RENCANA ANGGARAN BIAYA

Perhitungan Volume
Kegiatan : Tugas Besar Rencana Anggaran Biaya
Pekerjaan : Pembangunan Rumah 2 Lantai
Lokasi : Kabupaten 50 Kota
Tahun Anggaran : 2023

No Sketsa Gambar Uraian Perhitungan Jumlah

PEKERJAAN PENDAHULUAN

Pekerjaan pemasangan bowplank :

Volume : 50 m 50 m3

PEKERJAAN PONDASI

Pekerjaan Pondasi Cakar Ayam


Pek. Galian pondasi cakar ayam
Tinggi = 1.6 m
Panjang = 1 m
Lebar = 1 m
Banyak = 15 ttk
volume = 1 x 1 x 1.6 x 15
= 24 m3 24 m3

Pek. Lantai Kerja Cor Beton (K100)


Tinggi = 0.1 m
Panjang = 1 m
Lebar = 1 m
Banyak = 15 ttk
volume = 1 x 1 x 0.1 x 15
= 1.5 m3 1.5 m3

Pek. Pondasi Cakar Ayam


Beton :
Tapak 1
Tinggi = 0.2 m
Panjang = 1 m
Lebar = 1 m
Banyak = 15 ttk
volume = 1 x 1 x 0.2 x 15
= 3 m3

Tapak 2
Tinggi = 0.1 m
Panjang = 1 m
Lebar atas = 0.3 m
Banyak = 15 ttk
volume = 1 x 0.3 x 0.1 x 15
= 0.45 m3

Sekolah Tinggi Teknologi Payakumbuh


ANDIKA
201011025
RENCANA ANGGARAN BIAYA
volume = 3 + 0.4500
= 3.4500 m3 3.4500 m3

Pedestal
Tinggi = 1 m
Panjang = 0.3 m
Lebar = 0.3 m
Banyak = 15 ttk
volume = 0.3 x 0.3 x 1 x 15
= 1.35 m3
Volume Total Pondasi Cakar Ayam
= 3.4500 + 1.35
= 4.8000 m3 4.8000 m3

Pembesian
Untuk Tapak
Besi yang dipakai (Ø) = 12 mm
Berat besi/M = 0.89 kg/m
Panjang 1 unit = 2.88 m
Banyak = 10 buah
Total berat besi tapak = 0.88776 x 2.88 x 10
= 25.56749 m3
Untuk pedestal
Besi utama
Besi yang dipakai (Ø) = 16 mm
Berat besi/M = 1.58 kg/m
= 6 buah
Banyak dalam penampang
Panjang besi 1 unit = 11.52 m
Berat besi utama = 1.57824 x 11.52 x 6
= 109.0879 kg 109.0879 kg
Besi sengkang
Besi yang dipakai (Ø) = 10 mm
Berat besi/M = 0.62 kg/m
= 8 buah
Banyak dalam penampang
Panjang besi 1 unit = 1.04 m
Berat besi sengkang = 0.6165 x 8 x 1.04 = 5.12928 kg
= 109.0879 + 5.12928
Total berat besi pedestal = 114.2172 kg
= 139.7847 x 2.88
Total satu unit pondasi = 402.58 kg 402.58 kg

Bekisting
Bekisting untuk tapak
Tinggi : 0.3 m
Keliling tapak : 4 m
Volume : 0.3 x 4 = 1.2 m2

Sekolah Tinggi Teknologi Payakumbuh


ANDIKA
201011025
RENCANA ANGGARAN BIAYA
Bekisting untuk pedestal
Tinggi : 1 m
Keliling tapak : 4 m
Volume : 1 x 4 = 4 m2

Volume Bekisting : 1.2 + 4 = 5.2 m2


Untuk 3x pakai : 5.2 / 3 = 1.733333 m2 1.733333 m2

Urugan kembali : luas x t x n


Pondasi cakar ayam = 1 x 1.6 x 15
= 24 m3

= 0.09 x 1 x 15
Pengurangan podestal = 1.35 m3 1.35 m3

Pekerjaan Pondasi Cakar Ayam (Tangga)


Pek. Galian pondasi cakar ayam
Tinggi = 1.2 m
Panjang = 1.5 m
Lebar = 0.8 m
Banyak = 1 ttk
volume = 1.5 x 0.8 x 1.2 x 1
= 1.44 m3 1.44 m3

Pek. Lantai Kerja Cor Beton (K100)


Tinggi = 0.1 m
Panjang = 0.8 m
Lebar = 0.8 m
Banyak = 1 ttk
volume = 0.8 x 0.8 x 0.1 x 1
= 0.064 m3 0.064 m3

Pek. Pondasi Cakar Ayam


Beton :
Tapak 1
Tinggi = 0.2 m
Panjang = 0.8 m
Lebar = 0.8 m
Banyak = 1 ttk
volume = 0.8 x 0.8 x 0.2 x 1
= 0.128 m3

Tapak 2
Tinggi = 0.1 m
Panjang = 0.8 m
Lebar atas = 0.2 m
Banyak = 1 ttk
volume = 0.8 x 0.2 x 0.1 x 1
= 0.016 m3

Sekolah Tinggi Teknologi Payakumbuh


ANDIKA
201011025
RENCANA ANGGARAN BIAYA
volume = 0.128 + 0.0160
= 0.1440 m3

Pedestal
Tinggi = 1 m
Panjang = 0.2 m
Lebar = 0.2 m
Banyak = 1 ttk
volume = 0.2 x 0.2 x 1 x 1
= 0.04 m3
Volume Total Pondasi Cakar Ayam
= 0.1440 + 0.04
= 0.1840 m3 0.1840 m3

Pembesian
Untuk Tapak
Besi yang dipakai (Ø) = 12 mm
Berat besi/M = 0.89 kg/m
Panjang 1 unit = 1.95 m
Banyak = 5.333333 buah
Total berat besi tapak = 0.89 x 1.95 x 5.333333
= 9.256 kg
Untuk pedestal
Besi utama
Besi yang dipakai (Ø) = 16 mm
Berat besi/M = 1.58 kg/m
= 4 buah
Banyak dalam penampang
Panjang besi 1 unit = 6 m
Berat besi utama = 1.58 x 6 x 4
= 37.92 kg 37.92 M3

Besi sengkang
Besi yang dipakai (Ø) = 10 mm
Berat besi/M = 0.62 kg/m
= 6 buah
Banyak dalam penampang
Panjang besi 1 unit = 0.7 m
Berat besi sengkang = 0.62 x 6 x 0.7 = 2.604 kg
= 37.92 + 2.604
Total berat besi pedestal = 40.524 kg
= 49.78 x 1.95
Total satu unit pondasi = 97.071 kg

Sekolah Tinggi Teknologi Payakumbuh


ANDIKA
201011025
RENCANA ANGGARAN BIAYA
Bekisting
Bekisting untuk tapak
Tinggi : 0.3 m
Keliling tapak : 4 m
Volume : 0.3 x 4 = 1.2 m2

Bekisting untuk pedestal


Tinggi : 1 m
Keliling tapak : 4 m
Volume : 1 x 4 = 4 m2

Volume Bekisting : 1.2 + 4 = 5.2 m2


Untuk 3x pakai : 5.2 / 3 = 1.733333 m2

Urugan kembali : luas x t x n


Pondasi cakar ayam = 1 x 1.6 x 1
= 1.6 m3

= 0.09 x 1 x 1
Pengurangan podestal = 0.09 m3

Pek. Pondasi Batu Kali 1:4


Pek. Galian Pondasi Batu Kali
Tinggi = 0.75 m
Panjang = 112 m
Lebar = 0.8 m
Banyak = 1 ttk
volume = 0.75 x 112 x 0.8 x 1
= 67.2 m3 67.2 m3

Pek. Aanstampang
Tinggi = 0.2 m
Panjang = 112 m
Lebar = 0.8 m
Banyak = 1 ttk
volume = 0.2 x 112 x 0.8 x 1

= 17.92 m3 17.92 m3
Pek. Pasangan Batu Kali
volume = 0.45 x 0.6 x 112
= 30.24 m3 30.24 m3

Pek.Urugan Kembali
volume = 0.33 x 67.2
= 22.176 m3 22.176 m3

Sekolah Tinggi Teknologi Payakumbuh


ANDIKA
201011025
RENCANA ANGGARAN BIAYA
PEKERJAAN BETON BERTULANG

Pek. Sloof 15/20 Beton Bertulang fc' 14,5 Mpa (K-175)


