Anda di halaman 1dari 28

ANALISIS HARGA SATUAN PEKERJA (AHSP) SRAGEN 2021

DAFTAR HARGA UPAH, BAHAN DAN SEWA ALAT

NO. URAIAN KODE SATUAN HARGA KET.


A. UPAH
1 Kepala Tukang OH 105,000.00
2 Tukang OH 95,000.00
3 Tukang Alumunium OH 95,000.00
3 Tukang Batu OH 95,000.00
4 Tukang Besi OH 95,000.00
5 Tukang Cat OH 95,000.00
6 Tukang Ereksi OH 95,000.00
5 Tukang Kayu OH 95,000.00
6 Tukang Las Konstruksi OH 95,000.00
7 Tukang Pipa OH 95,000.00
8 Tukang vibrator OH 95,000.00
6 Pekerja OH 76,000.00
7 Mandor OH 115,000.00
8 Operator Alat Berat OH 150,000.00
9 Operator Alat Pipa OH 150,000.00
9 Operator Crane OH 150,000.00
10 Pembantu Operator Crane OH 100,000.00

B. BAHAN
1 Air Ltr 110.00
2 Air test (air bersih) m³ 70,000.00
2 Akustik 60 x 120 Lembar
3 Akustik ukuran 30 x 30 cm Lembar
4 Akustik ukuran 30 x 60 cm Lembar
5 Alang-alang Ikat
2 Aluminium Composite Panel Lbr
3 Aluminium strip m
4 Alumunium foil m²
5 Alumunium gel tbl 0,55 Lbr
3 Ampelas Lbr
4 Asbes gelombang 92x250 Lbr
5 Asbes semen m²
5 Bahan bakar Liter
4 Bahan tambahan kimia Liter
5 Baja ringan canai dingin C75 batang 130,000.00
6 Baja strip (0,2 x 2) cm Kg
7 Baja tulangan Kg
8 Bak cuci piring Unit 500,000.00
9 Bak fibreglass Unit 250,000.00
10 Balok kayu m³ 1,750,000.00
3 Balok kayu kelas II m³ 1,750,000.00
4 Balok kayu, 6 x 12 Batang 80,000.00
5 Bambu diameter 8 - 10 cm Batang 3,200.00
6 Bata berongga m³
4 Bata merah Bh 800.00
5 Bata pelapis Dinding 3cm x 7cm x 24cm Bh
6 Bata ringan tebal 7,5 cm m³
7 Bata rooster m³
8 Bathcuip Unit
5 Batu Kali/Belah m³ 210,000.00
6 Batu granit Kg 615,000.00
7 Batu paras Dinding Bh
6 Batu pecah m³ 270,300.00
7 Batu traso Kg
18 Baut (Srew driver) Bh 600.00
19 Besi angker dia 8 Kg
7 Besi beton polos 8mm Kg 12,900.00
8 Besi beton polos 10mm Kg 13,300.00
7 Besi hollow 50.50.3 Kg
8 Besi IWF Kg
9 Besi lis kaca (1 x 1) cm m
10 Besi plat baja Kg
11 Besi Profil Kg
12 Besi scuare tube m
13 Besi siku L 30.30.3 Kg
9 Besi strip Kg 12,900.00
10 Bilik bambu m²
11 Bubung stel gel. Lbr
12 Cat antara Kg
13 Cat Besi Kg
14 Cat dasar Besi Kg
15 Cat Dasar Kayu Kg 80,000.00
16 Cat Dasar Tembok Kg
17 Cat menie Kg
18 Cat Penutup Kayu Kg
19 Cat Penutup Tembok Kg 10,500.00
20 Closet Duduk Unit 950,000.00
21 Closet Jongkok Unit
22 Dempul Kg
23 Dinding batu tempel hitam Bh
10 Dolken kayu Ø 8-10/400 cm Btg 10,000.00
11 Door closer Set
12 Door holder Set 40,000.00
13 Door stop Set 28,000.00
14 Dynabol dia 12 x 120 mm Bh 3,300.00
15 Engsel angin Bh
16 Engsel kupu-kupu Bh 25,000.00
17 Engsel pintu Bh 45,000.00
18 Fhiser Bh 100.00
19 Fitting Lampu Bh 11,000.00
20 Floor drain Unit 26,000.00
21 Floor Harderner Unit
22 Formika Lembar
23 Genteng aspal Bh
24 Genteng beton Bh
25 Genteng bubung Bh 5,000.00
26 Genteng kodok Bh 1,700.00
27 Genteng metal Bh 60,000.00
28 Genteng palentong Bh
29 Gypsum board 9 mm (1200 x 2400 mm) Lembar
30 HB-10 m³
31 HB-15 m³
32 HB-20 m³
72 Ijuk Kg
73 Jaring kawat baja dilas Kg
74 Jendela naco Bh
75 Kabel NYM 3x2,5 mm² m 19,000.00
76 Kaca buram 12 mm m²
77 Kaca cermin 5 mm m²
78 Kaca cermin 8 mm m²
79 Kaca patri 5mm m²
80 Kaca polos m²
81 Kaca tebal 3 mm m²
82 Kaca tebal 5 mm m² 135,000.00
83 Kaca tebal 8 mm m²
84 Kaca wireglassed 5mm m²
85 Kait angin Bh 15,000.00
86 Besi beton (8mm-10mm) Kg 26,200.00
11 Kapur Kg 5,000.00
12 Kapur Pasang Kg
13 Kapur sirih Kg
12 Kawat beton Kg 19,000.00
13 Kawat dia 4 mm Kg
14 Kawat duri Kg
15 Kawat jaring Kg
16 Kawat las Kg
17 Kawat las listrik Kg
18 Kawat nyamuk Kg
19 Kayu m³
20 Kayu 5/7 m³
21 Kayu balok 5/7 m³
22 Kayu balok 5/7 kelas III m³
23 Kayu balok borneo m³
13 Kayu kaso 5/7 m³ 3,500,000.00
14 Kayu kelas II m³ 5,500,000.00
15 Kayu kelas II balok m³ 5,500,000.00
16 Kayu kelas III m³ 3,500,000.00
17 Kayu kelas III (papan) m³ 3,500,000.00
18 Kayu Papan m³ 3,500,000.00
19 Kayu papan 3/20 m³ 3,500,000.00
19 Kayu Papan kelas I m³ 7,500,000.00
20 Kayu Papan kelas II m³ 5,500,000.00
21 Kayu papan kelas III m³ 3,500,000.00
22 Keramik artistik 10cm x 10cm atau 5cm x 20cm Bh
23 Keramik artistik 10cm x 20cm Bh
24 Keramik Dinding 10cm x 20cm Bh
25 Keramik Dinding 20cm x 20cm Bh
26 Keramik Dinding artistik Bh
27 Keramik Dinding artistik 5cm x 20cm Bh
28 Keramik mozaik ukuran 30cm x 30cm Bh
29 Keramik ukuran 20cm x 20cm Bh
30 Keramik ukuran 30cm x 30cm Bh
31 Keramik ukuran 60cm x 60cm Bh
22 Kerikil m³ 265,000.00
23 Kerikil (Maks 30 mm) Kg 196.30
24 Klem Pipa Bh
25 Klem Pipa Listrik Bh 600.00
26 Kolom Benton Pracetak Batang
27 Koral m³
28 Koral beton m³
29 Kran air m 15,000.00
30 Kuas Bh
31 Kunci lemari Bh
32 Kunci silinder Bh
33 Kunci slot Bh
34 Kunci tanam Bh
35 Kunci tanam antik Bh
36 Kunci tanam biasa Bh 130,000.00
37 Kunci tanam KM Bh 60,000.00
38 L.Bow Bh 1,000.00
39 Lantai Karpet m²
40 Lantai Kerja tebal 10cm m²
41 Las Dop Bh 200.00
24 Lem Kayu/Karet Kg 25,000.00
marmer Dinding 100cm x 100cm Bh
marmer ukuran 60cm x 60cm Bh 50,625.00
25 Meni besi Liter 30,000.00
26 Menie A Liter
27 Menie B Liter
28 Menie besi Liter
26 Minyak bekisting Liter 30,000.00
27 Minyak pelumas Liter
28 Mangkok (Listrik) Bh 2,500.00
29 Mortar siap pakai Kg
30 Nok genteng aspal Bh
31 Nok genteng beton Bh
32 Nok genteng metal Bh
33 Nok paten 92cm Bh
34 Nok standar 40x18 Bh
152 Oli Liter
27 Paku 2”-3” Kg 15,000.00
28 Paku 5 - 10 cm Kg 15,000.00
29 Paku Biasa Kg 15,000.00
30 Paku biasa ½”-1” Kg 15,000.00
31 Paku biasa 2” - 5” Kg
32 Paku hak panj 15cm Kg
33 Paku pancing 6x23 Kg
34 Paku skrup Kg
30 Paku tripleks Kg 30,000.00
31 Panel Beton Pracetak Lbr
32 Parquet kayu m²
33 Parquet kayu gymfloor m²
31 Pasir Beton m³ 248,500.00
32 Pasir Beton (Kg) Kg 177.50
33 Pasir Pasang m³ 263,500.00
34 Pasir Urug m³ 118,800.00
35 Paving block 6 cm m²
36 Paving block 6cm berwarna m²
37 Paving block 8 cm berwarna m²
38 Paving block 8 cm natural m²
39 Pengencer Kg 50,000.00
40 Pengelasan cm
35 Penjaga jarak bekisting / spacer Buah 5,000.00
36 Perancah kayu m³
37 Phenol film 12mm Lbr
38 Pintu alluminium m
39 Pintu gulung besi m²
40 Pintu lipat m²
41 Pipa Baja Ø 100 mm m
42 Pipa Baja Ø 1000 mm m
43 Pipa Baja Ø 1100 mm m
44 Pipa Baja Ø 1200 mm m
45 Pipa Baja Ø 125 mm m
46 Pipa Baja Ø 150 mm m
47 Pipa Baja Ø 200 mm m
48 Pipa Baja Ø 250 mm m
49 Pipa Baja Ø 300 mm m
50 Pipa Baja Ø 400 mm m
51 Pipa Baja Ø 450 mm m
52 Pipa Baja Ø 500 mm m
53 Pipa Baja Ø 600 mm m
54 Pipa Baja Ø 63 mm m
55 Pipa Baja Ø 800 mm m
56 Pipa Baja Ø 900 mm m
57 Pipa Beton Bh
58 Pipa Conduit m 6,500.00
59 Pipa DCI Ø 100 mm m
60 Pipa DCI Ø 1000 mm m
61 Pipa DCI Ø 1100 mm m
62 Pipa DCI Ø 1200 mm m
63 Pipa DCI Ø 125 mm m
64 Pipa DCI Ø 150 mm m
65 Pipa DCI Ø 200 mm m
66 Pipa DCI Ø 250 mm m
67 Pipa DCI Ø 300 mm m
68 Pipa DCI Ø 400 mm m
69 Pipa DCI Ø 450 mm m
70 Pipa DCI Ø 500 mm m
71 Pipa DCI Ø 600 mm m
72 Pipa DCI Ø 800 mm m
73 Pipa DCI Ø 900 mm m
74 Pipa galvanis ½” m
75 Pipa galvanis 1” m
76 Pipa galvanis 11/2” m
77 Pipa galvanis 3/4” m
78 Pipa galvanis 3” m
79 Pipa galvanis 4” m
80 Pipa GIP Ø 100 mm m
81 Pipa GIP Ø 1000 mm m
82 Pipa GIP Ø 1100 mm m
83 Pipa GIP Ø 1200 mm m
84 Pipa GIP Ø 125 mm m
85 Pipa GIP Ø 150 mm m
86 Pipa GIP Ø 200 mm m
87 Pipa GIP Ø 250 mm m
88 Pipa GIP Ø 300 mm m
89 Pipa GIP Ø 400 mm m
90 Pipa GIP Ø 450 mm m
91 Pipa GIP Ø 500 mm m
92 Pipa GIP Ø 600 mm m
93 Pipa GIP Ø 63 mm m
94 Pipa GIP Ø 800 mm m
95 Pipa GIP Ø 900 mm m
96 Pipa HDPE Ø 100 mm Bh
97 Pipa HDPE Ø 1000 mm Bh
98 Pipa HDPE Ø 1100 mm Bh
99 Pipa HDPE Ø 1200 mm Bh
100 Pipa HDPE Ø 125 mm Bh
101 Pipa HDPE Ø 150 mm Bh
102 Pipa HDPE Ø 200 mm Bh
103 Pipa HDPE Ø 250 mm Bh
104 Pipa HDPE Ø 300 mm Bh
105 Pipa HDPE Ø 400 mm Bh
106 Pipa HDPE Ø 450 mm Bh
107 Pipa HDPE Ø 500 mm Bh
108 Pipa HDPE Ø 600 mm Bh
109 Pipa HDPE Ø 63 mm Bh
110 Pipa HDPE Ø 800 mm Bh
111 Pipa HDPE Ø 900 mm Bh
112 Pipa listrik 5/8” Btg
113 Pipa Ø 100 mm Bh
114 Pipa Ø 150 mm Bh
115 Pipa Ø 200 mm Bh
116 Pipa Ø 250 mm Bh
117 Pipa Ø 300 mm Bh
118 Pipa Ø 400 mm Bh
119 Pipa Ø 450 mm Bh
120 Pipa Ø 500 mm Bh
121 Pipa Ø 600 mm Bh
122 Pipa Ø 700 mm Bh
123 Pipa Ø 80 mm Bh
124 Pipa Ø 800 mm Bh
125 Pipa PVC 1/2” m 30,000.00
126 Pipa PVC 1” m
127 Pipa PVC 11/2” m
128 Pipa PVC 2” m
129 Pipa PVC 21/2” m
130 Pipa PVC 3/4” m
131 Pipa PVC 3” m
132 Pipa PVC 4” m
133 Pipa PVC Ø 1000 mm m
134 Pipa PVC Ø 110 mm m
135 Pipa PVC Ø 1100 mm m
136 Pipa PVC Ø 1200 mm m
137 Pipa PVC Ø 150 mm m
138 Pipa PVC Ø 200 mm m
139 Pipa PVC Ø 250 mm m
140 Pipa PVC Ø 300 mm m
141 Pipa PVC Ø 400 mm m
142 Pipa PVC Ø 450 mm m
143 Pipa PVC Ø 500 mm m
144 Pipa PVC Ø 600 mm m
145 Pipa PVC Ø 63 mm m
146 Pipa PVC Ø 800 mm m
147 Pipa PVC Ø 90 mm m
148 Pipa PVC Ø 900 mm m
41 Pipa tanah Bh 165,000.00
42 Plafond PVC m² 25,000.00
175 Plamur Kg 6,000.00
176 List PVC m 13,000.00
177 Plint internal cove artistik 5cm x 5cm x 20cm Bh
178 Plint keramik ukuran 10cm x 10cm Bh
179 Plint keramik ukuran 10cm x 20cm Bh
180 Plint keramik ukuran 5cm x 20cm Bh
181 Plint ubin granit ukuran 10cm x 30cm Bh
182 Plint ubin granit ukuran 10cm x 40cm Bh
183 Plint ubin Pc abu-abu ukuran 10cm x 30cm Bh
184 Plint ubin Pc abu-abu ukuran 10cm x 40cm Bh
185 Plint ubin Pc abu-abu ukuran 15cm x 20cm Bh
186 Plint ubin teralux kerang ukuran 10cm x 30cm Bh
187 Plint ubin teralux kerang ukuran 10cm x 40cm Bh
188 Plint ubin teralux marmer ukuran 10cm x 30cm Bh
189 Plint ubin teralux marmer ukuran 10cm x 40cm Bh
190 plint ubin teralux marmer ukuran 10cm x 60cm Bh
191 Plint ubin teraso ukuran 10cm x 30cm Bh
192 Plint ubin teraso ukuran 10cm x 40cm Bh
193 Plint ubin warna ukuran 10cm x 20cm Bh
194 Plint ubin warna ukuran 10cm x 30cm Bh
195 Plint ubin warna ukuran 10cm x 40cm Bh
196 plint vynil 15cm x 30cm Bh
36 Plywood 4 mm Lembar 95,000.00
37 Plywood 6 mm Lembar 115,000.00
38 Plywood 9 mm Lembar 135,000.00
39 Politur L
40 Politur jadi L
41 Porselen 11x11 BH
42 Porselen Dinding 10x20 BH
43 Porselen Dinding 11x11 BH
44 Porselen Dinding 20x20 BH
45 Profil Allum"T" M
46 Profil alluminium M
47 Profil kaca M
48 Ramset Buah
49 Rangka metal hollow 40.40.2 mm M1
50 Rel pintu sorong Set
51 Reng (3 x 4) cm m³
52 Reng 2 x 3 cm m³
53 Reng Canai Dingin M1 7,000.00
54 Residu atau ter Ltr
55 Rolling dor alluminium m²
56 Rooflight 90x180 m²
57 Sabun Kg
58 Saklar (standar) Bh 11,500.00
59 Screening Kg
60 Screw Bh 80.00
61 Sealant Kg
62 Sealtape Bh 1,200.00
63 Sealtape Listrik Bh 5,000.00
64 Semen grout Kg
65 Semen Merah Kg
66 Semen Mortar pasangan Kg
67 Semen Mortar Acian Kg
39 Semen portland Kg 1,450.00
40 Semen Warna Kg 15,000.00
41 Seng gelombang Lbr
42 Seng plat Lbr
43 Sirap kayu Bh
40 Sirtu m³ 132,500.00
41 Skrup fixer Buah
42 Socket Pipa Bh 800.00
43 Soda api Kg
41 Solar Ltr 9,800.00
42 Spring knip Bh
43 Strorox - 100 Kg
44 Sunscreen alluminium m²
45 Talang / Jurai Canai Dingin M1 26,600.00
46 Tali ijuk Kg 4,300.00
47 Tanah Liat m³
42 Tanah Timbun m³ 73,000.00
43 Teak oil Ltr
44 Teakwood 4 mm 90 x 220 cm Lembar
45 Teakwood 4 mm, 120 x 240 Lembar
46 Tee Doos Bh 12,000.00
47 Tee Ø 1000 mm Bh
48 Tee Ø 1100 mm Bh
49 Tee Ø 1200 mm Bh
50 Tee Ø 150 mm Bh
51 Tee Ø 250 mm Bh
52 Tee Ø 300 mm Bh
53 Tee Ø 400 mm Bh
54 Tee Ø 450 mm Bh
55 Tee Ø 500 mm Bh
56 Tee Ø 600 mm Bh
57 Tee Ø 700 mm Bh
58 Tee Ø 800 mm Bh
59 Tee Ø 900 mm Bh
269 Teraso cor di tempat, tebal 3cm m³
270 ubin granit ukuran 30cm x30cm Bh
271 ubin granit ukuran 60cm x60cm Bh 50,625.00
272 Ubin keramik Bh
273 ubin PC abu-abu ukuran 20cm x20 cm Bh
274 ubin PC abu-abu ukuran 30cm x30 cm Bh
275 ubin PC abu-abu ukuran 40cm x40cm Bh
276 ubin teralux marmer ukuran 30cm x30cm Bh
277 ubin teralux marmer ukuran 40cm x40cm Bh 70,000.00
278 ubin teralux marmer ukuran 60cm x60cm Bh
279 ubin teralux ukuran 30cm x30cm Bh
280 ubin teraso ukuran 30cm x30cm Bh
281 ubin teraso ukuran 40cm x40cm Bh
282 ubin warna ukuran 20cm x20cm Bh
283 ubin warna ukuran 30cm x30cm Bh 4,500.00
284 ubin warna ukuran 40cm x40 cm Bh
270 underlayer (pelapis bawah karpet) Bh
271 Urinoir Unit
272 Valve Ø 1000 mm Bh
273 Valve Ø 1100 mm Bh
274 Valve Ø 1200 mm Bh
275 Valve Ø 150 mm Bh
276 Valve Ø 200 mm Bh
277 Valve Ø 250 mm Bh
278 Valve Ø 300 mm Bh
279 Valve Ø 400 mm Bh
280 Valve Ø 450 mm Bh
281 Valve Ø 500 mm Bh
282 Valve Ø 600 mm Bh
283 Valve Ø 700 mm Bh
284 Valve Ø 800 mm Bh
285 Valve Ø 900 mm Bh
272 Venetions Blinds dan vertical blinds (tirai) m²
273 Vernis Ltr
274 Vynil ukuran 30cm x 30cm Bh
275 Wallpaper M
276 Wallpaper lebar 50 cm M
277 Wastafel Unit
278 Waterdrain Bh 20,000.00
279 Waterstop lebar 150 mm m
280 Waterstop lebar 200 mm m
281 Waterstop lebar 230 mm - 320 mm m

