KEGIATAN : PEMBANGUNAN, REHABILITASI DAN RENOVASI SARANA PRASARANA INFRASTRUKTUR PERGURUAN TINGGI NEGERI
PEKERJAAN : PEMBANGUNAN GEDUNG AKUNTANSI, TEKNIK INFORMASI, TEKNIK SIPIL POLITEKNIK NEGERI SAMARINDA
LOKASI : KOTA SAMARINDA
1 2 3 4
BAGIAN I GEDUNG AKUTANSI
I PEKERJAAN PENDAHULUAN 92,040,000.00
KESELAMATAN DAN KESEHATAN KERJA (K3) 92,040,000.00
II PEKERJAAN ARSITEKTUR 162,277,251,325.40
A PEKERJAAN PASANGAN DINDING 160,555,595,854.00
B PEKERJAAN PINTU/ JENDELA -
C PEKERJAAN LANTAI 834,223,940.00
D PEKERJAAN PLAFOND 58,294,668.00
E PEKERJAAN FINISHING -
F PEKERJAAN ATAP KANOPI -
G PEKERJAAN SANITAIR 10,400,740.00
H PEKERJAAN HALAMAN 818,736,123.40
III PEKERJAAN MEKANIKAL 7,696,920.00
A PEKERJAAN INSTALASI AIR BERSIH -
B PEK. INSTALASI AIR BUANGAN, AIR KOTOR & AIR HUJAN -
C PEKERJAAN INSTALASI AIR CONDITIONING (AC) -
D PEKERJAAN INSTALASI EXHAUST FAN -
E PEKERJAAN INSTALASI APAR (PEMADAM KEBAKARAN) -
F PEKERJAAN RESAPAN AIR BEKAS 7,696,920.00
IV PEKERJAAN ELEKTRIKAL -
A PEKERJAAN LANTAI - 2 (elevasi + 4,77) -
B PEKERJAAN LANTAI - 3 (Elevasi + 8,77) -
C PEKERJAAN LANTAI ATAP/ RL Elevasi + 12,77 -
TOTAL GEDUNG AKUTANSI 162,376,988,245.40
BAGIAN II GEDUNG TEKNIK SIPIL
I PEKERJAAN PENDAHULUAN - -
II PEK. PEMATANGAN LAHAN DAN TURAP 270,096,163.20 270,096,163.20
III PEKERJAAN SUB STRUKTUR. 645,680,142.40 645,680,142.40
IV PEKERJAAN UPPER STRUKTUR 3,396,981,681.00 3,396,981,681.00
V PEKERJAAN RANGKA KUDA - KUDA DAN ATAP - -
VI PEKERJAAN ARSITEKTUR 3,575,060,754.80
A PEKERJAAN PASANGAN DINDING 2,427,289,397.00
B PEKERJAAN PINTU/ JENDELA -
C PEKERJAAN LANTAI 1,146,490,288.80
D PEKERJAAN PLAFOND -
E PEKERJAAN FINISHING -
F PEKERJAAN SANITAIR 1,281,069.00
VII PEKERJAAN JEMBATAN PENGHUBUNG 472,168,812.63
A PEKERJAAN SUB STRUKTUR. 986,572.80
B PEKERJAAN UPPER STRUKTUR 328,943,319.83
C PEKERJAAN PASANGAN DINDING 75,527,320.00
D PEKERJAAN LANTAI 66,711,600.00
E PEKERJAAN FINISHING -
VIII PEKERJAAN HALAMAN DAN TAMAN 296,824,412.80 296,824,412.80
IX PEKERJAAN MEKANIKAL 260,040.00
A PEKERJAAN INSTALASI AIR BERSIH -
B PEK. INSTALASI AIR BUANGAN, AIR KOTOR & AIR HUJAN 260,040.00
C PEKERJAAN INSTALASI AIR CONDITIONING (AC) -
D PEKERJAAN INSTALASI APAR (PEMADAM KEBAKARAN) -
E PEKERJAAN INSTALASI EXHAUST FAN -
F PEKERJAAN INSTALASI FIRE ALARM -
X PEKERJAAN ELEKTRIKAL -
A PEKERJAAN LANTAI 1 (Elev. - 4.00) -
B PEKERJAAN LANTAI 2 (Elev. ± 0.00) -
C PEKERJAAN LANTAI - 3 (Elev. ± 4.00) -
D PEKERJAAN LANTAI ATAP /PETIR -
XI KESELAMATAN DAN KESEHATAN KERJA (K3) - -
1 2 3 4
BAGIAN III GEDUNG TEKNIK INFORMASI (TI)
A PEKERJAAN PERSIAPAN (K3) 91,315,000.00
KESELAMATAN DAN KESEHATAN KERJA (K3) 91,315,000.00
B PEKERJAAN STRUKTUR CORE LIFT 153,526,395.40
I Pekerjaan Galian dan Urugan 914,732.00
II Pekerjaan Struktur Pondasi, Beton dan Baja 152,611,663.40
III Pekerjaan Rangka Atap & Talang -
C PEKERJAAN ARSITEKTUR
I PEKERJAAN PASANGAN & DINDING 572,670,168.00
I.1 Pekerjaan Lantai - 1 1,727,460.00
I.2 Pekerjaan Lantai - 2 15,130,629.00
I.3 Pekerjaan Lantai - 3 189,506,026.00
I.4 Pekerjaan Lantai - 4 254,610,273.00
I.5 Pekerjaan Lantai - RL 111,695,780.00
II PEKERJAAN KUSEN, PINTU & JENDELA ALUMINIUM -
II.1 Pekerjaan Lantai - 1 -
II.2 Pekerjaan Lantai - 2 -
II.3 Pekerjaan Lantai - 3 -
II.4 Pekerjaan Lantai - 4 -
II.5 Pekerjaan Lantai - RL -
III PEKERJAAN LANTAI 157,215,859.00
III.1 Pekerjaan Lantai - 1 20,165,202.00
III.2 Pekerjaan Lantai - 2 14,523,799.00
III.3 Pekerjaan Lantai - 3 61,263,429.00
III.4 Pekerjaan Lantai - 4. 61,263,429.00
III.5 Pekerjaan Lantai - RL. -
IV PEKERJAAN PLAFOND 13,462,496.00
IV.1 Pekerjaan Lantai - 1 -
IV.2 Pekerjaan Lantai - 2 6,731,248.00
IV.3 Pekerjaan Lantai - 3 -
IV.4 Pekerjaan Lantai - 4 6,731,248.00
V PEKERJAAN SANITAIR -
V.1 Pekerjaan Lantai - 1 -
V.2 Pekerjaan Lantai - 2 -
V.3 Pekerjaan Lantai - 3 -
V.4 Pekerjaan Lantai - 4 -
V.5 Pekerjaan Lantai - RL. -
VI PEKERJAAN PENGECATAN / FINISHING -
VI.1 Pekerjaan Lantai - 1 -
VI.2 Pekerjaan Lantai - 2 -
VI.3 Pekerjaan Lantai - 3 -
VI.4 Pekerjaan Lantai - 4 -
VI.5 Pekerjaan Lantai - RL. -
VII PEKERJAAN ATAP - -
VIII PEKERJAAN RAILLING 32,777,868.00 32,777,868.00
IX PEKERJAAN LAIN - LAIN 4,324,847.00 4,324,847.00
X PEKERJAAN BANGUNAN LIFT 60,642,508.00 60,642,508.00
XI PEKERJAAN GROUND TANK, RUMAH GENSET DAN RUANG POMPA 119,541,587.60
XI.1 Pekerjaan Ground Tank 29,014,920.80
XI.2 Pekerjaan Rumah Genset dan Ruang Pompa 90,526,666.80
D PEKERJAAN ELEKTRIKAL
I PEKERJAAN ELEKTRIKAL GEDUNG -
I.1 Pekerjaan Lantai - 1 -
I.2 Pekerjaan Lantai - 2 -
I.3 Pekerjaan Lantai - 3 -
I.4 Pekerjaan Lantai - 4 -
I.5 Pekerjaan Lantai - RL. -
II PEKERJAAN PENANGKAL PETIR - -
III PEKERJAAN JARINGAN LAN -
III.1 Pekerjaan Lantai - 1 -
III.2 Pekerjaan Lantai - 2 -
III.3 Pekerjaan Lantai - 3 -
III.4 Pekerjaan Lantai - 4 -
NO URAIAN PEKERJAAN HARGA PEKERJAAN (Rp) JUMLAH HARGA (Rp)
1 2 3 4
E PEKERJAAN MEKANIKAL
I INSTALASI AIR BERSIH -
I.1 Pekerjaan Lantai - 1 -
I.2 Pekerjaan Lantai - 2 -
I.3 Pekerjaan Lantai - 3 -
I.4 Pekerjaan Lantai - 4 -
I.5 Pekerjaan Lantai -Atap dan Shaft -
II INSTALASI AIR KOTOR 29,498,208.00
II.1 Pekerjaan Lantai - 1 29,498,208.00
II.2 Pekerjaan Lantai - 2 -
II.3 Pekerjaan Lantai - 3 -
II.4 Pekerjaan Lantai - 4 -
II.5 Pekerjaan Lantai - RL. -
III PEKERJAAN TATA UDARA -
III.2 Pekerjaan Lantai - 2 -
III.3 Pekerjaan Lantai - 3 -
III.4 Pekerjaan Lantai - 4 -
IV PEKERJAAN PEMADAM KEBAKARAN - -
V PEKERJAAN LIFT ELEVATOR - -
PEMBULATAN 189,495,938,000.00
Terbilang : Seratus Delapan Puluh Sembilan Milyar Empat Ratus Sembilan Puluh Lima Juta Sembilan Ratus Tiga Puluh Delapan Ribu Rupiah
JUNAIDIN
Direktur
BILL OF QUANTITY (BOQ) SUB REKAP
GEDUNG AKUNTANSI
KEGIATAN : PEMBANGUNAN, REHABILITASI DAN RENOVASI SARANA PRASARANA INFRASTRUKTUR PERGURUAN TINGGI NEGERI
PEKERJAAN : PEMBANGUNAN GEDUNG AKUNTANSI, TEKNIK INFORMASI, TEKNIK SIPIL POLITEKNIK NEGERI SAMARINDA
LOKASI : KOTA SAMARINDA
HARGA PEKERJAAN
NO URAIAN PEKERJAAN JUMLAH HARGA (Rp)
(Rp)
1 2 3 4
1 2 3 4 6 7
I PEKERJAAN PENDAHULUAN
1 Penyiapan RK3K Terdiri atas
a Pembuatan manual prosedur, instruksi kerja
dan ijin kerja Ls 1.00 1,000,000.00 1,000,000.00
b Pembuatan Kartu Identitas Pekerja (KIP) Org 30.00 5,000.00 150,000.00
2 Sosialisasidan Promosi K3 terdiri atas : -
a Spanduk (banner) Lb 1.00 100,000.00 100,000.00
b Poster Lb 1.00 100,000.00 100,000.00
c Papan Informasi K3 Bh 1.00 100,000.00 100,000.00
3 Alat Pelindung Kerja terdiri atas : -
a Jaring Pengaman + Pemasangan ls 1.00 2,500,000.00 2,500,000.00
b Tali Keselamatan (lifeline) + Acesories Ls 1.00 3,000,000.00 3,000,000.00
c Pagar Pengaman (guard railling) Ls 1.00 15,000,000.00 15,000,000.00
d Pembatas Area Ls 1.00 1,500,000.00 1,500,000.00
4 Alat Pelindung Diri terdiri atas : -
a Topi Perlindungan Bh 30.00 40,000.00 1,200,000.00
b Pelindung Mata Psg 30.00 15,000.00 450,000.00
c Pelindung Pernapasan dan Mulut (Masker) Psg 30.00 5,000.00 150,000.00
d Sarung Tangan (Kulit, Katun dan Karet) Psg 30.00 8,000.00 240,000.00
e Sepatu Keselamatan Psg 30.00 125,000.00 3,750,000.00
f Rompi Keselamatan (Safety Vest) Psg 30.00 50,000.00 1,500,000.00
5 Asuransi dan Perijinan terdiri atas : -
a BPJS Ketenaga Kerjaandan esehatan Kerja, -
(Berdasarkan Kepmenaker No. Kep. 196/MEN/ -
1999, untuk Tenaga harian proyek Ls 1.00 4,750,000.00 4,750,000.00
6 Personil K3 terdiri atas : -
a Ahli K3 OB 4.00 7,550,000.00 30,200,000.00
c Petugas P3K Ob 4.00 3,500,000.00 14,000,000.00
7 Pasilitas sarana Kesehatan -
a Peralatan P3K (Kotak P3K , Tandu, Tabung Ls 1.00 5,000,000.00 5,000,000.00
Oksigen, Obat Luka, Perban dll. -
8 Rambu - Rambu terdiri atas : -
a Rambu Petunjuk Bh 2.00 650,000.00 1,300,000.00
b RambuLarangan Bh 2.00 650,000.00 1,300,000.00
c Rambu Peringatan Bh 2.00 650,000.00 1,300,000.00
d Rambu Kewajiban Bh 2.00 650,000.00 1,300,000.00
e Rambu Informasi Bh 2.00 650,000.00 1,300,000.00
9 Lain -Lain Terkait Pengendalian ResikoK3 -
a Bendera K3 Bh 1.00 650,000.00 650,000.00
b APAR Bh 1.00 200,000.00 200,000.00
TOTAL 92,040,000.00
BILL OF QUANTITY
GEDUNG AKUNTANSI
KEGIATAN : PEMBANGUNAN, REHABILITASI DAN RENOVASI SARANA PRASARANA INFRASTRUKTUR PERGURUAN TINGGI NEGERI
PEKERJAAN : PEMBANGUNAN GEDUNG AKUNTANSI, TEKNIK INFORMASI, TEKNIK SIPIL POLITEKNIK NEGERI SAMARINDA
LOKASI : KOTA SAMARINDA
NO URAIAN PEKERJAAN SAT. VOLUME HARGA SATUAN (Rp) JUMLAH HARGA (Rp) TOTAL HARGA (Rp)
1 2 3 4 5 6 7
II PEKERJAAN ARSITEKTUR
A. PEKERJAAN PASANGAN DINDING
- Lantai Besment (Elevasi - 3,23)
1 Railing Tangga Stainless Steel M' 12.00 - -
Jumlah -
1 2 3 4 5 6 7
1 2 3 4 5 6 7
9 PEK. JENDELA TYPE J5a. Uk 200 x 120 CM (1 unit)
- Pekerjaan Kusen Alumunium M' 9.95 - -
- Kaca 5 mm M² 1.44 - -
Jumlah -
- Lantai 3 (Elevasi + 8, 77)
1 PEK. PINTU TYPE P1a. 155 x 220 CM (1 Unit)
- Daun Pintu Kaca Tempered 12mm M² 3.41 - -
- Floor Hinge Bh 2.00 - -
- Pull Handle Bh 2.00 - -
- Patch Fitting Bh 1.00 - -
- Bottom pivot patch Bh 2.00 - -
- Top pivot patch Bh 2.00 - -
1 2 3 4 5 6 7
4 PEK. PINTU TYPE P3. uk 200 x 240 CM (2 Unit)
- Pekerjaan Kusen Alumunium M' 15.00 - -
- Daun Pintu Panel M² 11.20 - -
- Kaca 5 mm M² 1.18 - -
- Kunci Pintu Bh 2.00 - -
- Engsel tanam Bh 8.00 - -
- Espagnollete Tanam Bh 4.00 - -
- Finis Duco Milamin M² 22.40 - -
- Door Closer Bh 4.00 - -
1 2 3 4 5 6 7
11 PEK. PINTU TYPE PJ3. uk 325 x260 CM (2 Unit)
- Pekerjaan Kusen Alumunium M' 41.40 - -
- Daun Pintu Double Teakwood M² 5.04 - -
- Kaca 5 mm M² 9.02 - -
- Espagnollete Tanam Bh 2.00 - -
- Kunci Pintu Bh 2.00 - -
- Engsel Pintu Bh 12.00 - -
- Lapisan Sunblast M² 5.04 - -
- Finis Duco Milamin M² 10.08 - -
- Door Closer Bh 2.00 - -
1 2 3 4 5 6 7
17 PEK. JENDELA TYPE J3a. Uk 80 x 155 CM (2 Unit)
- Pekerjaan Kusen Alumunium M' 9.60 - -
- Jendela Type Alumunium + Kaca 5 mm M² 1.20 - -
- Kaca 5 mm M² 0.48 - -
- Engsel Jendela Bh 4.00 - -
- Handle Jendela Bh 2.00 - -
- Kaitan Angin Bh 4.00 - -
- Grendel Jendela Bh 4.00 - -
Jumlah -
- RL.1 Roof Tank (Elevasi + 12,77)
1 PEK. PINTU TYPE P4. uk 130x250 CM (2 Unit)
- Pekerjaan Kusen Alumunium M' 15.80 - -
- Daun Pintu Double Teakwood M² 5.20 - -
- Kaca 5 m M² 0.93 - -
- Kunci Pintu Bh 2.00 - -
- Engsel Pintu Bh 12.00 - -
- Espagnollete Tanam Bh 2.00 - -
- Finis Duco Milamin M² 10.40 - -
- Door Closer Bh 4.00 - -
Jumlah -
TOTAL : II. B. PEKERJAAN PINTU & JENDELA -
C. PEKERJAAN LANTAI
- Lantai Besment (Elevasi - 3,23)
1 Keramik Tangga 30/60 + (Granite Tile) M² 24.00 341,200.00 8,188,800.00
Jumlah 8,188,800.00
- Lantai 1 (Elevasi + 0, 77)
1 Keramik Tangga 30/60 + (Granite Tile) M² 41.19 341,200.00 14,054,028.00
Jumlah 14,054,028.00
NO URAIAN PEKERJAAN SAT. VOLUME HARGA SATUAN (Rp) JUMLAH HARGA (Rp) TOTAL HARGA (Rp)
1 2 3 4 5 6 7
- Lantai 2 (Elevasi + 4, 77)
1 Keramik Lantai 60/60 (Homogenus Tile) M² 843.06 411,800.00 347,172,108.00
2 Keramik Lantai 30/30 Km/Wc M² 69.53 282,100.00 19,614,413.00
3 Keramik Dinding Km/Wc M² 168.68 - -
4 Keramik Tangga 30/60 + (Granite Tile) M² 41.19 341,200.00 14,054,028.00
Jumlah 380,840,549.00
- Lantai 3 (Elevasi + 8, 77)
1 Keramik Lantai 60/60 (Homogenus Tile) M² 871.90 411,800.00 359,048,420.00
2 Keramik Lantai 30/30 Km/Wc M² 59.63 282,100.00 16,821,623.00
3 Keramik Dinding 20/25 Km/Wc M² 132.02 343,600.00 45,362,072.00
4 Keramik Tangga 30/60 + (Granite Tile) M² 29.04 341,200.00 9,908,448.00
Jumlah 431,140,563.00
TOTAL : II.C. PEKERJAAN LANTAI 834,223,940.00
D. PEKERJAAN PLAFOND
- Lantai Besment (Elevasi - 3,23)
1 Pas. Plafond Gypsum t 9 mm M² 58.05 - -
2 Pas. List Profil Gypsum Standart Lebar Sampai 5-10cm M' 38.00 32,600.00 1,238,800.00
Jumlah 1,238,800.00
- Lantai 2 (Elevasi + 4, 77)
1 Pas. Rangka Plafond Hollow M² 912.58 - -
2 Pas. Plafond Gypsum t 9 mm M² 693.06 - -
3 Plafond Calsiboard 4.5 mm M² 69.53 - -
4 List Plafond Gipsum Standart M' 781.78 32,600.00 25,486,028.00
Jumlah 25,486,028.00
- Lantai 3 (Elevasi + 8, 77)
1 Pas. Rangka Plafond Hollow M² 1,156.73 - -
2 Pas. Plafond Gypsum t 9 mm M² 870.74 - -
3 Plafond Calsiboard 4.5 mm M² 285.99 - -
4 List Plafond Gypsum Standart M' 901.40 32,600.00 29,385,640.00
Jumlah 29,385,640.00
- RL.1 Roof Tank (Elevasi + 12,77)
1 Pas. Rangka Plafond Hollow M² 252.90 - -
2 Plafond Calsiboard 4.5 mm M² 252.90 - -
3 List Plafond Kayu Profil M² 67.00 32,600.00 2,184,200.00
Jumlah 2,184,200.00
TOTAL : II.D. PEKERJAAN PLAFOND 58,294,668.00
E. PEKERJAAN FINISHING
- Lantai Besment (Elevasi - 3,23)
1 Cat Tembok Luar M² 207.71 - -
2 Cat Plafond M² 58.05 - -
Jumlah -
- Lantai 1 (Elevasi + 0, 77)
1 Cat Tembok Luar M² 507.13 - -
Jumlah -
- Lantai 2 (Elevasi + 4, 77)
1 Cat Tembok Luar M² 552.34 - -
2 Cat Tembok Dalam M² 1,190.19 - -
3 Cat Plafond M² 912.58 - -
Jumlah -
- Lantai 3 (Elevasi + 8, 77)
1 Cat Tembok Luar M² 428.00 - -
2 Cat Tembok Dalam M² 1,863.99 - -
3 Cat Plafond M² 1,156.73 - -
Jumlah -
- RL.1 roof tank (Elevasi +12,77)
1 Cat Tembok Luar M² 92.98 - -
2 Cat Tembok Dalam M² 175.77 - -
3 Cat Plafond M² 252.90 - -
4 Cat Listplank M² 71.63 - -
Jumlah -
TOTAL : II. E. PEKERJAAN FINISHING -
NO URAIAN PEKERJAAN SAT. VOLUME HARGA SATUAN (Rp) JUMLAH HARGA (Rp) TOTAL HARGA (Rp)
1 2 3 4 5 6 7
PEKERJAAN ATAP KANOPI
F.
