Halaman 2
NO. JENIS BAHAN SATUAN HARGA (Rp.) KETERANGAN
1 2 3 4 5
46 Kapur padam M3
47 Semen Plesteran Dinding Bata Ringan (PM - 200) Kg
48 Semen Acian Dinding Bata Ringan (PM - 300) Kg
49 Semen Perekat Dinding Bata Ringan (PM -110) Kg
50 Floor Hardener (MU 700) Kg
51 Compound Zak
52 Panel Beton Pracetak Uk.5 x 40 x 240 cm K.250 Lbr
53 Kolom Beton Pracetak Panjang 3 M' K.250 Btg
54 Kolom Beton Pracetak Sudut Panjang 3 M' K.250 Btg
Halaman 3
NO. JENIS BAHAN SATUAN HARGA (Rp.) KETERANGAN
1 2 3 4 5
48 Triplek 6 mm Lbr
49 Triplek 8 mm Lbr
50 Triplek 9 mm Lbr
51 Lambresering M2
Halaman 4
NO. JENIS BAHAN SATUAN HARGA (Rp.) KETERANGAN
1 2 3 4 5
53 Rangka Hollow 40 x 40 x 0,3 mm M'
54 Rangka Hollow 40 x 40 x 0,4 mm M'
55 Rangka Hollow 40 x 20 x 0,8 mm M'
56 Rangka Hollow 40 x 20 x 0,25 mm M'
57 Rangka Hollow 40 x 20 x 0,4 mm M'
58 Spandrell uk. 11 cm x 6 m Lbr
59 UNP 50.50 (6 m) Btg
60 UNP 100.100 (6 m) Btg
61 UNP 150.150 (6 m) Btg
62 UNP 200.200 (6 m) Btg
63 CNP 125.50.20 tebal 2,2 mm (6 m) Btg
64 CNP 125.50.20 tebal 3 mm (6 m) Btg
65 CNP 100.50.20 tebal 2,2 mm (6 m) Btg
66 CNP 100.50.20 tebal 3 mm (6 m) Btg
67 CNP 75.35.20 tebal 2 mm (6 m) Btg
68 CNP 75.45.20 tebal 2,2 mm (6 m) Btg
69 CNP 75.45.15 tebal 2,2 mm (6 m) Btg
70 CNP 75.45.15 tebal 1,8 mm (6 m) Btg
71 CNP 75.35.15 tebal 1,5 mm (6 m) Btg
72 Canal 100 MMI (6 m) Btg
73 Canal 75 MMI (6 m) Btg
74 Canal 75 Polos (6 m) Btg
75 Canal 75 JP (6 m) Btg
76 Canal 75 GG (6 m) Btg
77 Canal 72 MMI (6 m) Btg
78 Canal 72 Polos (6 m) Btg
79 Reng 32 MMI Btg
80 Reng 30 MMI Btg
81 Reng 28 MMI Btg
82 Reng 32 JP Btg
83 Reng 30 JP Btg
84 Plat Aluminium ( 90 x 200 ) cm Lbr
85 Aluminium Composit Panel (ACP) (Indoor) M2
86 Aluminium Composit Panel (ACP) (Outdoor) Type PVDF t. 5 mm M2
87 Besi tempa untuk teralis pagar (rangkap) M2
88 Kawat beton Kg
89 Kawat F4, t. 4 mm (Penggantung Plafond) Btg
90 Kawat harmonika M2
91 Kawat nyamuk (Ram nyamuk hijau) M2
92 Kawat duri M'
93 Kawat Bronjong Galvanis Uk. 2 x 1 x 0,5 M3
94 Karung Plastik Kap. 50 kg Bh
95 Ram kawat hitam (saringan) M2
96 Paku sekrup Bh
97 Paku triplek Kg
98 Paku asbes Kg
99 Paku pancing Kg
100 Paku payung asbes Kg
101 Paku payung Sekrup Kg
102 Paku biasa 2"-5" Kg
103 Paku biasa 1/2" - 1" Kg
104 Paku gypsum Kg
105 Paku beton ( 2 cm s/d 12 cm) Kg
106 Timbal t. 3 mm (Uk. 1 x 10 m) Lbr
107 Skrup Fixer Bh
108 Baud D.12 mm Bh
109 Baud D.16 mm Bh
110 Baud D.19 mm Bh
Halaman 5
NO. JENIS BAHAN SATUAN HARGA (Rp.) KETERANGAN
1 2 3 4 5
111 Dina Bolt M 12 P. 6 - 12 cm Bh
112 Kawat las listrik Kg
113 Shadow Line Btg
114 Daun Pintu Aluminium Natural dengan kaca lengkap acesories Unit
115 Daun Pintu Aluminium Warna dengan kaca lengkap acesories Unit
116 Daun Pintu Frameless Kaca Bening 10 mm lengkap acesories Unit
117 Daun Pintu Sliding Aluminium dengan kaca lengkap acesories Unit
118 Daun Pintu Kaca Tempered t.12 mm lengkap acesories Unit
119 Daun jendela Casement Allumunium Natural dgn kaca + Accs. M2
120 Daun jendela Casement Allumunium Warna dgn kaca + Accs. M2
121 Siku Alumunium M'
122 List Stainless T Btg
123 Lapisan HPL 120 x 240 Cm M2
124 HPL Art Foam Pure Lunch Lbr
125 HPL ex-Himel Lbr
126 HPL ex-Taco (Polos/Biasa) Lbr
127 HPL ex-Taco (Texture) Lbr
128 Edging HPL m'
129 Kusen Aluminium Standar Natural 4" M'
130 Kusen Aluminium Standar Natural 3" M'
131 Kusen Aluminium Warna Doff 4" M'
132 Kusen Aluminium Warna Doff 3" M'
133 Kusen Aluminium Warna 4" M'
134 Kusen Aluminium Warna 3" M'
135 Polycarbonate Sheet / Twin Lite Uk.11,8 x 2,1 t. 5 mm Lbr
136 Polycarbonate + kerangka besi M2
137 Polycarbonate + kerangka stainless steel M2
138 Folding Gate (Pintu Lipat) M2
139 Fibre Glass ( Acyrlic ) tebal 5 mm Lbr
140 Rolling Door / Grille M2
141 Pintu Henderson M2
142 Pagar BRC tinggi 120 cm, p.240 cm Lbr
143 Pagar BRC tinggi 60 cm, p.240 cm tbl. 5 mm Lbr
144 Pagar BRC tinggi 90 cm, p.240 cm tbl. 5 mm Lbr
145 Kuda - kuda Baja Ringan Zingallum tbl. 0,75 mm M2
146 Wiremesh M-5 uk. 2,10 x 5,40 m M2
147 Wiremesh M-6 uk. 2,10 x 5,40 m M2
148 Wiremesh M-8 uk. 2,10 x 5,40 m M2
149 Wiremesh M-10 uk. 2,10 x 5,40 m M2
150 Tiang Pancang Kotak Masif 25 x 25 klas A K-500 (P. 6 s/d. 8) M'
151 Tiang Pancang Kotak Masif 25 x 25 klas B K-500 (P. 6 s/d. 8) M'
152 Tiang Pancang Kotak Masif 25 x 25 klas C K-500 (P. 6 s/d. 8) M'
153 Sambungan TP Kotak 25x25 - Kelas A joint
154 Sambungan TP Kotak 25x25 - Kelas B joint
155 Sambungan TP Kotak 25x25 - Kelas C joint
156 Tiang Pancang Kotak Masif 20 x 20 klas A K-500 (P. 6 s/d. 9) M'
157 Tiang Pancang Segitiga (Triangular ) 22 Kelas A K-500 (P.6) M'
158 Tiang Pancang Segitiga (Triangular ) 24 Kelas A K-500 (P.6) M'
