Daftar Harga Satuan Bahan Bangunan
Daftar Harga Satuan Bahan Bangunan
B. HARGA BAHAN
1 Air Liter 125.00
T Ampelas Lembar 3,500.00
T Besi Strip Tebal 5 mm Kg 150,000.00
T Balok Kayu Kelas II M3 3,900,000.00
2 Batu Bata Buah 1,000.00
3 Batu Kali/ Batu Belah (Sungai/Gunung) M3 250,000.00
4 Besi beton polos kg 17,000.00
5 Besi Beton Ulir kg 25,000.00
T Besi Baja Profil kg 150,000.00
6 Bubungan Genteng M1 60,000.00
7 Bubungan Seng M1 55,000.00
8 Cat Dasar Tembok/Sealer Setara Vinilex kg 40,000.00
9 Cat Kayu Dasar kg 45,000.00
10 Cat Kayu Mengkilap Kg 60,000.00
11 Cat Menie Besi Kg 40,000.00
12 Cat Tembok Setara Vinilex Kg 50,000.00
13 Dempul Kayu Kg 18,000.00
14 Dolken Kayu Ф8-10/400 Cm Batang 75,000.00
15 Door Holder pasang 135,000.00
16 Engsel Jendela pasang 25,000.00
17 Engsel Pintu Pasang 30,000.00
18 Floor Drain buah 27,000.00
19 Gypsum Board Tebal 9 mm Lembar 125,000.00
20 Jaring Kawat Baja kg 36,000.00
21 Hak Angin Pasang 18,000.00
22 Kaca Bening Uk.2mm M2 75,000.00
23 Kaca Bening Uk.3mm M2 85,000.00
24 Kaca Bening Uk.5 mm M2 120,000.00
25 Kaca Rayband Uk.3 mm M2 130,000.00
26 Kaca Rayband Uk. 5 mm M2 135,000.00
27 Kaso-Kaso (5x7) Cm M3 3,500,000.00
28 Kawat Beton kg 25,000.00
29 Kawat Duri kg 50,000.00
30 Kawat Harmonika M2 60,000.00
31 Kawat Nyamuk/Kasa Logam M2 40,000.00
32 Kawat Nyamuk/ Kasa Plastik M2 30,000.00
33 Kayu Bakau 10 Cm Batang 60,000.00
34 Kayu Klas I (Seumantok/Ulim/dll) M3 5,500,000.00
T Kerawang/Rooster Bh 700,000.00
T Kayu Kaso 5 x 7 cm M3 325,000.00
T Kayu Dolken dia. 8 - 10 Cm, L = 4 M Batang 70,000.00
35 Kayu Klas II (Kamper/Kruing/dll) M3 4,800,000.00
36 Kayu Klas III (Borneo/dll) M3 3,900,000.00
37 Kayu Klas IV (Sengon/dll) M3 3,750,000.00
38 Keramik Non Pholised 20 x 20 Cm Setara Ikat Bh 3,000.00
39 Keramik Uk. 20 x 25 Cm Bh 3,500.00
40 Keramik Uk. 40 x 40 cm Bh 12,000.00
41 Keramik Uk. 20 x 25 Cm Bh 3,500.00
42 Keramik Uk. 30 x 30 Cm Bh 6,200.00
43 Kertas Amplas Lembar 3,000.00
44 Kloset Duduk Keramik Setara Toto+Tabung Buah 1,500,000.00
45 Kloset Jongkok Keramik Setara Toto Buah 350,000.00
46 Kran Air 3/4" Buah 10,000.00
47 Kuas Cat Buah 15,000.00
48 Kunci Pintu (Standar) Buah 150,000.00
49 Kunci Pintu Biasa Buah 100,000.00
50 Lampu Hemat Energi 11 watt setara hannochs Buah 35,000.00
51 Lampu Hemat Energi 18 watt setara hannochs Buah 40,000.00
52 Lampu Hemat Energi 20 watt setara hannochs Buah 45,000.00
53 Lem Kayu kg 18,000.00
54 List Eternit kayu M1 8,000.00
55 Marmer M2 50,000.00
56 Minyak Cat Liter 25,000.00
57 Minyak Bekisting Liter 5,000.00
58 Multipleks 3 mm Lembar 70,000.00
59 Multipleks 4 mm Lembar 75,000.00
60 Multipleks 6 mm Lembar 125,000.00
61 Multipleks 9 mm Lembar 155,000.00
62 Pacok Jendela dan Ventilasi pasang 7,500.00
63 Paku Asbes Kg 20,000.00
64 Paku Beton 8 Inci Kotak 19,000.00
65 Paku Kait Buah 1,000.00
66 Paku Kayu Kg 18,000.00
67 Paku Triplek Kg 19,000.00
68 Paku Seng Kg 20,000.00
69 Paku Sumbat Buah 1,200.00
70 Paku Sekrup kg 23,000.00
71 Kerikil Kg 200,000.00
72 Pasir Beton M3 250,000.00
73 Pasir Pasang M3 190,000.00
74 Pasir Urug M3 150,000.00
75 Pelumas/oil Liter 40,000.00
76 Pipa Leading Ф 1" Glavanis Tebal 3,2 mm Batang 75,000.00
77 Pipa Leading Ф 2" Glavanis Tebal 3,2 mm Batang 85,000.00
78 Pipa Leading Ф 3" Glavanis Tebal 3,2 mm Batang 90,000.00
79 Pipa PVC Ф 1" Batang 40,000.00
80 Pipa PVC Ф 2" Batang 50,000.00
81 Pipa PVC Ф 3" Batang 60,000.00
82 Plamir Tembok Kg 30,000.00
83 Plin Keramik Buah 5,000.00
84 Plywood tebal 9mm Lembar 150,000.00
T Plamir Kayu Kg 18,000.00
85 Pemasangan Atap baja Ringan M2 350,000.00
86 Residu Kg 10,000.00
87 Reservoir Air 500 ltr Buah 2,500,000.00
T Profil Aluminium M 80,000.00
T Penjaga Jarak Bekisting / Spacer Bh 30,000.00
T Rabung Seng Genteng M 130,000.00
88 Reservoir Air 1000 ltr Buah 4,000,000.00
89 Reservoir Air 500 ltr stainless Steel Buah 2,000,000.00
90 Schakelar Buah 12,500.00
91 Semen @ 40 kg Zak 55,000.00
92 Semen @ 40 kg Kg 1,375.00
93 Semen Putih @ 50 kg Zak 220,000.00
94 Semen Putih @ 50 kg Kg 4,400.00
95 Semen Warna Kg 7,500.00
96 Seng Genteng Metal M2 75,000.00
97 Seng BJLS 0,20 Cat Pabrik M2 70,000.00
98 Seng Gelobang BJLS 30 M2 50,000.00
99 Seng Gelombang BJLS 30 Cat Pabrik M2 55,000.00
100 Seng Plat BJLS 20 M2 60,000.00
101 Seng Plat BJLS 30 M2 65,000.00
102 Solar (Industri) Liter 12,500.00
103 Sekrup Fixer Buah 500.00
104 Sealant Kg 15,500.00
105 Sumur + Pompa Tangan Terpasang Unit 2,000,000.00
106 Tanah Timbun M3 75,000.00
107 Tiang Pancang M1 300,000.00
108 Teralis Besi M2 380,000.00
109 Titik Lampu + Instalasi Titik 150,000.00
110 Urinoir Keramik Unit 2,500,000.00
111 Vinyl M2 25,000.00
112 WireMesh (Ulir) kg 175,000.00
113 Zakering (Kast Lokal 1 Zekering) Unit 350,000.00
114 Besi Strip Tebal 5 mm Kg 15,000.00
115 Jendela UPVC M2 120,000.00
C. ALAT
1 Stamper Hari-Sewa 50,000.00
2 Dump Truck Jam 200,000.00
3 Molen Jam 100,000.00
Catatan : Bila Bahan Tidak Tercantum Di tabel ini boleh di Tambah
ANALISA HARGA SATUAN PEKERJAAN
Jenis Pekerjaan : Beton Mutu F'c= 26,4 Mpa (K 300),Slump (12 ± 2) cm, W/c= 0,52
Satuan / Unit : M3
Analisa : AHSP PU A.4.1.1.8
No. Uraian Satuan Koefisien Harga Satuan Jumlah Harga
A. TENAGA
1 Pekerja OH 1.6500 150,000.00 247,500.00
2 Tukang OH 0.2750 165,000.00 45,375.00
3 Kepala tukang OH 0.0280 175,000.00 4,900.00
4 Mandor OH 0.0830 170,000.00 14,110.00
Jumlah Tenaga Kerja 311,885.00
B. BAHAN
1 Semen Portland Kg 413.00 1,375.00 567,875.00
2 Pasir Beton Kg 681.00 250,000.00 170,250,000.00
3 Kerikil Kg 1,021.00 200,000.00
4 Air Liter 215.00 125.00 26,875.00
Jumlah Bahan 170,844,750.00
C. PERALATAN
Jumlah Peralatan
D. Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 171,156,635.00
E. Overhead & Profit 10% X D 17,115,663.50
F. Harga Satuan Pekerjaan ( D + E ) 188,272,298.50
Lebar
Panjang
Luas (PxL)
GAMBAR :
1. Pembersihan Lahan
2.00
I. PEKERJAAN PERSIAPAN
= 19
= 22
= 418
GUDANG
+ 0.05
PERHITUNGAN
R.CUCI
- 0.05
KM/WC TERAS
- 0.05
- 0.05
418
VOL
M2
SAT
DAPUR
± 0.00
18.00 R.MAKAN/ R.KELG 22.00
± 0.00 KM/WC
- 0.05
R.TIDUR
KM/WC
+ 0.05
- 0.05
LANTAI 1
Garasi
- 0.05
TERAS
- 0.05
2.00
19.00
2. Pasang Bawplank/Pengukuran
GAMBAR :
20.0
17.0
15.0
1.0
18.0
1.0
A
7
2 Ø 20
4 .5 0
P-1 P-1
Ø12 - 12
P-1
6 P-1 P-1
B B
1 . 51 0. 0 0 3 . 0 0 2 . 5 0 3 . 5 0
Ø12 - 20
P-1 P-1
Ø12- 12
P-1 P-1
38 80
P-1 P-1 P-1
5 P-1 P-1
P-1
2 Ø 20 Ø12 - 20
4 P-1 P-1 P-1
P-1
P-1
P-1 P-1
13
A
3 P-1
2 P-1 P-1
80
1 P-1 P-1
24.3 M 3 7
0.10
c. Pasir Alas
Tinggi = 0.05 M
Lebar = 1 M
Panjang = 1 M TANAH URUG TANAH URUG
Unit = 27 Unit 1.70
1.55
Volume = ( P x L x T ) x Unit 1.35 M3
d. Lantai Kerja/Coran
2.75
Tinggi = 0.1 M
Lebar = 1 M
Panjang = 1 M
Unit = 27 Unit Ø12-15
6Ø20
Volume = (PxLxT)xUnit 2.7 M3 0.80
1.20
e. Pondasi Tapak Berulang 1:2:3
Pias I 0.10 Ø12-12
0.15 4Ø20
Ø12-12
0.10
0.05
0.10 0.21 0.38 0.21 0.10
1.00
Volume = ( P x L x T ) x Unit 2.59 M3
Ø6 - 15
2 Ø 12 2 Ø 12 2 Ø 12
Pias II
Tinggi = 0.1 M
Lebar = 0.8 M
Panjang = 0.8 M
Unit = 27 Unit
LANTAI KERAMIK
Volume = (( P x L x 1/2XT ) x Unit 0.86 M3 SP ESI
P ASIR URUG
LANTAI ±0 .0 0
7
Pias III 0.10
Tinggi = 0.8 M
Lebar = 0.13 M
Panjang = 0.38 M
Unit = 27 Unit
Volume = ( P x L x T ) x Unit 1.07 M3 TANAH URUG TANAH URUG 1.55
1.70
Ø12-15
6Ø20
0.80
1.20
Ø12-12
12 0.10
4Ø20
Ø12-12
0.15
0.10
0.05
0.10 0.21 0.38 0.21 0.10
1.00
NO
3.5 5.0 3.5 3.0 GAMBAR :
2.0 2.0
PERHITUNGAN
