BEBAN PONDASI , MOMENT , & GESER

JUMLAH KOLOM = 43 BUAH JUMLAH PANCANG = 141 TITIK


GAYA AKSIAL
UNTUK DAERAH S-03 UNTUK DAERAH S-02 UNTUK DAERAH S
P1 = P10 = 369 P7
P2 = P11 = 375 P8
P3 = P12 = 383 P9
258 t
P4 = P16 = 375 P13
P5 = P17 = 375 P14
P6 = P18 = 383 t P15
P22 = 375 P19
P23 = 375 P20
P24 = 383 P21
P28 = 272 P25
P29 = 272 P26
P27

MOMEN
UNTUK DAERAH S-03 UNTUK DAERAH S-02 UNTUK DAERAH S
M1 = M10 = 41.38 M7
M2 = M11 = -24.12 M8
M3 = M12 = -36.32 M9
-20.01 tm
M4 = M16 = -24.12 M13
M5 = M17 = -24.12 M14
M6 = M18 = -36.32 tm M15
M22 = -24.12 M19
M23 = -24.12 M20
M24 = -36.32 M21
M28 = 12.36 M25
M29 = 12.36 M26
M27

GESER
UNTUK DAERAH S-03 UNTUK DAERAH S-02 UNTUK DAERAH S
D1 = D10 = 11.88 D7
D2 = D11 = 13.32 D8
D3 = D12 = 13.53 D9
4.44 t
D4 = D16 = 13.32 D13
D5 = D17 = 13.32 D14
D6 = D18 = 13.53 t D15
D22 = 13.32 D19
D23 = 13.32 D20
D24 = 13.53 D21
D28 = 5.72 D25
D29 = 5.72 D26
D27
JUMLAH PILE CAP = 29 BUAH

UNTUK DAERAH S-01


= 383
= 412
= 412
= 383
= 412
= 594
t
= 383
= 412
= 412
= 204
= 272
= 272

UNTUK DAERAH S-01


= -36.32
= -29.45
= -29.45
= -36.32
= -29.45
= -42.41
tm
= -36.32
= -29.45
= -29.45
= 14.46
= 12.36
= 12.36

UNTUK DAERAH S-01


= 13.53
= 11.62
= 11.26
= 13.53
= 11.62
= 10.56
t
= 13.53
= 11.62
= 11.62
= 4.6
= 5.72
= 5.72
Perencanaan Pondasi Bored Pile P1,2,3,4,5,6

1 Menghitung daya dukung tanah dan daya dukung pondasi RUMUS


Data perencanaan: KONTROL
Panjang Tiang (L) = 13.4 m KETENTUAN
Diameter Tiang (d) = 0.6 m
Beban Pondasi (Pu) = 258 t = 2530.13 kN
Momen (Mu) = -20.01 tm = -196.23 kN-m
A tiang = 2827.43 cm2
O tiang = 188.5 cm
qc = 40 kg/cm2
Tf = 1272 kg/cm
As = 25.26 cm2

daya dukung ujung tiang


𝑞_(𝑒 =) 𝑞_𝑐
×𝐾_𝑐×𝐴_𝑡𝑖𝑎𝑛𝑔
qe = qc x Kc x A tiang
= 40 x 0.375 x 2827.43
= 42411.5 kg

daya dukung lekatan

𝑞_(𝑠 =) 〖 𝐽𝐻〗 _𝑝
×𝐴_𝑠
qs = JHp x As
= 1272 x 25.3
= 32128.6910771444

daya dukung batas dan daya dukung ijin


𝑞_(𝑢𝑙𝑡 =)
qult
〖 𝑞〗=
_𝑒+𝑞_𝑠
qe + qs
= 74540.1919006066 kg
= 730.993 kN

𝑞_( 𝑖𝑗𝑖𝑛 = )
𝑞_𝑢𝑙𝑡 / 〖 𝑆〗 _𝑓
q ijin = qult / Sf Sf = 3
= 730.993 / 3
= 243.664433303893 kN

Atiang  qc O Tf
Qtiang  
3 5
2827.43 x 40 188.495559215 x 1272
Q tiang = +
3 5
= 85652.382 Kg
= 839.967 kN

2 Menentukan jumlah pondasi

Pu
n 
Q tiang
n > 2530.13 / 839.97
n > 3.01217541943288
Diambil nilai n = 4 buah
3 Menghitung kemampuan kelompok tiang
Metode Converse Labarre

Eg = Efisiensi kelompok tiang


m = Jumlah baris tiang = 1
n = Jumlah pondasi = 4
θ = Arc tg D/s = 26.565051177078
D = Diameter tiang
st = Jarak antar tiang
= 2 x D = 1.2 m

