INSTRUKSI KERJA PEKERJAAN PADA PENGGANTIAN

ISOLATOR SATU RENCENG UNTUK 70 kV PADA


ISOLATOR TIPE TUMPU VERTIKAL DALAM KONDISI
OFFLINE
NO: IK/MHAR/TRS.01-013

PT PLN (PERSERO)
TRANSMISI JAWA BAGIAN BARAT
2016
NO. DOKUMEN : IK/MHAR/TRS.01-013
PT.PLN ( PERSERO)
BERLAKU EFEKTIF : MEI 2016
TRANSMISI JAWA BAGIAN BARAT
CINERE 16514 – JAKARTA SELATAN DI BERIKAN KE :
INSTRUKSI KERJA PEKERJAAN PADA PENGGANTIAN ISOLATOR SATU RENCENG UNTUK 70 kV PADA
ISOLATOR TIPE TUMPU VERTIKAL DALAM KONDISI OFFLINE

I. DAFTAR ISI

I. DAFTAR ISI .............................................................................................................................................. I


II. LEMBAR PENGESAHAN.......................................................................................................................... II
III. DAFTAR DISTRIBUSI .............................................................................................................................. IV
IV. CATATAN PERUBAHAN .......................................................................................................................... V
1. TUJUAN ................................................................................................................................................. 1
2. RUANG LINGKUP ................................................................................................................................... 1
3. PERALATAN KERJA ................................................................................................................................. 1
4. PERLENGKAPAN K3................................................................................................................................ 2
5. PEKERJAAN MULAI ................................................................................................................................ 2
6. LANGKAH-LANGKAH PELAKSANAAN ..................................................................................................... 3
7. PEKERJAAN SELESAI............................................................................................................................... 3
8. NETWORK PLANING .............................................................................................................................. 4
9. DOKUMENTASI ...................................................................................................................................... 4
10.GAMBAR PERALATAN KERJA ................................................................................................................. 5
11.GAMBAR PERLENGKAPAN K3 ................................................................................................................ 6

EDISI : 01 REVISI : 00 HALAMAN : I


NO. DOKUMEN : IK/MHAR/TRS.01-013
PT.PLN ( PERSERO)
BERLAKU EFEKTIF : MEI 2016
TRANSMISI JAWA BAGIAN BARAT
CINERE 16514 – JAKARTA SELATAN DI BERIKAN KE :
INSTRUKSI KERJA PEKERJAAN PADA PENGGANTIAN ISOLATOR SATU RENCENG UNTUK 70 kV PADA
ISOLATOR TIPE TUMPU VERTIKAL DALAM KONDISI OFFLINE