III PEKERJAAN TANAH PONDASI MENERUS
2.5
4.5
2.0
1.5
VOL
15.5
3.5
2.0
SAT
1.0
2.5
4.5
3.5
3.0
2.0
1.0
1.5 1.5
f Sloof 25/40
Tinggi = 0.4 M
Lebar = 0.25 M
Panjang = 125.2 M
Volume = (P*L*T) 12.52 M3
125,2x0,25x0,4
IV PEKERJAAN LANTAI
GAMBAR :
- 0 .0 5 ± 0 .0 0
125
3
15 7
10
15
26
67
25
Sloof S=25 / 40
Angker Ø 12 - 100
80 80
Pond. Batu gunung
Tanah Urug
Pas. Batu Kosong
Pasir Alas
15 15
5 5
35 35
70 10 10 70 10
25
d Teras 15
Teras Depan Elv. -0,05 (Bagian 1)
Tinggi = 0.67 M 15
Lebar = 1.25 M
Panjang = 2.78 M
Volume = (PxLxT)
(2,78x1,25x0,67) 2.33 M3
24
5
Teras Belakang Elv. -0,05 (Bagian 2)
Tinggi = 0.67
3
Lebar = 1.75
Panjang = 4.75
Volume = (PxLxT)
(4,75x1,75x0,67) 5.57
e Tangga Belakang Elv. -0.35 (Bagian 1)
Tinggi = 0.11 M
Lebar = 0.17 M
Panjang = 6.69 M
Volume = (PxLxT)
= (6,69x 0,17 x 0,11) 0.13 M3
= 4,90 + 1,68
Volume Total 6.57 M3 3
7
10
n R.Makan/R.Keluarga/Dapur Elv. ± 0.00
I
Tinggi = 0.7 M
Lebar = 3.25 M
Panjang = 11.75 M 67
Volume = (PxLxT)
(11,75x3,25x0,7) 26.73 M3
II
Tinggi = 0.7 M
Lebar = 1.25 M
Panjang = 2.75 M
Volume = (PxLxT)
(2,75x1,25x0,7) 2.41 M3
III
Tinggi = 0.7 M
Lebar = 0.5 M
Panjang = 1 M
Volume = (PxLxT)
= 1x0,5x0,7) 0.35 M3
d Teras
Teras Depan Elv. -0,05 (Bagian 1) 67
Tinggi = 0.1 M
Lebar = 1.37 M
Panjang = 2.9 M
Volume = (PxLxT)
(2,9x1,37x0,1) 0.40 M3
II
Tinggi = 0.1 M
Lebar = 0.5 M
67
Panjang = 0.87 M
Volume = (PxLxT)
(0,87x0,5x0,1) 0.044
II
Tinggi = 0.1 M
Lebar = 0.5 M
Panjang = 1.87 M
Volume = (PxLxT)
= (1,87x0,5x0,1) 0.09 M3
II
Tinggi = 0.1 M
Lebar = 1.37 M
Panjang = 2 M
Volume = (PxLxT) M2
(2x1,37x0,1) 0.27 M3
II
Tinggi = 0.1 M
Lebar = 1.37 M
Panjang = 2.63 M
Volume = (PxLxT)
(2,63x1,37x0,1) 0.36 M3
III
Tinggi = 0.1 M
Lebar = 0.5 M
Panjang = 1.12 M
Volume = (PxLxT)
= (1,12x0,5x0,1) 0.06 M3
15
Belakang
Tinggi = 0.05 M
Lebar = 0.69 M
Panjang = 6.69 M
24
Volume = (PxLxT)
= M3 5
(6,69 x 0,69 x 0,05) 0.23
3
b Teras
Teras Depan Elv. -0,05 (Bagian 1)
Tinggi = 0.07 M
Lebar = 1.5 M
Panjang = 2.9 M
Volume = (PxLxT) Lantai Keramik 40 x 40 cm + spesi
(2,9x1,50x0,07) 0.30 M3 Beton Cor 1 : 3 : 5 t = 7 cm
Pasir Urug t = 10 cm
Teras Belakang Elv. -0,05 (Bagian 2)
Tinggi = 0.07 + 0.00 ± 0.00
Lebar =2 3
Panjang = 4.87 7 3
10 7
Volume = (PxLxT) 10
(4,87x2,0x0,07) 0.68
II
Tinggi = 0.07 M
Lebar = 0.5 M
Panjang = 0.87 M
Volume = (PxLxT)
(0,87x0,5x0,07) 0.030
II
Tinggi = 0.07 M
Lebar = 1.37 M
Panjang = 2 M
Volume = (PxLxT) M2
(2x1,37x0,07) 0.19 M3
Panjang = 4.87
- 0.05 - 0.05
2.00
Volume = (PxL )
(4,87x2,0) M2 1.50
9.74
3.50 DAPUR
18.00 2.00
± 0.00
Lebar = 4.37 M
Panjang = 5.37 M KM/WC
R.TIDUR
+ 0.05
- 0.05
R.TAMU
II
Lebar = 1.37 M
Panjang = 2.63 M
Volume = (PxL)
(2,63x1,37) 3.60 M2
III
Lebar = 0.5 M
Panjang = 1.12 M
Volume = (PxL)
= (1,12x0,5x) 0.56 M2
2 Garasi Elv.-0.05
I
Lebar = 4.87 M
Panjang = 5.37 M
Volume = ( P x L)
(5,37x4,87) 26.15 M2
II
Lebar = 0.5 M
Panjang = 0.87 M
Volume = (PxL)
(0,87x0,5) 0.44 M2
II
Lebar = 1.37 M
Panjang =2 M
Volume = (PxL) M2
(2x1,37) 2.74 M2
II
Lebar = 1.37 M
Panjang =2 M
Volume = (PxL) M2
(2x1,37) 2.74 M2
KM/WC
- 0.05
Lebar = 0.13 M
+ 0.05
R.TIDUR
Panjang = 0.13 M
Unit = 21 Unit
Volume = (PxLxT)xUnit
(0,13x0,13x4,40)x21 1.56 M3
TERAS
- 0.05
± 0.00
R.MAKAN/ R.KELG
TERAS
- 0.05
b Kolom KI 20/20
KM/WC
- 0.05
Tinggi = 4.4 M
Lebar = 0.2 M
KM/WC
- 0.05
R.CUCI
Garasi
=
- 0.05
Panjang 0.2 M
- 0.05
GUDANG
+ 0.05
DAPUR
± 0.00
Unit = 27 Unit
Volume = (PxLxT)xUnit
(02x0,2x4,4)x24 4.75 M3
M3
= (125,2x0,20x0,30)
Ø6-10
VI PEKERJAAN DINDING
GAMBAR : 1 5 .0 0
3.5 0 8.50 3.0 0
2.0 0 GUDANG
+ 0.05
4.50
R.CUCI
- 0.05
4 .50
KM/WC TERAS
- 0.05 - 0.05
2.00
1 .5 0
3 .5 0 DAPUR
1 8.00 2.00
± 0.00
R.MAKAN/ R.KELG
± 0.00 KM/WC
- 0.05
R.TIDUR
KM/WC
+ 0.05
- 0.05
Garasi 4.50
5 .5 0 - 0.05
R.TAMU
± 0.00
2.00
TERAS
- 0.05
1 .5 0
5 .00 5 .00 5 .0 0
15 .0 0
3.50
20/30 20/30
Pas. Bata
0.50
0.40
0.80
0.20 25/40 25/40 25/40 25/40
0.30
0.30 1.00 1.00 1.00 1.00
Kusen Pintu P4
DETAIL P 3
Tinggi = 2.77 M DETAIL P 1
Lebar = 1.01 M
Jumlah = 4 Unit
Luas = (LxT)xUnit
= (1,01x2,77)x4 11.19 M2
Kusen Pintu P5
Tinggi = 2.16 M
Lebar = 0.8 M
Jumlah = 3 Unit
Luas = (LxT)xUnit
= (0,80x2,16)x3 5.18 M2
Kusen Jendela J1
Tinggi = 2.38 M
Lebar = 0.62 M
Jumlah = 4 Unit
Luas = (LxT)xUnit
= (0,62x2,38)x4 5.90 M2
Kusen Jendela J3
Tinggi = 1.88 M
Lebar = 1.18 M
Jumlah = 1 Unit
Luas = (LxT)xUnit
= (1,18x1,88)x1 2.22 M2
Kusen Ventilasi V1
Tinggi = 0.3 M DETAIL V2
DETAIL V 1
Lebar = 0.62 M
Jumlah = 1 Unit
Luas = (LxT)xUnit
= (0,62x0,38)x1 0.19 M2
Kusen Ventilasi V2
Tinggi = 0.3 M
Lebar = 1.18 M
Jumlah = 1 Unit
Luas = (LxT)xUnit
= (1,18x0,3)x1 0.35 M2
1 Tinggi = 0.50 M
Panjang = 75.43 M
Luas = PxT
= 75,43x0,50 37.72 M2
Elv. -0.20
Tinggi = 0.36 M
Panjang = 5.59 M
Volume = PxT
= 5,59x0,36 2.01 M2
Tinggi = 3.90 M
Panjang = 75.43 M
Luas = (PxT)
= (75,43x3,9) 294.18 M2
Wc
Tinggi = 2.00 M
Panjang = 24.06 M
Luas = (PxT)
= (24,06x2) 48.12 M2
137
79
185
a Anak Tangga
Lebar = 1.12 M
Tinggi = 0.2 M
Jumlah = 20 Unit
Alas = 0.3 M
Volume = 1/2 A x T x L x Unit
= 1/2 0,3 x 0,1 x 1,12 x 20 0.67 M3
b Plat Tangga
Lebar = 1.12 M
Panjang = 3.22 M
Tinggi = 0.09 M
Volume = PxLxT
= 3,22x1,12x0,9 0.32 M3
c Plat Bordes
Lebar = 0.97 M
Panjang = 2.37 M
Tinggi = 0.08 M 200
Volume = PxLxT
= 2,37x0,97x0,08 0.18 M3
300
Lebar = 0.1 M
Panjang = 3.57 M
Tinggi = 0.15 M
Volume = PxLxT
= 3,57x0,1x0,15 0.05 M3
e Sloof 25/40
Lebar = 0.25 M
Panjang = 1.3 M
Tinggi = 0.40 M
Volume = PxLxT
= 1,3x0,25x0,40 0.13 M3
f Keramik
Anak Tangga
Panjang = 1.12 M
Lebar = 0.3 M
Jumlah = 20 Unit
Luas = PxLxJumlah
= 1,12x0,3x20 6.72 M2
Bordes
Panjang = 2.37
Lebar = 0.97
Luas = PxL
= 2,37x0,97 2.3 M2
VIII PEKERJAAN PAGAR BETON
NO PERHITUNGAN VOL SAT GAMBAR
a. Pekerjaan Pondasi menerus
1. Galian Tanah Pondasi Menerus
Panjang Horizontal = 25.5 M
Panjang Vertikal = 28.5 M
Total Panjang = 54 M
Tinggi =1 M
Lebar = 0.90 M
Volume = (P*L*T)
(54x0,90x1) 48.6 M3
c Pekerjaan Dinding
Mengitung Dinding Bata Transram 1 : 2
Tinggi = 0.50 M
Panjang = 52.92 M
Luas = PxT
= 52,92x0,50 26.46 M2
d Ring Balok
Tinggi
Panjang
=
=
0.30
54
M
M
30 7Ø12
Lebar = 0.20 M
Volume =
=
(PxLxT)
54x0,20x0,3 3.24 M3 20
VIII PEKERJAAN PLAFOND
a Plafond Triplek 6mm
1 Teras
Teras Depan Elv. -0,05 (Bagian 1)
Lebar = 1.5 M
Panjang = 2.9 M
Volume = (PxL )
(2,9x1,50) 4.35 M2
II
Lebar = 1.37 M
Panjang = 2.63 M
Volume = (PxL)
(2,63x1,37) 3.60 M2
III
Lebar = 0.5 M
Panjang = 1.12 M
Volume = (PxL)
= (1,12x0,5x) 0.56 M2
8 Garasi Elv.-0.05
I
Lebar = 4.87 M
Panjang = 5.37 M
Volume = ( P x L)
(5,37x4,87) 26.15 M2
II
Lebar = 0.5 M
Panjang = 0.87 M
Volume = (PxL)
(0,87x0,5) 0.44 M2
II
Lebar = 1.37 M
Panjang =2 M
Volume = (PxL) M2
(2x1,37) 2.74 M2
10 Bag.Luar
I
Lebar =1 M
Panjang = 22 M
Volume = (PxL) M2
(22x1) 22.00 M2
P-3
P-5 V2
P-3
P-5
P-5
P-3
P-6
V1 P-3
P-3
J-4
Kusen Pintu P3
Tinggi = 0.06 M
Lebar = 0.13 M
Panjang = 6.16 M
Jumlah = 6 Unit DETAIL P1
DETAIL P 3
Luas = (PxLxT)xUnit
= (6,16x0,13x0,06)x6 0.29 M3
Kusen Pintu P4
Tinggi = 0.06 M
Lebar = 0.13 M
Panjang = 6.55 M
Jumlah = 4 Unit
Luas = (PxLxT)xUnit
= (6,55x0,13x0,06)x4 0.20 M3
Kusen Pintu P5
Tinggi = 0.06 M
DETAIL P 5
Lebar = 0.13 M DETAIL P 4
Panjang = 5.12 M
Jumlah = 3 Unit
Luas = (PxLxT)xUnit
= (3,73x0,13x0,06)x3 0.12 M3
Kusen Pintu Garasi
Tinggi = 0.06 M
Lebar = 0.13 M
Panjang = 8.98 M
Jumlah = 1 Unit
Luas = (PxLxT)xUnit
DETAIL P. Garasi
= (8,98x0,13x0,06)x1 0.07 M3
Kusen Jendela J1
Tinggi = 0.06 M