- Lantai 1 (Elevasi + 0, 77)
1 Rangka Atap Besi Kotak 5/10 dan 5/5 M² 28.62 - -
2 Atap Spandek M² 28.62 - -
Jumlah -
TOTAL : II. F. PEKERJAAN ATAP KANOPI -
G. PEKERJAAN SANITAIR
- Lantai 1 (Elevasi + 0, 77)
1 Railing Disabilitas (besi stainless Steel Ø 2 " ) M' 6.20 - -
2 Dinding Partisi (rangka Hollow, GRC 9 mm) M² 4.80 - -
Jumlah -
- Lantai 2 (Elevasi + 4, 77)
1 Kloset Duduk Unit 5.00 - -
2 kloset Jongkok Unit 4.00 - -
3 Meja Wastafel Beton
- Pembesian kg 53.87 7,600.00 409,412.00
- begesting M² 5.99 418,100.00 2,504,419.00
- Plat Beton K175 Tbl 10 cm M³ 0.60 994,600.00 596,760.00
- Pas. Keramik 30x30 M² 5.99 282,100.00 1,689,779.00
4 Satu Wastafel+Kran+Instalasi Unit 1.00 - -
5 Dua Wastafel+Kran+Instalasi Unit 4.00 - -
6 Cermin 5 mm M² 3.78 - -
7 Kran air Jet washer + acsesories bh 9.00 - -
8 Kran Air bh 9.00 - -
9 Urinoir Unit 6.00 - -
10 Penyekat Urinoir bh 4.00 - -
11 Pemasangan Floor Drain bh 16.00 - -
Jumlah 5,200,370.00
- Lantai 3 (Elevasi + 8, 77)
1 Kloset Duduk Unit 4.00 - -
2 Kloset Jongkok Unit 4.00 - -
3 Meja Wastafel Beton
- Pembesian kg 53.87 7,600.00 409,412.00
- begesting M² 5.99 418,100.00 2,504,419.00
- Plat Beton K175 Tbl 10 cm M³ 0.60 994,600.00 596,760.00
- Pas. Keramik 30x30 M² 5.99 282,100.00 1,689,779.00
4 Satu Wastafel+Kran+Instalasi Unit 1.00 - -
5 Dua Wastafel+Kran+Instalasi Unit 4.00 - -
6 Cermin 5 mm M² 3.78 - -
7 Kran air Jet washer + acsesories bh 8.00 - -
8 Kran Air bh 8.00 - -
9 Urinoir Unit 6.00 - -
10 Penyekat Urinoir bh 4.00 - -
11 Pemasangan Floor Drain bh 13.00 - -
Jumlah 5,200,370.00
TOTAL : II. G. PEKERJAAN SANITAIR 10,400,740.00
H. PEKERJAAN HALAMAN
- Lantai 1 (Elevasi ± 0, 00)
1 Pekerjaan Selasar
- Galian Tanah M³ 2.91 85,640.00 249,212.40
- Pasangan Batu Gunung penahan tanah M³ 3.24 - -
- Pasangan Batu Bata 1 : 2 (selsara Gedung) M² 15.60 310,000.00 4,836,000.00
- Plesteran Pasangan M² 22.35 93,600.00 2,091,960.00
- Cor Rabat Selasar mutu fc 14,5 Mpa (K175) M³ 10.28 994,600.00 10,224,488.00
2 Pekerjaan Pengecoran Halaman
- Galian Tanah + Pembuangan M³ 40.86 142,340.00 5,816,012.40
- Pembesian kg 1,958.38 7,600.00 14,883,688.00
- Begesting M² 6.11 418,100.00 2,554,591.00
- Cor beton mutu fc 21,75 Mpa (K. 250) M³ 34.86 1,065,700.00 37,150,302.00
3 Pekerjaan Saluran Gedung
- Galian Tanah M³ 2.40 85,640.00 205,536.00
- Pasangan Batu Bata 1 : 2 (selsara Gedung) M² 12.00 310,000.00 3,720,000.00
- Plesteran Pasangan M² 12.00 93,600.00 1,123,200.00
- Cor Rabat Selasar mutu fc 14,5 Mpa (K175) M³ 0.63 994,600.00 626,598.00
- Pipa Pvc 4" M' 4.00 - -
NO URAIAN PEKERJAAN SAT. VOLUME HARGA SATUAN (Rp) JUMLAH HARGA (Rp) TOTAL HARGA (Rp)
1 2 3 4 5 6 7
4 Pembuatan Ramp Disabilitas
- Pembesian kg 75.60 7,600.00 574,560.00
- Begesting M² 4.00 418,100.00 1,672,400.00
- Cor Beton mutu fc 14,5 Mpa (K175) M³ 1.26 994,600.00 1,253,196.00
- Keramik Lantai 60/60 (unpolish Tile) M² 8.40 411,800.00 3,459,120.00
- Pasangan Guiding block M² 1.53 - -
- Railling Tangga Stainless Steel (disabilitas) M' 13.80 - -
Jumlah 90,440,863.80
- Lantai Besment (Elevasi - 3,23)
1 Pekerjaan Selasar
- Galian Tanah M³ 3.40 85,640.00 291,176.00
- Pasangan Batu Bata 1 : 2 (selasar Gedung) M² 34.00 310,000.00 10,540,000.00
- Plesteran Pasangan M² 34.00 93,600.00 3,182,400.00
- Cor Rabat Selasar mutu fc 14,5 Mpa (K175) M³ 8.50 994,600.00 8,454,100.00
2 Pekerjaan Saluran Gedung
- Galian Tanah M³ 7.84 85,640.00 671,417.60
- Pasangan Batu Bata 1 : 2 (selsara Gedung) M² 39.20 310,000.00 12,152,000.00
- Plesteran Pasangan M² 39.20 93,600.00 3,669,120.00
- Cor Beton Saluran mutu fc 14,5 Mpa (K175) M³ 6.86 994,600.00 6,822,956.00
3 Pekerjaan Halaman Parkir
- Urugan pasir t = 5cm M³ 49.61 174,400.00 8,651,984.00
- Cor Lantai Kerja mutu fc 7,4 Mpa (K100) t = 5 cm M³ 49.61 897,300.00 44,515,053.00
- Pembesian Kg 20,005.62 7,600.00 152,042,712.00
- Bekesting M² 505.20 418,100.00 211,224,120.00
- Cor beton mutu fc 26,4 Mpa (K300) M³ 218.99 1,100,800.00 241,064,192.00
- Kanstin Beton M' 104.53 239,300.00 25,014,029.00
Jumlah 728,295,259.60
TOTAL : II. H. PEKERJAAN HALAMAN 818,736,123.40
TOTAL : RAB ARSITEKTUR AKUTANSI 162,277,251,325.40
1 2 3 4 5 6 7
1 2 3 4 5 6 7
2 AC wall mounted, single split system : 18.000 BTUH
Instalasi Air Conditioning (AC) Lt 2 dan Lt 3
a. Unit air conditioning (AC) : unit 28.00 - -
- Fan coil unit (FCU) : wall mounted, single split system
Tipe : 18.000 BTUH
Kapasitas : Ruang Senat Jurusan
Servis : FCU.1-02
Kode unit : lantai 2 dan lantai 3
Lokasi
- Condensing uni : 1100 W / 220 V / 1 Ph / 50 Hz
Konsumsi daya : CU.1-02
Kode unit : outdoor lantai 1
Lokasi
a. Pipa refrigerant m 30.00 - -
b. Instalasi kabel daya : NYM 3 x 2,5 mm2 m 68.00 - -
c. Instalasi pipa drain/kondensat AC :
- Pipa drain/kondensat AC ø 20 mm m 14.00 - -
d. Fitting & aksesoris pipa drain/kondensat AC ls 1.00 - -
1 2 3 4 5 6 7
1 2 3 4 5 6 7
4 Kotak Kontak
- Kotak Kontak Biasa 1 Fasa 15 A, 250 VAC bh 46.00 - -
- Kotak Kontak Ceiling1 Fasa 15 A, 250 VAC bh 8.00 - -
- Instalasi Penerangan Kabel Dalam Pipa Kondui uPVC titik 54.00 - -
5 LD PROYEKTOR
- LCD Proyectore (XGA 1024x 768 - 3000 lumean) bh 8.00 - -
- Tiang Penggantung LCD Otomatis unit 8.00 - -
- Instalasi Penerangan Kabel Dalam Pipa Kondul uPVC ttk 8.00 - -
- Kotak Kontak 1 Fasa 15 A 250 VAC bh 8.00 - -
- Kabel Data HDMI m 120.00 - -
- Autlet Data bh 8.00 - -
6 Test commisioning lantai - 2 (elevasi + 4,77) ls 1.00 - -
TOTAL : IV. A. PEKERJAAN LANTAI 2 -
KEGIATAN : PEMBANGUNAN, REHABILITASI DAN RENOVASI SARANA PRASARANA INFRASTRUKTUR PERGURUAN TINGGI NEGERI
PEKERJAAN : PEMBANGUNAN GEDUNG AKUNTANSI, TEKNIK INFORMASI, TEKNIK SIPIL POLITEKNIK NEGERI SAMARINDA
LOKASI : KOTA SAMARINDA
I PEKERJAAN PENDAHULUAN - -
VI PEKERJAAN ARSITEKTUR
A PEKERJAAN PASANGAN DINDING 2,427,289,397.00
- Lantai 1 (Elv. - 4.00) 740,164,766.00
- Lantai 2 (Elevasi ± 0.00) 794,174,889.00
- Lantai 3 (Elevasi ± 4.00) 806,000,922.00
- RL.1 (Elevasi +8,8.000) 86,948,820.00
B PEKERJAAN PINTU/ JENDELA -
- Lantai 1 (Elv. - 4.00) -
- Lantai 2 (Elevasi ± 0.00) -
- Lantai 3 (Elevasi ± 4.00) -
C PEKERJAAN LANTAI 1,146,490,288.80
- Lantai 1 (Elv. - 4.00) 426,044,685.60
- Lantai 2 (Elevasi ± 0.00) 364,294,149.60
- Lantai 3 (Elevasi ± 4.00) 356,151,453.60
D PEKERJAAN PLAFOND -
- Lantai 1 (Elv. - 4.00) -
- Lantai 2 (Elevasi ± 0.00) -
- Lantai 3 (Elevasi ± 4.00) -
- RL.1 (Elevasi +8,8.000) -
E PEKERJAAN FINISHING -
- Lantai 1 (Elv. - 4.00) -
- Lantai 2 (Elevasi ± 0.00) -
- Lantai 3 (Elevasi ± 4.00) -
- RL.1 (Elevasi +8,8.000) -
F PEKERJAAN SANITAIR 1,281,069.00
- Lantai 1 (Elv. - 4.00) 427,023.00
- Lantai 2 (Elevasi ± 0.00) 427,023.00
- Lantai 3 (Elevasi ± 4.00) 427,023.00
NO URAIAN PEKERJAAN HARGA PEKERJAAN (Rp) JUMLAH HARGA (Rp)
1 2 3 4
IX PEKERJAAN MEKANIKAL
A PEKERJAAN INSTALASI AIR BERSIH -
- Toilet Lantai - 1 ( Elevasi - 4.00) -
- Toilet Lantai - 2 ( Elevasi ±0.00 ) -
- Toilet Lantai - 3 ( Elevasi ± 4.00 ) -
- Pek. Intalasi Air Bersih Lantai RL -
B PEK. INSTALASI AIR BUANGAN, AIR KOTOR & AIR HUJAN 260,040.00
- Toilet Lantai - 1( Elev.± -4.00) 260,040.00
- Toilet Lantai - 2 ( Elev.± 0.00) -
- Toilet Lantai - 3 ( Elev.± 4.00) -
C PEKERJAAN INSTALASI AIR CONDITIONING (AC) - -
D PEKERJAAN INSTALASI APAR (PEMADAM KEBAKARAN) - -
E PEKERJAAN INSTALASI EXHAUST FAN - -
F PEKERJAAN INSTALASI FIRE ALARM - -
X PEKERJAAN ELEKTRIKAL -
A PEKERJAAN LANTAI - 1 (Elev. - 4.00) -
B PEKERJAAN LANTAI - 2 (Elev. ± 0.00) -
C PEKERJAAN LANTAI - 3 (Elev. ± 4.00) -
D PEKERJAAN LANTAI ATAP/PETIR -
JUMLAH 8,657,072,006.83
BILL OF QUANTITY (BOQ) GEDUNG
GEDUNG TEKNIK SIPIL
KEGIATAN : PEMBANGUNAN, REHABILITASI DAN RENOVASI SARANA PRASARANA INFRASTRUKTUR PERGURUAN TINGGI NEGERI
PEKERJAAN : PEMBANGUNAN GEDUNG AKUNTANSI, TEKNIK INFORMASI, TEKNIK SIPIL POLITEKNIK NEGERI SAMARINDA
LOKASI : KOTA SAMARINDA
1 2 3 4 5 6
Keselamatan dan Kesehatan Kerja
1
- Penyiapan RK3K Terdiri atas
a Pembuatan manual prosedur, instruksi kerja
dan ijin kerja Ls 1.00 - -
b Pembuatan Kartu Identitas Pekerja (KIP) Org 30.00 - -
- Sosialisasidan Promosi K3 terdiri atas :
a Spanduk (banner) Lb 4.00 - -
b Poster Lb 2.00 - -
c Papan Informasi K3 Bh 2.00 - -
- Alat Pelindung Kerja terdiri atas :
a Jaring Pengaman Ls 1.00 - -
b Tali Keselamatan (lifeline) Ls 1.00 - -
c Pagar Pengaman (guard railling) Ls 1.00 - -
d Pembatas Area Ls 1.00 - -
- Alat Pelindung Diri terdiri atas :
a Helm Sefety Bh 25.00 - -
b Pelindung Mata Psg 60.00 - -
c Pelindung Pernapasan dan Mulut (Masker) Psg 60.00 - -
d Sarung Tangan (Kulit, Katun dan Karet) Psg 60.00 - -
e Sepatu Keselamatan Psg 60.00 - -
f Rompi Keselamatan (safety Vest) Psg 15.00 - -
- Asuransi dan Perijinan terdiri atas :
a BPJS Ketenaga Kerjaandan esehatan Kerja,
(Berdasarkan Kepmenaker No. Kep. 196/MEN/ -
1999, untuk Tenaga harian proyek Ls 1.00 - -
- Personil K3 terdiri atas :
a Ahli K3 OB 4.00 - -
b Petugas Tanggap Darurat OB 4.00 - -
c PetugasK3 OB 4.00 - -
- Pasilitas sarana Kesehatan
a Peralatan P3K (Kotak P3K , Tandu, Tabung Ls 1.00 - -
Oksigen, Obat Luka, Perban dll.
- Rambu - Rambu terdiri atas :
a Rambu Petunjuk Bh 4.00 - -
b RambuLarangan Bh 4.00 - -
c Rambu Peringatan Bh 4.00 - -
d Rambu Kewajiban Bh 4.00 - -
e Rambu Informasi Bh 4.00 - -
- Lain -Lain Terkait Pengendalian ResikoK3
a Alat Pemadam ApiRingan (Apar); 3,3 kg Bh 1.00 - -
b Bendera K3 Bh 4.00 - -
c Pelaporan dan Penyelidikan Insiden Ls 1.00 - -
Jumlah -
BILL OF QUANTITY (BOQ)
GEDUNG TEKNIK SIPIL
KEGIATAN : PEMBANGUNAN, REHABILITASI DAN RENOVASI SARANA PRASARANA INFRASTRUKTUR PERGURUAN TINGGI NEGERI
PEKERJAAN : PEMBANGUNAN GEDUNG AKUNTANSI, TEKNIK INFORMASI, TEKNIK SIPIL POLITEKNIK NEGERI SAMARINDA
LOKASI : KOTA SAMARINDA
1 2 3 4 5 6 7
I PEKERJAAN PENDAHULUAN
2 Bowplank + Pengukuran lokasi + Pematokan M' 175.00 - -
3 Pembersihan Lahan/Stripping M² 346.50 - -
4 Mobilisasi/Demobilisasi Ls 1.00 - -
1 2 3 4 5 6 7
2 Pondasi Type B 160x 160 x 50 cm fc' 26,4 Mpa
Pembesian Ulir Kg 6,232.41 7,600.00 47,366,316.00
Bekesting / Cetakan Untuk Pondasi M² 60.80 418,100.00 25,420,480.00
Beton fc 26,4 Mpa M³ 24.32 1,100,800.00 26,771,456.00
3 Pondasi Type C 155x 155 x 50 cm fc' 26,4 MPa
Pembesian Ulir Kg 734.22 7,600.00 5,580,072.00
Bekesting / Cetakan Untuk Pondasi M² 9.30 418,100.00 3,888,330.00
Beton fc 26,4 Mpa M³ 3.60 1,100,800.00 3,962,880.00
4 Pondasi Type D 155x 155 x 50 cm fc' 26,4 MPa
Pembesian Ulir Kg 1,122.07 7,600.00 8,527,732.00
Bekesting / Cetakan Untuk Pondasi M² 9.92 418,100.00 4,147,552.00
Beton fc 26,4 Mpa M³ 3.84 1,100,800.00 4,227,072.00
5 Pondasi Type E110 x 110 x 40 cm fc' 26,4 MPa
Pembesian Ulir Kg 114.42 7,600.00 869,592.00
Bekesting / Cetakan Untuk Pondasi M² 1.76 418,100.00 735,856.00
Beton fc 26,4 Mpa M³ 0.48 1,100,800.00 528,384.00
6 Pondasi Type F120 x 120 x 40 cm fc' 26,4 MPa
Pembesian Ulir Kg 1,094.70 7,600.00 8,319,720.00
Bekesting / Cetakan Untuk Pondasi M² 19.20 418,100.00 8,027,520.00
Beton fc 26,4 Mpa M³ 5.76 1,100,800.00 6,340,608.00
7 Kolom K1 35x50 fc' 26,4 MPa
Pembesian Ulir Kg 893.33 7,600.00 6,789,308.00
Pembesian Polos Kg 138.24 7,600.00 1,050,624.00
Bekesting / Cetakan Untuk Kolom M² 34.00 418,100.00 14,215,400.00
Beton fc 26,4 Mpa M³ 3.68 1,100,800.00 4,050,944.00
8 Kolom K2 40x40 fc' 26,4 MPa
Pembesian Ulir Kg 6,485.60 7,600.00 49,290,560.00
Pembesian Polos Kg 1,227.60 7,600.00 9,329,760.00
Bekesting / Cetakan Untuk Kolom M² 309.76 308,100.00 95,437,056.00
Beton fc 26,4 Mpa M³ 30.98 1,100,800.00 34,102,784.00
9 Kolom K3 35x35 fc' 26,4 MPa
Pembesian Ulir Kg 170.28 7,600.00 1,294,128.00
Pembesian Polos Kg 48.36 7,600.00 367,536.00
Bekesting / Cetakan Untuk Kolom M² 12.40 308,100.00 3,820,440.00
Beton fc' 26,4 MPa M³ 1.09 1,100,800.00 1,199,872.00
10 Balok Tee Bim 25x40 fc' 26,4 MPa
Pembesian Ulir Kg 6,099.64 7,600.00 46,357,264.00
Besi Polos Kg 1,953.60 7,600.00 14,847,360.00
Bekesting / Cetakan Untuk Sloof M² 318.24 223,400.00 71,094,816.00
Beton fc' 26,4 MPa M³ 47.74 1,100,800.00 52,552,192.00
11 Balok Tee Bim 20x30 fc' 26,4 MPa
Pembesian Ulir Kg 205.77 7,600.00 1,563,852.00
Pembesian Polos Kg 56.88 7,600.00 432,288.00
Bekesting / Cetakan Untuk Sloof M² 7.02 223,400.00 1,568,268.00
Beton fc' 26,4 MPa M³ 0.70 1,100,800.00 770,560.00
12 Plat Lantai Dasar t= 12 cm fc' 26,4 MPa
Pembesian Polos Kg 13,824.54 7,600.00 105,066,504.00
Bekisting/Perancah Lantai M² 21.82 418,100.00 9,122,942.00
Beton fc' 26,4 MPa M³ 102.75 1,100,800.00 113,107,200.00
13
Pek. Beton Tangga t = 15 cm
Pembesian Ulir Kg 591.44 7,600.00 4,494,944.00
Pembesian Polos Kg 583.42 7,600.00 4,433,992.00
Bekesting / Cetakan Untuk Tangga M² 46.54 418,100.00 19,458,374.00
Beton fc' 26,4 MPa M³ 6.03 1,100,800.00 6,637,824.00
14 Cor Lantai Selasar Gedung
Pembesian Polos Kg 730.79 7,600.00 5,554,004.00
Bekesting / Cetakan Untuk Sloof M² 11.75 223,400.00 2,624,950.00
Beton fc' 26,4 MPa M³ 8.23 1,100,800.00 9,059,584.00
Jumlah 939,959,446.00
1 2 3 4 5 6 7
Bekesting / Cetakan Untuk Balok M² 249.04 311,000.00 77,451,440.00
Beton fc' 26,4 MPa M³ 37.36 1,100,800.00 41,125,888.00
3 Balok 5 20x30 fc' 26,4 MPa
Pembesian Ulir Kg 142.90 7,600.00 1,086,040.00
Pembesian Polos Kg 2.16 7,600.00 16,416.00
Bekesting / Cetakan Untuk Balok M² 6.12 311,000.00 1,903,320.00
Beton fc' 26,4 MPa M³ 0.61 1,100,800.00 671,488.00
4 Balok 6 15x20 fc' 26,4 Mpa
Pembesian Ulir Kg 211.45 7,600.00 1,607,020.00
Pembesian Polos Kg 35.55 7,600.00 270,180.00
Bekesting / Cetakan Untuk Sloof M² 32.77 223,400.00 7,320,818.00
Beton fc' 26,4 MPa M³ 2.46 1,100,800.00 2,707,968.00
5 Pek. Plat Lantai t = 12 cm fc' 26,4 MPa
Pembesian Polos Kg 8,816.94 7,600.00 67,008,744.00
Bekisting/Perancah Lantai M² 549.37 7,600.00 4,175,212.00
Beton fc' 26,4 MPa M³ 64.15 1,100,800.00 70,616,320.00
6 Pek. Plat Lantai tribun minit = 12 cm fc' 26,4 MPa
Pembesian Ulir Kg 4,715.80 7,600.00 35,840,080.00
Pembesian Polos Kg 1,347.84 7,600.00 10,243,584.00
