TUGAS AKHIR
ERNA SAIYAH
NIM : 140309241192
TUGAS AKHIR
ERNA SAIYAH
NIM : 140309241192
ii
LEMBAR PENGESAHAN
Disusun oleh :
ERNA SAIYAH
NIM : 140309241192
Pembimbing I Pembimbing II
Penguji I Penguji II
Mengetahui,
Ketua Jurusan Teknik Sipil
iii
SURAT PERNYATAAN PERSETUJUAN
PUBLIKASI KARYA ILMIAH
KEPENTINGAN AKADEMIS
Dibuat di : Balikpapan
Pada tanggal :12 July 2017
Yang Menyatakan
Erna Saiyah
iv
SURAT PERNYATAAN
Materai 6000
ERNA SAIYAH
NIM : 140309241192
v
LEMBAR PERSEMBAHAN
vi
ABSTRACT
Project to build something like a house of course need to some planing like
a coast estimate to avoid overbudget. This planing related with scheduling, and
scheduling can help to monitoring progress to avoid this project doesn’t finish to
be on time.
Curve S method is a one of method use to planning coast of estimate. Some
point use to count a coast for project there are: materials, price to pay workers,
tools, overhead and profit.
The result of using the working unit cost analysis of DPU Kota
Balikpapan in 2016 (Permen PU No. 28 / PRT / M / 2016) and the list of wage and
material prices in 2017 Balikpapan City, the construction of 3 storey building with
246.5 m² area cost Rp Rp. 1,640,054,194,59 - .. The execution time in the S curve
for 8 months 2 weeks or 238 days, with a duration of 1 week equals 7 working days
Key words: Cost Of estimate, Curve S Methode, Scheduling
vii
ABSTRAK
Kegiatan pembangunan proyek tentunya membutuhkan adanya
perencanaan yang matang sehingga mempermudah proses jalanya pekerjaaan
pembangunan proyek. Perencanaan tersebut meliputi kegiatan perhitungan biaya
untuk menghindari adanya pembengkakan biaya juga penjadwalan agar proyek
berjalan sesuai jadwal yang telah ditentukan.
Metode kurva S merupakan metode yang umum digunakan untuk
menghitung rencana anggaran biaya. Adapun hal-hal pokok yang diperlukan untuk
menghitung estimasi biaya yaitu: Bahan-bahan, harga upah, peralatan, biaya tak
terduga dan keuntungan.
Hasil dari menggunakan analisa harga satuan pekerjaan dari DPU Kota
Balikpapan Tahun 2016 (Permen PU No. 28/PRT/M/2016) dan daftar harga upah
dan bahan tahun 2017 Kota Balikpapan, pembangunan gedung ruko 3 lantai dengan
luas 246.5 m² tersebut memerlukan biaya sebesar Rp. 1,640,054,194.59-..Waktu
pelaksanaannya dalam kurva S selama 8 bulan 2 minggu atau 238 hari, dengan
durasi 1 minggu sama dengan 7 hari kerja.
viii
KATA PENGANTAR
Dengan memanjatkan puji syukur kehadirat Tuhan Yang Maha Kuasa, karena
atas rahmat serta hidayah-Nya penulis dapat menyelesaikan proposal tugas akhir
dengan judul “Rencana Anggaran Biaya dan Penjadwalan Pembangunan Rumah
Tinggal 3 Lantai di Balikpapan”.
Penulis menyampaikan ucapan terima kasih yang sebesar-besarnya kepada:
1. Ramli,S.E.,M.M. sebagai Direktur Politeknik Negeri Balikpapan
2. Drs. Sunarno, M.Eng., sebagai Ketua Jurusan Teknik Sipil Politeknik Negeri
Balikpapan.
3. Mahfud,S.pd., M.T, selaku pembimbing I dan Melviana Firsty, S.T., M.T
selaku pembimbing II yang telah memberikan pengarahan selama pengerjaan
tugas akhir ini.
4. Seluruh staf dan karyawan jurusan Teknik Sipil Politeknik Negeri Balikpapan
yang telah membantu.
5. Ayahanda Suyanto dan ibunda Suwati terima kasih selalu memberi semangat
dan doa. Serta kakak tercinta Pratu Lestiawan Purwanto dan Dewi Ieawati
S.E dan adikku tercinta Novia Hidayah terima kasih telah banyak membantu.
6. Seluruh teman-teman angkatan 2014 khusunya 3TS2 Teknik Sipil yang telah
banyak membantu selama penyusunan tugas akhir ini hingga selesai.
7. Semua pihak yang tidak dapat menyebutkan satu persatu, yang telah
memberikan bantuan pada tugas akhir ini.
Penulis menyadari bahwa tugas akhir ini bukanlah karya yang sempurna, dan
masih banyak ditemui kekurangan dan kelemahan. Oleh karena itu, saran dan
masukan yang membangunan sangat diharapkan.
Erna Saiyah
DAFTAR ISI
Halaman
ix
JUDUL .................................................................................................................... ii
LEMBAR PENGESAHAN ................................................................................... iii
SURAT PERNYATAAN....................................................................................... iv
LEMBAR PERSEMBAHAN ................................................................................ vi
ABSTRAK ............................................................................................................ vii
KATA PENGANTAR ........................................................................................... ix
DAFTAR ISI ............................................................................................................x
DAFTAR GAMBAR ............................................................................................ xii
DAFTAR TABEL ................................................................................................ xiv
LAMPIRAN ...........................................................................................................xv
BAB 1. PENDAHULUAN .....................................................................................1
1.1 Latar Belakang ...................................................................................................1
1.2 Rumusan Masalah ..............................................................................................2
1.3 Batasan Masalah.................................................................................................2
1.4 Tujuan Penelitian ...............................................................................................2
1.5 Manfaat penelitian ..............................................................................................2
BAB 11 LANDASAN TEORI ...............................................................................4
2.1 Rencana Anggaran Biaya ..................................................................................4
2.1.1 Macam-Macam Rencana Anggaran Biaya......................................................6
2.1.2 Harga Satuan Pekerjaan..................................................................................7
2.1.3 Dasar Pertimbangan Dalam Estimasi Biaya ..................................................7
2.1.4 Macam-Macam Daftar Analisa Perhitungan Biaya ........................................8
2.1.5 Hal-Hal Pokok Dalam Menghitung Estimasi Biaya .......................................9
2.1.6 Kualifikasi Dan Tugas Seorang Estimator ....................................................10
2.1.7 Kondisi Yang Mempengaruhi Estimasi Biaya ..............................................10
2.1.8 Resiko Dalam Estimasi .................................................................................12
2.2 Volume Pekerjaan ............................................................................................12
2.3 Penjadwalan .....................................................................................................13
2.3.1 Dasar Pembuatan Penjadwalan .....................................................................13
2.3.2 Manfaat Pembuatan Penjadwalan ................................................................14
2.3.3 Faktor Yang Mempengaruhi Penjadwalan ....................................................15
2.3.4 Metode Penjadwalan Proyek .........................................................................15
x
2.3.4.1 Kurva S atau Hannum Curve .....................................................................16
BAB III METODOLOGI ....................................................................................18
3.1 Data Umum ......................................................................................................18
3.2 Data Penunjang ................................................................................................18
3.3 Tahap Dan Prosedur Perhitungan.....................................................................19
3.3.1 Flow Chart Rencana Anggaran Biaya ..........................................................20
3.3.2 Flow Chart Penjadwalan ...............................................................................21
3.4 Perhitungan Volume Masing-Masing Pekerjaan .............................................22
BAB IV PEMBAHASAN.....................................................................................27
