II BAHAN / MATERIAL
1 Air m3 M.02 25,000.00
2 Batu bata / merah bakar kelas I bh M.04.a 550.00
3 Batu bata / merah bakar kelas II bh M.04.b 500.00
4 Batu gunung m3 M.05 181,500.00
5 Batu brojol/batu kali m3 M.06 198,000.00
6 Kerikil/Koral/Agregat Beton m3 M.12 319,000.00
7 Pasir beton m3 M.14.a 220,000.00
8 Pasir pasang kali/gunung m3 M.14.b 192,500.00
9 Pasir urug m3 M.14.d 178,200.00
10 Portland Cement (PC 50 kg / zak) Zak M.15 68,000.00
11 Sirtu m3 M.16 187,000.00
12 Tanah urug m3 M.17.b 143,000.00
13 Kayu klas 3 m3 M.33.a 4,500,000.00
14 Kayu kelas 2 m3 M.35.c 8,000,000.00
15 Baja Tulangan kg M.55.d 13,000.00
16 Kawat beton / Bendrat kg M.60 22,000.00
17 Paku kg M.64.a 16,500.00
18 Linggis (Baja keras) bh To.13 105,000.00
19 Pahat Beton (baja keras) bh To.14 75,000.00
20 Palu/godam pemecah batu bh To.15 178,000.00
III PERALATAN
1 Jack hammer Sewa-hari E.14 250,000.00
2 Waterpass Sewa-hari E.50 175,000.00
3 Theodolit Sewa-hari E.41 175,000.00
4 Tripod tinggi 5 m Sewa-hari E.45 200,000.00
5 Chainsaw Sewa-hari E.06 175,000.00
JADWAL WAKTU PELAKSANAAN PEKERJAAN
NOMOR PAKET :
NAMA PEKERJAAN : REHABILITASI JARINGAN IRIGASI
LOKASI / PROPINSI : KABUPATEN LOMBOK BARAT, PROVINSI N.T.B.
BAGIAN PROYEK / PROYEK : SWAKELOLA
PELAKSANA :
Disetuji,
Pejabat Pembuat Komitmen ( PPK )
WISMP II
KHAIRUL SUDRAJAT, ST
NIP. 19830304 201001 1 018
JADWAL WAKTU PELAKSANAAN PEKERJAAN
NOMOR PAKET :
NAMA PEKERJAAN : REHABILITASI JARINGAN IRIGASI GEGUTU
LOKASI / PROPINSI : KABUPATEN LOMBOK BARAT, PROVINSI N.T.B.
BAGIAN PROYEK / PROYEK :
PELAKSANA : GABUNGAN P3A GEGUTU
Nomor
Mata Harga Satuan Jumlah Harga
Uraian Pekerjaan Sat. Volome
Pemba Rp. Rp.
yaran
1 2 3 4 5 6=4x5
BANTIR, 2020
KT.
Ketua
DAFTAR KEBUTUHAN UPAH PEKERJA DAN BAHAN DAERAH IRIGASI TERSIER
Keterangan
- Bahan : Rp 84,935,782.85
- Upah Tenaga : Rp 63,864,253.15
- Pek. Persiapan : Rp 1,200,000.00
- Total Biaya 150,000,036.00
DAFTAR HARGA SATUAN UPAH DAN BAHAN
NOMOR PAKET :
NAMA PEKERJAAN : REHABILITASI JARINGAN IRIGASI TERSIER (RJITT)
