Anda di halaman 1dari 12

METHODE KERJA PONDASI BORED PILE

A. DATA TEKNIS : C. SQUENCE OF WORKS :


A. PEKERJAAN PERSIAPAN
1. NAMA PROYEK :
1. UKUR DAN TENTUKAN POSISI TITIK – TITIK BORE PILE DI SITE
2. JUMLAH TITIK PONDASI :
2. BUAT PABRIKASI KERANJANG BESI BORE PILE
3. DIAMETER BORED PILE :
3. BUAT SHEDULE PENGECORAN BORED PILE DAN TERUS
4. KEDALAMAN BORE PILE :
DIKENDALIKAN
5. MUTU BETON :
4. BUAT FORMAT UNTUK MONITORING REPORT BORE PILE
6. MUTU BESI UNTUK SPIRAL :
7. MUTU BESI UNTUK TULANGAN POKOK :
B. PEKERJAAN BORED PILE
8. VOLUME BETON PEK. TTK BORED PILE :
1. SET ALAT PADA POSISI TITIK YANG AKAN DI BOR
9. BERAT KERANJANG :
2. BILA KONDISI LAPISAN TANAH BAIK
- BOR SAMPAI KEDALAMAN 6 m SAJA
DAN PASANG CASING 6 m
B. PERALATAN YANG DIGUNAKAN :

1. SERVICE CRANE
2. KELLY
3. AUGER MACHINE
4. DIESEL GENSET
5. PIPE CASING DIA. 0.8 M, LENGTH = 16 M
6. CLEANING BUCKET
7. PIPE TREMIE
8. THEODLITE
9. READY MIX (TRUCK MIXER)
10. TREMIE PIPE CONE

3. BILA KONDISI LAPISAN TANAH JELEK


- GUNAKAN FULL CASING UNTUK
MENCEGAH KELONGSORAN TANAH
PADA SAAT PROSES BORING
- MASUKKAN FULL CASING KEDALAM
LUBANG BOR SEBELUM PROSES
PENGEBORAN DIMULAI DENGAN ALAT
BANTU VIBRO HAMMER

GENSET

5–6M
TEMPORARY FULL CASING
METHODE KERJA PONDASI BORED PILE

4. KEMUDIAN DILANJUTKAN DENGAN PROSES PENGEBORAN SAMPAI 6. BERSIHKAN LUMPUR PADA DASAR LUBANG BOR DENGAN
KEDALAMAN YANG DIKEHENDAKI BUCKET CLEANING
5. CHECK APAKAH KEDALAMAN YANG DIKEHENDAKI SUDAH TERCAPAI 7. SELAMA PROSES BERLANGSUNG, CATAT :
- KEDALAMAN MUKA AIR TANAH
- JENIS LAPISAN TANAH BERIKUT DEDALAMAN DAN KETEBALAN
DARI LAPISAN TANAH
8. BUAT LAPORAN HARIAN BORE PILE

TEMPORARY
CASING 6 M TEMPORARY FULL CASING
ELEV. – 6.00 ELEV. – 6.00 (BILA DIPERLUKAN)

CLEANING BUCKET
METHODE KERJA PONDASI BORED PILE

D. CONCRETE WORK

1. PESAN BETON K - 400., SLUMP 18 +/- 2 CM, KE BATCHING 3. PASANG PIPA TREMI BILA TERDAPAT MUKA AIR TANAH DALAM LUBANG BOR
PLAN 4. JIKA TIDAK ADA AIR TANAH PENGGUNAAN PIPATREMIC TIDAK MUTLAK
2. PASANG KERANJANG BESI DIPERLUKAN (CUKUP PAKAI CORONG)

PIPA TREMI

ELEV. – 6.00 KERANJANG PEMBESIAN KERANJANG PEMBESIAN

TEMPORARY FULL TEMPORARY FULL


CASING DIA. 80 cm L=16 M CASING DIA. 80 cm L=16 M
METHODE KERJA PONDASI BORED PILE

5. PROSES PENGECORAN PONDASI BORE PILE 6. SEGERA SETELAH PENGECORAN SLESAI, TARIKTEMPORARY CASING
SELAMA PROSES BERLANGSUNG, CHECK ADAKAH VOLUME DARI LUBANG BOR
TEORITIC PER LUBANG SUDAH SESUAI DENGAN VOLUME 7. PEKERJAAN BOR SELESAI
BETON YANG DIKIRIM / DICOR KEDALAM LUBANG

EXISTING

TEMPORARY FULL CASING


PIPA TREMI

KERANJANG BESI

TEMPORARY FULL
CASING
DASAR
METHODE OF BORED PILE FOUNDATION

8. BILA BATAS PENGECORAN AKHIR PONDASI BORE PILE TERLETAK


DIKEDALAMAN TERTENTU DARI MUKA TANAH STRUKTUR PONDASI BORED PILE
- ISI VOLUME LUBANG TERSEBUT DENGAN PASIR A. METHODE URUTAN BORED PILE AND COR
DENGAN DASAR PERTIMBANGAN K 3

SAND FILLING

OVER POUR WILL 1.25 M


BE CUT OFF

BORE PILE 13 M
DIA. 80cm
FLOW CHART METHOD OF BORED PILE WORK
METHODE PEKERJAAN BORED PILE

START

UITZET
A. SEBELUM PENGEBORAN DIBUAT
TEST-PIT TERLEBIH DAHULU DAN
SEGALA SESUATU
STEL BESI BONGKAR ASPAL/
PEKERJAAN SURVEY (RANJANG) RIGID. PAV
SETTING ALAT

