KET :
- RUAS JALAN TOL CISUMDAWU
TOTAL PANJANG : 34,094 Km
TARGET SELESAI : April 2022
- AKSES TOL BANDARA KERTAJATI
TOTAL PANJANG : 3,382 Km
TARGET SELESAI : Oktober 2021
RUAS JALAN TOL CISUMDAWU PT. CITRA KARYA JABAR TOL (CKJT)
Panjang total 34,094 km
Kecepatan
60-80 km/jam
rencana
Lebar lajur 4,0 m
PROGRES TANAH
PANJANG PROGRES KONSTRUKSI
BEBAS TARGET PENYELESAIAN
(km)
(%) RENCANA REALISASI DEVIASI
8,20 91,414 70,233 14,633 -55,60 Nopember 2022
PEKERJAAN YANG SEDANG CISUMDAWU – SEKSI 4
1
DILAKSANAKAN (PT. WIJAYA KARYA)
- Timbunan
- Blasting
- Drainase
- Underpass box
- Bore pile abutment
2 RUAS JALAN TOL CISUMDAWU SEKSI 5A PT. CITRA KARYA JABAR TOL (CKJT)
Panjang total 7,45 km
PROGRES TANAH
PANJANG PROGRES KONSTRUKSI
BEBAS TARGET PENYELESAIAN
(km)
(%) RENCANA REALISASI DEVIASI
7,450 91,096 94,22 24,43 -69,79 Juni 2022
PEKERJAAN YANG SEDANG CISUMDAWU – SEKSI 5A
2
DILAKSANAKAN (PT. ADHI KARYA)
- Timbunan
- Underpass bridge
- Bore pile underpass bridge
3 RUAS JALAN TOL CISUMDAWU SEKSI 5B PT. CITRA KARYA JABAR TOL (CKJT)
Panjang total 7,45 km
PROGRES TANAH
PANJANG PROGRES KONSTRUKSI
BEBAS TARGET PENYELESAIAN
(km)
(%) RENCANA REALISASI DEVIASI
7,450 72,680 37,752 39,613 +1,635 Juni 2022
PEKERJAAN YANG SEDANG CISUMDAWU – SEKSI 5B
3
DILAKSANAKAN (PT. GIRDER INDONESIA)
- Pemadatan
- Box underpass
4 RUAS JALAN TOL CISUMDAWU SEKSI 6A PT. CITRA KARYA JABAR TOL (CKJT)
Panjang total 3,033 km
PROGRES TANAH
PANJANG PROGRES KONSTRUKSI
BEBAS TARGET PENYELESAIAN
(km)
(%) RENCANA REALISASI DEVIASI
3,033 98,18 83,254 76,275 -6,970 Februari 2022
PEKERJAAN YANG SEDANG CISUMDAWU – SEKSI 6A
4
DILAKSANAKAN (PT. GIRDER INDONESIA)
- - Pemadatan
- Box underpass
- Rigid Pavement
5 RUAS JALAN TOL CISUMDAWU SEKSI 6B PT. CITRA KARYA JABAR TOL (CKJT)
Panjang total 3,032 km
PROGRES TANAH
PANJANG PROGRES KONSTRUKSI
BEBAS TARGET PENYELESAIAN
(km)
(%) RENCANA REALISASI DEVIASI
3,032 100 91,765 89,289 -2,476 Januari 2022
PEKERJAAN YANG SEDANG CISUMDAWU – SEKSI 6B
5
DILAKSANAKAN (PT. BRANTAS ABIPRAYA)
- - Drainage
- parapet
- Rigid Pavement
6 RUAS JALAN TOL CISUMDAWU SEKSI 6B PT. CITRA KARYA JABAR TOL (CKJT)
Panjang total 4,929 km
PROGRES TANAH
PANJANG PROGRES KONSTRUKSI
BEBAS TARGET PENYELESAIAN
(km)
(%) RENCANA REALISASI DEVIASI
4,929 100 90,149 74,678 -15,471 Februari 2022
PEKERJAAN YANG SEDANG CISUMDAWU – DAWUAN JUNCTION
6
DILAKSANAKAN (PT. PEMBANGUNAN PERUMAHAN)
- - Drainage
- Erection girde
- Underpassr
- Perkerasan
- Rigid Pavement