Ari D. Pasek 1
SIKLUS AIR
Ari D. Pasek 2
SOLAR ENERGY flux on the Earth surface:
Mini-hydro
100 kW
Micro-hydro
1 kW
Pico-hydro
Ari D. Pasek
TYPICAL MINI HYDRO POWER PLANT
(Mongango – Gorontalo)
h f
g i
k a. Weir & intake g. Cofferdam Upstream
b. Desand Basin h. River Diversion
a
b c. Canal i. Access Road
c
j d. Head Tank j. Cofferdam Downstream
e. Penstock k. Temporary Bridge
f. Power House dan Tail Race
Ari D. Pasek 5
ASPEK PEKERJAAN Aspek pekerjaan mencakup
PADA PLTA
Aspek Topografi
Aspek Hidrologi
Aspek Geoteknik
Ari D. Pasek 6
ASPEK TOPOGRAFI
Ari D. Pasek 7
A
Canal
H b = gross head (tinggi
angkat kotor) in metres
H b = gross head
L = losses in hydraulic structure in Pennstoc
k
metres
H = H b − L = net head (tinggi angkat bersih) Turbin
e B
Ari D. Pasek
ASPEK HIDROLOGI
Aspek hidrologi mencakup:
• Memprediksi debit sungai dan flow duration curve, debit perancangan, debit banjir sehingga dapat
ditentukan debit untuk daya maupun debit untuk merancangan bangunan hidrolika.
• Memprediksi sistem pembuatan cofferdam dan diversion river serta dimensinya.
• Memprediksi posisi bangunan intake yang paling sesuai untuk diterapkan, dengan mempertimbangkan :
• Elevasi muka air banjir (muka air maksimum), muka air rata-rata, muka air pada musin kemarau (muka air
minimum).
• Jumlah galian dan timbunan yang optimal
• Kemungkinan terjadi pendangkalan, pengikisan (erosi).
• Memprediksi design dan dimensi bangunan intake, termasuk sistem limpasan.
• Memprediksi sistem bangunan penyadapan secara keseluruhan yang paling sesuai untuk diterapkan,
dengan mempertimbangkan terhadap :
• Kandungan sedimen (karakteristik air sungai) terutama pada waktu musim hujan.
• Jarak antara lokasi bangunan intake dengan daerah erosi pada aliran sungai.
• Memprediksi design dan dimensi bangunan desand dan sistem pelimpasannya
• Memprediksi design dan dimensi canal/saluran pembawa
• Memprediksi design dan dimensi headtank/kolam penenang dan saluran limpasannya
• Memprediksi adanya natural drain dan dimensi side drain maupun cross drain yang diperlukan
• Memprediksi design dan dimensi tailrace
Ari D. Pasek 9
CATCHMENT AREA
Power plant
Gauging Station
Meteorology Station
funnel
•Mechanical/Battery
collector Clock
•Weekly recording
time
•One year chart paper
Common Precipitation Collector included
80
60
Flow (m3/d)
60 50
40
40 30
20
20
10
0 -
1
17
33
49
65
81
97
113
129
145
161
177
193
209
225
241
257
273
289
305
321
337
353
Day
Precipitation Daily flow
Ari D. Pasek 11
HYDROLOGY ANALYSIS
Rainfall Analyze
Gumbell Method (Hydrology Analyze )
Design Discharge
( Q2Year)
Q2Year
Ari D. Pasek 12
Example: Flood Flow Nakayasu Hydrograph
Onggak Mongondow River Flood Flow Hydrograph
600.00
Design Flood Flow
Q100 years = 510.45 m3/s
300.00
Design Flood Flow
Q5 yeras= 307.51 m3/s
100.00
0.00
0.0 2.0 4.0 6.0 8.0 10.0 11.2 13.0 15.0 16.9 18.0 20.0 22.0 24.0 26.0 28.0 30.0 32.0 34.0 36.0 38.0 40.0 42.0 44.0 46.0 48.0
Time (Hour)
Ari D. Pasek 13
Example: Flow duration curve generated by Thorn-White method
80.00
70.00
60.00
50.00
Discharge (m3/sec)
40.00
30.00
20.00
15,58 m3/det
13,21 m3/det
10.00
39,63 %
0.00
0.00 10.00 20.00 30.00 40.00 50.00 60.00 70.00 80.00 90.00 100.00
% of Occurence
Ari D. Pasek 14
ANNUAL ENERGY GENERATED
160
Design 140
Flow rate
120
