Lampu SL 11 Watt Rp 70,000 bh
11 Lampu SL 9 Watt Rp 50,000 bh
12 Lampu Jalan LED( 2 x 120 W ) IP-65+D299 Rp 14,000,000 bh
13 Saklar ganda 10 A Rp 41,000 bh
14 Saklar hotel 10 A Rp 46,900 bh
15 Saklar tunggal 10 A Rp 27,800 bh
16 Stop kontak daya 10/16 A Rp 62,600 bh
17 Stop kontak daya 10/16 A - 3 Phase Rp 475,700 bh
18 Socket Pipa Rp 700 bh
19 Tee Doos Rp 4,000 bh
20 Pipa Conduit Rp 5,600 m¹
21 Las Doop Rp 500 bh
22 Klem Pipa Rp 500 bh
23 Isolasi ban Rp 1,600 bh
24 Fhiser Rp 300 bh
25 Fuse & Indicator Rp 95,000 bh
26 Pilot Lamp Rp 23,400 bh
27 Box Panel ( 60 x 60 x 20 ) cm Rp 4,500,000 bh
28 Grounding BC 6-10 mm2 Rp 690,600 LS
29 Grounding BC 35 mm2 Rp 1,150,000 LS
30 MCB 10A/ 3 Pole, 6 kA Rp 98,810 bh
31 MCB 16A/ 3 Pole, 6 kA Rp 98,810 bh
32 MCB 20A/ 3 Pole, 10 kA Rp 175,727 bh
33 MCB 63A/ 3 Pole, 10 kA Rp 178,686 bh
34 Testing/pengukuran pentanahan Rp 1,000,000 titik
35 Tiang / Menara - dudukan EF, Pipa GSP, dia. 2" sepanj Rp 1,500,000 unit
36 Box Panel Plastik Golf Opaque Door (IEC 61439-3) 12 Rp 224,600 unit
C. PEKERJAAN MATV
1 Kabel Coaxial RG11( 0,6 mm2 ) Rp 14,400 m¹

D. PEKERJAAN DATA
1 HUB Un Managable Path Panel 1 x24 port Rp 6,400,000 bh
2 Gbit switch 1 x 24 Port Rp 13,500,000 bh
3 HUB Un Managable Path Panel 1 x 8 port + midspan PoRp 3,800,000 bh
4 Socket Data ( RG-45 ) Rp 99,900 bh
5 Kabel Fiber Optic Rp 300,000 bh

E. PEKERJAAN TELEPHONE
1 Socket Telephone RJ-11 Rp 99,900 bh
2 Terminal Box 10 Pairs Rp 515,300 bh
3 Terminal Box 20 Pairs Rp 777,000 bh
4 Kabel ITC 10x2x2x0,6 mm2 Rp 30,100 m¹
5 Kabel ITC 20x2x2x0,6 mm2 Rp 60,300 m¹
DAFTAR HARGA BAHAN DAN UPAH MEKANIKAL & PLUMBING
LANJUTAN PEMBANGUNAN IPWL
DI KABUPATEN TAKALAR SULAWESI SELATAN

NO URAIAN HARGA SATUAN


A. DAFTAR UPAH
1 Pekerja Rp 80,144 hari
2 Tukang pipa Rp 100,180 hari
3 Tukang listrik Rp 100,180 hari
4 Tukang AC Rp 100,180 hari
5 Kepala tukang AC Rp 135,243 hari
6 Kepala tukang listrik Rp 135,243 hari
7 Kepala tukang pipa Rp 135,243 hari
8 Mandor Rp 150,270 hari

