Time Schedule Final
Time Schedule Final
JADWAL PELAKSANAAN PEKERJAAN 270 ( DUA RATUS TUJUH PULUH ) HARI KALENDER TA. 2021
NOMOR BOBOT BULAN KE - I ( APRIL ) BULAN KE - II ( MEI ) BULAN KE - III ( JUNI ) BULAN KE - IV ( JULI ) BULAN KE - V ( AGUSTUS ) BULAN KE - VI ( SEPTEMBER ) BULAN KE - VII ( OKTOBER ) BULAN KE - VIII ( NOVEMBER ) BULAN KE - IX ( DESEMBER )
JUMLAH HARGA
MATA URAIAN PEKERJAAN TOTAL KET.
(Rp.) MG - 1 MG - 2 MG - 3 MG - 4 MG - 5 MG - 6 MG - 7 MG - 8 MG - 9 MG - 10 MG - 11 MG - 12 MG - 13 MG - 14 MG - 15 MG - 16 MG - 17 MG - 18 MG - 19 MG - 20 MG - 21 MG - 22 MG - 23 MG - 24 MG - 25 MG - 26 MG - 27 MG - 28 MG - 29 MG - 30 MG - 31 MG - 32 MG - 33 MG - 34 MG - 35 MG - 36
PEMBAYARAAN (%)
06/4 - 11/4 12/4 - 18/4 19/4 - 25/4 26/4 - 03/5 04/5 - 10/5 11/5 - 17/5 18/5 - 25/5 26/5 - 02/6 03/6 - 10/6 11/6 - 18/6 19/6 - 25/6 26/6 - 03/7 04/7 - 11/7 12/7 - 18/7 19/7 - 25/7 26/7 - 03/8 04/8 - 11/8 12/8 - 18/8 19/8 - 25/8 26/8 - 02/9 03/9 - 10/9 11/9 - 18/9 19/9 - 25/9 26/9 - 03/10 04/10 - 11/10 12/10 - 18/10 19/10 - 25/10 26/10 - 02/11 03/11 - 10/11 11/11 - 18/11 19/11 - 25/11 26/11 - 03/12 04/12 - 11/12 12/12 - 18/12 19/12 - 25/12 26/12 - 31/12
DIVISI 1. UMUM 100
1.2 Mobilisasi Rp 68,761,000.00 0.579 0.012 0.012 0.012 0.012 0.012 0.012 0.012 0.012 0.012 0.012 0.012 0.012 0.012 0.012 0.012 0.012 0.012 0.012 0.012 0.012 0.012 0.012 0.012 0.012 0.012 0.012 0.012 0.012 0.012 0.012 0.012 0.012 0.012 0.012 0.174
1.8.(1) Manajemen dan Keselamatan Lalu Lintas Rp 32,260,000.00 0.272 0.008 0.008 0.008 0.008 0.008 0.008 0.008 0.008 0.008 0.008 0.008 0.008 0.008 0.008 0.008 0.008 0.008 0.008 0.008 0.008 0.008 0.008 0.008 0.008 0.008 0.008 0.008 0.008 0.008 0.008 0.008 0.008 0.008 0.008 0.008
1.8.(2) Jembatan Sementara Rp 131,474,821.62 1.107 0.320 0.410 0.377
1.19 Keselamatan dan Kesehatan Kerja Rp 64,674,184.81 0.545 0.016 0.016 0.016 0.016 0.016 0.016 0.016 0.016 0.016 0.016 0.016 0.016 0.016 0.016 0.016 0.016 0.016 0.016 0.016 0.016 0.016 0.016 0.016 0.016 0.016 0.016 0.016 0.016 0.016 0.016 0.016 0.016 0.016 0.016 0.016
1.21 Manajemen Mutu Rp 33,407,000.00 0.281 0.008 0.008 0.008 0.008 0.008 0.008 0.008 0.008 0.008 0.008 0.008 0.008 0.008 0.008 0.008 0.008 0.008 0.008 0.008 0.008 0.008 0.008 0.008 0.008 0.008 0.008 0.008 0.008 0.008 0.008 0.008 0.008 0.008 0.008 0.008 90
DIVISI 2. DRAINASE
2.1.(1) Galian untuk Selokan Drainase dan Saluran Air Rp 20,551,093.28 0.173 0.173
2.2.(1) Pasangan Batu dengan Mortar Rp 128,744,587.49 1.084 0.784 0.300
DIVISI 3. PEKERJAAN TANAH DAN GEOSINTETIK
3.1.(1) Galian Biasa Rp 7,314,636.03 0.062 0.031 0.031 80