Beton
Panjang = 105.5 m
dimensi = 0.15 x 0.2 = 0.03 m2
volume = 0.03 x 105.5 = 3.165 m3 3.165 m3

Pembesian
Besi utama
Besi yang dipakai (Ø) = 10 mm
Berat besi/M = 0.62 kg/m
= 4 buah
Banyak dalam penampang
Panjang besi 1 unit = 105.5 m
Berat besi utama = 0.6165 x 4 x 105.5
= 260.163 kg

Besi Sengkang
Besi yang dipakai (Ø) = 8 mm
Berat besi/M = 0.39 kg/m
= 703.3333 buah 704
Banyak dalam penampang
Panjang besi 1 unit = 0.64 m
Berat besi sengkang = 0.39456 x 704 x 0.64
= 177.773 kg
Total = 260.163 + 177.773 = 437.936 kg 437.936 kg

Bekisting
Panjang = 105.5 m
Tinggi = 0.2 m
Sisi = 2 sisi
Volume = 105.5 x 0.2 x 2
= 42.2 m2 42.2 m2

Pek. Sloof 30/40 Beton Bertulang fc' 14,5 Mpa (K-175)


Beton
Panjang = 83 m
dimensi = 0.3 x 0.4 = 0.12 m2
volume = 0.12 x 83 = 9.96 m3 9.96 m3

Pembesian
Besi utama
Besi yang dipakai (Ø) = 16 mm
Berat besi/M = 1.58 kg/m
= 5 buah
Banyak dalam penampang

Sekolah Tinggi Teknologi Payakumbuh


ANDIKA
201011025
RENCANA ANGGARAN BIAYA
Panjang besi 1 unit = 83 m
Berat besi utama = 1.57824 x 5 x 83
654.9696 kg
Besi Pinggang
Besi yang dipakai (Ø) = 12 mm
Berat besi/M = 0.89 kg/m
= 2 buah
Banyak dalam penampang
Panjang besi 1 unit = 83 m
Berat besi utama = 0.88776 x 2 x 83
147.3682 kg
Besi Sengkang ( Tumpuan)
Besi yang dipakai (Ø) = 10 mm
Berat besi/M = 0.62 kg/m
= 415 buah
Banyak dalam penampang
Panjang besi 1 unit = 11.24 m
Berat besi utama = 0.62 x 415 x 11.24
2892.052 kg
Besi Sengkang ( Lapangan)
Besi yang dipakai (Ø) = 10 mm
Berat besi/M = 0.62 kg/m
= 276.6667 buah
Banyak dalam penampang
Panjang besi 1 unit = 11.24 m
Berat besi utama = 0.6165 x 276.6667 x 11.24
= 1917.151 kg
Total = 654.9696 + 147.3682 + 2892.052 + 1917.1506
= 5611.54 kg 5611.54 kg

Bekisting
Panjang = 83 m
Tinggi = 0.4 m
Sisi = 2 sisi
Volume = 83 x 0.4 x 2
= 66.4 m2 66.4 m2

Pek. Kolom 15/15 Beton Bertulang fc' 14,5 Mpa (K-175)


Lantai 1 type 1
Beton
Tinggi = 3.4 m
dimensi = 0.15 x 0.15 = 0.0225 m2
Banyak = 34 buah
volume = 3.4 x 0.0225 x 34

= 2.601 m3 2.601 m3
Pembesian
Besi utama
Besi yang dipakai (Ø) = 10 mm
Berat besi/M = 0.62 kg/m

Sekolah Tinggi Teknologi Payakumbuh


ANDIKA
201011025
RENCANA ANGGARAN BIAYA
= 4 buah
Banyak dalam penampang
Panjang besi 1 unit = 3.6 m
Banyak = 34 buah
Berat besi utama = 0.6165 x 4 x 3.6 x 34
= 301.8384 kg 301.8384 kg

Besi Sengkang
Besi yang dipakai (Ø) : 8 mm
Berat besi/M : 0.39 kg/m
: 22.66667 buah 23
Banyak dalam penampang
: 0.52 m
Panjang besi sengkang 1 unit
Berat besi utama : 0.39456 x 23 x 0.52 x 0.52
2.453848 kg 2.453848 kg

Bekisting
Panjang = 3.4 m
Lebar = 0.15 m
Sisi = 2 sisi
Volume = 3.4 x 0.15 x 2
= 1.02 m2 1.02 m2

Pek. Kolom 15/15 Beton Bertulang fc' 14,5 Mpa (K-175)


Lantai 2 type 1
Beton
Tinggi = 3.55 m
dimensi = 0.15 x 0.15 = 0.0225 m2
Banyak = 14 buah
volume = 3.55 x 0.0225 x 14
= 1.11825 m3 1.11825 m3
Pembesian
Besi utama
Besi yang dipakai (Ø) = 10 mm
Berat besi/M = 0.62 kg/m
= 4 buah
Banyak dalam penampang
Panjang besi 1 unit = 3.75 m
Banyak = 14 buah
Berat besi utama = 0.6165 x 4 x 3.75 x 14
= 129.465 kg 129.465 kg

Sekolah Tinggi Teknologi Payakumbuh


ANDIKA
201011025
RENCANA ANGGARAN BIAYA
Besi Sengkang
Besi yang dipakai (Ø) : 8 mm
Berat besi/M : 0.39 kg/m
: 23.66667 buah 23
Banyak dalam penampang
: 0.52 m
Panjang besi sengkang 1 unit
Berat besi utama : 0.39456 x 23 x 0.52 x 0.52
2.453848 kg 2.453848 kg

Bekisting
Panjang = 3.55 m
Lebar = 0.15 m
Sisi = 2 sisi
Volume = 3.55 x 0.15 x 2
= 1.065 m2 1.065 m2

Pek. Kolom 30/30 Beton Bertulang fc' 14,5 Mpa (K-175)


Lantai 1 type 1
Beton
Tinggi = 3.4 m
dimensi = 0.3 x 0.3 = 0.09 m2
Banyak = 15 buah
volume = 3.4 x 0.09 x 15
= 4.59 m3 4.59 m3
Pembesian
Besi utama
Besi yang dipakai (Ø) = 16 mm
Berat besi/M = 1.58 kg/m
= 8 buah
Banyak dalam penampang
Panjang besi 1 unit = 4 m
Banyak = 15 buah
Berat besi utama = 1.57824 x 8 x 4 x 15
= 757.5552 kg 757.5552 kg

Besi Sengkang (Tumpuan)


Besi yang dipakai (Ø) = 10 mm
Berat besi/M = 0.62 kg/m
= 17 buah 17
Banyak dalam penampang
= 0.52 m
Panjang besi sengkang 1 unit
Berat besi utama = 0.6165 x 17 x 0.52 x 0.52 x 15
42.50891 kg 42.50891 kg

Sekolah Tinggi Teknologi Payakumbuh


ANDIKA
201011025
RENCANA ANGGARAN BIAYA
Besi Sengkang (Lapangan)
Besi yang dipakai (Ø) : 10 mm
Berat besi/M : 0.62 kg/m
: 11.33333 buah 12
Banyak dalam penampang
: 0.52 m
Panjang besi sengkang 1 unit
Berat besi utama : 0.62 x 12 x 0.52 x 0.52 x 15
30.00629 kg
Total besi lantai 1 = 830.0704 kg 830.0704 kg

Bekisting
Panjang = 3.4 m
Lebar = 0.3 m
Sisi = 4 sisi
Volume = 3.4 x 0.3 x 4 x 15
= 61.2 m2 61.2 m2

Lantai 2 type 1
Beton
Tinggi = 3.75 m
dimensi = 0.3 x 0.3 = 0.09 m2
Banyak = 15 buah
volume = 3.75 x 0.09 x 15
= 5.0625 m3 5.0625 m3
Pembesian
Besi utama
Besi yang dipakai (Ø) = 16 mm
Berat besi/M = 1.58 kg/m
= 8 buah
Banyak dalam penampang
Panjang besi 1 unit = 4 m
Banyak = 15 buah
Berat besi utama = 1.57824 x 8 x 4 x 15
= 757.5552 kg 757.5552 kg

Besi Sengkang (Tumpuan)


Besi yang dipakai (Ø) : 10 mm
Berat besi/M : 0.62 kg/m
: 18.75 buah 19
Banyak dalam penampang
: 0.52 m
Panjang besi sengkang 1 unit
Berat besi utama : 0.6165 x 19 x 0.52 x 0.52 x 15
47.50996 kg 47.50996 kg

