Anda di halaman 1dari 6

KASBON KE MATRIAL

NO Tanggal NAMA BARANG SATUAN HARGA QTY JUMLAH


1 1/25/2023 Pasir Truk 1850000 1 1850000
2 Semen Sak 71000 50 3550000
3 Wiremesh lembar 630000 5 3150000
4 Bondek 8 m Lembar 1200000 4 4800000
5 Bondek 6 M Lembar 900000 4 3600000
6 Besi 8 sni Batang 51000 20 1020000
7 Besi 10 SNI Batang 78000 10 780000
8 1/27/2023 Pasir L300 500000 1 500000
9 Split Kijang 390000 1 390000
10 1/28/2023 Bondek 6 M Lembar 900000 3 2700000
11 weermes 8 Lembar 630000 2 1260000
12 Besi 6 Batang 35000 1 35000
13 Semen Sak 71000 10 710000
14 Cor Semen Botol 25000 5 125000
15 Pasir L30 500000 1 500000
16 Split kijang 380000 1 380000
17 1/29/2023 Kayu Balok 5X10 Batang 65000 1 65000
18 1/30/2023 Bambu Batang 18500 20 370000
19 2/2/2023 Triplek Lembar 95000 6 570000
20 Kaso Ikat 85000 3 255000
21 2/11/2023 Pasir Truk 1960000 1 1960000
22 2/12/2023 Split L300 550000 1 550000
23 Split Sarongge colt 320000 1 320000
24 Paku 7 Kg 20000 3 60000
25 Bambu Batang 18000 20 360000
26 Balok Batang 65000 4 260000
TOTAL 30120000
wiremesh 2 630000 1260000 Alderon 18 X 150000 2700000
Bondek 3 900000 2700000
pasir 1 1850000 1850000
split 1 500000 500000
semen 20 72000 1440000
Matrial 7750000
Total 5050000
Rencana Naik Atas Rencana Naik Atas

NO NAMA BARANGSATUAN HARGA QTY JUMLAH NO NAMA BARANG


1 Pasir Truk 1850000 1 1850000 1 Pasir
2 Semen Sak 71000 20 1420000 2 Semen
3 tiang Batang 75000 16 1200000 3 toren
4 Alderon Meter 70000 75 5250000 4 Alderon
5 helbel kibik 580000 5 2900000 5 helbel
besi batang 78000 16 1248000 kusen
6 gipsum Lembar 75000 25 1875000 6 gipsum
keramik dus 125000 51 6375000 keramik
cat pel 1040000 4 4160000 cat
26278000

TOTAL 52556000
Rencana Naik Atas

SATUAN HARGA QTY JUMLAH


Truk 1850000 1 1850000
Sak 71000 20 1420000
800000 1 800000
Meter 70000 16 1120000
kibik 580000 2 1160000
3200000 1 3200000
Lembar 75000 25 1875000
dus 125000 51 6375000
pel 1040000 4 4160000
21960000
KASBON KE MATRIAL

NO Tanggal NAMA BARANG SATUAN HARGA QTY JUMLAH Pekerja


1 1/25/2023 Pasir Truk 1850000 2 3700000 5
2 Semen Sak 60000 50 3000000
3 Bata herbel Kibik 630000 13 8190000
4 sumur bor 6000000 1 6000000
6 Besi 8 sni Batang 100000 70 7000000
8 1/27/2023 Pasir L300 500000 2 1000000
9 Kusen 5000000 1 5000000
19 2/2/2023 Triplek Lembar 95000 15 1425000
24 Paku 7 Kg 20000 20 400000
TOTAL 35715000 69000000

Total Pengeluaran
Matrial Pekerja Total
35715000 65450000 101165000
Perhari Jumlah Bnayaknya Hari Total
170000 850000 77 65450000

33285000 32165000

Anda mungkin juga menyukai