LAPORAN 

MINGGUAN
PROYEK RELOKASI DPPU SUPADIO ‐ PONTIANAK
PERIODE : MINGGU KE ‐ 75 (26 Juli ‐ 01 Aug 2017) TANGGAL : Wednesday, August 2, 2017

DATA PROYEK RINGKASAN KEMAJUAN PEKERJAAN MANAJEMEN KONSTRUKSI AKTIVITAS PEKERJAAN UTAMA STATUS / PERMASALAHAN


NAMA PROYEK RELOKASI DPPU SUPADIO WAKTU TERPAKAI 525 Hari AKTIVITAS MINGGU INI STATUS
LOKASI PROYEK AP2 SUPADIO ‐ PONTIANAK WAKTU TERPAKAI TERHADAP KONTRAK 100.00 % A. Engineering 1. Office Building : Pemasangan dinding bata ringan lantai 2, bagian luar dan dalam
NOMOR KONTRAK RENCANA PROGRESS KUMULATIF 100.0000 % Engineering Detail, Design & Survey 2. Electrical House : Pemasangan dinding bata ringan
TANGGAL KONTRAK AKTUAL PROGRESS KUMULATIF 40.6954 % Submit Dokumen Eng 3. Tanki T‐201, T‐202, T‐203 : Erection shell plate # 3
LUAS AREA SELISIH / DEVIASI ‐59.3046 % ‐ Kalkulasi Civil Work 4. Fire Pump House : Pemasangan anchor bolt
PROJECT COORDINATOR II ‐ PT PERTAMINA IMAN SETIAWAN PROGRESS MINGGU INI 0.3905 % ‐ Drawing Civil 5. Loading/Unloading shed : Erection 2 kolom, 2 rafter, 1 sub rafter
SITE PROJECT MANAGER ‐ PT PERTAMINA TEUKU DARMI ‐ All Data Sheet 6. Dokumen Engineering hanya masih 163 dari 332 yang selesai
LEAD ENGINEER ‐ PT PERTAMINA AMBAR PROGRESS KEUANGAN
PROJECT MANAGER ‐ PT INDRABAS M. ALWI PERIODE PENGELUARAN PROGRESS TAGIHAN INVOICE B. Procurement PERMASALAHAN
SITE MANAGER ‐ PT INDRABAS KAHONO S/D TGL TOTAL KURS % JUMLAH % ‐ Purchase Order (PO) 1. Dokumen engineering belum selesai masih on progress
ENGINEERING MANAGER ‐ PT INDRABAS RP 1 Floating Suction Brand Gammon, Type GTP ‐ 1644‐8‐3VR     masih dilakukan revisi dokumen
TANGGAL MULAI PEKERJAAN 24 FEBRUARI 2016 USD 2 TAS (PLC & ESD System, HMI System, Printer & Networki 2. Rumah Pompa baru dapat dikerjakan karena 
WAKTU PEKERJAAN 18 BULAN TOTAL 3 Drain Tank DT‐401/402, ID 1300 X 3900 (T/T) :  2 unit     Drawing dan Kalkulasi baru di approve
NILAI KONTRAK 91,900,000,000 4 Drain Tank DT‐501, ID 1800 X 3900 (T/T) :  1 unit 3. Keperluan menambah tenaga kerja untuk mempercepat target penyelesaian pekerjaan
REKAPITULASI EPC MINGGUAN ‐ On Site
BOBOT MINGGU LALU MINGGU INI AKUMULASI DEVIASI RP 1 CBM Roof CD Klip 672, Colorbond AZ 150 G550 :  225 m’
NO URAIAN
RP USD TOTAL ACT PLAN ACT PLAN ACT PLAN USD 2 Fixing Strap 672 : 300 pcs
A Engineering 2.6963             ‐ 1.7762 1.4945 1.7630 0.0461 0.0000 1.5406 1.7630 ‐0.2224 TOTAL SARAN KONSULTAN
B Procurement 66.3351       100.00 77.8221 28.7963 77.9872 0.2335 0.0000 29.0298 77.9872 ‐48.9574 C. Konstruksi 1. Diharapkan Engineering dapat mempercepat proses penyelesaian
C Construction 30.9686             ‐ 20.4016 10.0141 20.2498 0.1109 0.0000 10.1250 20.2498 ‐10.1247 Fuel Storage & Pumping Station   dokumen‐dokumen Engineering sebelum akhir bulan Juli atau Agustus
‐ Pengelasan fuel tanks 2. Diharapkan ada penambahan tenaga kerja welder untuk
TOTAL 100.00 100.00 100.00 40.3049 100.0000 0.3905 0.0000 40.6954 100.0000 ‐59.3046 ‐ Pekerjaan struktur office   menyelesaikan pengelasan komponen‐komponen semua tangki
‐ Pekerjaan struktur loading/unloading shed 3. Diharapkan ada percepatan kerja terutama untuk bangunan Office,