Outflow
80
60
40
20 Turbine 1 + Turbine 2
Turbine 2
0
0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100%
Probability
Annual Energy generated = 9.8 x Hnet x Area x overall x 3600 x 365 x 24 Ari D. Pasek 15
River Rating Curve
River Rating Curve: is a relation between river/stream level/stage and
river/stream flow
H1
H2
Ari D. Pasek 16
Example: Calculation Result of Manning Method
H Actual 3
h (m) n s A P v (m/s) Q (m /s)
(m)
37.83 0.50 0.045 0.030 3.27 11.18 1.70 5.57
38.33 1.00 0.045 0.030 10.18 16.75 2.78 28.28
38.83 1.50 0.045 0.030 19.83 22.32 3.58 70.95
39.33 2.00 0.045 0.030 32.11 26.92 4.36 139.87
39.83 2.50 0.045 0.030 45.91 29.30 5.22 239.83
40.33 3.00 0.045 0.030 60.76 31.65 5.98 363.54
40.83 3.50 0.045 0.030 76.67 33.95 6.67 511.26
41.33 4.00 0.045 0.030 93.70 36.60 7.25 679.17
41.83 4.50 0.045 0.030 111.96 39.29 7.79 871.74
5.00
4.50 41.83
3.50 40.83
3.00 0.4329
40.33
y = 0.2362x
2.50 39.83
2.00 39.33
1.50 38.83
1.00 38.33
0.50 37.83
0.00 37.33
0.00 100.00 200.00 300.00 400.00 500.00 600.00 700.00 800.00 900.00 1000.0
3 0
Discharge (m /det)
Ari D. Pasek 17
ASPEK GEOTEKNIK
Aspek pekerjaan geoteknik meliputi:
• Memprediksi rencana jumlah titik, lokasi dan jenis pengeboran
• Memprediksi hasil laboratorium yang diperoleh
• Memprediksi peta geoteknik yang dihasilkan
• Memprediksi posisi dan lintasan bangunan hidrolika dan access road.
• Memprediksi volume galian dan timbunan
• Memprediksi perhitungan stabilitas lereng pada bangunan hidrolika yang
diperlukan
• Memprediksi perhitungan pondasi bangunan hidrolika termasuk pondasi penstock
dan powerhouse
• Memprediksi perhitungan rembesan di weir dan lokasi yang lain yang diperlukan.
Ari D. Pasek 18
ASPEK SIPIL
Ari D. Pasek 19
Weir
Structural stability
• Fall resistance, sliding resistance, soil bearing capacity against resultant external force (weir
own weight, water pressure, sedimentation weight, earth quake and up lift)
Ari D. Pasek 20
Type of Weir
Ari D. Pasek 21
Type of Weir
Ari D. Pasek 22
Type of Weir
Ari D. Pasek 23
Typical Weir
Ari D. Pasek 24
Typical Weir Intake
Ari D. Pasek 25
Weir Intake
Types of intake structures are chiefly distinguished by the method used to
divert water from the
river:
• lateral intake
• bottom intake,
• overhead intake (intake of the water via inlets arranged in piers)
Ari D. Pasek 26
03- 102- 01
SIDE DRAINAGE
SUB SOIL DRAINAGE
40000
HAND RAIL, H=1000
GALVANIS PIPE Ø2"
X = 638778.8463 +49.35
L
+49.20
NE
Y = 85658.8474
AN
+49.35
CH
200
1250
+50.00
500 X = 638744.8661 X = 638741.7605
Y = 85657.6893 Y = 85660.7352
+42.12 +41.52
12000
5700
INTAKE CANAL 2% X = 638741.8269
03- 102- 01
+43.34 Y = 85658.7864 OPEN CANAL
500 03- 102- 01
X = 638741.5663
STEEL LADDER Y = 85666.4319
+49.35
+48.50
1000 950 500
1250
Y = 85669.7433 2000 29800 700 1800 1250 2000
X = 638777.1298
200
Y = 85670.9424
+4
1000
9.3 X = 638741.4999
5 +41.02 Y = 85668.3808
+48.50
X = 638744.4573
+48.50 Y = 85669.6823
+48.50
X = 638746.8559
Y = 85669.7641
HAND RAIL, H=1000
X = 638776.651
Y = 85676.1752
3 GALVANIS PIPE Ø2"
03- 103- 01
+45.00
+41.02 +41.02
500
+43.40
+43.40
02
2-
- 10
03
70
00
05
50
TO R
IVER
0
1.0
+4 RIPRAP
DESAND BASIN LAYOUT Ø30 Cm
70
00
25
SCALE 1 : 150
00
01
2-
- 10
03
02
- 10
2- 98
03 0.4
TO
+4
ER
RIV
RIV
ER
Setting Basin and Desand Ari D. Pasek 27