II. LEMBAR PENGESAHAN

DIBUAT

NAMA JABATAN TANDA TANGAN TANGGAL

ENU SUHENDI EII STRATEGI HAR TJBB 14 APRIL 2016

SPV DAL HAR TRANSMISI


EDI BAGINDO 14 APRIL 2016
DAN KABEL TJBB

SPV ASESMEN TRANSMISI


EKO SUPRIYANTO 14 APRIL 2016
DAN KABEL TJBB

HERMAWAN JE HAR JARINGAN TJBB 14 APRIL 2016

BANGKIT MULYO JE REN HAR JARINGAN


14 APRIL 2016
KUNCORO TJBB

JE ASESMEN TRANSMISI
AGUNG ALIFSAG NUR 14 APRIL 2016
DAN KABEL TJBB

SPV HAR JARINGAN


ARIF SETYAWAN 14 APRIL 2016
APP CILEGON

SPV HAR JARINGAN


YULI KARYANTO 14 APRIL 2016
APP CAWANG

JE HAR JARINGAN
TONIH 14 APRIL 2016
APP CILEGON

JE HAR JARINGAN
BUDI WARDOYO 14 APRIL 2016
APP DURIKOSAMBI

JE HAR JARINGAN
HOLILUDIN 14 APRIL 2016
APP CAWANG

JE HAR JARINGAN
BAEHAQI 14 APRIL 2016
APP CILEGON

EDISI : 01 REVISI : 00 HALAMAN : II


NO. DOKUMEN : IK/MHAR/TRS.01-013
PT.PLN ( PERSERO)
BERLAKU EFEKTIF : MEI 2016
TRANSMISI JAWA BAGIAN BARAT
CINERE 16514 – JAKARTA SELATAN DI BERIKAN KE :
INSTRUKSI KERJA PEKERJAAN PADA PENGGANTIAN ISOLATOR SATU RENCENG UNTUK 70 kV PADA
ISOLATOR TIPE TUMPU VERTIKAL DALAM KONDISI OFFLINE

III. DAFTAR DISTRIBUSI

NO BIDANG/UNIT PERSONIL TANGGAL

GENERAL MANAGER

MANAGER BIDANG HAR

MANAGER BIDANG REN

MANAGER BIDANG KON

MANAGER BIDANG KSA

DM HAR JARINGAN

1 TJBB DM HAR GI

DM HAR PRO

DM PDKB DAN FASHAR

DM LK2

DM RENUS TI

DM ENJINEERING

DM MANAJEMEN ASET

2 APP CAWANG MANAGER

EDISI : 01 REVISI : 00 HALAMAN : IV


NO. DOKUMEN : IK/MHAR/TRS.01-013
PT.PLN ( PERSERO)
BERLAKU EFEKTIF : MEI 2016
TRANSMISI JAWA BAGIAN BARAT
CINERE 16514 – JAKARTA SELATAN DI BERIKAN KE :
INSTRUKSI KERJA PEKERJAAN PADA PENGGANTIAN ISOLATOR SATU RENCENG UNTUK 70 kV PADA
ISOLATOR TIPE TUMPU VERTIKAL DALAM KONDISI OFFLINE

NO BIDANG/UNIT PERSONIL TANGGAL

3 APP CILEGON MANAGER

4 APP DURIKOSAMBI MANAGER

5 APP PULOGADUNG MANAGER

NO PENGENDALIAN DOKUMEN :

EDISI : 01 REVISI : 00 HALAMAN : V


NO. DOKUMEN : IK/MHAR/TRS.01-013
PT.PLN ( PERSERO)
BERLAKU EFEKTIF : MEI 2016
TRANSMISI JAWA BAGIAN BARAT
CINERE 16514 – JAKARTA SELATAN DI BERIKAN KE :
INSTRUKSI KERJA PEKERJAAN PADA PENGGANTIAN ISOLATOR SATU RENCENG UNTUK 70 kV PADA
ISOLATOR TIPE TUMPU VERTIKAL DALAM KONDISI OFFLINE

IV. CATATAN PERUBAHAN


TANDA
REV PARAG DISAHKLAN FUNGSI/
TGL HAL ALASAN TANGAN
KE RAF OLEH JABATAN

*) Catatan : Ruang/Space formulir catatan perubahan dokumen ini dapat disesuaikan dengan
kebutuhan

EDISI : 01 REVISI : 00 HALAMAN : VI


NO. DOKUMEN : IK/MHAR/TRS.01-013
PT.PLN ( PERSERO)
BERLAKU EFEKTIF : MEI 2016
TRANSMISI JAWA BAGIAN BARAT
CINERE 16514 – JAKARTA SELATAN DI BERIKAN KE :
INSTRUKSI KERJA PEKERJAAN PADA PENGGANTIAN ISOLATOR SATU RENCENG UNTUK 70 kV PADA
ISOLATOR TIPE TUMPU VERTIKAL DALAM KONDISI OFFLINE

1. TUJUAN
Intruksi kerja ini disusun sebagai petunjuk pelaksanaan pekerjaan dalam keadaan tidak
bertegangan (OFF LINE) pada ISOLATOR SUTT 70kV untuk isolator tipe tumpu vertikal.