159 Tiang Pancang Segitiga (Triangular ) 26 Kelas A K-500 (P.6) M'
160 Tiang Pancang Segitiga (Triangular ) 28 Kelas A K-500 (P.6 s.d/.8) M'
161 Tiang Pancang Segitiga (Triangular ) 28 Kelas B K-500 (P.6 s.d/.9) M'
162 Tiang Pancang Segitiga (Triangular ) 30 Kelas A K-500 (P.6 s.d/.8) M'
163 Tiang Pancang Segitiga (Triangular ) 30 Kelas B K-500 (P.6 s.d/.9) M'
164 Tiang Pancang Segitiga (Triangular ) 32 Kelas A K-500 (P.6 s.d/.8) M'
165 Tiang Pancang Segitiga (Triangular ) 32 Kelas B K-500 (P.6 s.d/.9) M'
166 Tiang Pancang Beton Bulat d. 300 (p. 6 s/d. 8) Bottom M'
167 Tiang Pancang Beton Bulat d. 300 (p. 6 s/d. 8) Middle M'
168 Tiang Pancang Beton Bulat d. 300 (p. 9 s/d. 11) Bottom M'
Halaman 6
NO. JENIS BAHAN SATUAN HARGA (Rp.) KETERANGAN
1 2 3 4 5
169 Tiang Pancang Beton Bulat d. 300 (p. 9 s/d. 11) Middle M'
170 Tiang Pancang Beton Bulat d. 300 (p. 12 s/d. 13) Bottom M'
171 Tiang Pancang Beton Bulat d. 300 (p. 12 s/d. 13) Middle M'
172 Tiang Pancang Beton Bulat d. 350 (p. 6 s/d. 8) Bottom M'
173 Tiang Pancang Beton Bulat d. 350 (p. 6 s/d. 8) Middle M'
174 Tiang Pancang Beton Bulat d. 350 (p. 9 s/d. 11) Bottom M'
175 Tiang Pancang Beton Bulat d. 350 (p. 9 s/d. 11) Middle M'
176 Tiang Pancang Beton Bulat d. 350 (p. 12 s/d. 14) Bottom M'
177 Tiang Pancang Beton Bulat d. 350 (p. 12 s/d. 14) Middle M'
178 Tiang Pancang Beton Bulat d. 350 (p. 15) Bottom M'
179 Tiang Pancang Beton Bulat d. 350 (p. 15) Middle M'
180 Tiang Pancang Beton Bulat d. 400 (p. 6 s/d. 8) Bottom M'
181 Tiang Pancang Beton Bulat d. 400 (p. 6 s/d. 8) Middle M'
182 Tiang Pancang Beton Bulat d. 400 (p. 9 s/d. 11) Bottom M'
183 Tiang Pancang Beton Bulat d. 400 (p. 9 s/d. 11) Middle M'
184 Tiang Pancang Beton Bulat d. 400 (p. 12 s/d. 14) Bottom M'
185 Tiang Pancang Beton Bulat d. 400 (p. 12 s/d. 14) Middle M'
186 Tiang Pancang Beton Bulat d. 400 (p. 15 s/d. 16) Bottom M'
187 Tiang Pancang Beton Bulat d. 400 (p. 15 s/d. 16) Middle M'
188 Tiang Pancang Beton Bulat d. 450 (p. 6 s/d. 8) Bottom M'
189 Tiang Pancang Beton Bulat d. 450 (p. 6 s/d. 8) Middle M'
190 Tiang Pancang Beton Bulat d. 450 (p. 9 s/d. 11) Bottom M'
191 Tiang Pancang Beton Bulat d. 450 (p. 9 s/d. 11) Middle M'
192 Tiang Pancang Beton Bulat d. 450 (p. 12 s/d. 14) Bottom M'
193 Tiang Pancang Beton Bulat d. 450 (p. 12 s/d. 14) Middle M'
194 Tiang Pancang Beton Bulat d. 450 (p. 15 s/d. 16) Bottom M'
195 Tiang Pancang Beton Bulat d. 450 (p. 15 s/d. 16) Middle M'
196 Tiang Pancang Beton Bulat d. 500 (p. 6 s/d. 8) Bottom M'
197 Tiang Pancang Beton Bulat d. 500 (p. 6 s/d. 8) Middle M'
198 Tiang Pancang Beton Bulat d. 500 (p. 9 s/d. 11) Bottom M'
199 Tiang Pancang Beton Bulat d. 500 (p. 9 s/d. 11) Middle M'
200 Tiang Pancang Beton Bulat d. 500 (p. 12 s/d. 14) Bottom M'
201 Tiang Pancang Beton Bulat d. 500 (p. 12 s/d. 14) Middle M'
202 Tiang Pancang Beton Bulat d. 500 (p. 15 s/d. 16) Bottom M'
203 Tiang Pancang Beton Bulat d. 500 (p. 15 s/d. 16) Middle M'
204 Tiang Pancang Beton Bulat d. 600 (p. 6 s/d. 8) Bottom M'
205 Tiang Pancang Beton Bulat d. 600 (p. 6 s/d. 8) Middle M'
206 Tiang Pancang Beton Bulat d. 600 (p. 9 s/d. 11) Bottom M'
207 Tiang Pancang Beton Bulat d. 600 (p. 9 s/d. 11) Middle M'
208 Tiang Pancang Beton Bulat d. 600 (p. 12 s/d. 14) Bottom M'
209 Tiang Pancang Beton Bulat d. 600 (p. 12 s/d. 14) Middle M'
210 Tiang Pancang Beton Bulat d. 600 (p. 15 s/d. 16) Bottom M'
211 Tiang Pancang Beton Bulat d. 600 (p. 15 s/d. 16) Middle M'
GIRDER H-90 cm
1 PC. I Girder H-90 cm L-12,6m, Ctc-185, K.500 M'
2 PC. I Girder H-90 cm L-13,6m, Ctc-185, K.500 M'
3 PC. I Girder H-90 cm L-14,6m, Ctc-185, K.500 M'
4 PC. I Girder H-90 cm L-15,6m, Ctc-185, K.500 M'
5 PC. I Girder H-90 cm L-16,6m, Ctc-185, K.500 M'
GIRDER H-125 cm
1 PC. I Girder H-125 cm L-16,6m, Ctc-185, K.500 M'
2 PC. I Girder H-125 cm L-17,6m, Ctc-185, K.500 M'
3 PC. I Girder H-125 cm L-18,6m, Ctc-185, K.500 M'
4 PC. I Girder H-125 cm L-19,6m, Ctc-185, K.500 M'
5 PC. I Girder H-125 cm L-20,6m, Ctc-185, K.500 M'
6 PC. I Girder H-125 cm L-21,6m, Ctc-185, K.500 M'
7 PC. I Girder H-125 cm L-22,6m, Ctc-185, K.600 M'
8 PC. I Girder H-125 cm L-23,6m, Ctc-185, K.700 M'
Halaman 7
NO. JENIS BAHAN SATUAN HARGA (Rp.) KETERANGAN
1 2 3 4 5
GIRDER H-160 cm
1 PC. I Girder H-160 cm L-22,6m, Ctc-185, K.500 M'
2 PC. I Girder H-160 cm L-23,6m, Ctc-185, K.500 M'
3 PC. I Girder H-160 cm L-24,6m, Ctc-185, K.500 M'
4 PC. I Girder H-160 cm L-25,6m, Ctc-185, K.500 M'
5 PC. I Girder H-160 cm L-26,6m, Ctc-185, K.500 M'
6 PC. I Girder H-160 cm L-27,6m, Ctc-185, K.500 M'
7 PC. I Girder H-160 cm L-28,6m, Ctc-185, K.500 M'
8 PC. I Girder H-160 cm L-29,6m, Ctc-185, K.500 M'
9 PC. I Girder H-160 cm L-30,6m, Ctc-140, K.600 M'