Bekisting/Perancah Lantai M² 129.60 418,100.00 54,185,760.00
Beton fc' 26,4 MPa M³ 15.55 1,100,800.00 17,117,440.00
7 Pek. Plat Kanopi t = 10 cm fc' 26,4 MPa
Pembesian Polos Kg 1,069.64 7,600.00 8,129,264.00
Bekisting/Perancah Lantai M² 67.50 418,100.00 28,221,750.00
Beton fc' 26,4 MPa M³ 15.69 1,100,800.00 17,271,552.00
8 Kolom K1 35x50 fc' 26,4 MPa
Pembesian Ulir Kg 1,179.20 7,600.00 8,961,920.00
Pembesian Polos Kg 178.56 7,600.00 1,357,056.00
Bekesting / Cetakan Untuk Kolom M² 45.90 308,100.00 14,141,790.00
Beton fc' 26,4 MPa M³ 4.73 1,100,800.00 5,206,784.00
9 Kolom K2 40x40 fc' 26,4 MPa
Pembesian Ulir Kg 6,485.60 7,600.00 49,290,560.00
Pembesian Polos Kg 1,227.60 7,600.00 9,329,760.00
Bekesting / Cetakan Untuk Kolom M² 309.76 308,100.00 95,437,056.00
Beton fc' 26,4 MPa M³ 30.98 1,100,800.00 34,102,784.00
10 Kolom K3 35x35 fc' 26,4 MPa
Pembesian Ulir Kg 196.53 7,600.00 1,493,628.00
Pembesian Polos Kg 48.36 7,600.00 367,536.00
Bekesting / Cetakan Untuk Kolom M² 12.32 308,100.00 3,795,792.00
Beton fc' 26,4 MPa M³ 1.08 1,100,800.00 1,188,864.00
11 Kolom KP1 10x18 fc' 26,4 MPa
Pembesian Polos Kg 1,159.93 7,600.00 8,815,468.00
Bekesting / Cetakan Untuk Kolom M² 38.80 308,100.00 11,954,280.00
Beton fc' 26,4 MPa M³ 3.33 1,100,800.00 3,665,664.00
12 Pek. Beton Tangga t = 15 cm
Pembesian Ulir Kg 591.44 7,600.00 4,494,944.00
Pembesian Polos Kg 583.42 7,600.00 4,433,992.00
Bekesting / Cetakan Untuk Tangga M² 46.54 418,100.00 19,458,374.00
Beton fc' 26,4 MPa M³ 6.03 1,100,800.00 6,637,824.00
13 Pekerjaan Waterproofing M² 131.00 - -
Jumlah 910,324,988.00
- Lantai 3 (Elevasi ± 4.00)
1 Balok 30x50 fc' 26,4 MPa
Pembesian Ulir Kg 4,257.56 7,600.00 32,357,456.00
Pembesian Polos Kg 1,891.80 7,600.00 14,377,680.00
Bekesting / Cetakan Untuk Balok M² 225.00 311,000.00 69,975,000.00
Beton fc' 26,4 MPa M³ 33.75 1,100,800.00 37,152,000.00
2 Balok 25x40 fc' 26,4 MPa
Pembesian Ulir Kg 4,209.52 7,600.00 31,992,352.00
Pembesian Polos Kg 1,300.68 7,600.00 9,885,168.00
Bekesting / Cetakan Untuk Balok M² 245.52 311,000.00 76,356,720.00
Beton fc' 26,4 MPa M³ 36.83 1,100,800.00 40,542,464.00
JUMLAH HARGA TOTAL HARGA
NO URAIAN PEKERJAAN SAT. VOLUME HARGA SATUAN (Rp)
( Rp ) ( Rp )
1 2 3 4 5 6 7
3 Balok 5 20x30 fc' 26,4 MPa
Pembesian Ulir Kg 836.37 7,600.00 6,356,412.00
Pembesian Polos Kg 253.88 7,600.00 1,929,488.00
Bekesting / Cetakan Untuk Balok M² 42.06 311,000.00 13,080,660.00
Beton fc' 26,4 MPa M³ 4.21 1,100,800.00 4,634,368.00
3 Pek. Plat Lantai t = 12 cm fc' 26,4 MPa
Pembesian Polos Kg 16,598.10 7,600.00 126,145,560.00
Bekisting/Perancah Lantai M² 829.18 418,100.00 346,680,158.00
Beton fc' 26,4 MPa M³ 97.14 1,100,800.00 106,931,712.00
4 Pek. Plat Atap Kanopi t = 10 cm fc' 26,4 MPa
Pembesian Polos Kg 1,190.60 7,600.00 9,048,560.00
Bekisting/Perancah Lantai M² 152.88 418,100.00 63,919,128.00
Beton fc' 26,4 MPa M³ 13.89 1,100,800.00 15,290,112.00
5 Kolom K2 40x40 fc' 26,4 MPa
Pembesian Ulir Kg 6,485.60 7,600.00 49,290,560.00
Pembesian Polos Kg 1,227.60 7,600.00 9,329,760.00
Bekesting / Cetakan Untuk Kolom M² 309.76 308,100.00 95,437,056.00
Beton fc' 26,4 MPa M³ 30.98 1,100,800.00 34,102,784.00
6 Kolom K3 35x35 fc' 26,4 MPa
Pembesian Ulir Kg 196.53 7,600.00 1,493,628.00
Pembesian Polos Kg 48.36 7,600.00 367,536.00
Bekesting / Cetakan Untuk Kolom M² 12.32 308,100.00 3,795,792.00
Beton fc' 26,4 MPa M³ 1.08 1,100,800.00 1,188,864.00
7 Kolom K1 35x50 fc' 26,4 MPa
Pembesian Ulir Kg 1,572.27 7,600.00 11,949,252.00
Pembesian Polos Kg 238.08 7,600.00 1,809,408.00
Bekesting / Cetakan Untuk Kolom M² 61.20 308,100.00 18,855,720.00
Beton fc' 26,4 MPa M³ 6.30 1,100,800.00 6,935,040.00
8 Pekerjaan Waterproofing M² 138.88 - -
Jumlah 1,241,210,398.00
- RL. (Elevasi +7,80)
1 Balok 15x20 cm fc' 18.67 MPa
Pembesian Ulir Kg 238.62 7,600.00 1,813,512.00
Pembesian Polos Kg 72.72 7,600.00 552,672.00
Bekesting / Cetakan Untuk Balok M² 77.22 311,000.00 24,015,420.00
Beton fc' 26,4 MPa M³ 4.21 1,100,800.00 4,634,368.00
2 Balok 20x30 cm fc' 26,4 MPa
Pembesian Ulir Kg 593.80 7,600.00 4,512,880.00
Pembesian Polos Kg 97.20 7,600.00 738,720.00
Bekesting / Cetakan Untuk Balok M² 16.00 311,000.00 4,976,000.00
Beton fc' 26,4 MPa M³ 1.20 1,100,800.00 1,320,960.00
3 Pek. Plat Dak t = 12 cm fc' 26,4 MPa
Pembesian Polos Kg 499.88 7,600.00 3,799,088.00
Bekisting/Perancah Lantai M² 22.37 418,100.00 9,352,897.00
Beton fc' 26,4 MPa M³ 2.42 1,100,800.00 2,663,936.00
4 Pek. Plat Kanopi t = 10 cm fc' 26,4 MPa
Pembesian Ulir Kg 3,105.84 7,600.00 23,604,384.00
Bekisting/Perancah Lantai M² 135.52 418,100.00 56,660,912.00
Beton fc' 26,4 MPa M³ 12.32 1,100,800.00 13,561,856.00
5 Pekerjaan Waterproofing M² 143.36 - -
Jumlah 152,207,605.00
- RL.2 (Elevasi +9.51)
1 Balok 20x30 cm fc' 26,4 MPa
Pembesian Ulir Kg 3,958.61 7,600.00 30,085,436.00
Pembesian Polos Kg 1,150.92 7,600.00 8,746,992.00
Bekesting / Cetakan Untuk Balok M² 255.60 311,000.00 79,491,600.00
Beton fc' 26,4 MPa M³ 19.17 1,100,800.00 21,102,336.00
2 Balok 25x40 fc' 26,4 MPa
Pembesian Ulir Kg 388.96 7,600.00 2,956,096.00
Pembesian Polos Kg 126.00 7,600.00 957,600.00
Bekesting / Cetakan Untuk Balok M² 20.88 311,000.00 6,493,680.00
Beton fc' 26,4 MPa M³ 3.13 1,100,800.00 3,445,504.00
Jumlah 153,279,244.00
1 2 3 4 5 6 7
V. PEKERJAAN RANGKA KUDA - KUDA DAN ATAP
1 Pek. Kuda - kuda Baja Siku Kg 47,562.28 - -
2 Pek. Gording Kanal C Kg 8,728.82 - -
3 Pek. Tie Rod/Ikatan Angin Kg 117.70 - -
4 Pek. Plat Simpul Kg 4,322.75 - -
5 Pas .Baut Ø 16 mm bh 4,838.00 - -
6 Pas. Angkur Ø 22 - h. 50 cm bh 148.00 - -
7 Pek. Pas. Rangka Atap genteng metal (Baja Ringan) M² 897.50 - -
8 Pek. Pas. Atap Metal M² 897.50 - -
9 Pek. Talang Jurai dalam M' 21.80 - -
10 Pek. Bubungan Atap M' 97.50 - -
11 Pas.LisplanK GRC 9/30 CM M' 135.50 - -
1 2 3 4 5 6 7
1 2 3 4 5 6 7
Jumlah -
1 2 3 4 5 6 7
Jumlah -
- Lantai 3 (Elevasi ± 4.00)
1 PEK. PINTU TYPE PH1. 170 x 280 CM (1 Unit)
- Kusen Pintu Allumunium M' 34.90 - -
- Daun Pintu Kaca Tempered 12 mm M² 4.08 - -
- Kaca t = 5 mm M² 4.33 - -
- Engsel Pintu + Aksesories Bh 1.00 - -
- Kunci Pintu + Aksesories Bh 1.00 - -
- Handle Pintu Bh 2.00 - -
JUMLAH HARGA TOTAL HARGA
NO URAIAN PEKERJAAN SAT. VOLUME HARGA SATUAN (Rp)
( Rp ) ( Rp )
1 2 3 4 5 6 7
1 2 3 4 5 6 7
Jumlah -
D. PEKERJAAN PLAFOND
- Lantai 1 (Elv. - 4.00)
1 Pas. Rangka Plapond Hollow M² 651.20 - -
2 Pas. Plapond Gypsum t 9 mm M² 629.15 - -
3 Plafond Kalsibord 4.5 mm M² 22.05 - -
5 Pas. List Profil Gipsum Standart Lebar Sampai 5-10cm M' 453.10 - -
Jumlah -
- Lantai 2 (Elevasi ± 0.00)
1 Pas. Rangka Plapond Hollow M² 616.95 - -
2 Pas. Plapond Gypsum t 9 mm M² 749.70 - -
3 Plafond Kalsibord 4.5 mm M² 29.25 - -
5 Pas. List Profil Gipsum Standart Lebar Sampai 5-10cm M' 363.70 - -
Jumlah -
- Lantai 3 (Elevasi ± 4.00)
1 Pas. Rangka Plapond Hollow M² 872.58 - -
2 Pas. Plapond Gypsum t 9 mm M² 850.53 - -
3 Plafond Kalsibord 4.5 mm M² 22.05 - -
4 List Plafond Gipsum Standart M' 454.00 - -
Jumlah -
JUMLAH HARGA TOTAL HARGA
NO URAIAN PEKERJAAN SAT. VOLUME HARGA SATUAN (Rp)
( Rp ) ( Rp )
1 2 3 4 5 6 7
- RL.1 (Elevasi +8,8.000)
1 Pas. Rangka Plapond Hollow M² 108.00 - -
2 Plafond Kalsibord 4.5 mm M² 108.00 - -
3 List Plafond Gipsum Standart M' 230.00 - -
Jumlah -
TOTAL : VI.D. PEKERJAAN PLAFOND -
E. PEKERJAAN FINISHING
- Lantai 1 (Elv. - 4.00)
1 Cat Tembok Luar M² 656.54 - -
2 Cat Tembok Dalam M² 1,275.35 - -
3 Cat Plafond M² 716.00 - -
Jumlah -
- Lantai 2 (Elevasi ± 0.00)
1 Cat Tembok Luar M² 822.00 - -
2 Cat Tembok Dalam M² 1,227.53 - -
3 Cat Plafond M² 616.95 - -
Jumlah -
- Lantai 3 (Elevasi ± 4.00)
1 Cat Tembok Luar M² 545.79 - -
2 Cat Tembok Dalam M² 1,329.66 - -
3 Cat Plafond M² 872.58 - -
Jumlah -
- RL.1 (Elevasi +8,8.000)
1 Cat Tembok Luar M² 158.55 - -
2 Cat Plafond M² 108.00 - -
3 Cat lis plapond M² 13.50 - -
4 Cat Listplang M² 40.50 - -
Jumlah -
F. PEKERJAAN SANITAIR
- Lantai 1 (Elv. - 4.00)
1 Klosed Jongkok Unit 2.00 - -
2 Klosed Duduk Unit 2.00 - -
3 Bak Air Fibber glass kap.0,30m3 Unit 1.00 - -
4 Bioseptic tank (kapasitas 7 m3) Unit 1.00 - -
5 Urinoir Unit 2.00 - -
6 Penyekat Urinoir Unit 1.00 - -
7 Meja Wastafel Beton
- Pembesian kg 19.44 7,600.00 147,744.00
- begesting M² 1.44 - -
- Plat Beton K150 Tbl 10 cm M³ 0.36 - -
- Pas. Keramik 30x30 M² 0.99 282,100.00 279,279.00
8 Satu Wastafel+Kran+Instalas Unit 1.00 - -
9 Dua Wastafel+Kran+Instalasi Unit 1.00 - -
10 Bak Cuci Piring Stainlessteel Unit 1.00 - -
11 Pasanga Kaca Cermin 5 mm M² 2.52 - -
12 Kran air Jet washer + acsesories bh 2.00 - -
13 Kran Air bh 4.00 - -
14 Flour drain bh 6.00 - -
15 Reling Tangga Disabilitas M' 3.50 - -
Jumlah 427,023.00
- Lantai 2 (Elevasi ± 0.00)
1 Klosed Duduk Unit 2.00 - -
2 Klosed Jongkok Unit 1.00 - -
3 Bak Air Fibber glass kap.0,30m3 Unit 1.00 - -
4 Meja Wastafel Beton
- Pembesian kg 19.44 7,600.00 147,744.00
- begesting M² 1.44 - -
- Plat Beton K150 Tbl 10 cm M³ 0.36 - -
- Pas. Keramik 30x30 M² 0.99 282,100.00 279,279.00
5 Satu Wastafel+Kran+Instalasi+Meja Beton Unit 1.00 - -
6 Dua Wastafel+Kran+Instalasi+Meja Beton Unit 1.00 - -
7 Pasanga Kaca Cermin 5 mm M² 2.52 - -
8 Kran air Jet washer + acsesories bh 2.00 - -
9 Kran Air bh 7.00 - -
10 Flour drain bh 7.00 - -
11 Reling Tangga Disabilitas M' 6.00 - -
Jumlah 427,023.00
JUMLAH HARGA TOTAL HARGA
NO URAIAN PEKERJAAN SAT. VOLUME HARGA SATUAN (Rp)
( Rp ) ( Rp )
1 2 3 4 5 6 7
- Lantai 3 (Elevasi ± 4.00)
1 Klosed Duduk Unit 2.00 - -
2 Klosed Jongkok Unit 1.00 - -
3 Bak Air Fibber glass kap.0,30m3 Unit 1.00 - -
4 Meja Wastafel Beton
- Pembesian kg 19.44 7,600.00 147,744.00
- begesting M² 1.44 - -
- Plat Beton K150 Tbl 10 cm M³ 0.36 - -
- Pas. Keramik 30x30 M² 0.99 282,100.00 279,279.00
5 Satu Wastafel+Kran+Instalasi+Meja Beton Unit 1.00 - -
6 Dua Wastafel+Kran+Instalasi+Meja Beton Unit 1.00 - -
7 Kran air Jet washer + acsesories bh 2.00 - -
8 Pasangan Kaca Cermin 5 mm M² 2.52 - -
9 Kran Air bh 3.00 - -
10 Urinoir Unit 2.00 - -
11 Penyekat Urinoir bh 1.00 - -
12 Flour drain bh 5.00 - -
Jumlah 427,023.00
1 2 3 4 5 6 7
2 Pek. Plat Lantai t = 12 cm fc' 26,4 MPa
Pembesian Polos Kg 1,381.68 7,600.00 10,500,768.00
Bekisting/Perancah Lantai M² 97.72 418,100.00 40,856,732.00
Beton fc' 26,4 MPa M³ 11.66 1,100,800.00 12,835,328.00
3 Kolom K1 35x50 fc' 26,4 MPa
Pembesian Ulir Kg 1,572.27 7,600.00 11,949,252.00
Pembesian Polos Kg 238.08 7,600.00 1,809,408.00
Bekesting / Cetakan Untuk Kolom M² 54.40 308,100.00 16,760,640.00
Beton fc' 26,4 MPa M³ 5.60 1,100,800.00 6,164,480.00
4 Pek. Plat Atap Kanopi t = 10 cm fc' 26,4 MPa
Pembesian Polos Kg 416.58 7,600.00 3,166,008.00
Bekisting/Perancah Lantai M² 49.14 418,100.00 20,545,434.00
Beton fc' 26,4 MPa M³ 5.90 1,100,800.00 6,494,720.00
5 Pekerjaan Waterproofing M² 117.00 - -
Jumlah 328,943,319.83
1 2 3 4 5 6 7
B. Pekerjaan Ramp Disabilitas
1 Galian Tanah M³ 1.67 85,640.00 143,018.80
2 Pas. Pondasi Batu Gunung M³ 2.14 - -
3 Urungan Pasir t = 5 cm M³ 1.43 174,400.00 249,392.00
4 Besi Beton Ø 10 - 15 cm kg 262.64 8,380.00 2,200,923.20
5 Begesting M² 5.00 418,100.00 2,090,500.00
6 Cor beton mutu fc 16,9 Mpa M³ 1.63 1,026,300.00 1,672,869.00
7 Keramik Lantai 60/60 (unpolish Tile) M² 22.50 411,800.00 9,265,500.00
8 Pasangan Guiding block M² 7.50 427,000.00 3,202,500.00
9 Relling Tangga Standlisteel (disabilitas) M' 50.00 - -
Jumlah 18,824,703.00
C. Pekerjaan Tangga Darurat
1 Galian Tanah M³ 1.67 85,640.00 143,018.80
2 Pek. Pacang Ulin 10/10 - 2 m titik 4.00 250,500.00 1,002,000.00
3 Pas. Pondasi Batu Gunung M³ 2.14 - -
4 Pekerjaan Beton Sloof 20/25
- Pembesian Polos kg 34.48 7,600.00 262,048.00
- Bekesting / Cetakan Untuk Sloof M² 2.50 223,400.00 558,500.00
- Beton fc' 26,4 MPa M³ 0.35 1,100,800.00 385,280.00
5 Cor Beton Lantai t = 10 cm mutu fc 16,9 Mpa M³ 0.30 1,026,300.00 307,890.00
6 Pekerjaan Baja
- Baja INP 160 (160 x 74 x 6,5 x 9,5 x 3,8 ) kg 2,741.43 - -
- Plat Siku L 70.70.7 kg 8.86 - -
- Plat Siku L 60.60.6 kg 86.72 - -
- Plat Baja t = 1 cm kg 2,289.06 - -
- Baut Ø 3/4" bh 8.00 - -
- Baut Ø 1/2" bh 384.00 - -
7 Reling tangga Besi Kotak 4x4 dan 2x4 M² 37.68 - -
Jumlah 2,658,736.80
IX PEKERJAAN MEKANIKAL
1 2 3 4 5 6 7
b. Pipa venting tanki air :
- Pipa PVC AW class ø 40 mm, lengkap dengan insect screen m 3.00 - -
c. Mesin Pompa Air/Swage Pump (Komplit) unit 1.00 - -
d. Fitting & aksesoris pipa PVC AW class ls 1.00 - -
2 Pipa PVC AW :
a. Pipa tegak PVC AW ø 3/4* (Rooftank) m 18.00 - -
b. Pipa PVC AW ø 1,5" (ke lantai 1 & taman) m 34.76 - -
c. Pipa PVC AW ø 2" (drain & overflow) m 21.36 - -
3 Fitting & aksesoris pipa GSP medium class ls 1.00 - -
Jumlah Instalasi Air Bersih - RL Jumlah : -
JUMLAH - A. PEKERJAAN INSTALASI AIR BERSIH : -
B PEK. INSTALASI AIR BUANGAN, AIR KOTOR & AIR HUJAN
Pengadaan dan pemasangan instalasi air bekas, air kotor, air hujan,
dan pipa ventilasinya dalam gedung berikut fixtures, fittings,
aksesoris, hanger & support dan perlengkapannya
beserta pengetesan sistem dan instalasi.
B.1 - Toilet Lantai - 1( Elev. ± -4.00)
1 Pekerjaan instalasi air bekas :
a. Pipa uPVC class AW :
- Pipa uPVC class AW ø 50 mm m 2.50 - -
b. Fitting & aksesoris pipa uPVC class AW ls 1.00 - -
2 Pekerjaan instalasi air kotor :
a. Pipa uPVC class AW :
- Pipa uPVC class AW ø 100 mm m 8.00 - -
b. Fitting & aksesoris pipa uPVC class AW ls 1.00 - -
3 Galian tanah dan urugan kembali jalur pipa m 1.00 260,040.00 260,040.00
Jumlah 260,040.00
SUB JUMLAH - B PEK. INSTALASI AIR BUANGAN, AIR KOTOR & AIR HUJAN : 260,040.00
1 2 3 4 5 6 7
b. Pipa refrigerant m 50.25 - -
c. Instalasi kabel daya : NYM 3 x 2,5 mm2 m 120.00 - -
d. Instalasi pipa drain/kondensat AC :
- Pipa drain/kondensat AC ø 20 mm m 45.00 - -
e. Fitting & aksesoris pipa drain/kondensat AC ls 1.00 - -
1 2 3 4 5 6 7
E. PEKERJAAN INSTALASI EXHAUST FAN
Pengadaan dan pemasangan exhaust fan lengkap dengan kabel daya
dan perlengkapannya beserta pengetesan sistem dan instalasi.
