Divisi : Struktur
Jenis : Baja Tulangan U24 Polos
No Item : 7.3.(1)
Satuan : kg
SKETSA
Tulangan Dowel
0+300 - 0+643 KI 32.00 0.45 10.00 69.00 7,800.00 1,946.82 Segmen 1
0+300 - 0+643 KA 32.00 0.45 10.00 69.00 7,800.00 1,946.82 Segmen 1
halaman 1 / 364
No. Lokasi Dia Panjang Jumlah per Jumlah BJ Vol Keterangan
STA Jalur (mm) Tulangan Segmen Segmen (kg/m3) (kg)
1 2 3 4 5 6 7 8 9 10
Tulangan Tiebar
0+300 - 0+643 Ki/Ka 16.00 0.50 9.00 69.00 7,800.00 486.71 Segmen 1
6+200 - 6+900 Ki/Ka 16.00 0.50 9.00 140.00 7,800.00 987.52 Segmen 2
TOTAL 26,994.65
Tulangan Wiremesh
20+425 - 20+475 KI M8 5.45 13.64 10.00 743.22 Segmen 1
20+425 - 20+475 KA M8 5.45 13.64 10.00 743.22 Segmen 1
TOTAL 2,972.89
Tulangan Dudukan Wiremesh
0+300 0 0+643 KI 8.00 0.74 25.00 69.00 7,800.00 500.22 Segmen 1
0+300 - 0+643 KA 8.00 0.74 25.00 69.00 7,800.00 500.22 Segmen 1
halaman 2 / 364
PEKERJAAN PERENCANAAN TEKNIS (DED)
: Preservasi Jalan Serdang - Bojonegara - Merak
LEMBAR PERHITUNGAN KUANTITAS
Data Perhitungan :
SALURAN SAMPING - OPRIT A1 : Panjang L1 = 50.00 M
STA. AWAL 0 + 000 Luasan A1 = 1.49 M2
STA. AKHIR 0 + 050
Volume Segmen :
- Oprit A1 = L1 x A1 x N1
= 50.00 x 1.49 x 2 = 150.00 M3
- Oprit A2 = L2 x A2 x N2
= 100.00 x 1.49 x 2 = 299.00 M3
Data Perhitungan :
SALURAN SAMPING Lokasi 1 2
STA. AWAL 0+000 0+120
STA. AKHIR 0+050 0+230
Data Perhitungan :
SALURAN SAMPING
PEKERJAAN PERENCANAAN TEKNIS (DED)
: Preservasi Jalan Serdang - Bojonegara - Merak
LEMBAR PERHITUNGAN KUANTITAS
Data Perhitungan :
TEMBOK PENAHAN STA. 0+000 0+100 0+000 0+100
(INTERSECTION JALAN LOKAL DI STA. 0+050)
T 0.10 0.10 0.10 0.10
H2 1.00 1.00 1.00 1.00
B = Lebar Slope
VOL. 12.50 17.50
Data Perhitungan :
OPRIT JEMBATAN
STA. LUASAN LUAS RATA PANJANG VOLUME
M2 M2 M M3
0+000 0+050 0+130 0+230
0 + 000
0 + 025
0 + 050
0 + 075
OPRIT A1 JEMBATAN OPRIT A2
0 + 093
0 + 193
0 + 200
0 + 225
0 + 250
0 + 275
0 + 300
0 + 325
*) Luasan didapat dari bidang gambar cross section auto desk land
pada gambar rencana jembatan
Total Volume : - M3
Data Perhitungan :
H2
H3
W
Volume Segmen :
A1 = L x w x H1
= 15.20 x 8.20 x 2.00 = 250.00 m3
A2 = L x w x H1
= 15.20 x 8.20 x 2.00 = 250.00 m3
L
Total Volume : 500.00 m3
Data Perhitungan :
H2
H3
W Volume Segmen :
A1 = L x w x H2
= 15.20 x 8.20 x 1.30 = 163.00 m3
A2 = L x w x H2
= 15.20 x 8.20 x 1.80 = 225.00 m3
L
Total Volume : 388.00 m3
Data Perhitungan :
H2
H3
W Volume Segmen :
A1 = L x w x H3
= 15.20 x 8.20 x 0.00 = 0.00 m3
A2 = L x w x H3
= 15.20 x 8.20 x 0.00 = 0.00 m3
L
Total Volume : 0.00 m3
Data Perhitungan :
Lokasi 1 2 3 4 5
B
L
T
L
L
Data Perhitungan :
OPRIT JEMBATAN
STA. LUASAN LUAS RATA PANJANG VOLUME
M2 M2 M M3
0+000 0+050 0+130 0+230
0 + 000
0 + 025
0 + 050 9.95 9.95 25.00 248.75
0 + 075 9.95 9.95 17.83 177.39
OPRIT A1 JEMBATAN OPRIT A2 0 + 093 9.95
1,368.00
*) Luasan didapat dari bidang gambar cross section auto desk land
pada gambar rencana jembatan
Data Perhitungan :
OPRIT JEMBATAN
STA. LUASAN LUAS RATA PANJANG VOLUME
M2 M2 M M3
0+000 0+050 0+130 0+230
0 + 000
0 + 025
0 + 050 5.50 25.85 25.00 646.25
0 + 075 46.20 56.10 17.83 1,000.15
OPRIT A1 JEMBATAN OPRIT A2 0 + 093 66.00
INTERSECTION
0 + 000 4.00 4.00 100.00 400.00
0 + 100 4.00
4,850.00
*) Luasan didapat dari bidang gambar cross section auto desk land
pada gambar rencana jembatan
Data Perhitungan :
ABUTMEN A1 + A2 ABUTMEN
B1 = 2.80 m
B2 = 2.20 m
H1 = 5.90 m
B1 B2 H2 = 4.50 m
L = 11.00 m
H2 Volume :
Va = B1 x H1 x L x 2
H1 = 2.80 x 5.90 x 11.00 x 2 = 364.00 m3
H1
Vb = 0.5 x ( H2 + H1 ) x B2 x L x 2
= 5.20 x 2.20 x 11.00 x 2 = 252.00 m3
Data Perhitungan :
OPRIT JEMBATAN
STA. LEBAR LBR RATA-2 PANJANG VOLUME
M M M M2
0+000 0+050 0+130 0+230
0 + 000
0 + 025
0 + 050 9.00 9.00 25.00 225.00
0 + 075 9.00 9.00 17.83 160.45
OPRIT A1 JEMBATAN OPRIT A2 0 + 093 9.00
OPRIT A1 JEMBATAN OPRIT A2
INTERSECTION
0 + 000 4.00 4.00 100.00 400.00
0 + 100 4.00
TOTAL 1,975.00
Data dimensi :
0+000 0+050 0+130 0+230 - OPRIT A1 : PANJANG = 50.00 M
STA. AWAL 0 + 000 LEBAR = 10.00 M
STA. AKHIR 0 + 050
Volume Segmen :
- Oprit A1 = P x L
= 500.0 M2
- Oprit A2 = P x L
= 1,000.0 M2
STA. 0+000 0+025 0+050 0+093 0+193 0+200 0+225 0+250 0+275 0+300 0+325
KIRI
LEBAR
TEBAL
VOLUME 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
STA. 0+000 0+025 0+050 0+093 0+193 0+200 0+225 0+250 0+275 0+300 0+325
KANAN
LEBAR
TEBAL
VOLUME 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
STA. 0+000 0+050 0+125 0+171 0+182 0+225 0+332 0+332 0+332 0+332 0+332
KIRI
LEBAR
TEBAL
VOLUME 0.00 0.00 0.00 7.18 0.00 0.00 0.00 0.00 0.00 0.00
STA. 0+000 0+050 0+125 0+171 0+182 0+225 0+332 0+332 0+332 0+332 0+332
KANAN
LEBAR
TEBAL
VOLUME 0.00 0.00 0.00 7.18 0.00 0.00
TOTAL VOLUME AC-BC (M3) -
TOTAL VOLUME AC-BC (TON) BERAT JENIS AC-BC = 2,35 T/M3 > 2.35 x - -
PEKERJAAN PERENCANAAN TEKNIS (DED)
: Preservasi Jalan Serdang - Bojonegara - Merak
LEMBAR PERHITUNGAN KUANTITAS
-
PEKERJAAN PERENCANAAN TEKNIS (DED)
: Preservasi Jalan Serdang - Bojonegara - Merak
LEMBAR PERHITUNGAN KUANTITAS
Data Perhitungan :
LANTAI JEMBATAN B1 = 0.00 m T1 = 0.26 m
B2 = 10.00 m T2 = 0.10 m
L = 80.00 m
B T1
T2 A Volume Segmen :
A = 0.50 x B1 x T2 x L x 2
B1 = 0.50 x 0.00 x 0.10 x 80.00 x 2 = - m3
B = B2 x T1 x L x 2
B2
= 10.00 x 0.26 x 80.00 x 2 = 408.00 m3
B2
Volume : 408.00 m3
Total Volume : 429.00 m3 Faktor = 5%
PEKERJAAN PERENCANAAN TEKNIS (DED)
: Preservasi Jalan Serdang - Bojonegara - Merak
LEMBAR PERHITUNGAN KUANTITAS
Volume Segmen :
L V = B x H x L x N
= 0.80 x 0.35 x 80.00 x 2 = 45.00 m3
B
LANTAI JEMBATAN
Data Perhitungan :
ABUTMEN A1 B1 = 8.00 m H1 = 1.80 m H9 = m
B2 = 2.40 m H2 = 0.50 m
B4 B5 B6 B7 B3 = 0.80 m H3 = 1.60 m B2' = 1.30 m
B4 = 0.40 m H4 = 4.60 m
H5 E B5 = 2.80 m H5 = 0.70 m
0.40
0.50
I B6 = 1.40 m H6 = 6.20 m
B7 = 0.40 m H7 = 5.56 m L1 = 10.60 m
H7 B56= 5.00 m H8 = 7.40 m L2 = 8.60 m
D G Volume Segmen
H4 H6 F
H8 A = B1 x H1 x L1
= 8.00 x 1.80 x 10.60 = 152.64 m3
B3 B =( B1 + B2' )/ 2 x H2 x L1
B2
= 4.65 x 0.50 x 10.60 = 24.65 m3
H3 C C = B2 x H3 x L1
H = 2.40 x 1.60 x 10.60 = 40.70 m3
H2 B D = H4 x B3 x L1
H1 A = 4.60 x 0.80 x 10.60 = 39.01 m3
E = B4 x H5 x L1
B1 = 0.40 x 0.70 x 10.60 = 2.97 m3
F =( H6 + H8 )/ 2 x B5 x B7 x 2
= 6.80 x 2.80 x 0.40 x 2 = 15.23 m3
G =( H7 + H8 )/ 2 x B6 x B7 x 2
= 6.48 x 1.40 x 0.40 x 2 = 7.26 m3
I =( 0.40+0.50 )/ 2 x 0.1 x B56 x 2
= 0.475 x 0.10 x 5.00 x 2 = 0.48 m3
H =( 0.3 x 0.3 )/ 2 x H6B5 x 2
= 0.30 x 9.00 x 2.00 = 5.40 m3
Volume : 288.40 m3
Faktor = 5% Total Volume : 303.00 m3
Data Perhitungan :
ABUTMEN A2 B1 = 8.00 m H1 = 1.80 m H9 = m
B2 = 2.40 m H2 = 0.50 m
B4 B5 B6 B7 B3 = 0.80 m H3 = 1.60 m B2' = 1.30 m
B4 = 0.40 m H4 = 4.60 m
H5 E B5 = 2.80 m H5 = 0.70 m
0.40
0.50
I B6 = 1.40 m H6 = 6.20 m
B7 = 0.40 m H7 = 5.56 m L1 = 10.60 m
H7 B56= 5.00 m H8 = 7.40 m L2 = 8.60 m
D G Volume Segmen
H4 H6 F
H8 A = B1 x H1 x L1
= 8.00 x 1.80 x 10.60 = 152.64 m3
B3 B =( B1 + B2' )/ 2 x H2 x L1
B2
= 4.65 x 0.50 x 10.60 = 24.65 m3
H3 C C = B2 x H3 x L1
H = 2.40 x 1.60 x 10.60 = 40.70 m3
H2 B D = H4 x B3 x L1
H1 A = 4.60 x 0.80 x 10.60 = 39.01 m3
E = B4 x H5 x L1
B1 = 0.40 x 0.70 x 10.60 = 2.97 m3
F =( H6 + H8 )/ 2 x B5 x B7 x 2
= 6.80 x 2.80 x 0.40 x 2 = 15.23 m3
G =( H7 + H8 )/ 2 x B6 x B7 x 2
= 6.48 x 1.40 x 0.40 x 2 = 7.26 m3
I =( 0.40+0.50 )/ 2 x 0.1 x B56 x 2
= 0.475 x 0.10 x 5.00 x 2 = 0.48 m3
H =( 0.3 x 0.3 )/ 2 x H6B5 x 2
= 0.30 x 9.00 x 2.00 = 5.40 m3
Volume : 288.40 m3
Data Perhitungan :
PELAT INJAK B = 5.00 m
L = 7.00 m
B T = 0.30 m
L
N = 2
PELAT INJAK T
Volume Segmen :
PADA ABUTMEN A1
A1 = B x T x L x N
= 5.00 x 0.30 x 7.00 x 2 = 21.00 m3
PADA ABUTMEN A2
A2 = B x T x L x N
= 5.00 x 0.30 x 7.00 x 2 = 21.00 m3
Volume : 42.00 m3
Total Volume : 45.00 m3 Faktor = 5%
Data Perhitungan :
TROTOAR / SIDEWALK DIDEPAN LONENG TROTOAR
B = 0.80 m
L = 10.86 m
B T = 0.30 m
N = 2 KIRI / KANAN
Volume Segmen :
L V1 = B x T x L x N
= 0.80 x 0.30 x 10.86 x 2 = 6.00 m3
B
LANTAI JEMBATAN
Total Volume : 6.00 m3
Volume Segmen :
PLAT INJAK A1&A2
V1 = B x T x L x N
= 5.20 x 0.10 x 7.20 x 2 = 8.00 m3
L
SALURAN
V3 = B x T x L x N
= 1.00 x 0.10 x 160.00 x 2 = 32.00 m3
B
B
1. LANTAI JEMBATAN
W = 26,400.00 Kg
3. ABUTMEN A1
W = 19,358.50 Kg
4. ABUTMEN A2
W = 19,358.50 Kg
OPRIT A1 JEMBATAN OPRIT A2
5. PELAT INJAK A1 + A2
W = 1,650.00 Kg
6 FOOT PLAT
W = 62,376.16 Kg
7 WING WALL
W = 27,452.60 Kg
NOMOR PEKERJAAN : 0
NAMA PEKERJAAN : DINDING PENAHAN TANAH SEGMENTAL
SATUAN : M2
NAMA JEMBATAN : : Banten
Data Perhitungan :
TOTAL 498.00
TOTAL KIRI+KANAN 996.00
Data Perhitungan :
n1 n2 Total Lp
Struktur Lpd (m) Koefisien Lp (m)
(lajur) (lajur) (m)
Abutmen A1 4 7 26.00 1 26.00 728.00
Abutmen A2 4 7 26.00 1 26.00 728.00
TOTAL 1,456.00
PEKERJAAN PERENCANAAN TEKNIS (DED)
: Preservasi Jalan Serdang - Bojonegara - Merak
LEMBAR PERHITUNGAN KUANTITAS
Data Perhitungan :
PARAPET WALL ( TEMBOK SEDADA ) ABUTMEN A1 ABUTMEN A2
L = 6.00 m L = 6.00 m
L W
H = 1.00 m H = 1.00 m
W = 0.50 m W = 0.50 m
H
N = 2 N = 2
Volume Segmen :
V1 = L x W x H x N
= 6.00 x 0.50 x 1.00 x 2 = 6.00 m3
V2 = L x W x H x N
= 6.00 x 0.50 x 1.00 x 2 = 6.00 m3
Data Perhitungan :
TANGGA INSPEKSI B1 = 0.50 m H1 = 0.80 m H5 = 0.20 m w1 = 0.15 m
B4
B2 = 1.00 m H2 = 0.20 m H6 = 0.50 m w2 = 0.80 m
B3 = 0.30 m H3 = 0.25 m w3 = 1.10 m
B4 = 0.30 m H4 = 0.15 m L = 12.00 m
F H6
N = 32.00
D
Volume Segmen :
B3 A = B1 x H1 x w3
= 0.50 x 0.80 x 1.10 = 0.44 m3
E
C B = B2 x H2 x w3
L
H3
H2 B
B3
E
C
L
H3 = 1.00 x 0.20 x 1.10 = 0.22 m3
H2 B C = L x H4 x w3
B2 = 12.00 x 0.15 x 1.10 = 1.98 m3
H1 A D = L x H5 x w1 x 2
w3 = 12.00 x 0.20 x 0.15 x 2.00 = 0.72 m3
w1 w2
B1 E = 0.50 x H3 x B3 x w2 x N
= 0.50 x 0.25 x 0.30 x 0.80 x 32.00 = 0.96 m3
F = H6 x B4 x w3
= 0.50 x 0.30 x 1.10 = 0.17 m3
Data Perhitungan :
PASANGAN BATU TEMBOK PENAHAN STA. 0+000 0+055 0+000 0+058
(INTERSECTION DGN JALAN LOKAL DI STA. 0+050) B1 0.50 0.50 0.50 0.60
B2 0.54 0.54 0.54 0.54
B1
B3 1.54 1.54 1.54 1.54
H1 0.50 0.50 0.50 0.50
H2 1.00 1.00 1.00 1.00
H2
B
JARAK 55.00 58.02
H2
B VOL. 70.95 76.30
H1 A
STA. 0+093 0+193
B3 B 12.50 17.50
L 10.00 10.00
PASANGAN BATU SLOPE PROTECTION T 0.30 0.30
(DI ABUTMEN BAWAH JEMBATAN)
Data Perhitungan :
ABUTMEN A1 = 9.00 m
Expansion Joint
ABUTMEN A2 = 9.00 m
L Lantai Jembatan
L Lantai Jembatan
Data Perhitungan :
ABUTMEN A1 - A2 L1 = m KANAN
ABUTMEN A1 - A2 L2 = m KIRI
Total Kuantitas : = 0.00 M
Data Perhitungan :
N 5 N 4 N 2
VOL. 15.00 VOL. 60.00 VOL. 60.00
N 2 N 2
VOL. 3.00 VOL. 2.00
L1
LANTAI JEMBATAN
L1 dr ke n1 n2 L1 L2 QTY
KANAN A1 A2 34.00 1 100.00 1.50 51.00 m
LANTAI JEMBATAN KIRI A1 A2 34.00 1 100.00 1.50 51.00 m
L2
TOTAL 102.00 m
NOMOR PEKERJAAN :
NAMA PEKERJAAN :
SATUAN : Kuantitas : - 0
NAMA JEMBATAN : : Banten
Volume Segmen :
OPRIT A1 JEMBATAN OPRIT A2
- Vol.1 = P x L = 34.00 M2 KIRI
- Vol.2 = P x L = 34.00 M2 KANAN
- Vol.3 = P x L = 68.00 M2 TENGAH
Data dimensi :
LANTAI JEMBATAN - Jembatan
STA. A1 0 + 000
0+000 0+050 0+130 0+280 STA. A2 0 + 280
Data Dimensi :
0+000 0+050 0+130 0+280
QTY 0+050 0+090 0+193 0+325
KIRI 1.00 1.00 2.00
KANAN 1.00 1.00 2.00
OPRIT A1 JEMBATAN OPRIT A2 JMLH 2.00 1.00 1.00 4.00
QTY
KIRI
KANAN
JMLH 0.00
Data Dimensi :
0+000 0+050 0+130 0+280 QTY 0+050 0+090 0+193 0+325
KIRI 1.00 1.00 1.00
KANAN 1.00 1.00 1.00
JMLH 2.00 1.00 1.00 2.00
OPRIT A1 JEMBATAN OPRIT A2
QTY
KIRI
KANAN
JMLH 0.00
Data Dimensi :
0+000 0+050 0+130 0+280 Lokasi 1 2 3
STA. AWAL 0+050 0+193 0+050
STA. AKHIR 0+093 0+275 (Jl. Lokal)
Data Dimensi :
0+000 0+050 0+130 0+280 Lokasi 1 2 3
STA. AWAL 0+050 0+193 0+050
STA. AKHIR 0+093 0+275 (Jl. Lokal)
NOMOR PEKERJAAN :
NAMA PEKERJAAN :
SATUAN :
NAMA JEMBATAN : : Banten
Data dimensi :
LANTAI JEMBATAN - Jembatan
STA. A1 0 + 000
0+000 0+050 0+130 0+280 STA. A2 0 + 280
Pagu
LINGKUP PEKERJAAN Total
Harga
No. Mata Harga Satuan KUANTITAS
Uraian Satuan
Pembayaran (Rupiah) TOTAL
Pemeliharaan Rutin Pemeliharaan Rutin
Rekontruksi Jalan Rehabilitasi Minor Prevervasi Jembatan (Rupiah)
Jalan Jembatan
a b c e d f =d x e
DIVISI 1. UMUM
1.2 Mobilisasi LS 160,300,000.00 1.00 1.00 160,300,000.00
1.8.(1) Manajemen dan Keselamatan Lalu Lintas LS 103,400,000.00 1.00 1.00 103,400,000.00
1.17.(1a) Pengujian pH Buah 50,000.00 6.00 6.00 300,000.00
1.17.(1b) Pengujian Oksigen Terlarut (DO) Buah 50,000.00 6.00 6.00 300,000.00
1.17.(1c) Pengujian Zat Padat Terlarut (TDS) Buah 50,000.00 6.00 6.00 300,000.00
1.17.(1d) Pengujian Zat Tersuspensi (TSS) Buah 50,000.00 6.00 6.00 300,000.00
1.17.(1e) Pengujian Biological Oxygen Demand (BOD) Buah 50,000.00 6.00 6.00 300,000.00
1.17.(1f) Pengujian Chemical Oxygen Demand (COD) Buah 50,000.00 6.00 6.00 300,000.00
1.17.(1g) Pengujian Coliform Buah 100,000.00 6.00 6.00 600,000.00
1.17.(1h) Pengujian E. Coli Buah 50,000.00 6.00 6.00 300,000.00
1.17.(1i) Pengujian Destruksi Cu, Pb, Cd, Ni, Fe, Zn, Ag, Co, Mn Buah 400,000.00 6.00 6.00 2,400,000.00
1.17.(1j) Pengujian Temperatur (Suhu) Buah 50,000.00 6.00 6.00 300,000.00
1.17.(2a) Pengujian Vibrasi Lingkungan untuk Kenyamanan dan Kesehatan Buah 1,000,000.00 6.00 6.00 6,000,000.00
1.17.(2b) Pengujian tingkat getaran kendaraan bermotor Buah 50,000.00 6.00 6.00 300,000.00
1.17.(3a) Pengujian NoX Buah 200,000.00 6.00 6.00 1,200,000.00
1.17.(3b) Pengujian Sulfurdioksida (SO2) Buah 150,000.00 6.00 6.00 900,000.00
1.17.(3c) Pengujian Karbondioksida (CO2) Buah 150,000.00 6.00 6.00 900,000.00
1.17.(3d) Pengujian Hidro Carbon (HC)-CH4 Buah 150,000.00 6.00 6.00 900,000.00
1.17.(3f) Pengujian Total Partikulat (TSP) - Debu Buah 500,000.00 6.00 6.00 3,000,000.00
1.17.(3g) Pengujian Timah Hitam (Pb) Buah 50,000.00 6.00 6.00 300,000.00
1.17.(3h) Pengujian Parameter Udara Emisi dan Ambien lainnya : ………….. Buah 50,000.00 6.00 6.00 300,000.00
1.19 Keselamatan dan Kesehatan Kerja LS 174,900,000.00 1.00 1.00 174,900,000.00
1.21 Manajemen Mutu LS 141,400,000.00 1.00 1.00 141,400,000.00
Jumlah Harga Pekerjaan DIVISI 1 (masuk pada Rekapitulasi Perkiraan Harga Pekerjaan) 599,200,000.00
DIVISI 2. DRAINASE
2.1.(1) Galian untuk Selokan Drainase dan Saluran Air M3 41,921.47 92.73 92.73 3,887,377.79
2.2.(1) Pasangan Batu dengan Mortar M3 817,427.78 48.22 48.22 39,416,367.42
2.3.(1) Gorong-gorong Pipa Beton Tanpa Tulangan diameter dalam 20 cm M1 186,664.65 20.00 380.00 400.00 74,665,860.97
2.3.(15) Gorong-gorong Kotak Beton Bertulang, ukuran dalam 200 cm x 100 cm M1 5,334,761.58 87.00 87.00 464,124,257.59
2.3.(21) Gorong-gorong Kotak Beton Bertulang, ukuran dalam 500 cm x 250 cm M1 54,988,868.56 12.00 12.00 659,866,422.72
2.3.(26) Saluran berbentuk U Tipe DS 3 M1 1,101,010.00 6,958.00 6,958.00 7,660,827,580.00
2.3.(27) Saluran berbentuk U Tipe DS 3a (dengan tutup) M1 1,299,000.00 250.00 250.00 324,750,000.00
2.3.(29) Saluran berbentuk U Tipe DS 4a (dengan tutup) M1 1,472,819.00 1,280.00 1,280.00 1,885,208,320.00
Jumlah Harga Pekerjaan DIVISI 2 (masuk pada Rekapitulasi Perkiraan Harga Pekerjaan) 11,112,746,186.50
###
DIVISI 3. PEKERJAAN TANAH DAN GEOSINTETIK
3.1.(1) Galian Biasa M3 41,921.47 5,168.70 5,168.70 216,679,495.37
3.1.(7) Galian Perkerasan Beraspal dengan Cold Milling Machine M3 477,210.92 13.95 5.69 19.64 9,372,422.55
3.1.(10). Galian Perkerasan Beton M3 382,562.08 125.00 125.00 47,820,259.94
3.2.(1a) Timbunan Biasa dari sumber galian M3 264,138.09 642.00 642.00 169,576,656.25
3.2.(2a) Timbunan Pilihan dari sumber galian M3 288,972.02 150.00 150.00 43,345,803.16
3.3.(1) Penyiapan Badan Jalan M2 10,645.48 12,148.00 12,148.00 129,321,264.23
3.4.(2) Pemotongan Pohon Pilihan diameter 15 – 30 cm buah 122,977.93 10.00 10.00 1,229,779.32
3.4.(3) Pemotongan Pohon Pilihan diameter > 30 – 50 cm buah 395,981.21 10.00 10.00 3,959,812.09
3.4.(4) Pemotongan Pohon Pilihan diameter > 50 – 75 cm buah 987,045.54 10.00 10.00 9,870,455.40
3.4.(5) Pemotongan Pohon Pilihan diameter > 75 cm buah 1,632,233.46 5.00 5.00 8,161,167.31
Jumlah Harga Pekerjaan DIVISI 3 (masuk pada Rekapitulasi Perkiraan Harga Pekerjaan) 639,337,115.63
DAFTAR KUANTITAS HARGA
Pagu
LINGKUP PEKERJAAN Total
Harga
No. Mata Harga Satuan KUANTITAS
Uraian Satuan
Pembayaran (Rupiah) TOTAL
Pemeliharaan Rutin Pemeliharaan Rutin
Rekontruksi Jalan Rehabilitasi Minor Prevervasi Jembatan (Rupiah)
Jalan Jembatan
a b c e d f =d x e
Jumlah Harga Pekerjaan DIVISI 4 (masuk pada Rekapitulasi Perkiraan Harga Pekerjaan) 977,109,252.00
DAFTAR KUANTITAS HARGA
Pagu
LINGKUP PEKERJAAN Total
Harga
No. Mata Harga Satuan KUANTITAS
Uraian Satuan
Pembayaran (Rupiah) TOTAL
Pemeliharaan Rutin Pemeliharaan Rutin
Rekontruksi Jalan Rehabilitasi Minor Prevervasi Jembatan (Rupiah)
Jalan Jembatan
a b c e d f =d x e
Jumlah Harga Pekerjaan DIVISI 5 (masuk pada Rekapitulasi Perkiraan Harga Pekerjaan) 40,030,165,150.12
Jumlah Harga Pekerjaan DIVISI 6 (masuk pada Rekapitulasi Perkiraan Harga Pekerjaan) 5,844,824,085.98
DIVISI 7. STRUKTUR
7.1 (5a) Beton struktur, fc’30 MPa M3 1,608,410.80 32.76 52,691,537.74
7.1 (10) Beton, fc’10 Mpa M3 1,452,674.69 2.40 3,486,419.26
7.3 (1) Baja Tulangan Polos-BjTP 280 Kg 17,020.00 250.00 4,255,000.00
7.3 (3) Baja Tulangan Sirip BjTS 420A Kg 15,678.33 2,880.72 45,164,888.40
7.3 (8) Anyaman Kawat Yang Dilas (Welded Wire Mesh) Kg 19,463.75 500.00 9,731,875.00
7.4 (1b) Penyediaan Baja Struktur Grade 345 (kuat leleh 345 Mpa) Kg 25,000.00 402.40 10,060,000.00
DAFTAR KUANTITAS HARGA
Pagu
LINGKUP PEKERJAAN Total
Harga
No. Mata Harga Satuan KUANTITAS
Uraian Satuan
Pembayaran (Rupiah) TOTAL
Pemeliharaan Rutin Pemeliharaan Rutin
Rekontruksi Jalan Rehabilitasi Minor Prevervasi Jembatan (Rupiah)
Jalan Jembatan
a b c e d f =d x e
7.9.(1) Pasangan Batu M3 740,977.66 562.40 416,725,837.66
7.10.(1) Pasangan Batu Kosong yang Diisi Adukan M3 763,836.59 13.20 10,082,643.00
7.10.(3a) Bronjong dengan kawat yang dilapisi Galvanis M3 552,230.00 100.00 55,223,000.00
7.14.(1) Papan Nama Jembatan Buah 691,918.76 2.00 1,383,837.52
Jumlah Harga Pekerjaan DIVISI 7 (masuk pada Rekapitulasi Perkiraan Harga Pekerjaan) 608,805,038.58
Jumlah Harga Pekerjaan DIVISI 8 (masuk pada Rekapitulasi Perkiraan Harga Pekerjaan) 150,699,600.00
###
Jumlah Harga Pekerjaan DIVISI 9 (masuk pada Rekapitulasi Perkiraan Harga Pekerjaan) 1,964,831,820.45
###
###
DIVISI 10. PEKERJAAN PEMELIHARAAN KINERJA
10.1.(1) Galian pada Saluran Air atau Lereng untuk Pemeliharaan M3 41,921.47 322.22 13,507,935.65
10.1.(2) Timbunan Pilihan pada Lereng Tepi Saluran untuk Pemeliharaan M3 288,972.02 99.80 28,839,407.71
10.1.(3) Pebaikan Pasangan Batu dengan Mortar M3 740,977.66 67.30 49,867,796.72
10.1.(4) Perbaikan Lapis Fondasi Agregat Kelas A M 3
305,975.57 3.50 1,070,914.49
10.1.(5) Perbaikan Lapis Fondasi Agregat Kelas B M3 270,726.80 16.40 4,439,919.49
10.1.(6) Perbaikan Lapis Fondasi Agregat Kelas S M3 238,380.17 121.30 28,915,514.46
10.1.(7) Perbaikan dan Perataan Permukaan JalanTanah M 2
10,645.48 5,000.00 53,227,388.96
10.1.(9) Perbaikan Campuran Aspal Panas M3 3,500,000.00 0.90 3,150,000.00
10.1.(14) Perbaikan Perkerasan Beton Semen M3 1,770,900.00 73.06 129,381,954.00
10.1.(15) Perbaikan Lapis Fondasi Bawah Beton Kurus M3 1,098,099.40 24.50 26,903,435.42
10.1.(16) Perbaikan Pasangan Batu M3 740,977.66 28.40 21,043,765.63
10.1.(17) Pengecatan Kereb pada Trotoar atau Median M2 50,000.00 200.00 10,000,000.00
10.1.(18) Perbaikan Rel Pengaman M1 30,000.00 200.00 6,000,000.00
10.1.(19) Pembersihan Patok Buah 15,000.00 27.00 405,000.00
10.1.(20) Pembersihan Rambu Buah 15,000.00 74.00 1,110,000.00
10.1.(21) Pembersihan Drainase M1 20,000.00 14,530.00 290,600,000.00
10.1.(22) Pengendalian Tanaman M2 700.00 643,396.00 450,377,200.00
10.2.(1) Pemeliharaan Kinerja Jembatan Serdang bentang 7.00 m LS 5,000,000.00 1.00 5,000,000.00
10.2.(2) Pemeliharaan Kinerja Jembatan Trumix Seruni bentang 9.00 m LS 7,500,000.00 1.00 7,500,000.00
10.2.(3) Pemeliharaan Kinerja Jembatan Fly Over Seruni bentang 68.30 m LS 40,000,000.00 1.00 40,000,000.00
10.2.(4) Pemeliharaan Kinerja Jembatan Serdang Terate bentang 36.50 m LS 20,000,000.00 1.00 20,000,000.00
10.2.(5) Pemeliharaan Kinerja Jembatan Serdang Terate II Amnonim bentang 7.00 m LS 5,000,000.00 1.00 5,000,000.00
10.2.(6) Pemeliharaan Kinerja Jembatan Terate III bentang 7.00 m LS 5,000,000.00 1.00 5,000,000.00
10.2.(7) Pemeliharaan Kinerja Jembatan Grenyang bentang 8.00 m LS 5,500,000.00 1.00 5,500,000.00
10.2.(8) Pemeliharaan Kinerja Jembatan Ragas bentang 7.10 m LS 5,000,000.00 1.00 5,000,000.00
DAFTAR KUANTITAS HARGA
Pagu
LINGKUP PEKERJAAN Total
Harga
No. Mata Harga Satuan KUANTITAS
Uraian Satuan
Pembayaran (Rupiah) TOTAL
Pemeliharaan Rutin Pemeliharaan Rutin
Rekontruksi Jalan Rehabilitasi Minor Prevervasi Jembatan (Rupiah)
Jalan Jembatan
a b c e d f =d x e
10.2.(9) Pemeliharaan Kinerja Jembatan Ragas II bentang 7.00 m LS 5,000,000.00 1.00 5,000,000.00
10.2.(10) Pemeliharaan Kinerja Jembatan Pangoreng bentang 26 m LS 15,000,000.00 1.00 15,000,000.00
10.2.(11) Pemeliharaan Kinerja Jembatan Cicegah bentang 7.60 m LS 5,000,000.00 1.00 5,000,000.00
10.2.(12) Pemeliharaan Kinerja Jembatan Lebak Gede I bentang 6.00 m LS 5,000,000.00 1.00 5,000,000.00
10.2.(13) Pemeliharaan Kinerja Jembatan Lebak Gede II bentang 6.00 m LS 5,000,000.00 1.00 5,000,000.00
Jumlah Harga Pekerjaan DIVISI 10 (masuk pada Rekapitulasi Perkiraan Harga Pekerjaan) 1,246,840,232.52
JADWAL WAKTU PELAKSANAAN
Bulan I Bulan II Bulan III Bulan IV Bulan V Bulan VI Bulan VII Bulan VIII Bulan IX Bulan X Bulan XI Bulan XII Bulan XIII Bulan XIV Bulan XV Bulan XVI Bulan XVII Bulan XVIII Bulan XIX Bulan XX
No. Mata
Total Perkiraan
Uraian Satuan Ket.