HAND RAIL, H=1000
GALVANIS PIPE Ø2" VEL
12000 D LE
OUN TEMPORARY CUTTING LINE
INAL GR
1000 ORIG 2000 2000
500 4750
1000
250 COMPACTED BACK FILL
+49.35 +49.35
150
FWL +48.84
+48.50
5830
+46.16 400x400
25
CONCRETE LINING 250mm, Thk NWL +46.067
0
1000
7830
R=50 CONCRETE BEAM 200x400
9500
8830
CLASS B
2500 7000 PLASTER t=25mm
1
DRAINAGE
1:
"B"
4683
+43.40 +43.34
+42.898 +42.84 CONCRETE BEAM 250x450
3000
500 "C"
PLASTER t=25mm CONCRETE COLUMN
2400
500
1
STONE MASONRY (1:4)
1:
+41.00 +41.02 +41.02 STONE MASONRY (1:4) 400x400CLASS B
1000
500
50 250
+40.498
500
500
550
500
EXISTING SOIL 1000 1000
1500 EXISTING SOIL SUB DRAIN EXISTING SOIL
STONE MASONRY (1:4)
300 SAND BEDDING 100 mm, Thk DETAIL A SAND BEDDING 100 mm, Thk
SAND BEDDING 100 mm, Thk SAND BEDDING 100 mm, Thk EXISTING SOIL
RIPRAP Ø30 Cm 300 STONE MASONRY (1:4) SEE DRAWING NO.
MHPP- DWG- Lob- 03- 103- 01
500 4523 500 4977 500 12000 5250
RIVER
B SECTION B - B
03- 101-01
SCALE 1 : 150
Ari D. Pasek 28
Canal
Function
• Conveys water from intake to forebay
Specification to be decided
• Structure type
• Longitudinal slope
• Cross section (flow capacity)
• Material to be used
Ari D. Pasek 29
Canal
Ari D. Pasek 30
Canal
Ari D. Pasek 31
Forebay / Head Tank
The forebay tank forms the connection between the channel and the
penstock . The main purpose is to allow the last particles to settle down
before the water enters the penstock. Depending on its size it can also serve
as a reservoir to store water. A sluice will make it possible to close the
entrance to the penstock. In front of the penstock a trashrack is normally
installed to prevent large particles entering the penstock
Ari D. Pasek 32
38000
11000
8600 2400
26000
+47.00
+42.56
+42.57
+40.45
+43.31
+40.97
+41.82
+43.32
+41.84
+40.95
+44.10
+44.12
X = 638545.7463
Y = 85303.2822
0 X = 638544.1134
7.0 00
+47.00
+4 X = 638558.5334 Y = 85303.1278 30
X = 638559.3629 Y = 85326.7184
Y = 85339.0185
X = 638537.5884
Y = 85307.736 GATE SLOT REFER TO
MECHANICAL DRAWING
21000
+47.00
17100
+40.40
5700
X = 638535.7715
Y = 85308.8788 +39.90
STOP LOG SLOT
X = 638537.1343
Y = 85325.1715
17000
+47.00
X = 638545.1343 X = 638535.5968 X = 638529.7403
+47 Y = 85337.8082
X = 638554.538 .00 Y = 85322.7269 Y = 85313.4156
Y = 85342.0532 2600 2800 8200 2800 600 HAND RAIL, H=1000
Trash Rack
GALVANIS PIPE Ø2"
1500
+47.00
Ari D. Pasek 33
D
LE
1
VE
L
1.5
1000
1:
1.5
1000
:1
HAND RAIL, H=1000 355
200 250
GALVANIS PIPE Ø2" REFER TO
1.5
1000 1683 1912 800 MECHANICAL DRAWING
:1
STEEL LADDER 1500
REFER TO MECHANICAL DRAWING FLUSH GATE 750 1304
2200 INCLINE WALL 696 STONE MASONRY (1:4)
1.5
1000 COMPACTED 500 1800
BACK FILL VENTILATION OF PENSTOCK Ø100
:
+47.00 +47.00
1
+45.98 POINTING FINISH
254
1.5
8
4400
PLASTER t =25mm (1:2) DYNA BOLT
1:
REINFORCEMENT CONCRETE
5600
PLASTER t =25mm (1:2) TRASHRACK
+42.561 2000
+41.90 200
75
WATER STOP 0
°
3000
2000
+40.90
+40.40
800
+39.90
500
EXISTING SOIL EXISTING SOIL EXISTING SOIL
28°
STONE MASONRY (1:4) 250 250 6540 4000 5110 1450 6700
00
4300 2200 1300 17100
17501000
Ø20
SAND BEDDING T=100mm STONE MASONRY (1:4)
SAND BEDDING T=100mm
MEN HOLE REFER TO
MECHANICAL DRAWING
SECTION E - E
Ari D. Pasek 34
Gate
Maintenance is necessary on all turbine setups, whether for repair or preventative.