1 2 3 4 5 6 7
X PEKERJAAN ELEKTRIKAL
A PEKERJAAN LANTAI 1 (Elev. - 4.00)
1 Kabel Feeder
- dari PLN ke PUTR, NYY 4x70 mm2 m 50.00 - -
- dari PUTR ke PSD, NYFGbY 4x50 mm 2 m 15.00 - -
- dari PUTR ke P-AB, NYFGbY 4x4 mm 2 m 10.00 - -
- dari PSD ke P-1, NYY 4x6 mm 2 m 8.00 - -
- dari PSD ke PAC-1, NYY 4x16 mm 2 m 12.00 - -
2 Panel Hubung Bagi
- Panel LVMDP unit 1.00 - -
- Panel P 1 unit 1.00 - -
- Pembumian Pengaman ttk 1.00 - -
3 Pencahayaan
- Lampu RM 300 Led 2 x 18 Wat Mirror Louvere bh 24.00 - -
- Lampu RM 300 Led 2 x 36 Wat Mirror Reflector bh 14.00 - -
- Lampu RM 300 Led 2 x 36 Watt Open Type/TKI bh 47.00 - -
- Lampu RM Down Light 18 Wat bh 40.00 - -
- Saklar Tunggal 10A 250 VAC bh 3.00 - -
- Saklar Ganda 10A 250 VAC bh 27.00 - -
- Instalasi Penerangan Kabel Dalam Pipa Kondui uPVC titik 246.00 - -
4 Kotak Kontak
- Kotak Kontak 1 Fasa 15 A, 250 VAC bh 56.00 - -
- Instalasi Penerangan Kabel Dalam Pipa Kondui uPVC titik 56.00 - -
5 LD PROYEKTOR
- Tiang Penggantung LCD Otomatis unit 3.00 - -
- Instalasi Daya 2 x 2.5 mm ttk 3.00 - -
- Kotak Kontak 1 Fasa 15 A 250 VAC bh 3.00 - -
- Instalasi Penerangan Kabel Dalam Pipa Kondul uPVC ttk 3.00 - -
- Kabel Data HDMI m 36.00 - -
- Autlet Data bh 1.00 - -
Jumlah -
1 2 3 4 5 6 7
5 LD PROYEKTOR
- Tiang Penggantung LCD Otomatis unit 1.00 - -
- Instalasi Daya 2 x 2.5 mm ttk 1.00 - -
- Kotak Kontak 1 Fasa 15 A 250 VAC bh 1.00 - -
- Instalasi Penerangan Kabel Dalam Pipa Kondul uPVC ttk 1.00 - -
- Kabel Data HDMI m 16.00 - -
- Autlet Data bh 1.00 - -
Jumlah -
KEGIATAN : PEMBANGUNAN, REHABILITASI DAN RENOVASI SARANA PRASARANA INFRASTRUKTUR PERGURUAN TINGGI NEGERI
PEKERJAAN : PEMBANGUNAN GEDUNG AKUNTANSI, TEKNIK INFORMASI, TEKNIK SIPIL POLITEKNIK NEGERI SAMARINDA
LOKASI : KOTA SAMARINDA
C PEKERJAAN ARSITEKTUR
I PEKERJAAN PASANGAN & DINDING 572,670,168.00
I.1 Pekerjaan Lantai - 1 1,727,460.00
I.2 Pekerjaan Lantai - 2 15,130,629.00
I.3 Pekerjaan Lantai - 3 189,506,026.00
I.4 Pekerjaan Lantai - 4 254,610,273.00
I.5 Pekerjaan Lantai - Atas 111,695,780.00
V PEKERJAAN SANITAIR -
V.1 Pekerjaan Lantai - 1 -
V.2 Pekerjaan Lantai - 2 -
V.3 Pekerjaan Lantai - 3 -
V.4 Pekerjaan Lantai - 4 -
V.5 Pekerjaan Lantai - RL. -
D PEKERJAAN ELEKTRIKAL
I PEKERJAAN ELEKTRIKAL GEDUNG -
I.1 Pekerjaan Lantai - 1 -
I.2 Pekerjaan Lantai - 2 -
I.3 Pekerjaan Lantai - 3 -
I.4 Pekerjaan Lantai - 4 -
I.5 Pekerjaan Lantai - Top -
E PEKERJAAN MEKANIKAL
I INSTALASI AIR BERSIH -
I.1 Pekerjaan Lantai -1 -
I.2 Pekerjaan Lantai -2 -
I.3 Pekerjaan Lantai -3 -
I.4 Pekerjaan Lantai -4 -
I.5 Pekerjaan Lantai -Atap dan Shaft -
HARGA TOTAL HARGA
NO URAIAN PEKERJAAN
( Rp ) ( Rp )
1 2 3 4
TOTAL 1,234,974,937.00
BILL OF QUANTITY (BOQ)
GEDUNG TEKNIK INFORMASI
KEGIATAN : PEMBANGUNAN, REHABILITASI DAN RENOVASI SARANA PRASARANA INFRASTRUKTUR PERGURUAN TINGGI NEGERI
PEKERJAAN : PEMBANGUNAN GEDUNG AKUNTANSI, TEKNIK INFORMASI, TEKNIK SIPIL POLITEKNIK NEGERI SAMARINDA
LOKASI : KOTA SAMARINDA
HARGA SATUAN
NO ITEM PEKERJAAN UNIT VOLUME TOTAL HARGA (Rp)
(Rp)
1 2 3 4 5 6
TOTAL 91,315,000.00
BILL OF QUANTITY (BOQ)
GEDUNG TEKNIK INFORMASI
KEGIATAN : PEMBANGUNAN, REHABILITASI DAN RENOVASI SARANA PRASARANA INFRASTRUKTUR PERGURUAN TINGGI NEGERI
PEKERJAAN : PEMBANGUNAN GEDUNG AKUNTANSI, TEKNIK INFORMASI, TEKNIK SIPIL POLITEKNIK NEGERI SAMARINDA
LOKASI : KOTA SAMARINDA
C PEKERJAAN ARSITEKTUR
I PEKERJAAN PASANGAN & DINDING
I.1 Pekerjaan Lantai - 1
1 Pemasangan dinding HB20 campuran 1PC:4PP M² 3.15 371,000.00 1,168,650.00
2 Pemasangan plesteran 1PC:4PP tebal 10 mm M² 6.30 88,700.00 558,810.00
3 Acian Dinding Pas Bata Ringan M² 125.66 - -
4 Dinding keramik 20/45 (toilet) M² 54.39 - -
5 Dinding keramik 40/40 (Lift) M² 4.20 - -
6 Pas. Batu Alam (Palimanan) M² 73.00 - -
7 Cubicle Toilet 1
M 19.28 - -
Sub Total - Pekerjaan Lantai - 1 1,727,460.00
I.2 Pekerjaan Lantai - 2
1 Pemasangan dinding HB20 campuran 1PC:4PP M² 4.55 371,000.00 1,688,050.00
2 Pemasangan plesteran 1PC:4PP tebal 10 mm M² 9.10 88,700.00 807,170.00
3 Acian Dinding M² 194.53 56,300.00 10,952,039.00
4 Acian Kolom M² 29.90 56,300.00 1,683,370.00
5 Dinding keramik 20/45 (toilet) M² 54.39 - -
6 Dinding keramik 40/40 (Lift) M² 4.20 - -
7 Cubicle Toilet 1
M 19.28 - -
Sub Total - Pekerjaan Lantai - 2 15,130,629.00
HARGA SATUAN JUMLAH HARGA TOTAL HARGA
NO URAIAN PEKERJAAN SAT. VOLUME
( Rp ) ( Rp ) ( Rp )
1 2 3 4 5 6 7
IV PEKERJAAN PLAFOND
IV.1 Pekerjaan Lantai - 1
1 Pas.Plafond Calsiboard 4,5 mm M² 39.55 - -
2 Rangka Plafond Besi Hollow Modul 60x60 cm M² 39.55 - -
3 List kayu + fin.cat 1
M 44.96 - -
Sub Total - Lantai 1 -
IV.2 Pekerjaan Lantai - 2
1 Plafond Gypsum board t = 9 mm M² 376.74 - -
2 Rangka Plafond Besi Hollow Modul 60x60 cm M² 376.74 - -
3 Pas.Plafond Calsiboard 4,5 mm M² 151.90 - -
4 Rangka Plafond Besi Hollow Modul 60x60 cm M² 151.90 - -
5 Pas.Cornice Gypsum / List Gypsum Standart 1
M 206.48 32,600.00 6,731,248.00
6 List kayu + fin.cat 1
M 44.96 - -
Sub Total - Lantai 2 6,731,248.00
IV.3 Pekerjaan Lantai - 3
1 Plafond Gypsum board t = 9 mm M² 376.74 - -
2 Rangka Plafond Besi Hollow Modul 60x60 cm M² 376.74 - -
3 Pas.Plafond Calsiboard 4,5 mm M² 151.90 - -
4 Rangka Plafond Besi Hollow Modul 60x60 cm M² 151.90 - -
5 Pas.Cornice Gypsum / List Gypsum 1
M 206.48 - -
6 List kayu + fin.cat 1
M 44.96 - -
Sub Total - Lantai 3 -
IV.4 Pekerjaan Lantai - 4
1 Plafond Gypsum board t = 9 mm M² 376.74 - -
2 Rangka Plafond Besi Hollow Modul 60x60 cm M² 376.74 - -
3 Pas.Plafond Calsiboard 4,5 mm M² 151.90 - -
4 Rangka Plafond Besi Hollow Modul 60x60 cm M² 151.90 - -
5 Pas.Cornice Gypsum / List Gypsum 1
M 206.48 32,600.00 6,731,248.00
6 List kayu + fin.cat 1
M 44.96 - -
Sub Total - Lantai 4 6,731,248.00
TOTAL C.IV PEKERJAAN PLAFOND 13,462,496.00
V PEKERJAAN SANITAIR
V.1 Pekerjaan Lantai - 1
1 Closet duduk Unit 8.00 - -
2 Wastafel Unit 4.00 - -
3 Meja Wastafel Unit 2.00 - -
4 Dinding Sekat Urinoir Unit 3.00 - -
5 Cermin 600x900 Unit 2.00 - -
6 Urinoir Unit 3.00 - -
7 Jet Washer Unit 8.00 - -
8 Kran dinding Unit 4.00 - -
9 Floor drain Unit 12.00 - -
Sub Total - Lantai 1 -
V.2 Pekerjaan Lantai - 2
1 Closet duduk Unit 8.00 - -
2 Wastafel Unit 4.00 - -
3 Meja Wastafel Unit 2.00 - -
4 Dinding Sekat Urinoir Unit 3.00 - -
5 Cermin 600x900 Unit 2.00 - -
6 Urinoir Unit 3.00 - -
7 Jet Washer Unit 8.00 - -
8 Kran dinding Unit 4.00 - -
9 Floor drain Unit 12.00 - -
Sub Total - Lantai 2 -
V.3 Pekerjaan Lantai - 3
1 Closet duduk Unit 8.00 - -
2 Wastafel Unit 4.00 - -
3 Meja Wastafel Unit 2.00 - -
HARGA SATUAN JUMLAH HARGA TOTAL HARGA
NO URAIAN PEKERJAAN SAT. VOLUME
( Rp ) ( Rp ) ( Rp )
1 2 3 4 5 6 7
18 Pekerjaan Atap
- Rangka Atap Baja Ringan M² 34.10 - -
- Penutup Atap M² 34.10 - -
- Pas. Lisplank M1 26.00 - -
19 Lampu Downlight 18 W (LED) bh 3.00 - -
17 Stop kontak bh 2.00 - -
18 Saklar tunggal bh 1.00 - -
19 Saklar ganda bh 2.00 - -
20 Instalasi lampu dalam pipa conduit 20 mm2 ttk 3.00 - -
21 Instalasi Stop kontak dinding dalam pipa conduit 20 mm2 ttk 2.00 - -
Sub Total - Pekerjaan Rumah Genset dan Ruang Pompa 61,511,746.00
TOTAL C.XI GROUND TANK, RUMAH POMPA DAN RUANG GENSET 90,526,666.80
TOTAL C (I+II+III+IV+V+VI+VII+VIII+IX+X+XI) PEKERJAAN ARSITEKTUR BANGUNAN 931,620,412.80
D PEKERJAAN ELEKTRIKAL
I PEKERJAAN ELEKTRIKAL GEDUNG
I.1 Pekerjaan Lantai - 1
2 Lampu Downlight 13 W (LED) bh 12.00 - -
4 Exhaust ceiling Fan bh 8.00 - -
9 Instalasi lampu dalam pipa conduit 20 mm2 ttk 12.00 - -
10 Instalasi Exhaust ceiling Fan ttk 8.00 - -
12 Panel LP-1 unit 1.00 - -
13 Panel AC-1 unit 1.00 - -
14 Panel Pompa Transfer unit 1.00 - -
15 Panel LVMDP+Kapasitor bank unit 1.00 - -
16 Panel ATS + AMF unit 1.00 - -
17 Kabel Power NYFGBY 4x95 mm2 m' 380.00 - -
18 Kabel Power NYY 4x16 mm2 m' 140.00 - -
19 Kabel Power NYY 4x6 mm2 m' 384.40 - -
20 Kabel Tray 200 x 100 m' 83.00 - -
21 Grounding tahanan 2 ohm lot 1.00 - -
22 Support dan material bantu ls 1.00 - -
Sub Total Pekerjaan Elektrikal Lantai - 1 -
E PEKERJAAN MEKANIKAL
I INSTALASI AIR BERSIH
I.1 Pekerjaan Lantai -1
1 Pipa PVC AW Ø 1" m' 80.00 - -
2 Pipa PVC AW Ø 3/4" m' 65.00 - -
3 Pipa PVC AW Ø 1" (external) m' 125.00 - -
4 Gate Valve Ø 1" bh 2.00 - -
5 Support , Fitting dan material bantu ls 1.00 - -
6 Pompa Transfer kap. 350ltr/mnt, head 40mtr bh 2.00 - -
7 Instalasi Pompa Transfer dan perlengkapanya ls 1.00 - -
8 Testing dan Comissioning ls 1.00 - -
Sub Total Pekerjaan Instalasi Air Bersih Lantai - 1 -
- Condensing unit
Lokasi : outdoor lantai 4
a. Pipa refrigerant m 120.00 - -
b. Instalasi kabel daya : NYM 3 x 2,5 mm2 m 58.00 - -
c. Instalasi pipa drain/kondensat AC :
- Pipa drain/kondensat AC ø 20 mm m 25.00 - -
d. Fitting & aksesoris pipa drain/kondensat AC ls 1.00 - -
Testing & commissioning instalasi air conditioning (AC) lot 1.00 - -
Sub Total Pekerjaan Tata Udara Lantai -4 -
TOTAL E.III PEKERJAAN TATA UDARA -
Pekerjaan Pendukung
HARGA SATUAN JUMLAH HARGA TOTAL HARGA
NO URAIAN PEKERJAAN SAT. VOLUME
( Rp ) ( Rp ) ( Rp )
1 2 3 4 5 6 7
1 1 m³ Membuat beton mutu fc=7,4 Mpa (K 100), slum (12 ± 2) cm, w/c = 0.87
Bahan Rp 526,085.99
Portland Cement 247.000 kg Rp 1,220.00 Rp 301,340.00
Pasir Beton 0.869 m3 Rp 108,584.48 Rp 94,359.91
Kerikil (maksimum 30 mm) 0.999 m3 Rp 130,301.38 Rp 130,171.08
Air 0.215 Liter Rp 1,000.00 Rp 215.00
Tenaga Kerja Rp 289,636.24
Pekerja 1.650 org/hr Rp 137,242.34 Rp 226,449.86
Tukang Batu 0.275 org/hr Rp 166,063.23 Rp 45,667.39
Kepala Tukang 0.028 org/hr Rp 157,828.69 Rp 4,419.20
Mandor 0.083 org/hr Rp 157,828.69 Rp 13,099.78
Jumlah : Rp 815,722.23
Keuntungan : Rp 81,572.22
Jumlah : Rp 897,294.45
Dibulatkan : Rp 897,300.00
1 1 m² Pasangan Dinding Bata Merah kelas 1 Uk.(5x11x22)cm Tebal 1 Bata. Campuran Spesi 1PC : 2PP
Bahan Rp 158,405.48
Bata Merah kelas 1 140.000 Buah Rp 700.00 Rp 98,000.00
PC 43.500 kg Rp 1,220.00 Rp 53,070.00
PP 0.080 m³ Rp 91,693.56 Rp 7,335.48
Tenaga Kerja Rp 123,449.49
Pekerja 0.600 org/hr Rp 137,242.34 Rp 82,345.40
Tukang Batu 0.200 org/hr Rp 166,063.23 Rp 33,212.65
Kepala Tukang 0.020 org/hr Rp 157,828.69 Rp 3,156.57
Mandor 0.030 org/hr Rp 157,828.69 Rp 4,734.86
Jumlah : Rp 281,854.97
Keuntungan 10% : Rp 28,185.50
Jumlah : Rp 310,040.47
Dibulatkan : Rp 310,000.00
2 1 m² Pasangan Dinding Bata Merah kelas 1 Uk.(5x11x22)cm Tebal 1 Bata. Campuran Spesi 1PC : 4PP
Bahan Rp 138,918.50
Bata Merah kelas 1 140.000 Buah Rp 700.00 Rp 98,000.00
PC 26.550 kg Rp 1,220.00 Rp 32,391.00
PP 0.093 m³ Rp 91,693.56 Rp 8,527.50
Tenaga Kerja Rp 123,449.49
Pekerja 0.600 org/hr Rp 137,242.34 Rp 82,345.40
Tukang Batu 0.200 org/hr Rp 166,063.23 Rp 33,212.65
Kepala Tukang 0.020 org/hr Rp 157,828.69 Rp 3,156.57
Mandor 0.030 org/hr Rp 157,828.69 Rp 4,734.86
Jumlah : Rp 262,367.99
Keuntungan 10% : Rp 26,236.80
Jumlah : Rp 288,604.79
Dibulatkan : Rp 288,600.00
3 1 m² Pasangan Dinding Bata Merah kelas 1 Uk.(5x11x22)cm Tebal 1/2 Bata. Campuran Spesi 1PC : 2PP
Bahan Rp 75,603.36
Bata Merah kelas 1 70.000 Buah Rp 700.00 Rp 49,000.00
PC 18.950 kg Rp 1,220.00 Rp 23,119.00
PP 0.038 m³ Rp 91,693.56 Rp 3,484.36
Tenaga Kerja Rp 61,724.74
Pekerja 0.300 org/hr Rp 137,242.34 Rp 41,172.70
Tukang Batu 0.100 org/hr Rp 166,063.23 Rp 16,606.32
Kepala Tukang 0.010 org/hr Rp 157,828.69 Rp 1,578.29
Mandor 0.015 org/hr Rp 157,828.69 Rp 2,367.43
Jumlah : Rp 137,328.10
Keuntungan 10% : Rp 13,732.81
Jumlah : Rp 151,060.91
Dibulatkan : Rp 151,100.00
17 1 m² Pasangan Dinding HB/CB 20.Campuran Spesi 1PC :4PP
Bahan Rp 259,154.63
HB 20 12.500 bh Rp 12,500.00 Rp 156,250.00
PC 24.260 kg Rp 1,220.00 Rp 29,597.20
PP 0.772 m³ Rp 91,693.56 Rp 70,787.43
Besi Angkur Diameter 8 mm 0.280 kg Rp 9,000.00 Rp 2,520.00
Tenaga Kerja 78152.65091975
Pekerja 0.350 org/hr Rp 137,242.34 Rp 48,034.82
Tukang Batu 0.150 org/hr Rp 166,063.23 Rp 24,909.48
Kepala Tukang 0.015 org/hr Rp 157,828.69 Rp 2,367.43
Mandor 0.018 org/hr Rp 157,828.69 Rp 2,840.92
Jumlah : Rp 337,307.28
Keuntungan 10% : Rp 33,730.73
Jumlah : Rp 371,038.01
Dibulatkan : Rp 371,000.00
PEKERJAAN PLESTERAN
PEKERJAAN PLESTERAN
#VALUE! 1 m² Plesteran 1PC : 1/2KP : 3PP Tebal 15 mm
Bahan Rp -
Portland Cement 5.760 Kg Rp 1,220.00
Kapur 0.003 m³ Rp -
Pasir Pasang 0.013 m³ Rp 91,693.56
Tenaga Kerja Rp -
Pekerja 0.360 org/hr Rp 137,242.34
Tukang Batu 0.120 org/hr Rp 166,063.23
Kepala Tukang 0.012 org/hr Rp 157,828.69
Mandor 0.018 org/hr Rp 157,828.69
Jumlah Rp -
Keuntungan 10% : Rp -
Jumlah : Rp -
Dibulatkan : Rp -
#VALUE! 1 m² Plesteran 1PC : 2KP : 8PP Tebal 15 mm
Bahan Rp -
Portland Cement 3.000 Kg Rp 1,220.00
Kapur 0.005 m³ Rp -
Pasir Pasang 0.020 m³ Rp 91,693.56
Tenaga Kerja Rp -
Pekerja 0.360 org/hr Rp 137,242.34
Tukang Batu 0.120 org/hr Rp 166,063.23
Kepala Tukang 0.012 org/hr Rp 157,828.69
Mandor 0.018 org/hr Rp 157,828.69
Jumlah Rp -
Keuntungan 10% : Rp -
Jumlah : Rp -
Dibulatkan : Rp -
#VALUE! 1 m² Plesteran 1SM : 1KP : 1PP Tebal 15 mm
Bahan Rp -
SM 0.009 Kg Rp -
Kapur 0.009 m³ Rp -
Pasir Pasang 0.009 m³ Rp 91,693.56
Tenaga Kerja Rp -
Pekerja 0.360 org/hr Rp 137,242.34
Tukang Batu 0.120 org/hr Rp 166,063.23
Kepala Tukang 0.012 org/hr Rp 157,828.69
Mandor 0.018 org/hr Rp 157,828.69
Rp -
Keuntungan 10% : Rp -
Jumlah : Rp -
Dibulatkan : Rp -
#VALUE! 1 m² Plesteran 1SM : 1KP : 2PP Tebal 15 mm
Bahan Rp -
SM 0.007 Kg Rp -
Kapur 0.007 m³ Rp -
Pasir Pasang 0.015 m³ Rp 91,693.56
Tenaga Kerja Rp -
Pekerja 0.360 org/hr Rp 137,242.34
Tukang Batu 0.120 org/hr Rp 166,063.23
Kepala Tukang 0.012 org/hr Rp 157,828.69
Mandor 0.018 org/hr Rp 157,828.69
Jumlah Rp -
Keuntungan 10% : Rp -
Jumlah : Rp -
Dibulatkan : Rp -
A.4.4.2.13 1 m² Plesteran 1 : 1 Tebal 20 mm
Bahan Rp 19,106.77
Portland Cement 13.632 Kg Rp 1,220.00 Rp 16,631.04