C. ALAT
1 Alat Rangka Atap Baja Canai Dingin
2 Mobile Crane =< 3 ton
3 Peralatan Kerja Paving Blok
4 Peralatan Pasang Dinding Bata Ringan
5 Peralatan potong pipa T1/manual (gergaji) /saw
6 Peralatan potong pipa T2/mekanik / cilinder
7 Peralatan potong pipa T2/mekanik / cilinder saw
8 Sewa alat Las Listrik
9 Sewa alat Perakitan Baja IWF
10 Sewa crane
11 Sewa excavator type 225 kap 0,5 -1,0 m³
12 Sewa Genset 1500 watt
13 Sewa pipe support
14 Sewa Pompa Submersible 3m³/h
15 Sewa Tripot/Tackel & handle crane 2 T
ANALISIS HARGA SATUAN PEKERJA (AHSP) - SRAGEN 2021
DAFTAR HARGA SATUAN DAN BAHAN

A.2.2.1.1. (K3) Pengukuran dan pemasangan 1 m² Bouwplank


No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)
A TENAGA
Pekerja L.01.01 OH 0.1 76,000.00 7,600.00
Tukang Kayu L.02.04 OH 0.1 95,000.00 9,500.00
Kepala Tukang L.03.01 OH 0.01 105,000.00 1,050.00
Mandor L.04.01 OH 0.005 115,000.00 575.00
JUMLAH TENAGA KERJA 18,725.00
B BAHAN
Dolken kayu Ø 8-10/400 cm Batang 1.25 10,000.00 12,500.00
Semen Portland Kg 5 - -
Pasir beton m³ 0.005 248,500.00 1,242.50
Koral beton m³ 0.009 - -
Kayu 5/7 m³ 0.072 - -
Paku biasa Kg 0.06 15,000.00 900.00
Residu atau ter Liter 0.4 - -
JUMLAH HARGA BAHAN 14,642.50
C PERALATAN
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 33,367.50
E Overhead & Profit 10% 10% 3,336.75
F Harga Satuan Pekerjaan (D+E) 36,704.25