2. RUANG LINGKUP
Meliputi pekerjaan pada:
a. Penggantian Isolator satu renceng untuk 70kV isolator Tipe tumpu vertikal

3. PERALATAN KERJA
VOLUME
NO NAMA ALAT UKURAN SATUAN
70kV
1 Tambang safety line 5/8 ‘’ x 100 m Roll 1
2 Tambang Transportasi 5/8” Roll 1
3 Snatch Block 1250-2500 lbs Buah 3
4 Capstan Hoist + Asesoris Set 1
5 lever block 1 ½ - 3 ton Buah 1
6 Webbing Sling 1 meter 1 ½ - 3 ton Buah 3
7 Webbing Sling 2 meter 1 ½ - 3 ton Buah 2
8 Tool Kit Set 2
9 Tools Bag Buah 1
10 Shackle 2-3 ¼ ton Buah 3
Spesial Tools (pengaman yolk
11 optional Buah
double isolator)
12 Karabiner Besar 30 KN Buah 2
13 Karabiner Kecil 22-25 KN Buah 4
14 Terpal Plastik 4x4m Lembar 2
15 Portable Generator 3 kVA Buah 1

EDISI : 01 REVISI : 00 HALAMAN : 1


NO. DOKUMEN : IK/MHAR/TRS.01-013
PT.PLN ( PERSERO)
BERLAKU EFEKTIF : MEI 2016
TRANSMISI JAWA BAGIAN BARAT
CINERE 16514 – JAKARTA SELATAN DI BERIKAN KE :
INSTRUKSI KERJA PEKERJAAN PADA PENGGANTIAN ISOLATOR SATU RENCENG UNTUK 70 kV PADA
ISOLATOR TIPE TUMPU VERTIKAL DALAM KONDISI OFFLINE

4. PERLENGKAPAN K3
VOLUME
NO NAMA ALAT UKURAN SATUAN
70kV
1 Full Body Hardness Buah 3
2 Rope adjuster Buah 3
3 Lanyard Buah 3
4 Safety Helmet Buah 7
5 Safety Shoes Pasang 7
6 Safety Gloves Pasang 7
7 Kaca Mata Pengaman Buah 7
8 Rambu – Rambu K3 Set 1
9 Perlengkapan P3K Set 1
10 Rompi Pengawas Buah 2
11 Perlengkapan Komunikasi Buah 2
Perlengkapan Diskusi Lengkap
12 Buah 1
Dengan Buku Instruksi Kerja

5. PEKERJAAN MULAI
NO. PIC DURASI
NO LANGKAH-LANGKAH PELAKSANAAN KEGIATAN
LINT. (JML) (MENIT)
PERSIAPAN PEKERJAAN
Menyatakan bahwa kondisi sudah tidak
1 1 bertegangan dan telah di lakukan grounding 1A PP (1) 10
sistim di GI
Lakukan Safety meeting dan pembagian PP dan PK3
2 2 1B 10
tugas (2)
3 3 Memimpin doa sebelum pekerjaan dimulai 1C PK3 (1) 10

EDISI : 01 REVISI : 00 HALAMAN : 2


NO. DOKUMEN : IK/MHAR/TRS.01-013
PT.PLN ( PERSERO)
BERLAKU EFEKTIF : MEI 2016
TRANSMISI JAWA BAGIAN BARAT
CINERE 16514 – JAKARTA SELATAN DI BERIKAN KE :
INSTRUKSI KERJA PEKERJAAN PADA PENGGANTIAN ISOLATOR SATU RENCENG UNTUK 70 kV PADA
ISOLATOR TIPE TUMPU VERTIKAL DALAM KONDISI OFFLINE