Pasir Pasang 0.027 m³ Rp 91,693.56 Rp 2,475.73
Tenaga Kerja Rp 94,738.39
Pekerja 0.400 org/hr Rp 137,242.34 Rp 54,896.94
Tukang Batu 0.200 org/hr Rp 166,063.23 Rp 33,212.65
Kepala Tukang 0.020 org/hr Rp 157,828.69 Rp 3,156.57
Mandor 0.022 org/hr Rp 157,828.69 Rp 3,472.23
Jumlah Rp 113,845.15
Keuntungan 10% : Rp 11,384.52
Jumlah : Rp 125,229.67
Dibulatkan : Rp 125,200.00
A.4.4.2.14 1 m² Plesteran 1 : 3 Tebal 20 mm
Bahan Rp 15,491.46
Portland Cement 10.368 Kg Rp 1,220.00 Rp 12,648.96
Pasir Pasang 0.031 m³ Rp 91,693.56 Rp 2,842.50
Tenaga Kerja Rp 94,738.39
Pekerja 0.400 org/hr Rp 137,242.34 Rp 54,896.94
Tukang Batu 0.200 org/hr Rp 166,063.23 Rp 33,212.65
Kepala Tukang 0.020 org/hr Rp 157,828.69 Rp 3,156.57
Mandor 0.022 org/hr Rp 157,828.69 Rp 3,472.23
Jumlah Rp 110,229.85
Keuntungan 10% : Rp 11,022.98
Jumlah : Rp 121,252.83
Dibulatkan : Rp 121,300.00
A.4.4.2.15 1 m² Plesteran 1 : 4 Tebal 20 mm
Bahan Rp 13,084.59
NO. URAIAN KOEF SATUAN HARGA STUAN SUB. JUMLAH JUMLAH
1 2 2 3 4 5 6
PEKERJAAN PLESTERAN
Portland Cement 8.320 Kg Rp 1,220.00 Rp 10,150.40
Pasir Pasang 0.032 m³ Rp 91,693.56 Rp 2,934.19
Tenaga Kerja Rp 94,738.39
Pekerja 0.400 org/hr Rp 137,242.34 Rp 54,896.94
Tukang Batu 0.200 org/hr Rp 166,063.23 Rp 33,212.65
Kepala Tukang 0.020 org/hr Rp 157,828.69 Rp 3,156.57
Mandor 0.022 org/hr Rp 157,828.69 Rp 3,472.23
Jumlah Rp 107,822.98
Keuntungan 10% : Rp 10,782.30
Jumlah : Rp 118,605.28
Dibulatkan : Rp 118,600.00
NO. URAIAN KOEF SATUAN HARGA STUAN SUB. JUMLAH JUMLAH
1 2 2 3 4 5 6
PEKERJAAN PLESTERAN
1 m² PEMASANGAN 1M2 PLESTERAN BATA RINGAN TEBAL 1CM
Bahan Rp 10,150.40
Portland Cement 8.320 Kg Rp 1,220.00 Rp 10,150.40
Pasir Pasang 0.032 m³ Rp - Rp -
Tenaga Kerja Rp 94,738.39
Pekerja 0.400 org/hr Rp 137,242.34 Rp 54,896.94
Tukang Batu 0.200 org/hr Rp 166,063.23 Rp 33,212.65
Kepala Tukang 0.020 org/hr Rp 157,828.69 Rp 3,156.57
Mandor 0.022 org/hr Rp 157,828.69 Rp 3,472.23
Jumlah Rp 104,888.79
Keuntungan 10% : Rp 10,488.88
Jumlah : Rp 115,377.67
Dibulatkan : Rp 115,400.00
#VALUE! 1 m' Plesteran Granit 1PC : 2Teraso Tebal 10 mm
Bahan Rp 49,700.00
Portland Cement 10.000 Kg Rp 1,220.00 Rp 12,200.00
Batu Teraso 15.000 Kg Rp 2,500.00 Rp 37,500.00
Tenaga Kerja Rp 106,383.40
Pekerja 0.450 org/hr Rp 137,242.34 Rp 61,759.05
Tukang Batu 0.225 org/hr Rp 166,063.23 Rp 37,364.23
Kepala Tukang 0.023 org/hr Rp 157,828.69 Rp 3,630.06
Mandor 0.023 org/hr Rp 157,828.69 Rp 3,630.06
Jumlah Rp 156,083.40
Keuntungan 10% : Rp 15,608.34
Jumlah : Rp 171,691.74
Dibulatkan : Rp 171,700.00
NO. URAIAN KOEF SATUAN HARGA STUAN SUB. JUMLAH JUMLAH
1 2 2 3 4 5 6
PEKERJAAN PLESTERAN
D.7 1 m² Pasang rangka hollow Metal Furing uk. gypsum / calcium cilicate
Bahan Rp 79,344.58
Metal Furing 4 x 4 cm 0.5000 btg Rp 73,203.02 Rp 36,601.51
Metal Furig 2 x 4 cm 0.3333 btg Rp 110,000.00 Rp 36,666.67
Drywall Screw 25mmX083 24.306 pc(s) Rp 250.00 Rp 6,076.40
Tenaga Kerja Rp 70,470.66
Tukang 0.2000 org/hr Rp 166,729.00 Rp 33,345.80
Pekerja 0.2000 org/hr Rp 157,643.00 Rp 31,528.60
Kepala Tukang 0.0200 org/hr Rp 182,676.00 Rp 3,653.52
Mandor 0.0100 org/hr Rp 194,274.00 Rp 1,942.74
JumlahRp 149,815.24
Keuntungan 10% : Rp 14,981.52
Jumlah : Rp 164,796.76
Dibulatkan : Rp 164,800.00
D.8 1 m² Pasang plafond gyfsum board t=9mm berikut rangka Metal Furing
Pasang rangka hollow Metal Furing uk.
A.4.5.1.7 1 m2 Rp 149,815.24 Rp 149,815.24
gypsum / calcium cilicate
Pasang Langit-langit Gypsum Board 120 x
D.7 1 m2 Rp 43,420.93 Rp 43,420.93
240 x 9 mm. Tebal 9 mm
Jumlah Rp 193,236.17
Dibulatkan : Rp 193,200.00
D.9 1 m² Pasang plafond calcium cilicate GRC t=6mm berikut rangka hollow galvanises
Pasang rangka hollow Metal Furing uk.
A.4.5.1.7 1 m2 Rp 149,815.24 Rp 149,815.24
gypsum / calcium cilicate
Pasang Langit-langit calcium cilicate Board
A.4.5.1.7 1 m2 Rp 50,656.71 Rp 50,656.71
120 x 240 Tebal 4 mm
Jumlah Rp 200,471.95
Dibulatkan : Rp 200,500.00
D.10 1 m² Pasang plafond gyfsum tile 600 x 1200 t=6mm berikut rangka metal furing BMSys
Pasang rangka metal furing BMSys ( Untuk
1 m2 Rp 70,470.66 Rp 70,470.66
ceilling
Pasangpanel 600 x 1200
Langit-langit ) tile 600 x
gyfsum
8 1 m2 Rp 25,985.50 Rp 25,985.50
1200mm
Jumlah Rp 96,456.16
Dibulatkan : Rp 96,500.00
a. Bahan: 296,296.04
- Polycarbonat t 6 mm setara twinlate/Impral 1.1000 m2 107,400.00 118,140.00
- Sekroof 42.0000 bh 250.00 10,500.00
- Rangka hollow 40.40.1.6 5.0000 m1 29,281.21 146,406.04
- Kawat las 0.2500 kg 85,000.00 21,250.00
b. Upah: 102,124.80
- Pekerja 0.4000 hari 157,643.00 63,057.20
- Tukang las 0.2000 hari 157,643.00 31,528.60
- Kepala Tukang 0.0200 bh 182,676.00 3,653.52
- Mandor 0.0200 hari 194,274.00 3,885.48
Jumlah Rp 398,420.84
Keuntungan 10% : Rp 39,842.08
Jumlah : Rp 438,262.93
Dibulatkan : Rp 438,300.00
I.1a 1 m2 Atap Kanopy Twinlight
a. Bahan: 128,640.00
- Polycarbonat t 6 mm setara twinlate/Impral 1.1000 m2 107,400.00 118,140.00
- Sekroof 42.0000 bh 250.00 10,500.00
- Rangka hollow 40.40.1.6 5.0000 m1 852.33
- Kawat las 0.2500 kg 6,500.00
b. Upah: 102,124.80
- Pekerja 0.4000 hari 157,643.00 63,057.20
- Tukang las 0.2000 hari 157,643.00 31,528.60
- Kepala Tukang 0.0200 bh 182,676.00 3,653.52
- Mandor 0.0200 hari 194,274.00 3,885.48
Jumlah Rp 230,764.80
Keuntungan 10% : Rp 23,076.48
Jumlah : Rp 253,841.28
Dibulatkan : Rp 253,800.00
I.2 1 m2 Glass wool WM6
a. Bahan: 27,300.00
- WM6 1.0500 m2 26,000.00 27,300.00
b. Upah: 42,216.59
- Pekerja 0.1500 hari 157,643.00 23,646.45
- Tukang 0.0500 hari 157,643.00 7,882.15
- Kepala tukang 0.0500 hari 182,676.00 9,133.80
- Mandor 0.0080 hari 194,274.00 1,554.19
Jumlah Rp 69,516.59
Keuntungan 10% : Rp 6,951.66
Jumlah : Rp 76,468.25
Dibulatkan : Rp 76,500.00
A.4.5.2.1 1 m2 Pasang atap genteng palentong biasa
1 Bahan 50,000.00
Genteng palentong 25.000 bh 2,000.00 50,000.00
2 Tenaga 38,393.94
Pekerja 0.150 oh 157,643.00 23,646.45
Tukang kayu 0.075 oh 157,643.00 11,823.23
Kepala tukang 0.008 oh 182,676.00 1,370.07
Mandor 0.008 oh 194,274.00 1,554.19
Jumlah Rp 88,393.94
Keuntungan 10% : Rp 8,839.39
Jumlah : Rp 97,233.33
Dibulatkan : Rp 97,200.00
Jumlah Rp 154,184.72
Keuntungan 10% : Rp 15,418.47
Jumlah : Rp 169,603.19
Dibulatkan : Rp 169,600.00
I.5 1 m2 Pasang atap genteng morando
1 Bahan 58,000.00
Genteng morando 20.000 bh 2,900.00 58,000.00
2 Tenaga 35,755.28
Pekerja 0.150 oh 157,643.00 23,646.45
Tukang kayu 0.060 oh 157,643.00 9,458.58
Kepala tukang 0.006 oh 182,676.00 1,096.06
Mandor 0.008 oh 194,274.00 1,554.19
Jumlah Rp 93,755.28
Keuntungan 10% : Rp 9,375.53
Jumlah : Rp 103,130.81
Dibulatkan : Rp 103,100.00
I.6 1 m' Pasang genteng bubung morando
1 Bahan 58,056.85
Genteng bubung morando 5.000 bh 9,000.00 45,000.00
Semen portland 0.160 zak 61,000.00 9,760.00
Pasir pasang 0.032 m3 103,026.47 3,296.85
2 Tenaga 98,627.87
Pekerja 0.400 oh 157,643.00 63,057.20
Tukang kayu 0.200 oh 157,643.00 31,528.60
Kepala tukang 0.020 oh 182,676.00 3,653.52
Mandor 0.002 oh 194,274.00 388.55
Jumlah Rp 156,684.72
Keuntungan 10% : Rp 15,668.47
Jumlah : Rp 172,353.19
Dibulatkan : Rp 172,400.00
I.7 1 m' Pasang genteng samping penutup lisplang morando
1 Bahan 80,056.85
Genteng samping penutup lisplang morando 5.000 bh 13,400.00 67,000.00
Semen portland 0.160 zak 61,000.00 9,760.00
Pasir pasang 0.032 m3 103,026.47 3,296.85
2 Tenaga 98,627.87
Pekerja 0.400 oh 157,643.00 63,057.20
Tukang kayu 0.200 oh 157,643.00 31,528.60
Kepala tukang 0.020 oh 182,676.00 3,653.52
Mandor 0.002 oh 194,274.00 388.55
Jumlah Rp 178,684.72
Keuntungan 10% : Rp 17,868.47
Jumlah : Rp 196,553.19
Dibulatkan : Rp 196,600.00
Jumlah Rp 118,885.28
Keuntungan 10% : Rp 11,888.53
Jumlah : Rp 130,773.80
Dibulatkan : Rp 130,800.00
A.4.5.2.6 1 m' Pasang Bubungan Palentong Besar Ex. Jatiwangi Glazur
1 Bahan 540,496.85
Bubungan Genteng Glazur Ex. Jatiwangi 4.000 bh 12,300.00 49,200.00
Semen portland 8.000 zak 61,000.00 488,000.00
Pasir pasang 0.032 m3 103,026.47 3,296.85
2 Tenaga 98,627.87
Pekerja 0.400 oh 157,643.00 63,057.20
Tukang kayu 0.200 oh 157,643.00 31,528.60
Kepala tukang 0.020 oh 182,676.00 3,653.52
Mandor 0.002 oh 194,274.00 388.55
Jumlah Rp 639,124.72
Keuntungan 10% : Rp 63,912.47
Jumlah : Rp 703,037.19
Dibulatkan : Rp 703,000.00
I.10 1 m2 Pasang Atap Genteng Keramik Glazur Ex. Kanmuri
1 Bahan 204,000.00
Genteng Keramik Glazur Ex. Kanmuri 20.000 bh 10,200.00 204,000.00
2 Tenaga 35,755.28
Pekerja 0.150 oh 157,643.00 23,646.45
Tukang kayu 0.060 oh 157,643.00 9,458.58
Kepala tukang 0.006 oh 182,676.00 1,096.06
Mandor 0.008 oh 194,274.00 1,554.19
Jumlah Rp 239,755.28
Keuntungan 10% : Rp 23,975.53
Jumlah : Rp 263,730.81
Dibulatkan : Rp 263,700.00
I.11 1 m' Pasang Bubungan Keramik Glazur Ex. Kanmuri
1 Bahan 99,056.85
Bubungan Genteng Keramik Glazur Ex. Kanmu 5.000 bh 17,200.00 86,000.00
Semen portland 0.160 zak 61,000.00 9,760.00
Pasir pasang 0.032 m3 103,026.47 3,296.85
2 Tenaga 98,627.87
Pekerja 0.400 oh 157,643.00 63,057.20
Tukang kayu 0.200 oh 157,643.00 31,528.60
Kepala tukang 0.020 oh 182,676.00 3,653.52
Mandor 0.002 oh 194,274.00 388.55
Jumlah Rp 197,684.72
Keuntungan 10% : Rp 19,768.47
Jumlah : Rp 217,453.19
Dibulatkan : Rp 217,500.00
Jumlah Rp 221,936.55
Keuntungan 10% : Rp 22,193.65
Jumlah : Rp 244,130.20
Dibulatkan : Rp 244,100.00
A.4.5.2.35 1 m' Pasang nok genteng beton
1 Bahan 91,496.43
Nok genteng beton 3.500 bh 19,400.00 67,900.00
Paku biasa 2" x 5" 0.050 kg 12,471.63 623.58
Semen abu-abu 10.800 kg 1,220.00 13,176.00
Pasir pasang 0.032 m3 103,026.47 3,296.85
Semen warna 1.000 kg 6,500.00 6,500.00
2 Tenaga 102,124.80
Pekerja 0.400 oh 157,643.00 63,057.20
Tukang kayu 0.200 oh 157,643.00 31,528.60
Kepala tukang 0.020 oh 182,676.00 3,653.52
Mandor 0.020 oh 194,274.00 3,885.48
Jumlah Rp 193,621.23
Keuntungan 10% : Rp 19,362.12
Jumlah : Rp 212,983.35
Dibulatkan : Rp 213,000.00
I.14 1 m2 Pasang atap Bitumen 400x1060 mm/Onduvila
1 Bahan 91,500.00
Atap Bitumen Casa Ex. Gutta uk. 3x500x105 2.610 bh 30,000.00 78,300.00
Paku Sekrup 12.000 kg 1,100.00 13,200.00
2 Tenaga 51,062.40
Pekerja 0.200 oh 157,643.00 31,528.60
Tukang kayu 0.100 oh 157,643.00 15,764.30
Kepala tukang 0.010 oh 182,676.00 1,826.76
Mandor 0.010 oh 194,274.00 1,942.74
Jumlah Rp 142,562.40
Keuntungan 10% : Rp 14,256.24
Jumlah : Rp 156,818.64
Dibulatkan : Rp 156,800.00
A.4.5.2.39 1 m1 Pasang Nok Atap Bitumen Ukuran l: 800 mm/Onduvila
1 Bahan 66,000.00
Nok Atap Bitumen Casa Ex. Gutta uk 1.100 bh 50,000.00 55,000.00
Paku Sekrup 10.000 kg 1,100.00 11,000.00
2 Tenaga 68,322.90
Pekerja 0.250 oh 157,643.00 39,410.75
Tukang kayu 0.150 oh 157,643.00 23,646.45
Kepala tukang 0.015 oh 182,676.00 2,740.14
Mandor 0.013 oh 194,274.00 2,525.56
Jumlah Rp 134,322.90
Keuntungan 10% : Rp 13,432.29
Jumlah : Rp 147,755.19
Dibulatkan : Rp 147,800.00
Jumlah Rp 62,381.45
Keuntungan 10% : Rp 6,238.15
Jumlah : Rp 68,619.60
Dibulatkan : Rp 68,600.00
A.4.5.2.40 1 m2 Pasang atap nok seng
1 Bahan 14,898.87
Nok Seng plat 3" x 6" bjls 28 0.300 lbr 48,000.00 14,400.00
Paku biasa 1/2" - 1" 0.040 kg 12,471.63 498.87
2 Tenaga 37,308.51
Pekerja 0.150 oh 157,643.00 23,646.45
Tukang kayu 0.070 oh 157,643.00 11,035.01
Kepala tukang 0.008 oh 182,676.00 1,461.41
Mandor 0.006 oh 194,274.00 1,165.64
Jumlah Rp 52,207.38
Keuntungan 10% : Rp 5,220.74
Jumlah : Rp 57,428.11
Dibulatkan : Rp 57,400.00
I.17 1 m2 Pasang atap Zinc - Allumunium Prepainted TCT 0.45mm
a. Bahan: 142,259.83
- Union Pesona TCT 0.45mm lebar 990mm c 1.0500 m2 133,110.00 139,765.50
- Paku hak panjang 15 cm 0.2000 kg 12,471.63 2,494.33
b. Upah: 55,818.67
- Kepala Tukang las 0.0100 hari 157,643.00 1,576.43
- Tukang las 0.1000 hari 157,643.00 15,764.30
- Pekerja 0.2000 hari 182,676.00 36,535.20
- Mandor 0.0100 hari 194,274.00 1,942.74
Jumlah Rp 198,078.50
Keuntungan 10% : Rp 19,807.85
Jumlah : Rp 217,886.34
Dibulatkan : Rp 217,900.00
#VALUE! 1 m2 Pasang atap Zinc - Allumunium Standing seam TCT 0.50 mm
1 Bahan 249.43
Zinc - Allumunium Standing seam TCT 0.50 1.050 m3 0.00 -
Paku hak panjang 15 cm 0.020 kg 12,471.63 249.43
2 Tenaga 144,505.75
Pekerja 0.150 oh 157,643.00 23,646.45
Tukang kayu 0.750 oh 157,643.00 118,232.25
Kepala tukang 0.008 oh 182,676.00 1,461.41
Mandor 0.006 oh 194,274.00 1,165.64
Jumlah Rp 144,755.18
Keuntungan 10% : Rp 14,475.52
Jumlah : Rp 159,230.70
Dibulatkan : Rp 159,200.00
A.4.5.2.52 1 m1 Pasang nok Zincalume t=0.45mm
1 Bahan 63,543.87
- Nok Standar untuk sudut atap curam 1.200 m1 52,537.50 63,045.00
Paku hak panjang 15 cm 0.040 kg 12,471.63 498.87
2 Tenaga 209,270.75
Pekerja 1.000 oh 157,643.00 157,643.00
Tukang kayu 0.150 oh 157,643.00 23,646.45
Kepala tukang 0.100 oh 182,676.00 18,267.60
Mandor 0.050 oh 194,274.00 9,713.70
Jumlah Rp 272,814.62
Keuntungan 10% : Rp 27,281.46
Jumlah : Rp 300,096.08
Dibulatkan : Rp 300,100.00
A.4.5.2.53 1 m1 Pasang Lisplank GRC
1 Bahan 25,360.03
GRC 0.330 Lbr 75,000.00 24,750.00
Paku GRC 0.050 kg 12,200.50 610.03
2 Tenaga 51,917.79
Pekerja 0.100 oh 157,643.00 15,764.30
Tukang kayu 0.200 oh 157,643.00 31,528.60
Kepala tukang 0.020 oh 182,676.00 3,653.52
Mandor 0.005 oh 194,274.00 971.37
ANALISIS HARGA SATUAN PEKERJAAN BIDANG PEKERJAAN UMUMNOMOR : 28/PRT/M/2016
NO. URAIAN KOEF SATUAN HARGA STUAN SUB. JUMLAH JUMLAH
1 2 2 3 4 5 6
Persyaratan teknis dalam perhitungan harga satuan pekerjaan :
a. Pelaksanaan perhitungan satuan pekerjaan harus didasarkan pada gambar teknis dan rencana kerja syarat-syarat (RKS).
b. Pelaksanaan Koefisien bahan telah ditambahkan toleransi sebesar 5% - 20%, dimana didalamnya termasuk angka susut,
yang besarnya tergantung dari jenis bahan dan komposisi adukan.
c. Jam kerja efektif untuk tenaga kerja diperhitungkan 5 jam per hari.