Kuantitas BOBOT (%) Hari ke Hari ke Hari ke Hari ke Hari ke Hari ke Hari ke Hari ke Hari ke Hari ke Hari ke Hari ke Hari ke Hari ke Hari ke Hari ke Hari ke Hari ke Hari ke Hari ke Hari ke Hari ke Hari ke Hari ke Hari ke Hari ke Hari ke Hari ke Hari ke Hari ke Hari ke Hari ke Hari ke Hari ke Hari ke Hari ke Hari ke Hari ke Hari ke Hari ke
Pembayaran
1 - 15 16 - 30 31 - 45 46 - 60 61 - 75 76 - 90 91 - 105 106 - 120 121 - 135 136 - 150 151 - 165 166 - 180 181 - 195 196 - 210 211 - 225 226 - 240 241 - 255 256 - 270 271 -285 286 - 300 301 - 315 316 - 330 331 - 345 346 - 360 361 - 375 376 -390 391 - 405 406 -420 421 - 435 436 -450 451 - 465 466 -480 481 -495 496 -510 511 -525 526 -540 541 -555 556 -570 571 -585 586 - 600
DIVISI 1. UMUM
1.2 Mobilisasi LS 1.00 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509
1.8.(1) Manajemen dan Keselamatan Lalu Lintas LS 1.00 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509
1.17.(1a) Pengujian pH Buah 6.00 Err:509 Err:509 Err:509 Err:509
1.17.(1b) Pengujian Oksigen Terlarut (DO) Buah 6.00 Err:509 Err:509 Err:509 Err:509
1.17.(1c) Pengujian Zat Padat Terlarut (TDS) Buah 6.00 Err:509 Err:509 Err:509 Err:509
1.17.(1d) Pengujian Zat Tersuspensi (TSS) Buah 6.00 Err:509 Err:509 Err:509 Err:509
1.17.(1e) Pengujian Biological Oxygen Demand (BOD) Buah 6.00 Err:509 Err:509 Err:509 Err:509
1.17.(1f) Pengujian Chemical Oxygen Demand (COD) Buah 6.00 Err:509 Err:509 Err:509 Err:509
1.17.(1g) Pengujian Coliform Buah 6.00 Err:509 Err:509 Err:509 Err:509
1.17.(1h) Pengujian E. Coli Buah 6.00 Err:509 Err:509 Err:509 Err:509
1.17.(1i) Pengujian Destruksi Cu, Pb, Cd, Ni, Fe, Zn, Ag, Co, Mn Buah 6.00 Err:509 Err:509 Err:509 Err:509
1.17.(1j) Pengujian Temperatur (Suhu) Buah 6.00 Err:509 Err:509 Err:509 Err:509
1.17.(2a) Pengujian Vibrasi Lingkungan untuk Kenyamanan dan Kesehatan Buah 6.00 Err:509 Err:509 Err:509 Err:509
1.17.(2b) Pengujian tingkat getaran kendaraan bermotor Buah 6.00 Err:509 Err:509 Err:509 Err:509
1.17.(3a) Pengujian NoX Buah 6.00 Err:509 Err:509 Err:509 Err:509
1.17.(3b) Pengujian Sulfurdioksida (SO2) Buah 6.00 Err:509 Err:509 Err:509 Err:509
1.17.(3c) Pengujian Karbondioksida (CO2) Buah 6.00 Err:509 Err:509 Err:509 Err:509
1.17.(3d) Pengujian Hidro Carbon (HC)-CH4 Buah 6.00 Err:509 Err:509 Err:509 Err:509
1.17.(3f) Pengujian Total Partikulat (TSP) - Debu Buah 6.00 Err:509 Err:509 Err:509 Err:509
1.17.(3g) Pengujian Timah Hitam (Pb) Buah 6.00 Err:509 Err:509 Err:509 Err:509
1.17.(3h) Pengujian Parameter Udara Emisi dan Ambien lainnya : ………….. Buah 6.00 Err:509 Err:509 Err:509 Err:509
1.19 Keselamatan dan Kesehatan Kerja LS 1.00 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509
1.21 Manajemen Mutu LS 1.00 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509
DIVISI 2. DRAINASE Err:509
2.1.(1) Galian untuk Selokan Drainase dan Saluran Air M3 92.73 Err:509 Err:509 Err:509
2.2.(1) Pasangan Batu dengan Mortar M3 48.22 Err:509 Err:509
2.3.(1) Gorong-gorong Pipa Beton Tanpa Tulangan diameter dalam 20 cm M1 400.00 Err:509 Err:509 Err:509
2.3.(15) Gorong-gorong Kotak Beton Bertulang, ukuran dalam 200 cm x 100 cm M1 87.00 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509
2.3.(21) Gorong-gorong Kotak Beton Bertulang, ukuran dalam 500 cm x 250 cm M1 12.00 Err:509 Err:509 Err:509 Err:509 Err:509
2.3.(26) Saluran berbentuk U Tipe DS 3 M1 6,958.00 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509
2.3.(27) Saluran berbentuk U Tipe DS 3a (dengan tutup) M1 250.00 Err:509 Err:509 Err:509
2.3.(29) Saluran berbentuk U Tipe DS 4a (dengan tutup) M1 1,280.00 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509
DIVISI 3. PEKERJAAN TANAH DAN GEOSINTETIK Err:509
3.1.(1) Galian Biasa M 3 5,168.70 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509
3.1.(7) Galian Perkerasan Beraspal dengan Cold Milling Machine M3 19.64 Err:509 Err:509
3.1.(10). Galian Perkerasan Beton M3 125.00 Err:509 Err:509 Err:509
3.2.(1a) Timbunan Biasa dari sumber galian M3 642.00 Err:509 Err:509 Err:509 Err:509
3.2.(2a) Timbunan Pilihan dari sumber galian M3 150.00 Err:509 Err:509
3.3.(1) Penyiapan Badan Jalan M2 12,148.00 Err:509 Err:509 Err:509 Err:509 Err:509
3.4.(2) Pemotongan Pohon Pilihan diameter 15 – 30 cm buah 10.00 Err:509 Err:509
3.4.(3) Pemotongan Pohon Pilihan diameter > 30 – 50 cm buah 10.00 Err:509 Err:509
3.4.(4) Pemotongan Pohon Pilihan diameter > 50 – 75 cm buah 10.00 Err:509 Err:509
3.4.(5) Pemotongan Pohon Pilihan diameter > 75 cm buah 5.00 Err:509 Err:509
DIVISI 4. PEKERJAAN PREVENTIF Err:509
4.9.(3) Tambalan Penuh dengan Beton Semen Cepat Mengeras untuk Pembukaan Lalu Lintas Umur Beton lebihM3 376.28 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509
4.9.(5) Pemasangan Sealant M1 20,717.00 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509
DIVISI 5. PERKERASAN BERBUTIR Err:509
5.1.(1) Lapis Pondasi Agregat Kelas A M3 5,805.00 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509
5.1.(2) Lapis Pondasi Agregat Kelas B M3 66.18 Err:509 Err:509 Err:509
5.1.(3) Lapis Pondasi Agregat Kelas S M3 200.00 Err:509 Err:509 Err:509 Err:509 Err:509
5.3.(3) Lapis Pondasi bawah Beton Kurus M 3 5,928.50 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509
SKh 1.5.3.(3) Perkerasan Jalan Beton Semen Untuk Pembukaan Lalu Lintas Umur 17,888.25 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509
Beton Lebih dari 3 hari kurang dari 7 hari - Err:509
DIVISI 6. PERKERASAN ASPAL Err:509
6.1 (1) Lapis Resap Pengikat - Aspal Cair/Emulsi Liter 504.00 Err:509 Err:509 Err:509 Err:509
6.1 (2a) Lapis Perekat - Aspal Cair/Emulsi Liter 5,821.35 Err:509 Err:509 Err:509 Err:509 Err:509
6.3(5a) Laston Lapis Aus (AC-WC) Ton 2,184.37 Err:509 Err:509 Err:509 Err:509
6.3(6a) Laston Lapis Antara (AC-BC) Ton 2,028.84 Err:509 Err:509 Err:509 Err:509 Err:509
6.3.(8) Bahan anti pengelupasan Kg 772.00 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509
DIVISI 7. STRUKTUR Err:509
7.1 (5a) Beton struktur, fc’30 MPa M3 32.76 Err:509 Err:509 Err:509
7.1 (10) Beton, fc’10 Mpa M3 2.40 Err:509 Err:509
7.3 (1) Baja Tulangan Polos-BjTP 280 Kg 250.00 Err:509 Err:509 Err:509
7.3 (3) Baja Tulangan Sirip BjTS 420A Kg 2,880.72 Err:509 Err:509 Err:509
7.3 (8) Anyaman Kawat Yang Dilas (Welded Wire Mesh) Kg 500.00 Err:509 Err:509 Err:509
7.4 (1b) Penyediaan Baja Struktur Grade 345 (kuat leleh 345 Mpa) Kg 402.40 Err:509 Err:509 Err:509
7.9.(1) Pasangan Batu M3 562.40 Err:509 Err:509 Err:509 Err:509 Err:509
7.10.(1) Pasangan Batu Kosong yang Diisi Adukan M3 13.20 Err:509 Err:509
7.10.(3a) Bronjong dengan kawat yang dilapisi Galvanis M3 100.00 Err:509 Err:509 Err:509
7.14.(1) Papan Nama Jembatan Buah 2.00 Err:509 Err:509
DIVISI 8. REHABILITASI JEMBATAN Err:509
8.2.(2) Perbaikan Dengan Cara Graut M3 2.35 Err:509 Err:509
8.7.(1b) Pengecatan struktur baja pada daerah kering tebal 240 mikron M2 818.16 Err:509 Err:509 Err:509
8.7.(3a) Pengecatan pada elemen sandaran dan/atau pagar pengaman (gruard rail) 80 mikron M2 161.00 Err:509 Err:509 Err:509
8.11.(1) Penggantian dan Perbaikan Sambungan Siar Muai Tipe Asphaltic Plug M 1 27.30 Err:509 Err:509
8.11.(3) Penggantian Karet Pengisi Sambungan Siar Muai Tipe Strip Seal M1 2.50 Err:509 Err:509
DIVISI 9. PEKERJAAN HARIAN & PEKERJAAN LAIN-LAIN Err:509
9.2.(1) Marka Jalan Termoplastik M2 7,377.01 Err:509 Err:509 Err:509 Err:509
9.2.(3a) Rambu Jalan Tunggal dengan Permukaan Pemantul Engineering Grade Buah 36.00 Err:509 Err:509
9.2.(3b) Rambu Jalan Ganda dengan Permukaan Pemantul Engineering Grade Buah 2.00 Err:509 Err:509
9.2.(6a) Patok Kilometer Buah 6.00 Err:509 Err:509
9.2.(7) Rel Pengaman M1 60.00 Err:509 Err:509
9.2.(10b) Kereb Pracetak Jenis 2 (Penghalang/Barrier) M1 1,407.00 Err:509 Err:509 Err:509 Err:509 Err:509
9.2.(10f) Kereb Pracetak Jenis 6 (Kereb dengan Bukaan) Buah 385.00 Err:509 Err:509 Err:509
9.2.(10g) Kereb Pracetak Jenis 7 (Kereb pada Pelandaian Trotoar) Buah 45.00 Err:509 Err:509
9.2.(10h) Kereb Pracetak Jenis 8 (Kereb pada Pelandaian Trotoar) Buah 45.00 Err:509 Err:509
9.2.(10i) Kereb Pracetak Jenis 9 (Kereb pada Pelandaian Trotoar) Buah 495.00 Err:509 Err:509 Err:509
9.2.(12a) Perkerasan Blok Beton pada Trotoar dan Median M2 2,860.00 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509
DIVISI 10. PEKERJAAN PEMELIHARAAN KINERJA Err:509
10.1.(1) Galian pada Saluran Air atau Lereng untuk Pemeliharaan M3 322.22 Err:509 Err:509 Err:509
10.1.(2) Timbunan Pilihan pada Lereng Tepi Saluran untuk Pemeliharaan M3 99.80 Err:509 Err:509 Err:509
10.1.(3) Pebaikan Pasangan Batu dengan Mortar M3 67.30 Err:509 Err:509
10.1.(4) Perbaikan Lapis Fondasi Agregat Kelas A M3 3.50 Err:509 Err:509
10.1.(5) Perbaikan Lapis Fondasi Agregat Kelas B M 3 16.40 Err:509 Err:509
10.1.(6) Perbaikan Lapis Fondasi Agregat Kelas S M3 121.30 Err:509 Err:509
10.1.(7) Perbaikan dan Perataan Permukaan JalanTanah M2 5,000.00 Err:509 Err:509 Err:509
10.1.(9) Perbaikan Campuran Aspal Panas M3 0.90 Err:509 Err:509
10.1.(14) Perbaikan Perkerasan Beton Semen M3 73.06 Err:509 Err:509 Err:509
10.1.(15) Perbaikan Lapis Fondasi Bawah Beton Kurus M3 24.50 Err:509 Err:509 Err:509
10.1.(16) Perbaikan Pasangan Batu M3 28.40 Err:509 Err:509
10.1.(17) Pengecatan Kereb pada Trotoar atau Median M 2 200.00 Err:509 Err:509 Err:509
10.1.(18) Perbaikan Rel Pengaman M1 200.00 Err:509 Err:509 Err:509
10.1.(19) Pembersihan Patok Buah 27.00 Err:509 Err:509 Err:509 Err:509
10.1.(20) Pembersihan Rambu Buah 74.00 Err:509 Err:509 Err:509 Err:509
10.1.(21) Pembersihan Drainase M1 14,530.00 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509
10.1.(22) Pengendalian Tanaman M2 643,396.00 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509
10.2.(1) Pemeliharaan Kinerja Jembatan Serdang bentang 7.00 m LS 1.00 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509
10.2.(2) Pemeliharaan Kinerja Jembatan Trumix Seruni bentang 9.00 m LS 1.00 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509
10.2.(3) Pemeliharaan Kinerja Jembatan Fly Over Seruni bentang 68.30 m LS 1.00 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509
10.2.(4) Pemeliharaan Kinerja Jembatan Serdang Terate bentang 36.50 m LS 1.00 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509
10.2.(5) Pemeliharaan Kinerja Jembatan Serdang Terate II Amnonim bentang 7.00 m LS 1.00 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509
10.2.(6) Pemeliharaan Kinerja Jembatan Terate III bentang 7.00 m LS 1.00 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509
10.2.(7) Pemeliharaan Kinerja Jembatan Grenyang bentang 8.00 m LS 1.00 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509
10.2.(8) Pemeliharaan Kinerja Jembatan Ragas bentang 7.10 m LS 1.00 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509
10.2.(9) Pemeliharaan Kinerja Jembatan Ragas II bentang 7.00 m LS 1.00 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509
10.2.(10) Pemeliharaan Kinerja Jembatan Pangoreng bentang 26 m LS 1.00 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509
10.2.(11) Pemeliharaan Kinerja Jembatan Cicegah bentang 7.60 m LS 1.00 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509
10.2.(12) Pemeliharaan Kinerja Jembatan Lebak Gede I bentang 6.00 m LS 1.00 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509
10.2.(13) Pemeliharaan Kinerja Jembatan Lebak Gede II bentang 6.00 m LS 1.00 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509
Err:509
BOBOT RENCANA MINGGUAN (%) Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509
BOBOT RENCANA KOMULATIF MINGGUAN (%) - Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509
DIVISI 1. UMUM
1.2 Mobilisasi LS - - -
1.8.(1) Manajemen dan Keselamatan Lalu Lintas LS - - -
1.8.(2) Jembatan Sementara LS - - -
1.17.(1a) Pengujian pH Buah - - -
1.17.(1b) Pengujian Oksigen Terlarut (DO) Buah - - -
1.17.(1c) Pengujian Zat Padat Terlarut (TDS) Buah - - -
1.17.(1d) Pengujian Zat Tersuspensi (TSS) Buah - - -
1.17.(1e) Pengujian Biological Oxygen Demand (BOD) Buah - - -
1.17.(1f) Pengujian Chemical Oxygen Demand (COD) Buah - - -
1.17.(1g) Pengujian Coliform Buah - - -
1.17.(1h) Pengujian E. Coli Buah - - -
1.17.(1i) Pengujian Destruksi Cu, Pb, Cd, Ni, Fe, Zn, Ag, Co, Mn Buah - - -
1.17.(1j) Pengujian Temperatur (Suhu) Buah - - -
1.17.(1k) Pengujian Parameter Kualitas Air Lainnya Buah - - -
1.17.(2a) Pengujian Vibrasi Lingkungan untuk Kenyamanan dan Kesehatan Buah - - -
1.17.(2b) Pengujian tingkat getaran kendaraan bermotor Buah - - -
1.17.(2c) Pengujian Parameter Kebisingan dan/atau Getaran Lainnya ……… Buah - - -
1.17.(3a) Pengujian NoX Buah - - -
1.17.(3b) Pengujian Sulfurdioksida (SO2) Buah - - -
1.17.(3c) Pengujian Karbondioksida (CO2) Buah - - -
1.17.(3d) Pengujian Hidro Carbon (HC)-CH4 Buah - - -
1.17.(3f) Pengujian Total Partikulat (TSP) - Debu Buah - - -
1.17.(3g) Pengujian Timah Hitam (Pb) Buah - - -
1.17.(3h) Pengujian Parameter Udara Emisi dan Ambien lainnya : ………….. Buah - - -
1.19 Keselamatan dan Kesehatan Kerja LS - - -
1.20.(1) Pengeboran, termasuk SPT dan Laporan M1 - - -
1.20.(2) Sondir termasuk Laporan M1 - - -
1.21 Manajemen Mutu LS - - -
-
-
Jumlah Harga Pekerjaan DIVISI 1 (masuk pada Rekapitulasi Perkiraan Harga Pekerjaan) -
-
-
DIVISI 2. DRAINASE -
2.1.(1) Galian untuk Selokan Drainase dan Saluran Air M3 - - -
2.2.(1) Pasangan Batu dengan Mortar M3 - - -
2.3.(1) Gorong-gorong Pipa Beton Tanpa Tulangan diameter dalam 20 cm M1 - - -
2.3.(2) Gorong-gorong Pipa Beton Tanpa Tulangan diameter dalam 25 cm M1 - - -
2.3.(3) Gorong-gorong Pipa Beton Tanpa Tulangan diameter dalam 30 cm M1 - - -
2.3.(4) Gorong-gorong Pipa Beton Bertulang, diameter dalam 40 cm M1 - - -
2.3.(5) Gorong-gorong Pipa Beton Bertulang, diameter dalam 60 cm M1 - - -
2.3.(6) Gorong-gorong Pipa Beton Bertulang, diameter dalam 80 cm M1 - - -
2.3.(7) Gorong-gorong Pipa Beton Bertulang, diameter dalam 100 cm M1 - - -
2.3.(8) Gorong-gorong Pipa Beton Bertulang, diameter dalam 120 cm M1 - - -
2.3.(9) Gorong-gorong Pipa Beton Bertulang, diameter dalam 150 cm M1 - - -
2.3.(10) Gorong-gorong Pipa Baja Bergelombang Ton - - -
2.3.(11) Gorong-gorong Kotak Beton Bertulang, ukuran dalam 40 cm x 40 cm M1 - - -
2.3.(12) Gorong-gorong Kotak Beton Bertulang, ukuran dalam 50 cm x 50 cm M1 - - -
2.3.(13) Gorong-gorong Kotak Beton Bertulang, ukuran dalam 60 cm x 60 cm M1 - - -
2.3.(14) Gorong-gorong Kotak Beton Bertulang, ukuran dalam 80 cm x 80 cm M1 - - -
2.3.(15) Gorong-gorong Kotak Beton Bertulang, ukuran dalam 100 cm x 100 cm M1 - - -
2.3.(16) Gorong-gorong Kotak Beton Bertulang, ukuran dalam 120 cm x 120 cm M1 - - -
2.3.(17) Gorong-gorong Kotak Beton Bertulang, ukuran dalam 140 cm x 140 cm M1 - - -
2.3.(18) Gorong-gorong Kotak Beton Bertulang, ukuran dalam 150 cm x 150 cm M1 - - -
2.3.(19) Gorong-gorong Kotak Beton Bertulang, ukuran dalam 160 cm x 160 cm M1 - - -
2.3.(20) Gorong-gorong Kotak Beton Bertulang, ukuran dalam 180 cm x 180 cm M1 - - -
2.3.(21) Gorong-gorong Kotak Beton Bertulang, ukuran dalam 200 cm x 200 cm M1 - - -
2.3.(22) Saluran berbentuk U Tipe DS 1 M1 - - -
2.3.(23) Saluran berbentuk U Tipe DS 1a (dengan tutup) M1 - - -
2.3.(24) Saluran berbentuk U Tipe DS 2 M1 - - -
2.3.(25) Saluran berbentuk U Tipe DS 2a (dengan tutup) M1 - - -
2.3.(26) Saluran berbentuk U Tipe DS 3 M1 - - -
2.3.(27) Saluran berbentuk U Tipe DS 3a (dengan tutup) M1 - - -
2.3.(28) Saluran berbentuk U Tipe DS 4 M1 - - -
2.3.(29) Saluran berbentuk U Tipe DS 4a (dengan tutup) M1 - - -
2.3.(30) Saluran berbentuk U Tipe DS 5 M1 - - -
2.3.(31) Saluran berbentuk U Tipe DS 5a (dengan tutup) M1 - - -
2.3.(32) Saluran berbentuk U Tipe DS 6 M1 - - -
2.3.(33) Saluran berbentuk U Tipe DS 6a (dengan tutup) M1 - - -
2.3.(34) Pasangan Batu tanpa Adukan (Aanstamping) M3 - - -
2.4.(1) Bahan Drainase Porous atau Penyaring (Filter) M3 - - -
2.4.(2) Pipa Berlubang Banyak (Perforated Pipe) untuk Pekerjaan Drainase Bawah Permukaan, di M1 - - -
2.4.(3) Pipa Berlubang Banyak (Perforated Pipe) untuk Pekerjaan Drainase Bawah Permukaan, di M1 - - -
2.4.(4) Pipa Berlubang Banyak (Perforated Pipe) untuk Pekerjaan Drainase Bawah Permukaan, di M1 - - -
2.4.(5) Pipa Berlubang Banyak (Perforated Pipe) untuk Pekerjaan Drainase Bawah Permukaan, di M1 - - -
Jumlah Harga Pekerjaan DIVISI 2 (masuk pada Rekapitulasi Perkiraan Harga Pekerjaan)
Jumlah Harga Pekerjaan DIVISI 3 (masuk pada Rekapitulasi Perkiraan Harga Pekerjaan)
Jumlah Harga Pekerjaan DIVISI 4 (masuk pada Rekapitulasi Perkiraan Harga Pekerjaan)
Jumlah Harga Pekerjaan DIVISI 5 (masuk pada Rekapitulasi Perkiraan Harga Pekerjaan)
Jumlah Harga Pekerjaan DIVISI 6 (masuk pada Rekapitulasi Perkiraan Harga Pekerjaan)
DIVISI 7. STRUKTUR
7.1 (1) Beton struktur, fc’50 MPa M3 -
7.1 (2) Beton struktur, fc’45 MPa M3 -
7.1 (3) Beton struktur, fc’40 MPa M3 -
7.1 (4) Beton struktur, fc’35 MPa M3 -
7.1 (5a) Beton struktur, fc’30 MPa M3 - -
7.1 (5b) Beton strukutr bervolome besar, fc'30 MPa M3 - -
7.1 (5c) Beton strukutr memadat sendiri, fc'30 MPa M3 - -
7.1 (6a) Beton struktur, fc’25 Mpa M3 - -
7.1 (6b) Beton struktur bervolume besar, fc’25 Mpa M3 - -
7.1 (6c) Beton struktur memadat sendiri, fc’25 Mpa M3 - -
7.1 (7a) Beton strukur, fc’20 MPa M3 - -
7.1 (7b) Beton strukut bervolume besar, fc’20 MPa M3 - -
7.1 (7c) Beton strukut memadat sendiri, fc’20 MPa M3 - -
7.1 (7d) Beton strukut, fc’20 MPa yang dilaksanakan di air M3 - -
7.1 (8) Beton , fc’15 Mpa M3 - -
7.1 (9) Beton Siklop, fc’15 Mpa M3 - -
7.1 (10) Beton, fc’10 Mpa M3 - -
7.2 (1a) Penyediaan Unit Pracetak Gelagar Tipe I Bentang 16 meter Buah - -
7.2 (1b) Penyediaan Unit Pracetak Gelagar Tipe I Bentang 25 meter Buah - -
7.2 (1c) Penyediaan Unit Pracetak Gelagar Tipe I Bentang … meter Buah - -
7.2 (2a) Pemasangan Unit Pracetak Gelagar Tipe I Bentang 16 meter Buah - -
7.2 (2b) Pemasangan Unit Pracetak Gelagar Tipe I Bentang 25 meter Buah - -
7.2 (2c) Pemasangan Unit Pracetak Gelagar Tipe I Bentang … meter Buah - -
7.2 (3a) Penyediaan Unit Pracetak Gelagar Tipe U Bentang 16 meter Buah - -
7.2 (3b) Penyediaan Unit Pracetak Gelagar Tipe U Bentang … meter Buah - -
7.2 (4a) Pemasangan Unit Pracetak Gelagar Tipe U Bentang 16 meter Buah - -
7.2 (4b) Pemasangan Unit Pracetak Gelagar Tipe U Bentang … meter Buah - -
7.2.(5) Penyediaan Unit Pracetak Gelagar Box bentang ... meter lebar ……meter Buah - -
7.2.(6) Pemasangan Unit Pracetak Gelagar Box bentang ... meter lebar ……meter Buah - -
7.2.(7) Baja Prategang Kg - -
7.2.(8) Penyediaan Pelat Berongga (Voided Slab) Pracetak bentang ….. Meter Buah - -
7.2.(9) Pemasangan Pelat Berongga (Voided Slab) Pracetak bentang ….. Meter Buah - -
7.2.(10) Beton Pratekan untuk Diafragma fc' 45 MPa termasuk Pekerjaan pasca-tarik (post-tensionM3 - -
7.2.(11a) Penyediaan Balok T Beton Pratekan bentang 40m Buah - -
7.2.(11b) Pemasangan Balok T Beton Pratekan bentang 60 m Buah - -
7.2.(12a) Penyediaan Panel Full Depth slab Buah - -
7.2.(12b) Penyediaan Panel Full Depth slab Buah - -
7.3 (1) Baja Tulangan Polos-BjTP 280 Kg - -
7.3 (2) Baja Tulangan Sirip BjTS 280 Kg - -
7.3 (3) Baja Tulangan Sirip BjTS 420A Kg - -
7.3 (4) Baja Tulangan Sirip BjTS 420B Kg - -
7.3 (5) Baja Tulangan Sirip BjTS 520 Kg - -
7.3 (6) Baja Tulangan Sirip BjTS 550 Kg - -
7.3 (7) Baja Tulangan Sirip BjTS 700 Kg - -
7.3 (8) Anyaman Kawat Yang Dilas (Welded Wire Mesh) Kg - -
7.4 (1a) Penyediaan Baja Struktur Grade 250 (Kuat Leleh 250 MPa) Kg - -
7.4 (1b) Penyediaan Baja Struktur Grade 345 (Kuat Leleh 345 MPa) Kg - -
7.4 (1c) Penyediaan Baja Struktur Grade 485 (Kuat Leleh 485 MPa) Kg - -
7.4 (1d) Penyediaan Baja Struktur Grade 690 (Kuat Leleh 690 Mpa Untuk Tebal Pelat < 2,5) Kg - -
7.4 (1e) Penyediaan Baja Struktur Grade 690 (Kuat Leleh 620 Mpa Untuk Tebal Pelat < 2,5-4,0 inchKg - -
7.4 (2) Pemasangan Baja Struktur Kg - -
7.4 (3) Penyediaan Struktur Jembatan Rangka Baja Standar …… m Kg - -
7.4 (4) Pemasangan Jembatan Rangka Baja Standar Panjang ….. M Kg - -
7.4 (5a) Pemasangan Jembatan Rangka Baja yang disediakan Pengguna Jasa Kg - -
7.4 (5b) Pengangkutan Bahan Jembatan yang disediakan Pengguna Jasa Kg - -
7.5.(1) Tiang bor sekan primer diameter 80 cm (fc' > 15 MPa) M1 - -
7.5.(2) Tiang bor sekan sekunder diameter 80 cm (fc' > 30 MPa) M1 - -
7.5.(3) Tiang bor sekan primer diameter 100 cm (fc' > 15MPa) M1 - -
7.5.(4) Tiang bor sekan sekunder diameter 100 cm (fc' > 30 MPa) M1 - -
7.5.(5) Tiang bor sekan primer diameter 120 cm (fc' > 15 MPa) M1 - -
7.5.(6) Tiang bor sekan sekunder diameter 120 cm (fc' > 30 MPa) M1 - -
7.5.(7) Tiang bor sekan primer diameter 150 cm (fc' > 15 MPa) M1 - -
7.5.(8) Tiang bor sekan sekunder diameter 150 cm (fc' > 15 MPa) M1 - -
7.5.(9) Tiang bor sekan primer diameter …… cm (fc' > 15 MPa) M1 - -
7.5.(10) Tiang bor sekan sekunder diameter ….. cm (fc' > 15 MPa) M1 - -
7.6 (1) Fondasi Cerucuk, Penyediaan dan Pemancangan M1 - -
7.6 (2) Dinding Turap Kayu Tanpa Pengawetan, Penyediaan dan Pemancangan M2 - -
7.6.(3) Dinding Turap Kayu Dengan Pengawetan, Penyediaan dan Pemancangan M2 - -
7.6.(4) Dinding Turap Baja, Penyediaan dan Pemancangan M2 - -
7.6.(5) Dinding Turap Beton, Penyediaan dan Pemancangan M2 - -
7.6.(6) Penyediaan Tiang Pancang Kayu Tanpa Pengawetan Ukuran…… mm M1 - -
7.6.(7) Penyediaan Tiang Pancang Kayu Dengan Pengawetan Ukuran…… mm M1 - -
7.6 (8a) Penyediaan Tiang Pancang Baja Diameter 500 mm tebal 10 mm M1 - -
7.6 (8b) Penyediaan Tiang Pancang Baja Diameter …. mm tebal …... mm M1 - -
7.6.(8c) Penyediaan Tiang Pancang Baja Diameter …... mm tebal …… mm M1 - -
7.6.(9a) Penyediaan Tiang Pancang Baja H Beam Ukuran 300 mm x 300 mm x 10 mm x 15 mm M1 - -
7.6.(9b) Penyediaan Tiang Pancang Baja H Beam Ukuran …..mm x …….. mm x …….mm x ……... mm M1 - -
7.6.(10a) Penyediaan Tiang Pancang Beton Bertulang Pracetak ukuran 350 mm x 350 mm M1 - -
7.6.(10b) Penyediaan Tiang Pancang Beton Bertulang Pracetak ukuran ……..mm x ……... mm M1 - -
7.6.(11a) Penyediaan Tiang Pancang Beton Pratekan Pracetak ukuran 400 mm x 400 mm M1 - -
7.6.(11b) Penyediaan Tiang Pancang Beton Pratekan Pracetak ukuran ……. mm x ………. mm M1 - -
7.6.(12a) Penyediaan Tiang Pancang Beton Pratekan Pracetak diameter 450 mm M1 - -
7.6.(12b) Penyediaan Tiang Pancang Beton Pratekan Pracetak diameter ……...mm M1 - -
7.6.(13) Pemancangan Tiang Pancang Kayu Ukuran ….. Mm M1 - -
7.6.(14a) Pemancangan Tiang Pancang Baja Diameter 500 mm M1 - -
7.6.(14b) Pemancangan Tiang Pancang Baja Diameter …….. mm M1 - -
7.6.(15a) Pemancangan Tiang Pancang Baja H beam Ukuran 300 mm x 300 mm x 10 mm x 15 mm M1 - -
7.6.(15b) Pemancangan Tiang Pancang Baja H beam Ukuran…….. mm x …….. mm x …….. mm x …….. M1 - -
7.6.(16a) Pemancangan Tiang Pancang Beton Bertulang Pracetak ukuran 350 mm x 350 mm M1 - -
7.6.(16b) Pemancangan Tiang Pancang Beton Bertulang Pracetak ukuran………. mm x ………... mm M1 - -
7.6.(17a) Pemancangan Tiang Pancang Beton Pratekan Pracetak ukuran 400 mm x 400 mm M1 - -
7.6.(17b) Pemancangan Tiang Pancang Beton Pratekan Pracetak ukuran ………. mm x ….. mm M1 - -
7.6.(18a) Pemancangan Tiang Pancang Beton Pratekan Pracetak diameter 450 mm M1 - -
7.6.(18b) Pemancangan Tiang Pancang Beton Pratekan Pracetak diameter ….. mm - -
7.6.(19a) Tiang Bor Beton, diameter 800 mm M1 - -
7.6.(19b) Tiang Bor Beton, diameter ….. mm M1 - -
7.6.(20) Tambahan Biaya untuk Nomor Mata Pembayaran 7.6.(13)s/d 7.6.(18) bila Tiang Pancang dM1 - -
7.6.(21) Tambahan Biaya untuk Nomor Mata Pembayaran 7.6.(19) Bila Tiang Bor Beton dikerjakan M1 - -
7.6.(22) Pengujian Pembebanan Pada Tiang Dengan Diameter sampai 600 mm Buah - -
7.6.(23) Pengujian Pembebanan Pada Tiang Dengan Diameter di atas 600 mm Buah - -
7.6.(24) Tiang Uji jenis …. Ukuran …… M1 - -
7.6.(25a) Pengujian Pembebanan Statis pada Tiang ukuran / diameter .... Dengan beban hidrolik CarBuah - -
7.6 (25b) Pengujian Pembebanan Statis pada Tiang ukuran / diameter .... Dengan beban hidrolik C Buah - -
7.6 (26a) Pengujian Pembebanan Statis pada Tiang ukuran / diameter ……. meja beban statis Cara bBuah - -
7.6 (26b) Pengujian Pembebanan Statis pada Tiang ukuran / diameter ……. meja beban statis Cara Buah - -
7.6 (27a) Pengujian Crosshole sonic logging (CSL) pada Tiang bor beton diameter .... Buah - -
7.6 (27b) Pengujian Pembebanan Dinamis Jenis PDLT (Pile Dynamic Load Testing) pada TiangukuranBuah/ - -
7.6 (28) Pengujian Keutuhan Tiang dengan Pile Integrated Test (PIT) Buah - -
7.7.(1) Dinding Sumuran Silinder terpasang, Diameter ……………. M1 - -
7.9.(1) Pasangan Batu M3 - -
7.10.(1) Pasangan Batu Kosong yang Diisi Adukan M3 - -
7.10.(2) Pasangan Batu Kosong M3 - -
7.10.(3a) Bronjong dengan kawat yang dilapisi Galvanis M3 - -
7.10.(3b) Bronjong dengan kawat yang dilapisi PVC M3 - -
7.10.(4) Tambahan Biaya untuk Anyaman Penulangan Tanah dengan Kawat yang Dilapisi PVC M2 - -
7.11.(1a) Sambungan Siar Muai Tipe Asphaltic Plug, Fixed M1 - -
7.11.(1b) Sabungan siar Muai Tipe Asphaltic Plug, Movable M1 - -
7.11.(2) Sambungan Siar Muai Tipe Silicone Seal M1 - -
7.11.(3) Sambungan Siar Muai Tipe Strip seal M1 - -
7.11.(4) Sambungan Siar Muai Tipe Compression Seal M1 - -
7.11.(5) Sambungan Siar Muai Expansion Joint Tipe Modular, lebar …….. M1 - -
7.11.(6) Sambungan Siar Muai Expansion Joint Tipe Finger Plate, lebar …….. M1 - -
7.11.(7) Sambungan Siar Muai Expansion Tipe Karet dengan Lebar Celah …….. Cm M3 - -
7.11.(8) Joint Filler untuk Sambungan Konstruksi M3 - -
7.11.(9) Sambungan Siar Muai Tipe Modular, Lebar …….. M3 - -
7.12.(1a) Landasan Logam Tipe Fixed Buah - -
7.12.(1b) Landasan Logam Tipe Moveable Buah - -
7.12.(1c) Landasan Logam Tipe ……. Buah - -
7.12.(2) Landasan Elastomerik Karet Alam Berlapis Baja Ukuran ….. Mm x ….. Mm x…….. Mm Buah - -
7.12.(3) Landasan Elastomerik Karet Sintetis Berlapis Baja Ukuran ….. Mm x ….. Mm x…….. Mm Buah - -
7.12.(4) Landasan karet Strip M1 - -
7.12.(5) Landasan Tipe Logam Berongga (Pot Bearing) Buah - -
7.12.(6) Landasan Tipe Logam Jenis Spherical Buah - -
7.13.(1) Sandaran (Railing) M1 - -
7.14.(1) Papan Nama Jembatan M1 2.00 2.00 4.00
7.15.(1) Pembongkaran Pasangan Batu M3 - -
7.15.(2) Pembongkaran Beton M3 - -
7.15.(3) Pembongkaran Beton Pratekan M3 -
7.15.(4) Pembongkaran Bangunan Gedung M2 -
7.15.(5) Pembongkaran Rangka Baja M2 -
7.15.(6) Pembongkaran Balok Baja (Steel Stingers) M1 -
7.15.(7) Pembongkaran Lantai Jembatan Kayu M2 -
7.15.(8) Pembongkaran Jembatan Kayu M2 -
7.15.(9) Pengangkutan Hasil Bongkaran yang melebihi 5 km M3/ km -
7.16.(1) Dreck drain Buah -
7.16.(2a) Pipa Drainase Baja diameter 150 mm M1 -
7.16.(2b) Pipa Drainase Baja diameter ……. Mm M1 -
7.16.(3a) Pipa Drainase PVC diameter 150 mm M1 -