6. LANGKAH-LANGKAH PELAKSANAAN
NO. PIC DURASI
NO LANGKAH-LANGKAH PELAKSANAAN KEGIATAN
LINT. (JML) (MENIT)
PELAKSANAAN PEKERJAAN
1 4A Lakukan pemasangan Rambu dan Safety Line 2A TIM HAR (2) 20
Lakukan tes tegangan dan Pasang Grounding
2 5 2B TIM HAR (4) 10
lokal
3 4B Pasang capstan hoist pada kaki tower 2C TIM HAR (2) 30
Naikkan dan pasang web sling, Snatch Block
4 6 2D TIM HAR (4) 10
serta tambang transportasi
Naikkan alat-alat kerja dan tempatkan toll
5 7 2E TIM HAR (4) 20
bag pada possinya
Pasang lever block serta pasang pada
6 8 2F TIM HAR (4) 10
tempatnya
Lepaskan ikatan isolator dengan konduktor
Mengambil alih beban konduktor dengan
7 9 2G TIM HAR (4) 30
lever block
ikat isolator ke tambang transportasi
10 10 lepas dan turunkan isolator 2H TIM HAR (4) 10
11 11 naikkan isolator pengganti 2I TIM HAR (4) 10
Balik urutan instruksi kerja untuk
12 12 2J TIM HAR (4) 30
menyelesaikan pekerjaan
Turun kan semua peralatan dari
13 13 2K TIM HAR (4) 20
tower,periksa secara seksama
14 14A Buka grounding lokal 2L TIM HAR (4) 10
Lepas Safety Line, capstain hoist dan rambu-
15 14B 2M TIM HAR (4) 20
rambu

7. PEKERJAAN SELESAI
NO. PIC DURASI
NO LANGKAH-LANGKAH PELAKSANAAN KEGIATAN
LINT. (JML) (MENIT)
PEKERJAAN SELESAI
koordinasi dengan pengawas manuver
1 15 3A PP (1)
bahwa pekerjaan telah selesai 20
2 16 Memimpin doa setelah pekerjaan selesai 3B PK3 (1)

EDISI : 01 REVISI : 00 HALAMAN : 3


NO. DOKUMEN : IK/MHAR/TRS.01-013
PT.PLN ( PERSERO)
BERLAKU EFEKTIF : MEI 2016
TRANSMISI JAWA BAGIAN BARAT
CINERE 16514 – JAKARTA SELATAN DI BERIKAN KE :
INSTRUKSI KERJA PEKERJAAN PADA PENGGANTIAN ISOLATOR SATU RENCENG UNTUK 70 kV PADA
ISOLATOR TIPE TUMPU VERTIKAL DALAM KONDISI OFFLINE

8. NETWORK PLANING
Terlampir

9. DOKUMENTASI
Instruksi Kerja ini didokumentasikan dalam bentuk hard copy (kertas) dan Soft Copy (CD) serta
pengendaliannya diatur dalam “PROSEDUR PENGENDALIAN DOKUMEN”.

EDISI : 01 REVISI : 00 HALAMAN : 4


NO. DOKUMEN : IK/MHAR/TRS.01-013
PT.PLN ( PERSERO)
BERLAKU EFEKTIF : MEI 2016
TRANSMISI JAWA BAGIAN BARAT
CINERE 16514 – JAKARTA SELATAN DI BERIKAN KE :
INSTRUKSI KERJA PEKERJAAN PADA PENGGANTIAN ISOLATOR SATU RENCENG UNTUK 70 kV PADA
ISOLATOR TIPE TUMPU VERTIKAL DALAM KONDISI OFFLINE

10. GAMBAR PERALATAN KERJA

TAMBANG SAFETY TAMBANG


SNATCH BLOCK CAPSTAN HOIST
LINE TRANSPORTASI

WEBBING SLING 1 WEBBING SLING 2


LEVER BLOCK TOOL KIT
METER METER

TOOLS BAG SHACKLE SPESIAL TOOLS KARABINER BESAR

PORTABLE
KARABINER KECIL TERPAL PLASTIK
GENERATOR

EDISI : 01 REVISI : 00 HALAMAN : 5


NO. DOKUMEN : IK/MHAR/TRS.01-013
PT.PLN ( PERSERO)
BERLAKU EFEKTIF : MEI 2016
TRANSMISI JAWA BAGIAN BARAT
CINERE 16514 – JAKARTA SELATAN DI BERIKAN KE :
INSTRUKSI KERJA PEKERJAAN PADA PENGGANTIAN ISOLATOR SATU RENCENG UNTUK 70 kV PADA
ISOLATOR TIPE TUMPU VERTIKAL DALAM KONDISI OFFLINE