4 - 1 x 1 + 1 - 1 x 4
Eg = 1 - 26.57
90 x 4 x 1
= 1 - 0.221
= 0.779

Metode Los Angeles Group

ELA = Efisiensi kelompok tiang


m = Jumlah baris tiang
n = Jumlah kolom tiang
D = Diameter tiang
st = Jarak antar tiang

- 0.6 m 1 4 - 1 + 1 - 1 + 2 1 - 1 4 - 1
ELA = 1
15.07964
= 0.881

diambil nilai efisien yang terkecil yaitu = 0.779

Qt = 0.779 x 4.000 x 839.967


= 2616.08 kN > 2530.13 kN OK

4 Penurunan pondasi kelompok tiang


Penurunan tiang tunggal

s  s1  s 2  s3
Q
wp    Qws   L
s1 
Ap  E p
 L
C s   0 .93  0 .16  Cp
Q wp  C p  D 
s2 
D  qp

Qws  C s
s3 
L  qp
Tabel Nilai tipikal Cp (dari Design pf Pile Foundation by A.S. Vesic, 1977)
Jenis Tanah Tiang Pancang Tiang Bor
Pasir (padat ke lepas) 0.02 - 0.04 0.09 - 0.18
Lempung (kaku ke lunak) 0.02 - 0.03 0.03 - 0.06
Lanau (padat ke lepas) 0.03 - 0.05 0.09 - 0.12

Qwp = Beban yang dipikul ujung tiang = 369.704 kN


Qws = Beban yang dipikul kulit tiang = 470.263335502 kN
Ap = Luas penampang tiang = 0.2827 m2
Ep = Modulus young bahan tiang = 25332084.399 kN/m2
Cp = Koefisien empiris, Vesic = 0.09
qp = Tahanan ujung batas tiang = 1307.56 kN/m2
D = Diameter tiang = 0.6 m
L = Panjang tiang = 13.4 m
Cs = Konstanta Vesic = 0.15175174502
ξ = Kontanta nilai distribusi tekanan friksi = 0.5

369.704 + 0.5 x 470.263335502 x 13.4


s1 =
0.2827 x 25332084.3990383
= 0.1132 cm

369.704 x 0.09
s2 =
0.6 x 1307.56
= 4.2412 cm

470.263335501839 x 0.151751745018
s3 =
13.4 x 1307.56
= 0.4073 cm

s = 0.1132 + 4.241 + 0.407294


= 4.7616 cm

Penurunan kelompok tiang

Bg
sg 
Ds
Bg = Lebar tiang kelompok = 1.5 m
D = diameter tiang tunggal = 0.6 m
s = Penurunan tiang tunggal = 4.762 cm

1.5
sg =
0.6 x 4.762
= 0.7246 cm

5 Penulangan Pilar Pondasi

Direncanakan menggunakan:
db = 13 mm
fy = 390 MPa
fc' = 29.05 MPa
b = 600 mm
d = 506.5 mm

Karena fc' ≥ 28 MPa, maka β1 = 0,05.(fc'-28)


0.85 -
510   1  fc ' 7
 
b
600  fy  fy = 0.84 > 0.65 OK

510 x 0.8425 x 29.05


ρb = = 0.0323
600 + 390 x 390

 maks  0.75   b
ρmaks = 0.75 x 0.0323
= 0.0242
Karena fc' ≤ 31.36 MPa, maka:
1 .4
 min 
fy
1.4
ρmin = = 0.004
390
M u
K 
b  d 2

-196.2321 x 1000000 = -1.594 MPa


K =
0.8 x 600 x 256542

382.5   1  fc'600  fy  225   1 


Kmaks 
600  fy
2

Kmaks 382.5 x 0.84 x 29.05 x 600 + 390 - 225 x 0.84


=
600 + 390 2
Kmaks = 7.645 MPa

K < Kmaks OK

 2 K 
a  1  1  d
 0.85  fc' 

2 x -1.594
a = 1 - 1 - x 507
0.85 x 29.05
= -31.6959 mm

0.85  fc'a  b
As 
fy

As = 0.85 x 29.05 x -31.70 x 600


390
= -1204.080 mm2

As min   min  b  d
As min = 0.0036 x 600 x 506.50
= 1090.923 mm2

Jumlah Tulangan

1090.9231
n = = 8.22 = 9 9 D 13
0.25 x 3.1415927 x 169

6 Penulangan Begel Pilar Pondasi


Nu,k = 2530.129 kN

 0,29Nu ,k 
Vc  0,171    fc '  b  d
 Ag 

0.29 x 2530 x 1000
Vc = 0.17 1 + x 1 x 5.389805 x 600 x 506.5
282743
= 1001058.404 N