7.16.(3b) Pipa Drainase PVC diameter …… mm M1 -
7.16.(4) Pipa Penyalur PVC M1 -
7.11.(1) Pengujian Pembebanan Jembatan Buah Jembatan -
Jumlah Harga Pekerjaan DIVISI 7 (masuk pada Rekapitulasi Perkiraan Harga Pekerjaan)
Jumlah Harga Pekerjaan DIVISI 8 (masuk pada Rekapitulasi Perkiraan Harga Pekerjaan)
Jumlah Harga Pekerjaan DIVISI 10 (masuk pada Rekapitulasi Perkiraan Harga Pekerjaan)
Harga Satuan Jumlah Harga
(Rupiah) Harga (Rupiah)
158,212,000.00 -
152,020,000.00 -
413,725,754.91 -
20,700.00 -
46,500.00 -
46,500.00 -
46,500.00 -
46,500.00 -
46,500.00 -
98,147.00 -
69,582.00 -
338,800.00 -
45,000.00 -
46,500.00 -
1,135,200.00 -
62,500.00 -
62,500.00 -
204,400.00 -
141,900.00 -
141,900.00 -
141,900.00 -
774,000.00 -
62,500.00 -
62,500.00 -
171,500,000.00 -
577,202.40 -
443,269.87 -
584,470,666.67 -
98,721.27 -
946,334.64 -
163,375.43 -
263,988.87 -
271,190.13 -
585,817.63 -
879,048.63 -
1,338,457.76 -
1,771,250.77 -
2,285,617.86 -
3,364,288.81 -
17,165,302.71 -
532,266.46 -
708,577.00 -
897,099.41 -
1,392,514.45 -
2,380,470.35 -
3,592,257.96 -
5,869,901.05 -
7,022,502.25 -
8,912,288.65 -
12,825,199.60 -
18,000,144.43 -
685,739.00 -
825,395.00 -
904,239.00 -
1,149,979.00 -
1,105,489.00 -
1,402,979.00 -
1,427,529.00 -
1,729,287.00 -
423,744.00 -
580,896.00 -
423,744.00 -
580,896.00 -
740,455.51 -
270,350.56 -
71,034.92 -
101,476.05 -
138,865.04 -
175,687.55 -
98,531.11 -
67,818.24 -
102,095.96 -
80,051.66 -
894,508.52 -
1,301,659.66 -
510,729.46 13,535,862.90
528,497.24 -
36,899.66 -
416,056.68 -
266,014.03 -
60,009.36 -
303,662.07 -
102,180.65 -
296,158.78 -
368,000.71 -
338,783.75 -
12,179.48 -
24,724.92 -
175,823.39 -
565,202.35 -
1,402,405.03 -
2,247,970.71 -
215,898.62 -
183,372.31 -
246,515.90 -
255,579.90 -
274,015.54 -
81,274.77 -
13,535,862.90
12,287.53 -
12,287.53 -
12,287.53 -
13,085.40 -
21,085.31 -
18,531.17 -
18,898.35 -
21,113.93 -
27,181.93 -
29,391.46 -
7,237.51 -
108,703.74 -
3,069.59 -
82,101.54 -
1,557,517.97 -
1,825,521.91 -
- -
- -
1,451,633.98 -
1,328,288.88 -
1,205,718.99 -
1,244,545.54 -
1,945,652.62 -
1,967,249.94 -
425,150.31 -
321,494.59 -
321,894.23 -
10,514,909.94 -
13,276,869.79 -
13,276,832.38 -
341,456.65 -
11,054.26 -
296,761.70 -
25,438.40 -
- -
- -
- -
- -
- -
- -
- -
106,118.32 -
162,221.86 -
781,771.40 -
- -
- -
- -
- -
- -
5,365.30 -
451,184.71 -
471,040.33 -
545,537.06 -
503,133.10 -
508,475.48 -
523,269.59 -
551,630.02 -
509,901.32 -
1,793,566.83 -
3,547,472.43 -
3,090,349.42 -
1,994,472.74 -
4,982,268.99 -
4,551,003.81 -
1,150,898.95 -
854,667.99 -
883,776.57 -
645,606.14 -
579,630.24 -
20,100.28 5,767,977.68
23,621.44 2,541,902.69
24,843.88 -
6,743.21 -
9,477.79 -
11,442.50 -
21,552.34 -
11,925.44 -
13,464.06 -
14,010.16 -
1,326,062.33 -
1,511,624.00 -
1,311,113.28 -
1,471,296.53 -
1,402,274.78 -
1,224,461.76 -
1,304,923.47 46,379,459.37
1,408,358.95 -
1,242,416.23 -
1,352,049.40 -
1,135,728.55 -
1,202,281.41 -
67,980.00 437,456.60
1,316,564.93 -
1,270,875.22 -
1,034,781.14 -
1,205,532.99 -
1,148,529.95 -
1,103,125.51 -
1,490,942.73 -
1,428,435.49 -
1,321,341.53 -
1,136,562.16 -
1,807,248.00 -
1,414,347.82 -
55,126,796.34
2,502,751.60 -
2,444,498.19 -
2,379,125.49 -
2,313,431.52 -
2,022,774.89 -
2,310,885.24 -
2,012,954.36 -
1,942,984.84 -
2,025,484.84 -
1,981,341.60 -
1,945,421.58 -
2,027,921.58 -
2,238,319.23 -
2,902,379.20 -
1,715,725.96 -
812,164.09 -
1,353,917.61 -
151,830,935.63 -
248,655,926.42 -
- -
11,908,427.16 -
13,780,476.71 -
- -
410,769,699.78 -
- -
13,780,476.71 -
- -
- -
- -
580,328.65 -
- -
- -
- -
- -
- -
1,427,665.96 -
660,848.49 -
16,450.64 -
16,903.84 -
17,130.44 -
15,746.38 -
16,450.64 -
16,450.64 -
16,450.64 -
19,237.18 -
29,600.47 -
19,160.23 -
20,260.23 -
24,660.23 -
21,360.23 -
3,111.70 -
29,610.23 -
3,111.70 -
3,111.70 -
29,610.23 -
1,648,218.44 -
2,808,362.84 -
2,197,848.16 -
3,330,938.78 -
2,869,617.83 -
4,213,575.73 -
4,106,284.72 -
6,038,011.69 -
- -
- -
62,435.56 -
148,926.21 -
196,157.37 -
2,777,685.32 -
737,717.89 -
64,033.52 -
66,821.96 -
2,688,314.09 -
- -
- -
842,901.01 -
- -
769,612.84 -
- -
1,070,958.88 -
- -
773,191.58 -
- -
330,578.45 -
286,448.54 -
- -
248,927.10 -
- -
248,927.10 -
- -
248,927.10 -
- -
464,787.60 -
- -
2,152,003.72 -
- -
84,919.50 -
135,136.25 -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
8,325,593.75 -
745,094.29 -
587,688.07 -
588,519.98 -
595,946.08 -
917,113.61 -
246,193.44 -
2,144,634.02 -
3,045,197.82 -
749,798.88 -
1,377,254.76 -
1,476,058.31 -
1,193,445.90 -
4,146,948.94 -
1,934,040.99 -
2,513,531.38 -
317,548.31 -
2,103,394.37 -
2,270,352.23 -
- -
1,248,452.23 -
992,152.23 -
305,214.17 -
13,236,557.73 -
14,651,857.50 -
91,595.08 -
354,119.18 1,416,476.72
359,382.48 -
530,396.11 -
455,988.14 -
275,488.97 -
1,116,957.05 -
411,697.48 -
166,168.67 -
46,066.43 -
- -
138,095.99 -
274,483.36 -
- -
83,885.86 -
- -
83,885.86 -
- -
1,416,476.72
599,495.23 -
158,933.20 -
97,042.52 -
119,645.44 -
3,165,666.24 -
3,768,693.20 -
54,757.58 21,342,314.60
- -
54,757.58 -
- -
1,077,664.49 -
2,154,014.49 -
1,077,664.49 -
1,077,664.49 -
2,720,514.49 -
- -
1,113,856.11 -
213,964,260.64 -
47,240.61 -
- -
- -
68,690.61 -
- -
- -
47,240.61 -
- -
47,240.61 -
- -
47,240.61 -
- -
33,743.29 -
- -
33,743.29 -
- -
88,610.32 -
- -
79,865.95 -
- -
78,664.33 -
- -
78,664.33 -
- -
103,187.42 -
179,969.04 26,800,988.78
- -
179,969.04 -
179,969.04 -
- -
179,969.04 61,483.18
179,478.05 -
- -
6,354,867.10 -
1,370,772.96 -
1,373,518.56 -
1,351,480.00 -
- -
36,003,166.00 -
7,265,278.76 -
8,916,162.29 -
6,283,365.40 -
6,227,542.36 -
5,976,338.67 -
6,478,746.05 -
7,247,850.43 -
11,373,228.37 -
7,159,742.08 -
44,466.91 -
44,466.91 -
44,466.91 -
44,466.91 -
44,466.91 -
4,571,681.64 -
758,620.22 -
1,367,737.56 -
1,476,058.31 -
228,547.68 -
4,148,727.68 -
214,272.00 -
4,024,588.59 -
8,465,609.77 -
4,244,038.59 -
12,097,390.97 -
8,941,588.59 -
8,432,609.77 -
215,980.69 -
215,980.69 -
434,044.33 -
623,348.47 -
2,826,353.60 78,428,486.12
3,239,479.56 -
157,779.77 -
167,506.26 -
579,731.26 2,550,817.53
129,184,090.20
21,870.79 -
19,645.91 -
20,786.51 -
113,664.78 -
411,007.34 -
331,850.32 -
298,036.93 -
233,100.30 -
469,935.35 -
288,811.15 -
216,159.53 -
288,811.15 -
486,602.28 -
708,693.47 -
464,627.59 -
404,746.66 -
54,798.10 -
480,850.45 -
184,545.13 -
84,591.41 -
52,418.15 -
49,854.87 -
261,529.79 2,975,162.85
125,561.29 -
424,960.46 -
733,406.28 -
169,073.25 -
227,912.90 -
140,609.38 -
232,014.74 -
108,964.41 -
1,132,509.87 -
107,721.18 -
147,871.18 -
225,281.95 -
246,823.62 -
178,460.58 -
176,115.84 -
181,446.90 -
209,738.59 -
247,019.62 -
136,932.03 -
133,708.25 -
101,029.80 -
74,847.44 -
45,938.90 -
169,679.99 -
13,047.83 -
737,257.31 -
2,611,004.61 -
3,656,004.61 19,215,960.22
2,163,314.82 -
2,548,314.82 -
2,281,004.61 -
2,776,004.61 -
744,194.76 -
744,194.76 -
61,837.20 -
15,379.58 -
64,241.10 -
59,291.10 -
22,191,123.06
113,664.78 27,350,456.31
364,231.05 -
972,735.19 -
837,813.36 -
776,830.59 -
775,692.38 -
7,183.27 -
7,867.43 -
2,847,118.97 -
1,843,347.79 -
1,437,055.76 -
1,770,611.98 -
411,796.93 -
2,060,716.08 -
1,452,915.34 -
916,804.03 -
44,831.78 -
33,977.70 -
18,027.98 -
18,027.98 -
45,484.19 -
1,158.84 231,768.47
1,000,000.00 -
- -
- -
- -
- -
27,582,224.78
REPUBLIK INDONESIA
KEMENTERIAN PEKERJAAN UMUM DAN PERUMAHAN RAKYAT
DIREKTORAT JENDERAL BINA MARGA
BALAI PELAKSANAAN JALAN NASIONAL VI BANTEN
Perkiraan
No. Mata Uraian Satuan Kuantitas Harga Jumlah Nameng Jumlah Tambak
Pembayaran jumlah Satuan Harga Harga
Jbt. Nameng Jbt. Tambak
vol (Rupiah) (Rupiah) (Rupiah)
a b c d e f = (d x e)
DIVISI 1. UMUM
- 0.00
Jumlah Harga Pekerjaan DIVISI 1 (masuk pada Rekapitulasi Perkiraan Harga Pekerjaan)
DIVISI 2. DRAINASE
- 0.00
Jumlah Harga Pekerjaan DIVISI 2 (masuk pada Rekapitulasi Perkiraan Harga Pekerjaan)
- 0.00
DIVISI 3. PEKERJAAN TANAH DAN GEOSINTETIK - 0.00
3.1.(1) Galian Biasa M3 - - - 98,531.11 0.00 0
3.1.(2) Galian Batu Lunak M3 - - - 67,818.24 0.00 0
3.1.(3) Galian Batu M3 - - - 102,095.96 0.00 0
3.1.(4) Galian Struktur dengan kedalaman 0 - 2 meter M 3
- - - 80,051.66 0.00 0
3.1.(5) Galian Struktur dengan kedalaman 2 - 4 meter M 3
- - - 894,508.52 0.00 0
3.1.(6) Galian Struktur dengan kedalaman 4 - 6 meter M 3
- - - 1,301,659.66 0.00 0
3.1.(7) Galian Perkerasan Beraspal dengan Cold Milling Machine M3 - 16.1 16.1 510,729.46 0.00 8,218,914
3.1.(8) Galian Perkerasan Beraspal tanpa Cold Milling Machine M3 - - - 528,497.24 0.00 0
3.1.(9) Galian Perkerasan berbutir M3 - - - 36,899.66 0.00 0
3.1.(10). Galian Perkerasan Beton M3 - - - 416,056.68 0.00 0
3.2.(1a) Timbunan Biasa dari sumber galian M3 - - 266,014.03 0.00 0
3.2.(1b) Timbunan Biasa dari hasil galian M3 - - - 60,009.36 0.00 0
3.2.(2a) Timbunan Pilihan dari sumber galian M 3
- - - 303,662.07 0.00 0
3.2.(2b) Timbunan Pilihan dari galian M 3
- - - 102,180.65 0.00 0
3.2.(3a) Timbunan Pilihan (diukur diatas bak truk) M 3
- - - 296,158.78 0.00 0
3.2.(3b) Timbunan Pilihan (diukur dengan rod & plate) M3 - - - 368,000.71 0.00 0
3.2.(4) Penimbunan Kembali Berbutir (Granular Backfill) M3 - - - 338,783.75 0.00 0
3.3.(1) Penyiapan Badan Jalan M2 - - - 12,179.48 0.00 0
3.4.(1) Pembersihan dan Pengupasan Lahan M2 - 24,724.92 0.00 0
3.4.(2) Pemotongan Pohon Pilihan diameter 15 – 30 cm buah - 175,823.39 0.00 0
3.4.(3) Pemotongan Pohon Pilihan diameter > 30 – 50 cm buah - 565,202.35 0.00 0
3.4.(4) Pemotongan Pohon Pilihan diameter > 50 – 75 cm buah - 1,402,405.03 0.00 0
3.4.(5) Pemotongan Pohon Pilihan diameter > 75 cm buah - 2,247,970.71 0.00 0
3.5.(1) Geotekstil Filter untuk Drainage Bawah Permukaan (Kelas 2) M 2
- 215,898.62 0.00 0
3.5.(2a) Geotekstil Separator Kelas 1 M2 - 183,372.31 0.00 0
3.5.(2b) Geotekstil Separator Kelas 2 M2 - 246,515.90 0.00 0
3.5.(2c) Geotekstil Separator Kelas 3 M2 - 255,579.90 0.00 0
3.5.(3) Geotekstil Stabilisator (Kelas 1) M2 - 274,015.54 0.00 0
Skh-3.5.3.(1) Geomembran M2 - 81,274.77 0.00 0
- 0.00
Jumlah Harga Pekerjaan DIVISI 3 (masuk pada Rekapitulasi Perkiraan Harga Pekerjaan) 0.00 8,218,913.85
- 0.00
DIVISI 4. PEKERJAAN PREVENTIF - 0.00
- 0.00
Jumlah Harga Pekerjaan DIVISI 4 (masuk pada Rekapitulasi Perkiraan Harga Pekerjaan)
- 0.00
DIVISI 5. PERKERASAN BERBUTIR - 0.00
- 0.00
Jumlah Harga Pekerjaan DIVISI 5 (masuk pada Rekapitulasi Perkiraan Harga Pekerjaan)
- 0.00
DIVISI 6. PERKERASAN ASPAL - 0.00
6.1 (1) Lapis Resap Pengikat - Aspal Cair/Emulsi Liter 51.6 257.5 309.1 20,100.28 1,037,174.69 5,175,421
6.1 (2a) Lapis Perekat - Aspal Cair/Emulsi Liter 19.3 96.6 115.9 23,621.44 457,074.78 2,280,768
6.1 (2b) Lapis Perekat - Aspal Emulsi Modifikasi Polimer Liter - - 24,843.88 0.00 0
6.2 (1) Agregat Penutup BURTU M2 - - 6,743.21 0.00 0
6.2 (2) Agregat Penutup BURDA M2 - - - 9,477.79 0.00 0
6.2 (3a) Bahan Aspal Keras untuk Pekerjaan Pelaburan Liter - - - 11,442.50 0.00 0
6.2 (3b) Bahan Aspal Emulsi Modifikasi untuk Pekerjaan Pelaburan Liter - - - 21,552.34 0.00 0
6.2 (4a) Aspal Cair untuk Precoated Liter - - 11,925.44 0.00 0
6.2 (4b) Aspal Emulsi untuk Precoated Liter - - 13,464.06 0.00 0
6.2 (4c) Aspal Emulsi Modifikasi Polimer untuk Precoated Liter - - 14,010.16 0.00 0
6.3 (1a) Stone Matrix Asphalt Halus (SMA Halus) Ton - - 1,326,062.33 0.00 0
6.3 (1b) Stone Matrix Asphalt Modifikasi Halus (SMA Mod Halus) Ton - - 1,511,624.00 0.00 0
6.3 (2a) Stone Matrix Asphalt Kasar (SMA Kasar) Ton - - 1,311,113.28 0.00 0
6.3 (2b) Stone Matrix Asphalt Modifikasi Kasar (SMA Mod Kasar) Ton - - 1,471,296.53 0.00 0
6.3(3) Lataston Lapis Aus (HRS-WC) Ton - - - 1,402,274.78 0.00 0
6.3.(4) Lataston Lapis Fondasi (HRS-Base) Ton - - - 1,224,461.76 0.00 0
6.3(5a) Laston Lapis Aus (AC-WC) Ton 5.9 37.0 42.9 1,304,923.47 7,743,415.85 48,298,806
6.3(5b) Laston Lapis Aus Modifikasi (AC-WC Mod) Ton - - - 1,408,358.95 0.00 0
6.3(6a) Laston Lapis Antara (AC-BC) Ton - - - 1,242,416.23 0.00 0
6.3(6b) Laston Lapis Antara Modifikasi (AC-BC Mod) Ton - - - 1,352,049.40 0.00 0
6.3(7a) Laston Lapis Fondasi (AC-Base) Ton - - - 1,135,728.55 0.00 0
6.3(7b) Laston Lapis Fondasi Modifikasi (AC-Base Mod) Ton - - - 1,202,281.41 0.00 0
6.3.(8) Bahan anti pengelupasan Kg 1.2 5.8 6.93 67,980.00 78,661.70 392,516
6.4.(1a) Laston Hangat Pen.60-70, WMAC Lapis Aus (WMAC-WC) dengan Zeolit Ton - - - 1,316,564.93 0.00 0
6.4.(1b) Laston Hangat Pen.60-70, WMAC Lapis Aus (WMAC-WC) dengan Wax Ton - - - 1,270,875.22 0.00 0
6.4.(2a) Laston Hangat Pen.60-70, WMAC Lapis Antara (WMAC-BC) dengan Zeolit Ton - - - 1,034,781.14 0.00 0
6.4.(2b) Laston Hangat Pen.60-70, WMAC Lapis Antara (WMAC-BC) dengan Wax Ton - - - 1,205,532.99 0.00 0
6.4.(3a) Laston Hangat Pen.60-70, WMAC Lapis Fondasi (WMAC-Base) dengan Zeolit Ton - - - 1,148,529.95 0.00 0
6.4.(3b) Laston Hangat Pen.60-70, WMAC Lapis Fondasi (WMAC-Base) dengan Wax Ton - - - 1,103,125.51 0.00 0
6.5.(1) Laston Lapis Aus Asbuton (AC-WC Asb) Ton - - - 1,490,942.73 0.00 0
6.5.(2) Laston Lapis Antara Asbuton (AC-BC Asb) Ton - - - 1,428,435.49 0.00 0
6.5.(3) Laston Lapis Fondasi Asbuton (AC-Base Asb) Ton - - - 1,321,341.53 0.00 0
6.6.(1) CPHMA Kemasa Kantong Ton - - 1,136,562.16 0.00 0
6.7.(1) Lapis Penetrasi Macadam M 3
- - 1,807,248.00 0.00 0
6.7.(2) Lapis Penetrasi Macadam Asbuton M 3
- - 1,414,347.82 0.00 0
Jumlah Harga Pekerjaan DIVISI 6 (masuk pada Rekapitulasi Perkiraan Harga Pekerjaan) 9,316,327.02 56,147,510.83
DIVISI 7. STRUKTUR
7.1 (1) Beton struktur, fc’50 MPa M3 - - - 2,502,751.60 0.00 0
7.1 (2) Beton struktur, fc’45 MPa M3 - - - 2,444,498.19 0.00 0
7.1 (3) Beton struktur, fc’40 MPa M3 - - - 2,379,125.49 0.00 0
7.1 (4) Beton struktur, fc’35 MPa M 3
- - - 2,313,431.52 0.00 0
7.1 (5a) Beton struktur, fc’30 MPa M 3
- - - 2,022,774.89 0.00 0
7.1 (5b) Beton strukutr bervolome besar, fc'30 MPa M 3
- - - 2,310,885.24 0.00 0
7.1 (5c) Beton strukutr memadat sendiri, fc'30 MPa M3 - - - 2,012,954.36 0.00 0
7.1 (6a) Beton struktur, fc’25 Mpa M3 - - - 1,942,984.84 0.00 0
7.1 (6b) Beton struktur bervolume besar, fc’25 Mpa M3 - - - 2,025,484.84 0.00 0
7.1 (6c) Beton struktur memadat sendiri, fc’25 Mpa M3 - - - 1,981,341.60 0.00 0
7.1 (7a) Beton strukur, fc’20 MPa M3 4.5 - 4.5 1,945,421.58 8,754,397.10 0
7.1 (7b) Beton strukut bervolume besar, fc’20 MPa M3 - - - 2,027,921.58 0.00 0
7.1 (7c) Beton strukut memadat sendiri, fc’20 MPa M 3
- - - 2,238,319.23 0.00 0
7.1 (7d) Beton strukut, fc’20 MPa yang dilaksanakan di air M 3
- - - 2,902,379.20 0.00 0
7.1 (8) Beton , fc’15 Mpa M 3
30.0 - 30.0 1,715,725.96 51,471,778.82 0
7.1 (9) Beton Siklop, fc’15 Mpa M3 - - - 812,164.09 0.00 0
7.1 (10) Beton, fc’10 Mpa M3 - - - 1,353,917.61 0.00 0
7.2 (1a) Penyediaan Unit Pracetak Gelagar Tipe I Bentang 16 meter Buah - - - 151,830,935.63 0.00 0
7.2 (1b) Penyediaan Unit Pracetak Gelagar Tipe I Bentang 25 meter Buah - - - 248,655,926.42 0.00 0
7.2 (1c) Penyediaan Unit Pracetak Gelagar Tipe I Bentang … meter Buah - - - - 0.00 0
7.2 (2a) Pemasangan Unit Pracetak Gelagar Tipe I Bentang 16 meter Buah - - 11,908,427.16 0.00 0
7.2 (2b) Pemasangan Unit Pracetak Gelagar Tipe I Bentang 25 meter Buah - - 13,780,476.71 0.00 0
7.2 (2c) Pemasangan Unit Pracetak Gelagar Tipe I Bentang … meter Buah - - - 0.00 0
7.2 (3a) Penyediaan Unit Pracetak Gelagar Tipe U Bentang 16 meter Buah - - 410,769,699.78 0.00 0
7.2 (3b) Penyediaan Unit Pracetak Gelagar Tipe U Bentang … meter Buah - - - 0.00 0
7.2 (4a) Pemasangan Unit Pracetak Gelagar Tipe U Bentang 16 meter Buah - - 13,780,476.71 0.00 0
7.2 (4b) Pemasangan Unit Pracetak Gelagar Tipe U Bentang … meter Buah - - - 0.00 0
7.2.(5) Penyediaan Unit Pracetak Gelagar Box bentang ... meter lebar ……meter Buah - - - 0.00 0
7.2.(6) Pemasangan Unit Pracetak Gelagar Box bentang ... meter lebar ……meter Buah - - - 0.00 0
7.2.(7) Baja Prategang Kg - - 580,328.65 0.00 0
7.2.(8) Penyediaan Pelat Berongga (Voided Slab) Pracetak bentang ….. Meter Buah - - - 0.00 0
7.2.(9) Pemasangan Pelat Berongga (Voided Slab) Pracetak bentang ….. Meter Buah - - - 0.00 0
7.2.(10) Beton Pratekan untuk Diafragma fc' 45 MPa termasuk Pekerjaan pasca-tarik (post-tension) M 3
- - 0.00 0
7.2.(11a) Penyediaan Balok T Beton Pratekan bentang 40m Buah - - 0.00 0
7.2.(11b) Pemasangan Balok T Beton Pratekan bentang 60 m Buah - - 0.00 0
7.2.(12a) Penyediaan Panel Full Depth slab Buah - 1,427,665.96 0.00 0
7.2.(12b) Penyediaan Panel Full Depth slab Buah - 660,848.49 0.00 0
7.3 (1) Baja Tulangan Polos-BjTP 280 Kg - 16,450.64 0.00 0
7.3 (2) Baja Tulangan Sirip BjTS 280 Kg - - - 16,903.84 0.00 0
7.3 (3) Baja Tulangan Sirip BjTS 420A Kg - - - 17,130.44 0.00 0
7.3 (4) Baja Tulangan Sirip BjTS 420B Kg - - - 15,746.38 0.00 0
7.3 (5) Baja Tulangan Sirip BjTS 520 Kg - - - 16,450.64 0.00 0
7.3 (6) Baja Tulangan Sirip BjTS 550 Kg - - - 16,450.64 0.00 0
7.3 (7) Baja Tulangan Sirip BjTS 700 Kg - - - 16,450.64 0.00 0
7.3 (8) Anyaman Kawat Yang Dilas (Welded Wire Mesh) Kg - - - 19,237.18 0.00 0
7.4 (1a) Penyediaan Baja Struktur Grade 250 (Kuat Leleh 250 MPa) Kg - - - 29,600.47 0.00 0
7.4 (1b) Penyediaan Baja Struktur Grade 345 (Kuat Leleh 345 MPa) Kg - - - 19,160.23 0.00 0
7.4 (1c) Penyediaan Baja Struktur Grade 485 (Kuat Leleh 485 MPa) Kg - - - 20,260.23 0.00 0
7.4 (1d) Penyediaan Baja Struktur Grade 690 (Kuat Leleh 690 Mpa Untuk Tebal Pelat < 2,5) Kg - - - 24,660.23 0.00 0
7.4 (1e) Penyediaan Baja Struktur Grade 690 (Kuat Leleh 620 Mpa Untuk Tebal Pelat < 2,5-4,0 inch) Kg - - - 21,360.23 0.00 0
7.4 (2) Pemasangan Baja Struktur Kg - - - 3,111.70 0.00 0
7.4 (3) Penyediaan Struktur Jembatan Rangka Baja Standar …… m Kg - - - 29,610.23 0.00 0
7.4 (4) Pemasangan Jembatan Rangka Baja Standar Panjang ….. M Kg - - - 3,111.70 0.00 0
7.4 (5a) Pemasangan Jembatan Rangka Baja yang disediakan Pengguna Jasa Kg - - - 3,111.70 0.00 0
7.4 (5b) Pengangkutan Bahan Jembatan yang disediakan Pengguna Jasa Kg - - - 29,610.23 0.00 0
7.5.(1) Tiang bor sekan primer diameter 80 cm (fc' > 15 MPa) M1 - - - 1,648,218.44 0.00 0
7.5.(2) Tiang bor sekan sekunder diameter 80 cm (fc' > 30 MPa) M1 - - - 2,808,362.84 0.00 0
7.5.(3) Tiang bor sekan primer diameter 100 cm (fc' > 15MPa) M 1
- - - 2,197,848.16 0.00 0
7.5.(4) Tiang bor sekan sekunder diameter 100 cm (fc' > 30 MPa) M1 - - - 3,330,938.78 0.00 0
7.5.(5) Tiang bor sekan primer diameter 120 cm (fc' > 15 MPa) M1 - - - 2,869,617.83 0.00 0
7.5.(6) Tiang bor sekan sekunder diameter 120 cm (fc' > 30 MPa) M1 - - - 4,213,575.73 0.00 0
7.5.(7) Tiang bor sekan primer diameter 150 cm (fc' > 15 MPa) M1 - - - 4,106,284.72 0.00 0
7.5.(8) Tiang bor sekan sekunder diameter 150 cm (fc' > 15 MPa) M1 - - - 6,038,011.69 0.00 0
7.5.(9) Tiang bor sekan primer diameter …… cm (fc' > 15 MPa) M1 - - - - 0.00 0
7.5.(10) Tiang bor sekan sekunder diameter ….. cm (fc' > 15 MPa) M 1
- - - - 0.00 0
7.6 (1) Fondasi Cerucuk, Penyediaan dan Pemancangan M 1
- - - 62,435.56 0.00 0
7.6 (2) Dinding Turap Kayu Tanpa Pengawetan, Penyediaan dan Pemancangan M 2
- - - 148,926.21 0.00 0
7.6.(3) Dinding Turap Kayu Dengan Pengawetan, Penyediaan dan Pemancangan M 2
- - - 196,157.37 0.00 0
7.6.(4) Dinding Turap Baja, Penyediaan dan Pemancangan M2 - - - 2,777,685.32 0.00 0
7.6.(5) Dinding Turap Beton, Penyediaan dan Pemancangan M2 - - - 737,717.89 0.00 0
7.6.(6) Penyediaan Tiang Pancang Kayu Tanpa Pengawetan Ukuran…… mm M1 - - - 64,033.52 0.00 0
7.6.(7) Penyediaan Tiang Pancang Kayu Dengan Pengawetan Ukuran…… mm M1 - - - 66,821.96 0.00 0
7.6 (8a) Penyediaan Tiang Pancang Baja Diameter 500 mm tebal 10 mm M1 - - - 2,688,314.09 0.00 0
7.6 (8b) Penyediaan Tiang Pancang Baja Diameter …. mm tebal …... mm M 1
- - - - 0.00 0
7.6.(8c) Penyediaan Tiang Pancang Baja Diameter …... mm tebal …… mm M 1
- - - - 0.00 0
7.6.(9a) Penyediaan Tiang Pancang Baja H Beam Ukuran 300 mm x 300 mm x 10 mm x 15 mm M 1
- - - 842,901.01 0.00 0
7.6.(9b) Penyediaan Tiang Pancang Baja H Beam Ukuran …..mm x …….. mm x …….mm x ……... mm M 1
- - - - 0.00 0
7.6.(10a) Penyediaan Tiang Pancang Beton Bertulang Pracetak ukuran 350 mm x 350 mm M1 - - - 769,612.84 0.00 0
7.6.(10b) Penyediaan Tiang Pancang Beton Bertulang Pracetak ukuran ……..mm x ……... mm M1 - - - - 0.00 0
7.6.(11a) Penyediaan Tiang Pancang Beton Pratekan Pracetak ukuran 400 mm x 400 mm M1 - - - 1,070,958.88 0.00 0
7.6.(11b) Penyediaan Tiang Pancang Beton Pratekan Pracetak ukuran ……. mm x ………. mm M1 - - - - 0.00 0
7.6.(12a) Penyediaan Tiang Pancang Beton Pratekan Pracetak diameter 450 mm M1 - - - 773,191.58 0.00 0
7.6.(12b) Penyediaan Tiang Pancang Beton Pratekan Pracetak diameter ……...mm M 1
- - - - 0.00 0
7.6.(13) Pemancangan Tiang Pancang Kayu Ukuran ….. Mm M 1
- - - 330,578.45 0.00 0
7.6.(14a) Pemancangan Tiang Pancang Baja Diameter 500 mm M 1
- - - 286,448.54 0.00 0
7.6.(14b) Pemancangan Tiang Pancang Baja Diameter …….. mm M 1
- - - - 0.00 0
7.6.(15a) Pemancangan Tiang Pancang Baja H beam Ukuran 300 mm x 300 mm x 10 mm x 15 mm M1 - - - 248,927.10 0.00 0
7.6.(15b) Pemancangan Tiang Pancang Baja H beam Ukuran…….. mm x …….. mm x …….. mm x ……... mm M1 - - - - 0.00 0
7.6.(16a) Pemancangan Tiang Pancang Beton Bertulang Pracetak ukuran 350 mm x 350 mm M1 - - - 248,927.10 0.00 0
7.6.(16b) Pemancangan Tiang Pancang Beton Bertulang Pracetak ukuran………. mm x ………... mm M1 - - - - 0.00 0
7.6.(17a) Pemancangan Tiang Pancang Beton Pratekan Pracetak ukuran 400 mm x 400 mm M1 - - - 248,927.10 0.00 0
7.6.(17b) Pemancangan Tiang Pancang Beton Pratekan Pracetak ukuran ………. mm x ….. mm M 1
- - - - 0.00 0
7.6.(18a) Pemancangan Tiang Pancang Beton Pratekan Pracetak diameter 450 mm M 1
- - - 464,787.60 0.00 0
7.6.(18b) Pemancangan Tiang Pancang Beton Pratekan Pracetak diameter ….. mm - - - - 0.00 0
7.6.(19a) Tiang Bor Beton, diameter 800 mm M 1
- - - 2,152,003.72 0.00 0
7.6.(19b) Tiang Bor Beton, diameter ….. mm M1 - - - - 0.00 0
Tambahan Biaya untuk Nomor Mata Pembayaran 7.6.(13)s/d 7.6.(18) bila Tiang Pancang dikerjakan di tempat Yang Berair
7.6.(20) M1
- - - 84,919.50 0.00 0
7.6.(21) Tambahan Biaya untuk Nomor Mata Pembayaran 7.6.(19) Bila Tiang Bor Beton dikerjakan ditempat Yang Berair M1 - - - 135,136.25 0.00 0
7.6.(22) Pengujian Pembebanan Pada Tiang Dengan Diameter sampai 600 mm Buah - - - - 0.00 0
7.6.(23) Pengujian Pembebanan Pada Tiang Dengan Diameter di atas 600 mm Buah - - - - 0.00 0
7.6.(24) Tiang Uji jenis …. Ukuran …… M 1
- - - - 0.00 0
7.6.(25a) Pengujian Pembebanan Statis pada Tiang ukuran / diameter .... Dengan beban hidrolik Cara Beban Siklik Buah - - - - 0.00 0
7.6 (25b) Pengujian Pembebanan Statis pada Tiang ukuran / diameter .... Dengan beban hidrolik Cara Beban Bertahap Buah - - - - 0.00 0
7.6 (26a) Pengujian Pembebanan Statis pada Tiang ukuran / diameter ……. meja beban statis Cara beban Siklik Buah - - - - 0.00 0
7.6 (26b) Pengujian Pembebanan Statis pada Tiang ukuran / diameter ……. meja beban statis Cara beban Bertahap Buah - - - - 0.00 0
7.6 (27a) Pengujian Crosshole sonic logging (CSL) pada Tiang bor beton diameter .... Buah - - - - 0.00 0
7.6 (27b) Pengujian Pembebanan Dinamis Jenis PDLT (Pile Dynamic Load Testing) pada Tiangukuran / diameter .... Buah - - - - 0.00 0
7.6 (28) Pengujian Keutuhan Tiang dengan Pile Integrated Test (PIT) Buah - - - - 0.00 0
7.7.(1) Dinding Sumuran Silinder terpasang, Diameter ……………. M 1
- - - 8,325,593.75 0.00 0
7.9.(1) Pasangan Batu M 3
- - - 745,094.29 0.00 0
7.10.(1) Pasangan Batu Kosong yang Diisi Adukan M3 - - - 587,688.07 0.00 0
7.10.(2) Pasangan Batu Kosong M3 - - - 588,519.98 0.00 0
7.10.(3a) Bronjong dengan kawat yang dilapisi Galvanis M3 - - - 595,946.08 0.00 0
7.10.(3b) Bronjong dengan kawat yang dilapisi PVC M3 - - - 917,113.61 0.00 0
7.10.(4) Tambahan Biaya untuk Anyaman Penulangan Tanah dengan Kawat yang Dilapisi PVC M2 - - - 246,193.44 0.00 0
7.11.(1a) Sambungan Siar Muai Tipe Asphaltic Plug, Fixed M 1
- - - 2,144,634.02 0.00 0
7.11.(1b) Sabungan siar Muai Tipe Asphaltic Plug, Movable M 1
- - - 3,045,197.82 0.00 0
7.11.(2) Sambungan Siar Muai Tipe Silicone Seal M 1
- - - 749,798.88 0.00 0
7.11.(3) Sambungan Siar Muai Tipe Strip seal M1 - - - 1,377,254.76 0.00 0
7.11.(4) Sambungan Siar Muai Tipe Compression Seal M1 - - - 1,476,058.31 0.00 0
7.11.(5) Sambungan Siar Muai Expansion Joint Tipe Modular, lebar …….. M1 - - - 1,193,445.90 0.00 0
7.11.(6) Sambungan Siar Muai Expansion Joint Tipe Finger Plate, lebar …….. M1 - - - 4,146,948.94 0.00 0
7.11.(7) Sambungan Siar Muai Expansion Tipe Karet dengan Lebar Celah …….. Cm M3 - - - 1,934,040.99 0.00 0
7.11.(8) Joint Filler untuk Sambungan Konstruksi M3 - - - 2,513,531.38 0.00 0
7.11.(9) Sambungan Siar Muai Tipe Modular, Lebar …….. M3 - - - 317,548.31 0.00 0
7.12.(1a) Landasan Logam Tipe Fixed Buah - - - 2,103,394.37 0.00 0
7.12.(1b) Landasan Logam Tipe Moveable Buah - - - 2,270,352.23 0.00 0
7.12.(1c) Landasan Logam Tipe ……. Buah - - - - 0.00 0
7.12.(2) Landasan Elastomerik Karet Alam Berlapis Baja Ukuran ….. Mm x ….. Mm x…….. Mm Buah - - - 1,248,452.23 0.00 0
7.12.(3) Landasan Elastomerik Karet Sintetis Berlapis Baja Ukuran ….. Mm x ….. Mm x…….. Mm Buah - - - 992,152.23 0.00 0
7.12.(4) Landasan karet Strip M1 - - - 305,214.17 0.00 0
7.12.(5) Landasan Tipe Logam Berongga (Pot Bearing) Buah - - - 13,236,557.73 0.00 0
7.12.(6) Landasan Tipe Logam Jenis Spherical Buah - - - 14,651,857.50 0.00 0
7.13.(1) Sandaran (Railing) M1 - - - 91,595.08 0.00 0
7.14.(1) Papan Nama Jembatan M 1
2.0 2.0 4.0 354,119.18 708,238.36 708,238
7.15.(1) Pembongkaran Pasangan Batu M 3
- 86.8 86.8 359,382.48 0.00 31,194,399
7.15.(2) Pembongkaran Beton M3 - - - 530,396.11 0.00 0
7.15.(3) Pembongkaran Beton Pratekan M3 - - - 455,988.14 0.00 0
7.15.(4) Pembongkaran Bangunan Gedung M2 - - - 275,488.97 0.00 0
7.15.(5) Pembongkaran Rangka Baja M2 - - - 1,116,957.05 0.00 0
7.15.(6) Pembongkaran Balok Baja (Steel Stingers) M1 - - - 411,697.48 0.00 0
7.15.(7) Pembongkaran Lantai Jembatan Kayu M2 - - - 166,168.67 0.00 0
7.15.(8) Pembongkaran Jembatan Kayu M2 - - - 46,066.43 0.00 0
7.15.(9) Pengangkutan Hasil Bongkaran yang melebihi 5 km M 3/ km
- - - - 0.00 0
7.16.(1) Dreck drain Buah - - - 138,095.99 0.00 0
7.16.(2a) Pipa Drainase Baja diameter 150 mm M 1
- - - 274,483.36 0.00 0
7.16.(2b) Pipa Drainase Baja diameter ……. Mm M1 - - - - 0.00 0
7.16.(3a) Pipa Drainase PVC diameter 150 mm M1 - - - 83,885.86 0.00 0
7.16.(3b) Pipa Drainase PVC diameter …… mm M1 - - - - 0.00 0
7.16.(4) Pipa Penyalur PVC M1 - - - 83,885.86 0.00 0
7.11.(1) Pengujian Pembebanan Jembatan Buah Jembatan - - - - 0.00 0
- - - 0.00 0
Jumlah Harga Pekerjaan DIVISI 7 (masuk pada Rekapitulasi Perkiraan Harga Pekerjaan) 60,934,414.28 31,902,637.62
Jumlah Harga Pekerjaan DIVISI 8 (masuk pada Rekapitulasi Perkiraan Harga Pekerjaan) #REF! #REF!