A.2.2.1.2 (K3) Pembuatan 1 m² Bedeng pekerja


No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)
A TENAGA
Pekerja L.01.01 OH 0.2 76,000.00 15,200.00
Tukang Kayu L.02.04 OH 0.4 95,000.00 38,000.00
Kepala Tukang L.03.01 OH 0.02 105,000.00 2,100.00
Mandor L.04.01 OH 0.02 115,000.00 2,300.00
JUMLAH TENAGA KERJA 57,600.00
B BAHAN
Dolken kayu Ø 8-10/400 cm Batang 1.25 10,000.00 12,500.00
Semen Portland Kg 2.5 1,450.00 3,625.00
Seng gelombang Lbr 1.2 - -
Pasir beton m³ 0.005 248,500.00 8.00
Koral beton m³ 0.009 - -
Kayu 5/7 m³ 0.072 - -
Paku biasa Kg 0.06 15,000.00 900.00
Meni besi Liter 0.45 30,000.00 13,500.00
JUMLAH HARGA BAHAN 31,767.50
C PERALATAN
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 89,367.50
E Overhead & Profit 10% 0.1 8,936.75
F Harga Satuan Pekerjaan (D+E) 98,304.00

A.2.2.1.3. Pembersihan 1 m² Lapangan dan peralatan


No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)
A TENAGA
Pekerja L.01.01 OH 0.2 76,000.00 15,200.00
Tukang Kayu L.02.04 OH 0.3 95,000.00 28,500.00
Kepala Tukang L.03.01 OH 0.02 105,000.00 2,100.00
Mandor L.04.01 OH 0.02 115,000.00 2,300.00
JUMLAH TENAGA KERJA 48,100.00
B BAHAN
Dolken kayu Ø 8-10/400 cm Batang 1 10,000.00 10,000.00
Semen Portland Kg 2 1,450.00 2,900.00
Kawat duri M’ 25 - -
Pasir beton m³ 0.005 248,500.00 1,242.50
Koral beton m³ 0.009 - -
Paku biasa 2” - 5” Kg 0.06 - -
JUMLAH HARGA BAHAN 14,142.50
C PERALATAN
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 62,242.50
E Overhead & Profit 10% 0.1 6,224.25
F Harga Satuan Pekerjaan (D+E) 68,466.00

A.2.2.1.11. Pembuatan 1 buah kotak adukan ukuran 40cm x50cm x25cm


No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)
A TENAGA
Tukang Kayu L.02.04 OH 0.3 95,000.00 28,500.00
Kepala Tukang L.03.01 OH 0.03 105,000.00 3,150.00
JUMLAH TENAGA KERJA 31,650.00
B BAHAN
Kayu papan kelas III m³ 0.036 3,500,000.00 126,000.00
Kayu balok 5/7 kelas III m³ 0.021 - -
Paku biasa Kg 0.08 15,000.00 1,200.00
JUMLAH HARGA BAHAN 127,200.00
C PERALATAN
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 158,850.00
E Overhead & Profit 10% 0.1 15,885.00
F Harga Satuan Pekerjaan (D+E) 174,735.00

A.2.3.1 HARGA SATUAN PEKERJAAN TANAH

A.2.3.1.1. Penggalian 1 m³ tanah biasa sedalam 1 m

No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)
A TENAGA
Pekerja L.01.01 OH 0.75 76,000.00 57,000.00
Mandor L.04.01 OH 0.025 115,000.00 2,875.00
JUMLAH TENAGA KERJA 59,875.00
B BAHAN
JUMLAH HARGA BAHAN -
C PERALATAN
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 59,875.00
E Overhead & Profit 10% 0.1 5,987.50
F Harga Satuan Pekerjaan (D+E) 65,862.00

A.2.3.1.9. Pengurugan kembali 1 m³ galian tanah Tanah Biasa Sedalam 1m


Pengurugan kembali 1 m³ galian dihitung dari 1/3 kali dari koefisien pekerjaan galian
No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)
A TENAGA
Pekerja L.01.01 OH 0.25 76,000.00 19,000.00
Mandor L.04.01 OH 0.025 115,000.00 2,875.00
JUMLAH TENAGA KERJA 21,875.00
B BAHAN
JUMLAH HARGA BAHAN
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) 21,875.00
E Overhead & Profit 10% 0.1 2,187.50
F Harga Satuan Pekerjaan (D+E) 24,062.00

A.2.3.1.11. Pengurugan 1 m³ dengan pasir urug dibawah pondasi


No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)
A TENAGA
Pekerja L.01.01 OH 0.3 76,000.00 22,800.00
Mandor L.04.01 OH 0.01 115,000.00 1,150.00
JUMLAH TENAGA KERJA 23,950.00
B BAHAN
Pasir urug m³ 1.2 118,800.00 142,560.00
JUMLAH HARGA BAHAN 142,560.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) 166,510.00
E Overhead & Profit 10% 0.1 16,651.00
F Harga Satuan Pekerjaan (D+E) 183,161.00

A.3.2.1 HARGA SATUAN PEKERJAAN PONDASI

A.3.2.1.4. Pemasangan 1 m³ pondasi Batu Kali/Belah campuran 1SP : 6PP 2.4

No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)
A TENAGA
Pekerja L.01.01 OH 1.5 76,000.00 114,000.00
Tukang Batu L.02.03 OH 0.75 95,000.00 71,250.00
Kepala Tukang L.03.01 OH 0.075 105,000.00 7,875.00
Mandor L.04.01 OH 0.075 115,000.00 8,625.00
JUMLAH TENAGA KERJA 201,750.00
B BAHAN
Batu Kali/Belah m³ 1.2 210,000.00 252,000.00
Semen Portland Kg 117 1,450.00 169,650.00
Pasir Pasang m³ 0.561 263,500.00 147,823.50
JUMLAH HARGA BAHAN 569,473.50
C PERALATAN
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 771,223.50
E Overhead & Profit 10% 0.1 77,122.35
F Harga Satuan Pekerjaan (D+E) 848,345.00

A.3.2.1.9. Pemasangan 1 m³ batu kosong (anstamping) 1.248


No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)
A TENAGA
Pekerja L.01.01 OH 0.78 76,000.00 59,280.00
Tukang Batu L.02.03 OH 0.39 95,000.00 37,050.00
Kepala Tukang L.03.01 OH 0.039 105,000.00 4,095.00
Mandor L.04.01 OH 0.039 115,000.00 4,485.00
JUMLAH TENAGA KERJA 104,910.00
B BAHAN
Batu Kali/Belah m³ 1.2 210,000.00 252,000.00
Pasir urug m³ 0.432 118,800.00 51,321.60
JUMLAH HARGA BAHAN 303,321.60
C PERALATAN
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 408,231.60
E Overhead & Profit 10% 0.1 40,823.16
F Harga Satuan Pekerjaan (D+E) 449,054.00

A.4.1.1.20 (K3) Pemasangan 1 m² bekisting untuk pondasi


No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)
A TENAGA
Pekerja L.01.01 OH 0.52 76,000.00 39,520.00
Tukang Kayu L.02.04 OH 0.26 95,000.00 24,700.00
Kepala Tukang L.03.01 OH 0.026 105,000.00 2,730.00
Mandor L.04.01 OH 0.026 115,000.00 2,990.00
JUMLAH TENAGA KERJA 69,940.00
B BAHAN
Kayu kelas III m³ 0.04 3,500,000.00 140,000.00
Paku 5 - 10 cm Kg 0.3 15,000.00 4,500.00
Minyak bekisting Liter 0.1 30,000.00 3,000.00
JUMLAH HARGA BAHAN 147,500.00
C PERALATAN
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 217,440.00
E Overhead & Profit 10% 0.1 21,744.00
F Harga Satuan Pekerjaan (D+E) 239,184.00
G Untuk 2 x Pemakaian 119,592.00

A.4.1.1.21 (K3) Pemasangan 1 m² bekisting untuk sloof


No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)
A TENAGA
Pekerja L.01.01 OH 0.52 76,000.00 39,520.00
Tukang Kayu L.02.04 OH 0.26 95,000.00 24,700.00
Kepala Tukang L.03.01 OH 0.026 105,000.00 2,730.00
Mandor L.04.01 OH 0.026 115,000.00 2,990.00
JUMLAH TENAGA KERJA 69,940.00
B BAHAN
Kayu kelas III m³ 0.045 3,500,000.00 157,500.00
Paku 5 - 10 cm Kg 0.3 15,000.00 4,500.00
Minyak bekisting Liter 0.1 30,000.00 3,000.00
JUMLAH HARGA BAHAN 165,000.00
C PERALATAN
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 234,940.00
E Overhead & Profit 10% 0.1 23,494.00
F Harga Satuan Pekerjaan (D+E) 258,434.00
G Untuk 2 x Pemakaian 129,217.00

A.4.1.1.22 Pemasangan 1 m² bekisting untuk sloof


No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)
A TENAGA
Pekerja L.01.01 OH 0.66 76,000.00 50,160.00
Tukang Kayu L.02.04 OH 0.33 95,000.00 31,350.00
Kepala Tukang L.03.01 OH 0.033 105,000.00 3,465.00
Mandor L.04.01 OH 0.033 115,000.00 3,795.00
JUMLAH TENAGA KERJA 88,770.00
B BAHAN
Kayu kelas III m³ 0.04 3,500,000.00 140,000.00
Paku Biasa Kg 0.4 15,000.00 6,000.00
Minyak bekisting Liter 0.2 30,000.00 6,000.00
Balok kayu kelas II m³ 0.015 1,750,000.00 26,250.00
Plywood 9 mm Lbr 0.35 135,000.00 47,250.00
Dolken kayu Ø 8-10/400 cm Batang 2 10,000.00 20,000.00
JUMLAH HARGA BAHAN 245,500.00
C PERALATAN
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 334,270.00
E Overhead & Profit 10% 0.1 33,427.00
F Harga Satuan Pekerjaan (D+E) 367,697.00
G Untuk 2 x Pemakaian 183,848.50
A.4.1.1.23 (K3) Pemasangan 1 m² bekisting untuk balok
No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)
A TENAGA
Pekerja L.01.01 OH 0.66 76,000.00 50,160.00
Tukang Kayu L.02.04 OH 0.33 95,000.00 31,350.00
Kepala Tukang L.03.01 OH 0.033 105,000.00 3,465.00
Mandor L.04.01 OH 0.033 115,000.00 3,795.00
JUMLAH TENAGA KERJA 88,770.00
B BAHAN
Kayu kelas III m³ 0.04 3,500,000.00 140,000.00
Paku Biasa Kg 0.4 15,000.00 6,000.00
Minyak bekisting Liter 0.2 30,000.00 6,000.00
Balok kayu kelas II m³ 0.018 1,750,000.00 31,500.00
Plywood 9 mm Lbr 0.35 135,000.00 47,250.00
Dolken kayu Ø 8-10/400 cm Batang 2 10,000.00 20,000.00
JUMLAH HARGA BAHAN 250,750.00
C PERALATAN
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 339,520.00
E Overhead & Profit 10% 0.1 33,952.00
F Harga Satuan Pekerjaan (D+E) 373,472.00