11. GAMBAR PERLENGKAPAN K3

FULL BODY HARDNESS ROPE ADJUSTER LANYARD SAFETY HELMET

KACA MATA
SAFETY SHOES SAFETY GLOVES RAMBU – RAMBU K3
PENGAMAN

PERLENGKAPAN
PERLENGKAPAN P3K ROMPI PENGAWAS BUKU SOP, IKA, P3K
KOMUNIKASI

EDISI : 01 REVISI : 00 HALAMAN : 6


INSTRUKTUR KERJA PERBAIKAN/PENGGANTIAN ISOLATOR SATU RENCENG TIPE TUMPU
TOWER SUSPENSION 70kV
No. Jml. JUMLAH DURASI
LANGKAH-LANGKAH PELAKSANAAN Kegiatan PIC jam 1 jam 2 jam 3 jam 4
Lintasan Pelaksana WAKTU
10 20 30 40 50 60 10 20 30 40 50 60 10 20 30 40 50 60 10 20 30 40 50 60
Persiapan Pekerjaan
Menyatakan bahwa kondisi sudah tidak
1 bertegangan dan telah di lakukan grounding 1A 1 PP 10
sistim di GI
2 Lakukan Safety meeting dan pembagian tugas 1B 2 PP dan PK3 10
3 Memimpin doa sebelum pekerjaan dimulai 1C 1 PK3 10
Pelaksanaan Pekerjaan
4A Lakukan pemasangan Rambu dan Safety Line 2A 2 20

5 Lakukan tes tegangan dan Pasang Grounding lokal 2B 4 10


4B Pasang capstan hoist pada kaki tower 2C 2 30
Naikkan dan pasang web sling, Snatch Block serta
6 2D 4 10
tambang transportasi
Naikkan alat-alat kerja dan tempatkan toll bag
7 2E 4 20
pada possinya
8 Pasang lever block serta pasang pada tempatnya 2F 4 10
Lepaskan ikatan isolator dengan konduktor
Mengambil alih beban konduktor dengan lever TIM HAR
9 2G 4 30
block
ikat isolator ke tambang transportasi
10 lepas dan turunkan isolator 2H 4 10
11 naikkan isolator pengganti 2I 4 10
Balik urutan instruksi kerja untuk menyelesaikan
12 2J 4 30
pekerjaan
Turun kan semua peralatan dari tower,periksa
13 2K 4 20
secara seksama
14A Buka grounding lokal 2L 4 10
Lepas Safety Line, capstain hoist dan rambu-
14B 2M 4 20
rambu
Pekerjaan Selesai
15 pekerjaan telah selesai 3A 1 PP
20
16 Memimpin doa setelah pekerjaan selesai 3B 1 PK3
TOTAL WAKTU 10 20 30 40 50 60 70 80 90 100 110 120 130 140 150 160 170 180 190 200 210 220 230 240

CRITICAL PATH PERBAIKAN/PENGGANTIAN ISOLATOR SATU RENCENG TIPE TUMPU


TOWER SUSPENSION 70kV
0 0 2A 4A 20 2B 5 30 2D 6 40 2E 7 60 2G 9 90 2H 10 100
0 0 20 2 20 10 4 30 10 4 40 20 4 60 30 4 90 10 4 100
2F 10
2C 4A 30 8 60
30 2 30 4 60
2I 10
14A170 2L 13 160 2K 12 140 2J 11 110
4 170 10 4 160 20 4 140 30 4 110

14B180 2M
4 180 20