FISIK UPAH

PEKERJAAN JUMLAH
NILAI PERSENTASE NILAI PERSENTASE
JALAN SEP. 70 M' 109,144,400.00 50% 109,308,900.00 50% 218,453,300.00
TPT SEP. 31 M' 33,357,500.00 70% 14,042,500.00 30% 47,400,000.00
BRONJONG SEP. 9 M' 77,733,900.00 50% 77,842,800.00 50% 155,576,700.00
TOTAL 220,235,800.00 201,194,200.00 421,430,000.00
REKAPITULASI RENCANA ANGGARAN BIAYA
PEKERJAAN KEGIATAN FISIK DANA DESA TA.2021
DESA : SISOBALAURU
KECAMATAN : HILIDUHO
KABUPATEN / KOTA : NIAS
PROVINSI : SUMATERA UTARA
NO. RAB :
BIDANG : PEMBANGUNAN DESA
KEGIATAN : PEKERJAAN PENGASPALAN JALAN RUAS JALAN UMUM, Sep. 87 M' x 3 M'
PEKERJAAN GALIAN PEMBENTUKAN BADAN JALAN, Sep. 95 M' x 4 M'
PEKERJAAN GALIAN PARIT TANAH, Sep. 248 M'

URAIAN HARGA SATUAN JLH. HARGA


NO SAT. VOLUME
PEKERJAAN
Rp. Rp.
1 2 4 5 6 7
I PEKERJAAN PENGASPALAN JALAN RUAS JALAN UMUM, Sep. 87 M' x 3 M'
PEKERJAAN GALIAN PEMBENTUKAN BADAN JALAN, Sep. 95 M' x 4 M'
PEKERJAAN GALIAN PARIT TANAH, Sep. 248 M'
A. Upah
- Pekerja HOK 709.00 100,000.00 70,900,000.00
- Tukang Siram Aspal HOK 4.00 225,000.00 900,000.00
Sub. Total Upah 71,800,000.00
B. Bahan
- Batu Gunung Belah 10/15 M3 42.00 187,500.00 7,875,000.00
- Batu Pecah 5/7 (Manual) M3 35.00 187,500.00 6,562,500.00
- Batu Pecah 3/5 (Manual) M3 21.00 225,000.00 4,725,000.00
- Kepala Pasir M3 1.00 181,300.00 181,300.00
- Minyak Bakar Ltr 103.00 11,200.00 1,153,600.00
- Aspal KG 1,284.00 13,600.00 17,462,400.00
- Kayu Api/Kayu Bakar M3 3.50 120,000.00 420,000.00
Sub. Total Bahan 38,379,800.00
C. Peralatan
- Mobilisasi Kali 1.00 7,752,000.00 7,752,000.00
- Mesin gilas roda besi 6 - 8 T Jam 11.00 355,300.00 3,908,300.00
- Meteran uk. 50.0 m Bh 2.00 63,600.00 127,200.00
- Gerobak sorong Unit 10.00 605,500.00 6,055,000.00
- Sekop besar + gagang Bh 17.00 113,800.00 1,934,600.00
- Cangkul + gagang Bh 17.00 113,800.00 1,934,600.00
- Plengki Rotan Bh 26.00 20,700.00 538,200.00
- Gayung Aspal (kaleng) Bh 4.00 16,750.00 67,000.00
- Kaleng Siram Aspal Bh 4.00 33,500.00 134,000.00
- Sarung Tangan Pekerja (karet) Psg 26.00 14,800.00 384,800.00
- Tembilang/penggali + gagang Bh 14.00 66,900.00 936,600.00
- Pecok/Bolak baling + gagang Bh 15.00 139,400.00 2,091,000.00
- Martil Batu Uk. 3 Kg (godam) Bh 9.00 222,200.00 1,999,800.00
- Demobilisasi Kali 1.00 7,752,000.00 7,752,000.00
Sub. Total Peralatan 35,615,100.00
D. Upah Angkut / Pikul Tenaga Manusia
- Batu Gunung Belah 10/15 HOK 42.00 56,250.00 2,362,500.00
- Batu Pecah 5/7 (Manual) HOK 35.00 56,250.00 1,968,750.00
- Batu Pecah 3/5 (Manual) HOK 21.00 56,250.00 1,181,250.00
- Batu Pecah 2/3 (Manual) HOK 10.00 56,250.00 562,500.00
- Batu Pecah 1/2 (Manual) HOK 5.00 56,250.00 281,250.00
- Kepala Pasir HOK 1.00 56,250.00 56,250.00
- Tanah Timbunan Biasa HOK 32.00 187,500.00 6,000,000.00
Sub. Total Upah Angkut / Pikul Tenaga Manusia 12,412,500.00
URAIAN HARGA SATUAN JLH. HARGA
NO SAT. VOLUME
PEKERJAAN
Rp. Rp.
1 2 4 5 6 7
E. Ongkos Angkut Truk
- Batu Gunung Belah 10/15 M3 42.00 326,400.00 13,708,800.00
- Batu Pecah 5/7 (Manual) M3 35.00 357,000.00 12,495,000.00
- Batu Pecah 3/5 (Manual) M3 21.00 357,000.00 7,497,000.00
- Kepala Pasir M3 1.00 249,900.00 249,900.00
- Aspal KG 1,284.00 600.00 770,400.00
- Kayu Api/Kayu Bakar M3 3.50 122,400.00 428,400.00
Sub. Total Upah Angkut Truk 35,149,500.00
F. Upah Mengumpulkan Tenaga Manusia
- Tanah Timbunan Biasa HOK 32.00 72,600.00 2,323,200.00
Sub. Total Upah Mengumpulkan Tenaga Manusia 2,323,200.00
G. Upah Memecah Tenaga Manusia
- Batu Gunung Belah 10/15 HOK 42.00 150,000.00 6,300,000.00
- Batu Pecah 5/7 (Manual) HOK 35.00 150,000.00 5,250,000.00
- Batu Pecah 3/5 (Manual) HOK 21.00 180,000.00 3,780,000.00
- Batu Pecah 2/3 (Manual) HOK 10.00 270,000.00 2,700,000.00
- Batu Pecah 1/2 (Manual) HOK 5.00 484,000.00 2,420,000.00
Sub. Total Upah Memecah Tenaga Manusia 20,450,000.00
H. Upah Menggali Tenaga Manusia
- Tanah Timbunan Biasa HOK 32.00 72,600.00 2,323,200.00
Sub. Total Upah Menggali Tenaga Manusia 2,323,200.00

JUMLAH TOTAL ( A + B + C + D + E + F + G + H ) Rp. 218,453,300.00

Terbilang : Dua Ratus Delapan Belas Juta Empat Ratus Lima Puluh Tiga Ribu Tiga Ratus Rupiah

SISOBALAURU, 2021

DISETUJUI OLEH : DIVERIFIKASI OLEH : DIBUAT OLEH :


Pj. KEPALA DESA SEKRETARIS DESA TIM PELAKSANA KEGIATAN

WA'OZISOKHI WARUWU, S.Pd.SD SIASA NDRAHA OTONI NDRAHA


Ketua
RINCIAN RENCANA ANGGARAN BIAYA
PEKERJAAN KEGIATAN FISIK DANA DESA TA.2021
DESA : SISOBALAURU
KECAMATAN : HILIDUHO
KABUPATEN / KOTA : NIAS
PROVINSI : SUMATERA UTARA
NO. RAB :
BIDANG : PEMBANGUNAN DESA
KEGIATAN : PEKERJAAN PENGASPALAN JALAN RUAS JALAN UMUM, Sep. 87 M' x 3 M'
PEKERJAAN GALIAN PEMBENTUKAN BADAN JALAN, Sep. 95 M' x 4 M'
PEKERJAAN GALIAN PARIT TANAH, Sep. 248 M'

KODE
URAIAN HARGA SATUAN JLH. HARGA
NO ANALISA SAT. VOLUME
PEKERJAAN
PEKERJAAN Rp. Rp.
1 2 3 4 5 6 7
I PEKERJAAN PENGASPALAN JALAN RUAS JALAN UMUM, Sep. 87 M' x 3 M'
PEKERJAAN GALIAN PEMBENTUKAN BADAN JALAN, Sep. 95 M' x 4 M'
PEKERJAAN GALIAN PARIT TANAH, Sep. 248 M'
1 Pek. Pembersihan Semak pada Damija K-210
A. Upah
- Pekerja HOK 14.00 100,000.00 1,400,000.00

B. Bahan - - - -

C. Peralatan - - - -

D. Upah Angkut / Pikul Tenaga Manusia - - - -

E. Ongkos Angkut Truk - - - -

Sub. Total.1 1,400,000.00


2 Pek. Leveling / Pasangan LPB dari telford K-516
A. Upah
- Pekerja HOK 67.00 100,000.00 6,700,000.00

B. Bahan
- Batu Gunung Belah 10/15 M3 42.00 187,500.00 7,875,000.00
- Batu Pecah 5/7 (Manual) M3 17.00 187,500.00 3,187,500.00

C. Peralatan
- Mobilisasi Kali 1.00 7,752,000.00 7,752,000.00
- Mesin gilas roda besi 6 - 8 T Jam 5.00 355,300.00 1,776,500.00
- Meteran uk. 50.0 m Bh 2.00 63,600.00 127,200.00
- Gerobak sorong Unit 10.00 605,500.00 6,055,000.00
- Sekop besar + gagang Bh 17.00 113,800.00 1,934,600.00
- Cangkul + gagang Bh 17.00 113,800.00 1,934,600.00
- Plengki Rotan Bh 26.00 20,700.00 538,200.00
- Gayung Aspal (kaleng) Bh 4.00 16,750.00 67,000.00
- Kaleng Siram Aspal Bh 4.00 33,500.00 134,000.00
- Sarung Tangan Pekerja (karet) Psg 26.00 14,800.00 384,800.00
- Tembilang/penggali + gagang Bh 14.00 66,900.00 936,600.00
- Pecok/Bolak baling + gagang Bh 15.00 139,400.00 2,091,000.00
- Martil Batu Uk. 3 Kg (godam) Bh 9.00 222,200.00 1,999,800.00

D. Upah Angkut / Pikul Tenaga Manusia


- Batu Gunung Belah 10/15 HOK 42.00 56,250.00 2,362,500.00
- Batu Pecah 5/7 (Manual) HOK 17.00 56,250.00 956,250.00

E. Ongkos Angkut Truk


- Batu Gunung Belah 10/15 M3 42.00 326,400.00 13,708,800.00
- Batu Pecah 5/7 (Manual) M3 17.00 357,000.00 6,069,000.00

F. Upah Memecah Tenaga Manusia


KODE
URAIAN HARGA SATUAN JLH. HARGA
NO ANALISA SAT. VOLUME
PEKERJAAN
PEKERJAAN Rp. Rp.
1 2 3 4 5 6 7
- Batu Gunung Belah 10/15 HOK 42.00 150,000.00 6,300,000.00
- Batu Pecah 5/7 (Manual) HOK 17.00 150,000.00 2,550,000.00

Sub. Total.2 75,440,350.00


KODE
URAIAN HARGA SATUAN JLH. HARGA
NO ANALISA SAT. VOLUME
PEKERJAAN
PEKERJAAN Rp. Rp.
1 2 3 4 5 6 7
3 Pek. Pasangan LPA kelas B tebal 10 cm K-523
A. Upah
- Pekerja HOK 27.00 100,000.00 2,700,000.00

B. Bahan
- Batu Pecah 5/7 (Manual) M3 18.00 187,500.00 3,375,000.00
- Batu Pecah 3/5 (Manual) M3 10.00 225,000.00 2,250,000.00

C. Peralatan
- Mesin gilas roda besi 6 - 8 T Jam 3.00 355,300.00 1,065,900.00

D. Upah Angkut / Pikul Tenaga Manusia


- Batu Pecah 5/7 (Manual) HOK 18.00 56,250.00 1,012,500.00
- Batu Pecah 3/5 (Manual) HOK 10.00 56,250.00 562,500.00
- Batu Pecah 2/3 (Manual) HOK 4.00 56,250.00 225,000.00
- Batu Pecah 1/2 (Manual) HOK 2.00 56,250.00 112,500.00

E. Ongkos Angkut Truk


- Batu Pecah 5/7 (Manual) M3 18.00 357,000.00 6,426,000.00
- Batu Pecah 3/5 (Manual) M3 10.00 357,000.00 3,570,000.00

F. Upah Memecah Tenaga Manusia


- Batu Pecah 5/7 (Manual) HOK 18.00 150,000.00 2,700,000.00
- Batu Pecah 3/5 (Manual) HOK 10.00 180,000.00 1,800,000.00
- Batu Pecah 2/3 (Manual) HOK 4.00 270,000.00 1,080,000.00
- Batu Pecah 1/2 (Manual) HOK 2.00 484,000.00 968,000.00

Sub. Total.3 27,847,400.00


4 Pek. Lapis aspal resap perekat ( Primecoat ) K-880
A. Upah
- Pekerja HOK 2.00 100,000.00 200,000.00
- Tukang Siram Aspal HOK 2.00 225,000.00 450,000.00

B. Bahan
- Minyak Bakar Ltr 103.00 11,200.00 1,153,600.00
- Aspal KG 135.00 13,600.00 1,836,000.00
- Kayu Api/Kayu Bakar M3 1.50 120,000.00 180,000.00

C. Peralatan - - - -

D. Upah Angkut / Pikul Tenaga Manusia - - - -

E. Ongkos Angkut Truk


- Aspal KG 135.00 600.00 81,000.00
- Kayu Api/Kayu Bakar M3 1.50 122,400.00 183,600.00

Sub. Total.4 4,084,200.00


KODE
URAIAN HARGA SATUAN JLH. HARGA
NO ANALISA SAT. VOLUME
PEKERJAAN
PEKERJAAN Rp. Rp.
1 2 3 4 5 6 7
5 Pek. Lapis penetrasi macadam ( Lapen ) K-618
A. Upah
- Pekerja HOK 33.00 100,000.00 3,300,000.00
- Tukang Siram Aspal HOK 2.00 225,000.00 450,000.00

B. Bahan
- Batu Pecah 3/5 (Manual) M3 11.00 225,000.00 2,475,000.00
- Kepala Pasir M3 1.00 181,300.00 181,300.00
- Aspal KG 1,149.00 13,600.00 15,626,400.00
- Kayu Api/Kayu Bakar M3 2.00 120,000.00 240,000.00

C. Peralatan
- Mesin gilas roda besi 6 - 8 T Jam 3.00 355,300.00 1,065,900.00
- Demobilisasi Kali 1.00 7,752,000.00 7,752,000.00

D. Upah Angkut / Pikul Tenaga Manusia


- Batu Pecah 3/5 (Manual) HOK 11.00 56,250.00 618,750.00
- Batu Pecah 2/3 (Manual) HOK 6.00 56,250.00 337,500.00
- Batu Pecah 1/2 (Manual) HOK 3.00 56,250.00 168,750.00
- Kepala Pasir HOK 1.00 56,250.00 56,250.00

E. Ongkos Angkut Truk


- Batu Pecah 3/5 (Manual) M3 11.00 357,000.00 3,927,000.00
- Kepala Pasir M3 1.00 249,900.00 249,900.00
- Aspal KG 1,149.00 600.00 689,400.00
- Kayu Api/Kayu Bakar M3 2.00 122,400.00 244,800.00

F. Upah Memecah Tenaga Manusia


- Batu Pecah 3/5 (Manual) HOK 11.00 180,000.00 1,980,000.00
- Batu Pecah 2/3 (Manual) HOK 6.00 270,000.00 1,620,000.00
- Batu Pecah 1/2 (Manual) HOK 3.00 484,000.00 1,452,000.00

Sub. Total.5 42,434,950.00


6 Pek. Bahu jalan ( Tanah Timbunan Biasa ) K-410
A. Upah
- Pekerja HOK 27.00 100,000.00 2,700,000.00

B. Bahan - - - -

C. Peralatan - - - -

D. Upah Angkut / Pikul Tenaga Manusia


- Tanah Timbunan Biasa HOK 32.00 187,500.00 6,000,000.00

E. Ongkos Angkut Truk - - - -

F. Upah Mengumpulkan Tenaga Manusia


- Tanah Timbunan Biasa HOK 32.00 72,600.00 2,323,200.00

G. Upah Menggali Tenaga Manusia


- Tanah Timbunan Biasa HOK 32.00 72,600.00 2,323,200.00

Sub. Total.6 13,346,400.00


KODE
URAIAN HARGA SATUAN JLH. HARGA
NO ANALISA SAT. VOLUME
PEKERJAAN
PEKERJAAN Rp. Rp.
1 2 3 4 5 6 7
7 Pek. Galian Parit Tanah K-110
A. Upah
- Pekerja HOK 90.00 100,000.00 9,000,000.00

B. Bahan - - - -

C. Peralatan - - - -

D. Upah Angkut / Pikul Tenaga Manusia - - - -

E. Ongkos Angkut Truk - - - -

Sub. Total.7 9,000,000.00


8 Pek. Galian Pembentukan Badan Jalan K-320
A. Upah
- Pekerja HOK 449.00 100,000.00 44,900,000.00

B. Bahan - - - -

C. Peralatan - - - -

D. Upah Angkut / Pikul Tenaga Manusia - - - -

E. Ongkos Angkut Truk - - - -

Sub. Total.8 44,900,000.00

JUMLAH TOTAL ( 1 + 2 + 3 + 4 + 5 + 6 + 7 + 8 ) Rp. 218,453,300.00

Terbilang : Dua Ratus Delapan Belas Juta Empat Ratus Lima Puluh Tiga Ribu Tiga Ratus Rupiah

SISOBALAURU, 2021

DISETUJUI OLEH : DIVERIFIKASI OLEH : DIBUAT OLEH :


Pj. KEPALA DESA SEKRETARIS DESA TIM PELAKSANA KEGIATAN

WA'OZISOKHI WARUWU, S.Pd.SD SIASA NDRAHA OTONI NDRAHA


Ketua
RINCIAN ANALISA SATUAN PEKERJAAN
PEKERJAAN KEGIATAN FISIK DANA DESA TA.2021
(Ref. ANALISA K BINAMARGA Thn.1995)
DESA : SISOBALAURU
KECAMATAN : HILIDUHO
KABUPATEN / KOTA : NIAS
PROVINSI : SUMATERA UTARA
NO. RAB :
BIDANG : PEMBANGUNAN DESA
KEGIATAN : PEKERJAAN PENGASPALAN JALAN RUAS JALAN UMUM, Sep. 87 M' x 3 M'
PEKERJAAN GALIAN PEMBENTUKAN BADAN JALAN, Sep. 95 M' x 4 M'
PEKERJAAN GALIAN PARIT TANAH, Sep. 248 M' VOLUME

URAIAN KODE URAIAN KEBUTUHAN TERHADAP ANALISA SATUAN PEKERJAAN


NO PEKER ANALISA SAT.
JAAN PEKERJAAN ANALISA SATUAN PEKERJAAN SATUAN KOEFISIEN VOLUME
1 2 3 4 5 6 7 8 9 = (5 * 8)
TOS
1 Pek. Pembersihan Semak pada Damija K-210 m2 348.00 Pengupasan Tanah dan Pembersihan Semak pada Damija
Tenaga Kerja Pekerja OH 0.040 13.920
Bahan
Peralatan
2 Pek. Leveling / Pasangan LPB dari telford K-516 m3 66.12 Konstruksi Lapis Pondasi Bawah (LPB) - Telford (t = 20 cm)
Tenaga Kerja Pekerja OH 1.000 66.120
Batu Gunung Belah 10/15 M3 0.625 41.325
Bahan
Batu Pecah 5/7 (Manual) M3 0.250 16.530
Peralatan Mesin gilas roda besi 6 - 8 T JAM 0.063 4.166
3 Pek. Pasangan LPA kelas B tebal 10 cm K-523 m3 26.10 Konstruksi Lapis Pondasi Atas (LPA) Kelas - B (t = 10 cm)
Tenaga Kerja Pekerja OH 1.000 26.100
Batu Pecah 5/7 (Manual) M3 0.688 17.957
Batu Pecah 3/5 (Manual) M3 0.375 9.788
Bahan
Batu Pecah 2/3 (Manual) M3 0.125 3.263
Batu Pecah 1/2 (Manual) M3 0.063 1.644
Peralatan Mesin gilas roda besi 6 - 8 T JAM 0.083 2.166
4 Pek. Lapis aspal resap perekat ( Primecoat ) K-880 Ltr 208.80 Lapisan Aspal Resap Pelekat (Prime Coat)
Pekerja OH 0.005 1.044
Tenaga Kerja
Tukang Siram Aspal OH 0.005 1.044
Minyak Bakar Ltr 0.489 102.103
Bahan
Aspal KG 0.642 134.050
Peralatan
VOLUME
URAIAN KODE URAIAN KEBUTUHAN TERHADAP ANALISA SATUAN PEKERJAAN
NO PEKER ANALISA SAT.
JAAN PEKERJAAN ANALISA SATUAN PEKERJAAN SATUAN KOEFISIEN VOLUME
1 2 3 4 5 6 7 8 9 = (5 * 8)
TOS
5 Pek. Lapis penetrasi macadam ( Lapen ) K-618 m2 261.00 Lapisan Penetrasi Macadam (Lapen) (t = 5 cm)
Pekerja OH 0.124 32.364
Tenaga Kerja
Tukang Siram Aspal OH 0.004 1.044
Batu Pecah 3/5 (Manual) M3 0.040 10.440
Batu Pecah 2/3 (Manual) M3 0.022 5.742
Bahan Batu Pecah 1/2 (Manual) M3 0.011 2.871
Kepala Pasir M3 0.0025 0.653
Aspal KG 4.400 1,148.400
Peralatan Mesin gilas roda besi 6 - 8 T JAM 0.011 2.871
6 Pek. Bahu jalan ( Tanah Timbunan Biasa ) K-410 m3 26.10 Membentuk Bahu Jalan (Tanah Timbunan Biasa)
Tenaga Kerja Pekerja OH 1.000 26.100
Bahan Tanah Timbunan Biasa M3 1.200 31.320
Peralatan
7 Pek. Galian Parit Tanah K-110 m3 133.92 Membuat Parit Galian Tanah
Tenaga Kerja Pekerja OH 0.667 89.325
Bahan
Peralatan
8 Pek. Galian Pembentukan Badan Jalan K-320 m3 399.00 Membentuk Badan Jalan / Subgrade di Daerah Galian
Tenaga Kerja Pekerja OH 1.125 448.875
Bahan
Peralatan

SISOBALAURU, 2021

DISETUJUI OLEH : DIVERIFIKASI OLEH : DIBUAT OLEH :


Pj. KEPALA DESA SEKRETARIS DESA TIM PELAKSANA KEGIATAN

WA'OZISOKHI WARUWU, S.Pd.SD SIASA NDRAHA OTONI NDRAHA


Ketua
AAN
DIBULATKAN
10

14.000

67.000
42.000
17.000
5.000

27.000
18.000
10.000
4.000
2.000
3.000

2.000
2.000
103.000
135.000
AAN
DIBULATKAN
10

33.000
2.000
11.000
6.000
3.000
1.000
1,149.000
3.000

27.000
32.000

90.000

449.000
TAKE OF SHEET (TOS)
PERHITUNGAN VOLUME
K-210. Pengupasan Tanah dan Pembersihan Semak pada Damija
PEKERJAAN PENGASPALAN JALAN RUAS JALAN UMUM, Sep. 87 M' x 3 M'

DESA : SISOBALAURU
KECAMATAN : HILIDUHO
KABUPATEN / KOTA : NIAS
PROVINSI : SUMATERA UTARA
NO. RAB :
BIDANG : PEMBANGUNAN DESA
KEGIATAN : PEKERJAAN PENGASPALAN JALAN RUAS JALAN UMUM, Sep. 87 M' x 3 M'

Sketsa

Pas. Leveling Lapis Pondasi Bawah (LPB)


Telford, t = 20 cm
Lapisan Penetrasi Macadam (Lapen)
t = 5 cm
Lapisan Aspal Resap Pelekat (Primecoat)
Timbunan Bahu Jalan Pas. Lapis Pondasi Atas (LPA)
(tanah biasa) t = 10 cm
t = 30 cm
2 %
? 2 %
Pas. Lapis Pondasi Bawah (LPB)
Telford, t = 20 cm
4 % 4 %

0,30 0,30

0,40 0,40
0,50 3,00 0,50
POT. TIPIKAL MELINTANG PENGASPALAN JALAN
P0+000 - P0+087

LEBAR LEBAR RATA - PANJANG


RATA KUANTITAS
NO. STATION / LETAK SISI (m
(m) ) (m)
( M2 )

L L P
1 2 3 4 5 6 7=(5x6)

1 STA. 0 + 000 Tengah 4.00


4.00 87.00 348.00
2 STA. 0 + 087 Tengah 4.00

Jumlah halaman ini 87.00 348.00


Jumlah s/d halaman ini 87.00 348.00

SISOBALAURU, 2021

DISETUJUI OLEH : DIVERIFIKASI OLEH : DIBUAT OLEH :


Pj. KEPALA DESA SEKRETARIS DESA TIM PELAKSANA KEGIATAN
TAKE OF SHEET (TOS)
PERHITUNGAN VOLUME
K-210. Pengupasan Tanah dan Pembersihan Semak pada Damija
PEKERJAAN PENGASPALAN JALAN RUAS JALAN UMUM, Sep. 87 M' x 3 M'

DESA : SISOBALAURU
KECAMATAN : HILIDUHO
KABUPATEN / KOTA : NIAS
PROVINSI : SUMATERA UTARA
NO. RAB :
BIDANG : PEMBANGUNAN DESA
KEGIATAN : PEKERJAAN PENGASPALAN JALAN RUAS JALAN UMUM, Sep. 87 M' x 3 M'

WA'OZISOKHI WARUWU, S.Pd.SD SIASA NDRAHA OTONI NDRAHA


Ketua
TAKE OF SHEET (TOS)
PERHITUNGAN VOLUME
K-516. Konstruksi Lapis Pondasi Bawah (LPB) - Telford (t = 20 cm)
PEKERJAAN PENGASPALAN JALAN RUAS JALAN UMUM, Sep. 87 M' x 3 M'

DESA : SISOBALAURU
KECAMATAN : HILIDUHO
KABUPATEN / KOTA : NIAS
PROVINSI : SUMATERA UTARA
NO. RAB :
BIDANG : PEMBANGUNAN DESA
KEGIATAN : PEKERJAAN PENGASPALAN JALAN RUAS JALAN UMUM, Sep. 87 M' x 3 M'

Sketsa

Pas. Leveling Lapis Pondasi Bawah (LPB)


Telford, t = 20 cm
Lapisan Penetrasi Macadam (Lapen)
t = 5 cm
Lapisan Aspal Resap Pelekat (Primecoat)
Timbunan Bahu Jalan Pas. Lapis Pondasi Atas (LPA)
(tanah biasa) t = 10 cm
t = 30 cm
2 %
? 2 %
Pas. Lapis Pondasi Bawah (LPB)
Telford, t = 20 cm
4 % 4 %

0,30 0,30

0,40 0,40
0,50 3,00 0,50
POT. TIPIKAL MELINTANG PENGASPALAN JALAN
P0+000 - P0+087

LEBAR LEBAR TEBAL


TEBAL PANJANG
RATA - RATA -
RATA RATA KUANTITAS
NO. STATION / LETAK SISI
(m) (m) ( M3 )
(m) (m)
(m)
L L T T P
1 2 3 4 5 6 7 8 9=(5x7x8)

1 STA. 0 + 000 Tengah 3.00 0.20


3.00 0.20 87.00 52.20
2 STA. 0 + 087 Tengah 3.00 0.20

Jumlah halaman ini 87.00 52.20


Jumlah s/d halaman ini 87.00 52.20

SISOBALAURU, 2021

DISETUJUI OLEH : DIVERIFIKASI OLEH : DIBUAT OLEH :


Pj. KEPALA DESA SEKRETARIS DESA TIM PELAKSANA KEGIATAN
TAKE OF SHEET (TOS)
PERHITUNGAN VOLUME
K-516. Konstruksi Lapis Pondasi Bawah (LPB) - Telford (t = 20 cm)
PEKERJAAN PENGASPALAN JALAN RUAS JALAN UMUM, Sep. 87 M' x 3 M'

DESA : SISOBALAURU
KECAMATAN : HILIDUHO
KABUPATEN / KOTA : NIAS
PROVINSI : SUMATERA UTARA
NO. RAB :
BIDANG : PEMBANGUNAN DESA
KEGIATAN : PEKERJAAN PENGASPALAN JALAN RUAS JALAN UMUM, Sep. 87 M' x 3 M'

WA'OZISOKHI WARUWU, S.Pd.SD SIASA NDRAHA OTONI NDRAHA


Ketua
Sketsa

Pas. Leveling Lapis Pondasi Bawah (LPB)


Telford, t = 20 cm
Lapisan Penetrasi Macadam (Lapen)
t = 5 cm
Lapisan Aspal Resap Pelekat (Primecoat)
Timbunan Bahu Jalan Pas. Lapis Pondasi Atas (LPA)
(tanah biasa) t = 10 cm
t = 30 cm
2 %
? 2 %
Pas. Lapis Pondasi Bawah (LPB)
Telford, t = 20 cm
4 % 4 %