Sekolah Tinggi Teknologi Payakumbuh


ANDIKA
201011025
RENCANA ANGGARAN BIAYA
Besi Sengkang (Lapangan)
Besi yang dipakai (Ø) : 10 mm
Berat besi/M : 0.62 kg/m
: 12.5 buah 13
Banyak dalam penampang
: 0.52 m
Panjang besi sengkang 1 unit
Berat besi utama : 0.6165 x 13 x 0.52 x 0.52 x 15
32.50681 kg
Total besi lantai 2 = 837.572 kg 837.572 kg

Bekisting
Panjang = 3.75 m
Lebar = 0.4 m
Sisi = 4 sisi
Volume = 3.75 x 0.4 x 4 x 15
= 90 m2 90 m2

Pek. Balok 15/20 Beton Bertulang fc' 14,5 Mpa (k-175) Elv. +3.60
Beton
Panjang = 85.5 m
dimensi = 0.15 x 0.2 = 0.03 m2
Banyak = 1 buah
volume = 85.5 x 0.03 x 1
= 2.565 m3 2.565 m3

Pembesian
Besi utama
Besi yang dipakai (Ø) = 10 mm
Berat besi/M = 0.62 kg/m
= 4 buah
Banyak dalam penampang
Panjang besi 1 unit = 85.5 m
Berat besi utama = 0.6165 x 4 x 85.5
= 210.843 kg 210.843 kg

Besi Sengkang
Besi yang dipakai (Ø) = 8 mm
Berat besi/M = 0.39 kg/m
= 570 buah 570
Banyak dalam penampang
Panjang besi 1 unit = 0.64 m
Berat besi sengkang = 0.39456 x 570 x 0.64
= 143.9355 kg
Total = 210.843 + 143.9355 = 354.7785 kg 354.7785 kg

Sekolah Tinggi Teknologi Payakumbuh


ANDIKA
201011025
RENCANA ANGGARAN BIAYA
Bekisting
Panjang = 85.5 m
Lebar = 0.2 m
Sisi = 2 sisi
Volume = 85.5 x 0.2 x 2 x 1
= 34.2 m2 34.2 m2

Pek. Balok 25/40 Beton Bertulang fc' 14,5 Mpa (k-175) Elv. +3.60
Beton
Panjang = 85.5 m
dimensi = 0.25 x 0.4 = 0.1 m2
Banyak = 1 buah
volume = 85.5 x 0.1 x 1
= 8.55 m3 8.55 m3

Pembesian
Besi utama
Besi yang dipakai (Ø) = 16 mm
Berat besi/M = 1.58 kg/m
= 5 buah
Banyak dalam penampang
Panjang besi 1 unit = 1 m
Berat besi utama = 1.57824 x 5 x 1
7.8912 kg 7.8912 kg
Besi Pinggang
Besi yang dipakai (Ø) = 12 mm
Berat besi/M = 0.89 kg/m
= 2 buah
Banyak dalam penampang
Panjang besi 1 unit = 1 m
Berat besi utama = 0.88776 x 2 x 1
1.77552 kg 1.77552 kg
Besi Sengkang ( Tumpuan)
Besi yang dipakai (Ø) = 10 mm
Berat besi/M = 0.62 kg/m
= 427.5 buah 428
Banyak dalam penampang
Panjang besi 1 unit = 11.24 m
Berat besi utama = 0.62 x 428 x 11.24
2982.646 kg 2982.646 kg
Besi Sengkang ( Lapangan)
Besi yang dipakai (Ø) = 10 mm
Berat besi/M = 0.62 kg/m
= 285 buah
Banyak dalam penampang
Panjang besi 1 unit = 11.24 m
Berat besi utama = 0.6165 x 285 x 11.24
= 1974.896 kg
Total = 7.8912 + 1.77552 + 2982.646 + 1974.8961
= 4967.209 kg 4967.209 kg

Sekolah Tinggi Teknologi Payakumbuh


ANDIKA
201011025
RENCANA ANGGARAN BIAYA
Bekisting
Panjang = 85.5 m
Tinggi = 0.4 m
Sisi = 1.05
Volume = 85.5 x 0.4 x 1.05
= 35.91 m2 35.91 m2

Pek. Balok 15/30 Beton Bertulang fc' 14,5 Mpa (k-175) Elv. +3.60
Beton
Panjang = 9.5 m
dimensi = 0.15 x 0.3 = 0.045 m2
Banyak = 1 buah
volume = 9.5 x 0.045 x 1
= 0.4275 m3 0.4275 m3

Pembesian
Besi utama
Besi yang dipakai (Ø) = 10 mm
Berat besi/M = 0.62 kg/m
= 5 buah
Banyak dalam penampang
Panjang besi 1 unit = 1 m
Berat besi utama = 0.6165 x 5 x 1
3.0825 kg 3.0825 kg
Besi Pinggang
Besi yang dipakai (Ø) = 10 mm
Berat besi/M = 0.62 kg/m
= 2 buah
Banyak dalam penampang
Panjang besi 1 unit = 1 m
Berat besi utama = 0.6165 x 2 x 1
1.233 kg 1.233 kg
Besi Sengkang ( Tumpuan)
Besi yang dipakai (Ø) = 8 mm
Berat besi/M = 0.39 kg/m
= 47.5 buah 48
Banyak dalam penampang
Panjang besi 1 unit = 11.24 m
Berat besi utama = 0.39456 x 48 x 11.24
212.873 kg 212.873 kg
Besi Sengkang ( Lapangan)
Besi yang dipakai (Ø) = 10 mm
Berat besi/M = 0.62 kg/m
= 31.66667 buah 32
Banyak dalam penampang
Panjang besi 1 unit = 11.24 m
Berat besi utama = 0.6165 x 32 x 11.24
= 221.7427 kg
Total = 3.0825 + 1.233 + 212.873 + 221.74272
= 438.9312 kg 438.9312 kg

Sekolah Tinggi Teknologi Payakumbuh


ANDIKA
201011025
RENCANA ANGGARAN BIAYA
Bekisting
Panjang = 9.5 m
Tinggi = 0.4 m
Sisi = 2
Volume = 9.5 x 0.4 x 2
= 7.6 m2 7.6 m2

Pek. Balok 15/20 Beton Bertulang fc' 14,5 Mpa (k-175) Elv. +7.35
Beton
Panjang = 112 m
dimensi = 0.15 x 0.2 = 0.03 m2
Banyak = 1 buah
volume = 112 x 0.03 x 1
= 3.36 m3 3.36 m3

Pembesian
Besi utama
Besi yang dipakai (Ø) = 10 mm
Berat besi/M = 0.62 kg/m
= 4 buah
Banyak dalam penampang
Panjang besi 1 unit = 112 m
Berat besi utama = 0.6165 x 4 x 112
= 276.192 kg 276.192 kg

Besi Sengkang
Besi yang dipakai (Ø) = 8 mm
Berat besi/M = 0.39 kg/m
= 746.6667 buah 747
Banyak dalam penampang
Panjang besi 1 unit = 0.64 m
Berat besi sengkang = 0.39456 x 747 x 0.64
= 188.6312 kg
Total = 276.192 + 188.6312 = 464.8232 kg 464.8232 kg

Bekisting
Panjang = 112 m
Lebar = 0.2 m
Sisi = 2 sisi
Volume = 112 x 0.2 x 2 x 1
= 44.8 m2 44.8 m2

Pek. Afwerking Beton


= kll x p x n
Sloof 30/40 = 0.86 x 83 x 1 = 71.38 m2

= kll x t x n
Kolom 30/30 = 1.2 x 7.3 x 15 = 131.4 m2

Sekolah Tinggi Teknologi Payakumbuh


ANDIKA
201011025
RENCANA ANGGARAN BIAYA
= kll x p x n
Balok 25/40 = 0.9 x 85.5 x 1 = 76.95 m2
Total = 279.73 m2 279.73 m2

Pengurangan
p x t x n
kolom 30/30

balok 25/40 = 0.25 x 0.4 x 21 = 2.1 m2


balok 15/30 = 0.25 x 0.4 x 9 = 0.9 m2
balok 15/20 = 0.25 x 0.4 x 38 = 3.8 m2

Balok 25/40
Pelat Lantai = 1.35 x 1.3 x 1 = 1.755 m2
= 3.35 x 1.3 x 1 = 4.355 m2
= 3.85 x 1.3 x 1 = 5.005 m2
= 3.75 x 3.75 x 2 = 28.125 m2
= 3.75 x 3.3 x 2 = 24.75 m2
= 3.35 x 1.05 x 1 = 3.5175 m2
= 3.8 x 3.75 x 1 = 14.25 m2
Total = 88.5575 m2