Jumlah Harga Pekerjaan DIVISI 9 (masuk pada Rekapitulasi Perkiraan Harga Pekerjaan) 3,067,738.69 6,916,141.62
Jumlah Harga Pekerjaan DIVISI 10 (masuk pada Rekapitulasi Perkiraan Harga Pekerjaan) 7,776,023.58 84,639,282.14
###
REKAPITULASI
PERKIRAAN HARGA PEKERJAAN
Jumlah Harga
No. Divisi Uraian Pekerjaan
(Rupiah)
1 Umum 599,200,000.00
2 Drainase 11,112,746,186.50
3 Pekerjaan Tanah Dan Geosintetik 639,337,115.63
4 Pelebaran Preventif 977,109,252.00
5 Pekerasan Berbutir Dan Perkerasan Beton Semen 40,030,165,150.12
6 Perkerasan Aspal 5,844,824,085.98
7 Struktur 608,805,038.58
8 Rehabilitasi Jembatan 150,699,600.00
9 Pekerjaan Harian Dan Pekerjaan Lain-Lain 1,964,831,820.45
10 Pekerjaan Pemeliharaan Kinerja 1,246,840,232.52
(A) Jumlah Harga Pekerjaan ( termasuk Biaya Umum dan Keuntungan ) 63,174,558,481.79
(B) Pajak Pertambahan Nilai ( PPN ) = 10% x (A) 6,317,455,848.18
(C) JUMLAH TOTAL HARGA PEKERJAAN = (A) + (B) 69,492,014,329.97
(D) DIBULATKAN 69,492,010,000.00
Terbilang : Enam Puluh Sembilan Milyar Empat Ratus Sembilan Puluh Dua Juta Sepuluh Ribu Rupiah
REKAPITULASI
PERKIRAAN HARGA PEKERJAAN
Pagu
Total
Harga
No. Mata Harga Satuan KUANTITAS
Uraian Satuan
Pembayaran (Rupiah) TOTAL
(Rupiah)
a b c e d f =d x e
DIVISI 1. UMUM
1.2 Mobilisasi LS 160,300,000.00 1.00 160,300,000.00
1.8.(1) Manajemen dan Keselamatan Lalu Lintas LS 103,400,000.00 1.00 103,400,000.00
1.17.(1a) Pengujian pH Buah 50,000.00 6.00 300,000.00
1.17.(1b) Pengujian Oksigen Terlarut (DO) Buah 50,000.00 6.00 300,000.00
1.17.(1c) Pengujian Zat Padat Terlarut (TDS) Buah 50,000.00 6.00 300,000.00
1.17.(1d) Pengujian Zat Tersuspensi (TSS) Buah 50,000.00 6.00 300,000.00
1.17.(1e) Pengujian Biological Oxygen Demand (BOD) Buah 50,000.00 6.00 300,000.00
1.17.(1f) Pengujian Chemical Oxygen Demand (COD) Buah 50,000.00 6.00 300,000.00
1.17.(1g) Pengujian Coliform Buah 100,000.00 6.00 600,000.00
1.17.(1h) Pengujian E. Coli Buah 50,000.00 6.00 300,000.00
1.17.(1i) Pengujian Destruksi Cu, Pb, Cd, Ni, Fe, Zn, Ag, Co, Mn Buah 400,000.00 6.00 2,400,000.00
1.17.(1j) Pengujian Temperatur (Suhu) Buah 50,000.00 6.00 300,000.00
1.17.(2a) Pengujian Vibrasi Lingkungan untuk Kenyamanan dan Kesehatan Buah 1,000,000.00 6.00 6,000,000.00
1.17.(2b) Pengujian tingkat getaran kendaraan bermotor Buah 50,000.00 6.00 300,000.00
1.17.(3a) Pengujian NoX Buah 200,000.00 6.00 1,200,000.00
1.17.(3b) Pengujian Sulfurdioksida (SO2) Buah 150,000.00 6.00 900,000.00
1.17.(3c) Pengujian Karbondioksida (CO2) Buah 150,000.00 6.00 900,000.00
1.17.(3d) Pengujian Hidro Carbon (HC)-CH4 Buah 150,000.00 6.00 900,000.00
1.17.(3f) Pengujian Total Partikulat (TSP) - Debu Buah 500,000.00 6.00 3,000,000.00
1.17.(3g) Pengujian Timah Hitam (Pb) Buah 50,000.00 6.00 300,000.00
1.17.(3h) Pengujian Parameter Udara Emisi dan Ambien lainnya : ………….. Buah 50,000.00 6.00 300,000.00
1.19 Keselamatan dan Kesehatan Kerja LS 174,900,000.00 1.00 174,900,000.00
1.21 Manajemen Mutu LS 141,400,000.00 1.00 141,400,000.00
Jumlah Harga Pekerjaan DIVISI 1 (masuk pada Rekapitulasi Perkiraan Harga Pekerjaan) 599,200,000.00
DIVISI 2. DRAINASE
2.1.(1) Galian untuk Selokan Drainase dan Saluran Air M3 41,921.47 92.73 3,887,377.79
2.2.(1) Pasangan Batu dengan Mortar M3 817,427.78 48.22 39,416,367.42
2.3.(1) Gorong-gorong Pipa Beton Tanpa Tulangan diameter dalam 20 cm M1 186,664.65 400.00 74,665,860.97
2.3.(15) Gorong-gorong Kotak Beton Bertulang, ukuran dalam 200 cm x 100 cm M1 5,334,761.58 87.00 464,124,257.59
2.3.(21) Gorong-gorong Kotak Beton Bertulang, ukuran dalam 500 cm x 250 cm M1 54,988,868.56 12.00 659,866,422.72
2.3.(26) Saluran berbentuk U Tipe DS 3 M1 1,101,010.00 6,958.00 7,660,827,580.00
2.3.(27) Saluran berbentuk U Tipe DS 3a (dengan tutup) M1 1,299,000.00 250.00 324,750,000.00
2.3.(29) Saluran berbentuk U Tipe DS 4a (dengan tutup) M1 1,472,819.00 1,280.00 1,885,208,320.00
Jumlah Harga Pekerjaan DIVISI 2 (masuk pada Rekapitulasi Perkiraan Harga Pekerjaan) 11,112,746,186.50
###
DIVISI 3. PEKERJAAN TANAH DAN GEOSINTETIK
3.1.(1) Galian Biasa M3 41,921.47 5,168.70 216,679,495.37
3.1.(7) Galian Perkerasan Beraspal dengan Cold Milling Machine M3 477,210.92 19.64 9,372,422.55
3.1.(10). Galian Perkerasan Beton M3 382,562.08 125.00 47,820,259.94
3.2.(1a) Timbunan Biasa dari sumber galian M3 264,138.09 642.00 169,576,656.25
3.2.(2a) Timbunan Pilihan dari sumber galian M3 288,972.02 150.00 43,345,803.16
3.3.(1) Penyiapan Badan Jalan M2 10,645.48 12,148.00 129,321,264.23
3.4.(2) Pemotongan Pohon Pilihan diameter 15 – 30 cm buah 122,977.93 10.00 1,229,779.32
3.4.(3) Pemotongan Pohon Pilihan diameter > 30 – 50 cm buah 395,981.21 10.00 3,959,812.09
3.4.(4) Pemotongan Pohon Pilihan diameter > 50 – 75 cm buah 987,045.54 10.00 9,870,455.40
3.4.(5) Pemotongan Pohon Pilihan diameter > 75 cm buah 1,632,233.46 5.00 8,161,167.31
Jumlah Harga Pekerjaan DIVISI 3 (masuk pada Rekapitulasi Perkiraan Harga Pekerjaan) 639,337,115.63
Jumlah Harga Pekerjaan DIVISI 4 (masuk pada Rekapitulasi Perkiraan Harga Pekerjaan) 977,109,252.00
DAFTAR KUANTITAS HARGA
Pagu
Total
Harga
No. Mata Harga Satuan KUANTITAS
Uraian Satuan
Pembayaran (Rupiah) TOTAL
(Rupiah)
a b c e d f =d x e
Jumlah Harga Pekerjaan DIVISI 5 (masuk pada Rekapitulasi Perkiraan Harga Pekerjaan) 40,030,165,150.12
Jumlah Harga Pekerjaan DIVISI 6 (masuk pada Rekapitulasi Perkiraan Harga Pekerjaan) 5,844,824,085.98
DIVISI 7. STRUKTUR
7.1 (5a) Beton struktur, fc’30 MPa M3 1,608,410.80 32.76 52,691,537.74
7.1 (10) Beton, fc’10 Mpa M3 1,452,674.69 2.40 3,486,419.26
7.3 (1) Baja Tulangan Polos-BjTP 280 Kg 17,020.00 250.00 4,255,000.00
7.3 (3) Baja Tulangan Sirip BjTS 420A Kg 15,678.33 2,880.72 45,164,888.40
7.3 (8) Anyaman Kawat Yang Dilas (Welded Wire Mesh) Kg 19,463.75 500.00 9,731,875.00
7.4 (1b) Penyediaan Baja Struktur Grade 345 (kuat leleh 345 Mpa) Kg 25,000.00 402.40 10,060,000.00
7.9.(1) Pasangan Batu M3 740,977.66 562.40 416,725,837.66
7.10.(1) Pasangan Batu Kosong yang Diisi Adukan M3 763,836.59 13.20 10,082,643.00
7.10.(3a) Bronjong dengan kawat yang dilapisi Galvanis M3 552,230.00 100.00 55,223,000.00
7.14.(1) Papan Nama Jembatan Buah 691,918.76 2.00 1,383,837.52
Jumlah Harga Pekerjaan DIVISI 7 (masuk pada Rekapitulasi Perkiraan Harga Pekerjaan) 608,805,038.58
DAFTAR KUANTITAS HARGA
Pagu
Total
Harga
No. Mata Harga Satuan KUANTITAS
Uraian Satuan
Pembayaran (Rupiah) TOTAL
(Rupiah)
a b c e d f =d x e
Jumlah Harga Pekerjaan DIVISI 8 (masuk pada Rekapitulasi Perkiraan Harga Pekerjaan) 150,699,600.00
###
Jumlah Harga Pekerjaan DIVISI 9 (masuk pada Rekapitulasi Perkiraan Harga Pekerjaan) 1,964,831,820.45
###
###
DIVISI 10. PEKERJAAN PEMELIHARAAN KINERJA
10.1.(1) Galian pada Saluran Air atau Lereng untuk Pemeliharaan M3 41,921.47 322.22 13,507,935.65
10.1.(2) Timbunan Pilihan pada Lereng Tepi Saluran untuk Pemeliharaan M3 288,972.02 99.80 28,839,407.71
10.1.(3) Pebaikan Pasangan Batu dengan Mortar M3 740,977.66 67.30 49,867,796.72
10.1.(4) Perbaikan Lapis Fondasi Agregat Kelas A M3 305,975.57 3.50 1,070,914.49
10.1.(5) Perbaikan Lapis Fondasi Agregat Kelas B M3 270,726.80 16.40 4,439,919.49
10.1.(6) Perbaikan Lapis Fondasi Agregat Kelas S M3 238,380.17 121.30 28,915,514.46
10.1.(7) Perbaikan dan Perataan Permukaan JalanTanah M2 10,645.48 5,000.00 53,227,388.96
10.1.(9) Perbaikan Campuran Aspal Panas M3 3,500,000.00 0.90 3,150,000.00
10.1.(14) Perbaikan Perkerasan Beton Semen M3 1,770,900.00 73.06 129,381,954.00
10.1.(15) Perbaikan Lapis Fondasi Bawah Beton Kurus M3 1,098,099.40 24.50 26,903,435.42
10.1.(16) Perbaikan Pasangan Batu M3 740,977.66 28.40 21,043,765.63
10.1.(17) Pengecatan Kereb pada Trotoar atau Median M2 50,000.00 200.00 10,000,000.00
10.1.(18) Perbaikan Rel Pengaman M1 30,000.00 200.00 6,000,000.00
10.1.(19) Pembersihan Patok Buah 15,000.00 27.00 405,000.00
10.1.(20) Pembersihan Rambu Buah 15,000.00 74.00 1,110,000.00
10.1.(21) Pembersihan Drainase M1 20,000.00 14,530.00 290,600,000.00
10.1.(22) Pengendalian Tanaman M2 700.00 643,396.00 450,377,200.00
10.2.(1) Pemeliharaan Kinerja Jembatan Serdang bentang 7.00 m LS 5,000,000.00 1.00 5,000,000.00
10.2.(2) Pemeliharaan Kinerja Jembatan Trumix Seruni bentang 9.00 m LS 7,500,000.00 1.00 7,500,000.00
10.2.(3) Pemeliharaan Kinerja Jembatan Fly Over Seruni bentang 68.30 m LS 40,000,000.00 1.00 40,000,000.00
10.2.(4) Pemeliharaan Kinerja Jembatan Serdang Terate bentang 36.50 m LS 20,000,000.00 1.00 20,000,000.00
10.2.(5) Pemeliharaan Kinerja Jembatan Serdang Terate II Amnonim bentang 7.00 m LS 5,000,000.00 1.00 5,000,000.00
10.2.(6) Pemeliharaan Kinerja Jembatan Terate III bentang 7.00 m LS 5,000,000.00 1.00 5,000,000.00
10.2.(7) Pemeliharaan Kinerja Jembatan Grenyang bentang 8.00 m LS 5,500,000.00 1.00 5,500,000.00
10.2.(8) Pemeliharaan Kinerja Jembatan Ragas bentang 7.10 m LS 5,000,000.00 1.00 5,000,000.00
10.2.(9) Pemeliharaan Kinerja Jembatan Ragas II bentang 7.00 m LS 5,000,000.00 1.00 5,000,000.00
10.2.(10) Pemeliharaan Kinerja Jembatan Pangoreng bentang 26 m LS 15,000,000.00 1.00 15,000,000.00
10.2.(11) Pemeliharaan Kinerja Jembatan Cicegah bentang 7.60 m LS 5,000,000.00 1.00 5,000,000.00
10.2.(12) Pemeliharaan Kinerja Jembatan Lebak Gede I bentang 6.00 m LS 5,000,000.00 1.00 5,000,000.00
10.2.(13) Pemeliharaan Kinerja Jembatan Lebak Gede II bentang 6.00 m LS 5,000,000.00 1.00 5,000,000.00
Jumlah Harga Pekerjaan DIVISI 10 (masuk pada Rekapitulasi Perkiraan Harga Pekerjaan) 1,246,840,232.52
Daftar 1 : Mata Pembayaran Umum
Pagu
Jumlah
Harga-Harga
No. Mata Harga Satuan Total Perkiraan
Uraian Satuan
Pembayaran (Rupiah) Kuantitas
(Rupiah)
a b c e d f =d x e
DIVISI 1. UMUM
1.2 Mobilisasi LS 160,300,000.00 1.00 160,300,000.00
1.17.(1a) Pengujian pH Buah 50,000.00 6.00 300,000.00
1.17.(1b) Pengujian Oksigen Terlarut (DO) Buah 50,000.00 6.00 300,000.00
1.17.(1c) Pengujian Zat Padat Terlarut (TDS) Buah 50,000.00 6.00 300,000.00
1.17.(1d) Pengujian Zat Tersuspensi (TSS) Buah 50,000.00 6.00 300,000.00
1.17.(1e) Pengujian Biological Oxygen Demand (BOD) Buah 50,000.00 6.00 300,000.00
1.17.(1f) Pengujian Chemical Oxygen Demand (COD) Buah 50,000.00 6.00 300,000.00
1.17.(1g) Pengujian Coliform Buah 100,000.00 6.00 600,000.00
1.17.(1h) Pengujian E. Coli Buah 50,000.00 6.00 300,000.00
1.17.(1i) Pengujian Destruksi Cu, Pb, Cd, Ni, Fe, Zn, Ag, Co, Mn Buah 400,000.00 6.00 2,400,000.00
1.17.(1j) Pengujian Temperatur (Suhu) Buah 50,000.00 6.00 300,000.00
1.17.(2a) Pengujian Vibrasi Lingkungan untuk Kenyamanan dan Kesehatan Buah 1,000,000.00 6.00 6,000,000.00
1.17.(2b) Pengujian tingkat getaran kendaraan bermotor Buah 50,000.00 6.00 300,000.00
1.17.(3a) Pengujian NoX Buah 200,000.00 6.00 1,200,000.00
1.17.(3b) Pengujian Sulfurdioksida (SO2) Buah 150,000.00 6.00 900,000.00
1.17.(3c) Pengujian Karbondioksida (CO2) Buah 150,000.00 6.00 900,000.00
1.17.(3d) Pengujian Hidro Carbon (HC)-CH4 Buah 150,000.00 6.00 900,000.00
1.17.(3f) Pengujian Total Partikulat (TSP) - Debu Buah 500,000.00 6.00 3,000,000.00
1.17.(3g) Pengujian Timah Hitam (Pb) Buah 50,000.00 6.00 300,000.00
1.17.(3h) Pengujian Parameter Udara Emisi dan Ambien lainnya : ………….. Buah 50,000.00 6.00 300,000.00
1.21 Manajemen Mutu LS 141,400,000.00 1.00 141,400,000.00
Jumlah Harga Pekerjaan DIVISI 1 (masuk pada Rekapitulasi Perkiraan Harga Pekerjaan) Err:509
Pagu
Jumlah
Harga-Harga
No. Mata Harga Satuan Total Perkiraan
Uraian Satuan
Pembayaran (Rupiah) Kuantitas
(Rupiah)
a b c e d f =d x e
DIVISI 2. DRAINASE
2.3.(26) Saluran berbentuk U Tipe DS 3 M1 1,101,010.00 6,958.00 7,660,827,580.00
Jumlah Harga Pekerjaan DIVISI 2 (masuk pada Rekapitulasi Perkiraan Harga Pekerjaan) 7,660,827,580.00
Jumlah Harga Pekerjaan DIVISI 5 (masuk pada Rekapitulasi Perkiraan Harga Pekerjaan) 31,678,301,925.00
Jumlah Harga Pekerjaan DIVISI 6 (masuk pada Rekapitulasi Perkiraan Harga Pekerjaan) 3,074,058,180.33
Pagu
Jumlah
Harga-Harga
No. Mata Harga Satuan Total Perkiraan
Uraian Satuan
Pembayaran (Rupiah) Kuantitas
(Rupiah)
a b c e d f =d x e
DIVISI 2. DRAINASE
2.1.(1) Galian untuk Selokan Drainase dan Saluran Air M3 41,921.47 92.73 3,887,377.79
2.2.(1) Pasangan Batu dengan Mortar M3 817,427.78 48.22 39,416,367.42
2.3.(1) Gorong-gorong Pipa Beton Tanpa Tulangan diameter dalam 20 cm M1 186,664.65 400.00 74,665,860.97
2.3.(15) Gorong-gorong Kotak Beton Bertulang, ukuran dalam 200 cm x 100 cm M1 5,334,761.58 87.00 464,124,257.59
2.3.(21) Gorong-gorong Kotak Beton Bertulang, ukuran dalam 500 cm x 250 cm M 1
54,988,868.56 12.00 659,866,422.72
2.3.(27) Saluran berbentuk U Tipe DS 3a (dengan tutup) M1 1,299,000.00 250.00 324,750,000.00
2.3.(29) Saluran berbentuk U Tipe DS 4a (dengan tutup) M1 1,472,819.00 1,280.00 1,885,208,320.00
Jumlah Harga Pekerjaan DIVISI 2 (masuk pada Rekapitulasi Perkiraan Harga Pekerjaan) Err:509
###
DIVISI 3. PEKERJAAN TANAH DAN GEOSINTETIK
3.1.(1) Galian Biasa M 3
41,921.47 5,168.70 216,679,495.37
3.1.(7) Galian Perkerasan Beraspal dengan Cold Milling Machine M3 477,210.92 19.64 9,372,422.55
3.1.(10). Galian Perkerasan Beton M3 382,562.08 125.00 47,820,259.94
3.2.(1a) Timbunan Biasa dari sumber galian M3 264,138.09 642.00 169,576,656.25
3.2.(2a) Timbunan Pilihan dari sumber galian M3 288,972.02 150.00 43,345,803.16
3.3.(1) Penyiapan Badan Jalan M2 10,645.48 12,148.00 129,321,264.23
3.4.(2) Pemotongan Pohon Pilihan diameter 15 – 30 cm buah 122,977.93 10.00 1,229,779.32
3.4.(3) Pemotongan Pohon Pilihan diameter > 30 – 50 cm buah 395,981.21 10.00 3,959,812.09
3.4.(4) Pemotongan Pohon Pilihan diameter > 50 – 75 cm buah 987,045.54 10.00 9,870,455.40
3.4.(5) Pemotongan Pohon Pilihan diameter > 75 cm buah 1,632,233.46 5.00 8,161,167.31
Jumlah Harga Pekerjaan DIVISI 3 (masuk pada Rekapitulasi Perkiraan Harga Pekerjaan) Err:509
Jumlah Harga Pekerjaan DIVISI 4 (masuk pada Rekapitulasi Perkiraan Harga Pekerjaan) Err:509
Daftar 4 : Mata Pembayaran Lainnya
Pagu
Jumlah
Harga-Harga
No. Mata Harga Satuan Total Perkiraan
Uraian Satuan
Pembayaran (Rupiah) Kuantitas
(Rupiah)
a b c e d f =d x e
Jumlah Harga Pekerjaan DIVISI 5 (masuk pada Rekapitulasi Perkiraan Harga Pekerjaan) Err:509
Jumlah Harga Pekerjaan DIVISI 6 (masuk pada Rekapitulasi Perkiraan Harga Pekerjaan) Err:509
DIVISI 7. STRUKTUR
7.1 (5a) Beton struktur, fc’30 MPa M3 1,608,410.80 32.76 52,691,537.74
7.1 (10) Beton, fc’10 Mpa M3 1,452,674.69 2.40 3,486,419.26
7.3 (1) Baja Tulangan Polos-BjTP 280 Kg 17,020.00 250.00 4,255,000.00
7.3 (3) Baja Tulangan Sirip BjTS 420A Kg 15,678.33 2,880.72 45,164,888.40
7.3 (8) Anyaman Kawat Yang Dilas (Welded Wire Mesh) Kg 19,463.75 500.00 9,731,875.00
7.4 (1b) Penyediaan Baja Struktur Grade 345 (kuat leleh 345 Mpa) Kg 25,000.00 402.40 10,060,000.00
7.9.(1) Pasangan Batu M3 740,977.66 562.40 416,725,837.66
7.10.(1) Pasangan Batu Kosong yang Diisi Adukan M3 763,836.59 13.20 10,082,643.00
7.10.(3a) Bronjong dengan kawat yang dilapisi Galvanis M3 552,230.00 100.00 55,223,000.00
7.14.(1) Papan Nama Jembatan Buah 691,918.76 2.00 1,383,837.52
Jumlah Harga Pekerjaan DIVISI 7 (masuk pada Rekapitulasi Perkiraan Harga Pekerjaan) Err:509
Jumlah Harga Pekerjaan DIVISI 8 (masuk pada Rekapitulasi Perkiraan Harga Pekerjaan) Err:509
Daftar 4 : Mata Pembayaran Lainnya
Pagu
Jumlah
Harga-Harga
No. Mata Harga Satuan Total Perkiraan
Uraian Satuan
Pembayaran (Rupiah) Kuantitas
(Rupiah)
a b c e d f =d x e
###
Jumlah Harga Pekerjaan DIVISI 9 (masuk pada Rekapitulasi Perkiraan Harga Pekerjaan) Err:509
###
###
DIVISI 10. PEKERJAAN PEMELIHARAAN KINERJA
10.1.(1) Galian pada Saluran Air atau Lereng untuk Pemeliharaan M3 41,921.47 322.22 13,507,935.65
10.1.(2) Timbunan Pilihan pada Lereng Tepi Saluran untuk Pemeliharaan M3 288,972.02 99.80 28,839,407.71
10.1.(3) Pebaikan Pasangan Batu dengan Mortar M3 740,977.66 67.30 49,867,796.72
10.1.(4) Perbaikan Lapis Fondasi Agregat Kelas A M 3
305,975.57 3.50 1,070,914.49
10.1.(5) Perbaikan Lapis Fondasi Agregat Kelas B M3 270,726.80 16.40 4,439,919.49
10.1.(6) Perbaikan Lapis Fondasi Agregat Kelas S M3 238,380.17 121.30 28,915,514.46
10.1.(7) Perbaikan dan Perataan Permukaan JalanTanah M2 10,645.48 5,000.00 53,227,388.96
10.1.(9) Perbaikan Campuran Aspal Panas M3 3,500,000.00 0.90 3,150,000.00
10.1.(14) Perbaikan Perkerasan Beton Semen M3 1,770,900.00 73.06 129,381,954.00
10.1.(15) Perbaikan Lapis Fondasi Bawah Beton Kurus M3 1,098,099.40 24.50 26,903,435.42
10.1.(16) Perbaikan Pasangan Batu M3 740,977.66 28.40 21,043,765.63
10.1.(17) Pengecatan Kereb pada Trotoar atau Median M2 50,000.00 200.00 10,000,000.00
10.1.(18) Perbaikan Rel Pengaman M1 30,000.00 200.00 6,000,000.00
10.1.(19) Pembersihan Patok Buah 15,000.00 27.00 405,000.00
10.1.(20) Pembersihan Rambu Buah 15,000.00 74.00 1,110,000.00
10.1.(21) Pembersihan Drainase M1 20,000.00 14,530.00 290,600,000.00
10.1.(22) Pengendalian Tanaman M2 700.00 643,396.00 450,377,200.00
10.2.(1) Pemeliharaan Kinerja Jembatan Serdang bentang 7.00 m LS 5,000,000.00 1.00 5,000,000.00
10.2.(2) Pemeliharaan Kinerja Jembatan Trumix Seruni bentang 9.00 m LS 7,500,000.00 1.00 7,500,000.00
10.2.(3) Pemeliharaan Kinerja Jembatan Fly Over Seruni bentang 68.30 m LS 40,000,000.00 1.00 40,000,000.00
10.2.(4) Pemeliharaan Kinerja Jembatan Serdang Terate bentang 36.50 m LS 20,000,000.00 1.00 20,000,000.00
10.2.(5) Pemeliharaan Kinerja Jembatan Serdang Terate II Amnonim bentang 7.00 m LS 5,000,000.00 1.00 5,000,000.00
10.2.(6) Pemeliharaan Kinerja Jembatan Terate III bentang 7.00 m LS 5,000,000.00 1.00 5,000,000.00
10.2.(7) Pemeliharaan Kinerja Jembatan Grenyang bentang 8.00 m LS 5,500,000.00 1.00 5,500,000.00
10.2.(8) Pemeliharaan Kinerja Jembatan Ragas bentang 7.10 m LS 5,000,000.00 1.00 5,000,000.00
10.2.(9) Pemeliharaan Kinerja Jembatan Ragas II bentang 7.00 m LS 5,000,000.00 1.00 5,000,000.00
10.2.(10) Pemeliharaan Kinerja Jembatan Pangoreng bentang 26 m LS 15,000,000.00 1.00 15,000,000.00
10.2.(11) Pemeliharaan Kinerja Jembatan Cicegah bentang 7.60 m LS 5,000,000.00 1.00 5,000,000.00
10.2.(12) Pemeliharaan Kinerja Jembatan Lebak Gede I bentang 6.00 m LS 5,000,000.00 1.00 5,000,000.00
10.2.(13) Pemeliharaan Kinerja Jembatan Lebak Gede II bentang 6.00 m LS 5,000,000.00 1.00 5,000,000.00
-
Jumlah Harga Pekerjaan DIVISI 10 (masuk pada Rekapitulasi Perkiraan Harga Pekerjaan) Err:509
Jumlah
Harga-Harga
No. Mata Harga Satuan Total Perkiraan Bobot
Uraian Satuan
Pembayaran (Rupiah) Kuantitas Komulatif (%)
(Rupiah)
a b c e d f =d x e
DIVISI 2. DRAINASE
2.3.(26) Saluran berbentuk U Tipe DS 3 M1 1,101,010.00 6,958.00 7,660,827,580.00 12.13
Jumlah Harga Pekerjaan DIVISI 2 (masuk pada Rekapitulasi Perkiraan Harga Pekerjaan) 7,660,827,580.00
Jumlah Harga Pekerjaan DIVISI 5 (masuk pada Rekapitulasi Perkiraan Harga Pekerjaan) 39,964,572,416.90
Jumlah Harga Pekerjaan DIVISI 6 (masuk pada Rekapitulasi Perkiraan Harga Pekerjaan) 3,074,058,180.33
III.
D. MOBILISASI FASILITAS LABORATORIUM set 1 5,000,000.00 5,000,000.00
1 Ruang Laboratorium (sesuai Gambar) M2 -
3
2 Soil & Aggregate Testing Set -
Compaction Test 5
CBR Test 6
Specific Gravity 7
Atterberg Limits 8
Grain Size Analysis 9
Field Density Test by Sand Cone Methode 10
Moisture Content 11
Abrasion of Aggregate by Los Angeles Machine
IV.
3 Bituminous Testing ###
Marshall Asphalt Test ###
Extraction Test, Centrifuge/Refflux Method set -
Specific Gravity for Coarse Aggregate ###
Specific Gravity for Fine Aggregate
Mix Air Void Content (Accurate Method) set -
Core Drill set -
Metal Thermometer ###
Accessories and Tolls ###
Penetration Test
Softening Point VI.
Refusal Density Compactor set -
4 Concrete Testing
Slump Cone buah -
Cylinder/Cube Mould for Compressive Strength buah -
Beam Mould for Flexural Strength (RIGID) buah -
Crushing Machine buah -
B. PERALATAN
contoh :
1 ASPHALT FINISHER E02 Unit 1.00 4,000,000.00 4,000,000.00
2 COMPRESSOR 4000-6500 L\M E05 Unit 1.00 500,000.00 500,000.00
3 CONCRETE MIXER 0.3-0.6 M3 E06 Unit 2.00 500,000.00 1,000,000.00
4 DUMP TRUCK 3 - 4 M3 E08 Unit 6.00 500,000.00 3,000,000.00
5 DUMP TRUCK 6-8 M3 E09 Unit 5.00 500,000.00 2,500,000.00
6 EXCAVATOR 80-140 HP E10 Unit 1.00 3,000,000.00 3,000,000.00
7 FLAT BED TRUCK 3-4 TON E11 Unit 1.00 500,000.00 500,000.00
8 GENERATOR SET E12 Unit 1.00 500,000.00 500,000.00
9 MOTOR GRADER >100 HP E13 Unit 1.00 3,000,000.00 3,000,000.00
10 THREE WHEEL ROLLER 6-8 T E16 Unit 1.00 3,000,000.00 3,000,000.00
11 TANDEM ROLLER 6-8 T. E17 Unit 1.00 3,000,000.00 3,000,000.00
12 TIRE ROLLER 8-10 T. E18 Unit 2.00 3,000,000.00 6,000,000.00
13 VIBRATORY ROLLER 10-12 T. E19 Unit 1.00 3,000,000.00 3,000,000.00
14 CONCRETE VIBRATOR E20 Unit 2.00 300,000.00 600,000.00
15 WATER TANKER 3000-4500 L. E23 Unit 1.00 500,000.00 500,000.00
16 PEDESTRIAN ROLLER E24 Unit 1.00 500,000.00 500,000.00
17 TAMPER E25 Unit 1.00 500,000.00 500,000.00
18 JACK HAMMER E26 Unit 2.00 300,000.00 600,000.00
19 FULVI MIXER E27 Unit 1.00 500,000.00 500,000.00
20 TRAILER 20 TON E29 Unit 1.00 1,000,000.00 1,000,000.00
21 WELDING SET E32 Unit 1.00 200,000.00 200,000.00
22 COLD MILLING MACHINE E37 Unit 1.00 4,000,000.00 4,000,000.00
23 ROCK DRILL BREAKER E36 Unit 1.00 500,000.00 500,000.00
B. URUTAN KERJA
1 Penyedia setelah menerima SPMK mengusulkan personil
Tenaga Ahli Mutu Pekerjaan sbg Manajer Kendali Mutu
2 Tenaga Ahli dibantu oleh Asisten Kendali Mutu yang
berpengalaman dibidangnya dan tenaga pendukung
3 Membuat RMK dan laporan mutu yg disetujui PPK
4 Melakukan pengendalian mutu semua pekerjaan dan
membuat laporan secara berkala
C. TENAGA / PERSONIL
Catatan : 1. Harga Satuan Personil tersebut sudah termasuk seluruh pajak dan bea (kecuali PPN),
Asuransi Tenaga Kerja dan pengeluaran lainnya.