3.1.(4) Galian Struktur dengan kedalaman 0 - 2 meter Rp 25,317,925.45 0.213 0.053 0.053 0.053 0.053
3.2.(1a) Timbunan Biasa dari sumber galian Rp 55,395,586.61 0.467 0.467
3.2.(2a) Timbunan Pilihan dari sumber galian Rp 100,618,262.78 0.847 0.100 0.100 0.647
3.2.(4) Penimbunan Kembali Berbutir (Granular Backfill) Rp 28,203,236.80 0.238 0.119 0.119
3.3.(1) Penyiapan Badan Jalan Rp 2,403,733.50 0.020 0.020
70
DIVISI 5. PERKERASAN BERBUTIR DAN PERKERASAN BETON SEMEN
5.1.(1) Lapis Pondasi Agregat Kelas A Rp 80,420,589.59 0.677 0.677
5.1.(2) Lapis Pondasi Agregat Kelas B Rp 102,596,873.40 0.864 0.864
5.1.(3) Lapis Pondasi Agregat Kelas S Rp 36,554,376.06 0.308 0.154 0.154
7.1.(5a) Beton struktur, fc’30 Mpa Rp 760,767,270.03 6.407 0.481 0.481 0.481 0.481 1.333 1.800 0.867 0.485
7.1.(7a) Beton struktur, fc’20 MPa Rp 556,216,141.99 4.685 0.703 0.703 0.703 0.703 0.703 0.703 0.468
7.1.(10) Beton, fc’10 Mpa Rp 53,061,897.93 0.447 0.112 0.112 0.112 0.112
7.3.(1) Baja Tulangan Polos BjTP 280 Rp 20,290,742.73 0.171 0.171
7.3.(3) Baja Tulangan Sirip BjTS 420A Rp 1,836,157,083.09 15.465 0.900 0.646 0.773 0.619 0.619 0.619 0.773 0.773 0.773 0.619 0.619 0.619 2.300 2.500 1.200 1.114 40
7.4.(3) Penyediaan Struktur Jembatan Rangka Baja Standar 50 m Rp 5,533,132,235.84 46.602 0.900 0.900 1.400 2.900 3.900 4.100 4.700 5.400 5.800 6.200 4.000 2.700 1.700 1.300 0.702
7.4.(4) Pemasangan Jembatan Rangka Baja Standar Panjang 50 M Rp 491,129,022.08 4.136 0.800 0.900 2.200 0.236
7.6.(19a) Tiang Bor Beton, diameter 800 mm Rp 753,473,032.32 6.346 1.573 1.600 1.586 1.586
7.6.(19b) Tiang Bor Beton, diameter 500 mm Rp 358,511,155.92 3.019 0.755 0.755 0.755 0.755
7.6.(27a) Pengujian Crosshole sonic logging (CSL) pada Tiang bor beton diameter .... Rp 11,629,833.62 0.098 0.012 0.012 0.012 0.012 0.012 0.012 0.012 0.012
30
7.9.(1) Pasangan Batu Rp 29,719,700.30 0.250 0.250
7.11.(6) Sambungan Siar Muai Expansion Joint Tipe Finger Plate, lebar 20 Rp 58,466,513.42 0.492 0.492
7.12.(2) Landasan Elastomerik Karet Alam Berlapis Baja Ukuran 400 Mm x450 Mm x 100 Mm Rp 8,016,066.64 0.068 0.068
7.14.(1) Papan Nama Jembatan Rp 1,329,668.66 0.011 0.011
7.15.(8) Pembongkaran Jembatan Kayu Rp 4,989,186.00 0.042 0.042
7.16.(2a) Pipa Drainase Baja diameter 150 mm Rp 7,197,719.10 0.061 0.020 0.020 0.020 20
PROGRESS MINGGUAN
RENCANA
##
KOMULATIF PROGRESS MINGGUAN 0 0.043 0.087 0.130 0.493 0.946 1.367 1.618 3.246 4.902 6.010 8.744 11.601 15.994 22.635 29.119 35.349 43.035 51.121 58.853 63.996 67.358 70.490 73.459 75.807 78.051 80.650 83.337 85.934 87.777 89.885 91.746 93.301 95.447 97.968 100.000
PROGRESS MINGGUAN
REALISASI
KOMULATIF PROGRESS MINGGUAN
DEVIASI