Jumlah Rp 77,277.82
Keuntungan 10% : Rp 7,727.78
Jumlah : Rp 85,005.60
Dibulatkan : Rp 85,000.00
#VALUE! 1 m1 Pasang atap arah melintang ( Transvarsa pascia capping ) TCT 0.45mm
1 Bahan -
- Penutup atap arah memanjang 1.100 m1 26,055.00
Paku hak panjang 15 cm 0.040 kg 12,200.50
2 Tenaga -
Pekerja 0.250 oh 157,643.00
Tukang kayu 0.150 oh 157,643.00
Kepala tukang 0.015 oh 182,676.00
Mandor 0.013 oh 194,274.00
Jumlah Rp -
Keuntungan 10% : Rp -
Jumlah : Rp -
Dibulatkan : Rp -
Jumlah Rp 74,414.02
Keuntungan 10% : Rp 7,441.40
Jumlah : Rp 81,855.42
Dibulatkan : Rp 81,900.00
I.21 1 m' Pasang talang gantung
1 Bahan 126,787.50
Talang alumunium 1.050 m' 120,750.00 126,787.50
2 Tenaga 26,114.02
Pekerja 0.100 oh 157,643.00 15,764.30
Tukang kayu 0.050 oh 157,643.00 7,882.15
Kepala tukang 0.005 oh 182,676.00 913.38
Mandor 0.008 oh 194,274.00 1,554.19
Jumlah Rp 152,901.52
Keuntungan 10% : Rp 15,290.15
Jumlah : Rp 168,191.67
Dibulatkan : Rp 168,200.00
I.22 1 m' Talang jurai atau datar zincalume
a. Bahan: 107,250.00
- Zincalume Plat L = 90 CM t=0.45mm 1.100 m1 97,500.00 107,250.00
b. Upah: 48,950.48
Pekerja 0.100 oh 157,643.00 15,764.30
Tukang 0.150 hari 157,643.00 23,646.45
Kepala tukang 0.015 oh 182,676.00 2,740.14
Mandor 0.035 hari 194,274.00 6,799.59
Jumlah Rp 156,200.48
Keuntungan 10% : Rp 15,620.05
Jumlah : Rp 171,820.53
Dibulatkan : Rp 171,800.00
#VALUE! 1 m1 Talang Vertikal Pralon D 1 1/2"
a. Bahan: -
- Pralon Ø 1 1/2" setara AW 0.2750 btg 14,650.00
- Sambungan Pelengkap (10% harga pralon) 0.1000 ls 1,465.00
- Lem PVC 0.0200 kg 84,000.00
b. Upah: -
- Tukang pipa 0.0750 hari 157,643.00
- Mandor 0.0100 hari 194,274.00
Jumlah Rp -
Keuntungan 10% : Rp -
Jumlah : Rp -
Dibulatkan : Rp -
#VALUE! 1 m1 Talang Vertikal Pralon D 2"
a. Bahan: -
- Pralon Ø 2" setara AW 0.2750 btg 19,275.00
- Sambungan Pelengkap (10% harga pralon) 0.1000 ls 1,927.50
- Lem PVC 0.0200 kg 84,000.00
b. Upah: -
- Tukang pipa 0.0750 hari 157,643.00
- Mandor 0.0100 hari 194,274.00
Jumlah Rp -
Keuntungan 10% : Rp -
Jumlah : Rp -
Dibulatkan : Rp -
#VALUE! 1 m1 Talang Vertikal Pralon D 2 1/2"
a. Bahan: -
- Pralon Ø 2 1/2" setara AW 0.2750 btg 31,750.00
- Sambungan Pelengkap (10% harga pralon) 0.1000 ls 3,175.00
- Lem PVC 0.0200 kg 84,000.00
b. Upah: -
- Tukang pipa 0.0750 hari 157,643.00
- Mandor 0.0100 hari 194,274.00
Jumlah Rp -
ANALISIS HARGA SATUAN PEKERJAAN BIDANG PEKERJAAN UMUMNOMOR : 28/PRT/M/2016
NO. URAIAN KOEF SATUAN HARGA STUAN SUB. JUMLAH JUMLAH
1 2 2 3 4 5 6
Persyaratan teknis dalam perhitungan harga satuan pekerjaan :
a. Pelaksanaan perhitungan satuan pekerjaan harus didasarkan pada gambar teknis dan rencana kerja syarat-syarat (RKS).
b. Pelaksanaan Koefisien bahan telah ditambahkan toleransi sebesar 5% - 20%, dimana didalamnya termasuk angka susut,
yang besarnya tergantung dari jenis bahan dan komposisi adukan.
c. Jam kerja efektif untuk tenaga kerja diperhitungkan 5 jam per hari.
a. Bahan: 12,367.50
- Pralon Ø 3" setara AW 0.2750 btg 37,500.00 10,312.50
- Sambungan Pelengkap (10% harga pralon) 0.1000 ls 3,750.00 375.00
- Lem PVC 0.0200 kg 84,000.00 1,680.00
b. Upah: 13,765.97
- Tukang pipa 0.0750 hari 157,643.00 11,823.23
- Mandor 0.0100 hari 194,274.00 1,942.74
Jumlah Rp 26,133.47
Keuntungan 10% : Rp 2,613.35
Jumlah : Rp 28,746.81
Dibulatkan : Rp 28,700.00
a. Bahan: 19,428.38
- Pralon Ø 4" setara AW 0.2750 btg 62,275.00 17,125.63
- Sambungan Pelengkap (10% harga pralon) 0.1000 ls 6,227.50 622.75
- Lem PVC 0.0200 kg 84,000.00 1,680.00
b. Upah: 13,765.97
- Tukang pipa 0.0750 hari 157,643.00 11,823.23
- Mandor 0.0100 hari 194,274.00 1,942.74
Jumlah Rp 33,194.34
Keuntungan 10% : Rp 3,319.43
Jumlah : Rp 36,513.77
Dibulatkan : Rp 36,500.00
#VALUE! 1 m1 Sparing Pralon d 1 1/2"
a. Bahan: -
- Pralon Ø 1 1/2" setara AW 0.0750 btg 14,650.00
- Lem PVC 0.0010 kg 84,000.00
b. Upah: -
- Tukang pipa 0.0125 hari 157,643.00
- Mandor 0.0006 hari 194,274.00
Jumlah Rp -
Keuntungan 10% : Rp -
Jumlah : Rp -
Dibulatkan : Rp -
#VALUE! 1 m1 Sparing Pralon d 2"
a. Bahan: -
- Pralon Ø 2" setara AW 0.0750 btg 19,275.00
- Lem PVC 0.0010 kg 84,000.00
b. Upah: -
- Tukang pipa 0.0125 hari 157,643.00
- Mandor 0.0006 hari 194,274.00
Jumlah Rp -
Keuntungan 10% : Rp -
Jumlah : Rp -
Dibulatkan : Rp -
#VALUE! 1 m1 Sparing Pralon d 2 1/2"
a. Bahan: -
- Pralon Ø 2 1/2" setara AW 0.0750 btg 31,750.00
- Lem PVC 0.0010 kg 84,000.00
b. Upah: -
- Tukang pipa 0.0125 hari 157,643.00
- Mandor 0.0006 hari 194,274.00
Jumlah Rp -
Keuntungan 10% : Rp -
Jumlah : Rp -
Dibulatkan : Rp -
I.25 1 m1 Sparing Pralon d 3"
a. Bahan: 2,896.50
- Pralon f 3" setara AW 0.0750 btg 37,500.00 2,812.50
- Lem PVC 0.0010 kg 84,000.00 84.00
b. Upah: 2,091.96
- Tukang pipa 0.0125 hari 157,643.00 1,970.54
- Mandor 0.0006 hari 194,274.00 121.42
Jumlah Rp 4,988.46
Keuntungan 10% : Rp 498.85
Jumlah : Rp 5,487.30
Dibulatkan : Rp 5,500.00
I.26 1 m1 Sparing Pralon d 4"
a. Bahan: 4,754.63
- Pralon f 3" setara AW 0.0750 btg 62,275.00 4,670.63
- Lem PVC 0.0010 kg 84,000.00 84.00
b. Upah: 2,091.96
- Tukang pipa 0.0125 hari 157,643.00 1,970.54
- Mandor 0.0006 hari 194,274.00 121.42
Jumlah Rp 6,846.58
Keuntungan 10% : Rp 684.66
Jumlah : Rp 7,531.24
Dibulatkan : Rp 7,500.00
ANALISIS HARGA SATUAN PEKERJAAN BIDANG PEKERJAAN UMUMNOMOR : 28/PRT/M/2016
NO. URAIAN KOEF SATUAN HARGA STUAN SUB. JUMLAH JUMLAH
1 2 2 3 4 5 6
Persyaratan teknis dalam perhitungan harga satuan pekerjaan :
a. Pelaksanaan perhitungan satuan pekerjaan harus didasarkan pada gambar teknis dan rencana kerja syarat-syarat (RKS).
b. Pelaksanaan Koefisien bahan telah ditambahkan toleransi sebesar 5% - 20%, dimana didalamnya termasuk angka susut,
yang besarnya tergantung dari jenis bahan dan komposisi adukan.
c. Jam kerja efektif untuk tenaga kerja diperhitungkan 5 jam per hari.
a. Bahan: 49,500.00
- Flashing, seng BJLS 28 1.1000 m2 45,000.00 49,500.00
b. Upah: 30,446.04
- Tukang 0.1500 hari 157,643.00 23,646.45
- Mandor 0.0350 hari 194,274.00 6,799.59
Jumlah Rp 79,946.04
Keuntungan 10% : Rp 7,994.60
Jumlah : Rp 87,940.64
Dibulatkan : Rp 87,900.00
I.28 1 m1 Pasang Talang Flasing jurai atau datar Bitumen Casa Ex. Gutta
1 Bahan 92,800.00
Flasing Atap Bitumen Casa Ex. Gutta uk 1.050 bh 80,000.00 84,000.00
Paku Sekrup 8.000 kg 1,100.00 8,800.00
2 Tenaga 36,099.27
Pekerja 0.084 oh 157,643.00 13,242.01
Tukang kayu 0.125 oh 157,643.00 19,705.38
Kepala tukang 0.013 oh 182,676.00 2,374.79
Mandor 0.004 oh 194,274.00 777.10
Jumlah Rp 128,899.27
Keuntungan 10% : Rp 12,889.93
Jumlah : Rp 141,789.20
Dibulatkan : Rp 141,800.00
1 2 3
1 2 3
1 2 3
PEKERJAAN KACA
1 PEMASANGAN 1 M2 KACA CERMIN TEBAL 5 MM -
PEKERJAAN PENGECATAN
1 1 M2 PENGECATAN BIDANG KAYU BARU (1 LAPIS PLAMUR, 1 LAPIS CAT DASAR, 2 LAPIS CAT PENUTUP) -
2 PENGECATAN 1 M2 TEMBOK BARU INTERIOR ( 1 LAPIS PLAMIR, 1 LAPIS CAT DASAR, 2 LAPIS CAT PENUTUP) -
3 PENGECATAN 1 M2 TEMBOK BARU EXTERIOR ( 1LAPIS PLAMUUR, 1 LAPIS CAT DASAR, 2 LAPIS CATPENUTUP) -
4 PENGECATAN 1 M2 PLAFOND -
5 Pengecatan 1 m2 permukaan baja galvanis secara manual sistem 1 lapis cat mutakhir -
6 PEKERJAAN 1 M2 WATERPROOFING -
7 PELABURAN 1 M2 BIDANG KAYU DENGAN VERNIS -
1 2 3
PEKERJAAAN MEKANIKAL
1 Pipa uPVC class AW ø 3/4" -
2 Pipa uPVC class AW ø 1" -
3 Pipa uPVC class AW ø 1,5" -
4 Pipa uPVC class AW ø 2" -
5 Pipa uPVC class AW ø 4" -
6 Pipa uPVC class AW ø 6" -
7 Pipa Baja Galvanis mediun class Gate valve, JIS 10K ø 25 mm -
8 Floor Clean out ø 80 mm -
9 Floor Clean out ø 100 mm -
10 Tangki Air Fiberglass -
11 Pompa Transfer kap. 350ltr/mnt, head 40mtr -
12 POMPA BOOSTER (PACKAGE BOOSTER PUMP) -
13 Pompa Air Transper 50 liter/menit -
14 Pompa Transper 8 m3/Jam -
15 Exhaust Fan : 200 CMH -
16 AC wall mounted, single split system : 4.500 BTUH -
17 AC wall mounted, single split system : 9.000 BTUH -
18 AC wall mounted, single split system : 18.000 BTUH -
19 AC wall mounted, single split system : 24.000 BTUH -
20 Refrigerant AC wall mounted, single split system : 4. 500 BTUH -
21 Refrigerant AC wall mounted, single split system : 9. 000 BTUH -
22 Refrigerant AC wall mounted, single split system : 18. 000 BTUH -
23 Refrigerant AC wall mounted, single split system : 24. 000 BTUH -
24 Drain/kondensat AC ø 20 mm -
25 Portable fire extinguisher karbon dioksida agent (CO.2.0.) : 2 kg -
26 Portable fire extinguisher karbon dioksida agent (CO.2.0.) : 3 kg -
27 Kabel NYM : 3 x 2,5 mm2 -
28 Instalasi Detektor/titik -
PEKERJAAAN ELEKTRIKAL
1 PEMASANGAN/INSTALASI KABEL 4 x 4 mm² -
2 PEMASANGAN/INSTALASI KABEL 4 x 6 mm² -
3 PEMASANGAN/INSTALASI KABEL 4 x 16 mm² -
4 PEMASANGAN/INSTALASI KABEL 4 x 70 mm² -
5 PEMASANGAN/INSTALASI KABEL NYFGbY 4 x 50 mm² -
6 PEMASANGAN/INSTALASI KABEL NYFGbY 4 x 95 mm² -
7 PEMASANGAN/ INSTALASI KABEL DATA HDMI -
NO. URAIAN ANALISA HARGA
1 2 3
8 ELEKTRODA PEMBUMIAN -
9 PANEL PUTR (Box uk. 1.800 x 600 x 400 mm ) + Komponen -
10 PANEL P-1 (Box Panel ukuran 800 x 600 x 250 mm) + Komponen -
11 PANEL P - 3 (Box Panel ukuran 800 x 600 x 250 mm) + Komponen -
12 PANEL PAC - 1 ( Box Panel ukuran 700 x 500 x 250 mm) + Komponen -
13 LAMPU RM 300 LED 2 x 10 WATT MIRROR LOUVERE -
14 LAMPU RM 300 Led 2 x 18 Wat Mirror Louvere -
15 LAMPU RM 300 Led 2 x 36 Wat Mirror Reflector -
16 LAMPU RM 300 Led 2 x 36 Watt Open Type/TKI -
17 LAMPU RM DOWN LIGHT 13 Wat -
18 LAMPU RM DOWN LIGHT 18 Wat -
19 LAMPU GMS T 8 ACR-SCR 1 X 18 Wat -
20 LAMPU DOWN LIGHT RD 125 E27 Led 1 x 3 Watt -
21 LAMPU GMS GMS TP LED 1 x 10 WATT ACRYLIC COVER -
22 LAMPU GMS GMS TP LED 1 x 18 WATT ACRYLIC COVER -
23 LAMPU KELUAR/EXIT, TL -D 1x10 W -
24 SAKLAR TUNGGAL, 10 A, 250 VAC -
25 SAKLAR GANDA, 10 A, 250 VAC -
26 SAKLAR CELING, 15 A, 250 VAC -
27 INSTALASI PENERANGAN KABEL DALAM PIPA KONDUCIT uPVC -
28 KONTAK - KONTAK BIASA 1 FASE, 15 A, 250 VAC -
29 KABEL TRAY 200 x 100 -
30 KABEL TELPON ITC (STELL-K011) 30 x 2 x 0,6 mm² -
31 INSTALASI LAN UTP cat 6 -
32 OUTLET DATA Rj 45 DINDING 2 GANG -
33 OUTLET DATA Rj 45 LANTAI 2 GANG -
34 SWITCH HUB 24 porth -
35 WALL MOUNT RACK -
36 SERVER : Xeon dual core. Ram 1Gb. 250 Gb SS Sata -
37 MAIN SWITCH ROUTER & FIRE WALL -
38 TIANG PENGGANTUNG LCD -
118
UPAH
NO KEAHLIAN SAT
Rp.
I. PEKERJA.
1 Tenaga/ Pekerja 137,242 /Org/Hr
2 Tukang Aspal 166,063 /Org/Hr
3 Tukang Batu 166,063 /Org/Hr
4 Tukang Besi 166,063 /Org/Hr
5 Tukang Cat 166,063 /Org/Hr
6 Tukang Gypsum 166,063 /Org/Hr
7 Tukang Kayu 166,063 /Org/Hr
8 Tukang Las 166,063 /Org/Hr
9 Tukang Listrik 166,063 /Org/Hr
10 Tukang Taman 166,063 /Org/Hr
11 Tukang Cat Melamik 166,063 /Org/Hr
12 Tukang Pipa 166,063 /Org/Hr
13 Tukang Aluminium 166,063 /Org/Hr
14 Kepala Tukang 157,829 /Org/Hr
15 Operator 166,063 /Org/Hr
16 Mandor 157,829 /Org/Hr
II. BAHAN.
HARGA
NO JENIS MATERIAL SAT
Rp.
A BAHAN DASAR
1 Pasir Beton 108,584 m3
2 Pasir Pasang 91,694 m3
3 Pasir Urug 96,520 m3
4 Batu Belah / Batu Kali / Batu Gunung 125,475 m3
5 Batu Split 1x2 130,301 m3
6 Batu Split 2x3 130,301 m3
7 Batu lime stone 91,694 m3
8 Sirtu (Pasir Batu) 91,694 m3
9 Tanah Urug setempat 96,520 m3
10 Tanah Subur 33,782 m3
11 Tanah Urug pilihan - Material Jalan 96,520 m3
12 Bata Merah bakar Kelas 1 700 bh
13 Batako 2,600 bh
14 Hollow Block 20 12,500 bh
15 Beton ringan ( Celcon block ) 10,241 Bh
16 Roaster Kembang biasa uk. 22x220x15 cm 12,500 bh
17 Roaster beton uk. 12x30x15 cm 18,100 bh
18 Terawang Beton Grc Cetak Ornamen Betawi 238,588 m2
19 Glass block Lokal 20 x 20 cm ex. Mulya 30,300 bh
20 Semen PC type I @ 50 kg Tiga Roda 61,000 Zak
21 Semen putih @50 kg Tiga Roda 116,000 Zak
22 Semen Mortar Instant ( MU -100) 65,000 kg
23 Semen Warna untuk nat kemasan plastik 6,500 kg
24 Semen Grouting 4,584,678 m3
25 Sement / mortal ( MU -300) 1,425 kg
26 Sement / mortal ( MU -200) 4,450 kg
27 Air 1,000 liter
27 Semen PC type I @ 1 kg Tiga Roda 1,300 kg
B BETON
B.1 BETON READY MIX
1 Readymix Mutu Beton K-175 450,063 m3
2 Readymix Mutu Beton K-225 461,450 m3
3 Readymix Mutu Beton K-250 472,837 m3
4 Readymix Mutu Beton K-300 492,900 m3
6 Sewa pompa beton 256,048 jam
7 Sewa vibrator 100,857 jam
C BAHAN BESI
1 Besi beton polos 4,880 kg
2 Besi beton ulir 4,880 kg
3 Kawat beton 13,014 kg
4 Paku rata-rata 12,472 kg
5 Sekruf 12,201 kg
6 Paku hak panjang / paku kait 12,201 kg
7 Skruf gyp 12,201 kg
8 Skruf plafond 12,201 kg
9 Drywall Screw 25mmX083 250 bh
10 Skrup Fixer 1,200 bh
11 Skrup atap bitumen 1,100 bh
11 WM - M5-150 2,1 x 5,4 m 26,000 m2
12 WM - M6-150 2,1 x 5,4 m 36,000 m2
13 WM - M8-150 2,1 x 5,4 m 48,000 m2
14 WM - M9-150 2,1 x 5,4 m 66,000 m2
15 WM - M10-150 2,1 x 5,4 m 110,000 m2
16 Skruf + fiser untuk kusen alumunium 3,500 bh
17 Baja HB & IWF 9,500 kg
18 Siku 9,500 kg
19 Jenis CNP 9,500 kg
20 Jenis UNP 9,500 kg
21 Jenis Lips Canal 9,500 kg
22 Jenis plat ukuran 4' x 8' berlaku untuk semua ketebalan 9,500 kg
23 Besi hollow kotak 40/40 mm t.1,6mm pj=6m 87,844 btg
24 Besi kotak hollow 40/20 mm t.1,6mm pj=6m 66,696 btg
25 Besi hollow kotak 20/80 mm t.1,6mm pj=6m 104,111 btg
26 Besi kotak 20/20 mm (untuk rangka plafond) pj=4m 43,000 btg
II. BAHAN.
HARGA
NO JENIS MATERIAL SAT
Rp.