I. TENAGA KERJA
II. BAHAN
1 Batu Gunung m3 181,500.00
2 Pasir Pasang m3 192,500.00
3 Portland Cement ( PC ) Zak 68,000.00
4 Tanah Urug m3 143,000.00
5 Kerikil m3
6 Kawat Beronjong Kg. -
7 Paku Kg.
8 Besi Beton Kg.
9 Kayu Perancah m3 -
10 Kayu Bekisting m3 -
11 Kawat beton Kg. -
12 Kawat Dilgavanis 4 mm. Kg. -
A UPAH
B BAHAN
C JUMLAH 817,680.00
D BIAYA UMUM DAN KEUNTUNGAN = 10 % X C ( TIDAK DIPUNGUT)
E JUMLAH HARGA SATUAN PEKERJAAN = C + D 817,680.00
F JUMLAH HARGA SATUAN DIBULATKAN 817,680.00
0
0
0
ANALISA HARGA SATUAN
A UPAH
B BAHAN
1 Batu m3 - -
2 Pasir m3 0.012 192,500.00 2,310.00
3 Portland Cement ( PC ). 50 Kg. Kg 6.340 1,360.00 8,622.40
C JUMLAH 46,332.40
D BIAYA UMUM DAN KEUNTUNGAN = 10 % X C ( TIDAK DIPUNGUT)
E JUMLAH HARGA SATUAN PEKERJAAN = C + D 46,332.40
F JUMLAH HARGA SATUAN DIBULATKAN 46,332.40
0
0
0
0
ANALISA HARGA SATUAN
A UPAH
B BAHAN
1 Batu m3 - -
2 Pasir m3 0.030 192,500.00 5,775.00
3 Portland Cement ( PC ). 50 Kg. Kg 7.776 1,360.00 10,575.36
C JUMLAH 61,662.36
D BIAYA UMUM DAN KEUNTUNGAN = 10 % X C ( TIDAK DIPUNGUT)
E JUMLAH HARGA SATUAN PEKERJAAN = C + D 61,662.36
F JUMLAH HARGA SATUAN DIBULATKAN 61,662.36
0
0
0
Ketua
ANALISA HARGA SATUAN
A UPAH
B BAHAN
1 Batu m3 - - -
2 Pasir m3 - 192,500.00 -
3 Portland Cement ( PC ). 50 Kg. Kg - 1,360.00 -
C JUMLAH 41,099.00
D BIAYA UMUM DAN KEUNTUNGAN = 10 % X C ( TIDAK DIPUNGUT)
E JUMLAH HARGA SATUAN PEKERJAAN = C + D 41,099.00
F JUMLAH HARGA SATUAN DIBULATKAN 41,099.00
0
0
0
Ketua
ANALISA HARGA SATUAN
A UPAH
B BAHAN
C JUMLAH 200,800.00
D BIAYA UMUM DAN KEUNTUNGAN = 10 % X C ( TIDAK DIPUNGUT)
E JUMLAH HARGA SATUAN PEKERJAAN = C + D 200,800.00
F JUMLAH HARGA SATUAN DIBULATKAN 200,800.00
DAFTAR REKAPITULASI RENCANA ANGGARAN BIAYA
NOMOR PAKET :
NAMA PEKERJAAN : REHABILITASI JARINGAN IRIGASI TERSIER
LOKASI / PROPINSI : KABUPATEN LOMBOK BARAT, PROPINSI N.T.B.
BAGIAN PROYEK / PROYEK : SWAKELOLA
PELAKSANA : -
1 BAB. I
PEKERJAAN PERSIAPAN 1,200,000.00
2 BAB. II
PEKERJAAN SALURAN 148,800,036.00
Bantir, 2020
Ketua
Ketua
PERHITUNGAN VOLUME BANGUNAN
Pekerjaan :
Tahun Anggaran :
Lokasi :
VOLUME GALIAN
R.0 0.26 m²
0.31 m² 50.00 m 0.31 m² x 50.00 m 15.25 m³
R.1 0.35 m²
0.85 m² 50.00 m 0.85 m² x 50.00 m 42.25 m³
R.2 1.34 m²
1.32 m² 50.00 m 1.32 m² x 50.00 m 65.75 m³
R.3 1.29 m²
1.04 m² 40.00 m 1.04 m² x 40.00 m 41.40 m³
R.4 0.78 m²
0.39 m² 17.00 m 0.39 m² x 17.00 m 0.00 m³
R.5 0.00 m²
0.00 m² 0.00 m 0.00 m² x 0.00 m 0.00 m³
R.6 0.00 m²
0.00 m² 0.00 m 0.00 m² x 0.00 m 0.00 m³
R.7 0.00 m²
0.00 m² 0.00 m 0.00 m² x 0.00 m 0.00 m³
R.8 0.00 m²
0.00 m² 0.00 m 0.00 m² x 0.00 m 0.00 m³
R.9 0.00 m²
207.00 m 164.65 m³
PASANGAN
1 0.35 m² 0.35 m² 207.00 m 0.35 m² x 207 m x 2 144.90 m³
0.00 m² 0.00 m² 0.00 m 0.00 m² x 0m x 2 0.00 m³
144.90 m³
SIARAN
1 0.62 m² 0.62 m² 207.00 m 0.62 m² x 207 m x 2 256.68 m³
0.00 m² 0.00 m² 0.00 m 0.00 m² x 0m x 2 0.00 m³
256.68 m³
PELESTERAN
1 0.40 m² 0.40 m² 207.00 m 0.40 m² x 207 m x 2 165.60 m³
0.40 m² 0.40 m² 0.00 m 0.40 m² x 0m x 2 0.00 m³
165.60 m³