Total Afwerking = 279.73 - 88.5575 = 191.1725 m2 191.1725 m2

PEKERJAAN DINDING BATA

Pek. 1/2 Bata 1:4 p x t x n


Lantai 1 = 5 x 3 x 1 = 15 m2
= 3 x 2.9 x 1 = 8.7 m2
= 2 x 3.4 x 2 = 13.6 m2
= 5 x 3.4 x 1 = 17 m2
= 4 x 3.4 x 3 = 40.8 m2
= 1.5 x 3.4 x 1 = 5.1 m2
= 3.5 x 3.4 x 1 = 11.9 m2
= 5 x 3 x 1 = 15 m2
= 5 x 3.2 x 3 = 48 m2
= 4 x 3.2 x 6 = 76.8 m2
= 1 x 3.2 x 1 = 3.2 m2
= 2 x 3 x 1 = 6 m2
= 2 x 2.9 x 2 = 11.6 m2
= 1 x 3.4 x 1 = 3.4 m2
= 7 x 3.4 x 2 = 47.6 m2
= 1 x 3.5 x 1 = 3.5 m2
= 2 x 3.2 x 1 = 6.4 m2
= 5.5 x 3.2 x 1 = 17.6 m2
= 1.5 x 3.4 x 3 = 15.3 m2
= 2 x 3.2 x 1 = 6.4 m2
= 4 x 3.2 x 5 = 64 m2

Sekolah Tinggi Teknologi Payakumbuh


ANDIKA
201011025
RENCANA ANGGARAN BIAYA
= 3.5 x 3.4 x 1 = 11.9 m2
= 0.9 x 3.2 x 3 = 8.64 m2
= 7 x 2 x 2 = 14 m2
2

Lantai 2 = 5 x 4 x 2 = 40 m2
= 4 x 4 x 4 = 64 m2
= 3.5 x 3.3 x 1 = 11.55 m2
= 1.5 x 3.3 x 1 = 4.95 m2
= 5 x 3.55 x 1 = 17.75 m2
= 3.25 x 3.55 x 1 = 11.5375 m2
= 0.75 x 4 x 2 = 6 m2
= 5 x 4 x 1 = 20 m2
= 4 x 4 x 3 = 48 m2
= 4 x 3.55 x 1 = 14.2 m2
= 3.5 x 3.55 x 1 = 12.425 m2
= 3.75 x 3.55 x 2 = 26.625 m2
= 0.75 x 4 x 2 = 6 m2
= 0.9 x 3.4 x 3 = 9.18 m2
Total = 763.6575 m2 763.6575 m2

Pengurangan
Lantai 1 p x t x n
Kolom 15/15 = 0.15 x 3.6 x 21 = 11.34 m2
Kolom 15/15 = 0.15 x 3 x 4 = 1.8 m2
Kolom 30/30 = 0.3 x 3.6 x 15 = 16.2 m2
Balok 15/15 = 0.15 x 6 x 2 = 1.8 m2

p x t x n
PJ1 = 0.95 x 1.6 x 4 = 6.08 m2
= 1.3 x 2.1 x 2 = 5.46 m2
PJ2 = 4.75 x 2.1 x 1 = 9.975 m2
P2 = 3.7 x 2.1 x 2 = 15.54 m2
P3 = 0.9 x 2.1 x 6 = 11.34 m2
P4 = 0.7 x 2 x 4 = 5.6 m2
J1 = 1 x 1.6 x 6 = 9.6 m2
J2 = 1.3 x 1.6 x 1 = 2.08 m2
J4 = 0.5 x 1.6 x 3 = 2.4 m2
V1 = 0.6 x 0.4 x 4 = 0.96 m2
V2 = 0.3 x 0.3 x 114 = 10.26 m2

Lantai 2 p x t x n
Kolom 15/15 = 0.15 x 4 x 3 = 1.8 m2
Kolom 30/30 = 0.3 x 3.6 x 15 = 16.2 m2

Sekolah Tinggi Teknologi Payakumbuh


ANDIKA
201011025
RENCANA ANGGARAN BIAYA
p x t x n
PJ1 = 0.95 x 1.6 x 1 = 1.52 m2
= 1.3 x 2.1 x 1 = 2.73 m2
PJ2 = - x - x - = - m2
P2 = - x - x - = - m2
P3 = 0.9 x 2.1 x 2 = 3.78 m2
P4 = 0.7 x 2 x 3 = 4.2 m2
J1 = 1 x 1.6 x 5 = 8 m2
J3 = 4.7 x 3.2 x 1 = 15.04 m2
J4 = 0.5 x 1.6 x 2 = 1.6 m2
V1 = 0.6 x 0.4 x 3 = 0.72 m2
Total = 166.025 m2 166.025 m2

= 763.6575 - 166.025 = 597.6325 m2 597.6325 m2


Total Pas Batu Bata 1/4

Pek. Plesteran 1:2 + Aci


= 597.6325 x 2 = 1195.265 m2 1195.265 m2

PEKERJAAN KUZEN PINTU DAN JENDELA ALUMUNIUM

Pek. Kuzen Pintu dan Jendela Aluminium

p x n x unit
PJ1 = 3.2 x 1 x 4 = 12.8 m
= 0.95 x 2 x 4 = 7.6 m
= 2.05 x 2 x 4 = 16.4 m
= 1.55 x 2 x 4 = 12.4 m

PJ2 = 4.75 x 2 x 1 = 9.5 m


= 2.05 x 4 x 1 = 8.2 m
= 0.6 x 2 x 1 = 1.2 m

PJ2 = 3.7 x 1 x 2 = 7.4 m


= 2.05 x 2 x 2 = 8.2 m

P3 = 0.9 x 1 x 8 = 7.2 m
= 2.05 x 2 x 8 = 32.8 m

P4 = 0.7 x 1 x 7 = 4.9 m
= 1.95 x 2 x 7 = 27.3 m

J1 = 1 x 2 x 11 = 22 m
= 1.5 x 2 x 11 = 33 m

Sekolah Tinggi Teknologi Payakumbuh


ANDIKA
201011025
RENCANA ANGGARAN BIAYA
J2 = 2.3 x 2 x 1 = 4.6 m
= 1.5 x 3 x 1 = 4.5 m
= 1.8 x 1 x 1 = 1.8 m

J3 = 4.7 x 5 x 1 = 23.5 m
= 3.1 x 6 x 1 = 18.6 m

J4 = 0.5 x 2 x 6 = 6 m
= 1.5 x 2 x 6 = 18 m

J4 = 0.6 x 2 x 6 = 7.2 m
= 0.4 x 2 x 6 = 4.8 m
Total = 299.9 m 299.9 m

Pek. Daun Pintu Aluminium


p x l x unit
PJ1 = 2.05 x 0.6 x 8 = 9.84 m2

PJ2 = 2.05 x 0.6 x 6 = 1.46 m2

P2 = 2.05 x 0.6 x 6 = 2.94 m2

P3 = 2.05 x 0.8 x 8 = 13.12 m2

P4 = 1.95 x 0.6 x 6 = 7.02 m2


Total = 27.36 m2 27.36 m

Pek. Daun Jendela Aluminium


p x l x unit
J2 = 1.5 x 0.4 x 1 = 0.6 m2

J4 = 1.5 x 0.4 x 5 = 3 m2
Total = 3.6 m2

Pek. Kaca Polos 5 mm


p x l x unit
PJ1 = 1.5 x 0.9 x 8 = 10.8 m2

PJ2 = 2 x 0.5 x 2 = 2 m2
= 1.85 x 0.4 x 6 = 4.44 m2

P2 = 1.85 x 0.4 x 12 = 8.88 m2

J1 = 1.5 x 0.9 x 11 = 14.85 m2

J2 = 0.9 x 0.73 x 4 = 2.628 m2


= 1.38 x 0.3 x 4 = 1.656 m2

Sekolah Tinggi Teknologi Payakumbuh


ANDIKA
201011025
RENCANA ANGGARAN BIAYA
J3 = 0.85 x 0.74 x 20 = 12.58 m2

J4 = 1.38 x 0.74 x 5 = 5.106 m2

v1 = 0.18 x 0.5 x 12 = 1.08 m2


Total = 71.22 m2 71.22 m2

Pasangan Handle + Kunci


n x unit
PJ1 = 4 x 4 = 16 bh
PJ2 = 2 x 1 = 2 bh
P2 = 2 x 2 = 4 bh
P3 = 2 x 8 = 16 bh
P4 = 2 x 4 = 8 bh
Total = 38 bh 38 bh