Lebar = 0.13 M
Panjang = 6 M
Jumlah = 4 Unit
Luas = (PxLxT)xUnit
= (6x0,13x0,06)x4 0.19 M3
Kusen Jendela J3
Tinggi
Lebar
=
=
0.06
0.13
M
M
Panjang = 6.12 M
Jumlah = 1 Unit
Luas = (PxLxT)xUnit
= (6,12x0,13x0,06)x1 0.05 M3
Kusen Jendela J4 DETAIL J 1
Tinggi = 0.06 M DETAIL J 3
Lebar = 0.13 M
Panjang = 7.24 M
Jumlah = 2 Unit
Luas = (PxLxT)xUnit
= (7,24x0,13x0,06)x2 0.11 M3
Kusen Ventilasi V1
Tinggi = 0.06 M
Lebar = 0.13 M
Panjang = 1.84 M DETAIL V 1
Jumlah = 1 Unit
Luas = (PxLxT)xUnit
DETAIL J 4
= (1,84x0,13x0,06)x1 0.014 M 3
Kusen Ventilasi V2
Tinggi = 0.06 M
Lebar = 0.13 M
Panjang = 2.96 M
Jumlah = 1 Unit
Luas = (PxLxT)xUnit
= (2,96x0,13x0,06)x1 0.02 M3
DETAIL V2
Total = 0,06+0,29+0,20+0,12+0,07+ 1.12 M3
0,19+0,11+0,014+0,02+0,05
b Daun Pintu
Daun Pintu P1
Lebar = 2.31 M
Panjang = 1.32 M
Unit = 2 Unit
Volume = (PxLx)xUnit
(1,32x2,31)x2 6.10 M2
Daun Pintu P3
Lebar = 2.11 M
Panjang = 0.82 M
=
Unit 6 Unit
Volume = (PxL)xUnit
(0,82x2,11)x6 10.38 M2
Daun Pintu P5
Lebar = 2.16 M
Panjang = 0.7 M
Unit = 3 Unit
Volume = (PxL)xUnit
(0,7x2,16)x3 4.54 M2
Ambang Daun Pintu P4
Lebar = 0.06 M
Panjang = 6.36 M
Unit = 8 Unit
Volume = (PxL)xUnit
(6,36x0,06)x8 3.05 M2
Daun Pintu Garasi
Lebar = 2.51 M
Panjang = 0.5 M
Unit = 8 Unit
Volume = (PxL)xUnit
(0,5x2,51)x8 10.04 M2
Daun Jendela J3
Lebar = 0.08 M
Panjang = 3.64 M
Unit = 2 Unit
Volume = (PxLx)xUnit
(3,64x0.08)x2 0.58 M2
Daun Jendela J4
Lebar = 0.08 M
Panjang = 3.68 M
Unit = 6 Unit
Volume = (PxLx)xUnit
(3,68x0.08)x6 1.77 M2
d Ambang Daun Ventilasi
Daun Ventilasi P1
Lebar = 0.09 M
Panjang = 2.10 M
Unit = 1 Unit
Volume = (PxLx)xUnit
(2,10x0.09)x1 0.19 M2
Daun Ventilasi J1
Lebar
Panjang
=
=
0.09
1.88
M
M
Unit = 4 Unit
Volume = (PxLx)xUnit
(1,89x0.09)x4 0.68 M2
e Ventilasi Pintu
Pintu Garasi
Tinggi = 0.42 M
Lebar = 0.31 M
Panjang = 0.13 M
Jumlah = 8 Unit
Luas = (PxLxT)xUnit
= (0,13x0,31x0,42)x8 0.14 M3
Papan Ventilasi P3
Tinggi = 0.42 M
Lebar = 0.01 M
Panjang = 0.15 M
Unit = 10 Unit
Volume = (PxLxT)xUnit
(0,15x0,01x0,42)x10 0.01 M3
d Kaca
Kaca Jendela J1
Lebar = 1.64 M
Panjang = 0.36 M
Unit = 4 Unit
Volume = (PxL)xUnit
(0,36x1,64)x10 2.36 M2
Kaca Ventilasi J1
Lebar = 0.24 M
Panjang = 0.36 M
Unit = 4 Unit
Volume = (PxL)xUnit
(0,36x0.24)x4 0.35 M2
Kaca Jendela J3
Lebar = 1.15 M
Panjang = 0.36 M
Unit = 2 Unit
Volume = (PxL)xUnit
(0,36x1,15)x2 0.83 M2
Kaca Ventilasi J3
Lebar = 0.4 M
Panjang = 0.52 M
Unit = 2 Unit
Volume = (PxL)xUnit
(0,52x0.4)x2 0.42 M2
Kaca Jendela J4
Lebar = 1.15 M
Panjang = 0.36 M
Unit = 6 Unit
Volume = (PxL)xUnit
(0,36x1,15)x6 2.48 M2
Kaca Ventilasi J4
Lebar = 0.4 M
Panjang = 0.54 M
Unit = 6 Unit
Volume = (PxL)xUnit
(0,54x0.4)x6 1.30 M2
Kaca Ventilasi P1
Lebar = 0.24 M
Panjang = 0.46 M
Unit = 2 Unit
Volume = (PxL)xUnit
(0,46x0.24)x2 0.22 M2
Kaca P4
Lebar = 0.35 M
Panjang = 2.49 M
Unit = 8 Unit
Volume = (PxL)xUnit
(2,49x0,35)x8 6.97 M2
Kaca Ventilasi V1
Lebar = 0.2 M
Panjang = 0.52 M
Unit = 1 Unit
Volume = (PxL)xUnit
(0,52x0.2)x1 0.10 M2
Kaca Ventilasi V2
Lebar = 0.2 M
Panjang
Unit
=
=
0.52
2
M
Unit
Volume = (PxL)xUnit
(0,52x0.2)x4 0.21 M2
Pengecatan Kusen
P1 = (0,13+0,06)x7,06x1 1.34 M2
P3 = (0,13+0,06)x6,16x6 7.02 M2
P4 = (0,13+0,06)x6,55x4 4.98 M2
P5 = (0,13+0,06)x5,12x3 2.92 M2
P.Garasi = (0,13+0,06)x0,5x8 0.76 M2
J1 = (0,13+0,06)x6x4 4.56 M2
J3 = (0,13+0,06)x6,12x1 1.16 M2
J4 = (0,13+0,06)x7,24x2 2.75 M2
V1 = (0,13+0,06)x1,84x1 0.35 M2
V2 = (0,13+0,06)x2,96x1 0.55 M2
Total = 2,18+3,77+12,58+12,26 26.40 M2
IV. PEKERJAAN ATAP
GAMBAR :
1.50 1.50
5.50 5.50
4.50 4.50
.50
b Kaki Kuda-Kuda
Tinggi = 0.12 M
Rabung
Lebar = 0.06 M Nok 5/10
Makelar 6/12
Panjang = 4.99 M Kasau 5/7
Unit = 2 Unit Kaki Kuda-Kuda 6/12
Gapit 2x4/12
Volume = (PxLxT)xUnit 84 Gording 5/10
Tupai-Tupai
(0,12x0,06x4,99)x2 0.07 M3 100
532 Skord Miring 6/12
516 Gapit 2x4/12
100 Skord Tegak 6/12
Atap Seng
c Makelar 100 Balok Tarik 2x5/12
Tinggi = 0.12 M 100
Lebar = 0.06 M
Panjang = 2.1 M
BAUT Ø5/8"
Unit = 1 Unit Ring Balok 20/30 PLAFFOND TRIPLEK 6mm
Volume = (PxLxT)xUnit
(0,12x0,06x2,10)x1 0.02 M3 650
d Balok Gapit
Tinggi = 0.12 M
Lebar = 0.04 M
Panjang = 4.06 M
Unit = 2 Unit
Volume = (PxLxT)xUnit
(0,12x0,04x4,06)x2 0.04 M3
e Sokong Miring
Tinggi = 0.12 M
Lebar = 0.06 M
Panjang = 1.66 M
Unit = 2 Unit
Volume = (PxLxT)xUnit
(0,12x0,06x1,66)x2 0.02 M3
f Sokong Tegak
Tinggi = 0.12 M
Lebar = 0.06 M
Panjang = 1.07 M
Unit = 2 Unit
Volume = (PxLxT)xUnit
(0,12x0,06x1,07)x2 0.02 M3
b KD-4 1/2
a Balok Tarik
Tinggi = 0.12 M
Lebar = 0.05 M
Panjang = 3.67 M
Unit = 2 Unit
Volume = (PxLxT)xUnit
(0,12x0,05x3,67)x2 0.04 M3
b Kaki Kuda-Kuda
Tinggi = 0.12 M
Lebar = 0.06 M
Panjang = 5.14 M
Unit = 1 Unit
Volume = (PxLxT)xUnit
(0,12x0,06x5,14)x1 0.04 M3
c Balok Gapit
Tinggi = 0.12 M
Lebar = 0.04 M
Panjang = 2.32 M
Unit = 2 Unit
Volume = (PxLxT)xUnit
(0,12x0,04x2,32)x2 0.02 M3
d Sokong Miring
Tinggi = 0.12 M
Lebar = 0.06 M
Panjang = 1.84 M
Unit = 1 Unit
Volume = (PxLxT)xUnit
(0,12x0,06x1,84)x1 0.01 M3
e Sokong Tegak
Tinggi = 0.12 M
Lebar = 0.06 M
Panjang = 1.17 M
Unit = 1 Unit
Volume = (PxLxT)xUnit
(0,12x0,06x1,17)x2 0.01 M3
c Ikatan Angin
a Tinggi = 0.12 M
Lebar = 0.04 M
Panjang = 2.06 M
Unit = 2 Unit
Volume = (PxLxT)xUnit
(0,10x0,05x2,06)x2 0.02 M3
2. RANGKA ATAP
A Gording
a Tinggi = 0.1 M
Lebar = 0.05 M
Panjang = 5.88 M
Unit = 1 Unit
Volume = (PxLxT)xUnit
(0,10x0,05x5,88)x1 0.03 M3
b Tinggi = 0.1 M
Lebar = 0.05 M
Panjang = 4.88 M
Unit = 1 Unit
Volume = (PxLxT)xUnit
(0,10x0,05x4,88)x1 0.02 M3
c Tinggi = 0.1 M
Lebar = 0.05 M
Panjang = 3.88 M
Unit = 1 Unit
Volume = (PxLxT)xUnit
(0,10x0,05x3,88)x1 0.02 M3
d Tinggi = 0.1 M
Lebar = 0.05 M
Panjang = 2.88 M
Unit = 2 Unit
Volume = (PxLxT)xUnit
(0,10x0,05x2,88)x2 0.03 M3
e Tinggi = 0.1 M
Lebar = 0.05 M
Panjang = 1.88 M
Unit = 3 Unit
Volume = (PxLxT)xUnit
(0,10x0,05x1,88)x3 0.03 M3
f Tinggi = 0.1 M
Lebar = 0.05 M
Panjang = 8.26 M
Unit = 1 Unit
Volume = (PxLxT)xUnit
(0,10x0,05x8,26)x1 0.04 M3
g Tinggi = 0.1 M
Lebar = 0.05 M
Panjang = 6.26 M
Unit = 1 Unit
Volume = (PxLxT)xUnit
(0,10x0,05x6,26)x1 0.03 M3
h Tinggi = 0.1 M
Lebar = 0.05 M
Panjang = 4.26 M
Unit = 1 Unit
Volume = (PxLxT)xUnit
(0,10x0,05x4,26)x1 0.02 M3
i Tinggi = 0.1 M
Lebar = 0.05 M
Panjang = 2.26 M
Unit = 1 Unit
Volume = (PxLxT)xUnit
(0,10x0,05x2,26)x1 0.01 M3
j Tinggi = 0.1 M
Lebar = 0.05 M
Panjang = 2.82 M
Unit = 4 Unit
Volume = (PxLxT)xUnit
(0,10x0,05x2,82)x4 0.06 M3
k Tinggi = 0.1 M
Lebar = 0.05 M
Panjang = 1.32 M
Unit = 3 Unit
Volume = (PxLxT)xUnit
(0,10x0,05x1,32)x3 0.02 M3
l Tinggi = 0.1 M
Lebar = 0.05 M
Panjang = 0.88 M
Unit = 1 Unit
Volume = (PxLxT)xUnit
(0,10x0,05x0,88)x1 0.004 M3
B Kasau
1 Tinggi = 0.07 M
Lebar = 0.05 M
Panjang = 4.2 M
Unit = 4 Unit
Volume = (PxLxT)xUnit
(0,07x0,05x4,2)x4 0.06 M3
2 Tinggi = 0.07 M
Lebar = 0.05 M
Panjang = 3.89 M
Unit = 3 Unit
Volume = (PxLxT)xUnit
(0,07x0,05x3,89)x3 0.04 M3
3 Tinggi = 0.07 M
Lebar = 0.05 M
Panjang = 3.39 M
Unit = 3 Unit
Volume = (PxLxT)xUnit
(0,07x0,05x3,39)x3 0.04 M3
4 Tinggi = 0.07 M
Lebar = 0.05 M
Panjang = 2.89 M
Unit = 4 Unit
Volume = (PxLxT)xUnit
(0,07x0,05x2,89)x4 0.04 M3
5 Tinggi = 0.07 M
Lebar = 0.05 M
Panjang = 3.89 M
Unit = 3 Unit
Volume = (PxLxT)xUnit
(0,07x0,05x3,89)x3 0.04 M3
6 Tinggi = 0.07 M
Lebar = 0.05 M
Panjang = 3.39 M
Unit = 3 Unit
Volume = (PxLxT)xUnit
(0,07x0,05x3,39)x3 0.04 M3
7 Tinggi = 0.07 M
Lebar = 0.05 M
Panjang = 2.89 M
Unit = 4 Unit