10 PC. I Girder H-160 cm L-31,6m, Ctc-140, K.600 M'
GIRDER H-170 cm
1 PC. I Girder H-170 cm L-30,8m, Ctc-185, K.500 M'
2 PC. I Girder H-170 cm L-31,8m, Ctc-185, K.500 M'
3 PC. I Girder H-170 cm L-32,8m, Ctc-185, K.500 M'
4 PC. I Girder H-170 cm L-33,8m, Ctc-185, K.500 M'
5 PC. I Girder H-170 cm L-34,8m, Ctc-185, K.500 M'
6 PC. I Girder H-170 cm L-35,8m, Ctc-185, K.500 M'
7 PC. I Girder H-170 cm L-36,8m, Ctc-185, K.700 M'
8 PC. I Girder H-170 cm L-37,8m, Ctc-185, K.700 M'
9 PC. I Girder H-170 cm L-38,8m, Ctc-185, K.700 M'
10 PC. I Girder H-170 cm L-39,8m, Ctc-140, K.700 M'
11 PC. I Girder H-170 cm L-40,8m, Ctc-140, K.700 M'
12 PC. I Girder H-170 cm L-41,8m, Ctc-140, K.700 M'
GIRDER H-210 cm
1 PC. I Girder H-210 cm L-35,8m, Ctc-185, K.500 M'
2 PC. I Girder H-210 cm L-36,8m, Ctc-185, K.500 M'
3 PC. I Girder H-210 cm L-37,8m, Ctc-185, K.500 M'
4 PC. I Girder H-210 cm L-38,8m, Ctc-185, K.500 M'
5 PC. I Girder H-210 cm L-39,8m, Ctc-185, K.500 M'
6 PC. I Girder H-210 cm L-40,8m, Ctc-185, K.600 M'
7 PC. I Girder H-210 cm L-41,8m, Ctc-185, K.600 M'
8 PC. I Girder H-210 cm L-42,8m, Ctc-185, K.600 M'
9 PC. I Girder H-210 cm L-43,8m, Ctc-185, K.600 M'
10 PC. I Girder H-210 cm L-44,8m, Ctc-185, K.700 M'
11 PC. I Girder H-210 cm L-45,8m, Ctc-185, K.700 M'
12 PC. I Girder H-210 cm L-46,8m, Ctc-140, K.700 M'
13 PC. I Girder H-210 cm L-47,8m, Ctc-140, K.700 M'
14 PC. I Girder H-210 cm L-48,8m, Ctc-140, K.700 M'
15 PC. I Girder H-210 cm L-49,8m, Ctc-140, K.700 M'
16 PC. I Girder H-210 cm L-50,8m, Ctc-140, K.700 M'
DIAFRAGMA
1 Diafragma PC. I Girder H-90cm, Ctc-185 cm, K.350 M'
2 Diafragma PC. I Girder H-90cm, Ctc-140 cm, K.350 M'
3 Diafragma PC. I Girder H-125cm, Ctc-185 cm, K.350 M'
4 Diafragma PC. I Girder H-125cm, Ctc-140 cm, K.350 M'
5 Diafragma PC. I Girder H-160cm, Ctc-185 cm, K.350 M'
6 Diafragma PC. I Girder H-160cm, Ctc-140 cm, K.350 M'
7 Diafragma PC. I Girder H-170cm, Ctc-185 cm, K.350 M'
8 Diafragma PC. I Girder H-170cm, Ctc-140 cm, K.350 M'
9 Diafragma PC. I Girder H-210cm, Ctc-185 cm, K.350 M'
10 Diafragma PC. I Girder H-210cm, Ctc-140 cm, K.350 M'
PLAT DECK
Platdeck Pracetak PC I Garder H-90 cm ; Ctc-185 cm
11 M'
(100cmx160cmx7cm) ; K.350
Platdeck Pracetak PC I Garder H-90 cm ; Ctc-140 cm
12 M'
(100cmx160cmx7cm) ; K.350
Halaman 8
NO. JENIS BAHAN SATUAN HARGA (Rp.) KETERANGAN
1 2 3 4 5
Platdeck Pracetak PC I Garder H-125 cm ; Ctc-185 cm
13 M'
(100cmx160cmx7cm) ; K.350
Platdeck Pracetak PC I Garder H-125 cm ; Ctc-140 cm
14 M'
(100cmx160cmx7cm) ; K.350
Platdeck Pracetak PC I Garder H-160 cm ; Ctc-185 cm
15 M'
(100cmx160cmx7cm) ; K.350
Platdeck Pracetak PC I Garder H-160 cm ; Ctc-140 cm
16 M'
(100cmx160cmx7cm) ; K.350
Platdeck Pracetak PC I Garder H-170 cm ; Ctc-185 cm
17 M'
(100cmx160cmx7cm) ; K.350
Platdeck Pracetak PC I Garder H-170 cm ; Ctc-140 cm
18 M'
(100cmx160cmx7cm) ; K.350
Platdeck Pracetak PC I Garder H-210 cm ; Ctc-185 cm
19 M'
(100cmx160cmx7cm) ; K.350
Platdeck Pracetak PC I Garder H-210 cm ; Ctc-140 cm
20 M'
(100cmx160cmx7cm) ; K.350
Halaman 9
NO. JENIS BAHAN SATUAN HARGA (Rp.) KETERANGAN
1 2 3 4 5
b = 1,10, h = 1,80 M'
16 Pintu Sorong Baja (satu draad) stang
b = 1,20, h = 0,50 M'
b = 1,20, h = 1,00 M'
b = 1,20, h = 1,80 M'
17 Pintu Sorong Baja (satu draad) stang
b = 1,30, h = 1,00 M'
b = 1,30, h = 1,50 M'
b = 1,30, h = 2.00 M'
18 Pintu Sorong Baja (dua draad) stang
b = 1,40, h = 1,00 M'
b = 1,40, h = 1,50 M'
b = 1,40, h = 2,00 M'
19 Pintu Sorong Baja (dua draad) stang
b = 1,50, h = 1,00 M'
b = 1,50, h = 1,50 M'
b = 1,50, h = 2,00 M'
20 Pintu Sorong Baja (dua draad) stang
b = 1,60, h = 1,00 M'
b = 1,60, h = 1,50 M'
b = 1,60, h = 2,00 M'
21 Pintu Sorong Baja (dua draad) stang
b = 1,70, h = 1,00 M'
b = 1,70, h = 1,50 M'
b = 1,70, h = 2,00 M'
22 Pintu Sorong Baja (dua draad) stang
b = 1,80, h = 1,00 M'
b = 1,80, h = 1,50 M'
b = 1,80, h = 2,00 M'
23 Pintu Sorong Baja (dua draad) stang
b = 1,90, h = 1,00 M'
b = 1,90, h = 1,50 M'
b = 1,90, h = 2,00 M'
24 Pintu Sorong Baja (dua draad) stang
b = 2,00, h = 1,00 M'
b = 2,00, h = 1,50 M'
b = 2,00, h = 2,00 M'
Halaman 10
NO. JENIS BAHAN SATUAN HARGA (Rp.) KETERANGAN
1 2 3 4 5
20 Pipa GIP medium B d. 3" (P.6 m / btg ) M'
21 Pipa GIP medium B d. 6" (P.6 m / btg ) M'
22 Pipa GIP medium B d. 8" (P.6 m / btg ) M'
23 Pipa PVC 1/2" AW M'
24 Pipa PVC 3/4" AW M'
25 Pipa PVC 1" AW M'
26 Pipa PVC 1 1/4" AW M'
27 Pipa PVC 1 1/2" AW M'
28 Pipa PVC 2" AW M'
29 Pipa PVC 2 1/2" AW M'
30 Pipa PVC 3" AW M'
31 Pipa PVC 4" AW M'
32 Pipa PVC 5" AW M'
33 Pipa PVC 6" AW M'
34 Pipa PVC 8" AW M'
35 Pipa PVC 10" AW M'
36 Knee 45° AW 4" Bh
37 Knee 45° D 4" Bh
38 Knee 45° AW 3" Bh
