DI LOKASI……………………………………………………. UPL……………………………
No Nama Material VOL Sat Cek Cek
1 Line Tap 150/150 mm 3 Bh
2 A3C 70 mm 22,5 Mtr
3 Top teis (Bending) 3 Bh
4 Isolator 3 Bh
5 Crooss arm ……………….. 1 Bh
6 Arm tei type …………….. 1 Bh
7 Baut 16X400 2 Bh
8 Baut 16X50 1 Bh
9 Dudukan Trafo 1 Set
10 CO 3 Bh
11 LA 3 Bh
12 NYA 35 mm 4 Mtr
13 NYA 50 mm 3 Mtr
14 SKAT 70 mm 9 Bh
15 SKT 70 mm 8 Bh
16 SKT 150 mm 8 Bh
17 SKT 35/50 mm 19 Bh
18 Joint sleve AL-CU 70 mm 8 Bh
19 NYA 150 mm 35 Mtr
20 NYAF 4X70 mm 17 Mtr
21 Pipa 3 " - 6 mtr 1 Bh
22 L Bo 3 " - besi 1 Bh
23 Sock 3 " - besi 1 Bh
24 L Bo 3 " - PVC 3 Bh
25 Pipa 2 " - 6 mtr 2 Bh
26 L Bo 2 " - besi 2 Bh
27 Sock 2 " - besi 2 Bh
28 L Bo 2 " - PVC 3 Bh
29 Ground Rod 2,5 mtr 3 Bh
30 Pipa besi 3/4 " - 4 Mtr 3 Bh
31 Pipa besi 3/4 " - 1 Mtr 1 Bh
32 Link 6 Bh
33 Yuke 8 Bh
34 Stainless stell 5 Mtr
35 Penghalang Panjat 2 Bh
36 Tanda bahaya kecil 2 Bh
37 Tanda bahaya besar 1 Bh
38 Fusling 3 Bh
…………………
Cek Cek
67
47
59
52
36
44
38
38
54
32
50
52
32
43
644
REANCANA ANGGARAN BIAYA
Pekerjaan : Pasang Baru dan perubahaan Instalasi List
Lokasi : Dinas Peternakan Kab Bangkalan
HARGA SATUAN
N0 Nama material Sat Vol
Material
1 Kotak Panel 3 Phase dengan MCB 3 Phasa 25 A + Grounding set 1 Rp 3,000,000.00
2 Kabel U .(NYAF 4X6 mm) Mtr 4 Rp 200,000.00
3 Kabel Jalur NYAF 4X4 mm Mtr 0 Rp 8,000.00
4 Gambar&Jaminan Pelanggan daya 16500
5 Pasang Baru 3 Phasa 1 Rp 19,245,000.00
NB:
UNTUK NO. 3 MENYESUAIKAN KEADAAN DILAPANGAN
REANCANA ANGGARAN BIAYA
: Pasang Baru dan perubahaan Instalasi Listrik
: Dinas Peternakan Kab Bangkalan
JUMLAH Rp 27,065,000.00
PPN 10% Rp 2,706,500.00
JUMLAH TOTAL Rp 29,771,500.00
SUPRIYADI