Vu = 43541.7480 N

Vu < φ.Vc/2 φ = 0.75


43541.7480 < 375396.901602825 OK

φ.Vc/2 < Vu < φ.Vc


375396.9016 < 43541.7480 < 750793.803205651 TIDAK OK

Vu > φ.Vc
43541.7480 > 750793.803 TIDAK OK

Karena Vu < φ.Vc/2, maka perlu tulangan geser


Pakai tulangan geser φ D = 12 mm

Kontrol spasi begel


s ≤ d/2 = 507 / 2 = 253.3 mm

Jadi digunakan tulangan geser φ D= 12 - 200 mm


Perencanaan Pile Cap P1,2,3,4,5,6

Berat jenis beton bertulang = 2400 kg/m3 = 0.0024 kg/cm3


Reaksi terbesar = 258.0 ton + 10752 kg
Momen terbesar = -20.01 tm = -20010 kgm

ϕ Nc Nq Nγ Nc' Nq' Nγ'


0.0 5.7 1.0 0.0 5.7 1.0 0.0
5.0 7.3 1.6 0.5 6.7 1.4 0.2
10.0 9.6 2.7 1.2 8.0 1.9 0.5
15.0 12.9 4.4 2.5 9.7 2.7 0.9
20.0 17.7 7.4 5.0 11.8 3.9 1.7
25.0 25.1 12.7 9.7 14.8 5.6 3.2
30.0 37.2 22.5 19.7 19.0 8.3 5.7
34.0 52.6 36.5 35.0 23.7 11.7 9.0
35.0 57.8 41.4 42.4 25.2 12.6 10.1
40.0 95.7 81.3 100.4 34.9 20.5 18.8
45.0 172.3 173.3 297.5 51.2 35.1 37.7
48.0 258.3 287.9 780.1 66.8 50.5 60.4
50.0 347.6 415.1 1153.2 81.3 65.6 87.1

Jenis tanah kohesi (kg/cm2) Jenis tanah kohesi (kg/cm2)


Kerikil Bergradasi Baik 0.000 Pasir Berlempung 0.155 ~ 0.766
Kerikil Bergradasi Jelek 0.000 Lumpur 0.063 ~ 0.673
Kerikil Berpasir 0.000 Lumpur Berlempung 0.167 ~ 0.647
Kerikil Berlempung 0.000 Lempung 0.105 ~ 0.386
Pasir Bergragasi Baik 0.401 ~ 1.042 Lempung Organik 0.000
Pasir Bergragasi Jelek 0.063 ~ 0.232 Lumpur Elastis 0.301 ~ 0.738
Pasir Berlumpur 0.063 ~ 0.520 Lempung Jenuh 0.345 ~ 1.048
Pasir Berlempung, Lumpur 0.218 ~ 0.513 Tanah Organik 0.000

Kolom Panjang (cm) Lebar (cm)


K3 60 60

fy = 390 MPa
fc' = 29.1 MPa
Sudut geser tanah (ϕ) = 30
sehingga :
Nc = 37.2
Nq = 22.5
Nγ = 19.7
kohesi tanah {C} = 0.461
berat jenis tanah {γ') = 2.62 t/m3
= 0.0026 kg/cm3
Kedalaman pondasi = 13.4 cm
ρo = Df x ϒ
ρo = 0.035 kg/cm2
Rencana luasan pondasi =
h = 160 cm = 1600 mm = 1.6 m
b = 280 cm = 2800 mm = 2.8 m
t = 50 cm = 500 mm = 0.5 m
d = 39.950 cm = 399.50 mm = 0.4 m
Tulangan pokok = 19 mm
Tulangan bagi = 16 mm
1) Menentukan ukuran pile cap
σult = C.Nc.(1+0,3.B/L)+ ρo.Nq + 0,5 γ'.B.Nγ.(1-0,2.B/L)
σult = 29.5980 kg/cm2
σ = 9.8660 kg/cm2
Cek tegangan tanah yang terjadi
Pu,k Mu,x +
σmaks = + q ≤ σ
B.L 1/6.B.L2 -
268752.00 -2001000
σmaks = + + 0.120
44800.0 1194667
= 4.4440 ≤ 9.8660 kg/cm2 ok

268752 -2001000
σmin = - + 0.120
44800 1194667
= 7.7939 ≤ 9.8660 kg/cm2 ok

2) kontrol tegangan geser 1 arah


Gaya geser oleh tekanan tanah ke atas (Vu):

Vu = a.B.(σmaks+σa)/2
ag = 10.050 cm
Vu = 12801.426 kg = 125539.742 N
σa = 7.794 + 160 - 10.050 x 4.44 - 7.794 / 160
= 4.6544 kg/cm2

Gaya geser yang dapat ditahan oleh beton {Ф.Vc}.