39 Knee 45° D 3" Bh
40 Bak cuci piring stainnless steel Bh
41 Water drain besi (floor drain) Bh
42 Water Turn 500 Lt (Penguin) Bh
43 Water Turn 1000 Lt (Penguin) Bh
44 Kran air Kw. 2 Bh
45 Kran air Kw. 1 Bh
46 Stop kran 3/4" Bh
47 Stop kran 1/2" Bh
48 Stop kran 1" Bh
49 Stop kran 2" Bh
50 Jet Pump 350 watt Bh
51 Mesin Pompa Shimizu PS 128 Non Otomatis (Sedot) Bh
52 Mesin Pompa Shimizu PS 135 Otomatis (Sedot) Bh
53 Mesin Pompa Shimizu PS 133 Otomatis (Dorong) Bh
54 Mesin Pompa Shimizu PS 228 Otomatis (Dorong) Bh
55 Mesin Summersible Shimizu 1/3 hp Bh
56 Mesin Summersible Shimizu 1/2 hp Bh
57 Mesin Summersible Shimizu 3/4 hp Bh
58 Mesin Summersible Shimizu 1 hp Bh
59 Mesin Summersible Shimizu 1 1/2 hp Bh
60 Mesin Summersible Kyodo 2 hp Bh
61 Pintu Vynil KM/WC ( 190 x 70 ) Cm kw1 Unit
62 Pintu Vynil serat jati KM/WC ( 190 x 70 ) Cm kw1 Unit
63 Seal tape Bh
64 Floor drain plastik Bh
65 Floor drain alumunium Bh
66 Grefel beton d. 20 cm (Pjg. 1 M) Bh
67 Grefel beton d. 30 cm (Pjg. 1 M) Bh
68 Paving block warna 6 cm ( 50 Bh ) M2
69 Paving block warna 8 cm ( 50 Bh ) M2
70 Paving block natural 6 cm ( 50 Bh ) M2
71 Paving block natural 8 cm ( 50 Bh ) M2
72 Paving Ton natural uk. 20 x 10 t. 6 cm (50 Bh) M2
73 Paving Ton natural uk. 20 x 10 t. 8 cm (50 Bh) M2
74 Paving Ton warna uk. 20 x 10 t. 6 cm (50 Bh) M2
75 Paving Ton warna uk. 20 x 10 t. 8 cm (50 Bh) M2
76 Paving ton Truepave uk. 20 x 10 t. 6 cm (50 Bh) Ex CISANGKAN M2
77 Paving ton Truepave uk. 20 x 10 t. 8 cm (50 Bh) Ex CISANGKAN M2
Halaman 11
NO. JENIS BAHAN SATUAN HARGA (Rp.) KETERANGAN
1 2 3 4 5
78 Paving ton Truepave uk. 20 x 10 t. 10 cm (50 Bh) M2
79 Paving ton Halfpave uk. 10 x 10 t. 6 cm (100 Bh) M2
80 Paving ton Halfpave uk. 10 x 10 t. 8 cm (100 Bh) M2
81 Paving ton Fullpave uk. 20 x 20 t. 6 cm (25 Bh) M2
82 Paving ton Fullpave uk. 20 x 20 t. 8 cm (25 Bh) M2
83 Paving ton Topi Uskup uk. 28x20x10 cm t. 6 cm (20 Bh) M2
84 Paving ton Topi Uskup uk. 28x20x10 cm t. 8 cm (20 Bh) M2
85 Paving ton Intepave uk. 20 x 10 cm t. 6 cm (50 Bh) M2
86 Paving ton Intepave uk. 20 x 10 cm t. 8 cm (50 Bh) M2
87 Paving ton Clasic Set t. 6 cm M2
88 Paving ton Clasic Set t. 8 cm M2
89 Paving ton Altstadt Set t. 6 cm M2
90 Paving ton Altstadt Set t. 8 cm M2
91 Paving ton Hexagon t. 6 cm M2
92 Paving ton Hexagon t. 8 cm M2
93 Paving ton Octagon t. 6 cm M2
94 Paving ton Octagon t. 8 cm M2
95 Paving ton Natural t. 10 cm M2
96 Paving ton Kubus uk. 8 x 8 cm t. 6 cm (156 Bh) M2
97 Paving ton Kubus uk. 8 x 8 cm t. 8 cm (156 Bh) M2
98 Paving ton Quatro uk. 10 x 20 cm t. 6 cm (50 Bh) M2
99 Paving ton Quatro uk. 10 x 20 cm t. 8 cm (50 Bh) M2
100 Grassblock ton uk. 45 x 30 cm t. 6 (7,5 Bh) M2
101 Grassblock ton uk. 40 x 40 cm t. 8 (6,25 Bh) M2
102 Grassblock ton uk. 45 x 30 cm t. 10 (7,5 Bh) M2
103 Bataton U 14FS uk. 29 x 14 x 14 cm M'
104 Bataton U 14HS uk. 14 x 14 x 14 cm M'
105 Bataton H 14FS uk. 29 x 14 x 14 cm M2
106 Bataton H 14HS uk. 14 x 14 x 14 cm M2
107 Bataton H 10FS uk. 29 x 10 x 14 cm M2
108 Bataton H 10HS uk. 29 x 10 x 14 cm M2
109 Bataton Kolom uk. 29 x 29 x 14 cm M'
110 Curve Tile uk. 50 x 30 cm M2
111 Kusen Pintu uk. 200 x 90 x 14 cm Bh
112 Kusen Pintu WC uk. 200 x 75 x 14 cm Bh
113 Kusen Jendela uk. 120 x 75 x 14 cm Bh
114 Kusen Jendela Double uk. 150 x 120 x 14 cm Bh
115 Kusen Jendela Minimalis uk. 120 x 60 x 14 Bh
116 Kusen Jendela Minimalis uk. 165 x 60 x 14 Bh
117 Kusen Pintu Double uk. 210 x 160 x 14 cm Bh
118 Support Beam 300 cm (Balok Penyangga) uk. 300x10x6 Bh
119 Support Beam 180 cm (Balok Penyangga) uk. 180x10x6 Bh
120 Support Beam 165 cm (Balok Penyangga) uk. 165x10x6 Bh
121 Support Beam 150 cm (Balok Penyangga) uk. 150x10x6 Bh
122 Kansteen Beton (Uk. 60 x 30 cm) profil Bh
123 Kansteen Beton (Uk. 50 x 25 cm) t. 10 cm Bh
124 Kansteen K.03.1 (15.18.40) Bh
125 Kansteen K.03.2 (15.18.20) Bh
126 Kansteen K.03.3 (15.18.40) Bh
127 Kansteen K.04.2 (15.28.60) Bh
128 Kansteen K.04.2 (15.28.20) Bh
129 Kansteen K.04.3 (15.28.60) Bh
130 U-Ditch 300 x 300 Bh
131 U-Ditch 300 x 400 Bh
132 U-Ditch 400 x 400 Bh
133 U-Ditch 400 x 500 Bh
134 U-Ditch 400 x 600 Bh
135 U-Ditch 500 x 500 Bh
Halaman 12
NO. JENIS BAHAN SATUAN HARGA (Rp.) KETERANGAN
1 2 3 4 5
136 U-Ditch 500 x 600 Bh
137 U-Ditch 500 x 700 Bh
138 U-Ditch 600 x 600 Bh
139 U-Ditch 600 x 700 Bh
140 U-Ditch 600 x 700 x 1200 Bh
141 U-Ditch 600 x 800 Bh
142 U-Ditch 800 x 800 Bh
143 U-Ditch 800 x 900 Bh
144 U-Ditch 800 x 1000 Bh
145 U-Ditch 1000 x 1000 x 1200 Bh
146 U-Ditch 2000 x 2000 Bh
147 Tutup U-Ditch Light Duty CUD 300 LD Bh
148 Tutup U-Ditch Light Duty CUD 400 LD Bh
149 Tutup U-Ditch Light Duty CUD 500 LD Bh
150 Tutup U-Ditch Light Duty CUD 600 LD Bh
