Rencana Anggaran Lapangan

Site : SUL-SSL-0100-T-B PADINGDING

NO ITEM PEKERJAAN sat qty Sat Harga Jumlah Harga SUB TOTAL

PONDASI BATU KALI


Volume m3 6.48
Pasir m3 3.37 335,000 1,128,950
Batu Kali m3 7.76 300,000 2,328,000
Semen zak 21.06 47,000 989,820
Papan lbr 12 30,000 360,000
Balok 5/7 btg 8 40,000 320,000
5,126,770
TIMBUNAN PONDASI
Tanah urug m3 2 150,000 300,000
300,000
PLAT
Volume m3 0.63
Pasir m3 3.78 335,000 1,266,300
Chipping m3 0.504 350,000 176,400
Semen zak 0.38 47,000 17,860
Besi Ø10 btg 10 58,000 580,000
2,040,560
TANGGA BATU KALI
Volume 1.672
Pasir m3 0.869 335,000 291,115
Batu Kali m3 2.006 300,000 601,800
Semen zak 5.434 47,000 255,398
1,148,313
PLESTER & CAT PONDASI RBS
Pasir m3 0.501 335,000 167,835
Semen zak 2 47,000 94,000
Cat klg 1 210,000 210,000
CERUCUK PONDASI RBS 471,835
Balok Kayu 5/7 btg 50 40,000 2,000,000
2,000,000

11,087,478

UPAH KERJA 3,000,000


14,087,478
PEKERJAAN ME
UPAH KERJA 3,000,000
17,087,478
0.3
0

1.20

0.1
0.1 0.5 0.1