B. PEKERJAAN VAC :
1 Exhaust Fan , Kapasitas : 150 CFM/ Wall Type Rp 435,000 unit
2 Exhaust Fan , Kapasitas : 200 CFM/ Wall Type Rp 580,000 unit
3 Exhaust Fan , Kapasitas : 250 CFM/ Wall Type Rp 725,000 unit
4 Exhaust Fan , Kapasitas : 300 CFM/ Wall Type Rp 870,000 unit
5 Exhaust Fan , Kapasitas : 350 CFM/ Wall Type Rp 1,015,000 unit
6 Exhaust Fan , Kapasitas : 500 CFM/ Wall Type Rp 1,450,000 unit
7 Exhaust Fan , Kapasitas : 750 CFM / Wall Type Rp 2,175,000 unit
8 Exhaust Fan , Kapasitas : 6000 CFM / Wall Type Rp 9,000,000 unit
9 Exhaust Fan , Kapasitas : 950 CFM/ Inline Type Rp 3,705,000 unit
10 Exhaust Fan , Kapasitas : 800 CFM/ Inline Type Rp 3,120,000 unit
11 Exhaust Fan , Kapasitas : 700 CFM/ Inline Type Rp 2,809,100 unit
12 Exhaust Fan , Kapasitas : 600 CFM/ Inline Type Rp 2,340,000 unit
13 Exhaust Fan , Kapasitas : 500 CFM/ Inline Type Rp 1,950,000 unit
14 Exhaust Fan , Kapasitas : 400 CFM/ Inline Type Rp 1,560,000 unit
15 Exhaust Fan , Kapasitas : 350 CFM/ Inline Type Rp 1,365,000 unit
16 Exhaust Fan , Kapasitas : 250 CFM/ Inline Type Rp 975,000 unit
17 Ceilling Fan Kapasitas 100 Cfm Rp 250,000 unit
18 Ceilling Fan Kapasitas 250 Cfm Rp 625,000 unit
19 Single Split ( OU + IU ) 16 000 BTU/h - Wall type Rp 6,500,000 unit
20 Single Split ( OU + IU ) 18 000 BTU/h - Wall type Rp 7,290,000 unit
21 Pemipaan Refrigrant 3/8 - 5/8" berisolasi Rp 115,000 m'
22 Pemipaan Refrigrant 1/4 - 1/2" berisolasi Rp 95,000 m'
23 Pemipaan Drain / PVC AW berisolasi Rp 75,000 m'

C. PEKERJAAN FIRE HYDRANT


1 Fire Extinguisher ( Dry Chemical ) Kap. 6 Kg Rp 1,189,300 bh
2 Dudukan Fire Extinguisher Rp 114,200 bh
3 PIPA GALVANIZED Medium A, di. 50 mm Rp 200,000 m¹
4 PIPA GALVANIZED Medium A, di. 65 mm Rp 250,000 m¹