151 Tutup U-Ditch Light Duty CUD 800 LD Bh
152 Tutup U-Ditch Heavy Duty CUD 300 LD Bh
153 Tutup U-Ditch Heavy Duty CUD 400 LD Bh
154 Tutup U-Ditch Heavy Duty CUD 500 LD Bh
155 Tutup U-Ditch Heavy Duty CUD 600 LD Bh
156 Tutup U-Ditch Heavy Duty CUD 800 LD Bh
157 Box Culvert 400 x 400 x 1000 Bh
158 Box Culvert 500 x 500 x 1000 Bh
159 Box Culvert 600 x 600 x 1000 Bh
160 Box Culvert 800 x 800 x 1000 Bh
161 Box Culvert 800 x 800 x 1200 Bh
162 Box Culvert 1000 x 1000 x 1000 Bh
163 Box Culvert 1000 x 1000 x 1200 Bh
164 Box Culvert 1200 x 1200 x 1000 Bh
165 Box Culvert 1500 x 1500 x 1000 Bh
166 Box Culvert 1500 x 1500 x 1200 Bh
167 Box Culvert 1800 x 1800 x 1000 Bh
168 Box Culvert 2000 x 1000 x 1000 Bh
169 Box Culvert 2000 x 2000 x 1000 Bh
170 Buis beton D. 20 (Pjg. 1 M, T= 3.5 Cm) Bh
171 Buis beton D. 30 (Pjg. 1 M, T= 3.5 Cm) Bh
172 Buis beton D. 40 (Pjg. 1 M, T= 5 Cm) Bh
173 Buis beton D. 50 (Pjg. 1 M, T= 8 Cm) Bh
174 Buis beton D. 60 (Pjg. 1 M, T= 8 Cm) Bh
175 Buis beton D. 70 (Pjg. 1 M, T= 8 Cm) Bh
176 Buis beton D. 60 (Pjg. 0,5 M, T= 8 Cm) Bh
177 Buis beton D. 80 (Pjg. 0,5 M, T= 8 Cm) Bh
178 Buis beton D. 100 (Pjg. 0,5 M, T=10 Cm) Bh
179 Waterstop PVC 150 mm m'
180 Waterstop PVC 200 mm m'
181 Roof drain plastik 4" Bh
182 Roof drain besi 4" Bh
Halaman 13
NO. JENIS BAHAN SATUAN HARGA (Rp.) KETERANGAN
1 2 3 4 5
10 Papan Lisplank GRC L = 0,20 M, P. 2,40 M Lbr
11 Papan Lisplank GRC L = 0,10 M, P. 2,40 M Lbr
12 Spandek t. 0,3 mm Uk. 110 x 600 cm Lbr
13 Spandek t. 0,25 mm Uk.110 x 600 cm Lbr
14 Plat asbes T = 4 mm Uk. 100 x 100 cm Lbr
15 Plat asbes T = 5 mm Uk. 100 x 100 cm Lbr
16 Plafond GRC uk. 120 cm x 240 cm Lbr
17 Plafond gypsum uk. 120 cm x 240 cm Lbr
18 Plafond akustik uk. 60 cm x 120 cm Lbr
19 Plafond PVC Shunda Plafon Polos, L. 30 cm M2
20 Plafond PVC Shunda Plafon Motif, L. 30 cm M2
21 Plafond PVC Shunda Plafon Coklat, L. 30 cm M2
22 Plafond PVC Shunda Plafon Coklat Urat Jati, L. 30 cm M2
23 List Plafon PVC, L. 4 cm Putih M'
24 List Plafon PVC, L. 4 cm Coklat M'
25 List Plafon PVC, L. 7 cm M'
26 Asbes gelombang besar 5 mm 105 x 150 Lbr
27 Asbes gelombang besar 5 mm 105 x 300 Lbr
28 Asbes gelombang kecil 4 mm 105 x 150 Lbr
29 Asbes gelombang kecil 4 mm 80 x 150 Lbr
30 Asbes gelombang kecil 4 mm 80 x 180 Lbr
31 Asbes gelombang kecil 4 mm 80 x 210 Lbr
32 Asbes gelombang kecil 4 mm 80 x 240 Lbr
33 Asbes gelombang kecil 4 mm 80 x 360 Lbr
34 Asbes gelombang kecil 4 mm 105 x 210 Lbr
35 Asbes gelombang kecil 4 mm 105 x 240 Lbr
36 Asbes gelombang kecil 4 mm 105 x 300 Lbr
37 Asbes gelombang kecil 4 mm 105 x 360 Lbr
38 Asbes gelombang 5 mm 92 x 250 Lbr
39 Asbes gelombang 4 mm 92 x 250 Lbr
40 Asbes gelombang 5 mm 92 x 225 Lbr
41 Asbes gelombang 4 mm 92 x 225 Lbr
42 Baja Ringan Zincallume t. 0,75 mm M2
43 Baja Ringan Zincallume t. 1,00 mm M2
44 Rangka Baja Ringan Zincallume C70 t. 0,7 mm (6 m) Btg
45 Rangka Baja Ringan Zincallume C70 t. 0,75 mm (6 m) Btg
46 Rangka Baja Ringan Zincallume C70 t. 0,8 mm (6 m) Btg
47 Rangka Baja Ringan Zincallume C75 t. 0,75 mm (6 m) setara Taso Btg
48 Rangka Baja Ringan Zincallume C75 t. 1 mm (6 m) setara Taso Btg
49 Rangka Baja Ringan Zincallume C75 t. 1 mm (6 m) setara Taso Btg
50 Reng Baja Ringan Zincallume t.0,65 mm (6 m) Btg
51 Reng Baja Ringan Zincallume t.0,75 mm (6 m) Btg
52 Genteng plentong kecil (bakar) Bh
53 Genteng plentong super (bakar) Bh
54 Genteng kodok Natural Bh
55 Genteng kodok Glazuur Bh
56 Genteng kodok / Alto transparant (brown) Bh
57 Genteng keramik morando natural Bh
58 Genteng keramik morando transparan Bh
59 Genteng keramik morando warna Bh
60 Genteng beton Natural Bh
61 Genteng beton (setara Cisangkan - Victoria) Bh
62 Genteng metal M2
63 Genteng metal pasir 2 x 4 M2
64 Genteng metal polos 2 x 4 M2
65 Genteng metal Multi Roof t. 0,4 mm M2
66 Genteng metal Multi Roof t. 0,3 mm M2
67 Genteng metal Multi Roof t. 25 mm M2
Halaman 14
NO. JENIS BAHAN SATUAN HARGA (Rp.) KETERANGAN
1 2 3 4 5
68 Genteng metal Sakura t. 0,25 mm M2
69 Genteng metal Sakura t. 0,3 mm M2
70 Genteng Tegola M2
71 Genteng Bitumen Gelombang Monolayer Uk.200x97x0.3 cm (Onduline) Lbr
72 Genteng Bitumen Gelombang Monolayer Uk.106x40x0.3 cm (Onduvila) Lbr
73 Nok / Rigde Bitumen Lbr
74 Bubung genteng plentong kecil Bh
75 Bubung genteng plentong super Bh
76 Bubung genteng kodok / Alto natural Bh
77 Bubung genteng kodok / Alto transparan (brown) Bh
78 Bubung genteng morando natural Bh
79 Bubung genteng morando transparan Bh
80 Bubung genteng morando warna Bh
81 Bubung genteng beton natural Bh
82 Bubung genteng beton (setara Cisangkan) Bh
83 Bubung genteng metal (p.90 cm) Bh
84 Bubung genteng metal natural Type U (p.100 cm) Bh