0,30 0,30

0,40 0,40
0,50 3,00 0,50
POT. TIPIKAL MELINTANG PENGASPALAN JALAN
P0+000 - P0+087

LEBAR LEBAR TEBAL


TEBAL PANJANG
RATA - RATA -
RATA RATA KUANTITAS
NO. STATION / LETAK SISI
(m) (m) ( M3 )
(m) (m)
(m)
L L T T P
1 2 3 4 5 6 7 8 9=(5x7x8)

1 STA. 0 + 000 Kiri 0.40 0.20


0.40 0.20 87.00 6.96
2 STA. 0 + 087 Kiri 0.40 0.20

1 STA. 0 + 000 Kanan 0.40 0.20


0.40 0.20 87.00 6.96
2 STA. 0 + 087 Kanan 0.40 0.20

Jumlah halaman ini 87.00 13.92


Jumlah s/d halaman ini 174.00 13.92

SISOBALAURU, 2021

DISETUJUI OLEH : DIVERIFIKASI OLEH : DIBUAT OLEH :


TAKE OF SHEET (TOS)
PERHITUNGAN VOLUME
K-516. Konstruksi Lapis Pondasi Bawah (LPB) - Telford (t = 20 cm)
PEKERJAAN PENGASPALAN JALAN RUAS JALAN UMUM, Sep. 87 M' x 3 M'

DESA : SISOBALAURU
KECAMATAN : HILIDUHO
KABUPATEN / KOTA : NIAS
PROVINSI : SUMATERA UTARA
NO. RAB :
BIDANG : PEMBANGUNAN DESA
KEGIATAN : PEKERJAAN PENGASPALAN JALAN RUAS JALAN UMUM, Sep. 87 M' x 3 M'

Pj. KEPALA DESA SEKRETARIS DESA TIM PELAKSANA KEGIATAN

WA'OZISOKHI WARUWU, S.Pd.SD SIASA NDRAHA OTONI NDRAHA


Ketua
TAKE OF SHEET (TOS)
PERHITUNGAN VOLUME
K-523. Konstruksi Lapis Pondasi Atas (LPA) Kelas - B (t = 10 cm)
PEKERJAAN PENGASPALAN JALAN RUAS JALAN UMUM, Sep. 87 M' x 3 M'

DESA : SISOBALAURU
KECAMATAN : HILIDUHO
KABUPATEN / KOTA : NIAS
PROVINSI : SUMATERA UTARA
NO. RAB :
BIDANG : PEMBANGUNAN DESA
KEGIATAN : PEKERJAAN PENGASPALAN JALAN RUAS JALAN UMUM, Sep. 87 M' x 3 M'

Sketsa

Pas. Leveling Lapis Pondasi Bawah (LPB)


Telford, t = 20 cm
Lapisan Penetrasi Macadam (Lapen)
t = 5 cm
Lapisan Aspal Resap Pelekat (Primecoat)
Timbunan Bahu Jalan Pas. Lapis Pondasi Atas (LPA)
(tanah biasa) t = 10 cm
t = 30 cm
2 %
? 2 %
Pas. Lapis Pondasi Bawah (LPB)
Telford, t = 20 cm
4 % 4 %

0,30 0,30

0,40 0,40
0,50 3,00 0,50
POT. TIPIKAL MELINTANG PENGASPALAN JALAN
P0+000 - P0+087

LEBAR LEBAR TEBAL


TEBAL PANJANG
RATA - RATA -
RATA RATA KUANTITAS
NO. STATION / LETAK SISI
(m) (m) ( M3 )
(m) (m)
(m)
L L T T P
1 2 3 4 5 6 7 8 9=(5x7x8)

1 STA. 0 + 000 Tengah 3.00 0.10


3.00 0.10 87.00 26.10
2 STA. 0 + 087 Tengah 3.00 0.10

Jumlah halaman ini 87.00 26.10


Jumlah s/d halaman ini 87.00 26.10

SISOBALAURU, 2021

DISETUJUI OLEH : DIVERIFIKASI OLEH : DIBUAT OLEH :


Pj. KEPALA DESA SEKRETARIS DESA TIM PELAKSANA KEGIATAN
TAKE OF SHEET (TOS)
PERHITUNGAN VOLUME
K-523. Konstruksi Lapis Pondasi Atas (LPA) Kelas - B (t = 10 cm)
PEKERJAAN PENGASPALAN JALAN RUAS JALAN UMUM, Sep. 87 M' x 3 M'

DESA : SISOBALAURU
KECAMATAN : HILIDUHO
KABUPATEN / KOTA : NIAS
PROVINSI : SUMATERA UTARA
NO. RAB :
BIDANG : PEMBANGUNAN DESA
KEGIATAN : PEKERJAAN PENGASPALAN JALAN RUAS JALAN UMUM, Sep. 87 M' x 3 M'

WA'OZISOKHI WARUWU, S.Pd.SD SIASA NDRAHA OTONI NDRAHA


Ketua
TAKE OF SHEET (TOS)
PERHITUNGAN VOLUME
K-880. Lapisan Aspal Resap Pelekat (Prime Coat)
PEKERJAAN PENGASPALAN JALAN RUAS JALAN UMUM, Sep. 87 M' x 3 M'

DESA : SISOBALAURU
KECAMATAN : HILIDUHO
KABUPATEN / KOTA : NIAS
PROVINSI : SUMATERA UTARA
NO. RAB :
BIDANG : PEMBANGUNAN DESA
KEGIATAN : PEKERJAAN PENGASPALAN JALAN RUAS JALAN UMUM, Sep. 87 M' x 3 M'

Sketsa

Pas. Leveling Lapis Pondasi Bawah (LPB)


Telford, t = 20 cm
Lapisan Penetrasi Macadam (Lapen)
t = 5 cm
Lapisan Aspal Resap Pelekat (Primecoat)
Timbunan Bahu Jalan Pas. Lapis Pondasi Atas (LPA)
(tanah biasa) t = 10 cm
t = 30 cm
2 %
? 2 %
Pas. Lapis Pondasi Bawah (LPB)
Telford, t = 20 cm
4 % 4 %

0,30 0,30

0,40 0,40
0,50 3,00 0,50
POT. TIPIKAL MELINTANG PENGASPALAN JALAN
P0+000 - P0+087

LEBAR LEBAR
PANJANG KUANTITAS KOEF.
RATA - PENGHAM KUANTITAS
RATA BRUTO
PARAN
NO. STATION / LETAK SISI
(m) (m) ( M2 )
(m) ( m2 )
L L P ( Ltr/m2 )
1 2 3 4 5 6 7=(5x6) 8 9=(7x8)

1 STA. 0 + 000 Tengah 3.00


3.00 87.00 261.00 0.80 208.80
2 STA. 0 + 087 Tengah 3.00

Jumlah halaman ini 87.00 208.80


Jumlah s/d halaman ini 87.00 208.80

SISOBALAURU, 2021

DISETUJUI OLEH : DIVERIFIKASI OLEH : DIBUAT OLEH :


Pj. KEPALA DESA SEKRETARIS DESA TIM PELAKSANA KEGIATAN
TAKE OF SHEET (TOS)
PERHITUNGAN VOLUME
K-880. Lapisan Aspal Resap Pelekat (Prime Coat)
PEKERJAAN PENGASPALAN JALAN RUAS JALAN UMUM, Sep. 87 M' x 3 M'

DESA : SISOBALAURU
KECAMATAN : HILIDUHO
KABUPATEN / KOTA : NIAS
PROVINSI : SUMATERA UTARA
NO. RAB :
BIDANG : PEMBANGUNAN DESA
KEGIATAN : PEKERJAAN PENGASPALAN JALAN RUAS JALAN UMUM, Sep. 87 M' x 3 M'

WA'OZISOKHI WARUWU, S.Pd.SD SIASA NDRAHA OTONI NDRAHA


Ketua
TAKE OF SHEET (TOS)
PERHITUNGAN VOLUME
K-618. Lapisan Penetrasi Macadam (Lapen) (t = 5 cm)
PEKERJAAN PENGASPALAN JALAN RUAS JALAN UMUM, Sep. 87 M' x 3 M'

DESA : SISOBALAURU
KECAMATAN : HILIDUHO
KABUPATEN / KOTA : NIAS
PROVINSI : SUMATERA UTARA
NO. RAB :
BIDANG : PEMBANGUNAN DESA
KEGIATAN : PEKERJAAN PENGASPALAN JALAN RUAS JALAN UMUM, Sep. 87 M' x 3 M'

Sketsa

Pas. Leveling Lapis Pondasi Bawah (LPB)


Telford, t = 20 cm
Lapisan Penetrasi Macadam (Lapen)
t = 5 cm
Lapisan Aspal Resap Pelekat (Primecoat)
Timbunan Bahu Jalan Pas. Lapis Pondasi Atas (LPA)
(tanah biasa) t = 10 cm
t = 30 cm
2 %
? 2 %
Pas. Lapis Pondasi Bawah (LPB)
Telford, t = 20 cm
4 % 4 %

0,30 0,30

0,40 0,40
0,50 3,00 0,50
POT. TIPIKAL MELINTANG PENGASPALAN JALAN
P0+000 - P0+087

LEBAR LEBAR RATA - PANJANG


RATA KUANTITAS
NO. STATION / LETAK SISI (m
(m) ) (m)
( M2 )

L L P
1 2 3 4 5 6 7=(5x6)

1 STA. 0 + 000 Tengah 3.00


3.00 87.00 261.00
2 STA. 0 + 087 Tengah 3.00

Jumlah halaman ini 87.00 261.00


Jumlah s/d halaman ini 87.00 261.00

SISOBALAURU, 2021

DISETUJUI OLEH : DIVERIFIKASI OLEH : DIBUAT OLEH :


Pj. KEPALA DESA SEKRETARIS DESA TIM PELAKSANA KEGIATAN
TAKE OF SHEET (TOS)
PERHITUNGAN VOLUME
K-618. Lapisan Penetrasi Macadam (Lapen) (t = 5 cm)
PEKERJAAN PENGASPALAN JALAN RUAS JALAN UMUM, Sep. 87 M' x 3 M'

DESA : SISOBALAURU
KECAMATAN : HILIDUHO
KABUPATEN / KOTA : NIAS
PROVINSI : SUMATERA UTARA
NO. RAB :
BIDANG : PEMBANGUNAN DESA
KEGIATAN : PEKERJAAN PENGASPALAN JALAN RUAS JALAN UMUM, Sep. 87 M' x 3 M'

WA'OZISOKHI WARUWU, S.Pd.SD SIASA NDRAHA OTONI NDRAHA


Ketua
TAKE OF SHEET (TOS)
PERHITUNGAN VOLUME
K-410. Membentuk Bahu Jalan (Tanah Timbunan Biasa)
PEKERJAAN PENGASPALAN JALAN RUAS JALAN UMUM, Sep. 87 M' x 3 M'

DESA : SISOBALAURU
KECAMATAN : HILIDUHO
KABUPATEN / KOTA : NIAS
PROVINSI : SUMATERA UTARA
NO. RAB :
BIDANG : PEMBANGUNAN DESA
KEGIATAN : PEKERJAAN PENGASPALAN JALAN RUAS JALAN UMUM, Sep. 87 M' x 3 M'

Sketsa

Pas. Leveling Lapis Pondasi Bawah (LPB)


Telford, t = 20 cm
Lapisan Penetrasi Macadam (Lapen)
t = 5 cm
Lapisan Aspal Resap Pelekat (Primecoat)
Timbunan Bahu Jalan Pas. Lapis Pondasi Atas (LPA)
(tanah biasa) t = 10 cm
t = 30 cm
2 %
? 2 %
Pas. Lapis Pondasi Bawah (LPB)
Telford, t = 20 cm
4 % 4 %

0,30 0,30

0,40 0,40
0,50 3,00 0,50
POT. TIPIKAL MELINTANG PENGASPALAN JALAN
P0+000 - P0+087

LEBAR LEBAR TEBAL


TEBAL PANJANG
RATA - RATA -
RATA RATA KUANTITAS
NO. STATION / LETAK SISI
(m) (m) ( M3 )
(m) (m)
(m)
L L T T P
1 2 3 4 5 6 7 8 9=(5x7x8)

1 STA. 0 + 000 Kanan 0.50 0.30


0.50 0.30 87.00 13.05
2 STA. 0 + 087 Kanan 0.50 0.30

Jumlah halaman ini 87.00 13.05


Jumlah s/d halaman ini

SISOBALAURU, 2021

DISETUJUI OLEH : DIVERIFIKASI OLEH : DIBUAT OLEH :


Pj. KEPALA DESA SEKRETARIS DESA TIM PELAKSANA KEGIATAN
TAKE OF SHEET (TOS)
PERHITUNGAN VOLUME
K-410. Membentuk Bahu Jalan (Tanah Timbunan Biasa)
PEKERJAAN PENGASPALAN JALAN RUAS JALAN UMUM, Sep. 87 M' x 3 M'

DESA : SISOBALAURU
KECAMATAN : HILIDUHO
KABUPATEN / KOTA : NIAS
PROVINSI : SUMATERA UTARA
NO. RAB :
BIDANG : PEMBANGUNAN DESA
KEGIATAN : PEKERJAAN PENGASPALAN JALAN RUAS JALAN UMUM, Sep. 87 M' x 3 M'

WA'OZISOKHI WARUWU, S.Pd.SD SIASA NDRAHA OTONI NDRAHA


Ketua
Sketsa

Pas. Leveling Lapis Pondasi Bawah (LPB)


Telford, t = 20 cm
Lapisan Penetrasi Macadam (Lapen)
t = 5 cm
Lapisan Aspal Resap Pelekat (Primecoat)
Timbunan Bahu Jalan Pas. Lapis Pondasi Atas (LPA)
(tanah biasa) t = 10 cm
t = 30 cm
2 %
? 2 %
Pas. Lapis Pondasi Bawah (LPB)
Telford, t = 20 cm
4 % 4 %

0,30 0,30

0,40 0,40
0,50 3,00 0,50
POT. TIPIKAL MELINTANG PENGASPALAN JALAN
P0+000 - P0+087

LEBAR LEBAR TEBAL


TEBAL PANJANG
RATA - RATA -
RATA RATA KUANTITAS
NO. STATION / LETAK SISI
(m) (m) ( M3 )
(m) (m)
(m)
L L T T P
1 2 3 4 5 6 7 8 9=(5x7x8)

1 STA. 0 + 000 Kiri 0.50 0.30


0.50 0.30 87.00 13.05
2 STA. 0 + 087 Kiri 0.50 0.30

Jumlah halaman ini 87.00 13.05


Jumlah s/d halaman ini 174.00 26.10

SISOBALAURU, 2021

DISETUJUI OLEH : DIVERIFIKASI OLEH : DIBUAT OLEH :


TAKE OF SHEET (TOS)
PERHITUNGAN VOLUME
K-410. Membentuk Bahu Jalan (Tanah Timbunan Biasa)
PEKERJAAN PENGASPALAN JALAN RUAS JALAN UMUM, Sep. 87 M' x 3 M'

DESA : SISOBALAURU
KECAMATAN : HILIDUHO
KABUPATEN / KOTA : NIAS
PROVINSI : SUMATERA UTARA
NO. RAB :
BIDANG : PEMBANGUNAN DESA
KEGIATAN : PEKERJAAN PENGASPALAN JALAN RUAS JALAN UMUM, Sep. 87 M' x 3 M'

Pj. KEPALA DESA SEKRETARIS DESA TIM PELAKSANA KEGIATAN

WA'OZISOKHI WARUWU, S.Pd.SD SIASA NDRAHA OTONI NDRAHA


Ketua
TAKE OF SHEET (TOS)
PERHITUNGAN VOLUME
K-110. Membuat Parit Galian Tanah
PEKERJAAN GALIAN PARIT TANAH, Sep. 248 M

DESA : SISOBALAURU
KECAMATAN : HILIDUHO
KABUPATEN / KOTA : NIAS
PROVINSI : SUMATERA UTARA
NO. RAB :
BIDANG : PEMBANGUNAN DESA
KEGIATAN : PEKERJAAN GALIAN PARIT TANAH, Sep. 248 M

Sketsa

130

60

50
POT. TIPIKAL MELINTANG GALIAN PARIT TANAH
SEP. 223 M' (KANAN)

LEBAR
LEBAR TINGGI
BAWAH PANJANG
ATAS LUAS
LUAS RATA -
KUANTITAS
NO. STATION / LETAK SISI RATA
( m2 )
(m) ( M3 )
(m) (
(m) m2 )
(m)
L1 L2 T A P
1 2 3 4 5 6 7=(((4+5)/2)*6) 8 9 10=(8x9)

1 STA. 0 + 000 Kanan 1.30 0.50 0.60 0.54


0.54 223.00 120.42
2 STA. 0 + 223 Kanan 1.30 0.50 0.60 0.54

Jumlah halaman ini 223.00 120.42


Jumlah s/d halaman ini

SISOBALAURU, 2021

DISETUJUI OLEH : DIVERIFIKASI OLEH : DIBUAT OLEH :


Pj. KEPALA DESA SEKRETARIS DESA TIM PELAKSANA KEGIATAN
TAKE OF SHEET (TOS)
PERHITUNGAN VOLUME
K-110. Membuat Parit Galian Tanah
PEKERJAAN GALIAN PARIT TANAH, Sep. 248 M

DESA : SISOBALAURU
KECAMATAN : HILIDUHO
KABUPATEN / KOTA : NIAS
PROVINSI : SUMATERA UTARA
NO. RAB :
BIDANG : PEMBANGUNAN DESA
KEGIATAN : PEKERJAAN GALIAN PARIT TANAH, Sep. 248 M

WA'OZISOKHI WARUWU, S.Pd.SD SIASA NDRAHA OTONI NDRAHA


Ketua
TAKE OF SHEET (TOS)
PERHITUNGAN VOLUME
K-110. Membuat Parit Galian Tanah
PEKERJAAN GALIAN PARIT TANAH, Sep. 248 M

DESA : SISOBALAURU
KECAMATAN : HILIDUHO
KABUPATEN / KOTA : NIAS
PROVINSI : SUMATERA UTARA
NO. RAB :
BIDANG : PEMBANGUNAN DESA
KEGIATAN : PEKERJAAN GALIAN PARIT TANAH, Sep. 248 M

Sketsa

130

60

50
POT. TIPIKAL MELINTANG GALIAN PARIT TANAH
SEP. 25 M' (KIRI)

LEBAR
LEBAR TINGGI
BAWAH PANJANG
ATAS LUAS
LUAS RATA -
KUANTITAS
NO. STATION / LETAK SISI RATA
( m2 )
(m) ( M3 )
(m) (
(m) m2 )
(m)
L1 L2 T A P
1 2 3 4 5 6 7=(((4+5)/2)*6) 8 9 10=(8x9)

1 STA. 0 + 000 Kiri 1.30 0.50 0.60 0.54


0.54 25.00 13.50
2 STA. 0 + 025 Kiri 1.30 0.50 0.60 0.54

Jumlah halaman ini 25.00 13.50


Jumlah s/d halaman ini 248.00 133.92

SISOBALAURU, 2021

DISETUJUI OLEH : DIVERIFIKASI OLEH : DIBUAT OLEH :


Pj. KEPALA DESA SEKRETARIS DESA TIM PELAKSANA KEGIATAN
TAKE OF SHEET (TOS)
PERHITUNGAN VOLUME
K-110. Membuat Parit Galian Tanah
PEKERJAAN GALIAN PARIT TANAH, Sep. 248 M

DESA : SISOBALAURU
KECAMATAN : HILIDUHO
KABUPATEN / KOTA : NIAS
PROVINSI : SUMATERA UTARA
NO. RAB :
BIDANG : PEMBANGUNAN DESA
KEGIATAN : PEKERJAAN GALIAN PARIT TANAH, Sep. 248 M

WA'OZISOKHI WARUWU, S.Pd.SD SIASA NDRAHA OTONI NDRAHA


Ketua
TAKE OF SHEET (TOS)
PERHITUNGAN VOLUME
K-320. Membentuk Badan Jalan / Subgrade di Daerah Galian
PEKERJAAN GALIAN PEMBENTUKAN BADAN JALAN, Sep. 95 M' x 4 M'

DESA : SISOBALAURU
KECAMATAN : HILIDUHO
KABUPATEN / KOTA : NIAS
PROVINSI : SUMATERA UTARA
NO. RAB :
BIDANG : PEMBANGUNAN DESA
KEGIATAN : PEKERJAAN GALIAN PEMBENTUKAN BADAN JALAN, Sep. 95 M' x 4 M'

Sketsa

Galian Pembentukan Badan Jalan 1,8 m'

95 m'

POT. TIPIKAL MEMANJANG GALIAN BADAN JALAN


P0+000 - P0+95

Galian Pembentukan Badan Jalan

30

4,00
POT. TIPIKAL MELINTANG GALIAN BADAN JALAN
P0+000

Galian Pembentukan Badan Jalan

150

4,00
POT. TIPIKAL MELINTANG GALIAN BADAN JALAN
P0+048

Galian Pembentukan Badan Jalan

30

4,00
POT. TIPIKAL MELINTANG GALIAN BADAN JALAN
P0+095

LEBAR TINGGI TINGGI PANJANG


TINGGI LUAS LUAS
RATA - RATA - KUANTITA
NO. STATION / LETAK SISI RATA ( RATA S
m2 ) (m)
(m) (m) (m) ( ( ( M3 )
m) m2 )
L T1 T2 A P
1 2 3 4 5 6 7 8=(4*7) 9 10 11=(9x10)

1 STA. 0 + 000 Tengah 4.00 0.30 0.30 0.30 1.20


4.20 47.50 199.50
2 STA. 0 + 048 Tengah 4.00 1.80 1.80 1.80 7.20
4.20 47.50 199.50
3 STA. 0 + 095 Tengah 4.00 0.30 0.30 0.30 1.20

Jumlah halaman ini 95.00 399.00


Jumlah s/d halaman ini 95.00 399.00

SISOBALAURU, 2021

DISETUJUI OLEH : DIVERIFIKASI OLEH : DIBUAT OLEH :


Pj. KEPALA DESA SEKRETARIS DESA TIM PELAKSANA KEGIATAN
TAKE OF SHEET (TOS)
PERHITUNGAN VOLUME
K-320. Membentuk Badan Jalan / Subgrade di Daerah Galian
PEKERJAAN GALIAN PEMBENTUKAN BADAN JALAN, Sep. 95 M' x 4 M'

DESA : SISOBALAURU
KECAMATAN : HILIDUHO
KABUPATEN / KOTA : NIAS
PROVINSI : SUMATERA UTARA
NO. RAB :
BIDANG : PEMBANGUNAN DESA
KEGIATAN : PEKERJAAN GALIAN PEMBENTUKAN BADAN JALAN, Sep. 95 M' x 4 M'

WA'OZISOKHI WARUWU, S.Pd.SD SIASA NDRAHA OTONI NDRAHA


Ketua
REKAPITULASI RENCANA ANGGARAN BIAYA
PEKERJAAN KEGIATAN FISIK DANA DESA (SILPA TA.2020)
DESA : SISOBALAURU
KECAMATAN : HILIDUHO
KABUPATEN / KOTA : NIAS
PROVINSI : SUMATERA UTARA
NO. RAB :
BIDANG : PEMBANGUNAN DESA
KEGIATAN : PEK. TEMBOK PENAHAN TANAH 2 Tpt Sep. 36.40 M' & Tinggi 1.50 M' (Kanan = 18.20 M' + Kiri = 18.20 M')

URAIAN HARGA SATUAN JLH. HARGA


NO SAT. VOLUME
PEKERJAAN
Rp. Rp.
1 2 4 5 6 7
I PEK. TEMBOK PENAHAN TANAH 2 Tpt Sep. 36.40 M' & Tinggi 1.50 M' (Kanan = 18.20 M' + Kiri = 18.20 M')
A. Upah
- Pekerja HOK 74.00 100,000.00 7,400,000.00
- Tukang HOK 31.00 120,000.00 3,720,000.00
- Kep. Tukang HOK 4.00 140,000.00 560,000.00
Sub. Total Upah 11,680,000.00
B. Bahan
- Papan Bekisting,uk. 0.20 m x 0.02 m x 2.0 m Lbr 4.00 21,200.00 84,800.00
- Kayu segi/Broti, uk. 5 - 7 cm. Pjg. 3.00 M' Btg 4.00 27,900.00 111,600.00
- Paku Biasa Kg 0.50 20,000.00 10,000.00
- Semen PC Zak 87.00 99,300.00 8,639,100.00
- Pasir Pasangan M3 14.00 181,300.00 2,538,200.00
- Batu Gunung Belah 10/15 M3 28.00 187,500.00 5,250,000.00
Sub. Total Bahan 16,633,700.00
C. Peralatan
- Meteran uk. 5.0 m Bh 1.00 30,200.00 30,200.00
- Gerobak sorong Unit 2.00 605,500.00 1,211,000.00
- Sekop besar + gagang Bh 2.00 113,800.00 227,600.00
- Raskam besi Bh 2.00 50,200.00 100,400.00
- Raskam Plastik Bh 2.00 33,500.00 67,000.00
- Cangkul + gagang Bh 3.00 113,800.00 341,400.00
- Tembilang/penggali + gagang Bh 2.00 66,900.00 133,800.00
- Ember cor Bh 8.00 13,400.00 107,200.00
- Sendok Semen Bh 4.00 30,100.00 120,400.00
- Pecok/Bolak baling + gagang Bh 2.00 139,400.00 278,800.00
- Selang Ukur Glg 1.00 16,800.00 16,800.00
- Palu/Penokok Bh 2.00 46,900.00 93,800.00
- Drum Plastik 200 ltr (Tampungan Air Hujan) Bh 1.00 328,400.00 328,400.00
- Benang Tukang (Nilon) Glg 1.00 16,800.00 16,800.00
- Sarung Tangan Pekerja (karet) Psg 9.00 14,800.00 133,200.00
Sub. Total Peralatan 3,206,800.00
D. Upah Angkut / Pikul Tenaga Manusia
- Pasir Pasangan HOK 14.00 56,250.00 787,500.00
- Batu Gunung Belah 10/15 HOK 28.00 56,250.00 1,575,000.00
Sub. Total Upah Angkut / Pikul Tenaga Manusia 2,362,500.00
URAIAN HARGA SATUAN JLH. HARGA
NO SAT. VOLUME
PEKERJAAN
Rp. Rp.
1 2 4 5 6 7
E. Ongkos Angkut Truk
- Papan Bekisting,uk. 0.20 m x 0.02 m x 2.0 m Lbr 4.00 1,000.00 4,000.00
- Kayu segi/Broti, uk. 5 - 7 cm. Pjg. 3.00 M' Btg 4.00 1,300.00 5,200.00
- Semen PC Zak 87.00 10,000.00 870,000.00
- Pasir Pasangan M3 14.00 249,900.00 3,498,600.00
- Batu Gunung Belah 10/15 M3 28.00 326,400.00 9,139,200.00
Sub. Total Upah Angkut Truk 13,517,000.00

JUMLAH TOTAL ( A + B + C + D + E ) Rp. 47,400,000.00

Terbilang : Empat Puluh Tujuh Juta Empat Ratus Ribu Rupiah

SISOBALAURU, 2021

DISETUJUI OLEH : DIVERIFIKASI OLEH : DIBUAT OLEH :


Pj. KEPALA DESA SEKRETARIS DESA TIM PELAKSANA KEGIATAN

WA'OZISOKHI WARUWU, S.Pd.SD SIASA NDRAHA OTONI NDRAHA


Ketua
RINCIAN RENCANA ANGGARAN BIAYA
PEKERJAAN KEGIATAN FISIK DANA DESA (SILPA TA.2020)
DESA : SISOBALAURU
KECAMATAN : HILIDUHO
KABUPATEN / KOTA : NIAS
PROVINSI : SUMATERA UTARA
NO. RAB :
BIDANG : PEMBANGUNAN DESA
KEGIATAN : PEK. TEMBOK PENAHAN TANAH 2 Tpt Sep. 36.40 M' & Tinggi 1.50 M' (Kanan = 18.20 M' + Kiri = 18.20 M')
KODE
URAIAN HARGA SATUAN JLH. HARGA
NO ANALISA SAT. VOLUME
PEKERJAAN
PEKERJAAN Rp. Rp.
1 2 3 4 5 6 7
I PEK. TEMBOK PENAHAN TANAH 2 Tpt Sep. 36.40 M' & Tinggi 1.50 M' (Kanan = 18.20 M' + Kiri = 18.20 M')
1 Pek. Galian tanah A.2.3.1.1.
A. Upah
- Pekerja HOK 8.00 100,000.00 800,000.00

B. Bahan
- Papan Bekisting,uk. 0.20 m x 0.02 m x 2.0 m Lbr 4.00 21,200.00 84,800.00
- Kayu segi/Broti, uk. 5 - 7 cm. Pjg. 3.00 M' Btg 4.00 27,900.00 111,600.00
- Paku Biasa Kg 0.50 20,000.00 10,000.00

