EINRIP General Specification

Divisi 1 - Umum

TABLE OF CONTENTS

TABLE OF CONTENTS .........................................................................................................................................I

DIVISI I................................................................................................................................................................... 1

UMUM .................................................................................................................................................................... 1
SEKSI 1.1 ............................................................................................................................................................ 1
RINGKASAN PEKERJAAN .............................................................................................................................. 1
1.1.1 LINGKUP PEKERJAAN................................................................................................................ 1
1.1.2 KETENTUAN REKAYASA (ENGINEERING)............................................................................ 1
1.1.3 SISTEM SPESIFIKASI................................................................................................................... 1
1.1.4 PEMBAYARAN PEKERJAAN ....................................................................................................... 2

SEKSI 1.2 ............................................................................................................................................................ 3


MOBILISASI DAN DEMOBILISASI ................................................................................................................ 3
1.2.1 UMUM ............................................................................................................................................ 3
1.2.2 PROGRAM MOBILISASI............................................................................................................... 3
1.2.3 PENGUKURAN DAN PEMBAYARAN......................................................................................... 5

SEKSI 1.3 ............................................................................................................................................................ 6


KANTOR LAPANGAN DAN FASILITASNYA ............................................................................................... 6
1.3.1 UMUM ............................................................................................................................................ 6
1.3.2 KANTOR KONTRAKTOR DAN FASILITASNYA ....................................................................... 7
1.3.3 BENGKEL DAN GUDANG KONTRAKTOR ................................................................................ 7
1.3.4 KANTOR DAN AKOMODASI UNTUK DIREKSI PEKERJAAN................................................. 8
1.3.5 PENGUKURAN DAN PEMBAYARAN......................................................................................... 8

SEKSI 1.4 ............................................................................................................................................................ 9


FASILITAS DAN PELAYANAN PENGUJIAN................................................................................................ 9
1.4.1 UMUM ............................................................................................................................................ 9
1.4.2 FASILITAS LABORATORIUM DAN PENGUJIAN.................................................................... 10
1.4.3 PROSEDUR PELAKSANAAN ..................................................................................................... 15
1.4.4 PENGUKURAN DAN PEMBAYARAN....................................................................................... 16

SEKSI 1.5 .......................................................................................................................................................... 17


TRANSPORTASI DAN PENANGANAN........................................................................................................ 17
1.5.1 UMUM .......................................................................................................................................... 17
1.5.2 KETENTUAN PRA PELAKSANAAN ........................................................................................ 17
1.5.3 PELAKSANAAN.......................................................................................................................... 18
1.5.4 CARA PENGUKURAN DAN PEMBAYARAN ......................................................................... 18

SEKSI 1.6 .......................................................................................................................................................... 20


PEMBAYARAN SERTIFIKAT BULANAN ................................................................................................... 20
1.6.1 UMUM .......................................................................................................................................... 20
1.6.2 PENYIAPAN DAN PENYERAHAN ............................................................................................ 20
1.6.3 PENGESAHAN OLEH DIREKSI PEKERJAAN......................................................................... 22

SEKSI 1.7 .......................................................................................................................................................... 24


PEMBAYARAN SEMENTARA (PROVISIONAL SUMS) ............................................................................ 24
1.7.1 UMUM .......................................................................................................................................... 24

SEKSI 1.8 .......................................................................................................................................................... 25


MANAJEMEN LALU LINTAS AN KESELAMATAN................................................................................... 25
1.8.1 UMUM .......................................................................................................................................... 25
1.8.2 RENCANA MANAJEMEN LALU LINTAS DAN KESELAMATAN....................................... 25
1.8.3 URAIAN BAHAN DAN PERALATAN ...................................................................................... 28
1.8.4 PEKERJAAN JALAN ATAU JEMBATAN SEMENTARA.......................................................... 34
1.8.5 PEMELIHARAAN UNTUK KESELAMATAN LALU LINTAS ............................................... 35

1-i
EINRIP General Specification
Divisi 1 - Umum

1.8.6 PENGUKURAN DAN PEMBAYARAN ..................................................................................... 35

SEKSI 1.9 .......................................................................................................................................................... 38


REKAYASA LAPANGAN................................................................................................................................ 38
1.9.1 UMUM .......................................................................................................................................... 38
1.9.2 PEKERJAAN SURVEI LAPANGAN UNTUK REVISI MINOR.................................................. 38
1.9.3 PEKERJAAN SURVEI PELAKSANAAN RUTIN ....................................................................... 39
1.9.4 PENETAPAN TITIK PENGUKURAN.......................................................................................... 40
1.9.5 TENAGA AHLI REKAYASA LAPANGAN ................................................................................ 41
1.9.6 PENGENDALIAN MUTU BAHAN.............................................................................................. 41
1.9.7 DASAR PEMBAYARAN............................................................................................................. 41

SEKSI 1.10 ....................................................................................................................................................... 43


STANDAR RUJUKAN...................................................................................................................................... 43

SEKSI 1.11 ........................................................................................................................................................ 48


BAHAN DAN PENYIMPANAN...................................................................................................................... 48
1.11.1 UMUM .......................................................................................................................................... 48
1.11.2 PENGADAAN BAHAN ............................................................................................................... 48
1.11.3 PENYIMPANAN BAHAN ........................................................................................................... 49
1.11.4 PEMBAYARAN............................................................................................................................ 50

SEKSI 1.12 ........................................................................................................................................................ 51


JADWAL PELAKSANAAN ............................................................................................................................ 51
1.12.1 UMUM .......................................................................................................................................... 51
1.12.2 DETIL JADWAL PELAKSANAAN ............................................................................................. 51
1.12.3 REVISI PROGRAM (JADWAL PELAKSANAAN) ..................................................................... 52

SEKSI 1.13 ........................................................................................................................................................ 54


PROSEDUR VARIASI ..................................................................................................................................... 54
1.13.1 UMUM .......................................................................................................................................... 54
1.13.2 PROSEDUR AWAL VARIASI ..................................................................................................... 55
1.13.3 PELAKSANAAN VARIASI.......................................................................................................... 55
1.13.4 PELAKSANAAN ADDENDA ...................................................................................................... 56

SEKSI 1.14 ........................................................................................................................................................ 57


PENUTUPAN KONTRAK ................................................................................................................................ 57
1.14.1 UMUM .......................................................................................................................................... 57
1.14.2 SERTIKAT KINERJA ................................................................................................................... 57
1.14.3 SERTIFIKAT PEMBAYARAN AKHIR........................................................................................ 57
1.14.4 ADDENDUM PENUTUP.............................................................................................................. 58

SEKSI 1.15 ........................................................................................................................................................ 59


DOKUMEN REKAMAN PROYEK .................................................................................................................. 59
1.15.1 UMUM .......................................................................................................................................... 59
1.15.2 DOKUMENT REKAMAN PROYEK............................................................................................ 59
1.15.3 BAHAN REKAMAN PROYEK .................................................................................................... 60
1.15.4 PEMELIHARAAN DOKUMEN PELAKSANAAN PROYEK ................................................... 60
1.15.5 DOKUMEN REKAMAN AKHIR ................................................................................................. 61

SEKSI 1.16 ........................................................................................................................................................ 63


PEKERJAAN PEMBERSIHAN......................................................................................................................... 63
1.16.1 UMUM .......................................................................................................................................... 63
1.16.2 PEMBERSIHAN SELAMA PELAKSANAAN ........................................................................... 63
1.16.3 PEMBERSIHAN AKHIR .............................................................................................................. 64
1.16.4 DASAR PEMBAYARAN.............................................................................................................. 64

SEKSI 1.17 ........................................................................................................................................................ 65


USAHA PERLINDUNGAN LINGKUNGAN HIDUP....................................................................................... 65
1.17.1 UMUM .......................................................................................................................................... 65

1 - ii
EINRIP General Specification
Divisi 1 - Umum

1.17.2 UPAYA PENGELOLAAN LINGKUNGAN (UKL).................................................................... 66


1.17.3 IMPLEMENTASI STUDI LINGKUNGAN HIDUP YANG DIPERLUKAN ............................. 70
1.17.4 LAPORAN BULANAN................................................................................................................ 70
1.17.5 DASAR PEMBAYARAN............................................................................................................. 71

SEKSI 1.18 ....................................................................................................................................................... 82


PENGUJIAN PENGEBORAN......................................................................................................................... 82
1.18.1 UMUM .......................................................................................................................................... 82
1.18.2 PENGUJIAN BOR (LUBANG).................................................................................................... 82
1.18.3 PENGUKURAN DAN PEMBAYARAN ..................................................................................... 83

SEKSI 1.19 ....................................................................................................................................................... 84


RELOKASI UILITAS DAN PELAYANAN YANG ADA............................................................................... 84
1.19.1 URAIAN........................................................................................................................................ 84
1.19.2 PENGATURAN DENGAN PEJABAT SETEMPAT................................................................... 84
1.19.3 PEMERIKSAAN PEKERJAAN DAN RELOKASI FASILITAS ................................................ 84
1.19.4 JADWAL PEKERJAAN ............................................................................................................... 84
1.19.5 PELAKSANAAN.......................................................................................................................... 85
1.19.6 PENGUKURAN DAN PEMBAYARAN ..................................................................................... 86

SEKSI 1.20 ....................................................................................................................................................... 90


USULAN PERUBAHAN REKAYASA NILAI ............................................................................................. 87
1.20.1 USULAN PERUBAHAN REKAYASA NILAI (UPRN) OLEH KONTRAKTOR ...................... 87
1.20.2 LINGKUP REKAYASA NILAI ................................................................................................... 87
1.20.3 PENGAJUAN UPRN .................................................................................................................... 88
1.20.4 DASAR PEMBAYARAN............................................................................................................. 91
1.20.5 PADA SAAT PEKERJAAN RANCANGAN UPRN SELESAI .................................................. 92

1 - iii
EINRIP General Specification
Divisi 1 - Umum

DIVISI I
UMUM

SEKSI 1.1
RINGKASAN PEKERJAAN

1.1.1 LINGKUP PEKERJAAN

Untuk lingkup pekerjaan yang dicakup dalam Spesifikasi ini silahkan merujuk Bagian 2
Seksi 1 Lingkup Pekerjaan.

1.1.2 KETENTUAN REKAYASA (ENGINEERING)

- Uraian dari pekerjaan lapangan


- Tahap lingkup rinjauan terhadap rancangan
- Dalam EINRIP hanya terdapat tinjauan minor (minor review) karena rancangan detil
telah diselesaikan sebelum penetapan pemenang.

1.1.3 SISTEM SPESIFIKASI

Secara umum, setiap mata pembayaran dalam Spesifikasi ini diatur dalam bentuk berikut
ini :

1.1.3.1 Umum

Bagian ini menguraikan hal-hal yang umum sehubungan dengan pekerjaan/kegiatan yang
akan dilaksanakan oleh Kontraktor.

1.1.3.2 Bahan

Bagian ini menguraikan spesifikasi dan ketentuan bahan yang diperlukan dalam pekerjaan secara
terinci. Secara umum, uraian material terdiri dari ketentuan-ketentuan bahan baku, bahan campuran
dan bahan pabrikan.

1.1.3.3 Pelaksanaan

Bagian ini menguraikan petunjuk pelaksanaan secara terinci. Termasuk ketentuan-ketentuan


peralatan, percobaan dan pelaksanaan.

1.1.3.4 Pengendalian Mutu

Bagian ini menguraikan perintah dan petunjuk yang lengkap untuk mencapai mutu yang
disyaratkan.

1.1.3.5 Pengukuran dan Pembayaran

Bagian ini menguraikan cara pengukuran dan pembayaran kepada kontraktor untuk mata
pembayaran yang dicakup dalam spesifikasi.

1 -1
EINRIP General Specification
Divisi 1 - Umum

1.1.4 PEMBAYARAN PEKERJAAN

1.1.4.1 Kontraktor harus melaksanakan Pekerjaan sesuai dengan detil yang diberikan dalam
Gambar, dan sebagaimana yang diperintahkan oleh Direksi Pekerjaan, dimana sebagian
besar pekerjaan tersebut akan dibayar menurut sistem Harga Satuan. Pembayaran kepada
Kontraktor harus dilakukan berdasarkan kuantitas aktual yang diukur pada masing-masing
Mata Pembayaran dalam Kontrak yang telah dilaksanakan sesuai dengan Seksi yang
berkaitan dari Spesifikasi ini, baik cara pengukuran maupun pembayarannya. Pembayaran
juga akan dilakukan berdasarkan pengukuran dan pembayaran Lump Sum untuk mata
pembayaran Mobilisasi, Manajemen Lalu Lintas dan Keselamatan, Cofferdams dan
Pengeringan Air, dan Pekerjaan Pemeliharaan Rutin, serta pengukuran dan pembayaran
untuk pekerjaan yang diperintahkan atas dasar Pekerjaan Harian.

1.1.4.2 Pembayaran yang diberikan kepada Kontraktor harus mencakup kompensasi penuh untuk
seluruh biaya yang dikeluarkan seluruh pekerja, bahan, peralatan konstruksi,
pengorganisasian pekerjaan, biaya tak terduga, keuntungan, retribusi, pajak, pengamanan
pekerjaan yang telah selesai dikerjakan, pembayaran kepada pihak ketiga untuk tanah atau
untuk penggunaan atas tanah, atau untuk kerusakan bangunan (property), maupun untuk
semua biaya pekerjaan tambah yang tidak dibayar secara terpisah, seperti pembuatan
drainase sementara untuk melindungi pekerjaan selama pelaksanaan, pengangkutan,
perkakas, peledakan dan bahan untuk peledakan, penurapan, penyangga, pembuatan tempat
kerja (staging), pembuatan tanda sumbu (centering) dan penopang dan lain-lain biaya yang
diperlukan atau lazim dipakai untuk pelaksanaan dan penyelesaian yang sebagaimana
mestinya dari Pekerjaan tersebut.

1 -2
EINRIP General Specification
Divisi 1 - Umum

SEKSI 1.2

MOBILISASI DAN DEMOBILISASI

1.2.1 UMUM

1.2.1.1 Uraian

Cakupan kegiatan mobilisasi yang diperlukan dalam Kontrak ini akan tergantung pada
jenis dan volume pekerjaan yang harus dilaksanakan, sebagaimana disyaratkan di bagian-
bagian lain dari Dokumen Kontrak, dan secara umum harus memenuhi berikut:

1.2.1.1 Ketentuan Mobilisasi untuk semua Kontrak

a) Pembelian atau penyewaan lahan untuk base camp Kontraktor, jalan alih sementara,
untuk penyimpanan peralatan, untuk bangunan kantor, rumah, atauu penggunaan lain
yang perlu untuk pelaksanaan pelaksanaan.

b) Mobilisasi dan pemasangan Instalasi Konstruksi dan semua peralatan yang diperlukan
untuk pelaksanaan pekerjaan, dari lokasi asal sampai lokasi lapangan di mana instalasi
dan peralatan itu digunakan menurut Kontrak ini.

c) Penyediaan dan pemeliharaan base camp Kontraktor, jika perlu termasuk kantor
lapangan, tempat tinggal, bengkel, gudang, dan sebagainya.

d) Perkuatan jembatan lama jika perlu, untuk Pengangkutan Peralatan Konstruksi.

1.2.1.3 Ketentuan mobilisasi Kantor Lapangan dan Fasilitasnya untuk Direksi Pekerjaan

Penyediaan dan pemeliharaan Kantor Lapangan dan Fasilitasnya dirinci dalam Seksi 1.3

1.2.1.4 Ketentuan mobilisasi Fasilitas Pengendalian Mutu

Penyediaan dan pemeliharaan laboratorium lapangan beserta peralatan laboratorium


sebagaimana dirinci dalam Seksi 1.4 dari Spesifikasi ini. Gedung laboratorium dan
peralatannya, yang dipasok menurut Kontrak ini, akan tetap menjadi milik Kontraktor pada
waktu proyek selesai.

1.2.1.5 Kegiatan Demobilisasi untuk semua Kontrak

Pembongkaran tempat kerja oleh Kontraktor pada saat akhir Waktu untuk Penyelesaian
Pekerjaan, termasuk pemindahan semua instalasi, instalasi dan peralatan konstruksi dari tanah
milik Pemerintah dan pengembalian kondisi tempat kerja menjadi kondisi seperti semula
sebelum Tanggal Mulai Kerja dari Pekerjaan. Dalam hal ini, pemindahan peralatan dari tanah
milik Pemerintah tidak akan mengurangi kewajiban Kontraktor untuk menyediakan semua
sumber daya yang diperlukan selama Periode Pemberitahuan Cacat Mutu seperti keuangan,
manajemen, peralatan, pekerja dan bahan.

1.2.2 PROGRAM MOBILISASI

1.2.1.1 Dalam waktu 7 hari setelah Perjanjian Kontrak ditandatangani, Kontraktor harus menghadiri
Rapat Pra Pelaksanaan dengan Pemilik, Direksi Pekerjaan dan Wakil Direksi Pekerjaan (jika
ada), untuk membahas semua hal baik yang teknis maupun yang non teknis dalam proyek ini.
Agenda dalam rapat harus mencakup (tidak terbatas pada) berikut ini :

a) Pendahuluan

1 -3
EINRIP General Specification
Divisi 1 - Umum

b) Pertukaran Struktur Organisasi


i) Struktur Organisasi Pemilik
ii) Struktur Organisasi Kontraktor
iii) Struktur Organisasi Direksi Pekerjaan
c) Masalah-masalah Lapangan
i) Daerah Milik Jalan
ii) Sumber-sumber Bahan
iii) Lokasi Base Camp
d) Persetujuan
e) Pengajuan
f) Dokumen Pelaksanaan Akhir
g) Tahapan dan Kejadian Penting
h) Rencana Kerja
i) Bagan Jadwal Pelaksanaan yang menunjukkan waktu dan urutan kegiatan
utama yang membentuk Pekerjaaan
ii) Rencana Mobilisasi
iii) Rencana Relokasi
iv) Rencana Kesehatan dan Keselamatan
v) Rencana Mutu
vi) Rencana Manajemen Lalu Lintas dan Keselamatan
vii) Rencana Inspeksi dan Pengujian
viii) Rencana Manajemen Lingkungan
i) Komunikasi dan korespondensi
j) Rapat koordinasi, jadwal dan banyaknya
k) Pelaporan dan pemantauan

1.2.2.2 Setelah rapat ini, dalam waktu 15 hari setelah Rapat Pra Pelaksanaan, Kontraktor harus
menyerahkan kepada Direksi Pekerjaan untuk mendapat persetujuannya program mobilisasi
yang terinci (termasuk program perkuatan jembatan, bila ada) dan jadwal pelaksanaan yang
terinci yang menunjukkan bagaimana Pekerjaan harus diselesaikan dalam Waktu untuk
Penyelesaian Pekerjaan yang tercantum dalam Kontrak.

1.2.2.3 Program mobilisasi harus menetapkan waktu untuk semua kegiatan mobilisasi yang
disyaratkan dalam Pasal 1.2.1 dan harus mencakup informasi tambahan berikut :

a) Lokasi base camp Kontraktor dengan denah lokasi umum dan denah detil di lapangan
yang menunjukkan lokasi kantor Kontraktor, bengkel, gudang dan perlatan konstruksi
utama serta laboratorium bilamana fasilitas tersebut termasuk dalam cakupan Kontrak.

b) Jadwal Pengiriman Peralatan yang menunjukkan lokasi asal dari semua peralatan yang
tercantum dalam Daftar Peralatan yang diusulkan dalam Penawaran, bersama dengan
usulan cara pengangkutan dan jadwal kedatangan peralatan di lapangan. Jadwal ini
harus dapat diterima Direksi Pekerjaan sebagaimana tanggal kedatangan, jenis, ukuran,
kapasitas atau power dan kuantitas jenis-jenis yang tercakup. Untuk masing-masing
peralatan, jenis, buatan, nomor identifikasi dan tahun pembuatan, dan apakah telah
direkondisi atau bukan, harus dicantumkan. Kontraktor harus sesuai pada waktunya
menempatkan di Lapangan semua Peralatan Konstruksi yang terdaftar.

c) Setiap perubahan pada peralatan maupun personil yang diusulkan dalam Pena-waran
harus memperoleh persetujuan dari Direski Pekerjaan.

d) Suatu daftar detil yang menunjukkan struktur yang memerlukan perkuatan agar aman
dilewati alat-alat berat, usulan metodologi pelaksanaan dan jadwal tanggal mulai dan
tanggal selesai untuk perkuatan setiap struktur.

1 -4
EINRIP General Specification
Divisi 1 - Umum

e) Suatu jadwal kemajuan yang lengkap dalam format bagan balok (bar chart) yang
menunjukkan tiap kegiatan mobilisasi utama dan suatu kurva kemajuan untuk
menyatakan persentase kemajuan mobilisasi.

1.2.2.4 Periode Mobilisasi

Program mobilisasi harus selesai dalam 90 hari sejak Tanggal Mulai Kerja dari Pekerjaan
kecuali fasilitas dan pelayanan pengemdalian mutu harus terpasang dan beroperasi dalam
60 hari. Denda akan dikenakan sesuai dengan Pasal 1.2.3.2 untuk keterlambatan.

1.2.3 PENGUKURAN DAN PEMBAYARAN

1.2.3.1 Pengukuran

Pengukuran kemajuan mobilisasi akan ditentukan oleh Direksi Pekerjaan atas dasar jadwal
kemajuan mobilisasi yang lengkap dan telah disetujui seperti yang diuraikan dalam Pasal
1.2.2.2 diatas.

1.2.3.2 Dasar Pembayaran

Mobilisasi harus dibayar atas dasar lump sum menurut jadwal pembayaran yang diberikan di
bawah, dimana pembayaran tersebut merupakan kompensasi penuh untuk penyediaan dan
pemasangan semua peralatan, dan untuk semua pekerja, bahan, perkakas, dan biaya lainnya
yang perlu untuk menyelesaikan pekerjaan yang diuraikan dalam Pasal 1.2.1.1 dari Spesifikasi
ini. Walaupun demikian Direksi Pekerjaan dapat, setiap saat selama pelaksanaan pekerjaan,
memerintahkan Kontraktor untuk menambah peralatan yang dianggap perlu tanpa
menyebabkan perubahan harga lump sum untuk Mobilisasi.

 50 % (lima puluh persen) bila mobilisasi 50 % selesai, dan pelayanan atau fasilitas
pengujian laboratorium telah lengkap dimobilisasi.

 20 % (dua puluh persen) bila semua peralatan utama berada di lapangan dan diterima
oleh Direksi Pekerjaan.

 30 % (tiga puluh persen) bila demobilisasi selesai dilaksanakan.

Bilamana Kontraktor tidak menyelesaikan mobilisasi sesuai dengan salah satu dari kedua
batas waktu yang disyaratkan dalam Pasal 1.2.1.4 maka jumlah yang disahkan Direksi
Pekerjaan untuk pembayaran adalah persentase angsuran penuh dari harga lump sum
Mobilisasi dikurangi sejumlah dari 1 % (satu persen) nilai angsuran untuk setiap
keterlambatan satu hari dalam penyelesaian sampai maksimum 50 (lima puluh) hari.

Nomor Mata Uraian Satuan


Pembayaran Pengukuran

1.2 Mobilisasi Lump Sum

1 -5
EINRIP General Specification
Divisi 1 - Umum

SEKSI 1.3

KANTOR LAPANGAN DAN FASILITASNYA

1.3.1 UMUM

1.3.1.1 Uraian Pekerjaan

Menurut Seksi ini, Kontraktor harus membangun, menyediakan, memasang, memelihara,


membersihkan, menjaga, dan pada saat selesainya Kontrak harus memindahkan atau
membuang semua bangunan kantor darurat, gudang-gudang penyimpanan, barak-barak
pekerja dan bengkel-bengkel yang dibutuhkan untuk pengelolaan dan pengawasan proyek.

1.3.1.2 Ketentuan Umum

a) Kontraktor harus mentaati semua peraturan-peraturan Nasional maupun Daerah.

b) Kantor dan fasilitasnya harus ditempatkan sesuai dengan Lokasi Umum dan Denah
Lapangan yang telah disetujui dan merupakan bagian dari Program Mobilisasi seperti
dirinci dalam Pasal 1.2.2.2, dimana penempatannya harus diusahakan sedekat mungkin
dengan daerah kerja (site) dan telah mendapat persetujuan dari Direksi Pekerjaan.

c) Bangunan untuk kantor dan fasilitasnya harus ditempatkan sedemikian rupa sehingga
terbebas dari polusi yang dihasilkan oleh kegiatan pelaksanaan.

d) Bangunan yang dibuat harus mempunyai kekuatan struktural yang baik, tahan cuaca,
dan elevasi lantai yang lebih tinggi dari tanah di sekitarnya.

e) Bangunan untuk penyimpanan bahan harus diberi bahan pelindung yang cocok
sehingga bahan-bahan yang disimpan tidak akan mengalami kerusakan.

f) Sesuai pilihan Kontraktor, bangunan dapat dibuat di tempat atau dirakit dari komponen-
komponen pra-fabrikasi.

g) Kantor lapangan dan gudang sementara harus didirikan diatas pondasi yang mantap dan
dilengkapi dengan penghubung dengan untuk pelayanan utilitas.

h) Bahan, peralatan dan perlengkapan yang digunakan untuk bangunan dapat baru atau
bekas pakai, tetapi dengan syarat harus dapat berfingsi, cocok dengan maksud
pemakaiannya dan tidak bertentangan dengan perundang-undangan dan peraturan yang
berlaku.

i) Lahan untuk kantor lapangan dan semacamnya harus ditimbun dan diratakan sehingga
layak untuk ditempati bangunan, bebas dari genangan air, diberi pagar keliling, dan
dilengkapi minimum dengan jalan masuk dari kerikil serta tempat parkir.

j) Kontraktor harus menyediakan alat pemadam kebakaran yang memadai di seluruh


barak, kantor, gudang dan bengkel.

1 -6
EINRIP General Specification
Divisi 1 - Umum

1.3.2 KANTOR KONTRAKTOR DAN FASILITASNYA

1.3.2.1 Umum

Kontraktor harus menyediakan kantor lapangan yang memadai untuk Kontraktor dan Direksi
Pekerjaan, akomodasi dan fasilitas untuk personil Kontraktor sehingga memenuhi kebutuhan
proyek sesuai Seksi dari Spesifikasi ini.

1.3.2.2 Ukuran

Ukuran sesuai untuk kebutuhan umum dan harus menyediakan sebuah ruangan yang
digunakan untuk rapat kemajuan pekerjaan.

1.3.2.3 Telepon

Telepon satu atau dua arah harus disediakan dan harus dapat beroperasi selama Kontrak.

Bilamana sambungan saluran telepon tidak mungkin disediakan, atau tidak dapat disediakan
dalam periode mobilisasi, maka Kontraktor harus menyediakan suatu sistem radio pemancar
yang dapat berkomunikasi 2 arah (2-way) dengan jelas dan dapat diandalkan antara kantor
Pemilik di Ibukota Propinsi dan titik terjauh di lapangan. Sistem radio ini harus paling sedikit
mempunyai 6 (enam) stasiun yang mampu untuk mengirim dan menerima pesan secara lisan,
yang akan dipasang dan digunakan sesuai dengan petunjuk dari Direksi Pekerjaan.

1.3.2.4 Perlengkapan dalam Ruang Rapat dan Ruang Penyimpanan Dokumentasi Proyek

a) Meja rapat dengan kursi untuk paling sedikit 8 orang

b) Rak atau laci untuk penyimpanan gambar dan arsip untuk Dokumentasi Proyek secara
vertikal atau horisontal, yang ditempatkan di dalam atau dekat dengan ruang rapat.

1.3.2.5 Kantor Pendukung

Bilamana Kontraktor menganggap perlu untuk mendirikan satu kantor pendukung atau lebih,
yang akan digunakan untuk keperluan sendiri pada jarak 50 km atau lebih dari kantor utama di
lapangan, maka Kontraktor harus menyediakan, memelihara dan melengkapi satu ruangan
pada setiap kantor pendukung dengan ukuran sekitar 12 meter persegi yang akan digunakan
oleh Staf Direksi Pekerjaan untuk setiap kantor pendukung.

1.3.3 BENGKEL DAN GUDANG KONTRAKTOR

1.3.3.1 Kontraktor harus menyediakan sebuah bengkel di lapangan yang diberi perlengkapan yang
memadai serta dilengkapi dengan daya listrik, sehingga dapat digunakan untuk memperbaiki
peralatan yang digunakan dalam pelaksanaan Pekerjaan. Sebuah gudang untuk penyimpanan
suku cadang juga harus disediakan.

1.3.3.2 Bengkel tersebut harus dikelola oleh seorang kepala bengkel yang mampu melakukan
perbaikan mekanis dan memiliki sejumlah tenaga pembantu yang terlatih.

1 -7
EINRIP General Specification
Divisi 1 - Umum

1.3.4 KANTOR DAN AKOMODASI UNTUK DIREKSI PEKERJAAN

Ketentuan ini akan disediakan dalam Kontrak lain yang terpisah.

1.3.5 PENGUKURAN DAN PEMBAYARAN

Bangunan yang diuraikan dalam Seksi ini akan dibayar menurut pembayaran Lump Sum
untuk Mobilisasi sesuai dengan Seksi 1.2 dari Spesifikasi ini, dimana pembayaran harus
dianggap kompensasi penuh untuk pembuatan, penyediaan, pelayanan, pemeliharaan,
pembersihan dan pembongkaran semua bangunan tersebut setelah Pekerjaan selesai.

1 -8
EINRIP General Specification
Divisi 1 - Umum

SEKSI 1.4

FASILITAS DAN PELAYANAN PENGUJIAN

1.4.1 UMUM

1.4.1.1 Uraian

Pekerjaan ini mencakup penyediaan bahan, fasilitas, pekerja, pelayanan dan hal-hal lain
yang diperlukan untuk melaksanakan pengujian yang disyaratkan, dan penyediaan gedung
laboratorium dan peralatannya bilamana secara khusus dimasukkan dalam lingkup Kontrak
ini. Kontraktor harus bertanggungjawab atas pelaksanaan semua pengujian menurut
perintah dan pengawasan dari Direksi Pekerjaan. Daftar Peralatan Laboratorium yang
mungkin diperlukan untuk pekerjaan pengujian diberikan dalam Lampiran 1.4.A dari
Spesifikasi ini.

1.4.1.2 Lokasi Pengujian Pengendalian Mutu

Kontrakto harus melaksanakan pengujian pengendalian mutu di laboratorium lapangan atau di


lapangan atau di laboratorium lain yang disetujui oleh Direksi Pekerjaan.

1.4.1.3 Pekerjaan Yang Tidak Termasuk Dalam Seksi Ini

Pengujian yang dilaksanakan oleh Pemilik dan Direksi Pekerjaan.

1.4.1.4 Pengajuan Kesiapan Kerja

a) Usulan labaratorium pengujian : detil-detil dari mobilisasi laboratorium lapangan dan


peralatannya harus disediakan sebagai bagian dari program mobilisasi.

b) Usulan personil penguji : disertai dengan data-data yang diperlukan, suatu daftar
personil beserta Daftar Riwayat Hidup semua teknisi laboratorium yang diusulkan
Kontraktor untuk memriksa dan menguji menurut Kontrak ini harus diserahkan.

c) Jadwal pengujian : jadwal induk (master schedule) semua pekerjaan yang akan diuji.
Dengan koordinasi dengan jadwal pelaksanaan (construction schedule) dapat ditentukan
tanggal sementara untuk masing-masing kegiatan pengujian. Jadwal kegiatan pengujian
ini harus diserahkan kepada Direksi Pekerjaan dalam formulir pendahuluan
(preliminary form) untuk dievaluasi pada setiap awal bulan.

d) Formulir pengujian : Dalam waktu 60 (enam puluh) hari setelah Tanggal Mulai Kerja
usulan formulir pengujian standar yang akan digunakan dalam Kontrak, semua jenis
pengujian yang disyaratkan dalam Spesifikasi, harus diserahkan kepada Direksi
Pekerjaaan untuk mendapat persetujuan. Bilamana Kontraktor sedemikian memilih
maka Direksi Pekerjaan dapat memerintahkan Kontraktor untuk menggunakan formulir
alternative.

1.4.1.1 Tahapan-tahapan Penentu

Kontraktor harus memberitahu kepada Direksi Pekerjaan, dan Direksi Pekerjaan atau
wakilnya akan memeriksa dan menyetujui tahap pekerjaan berikut sebelum dilaksanakan
pekerjaan diatasnya.

(a) Penetapan Titik Pengukuran


(b) Elevasi Lapangan

1 -9
EINRIP General Specification
Divisi 1 - Umum

(c) Pengujian Tiang Pancang


(d) Galian Pondasi Jembatan
(e) Penulangan Baja dan Cetakan sebelum pengecoran beton
(f) Permukaan Tanah Dasar
(g) Permukaan Pondasi Kelas B yang telah dipadatkan
(h) Permukaan Pondasi Kelas A yang telah dipadatkan termasuk proof rolling, impact
hammer atau pengujian lain yang dinominasi oleh Direksi Pekerjaan.
(i) Penyiapan aspal lama untuk pelapisan ulang
(j) Setiap lapisan aspal
(k) Gorong-gorong pipa, strukur drainase
(l) Saluran tanah dasar, saluran buangan udara dan timbunan yang rembes
(m) Utilitas di bawah tanah

Direksi Pekerjaan dapat menominasi kegiatan lain bilamana inspeksi diperlukan, dan juga
menominasi setiap pengujian yang harus disediakan sebelum memberikan persetujuan
untuk melaksanakan pekerjaan diatasnya. Untuk masing-masing dari tahap dan kegiatan
yang disebutkan, Direksi Pekerjaan dan Kontraktor harus menyepakati prosedur, tempat
dan waktu pemberitahuan untuk menginspeksi. Kontraktor tidak terikat untuk menunda
pekerjaan jika Direksi Pekerjaan atau wakilnya tidak hadir pada jam yang ditentukan
asalkan pemberitahuan telah diberikan dengan tepat, dan asalkan semua ketentuan
pelaksanaan telah dipenuhi.

1.4.2 FASILITAS LABORATORIUM DAN PENGUJIAN

1.4.2.1 Kontraktor harus menyediakan pelayanan pengujian dan/atau fasilitas laboratorium


sebagaimana disyaratkan untuk memenuhi seluruh ketentuan pengendalian mutu dari
Spesifikasi ini.