Volume = (PxLxT)xUnit
(0,07x0,05x2,89)x4 0.04 M3
8 Tinggi = 0.07 M
Lebar = 0.05 M
Panjang = 2.39 M
Unit = 5 Unit
Volume = (PxLxT)xUnit
(0,07x0,05x2,39)x5 0.04 M3
9 Tinggi = 0.07 M
Lebar = 0.05 M
Panjang = 1.89 M
Unit = 5 Unit
Volume = (PxLxT)xUnit
(0,07x0,05x1,89)x5 0.03 M3
10 Tinggi = 0.07 M
Lebar = 0.05 M
Panjang = 1.39 M
Unit = 5 Unit
Volume = (PxLxT)xUnit
(0,07x0,05x1,39)x5 0.02 M3
11 Tinggi = 0.07 M
Lebar = 0.05 M
Panjang = 0.89 M
Unit = 6 Unit
Volume = (PxLxT)xUnit
(0,07x0,05x0,89)x6 0.02 M3
12 Tinggi = 0.07 M
Lebar = 0.05 M
Panjang = 0.39 M
Unit = 6 Unit
Volume = (PxLxT)xUnit
(0,07x0,05x0,39)x6 0.01 M3
13 Tinggi = 0.07 M
Lebar = 0.05 M
Panjang = 2.82 M
Unit = 3 Unit
Volume = (PxLxT)xUnit
(0,07x0,05x2,82)x3 0.03 M3
14 Tinggi = 0.07 M
Lebar = 0.05 M
Panjang = 2.63 M
Unit = 1 Unit
Volume = (PxLxT)xUnit
(0,07x0,05x2,63)x4 0.009 M3
15 Tinggi = 0.07 M
Lebar = 0.05 M
Panjang = 2.13 M
Unit = 1 Unit
Volume = (PxLxT)xUnit
(0,07x0,05x2,13)x1 0.007 M3
16 Tinggi = 0.07 M
Lebar = 0.05 M
Panjang = 1.63 M
Unit = 1 Unit
Volume = (PxLxT)xUnit
(0,07x0,05x1,63)x1 0.006 M3
17 Tinggi = 0.07 M
Lebar = 0.05 M
Panjang = 1.13 M
Unit = 1 Unit
Volume = (PxLxT)xUnit
(0,07x0,05x1,13)x1 0.004 M3
18 Tinggi = 0.07 M
Lebar = 0.05 M
Panjang = 1.32 M
Unit = 4 Unit
Volume = (PxLxT)xUnit
(0,07x0,05x1,32)x4 0.018 M3
19 Tinggi = 0.07 M
Lebar = 0.05 M
Panjang = 0.92 M
Unit = 1 Unit
Volume = (PxLxT)xUnit
(0,07x0,05x0,92)x1 0.003 M3
20 Tinggi = 0.07 M
Lebar = 0.05 M
Panjang = 0.42 M
Unit = 1 Unit
Volume = (PxLxT)xUnit
(0,07x0,05x0,42)x1 0.001 M3
1 Lebar = 5.5 M
Panjang = 8.5 M
Volume = (PxL)
(8,5x5,5) 46.75 M2
2 Lebar = 5.32 M
Panjang =6 M
Volume = (PxL)
(6x5,32) 31.92 M2
3 Lebar = 5.32 M
Panjang =3 M
Volume = (PxL)
(3x5,32) 15.96 M2
4 Lebar = 3.23 M
Panjang = 1.5 M
Volume = (PxL)
(1,5x3,23) 4.85 M2
5 Lebar = 3.23 M
Panjang =3 M
Volume = (PxL)
(3x3,23) 9.69 M2
Panjang = 22 M
Jumlah =2 Unit
Total = (P x Unit) 44
M
(22 x 2)
E Rabung
F Jurai Luar
G Jurai Dalam
2.00
4.50 8.00
2.00
1.50
3.50 R .TIDUR
+ 0.00
2.00
KM/WC
22.00 - 0.05
.20
.97
2.37 4.50
B 5.50 B
KM/WC
- 0.05
R.TIDUR
+ 0.00 2.00
7.50
6.50
A 4.00
3.37 4.87
1.87 1.87 20/30 20/30
3.37 3.851.87
12 Ø 100
1 2 Ø 15
1 2 Ø 15
1 2 Ø 15
1 2 Ø 15
1 2 Ø 15
1 2 Ø 15
20/30
3.37 3.37
20/30
20/30
12 Ø100
20/30
2.39
20/30
12 Ø 15
12 Ø 15
12 Ø 15
20/30
20/30
12 Ø 15
1.87
5.37
12 Ø 15
1.87
1.87
20/30
12 Ø 15
20/30
20/30
20/30
20/30
12 Ø 15
12 Ø 15
12 Ø 15
NO PERHITUNGAN VOL SAT GAMBAR
1 PLAT LANTAI
a Pias I
Tinggi = 0.12 M
Panjang = 5.37 M
Lebar = 3.37 M
Banyak Pias I (U) = 1
Volume = (PxLxT)xU
= (3,37x5,37x0,12)x1 2.17 M3
b Pias II
Tinggi = 0.12 M
Panjang = 3.37 M
Lebar = 3.37 M
Banyak Pias I (U) = 1
Volume = (PxLxT)xU
= (3,37x3,37x0,12)x1 1.36 M3
c Pias III
Tinggi = 0.12 M
Panjang = 1.87 M
Lebar = 3.37 M
Banyak Pias I (U) = 1
Volume = (PxLxT)xU
= (1,87x3,37x0,12)x1 0.76 M3
d Pias IV
Tinggi = 0.12 M
Panjang = 1.87 M
Lebar = 4.87 M
Banyak Pias I (U) = 1
Volume = (PxLxT)xU
= (1,87x4,87x0,12)x1 1.09 M3
e Pias V
Tinggi = 0.12 M
Panjang = 1.87 M
Lebar = 3.85 M
Banyak Pias I (U) = 1
Volume = (PxLxT)xU
= (1,87x3,85x0,12)x1 0.86 M3
f Pias VI
Tinggi = 0.12 M
Panjang = 1.87 M
Lebar = 1.87 M
Banyak Pias I (U) = 1
Volume = (PxLxT)xU
= (1,87x1,87x0,12)x1 0.42 M3
g Pias VII
Tinggi = 0.12 M
Panjang = 0.85 M
Lebar = 1.37 M
Banyak Pias I (U) = 1
Volume = (PxLxT)xU
= (0,85x1,37x0,12)x1 0.14 M3
h Pias VIII
Tinggi = 0.12 M
Panjang = 3.37 M
Lebar = 2.39 M
Banyak Pias I (U) = 1
Volume = (PxLxT)xU
= (3,37x2,39x0,12)x1 0.97 M3
i Pias IX
Tinggi = 0.12 M
Panjang = 2.50 M
Lebar = 2.37 M
Banyak Pias I (U) = 1
Volume = (PxLxT)xU
= (2,50x2,37x0,12)x1 0.71 M3
j Pias X
Tinggi = 0.12 M
Panjang = 1.37 M
Lebar = 3.98 M
Banyak Pias I (U) = 1
Volume = (PxLxT)xU
= (1,37x3,98x0,12)x1 0.65 M3
k Pias XI
Tinggi = 0.12 M
Panjang = 2.50 M
Lebar = 1.87 M
Banyak Pias I (U) = 1
Volume = (PxLxT)xU
= (2,50x1,87x0,12)x1 0.56 M3
l Pias XII
1 Tinggi = 0.12 M
Panjang = 1.87 M
Lebar = 1.87 M
Banyak Pias I (U) = 1
Volume = (PxLxT)xU
= (1,87x1,87x0,12)x1 0.42 M3
2 Tinggi = 0.12 M
Panjang = 0.50 M
Lebar = 1.37 M
Banyak Pias I (U) = 1
Volume = (PxLxT)xU
= (0,50x1,37x0,12)x1 0.08 M3
2 Tinggi = 0.12 M
Panjang = 0.50 M
Lebar = 2.37 M
Banyak Pias I (U) = 1
Volume = (PxLxT)xU
= (0,50x2,37x0,12)x1 0.14 M3
2 BALOK LANTAI
a Balok Lantai 20/30
Tinggi = 0.3 M
Panjang = 89.53 M
Lebar = 0.20 M
Volume = (PxLxT)
= 89,53x0,20x0,30 5.37 M3
2 Balkon
4.50
Belakang Elv. +4.05 2.00
Lebar = 8.63 M
Panjang =2 M 1.50
Volume = (PxL )
3.50 R.TIDUR
+ 0.00
(2x8,63) 17.26 M 2
18.00 2.00
Lebar = 3.34 M
Panjang = 5.37 M 4.50
Volume = (PxL ) 5.50
KM/WC
3 Kamar Tidur
R.TIDUR
+ 0.00 2.00
K.Tidur 1
2.50
Lebar = 3.37 M TERAS 1.50
- 0.05
Panjang = 3.37 M
Volume = (PxL )
(3,37x3,37) 11.36 M2 5.00 5.00
K.Tidur 2
I
Lebar = 4.37 M
Panjang = 3.87 M
Volume = (PxL )
(3,87x4,37) 16.91 M2
II
Lebar = 0.5 M
Panjang = 2.37 M
Volume = (PxL )
(2,37x0,50) 1.19 M2
4 Ruang Santai
I
Lebar = 6.37 M
Panjang = 3.37 M
Volume = (PxL )
(3,37x6,37) 21.47 M2
II
Lebar = 1.87 M
Panjang = 2.5 M
Volume = (PxL )
(2,5x1,87) 4.68 M2
b Keramik 30x30
WC 1
Lebar = 1.87 M
Panjang = 1.87 M
Luas = (PxL)
= (1,87x1,87) 3.5 M2
WC 2
I
Lebar = 1.87 M
Panjang = 1.87 M
Luas = (PxL)
= (1,87x1,87) 3.5 M2
II
Lebar = 1.37 M
Panjang = 0.5 M
Luas = (PxL)
= (0,5x1,37) 0.7 M2
KP
KI
KP KP KP
KP
KI KP KP KP
11.0
KP KP KI KI
KI
KP
KP
KP
KP KI
KI KP KI
KP
KI KI
2 Tinggi = 1.67 M
Lebar = 0.13 M
Panjang = 0.13 M
Unit = 1 Unit
Volume = (PxLxT)xUnit
(0,13x0,13x1,67)x1 0.03 M3
b Kolom KI 20/20
1 Tinggi = 3.41 M
Lebar = 0.2 M
Panjang = 0.2 M
Unit = 11 Unit
Volume = (PxLxT)xUnit
(0,2x0,2x3,41)x13 1.50 M3
2 Tinggi = 1.67 M
Lebar = 0.2 M
Panjang = 0.2 M
Unit = 2 Unit
Volume = (PxLxT)xUnit
(0,2x0,2x1,67)x2 0.13 M3
Jendela
DETAIL P 3
Tinggi = 1.92 M
Lebar = 0.56 M
Jumlah = 2 Unit
Luas = (LxT)xUnit
= (0,56x1,92)x2 2.15 M2
Kusen Pintu P3
Tinggi = 2.62 M
Lebar = 0.92 M
Jumlah = 2 Unit
Luas = (LxT)xUnit
= (0,92x2,62)x2 4.82 M2
Kusen Pintu P5
Tinggi = 2.16 M
Lebar = 0.8 M
Jumlah = 2 Unit
Luas = (LxT)xUnit
= (0,80x2,16)x2 3.46 M 2
Kusen Jendela J2
Tinggi = 1.92 M
Lebar = 0.62 M
Jumlah = 6 Unit
Luas = (LxT)xUnit
= (0,62x1,92)x6 7.14 M2
Kusen Jendela J3
Tinggi = 1.88 M
Lebar = 1.18 M
Jumlah = 1 Unit
Luas = (LxT)xUnit
= (1,18x1,88)x1 2.22 M2
Kusen Ventilasi V1
Tinggi = 0.3 M
Lebar = 0.62 M
Jumlah = 1 Unit DETAIL P 5
Luas = (LxT)xUnit
= (0,62x0,38)x1 0.19 M2
Kusen Ventilasi V2
Tinggi = 0.3 M DETAIL V2
Lebar = 1.18 M
Jumlah = 1 Unit
Luas = (LxT)xUnit
=
(1,18x0,3)x1 0.35 M2
DETAIL V1
Total Luas Kusen = P2+PJ+P3+P5+J2+J3+V1+V2 25.80 M2
Tinggi = 3.50 M
Panjang = 43.49 M NOK 5/10
Luas = (PxT) TIANG KUDA-KUDA 6/12
NOK 5/10
TIANG KUDA-KUDA 6/12
= (43,49x3,5) 152.22 M 2
KAKI KUDA-KUDA 6/12
IKATAN ANGN 4/12
KASAU 5/7
TIANG KUDA-KUDA 6/12
Wc GORDING 5/10
KAKI KUDA-KUDA 6/12
Tinggi = 1.60 M
Panjang = 13.96 M
Luas = (PxT) Pas. Bata 1:4
= (13,96x1,6) 22.34 M2
1.80
Atas Ringbalok
Tinggi = 1.67 M
Panjang = 5.21 M Pas. Bata 1:4 Pas. Bata
Luas = (PxT)
= (5,216x1,67) 8.70 M2
3.50
Balkon Samping
+4.05 + 4.10
Tinggi = 0.80 M
Panjang = 3.33 M
Luas = (PxT)
= (3,33x0,80) M2 20/30 20/30
2.66
3.50
Volume Total = Volume Dinding Bata 1:4 - 156.66
M2
L.Total Kusen - L. Kusen P5
1 5 /2 0
1 5 /2 0
15/20 15/20
15/20 15/20
1 5 /2 0
1 5 /2 0
1 5 /2 0
1 5 /2 0
15/20
1 5 /2 0
15/20
11.0
1 5 /2 0
15/20
15/20
1 5 /2 0
1 5 /2 0