Flow to the turbine must be first cutoff to the turbine to do this. This is typically done
through the use of gates and or valves located before the turbine. When determining
the gate or valve to be implemented, it is important to make sure that all of the
pressure created from the flow can be withstood
Sluice Gates
Ari D. Pasek 35
Penstock Intake
Ari D. Pasek 36
Penstock Intake
Optimizing power intake
4 2
t V0
hscreen = Kt ( ) (
3
) sin
b 2g
Ari D. Pasek 37
Penstock Intake
Filter Screen at Penstock Intake
Ari D. Pasek 38
Penstock
The penstock is the pipe which conveys water under pressure from the
head tank to the turbine. The penstock often constitutes a major expense
in the total micro-hydro budget, as much as 40% is not uncommon in high
head installations, and it is therefore worthwhile optimizing the design.
The trade-off is between head loss and capital cost. Head loss due to
friction in the pipe decrease dramatically with increasing pipe diameter.
Conversely, pipe costs increase steeply with diameter. Therefore a
compromise between cost and performance is required.
Ari D. Pasek 39
Penstock
Function
• Convey water under pressure from forebay to turbine
Specification to be decided
• Route (Slope, geological conditions etc)
• Material to be used
• Diameter
• Construction cost
• Electricity generation decrease due to loss at penstock
• Durability (Life time, O&M cost)
• Thickness
• Water pressure, own weight, water weight, other external force
Ari D. Pasek 40
Penstock
Effective Head (Net head) is the total head actually acting on the turbine
Ari D. Pasek 41
Penstock
The head loss at the penstock (HL2) can be calculated by the following
equations.
HL2 = hf + he + hv + ho
where,
hf: Frictional loss at penstock
he: Inlet loss
hv: Valve loss
ho: Other losses (bend losses, loss on changes in crosssectional area
and others)
Ari D. Pasek 42
Penstock
Where,
pin and pout = average pressures at the inlet and outlet
Q = VA = steady discharge A = pipe cross-sectional area
Wbend = weight of the bend Wf = weight of the fluid in the bend
Fx and Fy = entire load is assumed to be carried by the anchor block, force components on the pipe bend due to the
anchor block
Vin = (V,0), and Vout = (V cos q, V sin q) = velocity vectors
pinA, 0 = pressure force at the inlet (–pout A cos Ѳ, –pout A sin Ѳ) = pressure force at the outlet
Ari D. Pasek 43
Type of Anchor Block
Ari D. Pasek 44
Penstock
Ari D. Pasek 45
Penstock
Water hammer cycle due to instantaneous valve closure
Ari D. Pasek 46
Penstock
Ari D. Pasek 47
Penstock
Water elevation obtained neglecting friction at the time of closure the surge , is
ymax = Vo [(A/S)(L/g)]1/2
Where,
Vo = steady state flow velocity in the pipe L = length
A = horizontal pipe of cross-sectional area S = surge tank of cross section
Minimum cross-sectional area required for stability of the surge tank derived by Thoma and cited by
Rich (1963) and by Coleman et al. (1999) is
S = (A L ) / ( 2 g k Hs)
Where ,
k = Hi/V2 = is the ratio of the head loss between the reservoir and the surge tank to the square of
the flow velocity in the conduit
Hs = the steady state head in the surge tank
Ari D. Pasek 48
Governor and Valve
Ari D. Pasek 49
Governor and Valve
Ari D. Pasek 50
Power House
Function:
• Provides shelter for the electro-mechanical equipment (turbine,
• generator, control panels, etc.)
Foundation:
• For Impulse turbine
– Pelton turbine, Turgo turbine or cross-flow turbine
• For Reaction turbine
– Francis turbine or propeller turbine, etc.
Ari D. Pasek 51
Powerhouse
Power-house should include:
• A door to handle largest single item
• Windows, louver, and roof vents to provide
good ventilation
• Conduits for electrical wire
• Floor drains
• Small pipe openings
• Lighting
• Have a strong roof structure
• Storage space for spare parts and repair
• Concrete pad to mount turbine generator
Ari D. Pasek 52
Powerhouse Ari D. Pasek 53
Ari D. Pasek 54
Ari D. Pasek 55
Powerhouse
Foundation for Impulse Turbine
Ari D. Pasek 56
Powerhouse
Foundation for Reaction Turbine
Ari D. Pasek 57
V Head Loss
No. Location Formula Coefficient
(m/s) hL (m)
I INTAKE
1 Screen
( a ) . V2 .g . sin q k = 0.100
4 2
hs = k . t 3
1.56 0.0010
head loss t = 2.000 cm
a
q
=
=
15.000 cm
75.000 Head Loss in
V
2
Open Channel
2 Entry 1 ke = 0.700
hi = − 1 .