1.4.2.2 Bilamana secara khusus dimasukkan dalam lingkup Kontrak ini, maka Kontraktor harus
menyediakan dan memelihara sebuah laboratorium lengkap dengan peralatannya di lapangan,
sesuai dengan ketentuan berikut :

a) Tempat Kerja

i) Laboratorium haruslah sebuah bangunan terpisah yang ditempatkan sesuai


dengan Lokasi Umum dan Denah Tempat Kerja yang telah disetujui dan
merupakan bagian dari Program Mobilisasi. Lokasi laboratorium harus
ditempatkan sedemikian rupa sehingga mempunyai jarak tertentu dari peralatan
konstruksi, bebas dari polusi dan gangguan berupa getaran selama pengoperasian
peralatan.

ii) Denah bangunan harus sesuai dengan Gambar atau sebagaimana yang
diperintahkan oleh Direksi Pekerjaaan untuk akomodasi dan pengope-rasian
perlengkapan yang diperlukan untuk pelaksanaan semua pengujian yang
disyaratkan atau diperlukan dan juga untuk menyediakan fasilitas kantor untuk
personil penguji baik dari Kontraktor maupun dari Direksi Pekerjaan.

iii) Bangunan harus dilengkapi dengan lantai beton beserta fasilitas pem-buangan air
kotor, dan dilengkapi dengan dua buah pendingin udara (air conditioning)
masing-masing berkapasitas 1,5 PK, serta harus memenuhi semua ketentuan
lainnya dalam Pasal 1.3.1.2 dari Spesifikasi ini.

iv) Perlengkapan di dalam ruangan bangunan harus terdiri atas meja kerja, lemari,
ruang penyimpan yang dapat dikunci, tangki perawatan, laci arsip (filing

1 -10
EINRIP General Specification
Divisi 1 - Umum

cabinet), meja dan kursi dengan mutu standar dan jumlah yang mencukupi
kebutuhan.

b) Peralatan dan Perlengkapan

Peralatan dan perlengkapan laboratorium yang terdaftar di bawah ini harus disediakan
dan dapat dioperasikan sesuai dengan Pasal 1.2.2.4 dari Spesifkasi ini.

Jenis dan kuantitas peralatan laboratorium yang ditunjukkan dalam daftar ini
diberikan sebagai petunjuk saja sebagai peralatan laboratorium minimum yang
diperlukan untuk proyek. Setiap kekurangan peralatan pengujian yang diperlukan
seperti yang tercantum di dalam daftar ini dengan cara apapun tidak akan
membebaskan tanggung jawab Kontraktor secara penuh untuk melaksanakan semua
pekerjaan pengujian sesuai Spesifikasi atau sebagaimana yang diperintahkan oleh
Direksi Pekerjaan.

URAIAN KUANTITAS

1. PEMERIKSAAN TANAH

1.1 Pemeriksaan Kepadatan :

Standard Proctor mould 5


Standard Proctor hammer 1
Modified compaction mould 5
Modified compaction hammer 1
Straight edge 1
Sample ejector 1
Mixing spoon 1
Mixing trowel 1
Spatula 1
Mixing Pan 5
Aluminium pan 25 cm diameter 1
Wash bottle 1
Moisture cans 36

1.2 CBR Laboratorium :

Mechanical loading press 1


6000 lbs capacity Proving ring 1
CBR moulds 6
Spacer disk 6
Swell plate surcharge plate 6
Tripod attachment 6
Swell dial indicator 6
Surcharge weight 6
Slotted surcharge weight 6
Steel cutting edge 1

1 -11
EINRIP General Specification
Divisi 1 - Umum

URAIAN KUANTITAS

1.3 Berat Jenis :

Pycnometer bottles of 100 cc capacity 3


Porcelain mortar and pestle 1
Hot plate, 1000 watts, 220 volts 50 cycle 1

1.4 Batas-batas Atterberg :

Standard liquid limit device 1


ASTM grooving tool 1
Evaporating dish 3
Flexible spatula 2
100 cm graduated cylinder 2
Casagrande grooving tool 1
Plastic limit glass plate 1

1.5 Analisa Saringan :

Hydrometer jars 3
Mechanical stirrer, electric powered 220 V 50 cycle 1
Dispersion cups with baffles 2
Hydrometer, scale 0 - 60 gr 1
Set brass sieves, 8 inches diameter, 75 mm, 50, 38, 25, 19, 12.5, 9.5,
No. 4, 10, 30, 60, 100 including cover and pan 2
No. 200 brass sieves 4
Wet washing sieve 1
50 ml. Graduated cylinder 1
Sieve brushes for fine sieve 2
Sieve brushes for coarse sieves 2

1.6 Pemeriksaan Kepadatan Lapangan dengan Metode Kerucut Pasir (Sand Cone) :

Sand cone 1
Replacement jug 1
Field density plate 1
Spoon 1
Steel chisel, 1 inch 1
Rubber mallet 1
Sand scoop 1
1 gallon field cans 6

1.7 Kadar Air :

Speedy, moisture tester, 26 grams capacity 1


Cans “Speedy” reagent 6

1 -12
EINRIP General Specification
Divisi 1 - Umum

URAIAN KUANTITAS

2. PEMERIKSAAN ASPAL

2.1 Pengujian Metode Marshall :

Stability compression machine 220 volt 50 cycles complete with 6000


lbs proving ring 1
Stability compaction mould 4” 15
Stability compaction mould 6” (if AC-Base to be used) 15
Mechanical compaction hammer for 4” mould 1
Mechanical compaction hammer for 6” mould (if AC-Base to be used) 1
Mould holder for 4” mould 1
Mould holder for 6” mould (if AC-Base to be used) 1
Stability mould 4” 1
Stability mould 6” (if AC-Base to be used) 1
Dial flow indicator 1
Pedestal 1
Water bath 220 V 50 cycle 1
Sample extractor 1
Stainless steel mixing bowls 2

2.2 Pemeriksaan Ekstraksi dengan Metode Sentrifugal :

Centrifuge extraction, 1500 gram capacity, 220 V 50 cycle 1


Boxes filter paper rings (100 - box) 10
Extractor bowl 1
Bowl cover 1
Bowl nut 1

2.3 Pemeriksaan Ekstraksi dengan Metode Refluks :

Reflux extractor set, 1000 gram capacity 1


Boxes filter paper (50 - box) 1

2.4 Berat Jenis Agregat Kasar :

Density Basket 1
Sample Splitter 1” 1
Sample Splitter 1/2” 1

2.5 Berat Jenis Agregat Halus :

Cone 1
Tamper 1
Pycnometer 1
Thermometer (Glass), 0 – 150 0 C 3
Desiccator 1

1 -13
EINRIP General Specification
Divisi 1 - Umum

URAIAN KUANTITAS

2.6 Kadar Pori Dalam Campuran (Metode Akurat) :

200 cc Conical Flask with neck large enough to admit 25 mm aggregate,


with airtight ground glass stoppers 2
Vacuum pump ( + special oil) 1
Rubber tubing 1
Warm air fan 1

2.7 Pengeboran Benda Uji Inti :

Core drill machine, 7 HP, 4 cycle 1


9” extension shaft 1
18” strap wrench 1
Diamond bit 4” diameter (resettable) 2
Expanding adaptor 1

2.8 Termometer Logam :

0 - 100 0 Metal Thermometer 1


0 - 250 0 Metal Thermometer 1

2.9 Perlengkapan dan Peralatan :

Heavy duty balance complete with set of weights, scoop and


counterweight 1
Triple beam scale complete with set of weights 1
Generator, 10 kVA 1
Double wall oven, 1600 W 240 volt 50 cycle 2
Plastic funnels 3
Sodium hexametaphosphate 1 lb.
Pairs asbestos gloves 2
Laboratory tongs 2

2.10 Penetrometer :

Penetration Apparatus 1
Penetration Nedle 2
Sample Container diametre 55 mm, internal depth 35 mm 6
Water Batch min.10 litres, 25 + 0.1°C 1
Transfer Dish, min. 350 ml 1
Timing Device, accurate to within 0.1 s for 60 s interval 1
Thermometer, maximum scale error of 0.1 °C 1

1 -14
EINRIP General Specification
Divisi 1 - Umum

URAIAN KUANTITAS

2.11 Titik Lembek :

Ring 2
Pouring Plate 1
Ball 2
Ball Center Guide 2
Bath (a glass vessel) 1
Ring Holder and Assembly 1

2.12 Refusal Density Compactor of BS 598 Part 104 (1989) : 1 set

3. PENGUJIAN BETON (untuk pekerjaan jembatan)

Slump Cone 1
Cylinder/Cube moulds 10
“Speedy” moisture tester 1
Cube crushing machine (provisional) 1

Kalibrasi semua perlengkapan pengukur harus disahkan oleh laboratorium independen


yang disetujui oleh Direksi Pekerjaan dan masih berlaku tidak kurang dari 12 bulan
sebelum Tanggal Mulai Kerja dan Kontraktor harus menyediakan bukti-bukti untuk hal ini
sebagaimana diminta oleh Direksi Pekerjaan.

1.4.3 PROSEDUR PELAKSANAAN

1.4.3.1 Peraturan dan Rujukan

Pengujian harus dilaksanakan dengan teliti sesuai dengan peraturan, petunjuk dan rujukan
yang ditentukan.

1.4.3.2 Personil

Personil yang bertugas pada pengujian bahan haruslah terdiri atas tenaga-tenaga yang
mempunyai pengalaman cukup dan telah terbiasa melakukan pengujian bahan yang
diperlukan dan harus mendapat persetujuan terlebih dahulu dari Direksi Pekerjaan

1.4.3.3 Formulir

Formulir yang dapat digunakan untuk pengujian yang sebenarnya dan pelaporan hasil
pengujian hanyalah formulir telah disetujui terlebih dahulu oleh Direksi Pekerjaan

1.4.3.4 Pemberitahuan

Kontraktor harus memberitahu Direksi Pekerjaan rencana waktu untuk semua pengujian
pengendalian mutu, paling sedikit satu jam sebelum pengujian dilaksanakan.

1 -15
EINRIP General Specification
Divisi 1 - Umum

1.4.3.5 Distribusi

Laporan pengujian harus segera dikerjakan dan didistribusikan sehingga memungkinkan untuk
melakukan pengujian ulang, penggantian bahan atau pemadatan ulang sedemikian hingga
dapat mengurangi keterlambatan dalam pelaksanaan Pekerjaan.

1.4.4 PENGUKURAN DAN PEMBAYARAN

1.4.4.1 Contoh

Semua contoh apakah berasal dari lokasi sumber bahan atau dari perkerasan yang telah selesai
harus disediakan oleh Kontraktor, tanpa biaya tambahan terhadap Kontrak.

1.4.4.2 Pengujian

Biaya untuk melaksanakan semua pengujian pengendalian mutu yang diperlukan menurut
Kontrak, harus ditanggung oleh Kontraktor, dan seluruh biaya tersebut sudah harus dipandang
sudah dimasukkan dalam Harga Satuan bahan yang bersangkutan, kecuali seperti disyaratkan
di bawah ini.

Jika setiap pengujian yang tidak diperuntukkan atau atau tidak disyaratkan, atau karena belum
perlu dilaksanakan, atau karena belum disyaratkan di dalam Dokumen Kontrak ternyata
diperintahkan untuk dilaksanakan oleh Direksi Pekerjaan, atau bilamana Direksi Pekerjaan
memerintahkan kepada Pihak Ketiga untuk melaksanakan pengujian yang tidak termasuk
ketentuan dalam Pasal 1.2.1.3 atau pelaksanaan pengujian di luar lingkup Pekerjaan atau
pengujian di tempat suatu pabrik pembuat atau fabrikasi bahan, maka biaya untuk pelaksanaan
pengujian tersebut menjadi beban Pemilik, kecuali jika hasil pengujian tersebut menunjukkan
bahwa pengerjaan atau bahan tersebut tidak sesuai dengan yang disyaratkan dalam Dokumen
Kontrak, dengan demikian maka biaya pengujian menjadi beban Kontraktor.

1.4.4.3 Fasilitas Laboratorium dan Pengujian

Tidak ada biaya tambahan yang akan dibayarkan kepada Kontraktor untuk penyediaan dan
pemeliharaan bangunan laboratorium, perlengkapan dalam bangunan, peralatan dan
perlengkapan dan kompensasi untuk pekerjaan ini harus dianggap telah termasuk dalam
pembayaran Lump Sum untuk Mobilisasi.

1 -16
EINRIP General Specification
Divisi 1 - Umum

SEKSI 1.5

TRANSPORTASI DAN PENANGANAN

1.5.1 UMUM

1.5.1.1 Uraian

Seksi ini menetapkan ketentuan-ketentuan untuk transportasi dan penanganan tanah, bahan
campuran panas, bahan-bahan lain, peralatan, dan perlengkapan.

Ketentuan Seksi 1.8, Manajemen Lalu Lintas dan Keselamatan, Seksi 1.11, Bahan dan
Penyimpanan, dan Seksi 10.2, Pemeliharaan Jalan Samping dan Jembatan, harus diberlakukan
sebagai pelengkap isi dari Seksi ini.

1.5.1.2 Pekerjaan Seksi Lain Yang Berkaitan Dengan Seksi Ini

a) Syarat-syarat Kontrak : Pasal-pasal yang berkaitan


b) Manajemen Lalu Lintas dan Keselamatan : Seksi 1.8
c) Bahan dan Penyimpanan : Seksi 1.11
d) Usaha Perlindungan Lingkungan Hidup : Seksi 1.17
e) Galian : Seksi 3.1
f) Pemeliharaan Jalan Samping dan Jembatan : Seksi 10.2

1.5.2 KETENTUAN PRA PELAKSANAAN

1.5.2.1 Rencana Route Pengangkutan

Sebelum memulai setiap pengoperasian di jalan-jalan umum yang akan digunakan untuk
mengangkut bahan Kontraktor harus menyediakan informasi berikut ini :

• Peta terinci yang menunjukkan lokasi semua sumber bahan untuk proyek dan route
sepanjang jalan yang dilewati bahan tersebut dari lokasi sumber bahan ke tempat
pekerjaan. Peta ini mencakup lokasi dari setiap penumpukan bahan.

• Kontraktor harus memperoleh dari pemerintah setempat, batas tekanan gandar


sepanjang semua route yang ditentukan dan menunjukkan route-route ini diatas peta.

• Kontraktor harus memperoleh ijin sebagaimana diperlukan jika Kontraktor


berencana membawa muatan yang melampaui batas yang disyaratkan melewati
setiap jalan dan jembatan. Ijin ini hanya digunakan untuk muatan yang tidak dapat
dibagi-bagi.

1.5.2.2 Penilaian Kondisi Infrastruktur

Atas persetujuan Rencana Route Pengangkutan, Kontraktor harus, di bawah pengawasan


Direksi Pekerjaan, melakukan survei yang lengkap terhadap semua infrastruktur pada jalur-
jalur pengangkutan.

Survei ini hampir dapat dipastikan berkonsentrasi pada jalan dan jembatan, tetapi dapat
mencakup struktur lian yang mungkin terpengaruh oleh frekwensi lintasan kendaraan berat.
Survei ini harus mencatat semua kerusakan awal (sebelum digunakan) pada semua jalan.

1 -17
EINRIP General Specification
Divisi 1 - Umum

Permukaan atau struktur, didukung dengan photo dan rujukan melintang yang tepat pada
lokasi-lokasi yang ada di dalam peta.

1.5.3 PELAKSANAAN

1.5.3.1 Standard

Pelaksanaan pekerjaan harus mengacu pada Peraturan Pemerintah, Peraturan Daerah Tingkat I
dan Tingkat II, yang berlaku maupun ketentuan-ketentuan tentang pelestarian sumber daya
alam dan lingkungan hidup.

1.5.3.2 Koordinasi

Kontraktor harus memperhatikan koordinasi yang diperlukan dalam kegiatan trans-portasi


baik untuk pekerjaan yang sedang dilaksanakan atau yang sedang dilaksanakan dalam
Kontrak-kontrak lainya, maupun untuk pekerjaan dengan Sub Kontraktor atau perusahaan
utilitas dan lainnya yang dipandang perlu.

Bilamana terjadi tumpang tindih pelaksanaan antara beberapa Kontraktor, maka Direksi
Pekerjaan harus mempunyai kekuasaan penuh untuk memerintahkan setiap Kontraktor dan
berhak menentukan urutan pekerjaan selanjutnya untuk menjaga kelancaran penyelesaian
seluruh proyek, dan dalam segala hal keputusan Direksi Pekerjaaan harus diterima dan
dianggap sebagai keputusan akhir tanpa menyebabkan adanya tuntutan apapun.

1.5.3.3 Pembatasan Beban Transportasi dan Kerusakan

a) Bilamana diperlukan, Direksi Pekerjaan dapat mengatur batas beban dan muatan sumbu
untuk melindungi jalan atau jembatan yang ada di lingkungan proyek.

b) Kontraktor harus bertanggung jawab atas setiap kerusakan jalan maupun jembatan yang
disebabkan oleh kegiatan pelaksanaan pekerjaan.

c) Bilamana menurut pendapat Direksi Pekerjaan, kegiatan pengangkutan yang dilakukan


oleh Kontraktor akan mengakibatkan kerusakan jalan raya atau jembatan, atau bilamana
terjadi banjir yang dapat menghentikan kegiatan pengangkutan Kontraktor, maka
Direksi Pekerjaan dapat memerintahkan Kontraktor untuk menggunakan jalan
alternatif, dan Kontraktor tak berhak mengajukan tuntutan apapun untuk kompensasi
tambahan sebagai akibat dari perintah Direksi Pekerjaan.

1.5.3.4 Pembuangan Bahan di luar Daerah Milik Jalan

a) Kontraktor harus mengatur pembuangan bahan di luar Daerah Milik Jalan sebagaimana
disyaratkan dalam Pasal 3.1.1.11.(d) dari Spesifikasi ini.

b) Bilamana terdapat bahan yang hendak dibuang di luar Daerah Milik Jalan, maka
Kontraktor harus mendapatkan ijin tertulis dari pemilik tanah dimana bahan buangan
tersebut akan ditempatkan, dan ijin tersebut harus ditembuskan kepada Direksi
Pekerjaan bersama dengan permohonan (request) untuk pelaksanaan.

c) Bilamana bahan yang dibuang seperti yang disyaratkan diatas dan lokasi pem-buangan
tersebut terlihat dari jalan, maka Kontraktor harus membuang bahan tersebut dan
meratakannya sedemikian hingga dapat diterima oleh Direksi Pekerjaan.

1.5.4 CARA PENGUKURAN DAN PEMBAYARAN

1 -18
EINRIP General Specification
Divisi 1 - Umum

Tidak ada pembayaran yang dilakukan pada Seksi ini. Biaya untuk kebutuhan-kebutuhan
dalam Seksi ini harus sudah termasuk dalam semua Mata Pembayaran yang terdapat dalam
Daftar Kuantitas dan Harga, tanpa tambahan biaya. Peralatan yang dipasok oleh Kontraktor
untuk semua kegiatan dalam Seksi ini akan tetap menjadi milik Kontraktor pada saat
penyelesaian Proyek.

1 -19
EINRIP General Specification
Divisi 1 - Umum

SEKSI 1.6

PEMBAYARAN SERTIFIKAT BULANAN

1.6.1 UMUM

1.6.1.1 Uraian

Seksi ini merinci ketentuan dan dan prosedur untuk pelaksanaan pembayaran bulanan
sementara secara teratur melalui Usulan Sertifikat Bulanan yang harus disiapkan oleh
Kontraktor, diperiksa dan disahkan oleh Direksi Pekerjaan dan dimintakan kepada Pemilik
untuk pembayaran.

1.6.1.2 Pekerjaan Seksi Lain Yang Berkaitan Dengan Seksi Ini

a) Syarat-syarat Kontrak : Pasal-pasal yang


berkaitan
b) Prosedur Variasi : Seksi 1.13
c) Penutupan Kontrak : Seksi 1.14
d) Pekerjaan Harian : Seksi 9.1
e) Pasal-pasal yang berkaitan dengan Pengukuran dan Pembayaran untuk setiap Seksi
dalam spesifikasi ini.

1.6.1.3 Pengajuan Kesiapan Kerja

Usulan Sertifikat Bulanan harus diserahkan pada setiap bulan dari Waktu untuk Penyelesaian.

Kontraktor harus bertanggungjawab penuh untuk penyiapan dan pengajuan setiap Usulan
Sertifikat Bulanan, dan harus mengikuti ketentuan berikut :

a) Usulan Sertifikat Bulanan harus disiapkan menurut formulir yang ditetapkan oleh
Direksi Pekerjaan.

b) Usulan Sertifikat Bulanan harus dilengkapi dengan dokumen pendukung yang cukup
pengajuan tersebut lengkap dan dapat dipertanggungjawabkan, agar supaya Direksi
Pekerjaan dapat mengesahkan pelaksanaan pembayaran dalam batas waktu sesuai
Syarat-syarat Umum Kontrak dan Spesifikasi ini.

c) Usulan Sertifikat Bulanan yang sudah dilengkapi dengan dokumen pendukung harus
diserahkan kepada Direksi Pekerjaan sesuai dengan waktu yang disyaratkan di bawah
ini.

d) Bilamana Kontraktor gagal menyiapkan data pendukung yang dapat diterima Direksi
Pekerjaan, atau dengan perkataan lain terlambat menyerahkan, maka tanggal
pelaksanaan pembayaran dapat diundurkan dan Pemilik tidak bertang-gungjawab atas
keterlambatan ini.

1.6.2 PENYIAPAN DAN PENYERAHAN

1.6.2.1 Waktu

Setiap Usulan Sertifikat Bulanan harus diberi tanggal menurut tanggal terakhir dari bulan
kalender, tetapi jumlah tuntutan penagihan (claim) harus didasarkan atas nilai yang sudah

1 -20
EINRIP General Specification
Divisi 1 - Umum

diselesaikan sampai hari kedua puluh lima pada periode bulan yang bersangkutan. Usulan
Sertifikat Bulanan yang telah disiapkan itu harus dikirimkan kepada Direksi Pekerjaan paling
lambat pada hari terakhir dari setiap bulan kalender.

1.6.2.2 Isi

a) Usulan Sertifikat Bulanan harus merangkum ringkasan nilai semua jenis peker-jaan
yang telah diselesaikan menurut masing-masing Divisi dari Spesifikasi ini terhitung
sejak tanggal awal Kontrak, dan juga harus menunjukkan persentase pekerjaan yang
telah diselesaikan dari setiap Divisi sebagai nilai pekerjaan yang telah diselesaikan
dibandingkan terhadap Jumlah Harga Kontrak dari masing-masing Divisi yang
bersangkutan. Jumlah kotor Usulan Sertifikat Bulanan yang diperoleh harus dihitung
dari jumlah nilai pekerjaan yang telah diselesaikan dari masing-masing Divisi, termasuk
nilai “material on site” yang telah disetujui untuk dibayar dan juga setiap pekerjaan
tambahan yang telah disahkan melalui Variasi.

b) Nilai pekerjaan yang telah diselesaikan dari setiap Divisi sebagaimana tercantum pada
Usulan Sertifikat Bulanan harus didukung penuh dengan lampiran doku-mentasi yang
menunjukkan bagaimana setiap nilai itu dihitung. Perhitungan yang demikian akan
mencakup hal-hal berikut ini tetapi tidak terbatas pada :

i) Sertifikat pengukuran kuantitas dan Harga Satuan Mata Pembayaran menurut


Kontrak yang dimasukkan dalam Daftar Kuantitas dan Harga.

ii) Sertifikat pengukuran kuantitas dan dimana ketentuan dalam Spesifikasi ini
mengsyaratkan penyesuaian Harga Satuan Mata Pembayaran sebagaimana
diperlukan untuk pelaksanaan pelapisan ulang (overlay) yang disetujui dengan
tebal atau kadar aspal kurang dari yang disyaratkan.

iii) Pencantuman setiap pekerjaan yang dilaksanakan menurut suatu Variasi yang
sah, dimana Harga Satuan baru atau alternatif jumlah pembayaran yang telah
ditetapkan untuk pekerjaan yang dimaksud dalam Divisi yang bersangkutan.

c) Selembar atau lebih ringkasan yang terpisah dan menunjukkan status berikut ini harus
dilampirkan dalam Usulan Sertifikat Bulanan :

i) Uang Muka dan Pengembalian Uang Muka.

ii) Uang Yang Ditahan (Retention Money).

iii) Variasi yang diminta dan usulan cara pembayaran (jika ada).

iv) Variasi.

v) Tuntutan Penagihan (Claim, jika ada).

vi) PPN (Pajak Pertambahan Nilai)

d) Bilamana Kontraktor telah mengajukan usulan pembayaran terpisah pada suatu Seksi
atau Bagian Pekerjaan yang telah diselesaikan, maka baik Usulan Sertifikat Bulanan
maupun dokumen pendukungnya harus memuat perhitungan yang menunjukkan nilai
pekerjaan yang telah diselesaikan.

1 -21
EINRIP General Specification
Divisi 1 - Umum

1.6.2.3 Data Pendukung Lainnya

Kontraktor harus memelihara semua arsip pengukuran yang sudah disetujui beserta data
pendukung lainnya dan harus mengupayakan semua arsip ini tersedia setiap saat jika
diperlukan oleh Direksi Pekerjaan dan Wakil Direksi Pekerjaan untuk memeriksa ulang
perhitungan kuantitas Kontraktor dalam Usulan Sertifikat Bulanan. Cara perhitungan yang
digunakan untuk menentukan kuantitas untuk pembayaran harus benar-benar sesuai dengan
ketentuan-ketentuan yang berhubungan dengan pengukuran dan pembayaran untuk tiap Seksi
dari Spesifikasi ini.

1.6.3 PENGESAHAN OLEH DIREKSI PEKERJAAN

1.6.3.1 Waktu

a) Direksi Pekerjaan dan/atau Wakilnya akan memeriksa detil dan perhitungan setiap
Usulan Sertifikat Bulanan, kemudian Kontraktor harus diberitahu akan persetujuan atau
penolakannya dalam waktu 7 (tujuh) hari setelah tanggal penyerahan Usulan Sertifikat
Bulanan tersebut.

b) Tanpa memandang apakah diadakan koreksi atau tidak terhadap Usulan Serti-fikat
Bulanan, sebagaimana yang ditetapkan oleh Direksi Pekerjaan selama pemeriksaannya,
setiap Sertifikat Bulanan harus dilengkapi dengan tandatangan dari semua pihak, dan
harus siap untuk disampaikan kepada Pemilik paling lambat hari kesepuluh bulan
berikutnya.

1.6.3.2 Koreksi Terhadap Usulan Sertifikat Bulanan

a) Bilamana Direksi Pekerjaan menetapkan bahwa diperlukan koreksi atau koreksi-koreksi


terhadap Usulan Sertifikat Bulanan sebagaimana yang diusulkan oleh Kontraktor, maka
ia dapat melaksanakan salah satu dari tindakan berikut :

i) Mengembalikan Usulan Sertifikat Bulanan tersebut kepada Kontraktor untuk


disetujui, disesuaikan dan diajukan kembali oleh Kontraktor, atau

ii) Membuat usulan perubahan sebagaimana yang diperlukan untuk memper-baiki


Usulan Sertifikat Bulanan tersebut dan segera memberitahu Kon-traktor secara
tertulis tentang detil dan alasan usulan perubahan tersebut.

b) Bilamana kuantitas tertentu yang ditagihkan telah dimasukkan ke dalam Usulan


Sertifikat Bulanan oleh Kontraktor atau cara pengukuran yang diajukan belum dapat
disetujui oleh Direksi Pekerjaan sebelum tanggal terakhir (closing date) penyerahan
Sertifikat Bulanan kepada Pemilik, maka Mata Pembayaran tersebut tidak boleh
dimasukkan dan disahkan dalam Sertifikat Bulanan ini, tetapi dapat dimasukkan ke
dalam Usulan Sertifikat Bulanan bulan berikutnya setelah diperoleh persetujuan.
Persetujuan tersebut harus didasarkan atas hasil pengukuran ulang yang dilakukan
bersama, atau melalui suatu pembuktian yang diajukan oleh Kontraktor dan dapat
diterima oleh Direksi Pekerjaan.

1.6.3.3 Pengesahan Untuk Pembayaran

Dalam batas waktu seperti ditetapkan di atas, Direksi Pekerjaan harus menghitung jumlah
neto Sertifikat Bulanan dengan cara pemotongan dari jumlah total (gross sum) yang
diusulkan oleh Kontraktor atau jumlah yang disetujui lain atau jumlah yang telah diubah
sebagaimana ditetapkan oleh Direksi Pekerjaan dengan sejumlah yang disyaratkan dalam

1 -22
EINRIP General Specification
Divisi 1 - Umum

Syarat-syarat Kontrak. Usulan Sertifikat Bulanan yang telah lengkap akan disahkan untuk
pembayaran oleh Direksi Pekerjaan, dan diteruskan kepada Pemilik untuk pelaksanaan
proses pembayaran, dan satu salinannya harus disampaikan kepada Kontraktor.

1 -23
EINRIP General Specification
Divisi 1 - Umum

SEKSI 1.7

PEMBAYARAN SEMENTARA (PROVISIONAL SUMS)

1.7.1 UMUM

1.7.1.1 Pembayaran Sementara tidak termasuk dalam Kontrak ini

1 -24
EINRIP General Specification
Divisi 1 - Umum

SEKSI 1.8

MANAJEMEN LALU LINTAS AN KESELAMATAN

1.8.1 UMUM

1.8.1.1 Uraian

a) Kontraktor harus menyediakan perlengkapan dan pelayanan lalu lintas untuk


mengendalikan dan melindungi karyawan Kontraktor dan Direksi Pekerjaan, dan
pengguna jalan yang melalui daerah konstruksi, termasuk lokasi sumber bahan dan
route pengangkutan, sesuai dengan spesifikasi berikut dan memenuhi detil dan lokasi
yang ditunjukkan dalam denah atau yang diterbitkan oleh Direksi Pekerjaan.

b) Kontraktor harus menyediakan, memasang pada setiap saat selama Waktu Penylesaian,
rambu lalu lintas yang diperlukan, barikade, rel pengaman lentur atau kaku, lampu,
tanda-tanda (signal), marka jalan dan perlengkapan lalu lintas lainnya dan harus
menyediakan bendera dan petunjuk lalu lintas dengan cara lain sepanjang zone kerja.
Pengendalian lalu lintas harus dilakukan sesuai dengan perundangan dan peraturan
yang berlaku.

c) Semua perlengkapan yang disebutkan diatas harus memenuhi ketentuan-ketentuan dari


Direktorat Jenderal Bina Marga.

d) Semua pengatur lalu lintas yang disediakan dan dipasang oleh Kontraktor harus ditinjau
oleh Direksi Pekerjaan agar sesuai dengan ukuran, lokasi, reflektifisitas (daya pantul),
visibilitas (daya lihat), kecocokan dan pengunaan yang sebagaimana mestinya sesuai
dengan kondisi kerja yang khusus.

1.8.1.2 Pekerjaan Seksi Lain Yang Berkaitan Dengan Seksi Ini

a) Syarat-syarat Kontrak : Pasal-pasal yang


berkaitan
b) Transportasi dan Penanganan : Seksi 1.11
c) Pekerjaan Pembersihan : Seksi 1.16
d) Usaha Perlindungan Lingkungan Hidup : Seksi 1.17
e) Pengembalian Kondisi Perkerasan Lama : Seksi 8.1
f) Pemeliharaan Rutin Perkerasan, Bahu Jalan, Drainase, : Seksi 10.1
Perlengkapan Jalan dan Jembatan
g) Pemeliharaan Jalan Samping dan Jembatan : Seksi 10.2

1.8.2 RENCANA MANAJEMEN LALU LINTAS DAN KESELAMATAN

1.8.2.1 Urutan Pekerjaan dan Rencana Manajemen Lalu Lintas

Kontraktor harus menjaga seluruh panjang dari proyek dalam kondisi sedemikian hingga
lalu lintas dapat ditampung dengan aman dan karyawan Kontraktor dapat dilindungi.

Sebelum memulai pekerjaan apapun, Kontraktor harus menyiapakan dan mengajukan


kepada Direksi Pekerjaan, Rencana Manajemen Lalu Lintas dan Keselamatan (RMLK)
untuk pengoperasiannya selama tahap pemeliharaan dan tahap pelaksanaan. RMLK harus
berdasarkan analisa aliran lalu lintas tingkat makro dan juga mikro dan tidak boleh
terkonsentrasi di daerah konstruksi. RMLK harus dimutakhirkan secara regular
berdasarkan pengalaman dan kondisi tempat pekerjaan. RMLK harus memperhitungkan

1 -25
EINRIP General Specification
Divisi 1 - Umum

Prosedur Keselamatan (lihat Ayat 4.8 dari Syarat-syarat Umum) dan ketentuan-ketentuan
berikut. RMLK harus memperhitungkan dan menyediakan perlengkapan khusus untuk
pejalan kaki dan kendaraan tidak bermotor jika berada di dekat pekerjaan.

1.8.2.2 Ijin Penutupan Jalan

Daerah konstruksi dibagi-bagi dalam DAERAH KERJA dimana DAERAH KERJA ini
dibagi-bagi lagi dalam ZONE KERJA sebagaimana yang didefinisikan dalam Lampiran
1.8.A. Pekerjaan diperbolehkan dilaksanakan secara simultan dengan DAERAH KERJA
dan ZONE KERJA dalam jumlah tertentu sebagaimana yang ditunjukkan dalam Lampiran
1.8.A pada akhir Seksi ini.

1.8.2.3 Implementasi Pekerjaan Manajemen Lalu Lintas dan Keselamatan

Jika pada setiap saat, Direksi Pekerjaan menetapkan bahwa ketentuan-ketentuan yang
sebagaimana mestinya untuk pengendalian lalu lintas yang aman tidak disediakan,
dipelihara atau dilaksanakan sesuai lingkup dari RMLK, Direksi Pekerjaan dapat
membatasi operasi-operasi Kontraktor yang mempengaruhi situasi semacam ini sampai
penyesuaian yang diperlukan telah dilaksanakan. Direksi Pekerjaan dapat juga
menagguhkan seluruh pekerjaan sampai penyesuaian tersebut dicapai.

Bilamana keselamatan umum atau karayawan Kontraktor diabaikan secara serius dan
dengan sengaja oleh Kontraktor, Direksi Pekerjaan dapat melakukan tindakan perbaikan
yang sepadan dan memotong biaya daripadanya sebagai kompensasi kerugian dari jumlah
yang dibayarkan kepada Kontraktor.

Semua personil paling sedikit berusia 18 tahun, dan harus mengenakan bajau yang reflektif,
sepatu boot dan helm kerja pada setiap saat selama jam kerja.

Operasi pada malam hari harus diterangi dengan lampu and/atau system reflektif yang
disetujui Direksi Pekerjaan. Sistem penerangan harus ditempatkan dan dioperasikan
sedemikian agar dapat menghindarkan sorot cahaya terhadap pengguna jalan yang
mendekati lokasi tersebut. Lampu pijar tidak akan diperkenankan.

1.8.2.4 Koordinasi Antara Berbagai Kontrak-kontrak Pekerjaan Sipil

Kontraktor akan diberitahu setiap pekerjaan sipil lainnya yang terdaftar dalam Lampiran
1.8.A yang dijadwalkan untuk dicapai selama Waktu untuk Penyelesaian.