Pasangan Engsel Pintu


n x unit
PJ1 = 3 x 4 = 12 bh
PJ2 = 3 x 1 = 3 bh
P2 = 3 x 2 = 6 bh
P3 = 3 x 8 = 24 bh
P4 = 3 x 4 = 12 bh
Total = 45 bh 45 bh

Pasangan Engsel Jendela


n x unit
PJ1 = - x - = - bh
PJ2 = - x - = - bh
P2 = - x - = - bh
J2 = 2 x 1 = 2 bh
J4 = 2 x 5 = 10 bh
Total = 12 bh 12 bh

Pasangan Grandel Pintu


n x unit
PJ1 = 3 x 4 = 12 bh
PJ2 = 3 x 1 = 3 bh
P2 = 3 x 2 = 6 bh
P3 = 1 x 8 = 8 bh
P4 = 1 x 4 = 4 bh
Total = 33 bh 33 bh

Pasangan Grandel Jendela


n x unit
J2 = 2 x 1 = 2 bh
J4 = 2 x 5 = 10 bh

Total = 12 bh 12 bh

Sekolah Tinggi Teknologi Payakumbuh


ANDIKA
201011025
RENCANA ANGGARAN BIAYA
Pasangan Kait Angin Jendela
n x unit
J2 = 2 x 1 = 2 bh
J4 = 2 x 5 = 10 bh
Total = 12 bh 12 bh

Pasangan Hand Vatend Jendela


n x unit
J2 = 2 x 1 = 2 bh
J4 = 2 x 5 = 10 bh
Total = 12 bh 12 bh

Ventilasi Beton = 114 bh

PEKERJAAN ATAP

Pek. Kuda-Kuda Atap Baja Ringan

Volume 1 = 4.84 x 4.74 x 2 = 45.8832 m2


= 4.13 x 3.85 x 2 = 31.801 m2

Volume 2 = 11.88 + 4 x 3.94 x 1 = 31.2836 m2


2

Volume 3 = 7.88 x 3.94 x 1 = 15.5236 m2


2

Volume 4 = 10.38 + 3.5 x 3.44 x 1 = 23.8736 m2


2

Volume 5 = 1 x 0.5 x 1 = 0.25 m2


2

Volume 6 = 6.88 x 3.44 x 1 = 11.8336 m2


2

Volume 7 = 4.86 x 4.86 x 1 = 11.8098 m2


2

Volume 8 = 5.57 x 5.57 x 1 = 15.51245 m2


2
Total = 187.7709 m2 187.7709 m2

Sekolah Tinggi Teknologi Payakumbuh


ANDIKA
201011025
RENCANA ANGGARAN BIAYA
Pek. Atap Seng Metal Warna
= 187.7709 m2 187.7709 m2

Pek. Perabung Atap


LT 2 = 103.22 m
LT1 = 7.75 m
= 110.97 m 103.22 m2

Pek. Listplank 2/10+2/10


LT 1 = 15.96 m
LT 2 = 44.52 m
= 60.48 m 15.96 m2

PEKERJAAN PLAFOND

Pek. Rangka Plafond 60cm x 60 cm


p x l x n
Lantai 1 = 6.85 x 3.85 x 1 = 26.3725 m2
= 1.85 x 1.35 x 1 = 2.4975 m2
= 1.85 x 0.85 x 1 = 1.5725 m2
= 2.85 x 0.35 x 1 = 0.9975 m2
= 3.85 x 2.35 x 1 = 9.0475 m2
= 3.85 x 1.35 x 1 = 5.1975 m2
= 3.85 x 3.85 x 3 = 44.4675 m2
= 1.35 x 1.35 x 2 = 3.645 m2
= 4.85 x 3.85 x 1 = 18.6725 m2
= 4.85 x 3.85 x 1 = 18.6725 m2
= 4.85 x 1.35 x 1 = 6.5475 m2
= 3.85 x 2.85 x 1 = 10.9725 m2
= 7.85 x 3.85 x 1 = 30.2225 m2
= 7.1 x 3.85 x 1 = 27.335 m2
Total = 206.22 m2 206.22 m2

Lantai 2 = 2.85 x 1.35 x 1 = 3.8475 m2


= 1.85 x 1.35 x 1 = 2.4975 m2
= 4.85 x 3.85 x 1 = 18.6725 m2
= 4.85 x 4.85 x 1 = 23.5225 m2
= 10.35 x 3.85 x 1 = 39.8475 m2
= 3.85 x 3.85 x 1 = 14.8225 m2
= 3.85 x 3.85 x 1 = 14.8225 m2
= 3.35 x 3.35 x 1 = 11.2225 m2
Total = 129.255 m2 129.255 m2

Total Pek. Plafond Gypsum = 206.22 + 129.255 = 335.475 m2 335.475 m2


60x60cm

Sekolah Tinggi Teknologi Payakumbuh


ANDIKA
201011025
RENCANA ANGGARAN BIAYA
Pek. Pasangan List Plafond
Lantai 1 p x n
= 21.4 x 1 = 21.4 m
= 15.4 x 2 = 30.8 m
= 20.3 x 1 = 20.3 m
= 49.35 x 1 = 49.35 m
= 6.4 x 1 = 6.4 m
= 5.4 x 1 = 5.4 m
= 8.4 x 1 = 8.4 m
= 19.4 x 1 = 19.4 m
= 38.7 x 1 = 38.7 m
= 16.25 x 1 = 16.25 m
= 5.4 x 1 = 5.4 m

Lantai 2 p x n
= 8.4 x 1 = 8.4 m
= 10.1 x 1 = 10.1 m
= 17.4 x 1 = 17.4 m
= 15.4 x 1 = 15.4 m
= 43.2 x 1 = 43.2 m
= 16.25 x 1 = 16.25 m
= 5.4 x 1 = 5.4 m
Total = 337.95 m 337.95 m

PEKERJAAN LANTAI

Pek. Timbunan tanah


p x l x t x n
Lantai 1 = 6.85 x 3.85 x 0.1 x 1 = 2.63725 m3
= 1.85 x 4.85 x 0.09 x 1 = 0.807525 m3
= 1.85 x 1.35 x 0.09 x 1 = 0.224775 m3
= 1.85 x 0.85 x 0.09 x 1 = 0.141525 m3
= 2.85 x 0.35 x 0.09 x 1 = 0.089775 m3
= 3.85 x 2.35 x 0.09 x 1 = 0.814275 m3
= 3.85 x 1.35 x 0.09 x 1 = 0.467775 m3
= 3.85 x 3.85 x 0.09 x 4 = 5.3361 m3
= 1.35 x 1.35 x 0.09 x 1 = 0.164025 m3
= 4.85 x 3.85 x 0.09 x 1 = 1.680525 m3
= 4.85 x 3.85 x 0.09 x 1 = 1.680525 m3
= 4.85 x 1.35 x 0.09 x 1 = 0.589275 m3
= 4.85 x 4.85 x 0.04 x 1 = 0.9409 m3
= 10.35 x 3.85 x 0.04 x 1 = 1.5939 m3
= 3.85 x 2.35 x 0.09 x 1 = 0.814275 m3
= 3.35 x 1.85 x 0.09 x 1 = 0.557775 m3
= 3.1 x 3.1 x 0.04 x 1 = 0.3844 m3
Total = 18.9246 m3 18.9246 m3

Sekolah Tinggi Teknologi Payakumbuh


ANDIKA
201011025
RENCANA ANGGARAN BIAYA
Pek. Pasir Urug t:7cm
p x l x t x n
Lantai 1 = 6.85 x 3.85 x 0.1 x 1 = 2.63725 m3
= 1.85 x 4.85 x 0.1 x 1 = 0.89725 m3
= 1.85 x 1.35 x 0.1 x 1 = 0.24975 m3
= 1.85 x 0.85 x 0.1 x 1 = 0.15725 m3
= 2.85 x 0.35 x 0.1 x 1 = 0.09975 m3
= 3.85 x 2.35 x 0.1 x 1 = 0.90475 m3
= 3.85 x 1.35 x 0.1 x 1 = 0.51975 m3
= 3.85 x 3.85 x 0.1 x 4 = 5.929 m3
= 1.35 x 1.35 x 0.1 x 1 = 0.18225 m3
= 4.85 x 3.85 x 0.1 x 1 = 1.86725 m3
= 4.85 x 3.85 x 0.1 x 1 = 1.86725 m3
= 4.85 x 1.35 x 0.1 x 1 = 0.65475 m3
= 4.85 x 4.85 x 0.1 x 1 = 2.35225 m3
= 10.35 x 3.85 x 0.1 x 1 = 3.98475 m3
= 3.85 x 2.35 x 0.1 x 1 = 0.90475 m3
= 3.35 x 1.85 x 0.1 x 1 = 0.61975 m3
= 3.1 x 3.1 x 0.1 x 1 = 0.961 m3
Total = 24.78875 m3 24.78875 m3