C. Peralatan
- Meteran uk. 5.0 m Bh 1.00 30,200.00 30,200.00
- Gerobak sorong Unit 2.00 605,500.00 1,211,000.00
- Sekop besar + gagang Bh 2.00 113,800.00 227,600.00
- Raskam besi Bh 2.00 50,200.00 100,400.00
- Raskam Plastik Bh 2.00 33,500.00 67,000.00
- Cangkul + gagang Bh 3.00 113,800.00 341,400.00
- Tembilang/penggali + gagang Bh 2.00 66,900.00 133,800.00
- Ember cor Bh 8.00 13,400.00 107,200.00
- Sendok Semen Bh 4.00 30,100.00 120,400.00
- Pecok/Bolak baling + gagang Bh 2.00 139,400.00 278,800.00
- Selang Ukur Glg 1.00 16,800.00 16,800.00
- Palu/Penokok Bh 2.00 46,900.00 93,800.00
- Drum Plastik 200 ltr (Tampungan Air Hujan) Bh 1.00 328,400.00 328,400.00
- Benang Tukang (Nilon) Glg 1.00 16,800.00 16,800.00
- Sarung Tangan Pekerja (karet) Psg 9.00 14,800.00 133,200.00

D. Upah Angkut / Pikul Tenaga Manusia - - - -

E. Ongkos Angkut Truk


- Papan Bekisting,uk. 0.20 m x 0.02 m x 2.0 m Lbr 4.00 1,000.00 4,000.00
- Kayu segi/Broti, uk. 5 - 7 cm. Pjg. 3.00 M' Btg 4.00 1,300.00 5,200.00

Sub. Total.1 4,222,400.00


2 Pek. Pasangan batu A.3.2.1.2.
A. Upah
- Pekerja HOK 35.00 100,000.00 3,500,000.00
- Tukang HOK 18.00 120,000.00 2,160,000.00
- Kep. Tukang HOK 2.00 140,000.00 280,000.00

B. Bahan
- Semen PC Zak 75.00 99,300.00 7,447,500.00
- Pasir Pasangan M3 12.00 181,300.00 2,175,600.00
- Batu Gunung Belah 10/15 M3 28.00 187,500.00 5,250,000.00

C. Peralatan - - - -

D. Upah Angkut / Pikul Tenaga Manusia


- Pasir Pasangan HOK 12.00 56,250.00 675,000.00
- Batu Gunung Belah 10/15 HOK 28.00 56,250.00 1,575,000.00

E. Ongkos Angkut Truk


- Semen PC Zak 75.00 10,000.00 750,000.00
KODE
URAIAN HARGA SATUAN JLH. HARGA
NO ANALISA SAT. VOLUME
PEKERJAAN
PEKERJAAN Rp. Rp.
1 2 3 4 5 6 7
- Pasir Pasangan M3 12.00 249,900.00 2,998,800.00
- Batu Gunung Belah 10/15 M3 28.00 326,400.00 9,139,200.00

Sub. Total.2 35,951,100.00


KODE
URAIAN HARGA SATUAN JLH. HARGA
NO ANALISA SAT. VOLUME
PEKERJAAN
PEKERJAAN Rp. Rp.
1 2 3 4 5 6 7
3 Pek. Plesteran permukaan yang nampak A.4.4.2.3.
A. Upah
- Pekerja HOK 15.00 100,000.00 1,500,000.00
- Tukang HOK 8.00 120,000.00 960,000.00
- Kep. Tukang HOK 1.00 140,000.00 140,000.00

B. Bahan
- Semen PC Zak 8.00 99,300.00 794,400.00
- Pasir Pasangan M3 2.00 181,300.00 362,600.00

C. Peralatan - - - -

D. Upah Angkut / Pikul Tenaga Manusia


- Pasir Pasangan HOK 2.00 56,250.00 112,500.00

E. Ongkos Angkut Truk


- Semen PC Zak 8.00 10,000.00 80,000.00
- Pasir Pasangan M3 2.00 249,900.00 499,800.00

Sub. Total.3 4,449,300.00


4 Pek. Acian permukaan yang nampak A.4.4.2.27.
A. Upah
- Pekerja HOK 10.00 100,000.00 1,000,000.00
- Tukang HOK 5.00 120,000.00 600,000.00
- Kep. Tukang HOK 1.00 140,000.00 140,000.00

B. Bahan
- Semen PC Zak 4.00 99,300.00 397,200.00

C. Peralatan - - - -

D. Upah Angkut / Pikul Tenaga Manusia - - - -

E. Ongkos Angkut Truk


- Semen PC Zak 4.00 10,000.00 40,000.00

Sub. Total.4 2,177,200.00


5 Pek. Pengurugan Kembali ( dari Bekas Galian ) A.2.3.1.9.
A. Upah
- Pekerja HOK 6.00 100,000.00 600,000.00

B. Bahan - - - -

C. Peralatan - - - -

D. Upah Angkut / Pikul Tenaga Manusia - - - -

E. Ongkos Angkut Truk - - - -

Sub. Total.5 600,000.00

JUMLAH TOTAL ( 1 + 2 + 3 + 4 + 5 ) Rp. 47,400,000.00

Terbilang : Empat Puluh Tujuh Juta Empat Ratus Ribu Rupiah

SISOBALAURU, 2021

DISETUJUI OLEH : DIVERIFIKASI OLEH : DIBUAT OLEH :


Pj. KEPALA DESA SEKRETARIS DESA TIM PELAKSANA KEGIATAN
KODE
URAIAN HARGA SATUAN JLH. HARGA
NO ANALISA SAT. VOLUME
PEKERJAAN
PEKERJAAN Rp. Rp.
1 2 3 4 5 6 7

WA'OZISOKHI WARUWU, S.Pd.SD SIASA NDRAHA OTONI NDRAHA


Ketua
RINCIAN ANALISA SATUAN PEKERJAAN
PEKERJAAN KEGIATAN FISIK DANA DESA (SILPA TA.2020)
(Ref. ANALISA SNI Thn.2016 - PERMEN PUPR No. 28/PRT/M/2016)
DESA : SISOBALAURU
KECAMATAN : HILIDUHO
KABUPATEN / KOTA : NIAS
PROVINSI : SUMATERA UTARA
NO. RAB :
BIDANG : PEMBANGUNAN DESA
KEGIATAN : PEK. TEMBOK PENAHAN TANAH 2 Tpt Sep. 36.40 M' & Tinggi 1.50 M' (Kanan = 18.20 M' + Kiri = 18.20 M')
VOLUME
URAIAN KODE URAIAN KEBUTUHAN TERHADAP ANALISA SATUAN PEKERJAAN
NO PEKERJA ANALISA SAT.
AN PEKERJAAN ANALISA SATUAN PEKERJAAN SATUAN KOEFISIEN VOLUME
1 2 3 4 5 6 7 8 9 = (5 * 8)
TOS
1 Pek. Galian tanah A.2.3.1.1. m3 10.01 Penggalian 1 m3 tanah biasa sedalam 1 m
Tenaga Kerja Pekerja OH 0.750 7.508
Bahan
Peralatan
2 Pek. Pasangan batu A.3.2.1.2. m3 22.75 Pemasangan 1 m3 batu belah campuran 1SP : 4PP
Pekerja OH 1.500 34.125
Tenaga Kerja Tukang OH 0.750 17.063
Kep. Tukang OH 0.075 1.706
Semen PC Zak 3.260 74.165
Bahan Pasir Pasangan M3 0.520 11.830
Batu Gunung Belah 10/15 M3 1.200 27.300
Peralatan
3 Pek. Plesteran permukaan yang nampak A.4.4.2.3. m2 47.32 Pemasangan 1 m2 plesteran 1SP : 3PP tebal 15mm
Pekerja OH 0.300 14.196
Tenaga Kerja Tukang OH 0.150 7.098
Kep. Tukang OH 0.015 0.710
Semen PC Zak 0.156 7.359
Bahan
Pasir Pasangan M3 0.023 1.088
Peralatan
VOLUME
URAIAN KODE URAIAN KEBUTUHAN TERHADAP ANALISA SATUAN PEKERJAAN
NO PEKERJA ANALISA SAT.
AN PEKERJAAN ANALISA SATUAN PEKERJAAN SATUAN KOEFISIEN VOLUME
1 2 3 4 5 6 7 8 9 = (5 * 8)
TOS
4 Pek. Acian permukaan yang nampak A.4.4.2.27. m2 47.32 Pemasangan 1 m2 acian
Pekerja OH 0.200 9.464
Tenaga Kerja Tukang OH 0.100 4.732
Kep. Tukang OH 0.010 0.473
Bahan Semen PC Zak 0.065 3.076
Peralatan
5 Pek. Pengurugan Kembali ( dari Bekas Galian ) A.2.3.1.9. m3 10.01 Pengurugan kembali 1 m3 galian tanah
Tenaga Kerja Pekerja OH 0.500 5.005
Bahan
Peralatan

SISOBALAURU, 2021

DISETUJUI OLEH : DIVERIFIKASI OLEH : DIBUAT OLEH :


Pj. KEPALA DESA SEKRETARIS DESA TIM PELAKSANA KEGIATAN

WA'OZISOKHI WARUWU, S.Pd.SD SIASA NDRAHA OTONI NDRAHA


Ketua
AAN
DIBULATKAN
10

8.000

35.000
18.000
2.000
75.000
12.000
28.000

15.000
8.000
1.000
8.000
2.000
AAN
DIBULATKAN
10

10.000
5.000
1.000
4.000

6.000
TAKE OF SHEET (TOS)
PERHITUNGAN VOLUME
SNI. A.2.3.1.1. Penggalian 1 m3 tanah biasa sedalam 1 m
PEK. TEMBOK PENAHAN TANAH 2 Tpt Sep. 36.40 M' & Tinggi 1.50 M' (Kanan = 18.20 M' + Kiri = 18.20 M')

DESA : SISOBALAURU
KECAMATAN : HILIDUHO
KABUPATEN / KOTA : NIAS
PROVINSI : SUMATERA UTARA
NO. RAB :
BIDANG : PEMBANGUNAN DESA
KEGIATAN : PEK. TEMBOK PENAHAN TANAH 2 Tpt Sep. 36.40 M' & Tinggi 1.50 M' (Kanan = 18.20 M' + Kiri = 18.20 M')

Sketsa

Pas. Batu Gunung


Camp. 1 : 4
Timbunan
tanah setempat
(dari sisa galian)

50 25 Plasteran Permukaan
yang tampak Camp. 1 : 3
& Acian

100

5 45 5 50

55
POT. TIPIKAL MELINTANG TEMBOK PENAHAN TANAH
SEP. 18,20 M' & TINGGI 1,50 M'

BIDANG PERSEGI BIDANG TRAPESIUM BIDANG SEGITIGA


LUAS LUAS RATA - PANJANG
LEBAR TINGGI LEBAR TINGGI RATA
No POSISI / LETAK SISI TINGGI TINGGI RATA LEBAR LEBAR RATA 1/2
(m) - RATA ( m ) (m) - RATA ( m ) ( m2 ) ( m2 ) (m)
(m) (m) (m) (m)
L T T1 T2 T L1 L2 L L T A A P
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17

0 + 000 Kanan 0.55 0.50 0.28


1 STA. 0.28 18.20
0 + 018.2 Kanan 0.55 0.50 0.28

Jumlah halaman ini 18.20


Jumlah s/d halaman ini 18.20

SISOBALAURU, 2021

DISETUJUI OLEH : DIVERIFIKASI OLEH : DIBUAT OLEH :


Pj. KEPALA DESA SEKRETARIS DESA TIM PELAKSANA KEGIATAN

WA'OZISOKHI WARUWU, S.Pd.SD SIASA NDRAHA OTONI NDRAHA


Ketua
TAKE OF SHEET (TOS)
PERHITUNGAN VOLUME
SNI. A.2.3.1.1. Penggalian 1 m3 tanah biasa sedalam 1 m
PEK. TEMBOK PENAHAN TANAH 2 Tpt Sep. 36.40 M' & Tinggi 1.50 M' (Kanan = 18.20 M' + Kiri = 18.20 M')

DESA : SISOBALAURU
KECAMATAN : HILIDUHO
KABUPATEN / KOTA : NIAS
PROVINSI : SUMATERA UTARA
NO. RAB :
BIDANG : PEMBANGUNAN DESA
KEGIATAN : PEK. TEMBOK PENAHAN TANAH 2 Tpt Sep. 36.40 M' & Tinggi 1.50 M' (Kanan = 18.20 M' + Kiri = 18.20 M')

Sketsa

Pas. Batu Gunung


Camp. 1 : 4
Timbunan
tanah setempat
(dari sisa galian)

Plasteran Permukaan 25 50
yang tampak Camp. 1 : 3
& Acian

100

50 5 45 5

55
POT. TIPIKAL MELINTANG TEMBOK PENAHAN TANAH
SEP. 18,20 M' & TINGGI 1,50 M'

BIDANG PERSEGI BIDANG TRAPESIUM BIDANG SEGITIGA


LUAS LUAS RATA - PANJANG
LEBAR TINGGI LEBAR TINGGI RATA
No POSISI / LETAK SISI TINGGI TINGGI RATA LEBAR LEBAR RATA 1/2
(m) - RATA ( m ) (m) - RATA ( m ) ( m2 ) ( m2 ) (m)
(m) (m) (m) (m)
L T T1 T2 T L1 L2 L L T A A P
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17

0 + 000 Kiri 0.55 0.50 0.28


2 STA. 0.28 18.20
0 + 018.2 Kiri 0.55 0.50 0.28

Jumlah halaman ini 18.20


Jumlah s/d halaman ini 18.20

SISOBALAURU, 2021

DISETUJUI OLEH : DIVERIFIKASI OLEH : DIBUAT OLEH :


Pj. KEPALA DESA SEKRETARIS DESA TIM PELAKSANA KEGIATAN

WA'OZISOKHI WARUWU, S.Pd.SD SIASA NDRAHA OTONI NDRAHA


Ketua
JUMLAH KUANTITAS

(n) (m3)
18 19=(16x17x18)

1.00 5.01

5.01
5.01
JUMLAH KUANTITAS

(n) (m3)
18 19=(16x17x18)

1.00 5.01

5.01
5.01
TAKE OF SHEET (TOS)
PERHITUNGAN VOLUME
SNI. A.3.2.1.2. Pemasangan 1 m3 batu belah campuran 1SP : 4PP
PEK. TEMBOK PENAHAN TANAH 2 Tpt Sep. 36.40 M' & Tinggi 1.50 M' (Kanan = 18.20 M' + Kiri = 18.20 M')

DESA : SISOBALAURU
KECAMATAN : HILIDUHO
KABUPATEN / KOTA : NIAS
PROVINSI : SUMATERA UTARA
NO. RAB :
BIDANG : PEMBANGUNAN DESA
KEGIATAN : PEK. TEMBOK PENAHAN TANAH 2 Tpt Sep. 36.40 M' & Tinggi 1.50 M' (Kanan = 18.20 M' + Kiri = 18.20 M')

Sketsa

Pas. Batu Gunung


Camp. 1 : 4
Timbunan
tanah setempat
(dari sisa galian)

50 25 Plasteran Permukaan
yang tampak Camp. 1 : 3
& Acian

100

5 45 5 50

55
POT. TIPIKAL MELINTANG TEMBOK PENAHAN TANAH
SEP. 18,20 M' & TINGGI 1,50 M'

BIDANG PERSEGI BIDANG TRAPESIUM BIDANG SEGITIGA


LUAS LUAS RATA - PANJANG
LEBAR TINGGI LEBAR TINGGI RATA
No POSISI / LETAK SISI TINGGI TINGGI RATA LEBAR LEBAR RATA 1/2
(m) - RATA ( m ) (m) - RATA ( m ) ( m2 ) ( m2 ) (m)
(m) (m) (m) (m)
L T T1 T2 T L1 L2 L L T A A P
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17

0 + 000 Kanan 0.55 0.50 1.00 0.25 0.45 0.35 0.63


1 STA. 0.63 18.20
0 + 018.2 Kanan 0.55 0.50 1.00 0.25 0.45 0.35 0.63

Jumlah halaman ini 18.20


Jumlah s/d halaman ini 18.20

SISOBALAURU, 2021

DISETUJUI OLEH : DIVERIFIKASI OLEH : DIBUAT OLEH :


Pj. KEPALA DESA SEKRETARIS DESA TIM PELAKSANA KEGIATAN

WA'OZISOKHI WARUWU, S.Pd.SD SIASA NDRAHA OTONI NDRAHA


Ketua
TAKE OF SHEET (TOS)
PERHITUNGAN VOLUME
SNI. A.3.2.1.2. Pemasangan 1 m3 batu belah campuran 1SP : 4PP
PEK. TEMBOK PENAHAN TANAH 2 Tpt Sep. 36.40 M' & Tinggi 1.50 M' (Kanan = 18.20 M' + Kiri = 18.20 M')

DESA : SISOBALAURU
KECAMATAN : HILIDUHO
KABUPATEN / KOTA : NIAS
PROVINSI : SUMATERA UTARA
NO. RAB :
BIDANG : PEMBANGUNAN DESA
KEGIATAN : PEK. TEMBOK PENAHAN TANAH 2 Tpt Sep. 36.40 M' & Tinggi 1.50 M' (Kanan = 18.20 M' + Kiri = 18.20 M')

Sketsa

Pas. Batu Gunung


Camp. 1 : 4
Timbunan
tanah setempat
(dari sisa galian)

Plasteran Permukaan 25 50
yang tampak Camp. 1 : 3
& Acian

100

50 5 45 5

55
POT. TIPIKAL MELINTANG TEMBOK PENAHAN TANAH
SEP. 18,20 M' & TINGGI 1,50 M'

BIDANG PERSEGI BIDANG TRAPESIUM BIDANG SEGITIGA


LUAS LUAS RATA - PANJANG
LEBAR TINGGI LEBAR TINGGI RATA
No POSISI / LETAK SISI TINGGI TINGGI RATA LEBAR LEBAR RATA 1/2
(m) - RATA ( m ) (m) - RATA ( m ) ( m2 ) ( m2 ) (m)
(m) (m) (m) (m)
L T T1 T2 T L1 L2 L L T A A P
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17

0 + 000 Kiri 0.55 0.50 1.00 0.25 0.45 0.35 0.63


2 STA. 0.63 18.20
0 + 018.2 Kiri 0.55 0.50 1.00 0.25 0.45 0.35 0.63

Jumlah halaman ini 18.20


Jumlah s/d halaman ini 18.20

SISOBALAURU, 2021

DISETUJUI OLEH : DIVERIFIKASI OLEH : DIBUAT OLEH :


Pj. KEPALA DESA SEKRETARIS DESA TIM PELAKSANA KEGIATAN

WA'OZISOKHI WARUWU, S.Pd.SD SIASA NDRAHA OTONI NDRAHA


Ketua
JUMLAH KUANTITAS

(n) (m3)
18 19=(16x17x18)

1.00 11.38

11.38
11.38
JUMLAH KUANTITAS

(n) (m3)
18 19=(16x17x18)

1.00 11.38

11.38
11.38
TAKE OF SHEET (TOS)
PERHITUNGAN VOLUME
SNI. A.4.4.2.3. Pemasangan 1 m2 plesteran 1SP : 3PP tebal 15mm
PEK. TEMBOK PENAHAN TANAH 2 Tpt Sep. 36.40 M' & Tinggi 1.50 M' (Kanan = 18.20 M' + Kiri = 18.20 M')

DESA : SISOBALAURU
KECAMATAN : HILIDUHO
KABUPATEN / KOTA : NIAS
PROVINSI : SUMATERA UTARA
NO. RAB :
BIDANG : PEMBANGUNAN DESA
KEGIATAN : PEK. TEMBOK PENAHAN TANAH 2 Tpt Sep. 36.40 M' & Tinggi 1.50 M' (Kanan = 18.20 M' + Kiri = 18.20 M')

Sketsa

Pas. Batu Gunung


Camp. 1 : 4
Timbunan
tanah setempat
(dari sisa galian)

50 25 Plasteran Permukaan
yang tampak Camp. 1 : 3
& Acian

100

5 45 5 50

55
POT. TIPIKAL MELINTANG TEMBOK PENAHAN TANAH
SEP. 18,20 M' & TINGGI 1,50 M'

LEBAR - 1 LEBAR - 2 LEBAR - 3 LEBAR LEBAR PANJANG


RATA -
RATA KUANTITAS
NO. STATION / LETAK SISI
( (m) ( M2 )
(m)
(m) m) (m) (m)
L1 L2 L3 L LR P
1 2 3 4 5 6 7=(4+5+6) 8 9 10=(8x9)

STA. 0 + 000 Kanan 0.05 0.25 1.00 1.30


1 1.30 18.20 23.66
STA. 0 + 018.2 Kanan 0.05 0.25 1.00 1.30

Jumlah halaman ini 18.20 23.66


Jumlah s/d halaman ini 18.20 23.66

SISOBALAURU, 2021

DISETUJUI OLEH : DIVERIFIKASI OLEH : DIBUAT OLEH :


Pj. KEPALA DESA SEKRETARIS DESA TIM PELAKSANA KEGIATAN
TAKE OF SHEET (TOS)
PERHITUNGAN VOLUME
SNI. A.4.4.2.3. Pemasangan 1 m2 plesteran 1SP : 3PP tebal 15mm
PEK. TEMBOK PENAHAN TANAH 2 Tpt Sep. 36.40 M' & Tinggi 1.50 M' (Kanan = 18.20 M' + Kiri = 18.20 M')

DESA : SISOBALAURU
KECAMATAN : HILIDUHO
KABUPATEN / KOTA : NIAS
PROVINSI : SUMATERA UTARA
NO. RAB :
BIDANG : PEMBANGUNAN DESA
KEGIATAN : PEK. TEMBOK PENAHAN TANAH 2 Tpt Sep. 36.40 M' & Tinggi 1.50 M' (Kanan = 18.20 M' + Kiri = 18.20 M')

WA'OZISOKHI WARUWU, S.Pd.SD SIASA NDRAHA OTONI NDRAHA


Ketua
Sketsa

Pas. Batu Gunung


Camp. 1 : 4
Timbunan
tanah setempat
(dari sisa galian)

Plasteran Permukaan 25 50
yang tampak Camp. 1 : 3
& Acian

100

50 5 45 5

55
POT. TIPIKAL MELINTANG TEMBOK PENAHAN TANAH
SEP. 18,20 M' & TINGGI 1,50 M'

LEBAR - 1 LEBAR - 2 LEBAR - 3 LEBAR LEBAR


RATA - PANJANG
RATA KUANTITAS
NO. STATION / LETAK SISI
( (m) ( M2 )
(m)
(m) m) (m) (m)
L1 L2 L3 L LR P
1 2 3 4 5 6 7=(4+5+6) 8 9 10=(8x9)

STA. 0 + 000 Kiri 0.05 0.25 1.00 1.30


2 1.30 18.20 23.66
STA. 0 + 018.2 Kiri 0.05 0.25 1.00 1.30

Jumlah halaman ini 18.20 23.66


Jumlah s/d halaman ini 18.20 23.66

SISOBALAURU, 2021
TAKE OF SHEET (TOS)
PERHITUNGAN VOLUME
SNI. A.4.4.2.3. Pemasangan 1 m2 plesteran 1SP : 3PP tebal 15mm
PEK. TEMBOK PENAHAN TANAH 2 Tpt Sep. 36.40 M' & Tinggi 1.50 M' (Kanan = 18.20 M' + Kiri = 18.20 M')

DESA : SISOBALAURU
KECAMATAN : HILIDUHO
KABUPATEN / KOTA : NIAS
PROVINSI : SUMATERA UTARA
NO. RAB :
BIDANG : PEMBANGUNAN DESA
KEGIATAN : PEK. TEMBOK PENAHAN TANAH 2 Tpt Sep. 36.40 M' & Tinggi 1.50 M' (Kanan = 18.20 M' + Kiri = 18.20 M')

DISETUJUI OLEH : DIVERIFIKASI OLEH : DIBUAT OLEH :


Pj. KEPALA DESA SEKRETARIS DESA TIM PELAKSANA KEGIATAN

WA'OZISOKHI WARUWU, S.Pd.SD SIASA NDRAHA OTONI NDRAHA


Ketua
TAKE OF SHEET (TOS)
PERHITUNGAN VOLUME
SNI. A.4.4.2.27. Pemasangan 1 m2 acian
PEK. TEMBOK PENAHAN TANAH 2 Tpt Sep. 36.40 M' & Tinggi 1.50 M' (Kanan = 18.20 M' + Kiri = 18.20 M')

DESA : SISOBALAURU
KECAMATAN : HILIDUHO
KABUPATEN / KOTA : NIAS
PROVINSI : SUMATERA UTARA
NO. RAB :
BIDANG : PEMBANGUNAN DESA
KEGIATAN : PEK. TEMBOK PENAHAN TANAH 2 Tpt Sep. 36.40 M' & Tinggi 1.50 M' (Kanan = 18.20 M' + Kiri = 18.20 M')

Sketsa

Pas. Batu Gunung


Camp. 1 : 4
Timbunan
tanah setempat
(dari sisa galian)

50 25 Plasteran Permukaan
yang tampak Camp. 1 : 3
& Acian

100

5 45 5 50

55
POT. TIPIKAL MELINTANG TEMBOK PENAHAN TANAH
SEP. 18,20 M' & TINGGI 1,50 M'

LEBAR - 1 LEBAR - 2 LEBAR - 3 LEBAR LEBAR PANJANG


RATA -
RATA KUANTITAS
NO. STATION / LETAK SISI
( (m) ( M2 )
(m)
(m) m) (m) (m)
L1 L2 L3 L LR P
1 2 3 4 5 6 7=(4+5+6) 8 9 10=(8x9)

STA. 0 + 000 Kanan 0.05 0.25 1.00 1.30


1 1.30 18.20 23.66
STA. 0 + 018.2 Kanan 0.05 0.25 1.00 1.30

Jumlah halaman ini 18.20 23.66


Jumlah s/d halaman ini 18.20 23.66

SISOBALAURU, 2021

DISETUJUI OLEH : DIVERIFIKASI OLEH : DIBUAT OLEH :


Pj. KEPALA DESA SEKRETARIS DESA TIM PELAKSANA KEGIATAN
TAKE OF SHEET (TOS)
PERHITUNGAN VOLUME
SNI. A.4.4.2.27. Pemasangan 1 m2 acian
PEK. TEMBOK PENAHAN TANAH 2 Tpt Sep. 36.40 M' & Tinggi 1.50 M' (Kanan = 18.20 M' + Kiri = 18.20 M')

DESA : SISOBALAURU
KECAMATAN : HILIDUHO
KABUPATEN / KOTA : NIAS
PROVINSI : SUMATERA UTARA
NO. RAB :
BIDANG : PEMBANGUNAN DESA
KEGIATAN : PEK. TEMBOK PENAHAN TANAH 2 Tpt Sep. 36.40 M' & Tinggi 1.50 M' (Kanan = 18.20 M' + Kiri = 18.20 M')

WA'OZISOKHI WARUWU, S.Pd.SD SIASA NDRAHA OTONI NDRAHA


Ketua
Sketsa

Pas. Batu Gunung


Camp. 1 : 4
Timbunan
tanah setempat
(dari sisa galian)

Plasteran Permukaan
yang tampak Camp. 1 : 3
25 50
& Acian

100

50 5 45 5

55
POT. TIPIKAL MELINTANG TEMBOK PENAHAN TANAH
SEP. 18,20 M' & TINGGI 1,50 M'

LEBAR - 1 LEBAR - 2 LEBAR - 3 LEBAR LEBAR


RATA - PANJANG
RATA KUANTITAS
NO. STATION / LETAK SISI
( (m) ( M2 )
(m)
(m) m) (m) (m)
L1 L2 L3 L LR P
1 2 3 4 5 6 7=(4+5+6) 8 9 10=(8x9)

STA. 0 + 000 Kiri 0.05 0.25 1.00 1.30


2 1.30 18.20 23.66
STA. 0 + 018.2 Kiri 0.05 0.25 1.00 1.30

Jumlah halaman ini 18.20 23.66


Jumlah s/d halaman ini 18.20 23.66

SISOBALAURU, 2021
TAKE OF SHEET (TOS)
PERHITUNGAN VOLUME
SNI. A.4.4.2.27. Pemasangan 1 m2 acian
PEK. TEMBOK PENAHAN TANAH 2 Tpt Sep. 36.40 M' & Tinggi 1.50 M' (Kanan = 18.20 M' + Kiri = 18.20 M')

DESA : SISOBALAURU
KECAMATAN : HILIDUHO
KABUPATEN / KOTA : NIAS
PROVINSI : SUMATERA UTARA
NO. RAB :
BIDANG : PEMBANGUNAN DESA
KEGIATAN : PEK. TEMBOK PENAHAN TANAH 2 Tpt Sep. 36.40 M' & Tinggi 1.50 M' (Kanan = 18.20 M' + Kiri = 18.20 M')

DISETUJUI OLEH : DIVERIFIKASI OLEH : DIBUAT OLEH :


Pj. KEPALA DESA SEKRETARIS DESA TIM PELAKSANA KEGIATAN

WA'OZISOKHI WARUWU, S.Pd.SD SIASA NDRAHA OTONI NDRAHA


Ketua
TAKE OF SHEET (TOS)
PERHITUNGAN VOLUME
SNI. A.2.3.1.9. Pengurugan kembali 1 m3 galian tanah
PEK. TEMBOK PENAHAN TANAH 2 Tpt Sep. 36.40 M' & Tinggi 1.50 M' (Kanan = 18.20 M' + Kiri = 18.20 M')

DESA : SISOBALAURU
KECAMATAN : HILIDUHO
KABUPATEN / KOTA : NIAS
PROVINSI : SUMATERA UTARA
NO. RAB :
BIDANG : PEMBANGUNAN DESA
KEGIATAN : PEK. TEMBOK PENAHAN TANAH 2 Tpt Sep. 36.40 M' & Tinggi 1.50 M' (Kanan = 18.20 M' + Kiri = 18.20 M')

