SNI 2847:2019
No Reg: WBP-ANA-21226-00
Page 1 of 13
Structure Calculation
Tidak
dipersyaratkan.
Syarat Gaya Aksial Pu <= 0.1 Ag fc' ? OK
Baca R18.6.1 dan
18.6.4.7
WBP-ERD-2021 Page 3 of 13
Structure Calculation
WBP-ERD-2021
Mu kN-m Page
163.344
4 of 13
Cek ϕMn > Mu ϕMn > Mu ? OK
2
As Perlu Mu / [fy * (d - a/2)] mm 545.857
Structure Calculation
WBP-ERD-2021 Page 5 of 13
Structure Calculation
Tumpuan
Gaya Desain
Vg,tumpuan S21.5.4 R18.6.5 Input [Kombinasi 1.2 D + L] kN 68.048
As+ Tumpuan Dari Sheet Desain Lentur mm2 599.524
As- Tumpuan Dari Sheet Desain Lentur mm2 1417.644
+
apr 1.25 a (tumpuan positif) mm 44.083
apr- 1.25 a (tumpuan negatif) mm 104.239
Mpr+ S21.5.4 R18.6.5 As+ * (1.25 fy ) * (d - apr+/2) N mm 225190639
-
Mpr S21.5.4 R18.6.5 As- -
* (1.25 fy ) * (d - apr /2) N mm 510103486
Vsway atau Vpr 21.5.4.1 18.6.5.1 (Mpr+ + Mpr-) / Ln N 37515
Ve 21.5.4.1 18.6.5.1 Vg + Vpr N 105563
Tahanan Geser Beton
Vpr N 37515
1/2 Ve N 52782
Pu N 0
Ag fc' / 20 N 336000
Vc Diperhitungkan? 21.5.4.2 18.6.5.2 Vc = 0 jika Vpr >= 1/2 Ve dan Pu < Ag fc' / 20 Iya
Vc N 199027
Penulangan Geser
Jumlah Kaki Input 2
Av n *π/4 *ds2 mm 2
265.465
Spasi Input mm 100
Spasi Max 1 21.5.3.2 18.6.4.4 d/4 mm 184.38
Spasi Max 2 21.5.3.2 18.6.4.4 6 db mm 114.00
Spasi Max 3 21.5.3.2 18.6.4.4 150 mm mm 150.00
Cek Spasi OK
Vs 11.4.7.2 22.5.10.5.3 Av * fy * d / s N 822277
0.5
Batas Vs 11.4.7.9 22.5.1.2 0.66 * (fc') *b*d N 772692
ϕ 9.3.2.3 12.5.3.2, 21.2.4 0.75
Vn Vc + Vs N 971718
Vu N 105563
ϕVn / Vu 6.904
Cek Kapasitas ϕVn / Vu >= 1 ? OK
Lapangan
Penulangan Geser
Jumlah Kaki Input 2
Av n *π/4 *ds2 mm2 265.465
Spasi Input mm 200
Spasi Max 21.5.3.4 18.6.4.6 d/2 mm 368.75
Cek Spasi OK
Vs 11.4.7.2 22.5.10.5.3 Av * fy * d / s N 411138
Batas Vs 11.4.7.9 22.5.1.2 0.66 * (fc')0.5 * b * d N 772692
0.5
Vc 11.2.1.1 22.5.5.1 0.17 * (fc') *b*d N 199027
ϕ 9.3.2.3 12.5.3.2, 21.2.4 0.75
Vn Vc + Vs 610165
Vu N 66328.5
ϕVn / Vu 6.899
Cek Kapasitas ϕVn / Vu >= 1 ? OK
WBP-ERD-2021 Page 6 of 13
Structure Calculation
WBP-ERD-2021 Page 7 of 13
Structure Calculation
WBP-ERD-2021 Page 8 of 13
Structure Calculation
WBP-ERD-2021 Page 9 of 13
Structure Calculation
WBP-ERD-2021 Page 10 of 13
Structure Calculation
WBP-ERD-2021 Page 11 of 13
Structure Calculation
Cek Spasi
smax,1 18.7.5.3 b/4 mm 150
smax,2 18.7.5.3 6 * db mm 150
hx 18.7.5.3 xi max mm 300
smax,3 = so 18.7.5.3 100 <= 100 + (350 - hx) / 3 <= 150 mm 116.667
smax 18.7.5.3 Min (smax1 , smax2 , smax3 ) mm 116.667
Cek Spasi OK
Kuat Geser Zona Sendi Plastis
Gaya Geser Desain (Perlu input dari PCA Column, atau SP Column, atau CSI Column, dll. dengan fpr = 1.25 fy )
Mpr Kolom Input, (nilai terbesar) kN m 684.200
Vu 1 18.7.6.1 2 * Mpr Kolom / Ln N 106078
Gaya Geser Hasil Analisis Struktur
Vu 2 , Sumbu Lemah Dari Sheet Gaya Dalam N 40532
Vu 2 , Sumbu Kuat Dari Sheet Gaya Dalam N 27104
Tahanan Geser Beton Sumbu Lemah
Vu Max (Vu1 , Vu2 ) N 106078
φ Tabel 21.2.1 0.75
0.5
Vc 22.5.6.1 0.17 (1 + N u/(14 Ag)] (fc') h d; d = b - cc - ds - db / 2 N 311547
Vs Perlu 22.5.10.1 Vu / φ - Vc N -170110
2
As/s Perlu 22.5.10.5.3 Vs / (fy * d); d = b - cc - ds - db / 2 mm / mm -0.7438
0.5 2
As/s Min 1 10.6.2.2 0.062 (fc') h / fy mm / mm 0.4851
2
As/s Min 2 10.6.2.2 0.35 h / fy mm / mm 0.5000
Cek As/s Ash / s 1 >= Max (As/s Perlu, As/s Min) ? OK
Tahanan Geser Beton Sumbu Kuat
Vu Max (Vu1 , Vu2 ) N 106078
φ Tabel 21.2.1 0.75
0.5
Vc 22.5.6.1 0.17 (1 + N u/(14 Ag)] (fc') b d; d = h - cc - ds - db / 2 N 311547
Vs Perlu 22.5.10.1 Vu / φ - Vc N -170110
2
As/s Perlu 22.5.10.5.3 Vs / (fy * d); d = h - cc - ds - db / 2 mm / mm -0.7438
0.5 2
As/s Min 1 10.6.2.2 0.062 (fc') b / fy mm / mm 0.4851
2
As/s Min 2 10.6.2.2 0.35 b / fy mm / mm 0.5000
Cek As/s Ash / s 2 >= Max (As/s Perlu, As/s Min) ? OK
WBP-ERD-2021 Page 12 of 13
Structure Calculation
WBP-ERD-2021 Page 13 of 13
Structure Calculation
WBP-ERD-2021 Page 14 of 13