A.4.1.1.24 (K3) Pemasangan 1 m² bekisting untuk lantai


No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)
A TENAGA
Pekerja L.01.01 OH 0.66 76,000.00 50,160.00
Tukang Kayu L.02.04 OH 0.33 95,000.00 31,350.00
Kepala Tukang L.03.01 OH 0.033 105,000.00 3,465.00
Mandor L.04.01 OH 0.033 115,000.00 3,795.00
JUMLAH TENAGA KERJA 88,770.00
B BAHAN
Kayu kelas III m³ 0.04 3,500,000.00 140,000.00
Paku Biasa Kg 0.4 15,000.00 6,000.00
Minyak bekisting Liter 0.2 30,000.00 6,000.00
Balok kayu kelas II m³ 0.015 1,750,000.00 26,250.00
Plywood 9 mm Lbr 0.35 135,000.00 47,250.00
Dolken kayu Ø 8-10/400 cm Batang 6 10,000.00 60,000.00
JUMLAH HARGA BAHAN 285,500.00
C PERALATAN
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 374,270.00
E Overhead & Profit 10% 0.1 37,427.00
F Harga Satuan Pekerjaan (D+E) 411,697.00

A.4.1.1.25 (K3) Pemasangan 1 m² bekisting untuk dinding


No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)
A TENAGA
Pekerja L.01.01 OH 0.66 76,000.00 50,160.00
Tukang Kayu L.02.04 OH 0.33 95,000.00 31,350.00
Kepala Tukang L.03.01 OH 0.033 105,000.00 3,465.00
Mandor L.04.01 OH 0.033 115,000.00 3,795.00
JUMLAH TENAGA KERJA 88,770.00
B BAHAN
Kayu kelas III m³ 0.03 3,500,000.00 105,000.00
Paku Biasa Kg 0.4 15,000.00 6,000.00
Minyak bekisting Liter 0.2 30,000.00 6,000.00
Balok kayu kelas II m³ 0.02 1,750,000.00 35,000.00
Plywood 9 mm Lbr 0.35 135,000.00 47,250.00
Dolken kayu Ø 8-10/400 cm Batang 3 10,000.00 30,000.00
Penjaga jarak bekisting / spacer Buah 4 5,000.00 20,000.00
JUMLAH HARGA BAHAN 249,250.00
C PERALATAN
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 338,020.00
E Overhead & Profit 10% 0.1 33,802.00
F Harga Satuan Pekerjaan (D+E) 371,822.00

A.4.1.1.29 Membuat 1 m³ sloof beton bertulang 15 X 20cm

No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)
A TENAGA
Pekerja L.01.01 OH 5.65 76,000.00 429,400.00
Tukang batu L.02.03 OH 0.275 95,000.00 26,125.00
Tukang kayu L.02.04 OH 1.56 95,000.00 148,200.00
Tukang besi L.02.05 OH 1.4 95,000.00 133,000.00
Kepala tukang L.03.01 OH 0.323 105,000.00 33,915.00
Mandor L.04.01 OH 0.283 115,000.00 32,545.00
JUMLAH TENAGA KERJA 803,185.00
B BAHAN
Kayu kelas III m³ 0.27 3,500,000.00 945,000.00
Paku Biasa Kg 0.3 15,000.00 4,500.00
Minyak bekisting Liter 0.1 30,000.00 3,000.00
Besi beton (8mm-10mm) Kg 172.543 26,200.00 4,520,626.60
Kawat beton Kg 3 19,000.00 57,000.00
Semen Portland Kg 336 1,450.00 487,200.00
Pasir Beton m³ 0.54 248,500.00 134,190.00
Kerikil m³ 0.81 265,000.00 214,650.00
JUMLAH HARGA BAHAN 6,366,166.60
C PERALATAN
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 7,169,351.60
E Overhead & Profit 10% 0.1 716,935.16
F Harga Satuan Pekerjaan (D+E) 7,886,286.00

A.4.1.1.30 Membuat 1 m³ kolom beton bertulang 15 X 15cm


No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)
A TENAGA
Pekerja L.01.01 OH 7.05 76,000.00 535,800.00
Tukang batu L.02.03 OH 0.275 95,000.00 26,125.00
Tukang kayu L.02.04 OH 1.65 95,000.00 156,750.00
Tukang besi L.02.05 OH 2.1 95,000.00 199,500.00
Kepala tukang L.03.01 OH 0.403 105,000.00 42,315.00
Mandor L.04.01 OH 0.353 115,000.00 40,595.00
JUMLAH TENAGA KERJA 1,001,085.00
B BAHAN
Kayu kelas III m³ 0.4 3,500,000.00 1,400,000.00
Paku Biasa Kg 0.3 15,000.00 4,500.00
Minyak bekisting Liter 0.1 30,000.00 3,000.00
besi beton (8mm-10mm) Kg 238.0889 26,200.00 6,237,929.18
Kawat beton Kg 4.5 19,000.00 85,500.00
Semen Portland Kg 336 1,450.00 487,200.00
Pasir Beton m³ 0.54 248,500.00 134,190.00
Kerikil m³ 0.81 265,000.00 214,650.00
Kayu kelas II balok m³ 0.015 5,500,000.00 82,500.00
Plywood 9 mm Lbr 0.35 135,000.00 47,250.00
Dolken kayu Ø 8-10/400 cm Batang 2 10,000.00 20,000.00
JUMLAH HARGA BAHAN 8,716,719.18
C PERALATAN
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 9,717,804.18
E Overhead & Profit 10% 0.1 971,780.42
F Harga Satuan Pekerjaan (D+E) 10,689,584.00

A.4.1.1.36 Membuat 1 m’ ring balok beton bertulang (15 x 15) cm

No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)
A TENAGA
Pekerja L.01.01 OH 0.297 76,000.00 22,572.00
Tukang batu L.02.03 OH 0.033 95,000.00 3,135.00
Tukang kayu L.02.04 OH 0.033 95,000.00 3,135.00
Tukang besi L.02.05 OH 0.033 95,000.00 3,135.00
Kepala tukang L.03.01 OH 0.01 105,000.00 1,050.00
Mandor L.04.01 OH 0.015 115,000.00 1,725.00
JUMLAH TENAGA KERJA 34,752.00
B BAHAN
Kayu kelas III m³ 0.003 3,500,000.00 10,500.00
Paku Biasa Kg 0.02 15,000.00 300.00
Minyak bekisting Liter 1.2 30,000.00 36,000.00
Besi beton (8mm-10mm) Kg 3.6 26,200.00 94,320.00
Kawat beton Kg 0.05 19,000.00 950.00
Semen Portland Kg 5.5 1,450.00 7,975.00
Pasir Beton m³ 0.009 248,500.00 2,236.50
Kerikil m³ 0.015 265,000.00 3,975.00
JUMLAH HARGA BAHAN 156,256.50
C PERALATAN
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 191,008.50
E Overhead & Profit 10% 0.1 19,100.85
F Harga Satuan Pekerjaan (D+E) 210,109.00

A.4.4.1.10 Pemasangan 1m² dinding bata merah (5x11x22)cm tebal ½ batu campuran 1 SP : 5 PP
No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)
A TENAGA
Pekerja L.01.01 OH 0.3 76,000.00 22,800.00
Tukang Batu L.02.03 OH 0.1 95,000.00 9,500.00
Kepala Tukang L.03.01 OH 0.01 105,000.00 1,050.00
Mandor L.04.01 OH 0.015 115,000.00 1,725.00
JUMLAH TENAGA KERJA 35,075.00
B BAHAN
Bata merah m³ 70 800.00 56,000.00
Semen Portland Kg 9.68 1,450.00 14,036.00
Pasir Pasang m³ 0.045 263,500.00 11,857.50
JUMLAH HARGA BAHAN 81,893.50
C PERALATAN
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 116,968.50
E Overhead & Profit 10% 0.1 11,696.85
F Harga Satuan Pekerjaan (D+E) 128,665.00

A.4.4.2.15. Pemasangan 1 m² plesteran 1SP : 4PP tebal 20 mm.


No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)
A TENAGA
Pekerja L.01.01 OH 0.4 76,000.00 30,400.00
Tukang Batu L.02.03 OH 0.2 95,000.00 19,000.00
Kepala Tukang L.03.01 OH 0.02 105,000.00 2,100.00
Mandor L.04.01 OH 0.022 115,000.00 2,530.00
JUMLAH TENAGA KERJA 54,030.00
B BAHAN
Semen Portland Kg 8.32 1,450.00 12,064.00
Pasir Pasang m³ 0.032 263,500.00 8,432.00
JUMLAH HARGA BAHAN 20,496.00
C PERALATAN
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 74,526.00
E Overhead & Profit 10% 0.1 7,452.60
F Harga Satuan Pekerjaan (D+E) 81,978.00

A.4.4.3.24. Pemasangan 1 m’ plint ubin granit ukuran 60cm x 60cm


No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)
A TENAGA
Pekerja L.01.01 OH 0.09 76,000.00 6,840.00
Tukang Batu L.02.03 OH 0.09 95,000.00 8,550.00
Kepala tukang L.03.01 OH 0.009 105,000.00 945.00
Mandor L.04.01 OH 0.005 115,000.00 575.00
JUMLAH TENAGA KERJA 16,910.00
B BAHAN
ubin granit ukuran 60cm x60cm Bh 2.65 50,625.00 134,156.25
Semen Portland Kg 1.14 1,450.00 1,653.00
Semen Warna Kg 0.1 15,000.00 1,500.00
Pasir Pasang m³ 0.003 263,500.00 790.50
JUMLAH HARGA BAHAN 138,099.75
C PERALATAN
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 155,009.75
E Overhead & Profit 10% 0.1 15,500.98
F Harga Satuan Pekerjaan (D+E) 170,510.00

A.4.5.1.7. Pemasangan 1 m² langit-langit gypsum board ukuran (120x240x9) mm, tebal 9 mm


No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)
A TENAGA
Pekerja L.01.01 OH 0.1 76,000.00 7,600.00
Tukang kayu L.02.04 OH 0.05 95,000.00 4,750.00
Kepala tukang L.03.01 OH 0.005 105,000.00 525.00
Mandor L.04.01 OH 0.005 115,000.00 575.00
JUMLAH TENAGA KERJA 13,450.00
B BAHAN
Gypsum board 9 mm (1200 x 2400 mm) Lembar 0.364 - -
Paku skrup Kg 0.11 - -
JUMLAH HARGA BAHAN -
C PERALATAN
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 13,450.00
E Overhead & Profit 10% 0.1 1,345.00
F Harga Satuan Pekerjaan (D+E) 14,795.00

A.4.5.1.10. Pemasangan 1 m² Plafond PVC


No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)
A TENAGA
Pekerja L.01.01 OH 0.15 76,000.00 11,400.00
Tukang Kayu L.02.04 OH 0.25 95,000.00 23,750.00
Kepala tukang L.03.01 OH 0.025 105,000.00 2,625.00
Mandor L.04.01 OH 0.075 115,000.00 8,625.00
JUMLAH TENAGA KERJA 46,400.00
B BAHAN
Plafond PVC m² 1.05 25,000.00 26,250.00
Screw bh 18 80.00 1,440.00
JUMLAH HARGA BAHAN 27,690.00
C PERALATAN
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 74,090.00
E Overhead & Profit 10% 0.1 7,409.00
F Harga Satuan Pekerjaan (D+E) 81,499.00