2. Biaya tersebut sudah termasuk biaya pembuatan laporan yang terkait dengan mutu pekerjaan
3. Biaya satuan tersebut sudah termasuk kebutuhan perlengkapan dan peralatan pendukung yang
diperlukan pembuatan laporan mutu seperti komputer, printer, kertas dan sebagainya.
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN
B. URUTAN KERJA
1 Penyedia menyiapkan perlengkapan pengabilan sampel serta menghubungi
petugas untuk melakukan uji mutu air
2 Buat rencana kerja pengujian lingkungan sesuai schedule
pekerjaan dan koordinasikan dengan seluruh personil yang terkait
3 Pemilihan lokasi pengujian
4 Melaksanakan pengujian
Catatan :
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN
B. URUTAN KERJA
1 Penyedia menyiapkan perlengkapan pengabilan sampel serta menghubungi
petugas untuk melakukan uji mutu air
2 Buat rencana kerja pengujian lingkungan sesuai schedule
pekerjaan dan koordinasikan dengan seluruh personil yang terkait
3 Pemilihan lokasi pengujian
4 Melaksanakan pengujian
Catatan :
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN
B. URUTAN KERJA
1 Penyedia menyiapkan perlengkapan pengabilan sampel serta menghubungi
petugas untuk melakukan uji mutu air
2 Buat rencana kerja pengujian lingkungan sesuai schedule
pekerjaan dan koordinasikan dengan seluruh personil yang terkait
3 Pemilihan lokasi pengujian
4 Melaksanakan pengujian
Catatan :
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN
B. URUTAN KERJA
1 Penyedia menyiapkan perlengkapan pengabilan sampel serta menghubungi
petugas untuk melakukan uji mutu air
2 Buat rencana kerja pengujian lingkungan sesuai schedule
pekerjaan dan koordinasikan dengan seluruh personil yang terkait
3 Pemilihan lokasi pengujian
4 Melaksanakan pengujian
Catatan :
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN
B. URUTAN KERJA
1 Penyedia menyiapkan perlengkapan pengabilan sampel serta menghubungi
petugas untuk melakukan uji mutu air
2 Buat rencana kerja pengujian lingkungan sesuai schedule
pekerjaan dan koordinasikan dengan seluruh personil yang terkait
3 Pemilihan lokasi pengujian
4 Melaksanakan pengujian
Catatan :
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN
B. URUTAN KERJA
1 Penyedia menyiapkan perlengkapan pengabilan sampel serta menghubungi
petugas untuk melakukan uji mutu air
2 Buat rencana kerja pengujian lingkungan sesuai schedule
pekerjaan dan koordinasikan dengan seluruh personil yang terkait
3 Pemilihan lokasi pengujian
4 Melaksanakan pengujian
Catatan :
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN
B. URUTAN KERJA
1 Penyedia menyiapkan perlengkapan pengabilan sampel serta menghubungi
petugas untuk melakukan uji mutu air
2 Buat rencana kerja pengujian lingkungan sesuai schedule
pekerjaan dan koordinasikan dengan seluruh personil yang terkait
3 Pemilihan lokasi pengujian
4 Melaksanakan pengujian
Catatan :
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN
B. URUTAN KERJA
1 Penyedia menyiapkan perlengkapan pengabilan sampel serta menghubungi
petugas untuk melakukan uji mutu air
2 Buat rencana kerja pengujian lingkungan sesuai schedule
pekerjaan dan koordinasikan dengan seluruh personil yang terkait
3 Pemilihan lokasi pengujian
4 Melaksanakan pengujian
Catatan :
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN
B. URUTAN KERJA
1 Penyedia menyiapkan perlengkapan pengabilan sampel serta menghubungi
petugas untuk melakukan uji mutu air
2 Buat rencana kerja pengujian lingkungan sesuai schedule
pekerjaan dan koordinasikan dengan seluruh personil yang terkait
3 Pemilihan lokasi pengujian
4 Melaksanakan pengujian
Catatan :
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN
B. URUTAN KERJA
1 Penyedia menyiapkan perlengkapan pengabilan sampel serta menghubungi
petugas untuk melakukan uji mutu air
2 Buat rencana kerja pengujian lingkungan sesuai schedule
pekerjaan dan koordinasikan dengan seluruh personil yang terkait
3 Pemilihan lokasi pengujian
4 Melaksanakan pengujian
Catatan :
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN
B. URUTAN KERJA
1 Penyedia menyiapkan perlengkapan pengabilan sampel serta menghubungi
petugas untuk mendatangkan peralatan uji kebisingan
2 Buat rencana kerja pengujian lingkungan sesuai schedule
pekerjaan dan koordinasikan dengan seluruh personil yang terkait
3 Pemilihan lokasi pengujian
4 Melaksanakan pengujian
Catatan :
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN
B. URUTAN KERJA
1 Penyedia menyiapkan perlengkapan pengabilan sampel serta menghubungi
petugas untuk mendatangkan peralatan uji kebisingan
2 Buat rencana kerja pengujian lingkungan sesuai schedule
pekerjaan dan koordinasikan dengan seluruh personil yang terkait
3 Pemilihan lokasi pengujian
4 Melaksanakan pengujian
Catatan :
Analisa El - 117(c)
B. URUTAN KERJA
1 Penyedia menyiapkan perlengkapan pengabilan sampel serta menghubungi
petugas untuk mendatangkan peralatan uji udara emisi dan ambien
2 Buat rencana kerja pengujian lingkungan sesuai schedule
pekerjaan dan koordinasikan dengan seluruh personil yang terkait
3 Pemilihan lokasi pengujian
4 Melaksanakan pengujian
Catatan :
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN
B. URUTAN KERJA
1 Penyedia menyiapkan perlengkapan pengabilan sampel serta menghubungi
petugas untuk mendatangkan peralatan uji udara emisi dan ambien
2 Buat rencana kerja pengujian lingkungan sesuai schedule
pekerjaan dan koordinasikan dengan seluruh personil yang terkait
3 Pemilihan lokasi pengujian
4 Melaksanakan pengujian
Catatan :
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN
B. URUTAN KERJA
1 Penyedia menyiapkan perlengkapan pengabilan sampel serta menghubungi
petugas untuk mendatangkan peralatan uji udara emisi dan ambien
2 Buat rencana kerja pengujian lingkungan sesuai schedule
pekerjaan dan koordinasikan dengan seluruh personil yang terkait
3 Pemilihan lokasi pengujian
4 Melaksanakan pengujian
Catatan :
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN
B. URUTAN KERJA
1 Penyedia menyiapkan perlengkapan pengabilan sampel serta menghubungi
petugas untuk mendatangkan peralatan uji udara emisi dan ambien
2 Buat rencana kerja pengujian lingkungan sesuai schedule
pekerjaan dan koordinasikan dengan seluruh personil yang terkait
3 Pemilihan lokasi pengujian
4 Melaksanakan pengujian
Catatan :
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN
B. URUTAN KERJA
1 Penyedia menyiapkan perlengkapan pengabilan sampel serta menghubungi
petugas untuk mendatangkan peralatan uji udara emisi dan ambien
2 Buat rencana kerja pengujian lingkungan sesuai schedule
pekerjaan dan koordinasikan dengan seluruh personil yang terkait
3 Pemilihan lokasi pengujian
4 Melaksanakan pengujian
Catatan :
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN
B. URUTAN KERJA
1 Penyedia menyiapkan perlengkapan pengabilan sampel serta menghubungi
petugas untuk mendatangkan peralatan uji udara emisi dan ambien
2 Buat rencana kerja pengujian lingkungan sesuai schedule
pekerjaan dan koordinasikan dengan seluruh personil yang terkait
3 Pemilihan lokasi pengujian
4 Melaksanakan pengujian
Catatan :
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN
B. URUTAN KERJA
1 Penyedia menyiapkan perlengkapan pengabilan sampel serta menghubungi
petugas untuk mendatangkan peralatan uji udara emisi dan ambien
2 Buat rencana kerja pengujian lingkungan sesuai schedule
pekerjaan dan koordinasikan dengan seluruh personil yang terkait
3 Pemilihan lokasi pengujian
4 Melaksanakan pengujian
Catatan :
ITEM PEMBAYARAN NO. : 2.1.(1) Analisa EI-211
JENIS PEKERJAAN : Galian untuk Selokan Drainase dan Saluran Air
SATUAN PEMBAYARAN : M3 URAIAN ANALISA HARGA SATUAN
I. ASUMSI
1 Menggunakan alat berat (cara mekanik)
2 Lokasi pekerjaan : sepanjang jalan
3 Kondisi Jalan : baik
4 Jam kerja efektif per-hari Tk 7.00 jam
5 Faktor pengembangan bahan Fk 1.20 -
2. ALAT
2.a. MINI EXCAVATOR (E10a)
Kapasitas Bucket V 0.93 M3
Faktor Bucket Fb 1.00 -
Faktor Efisiensi alat Fa 0.83 -
Faktor konversi , kedalaman 40 %-75 %, Normal Fv 1.00
Waktu siklus Ts1 menit
- Menggali , memuat (swing 180ᵒ) T1 0.240 menit
- Lain lain T2 0.080 menit
Waktu siklus = T1 + T2 Ts1 0.32 menit Permen PUPR
No 28/PRT/M/2016
3. TENAGA
Produksi menentukan : EXCAVATOR Q1 173.68 M3/Jam
Produksi Galian / hari = Tk x Q1 Qt 1,215.74 M3
Kebutuhan tenaga :
- Pekerja P 3.00 orang
- Mandor M 1.00 orang
Koefisien tenaga / M3 :
- Pekerja = (Tk x P) : Qt (L01) 0.0173 Jam
- Mandor = (Tk x M) : Qt (L03) 0.0058 Jam
Rp. 41,921.47 / M3
I. ASUMSI
1 Menggunakan alat (cara mekanik)
2 Lokasi pekerjaan : sepanjang jalan
3 Bahan dasar (batu, pasir dan semen) diterima
seluruhnya di lokasi pekerjaan
4 Jarak rata-rata Base camp ke lokasi pekerjaan L 35.0 KM
5 Jam kerja efektif per-hari Tk 7.00 jam
6 Perbandingan Pasir & Semen : - Volume Semen Sm 17 % 1:5
: - Volume Pasir Ps 83 %
7 Perbandingan Batu & Mortar :
- Batu Bt 60 %
- Mortar (campuran semen & pasir) Mr 40 %
8 Berat Jenis Bahan :
- Pasangan Batu Dengan Mortar D1 2.00 ton/M3
- Batu D2 1.05 ton/M3 lepas
- Adukan (mortar) D3 1.90 ton/M3
- Pasir D4 1.45 ton/M3
- Semen Portland D5 3.14 ton/M3 Berat Jenis
1. BAHAN
1.a. Batu -----> {(Bt x D1 x 1 M3) : D2} x 1.05 (M02) 1.20 M3 Lepas
1.b. Semen ----> Sm x {(Mr x D1 x 1 M3} : D3} x 1.03 0.0737
x {D5 x (1000)} (M12) 232.00 Kg
1.c. Pasir -----> Ps x {(Mr x D1 x 1 M3) : D4} x 1.05 (M01) 0.4808 M3
2. ALAT
2.a. CONCRETE MIXER (E06)
Kapasitas Alat V 500.00 Liter
Faktor Efisiensi Alat Fa 0.83 -
Waktu siklus : (T1 + T2 + T3 + T4)
- Memuat T1 4.00 menit
- Mengaduk T2 4.00 menit
- Menuang T3 1.00 menit
- Menunggu, dll. T4 1.00 menit
Ts1 10.00 menit
3. TENAGA
Produksi Pas. Batu yang menentukan ( Prod. C. Mixer ) Q1 2.49 M3/Jam
Produksi Pasangan Batu dalam 1 hari = Tk x Q1 Qt 17.43 M3
Koefisien Tenaga / M3 :
- Mandor = (Tk x M) : Qt (L03) 0.4016 jam
- Tukang = (Tk x Tb) : Qt (L02) 1.2048 jam
- Pekerja = (Tk x P) : Qt (L01) 2.4096 jam
Rp. 817,427.78 / M3
I. ASUMSI
1 Pekerjaan dilakukan secara mekanik/manual
2 Lokasi pekerjaan : sepanjang jalan
3 Diameter bagian dalam gorong-gorong d 0.20 m
4 Jarak rata-rata Base Camp ke lokasi pekerjaan L 20.00 Km
5 Jam kerja efektif per-hari Tk 7.00 jam
6 Tebal gorong-gorong tg 2.90 Cm
2. ALAT
2.a. TAMPER (tebal lapis porous) (E25)
Kecepatan v 1.00 Km / Jam Diperhitungkan
Efisiensi alat Fa 0.83 - hanya tamper
Lebar pemadatan Lb 0.50 M
Banyak lintasan n 10 lintasan
Tebal lapis hamparan tp 0.10 M
3. TENAGA
Produksi menentukan : Flat Bed Truck Q2 14.61 M'/jam
Produksi Gorong-gorong Tanpa Tulangan / hari = Tk x Q2 Qt 102.24 M
Kebutuhan tenaga :
- Pekerja P 14.00 orang
- Tukang T 8.00 orang
- Mandor M 1.00 orang
Koefisien tenaga / M1 :
- Pekerja = (Tk x P) : Qt (L01) 0.9585 Jam
- Tukang = (Tk x T) : Qt (L02) 0.5477 Jam
- Mandor = (Tk x M) : Qt (L03) 0.0685 Jam
PROYEK :
No. PAKET KONTRAK : ………………………………………………
NAMA PAKET : Preservasi Jalan Serdang - Bojonegara - Merak
………………………………………………………………….
PROP / KAB / KODYA : Banten
ITEM PEMBAYARAN NO. : 2.1.(1)
JENIS PEKERJAAN : Galian untuk Selokan Drainase dan Saluran Air
SATUAN PEMBAYARAN : M3
% TKDN KDN
PERKIRAAN HARGA JUMLAH (Rp.)
NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA d e=cxd
(Rp.) (Rp.)
a b c
A. TENAGA
B. BAHAN
C. PERALATAN
PROYEK :
No. PAKET KONTRAK : ………………………………………………
NAMA PAKET : Preservasi Jalan Serdang - Bojonegara - Merak
………………………………………………………………….
PROP / KAB / KODYA : Banten
ITEM PEMBAYARAN NO. : 2.2.(1)
JENIS PEKERJAAN : Pasangan Batu dengan Mortar
SATUAN PEMBAYARAN : M3
% TKDN KDN
PERKIRAAN HARGA JUMLAH (Rp.)
NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA d e=cxd
(Rp.) (Rp.)
A. TENAGA
B. BAHAN
C. PERALATAN
PROYEK :
No. PAKET KONTRAK : ………………………………………………
NAMA PAKET : …………………………………………………………………..
………………………………………………………………….
PROP / KAB / KODYA : ………………………………………………
ITEM PEMBAYARAN NO. : 2.3.(1) PERKIRAAN VOL. PEK. : 0.00
JENIS PEKERJAAN : Gorong-gorong Pipa Beton Tanpa Tulangan diameter dalam 20 cmTOTAL HARGA (Rp.) : 0.00
SATUAN PEMBAYARAN : M' 0 % THD. BIAYA PROYEK : 0.00
% TKDN KDN
PERKIRAAN HARGA JUMLAH (Rp.)
NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA d e=cxd
(Rp.) (Rp.)
A. TENAGA
B. BAHAN
C. PERALATAN
26,114.06
f=c-e
0
0
572.99
8,402.60
0
8,975.59
8,975.59
0.25
KLN
f=c-e
0
0
8,048.72
-
8,048.72
8,048.72
0.01
KLN
f=c-e
0
0
50.85
4,339.06
4,314.78
8,704.69
8,704.69
0.05
ITEM PEMBAYARAN NO. : 2.3.(21) Analisa EI-2321
JENIS PEKERJAAN : Gorong-gorong Kotak Beton Bertulang, ukuran dalam 200 x 100 cm
SATUAN PEMBAYARAN : M1 URAIAN ANALISA HARGA SATUAN
I. ASUMSI
1 Pekerjaan dilakukan secara mekanik
2 Lokasi pekerjaan : sepanjang jalan Uk 200 x 100 cm
3 Saluran berbentuk Box Culvert Pracetak di terima h 1.00 m
seluruhnya dilokasi pekerjaan w 2.00 m
4 Material Porus untuk alas (sand bedding) Tk 7.00 jam
5 Jenis Box Culvert adalah Tipe HD (Heavy Duty) tb 15.00 Cm
Setara K-300
6 Ukuran merupakan Dimensi Dalam Saluran
2. ALAT
2.a. TAMPER (pemadatan lapis dasar) (E25)
Kecepatan v 1.00 Km / Jam
Efisiensi alat Fa 0.83 -
Lebar pemadatan (Lb = w ) Lb 2.00 M
Banyak lintasan n 20 lintasan
Tebal lapis hamparan tp 0.10 M
Kap. Prod. / Jam = v x 1000 x Fa x Lb x tp Q1 52.01 M' / Jam
n x (El-241)
3. TENAGA
I. ASUMSI
1 Pekerjaan dilakukan secara mekanik
2 Lokasi pekerjaan : sepanjang jalan Uk 500 x 250 cm
3 Saluran berbentuk Box Culvert Pracetak di terima h 2.50 m
seluruhnya dilokasi pekerjaan w 5.00 m
4 Material Porus untuk alas (sand bedding) Tk 7.00 jam
5 Jenis Box Culvert adalah Tipe HD (Heavy Duty) tb 30.00 Cm
Setara K-300
6 Ukuran merupakan Dimensi Dalam Saluran
2. ALAT
2.a. TAMPER (pemadatan lapis dasar) (E25)
Kecepatan v 1.00 Km / Jam
Efisiensi alat Fa 0.83 -
Lebar pemadatan (Lb = w ) Lb 5.00 M
Banyak lintasan n 20 lintasan
Tebal lapis hamparan tp 0.10 M
Kap. Prod. / Jam = v x 1000 x Fa x Lb x tp Q1 25.83 M' / Jam
n x (El-241)
3. TENAGA
PROYEK :
No. PAKET KONTRAK : ………………………………………………
NAMA PAKET : Preservasi Jalan Serdang - Bojonegara - Merak
………………………………………………………………….
PROP / KAB / KODYA : Banten
ITEM PEMBAYARAN NO. : 2.3.(21)
JENIS PEKERJAAN : Gorong-gorong Kotak Beton Bertulang, ukuran dalam 200 x 100 cm
SATUAN PEMBAYARAN : M1
A. TENAGA
B. BAHAN
C. PERALATAN
PROYEK :
No. PAKET KONTRAK : ………………………………………………
NAMA PAKET 0
0
PROP / KAB / KODYA 0
ITEM PEMBAYARAN NO. : 2.3.(21)
JENIS PEKERJAAN : Gorong-gorong Kotak Beton Bertulang, ukuran dalam 500 x 250 cm
SATUAN PEMBAYARAN : M1
A. TENAGA
B. BAHAN
C. PERALATAN
I. ASUMSI
1 Pekerjaan dilakukan secara mekanik
2 Lokasi pekerjaan : sepanjang jalan
3
Material diambil dari pabrikasi
2. PERALATAN
2.a. EXCAVATOR (E10)
Kapasitas Bucket V 0.93 M3
Faktor Bucket Fb 1.00 -
Faktor Efisiensi alat Fa 0.85
Faktor konversi , kedalaman < 40 % Fv 0.90 Faktor konversi
Waktu siklus Ts1 menit dihapus, masuk
- Menggali , memuat T1 1.00 menit dalam waktu siklus
- Lain lain T2 0.10 menit disesuaikam
Waktu siklus = T1 x Fv Ts1 1.10 menit
continued
PAY ITEM NUMBER : 2.3.(26) Analisa LI - 2326
WORK ITEM : Saluran berbentuk U Tipe DS 3
UNIT : M1 0
next page
3. TENAGA
Produksi Saluran DS dalam/ hari Qt 10.00 M'
Koefisien Tenaga / M3 :
- Mandor = (Tk x M) : Qt (L03) 0.7000 Jam
- Tukang = (Tk x Tb) : Qt (L02) 0.7000 Jam
- Pekerja = (Tk x P) : Qt (L01) 2.1000 Jam
Rupiah 1,101,010.00 / M1
I. ASUMSI
1 Pekerjaan dilakukan secara mekanik
2 Lokasi pekerjaan : sepanjang jalan
3
Material diambil dari pabrikasi
2. PERALATAN
2.a. EXCAVATOR (E10)
Kapasitas Bucket V 0.93 M3
Faktor Bucket Fb 1.00 -
Faktor Efisiensi alat Fa 0.85
Faktor konversi , kedalaman < 40 % Fv 0.90 Faktor konversi
Waktu siklus Ts1 menit dihapus, masuk
- Menggali , memuat T1 1.00 menit dalam waktu siklus
- Lain lain T2 0.10 menit disesuaikam
Waktu siklus = T1 x Fv Ts1 1.10 menit
continued
PAY ITEM NUMBER : 2.3.(26) Analisa LI - 2326
WORK ITEM : Saluran berbentuk U Tipe DS 3a (dengan tutup)
UNIT : M1 0
next page
3. TENAGA
Produksi Saluran DS dalam/ hari Qt 8.00 M'
Koefisien Tenaga / M3 :
- Mandor = (Tk x M) : Qt (L03) 0.8750 Jam
- Tukang = (Tk x Tb) : Qt (L02) 0.8750 Jam
- Pekerja = (Tk x P) : Qt (L01) 2.6250 Jam
Rupiah 1,299,000.00 / M1
I. ASUMSI
1 Pekerjaan dilakukan secara mekanik
2 Lokasi pekerjaan : sepanjang jalan
3
Material diambil dari pabrikasi
2. PERALATAN
2.a. EXCAVATOR (E10)
Kapasitas Bucket V 0.93 M3
Faktor Bucket Fb 1.00 -
Faktor Efisiensi alat Fa 0.85
Faktor konversi , kedalaman < 40 % Fv 0.90 Faktor konversi
Waktu siklus Ts1 menit dihapus, masuk
- Menggali , memuat T1 1.00 menit dalam waktu siklus
- Lain lain T2 0.10 menit disesuaikam
Waktu siklus = T1 x Fv Ts1 1.10 menit
continued
PAY ITEM NUMBER : 2.3.(28) Analisa LI - 2326
WORK ITEM : Saluran berbentuk U Tipe DS 4a (dengan tutup)
UNIT : M1 0
next page
3. TENAGA
Produksi Saluran DS dalam/ hari Qt 7.00 M'
Koefisien Tenaga / M3 :
- Mandor = (Tk x M) : Qt (L03) 1.0000 Jam
- Tukang = (Tk x Tb) : Qt (L02) 1.0000 Jam
- Pekerja = (Tk x P) : Qt (L01) 3.0000 Jam
Rupiah 1,472,819.00 / M1
PROYEK
No. PAKET KONTRAK
NAMA PAKET 0
A. TENAGA
B. MATERIAL
1. U-Ditch 80 x 80 x 100 Cm M1 1.0000 790,000.00 790,000.00
C. PERALATAN
PROYEK
No. PAKET KONTRAK
NAMA PAKET 0
A. TENAGA
B. MATERIAL
1. U-Ditch 80 x 80 x 100 Cm M1 1.0000 790,000.00 790,000.00
2. Penutup M1 1.0000 200,000.00 200,000.00
C. PERALATAN
PROYEK
No. PAKET KONTRAK
NAMA PAKET
A. TENAGA
B. MATERIAL
1. U-Ditch 100 x 100 x 100 Cm M1 1.0000 840,000.00 840,000.00
2. Penutup M1 1.0000 220,000.00 220,000.00
C. PERALATAN
100 48,000.00 0
100 17,000.00 0
100 19,000.00
100 790,000.00
790,000.00 0.83 -
75 5,769.88 1,923.29
75 25,184.61 8,394.87
75 31,520.80 10,506.93
100 60,000.00 0
100 21,250.00 0
100 23,750.00
100 790,000.00
790,000.00 0.67 -
75 5,769.88 1,923.29
75 25,184.61 8,394.87
75 33,378.29 11,126.10
100 68,571.43 0
100 24,285.71 0
100 27,142.86
100 840,000.00
840,000.00 0.71 -
75 5,769.88 1,923.29
75 25,184.61 8,394.87
75 44,504.39 14,834.80
I. ASUMSI
1 Menggunakan alat berat (cara mekanik)
2 Lokasi pekerjaan : sepanjang jalan
3 Kondisi Jalan : baik
4 Jam kerja efektif per-hari Tk 7.00 Jam
5 Faktor pengembangan bahan Fk 1.20 -
1. BAHAN
Tidak ada bahan yang diperlukan
2. ALAT
2.a. EXCAVATOR (E10)
Kapasitas Bucket V 0.93 M3
Faktor Bucket Fb 1.00 -
Faktor Efisiensi alat Fa 0.83
Faktor konversi , kedalaman 40 %-75 %, Mudah Fv 1.00
Waktu siklus Ts1 menit
- Menggali , memuat (swing 180ᵒ) T1 0.240 menit
- Lain lain T2 0.080 menit
Waktu siklus = T1 + T2 Ts1 0.32 menit Permen PUPR No
28/PRT/M/2016
3. TENAGA
Produksi menentukan : EXCAVATOR Q1 173.68 M3/Jam
Produksi Galian / hari = Tk x Q1 Qt 1,215.74 M3
Kebutuhan tenaga :
- Pekerja P 3.00 orang
- Mandor M 1.00 orang
Koefisien tenaga / M3 :
- Pekerja = (Tk x P) : Qt (L01) 0.0173 Jam
- Mandor = (Tk x M) : Qt (L03) 0.0058 Jam
Rp. 41,921.47 / M3
PROYEK :
No. PAKET KONTRAK :
NAMA PAKET : Preservasi Jalan Serdang - Bojonegara - Merak
-
PROP / KAB / KODYA : Banten
ITEM PEMBAYARAN NO. : 3.1.(1)
JENIS PEKERJAAN : Galian Biasa
SATUAN PEMBAYARAN : M3
A. TENAGA
B. BAHAN
C. PERALATAN
I. ASUMSI
1 Pekerjaan dilakukan secara mekanis
2 Lokasi pekerjaan : sepanjang jalan
3 Kondisi Jalan : baik
4 Jam kerja efektif per-hari Tk 7.00 Jam
5 Faktor pengembangan bahan Fk 1.20 -
6 Faktor pengembangan bahan (padat ke asli) Fv 1.20 -
7 Tebal hamparan padat t 0.20 M
8 Berat volume bahan (lepas) D 1.45 Ton/M3 1,3-1,6
2. ALAT
2.a. WHEEL LOADER (E15)
Kapasitas Bucket V 1.50 M3
Faktor Bucket Fb 0.85 -
Faktor Efisiensi Alat Fa 0.83 -
Waktu sklus Ts1
- Muat T1 0.45 menit
Ts1 0.45 menit
3. TENAGA
Produksi menentukan : MOTOR GRADER Q3 336.00 M3/Jam
Produksi Timbunan / hari = Tk x Q1 Qt 2,352.00 M3
Kebutuhan tenaga :
- Pekerja P 4.00 orang
- Mandor M 1.00 orang
Koefisien tenaga / M3 :
- Pekerja = (Tk x P) : Qt (L01) 0.0119 Jam
- Mandor = (Tk x M) : Qt (L03) 0.0030 Jam
I. ASUMSI
1 Pekerjaan dilaksanakan hanya pada tanah galian
2 Pekerjaan dilakukan secara mekanis
3 Lokasi pekerjaan : sepanjang jalan
4 Kondisi Jalan : jelek / belum padat
5 Jam kerja efektif per-hari Tk 7.00 Jam
6 Faktor Pengembangan Bahan Fk 1.20
2. ALAT
2.a. MOTOR GRADER (E13)
Panjang operasi grader sekali jalan Lh 50.00 M
Lebar Area Pemadatan w 3.50 M
Lebar Efektif kerja Blade b 2.60 M
Lebar overlap bo 0.30 M
Faktor Efisiensi Alat Fa 0.83 -
Kecepatan rata-rata alat v 4.00 Km / Jam
Jumlah lintasan n 6.00 lintasan
Jumlah lajur lintasan = w/(b-bo) N 2.00 lajur
Waktu siklus
- Perataan 1 kali lintasan = Lh : (v x 1000) x 60 T1 0.75 menit
- Lain-lain T2 1.00 menit
Ts1 1.75 menit
3. TENAGA
Produksi menentukan : MOTOR GRADER Q1 581.00 M2/Jam
Produksi Pekerjaan / hari = Tk x Q1 Qt 4,067.00 M2
Kebutuhan tenaga :
- Pekerja P 2.00 orang
- Mandor M 1.00 orang
Koefisien tenaga / M2
- Pekerja = (Tk x P) : Qt (L01) 0.0034 Jam
- Mandor = (Tk x M) : Qt (L02) 0.0017 Jam
Rp. 10,645.48 / M2
PROYEK -
No. PAKET KONTRAK :
NAMA PAKET : Preservasi Jalan Serdang - Bojonegara - Merak
-
PROP / KAB / KODYA : Banten
ITEM PEMBAYARAN NO. : 3.2.(2a)
JENIS PEKERJAAN : Timbunan Pilihan Dari Sumber Galian
SATUAN PEMBAYARAN : M3
A. TENAGA
B. BAHAN
C. PERALATAN
1. Wheel Loader (E15) Jam 275,684.81 0.00
2. Dump Truck (E09) Jam 304,463.40 0.00
1. Motor Grader (E13) Jam 0.0030 339,207.16 1,009.55
2. Tandem (E17) Jam 0.0084 350,000.00 2,928.38
3. Water Tanker (E23) Jam 0.0341 204,742.50 6,989.20
4. Alat Bantu Ls 1.0000 0.00 0.00
PROYEK -
No. PAKET KONTRAK :
NAMA PAKET : Preservasi Jalan Serdang - Bojonegara - Merak
-
PROP / KAB / KODYA : Banten
ITEM PEMBAYARAN NO. : 3.3.(1)
JENIS PEKERJAAN : Penyiapan Badan Jalan
SATUAN PEMBAYARAN : M2
A. TENAGA
B. BAHAN
C. PERALATAN
1. Motor Grader (E13) jam 0.0017 339,207.16 583.83
2. Tandem / Vibro Roller (E17) jam 0.0244 350,000.00 8,547.70
3 Alat Bantu Ls 1.0000 0.00 0.00
Note: 1 Satuan dapat berdasarkan atas jam operasi untuk Tenaga Kerja dan Peralatan, volume dan/atau ukuran
berat untuk bahan-bahan.
2 Kuantitas satuan adalah kuantitas perkiraan setiap komponen untuk menyelesaikan satu satuan pekerjaan
dari nomor mata pembayaran. Harga Satuan yang disampaikan Penyedia Jasa tidak dapat diubah kecuali
terdapat Penyesuaian Harga (Eskalasi/Deskalasi) sesuai ketentuan dalam Instruksi Kepada Peserta Lelang
3 Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis dipakai dan operator.
4 Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan (tetapi tidak termasuk PPN
yang dibayar dari kontrak) dan biaya-biaya lainnya.
ITEM PEMBAYARAN NO. : 3.4.(2) Analisa EI-342
JENIS PEKERJAAN : Pemotongan Pohon Pilihan diameter 15 – 30 cm
SATUAN PEMBAYARAN : buah URAIAN ANALISA HARGA SATUAN
I. ASUMSI
1 Menggunakan tenaga pekerja/peralatan
2 Lokasi pekerjaan : sepanjang jalan
3 Kondisi Jalan : sedang / baik
4 Jam kerja efektif per-hari Tk 7.00 Jam
5 1 Pohon diameter 15-30 cm setara dengan volume Vp 0.25 M3
6 Berat Jenis Kayu BjK 0.70 ton/M3
7 Jarak antar Pohon s 1.50 m'
1. BAHAN
Tidak ada bahan yang diperlukan
2. ALAT
2.a TRACK LOADER (E14)
Kapasitas Bucket V 0.80 M3
Faktor Bucket Fb 0.85 -
Faktor Efisiensi Alat Fa 0.83 -
Waktu sklus Ts1
- Muat T1 0.45 menit
Ts1 0.45 menit
3. TENAGA
I. ASUMSI
1 Menggunakan tenaga pekerja/peralatan
2 Lokasi pekerjaan : sepanjang jalan
3 Kondisi Jalan : sedang / baik
4 Jam kerja efektif per-hari Tk 7.00 Jam
5 1 Pohon diameter 15-30 cm setara dengan volume Vp 0.71 M3
6 Berat Jenis Kayu BjK 0.70 ton/M3
7 Jarak antar Pohon s 2.75 m'
1. BAHAN
Tidak ada bahan yang diperlukan
2. ALAT
2.a TRACK LOADER (E14)
Kapasitas Bucket V 0.80 M3
Faktor Bucket Fb 0.85 -
Faktor Efisiensi Alat Fa 0.83 -
Waktu sklus Ts1
- Muat T1 0.45 menit
Ts1 0.45 menit
3. TENAGA
I. ASUMSI
1 Menggunakan tenaga pekerja/peralatan
2 Lokasi pekerjaan : sepanjang jalan
3 Kondisi Jalan : sedang / baik
4 Jam kerja efektif per-hari Tk 7.00 Jam
5 1 Pohon diameter 15-30 cm setara dengan volume Vp 1.66 M3
6 Berat Jenis Kayu BjK 0.70 ton/M3
7 Jarak antar Pohon s 4.00 m'
1. BAHAN
Tidak ada bahan yang diperlukan
2. ALAT
2.a TRACK LOADER (E14)
Kapasitas Bucket V 0.80 M3
Faktor Bucket Fb 0.85 -
Faktor Efisiensi Alat Fa 0.83 -
Waktu sklus Ts1
- Muat T1 0.45 menit
Ts1 0.45 menit
3. TENAGA
Koefisien tenaga / M3 :
- Pekerja = (Tk x P) : Qt (L01) 0.6378 jam
- Mandor = (Tk x M) : Qt (L03) 0.0638 jam
I. ASUMSI
1 Menggunakan tenaga pekerja/peralatan
2 Lokasi pekerjaan : sepanjang jalan
3 Kondisi Jalan : sedang / baik
4 Jam kerja efektif per-hari Tk 7.00 Jam
5 1 Pohon diameter 15-30 cm setara dengan volume Vp 3.01 M3
6 Berat Jenis Kayu BjK 0.70 ton/M3
7 Jarak antar Pohon s 6.00 m'
1. BAHAN
Tidak ada bahan yang diperlukan
2. ALAT
2.a TRACK LOADER (E14)
Kapasitas Bucket V 0.80 M3
Faktor Bucket Fb 0.85 -
Faktor Efisiensi Alat Fa 0.83 -
Waktu sklus Ts1
- Muat T1 0.45 menit
Ts1 0.45 menit
3. TENAGA
Koefisien tenaga / M3 :
- Pekerja = (Tk x P) : Qt (L01) 1.4352 jam
- Mandor = (Tk x M) : Qt (L03) 0.1435 jam
I. ASUMSI
1 Pekerjaan dilakukan secara mekanik
2 Lokasi pekerjaan : sepanjang jalan
3 Kondisi Jalan : baik
4 Jam kerja efektif per-hari Tk 7.00 Jam
5 Faktor pengembangan bahan Fk 1.24 -
6 Berat volume bahan (lepas) D 1.60 Ton/M3
1. BAHAN
Tidak ada bahan yang diperlukan
2. ALAT
2.a. COLD MILLING (E36)
Kapasitas lebar galian/pembongkaran b 1 m
tebal galian/pembongkaran t 0.04 m
kecepatan laju pembongkaran v 3.00 m/menit
Faktor effesiensi kerja Fa 0.70
3. TENAGA
Produksi menentukan : COLD MILLING Q1 5.04 M3/Jam
Produksi Galian / hari = Tk x Q1 Qt 35.28 M2
Kebutuhan tenaga :
- Pekerja P 2.00 orang
- Mandor M 1.00 orang
Koefisien tenaga / M3 :
- Pekerja = (Tk x P) : Qt (L01) 0.3968 Jam
- Mandor = (Tk x M) : Qt (L03) 0.1984 Jam
Rp. 477,210.92 / M2
PROYEK -
No. PAKET KONTRAK :
NAMA PAKET : Preservasi Jalan Serdang - Bojonegara - Merak
PROP / KAB / KODYA -
ITEM PEMBAYARAN NO. : Banten
JENIS PEKERJAAN : Pemotongan Pohon Pilihan diameter 15 – 30 cm
SATUAN PEMBAYARAN : buah
(Rp.) (Rp.)