4.1 Perhitungan Volume Pekerjaan ........................................................................27
4.2 Uraian Perhitungan Volume Pekerjaan ............................................................27
4.2.1 Perhitungan Volume Pekerjaan Pendahuluan ..............................................29
4.2.2 Perhitungan Volume Pekerjaan Tanah dan Pondasi .....................................30
4.2.3 Perhitungan Volume Pekerjaan Beton ..........................................................31
4.2.4 Perhitungan Volume Pekerjaan Pembesian ..................................................36
4.2.5 Perhitungan Volume Pekerjaan Bekisting ....................................................40
4.2.6 Perhitungan Volume Pekerjaan Dinding .......................................................45
4.2.7 Perhitungan Volume Pekerjaan Lantai..........................................................49
4.2.8 Perhitungan Volume Pekerjaan Plafon .........................................................51
4.2.9 Perhitungan Volume Pekerjaan Kusen, Daun Pintu dan Jendela ..................51
4.2.10 Perhitungan Volume Pekerjaan Instalasi Listrik .........................................54
4.2.11 Perhitungan Volume Pekerjaan Sanitasi Air ...............................................55
4.2.12 Perhitungan Volume Pekerjaan Pengecatan................................................56
4.2.13 Perhitungan Volume Pekerjaan Pengunci dan Penggantung ......................56
4.3 Analisa Harga Satuan Pekerjaan (AHSP) 2016 ...............................................57
4.4 Rencana Anggaran Biaya .................................................................................57
4.4.1 Rencana Anggaran Biaya Pendahuluan ........................................................57
4.4.2 Rencana Anggaran Biaya Pekerjaan Tanah dan Pondasi ..............................58
4.4.3 Rencana Anggaran Biaya Pekerjaan Beton...................................................58
4.4.4 Rencana Anggaran Biaya Pekerjaan Pembesian ...........................................58
4.4.5 Rencana Anggaran Biaya Pekerjaan Bekisting .............................................59
4.4.6 Rencana Anggaran Biaya Pekerjaan Dinding ...............................................60
xi
4.4.7 Rencana Anggaran Biaya Pekerjaan Lantai ..................................................60
4.4.8 Rencana Anggaran Biaya Pekerjaan Plafon ..................................................61
4.4.9 Rencana Anggaran Biaya Pekerjaan Kusen, Daun Pintu, dan Jendela .........61
4.4.10 Rencana Anggaran Biaya Pekerjaan Instalasi Listrik .................................62
4.4.11 Rencana Anggaran Biaya Pekerjaan Sanitair dan Instalasi Air ..................62
4.4.12 Rencana Anggaran Biaya Pekerjaan Pengecatan ........................................63
4.4.13 Rencana Anggaran Biaya Pekerjaan Pengunci dan Penggantung ..............63
4.5 Rekapitulasi Rencana Anggaran Biaya ...........................................................63
4.6 Penjadwalan .....................................................................................................65
BAB V PENUTUP ................................................................................................66
5.1 Kesimpulan ......................................................................................................66
5.2 Saran .................................................................................................................66
DAFTAR PUSTAKA ............................................................................................67
LAMPIRAN ...........................................................................................................68
xii
DAFTAR GAMBAR
Halaman
Gambar 2.1 Susuna Rencana Anggaran Biaya 6
Gambar 3.2 Flow Chart Rencana Anggaran Biaya 20
Gambar 3.3 Flow Chart Penjadwalan 21
Gambar 4.1 Pemasangan Bouwplank 29
Gambar 4.2 Rencana Pondasi 30
Gambar 4.3 Rencana Pondasi Batu Gunung 30
Gambar 4.4 Pondasi Foot Plat 33
Gambar 4.5 Cor Sloof 30/40 33
Gambar 4.6 Balok 30/40 lantai 2 34
Gambar 4.7 Ringbalk 30/40 atap dak 34
Gambar 4.8 Plat Lantai 2 33
Gambar 4.9 Plat Lantai 3 34
Gambar 4.10 Plat Atap Dak 34
Gambar 4.11 Tangga Beton Lt.1-2 dan Lt.2-3 35
Gambar 4.12 Pembesian Pondasi Foot Plat 36
Gambar 4.13 Pembesian Sloof 30/40 36
Gambar 4.14 Bekisting Sloof 30/40 41
Gambar 4.15 Bekisting Balok 30/40 lantai 2 41
Gambar 4.16 Bekisting Balok 30/40 Atap Dak 42
Gambar 4.17 Bekisting Tangga 44
Gambar 4.18 Keramik lt.1 49
Gambar 4.19 Keramik lt.2 50
Gambar 4.20 Kusen Pintu Kayu Bangkirai (P1) 52
Gambar 4.21 Kusen Pintu Kayu Bangkirai (P2) 52
Gambar 4.22 Kusen Jendela Bangkirai (J1) 52
Gambar 4.23 Rangka Ventilasi Kayu Bangkirai (V1) 53
Gambar 4.24 Daun Pintu Kayu Bangkirai (P1) 53
Gambar 4.25 Kaca Jendela Mati Bening (J1) 53
Gambar 4.26 Pintu Rolling Door 54
xiii
Gambar 4.27 Keterangan Instalasi Listrik 54
Gambar 4.28 Keterangan Instalasi Air 55
xiv
DAFTAR TABEL
Halaman
Tabel 3.2 Contoh Perhitungan Volume 22
Tael 4.1 Perhitungan Bekisting Plat Lantai 2 43
Tabel 4.2 Perhitungan Bekisting Plat Lantai 3 43
Tabel 4.3 Perhitungan Bekisting Plat Atap Dak 44
Tabel 4.4 Luas Dinding Lantai 1 45
Tabel 4.5 Luas Dinding Lantai 2 46
Tabel 4.6 Luas Dinding Lantai 2 Kamar Mandi 46
Tabel 4.7 Luas Dinding Lantai 3 47
Tabel 4.8 Luas Dinding Lantai 3 Kamar Mandi 48
Tabel 4.9 Rencana Anggaran Biaya Pendahuluan 57
Tabel 4.10 Rencana Anggaran Biaya Tanah dan Pondasi 58
Tabel 4.11 Rencana Anggaran Biaya Beton 58
Tabel 4.12 Rencana Anggaran Biaya Pembesian 59
Tabel 4.13 Rencana Anggaran Biaya Bekisting 60
Tabel 4.14 Rencana Anggaran Biaya Dinding 60
Tabel 4.15 Rencana Anggaran Biaya Lantai 61
Tabel 4.16 Rencana Anggaran Biaya Plafon 61
Tabel 4.17 Rencana Anggaran Biaya Kusen, Daun Pintu, Jendela 61
Tabel 4.18 Rencana Anggaran Biaya Instalasi Listrik 62
Tabel 4.19 Rencana Anggaran Biaya Sanitasi Air 62
Tabel 4.20 Rencana Anggaran Biaya Pengecatan 63
Tabel 4.21 Rencana Anggaran Biaya pek. Kunci dan Penggantung 63
Tabel 4.22 Rekapitulasi Rencana Anggaran Biaya 64
xv
DAFTAR LAMPIRAN
Halaman
Lampiran 1: Gambar Bestek Bangunan Ruko 69
Lampiran 2: Hasil Rekapitulasi Rencana Anggaran Biaya Ruko 3 Lantai 82
Lampiran 3: Daftar Harga dan Upah 85
Lampiran 4: Analisa Harga Satuan Pekerjaan 114
xvi
BAB I
PENDAHULUAN
1
2
4
5
2. Penasehat (adviser)
Sebagaimana hal diatas, ahli-ahli bangunan yang menerima pekerjaan
tersebut umumnya adalah seorang tenaga teknik (Sarjana teknik, Arsitek, Sipil)
jadi, yang menerima pekerjaan disebut penasehat atau perencana. Dalam
melakukan pekerjaanya, tenaga ahli atau penasehat akan menyalurkan keinginan
principal untuk diterapkan dalam bidang ilmu ketekniksipilan sesuai dengan
manfaat dan penggunaan bangunan yang dimaksud.
3. Direksi (pengawas)
Saat melaksanakan pekerjaan pemborong perlu mengawasi pekerjaannya,
biasanya ini dilakukan oleh seorang yang disebut direksi atau pengawas yang
mempunyai staf tenaga ahli dibidangnya masing-masing. Apabila bangunan
tersebut dimiliki oleh instansi pemerintah maka, pengawannya adalah berasa dari
Dinas Pekerjaan Umum (DPU) yang biasanya disebut “pemimpin proyek” atau
supervisior yang ditunjukan oleh dinas (perusahaan konsultan pengawas).
4. Pemborong
Pada waktu pelaksanaan pembangunan yang melaksanakan proyek
pembangunan tersebut adalah pemborong dimana keuntungan diambil dari
pekerjaannya.
5. Pelaksana
Pelaksana adalah teknisi yang bertanggung jawab pekerjaan dan
terlaksananya pekerjaan seorang elaksana ditunjuk oleh pemborong dari setiap saat
berada ditempat pekerjaan, karena dalam beberapa hal pemborong sering
berhalangan hadir. Penunjukan seorang pelaksana harus diberitahukan kepada
pihak direksi, dan mendapat persetujuan karena pihak direksi dapat menolak
pelaksana ditunjuk pemborong apabila dianggap tidak memenuhi syarat. Adapun
Susunan dari Rencana Anggaran Biaya yaitu:
6
Bestek dan
Gambar Bestek
Harga Satuan
Upah dan Bahan
Perhitungan Volume
Tiap Jenis Pekerjaan Perhitungan Satuan Tiap
Jenis Pekerjaan
Berdasarkan standar DPU
Perhitungan RAB
Secara Keseluruhan
a. Bestek, Gunanya untuk menentukan spesifikasi bahan dan syarat- syarat teknis.
b. Gambar bestek, Gunanya untuk menetukan atau menghitung besarnya masing-
masing volume pekerjaan.
c. Harga Satuan pekerjaan, Didapat dari harga satuan bahan dan harga satuan upah
berdasarkan perhitungan analisa BOW maupun SNI.
Estimasi-estimasi biaya ini dibuat secara terus -menerus untuk mengontrol agar
biaya proyek tidak lebih besar dari anggaran proyek menurut hasil estimasi biaya
pendahuluan.
Untuk membuat estimasi pendahuluan ini dibutuhkan data-data sebagai berikut. :
a. Produk yang dihasilkan oleh proyek, berikut kapasitas produksi dan lokasinya.
b. Gambaran mengenai fasilitas-fasilitas yang terdapat pada proyek.
c. Denah / tata Ietak proyek.
d. Waktu dibuatnya estimasi biaya proyek.
e. Daftar peralatan utama yang akan dibeli.
f. Persetujuan pemilik proyek terhadap gambaran rencana proyek secara umum.
Sebelum menghitung estimasi biaya ada beberapa hal pokok yang penting
dan harus sangat diperhatikan, antara lain:
1. Bahan-bahan
Membuat daftar jenis dan harga bahan yang akan digunakan dalam suatu
pekerjaan. Dimana harga bahan yang dibuat merupakan harga bahan yang akan
digunakan pada lokasi pekerjaan.
2. Harga Upah
Panjangnya jam kerja untuk para pekerja dan jenis pekerjaan tersebut
sangatlah berpengaruh bagi harga upah.
3. Peralatan
Membuat daftar untuk alat-alat yang akan digunakan dalam pekerjaan
tersebut serta biaya total sewa alat yang akan dipergunakan dalam pekerjaan.
4. Biaya Tak Terduga (Overhead)
Biaya tak terduga adalah biaya yang tidak dimasukkan kedalam suatu jenis
pekerjaan dan tidak dapat dimasukan pada sebuah proyek.
5. Keuntungan (Profit)
Jasa pekerjaan konstruksi atau juga dinamakan dengan keuntungan
pelaksanaan haruslah dihitung dalam rencana anggaran biaya, akan tetapi tidak
boleh disampaikan dalam rencana anggaran biaya tersebut. Besarnya keuntungan
yang diperoleh adalah sebesar biaya proyek yang akan dilaksanakan nantinya.
1. Mengumpulkan Data
Mengumpulkan data, memisahkan, dan mengelola adalah sangat penting
dalam menghitung biaya secara tepat dan kemudian harus menyimpan data-data
dan biaya-biaya proyek yang sudah selesai dikerjakan.
2. Meninjau Lapangan
Sebelum menghitung perkiraan biaya proyek, seorang estimator terlebih
dahulu harus meninjau keadaan lapangan untuk mengetahui kondisi setempat.
2.3 Penjadwalan
Penjadwalan adalah pengukuran (ploting) kegiatan pelaksanaan kedalam
unsure waktu sepanjang masa pelaksanaan pekerjaan proyek. Dimana kegiatan
merupakan semua kegiatan pelaksanaan, sedangkan waktu adalah waktu yang
diperlukan untuk menyelesaikan kegiatan-kegiatan tersebut. Factor waktu harus
mendapat perbaikan karena banyak hal yang mempengaruhi untuk dapat
dimanfaatkan secara produktif. Antara lain factor cuaca, jumlsh hari libur, waktu
istirahat, factor lapangan dan lain-lain. Beberapa syarat dalam penjadwalan perlu
diperhatikan, antara lain:
1. Pekerjaan yang dijadwalkan tidak boleh lebih dari kemampuan yang tersedia.
2. Pekerjaan yang mempunyai pengaruh pekerjaan lain harus diprioritaskan.
3. Penjadwalan harus meminjam kelangsungan pekerjaan secara terus menerus
dalam keseluruhannya.
4. Perencanaan kerja dan penjadwalannya dapat dibuat dalam bentuk Barchart,
Seperti contoh Tabel 2.1 dibawah ini.
5.
Tabel 2.1 Contoh Bar Chart
No. Pekerjaan Minggu/Bulan
13
I II III IV
1 Pondasi
2 Struktur
3 Finishing
masih sedikit, kemudian pada pertengahan meningkat dalam jumlah cukup besar,
lalu pada akhir proyek volume kegiatan kembali mengecil.
Untuk menentukan bobot pekerjaan pendekatan yang dilakukan dapat
berupa perhitungan presentase berdasarkan biaya per jam pekerjaan / kegiatan
dibagi nilai anggaran, karena satuan biaya dapat dijadikan bentuk presentase
sehingga lebih mudah untuk menghitungnya. Bobot kegiatan adalah nilai
presentase proyek dimana penggunaanya dipakai untuk mengetahui kemajuan
proyek tersebut.
Keunggulan penggunaan kurva S pada system penjadwalan adalah mudah
dibaca dan dimengerti oleh seluruh level mulai dari pelaksana sampai manajer
karena bentuk grafiknya yang sederhana dan merupai bentuk S. Oleh karena itu,
kurva S sangat umum digunakan pada industri konstruksi, terutama pada tahapan
awal proyek dimana banyak terjadi perubahan-perubahan rencana.
Kelemahan kurva S terletak pada kurang penjelasan akan terkaitan antara
kegiatan, dan tidak dapat secara langsung memberikan informasi mengenai akibat-
akibat yang akan terjadi bila ada sesuatu perubahan.
diketahui seberapa besar prestasi pekerjaan, apakah lebih cepat atau terlambat
dari jadwal.
5. Sebagai pedoman manajer proyek untuk mengambil kebijakan agar
pelaksanaan pekerjaan bisa selesai sesuai batas waktu kontrak.
6. Untuk manajemen pengadaan material, tenaga dan peralatan proyek sesuai
dengan jenis kegiatan yang akan dikerjakan setiap tanggalnya.
7. Sebagai bahan pelaporan proyek dari kontraktor kepada manajemen
konstruksi, konsultan pengawas, atau owner sebagai pemilik proyek.
BAB III
METODOLOGI PENULISAN
18
19
Mulai
PENGUMPULAN
DATA
HSPK GAMBAR
BESTEK
AHSP VOLUME
PEKERJAA
N
Selesai
Mulai
Volume masing-masing
Item Pekerjaan
Bobot Perkerjaan
Penjadwalan
Kurva S
Selesai
Pekerjaan Rumus
Pekerjaan Persiapam
Pembersihan Lapangan V= Luas = Panjang x Lebar
Pemasangan Bowplank V= Keliling = 2(p+l)
Penggalian
V = Luas penampang galian x jumlah
Galian Tanah Pondasi
panjang pondasi
Urugan Kembali V = ¼ galian
Pasangan Pada Galian
Urugan Pasir V = Luas penampang urugan x jumlah
panjang pondasi
V = Luas Penampang Anstamping x
Anstamping Batu Kali
jumlah panjang pondasi
V = Luas penampang pondasi x
Pasangan Batu Kali Batu Gunung
jumlah panjang pondasi
Pekerjaan beton/dinding
Beton bertulang
V = jumlah panjang sloof x luas
Beton sloof
penampang sloof
V = jumlah panjang reng balok x
Kolom praktis
penampang reng balok
V = jumlah panjang reng balok x
Ring balk
penampang reng balok
Beton tak bertulang
Beton cor 1:2:3 V = Luas bidang x tebal
Bak mandi V = luas penampang bak x tinggi bak
Dinding
V = luas pas tembok 1:2 = panjang
Pas. Tembok 1:2
dinding x tinggi
V = luas pas tembok 1:4 = panjang
Pas. Tembok 1:4
dinding x tinggi
23
Kusen
V = panjang kusen seluruhnya x luas
Kusen pintu dan jendela
penampang
V = panjang kayu yang menyentuh
Memeni kayu yang menyentuh
pasangan x lebar kusen = luas daun
pasangan
telinga
V = panjang baut angker x berat 1
Baut Angker
buah baut x banyak baut
Pekerjaan kap/atap
Pekerjaan kuda-kuda kayu
Pas.kuda-kuda kayu m3 V = Volume kuda kuda kayu
V = lebar penampang kayu x tinggi
penampang kayu x jumlah psg
Pas Gording m3
konstruksi kuda-kuda kayu yang sama
ukurannya
V = panjang papan routter dalam
Pas Routter m
meter
Pas Rangka atap m2 V = (luas atap x kell kayu) : cos 300
V = panjang semua kuda-kuda x kell
Pek Residu kuda-kuda m3
kayu
V = panjang baut angker x berat 1
Pek Angker/m2
buah baut x banyak baut
V = panjang papan lisplank x lebar
Pek Papan Lisplank
kayu
Pas.Atap
Pas Atap Genteng Metal V = luas bidang atap
Pas perabung genteng metal V = Perabung
Pas bola-bola V = panjang bola-bola
Pekerjaan Palfon
V = luas keseluruhan ruangan yang
Rangka Plafon Dalam
akan dipasang plafon
24
27
28
4. Pekerjaan Pembesian
Pada bagian ini pekerjaan yang harus dilakukan antara lain, pembesian
pondasi foot plat, pembesian sloof, pembesian kolom, pembesian sengkang kolom,
pembesian kolom 30/30 lantai 1 2 3 dan atap dak, pembesian balok 30/40 lantai 2
dan 3, pembesian balok 25/30 lantai 2 dan 3, pembesian ringbalk atap dak,
pembesian plat lantai 2 dan 3 kemudian atap dak, plat bordes dan pembesian untuk
tangga.
5. Pekerjaan Bekisting
Adapun bagian yang harus dikerjaan pada pekerjaan bekisting yaitu, bekisting
sloof 30/40, pemasangan bekisting pada kolom lantai satu dua dan tiga, bekesting
balok pada lantai 2 dan 3, bekesting ringbalk, plat lantai , atap dak dan tangga mulai
dari lantai 1 sampai dengan 3.
6. Pekerjaan Dinding
Untuk pekerjaan dinding pekerjaan yang harus dilakukan meliputi, pekerjaan
pasangan dinding bata 1 : 4 lantai satu dua dan tiga, pekerjaan plesteran 1 : 4 pada
lantai satu dua dan tiga, pekerjaan plesteran 1 : 2 dinding kamar mandi pada lantai
dua dan tiga.
7. Pekerjaan Lantai
Pada pekerjaan lantai terdapat beberapa pekerjaan yang perlu di lakukan
yaitu, pemasangan keramik 30x30 meliputi lantai 1 lantai 2 dan teras pada lantai 2,
pemasangan keramik 20x20 kamar mandi lantai 2 dan pada dinding kamar mandi,
kemudian ada pemasangan keramik pada tangga dengan ukuran 30x30.
8. Pekerjaan Plafon
Pada pekerjaan plafon pekerjaan yang perlu dilakukan yaitu pemasangan
plafon gypsum board.
9. Pekerjaan Kusen, Daun Pintu dan Jendela
Pada pekerjaan kusen yang perlu di lihat yaitu, pek. Kusen pintu, jendela,
rangka ventilasi, daun pintu panel kayu bangkirai, kaca jendela mati bening 5 mm,
pintu rolling door.
28
29
29
30
30
31
31
32
32
33
33
34
34
35
35
36
36
37
37
38
= 871.79 kg
Berat besi sloof 30/40 Ø10 =871.79 kg
5. Pembesian sloof 20/40 Ø16
Berat besi sloof 20/40 Ø16 =893.54 kg
6. Pembesian sloof 20/40 Ø12
Berat besi sloof 20/40 Ø12 =160.44 kg
7. Pembesian sloof 20/40 Ø10
Berat besi sloof 20/40 Ø10 =380.47 kg
8. Pembesian kolom pada pondasi FP1 Ø22
Berat besi kolom pada pondasi FP1 Ø22 =575.77 kg
9. Pembesian kolom pada pondasi FP2 Ø22
Berat besi kolom pada pondasi FP2 Ø22 =772.64kg
10. Pembesian kolom pada pondasi FP3 Ø22
Berat besi kolom pada pondasi FP3 Ø22 = 1494.28 kg
11. Pembesian sengkang kolom pada pondasi Ø10
Berat besi sengkang kolom pada pondasi Ø10 =270.58 kg
12. Pembesian kolom 30/30 lantai 1-lantai 2 Ø22
Berat besi kolom 30/30 lantai 1-lantai 2 Ø22 =313.65 kg
13. Pembesian kolom 30/30 lantai 1-lantai 2 Ø10
Berat besi kolom 30/30 lantai 1-lantai 2 Ø10 =2882.41 kg
14. Pembesian kolom 30/30 lantai 2-lantai 3 Ø22
Berat besi kolom 30/30 lantai 2-lantai 3 Ø22 =523.08 kg
15. Pembesian kolom 30/30 lantai 2-lantai 3 Ø10
Berat besi kolom 30/30 lantai 2-lantai 3 Ø10 =523.08 kg
16. Pembesian kolom 30/30 lantai 3-atap dak Ø22
Berat besi kolom 30/30 lantai 3-atap dak Ø22 =2882.41 kg
17. Pembesian kolom 30/30 lantai 3-atap dak Ø10
Berat besi kolom 30/30 lantai 3-atap dak Ø10 =523.08 kg
18. Pembesian kolom 30/30 atas atap Ø22
Berat besi kolom 30/30 atas atap Ø22 =143.23 kg
19. Pembesian kolom 30/30 atas atap Ø10
Berat besi kolom 30/30 atas atap Ø10 =26.3 kg
38
39
39
40
40
41
41
42
42
43
Jumlah
Panjang Lebar Volume
Panel Panel
(m) (m) (bh) (m²)
Panel 2 2.25 2.00 4.00 18.00
Panel 3 4.00 2.25 4.00 18.00
Panel 4 4.00 5.00 6.00 120.00
Panel 5 1.50 5.00 2.00 15.00
Total 193.00
43
44
44
45
45
46
46
47
47
48
48
49
49
50
Optrade = 0.21 m
Antrade = 0.25 m
Lebar anak tangga = 1.00 m
Jumlah anak tangga = 19 buah
Panjang plat bordes = 2.28 m
Lebar plat bordes = 1 m
V1 = 0.21 × 1.00 × 19 = 3.99 m²
V2 = 0.25 × 1.00 × 19 = 4.75 m²
V3 = 2.28 × 1.00 = 2.28 m²
Vtotal = (V1 + V2 + V3) × Jumlah tangga
= (3.99 + 4.75 +2.28) × 2
= 83.39 m²
4.2.8 Perhitungan Volume Pekerjaan Plafon
1. Pemasangan plafon gypsum board = luas keramik lantai keseluruhan
Keramik 30 x 30 = 200.00 + 160.40 + 160.40 = 481.20 m²
Keramik kamar mandi = 10.00 + 10.00 = 20.00 m²
Keramik teras/ balkon = 2.00 = 2.00 m²
Vtotal pekerjaan plafon = 481.20 + 20.00 + 2.00 = 503.20 m²
4.2.9 Perhitungan Volume Pekerjaan Kusen, Daun Pintu & Jendela
1. Kusen pintu kayu bangkirai (P1)
50
51
51
52
52
53
Lantai 2
1. Pemasangan instalasi pipa Ø6" air kotor septictank= 75.53 m
2. Pemasangan instalasi pipa Ø4" air bekas= 50.49 m
3. Pemasangan instalasi pipa Ø3/4" air bersih= 29.56 m
4. Pemasangan kran air= 2 Buah
5. Pemasangan bak kontrol 30 x 30= 2 Buah
6. Pemasangan closet duduk = 2 Buah
53
54
54
55
55
56
56
57
57
58
Pada perhitungan Rencana Anggaran Biaya Bekisting kolom, balok, plat dan
tangga penggunaannya dapat dipakai secara berulang agar dapat menghemat
pekerjaan tersebut. Pekerjaan beton diperoleh hasil perhitungan sebesar Rp.
278,409,447.90 dengan harga satuan bekisting sloof sebesar Rp. 237,601.13, harga
satuan bekisting kolom sebesar Rp. 439,901.80 , harga satuan bekisting balok
sebesar Rp. 461,569.45, harga satuan bekisting plat sebesar Rp. 484,282.60 dan
harga satuan bekisting tangga sebesar Rp. 412,420.82 seperti pada tabel 4.13
58
59
4.4.9 Rencana Anggaran Biaya Pekerjaan Kusen, Daun Pintu dan Jendela
Pada pekerjaan kusen, daun pintu dan jendela diperoleh hasil perhitungan
sebesar Rp. 40,729,564.69 dengan harga satuan kusen kayu bangkirai sebesar Rp.
12,400,682.88, daun pintu kayu bangkirai sebesar Rp. 926,578.00, daun jendela
kayu bangkirai sebesar Rp.679,539,.60, kaca jendela kayu bangkirai 5 mm sebesar
Rp. 251,293.04 dan pintu rolling door sebesar Rp. 1,828,802.222seperti pada tabel
4.17.
Tabel 4.17 Rencana Anggaran Biaya Pekerjaan Kusen, Daun pintu, dan Jendela
59
60
60
61
61
62
62
4.6
III PEKERJAAN BETON 13.87% 0.58% 0.60% 0.55% 0.55% 0.58% 0.58% 0.58% 0.58% 0.58% 0.58% 0.58% 0.58% 0.58% 0.58% 0.58% 0.58% 0.58% 0.58% 0.58% 0.58% 0.58% 0.60% 0.58% 0.58%
Penjadwalan
80.0%
IV PEKERJAAN PEMBESIAN 27.23% 1.05% 1.05% 1.05% 1.05% 1.05% 1.05% 1.05% 1.05% 1.05% 1.05% 1.05% 1.05% 1.05% 1.05% 1.05% 1.05% 1.05% 1.05% 1.05% 1.05% 1.05% 1.05% 1.05% 1.05% 1.05% 1.05%
V PEKERJAAN BEKISTING 16.98% 0.65% 0.65% 0.65% 0.65% 0.65% 0.65% 0.65% 0.65% 0.65% 0.65% 0.65% 0.65% 0.65% 0.65% 0.65% 0.65% 0.65% 0.65% 0.65% 0.65% 0.65% 0.65% 0.65% 0.65% 0.65% 0.65%
60.0%
VI PEKERJAAN DINDING 18.29% 0.73% 0.73% 0.73% 0.73% 0.73% 0.73% 0.73% 0.73% 0.73% 0.73% 0.73% 0.73% 0.73% 0.73% 0.73% 0.73% 0.73% 0.73% 0.73% 0.73% 0.73% 0.73% 0.73% 0.73% 0.73%
VII PEKERJAAN LANTAI 5.79% 0.39% 0.39% 0.39% 0.39% 0.39% 0.39% 0.39% 0.39% 0.39% 0.39% 0.39% 0.39% 0.39% 0.39% 0.39%
63
VIII PEKERJAAN PLAFON 3.22% 0.32% 0.32% 0.32% 0.32% 0.32% 0.32% 0.32% 0.32% 0.32% 0.32%
40.0%
IX PEK. KUSEN, DAUN PINTU DAN JENDELA 2.48% 0.13% 0.13% 0.13% 0.13% 0.13% 0.13% 0.13% 0.13% 0.13% 0.13% 0.13% 0.13% 0.13% 0.13% 0.13% 0.13% 0.13% 0.13% 0.13%
X PEMASANGAN INSTALASI LISTRIK 1.28% 0.14% 0.14% 0.14% 0.14% 0.14% 0.14% 0.14% 0.14% 0.14%
20.0%
XI PEK. SANITAIR DAN INSTALASI AIR 3.38% 0.38% 0.38% 0.38% 0.38% 0.38% 0.38% 0.38% 0.38% 0.38%
XII PEKERJAAN PENGECATAN 5.57% 0.80% 0.80% 0.80% 0.80% 0.80% 0.80% 0.80%
RENCANA PROGRES MINGGUAN 100.00% 0.40% 0.56% 0.16% 1.21% 1.86% 2.28% 2.30% 2.99% 2.99% 3.14% 3.14% 3.14% 3.14% 3.14% 3.14% 3.53% 3.53% 3.90% 3.90% 4.37% 4.37% 4.37% 4.37% 4.37% 4.37% 4.37% 4.81% 4.79% 4.51% 2.57% 1.53% 1.53% 1.03% 0.24%
RENCANA KOMULATIF MINGGUAN 0.4% 1.0% 1.1% 2.3% 4.2% 6.5% 8.8% 11.7% 14.7% 17.9% 21.0% 24.2% 27.3% 30.4% 33.6% 37.1% 40.6% 44.5% 48.4% 52.8% 57.2% 61.5% 65.9% 70.3% 74.6% 79.0% 83.8% 88.6% 93.1% 95.7% 97.2% 98.7% 99.8% 100%
63
BAB V
PENUTUP
5.1 Kesimpulan
Rencana Anggaran Biaya Gedung Ruko 3 Lantai dengan luas bangunan 630
m² di Jalan Soekarno Hatta Km. 3 Balikpapan, direncanakan sesuai dengan analisa
harga satuan pekerjaan dari DPU Kota Balikpapan Tahun 2016. (Permen PU No.
28/PRT/M/2016). Hasil yang diperoleh penulis, yaitu sebagai berikut :
1. Rencana Anggaran Biaya di Jalan Soekarno Hatta Km. 3 Balikpapan yang
dibutuhkan untuk menyelesaikan proyek pembangunan ruko 3 lantai dengan
menggunakan harga satuan upah dan bahan Kota Balikpapan Tahun 2017
sebesarRp. 1,640,054,194.59-.
2. Waktu yang dibutuhkan untuk menyelesaikan proyek pembangunan ruko 3
lantai di Jalan Soekarno Hatta Km. 3 Balikpapanyang telah direncanakan
dengan durasi 1 minggu 7 hari , maka proyek tersebut dapat diselesaikan
dalam waktu 8 bulan 2 minggu atau 238 hari.
3. Metode kurva S merupakan metode yang umum digunakan untuk menghitung
rencana anggaran biaya. Adapun hal-hal pokok yang diperlukan untuk
menghitung estimasi biaya yaitu: Bahan-bahan, harga upah, peralatan, biaya
tak terduga dan keuntungan.
5.2 Saran
Saran-saran yang dapat diberikan oleh penulis kepada pembaca khususnya
kepada mahasiswa jurusan Teknik Sipil adalah :
1. Dalam perhitungan Rencana Anggaran Biaya dibutuhkan data-data yang
lengkap dari berbagai sumber.
2. Dalam menyusun rencana penjadwalan, dibutuhkan keahlian dalam
menempatkan lebih dari satu pekerjaan didalam durasi tertentu, sehingga
menghasilkan waktu yang lebih efektif.
64
DAFTAR PUSTAKA
Ibrahim, H. B. (1993). Rencana dan Estimate Real of Cost. Jakarta: Bumi aksara.
65
LAMPIRAN
66
LAMPIRAN 1
67
68
69
70
71
72
73
74
75
76
77
78
79
LAMPIRAN 2
Harga Satuan Jumlah Harga
NO Uraian Pekerjaan Volume Sat
(Rp) (Rp)
1 2 3 4 5 6=(3×5)
I PEKERJAAN PENDAHULUAN
1 Pembersihan lokasi pekerjaan (mulai pekerjaan awal-akhir) 1.00 ls 2,000,000.00 2,000,000.00
2 Pengukuran dan pemasangan bouwplank 60.00 m' 85,198.02 5,111,881.01
3 Penyediaan air kerja 1.00 ls 2,000,000.00 2,000,000.00
4 Penyediaan listrik 1.00 ls 4,000,000.00 4,000,000.00
SUB TOTAL 13,111,881.01
II PEKERJAAN TANAH DAN PONDASI
1 Galian pondasi foot plat 25.20 m³ 99,370.12 2,504,127.02
2 Pek. Pancang mini pile 10x10 18.00 titik -
3 pondasi batu gunung 41.13 m³ 87,883.00 3,614,627.79
4 Urugan tanah pondasi 13.57 m³ 257,057.20 3,488,266.20
5 Urugan kembali bekas galian pondasi 12.60 m³ 63,871.00 804,774.60
SUB TOTAL 10,411,795.62
III PEKERJAAN BETON
1 Pondasi foot plat Beton K250 12.60 m³ 1,430,753.38 18,027,492.53
2 Cor sloof 30/40 Beton K250 14.40 m³ 1,430,753.38 20,602,848.60
3 Cor kolom 30/30 lantai 1 Beton K250 5.67 m³ 1,430,753.38 8,112,371.64
4 Cor kolom 30/30 lantai 2 Beton K175 5.67 m³ 1,358,833.00 7,704,583.09
5 Cor kolom 30/30 lantai 3 Beton K175 5.67 m³ 1,358,833.00 7,704,583.09
6 Balok 30/40 lantai 2 Beton K250 10.08 m³ 1,430,753.38 14,421,994.02
7 Balok 25/30 lantai 2 Beton K250 1.62 m³ 1,430,753.38 2,317,820.47
8 Balok 25/30 lantai 3 Beton K250 2.84 m³ 1,430,753.38 4,063,339.59
9 Balok 30/40 lantai 3 Beton K250 10.08 m³ 1,430,753.38 14,421,994.02
10 Ringbalk 30/40 atap dak Beton K250 10.08 m³ 1,430,753.38 14,421,994.02
11 Ringbalk 25/30 atap dak Beton K250 3.15 m³ 1,430,753.38 4,506,873.13
12 Tangga beton lt.1-2 Beton K250 2.77 m³ 1,430,753.38 3,963,186.85
13 Tangga beton lt 2 ke lt 3 Beton K250 2.77 m³ 1,430,753.38 3,963,186.85
14 Plat lantai 2 Beton K250 23.16 m³ 1,430,753.38 33,136,248.17
15 Plat lantai 3 Beton K250 23.16 m³ 1,430,753.38 33,136,248.17
16 Plat atap dak Beton K250 25.80 m³ 1,430,753.38 36,913,437.08
SUB TOTAL 227,418,201.33
IV PEKERJAAN PEMBESIAN
1 Pembesian pondasi foot plat Ø22 4941.27 kg 10,956.26 54,137,852.72
2 Pembesian sloof 30/40 Ø16 1494.28 kg 10,956.26 16,371,724.39
3 Pembesian kolom pada pondasi FP1 Ø22 575.77 kg 10,956.26 6,308,287.44
4 Pembesian kolom pada pondasi FP2 Ø22 772.64 kg 10,956.26 8,465,246.89
5 Pembesian kolom pada pondasi FP3 Ø22 270.58 kg 10,956.26 2,964,545.59
6 Pembesian sengkang kolom pada pondasi Ø10 313.65 kg 12,233.64 3,837,079.64
7 Pembesian kolom 30/30 lantai 1-lantai 2 Ø22 2882.41 kg 10,956.26 31,580,441.48
8 Pembesian kolom 30/30 lantai 1-lantai 2 Ø10 523.08 kg 12,233.64 6,399,169.83
9 Pembesian kolom 30/30 lantai 2-lantai 3 Ø22 2882.41 kg 10,956.26 31,580,441.48
10 Pembesian kolom 30/30 lantai 2-lantai 3 Ø10 523.08 kg 12,233.64 6,399,169.83
11 Pembesian kolom 30/30 lantai 3-atap dak Ø22 2882.41 kg 10,956.26 31,580,441.48
12 Pembesian kolom 30/30 lantai 3-atap dak Ø10 523.08 kg 12,233.64 6,399,169.83
13 Pembesian balok 30/40 lantai 2 Ø16 1387.56 kg 10,956.26 15,202,472.02
14 Pembesian balok 30/40 lantai 2 Ø12 250.22 kg 12,385.42 3,099,080.19
15 Pembesian balok 25/30 lantai 2 Ø10 704.44 kg 12,233.64 8,617,861.89
16 Pembesian balok 30/40 lantai 3 Ø16 813.74 kg 10,956.26 8,915,549.30
17 Pembesian balok 30/40 lantai 3 Ø12 216.93 kg 12,385.42 2,686,769.51
18 Pembesian balok 25/30 lantai 3 Ø10 495.41 kg 12,233.64 6,060,665.15
19 Pembesian ringbalk 30/40 atap dak Ø16 925.04 kg 10,956.26 10,134,981.35
20 Pembesian ringbalk 25/30 atap dak Ø12 250.22 kg 12,385.42 3,099,080.19
21 Pembesian plat lantai 2 Ø10 3678.10 kg 14,068.68 51,746,013.12
22 Pembesian plat lantai 3 Ø10 3678.10 kg 14,068.68 51,746,013.12
23 Pembesian plat atap dak Ø10 4035.61 kg 14,068.68 56,775,707.03
24 Pembesian plat bordes Ø12 134.23 kg 14,243.23 1,911,869.41
25 Pembesian plat bordes Ø10 140.56 kg 14,068.68 1,977,493.71
26 Pembesian tangga Ø12 572.60 kg 14,243.23 8,155,676.26
27 Pembesian tangga Ø10 745.30 kg 14,068.68 10,485,387.45
SUB TOTAL 446,638,190.28
80
V PEKERJAAN BEKISTING
1 Pemasangan bekisting sloof 30/40 84.00 m² 237,601.13 19,958,495.09
2 Pemasangan bekisting kolom 30/30 lantai 1 6.48 m² 237,601.13 1,539,655.34
3 Pemasangan bekisting kolom 30/30 lantai 2 6.48 m² 439,901.80 2,850,563.63
4 Pemasangan bekisting kolom 30/30 lantai 3 6.48 m² 439,901.80 2,850,563.63
5 Pemasangan bekisting balok 30/40 lantai 2 130.79 m² 116,414.10 15,225,800.14
6 Pemasangan bekisting balok 25/30 lantai 2 38.43 m² 116,414.10 4,473,793.86
7 Pemasangan bekisting balok 30/40 lantai 3 130.79 m² 116,414.10 15,225,800.14
8 Pemasangan bekisting balok 25/30 lantai 3 38.43 m² 116,414.10 4,473,793.86
9 Pemasangan bekisting Ringbalk 30/40 atap dak 130.79 m² 461,569.45 60,368,668.50
10 Pemasangan bekisting ringbalk 25/30 atap dak 38.43 m² 461,569.45 17,738,114.00
11 Pemasangan bekisting plat lantai 2 193.00 m² 116,414.10 22,467,921.30
12 Pemasangan bekisting plat lantai 3 193.00 m² 116,414.10 22,467,921.30
13 Pemasangan bekisting atap dak 215.00 m² 116,414.10 25,029,031.50
14 Pemasangan bekisting tangga lt 1-2 106.11 m² 116,414.10 12,352,583.74
15 Pemasangan bekisting tangga lt 2-3 106.11 m² 484,282.60 51,386,741.87
SUB TOTAL 278,409,447.90
VI PEKERJAAN DINDING
1 Pek. Pasangan bata 1 : 4 lantai 1 248.00 m³ 174,074.24 43,170,410.28
2 Pek. Pasangan bata 1 : 4 lantai 2 279.57 m³ 174,074.24 48,665,933.88
3 Pek. Pasangan bata 1 : 4 lantai 3 338.22 m³ 174,074.24 58,875,387.76
4 Pek. Plesteran 1 : 4 lantai 1 496.00 m² 78,971.12 39,169,676.02
5 Pek. Plesteran 1 : 4 lantai 2 559.14 m² 78,971.12 44,155,912.60
6 Pek. Plesteran 1 : 4 lantai 3 676.44 m² 78,971.12 53,419,225.09
7 Pek. Plesteran 1 : 2 dinding kamar mandi lantai 2 74.16 m² 83,988.05 6,228,553.54
8 Pek. Plesteran 1 : 2 dinding kamar mandi lantai 3 74.16 m² 83,988.05 6,228,553.54
SUB TOTAL 299,913,652.69
VII PEKERJAAN LANTAI
1 Pemasangan keramik 30 x 30 lt. 1 200.00 m² 82,123.00 16,424,599.00
2 Pemasangan keramik 30 x 30 lantai 2 160.40 m² 190,199.08 30,507,931.63
3 Pemasangan keramik 30 x 30 teras lantai 2 2.00 m² 184,439.19 368,878.37
4 Pemasangan keramik 20 x 20 teras lantai 2 2.00 m² 244,498.74 488,997.48
5 Pemasangan keramik 20 x 20 kamar mandi lantai 2 6.00 m² 82,123.00 492,737.97
6 Pemasangan keramik 20 x 20 dinding kamar mandi lt. 2 10.48 m² 190,199.08 1,993,286.31
7 Pemasangan keramik 30 x 30 lt. 3 160.40 m² 184,439.19 29,584,045.27
8 Pemasangan keramik 20 x 20 kamar mandi lt.3 10.00 m² 244,498.74 2,444,987.40
9 Pemasangan keramik 20 x 20 dinding kamar mandi lt.3 10.48 m² 82,123.00 860,648.99
10 Pemasangan keramik 30 x 30 tangga lt. 1-2 dan lt. 2-3 83.39 m² 141,731.50 11,818,989.53
SUB TOTAL 94,985,101.95
VIII PEKERJAAN PLAFON
1 Pemasangan plafon gypsum board 503.00 m² 104,922.38 52,775,955.88
SUB TOTAL 52,775,955.88
IX PEKERJAAN KUSEN, DAUN PINTU DAN JENDELA
1 Kusen pintu kayu bangkirai (P1) 0.47 m³ 12,400,682.88 5,828,320.95
2 Kusen pintu kayu bangkirai (P2) 0.16 m³ 12,400,682.88 1,946,907.21
3 Kusen jendela kayu bangkirai (J1) 0.14 m³ 12,400,682.88 1,674,092.19
6 Rangka ventilasi kayu bangkirai (V1) 0.05 m³ 12,400,682.88 620,034.14
8 Daun pintu panel kayu bangkirai (P1) 16.35 m² 926,578.00 15,149,550.30
10 Kaca jendela mati bening 5 mm (J1) 6.05 m² 251,293.04 1,520,322.91
14 Pintu rolling door 7.65 m² 1,828,802.22 13,990,336.98
SUB TOTAL 40,729,564.69
X PEKERJAAN INSTALASI LISTRIK
1 Pemasangan instalasi titik lampu 31 titik 293,250.00 9,090,750.00
2 Pemasangan instalasi stop kontak 23 titik 354,430.00 8,151,890.00
3 Pemasangan box MCB 1 unit 189,635.00 189,635.00
4 Pemasangan saklar tunggal 8 buah 124,430.00 995,440.00
5 Pemasangan saklar ganda 15 buah 124,430.00 1,866,450.00
6 Lampu TL 40 watt panjang 6 buah 48,700.00 292,200.00
7 Lampu pijar 25 watt 15 buah 16,700.00 250,500.00
8 Lampu pijar 5 watt 10 buah 13,300.00 133,000.00
SUB TOTAL 20,969,865.00
81
XI PEKERJAAN SANITAIR DAN INSTALASI AIR
1 Pemasangan instalasi pipa Ø6" air kotor septictank 85.14 m' 160,800.00 13,690,512.00
2 Pemasangan instalasi pipa Ø4" air bekas 81.08 m' 274,432.00 22,250,946.56
3 Pemasangan instalasi pipa Ø3/4" air bersih 59.12 m' 36,180.00 2,138,961.60
4 Pemasangan kran air 4 buah 173,357.33 693,429.30
5 Pemasangan bak kontrol 30 x 30 4 buah 507,750.07 2,031,000.28
6 Pemasangan kitchen zink 4 buah 531,998.05 2,127,992.20
7 Pemasangan closet duduk 4 buah 399,311.05 1,597,244.20
8 Pemasangan floor drain 4 buah 451,146.15 1,804,584.60
9 Pemasangan bak mandi terazo 4 buah 1,605,474.44 6,421,897.75
10 Septic tank buis beton Ø100 cm 2 unit 1,365,663.59 2,731,327.19
SUB TOTAL 55,487,895.68
XII PEKERJAAN PENGECATAN
1 Cat dinding lantai 1 496.00 m² 41,062.01 20,366,758.30
2 Cat dinding lantai 2 559.14 m² 41,062.01 22,959,413.78
3 Cat dinding lantai 3 676.44 m² 41,062.01 27,775,987.87
5 Cat plafon 503.20 m² 40,265.65 20,261,674.68
SUB TOTAL 91,363,834.63
XIII PEKERJAAN PENGUNCI DAN PENGGANTUNG
1 Pemasangan kunci tanam 16 set 108,874.41 1,741,990.56
2 Pemasangan engsel pintu 4" 48 buah 66,255.23 3,180,250.85
3 Pemasangan engsel jendela 3" 8 buah 38,169.54 305,356.28
4 Pemasangan grendel pintu tanam 16 buah 136,679.57 2,186,873.12
5 Pemasangan grendel jendela 4 buah 58,749.82 234,999.28
6 Pemasangan hak angin 4 buah 47,334.46 189,337.84
SUB TOTAL 7,838,807.93
TOTAL 1,640,054,194.59
82
LAMPIRAN 3
83
84
85
86
87
88
89
90
91
92
93
94
95
96
97
98
99
100
101
102
103
104
105
106
107
108
109
110
111
112
LAMPIRAN 4
HARGA SATUAN
No URAIAN SAT KOEF JUMLAH (Rp)
(Rp)
PEKERJAAN PENDAHULUAN
Pengukuran dan pemasangan 1 m' bouwplank
A TENAGA
Pekerja OH 0.10 Rp 97,300.00 Rp 9,730.00
Tukang kayu OH 0.10 Rp 129,800.00 Rp 12,980.00
Kepala tukang OH 0.01 Rp 145,900.00 Rp 1,459.00
Mandor OH 0.005 Rp 137,800.00 Rp 689.00
JUMLAH TENAGA KERJA Rp 24,858.00
B BAHAN
Kayu balok 5/7 m³ 0.012 Rp 2,358,400.00 Rp 28,300.80
Paku 2"-3" kg 0.02 Rp 27,121.60 Rp 542.43
Kayu papan 3/20 m³ 0.007 Rp 2,912,000.00 Rp 20,384.00
JUMLAH HARGA BAHAN Rp 49,227.23
C PERALATAN
113
Pengurugan 1 m³ dengan pasir urug
A TENAGA
Pekerja OH 0.3 Rp 97,300.00 Rp 29,190.00
Mandor OH 0.010 Rp 137,800.00 Rp 1,378.00
JUMLAH TENAGA KERJA Rp 30,568.00
B BAHAN
Pasir urug m³ 1.200 Rp 160,800.00 Rp 192,960.00
JUMLAH HARGA BAHAN Rp 192,960.00
C PERALATAN
114
Membuat 1 m³ beton mutu f'c = 21.7 Mpa
A TENAGA
Pekerja OH 1.650 Rp 97,300.00 Rp 160,545.00
Tukang batu OH 0.275 Rp 129,800.00 Rp 35,695.00
Kepala tukang OH 0.028 Rp 145,900.00 Rp 4,085.20
Mandor OH 0.083 Rp 137,800.00 Rp 11,437.40
JUMLAH TENAGA KERJA Rp 211,762.60
B BAHAN
Semen portland kg 384.000 Rp 1,391.00 Rp 534,144.00
Pasir beton kg 692 Rp 306.29 Rp 211,949.71
Kerikil (maksimum
kg 1039 Rp 268.89
30 mm) Rp 279,375.56
Air liter 215 Rp 32.10 Rp 6,901.50
JUMLAH HARGA BAHAN Rp 1,032,370.77
C PERALATAN
115
Pembesian 10 kg dengan besi polos Ø12
A TENAGA
Pekerja OH 0.070 Rp 97,300.00 Rp 6,811.00
Tukang besi OH 0.070 Rp 129,800.00 Rp 9,086.00
Kepala tukang OH 0.007 Rp 145,900.00 Rp 1,021.30
Mandor OH 0.004 Rp 137,800.00 Rp 551.20
JUMLAH TENAGA KERJA Rp 17,469.50
B BAHAN
Besi beton (polos/
kg 10.500 Rp 9,809.33
ulir) Rp 102,997.99
Kawat beton kg 0.150 Rp 22,578.14 Rp 3,386.72
JUMLAH HARGA BAHAN Rp 106,384.72
C PERALATAN
116
Pemasangan 1 m² bekisting untuk kolom
A TENAGA
Pekerja OH 0.660 Rp 97,300.00 Rp 64,218.00
Tukang kayu OH 0.330 Rp 129,800.00 Rp 42,834.00
Kepala tukang OH 0.033 Rp 145,900.00 Rp 4,814.70
Mandor OH 0.033 Rp 137,800.00 Rp 4,547.40
JUMLAH TENAGA KERJA Rp 116,414.10
B BAHAN
Kayu kelas III m³ 0.040 Rp 2,358,400.00 Rp 94,336.00
Paku 5-12 cm kg 0.400 Rp 26,818.00 Rp 10,727.20
Minyak bekisting liter 0.200 Rp 6,250.00 Rp 1,250.00
Balok kayu kelas II m³ 0.015 Rp 6,240,000.00 Rp 93,600.00
Plywood tebal 9 mm lbr 0.350 Rp 134,000.00
Rp 46,900.00
Dolken kayu Ø8-10
batang 2.000 Rp 9,648.00
cm-panj 4 m Rp 19,296.00
JUMLAH HARGA BAHAN Rp 266,109.20
C PERALATAN
117
Pemasangan 1 m² bekisting untuk lantai
A TENAGA
Pekerja OH 0.660 Rp 97,300.00 Rp 64,218.00
Tukang kayu OH 0.330 Rp 129,800.00 Rp 42,834.00
Kepala tukang OH 0.033 Rp 145,900.00 Rp 4,814.70
Mandor OH 0.033 Rp 137,800.00 Rp 4,547.40
JUMLAH TENAGA KERJA Rp 116,414.10
B BAHAN
Kayu kelas III m³ 0.040 Rp 2,358,400.00 Rp 94,336.00
Paku 5-12 cm kg 0.400 Rp 26,818.00 Rp 10,727.20
Minyak bekisting liter 0.200 Rp 6,250.00 Rp 1,250.00
Balok kayu kelas II m³ 0.015 Rp 6,240,000.00 Rp 93,600.00
Plywood tebal 9 mm lbr 0.350 Rp 134,000.00
Rp 46,900.00
Dolken kayu galam,
(8-10) cm panjang 4 batang 6.000 Rp 9,648.00
m Rp 57,888.00
JUMLAH HARGA BAHAN Rp 304,701.20
C PERALATAN
118
PEKERJAAN BESI & ALUMINIUM
Pemasangan 1 m² pintu rolling door besi
A TENAGA
Pekerja OH 1.200 Rp 97,300.00 Rp 116,760.00
Tukang besi OH 1.200 Rp 129,800.00 Rp 155,760.00
Kepala tukang OH 0.120 Rp 145,900.00 Rp 17,508.00
Mandor OH 0.006 Rp 137,800.00 Rp 826.80
JUMLAH TENAGA KERJA Rp 290,854.80
B BAHAN
Pintu gulung besi m² 1.000 Rp 1,299,408.00 Rp 1,299,408.00
JUMLAH HARGA BAHAN Rp 1,299,408.00
C PERALATAN
119
Pemasangan 1 m² plesteran 1SP:4PP tebal 15 mm
A TENAGA
Pekerja OH 0.300 Rp 97,300.00 Rp 29,190.00
Tukang batu OH 0.150 Rp 129,800.00 Rp 19,470.00
Kepala tukang OH 0.015 Rp 145,900.00 Rp 2,188.50
Mandor OH 0.015 Rp 137,800.00 Rp 2,067.00
JUMLAH TENAGA KERJA Rp 52,915.50
B BAHAN
PC kg 6.240 Rp 1,391.00 Rp 8,679.84
PP m³ 0.024 Rp 294,800.00 Rp 7,075.20
JUMLAH HARGA BAHAN Rp 15,755.04
C PERALATAN
120
Pemasangan 1 m² lantai ubin warna ukuran 30 cm × 30 cm tangga
A TENAGA
Pekerja OH 0.260 Rp 51,000.00 Rp 13,260.00
Tukang batu OH 0.130 Rp 28,000.00 Rp 3,640.00
Kepala tukang OH 0.013 Rp 482,000.00 Rp 6,266.00
Mandor OH 0.013 Rp 18,000.00 Rp 234.00
JUMLAH TENAGA KERJA Rp 23,400.00
B BAHAN
Ubin warna buah 11.87 Rp 5,194.00 Rp 61,652.78
Semen portland kg 10.00 Rp 1,391.00 Rp 13,910.00
Semen warna kg 0.60 Rp 18,360.00 Rp 11,016.00
Pasir pasang m³ 0.045 Rp 294,800.00 Rp 13,266.00
JUMLAH HARGA BAHAN Rp 99,844.78
C PERALATAN
121
Pemasangan 1 m² dinding keramik ukuran 20 cm × 20 cm dinding kamar mandi
A TENAGA
Pekerja OH 0.90 Rp 97,300.00 Rp 87,570.00
Tukang batu OH 0.45 Rp 129,800.00 Rp 58,410.00
Kepala tukang OH 0.045 Rp 145,900.00 Rp 6,565.50
Mandor OH 0.045 Rp 137,800.00 Rp 6,201.00
JUMLAH TENAGA KERJA Rp 158,746.50
B BAHAN
Keramik artistik buah 26.50 72.380,00 Rp 1,918,070.00
Semen portland kg 9.30 Rp 1,391.00 Rp 12,936.30
Pasir pasang m³ 0.018 Rp 294,800.00 Rp 5,306.40
Semen warna kg 1.94 Rp 18,360.00 Rp 35,618.40
JUMLAH HARGA BAHAN Rp 53,861.10
C PERALATAN
122
PEKERJAAN SANITASI
Pemasangan 1 buah closet duduk
A TENAGA
Pekerja OH 1.00 Rp 97,300.00 Rp 97,300.00
Tukang batu OH 1.50 Rp 129,800.00 Rp 194,700.00
Kepala tukang OH 0.15 Rp 145,900.00 Rp 21,885.00
Mandor OH 0.16 Rp 137,800.00 Rp 22,048.00
JUMLAH TENAGA KERJA Rp 335,933.00
B BAHAN
Closet duduk unit 1.00 Rp 2.242.240,00 Rp 2.242.240,00
Semen portland kg 6.00 Rp 1,391.00 Rp 8,346.00
Pasir pasang m³ 0.01 Rp 294,800.00 Rp 2,948.00
JUMLAH HARGA BAHAN Rp 11,294.00
C PERALATAN
123
Pemasangan 1 buah floor drain
A TENAGA
Pekerja OH 0.01 Rp 97,300.00 Rp 973.00
Tukang batu OH 0.10 Rp 129,800.00 Rp 12,980.00
Kepala tukang OH 0.01 Rp 145,900.00 Rp 1,459.00
Mandor OH 0.005 Rp 137,800.00 Rp 689.00
JUMLAH TENAGA KERJA Rp 16,101.00
B BAHAN
Floor drain buah 1.00 Rp 376,200.00 Rp 376,200.00
JUMLAH HARGA BAHAN Rp 376,200.00
C PERALATAN
124
Pemasangan 1 m' pipa PVC tipe AW diameter ½"
A TENAGA
Pekerja OH 0.036 Rp 97,300.00 Rp 3,502.80
Tukang batu OH 0.06 Rp 129,800.00 Rp 7,788.00
Kepala tukang OH 0.006 Rp 145,900.00 Rp 875.40
Mandor OH 0.002 Rp 137,800.00 Rp 275.60
JUMLAH TENAGA KERJA Rp 12,441.80
B BAHAN
Pipa PVC 1/2" m 1.20 Rp 9,045.00 Rp 10,854.00
Perlengkapan % 0.35 Rp 3,165.75 Rp 1,108.01
JUMLAH HARGA BAHAN Rp 11,962.01
C PERALATAN
125
Septictank buis beton Ø100 cm kedalaman 2 m
A TENAGA
Pekerja OH 0.900 Rp 97,300.00 Rp 87,570.00
Mandor OH 0.045 Rp 137,800.00 Rp 6,201.00
JUMLAH TENAGA KERJA Rp 93,771.00
B BAHAN
Buis beton bulat bh 4.00 Rp 273,440.64 Rp 1,093,762.56
JUMLAH HARGA BAHAN Rp 1,093,762.56
C PERALATAN
126
Pemasangan 1 buah engsel jendela
A TENAGA
Pekerja OH 0.01 Rp 97,300.00 Rp 973.00
Tukang kayu OH 0.10 Rp 129,800.00 Rp 12,980.00
Kepala tukang OH 0.010 Rp 145,900.00 Rp 1,459.00
Mandor OH 0.0005 Rp 137,800.00 Rp 68.90
JUMLAH TENAGA KERJA Rp 15,480.90
B BAHAN
Engsel jendela buah 1.00 Rp 17,710.00 Rp 17,710.00
JUMLAH HARGA BAHAN Rp 17,710.00
C PERALATAN
127
Pemasangan 1 buah kunci slot jendela
A TENAGA
Pekerja OH 0.02 Rp 97,300.00 Rp 1,946.00
Tukang kayu OH 0.2 Rp 129,800.00 Rp 25,960.00
Kepala tukang OH 0.02 Rp 145,900.00 Rp 2,918.00
Mandor OH 0.001 Rp 137,800.00 Rp 137.80
JUMLAH TENAGA KERJA Rp 30,961.80
B BAHAN
Kunci slot jendela buah 1.00 Rp 20,125.00 Rp 20,125.00
JUMLAH HARGA BAHAN Rp 20,125.00
C PERALATAN
128
PEKERJAAN KUSEN KAYU
Pembuatan dan pemasangan 1 m³ kusen pintu dan kusen jendela, kayu kelas II atau III
A TENAGA
Pekerja OH 6.000 Rp 97,300.00 Rp 583,800.00
Tukang kayu OH 18.000 Rp 129,800.00 Rp 2,336,400.00
Kepala tukang OH 1.800 Rp 145,900.00 Rp 262,620.00
Mandor OH 0.300 Rp 137,800.00 Rp 41,340.00
JUMLAH TENAGA KERJA Rp 3,224,160.00
B BAHAN
Balok kayu m³ 1.20 Rp 6,240,000.00 Rp 7,488,000.00
Paku 10 cm kg 1.25 Rp 26,818.00 Rp 33,522.50
Lem kayu kg 1.00 Rp 37,520.00 Rp 37,520.00
JUMLAH HARGA BAHAN Rp 7,559,042.50
C PERALATAN
129
Pemasangan 1 m² kaca tebal 5 mm
A TENAGA
Pekerja OH 0.015 Rp 97,300.00 Rp 1,459.50
Tukang kayu OH 0.150 Rp 129,800.00 Rp 19,470.00
Kepala tukang OH 0.015 Rp 145,900.00 Rp 2,188.50
Mandor OH 0.0008 Rp 137,800.00 Rp 110.24
JUMLAH TENAGA KERJA Rp 23,228.24
B BAHAN
Kaca tebal 5 mm m² 1.10 Rp 174,784.50 Rp 192,262.95
Sealant kg 0.05 Rp 60,490.00 Rp 3,024.50
JUMLAH HARGA BAHAN Rp 195,287.45
C PERALATAN
130
Pemasangan 1 buah MCB
A TENAGA
Upah % 1.00 Rp 32,000.00 Rp 32,000.00
JUMLAH TENAGA KERJA Rp 32,000.00
B BAHAN
MCB buah 1.00 Rp 132,900.00 Rp 132,900.00
JUMLAH HARGA BAHAN Rp 132,900.00
C PERALATAN
131
132
133
134