15/20
10.0
NO PERHITUNGAN VOL SAT GAMBAR
1. Menghitung Ring Balok
Ø6-10
20
Balok Lantai 15/20
Tinggi = 0.2 M 7Ø12
Panjang = 89.53 M
Lebar = 0.20 M
Volume = (PxLxT)
= (89,53x0,13x0,2) 3.58 M3
J-3
P-3
PJ1
P-5
J-5
J-6
P-5
P-3
Kusen Pintu PJ
Tinggi = 0.06 M
Lebar = 0.13 M
Panjang = 8.76 M
Jumlah = 1 Unit
Luas = (PxLxT)xUnit
(8,76x0,13x0,06)x1 0.07 M3
Kusen Pintu P3 DETAIL P 3
Tinggi = 0.06 M
Lebar = 0.13 M
Panjang = 7.08 M
Jumlah = 2 Unit
Luas = (PxLxT)xUnit
= (7,08x0,13x0,06)x2 0.11 M3
Kusen Pintu P5
Tinggi = 0.06 M
Lebar = 0.13 M
Panjang = 5.92 M
Jumlah = 2 Unit
Luas = (PxLxT)xUnit
= (5,92x0,13x0,06)x2 0.09 M3
Kusen Jendela J2
Tinggi = 0.06 M
Lebar = 0.13 M
Panjang = 5 M
Jumlah = 6 Unit
Luas = (PxLxT)xUnit
= (5x0,13x0,06)x6 0.24 M3
Kusen Jendela J3
Tinggi = 0.06 M
Lebar = 0.13 M
Panjang = 4.96 M
Jumlah = 1 Unit
Luas = (PxLxT)xUnit
= (4,96x0,13x0,06)x1 0.04 M3
DETAIL P 5
Kusen Ventilasi V1
Tinggi = 0.06 M
Lebar = 0.13 M
Panjang = 1.84 M
Jumlah = 1 Unit
Luas = (PxLxT)xUnit
DETAIL V2
= (1,84x0,13x0,06)x1 0.014 M3
Kusen Ventilasi V2
Tinggi = 0.06 M
Lebar = 0.13 M DETAIL V1
Panjang = 2.96 M
Jumlah = 1 Unit
Luas = (PxLxT)xUnit
= (2,96x0,13x0,06)x1 0.02 M3
Total = 0,06+0,29+0,11+0,09+0,24+ 0.64 M3 DETAIL J 3
0,04+0,14+0,02
b Daun Pintu Dan Ambang Daun Jendela
Daun Pintu P2
Lebar = 0.66 M
Panjang = 2.28 M
Jumlah =2 Unit
Luas = (PxL)xUnit
(2,28x0,66x)x2 3.01 M 2
Daun Pintu Dan Ambang Jendela PJ
Pintu
Lebar = 0.83 M
Panjang = 2.28 M
Jumlah =1 Unit
Luas = (PxL)xUnit
(2,28x0,83)x1 1.89 M2
Daun Pintu P3
Lebar = 0.82 M
Panjang = 2.11 M
Jumlah = 2 Unit
Luas = (PxL)xUnit
= (2,11x0,82)x2 3.46 M2
Daun Pintu P5
Lebar = 0.7 M
Panjang = 2.11 M
Jumlah = 2 Unit
Luas = (PxL)xUnit
= (2,11x0,7)x2 2.95 M2
Ambang Daun Jendela J2
Lebar = 0.08 M
Panjang = 5 M
Jumlah = 6 Unit
Luas = (PxL)xUnit
= (5x0,08)x6 2.25 M 2
Ambang Daun Jendela J3
Lebar = 0.08 M
Panjang = 3.68 M
Jumlah = 2 Unit
Luas = (PxL)xUnit
= (3,68x0,08)x2 0.59 M 2
Papan Ventilasi P3
Tinggi = 0.42 M
Lebar = 0.01 M
Panjang = 0.15 M
Unit = 20 Unit
Volume = (PxLxT)xUnit
(0,15x0,01x0,42)x20
0.013 M3
c Kaca
Kaca Jendela PJ
Lebar = 0.34 M
Panjang = 1.64 M
Jumlah = 2 Unit
Luas = (PxL)xUnit
= (1,64x0,34)x2 1.12 M 2
Kaca Jendela J3
Lebar = 0.36 M
=
Panjang 1.15 M
Jumlah = 2 Unit
Luas = (PxL)xUnit
= (0,36x1,15)x2 0.83 M2
Kaca Ventilasi V1
Lebar = 0.2 M
Panjang = 0.52 M
Unit = 1 Unit
Volume = (PxL)xUnit
(0,52x0.2)x1 0.10 M2
Kaca Ventilasi V2
Lebar = 0.2 M
Panjang = 0.52 M
Unit = 2 Unit
Volume = (PxL)xUnit
(0,52x0.2)x4 0.21 M2
V. PEKERJAAN PLAFOND
A Plafond Triplek 6mm
1 Teras Elv. +4.00
Lebar = 2.9 M
Panjang = 1.37 M
Volume = (PxL )
(2,9x1,37) 3.97 M2
2 Kamar Tidur
K.Tidur 1
Lebar = 3.37 M
Panjang = 3.37 M
Volume = (PxL )
(3,37x3,37) 11.36 M2
K.Tidur 2
I
Lebar = 4.37 M
Panjang = 3.87 M
Volume = (PxL )
(3,87x4,37) 16.91 M2
II
Lebar = 0.5 M
Panjang = 2.37 M
Volume = (PxL )
(2,37x0,50) 1.19 M2
3 Ruang Santai
I
Lebar = 6.37 M
Panjang = 3.37 M
Volume = (PxL )
(3,37x6,37) 21.47 M2
II
Lebar = 1.87 M
Panjang = 2.5 M
Volume = (PxL )
(2,5x1,87) 4.68 M2
4 WC 1
Lebar = 1.87 M
Panjang = 1.87 M
Luas = (PxL)
= (1,87x1,87) 3.5 M2
5 WC 2
I
Lebar = 1.87 M
Panjang = 1.87 M
Luas = (PxL)
= (1,87x1,87) 3.5 M2
II
Lebar = 1.37 M
Panjang = 0.5 M
Luas = (PxL)
= (0,5x1,37) 0.7 M2
Volume Total = 3,5 + 0,7 4.18 M2
6 Bag.Luar
Lebar = 1 M
Panjang = 46.01 M
Luas = (PxL)
= (1,87x1,87) 46.0 M2
11.00 5.00
4.50 3.00 11.00 5.00
4.50 3.00
1.50
1.50
5.50
5.50
12.00 8.5012.00
12.00 8.5012.00
4.50
4.50
2.00 2.00
2.00 2.00
.50
Skala. 1 : 100 2.50 1.50 7.00 5.00 2.50 1.50 7.00 5.00
b Kaki Kuda-Kuda
Tinggi = 0.12 M
Lebar = 0.06 M
Panjang = 3.26 M
Unit =2 Unit
Volume = (PxLxT)xUnit
(0,12x0,06x3,26)x2 0.05 M3
Rabung
c Makelar Makelar 6/12
Tinggi = 0.12 M Kaki Kuda-Kuda 6/12
Lebar = 0.06 M Kasau 5/7
23
Panjang = 1.24 M Skord Miring 6/12
Unit = 1 Unit 100 Gapit 2x4/12 Atap Seng
328 Balok Tarik 2x5/12
Volume = (PxLxT)xUnit 345
(0,12x0,06x1,24)x1 0.01 M3 100 Gording 5/10
124 326 Tupai-Tupai
d Balok Gapit 78 254
100
Tinggi = 0.12 M
Lebar = 0.04 M
Panjang = 2.54 M BAUT Ø5/8"
Unit = 2 Unit
Volume = (PxLxT)xUnit Ring Balok 15/20
(0,12x0,04x2,54)x2 0.02 M3 100 350 100
e Sokong Miring
Tinggi = 0.12 M
Lebar = 0.06 M
Panjang = 0.78 M
Unit = 2 Unit
Volume = (PxLxT)xUnit
(0,12x0,06x0,78)x2 0.01 M3
B KD-2
a Balok Tarik
Tinggi = 0.16 M
Lebar = 0.05 M
Panjang = 7.21 M
Unit = 2 Unit
Volume = (PxLxT)xUnit
(0,16x0,05x7,21)x2 0.12 M3
RABUNG
NOK 5 /1 0
TIANG KUDA-KUDA 1 4 /1 4
KASAU 5 /7
KAKI KUDA-KUDA 6 /1 4
GAPIT 2 x4 /1 2
79 SKORD MIRING 6 /1 2
GAPIT 2 x 4 /1 2
b Kaki Kuda-Kuda 100 BAUT Ø1 2 mm
519
Tinggi = 0.14 M 499 SKORD TEGAK 6 /1 2
Lebar = 0.06 M 100 GORDING 5 /1 0
TUPAI-TUPAI
Panjang = 4.99 M 499 ATAP GENTENG METAL
100 3 0 02 1 3 BALOK TARIK 2 x 5 /1 6
Unit = 2 Unit 1 3125 2
Volume = (PxLxT)xUnit 100 RING BALOK 1 5 /2 5
D-2
86 119
(0,14x0,06x4,99)x2 0.08 M3 195
D-1
c Makelar
Tinggi = 0.14 M 60 60 60
Lebar = 0.14 M 226 268 226
721
Panjang = 2.13 M
Unit = 1 Unit
Volume = (PxLxT)xUnit
(0,14x0,14x1,24)x1 0.04 M3
C KD-2 1/2
a Balok Tarik
Tinggi = 0.16 M
Lebar = 0.05 M
Panjang = 3.7 M
Unit = 2 Unit
Volume = (PxLxT)xUnit
(0,16x0,05x3,7)x2 0.06 M3
b Kaki Kuda-Kuda
TIANG KUDA-KUDA 6/12
Tinggi = 0.14 M
Lebar = 0.06 M KAKI KUDA-KUDA 6/12
Panjang = 5.28 M KASAU 5/7
Unit = 1 Unit GORDING 5/10
Volume = (PxLxT)xUnit
(0,14x0,06x5,28)x1 0.04 M3
d Sokong Miring
Tinggi = 0.12 M
Lebar = 0.06 M
Panjang = 1.82 M
Unit = 1 Unit
Volume = (PxLxT)xUnit
(0,12x0,06x1,82)x2 0.01 M3
e Sokong Tegak
Tinggi = 0.12 M
Lebar = 0.06 M
Panjang = 1.06 M
Unit = 1 Unit
Volume = (PxLxT)xUnit
(0,12x0,06x1,06)x1 0.01 M3
D KD-3
a Balok Tarik
Tinggi = 0.12 M
Lebar = 0.05 M
Panjang = 5.61 M
Unit = 2 Unit
Volume = (PxLxT)xUnit
(0,12x0,05x5,61)x2 0.07 M3
b Kaki Kuda-Kuda
Tinggi = 0.12 M
Lebar = 0.06 M
Panjang = 4.13 M Rabung
Unit = 2 Unit Nok 5/10
Makelar 6/12
Volume = (PxLxT)xUnit
(0,12x0,06x4,13)x2 0.06 M3 Kaki Kuda-Kuda 6/12
98 Kasau 5/7
Unit = 1 Unit
Volume = (PxLxT)xUnit 561
BAUT Ø5/8"
PLAFFOND TRIPLEK 6mm
e Sokong Miring
Tinggi = 0.12 M
Lebar = 0.06 M
Panjang = 0.84 M
Unit = 2 Unit
Volume = (PxLxT)xUnit
(0,12x0,06x0,84)x2 0.01 M3
f Sokong Tegak
Tinggi = 0.12 M
Lebar = 0.06 M
Panjang = 1.23 M
Unit = 2 Unit
Volume = (PxLxT)xUnit
(0,12x0,06x1,23)x2 0.02 M3
b Kaki Kuda-Kuda
Tinggi = 0.12 M
Lebar = 0.06 M
= M
Panjang
=
3.38
Unit
IKATAN ANGN 4/12
Unit 1
Volume = (PxLxT)xUnit ATAP GENTENG METAL
(0,12x0,06x4,38)x1 0.02 M3
GAPIT 2x4/12
SKORD MIRING 6/12
c Balok Gapit
Tinggi = 0.12 M SKORD TEGAK 6/12
Lebar = 0.04 M
2.19
Panjang = 2 M BALOK TARIK 2x5/12
Unit = 2 Unit
Volume = (PxLxT)xUnit
(0,12x0,04x2)x2 0.02 M3
GORDING 5/10
d Sokong Miring
Tinggi = 0.12 M
Lebar = 0.06 M
Panjang = 1.41 M
Unit = 1 Unit
Volume = (PxLxT)xUnit
(0,12x0,06x1,41)x1 0.01 M3
e Sokong Tegak
Tinggi = 0.12 M
Lebar = 0.06 M
Panjang = 0.9 M
Unit = 1 Unit
Volume = (PxLxT)xUnit
(0,12x0,06x0,90)x1 0.01 M3
2.19
Panjang = 2.19 M BALOK TARIK 2x5/12
Unit = 2 Unit
Volume = (PxLxT)xUnit GORDING 5/10
(0,10x0,05x2,19)x2 0.02 M3
NOK 5/10
NOK 5/10
TIANG KUDA-KUDA 6/12
b Tinggi = 0.12 M
KAKI KUDA-KUDA 6/12
Lebar = 0.04 M IKATAN ANGN 4/12
KASAU 5/7
Panjang = 1.87 M TIANG KUDA-KUDA 6/12
GORDING 5/10
Unit = 2 Unit KAKI KUDA-KUDA 6/12
Volume = (PxLxT)xUnit
(0,10x0,05x1,87)x1 0.02 M3 Pas. Bata 1:4
1.80
c Tinggi = 0.12 M
Pas. Bata 1:4 Pas. Bata
Lebar = 0.04 M