A. TENAGA
B. BAHAN
C. PERALATAN
PROYEK -
No. PAKET KONTRAK :
NAMA PAKET : Preservasi Jalan Serdang - Bojonegara - Merak
PROP / KAB / KODYA -
ITEM PEMBAYARAN NO. : Banten
JENIS PEKERJAAN : Pemotongan Pohon Pilihan diameter > 30 – 50 cm
SATUAN PEMBAYARAN : buah
(Rp.) (Rp.)
A. TENAGA
B. BAHAN
C. PERALATAN
PROYEK -
No. PAKET KONTRAK :
NAMA PAKET : Preservasi Jalan Serdang - Bojonegara - Merak
PROP / KAB / KODYA -
ITEM PEMBAYARAN NO. : Banten
JENIS PEKERJAAN : Pemotongan Pohon Pilihan diameter >50 – 75 cm
SATUAN PEMBAYARAN : buah
(Rp.) (Rp.)
A. TENAGA
B. BAHAN
C. PERALATAN
PROYEK -
No. PAKET KONTRAK :
NAMA PAKET : Preservasi Jalan Serdang - Bojonegara - Merak
PROP / KAB / KODYA -
ITEM PEMBAYARAN NO. : Banten
JENIS PEKERJAAN : Pemotongan Pohon Pilihan diameter > 75 cm
SATUAN PEMBAYARAN : buah
(Rp.) (Rp.)
A. TENAGA
B. BAHAN
C. PERALATAN
PROYEK :
No. PAKET KONTRAK
NAMA PAKET : Preservasi Jalan Serdang - Bojonegara - Merak
………………………………………………………………….
PROP / KAB / KODYA : Banten
ITEM PEMBAYARAN NO. 3.1.(7) PERKIRAAN VOL. PEK. : 0.00
JENIS PEKERJAAN : Galian Perkerasan Beraspal dengan Cold Milling Mach TOTAL HARGA (Rp.) : 0.00
SATUAN PEMBAYARAN : M3 % THD. BIAYA PROYEK : 0.00
A. TENAGA
B. BAHAN
C. PERALATAN
1. Cold Milling (E36) Jam 0.1984 1,493,096.99 296,249.40
2 Dump Truck (E09) Jam 0.4863 205,103.54 99,738.41
3. Water Tanker (E32) M3 0.0221 204,742.50 4,522.42
4. Alat bantu Ls 1.0000 0.00 0.00
I. ASUMSI
1 Pekerjaan dilakukan secara mekanis
2 Lokasi pekerjaan : sepanjang jalan
3 Kondisi Jalan : baik
4 Jam kerja efektif per-hari Tk 7.00 Jam
5 Faktor pengembangan bahan (padat ke asli) Fv 1.20 -
6 Tebal hamparan padat t 0.15 M
7 Berat volume bahan (lepas) D 1.25 Ton/M3 1,1-1,4
2. ALAT
2.a. EXCAVATOR (E10)
Kapasitas Bucket V 0.93 M3
Faktor Bucket Fb 1.10 -
Faktor Efisiensi alat Fa 0.83
Faktor konversi , kedalaman 40 %-75 %, Normal Fv 1.00
Waktu siklus Ts1 menit
- Menggali , memuat T1 0.240 menit
- Lain lain T2 0.080 menit
Waktu siklus = T1 x Fv Ts1 0.32 menit Permen PUPR No
28/PRT/M/2016
3. TENAGA
Produksi menentukan : EXCAVATOR Q1 23.88 M3/Jam
Produksi Timbunan / hari = Tk x Q1 Qt 167.16 M3
Kebutuhan tenaga :
- Pekerja P 4.00 orang
- Mandor M 1.00 orang
Koefisien tenaga / M3 :
- Pekerja = (Tk x P) : Qt (L01) 0.1675 Jam
- Mandor = (Tk x M) : Qt (L02) 0.0419 Jam
Rp. 264,138.09 / M3
I. ASUMSI
1 Pekerjaan dilakukan secara mekanik/manual
2 Lokasi pekerjaan : sepanjang jalan
3 Kondisi Jalan : sedang/rusak
4 Jam kerja efektif per-hari Tk 7.00 Jam
5 Faktor pengembangan bahan Fk 1.20 -
6 Tebal perkerasan beton t 0.30 M
7 Berat volume perkerasan beton D 2.40 Ton/M3
8 Memakai Drill Breaker ( yes = 1 , No = 0 ) 0
1. BAHAN
Tidak ada bahan yang diperlukan
2. ALAT
2.a. JACK HAMMER + AIR COMPRESSOR
Kapasitas bongkar bk 6.00 menit/m2
Effesiensi kerja Fa 0.83
Kapa. Prod/jam = Fa x t x 60 Q1 2.490 M3
bk
Koefisien Alat / m3 = 1 : Q1 (E05/260 0.4016 Jam
3. TENAGA
Produksi menentukan : JACK HAMMER Q1 6.00 M3/Jam
Produksi Galian / hari = Tk x Q1 Qt 42.00 M3
Kebutuhan tenaga :
- Pekerja P 6.00 orang
- Mandor M 1.00 orang
Koefisien tenaga / M3 :
- Pekerja = (Tk x P) : Qt (L01) 1.0000 Jam
- Mandor = (Tk x M) : Qt (L03) 0.1667 Jam
Rp. 382,562.08 / M3
PROYEK :
No. PAKET KONTRAK : ………………………………………………
NAMA PAKET : Preservasi Jalan Serdang - Bojonegara - Merak
………………………………………………………………….
PROP / KAB / KODYA : Banten
ITEM PEMBAYARAN NO. : 3.2.(1a)
JENIS PEKERJAAN : Timbunan Biasa Dari Sumber Galian
SATUAN PEMBAYARAN : M3
A. TENAGA
B. BAHAN
C. PERALATAN
1. Excavator (E10) Jam 398,058.54 0.00
2. Dump Truck (E09) Jam 304,463.40 0.00
1. Motor Grader (E13) Jam 0.0020 339,207.16 673.03
2. Sheepfoot Roller Jam 0.0024 189,000.00 450.91
3. Tandem Roller (E17) Jam 0.0004 403,700.18 157.24
4. Water tank truck (E23) Jam 0.0070 204,742.50 1,438.95
5. Alat Bantu Ls 1.0000 0.00 0.00
PROYEK :
No. PAKET KONTRAK : ………………………………………………
NAMA PAKET : …………………………………………………………………..
………………………………………………………………….
PROP / KAB / KODYA : ………………………………………………
ITEM PEMBAYARAN NO. : 3.1.(9). PERKIRAAN VOL. PEK. : 1.00
JENIS PEKERJAAN : Galian Perkerasan Beton TOTAL HARGA (Rp.) : 85,392.52
SATUAN PEMBAYARAN : M3 % THD. BIAYA PROYEK : 0.01
A. TENAGA
B. BAHAN
C. PERALATAN
1. Jack Hammer E26 Jam 0.4016 425,294.38 170,800.96
2. Compresor E05 Jam 0.4016 148,769.95 59,746.97
3. Dump Truck E08 Jam 0.2455 304,463.40 74,733.80
KEGIATAN :
PEKERJAAN : Preservasi Jalan Serdang - Bojonegara - Merak
KABUPATEN :
PROPINSI : Banten
ITEM PEMBAYARAN : SKh-1.3.17 (1.b)
JENIS PEKERJAAN : Selimut Pengendali Erosi Tipe II
SATUAN PEMBAYARAN : M2
A. TENAGA
1 Mandor (L03) jam 0.0583 27,142.86 1,583.33
2 Tukang (L02) jam - - -
3 Pekerja (L01) jam 0.2917 22,857.14 6,666.67
B. BAHAN
1 Selimut Pengendali Erosi Tipe II M2 1.0000 130,000.00 130,000.00
2 Angkur Pin - Besi Ulir D10 Kg 0.308 15,291.00 4,711.35
(per titik = 50 cm, spacing 1mx1m)
C. PERALATAN
1 Alat Bantu Pemasangan Ls 1.0000 1,904.14 1,904.14
- Perancah
- Palu
- Alat Pelindung Diri
2 Welding Machine + Kawat Las Ls 1.0000 152.77 152.77
KEGIATAN :
PEKERJAAN : Preservasi Jalan Serdang - Bojonegara - Merak
KABUPATEN :
PROPINSI : Banten
ITEM PEMBAYARAN : SKh-1.3.17 (2.b)
JENIS PEKERJAAN : Penanaman Biji Vegetasi dengan Teknik Mulsa (mulching)
SATUAN PEMBAYARAN : M2
A. TENAGA
1 Mandor (L03) jam 0.0583 27,142.86 1,583.33
2 Tukang (L02) jam - - -
3 Pekerja (L01) jam 0.2917 22,857.14 6,666.67
B. BAHAN
1 Biji Vegetasi Teknik Mulsa (mulching) M2 1.00 40,000.00 40,000.00
2 Air Liter 450.00 50.00 22,500.00
C. PERALATAN
1 Alat Bantu Pemasangan Ls 1.00 500.00 500.00
- Terpal, Ember, Timbangan
- Bak Penampung Air, Selang, Pompa Air
2 Water Tank Ls 1.00 8,000.00 8,000.00
I. ASUMSI
1 Menggunakan alat berat (cara mekanik)
2 Lokasi pekerjaan : sepanjang jalan
3 Kondisi existing jalan : sedang
4 Jarak rata-rata Base Camp ke lokasi pekerjaan L 20.00 KM
5 Tebal lapis agregat padat t 0.20 M Spesifikasi 5.1.3.2.d)
6 Berat isi padat Bip 1.88 ton/m3
7 Jam kerja efektif per-hari Tk 7.00 jam
25-10&10-20&20-
8 Proporsi Campuran : - Fraksi Pecah Mesin 5-10 &10-20 & 20-30 30 40.00 % Gradasi harus
- Pasir Urug (PI ≤ 6%, LL ≤ 25%) PU 60.00 % memenuhi Spec.
2. ALAT
2.a. MOTOR GRADER (E13)
Panjang hamparan Lh 25.00 M
Lebar hamparan total (untuk menetukan jumlah lintasan) W 7.00 M
Lebar kerja blade b 2.10 M
Faktor Efisiensi alat Fa 0.83 -
Kecepatan rata-rata alat v 4.00 KM/jam
Jumlah lintasan n 4.00 lintasan 2 x pp maks (SU 5-7)
Lebar Overlap bo 0.30 M
Lajur lintasan (N = W/(b-bo)) N 4.00
Waktu Siklus : Ts3
- Perataan 1 lintasan = Lh : (v x 1000) x 60 T1 0.38 menit
- Lain-lain T2 2.00 menit
Ts3 2.38 menit
3. TENAGA
Koefisien tenaga / M3 :
- Pekerja = (Tk x P) : Qt (L01) 0.3748 jam
- Mandor = (Tk x M) : Qt (L03) 0.0469 jam
I. ASUMSI
1 Menggunakan alat berat (cara mekanik)
2 Lokasi pekerjaan : sepanjang jalan
3 Kondisi existing jalan : sedang
4 Jarak rata-rata Base Camp ke lokasi pekerjaan L 20.00 KM
5 Tebal lapis agregat padat t 0.20 M Spesifikasi 5.1.3.2.d)
6 Berat isi padat Bip 1.88 ton/m3
7 Jam kerja efektif per-hari Tk 7.00 jam
25-10&10-20&20-
8 Proporsi Campuran : - Fraksi Pecah Mesin 5-10 &10-20 & 20-30 30 40.00 % Gradasi harus
- Pasir Batu (4 ≤ PI ≤10 ; LL ≤ 35 %) St 60.00 % memenuhi Spesifikasi
2. ALAT
2.a. MOTOR GRADER (E13)
Panjang hamparan Lh 25.00 M
Lebar hamparan total (untuk menetukan jumlah lintasan) W 7.00 M
Lebar efektif kerja blade b 2.10 M
Faktor Efisiensi alat Fa 0.83 -
Kecepatan rata-rata alat v 4.00 KM/jam
Jumlah lintasan n 4.00 lintasan 2 x pp maks (SU 5-7)
Lebar Overlap bo 0.30 M
Lajur lintasan (N = W/(b-bo)) N 4.00
Waktu Siklus : Ts3
- Perataan 1 lintasan = Lh : (v x 1000) x 60 T1 0.38 menit
- Lain-lain T2 1.50 menit
Ts3 1.88 menit
3. TENAGA
Koefisien tenaga / M3 :
- Pekerja = (Tk x P) : Qt - 0.2959 jam
- Mandor = (Tk x M) : Qt - 0.0370 jam
I. ASUMSI
1 Menggunakan alat berat (cara mekanik)
2 Lokasi pekerjaan : sepanjang jalan
3 Kondisi existing jalan : sedang
4 Jarak rata-rata Base Camp ke lokasi pekerjaan L 20.00 KM
5 Tebal lapis agregat padat t 0.25 M Spesifikasi 5.1.3.2.d)
6 Berat isi padat Bip 1.88 ton/m3
7 Jam kerja efektif per-hari Tk 7.00 jam
25-10&10-20&20-
8 Proporsi Campuran : - Fraksi Pecah Mesin 5-10 &10-20 & 20-30 30 40.00 % Gradasi harus
- Pasir Batu (4 ≤ PI ≤15 ; LL ≤ 35 %) St 60.00 % memenuhi Spesifikasi
2. ALAT
2.a. MOTOR GRADER (E13)
Panjang hamparan Lh 50.00 M
Lebar hamparan total (untuk menetukan jumlah lintasan) W 1.00 M
Lebar efektif kerja blade b 1.00 M
Faktor Efisiensi alat Fa 0.83 -
Kecepatan rata-rata alat v 4.00 KM/jam
Jumlah lintasan n 4.00 lintasan 2 x pp maks (SU 5-7)
Lebar Overlap bo 0.00 M
Lajur lintasan (N = W/(b-bo)) N 1.00
Waktu Siklus : Ts3
- Perataan 1 lintasan = Lh : (v x 1000) x 60 T1 0.75 menit
- Lain-lain T2 1.00 menit
Ts3 1.75 menit
3. TENAGA
Koefisien tenaga / M3 :
- Pekerja = (Tk x P) : Qt - 0.2099 jam
- Mandor = (Tk x M) : Qt - 0.0262 jam
PROYEK :
No. PAKET KONTRAK :
NAMA PAKET : Preservasi Jalan Serdang - Bojonegara - Merak
-
PROP / KAB / KODYA : Banten
ITEM PEMBAYARAN NO. : 5.1.(1)
JENIS PEKERJAAN : Lapis Fondasi Agregat Kelas A
SATUAN PEMBAYARAN : M3
A. TENAGA
B. BAHAN
C. PERALATAN
1 Motor Grader (E13) jam 0.0067 339,207.16 2,270.46
2 Vibratory Roller (E19a) jam 0.0196 345,898.64 6,794.76
3 Water Tank Truck (E23) jam 0.0020 204,742.50 411.13
4 Alat Bantu Ls 1.0000 0.00 0.00
PROYEK :
No. PAKET KONTRAK :
NAMA PAKET : Preservasi Jalan Serdang - Bojonegara - Merak
-
PROP / KAB / KODYA : Banten
ITEM PEMBAYARAN NO. : 5.1.(2)
JENIS PEKERJAAN : Lapis Fondasi Agregat Kelas B
SATUAN PEMBAYARAN : M3
A. TENAGA
B. BAHAN
C. PERALATAN
1. Motor Grader (E13) jam 0.0053 339,207.16 1,792.47
2. Vibratory Roller (E19a) jam 0.0097 345,898.64 3,368.09
3. Water Tank Truck (E23) jam 0.0020 204,742.50 411.13
4. Alat Bantu Ls 1.0000 0.00 0.00
PROYEK :
No. PAKET KONTRAK :
NAMA PAKET : Preservasi Jalan Serdang - Bojonegara - Merak
-
PROP / KAB / KODYA : Banten
ITEM PEMBAYARAN NO. : 5.1.(3)
JENIS PEKERJAAN : Lapis Fondasi Agregat Kelas S
SATUAN PEMBAYARAN : M3
A. TENAGA
B. BAHAN
C. PERALATAN
1. Motor Grader (E13) jam 0.0037 339,207.16 1,271.46
2. Vibratory Roller (E19a) jam 0.0078 345,898.64 2,694.47
3. Water Tank Truck (E13) jam 0.0020 204,742.50 411.13
4. Alat Bantu Ls 1.0000 0.00 0.00
5
I. ASUMSI
1 Menggunakan alat (cara mekanik)
2 Lokasi pekerjaan : sepanjang jalan
3 Bahan dasar (batu, pasir dan semen) diterima
seluruhnya di lokasi pekerjaan
4 Jarak rata-rata Base camp ke lokasi pekerjaan L KM
5 Jam kerja efektif per-hari Tk 7.00 jam
6 Tebal Lapis pondasi bawah beton kurus t 0.10 m
2. ALAT
3. TENAGA
Produksi Beton dalam 1 hari Qt 30.00 M3 pekerjaan wil. Selatan
Koefisien Tenaga / M3 :
- Mandor = (Tk x M) : Qt (L03) 0.4667 jam
- Tukang = (Tk x Tb) : Qt (L02) 0.7000 jam
- Pekerja = (Tk x P) : Qt (L01) 2.3333 jam
Rp. 1,098,099.40 / M2
PROYEK : ………………………………………………
NAMA PAKET : Preservasi Jalan Serdang - Bojonegara - Merak
PROP / KAB / KODYA : Banten
ITEM PEMBAYARAN NO. : 5.3.(3)
JENIS PEKERJAAN : Lapis Pondasi Bawah Beton Kurus
SATUAN PEMBAYARAN : M3
A. TENAGA
1. Pekerja (L01) jam 2.3333 22,857.14 53,333.33
2. Tukang (L02) jam 0.7000 24,285.71 17,000.00
3. Mandor (L03) jam 2.0000 27,142.86 54,285.71
B. BAHAN
1. Beton B-0 Readymix M3 1.0250 810,000.00 830,250.00
C. PERALATAN
1 Alat Bantu Ls 1.0000 0.00 0.00
2
3
4
5
HARGA HARGA
No. URAIAN KODE SATUAN YG DIGUNAKAN SATUAN
( Rp.) ( Rp.)
BIAYA
No. URAIAN KO HP KAP. SEWA KET.
DE ALAT/JAM
(di luar PPN)
I. ASUMSI
1 Menggunakan alat (cara mekanik)
2 Lokasi pekerjaan : sepanjang jalan
3 Bahan dasar (batu, pasir dan semen) diterima
seluruhnya di lokasi pekerjaan
4 Jarak rata-rata Base camp ke lokasi pekerjaan L 19.0 KM
5 Jam kerja efektif per-hari Tk 7.00 jam
6 Tebal Lapis perkerasan beton padat t 0.29 m
7 Kadar Semen Minimum (Spesifikasi) Ks 365 Kg/M3
8 Ukuran Agregat Maksimum Ag 19 mm
9 Perbandingan Air/Semen Maksimum (Spesifikasi) Wcr 0.30 -
10 Perbandingan Camp. : Semen 480.00 Kg Berdasarkan
: Fly Ash 0.00 Kg JMF & sesuai
: Pasir 450.00 Kg dgn Spesifikasi
: Agregat Halus 346.15 Kg
: Agregat Kasar 698.85 Kg
: Air 197.00 Kg
: Super - Plasticiser 1.80 Kg
: Water Reducer 1.20 Kg
11 Berat Jenis Material :
- Beton D1 2.30 T/M3
- Semen D2 1.25 T/M3
- Pasir D3 1.30 T/M3
- Agregat Kasar D4 1.28 T/M3
- Fly ash D5 1.30 T/M3
- Super - Plasticiser D6 1.18 T/M3
- Water Reducer D7 1.00 T/M3
12 Dimensi Dowel Pjg D 450.00 mm
Dia D 38.00 mm
Dimensi Tie Bar Pjg TB 600.00 mm
Pjg TB 13.00 mm
1. BAHAN
1.a. Beton Fs 45 1.0500 M3
1.b. Baja Tulangan Dowel 17.6211 Kg
1.c. Baja Tulangan Tie Bar 4.2535 Kg
1.d. Join Sealant 0.3562 Kg
1.e. Cat Anti Karat 0.0200 Kg
1.h. Curing Compound 0.8700 Ltr
3. TENAGA
Produksi Beton dalam 1 hari = Tk x Q2 Qt 139.44 M3
Koefisien Tenaga / M3 :
- Mandor = (Tk x M) : Qt (L03) 0.0502 jam
- Tukang = (Tk x Tb) : Qt (L02) 0.2510 jam
- Pekerja = (Tk x P) : Qt (L01) 0.7530 jam
Rp. 1,770,900.00 / M2
PROYEK
NAMA PAKET
PROP / KAB / KODYA
ITEM PEMBAYARAN NO. : SKh 1.5.3.(3)
JENIS PEKERJAAN : Tambalan Penuh dengan Beton Semen Cepat Mengeras Untuk Pembukaan Lalu lintas Umur Beton
Lebih Dari 3 Hari dan Kurang Dari 7 Hari
SATUAN PEMBAYARAN : M3
% TKDN
PERKIRAAN HARGA JUMLAH
NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA d
(Rp.) (Rp.)
A. TENAGA
1. Pekerja jam 0.7530 22,857.14 17,211.70 100
2. Tukang jam 0.2510 24,285.71 6,095.81 100
3. Mandor jam 0.0502 27,142.86 1,362.59 100
B. BAHAN
1. Beton Fs 45 M3 1.0500 1,225,000.00 1,286,250.00 100
2 Baja Tulangan Dowel Kg 17.6211 9,000.00 158,589.90 98
3 Baja Tulangan Tie Bar Kg 4.2535 9,000.00 38,281.50 98
4 Join Sealant Kg 0.3562 30,000.00 10,686.00 100
5 Cat Anti Karat Kg 0.0200 55,000.00 1,100.00 98
6 Curing Compound Ltr 0.8700 10,000.00 8,700.00 98
C. PERALATAN
1 Wheel Loader jam 0.0244 0.00
2 Batching Plant jam 0.0502 0.00
3 Truck Mixer jam 0.3396 - 0.00
4 Con. Vibrator jam 0.0502 59,878.23 3,005.94 75
5 Water Tank Truck jam 0.0422 204,742.50 8,633.72 75
6 Conc. Paver jam 0.0087 - 0.00
7 Alat Bantu Ls 1.0000 - 0.00
17,211.70 0
6,095.81 0
1,362.59
-
24,670.11 1.60% 0.00%
1,286,250.00 0
155,418.10 3171.798
37,515.87 765.63
10,686.00 0
1,078.00 22
8,526.00 174
-
-
-
-
2,254.45 751.48
6,475.29 2,158.43
- -
I. ASUMSI
1 Menggunakan alat berat (cara mekanik)
2 Lokasi pekerjaan : sepanjang jalan
3 Jarak rata-rata Base Camp ke lokasi pekerjaan L 11.44 KM
4 Jam kerja efektif per-hari Tk 7.00 Jam
5 Faktor kehilangan bahan Fh 1.05
6 Bahan :
- Kadar Residu Aspal Emulsi Ae 90 %
1. BAHAN
Untuk mendapatkan 1 liter Lapis Resap Pengikat Aspal Emulsi
diperlukan : ( 1 liter x Fh ) PC 1.05 liter
2. ALAT
2.a. ASPHALT DISTRIBUTOR (E41)
Lebar penyemprotan b 3.50 M
Kecepatan penyemprotan V 30.00 Km/jam
Kapasitas pompa aspal pas 100 liter/menit pemakaian efektif 2 %
Faktor effisiensi kerja Fa 0.83
Kadar aplikasi 0.85 liter/m2 Pasal 6.1.4.2).a)
Kap. Prod. / jam = pas x Fa x 60 Q1 4,980.00 liter
3. TENAGA
Produksi menentukan : AIR COMPRESSOR Q4 1,365.35 liter
Produksi Lapis Resap Pengikat / hari = Tk x Q4 Qt 9,557.45 liter
Kebutuhan tenaga :
- Pekerja P 2.00 orang
- Mandor M 1.00 orang
I. ASUMSI
1 Menggunakan alat berat (cara mekanik)
2 Lokasi pekerjaan : sepanjang jalan
3 Jarak rata-rata Base Camp ke lokasi pekerjaan L 11.44 KM
4 Jam kerja efektif per-hari Tk 7.00 Jam
5 Faktor kehilangan bahan Fh 1.05 -
6 Bahan :
- Kadar Residu Aspal Emulsi As 90 %
1. BAHAN
Untuk mendapatkan 1 liter Lapis Perekat
diperlukan : ( 1 liter x Fh ) PC 1.05 liter
2. ALAT
2.a. ASPHALT DISTRIBUTOR (E41)
Lebar penyemprotan b 3.50 M
Kecepatan penyemprotan v 30.00 M/menit
Kapasitas pompa aspal pas 100 liter/menit
Faktor effesiensi kerja Fa 0.83
Kadar aplikasi 0.25 liter/m2 Table 6.1.4.1
Kap. Prod. / jam = pas x Fa x 60 Q1 4,980.00 liter
3. TENAGA
Produksi menentukan : POWER BROOM Q4 1,232.55 liter
Produksi Lapis Perekat / hari = Tk x Q4 Qt 8,627.85 liter
Kebutuhan tenaga :
- Pekerja P 2.00 orang
- Mandor M 1.00 orang
PROYEK :
No. PAKET KONTRAK :
NAMA PAKET : Preservasi Jalan Serdang - Bojonegara - Merak
-
PROP / KAB / KODYA : Banten
ITEM PEMBAYARAN NO. : 6.1 (1) :
JENIS PEKERJAAN : Lapis Resap Pengikat - Aspal Cair/Emulsi :
SATUAN PEMBAYARAN : Liter :
A. TENAGA
B. BAHAN
C. PERALATAN
PROYEK :
No. PAKET KONTRAK :
NAMA PAKET : Preservasi Jalan Serdang - Bojonegara - Merak
-
PROP / KAB / KODYA : Banten
ITEM PEMBAYARAN NO. : 6.1 (2a) :
JENIS PEKERJAAN : Lapis Perekat - Aspal Cair/Emulsi :
SATUAN PEMBAYARAN : Liter :
A. TENAGA
B. BAHAN
C. PERALATAN
I. ASUMSI
1 Menggunakan alat berat (cara mekanik)
2 Lokasi pekerjaan : sepanjang jalan
3 Kondisi existing jalan : sedang
4 Bahan diterima di lokasi pekerjaan
5 Tebal Lapis (AC-WC L) padat t 0.04 M
6 Jam kerja efektif per-hari Tk 7.00 Jam
7 Faktor kehilangan material AC-WC: Fh1 1.05 -
Jarak AMP ke lokasi pekerjaan L 50.00 km
8 Komposisi campuran AC-WC :
- Material AC-WC sesuai job mix
Berat isi bahan :
- AC-WC ( kadar aspal 5,4 % ) D1 2.27 ton / M3
1. BAHAN
AC-WC 1.0500 ton
2. ALAT
2.a. DUMP TRUCK (DT) (E08)
Kapasitas bak V 22.00 Ton
Faktor Efisiensi alat Fa 0.83 -
Kecepatan rata-rata bermuatan v1 40.00 KM / Jam
Kecepatan rata-rata kosong v2 60.00 KM / Jam
Kapasitas AMP / batch Q2b 2.50 ton
Waktu menyiapkan 1 batch AC-WC Tb 0.50 menit
Waktu Siklus Ts2
- Mengisi Bak = (V : Q2b) x Tb T1 4.40 menit
- Angkut = (L : v1) x 60 menit T2 75.00 menit
- Tunggu + dump + Putar T3 15.00 menit
- Kembali = (L : v2) x 60 menit T4 50.00 menit
Ts2 144.40 menit
3. TENAGA
Produksi menentukan Q2 527.55 M2 / Jam
Produksi AC-WC / hari = Tk x Q2 Qt 3,693 M2
Kebutuhan tenaga :
- Pekerja P 10.00 orang
- Mandor M 1.00 orang
PROYEK :
No. PAKET KONTRAK :
NAMA PAKET : Preservasi Jalan Serdang - Bojonegara - Merak
-
PROP / KAB / KODYA : Banten
ITEM PEMBAYARAN NO. : 6.3(5a) :
JENIS PEKERJAAN : Laston Lapis Aus (AC-WC) :
SATUAN PEMBAYARAN : Ton :
A. TENAGA
B. BAHAN
C. PERALATAN
1. Dump Truck E08 Jam 0.1318 304,463.40 40,128.25
2. Asp. Finisher E02 Jam 0.0176 807,729.98 14,176.87
3. Tandem Roller E17 Jam 0.0200 403,700.18 8,055.14
4. P. Tyre Roller E18 Jam 0.0087 391,956.88 3,391.86
5. Alat Bantu Ls 1.0000 2,500.00 2,500.00
I. ASUMSI
1 Menggunakan alat berat (cara mekanik)
2 Lokasi pekerjaan : sepanjang jalan
3 Kondisi existing jalan : sedang
4 Bahan diterima di lokasi pekerjaan
5 Tebal Lapis (AC-BC ) padat t 0.06 M
6 Jam kerja efektif per-hari Tk 7.00 Jam
7 Faktor kehilangan material AC-BC: Fh1 1.05 -
Jarak AMP ke lokasi pekerjaan L 50.00 km
8 Komposisi campuran AC-BC :
- Material AC-BC sesuai job mix
1. BAHAN
AC-BC 1.0500 ton
2. ALAT
2.a. DUMP TRUCK (DT) (E08)
Kapasitas bak V 22.00 Ton
Faktor Efisiensi alat Fa 0.83 -
Kecepatan rata-rata bermuatan v1 40.00 KM / Jam
Kecepatan rata-rata kosong v2 60.00 KM / Jam
Kapasitas AMP / batch Q2b 2.50 ton
Waktu menyiapkan 1 batch AC-BC Tb 0.50 menit
Waktu Siklus Ts2
- Mengisi Bak = (V : Q2b) x Tb T1 4.40 menit
- Angkut = (L : v1) x 60 menit T2 75.00 menit
- Tunggu + dump + Putar T3 15.00 menit
- Kembali = (L : v2) x 60 menit T4 50.00 menit
Ts2 144.40 menit
3. TENAGA
Produksi menentukan Q2 534.52 M2 / Jam
Produksi AC-BC / hari = Tk x Q2 Qt 3,742 M2
Kebutuhan tenaga :
- Pekerja P 10.00 orang
- Mandor M 1.00 orang
3. TENAGA
Produksi menentukan : AMP Q2 2.00 ton
Produksi AC-BC / hari = Tk x Q5 Qt 14.00 ton
Kebutuhan tenaga :
- Pekerja P 10.00 orang
- Mandor M 1.00 orang
PROYEK :
No. PAKET KONTRAK :
NAMA PAKET : Preservasi Jalan Serdang - Bojonegara - Merak
-
PROP / KAB / KODYA : Banten
ITEM PEMBAYARAN NO. : 6.3(6a) :
JENIS PEKERJAAN : Laston Lapis Antara (AC-BC) :
SATUAN PEMBAYARAN : Ton :
A. TENAGA
B. BAHAN
C. PERALATAN
I. ASUMSI
1 Menggunakan alat berat (cara mekanik)
2 Lokasi pekerjaan : sepanjang jalan
3 Jarak rata-rata Base Camp ke lokasi pekerjaan L 11.44 KM
4 Jam kerja efektif per-hari Tk 7.00 Jam
5 Faktor kehilangan bahan Fh 1.03 -
6 Bahan :
- Bahan anti pengelupasan
1. BAHAN
Untuk mendapatkan 1 Kg Bahan Anti Pengelupasan
diperlukan : (1 liter x Fh) Pc 1.03 Kg
2. ALAT
Tidak ada alat yang digunakan (E41)
3. TENAGA
Kebutuhan tenaga :
- Pekerja P 0.00 orang
- Mandor M 0.00 orang
PROYEK :
No. PAKET KONTRAK :
NAMA PAKET : Preservasi Jalan Serdang - Bojonegara - Merak
-
PROP / KAB / KODYA : Banten
ITEM PEMBAYARAN NO. : 6.3.(8) :
JENIS PEKERJAAN : Bahan Anti Pengelupasan :
SATUAN PEMBAYARAN : Kg :
A. TENAGA
B. BAHAN
C. PERALATAN
I. ASUMSI
1 Menggunakan alat (cara mekanik)
2 Lokasi pekerjaan : sepanjang jalan
3 Bahan dasar (batu, pasir dan semen) diterima
seluruhnya di lokasi pekerjaan
4 Jarak rata-rata Base camp ke lokasi pekerjaan L 11.44 KM
5 Jam kerja efektif per-hari Tk 7.00 jam
6 Perbandingan Camp/m3 beton : Semen Sm 336.8 Kg/M3 Berdasarkan
: Pasir Ps 789.6 Kg/M3 Mix Design ACI
: Agregat Kasar Kr 1,115.8 Kg/M3
: Air Air 185 Kg/M3
: Plasticizer Plt 1.01 Kg/M3
7 Berat Isi :
- Beton D1 2.20 T/M3 Berdasarkan
- Semen D2 1.13 T/M3 Panduan Analisis
- Pasir D3 1.45 T/M3 Harga Satuan
- Agregat Kasar D4 1.45 T/M3
- Air D5 1.00 T/M3
8 Faktor kehilangan bahan : Semen Fh1 1.03
: Agregat/pasir beton Fh2 1.05
2. ALAT
2.a. CONCRETE MIXING PLANT;HZS25; 25 M3/JAM; 15 HP (E80)
Kapasitas Alat V1 500.00 M3/jam
Faktor Efisiensi Alat Fa 0.83 -
Waktu siklus : (T1 + T2 + T3 + T4) Ts
- Memuat T1 2.00 menit
- Mengaduk T2 6.00 menit
- Menuang T3 1.00 menit
- Tunggu, dll. T4 1.00 menit
Ts1 10.00 menit
3. TENAGA
Produksi Beton dalam 1 hari = Tk x Q1 Qt 50.00 M3
Kebutuhan tenaga : - Mandor M 2.00 orang
- Tukang : Tb 5.00 orang
Tk batu = 6
Tk Kayu = 24
- Pekerja P 12.00 orang
Koefisien Tenaga / M3 :
- Mandor = (Tk x M) : Qt (L03) 0.2800 jam
- Tukang = (Tk x Tb) : Qt (L02) 0.7000 jam
- Pekerja = (Tk x P) : Qt (L01) 1.6800 jam
Rp. 1,608,410.80 / M3
PROYEK :
No. PAKET KONTRAK :
NAMA PAKET : Preservasi Jalan Serdang - Bojonegara - Merak
-
PROP / KAB / KODYA : Banten
ITEM PEMBAYARAN NO. :7.1 (5a) :
JENIS PEKERJAAN :Beton struktur fc’ 30 Mpa :
SATUAN PEMBAYARAN :M3 :
A. TENAGA
B. BAHAN
C. PERALATAN
I. ASUMSI
1 Menggunakan alat (cara mekanik)
2 Lokasi pekerjaan : sepanjang jalan
3 Bahan dasar (batu, pasir dan semen) diterima
seluruhnya di lokasi pekerjaan
4 Jarak rata-rata Base camp ke lokasi pekerjaan L 11.44 KM
5 Jam kerja efektif per-hari Tk 7.00 jam
6 Perbandingan Camp. : Semen Sm 231.0 Kg/M3 Berdasarkan
: Pasir Ps 823.0 Kg/M3 Mix Design ACI
: Agregat Kasar Kr 1,264.0 Kg/M3
: Air W 162 Kg/M3
: Plasticizer Plt 0.69 Kg/M3
7 Berat Isi :
- Beton D1 2.20 T/M3 Berdasarkan
- Semen D2 1.13 T/M3 Panduan Analisis
- Pasir D3 1.45 T/M3 Harga Satuan
- Agregat Kasar D4 1.45 T/M3
- Air D5 1.00 T/M3
8 Faktor kehilangan bahan : Semen Fh1 1.03
: Agregat/pasir beton Fh2 1.05
1. BAHAN
0
1,479
1.a. Beton Fc'10 (Readymix) 1.0200 M3
1.b. Kayu Perancah dan/atau Bekisting (M19) 0.2000 M3
1.c. Paku = M19 x 12 (M18) 2.4000 Kg
1.d. Air = Air x Fh1 (M170) 166.860 Ltr
1.e. Plastizier = Plt x Fh1 (M182) 0.714 Kg
2. ALAT
2.a. CONCRETE MIXER; 500 L; 15 HP (E43)
Kapasitas Alat V 500.00 liter
Faktor Efisiensi Alat Fa 0.83 -
Waktu siklus : (T1 + T2 + T3 + T4) Ts
- Memuat T1 2.00 menit
- Mengaduk T2 6.00 menit
- Menuang T3 1.00 menit
- Tunggu, dll. T4 1.00 menit
Ts 10.00 menit
3. TENAGA
Produksi Beton dalam 1 hari = Tk x Q1 Qt 50.00 M3
Kebutuhan tenaga : - Mandor M 1.00 orang
- Tukang : Tb 5.00 orang
Tk batu = 4
Tk Kayu = 8
- Pekerja P 12.00 orang
Koefisien Tenaga / M3 :
- Mandor = (Tk x M) : Qt (L03) 0.1400 jam
- Tukang = (Tk x Tb) : Qt (L02) 0.7000 jam
- Pekerja = (Tk x P) : Qt (L01) 1.6800 jam
Rp. 1,452,674.69 / M3
PROYEK :
No. PAKET KONTRAK :
NAMA PAKET : Preservasi Jalan Serdang - Bojonegara - Merak
-
PROP / KAB / KODYA : Banten
ITEM PEMBAYARAN NO. :7.1 (10) :
JENIS PEKERJAAN :Beton struktur fc’ = 10 Mpa :
SATUAN PEMBAYARAN :M3 :
A. TENAGA
B. BAHAN
C. PERALATAN
I. ASUMSI
1 Pekerjaan dilakukan secara manual
2 Lokasi pekerjaan : sepanjang jalan
3 Bahan dasar (besi dan kawat) diterima seluruhnya
di lokasi pekerjaan
4 Jarak rata-rata Base camp ke lokasi pekerjaan L 11.44 KM
5 Jam kerja efektif per-hari Tk 7.00 jam
6 Faktor Kehilangan Besi Tulangan Fh 1.03 -
1. BAHAN
1.a. Baja Tulangan Polos BjTP 280 = 1 x Fh (M57a) 1.1000 Kg
1.b. Kawat beton (M14) 0.0200 Kg
2. ALAT
2.a. ALAT BANTU Ls
Diperlukan :
- Gunting Potong Baja
- Kunci Pembengkok Tulangan
- Alat lainnya
3. TENAGA
Produksi kerja satu hari Qt 250.00 Kg
dibutuhkan tenaga : - Mandor M 1.00 orang
- Tukang Tb 1.00 orang
- Pekerja P 4.00 orang
Koefisien Tenaga / Kg :
- Mandor = ( M x Tk ) : Qt (L03) 0.0280 jam
- Tukang = ( Tb x Tk ) : Qt (L02) 0.0280 jam
- Pekerja = ( P x Tk ) : Qt (L01) 0.1120 jam
Rp. 17,020.00 / Kg
I. ASUMSI
1 Pekerjaan dilakukan secara manual
2 Lokasi pekerjaan : sepanjang jalan
3 Bahan dasar (besi dan kawat) diterima seluruhnya
di lokasi pekerjaan
4 Jarak rata-rata Base camp ke lokasi pekerjaan L 11.44 KM
5 Jam kerja efektif per-hari Tk 7.00 jam
6 Faktor Kehilangan Besi Tulangan Fh 1.03 -
1. BAHAN
1.a. Baja Tulangan Sirip BjTS 420 A = 1 x Fh (M57a) 1.1000 Kg
1.b. Kawat beton (M14) 0.0200 Kg
2. ALAT
2.a. ALAT BANTU Ls
Diperlukan :
- Gunting Potong Baja
- Kunci Pembengkok Tulangan
- Alat lainnya
3. TENAGA
Produksi kerja satu hari Qt 300.00 Kg
dibutuhkan tenaga : - Mandor M 1.00 orang
- Tukang Tb 1.00 orang
- Pekerja P 4.00 orang
Koefisien Tenaga / Kg :
- Mandor = ( M x Tk ) : Qt (L03) 0.0233 jam
- Tukang = ( Tb x Tk ) : Qt (L02) 0.0233 jam
- Pekerja = ( P x Tk ) : Qt (L01) 0.0933 jam
Rp. 15,678.33 / Kg
PROYEK :
No. PAKET KONTRAK :
NAMA PAKET : Preservasi Jalan Serdang - Bojonegara - Merak
-
PROP / KAB / KODYA : Banten
ITEM PEMBAYARAN NO. : 7.3 (1)
JENIS PEKERJAAN : Baja Tulangan Polos BjTP 280
SATUAN PEMBAYARAN : Kg
A. TENAGA
B. BAHAN
C. PERALATAN
PROYEK :
No. PAKET KONTRAK :
NAMA PAKET : Preservasi Jalan Serdang - Bojonegara - Merak
-
PROP / KAB / KODYA : Banten
ITEM PEMBAYARAN NO. : 7.3 (3)
JENIS PEKERJAAN : Baja Tulangan Sirip BjTS 420 A
SATUAN PEMBAYARAN : Kg
A. TENAGA
B. BAHAN
C. PERALATAN
I. ASUMSI
1 Pekerjaan dilakukan secara manual/mekanis
2 Lokasi pekerjaan : di lokasi Jembatan
3 Bahan dasar (besi) dan kawat las diterima seluruhnya
di lokasi pekerjaan
4 Jarak rata-rata Base camp ke lokasi pekerjaan L 11.44 KM
5 Jam kerja efektif per-hari Tk 7.00 jam
6 Faktor Kehilangan Besi Tulangan Fh 1.03 -
1. BAHAN
1.a. Wire Mesh M8 (2,1x5,4) berat 61,79/lbr=5,45 kg/m² beton (M57a) 1.1000 Kg
2. ALAT
2.a. ALAT BANTU Ls
Diperlukan :
- Gunting Potong Baja
- Kunci Pembengkok Tulangan
- Alat lainnya
3. TENAGA
Produksi kerja satu hari Qt 400.00 Kg
dibutuhkan tenaga : - Mandor M 1.00 orang
- Tukang Tb 2.00 orang
- Pekerja P 6.00 orang
Koefisien Tenaga / Kg :
- Mandor = ( M x Tk ) : Qt (L03) 0.0175 jam
- Tukang = ( Tb x Tk ) : Qt (L02) 0.0350 jam
- Pekerja = ( P x Tk ) : Qt (L01) 0.1050 jam
Rp. 19,463.75 / Kg
PROYEK :
No. PAKET KONTRAK :
NAMA PAKET : Preservasi Jalan Serdang - Bojonegara - Merak
-
PROP / KAB / KODYA : Banten
ITEM PEMBAYARAN NO. : 7.3 (8)
JENIS PEKERJAAN : Anyaman Kawat Yang Dilas (Welded Wire Mesh)