85 Bubung genteng metal berpasir (p.90 cm) Bh
86 Bubung genteng metal Warna Kotak (p.100 cm) Bh
87 Bubung genteng metal Warna Type 1/2 Lingkaran (p.100 cm) Bh
88 Nok / Rigde Tepi Bitumen Lbr
89 Nok stel gelombang M'
90 Seng gelombang BJLS 28 (80 x 180) Lbr
91 Seng gelombang BJLS 30 (80 x 180) Lbr
92 Seng Plat BJLS 28 Lbr
93 Seng Plat BJLS L. 90 Cm M'
94 Seng Plat BJLS L. 75 Cm M'
95 Seng Plat BJLS L. 60 Cm M'
96 Seng Plat BJLS L. 55 Cm M'
97 Seng Plat BJLS L. 45 Cm M'
Halaman 15
NO. JENIS BAHAN SATUAN HARGA (Rp.) KETERANGAN
1 2 3 4 5
27 Granit tile 60 x 60 cm (Halus) (setara Ex. Cina) M2
28 Granit tile 60 x 60 cm (Kasar) (setara indogress) M2
29 Granit tile 60 x 60 cm (Black) M2
30 Granit tile 3D 60 x 60 cm M2
31 Granit tile 80 x 80 cm M2
32 Granit tile 80 x 80 cm (setara indogress) M2
33 Granit tile 80 x 80 cm (setara Marco) M2
34 Granit tile 120 x 60 cm (Halus) M2
35 Granit tile 120 x 60 cm (Halus) (setara indogress) M2
36 Granit tile 120 x 60 cm (Halus) (setara Ex. Cina) M2
37 Granit slab (Batu) DN M2
38 Marmer Uk. 1 x 1 m M2
39 Stepnose 10 x 30 cm / anti slip Bh
40 Stepnose 10 x 40 cm / anti slip Bh
41 Stepnose 10 x 60 cm / anti slip Bh
42 Kuku Macan Polos M'
43 Kuku Macan Spiral M'
44 Tegel Badak Natural 20 x 20 cm Bh
45 Tegel Badak Natural 30 x 30 cm Bh
46 Tegel Badak Warna 20 x 20 cm Bh
47 Tegel Badak Warna 30 x 30 cm Bh
48 Tegel Cor Beton press warna alami uk. 20 x 20 cm M2
49 Tegel Cor Beton press warna alami uk. 30 x 30 cm M2
50 Parquet jati M2
51 Lantai Vynil Daichi Uk. 15 x 90 cm M2
52 Lantai Vynil Taco Uk. 15 x 90 cm M2
53 Wall paper M2
54 Wall paper Sticker Kertasive (Polos) M2
55 Wall paper Sticker Kertasive (Urat Kayu) M2
56 PVC Penutup Dinding Uk. 0,2 x 3 m M2
57 Roster Terawang 10 x 20 Bh
58 Roster Terawang 20 x 20 Bh
59 Roster Beton 20 x 20 Bh
60 Roster Kayu uk. 15 x 30 Bh
61 Roster Kayu uk. 20 x 20 Bh
62 Roster Genteng uk. 10 x 20 Bh
63 Roster Batu alam uk.15 x 15 Bh
64 Roster Batu alam uk. 30 x 30 Bh
65 Roster Batu alam uk. 20 x 50 Bh
66 Melati Beton Bh
67 Conblock Regular Full 15.01 Bh
68 Bataton U 14FS uk. 29 x 14 x 14 cm M'
69 Bataton U 14HS uk. 14 x 14 x 14 cm M'
70 Bataton H 14FS uk. 29 x 14 x 14 cm M2
Batu Andesit Alur Polos
71 Ukuran 10 x 20 M2
72 Ukuran 10 x 30 M2
73 Ukuran 15 x 30 M2
74 Ukuran 20 x 40 M2
Batu Andesit Alur Motif
75 Ukuran 10 x 20 M2
76 Ukuran 15 x 30 M2
77 Ukuran 20 x 40 M2
Batu Andesit Bakar Polos tebal 1.2 - 1.3 cm
78 Ukuran 10 x 20 M2
79 Ukuran 10 x 30 M2
80 Ukuran 15 x 30 M2
81 Ukuran 15 x 15 M2
Halaman 16
NO. JENIS BAHAN SATUAN HARGA (Rp.) KETERANGAN
1 2 3 4 5
82 Ukuran 20 x 30 M2
83 Ukuran 20 x 20 M2
84 Ukuran 20 x 40 M2
85 Ukuran 30 x 30 M2
86 Ukuran 30 x 60 M2
87 Ukuran 40 x 40 M2
Batu Andesit Bakar Bintik
88 Ukuran 10 x 20 M2
89 Ukuran 10 x 30 M2
90 Ukuran 15 x 30 M2
91 Ukuran 15 x 15 M2
92 Ukuran 30 x 30 M2
Batu Andesit Bakar tebal. 5 cm
93 Ukuran 10 x 10 M2
94 Ukuran 15 x 15 M2
95 Ukuran 15 x 30 M2
96 Ukuran 20 x 20 M2
97 Ukuran 20 x 40 M2
98 Ukuran 30 x 30 M2
Batu Andesit Bakar tebal. 3 cm
99 Ukuran 10 x 10 M2
100 Ukuran 15 x 15 M2
101 Ukuran 15 x 30 M2
102 Ukuran 20 x 20 M2
103 Ukuran 30 x 30 M2
Batu Templek
104 Acak Purwakarta M2
105 Ukuran 10 x 20 M2
106 Ukuran 10 x 30 M2
107 Ukuran 15 x 30 M2
108 Ukuran 20 x 40 M2
109 Ukuran 30 x 30 M2
Batu Bobos Palimanan Corak/Palem
110 Ukuran 10 x 20 M2
111 Ukuran 20 x 20 M2
112 Ukuran 20 x 30 M2
113 Ukuran 20 x 40 M2
114 Ukuran 15 x 30 M2
Batu Bobos Palimanan Putih (RTM)
115 Ukuran 10 x 20 M2
116 Ukuran 15 x 30 M2
Batu Andesit Susun Sirih
117 Ukuran 3 x 20 M2
118 Ukuran 3 x 30 M2
119 Ukuran 3 x 40 M2
120 Ukuran 3 x 50 M2
121 Ukuran 5 x 30 M2
122 Ukuran 5 x 40 M2
Batu Alam Profil
123 Ukuran 5 x 30 M2
124 Ukuran 3 x 50 M2
125 Ukuran 4 x 50 M2
126 Ukuran 5 x 50 M2
127 Ukuran 3 x 40 M2
128 Ukuran 4 x 40 M2
129 Ukuran 5 x 40 M2
Batu Candi Muntilan
130 Ukuran 10 x 20 M2
Halaman 17
NO. JENIS BAHAN SATUAN HARGA (Rp.) KETERANGAN
1 2 3 4 5
131 Ukuran 15 x 30 M2
132 Ukuran 20 x 40 M2
Koral
133 Koral Pancawarna M2
134 Koral bengkulu hitam M2
135 Koral Flores hijau M2
136 Koral Orange Bali M2
137 Koral Hitam Garut M2
138 Batu Sikat M2
Basaltu Bandung
139 Ukuran 10 x 20 M2
140 Ukuran 10 x 30 M2
141 Ukuran 15 x 30 M2
142 Ukuran 20 x 40 M2
143 Ukuran 30 x 60 M2
Batu Curi Subang
144 Ukuran 10 x 20 M2
145 Ukuran 10 x 30 M2
146 Ukuran 15 x 30 M2
147 Ukuran 20 x 40 M2
148 Ukuran 30 x 30 M2
149 Ukuran 30 x 60 M2
Batu Bilik Gelombang
150 Ukuran 15 x 30 M2
Prasasti
151 Marmer Uk. 30 x 60 cm M2
152 Marmer Uk. 60 x 90 cm M2
153 Granite Hitam Uk. 30 x 60 cm M2
154 Granite Hitam Uk. 60 x 90 cm M2
G BAHAN KACA
1 Kaca polos 3 mm M2