1.8.2.5 Pemeliharaan Rambu Jalan Sementara

Kontraktor harus menyediakan personil untuk melakukan pengawasan berkesinambungan


terhadap operasi pengendalian lalu lintasnya. Personil tersebut harus tersedia baik siang
maupun malam untuk menanggapi panggilan atas kerusakan barikade, lampu, rambu-
rambu, dsb. Baik oleh vadalisme atau kecelakaan lalu lintas.

Kontraktor harus memberitahu identitas personil tersebut kepada Direksi Pekerjaan


maupun pejabat lalu lintas setempat (termasuk polisi) di tempat kerja.

1.8.2.6 Bahan dan Peralatan

Semua bahan dan peralatan yang disediakan untuk implementasi kegiatan-kegiatan


manajemen lalu lintas dan keselamatan harus disediakan oleh Kontraktor dan tetap menjadi
miliknya pada akhir periode kontrak.

1 -26
EINRIP General Specification
Divisi 1 - Umum

Peralatan dan perkakas untuk menangani lalu lintas yang rusak oleh sebab apapun selama
kemajuan pekerjaan harus diperbaiki atau diganti segera, termasuk pengecatan jika perlu
oleh Kontraktor dengan biaya sendiri.

Bilamana pengatur lalu lintas disediakan oleh Kontraktor tidak diperlukan lagi untuk
pengendalian lalu lintas, perlengkapan tersebut harus disingkirkan dari tempat kerja di
lapangan.

Pengatur lalu lintas harus dibuat sedemikian hingga perlengkapan tersebut tidak boleh
merusak atau melukai kendaraan atau pengguna jalan jika tertabrak atau terjungkal dan
harus tetap stabil dan berdiri di tempat ketika berangin.

1.8.2.7 Koordinator Manajemen Lalu Lintas dan Keselamatan

Kontraktor harus mempekerjakan Koordinator Manajemen Lalu Lintas dan Keselamatan


(KMLK) yang memenuhi syarat dan memadai, dengan pengalaman yang sesuai minimum
3 tahun dalam tugas-tugas semacam ini dan staf yang diperlukan (jumlah minimum 2
orang) yang dibawahinya untuk seluruh pengendalian dari manajemen lalu lintas dan
keselamatan, termasuk koordinasi dengan pejabat lalu lintas tingkat propinsi dan setempat
dengan juridiksi terhadap daerah proyek, sedemikian hingga dapat memperkecil halangan,
resiko keselamatan dan memperlancar aliran lalu lintas yang melalui daerah konstruksi dan
melalui jalan-jalan pengalihan yang sesuai dan disetujui. Pemilihan KMLK harus disetujui
oleh Direksi Pekerjaan.

Koordinator Manajemen Lalu Lintas dan Keselamatan (KMLK) harus secara aktif
berpartisipasi dalam semua rapat requler maupun khusus dengan Direksi Pekerjaan.
KMLK harus siap sedia pada setiap saat (24 jam per hari, 7 hari per minggu) melalui
komunikasi yang mobil, untuk kesulitan-kesulitan, keadaan darurat dan hal-hal lain dari
lalu lintas dan manajemen keselamatan dalam seluruh waktu dari pekerjaan.

KMLK adalah individu yang akan dituju oleh Direksi Pekerjaan atas semua permintaan
yang berhubungan dengan hal-hal manajemen lalu lintas dan keselamatan. KMLK
mempunyai wewenang untuk mengambil keputusan dan berkoordinasi dengan personil
Kontraktor untuk hal-hal manajemen lalu lintas dan keselamatan.

Tugas-tugas KMLK harus mencakup berikut ini :

a) Memahami kebutuhan-kebutuhan kontraktual, termasuk denah, spesifikasi dan


lingkungan di mana pekerjaan sipil akan dilaksanakan;

b) Menginspeksi rutin terhadap kondisi dan keefektifan dari pengatur lalu lintas yang
digunakan dalam proyek dan memastikan bahwa perlengkapan tersebut dalam
berfungsi sebagaimana mestinya, bersih, dapat dilihat dan memenuhi spesifikasi,
denah dan peraturan-peraturan setempat;

c) Meninjau dan mengantisipasi kebutuhan atas pengatur lalu lintas yang sesuai,
menasehati Direksi Pekerjaan tentang hal-hal terkait, dan memastikan bahwa RMLK
telah diimplementasikan untuk pergerakan lalu lintas yang aman dan efisien;

d) Mengkoordinasikan pemeliharaan dari pengoperasian lalu lintas dengan Direksi


Pekerjaan;

e) Melakukan rapat keselamatan lalu lintas kontraktor sebelum pelaksanaan dimulai,


dan rapat berkala yang dianggap perlu atau sebagaimana diperintahkan oleh Direksi
Pekerjaan. Direksi Pekerjaan harus diberitahu sebelumnya untuk menghadiri rapat-
rapat ini.

1 -27
EINRIP General Specification
Divisi 1 - Umum

1.8.2.8 Penutupan Jalan Yang Tidak Sah

Semua penutupan jalan atau lajur yang premature di luar kerangka waktu yang sah
(Lampiran 1.8.A) dipandang sebagai penutupan jalan yang tidak sah.

Semua penutupan total jalan tanpa suatu jalan samping yang pantas harus dipandang
sebagai penutupan jalan yang tidak sah dan tunduk terhadap pemotongan permanent diatas.

1.8.2.9 Akses menuju Daerah Kerja

Kontraktor harus menggunakan sebuah Kendaraan Penghantar ketika memasuki atau


meninggalkan daerah kerja sampai jalan tersebut dibuka untuk lalu lintas. Kontraktor
harus menyediakan fasilitas yang sama untuk Personil Direski Pekerjaan dan Pemilik.

Manuver ini (memasuki dan meninggalkan daerah kerja) harus dilaksanakan dengan aman
sehinngga memperkecil resiko terhadap para pekerja dan pengguna jalan.

1.8.2.10 Kejadian Khusus dan Hari Libur

Tabel 1.8 A.3 mengidentifikasi kejadian khusus di mana selama waktu itu Direksi
Pekerjaan mencadangkan haknya untuk tidak mengijinkan penutupan jalan. Kontraktor
harus mempertimbangkan kejadian semacam ini dalam rencana kerjanya.

Bilamana terjadi Kejadian Kahar, Direksi Pekerjaan dapat juga membatalkan penutupan
jalan.

1.8.2.11 Penutupan Lajur/Jalan Dengan Menggunakan Tanda Visual (pasal ini harus merujuk gambar
standar untuk penutupan lajur)

Penutupan lajur dengan menggunakan tanda visualharus dilakukan sesuai dengan detil-detil
dalam Gambar atau sebagaimana yang diperintahkan oleh Direksi Pekerjaan.

1.8.2.12 Penutupan Jalan Keluar/Masuk pada Jalan Raya

Penutupan jalan keluar/masuk pada jalan raya harus dilakukan sesuai dengan detil-detil
dalam Gambar atau sebagaimana yang diperintahkan oleh Direksi Pekerjaan.

1.8.2.13 Penutupan Jalan Keluar/Masuk pada Jalan Dalam Kota

Penutupan jalan keluar/masuk pada jalan dalam kota harus dilakukan sesuai dengan detil-
detil dalam Gambar atau sebagaimana yang diperintahkan oleh Direksi Pekerjaan.

1.8.2.14 Penambahan Rambu-rambu Jalan

Atas permintaan Direksi Pekerjaan, Kontraktor harus menyediakan tambahan rambu jalan
atau perlengkapan penanganan lalu lintas. Peralatan ini harus sesuai dengan spesifikasi dari
Direksi Pekerjaan. Kontraktor harus menyediakan peralatan tersebut dalam waktu 48 jam
dan memasang serta memelihara peralatan tersebut selama Waktu untuk Penyelesaian.

1.8.3 URAIAN BAHAN DAN PERALATAN

1.8.3.1 Rambu Panah Berkedip

Rambu panah berkedip harus disediakan dalam lapisan email yang datar dengan mutu
komersial dagang dan harus dilengkapi dengan lampu kuning atau amber (warna kuning

1 -28
EINRIP General Specification
Divisi 1 - Umum

pesawat lalu lintas) yang membentuk panah atau kepala anak panah. Lampu tersebut harus
dikendalikan oleh sirkuit elektrik yang menyediakan kedipan penuh antara 30 to 45 kali
per menit. Pengendali ini termasuk perlengkapan untuk meredupkan lampu dengan
mengurangi voltasi sampai 50% ± 5 persen, untuk digunakan pada malam hari.

Rambu Panah Berkedip harus mampu dioperasikan dalam 4 mode display yang berbeda
sebagai berikut. Display yang digunakan haruslah sebagaimana yang ditunjukkan RMLK
yang disepakati atau yang diperitahkan oleh Direksi Pekerjaan.
(a) Display lewat ke kiri – (←)
(b) Display lewat ke kanan – (→)
(c) Display lewat ke kanan atau kiri – (↔)
(d) Display Hati-hati – (−)

Rambu panah berkedip harus mampu beroperasi dalam satu mode atau keduanya dari
berikut ini, menurut pendapat Kontraktor : 1) Mode panah berkedip; 2) Mode yang
Berentetan. Dalam mode berkedip, semua lampu yang membentuk kepala anak panah dan
lampu dari batang anak panah harus berkedip secara simultan.

1.8.3.2 Rambu Suar Berkedip Portabel

Rambu Suar Berkedip Portabel harus dipasang pada awal dan akhir lokasi proyek.

Masing-masing unit rambu suar berkedip portabel harus terdiri dari flasher (pengkedip),
dan sumber listrik dari baterei. Unit-unit itu harus dirakit sampai membentuk sebuah rambu
suar berkedip yang lengkap, berdiri sendiri-sendiri, yang dapat dikirim ke lapangan dan
dipasang sedemikian dapat segera beroperasi. Lensa-lensa harus terbuat dari lexan
polycarbonate yang tinggi untuk menahan kondisi-kondisi operasional dari hari demi hari.
Bagian tubuh harus dicetak dari polypropylene yang tahan tumbukan yang diperkuat
dengan baut yang ditumbuk secara pneumatik. Tempat baterei harus cukup besar untuk
menampung 2 buah baterei 12 volt, tempat baterei jenis otomatis dan harus mempunyai
bentuk dan berat sedemikian hingga rambu suar tidak akan menggelinding jika tertabrak
oleh kendaraan atau terdorong. Rambu suar harus dipoles dengan lapisan email warna
oranye 2 (dua) kali dengan mutu komersial. Rakitan rambu suar berkedip harus kedap air
dan harus mampu beroperasi minimum 150 jam antara pengisian ulang baterei atau
pemeliharaan rutin lainnya.

Unit flasher (pengkedip) harus menyediakan 50 sampai 60 kedipan per menit dengan waktu
jeda 250 sampai 350 milli-detik. Lampu haruslah dihitung pada 25 watt untuk operasi
dengan arus AC 120 volt.

1.8.3.3 Rambu-rambu Konstruksi dan Pengalihan

Istilah “Rambu-rambu Daerah Konstruksi” harus mencakup semua rambu-rambu


sementara yang diperlukan untuk arah lalu lintas umum yang melalui dan sekitar pekerjaan
selama pelaksanaan pekerjaan. Rambu-rambu ini ditunjukkan dan dirujuk dalam Gambar.

Rambu-rambu daerah konstruksi harus dipasang pada lokasi yang ditunjukkan dalam denah
sebagaimana yang diperintahkan oleh Direksi Pekerjaan.

Rambu-rambu daerah konstruksi dirancang sebagai rambu tetap yang dipasang pada denah
dan rambu-rambu daerah konstruksi dirancang sebagai rambu portabel pada denah harus
memenuhi semua ketentuan dalam Seksi 8.4 “Perlengkapan Jalan dan Pengatur Lalu
Lintas”.

1 -29
EINRIP General Specification
Divisi 1 - Umum

Rambu-rambu daerah konstruksi yang tidak dirancang sebagai rambu tetap atau portabel
pada denah akan menjadi pilihan Kontraktor, apakah tetap atau portabel.

Semua rambu daerah konstruksi harus memenuhi ketentuan-ketentuan dimensi, warna dan
tanda dalam denah dan spesifikasi ini.

Rambu-rambu daerah konstruksi harus terlihat dengan jarak 150 meter dan terbaca dengan
jarak 90 meter pada cuaca cerah siang hari dan pada malam hari dengan kuat penerangan
lampu dengan berkas cahaya rendah, oleh orang-orang dengan visi atau dikoreksi sampai
20/20.

Kontraktor mungkin diperlukan untuk menutupi rambu-rambu tertentu selama kemajuan


pekerjaan. Tutup untuk rambu-rambu daerah konstruksi haruslah dengan ukuran dan
ketebalan yang cukup untuk menutup seluruh informasi sedemikian hingga informasi
tsersebut tersebut tidak terlihat baik selama siang maupun malam hari. Tutup harus diikat
dengan kencang untuk mencegah pergerakan yang disebabkan oleh angin.

Kontraktor harus membersihkan semua panel dari rambu daerah konstruksi pada saat
pemasangan dan sesering mungkin setelah itu sebagaimana jika Direksi Pekerjaan
menetapkan perlu, tetapi paling sedikit setiap 4 bulan sekali.

Rambu yang digunakan dengan lembar bahan yang disebutkan akan dipandang memenuhi
syarat jika rambu tersebut memenuhi ketentuan-ketentuan untuk keterlihatan dan
keterbacaan dan warnanya memenuhi ketentuan-ketentuan yang diperintahkan oleh Direksi
Pekerjaan. Perbedaan menyolok warna reflektif antara siang dan malam akan menjadi dasar
untuk menolak rambu-rambu tersebut.

Untuk menyediakan rambu-rambu tersebut dengan memadai atas perubahan kondisi lalu
lintas dan kerusakan yang disebabkan oleh lalu lintas umum atau sebaliknya, Kontraktor
harus siap menyediakan panel dengan waktu pemberitahuan yang singkat, tiang dan
perangkat keras tiang tetap atau tiang rambu portabel dari tambahan rambu-rambu daerah
konstruksi. Kontraktor harus memelihara inventaris barang-barang yang umum diperlukan
di tempat kerja dan menyediakan barang-barang tersebut dalam waktu pemberitahuan yang
singkat.

a) Rambu-rambu Tetap

Rambu-rambu tetap harus dengan tiang kayu dengan cara yang sama sebagaimana
ditunjukkan dalam denah atau sebagaimana diperintahkan oleh Direksi Pekerjaan
untuk pemasangan rambu-rambu pada tepi jalan, kecuali berikut ini :

i) Pengaku dan rangka pada bagian belakang panel dari rambu tidak diperlukan

ii) Tinggi dari dasar dari panel diatas tepi jalur lalu lintas paling sedikit 1,5 meter
kecuali jika rambu ditempatkan pada jalur pejalan kaki dan sepeda maka
tinggi dari dasar panel rambu diatas tepi jalur lalu lintas paling sedikit harus
2,1 meter.

iii) Tiang rambu-rambu daerah konstruksi dapat dipasang tepat diatas penunjang
sementara rambu-rambu yang berbentuk datar sebagaimana disetujui oleh
Direksi Pekerjaan, atau rambu-rambu yang dapat dipasang pada tiang listrik
yang ada atau penunjang lainnya sebagaimana yang disetujui Direksi
Pekerjaan. Bilamana rambu-rambu daerah konstruksi dipasang pada tiang
listrik yang ada, maka tidak boleh dibuat lubang pada tiang yang menunjang
rambu tersebut.

1 -30
EINRIP General Specification
Divisi 1 - Umum

iv) Tiang yang tertanam harus 0,8 meter dan lubang tiang harus ditimbun kembali
di sekeliling tiang dengan beton semen yang dibuat dari campuran agregat
dan semen dengan mutu komersial yang mengandung semen tidak kurang dari
168 kilogram per kubik.

Ukuran tiang dan jumlah tiang haruslah sebagaimana yang ditunjukkan dalam
Gambar, kecuali jika rambu-rambu tetap dipasang dan jenis rambu yang dipasang
tidak ditunjukkan dalam Gambar, ukuran tiang dan jumlah tiang harus ditentukan
oleh Direksi Pekerjaan. Tiang haruslah dari kayu yang baik mutunya dan tidak cacat,
sesuai untuk tujuan yang dimaksud.

Panel-panel rambu untuk rambu tetap haruslah terdiri dari lembaran plywood.

Tanda dan tepi dapat dilakukan dengan proses sablon. Ukuran dan jarak huruf-huruf
dan lambang-lambang haruslah sebagaimana yang dilukiskan dalam lembar
spesifikasi rambu-rambu yang diterbitkan oleh Pemilik.

b) Rambu Portabel

Masing-masing rambu portabel haruslah terdiri dari dasar, penunjang atau kerangka
dan panel rambu. Unit-unit ini harus dapat dikirim ke lapangan untuk digunakan dan
ditempatkan untuk pengoperasian yang segera.

Panel-panel rambu untuk rambu portabel haruslah terdiri dari lembaran plywood.

Penunjang atau kerangka rambu harus mampu menunjang panel dengan dimensi
maksimum 120 cm, dalam posisi tegak lurus dengan pusat dari panel rambu dan
jarak minimum panel diatas perkerasan adalah 1,2 meter.

Jika rambu portable berpindah tempat atau terguling, oleh sebab apapun, selama
kemajuan pekerjaan, Kontraktor harus segera mengganti rambu-rambu itu pada
lokasi awal dari rambu-rambu tersebut.

1.8.3.4 Penghalang Lalu Lintas

Penghalang lalu lintas harus terdiri dari “jenis beton pracetak atau jenis plastik” yang baru
sebagaimana yang ditunjukkan dalam denah.

Penghalang lalu lintas harus digunakan untuk memandu lalu lintas untuk tidak melintasi
perkerasan yang baru dihampar dan dipasang pada lokasi yang ditunjukkan dalam denah
atau sebagaimana yang diperintahkan oleh Direksi Pekerjaan.

Penghalang lalu lintas yang dirancang sebagai beton pracetak dalam Gambar dan
penghalang lalu lintas yang dirancang sebagai “jenis plastik” dalam Gambar harus
memenuhi ketentuan-ketentuan dalam Seksi 8.4 “Perlengkapan Jalan dan Pengatur Lalu
Lintas”

Penghalang lalu lintas harus memenuhi ketentuan dimensi dan warna yang terdapat dalam
Gambar dan Spesifikasi ini.

a) Penghalang Lalu Lintas, Penghalang Beton Pracetak

Penghalang lalu lintas, jenis beton pracetak, harus terdiri dari unit penghalang beton
pracetak yang baru sebagaimana yang ditunjukkan dalam Gambar. Permukaan yang
terekspos harus baru saja terlapisi cat dengan warna sebagaimana yang ditunjukkan
dalam Denah sebelum digunakan pertama kali di proyek. Cat tersebut harus menuhi

1 -31
EINRIP General Specification
Divisi 1 - Umum

ketentuan-ketentuan dalam Seksi 8.4 “Perlengkapan Jalan dan Pengatur Lalu


Lintas”. Pengecatan ulang atau membuat unit-unit menjadi bagus, bilamana diminta
oleh Direksi Pekerjaan setelah unit-unit tersebut berada di lapangan, haruslah
menjadi tanggung-jawab Kontraktor.

Penghalang lalu lintas, jenis beton pracetak, harus digunakan untuk memandu lalu
lintas untuk tidak melintasi perkerasan semen yang baru dihampar.

Untuk fabrikasi penghalang lalu lintas beton pracetak, beton harus memenuhi
ketentuan-ketentuan Seksi 7.1. “Beton” dan baja tulangan harus memenuhi
ketentuan-ketentuan Seksi 7.3, “Baja Tulangan”

Unit-unit beton pracetak harus dipasang dengan jarak antara unit-unit tersebut
sebagaimana yang ditunjukkan dalam Denah. Unit-unit beton pracetak harus
ditempatkan lurus pada alinyemen lurus dan lengkung yang benar pada alinyemen
tikungan.

b) Penghalang Lalu Lintas, jenis Plastik

Penghalang lalu lintas, jenis plastik harus digunakan untuk pengalih lalu lintas dari
perkerasan aspal beton yang baru.

Penghalang lalu lintas, jenis plastik harus cukup berat agar dapat tetap stabil jika
terdapat angin atau pusaran angin akibat lewatnya lalu lintas.

Pemberat yang digunakan untuk penghalang lalu lintas, jenis plastik haruslah air.

1.8.3.5 Marka Jalan Sementara

Cata marka harus memenuhi ketentuan-ketentuan Seksi 8.4 “Perlengkapan Jalan dan
Pengatur Lalu Lintas”:

Marka sementara pada punggung jalan harus menerus, berwarna kuning dan mempunyai
lebar minimum 150 mm.

Marka jalan sementara harus dilaksanakan pada setiap pelapisan perkerasan sebelum jalan
dibuka untuk lalu lintas umum. Pada pelapisan ulang perkerasan aspal beton, marka
sementara harus dilaksanakan sesegera mungkin setelah suatu lapisan telah dihampar.
Sebagai gambaran minimum, marka sementara harus dilaksanakan pada hari yang sama
dengan pelapisan perkerasan aspal beton yang dihampar pada jalan tersebut di mana lalu
lintas dialihkan. Marka sementara pada permukaan akhir harus dibuang sebelum marka
permanen dilaksanakan.

Semua garis menerus dan marka jalan konstruksi yang berpotongan harus dibuang sampai
benar-benar bersih dengan pengaus pasir atau cara lain yang disetujui dan tidak merusak
permukaan atau tekstur perkerasan. Pola pembuangan harus dalam bentuk yang tidak sama
sehingga tidak menyisakan bekas marka yang dibuang dengan menggunakan pengausan
secara diagonal dan termasuk beberapa daerah permukaan sekitarnya. Kerusakan yang
terjadi pada permukaan harus diperbaiki dengan biaya Kontraktor dengan metoda yang
dapat diterima oleh Direksi Pekerjaan. Penumpukan pasir atau bahan lainnya yang
mengakibatakan bahaya terhadap lalu lintas harus dibuang. Pada saat selesai, permukaan
aspal yang diauskan dengan pasir harus dilapisi tipis dengan ter emulsi atau bahan sejenis
yang disetujui.

1 -32
EINRIP General Specification
Divisi 1 - Umum

1.8.3.6 Pagar yang Dapat Dilepas

Pagar yang dapat dilepas haruslah jenis Kawat Bergelombang (Cyclone Wire) atau
Lembaran Besi Bergalvanisasi yang Datar

Pagar yang dapat dilepas harus memenuhi detil-detil yang ditunjukkan dalam denah dan
harus sebagaimana yang disebutkan yang Seksi ini.

a) Pagar yang Dapat Dilepas, Jenis Kawat Bergelombang (Cyclone Wire)

Tiang yang tegak dan kerangka horisontal haruslah pipa besi bergalvanisasi,
berdiameter 75 mm, memenuhi ketentuan ASTM 501, Kawat Bergelombang
(Cyclone Wire) haruslah difabrikasi dari kawat bergalvanisasi dengan ukuran Gauge
10 memenuhi AASHTO M 181 dan diikat pada kerangka dengan kawat pengikat .

Jangkar tiang adalah blok penunjang berdiri dari beton pracetak yang difabrikasi
sesuai dengan detil dalam denah.

Untuk fabrikasi blok penunjang berdiri dari beton pracetak haruslah sesuai dengan
Seksi 7.1 “Beton” dan baja tulangan harus memenuhi ketentuan Seksi 7.3, “Baja
Tulangan”.

Tulangan dua lapis, berdiamater 12 mm, harus disediakan untuk setiap blok
penunjang berdiri dari beton pracetak sebagaimana yang ditunjukkan dalam denah.

Perhatian khusus harus diberikan dalam penanganan, penyimpanan dan pemasangan


untuk menghindari retak atau kerusakan terhadap blok penunjang berdiri dari beton
pracetak. Blok penunjang berdiri dari beton pracetak harus ditangani, diangkut dan
dipasang dalam posisi tegak dan titik-titik penunjang dan arah dari reaksi terhadap
blok haruslah kira-kira sama seperti ketika blok dalam posisi akhir.

b) Pagar yang Dapat Dilepas, Lembaran Besi Bergalvanisasi yang Datar

Tiang yang tegak dan kerangka horisontal haruslah pipa besi bergalvanisasi,
berdiameter 75 mm, memenuhi ketentuan ASTM 501. Lembaran besi bergalvanisasi
harus mempunyai ukuran Gauge 26 (tebal 0,48 mm) dicat dengan warna hijau,
memenuhi ketentuan Item 411, Plaint and tied to the pipe framing by tie wire.

Jangkar tiang adalah blok penunjang berdiri dari beton pracetak yang difabrikasi
sesuai dengan detil dalam denah.

Untuk fabrikasi blok penunjang berdiri dari beton pracetak haruslah sesuai dengan
Seksi 7.1 “Beton” dan baja tulangan harus memenuhi ketentuan Seksi 7.3, “Baja
Tulangan”.

Sebuah kait pengangkat, berdiameter 20 mm dan tulangan dua lapis, berdiamater 12


mm harus disediakan masing-masing untuk setiap blok beton dan blok penunjang
berdiri dari beton sebagaimana ditunjukkan dalam Denah.

Perhatian khusus harus diberikan dalam penanganan, penyimpanan dan pemasangan


untuk menghindari retak atau kerusakan terhadap beton pracetak. Beton pracetak
harus ditangani, diangkut dan dipasang dalam posisi tegak dan titik-titik penunjang
dan arah dari reaksi terhadap blok haruslah kira-kira sama seperti ketika blok dalam
posisi akhir.

1 -33
EINRIP General Specification
Divisi 1 - Umum

1.8.3.7 Lain-lain

Kontraktor harus menyediakan pengatur lalu lintas dan pelayanan berikut untuk
pengendalian dan pemeliharaan lalu lintas yang melalui daerah konstruksi dengan sub-
komponen yang berbeda sebagai berikut :

Uraian Satuan Jumlah


Lampu Berkedip Buah …….
Penghalang Lalu Lintas (Jenis Beton) Buah …….
Penghalang Lalu Lintas (Jenis Plastik) Buah …….
Detachable Pedestrian Barrier (Including Concrete Footings) Buah …….
Pemandu Lalu Lintas (Pengibar Bendera) Orang- …….
Hari
Pengawas Keselamatan (KMLK) Orang- …….
Hari
Papan Rambu Lalu Lintas (termasuk tiang dan pondasi telapak beton) Buah …….
Lampu Tali M …….
Marka Punggung (lebar 150 mm, Menerus Berwarna Kuning) M …….
Pelat Baja (4’x8’x3/4”) Buah …….
Jala Keselamatan dengan diameter 50 mm. Pengaku Horisontal dan M …….
Vertikal (termasuk asoseri)
Rambu Peringatan Buah …….
Lain-lain …….

1.8.4 PEKERJAAN JALAN ATAU JEMBATAN SEMENTARA

1.8.4.1 Umum

Kontraktor harus menyediakan memelihara, dan membongkar semua jalan, jembatan, jalan
masuk dan sejenisnya yang diperlukan oleh Kontraktor untuk menghubungkan Kontraktor
dengan jalan umum pada saat Penyelesaian Pekerjaan.

Jalan sementara ini harus dibangun sampai diterima Direksi Pekerjaan, meskipun demikian
Kontraktor tetap harus bertanggungjawab terhadap setiap kerusakan yang terjadi atau
disebabkan oleh jalan sementara ini.

1.8.4.2 Lahan Yang Diperlukan

Sebelum membuat jalan atau jembatan sementara, Kontraktor harus melakukan semua
pengaturan yang diperlukan, bila diperlukan termasuk pembayaran kepada pemilik tanah
yang bersangkutan atas pemakaian tanah itu dan harus memperoleh persetujuan dari
pejabat yang berwenang dan Direksi Pekerjaan. Setelah pekerjaan selesai, Kontraktor harus
membersihkan dan mengembalikan kondisi tanah itu ke kondisi semula sampai diterima
oleh Direksi Pekerjaan dan pemilik tanah yang bersangkutan.

1.8.4.3 Peralatan Kontraktor Lain Yang Lewat

Kontraktor harus melakukan semua pengaturan agar Pekerjaan yang sudah dilak-sanakan
dapat dilewati dengan aman oleh Peralatan Konstruksi, bahan dan karyawan Kontraktor

1 -34
EINRIP General Specification
Divisi 1 - Umum

lain yang melaksanakan pekerjaan di dekat proyek. Untuk keperluan ini, Kontraktor dan
Kontraktor lain yang melaksanakan pekerjaan di dekat proyek, harus menyerahkan suatu
jadwal transportasi yang demikian kepada Direksi Pekerjaan untuk mendapat
persetujuannya, paling sedikit 15 (limabelas) hari sebelumnya.

1.8.4.4 Jalan Alih Sementara atau Detour

Jalan alih sementara atau detour harus dibangun sebagaimana yang diperlukan untuk
kondisi lalu lintas yang ada, dengan memperhatikan ketentuan keselamatan dan kekuatan
struktur. Semua jalan alih yang demikian tidak boleh dibuka untuk lalu lintas umum sampai
alinyemen, pelaksanaan, drainase dan pemasangan rambu lalu lintas sementara telah
disetujui Direksi Pekerjaan. Selama digunakan untuk lalu lintas umum Kontraktor harus
memelihara pekerjaan yang telah dilaksanakan, drainase dan rambu lalu lintas sampai
diterima oleh Direksi Pekerjaan.

1.8.4.5 Jalan Samping (ramp) Sementara untuk Lalu Lintas

Kontraktor harus membangun dan memelihara jembatan dan jalan samping sementara
untuk jalan masuk umum dari dan ke jalan raya pada semua tempat bilamana jalan masuk
tersebut sudah ada sebelum Pekerjaan dimulai dan pada tempat lainnya yang diperlukan
atau diperintahkan oleh Direksi Pekerjaan.

1.8.5 PEMELIHARAAN UNTUK KESELAMATAN LALU LINTAS

1.8.5.1 Jalan Alih Sementara dan Pengendalian Lalu Lintas

Semua jalan alih sementara dan pemasangan pengendali lalu lintas yang disiapkan oleh
Kontraktor selama pelaksanaan Pekerjaan harus dipelihara agar tetap aman dan dalam
kondisi pelayanan yang memenuhi ketentuan dan dapat diterima Direksi Pekerjaaan
sehingga menjamin keselamatan lalu lintas dan bagi pemakai jalan umum.

1.8.5.2 Pembersihan Penghalang

Selama pelaksanaan pelaksanaan, Kontraktor harus menjamin bahwa perkerasan, bahu


jalan lokasi yang berdekatan dengan Daerah Milik Jalan harus dijaga agar bebas dari bahan
pelaksanaan, kotoran dan bahan yang tidak terpakai lainnya yang dapat mengganggu atau
membahayakan lalu lintas yang lewat. Pekerjaan juga harus dijaga agar bebas dari setiap
parkir liar atau kegiatan perdagangan kaki lima kecuali untuk daerah-daerah yang
digunakan untuk maksud tersebut.

1.8.6 PENGUKURAN DAN PEMBAYARAN

1.8.6.1 Pengukuran

Pengukuran Manajemen Lalu Lintas dan Keselamatan dilakukan berdasarkan gabungan


mobilisasi, demobilisasi dan pembayaran bulanan. Untuk pengukuran dari pembayaran
bulanan maka disyaratkan bahwa semua ketentuan harus dipenuh. Bilamana Kontraktor
tidak memenuhi semua dari ketentuan-ketentuan dari Pasal ini maka jenis pekerjaan yang
tersebut tidak akan dibayar bulan yang bersangkutan untuk Manajemen Lalu Lintas dan
Keselamatan.

1.8.6.2 Dasar Pembayaran

Pekerjaan Manajemen Lalu Lintas dan Keselamatan harus dibayar atas dasar lump sum
menurut jadwal pembayaran yang terdapat di bawah ini. Jumlah ini harus dipandang

1 -35
EINRIP General Specification
Divisi 1 - Umum

sebagai kompensasi penuh untuk penyediaan, semua bahan, semua peralatan, pekerja,
perkakas dan biaya lainnya yang perlu untuk pemasangan dan pemeliharaan semua
pemasangan sementara, untuk pengendalian lalu lintas selama Waktu untuk Penyelesaian
dan untuk pembersihan halangan apapun yang perlu untuk menyelesaikan pekerjaan yang
diuraikan dalam 1.8.1.1 dan 1.8.2 dari Spsifikasi ini. Akan tetapi, Direksi Pekerjaan dapat,
selama periode Waktu untuk Penyelesaian, memerintahkan Kontraktor untuk menyediakan
tambahan peralatan sebagaimana yang dianggap perlu dengan perubahan harga lump sum
untuk Manajemen Lalu Lintas dan Keselamatan.

 25 % (dua puluh lima persen) bilamana semua jenis peralatan utama telah berada di
lapangan, diterima dan disetujui oleh Direksi Pekerjaan.

 50 % (lima puluh persen) harus dibayar secara angsuran atas dasar bulanan,
berdasarkan kemajuan pekerjaan yang dapat diterima yaitu 50%/T pembayaran per
bulan, di mana T adalah Waktu untuk Penyelesaian dari Kontrak dalam.

 25 % (dua puluh lima persen) pada saat demobilisasi selesai.

Bilamana kuantitas tidak tercantum dalam Daftar Kuantitas dan Harga, tidak ada
pembayaran terpisah yang dilakukan untuk Manajemen Lalu Lintas dan Keselamatan yang
dilaksanakan sesuai dengan seksi dari Spesifikasi ini. Biaya untuk pekerjaan ini harus
sudah termasuk dalam harga satuan dari semua Mata Pembayaran yang terdapat dalam
Kontrak.

Jika Kontraktor gagal untuk melaksanakan pengoperasian manajemen lalu lintas dan
keselamatan sebagaimana yang disebutkan dalam Seksi dari Spesifikasi ini, Kontraktor
harus dibebani seluruh biaya actual ditambah 10 (sepuluh persen) untuk semua
pengoperasian manajemen lalu lintas dan keselamatan yang dilaksanakan oleh Direksi
Pekerjaan atau pihak-pihak lain sebagaimana yang diperintahkan oleh Direksi Pekerjaan.

Nomor Mata Uraian Satuan


Pembayaran Pengukuran

1.8 Manajemen Lalu Lintas dan Keselamatan Lump Sum

1 -36
EINRIP General Specification
Divisi 1 - Umum

LAMPIRAN 1.8.A
1.8.2.1 Urutan Pekerjaan dan Rencana Manajemen Lalu Lintas dan Keselamatan (Contoh
perlu dilengkapi dengan Gambar)

Pekerjaan terdiri dari pelaksanaan ……….……. dari ………….…...