SATUAN PEMBAYARAN : Kg
A. TENAGA
B. BAHAN
1. Wire Mesh M8 (2,1x5,4) berat 61,79/lbr=5,45 kg/m² beton Kg 1.10 12,000.00 13,200.00
C. PERALATAN
I. ASUMSI
1 Menggunakan alat (cara mekanik)
2 Lokasi pekerjaan : sepanjang jalan
3 Bahan dasar (batu, pasir dan semen) diterima
seluruhnya di lokasi pekerjaan
4 Jarak rata-rata Base camp ke lokasi pekerjaan L 11.44 KM
5 Jam kerja efektif per-hari Tk 7.00 jam
6 Perbandingan Pasir & Semen : - Volume Semen Sm 25 % Spec.
: - Volume Pasir Ps 75 % Spec.
7 Perbandingan Batu & Mortar :
- Batu Bt 65 %
- Mortar (campuran semen & pasir) Mr 35 %
8 Berat Jenis Bahan :
- Pasangan Batu Dengan Mortar D1 2.40 ton/M3
- Batu D2 1.60 ton/M3
- Adukan (mortar) D3 1.80 ton/M3
- Pasir D4 1.30 ton/M3
- Semen Portland D5 1.44 ton/M3
1. BAHAN
1.a. Batu -----> {(Bt x D1 x 1 M3) : D2} x 1.05 (M02) 1.0238 M3 Lepas
1.b. Semen ----> Sm x {(Mr x D1 x 1 M3} : D3} x 1.03 (M12) 0.1202 M3
x {D5 x (1000)} (M12) 173.00 Kg
1.c. Pasir -----> Ps x {(Mr x D1 x 1 M3) : D4} x 1.05 (M01a) 0.5088 M3
2. ALAT
2.a. CONCRETE MIXER (E06)
Kapasitas Alat V 500.00 liter
Faktor Efisiensi Alat Fa 0.83 -
Waktu siklus : (T1 + T2 + T3 + T4) Ts
- Memuat T1 4.00 menit
- Mengaduk T2 4.00 menit
- Menuang T3 1.00 menit
- Tunggu, dll. T4 1.00 menit
Ts 10.00 menit
3. TENAGA
Produksi menetukan : Produksi Concrete Mxer Q1 2.490 M3/Jam
Produksi Pasangan Batu dengan Mortar / hari = Tk x Q1 Qt 17.43 M3
Kebutuhan tenaga : - Mandor M 1.00 orang
- Tukang Batu Tb 4.00 orang
- Pekerja P 8.00 orang
Koefisien Tenaga / M3 :
- Mandor = (Tk x M) : Qt (L03) 0.4016 jam
- Tukang = (Tk x Tb) : Qt (L02) 1.6064 jam
- Pekerja = (Tk x P) : Qt (L01) 3.2129 jam
Rp. 740,977.66 / M3
I. ASUMSI
1 Menggunakan alat (cara mekanik)
2 Lokasi pekerjaan : sepanjang jalan
3 Bahan dasar (batu, pasir dan semen) diterima
seluruhnya di lokasi pekerjaan
4 Jarak rata-rata Base camp ke lokasi pekerjaan L 11.44 KM
5 Jam kerja efektif per-hari Tk 7.00 jam
6 Pengisi celah Pasangan Batu Kosong adalah beton 15 MPa - - -
Perbandingan Camp. : Semen Sm 264.0 Kg/M3 max size 25mm
: Pasir Ps 896.0 Kg/M3
: Agregat Kasar Kr 1,075.0 Kg/M3
: Air W 185 Kg/M3
: Plasticizer Plt 0.79 Kg/M3
1. BAHAN
1.a. Semen (PC) = Sm x 1.03 x Ae/100 (M12) 73.418 Kg
1.b. Pasir = (Ps/1000 : D3) x 1.05 x Ae/100 (M01) 0.2419 M3
1.c. Agregat Kasar = (Kr/1000 : D4) x 1.05 x Ae/100 (M03) 0.2102 M3
1.d. Air = W x 1.03 x Ae/100 (M170) 51.45 Ltr
1.e. Plastizier = Plt x 1.03 x Ae/100 (M182) 0.2203 Kg
1.f. Batu Belah = Bt/100 x D1/D5 x 1.05 (M06) 1.2972 M3
2. ALAT
2.a. CONCRETE MIXER (E06)
Kapasitas Alat V 500.00 liter
Faktor Efisiensi Alat Fa 0.83 -
Waktu siklus : (T1 + T2 + T3 + T4) Ts
- Memuat T1 2.00 menit sudah diselesaikan
- Mengaduk T2 6.00 menit
- Menuang T3 1.00 menit
- Tunggu, dll. T4 1.00 menit
Ts 10.00 menit
3. TENAGA
Produksi Beton dalam 1 hari = Tk x Q1 Qt 17.43 M3
Koefisien Tenaga / M3 :
- Mandor = (Tk x M) : Qt (L03) 0.4016 jam
- Tukang = (Tk x Tb) : Qt (L02) 2.8112 jam
- Pekerja = (Tk x P) : Qt (L01) 5.6225 jam
Rp. 763,836.59 / M3
I. ASUMSI
1 Pekerjaan dilakukan secara manual
2 Lokasi pekerjaan : sepanjang jalan
3 Bronjong dengan kawat dilapisi galvanis diterima
seluruhnya di lokasi pekerjaan
4 Jarak rata-rata Base camp ke lokasi pekerjaan L 11.44 KM
5 Jam kerja efektif per-hari Tk 7.00 jam
6 Faktor Kehilangan Material Fh 1.05 -
1. BAHAN
1.a. Bronjong dengan kawat dilapisi galvanis (M15a) 15.00 Kg
1.b. Batu (M02) 1.1000 M3
2. ALAT
2.a. ALAT BANTU
Diperlukan :
- Tang = 2 buah
- Pemotong kawat = 2 buah
- Palu pemecah batu = 2 buah
3. TENAGA
Produksi pekerjaan per hari Qt 50.00 M3
dibutuhkan tenaga : - Mandor M 1.00 orang
- Tukang Tb 3.00 orang
- Pekerja P 6.00 orang
Koefisien Tenaga / M3
- Mandor = ( M x Tk ) : Qt (L03) 0.1400 jam
- Tukang = ( Tb x Tk ) : Qt (L02) 0.4200 jam
- Pekerja = ( P x Tk ) : Qt (L01) 0.8400 jam
Rp. 552,230.00 / M3
PROYEK :
No. PAKET KONTRAK :
NAMA PAKET : Preservasi Jalan Serdang - Bojonegara - Merak
-
PROP / KAB / KODYA : Banten
ITEM PEMBAYARAN NO. : 7.9.(1)
JENIS PEKERJAAN : Pasangan Batu
SATUAN PEMBAYARAN : M3
A. TENAGA
B. BAHAN
C. PERALATAN
PROYEK :
No. PAKET KONTRAK :
NAMA PAKET : Preservasi Jalan Serdang - Bojonegara - Merak
-
PROP / KAB / KODYA : Banten
ITEM PEMBAYARAN NO. : 7.10 (1) PERKIRAAN VOL. PEK. : #REF!
JENIS PEKERJAAN : Pasangan Batu Kosong Yang Diisi Adukan TOTAL HARGA (Rp.) : #REF!
SATUAN PEMBAYARAN : M3 % THD. BIAYA PROYEK : #REF!
A. TENAGA
B. BAHAN
C. PERALATAN
PROYEK :
No. PAKET KONTRAK :
NAMA PAKET : Preservasi Jalan Serdang - Bojonegara - Merak
-
PROP / KAB / KODYA : Banten
ITEM PEMBAYARAN NO. : 7.10.(3a)
JENIS PEKERJAAN : Bronjong dengan kawat yang dilapisi galvanis
SATUAN PEMBAYARAN : M3
A. TENAGA
B. BAHAN
C. PERALATAN
I. ASUMSI
1 Menggunakan alat (cara mekanik)
2 Lokasi pekerjaan di lokasi jembatan
3 Bahan / material diterima seluruhnya di lokasi
pekerjaan proyek
4 Jarak rata-rata Base camp ke lokasi pekerjaan L 11.44 KM
5 Jam kerja efektif per-hari Tk 7.00 jam
1. BAHAN
1.a. Marmer 0.750 M2
1.b. Adukan Semen 0.0015 M3
2. ALAT
2.a. Alat bantu pertukangan
3. TENAGA
Produksi Papan Nama dalam 1 hari
Qt 3.00 Buah
Koefisien Tenaga / Bh :
- Mandor = (Tk x M) : Qt (L03) 2.33 jam
- Tukang = (Tk x Tb) : Qt (L02) 2.33 jam
- Pekerja = (Tk x P) : Qt (L01) 4.67 jam
PROYEK :
No. PAKET KONTRAK :
NAMA PAKET : Preservasi Jalan Serdang - Bojonegara - Merak
-
PROP / KAB / KODYA : Banten
ITEM PEMBAYARAN NO. : 7.14.(1)
JENIS PEKERJAAN : Papan Nama Jembatan
SATUAN PEMBAYARAN : Buah
A. TENAGA
B. BAHAN
C. PERALATAN
I. ASUMSI
1 Menggunakan alat (cara mekanik)
2 Beton berdasarkan analisa item pekerjaan ybs
3 Baja tulangan berdasarkan analisa item ybs
4 Jarak rata-rata Base camp ke lokasi pekerjaan L 18.48 KM
5 Jam kerja efektif per-hari Tk 7.00 jam
6 Panjang Tiang p 12.00 M
7 Ukuran diameter tiang bor beton Uk 0.60 M
8 Kebutuhan Baja tulangan Mb 120 Kg/M3
9 Faktor kehilangan Fh 1.08
1. BAHAN
1.a. Beton Memadat Sendiri fc 20 MPa = {1/4 Phi x (Uk)^2) x 1m x Fh (M252) 0.3054 M3
1.b. Baja Tulangan = (EI-715 x Mb) (M57a) 36.6435 Kg
1.c. Casing = Phi x Uk 1.8850 M2
2. ALAT
3. TENAGA
Produksi menentukan : BORE PILE MACHINE Q1 3.86 M'/jam
Pengeboran Tiang Bor Beton / hari = Tk x Q1 Qt 26.99 M
- Mandor M 1.00 orang
- Tukang T 3.00 orang
- Pekerja P 6.00 orang
I. ASUMSI
1 Menggunakan alat (cara mekanik)
2 Beton berdasarkan analisa item pekerjaan ybs
3 Baja tulangan berdasarkan analisa item ybs
4 Jarak rata-rata Base camp ke lokasi pekerjaan L 18.48 KM
5 Jam kerja efektif per-hari Tk 7.00 jam
6 Panjang Tiang p 12.00 M
7 Ukuran diameter tiang bor beton Uk 0.30 M
8 Kebutuhan Baja tulangan Mb 120 Kg/M3
9 Faktor kehilangan Fh 1.03
1. BAHAN
1.a. Beton Memadat Sendiri fc 20 MPa = {1/4 Phi x (Uk)^2) x 1m x Fh (M252) 0.0728 M3
1.b. Baja Tulangan = (EI-715 x Mb) (M57a) 8.7368 Kg
1.c. Casing = Phi x Uk 0.9425 M2
2. ALAT
3. TENAGA
Produksi menentukan : BORE PILE MACHINE Q1 4.27 M'/jam
Pengeboran Tiang Bor Beton / hari = Tk x Q1 Qt 29.88 M
- Mandor M 1.00 orang
- Tukang T 3.00 orang
- Pekerja P 6.00 orang
PROYEK :
No. PAKET KONTRAK :
NAMA PAKET : Rehabilitasi Jalan Dan Jembatan Ruas Cipanas - Warung Banten
-
PROP / KAB / KODYA : Banten
ITEM PEMBAYARAN NO. : 7.6.(19a)
JENIS PEKERJAAN : Tiang Bor Beton, diameter 600 mm
SATUAN PEMBAYARAN :M
A. TENAGA
B. BAHAN
C. PERALATAN
PROYEK :
No. PAKET KONTRAK :
NAMA PAKET : Rehabilitasi Jalan Dan Jembatan Ruas Cipanas - Warung Banten
-
PROP / KAB / KODYA : Banten
ITEM PEMBAYARAN NO. : 7.6.(19a)
JENIS PEKERJAAN : Tiang Bor Beton, diameter 300 mm
SATUAN PEMBAYARAN :M
A. TENAGA
B. BAHAN
C. PERALATAN
I. ASUMSI
1 PC I Girder dicetak di lokasi Pekerjaan
2 Jam kerja efektif per-hari Tk 7.00 jam
3 Tinggi PC I Girder H 1.60 M
4 Bentang PC I Girder L ?? M
5 Menggunakan beton K500
6 Komponen baja tulangan 250 kg/m3
7 Faktor kehilangan bahan 1.10
2. ALAT
2.a CRANE 1 (E31)
Kapasitas V2 1.00 Buah sepasang
Faktor Efisiensi alat Fa 0.83 -
Waktu siklus
- Waktu memuat dan membongkar T1 30.00 menit
- dan lain-lain ( termasuk mengatur dan menggeser) T2 15.00 menit
Ts2 45.00 menit
3. TENAGA
Produksi per hari (tergantung pada pekerjaan pembesian) Qt 7.00 Buah
Kebutuhan tenaga (di lokasi pekerjaan) :
- Mandor M 1.00 orang
- Tukang Tb 5.00 orang
- Pekerja P 18.00 orang
Koefisien Tenaga / M3 :
- Mandor = (Tk x M) : Qt (L03) 1.00 jam
- Tukang = (Tk x Tb) : Qt (L02) 5.00 jam
- Pekerja = (Tk x P) : Qt (L01) 18.00 jam
ITEM PEMBAYARAN NO. : 7.2 (1b) #REF!
JENIS PEKERJAAN : Unit Pracetak Gelagar U Penyediaan Unit Pracetak Gelagar Tipe U Bentang 16 meter
SATUAN PEMBAYARAN : Buah URAIAN ANALISA HARGA SATUAN
I. ASUMSI
1 PC I Girder dicetak di lokasi Pekerjaan
2 Jam kerja efektif per-hari Tk 7.00 jam
3 Tinggi PC I Girder H 0.00 M
4 Bentang PC I Girder L 0.00 M
5 Menggunakan beton K500
6 Komponen baja tulangan 250 kg/m3
7 Faktor kehilangan bahan 1.10
2. ALAT
2.a CRANE 1 (E31)
Kapasitas V2 1.00 Buah sepasang
Faktor Efisiensi alat Fa 0.83 -
Waktu siklus
- Waktu memuat dan membongkar T1 25.00 menit
- dan lain-lain ( termasuk mengatur dan menggeser) T2 15.00 menit
Ts2 40.00 menit
3. TENAGA
Produksi per hari (tergantung pada pekerjaan pembesian) Qt 7.00 Buah
Kebutuhan tenaga (di lokasi pekerjaan) :
- Mandor M 1.00 orang
- Tukang Tb 2.00 orang
- Pekerja P 8.00 orang
Koefisien Tenaga / M3 :
- Mandor = (Tk x M) : Qt (L03) 1.00 jam
- Tukang = (Tk x Tb) : Qt (L02) 2.00 jam
- Pekerja = (Tk x P) : Qt (L01) 8.00 jam
ITEM PEMBAYARAN NO. : 7.2 (2b) #REF!
JENIS PEKERJAAN : Pemasangan Unit Pracetak Gelagar Tipe I Bentang 16 meter
SATUAN PEMBAYARAN : Buah URAIAN ANALISA HARGA SATUAN
I. ASUMSI
1 PC I Girder dicetak di lokasi Pekerjaan
2 Jam kerja efektif per-hari Tk 7.00 jam
3 Tinggi PC I Girder H 1.60 M
4 Bentang PC I Girder L ?? M
5 Menggunakan beton K500
6 Komponen baja tulangan 250 kg/m3
7 Faktor kehilangan bahan 1.10
2. ALAT
2.a CRANE 1 (E31)
Kapasitas V2 1.00 Buah sepasang
Faktor Efisiensi alat Fa 0.83 -
Waktu siklus
- Waktu memuat dan membongkar T1 30.00 menit
- dan lain-lain ( termasuk mengatur dan menggeser) T2 15.00 menit
Ts2 45.00 menit
3. TENAGA
Produksi per hari (tergantung pada pekerjaan pembesian) Qt 7.00 Buah
Kebutuhan tenaga (di lokasi pekerjaan) :
- Mandor M 1.00 orang
- Tukang Tb 5.00 orang
- Pekerja P 18.00 orang
Koefisien Tenaga / M3 :
- Mandor = (Tk x M) : Qt (L03) 1.00 jam
- Tukang = (Tk x Tb) : Qt (L02) 5.00 jam
- Pekerja = (Tk x P) : Qt (L01) 18.00 jam
ITEM PEMBAYARAN NO. : 7.2 (1c) #REF!
JENIS PEKERJAAN : Unit Pracetak Gelagar U Penyediaan Unit Pracetak Gelagar Tipe U Bentang 10 meter
SATUAN PEMBAYARAN : Buah URAIAN ANALISA HARGA SATUAN
I. ASUMSI
1 PC I Girder dicetak di lokasi Pekerjaan
2 Jam kerja efektif per-hari Tk 7.00 jam
3 Tinggi PC I Girder H 0.00 M
4 Bentang PC I Girder L 0.00 M
5 Menggunakan beton K500
6 Komponen baja tulangan 250 kg/m3
7 Faktor kehilangan bahan 1.10
2. ALAT
2.a CRANE 1 (E31)
Kapasitas V2 1.00 Buah sepasang
Faktor Efisiensi alat Fa 0.83 -
Waktu siklus
- Waktu memuat dan membongkar T1 25.00 menit
- dan lain-lain ( termasuk mengatur dan menggeser) T2 15.00 menit
Ts2 40.00 menit
3. TENAGA
Produksi per hari (tergantung pada pekerjaan pembesian) Qt 7.00 Buah
Kebutuhan tenaga (di lokasi pekerjaan) :
- Mandor M 1.00 orang
- Tukang Tb 2.00 orang
- Pekerja P 8.00 orang
Koefisien Tenaga / M3 :
- Mandor = (Tk x M) : Qt (L03) 1.00 jam
- Tukang = (Tk x Tb) : Qt (L02) 2.00 jam
- Pekerja = (Tk x P) : Qt (L01) 8.00 jam
ITEM PEMBAYARAN NO. : 7.2 (2a) #REF!
JENIS PEKERJAAN : Pemasangan Unit Pracetak Gelagar Tipe I Bentang 10 meter
SATUAN PEMBAYARAN : Buah URAIAN ANALISA HARGA SATUAN
I. ASUMSI
1 PC Diafragma dicetak di lokasi proyek K 350
2 Lokasi pekerjaan : di setiap jembatan
3 Bahan diterima di lokasi jembatan
4 Jam kerja efektif per-hari Tk 7.00 jam
5 Faktor kehilangan bahan 1.1 1.10
6 Ukuran 1.65 x 1.20 x 0.3 0.3960 M3
7 tulangan 150 kg/m3
1. BAHAN
- Pracetak PC Diafragma bentang K 350 0.3960 m3
- tulangan 59.4000 kg
2.
ALAT
3. TENAGA
Produksi per hari (unloading) = Q2 x Tk Qt 46.48 Buah
Kebutuhan tenaga (di lokasi pekerjaan) :
- Mandor M 1.00 orang
- Tukang Tb 5.00 orang
- Pekerja P 10.00 orang
Koefisien Tenaga / M3 :
- Mandor = (Tk x M) : Qt (L03) 0.1506 jam
- Tukang = (Tk x Tb) : Qt (L02) 0.7530 jam
- Pekerja = (Tk x P) : Qt (L01) 1.5060 jam
PROYEK :
No. PAKET KONTRAK : ………………………………………………
NAMA PAKET : Preservasi Jalan Serdang - Bojonegara - Merak
(Rp.) (Rp.)
A. TENAGA
B. BAHAN
C. PERALATAN
1. Crane 1 (E31) 459,000.09 0.00
2 Crane 2 (E31) 459,000.09 0.00
3 Alat Bantu LS 0.00 0.00
PROYEK :
No. PAKET KONTRAK : ………………………………………………
NAMA PAKET : Preservasi Jalan Serdang - Bojonegara - Merak
(Rp.) (Rp.)
A. TENAGA
B. BAHAN
C. PERALATAN
PROYEK :
No. PAKET KONTRAK : ………………………………………………
NAMA PAKET : Preservasi Jalan Serdang - Bojonegara - Merak
(Rp.) (Rp.)
A. TENAGA
B. BAHAN
C. PERALATAN
1. Crane 1 (E31) 459,000.09 0.00
2 Crane 2 (E31) 459,000.09 0.00
3 Alat Bantu LS 0.00 0.00
PROYEK :
No. PAKET KONTRAK : ………………………………………………
NAMA PAKET : Preservasi Jalan Serdang - Bojonegara - Merak
(Rp.) (Rp.)
A. TENAGA
B. BAHAN
C. PERALATAN
PROYEK :
No. PAKET KONTRAK : ………………………………………………
NAMA PAKET : Preservasi Jalan Serdang - Bojonegara - Merak
A. TENAGA
B. BAHAN
C. PERALATAN
I. ASUMSI
1 Pekerjaan dilakukan secara manual
2 Lokasi pekerjaan : sepanjang jalan
3 Bahan dasar (besi dan kawat) diterima seluruhnya
di lokasi pekerjaan
4 Jarak rata-rata Base camp ke lokasi pekerjaan L 11.44 KM
5 Jam kerja efektif per-hari Tk 7.00 jam
6 Faktor Kehilangan Material Fh 1.03 -
7 Tebal lapisan cat secara manual t 0.0020 M
8 Berat Jenis Bahan Cat BJ.Cat Kg/Liter
9 Perbandingan pemakaian bahan : - Cat C 100.00 %
1. BAHAN
1.a. Cat Marka Thermoplastic = 1x1x t x Fh (M17b) 2.0600 Kg
1.b. Glass Bead = 0,45 x Fh 0.4635 Kg
2. ALAT
2.a. THERMOPLASTIC SPREADING MACHINE
Kapasitas penyemprotan V 40.00 Ltr/Jam
Jumlah cat cair = (1 M x 1 M) x t x 1000 R 3.00 Ltr/M2
Waktu siklus: Ts
- Pemanasan T1 10.00 menit
- Penyemprotan T2 3.00 menit
- Lain-lain T3 2.00 menit
Ts 15.00 menit
Kap. Prod. / Jam = V:R Q1 13.33 M2/Jam
3. TENAGA
Produksi pekerjaan per hari = Q1 x Tk Qt 93.33 M2
dibutuhkan tenaga : - Mandor M 1.00 orang
- Tukang Cat Tb 1.00 orang
- Pekerja P 8.00 orang
Koefisien Tenaga / M2 :
- Mandor = ( M x Tk ) : Qt (L03) 0.0750 jam
- Tukang = ( Tb x Tk ) : Qt (L02) 0.0750 jam
- Pekerja = ( P x Tk ) : Qt (L01) 0.6000 jam
Rp. 163,302.11 / M2
PROYEK :
No. PAKET KONTRAK :
NAMA PAKET : Preservasi Jalan Serdang - Bojonegara - Merak
PROP / KAB / KODYA : Banten
ITEM PEMBAYARAN NO. : 9.2.(1)
JENIS PEKERJAAN : Marka Jalan Termoplastik
SATUAN PEMBAYARAN : M2
A. TENAGA
B. BAHAN
C. PERALATAN
I. ASUMSI
1 Menggunakan cara manual
2 Lokasi pekerjaan : sepanjang jalan
3 Bahan dasar (plat rambu jadi, pipa dan beton cetak)
diangkut dengan Truk ke lokasi pekerjaan
4 Jarak rata-rata Base camp ke lokasi pekerjaan L 11.44 KM
5 Jam kerja efektif per-hari Tk 7.00 jam
1. BAHAN
1.a. Pelat Rambu Jadi (Engineering Grade) (M35a) 1.00 Buah
1.b. Pipa Galvanis Dia. 5" (M24) 1.00 Batang gambar
1.c. Beton fc 20 MPa (M60) 0.016 M3
2. ALAT
2.a. DUMP TRUCK 4m3 (E08)
Kapasitas 1 kali Angkut Cp 30.0 Buah
Waktu Siklus : Ts
- Memuat = atur, ikat, dll. T1 30.0 menit
- Angkut = (2 x L : 25 Km/Jam) x 60 menit T2 54.9 menit
- Menurunkan = Rata-rata 0,5 menit / buah T3 15.0 menit
- Lain-lain = geser, atur, tunggu, dll. T4 30.0 menit
Ts 129.9 menit
3. TENAGA
Produksi pemasangan rambu dalam 1 hari = Tk x Q1 Qt 96.99 Buah
Kebutuhan tenaga : - Mandor M 1.00 orang
- Tukang Tb 2.00 orang
- Pekerja P 15.00 orang
Koefisien Tenaga / Buah :
- Mandor = (Tk x M) : Qt (L03) 0.0722 jam
- Tukang = (Tk x Tb) : Qt (L02) 0.1444 jam
- Pekerja = (Tk x P) : Qt (L01) 1.0826 jam
I. ASUMSI
1 Menggunakan cara manual
2 Lokasi pekerjaan : sepanjang jalan
3 Bahan dasar (plat rambu jadi, pipa dan beton cetak)
diangkut dengan Truk ke lokasi pekerjaan
4 Jarak rata-rata Base camp ke lokasi pekerjaan L 11.44 KM
5 Jam kerja efektif per-hari Tk 7.00 jam
1. BAHAN
1.a. Pelat Rambu Jadi (Engineering Grade) (M35a) 2.00 Buah termasuk lengan
1.b. Pipa Galvanis Dia.5" (M24) 1.00 Batang
1.c. Beton fc 20 Mpa (M60) 0.016 M3
2. ALAT
2.a. DUMP TRUCK 3- 4 M3 (E08)
Kapasitas 1 kali Angkut Cp 20.0 Buah
Waktu Siklus : Ts
- Memuat = atur, ikat, dll. T1 30.0 menit
- Angkut = (2 x L : 25 Km/Jam) x 60 menit T2 54.9 menit
- Menurunkan = Rata-rata 2.5 menit / buah T3 10.0 menit
- Lain-lain = geser, atur, tunggu, dll. T4 30.0 menit
Ts 124.9 menit
3. TENAGA
Produksi pemasangan rambu dalam 1 hari = Tk x Q1 Qt 67.25 Buah
Kebutuhan tenaga : - Mandor M 1.00 orang
- Tukang Tb 2.00 orang
- Pekerja P 15.00 orang
Koefisien Tenaga / Buah :
- Mandor = (Tk x M) : Qt (L03) 0.1041 jam
- Tukang = (Tk x Tb) : Qt (L02) 0.2082 jam
- Pekerja = (Tk x P) : Qt (L01) 1.5614 jam
I. ASUMSI
1 Menggunakan cara manual
2 Lokasi pekerjaan : sepanjang jalan
3 Bahan dasar (patok kilometer beton cetak)
diangkut dengan Truk ke lokasi pekerjaan
4 Jarak rata-rata Base camp ke lokasi pekerjaan L 11.44 KM
5 Jam kerja efektif per-hari Tk 7.00 jam
6 Faktor kehilangan bahan Fh 1.03 -
7 Tulangan praktis Rc 50.00 Kg/M3
2. ALAT
2.a. DUMP TRUCK (E08)
Kapasitas 1 kali Angkut Cp 15.0 Buah
Waktu Siklus : Ts
- Memuat = muat, atur, ikat, dll T1 20.0 menit
- Angkut = (2 x L : 25 Km/Jam) x 60 T2 54.92 menit
- Menurunkan = Rata-rata 1.5 menit / buah T3 22.5 menit
- Lain-lain = geser, tunggu, dll T4 10.0 menit
Ts 107.4 menit
3. TENAGA
Produksi pasang patok kilometer / hari = Tk x Q1 Qt 58.65 Buah
Kebutuhan tenaga : - Mandor M 1.00 orang
- Tukang Tb 2.00 orang
- Pekerja P 5.00 orang
Koefisien Tenaga / Buah :
- Mandor = (Tk x M) : Qt (L03) 0.1194 jam
- Tukang = (Tk x Tb) : Qt (L02) 0.2387 jam
- Pekerja = (Tk x P) : Qt (L01) 0.5968 jam
PROYEK :
No. PAKET KONTRAK :
NAMA PAKET : Preservasi Jalan Serdang - Bojonegara - Merak
PROP / KAB / KODYA : Banten
ITEM PEMBAYARAN NO. : 9.2.(3a)
JENIS PEKERJAAN : Rambu Jalan Tunggal dengan Permukaan Pemantul Engineering Grade
SATUAN PEMBAYARAN : Buah
A. TENAGA
B. BAHAN
C. PERALATAN
PROYEK :
No. PAKET KONTRAK :
NAMA PAKET : Preservasi Jalan Serdang - Bojonegara - Merak
PROP / KAB / KODYA : Banten
ITEM PEMBAYARAN NO. : 9.2.(3b) PERKIRAAN VOL. PEK. : #REF!
JENIS PEKERJAAN : Rambu Jalan Ganda dengan Permukaan PemantTOTAL HARGA (Rp.) : #REF!
SATUAN PEMBAYARAN : Buah % THD. BIAYA PROYEK : #REF!
A. TENAGA
B. BAHAN
C. PERALATAN
PROYEK :
No. PAKET KONTRAK :
NAMA PAKET : Preservasi Jalan Serdang - Bojonegara - Merak
PROP / KAB / KODYA : Banten
ITEM PEMBAYARAN NO. : 9.2.(6a) PERKIRAAN VOL. PEK. : #REF!