Panjang = 1.89 M
Unit = 6 Unit
Volume = (PxLxT)xUnit 3.50
(0,10x0,05x1,89)x6 0.05 M3
+4.05 + 4.10
Volume Total = a+b+c 0.09
M3
a Tinggi = 0.1 M
Lebar = 0.05 M
Panjang = 10.88 M
Unit = 1 Unit
Volume = (PxLxT)xUnit
(0,10x0,05x10,88)x1 0.05 M3
b Tinggi = 0.1 M
Lebar = 0.05 M
Panjang = 9.88 M
Unit = 1 Unit
Volume = (PxLxT)xUnit
(0,10x0,05x9,88)x1 0.05 M3
c Tinggi = 0.1 M
Lebar = 0.05 M
Panjang = 8.88 M
Unit = 1 Unit
Volume = (PxLxT)xUnit
(0,10x0,05x8,88)x2 0.04 M3
d Tinggi = 0.1 M
Lebar = 0.05 M
Panjang = 8.31 M
Unit = 1 Unit
Volume = (PxLxT)xUnit
(0,10x0,05x8,31)x1 0.04 M3
e Tinggi = 0.1 M
Lebar = 0.05 M
Panjang = 5.01 M
Unit = 1 Unit
Volume = (PxLxT)xUnit
(0,10x0,05x5,01)x1 0.03 M3
f Tinggi = 0.1 M
Lebar = 0.05 M
Panjang = 4.44 M
Unit = 1 Unit
Volume = (PxLxT)xUnit
(0,10x0,05x4,44)x1 0.02 M3
g Tinggi = 0.1 M
Lebar = 0.05 M
Panjang = 3.44 M
Unit = 1 Unit
Volume = (PxLxT)xUnit
(0,10x0,05x3,44)x1 0.02 M3
h Tinggi = 0.1 M
Lebar = 0.05 M
Panjang = 2.44 M
Unit = 1 Unit
Volume = (PxLxT)xUnit
(0,10x0,05x2,44)x1 0.01 M3
i Tinggi = 0.1 M
Lebar = 0.05 M
Panjang = 4.32 M
Unit =3 Unit
Volume = (PxLxT)xUnit
(0,10x0,05x4,32)x3 0.06 M3
j Tinggi = 0.1 M
Lebar = 0.05 M
Panjang = 3.76 M
Unit = 1 Unit
Volume = (PxLxT)xUnit
(0,10x0,05x3,76)x1 0.02 M3
k Tinggi = 0.1 M
Lebar = 0.05 M
Panjang = 1.76 M
Unit = 2 Unit
Volume = (PxLxT)xUnit
(0,10x0,05x1,76)x2 0.02 M3
l Tinggi = 0.1 M
Lebar = 0.05 M
Panjang = 1.32 M
Unit = 4 Unit
Volume = (PxLxT)xUnit
(0,10x0,05x1,32)x4 0.03 M3
m Tinggi = 0.1 M
Lebar = 0.05 M
Panjang = 0.26 M
Unit = 2 Unit
Volume = (PxLxT)xUnit
(0,10x0,05x0,26)x2 0.003 M3
n Tinggi = 0.1 M
Lebar = 0.05 M
Panjang = 1.83 M
Unit = 5 Unit
Volume = (PxLxT)xUnit
(0,10x0,05x1,83)x5 0.05 M3
o Tinggi = 0.1 M
Lebar = 0.05 M
Panjang = 6.76 M
Unit = 1 Unit
Volume = (PxLxT)xUnit
(0,10x0,05x6,76)x1 0.03 M3
p Tinggi = 0.1 M
Lebar = 0.05 M
Panjang = 4.76 M
Unit = 1 Unit
Volume = (PxLxT)xUnit
(0,10x0,05x4,76)x1 0.02 M3
q Tinggi = 0.1 M
Lebar = 0.05 M
Panjang = 2.76 M
Unit = 1 Unit
Volume = (PxLxT)xUnit
(0,10x0,05x2,76)x1 0.014 M3
r Tinggi = 0.1 M
Lebar = 0.05 M
Panjang = 0.76 M
Unit = 1 Unit
Volume = (PxLxT)xUnit
(0,10x0,05x0,76)x1 0.004 M3
s Tinggi = 0.1 M
Lebar = 0.05 M
Panjang = 11.76 M
Unit = 1 Unit
Volume = (PxLxT)xUnit
(0,10x0,05x11,76)x1 0.059 M3
t Tinggi = 0.1 M
Lebar = 0.05 M
Panjang = 9.76 M
Unit = 1 Unit
Volume = (PxLxT)xUnit
(0,10x0,05x9,76)x1 0.05 M3
u Tinggi = 0.1 M
Lebar = 0.05 M
Panjang = 7.76 M
Unit = 1 Unit
Volume = (PxLxT)xUnit
(0,10x0,05x7,76)x1 0.039 M3
v Tinggi = 0.1 M
Lebar = 0.05 M
Panjang = 5.76 M
Unit = 1 Unit
Volume = (PxLxT)xUnit
(0,10x0,05x5,76)x1 0.03 M3
w Tinggi = 0.1 M
Lebar = 0.05 M
Panjang = 2.18 M
Unit = 1 Unit
Volume = (PxLxT)xUnit
(0,10x0,05x2,18)x1 0.011 M3
2 Tinggi = 0.07 M
Lebar = 0.05 M
Panjang = 2.97 M
Unit = 3 Unit
Volume = (PxLxT)xUnit
(0,07x0,05x2,97)x3 0.03 M3
3 Tinggi = 0.07 M
Lebar = 0.05 M
Panjang = 3.47 M
Unit = 2 Unit
Volume = (PxLxT)xUnit
(0,07x0,05x3,47)x2 0.02 M3
4 Tinggi = 0.07 M
Lebar = 0.05 M
Panjang = 3.97 M
Unit = 2 Unit
Volume = (PxLxT)xUnit
(0,07x0,05x3,97)x2 0.03 M3
5 Tinggi = 0.07 M
Lebar = 0.05 M
Panjang = 3.89 M
Unit = 3 Unit
Volume = (PxLxT)xUnit
(0,07x0,05x3,89)x3 0.04 M3
6 Tinggi = 0.07 M
Lebar = 0.05 M
Panjang = 3.39 M
Unit = 4 Unit
Volume = (PxLxT)xUnit
(0,07x0,05x3,39)x4 0.05 M3
7 Tinggi = 0.07 M
Lebar = 0.05 M
Panjang = 2.89 M
Unit = 4 Unit
Volume = (PxLxT)xUnit
(0,07x0,05x2,89)x4 0.04 M3
8 Tinggi = 0.07 M
Lebar = 0.05 M
Panjang = 2.39 M
Unit = 4 Unit
Volume = (PxLxT)xUnit
(0,07x0,05x2,39)x4 0.03 M3
9 Tinggi = 0.07 M
Lebar = 0.05 M
Panjang = 1.89 M
Unit = 4 Unit
Volume = (PxLxT)xUnit
(0,07x0,05x1,89)x4 0.03 M3
10 Tinggi = 0.07 M
Lebar = 0.05 M
Panjang = 1.39 M
Unit = 4 Unit
Volume = (PxLxT)xUnit
(0,07x0,05x1,39)x4 0.02 M3
11 Tinggi = 0.07 M
Lebar = 0.05 M
Panjang = 0.89 M
Unit = 4 Unit
Volume = (PxLxT)xUnit
(0,07x0,05x0,89)x4 0.01 M3
12 Tinggi = 0.07 M
Lebar = 0.05 M
Panjang = 0.39 M
Unit = 4 Unit
Volume = (PxLxT)xUnit
(0,07x0,05x0,39)x16 0.01 M3
13 Tinggi = 0.07 M
Lebar = 0.05 M
Panjang = 4.2 M
Unit = 3 Unit
Volume = (PxLxT)xUnit
(0,07x0,05x4,2)x3 0.044 M3
14 Tinggi = 0.07 M
Lebar = 0.05 M
Panjang = 3.45 M
Unit = 4 Unit
Volume = (PxLxT)xUnit
(0,07x0,05x3,45)x4 0.048 M3
15 Tinggi = 0.07 M
Lebar = 0.05 M
Panjang = 2.47 M
Unit = 2 Unit
Volume = (PxLxT)xUnit
(0,07x0,05x2,47)x2 0.017 M3
16 Tinggi = 0.07 M
Lebar = 0.05 M
Panjang = 1.97 M
Unit = 2 Unit
Volume = (PxLxT)xUnit
(0,07x0,05x1,97)x2 0.014 M3
17 Tinggi = 0.07 M
Lebar = 0.05 M
Panjang = 1.47 M
Unit = 3 Unit
Volume = (PxLxT)xUnit
(0,07x0,05x1,47)x3 0.015 M3
18 Tinggi = 0.07 M
Lebar = 0.05 M
Panjang = 0.97 M
Unit = 4 Unit
Volume = (PxLxT)xUnit
(0,07x0,05x0,97)x4 0.014 M3
19 Tinggi = 0.07 M
Lebar = 0.05 M
Panjang = 1.83 M
Unit = 3 Unit
Volume = (PxLxT)xUnit
(0,07x0,05x1,83)x3 0.019 M3
20 Tinggi = 0.07 M
Lebar = 0.05 M
Panjang = 1.81 M
Unit = 1 Unit
Volume = (PxLxT)xUnit
(0,07x0,05x1,81)x1 0.01 M3
21 Tinggi = 0.07 M
Lebar = 0.05 M
Panjang = 1.31 M
Unit = 1 Unit
Volume = (PxLxT)xUnit
(0,07x0,05x1,31)x1 0.005 M3
22 Tinggi = 0.07 M
Lebar = 0.05 M
Panjang = 0.81 M
Unit = 1 Unit
Volume = (PxLxT)xUnit
(0,07x0,05x0,81)x1 0.003 M3
23 Tinggi = 0.07 M
Lebar = 0.05 M
Panjang = 0.31 M
Unit = 1 Unit
Volume = (PxLxT)xUnit
(0,07x0,05x0,31)x1 0.001 M3
25 Tinggi = 0.07 M
Lebar = 0.05 M
Panjang = 4.05 M
Unit = 1 Unit
Volume = (PxLxT)xUnit
(0,07x0,05x4,05)x1 0.014 M3
26 Tinggi = 0.07 M
Lebar = 0.05 M
Panjang = 3.55 M
Unit = 1 Unit
Volume = (PxLxT)xUnit
(0,07x0,05x3,55)x1 0.012 M3
27 Tinggi = 0.07 M
Lebar = 0.05 M
Panjang = 3.05 M
Unit = 1 Unit
Volume = (PxLxT)xUnit
(0,07x0,05x3,05)x1 0.011 M3
28 Tinggi = 0.07 M
Lebar = 0.05 M
Panjang = 2.24 M
Unit = 1 Unit
Volume = (PxLxT)xUnit
(0,07x0,05x2,24)x1 0.008 M3
29 Tinggi = 0.07 M
Lebar = 0.05 M
Panjang = 1.24 M
Unit = 1 Unit
Volume = (PxLxT)xUnit
(0,07x0,05x1,24)x1 0.004 M3
30 Tinggi = 0.07 M
Lebar = 0.05 M
Panjang = 0.24 M
Unit = 1 Unit
Volume = (PxLxT)xUnit
(0,07x0,05x0,24)x1 0.001 M3
31 Tinggi = 0.07 M
Lebar = 0.05 M
Panjang = 0.05 M
Unit = 1 Unit
Volume = (PxLxT)xUnit
(0,07x0,05x0,05)x1 0.00 M3
32 Tinggi = 0.07 M
Lebar = 0.05 M
Panjang = 0.55 M
Unit = 1 Unit
Volume = (PxLxT)xUnit
(0,07x0,05x0,55)x1 0.002 M3
33 Tinggi = 0.07 M
Lebar = 0.05 M
Panjang = 1.05 M
Unit = 1 Unit
Volume = (PxLxT)xUnit
(0,07x0,05x1,05)x1 0.004 M3
34 Tinggi = 0.07 M
Lebar = 0.05 M
Panjang = 2.24 M
Unit = 1 Unit
Volume = (PxLxT)xUnit
(0,07x0,05x2,24)x1 0.008 M3
35 Tinggi = 0.07 M
Lebar = 0.05 M
Panjang = 1.55 M
Unit = 1 Unit
Volume = (PxLxT)xUnit
(0,07x0,05x1,55)x1 0.005 M3
36 Tinggi = 0.07 M
Lebar = 0.05 M
Panjang = 2.05 M
Unit = 1 Unit
Volume = (PxLxT)xUnit
(0,07x0,05x2,05)x1 0.007 M3
37 Tinggi = 0.07 M
Lebar = 0.05 M
Panjang = 2.55 M
Unit = 1 Unit
Volume = (PxLxT)xUnit
(0,07x0,05x2,55)x1 0.009 M3
1 Lebar = 4.6 M
Panjang =7 M
Volume = (PxL)
(7x4,6) 32.20 M2
2 Lebar = 4.46 M
Panjang =2 M
Volume = (PxL)
(2x4,46) 8.92 M2
3 Lebar = 5.3 M
Panjang = 1.5 M
Volume = (PxL)
(1,5x5,3) 7.95 M2
4 Lebar = 5.3 M
Panjang = 4.5 M
Volume = (PxL)
(4,5x5,3) 23.85 M2
5 Lebar = 3.57 M
Panjang = 2.5 M
Volume = (PxL)
(2,5x3,57) 8.93 M2
6 Lebar = 3.57 M
Panjang = 5.27 M
Volume = (PxL)
(5,27x3,57) 18.81 M2
7 Lebar = 3.57 M
Panjang = 5.73 M
Volume = (PxL)
(5,73x3,57) 20.46 M2
8 Lebar = 5.3 M
Panjang = 6.48 M
Volume = (PxL)
(6,48x5,3) 34.34 M2
9 Lebar = 4.6 M