2 Kaca polos 5 mm M2
3 Kaca polos 8 mm M2
4 Kaca polos 10 mm M2
5 Kaca polos 12 mm M2
6 Kaca rayband 3 mm M2
7 Kaca rayband 5 mm M2
8 Kaca Tempered 8 mm M2
9 Kaca Tempered 10 mm M2
10 Kaca Tempered 12 mm M2
11 Kaca Patri M2
12 Kaca Es t. 5 mm M2
13 Kaca Es random t. 5 mm M2
14 Kaca Pasta M2
15 Kaca Grafir t. 8 mm M2
16 Kaca Grafir corak t. 5 mm M2
17 Glass Block 20 x 20 cm Bh
18 Jendela naco + Rangka Daun
19 Pintu besi M2
20 Jendela besi / tralis M2
21 Sekrup Kg
22 Sealant Besar Tube
23 Sealant Kecil Tube
24 Cermin t. 5 mm M2
25 Kaca One way t. 5 mm M2
26 Kaca Bevel t. 3 cm M'
27 Kaca Bevel t. 2 cm M'
Halaman 18
NO. JENIS BAHAN SATUAN HARGA (Rp.) KETERANGAN
1 2 3 4 5
28 Sandblast Kaca M2
Halaman 19
NO. JENIS BAHAN SATUAN HARGA (Rp.) KETERANGAN
1 2 3 4 5
11 Bottom straightrap Psg
12 Top straighinge Psg
13 Kait angin Bh
14 Kunci Slot (grendel Pintu dan Jendela) Bh
15 Slot jendela Bh
16 Slot pintu 3" Bh
17 Slot pintu 4" Bh
18 Door holder Bh
19 Door Closer Bh
20 Expanolete Ps
Halaman 20
NO. JENIS BAHAN SATUAN HARGA (Rp.) KETERANGAN
1 2 3 4 5
30 Lampu LED 10 watt (setara Phillip) Bh
31 Lampu LED 13 watt (setara Phillip) Bh
32 TL. 1 x 40 W Phillip Bh
33 TL. 2 x 40 W Phillip Bh
34 TL. 1 x 20 W Phillip Bh
35 TL. 2 x 20 W Phillip Bh
36 TL. 2 x 20 W RM Bh
37 TL. 2 x 40 W RM Bh
38 Lampu Taman Bh
39 Armatur Lampu Baret Bh
40 Dudukan Downlight Stainlesstell 4" Bh
41 Kabel NYY 3 x 4 mm setara Supreme M'
42 Kabel NYY 4 x 6 mm setara Supreme M'
43 Kabel NYY 3 x 2,5 mm setara Supreme M'
44 Kabel NYY 3 x 1,5 mm setara Supreme M'
45 Kabel NYY 2 x 2,5 mm setara Supreme M'
46 Kabel NYY 2 x 1,5 mm setara Supreme M'
47 Kawat BC 25 mm M'
48 Kawat BC 16 mm M'
49 Kawat BC 6 mm M'
50 Kap Gembreng Bh
51 Down Light 8" Bh
52 Down Light 6" Bh
53 Down Light 4" Bh
54 Down Light 3" Bh
55 Down Light Outbow bulat 3" Bh
56 Down Light Outbow bulat 3,5" Bh
57 Down Light Outbow bulat 4" Bh
58 Down Light Outbow bulat 5" Bh
59 Down Light Outbow kotak 4" Bh
60 Fitting Plafond kotak Bh
61 Photocell 6 A Bh
62 MCB 1 phase 6 A Bh
63 Box MCB Uk. 40 x 50 cm + Dudukan Bh
64 Besi Arde (crum tembaga /2,40 m) Btg
65 Besi Arde (crum tembaga / 2 m) Btg
66 Besi Arde (crum tembaga / 1,5 m) Btg
L ALAT BANTU
1 Cangkul atau sekop Bh
2 Parang Bh
3 Pikulan dan 2 Bakul Bh
4 Palu / Godam Pemecah Batu Bh
5 Stamper 250 Kg Hari
Halaman 21
ANALISIS HARGA SATUAN PEKERJAAN (AHSP)
BANGUNAN GEDUNG DAN PERUMAHAN
TAHUN ANGGARAN 2022
(KONTRAKTUAL)
LANTAI - 1 (DASAR)
JUMLAH
OVERHEAD & PROFIT (15 %)
HARGA SATUAN PEKERJAAN
A.5 DIBULATKAN
B PEKERJAAN TANAH
B.1 1 M3 GALIAN TANAH BIASA SEDALAM 1 METER
UPAH
Pekerja 0.7500 Org
Mandor 0.0250 Org
ALAT
JUMLAH
OVERHEAD & PROFIT (15 %)
HARGA SATUAN PEKERJAAN
B.1 DIBULATKAN
JUMLAH
OVERHEAD & PROFIT (15 %)
HARGA SATUAN PEKERJAAN
B.11 DIBULATKAN
JUMLAH
OVERHEAD & PROFIT (15 %)
HARGA SATUAN PEKERJAAN
B.12 DIBULATKAN
Halaman 22
1 2 3 4 5 6 = (3 x 5) 7 = (3 x 5) 8 = (3 x 5) 9 = (6+7+8)
JUMLAH
OVERHEAD & PROFIT (15 %)
HARGA SATUAN PEKERJAAN
D.3 DIBULATKAN
JUMLAH
OVERHEAD & PROFIT (15 %)
HARGA SATUAN PEKERJAAN
D.6 DIBULATKAN
E PEKERJAAN PLESTERAN
E.3 1 M2 PLESTERAN, 1Pc : 5PP, TEBAL 20 mm
BAHAN
Semen Portland 6.9120 Kg
Pasir Pasang 0.0350 M3
UPAH
Pekerja 0.4000 Org
Tukang Batu 0.2000 Org
Kepala Tukang 0.0200 Org
Mandor 0.0220 Org
ALAT
JUMLAH
OVERHEAD & PROFIT (15 %)
HARGA SATUAN PEKERJAAN
E.3 DIBULATKAN
E.6 1 M2 ACIAN
BAHAN
Semen Portland 3.2500 Kg
UPAH
Pekerja 0.2000 Org
Tukang Batu 0.1000 Org
Kepala Tukang 0.0100 Org
Mandor 0.0100 Org
ALAT
JUMLAH
OVERHEAD & PROFIT (15 %)
HARGA SATUAN PEKERJAAN
E.6 DIBULATKAN
Halaman 23
1 2 3 4 5 6 = (3 x 5) 7 = (3 x 5) 8 = (3 x 5) 9 = (6+7+8)
Kayu Kruing, Balok 1.1000 M3
Paku 10 cm 1.2500 Kg
Lem Kayu 1.0000 Kg
UPAH
Pekerja 7.0000 Org
Tukang Kayu 21.0000 Org
Kepala Tukang 2.1000 Org
Mandor 0.3500 Org
ALAT
JUMLAH
OVERHEAD & PROFIT (15 %)
HARGA SATUAN PEKERJAAN
F.3 DIBULATKAN
JUMLAH
OVERHEAD & PROFIT (15 %)
HARGA SATUAN PEKERJAAN
F.8 DIBULATKAN
JUMLAH
OVERHEAD & PROFIT (15 %)
HARGA SATUAN PEKERJAAN
F.11 DIBULATKAN
JUMLAH
OVERHEAD & PROFIT (15 %)
HARGA SATUAN PEKERJAAN
F.14 DIBULATKAN
Halaman 24
1 2 3 4 5 6 = (3 x 5) 7 = (3 x 5) 8 = (3 x 5) 9 = (6+7+8)
Kepala Tukang 0.2000 Org
Mandor 0.3350 Org
ALAT
JUMLAH
OVERHEAD & PROFIT (15 %)
HARGA SATUAN PEKERJAAN
F.16 DIBULATKAN
G PEKERJAAN BETON
G.2 1 M3 COR BETON SITE MIX K. 175
BAHAN
Semen Portland 340.0000 Kg
Split pecah mesin 2/3 0.8300 M3
Pasir Beton 0.5400 M3
UPAH
Pekerja 1.5000 Org
Tukang Batu 0.5000 Org
Kepala Tukang 0.0500 Org
Mandor 0.0100 Org
ALAT
Peralatan 0.0750 Lot
JUMLAH
OVERHEAD & PROFIT (15 %)
HARGA SATUAN PEKERJAAN
G.2 DIBULATKAN
JUMLAH
OVERHEAD & PROFIT (15 %)
HARGA SATUAN PEKERJAAN