Kontraktor harus memperhitungkan larangan-larangan berikut ketika menyiapkan Rencana


Manajemen Lalu Lintas dan Keselamatan.

Daerakh konstruksi dibagi dalam 1 (satu) Daerah Kerja, yang kemudian dibagi-bagi lagi dalam Zone-
zone Kerja.

• Daerah Kerja 1 terletak sepanjang Proyek, antara Sta…….…. sampai Sta. ……………
o Zone Kerja 1 memperkenankan Kontraktor untuk melaksanakan pekerjaan pada lajur
(kiri, tengah, kanan) antara Sta……. sampai Sta…….. Penutupan seluruh lajur
diperkenankan dengan jalan keluar/masuk no.01 (Sta. ………..) dan jalan keluar/masuk
no.02 (Sta………), tidak ada pengalihan Lalu Lintas.

Kontraktor diperkenankan bekerja pada Daerah Kerja 1 secara simultan.


Penutupan jalan yang diperbolehkan adalah sebagai berikut :

Tabel 1.8.A.1
Zone Kerja 1-A
HARI JAM
Minggu sampai Kamis -------
Jumat -------
Sabtu -------

Pengoperasain-pengoperasian Kontraktor yang memerlukan penutupan jalan harus dilaksankan dalam


jam-jam yang disebutkan diatas. Pengoperasian ini termasuk pemasangan dan pembongkaran rambu
lalu lintas sementara dan pengalihan. Penutupan jalan di luar yang disebutkan dalam kerangka waktu
yang disebutkan diatas akan menghasilkan penutupan jalan yang tidak sah dan tunduk pada
pemotongan yang disebutkan dalam Pasal 1.8.2.8 dari Spesifikasi ini .

1.8.1.4 Koordinasi antara Berbagai Kontrak Pekerjaan Sipil

Tabel 1.8.A.2
KONTRAK TANGGAL KENDALA KHUSUS

1.8.1.10 Kejadian Khusus dan Hari Libur

Tabel 1.8.A.3
KEJADIAN TANGGAL KENDALA KHUSUS
“Ramadhan” sebagai Tidak boleh ada penutupan setelah matahari
contoh terbenam

1 -37
EINRIP General Specification
Divisi 1 - Umum

SEKSI 1.9

REKAYASA LAPANGAN

1.9.1 UMUM

1.9.1.1 Uraian

Rekayasa Lapangan adalah suatu kegiatan untuk mencari kesesuaian antara rancangan asli
yang ditunjukkan dalam Gambar dengan kebutuhan aktual lapangan. Kegiatan ini terdiri dari
survai lapangan dan analisis data lapangan.

Kontraktor harus menyediakan personil ahli teknik untuk memperlancar pelaksanaan


pelakerjaan sehingga diperoleh mutu, kinerja dan dimensi sesuai yang disyaratkan dalam
ketentuan.

Pada awal pelaksanaan pekerjaan, personil tersebut harus disertakan dalam pelaksanaan suatu
survei lapangan yang lengkap dan menyiapkan laporan hasil survei lapangan untuk
menentukan kondisi fisik dan struktur Lapangan yang ada. Selanjutnya personil tersebut harus
disertakan dalam dalam pematokan (staking out) dan survei seluruh proyek, investigasi dan
pengujian bahan tanah dan campuran aspal, and rekayasa serta penggambaran untuk
menyimpan Dokumen Rekaman Proyek.

1.9.1.2 Pekerjaan Seksi Lain Yang Berkaitan Dengan Seksi Ini

a) Syarat-syarat Kontrak : Pasal-pasal yang


berkaitan
b) Mobilisasi dan Demobilisasi : Seksi 1.2
c) Pelayanan Pengujian Laboratorium : Seksi 1.4
d) Dokumen Rekaman Proyek : Seksi 1.15
e) Usaha Perlindungan Lingkungan Hidup : Seksi 1.17
f) Selokan dan Saluran Air : Seksi 2.1
g) Gorong-gorong dan Drainase Beton : Seksi 2.3
h) Pengembalian Kondisi Perkerasan Lama : Seksi 8.1
i) Pemeliharaan Rutin Perkerasan, Bahu Jalan, Drainase, : Seksi 10.1
Perlengkapan Jalan dan Jembatan
j) Pemeliharaan Jalan Samping dan Jembatan : Seksi 10.2

1.9.2 PEKERJAAN SURVEI LAPANGAN UNTUK REVISI MINOR

1.9.2.1 Uraian

Selama 30 hari pertama sejak periode mobilisasi. Kontraktor harus mengerahkan personil
tekniknya untuk melakukan survei lapangan dan membuat laporan tentang kondisi fisik dan
struktur dari perkerasan, drainase selokan, gorong-gorong, jembatan dan struktur lainnya, dan
perlengkapan jalan lainnya seperti rambu jalan, patok kilometer, pagar pengaman.

Pekerjaan survei lapangan ini harus mencakup inventarisasi geometrik yang meliputi : lebar
perkerasan, kondisi permukaan, jenis lapis permukaan, detil bahu jalan; radius tikungan,
lereng melintang (superelevasi di tikungan), dan kelandaian.

Pelaporan gambar potongan memanjang yang lengkap sepanjang dari tiap tepi jalan haruslah
dalam bentuk baku yang diterima oleh Direksi Pekerjaan dan harus diserahkan kepada Direksi

1 -38
EINRIP General Specification
Divisi 1 - Umum

Pekerjaan dalam jumlah satu asli dan tiga salinan sebagai bagian dari seluruh laporan survei
Kontrakor.

1.9.2.2 Pekerjaan Persiapan

Sebelum pekerjaan survey dimulai Kontraktor harus mempelajari Gambar dalam Kontrak
dan berkonsultasi dengan Direksi Pekerjaan. Kontraktor harus melaksanakan pekerjaan
sesuai dengan maksud dari Gambar dan Spesifikasi, dan tidak boleh mengambil
keuntungan atas setiap kesalahan atau kekurangan dalam Gambar atau perbedaan antara
Gambar dan Spesifikasi dan Kontraktor harus menandai dan memperbaiki setiap kesalahan
atau kekurangan, terutama yang berhubungan dengan lebar perkerasan lama dan lokasi dan
arah setiap pelebaran perkerasan dan struktur untuk drainase. Direksi Pekerjaan akan
melakukan perbaikan dan interpretasi untuk melengkapi Spesifikasi dan Gambar ini.
Bilamana dimensi yang diberikan dalam Gambar atau dapat dihitung, pengukuran
berdasarkan skala tidak boleh digunakan kecuali bila disetujui oleh Direksi Pekerjaan.
Setiap penyimpangan dari Gambar sehubungan dengan kondisi lapangan yang tidak
terantisipasi akan ditentukan dan diperintahkan secara tertulis oleh Direksi Pekerjaan.
Kontraktor dan Direksi Pekerjaan harus mencapai kesepakatan terhadap ketepatan atas
setiap perubahan yang diambil terhadap Gambar dalam Kontrak ini.

1.9.2.3 Survei Kondisi Perkerasan Lama

Kontraktor harus melaksanakan dan melaporkan pekerjaan survei pada jalan lama

1.9.2.4 Kegagalan Dalam Melaksanakan Pekerjaan Survei Lapangan

Penyelesaian pekerjaan survei lapangan yang tepat waktu, yang tercakup dalam Seksi ini
akan sangat menentukan bagi kewajiban Direksi Pekerjaan dalam melaksanakan setiap
revisi minor pada rancangan dan menyediakan gambar pelaksanaan bagi Kontraktor
sebelum dimulainya kegiatan pelaksanaan yang ditentukan.

Oleh karena itu Direksi Pekerjaan akan memantau kemajuan kegiatan survei lapangan oleh
Kontraktor untuk mamastikan bahwa pekerjaan ini dapat diselesaikan dalam kerangka
waktu yang dijadwalkan.

Jika menurut pendapat Direksi Pekerjaan, kemajuan pekerjaan Kontraktor tidak memenuhi
memenuhi waktu yang telah dijadwalkan atau bilamana Kontraktor tidak memulai
pekerjaan tersebut, atau tidak melaksanakan pekerjaan tersebut menurut standar yang
diminta Direksi Pekerjaan, maka Direksi Pekerjaan dapat memilih untuk menyelesaikan
survei lapangan itu dengan sumber dayanya sendiri atau sumber daya lainnya sebagaimana
dipandang perlu.

Dalam hal ini, Direksi Pekerjaan akan mengenakan sanksi yang dirinci dalam Pasal 1.9.7
bilamana menentukan tingkat pembayaran untuk atau dari Kontraktor untuk pekerjaan
survei lapangan yang dilaksanakan sedemkian.

1.9.3 PEKERJAAN SURVEI PELAKSANAAN RUTIN

1.9.3.1 Setelah Direksi Pekerjaan menyelesaikan revisi minor pada rancangan dan menerbitkan
gambar kerja, Kontraktor harus yakin bahwa surveyor telah dilengkapi dengan semua gambar
yang berisi informasi yang paling mutakir tentang lebar perkerasan yang diperlukan dan
potongan melintang standar. Semua pengukuran survei lapangan harus dicatat dalam buku
catatan standar untuk survei lapangan. Lembar halaman yang terlepas tak boleh digunakan.

1 -39
EINRIP General Specification
Divisi 1 - Umum

1.9.3.2 Penomoran Stasiun (Sta.) pada setiap patok kilometer lama di Lapangan harus diperiksa dan
sebuah denah yang menunjukkan dengan pasti posisi setiap patok kilometer yang
berhubungan dengan Chainage proyek. Jika tidak benar-benar mutlak diperlukan untuk
pelaksanaan Pekerjaan, dan tidak ada persetujuan tertulis sebelumnya dari Direksi Pekerjaan,
patok kilometer lama tidak boleh dipindah atau digeser selama Waktu untuk Penyelesaian,
kecuali jika benar-benar mutlak diperlukan untuk pelaksanaan pekerjaan yang sebagaimana
mestinya.

1.9.3.3 Pada lokasi dimana akan diadakan pekerjaan perbaikan tepi perkerasan atau pelebaran,
penampang melintang asli dari jalan lama harus diukur dan dicatat untuk perhitungan
kuantitas.

1.9.3.4 Untuk pengukuran semua lapis perata, dan bilamana diperlukan untuk penyesuaian punggung
jalan (camber), harus diadakan pengukuran profil memanjang sepanjang sumbu jalan jalan
bersama dengan dan profil penampanag melintang.

1.9.4 PENETAPAN TITIK PENGUKURAN

1.9.4.1 Pada umumnya, alinyemen jalan lama, permukaan jalur lalu lintas (carriageway surface), dan
patok kilometer lama harus menjadi patokan untuk memulai pekerjaan pemeliharaan ruti,
kecuali bila diperlukan perubahan kecil pada alinemen jalan, maka dalam hal ini diperlukan
titik kontrol sementara yang akan diterbitkan oleh Direksi Pekerjaan dan data-data detilnya
akan diserahkan kepada Kontraktor bersama dengan semua data yang bersangkutan untuk
menentukan titik pengukuran pada alinyemen yang akan diubah.

1.9.4.2 Jika dipandang perlu menurut pendapat Direksi Pekerjaan maka Kontraktor harus melakukan
survei dengan akurat dan memasang “Bench Mark” (BM) permanen pada lokasi tertentu di
sepanjang proyek untuk memungkinkan revisi minor pada rancangan, pengukuran ketinggian
permukaan perkerasan atau penetapan titik pengukuran (setting out) yang akan dilakukan.
Bench Mark permanen harus dibuat di atas tanah yang tidak akan mudah bergeser.

1.9.4.3 Kontraktor harus memasang titik patok pelaksanaan yang menunjukkan garis dan ketinggian
untuk pekerjaan perbaikan tepi perkerasan, lebar bahu, dan drainase saluran samping sesuai
dengan penampang melintang standar yang diberikan dalam Gambar dan harus mendapatkan
persetujuan Direksi Pekerjaan sebelum memulai pelaksanaan pekerjaan. Jika menurut
pendapat Direksi Pekerjaan, setiap perubahan dari garis dan ketinggian diperlukan, baik
sebelum maupun sesudah penempatan patok, maka Direksi Pekerjaan akan mengeluarkan
perintah yang terinci kepada Kontraktor untuk melaksanakan perubahan tersebut dan
Kontraktor harus mengubah penempatan patok sambil menunggu persetujuan lebih lanjut.

1.9.4.4 Bilamana diperlukan untuk tujuan pengukuran kuantitas, maka Kontraktor harus melakukan
pengukuran penampang melintang pada permukaan tanah asli dalam interval 25 m, atau jika
diperintahkan lain oleh Direksi Pekerjaan. Profil yang diterbitkan harus digambar di atas
kertas kalkir dengan skala, ukuran dan tata letak (layout) sebagaimana yang ditentukan oleh
Direksi Pekerjaan. Gambar penampang melintang harus menunjukkan elevasi permukaan
akhir yang diusulkan, yang diperoleh dari gambar detil rancangan.

Gambar profil asli bersama dengan tiga salinannya harus diserahkan kepada Direksi
Pekerjaan. Direksi Pekerjaan akan menandatangani satu salinan untuk disetujui atau untuk
direvisi, dan selanjutnya dikembalikan kepada Kontraktor.

1 -40
EINRIP General Specification
Divisi 1 - Umum

1.9.4.5 Bilamana Direksi Pekerjaan memandang perlu, maka Kontraktor harus menyediakan semua
instrumen, personil, pekerja dan bahan yang mungkin diperlukan untuk memeriksa penetapan
titik pengukuran (setting out) atau untuk setiap pekerjaan relevan lainnya yang harus
dilakukan.

1.9.4.5 Kontraktor tidak boleh memulai setiap bagian dari Pekerjaan sampai kontraktor elah
memperoleh persetujuan penetapan titik pengukuran dari Pekerjaan tersebut.

1.9.5 TENAGA AHLI REKAYASA LAPANGAN

1.9.5.1 Kontraktor harus menyediakan tenaga ahli dalam bidang konstruksi yang berpengalaman,
untuk mengarahkan dan mengatur kegiatan pekerjaan perbaikan tepi perkerasan, pelaksanaan
overlay, termasuk lapis perata, dan pelaksanaan bahu jalan, saluran samping dan struktur
untuk drainase.

1.9.5.2 Kontraktor harus menyediakan tenaga ahli dalam bidang tanah/aspal yang bertanggung-jawab
atas produksi aspal beton, termasuk pengadaan bahan, pembuatan rumus perbandingan
campuran, penyetelan bukaan penampung dingin dan panas dan semua kebutuhan lainnya
untuk menjamin agar persyaratan campuran aspal panas dapat dipenuhi.

1.9.6 PENGENDALIAN MUTU BAHAN

1.9.6.1 Personil bidang tanah/aspal yang disediakan Kontraktor harus melakukan investigasi sumber
bahan, membuat rancangan campuran percobaan untuk campuran aspal panas, dan secara rutin
melakukan pengujian laboratorium untuk pengendalian mutu bahan aspal, pondasi dan bahu
jalan. Catatan harian dan arsip hasil pengujian harus disimpan dan setiap saat dapat
ditunjukkan kepada Direksi Pekerjaan jika ada pemeriksaan.

1.9.6.2 Seluruh pengujian laboratorium harus dilakukan oleh Kontraktor di bawah pengawasan
Direksi Pekerjaan seperti diuraikan dalam Seksi 1.4 dari Spesifikasi ini.

1.9.7 DASAR PEMBAYARAN

1.9.7.1 Rekayasa Lapangan Rutin Selama Waktu untuk Penyelesaian

Ketentuan Pasal 1.9.3, 1.9.4, 1.9.5, dan 1.9.6 dalam Seksi dari Spesifikasi ini untuk
penyediaan pekerja, bahan dan peralatan untuk semua kegiatan Rekayasa Lapangan Rutin
selama Waktu untuk Penyelesaian harus dipenuhi tanpa pembayaran tambahan dan semua
biaya tersebut harus dipandang telah termasuk dalam Harga Satuan yang telah dimasukkan
dalam berbagai Mata Pembayaran yang tercantum dalam Daftar Kuantitas dan Harga.
Peralatan survei dan peralatan lain yang disediakan Kontraktor harus tetap menjadi milik
Kontraktor setelah Kontrak selesai.

1.9.7.2 Pekerjaan Survei Lapangan Untuk Revisi Minor pada Rancangan

a) Kecuali untuk yang disebutkan di bawah ini, penyediaan semua pekerja, bahan dan
peralatan yang dibutuhkan untuk melaksanakan survei lapangan dengan baik, untuk
menyiapkan penampang memanjang dan gambar-gambar lainnya sebagaimana
diperlukan, dan untuk menyiapkan dan menyediakan laporan survei lapangan menurut
ketentuan yang disyaratkan dalam Seksi dari Spesifikasi ini harus dipenuhi tanpa
pembayaran tambahan dan semua biaya tersebut harus dipandang telah termasuk dalam
Harga Satuan yang dimasukkan dalam berbagai Mata Pembayaran yang tercantum
dalam Daftar Kuantitas dan Harga.

1 -41
EINRIP General Specification
Divisi 1 - Umum

b) Investigasi tanah dan/atau perkerasan yang dilaksanakan bukan untuk keperluan revisi
minor pada rancangan akan dibayar atas dasar Pekerjaan Harian sesuai dengan Seksi
9.1 dari Spesifikasi ini.

c) Bilamana Direksi Pekerjaan mengenakan ketentuan Pasal 1.9.2.4 dan memilih untuk
melaksanakan pekerjaan survei lapangan dengan menggunakan sumber dayanya sendiri
atau pihak lain sehubungan dengan kemajuan pelaksanaan pekerjaan Kontraktor yang
tidak memenuhi jadwal yang telah ditentukan, maka biaya aktual yang dikeluarkan
Direksi Pekerjaan dalam menyelesaikan pekerjaan ini harus sepenuhnya ditanggung
oleh Kontraktor.

1 -42
EINRIP General Specification
Divisi 1 - Umum

SEKSI 1.10

STANDAR RUJUKAN

1.10.1 UMUM

1.10.1.1 Uraian

Bilamana bahan atau pengerjaan yang disyaratkan oleh Spesifikasi ini harus memenuhi atau
melebihi peraturan atau standar yang disebutkan, maka Kontraktor harus bertang-gungjawab
untuk menyediakan bahan dan pengerjaan yang demikian.

Peraturan dan standar yang disebutkan ini akan menetapkan ketentuan mutu untuk berbagai
jenis pekerjaan yang akan dilaksanakan, dan cara pengujian untuk menentukan mutu yang
disyaratkan dapat dicapai.

1.10.1.2 Pekerjaan Seksi Lain Yang Berkaitan Dengan Seksi Ini

a) Syarat-syarat Kontrak : Pasal-pasal yang


berkaitan
b) Pelayanan Pengujian Laboratorium : Seksi 1.4
c) Nama peraturan atau standar yang disebutkan dalam Gambar dan dalam Seksi lain dari
Spesifikasi ini.

1.10.2 JAMINAN MUTU

1.10.2.1 Sewaktu Pengadaan

Dalam pengadaan seluruh jenis bahan yang digunakan dalam pekerjaan ini, Kontraktor
harus bertanggungjawab untuk memeriksa dengan detil ketentuan-ketentuan yang terda-pat
dalam peraturan dan standar yang disebutkan, dan memeriksa bahwa bahan-bahan yang
digunakan dalam pekerjaan ini telah memenuhi atau melebihi ketentuan yang disyaratkan.

1.10.2.2 Sewaktu Pelaksanaan

Direksi Pekerjaan berhak untuk menolak hasil pekerjaan yang tidak memenuhi ketentuan
minimum yang disyaratkan. Direksi Pekerjaan juga berhak, dan tanpa merugikan pihak lain,
untuk menerima hasil pekerjaan yang tidak memenuhi ketentuan dengan cara mengadakan
penyesuaian terhadap Harga Satuan atau Nilai pekerjaan tersebut.

1.10.2.3 Tanggung Jawab Kontraktor

Bilamana disyaratkan dalam Dokumen Kontrak atau diminta secara tertulis oleh Direksi
Pekerjaan, maka Kontraktor tetap harus bertanggungjawab untuk menyerahkan kepada
Direksi Pekerjaan seluruh bukti yang menyatakan bahwa bahan atau pengerjaan, atau
keduanya, memenuhi atau melebihi ketentuan yang terdapat dalam peraturan dan standar yang
disebutkan.

1 -43
EINRIP General Specification
Divisi 1 - Umum

1.10.2.4 Standar

Penggunaan standar yang tercantum dalam Spesifikasi ini mencakup, tetapi tidak terbatas
pada, standar yang dirumuskan oleh badan-badan dan organisasi-organisasi berikut :

SII = Standar Industri Indonesia


SNI = Standar Nasional Indonesia
AASHTO = American Association of State Highway and Transportation Officials
ACI = American Concrete Institute
AISC = American Institute of Steel Construction.
ANSI = American National Standard Institute
ASTM = American Society for Testing and Materials
AWS = American Welding Society Inc.
CRSI = Concrete Reinforcing Steel Institute
NEC = National Electrical Code
BS = British Standards

1.10.2.5 Tanggal Penerbitan

Tanggal pada saat penerbitan Dokumen Kontrak harus diambil sebagai tanggal pener-bitan,
kecuali bilamana disebutkan tanggal penerbitan tertentu maka tanggal penerbitan tersebut
harus diambil sesuai dengan standar yang berkaitan.

1.10.2.6 Dari seluruh spesifikasi ini ekuivalensi berikut ini harus digunakan :

PADANAN AASHTO TERHADAP STANDAR NASIONAL INDONESIA

STANDAR NASIONAL
AASHTO JUDUL
INDONESIA
AASHTO T11-05 SNI 03-4142-1996 Metode Pengujian Jumlah Bahan Dalam Agregat Yang
Lolos Saringan No.200 (0,075 mm).
AASHTO T21-05 SNI 03-2816-1992 Metode Pengujian Kotoran Organik Dalam Pasir Untuk
Campuran Mortar dan Beton.
AASHTO T22-07 SNI 03-1974-1990 Metode Pengujian Kuat Tekan Beton
AASHTO T23-04 SNI 03-4810-1998 Metode Pembuatan dan Perawatan Benda Uji Beton di
La-pangan.
AASHTO T27-06 SNI 03-1968-1990 Metode Pengujian Tentang Analisa Saringan Agregat
Ha-lus dan Kasar.
AASHTO T48-06 SNI 06-2433-1991 Metode Pengujian Titik Nyala dan Titik Bakar Dengan
Cleveland Open Cup.
AASHTO T49-07 SNI 06-2456-1991 Cara Uji Penetrasi Aspal.
AASHTO T51-06 SNI 06-2432-1991 Metode Pengujian Daktilitas Bahan-bahan Aspal.
AASHTO T53-06 SNI 06-2434-1991 Cara Uji Titik Lembek Aspal dengan Alat Cincin dan
Bola (Ring and Ball).
AASHTO T55-02 SNI 06-2490-1991 Cara Uji Kadar Air dalam Produk Minyak dan Bahan
(2006) Mengandung Aspal dengan Cara Penyulingan.
AASHTO T78-05 SNI 06-2488-1991 Metode Pengujian Fraksi Aspal Cair Dengan Cara
Penyulingan.
AASHTO T84-00 SNI 03-1970-1990 Cara Uji Berat Jenis dan Penyerapan Agregat Kasar.
(2004)

1 -44
EINRIP General Specification
Divisi 1 - Umum

STANDAR NASIONAL
AASHTO JUDUL
INDONESIA
AASHTO T85-891 SNI 03-1969-1990 Cara Uji Berat Jenis dan Penyerapan Air Agregat Halus.
(2004)
AASHTO T87-86 SNI 03-1975-1990 Metode Mempersiapkan Contoh Tanah dan Tanah Me-
(2004) ngandung Agregat.
AASHTO T88-00 SNI 03-3423-1994 Cara Uji Analisis Ukuran Butir Tanah.
(2004)
AASHTO T89-02 SNI 03-1967-1990 Cara Uji Penentuan Batas Cair untuk Tanah.
AASHTO T90-00 SNI 03-1966-1990 Cara Uji Penentuan Batas Plastis dan Indeks Plastisitas
(2004) Tanah.
AASHTO T96-02 SNI 03-2417-1991 Cara Uji Keausan Agregat dengan Mesin Abrasi Los
(2006) Angeles.
AASHTO T99-01 SNI 03-1742-1989 Cara Uji Kepadatan Ringan untuk Tanah.
(2004)
AASHTO T104-99 SNI 03-3407-1994 Cara Uji Sifat Kekekalan Agregat dengan Cara
(2003) Perendaman Menggunakan Larutan Natrium Sulfat atau
Magnesium Sulfat.
AASHTO T106M/ SNI 03-6825-2002 Metode Pengujian Kekuatan Tekan Mortar Semen
T106-07 Portland Untuk Pekerjaan Sipil.
AASHTO T112-00 SNI 03-4141-1996 Metode Pengujian Gumpalan Lempung dan Butir-butir
(2004) Mudah Pecah Dalam Agregat.
AASHTO T119-07 SNI 03-1972-1990 Metode Pengujian Slump Beton.
AASHTO T126-90 SNI 03-2493-1991 Metode Pembuatan dan Perawatan Benda Uji Beton Di
Laboratorium.
AASHTO T128-86 SNI 15-2530-1991 Metode Pengujian Kehalusan Semen Portland.
AASHTO T129-06 SNI 03-6826-2002 Metode Pengujian Konsistensi Normal Semen Portland
Dengan Alat Vicat Untuk Pekerjaan Sipil.
AASHTO T131-06 SNI 03-6827-2002 Metode Pengujian Waktu Ikat Awal Semen Portland
Dengan Alat Vicat Untuk Pekerjaan Sipil.
AASHTO T133-98 SNI 15-2531-1991 Metode Pengujian Berat Jenis Semen Portland.
(2006)
AASHTO T134-05 SNI 03-6886-2002 Metode Pengujian Hubungan Antara Kadar Air dan
Kepadatan pada Campuran Tanah Semen
AASHTO T135-97 SNI 13-6427-2000 Metode Pengujian Uji Basah dan Kering Campuran
(2005) Tanah Semen Dipadatkan
AASHTO T141-05 SNI 03-2458-1991 Metode Pengujian Pengambilan Contoh Untuk
Campuran Beton Segar.
AASHTO T144-86 SNI 03-6412-2000 Metode Pengujian Kadar Semen pada Campuran Segar
Semen Tanah.
AASHTO T164 -06 SNI-03-6894-2002 Metode Pengujian Kadar Aspal dan Campuran Beraspal
Cara Sentrifius
AASHTO T165-02 SNI 03-6753-2002 Cara Uji Ketahanan Campuran Beraspal Terhadap
(2006) Kerusakan Akibat Rendaman.
AASHTO T166-07 SNI 03-6756-2002 Metode Pengujian untuk Menentukan Tingkat Kepadatan
Perkerasan Beraspal.
AASHTO T170-00 SNI 03-4797-1998 Metode Pengujian Pemulihan Aspal Dengan Alat
(2005) Penguap Putar.
AASHTO T176-02 SNI 03-4478-1997 Metode Pengujian Agregat Halus Atau Pasir Yang Me-
ngandung Bahan Plastis Dengan Cara Setara Pasir.

1 -45
EINRIP General Specification
Divisi 1 - Umum

STANDAR NASIONAL
AASHTO JUDUL
INDONESIA
AASHTO T179-05 SNI 06-2440-1991 Metode Pengujian Kehilangan Berat Minyak dan Aspal
Dengan Cara A.
AASHTO T180-01 SNI 03-1743-1989 Cara Uji Kepadatan Berat untuk Tanah.
(2004)
AASHTO T182-84 SNI 03-2439-1991 Cara Uji Penyelimutan dan Pengelupasan Pada
(2002) Campuran Agregat-Aspal.
AASHTO T191-02 SNI 03-2828-1992 Metode Pengujian Kepadatan Lapangan Dengan Alat
(2006) Ko-nus Pasir.
AASHTO T193-99 SNI 03-1744-1989 Metode Pengujian CBR Laboratorium.
(2003)
AASHTO T209-05 SNI 03-6893-2002 Metode Pengujian Berat Jenis Maksimum Campuran
Beraspal.
AASHTO T228-06 SNI 06-2441-1991 Metode Pengujian Berat Jenis Aspal Padat.
AASHTO T245-97 SNI 06-2489-1991 Metode Pengujian Campuran Aspal Dengan Alat
(2004) Marshall.
AASHTO T255-96 SNI 03-1971-1990 Metode Pengujian Kadar Air Agregat.
(2004)
AASHTO T258-81 SNI 03-6795-2002 Metode Pengujian unuk Menentukan Tanah Ekspansif
(2004)
AASHTO M6-03 SNI 03-6820-2002 Spesifikasi Agregat Halus Untuk Pekerjaan Adukan dan
Plesteran Dengan Bahan Dasar Semen.
AASHTO M17-07 SNI 03-6723-2002 Spesifikasi Bahan Pengisi untuk Campuran Aspal.
AASHTO M29-03 SNI 03-6819-2002 Spesifikasi Agregat Halus Untuk Campuran Perkerasan
Aspal.
AASHTO M81-92 SNI 03-4800-1998 Spesifikasi Aspal Cair Tipe Penguapan Cepat.
(2004)
AASHTO M82-75 SNI 03-4799-1998 Spesifikasi Aspal Cair Tipe Penguapan Sedang.
(2004)
AASHTO M85-07 SII 0013-81 Semen Portland
AASHTO M145-91 SNI 03-6797-2002 Tata Cara Klasifikasi Tanah dan Campuran Tanah
(2004) Agregat untuk Konstruksi Jalan
AASHTO M179-84 SNI 03-6799-2002 Spesifikasi Pipa Saluran Dari Tanah Lempung.
(1990)
AASHTO M208-01 SNI 03-4798-1998 Spesifikasi Aspal Emulsi Kationik.
(2005)
AASHTO M247-07 SNI 15-4839-1998 Spesifikasi Manik-manik Kaca (Glass Bead) Untuk
Marka Jalan
AASHTO M248-91 SNI 06-4825-1998 Spesifikasi Campuran Cat Marka Jalan Siap Pakai
(2003) Warna Putih dan Kuning
AASHTO M249-98 SNI 06-4826-1998 Spesifikasi Cat Termoplastik Pemantul Warna Putih dan
(2003) Warna Kuning Untuk Marka Jalan (Bentuk Padat )
AASHTO M251-06 SNI 03-4816-1998 Spesifikasi Bantalan Karet Untuk Perletakan Jembatan

1 -46
EINRIP General Specification
Divisi 1 - Umum

PADANAN ASTM TERHADAP STANDAR NASIONAL INDONESIA

STANDAR NASIONAL
ASTM JUDUL
INDONESIA
ASTM C 1252 – 93 Metode Pengujian Kadar Rongga Agregat Halus yang
SNI 03-6877-2002
or AASHTO TP-33 tidak dipadatkan.
ASTM D 1632 - 63 SNI 03-6798-2002 Tata Cara Pembuatan dan Perawatan Benda Uji Kuat
Tekan dan Lentur Tanah Semen di Laboratorium.
ASTM D 1633 - 94 SNI 03-6887-2002 Metode Pengujian Kuat Tekan Bebas Tanah Semen.

PADANAN BRITISH STANDARD TERHADAP STANDAR NASIONAL INDONESIA

BRITISH STANDAR NASIONAL


JUDUL
STANDARD INDONESIA
BS 1924 Test 18 SNI 19-6426-2000 Metoda Pengujian Pengukuran pH Pasta Tanah Semen
untuk Stabilisasi.
BSI 1973 SNI 03-2834-2000 Tata Cara Pembuatan Rencana Campuran Beton Normal

1 -47
EINRIP General Specification
Divisi 1 - Umum

SEKSI 1.11

BAHAN DAN PENYIMPANAN

1.11.1 UMUM

1.11.1.1 Uraian

Bahan yang dipergunakan di dalam Pekerjaan harus :

a) Memenuhi spesifikasi dan standar yang berlaku.

b) Memenuhi ukuran, pembuatan, jenis dan mutu yang disyaratkan dalam Gambar dan
Seksi lain dari Spesifikasi ini, atau sebagaimana secara khusus disetujui tertulis oleh
Direksi Pekerjaan.

c) Semua produk harus baru.

1.11.1.2 Pekerjaan Seksi Lain Yang Berkaitan Dengan Seksi Ini

a) Syarat-syarat Kontrak : Pasal-pasal yang


berkaitan
b) Transportasi dan Penanganan : Seksi 1.5
c) Pekerjaan Pembersihan : Seksi 1.16
d) Usaha Perlindungan Lingkungan Hidup : Seksi 1.17

1.11.1.3 Pengajuan

a) Sebelum mengadakan pemesanan atau membuka daerah sumber bahan untuk setiap
jenis bahan, maka Kontraktor harus menyerahkan kepada Direksi Pekerjaan contoh
bahan, bersama dengan detil lokasi sumber bahan dan Pasal ketentuan bahan dalam
Spesifikasi yang mungkin dapat dipenuhi oleh contoh bahan, untuk mendapatkan
persetujuan

b) Kontraktor harus melakukan semua pengaturan untuk memilih lokasi, memilih bahan,
dan mengolah bahan alami sesuai dengan Spesifikasi ini, dan harus menyerahkan
kepada Direksi Pekerjaan semua informasi yang berhubungan dengan lokasi sumber
bahan paling sedikit 30 hari sebelum pekerjaan peng-olahan bahan dimulai, untuk
mendapatkan persetujuan. Persetujuan Direksi Pekerjaan atas sumber bahan tersebut
tidak dapat diartikan bahwa seluruh bahan yang terdapat di lokasi sumber bahan telah
disetujui untuk dipakai.

c) Bilamana bahan aspal, semen, baja dan bahan-bahan fabrikasi lainnya akan digunakan,
maka sertifikat pabrik (mill certificate) bahan tersebut harus diserahkan kepada Direksi
Pekerjaan untuk mendapatkan persetujuan awal. Direksi Pekerjaan akan memberikan
persetujuan tertulis kepada Kontraktor untuk melakukan pemesanan bahan. Selanjutnya
bahan yang sudah sampai di lapangan harus diuji di bawah pengawasan Direksi
Pekerjaan atau sebagaimana yang diperintahkan oleh Direksi Pekerjaan.

1.11.2 PENGADAAN BAHAN

1.11.2.1 Sumber Bahan

Kontraktor tetap harus bertanggungjawab untuk mengidentifikasi dan memeriksa ualang


apakah bahan tersebut cocok untuk dipergunakan dalam pelaksanaan pekerjaan.