27 Besi kotak 20/40 mm (untuk rangka plafond) pj=4m 66,696 btg
28 Besi kotak 40/40 mm (untuk rangka plafond) pj=6m 87,844 btg
29 Besi hollow kotak 40/60 mm t.1,6mm pj=6m 78,625 btg
30 Besi hollow galvanis 40/40 mm t= 0.35mm 73,203 btg
31 Besi hollow galvanis 20/40 mm t= 0.35mm 110,000 btg
32 Besi Strips 10,500 kg
33 Kawat las 85,000 kg
33 Angker dia 8 9,000 bh
34 Angker dia 12 13,920 bh
35 Angker dia 16 18,120 bh
36 Angker dia 19 21,889 bh
37 Angker dia 20 23,150 bh
38 Angker dia 22 A 327 25,465 bh
39 Angker dia 32 37,040 bh
40 Baut HTB M12 - panjang 60 mm 2,557 bh
41 Baut HTB M16 - panjang 60 mm 4,759 bh
42 Baut HTB M20 - panjang 60 mm 8,457 bh
43 Baut HTB M22 - panjang 70 mm 14,330 bh
44 Baut HTB M25 - panjang 70 mm 22,400 bh
44 Baut HTB M27 - panjang 70 mm 32,872 bh
45 Walter mur 16 42,000 bh
46 Kawat harmonika 29,000 m2
47 Kawat nyamuk 21,000 m2
48 Kawat kassa 21,400 m2
49 Kawat duri 1,580 m'
50 Kawat bronjong 27,000 m2
50 Jaring pengaman plastik 6,500 bh
51 Plat Boundex 0.75 mm 125,000 m2
52 Turnbuckle M-16 45,000 bh
-
D TIANG PANCANG - K 500 -
1 Tiang Pancang 20x20 P. 6 ( Single joint) 170,000 m1
2 Tiang pancang 20x20 P. 6 ( Double joint) 250,000 m1
3 Tiang pancang30x30 P. 6 ( Double joint) 315,000 m1
4 Joint plate 25x25 ( Sudah termasuk pada tiang pancang ) - joint
5 Mob/Demob tiang pancang -
- Crane pancang + Hidrolik hammer 7 Ton ( 1 unit ) 35,000,000
- Crane service 5,000,000
6 Biaya lain - lain untuk pemancangan : - LS
- Keamanan alat 10,000,000 LS
- Perlengkapan safety 5,000,000 LS
- Akomodasi & transfortasi Crew 10,000,000 LS
- Asuransi Jamsostek 1,000,000 LS
11 Biaya pemotongan tiang pancang tiang pancang 45x45cm - joint
12 Biaya pemotongan tiang pancang tiang pancang 20x20cm 75,000 joint
13 Biaya pemotongan tiang pancang tiang pancang spun pile Ø 50 cm 115,000 joint
14 Biaya penyambungan tiang pancang 45x45cm ( Las AWS E6013 ) 165,000 joint
15 Biaya penyambungan tiang pancang 20x20cm ( Las AWS E6013 ) 110,000 joint
16 Biaya pemancangan tiang pancang 45x45cm 85,000 m1
17 Biaya pemancangan tiang pancang 20x20cm 70,000 m1
18 Biaya pemancangan tiang pancang spun pile Ø 50 cm - m1
19 Handling tiang pancang 15,000 m1
D KAYU
1 Kayu Kelas I, (Kayu Kamper dan sejenisnya) :
- Jenis Papan 2,980,523 m3
- Jenis Balok 4,639,694 m3
2 Kayu Kelas II, (Kayu Meranti dan sejenisnya)
- Jenis Papan 2,524,469 m3
- Jenis Balok 2,094,474 m3
3 Kayu Kelas III (Borneo dan sejenisnya)
- Jenis Papan 2,094,474 m3
- Jenis Balok 1,718,530 m3
- Kayu lokal kelas III 1,689,092 m3
4 Kayu lokal kelas IV (Kayu Albasia dan sejenisnya)
- Jenis Papan 1,557,825 m3
- Jenis Balok 1,450,206 m3
- Kayu lokal kelas III 1,689,092 m3
5 Dolken Ø 8-10cm panjang 4m - 5m 25,000 bt
6 Multiplek 18 mm phenolic 2 muka - lbr
7 Multiplek 18 mm - lbr
8 Multiplek 15 mm - lbr
9 Multiplek 12 mm phenolic 2 muka 122,600 lbr
6 Multiplek 12 mm 151,500 lbr
7 Multiplek 9 mm 122,600 lbr
8 Multiplek 6 mm 87,600 lbr
9 Multiplek 4 mm 69,100 lbr
10 Multiplek 3 mm 58,800 lbr
11 Teak wood ukuran normal ( Jati ) 3mm 91,600 lbr
12 Teak wood ukuran normal ( Jati ) 4mm 119,900 lbr
13 Formika uk. Besar 120 x 240 warna putih 200,000 lbr
14 Formika uk. Besar 120 x 240 warna 230,000 lbr
15 Melaminto uk. 120 x 240 ( Triplek lapis ) 150,000 lbr
16 Profil kayu jati Jabar 35,000 m1
II. BAHAN.
HARGA
NO JENIS MATERIAL SAT
Rp.
E BAHAN LANGIT - LANGIT
1 Silicate uk. 120 x 240 t=4mm ex. GRC 53,953 lbr
2 Silicate uk. 120 x 240 t=6mm ex. GRC 54,767 lbr
3 Gypsum water prof 2.4 x 1.2 t= 9 mm 127,427 lbr
4 Gypsum 2.4 x 1.2 t= 9 mm DN setara Jayaboard 46,091 lbr
5 Gypsum 2.4 x 1.2 t= 12 mm 65,069 lbr
6 List Gypsum T. 8 - 10 cm 10,000 m1
7 List Plafond Gypsum T, 5 - 7 cm 9,000 m1
8 Tepung Gypsum @ 20 kg 71,600 zak
9 Plafond Akustik 67,000 lbr
10 Textile tape 39,600 roll
11 Kalsiplank uk. 8 x 300 x 3000 setara ex. Kalsiboard 75,000 lbr
12 Rangka Metal BMSys ( untuk partisi gyfsum )
- Wall Track 41,300 pc(s)
- Wall Stud 45,800 pc(s)
- Jointing Compound UB-10/20/888/CCL 20kg/bag(s) 71,600 bag(s)
- UB Tape 75m/roll(s) 39,600 roll(s)
- Drywall Screw 25mmX083 500 pc(s)
- Jaya Sealant 580ml 20,000 pc(s)
II. BAHAN.
HARGA
NO JENIS MATERIAL SAT
Rp.
F.2 Granit ex.
1 Homogeneus 30 x 30 type Polised Setara Niro granit 247,000 m2
2 Homogeneus 40 x 40 type Polised Setara Niro granit 338,200 m2
3 Homogeneus 40 x 40 type Unpolised Setara Niro granit 257,600 m2
4 Homogeneus 60 x 60 type Polised Setara Niro granit 487,600 m2
5 Homogeneus 60 x 60 type Unpolised Setara Niro granit 391,200 m2
6 Homogeneus tile 60 x 60 type Polised Ex. Valentino gress super white 150,000 m2
7 Homogeneus 60 x 60 type polised Setara Garuda 103,900 m2
8 Plint Homogeneus 10 x 30 cm polised Setara lantai 25,000 bh
9 Plint Homogeneus 10 x 40 cm polised setara lantai 29,100 bh
10 Plint Homogeneus 10 x 60 cm polised setara lantai 30,000 bh
11 Stair nozing Homogeneus 10 x 30 unpolised 25,000 bh
12 Stair nozing Homogeneus 10 x 40 unpolised 30,000 bh
13 Stair nozing Homogeneus 10 x 20 unpolised 17,000 bh
14 Stair nozing Homogeneus 6 x 20 unpolised 15,000 bh
II. BAHAN.
HARGA
NO JENIS MATERIAL SAT
Rp.
25 Zincalume Hi- Tensile G 550 Union :
- Zinc - Allumunium Union Clip Panel 121,840 m2
- Prepainted Zinc - Allumunium Union 156,492 m2
- Zincalume Plat L = 90 CM t=0.45mm 97,500 m1
- Union Pesona TCT 0.45mm lebar 990mm Colorbond 133,110 m2
- Nok Standar untuk sudut atap curam 52,538 m1
- Nok Standar untuk sudut atap kurang dari 5⁰ 52,538 m1
26 Alumunium foil Setara Primary Smart - Foam 5 mm 46,000 m2
27 Polycarbonat t 6 mm setara twinlate/Impralon 107,400 m2
28 Rangka atap baja ringan ( Harga terpasang ) 165,000 m2
29 Alumunium Composite Panel forporated ex Alucomp type 03 326,700 m2
30 Alumunium Composite Panel ex Alucomp type 03 267,300 m2
31 Rangka alumunium hollow 33x38x1mm, MF, bracket besi hollow 40x40x4
zincromate + silicone sealant dan accessories 250,000 m2
II. BAHAN.
HARGA
NO JENIS MATERIAL SAT
Rp.
I JENIS CAT
1 Cat Tembok Dalam Setara Catilax ICI 45,000 Kg
2 Cat Tembok Dalam Setara Vinilex 55,000 Kg
3 Cat Tembok Dalam ex Nipponpaint 59,600 Kg
4 Cat Tembok Dalam ex Mowilex Type Acrylic Emulsion paint 62,000 Kg
5 Cat Tembok Dalam ex DULUX Type Acrylic Emulsion paint 65,000 Kg
6 Cat Tembok Dalam ex JOTUN Premium 62,000 Kg
7 Cat Tembok Luar ex Nipponpaint Type Weatherbond 106,000 Kg
8 Cat Tembok Luar ex Mowilex Type Weathercoat 95,000 Kg
9 Cat Tembok Luar ex DULUX Type Weathersheild 95,000 Kg
10 Cat Tembok Luar ex JOTUN Type Jotasheild 102,000 Kg
11 Cat Dasar Interior setara mutu tinggi 42,000 Kg
12 Cat Dasar Exterior setara mutu tinggi 46,000 Kg
12 Cat Kayu dan Besi setara mutu Seiv 55,000 kg
13 Cat Kayu dan Besi setara ICI. Dulux 55,000 ltr
14 Minyak cat standard biasa 15,000 Lt
15 Thiner ( minyak cat A spesial ) 35,000 Lt
16 Wood filer setara mutu tinggi 43,000 kg
17 Wood stand setara Impra 43,000 kg
18 Sanding Sealer setara Impra 39,000 Itr
19 Clear Melamic Setara Impra 45,000 kg
20 Meni kayu setara mutu menengah 55,000 kg
21 Meni besi setara mutu menengah 30,000 Lt
22 Plitur Impra 59,000 kg
23 Dempul kayu setara mutu menengah 20,000 kg
24 Dempul duko setara mutu tinggi 40,000 kg
25 Kwas setara Makita 17,500 bh
26 Rool cat 25,000 bh
27 Ampelas tembok 3,200 bh
28 Ampelas kayu & besi 3,200 bh
29 PlamIr tembok setara mutu ICI. Dulux 21,000 kg
30 Minyak bekisting 6,000 Lt
31 Ram kawat ayam 10,500 m2
32 Coating Primer 19,000 m2
33 Water Proofing Produck Sika :
- Sika rain Tite ( Untuk atap beton ) 40,000 kg
- Sika top 107 Seal ( Untuk toilet, balkon & area basah ) 18,000 kg
II. BAHAN.
HARGA
NO JENIS MATERIAL SAT
Rp.
- Sikafloor Epolem Module ( Water cistern & rain water tank ) 96,000 kg
- Sikagard 81 Epolem ( Water cistern & rain water tank ) 26,000 kg
- Sikagard 720 Epolem ( Water cistern & rain water tank ) 25,000 kg
- Sikagard 62 ( Water cistern & rain water tank ) 361,000 kg
- Sika Chapdur ( Floor hardener ) Natural 4,235 kg
- Sika Chapdur ( Floor hardener ) warna 5,082 kg
K SALURAN AIR
K.1 Saluran pipa air kotor
1 Buis beton 1/2 Ø 20 cm 60,000 bh
2 Buis beton 1/2 Ø 30 cm 80,000 bh
3 Buis beton Ø 20 cm panjang 1M 105,000 bh
4 Buis beton Ø 30 cm panjang 1M 140,000 bh
5 Buis beton Ø 40 cm panjang 1M 200,000 bh
6 Buis beton Ø 50 cm panjang 1M 310,000 bh
K.2 PVC
1 Pipa PVC Ø 1/2" setara standard AW 4,425 Meter
2 Pipa PVC Ø 3/4" setara standard AW 5,000 Meter
3 Pipa PVC Ø 1" setara standard AW 8,300 Meter
4 Pipa PVC Ø 1 1/4" setara standard AW 12,225 Meter
5 Pipa PVC Ø 1 1/2" setara standard AW 14,650 Meter
6 Pipa PVC Ø 2" setara standard AW 19,275 Meter
7 Pipa PVC Ø 2 1/2" setara standard AW 31,750 Meter
8 Pipa PVC Ø 3" setara standard AW 37,500 Meter
9 Pipa PVC Ø 4" setara standard AW 62,275 Meter
10 Pipa PVC Ø 5" setara standard AW 99,850 Meter
11 Pipa PVC Ø 6" setara standard AW 139,075 Meter
12 Pipa PVC Ø 8" setara standard AW 216,500 Meter
13 Pipa PVC Ø 10" setara standard AW 343,500 Meter
14 Lem PVC 84,000 kg
15 Gergaji besi 15,000 bh
14 BSP 15mm - Meter
15 BSP 25mm - Meter
16 BSP 32mm - Meter
17 BSP 40mm - Meter
18 BSP 50mm - Meter
19 BSP 65mm - Meter
20 BSP 80mm - Meter
21 BSP 100mm - Meter
22 BSP 125mm - Meter
23 BSP 150mm - Meter
24 BSP 200mm - Meter
P.5 POMPA
EX.VERSA
1 Pompa horisontal single stage 4,025,000 paket
2 Pompa transfer air bersih (2x 320 l/m) 3 phase, head 42 m paket
3 Pompa transfer air olahan (2x 320 l/m) 3 phase, head 42 m paket
4 Pompa booster air bersih (2x 150 l/m) 3 phase, head 10 m paket
5 Pompa sewage pit (2x 300 l/m) 3 phase, head 25 m paket
6 Pompa transfer air bersih (2x 500 l/m) 3 phase, head 60 m paket
7 Pompa transfer air olahan (2x 420 l/m) 3 phase, head 60 m paket
8 Pompa filter STP (300 l/m) 3 phase, head 25 m paket
9 Pompa filter air hujan (400 l/m) 3 phase, head 25 m paket
10 Pompa sumur dalam (150 l/m) 3 phase, head 100 m paket
11 Pompa booster air bersih (2x 120 l/m) 3 phase, head 10 m paket
12 Pompa booster air bersih (2x 110 l/m) 3 phase, head 10 m paket
13 Pompa bak kontrol (2x 100 l/m) 3 phase, head 20 m paket
14 Pompa grease trap (2x 100 l/m) 3 phase, head 15 m paket
15 Pompa pit basement (2x 300 l/m) 3 phase, head 15 m paket
16 Pompa pit ruang pompa (100 l/m) 3 phase, head 10 m paket
17 Pompa filter STP (300 l/m) 3 phase, head 15 m paket
18 Pompa filter air hujan (400 l/m) 3 phase, head 15 m paket
19 Pompa filter sumur (150 l/m) 3 phase, head 15 m paket
L SANITARY ACCESSORIES
1 1 Unit Closet duduk lengkap setara INA 1,183,000 unit
2 1 Unit Closet duduk setara Standart dengan tangki 1,800,000 unit
3 1 Unit Closet duduk porselin LUX dengan tangki 1,900,000 unit
II. BAHAN.
HARGA
NO JENIS MATERIAL SAT
Rp.
6 Closet jongkok unit
- CE 7 250,000 bh
- CE 6 567,200 bh
7 Urinal U 370 M 5,250,000 unit
8 Urinal U 57 M 1,500,000 unit
9 Urinal partition unit
- Urinal partition w/fittings tipe A100 1,150,000 unit
7 Washtafel Standart INA 1,016,000 unit
8 Washtafel Lux INA 1,200,000 unit
9 WASTAFEL L 521 V1A 1,332,500 unit
- L 521 V1A 525,000 bh
- T 205 MCB 199,500 bh
- TX 709-AN 318,000 bh
- TS 251 FT2N 165,000 bh
- TS 126 AR 125,000 bh
10 WASTAFEL L 237 V1B 1,456,000 unit
- L 237 V1B - bh
- T 205 MCB - bh
- T6 PV1 - bh
- TS 251 F - bh
- TS 126 AR - bh
11 WASTAFEL TOTO Type LW 535 J SHEET 2,581,000 unit
Lw 535 J bh
- T 205 QN bh
- TX 709 AV4N bh
- TS 251 FT2N bh
- TL 220 D bh
9 WASTAFEL L529 VI LENGKAP 1,655,000 unit
10 WASTAFEL L 38 V1 SHEET - unit
L 38 V1 bh
- T 205 MCB bh
- TX 709 AN bh
- TS 251 FT2N bh
- TS 126 AR & T 9 R, T 8 C bh
11 Wastafel pedestal ex. TOTO Tipe Vision LW 825 CJ komplit 1,408,000 unit
12 Wastafel dinding ex. TOTO Tipe LW 825 J komplit 4,058,000 unit
13 Bak mandi teraso volume air 0.30 m3 282,150 unit
14 Bak mandi fiberglass volume air 0.30 m3 183,750 unit
15 Bak mandi fiberglass volume air 1 m3 1,320,000 unit
16 Bath tube ex. Toto 3,750,000 unit
11 Kitchen zink setara 1 lobang stinless lengkap 385,000 unit
12 Meja beton untuk pantry 125x50 295,000 bh
15 Kran Air Biasa 69,000 unit
16 Belokan knee 1 inch 1,200 bh
Percabangan pipa 1 inch
Percabangan pipa 2 inch
17 Shower Spray TX 403 S N5 + TS 251 F 328,000 unit
18 Floor drain TX 1 AN 119,000 unit
19 Floor drain biasa 15,000 unit
20 Soap holder/Tempat sabun colour 29,000 unit
21 Kran dinding T 23B 13V7N 187,000 unit
22 Kran dinding T 30 AR13 V7N 299,000 unit
23 Kran dinding Toto tipe T 26-13 ( kran taman ) 725,000 unit
24 Kran dinding ex SUN-EI Type TY 20 JNR 195,000 unit
25 Hand shower set THX 17ZB/ TX 402 XZ 512,000 bh
26 Hand shower set THX 18ZB/ TX 402 XZ 622,000 bh
27 Hand shower set THX 19ZB/ TX 402 XZ 842,000 bh
28 Hand shower set TX 423 SZ/sink tap 591,000 bh
29 Gate valve 2 inch 525,000 bh
30 Pipa galvanised I inch 54,208 m
31 Pipa galvanised 2 inch 101,708 m
30 Hand shower B250 298,000 bh
31 Fixed Shower Head TX 422 S - Valve: TX 419 SCN 1,240,000 unit
32 Fixed shower head TB 18 D (Luxury shower head) 2,720,000 unit
33 Fixed shower head TX422SC - Valve: TX 419 SCN (Curio fixed shower head - 3 1,240,000 unit
34 Fixed shower head TX435SZ (3S Massage) 601,000 unit
35 Fixed shower head TX439SZ (3S Massage) 872,000 unit
36 Head shower ex. TOTO tipe TX422S + TX452SF + TGB 9 MZN 510,850 unit
37 Paper Holder ex. Toto :
- Paper Holder TS 116 R 209,000 bh
- Paper Holder TOTO TX 703 AC 268,000 bh
- Paper Holder TOTO TX11B 209,000 bh
38 Soap holder/Tempat sabun ex. Toto tipe :
- S 6N colour 61,000 unit
- S 11N colour 47,000 unit
- S 156N colour 61,000 unit
- S 160V1 colour 205,000 unit
- S 161 colour 294,000 unit
- Soap Dispencer TS 125 R 232,000 bh
- Soap Basket ex TOTO Type TX 2 BV1B 234,000 unit
II. BAHAN.
HARGA
NO JENIS MATERIAL SAT
Rp.
38 Tissue Dispencer ex. Toto tipe TX 8 374,400 unit
39 Grab Bar ex. Toto tipe :
- TX3A1 Grab Bar (Panjang 350 mm) 488,000 bh
- TX3A2 Grab Bar (Panjang 500 mm) 592,000 bh
- TX3A3 Grab Bar (Panjang 800 mm) 723,000 bh
40 Double Robe Hook TOTO Type TS 118 WS 92,000 bh
41 Towel bar ex. Toto tipe :
- Towel bar TX 5 B (L=660 mm) 449,000 bh
- Towel bar TX 5A2 (L=660 mm) 420,000 bh
- Towel bar TX 5A1 (L=558 mm) 383,000 bh
42 - Towel Ring TS 115 S 153,600 bh
M ACCESSORIES PINTU
Ex. setara Griff
1 Lockcase :
- Kenobset WC setara Griff 170,978 set
- Lockcase setara Griff ( untuk pintu dobel ) 223,125 bh
- Lockcase setara Griff ( untuk pintu singel ) 204,850 bh
- Lockcase setara Griff ( untuk pintu geser ) 236,725 bh
- Lockase KM ex setara Griff (untuk KM/WC) 252,450 bh
- Kunci Tanam besar 36,000 bh
- Kunci Tanam Kecil 29,000 bh
2 Lever Handle :
- Lever Handle setara Griff 72,450 psg
3 Double Cylinder :
- Double Cylinder 60mm normal setara setara Griff (untuk toilet) 273,000 bh
- Double Cylinder 60mm normal setara setara Griff Type 3301.60 157,000 bh
4 Tubular Pull Handle :
- Tubular Pull Handle setara Griff ( pintu kaca & alumunium ) 404,300 psg
- Tubular Pull Handle setara Griff ( pintu kayu ) 379,000 psg
- Tubular Pull Handle setara Griff ( pintu kayu & kaca ) 539,200 psg
- Tubular Pull Handle setara Griff ( pintu kaca ) 843,700 psg
- Pull Handle on Backplate 84,000 psg
5 Engsel pintu :
- Engsel setara Griff (4"x3"x2,5) washer 98,000 bh
- Engsel setara Griff (4"x3"x2,5) with ball beering 104,100 bh
6 Floor hinge setara setara Griff 952,000 set
7 Sliding track huskey 100 ex. setara Griff ( untuk pintu geser ) panjang 3 m 1,515,000 set
8 Engsel jendela :
- Friction stay setara Griff tipe 1909-SS-8" ( untuk boven jungkit ) 120,400 psg
9 Slot tarikan jendela alumunium :
- Rambuncis ex. setara Griff 51,000 bh
10 Fush Plate ( untuk pintu geser ) tipe :
- setara Griff 138,600 bh
13 Fushbolt : 126,500 bh
- Fushbolt tanam atas bawah 8+12" ex. setara Griff 210,500 psg
- Fushbolt ex setara Griff (untuk pintu Rangka) 175,000 psg
- Door Viewer ( untuk dudukan Fushbolt bawah ) 64,800 bh
14 Panicbar ( untuk pintu baja ) 2,915,000 bh
15 Floor hinge setara setara Griff , lengkap ( untuk pintu alumunium ) 1,320,000 bh
16 Top Fact fiting setara setara Griff ( untuk pintu kaca engsel atas ) 660,000 bh
17 Over & side panel Fact ex. setara Griff (untuk pasangan Top Pact - kaca ke ka 970,000 bh
18 Bottom Fact fiting setara setara Griff ( untuk pintu kaca engsel bawah ) 660,000 bh
19 Corner Lock setara setara Griff ( untuk kunci bawah pintu kaca ) 870,000 bh
20 Escutcheon ex. setara Griff 76,500 set
21 Door closer ex setara Griff 662,000 set
22 Sliding track huskey 100 ex. setara Griff ( untuk pintu geser ) panjang 2 m 827,000 set
23 Roda bulat Ø100mm 23,750 bh
II. BAHAN.
HARGA
NO JENIS MATERIAL SAT
Rp.