Sketsa

Pas. Batu Gunung


Camp. 1 : 4
Timbunan
tanah setempat
(dari sisa galian)

50 25 Plasteran Permukaan
yang tampak Camp. 1 : 3
& Acian

100

5 45 5 50

55
POT. TIPIKAL MELINTANG TEMBOK PENAHAN TANAH
SEP. 18,20 M' & TINGGI 1,50 M'

BIDANG PERSEGI BIDANG TRAPESIUM BIDANG SEGITIGA


LUAS LUAS RATA - PANJANG
LEBAR TINGGI LEBAR TINGGI RATA
No POSISI / LETAK SISI TINGGI TINGGI RATA LEBAR LEBAR RATA 1/2
(m) - RATA ( m ) (m) - RATA ( m ) ( m2 ) ( m2 ) (m)
(m) (m) (m) (m)
L T T1 T2 T L1 L2 L L T A A P
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17

0 + 000 Kanan 1.00 0.05 0.50 0.28 0.28


1 STA. 0.28 18.20
0 + 018.2 Kanan 1.00 0.05 0.50 0.28 0.28

Jumlah halaman ini 18.20


Jumlah s/d halaman ini 18.20

SISOBALAURU, 2021

DISETUJUI OLEH : DIVERIFIKASI OLEH : DIBUAT OLEH :


Pj. KEPALA DESA SEKRETARIS DESA TIM PELAKSANA KEGIATAN

WA'OZISOKHI WARUWU, S.Pd.SD SIASA NDRAHA OTONI NDRAHA


Ketua
TAKE OF SHEET (TOS)
PERHITUNGAN VOLUME
SNI. A.2.3.1.9. Pengurugan kembali 1 m3 galian tanah
PEK. TEMBOK PENAHAN TANAH 2 Tpt Sep. 36.40 M' & Tinggi 1.50 M' (Kanan = 18.20 M' + Kiri = 18.20 M')

DESA : SISOBALAURU
KECAMATAN : HILIDUHO
KABUPATEN / KOTA : NIAS
PROVINSI : SUMATERA UTARA
NO. RAB :
BIDANG : PEMBANGUNAN DESA
KEGIATAN : PEK. TEMBOK PENAHAN TANAH 2 Tpt Sep. 36.40 M' & Tinggi 1.50 M' (Kanan = 18.20 M' + Kiri = 18.20 M')

Sketsa

Pas. Batu Gunung


Camp. 1 : 4
Timbunan
tanah setempat
(dari sisa galian)

Plasteran Permukaan 25 50
yang tampak Camp. 1 : 3
& Acian

100

50 5 45 5

55
POT. TIPIKAL MELINTANG TEMBOK PENAHAN TANAH
SEP. 18,20 M' & TINGGI 1,50 M'

BIDANG PERSEGI BIDANG TRAPESIUM BIDANG SEGITIGA


LUAS LUAS RATA - PANJANG
LEBAR TINGGI LEBAR TINGGI RATA
No POSISI / LETAK SISI TINGGI TINGGI RATA LEBAR LEBAR RATA 1/2
(m) - RATA ( m ) (m) - RATA ( m ) ( m2 ) ( m2 ) (m)
(m) (m) (m) (m)
L T T1 T2 T L1 L2 L L T A A P
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17

0 + 000 Kiri 1.00 0.05 0.50 0.28 0.28


2 STA. 0.28 18.20
0 + 018.2 Kiri 1.00 0.05 0.50 0.28 0.28

Jumlah halaman ini 18.20


Jumlah s/d halaman ini 18.20

SISOBALAURU, 2021

DISETUJUI OLEH : DIVERIFIKASI OLEH : DIBUAT OLEH :


Pj. KEPALA DESA SEKRETARIS DESA TIM PELAKSANA KEGIATAN

WA'OZISOKHI WARUWU, S.Pd.SD SIASA NDRAHA OTONI NDRAHA


Ketua
JUMLAH KUANTITAS

(n) (m3)
18 19=(16x17x18)

1.00 5.01

5.01
5.01
JUMLAH KUANTITAS

(n) (m3)
18 19=(16x17x18)

1.00 5.01

5.01
5.01
REKAPITULASI RENCANA ANGGARAN BIAYA
PEKERJAAN KEGIATAN FISIK DANA DESA TA.2021
DESA : SISOBALAURU
KECAMATAN : HILIDUHO
KABUPATEN / KOTA : NIAS
PROVINSI : SUMATERA UTARA
NO. RAB :
BIDANG : PEMBANGUNAN DESA
KEGIATAN : PEK. BRONJONG PENAHAN 1 Tpt Sep. 14 M' & Tinggi 5.50 M'

URAIAN HARGA SATUAN JLH. HARGA


NO SAT. VOLUME
PEKERJAAN
Rp. Rp.
1 2 4 5 6 7
I PEK. BRONJONG PENAHAN 1 Tpt Sep. 14 M' & Tinggi 5.50 M'
A. Upah
- Pekerja HOK 129.00 100,000.00 12,900,000.00
Sub. Total Upah 12,900,000.00
B. Bahan
- Papan Bekisting,uk. 0.20 m x 0.02 m x 2.0 m Lbr 18.00 21,200.00 381,600.00
- Kayu segi/Broti, uk. 5 - 7 cm. Pjg. 3.00 M' Btg 36.00 27,900.00 1,004,400.00
- Kayu Bulat Ø 7 - 8 cm; 3,5 m Btg 42.00 8,400.00 352,800.00
- Paku Biasa Kg 2.00 20,000.00 40,000.00
- Geotextile Non Woven 250 gr/m2 (4mx100m) Roll 1.00 13,380,000.00 13,380,000.00
- Kawat Bronjong Pabrikasi Type - 1 Unit 50.00 376,900.00 18,845,000.00
- Kawat Bronjong Pabrikasi Type - 2 Unit 60.00 599,900.00 35,994,000.00
Sub. Total Bahan 69,997,800.00
C. Peralatan
- Meteran uk. 5.0 m Bh 1.00 30,200.00 30,200.00
- Meteran uk. 50.0 m Bh 1.00 63,600.00 63,600.00
- Gerobak Sorong Unit 4.00 605,500.00 2,422,000.00
- Sekop besar + gagang Bh 4.00 113,800.00 455,200.00
- Cangkul + gagang Bh 4.00 113,800.00 455,200.00
- Tembilang/penggali + gagang Bh 4.00 66,900.00 267,600.00
- Linggis Ulir Bh 4.00 39,100.00 156,400.00
- Pecok/Bolak baling + gagang Bh 5.00 139,400.00 697,000.00
- Sarung Tangan Pekerja (karet) Psg 9.00 14,800.00 133,200.00
- Selang Ukur Glg 1.00 16,800.00 16,800.00
- Palu/Penokok Bh 4.00 46,900.00 187,600.00
- Benang Tukang (Nilon) Glg 2.00 16,800.00 33,600.00
- Tang Kakak tua (pengikat kawat) Bh 4.00 42,925.00 171,700.00
- Unting unting Bh 2.00 22,300.00 44,600.00
- Plengki Rotan Bh 9.00 20,700.00 186,300.00
- Martil Batu Uk. 3 Kg (godam) Bh 4.00 222,200.00 888,800.00
Sub. Total Peralatan 6,209,800.00
D. Upah Angkut / Pikul Tenaga Manusia
- Batu Kali Belah 15/20 HOK 182.00 56,250.00 10,237,500.00
- Papan Bekisting,uk. 0.20 m x 0.02 m x 2.0 m HOK 18.00 900.00 16,200.00
- Kayu segi/Broti, uk. 5 - 7 cm. Pjg. 3.00 M' HOK 36.00 900.00 32,400.00
- Kayu Bulat Ø 7 cm - 8 cm HOK 42.00 1,350.00 56,700.00
Sub. Total Upah Angkut / Pikul Tenaga Manusia 10,342,800.00
E. Ongkos Angkut Truk
- Papan Bekisting,uk. 0.20 m x 0.02 m x 2.0 m Lbr 18.00 1,000.00 18,000.00
- Kayu segi/Broti, uk. 5 - 7 cm. Pjg. 3.00 M' Btg 36.00 1,300.00 46,800.00
- Kayu Bulat Ø 7 - 8 cm; 3,5 m Btg 42.00 1,700.00 71,400.00
- Geotextile Non Woven 250 gr/m2 (4mx100m) Roll 1.00 68,100.00 68,100.00
- Kawat Bronjong Pabrikasi Type - 1 Unit 50.00 9,400.00 470,000.00
URAIAN HARGA SATUAN JLH. HARGA
NO SAT. VOLUME
PEKERJAAN
Rp. Rp.
1 2 4 5 6 7
- Kawat Bronjong Pabrikasi Type - 2 Unit 60.00 14,200.00 852,000.00
Sub. Total Upah Angkut Truk 1,526,300.00
URAIAN HARGA SATUAN JLH. HARGA
NO SAT. VOLUME
PEKERJAAN
Rp. Rp.
1 2 4 5 6 7
F. Upah Mengumpulkan Tenaga Manusia
- Batu Kali Belah 15/20 HOK 182.00 150,000.00 27,300,000.00
Sub. Total Upah Mengumpulkan Tenaga Manusia 27,300,000.00
G. Upah Memecahkan Tenaga Manusia
- Batu Kali Belah 15/20 HOK 182.00 150,000.00 27,300,000.00
Sub. Total Upah Memecahkan Tenaga Manusia 27,300,000.00

JUMLAH TOTAL ( A + B + C + D + E + F + G ) Rp. 155,576,700.00

Terbilang : Seratus Lima Puluh Lima Juta Lima Ratus Tujuh Puluh Enam Ribu Tujuh Ratus Rupiah

SISOBALAURU, 2021

DISETUJUI OLEH : DIVERIFIKASI OLEH : DIBUAT OLEH :


Pj. KEPALA DESA SEKRETARIS DESA TIM PELAKSANA KEGIATAN

WA'OZISOKHI WARUWU, S.Pd.SD SIASA NDRAHA OTONI NDRAHA


Ketua
RINCIAN RENCANA ANGGARAN BIAYA
PEKERJAAN KEGIATAN FISIK DANA DESA TA.2021
DESA : SISOBALAURU
KECAMATAN : HILIDUHO
KABUPATEN / KOTA : NIAS
PROVINSI : SUMATERA UTARA
NO. RAB :
BIDANG : PEMBANGUNAN DESA
KEGIATAN : PEK. BRONJONG PENAHAN 1 Tpt Sep. 14 M' & Tinggi 5.50 M'

KODE
URAIAN HARGA SATUAN JLH. HARGA
NO ANALISA SAT. VOLUME
PEKERJAAN
PEKERJAAN Rp. Rp.
1 2 3 4 5 6 7
I PEK. BRONJONG PENAHAN 1 Tpt Sep. 14 M' & Tinggi 5.50 M'
1 Pek. Galian Tanah A.2.3.1.1.
A. Upah
- Pekerja HOK 48.00 100,000.00 4,800,000.00

B. Bahan
- Papan Bekisting,uk. 0.20 m x 0.02 m x 2.0 m Lbr 18.00 21,200.00 381,600.00
- Kayu segi/Broti, uk. 5 - 7 cm. Pjg. 3.00 M' Btg 36.00 27,900.00 1,004,400.00
- Paku Biasa Kg 2.00 20,000.00 40,000.00

C. Peralatan
- Meteran uk. 5.0 m Bh 1.00 30,200.00 30,200.00
- Meteran uk. 50.0 m Bh 1.00 63,600.00 63,600.00
- Gerobak Sorong Unit 4.00 605,500.00 2,422,000.00
- Sekop besar + gagang Bh 4.00 113,800.00 455,200.00
- Cangkul + gagang Bh 4.00 113,800.00 455,200.00
- Tembilang/penggali + gagang Bh 4.00 66,900.00 267,600.00
- Linggis Ulir Bh 4.00 39,100.00 156,400.00
- Pecok/Bolak baling + gagang Bh 5.00 139,400.00 697,000.00
- Sarung Tangan Pekerja (karet) Psg 9.00 14,800.00 133,200.00
- Selang Ukur Glg 1.00 16,800.00 16,800.00
- Palu/Penokok Bh 4.00 46,900.00 187,600.00
- Benang Tukang (Nilon) Glg 2.00 16,800.00 33,600.00
- Tang Kakak tua (pengikat kawat) Bh 4.00 42,925.00 171,700.00
- Unting unting Bh 2.00 22,300.00 44,600.00
- Plengki Rotan Bh 9.00 20,700.00 186,300.00
- Martil Batu Uk. 3 Kg (godam) Bh 4.00 222,200.00 888,800.00

D. Upah Angkut / Pikul Tenaga Manusia


- Papan Bekisting,uk. 0.20 m x 0.02 m x 2.0 m HOK 18.00 900.00 16,200.00
- Kayu segi/Broti, uk. 5 - 7 cm. Pjg. 3.00 M' HOK 36.00 900.00 32,400.00

E. Ongkos Angkut Truk


- Papan Bekisting,uk. 0.20 m x 0.02 m x 2.0 m Lbr 18.00 1,000.00 18,000.00
- Kayu segi/Broti, uk. 5 - 7 cm. Pjg. 3.00 M' Btg 36.00 1,300.00 46,800.00

Sub. Total.1 12,549,200.00


2 Pek. Pemasangan Cerucuk Kayu Bulat (Ø 7cm - 8cm) P.07.b
A. Upah
- Pekerja HOK 18.00 100,000.00 1,800,000.00

B. Bahan
- Kayu Bulat Ø 7 cm - 8 cm Btg 42.00 8,400.00 352,800.00

C. Peralatan - - - -

D. Upah Angkut / Pikul Tenaga Manusia


- Kayu Bulat Ø 7 cm - 8 cm HOK 42.00 1,350.00 56,700.00

E. Ongkos Angkut Truk


KODE
URAIAN HARGA SATUAN JLH. HARGA
NO ANALISA SAT. VOLUME
PEKERJAAN
PEKERJAAN Rp. Rp.
1 2 3 4 5 6 7
- Kayu Bulat Ø 7 cm - 8 cm Btg 42.00 1,700.00 71,400.00

Sub. Total.2 2,280,900.00


KODE
URAIAN HARGA SATUAN JLH. HARGA
NO ANALISA SAT. VOLUME
PEKERJAAN
PEKERJAAN Rp. Rp.
1 2 3 4 5 6 7
3 Pek. Pemasangan Geotekstil Type A (Non Woven) P.09.a.1
A. Upah
- Pekerja HOK 12.00 100,000.00 1,200,000.00

B. Bahan
- Geotextile Non Woven 250 gr/m2 (4mx100m) Roll 1.00 13,380,000.00 13,380,000.00

C. Peralatan - - - -

D. Upah Angkut / Pikul Tenaga Manusia - - - -

E. Ongkos Angkut Truk


- Geotextile Non Woven 250 gr/m2 (4mx100m) Roll 1.00 68,100.00 68,100.00

Sub. Total.3 14,648,100.00


4 Pek. Pasangan Bronjong Type I P.06.b.4.(1)
A. Upah
- Pekerja HOK 15.00 100,000.00 1,500,000.00

B. Bahan
- Kawat Bronjong Pabrikasi Type - 1 Unit 50.00 376,900.00 18,845,000.00

C. Peralatan - - - -

D. Upah Angkut / Pikul Tenaga Manusia


- Batu Kali Belah 15/20 HOK 65.00 56,250.00 3,656,250.00

E. Ongkos Angkut Truk


- Kawat Bronjong Pabrikasi Type - 1 Unit 50.00 9,400.00 470,000.00

F. Upah Mengumpulkan Tenaga Manusia


- Batu Kali Belah 15/20 HOK 65.00 150,000.00 9,750,000.00

G. Upah Memecah Tenaga Manusia


- Batu Kali Belah 15/20 HOK 65.00 150,000.00 9,750,000.00

Sub. Total.4 43,971,250.00


5 Pek. Pasangan Bronjong Type II P.06.b.4.(2)
A. Upah
- Pekerja HOK 27.00 100,000.00 2,700,000.00

B. Bahan
- Kawat Bronjong Pabrikasi Type - 2 Unit 60.00 599,900.00 35,994,000.00

C. Peralatan - - - -

D. Upah Angkut / Pikul Tenaga Manusia


- Batu Kali Belah 15/20 HOK 117.00 56,250.00 6,581,250.00

E. Ongkos Angkut Truk


- Kawat Bronjong Pabrikasi Type - 2 Unit 60.00 14,200.00 852,000.00

F. Upah Mengumpulkan Tenaga Manusia


- Batu Kali Belah 15/20 HOK 117.00 150,000.00 17,550,000.00

G. Upah Memecah Tenaga Manusia


- Batu Kali Belah 15/20 HOK 117.00 150,000.00 17,550,000.00

Sub. Total.5 81,227,250.00


KODE
URAIAN HARGA SATUAN JLH. HARGA
NO ANALISA SAT. VOLUME
PEKERJAAN
PEKERJAAN Rp. Rp.
1 2 3 4 5 6 7
6 Pek. Pengurugan Kembali ( dari Bekas Galian ) A.2.3.1.9.
A. Upah
- Pekerja HOK 9.00 100,000.00 900,000.00

B. Bahan - - - -

C. Peralatan - - - -

D. Upah Angkut / Pikul Tenaga Manusia - - - -

E. Ongkos Angkut Truk - - - -

Sub. Total.6 900,000.00

JUMLAH TOTAL ( 1 + 2 + 3 + 4 + 5 + 6 ) Rp. 155,576,700.00

Terbilang : Seratus Lima Puluh Lima Juta Lima Ratus Tujuh Puluh Enam Ribu Tujuh Ratus Rupiah

SISOBALAURU, 2021

DISETUJUI OLEH : DIVERIFIKASI OLEH : DIBUAT OLEH :


Pj. KEPALA DESA SEKRETARIS DESA TIM PELAKSANA KEGIATAN

WA'OZISOKHI WARUWU, S.Pd.SD SIASA NDRAHA OTONI NDRAHA


Ketua
RINCIAN ANALISA SATUAN PEKERJAAN
PEKERJAAN KEGIATAN FISIK DANA DESA TA.2021
(Ref. ANALISA SNI Thn.2016 - PERMEN PUPR No. 28/PRT/M/2016)
DESA : SISOBALAURU
KECAMATAN : HILIDUHO
KABUPATEN / KOTA : NIAS
PROVINSI : SUMATERA UTARA
NO. RAB :
BIDANG : PEMBANGUNAN DESA
KEGIATAN : PEK. BRONJONG PENAHAN 1 Tpt Sep. 14 M' & Tinggi 5.50VOLUME
M'

KODE URAIAN KEBUTUHAN TERHADAP ANALISA SATUAN PEKERJAAN


URAIAN
NO ANALISA SAT.
PEKERJAAN
PEKERJAAN ANALISA SATUAN PEKERJAAN SATUAN KOEFISIEN VOLUME
1 2 3 4 5 6 7 8 9 = (5 * 8)
TOS
1 Pek. Galian Tanah A.2.3.1.1. m3 63.00 Penggalian 1 m3 tanah biasa sedalam 1 m'
Tenaga Kerja Pekerja OH 0.750 47.250
Bahan
Peralatan
2 Pek. Pemasangan Cerucuk Kayu Bulat (Ø 7cm - 8cm) P.07.b m' 147.00 Pemasangan Cerucuk Kayu Bulat (Ø 7cm - 8cm) 1 m'
Tenaga Kerja Pekerja OH 0.120 17.640
Bahan (Dihitung di lembar RAB)
Peralatan
3 Pek. Pemasangan Geotekstil Type A (Non Woven) P.09.a.1 m2 112.00 Pemasangan Geotekstil Type A (250 gr/m2) (Non Woven) 1 m2
Tenaga Kerja Pekerja OH 0.100 11.200
Bahan (Dihitung di lembar RAB)
Peralatan
4 Pek. Pasangan Bronjong Type I P.06.b.4.(1) Unit 50.00 Pasangan bronjong pabrikasi Type - 1 uk. (2,0 mm x 1,0 mm x 0,5 mm)
Tenaga Kerja Pekerja (isi batu dan pasang) OH 0.300 15.000
Batu Kali Belah 15/20 M3 1.300 65.000
Bahan
Kawat Bronjong Pabrikasi Type - 1 Unit 1.000 50.000
Peralatan
5 Pek. Pasangan Bronjong Type II P.06.b.4.(2) Unit 60.00 Pasangan bronjong pabrikasi Type - 2 uk. (3,0 mm x 1,0 mm x 0,5 mm)
Tenaga Kerja Pekerja (isi batu dan pasang) OH 0.450 27.000
Batu Kali Belah 15/20 M3 1.950 117.000
Bahan
Kawat Bronjong Pabrikasi Type - 2 Unit 1.000 60.000
Peralatan
VOLUME
KODE URAIAN KEBUTUHAN TERHADAP ANALISA SATUAN PEKERJAAN
URAIAN
NO ANALISA SAT.
PEKERJAAN
PEKERJAAN ANALISA SATUAN PEKERJAAN SATUAN KOEFISIEN VOLUME
1 2 3 4 5 6 7 8 9 = (5 * 8)
TOS
6 Pek. Pengurugan Kembali ( dari Bekas Galian ) A.2.3.1.9. m3 16.70 Pengurugan kembali 1 m3 galian tanah
Tenaga Kerja Pekerja OH 0.500 8.350
Bahan
Peralatan

SISOBALAURU, 2021

DISETUJUI OLEH : DIVERIFIKASI OLEH : DIBUAT OLEH :


Pj. KEPALA DESA SEKRETARIS DESA TIM PELAKSANA KEGIATAN

WA'OZISOKHI WARUWU, S.Pd.SD SIASA NDRAHA OTONI NDRAHA


Ketua
DIBULATKAN
10

48.000

18.000

12.000

15.000
65.000
50.000

27.000
117.000
60.000
DIBULATKAN
10

9.000
TAKE OF SHEET (TOS)
PERHITUNGAN VOLUME
SNI. A.2.3.1.1. Penggalian 1 m3 tanah biasa sedalam 1 m
PEK. BRONJONG PENAHAN 1 Tpt Sep. 14 M' & Tinggi 5.50 M'

DESA : SISOBALAURU
KECAMATAN : HILIDUHO
KABUPATEN / KOTA : NIAS
PROVINSI : SUMATERA UTARA
NO. RAB :
BIDANG : PEMBANGUNAN DESA
KEGIATAN : PEK. BRONJONG PENAHAN 1 Tpt Sep. 14 M' & Tinggi 5.50 M'

Sketsa

100 50
100 50 50 50 TYP E 1 X 1 TYP E 1 X 1 TYP E 2 X 1 TYP E 1 X 1 TYP E 2 X 1 TYP E 1 X 1 LAYER 11
Geotextile Non Woven 100 50 50 50 TYP E 2 X 1 TYP E 1 X 1 TYP E 2 X 1 TYP E 2 X 1 TYP E 2 X 1 LAYER 10
250 gr/m2
100 50 50 50 TYP E 1 X 1 TYP E 1 X 1 TYP E 2 X 1 TYP E 1 X 1 TYP E 2 X 1 TYP E 1 X 1 LAYER 9
Timbunan Tanah 100 50 50 50 TYP E 2 X 1 TYP E 1 X 1 TYP E 2 X 1 TYP E 2 X 1 TYP E 2 X 1 LAYER 8
(dari Sisa Galian) 400 400
100 50 50 50 TYP E 1 X 1 TYP E 1 X 1 TYP E 2 X 1 TYP E 1 X 1 TYP E 2 X 1 TYP E 1 X 1 LAYER 7
Pasangan Bronjong
dengan Kawat Pabrikasi 100 50 50 50 TYP E 2 X 1 TYP E 1 X 1 TYP E 2 X 1 TYP E 2 X 1 TYP E 2 X 1 LAYER 6
100 100 TYP E TYP E TYP E TYP E TYP E
50 50 50 1 X1 1 X1 1 X1 1 X1 TYP E 2 X 1 TYP E 2 X 1 TYP E 2 X 1 1 X1
LAYER 5
100 100 100 MTA 50 50 TYP E 2 X 1 TYP E 1 X 1 TYP E 2 X 1 TYP E 2 X 1 TYP E 2 X 1 LAYER 4
100 100 100 50 50 TYP E 1 X 1 TYP E 1 X 1 TYP E 2 X 1 TYP E 1 X 1 TYP E 2 X 1 TYP E 1 X 1 LAYER 3
Galian Pondasi 100 100 100 50 150 150 50 TYP E 2 X 1 TYP E 1 X 1 TYP E 2 X 1 TYP E 2 X 1 TYP E 2 X 1 LAYER 2
100 100 100 50 50 TYP E 1 X 1 TYP E 1 X 1 TYP E 2 X 1 TYP E 1 X 1 TYP E 2 X 1 TYP E 1 X 1 LAYER 1

50 300
Cerucuk Kayu Bulat
Ø 7cm - 8cm
350 350

100 100 100 100 100 100 100 100 100 100 100 100 100 100 100

Tampak Samping Bronjong Tampak Depan Bronjong


Skala 1:100 Skala 1:100

BIDANG PERSEGI BIDANG TRAPESIUM BIDANG SEGITIGA


LUAS LUAS RATA - PANJANG
LEBAR TINGGI LEBAR TINGGI RATA
No POSISI / LETAK SISI TINGGI TINGGI RATA LEBAR LEBAR RATA 1/2
(m) - RATA ( m ) (m) - RATA ( m ) ( m2 ) ( m2 ) (m)
(m) (m) (m) (m)
L T T1 T2 T L1 L2 L L T A A P
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17

0 + 000 Kanan 3.00 1.50 4.50


1 STA. 4.50 14.00
0 + 014 Kanan 3.00 1.50 4.50

Jumlah halaman ini 14.00


Jumlah s/d halaman ini 14.00

SISOBALAURU, 2021

DISETUJUI OLEH : DIVERIFIKASI OLEH : DIBUAT OLEH :


Pj. KEPALA DESA SEKRETARIS DESA TIM PELAKSANA KEGIATAN

WA'OZISOKHI WARUWU, S.Pd.SD SIASA NDRAHA OTONI NDRAHA


Ketua
JUMLAH KUANTITAS

(n) (m3)
18 19=(16x17x18)

1.00 63.00

63.00
63.00

2021
TAKE OF SHEET (TOS)
PERHITUNGAN VOLUME
SNI. P.07.b Pemasangan Cerucuk Kayu Bulat (Ø 7cm - 8cm) 1 m
PEK. BRONJONG PENAHAN 1 Tpt Sep. 14 M' & Tinggi 5.50 M'

DESA : SISOBALAURU
KECAMATAN : HILIDUHO
KABUPATEN / KOTA : NIAS
PROVINSI : SUMATERA UTARA
NO. RAB :
BIDANG : PEMBANGUNAN DESA
KEGIATAN : PEK. BRONJONG PENAHAN 1 Tpt Sep. 14 M' & Tinggi 5.50 M'

Sketsa

100 50
100 50 50 50 TYPE 1 X 1 TYPE 1 X 1 TYPE 2 X 1 TYPE 1 X 1 TYPE 2 X 1 TYPE 1 X 1 LAYER 11
Geotextile Non Woven 100 50 50 50 TYPE 2 X 1 TYPE 1 X 1 TYPE 2 X 1 TYPE 2 X 1 TYPE 2 X 1 LAYER 10
250 gr/m2
100 50 50 50 TYPE 1 X 1 TYPE 1 X 1 TYPE 2 X 1 TYPE 1 X 1 TYPE 2 X 1 TYPE 1 X 1 LAYER 9
Timbunan Tanah 100 50 50 50 TYPE 2 X 1 TYPE 1 X 1 TYPE 2 X 1 TYPE 2 X 1 TYPE 2 X 1 LAYER 8
(dari Sisa Galian) 400 400
100 50 50 50 TYPE 1 X 1 TYPE 1 X 1 TYPE 2 X 1 TYPE 1 X 1 TYPE 2 X 1 TYPE 1 X 1 LAYER 7
Pasangan Bronjong
dengan Kawat Pabrikasi 100 50 50 50 TYPE 2 X 1 TYPE 1 X 1 TYPE 2 X 1 TYPE 2 X 1 TYPE 2 X 1 LAYER 6
100 100 TYPE TYPE TYPE TYPE TYPE
50 50 50 1 X1 1 X1 1 X1 1 X1 TYPE 2 X 1 TYPE 2 X 1 TYPE 2 X 1 1 X1
LAYER 5
100 100 100 MTA 50 50 TYPE 2 X 1 TYPE 1 X 1 TYPE 2 X 1 TYPE 2 X 1 TYPE 2 X 1 LAYER 4
100 100 100 50 50 TYPE 1 X 1 TYPE 1 X 1 TYPE 2 X 1 TYPE 1 X 1 TYPE 2 X 1 TYPE 1 X 1 LAYER 3
Galian Pondasi 100 100 100 50 150 150 50 TYPE 2 X 1 TYPE 1 X 1 TYPE 2 X 1 TYPE 2 X 1 TYPE 2 X 1 LAYER 2
100 100 100 50 50 TYPE 1 X 1 TYPE 1 X 1 TYPE 2 X 1 TYPE 1 X 1 TYPE 2 X 1 TYPE 1 X 1 LAYER 1

