1. IRIGASI SALURAN KE PERSAWAHAN 190,211,800.00 190,174,100.00 37,700.00
PANCANEGARA 2. PAVING BLOK KE PESANTREN 45,460,480.00 38,522,800.00 6,937,680.00 1. SPAL KP. CIWATU 85,854,100.00 SINDANGHEULA 235,290,250.00 77,764,150.00 2. RABAT BETON KE ARAH PEMAKAMAN 71,672,000.00 1. TPT PERSAWAHAN (CIKAUNG TIMUR) 189,000,000.00 On Progres PABUARAN 2. RABAT BETON READY MIX KP. CIKAMPENG 197,382,000.00 135,135,000.00 62,247,000.00 1. RABAT BETON READY MIX KP. SABELAH 243,222,560.00 235,358,800.00 7,863,760.00 SINDANGSARI 2. TPT 240,326,000.00 85,742,700.00 154,583,300.00 1. SITEMIX KP. PARIGI On Progres 2. PENGEBORAN TANJUNG SARI 203,675,000.00 On Progres 3. DRAINASE CISITU On Progres 1. JALAN PAVING belum ada On Progres 2. JALAN BETON TALAGA WARNA belum ada On Progres 3. SALURAN JALAN belum ada On Progres 1. PAVING KADUBEREUM 268,750,000.00 268,638,200.00 111,800.00 1. PASANGAN BATU belum ada On Progres SUKADANA 2. JALAN BETON SITEMIX belum ada On Progres - -