JENIS PEKERJAAN : Patok Kilometer TOTAL HARGA (Rp.) : #REF!
SATUAN PEMBAYARAN : Buah % THD. BIAYA PROYEK : #REF!
A. TENAGA
B. BAHAN
C. PERALATAN
I. ASUMSI
1 Menggunakan cara manual
2 Lokasi pekerjaan : sepanjang jalan
3 Bahan dasar rel pengaman diterima di lokasi pekerjaan
4 Jarak rata-rata Base camp ke lokasi pekerjaan L 11.44 Km ukuran
5 Jam kerja efektif per-hari Tk 7.00 jam sesuai
6 Faktor kehilangan bahan Fh 1.03 - drawing
2. ALAT
2.a DUMP TRUCK (E08)
Kapasitas 1 kali Angkut Cp 15.0 M'
Waktu Siklus : Ts
- Memuat T1 50.0 menit
- Angkut = (2 x L : 25 Km/Jam) x 60 T2 54.92 menit
- Menurunkan T3 60.0 menit
- Lain-lain T4 30.0 menit
Ts 194.9 menit
3. TENAGA
Produksi pasang pagar pengaman / hari = Tk x Q1 Qt 32.32 M'
Kebutuhan tenaga : - Mandor M 1.00 orang
- Tukang Tb 2.00 orang
- Pekerja P 8.00 orang
Koefisien Tenaga / M' :
- Mandor = (Tk x M) : Qt (L03) 0.2166 jam
- Tukang = (Tk x Tb) : Qt (L02) 0.4331 jam
- Pekerja = (Tk x P) : Qt (L01) 1.7326 jam
PROYEK :
No. PAKET KONTRAK :
NAMA PAKET : Preservasi Jalan Serdang - Bojonegara - Merak
PROP / KAB / KODYA : Banten
ITEM PEMBAYARAN NO. : 9.2.(7)
JENIS PEKERJAAN : Rel Pengaman
SATUAN PEMBAYARAN : M2
A. PEKERJA
B. BAHAN
1. Rel Pengaman ( Termasuk Tiang Blok Baut (M36) M' 1.0300 450,000.00 463,500.00
C. PERALATAN
I. ASUMSI
1 Menggunakan cara manual
2 Lokasi pekerjaan : sepanjang jalan
3 Bahan dasar kerb pracetak jenis-1 dibuat di base camp, kemudian
diangkut dengan Truk ke lokasi pekerjaan
4 Jarak rata-rata Base camp ke lokasi pekerjaan L 11.44 KM
5 Jam kerja efektif per-hari Tk 7.00 jam
6 Faktor kehilangan bahan Fh 1.05 -
2. ALAT
2.a. Flat Bed Truck (E11)
Kapsitas Bak Cp 36.00 Buah
Waktu Siklus : Ts
- Memuat = naik & atur rata-rata 3 menit/m T1 24.00 menit
- Angkut V=30 Km/jam = Lef x V x 60 T2 22.88 menit
- Kembali V=50 Km/jam = Lef x V x 60 T3 13.73 menit
- Menurunkan = Rata-rata 2 menit/m T4 36.00 menit
- Lain-lain = geser, atur, tunggu dll T5 7.00 menit
Ts 103.61 menit
3. TENAGA
Produksi pasang kerb pracetak / hari = Tk x Q1 Qt 145.93 M'
Kebutuhan tenaga : - Mandor M 1.00 orang
- Tukang Tb 4.00 orang
- Pekerja P 10.00 orang
Koefisien Tenaga / Buah :
- Mandor = (Tk x M) : Qt (L03) 0.0480 jam
- Tukang = (Tk x Tb) : Qt (L02) 0.1919 jam
- Pekerja = (Tk x P) : Qt (L01) 0.4797 jam
I. ASUMSI
1 Menggunakan cara manual
2 Lokasi pekerjaan : sepanjang jalan
3 Bahan dasar kerb pracetak jenis-1 dibuat di base camp, kemudian
diangkut dengan Truk ke lokasi pekerjaan
4 Jarak rata-rata Base camp ke lokasi pekerjaan L 11.44 KM
5 Jam kerja efektif per-hari Tk 7.00 jam
6 Faktor kehilangan bahan Fh 1.05 -
2. ALAT
3. TENAGA
Produksi pasang kerb pracetak / hari = Tk x Q1 Qt 95.62 M'
Kebutuhan tenaga : - Mandor M 1.00 orang
- Tukang Tb 4.00 orang
- Pekerja P 10.00 orang
Koefisien Tenaga / Buah :
- Mandor = (Tk x M) : Qt (L03) 0.0732 jam
- Tukang = (Tk x Tb) : Qt (L02) 0.2928 jam
- Pekerja = (Tk x P) : Qt (L01) 0.7321 jam
I. ASUMSI
1 Menggunakan cara manual
2 Lokasi pekerjaan : sepanjang jalan
3 Bahan dasar kerb pracetak jenis-1 dibuat di base camp, kemudian
diangkut dengan Truk ke lokasi pekerjaan
4 Jarak rata-rata Base camp ke lokasi pekerjaan L 11.44 KM
5 Jam kerja efektif per-hari Tk 7.00 jam
6 Faktor kehilangan bahan Fh 1.05 -
2. ALAT
3. TENAGA
Produksi pasang kerb pracetak / hari = Tk x Q1 Qt 152.34 M'
Kebutuhan tenaga : - Mandor M 1.00 orang
- Tukang Tb 4.00 orang
- Pekerja P 10.00 orang
Koefisien Tenaga / Buah :
- Mandor = (Tk x M) : Qt (L03) 0.0459 jam
- Tukang = (Tk x Tb) : Qt (L02) 0.1838 jam
- Pekerja = (Tk x P) : Qt (L01) 0.4595 jam
I. ASUMSI
1 Menggunakan cara manual
2 Lokasi pekerjaan : sepanjang jalan
3 Bahan dasar kerb pracetak jenis-1 dibuat di base camp, kemudian
diangkut dengan Truk ke lokasi pekerjaan
4 Jarak rata-rata Base camp ke lokasi pekerjaan L 11.44 KM
5 Jam kerja efektif per-hari Tk 7.00 jam
6 Faktor kehilangan bahan Fh 1.05 -
2. ALAT
3. TENAGA
Produksi pasang kerb pracetak / hari = Tk x Q1 Qt 152.34 M'
Kebutuhan tenaga : - Mandor M 1.00 orang
- Tukang Tb 4.00 orang
- Pekerja P 10.00 orang
Koefisien Tenaga / Buah :
- Mandor = (Tk x M) : Qt (L03) 0.0459 jam
- Tukang = (Tk x Tb) : Qt (L02) 0.1838 jam
- Pekerja = (Tk x P) : Qt (L01) 0.4595 jam
I. ASUMSI
1 Menggunakan cara manual
2 Lokasi pekerjaan : sepanjang jalan
3 Bahan dasar kerb pracetak jenis-1 dibuat di base camp, kemudian
diangkut dengan Truk ke lokasi pekerjaan
4 Jarak rata-rata Base camp ke lokasi pekerjaan L 11.44 KM
5 Jam kerja efektif per-hari Tk 7.00 jam
6 Faktor kehilangan bahan Fh 1.05 -
2. ALAT
3. TENAGA
Produksi pasang kerb pracetak / hari = Tk x Q1 Qt 165.43 M'
Kebutuhan tenaga : - Mandor M 1.00 orang
- Tukang Tb 4.00 orang
- Pekerja P 10.00 orang
Koefisien Tenaga / Buah :
- Mandor = (Tk x M) : Qt (L03) 0.0423 jam
- Tukang = (Tk x Tb) : Qt (L02) 0.1693 jam
- Pekerja = (Tk x P) : Qt (L01) 0.4231 jam
I. ASUMSI
1 Menggunakan cara manual
2 Lokasi pekerjaan : sepanjang jalan frontage
3 Bahan dasar ( blok beton ) telah berada di lokasi
pekerjaan / proyek
4 Jarak rata-rata Base camp ke lokasi pekerjaan L 11.44 KM
5 Jam kerja efektif per-hari Tk 7.00 jam
6 Faktor kehilangan bahan Paving block Fh1 1.03 -
Pasir Fh2 1.05
2. ALAT
2.a. TAMPER (E25)
Kecepatan V 0.60 Km / Jam
Efisiensi alat Fa 0.83 -
Lebar pemadatan Lb 0.40 M
Banyak lintasan n 4 lintasan
Tebal lapis hamparan rata-rata tp 0.05 M
3. TENAGA
Produksi paving block / hari = Tk x Q1 Qt 17.43 M2 terlalu sedikit
Kebutuhan tenaga : - Mandor M 1.00 orang
- Tukang Tb 1.00 orang
- Pekerja P 2.00 orang
Koefisien Tenaga / Buah :
- Mandor = (Tk x M) : Qt (L03) 0.4016 jam
- Tukang = (Tk x Tb) : Qt (L02) 0.4016 jam
- Pekerja = (Tk x P) : Qt (L01) 0.8032 jam
PROYEK
No. PAKET KONTRAK :
NAMA PAKET :
PROP / KAB / KODYA : Preservasi Jalan Serdang - Bojonegara - Merak
ITEM PEMBAYARAN NO. : Banten PERKIRAAN VOL. PEK. : #REF!
JENIS PEKERJAAN : Kerb Pracetak Jenis 2 (Penghalang/Barrier) TOTAL HARGA (Rp.) : #REF!
SATUAN PEMBAYARAN : M' % THD. BIAYA PROYEK : #REF!
A. TENAGA
0.0000
0.24825 1. Pekerja Biasa (L01) jam 0.48 22,857.14 10,964.06
2. Tukang (L02) jam 0.19 24,285.71 4,659.73
3. Mandor (L03) jam 0.05 27,142.86 1,301.98
B. BAHAN
C. PERALATAN
PROYEK :
No. PAKET KONTRAK :
NAMA PAKET : Preservasi Jalan Serdang - Bojonegara - Merak
PROP / KAB / KODYA : Banten
ITEM PEMBAYARAN NO. : 9.2.(10f) PERKIRAAN VOL. PEK. : #REF!
JENIS PEKERJAAN : Kerb Pracetak Jenis 6 (Kerb dengan bukaan) TOTAL HARGA (Rp.) : #REF!
SATUAN PEMBAYARAN : Buah % THD. BIAYA PROYEK : #REF!
A. TENAGA
0.0000
0.24825 1. Pekerja Biasa (L01) jam 0.73 22,857.14 16,732.63
2. Tukang (L02) jam 0.29 24,285.71 7,111.37
3. Mandor (L03) jam 0.07 27,142.86 1,987.00
B. BAHAN
C. PERALATAN
PROYEK :
No. PAKET KONTRAK :
NAMA PAKET : Preservasi Jalan Serdang - Bojonegara - Merak
PROP / KAB / KODYA : Banten
ITEM PEMBAYARAN NO. : 9.2.(10g) PERKIRAAN VOL. PEK. : #REF!
JENIS PEKERJAAN : Kerb Pracetak Jenis 7 (Kerb pd pelandaian trotoaTOTAL HARGA (Rp.) : #REF!
SATUAN PEMBAYARAN : Buah % THD. BIAYA PROYEK : #REF!
A. TENAGA
0.0000
0.24825 1. Pekerja Biasa (L01) jam 0.46 22,857.14 10,502.58
2. Tukang (L02) jam 0.18 24,285.71 4,463.59
3. Mandor (L03) jam 0.05 27,142.86 1,247.18
B. BAHAN
C. PERALATAN
PROYEK :
No. PAKET KONTRAK :
NAMA PAKET : Preservasi Jalan Serdang - Bojonegara - Merak
PROP / KAB / KODYA : Banten
ITEM PEMBAYARAN NO. : 9.2.(10h) PERKIRAAN VOL. PEK. : #REF!
JENIS PEKERJAAN : Kerb Pracetak Jenis 8 (Kerb pd pelandaian trotoaTOTAL HARGA (Rp.) : #REF!
SATUAN PEMBAYARAN : Buah % THD. BIAYA PROYEK : #REF!
A. TENAGA
0.0000
0.24825 1. Pekerja Biasa (L01) jam 0.46 22,857.14 10,502.58
2. Tukang (L02) jam 0.18 24,285.71 4,463.59
3. Mandor (L03) jam 0.05 27,142.86 1,247.18
B. BAHAN
C. PERALATAN
PROYEK :
No. PAKET KONTRAK :
NAMA PAKET : Preservasi Jalan Serdang - Bojonegara - Merak
PROP / KAB / KODYA : Banten
ITEM PEMBAYARAN NO. : 9.2.(10i) PERKIRAAN VOL. PEK. : #REF!
JENIS PEKERJAAN : Kerb Pracetak Jenis 9 (Kerb pd pelandaian trotoaTOTAL HARGA (Rp.) : #REF!
SATUAN PEMBAYARAN : Buah % THD. BIAYA PROYEK :
A. TENAGA
0.0000
0.24825 1. Pekerja Biasa (L01) jam 0.42 22,857.14 9,671.90
2. Tukang (L02) jam 0.17 24,285.71 4,110.56
3. Mandor (L03) jam 0.04 27,142.86 1,148.54
B. BAHAN
C. PERALATAN
PROYEK :
No. PAKET KONTRAK :
NAMA PAKET : Preservasi Jalan Serdang - Bojonegara - Merak
PROP / KAB / KODYA : Banten
ITEM PEMBAYARAN NO. : 9.2.(12a) PERKIRAAN VOL. PEK. : #REF!
JENIS PEKERJAAN : Perkerasan Blok Beton pada Trotoar dan Media TOTAL HARGA (Rp.) : #REF!
SATUAN PEMBAYARAN : M2 % THD. BIAYA PROYEK : #REF!
A. TENAGA
B. BAHAN
C. PERALATAN
1 2 3
RKJ 1.2 1
RKJ 1.8.(1) 2
RKJ 1.17.(1a) 3
RKJ 1.17.(1b) 4
RKJ 1.17.(1c) 5
RKJ 1.17.(1d) 6
RKJ 1.17.(1e) 7
RKJ 1.17.(1f) 8
RKJ 1.17.(1g) 9
RKJ 1.17.(1h) 10
RKJ 1.17.(1i) 11
RKJ 1.17.(1j) 12
RKJ 1.17.(2a) 13
RKJ 1.17.(2b) 14
RKJ 1.17.(3a) 15
RKJ 1.17.(3b) 16
RKJ 1.17.(3c) 17
RKJ 1.17.(3d) 18
RKJ 1.17.(3f) 19
RKJ 1.17.(3g) 20
RKJ 1.17.(3h) 21
RKJ 1.19 22
RKJ 1.21 23
PL 2.1.(1) 24
PL 2.2.(1) 25
PL 2.3.(1) 26
PL 2.3.(15) 27
PL 2.3.(21) 28
PL 2.3.(26) 29
PL 2.3.(27) 30
PL 2.3.(29) 31
PL 3.1.(1) 32
PL 3.1.(7) 33
PL 3.1.(10). 34
PL 3.2.(1a) 35
PL 3.2.(2a) 36
PL 3.3.(1) 37
PL 3.4.(2) 38
PL 3.4.(3) 39
PL 3.4.(4) 40
PL 3.4.(5) 41
PL 4.9.(3) 42
PL 4.9.(5) 43
PL 5.1.(1) 44
PL 5.1.(2) 45
PL 5.1.(3) 46
PL 5.3.(3) 47
PL SKh 1.5.3.( 48
PL 6.1 (1) 49
PL 6.1 (2a) 50
PL 6.3(5a) 51
PL 6.3(6a) 52
PL 6.3.(8) 53
PL 7.1 (5a) 54
PL 7.1 (10) 55
PL 7.3 (1) 56
PL 7.3 (3) 57
PL 7.3 (8) 58
PKPL/RJ/PKRK/PKRJ7.4 (1b) 59
PL 7.9.(1) 60
PL 7.10.(1) 61
PL 7.10.(3a) 62
RJ 7.14.(1) 63
RJ 8.2.(2) 64
RK 8.7.(1b) 65
RK 8.7.(3a) 66
RK 8.11.(1) 67
RK 8.11.(3) 68
RK 9.2.(1) 69
RK 9.2.(3a) 70
RK 9.2.(3b) 71
RK 9.2.(6a) 72
PL 9.2.(7) 73
PL 9.2.(10b) 74
RK 9.2.(10f) 75
PL 9.2.(10g) 76
PL 9.2.(10h) 77
PL 9.2.(10i) 78
PL 9.2.(12a) 79
RK 10.1.(1) 80
RK 10.1.(2) 81
RK 10.1.(3) 82
RK 10.1.(4) 83
RK 10.1.(5) 84
RK 10.1.(6) 85
RK 10.1.(7) 86
PKRJL 10.1.(9) 87
PKRJL 10.1.(14) 88
RK 10.1.(15) 89
PKRJL/RK 10.1.(16) 90
PKRJ 10.1.(17) 91
PKRJ 10.1.(18) 92
PKRJ 10.1.(19) 93
PKRJ 10.1.(20) 94
PKRJ 10.1.(21) 95
PKRJ 10.1.(22) 96
PKRJ 10.2.(1) 97
PKRJ 10.2.(2) 98
PKRJ 10.2.(3) 99
PL
RJ
RK
PKPL
PKD
PKRK
PKRJ
PKRJL
TKDN Gabungan Barang dan Jasa untuk Konstruksi/Fabrikasi
Nama Penyedia Barang/Jasa
Personil
3 7
Mobilisasi 0.00%
Pengujian pH 100.00%
Pengujian Destruksi Cu, Pb, Cd, Ni, Fe, Zn, Ag, Co, Mn 100.00%
Tambalan Penuh dengan Beton Semen Cepat Mengeras untuk Pembukaan Lalu Lintas Umur Beton lebih dari 31.60%
Perkerasan Jalan Beton Semen Untuk Pembukaan Lalu Lintas Umur Beton Lebih dari 3 hari kurang dari 7 ha 1.60%
Penyediaan Baja Struktur Grade 345 (kuat leleh 345 Mpa) 0.00%
Pengecatan struktur baja pada daerah kering tebal 240 mikron 100.00%
Pengecatan pada elemen sandaran dan/atau pagar pengaman (gruard rail) 80 mikron 100.00%
PELEBARAN
RUTIN JEMBATAN
RUTIN KONDISI
PK PELEBARAN
PK DRAINASE
PK RUTIN KONDISI
PK RUTIN JEMBATAN
PK RUTIN JALAN
5 6 7 8 9 10 11
% Rencana Tahun 2022
KDN KLN
Vol Sat
Bahan Alat Total Personil Bahan Alat Total
8 9 10 11 12 13 14 15 16
6.00 Buah
6.00 Buah
SUB TOTAL
Rencana Tahun 2022
KDN
Harsat Jumlah Harga
Personil Bahan
17 18 19 20
160,300,000.00 160,300,000.00 - -
25,000.00 10,060,000.00 - -
3,000,000.00 81,900,000.00 - -
1,200,000.00 3,000,000.00 - -
KDN KLN
144,515,610.56 144,515,610.56 - -
- 103,400,000.00 - -
- 300,000.00 - -
- 300,000.00 - -
- 300,000.00 - -
- 300,000.00 - -
- 300,000.00 - -
- 300,000.00 - -
- 600,000.00 - -
- 300,000.00 - -
- 2,400,000.00 - -
- 300,000.00 - -
- 6,000,000.00 - -
- 300,000.00 - -
- 1,200,000.00 - -
- 900,000.00 - -
- 900,000.00 - -
- 900,000.00 - -
- 3,000,000.00 - -
- 300,000.00 - -
- 300,000.00 - -
2,871,456.38 2,930,225.79 - -
1,338,976.79 38,970,041.96 - -
2,536,404.54 73,820,391.82 - -
15,766,333.81 458,868,812.86 - -
22,415,708.98 652,394,519.73 - -
499,908,332.35 7,493,391,299.54 - -
21,191,604.85 316,213,419.49 - -
123,019,522.05 1,835,652,561.40 - -
160,052,804.75 163,328,567.07 - -
6,784,443.13 7,110,941.43 - -
- 36,849,197.98 - -
5,532,362.65 167,785,360.51 - -
1,413,697.07 42,874,570.64 - -
3,524,660.20 3,589,197.09 - -
384,099.17 410,476.50 - -
2,903,366.22 2,980,459.39 - -
7,262,162.45 7,449,734.58 - -
5,962,611.48 6,173,630.14 - -
47,446,326.28 1,760,372,741.76 - -
318,033.64 17,810,688.41 - -
755,043.38 47,424,352.87 - -
- 26,884,359.60 - 548,660.40
- 45,138,376.18 - 26,502.62
- 9,306,950.00 - 151,800.00
- - - -
15,756,366.37 411,473,713.86 - -
390,620.20 9,952,436.26 - -
- 55,223,000.00 - -
- 1,383,837.52 - -
- 7,050,000.00 - -
- 49,089,600.00 - -
- 9,660,000.00 - -
61,425,000.00 61,425,000.00 - -
2,250,000.00 2,250,000.00 - -
2,298,727.80 38,144,197.20 - -
15,290,479.09 151,228,147.83 - -
6,385,288.01 19,929,452.66 - -
468,450.72 3,803,394.36 - -
468,450.72 3,803,394.36 - -
4,745,398.16 35,007,298.76 - -
37,020,174.35 461,755,706.88 - -
- 13,507,936.06 - -
- 28,839,407.60 - -
- 49,867,796.52 - -
- 1,070,914.50 - -
70,314.82 4,416,481.25 - -
- 28,915,514.62 - -
- 53,227,400.00 - -
- 3,150,000.00 - -
- 129,381,954.00 - -
- 26,903,435.30 - -
- 21,043,765.54 - -
- 10,000,000.00 - -
- 6,000,000.00 - -
- 405,000.00 - -
- 1,110,000.00 - -
- 290,600,000.00 - -
- 450,377,200.00 - -
- 5,000,000.00 - -
- 7,500,000.00 - -
- 40,000,000.00 - -
- 20,000,000.00 - -
- 5,000,000.00 - -
- 5,000,000.00 - -
- 5,500,000.00 - -
- 5,000,000.00 - -
- 5,000,000.00 - -
- 15,000,000.00 - -
- 5,000,000.00 - -
- 5,000,000.00 - -
- 5,000,000.00 - -
2,481,452,291 58,209,313,094
- 8,433,838
265,532,532 1,245,518,183
- -
- 76,990
- -
- 886,492,200
- 140,372,290
Self Assessment
TKDN KLN
KLN TOTAL
(%) (%)
Alat Total
25 26 27 28 29 30
- - - 0.00% 0.00% c
c
c
1,023,601,792.85 1,868,804,365.94 63,256,310,502.04 97.17% 2.96% c
c
81,699,183.30 c
c
c
c
c
c
c
c
Realisasi Jan 2022 sd Agustus 2022
31 32 33 34 35 36 37
KDN
- - - - -
33,125,490.71 - - 33,125,490.71 -
- - - - -
- - - - -
- - - - -
- - - - -
- - - - -
- - - - -
- - - - -
- - - - -
- - - - -
- - - - -
- - - - -
- - - - -
- - - - -
- - - - -
- - - - -
22,899.69 - - 22,899.69 -
- - - - -
16,000,000.00 - - 16,000,000.00 -
14,381.33 - - 14,381.33 -
- - - - -
- - - - -
- - - - -
- - - - -
- - - - -
- - - - -
- - - - -
- - - - -
- - - - -
- 423,256,914.87 - 423,256,914.87 -
- - - - -
- - - - -
60,409.21 240,447.25 - 300,856.47 -
- - - - -
- - - - -
- - - - -
9,720,000.00 - - 9,720,000.00 -
453,248.56 - - 453,248.56 -
- - 364,500,000.00 364,500,000.00 -
- - 145,800,000.00 145,800,000.00 -
- - - - -
- - - - -
- - - - -
- - - - -
- - - - -
- - - - -
- - - - -
- - - - -
- - - - -
- - - - -
3,521,403.48 - - 3,521,403.48 -
- - - - -
- - - - -
- - - - -
- - - - -
- - - - -
56,668,800.00 - - 56,668,800.00 -
52,915,792,623.62 - - 52,915,792,623.62 -
1,199,927,839,867.27 - - 1,199,927,839,867.27 -
5,360.00 - - 5,360.00 -
2,406.25 - - 2,406.25 -
84.22 - - 84.22 -
535,937.50 - - 535,937.50 -
803,906.25 - - 803,906.25 -
4,287,500.00 - - 4,287,500.00 -
2,406,250.00 - - 2,406,250.00 -
535,937.50 - - 535,937.50 -
601,562.50 - - 601,562.50 -
589,531.25 - - 589,531.25 -
535,937.50 - - 535,937.50 -
601,562.50 - - 601,562.50 -
1,607,812.50 - - 1,607,812.50 -
601,562.50 - - 601,562.50 -
601,562.50 - - 601,562.50 -
601,562.50 - - 601,562.50 -
ah)
TKDN
KLN TOTAL
(%)
Bahan Alat Total
43 44 45 46 47
- - - - 0.00%
- - - 33,125,490.71 0.05%
- - - - 0.00%
- - - - 0.00%
- - - - 0.00%
- - - - 0.00%
- - - - 0.00%
- - - - 0.00%
- - - - 0.00%
- - - - 0.00%
- - - - 0.00%
- - - - 0.00%
- - - - 0.00%
- - - - 0.00%
- - - - 0.00%
- - - - 0.00%
- - - - 0.00%
- - - 22,899.69 0.00%
- - - - 0.00%
- - - 16,000,000.00 0.03%
- - - 14,381.33 0.00%
- - - - 0.00%
- - - - 0.00%
- - - - 0.00%
- - - - 0.00%
- - - - 0.00%
- - - - 0.00%
- - - - 0.00%
- - - - 0.00%
- - - - 0.00%
- - - - 0.00%
- - - - 0.00%
4,907.09 - 4,907.09 305,763.55 0.00%
- - - - 0.00%
- - - - 0.00%
- - - - 0.00%
- - - 22,662,428.14 0.04%
- - - 9,720,000.00 0.02%
- - - 453,248.56 0.00%
- - - - 0.00%
- - - - 0.00%
- - - - 0.00%
- - - - 0.00%
- - - - 0.00%
- - - - 0.00%
- - - - 0.00%
- - - - 0.00%
- - - - 0.00%
- - - - 0.00%
- - - 3,521,403.48 0.01%
- - - - 0.00%
- - - - 0.00%
- - - - 0.00%
- - - - 0.00%
- - - - 0.00%
- - - 56,668,800.00 0.09%
- - - 52,915,792,623.62 83.76%
- - - 1,199,927,839,867.27 1899.38%
- - - 5,360.00 0.00%
- - - 2,406.25 0.00%
- - - 84.22 0.00%
- - - 535,937.50 0.00%
- - - 803,906.25 0.00%
- - - 4,287,500.00 0.01%
- - - 2,406,250.00 0.00%
- - - 535,937.50 0.00%
- - - 601,562.50 0.00%
- - - 589,531.25 0.00%
- - - 535,937.50 0.00%
- - - 601,562.50 0.00%
- - - 1,607,812.50 0.00%
- - - 601,562.50 0.00%
- - - 601,562.50 0.00%
- - - 601,562.50 0.00%
#N/A
Sisa Alokasi SD Des 2022
KLN
(%) Vol Sat Harsat Jumlah Harga
Personil
48 49 50 51 52 53 54 55
KDN KLN
- - - - -
- - (33,125,490.71) - -
- - - - -
- - - - -
- - - - -
- - - - -
- - - - -
- - - - -
- - - - -
- - - - -
- - - - -
- - - - -
- - - - -
- - - - -
- - - - -
- - - - -
- - - - -
- - (22,899.69) - -
- - - - -
- - (16,000,000.00) - -
- - (14,381.33) - -
- (53,171,055.53) (54,259,294.76) - -
- - - - -
- - - - -
- - - - -
- (605,992,056.48) (618,394,750.38) - -
- 4,818,889.09 5,050,795.97 - -
(38,105,998.17) - (42,663,006.49) - -
- (418,676.71) (426,342.72) - -
- (13,059,371.82) (13,956,201.09) - -
- (1,096,311,083.77) (1,125,421,464.00) - -
- (35,438,421,262.01) (36,353,749,232.82) - -
- (4,770,089.19) (4,938,904.11) - -
- - - - -
- - - - -
- - - - -
(9,281,534.72) - (11,613,398.35) - (189,419.08)
- - - - -
- - - - -
- - - - -
(13,847,699.70) - (19,782,428.14) - -
- - (9,720,000.00) - -
- - 7,046,751.44 - -
- (358,875,000.00) (358,875,000.00) - -
- (145,800,000.00) (145,800,000.00) - -
- - - - -
- - - - -
- - - - -
- - - - -
- - 1,584,631.57 - -
- - 28,839,407.60 - -
- - 49,867,796.52 - -
- - 1,070,914.50 - -
- - 53,227,400.00 - -
- - 3,150,000.00 - -
- - 72,713,154.00 - -
- - (52,888,889,188.32) - -
- - (1,199,906,796,101.73) - -
- - 9,994,640.00 - -
- - 290,597,593.75 - -
- - 450,377,115.78 - -
- - 4,464,062.50 - -
- - 6,696,093.75 - -
- - 35,712,500.00 - -
- - 17,593,750.00 - -
- - 4,464,062.50 - -
- - 4,398,437.50 - -
- - 4,910,468.75 - -
- - 4,464,062.50 - -
- - 4,398,437.50 - -
- - 13,392,187.50 - -
- - 4,398,437.50 - -
- - 4,398,437.50 - -
- - 4,398,437.50 - -
TKDN KLN
KLN TOTAL
(%) (%)
Alat Total
61 62 63 64 65 66 67
- - - 0.00% 0.00% -
- - - 0.00% 0.00% -
- - - 0.00% 0.00% -
- - - 0.00% 0.00% -
- - - 0.00% 0.00% -
- - - 0.00% 0.00% -
- - - 0.00% 0.00% -
- - - 0.00% 0.00% -
- - - 0.00% 0.00% -
- - - 0.00% 0.00% -
- - - 0.00% 0.00% -
- - - 0.00% 0.00% -
- - - 0.00% 0.00% -
- - - 0.00% 0.00% -
- - - 0.00% 0.00% -
- - - 0.00% 0.00% -
- - - 0.00% 0.00% -
- - - 0.00% 0.00% -
- - - 0.00% 0.00% -
- - - 0.00% 0.00% -
- - - 0.00% 0.00% -
- - - 0.00% 0.00% -
- - - 0.00% 0.00% -
- (189,419.08) (11,802,817.43) -0.02% 0.00% ###
- - - 0.00% 0.00% -
- - - 0.00% 0.00% -
- - - 0.00% 0.00% -
- - - 0.00% 0.00% -
- - - 0.00% 0.00% -
- - - 0.00% 0.00% -
#N/A
kode
68
RKJ
RKJ
RKJ
RKJ
RKJ
RKJ
RKJ
RKJ
RKJ
RKJ
RKJ
RKJ
RKJ
RKJ
RKJ
RKJ
RKJ
RKJ
RKJ
RKJ
RKJ
RKJ
RKJ
PL
PL
PL
PL
PL
PL
PL
PL
PL
PL
PL
PL
PL
PL
PL
PL
PL
PL
PL
PL
PL
PL
PL
PL
PL
PL
PL
PL
PL
PL
PL
PL
PL
PL
PL
PKPL/RJ/PKRK/PKRJ
PL
PL
PL
RJ
RJ
RK
RK
RK
RK
RK
RK
RK
RK
PL
PL
RK
PL
PL
PL
PL
RK
RK
RK
RK
RK
RK
RK
PKRJL
PKRJL
RK
PKRJL/RK
PKRJ
PKRJ
PKRJ
PKRJ
PKRJ
PKRJ
PKRJ
PKRJ
PKRJ
PKRJ
PKRJ
PKRJ
PKRJ
PKRJ
PKRJ
PKRJ
PKRJ
PKRJ
PKRJ
Kementerian Pekerjaan Umum dan Perumahan Rakyat
Direktorat Jenderal Bina Marga PT. PUNDI VIWI PERDANA
Balai Pelaksanaan Jalan Nasional Banten Engineering & Management Consultans
Satuan Kerja Pelaksanaan Jalan Nasional Wilayah I
Provinsi Banten
Progres sd
NO. MATA agust 2022 Sisa Alokasi 2022
PEMBAYAR URAIAN PEKERJAAN Ket.
AN PERKIRAAN HARGA SATUAN BOBOT
SAT. VOLUME (Rp) JUMLAH HARGA (Rp) (%)
Sisa 2021 & 2023 Vol Vol Jumlah Harga
a b c d e f g q
DIVISI 1. UMUM 90%
1.2 Mobilisasi LS 1.00 160,300,000.00 160,300,000.00 0.254 1.000 0.70 0.00 0.00 1,790,179,000
1.8.(1) Manajemen dan Keselamatan Lalu Lintas LS 1.00 103,400,000.00 103,400,000.00 0.164 1.000 0.52 (0.32) (33,125,490.71) 178,554,000
1.17.(1a) Pengujian pH Buah 6.00 50,000.00 300,000.00 0.000 6.000 3.00 0.00 0.00 34,000
1.17.(1b) Pengujian Oksigen Terlarut (DO) Buah 6.00 50,000.00 300,000.00 0.000 6.000 3.00 0.00 0.00 46,000
1.17.(1c) Pengujian Zat Padat Terlarut (TDS) Buah 6.00 50,000.00 300,000.00 0.000 6.000 3.00 0.00 0.00 46,000
1.17.(1d) Pengujian Zat Tersuspensi (TSS) Buah 6.00 50,000.00 300,000.00 0.000 6.000 3.00 0.00 0.00 46,000
1.17.(1e) Pengujian Biological Oxygen Demand (BOD) Buah 6.00 50,000.00 300,000.00 0.000 6.000 3.00 0.00 0.00 46,000
1.17.(1f) Pengujian Chemical Oxygen Demand (COD) Buah 6.00 50,000.00 300,000.00 0.000 6.000 3.00 0.00 0.00 46,000
1.17.(1g) Pengujian Coliform Buah 6.00 100,000.00 600,000.00 0.001 6.000 3.00 0.00 0.00 69,000
1.17.(1h) Pengujian E. Coli Buah 6.00 50,000.00 300,000.00 0.000 6.000 3.00 0.00 0.00 415,000
1.17.(1i) Pengujian Destruksi Cu, Pb, Cd, Ni, Fe, Zn, Ag, Co, Mn Buah 6.00 400,000.00 2,400,000.00 0.004 6.000 3.00 0.00 0.00 46,000
1.17.(1j) Pengujian Temperatur (Suhu) Buah 6.00 50,000.00 300,000.00 0.000 6.000 3.00 0.00 0.00 57,000
1.17.(2a) Pengujian Vibrasi Lin Buah 6.00 1,000,000.00 6,000,000.00 0.009 6.000 3.00 0.00 0.00 69,000
1.17.(2b) Pengujian tingkat getaran kendaraan bermotor Buah 6.00 50,000.00 300,000.00 0.000 6.000 3.00 0.00 0.00 69,000
1.17.(3a) Pengujian NoX Buah 6.00 200,000.00 1,200,000.00 0.002 6.000 3.00 0.00 0.00 69,000
1.17.(3b) Pengujian Sulfurdioksida (SO2) Buah 6.00 150,000.00 900,000.00 0.001 6.000 3.00 0.00 0.00 69,000
1.17.(3c) Pengujian Karbondioksida (CO2) Buah 6.00 150,000.00 900,000.00 0.001 6.000
1.17.(3d) Pengujian Hidro Carbon (HC)-CH4 Buah 6.00 150,000.00 900,000.00 0.001 6.000 0.47 (0.15) (22,899.69) 1,188,612,200
1.17.(3f) Pengujian Total Partikulat (TSP) - Debu Buah 6.00 500,000.00 3,000,000.00 0.005 6.000
1.17.(3g) Pengujian Timah Hitam (Pb) Buah 6.00 50,000.00 300,000.00 0.000 6.000 320.00 (320.00) (16,000,000.00) 1,436,875
1.17.(3h) Pengujian Parameter Udara Emisi dan Ambien lainnya : ………….. Buah 6.00 50,000.00 300,000.00 0.000 6.000 0.49 (0.29) (14,381.33) 293,250,000
1.19 Keselamatan dan Kesehatan Kerja LS 1.00 174,900,000.00 174,900,000.00 0.277 1.000 0.47 (0.15) (26,701,034.61) 1,188,612,200
1.21 Manajemen Mutu LS 1.00 141,400,000.00 141,400,000.00 0.224 1.000