Cd
2
2 .g 1.56 0.0868
head loss Cd = 0.767
1
Cd = 0 .5
( ke + 1 )
2 DESAND
1 Entry 1 V
2
hi = − 1 .
head loss Cd 2 .g ke = 0.200
2
0.40 0.0016
1 Cd = 0.913
Cd = 0 .5
( ke + 1 )
2 Friction −4 n = 0.025
head loss hi = V 2.n2.R 3 .L R = 2.371 0.40 0.0008
L = 25.000
3 CANAL
1 Entry 1 V
2 ke = 0.200
hi = − 1 . 0.40 0.0016
head loss Cd 2 .g Cd = 0.913
2
1
Cd = 0 .5
( ke + 1 )
2 Friction −4 n = 0.028
head loss hi = V 2.n2.R 3 .L R = 1.275 1.32 0.4234
L = 423.050
4 HEAD TANK
1 Entry 1 V
2
ke = 0.200
hi = − 1 . 0.40 0.0016
head loss Cd 2 .g Cd = 0.913
2
1
Cd = 0 .5
( ke + 1 )
2 Friction −4 n = 0.025
head loss hi = V 2.n2.R 3 .L R = 2.289 0.40 0.0012 Ari D. Pasek 58
L = 36.000
ASPEK MEKANIKAL ELEKTRIKAL
Ari D. Pasek 59
HYDRAULIC TURBINE
H = (net) head t rated
Q = flow rate
N = rotational speed
N, H = constant
Dimensional analysis
Q
N Q
= 3 4
(Dimensionless) specific speed
( gH ) rated
H (m)
Q (m3/s ) Ω is directly related to
N (rad/s ) geometry (type) of turbine
g (m/s 2 )
Ari D. Pasek
Francis
Pelton
Kaplan
N Q Type (geometry)
= 3 4
( gH ) rated
Ari D. Pasek
Pelton turbines (low Ω)
N Q
= 3 4
( gH ) rated
Usually:
• High H
• Small Q
Ari D. Pasek
Twin jet Pelton turbine
wheel or runner
nozzle
pennstock
Ari D. Pasek
Large Pelton turbine
• Vertical axis
• 6 jets (6 nozzles)
Ari D. Pasek
Francis turbines (medium Ω)
N Q
= 3 4
( gH ) rated
Ari D. Pasek
Francis turbine
Spiral
casing
draft
tube
Ari D. Pasek
Reversible Francis pump-turbine
Ari D. Pasek
Kaplan turbines (high Ω)
Usually:
N Q • Low H
= 3 4
( gH ) rated • Large Q
Ari D. Pasek
Kaplan turbine
Electrical
generator
spiral
casing
Guide
vanes
runner
Ari D. Pasek
Kaplan turbine
Double control
Guide-vane
control
Rotor-blade
control
Ari D. Pasek
Cross-flow turbine (also known as Mitchel-Banki and
Ossberger turbine)
Ari D. Pasek
Cross-flow turbine
Ari D. Pasek
Head-flow ranges of small hydro turbines
Ari D. Pasek
H
(m)
Q (m3/s)
gH
2 2
0 . 59
N D
Diameter D
Ari D. Pasek
Francis and
Kaplan
turbines
N Q
= 3 4
( gH ) rated
D
D ( gH )1 4 Specific diameter
=
Q
rated
(dimensionless)
Ari D. Pasek
1.0
Pelton
0.8
Cross-
flow
Efficiency
0.6
t Kaplan
Francis Propeller
0.4
0.2
0.0
0.0 0.2 0.4 0.6 0.8 1.0
Flow rate as proportion of design flow rate
Ari D. Pasek
Tail Race
Ari D. Pasek 80
Tail Race Type
Stilling basin type III for F > 4,5 and V1 < 60 ft/s
Submerged bucket dissipators sloted bucket
Ari D. Pasek
US$/kW
kW installed
Range of costs for small hydropower projects.
Ari D. Pasek
Small hydropower : specific costs of installed capacity
€/kW
Head (m)
Ari D. Pasek
Thank You
Ari D. Pasek 85