Table of Contents
1. POWER MONITORING DENGAN DRY CONTACT..............................................3
1.1 Landasan informasi...................................................................3
1.2 Tabel alarm dan koneksi.............................................................3
1.3 Material list...........................................................................4
2. HARDWARE INSTALLATION.................................................................6
2.1 DB25 Converter ke SA................................................................6
2.2 Alarm PLN failure.....................................................................6
2.3 Alarm Rectifier Module/Arrester Rectifier..........................................7
2.4 Alarm DC low voltage alarm.........................................................7
2.5 Alarm Input SPD PLN Failure.........................................................7
2.6 Alarm Battery stolen.................................................................8
2.7 Alarm High temperature.............................................................8
2.8 Alarm Diesel Generator Set On......................................................8
2.9 Alarm Door Open.....................................................................8
3. SETTING ALARM CSU VIA LAPTOP.........................................................9
This material is proprietary to PT SMART TELECOM and is strictly confidential. No information contained herein
may be copied, translated, transcribed or duplicated for any commercial purposes or disclosed to third parties in
any form without the prior written consent of PT SMART TELECOM.
[POC Test] | 2 / 12
Panduan Dry contact untuk ZXDU68 W201 Smartfren LTE Project
1. Beberapa alarm akan menghubungkan koneksi dari SA cable (cable B3) ke dry contact di SIB pada ZXDU68 W201
2. Beberapa alarm akan menghubungkan konesi dari SA cable (cable B3) ke ke dry contact di ACPDB
3. Tabel dibawah untuk pembagian koneksi dan alarm dry contactnya pada ZXDU68 W201
4 Input SPD PLN Failure Dry contat di ACPDB / DB 25 Pin 4 -17 Koneksi ke terminal di ACPDB Dry contact number : 3
Genset ON (198092567)
Diesel Generator Set
7 ATS FGS / DB 25 Pin 7 -20 DB 25 Pin 7 -20 di loop Dry contact number : 6
On
Alarm Status : Alarm when open (1)
This material is proprietary to PT SMART TELECOM and is strictly confidential. No information contained herein
may be copied, translated, transcribed or duplicated for any commercial purposes or disclosed to third parties in
any form without the prior written consent of PT SMART TELECOM.
[POC Test] | 3 / 12
Panduan Dry contact untuk ZXDU68 W201 Smartfren LTE Project
1 0.3mm2 black single core heat resistant Flexible power cable 10 M Lilitan batere
2 Black dual core heat resistant Flexible power cable 30 M Untuk alarm koneksi dari SIB ke SA
SA cable
This material is proprietary to PT SMART TELECOM and is strictly confidential. No information contained herein
may be copied, translated, transcribed or duplicated for any commercial purposes or disclosed to third parties in
any form without the prior written consent of PT SMART TELECOM.
[POC Test] | 4 / 12
Panduan Dry contact untuk ZXDU68 W201 Smartfren LTE Project
This material is proprietary to PT SMART TELECOM and is strictly confidential. No information contained herein
may be copied, translated, transcribed or duplicated for any commercial purposes or disclosed to third parties in
any form without the prior written consent of PT SMART TELECOM.
[POC Test] | 5 / 12
Panduan Dry contact untuk ZXDU68 W201 Smartfren LTE Project
2. Hardware installation
2.1 DB25 Converter ke SA
Install DB25 converter ke SA cable, koneksi kabel SA nya di konektor dengan inisial B3.
Step :
a. Install kabel signal dari DB25 pin 1 ke terminal dry contact di ACPDB
b. Install kabel signal dari terminal dry contact untuk terminal lainnya di ACPDB ke SIB X14 pin 2
Option 2 : Jika ACPDB panel tidak tersedia terminal dry contact alarm untuk phase failure
Step :
This material is proprietary to PT SMART TELECOM and is strictly confidential. No information contained herein
may be copied, translated, transcribed or duplicated for any commercial purposes or disclosed to third parties in
any form without the prior written consent of PT SMART TELECOM.
[POC Test] | 6 / 12
Panduan Dry contact untuk ZXDU68 W201 Smartfren LTE Project
Step :
Step :
Jika ACPDB panel tersedia terminal dry contact alarm untuk arrester failure
Step :
b. Install kabel signal dari terminal dry contact untuk terminal lainnya di ACPDB ke DB25 pin 17
Jika tidak tersedia, cukup di loop koneksi di DB25 converter pin 4 ke pin 17
This material is proprietary to PT SMART TELECOM and is strictly confidential. No information contained herein
may be copied, translated, transcribed or duplicated for any commercial purposes or disclosed to third parties in
any form without the prior written consent of PT SMART TELECOM.
[POC Test] | 7 / 12
Panduan Dry contact untuk ZXDU68 W201 Smartfren LTE Project
Step
b. Install kabel signal dari DB25 pin 18 ke SIB X15 Pin 3 setelah
Step
b. install kabel signal dari DB25 pin 6 ke SIB SIB X15 Pin 5
Step :
This material is proprietary to PT SMART TELECOM and is strictly confidential. No information contained herein
may be copied, translated, transcribed or duplicated for any commercial purposes or disclosed to third parties in
any form without the prior written consent of PT SMART TELECOM.
[POC Test] | 8 / 12
Panduan Dry contact untuk ZXDU68 W201 Smartfren LTE Project
Dikarenakan default CSU sudah di set alokasi relaynya, untuk memudahkan perubahan harus menggunakan laptop yang di
hubungkan ke CSU
Step
1. Dari CSU pilih menu local set, akan tampil beberapa sub menu
2. Local menuNetworkWire NetworkLokal IPGanti ke StaticEnter kemudian “ESC” dan pilih “YES”
3. Konek kabel LAN dari laptop ke CSU di coba beberapa kemungkinan user dan password dibawah
4. Set IP laptop
This material is proprietary to PT SMART TELECOM and is strictly confidential. No information contained herein
may be copied, translated, transcribed or duplicated for any commercial purposes or disclosed to third parties in
any form without the prior written consent of PT SMART TELECOM.
[POC Test] | 9 / 12
Panduan Dry contact untuk ZXDU68 W201 Smartfren LTE Project
5. Via browser, masukin IP CSU, masukin user : Power dan Password : 0063
This material is proprietary to PT SMART TELECOM and is strictly confidential. No information contained herein
may be copied, translated, transcribed or duplicated for any commercial purposes or disclosed to third parties in
any form without the prior written consent of PT SMART TELECOM.
[POC Test] | 10 / 12
Panduan Dry contact untuk ZXDU68 W201 Smartfren LTE Project
7. Set Alarm level dibawah ini dan untuk alarm lainya harus di set di set NULL
SET SEMUA ALARM Selain dari tabel diatas untuk output relaynya : NULL
This material is proprietary to PT SMART TELECOM and is strictly confidential. No information contained herein
may be copied, translated, transcribed or duplicated for any commercial purposes or disclosed to third parties in
any form without the prior written consent of PT SMART TELECOM.
[POC Test] | 11 / 12
Panduan Dry contact untuk ZXDU68 W201 Smartfren LTE Project
This material is proprietary to PT SMART TELECOM and is strictly confidential. No information contained herein
may be copied, translated, transcribed or duplicated for any commercial purposes or disclosed to third parties in
any form without the prior written consent of PT SMART TELECOM.
[POC Test] | 12 / 12