B. PENGEBORAN DIBUAT DALAM 2


(DUA) TAHAPAN YANG BERBEDA GALIAN
YAITU : 1.50 – 2.00 M
- ZONE A
- ZONE B
PENGEBORAN
MENGGUNAKAN 1 (SATU) UNIT ALAT
BOR DAN 1 (SATU) UNIT SERVICE
CASSING + VERTICALITY
CRANE + MASUK BESI RANJANG

C. PEMBUATAN (RANJANG) PEMBESIAN


DISESUAIKAN LOKASI STOCK PILE COR

D. CAPASITAS PRODUKSI KURANG LEBIH


2 – 3 TITIK/HARI TUTUP KEMBALI
BEKAS LUBANG

FINISH
METHODE PEKERJAAN BENTONITE

A. DATA TEKNIS SEBAGAI BERIKUT :


- DIA. 60 cm
- L = 11 – 18 m
- 1 m3 = 60 kg SEMUA BENTONITE +
300 kg SEMEN

B. PENENTUAN TITIK BOR

C. PENGEBORAN SESUAIKAN PEIL


KEDALAMAN YANG DITENTUKAN

D. COR YAITU :
- TUANGKAN SEMUA SEMEN
BENTONITE (SESUAI MIX
DESIGN) KEDALAM BUCKET COR /
CONCRETE PUMP KEMUDIAN
LUAPANNYA DIALIRKAN KE TANK
BENTONITE
- SETELAH SEMEN BENTONITE
MASUKKAN KEDALAM LUBANG
SAMPAI MELUAP DAN FRESH
SEHINGGA DIDAPATKAN KAPASTIAN
BAHWA LUBANG TELAH FULL
SELANJUTNYA SEGERA PIPA TREMIE
DAN CASING DICABUT ARTINYA
BAHWA PEMBUATAN BENTONITE
PILE
TELAH SELESAI
METHODE PEKERJAAN JEMBATAN
( TOP DOWN )

A. BONGKAR ASPAL / RIGIT PAV DAN GALIAN TANAH


DAN PEMOTONGAN KEPALA BORED PILE

B. PENGUKURAN UNTUK MENENTUKAN PEIL DAN COR CAPPING BEAM


BUAT / PASANG BEKISTING YAITU TERDIRI : COR (PLAT JEMBATAN
- PEMADATAN TANAH
- PAS. LANTAI KERJA
- PAS. MULTIPLEX 12 mm
MULTIPLEX 12 mm
(BILA TIDAK TERGALI MAKA MENGGUNAKAN LT. KERJA
BEKISTING BATACO)
BORED PILE
C. STEL PEMBESIAN SESUAI GBR / BISTAT

D. PENGECORAN YAITU SETELAH PEMBERSIHAN


DAN PENENTUAN PEIL
METHODE PEMANCANGAN SHEET PILE

START

UITZET

A. PEMANCANGAN DIBUAT DALAM 2 TAHAP BERSAMAAN


YAITU SISI KIRI DAN KANAN (LIHAT GAMBAR)
DENGAN MENGGUNKAN 2 ALAT YAITU MASING-MASING KEDALAMAN BONGKAR ASPAL/
SETTING ALAT
SHEET PILE RIGID. PAV
1 UNIT DRIVE PILING DAN 1 UNIT SERVICE CRANE
PENGIRIMAN DARI WORK SHOP DISESUAIKAN
DENGAN HASIL PEMANCANGAN DILAPANGAN GALIAN
(KARENA STOCK PILE TERBATAS) 1.50 – 2.00 M

B. SEBELUM PANCANG LEBIH DAHULU DIBUAT


TEST-PIT DAN GUIDE BEAM SEPANJANG PASANG GUIDE BEAM
RETAINNING WALL SEBAGAI REFERENSI
(HARUS KOKOH / KUAT) UNTUK CEK
TERHADAP VERTIKAL / HORIZONTAL SHEET PILE UP

C. CAPASITAS PRODUKSI KURANG LEBIH 4 – 5 TITIK/HARI


DAN HARUS ADA DATA KALENDERING PEMANCANGAN

TUTUP KEMBALI
BEKAS LUBANG

FINISH
FLOW CHART PEKERJAAN
UNDERPASS CAWANG
START

PERSIAPAN

PELEBARAN JALAN KOORDINASI DENGAN INSTANSI TERKAIT


TRAFIC MANAGEMENT
PADA TROTOAR / PENEBANGAN / JARINGAN/PIPA/GAS/DLL
PEMINDAHAN POHON

GALIAN
TRAFIC MANAGEMENT
1.50 – 2.00 M

YA TIDAK
YA / TIDAK

PEKERJAAN BORED PILE PEKERJAAN SHEET PILE

CAPPING BEAM
PEIR / ABUTMENT JEMBATAN

SLAB & OPRIT JEMBATAN

FINISH
FLOW CHART PEKERJAAN
UNDERPASS TOMANG
START

PERSIAPAN

PELEBARAN JALAN KOORDINASI DENGAN INSTANSI TERKAIT


TRAFIC MANAGEMENT
PADA TROTOAR / PENEBANGAN / JARINGAN/PIPA/GAS/DLL
PEMINDAHAN POHON

GALIAN
TRAFIC MANAGEMENT
1.50 – 2.00 M

YA TIDAK
YA / TIDAK

PEKERJAAN BORED PILE PEKERJAAN SHEET PILE

CAPPING BEAM
PEIR / ABUTMENT JEMBATAN

SLAB & OPRIT JEMBATAN

FINISH

Anda mungkin juga menyukai