Pek. Cor Beton (K-100) t ; 7cm


p x l x t x n
Lantai 1 = 6.85 x 3.85 x 0.07 x 1 = 1.846075 m3
= - x - x - x - = - m3
= 1.85 x 1.35 x 0.07 x 1 = 0.174825 m3
= 1.85 x 0.85 x 0.07 x 1 = 0.110075 m3
= 2.85 x 0.35 x 0.07 x 1 = 0.069825 m3
= 3.85 x 2.35 x 0.07 x 1 = 0.633325 m3
= 3.85 x 1.35 x 0.07 x 1 = 0.363825 m3
= 3.85 x 3.85 x 0.07 x 4 = 4.1503 m3
= 1.35 x 1.35 x 0.07 x 1 = 0.127575 m3
= 4.85 x 3.85 x 0.07 x 1 = 1.307075 m3
= 4.85 x 3.85 x 0.07 x 1 = 1.307075 m3
= 4.85 x 1.35 x 0.07 x 1 = 0.458325 m3
= 4.85 x 4.85 x 0.07 x 1 = 1.646575 m3
= 10.35 x 3.85 x 0.07 x 1 = 2.789325 m3
= 3.85 x 2.35 x 0.07 x 1 = 0.633325 m3
= 3.35 x 1.85 x 0.07 x 1 = 0.433825 m3
= 3.1 x 3.1 x 0.07 x 1 = 0.6727 m3
Total = 16.72405 m3 16.72405 m3

Pek. Pasangan Granite 60x60

p x l x n
Lantai 1 = 6.85 x 3.85 x 1 = 26.3725 m2
= - x - x - = - m2
= 1.85 x 1.35 x 1 = 2.4975 m2
= 1.85 x 0.85 x 1 = 1.5725 m2
= 2.85 x 0.35 x 1 = 0.9975 m2

Sekolah Tinggi Teknologi Payakumbuh


ANDIKA
201011025
RENCANA ANGGARAN BIAYA
= 3.85 x 3.85 x 4 = 59.29 m2
= - x - x - = - m2
= 4.85 x 3.85 x 1 = 18.6725 m2
= 4.85 x 3.85 x 1 = 18.6725 m2
= 4.85 x 1.35 x 1 = 6.5475 m2
= 4.85 x 4.85 x 1 = 23.5225 m2
= 10.35 x 3.85 x 1 = 39.8475 m2
= 3.85 x 2.35 x 1 = 9.0475 m2
= 3.35 x 1.85 x 1 = 6.1975 m2
= 3.1 x 3.1 x 1 = 9.61 m2
Total = 222.8475 m2

Lantai 2 = 2.85 x 1.35 x 1 = 3.8475 m2


= 1.85 x 1.35 x 1 = 2.4975 m2
= 4.85 x 3.85 x 1 = 18.6725 m2
= 4.85 x 4.85 x 1 = 23.5225 m2
= 10.35 x 3.85 x 1 = 39.8475 m2
= 3.85 x 3.85 x 1 = 14.8225 m2
= 3.85 x 3.85 x 1 = 14.8225 m2
= 3.85 x 1.85 x 1 = 7.1225 m2
= 3.85 x 2.35 x 1 = 9.0475 m2
= 3.35 x 3.35 x 1 = 11.2225 m2
Total = 145.425 m2

Pengurangan
Void = 4.85 x 3.35 x 1 = 16.2475 m2
Void tangga = 3.85 x 3.85 x 1 = 14.8225 m2
Total Pek. Pasangan Granite 60x60 = 31.07 m2 31.07 m2

= 145.425 - 31.07 = 114.355 m2 114.355 m2


Total Pek. Pasangan granite
60x60 (lantai 2)

= 222.8475 + 114.355 = 337.2025 m2 337.2025 m2


Total Pek. Pasangan granite
60x60

Pek. Pasangan Keramik 30x30 anti slip

p x l x n
Lantai 1 = 1.85 x 1.85 x 1 = 3.4225 m2
= 3.35 x 1.35 x 1 = 4.5225 m2
= 1.35 x 1.35 x 2 = 3.645 m2
Total = 11.59 m2 11.59 m2

p x l x n
Lantai 2 = 2.85 x 1.35 x 1 = 3.8475 m2
= 1.35 x 1.35 x 1 = 1.8225 m2
= Total = 5.67 m2

Sekolah Tinggi Teknologi Payakumbuh


ANDIKA
201011025
RENCANA ANGGARAN BIAYA
= 11.59 + 5.67 = 17.26 m2 17.26 m2
Total Pek. Pasangan keramik
30x30 Anti Slip

PEKERJAAN PELAT LANTAI t= 12cm

Pek. Pelat Lantai


p x l x t x n =
Elv. +3.00 = 1.85 x 1.35 x 0.12 x 1 = 0.2997 m3

Elv. +3.50 = 1.35 x 1.3 x 0.12 x 1 = 0.2106 m3


= 3.35 x 1.3 x 0.12 x 1 = 0.5226 m3
= 3.85 x 1.3 x 0.12 x 1 = 0.6006 m3
= 3.75 x 3.75 x 0.12 x 2 = 3.375 m3
= 3.75 x 3.3 x 0.12 x 2 = 2.97 m3
= 3.35 x 1.05 x 0.12 x 1 = 0.4221 m3
= 3.8 x 3.75 x 0.12 x 1 = 1.71 m3

Elv. +6.50 = 3.85 x 2.35 x 0.12 x 1 = 1.0857 m3


= 3.35 x 1.85 x 0.12 x 1 = 0.7437 m3

Elv. +7.00 = 2.85 x 1.35 x 0.12 x 1 = 0.4617 m3


= 48.15 x 1 x 0.1 x 1 = 4.815 m3
Total = 17.2167 m3 17.2167 m3

Tulangan arah X Elv.+3.00


Ø Besi (mm)) =
10 = Berat/m (kg) x Bnyk Btg x Panjang x Lapis
10 = 0.62 x 10 x 2 x 2 = 24.66 kg

Tulangan arah Y Elv.+3.00


Ø Besi (mm)) =
10 = Berat/m (kg) x Bnyk Btg x Panjang x Lapis
10 = 0.62 x 13.33333 x 1.5 x 2 = 24.66 kg

Tulangan arah X Elv.+3.50


Ø Besi (mm)) =
10 = Berat/m (kg) x Bnyk Btg x Panjang x Lapis
10 = 0.62 x 10 x 1.5 x 2 = 18.495 kg
10 = 0.62 x 10 x 3.5 x 2 = 43.155 kg
10 = 0.62 x 26.66667 x 5 x 2 = 164.4 kg
10 = 0.62 x 10 x 5 x 2 = 61.65 kg
10 = 0.62 x 23.33333 x 4 x 2 = 115.08 kg
10 = 0.62 x 26.66667 x 4 x 2 = 131.52 kg
10 = 0.62 x 14 x 5.2 x 2 = 89.7624 kg
10 = 0.62 x 26.66667 x 4 x 2 = 131.52 kg
10 = 0.62 x 23.33333 x 4 x 2 = 115.08 kg
10 = 0.62 x 26.66667 x 4 x 2 = 131.52 kg
10 = 0.62 x 31.33333 x 1.85 x 2 = 71.4729 kg

Sekolah Tinggi Teknologi Payakumbuh


ANDIKA
201011025
RENCANA ANGGARAN BIAYA
Tulangan arah Y Elv.+3.50
Ø Besi (mm)) =
10 = Berat/m (kg) x Bnyk Btg x Panjang x Lapis
10 = 0.62 x 10 x 1.5 x 2 = 18.495 kg
10 = 0.62 x 23.33333 x 1.5 x 2 = 43.155 kg
10 = 0.62 x 33.33333 x 4 x 2 = 164.4 kg
10 = 0.62 x 33.33333 x 1.5 x 2 = 61.65 kg
10 = 0.62 x 26.66667 x 3.5 x 2 = 115.08 kg
10 = 0.62 x 26.66667 x 4 x 2 = 131.52 kg
10 = 0.62 x 34.66667 x 2.1 x 2 = 89.7624 kg
10 = 0.62 x 26.66667 x 4 x 2 = 131.52 kg
10 = 0.62 x 26.66667 x 3.5 x 2 = 115.08 kg
10 = 0.62 x 26.66667 x 4 x 2 = 131.52 kg
10 = 0.62 x 12.33333 x 4.7 x 2 = 71.4729 kg

