II Pengukuran Topografi
No. Uraian Satuan Volume Harga Satuan Jumlah Sub Total
A Biaya Personil
1 Geodetic Enggineer 1 org 9 hari Org-hari 9 350,000.00 3,150,000.00
2 Surveyor 1 org 7 hari Org-hari 7 250,000.00 1,750,000.00
3 Assisten Surveyor 1 org 7 hari Org-hari 7 150,000.00 1,050,000.00
4 Juru Hitung/Draftman 1 org 9 hari Org-hari 9 200,000.00 1,800,000.00
5 Tenaga Lokal 4 org 7 hari Org-hari 28 150,000.00 4,200,000.00
6 Konsumsi Personil di lapangan 4 org 7 hari Org-hari 28 75,000.00 2,100,000.00
7 Konsumsi Tenaga Lokal 4 org 7 hari Org-hari 28 25,000.00 700,000.00
Sub Biaya Personil (A) 14,750,000.00
B Biaya Peralatan
1 Sewa Laptop High End (i7) 1 unit 9 hari
Unit-hari 9 250,000.00 2,250,000.00
2 Sewa Total Station 1 unit 7 hari
Unit-hari 7 250,000.00 1,750,000.00
3 Sewa GPS Geodetic 3 unit 5 hari
Unit-hari 15 350,000.00 5,250,000.00
4 Sewa HT 2 unit 7 hari
Unit-hari 14 5,000.00 70,000.00
5 Sewa Kamera 1 unit Unit 1 500,000.00 500,000.00
6 Sewa GPS Navigasi (handheld ) 1 unit 7 hari Unit-hari 7 15,000.00 105,000.00
Sub Biaya Peralatan (B) 9,925,000.00
III Jasa Prosesing pembuatan desain jalan & Perhitungan volume cut/fill
No. Uraian Satuan Volume Harga Satuan Jumlah Sub Total
A Material
1 Jasa prosesing desain jalan & perhitungan 1 LS 1 2,000,000.00 2,000,000.00
volume cut/fill
CATATAN
1. Biaya tersebut adalah komponen dari :
- Pemasangan BM, Patok STA & Pembuatan Deskripsinya
- Pengukuran topografi skala 1:1000
- Laporan Topografi
- Pembuatan desain jalan dan perhitungan volume
- Foto dokumentasi kegiatan
- File dalam bentuk Flash Disk
2. Pelaksanaan 7 hari di lapangan, Total Penyelesaian pekerjaan 9 hari
3. Biaya tersebut belum termasuk pajak (ppn & pph)