Kurva S RPDB 5-MGM
Kurva S RPDB 5-MGM
MINGGU KE
1 2 3 4 5 6 7 8 9 10 11 12 13 14
PERIODE HARI KALENDER
Bobot
NO JENIS PEKERJAAN Biaya 21/08/2022 28/08/2022 04/09/2022 11/09/2022 18/09/2022 25/09/2022 02/10/2022 09/10/2022 16/10/2022 23/10/2022 30/10/2022 06/11/2022 13/11/2022 20/11/2022 BOBOT (%)
Pekerjaan (%)
s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d
27/08/2022 03/09/2022 10/09/2022 17/09/2022 24/09/2022 01/10/2022 08/10/2022 15/10/2022 22/10/2022 29/10/2022 05/11/2022 12/11/2022 19/11/2022 25/11/2022
1 2 3 5 6 7
I PEKERJAAN PONDASI DAN BETON 27,658,053.86 7.902 0.99 0.99 0.99 0.99 0.99 0.99 0.99 0.99
II PEKERJAAN PASANGAN DINDING 54,570,901.72 15.592 1.95 1.95 1.95 1.95 1.95 1.95 1.95 1.95
PEKERJAAN ATAP, LISTRIK, LANTAI DAN PENGECATAN
III 43,345,943.86 12.385 1.77 1.77 1.77 1.77 1.77 1.77 1.77
I PEKERJAAN PIPA DAN ACCESORIS 50,102,976.00 14.315 1.79 1.79 1.79 1.79 1.79 1.79 1.79 1.79
II PEKERJAAN SEPTICTANK TYPE 1 (1-5 Jiwa) 119,342,502.72 34.098 4.26 4.26 4.26 4.26 4.26 4.26 4.26 4.26
III PEKERJAAN RESAPAN 45,255,033.75 12.930 1.62 1.62 1.62 1.62 1.62 1.62 1.62 1.62
349,999,411.91
350,000,000.00
RENCANA REALISASI
JUMLAH BOBOT 100.00
RENCANA BOBOT MINGGUAN 0.40 0.99 5.12 10.60 11.00 12.37 12.77 12.37 12.77 11.39 8.04 1.77 0.40 -
KUMULATIF RENCANA BOBOT MINGGUAN 0 0.40 1.38 6.51 17.11 28.11 40.49 53.26 65.63 78.40 89.79 97.83 99.60 100 100
REALISASI BOBOT MINGGUAN - - - 12.71 13.62 - - 14.19 14.25 13.87 - - 10.37 11.41 - 9.58
KUMULATIF REALISASI BOBOT MINGGUAN 0 0 - 12.71 26.33 26.33 26.33 40.52 54.77 68.64 68.64 68.64 79.01 90.42 90.42 100.0
DEVIASI (+/-) % (0.40) 11.33 19.82 9.22 (1.78) 0.03 1.51 3.01 (9.76) (21.15) (18.82) (9.18) (9.58) 0.00
Friska Nur Afianti, S.T., M.Eng. Adi Tia Mustofa, S.T. Nisfi Pratidina, S.T. Saepul Ulum, S.T. Edi Saripin Atep Dayat Hidayat
NIP. 198701262009122003