DETAIL PROGRESS MINGGUAN ‐ Pekerjaan struktur elektrikal house     Loading/Unloading shed, dan workshop agar target cepat selesai
BOBOT MINGGU LALU MINGGU INI AKUMULASI DEVIASI ‐ Pekerjaan struktur fire house
NO URAIAN
RP USD TOTAL ACT PLAN ACT PLAN ACT PLAN ‐ Pekerjaan struktur guard house
A General Requirement ‐ Pekerjaan struktur parking shelter TINDAKAN PERTAMINA
1 Project Management 9.0861                  ‐ 5.9412 5.6383 5.9412 0.0000 0.0000 5.6383 5.9412 ‐0.3029
2 Engineering Detail, Design & Survey 2.6963                  ‐ 1.7630 1.4945 1.7630 0.0461 0.0000 1.5406 1.7630 ‐0.2224 RENCANA MINGGU DEPAN
B Fuel Storage & Pumping Station A. Engineering
1 Storage Tanks And Vessels 14.2895                  ‐ 9.3436 6.7145 9.3436 0.1234 0.0000 6.8380 9.3436 ‐2.5056 Engineering Detail, Design & Survey
2 Mechanical 1.0597 35.6096 13.0181 6.5362 13.0181 0.0000 0.0000 6.5362 13.0181 ‐6.4819 ‐ Kalkulasi Sipil
3 Fire Protection 8.3970 8.4348 8.4101 3.6299 8.4101 0.0000 0.0000 3.6299 8.4101 ‐4.7802 ‐ Drawing Sipil
4 Piping 19.1387                  ‐ 12.5144 4.1572 12.5144 0.0000 0.0000 4.1572 12.5144 ‐8.3572 ‐ Datasheet Electrical KURVA MONITORING MINGGU KE 75
5 Electrical 9.7267 18.8265 12.8763 3.4084 12.8763 0.0000 0.0000 3.4084 12.8763 ‐9.4679 ‐ Datasheet Instrument 5.0000 100.0000
6 Instrumentation And Control System 3.7630 37.1290 15.3116 0.3852 15.3116 0.0870 0.0000 0.4722 15.3116 ‐14.8395 ‐ Datasheet Fire Fighting 4.5000 90.0000
7 Civil Works 20.5647                  ‐ 13.4469 5.4118 13.4469 0.0000 0.0000 5.4118 13.4469 ‐8.0350 4.0000 80.0000
8 Building Works 9.4808                  ‐ 6.1993 2.8931 6.1993 0.1340 0.0000 3.0271 6.1993 ‐3.1722 B. Procurement 3.5000 70.0000
C Inspection, Test, Commisioning And Certification 1.7975                  ‐ 1.1754 0.0357 1.1754 0.0000 0.0000 0.0357 1.1754 ‐1.1397 Purchase Order (PO) 3.0000 60.0000
‐ Kabel Elektrikal 2.5000 50.0000
2.0000 40.0000
TOTAL 100.00 100.00 100.00 40.3049 100.0000 0.3905 0.0000 40.6954 100.0000 ‐59.3046 ‐ Instrumen: Switches dan Gauges
1.5000 30.0000
WEATHER CONDITION ‐ Perlengkapan sistem Piping 1.0000 20.0000
‐ Komponen Arsitektural Office 0.5000 10.0000
√ Cerah √ Pagi hari ‐ sore hari ‐ Lighting Fixtures 0.0000 0.0000
√ Hujan ‐ Penangkal petir 1 2 3 4 5
‐ Foam System Rencana Aktual Kumulatif Progress
HSE REPORT
UMUM C. Konstruksi BULAN  Jul‐17
LOST
PROJECT MANHOURS SAFE MH LOST TIME ‐ Pengelasan Tangki Minggu 1 2 3 4 5
MAN POWER TIME
MGG. LALU MGG. INI CUMM. CUMM. ACCIDENT ‐ Pekerjaan Arsitektur Office Rencana 0.1592
INJURIES
Direct 12 1,624 488 2,112 ‐ 2,112 ‐ Pekerjaan Arsitektur Elektrikal House Kumulatif 100.0000 100.0000 100.0000 100.0000 100.0000
 MANHOURS Indirect 85 9,000 3,280 12,280 ‐ 12,280 ‐ Pekerjaan Struktur Fire House Aktual 1.0099 0.6461 1.0241 0.3905
Total 97 10,624 3,768 14,392 ‐ 14,392 ‐ Pekerjaan Struktur Filling Shed Kumulatif 37.3238 38.5648 39.2808 40.3049 40.6954
‐ Pekerjaan Struktur Parking Shelter Deviasi ‐62.4451 ‐61.4352 ‐60.7192 ‐59.6951 ‐59.3046

PT. Pertamina (Persero) Jakarta, 02 Agustus 2017
Direktorat Pemasaran ‐ PC LPG PT. Indrabas Purnama Makmur

Teuku Darmi Kahono
Site Project Manager Site Manager