D. PEKERJAAN PLUMBING
1 Submersible kuras Rp 10,275,000 unit
2 GATE VALVE DIA.25 MM / 10 Kg Rp 154,700 bh
3 GATE VALVE DIA.32 MM / 10 Kg Rp 214,100 bh
4 GATE VALVE DIA.40 MM / 10 Kg Rp 373,500 bh
5 GATE VALVE DIA.50 MM / 10 Kg Rp 489,400 bh
6 GATE VALVE DIA.65 MM / 10 Kg Rp 616,400 bh
7 GATE VALVE DIA.80 MM / 10 Kg Rp 808,200 bh
8 Floor Clean Out dia. 50 mm Rp 150,700 bh
9 Floor Clean Out dia. 65 mm Rp 191,900 bh
10 Floor Clean Out dia. 80 mm Rp 234,700 bh
11 Floor Clean Out dia. 100 mm Rp 293,400 bh
12 Floor Clean Out dia. 150 mm Rp 325,000 bh
13 Roof Drain diameter 150 mm Rp 412,000 bh
14 Roof Drain diameter 100 mm Rp 372,600 bh
15 Roof Drain diameter 80 mm Rp 298,200 bh
16 Roof Drain diameter 65 mm Rp 225,000 bh
17 Bak Kontrol Rp 317,200 unit
18 PIPA PVC Dia. 1” Rp 10,960 m¹
19 PIPA PVC Dia. 1 1/2” Rp 24,700 m¹
20 PIPA PVC Dia. 1 1/4” Rp 15,300 m¹
21 PIPA PVC Dia. 2 1/2” Rp 43,600 m¹
22 PIPA PVC Dia. 2” Rp 31,900 m¹
23 PIPA PVC Dia. 3” Rp 62,200 m¹
24 PIPA PVC Dia. 4” Rp 91,100 m¹
25 PIPA PVC Dia. 6” Rp 187,700 m¹
26 PIPA PVC Dia. 8” Rp 221,600 m¹
27 PIPA PVC Dia. 10” Rp 268,000 m¹
28 SEPTIK TANK BIOLOGICAL SISTEM KAP. 1 M3 Rp 4,500,000 unit
29 SEPTIK TANK BIOLOGICAL SISTEM KAP. 2 M3 Rp 6,500,000 unit
30 SEPTIK TANK BIOLOGICAL SISTEM KAP. 3 M3 Rp 9,250,000 unit
31 SEPTIK TANK BIOLOGICAL SISTEM KAP. 4 M3 Rp 12,540,000 unit
32 SEPTIK TANK BIOLOGICAL SISTEM KAP. 16 M3 Rp 42,856,600 unit
33 Pompa Transfer ( Multi Stage ) Kapasitas : 5.5kW Rp 19,998,333 unit
34 Dosing Pump & Chemical tank Rp 10,650,000 unit
35 Dudukan Tanki Air Rp 1,775,000 unit
36 Reservoir bawah, FRP Modul Sistem, kapasitas : 100 M3 Rp 325,000,000 unit
37 Ploating valve dia 50 mm Rp 1,263,918 bh
38 Water Level Control ( WLC ) Rp 2,642,383 Set
39 GATE VALVE DIA.50 MM / 10 Kg Rp 425,000 bh
40 GATE VALVE DIA.65 MM / 10 Kg Rp 1,053,522 bh
41 FLEXIBLE JOINT DIA.65 MM/ 10 KG Rp 317,346 bh
42 STRAINER DIA.80 MM Rp 1,104,571 bh
43 CHECK VALVE DIA. 65 MM Rp 1,170,198 bh
44 Bobin Filter d.1600 Rp 98,700,000 bh

E. PIPA AIR BERSIH


1 PPR PN-10 Ø 20 mm Rp 27,600 m¹
2 PPR PN-10 Ø 25 mm Rp 44,500 m¹
3 PPR PN-10 Ø 32 mm Rp 68,200 m¹
4 PPR PN-10 Ø 40 mm Rp 104,900 m¹
5 PPR PN-10 Ø 50 mm Rp 167,000 m¹
6 PPR PN-10 Ø 63 mm Rp 266,200 m¹
7 Pipa Galvanis Iron Pipe (GIP) :
- Pipa GIP diameter 50 mm (2") Rp 210,000 m¹
- Pipa GIP diameter 80 mm (3") Rp 252,000 m¹
7 Pipa Header diameter 100 mm Rp 1,427,100 unit
8 Pipa Header diameter 200 mm Rp 2,283,300 unit
9 Water Hammer Rp 750,000 unit
10 Pipa HDPE PE 100 dia. 150 mm Rp 187,000 m¹
11 Pipa HDPE PE 100 dia. 32 mm Rp 16,500 m¹
DAFTAR HARGA UPAH PEKERJAAN KONSTRUKSI

NO URAIAN PEKERJA KODE SATUAN HARGA SATUAN KET.

1 2 3 4 5 6

1 Pekerja Org/Hr 80,144.00


2 Tukang Batu Org/Hr 100,180.00
3 Tukang Kayu Org/Hr 100,180.00
4 Tukang Besi/Aluminium Org/Hr 100,180.00
5 Tukang Cat Org/Hr 100,180.00
6 Tukang Listrik Org/Hr 100,180.00
7 Tukang Las Org/Hr 100,180.00
8 Kepala Tukang Org/Hr 135,243.00
9 Mandor Org/Hr 150,270.00
10 Sopir Org/Hr 80,144.00
11 Operator Alat Berat Org/Hr 135,243.00
12 Pembantu Operator Org/Hr 100,180.00