Panjang = 5.52 M
Volume = (PxL)
(5,52x4,6) 25.39 M2
D Rabung
E Jurai Luar
F Jurai Dalam
Panjang = 40.5 M
Jumlah =2 Unit
Total = (P x Unit) 81
M
(40,5 x 2)
RENCANA ANGGARAN BIAYA
Pekerjaan Lantai 1
1 2 3 4 5 6 7=3x6
A PEKERJAAN PERSIAPAN
1 Pembersihan Lapangan 418.00 m2 AHSP PU A.2.2.1.9 Rp 25,850.00 Rp 10,805,300.00
2 Pengukuran / Pemasangan Bouplank 74.00 m1 AHSP PU A.2.2.1.4 Rp 118,261.00 Rp 8,751,314.00
3 Administrasi dan Dokumentasi 1.00 Ls Taksir Rp 1,000,000.00 Rp 1,000,000.00
4 K3 dan Lain-lain 1.00 Ls Taksir Rp 1,500,000.00 Rp 1,500,000.00
5 Papan Nama Proyek 1.00 Ls Taksir Rp 500,000.00 Rp 500,000.00
Sub Jumlah Rp 22,556,614.00
B PEKERJAAN TANAH DAN PONDASI
1 Galian Tanah Pondasi Tapak 32.40 m3 AHSP PU A.2.3.1.8a Rp 96,626.20 Rp 3,130,688.88
Urugan Kembali Galian Pondasi Tapak 24.30 m3 AHSP PU A.2.3.1.9 Rp 56,827.10 Rp 1,380,898.53
Pas. Pasir Alas 1.35 m3 AHSP PU A.2.3.1.11 Rp 249,370.00 Rp 336,649.50
Beton Cor K-100 2.70 m3 AHSP PU A.4.1.1.1 Rp 997,879.09 Rp 2,694,273.55
2 Anak Tangga
Beton K-250 0.67 m3 AHSP PU A.4.1.1.8 Rp 1,178,603.83 Rp 792,021.78
Besi Tulangan Pokok ø 10 205.40 kg AHSP PU A.4.1.1.17.a Rp 32,595.75 Rp 6,695,167.05
Bekisting + Perawatan Beton 5.60 m2 AHSP PU A.4.1.1.26 Rp 594,863.50 Rp 3,331,235.60
4 Plat Bordes
Beton K-250 0.18 m3 AHSP PU A.4.1.1.8 Rp 1,178,603.83 Rp 216,759.39
Besi Tulangan Pokok ø 12 68.47 kg AHSP PU A.4.1.1.17.a Rp 32,595.75 Rp 2,231,722.35
Bekisting + Perawatan Beton 1.53 m2 AHSP PU A.4.1.1.26 Rp 594,863.50 Rp 911,687.80
5 Keramik
Pas. Keramik Anak Tangga + Bordes 9.02 m2 AHSP PU A.4.4.3.34.a Rp 314,776.00 Rp 2,838,933.27
Sub Jumlah Rp 30,836,451.15
G PEKERJAAN PINTU, JENDELA
1 Pas. Pintu P1
Kusen Pintu 0.06 m3 AHSP PU A.4.6.1.1 Rp 11,096,250.00 Rp 611,048.30
Daun Pintu 6.10 m2 AHSP PU A.4.6.1.5 Rp 997,700.00 Rp 6,084,373.68
Daun Ventilasi 0.19 m2 AHSP PU A.4.6.1.6 Rp 753,940.00 Rp 142,494.66
-Kaca 5mm 0.22 m2 AHSP PU A.4.6.2.17 Rp 178,789.60 Rp 178,789.60
- Hak Angin / Gagang Jendela 4.00 Buah AHSP PU A.4.6.2.9 Rp 52,537.10 Rp 210,148.40
- Engsel Jendela 4.00 Buah AHSP PU A.4.6.2.6 Rp 247,237.10 Rp 988,948.40
- Pacok Jendela 2.00 Buah AHSP PU A.4.6.2.10 Rp 40,987.10 Rp 81,974.20
Kunci Pintu (Standar) 2.00 Buah AHSP PU A.4.6.2.4 Rp 266,761.00 Rp 533,522.00
Engsel Pintu 4.00 Buah AHSP PU A.4.6.2.5 Rp 252,737.10 Rp 1,010,948.40
Pacok Pintu 2.00 Buah Taksir Rp 15,000.00 Rp 30,000.00
2 Pas. Pintu P3
Kusen Pintu 0.288 m3 AHSP PU A.4.6.1.1 Rp 11,096,250.00 Rp 3,198,915.72
Daun Pintu 10.38 m2 AHSP PU A.4.6.1.5 Rp 997,700.00 Rp 10,357,323.24
Papan Ventilasi/Jelusi 0.01 m3 AHSP PU A.4.6.1.10 Rp 940,665.00 Rp 5,926.19
Kunci Pintu (Standar) 6.00 Buah AHSP PU A.4.6.2.4 Rp 266,761.00 Rp 1,600,566.00
Engsel Pintu 12.00 Buah AHSP PU A.4.6.2.5 Rp 252,737.10 Rp 3,032,845.20
3 Pas. Pintu P4
Kusen Pintu 0.204 m3 AHSP PU A.4.6.1.1 Rp 11,096,250.00 Rp 2,267,629.65
Ambang Daun Pintu 3.05 m2 AHSP PU A.4.6.1.5 Rp 997,700.00 Rp 3,045,778.56
-Kaca 5mm 6.97 m2 AHSP PU A.4.6.2.17 Rp 178,789.60 Rp 1,246,521.09
Kunci Pintu (Standar) 8.00 Buah AHSP PU A.4.6.2.4 Rp 266,761.00 Rp 2,134,088.00
Engsel Pintu 16.00 Buah AHSP PU A.4.6.2.5 Rp 252,737.10 Rp 4,043,793.60
Pacok Pintu 4.00 Buah Taksir Rp 15,000.00 Rp 60,000.00
4 Pas. Pintu P5
Kusen Pintu 0.120 m3 AHSP PU A.4.6.1.1 Rp 11,096,250.00 Rp 1,329,419.52
Daun Pintu 4.54 m2 AHSP PU A.4.6.1.6 Rp 753,940.00 Rp 3,419,871.84
Pacok Pintu 3.00 Buah Taksir Rp 15,000.00 Rp 45,000.00
Engsel Pintu 6.00 Buah AHSP PU A.4.6.2.5 Rp 252,737.10 Rp 1,516,422.60
7 Jendela J3
Kusen Jendela 0.048 m3 AHSP PU A.4.6.1.1 Rp 11,096,250.00 Rp 529,690.59
Daun Jendela 0.58 m2 AHSP PU A.4.6.1.6 Rp 753,940.00 Rp 439,094.66
- Kaca 5 mm 0.83 m2 AHSP PU A.6.2.17 Rp 178,789.60 Rp 148,037.79
- Hak Angin / Gagang Jendela 4.00 Buah AHSP PU A.4.6.2.9 Rp 52,537.10 Rp 210,148.40
- Engsel Jendela 4.00 Buah AHSP PU A.4.6.2.6 Rp 247,237.10 Rp 988,948.40
- Pacok Jendela 2.00 Buah AHSP PU A.4.6.2.10 Rp 40,987.10 Rp 81,974.20
8 Jendela J4
Kusen Jendela 0.113 m3 AHSP PU A.4.6.1.1 Rp 11,096,250.00 Rp 1,253,254.86
Daun Jendela 1.77 m2 AHSP PU A.4.6.1.6 Rp 753,940.00 Rp 1,331,759.62
- Kaca 5 mm 3.78 m2 AHSP PU A.6.2.17 Rp 178,789.60 Rp 675,824.69
- Hak Angin / Gagang Jendela 12.00 Buah AHSP PU A.4.6.2.9 Rp 52,537.10 Rp 630,445.20
- Engsel Jendela 12.00 Buah AHSP PU A.4.6.2.6 Rp 247,237.10 Rp 2,966,845.20
- Pacok Jendela 6.00 Buah AHSP PU A.4.6.2.10 Rp 40,987.10 Rp 245,922.60
9 Ventilasi V1
Kusen Ventilasi 0.014 m3 AHSP PU A.4.6.1.1 Rp 11,096,250.00 Rp 159,253.38
- Kaca 5 mm 0.10 m2 AHSP PU A.6.2.17 Rp 178,789.60 Rp 18,594.12
10 Ventilasi V2
Kusen Ventilasi 0.023 m3 AHSP PU A.4.6.2.6 Rp 247,237.10 Rp 5,708.21
- Kaca 5 mm 0.21 m2 AHSP PU A.6.2.17 Rp 178,789.60 Rp 37,188.24
E PEKERJAAN ATAP
1 Rangka kuda-kuda Kayu K1
-KD-4 0.51 M3 AHSP PU A.4.6.1.14 Rp 13,234,100.00 Rp 6,761,672.24
- KD-41/2 0.25 M3 AHSP PU A.4.6.1.14 Rp 13,234,100.00 Rp 3,308,313.25
2 Gording Kayu Kelas II 0.32 M3 AHSP PU A.4.6.1.15 Rp 11,053,240.00 Rp 3,492,823.84
3 Atap Seng 109.17 M2 AHSP PU A.4.5.2.39.a Rp 90,194.50 Rp 9,846,082.59
4 Kasau Kelas II 0.50 M3 AHSP PU A.4.6.1.15 Rp 11,053,240.00 Rp 5,502,358.14
5 Rabung Seng 2.82 M1 AHSP PU A.4.5.2.39.a Rp 90,194.50 Rp 254,348.49
6 Jurai Seng 17.91 M1 AHSP PU A.4.5.2.39.a Rp 90,194.50 Rp 1,615,383.50
7 Papan Listplank Uk. 2,5/25 cm 44.00 M1 AHSP PU A.4.6.1.21 Rp 116,589.00 Rp 5,129,916.00
8 Ikatan Angin 0.02 M3 AHSP PU A.4.6.1.15 Rp 11,053,240.00 Rp 218,588.87
Sub Jumlah Rp 36,129,486.93
Pekerjaan Lantai 2
A PEKERJAAN BETON BERTULANG
1 Beton Bertulang Kolom KI- 20/20
Beton K-250 1.63 M3 AHSP PU A.4.1.1.8 Rp 1,178,603.83 Rp 1,925,838.66
Besi Tulangan Pokok ø 12 133.16 Kg AHSP PU A.4.1.1.17.a Rp 32,595.75 Rp 4,340,580.45
Besi Tulangan Sengkang ø 6 - 15 cm 0.29 Kg AHSP PU A.4.1.1.17 Rp 23,355.75 Rp 6,738.65
Bekisting + Perawatan Beton 10.00 M2 AHSP PU A.4.1.1.22 Rp 638,038.50 Rp 6,380,385.00
2 Pek. Keramik
Pas. Keramik Lantai 40/40 94.76 m2 AHSP PU A.4.4.3.34.a Rp 314,776.00 Rp 29,829,590.25
Pas. Keramik Lantai 30/30 7.68 m2 AHSP PU A.4.4.3.35 Rp 310,165.90 Rp 2,381,701.91
2 Pas. Pintu PJ
Kusen PJ 0.068 m3 AHSP PU A.4.6.1.1 Rp 11,096,250.00 Rp 758,184.57
Daun Pintu 1.89 m2 AHSP PU A.4.6.1.5 Rp 997,700.00 Rp 1,888,047.48
Kunci Pintu (Standar) 1.00 Buah AHSP PU A.4.6.2.4 Rp 266,761.00 Rp 266,761.00
Engsel Pintu 2.00 Buah AHSP PU A.4.6.2.5 Rp 10,500.00 Rp 21,000.00
Daun Jendela 1.89 m2 AHSP PU A.4.6.1.6 Rp 940,665.00 Rp 1,780,490.71
- Kaca 5 mm 1.12 m2 AHSP PU A.6.2.17 Rp 178,789.60 Rp 199,386.16
- Hak Angin / Gagang Jendela 4.00 Buah AHSP PU A.4.6.2.9 Rp 52,537.10 Rp 210,148.40
- Engsel Jendela 4.00 Buah AHSP PU A.4.6.2.6 Rp 247,237.10 Rp 988,948.40
- Pacok Jendela 2.00 Buah AHSP PU A.4.6.2.10 Rp 40,987.10 Rp 81,974.20
3 Pas. Pintu P3
Kusen Pintu 0.110 m3 AHSP PU A.4.6.1.1 Rp 11,096,250.00 Rp 1,225,558.62
Daun Pintu 3.46 m2 AHSP PU A.4.6.1.5 Rp 997,700.00 Rp 3,452,441.08
Papan Ventilasi/Jelusi 0.01 m3 AHSP PU A.4.6.1.10 Rp 940,665.00 Rp 11,852.38
Kunci Pintu (Standar) 2.00 Buah AHSP PU A.4.6.2.4 Rp 266,761.00 Rp 533,522.00
Engsel Pintu 4.00 Buah AHSP PU A.4.6.2.5 Rp 252,737.10 Rp 1,010,948.40
Pacok Pintu 4.00 Buah Taksir Rp 15,000.00 Rp 60,000.00
4 Pas. Pintu P5
Kusen Pintu 0.092 m3 AHSP PU A.4.6.1.1 Rp 11,096,250.00 Rp 1,024,760.88
Daun Pintu 2.95 m2 AHSP PU A.4.6.1.5 Rp 997,700.00 Rp 2,947,205.80