50 300
Cerucuk Kayu Bulat
Ø 7cm - 8cm
350 350

100 100 100 100 100 100 100 100 100 100 100 100 100 100 100

Tampak Samping Bronjong Tampak Depan Bronjong


Skala 1:100 Skala 1:100

JUMLAH JUMLAH JUMLAH


ARAH SISI ARAH SISI TOTAL PANJANG @
VOLUME
PANJANG LEBAR BTG KUANTITAS
NO. STATION / LETAK SISI
( Btg )
( M' )
( ( Btg ) ( M' )
Btg ) ( Btg ) n V
1 2 3 4 5 6=(4x5) 7=6 8 9=(7x8)
1 LAPIS - 1 Kanan 14.00 3.00 42.00 42.00 3.50 147.00

Jumlah halaman ini 42.00 147.00


Jumlah s/d halaman ini 42.00 147.00

SISOBALAURU, 2021

DISETUJUI OLEH : DIVERIFIKASI OLEH : DIBUAT OLEH :


Pj. KEPALA DESA SEKRETARIS DESA TIM PELAKSANA KEGIATAN
TAKE OF SHEET (TOS)
PERHITUNGAN VOLUME
SNI. P.07.b Pemasangan Cerucuk Kayu Bulat (Ø 7cm - 8cm) 1 m
PEK. BRONJONG PENAHAN 1 Tpt Sep. 14 M' & Tinggi 5.50 M'

DESA : SISOBALAURU
KECAMATAN : HILIDUHO
KABUPATEN / KOTA : NIAS
PROVINSI : SUMATERA UTARA
NO. RAB :
BIDANG : PEMBANGUNAN DESA
KEGIATAN : PEK. BRONJONG PENAHAN 1 Tpt Sep. 14 M' & Tinggi 5.50 M'

WA'OZISOKHI WARUWU, S.Pd.SD SIASA NDRAHA OTONI NDRAHA


Ketua
TAKE OF SHEET (TOS)
PERHITUNGAN VOLUME
SNI. P.09.a.1 Pemasangan Geotekstil Type A (250 gr/m2) (Non Woven) 1 m2
PEK. BRONJONG PENAHAN 1 Tpt Sep. 14 M' & Tinggi 5.50 M'

DESA : SISOBALAURU
KECAMATAN : HILIDUHO
KABUPATEN / KOTA : NIAS
PROVINSI : SUMATERA UTARA
NO. RAB :
BIDANG : PEMBANGUNAN DESA
KEGIATAN : PEK. BRONJONG PENAHAN 1 Tpt Sep. 14 M' & Tinggi 5.50 M'

Sketsa

100 50
100 50 50 50 TYPE 1 X 1 TYPE 1 X 1 TYPE 2 X 1 TYPE 1 X 1 TYPE 2 X 1 TYPE 1 X 1 LAYER 11
Geotextile Non Woven 100 50 50 50 TYPE 2 X 1 TYPE 1 X 1 TYPE 2 X 1 TYPE 2 X 1 TYPE 2 X 1 LAYER 10
250 gr/m2
100 50 50 50 TYPE 1 X 1 TYPE 1 X 1 TYPE 2 X 1 TYPE 1 X 1 TYPE 2 X 1 TYPE 1 X 1 LAYER 9
Timbunan Tanah 100 50 50 50 TYPE 2 X 1 TYPE 1 X 1 TYPE 2 X 1 TYPE 2 X 1 TYPE 2 X 1 LAYER 8
(dari Sisa Galian) 400 400
100 50 50 50 TYPE 1 X 1 TYPE 1 X 1 TYPE 2 X 1 TYPE 1 X 1 TYPE 2 X 1 TYPE 1 X 1 LAYER 7
Pasangan Bronjong
dengan Kawat Pabrikasi 100 50 50 50 TYPE 2 X 1 TYPE 1 X 1 TYPE 2 X 1 TYPE 2 X 1 TYPE 2 X 1 LAYER 6
100 100 TYPE TYPE TYPE TYPE TYPE
50 50 50 1 X1 1 X1 1 X1 1 X1 TYPE 2 X 1 TYPE 2 X 1 TYPE 2 X 1 1 X1
LAYER 5
100 100 100 MTA 50 50 TYPE 2 X 1 TYPE 1 X 1 TYPE 2 X 1 TYPE 2 X 1 TYPE 2 X 1 LAYER 4
100 100 100 50 50 TYPE 1 X 1 TYPE 1 X 1 TYPE 2 X 1 TYPE 1 X 1 TYPE 2 X 1 TYPE 1 X 1 LAYER 3
Galian Pondasi 100 100 100 50 150 150 50 TYPE 2 X 1 TYPE 1 X 1 TYPE 2 X 1 TYPE 2 X 1 TYPE 2 X 1 LAYER 2
100 100 100 50 50 TYPE 1 X 1 TYPE 1 X 1 TYPE 2 X 1 TYPE 1 X 1 TYPE 2 X 1 TYPE 1 X 1 LAYER 1

50 300
Cerucuk Kayu Bulat
Ø 7cm - 8cm
350 350

100 100 100 100 100 100 100 100 100 100 100 100 100 100 100

Tampak Samping Bronjong Tampak Depan Bronjong


Skala 1:100 Skala 1:100

LEBAR PANJANG LUAS


VOLUME KUANTITAS
TERPASAN VOLUME
NO. STATION / LETAK SISI G (M2) PEMBELIAN
( M' ( (ROLL)
) M' ) ( M2 ) ( M2 )
L P A V
1 2 3 4 5 6=(4x5) 7=6 8=7 9
1 LAPIS - 5 Kanan 1.00 14.00 14.00 14.00 14.00
2 LAPIS - 6 Kanan 0.50 14.00 7.00 7.00 7.00
3 LAPIS - 7 Kanan 1.00 14.00 14.00 14.00 14.00 PERSYAR
ATAN
4 LAPIS - 8 Kanan 1.00 14.00 14.00 14.00 14.00 PEMBELI
5 LAPIS - 9 Kanan 0.50 14.00 7.00 7.00 7.00 AN
6 LAPIS - 9 Kanan 1.00 14.00 14.00 14.00 14.00 SETIAP 1
ROLL
7 LAPIS - 10 Kanan 1.00 14.00 14.00 14.00 14.00 (400
8 LAPIS - 11 Kanan 2.00 14.00 28.00 28.00 28.00 M2)

Jumlah halaman ini 112.00 112.00


Jumlah s/d halaman ini 112.00 112.00

SISOBALAURU, 2021

DISETUJUI OLEH : DIVERIFIKASI OLEH : DIBUAT OLEH :


Pj. KEPALA DESA SEKRETARIS DESA TIM PELAKSANA KEGIATAN
TAKE OF SHEET (TOS)
PERHITUNGAN VOLUME
SNI. P.09.a.1 Pemasangan Geotekstil Type A (250 gr/m2) (Non Woven) 1 m2
PEK. BRONJONG PENAHAN 1 Tpt Sep. 14 M' & Tinggi 5.50 M'

DESA : SISOBALAURU
KECAMATAN : HILIDUHO
KABUPATEN / KOTA : NIAS
PROVINSI : SUMATERA UTARA
NO. RAB :
BIDANG : PEMBANGUNAN DESA
KEGIATAN : PEK. BRONJONG PENAHAN 1 Tpt Sep. 14 M' & Tinggi 5.50 M'

WA'OZISOKHI WARUWU, S.Pd.SD SIASA NDRAHA OTONI NDRAHA


Ketua
TAKE OF SHEET (TOS)
PERHITUNGAN VOLUME
SNI. P.06.b.4.(1) Pasangan bronjong pabrikasi Type - 1 uk. (2,0 mm x 1,0 mm x 0,5 mm)
PEK. BRONJONG PENAHAN 1 Tpt Sep. 14 M' & Tinggi 5.50 M'

DESA : SISOBALAURU
KECAMATAN : HILIDUHO
KABUPATEN / KOTA : NIAS
PROVINSI : SUMATERA UTARA
NO. RAB :
BIDANG : PEMBANGUNAN DESA
KEGIATAN : PEK. BRONJONG PENAHAN 1 Tpt Sep. 14 M' & Tinggi 5.50 M'

Sketsa

TYPE 1 X 1 TYPE 1 X 1 TYPE 2 X 1 TYPE 1 X 1 TYPE 2 X 1 TYPE 1 X 1 LAYER 11

TYPE 2 X 1 TYPE 1 X 1 TYPE 2 X 1 TYPE 2 X 1 TYPE 2 X 1 LAYER 10

50 TYPE 1 X 1 TYPE 1 X 1 TYPE 2 X 1 TYPE 1 X 1 TYPE 2 X 1 TYPE 1 X 1 LAYER 11 TYPE 1 X 1 TYPE 1 X 1 TYPE 2 X 1 TYPE 1 X 1 TYPE 2 X 1 TYPE 1 X 1 LAYER 9

50 TYPE 2 X 1 TYPE 1 X 1 TYPE 2 X 1 TYPE 2 X 1 TYPE 2 X 1 LAYER 10


TYPE 2 X 1 TYPE 1 X 1 TYPE 2 X 1 TYPE 2 X 1 TYPE 2 X 1 LAYER 8
50 TYPE 1 X 1 TYPE 1 X 1 TYPE 2 X 1 TYPE 1 X 1 TYPE 2 X 1 TYPE 1 X 1 LAYER 9
50 TYPE 2 X 1 TYPE 1 X 1 TYPE 2 X 1 TYPE 2 X 1 TYPE 2 X 1 LAYER 8 TYPE 1 X 1 TYPE 1 X 1 TYPE 2 X 1 TYPE 1 X 1 TYPE 2 X 1 TYPE 1 X 1 LAYER 7
400
50 TYPE 1 X 1 TYPE 1 X 1 TYPE 2 X 1 TYPE 1 X 1 TYPE 2 X 1 TYPE 1 X 1 LAYER 7
TYPE 2 X 1 TYPE 1 X 1 TYPE 2 X 1 TYPE 2 X 1 TYPE 2 X 1 LAYER 6
50 TYPE 2 X 1 TYPE 1 X 1 TYPE 2 X 1 TYPE 2 X 1 TYPE 2 X 1 LAYER 6
TYPE TYPE TYPE TYPE TYPE
50 1 X1 1 X1 1 X1 1 X1 TYPE 2 X 1 TYPE 2 X 1 TYPE 2 X 1 1 X1
LAYER 5

TYPE 1 X 1
TYPE 1 X 1
TYPE 1 X 1
TYPE 1 X 1

TYPE 1 X 1
TYPE 2 X 1 TYPE 2 X 1 TYPE 2 X 1
50 TYPE 2 X 1 TYPE 1 X 1 TYPE 2 X 1 TYPE 2 X 1 TYPE 2 X 1 LAYER 4 LAYER 5
TYPE 2 X 1 TYPE 2 X 1 TYPE 2 X 1
50 TYPE 1 X 1 TYPE 1 X 1 TYPE 2 X 1 TYPE 1 X 1 TYPE 2 X 1 TYPE 1 X 1 LAYER 3
150 50 TYPE 2 X 1 TYPE 1 X 1 TYPE 2 X 1 TYPE 2 X 1 TYPE 2 X 1 LAYER 2 TYPE 2 X 1 TYPE 1 X 1 TYPE 2 X 1 TYPE 2 X 1 TYPE 2 X 1
50 TYPE 1 X 1 TYPE 1 X 1 TYPE 2 X 1 TYPE 1 X 1 TYPE 2 X 1 TYPE 1 X 1 LAYER 1 TYPE 1 X 1 TYPE 1 X 1 TYPE 2 X 1 TYPE 1 X 1 TYPE 2 X 1 TYPE 1 X 1 LAYER 4

TYPE 2 X 1 TYPE 1 X 1 TYPE 2 X 1 TYPE 2 X 1 TYPE 2 X 1

350 TYPE 1 X 1 TYPE 1 X 1 TYPE 2 X 1 TYPE 1 X 1 TYPE 2 X 1 TYPE 1 X 1

TYPE 2 X 1 TYPE 1 X 1 TYPE 2 X 1 TYPE 2 X 1 TYPE 2 X 1 LAYER 3


100 100 100 100 100 100 100 100 100 100 100 100 100
TYPE 1 X 1 TYPE 1 X 1 TYPE 2 X 1 TYPE 1 X 1 TYPE 2 X 1 TYPE 1 X 1

TYPE 2 X 1 TYPE 1 X 1 TYPE 2 X 1 TYPE 2 X 1 TYPE 2 X 1

Tampak Depan Bronjong TYPE 1 X 1 TYPE 1 X 1 TYPE 2 X 1 TYPE 1 X 1 TYPE 2 X 1 TYPE 1 X 1 LAYER 2

Skala 1:100 TYPE 2 X 1 TYPE 1 X 1 TYPE 2 X 1 TYPE 2 X 1 TYPE 2 X 1

TYPE 1 X 1 TYPE 1 X 1 TYPE 2 X 1 TYPE 1 X 1 TYPE 2 X 1 TYPE 1 X 1

TYPE 2 X 1 TYPE 1 X 1 TYPE 2 X 1 TYPE 2 X 1 TYPE 2 X 1 LAYER 1

TYPE 1 X 1 TYPE 1 X 1 TYPE 2 X 1 TYPE 1 X 1 TYPE 2 X 1 TYPE 1 X 1

Tampak Atas Lapisan Bronjong


Skala 1:100

PANJANG LEBAR TINGGI

VOLUME KUANTITAS
JUMLAH
NO. STATION / LETAK SISI (M3)
P ( L (m T n V
m4 ) ) (m ) ( UNIT )
1 2 3 5 6 7 8=(4x5x6x7) 9=7
1 LAPIS - 1 Kanan 2.00 1.00 0.50 9.00 9.00 9.00
2 LAPIS - 2 Kanan 2.00 1.00 0.50 6.00 6.00 6.00
3 LAPIS - 3 Kanan 2.00 1.00 0.50 9.00 9.00 9.00
4 LAPIS - 4 Kanan 2.00 1.00 0.50 6.00 6.00 6.00
5 LAPIS - 5 Kanan 2.00 1.00 0.50 5.00 5.00 5.00
6 LAPIS - 6 Kanan 2.00 1.00 0.50 1.00 1.00 1.00
7 LAPIS - 7 Kanan 2.00 1.00 0.50 4.00 4.00 4.00
8 LAPIS - 8 Kanan 2.00 1.00 0.50 1.00 1.00 1.00
9 LAPIS - 9 Kanan 2.00 1.00 0.50 4.00 4.00 4.00
10 LAPIS - 10 Kanan 2.00 1.00 0.50 1.00 1.00 1.00
Jumlah halaman ini 46.00 46.00
Jumlah s/d halaman ini

SISOBALAURU, 2021

DISETUJUI OLEH : DIVERIFIKASI OLEH : DIBUAT OLEH :


Pj. KEPALA DESA SEKRETARIS DESA TIM PELAKSANA KEGIATAN
TAKE OF SHEET (TOS)
PERHITUNGAN VOLUME
SNI. P.06.b.4.(1) Pasangan bronjong pabrikasi Type - 1 uk. (2,0 mm x 1,0 mm x 0,5 mm)
PEK. BRONJONG PENAHAN 1 Tpt Sep. 14 M' & Tinggi 5.50 M'

DESA : SISOBALAURU
KECAMATAN : HILIDUHO
KABUPATEN / KOTA : NIAS
PROVINSI : SUMATERA UTARA
NO. RAB :
BIDANG : PEMBANGUNAN DESA
KEGIATAN : PEK. BRONJONG PENAHAN 1 Tpt Sep. 14 M' & Tinggi 5.50 M'

WA'OZISOKHI WARUWU, S.Pd.SD SIASA NDRAHA OTONI NDRAHA


Ketua
Sketsa

TYPE 1 X 1 TYPE 1 X 1 TYPE 2 X 1 TYPE 1 X 1 TYPE 2 X 1 TYPE 1 X 1 LAYER 11

TYPE 2 X 1 TYPE 1 X 1 TYPE 2 X 1 TYPE 2 X 1 TYPE 2 X 1 LAYER 10

50 TYPE 1 X 1 TYPE 1 X 1 TYPE 2 X 1 TYPE 1 X 1 TYPE 2 X 1 TYPE 1 X 1 LAYER 11 TYPE 1 X 1 TYPE 1 X 1 TYPE 2 X 1 TYPE 1 X 1 TYPE 2 X 1 TYPE 1 X 1 LAYER 9

50 TYPE 2 X 1 TYPE 1 X 1 TYPE 2 X 1 TYPE 2 X 1 TYPE 2 X 1 LAYER 10


TYPE 2 X 1 TYPE 1 X 1 TYPE 2 X 1 TYPE 2 X 1 TYPE 2 X 1 LAYER 8
50 TYPE 1 X 1 TYPE 1 X 1 TYPE 2 X 1 TYPE 1 X 1 TYPE 2 X 1 TYPE 1 X 1 LAYER 9
50 TYPE 2 X 1 TYPE 1 X 1 TYPE 2 X 1 TYPE 2 X 1 TYPE 2 X 1 LAYER 8 TYPE 1 X 1 TYPE 1 X 1 TYPE 2 X 1 TYPE 1 X 1 TYPE 2 X 1 TYPE 1 X 1 LAYER 7
400
50 TYPE 1 X 1 TYPE 1 X 1 TYPE 2 X 1 TYPE 1 X 1 TYPE 2 X 1 TYPE 1 X 1 LAYER 7
TYPE 2 X 1 TYPE 1 X 1 TYPE 2 X 1 TYPE 2 X 1 TYPE 2 X 1 LAYER 6
50 TYPE 2 X 1 TYPE 1 X 1 TYPE 2 X 1 TYPE 2 X 1 TYPE 2 X 1 LAYER 6
TYPE TYPE TYPE TYPE TYPE
50 1 X1 1 X1 1 X1 1 X1 TYPE 2 X 1 TYPE 2 X 1 TYPE 2 X 1 1 X1
LAYER 5

TYPE 1 X 1
TYPE 1 X 1
TYPE 1 X 1
TYPE 1 X 1

TYPE 1 X 1
TYPE 2 X 1 TYPE 2 X 1 TYPE 2 X 1
50 TYPE 2 X 1 TYPE 1 X 1 TYPE 2 X 1 TYPE 2 X 1 TYPE 2 X 1 LAYER 4 LAYER 5
TYPE 2 X 1 TYPE 2 X 1 TYPE 2 X 1
50 TYPE 1 X 1 TYPE 1 X 1 TYPE 2 X 1 TYPE 1 X 1 TYPE 2 X 1 TYPE 1 X 1 LAYER 3
150 50 TYPE 2 X 1 TYPE 1 X 1 TYPE 2 X 1 TYPE 2 X 1 TYPE 2 X 1 LAYER 2 TYPE 2 X 1 TYPE 1 X 1 TYPE 2 X 1 TYPE 2 X 1 TYPE 2 X 1
50 TYPE 1 X 1 TYPE 1 X 1 TYPE 2 X 1 TYPE 1 X 1 TYPE 2 X 1 TYPE 1 X 1 LAYER 1 TYPE 1 X 1 TYPE 1 X 1 TYPE 2 X 1 TYPE 1 X 1 TYPE 2 X 1 TYPE 1 X 1 LAYER 4

TYPE 2 X 1 TYPE 1 X 1 TYPE 2 X 1 TYPE 2 X 1 TYPE 2 X 1

350 TYPE 1 X 1 TYPE 1 X 1 TYPE 2 X 1 TYPE 1 X 1 TYPE 2 X 1 TYPE 1 X 1

TYPE 2 X 1 TYPE 1 X 1 TYPE 2 X 1 TYPE 2 X 1 TYPE 2 X 1 LAYER 3


100 100 100 100 100 100 100 100 100 100 100 100 100
TYPE 1 X 1 TYPE 1 X 1 TYPE 2 X 1 TYPE 1 X 1 TYPE 2 X 1 TYPE 1 X 1

TYPE 2 X 1 TYPE 1 X 1 TYPE 2 X 1 TYPE 2 X 1 TYPE 2 X 1

Tampak Depan Bronjong TYPE 1 X 1 TYPE 1 X 1 TYPE 2 X 1 TYPE 1 X 1 TYPE 2 X 1 TYPE 1 X 1 LAYER 2

Skala 1:100 TYPE 2 X 1 TYPE 1 X 1 TYPE 2 X 1 TYPE 2 X 1 TYPE 2 X 1

TYPE 1 X 1 TYPE 1 X 1 TYPE 2 X 1 TYPE 1 X 1 TYPE 2 X 1 TYPE 1 X 1

TYPE 2 X 1 TYPE 1 X 1 TYPE 2 X 1 TYPE 2 X 1 TYPE 2 X 1 LAYER 1

TYPE 1 X 1 TYPE 1 X 1 TYPE 2 X 1 TYPE 1 X 1 TYPE 2 X 1 TYPE 1 X 1

Tampak Atas Lapisan Bronjong


Skala 1:100

PANJANG LEBAR TINGGI

VOLUME KUANTITAS
JUMLAH (M3)
NO. STATION / LETAK SISI
P ( L (m T n V
m4 ) ) (m ) ( UNIT )
1 2 3 5 6 7 8=(4x5x6x7) 9=7
11 LAPIS - 11 Kanan 2.00 1.00 0.50 4.00 4.00 4.00
12 LAPIS - 12 Kanan 2.00 1.00 0.50 1.00
13 LAPIS - 13 Kanan 2.00 1.00 0.50 4.00
14 LAPIS - 14 Kanan 2.00 1.00 0.50 1.00
15 LAPIS - 15 Kanan 2.00 1.00 0.50 4.00
16 LAPIS - 16 Kanan 2.00 1.00 0.50 1.00
17 LAPIS - 17 Kanan 2.00 1.00 0.50 4.00

Jumlah halaman ini 4.00 4.00


Jumlah s/d halaman ini 50.00 50.00

SISOBALAURU, 2021
TAKE OF SHEET (TOS)
PERHITUNGAN VOLUME
SNI. P.06.b.4.(1) Pasangan bronjong pabrikasi Type - 1 uk. (2,0 mm x 1,0 mm x 0,5 mm)
PEK. BRONJONG PENAHAN 1 Tpt Sep. 14 M' & Tinggi 5.50 M'

DESA : SISOBALAURU
KECAMATAN : HILIDUHO
KABUPATEN / KOTA : NIAS
PROVINSI : SUMATERA UTARA
NO. RAB :
BIDANG : PEMBANGUNAN DESA
KEGIATAN : PEK. BRONJONG PENAHAN 1 Tpt Sep. 14 M' & Tinggi 5.50 M'

DISETUJUI OLEH : DIVERIFIKASI OLEH : DIBUAT OLEH :


Pj. KEPALA DESA SEKRETARIS DESA TIM PELAKSANA KEGIATAN

WA'OZISOKHI WARUWU, S.Pd.SD SIASA NDRAHA OTONI NDRAHA


Ketua
TAKE OF SHEET (TOS)
PERHITUNGAN VOLUME
SNI. P.06.b.4.(2) Pasangan bronjong pabrikasi Type - 2 uk. (3,0 mm x 1,0 mm x 0,5 mm)
PEK. BRONJONG PENAHAN 1 Tpt Sep. 14 M' & Tinggi 5.50 M'

DESA : SISOBALAURU
KECAMATAN : HILIDUHO
KABUPATEN / KOTA : NIAS
PROVINSI : SUMATERA UTARA
NO. RAB :
BIDANG : PEMBANGUNAN DESA
KEGIATAN : PEK. BRONJONG PENAHAN 1 Tpt Sep. 14 M' & Tinggi 5.50 M'

Sketsa

TYPE 1 X 1 TYPE 1 X 1 TYPE 2 X 1 TYPE 1 X 1 TYPE 2 X 1 TYPE 1 X 1 LAYER 11

TYPE 2 X 1 TYPE 1 X 1 TYPE 2 X 1 TYPE 2 X 1 TYPE 2 X 1 LAYER 10

50 TYPE 1 X 1 TYPE 1 X 1 TYPE 2 X 1 TYPE 1 X 1 TYPE 2 X 1 TYPE 1 X 1 LAYER 11 TYPE 1 X 1 TYPE 1 X 1 TYPE 2 X 1 TYPE 1 X 1 TYPE 2 X 1 TYPE 1 X 1 LAYER 9

50 TYPE 2 X 1 TYPE 1 X 1 TYPE 2 X 1 TYPE 2 X 1 TYPE 2 X 1 LAYER 10


TYPE 2 X 1 TYPE 1 X 1 TYPE 2 X 1 TYPE 2 X 1 TYPE 2 X 1 LAYER 8
50 TYPE 1 X 1 TYPE 1 X 1 TYPE 2 X 1 TYPE 1 X 1 TYPE 2 X 1 TYPE 1 X 1 LAYER 9
50 TYPE 2 X 1 TYPE 1 X 1 TYPE 2 X 1 TYPE 2 X 1 TYPE 2 X 1 LAYER 8 TYPE 1 X 1 TYPE 1 X 1 TYPE 2 X 1 TYPE 1 X 1 TYPE 2 X 1 TYPE 1 X 1 LAYER 7
400
50 TYPE 1 X 1 TYPE 1 X 1 TYPE 2 X 1 TYPE 1 X 1 TYPE 2 X 1 TYPE 1 X 1 LAYER 7
TYPE 2 X 1 TYPE 1 X 1 TYPE 2 X 1 TYPE 2 X 1 TYPE 2 X 1 LAYER 6
50 TYPE 2 X 1 TYPE 1 X 1 TYPE 2 X 1 TYPE 2 X 1 TYPE 2 X 1 LAYER 6
TYPE TYPE TYPE TYPE TYPE
50 1 X1 1 X1 1 X1 1 X1 TYPE 2 X 1 TYPE 2 X 1 TYPE 2 X 1 1 X1
LAYER 5

TYPE 1 X 1
TYPE 1 X 1
TYPE 1 X 1
TYPE 1 X 1

TYPE 1 X 1
TYPE 2 X 1 TYPE 2 X 1 TYPE 2 X 1
50 TYPE 2 X 1 TYPE 1 X 1 TYPE 2 X 1 TYPE 2 X 1 TYPE 2 X 1 LAYER 4 LAYER 5
TYPE 2 X 1 TYPE 2 X 1 TYPE 2 X 1
50 TYPE 1 X 1 TYPE 1 X 1 TYPE 2 X 1 TYPE 1 X 1 TYPE 2 X 1 TYPE 1 X 1 LAYER 3
150 50 TYPE 2 X 1 TYPE 1 X 1 TYPE 2 X 1 TYPE 2 X 1 TYPE 2 X 1 LAYER 2 TYPE 2 X 1 TYPE 1 X 1 TYPE 2 X 1 TYPE 2 X 1 TYPE 2 X 1
50 TYPE 1 X 1 TYPE 1 X 1 TYPE 2 X 1 TYPE 1 X 1 TYPE 2 X 1 TYPE 1 X 1 LAYER 1 TYPE 1 X 1 TYPE 1 X 1 TYPE 2 X 1 TYPE 1 X 1 TYPE 2 X 1 TYPE 1 X 1 LAYER 4

TYPE 2 X 1 TYPE 1 X 1 TYPE 2 X 1 TYPE 2 X 1 TYPE 2 X 1

350 TYPE 1 X 1 TYPE 1 X 1 TYPE 2 X 1 TYPE 1 X 1 TYPE 2 X 1 TYPE 1 X 1

TYPE 2 X 1 TYPE 1 X 1 TYPE 2 X 1 TYPE 2 X 1 TYPE 2 X 1 LAYER 3


100 100 100 100 100 100 100 100 100 100 100 100 100
TYPE 1 X 1 TYPE 1 X 1 TYPE 2 X 1 TYPE 1 X 1 TYPE 2 X 1 TYPE 1 X 1

TYPE 2 X 1 TYPE 1 X 1 TYPE 2 X 1 TYPE 2 X 1 TYPE 2 X 1

Tampak Depan Bronjong TYPE 1 X 1 TYPE 1 X 1 TYPE 2 X 1 TYPE 1 X 1 TYPE 2 X 1 TYPE 1 X 1 LAYER 2

Skala 1:100 TYPE 2 X 1 TYPE 1 X 1 TYPE 2 X 1 TYPE 2 X 1 TYPE 2 X 1

TYPE 1 X 1 TYPE 1 X 1 TYPE 2 X 1 TYPE 1 X 1 TYPE 2 X 1 TYPE 1 X 1

TYPE 2 X 1 TYPE 1 X 1 TYPE 2 X 1 TYPE 2 X 1 TYPE 2 X 1 LAYER 1

TYPE 1 X 1 TYPE 1 X 1 TYPE 2 X 1 TYPE 1 X 1 TYPE 2 X 1 TYPE 1 X 1

Tampak Atas Lapisan Bronjong


Skala 1:100

PANJANG LEBAR TINGGI

VOLUME KUANTITAS
JUMLAH
NO. STATION / LETAK SISI (M3)
P ( L (m T n V
m4 ) ) (m ) ( UNIT )
1 2 3 5 6 7 8=(4x5x6x7) 9=7
1 LAPIS - 1 Kanan 3.00 1.00 0.50 8.00 12.00 8.00
2 LAPIS - 2 Kanan 3.00 1.00 0.50 10.00 15.00 10.00
3 LAPIS - 3 Kanan 3.00 1.00 0.50 8.00 12.00 8.00
4 LAPIS - 4 Kanan 3.00 1.00 0.50 10.00 15.00 10.00
5 LAPIS - 5 Kanan 3.00 1.00 0.50 6.00 9.00 6.00
6 LAPIS - 6 Kanan 3.00 1.00 0.50 4.00 6.00 4.00
7 LAPIS - 7 Kanan 3.00 1.00 0.50 2.00 3.00 2.00
8 LAPIS - 8 Kanan 3.00 1.00 0.50 4.00 6.00 4.00
9 LAPIS - 9 Kanan 3.00 1.00 0.50 2.00 3.00 2.00
10 LAPIS - 10 Kanan 3.00 1.00 0.50 4.00 6.00 4.00
Jumlah halaman ini 87.00 58.00
Jumlah s/d halaman ini