1 -48
EINRIP General Specification
Divisi 1 - Umum

1.11.2.2 Variasi Mutu Bahan

Kontraktor harus menentukan sendiri jumlah serta jenis peralatan dan pekerja yang dibutuhkan
untuk menghasilkan bahan yang memenuhi Spesifikasi. Kontraktor harus menyadari bahwa
contoh-contoh bahan tersebut tidak mungkin dapat menentukan batas-batas mutu bahan
dengan tepat pada seluruh deposit, dan variasi mutu bahan harus dipandang sebagai hal yang
biasa dan sudah diperkirakan. Direksi Pekerjaan dapat memerintahkan Kontraktor untuk
melakukan pengadaan bahan dari setiap tempat pada suatu deposit dan dapat menolak tempat-
tempat tertentu pada suatu deposit yang tidak dapat diterima.

1.11.2.3 Persetujuan

a) Pemesanan bahan tidak boleh dilakukan sebelum mendapat persetujuan tertulis dari
Direksi Pekerjaan sesuai dengan maksud penggunaannya. Bahan tidak boleh
dipergunakan untuk maksud lain selain dari peruntukan yang telah disetujui.

b) Jika mutu bahan yang dikirim ke lapangan tidak sesuai dengan mutu bahan yang
sebelumnya telah diperiksa dan diuji, maka bahan tersebut harus ditolak, dan harus
disingkirkan dari lapangan dalam waktu 48 jam, kecuali terdapat persetujuan lain dari
Direksi Pekerjaan.

1.11.3 PENYIMPANAN BAHAN

1.11.3.1 Umum

Bahan harus disimpan sedemikian rupa sehingga mutunya terjamin dan terpelihara serta siap
dipergunakan untuk Pekerjaan. Bahan yang disimpan harus ditempatkan sedemikian rupa
sehingga selalu siap pakai, dan mudah diperiksa oleh Direksi Pekerjaan. Tanah dan bangunan
(property) orang lain tidak boleh dipakai tanpa ijin tertulis dari pemilik atau penyewanya.

1.11.3.2 Tempat Penyimpanan di Lapangan

Tempat penyimpanan di lapangan harus bebas dari tanaman dan sampah, bebas dari genangan
air dan permukaannya harus lebih tinggi dari sekitarnya. Bahan yang langsung ditempatkan
diatas tanah tidak boleh digunakan untuk Pekerjaan, kecuali jika permukaan tanah tersebut
telah disiapkan sebelumnya dan diberi lapis permukaan yang terbuat dari pasir atau kerikil
setebal 10 cm sedemikian hingga diterima oleh Direksi Pekerjaan.

1.11.3.3 Penumpukan Bahan (Stockpiles)

a) Bahan harus disimpan sedemikian hingga dapat mencegah terjadinya segregasi dan
menjamin gradasi yang sebagaimana mestinya, serta tidak terdapat kadar air yang
berlebihan. Tinggi maksimum dari penumpukan bahan harus dibatasi sampai
maksimum 5 meter

b) Penumpukan berbagai jenis agregat yang akan dipergunakan untuk campuran aspal,
burtu atau burda, penetrasi macadam atau beton harus dilakukan secara terpisah
menurut masing-masing ukuran nominal agregat. Dinding pemisah dari papan dapat
digunakan untuk harus mencegah tercampurnya agregat-agregat tersebut.

c) Tumpukan agregat untuk untuk lapis pondasi atas dan bawah harus dilindungi dari
hujan untuk mencegah terjadinya kejenuhan agregat yang akan mengurangi mutu bahan
yang dihampar atau paling tidak mempengaruhi penghamparan bahan.

1 -49
EINRIP General Specification
Divisi 1 - Umum

1.11.4 PEMBAYARAN

1.11.4.1 Kontraktor harus melakukan semua pengaturan dengan pemilik atau pemakai lahan untuk
memperoleh hak konsesi yang diperlukan sehingga dapat mengambil bahan yang akan
digunakan dalam Pekerjaan. Kontraktor bertanggungjawab atas semua kompensasi dan
restribusi yang harus dibayarkan sehubungan dengan penggalian bahan atau keperluan
lainnya. Tidak ada pembayaran terpisah yang akan dilakukan untuk kompensasi dan restribusi
yang dibayar Kontraktor, dan seluruh biaya tersebut harus sudah dimasukkan ke dalam Harga
Satuan untuk mata pembayaran yang terkait dalam Daftar Kuantitas dan Harga.

1.11.4.2 Kontraktor harus bertanggungjawab untuk membuat jalan masuk, membuang gundukan tanah
dan semua biaya pelaksanaan lainnya yang diperlukan untuk pengadaan bahan, termasuk
pengembalian lapisan humus dan meninggalkan daerah dan jalan masuk itu dalam kondisi rapi
dan dapat diterima. Seluruh biaya tersebut harus sudah dimasukkan ke dalam Harga Satuan
untuk mata pembayaran yang terkait dalam Daftar Kuantitas dan Harga.

1 -50
EINRIP General Specification
Divisi 1 - Umum

SEKSI 1.12

JADWAL PELAKSANAAN

1.12.1 UMUM

1.12.1.1 Uraian

Jadwal pelaksanaan diperlukan untuk perencanaan, pelaksanaan dan pemantauan yang


sebagaimana mestinya atas pekerjaan. Jadwal tersebut diperlukan untuk menjelaskan kegiatan-
kegiatan pekerjaan setelah kegiatan dalam program mobilisasi telah selesai.

1.12.1.2 Pekerjaan Seksi Lain Yang Berkaitan Dengan Seksi Ini

a) Syarat-syarat Kontrak : Pasal-pasal yang


berkaitan
b) Mobilisasi dan Demobilisasi : Seksi 1.2
c) Rekayasa Lapangan : Seksi 1.9
d) Bahan dan Penyimpanan : Seksi 1.11
e) Prosedur Variasi : Seksi 1.13

1.12.1.3 Pengajuan

a) Kontraktor harus menyiapkan jadwal pelaksanaan dalam batas waktu 15 hari setelah
Surat Penunjukan Pemenang. Jadwal pelaksanaan itu harus diserahkan dan mendapat
persetujuan dari Direksi Pekerjaan, dengan detil yang disyaratkan dalam Pasal 1.12.2
dari Spesifikasi ini, dimana detil tersebut harus menunjukkan urutan kegiatan yang
diusulkan oleh Kontraktor dalam melaksanakan Pekerjaan.

b) Setiap akhir setiap bulan Kontraktor harus melengkapi Jadwal Pelaksanaan untuk
menggambarkan secara akurat kemajuan pekerjaan (progress) aktual sampai tanggal 25
pada bulan tersebut.

c) Setiap interval mingguan Kontraktor harus menyerahkan pada setiap hari Senin pagi,
jadwal kegiatan mingguan yang menunjukkan lokasi seluruh operasi dan kegiatan yang
akan dilaksanakan selama minggu tersebut.

d) Jadwal Pelaksanaan untuk Sub Kontraktor harus diserahkan terpisah atau men-jadi satu
dalam seluruh jadwal pelaksanaan.

1.12.2 DETIL JADWAL PELAKSANAAN

1.12.2.1 Jadwal Kemajuan Keuangan

Kontraktor harus membuat Jadwal Kemajuan Keuangan dalam bentuk diagram balok
horisontal dan dilengkapi kurva yang menggambarkan seluruh kemajuan pekerjaan dengan
karakteristik berikut :

a) Setiap jenis Mata Pembayaran atau kegiatan dari kelompok Mata Pembayaran yang
berkaitan harus digambarkan dalam diagram balok yang terpisah, dan harus dibentuk
sesuai dengan urutan dari masing-masing kegiatan pekerjaan.

b) Skala waktu dalam arah horisontal harus dinyatakan berdasarkan satuan bulan.

1 -51
EINRIP General Specification
Divisi 1 - Umum

c) Setiap diagram balok horisontal harus mempunyai ruangan untuk mencatat kemajuan
aktual dari setiap pekerjaan dibandingkan dengan kemajuan rencana.

d) Kurva seluruh kemajuan pekerjaan (overall progress) harus dapat memberikan


gambaran tentang kemajuan keuangan rencana pada setiap akhir bulan terhadap
kemajuan keuangan aktual.

e) Skala dan format dari Jadwal Kemajuan Keuangan harus sedemikian rupa hingga
tersedia ruangan untuk pencatatan, revisi dan pemutakhiran mendatang. Ukuran lembar
kertas minimum adalah A3.

1.12.2.2 Analisa Jaringan (Network Analysis)

Jika diperlukan oleh Direksi Pekerjaan, Kontraktor harus menyediakan Analisa Jaringan yang
menunjukkan awal dan akhir setiap tanggal mulainya suatu kegiatan sehingga dapat diperoleh
suatu jadwal jalur kritis (critical path schedule) dan dapat diperoleh jadwal untuk menentukan
jenis-jenis pekerjaan yang kritis dalam seluruh jadwal pelaksanaan.

1.12.2.3 Jadwal Produksi Untuk Instalasi Pencampur Aspal (AMP) dan Peralatan Pendukung

Kontraktor harus menyediakan Jadwal untuk Instalasi Pencampur Aspal dan Peralatan
Pendukung secara terpisah, disertai dengan suatu perhitungan yang menunjukkan bahwa hasil
produksi Instalasi Pencampur Aspal dapat tercapai sesuai rencana kebutuhan.

1.12.2.4 Jadwal Penyediaan Bahan

Kontraktor harus menyediakan jadwal yang terpisah untuk lokasi semua sumber bahan,
bersama dengan rencana tanggal penyerahan contoh-contoh bahan dan rencana produksi
bahan dan jadwal pengiriman.

1.12.2.5 Jadwal Pelaksanaan Jembatan

Kontraktor harus menyediakan jadwal pelaksanaan setiap jembatan dengan skala balok
horisontal untuk setiap jenis pekerjaan dan pelengkapnya untuk pencatatan kemajuan
pekerjaan (progress) aktual terhadap program untuk setiap mata pembayaran.

1.12.3 REVISI PROGRAM (JADWAL PELAKSANAAN)

1.12.3.1 Waktu

Jika, pada setiap saat :

a) Kemajuan pekerjaan aktual terlalu lambat untuk dapat selesai dalam Waktu unuk
Penyelesaian, dan/atau

b) Kemajuan pekerjaan jatuh (atau akan jatuh) lebih lambat dari program yang sedang
berjalan menurut Ayat 8.3 [Program] dari Syarat-syarat Kontrak, selain dari akibat
yang disebabkan oleh daftar yang terdapat dalam Ayat 8.4 [Perpanjangan Waktu
untuk Penyelesaian] dari Syarat-syarat Kontrak, selanjutnya Direksi Pekerjaan dapat
memerintahkan Kontraktor untuk mengajukan, menurut Ayat 8.3 [Program] dari
Syarat-syarat Kontrak, suatu revisi program dan laporan pendukung yang
menguraikan usulan revisi metoda yang akan diambil Kontraktor agar dapat
mempercepat kemajuan pekerjaan dan selesai dalam Waktu untuk Penyelesaian.

1 -52
EINRIP General Specification
Divisi 1 - Umum

1.12.3.2 Laporan

Pada saat menyerahkan Revisi Jadwal Pelaksanaan maka Kontraktor harus melengkapi
laporan ringkas yang memberikan alasan-alasan timbulnya revisi, yang harus meliputi :

a) Uraian revisi, termasuk pengaruh pada seluruh jadwal karena adanya perubahan
cakupan, revisi dalam kuantitas atau perubahan jangka waktu kegiatan dan perubahan
lainnya yang dapat mempengaruhi jadwal.

b) Pembahasan lokasi-lokasi ynag bermasalah, termasuk faktor-faktor penghambat yang


sedang berlangsung maupun yang harus diperkirakan serta dampaknya.

c) Usulan revisi metoda yang akan diambil Kontraktor agar dapat mempercepat kemajuan
pekerjaan dan selesai dalam Waktu untuk Penyelesaian, dan dampaknya.

1 -53
EINRIP General Specification
Divisi 1 - Umum

SEKSI 1.13

PROSEDUR VARIASI

1.13.1 UMUM

1.13.1.1 Uraian

Perubahan-perubahan atas pekerjaan dapat terjadi karena diprakarsai baik oleh Direksi
Pekerjaan maupun oleh Kontraktor, dan harus disepakati serta ditandatangani oleh kedua
belah pihak yang dituangkan dalam Variasi. Bilamana dasar pembayaran yang dituang-kan
dalam Variasi tersebut mengakibatkan variasi dalam Struktur Harga Satuan Mata Pembayaran
atau variasi dalam Jumlah Harga Kontrak, maka Variasi tersebut harus dinegosiasi dan
dituangkan dalam Addendum Kontrak.

Variasi dan Addenda Kontrak harus memenuhi ketentuan berikut :

a) Variasi :

Perintah tertulis yang dibuat oleh Direksi Pekerjaan dan ditandatangani pula oleh
Kontraktor, menunjukkan bahwa Kontraktor menerima perubahan-perubahan dalam
Pekerjaan atau Dokumen Kontrak, persetujuan Kontraktor atas dasar pembayaran dan
penyesuaian waktu, jika ada, untuk pelaksanaan atas perubahan-perubahan tersebut.
Variasi harus diterbitkan dalam format standar dan harus mencakup semua perintah
yang dikeluarkan oleh Direksi Pekerjaan yang akan mempengaruhi perubahan
Dokumen Kontrak atau perintah sebelumnya yang telah dikeluarkan oleh Direksi
Pekerjaan.

b) Addenda :

Perjanjian tertulis antara Pemilik dan Kontraktor, yang memuat perubahan-perubahan


dalam Pekerjaan atau Dokumen Kontrak yang mengakibatkan variasi dalam struktur
Harga Satuan Mata Pembayaran atau variasi yang diperkirakan dalam Jumlah Harga
Kontrak dan telah dinegosiasi dan disepakati terlebih dahulu dalam Variasi. Addenda
juga harus dibuat pada saat penutupan Kontrak dan semua perubahan kontraktual atau
teknis penting lainnya tanpa memandang apakah terjadi variasi struktur Harga Satuan
atau Jumlah Harga Kontrak

1.13.1.2 Pekerjaan Seksi Lain Yang Berkaitan Dengan Seksi Ini

a) Syarat-syarat Kontrak : Pasal-pasal yang


berkaitan
b) Pembayaran Sertifikat Bulanan : Seksi 1.6
c) Rekayasa Lapangan : Seksi 1.9
d) Jadwal Pelaksanaan : Seksi 1.12
e) Penutupan Kontrak : Seksi 1.14
f) Dokumen Rekaman Proyek : Seksi 1.15

1.13.1.3 Pengajuan

a) Pihak Kontraktor harus menunjuk secara tertulis salah seorang anggota dalam
perusahaannya untuk menerima variasi dalam Pekerjaan dan bertanggungjawab untuk
memberitahu kepada para pelaksana lainnya tentang adanya variasi tersebut.
b) Direksi Pekerjaan akan menunjuk secara tertulis orang yang diberi wewenang untuk
mengurus prosedur Variasi atas nama Pemilik.

1 -54
EINRIP General Specification
Divisi 1 - Umum

c) Kontraktor harus melengkapi perhitungan untuk setiap usulan pekerjaan yang akan
dibayar lump sum, dan untuk setiap Harga Satuan yang belum ditetapkan sebelumnya
dengan data pendukung yang lengkap sehingga dapat dievaluasi oleh Direksi Pekerjaan.

1.13.2 PROSEDUR AWAL VARIASI

1.13.2.1 Direksi Pekerjaan dapat memprakarsai Variasi dengan memberitahu secara tertulis kepada
Kontraktor, uraian berikut :

a) Uraian detil usulan perubahan dan lokasinya dalam proyek.

b) Gambar dan Spesifikasi tambahan atau revisinya untuk melengkapi detil usulan
perubahan.

c) Perkiraan jangka waktu yang diperlukan untuk membuat usulan perubahan.

d) Baik usulan perubahan dapat dilaksanakan menurut struktur Harga Satuan Mata
Pembayaran yang ada, maupun setiap Harga Satuan baru atau Jumlah Harga tambahan
yang diperlukan harus disepakati terlebih dahulu untuk kemudian dituangkan ke dalam
Addendum Kontrak.

Pemberitahuan yang demikian hanya merupakan informasi, dan bukan sebagai suatu perintah
untuk melakukan perubahan dan juga bukan untuk menghentikan pekerjaan yang sedang
berlangsung.

1.13.2.2 Kontraktor dapat mengajukan permohonan perubahan dengan memberitahu secara tertu-lis
kepada Direksi Pekerjaan, uraian berikut :

a) Uraian usulan perubahan.

b) Keterangan tentang alasan untuk mengajukan perubahan.

c) Keterangan tentang pengaruh terhadap Jadwal Pelaksanaan (bila ada).

d) Keterangan tentang pengaruh terhadap pekerjaan Sub Kontraktor (bila ada).

e) Penjelasan detil baik untuk semua maupun sebagian dari usulan perubahan akan
dilaksanakan menurut struktur Harga Satuan Mata Pembayaran yang ada, bersama
dengan setiap Harga Satuan baru atau Jumlah Harga yang dipandang Kontraktor
memerlukan kesepakatan.

1.13.3 PELAKSANAAN VARIASI

1.13.3.1 Isi Variasi akan didasarkan pada salah satu dari :

a) Permintaan Direksi Pekerjaan dan jawaban Kontraktor sebagaimana disepakati bersama


antara Direksi Pekerjaan dan Kontraktor; atau

b) Permohonan Kontraktor atas suatu perubahan, sebagaimana diterima oleh Direksi


Pekerjaan

1.13.3.2 Direksi Pekerjaan akan menyiapkan Variasi dan memberi nomor urut Variasi tersebut.

1 -55
EINRIP General Specification
Divisi 1 - Umum

1.13.3.3 Variasi akan menguraikan perubahan dalam Pekerjaan, baik penambahan maupun
penghapusan, dengan lampiran Dokumen Kontrak yang direvisi seperlunya untuk menentukan
detil perubahan tersebut.

1.13.3.4 Variasi akan menetapkan dasar pembayaran dan setiap penyesuaian waktu yang dibutuhkan
sebagai akibat adanya perubahan tersebut, dan bilamana diperlukan, akan menetapkan setiap
Harga Satuan baru atau Jumlah Harga tambahan yang telah dinegosiasi sebelumnya antara
Direksi Pekerjaan dan Kontraktor, yang diperlukan untuk dituangkan dalam Addendum.

1.13.3.5 Direksi Pekerjaan akan menandatangani dan memberi tanggal Variasi tersebut sebagai
perintah supaya Kontraktor dapat memulai melaksanaan perubahan.

1.13.3.6 Kontraktor harus menandatangani dan memberi tanggal Variasi tersebut, untuk menun-jukkan
bahwa Kontraktor sepakat atas detil didalam perubahan tersebut.

1.13.4 PELAKSANAAN ADDENDA

1.13.4.1 Isi Addenda akan didasarkan pada salah satu dari hal-hal berikut :

a) Perintah Pemilik untuk melaksanakan perubahan atas Dokumen Kontrak, atau;

b) Karena adanya perubahan kontraktual atau teknis yang penting, atau;

c) Variasi atau Variasi-variasi yang telah ditandatangani yang berisi Harga Satuan Mata
Pembayaran baru atau Jumlah Harga tambahan, atau;

d) Karena adanya perubahan perkiraan kuantitas sebagai akibat suatu variasi dalam
Jumlah Harga Kontrak, sebagaimana yang dimasukkan ke dalam Perjanjian Kontrak
atau Addendum sebelumnya, atau;

e) Perhitungan kuantitas akhir dan Jumlah Harga Kontrak. untuk Addenda Penutup pada
saat Penutupan Kontrak;

1.13.4.2 Direksi Pekerjaan akan menyiapkan Addendum.

1.13.4.3 Addendum akan menguraikan setiap perubahan kontraktual, teknis atau kuantitas, baik
penambahan ataupun penghapusan mata pembayaran, dengan lampiran-lampiran Dokumen
Kontrak yang direvisi untuk menentukan detil perubahan.

1.13.4.4 Addendum akan memberikan perhitungan ringkas untuk setiap tambahan atau penye-suaian
Harga Satuan bersama dengan setiap variasi dalam Harga Kontrak atau penyesuaian Periode
Kontrak.

1.13.4.5 Pemilik dan Kontraktor akan menandatangani Addendum tersebut dan menyampai-kannya
kepada Pemilik untuk persetujuan dan tandatangannya.

1 -56
EINRIP General Specification
Divisi 1 - Umum

SEKSI 1.14

PENUTUPAN KONTRAK

1.14.1 UMUM

1.14.1.1 Kontraktor harus mengikuti semua ketentuan seperti disebutkan dalam Syarat-syarat Kontrak
dan Spesifikasi yang menyangkut Penutupan Kontrak.

1.14.1.2 Pekerjaan Seksi Lain Yang Berkaitan Dengan Seksi Ini

a) Syarat-syarat Kontrak : Pasal-pasal yang


berkaitan
b) Pembayaran Sertifikat Bulanan : Seksi 1.6
c) Prosedur Variasi : Seksi 1.13
d) Dokumen Rekaman Proyek : Seksi 1.15
e) Pekerjaan Pembersihan : Seksi 1.16

1.14.2 SERTIKAT KINERJA

1.14.2.1 Waktu

Dalam batas waktu dan sesuai dengan ketentuan pada Pasal-pasal yang berkaitan dalam
Syarat-syarat Kontrak dan bilamana Kontraktor menganggap bahwa Pekerjaan tersebut telah
selesai, termasuk semua kewajiban dalam Periode Pemberitahuan Cacat Mutu, maka
Kontraktor harus mengajukan permohonan untuk penyerahan akhir. Setelah penyelesaian
seluruh pekerjaan perbaikan (remedial work) yang diminta oleh Panitia Serah Terima, dan
dilanjutkan dengan pemeriksaan akhir dan Pekerjaan tersebut dapat diterima, maka Direksi
Pekerjaan harus menyiapkan dan menerbitkan Sertifikat KInerja.

1.14.2.2 Isi Permohonan Kontraktor

Permohonan penerbitan Sertifikat Kinerja harus memuat keterangan Kontraktor berikut :

a) Dokumen Kontrak telah sepenuhnya ditelaah, dan;

b) Pekerjaan telah dilaksanakan sesuai dengan Dokumen Kontrak, dan;

c) Pekerjaan telah sepenuhnya diperiksa dan diuji sesuai dengan ketentuan dalam
Dokumen Kontrak, dan bahwa semua pemeriksaan dan hasil pengujian telah diterima
oleh Direksi Pekerjaan, dan;

d) Pekerjaan telah lengkap dan siap untuk pemeriksaan akhir dan Sertifikat Kinerja.

1.14.3 SERTIFIKAT PEMBAYARAN AKHIR

1.14.3.1 Waktu

Dalam batas waktu dan sesuai dengan ketentuan pada Pasal-pasal yang berkaitan dalam
Syarat-syarat Kontrak, Kontraktor harus mengajukan permohonan pembayaran akhir bersama
dengan semua detil pendukung sebagaimana diperlukan oleh Direksi Pekerjaan. Setelah
ditelaah oleh Direksi pekerjaan dan jika perlu diamandemen oleh Kontraktor, Direksi
Pekerjaan akan menerbitkan Sertifikat Pembayaran Akhir untuk pembayaran oleh Pemilik.

1 -57
EINRIP General Specification
Divisi 1 - Umum

1.14.3.2 Isi Sertifikat

Isi Sertifikat untuk Pembayaran Akhir yang diterbitkan oleh Direksi Pekerjaan, harus
termasuk, tetapi tidak terbatas pada hal-hal berikut :

a) Jumlah Harga Kontrak seperti yang tercantum dalam Kontrak.

b) Kuantitas akhir pekerjaan yang telah diselesaikan seperti yang dibuktikan dalam
Sertifikat pengukuran dan hasil perhitungan pada pekerjaan yang bersangkutan

c) Nilai setiap pekerjaan tambah atau kurang seperti disahkan dalam Addenda selama
Periode Kontrak.

d) Nilai setiap penambahan atau pengurangan terhadap Jumlah Harga Kontrak sebagai
akibat dari :

i) Denda akibat keterlambatan, bila ada.

ii) Pekerjaan yang tidak lengkap atau tidak benar.

iii) Variasi yang telah disetujui tetapi masih harus dituangkan dalam Addendum.

iv) Setiap penyesuaian lainnya yang diperlukan pada ketentuan dan persyaratan
dalam Dokumen Kontrak.

e) Perhitungan Jumlah Harga Kontrak akhir.

f) Ringkasan lembaran neraca yang menunjukkan selesainya Pengembalian Semua Uang


Muka dan pencairan semua Uang Yang Ditahan (Retention Money).

g) Jadwal tentang seluruh pembayaran yang telah disahkan oleh Direksi Pekerjaan.

h) Jumlah yang menjadi hak atau yang harus dipotong dari Kontraktor.

1.14.4 ADDENDUM PENUTUP

Berdasarkan detil-detil Sertifikat Pembayaran Akhir yang disahkan oleh Direksi Pekerjaan dan
Sertifikat Penyesuaian Harga Akhir, Direksi Pekerjaan harus juga menyiapkan Addendum
Penutup yang harus ditandatangani Pemilik dan Kontraktor, dilengkapi dengan perhitungan
akhir dari Jumlah Harga Kontrak. Setelah memperoleh tanda tangan Kontraktor, selanjutnya
Direksi Pekerjaan harus menyerahkan Addendum Penutup tersebut ke Pemilik untuk
ditandatangani bersama-sama dengan Sertifikat Pembayaran Akhir yang telah disetujui.

1 -58
EINRIP General Specification
Divisi 1 - Umum

SEKSI 1.15

DOKUMEN REKAMAN PROYEK

1.15.1 UMUM

1.15.1.1 Uraian

Selama pelaksanaan Pekerjaan Kontraktor harus menjaga rekaman yang akurat dari semua
perubahan yang terjadi dalam Dokumen Kontrak dalam satu set Dokumen Rekaman Proyek,
dan harus memindahkan informasi akhir tersebut ke dalam Dokumen Rekaman Akhir sebelum
penyelesaian Pekerjaan.

1.15.1.2 Pekerjaan Seksi Lain Yang Berkaitan Dengan Seksi Ini

a) Pembayaran Sertifikat Bulanan : Seksi 1.6


b) Penutupan Kontrak : Seksi 1.14

1.15.1.3 Pengajuan

a) Kontraktor harus menyerahkan kepada Direksi Pekerjaan satu set Dokumen


Rekaman Proyek yang dalam keadaan terpelihara pada setiap bulan tanggal 25 untuk
mendapat persetujuan dari Direksi Pekerjaan. Dokumen Rekaman Proyek yang telah
disetujui Direksi Pekerjaan ini, menjadi prasyarat untuk pengesahan Sertifikat
Bulanan.

b) Kontraktor harus menyerahkan kepada Direksi Rekaman Proyek akhir pada saat
permohonan Serifikat Serah Terima Pekerjaan untuk mendapat persetujuan dari
Direksi Pekerjaan, disertai dengan surat pengantar yang berisi :

i) Tanggal.

ii) Nomor dan Nama Proyek.

iii) Nama dan Alamat Kontraktor.

iv) Judul dan Nomor tiap Dokumen Rekaman.

v) Sertifikat yang menyatakan bahwa setiap dokumen yang diserahkan telah


lengkap dan benar.

vi) Tanda tangan Kontraktor, atau wakilnya yang sah.

1.15.2 DOKUMENT REKAMAN PROYEK

1.15.2.1 Dokumen Kerja (Job Set)

Segera setelah Pengumuman Pemenang, Kontraktor dapat memperoleh 1 (satu) set lengkap
semua Dokumen yang berhubungan dengan Kontrak tanpa biaya dari Direksi Pekerjaan.
Dokumen Kerja akan mencakup :

1 -59
EINRIP General Specification
Divisi 1 - Umum

a) Syarat-syarat Kontrak.

b) Spesifikasi.

c) Gambar.

d) Addenda (bila ada).

e) Modifikasi lainnya terhadap Kontrak.

f) Catatan hasil pengujian lapangan.

g) Rencana relokasi dan laporannya.

h) Rencana Manajemen Lingkungan dan laporannya.

i) Rencana Kesehatan dan Keselamatan dan laporannya.

j) Rencana Manajemen Lalu Lintas dan Keselamatan serta laporannya.

1.15.2.2 Penyimpanan Dokumen Kerja

Dokumen Kerja harus disimpan dan diarsipkan dalam rak-rak di kantor lapangan, dan
Kontraktor harus menjaga dokumen kerja tersebut terlindung dari kehilangan atau kerusakan
sampai pemindahan data akhir ke dalam Dokumentasi Proyek Akhir telah selesai
dilaksanakan. Dokumen rekaman tersebut tidak boleh digunakan untuk maksud-maksud
pelaksanaan pekerjaan dan dokumen tersebut harus selalu tersedia setiap saat untuk diperiksa
oleh Direksi Pekerjaan atau Pemilik.

1.15.3 BAHAN REKAMAN PROYEK

Segera setelah semua bahan, aspal, agregat, bahan bahu jalan, semen, beton, campuran aspal
panas, dan sebagainya disetujui, maka semua contoh yang telah disetujui harus disimpan
dengan baik di lapangan.

1.15.4 PEMELIHARAAN DOKUMEN PELAKSANAAN PROYEK

1.15.4.1 Penanggungjawab

Kontraktor harus melimpahkan tanggung jawab pemeliharaan Dokumen Rekaman kepada


salah seseorang staf yang ditunjuk sebagaimana yang telah disetujui oleh Direksi Pekerjaan
sebelumnya.

1.15.4.2 Pemberian Tanda

Segera setelah diterimanya Dokumen Kerja (Job Set), Kontraktor harus memberi tanda pada
setiap dokumen dengan judul “Dokumen Rekaman Proyek – Dokumen Kerja”, dalam huruf
cetak setinggi 5 cm.

1.15.4.3 Pemeliharaan

Pada saat penyelesaian Kontrak, kemungkinan sejumlah Dokumen Kerja harus dike-
luarkan untuk mencatat masukan-masukan baru dan untuk pemeriksaan, dan dalam
kondisi-kondisi yang demikian kegiatan seperti ini akan dilaksanakan, maka Kontraktor

1 -60
EINRIP General Specification
Divisi 1 - Umum

harus mencari cara yang cocok untuk melindungi dokumen kerja tersebut untuk disetujui
Direksi Pekerjaan.

1.15.4.4 Tata Cara Membuat Catatan dalam Gambar

Catatan pada Gambar harus dilakukan dengan menggunakan pensil berwarna yang dapat
dihapus (tidak boleh memakai tinta), perubahan harus diuraikan dengan jelas dengan
pencatatan dan kalau perlu dengan garis grafis. Catat tanggal semua masukan. Berilah tanda
perhatian pada setiap catatan dengan tanda “awan” pada tempat atau tempat-tempat yang
mengalami perubahan. Bilamana terjadi perubahan yang tumpang tindih (over-laping), maka
disarankan menggunakan warna yang berbeda untuk setiap perubahan. Dokumen rekaman
harus selalu diperbaharui jangan sampai terdapat bagian yang tertanam dalam setiap pekerjaan
yang dikerjakan tidak tercatat.

Beri tanda yang jelas untuk mencatat setiap detil pelaksanaan, misalnya :

a) Kedalaman berbagai elemen pondasi sehubungan dengan data yang ditunjukkan.

b) Posisi horisontal maupun vertikal untuk utilitas bawah permukaan harus ditandai pada
bagian permukaan pekerjaan yang permanen.

c) Lokasi utilitas yang tertanam dalam pekerjaan harus diberi tanda sehingga mudah
terlihat dengan tanda-tanda khusus pada struktur.

d) Perubahan dimensi dan detil pelaksanaan di lapangan.

e) Perubahan yang terjadi dengan adanya Variasi.

f) Gambar detil yang tidak terdapat dalam Gambar asli.

1.15.4.5 Waktu Pencatatan

Semua catatan harus dibuat dalam jangka waktu 24 jam terhitung sejak diterimanya informasi.

1.15.4.6 Keakuratan

Gunakan semua sarana yang diperlukan, termasuk perlengkapan khusus yang dipakai untuk
pengukuran, untuk menentukan lokasi bagian-bagian yang terpasang dan untuk memperoleh
data masukan yang akurat.

Kontraktor harus melakukan koordinasi atas semua perubahan yang terjadi dalam Dokumen
Rekaman, membuat catatan yang sesuai dan sebagaimana mestinya pada setiap halaman
Spesifikasi dan pada lembaran Gambar dan pada Dokumen lainnya, dimana pencatatan yang
demikian diperlukan untuk menunjukkan perubahan yang sebenarnya terjadi. Keakuratan
rekaman harus sedemikian rupa sehingga setiap pencarian bagian-bagian pekerjaan yang
ditunjukkan dalam Dokumen Kontrak di kemudian hari dapat dengan mudah diperoleh dari
Dokumen Rekaman yang telah disetujui.

1.15.5 DOKUMEN REKAMAN AKHIR

1.15.5.1 Umum

Tujuan pembuatan Dokumen Rekaman Akhir adalah menyiapkan informasi nyata


menyangkut semua aspek Pekerjaan, baik yang tertanam maupun yang terlihat, untuk

1 -61
EINRIP General Specification
Divisi 1 - Umum

memungkinkan modifikasi rancangan di kemudian hari dapat dilaksanakan tanpa pengukuran


ulang yang lama dan mahal, tanpa investigasi dan pemeriksaan ulang.

1.15.5.2 Pemindahan Data ke dalam Gambar

Seluruh perubahan data yang ditunjukkan dalam Dokumen Kerja dari Gambar Rekaman
harus dipindahkan dengan teliti ke dalam Gambar Rekaman Akhir menurut masing-masing
gambar aslinya, dan penjelasan yang lengkap dari semua perubahan selama pelaksanaan dan
lokasi aktual dari semua jenis pekerjaan harus ditunjukkan dengan jelas. Berilah tanda
perhatian pada setiap catatan dengan tanda “awan” yang mengelilingi tempat atau tempat-
tempat yang mengalami perubahan. Buatlah semua catatan perubahan pada dokumen yang asli
dengan rapi, konsisten, dan ditulis dengan tinta atau pinsil keras hitam.

1.15.5.3 Pemindahan Data ke Dokumen Lain

Bilamana dokumen selain Gambar telah dijaga bersih selama pelaksanaan Pekerjaan, dan bila
setiap data masukan telah dicatat dengan rapi agar dapat disetujui oleh Direksi Pekerjaan,
maka dokumen kerja (job set) dari Dokumen tersebut (selain Gambar) akan diterima Direksi
Pekerjaan sebagai Dokumen Rekaman Akhir untuk Dokumen tersebut. Bilamana Dokumen
yang demikian belum dapat disetujui oleh Direksi Pekerjaan, maka Kontraktor harus
menyiapkan salinan baru dari Dokumen yang diperoleh dari Direksi Pekerjaan. Pemindahan
perubahan data ke dalam salinan baru ini harus dilakukan dengan hati-hati agar dapat disetujui
oleh Direksi Pekerjaan.