A.4.5.1.10. Pemasangan 1 m List Plafond PVC

No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)
A TENAGA
Pekerja L.01.01 OH 0.1 76,000.00 7,600.00
Tukang Kayu L.02.04 OH 0.05 95,000.00 4,750.00
Kepala tukang L.03.01 OH 0.005 105,000.00 525.00
Mandor L.04.01 OH 0.005 115,000.00 575.00
JUMLAH TENAGA KERJA 13,450.00
B BAHAN
List PVC M' 1.05 13,000.00 13,650.00
Screw bh 6 80.00 480.00
JUMLAH HARGA BAHAN 14,130.00
C PERALATAN
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 27,580.00
E Overhead & Profit 10% 0.1 2,758.00
F Harga Satuan Pekerjaan (D+E) 30,338.00

A.4.5.2.30. Pemasangan 1 m² genteng beton


No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)
A TENAGA
Pekerja L.01.01 OH 0.2 76,000.00 15,200.00
Tukang Kayu L.02.04 OH 0.1 95,000.00 9,500.00
Kepala tukang L.03.01 OH 0.01 105,000.00 1,050.00
Mandor L.04.01 OH 0.01 115,000.00 1,150.00
JUMLAH TENAGA KERJA 26,900.00
B BAHAN
Genteng beton Bh 11 - -
Paku Biasa Kg 0.03 15,000.00 450.00
JUMLAH HARGA BAHAN 450.00
C PERALATAN
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 27,350.00
E Overhead & Profit 10% 0.1 2,735.00
F Harga Satuan Pekerjaan (D+E) 30,085.00

A.4.5.2.32. Pemasangan 1 m² genteng metal ukuran 80 x 100 atap pelana

No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)
A TENAGA
Pekerja L.01.01 OH 0.2 76,000.00 15,200.00
Tukang Kayu L.02.04 OH 0.1 95,000.00 9,500.00
Kepala tukang L.03.01 OH 0.01 105,000.00 1,050.00
Mandor L.04.01 OH 0.001 115,000.00 115.00
JUMLAH TENAGA KERJA 25,865.00
B BAHAN
Genteng metal Bh 1.3 60,000.00 78,000.00
Paku biasa ½”-1” Kg 0.2 15,000.00 3,000.00
JUMLAH HARGA BAHAN 81,000.00
C PERALATAN
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 106,865.00
E Overhead & Profit 10% 0.1 10,686.50
F Harga Satuan Pekerjaan (D+E) 117,551.00

A.4.5.2.35. Pemasangan 1 m’ nok genteng beton


No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)
A TENAGA
Pekerja L.01.01 OH 0.4 76,000.00 30,400.00
Tukang Kayu L.02.04 OH 0.2 95,000.00 19,000.00
Kepala tukang L.03.01 OH 0.02 105,000.00 2,100.00
Mandor L.04.01 OH 0.02 115,000.00 2,300.00
JUMLAH TENAGA KERJA 53,800.00
B BAHAN
Nok genteng beton Bh 3.5 - -
Paku Biasa Kg 0.05 15,000.00 750.00
Semen Portland Kg 10.8 1,450.00 15,660.00
Pasir Pasang m³ 0.032 263,500.00 8,432.00
Semen warna Kg 1 15,000.00 15,000.00
JUMLAH HARGA BAHAN 39,842.00
C PERALATAN
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 93,642.00
E Overhead & Profit 10% 0.1 9,364.20
F Harga Satuan Pekerjaan (D+E) 103,006.00
A.4.5.2.37. Pemasangan 1 m’ nok genteng metal

No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)
A TENAGA
Pekerja L.01.01 OH 0.25 76,000.00 19,000.00
Tukang Kayu L.02.04 OH 0.15 95,000.00 14,250.00
Kepala tukang L.03.01 OH 0.015 105,000.00 1,575.00
Mandor L.04.01 OH 0.013 115,000.00 1,495.00
JUMLAH TENAGA KERJA 36,320.00
B BAHAN
Nok genteng metal Bh 1.1 - -
Paku Biasa Kg 0.05 15,000.00 750.00
JUMLAH HARGA BAHAN 750.00
C PERALATAN
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 37,070.00
E Overhead & Profit 10% 0.1 3,707.00
F Harga Satuan Pekerjaan (D+E) 40,777.00

A.4.6.1.1. Pembuatan dan pemasangan 1 m³ kusen pintu dan kusen jendela, kayu kelas I
No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)
A TENAGA
Pekerja L.01.01 OH 7 76,000.00 532,000.00
Tukang kayu L.02.04 OH 21 95,000.00 1,995,000.00
Kepala tukang L.03.01 OH 2.1 105,000.00 220,500.00
Mandor L.04.01 OH 0.35 115,000.00 40,250.00
JUMLAH TENAGA KERJA 2,787,750.00
B BAHAN
Balok kayu m³ 1.1 1,750,000.00 1,925,000.00
Paku Biasa Kg 1.25 15,000.00 18,750.00
Lem Kayu/Karet Kg 1 25,000.00 25,000.00
JUMLAH HARGA BAHAN 1,968,750.00
C PERALATAN
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 4,756,500.00
E Overhead & Profit 10% 0.1 475,650.00
F Harga Satuan Pekerjaan (D+E) 5,232,150.00

A.4.6.1.2. Pembuatan dan pemasangan 1 m³ kusen pintu dan kusen jendela, kayu kelas II atau III
No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)
A TENAGA
Pekerja L.01.01 OH 6 76,000.00 456,000.00
Tukang kayu L.02.04 OH 18 95,000.00 1,710,000.00
Kepala tukang L.03.01 OH 1.8 105,000.00 189,000.00
Mandor L.04.01 OH 0.3 115,000.00 34,500.00
JUMLAH TENAGA KERJA 2,389,500.00
B BAHAN
Balok kayu m³ 1.2 1,750,000.00 2,100,000.00
Paku Biasa Kg 1.25 15,000.00 18,750.00
Lem Kayu/Karet Kg 1 25,000.00 25,000.00
JUMLAH HARGA BAHAN 2,143,750.00
C PERALATAN
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 4,533,250.00
E Overhead & Profit 10% 0.1 453,325.00
F Harga Satuan Pekerjaan (D+E) 4,986,575.00

A.4.6.1.3. Pembuatan dan pemasangan 1 m² pintu klamp standar, kayu kelas II


No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)
A TENAGA
Pekerja L.01.01 OH 0.35 76,000.00 26,600.00
Tukang kayu L.02.04 OH 1.05 95,000.00 99,750.00
Kepala tukang L.03.01 OH 0.105 105,000.00 11,025.00
Mandor L.04.01 OH 0.018 115,000.00 2,070.00
JUMLAH TENAGA KERJA 139,445.00
B BAHAN
kayu Papan m³ 0.04 3,500,000.00 140,000.00
Paku Biasa Kg 0.05 15,000.00 750.00
JUMLAH HARGA BAHAN 140,750.00
C PERALATAN
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 280,195.00
E Overhead & Profit 10% 0.1 28,019.50
F Harga Satuan Pekerjaan (D+E) 308,214.00

A.4.6.1.6. Pembuatan dan pemasangan 1 m² pintu dan jendela kaca, kayu kelas I atau II
No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)
A TENAGA
Pekerja L.01.01 OH 0.8 76,000.00 60,800.00
Tukang kayu L.02.04 OH 2.4 95,000.00 228,000.00
Kepala tukang L.03.01 OH 0.24 105,000.00 25,200.00
Mandor L.04.01 OH 0.04 115,000.00 4,600.00
JUMLAH TENAGA KERJA 318,600.00
B BAHAN
kayu Papan m³ 0.024 3,500,000.00 84,000.00
Lem Kayu/Karet Kg 0.3 25,000.00 7,500.00
JUMLAH HARGA BAHAN 91,500.00
C PERALATAN
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 410,100.00
E Overhead & Profit 10% 0.1 41,010.00
F Harga Satuan Pekerjaan (D+E) 451,110.00

A.4.6.1.15. Pemasangan 1 m³ konstruksi gordeng, kayu kelas II


No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)
A TENAGA
Pekerja L.01.01 OH 6.7 76,000.00 509,200.00
Tukang kayu L.02.04 OH 20.1 95,000.00 1,909,500.00
Kepala tukang L.03.01 OH 2.01 105,000.00 211,050.00
Mandor L.04.01 OH 0,335 115,000.00
JUMLAH TENAGA KERJA
B BAHAN
Balok kayu m³ 1.1 1,750,000.00 1,925,000.00
Besi strip Kg 15 12,900.00 193,500.00
Paku Biasa Kg 3 15,000.00 45,000.00
JUMLAH HARGA BAHAN 2,163,500.00
C PERALATAN
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 2,374,550.00
E Overhead & Profit 10% 0.1 237,455.00
F Harga Satuan Pekerjaan (D+E) 2,612,005.00

A.4.6.1.21. Pemasangan 1 m’ lisplank ukuran (3 x 20) cm, kayu kelas I atau kelas II
No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)
A TENAGA
Pekerja L.01.01 OH 0.1 76,000.00 7,600.00
Tukang kayu L.02.04 OH 0.2 95,000.00 19,000.00
Kepala tukang L.03.01 OH 0.02 105,000.00 2,100.00
Mandor L.04.01 OH 0.005 115,000.00 575.00
JUMLAH TENAGA KERJA 29,275.00
B BAHAN
Kayu Papan m³ 0.0108 3,500,000.00 37,800.00
Paku Biasa Kg 0.1 15,000.00 1,500.00
JUMLAH HARGA BAHAN 39,300.00
C PERALATAN
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 68,575.00
E Overhead & Profit 10% 0.1 6,857.50
F Harga Satuan Pekerjaan (D+E) 75,432.00

A.4.6.2 HARGA SATUAN PEKERJAAN KUNCI DAN KACA

A.4.6.2.1. Pemasangan 1 buah kunci tanam antik


No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)
A TENAGA
Pekerja L.01.01 OH 0.06 76,000.00 4,560.00
Tukang kayu L.02.04 OH 0.6 95,000.00 57,000.00
Kepala tukang L.03.01 OH 0.06 105,000.00 6,300.00
Mandor L.04.01 OH 0.003 115,000.00 345.00
JUMLAH TENAGA KERJA 68,205.00
B BAHAN
Kunci tanam antik Bh 1 - -
JUMLAH HARGA BAHAN -
C PERALATAN
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 68,205.00
E Overhead & Profit 10% 0.1 6,820.50
F Harga Satuan Pekerjaan (D+E) 75,025.00

A.4.6.2.2. Pemasangan 1 buah kunci tanam biasa


No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)
A TENAGA
Pekerja L.01.01 OH 0.01 76,000.00 760.00
Tukang kayu L.02.04 OH 0.5 95,000.00 47,500.00
Kepala tukang L.03.01 OH 0.05 105,000.00 5,250.00
Mandor L.04.01 OH 0.005 115,000.00 575.00
JUMLAH TENAGA KERJA 54,085.00
B BAHAN
Kunci tanam biasa Bh 1 130,000.00 130,000.00
JUMLAH HARGA BAHAN 130,000.00
C PERALATAN
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 184,085.00
E Overhead & Profit 10% 0.1 18,408.50
F Harga Satuan Pekerjaan (D+E) 202,493.00