SISOBALAURU, 2021

DISETUJUI OLEH : DIVERIFIKASI OLEH : DIBUAT OLEH :


Pj. KEPALA DESA SEKRETARIS DESA TIM PELAKSANA KEGIATAN
TAKE OF SHEET (TOS)
PERHITUNGAN VOLUME
SNI. P.06.b.4.(2) Pasangan bronjong pabrikasi Type - 2 uk. (3,0 mm x 1,0 mm x 0,5 mm)
PEK. BRONJONG PENAHAN 1 Tpt Sep. 14 M' & Tinggi 5.50 M'

DESA : SISOBALAURU
KECAMATAN : HILIDUHO
KABUPATEN / KOTA : NIAS
PROVINSI : SUMATERA UTARA
NO. RAB :
BIDANG : PEMBANGUNAN DESA
KEGIATAN : PEK. BRONJONG PENAHAN 1 Tpt Sep. 14 M' & Tinggi 5.50 M'

WA'OZISOKHI WARUWU, S.Pd.SD SIASA NDRAHA OTONI NDRAHA


Ketua
TAKE OF SHEET (TOS)
PERHITUNGAN VOLUME
SNI. P.06.b.4.(2) Pasangan bronjong pabrikasi Type - 2 uk. (3,0 mm x 1,0 mm x 0,5 mm)
PEK. BRONJONG PENAHAN 1 Tpt Sep. 14 M' & Tinggi 5.50 M'

DESA : SISOBALAURU
KECAMATAN : HILIDUHO
KABUPATEN / KOTA : NIAS
PROVINSI : SUMATERA UTARA
NO. RAB :
BIDANG : PEMBANGUNAN DESA
KEGIATAN : PEK. BRONJONG PENAHAN 1 Tpt Sep. 14 M' & Tinggi 5.50 M'

Sketsa

TYPE 1 X 1 TYPE 1 X 1 TYPE 2 X 1 TYPE 1 X 1 TYPE 2 X 1 TYPE 1 X 1 LAYER 11

TYPE 2 X 1 TYPE 1 X 1 TYPE 2 X 1 TYPE 2 X 1 TYPE 2 X 1 LAYER 10

50 TYPE 1 X 1 TYPE 1 X 1 TYPE 2 X 1 TYPE 1 X 1 TYPE 2 X 1 TYPE 1 X 1 LAYER 11 TYPE 1 X 1 TYPE 1 X 1 TYPE 2 X 1 TYPE 1 X 1 TYPE 2 X 1 TYPE 1 X 1 LAYER 9

50 TYPE 2 X 1 TYPE 1 X 1 TYPE 2 X 1 TYPE 2 X 1 TYPE 2 X 1 LAYER 10


TYPE 2 X 1 TYPE 1 X 1 TYPE 2 X 1 TYPE 2 X 1 TYPE 2 X 1 LAYER 8
50 TYPE 1 X 1 TYPE 1 X 1 TYPE 2 X 1 TYPE 1 X 1 TYPE 2 X 1 TYPE 1 X 1 LAYER 9
50 TYPE 2 X 1 TYPE 1 X 1 TYPE 2 X 1 TYPE 2 X 1 TYPE 2 X 1 LAYER 8 TYPE 1 X 1 TYPE 1 X 1 TYPE 2 X 1 TYPE 1 X 1 TYPE 2 X 1 TYPE 1 X 1 LAYER 7
400
50 TYPE 1 X 1 TYPE 1 X 1 TYPE 2 X 1 TYPE 1 X 1 TYPE 2 X 1 TYPE 1 X 1 LAYER 7
TYPE 2 X 1 TYPE 1 X 1 TYPE 2 X 1 TYPE 2 X 1 TYPE 2 X 1 LAYER 6
50 TYPE 2 X 1 TYPE 1 X 1 TYPE 2 X 1 TYPE 2 X 1 TYPE 2 X 1 LAYER 6
TYPE TYPE TYPE TYPE TYPE
50 1 X1 1 X1 1 X1 1 X1 TYPE 2 X 1 TYPE 2 X 1 TYPE 2 X 1 1 X1
LAYER 5

TYPE 1 X 1
TYPE 1 X 1
TYPE 1 X 1
TYPE 1 X 1

TYPE 1 X 1
TYPE 2 X 1 TYPE 2 X 1 TYPE 2 X 1
50 TYPE 2 X 1 TYPE 1 X 1 TYPE 2 X 1 TYPE 2 X 1 TYPE 2 X 1 LAYER 4 LAYER 5
TYPE 2 X 1 TYPE 2 X 1 TYPE 2 X 1
50 TYPE 1 X 1 TYPE 1 X 1 TYPE 2 X 1 TYPE 1 X 1 TYPE 2 X 1 TYPE 1 X 1 LAYER 3
150 50 TYPE 2 X 1 TYPE 1 X 1 TYPE 2 X 1 TYPE 2 X 1 TYPE 2 X 1 LAYER 2 TYPE 2 X 1 TYPE 1 X 1 TYPE 2 X 1 TYPE 2 X 1 TYPE 2 X 1
50 TYPE 1 X 1 TYPE 1 X 1 TYPE 2 X 1 TYPE 1 X 1 TYPE 2 X 1 TYPE 1 X 1 LAYER 1 TYPE 1 X 1 TYPE 1 X 1 TYPE 2 X 1 TYPE 1 X 1 TYPE 2 X 1 TYPE 1 X 1 LAYER 4

TYPE 2 X 1 TYPE 1 X 1 TYPE 2 X 1 TYPE 2 X 1 TYPE 2 X 1

350 TYPE 1 X 1 TYPE 1 X 1 TYPE 2 X 1 TYPE 1 X 1 TYPE 2 X 1 TYPE 1 X 1

TYPE 2 X 1 TYPE 1 X 1 TYPE 2 X 1 TYPE 2 X 1 TYPE 2 X 1 LAYER 3


100 100 100 100 100 100 100 100 100 100 100 100 100
TYPE 1 X 1 TYPE 1 X 1 TYPE 2 X 1 TYPE 1 X 1 TYPE 2 X 1 TYPE 1 X 1

TYPE 2 X 1 TYPE 1 X 1 TYPE 2 X 1 TYPE 2 X 1 TYPE 2 X 1

Tampak Depan Bronjong TYPE 1 X 1 TYPE 1 X 1 TYPE 2 X 1 TYPE 1 X 1 TYPE 2 X 1 TYPE 1 X 1 LAYER 2

Skala 1:100 TYPE 2 X 1 TYPE 1 X 1 TYPE 2 X 1 TYPE 2 X 1 TYPE 2 X 1

TYPE 1 X 1 TYPE 1 X 1 TYPE 2 X 1 TYPE 1 X 1 TYPE 2 X 1 TYPE 1 X 1

TYPE 2 X 1 TYPE 1 X 1 TYPE 2 X 1 TYPE 2 X 1 TYPE 2 X 1 LAYER 1

TYPE 1 X 1 TYPE 1 X 1 TYPE 2 X 1 TYPE 1 X 1 TYPE 2 X 1 TYPE 1 X 1

Tampak Atas Lapisan Bronjong


Skala 1:100

PANJANG LEBAR TINGGI

VOLUME KUANTITAS
JUMLAH
NO. STATION / LETAK SISI (M3)
P ( L (m T n V
m4 ) ) (m ) ( UNIT )
1 2 3 5 6 7 8=(4x5x6x7) 9=7
11 LAPIS - 11 Kanan 3.00 1.00 0.50 2.00 3.00 2.00
12 LAPIS - 12 Kanan 3.00 1.00 0.50 4.00
13 LAPIS - 13 Kanan 3.00 1.00 0.50 2.00
14 LAPIS - 14 Kanan 3.00 1.00 0.50 4.00
15 LAPIS - 15 Kanan 3.00 1.00 0.50 2.00
16 LAPIS - 16 Kanan 3.00 1.00 0.50 4.00
17 LAPIS - 17 Kanan 3.00 1.00 0.50 2.00

Jumlah halaman ini 3.00 2.00


Jumlah s/d halaman ini 90.00 60.00

SISOBALAURU, 2021

DISETUJUI OLEH : DIVERIFIKASI OLEH : DIBUAT OLEH :


Pj. KEPALA DESA SEKRETARIS DESA TIM PELAKSANA KEGIATAN
TAKE OF SHEET (TOS)
PERHITUNGAN VOLUME
SNI. P.06.b.4.(2) Pasangan bronjong pabrikasi Type - 2 uk. (3,0 mm x 1,0 mm x 0,5 mm)
PEK. BRONJONG PENAHAN 1 Tpt Sep. 14 M' & Tinggi 5.50 M'

DESA : SISOBALAURU
KECAMATAN : HILIDUHO
KABUPATEN / KOTA : NIAS
PROVINSI : SUMATERA UTARA
NO. RAB :
BIDANG : PEMBANGUNAN DESA
KEGIATAN : PEK. BRONJONG PENAHAN 1 Tpt Sep. 14 M' & Tinggi 5.50 M'

WA'OZISOKHI WARUWU, S.Pd.SD SIASA NDRAHA OTONI NDRAHA


Ketua
TAKE OF SHEET (TOS)
PERHITUNGAN VOLUME
SNI. P.06.b.4.(3) Pasangan bronjong pabrikasi Type - 3 uk. (3,0 mm x 1,5 mm x 0,5 mm)
PEK. BRONJONG PENAHAN 1 Tpt Sep. 9 M'

DESA : SISOBALAURU
KECAMATAN :
KABUPATEN / KOTA :
PROVINSI :
NO. RAB : PEK. BRONJONG PENAHAN 1 Tpt Sep. 9 M'
BIDANG :
KEGIATAN :
### :
### :

Sketsa

PANJANG LEBAR TINGGI

VOLUME KUANTITAS
JUMLAH
NO. STATION / LETAK SISI (M3)
P ( L (m T n V
m4 ) ) (m ) ( UNIT )
1 2 3 5 6 7 8=(4x5x6x7) 9=7
1 LAPIS - 4 Kanan 3.00 1.50 0.50 3.00 6.75 3.00
2 LAPIS - 6 Kanan 3.00 1.50 0.50 3.00 6.75 3.00
3
4
5
6
7
8
9
10
Jumlah halaman ini 13.50 6.00
Jumlah s/d halaman ini 13.50 6.00

0 0
0 0
TAKE OF SHEET (TOS)
PERHITUNGAN VOLUME
SNI. P.06.b.4.(3) Pasangan bronjong pabrikasi Type - 3 uk. (3,0 mm x 1,5 mm x 0,5 mm)
PEK. BRONJONG PENAHAN 1 Tpt Sep. 9 M'

DESA : SISOBALAURU
KECAMATAN :
KABUPATEN / KOTA :
PROVINSI :
NO. RAB : PEK. BRONJONG PENAHAN 1 Tpt Sep. 9 M'
BIDANG :
KEGIATAN :
### :
### :

0 0
TAKE OF SHEET (TOS)
PERHITUNGAN VOLUME
SNI. A.2.3.1.9. Pengurugan kembali 1 m3 galian tanah
PEK. BRONJONG PENAHAN 1 Tpt Sep. 14 M' & Tinggi 5.50 M'

DESA : SISOBALAURU
KECAMATAN : HILIDUHO
KABUPATEN / KOTA : NIAS
PROVINSI : SUMATERA UTARA
NO. RAB :
BIDANG : PEMBANGUNAN DESA
KEGIATAN : PEK. BRONJONG PENAHAN 1 Tpt Sep. 14 M' & Tinggi 5.50 M'

Sketsa

Timbunan Tanah
(dari Sisa Galian) 50 50 50 50

50

50

50

50

MTA

Tampak Samping Bronjong


Skala 1:100

BIDANG PERSEGI BIDANG TRAPESIUM BIDANG SEGITIGA


LUAS LUAS RATA - PANJANG
LEBAR TINGGI LEBAR TINGGI RATA
No POSISI / LETAK SISI TINGGI TINGGI RATA LEBAR LEBAR RATA 1/2
(m) - RATA ( m ) (m) - RATA ( m ) ( m2 ) ( m2 ) (m)
(m) (m) (m) (m)
L T T1 T2 T L1 L2 L L T A A P
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17

0 + 000 Kanan 0.50 0.50 0.50 0.13


1 STA. 0.13 14.00
0 + 014 Kanan 0.50 0.50 0.50 0.13

Jumlah halaman ini 14.00


Jumlah s/d halaman ini

SISOBALAURU, 2021

DISETUJUI OLEH : DIVERIFIKASI OLEH : DIBUAT OLEH :


Pj. KEPALA DESA SEKRETARIS DESA TIM PELAKSANA KEGIATAN

WA'OZISOKHI WARUWU, S.Pd.SD SIASA NDRAHA OTONI NDRAHA


Ketua
TAKE OF SHEET (TOS)
PERHITUNGAN VOLUME
SNI. A.2.3.1.9. Pengurugan kembali 1 m3 galian tanah
PEK. BRONJONG PENAHAN 1 Tpt Sep. 14 M' & Tinggi 5.50 M'

DESA : SISOBALAURU
KECAMATAN : HILIDUHO
KABUPATEN / KOTA : NIAS
PROVINSI : SUMATERA UTARA
NO. RAB :
BIDANG : PEMBANGUNAN DESA
KEGIATAN : PEK. BRONJONG PENAHAN 1 Tpt Sep. 14 M' & Tinggi 5.50 M'

Sketsa

50

50 Timbunan Tanah
(dari Sisa Galian)
38

MTA

Tampak Samping Bronjong


Skala 1:100

BIDANG PERSEGI BIDANG TRAPESIUM BIDANG SEGITIGA


LUAS LUAS RATA - PANJANG
LEBAR TINGGI LEBAR TINGGI RATA
No POSISI / LETAK SISI TINGGI TINGGI RATA LEBAR LEBAR RATA 1/2
(m) - RATA ( m ) (m) - RATA ( m ) ( m2 ) ( m2 ) (m)
(m) (m) (m) (m)
L T T1 T2 T L1 L2 L L T A A P
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17

0 + 000 Kanan 0.50 0.38 0.50 0.44 0.22


2 STA. 0.22 14.00
0 + 014 Kanan 0.50 0.38 0.50 0.44 0.22

Jumlah halaman ini 14.00


Jumlah s/d halaman ini

SISOBALAURU, 2021

DISETUJUI OLEH : DIVERIFIKASI OLEH : DIBUAT OLEH :


Pj. KEPALA DESA SEKRETARIS DESA TIM PELAKSANA KEGIATAN

WA'OZISOKHI WARUWU, S.Pd.SD SIASA NDRAHA OTONI NDRAHA


Ketua
TAKE OF SHEET (TOS)
PERHITUNGAN VOLUME
SNI. A.2.3.1.9. Pengurugan kembali 1 m3 galian tanah
PEK. BRONJONG PENAHAN 1 Tpt Sep. 14 M' & Tinggi 5.50 M'

DESA : SISOBALAURU
KECAMATAN : HILIDUHO
KABUPATEN / KOTA : NIAS
PROVINSI : SUMATERA UTARA
NO. RAB :
BIDANG : PEMBANGUNAN DESA
KEGIATAN : PEK. BRONJONG PENAHAN 1 Tpt Sep. 14 M' & Tinggi 5.50 M'

Sketsa

88

50 Timbunan Tanah
(dari Sisa Galian)
82

MTA

Tampak Samping Bronjong


Skala 1:100

BIDANG PERSEGI BIDANG TRAPESIUM BIDANG SEGITIGA


LUAS LUAS RATA - PANJANG
LEBAR TINGGI LEBAR TINGGI RATA
No POSISI / LETAK SISI TINGGI TINGGI RATA LEBAR LEBAR RATA 1/2
(m) - RATA ( m ) (m) - RATA ( m ) ( m2 ) ( m2 ) (m)
(m) (m) (m) (m)
L T T1 T2 T L1 L2 L L T A A P
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17

0 + 000 Kanan 0.50 0.88 0.82 0.85 0.43


3 STA. 0.43 14.00
0 + 014 Kanan 0.50 0.88 0.82 0.85 0.43

Jumlah halaman ini 14.00


Jumlah s/d halaman ini

SISOBALAURU, 2021

DISETUJUI OLEH : DIVERIFIKASI OLEH : DIBUAT OLEH :


Pj. KEPALA DESA SEKRETARIS DESA TIM PELAKSANA KEGIATAN

WA'OZISOKHI WARUWU, S.Pd.SD SIASA NDRAHA OTONI NDRAHA


Ketua
TAKE OF SHEET (TOS)
PERHITUNGAN VOLUME
SNI. A.2.3.1.9. Pengurugan kembali 1 m3 galian tanah
PEK. BRONJONG PENAHAN 1 Tpt Sep. 14 M' & Tinggi 5.50 M'

DESA : SISOBALAURU
KECAMATAN : HILIDUHO
KABUPATEN / KOTA : NIAS
PROVINSI : SUMATERA UTARA
NO. RAB :
BIDANG : PEMBANGUNAN DESA
KEGIATAN : PEK. BRONJONG PENAHAN 1 Tpt Sep. 14 M' & Tinggi 5.50 M'

Sketsa

32
Timbunan Tanah
41
(dari Sisa Galian)
MTA

Tampak Samping Bronjong


Skala 1:100

BIDANG PERSEGI BIDANG TRAPESIUM BIDANG SEGITIGA


LUAS LUAS RATA - PANJANG
LEBAR TINGGI LEBAR TINGGI RATA
No POSISI / LETAK SISI TINGGI TINGGI RATA LEBAR LEBAR RATA 1/2
(m) - RATA ( m ) (m) - RATA ( m ) ( m2 ) ( m2 ) (m)
(m) (m) (m) (m)
L T T1 T2 T L1 L2 L L T A A P
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17

0 + 000 Kanan 0.32 0.41 0.37 0.05


4 STA. 0.05 14.00
0 + 014 Kanan 0.32 0.41 0.37 0.05

Jumlah halaman ini 14.00


Jumlah s/d halaman ini 14.00

SISOBALAURU, 2021

DISETUJUI OLEH : DIVERIFIKASI OLEH : DIBUAT OLEH :


Pj. KEPALA DESA SEKRETARIS DESA TIM PELAKSANA KEGIATAN

WA'OZISOKHI WARUWU, S.Pd.SD SIASA NDRAHA OTONI NDRAHA


Ketua
JUMLAH KUANTITAS

(n) (m3)
18 19=(16x17x18)

4.00 7.00

7.00

2021
JUMLAH KUANTITAS

(n) (m3)
18 19=(16x17x18)

1.00 3.08

3.08

2021
JUMLAH KUANTITAS

(n) (m3)
18 19=(16x17x18)

1.00 5.95

5.95

2021
JUMLAH KUANTITAS

(n) (m3)
18 19=(16x17x18)

1.00 0.67

0.67
16.70

2021
DAFTAR HARGA BAHAN/MATERIAL, ALAT BANTU, SEWA ALAT BERAT DAN UPAH

DESA : SISOBALAURU
KECAMATAN : HILIDUHO
KABUPATEN / KOTA : NIAS
PROVINSI : SUMATERA UTARA
NO. RAB :
BIDANG : PEMBANGUNAN DESA

HARGA UPAH
No Uraian Tenaga Kerja Sat. Keterangan Produktifitas
(Rp.)
A. UPAH TENAGA KERJA :
1 Pekerja OH 100,000 1 HARI = 8 JAM KERJA
2 Tukang Kayu, Batu dan Besi OH 120,000 1 HARI = 8 JAM KERJA
3 Tukang Siram Aspal OH 225,000 1 HARI = 8 JAM KERJA
4 Kepala Tukang OH 140,000 1 HARI = 8 JAM KERJA
A1. UPAH TENAGA KERJA PENGUMPUL :
1 Batu Kali/Sungai belah 15-20 cm OH 150,000.00 1 HARI = 8 JAM KERJA
2 Tanah Timbunan Biasa OH 72,600.00 1 HARI = 8 JAM KERJA
A2. UPAH TENAGA KERJA PEMECAH BATU :
1 Batu Kali/Sungai belah 15-20 cm OH 150,000.00 1 HARI = 8 JAM KERJA
2 Batu Gunung belah 10-15 cm OH 150,000.00 1 HARI = 8 JAM KERJA
3 Batu Pecah 5-7 cm Jenis Keras (Manual) OH 150,000.00 1 HARI = 8 JAM KERJA
4 Batu Pecah 3-5 cm Jenis Keras (Manual) OH 180,000.00 1 HARI = 8 JAM KERJA
5 Batu Pecah 2-3 cm Jenis Keras (Manual) OH 270,000.00 1 HARI = 8 JAM KERJA
6 Batu Kali Pecah 1-2 cm Jenis Keras (Manual) OH 484,000.00 1 HARI = 8 JAM KERJA
A3. UPAH TENAGA KERJA PENGGALIAN :
1 Tanah Timbunan Biasa OH 72,600.00 1 HARI = 8 JAM KERJA
A4. UPAH ANGKUT / PIKUL PUNDAK TENAGA MANUSIA SAMPAI DI LOKASI PEKERJAAN :
1 Batu Kali/Sungai belah 15-20 cm OH 56,250.00 1 HARI = 8 JAM KERJA
2 Batu Gunung belah 10-15 cm OH 56,250.00 1 HARI = 8 JAM KERJA
3 Batu Pecah 5-7 cm Jenis Keras (Manual) OH 56,250.00 1 HARI = 8 JAM KERJA
4 Batu Pecah 3-5 cm Jenis Keras (Manual) OH 56,250.00 1 HARI = 8 JAM KERJA
5 Batu Pecah 2-3 cm Jenis Keras (Manual) OH 56,250.00 1 HARI = 8 JAM KERJA
6 Batu Kali Pecah 1-2 cm Jenis Keras (Manual) OH 56,250.00 1 HARI = 8 JAM KERJA
7 Kepala Pasir OH 56,250.00 1 HARI = 8 JAM KERJA
8 Pasir Pasangan OH 56,250.00 1 HARI = 8 JAM KERJA
9 Tanah Timbunan Biasa OH 187,500.00 1 HARI = 8 JAM KERJA
10 Semen Portland @50 kg Type PCC OH 6,000.00 1 HARI = 8 JAM KERJA
11 Kayu Bulat Ø 7 - 8 cm; 3,5 m (dolo-dolo) OH 1,350.00 1 HARI = 8 JAM KERJA
12 Papan Bekisting,uk. 0.20 m x 0.02 m x 2.0 m OH 900.00 1 HARI = 8 JAM KERJA
13 Kayu segi/Broti, uk. 5 - 7 cm. Pjg. 3.00 M' OH 900.00 1 HARI = 8 JAM KERJA
DAFTAR HARGA BAHAN/MATERIAL, ALAT BANTU, SEWA ALAT BERAT DAN UPAH

DESA : SISOBALAURU
KECAMATAN : HILIDUHO
KABUPATEN / KOTA : NIAS
PROVINSI : SUMATERA UTARA
NO. RAB :
BIDANG : PEMBANGUNAN DESA

HARGA TOTAL BIAYA TOTAL


BAHAN, MATERIAL ONGKOS ANGKUT
DAN ALAT BANTU DENGAN TRUK Keterangan Sumber
No Uraian Bahan / Material dan Alat Bantu Sat.
(Termasuk Pajak) (Termasuk Pajak) Quarry/toko/distributor

(Rp.) (Rp.)
B. BAHAN :
B1. MATERIAL / BAHAN YANG DIDATANGKAN :
1 Batu Gunung belah 15-20 cm M³ 187,500 326,400 KEC. HILIDUHO (Ds. Sisobahili)
2 Batu Gunung belah 10-15 cm M³ 187,500 326,400 KEC. HILIDUHO (Ds. Sisobahili)
3 Batu Pecah 5-7 cm Jenis Keras (Manual) M³ 187,500 357,000 KEC. HILIDUHO (Ds. Sisobahili)
4 Batu Pecah 3-5 cm Jenis Keras (Manual) M³ 225,000 357,000 KEC. HILIDUHO (Ds. Sisobahili)
5 Base B M³ 681,300 351,900 KEC. HILIDUHO (Ds. Hiligodu)
6 Kerikil Sungai di saring, uk. 0.5 - 2 cm M³ 187,500 249,900 KEC. HILIDUHO (Ds. Ononamolo-I)
7 Kerikil Sungai tidak di saring M³ 150,000 249,900 KEC. HILIDUHO (Ds. Ononamolo-I)
8 Kepala Pasir M³ 181,300 249,900 KEC. HILIDUHO (Ds. Ononamolo-I)
9 Pasir Pasangan M³ 181,300 249,900 KEC. HILIDUHO (Ds. Ononamolo-I)
10 Pasir Urug M³ 136,300 249,900 KEC. HILIDUHO (Ds. Ononamolo-I)
11 Sirtu M³ 136,300 249,900 KEC. HILIDUHO (Ds. Ononamolo-I)
12 Tanah Timbunan Biasa M³ 90,800 147,900 KEC. HILIDUHO
13 Kayu Jenis Keras M³ 3,345,000 122,400 KEC. HILIDUHO
14 Kayu Sembarang (Tanpa Jenis) M³ 2,676,000 122,400 KEC. HILIDUHO
15 Kayu Api/Kayu Bakar M³ 120,000 122,400 KEC. HILIDUHO
16 Batang Kelapa uk. Ø 20/25 cm Btg 190,000 20,400 KEC. HILIDUHO
17 Kayu Bulat Ø 7 - 8 cm; 3,5 m (dolo-dolo) Btg 8,400 1,700 KEC. HILIDUHO
18 Kayu Bulat Ø 10-15 cm; 3,5 m Btg 12,000 3,400 KEC. HILIDUHO
19 Papan Bekisting,uk. 0.20 m x 0.02 m x 2.0 m Lbr 21,200 1,000 KEC. HILIDUHO
20 Kayu segi/Broti, uk. 5 - 7 cm. Pjg. 3.00 M' Btg 27,900 1,300 KEC. HILIDUHO
B2. MATERIAL (PABRIKASI / TOKO / DISTRIBUTOR) :
1 Semen Portland @50 kg Type PCC Zak 99,300 10,000 GUNUNGSITOLI
2 Kawat Beton/Kawat Ikat Kg 29,000 - GUNUNGSITOLI
3 Kawat Bronjong Pabrikasi Type - 1 Unit 376,900 9,400 GUNUNGSITOLI
4 Kawat Bronjong Pabrikasi Type - 2 Unit 599,900 14,200 GUNUNGSITOLI
5 Kawat Bronjong Pabrikasi Type - 3 Unit 780,500 19,300 GUNUNGSITOLI
6 Paku Biasa Kg 20,000 - GUNUNGSITOLI
7 Aspal Kg 13,600 600 GUNUNGSITOLI
8 Minyak Solar (Non Subsidi) Ltr 9,400 - GUNUNGSITOLI
9 Minyak Bakar / Tanah (Non Subsidi) Ltr 11,200 - GUNUNGSITOLI
10 Minyak Bensin Ltr 6,500 - GUNUNGSITOLI
11 Minyak Pelumas/Olie Ltr 44,600 - GUNUNGSITOLI
12 Minyak Bekisting Kg 10,100 - GUNUNGSITOLI
13 Geotextile Non Woven 250 gr/m2 (4mx100m) Roll 13,380,000 68,100 GUNUNGSITOLI
DAFTAR HARGA BAHAN/MATERIAL, ALAT BANTU, SEWA ALAT BERAT DAN UPAH

DESA : SISOBALAURU
KECAMATAN : HILIDUHO
KABUPATEN / KOTA : NIAS
PROVINSI : SUMATERA UTARA
NO. RAB :
BIDANG : PEMBANGUNAN DESA

C. ALAT BANTU (TOKO / DISTRIBUTOR) :


1 Meteran uk. 5.0 m Bh 30,200 - GUNUNGSITOLI
2 Meteran uk. 50.0 m Bh 63,600 - GUNUNGSITOLI
3 Sendok Semen Bh 30,100 - GUNUNGSITOLI
4 Raskam Besi Bh 50,200 - GUNUNGSITOLI
5 Raskam Plastik Bh 33,500 - GUNUNGSITOLI
6 Sekop besar + gagang Bh 113,800 - GUNUNGSITOLI
7 Cangkul + gagang Bh 113,800 - GUNUNGSITOLI
8 Martil Batu Uk. 3 Kg (godam) Bh 222,200 - GUNUNGSITOLI
9 Tembilang/penggali + gagang Bh 66,900 - GUNUNGSITOLI
10 Pecok/Bolak baling + gagang Bh 139,400 - GUNUNGSITOLI
11 Linggis Ulir Bh 39,100 - GUNUNGSITOLI
12 Palu/Penokok Bh 46,900 - GUNUNGSITOLI
13 Drum Plastik 200 ltr (Tampungan Air Hujan) Bh 328,400 - GUNUNGSITOLI
14 Selang Ukur Glg 16,800 - GUNUNGSITOLI
15 Tenda / Terpal Plastik A2 uk. 4 x 6 m Lbr 167,300 - GUNUNGSITOLI
16 Sarung Tangan Pekerja (karet) Psg 14,800 - GUNUNGSITOLI
17 Gerobak Sorong Unit 605,500 - GUNUNGSITOLI
18 Plengki Rotan Bh 20,700 - GUNUNGSITOLI
19 Ember Cor Bh 13,400 - GUNUNGSITOLI
20 Kaleng Siram Aspal Bh 33,500 - GUNUNGSITOLI
21 Gayung Aspal (kaleng) Bh 16,750 - GUNUNGSITOLI
22 Gergaji Bh 50,200 - GUNUNGSITOLI
23 Waterpass Bh 56,900 - GUNUNGSITOLI
24 Unting unting Bh 22,300 - GUNUNGSITOLI
25 Tang Kakak tua (pengikat kawat) Bh 42,925 - GUNUNGSITOLI
26 Pahat Batu Bh 22,300 - GUNUNGSITOLI
27 Benang Tukang (Nilon) Glg 16,800 - GUNUNGSITOLI

HARGA SEWA,
MOBILISASI DAN Keterangan Produktifitas
No Uraian Alat Berat Sat. DEMOBILISASI + PPh

(Rp.)
D. SEWA ALAT BERAT :
1 HARI = 5 JAM KERJA
1 Mesin gilas roda besi 6 - 8 T Jam 355,300
(ANL. K - BM Thn.1995)
2 Mobilisasi Ls 7,752,000 1 KALI
3 Demobilisasi Ls 7,752,000 1 KALI

SISOBALAURU, 2021

DISETUJUI OLEH : DIVERIFIKASI OLEH : DIBUAT OLEH :


Pj. KEPALA DESA SEKRETARIS DESA TIM PELAKSANA KEGIATAN

WA'OZISOKHI WARUWU, S.Pd.SD SIASA NDRAHA OTONI NDRAHA


DAFTAR HARGA BAHAN/MATERIAL, ALAT BANTU, SEWA ALAT BERAT DAN UPAH

DESA : SISOBALAURU
KECAMATAN : HILIDUHO
KABUPATEN / KOTA : NIAS
PROVINSI : SUMATERA UTARA
NO. RAB :
BIDANG : PEMBANGUNAN DESA

Ketua
DAFTAR ANALISA HARGA UPAH TENAGA KERJA

DESA : SISOBALAURU
KECAMATAN : HILIDUHO
KABUPATEN / KOTA : NIAS
PROVINSI : SUMATERA UTARA
NO. RAB :
BIDANG : PEMBANGUNAN DESA

Harga Upah / Sat. Harga Tangkahan / Nilai Konversi ke Harga Upah /


No Uraian Sat. Dibulatkan Keterangan Produktifitas
(Rp.) m3 (Rp.) OH Sat.Volume (Rp.)