1.15.5.4 Peninjauan dan Persetujuan

Kontraktor harus menyerahkan kepada Direksi Pekerjaan satu set lengkap Dokumen Rekaman
Akhir pada saat mengajukan permohonan Sertifikat Serah Terima Pekerjaan. Bilamana
diminta oleh Direski Pekerjaaan, maka Kontraktor harus mengikuti rapat atau rapat-rapat
peninjauan (review), melaksanakan setiap perubahan yang diperlukan dan segera
menyerahkan kembali Dokumen Rekaman Akhir kepada Direksi Pekerjaan untuk dapat
diterima.

1.15.5.5 Perubahan Setelah Dokumen Diterima

Kontraktor tidak bertanggungjawab untuk mencatat perubahan Pekerjaan setelah Serah


Terima Pekerjaan, kecuali perubahan yang diakibatkan oleh penggantian, perbaikan, dan
perubahan yang dilakukan Kontraktor sebagai bagian dari kewajibannya.

1 -62
EINRIP General Specification
Divisi 1 - Umum

SEKSI 1.16

PEKERJAAN PEMBERSIHAN

1.16.1 UMUM

1.16.1.1 Uraian

Selama Waktu untuk Penyelesaian pekerjaan, Kontraktor harus memelihara Pekerjaan bebas
dari akumulasi sisa bahan bangunan, kotoran dan sampah, yang diakibatkan oleh operasi
pelaksanaan. Pada saat selesainya Pekerjaan, semua sisa bahan bangunan dan bahan-bahan tak
terpakai, sampah, perlengkapan, peralatan dan mesin-mesin harus disingkirkan, seluruh
permukaan terekspos yang nampak harus dibersihkan dan proyek ditinggal dalam kondisi siap
pakai dan diterima oleh Direksi Pekerjaan.

1.16.1.2 Pekerjaan Seksi Lain Yang Berkaitan Dengan Seksi Ini

a) Syarat-syarat Kontrak : Pasal-pasal yang


berkaitan
b) Penutupan Kontrak : Seksi 1.14
c) Usaha Perlindungan Lingkungan Hidup : Seksi 1.17
d) Pemeliharaan Rutin Perkerasan, Bahu Jalan, Drainase, : Seksi 10.1
Perlengkapan Jalan dan Jembatan

1.16.2 PEMBERSIHAN SELAMA PELAKSANAAN

1.16.2.1 Kontraktor harus melakukan pembersihan secara teratur untuk menjamin bahwa tempat kerja,
struktur, kantor sementara, tempat hunian dipelihara bebas dari akumulasi sisa bahan
bangunan, sampah dan kotoran lainnya yang diakibatkan oleh operasi-operasi di tempat kerja
dan memelihara tempat kerja dalam kondisi rapi dan bersih setiap saat.

1.16.2.2 Kontraktor harus menjamin bahwa sistem drainase terpelihara dan bebas dari kotoran dan
bahan yang lepas dan berada dalam kondisi operasional pada setiap saat

1.16.2.3 Kontraktor harus menjamin bahwa rumput yang tumbuh pada berm lama atau yang baru
dikerjakan dan pada talud samping dipangkas dan dipelihara sedemikian rupa sehingga
ketinggiannya maksimum 3 cm.

1.16.2.4 Bilamana dianggap perlu, Kontraktor harus menyemprot bahan dan sampah yang kering
dengan air untuk mencegah debu atau pasir yang beterbangan.

1.16.2.5 Kontraktor harus menjamin bahwa rambu jalan dan sejenisnya dibersihkan secara teratur agar
bebas dari kotoran dan bahan lainnya.

1.16.2.6 Kontraktor haruis menyediakan drum di lapangan untuk menampung sisa bahan bangunan,
kotoran dan sampah sebelum dibuang.

1.16.2.7 Kontraktor harus membuang sisa bahan bangunan, kotoran dan sampah di tempat yang telah
ditentukan sesuai dengan Peraturan Pusat maupun Daerah dan Undang-undang Pencemaran
Lingkungan yang berlaku.

1.16.2.8 Kontraktor tidak diperkenankan mengubur sampah atau sisa bahan bangunan di lokasi proyek
tanpa persetujuan dari Direksi Pekerjaan.

1 -63
EINRIP General Specification
Divisi 1 - Umum

1.16.2.9 Kontraktor tidak diperkenankan membuang limbah berbahaya, seperti cairan kimia, minyak
atau thinner cat ke dalam saluran atau sanitasi yang ada.

1.16.2.10 Kontraktor tidak diperkenankan membuang sisa bahan bangunan ke dalam sungai atau saluran
air.

1.16.2.11 Bilamana Kontraktor menemukan bahwa saluran drainase samping atau bagian lain dari
sistem drainase yang dipakai untuk pembuangan setiap jenis bahan selain dari pengaliran air
permukaan, baik oleh pekerja Kontraktor maupun pihak lain, maka Kontraktor harus segera
melaporkan kejadian tersebut kepada Direksi Pekerjaan, dan segera mengambil tindakan
sebagaimana diperintahkan oleh Direksi Pekerjaan untuk mencegah terjadinya pencemaran
lebih lanjut.

1.16.3 PEMBERSIHAN AKHIR

1.16.3.1 Pada saat penyelesaian Pekerjaan, tempat kerja harus ditinggal dalam keadaan bersih dan siap
untuk dipakai Pemilik. Kontraktor juga harus mengembalikan bagian-bagian dari tempat kerja
yang tidak diperuntukkan dalam Dokumen Kontrak ke kondisi semula.

1.16.3.2 Pada saat pembersihan akhir, semua perkerasan, kerb, dan struktur harus diperiksa ulang untuk
mengetahui kerusakan fisik yang mungkin ditemukan sebelum pembersihan akhir. Lokasi
yang diperkeras di tempat kerja dan semua lokasi diperkeras untuk umum yang bersebelahan
langsung dengan tempat kerja harus disikat sampai bersih. Permukaan lainnya harus digaru
sampai bersih dan semua kotoran yang terkumpul harus dibuang.

1.16.4 DASAR PEMBAYARAN

Tidak ada pembayaran terpisah yang akan dibuat untuk operasi pembersihan yang dilakukan
oleh Kontraktor sesuai dengan menurut Seksi dari Spesifikasi ini.

1 -64
EINRIP General Specification
Divisi 1 - Umum

SEKSI 1.17

USAHA PERLINDUNGAN LINGKUNGAN HIDUP

1.17.1 UMUM

1.17.1.1 Uraian

a) Seksi ini mencakup ketentuan-ketentuan penanganan dampak lingkungan dan


tindakan yang diperlukan untuk melaksanakan setiap pekerjaan sipil yang diperlukan
dalam Kontrak. Dalam banyak hal, pasal-pasal dari Seksi lain dari Spesifikasi ini
telah diambil sarinya dan tertuang di sini untuk meyakinkan kesadaran dan
pemenuhan akan ketentuan-ketentuan tersebut.

b) Kontraktor harus mengambil semua langkah yang layak untuk melindungi


lingkungan (baik di dalam dan di luar Lapangan, termasuk base camp dan instalasi
lain yang dibawah kendali Kontraktor) dan membatasi kerusakan dan gangguan
terhadap manusia dan harta milik sebagai akibat dari polusi, kebisingan dan sebab-
sebab lain dari pengoperasiannya. Kontraktor juga harus memastikan bahwa
pengangkutan dan kegiatan di sumber bahan dilaksanakan dengan cara yang
berwawasan lingkungan.

c) Sebagai suatu cara untuk memeperkecil gangguan lingkungan terhadap penduduk


yang berdekatan maka semua kegiatan konstruksi dan pengangkutan harus dibatasi
dalam jam-jam pengoperasian sebagaimana yang disebutkan dalam Bagian 3 Syarat-
syarat Kontrak, Bagian A Data Kontrak, kecuali jika disetujui lain oleh Direksi
Pekerjaan.

d) Sebelum memulai kegiatan fisik di lokasi manapun, Kontraktor harus diberitahu


kebutuhan-kebutuhan untuk menyiapkan laporan bulanan Pengelolaan dan
Pemantauan Lingkungan dengan mengidentifikasi setiap ayat : i) kegiatan-kegiatan
yang merugikan atau mengabaikan lingkungan, ii) menyediakan detil-detil dari
kegiatan dan pengabaian tersebut, iii) kegiatan-kegiatan yang dilaksanakan untuk
mengembalikan kondisi atau memperbaiki atas pengabaian tersebut, iv) detil-detil
laporan kepada Direksi Pekerjaan (rujuk pada Pasal 1.17.4 dari Spesifikasi ini).

1.17.1.2 Pekerjaan Seksi Lain Yang Berkaitan Dengan Seksi Ini

a) Syarat-syarat Kontrak : Pasal-pasal yang


berkaitan
b) Mobilisasi : Seksi 1.2
c) Kantor Lapangan dan Fasilitasnya : Seksi 1.3
d) Transportasi dan Penanganan : Seksi 1.5
e) Manajemen Lalu Lintas dan Keselamatan : Seksi 1.8
f) Bahan dan Peyimpanan : Seksi 1.11
g) Pekerjaan Pembersihan : Seksi 1.16
h) Relokasi Utilitas dan Pelayanan Yang Ada : Seksi 1.19
i) Selokan dan Saluran Air : Seksi 2.1
j) Gorong-gorong dan Drainase Beton : Seksi 2.3
k) Galian : Seksi 3.1
l) Timbunan : Seksi 3.2
m) Pelebaran Perkerasan : Seksi 4.1
n) Lapis Pondasi Agregat : Seksi 5.1
o) Lapis Pondasi Jalan Tanpa Penutup Aspal : Seksi 5.2
p) Lapis Resap Pengikat dan Lapis Perekat : Seksi 6.1

1 -65
EINRIP General Specification
Divisi 1 - Umum

q) Campuran Aspal Panas : Seksi 6.3


r) Pengembalian Kondisi Perkerasan Bahu Jalan Lama pada Perke- : Seksi 8.2
rasan Berpenutup Aspal
s) Lansekap : Seksi 8.3
t) Perlengkapan Jalan dan Pengatur Lalu Lintas : Seksi 8.4
u) Pengembalian Kondisi Struktur Jembatan Lama : Seksi 8.5
v) Pemeliharaan Rutin Perkersan, Bahu Jalan, Drainase, Perleng- : Seksi 10.1
kapan Jalan dan Jembatan
w) Pasal-pasal yang berkaitan dengan Usaha Perlindungan Lingkungan Hidup untuk setiap
Seksi dalam Spesifikasi ini.

1.17.2 UPAYA PENGELOLAAN LINGKUNGAN (UKL)

1.17.2.1 Dampak terhadap Sumber Air

a) Kontraktor harus memastikan bahwa semua pengaruh dari semua kegiatan


KOntraktor tidak akan melampaui ambanag batas yang diuraikan dalam Hukum
yang berlaku (rujuk terutama pada Peraturan Pemerintah No.82 Tahun 2001
tentang Manajemen Mutu Air dan Pengendalian Pencemaran Air).

b) Sungai atau saluran alami di dalam atau bersebelahan dengan pekerjaan dalam
Kontrak ini tidak boleh diganggu tanpa persetujuan Direksi Pekerjaan.

c) Jika setiap penggalian atau pengerukan pada dasar sungai tidak dapat dihindarkan
untuk pelaksanaan pekerjaan yang sebagaimana mestinya, Kontraktor harus, setelah
pekerjaan tersebut selesai, menimbun kembali penggalian tersebut sampai kembali
ke kondisi awal permukaan atau dasar sungai dengan bahan yang disetujui oleh
Direksi Pekerjaan.

d) Bahan yang ditumpuk pada daerah sungai dari pondasi atau penggalian lainnya, atau
dari penempatan cofferdam, harus disingkirkan seluruhnya setelah pelaksanaan.

e) Saluran air harus direlokasi untuk memastikan aliran dapat melewati daerah
pekerjaan tanpa halangan pada semua tingkat banjir, di mana stabilisasi timbunan
atau pekerjaan permanent lainnya secara tak terhindarkan akan menghalangi, atau
menghalangi sebagian, dari setiap saluran yang ada.

f) Semua galian harus dijaga bebas dari air dan Kontraktor harus menyediakan semua
bahan, peralatan dan pekerja yang perlu, untuk mengalihkan saluran dan pembuatan
saluran sementara, tumit (cut off walls) dan cofferdam.

g) Penggalian untuk bahan timbunan harus dilarang atau dibatasi bilamana penggalian
tersebut akan mengganggu semua saluran drainase.

h) Setiap cairan berbahaya atau bahan pencemar padat, seperti minyak hidrolik atau
minyak pelumas, yang jatuh atau tumpah diatas tempat kerja dan lingkungan yang
bersebelahan, base camp, atau route pengangkutan harus dibersihkan segera oleh
Kontraktor agar dapat menghindari pencemaran air dan tanah. Direksi Pekerjaan
harus menyetujui selesainya pembersihan.

i) Cara yang memadai untuk menjebak lanau di instalasi pencampur harus disediakan
melalui sistem pembuangan sementara ke dalam system drainase yang permanen.

1 -66
EINRIP General Specification
Divisi 1 - Umum

j) Pencucian kendaraan dan peralatan Kontraktor hanya diperkenankan pada daerah


yang khusus dirancang dan dilengkapi dan tidak akan diperkenankan untuk setiap
saluran air.

1.17.2.2 Dampak terhadap Mutu Udara

a) Kontraktor harus memastikan bahwa emisi dari semua kegiatan Kontraktor termasuk
kegiatan transportasi dijaga sampai tingkat yang sangat minim dengan peralatan
modern dan dengan manajemen dan pemeliharaan yang baik, dan setiap emisi tidak
akan melampaui ambang batas yang disebutkan dalam Hukum yang berlaku (rujuk
terutama pada Peraturan Pemerintah No. 41 tahun 1999 tentang Pengendalian
Pencemaran Udara).

b) Instalasi pencampuran aspal, mesin pemecah batu dan setiap peralatan konstruksi
yang tidak bergerak harus dipasang sejauh mungkin dari pemukiman dan daerah
sensitif lainnya untuk memastikan bahwa gangguan dan protes dari setiap anggota
dari masyarakat setempat seminim mungkin. Lokasi tersebut harus disetujui oleh
Direksi Pekerjaan.

c) Instalasi pencampur aspal (AMP) harus dilengkapi dengan alat pengumpul debu
(dust collector) yang lengkap yaitu sistem pusaran kering (dry cyclone) dan pusaran
basah (wet cyclone) atau tabung filter sehingga tidak menimbulkan pencemaran
debu. Bilamana salah satu sistem di atas rusak atau tidak berfungsi maka instalasi
pencampur aspal tidak boleh dioperasikan.

d) Truk harus ditutup dan semua penutup harus diikat dengan kencang.

e) Kontraktor harus mempertahankan di tempat kerja pemasokan air yang memadai


untuk pengendalian kadar air selama semua operasi penghamparan dan pemadatan,
dan harus membuang bahan yang berlebihan dari semua jalan yang ada.

1.17.2.3 Dampak Kebisingan

Kontraktor harus melakukan semua peringatan untuk memperkecil jumlah kebisingan dan
vibrasi yang dating dari kegiatan konstruksi dan pengangkutan, oleh semua kendaraan dan
peralatan, dengan menggunakan kendaraan dan peralatan yang modern serta dengan
manajemen dan pemeliharaan yang baik. Kontraktor harus memastikan bahwa semua
tingkat kebisingan dan vibrasi dari semua Kegiatan Kontraktor adalah sesuai dengan
Hukum yang berlaku (rujuk terutama pada Keputusan Menteri Lingkungan Hidup No.48
Tahun 1996 tentang Tingkat Baku Kebisingan dan Keputusan Menteri Lingkungan Hidup
No 49 Tahun 1996 tentang Tingkat Vibrasi.)

1.17.2.4 Dampak terhadap Lalu Lintas, Harta Milik yang Bersebelahan, dan Utilitas

a) Ketentuan-ketentuan yang diberikan dalam Seksi 1.8, tentang Manajemen Lalu


Lintas dan Keselamatan, harus berlaku.

b) Galian parit atau galian lainnya yang memotong jalan harus dilaksanakan dengan
menggunakan pelaksanaan setngah lebar jalan sedemikian hingga jalan tersebut
dapat dipertahankan terbuka untuk lalu lintas setiap saat.

c) Kontraktor harus bertanggung-jawab untuk semua akibat dari lalu lintas dan harus
melarang lalu lintas semacam ini jika perlu dengan menyediakan jalan alih atau
pelaksanaan setemgah lebar jalan.

1 -67
EINRIP General Specification
Divisi 1 - Umum

d) Semua pekerjaan harus dilaksanakan dengan ketidak-nyamanan bagi pengguna jalan


yang sekecil mungkin dan paling sedikit lalu lintas satu lajur harus dipertahankan
terbuka setiap saat.

e) Pada setiap saat selama pelaksanaan Pekerjaan, Kontraktor harus memastikan bahwa
perkerasan, bahu jalan dan daerah yang bersebelahan di dalam Daerah Milik Jalan
harus dijaga bebas dari bahan konstruksi, sampah atau benda-benda lepas lainnya
yang dapat menghalangi atau membahayakan kebebasan dan keselamatan lalu lintas
yang lewat. Pekerjaan juga harus dijaga bebas dari setiap parker yang tidak sah atau
kegiatan perdagangan di jalanan kecuali di daerah yang dirancang untuk tujuan
tersebut.

f) Kontraktor harus bertanggung-jawab untuk memperoleh setiap informasi yang ada


tentang keberadaan dan lokasi utilitas yang ada di bawah tanah dan untuk
memperoleh dan membayar setiap perijinan yang perlu atau keperluan lainnya untuk
pengalihan atau penghentian sementara.

g) Kontraktor harus bertanggung-jawab untuk hati-hati dan perlindungan atas setiap


pipa, kabel, selongsong bawah tanah yang ada atau jaringan bawah tanah lainnya
atau struktur yang mungkin diketemukan dan untuk memperbaiki setiap kerusakan
terhadap utilitas bawah tanah yang disebabkan oleh pengoperasiannya.

h) Semua lubang pada perkerasan beraspal dan lubang-lubang yang dibuat pada
Pekerjaan yang sudah selesai akibat pengujian kepadatan atau sebaliknya harus
diperbaiki sesegera mungkin setelah lapisan yang rusak tersebut digali, agar dapat
menghindarkan halangan atau bahaya terhadap lalu lintas.

i) Pada saat kapanpun selama waktu untuk penyelesaian kontraktor harus menyisakan
jalan masuk bagi kendaraan dan pejalan kaki menuju semua rumah, daerah bisnis,
indistri dan lainnya. Jalan masuk sementara harus disediakan bilamana pelaksanaan
telah mendekati jalan masuk permanen untuk setiap periode yang diatas 16 jam dan
semua penghuni dan anggota masyarakat yang terkena dampak ini harus diberitahu
paling tidak 24 jam sebelumnya atas setiap dampak yang akan terjadi pada jalan
masuk.

1.17.2.5 Kesehatan dan Keselamatan Manusia

a) Ketentuan-ketentuan yang diberikan dalam Syarat-syarat Khusus Ayat 6.7 Kesehatan


dan Keselamatan harus berlaku.

b) Kontraktor harus: i) memenuhi semua peraturan keselamatan yang berlaku (rujuk


terutama pada Undang-undang No.1 tahun 1970 tentang Keselamatan Kerja dan
Undang-undang No.12 tahun 1999 tentang Pengamanan Kebakaran di Tempat
Kerja); ii) memperhaikan keselamatan semua personil yang berada di Lapangan; dan
iii) menyediakan setiap Pekerjaan Sementara (termasuk jalan raya, jalan setapak,
pengaman dan pagar) yang mungkin perlu, karena pelaksanaan Pekerjaan, untuk
manfaat dan perlindungan bagi publik dan penghuni dari lahan yang bersebelahan.

c) Kontraktor harus senantiasa melakukan semua peringatan yang layak untuk menjaga
kesehatan dan keselamatan Personil Kontraktor dan harus menunjuk seorang petugas
pencegahan kecelakaan di Lapangan, bertanggungjawab untuk menjaga keselamatan
dan perlindungan terhadap kecelakaan.

d) Kontraktor harus senantiasa melakukan peringatan yang perlu untuk menlindungi


Personil Kontraktor ang dipekerjakan di Lapangan dari gangguan serangga dan
hama, dan mengurangi resiko terhadap kesehatan.

1 -68
EINRIP General Specification
Divisi 1 - Umum

e) Ketentuan-ketentuan yang diberikan dalam Pasal 3.1.1.5, tentang Keselamatan pada


Pekerjaan Galian, harus berlaku.

f) Semua gigi-gigi, pulley (roda penyesuai putaran), rantai, gigi jentera dan bagian
bergerak yang berbahaya lainnya dari Instalasi Pencampur harus diamankan dan
dilindungi seluruhnya.

g) Fasilitas pengendalian limbah sanitair yang sesuai harus disediakan untuk semua staf
proyek dan pekerja dan limbah tersebut harus dikumpulkan dan dibuang secara
berkala sesuai dengan hukum yang berlaku (rujuk terutama Peraturan Pemerintah
No.82 tahun 2001 tentang Manajemen Mutu dan Pengendalian Pencemaran Air,
dan Undang-undang No.1 ahun 1970 tentang Keselamatan Kerja).

1.17.2.6 Dampak terhadap Flora dan Fauna

a) Pemotongan pohon harus dilakukan hanya bilamana mutlak diperlukan baik untuk
pelebaran maupun untuk bahu jalan dan akan ditetapkan secara khusus serta
disepakati oleh semua pihak selama investigasi lapangan. Setiap pohon yang
ditebang harus diganti dengan dua pohon yang sudah hampir jadi (bukan pohon
kecil) dengan jenis yang sama atau sejenis. Tidak ada pohon yang boleh ditanam
dalam zone bebas.

b) Kontraktor harus memebatasi pergerakan para pekerja dan peralatannya di dalam


daearah yang peka terhadap, seperti Taman Nasional, sedemikin untuk
memeperkecil kerusakan terhadap tanaman alami dan harus berusaha untuk
menghindari setiap kerusakan terhadap lahan. Kerjasama lebih lanjut yang
bermanfaat dengan instansi setempat harus dilakukan.

1.17.2.7 Dampak Terhadap Tanah

a) Kontraktor harus memastikan bahwa permukaan tanah yang terganggu oleh


kegiatan-kegiatan Kontraktor tidak melampaui batas ambang yang disebutkan dalam
Hukum yang berlaku (rujuk terutama pada Peraturan Pemerintah No. 82 tahun
2001 tentang Manajemen Mutu dan Pengendalian Pencemaran Air)

b) Agar dapat menghindari kelongsoran dan erosi tanah selama penggalian untuk bahan
timbunan, tepi dari galian untuk bahan timbunan tersebut tidak boleh lebih dekat 2
meter dari tumit timbunan atau 10 meter dari puncak setiap galian.

1.17.2.8 Pembuangan Limbah

Pembuangan semua limbah padat dan cair dari kegiatan konstruksi hanya berlaku di tempat
pembuangan yang disetujui atau dengan persetujuan Direksi Pekerjaan yang telah
membicarakannya dengan instansi yang berwenang sebelumnya untuk memastikan bahwa
pembuangan tersebut telah sesuai dengan ketentuan-ketentuan mereka.

1.17.2.9 Dampak terhadap Warisan Budaya

Ketentuan-ketentuan yang diberikan dalam Syarat-syarat Umum Ayat 4.24, tentang fossil,
harus berlaku.

1.17.2.10 Hal-hal Lain

a) Kontraktor harus memperoleh semua bahan yang ditambang (pasir, kerikil, dsb) dari
Sumber Bahan yang (1) : dimiliki atau disewa, dioperasikan dan dikelola sesuai dengan

1 -69
EINRIP General Specification
Divisi 1 - Umum

hukum daerah dan nasional, dan (2) beroperasi dengan keselamatan dan secara
lingkungan yang dapat diterima dan sesuai dengan seksi ini.

b) Kontraktor harus memastikan bahwa Base Camp yang dioperasikan sesuai dengan
praktek secara lingkungan yang baik dan dampak lingkungan yang kurang baik tersebut
dipertahankan pada tingkat yang senimim mungkin dan sesuai dengan seksi ini, dan
masyarakat setempat tersebut tidak terganggu oleh setiap kegiatan dari Base Camp.

c) Sesuai dengan praktek pengembangan yang berkelanjutan, semua bahan kayu untuk
turap, tiang pancang pemikul beban, cerucuk, harus dibeli dealer yang sah (tidak berasal
dari penebangan liar) dan sertifikat keabsahan yang dilampirkan pada dokumen
pembelian harus diserahkan kepada Direksi Pekerjaan.

d) Semua bagian dari Lapangan harus dikembalikan ke kondisi semula seperti pada saat
sebelum pekerjaan dimulai.

1.17.3 IMPLEMENTASI STUDI LINGKUNGAN HIDUP YANG DIPERLUKAN

Untuk setiap sub-proyek yang mempunyai UKL/UPL atau AMDAL, agar memenuhi
hukum lingkungan hidup dari Pemerintah Indonesia, Kontraktor harus memenuhi setiap
rekomendasi-rekomendasi dalam dokumen selama waktu untuk penyelesaian. Semua
rekomendasi selama waktu untuk penyelesaian akan termasuk dalam Bagian 2 dari
Dokumen Kontrak dan rekomendasi-rekomendasi yang TIDAK termasuk dalam Usaha
Perlindungan Lingkungan yang diperlukan untuk diterapkan, akan diberikan dalam bentuk
saran dari Direksi Pekerjaan. Dokumen UKL/UPL atau Amdal yang lengkap juga akan
disediakan untuk Kontraktor dan Direksi Pekerjaan hanya sebagai informasi saja.

1.17.4 LAPORAN BULANAN

1.17.4.1 Pengajuan

Sebuah laporan bulanan Pemantauan dan Pengelolaaan Dampak Lingkungan perlu


diajukan setiap bulan kalender dari Waktu untuk Penyelesaian, sebagai bagian dari Laporan
Kemajuan Pekerjaaan.

Kontraktor harus bertanggungjawab penuh untuk penyiapan dan pengajuan setiap Laporan
Bulanan Pemantauan dan Pengelolaaan Dampak Lingkungan yang harus memenuhi berikut
ini :

a) Laporan Bulanan Pemantauan dan Pengelolaaan Dampak Lingkungan harus


disiapkan dalam bentuk yang disetujui Direksi Pekerjaan.

b) Laporan Bulanan Pemantauan dan Pengelolaaan Dampak Lingkungan harus


dilengkapi dengan dokumen pendukung yang memadai agar dapat memberikan
pengajuan yang lengkap dan benar-benar substansial, sedemikian hingga Direksi
Pekerjaan dapat mengesahkan permohonan pembayaran dalam waktu yang
ditetapkan dalam Pasal-pasal yang relevan dari Syarat-syarat Umum dan Spesifikasi
ini.

c) Usualan Sertifikat Bulanan Pemantauan dan Pengelolaaan Dampak Lingkungan


bersama dokumen pendukung ini harus diajukan kepada Direksi Pekerjaan sesuai
dengan waktu yang ditentukan di bawah ini.

Direksi Pekerjaan akan bertanggung-jawab atas pengesahan akurasi dari laporan.

1 -70
EINRIP General Specification
Divisi 1 - Umum

1.17.4.2 Waktu

Setiap Laporan Bulanan Pemantauan dan Pengelolaaan Dampak Lingkungan harus diberi
tanggal akhir dari bulan kalender yang dikumpulkan bersama dengan Usulan Sertifikat
Bulanan sebagaimana disebutkan dalam Pasal 1.6.2.1.

1.17.5 DASAR PEMBAYARAN

Tidak ada pembayaran terpisah yang akan dibuat untuk usaha perlindungan lingkungan
yang dilaksanakan sesuai dengan Seksi dari Spesifikasi ini kecuali untuk Pasal 1.17.2.6.(a)
dimana pembayaran akan dilakukan. Biaya pekerjaan ini harus sudah termasuk dalam
Harga Satuan dari semua Mata Pekerjaan yang terdapat dalam Kontrak, dimana harga
tersebut harus merupakan kompensasi penuh untuk penyediaan semua bahan, pekerja,
peralatan, perlengkapan dan biaya lainnya yang diperlukan untuk pengelolaan lingkungan.

Bilamana Kontraktor gagal dalam melaksanakan pekerjaan ini, Direksi Pekerjaan, tanpa
membebaskan kontraktor dari tanggungjawabnya, akan berhak melaksanakan pekerjaan
tersebut sebagaimana yang dipandang perlu dan membebankan semua biaya perbaikan
tersebut ditambah sepuluh persen dari biaya tersebut kepada Kontraktor, di mana nilai
biaya tersebut akan dipotongkan dari setiap uang yang dibayarkan atau akan dibayarkan
kepada Kontraktor menurut Kontrak. Direksi Pekerjaan akan bertanggung-jawab dalam
menetapkan pekerjaan-pekerjaan yang perlu diperbaiki dan menyiapkan suatu perkiraan
biaya.

1 -71
EINRIP General Specification
Divisi 1 - Umum
Eastern Indonesia National Roads Improvement Project (EINRIP)
STANDAR PENGELOLAAN DAN PEMANTAUAN LINGKUNGAN HIDUP
PADA TAHAP KONSTRUKSI
No. Paket : Tanggal :
Nama Paket : No. Laporan :
Provinsi :
Kepatuhan
Spesifikasi
Kegiatan Tingkatan Dampak Terhadap
Kontrak
Sumber Dampak Jenis Dampak Upaya Pengelolaan Lingkungan Spesifikasi Hambatan/Masalah
EINRIP
Signifi Moder Minor (VI.2)
Ada Tidak Ya Tidak
cant ate
Mobilisasi alat • Gangguan lalulintas terhadap √ • Kontraktor harus menyiapkan dan mengajukan kepada Direksi 1.8.2.1
berat dan pengguna jalan di dekat Pekerjaan, Rencana Manajemen Lalu Lintas dan Keselamatan (RMLK)
material daerah kerja dan sepanjang untuk pengoperasian-nya selama tahap pelaksanaan dan
jalur pengangkutan material. pemeliharaan. RMLK harus berdasarkan analisa aliran lalu lintas
• Kerusakan jalan dan jembatan √ tingkat makro/mikro dan tidak boleh terkonsentrasi di daerah
eksisting di jalur pengakutan konstruksi.
material. • Kontraktor harus menyediakan Peta terinci yang menunjukkan lokasi 1.5.2.1/
• Polusi udara selama √ semua sumber bahan untuk proyek dan route sepanjang jalan yang 1.8.2.4/5
pengangkutan material. dilewati bahan tersebut dari lokasi sumber bahan ke tempat pekerjaan
• Penyebaran debu karena √ dan memperoleh ijin dari pemerintah setempat serta melakukan
material dan permukaan tanah koordinasi dengan berbagai otoritas lalu lintas setempat.
terbuka. • Kontraktor harus memperoleh ijin sebagaimana diperlukan jika 1.5.2.1
• Kebisingan dan getaran di √ Kontraktor berencana membawa muatan yang melampaui batas yang
sekitar daerah kerja. disyaratkan melewati setiap jalan dan jembatan.
• Peningkatan resiko pengguna √ • Kontraktor harus mempekerjakan Koordinator Manajemen Lalu Lintas 1.8.2.7
jalan. dan Keselamatan (KMLK) yang memenuhi syarat dan memadai,
dengan pengalaman yang sesuai minimum 3 tahun dalam tugas-tugas
semacam ini dan staf yang diperlukan (jumlah minimum 2 orang) yang
dibawahinya untuk seluruh pengendalian dari manajemen lalu lintas
dan keselamatan, termasuk koordinasi dengan pejabat lalu lintas
tingkat propinsi dan setempat dengan juridiksi terhadap daerah proyek,
sedemikian hingga dapat memperkecil halangan, resiko keselamatan
dan memperlancar aliran lalu lintas yang melalui daerah konstruksi dan
melalui jalan-jalan pengalihan yang sesuai dan disetujui.
• Kontraktor harus menggunakan sebuah Kendaraan Penghantar ketika 1.8.2.9
memasuki atau meninggalkan daerah kerja sampai jalan tersebut
dibuka untuk lalu lintas. Manuver ini memperkecil resiko terhadap para
pekerja dan pengguna jalan.
• Pemasangan Rambu Panah Berkedip, Rambu Suar Berkedip Portabel, 1.8.3
Rambu-rambu Konstruksi dan Pengalihan, Penghalang lalu lintas,
Marka Jalan Sementara, Pagar yang Dapat Dilepas, pengatur lalu
lintas dan pelayanan untuk pengendalian dan pemeliharaan lalu lintas
yang melalui daerah konstruksi.
• Membangun dan memelihara jembatan dan jalan samping sementara 1.8.4.5
untuk jalan masuk umum dari dan ke jalan raya pada semua tempat
bilamana jalan masuk tersebut sudah ada sebelum Pekerjaan dimulai
dan pada tempat lainnya yang diperlukan/diperintahkan.
EINRIP General Specification
Divisi 1 - Umum
Kepatuhan
Spesifikasi
Kegiatan Tingkatan Dampak Terhadap
Kontrak
Sumber Dampak Jenis Dampak Upaya Pengelolaan Lingkungan Spesifikasi Hambatan/Masalah
EINRIP
Signifi Moder Minor (VI.2)
Ada Tidak Ya Tidak
cant ate
• Semua jalan alih sementara dan pemasangan pengendali lalu lintas 1.8.5.1
yang disiapkan oleh Kontraktor selama pelaksanaan Pekerjaan harus
dipelihara agar tetap aman dalam kondisi pelayanan yang memenuhi
ketentuan dan dapat diterima menjamin keselamatan.
• Perkerasan, bahu jalan lokasi yang berdekatan dengan Daerah Milik 1.8.5.2
Jalan harus dijaga agar bebas dari bahan pelaksanaan, kotoran dan
bahan yang tidak terpakai lainnya yang dapat mengganggu atau
membahayakan lalu lintas yang lewat.
• Kontraktor harus memastikan bahwa emisi dari semua kegiatan 1.17.2.2 (a)
Kontraktor tidak akan melampaui ambang batas yang disebutkan
dalam Hukum yang berlaku.
• Truk harus ditutup dan semua penutup harus diikat dengan kencang. 1.17.2.2 (d)
• Melaksanakan pekerjaan pemeliharaan rutin untuk menjamin agar 10.1.1
perkerasan, bahu jalan, drainase dan perlengkapan jalan lama selalu
dipelihara setiap saat dalam kondisi pelayanan yang dapat diterima.
• Upaya mitigasi lainnya (silahkan dideskripsikan disini):

Mobilisasi tenaga Dampak-damapk sosial yang • Memberikan informasi yang memadai dan konsultasi ke komunitas
kerja mungkin terjadi karena mobilisasi setempat dalam rangka memberikan gambaran dan pemahaman
tenaga kerja dari luar daerah: tentang proyek serta mendapatkan dukungan.
• Potensi dampak keresahan dan √ • Memprioritaskan warga terkena proyek untuk dipekerjakan di proyek
kesalahpahaman. apabila memenuhi kualifikasi pekerjaan.
• Potensi konflik sosial karena √ • Coordinasi dengan pemerintah daerah setempat untuk menjamin
kehadiran pekerja pendatang. terciptanya situasi dan kondisi yang aman.
• Kemungkinan timbulnya √ • Upaya mitigasi lainnya (silahkan dideskripsikan disini):
kecemburuan sosial.