G.23 DIBULATKAN
JUMLAH
OVERHEAD & PROFIT (15 %)
HARGA SATUAN PEKERJAAN
G.25 DIBULATKAN
H PEKERJAAN ATAP
Halaman 25
1 2 3 4 5 6 = (3 x 5) 7 = (3 x 5) 8 = (3 x 5) 9 = (6+7+8)
Pekerja 0.1000 Org
Tukang Kayu 0.2000 Org
Kepala Tukang 0.0200 Org
Mandor 0.0050 Org
ALAT
JUMLAH
OVERHEAD & PROFIT (15 %)
HARGA SATUAN PEKERJAAN
H.64 DIBULATKAN
JUMLAH
OVERHEAD & PROFIT (15 %)
HARGA SATUAN PEKERJAAN
H.30.rob DIBULATKAN
H.54.rob 1 M' PASANG NOK GENTENG METAL TIDAK BERPASIR
BAHAN
Nok Metal tidak Berpasir 1.1000 M'
Paku Biasa 1/2" - 1" 0.0500 Kg
UPAH
Pekerja 0.2500 Org
Tukang Kayu 0.1500 Org
Kepala Tukang 0.0150 Org
Mandor 0.0130 Org
ALAT
JUMLAH
OVERHEAD & PROFIT (15 %)
HARGA SATUAN PEKERJAAN
H.54.rob DIBULATKAN
I PEKERJAAN LANGIT-LANGIT
I.11 1 M2 LANGIT-LANGIT GRC, TANPA RANGKA
BAHAN
Plafond GRC 0.3472 Lbr
Paku Sekrup 0.1100 Kg
Cotton Plaster 0.0720 Bh
Compoun 0.1250 Zak
UPAH
Pekerja 0.1000 Org
Tukang Kayu 0.0500 Org
Kepala Tukang 0.0050 Org
Mandor 0.0050 Org
ALAT
JUMLAH
OVERHEAD & PROFIT (15 %)
HARGA SATUAN PEKERJAAN
I.11 DIBULATKAN
Halaman 26
1 2 3 4 5 6 = (3 x 5) 7 = (3 x 5) 8 = (3 x 5) 9 = (6+7+8)
ALAT
JUMLAH
OVERHEAD & PROFIT (15 %)
HARGA SATUAN PEKERJAAN
I.23 DIBULATKAN
JUMLAH
OVERHEAD & PROFIT (15 %)
HARGA SATUAN PEKERJAAN
L.1 DIBULATKAN
JUMLAH
OVERHEAD & PROFIT (15 %)
HARGA SATUAN PEKERJAAN
L.5 DIBULATKAN
JUMLAH
OVERHEAD & PROFIT (15 %)
HARGA SATUAN PEKERJAAN
L.6 DIBULATKAN
JUMLAH
OVERHEAD & PROFIT (15 %)
HARGA SATUAN PEKERJAAN
L.8 DIBULATKAN
Halaman 27
1 2 3 4 5 6 = (3 x 5) 7 = (3 x 5) 8 = (3 x 5) 9 = (6+7+8)
Keramik Putih 40 x 40 cm 1.1870 M2
Semen Portland 10.0000 Kg
Pasir Pasang 0.0450 M3
Semen Warna 0.5000 Kg
UPAH
Pekerja 0.7000 Org
Tukang Batu 0.3500 Org
Kepala Tukang 0.0350 Org
Mandor 0.0350 Org
ALAT
JUMLAH
OVERHEAD & PROFIT (15 %)
HARGA SATUAN PEKERJAAN
M.7 DIBULATKAN
P PEKERJAAN PENGECATAN
P.1 1 M2 MENGIKIS / MENGEROK PERMUKAAN CAT DINDING LAMA
BAHAN
Soda Api 0.0500 Kg
UPAH
Pekerja 0.1500 Org
Mandor 0.0030 Org
ALAT
JUMLAH
OVERHEAD & PROFIT (15 %)
HARGA SATUAN PEKERJAAN
P.1 DIBULATKAN
P.4 1 M2 PENGECATAN BID. KAYU BARU (1 LAPIS PLAMIR), 1 LAPIS CAT DASAR, 2 LAPIS CAT PENUTUP
BAHAN
Cat Meni 0.2000 Kg
Plamir 0.1500 Kg
Cat Dasar 0.1700 Kg
Cat Penutup 2 x 0.2600 Kg
Ampelas 0.0200 Lbr
Minyak Cat 0.0300 Ltr
Kuas 0.0100 Bh
UPAH
Pekerja 0.0700 Org
Tukang Cat 0.0090 Org
Kepala Tukang 0.0060 Org
Mandor 0.0030 Org
ALAT
JUMLAH
OVERHEAD & PROFIT (15 %)
HARGA SATUAN PEKERJAAN
P.4 DIBULATKAN
P.12 1 M2 PENGECATAN TEMBOK BARU 1 LAPIS PLAMIR, 1 LAPIS CAT DASAR, 2 LAPIS CAT PENUTUP
BAHAN
Plamir 0.1000 Kg
Cat Dasar 0.1000 Kg
Cat Penutup 2x 0.2600 Kg
Roll Cat 0.0100 Bh
Ampelas 0.5000 Lbr
UPAH
Pekerja 0.0200 Org
Tukang Cat 0.0630 Org
Kepala Tukang 0.0063 Org
Mandor 0.0030 Org
ALAT
JUMLAH
OVERHEAD & PROFIT (15 %)
HARGA SATUAN PEKERJAAN
P.12 DIBULATKAN
P.14 1 M2 PENGECATAN TEMBOK LAMA 1 LAPIS CAT DASAR, 2 LAPIS CAT PENUTUP
Halaman 28
1 2 3 4 5 6 = (3 x 5) 7 = (3 x 5) 8 = (3 x 5) 9 = (6+7+8)
BAHAN
Cat Dasar 0.1200 Kg
Cat Penutup 2x 0.1800 Kg
Roll Cat 0.0100 Bh
Ampelas 0.5000 Lbr
UPAH
Pekerja 0.0280 Org
Tukang Cat 0.0420 Org
Kepala Tukang 0.0042 Org
Mandor 0.0030 Org
ALAT
JUMLAH
OVERHEAD & PROFIT (15 %)
HARGA SATUAN PEKERJAAN
P.14 DIBULATKAN
JUMLAH
OVERHEAD & PROFIT (15 %)
HARGA SATUAN PEKERJAAN
P.16 DIBULATKAN
Halaman 29
DAFTAR HARGA SATUAN PEKERJAAN
TAHUN ANGGARAN 2022
(KONTRAKTUAL)
A PEKERJAAN PERSIAPAN A
1 1 M2 PEMBUATAN PAPAN NAMA PROYEK DIGITAL PRINTING A.5
B PEKERJAAN TANAH B
1 1 M3 GALIAN TANAH BIASA SEDALAM 1 METER B.1
2 1 M3 URUGAN TANAH LOKAL B.11
3 1 M3 URUGAN PASIR B.12
E PEKERJAAN PLESTERAN E
1 1 M2 PLESTERAN, 1Pc : 5PP, TEBAL 20 mm E.3
2 1 M2 ACIAN E.6
G PEKERJAAN BETON G
1 1 M3 COR BETON SITE MIX K. 175 G.2
2 1 M2 PASANG BEKISTING PAPAN G.23
3 1 KG PEMBESIAN DENGAN BESI ULIR G.25
H PEKERJAAN ATAP H
1 1 M' PASANG LISTPLANK GRC TUMPANGSARI (1/20 +1/10) CM H.64
2 1 M2 PASANG ATAP GENTENG METAL TIDAK BERPASIR H.30.rob
3 1 M' PASANG NOK GENTENG METAL TIDAK BERPASIR H.54.rob
I PEKERJAAN LANGIT-LANGIT I
1 1 M2 LANGIT-LANGIT GRC, TANPA RANGKA I.11
2 1 M2 PASANG RANGKA HOLLOW GALVALUME untuk PLAFON, MODUL 60x60 CM I.23
P PEKERJAAN PENGECATAN P
1 1 M2 MENGIKIS / MENGEROK PERMUKAAN CAT DINDING LAMA P.1
2 1 M2 PENGECATAN BID. KAYU BARU (1 LAPIS PLAMIR), 1 LAPIS CAT DASAR, 2 LAPIS CAT PENUTUPP.4
3 1 M2 PENGECATAN TEMBOK BARU 1 LAPIS PLAMIR, 1 LAPIS CAT DASAR, 2 LAPIS CAT PENUTUP P.12
4 1 M2 PENGECATAN TEMBOK LAMA 1 LAPIS CAT DASAR, 2 LAPIS CAT PENUTUP P.14
5 1 M2 PENGECATAN PLAFOND 1 LAPIS CAT DASAR, 2 LAPIS CAT PENUTUP P.16
Halaman 30
KODE HARGA SATUAN (Rp.) JUMLAH
No URAIAN PEKERJAAN
ANALISA UPAH BAHAN ALAT (Rp.)
1 2 3 4 5 6 7 = (4+5+6)
Halaman 31