ᶲ.Vc =
ᶲ fc '
b d
6
= 5.4
0.75 2800 400
6
= 753629.51 N = 76848.431 kg
jadi Vu < Ф.Vc oke

Kontrol tegangan geser 2 arah


Gaya geser yang bekerja pada penampang kritis
Vu = {B.L-(b+d).(h+d)}.(σmaks+σmin)/2
Vu = 212999.888 kg = 2088826 N

Gaya geser yang dapat ditahan oleh beton {Ф.Vc}.


ᶲ.Vc = 1/3. fc.bo' .d
= 7463085.385 N = 746308.54 kg
βc = 1 cm
B' = 100 cm
b0 = 10398 mm

ᶲ.Vc = ᶲ {1 +
2
βc } 6
fc ' .b0.d
oke
= 0.75 { 1 +
2
1 } 22389256
6
= 0.75 x 11194628.1 N
= 8395971.06 = 856146.42 kg
αs = 20 (untuk pile cap kolom sudut)

ᶲ.Vc = ᶲ { 2 +
αs.d
bo } fc ' .bo.d
12
= 0.75 { 2 +
7990
10398 } 22389256
12
= 0.75 x 5165233.1 N
= 3873924.8 = 395028.38 kg

2) Hitung penulangan pondasi


x = L/2 - bk/2
= 50.0
Mu =
= 5554.980 kg cm = 544760.270 N mm
K = Mu / (ᶲ . b . d2)
= 0.00427 MPa < 7.645 K maks oke
a = { 1 -
√ 1 -
2
0.85
.
.
K
fc' } . d

= { 1 -
√ 1 -
2
0.85
.
.
0.0043
29.1 } . 399.50

= 0.0690352844533 mm
Tulangan pokok = 19
As,u = (0.85 . fc' . a . b) / fy
= 4.3709070804 mm2
fc' < 31.36 MPa = As,u = 1.4 . b . d / fy
= 1434.10 mm2
Dipilih yang besar, yaitu As,u = 1434.1 mm2
Jarak tulangan, s
= 1/4 . π . D2 . S / As,u
= 197.70464406352 mm
s ≤ (2 . hf) = 1200 mm
s ≤ 450 mm
Dipilih yang terkecil = 197.70 mm = 195 mm
Luas tulangan = 1/4 . π . D2 . S
s
= 1453.99 mm2 > As,u oke

Tulangan bagi = 16
x = B/2 - bk/2
= 110.0
Mu =
= 26886.105 kg cm = 2636639.71 N mm
K = Mu / (ᶲ . b . d2)
= 0.02065 MPa < 7.6455 K maks oke
a = { 1 -
√ 1 -
2
0.85
.
.
K
fc' } . d

= { 1 -
√ 1 -
2
0.85
.
.
0.0207
29 } . 400

= 0.33424172884428 mm

As,u = (0.85 . fc' . a . b) / fy


= 21.162215101 mm2
fc' < 31.36 MPa = As,u = 1.4 . b . d / fy
= 1434.1 mm2
Dipilih yang besar, yaitu As,u = 1434.103 mm2
Jarak tulangan, s = 1/4 . π . D2 . S / As,u
= 140.20052321402 mm
s ≤ (2 . hf) = 1200 mm
s ≤ 450 mm
Dipilih yang terkecil = 140.2 mm = 140 mm

Luas tulangan = 1/4 . π. D2 . S


s
= 1436.157 mm2 > As,u oke

Jadi digunakan tulangan pokok = 19 - 195 mm2


Jadi digunakan tulangan bagi = 16 - 140 mm2

Panjang penyaluran tegangan tulangan (λd):


Rumus :
9 . fy
λd = . db dan λd harus > 300 mm
10 .
√ fc' ( c +dK )b
tr

9 . 390 . 1 . 1 . 0.8 . 1 . 19
λd =
10 . 5 . 2.1026

= 470.776 mm > 300 oke

= 480 mm
1.0 < 1.7 oke
KONTROL 2.1 < 2.5 oke
λd = 300 mm = 0.30 m
5.4 < 8.3 oke

3) Kuat dukung pondasi

Pu = ᶲ . 0.85 . fc' . A1
= 77435.680 > 2530.1286 kN oke