A. UPAH TENAGA KERJA :


1 Pekerja OH 100,000.00 100,000.00 1 HARI = 8 JAM KERJA
2 Tukang Kayu, Batu dan Besi OH 120,000.00 120,000.00 1 HARI = 8 JAM KERJA
3 Tukang Siram Aspal OH 225,000.00 225,000.00 1 HARI = 8 JAM KERJA
4 Kepala Tukang OH 140,000.00 140,000.00 1 HARI = 8 JAM KERJA
A1. UPAH TENAGA KERJA PENGUMPUL :
1 Batu Kali/Sungai belah 15-20 cm OH 100,000.00 150,000.00 1.50 1.50 150,000.00 1 HARI = 8 JAM KERJA
2 Tanah Timbunan Biasa OH 100,000.00 72,600.00 0.73 0.73 72,600.00 1 HARI = 8 JAM KERJA
A2. UPAH TENAGA KERJA PEMECAH BATU :
1 Batu Kali/Sungai belah 15-20 cm OH 100,000.00 150,000.00 1.50 1.50 150,000.00 1 HARI = 8 JAM KERJA
2 Batu Gunung belah 10-15 cm OH 100,000.00 150,000.00 1.50 1.50 150,000.00 1 HARI = 8 JAM KERJA
3 Batu Pecah 5-7 cm Jenis Keras (Manual) OH 100,000.00 150,000.00 1.50 1.50 150,000.00 1 HARI = 8 JAM KERJA
4 Batu Pecah 3-5 cm Jenis Keras (Manual) OH 100,000.00 180,000.00 1.80 1.80 180,000.00 1 HARI = 8 JAM KERJA
5 Batu Pecah 2-3 cm Jenis Keras (Manual) OH 100,000.00 270,000.00 2.70 2.70 270,000.00 1 HARI = 8 JAM KERJA
6 Batu Kali Pecah 1-2 cm Jenis Keras (Manual) OH 100,000.00 484,000.00 4.84 4.84 484,000.00 1 HARI = 8 JAM KERJA
A3. UPAH TENAGA KERJA PENGGALIAN :
1 Tanah Timbunan Biasa OH 100,000.00 72,600.00 0.73 0.73 72,600.00 1 HARI = 8 JAM KERJA

Harga Upah / KM / Nilai Konversi ke Harga Upah /


No Uraian Sat. Jarak Pikul (KM) Dibulatkan Keterangan Produktifitas
Sat. (Rp.) OH Sat.Volume (Rp.)

A4. UPAH ANGKUT / PIKUL PUNDAK TENAGA MANUSIA SAMPAI DI LOKASI PEKERJAAN
1 Batu Kali/Sungai belah 15-20 cm OH 375,000.00 0.15 56,250.00 56,250.00 56,250.00 1 HARI = 8 JAM KERJA
2 Batu Gunung belah 10-15 cm OH 375,000.00 0.15 56,250.00 56,250.00 56,250.00 1 HARI = 8 JAM KERJA
3 Batu Pecah 5-7 cm Jenis Keras (Manual) OH 375,000.00 0.15 56,250.00 56,250.00 56,250.00 1 HARI = 8 JAM KERJA
4 Batu Pecah 3-5 cm Jenis Keras (Manual) OH 375,000.00 0.15 56,250.00 56,250.00 56,250.00 1 HARI = 8 JAM KERJA
5 Batu Pecah 2-3 cm Jenis Keras (Manual) OH 375,000.00 0.15 56,250.00 56,250.00 56,250.00 1 HARI = 8 JAM KERJA
6 Batu Kali Pecah 1-2 cm Jenis Keras (Manual) OH 375,000.00 0.15 56,250.00 56,250.00 56,250.00 1 HARI = 8 JAM KERJA
7 Kepala Pasir OH 375,000.00 0.15 56,250.00 56,250.00 56,250.00 1 HARI = 8 JAM KERJA
8 Pasir Pasangan OH 375,000.00 0.15 56,250.00 56,250.00 56,250.00 1 HARI = 8 JAM KERJA
9 Tanah Timbunan Biasa OH 375,000.00 0.50 187,500.00 187,500.00 187,500.00 1 HARI = 8 JAM KERJA
10 Semen Portland @50 kg Type PCC OH 40,000.00 0.15 6,000.00 6,000.00 6,000.00 1 HARI = 8 JAM KERJA
11 Kayu Bulat Ø 7 - 8 cm; 3,5 m (dolo-dolo) OH 9,000.00 0.15 1,350.00 1,350.00 1,350.00 1 HARI = 8 JAM KERJA
12 Papan Bekisting,uk. 0.20 m x 0.02 m x 2.0 m OH 6,000.00 0.15 900.00 900.00 900.00 1 HARI = 8 JAM KERJA
13 Kayu segi/Broti, uk. 5 - 7 cm. Pjg. 3.00 M' OH 6,000.00 0.15 900.00 900.00 900.00 1 HARI = 8 JAM KERJA

SISOBALAURU, 2021

DISETUJUI OLEH : DIVERIFIKASI OLEH : DIBUAT OLEH :


Pj. KEPALA DESA SEKRETARIS DESA TIM PELAKSANA KEGIATAN

WA'OZISOKHI WARUWU, S.Pd.SD SIASA NDRAHA OTONI NDRAHA


Ketua
DAFTAR ANALISA HARGA BAHAN/MATERIAL, ALAT BANTU SAMPAI DI LOKASI PEKERJAAN

DESA : SISOBALAURU
KECAMATAN : HILIDUHO
KABUPATEN / KOTA : NIAS
PROVINSI : SUMATERA UTARA
NO. RAB :
BIDANG : PEMBANGUNAN DESA

Biaya angkut dengan truk


PAJAK MBLB PPN PPh 22 HARGA TOTAL PPh 23 BIAYA TOTAL
Harga
BAHAN, Bukit ONGKOS
Bahan/Material, Alat
MATERIAL DAN ANGKUT Kategori
No Jenis Bahan Sat. Sedang Jelek
ALAT BANTU DENGAN TRUK Biaya
di Quarry/toko
(Termasuk Pajak) (Termasuk Pajak)
25% 10% 1,5 % Jarak Angkut Ongkos Angkut Jarak Angkut Ongkos Angkut 2%

(Rp.) (Rp.) (Rp.) (Rp.) (Rp.) (Km) (Rp.) (Km) (Rp.) (Rp.) (Rp.)
B. BAHAN :
B1. MATERIAL / BAHAN YANG DIDATANGKAN :
1 Batu Gunung belah 15-20 cm M³ 150,000 37,500 - - 187,500 - - 10.00 320,000 6,400 326,400 I-a
2 Batu Gunung belah 10-15 cm M³ 150,000 37,500 - - 187,500 - - 10.00 320,000 6,400 326,400 I-a
3 Batu Pecah 5-7 cm Jenis Keras (Manual) M³ 150,000 37,500 - - 187,500 - - 10.00 350,000 7,000 357,000 I-a
4 Batu Pecah 3-5 cm Jenis Keras (Manual) M³ 180,000 45,000 - - 225,000 - - 10.00 350,000 7,000 357,000 I-a
5 Base B M³ 545,000 136,300 - - 681,300 - - 11.00 345,000 6,900 351,900 I-a
6 Kerikil Sungai di saring, uk. 0.5 - 2 cm M³ 150,000 37,500 - - 187,500 - - 7.00 245,000 4,900 249,900 I-a
7 Kerikil Sungai tidak di saring M³ 120,000 30,000 - - 150,000 - - 7.00 245,000 4,900 249,900 I-a
8 Kepala Pasir M³ 145,000 36,300 - - 181,300 - - 7.00 245,000 4,900 249,900 I-a
9 Pasir Pasangan M³ 145,000 36,300 - - 181,300 - - 7.00 245,000 4,900 249,900 I-a
10 Pasir Urug M³ 109,000 27,300 - - 136,300 - - 7.00 245,000 4,900 249,900 I-a
11 Sirtu M³ 109,000 27,300 - - 136,300 - - 7.00 245,000 4,900 249,900 I-a
12 Tanah Timbunan Biasa M³ 72,600 18,200 - - 90,800 - - 3.00 145,000 2,900 147,900 I-a
13 Kayu Jenis Keras M³ 3,000,000 - 300,000 45,000 3,345,000 - - 3.00 120,000 2,400 122,400 I-a
14 Kayu Sembarang (Tanpa Jenis) M³ 2,400,000 - 240,000 36,000 2,676,000 - - 3.00 120,000 2,400 122,400 I-a
15 Kayu Api/Kayu Bakar M³ 120,000 - - - 120,000 - - 3.00 120,000 2,400 122,400 I-a
16 Batang Kelapa uk. Ø 20/25 cm Btg 190,000 - - - 190,000 - - 3.00 20,000 400 20,400 I-a
17 Kayu Bulat Ø 7 - 8 cm; 3,5 m (dolo-dolo) Btg 8,400 - - - 8,400 - - 3.00 1,600 100 1,700 I-a
18 Kayu Bulat Ø 10-15 cm; 3,5 m Btg 12,000 - - - 12,000 - - 3.00 3,300 100 3,400 I-a
19 Papan Bekisting,uk. 0.20 m x 0.02 m x 2.0 m Lbr 19,000 - 1,900 300 21,200 - - 3.00 900 100 1,000 I-a
20 Kayu segi/Broti, uk. 5 - 7 cm. Pjg. 3.00 M' Btg 25,000 - 2,500 400 27,900 - - 3.00 1,200 100 1,300 I-a
B2. MATERIAL (PABRIKASI / TOKO / DISTRIBUTOR)
1 Semen Portland @50 kg Type PCC Zak 89,000 - 8,900 1,400 99,300 - - - - - 10,000 I-b
2 Kawat Beton/Kawat Ikat Kg 26,000 - 2,600 400 29,000 - - - - - - I-b
3 Kawat Bronjong Pabrikasi Type - 1 Unit 338,000 - 33,800 5,100 376,900 20.00 5,500 10.00 3,700 200 9,400 I-b
4 Kawat Bronjong Pabrikasi Type - 2 Unit 538,000 - 53,800 8,100 599,900 20.00 8,300 10.00 5,600 300 14,200 I-b
5 Kawat Bronjong Pabrikasi Type - 3 Unit 700,000 - 70,000 10,500 780,500 20.00 11,300 10.00 7,600 400 19,300 I-b
6 Paku Biasa Kg 17,900 - 1,800 300 20,000 - - - - - - I-b
7 Aspal Kg 12,100 - 1,300 200 13,600 20.00 300 10.00 200 100 600 I-b
8 Minyak Solar (Non Subsidi) Ltr 9,400 - - - 9,400 - - - - - - I-b
9 Minyak Bakar / Tanah (Non Subsidi) Ltr 11,200 - - - 11,200 - - - - - - I-b
10 Minyak Bensin Ltr 6,500 - - - 6,500 - - - - - - I-b
11 Minyak Pelumas/Olie Ltr 40,000 - 4,000 600 44,600 - - - - - - I-b
12 Minyak Bekisting Kg 9,000 - 900 200 10,100 - - - - - - I-b
13 Geotextile Non Woven 250 gr/m2 (4mx100m) Roll 12,000,000 - 1,200,000 180,000 13,380,000 20.00 39,700 10.00 27,000 1,400 68,100 I-b
Biaya angkut dengan truk
PAJAK MBLB PPN PPh 22 HARGA TOTAL PPh 23 BIAYA TOTAL
Harga
BAHAN, Bukit ONGKOS
Bahan/Material, Alat
MATERIAL DAN ANGKUT Kategori
No Jenis Bahan Sat. Sedang Jelek
ALAT BANTU DENGAN TRUK Biaya
di Quarry/toko
(Termasuk Pajak) (Termasuk Pajak)
25% 10% 1,5 % Jarak Angkut Ongkos Angkut Jarak Angkut Ongkos Angkut 2%

(Rp.) (Rp.) (Rp.) (Rp.) (Rp.) (Km) (Rp.) (Km) (Rp.) (Rp.) (Rp.)
C. ALAT BANTU (TOKO / DISTRIBUTOR)
1 Meteran uk. 5.0 m Bh 27,000 - 2,700 500 30,200 - - - - - - II - a
2 Meteran uk. 50.0 m Bh 57,000 - 5,700 900 63,600 - - - - - - II - a
3 Sendok Semen Bh 26,900 - 2,700 500 30,100 - - - - - - II - a
4 Raskam Besi Bh 45,000 - 4,500 700 50,200 - - - - - - II - a
5 Raskam Plastik Bh 30,000 - 3,000 500 33,500 - - - - - - II - a
6 Sekop besar + gagang Bh 102,000 - 10,200 1,600 113,800 - - - - - - II - a
7 Cangkul + gagang Bh 102,000 - 10,200 1,600 113,800 - - - - - - II - a
8 Martil Batu Uk. 3 Kg (godam) Bh 199,200 - 20,000 3,000 222,200 - - - - - - II - a
9 Tembilang/penggali + gagang Bh 60,000 - 6,000 900 66,900 - - - - - - II - a
10 Pecok/Bolak baling + gagang Bh 125,000 - 12,500 1,900 139,400 - - - - - - II - a
11 Linggis Ulir Bh 35,000 - 3,500 600 39,100 - - - - - - II - a
12 Palu/Penokok Bh 42,000 - 4,200 700 46,900 - - - - - - II - a
13 Drum Plastik 200 ltr (Tampungan Air Hujan) Bh 294,400 - 29,500 4,500 328,400 - - - - - - II - a
14 Selang Ukur Glg 15,000 - 1,500 300 16,800 - - - - - - II - a
15 Tenda / Terpal Plastik A2 uk. 4 x 6 m Lbr 150,000 - 15,000 2,300 167,300 - - - - - - II - a
16 Sarung Tangan Pekerja (karet) Psg 13,200 - 1,400 200 14,800 - - - - - - II - a
17 Gerobak Sorong Unit 543,000 - 54,300 8,200 605,500 - - - - - - II - a
18 Plengki Rotan Bh 18,500 - 1,900 300 20,700 - - - - - - II - a
19 Ember Cor Bh 12,000 - 1,200 200 13,400 - - - - - - II - a
20 Kaleng Siram Aspal Bh 30,000 - 3,000 500 33,500 - - - - - - II - a
21 Gayung Aspal (kaleng) Bh 14,950 - 1,500 300 16,750 - - - - - - II - a
22 Gergaji Bh 45,000 - 4,500 700 50,200 - - - - - - II - a
23 Waterpass Bh 51,000 - 5,100 800 56,900 - - - - - - II - a
24 Unting unting Bh 20,000 - 2,000 300 22,300 - - - - - - II - a
25 Tang Kakak tua (pengikat kawat) Bh 38,425 - 3,900 600 42,925 - - - - - - II - a
26 Pahat Batu Bh 20,000 - 2,000 300 22,300 - - - - - - II - a
27 Benang Tukang (Nilon) Glg 15,000 - 1,500 300 16,800 - - - - - - II - a

SISOBALAURU, 2021

DISETUJUI OLEH : DIVERIFIKASI OLEH : DIBUAT OLEH :


Pj. KEPALA DESA SEKRETARIS DESA TIM PELAKSANA KEGIATAN

WA'OZISOKHI WARUWU, S.Pd.SD SIASA NDRAHA OTONI NDRAHA


Ketua
Sumber Quarry/toko

KEC. HILIDUHO (Ds. Sisobahili)


KEC. HILIDUHO (Ds. Sisobahili)
KEC. HILIDUHO (Ds. Sisobahili)
KEC. HILIDUHO (Ds. Sisobahili)
KEC. HILIDUHO (Ds. Hiligodu)
KEC. HILIDUHO (Ds. Ononamolo-I)
KEC. HILIDUHO (Ds. Ononamolo-I)
KEC. HILIDUHO (Ds. Ononamolo-I)
KEC. HILIDUHO (Ds. Ononamolo-I)
KEC. HILIDUHO (Ds. Ononamolo-I)
KEC. HILIDUHO (Ds. Ononamolo-I)
KEC. HILIDUHO
KEC. HILIDUHO
KEC. HILIDUHO
KEC. HILIDUHO
KEC. HILIDUHO
KEC. HILIDUHO
KEC. HILIDUHO
KEC. HILIDUHO
KEC. HILIDUHO

GUNUNGSITOLI
GUNUNGSITOLI
GUNUNGSITOLI
GUNUNGSITOLI
GUNUNGSITOLI
GUNUNGSITOLI
GUNUNGSITOLI
GUNUNGSITOLI
GUNUNGSITOLI
GUNUNGSITOLI
GUNUNGSITOLI
GUNUNGSITOLI
GUNUNGSITOLI
Sumber Quarry/toko

GUNUNGSITOLI
GUNUNGSITOLI
GUNUNGSITOLI
GUNUNGSITOLI
GUNUNGSITOLI
GUNUNGSITOLI
GUNUNGSITOLI
GUNUNGSITOLI
GUNUNGSITOLI
GUNUNGSITOLI
GUNUNGSITOLI
GUNUNGSITOLI
GUNUNGSITOLI
GUNUNGSITOLI
GUNUNGSITOLI
GUNUNGSITOLI
GUNUNGSITOLI
GUNUNGSITOLI
GUNUNGSITOLI
GUNUNGSITOLI
GUNUNGSITOLI
GUNUNGSITOLI
GUNUNGSITOLI
GUNUNGSITOLI
GUNUNGSITOLI
GUNUNGSITOLI
GUNUNGSITOLI
DAFTAR ANALISA HARGA MOBILISASI, DEMOBILISASI DAN SEWA ALAT BERAT

DESA : SISOBALAURU
KECAMATAN : HILIDUHO
KABUPATEN / KOTA : NIAS
PROVINSI : SUMATERA UTARA
NO. RAB :
BIDANG : PEMBANGUNAN DESA
PPh 23

Harga Sewa, Mobilisasi


Keterangan
No Uraian Sat. Harga (Rp.) Dan Demobilisasi + Dibulatkan Jumlah Harga (Rp.)
Produktifitas
PPh
2 1 HARI = 5 JAM
D. SEWA ALAT BERAT : % KERJA

1 Mesin gilas roda besi 6 - 8 T Jam 348,400.00 6,900.00 355,300.00 355,300.00 355,300.00

2 Mobilisasi Ls 7,600,000.00 152,000.00 7,752,000.00 7,752,000.00 7,752,000.00 1 KALI


(ANL. K -
3 Demobilisasi Ls 7,600,000.00 152,000.00 7,752,000.00 7,752,000.00 7,752,000.00 BM 1Thn.1995)
KALI

SISOBALAURU, 2021

DISETUJUI OLEH : DIVERIFIKASI OLEH : DIBUAT OLEH :


Pj. KEPALA DESA SEKRETARIS DESA TIM PELAKSANA KEGIATAN

WA'OZISOKHI WARUWU, S.Pd.SD SIASA NDRAHA OTONI NDRAHA


Ketua
URAIAN ANALISA ALAT BERAT

DESA : SISOBALAURU
KECAMATAN : HILIDUHO
KABUPATEN / KOTA : NIAS
PROVINSI : SUMATERA UTARA
NO. RAB :
BIDANG : PEMBANGUNAN DESA

No. URAIAN KODE KOEF. SATUAN KET.

A. URAIAN PERALATAN
1. Jenis Peralatan THREE WHEEL ROLLER 6-8 T E16
2. Tenaga Pw 60.0 HP
3. Kapasitas Cp 8.0 Ton
4. Alat Baru : a. Umur Ekonomis A 5.0 Tahun
b. Jam Kerja Dalam 1 Tahun W 2,000.0 Jam
c. Harga Alat B 800,000,000 Rupiah
5. Alat Yang Dipakai : a. Umur Ekonomis A' 5.0 Tahun Alat Baru
b. Jam Kerja Dalam 1 Tahun W' 2,000.0 Jam Alat Baru
c. Harga Alat (*) B' 800,000,000 Rupiah Alat Baru

B. BIAYA PASTI PER JAM KERJA


1. Nilai Sisa Alat = 10 % x B C 80,000,000 Rupiah

2. Faktor Angsuran Modal = i x (1 + i)^A' D 0.33438 -


(1 + i)^A' - 1
3. Biaya Pasti per Jam :
a. Biaya Pengembalian Modal = ( B' - C ) x D E 120,376.69 Rupiah
W'

b. Asuransi, dll = 0.002 x B' F 800.00 Rupiah


W'

Biaya Pasti per Jam = (E+F) G 121,176.69 Rupiah

C. BIAYA OPERASI PER JAM KERJA

1. Bahan Bakar = (0.125-0.175 Ltr/HP/Jam) x Pw x Ms H 70,500.00 Rupiah

2. Pelumas = (0.01-0.02 Ltr/HP/Jam) x Pw x Mp I 26,760.00 Rupiah

3. Perawatan dan (12,5 % - 17,5 %) x B K 50,000.00 Rupiah


perbaikan = W'

4. Operator = ( 1 Orang / Jam ) x U1 L 60,000.00 Rupiah


5. Pembantu Operator = ( 1 Orang / Jam ) x U2 M 20,000.00 Rupiah

Biaya Operasi per Jam = (H+I+K+L+M) P 227,260.00 Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) S 348,400.00 Rupiah

E. LAIN - LAIN
1. Tingkat Suku Bunga i 20.00 % / Tahun
2. Upah Operator / Sopir U1 60,000.00 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 20,000.00 Rp./Jam
4. Bahan Bakar Bensin Mb 6,500.00 Liter
5. Bahan Bakar Solar Ms 9,400.00 Liter
6. Minyak Pelumas Mp 44,600.00 Liter

SISOBALAURU, 2021

DISETUJUI OLEH : DIVERIFIKASI OLEH : DIBUAT OLEH :


Pj. KEPALA DESA SEKRETARIS DESA TIM PELAKSANA KEGIATAN
WA'OZISOKHI WARUWU, S.Pd.SD SIASA NDRAHA OTONI NDRAHA
Ketua
ALAT BANTU

PEKERJAAN BRONJONG PEKERJAAN TPT


Meter, uk. Pjg. 5 m Bh 2.00 Meter, uk. Pjg. 5 m Bh
Meter, uk. Pjg. 50 m Bh 1.00
Gerobak sorong Unit 4.00 Gerobak sorong Unit
Sekop besar Bh 3.00 Sekop besar Bh
Raskam besi Bh
Raskam Plastik Bh
Cangkul Bh 3.00 Cangkul Bh
Tembilang Bh 3.00 Tembilang Bh
Ember cor Bh
Flongky Bh 6.00
Sendok Semen Bh
Martil uk. 3 Kg Bh 3.00 Martil uk. 3 Kg Bh

Linggis Ulir Btg 2.00 Linggis Ulir Btg


Pecok/bolak balik Bh 2.00 Pecok/bolak balik Bh
Tenda Plastik uk. 4 x 6 m Lbr
Sarung Tangan Pekerja Bh 8.00 Sarung Tangan Pekerja Bh
Selang Ukur Glg 1.00 Selang Ukur Glg
Palu/Penokok Bh 1.00 Palu/Penokok Bh
Ember Viber (Tampungan Air) Bh
Benang Tukang Glg 2.00 Benang Tukang Glg
JUMLAH
PT PEKERJAAN JALAN
1.00 Meter, uk. Pjg. 5 m Bh 1.00 4.00
Meter, uk. Pjg. 50 m Bh 1.00 2.00
1.00 Gerobak sorong Unit 1.00 6.00
1.00 Sekop besar Bh 1.00 5.00
4.00 4.00
5.00 5.00
1.00 Cangkul Bh 1.00 5.00
1.00 4.00
36.00 36.00
Flongky Bh 6.00 12.00
6.00 6.00
1.00 4.00
Gayung Aspal Bh 1.00 1.00
Kaleng Penyiram Aspal Bh 4.00 4.00
2.00 4.00
2.00 4.00
3.00 3.00
8.00 Sarung Tangan Pekerja Bh 8.00 24.00
1.00 2.00
1.00 2.00
1.00 1.00
1.00 3.00
DAFTAR HARGA SATUAN UPAH TENAGA KERJA
BAHAN / MATERIAL DAN PERALATAN

PROVINSI : SUMATERA UTARA


KABUPATEN / KOTA :
KECAMATAN :
DESA :
JENIS KEGIATAN :
VOLUME PENANGANAN :
SUMBER DANA :
BIAYA :
TAHUN ANGGARAN :

I. Harga satuan upah sehari


Orang/hari
Kode
No. Uraian Keterangan
(Rp.)
1 Pekerja 65,000.00
2 Tukang 80,000.00
3 Kepala tukang 90,000.00

II. Harga satuan bahan / material

No. Uraian Satuan volume Kode Harga / m3 (Rp.) Keterangan

1 Batu utuh m3 349,226.00


2 Batu pecah 1 - 2 cm m3 693,030.00
3 Batu belah uk. 10 -15 cm m3 354,226.00
4 Batu pecah 5 - 7 cm m3 469,489.00
5 Batu pecah 3 - 5 cm m3 539,489.00
6 Batu pecah 2 - 3 cm m3 539,226.00
7 Kerikil sungai (tidak disaring) m3 265,966.00
8 Pasir pasangan m3 275,966.00
9 Pasir urug m3 235,966.00
10 Pasir beton m3 275,966.00
11 Sirtu m3 250,966.00
12 Tanah timbunan pilihan m3 181,664.00
13 Tanah timbunan setempat m3 30,000.00
14 Aspal kg 11,297.85
15 Minyak bakar ltr 9,150.00
16 Semen zak 82,503.00 1 zak = 50 kg
17 Kawat bronjong kg 20,287.31
18 Paku biasa uk. 1" - 4" / Kg kg 15,287.31
19 Besi beton polos kg 12,387.31
20 Alat bantu set 175,000.00
21 Kayu sembarang m3 1,573,898.00
22 Papan kayu jenis keras m3 2,798,306.00
23 Agregrat disaring untuk anal.K-523 m3 508,639.75
24 Cat menie kg 29,750.00
25 Ter kayu kg 9,000.00
26 Kawat beton kg 20,287.31
27 Besi WF kg 16,787.31
28 Besi [ dan besi L kg 8,787.31
29 Baut + plat kuku (segala ukuran) Bh 11,787.31
30 Kawat Bronjong Galvanis Pabrikasi Type I kg 424,022.34
31 Kawat Bronjong Galvanis Pabrikasi Type II kg 711,033.51
32 Kawat Bronjong Galvanis Pabrikasi Type III kg 973,188.34