Tulangan arah X Elv.+6.50


Ø Besi (mm)) =
10 = Berat/m (kg) x Bnyk Btg x Panjang x Lapis
10 = 0.62 x 20.66667 x 6.2 x 2 = 157.9884 kg
10 = 0.62 x 31.33333 x 2.6 x 2 = 100.4484 kg

Tulangan arah Y Elv.+6.50


Ø Besi (mm)) =
10 = Berat/m (kg) x Bnyk Btg x Panjang x Lapis
10 = 0.62 x 41.33333 x 3.1 x 2 = 157.9884 kg
10 = 0.62 x 17.33333 x 4.7 x 2 = 100.4484 kg
Total = 2713.504 kg

Tulangan arah X Elv.+7.00


Ø Besi (mm)) =
10 = Berat/m (kg) x Bnyk Btg x Panjang x Lapis
10 = 0.62 x 10 x 1.5 x 2 = 18.495 kg
10 = 0.62 x 13.33333 x 2 x 2 = 32.88 kg
10 = 0.62 x 6.666667 x 48.15 x 2 = 395.793 kg

Tulangan arah Y Elv.+7.00


Ø Besi (mm)) =
10 = Berat/m (kg) x Bnyk Btg x Panjang x Lapis
10 = 0.62 x 10 x 1.5 x 2 = 18.495 kg
10 = 0.62 x 13.33333 x 2 x 2 = 32.88 kg
10 = 0.62 x 321 x 1 x 1 = 197.8965 kg
Total = 696.4395 kg 696.4395 kg

p x l x n =
Elv. +3.00 = 1.85 x 1.25 x 1 = 2.3125 m2

Elv. +3.50 = 1.35 x 1.3 x 1 = 1.755 m2


= 3.35 x 1.3 x 1 = 4.355 m2

Sekolah Tinggi Teknologi Payakumbuh


ANDIKA
201011025
RENCANA ANGGARAN BIAYA
= 3.75 x 3.3 x 2 = 24.75 m2
= 3.35 x 1.05 x 1 = 3.5175 m2
= 3.8 x 3.75 x 1 = 14.25 m2

Elv. +6.50 = 3.85 x 2.35 x 1 = 9.0475 m2


= 3.35 x 1.85 x 1 = 6.1975 m2

Elv. +7.00 = 2.85 x 1.35 x 1 = 3.8475 m2


= 48.15 x 1 x 1 = 48.15 m2
= 118.1825 m2 118.1825 m2

PEKERJAAN TANGGA

Pek. Sloof 20/30 Beton Bertulang fc' 14,5 Mpa (k-175)


Beton
Panjang = 1.5 m
dimensi = 0.15 x 0.2 = 0.03 m2
Banyak = 1 buah
volume = 1.5 x 0.03 x 1
= 0.045 m3 0.045 m3

Pembesian
Besi utama
Besi yang dipakai (Ø) = 10 mm
Berat besi/M = 0.62 kg/m
= 4 buah
Banyak dalam penampang
Panjang besi 1 unit = 1.5 m
Berat besi utama = 0.6165 x 4 x 1.5
= 3.699 kg 3.699 kg

Besi Sengkang
Besi yang dipakai (Ø) = 8 mm
Berat besi/M = 0.39 kg/m
= 15 buah 15
Banyak dalam penampang
Panjang besi 1 unit = 0.64 m
Berat besi sengkang = 0.39456 x 15 x 0.64
= 3.787776 kg
Total = 3.699 + 3.787776 = 7.486776 kg 7.486776 kg

Bekisting
Panjang = 1.5 m
Lebar = 0.2 m
Sisi = 2 sisi
Volume = 1.5 x 0.2 x 2 x 1
= 0.6 m2 0.6 m2

Sekolah Tinggi Teknologi Payakumbuh


ANDIKA
201011025
RENCANA ANGGARAN BIAYA

Pek. Balok 15/20 Beton Bertulang fc' 14,5 Mpa (k-175) Elv +1.00
Beton
Tinggi = 4 m
dimensi = 0.15 x 0.2 = 0.03 m2
Banyak = 1 buah
volume = 4 x 0.03 x 1
= 0.12 m3 0.12 m3

Pembesian
Besi utama
Besi yang dipakai (Ø) = 10 mm
Berat besi/M = 0.62 kg/m
= 4 buah
Banyak dalam penampang
Panjang besi 1 unit = 4 m
Berat besi utama = 0.6165 x 4 x 4
= 9.864 kg 9.864 kg

Besi Sengkang
Besi yang dipakai (Ø) = 8 mm
Berat besi/M = 0.39 kg/m
= 40 buah 40
Banyak dalam penampang
Panjang besi 1 unit = 0.64 m
Berat besi sengkang = 0.39456 x 40 x 0.64
= 10.10074 kg
Total = 9.864 + 10.10074 = 19.96474 kg 19.96474 kg

Bekisting
Panjang = 4 m
Lebar = 0.2 m
Sisi = 2 sisi
Volume = 4 x 0.2 x 2 x 1
= 1.6 m2 1.6 m2

Pek. Balok 15/20 Beton Bertulang fc' 14,5 Mpa (k-175) Elv+3.50
Beton
Tinggi = 4 m
dimensi = 0.15 x 0.2 = 0.03 m2
Banyak = 1 buah
volume = 4 x 0.03 x 1
= 0.12 m3 0.12 m3

Pembesian
Besi utama
Besi yang dipakai (Ø) = 10 mm
Berat besi/M = 0.62 kg/m
Banyak dalam penampang = 4 buah

Sekolah Tinggi Teknologi Payakumbuh


ANDIKA
201011025
RENCANA ANGGARAN BIAYA

Panjang besi 1 unit = 4 m


Berat besi utama = 0.6165 x 4 x 4
= 9.864 kg 9.864 kg

Besi Sengkang
Besi yang dipakai (Ø) = 8 mm
Berat besi/M = 0.39 kg/m
= 40 buah 40
Banyak dalam penampang
Panjang besi 1 unit = 0.64 m
Berat besi sengkang = 0.39456 x 40 x 0.64
= 10.10074 kg
Total = 9.864 + 10.10074 = 19.96474 kg 19.96474 kg

Bekisting
Panjang = 4 m
Lebar = 0.2 m
Sisi = 2 sisi
Volume = 4 x 0.2 x 2 x 1
= 1.6 m2 1.6 m2

Pek. Pelat Lantai Tangga


p x l x t x n
= 1.8 x 1.5 x 0.12 x 1 = 0.324 m3
= 1.05 x 1.5 x 0.12 x 1 = 0.189 m3
= 2.9 x 1.5 x 0.12 x 1 = 0.522 m3
= 1.5 x 1.5 x 0.12 x 2 = 0.54 m3

= 0.3 x 0.2 x 0.6 x 19 = 0.342 m3


2 Total = 1.917 m3 1.917 m3

Tulangan Tangga Besi Ø12


Tulangan arah Y
Ø Besi (mm)) =
= Berat/m (kg) x Bnyk Btg x Panjang x Lapis
13 = 1.04 x 10 x 1.8 x 2 = 37.50786 kg
13 = 1.04 x 10 x 1.5 x 2 = 31.25655 kg
13 = 1.04 x 5.25 x 1.5 x 2 = 16.40969 kg
13 = 1.04 x 10 x 1.5 x 2 = 31.25655 kg
13 = 1.04 x 10 x 2.9 x 2 = 60.42933 kg
10 = 0.62 x 7 x 3.14 x 2 = 27.10134 kg
10 = 0.62 x 170 x 0.6 x 2 = 125.766 kg

Tulangan arah X
Ø Besi (mm)) =
= Berat/m (kg) x Bnyk Btg x Panjang x Lapis
13 = 1.04 x 5.333333 x 1.5 x 2 = 16.67016 kg
13 = 1.04 x 4 x 1.5 x 2 = 12.50262 kg
13 = 1.04 x 10 x 1.05 x 2 = 21.87959 kg

