Anda di halaman 1dari 3

REKAPITULASI RAB Sched

REKAPITULASI
PEKERJAAN : PEMBANGUNAN GEDUNG ASRAMA TARUNI POLITEKNIK PELAYARAN SURABAYA
LOKASI : GUNUNG ANYAR, SURABAYA
MINGGU KE : 1 ( Satu )
TANGGAL : 31 Maret - 06 April 2022

NO URAIAN PEKERJAAN TOTAL BIAYA (Rp)

I. PEKERJAAN PERSIAPAN 112.755.766,504

II. PEKERJAAN LT.1


STRUKTUR BAWAH 677.401.759,829
STRUKTUR ATAS LT.1 624.246.438,589

III. PEKERJAAN LT.2


STRUKTUR ATAS LT.2 544.854.501,456
ARSITEKTUR LT.2 624.846.301,242
MEKANIKAL , ELEKTRIKAL DAN PLUMBING LT.2 118.489.985,066

IV. PEKERJAAN LT.3


STRUKTUR ATAS LT.3 294.702.729,149
ARSITEKTUR LT.3 624.846.301,242
MEKANIKAL , ELEKTRIKAL DAN PLUMBING SD LT.3 219.755.393,263

3.841.899.176,34
384.189.917,634
4.226.089.093,974
4.226.000.000