III. Harga satuan peralatan


Satuan Sewa / jam
Kode
No. Uraian Keterangan
volume (Rp.)
1 Mesin gilas roda besi 6 - 8 ton jam 273,514.19
2 Tamper 4 HP jam E-25 42,284.06
3 Pengaduk beton 250 ltr / 10 HP jam E-06 49,478.62
4 Pompa air (dia. 50 mm) 30 m3 / jam jam E-22 44,005.49
5 Alat penggetar beton 4 HP jam E-20 41,156.04
6 Motor grader 110 HP jam E-13 409,661.63
7 Dump truk 2 - 3 Ton jam E-08 192,492.20
8 Truk 3 Ton jam E-09 326,767.08
9 Asphalt Sprayer jam E-03 62,725.94
10 Excavator jam E-10 540,017.14
DAFTAR ANALISA HARGA SATUAN BAHAN DAN ALAT
PEKERJAAN KEGIATAN FISIK DANA DESA TA.2020
PROVINSI : SUMATERA UTARA
KABUPATEN : NIAS
KECAMATAN : HILIDUHO
DESA : SISOBALAURU
Harga Bahan,PAJAK MBLB PPN PPH 21 Harga
Satuan Ongkos
Alat di Angkut
Bahan Jarak
No Jenis Bahan Sat. Tangkahan/ 25% 10% 1,5 % Mobil/Truck
Termasuk Angkut
Quarry
Pajak
(Rp.) (Rp.) (Rp.) (Rp.) (Rp.) (Rp.)
A. BAHAN :
1. MATERIAL BAHAN LOKAL
1.1 Batu Gunung M³ 121,500 30,400 - - 151,900 10.00 280,000
1.2 Batu Gunung M³ 121,500 30,400 - - 151,900 10.00 280,000
1.3 Batu Kali/Su M³ 115,000 28,800 - - 143,800 0.78 -
1.3 Batu Pecah 5 M³ 157,000 39,300 - - 196,300 10.00 280,000
1.4 Batu Pecah 3 M³ 181,000 45,300 - - 226,300 10.00 280,000
1.5 Batu Pecah 2 M³ 272,000 68,000 - - 340,000 10.00 280,000
1.6 Batu Kali Pec M³ 605,900 151,500 - - 757,400 11.00 290,000
1.7 Base B M³ 545,300 136,400 - - 681,700 11.00 290,000
1.8 Kerikil Sungai M³ 151,500 37,900 - - 189,400 7.00 220,000
1.9 Kerikil Sungai M³ 121,200 30,300 - - 151,500 7.00 220,000
1.10 Kepala Pasir M³ 145,400 36,400 - - 181,800 7.00 220,000
1.11 Pasir Pasang M³ 145,400 36,400 - - 181,800 7.00 220,000
1.12 Pasir Urug M³ 109,000 27,300 - - 136,300 7.00 220,000
1.13 Sirtu M³ 109,000 27,300 - - 136,300 7.00 220,000
1.14 Tanah Timbu M³ 96,000 24,000 - - 120,000 3.00 100,000
1.15 Kayu Jenis K M³ 2,787,000 696,800 - - 3,483,800 3.00 100,000
1.16 Kayu Sembara M³ 2,544,000 636,000 - - 3,180,000 3.00 100,000
1.17 Kayu Api/Kay M³ 151,000 37,800 - - 188,800 3.00 100,000
1.18 Papan Bekisti Lbr 18,000 3,600 - - 21,600 - -
1.19 Kayu segi/Brot Btg 15,000 3,800 - - 18,800 - -
2. MATERIAL PABRIKASI
2.1 Semen Portl Zak 85,000 - 8,500 1,300 94,800 40.00 10,000
2.2 Btg
Besi Beton Polos SNI 34,800 - 3,500 600 38,900 40.00 1,000
2.3 Btg
Besi Beton Polos SNI 54,500 - 5,500 900 60,900 40.00 1,000
2.4 Btg
Besi Beton Polos SNI 87,100 - 8,700 1,400 97,200 40.00 1,000
2.5 Btg
Besi Beton Polos SNI 123,800 - 12,400 1,900 138,100 40.00 1,000
2.6 Kawat Beton/ Kg 26,000 - 2,600 400 29,000 40.00 -
2.7 Paku Biasa Kg 20,000 - 2,000 300 22,300 40.00 -
2.8 Aspal Kg 12,100 - 1,300 200 13,600 40.00 600
2.9 Minyak Solar Ltr 5,500 - 600 - 6,100 - -
2.10 Minyak Bakar Ltr 18,000 - 1,800 300 20,100 - -
2.11 Minyak Bensi Ltr 6,500 - 700 - 7,300 - -
2.12 Minyak Pelum Ltr 45,000 - 4,500 700 50,200 - -
2.13 Minyak Bekis Kg 9,000 - 900 200 10,100 - -
B. ALAT
3.1 Meteran uk. Bh 30,000 - 3,000 500 33,500 - -
3.2 Sendok Sem Bh 27,500 - 2,800 400 30,700 - -
3.3 Raskam Besi Bh 45,000 - 4,500 700 50,200 - -
3.4 Raskam Plast Bh 35,000 - 3,500 600 39,100 - -
3.5 Sekop besar Bh 120,000 - 12,000 1,800 133,800 - -
3.6 Cangkul Bh 78,800 - 7,900 1,200 87,900 - -
3.7 Martil Uk. 3 Bh 80,000 - 8,000 1,200 89,200 - -
3.8 Tembilang/pe Bh 75,000 - 7,500 1,200 83,700 - -
3.9 Pecok/Bolak Bh 150,000 - 15,000 2,300 167,300 - -
3.10 Linggis Ulir Bh 140,000 - 14,000 2,100 156,100 - -
3.11 Palu/Penoko Bh 38,000 - 3,800 600 42,400 - -
3.12 Ember Viber Bh 300,000 - 30,000 4,500 334,500 - -
3.13 Selang Ukur Glg 36,000 - 3,600 700 40,300 - -
3.14 Tenda Plastik Lbr 35,000 - 3,500 500 39,000 - -
3.15 Sarung Tanga Lsn 70,000 - 7,000 1,200 78,200 - -
3.16 Gerobak Sor Unit 600,000 - 60,000 - 660,000 - -
3.17 Flongky rotan Bh 25,000 - 2,500 - 27,500 - -
3.18 Ember Cor Bh 12,000 - 1,200 - 13,200 - -
3.19 Kaleng Siram Bh 85,000 - 8,500 - 93,500 - -
3.20 Gayung Aspa Bh 111,900 - - - 111,900 - -
3.21 Benang Tukan Glg 10,000 - 1,000 - 11,000 - -

DISETUJUI/MENGESAHKAN OLEH : DIVERIFIKASI OLEH :


Pj.KEPALA DESA SEKRETARIS DESA

WA'OZISOKHI WARUWU, S.Pd.SD SIASA NDRAHA


DAFTAR HARGA SATUAN BAHAN, ALAT DAN ONGKOS ANGKUT TRUCK /
MOBIL TERMASUK PAJAK
PEKERJAAN : PENGASPALAN RUAS JALAN UMUM DESA
VOLUME : 70 M' x 3.0 M'
SUMBER DANA : DANA DESA (DDS) TA.2020
LOKASI : DUSUN II
KECAMATAN : HILIDUHO
DESA : SISOBALAURU Angkut
HARGA BAHAN DAN HARGA
Mobil/Truck
NO. URAIAN ALAT TERMASUK Jarak (Km) TOTAL SATUAN
Termasuk
PAJAK (Rp.)
A. MATERIAL BAHAN LOKAL
1 Batu Gunung belah 15-20 cm 151,900 10.00 285,600 437,500 M³
2 Batu Gunung belah 10 - 15 cm 151,900 10.00 285,600 437,500 M³
3 Batu Kali/Sungai belah 10-15 cm 143,800 0.78 - 143,800 M³
4 Batu Pecah 5 -7 cm Jenis Keras (Manual 196,300 10.00 285,600 481,900 M³
5 Batu Pecah 3-5 cm Jenis Keras (Manual) 226,300 10.00 285,600 511,900 M³
6 Batu Pecah 2-3 cm Jenis Keras (Manual) 340,000 10.00 285,600 625,600 M³
7 Batu Kali Pecah 1-2 cm Jenis Keras (Mes 757,400 11.00 295,800 1,053,200 M³
8 Base B 681,700 11.00 295,800 977,500 M³
9 Kerikil Sungai di saring, uk. 0.5 - 2 cm 189,400 7.00 224,400 413,800 M³
10 Kerikil Sungai tidak di saring 151,500 7.00 224,400 375,900 M³
11 Kepala Pasir 181,800 7.00 224,400 406,200 M³
12 Pasir Pasangan 181,800 7.00 224,400 406,200 M³
13 Pasir Urug 136,300 7.00 224,400 360,700 M³
14 Sirtu 136,300 7.00 224,400 360,700 M³
15 Tanah Timbun 120,000 3.00 102,000 222,000 M³
16 Kayu Jenis Keras 3,483,800 3.00 102,000 3,585,800 M³
17 Kayu Sembarang (Tanpa Jenis) 3,180,000 3.00 102,000 3,282,000 M³
18 Kayu Api/Kayu Bakar 188,800 - 102,000 290,800 M³
19 Papan Bekisting,uk. 0.20 m x 0.02 m x 2 21,600 - - 21,600 Lbr
20 Kayu segi/Broti, uk. 5 - 7 cm. Pjg. 3.00 M 18,800 - - 18,800 Btg
B. MATERIAL BAHAN PABRIKASI
1 Semen Portland @50 kg Type PCC 94,800 40 10,200 105,000 Zak
2 Besi Beton Polos SNI Ø 6 mm, Pjg. 12 m 38,900 40 1,000 39,900 Btg
3 Besi Beton Polos SNI Ø 8 mm, Pjg. 12 m 60,900 40 1,000 61,900 Btg
4 Besi Beton Polos SNI Ø 10 mm, Pjg. 12 m 97,200 40 1,000 98,200 Btg
5 Besi Beton Polos SNI Ø 12 mm, Pjg. 12 m 138,100 40 1,000 139,100 Btg
6 Kawat Beton/Kawat Ikat 29,000 40 - 29,000 Kg
7 Paku Biasa 22,300 40 - 22,300 Kg
8 Aspal 13,600 40 600 14,200 Kg
9 Minyak Solar 6,100 40 - 6,100 Ltr
10 Minyak Bakar 20,100 40 - 20,100 Ltr
11 Minyak Bensin 7,300 40 - 7,300 Ltr
12 Minyak Pelumas/Silender 50,200 40 - 50,200 Ltr
13 Minyak Bekisting 10,100 40 10,100 Kg
C. ALAT :
1 Meteran uk. 5.0 m 33,500 40 - 33,500 Bh
2 Sendok Semen 30,700 40 - 30,700 Bh
3 Raskam Besi 50,200 40 - 50,200 Bh
4 Raskam Plastik 39,100 40 - 39,100 Bh
5 Sekop besar 133,800 40 - 133,800 Bh
6 Cangkul 87,900 40 - 87,900 Bh
7 Martil Uk. 3 Kg 89,200 40 - 89,200 Bh
8 Tembilang/penggali 83,700 40 - 83,700 Bh
9 Pecok/Bolak baling 167,300 40 - 167,300 Bh
10 Linggis Ulir 156,100 40 - 156,100 Bh
11 Gerobak Sorong 660,000 40 - 660,000 Unit
12 Flongky rotan 27,500 40 - 27,500 Bh
13 Ember Cor 13,200 40 - 13,200 Bh
14 Kaleng Siram Aspal 93,500 40 - 93,500 Bh
15 Gayung Aspal 111,900 40 - 111,900 Bh
16 Palu/Penokok 42,400 40 - 42,400 Bh
17 Ember Viber (Tampungan Air Hujan) 334,500 40 - 334,500 Bh
18 Selang Ukur 40,300 40 - 40,300 Glg
19 Tenda Plastik uk. 4 x 6 m' 39,000 40 - 39,000 Lbr
20 Sarung Tangan Pekerja 78,200 40 - 78,200 Lsn
21 Benang Tukang 11,000 40 - 11,000 Glg
D. UPAH : Kode Harga/Jam Jlh.Jam Kerja Harga total Satuan
1 Pekerja L01 8,750 8.00 70,000 Hok
2 Tukang L02 11,250 8.00 90,000 Hok
3 Kepala Tukang L03 15,000 8.00 120,000 Hok
4 Tukang Siram Aspal L04 15,000 8.00 120,000 Hok
5 Mandor L05 13,125 8.00 105,000 Hok

DAFTAR HARGA SATUAN SEWA ALAT BERAT MESIN GILAS TERMASUK


PAJAK
(PPn+PPh23) JUMLAH TOTAL
NO. URAIAN HARGA SATUAN
2% HARGA (Rp.)
1 Vibratory Roller 6 - 8 Ton 350,715.54 7,014 357,730 357,700 Jam
2 Mobilisasi 7,500,000 150,000 7,650,000 7,650,000 Kali
3 Demobilisasi 7,500,000 150,000 7,650,000 7,650,000 Kali

DAFTAR HARGA SATUAN UPAH PIKUL/ANGKUT BAHAN MATERIAL


MENGGUNAKAN TENAGA MANUSIA
JARAK
ANGKUT JUMLAH TOTAL
NO. URAIAN HARGA SBU (Rp.) SATUAN
HARGA (Rp.)
(Km/m)
1 Batu Kali/Sungai uk. 10-15 cm 300,000 0.78 234,000 234,000 Hok/M³
2 Pasir 300,000 1.06 319,200 319,000 Hok/M³
3 Kerikil 300,000 0.90 270,000 270,000 Hok/M³
4 Semen @ 50 Kg 27,500 0.73 20,075 20,000 Hok/Zak

DAFTAR HARGA SATUAN SEWA ALAT BERAT EXCAVATOR PC 210


TERMASUK PAJAK
(PPh23) JUMLAH TOTAL
NO. URAIAN HARGA SATUAN
2% HARGA (Rp.)
1 Excavator PC 210 23,000.00 500 23,500 23,500 M³
2 Mobilisasi 8,000,000 160,000 8,160,000 8,160,000 Kali
3 Demobilisasi 8,000,000 160,000 8,160,000 8,160,000 Kali

SISOBALAURU, AGUSTUS 2020


DISETUJUI/MENGESAHKAN OLEH : DIVERIFIKASI OLEH : DIBUAT OLEH :
Pj. KEPALA DESA SEKRETARIS DESA TIM PELAKSANA KEGIATAN

WA'OZISOKHI WARUWU, S.Pd.SD SIASA NDRAHA ZULIANUS NDRAHA


Ketua
UT TRUCK /

Keterangan

Luar Desa
Luar Desa
Material Lokal
Luar Desa
Luar Desa
Luar Desa
Luar Desa
Luar Desa
Luar Desa
Luar Desa
Luar Desa
Luar Desa
Luar Desa
Luar Desa
Material Lokal
Material Lokal
Material Lokal
Material Lokal
Material Lokal
Material Lokal

Gunungsitoli
Gunungsitoli
Gunungsitoli
Gunungsitoli
Gunungsitoli
Gunungsitoli
Gunungsitoli
Gunungsitoli
Gunungsitoli
Gunungsitoli
Gunungsitoli
Gunungsitoli
Gunungsitoli

Gunungsitoli
Gunungsitoli
Gunungsitoli
Gunungsitoli
Gunungsitoli
Gunungsitoli
Gunungsitoli
Gunungsitoli
Gunungsitoli
Gunungsitoli
Gunungsitoli
Gunungsitoli
Gunungsitoli
Gunungsitoli
Gunungsitoli
Gunungsitoli
Gunungsitoli
Gunungsitoli
Gunungsitoli
Gunungsitoli
Gunungsitoli

TERMASUK

ATERIAL
KET.

Sampai Lokasi
Sampai Lokasi
Sampai Lokasi
Sampai Lokasi

OR PC 210

AGUSTUS 2020
URAIAN ANALISA ALAT

Tabel-tabel di bawah ini


No. URAIAN KODE KOEF. SATUAN KET.
Merupakan acuan untuk
HARGA
A. URAIAN PERALATAN ALAT
1. Jenis Peralatan TRAILLER 15 TON E35
2. Tenaga Pw 150.0 HP UE'
3. Kapasitas Cp 15.0 Ton ###
4. Alat Baru : a. Umur Ekonomis A 10.0 Tahun E35
b. Jam Kerja Dalam 1 Tahun W 1,500.0 Jam ###
c. Harga Alat B 115,000,000 Rupiah ###
5. Alat Yang Dipakai : a. Umur Ekonomis A' 10.0 Tahun Alat Baru
b. Jam Kerja Dalam 1 Tahun W' 1,500.0 Jam Alat Baru
c. Harga Alat (*) B' 115,000,000 Rupiah Alat Baru
###
B. BIAYA PASTI PER JAM KERJA ###
1. Nilai Sisa Alat = 10 % x B C 11,500,000 Rupiah ###
###
2. Faktor Angsuran Modal = i x (1 + i)^A' D 0.23852 - ###
(1 + i)^A' - 1 ###
3. Biaya Pasti per Jam : ###
a. Biaya Pengembalian Modal = ( B' - C ) x D E 16,458.07 Rupiah ###
W' ###
###
b. Asuransi, dll = 0.002 x B' F 153.33 Rupiah ###
W' ###
###
Biaya Pasti per Jam = (E+F) G 16,611.40 Rupiah ###
###
C. BIAYA OPERASI PER JAM KERJA ###
###
1. Bahan Bakar = (0.125-0.175 Ltr/HP/Jam) x Pw x Ms H 172,031.25 Rupiah ###
###
###
2. Pelumas = (0.01-0.02 Ltr/HP/Jam) x Pw x Mp I 13,500.00 Rupiah ###
###
3. Perawatan dan = (12,5 % - 17,5 %) x B K 9,583.33 Rupiah ###
perbaikan W' ###
4. Operator = ( 1 Orang / Jam ) x U1 L 0.00 Rupiah ###
5. Pembantu Operator = ( 1 Orang / Jam ) x U2 M 28,125.00 Rupiah ###
###
Biaya Operasi per Jam = (H+I+K+L+M) P 223,239.58 Rupiah ###
###
D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) T 239,850.99 Rupiah ###
###
###
E. LAIN - LAIN ###
1. Tingkat Suku Bunga i 20.00 % / Tahun ###
2. Upah Operator / Sopir U1 0.00 Rp./Jam ###
3. Upah Pembantu Operator / Pmb.Sopir U2 9,375.00 Rp./Jam ###
4. Bahan Bakar Bensin Mb 8,700.00 Liter ###
5. Bahan Bakar Solar Ms 9,175.00 Liter ###
6. Minyak Pelumas Mp 9,000.00 Liter ###
7. PPN diperhitungkan pada lembar Rekapitulasi ###
Biaya Pekerjaan ###
###
###
URAIAN ANALISA ALAT

Tabel-tabel di bawah ini


No. URAIAN KODE KOEF. SATUAN KET.
Merupakan acuan untuk
HARGA
A. URAIAN PERALATAN ALAT
1. Jenis Peralatan COLD MILLING (WINGET) E36
2. Tenaga Pw 125.0 HP UE'
3. Kapasitas Cp - - ###
4. Alat Baru : a. Umur Ekonomis A 10.0 Tahun E35
b. Jam Kerja Dalam 1 Tahun W 1,500.0 Jam ###
c. Harga Alat B 474,750,000 Rupiah ###
5. Alat Yang Dipakai : a. Umur Ekonomis A' 5.0 Tahun Alat Baru
b. Jam Kerja Dalam 1 Tahun W' 1,500.0 Jam Alat Baru
c. Harga Alat (*) B' 474,750,000 Rupiah Alat Baru
###
B. BIAYA PASTI PER JAM KERJA ###
1. Nilai Sisa Alat = 10 % x B C 47,475,000 Rupiah ###
###
2. Faktor Angsuran Modal = i x (1 + i)^A' D 0.33438 - ###
(1 + i)^A' - 1 ###
3. Biaya Pasti per Jam : ###
a. Biaya Pengembalian Modal = ( B' - C ) x D E 95,248.06 Rupiah ###
W' ###
###
b. Asuransi, dll = 0.002 x B' F 633.00 Rupiah ###
W' ###
###
Biaya Pasti per Jam = (E+F) G 95,881.06 Rupiah ###
###
C. BIAYA OPERASI PER JAM KERJA ###
###
1. Bahan Bakar = (0.125-0.175 Ltr/HP/Jam) x Pw x Ms H 143,359.38 Rupiah ###
###
###
2. Pelumas = (0.01-0.02 Ltr/HP/Jam) x Pw x Mp I 11,250.00 Rupiah ###
###
3. Perawatan dan = (12,5 % - 17,5 %) x B' K 39,562.50 Rupiah ###
perbaikan W' ###
4. Operator = ( 1 Orang / Jam ) x U1 L 0.00 Rupiah ###
5. Pembantu Operator = ( 1 Orang / Jam ) x U2 M 28,125.00 Rupiah ###
###
Biaya Operasi per Jam = (H+I+K+L+M) P 222,296.88 Rupiah ###
###
D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) T 318,177.93 Rupiah ###
###
###
E. LAIN - LAIN ###
1. Tingkat Suku Bunga i 20.00 % / Tahun ###
2. Upah Operator / Sopir U1 0.00 Rp./Jam ###
3. Upah Pembantu Operator / Pmb.Sopir U2 9,375.00 Rp./Jam ###
4. Bahan Bakar Bensin Mb 8,700.00 Liter ###
5. Bahan Bakar Solar Ms 9,175.00 Liter ###
6. Minyak Pelumas Mp 9,000.00 Liter ###
7. PPN diperhitungkan pada lembar Rekapitulasi ###
Biaya Pekerjaan ###
###
###
URAIAN ANALISA ALAT
###
###
No. URAIAN KODE KOEF. SATUAN KET.
> 15th ?
Kondisi Alat
A. URAIAN PERALATAN Nilai B' dari
1. Jenis Peralatan ROCK DRILL BREAKER E37
2. Tenaga Pw 3.0 HP
3. Kapasitas Cp - - ###
4. Alat Baru : a. Umur Ekonomis A 10.0 Tahun E38
b. Jam Kerja Dalam 1 Tahun W 1,500.0 Jam ###
c. Harga Alat B 27,721,250 Rupiah ###
5. Alat Yang Dipakai : a. Umur Ekonomis A' 5.0 Tahun Alat Baru
b. Jam Kerja Dalam 1 Tahun W' 1,500.0 Jam Alat Baru
c. Harga Alat (*) B' 27,721,250 Rupiah Alat Baru
###
B. BIAYA PASTI PER JAM KERJA ###
1. Nilai Sisa Alat = 10 % x B C 2,772,125 Rupiah ###
###
2. Faktor Angsuran Modal = i x (1 + i)^A' D 0.33438 - ###
(1 + i)^A' - 1 ###
3. Biaya Pasti per Jam : ###
a. Biaya Pengembalian Modal = ( B' - C ) x D E 5,561.65 Rupiah ###
W' > 15th ?
Kondisi Alat
b. Asuransi, dll = 0.002 x B' F 36.96 Rupiah Nilai B' dari
W' Depresiasi

Biaya Pasti per Jam = (E+F) G 5,598.62 Rupiah ###


E39
C. BIAYA OPERASI PER JAM KERJA ###
###
1. Bahan Bakar = (0.125-0.175 Ltr/HP/Jam) x Pw x Ms H 3,440.63 Rupiah ###
###
###
2. Pelumas = (0.01-0.02 Ltr/HP/Jam) x Pw x Mp I 270.00 Rupiah ###
###
3. Perawatan dan = (12,5 % - 17,5 %) x B K 2,310.10 Rupiah ###
perbaikan W' ###
4. Operator = ( 1 Orang / Jam ) x U1 L 0.00 Rupiah ###
5. Pembantu Operator = ( 1 Orang / Jam ) x U2 M 28,125.00 Rupiah ###
###
Biaya Operasi per Jam = (H+I+K+L+M) P 34,145.73 Rupiah ###
> 15th ?
D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) T 39,744.34 Rupiah Kondisi Alat
Nilai B' dari
Depresiasi
E. LAIN - LAIN
1. Tingkat Suku Bunga i 20.00 % / Tahun ###
2. Upah Operator / Sopir U1 0.00 Rp./Jam E40
3. Upah Pembantu Operator / Pmb.Sopir U2 9,375.00 Rp./Jam ###
4. Bahan Bakar Bensin Mb 8,700.00 Liter ###
5. Bahan Bakar Solar Ms 9,175.00 Liter ###
6. Minyak Pelumas Mp 9,000.00 Liter ###
7. PPN diperhitungkan pada lembar Rekapitulasi ###
Biaya Pekerjaan ###
###
DAFTAR
HARGA DASAR SATUAN UPAH
HARGA
No. URAIAN KODE SATUAN SATUAN KETERANGAN
( Rp.)

1. Pekerja L01 Jam 9,375.00 75,000.00 / hari

2. Tukang L02 Jam 10,000.00 80,000.00 / hari

3. Mandor L03 Jam 10,000.00 80,000.00 / hari

4. Operator L04 Jam 0.00 0.00 / hari

-Mesin Gilas L04 Jam 18,750.00 150,000.00 / hari

-Excavator L04 Jam 21,875.00 175,000.00 / hari

-AMP (Asphalt Mixing Plant) L04 Jam 25,000.00 200,000.00 / hari

5. Pembantu Operator L05 Jam 9,375.00 75,000.00 / hari

6. Sopir / Driver L06 Jam 11,250.00 90,000.00 / hari

7. Pembantu Sopir / Driver L07 Jam 8,125.00 65,000.00 / hari

8. Mekanik L08 Jam 25,000.00 200,000.00 / hari

9. Pembantu Mekanik L09 Jam 8,125.00 65,000.00 / hari

10. Kepala Tukang L10 Jam 11,250.00 90,000.00 / hari

11.

12.

DAFTAR
HARGA DASAR SATUAN BAHAN
HARGA
No. URAIAN KODE SATUAN SATUAN KETERANGAN
( Rp.)

1 Bensin M20 LITER 8,700.00 Pertamina

2 Solar M21 LITER 9,175.00 Pertamina

3 Minyak Pelumas / Olie M22 LITER 9,000.00 Pertamina

4 Minyak tanah LITER 9,150.00 Pertamina


INFORMASI UMUM
No. URAIAN INFORMASI

1. Nomor Paket Kontrak :

2. Nama Paket Pembangunan / peningkatan lanjutan jalan ruas Hiliweto -


Lasara Siwalubanua, Kec. Ma'u
3. Propinsi / Kabupaten / Kotamadya : SUMATERA UTARA / NIAS

4. Lokasi pekerjaan Periksa lampiran

5. Kondisi jalan lama ..............................

6. Panjang efektif ( lihat sketsa di bawah ) 14.0 Kilometer ( Leff = a + b )

7. Lebar jalan lama ( bahu + perkerasan + bahu ) ( 0.50 + 3.00 + 0.50 )

8. Lebar Rencana ( bahu + perkerasan + bahu ) ( 0.50 + 3.00 + 0.50 )

9. Penampang jalan, jenis dan volume pekerjaan pokok Lihat lampiran.

10. Jangka waktu pelaksanaan pekerjaan 180 hari kalender


Atau : 6.00 bulan (Periode Pelaksanaan)

11. Jarak rata-rata Base Camp ke lokasi pekerjaan ---> L= 4.50 Kilometer

Perhitungan didasarkan pada sketsa di bawah ini : L = { (c+a/2)*a + (c+b/2)*b } / (a+b)

7.00 Km = a C 7.00 Km = b
A B
1.00 Km = c
Base Camp --------->
D
Kalkulasi Jarak Rata-Rata =

12. Jam kerja efektif dalam 1 hari 7.0 jam


13. Asuransi, Pajak, dsb. untuk Peralatan 0.002 x Harga Pokok Alat
14. Tingkat Suku Bunga Investasi Alat 20.00 %
15. Biaya Umum dan Keuntungan 11.80 % x Biaya Langsung
16. RINGKASAN METHODE PELAKSANAAN

a. Mobilisasi dilaksanakan sesuai ketentuan yang berlaku dalam Kontrak.

b. Pekerjaan Tanah dilaksanakan untuk . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .


...........................................................................
c. Pekerjaan Lapis Pondasi Agregat dilaksanakan untuk . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
...........................................................................
d. Pekerjaan Campuran Aspal Panas dilaksanakan untuk . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
...........................................................................
e. Pekerjaan Pasangan Batu dilaksanakan untuk . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
...........................................................................
f. Pekerjaan Pengembalian Kondisi dilaksanakan untuk . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
...........................................................................
g. ...........................................................................
...........................................................................

17. Lokasi Quarry Periksa lampiran.

18 Jumlah Jembatan = ...................... Buah Periksa lampiran.

19 Total Bentang Jembatan = .................. Buah Periksa lampiran.

20 ....................................

21 ....................................

22 ....................................
ORMASI

an lanjutan jalan ruas Hiliweto -


a'u

.............

meter

meter

ode Pelaksanaan)
ANALISA HARGA SATUAN PEKERJAAN

Analisa : Tambahan I
Pekerjaan : Bronjong kawat galvanis pabrikasi
Satuan : M3

TYPE I : Ukuran 2 x 1 x 0,5 m, Ø 2,7 mm


HARGA ( Rp. )
NO. URAIAN PEKERJAAN SATUAN VOLUME
SATUAN

A. UPAH
1. Pekerja Org/Hari 1.500 65,000.00
2. Mandor Org/Hari 0.025 80,000.00

Sub Total A

B. BAHAN
1. Batu kali M3 1.100 349,226.00
2. Kawat bronjong pabrikasi Type I Unit 1.000 424,022.34
Sub Total B

C. PERALATAN

Sub Total C

D. Jumlah Sub Total


E. Keuntungan dan Overhead ( 15 % * D )
F. Perda No. 6 Tahun 2011
G. