USULAN RENCANA ANGGARAN BIAYA

PROGRAM : PENINGKATAN SARANA DAN PRASARANA IBADAH


KEGIATAN : PEMBANGUNAN SARANA DAN PRASARANA IBADAH HAJI
PEKERJAAN : PEKERJAAN DRAINASE DAN JALAN
: PEKERJAAN LANDSCAPE
: PEKERJAAN PENERANGAN DAN LAMPU JALAN
: PEKERJAAN TIANG BENDERA
: PEKERJAAN HIDRANT
: PEKERJAAN PAGAR DEPAN
: PEKERJAAN GERBANG DAN POS JAGA
: PEKERJAAN PENERANGAN FASADE BANGUNAN

LOKASI : ASRAMA HAJI PALANGKA RAYA - KALIMANTAN TENGAH


TAHUN : 2019
RENCANA PENATAAN HALAMAN

KETERANGAN :
A. Gerbang Utama
B. Pargar
C. Parkir roda 4/ mobil
D. Parkir Bus
E. Parkir roda 2/ motor

B
C
D
B
A D
C
E
B
01

KETERANGAN :
A. Gerbang Utama
B. Pargar
C. Parkir roda 4/ mobil
D. Parkir Bus
E. Parkir roda 2/ motor

B
C
D
B
A D
C
E
B

RENCANA PENATAAN HALAMAN


02

RENCANA PENATAAN HALAMAN


REKAPITULASI
USULAN RENCANA ANGGARAN BIAYA
(RAB)

PROGRAM : PENINGKATAN SARANA DAN PRASARANA IBADAH


KEGIATAN : PEMBANGUNAN SARANA DAN PRASARANA IBADAH HAJI
PEKERJAAN : PEKERJAAN DRAINASE DAN JALAN
PEKERJAAN LANDSCAPE
PEKERJAAN PENERANGAN DAN LAMPU JALAN
PEKERJAAN TIANG BENDERA
PEKERJAAN HIDRANT
PEKERJAAN PAGAR DEPAN
PEKERJAAN GERBANG DAN POS JAGA
PEKERJAAN PENERANGAN FASADE BANGUNAN
LOKASI : ASRAMA HAJI PALANGKA RAYA - KALIMANTAN TENGAH
TAHUN : 2019

NO. PEKERJAAN HARGA


A PEKERJAAN DRAINASE DAN JALAN
A.1 PEKERJAAN PERSIAPAN 33.600.560,56
A.2 PEKERJAAN TANAH 155.318.959,09
A.3 PEKERJAAN SIRING 68.781.349,35
A.4 PEKERJAAN BETON 758.987.255,23
A.5 PEKERJAAN PLESTERAN 31.528.684,53
A.6 PEKERJAAN PENGECATAN 936.545,63
A.7 PEKERJAAN SANITASI GEDUNG 12.889.200,00
A.8 PEKERJAAN ASPAL 2.313.610.480,85
TOTAL - A 3.375.653.035,25
B PEKERJAAN LANDSCAPE
B.1 PEKERJAAN PERSIAPAN (landscape) 12.343.007,50
B.2 PEKERJAAN TANAH (landscape) 275.364.214,08
B.3 PEKERJAAN PENUTUP LANTAI DAN PENUTUP DINDING (landscape) 493.749.120,15
B.4 PEKERJAAN PENGECATAN (landscape) 27.909.059,63
B.5 PEKERJAAN SANITASI GEDUNG (landscape) 13.439.374,38
B.6 PEKERJAAN VEGETASI (landscape) 727.137.525,00
TOTAL - B 1.549.942.300,73
C PEKERJAAN PENERANGAN DAN LAMPU JALAN
C.1 PEKERJAAN PERSIAPAN (PJU) 10.641.870,00
C.2 PEKERJAAN TANAH (PJU) 1.512.053,99
C.3 PEKERJAAN BETON (PJU) 56.772.250,61
C.4 PEKERJAAN PLESTERAN (PJU) 3.959.896,75
C.5 PEKERJAAN PENGKABELAN (PJU) 534.853.500,00
C.6 PEKERJAAN JASA INSTALASI (PJU) 60.306.000,00
TOTAL - C 668.045.571,35
D PEKERJAAN TIANG BENDERA
D.1 PEKERJAAN PERSIAPAN (tiang bendera) 306.601,50
D.2 PEKERJAAN TANAH (tiang bendera) 1.916.294,09
D.3 PEKERJAAN BETON (tiang bendera) 17.841.707,49
D.4 PEKERJAAN DINDING PASANGAN (tiang bendera) 1.466.909,09
D.5 PEKERJAAN PLESTERAN (tiang bendera) 1.414.248,84
D.6 PEKERJAAN PENUTUP LANTAI (tiang bendera) 63.513.838,46
D.7 PEKERJAAN PENGECATAN (tiang bendera) 1.113.708,19
TOTAL - D 87.573.307,65
E PEKERJAAN HIDRANT
E.1 PEKERJAAN PERSIAPAN (hidrant) 10.641.870,00
E.2 PEKERJAAN TANAH (hidrant) 12.844.656,82
E.3 PEKERJAAN BETON (hidrant) 3.529.625,01
E.4 PEKERJAAN PLESTERAN (hidrant) 1.697.098,61
E.5 PEKERJAAN INSTALASI (hidrant) 435.174.375,00
TOTAL - E 463.887.625,44
NO. PEKERJAAN HARGA
F PEKERJAAN PAGAR DEPAN
F.1 PEKERJAAN PERSIAPAN (pagar) 19.608.092,25
F.2 PEKERJAAN TANAH (pagar) 30.941.612,72
F.3 PEKERJAAN SIRING (pagar) 143.851.279,21
F.4 PEKERJAAN BETON (pagar) 140.002.560,54
F.5 PEKERJAAN DINDING PASANGAN (pagar) 640.664.367,96
F.6 PEKERJAAN PLESTERAN (pagar) 108.982.458,48
F.7 PEKERJAAN PENGECATAN (pagar) 36.562.741,20
TOTAL - F 1.120.613.112,37
G PEKERJAAN GERBANG DAN POS JAGA
G.1 PEKERJAAN PERSIAPAN (gerbang dan pos jaga) 10.641.870,00
G.2 PEKERJAAN TANAH (gerbang dan pos jaga) 6.376.392,05
G.3 PEKERJAAN BETON (gerbang dan pos jaga) 175.165.514,36
G.4 PEKERJAAN DINDING PASANGAN (gerbang dan pos jaga) 22.003.636,32
G.5 PEKERJAAN PENUTUP LANTAI DAN DINDING (gerbang dan pos jaga) 89.746.138,38
G.6 PEKERJAAN PLESTERAN (gerbang dan pos jaga) 33.941.972,16
G.7 PEKERJAAN SANITASI GEDUNG (gerbang dan pos jaga) 40.601.559,60
G.8 PEKERJAAN PENGECATAN (gerbang dan pos jaga) 10.789.005,60
G.9 PEKERJAAN ELEKTRIKAL (gerbang dan pos jaga) 3.831.708,00
G.10 PEKERJAAN PINTU JENDELA (gerbang dan pos jaga) 6.102.021,02
TOTAL - G 399.199.817,50
H PEKERJAAN PENERANGAN FASADE BANGUNAN
H.1 PEKERJAAN PERSIAPAN (penerangan fasade) 670.450,00
H.2 PEKERJAAN PENGKABELAN DAN LAMPU (penerangan fasade) 302.139.500,00
H.3 PEKERJAAN JASA INSTALASI (penerangan fasade) 49.967.500,00
TOTAL - H 352.777.450,00
TOTAL 8.017.692.220,29
PPN 10% 801.769.222,03
TOTAL + PPN 10% 8.819.461.442,31
PEMBULATAN 8.819.461.440,00
REKAPITULASI BIAYA KONSTRUKSI
BIAYA KONTRUKSI FISIK 8.819.461.440,00
BIAYA PERENCANAAN 301.771.679,21
BIAYA PENGAWASAN 209.363.560,27
BIAYA PENGELOLAAN 184.227.559,33
9.514.824.238,82
PEMBULATAN 9.515.000.000,00
TERBILANG : ## SEMBILAN MILYAR LIMA RATUS LIMA BELAS JUTA RUPIAH##
USULAN RENCANA ANGGARAN BIAYA
(RAB)
PROGRAM : PENINGKATAN SARANA DAN PRASARANA IBADAH
KEGIATAN : PEMBANGUNAN SARANA DAN PRASARANA IBADAH HAJI
PEKERJAAN : PEKERJAAN DRAINASE DAN JALAN
PEKERJAAN LANDSCAPE
PEKERJAAN PENERANGAN DAN LAMPU JALAN
PEKERJAAN TIANG BENDERA
PEKERJAAN HIDRANT
PEKERJAAN PAGAR DEPAN
PEKERJAAN GERBANG DAN POS JAGA
PEKERJAAN PENERANGAN FASADE BANGUNAN
LOKASI : ASRAMA HAJI PALANGKA RAYA - KALIMANTAN TENGAH
TAHUN : 2019

NO. URAIAN PEKERJAAN ANALISA VOLUME SATUAN HARGA SATUAN (RP) JMLH HARGA (RP)

A PEKERJAAN DRAINASE DAN JALAN A


A.1 PEKERJAAN PERSIAPAN
1 Pengukuran dan pemasangan 1 m’ Bouwplank A.2.2.1.4 450,00 M1 24.497,88 11.024.043,75
2 Pembuatan gudang dan peralatan A.2.2.1.6 24,00 M2 886.822,50 21.283.740,00
3 Pembersihan lapangan dan perataan A.2.2.1.8 3.685,75 M2 350,75 1.292.776,81
JUMLAH A.1 33.600.560,56

A.2 PEKERJAAN TANAH


1 Penggalian tanah Siring batu & Saluran A.2.3.1.1 582,35 M3 83.806,25 48.804.569,69
2 Pengurugan kembali galian tanah A.2.3.1.9 58,97 M3 27.935,42 1.647.351,75
3 Pemadatan tanah ( per 20 cm) A.2.3.1.10 552,86 M3 64.112,50 35.445.236,75
4 Pengurugan dengan pasir urug A.2.3.1.11 552,86 M3 125.568,50 69.421.800,91
JUMLAH A.2 155.318.959,09

A.3 PEKERJAAN SIRING


1 Pemasangan pondasi batu belah campuran 1SP : 4PP A.3.2.1.2 63,00 M3 1.091.767,45 68.781.349,35
JUMLAH A.3 68.781.349,35

A.4 PEKERJAAN BETON


1 Membuat lantai kerja A.4.1.1.4 39,09 M3 880.436,77 34.416.273,28
2 Membuat beton Saluran A.4.1.1.7 193,22 M3 1.126.514,40 217.665.112,56
3 Pembesian Saluran dengan besi polos A.4.1.1.17 13.159,41 Kg 23.839,96 313.719.808,02
4 Pemasangan bekisting untuk lantai A.4.1.1.24 32,00 M2 384.220,75 12.295.064,00
5 Pemasangan bekisting untuk dinding A.4.1.1.25 483,09 M2 374.445,75 180.890.997,37
JUMLAH A.4 758.987.255,23

A.5 PEKERJAAN PLESTERAN


1 Pekerjaan plesteran 1SP : 2PP tebal 15 mm A.4.4.2.2 129,40 M2 74.441,57 9.632.739,16
2 Pemasangan finishing siar pasangan batu kali, campuran 1SP : 2PP A.4.4.2.26 300,00 M2 68.305,17 20.491.551,00
3 Pasangan acian A.4.4.2.27 32,35 M2 43.412,50 1.404.394,38
JUMLAH A.5 31.528.684,53

A.6 PEKERJAAN PENGECATAN


1 Pengecatan tembok baru ( 1lapis plamuur, 1 lapis cat dasar, 2 lapis cat penutup) A.4.7.1.10 37,50 M2 24.974,55 936.545,63
JUMLAH A.6 936.545,63

A.7 PEKERJAAN SANITASI GEDUNG


1 Pemasangan pipa PVC tipe AW Ø 2” A.5.1.1.29 150,00 M1 85.928,00 12.889.200,00
JUMLAH A.7 12.889.200,00

A.8 PEKERJAAN ASPAL


1 Perkerasan Agregat Kelas A Analisa EI.421 3.215,62 M2 155.057,87 498.607.186,32
2 Perkerasan Agregat Kelas B Analisa EI.422 482,34 M3 3.759.749,96 1.813.477.794,98
3 Lapisan aspal pengikat Tack Coat 96,47 M2 15.813,20 1.525.499,55
JUMLAH A.8 2.313.610.480,85
TOTAL JUMLAH A 3.375.653.035,25

B PEKERJAAN LANDSCAPE B
B.1 PEKERJAAN PERSIAPAN (landscape)
1 Pembuatan gudang semen dan peralatan (landscape) A.2.2.1.6 12,00 M2 886.822,50 10.641.870,00
2 Pembersihan lapangan dan perataan (landscape) A.2.2.1.8 4.850,00 M2 350,75 1.701.137,50
TOTAL B.1 12.343.007,50

B.2 PEKERJAAN TANAH (landscape)


1 Penggalian tanah biasa sedalam 1 m (landscape) A.2.3.1.1 54,00 M3 83.806,25 4.525.537,50
2 Pengurugan kembali galian tanah (landscape) A.2.3.1.9 54,00 M3 27.935,42 1.508.512,71
3 Pengurugan dengan pasir urug (landscape) A.2.3.1.11 111,75 M3 125.568,50 14.032.279,88
4 Pengurugan dengan tanah subur (landscape) A.2.3.1.11.a 990,40 M3 257.772,50 255.297.884,00
TOTAL B.2 275.364.214,08

B.3 PEKERJAAN PENUTUP LANTAI DAN PENUTUP DINDING (landscape)


1 Pemasangan paving block (landscape) LS-paving block 2.235,00 M2 150.998,45 337.481.535,75
2 Pemasangan grass block (landscape) LS-grass block 848,00 M2 130.873,45 110.980.685,60
3 Pemasangan batu sikat (landscape) LS-batu sikat 143,00 M2 316.691,60 45.286.898,80
TOTAL B.3 493.749.120,15

B.4 PEKERJAAN PENGECATAN (landscape)


1 Pengecatan tembok baru ( 1lapis plamuur, 1 lapis cat dasar, 2 lapis cat penutup) (landscape) A.4.7.1.10 1.117,50 M2 24.974,55 27.909.059,63
TOTAL B.4 27.909.059,63
NO. URAIAN PEKERJAAN ANALISA VOLUME SATUAN HARGA SATUAN (RP) JMLH HARGA (RP)

B.5 PEKERJAAN SANITASI GEDUNG (landscape)


1 Pemasangan pipa PVC tipe AW Ø 3/4” (landscape) A.5.1.1.26 250,00 M1 31.097,44 7.774.359,38
2 Pemasangan pipa PVC tipe AW Ø 1” (landscape) A.5.1.1.27 100,00 M1 35.598,25 3.559.825,00
3 Pemasangan 1 buah kran diameter ½” atau 3/4” (landscape) A.5.1.1.35 6,00 Buah 271.773,75 1.630.642,50
4 Pemasangan 1 buah stop kran Ø 1" (landscape) A.5.1.1.35.a 2,00 Buah 237.273,75 474.547,50
TOTAL B.5 13.439.374,38

B.6 PEKERJAAN VEGETASI (landscape)


1 Penanaman rumput gajah mini (landscape) V-gajah mini 4.740,00 M2 107.122,50 507.760.650,00
2 Penanaman pucuk merah (landscape) V-pucuk merah 50,00 Batang 234.772,50 11.738.625,00
3 Penanaman trembesi (landscape) V-trembesi 50,00 Batang 165.772,50 8.288.625,00
4 Penanaman ketapang kencana (landscape) V-ketapang kencana 50,00 Batang 579.772,50 28.988.625,00
5 Penanaman sawo kecik (landscape) V-sawo kecik 50,00 Batang 407.272,50 20.363.625,00
6 Penanaman tebubaya (landscape) V-tebubaya 50,00 Batang 476.272,50 23.813.625,00
7 Penanaman Bunga Rombusa Mini (Silver) (landscape) V-rombusa mini (silver) 500,00 Polibag 79.522,50 39.761.250,00
8 Penanaman Bunga Rombusa Mini (landscape) V-rombusa mini 500,00 Polibag 86.422,50 43.211.250,00
9 Penanaman Teh-tehan (landscape) V-teh tehan 500,00 Polibag 86.422,50 43.211.250,00
TOTAL B.6 727.137.525,00

C PEKERJAAN PENERANGAN DAN LAMPU JALAN C


C.1 PEKERJAAN PERSIAPAN (PJU)
1 Pembuatan gudang dan peralatan (PJU) A.2.2.1.6 12,00 M2 886.822,50 10.641.870,00
TOTAL C.1 10.641.870,00

C.2 PEKERJAAN TANAH (PJU)


1 Penggalian tanah biasa sedalam 1 m (PJU) A.2.3.1.1 13,00 M3 83.806,25 1.089.481,25
2 Pengurugan kembali galian tanah (PJU) A.2.3.1.9 12,25 M3 27.935,42 342.208,90
3 Pengurugan dengan pasir urug (PJU) A.2.3.1.11 0,64 M3 125.568,50 80.363,84
TOTAL C.2 1.512.053,99

C.3 PEKERJAAN BETON (PJU)


1 Membuat lantai kerja beton mutu f’c = 7,4 MPa (K 100),
slump (3-6) cm, w/c = 0,87 (PJU) A.4.1.1.4 1,54 M3 880.436,77 1.355.872,62
2 Membuat beton mutu f’c = 19,3 MPa (K 225), slump (12 ± 2) cm, w/c = 0,58 (PJU) A.4.1.1.7 8,81 M3 1.126.514,40 9.924.591,87
3 Pembesian dengan besi polos atau besi ulir (PJU) A.4.1.1.17 1.321,20 Kg 23.839,96 31.497.355,15
4 Pemasangan bekisting untuk pondasi (PJU) A.4.1.1.20 23,04 M2 147.700,25 3.403.013,76
5 Pemasangan bekisting untuk kolom (PJU) A.4.1.1.22 33,60 M2 315.220,75 10.591.417,20
TOTAL C.3 56.772.250,61

C.4 PEKERJAAN PLESTERAN (PJU)


1 Pemasangan plesteran 1SP : 2PP tebal 15 mm (PJU) A.4.4.2.2 33,60 M2 74.441,57 2.501.236,75
2 Pemasangan acian (PJU) A.4.4.2.27 33,60 M2 43.412,50 1.458.660,00
TOTAL C.4 3.959.896,75

C.5 PEKERJAAN PENGKABELAN (PJU)


1 Kabel NYY 2x 4mm (PJU) LS-Kabel NYY 2x 4mm 600,00 M1 17.250,00 10.350.000,00
2 Box Terminal MCB 10x15x20+ konektor+klem (PJU) LS-Box Terminal 24,00 Unit 408.250,00 9.798.000,00
3 MCB 2 dan 4 A (PJU) LS-MCB 2 dan 4 A 24,00 Buah 74.750,00 1.794.000,00
4 Ancoor Ø 12 mm panjang 50 cm (PJU) LS-Ancoor Ø 12 mm 96,00 Buah 138.000,00 13.248.000,00
5 Lampu PJU 1 Lengan (PJU) LS-Lampu PJU 1 Lengan 12,00 Buah 12.144.000,00 145.728.000,00
6 Lampu PJU 4 Lengan (PJU) LS-Lampu PJU 4 Lengan 12,00 Buah 14.544.625,00 174.535.500,00
7 Lampu PJU 28 w FER 101 (PJU) LS-Lampu PJU 28 w FER 101 24,00 Buah 7.475.000,00 179.400.000,00
TOTAL C.5 534.853.500,00

C.6 PEKERJAAN JASA INSTALASI (PJU)


1 Jasa pemasangan Kabel NYY 2 x 4mm (PJU) LS-jasa Kabel NYY 2x 4mm 600,00 M1 40.250,00 24.150.000,00
2 Jasa pemasangan Box Terminal MCB 10x15x20+ konektor+klem (PJU) LS-jasa Box Terminal 24,00 Buah 115.000,00 2.760.000,00
3 Jasa pemasangan MCB 2 dan 4 A (PJU) LS-jasa MCB 2 dan 4 A 24,00 Buah 115.000,00 2.760.000,00
4 Jasa pemasangan ancoor Ø 12 mm panjang 50 cm (PJU) LS-jasa Ancoor Ø 12 mm 96,00 Buah 57.500,00 5.520.000,00
5 Jasa pemasangan Lampu PJU 1 Lengan (PJU) LS-jasa Lampu PJU 1 Lengan 12,00 Buah 402.500,00 4.830.000,00
6 Jasa pemasangan Lampu PJU 4 Lengan (PJU) LS-jasa Lampu PJU 4 Lengan 12,00 Buah 1.610.000,00 19.320.000,00
7 Jasa pemasangan Lampu PJU 28 w FER 101 (PJU) LS-jasa Lampu PJU 28 w FER 101 24,00 Buah 40.250,00 966.000,00
TOTAL C.6 60.306.000,00

D PEKERJAAN TIANG BENDERA D


D.1 PEKERJAAN PERSIAPAN (tiang bendera)
1 Pengukuran dan pemasangan 1 m’ Bouwplank (tiang bendera) A.2.2.1.4 12,00 M1 24.497,88 293.974,50
2 Pembersihan lapangan dan perataan (tiang bendera) A.2.2.1.8 36,00 M2 350,75 12.627,00
TOTAL D.1 306.601,50

D.2 PEKERJAAN TANAH (tiang bendera)


1 Penggalian tanah biasa sedalam 2 m (tiang bendera) A.2.3.1.2 8,00 M3 156.414,38 1.251.315,00
2 Pengurugan kembali galian tanah (tiang bendera) A.2.3.1.9 6,40 M3 27.935,42 178.786,69
3 Pemadatan tanah ( per 20 cm) (tiang bendera) A.2.3.1.10 6,80 M3 64.112,50 435.965,00
4 Pengurugan dengan pasir urug (tiang bendera) A.2.3.1.11 0,40 M3 125.568,50 50.227,40
TOTAL D.2 1.916.294,09

D.3 PEKERJAAN BETON (tiang bendera)


1 Membuat lantai kerja beton mutu f’c = 7,4 MPa (K 100),
slump (3-6) cm, w/c = 0,87 (tiang bendera) A.4.1.1.4 0,80 M3 880.436,77 704.349,41
2 Membuat beton mutu f’c = 19,3 MPa (K 225), slump (12 ± 2) cm, w/c = 0,58 (tiang bendera) A.4.1.1.7 3,74 M3 1.126.514,40 4.213.163,86
3 Pembesian dengan besi polos atau besi ulir (tiang bendera) A.4.1.1.17 240,00 Kg 23.839,96 5.721.590,40
4 Pemasangan bekisting untuk pondasi (tiang bendera) A.4.1.1.20 3,20 M2 147.700,25 472.640,80
5 Pemasangan bekisting untuk kolom (tiang bendera) A.4.1.1.22 21,35 M2 315.220,75 6.729.963,01
TOTAL D.3 17.841.707,49
NO. URAIAN PEKERJAAN ANALISA VOLUME SATUAN HARGA SATUAN (RP) JMLH HARGA (RP)

D.4 PEKERJAAN DINDING PASANGAN (tiang bendera)


1 Pemasangan dinding bata merah (5x11x22) cm tebal ½ batu campuran 1SP : 2PP (tiang bendera) A.4.4.1.7 9,60 M2 152.803,03 1.466.909,09
TOTAL D.4 1.466.909,09

D.5 PEKERJAAN PLESTERAN (tiang bendera)


1 Pemasangan plesteran 1SP : 2PP tebal 15 mm (tiang bendera) A.4.4.2.2 12,00 M2 74.441,57 893.298,84
2 Pemasangan acian (tiang bendera) A.4.4.2.27 12,00 M2 43.412,50 520.950,00
TOTAL D.5 1.414.248,84

D.6 PEKERJAAN PENUTUP LANTAI (tiang bendera)


1 Pemasangan lantai ubin granit ukuran 40cm x40cm (tiang bendera) A.4.4.3.9 20,25 M2 3.136.485,85 63.513.838,46
TOTAL D.6 63.513.838,46

D.7 PEKERJAAN PENGECATAN (tiang bendera)


1 Pengecatan bidang kayu baru (1 lapis plamuur, 1 lapis cat dasar, 2 lapis cat penutup) (tiang bendera) A.4.7.1.4 21,35 M2 38.127,10 814.013,59
2 Pengecatan tembok baru ( 1lapis plamuur, 1 lapis cat dasar, 2 lapis cat penutup) (tiang bendera) A.4.7.1.10 12,00 M2 24.974,55 299.694,60
TOTAL D.7 1.113.708,19

E PEKERJAAN HIDRANT E
E.1 PEKERJAAN PERSIAPAN (hidrant)
1 Pembuatan gudang semen dan peralatan (hidrant) A.2.2.1.6 12,00 M2 886.822,50 10.641.870,00
TOTAL E.1 10.641.870,00

E.2 PEKERJAAN TANAH (hidrant)


1 Penggalian tanah biasa sedalam 1 m (hidrant) A.2.3.1.1 80,00 M3 83.806,25 6.704.500,00
2 Pengurugan kembali galian tanah (hidrant) A.2.3.1.9 40,00 M3 27.935,42 1.117.416,82
3 Pengurugan dengan pasir urug (hidrant) A.2.3.1.11 40,00 M3 125.568,50 5.022.740,00
TOTAL E.2 12.844.656,82

E.3 PEKERJAAN BETON (hidrant)


1 Membuat lantai kerja beton mutu f’c = 7,4 MPa (K 100),
slump (3-6) cm, w/c = 0,87 (hidrant) A.4.1.1.4 0,30 M3 880.436,77 264.131,03
2 Membuat beton mutu f’c = 19,3 MPa (K 225), slump (12 ± 2) cm, w/c = 0,58 (hidrant) A.4.1.1.7 0,77 M3 1.126.514,40 867.416,09
3 Pembesian dengan besi polos atau besi ulir (hidrant) A.4.1.1.17 76,80 Kg 23.839,96 1.830.908,93
4 Pemasangan bekisting untuk pondasi (hidrant) A.4.1.1.20 3,84 M2 147.700,25 567.168,96
TOTAL E.3 3.529.625,01

E.4 PEKERJAAN PLESTERAN (hidrant)


1 Pemasangan plesteran 1SP : 2PP tebal 15 mm (hidrant) A.4.4.2.2 14,40 M2 74.441,57 1.071.958,61
2 Pemasangan acian (hidrant) A.4.4.2.27 14,40 M2 43.412,50 625.140,00
TOTAL E.4 1.697.098,61

E.5 PEKERJAAN INSTALASI (hidrant)


1 Pilar hidrant two ways (hidrant) LS-Pilar hidrant two ways 3,00 Buah 8.652.600,00 25.957.800,00
2 Selang gulung (hidrant) LS-Selang gulung 8,00 Buah 3.544.875,00 28.359.000,00
3 Nozzle (hidrant) LS-Nozzle 8,00 Buah 1.173.000,00 9.384.000,00
4 Pipa kembar siam (hidrant) LS-Pipa kembar siam 2,00 Buah 5.654.550,00 11.309.100,00
5 Pemasangan pipa PVC Ø 300 mm (hidrant) LS-Pemasangan pipa PVC Ø 300 mm 500,00 Buah 603.750,00 301.875.000,00
6 Taper konsentris 12"-6" (hidrant) LS-Taper konsentris 12"-6" 1,00 Buah 900.450,00 900.450,00
7 Akhir pipa 12" (hidrant) LS-Akhir pipa 12" 4,00 Buah 1.288.575,00 5.154.300,00
8 Horizontal bend 90" (hidrant) LS-Horizontal bend 90" 2,00 Buah 1.466.250,00 2.932.500,00
9 Horizontal bend 45" (hidrant) LS-Horizontal bend 45" 2,00 Buah 1.380.000,00 2.760.000,00
10 Tee all flange 12"x3 (hidrant) LS-Tee all flange 12"x3 1,00 Buah 3.053.250,00 3.053.250,00
11 Check valve 12" (arrow) (hidrant) LS-Check valve 12" (arrow) 4,00 Buah 9.513.375,00 38.053.500,00
12 Reducer 12"-6" (hidrant) LS-Reducer 12"-6" 1,00 Buah 181.125,00 181.125,00
13 Reducer 6"-4" (hidrant) LS-Reducer 6"-4" 1,00 Buah 79.350,00 79.350,00
14 Reducer 4"-2" (hidrant) LS-Reducer 4"-2" 1,00 Buah 5.175.000,00 5.175.000,00
TOTAL E.5 435.174.375,00

F PEKERJAAN PAGAR DEPAN F


F.1 PEKERJAAN PERSIAPAN (pagar)
1 Pengukuran dan pemasangan 1 m’ Bouwplank (pagar) A.2.2.1.4 366,00 M1 24.497,88 8.966.222,25
2 Pembuatan gudang semen dan peralatan (pagar) A.2.2.1.6 12,00 M2 886.822,50 10.641.870,00
TOTAL F.1 19.608.092,25

F.2 PEKERJAAN TANAH (pagar)


1 Penggalian tanah biasa sedalam 1 m (pagar) A.2.3.1.1 292,80 M3 83.806,25 24.538.470,00
2 Pengurugan kembali galian tanah (pagar) A.2.3.1.9 97,60 M3 27.935,42 2.726.497,04
3 Pengurugan dengan pasir urug (pagar) A.2.3.1.11 29,28 M3 125.568,50 3.676.645,68
TOTAL F.2 30.941.612,72

F.3 PEKERJAAN SIRING (pagar)


1 Pemasangan pondasi batu belah campuran 1SP : 4PP (pagar) A.3.2.1.2 131,76 M3 1.091.767,45 143.851.279,21
TOTAL F.3 143.851.279,21

F.4 PEKERJAAN BETON (pagar)


1 Membuat lantai kerja beton mutu f’c = 7,4 MPa (K 100),
slump (3-6) cm, w/c = 0,87 (pagar) A.4.1.1.4 6,40 M3 880.436,77 5.634.795,32
2 Membuat beton mutu f’c = 19,3 MPa (K 225), slump (12 ± 2) cm, w/c = 0,58 (pagar) A.4.1.1.7 32,93 M3 1.126.514,40 37.096.119,22
3 Pembesian dengan besi polos atau besi ulir (pagar) A.4.1.1.17 2.680,00 Kg 23.839,96 63.891.092,80
4 Pemasangan bekisting untuk pondasi (pagar) A.4.1.1.20 32,00 M2 147.700,25 4.726.408,00
5 Pemasangan bekisting untuk sloof (pagar) A.4.1.1.21 183,00 M2 153.824,00 28.149.792,00
6 Pemasangan bekisting untuk kolom (pagar) A.4.1.1.22 1,60 M2 315.220,75 504.353,20
TOTAL F.4 140.002.560,54

F.5 PEKERJAAN DINDING PASANGAN (pagar)


1 Pemasangan dinding bata merah (5x11x22) cm tebal ½ batu campuran 1SP : 2PP (pagar) A.4.4.1.7 732,00 M2 152.803,03 111.851.817,96
2 Pemasangan pagar besi (pagar) LS-pagar besi 540,00 M2 979.282,50 528.812.550,00
NO. URAIAN PEKERJAAN ANALISA VOLUME SATUAN HARGA SATUAN (RP) JMLH HARGA (RP)

TOTAL F.5 640.664.367,96

F.6 PEKERJAAN PLESTERAN (pagar)


1 Pekerjaan plesteran 1SP : 2PP tebal 15 mm (pagar) A.4.4.2.2 1.464,00 M2 74.441,57 108.982.458,48
TOTAL F.6 108.982.458,48

F.7 PEKERJAAN PENGECATAN (pagar)


1 Pengecatan tembok baru ( 1lapis plamuur, 1 lapis cat dasar, 2 lapis cat penutup) (pagar) A.4.7.1.10 1.464,00 M2 24.974,55 36.562.741,20
TOTAL F.7 36.562.741,20

G PEKERJAAN GERBANG DAN POS JAGA G


G.1 PEKERJAAN PERSIAPAN (gerbang dan pos jaga)
1 Pembuatan gudang semen dan peralatan (gerbang dan pos jaga) A.2.2.1.6 12,00 M2 886.822,50 10.641.870,00
TOTAL G.1 10.641.870,00

G.2 PEKERJAAN TANAH (gerbang dan pos jaga)


1 Penggalian tanah biasa sedalam 1 m (gerbang dan pos jaga) A.2.3.1.1 25,60 M3 83.806,25 2.145.440,00
2 Pengurugan kembali galian tanah (gerbang dan pos jaga) A.2.3.1.9 22,00 M3 27.935,42 614.579,25
3 Pengurugan dengan pasir urug (gerbang dan pos jaga) A.2.3.1.11 28,80 M3 125.568,50 3.616.372,80
TOTAL G.2 6.376.392,05

G.3 PEKERJAAN BETON (gerbang dan pos jaga)


1 Membuat lantai kerja beton mutu f’c = 7,4 MPa (K 100),
slump (3-6) cm, w/c = 0,87 (gerbang dan pos jaga) A.4.1.1.4 7,20 M3 880.436,77 6.339.144,73
2 Membuat beton mutu f’c = 19,3 MPa (K 225), slump (12 ± 2) cm, w/c = 0,58 (gerbang dan pos jaga) A.4.1.1.7 23,04 M3 1.126.514,40 25.954.891,80
3 Pembesian dengan besi polos atau besi ulir (gerbang dan pos jaga) A.4.1.1.17 2.869,20 Kg 23.839,96 68.401.613,23
4 Pemasangan bekisting untuk pondasi (gerbang dan pos jaga) A.4.1.1.20 2,40 M2 147.700,25 354.480,60
5 Pemasangan bekisting untuk sloof (gerbang dan pos jaga) A.4.1.1.21 19,20 M2 153.824,00 2.953.420,80
6 Pemasangan bekisting untuk kolom (gerbang dan pos jaga) A.4.1.1.22 57,60 M2 315.220,75 18.156.715,20
7 Pemasangan bekisting untuk balok (gerbang dan pos jaga) A.4.1.1.23 36,00 M2 319.705,75 11.509.407,00
8 Pemasangan bekisting untuk lantai (gerbang dan pos jaga) A.4.1.1.24 108,00 M2 384.220,75 41.495.841,00
TOTAL G.3 175.165.514,36

G.4 PEKERJAAN DINDING PASANGAN (gerbang dan pos jaga)


1 Pemasangan dinding bata merah (5x11x22) cm tebal ½ batu campuran 1SP : 2PP (gerbang dan pos jaga) A.4.4.1.7 144,00 M2 152.803,03 22.003.636,32
TOTAL G.4 22.003.636,32

G.5 PEKERJAAN PENUTUP LANTAI DAN DINDING (gerbang dan pos jaga)
1 Pemasangan lantai keramik ukuran 40cm x 40cm (gerbang dan pos jaga) A.4.4.3.34.a 48,00 M2 394.081,31 18.915.902,88
2 Pemasangan dinding keramik 40cm x 40cm (gerbang dan pos jaga) A.4.4.3.54 66,00 M2 436.821,75 28.830.235,50
3 Pemasangan ornamen ukiran dinding (gerbang dan pos jaga) LS.ornamen 2,00 Buah 12.000.000,00 24.000.000,00
4 Pemasangan font stainless (gerbang dan pos jaga) LS.font stainless 1.200,00 Cm 15.000,00 18.000.000,00
TOTAL G.5 89.746.138,38

G.6 PEKERJAAN PLESTERAN (gerbang dan pos jaga)


1 Pemasangan plesteran 1SP : 2PP tebal 15 mm (gerbang dan pos jaga) A.4.4.2.2 288,00 M2 74.441,57 21.439.172,16
2 Pemasangan acian (gerbang dan pos jaga) A.4.4.2.27 288,00 M2 43.412,50 12.502.800,00
TOTAL G.6 33.941.972,16

G.7 PEKERJAAN SANITASI GEDUNG (gerbang dan pos jaga)


1 Pemasangan pipa PVC tipe AW Ø 3/4” (gerbang dan pos jaga) A.5.1.1.26 36,00 M1 31.097,44 1.119.507,75
2 Pemasangan pipa PVC tipe AW Ø 1” (gerbang dan pos jaga) A.5.1.1.27 36,00 M1 35.598,25 1.281.537,00
3 Pemasangan pipa PVC tipe AW Ø 3” (gerbang dan pos jaga) A.5.1.1.29 24,00 M1 85.928,00 2.062.272,00
4 Pemasangan pipa PVC tipe AW Ø 4” (gerbang dan pos jaga) A.5.1.1.32 24,00 M1 143.509,65 3.444.231,60
5 Pemasangan kloset jongkok (gerbang dan pos jaga) A.5.1.1.2 3,00 Buah 561.227,60 1.683.682,80
6 Pemasangan 1 buah kran diameter ½” atau 3/4” (gerbang dan pos jaga) A.5.1.1.35 3,00 Buah 271.773,75 815.321,25
7 Pemasangan 1 buah floor drain (gerbang dan pos jaga) A.5.1.1.36 3,00 Buah 248.026,25 744.078,75
8 Pemasangan 1 buah bak mandi (gerbang dan pos jaga) A.5.1.1.7 3,00 Buah 1.414.702,40 4.244.107,20
9 Pemasangan 1 buah septic tank (gerbang dan pos jaga) LS-septic tank 3,00 Buah 8.165.000,00 24.495.000,00
10 Pemasangan 1 buah stop kran Ø 1" (gerbang dan pos jaga) A.5.1.1.35.a 3,00 Buah 237.273,75 711.821,25
TOTAL G.7 40.601.559,60

G.8 PEKERJAAN PENGECATAN (gerbang dan pos jaga)


1 Pengecatan tembok baru ( 1lapis plamuur, 1 lapis cat dasar, 2 lapis cat penutup) (gerbang dan pos jaga) A.4.7.1.10 432,00 M2 24.974,55 10.789.005,60
TOTAL G.8 10.789.005,60

G.9 PEKERJAAN ELEKTRIKAL (gerbang dan pos jaga)


1 Stop kontak + instalasi beton (gerbang dan pos jaga) M.001 3,00 Titik 88.320,00 264.960,00
2 Stop kontak antena (gerbang dan pos jaga) M.002 3,00 Titik 69.000,00 207.000,00
3 Schakelar (standar) (gerbang dan pos jaga) M.003 3,00 Titik 16.468,00 49.404,00
4 Lampu PL 14 watt + armatur down light 4" (gerbang dan pos jaga) M.004 9,00 Titik 193.200,00 1.738.800,00
5 Titik lampu + instalasi beton (gerbang dan pos jaga) M.005 9,00 Titik 174.616,00 1.571.544,00
TOTAL G.9 3.831.708,00

G.10 PEKERJAAN PINTU JENDELA (gerbang dan pos jaga)


1 Pembuatan pintu P-1 (gerbang dan pos jaga)
1.1 Membuat dan memasang kusen alumunium P-1 (gerbang dan pos jaga) A.4.2.1.11 9,00 M1 133.891,17 1.205.020,49
1.2 Membuat dan memasang daun pintu jendela kaca alumunium P-1 (gerbang dan pos jaga) A.4.2.1.13 4,20 M2 630.893,45 2.649.752,49
1.3 Memasang kaca - tebal 5 mm P-1 (gerbang dan pos jaga) A.4.6.2.17 2,70 M2 148.017,08 399.646,10
2 Pembuatan pintu J-1 (gerbang dan pos jaga)
2.1 Membuat dan memasang kusen alumunium J-1 (gerbang dan pos jaga) A.4.2.1.11 3,00 M1 133.891,17 401.673,50
2.2 Membuat dan memasang daun pintu jendela kaca alumunium J-1 (gerbang dan pos jaga) A.4.2.1.13 0,75 M2 630.893,45 473.170,09
2.3 Memasang kaca - tebal 5 mm J-1 (gerbang dan pos jaga) A.4.6.2.17 0,27 M2 148.017,08 39.964,61
2.4 Memasang engsel jendela J-1 (gerbang dan pos jaga) A.4.6.2.6 6,00 Buah 42.230,88 253.385,25
2.5 Memasang kunci selot jendela J-1 (gerbang dan pos jaga) A.4.6.2.11 3,00 Buah 44.993,75 134.981,25
2.6 Memasang pegangan jendela J-1 (gerbang dan pos jaga) A.4.6.2.12.a 3,00 Buah 94.438,00 283.314,00
2.7 Memasang kait angin J-1 (gerbang dan pos jaga) A.4.6.2.9 6,00 Buah 43.518,88 261.113,25
TOTAL G.10 6.102.021,02
NO. URAIAN PEKERJAAN ANALISA VOLUME SATUAN HARGA SATUAN (RP) JMLH HARGA (RP)

H PEKERJAAN PENERANGAN FASADE BANGUNAN H


H.1 PEKERJAAN PERSIAPAN (penerangan fasade)
1 Persiapan dan pembongkaran (penerangan fasade) LS-persiapan dan pembongkaran 1,00 M3 670.450,00 670.450,00
TOTAL H.1 670.450,00

H.2 PEKERJAAN PENGKABELAN DAN LAMPU (penerangan fasade)


1 Kabel NYY 2x 4mm (penerangan fasade) LS-Kabel NYY 2x 4mm 990,00 M1 17.250,00 17.077.500,00
2 Revisi Box panel (penerangan fasade) LS-revisi Box Terminal 2,00 LS 5.750.000,00 11.500.000,00
3 Pengaman lampu tipe 1 (penerangan fasade) LS-pengaman spotlight-1 8,00 LS 575.000,00 4.600.000,00
4 Lengan lampu tipe 2 (penerangan fasade) LS-lengan spotlight-2 11,00 LS 1.380.000,00 15.180.000,00
5 Lampu sorot tipe 1 (penerangan fasade) LS-spotlight-1 8,00 Buah 8.004.000,00 64.032.000,00
6 Lampu sorot tipe 2 (penerangan fasade) LS-spotlight-2 11,00 Buah 17.250.000,00 189.750.000,00
TOTAL H.2 302.139.500,00

H.3 PEKERJAAN JASA INSTALASI (penerangan fasade)


1 Jasa pemasangan Kabel NYY 2 x 4mm (penerangan fasade) LS-jasa Kabel NYY 2x 4mm 990,00 M1 40.250,00 39.847.500,00
2 Jasa revisi Box panel (penerangan fasade) LS-jasa revisi Box Terminal 2,00 Buah 1.380.000,00 2.760.000,00
3 Jasa pengaman lampu tipe 1 (penerangan fasade) LS-jasa pengaman spotlight-1 8,00 Buah 172.500,00 1.380.000,00
4 Jasa pemasangan lengan lampu tipe 2 (penerangan fasade) LS-jasa lengan spotlight-2 11,00 Buah 287.500,00 3.162.500,00
5 Jasa pemasangan lampu sorot tipe 1 (penerangan fasade) LS-jasa spotlight-1 8,00 Buah 115.000,00 920.000,00
6 Jasa pemasangan lampu sorot tipe 2 (penerangan fasade) LS-jasa spotlight-2 11,00 Buah 172.500,00 1.897.500,00
TOTAL H.3 49.967.500,00
DAFTAR ANALISA SNI
PEKERJAAN PERSIAPAN
A.2.2.1.4 Pengukuran dan pemasangan 1 m’ Bouwplank Satuan M1
No. Uraian Kode Satuan Koef Hrg Sat (Rp) Jmlh Hrg (Rp)
1 TENAGA
Pembantu tukang kayu L.12 Orang/hari 0,0500 80.000,00 4.000,00
Tukang kayu L.07 Orang/hari 0,0500 120.000,00 6.000,00
Kepala tukang kayu L.03 Orang/hari 0,0050 157.500,00 787,50
Mandor L.01 Orang/hari 0,0050 215.000,00 1.075,00
Jumlah- 1
......................................................................................... 11.862,50
2 BAHAN
Balok kayu kelas III K-1 M3 0,0040 1.300.000,00 5.200,00
Paku kayu D-5 Kg 0,0200 12.000,00 240,00
Papan kayu kelas III K-4 M3 0,0040 1.000.000,00 4.000,00
Jumlah- 2
......................................................................................... 9.440,00
3 PERALATAN
Jumlah- 3
......................................................................................... -
4 JUMLAH (1+2+3) 21.302,50
5 OVERHEAD + KEUNTUNGAN J-1 15% x Jumlah 4 3.195,38
6 HARGA SATUAN PEKERJAAN (4+5) 24.497,88

A.2.2.1.6 Pembuatan gudang semen dan peralatan Satuan M2


No. Uraian Kode Satuan Koef Hrg Sat (Rp) Jmlh Hrg (Rp)
1 TENAGA
Pembantu tukang batu L.11 Orang/hari 1,0000 90.000,00 90.000,00
Tukang kayu L.07 Orang/hari 2,0000 120.000,00 240.000,00
Kepala tukang batu L.02 Orang/hari 0,2000 170.000,00 34.000,00
Mandor L.01 Orang/hari 0,0500 215.000,00 10.750,00
Jumlah- 1
......................................................................................... 374.750,00
2 BAHAN
Dolken kayu φ 8-10/400 cm
8-10/400 cm K-3 Batang 1,7000 15.000,00 25.500,00
Balok kayu kelas III K-1 M3 0,2100 1.300.000,00 273.000,00
Paku kayu D-5 Kg 0,3000 12.000,00 3.600,00
Semen portland C-2 Kg - 1.200,00 -
Pasir beton B-4 M3 - 116.700,00 -
Batu pecah 2-3 cm B-3 M3 - 350.000,00 -
Seng gelombang D-3 Lbr 0,8333 75.000,00 62.500,00
Seng plat D-4 M1 1,2000 26.500,00 31.800,00
Jumlah- 2
......................................................................................... 396.400,00
3 PERALATAN
Jumlah- 3
......................................................................................... -
4 JUMLAH (1+2+3) 771.150,00
5 OVERHEAD + KEUNTUNGAN J-1 15% x Jumlah 4 115.672,50
6 HARGA SATUAN PEKERJAAN (4+5) 886.822,50

A.2.2.1.8 Pembersihan lapangan dan perataan Satuan M2


No. Uraian Kode Satuan Koef Hrg Sat (Rp) Jmlh Hrg (Rp)
1 TENAGA
Pembantu tukang batu L.11 Orang/hari 0,0010 90.000,00 90,00
Mandor L.01 Orang/hari 0,0010 215.000,00 215,00
Jumlah- 1
......................................................................................... 305,00
2 BAHAN
Jumlah- 2
......................................................................................... -
3 PERALATAN
Jumlah- 3
......................................................................................... -
4 JUMLAH (1+2+3) 305,00
5 OVERHEAD + KEUNTUNGAN 15% x Jumlah 4 45,75
6 HARGA SATUAN PEKERJAAN (4+5) 350,75
PEKERJAAN TANAH
A.2.3.1.1 Penggalian tanah biasa sedalam 1 m Satuan M3
No. Uraian Kode Satuan Koef Hrg Sat (Rp) Jmlh Hrg (Rp)
1 TENAGA
Pembantu tukang batu L.11 Orang/hari 0,7500 90.000,00 67.500,00
Mandor L.01 Orang/hari 0,0250 215.000,00 5.375,00
Jumlah- 1
......................................................................................... 72.875,00
2 BAHAN
Jumlah- 2
......................................................................................... -
3 PERALATAN
Jumlah- 3
......................................................................................... -
4 JUMLAH (1+2+3) 72.875,00
5 OVERHEAD + KEUNTUNGAN 15% x Jumlah 4 10.931,25
6 HARGA SATUAN PEKERJAAN (4+5) 83.806,25

A.2.3.1.2 Penggalian tanah biasa sedalam 2 m Satuan M3


No. Uraian Kode Satuan Koef Hrg Sat (Rp) Jmlh Hrg (Rp)
1 TENAGA
Pembantu tukang batu L.11 Orang/hari 0,9000 90.000,00 81.000,00
Mandor L.01 Orang/hari 0,0450 215.000,00 9.675,00
Jumlah- 1
......................................................................................... 90.675,00
2 BAHAN
Jumlah- 2
......................................................................................... -
3 PERALATAN
Jumlah- 3
......................................................................................... 90.675,00
4 JUMLAH (1+2+3) 136.012,50
5 OVERHEAD + KEUNTUNGAN 15% x Jumlah 4 20.401,88
6 HARGA SATUAN PEKERJAAN (4+5) 156.414,38

A.2.3.1.9 Pengurugan kembali galian tanah Satuan M3


No. Uraian Kode Satuan Koef Hrg Sat (Rp) Jmlh Hrg (Rp)
1 TENAGA
Pembantu tukang batu L.11 Orang/hari 0,2500 90.000,00 22.500,00
Mandor L.01 Orang/hari 0,0083 215.000,00 1.791,67
Jumlah- 1
......................................................................................... 24.291,67
2 BAHAN
Jumlah- 2
......................................................................................... -
3 PERALATAN
Jumlah- 3
......................................................................................... -
4 JUMLAH (1+2+3) 24.291,67
5 OVERHEAD + KEUNTUNGAN 15% x Jumlah 4 3.643,75
6 HARGA SATUAN PEKERJAAN (4+5) 27.935,42

A.2.3.1.10 Pemadatan tanah ( per 20 cm) Satuan M3


No. Uraian Kode Satuan Koef Hrg Sat (Rp) Jmlh Hrg (Rp)
1 TENAGA
Pembantu tukang batu L.11 Orang/hari 0,5000 90.000,00 45.000,00
Mandor L.01 Orang/hari 0,0500 215.000,00 10.750,00
Jumlah- 1
......................................................................................... 55.750,00
2 BAHAN
Jumlah- 2
......................................................................................... -
3 PERALATAN
Jumlah- 3
......................................................................................... -
4 JUMLAH (1+2+3) 55.750,00
5 OVERHEAD + KEUNTUNGAN 15% x Jumlah 4 8.362,50
6 HARGA SATUAN PEKERJAAN (4+5) 64.112,50
A.2.3.1.11 Pengurugan dengan pasir urug Satuan M3
No. Uraian Kode Satuan Koef Hrg Sat (Rp) Jmlh Hrg (Rp)
1 TENAGA
Pembantu tukang batu L.11 Orang/hari 0,3000 90.000,00 27.000,00
Mandor L.01 Orang/hari 0,0100 215.000,00 2.150,00
Jumlah- 1
......................................................................................... 29.150,00
2 BAHAN
Pasir Urug M3 1,2000 66.700,00 80.040,00
Jumlah- 2
......................................................................................... 80.040,00
3 PERALATAN
Jumlah- 3
......................................................................................... -
4 JUMLAH (1+2+3) 109.190,00
5 OVERHEAD + KEUNTUNGAN 15% x Jumlah 4 16.378,50
6 HARGA SATUAN PEKERJAAN (4+5) 125.568,50

A.2.3.1.11.a Pengurugan dengan tanah subur Satuan M3


No. Uraian Kode Satuan Koef Hrg Sat (Rp) Jmlh Hrg (Rp)
1 TENAGA
Pembantu tukang batu L.11 Orang/hari 0,3000 90.000,00 27.000,00
Mandor L.01 Orang/hari 0,0100 215.000,00 2.150,00
Jumlah- 1
......................................................................................... 29.150,00
2 BAHAN
Tanah subur M3 1,2000 162.500,00 195.000,00
Jumlah- 2
......................................................................................... 195.000,00
3 PERALATAN
Jumlah- 3
......................................................................................... -
4 JUMLAH (1+2+3) 224.150,00
5 OVERHEAD + KEUNTUNGAN 15% x Jumlah 4 33.622,50
6 HARGA SATUAN PEKERJAAN (4+5) 257.772,50

LS-persiapan dan pembongkaran


Persiapan dan pembongkaran Satuan M3
No. Uraian Kode Satuan Koef Hrg Sat (Rp) Jmlh Hrg (Rp)
1 TENAGA
Pembantu tukang batu L.11 Orang/hari 6,0000 90.000,00 540.000,00
Mandor L.01 Orang/hari 0,2000 215.000,00 43.000,00
Jumlah- 1
......................................................................................... 583.000,00
2 PERALATAN
Jumlah- 3
......................................................................................... -
3 JUMLAH (1+2+3) 583.000,00
4 OVERHEAD + KEUNTUNGAN 15% x Jumlah 4 87.450,00
5 HARGA SATUAN PEKERJAAN (4+5) 670.450,00

V-pucuk merah Penanaman pucuk merah Satuan Batang


No. Uraian Kode Satuan Koef Hrg Sat (Rp) Jmlh Hrg (Rp)
1 TENAGA
Pembantu tukang batu L.11 Orang/hari 0,3000 90.000,00 27.000,00
Mandor L.01 Orang/hari 0,0100 215.000,00 2.150,00
Jumlah- 1
......................................................................................... 29.150,00
2 BAHAN
Pupuk kandang Kantong 0,5000 50.000,00 25.000,00
Pucuk merah Batang 1,2000 250.000,00 300.000,00
Jumlah- 2
......................................................................................... 25.000,00
3 PERALATAN
Jumlah- 3
......................................................................................... -
4 JUMLAH (1+2+3) 204.150,00
5 OVERHEAD + KEUNTUNGAN 15% x Jumlah 4 30.622,50
6 HARGA SATUAN PEKERJAAN (4+5) 234.772,50
V-sawo kecik Penanaman sawo kecik Satuan Batang
No. Uraian Kode Satuan Koef Hrg Sat (Rp) Jmlh Hrg (Rp)
1 TENAGA
Pembantu tukang batu L.11 Orang/hari 0,3000 90.000,00 27.000,00
Mandor L.01 Orang/hari 0,0100 215.000,00 2.150,00
Jumlah- 1
......................................................................................... 29.150,00
2 BAHAN
Pupuk kandang Kantong 0,5000 50.000,00 25.000,00
Sawo kecik Batang 1,2000 500.000,00 600.000,00
Jumlah- 2
......................................................................................... 25.000,00
3 PERALATAN
Jumlah- 3
......................................................................................... -
4 JUMLAH (1+2+3) 354.150,00
5 OVERHEAD + KEUNTUNGAN 15% x Jumlah 4 53.122,50
6 HARGA SATUAN PEKERJAAN (4+5) 407.272,50

V-ketapang kencanaPenanaman ketapang kencana Satuan Batang


No. Uraian Kode Satuan Koef Hrg Sat (Rp) Jmlh Hrg (Rp)
1 TENAGA
Pembantu tukang batu L.11 Orang/hari 0,3000 90.000,00 27.000,00
Mandor L.01 Orang/hari 0,0100 215.000,00 2.150,00
Jumlah- 1
......................................................................................... 29.150,00
2 BAHAN
Pupuk kandang Kantong 0,5000 50.000,00 25.000,00
Ketapang kencana Batang 1,2000 750.000,00 900.000,00
Jumlah- 2
......................................................................................... 25.000,00
3 PERALATAN
Jumlah- 3
......................................................................................... -
4 JUMLAH (1+2+3) 504.150,00
5 OVERHEAD + KEUNTUNGAN 15% x Jumlah 4 75.622,50
6 HARGA SATUAN PEKERJAAN (4+5) 579.772,50

V-gajah mini Penanaman rumput gajah mini Satuan M2


No. Uraian Kode Satuan Koef Hrg Sat (Rp) Jmlh Hrg (Rp)
1 TENAGA
Pembantu tukang batu L.11 Orang/hari 0,3000 90.000,00 27.000,00
Mandor L.01 Orang/hari 0,0100 215.000,00 2.150,00
Jumlah- 1
......................................................................................... 29.150,00
2 BAHAN
Pupuk kandang Kantong 0,5000 50.000,00 25.000,00
Rumput gajah mini M2 1,2000 65.000,00 78.000,00
Jumlah- 2
......................................................................................... 25.000,00
3 PERALATAN
Jumlah- 3
......................................................................................... -
4 JUMLAH (1+2+3) 93.150,00
5 OVERHEAD + KEUNTUNGAN 15% x Jumlah 4 13.972,50
6 HARGA SATUAN PEKERJAAN (4+5) 107.122,50

V-pucuk merah Penanaman pucuk merah Satuan Batang


No. Uraian Kode Satuan Koef Hrg Sat (Rp) Jmlh Hrg (Rp)
1 TENAGA
Pembantu tukang batu L.11 Orang/hari 0,3000 90.000,00 27.000,00
Mandor L.01 Orang/hari 0,0100 215.000,00 2.150,00
Jumlah- 1
......................................................................................... 29.150,00
2 BAHAN
Pupuk kandang Kantong 0,5000 50.000,00 25.000,00
Pucuk merah Batang 1,2000 250.000,00 300.000,00
Jumlah- 2
......................................................................................... 25.000,00
3 PERALATAN
Jumlah- 3
......................................................................................... -
4 JUMLAH (1+2+3) 204.150,00
5 OVERHEAD + KEUNTUNGAN 15% x Jumlah 4 30.622,50
6 HARGA SATUAN PEKERJAAN (4+5) 234.772,50
V-trembesi Penanaman trembesi Satuan Batang
No. Uraian Kode Satuan Koef Hrg Sat (Rp) Jmlh Hrg (Rp)
1 TENAGA
Pembantu tukang batu L.11 Orang/hari 0,3000 90.000,00 27.000,00
Mandor L.01 Orang/hari 0,0100 215.000,00 2.150,00
Jumlah- 1
......................................................................................... 29.150,00
2 BAHAN
Pupuk kandang Kantong 0,5000 50.000,00 25.000,00
Trembesi Batang 1,2000 150.000,00 180.000,00
Jumlah- 2
......................................................................................... 25.000,00
3 PERALATAN
Jumlah- 3
......................................................................................... -
4 JUMLAH (1+2+3) 144.150,00
5 OVERHEAD + KEUNTUNGAN 15% x Jumlah 4 21.622,50
6 HARGA SATUAN PEKERJAAN (4+5) 165.772,50

V-tebubaya Tebubaya Satuan Batang


No. Uraian Kode Satuan Koef Hrg Sat (Rp) Jmlh Hrg (Rp)
1 TENAGA
Pembantu tukang batu L.11 Orang/hari 0,3000 90.000,00 27.000,00
Mandor L.01 Orang/hari 0,0100 215.000,00 2.150,00
Jumlah- 1
......................................................................................... 29.150,00
2 BAHAN
Pupuk kandang Kantong 0,5000 50.000,00 25.000,00
Tebubaya Batang 1,2000 600.000,00 720.000,00
Jumlah- 2
......................................................................................... 25.000,00
3 PERALATAN
Jumlah- 3
......................................................................................... -
4 JUMLAH (1+2+3) 414.150,00
5 OVERHEAD + KEUNTUNGAN 15% x Jumlah 4 62.122,50
6 HARGA SATUAN PEKERJAAN (4+5) 476.272,50

Bunga Rombusa Mini (Silver)


V-rombusa mini (silver) Satuan Polibag
No. Uraian Kode Satuan Koef Hrg Sat (Rp) Jmlh Hrg (Rp)
1 TENAGA
Pembantu tukang batu L.11 Orang/hari 0,3000 90.000,00 27.000,00
Mandor L.01 Orang/hari 0,0100 215.000,00 2.150,00
Jumlah- 1
......................................................................................... 29.150,00
2 BAHAN
Pupuk kandang Kantong 0,5000 50.000,00 25.000,00
Bunga Rombusa Mini Silver Polibag 1,2000 25.000,00 30.000,00
Jumlah- 2
......................................................................................... 25.000,00
3 PERALATAN
Jumlah- 3
......................................................................................... -
4 JUMLAH (1+2+3) 69.150,00
5 OVERHEAD + KEUNTUNGAN 15% x Jumlah 4 10.372,50
6 HARGA SATUAN PEKERJAAN (4+5) 79.522,50
V-rombusa mini Bunga Rombusa Mini Satuan Polibag
No. Uraian Kode Satuan Koef Hrg Sat (Rp) Jmlh Hrg (Rp)
1 TENAGA
Pembantu tukang batu L.11 Orang/hari 0,3000 90.000,00 27.000,00
Mandor L.01 Orang/hari 0,0100 215.000,00 2.150,00
Jumlah- 1
......................................................................................... 29.150,00
2 BAHAN
Pupuk kandang Kantong 0,5000 50.000,00 25.000,00
Bunga Rombusa Mini Polibag 1,2000 35.000,00 42.000,00
Jumlah- 2
......................................................................................... 25.000,00
3 PERALATAN
Jumlah- 3
......................................................................................... -
4 JUMLAH (1+2+3) 75.150,00
5 OVERHEAD + KEUNTUNGAN 15% x Jumlah 4 11.272,50
6 HARGA SATUAN PEKERJAAN (4+5) 86.422,50

V-teh tehan Teh-tehan Satuan Polibag


No. Uraian Kode Satuan Koef Hrg Sat (Rp) Jmlh Hrg (Rp)
1 TENAGA
Pembantu tukang batu L.11 Orang/hari 0,3000 90.000,00 27.000,00
Mandor L.01 Orang/hari 0,0100 215.000,00 2.150,00
Jumlah- 1
......................................................................................... 29.150,00
2 BAHAN
Pupuk kandang Kantong 0,5000 50.000,00 25.000,00
Bunga Rombusa Mini Polibag 1,2000 35.000,00 42.000,00
Jumlah- 2
......................................................................................... 25.000,00
3 PERALATAN
Jumlah- 3
......................................................................................... -
4 JUMLAH (1+2+3) 75.150,00
5 OVERHEAD + KEUNTUNGAN 15% x Jumlah 4 11.272,50
6 HARGA SATUAN PEKERJAAN (4+5) 86.422,50

PEKERJAAN PONDASI
A.3.2.1.2 Pemasangan pondasi batu belah campuran 1SP : 4PP Satuan M3
No. Uraian Kode Satuan Koef Hrg Sat (Rp) Jmlh Hrg (Rp)
1 TENAGA
Pembantu tukang batu L.11 Orang/hari 1,5000 90.000,00 135.000,00
Tukang batu L.06 Orang/hari 0,7500 120.000,00 90.000,00
Kepala tukang batu L.02 Orang/hari 0,0750 170.000,00 12.750,00
Mandor L.01 Orang/hari 0,0750 215.000,00 16.125,00
Jumlah- 1
......................................................................................... 253.875,00
2 BAHAN
Batu belah B-1 M3 1,2000 380.000,00 456.000,00
Semen portland C-2 Kg 163,0000 1.200,00 195.600,00
Pasir Pasang B-5 M3 0,5200 84.400,00 43.888,00
Jumlah- 2
......................................................................................... 695.488,00
3 PERALATAN
Jumlah- 3
......................................................................................... -
4 JUMLAH (1+2+3) 949.363,00
5 OVERHEAD + KEUNTUNGAN 15% x Jumlah 4 142.404,45
6 HARGA SATUAN PEKERJAAN (4+5) 1.091.767,45
PEKERJAAN BETON
A.4.1.1.4 Membuat lantai kerja beton mutu f’c = 7,4 MPa (K 100),
slump (3-6) cm, w/c = 0,87 Satuan M3
No. Uraian Kode Satuan Koef Hrg Sat (Rp) Jmlh Hrg (Rp)
1 TENAGA
Pembantu tukang batu L.11 Orang/hari 1,2000 90.000,00 108.000,00
Tukang batu L.06 Orang/hari 0,2000 120.000,00 24.000,00
Kepala tukang batu L.02 Orang/hari 0,0200 170.000,00 3.400,00
Mandor L.01 Orang/hari 0,0600 215.000,00 12.900,00
Jumlah- 1
......................................................................................... 148.300,00
2 BAHAN
Semen portland C-2 Kg 230,0000 1.200,00 276.000,00
Pasir beton B-4 M3 0,6379 116.700,00 74.437,93
Batu pecah 2-3 cm B-3 M3 0,7607 350.000,00 266.259,26
Air A.1 Liter 200,0000 3,00 600,00
Jumlah- 2
......................................................................................... 617.297,19
3 PERALATAN
Jumlah- 3
......................................................................................... -
4 JUMLAH (1+2+3) 765.597,19
5 OVERHEAD + KEUNTUNGAN 15% x Jumlah 4 114.839,58
6 HARGA SATUAN PEKERJAAN (4+5) 880.436,77

A.4.1.1.7 Membuat beton mutu f’c = 19,3 MPa (K 225), slump (12 ± 2) cm, w/c = 0,58 Satuan M3
No. Uraian Kode Satuan Koef Hrg Sat (Rp) Jmlh Hrg (Rp)
1 TENAGA
Pembantu tukang batu L.11 Orang/hari 1,6500 90.000,00 148.500,00
Tukang batu L.06 Orang/hari 0,2750 120.000,00 33.000,00
Kepala tukang batu L.02 Orang/hari 0,0280 170.000,00 4.760,00
Mandor L.01 Orang/hari 0,0830 215.000,00 17.845,00
Jumlah- 1
......................................................................................... 204.105,00
2 BAHAN
Semen portland C-2 Kg 371,0000 1.200,00 445.200,00
Pasir beton B-4 M3 0,4986 116.700,00 58.183,29
Batu pecah 2-3 cm B-3 M3 0,7756 350.000,00 271.444,45
Air A.1 Liter 215,0000 3,00 645,00
Jumlah- 2
......................................................................................... 775.472,74
3 PERALATAN
Jumlah- 3
......................................................................................... -
4 JUMLAH (1+2+3) 979.577,74
5 OVERHEAD + KEUNTUNGAN 15% x Jumlah 4 146.936,66
6 HARGA SATUAN PEKERJAAN (4+5) 1.126.514,40

A.4.1.1.17 Pembesian dengan besi polos atau besi ulir Satuan Kg


No. Uraian Kode Satuan Koef Hrg Sat (Rp) Jmlh Hrg (Rp)
1 TENAGA
Pembantu tukang besi L.13 Orang/hari 0,0070 85.000,00 595,00
Tukang besi L.09 Orang/hari 0,0070 100.000,00 700,00
Kepala tukang besi L.04 Orang/hari 0,0007 150.000,00 105,00
Mandor L.01 Orang/hari 0,0004 215.000,00 86,00
Jumlah- 1
......................................................................................... 1.486,00
2 BAHAN
Besi beton polos D-1 Kg 1,0500 17.500,00 18.375,00
Kawat bindrat D-2 Kg 0,0150 57.960,00 869,40
Jumlah- 2
......................................................................................... 19.244,40
3 PERALATAN
Jumlah- 3
......................................................................................... -
4 JUMLAH (1+2+3) 20.730,40
5 OVERHEAD + KEUNTUNGAN 15% x Jumlah 4 3.109,56
6 HARGA SATUAN PEKERJAAN (4+5) 23.839,96
A.4.1.1.20 Pemasangan bekisting untuk pondasi Satuan M2
No. Uraian Kode Satuan Koef Hrg Sat (Rp) Jmlh Hrg (Rp)
1 TENAGA
Pembantu tukang kayu L.12 Orang/hari 0,5200 80.000,00 41.600,00
Tukang kayu L.07 Orang/hari 0,2600 120.000,00 31.200,00
Kepala tukang kayu L.03 Orang/hari 0,0260 157.500,00 4.095,00
Mandor L.01 Orang/hari 0,0260 215.000,00 5.590,00
Jumlah- 1
......................................................................................... 82.485,00
2 BAHAN
Papan kayu kelas III K-4 M3 0,0400 1.000.000,00 40.000,00
Paku kayu D-5 Kg 0,3000 12.000,00 3.600,00
Minyak bekisting F-6 Ltr 0,1000 23.500,00 2.350,00
Jumlah- 2
......................................................................................... 45.950,00
3 PERALATAN
Jumlah- 3
......................................................................................... -
4 JUMLAH (1+2+3) 128.435,00
5 OVERHEAD + KEUNTUNGAN 15% x Jumlah 4 19.265,25
6 HARGA SATUAN PEKERJAAN (4+5) 147.700,25

A.4.1.1.21 Pemasangan bekisting untuk sloof Satuan M2


No. Uraian Kode Satuan Koef Hrg Sat (Rp) Jmlh Hrg (Rp)
1 TENAGA
Pembantu tukang kayu L.12 Orang/hari 0,5200 80.000,00 41.600,00
Tukang kayu L.07 Orang/hari 0,2600 120.000,00 31.200,00
Kepala tukang batu L.02 Orang/hari 0,0260 170.000,00 4.420,00
Mandor L.01 Orang/hari 0,0260 215.000,00 5.590,00
Jumlah- 1
......................................................................................... 82.810,00
2 BAHAN
Papan kayu kelas III K-4 M3 0,0450 1.000.000,00 45.000,00
Paku kayu D-5 Kg 0,3000 12.000,00 3.600,00
Minyak bekisting F-6 Ltr 0,1000 23.500,00 2.350,00
Jumlah- 2
......................................................................................... 50.950,00
3 PERALATAN
Jumlah- 3
......................................................................................... -
4 JUMLAH (1+2+3) 133.760,00
5 OVERHEAD + KEUNTUNGAN 15% x Jumlah 4 20.064,00
6 HARGA SATUAN PEKERJAAN (4+5) 153.824,00

A.4.1.1.22 Pemasangan bekisting untuk kolom Satuan M2


No. Uraian Kode Satuan Koef Hrg Sat (Rp) Jmlh Hrg (Rp)
1 TENAGA
Pembantu tukang kayu L.12 Orang/hari 0,6600 80.000,00 52.800,00
Tukang kayu L.07 Orang/hari 0,3300 120.000,00 39.600,00
Kepala tukang batu L.02 Orang/hari 0,0330 170.000,00 5.610,00
Mandor L.01 Orang/hari 0,0330 215.000,00 7.095,00
Jumlah- 1
......................................................................................... 105.105,00
2 BAHAN
Papan kayu kelas III K-4 M3 0,0400 1.000.000,00 40.000,00
Paku kayu D-5 Kg 0,4000 12.000,00 4.800,00
Minyak bekisting F-6 Ltr 0,2000 23.500,00 4.700,00
Balok kayu kelas III K-1 M3 0,0150 1.300.000,00 19.500,00
Plywood tebal 9 mm K-6 Lbr 0,3500 200.000,00 70.000,00
Dolken kayu φ 8-10/400 cm
8-10/400 cm K-3 Batang 2,0000 15.000,00 30.000,00
Jumlah- 2
......................................................................................... 169.000,00
3 PERALATAN
Jumlah- 3
......................................................................................... -
4 JUMLAH (1+2+3) 274.105,00
5 OVERHEAD + KEUNTUNGAN 15% x Jumlah 4 41.115,75
6 HARGA SATUAN PEKERJAAN (4+5) 315.220,75
A.4.1.1.23 Pemasangan bekisting untuk balok Satuan M2
No. Uraian Kode Satuan Koef Hrg Sat (Rp) Jmlh Hrg (Rp)
1 TENAGA
Pembantu tukang kayu L.12 Orang/hari 0,6600 80.000,00 52.800,00
Tukang kayu L.07 Orang/hari 0,3300 120.000,00 39.600,00
Kepala tukang batu L.02 Orang/hari 0,0330 170.000,00 5.610,00
Mandor L.01 Orang/hari 0,0330 215.000,00 7.095,00
Jumlah- 1
......................................................................................... 105.105,00
2 BAHAN
Papan kayu kelas III K-4 M3 0,0400 1.000.000,00 40.000,00
Paku kayu D-5 Kg 0,4000 12.000,00 4.800,00
Minyak bekisting F-6 Ltr 0,2000 23.500,00 4.700,00
Balok kayu kelas III K-1 M3 0,0180 1.300.000,00 23.400,00
Plywood tebal 9 mm K-6 Lbr 0,3500 200.000,00 70.000,00
Dolken kayu φ 8-10/400 cm
8-10/400 cm K-3 Batang 2,0000 15.000,00 30.000,00
Jumlah- 2
......................................................................................... 172.900,00
3 PERALATAN
Jumlah- 3
......................................................................................... -
4 JUMLAH (1+2+3) 278.005,00
5 OVERHEAD + KEUNTUNGAN 15% x Jumlah 4 41.700,75
6 HARGA SATUAN PEKERJAAN (4+5) 319.705,75

A.4.1.1.24 Pemasangan bekisting untuk lantai Satuan M2


No. Uraian Kode Satuan Koef Hrg Sat (Rp) Jmlh Hrg (Rp)
1 TENAGA
Pembantu tukang kayu L.12 Orang/hari 0,6600 80.000,00 52.800,00
Tukang kayu L.07 Orang/hari 0,3300 120.000,00 39.600,00
Kepala tukang batu L.02 Orang/hari 0,0330 170.000,00 5.610,00
Mandor L.01 Orang/hari 0,0330 215.000,00 7.095,00
Jumlah- 1
......................................................................................... 105.105,00
2 BAHAN
Papan kayu kelas III K-4 M3 0,0400 1.000.000,00 40.000,00
Paku kayu D-5 Kg 0,4000 12.000,00 4.800,00
Minyak bekisting F-6 Ltr 0,2000 23.500,00 4.700,00
Balok kayu kelas III K-1 M3 0,0150 1.300.000,00 19.500,00
Plywood tebal 9 mm K-6 Lbr 0,3500 200.000,00 70.000,00
Dolken kayu φ 8-10/400 cm
8-10/400 cm K-3 Batang 6,0000 15.000,00 90.000,00
Jumlah- 2
......................................................................................... 229.000,00
3 PERALATAN
Jumlah- 3
......................................................................................... -
4 JUMLAH (1+2+3) 334.105,00
5 OVERHEAD + KEUNTUNGAN 15% x Jumlah 4 50.115,75
6 HARGA SATUAN PEKERJAAN (4+5) 384.220,75
A.4.1.1.25 Pemasangan bekisting untuk dinding Satuan M2
No. Uraian Kode Satuan Koef Hrg Sat (Rp) Jmlh Hrg (Rp)
1 TENAGA
Pembantu tukang kayu L.12 Orang/hari 0,6600 80.000,00 52.800,00
Tukang kayu L.07 Orang/hari 0,3300 120.000,00 39.600,00
Kepala tukang batu L.02 Orang/hari 0,0330 170.000,00 5.610,00
Mandor L.01 Orang/hari 0,0330 215.000,00 7.095,00
Jumlah- 1
......................................................................................... 105.105,00
2 BAHAN
Papan kayu kelas III K-4 M3 0,0300 1.000.000,00 30.000,00
Paku kayu D-5 Kg 0,4000 12.000,00 4.800,00
Minyak bekisting F-6 Ltr 0,2000 23.500,00 4.700,00
Balok kayu kelas III K-1 M3 0,0200 1.300.000,00 26.000,00
Plywood tebal 9 mm K-6 Lbr 0,3500 200.000,00 70.000,00
Dolken kayu φ 8-10/400 cm
8-10/400 cm K-3 Batang 3,0000 15.000,00 45.000,00
Penjaga jarak bekisting/spacer K-5 Buah 4,0000 10.000,00 40.000,00
Jumlah- 2
......................................................................................... 220.500,00
3 PERALATAN
Jumlah- 3
......................................................................................... -
4 JUMLAH (1+2+3) 325.605,00
5 OVERHEAD + KEUNTUNGAN 15% x Jumlah 4 48.840,75
6 HARGA SATUAN PEKERJAAN (4+5) 374.445,75

PEKERJAAN DINDING PASANGAN


A.4.4.1.7 Pemasangan dinding bata merah (5x11x22) cm tebal ½ batu campuran 1SP : 2PP Satuan M2
No. Uraian Kode Satuan Koef Hrg Sat (Rp) Jmlh Hrg (Rp)
1 TENAGA
Pembantu tukang batu L.11 Orang/hari 0,3000 90.000,00 27.000,00
Tukang batu L.06 Orang/hari 0,1000 120.000,00 12.000,00
Kepala tukang batu L.02 Orang/hari 0,0100 170.000,00 1.700,00
Mandor L.01 Orang/hari 0,0150 215.000,00 3.225,00
Jumlah- 1
......................................................................................... 43.925,00
2 BAHAN
Batu bata merah C-1 Buah 70,0000 900,00 63.000,00
Semen portland C-2 Kg 18,9500 1.200,00 22.740,00
Pasir Pasang B-5 M3 0,0380 84.400,00 3.207,20
Jumlah- 2
......................................................................................... 88.947,20
3 PERALATAN
Jumlah- 3
......................................................................................... -
4 JUMLAH (1+2+3) 132.872,20
5 OVERHEAD + KEUNTUNGAN 15% x Jumlah 4 19.930,83
6 HARGA SATUAN PEKERJAAN (4+5) 152.803,03

PEKERJAAN PLESTERAN
A.4.4.2.2 Pemasangan plesteran 1SP : 2PP tebal 15 mm. Satuan M2
No. Uraian Kode Satuan Koef Hrg Sat (Rp) Jmlh Hrg (Rp)
1 TENAGA
Pembantu tukang batu L.11 Orang/hari 0,3000 90.000,00 27.000,00
Tukang batu L.06 Orang/hari 0,1500 120.000,00 18.000,00
Kepala tukang batu L.02 Orang/hari 0,0150 170.000,00 2.550,00
Mandor L.01 Orang/hari 0,0150 215.000,00 3.225,00
Jumlah- 1
......................................................................................... 50.775,00
2 BAHAN
Semen portland C-2 Kg 10,2240 1.200,00 12.268,80
Pasir Pasang B-5 M3 0,0200 84.400,00 1.688,00
Jumlah- 2
......................................................................................... 13.956,80
3 PERALATAN
Jumlah- 3
......................................................................................... -
4 JUMLAH (1+2+3) 64.731,80
5 OVERHEAD + KEUNTUNGAN 15% x Jumlah 4 9.709,77
6 HARGA SATUAN PEKERJAAN (4+5) 74.441,57
LS-pagar besi Pemasangan pagar besi Satuan M2
No. Uraian Kode Satuan Koef Hrg Sat (Rp) Jmlh Hrg (Rp)
1 TENAGA
Pembantu tukang batu L.11 Orang/hari 0,6000 90.000,00 54.000,00
Tukang batu L.06 Orang/hari 0,3000 120.000,00 36.000,00
Kepala tukang batu L.02 Orang/hari 0,0300 170.000,00 5.100,00
Mandor L.01 Orang/hari 0,0300 215.000,00 6.450,00
Jumlah- 1
......................................................................................... 101.550,00
2 BAHAN
Pagar besi lengkap ornamen D-7 Kg 1,0000 750.000,00 750.000,00
Jumlah- 2
......................................................................................... 750.000,00
3 PERALATAN
Jumlah- 3
......................................................................................... -
4 JUMLAH (1+2+3) 851.550,00
5 OVERHEAD + KEUNTUNGAN 15% x Jumlah 4 127.732,50
6 HARGA SATUAN PEKERJAAN (4+5) 979.282,50

A.4.4.2.26 Pemasangan finishing siar pasangan batu kali, campuran 1SP : 2PP. Satuan M2
No. Uraian Kode Satuan Koef Hrg Sat (Rp) Jmlh Hrg (Rp)
1 TENAGA
Pembantu tukang batu L.11 Orang/hari 0,3000 90.000,00 27.000,00
Tukang batu L.06 Orang/hari 0,1500 120.000,00 18.000,00
Kepala tukang batu L.02 Orang/hari 0,0150 170.000,00 2.550,00
Mandor L.01 Orang/hari 0,0150 215.000,00 3.225,00
Jumlah- 1
......................................................................................... 50.775,00
2 BAHAN
Semen portland C-2 Kg 6,3400 1.200,00 7.608,00
Pasir Pasang B-5 M3 0,0120 84.400,00 1.012,80
Jumlah- 2
......................................................................................... 8.620,80
3 PERALATAN
Jumlah- 3
......................................................................................... -
4 JUMLAH (1+2+3) 59.395,80
5 OVERHEAD + KEUNTUNGAN 15% x Jumlah 4 8.909,37
6 HARGA SATUAN PEKERJAAN (4+5) 68.305,17

A.4.4.2.27 Pemasangan acian. Satuan M2


No. Uraian Kode Satuan Koef Hrg Sat (Rp) Jmlh Hrg (Rp)
1 TENAGA
Pembantu tukang batu L.11 Orang/hari 0,2000 90.000,00 18.000,00
Tukang batu L.06 Orang/hari 0,1000 120.000,00 12.000,00
Kepala tukang batu L.02 Orang/hari 0,0100 170.000,00 1.700,00
Mandor L.01 Orang/hari 0,0100 215.000,00 2.150,00
Jumlah- 1
......................................................................................... 33.850,00
2 BAHAN
Semen portland C-2 Kg 3,2500 1.200,00 3.900,00
Jumlah- 2
......................................................................................... 3.900,00
3 PERALATAN
Jumlah- 3
......................................................................................... -
4 JUMLAH (1+2+3) 37.750,00
5 OVERHEAD + KEUNTUNGAN 15% x Jumlah 4 5.662,50
6 HARGA SATUAN PEKERJAAN (4+5) 43.412,50
PEKERJAAN PENUTUP LANTAI & PENUTUP DINDING
A.4.4.3.9 Pemasangan lantai ubin granit ukuran 40cm x40cm Satuan M2
No. Uraian Kode Satuan Koef Hrg Sat (Rp) Jmlh Hrg (Rp)
1 TENAGA
Pembantu tukang batu L.11 Orang/hari 0,2500 90.000,00 22.500,00
Tukang batu L.06 Orang/hari 0,1250 120.000,00 15.000,00
Kepala tukang batu L.02 Orang/hari 0,0130 170.000,00 2.210,00
Mandor L.01 Orang/hari 0,0130 215.000,00 2.795,00
Jumlah- 1
......................................................................................... 42.505,00
2 BAHAN
Ubin granit C-4 Bh 6,6300 400.000,00 2.652.000,00
Semen portland C-2 Kg 9,8000 1.200,00 11.760,00
Semen warna C-3 Kg 1,3000 13.320,00 17.316,00
Pasir Pasang B-5 M3 0,0450 84.400,00 3.798,00
Jumlah- 2
......................................................................................... 2.684.874,00
3 PERALATAN
Jumlah- 3
......................................................................................... -
4 JUMLAH (1+2+3) 2.727.379,00
5 OVERHEAD + KEUNTUNGAN 15% x Jumlah 4 409.106,85
6 HARGA SATUAN PEKERJAAN (4+5) 3.136.485,85

LS-paving block Pemasangan paving block Satuan M2


No. Uraian Kode Satuan Koef Hrg Sat (Rp) Jmlh Hrg (Rp)
1 TENAGA
Pembantu tukang batu L.11 Orang/hari 0,2500 90.000,00 22.500,00
Tukang batu L.06 Orang/hari 0,1250 120.000,00 15.000,00
Kepala tukang batu L.02 Orang/hari 0,0130 170.000,00 2.210,00
Mandor L.01 Orang/hari 0,0130 215.000,00 2.795,00
Jumlah- 1
......................................................................................... 42.505,00
2 BAHAN
Paving block C-5 Bh 50,0000 1.700,00 85.000,00
Pasir Pasang B-5 M3 0,0450 84.400,00 3.798,00
Jumlah- 2
......................................................................................... 88.798,00
3 PERALATAN
Jumlah- 3
......................................................................................... -
4 JUMLAH (1+2+3) 131.303,00
5 OVERHEAD + KEUNTUNGAN 15% x Jumlah 4 19.695,45
6 HARGA SATUAN PEKERJAAN (4+5) 150.998,45

LS-grass block Pemasangan grass block Satuan M2


No. Uraian Kode Satuan Koef Hrg Sat (Rp) Jmlh Hrg (Rp)
1 TENAGA
Pembantu tukang batu L.11 Orang/hari 0,2500 90.000,00 22.500,00
Tukang batu L.06 Orang/hari 0,1250 120.000,00 15.000,00
Kepala tukang batu L.02 Orang/hari 0,0130 170.000,00 2.210,00
Mandor L.01 Orang/hari 0,0130 215.000,00 2.795,00
Jumlah- 1
......................................................................................... 42.505,00
2 BAHAN
Grass block C-6 Bh 27,0000 2.500,00 67.500,00
Pasir Pasang B-5 M3 0,0450 84.400,00 3.798,00
Jumlah- 2
......................................................................................... 71.298,00
3 PERALATAN
Jumlah- 3
......................................................................................... -
4 JUMLAH (1+2+3) 113.803,00
5 OVERHEAD + KEUNTUNGAN 15% x Jumlah 4 17.070,45
6 HARGA SATUAN PEKERJAAN (4+5) 130.873,45
LS-batu sikat Pemasangan batu sikat Satuan M2
No. Uraian Kode Satuan Koef Hrg Sat (Rp) Jmlh Hrg (Rp)
1 TENAGA
Pembantu tukang batu L.11 Orang/hari 0,5000 90.000,00 45.000,00
Tukang batu L.06 Orang/hari 0,2500 120.000,00 30.000,00
Kepala tukang batu L.02 Orang/hari 0,0260 170.000,00 4.420,00
Mandor L.01 Orang/hari 0,0260 215.000,00 5.590,00
Jumlah- 1
......................................................................................... 85.010,00
2 BAHAN
Batu sikat B-8 M2 1,0500 150.000,00 157.500,00
Semen portland C-2 Kg 9,8000 1.200,00 11.760,00
Semen warna C-3 Kg 1,3000 13.320,00 17.316,00
Pasir Pasang B-5 M3 0,0450 84.400,00 3.798,00
Jumlah- 2
......................................................................................... 190.374,00
3 PERALATAN
Jumlah- 3
......................................................................................... -
4 JUMLAH (1+2+3) 275.384,00
5 OVERHEAD + KEUNTUNGAN 15% x Jumlah 4 41.307,60
6 HARGA SATUAN PEKERJAAN (4+5) 316.691,60

PEKERJAAN PENGECATAN
A.4.7.1.4 Pengecatan bidang kayu baru (1 lapis plamuur, 1 Satuan M2
No. lapis cat dasar, 2 lapis Uraian
cat penutup) Kode Satuan Koef Hrg Sat (Rp) Jmlh Hrg (Rp)
1 TENAGA
Pembantu tukang cat L.14 Orang/hari 0,0700 80.000,00 5.600,00
Tukang Cat L.08 Orang/hari 0,0090 120.000,00 1.080,00
Kepala Tukang Cat L.05 Orang/hari 0,0060 140.000,00 840,00
Mandor L.01 Orang/hari 0,0030 215.000,00 645,00
Jumlah- 1
......................................................................................... 8.165,00
2 BAHAN
Cat menie kayu F-3 Kg 0,2000 37.000,00 7.400,00
Plamir F-7 Kg 0,1500 47.500,00 7.125,00
Cat dasar F-2 Kg 0,1700 21.200,00 3.604,00
Cat penutup F-4 Kg 0,2600 16.000,00 4.160,00
Kuas F-5 Bh 0,0100 40.000,00 400,00
Thinner F-8 Ltr 0,0300 30.000,00 900,00
Ampelas F-1 Lbr 0,2000 7.000,00 1.400,00
Jumlah- 2
......................................................................................... 24.989,00
3 PERALATAN
Jumlah- 3
......................................................................................... -
4 JUMLAH (1+2+3) 33.154,00
5 OVERHEAD + KEUNTUNGAN 15% x Jumlah 4 4.973,10
6 HARGA SATUAN PEKERJAAN (4+5) 38.127,10

A.4.7.1.10 Pengecatan tembok baru ( 1lapis plamuur, 1 lapis Satuan M2


No. cat dasar, 2 lapis cat penutup)
Uraian Kode Satuan Koef Hrg Sat (Rp) Jmlh Hrg (Rp)
1 TENAGA
Pembantu tukang cat L.14 Orang/hari 0,0200 80.000,00 1.600,00
Tukang Cat L.08 Orang/hari 0,0630 120.000,00 7.560,00
Kepala Tukang Cat L.05 Orang/hari 0,0063 140.000,00 882,00
Mandor L.01 Orang/hari 0,0030 215.000,00 645,00
Jumlah- 1
......................................................................................... 10.687,00
2 BAHAN
Plamir F-7 Kg 0,1000 47.500,00 4.750,00
Cat dasar F-2 Kg 0,1000 21.200,00 2.120,00
Cat penutup F-4 Kg 0,2600 16.000,00 4.160,00
Jumlah- 2
......................................................................................... 11.030,00
3 PERALATAN
Jumlah- 3
......................................................................................... -
4 JUMLAH (1+2+3) 21.717,00
5 OVERHEAD + KEUNTUNGAN 15% x Jumlah 4 3.257,55
6 HARGA SATUAN PEKERJAAN (4+5) 24.974,55
PEKERJAAN SANITSI GEDUNG
A.5.1.1.2 Pemasangan closet jongkok porslen Satuan Buah
No. Uraian Kode Satuan Koef Hrg Sat (Rp) Jmlh Hrg (Rp)
1 TENAGA
Pembantu tukang batu L.11 Orang/hari 1,0000 90.000,00 90.000,00
Tukang batu L.06 Orang/hari 1,5000 120.000,00 180.000,00
Kepala tukang batu L.02 Orang/hari 0,1500 170.000,00 25.500,00
Mandor L.01 Orang/hari 0,1600 215.000,00 34.400,00
Jumlah- 1
......................................................................................... 329.900,00
2 BAHAN
Closet jongkok C-14 Bh 1,0000 150.080,00 150.080,00
Semen portland C-2 Kg 6,0000 1.200,00 7.200,00
Pasir Pasang B-5 M3 0,0100 84.400,00 844,00
Jumlah- 2
......................................................................................... 158.124,00
3 PERALATAN
Jumlah- 3
......................................................................................... -
4 JUMLAH (1+2+3) 488.024,00
5 OVERHEAD + KEUNTUNGAN 15% x Jumlah 4 73.203,60
6 HARGA SATUAN PEKERJAAN (4+5) 561.227,60

A.5.1.1.26 Pemasangan pipa PVC tipe AW Ø 3/4” Satuan M1


No. Uraian Kode Satuan Koef Hrg Sat (Rp) Jmlh Hrg (Rp)
1 TENAGA
Pembantu tukang batu L.11 Orang/hari 0,0360 90.000,00 3.240,00
Tukang batu L.06 Orang/hari 0,0600 120.000,00 7.200,00
Kepala tukang batu L.02 Orang/hari 0,0060 170.000,00 1.020,00
Mandor L.01 Orang/hari 0,0020 215.000,00 430,00
Jumlah- 1
......................................................................................... 11.890,00
2 BAHAN
Pipa PVC 3/4” C-9 M1 1,2000 9.775,00 11.730,00
Pipa PVC 3/4” (perlengkapan) C-10 Ls 35% 9.775,00 3.421,25
Jumlah- 2
......................................................................................... 15.151,25
3 PERALATAN
Jumlah- 3
......................................................................................... -
4 JUMLAH (1+2+3) 27.041,25
5 OVERHEAD + KEUNTUNGAN 15% x Jumlah 4 4.056,19
6 HARGA SATUAN PEKERJAAN (4+5) 31.097,44

A.5.1.1.27 Pemasangan pipa PVC tipe AW Ø 1” Satuan M1


No. Uraian Kode Satuan Koef Hrg Sat (Rp) Jmlh Hrg (Rp)
1 TENAGA
Pembantu tukang batu L.11 Orang/hari 0,0360 90.000,00 3.240,00
Tukang batu L.06 Orang/hari 0,0600 120.000,00 7.200,00
Kepala tukang batu L.02 Orang/hari 0,0060 170.000,00 1.020,00
Mandor L.01 Orang/hari 0,0020 215.000,00 430,00
Jumlah- 1
......................................................................................... 11.890,00
2 BAHAN
Pipa PVC 1” C-3 M1 1,2000 12.300,00 14.760,00
Pipa PVC 1” (perlengkapan) C-4 M1 35% 12.300,00 4.305,00
Jumlah- 2
......................................................................................... 19.065,00
3 PERALATAN
Jumlah- 3
......................................................................................... -
4 JUMLAH (1+2+3) 30.955,00
5 OVERHEAD + KEUNTUNGAN 15% x Jumlah 4 4.643,25
6 HARGA SATUAN PEKERJAAN (4+5) 35.598,25
A.5.1.1.29 Pemasangan pipa PVC tipe AW Ø 2” Satuan M1
No. Uraian Kode Satuan Koef Hrg Sat (Rp) Jmlh Hrg (Rp)
1 TENAGA
Pembantu tukang batu L.11 Orang/hari 0,0540 90.000,00 4.860,00
Tukang batu L.06 Orang/hari 0,0900 120.000,00 10.800,00
Kepala tukang batu L.02 Orang/hari 0,0090 170.000,00 1.530,00
Mandor L.01 Orang/hari 0,0030 215.000,00 645,00
Jumlah- 1
......................................................................................... 17.835,00
2 BAHAN
Pipa PVC 2” C-5 M1 1,2000 36.700,00 44.040,00
Pipa PVC 2” (perlengkapan) C-6 Ls 35% 36.700,00 12.845,00
Jumlah- 2
......................................................................................... 56.885,00
3 PERALATAN
Jumlah- 3
......................................................................................... -
4 JUMLAH (1+2+3) 74.720,00
5 OVERHEAD + KEUNTUNGAN 15% x Jumlah 4 11.208,00
6 HARGA SATUAN PEKERJAAN (4+5) 85.928,00

A.5.1.1.35 Pemasangan 1 buah kran diameter ½” atau 3/4” Satuan Buah


No. Uraian Kode Satuan Koef Hrg Sat (Rp) Jmlh Hrg (Rp)
1 TENAGA
Pembantu tukang kayu L.12 Orang/hari 0,0100 80.000,00 800,00
Tukang kayu L.07 Orang/hari 0,4000 120.000,00 48.000,00
Kepala tukang kayu L.03 Orang/hari 0,0400 157.500,00 6.300,00
Mandor L.01 Orang/hari 0,0050 215.000,00 1.075,00
Jumlah- 1
......................................................................................... 56.175,00
2 BAHAN
Kran air C-1 Buah 1,0000 180.000,00 180.000,00
Sealtape C-16 Bh 0,0250 6.000,00 150,00
Jumlah- 2
......................................................................................... 180.150,00
3 PERALATAN
Jumlah- 3
......................................................................................... -
4 JUMLAH (1+2+3) 236.325,00
5 OVERHEAD + KEUNTUNGAN 15% x Jumlah 4 35.448,75
6 HARGA SATUAN PEKERJAAN (4+5) 271.773,75

A.5.1.1.35.a Pemasangan 1 buah stop kran Ø 1" Satuan Buah


No. Uraian Kode Satuan Koef Hrg Sat (Rp) Jmlh Hrg (Rp)
1 TENAGA
Pembantu tukang kayu L.12 Orang/hari 0,0100 80.000,00 800,00
Tukang kayu L.07 Orang/hari 0,4000 120.000,00 48.000,00
Kepala tukang kayu L.03 Orang/hari 0,0400 157.500,00 6.300,00
Mandor L.01 Orang/hari 0,0050 215.000,00 1.075,00
Jumlah- 1
......................................................................................... 56.175,00
2 BAHAN
Stop kran C-2 Buah 1,0000 150.000,00 150.000,00
Sealtape C-16 Bh 0,0250 6.000,00 150,00
Jumlah- 2
......................................................................................... 150.150,00
3 PERALATAN
Jumlah- 3
......................................................................................... -
4 JUMLAH (1+2+3) 206.325,00
5 OVERHEAD + KEUNTUNGAN 15% x Jumlah 4 30.948,75
6 HARGA SATUAN PEKERJAAN (4+5) 237.273,75
A.5.1.1.32 Pemasangan pipa PVC tipe AW Ø 4” Satuan M1
No. Uraian Kode Satuan Koef Hrg Sat (Rp) Jmlh Hrg (Rp)
1 TENAGA
Pembantu tukang batu L.11 Orang/hari 0,0810 90.000,00 7.290,00
Tukang batu L.06 Orang/hari 0,1350 120.000,00 16.200,00
Kepala tukang batu L.02 Orang/hari 0,0135 170.000,00 2.295,00
Mandor L.01 Orang/hari 0,0040 215.000,00 860,00
Jumlah- 1
......................................................................................... 26.645,00
2 BAHAN
Pipa PVC 4” C-7 M1 1,2000 63.320,00 75.984,00
Pipa PVC 4” (perlengkapan) C-8 Ls 35% 63.320,00 22.162,00
Jumlah- 2
......................................................................................... 98.146,00
3 PERALATAN
Jumlah- 3
......................................................................................... -
4 JUMLAH (1+2+3) 124.791,00
5 OVERHEAD + KEUNTUNGAN 15% x Jumlah 4 18.718,65
6 HARGA SATUAN PEKERJAAN (4+5) 143.509,65

A.5.1.1.36 Pemasangan floordrain Satuan Buah


No. Uraian Kode Satuan Koef Hrg Sat (Rp) Jmlh Hrg (Rp)
1 TENAGA
Pembantu tukang batu L.11 Orang/hari 0,0100 90.000,00 900,00
Tukang batu L.06 Orang/hari 0,1000 120.000,00 12.000,00
Kepala tukang batu L.02 Orang/hari 0,0100 170.000,00 1.700,00
Mandor L.01 Orang/hari 0,0050 215.000,00 1.075,00
Jumlah- 1
......................................................................................... 15.675,00
2 BAHAN
Floor drain C-13 Bh 1,0000 200.000,00 200.000,00
Jumlah- 2
......................................................................................... 200.000,00
3 PERALATAN
Jumlah- 3
......................................................................................... -
4 JUMLAH (1+2+3) 215.675,00
5 OVERHEAD + KEUNTUNGAN 15% x Jumlah 4 32.351,25
6 HARGA SATUAN PEKERJAAN (4+5) 248.026,25

A.5.1.1.7 Pemasangan bak fibreglass vol 1 m3 Satuan Buah


No. Uraian Kode Satuan Koef Hrg Sat (Rp) Jmlh Hrg (Rp)
1 TENAGA
Pembantu tukang batu L.11 Orang/hari 3,0000 90.000,00 270.000,00
Tukang batu L.06 Orang/hari 4,5000 120.000,00 540.000,00
Kepala tukang batu L.02 Orang/hari 0,0500 170.000,00 8.500,00
Mandor L.01 Orang/hari 0,9000 215.000,00 193.500,00
Jumlah- 1
......................................................................................... 1.012.000,00
2 BAHAN
Bak fibreglass C-11 Bh 1,0000 194.800,00 194.800,00
Bak fibreglass Perlengkapan C-12 Bh 12% 194.800,00 23.376,00
Jumlah- 2
......................................................................................... 218.176,00
3 PERALATAN
Jumlah- 3
......................................................................................... -
4 JUMLAH (1+2+3) 1.230.176,00
5 OVERHEAD + KEUNTUNGAN 15% x Jumlah 4 184.526,40
6 HARGA SATUAN PEKERJAAN (4+5) 1.414.702,40

LS-septic tank Pemasangan 1 buah septic tank Satuan Buah


No. Uraian Kode Satuan Koef Hrg Sat (Rp) Jmlh Hrg (Rp)
1 BAHAN
Septic tank lengkap C-15 Unit 1,0000 7.100.000,00 7.100.000,00
Jumlah- 2
......................................................................................... 7.100.000,00
2 PERALATAN
Jumlah- 3
......................................................................................... -
3 JUMLAH (1+2+3) 7.100.000,00
4 OVERHEAD + KEUNTUNGAN 15% x Jumlah 4 1.065.000,00
5 HARGA SATUAN PEKERJAAN (4+5) 8.165.000,00
Kabel NYY 2x 4mm (PJU)
LS-Kabel NYY 2x 4mm Satuan M1
No. Uraian Kode Satuan Koef Hrg Sat (Rp) Jmlh Hrg (Rp)
1 BAHAN
Kabel NYY 2x 4mm ME-1 M1 1,0000 15.000,00 15.000,00
Jumlah- 2
......................................................................................... 15.000,00
2 PERALATAN
Jumlah- 3
......................................................................................... -
3 JUMLAH (1+2+3) 15.000,00
4 OVERHEAD + KEUNTUNGAN 15% x Jumlah 4 2.250,00
5 HARGA SATUAN PEKERJAAN (4+5) 17.250,00

LS-Box Terminal Box Terminal MCB 10x15x20+ konektor+klem Satuan Unit


No. Uraian Kode Satuan Koef Hrg Sat (Rp) Jmlh Hrg (Rp)
1 BAHAN
Box Terminal MCB 10x15x20+ konektor+klem ME-2 Buah 1,0000 355.000,00 355.000,00
Jumlah- 2
......................................................................................... 355.000,00
2 PERALATAN
Jumlah- 3
......................................................................................... -
3 JUMLAH (1+2+3) 355.000,00
4 OVERHEAD + KEUNTUNGAN 15% x Jumlah 4 53.250,00
5 HARGA SATUAN PEKERJAAN (4+5) 408.250,00

LS-MCB 2 dan 4 A MCB 2 dan 4 A Satuan Buah


No. Uraian Kode Satuan Koef Hrg Sat (Rp) Jmlh Hrg (Rp)
1 BAHAN
MCB 2 dan 4 A ME-4 Buah 1,0000 65.000,00 65.000,00
Jumlah- 2
......................................................................................... 65.000,00
2 PERALATAN
Jumlah- 3
......................................................................................... -
3 JUMLAH (1+2+3) 65.000,00
4 OVERHEAD + KEUNTUNGAN 15% x Jumlah 4 9.750,00
5 HARGA SATUAN PEKERJAAN (4+5) 74.750,00

LS-Ancoor Ø 12 mmAncoor Ø 12 mm panjang 50 cm Satuan Buah


No. Uraian Kode Satuan Koef Hrg Sat (Rp) Jmlh Hrg (Rp)
1 BAHAN
Ancoor Ø 12 mm panjang 50 cm ME-5 Buah 1,0000 120.000,00 120.000,00
Jumlah- 2
......................................................................................... 120.000,00
2 PERALATAN
Jumlah- 3
......................................................................................... -
3 JUMLAH (1+2+3) 120.000,00
4 OVERHEAD + KEUNTUNGAN 15% x Jumlah 4 18.000,00
5 HARGA SATUAN PEKERJAAN (4+5) 138.000,00

Lampu PJU 1 Lengan


LS-Lampu PJU 1 Lengan Satuan Buah
No. Uraian Kode Satuan Koef Hrg Sat (Rp) Jmlh Hrg (Rp)
1 BAHAN
Lampu PJU 1 Lengan ME-6 Buah 1,0000 10.560.000,00 10.560.000,00
Jumlah- 2
......................................................................................... 10.560.000,00
2 PERALATAN
Jumlah- 3
......................................................................................... -
3 JUMLAH (1+2+3) 10.560.000,00
4 OVERHEAD + KEUNTUNGAN 15% x Jumlah 4 1.584.000,00
5 HARGA SATUAN PEKERJAAN (4+5) 12.144.000,00
Lampu PJU 4 Lengan
LS-Lampu PJU 4 Lengan Satuan Buah
No. Uraian Kode Satuan Koef Hrg Sat (Rp) Jmlh Hrg (Rp)
1 BAHAN
Lampu PJU 4 Lengan ME-7 Buah 1,0000 12.647.500,00 12.647.500,00
Jumlah- 2
......................................................................................... 12.647.500,00
2 PERALATAN
Jumlah- 3
......................................................................................... -
3 JUMLAH (1+2+3) 12.647.500,00
4 OVERHEAD + KEUNTUNGAN 15% x Jumlah 4 1.897.125,00
5 HARGA SATUAN PEKERJAAN (4+5) 14.544.625,00

LS-Lampu PJU 28 w FERLampu


101 PJU 28 w FER 101 Satuan Buah
No. Uraian Kode Satuan Koef Hrg Sat (Rp) Jmlh Hrg (Rp)
1 BAHAN
Lampu PJU 28 w FER 101 ME-8 Buah 1,0000 6.500.000,00 6.500.000,00
Jumlah- 2
......................................................................................... 6.500.000,00
2 PERALATAN
Jumlah- 3
......................................................................................... -
3 JUMLAH (1+2+3) 6.500.000,00
4 OVERHEAD + KEUNTUNGAN 15% x Jumlah 4 975.000,00
5 HARGA SATUAN PEKERJAAN (4+5) 7.475.000,00

Jasa Kabel NYY 2x 4mm


LS-jasa Kabel NYY 2x 4mm Satuan M1
No. Uraian Kode Satuan Koef Hrg Sat (Rp) Jmlh Hrg (Rp)
1 JASA
Pemasangan Kabel NYY 2 x 4mm JS-1 M1 1,0000 35.000,00 35.000,00
Jumlah- 2
......................................................................................... 35.000,00
2 PERALATAN
Jumlah- 3
......................................................................................... -
3 JUMLAH (1+2+3) 35.000,00
4 OVERHEAD + KEUNTUNGAN 15% x Jumlah 4 5.250,00
5 HARGA SATUAN PEKERJAAN (4+5) 40.250,00

LS-jasa Box TerminalJasa pemasangan Box Terminal MCB 10x15x20+ Satuan Buah
No. konektor+klem Uraian Kode Satuan Koef Hrg Sat (Rp) Jmlh Hrg (Rp)
1 JASA
Pemasangan Box Terminal MCB 10x15x20+ konektor+klemJS-2 Buah 1,0000 100.000,00 100.000,00
Jumlah- 2
......................................................................................... 100.000,00
2 PERALATAN
Jumlah- 3
......................................................................................... -
3 JUMLAH (1+2+3) 100.000,00
4 OVERHEAD + KEUNTUNGAN 15% x Jumlah 4 15.000,00
5 HARGA SATUAN PEKERJAAN (4+5) 115.000,00

LS-jasa MCB 2 dan 4 Pemasangan


A MCB 2 dan 4 A Satuan Buah
No. Uraian Kode Satuan Koef Hrg Sat (Rp) Jmlh Hrg (Rp)
1 JASA
Pemasangan Box Terminal MCB 10x15x20+ konektor+klemJS-2 Buah 1,0000 100.000,00 100.000,00
Jumlah- 2
......................................................................................... 100.000,00
2 PERALATAN
Jumlah- 3
......................................................................................... -
3 JUMLAH (1+2+3) 100.000,00
4 OVERHEAD + KEUNTUNGAN 15% x Jumlah 4 15.000,00
5 HARGA SATUAN PEKERJAAN (4+5) 115.000,00
Pemasangan ancoor Ø 12 mm panjang 50 cm
LS-jasa Ancoor Ø 12 mm Satuan Buah
No. Uraian Kode Satuan Koef Hrg Sat (Rp) Jmlh Hrg (Rp)
1 JASA
Pemasangan ancoor Ø 12 mm panjang 50 cm JS-4 Buah 1,0000 50.000,00 50.000,00
Jumlah- 2
......................................................................................... 50.000,00
2 PERALATAN
Jumlah- 3
......................................................................................... -
3 JUMLAH (1+2+3) 50.000,00
4 OVERHEAD + KEUNTUNGAN 15% x Jumlah 4 7.500,00
5 HARGA SATUAN PEKERJAAN (4+5) 57.500,00

Pemasangan ancoor Ø 12 mm panjang 50 cm


LS-jasa Ancoor Ø 12 mm Satuan Buah
No. Uraian Kode Satuan Koef Hrg Sat (Rp) Jmlh Hrg (Rp)
1 JASA
Pemasangan ancoor Ø 12 mm panjang 50 cm JS-4 Buah 1,0000 50.000,00 50.000,00
Jumlah- 2
......................................................................................... 50.000,00
2 PERALATAN
Jumlah- 3
......................................................................................... -
3 JUMLAH (1+2+3) 50.000,00
4 OVERHEAD + KEUNTUNGAN 15% x Jumlah 4 7.500,00
5 HARGA SATUAN PEKERJAAN (4+5) 57.500,00

LS-jasa Lampu PJUPemasangan


1 Lengan Lampu PJU 1 Lengan Satuan Buah
No. Uraian Kode Satuan Koef Hrg Sat (Rp) Jmlh Hrg (Rp)
1 JASA
Pemasangan Lampu PJU 1 Lengan JS-5 Buah 1,0000 350.000,00 350.000,00
Jumlah- 2
......................................................................................... 350.000,00
2 PERALATAN
Jumlah- 3
......................................................................................... -
3 JUMLAH (1+2+3) 350.000,00
4 OVERHEAD + KEUNTUNGAN 15% x Jumlah 4 52.500,00
5 HARGA SATUAN PEKERJAAN (4+5) 402.500,00

LS-jasa Lampu PJUPemasangan


4 Lengan Lampu PJU 4 Lengan Satuan Buah
No. Uraian Kode Satuan Koef Hrg Sat (Rp) Jmlh Hrg (Rp)
1 JASA
Pemasangan Lampu PJU 4 Lengan JS-6 Buah 1,0000 1.400.000,00 1.400.000,00
Jumlah- 2
......................................................................................... 1.400.000,00
2 PERALATAN
Jumlah- 3
......................................................................................... -
3 JUMLAH (1+2+3) 1.400.000,00
4 OVERHEAD + KEUNTUNGAN 15% x Jumlah 4 210.000,00
5 HARGA SATUAN PEKERJAAN (4+5) 1.610.000,00

LS-jasa Lampu PJUPemasangan Lampu PJU 28 w FER 101


28 w FER 101 Satuan Buah
No. Uraian Kode Satuan Koef Hrg Sat (Rp) Jmlh Hrg (Rp)
1 JASA
Pemasangan Lampu PJU 28 w FER 101 JS-7 Buah 1,0000 35.000,00 35.000,00
Jumlah- 2
......................................................................................... 35.000,00
2 PERALATAN
Jumlah- 3
......................................................................................... -
3 JUMLAH (1+2+3) 35.000,00
4 OVERHEAD + KEUNTUNGAN 15% x Jumlah 4 5.250,00
5 HARGA SATUAN PEKERJAAN (4+5) 40.250,00
LS-spotlight-1 Lampu sorot tipe 1 Satuan Buah
No. Uraian Kode Satuan Koef Hrg Sat (Rp) Jmlh Hrg (Rp)
1 JASA
Lampu sorot tipe 1 ME-30 Buah 1,0000 6.960.000,00 6.960.000,00
Jumlah- 2
......................................................................................... 6.960.000,00
2 PERALATAN
Jumlah- 3
......................................................................................... -
3 JUMLAH (1+2+3) 6.960.000,00
4 OVERHEAD + KEUNTUNGAN 15% x Jumlah 4 1.044.000,00
5 HARGA SATUAN PEKERJAAN (4+5) 8.004.000,00

LS-spotlight-2 Lampu sorot tipe 2 Satuan Buah


No. Uraian Kode Satuan Koef Hrg Sat (Rp) Jmlh Hrg (Rp)
1 JASA
Lampu sorot tipe 2 ME-31 Buah 1,0000 15.000.000,00 15.000.000,00
Jumlah- 2
......................................................................................... 15.000.000,00
2 PERALATAN
Jumlah- 3
......................................................................................... -
3 JUMLAH (1+2+3) 15.000.000,00
4 OVERHEAD + KEUNTUNGAN 15% x Jumlah 4 2.250.000,00
5 HARGA SATUAN PEKERJAAN (4+5) 17.250.000,00

LS-jasa revisi Box Jasa revisi Box panel


Terminal Satuan Buah
No. Uraian Kode Satuan Koef Hrg Sat (Rp) Jmlh Hrg (Rp)
1 JASA
Jasa revisi Box panel JS-8 Buah 1,0000 1.200.000,00 1.200.000,00
Jumlah- 2
......................................................................................... 1.200.000,00
2 PERALATAN
Jumlah- 3
......................................................................................... -
3 JUMLAH (1+2+3) 1.200.000,00
4 OVERHEAD + KEUNTUNGAN 15% x Jumlah 4 180.000,00
5 HARGA SATUAN PEKERJAAN (4+5) 1.380.000,00

LS-jasa pengamanJasa pengaman lampu tipe 1


spotlight-1 Satuan Buah
No. Uraian Kode Satuan Koef Hrg Sat (Rp) Jmlh Hrg (Rp)
1 JASA
Jasa pengaman lampu tipe 1 JS-9 Buah 1,0000 150.000,00 150.000,00
Jumlah- 2
......................................................................................... 150.000,00
2 PERALATAN
Jumlah- 3
......................................................................................... -
3 JUMLAH (1+2+3) 150.000,00
4 OVERHEAD + KEUNTUNGAN 15% x Jumlah 4 22.500,00
5 HARGA SATUAN PEKERJAAN (4+5) 172.500,00

Jasa lengan spotlight-2


LS-jasa lengan spotlight-2 Satuan Buah
No. Uraian Kode Satuan Koef Hrg Sat (Rp) Jmlh Hrg (Rp)
1 JASA
Jasa pemasangan lengan lampu tipe 2 JS-10 Buah 1,0000 250.000,00 250.000,00
Jumlah- 2
......................................................................................... 250.000,00
2 PERALATAN
Jumlah- 3
......................................................................................... -
3 JUMLAH (1+2+3) 250.000,00
4 OVERHEAD + KEUNTUNGAN 15% x Jumlah 4 37.500,00
5 HARGA SATUAN PEKERJAAN (4+5) 287.500,00
LS-jasa spotlight-1Jasa pemasangan lampu sorot tipe 1 Satuan Buah
No. Uraian Kode Satuan Koef Hrg Sat (Rp) Jmlh Hrg (Rp)
1 JASA
Jasa pemasangan lampu sorot tipe 1 JS-11 Buah 1,0000 100.000,00 100.000,00
Jumlah- 2
......................................................................................... 100.000,00
2 PERALATAN
Jumlah- 3
......................................................................................... -
3 JUMLAH (1+2+3) 100.000,00
4 OVERHEAD + KEUNTUNGAN 15% x Jumlah 4 15.000,00
5 HARGA SATUAN PEKERJAAN (4+5) 115.000,00

LS-jasa spotlight-2Jasa pemasangan lampu sorot tipe 2 Satuan Buah


No. Uraian Kode Satuan Koef Hrg Sat (Rp) Jmlh Hrg (Rp)
1 JASA
Jasa pemasangan lampu sorot tipe 2 JS-12 Buah 1,0000 150.000,00 150.000,00
Jumlah- 2
......................................................................................... 150.000,00
2 PERALATAN
Jumlah- 3
......................................................................................... -
3 JUMLAH (1+2+3) 150.000,00
4 OVERHEAD + KEUNTUNGAN 15% x Jumlah 4 22.500,00
5 HARGA SATUAN PEKERJAAN (4+5) 172.500,00

Pilar
LS-Pilar hidrant two wayshidrant two ways Satuan Buah
No. Uraian Kode Satuan Koef Hrg Sat (Rp) Jmlh Hrg (Rp)
1 BAHAN + UPAH
Pilar hidrant two ways ME-9 Buah 1,0000 7.524.000,00 7.524.000,00
Jumlah- 2
......................................................................................... 7.524.000,00
2 PERALATAN
Jumlah- 3
......................................................................................... -
3 JUMLAH (1+2+3) 7.524.000,00
4 OVERHEAD + KEUNTUNGAN 15% x Jumlah 4 1.128.600,00
5 HARGA SATUAN PEKERJAAN (4+5) 8.652.600,00

LS-Selang gulung Selang gulung Satuan Buah


No. Uraian Kode Satuan Koef Hrg Sat (Rp) Jmlh Hrg (Rp)
1 BAHAN + UPAH
Selang gulung ME-10 Set 1,0000 3.082.500,00 3.082.500,00
Jumlah- 2
......................................................................................... 3.082.500,00
2 PERALATAN
Jumlah- 3
......................................................................................... -
3 JUMLAH (1+2+3) 3.082.500,00
4 OVERHEAD + KEUNTUNGAN 15% x Jumlah 4 462.375,00
5 HARGA SATUAN PEKERJAAN (4+5) 3.544.875,00

LS-Nozzle Nozzle Satuan Buah


No. Uraian Kode Satuan Koef Hrg Sat (Rp) Jmlh Hrg (Rp)
1 BAHAN + UPAH
Nozzle ME-11 Buah 1,0000 1.020.000,00 1.020.000,00
Jumlah- 2
......................................................................................... 1.020.000,00
2 PERALATAN
Jumlah- 3
......................................................................................... -
3 JUMLAH (1+2+3) 1.020.000,00
4 OVERHEAD + KEUNTUNGAN 15% x Jumlah 4 153.000,00
5 HARGA SATUAN PEKERJAAN (4+5) 1.173.000,00
Pipa kembar siam
LS-Pipa kembar siam Satuan Buah
No. Uraian Kode Satuan Koef Hrg Sat (Rp) Jmlh Hrg (Rp)
1 BAHAN + UPAH
Pipa kembar siam ME-12 Buah 1,0000 4.917.000,00 4.917.000,00
Jumlah- 2
......................................................................................... 4.917.000,00
2 PERALATAN
Jumlah- 3
......................................................................................... -
3 JUMLAH (1+2+3) 4.917.000,00
4 OVERHEAD + KEUNTUNGAN 15% x Jumlah 4 737.550,00
5 HARGA SATUAN PEKERJAAN (4+5) 5.654.550,00

Pemasangan
LS-Pemasangan pipa PVC Ø 300pipa
mmPVC Ø 300 mm Satuan Buah
No. Uraian Kode Satuan Koef Hrg Sat (Rp) Jmlh Hrg (Rp)
1 BAHAN + UPAH
Pemasangan pipa PVC Ø 300 mm ME-13 M1 1,0000 525.000,00 525.000,00
Jumlah- 2
......................................................................................... 525.000,00
2 PERALATAN
Jumlah- 3
......................................................................................... -
3 JUMLAH (1+2+3) 525.000,00
4 OVERHEAD + KEUNTUNGAN 15% x Jumlah 4 78.750,00
5 HARGA SATUAN PEKERJAAN (4+5) 603.750,00

Taper
LS-Taper konsentris konsentris 12"-6"
12"-6" Satuan Buah
No. Uraian Kode Satuan Koef Hrg Sat (Rp) Jmlh Hrg (Rp)
1 BAHAN + UPAH
Taper konsentris 12"-6" ME-14 Buah 1,0000 783.000,00 783.000,00
Jumlah- 2
......................................................................................... 783.000,00
2 PERALATAN
Jumlah- 3
......................................................................................... -
3 JUMLAH (1+2+3) 783.000,00
4 OVERHEAD + KEUNTUNGAN 15% x Jumlah 4 117.450,00
5 HARGA SATUAN PEKERJAAN (4+5) 900.450,00

LS-Akhir pipa 12" Akhir pipa 12" Satuan Buah


No. Uraian Kode Satuan Koef Hrg Sat (Rp) Jmlh Hrg (Rp)
1 BAHAN + UPAH
Akhir pipa 12" ME-15 Buah 1,0000 1.120.500,00 1.120.500,00
Jumlah- 2
......................................................................................... 1.120.500,00
2 PERALATAN
Jumlah- 3
......................................................................................... -
3 JUMLAH (1+2+3) 1.120.500,00
4 OVERHEAD + KEUNTUNGAN 15% x Jumlah 4 168.075,00
5 HARGA SATUAN PEKERJAAN (4+5) 1.288.575,00

LS-Horizontal bendHorizontal
90" bend 90" Satuan Buah
No. Uraian Kode Satuan Koef Hrg Sat (Rp) Jmlh Hrg (Rp)
1 BAHAN + UPAH
Horizontal bend 90" ME-16 Buah 1,0000 1.275.000,00 1.275.000,00
Jumlah- 2
......................................................................................... 1.275.000,00
2 PERALATAN
Jumlah- 3
......................................................................................... -
3 JUMLAH (1+2+3) 1.275.000,00
4 OVERHEAD + KEUNTUNGAN 15% x Jumlah 4 191.250,00
5 HARGA SATUAN PEKERJAAN (4+5) 1.466.250,00
LS-Horizontal bendHorizontal
45" bend 45" Satuan Buah
No. Uraian Kode Satuan Koef Hrg Sat (Rp) Jmlh Hrg (Rp)
1 BAHAN + UPAH
Horizontal bend 45" ME-17 Buah 1,0000 1.200.000,00 1.200.000,00
Jumlah- 2
......................................................................................... 1.200.000,00
2 PERALATAN
Jumlah- 3
......................................................................................... -
3 JUMLAH (1+2+3) 1.200.000,00
4 OVERHEAD + KEUNTUNGAN 15% x Jumlah 4 180.000,00
5 HARGA SATUAN PEKERJAAN (4+5) 1.380.000,00

Tee all flange 12"x3


LS-Tee all flange 12"x3 Satuan Buah
No. Uraian Kode Satuan Koef Hrg Sat (Rp) Jmlh Hrg (Rp)
1 BAHAN + UPAH
Tee all flange 12"x3 ME-18 Buah 1,0000 2.655.000,00 2.655.000,00
Jumlah- 2
......................................................................................... 2.655.000,00
2 PERALATAN
Jumlah- 3
......................................................................................... -
3 JUMLAH (1+2+3) 2.655.000,00
4 OVERHEAD + KEUNTUNGAN 15% x Jumlah 4 398.250,00
5 HARGA SATUAN PEKERJAAN (4+5) 3.053.250,00

LS-Check valve 12"Check valve 12" (arrow)


(arrow) Satuan Buah
No. Uraian Kode Satuan Koef Hrg Sat (Rp) Jmlh Hrg (Rp)
1 BAHAN + UPAH
Check valve 12" (arrow) ME-19 Buah 1,0000 8.272.500,00 8.272.500,00
Jumlah- 2
......................................................................................... 8.272.500,00
2 PERALATAN
Jumlah- 3
......................................................................................... -
3 JUMLAH (1+2+3) 8.272.500,00
4 OVERHEAD + KEUNTUNGAN 15% x Jumlah 4 1.240.875,00
5 HARGA SATUAN PEKERJAAN (4+5) 9.513.375,00

LS-Reducer 12"-6"Reducer 12"-6" Satuan Buah


No. Uraian Kode Satuan Koef Hrg Sat (Rp) Jmlh Hrg (Rp)
1 BAHAN + UPAH
Reducer 12"-6" ME-20 Buah 1,0000 157.500,00 157.500,00
Jumlah- 2
......................................................................................... 157.500,00
2 PERALATAN
Jumlah- 3
......................................................................................... -
3 JUMLAH (1+2+3) 157.500,00
4 OVERHEAD + KEUNTUNGAN 15% x Jumlah 4 23.625,00
5 HARGA SATUAN PEKERJAAN (4+5) 181.125,00

LS-Reducer 6"-4" Reducer 6"-4" Satuan Buah


No. Uraian Kode Satuan Koef Hrg Sat (Rp) Jmlh Hrg (Rp)
1 BAHAN + UPAH
Reducer 6"-4" ME-21 Buah 1,0000 69.000,00 69.000,00
Jumlah- 2
......................................................................................... 69.000,00
2 PERALATAN
Jumlah- 3
......................................................................................... -
3 JUMLAH (1+2+3) 69.000,00
4 OVERHEAD + KEUNTUNGAN 15% x Jumlah 4 10.350,00
5 HARGA SATUAN PEKERJAAN (4+5) 79.350,00
LS-Reducer 4"-2" Reducer 4"-2" Satuan Buah
No. Uraian Kode Satuan Koef Hrg Sat (Rp) Jmlh Hrg (Rp)
1 BAHAN + UPAH
Reducer 4"-2" ME-22 Buah 1,0000 4.500.000,00 4.500.000,00
Jumlah- 2
......................................................................................... 4.500.000,00
2 PERALATAN
Jumlah- 3
......................................................................................... -
3 JUMLAH (1+2+3) 4.500.000,00
4 OVERHEAD + KEUNTUNGAN 15% x Jumlah 4 675.000,00
5 HARGA SATUAN PEKERJAAN (4+5) 5.175.000,00

Revisi Box panel


LS-revisi Box Terminal Satuan LS
No. Uraian Kode Satuan Koef Hrg Sat (Rp) Jmlh Hrg (Rp)
1 BAHAN + UPAH
Revisi Box panel ME-3 Buah 1,0000 5.000.000,00 5.000.000,00
Jumlah- 2
......................................................................................... 5.000.000,00
2 PERALATAN
Jumlah- 3
......................................................................................... -
3 JUMLAH (1+2+3) 5.000.000,00
4 OVERHEAD + KEUNTUNGAN 15% x Jumlah 4 750.000,00
5 HARGA SATUAN PEKERJAAN (4+5) 5.750.000,00

Pengaman lampu tipe 1


LS-pengaman spotlight-1 Satuan LS
No. Uraian Kode Satuan Koef Hrg Sat (Rp) Jmlh Hrg (Rp)
1 BAHAN + UPAH
Pengaman lampu tipe 1 ME-28 Buah 1,0000 500.000,00 500.000,00
Jumlah- 2
......................................................................................... 500.000,00
2 PERALATAN
Jumlah- 3
......................................................................................... -
3 JUMLAH (1+2+3) 500.000,00
4 OVERHEAD + KEUNTUNGAN 15% x Jumlah 4 75.000,00
5 HARGA SATUAN PEKERJAAN (4+5) 575.000,00

Lengan lampu tipe 2


LS-lengan spotlight-2 Satuan LS
No. Uraian Kode Satuan Koef Hrg Sat (Rp) Jmlh Hrg (Rp)
1 BAHAN + UPAH
Lengan lampu tipe 2 ME-29 Buah 1,0000 1.200.000,00 1.200.000,00
Jumlah- 2
......................................................................................... 1.200.000,00
2 PERALATAN
Jumlah- 3
......................................................................................... -
3 JUMLAH (1+2+3) 1.200.000,00
4 OVERHEAD + KEUNTUNGAN 15% x Jumlah 4 180.000,00
5 HARGA SATUAN PEKERJAAN (4+5) 1.380.000,00
Analisa EI.421 Perkerasan Agregat Kelas A Satuan M2
No. Uraian Kode Satuan Koef Hrg Sat (Rp) Jmlh Hrg (Rp)
1 TENAGA
Pembantu tukang batu L.11 Orang/hari 0,0241 12.857,14 309,86
Mandor L.01 Orang/hari 0,0024 30.714,29 74,03
Jumlah- 1
......................................................................................... 383,89
2 BAHAN
Aspal Curah F-9 Kg 6,6150 11.833,00 78.275,30
Filter F-11 Bh 4,8015 2.500,00 12.003,75
Batu pecah 1-2 cm B-2 M3 0,0149 466.700,00 6.953,83
Batu pecah 2-3 cm B-3 M3 0,0336 350.000,00 11.760,00
Jumlah- 2
......................................................................................... 108.992,88
3 PERALATAN
Sewa Asphatt Mixing Plant ALT-1 Jam 0,0024 5.700.000,00 13.737,00
Sewa Wheel Leader 10-15 HP ALT-2 Jam 0,0016 723.753,03 1.158,01
Sewa Dump Truck 8-10 m3 ALT-3 Jam 0,0385 97.500,00 3.753,75
Sewa Asphatt Finisher ALT-4 Jam 0,0030 1.285.087,50 3.855,27
Sewa Todem Roller ALT-5 Jam 0,0018 335.154,00 603,28
Sewa Tire Roller ALT-6 Jam 0,0025 339.540,00 848,85
Sewa Alat Bantu ALT-7 Jam 1,0000 1.500,00 1.500,00
Jumlah- 3
......................................................................................... 25.456,16
4 JUMLAH (1+2+3) 134.832,93
5 OVERHEAD + KEUNTUNGAN 15% x Jumlah 4 20.224,94
6 HARGA SATUAN PEKERJAAN (4+5) 155.057,87

Analisa EI.422 Perkerasan Agregat Kelas B Satuan M3


No. Uraian Kode Satuan Koef Hrg Sat (Rp) Jmlh Hrg (Rp)
1 TENAGA
Pembantu tukang batu L.11 Orang/hari 0,4293 12.857,14 5.519,58
Mandor L.01 Orang/hari 0,0613 30.714,29 1.882,79
Jumlah- 1
......................................................................................... 7.402,37
2 BAHAN
Aspal Curah F-9 Kg 157,0000 11.833,00 1.857.781,00
Filter F-11 Bh 139,2000 2.500,00 348.000,00
Batu pecah 1-2 cm B-2 M3 0,5341 466.700,00 249.264,47
Batu pecah 2-3 cm B-3 M3 0,7028 350.000,00 245.980,00
Jumlah- 2
......................................................................................... 2.701.025,47
3 PERALATAN
Sewa Asphatt Mixing Plant ALT-1 Jam 0,0613 5.700.000,00 349.410,00
Sewa Wheel Leader 10-15 HP ALT-2 Jam 0,0421 723.753,03 30.470,01
Sewa Dump Truck 8-10 m3 ALT-3 Jam 0,5429 97.500,00 52.932,75
Sewa Asphatt Finisher ALT-4 Jam 0,0767 1.285.087,50 98.566,22
Sewa Todem Roller ALT-5 Jam 0,0476 335.154,00 15.953,34
Sewa Tire Roller ALT-6 Jam 0,0356 339.540,00 12.087,63
Sewa Alat Bantu ALT-7 Jam 1,0000 1.500,00 1.500,00
Jumlah- 3
......................................................................................... 560.919,95
4 JUMLAH (1+2+3) 3.269.347,79
5 OVERHEAD + KEUNTUNGAN 15% x Jumlah 4 490.402,17
6 HARGA SATUAN PEKERJAAN (4+5) 3.759.749,96
Tack Coat Lapisan aspal pengikat Satuan M2
No. Uraian Kode Satuan Koef Hrg Sat (Rp) Jmlh Hrg (Rp)
1 TENAGA
Pembantu tukang batu L.11 Orang/hari 0,0201 12.857,14 258,43
Mandor L.01 Orang/hari 0,0030 30.714,29 92,15
Jumlah- 1
......................................................................................... 350,58
2 BAHAN
Aspal Curah F-9 Kg 0,8894 11.833,00 10.524,28
Minyak tanah F-10 Ltr 0,2530 7.000,00 1.771,00
Jumlah- 2
......................................................................................... 12.295,28
3 PERALATAN
Sewa Aspal Spatyer ALT-8 Jam 0,0030 34.500,00 103,50
Sewa Compresor ALT-9 Jam 0,0063 112.500,00 708,75
Sewa Dump Truck 8-10 m3 ALT-10 Jam 0,0030 97.500,00 292,50
Jumlah- 3
......................................................................................... 1.104,75
4 JUMLAH (1+2+3) 13.750,61
5 OVERHEAD + KEUNTUNGAN 15% x Jumlah 4 2.062,59
6 HARGA SATUAN PEKERJAAN (4+5) 15.813,20

M.001 Stop kontak + instalasi beton Satuan Titik


No. Uraian Kode Satuan Koef Hrg Sat (Rp) Jmlh Hrg (Rp)
1 TENAGA
Jumlah- 1
......................................................................................... -
2 BAHAN
Stop kontak + instalasi beton ME-23 Buah 1,0000 76.800,00 76.800,00
Jumlah- 2
......................................................................................... 76.800,00
3 PERALATAN
Jumlah- 3
......................................................................................... -
4 JUMLAH (1+2+3) 76.800,00
5 OVERHEAD + KEUNTUNGAN 15% x Jumlah 4 11.520,00
6 HARGA SATUAN PEKERJAAN (4+5) 88.320,00

M.002 Stop kontak antena Satuan Titik


No. Uraian Kode Satuan Koef Hrg Sat (Rp) Jmlh Hrg (Rp)
1 TENAGA
Jumlah- 1
......................................................................................... -
2 BAHAN
Stop kontak antena ME-24 Buah 1,0000 60.000,00 60.000,00
Jumlah- 2
......................................................................................... 60.000,00
3 PERALATAN
Jumlah- 3
......................................................................................... -
4 JUMLAH (1+2+3) 60.000,00
5 OVERHEAD + KEUNTUNGAN 15% x Jumlah 4 9.000,00
6 HARGA SATUAN PEKERJAAN (4+5) 69.000,00

M.003 Schakelar (standar) Satuan Titik


No. Uraian Kode Satuan Koef Hrg Sat (Rp) Jmlh Hrg (Rp)
1 TENAGA
Jumlah- 1
......................................................................................... -
2 BAHAN
Schakelar (standar) ME-25 Buah 1,0000 14.320,00 14.320,00
Jumlah- 2
......................................................................................... 14.320,00
3 PERALATAN
Jumlah- 3
......................................................................................... -
4 JUMLAH (1+2+3) 14.320,00
5 OVERHEAD + KEUNTUNGAN 15% x Jumlah 4 2.148,00
6 HARGA SATUAN PEKERJAAN (4+5) 16.468,00
M.004 Lampu PL 14 watt + armatur down light 4" Satuan Titik
No. Uraian Kode Satuan Koef Hrg Sat (Rp) Jmlh Hrg (Rp)
1 TENAGA
Jumlah- 1
......................................................................................... -
2 BAHAN
Lampu PL 14 watt + armatur down light 4" ME-26 Buah 1,0000 168.000,00 168.000,00
Jumlah- 2
......................................................................................... 168.000,00
3 PERALATAN
Jumlah- 3
......................................................................................... -
4 JUMLAH (1+2+3) 168.000,00
5 OVERHEAD + KEUNTUNGAN 15% x Jumlah 4 25.200,00
6 HARGA SATUAN PEKERJAAN (4+5) 193.200,00

M.005 Titik lampu + instalasi beton Satuan Titik


No. Uraian Kode Satuan Koef Hrg Sat (Rp) Jmlh Hrg (Rp)
1 TENAGA
Jumlah- 1
......................................................................................... -
2 BAHAN
Titik lampu + instalasi beton ME-27 Buah 1,0000 151.840,00 151.840,00
Jumlah- 2
......................................................................................... 151.840,00
3 PERALATAN
Jumlah- 3
......................................................................................... -
4 JUMLAH (1+2+3) 151.840,00
5 OVERHEAD + KEUNTUNGAN 15% x Jumlah 4 22.776,00
6 HARGA SATUAN PEKERJAAN (4+5) 174.616,00

A.4.2.1.11 Pemasangan kusen pintu alluminium Satuan M1


No. Uraian Kode Satuan Koef Hrg Sat (Rp) Jmlh Hrg (Rp)
1 TENAGA
Pembantu tukang besi L.13 Orang/hari 0,0430 85.000,00 3.655,00
Tukang Khusus Alumunium L.10 Orang/hari 0,0430 100.000,00 4.300,00
Kepala tukang batu L.02 Orang/hari 0,0043 170.000,00 731,00
Mandor L.01 Orang/hari 0,0021 215.000,00 451,50
Jumlah- 1
......................................................................................... 9.137,50
2 BAHAN
Profil alluminium D-8 M1 1,1000 96.000,00 105.600,00
Skrup fixer D-9 Buah 2,0000 124,80 249,60
Sealant D-12 Tube 0,0600 24.000,00 1.440,00
Jumlah- 2
......................................................................................... 107.289,60
3 PERALATAN
Jumlah- 3
......................................................................................... -
4 JUMLAH (1+2+3) 116.427,10
5 OVERHEAD + KEUNTUNGAN 15% x Jumlah 4 17.464,07
6 HARGA SATUAN PEKERJAAN (4+5) 133.891,17

A.4.2.1.13 Pemasangan pintu kaca rangka alluminium Satuan M2


No. Uraian Kode Satuan Koef Hrg Sat (Rp) Jmlh Hrg (Rp)
1 TENAGA
Pembantu tukang batu L.11 Orang/hari 0,0850 90.000,00 7.650,00
Tukang Khusus Alumunium L.10 Orang/hari 0,0850 100.000,00 8.500,00
Kepala tukang batu L.02 Orang/hari 0,0090 170.000,00 1.530,00
Mandor L.01 Orang/hari 0,0050 215.000,00 1.075,00
Jumlah- 1
......................................................................................... 18.755,00
2 BAHAN
Profil alluminium D-8 M1 4,4000 96.000,00 422.400,00
Profil kaca D-10 M2 1,0500 96.160,00 100.968,00
Sealant D-12 Tube 0,2700 24.000,00 6.480,00
Jumlah- 2
......................................................................................... 529.848,00
3 PERALATAN
Jumlah- 3
......................................................................................... -
4 JUMLAH (1+2+3) 548.603,00
5 OVERHEAD + KEUNTUNGAN 15% x Jumlah 4 82.290,45
6 HARGA SATUAN PEKERJAAN (4+5) 630.893,45
A.4.6.2.17 Pemasangan kaca tebal 5 mm Satuan M2
No. Uraian Kode Satuan Koef Hrg Sat (Rp) Jmlh Hrg (Rp)
1 TENAGA
Pembantu tukang kayu L.12 Orang/hari 0,0150 80.000,00 1.200,00
Tukang kayu L.07 Orang/hari 0,1500 120.000,00 18.000,00
Kepala tukang kayu L.03 Orang/hari 0,0150 157.500,00 2.362,50
Mandor L.01 Orang/hari 0,0008 215.000,00 172,00
Jumlah- 1
......................................................................................... 21.734,50
2 BAHAN
Kaca tebal 5 mm D-11 M2 1,1000 96.160,00 105.776,00
Sealant D-12 Tube 0,0500 24.000,00 1.200,00
Jumlah- 2
......................................................................................... 106.976,00
3 PERALATAN
Jumlah- 3
......................................................................................... -
4 JUMLAH (1+2+3) 128.710,50
5 OVERHEAD + KEUNTUNGAN 15% x Jumlah 4 19.306,58
6 HARGA SATUAN PEKERJAAN (4+5) 148.017,08

