CARGILL
KONTRAKTOR PELAKSANA :
KOTA : MAKASSAR
T.A. : 2023.00
1 PEK. PENDAHULUAN
A. LANGSIRAN ALAT KERJA LS 1.00 750,000.00 750,000.00
B. K3 KONSTRUKSI LS 1.00 15,000,000.00 15,000,000.00
C. PEKERJAAN PEMASANGAN DAN PEMBONGKARAN LS 1.00 9,500,000.00 9,500,000.00
SCAFOLDER
2 PEK. PEMBONGKARAN EXT LAMA
A. PEK. PEMBONGKARAN TOWER LAMA LS 1.00 8,000,000.00 8,000,000.00
B. PEK. PEMBONGKARAN PONDASI M2 6.30 195,000.00 1,228,500.00
3 PEK. STRUKTUR
A. PEK. GALIAN PONDASI M2 7.35 195,000.00 1,433,250.00
B. PEK. URUNGAN PASIR M3 0.70 265,000.00 185,500.00
C. PEK. PASANGAN BATU BELAH ,M3 4.90 750,000.00 3,675,000.00
D. PEK. PONDASI POER
1. PEMBESIAN KG 320.00 16,500.00 5,280,000.00
2. BEKISTING M2 3.50 220,000.00 770,000.00
3. BETON K250 M3 1.85 950,000.00 1,757,500.00
PEK. SLOFE
A. PEMBESIAN KG 96.00 16,500.00 1,584,000.00
B. BEKISTING M2 5.60 220,000.00 1,232,000.00
C. BETON K250 M3 0.62 950,000.00 589,000.00
PEK. BETON BERTULANG SELASAR TOWER
A. PEMBESIAN KG 100.00 16,500.00 1,650,000.00
B. BETON K250 M3 1.60 220,000.00 352,000.00
C. PEK. PENGECATAN SELASAR ( NIPPON PAINT ) M2 16.00 56,000.00 896,000.00
ANGKUR PENGIKAT KAKI TOWER DAN PONDASI SET 4.00 150,000.00 600,000.00
4 PEK. TOWER TANDON
A. PEK. PENGADAAN BESI SIKU 75X75X9 KG 2217.00 16,500.00 36,580,500.00
B. PEK. PENGELASAN BESI KG 4769.00 5,500.00 26,229,500.00
C. PEK. PENGECATAN ANTI KARAT BESI GALVANIS LS 1.00 15,000,000.00 15,000,000.00
D. PEK. PENGADAAN TANDON 1000 LITER BH 2.00 2,500,000.00 5,000,000.00
E. PEMBUATAN TANGGA TOWER KG 352.00 12,500.00 4,400,000.00
F. PEMBUATAN DUDUKAN TANDON ( BESI PLAT 14 MM ) KG 2200.00 12,500.00 27,500,000.00
G. PEMASANGAN PIPA PVC MASPION 1" INCH M' 25.00 120,000.00 3,000,000.00
5 PEK. PEMIPAAN DAN MESIN
A. PEK. PENGADAAN DAN PEMASANGAN MESIN AIR BH 2.00 4,500,000.00 9,000,000.00
B. PEK. PEMASANGAN PIPA PVC MASPOIN/GALVANIS 1" INCH M' 106.00 120,000.00 12,720,000.00
C. PEK. PEMBONGKARAN PAVING BLOK UNTUK M' 106.00 153,000.00 16,218,000.00
PEMASANGAN PIPA
D. PEK. PEMASANGAN KEMBALI PAVING BLOK M' 106.00 93,000.00 9,858,000.00
E. PEK. PEMBONGKARAN DINDING JALUR PIPA M2 10.00 187,000.00 1,870,000.00
F. PEK. PERBAIKAN KEMBALI DINDING M2 10.00 150,000.00 1,500,000.00
G. PEK. PENGADAAN DAN PEMASANGAN KERAN BH 2.00 250,000.00 500,000.00
WESTAFEL
6 PEK. AKHIR
A. PEMBERSIHAN LS 1.00 1,500,000.00 1,500,000.00
B. LANGSIRAN ALAT KERJA LS 1.00 750,000.00 750,000.00
223,858,750.00
JUMLAH 223,858,750.00
PPN 11% 24,624,462.50
HARGA TOTAL 248,483,212.50
DIBULATKAN
PEKERJAAN : TOWER TANDON PT. CARGILL
KONTRAKTOR PELAKSANA :
KOTA : MAKASSAR
T.A. : 2023.00