Pembangunan dan • Dampak visual dan estetika. √ • Kantor dan fasilitasnya harus ditempatkan sesuai dengan Lokasi 1.3.1.2 (b)
pengoperasian • Penyimpanan/pembuangan √ Umum dan Denah Lapangan yang telah disetujui dan merupakan dan
basecamp dan limbah cair dan limbah padat bagian dari Program Mobilisasi, harus diusahakan sedekat mungkin 1.17.2.2. (c)
AMP dan pembuangan yang tidak dengan daerah kerja (site) dan telah mendapat persetujuan di lokasi
memadai.
√ yang jauh dari pemukiman.
• Peningkatan polusi udara/
debu. • Alat pencampur aspal (AMP) harus terpasang pada areal yang jauh 6.3.4.1
• Peningkatan kebisingan. √ dari area pemukiman dan disetujui oleh ahli teknis untuk memastikan
• Polusi aliran permukaan karena √ tidak menganggu masyarakat setempat.
pembuangan limbah yang tidak • Kontraktor harus melakukan pembersihan secara teratur untuk 1.16.2.1
memadai (misalnya limbah oli, menjamin bahwa tempat kerja, struktur, kantor sementara, tempat
semen dan aspal). hunian dipelihara bebas dari akumulasi sisa bahan bangunan, sampah
• Dampak terhadap kesehatan √ dan kotoran lainnya yang diakibatkan oleh operasi-operasi di tempat
dan keamanan pekerja/ kerja dan memelihara tempat kerja dalam kondisi rapi dan bersih
manusia. setiap saat.
• Kontraktor harus menyediakan drum di lapangan untuk menampung 1.16.2.6
sisa bahan bangunan, kotoran dan sampah sebelum dibuang dari
daerah kerja.
EINRIP General Specification
Divisi 1 - Umum
Kepatuhan
Spesifikasi
Kegiatan Tingkatan Dampak Terhadap
Kontrak
Sumber Dampak Jenis Dampak Upaya Pengelolaan Lingkungan Spesifikasi Hambatan/Masalah
EINRIP
Signifi Moder Minor (VI.2)
Ada Tidak Ya Tidak
cant ate
Lanjutan… • Kontraktor harus membuang sisa bahan bangunan, kotoran dan 1.16.2.7
Pembangunan dan sampah di tempat yang telah ditentukan sesuai dengan Peraturan
pengoperasian Pusat maupun Daerah dan Undang-undang Pencemaran Lingkungan
basecamp dan yang berlaku.
AMP • Kontraktor tidak diperkenankan mengubur sampah atau sisa bahan 1.16.2.8
bangunan di lokasi proyek tanpa persetujuan dari Direksi Pekerjaan.
• Kontraktor tidak diperkenankan membuang limbah berbahaya, seperti 1.16.2.9
cairan kimia, minyak atau thinner cat ke dalam saluran atau sanitasi
yang ada.
• Kontraktor tidak diperkenankan membuang sisa bahan bangunan ke 1.16.2.10
dalam sungai atau saluran air.
• Kontraktor harus memastikan bahwa semua pengaruh dari semua 1.17.2.1 (a)
kegiatan Kontraktor tidak akan melampaui ambanag batas yang
diuraikan dalam Hkum yang berlaku. (Rujuk terutama pada Peraturan
Pemerintah No.82 Tahun 2001 sehubungan dengan Manajemen Mutu
Air Kualitas dan Pengendalian Pencemaran Air).
• Setiap cairan berbahaya atau bahan pencemar padat, seperti minyak 1.17.2.1 (h)
hidrolik atau minyak pelumas, yang jatuh atau tumpah diatas tempat
kerja dan lingkungan yang bersebelahan, base camp, atau route
pengangkutan harus dibersihkan segera oleh Kontraktor agar dapat
menghindari pencemaran air dan tanah. Direksi Pekerjaan harus
menyetujui selesainya pembersihan.
• Cara yang memadai untuk menjebak lanau di instalasi pencampur 1.17.2.1 (i)
harus disediakan melalui sistem pembuangan sementara ke dalam
system drainase yang permanen.
• Pencucian kendaraan dan peralatan Kontraktor hanya diperkenankan 1.17.2.1 (j)
pada daerah yang khusus dirancang dan dilengkapi dan tidak akan
diperkenankan untuk setiap saluran air.
• Instalasi pencampuran aspal harus dipasang di lokasi yang jauh dari 1.17.2.2 (b)
pemukiman dan disetujui oleh Direksi Pekerjaan sehingga tidak
mengganggu ataupun protes dari penduduk di sekitarnya.
• Instalasi pencampur aspal (AMP) harus dilengkapi dengan alat 1.17.2.2 (c)
pengumpul debu (dust collector) yang lengkap yaitu sistem pusaran
kering (dry cyclone) dan pusaran basah (wet cyclone) sehingga tidak
menimbulkan pencemaran debu. Bilamana salah satu sistem di atas
rusak atau tidak berfungsi maka instalasi pencampur aspal tidak boleh
dioperasikan.
• Kontraktor harus melakukan semua peringatan untuk memperkecil 1.17.2.3
kebisingan dan vibrasi yang timbul dari kegiatan konstruksi dan
pengangkutan, oleh semua kendaraan dan peralatan,dengan
menggunakan kendaraan dan peralatan yang modern serta dengan
manajemen dan pemeliharaan yang baik. Semua tingkat kebisingan
dan vibrasi dari semua Kegiatan Kontraktor adalah sesuai dengan
Hukum yang berlaku (Keputusan Menteri LH No.48 Tahun 1996
tentang Tingkat Baku Kebisingan dan Keputusan Menteri LH No 49
Tahun 1996 tentang Tingkat Vibrasi).
EINRIP General Specification
Divisi 1 - Umum
Kepatuhan
Spesifikasi
Kegiatan Tingkatan Dampak Terhadap
Kontrak
Sumber Dampak Jenis Dampak Upaya Pengelolaan Lingkungan Spesifikasi Hambatan/Masalah
EINRIP
Signifi Moder Minor (VI.2)
Ada Tidak Ya Tidak
cant ate
Lanjutan… • Kontraktor harus senantiasa melakukan semua peringatan yang layak 1.17.2.5 (a)
Pembangunan dan untuk menjaga kesehatan dan keselamatan Personil Kontraktor. Dalam
pengoperasian kerjasamanya dengan pejabat kesehatan setempat, Kontraktor harus
basecamp dan memastikan bahwa pertolongan pertama pada kecelakaan (P3K) dan
AMP kamar sakit harus tersedia di Lapangan setiap saat dan harus
dipasang informasi yang jelas pada tempat yang mudah dijangkau
tentang bagaimana mengangkut Personil yang terluka menuju ke
tempat pengobatan termasuk ketepatan lokasi dan detil-detil orang
yang dapat dihubungi pada tempat pengobatan tersebut, nama dan
detil-detil petugas pencegahan kecelakaan lapangan yang ditunjuk dan
pengaturan yang memadai telah dilakukan untuk semua kesejahteraan
dan higienis yang perlu dan untuk pencegahan wabah epidemik. Ini
harus termasuk sebuah mobil di lapangan yang selalu siap sedia untuk
digunakan mengangkut Personil menuju tempat pengobatan.
• Kontraktor harus senantiasa melakukan semua peringatan yang layak 1.17.2.5 (c)
untuk menjaga kesehatan dan keselamatan Personil Kontraktor dan
harus menunjuk seorang petugas pencegahan kecelakaan di
Lapangan, bertanggungjawab untuk menjaga keselamatan dan
perlindungan terhadap kecelakaan
• Kontraktor harus senantiasa melakukan peringatan yang perlu untuk 1.17.2.5 (d)
menlindungi Personil Kontraktor yang dipekerjakan di Lapangan dari
gangguan serangga dan hama, dan mengurangi resiko terhadap
kesehatan.
• Semua gigi-gigi, pulley (roda penyesuai putaran), rantai, gigi jentera 1.17.2.5 (f)
dan bagian bergerak yang berbahaya lainnya dari Instalasi Pencampur
harus diamankan dan dilindungi seluruhnya.
• Kontraktor harus menyediakan alat pemadam kebakaran yg memadai 1.3.1.2 (j)
di seluruh barak,kantor,gudang dan bengkel.
• Kontraktor harus memastikan bahwa Base Camp yang dioperasikan 1.17.2.10(b)
sesuai dengan praktek secara lingkungan yang baik dan dampak
lingkungan yang kurang baik tersebut dipertahankan pada tingkat yang
senimim mungkin dan sesuai dengan seksi ini, dan masyarakat
setempat tersebut tidak terganggu oleh setiap kegiatan dari Base
Camp.
• Upaya mitigasi lainnya (silahkan dideskripsikan disini):

Penyimpanan • Peningkatan polusi √ • Penumpukan berbagai jenis agregat yang akan dipergunakan untuk 1.11.3.3 (b)
material udara/debu. campuran aspal, burtu atau burda, penetrasi macadam atau beton
• Pencemaran air/kerusakan √ harus dilakukan secara terpisah menurut masing-masing ukuran
drainase. nominal agregat. Dinding pemisah dari papan dapat digunakan untuk
harus mencegah tercampurnya agregat-agregat tersebut.

• Kerusakan jalan. √ • Sungai atau saluran alami di dalam atau bersebelahan dengan 1.17.2.1 (b)
• Lokasi pembuangan sisa √ pekerjaan dalam Kontrak ini tidak boleh diganggu tanpa persetujuan
material. Direksi Pekerjaan.
EINRIP General Specification
Divisi 1 - Umum
Kepatuhan
Spesifikasi
Kegiatan Tingkatan Dampak Terhadap
Kontrak
Sumber Dampak Jenis Dampak Upaya Pengelolaan Lingkungan Spesifikasi Hambatan/Masalah
EINRIP
Signifi Moder Minor (VI.2)
Ada Tidak Ya Tidak
cant ate
Lanjutan… • Kontraktor harus mempertahankan di tempat kerja pemasokan air 1.17.2.2 (e)
Penyimpanan yang memadai untuk pengendalian kadar air selama semua operasi
material penghamparan dan pemadatan, dan harus membuang bahan yang
berlebihan dari semua jalan yang ada.
• Pada setiap saat selama pelaksanaan Pekerjaan, Kontraktor harus 1.17.2.4 (f)
memastikan bahwa perkerasan, bahu jalan dan daerah yang
bersebelahan di dalam Daerah Milik Jalan harus dijaga bebas dari
bahan konstruksi, sampah atau benda-benda lepas lainnya yang dapat
menghalangi atau membahayakan kebebasan dan keselamatan lalu
lintas yang lewat.
• Upaya mitigasi lainnya (silahkan dideskripsikan disini):

Pekerjaan • Gangguan fungsi saluran √ • Kontraktor harus mengerjakan relokasi atau perlindungan terhadap 2.1.1.1 (b)
Drainase drainase sungai yang ada, kanal irigasi atau saluran air lainnya yang pasti tidak
(termasuk kanal, • Perubahan aliran permukaan √ terhindarkan dari gangguan baik yang bersifat sementara maupun
gorong-gorong • Banjir mengalir diatas jalan √ tetap.
dan dinding • Gangguan lalu lintas √
penahan) • Sungai atau saluran alami di dalam atau bersebelahan dengan 1.17.2.1 (b)/
pekerjaan dalam Kontrak ini tidak boleh diganggu tanpa persetujuan 2.1.3.3. (a)
Direksi Pekerjaan.
• Jika setiap penggalian atau pengerukan pada dasar sungai tidak dapat 1.17.2.1 (c)/
dihindarkan untuk pelaksanaan pekerjaan yang sebagaimana 2.1.3.3. (b)
mestinya, Kontraktor harus, setelah pekerjaan tersebut selesai,
menimbun kembali penggalian tersebut sampai kembali ke kondisi
awal permukaan atau dasar sungai dengan bahan yang disetujui oleh
Direksi Pekerjaan.
• Bahan yang ditumpuk/tertinggal di daerah sungai dari pondasi atau 1.17.2.1 (d)/
penggalian lainnya, atau dari penempatan cofferdam, harus 2.1.3.3. (c)
disingkirkan seluruhnya setelah pelaksanaan.
• Saluran air harus direlokasi untuk memastikan aliran dapat melewati 1.17.2.1.(e)/
daerah pekerjaan tanpa halangan pada semua tingkat banjir, di mana 2.1.3.3. (c)
stabilisasi timbunan atau pekerjaan permanent lainnya secara tak
terhindarkan akan menghalangi, atau menghalangi sebagian, dari
setiap saluran yang ada.
• Upaya mitigasi lainnya (silahkan dideskripsikan di sini):

Pekerjaan tanah • Polusi udara dan sebaran √ • Kontraktor harus memikul semua tanggung jawab dalam menjamin 3.1.1.5. (a)
(galian, timbunan, debu. keselamatan pekerja, yang melaksanakan pekerjaan galian, penduduk
penyiapan badan • Gangguan aliran air √ dan bangunan yang ada di sekitar lokasi galian.
jalan) permukaan.
• Gangguan utilitas umum √ • Untuk menjaga stabilitas lereng galian dan keselamatan pekerja maka 3.1.1.5. (b) 0
(listrik, telepon, air bersih, galian tanah yang lebih dari 5 meter harus dibuat bertangga dengan
irigasi, dll). teras selebar 1 meter atau sebagaimana yang diperintahkan Direksi
• Kecelakaan pekerja dan orang √ Pekerjaan.
lainnya.
EINRIP General Specification
Divisi 1 - Umum
Kepatuhan
Spesifikasi
Kegiatan Tingkatan Dampak Terhadap
Kontrak
Sumber Dampak Jenis Dampak Upaya Pengelolaan Lingkungan Spesifikasi Hambatan/Masalah
EINRIP
Signifi Moder Minor (VI.2)
Ada Tidak Ya Tidak
cant ate
Lanjutan……. • Gangguan kondisi lalu lintas di √ • Dalam setiap saat, bilamana pekerja atau orang lain berada dalam 3.1.1.5. (e)
Pekerjaan tanah sepanjang rute pengangkutan lokasi galian dan harus bekerja di bawah permukaan tanah, maka
(galian, timbunan, material dan sekitar daerah Kontraktor harus menempatkan seorang pengawas keamanan di lokasi
penyiapan badan kerja. kerja yang tugasnya hanya memantau keamanan dan kemajuan.
jalan) • Kerusakan perkerasan jalan √ Sepanjang waktu penggalian, peralatan galian cadangan (yang belum
eksisting pada rute dipakai) serta perlengkapan P3K harus tersedia pada tempat kerja
pengangkutan material. galian.
• Dampak estetika lingkungan. √ • Semua galian terbuka harus diberi rambu peringatan dan penghalang 3.1.1.5. (g)
• Kebisingan dan getaran dari √ (barikade) yang cukup untuk mencegah pekerja atau orang lain
pengoperasian alat-alat berat. terjatuh ke dalamnya, dan setiap galian terbuka pada lokasi jalur lalu
• Erosi tanah dan potensi √ lintas maupun lokasi bahu jalan harus diberi rambu tambahan pada
longsor. malam hari berupa drum yang dicat putih (atau yang sejenis) beserta
• Penebangan pohon-pohon. √ lampu merah atau kuning guna menjamin keselamatan para pengguna
jalan, sesuai dengan yang diperintahkan Direksi Pekerjaan.
• Jalan umum dan jembatan yang berdekatan dengan proyek dan 10.2.2
digunakan oleh Kontraktor selama kegiatan transportasi dan
pengangkutan dalam pelaksanaan Pekerjaan, termasuk perkuatan
jembatan yang ada oleh Kontraktor, pembuatan jembatan sementara
oleh Kontraktor dan jalan masuk ke lokasi sumber bahan yang
menerima beban berat tambahan sebagai akibat kegiatan Kontraktor,
harus dipelihara secara keseluruhan oleh Kontraktor dengan biaya
sendiri selama waktu yang diperlukan untuk Pekerjaan tersebut dan
harus ditinggalkan dalam keadaan berfungsi dengan baik, mutu dan
kenyamanannya tidak lebih buruk daripada sebelum kegiatan
Kontraktor dimulai. Jembatan sementara yang dibuat oleh Kontraktor
menurut Seksi dari Spesifikasi ini tidak boleh dibongkar oleh Kontraktor
pada Tanggal Penyelesaian Pekerjaan kecuali diperintah lain oleh
Direksi Pekerjaan.
• Seluruh pekerjaan jalan sementara dan kelengkapan pengendali lalu 10.2.3.1
lintas yang disediakan oleh Kontraktor di atas jalan samping atau jalan
lokal ke lokasi pekerjaan setiap saat selama Periode Kontrak harus
dipelihara dalam kondisi aman dan dapat berfungsi menurut ketentuan
dan dapat diterima oleh Direksi Pekerjaan, sehingga dapat menjamin
keamanan lalu lintas lainnya dan masyarakat yang menggunakan jalan
tersebut. Ketentuan pengendalian lalu lintas harus memenuhi
ketentuan dari Seksi 1.8. Manajemen Lalu lintas dan Keselamatan.
• Galian parit atau galian lainnya yang memotong jalan harus 1.17.2.4.(b)/
dilaksanakan dengan menggunakan pelaksanaan setngah lebar jalan 3.1.1.6 (b)
sedemikian hingga jalan tersebut dapat dipertahankan terbuka untuk
lalu lintas setiap saat.
• Seluruh galian harus dijaga agar bebas dari air dan Kontraktor harus 1.17.2.1.(f)/
menyediakan semua bahan, perlengkapan dan pekerja yang 3.1.1.7 (a)
diperlukan untuk pengeringan (pemompaan), pengalihan saluran air dan 3.1.2.7
dan pembuatan drainase sementara, dinding penahan rembesan (cut
off wall) dan cofferdam. Pompa siap pakai di lapangan harus
senantiasa dipelihara sepanjang waktu untuk menjamin bahwa tak
akan terjadi gangguan dalam pengeringan dengan pompa.
EINRIP General Specification
Divisi 1 - Umum
Kepatuhan
Spesifikasi
Kegiatan Tingkatan Dampak Terhadap
Kontrak
Sumber Dampak Jenis Dampak Upaya Pengelolaan Lingkungan Spesifikasi Hambatan/Masalah
EINRIP
Signifi Moder Minor (VI.2)
Ada Tidak Ya Tidak
cant ate
Lanjutan……. • Bilamana Pekerjaan sedang dilaksanakan pada drainase lama atau 3.1.1.7 (b)
Pekerjaan tanah tempat lain dimana air atau tanah rembesan (seepage) mungkin sudah
(galian, timbunan, tercemari, maka Kontraktor harus senantiasa memelihara tempat kerja
penyiapan badan dengan memasok air bersih yang akan digunakan oleh pekerja
jalan) sebagai air cuci, bersama-sama dengan sabun dan desinfektan yang
memadai.
• Kontraktor harus bertanggung-jawab untuk memperoleh setiap 1.17.2.4(f)/
informasi yang ada tentang keberadaan dan lokasi utilitas yang ada di 3.1.1.9 (a)
bawah tanah dan untuk memperoleh dan membayar setiap perijinan
yang perlu atau keperluan lainnya atau wewenang lainnya yang
diperlukan dalam melaksanakan galian yang diperlukan dalam
Kontrak.
• Kontraktor harus bertanggung-jawab untuk hati-hati dan perlindungan 1.17.2.4(g)/
atas setiap pipa, kabel, selongsong bawah tanah yang ada atau 3.1.1.9 (b)
jaringan bawah tanah lainnya atau struktur yang mungkin diketemukan
dan untuk memperbaiki setiap kerusakan terhadap utilitas bawah tanah
yang disebabkan oleh pengoperasiannya.
• Setiap bahan galian yang sementara waktu diijinkan untuk ditempatkan 3.1.1.12(c)
dalam saluran air harus dibuang seluruhnya setelah pekerjaan berakhir
sedemikian rupa sehingga tidak mengganggu saluran air.
• Semua tindakan yang perlu harus dilakukan selama dan segera 3.1.2.4(b)
setelah pekerjaan galian selesai untuk menghindari kerusakan
permukaan galian. Tindakan-tindakan dapat mencakup drainase
sementara, sodding, dan tindakan lainnya yang sesuai.
• Setiap permukaan galian harus dibersihkan dari setiap material lepas 3.1.2.4(d)
yang dapat membahayakan setelah pekerjaan selesai.
• Penggalian sumber bahan harus dilarang atau dibatasi bilamana 3.1.2.8.(d) &
penggalian ini dapat mengganggu drainase alam atau yang dirancang; (e)
pada daerah yang lebih tinggi dari permukaan jalan, sumber bahan harus
diratakan sedemikian rupa sehingga mengalirkan seluruh air permukaan
ke gorong-gorong berikutnya tanpa genangan.
• Kontraktor harus mempertahankan di tempat kerja pemasokan air 1.17.2.2 (e)
yang memadai untuk pengendalian kadar air selama semua operasi
penghamparan dan pemadatan, dan harus membuang bahan yang
berlebihan dari semua jalan yang ada.
• Agar dapat menghindari kelongsoran dan erosi tanah selama 1.17.2.7
penggalian untuk bahan timbunan, tepi dari galian untuk bahan
timbunan tersebut tidak boleh lebih dekat 2 meter dari tumit timbunan
atau 10 meter dari puncak setiap galian.
• Pemotongan pohon harus dilakukan hanya bilamana mutlak diperlukan 1.17.2.6.(a)
baik untuk pelebaran maupun untuk bahu jalan dan akan ditetapkan
secara khusus serta disepakati oleh semua pihak selama investigasi
lapangan. Setiap pohon yang ditebang harus diganti dengan dua
pohon yang sudah hampir jadi (bukan pohon kecil) dengan jenis yang
sama atau sejenis. Tidak ada pohon yang boleh ditanam dalam zone
bebas.
EINRIP General Specification
Divisi 1 - Umum
Kepatuhan
Spesifikasi
Kegiatan Tingkatan Dampak Terhadap
Kontrak
Sumber Dampak Jenis Dampak Upaya Pengelolaan Lingkungan Spesifikasi Hambatan/Masalah
EINRIP
Signifi Moder Minor (VI.2)
Ada Tidak Ya Tidak
cant ate
• Sesuai dengan praktek pengembangan yang berkelanjutan, semua 1.17.2.10.(c)
bahan kayu untuk turap, tiang pancang pemikul beban, cerucuk, harus
dibeli dealer yang sah (tidak berasal dari penebangan liar) dan
sertifikat keabsahan yang dilampirkan pada dokumen pembelian harus
diserahkan kepada Direksi Pekerjaan.
• Kontraktor harus bertanggung-jawab untuk hati-hati dan perlindungan 1.17.2.4 (g)
atas setiap pipa, kabel, selongsong bawah tanah yang ada atau
jaringan bawah tanah lainnya atau struktur yang mungkin diketemukan
dan untuk memperbaiki setiap kerusakan terhadap utilitas bawah tanah
yang disebabkan oleh pengoperasiannya
• Kontraktor harus melakukan semua peringatan untuk memperkecil 1.17.2.3
jumlah kebisingan dan vibrasi yang dating dari kegiatan konstruksi dan
pengangkutan, oleh semua kendaraan dan peralatan, dengan
menggunakan kendaraan dan peralatan yang modern serta dengan
manajemen dan pemeliharaan yang baik. Kontraktor harus
memastikan bahwa semua tingkat kebisingan dan vibrasi dari semua
Kegiatan Kontraktor adalah sesuai dengan Hukum yang berlaku (Rujuk
terutama pada Keputusan Menteri Lingkungan Hidup No.48 Tahun
1996 tentang Tingkat Baku Kebisingan dan Keputusan Menteri
Lingkungan Hidup No 49 Tahun 1996 tentang Tingkat Vibrasi.)
• Upaya mitigasi lainnya (silahkan dideskripsikan di sini):

Pelebaran • Gangguan kelancaran dan √ • Seluruh pekerjaan jalan sementara dan kelengkapan pengendali lalu 10.2.3.1.
Perkerasan dan keamanan lalu lintas lintas yang disediakan oleh Kontraktor di atas jalan samping atau jalan
Bahu Jalan; • Pencemaran tanah √ lokal ke lokasi pekerjaan setiap saat selama Periode Kontrak harus
Perkerasan Jalan • Hilangnya vegetasi dan √ dipelihara dalam kondisi aman dan dapat berfungsi menurut ketentuan
dan Perkerasan pohon-pohon di tepi jalan dan dapat diterima oleh Direksi Pekerjaan, sehingga dapat menjamin
Jembatan. • Polusi udara √ keamanan lalu lintas lainnya dan masyarakat yang menggunakan jalan
• Kebisingan √ tersebut. Ketentuan pengendalian lalu lintas harus memenuhi
ketentuan dari Seksi 1.8, Manajemen Lalu lintas dan Keselamatan.
• Peningkatan kecelakaan lalu √ • Kontraktor harus bertanggung jawab atas semua akibat yang ditimbulkan 4.2.1.10.
lintas oleh lalu lintas yang melewati bahu jalan yang baru selesai dikerjakan dan dan 6.1.1.7
• Kerusakan jalur material dan √ bila perlu Kontraktor dapat melarang lalu lintas yang demikian ini dengan dan
jalan pengalihan menyediakan jalan alih (detour) atau pelaksanaan setengah badan jalan. 1.17.2.4.

• Semua lubang pada perkerasan beraspal dan lubang-lubang 1.17.2.4 (h)


yang dibuat pada Pekerjaan yang sudah selesai akibat pengujian
kepadatan atau sebaliknya harus diperbaiki sesegera mungkin setelah
lapisan yang rusak tersebut sudah digali kembali, agar menghidarkan
bahaya terhadap lalu lintas.
• Setiap cairan berbahaya atau bahan pencemar padat, seperti 1.17.2.1 (h)
minyak hidrolik atau minyak pelumas, yang jatuh atau tumpah diatas dan 6.3.6.4
tempat kerja dan lingkungan yang bersebelahan, base camp, atau (k)
route pengangkutan harus dibersihkan segera oleh Kontraktor agar
dapat menghindari pencemaran air dan tanah. Direksi Pekerjaan harus
menyetujui selesainya pembersihan.
EINRIP General Specification
Divisi 1 - Umum
Kepatuhan
Spesifikasi
Kegiatan Tingkatan Dampak Terhadap
Kontrak
Sumber Dampak Jenis Dampak Upaya Pengelolaan Lingkungan Spesifikasi Hambatan/Masalah
EINRIP
Signifi Moder Minor (VI.2)
Ada Tidak Ya Tidak
cant ate
Lanjutan…… • Pembuangan semua limbah padat dan cair dari kegiatan konstruksi 1.17.2.8
Pelebaran hanya berlaku di tempat pembuangan yang disetujui atau dengan
Perkerasan dan persetujuan Direksi Pekerjaan yang telah membicarakannya dengan
Bahu Jalan; instansi yang berwenang sebelumnya untuk memastikan bahwa
Perkerasan Jalan pembuangan tersebut telah sesuai dengan ketentuan-ketentuan
dan Perkerasan mereka.
Jembatan. • Kontraktor harus mempertahankan di tempat kerja pemasokan air 1.17.2.2 (e)
yang memadai untuk pengendalian kadar air selama semua operasi dan 5.1.3.2
penghamparan dan pemadatan, dan harus membuang bahan yang
berlebihan dari semua jalan yang ada. Rentang kadar air disyaratkan
dalam Pasal 5.1.3.3.
• Kontraktor harus memastikan bahwa emisi dari semua kegiatan 1.17.2.2 (a)
Kontraktor tidak akan melampaui ambang batas yang disebutkan
dalam Hukum yang berlaku
• Upaya mitigasi lainnya (silahkan dideskripsikan di sini):

Sumber material • Penurunan stabilitas lereng √ • Seluruh tempat bekas galian bahan atau sumber bahan yang 3.1.1.12 (d)
• Hilangnya vegetasi penutup √ digunakan oleh Kontraktor harus ditinggalkan dalam suatu kondisi
tanah yang rata dan rapi dengan tepi dan lereng yang stabil dan saluran
drainase yang memadai.
• Dampak estetika √ • Penggalian untuk bahan timbunan harus dilarang atau dibatasi 1.17.2.1 (g)
• Peningkatan sedimentasi √ bilamana penggalian tersebut akan mengganggu drainase alami atau
• Peningkatan erosi sungai (bila √ yang dirancang.
sumber material di sungai) • Agar dapat menghindari kelongsoran dan erosi tanah selama 1.17.2.7
• Dampak terhadap ekosistem √ penggalian untuk bahan timbunan, tepi dari galian untuk bahan
sungai timbunan tersebut tidak boleh lebih dekat 2 meter dari tumit timbunan
• Gangguan pola aliran sungai √ atau 10 meter dari puncak setiap galian.
• Kontraktor harus memperoleh semua bahan yang ditambang (pasir, 1.17.2.10.(a)
kerikil, dsb) dari Sumber Bahan yang (1) : dimiliki atau disewa,
dioperasikan dan dikelola sesuai dengan hukum daerah dan nasional,
dan (2) beroperasi dengan keselamatan dan secara lingkungan yang
dapat diterima dan sesuai dengan seksi ini.
• Kontraktor harus memikul semua tanggung jawab dalam menjamin 3.1.1.5
keselamatan pekerja, yang melaksanakan pekerjaan galian, penduduk
dan bangunan yang ada di sekitar lokasi galian.
• Upaya mitigasi lainnya (silahkan dideskripsikan di sini):

Peledakan untuk • Kebisingan yang berasal dari √ • Bahan peledak yang diperlukan untuk galian batu harus disimpan, 3.1.1.5 (f)
material peledakan ditangani, dan digunakan dengan hati-hati dan di bawah pengendalian
• Sebaran debu √ yang extra ketat sesuai dengan Peraturan dan Perundang-undangan
• Tertutupnya jalan-jalan akses √ yang berlaku. Kontraktor harus bertanggungjawab dalam mencegah
• Penurunan dan gangguan √ pengeluaran atau penggunaan yang tidak tepat atas setiap bahan
visual peledak dan harus menjamin bahwa penanganan peledakan hanya
• Getaran √ dipercayakan kepada orang yang berpengalaman dan
• Longsor akibat vegetasi √ bertanggungjawab.
penutup tanah
EINRIP General Specification
Divisi 1 - Umum
Kepatuhan
Spesifikasi
Kegiatan Tingkatan Dampak Terhadap
Kontrak
Sumber Dampak Jenis Dampak Upaya Pengelolaan Lingkungan Spesifikasi Hambatan/Masalah
EINRIP
Signifi Moder Minor (VI.2)
Ada Tidak Ya Tidak
cant ate
• Bilamana lalu lintas pada jalan terganggu karena peledakan atau 3.1.1.6 (c)
operasi-operasi pekerjaan lainnya, Kontraktor harus mendapatkan
persetujuan terlebih dahulu atas jadwal gangguan tersebut dari pihak
yang berwenang dan juga dari Direksi Pekerjaan.
• Bilamana diperintahkan oleh Direksi Pekerjaan, Kontraktor harus 3.1.2.1 (f)
menyediakan anyaman pelindung ledakan (heavy mesh blasting) untuk
melindungi orang, bangunan dan pekerjaan selama penggalian. Jika
dipandang perlu, peledakan harus dibatasi waktunya seperti yang
diuraikan oleh Direksi Pekerjaan.
• Penggalian batu harus dilakukan sedemikian, apakah dengan peledakan 3.1.2.1.(g)
atau cara lainnya, sehingga tepi-tepi potongan harus dibiarkan pada
kondisi yang aman dan serata mungkin. Batu yang lepas atau
bergantungan dapat menjadi tidak stabil atau menimbulkan bahaya
terhadap pekerjaan atau orang harus dibuang, baik terjadi pada
pemotongan batu yang baru maupun yang lama.
• Direksi Pekerjaan dapat melarang peledakan dan memerintahkan untuk 3.1.2.1 (e)
menggali batu dengan cara lain, jika, menurut pendapatnya, peledakan
tersebut berbahaya bagi manusia atau struktur di sekitarnya, atau
bilamana dirasa kurang cermat dalam pelaksanaan-nya.
• Kontraktor harus memastikan bahwa semua tingkat kebisingan dan 1.17.2.3
vibrasi dari semua Kegiatan Kontraktor adalah sesuai dengan Hukum
yang berlaku (Rujuk terutama pada Keputusan Menteri Lingkungan
Hidup No.48 Tahun 1996 tentang Tingkat Baku Kebisingan dan
Keputusan Menteri Lingkungan Hidup No 49 Tahun 1996 tentang
Tingkat Vibrasi.)
• Upaya mitigasi lainnya (silahkan dideskripsikan di sini):

Pekerjaan • Kecelakaan tenaga √ • Seluruh pekerjaan jalan sementara dan kelengkapan pengendali lalu 10.2.3.1.
struktur kerja atau orang lain lintas yang disediakan oleh Kontraktor di atas jalan samping atau jalan
• Gangguan kondisi √ lokal ke lokasi pekerjaan setiap saat selama Periode Kontrak harus
lalulintas sekitar jalan dipelihara dalam kondisi aman dan dapat berfungsi menurut ketentuan
• Peningkatan √ dan dapat diterima oleh Direksi Pekerjaan, sehingga dapat menjamin
sedimentasi √ keamanan lalu lintas lainnya dan masyarakat yang menggunakan jalan
• Kebisingan dan tersebut.
getaran dari alat berat
• Seluruh upaya pengelolaan pada kegiatan mobilisasi alat berat dan
pengangkutan masterial harus diaplikasikan.
• Upaya mitigasi lainnya (silahkan dideskripsikan di sini):

Diketahui, Disetujui, Disusun,

Tanggal/Bulan/Tahun Direksi Pekerjaan Tanggal/Bulan/Tahun Supervising Engineer Tanggal/Bulan/Tahun General Superintenden


EINRIP General Specification
Divisi 1 - Umum

SEKSI 1.18

PENGUJIAN PENGEBORAN

1.18.1 UMUM

Pekerjaan ini terdiri dari pengujian pengeboran untuk investigasi lapangan untuk setiap
pondasi struktur yang akan dibutuhkan.