A.4.6.2.3. Pemasangan 1 buah kunci kamar mandi


No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)
A TENAGA
Pekerja L.01.01 OH 0.005 76,000.00 380.00
Tukang kayu L.02.04 OH 0.5 95,000.00 47,500.00
Kepala tukang L.03.01 OH 0.05 105,000.00 5,250.00
Mandor L.04.01 OH 0.003 115,000.00 345.00
JUMLAH TENAGA KERJA 53,475.00
B BAHAN
Kunci tanam KM Bh 1 60,000.00 60,000.00
JUMLAH HARGA BAHAN 60,000.00
C PERALATAN
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 113,475.00
E Overhead & Profit 10% 0.1 11,347.50
F Harga Satuan Pekerjaan (D+E) 124,822.00

A.4.6.2.5. Pemasangan 1 buah engsel pintu


No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)
A TENAGA
Pekerja L.01.01 OH 0.015 76,000.00 1,140.00
Tukang kayu L.02.04 OH 0.15 95,000.00 14,250.00
Kepala tukang L.03.01 OH 0.015 105,000.00 1,575.00
Mandor L.04.01 OH 0.0008 115,000.00 92.00
JUMLAH TENAGA KERJA 17,057.00
B BAHAN
Engsel pintu Bh 1 45,000.00 45,000.00
JUMLAH HARGA BAHAN 45,000.00
C PERALATAN
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 62,057.00
E Overhead & Profit 10% 0.1 6,205.70
F Harga Satuan Pekerjaan (D+E) 68,262.00

A.4.6.2.6. Pemasangan 1 buah engsel jendela kupu-kupu


No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)
A TENAGA
Pekerja L.01.01 OH 0.01 76,000.00 760.00
Tukang kayu L.02.04 OH 0.1 95,000.00 9,500.00
Kepala tukang L.03.01 OH 0.01 105,000.00 1,050.00
Mandor L.04.01 OH 0.0005 115,000.00 57.50
JUMLAH TENAGA KERJA 11,367.50
B BAHAN
Engsel kupu-kupu Bh 1 25,000.00 25,000.00
JUMLAH HARGA BAHAN 25,000.00
C PERALATAN
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 36,367.50
E Overhead & Profit 10% 0.1 3,636.75
F Harga Satuan Pekerjaan (D+E) 40,004.00

A.4.6.2.9. Pemasangan 1 buah kait angin


No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)
A TENAGA
Pekerja L.01.01 OH 0.015 76,000.00 1,140.00
Tukang kayu L.02.04 OH 0.15 95,000.00 14,250.00
Kepala tukang L.03.01 OH 0.015 105,000.00 1,575.00
Mandor L.04.01 OH 0.008 115,000.00 920.00
JUMLAH TENAGA KERJA 17,885.00
B BAHAN
Kait angin Bh 1 15,000.00 15,000.00
JUMLAH HARGA BAHAN 15,000.00
C PERALATAN
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 32,885.00
E Overhead & Profit 10% 0.1 3,288.50
F Harga Satuan Pekerjaan (D+E) 36,173.00

A.4.6.2.12. Pemasangan 1 buah Door holder


No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)
A TENAGA
Pekerja L.01.01 OH 0.05 76,000.00 3,800.00
Tukang kayu L.02.04 OH 0.5 95,000.00 47,500.00
Kepala tukang L.03.01 OH 0.05 105,000.00 5,250.00
Mandor L.04.01 OH 0.003 115,000.00 345.00
JUMLAH TENAGA KERJA 56,895.00
B BAHAN
Door holder Bh 1 40,000.00 40,000.00
JUMLAH HARGA BAHAN 40,000.00
C PERALATAN
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 96,895.00
E Overhead & Profit 10% 0.1 9,689.50
F Harga Satuan Pekerjaan (D+E) 106,584.00

A.4.6.2.13. Pemasangan 1 buah door stop


No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)
A TENAGA
Pekerja L.01.01 OH 0.01 76,000.00 760.00
Tukang kayu L.02.04 OH 0.1 95,000.00 9,500.00
Kepala tukang L.03.01 OH 0.01 105,000.00 1,050.00
Mandor L.04.01 OH 0.005 115,000.00 575.00
JUMLAH TENAGA KERJA 11,885.00
B BAHAN
Door stop Bh 1 28,000.00 28,000.00
JUMLAH HARGA BAHAN 28,000.00
C PERALATAN
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 39,885.00
E Overhead & Profit 10% 0.1 3,988.50
F Harga Satuan Pekerjaan (D+E) 43,873.00

A.4.6.2.16. Pemasangan 1 m² kaca tebal 3 mm


No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)
A TENAGA
Pekerja L.01.01 OH 0.015 76,000.00 1,140.00
Tukang kayu L.02.04 OH 0.15 95,000.00 14,250.00
Kepala tukang L.03.01 OH 0.015 105,000.00 1,575.00
Mandor L.04.01 OH 0.0008 115,000.00 92.00
JUMLAH TENAGA KERJA 17,057.00
B BAHAN
Kaca tebal 3 mm m² 1.1 - -
SEalant Kg 0.05 - -
JUMLAH HARGA BAHAN -
C PERALATAN
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 17,057.00
E Overhead & Profit 10% 0.1 1,705.70
F Harga Satuan Pekerjaan (D+E) 18,762.00

A.4.6.2.17. Pemasangan 1 m² kaca tebal 5 mm


No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)
A TENAGA
Pekerja L.01.01 OH 0.015 76,000.00 1,140.00
Tukang kayu L.02.04 OH 0.15 95,000.00 14,250.00
Kepala tukang L.03.01 OH 0.015 105,000.00 1,575.00
Mandor L.04.01 OH 0.0008 115,000.00 92.00
JUMLAH TENAGA KERJA 17,057.00
B BAHAN
Kaca tebal 5 mm m² 1.1 135,000.00 148,500.00
SEalant Kg 0.05 - -
JUMLAH HARGA BAHAN 148,500.00
C PERALATAN
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 165,557.00
E Overhead & Profit 10% 0.1 16,555.70
F Harga Satuan Pekerjaan (D+E) 182,112.00

A.4.7.1.4. 1 m² Pengecatan bidang kayu baru (1 lapis plamur, 1 lapis cat dasar, 2 lapis cat penutup)
No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)
A TENAGA
Pekerja L.01.01 OH 0.07 76,000.00 5,320.00
Tukang cat L.02.08 OH 0.009 95,000.00 855.00
Kepala tukang L.03.01 OH 0.006 105,000.00 630.00
Mandor L.04.01 OH 0.003 115,000.00 345.00
JUMLAH TENAGA KERJA 7,150.00
B BAHAN
Cat menie Kg 0.2 - -
Plamur Kg 0.15 6,000.00 900.00
Cat dasar Kayu Kg 0.17 80,000.00 13,600.00
Cat Penutup Kayu Kg 0.26 - -
Kuas Bh 0.01 - -
Pengencer Kg 0.03 50,000.00 1,500.00
Ampelas Lbr 0.2 - -
JUMLAH HARGA BAHAN 16,000.00
C PERALATAN
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 23,150.00
E Overhead & Profit 10% 0.1 2,315.00
F Harga Satuan Pekerjaan (D+E) 25,465.00

A.4.7.1.10. Pengecatan 1 m² tembok baru ( 1lapis Plamur, 2 lapis cat)


No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)
A TENAGA
Pekerja L.01.01 OH 0.02 76,000.00 1,520.00
Tukang cat L.02.08 OH 0.063 95,000.00 5,985.00
Kepala tukang L.03.01 OH 0.0063 105,000.00 661.50
Mandor L.04.01 OH 0.003 115,000.00 345.00
JUMLAH TENAGA KERJA 8,511.50
B BAHAN
Plamur Kg 0.1 6,000.00 600.00
Cat Penutup Tembok Kg 0.26 10,500.00 2,730.00
JUMLAH HARGA BAHAN 3,330.00
C PERALATAN
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 11,841.50
E Overhead & Profit 10% 0.1 1,184.15
F Harga Satuan Pekerjaan (D+E) 13,025.00

A.5.1.1 3. Pemasangan 1 buah closet jongkok teraso


No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)
A TENAGA
Pekerja L.01.01 OH 1 76,000.00 76,000.00
Tukang batu L.02.03 OH 1.5 95,000.00 142,500.00
Kepala tukang L.03.01 OH 0.15 105,000.00 15,750.00
Mandor L.04.01 OH 0.05 115,000.00 5,750.00
JUMLAH TENAGA KERJA 240,000.00
B BAHAN
Closet jongkok Unit 1 - -
Semen Portland Kg 6 1,450.00 8,700.00
Pasir pasang m³ 0.01 263,500.00 2,635.00
Bata merah Bh 7 800.00 5,600.00
JUMLAH HARGA BAHAN 16,935.00
C PERALATAN
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 256,935.00
E Overhead & Profit 10% 0.1 25,693.50
F Harga Satuan Pekerjaan (D+E) 282,628.00

A.5.1.1 4. (K3) Pemasangan 1 buah urinoir

A.5.1.1 7. (K3) Pemasangan 1 buah bak fibreglass vol 1 m³


No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)
A TENAGA
Pekerja L.01.01 OH 3 76,000.00 228,000.00
Tukang batu L.02.03 OH 4.5 95,000.00 427,500.00
Kepala tukang L.03.01 OH 0.05 105,000.00 5,250.00
Mandor L.04.01 OH 0.9 115,000.00 103,500.00
JUMLAH TENAGA KERJA 764,250.00
B BAHAN
Bak fibreglass Unit 1 250,000.00 250,000.00
Perlengkapan % 0.12 250,000.00 30,000.00
JUMLAH HARGA BAHAN 280,000.00
C PERALATAN
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 1,044,250.00
E Overhead & Profit 10% 0.1 104,425.00
F Harga Satuan Pekerjaan (D+E) 1,148,675.00

A.5.1.1 10. Pemasangan 1 buah bak air fibreglass vol 1 m³


No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)
A TENAGA
Pekerja L.01.01 OH 0.3 76,000.00 22,800.00
Tukang batu L.02.03 OH 0.45 95,000.00 42,750.00
Kepala tukang L.03.01 OH 0.045 105,000.00 4,725.00
Mandor L.04.01 OH 0.015 115,000.00 1,725.00
JUMLAH TENAGA KERJA 72,000.00
B BAHAN
Bak fibreglass Unit 1 250,000.00 250,000.00
Perlengkapan % 0.12 250,000.00 30,000.00
JUMLAH HARGA BAHAN 280,000.00
C PERALATAN
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 352,000.00
E Overhead & Profit 10% 0.1 35,200.00
F Harga Satuan Pekerjaan (D+E) 387,200.00

A.5.1.1 12. Pemasangan 1 buah bak cuci piring stainlessteel


No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)
A TENAGA
Pekerja L.01.01 OH 0.03 76,000.00 2,280.00
Tukang batu L.02.03 OH 0.3 95,000.00 28,500.00
Kepala tukang L.03.01 OH 0.03 105,000.00 3,150.00
Mandor L.04.01 OH 0.015 115,000.00 1,725.00
JUMLAH TENAGA KERJA 35,655.00
B BAHAN
Bak cuci piring Unit 1 500,000.00 500,000.00
Waterdrain Bh 1 20,000.00 20,000.00
JUMLAH HARGA BAHAN 520,000.00
C PERALATAN
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 555,655.00
E Overhead & Profit 10% 0.1 55,565.50
F Harga Satuan Pekerjaan (D+E) 611,220.00