A.4.6.2.6 Pemasangan engsel jendela kupu-kupu Satuan Buah


No. Uraian Kode Satuan Koef Hrg Sat (Rp) Jmlh Hrg (Rp)
1 TENAGA
Pembantu tukang kayu L.12 Orang/hari 0,0100 80.000,00 800,00
Tukang kayu L.07 Orang/hari 0,1000 120.000,00 12.000,00
Kepala tukang kayu L.03 Orang/hari 0,0100 157.500,00 1.575,00
Mandor L.01 Orang/hari 0,0005 215.000,00 107,50
Jumlah- 1
......................................................................................... 14.482,50
2 BAHAN
Engsel kupu-kupu D-13 Buah 1,0000 22.240,00 22.240,00
Jumlah- 2
......................................................................................... 22.240,00
3 PERALATAN
Jumlah- 3
......................................................................................... -
4 JUMLAH (1+2+3) 36.722,50
5 OVERHEAD + KEUNTUNGAN 15% x Jumlah 4 5.508,38
6 HARGA SATUAN PEKERJAAN (4+5) 42.230,88

A.4.6.2.11 Pemasangan kunci slot Satuan Buah


No. Uraian Kode Satuan Koef Hrg Sat (Rp) Jmlh Hrg (Rp)
1 TENAGA
Pembantu tukang kayu L.12 Orang/hari 0,0200 80.000,00 1.600,00
Tukang kayu L.07 Orang/hari 0,2000 120.000,00 24.000,00
Kepala tukang kayu L.03 Orang/hari 0,0200 157.500,00 3.150,00
Mandor L.01 Orang/hari 0,0010 215.000,00 215,00
Jumlah- 1
......................................................................................... 28.965,00
2 BAHAN
Kunci slot D-14 Buah 1,0000 10.160,00 10.160,00
Jumlah- 2
......................................................................................... 10.160,00
3 PERALATAN
Jumlah- 3
......................................................................................... -
4 JUMLAH (1+2+3) 39.125,00
5 OVERHEAD + KEUNTUNGAN 15% x Jumlah 4 5.868,75
6 HARGA SATUAN PEKERJAAN (4+5) 44.993,75
A.4.6.2.12.a Pemasangan tarikan jendela Satuan Buah
No. Uraian Kode Satuan Koef Hrg Sat (Rp) Jmlh Hrg (Rp)
1 TENAGA
Pembantu tukang kayu L.12 Orang/hari 0,0500 80.000,00 4.000,00
Tukang kayu L.07 Orang/hari 0,5000 120.000,00 60.000,00
Kepala tukang kayu L.03 Orang/hari 0,0500 157.500,00 7.875,00
Mandor L.01 Orang/hari 0,0030 215.000,00 645,00
Jumlah- 1
......................................................................................... 72.520,00
2 BAHAN
Tarikan jendela D-15 Buah 1,0000 9.600,00 9.600,00
Jumlah- 2
......................................................................................... 9.600,00
3 PERALATAN
Jumlah- 3
......................................................................................... -
4 JUMLAH (1+2+3) 82.120,00
5 OVERHEAD + KEUNTUNGAN 15% x Jumlah 4 12.318,00
6 HARGA SATUAN PEKERJAAN (4+5) 94.438,00

A.4.6.2.9 Pemasangan kait angin Satuan Buah


No. Uraian Kode Satuan Koef Hrg Sat (Rp) Jmlh Hrg (Rp)
1 TENAGA
Pembantu tukang kayu L.12 Orang/hari 0,0150 80.000,00 1.200,00
Tukang kayu L.07 Orang/hari 0,1500 120.000,00 18.000,00
Kepala tukang kayu L.03 Orang/hari 0,0150 157.500,00 2.362,50
Mandor L.01 Orang/hari 0,0080 215.000,00 1.720,00
Jumlah- 1
......................................................................................... 23.282,50
2 BAHAN
Kait angin D-16 Buah 1,0000 14.560,00 14.560,00
Jumlah- 2
......................................................................................... 14.560,00
3 PERALATAN
Jumlah- 3
......................................................................................... -
4 JUMLAH (1+2+3) 37.842,50
5 OVERHEAD + KEUNTUNGAN 15% x Jumlah 4 5.676,38
6 HARGA SATUAN PEKERJAAN (4+5) 43.518,88

A.4.4.3.54 Pemasangan dinding keramik 20cm x 20cm Satuan M2


No. Uraian Kode Satuan Koef Hrg Sat (Rp) Jmlh Hrg (Rp)
1 TENAGA
Pembantu tukang batu L.11 Orang/hari 0,9000 90.000,00 81.000,00
Tukang batu L.06 Orang/hari 0,4500 120.000,00 54.000,00
Kepala tukang batu L.02 Orang/hari 0,0450 170.000,00 7.650,00
Mandor L.01 Orang/hari 0,0450 215.000,00 9.675,00
Jumlah- 1
......................................................................................... 152.325,00
2 BAHAN
Keramik homogenous 40x40 cm C-7 Bh 1,0500 180.000,00 189.000,00
Semen portland C-2 Kg 9,3000 1.200,00 11.160,00
Pasir Pasang B-5 M3 0,0180 84.400,00 1.519,20
Semen warna C-3 Kg 1,9400 13.320,00 25.840,80
Jumlah- 2
......................................................................................... 227.520,00
3 PERALATAN
Jumlah- 3
......................................................................................... -
4 JUMLAH (1+2+3) 379.845,00
5 OVERHEAD + KEUNTUNGAN 15% x Jumlah 4 56.976,75
6 HARGA SATUAN PEKERJAAN (4+5) 436.821,75
A.4.4.3.34.a Pemasangan lantai keramik ukuran 40cm x 40cm Satuan M2
No. Uraian Kode Satuan Koef Hrg Sat (Rp) Jmlh Hrg (Rp)
1 TENAGA
Pembantu tukang batu L.11 Orang/hari 0,7000 90.000,00 63.000,00
Tukang batu L.06 Orang/hari 0,3500 120.000,00 42.000,00
Kepala tukang batu L.02 Orang/hari 0,0350 170.000,00 5.950,00
Mandor L.01 Orang/hari 0,0350 215.000,00 7.525,00
Jumlah- 1
......................................................................................... 118.475,00
2 BAHAN
Keramik homogenous 40x40 cm C-7 Bh 1,0500 180.000,00 189.000,00
Semen portland C-2 Kg 8,1900 1.200,00 9.828,00
Pasir Pasang B-5 M3 0,0450 84.400,00 3.798,00
Semen warna C-3 Kg 1,6200 13.320,00 21.578,40
Jumlah- 2
......................................................................................... 224.204,40
3 PERALATAN
Jumlah- 3
......................................................................................... -
4 JUMLAH (1+2+3) 342.679,40
5 OVERHEAD + KEUNTUNGAN 15% x Jumlah 4 51.401,91
6 HARGA SATUAN PEKERJAAN (4+5) 394.081,31
DAFTAR HARGA BAHAN DAN UPAH
NO JENIS TENAGA / BAHAN KODE HARGA SATUAN
0 1 2 3 4
A. TENAGA
1 Mandor L.01 215.000,00 Orang/hari
2 Kepala tukang batu L.02 170.000,00 Orang/hari
3 Kepala tukang kayu L.03 157.500,00 Orang/hari
4 Kepala tukang besi L.04 150.000,00 Orang/hari
5 Kepala Tukang Cat L.05 140.000,00 Orang/hari
6 Tukang batu L.06 120.000,00 Orang/hari
7 Tukang kayu L.07 120.000,00 Orang/hari
8 Tukang Cat L.08 120.000,00 Orang/hari
9 Tukang besi L.09 100.000,00 Orang/hari
10 Tukang Khusus Alumunium L.10 100.000,00 Orang/hari
11 Pembantu tukang batu L.11 90.000,00 Orang/hari
12 Pembantu tukang kayu L.12 80.000,00 Orang/hari
13 Pembantu tukang besi L.13 85.000,00 Orang/hari
14 Pembantu tukang cat L.14 80.000,00 Orang/hari

B BAHAN
- BAHAN AIR
1 Air A.1 3,00 Liter

- BAHAN GALIAN
1 Batu belah B-1 380.000,00 M3
2 Batu pecah 1-2 cm B-2 466.700,00 M3
3 Batu pecah 2-3 cm B-3 350.000,00 M3
4 Pasir beton B-4 116.700,00 M3
5 Pasir Pasang B-5 84.400,00 M3
6 Pasir Urug B-6 66.700,00 M3
7 Tanah subur B-7 162.500,00 M3
8 Batu sikat B-8 150.000,00 M2
9 Pupuk kandang B-9 50.000,00 Kantong

- BAHAN CETAKAN DAN SEMEN


1 Batu bata merah C-1 900,00 Buah
2 Semen portland C-2 1.200,00 Kg
3 Semen warna C-3 13.320,00 Kg
4 Ubin granit C-4 400.000,00 Bh
5 Paving block C-5 1.700,00 Bh
6 Grass block C-6 2.500,00 Bh
7 Keramik homogenous 40x40 cm C-7 180.000,00 Bh

- BAHAN PIPA DAN SANITARI


1 Kran air C-1 180.000,00 Buah
2 Stop kran C-2 150.000,00 Buah
3 Pipa PVC 1” C-3 12.300,00 M1
4 Pipa PVC 1” (perlengkapan) C-4 12.300,00 M1
5 Pipa PVC 2” C-5 36.700,00 M1
6 Pipa PVC 2” (perlengkapan) C-6 36.700,00 Ls
7 Pipa PVC 4” C-7 63.320,00 M1
8 Pipa PVC 4” (perlengkapan) C-8 63.320,00 Ls
9 Pipa PVC 3/4” C-9 9.775,00 M1
10 Pipa PVC 3/4” (perlengkapan) C-10 9.775,00 Ls
11 Bak fibreglass C-11 194.800,00 Bh
12 Bak fibreglass Perlengkapan C-12 194.800,00 Bh
13 Floor drain C-13 200.000,00 Bh
14 Closet jongkok C-14 150.080,00 Bh
15 Septic tank lengkap C-15 7.100.000,00 Unit
NO JENIS TENAGA / BAHAN KODE HARGA SATUAN
16 Sealtape C-16 6.000,00 Bh

- BAHAN BESI
1 Besi beton polos D-1 17.500,00 Kg
2 Kawat bindrat D-2 57.960,00 Kg
3 Seng gelombang D-3 75.000,00 Lbr
4 Seng plat D-4 26.500,00 M1
5 Paku kayu D-5 12.000,00 Kg
6 Pagar besi lengkap ornamen D-7 750.000,00 Kg
7 Profil alluminium D-8 96.000,00 M1
8 Skrup fixer D-9 124,80 Buah
9 Profil kaca D-10 96.160,00 M2
10 Kaca tebal 5 mm D-11 96.160,00 M2
11 Sealant D-12 24.000,00 Tube
12 Engsel kupu-kupu D-13 22.240,00 Buah
13 Kunci slot D-14 10.160,00 Buah
14 Tarikan jendela D-15 9.600,00 Buah
15 Kait angin D-16 14.560,00 Buah

- BAHAN CAT, FINISHING DAN ASPAL


1 Ampelas F-1 7.000,00 Lbr
2 Cat dasar F-2 21.200,00 Kg
3 Cat menie kayu F-3 37.000,00 Kg
4 Cat penutup F-4 16.000,00 Kg
5 Kuas F-5 40.000,00 Bh
6 Minyak bekisting F-6 23.500,00 Ltr
7 Plamir F-7 47.500,00 Kg
8 Thinner F-8 30.000,00 Ltr
9 Aspal Curah F-9 11.833,00 Kg
10 Minyak tanah F-10 7.000,00 Ltr
11 Filter F-11 2.500,00 Bh

- BAHAN KAYU
1 Balok kayu kelas III K-1 1.300.000,00 M3
2 Dolken kayu φ 8-10/400 cm
8-10/400 cm K-3 15.000,00 Batang
3 Papan kayu kelas III K-4 1.000.000,00 M3
4 Penjaga jarak bekisting/spacer K-5 10.000,00 Buah
5 Plywood tebal 9 mm K-6 200.000,00 Lbr

- BAHAN TAMAN
1 Rumput gajah mini V-1 65.000,00 M2
2 Pucuk merah V-2 250.000,00 Batang
3 Ketapang kencana V-4 750.000,00 Batang
4 Trembesi V-5 150.000,00 Batang
5 Sawo kecik V-7 500.000,00 Batang
6 Tebubaya V-8 600.000,00 Batang
7 Bunga Rombusa Mini silver V-9 25.000,00 Polibag
8 Bunga Rombusa Mini V-10 35.000,00 Polibag
9 Teh-tehan V-11 25.000,00 Polibag

- MEKANIKAL ELEKTRIKAL
1 Kabel NYY 2x 4mm ME-1 15.000,00 M1
2 Box Terminal MCB 10x15x20+ konektor+klem ME-2 355.000,00 Buah
3 Revisi Box panel ME-3 5.000.000,00 Buah
4 MCB 2 dan 4 A ME-4 65.000,00 Buah
5 Ancoor Ø 12 mm panjang 50 cm ME-5 120.000,00 Buah
6 Lampu PJU 1 Lengan ME-6 10.560.000,00 Buah
7 Lampu PJU 4 Lengan ME-7 12.647.500,00 Buah
NO JENIS TENAGA / BAHAN KODE HARGA SATUAN
8 Lampu PJU 28 w FER 101 ME-8 6.500.000,00 Buah
9 Pilar hidrant two ways ME-9 7.524.000,00 Buah
10 Selang gulung ME-10 3.082.500,00 Set
11 Nozzle ME-11 1.020.000,00 Buah
12 Pipa kembar siam ME-12 4.917.000,00 Buah
13 Pemasangan pipa PVC Ø 300 mm ME-13 525.000,00 M1
14 Taper konsentris 12"-6" ME-14 783.000,00 Buah
15 Akhir pipa 12" ME-15 1.120.500,00 Buah
16 Horizontal bend 90" ME-16 1.275.000,00 Buah
17 Horizontal bend 45" ME-17 1.200.000,00 Buah
18 Tee all flange 12"x3 ME-18 2.655.000,00 Buah
19 Check valve 12" (arrow) ME-19 8.272.500,00 Buah
20 Reducer 12"-6" ME-20 157.500,00 Buah
21 Reducer 6"-4" ME-21 69.000,00 Buah
22 Reducer 4"-2" ME-22 4.500.000,00 Buah
23 Stop kontak + instalasi beton ME-23 76.800,00 Buah
24 Stop kontak antena ME-24 60.000,00 Buah
25 Schakelar (standar) ME-25 14.320,00 Buah
26 Lampu PL 14 watt + armatur down light 4" ME-26 168.000,00 Buah
27 Titik lampu + instalasi beton ME-27 151.840,00 Buah
28 Pengaman lampu tipe 1 ME-28 500.000,00 Buah
29 Lengan lampu tipe 2 ME-29 1.200.000,00 Buah
30 Lampu sorot tipe 1 ME-30 6.960.000,00 Buah
31 Lampu sorot tipe 2 ME-31 15.000.000,00 Buah

- JASA
1 Pemasangan Kabel NYY 2 x 4mm JS-1 35.000,00 M1
2 Pemasangan Box Terminal MCB 10x15x20+ konektor+klem JS-2 100.000,00 Buah
3 Pemasangan MCB 2 dan 4 A JS-3 50.000,00 Buah
4 Pemasangan ancoor Ø 12 mm panjang 50 cm JS-4 50.000,00 Buah
5 Pemasangan Lampu PJU 1 Lengan JS-5 350.000,00 Buah
6 Pemasangan Lampu PJU 4 Lengan JS-6 1.400.000,00 Buah
7 Pemasangan Lampu PJU 28 w FER 101 JS-7 35.000,00 Buah
8 Jasa revisi Box panel JS-8 1.200.000,00 Buah
9 Jasa pengaman lampu tipe 1 JS-9 150.000,00 Buah
10 Jasa pemasangan lengan lampu tipe 2 JS-10 250.000,00 Buah
11 Jasa pemasangan lampu sorot tipe 1 JS-11 100.000,00 Buah
12 Jasa pemasangan lampu sorot tipe 2 JS-12 150.000,00 Buah

- ALAT
1 Sewa Asphatt Mixing Plant ALT-1 5.700.000,00 Jam
2 Sewa Wheel Leader 10-15 HP ALT-2 723.753,03 Jam
3 Sewa Dump Truck 8-10 m3 ALT-3 97.500,00 Jam
4 Sewa Asphatt Finisher ALT-4 1.285.087,50 Jam
5 Sewa Todem Roller ALT-5 335.154,00 Jam
6 Sewa Tire Roller ALT-6 339.540,00 Jam
7 Sewa Alat Bantu ALT-7 1.500,00 Jam
8 Sewa Aspal Spatyer ALT-8 34.500,00 Jam
9 Sewa Compresor ALT-9 112.500,00 Jam
10 Sewa Dump Truck 8-10 m3 ALT-10 97.500,00 Jam

C OVERHEAD DAN KEUNTUNGAN


1 OVERHEAD + KEUNTUNGAN J-1 15%
LAY OUT PLAN
Asrama Haji Palangka Raya
B
C
selasar

toilet pria
rg.ganti rg.ganti
toilet wanita

G
I
J
K
aula serba
selasar guna selasar

selasar
B

L
A

E
F
PAGAR DEPAN DAN GERBANG
Asrama Haji Palangka Raya
ASRAMA HAJI
PALANGKA RAYA
LAMPU PENERANGAN JALAN
Asrama Haji Palangka Raya
0,40
0,40
2.40

0,20
0,40 DETAIL-A (landasan lampu sorot untuk kolom)
SKALA 1 : 20
0,10 0,10
2.60

0,37

besi pelat 27x27x16

0,37
0,27

0,60
0,60
8.00
3.50

0,60
0.20

1,00
plat besi tebal 12 mm plat besi tebal 16 mm

urug tanah kembali


Detail - 1
1.90

1.00

0,50
1,00

0,90
0.60

1,00
TIANG PJU-2 (satu lengan)

0,10
SKALA 1 : 50

rabat beton
0,80
1,00 DETAIL-1
SKALA 1 : 20
2.30 2.30

Detail - 3
DETAIL-3

0,37

besi pelat 27x27x16

0,37
0,27

0,60
8.00
9.00

0,60

0,60

1,00
plat besi tebal 12 mm plat besi tebal 16 mm

Detail - 2 urug tanah kembali


1.00

0,50
1,00

0,90

1,00
TIANG PJU-1 (empat lengan)
SKALA 1 : 50

0,10
rabat beton
0,80
1,00 DETAIL-2
SKALA 1 : 20
TIANG BENDERA
Asrama Haji Palangka Raya
PENERANGAN FASADE BANGUNAN
Asrama Haji Palangka Raya