1.18.2 PENGUJIAN BOR (LUBANG)

1.18.2.1 Umum

Bilamana pengujian diperlukan Kontraktor harus melakukan beberapa pengujian bor pada
setiap sisi jembatan untuk memberikan profil lapisan tanah yang benar-benar tepat atau
sebaliknya diperintahkan lain oleh Direksi Pekerjaan. Lokasi pengujian harus disepakati
Direksi Pekerjaan tetapi umumnya akan berada pada posisi yang diusulkan untuk abutmen
dan pier. Bilamana batu nampak pada permukaan maka Direksi Pekerjaan dapat tidak
memerlukan pengujian bor tersebut lagi.

1.18.2.2 Kedalaman Bor (Lubang)

Pengujian bor harus dilakukan sampai mencapai lapisan tanah keras (bearing stratum) dan
sampai kedalaman yang cukup untuk membuktikan kesinambungannya. Umumnya
kedalaman tersebut harus lima meter. Jika lapisan tanah keras tidak dapat dicapai sampai
kedalaman 50 meter, pengujian bor dapat dihentikan setelah mendapat persetujuan dari
Direksi Pekerjaan.

1.18.2.3 Metoda Pengeboran

Kontraktor dapat menggunakan mesin bor dengan pencucian (rotary wash drilling). Pada
lapisan dasar batu harus dibor menerus.

1.18.2.4 Pengujian yang Diperlukan pada Semua Lubang

Standard penetration test (SPT) dan benda uji yang terganggu (Disturb Sample, DS) pada
Pengujian Pengeboran harus dilakukan sebagaimana yang diperintahkan oleh Direksi
Pekerjaan. SPT dan DS harus diambil dengan interval 2 (dua) meter atau pada setiap
perubahan strata tanah mana yang lebih kecil. Elevasi muka air tanah harus dicatat untuk
setiap lubang. Pada pengeboran batu maka seluruh benda uji inti harus diambil dan
disimpan dalam kotak benda uji inti untuk pemeriksaan Direksi Pekerjaan. Sondir (Dutch
Cone Penetration Test, Dutch CPT) harus dilakukan untuk mengukur tahanan ujung dan
hambatan akibat gesekan dengan interval 0,2 m sampai tahanan ujung maksimum sebesar
250 kg/cm2 dicapai atau mencapi kedalaman 60 meter.

1.18.2.5 Pencatatan Hasil Bor

Jika diminta oleh Direksi Pekerjaan, Kontraktor harus menyediakan hasil bor yang telah
selesai pada hari kerja tesrsebut disertai informasi berikut ini :

a) Nama Jembatan
b) Posisi bor dan nomor kode
c) Pengurangan elevasi puncak dari bor

1 -82
EINRIP General Specification
Divisi 1 - Umum

d) Tanggal dan waktu pengeboran


e) Diameter bor
f) Jenis alat yang digunakan
g) Kedalaman di mana pengeboran diberi casing
h) Kedalaman setiap lapisan dari permukaan
i) Uraian strata
j) Kedalaman dan hasil dari pengujian
k) Elevasi muka air tanah tetap
l) Keterangan

Semua uraian dan klasifikasi tanah harus sesuai dengan “Prosedur Pengujian Tanah,
ASTM” dan “Unified Soil Classification System, USCS”.

1.18.2.6 Pengujian Lanjutan Yang Mungkin Diperlukan

Direksi Pekerjaan dapat memnita pengujian yang lebih terinci dari yang diuraikan diatas
pada setiap sisi jembatan jika ditemukan bahwa informasi tersebut tidak memadai.

Bilamana diperintahkan oleh Direksi Pekerjaan, benda uji inti yang tak terganggu harus
diambil dalam lapisan tanah kohesif dengan menggunakan tabung shelby.

Benda uji silinder yang disegel akan digunakan untuk pengangkutan dari lapangan ke
laboratorium. Semua laboratorium harus menjadi tanggungjawab Direksi Pekerjaan.

1.18.3 PENGUKURAN DAN PEMBAYARAN

1.18.3.1 Pengukuran

Pengujian pengeboran harus diukur untuk maksud pembayaran sebagai panjang dari lubang
yang dibor tidak peduli bahan apa yang dijumpai.

1.18.3.2 Dasar Pembayaran

Pembayaran akan dilakukan menurut kuantitas yang diukur diatas dan dengan Harga
Kontrak per meter panjang untuk mata pembayaran yang terdapat dalam daftar di bawah
ini serta ditunjukkan dalam Daftar Kuantitas dan Harga. Pembayaran harus sudah termasuk
kompensasi penuh untuk semua pengeboran, casing jika diperlukan, pengujian penetrasi
dan pengambilan benda uji, pencatatan dan penunjukkan hasil uji serta penyimpanan benda
uji sampai pembuangan benda uji disetujui oleh Direksi Pekerjaan.

Nomor Mata Uraian Satuan


Pembayaran Pengukuran

1.18.1 Pengeboran, termasuk SPT dan Laporan Meter Panjang

1.18.2 Sondir termasuk Laporan Meter Panjang

1 -83
EINRIP General Specification
Divisi 1 - Umum

SEKSI 1.19

RELOKASI UILITAS DAN PELAYANAN YANG ADA

1.19.1 URAIAN

Pekerjaan ini harus terdiri dari relokasi pelayanan bawah tanah seperti selongsong dan
kabel, tiang listrik, menara listrik, tiang telepon, tiang pesawat pengatur lalu lintas, beserta
seluruh alat penunjang yang berkaitan, sebagaimana yang perlu untuk pelaksanaan jalan
yang sebagaimana mestinya dan lancar, seperti yang ditunjukkan dalam Gambar atau
sebagaimana yang diperintahkan oleh Direksi pekerjaan.

1.19.2 PENGATURAN DENGAN PEJABAT SETEMPAT

1.19.2.1 Dalam konteks ini istilah Pejabat Setempat harus berarti setiap pejabat utilitas umum atau
pemasok atau lainnya yang bertanggung-jawab terhadap utilitas dan pelayanan umum.

1.19.2.2 Sesuai dengan Syarat-syarat Kontrak, Kontraktor bertanggung-jawab untuk menghubungi


Pejabat Setempat dan memberikan kepada Direksi Pekerjaan berikut ini :
Detil lokasi dari semua utilitas dan pelayanan yang perlu dipindahkan, ditempatkan atau terganggu
sementara untuk memperbolehkan pekerjan jalan yang direncanakan dapat berjalan.
Salinan-salinan dari aturan setempat, peraturan, standar dan spesifikasi.
Denah kerja yang detil menunjukkan relokasi utilitas dan pelayanan yang diperlukan.
Persetujuan tertulis atas denah-denah ini dari setiap pejabat setempat yang berkaitan, dan
Ijin atau Perijinan dari Pejabat Setempat yang diperlukan.

1.19.2.3 Pembayaran setiap biaya yang berhubungan dengan perolehan ijin tersebut dsb. Harus
menjadi tanggung-jawab Kontraktor. Dalam hal-hal seperti ini, Pemilik akan membantu
Kontraktor untuk menghubungi Pejabat Setempat.

1.19.2.4 Setiap kerusakan terhadap utilitas dan pelayanan yang ada akibat operasi Kontraktor harus
diperbaiki oleh Kontraktor dengan biayanya sendiri.

1.19.3 PEMERIKSAAN PEKERJAAN DAN RELOKASI FASILITAS

1.19.3.1 Dalam relokasi pekerjaan, jika dilaksanakan oleh Kontraktor dengan persetujuan Pejabat
Setempat dan Direksi Pekerjaan, harus tunduk pada pemeriksaan dan penerimaan dari
keduanya.

1.19.3.2 Terhadap masing-masing instansi yang melaksanakan pekerjaan, Kontarktor harus


bertanggung-jawab untuk melakukan pengaturan dengan masing-masing Pejabat Setempat
formalitas yang diperlukan untuk memastikan penyambungan kembali fasilitas tersebut
yang cepat dan memuaskan setelah relokasi pekerjaan tersebut selesai dikerjakan.

1.19.4 JADWAL PEKERJAAN

1.19.4.1 Pengaturan yang diperlukan dengan Pejabat Setempat, harus dilaksanakan selama Periode
Mobilisasi atau sebelumnya, dan Kontraktor harus mengajukan suatu program untuk
relokasi pekerjaan sebelum akhir Periode Mobilisasi kepada Direksi Pekerjaan.

1.19.4.2 Bilamana gangguan sementara terhadap pelayanan yang ada diperlukan selama Kontrak,
Kontraktor harus melakukan pengaturan yang diperlukan dengan Pejabat Setempat, dan

1 -84
EINRIP General Specification
Divisi 1 - Umum

mengajukan programnya untuk pekerjaan tersebut kepada Direksi Pekerjaan dalam waktu
30 hari setelah pemberitahuan tertulis dari Direksi Pekerjaan atas persetujuan tersebut.

1.19.4.3 Keterlambatan pengajuan program tersebut, atau keterlambatan mengawali pengaturan


dengan Pejabat Setempat oleh Kontarktor yang mengakibatkan keterlambatan pada
pekerjaan jalan dan jembatan yang timbul dengan cara apapun terhadap pelaksanaan
relokasi pekerjaan atau gangguan sementara terhadap pelayanan yang ada, tidak boleh
dipandang sebagai dasar untuk meminta perpanjangan waktu untuk Waktu untuk
Penyelesaian.

1.19.5 PELAKSANAAN

1.19.5.1 Bilamana Direksi Pekerjan memerintahkan beberapa atau semua dari pekerjaan relokasi yang
actual untuk dilaksanakan Kontraktor, Kontraktor harus melaksanakan pekerjaan dengan ketat
sesuai dengan Spesifikasi ini dan memenuhi seluruh aturan, peraturan, spesifikasi dan
ketentuan lain atau arahan dari Pejabat Setempat yang terkait.

1.19.5.2 Kontraktor, harus bertanggung-jawab untuk memperoleh dari Pejabat Setempat semua
informasi yang berhubungan dengan lokasi, fungsi dan penggunaan sekarang ini atas utilitas
dan pelayanan yang akan dipindahkan dan harus melakukan investigasi kondisi lapangan
secara keseluruhan sebelum memulai pengoperasiannya.

1.19.5.3 Setiap kerusakan atau tuntutan lebih lanjut yang disebabkan oleh operasi-operasi ini akibat
ketidaktahuan, kealpaan atau kecerobohan pada pihak Kontraktor harus diperbaiki oleh
Kontraktor dengan biayanya sendiri.

1.19.5.4 Pelayanan yang ada harus baik diputus secara sementara maupun permanen, haruslah salah
satu dialihkan atau diputus secara benar dan aman di bawah pengawasan Pejabat Setempat,
dan semua bahan yang masih dapat diselamatkan harus dibersihakan dengan hati-hati dan
disimpan di lapangan untuk pengembalian oleh pemilik (baik Pejabat Setempat atau Pemilik,
sebagaimana yang munkin terjadi).

1.19.5.5 Bahan-bahan yang terlapisi dengan pelapis lama yang akan dipasang kembali di lokasi baru
harus disiapkan, sebagaimana yang diperintahkan oleh Direksi Pekerjaan dan sesuai dengan
ketentuan-ketentuan dari Pejabat Setempat, dengan bahan pengawet atau pencegah karat dan
selanjutnya harus dicat ulang sebelum dipasang kembali.

1.19.5.6 Bahan-bahan lama yang rusak cukup serius atau lapuk dan akan dipasang kembali harus
dibuang keluar lapangan oleh Kontraktor, dan diganti dengan bahan yang semua baru
sebagimana yang diperintahkan oleh Direksi Pekerjaan. Jika kontribusi bahan-bahan lama
tidak dapat digunakan karena kerusakan yang disebabkan oleh Kontraktor, bahan-bahan
tersebut harus diperbaiki atau diganti oleh Kontraktor dengan biayanya sendiri kecuali jika
disepakati bersama oleh semua pihak yang terlibat bahwa kerusakan tersebut tidak dapat
dihindarkan.

1.19.5.7 Lubang atau kerusakan lain di lapangan yang diakibatkan harus dikembalikan kondisinya oleh
Kontraktor sebagaimana yang diperintahkan oleh Direksi Pekerjaan dan sesuai dengan
ketentuan-ketentuan yang relevan dengan Dokumen Kontrak.

1 -85
EINRIP General Specification
Divisi 1 - Umum

1.19.6 PENGUKURAN DAN PEMBAYARAN

1.19.6.1 Pengukuran

Mata Pembayaran yang terpisah untuk masing-masing Pejabat Setempat disediakan dalam
seksi ini untuk pemindahan, relokasi atau gangguan terhadap Utilitas dan Pelayanan Yang
Ada.
Pengukuran untuk pembayaran dalam kontrak ini untuk porsi pekerjaan relokasi yang dilaksanakan baik
oleh Pejabat Setempat/Perusahaan Utilitas terkait maupun oleh Kontraktor haruslah dalam satu satuan
dengan pengecualian relokasi pipa yang diukur dengan dasar meter panjang. Bilamana relokasi tersebut
dilaksanakan oleh Pejabat Setempat/Perusahaan Utilitas, Kontraktor harus melakukan pembayaran
terlebih dahulu langsung kepada Pejabat Setempat/Perusahaan. Penggantian akan dilaksanakan bilamana
pekerjaan tersebut selesai dan diterima oleh Direksi Pekerjaan.

a) Ongkos untuk ijin dari Pejabat Setempat, salinan-salinan aturan yang relevan, dsb.,
yang harus dibayar oleh Kontraktor tidak boleh diukur secara terpisah untuk
pembayaran.

1.19.6.2 Dasar Pembayaran

Pekerjaan yang diterima, diukur sebagaimana disyaratkan diatas, harus dibayar dengan
Harga Kontrak per satuan pengukuran untuk Mata Pembayaran yang terdaftar di bawah ini
dan ditunjukkan dalam Daftar Kuantitas dan Harga, di mana harga dan pembayaran
tersebut harus merupakan kompensasi penuh untuk relokasi utilitas yang terkait terhadap
posisi yang dirancang, dan untuk setiap bagian bahan atau pekerjaan pendukung yang
diperlukan, pengembalian kondisi daerah perkerasan lama setelah relokasi selesai, dan
semua pekerjaan lainnya atau biaya-biaya yang perlu atau umum untuk penyelesaian yang
sebagaimana mestinya atas pekerjaan yang diuraikan dalam Seksi ini.

Nomor Mata Uraian Satuan


Pembayaran Pengukuran

1.19.1 Relokasi Tiang Telepon Yang Ada Buah

1.19.2 Relokasi Tiang Listrik Yang Ada, Tegangan Buah


Rendah

1.19.3 Relokasi Tiang Listrik Yang Ada, Tegangan Buah


Menengah

1.19.4 Relokasi Pipa Utilitas Gas Yang Ada, diameter (....) Meter Panjang

1.19.5 Relokasi Utilitas Pesawat Lalu Lintas Yang Ada Unit

1.19.6 Relokasi Tiang Pesawat Lalu Lintas Yang Ada Buah

1.19.7 Relokasi Panel Listrik Yang Ada Buah

1 -86
EINRIP General Specification
Divisi 1 - Umum

SEKSI 1.20

USULAN PERUBAHAN REKAYASA NILAI

Kontraktor boleh, pada saat kapanpun, mengajukan kepada Direksi Pekerjaan suatu usulan tertulis
yang (menurut pendapat Kontraktor) akan, jika digunakan, i) mempercepat penyelesaian, ii)
mengurangi biaya Pemilik dalam melaksanakan, memelihara atau menjalankan Pekerjaan, iii)
meningkatkan efisiensi atau nilai bagi Pemilik atas Pekerjaan yang telah selesai, atau iv) sebaliknya
akan bermanfaat bagi Pemilik.

1.20.1 USULAN PERUBAHAN REKAYASA NILAI (UPRN) OLEH KONTRAKTOR

1.20.1.1 Kontraktor, jika diperbolehkan dalam Syarat-syarat Umum, didorong untuk


mengembangkan dan menawarkan usulan untuk memperbaiki teknik-teknik pelaksanaan,
alternatif bahan dan inovasi lainnya.

1.20.1.2 Usulan harus menyediakan suatu perbandingan proyek terhadap rancangan asli baik pada
segi biaya yang lebih rendah maupun dari segi peningkatan mutu, atau keduanya. Tidak
ada usulan yang dapat diterima jika mutu yang lebih rendah diterapkan pada proyek yang
dimaksud.

1.20.1.3 Jika usulan ditolak maka, pekerjaan harus diselesaikan sesuai Kontrak dengan harga
kontrak. Setiap keterlambatan proyek sehubungan dengan pengajuan dan peninjauan
usulan harus dipertimbangkan dalam kendali Kontraktor dan tidak dapat dimaklumi kecuali
keterlambatan tersebut disetujui sebagai bagian dari usulan.

1.20.1.4 UPRN harus memberikan penghematan biaya bagi Pemilik atau menyediakan peningkatan
mutu proyek tanpa mengorbankan fungsi-fungsi penting dan karakteristik dari fasilitas
tersebut. Fungsi-fungsi penting mencakup tetapi tidak terbatas pada : layanan hidup,
kebutuhan-kebutuhan akan pengembangan mendatang yang direncanakan, komitmen-
komitmen instansi pemerintah atau publik, ketentuan-ketentuan koridor, operasi ekonomi,
kemudahan pemeliharaan, penampilan yang diinginkan, keselamatan, dan dampak terhadap
lalu lintas publik atau terhadap lingkungan selama dan setelah pelaksanaan.

1.20.2 LINGKUP REKAYASA NILAI

1.20.2.1 UPRN mencakup rancangan dan pelaksanaan struktur yang mencakup tetapi tidak dibatasi
untuk jembatan, dinding penahan tanah, gorong-gorong beton persegi, gedung, pekerjaan
tanah (lereng atau timbunan).

1.20.2.2 Usulan perubahan jenis dan tebal struktur perkerasan akan ditolak.

1.20.2.3 Alternatif-alternatif yang diinvestigasi dan tidak dipilih dalam Laporan Rancangan Proyek
dapat disajikan dalam suatu UPRN, jika manfaat yang berarti dapat ditunjukkan kepada
Direksi Pekerjaan. Lagi pula, setiap kriteria rancangan dan kendala-kendala yang terdapat
dalam Laporan Rancangan Proyek tidak dapat diubah atau diperlonggar sebagai bagian dari
UPRN kecuali jika terdapat manfaat penting dan yang tidak diketahui sebelumnya dapat
dibuktikan kepada Direksi Pekerjaan.

1.20.2.4 Konsep rancangan hasil pengalaman atau jenis yang didemontrasikan, produk, struktur,
atau elemen-elemen yang belum pernah disetujui terlebih dahulu oleh Pemilik, secara
tertulis, untuk manfaat umum dapat dipandang sebagai suatu UPRN.

1 -87
EINRIP General Specification
Divisi 1 - Umum

1.20.2.5 Usulan harus memberikan penghematan biaya yang dicapai dan dibagikan kepada Pemilik.
Penghematan biaya yang ditimbulkan terhadap Kontrak sebagai akibat UPRN yang
ditawarkan oleh Kontraktor dan diterima oleh Direksi Pekerjaan harus dibagi antara
Kontraktor dan Pemilik.

1.20.3 PENGAJUAN UPRN

Kontraktor harus mengajukan Konsep Awal UPRN, diikuti dengan usulan lengkap jika
konsep awal tersebut disetujui. Usulan ini tunduk pada penolakan pada saat kapanpun jika
usulan tersebut tidak memenuhi kriteria yang dijabarkan dalam sub-seksi ini.

1.20.3.1 Pengajuan untuk Usulan Konseptual.

Untuk UPRN yang memerlukan sejumlah rancangan dan sumber-sumber pengembangan


lain yang penting, Kontraktor dapat mengajukan Usulan Konseptual untuk evaluasi awal.
Direksi Pekerjaan akan mengevaluasi informasi yang disediakan. Kontraktor kemudian
dinasehati secara tertulis jika dari Usulan Konseptual tersebut ditemukan kondisi atau
parameter yang menjadi dasar untuk penolakan. Tinjauan awal terhadap usulan konseptual
akan mengurangi resiko penolakan selanjutnya tetapi Pemilik tidak menjanjikan untuk
persetujuan akhir dari UPRN yang lengkap. Informasi berikut harus diajukan untuk setiap
Usulan Konseptual :

a) Pernyataan bahwa usulan tersebut diajukan sebagai suatu Konsep UPRN.

b) Uraian umum tentang perbedaan antara Kontrak yang ada dengan perubahan yang
diusulkan, dan keuntungan dan kerugian masing-masing, termasuk dampak terhadap
layanan hidup, kebutuhan-kebutuhan akan pengembangan mendatang yang
direncanakan, komitmen-komitmen instansi pemerintah atau publik, ketentuan-
ketentuan koridor, operasi ekonomi, kemudahan pemeliharaan, penampilan yang
diinginkan, keselamatan, dan dampak terhadap lalu lintas publik atau terhadap
lingkungan selama dan setelah pelaksanaan. Kontraktor harus mengajukan
permohonan secara tertulis informasi yang diperlukan dari Direksi Pekerjaan.

c) Satu set denah konseptual dan uraian perubahan yang diusulkan terhadap spesifikasi
Kontrak.

d) Perkiraan antisipasi penghematan biaya atau kenaikan biaya.

e) Pernyataan yang menyebutkan berikut ini :

i) Bilamana jawaban terhadap usulan konseptual dari Pemilik diperlukan untuk


mengcegah keterlambatan pelaksanaan kontrak yang ada.

ii) Jumlah waktu yang diperlukan untuk mengembangkan Usulan yang lengkap.

iii) Tanggal di mana Perintah Perubahan Kontrak harus dilaksanakan untuk


memperoleh manfaat maksimum dari Usulan.

iv) Dampak Usulan pada saat Kontrak selesai.

1.20.3.2 Pengajuan Usulan Perubahan Nilai Rekayasa Yang Lengkap.

Bahan dan informasi berikut harus diajukan untuk UPNR.

1 -88
EINRIP General Specification
Divisi 1 - Umum

a) Pernyataan bahwa usulan diajukan sebagai suatu UPNR

b) Uraian tentang perbedaan antara Kontrak yang ada dengan perubahan yang
diusulkan, dan keuntungan dan kerugian masing-masing, termasuk dampak terhadap
layanan hidup, kebutuhan-kebutuhan akan pengembangan mendatang yang
direncanakan, komitmen-komitmen instansi pemerintah atau publik, ketentuan-
ketentuan koridor, operasi ekonomi, kemudahan pemeliharaan, penampilan yang
diinginkan, keselamatan, dan dampak terhadap lalu lintas publik atau terhadap
lingkungan selama dan setelah pelaksanaan. Kontraktor harus mengajukan
permohonan secara tertulis informasi yang diperlukan dari Direksi Pekerjaan.

c) Suatu set lengkap rencana dan spesifikasi yang menunjukkan revisi yang diusulkan
relatif terhadap Kontrak asli. Pengajuan bagian ini harus mencakup catatan-catatan
rancangan dan detil-detil pelaksanaan. Usulan rencana dan spesifikasi harus ditanda-
tangani dan distempel oleh Insinyur dari Kontraktor.

d) Perbandingan biaya, ringkasan dari semua mata pembayaran yang diusulkan UPNR
untuk mengganti, mengurangi, menghapus, menambah, atau perubahan lainnya dari
pekerjaan Kontrak asli, termasuk semua dampak terhadap pengendalian lalu lintas,
jalan alih (detour) dan semua perubahan lainnya. Perbandingan biaya tidak boleh
termasuk penghematan biaya yang diakibatkan dari pengurangan inspeksi atau
kebutuhan pengujian yang hanya bersifat pura-pura, atau biaya tak terduga Pemilik;
Semua biaya dan harga satuan yang diusulkan harus didokumentasi oleh Kontraktor.

e) Penyataan yang menyebutkan tanggal di mana Perintah Perubahan Kontrak harus


dilaksanakan untuk memperoleh pengurangan biaya yang maksimum dari sisa waktu
Kontrak dan tanggal bilamana jawaban dari Pemilik diperlukan untuk menghindari
keterlambatan dalam pelaksanaan Kontrak.

f) Pernyataan yang merinci pengaruh yang akan dimiliki Usulan pada saat untuk
menyelesaikan Kontrak.

g) Uraian tentang penggunaan sebelumnya atau pengujian pada perubahan yang


diusulkan, kondisi-kondisi dan akibatnya. Jika Usulan diusulakan sebelumnya
kepada Pemilik proyek yang lain, usulan harus memberikan tanggal, nomor Kontrak,
dan tindakan yang diambil oleh Pemilik.

h) Perkiraan setiap pengaruh yang akan dimiliki UPRN atas biaya lain yang akan
ditanggung Pemilik.

i) Pernyataan biaya siklus umur, jika sesuai. Biaya siklus umur tidak boleh dipandang
sebagai bagian dari penghematan biaya tetapi harus dihitung sebagai penunjang
tambahan terhadap Usulan. Suatu rabat sebesar empat persen akan digunakan untuk
perhitungan siklus umur.

1.20.3.3 Evaluasi.

UPRN harus dievaluasi oleh Pemilik sesuai dengan Manual Pelaksanaan Pemilik.

Informasi tambahan yang diperlukan untuk mengevaluasi Usulan harus disediakan dalam
waktu yang tepat. Pengajuan informasi tambahan yang tidak tepat waktu akan
mengakibatkan ditolaknya Usulan. Bilamana perubahan rancangan diusulkan, informasi
tambahan harus termasuk hasil investigasi lapangan dan survei, rancangan dan perhitungan
serta lembar perubahan denah yang diperlukan untuk mengembangkan perubahan-
perubahan rancangan.

1 -89
EINRIP General Specification
Divisi 1 - Umum

a) Direksi Pekerjaan akan menetapkan jika Usulan memenuhi syarat untuk


pertimbangan dan evaluasi. Direksi Pekerjaan dapat menolak setiap Usulan yang
memerlukan waktu dan biaya yang berlebihan untuk peninjauan, evaluasi, atau
investigasinya. Direksi Pekerjaan dapat menolak usulan yang tidak konsisten dengan
rancangan Pemilik dan kriteria untuk proyek.

b) UPRN, apakah disetujui Pemilik atau tidak, hanya digunakan pada Kontrak yang
sedang berjalan yang dirujuk dalam Usulan dan menjadi milik dari Pemilik. Usulan
tidak diperkenankan adanya batasan-batasan yang dikenakan oleh Kontraktor dalam
penggunaan atau penyingkapannya. Pemilik berhak untuk menggunakan,
menduplikasi dan menyingkap seluruh atau sebagian data yang diperlukan untuk
pemanfaatan dari Usulan. Pemilik mempertahankan haknya untuk menggunakan
setiap Usulan yang disetujui atau bagian daripadanya untuk proyek-proyek lain tanpa
kewajiban apapun terhadap Kontraktor. Ketentuan ini tunduk kepada hak-hak yang
disediakan oleh hukum dengan memperhatikan bahan-bahan atau proses-proses yang
dipatenkan.

c) Jika Pemilik telah mempertimbangkan revisi-revisi terhadap Kontrak atau telah


menyetujui perubahan-perubahan dalam Kontrak yang selanjutnya diusulkan dalam
UPRN, Direksi Pekerjaan akan menolak Usulan tersebut dan dapat memproses untuk
melaksanakan perubahan ini tanpa kewajiban apapun terhadap Kontrakor.

d) Kontraktor tidak boleh menuntut tagihan kepada Pemilik untuk tambahan biaya atau
keterlambatan yang diakibatkan oleh penolakan atau penerimaan UPRN yang tidak
tepat waktu. Biaya-biaya ini termasuk tetapi tidak terbatas pada : biaya
pengembangan, kehilangan keuntungan yang diantisipasi, biaya meningkatnya bahan
atau pekerja, atau jawaban yang tidak tepat waktu.

e) Usulan harus ditolak jika opsi yang sama telah disediakan dalam Kontrak.

f) Usulan yang hanya mengurangi atau menghapus mata pembayaran harus ditolak.

g) Penghematan biaya dan manfaat lain yang ditimbulkan oleh Usulan harus cukup
untuk menjamin peninjauan dan pemrosesan, sebagaimana yang ditetapkan oleh
Direksi Pekerjaan.

h) Daerah Milik Jalan tidak dapat dijadikan bagian dari UPRN untuk menghilangkan
pentahapan dalam suatu proyek.

i) UPRN yang mengubah rancangan suatu struktur dapat dipertimbangkan oleh Direksi
Pekerjaan, jika rancangan memenuhi kondisi-kondisi berikut ini :

i) Rancangan tidak boleh mencakup pengalihan lalu lintas ke jalan kecil atau
jalan lokal sehingga menjadi lebih melebar dari rencana awal, kecuali jika
disetujui terlebih dahulu oleh instansi setempat yang terkena.

ii) Rancangan mempunyai potongan tipikal yang sama dengan rencana awal.

iii) Rancangan memenuhi atau melampaui manfaat dari penanganan konstruksi


atau rencana pentahapan lalu lintas yang ditunjukkan dalam rencana awal.

iv) Rancangan memenuhi atau melampaui semua komitmen lingkungan dan


memenuhi ketentuan-ketentuan dari Kontrak asli.

v) Rancangan tidak boleh meningkatkan dampak lingkungan melampaui yang


terdapat dalam Kontrak asli.

1 -90
EINRIP General Specification
Divisi 1 - Umum

vi) Rancangan memenuhi dan melampaui kebebasan vertikal atau horisontal dan
ketentuan-ketentuan hidrolik yang didtunjukkan dalam rencana awal.

vii) Rancangan mempunyai keluwesan yang sama atau lebih besar seperti
rancangan asli untuk mengakomodir pelebaran di kemudian hari.

viii) Rancangan tidak boleh mengubah lokasi garis as (centerline) dari elemen-
elemen bangunan bawah, tanpa menunjukkan manfaat yang berarti terhadap
rencana asli.

ix) Rancangan tidak boleh mengubah kelandaian atau elevasi dari permukaan
akhir, tanpa menunjukkan manfaat yang berarti terhadap rencana asli.

x) Rancangan harus sesuai dengan rencana pengembangan koridor mendatang,


arsitektur, aesthetik dan ketentuan-ketentuan perkerasan, jika digunakan.

xi) Rancangan tidak boleh memberikan dampak yang kurang baik terhadap
Inspeksi Jembatan Pemilik, pemeliharaan atau biaya jangka panjang atau
pengoperasian lainnya.

xii) Rancangan harus memenuhi semua standar dan kebijaksanaan Pemilik.

xiii) Rancangan harus mencakup semua tambahan biaya dan koordinasi yang
diperlukan untuk merelokasi utilitas.

xiv) Rancangan struktur utama yang disediakan oleh Kontraktor harus termasuk
peninjauan rencana dan pemeriksaan rancangan yang independen oleh seorang
Insinyur Profesional dan dipekerjakan oleh perusahaan selain dari engineer-of-
record. Peninjauan rancangan ini harus dilaksanakan tanpa adanya tambahan
biaya kepada Pemilik dan harus termasuk dalam biaya rekayasa Kontraktor.

xv) Kontraktor harus menyediakan untuk Pemilik semua perhitungan rancangan,


perhitungan pemeriksaan rancangan yang independen, suatu paket penilaian
untuk tiap jembatan yang disiapakan sesuai dengan Manual Penilaian
Jembatan Pemilik yang berlaku, dan suatu catatan tentang perhitungan
kuantitas untuk masing-masing struktur.

j) Direksi Pekerjaan akan menolak semua atau setiap bagian dari rancangan atau
konstruksi pekerjaan yang dilaksanakan menurut UPRN yang telah disetujui jika
hasil yang diperoleh tidak dapat diterima. Direksi Pekerjaan akan memerintahkan
pembuangan pekerjaan semacam ini dan memerlukan konstruksi yang dilaksanakan
menurut ketentuan-ketentuan Kontrak asli tanpa penggantian untuk pekerjaan yang
telah dilaksanakan menurut usulan, atau untuk pembuangan tersebut.

Jika rancangan struktur UPRN memenuhi ketentuan-ketentuan ini dan lainnya,


Pemilik dapat, menurut pendapatnya sendiri, menerima atau menolak usulan
tersebut.

1.20.4 DASAR PEMBAYARAN

Jika UPRN diterima, Kontrak Variasi harus mengesahkan perubahan-perubahan dan


pembaya ran. Penggantian biaya harus dilakukan sebagi berikut :

1.20.4.1 Perubahan harus dijadikan satu dalam Kontrak dengan perubahan dalam kuantitas dari
mata pembayaran yang terdapat dalam penawaran, harga satuan mata pembayaran baru

1 -91
EINRIP General Specification
Divisi 1 - Umum

yang disepakati, lump sum atau setiap kombinasi, sebagaimana yang sesuai, dalam
Kontrak. Kecuali jika terdapat perbedaan kondisi di lapangan, Kontraktor tidak boleh
menerima kompensasi tambahan untuk kuantitas yang melampaui, kesalahan rancangan,
survei tambahan, investigasi geoteknik, mata pembayaran tambahan atau kenaikan biaya
lainnya yang tidak dijumpai dalam UPRN yang diterima, kecuali jika disetujui lain oleh
Direksi Pekerjaan.

1.20.4.2 Pembayaran insentif harus dihitung sebagai berikut :

a) (biaya bruto pekerjaan yang dihapus) - (biaya bruto pekerjaan tambah) =


(penghematan bruto)

b) (penghematan bruto) - (biaya rekayasa Kontraktor) - (biaya rekayasa Pemilik) =


(penghematan netto)

c) Setiap penghematan netto sama atau kurang dari Rp 50.000.000 dapat diambil oleh
Kontraktor.

d) Jika penghematan netto lebih besar dari Rp 50,000,000 dan selanjutnya jumlah yang
diatas Rp 50.000.000 harus dibagi rata dengan Pemilik dan dihitung sebagai berikut:

 (penghematan bruto) - Rp 50.000.000 = penghematan yang dibagi

 Jumlah insentif Kontraktor = (penghematan yang dibagi) /2 + Rp 50,000,000

e) Biaya rekayasa Kontraktor hanya akan diganti jika di luar biaya konsultan yang
dibuktikan dengan tagihan-tagihan yang disahkan. Biaya rekayasa Pemilik haruslah
biaya aktual konsultan yang ditagihkan kepada Pemilik dan biaya personil pekerja
luar biasa dalam pekerjaan terkait. Biaya pekerja ini harus dihitung dalam jumlah
yang tetap dalam satuan Rupiah per jam per pekerja. Personil proyek yang ditunjuk
untuk kantor lapangan atau yang bekerja pada proyek dengan dasar regular tidak
boleh dimasukkan dalam biaya dari bagian Pemilik.

1.20.5 PADA SAAT PEKERJAAN RANCANGAN UPRN SELESAI

Pada saat pekerjaan rancangan UPRN selesai, Kontraktor harus menyediakan kepada
Direksi Pekerjaan setiap tambahan dokumentasi seperti survei, laporan geoteknik,
dokumentasi atau perhitungan dan gambar kerja yang diperlukan untuk menyelesaikan
pekerjaan, dan Denah Terlaksana yang menunjukkan pekerjaan UPRN.

1 -92