Pacok Pintu 2.00 Buah Taksir Rp 15,000.00 Rp 30,000.00
Engsel Pintu 4.00 Buah AHSP PU A.4.6.2.5 Rp 252,737.10 Rp 1,010,948.40
6 Jendela J2
Kusen Jendela 0.238 m3 AHSP PU A.4.6.1.1 Rp 11,096,250.00 Rp 2,638,066.86
Daun Jendela 2.25 m2 AHSP PU A.4.6.1.6 Rp 940,665.00 Rp 2,113,109.86
- Kaca 5 mm 3.54 m2 AHSP PU A.6.2.17 Rp 178,789.60 Rp 633,344.28
- Hak Angin / Gagang Jendela 12.00 Buah AHSP PU A.4.6.2.9 Rp 52,537.10 Rp 630,445.20
- Engsel Jendela 12.00 Buah AHSP PU A.4.6.2.6 Rp 247,237.10 Rp 2,966,845.20
- Pacok Jendela 6.00 Buah AHSP PU A.4.6.2.10 Rp 40,987.10 Rp 245,922.60
7 Jendela J3
Kusen Jendela 0.039 m3 AHSP PU A.4.6.1.1 Rp 11,096,250.00 Rp 429,291.72
Daun Jendela 0.59 m2 AHSP PU A.4.6.1.6 Rp 940,665.00 Rp 553,863.55
- Kaca 5 mm 0.83 m2 AHSP PU A.6.2.17 Rp 178,789.60 Rp 148,037.79
- Hak Angin / Gagang Jendela 4.00 Buah AHSP PU A.4.6.2.9 Rp 52,537.10 Rp 210,148.40
- Engsel Jendela 4.00 Buah AHSP PU A.4.6.2.6 Rp 247,237.10 Rp 988,948.40
- Pacok Jendela 2.00 Buah AHSP PU A.4.6.2.10 Rp 40,987.10 Rp 81,974.20
9 Ventilasi V1
Kusen Ventilasi 0.014 m3 AHSP PU A.4.6.1.1 Rp 11,096,250.00 Rp 159,253.38
- Kaca 5 mm 0.10 m2 AHSP PU A.6.2.17 Rp 178,789.60 Rp 18,594.12
10 Ventilasi V2
Kusen Ventilasi 0.023 m3 AHSP PU A.4.6.2.6 Rp 247,237.10 Rp 5,708.21
- Kaca 5 mm 0.21 m2 AHSP PU A.6.2.17 Rp 178,789.60 Rp 37,188.24
Sub Jumlah Rp 34,322,438.43
E PEKERJAAN INSTALASI LISTRIK
1 Lampu Saving Energi 20 Watt 6 Bh Taksir Rp 45,000.00 Rp 270,000.000
2 Lampu Saving Energi 18 Watt 2 Bh Taksir Rp 40,000.00 Rp 80,000.000
3 Lampu Saving Energi 11 Watt 2 Bh Taksir Rp 35,000.00 Rp 70,000.000
4 Saklar Tunggal 4 Bh Taksir Rp 10,000.00 Rp 40,000.000
5 Saklar Ganda 3 Bh Taksir Rp 15,000.00 Rp 45,000.000
Sub Jumlah Rp 505,000.000
F PEKERJAAN PLAFOND
1 Rangka Plafond Kayu Klas II 113.26 m2 AHSP PU A.4.6.1.20 Rp 105,872.25 Rp 11,990,826.35
2 Plafon Triplek 6 mm 113.26 m2 AHSP PU A.4.5.1.5 Rp 57,668.88 Rp 6,531,432.61
3 Kayu List Plafond 73.00 m1 AHSP PU A.4.5.1.9 Rp 54,004.50 Rp 3,942,328.50
Sub Jumlah Rp 22,464,587.465
G PEKERJAAN PENGECATAN
1 Cat Dinding Luar Dan Dalam 359.4 m2 AHSP PU A.4.7.1.10 Rp 38,414.75 Rp 13,808,120.42
2 Cat Plafond 113.26 m2 AHSP PU A.4.7.1.4 Rp 54,004.50 Rp 6,116,414.66
3 Cat Kusen 25.80 m2 AHSP PU A.4.7.1.4 Rp 54,004.50 Rp 1,393,505.12
Sub Jumlah Rp 21,318,040.20
H PEKERJAAN ATAP
1 Rangka kuda-kuda Kayu K1
-KD-1 0.70 M3 AHSP PU A.4.6.1.14 Rp 13,234,100.00 Rp 9,317,335.76
- KD-21/2 0.15 M3 AHSP PU A.4.6.1.14 Rp 13,234,100.00 Rp 1,938,319.22
-KD-2 0.74 M3 AHSP PU A.4.6.1.14 Rp 13,234,100.00 Rp 9,773,224.04
- KD-31/3 0.10 M3 AHSP PU A.4.6.1.14 Rp 13,234,100.00 Rp 1,261,580.28
-KD-3 0.41 M3 AHSP PU A.4.6.1.14 Rp 13,234,100.00 Rp 5,403,324.22
2 Gording Kayu Kelas II 0.70 M3 AHSP PU A.4.6.1.15 Rp 11,053,240.00 Rp 7,777,612.33
3 Atap Seng 157.00 M2 AHSP PU A.4.5.2.39.a Rp 90,194.50 Rp 14,160,626.69
4 Kasau Kelas II 0.73 M3 AHSP PU A.4.6.1.15 Rp 11,053,240.00 Rp 8,096,664.10
5 Rabung Seng 8.51 M1 AHSP PU A.4.5.2.39.a Rp 90,194.50 Rp 767,555.20
6 Jurai Seng 33.76 M1 AHSP PU A.4.5.2.39.a Rp 90,194.50 Rp 3,044,966.32
7 Papan Listplank Uk. 2,5/25 cm 81.00 M1 AHSP PU A.4.6.1.21 Rp 116,589.00 Rp 9,443,709.00
8 Ikatan Angin 0.09 M3 AHSP PU A.4.6.1.15 Rp 11,053,240.00 Rp 1,032,461.04
Sub Jumlah Rp 72,017,378.21
Sub Total Rp 1,357,154,875
PERHITUNGAN BESI DAN BEKISTING
1 2 3
40
Berat besi Ø 6, = Byk begel x Pjg begel x 0.006165 x dia.2
7Ø12 = 0.51 kg
Ø6-10 = 8.000 m2
1 2 3
20
= 1.67 ± ------->
2 btg
20
= 0.29 kg
8Ø12
1 2 3
13
= 32.44 kg
4Ø12
4. Papan mal = Pjg balok untuk 1 m3 beton xL.permukaan papan
= 30.77 m2
1 2 3
Balok RB 20/30
PERHITUNGAN Panjang balok untuk 1 m3
4 ( 0.20 x 0.30 ) M = 1/( b x h)
= 16.67 m'
Jumlah Tul. Pokok = 5.00 Batang a. Pembesian untuk 1 m3 beton adalah
Ø Tul. Pokok = 12.00 mm 1. Tul pokok = Pjg balok x byk tul x 0.006165 x dia.2
Jumlah Tul. Pinggang = 2.00 Batang Berat besi Ø 12, = 73.98 kg
Ø Tul. Pinggang = 12.00 mm
Ø Tul. Begel = 6.00 mm 2. Tul pinggang = Pjg balok x byk tul x 0.006165 x dia.2
Jarak Begel = 0.100 M Berat besi Ø 12, = 29.59 kg
Luas Permukaan Papan = 0.56 M2
3. Tulangan Begel Besi Ø 6,
Panjang begel = 0.850 m'
Banyak begel = Pjg balok untuk 1 m3 beton/jarak begel
= 166.67 ± ------->
167 btg
30 7Ø12
4. Papan mal
=
=
31.5044 kg
1 2 3
Balok RB 15/20
PERHITUNGAN Panjang balok untuk 1 m3
5 ( 0.15 x 0.20 ) M = 1/( b x h)
= 33.33 m'
Jumlah Tul. Pokok = 4.00 Batang a. Pembesian untuk 1 m3 beton adalah
Ø Tul. Pokok = 12.00 mm 1. Tul pokok = Pjg balok x byk tul x 0.006165 x dia.2
Jumlah Tul. Pinggang = 2.00 Batang Berat besi Ø 12, = 118.37 kg
Ø Tul. Pinggang = 12.00 mm
Ø Tul. Begel = 6.00 mm 2. Tul pinggang = Pjg balok x byk tul x 0.006165 x dia.2
Jarak Begel = 0.100 M Berat besi Ø 12, = 59.18 kg
Luas Permukaan Papan = 0.31 M2
3. Tulangan Begel Besi Ø 6,
Panjang begel = 0.550 m'
Banyak begel = Pjg balok untuk 1 m3 beton/jarak begel
Ø6-10 = 333.33 ± ------->
20
334 btg
7Ø12
1 2 3
Balok Bordes 20/30
PERHITUNGAN Panjang balok untuk 1 m3
6 ( 0.20 x 0.30 ) M = 1/( b x h)
= 16.67 m'
Jumlah Tul. Pokok = 6.00 Batang a. Pembesian untuk 1 m3 beton adalah
Ø Tul. Pokok = 16.00 mm 1. Tul pokok = Pjg balok x byk tul x 0.006165 x dia.2
Berat besi Ø 16, = 157.82 kg
= 37.5621 kg
1 2 3
1 2 3
1 2 3
PERHITUNGAN 1. Untuk Bidang 1.30 Meter
9 Anak Tangga = 12 cm Panjang Besi (Pjb) = 0.30 M
Jumlah Baris Besi (Jb) = 2.00 M
Bidang X = 0.20 M Jumlah Lapis (Jl) = 2.00 Lapis
Bidang Y = 0.30 M Diameter Besi (d) = 10.00 mm
Tebal Pengecoran = 0.12 M
Diameter Besi = 10.00 mm Berat Besi = Pjg*Jb*Jl*0.006162*d*d
Jarak Tulangan = 0.10 M = 0.739 Kg
1 2 3
1 2 3
38 80
13
Berat Besi Untuk 1 m3 Beton = 53.24 Kg / M3 Beton
80
Luas Bekisting Untuk 1 m3 Beton = 4.000 M2 / M3 Beton
1 2 3
PERHITUNGAN
12 Pedestal Pondasi tapak Panjang balok untuk 1 m3
( 0.13 x 0.38 ) M = 1/( b x h)
= 20.24 m'
Jumlah Tul. Pokok = 4.00 Batang a. Pembesian untuk 1 m3 beton adalah
Ø Tul. Pokok = 12.00 mm 1. Tul pokok = Pjg balok x byk tul x 0.006165 x dia.2
Jumlah Tul. Pinggang = 2.00 Batang Berat besi Ø 12, = 71.88 kg
Ø Tul. Pinggang = 12.00 mm
Ø Tul. Begel = 6.00 mm 2. Tul pinggang = Pjg balok x byk tul x 0.006165 x dia.2
Jarak Begel = 0.15 M Berat besi Ø 12, = 35.94 kg
Luas Permukaan Papan = 1.02 M2
3. Tulangan Begel Besi Ø 6,
Panjang begel = 0.870 m'
Banyak begel = Pjg balok untuk 1 m3 beton/jarak begel
2 Ø 12 = 134.95 ± ------->
Ø6 - 15 135 btg
2 Ø 12 2 Ø 12 2 Ø 12
2 Ø 12
Berat besi Ø 6, = Byk begel x Pjg begel x 0.006165 x dia.2
Ø6 - 15 = 26.0669 kg
2 Ø 12
13 38
2 Ø 12
Ø6 - 15
2 Ø 12 2 Ø 12 2 Ø 12
2 Ø 12
Ø6 - 15
LANTAI I
1 PEKERJAAN PERSIAPAN Rp 22,556,614
2 PEKERJAAN TANAH DAN PONDASI Rp 131,417,305
3 PEKERJAAN PASANGAN DAN PLASTERAN Rp 372,394,715
4 PEKERJAAN BETON BERTULANG Rp 146,566,245
5 PEKERJAAN LANTAI Rp 83,765,560
6 PEKERJAAN TANGGA Rp 30,836,451
7 PEKERJAAN PINTU, JENDELA Rp 79,191,320
8 PEKERJAAN INSTALASI LISTRIK Rp 905,000
9 PEKERJAAN PLAFOND Rp 31,667,389
10 PEKERJAAN PENGECATAN Rp 55,162,879
11 PEKERJAAN ATAP Rp 36,129,487
LANTAI II
1 PEKERJAAN BETON BERTULANG Rp 58,511,151
2 PEKERJAAN PASANGAN DAN PLASTERAN Rp 99,993,321
3 PEKERJAAN LANTAI Rp 57,429,993
4 PEKERJAAN PINTU, JENDELA DAN KUNCI Rp 34,322,438
5 PEKERJAAN INSTALASI LISTRIK Rp 505,000
6 PEKERJAAN PLAFOND Rp 22,464,587
7 PEKERJAAN PENGECATAN Rp 21,318,040
8 PEKERJAAN ATAP Rp 72,017,378