Sekolah Tinggi Teknologi Payakumbuh


ANDIKA
201011025
RENCANA ANGGARAN BIAYA
13 = 1.04 x 20 x 1.5 x 1 = 31.25655 kg
13 = 1.04 x 10 x 1.5 x 1 = 15.62828 kg
10 = 0.62 x 12 x 3.14 x 1 = 23.22972 kg
10 = 0.62 x 10 x 3.14 x 2 = 38.7162 kg
10 = 0.62 x 19.33333 x 3.14 x 2 = 74.85132 kg
10 = 0.62 x 10 x 3.14 x 2 = 38.7162 kg
Total = 603.1779 kg 603.1779 kg

Pek. Bekisting Tangga

p x l x n
= 1.8 x 1.5 x 1 = 2.7 m2
= 1.05 x 1.5 x 1 = 1.575 m2
= 2.9 x 1.5 x 1 = 4.35 m2
= 1.5 x 1.5 2 = 4.5 m2

= 0.3 x 0.2 x 19 = 0.57 m2


2 Total = 13.695 m2 13.695 m2

Pek. Afwerking Beton


= 13.695 m2

Pek. Pasangan granite 60x60


p x l x n =
= 1.8 x 1.5 x 1 = 2.7 m2
= 1.05 x 1.5 x 1 = 1.575 m2
= 2.9 x 1.5 x 1 = 4.35 m2
= 0.2 x 1.5 x 19 = 5.7 m2
= 1.5 x 1.5 x 2 = 4.5 m2
= 0.3 x 1.5 x 19 = 8.55 m2
Total = 27.375 m2 27.375 m2

PEKERJAAN BESI HOLLOW

Pek. Pagar Besi Hollow

Besi Hollow Type 1


Panjang = 2.43 m
Tinggi = 1.2 m
Banyak = 1 bh
Volume = 2.43 x 1.2 x 1 = 2.916 m2 2.916 m2

Besi Hollow Type 2


Panjang = 1.85 m
Tinggi = 1.2 m
Banyak = 1 bh
Volume = 1.85 x 1.2 x 1 = 2.22 m2 2.22 m2

Besi Hollow Type 3


Panjang = 1.73 m

Sekolah Tinggi Teknologi Payakumbuh


ANDIKA
201011025
RENCANA ANGGARAN BIAYA
Tinggi = 1.2 m
Banyak = 1 bh
Volume = 1.73 x 1.2 x 1 = 2.076 m2 2.076 m2

Besi Hollow Type 34


Panjang = 0.65 m
Tinggi = 1.2 m
Banyak = 2 bh
Volume = 0.65 x 1.2 x 2 = 1.56 m2

Besi Hollow Type 35


Panjang = 9.5 m
Tinggi = 1.2 m
Banyak = 1 bh
Volume = 9.5 x 1.2 x 1 = 11.4 m2

Besi Hollow Type 36


Panjang = 2 m
Tinggi = 0.8 m
Banyak = 1 bh
Volume = 2 x 0.8 x 1 = 1.6 m2

Besi Hollow Type 37


Panjang = 1.25 m
Tinggi = 0.8 m
Banyak = 1 bh
Volume = 1.25 x 0.8 x 1 = 1 m2

Besi Hollow Type 38


Panjang = 3.1 m
Tinggi = 0.8 m
Banyak = 1 bh
Volume = 3.1 x 0.8 x 1 = 2.48 m2
= 25.252 m2
PEKERJAAN DAPUR
p x t x n
Pas. Bata 1:4 = 2.25 x 0.8 x 1 = 1.8 m2 1.8 m2
= 2 x 0.8 x 1 = 1.6 m2 1.6 m2

Pek. Plesteran 1:2 + aci = 3.4 x 2 = 6.8 m2 6.8 m2

Pek. Meja Dapur = p x l x t x n


Plat 1:2 t:10cm = 2.25 x 0.8 x 0.8 x 1 = 1.44 m3 1.44 m3
= 2 x 0.8 x 0.8 x 1 = 1.28 m3

Tulangan Meja
Dapur Besi Ø 10

Tulangan Arah Y

Sekolah Tinggi Teknologi Payakumbuh


ANDIKA
201011025
RENCANA ANGGARAN BIAYA
Ø Besi (mm)) =
10 = Berat/m (kg) x Bnyk Btg x Panjang x Lapis
10 = 0.62 x 15 x 0.8 x 1 = 7.398 kg
10 = 0.62 x 5.333333 x 2 x 1 = 6.576 kg

Tulangan Arah X
Ø Besi (mm)) =
10 = Berat/m (kg) x Bnyk Btg x Panjang x Lapis
10 = 0.62 x 5.333333 x 2.25 x 1 = 7.398 kg
10 = 0.62 x 13.33333 x 0.8 x 1 = 6.576 kg
= 27.948 kg 27.948 kg

Pek. Afwerking = p x l x n
Beton Meja = 2.25 x 0.8 x 1 = 1.8 m2
= 2 x 0.8 x 1 = 1.6 m2

Pek. Keramik = p x l x n
30x30 Polos = 2.5 x 0.8 x 1 = 2 m2
= 0.8 x 0.8 X 2 = 1.28 m2
= 2 x 0.8 x 1 = 1.6 m2
Total = 4.88 m2 4.88 m2

PEKERJAAN INSTALASI LISTRIK

Pek. Instalasi Titik Lampu = 29 ttk

Pek. Istop Kontak = 12 bh

Pek. Saklar Ganda = 8 bh

Pek. Saklar Tunggal = 7 bh

Pek. Lampu Downlight = 7 bh

Pek. Lampu Esensial 40 Watt = 22 bh

PEKERJAAN SANITASI

Pipa Saluran Air Bersih 3/4" = 91.4 m

Pipa Saluran Air Kotor 4" = 30.3 m

Pipa Saluran Air FlourDrain 3" = 24.08 m

Sekolah Tinggi Teknologi Payakumbuh


ANDIKA
201011025
RENCANA ANGGARAN BIAYA
Bak Mandi = 1 bh

Kloset Duduk = 5 bh

FlourDrain = 6 bh

Shower = 5 bh

Cuci Piring Alumunium = 1 bh

Septic Tank = 2 unit

PEKERJAAN SELASAR

Pek. Galian Selasar

Panjang = 26.43 m
Tinggi = 0.1 m
Lebar = 0.2 m
Banyak = 1 bh
Volume = 26.43 x 0.1 x 0.2 x 1
= 0.5286 m3 0.5286 m3

Pek. Lantai Dasar Cor Beton K-100

Panjang = 26.43 m
Tinggi = 0.09 m
Lebar = 0.2 m
Banyak = 1 bh
Volume = 26.43 x 0.09 x 0.2 x 1
= 0.47574 m3 0.47574 m3

Pek. 1/2 Batu Bata 1:4

Panjang = 26.43 m
Tinggi = 0.17 m
Banyak = 1 bh
Volume = 26.43 x 0.17 x 1
= 4.4931 m2 4.4931 m3

Pek. 1Plesteran 1:4 + Aci

Panjang = 26.43 m
Tinggi = 0.2 m
Banyak = 1 bh
Volume = 26.43 x 0.2 x 1
= 5.286 m2 5.286 m3

Pek. Tanah Urug

Sekolah Tinggi Teknologi Payakumbuh


ANDIKA
201011025
RENCANA ANGGARAN BIAYA

Panjang = 26.43 m
Tinggi = 0.09 m
Lebar = 1 m
Banyak = 1 bh
Volume = 26.43 x 0.09 x 1 x 1
= 2.3787 m3 2.3787 m3

Pek. Pasir Urug

Panjang = 26.43 m
Tinggi = 0.1 m
Lebar = 1 m
Banyak = 1 bh
Volume = 26.43 x 0.1 x 1 x 1
= 2.643 m3 2.643 m3

Pek. Cor Beton K-100

Panjang = 26.43 m
Tinggi = 0.07 m
Lebar = 1 m
Banyak = 1 bh
Volume = 26.43 x 0.07 x 1 x 1
= 1.8501 m3 1.8501 m3

Pek. Keramik 30x30 Anti Slip

Panjang = 26.43 m
Lebar = 1 m
Banyak = 1 bh
Volume = 26.43 x 1 x 1
= 26.43 m2 26.43 m2

PEKERJAAN PENGECATAN

Dinding Bata = 1195.265 m2


Afwerking Beton = 13.695 m2
AfwerkingTangga = 191.1725 m2
Total = 1400.133 m2 1400.133 m2

Dibuat oleh :

ANDIKA
201011025

Sekolah Tinggi Teknologi Payakumbuh