A.5.1.1 14. Pemasangan 1 buah floor drain


No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)
A TENAGA
Pekerja L.01.01 OH 0.01 76,000.00 760.00
Tukang batu L.02.03 OH 0.1 95,000.00 9,500.00
Kepala tukang L.03.01 OH 0.01 105,000.00 1,050.00
Mandor L.04.01 OH 0.005 115,000.00 575.00
JUMLAH TENAGA KERJA 11,885.00
B BAHAN
Floor drain Unit 1 26,000.00 26,000.00
JUMLAH HARGA BAHAN 26,000.00
C PERALATAN
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 37,885.00
E Overhead & Profit 10% 0.1 3,788.50
F Harga Satuan Pekerjaan (D+E) 41,673.00

A.5.1.1 19. Pemasangan 1 buah kran diameter ½” atau 3/4”


No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)
A TENAGA
Pekerja L.01.01 OH 0.01 76,000.00 760.00
Tukang batu L.02.03 OH 0.4 95,000.00 38,000.00
Kepala tukang L.03.01 OH 0.04 105,000.00 4,200.00
Mandor L.04.01 OH 0.005 115,000.00 575.00
JUMLAH TENAGA KERJA 43,535.00
B BAHAN
Kran air M 1 15,000.00 15,000.00
Sealtape Buah 0.025 1,200.00 30.00
JUMLAH HARGA BAHAN 15,030.00
C PERALATAN
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 58,565.00
E Overhead & Profit 10% 0.1 5,856.50
F Harga Satuan Pekerjaan (D+E) 64,421.00

A.5.1.1 25. Pemasangan 1 m’ pipa PVC tipe AW diameter 1/2”


No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)
A TENAGA
Pekerja L.01.01 OH 0.036 76,000.00 2,736.00
Tukang batu L.02.03 OH 0.06 95,000.00 5,700.00
Kepala tukang L.03.01 OH 0.006 105,000.00 630.00
Mandor L.04.01 OH 0.002 115,000.00 230.00
JUMLAH TENAGA KERJA 9,296.00
B BAHAN
Pipa PVC 1/2” M 1.2 30,000.00 36,000.00
Perlengkapan % 0.35 30,000.00 10,500.00
JUMLAH HARGA BAHAN 46,500.00
C PERALATAN
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 55,796.00
E Overhead & Profit 10% 0.1 5,579.60
F Harga Satuan Pekerjaan (D+E) 61,375.00

A.5.1.1 33. Pemasangan 1 m’ pipa air limbah jenis pipa tanah


No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)
A TENAGA
Pekerja L.01.01 OH 0.08 76,000.00 6,080.00
Tukang batu L.02.03 OH 0.04 95,000.00 3,800.00
Kepala tukang L.03.01 OH 0.004 105,000.00 420.00
Mandor L.04.01 OH 0.004 115,000.00 460.00
JUMLAH TENAGA KERJA 10,760.00
B BAHAN
Pipa tanah Bh 1.6 165,000.00 264,000.00
Semen Portland Kg 35 1,450.00 50,750.00
Pasir pasang m³ 0.014 263,500.00 3,689.00
Pasir urug m³ 0.014 118,800.00 1,663.20
JUMLAH HARGA BAHAN 320,102.20
C PERALATAN
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 330,862.20
E Overhead & Profit 10% 0.1 33,086.22
F Harga Satuan Pekerjaan (D+E) 363,948.00

A.8.4.6.2 Memasang 1 Titik Instalasi Penerangan


No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)
A TENAGA
Pekerja L.01.01 OH 0.15 76,000.00 11,400.00
Tukang batu L.02.03 OH 0.15 95,000.00 14,250.00
Kepala tukang L.03.01 OH 0.03 105,000.00 3,150.00
Mandor L.04.01 OH 0.03 115,000.00 3,450.00
JUMLAH TENAGA KERJA 32,250.00
B BAHAN
Kabel NYM 3x2,5 mm² M' 11 19,000.00 209,000.00
Pipa Conduit M' 11 6,500.00 71,500.00
Socket Pipa bh 1 800.00 800.00
Tee Doos bh 2 12,000.00 24,000.00
Klem Pipa listrik bh 3 600.00 1,800.00
Fhiser bh 6 100.00 600.00
Las Dop bh 2 200.00 400.00
Sealtape Listrik bh 0.25 5,000.00 1,250.00
JUMLAH HARGA BAHAN 309,350.00
C PERALATAN
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 341,600.00
E Overhead & Profit 10% 0.1 34,160.00
F Harga Satuan Pekerjaan (D+E) 375,760.00

REKAPITULASI PEKERJAAN BETON


ANALISA HARGA SATUAN PEKERJAAN
PEKERJAAN PONDASI TAPAK

Pekerjaan Pondasi Tapak 120 x 120 cm Beton Bertulang


Satuan/Unit m³
Analisa Suplemen.ST.1

AHSP Uraian Satuan Koefisien Harga Satuan Jumlah Harga


BETON m³ 0 -
TULANGAN Kg 0 -
TULANGAN Kg 0 -
BEKESTING m² 0 -
Pekerjaan lain-lain Ls -
Jumlah harga per satuan pekerjaan -
RENCANA ANGGARAN BIAYA

PEKERJAAN : RUMAH
LOKASI : SRAGEN
TAHUN ANGGARAN : 2021

NO. URAIAN PEKERJAAN VOLUME SAT HARGA SATUAN JUMLAH HARGA TOTAL

I. PEKERJAAN PERSIAPAN
1 (K3) Pembersihan 1 m² lapangan dan perataan 115.5 m² 68,466.00 7,907,823.00
2 Pemasangan 1 m’ Bouwplank 51 M³ 36,705.00 1,871,955.00
3 Pembuatan 1 buah kotak adukan ukuran 40cm x50cm x25cm 0.05 M³ 174,735.00 8,736.75 9,788,514.75
II. PEKERJAAN TANAH DAN PASIR
1 Penggalian 1 m³ tanah biasa sedalam 1 m 50.099 m³ 65,862.00 3,299,620.34
2 Pengurugan kembali 1 m³ galian tanah Tanah Biasa Sedalam 1m 8.841 m³ 24,062.00 212,732.14
3 Pengurugan 1 m³ dengan pasir urug dibawah pondasi 5.894 m³ 183,161.00 1,079,550.93
4 Pengurukan 1 m³ dibawah lantai 4.945 m³ 183,161.00 905,731.15 5,497,634.56
III. PEKERJAAN BETON
1 Pemasangan 1 m³ pondasi Batu Kali/Belah campuran 1SP : 6PP 23.576 m³ 848,345.00 20,000,581.72
2 Pemasangan 1 m³ batu kosong (anstamping) 5.894 m³ 449,054.00 2,646,724.28
3 Membuat 1 m³ sloof beton bertulang 15 X 20cm 2.526 m³ 7,886,286.00 19,920,758.44
4 Membuat 1 m³ kolom beton bertulang 15 X 15cm 2.384 m³ 10,689,584.00 25,483,968.26
5 Membuat 1 m³ ring balk 2.526 m³ 7,886,286.00 19,920,758.44 87,972,791.12
IV.
V. PEKERJAAN PASANGAN DINDING
1 Pemasangan 1m² dinding bata merah ½ batu campuran 1 SP : 5 PP 292.13 m² 127,655.00 37,291,855.15 37,291,855.15
VI PEKERJAAN PENUTUP LANTAI
1 Pemasangan 1 m’ plint ubin granit ukuran 60cm x 60cm 90.5 m² 170,510.00 15,431,155.00 15,431,155.00
VII PEKERJAAN PLESTERAN
1 Pemasangan 1 m² plesteran 1SP : 4PP tebal 20 mm. 584.26 m² 81,978.00 47,896,466.28 47,896,466.28
VIII PEKERJAAN LANGIT-LANGIT (PLAFOND)
1 Pemasangan 1 m² Plafond pvc 111.3 m² 81,499.00 9,070,838.70
2 Pemasangan 1 m List Plafond pvc 90.5 m 30,338.00 2,745,589.00 11,816,427.70
IX PEKERJAAN PENUTUP ATAP
1 Pemasangan 1 m² genteng metal ukuran 80 x 100 atap pelana 186 m² 117,551.00 21,864,486.00 21,864,486.00
X PEKERJAAN KAYU
Pemasangan 1 m’ lisplank ukuran (3 x 20) cm, kayu kelas I atau kelas II 31.3 m 75,432.00 2,361,021.60
Pembuatan dan pemasangan 1 m³ kusen pintu dan kusen jendela, kayu kelas II atau III 0.590616 m³ 4,986,575.00 2,945,150.98
pembuatan dan pemasangan 1 m ᶟ pintu klamp standar,kayu kelas II 12.18 mᶟ 308,214.00 3,754,046.52
gording dan nok 0.7728 mᶟ 103,006.00 79,603.04 9,139,822.14
XI PEKERJAAN PENGECATAN
1 Pengecatan 1 m² tembok baru ( 1lapis Plamur, 2 lapis cat) 587.26 m² 13,025.00 7,649,061.50
2 pengecetan 1 m² kayu baru (1 lapis pelamur,1lapis cat dasar,2 lapis cat penutup) 12.7706 m² 25,460.00 325,139.48
3 pengecatan plafon gipsum 111.3 m² 25,460.00 2,833,698.00 10,807,898.98
XII PEKERJAAN KUNCI DAN KACA
1 Pemasangan 1 buah kunci tanam biasa 1 bh 202,493.00 1012465
2 Pemasangan 1 buah kunci kamar mandi 2 bh 124,822.00 124822
3 Pemasangan 1 buah engsel pintu 14 bh 68,262.00 955668
4 Pemasangan 1 buah engsel jendela kupu-kupu 22 bh 40,004.00 880088
5 Pemasangan 1 buah kait angin 11 bh 36,173.00 397903
6 Pemasangan 1 buah Door holder 3 bh 106,584.00 319752
7 Pemasangan 1 buah door stop 6 bh 43,873.00 263238
8 Pemasangan 1 m² kaca tebal 5 mm 8.2 m² 182,112.00 1,493,318.40 5,447,254.40
XIII PEKERJAAN SANITASI
1 (K3) Pemasangan closet jonkok 2 Bh 1,519,925.00 3,039,850.00
2 Pemasangan 1 buah bak cuci piring stainlessteel 1 Bh 611,220.00 611,220.00
3 Pemasangan 1 buah floor drain 2 Bh 41,673.00 83,346.00
4 Pemasangan 1 buah kran diameter ½” atau 3/4” 5 Bh 64,421.00 322,105.00
5 Pemasangan 1 m’ pipa PVC tipe AW diameter 1/2” 15 m 61,375.00 920,625.00
6 Pemasangan 1 m’ pipa air limbah jenis pipa tanah 4 m 363,948.00 1,455,792.00
7 Pemasangan 1 buah bak fibreglass vol 1mᶟ 2 Bh 1,115,675.00 2,231,350.00 8,664,288.00
XIV PEKERJAAN ELEKTRIKAL
1 (K3) Pemasangan 1 buah titik lampu 15 Unit 694,100.00 10,411,500.00 10,411,500.00
REKAPITULASI
HARGA PERKIRAAN SENDIRI (HPS)
PEKERJAAN : RUMAH TINGGAL
LOKASI : SRAGEN
TAHUN ANGGARAN : 2021