P TANAMAN
1 Angsana (2 s/d 3m) 178,000 btg
2 Bambu Jepang (2 s/d 3m) 105,300 m2
3 Bambu Kuning (2 s/d 3m) 126,000 m2
4 Rumput Gajah 6,000 m2
5 Rumput jepang 18,500 m2
6 Rumput peking 6,500 m2
7 Rumput bermuda ( terpasang belum PPN + keuntungan ) 92,800 m2
8 Pohon Kiara payung T= 1 - 2 m 40,000 btg
9 Pohon Nangka tinggi 40cm 12,500 btg
10 Lili Paris 3,000 btg
11 Klame of Irian 29,850 btg
12 Tanaman heloconia 8,900 btg
13 Pohon kecapi tinggi 40cm 11,500 btg
14 Pohon manggis t=2 - 4 m 75,000 btg
15 Pohon ceremai tinggi 40cm 47,500 btg
16 Dadap Merah t=2 - 4 m 228,000 btg
17 Pohon semak ekor tupai 32,500 btg
18 Pohon kaca piring tinggi 40cm 29,000 btg
19 Pohon trembesi t = 2,50 m - 3,00 m 397,500 btg
20 Palem botol (2 s/d 3m) 858,000 btg
21 Palem Raja t=2 - 4 m 214,500 btg
22 Pohon semak mahkota duri 14,000 btg
23 Pohon pisang - pisangan 12,000 btg
24 Pohon semak hias taiwan beuty 12,500 btg
25 Pohon hias bougenville t = 50 cm 35,500 btg
26 Pohon hias bougenville ping t = 50 cm 45,000 btg
27 Pohon hias bougenville ungu t = 50 cm 45,000 btg
28 Teh-Tehan ( Duranta) 3,250 btg
29 Perdu Oleander 23,500 btg
30 Pohon Sukun t=1,5 - 2 m 75,000 btg
31 Pohon Kelengkeng t=1 m 150,000 btg
32 Pohon Tabebuya Caraiba ` 134,400 btg
33 Pohon pucuk merah t=1 m 70,000 btg
34 Pohon bungur t=1,5 -3 m 95,000 btg
35 Pohon BarosT= 2,5 - 3 m 75,000 btg
36 Pohon Pinus t= 2,5 - 3 m 90,000 btg
37 Pohon Mahoni t= 2,5 - 3 m 115,000 btg
38 Pohon Kamboja t= 2,5 - 4 m 225,000 btg
39 Pohon Ketapang laut t= 2 - 4 m 145,000 btg
40 Pohon Ketapang kencana t= 2 - 4 m 185,000 btg
41 Pohon Biola cantik t=1 - 2 m 65,000 btg
42 Pohon Jabon t= 2,5 - 3 m 150,000 btg
43 Pohon Tanjung t= 2,5 - 3 m 65,000 btg
44 Pohon Kasia kuning t=1 m 50,000 btg
45 Pohon bunga kupu-kupu t= 1,5 - 3 m 65,000 btg
46 Aires polybeg 20 ( 1 Rumpun=1m2 ---25 pohon ) 1,500 btg
47 Lantana polybeg 20 ( 1 Rumpun=1m2 ---25 pohon ) 2,500 btg
48 Tegetes polybeg 20 ( 1 Rumpun=1m2 ---25 pohon ) 2,500 btg
N PAGAR
PAGAR PANEL BRC :
1 Ukuran 175x240 dia 8mm Elektroplating Galvanized 521,000 lbr
2 Ukuran 175x240 dia 8mm Hot dip Galvanized 693,000 lbr
3 Ukuran 175x240 dia 7mm Elektroplating Galvanized 398,000 lbr
4 Ukuran 175x240 dia 7mm Hot dip Galvanized 548,000 lbr
5 Ukuran 175x240 dia 6mm Elektroplating Galvanized 311,000 lbr
6 Ukuran 175x240 dia 6mm Hot dip Galvanized 413,000 lbr
1 Ukuran 190x240 dia 8mm Elektroplating Galvanized 549,000 lbr
2 Ukuran 190x240 dia 8mm Hot dip Galvanized 742,000 lbr
3 Ukuran 190x240 dia 7mm Elektroplating Galvanized 430,000 lbr
4 Ukuran 190x240 dia 7mm Hot dip Galvanized 588,000 lbr
5 Ukuran 190x240 dia 6mm Elektroplating Galvanized 326,000 lbr
6 Ukuran 190x240 dia 6mm Hot dip Galvanized 435,000 lbr
1 Ukuran 240x240 dia 8mm Elektroplating Galvanized 632,000 lbr
2 Ukuran 240x240 dia 8mm Hot dip Galvanized 856,000 lbr
3 Ukuran 240x240 dia 7mm Elektroplating Galvanized 493,000 lbr
4 Ukuran 240x240 dia 7mm Hot dip Galvanized 665,000 lbr
TIANG BRC :
1 Ukuran tinggi 175 dia 2" Elektroplating Galvanized 101,200 bh
2 Ukuran tinggi 175 dia 2" Hot dip Galvanized 122,100 bh
3 Ukuran tinggi 200 dia 2" Elektroplating Galvanized 118,800 bh
4 Ukuran tinggi 200 dia 2" Hot dip Galvanized 143,000 bh
5 Ukuran tinggi 220 dia 2" Elektroplating Galvanized 138,600 bh
6 Ukuran tinggi 220 dia 2" Hot dip Galvanized 159,500 bh
7 Ukuran tinggi 240 dia 2" Elektroplating Galvanized 158,500 bh
8 Ukuran tinggi 240 dia 2" Hot dip Galvanized 174,000 bh
9 Ukuran tinggi 300 dia 2" Elektroplating Galvanized 178,000 bh
10 Ukuran tinggi300 dia 2" Hot dip Galvanized 214,500 bh
Harga tianga diaatas sudah termasuk accessories ( tutup tiang, angkur dan U-Clip )
U. Atap
Komponen space frame : pipa Od 2,5"-16", balljoint T 84 - 300 M 16 / 42,
1 m2
base plate t=25mm + angkur M32-500 1,676,167.43
Komponen gording : dudukan gording, gording primer ∅3"t=2.8"(STK41),
2 m2
skunder ∅2" t=2.8mm(STK41), klem gording primer & sekunder 148,804.80
Komponen catwalk : dudukan catwalk ∅3" t=3mm, rangka baja CNP 125,
3 m2
siku 40.40.4, railling BSP Ø1" & expanded metal 604,103.80
Komponen Penutup atap geas Zipdeck : Standing seam (tapered)
4 m2
Colorbond TCT = 0,50mm (BMT), Alumunium Halter, Halter path 370,685.38
Lisplank Bulnose-Zinc Alum rangka pipa Ø2", hollow 40x40x2mm, hollow
5 m2
20x40x1,6mm + dudukan gording & ACPt=4mm 812,195.12
Komponen talang datar : Dudukan talang siku 50.50.5, pipa ∅ 2" t=2mm
6 STK 41, metal zincalume t=6mm, flshing zincalume t=6mm & corong
talang Od 12" 1,355,625.69 m2
- Harga per m2 atap space frame 2,416,490.94 bh
O LISTRIK
1 Kabel, NYM 3 x 2,5 mm2 13,500 M'
2 Pipa Conduit 8,000 M'
3 Socket Pipa 600 Bh
4 Tee Doos 5,100 Bh
5 Klem Pipa 600 Bh
6 Fhiser 3,600 Bh
7 Las Doop 4,358 Bh
8 Isolasi ban 10,000 Bh
9 Saklar Tunggal Single OB 11,000 Bh
10 Saklar Ganda ob 15,000 Bh
11 Stop Kontak In Bow 12,800 Bh
12 Lampu Philips LED 7 W 87,500 Bh
13 Lampu Philips LED 13 W 175,300 Bh
14 Lampu Philips LED 36 W 175,000 Bh
15 Lampu Philips PL 11 W 45,000 Bh
16 Lampu Flood light 250,000 Bh
17 Lampu Philips PL 18 W 49,500 Bh
18 Armateur Roseet Plafond 15,000 Bh
19 Armateur Downlight 4" 25,000 Bh
20 Armateur Downlight Outbow 4" 25,000 Bh
21 Lampu Baret TL 18 watt +Armateur Lampu Baret 30,000 Bh
22 Lampu Industrial Lampu Philips HPI-BU 250 watt + Cover 350,000 BH
23 Lampu Cold Storage 100 Watt + Cover 850,000 BH
24 Exhaust Fan 12" 210,000 Bh
25 Lampu LED Philips 2x 36 W + Armateur RM 650,000 Bh
26 Lampu LED Philips 2x 18 W + Armateur RM 450,000 Bh
27 MCCB 25 A, 3 P, 10 kA 253,000 Bh
28 7 x MCB 6 A, 1 P, 6 kA 205,000 Bh
29 fuse 2 A + fuse holder 9,500 Bh
30 3 x pilot lamp 74,000 Bh
31 1 lot busbar 40 A full neutral, 5 bus 110,900 Bh
32 1 lot internal wiring + aksesori 314,000 Bh
33 1 lot panel 50 (L) x 25 (D) x 60 (T) cm 470,000 Bh
34 1 lot instalasi kabel grounding 3,000,000 Bh
35 NYFGbY 2 x 120 sqmm 225,000 Bh
36 Alesis RA150 Stereo Power Amplifier 1,600,000 Bh
37 CCTV 16 chanel 12,000,000 pkt
38 AC split 2.5 PK 6,815,000 unit
39 Exhaust fan blower 70cm 400,000 bh
O LAIN LAIN
1 Solar 9,500
MinyakPelumas 55,000
A DAFTAR UPAH
1 Mandor Org/hr Rp 150,270.00
2 Kepala Tukang Batu Org/hr Rp 135,243.00
3 Kepala Tukang Kayu Org/hr Rp 135,243.00
4 Kepala Tukang Besi Org/hr Rp 135,243.00
5 Kepala Tukang Cat Org/hr Rp 135,243.00
6 Kepala Tukang Listrik Org/hr Rp 135,243.00
7 Kepala Tukang Org/hr Rp 135,243.00
8 Tukang Batu Org/hr Rp 100,180.00
9 Tukang Kayu Org/hr Rp 100,180.00
10 Tukang Besi/Baja Org/hr Rp 100,180.00
11 Tukang Cat Org/hr Rp 100,180.00
12 Tukang Listrik Org/hr Rp 100,180.00
13 Tukang Pipa Org/hr Rp 100,180.00
14 Tukang Plitur Org/hr Rp 100,180.00
15 Tukang Taman Org/hr Rp 100,180.00
16 Tukang Org/hr Rp 100,180.00
17 Pembantu Tukang Org/hr Rp 80,144.00
18 Pekerja Biasa Org/hr Rp 80,144.00
B. PEKERJAAN ELEKTRIKAL
1 Kabel NYM 3x2,5 mm2 Rp 14,950 m¹
2 Kabel NYY 4x25 mm2 Rp 135,000 m¹
3 Kabel NYY 4x4 mm2 Rp 34,500 m¹
4 Kabel NYY 4x6 mm2 Rp 42,000 m¹
5 Kabel NYY 4x10 mm2 Rp 74,000 m¹
6 Kabel NYY 4x50 mm2 Rp 264,000 m¹
7 Lampu Down Light LED 10 W Rp 224,250 bh
8 Lampu TL 36 Watt Rp 628,000 bh
9 Lampu SL 18 Watt Rp 85,000 bh
10 Lampu SL 11 Watt Rp 70,000 bh
11 Lampu SL 9 Watt Rp 50,000 bh
12 Lampu Jalan LED( 2 x 120 W ) IP-65+D299 Rp 14,000,000 bh
13 Saklar ganda 10 A Rp 41,000 bh
14 Saklar hotel 10 A Rp 46,900 bh
15 Saklar tunggal 10 A Rp 27,800 bh
16 Stop kontak daya 10/16 A Rp 62,600 bh
17 Stop kontak daya 10/16 A - 3 Phase Rp 475,700 bh
18 Socket Pipa Rp 700 bh
19 Tee Doos Rp 4,000 bh
20 Pipa Conduit Rp 5,600 m¹
21 Las Doop Rp 500 bh
22 Klem Pipa Rp 500 bh
23 Isolasi ban Rp 1,600 bh
24 Fhiser Rp 300 bh
25 Fuse & Indicator Rp 95,000 bh
26 Pilot Lamp Rp 23,400 bh
27 Box Panel ( 60 x 60 x 20 ) cm Rp 4,500,000 bh
28 Grounding BC 6-10 mm2 Rp 690,600 LS
29 Grounding BC 35 mm2 Rp 1,150,000 LS
30 MCB 10A/ 3 Pole, 6 kA Rp 98,810 bh
31 MCB 16A/ 3 Pole, 6 kA Rp 98,810 bh
32 MCB 20A/ 3 Pole, 10 kA Rp 175,727 bh
33 MCB 63A/ 3 Pole, 10 kA Rp 178,686 bh
34 Testing/pengukuran pentanahan Rp 1,000,000 titik
35 Tiang / Menara - dudukan EF, Pipa GSP, dia. 2" sepanj Rp 1,500,000 unit
36 Box Panel Plastik Golf Opaque Door (IEC 61439-3) 12 Rp 224,600 unit
C. PEKERJAAN MATV
1 Kabel Coaxial RG11( 0,6 mm2 ) Rp 14,400 m¹
D. PEKERJAAN DATA
1 HUB Un Managable Path Panel 1 x24 port Rp 6,400,000 bh
2 Gbit switch 1 x 24 Port Rp 13,500,000 bh
3 HUB Un Managable Path Panel 1 x 8 port + midspan PoRp 3,800,000 bh
4 Socket Data ( RG-45 ) Rp 99,900 bh
5 Kabel Fiber Optic Rp 300,000 bh
E. PEKERJAAN TELEPHONE
1 Socket Telephone RJ-11 Rp 99,900 bh
2 Terminal Box 10 Pairs Rp 515,300 bh
3 Terminal Box 20 Pairs Rp 777,000 bh
4 Kabel ITC 10x2x2x0,6 mm2 Rp 30,100 m¹
5 Kabel ITC 20x2x2x0,6 mm2 Rp 60,300 m¹
DAFTAR HARGA BAHAN DAN UPAH MEKANIKAL & PLUMBING
LANJUTAN PEMBANGUNAN IPWL
DI KABUPATEN TAKALAR SULAWESI SELATAN
B. PEKERJAAN VAC :
1 Exhaust Fan , Kapasitas : 150 CFM/ Wall Type Rp 435,000 unit
2 Exhaust Fan , Kapasitas : 200 CFM/ Wall Type Rp 580,000 unit
3 Exhaust Fan , Kapasitas : 250 CFM/ Wall Type Rp 725,000 unit
4 Exhaust Fan , Kapasitas : 300 CFM/ Wall Type Rp 870,000 unit
5 Exhaust Fan , Kapasitas : 350 CFM/ Wall Type Rp 1,015,000 unit
6 Exhaust Fan , Kapasitas : 500 CFM/ Wall Type Rp 1,450,000 unit
7 Exhaust Fan , Kapasitas : 750 CFM / Wall Type Rp 2,175,000 unit
8 Exhaust Fan , Kapasitas : 6000 CFM / Wall Type Rp 9,000,000 unit
9 Exhaust Fan , Kapasitas : 950 CFM/ Inline Type Rp 3,705,000 unit
10 Exhaust Fan , Kapasitas : 800 CFM/ Inline Type Rp 3,120,000 unit
11 Exhaust Fan , Kapasitas : 700 CFM/ Inline Type Rp 2,809,100 unit
12 Exhaust Fan , Kapasitas : 600 CFM/ Inline Type Rp 2,340,000 unit
13 Exhaust Fan , Kapasitas : 500 CFM/ Inline Type Rp 1,950,000 unit
14 Exhaust Fan , Kapasitas : 400 CFM/ Inline Type Rp 1,560,000 unit
15 Exhaust Fan , Kapasitas : 350 CFM/ Inline Type Rp 1,365,000 unit
16 Exhaust Fan , Kapasitas : 250 CFM/ Inline Type Rp 975,000 unit
17 Ceilling Fan Kapasitas 100 Cfm Rp 250,000 unit
18 Ceilling Fan Kapasitas 250 Cfm Rp 625,000 unit
19 Single Split ( OU + IU ) 16 000 BTU/h - Wall type Rp 6,500,000 unit
20 Single Split ( OU + IU ) 18 000 BTU/h - Wall type Rp 7,290,000 unit
21 Pemipaan Refrigrant 3/8 - 5/8" berisolasi Rp 115,000 m'
22 Pemipaan Refrigrant 1/4 - 1/2" berisolasi Rp 95,000 m'
23 Pemipaan Drain / PVC AW berisolasi Rp 75,000 m'
D. PEKERJAAN PLUMBING
1 Submersible kuras Rp 10,275,000 unit
2 GATE VALVE DIA.25 MM / 10 Kg Rp 154,700 bh
3 GATE VALVE DIA.32 MM / 10 Kg Rp 214,100 bh
4 GATE VALVE DIA.40 MM / 10 Kg Rp 373,500 bh
5 GATE VALVE DIA.50 MM / 10 Kg Rp 489,400 bh
6 GATE VALVE DIA.65 MM / 10 Kg Rp 616,400 bh
7 GATE VALVE DIA.80 MM / 10 Kg Rp 808,200 bh
8 Floor Clean Out dia. 50 mm Rp 150,700 bh
9 Floor Clean Out dia. 65 mm Rp 191,900 bh
10 Floor Clean Out dia. 80 mm Rp 234,700 bh
11 Floor Clean Out dia. 100 mm Rp 293,400 bh
12 Floor Clean Out dia. 150 mm Rp 325,000 bh
13 Roof Drain diameter 150 mm Rp 412,000 bh
14 Roof Drain diameter 100 mm Rp 372,600 bh
15 Roof Drain diameter 80 mm Rp 298,200 bh
16 Roof Drain diameter 65 mm Rp 225,000 bh
17 Bak Kontrol Rp 317,200 unit
18 PIPA PVC Dia. 1” Rp 10,960 m¹
19 PIPA PVC Dia. 1 1/2” Rp 24,700 m¹
20 PIPA PVC Dia. 1 1/4” Rp 15,300 m¹
21 PIPA PVC Dia. 2 1/2” Rp 43,600 m¹
22 PIPA PVC Dia. 2” Rp 31,900 m¹
23 PIPA PVC Dia. 3” Rp 62,200 m¹
24 PIPA PVC Dia. 4” Rp 91,100 m¹
25 PIPA PVC Dia. 6” Rp 187,700 m¹
26 PIPA PVC Dia. 8” Rp 221,600 m¹
27 PIPA PVC Dia. 10” Rp 268,000 m¹
28 SEPTIK TANK BIOLOGICAL SISTEM KAP. 1 M3 Rp 4,500,000 unit
29 SEPTIK TANK BIOLOGICAL SISTEM KAP. 2 M3 Rp 6,500,000 unit
30 SEPTIK TANK BIOLOGICAL SISTEM KAP. 3 M3 Rp 9,250,000 unit
31 SEPTIK TANK BIOLOGICAL SISTEM KAP. 4 M3 Rp 12,540,000 unit
32 SEPTIK TANK BIOLOGICAL SISTEM KAP. 16 M3 Rp 42,856,600 unit
33 Pompa Transfer ( Multi Stage ) Kapasitas : 5.5kW Rp 19,998,333 unit
34 Dosing Pump & Chemical tank Rp 10,650,000 unit
35 Dudukan Tanki Air Rp 1,775,000 unit
36 Reservoir bawah, FRP Modul Sistem, kapasitas : 100 M3 Rp 325,000,000 unit
37 Ploating valve dia 50 mm Rp 1,263,918 bh
38 Water Level Control ( WLC ) Rp 2,642,383 Set
39 GATE VALVE DIA.50 MM / 10 Kg Rp 425,000 bh
40 GATE VALVE DIA.65 MM / 10 Kg Rp 1,053,522 bh
41 FLEXIBLE JOINT DIA.65 MM/ 10 KG Rp 317,346 bh
42 STRAINER DIA.80 MM Rp 1,104,571 bh
43 CHECK VALVE DIA. 65 MM Rp 1,170,198 bh
44 Bobin Filter d.1600 Rp 98,700,000 bh
1 2 3 4 5 6