RINCIAN ANGGARAN BIAYA

RENOVASI RUMAH CIBUBUR BAGIAN BELAKANG

NO JENIS PEKERJAAN SATUAN HARGA (Rp)

I PEKERJAAN BONGKARAN
1 Bobok Dinding dan Bongkar Pintu Kamar Mandi m2 207,900
2 Urugan Puing m3 1,824,000

II PEKERJAAN BETON
1 Gali Tanah & Pasang Pondasi Cakar Ayam (ukuran 30 x 30 x 15) unit 2,800,000
2 Beton Sloof m1 1,087,500
3 Beton Kolom m1 5,600,000
4 Beton Balok m1 1,087,500
5 Cor Meja Beton Dapur (ukuran 60 x 100) unit 750,000

III PEKERJAAN DINDING & KERAMIK


1 Pasang Dinding Hebel 7,5 cm m2 2,365,000
2 Plester Aci m2 2,687,500
3 Pasang Keramik Lantai Granit 60/60 m2 10,260,000
4 Pasang Keramik Dinding Kamar Mandi Dan Ruang Cuci & Dapur m2 2,782,500
5 Pasang Batu Alam m2 16,920,000
6 Bongkar Pintu Dan Pasang Pintu Sliding unit 3,500,000
7 Pasang Kembali Pintu Kamar Mandi unit 300,000
V PEKERJAAN ATAP
1 Pasang Rangka Hollow Alumunium 4,4 x 9,5 + Atap Alderon Transculent m2 16,320,000
2 Pasang Rangka Hollow Alumunium 4,4 x 9,5 + Atap Kaca 8 mm atau 10 mm Tem m2 39,100,000
3 Pasang Talang Air Galvanis Coating m2 3,300,000
4 Pasang Kawat Nyamuk Stenlis unk Ventilasi ls 500,000

VII PEKERJAAN CAT


1 Amplas + Skraf + Cat Dasar + Cat Dulux Weathershield m2 2,800,000

VIII PEKERJAAN MEKANIKAL & ELEKTRIKAL


1 Pasang Instalasi + Saklar + Lampu Led Philips ttk 2,100,000
2 Pasang Instalasi + Stop Kontak ttk 1,200,000
3 Pasang Kran Air + Instalasi bh 800,000
4 Pasang Floor Drain + Instalasi Pipa bh 1,000,000
5 Pasang Pompa Taman bh 500,000
Perapihan Bak Kontrol ls 1,000,000

TOTAL 120,791,900

CATATAN :
1. Air & Listrik Kerja menjadi tanggung Jawab Pemilik Rumah
2. Pemilik harus memberi tempat tinggal pekerja
3. Izin terhadap lingkungan sekitar menjadi tanggung jawab pemilik
4. Bila ada bentuk premanisme terhadap kami yang kerja, maka akan menjadi tanggung jawab pemilik
5. Bila ada pekerjaan diluar uraian pekerjaan diatas, maka menjadi pekerjaan tambah dan akan dibicarakan dahulu dgn Pemilik

Jakarta, 11 Maret 2021


Hormat Kami

Ir. Benny Siswanto


RINCIAN ANGGARAN BIAYA
RENOVASI RUMAH CIBUBUR BAGIAN BELAKANG

NO JENIS PEKERJAAN SAT

I PEKERJAAN URUGAN
1 Urugan Puing m3

II PEKERJAAN BETON
1 Gali Tanah & Pasang Pondasi Cakar Ayam (ukuran 30 x 30 x 15) unit
2 Beton Sloof m1
3 Beton Kolom m1
4 Beton Balok m1

III PEKERJAAN DINDING & KERAMIK


1 Pasang Dinding Hebel 7,5 cm m2
2 Plester Aci m2
3 Pasang Keramik Lantai Granit 60/60 m2
4 Pasang Keramik Dinding Kamar Mandi Dan Ruang Cuci & Dapur m2
5 Pasang Batu Alam m2
6 Bongkar Pintu Dan Pasang Pintu Sliding unit

IV PEKERJAAN ATAP
1 Pasang Rangka Hollow Alumunium 4,4 x 9,5 + Atap Alderon Transculent m2
2 Pasang Rangka Hollow Alumunium 4,4 x 9,5 + Atap Kaca 8 mm atau 10 mm Tem m2
3 Pasang Talang Air Galvanis Coating m2
4 Pasang Kawat Nyamuk Stenlis unk Ventilasi ls

V PEKERJAAN CAT
1 Amplas + Skraf + Cat Dasar + Cat Dulux Weathershield m2

VI PEKERJAAN MEKANIKAL & ELEKTRIKAL


1 Pasang Instalasi + Saklar + Lampu Led Philips ttk
2 Pasang Instalasi + Stop Kontak ttk
3 Pasang Kran Air + Instalasi bh
4 Pasang Floor Drain + Instalasi Pipa bh
5 Pasang Pompa Taman bh
6 Perapihan Bak Kontrol ls

TOTAL

CATATAN :
1. Air & Listrik Kerja menjadi tanggung Jawab Pemilik Rumah
2. Pemilik harus memberi tempat tinggal pekerja
3. Izin terhadap lingkungan sekitar menjadi tanggung jawab pemilik
4. Bila ada bentuk premanisme terhadap kami yang kerja, maka akan menjadi tanggung jawab pemilik
5. Bila ada pekerjaan diluar uraian pekerjaan diatas, maka menjadi pekerjaan tambah dan akan dibicarakan dahulu dgn

Jakarta, 16 April 2021


Hormat Kami

Ir. Benny Siswanto


1,824,000

2,450,000
875,000
4,400,000
875,000

2,120,800
2,410,000
10,260,000
2,782,500
16,920,000
3,500,000

32,640,000
15,640,000
3,300,000
500,000

2,800,000

2,100,000
1,200,000
800,000
1,000,000
500,000
1,000,000

109,897,300

anggung jawab pemilik


mbah dan akan dibicarakan dahulu dgn Pemilik