NO URAIAN PEKERJAAN JUMLAH HARGA

1 PEKERJAAN PERSIAPAN 9,788,515.00


2 PEKERJAAN TANAH DAN PASIR 54,976,345.00
3 PEKERJAAN BETON 87,972,791.00
4 PEKERJAAN PASANGAN DINDING 37,291,855.00
5 PEKERJAAN PENUTUP LANTAI DAN PENUTUP DINDING 15,431,155.00
6 PEKERJAAN PLESTERAN 47,896,466.00
7 PEKERJAAN LANGIT-LANGIT (PLAFOND) 11,816,427.00
8 PEKERJAAN PENUTUP ATAP 21,864,486.00
9 PEKERJAAN KAYU 9,139,823.00
10 PEKERJAAN PENGECATAN 10,807,899.00
11 PEKERJAAN KUNCI DAN KACA 5,497,255.00
12 PEKERJAAN SANITASI 8,664,288.00
13 PEKERJAAN ELEKTRIKAL 10,411,500.00
TOTAL 331,558,805.00
Terbilang tiga ratus tiga puluh satu juta lima ratus lima puluh delapan ribu delapan ratus lima rupiah
PERHITUNGAN VOLUME & RAB
TUGAS MANAJEMEN KONSTRUKSI
UNIVERSITAS SURAKARTA

I. PEKERJAAN PERSIAPAN
NO URAIANPEKERJAAN RUMUS PERHITUNGAN VOLUME SATUAN
A Pembersihan lahan V=PxL panjang x lebar
11 x 10.5 115.5 M²

B Bouwplank V=(P+2)x2+(L+2)x2 panjang x lebar


26 x 25 51 M¹

C pembuatan 1kotak adukan ukuran 40cm x 50 cm x 25 cm panjang x lebar x tinggi


V=PxLxT 0.4 x 0.5 x 0.25 0.05 M¹

II. PEKERJAAN TANAH DAN PASIR


A Galian tanah VA= (a + b) xh xp lebar x tinggi x panjang
2 0.85 x 0.7 x 84.2 50.099 Mᶟ

B urukan tanah pondasi V=V.g.tanah -(V.pas.batu kali + V.urukan pasir) panjang - v.pas.batu + v.pasir uruk
23.576 - 29.47 + 2.947 8.841 Mᶟ

C Urukan pasir dibawah pondasi (t= 10cm) VA=h x b x p tinggi x lebar x panjang
0.1 x 0.7 x 84.2 5.894 Mᶟ

D Urukan pasir dibawah lantai (t= 5 cm) V= h x L tebal x luas lantai(L x P)


0.05 x 98.9 4.945 Mᶟ

III. PEKERJAAN BETON DAN PEMBESIAN


1 Pekerjaan pasangan pondasi 1 SP :6PP VA= (a + b ) x h x p lebar.a + lebar.b / 2 x tinggi x panjang
2 0.4 x 0.7 x 84.2 23.576 Mᶟ

2 Pekerjaan pas.batu kosong(anstampang) V= L x T x P L x T x P


0.7 x 0.1 x 84.2 5.894 Mᶟ

3 Pekerjaan sloof 15/20 VA= b x h x p lebar penampang sloof x tinggi penampang sloof x panjang fondasi
0.15 x 0.2 x 84.2 2.526 Mᶟ

Pembesian( 4 Ø10 )sloof 15/20 V=P x tulangan panjang x jumlah tulangan


84.2 x 4 336.8 M¹

Begel Ø8 sloof 15/20 panjang : jarak begel x panjang 1 begel


84.2 : 0.2 x 0.8 336.8 M¹

Bekisting III (papan 2/20) V=( P + 2) x T Panjang x tinggi


84.2
84.2 x 0.2 33.68 M²

4 Pekerjaan kolom 15/15 VA= (b x h x t ) x ∑k lebar kolom x tebal kolom x tinggi kolom x jumlah kolom
0.15 x 0.15 x 3.25 x 29 2.120625 Mᶟ

pembesian (4 Ø 10) kolom 15/15 V= P x tulangan panjang x tulangan


94.25 x 4 377 M¹

Begel Ø 8 kolom 15/15 panjang : jarak begel x panjang 1 begel


94.25 : 0.2 x 0.7 706.875 329.875 M¹

Bekisting III (Papan 2/20) V= (P x 4) x T Panjang x tinggi


94.25 x 0.15 x 4 56.55 M²

5 Pekerjaan kolom teras 15/35 VA= (b x h x t) x ∑k lebar x tebal x tinggi x jumlah kolom
0.15 x 0.35 2.5 x 2 0.2625 Mᶟ

Pembesian (6 Ø 10) kolom 15/35 V=p x tulangan panjang x tulangan


5 x 6 30 M¹

Begel Ø 8 kolom 15/35 panjang : jarak begel x panjang 1 begel


5 : 0.2 x 1.1 27.5 M¹

Bekisting III (Papan 2/20) V= (P x 4) x t panjang x tinggi


5 x 0.15 x 4 3 M²

6 Pekerjaan ring balok 15/20 V=b x h x p lebar x tebal x panjang


0.15 x 0.2 x 84.2 2.526 Mᶟ

Pembesian (4 Ø 10) ring balok 15/20 V= P x tulangan panjang x tulangan


84.2 x 4 336.8 M¹

Begel Ø 8 ring balok 15/20 panjang : jarak begel x panjang 1 begel


84.2 x 0.2 x 0.8 336.8 M¹

Bekisting III (papan 2/20) V=(P x 2) x t panjang x tinggi


84.2 x 0.2 x 2 33.68 M²

7 pekerjaan beton meja dapur V= b x h x p lebar x tebal x panjanag


0.7 x 0.1 x 3 0.21 Mᶟ

pembesian (4Ø 8) meja dapur

8 Beton topi teras depan dan samping V= b x h x p lebar x tebal x panjang


0.5 x 0.1 x 9.9 0.495 Mᶟ

9 beton lantai 5cm dibawah lantai V= h x L tebal x luas 4.945 Mᶟ


0.05 x 98.9

IV. PEKERJAAN PASANGAN DINDING DAN ACI


1 Pasangan dinding bata merah 1 : 5 (5 x 11 x 22)cm V1= (h x p) - Lp - Lj -Lg tinggi x panjang - Lp - Lj -Lg
3.25 x 84.2 - 26.52 247.13 M²
2 Pasangan dinding pada atap 1 : 5 V2= tinggi x panjang x jumlah dinding
2.5 x 4.5 x 4 45 M²
TOTAL VOLUME KESELURUHAN 292.13 M²

1 Pelesteran dan aci 1 : 5 V= (V1 x 2) + (V2 x 2) V1 + V2


494.26 + 90 584.26 M²

V. PEKERJAAN LANTAI KERAMIK


1 Lantai keramik 30/30 cm Luas
90.5 90.5 M²

2 Lantai keramik KM/WC 20/20 cm luas


6.4 6.4 M²

3 Lantai keramik teras depan 30/30 cm luas


10 10 M²

4 Dinding keramik 20/20 cm KM/WC V= h x p tinggi x panjang dinding


2 x 14 28 M²

5 Dinding keramik 20/20 cm meja dapur panjang x lebar


3 x 0.7 2.1 M²

6 Plin keramik V=∑PK Keliling


106.9 106.9 M¹

VII.PEKERJAAN PLAFON
1 Plafon gipsum V= ∑CD +∑CL Jumlah yg akan dipasang + Bagian luar
90.5 + 20.8 111.3 M²

2 Lisplafon V=∑PLp panjang profil


90.5 90.5 M¹

IX. PEKERJAAN PINTU KUSEN DAN JENDELA


A. KUSEN KAYU
1 Kusen kayu P1 V= L x P lebar penampang x tinngi penampang x luas penampang
bxhxp 0.12 x 0.06 x 6.1 0.04392 Mᶟ

2 Kusen kayu P2 lebar penampang x tinggi penampang x luas


0.12 x 0.06 x 26.25 0.189 Mᶟ

3 kusen kayu P3 KM/WC lebar penampang x tinggi penampang x luas


0.12 x 0.06 x 9.68 0.069696 Mᶟ

4 kusen J1 lebar penampang x tinggi penampang x luas


0.12 x 0.06 x 40 0.288 Mᶟ
TOTAL 0.590616 Mᶟ

B. DAUN PINTU DAN JENDELA


1 P1 V= l x h x ∑p lebar x tinggi x jumlah
1.6 x 2.1 x 1 3.36 M²

2 P2 V= l x h x ∑p lebar x tinggi x jumlah


0.84 x 2.1 x 5 8.82 M²

3 P3 KM/WC V=∑P unit 2 unit

4 J1 V= l x h x ∑j1 lebar x tinggi x jumlah


0.6 x 1.7 x 8 8.16 M²
TOTAL 12.18 M²

PEKERJAAN CAT
1 Dinding
A. Dempul 586.26 M²
B. Cat 587.26 M²

2 plafon
A. Dempul 111.3 M²
B. Cat 111.3 M²

3 Kusen P1,P2,P3,J1 0.590616 M²

4 Daun pintu P1,P2 M²


12.18

PEKERJAAN ATAP
1 Gording dan nok V= b x h x p lebar penampang x tinggi penampang x jumlah semua penampang
0.08 x 0.12 x 80.5 0.7728 Mᶟ

2 Kaso V= ∑LA Panjang atap jarak kaso sisi atap


12.6 : 0.45 x 2 56 bh

3 reng panjang usuk jarak panjang atap sisi atap


4 : 0.2 x 12.6 x 2 504 M¹

4 Lisplank kayu 2/30 V= ∑LP 31.3 M¹

5 pemasangan 1 M² genteng metal (80/100) V= ∑LA 186 M²

6 Nok genteng V= ∑NB 12.6 M¹

PEKERJAAN SANITAIR
1 bak air fiber glass 60 x 60 1 bh
bak air fiber glass 70 x 70 1 bh

2 kloset jongkok (merek amerika standard) 1 bh


kloset jongkok (merek totto) 1 bh

3 keran air biasa 1 bh


kran air mutu bagus 1 bh
keran angsa meja dapur 1 bh

4 floor drain (mutu bagus) 2 bh

5 kichen sink pda dapur 1 bh

PEKERJAAN INSTALASI AIR


1 Air kotor
pipa diameter 2 inci 10.5 m¹
pipa keni diameter 2 inci 5 bh
pipa tee diameter 2 inci 1 bh
pipa diameter 4 inci 7.5 m¹
pipa kene diameter 4 inci 2 bh
akesori lain( lem pipa,amplas) 1 Ls

Air bersih
pipa diameter 3/4 inci 20 m¹
pipa keni diameter 23/4 inci 11 bh
pipa tee diameter 3/4 inci 8 bh
pipa tee sokdrat luar dalam 0,75 inci 1 bh
akesori lain (lem pipa,amplas) 1 Ls

2 Septictank dan rembesan 1 unit

3 Penyambungan air dari PAM 1 unit

PEKERJAAN INSTALASI LISTRIK


1 Jumlah titik lampu keseluruhan 15 titik

2 instalasi titik daya stop kontak 3 titik

3 lampu
lampu baret 1 titik
lampu SL 5 titik
lampu taman 2 titik
lampu TL 1 X 18 7 titik

4 Panel listrik 1 bh

5 penyambungan daya listrik ke PLN 1 Ls

Anda mungkin juga menyukai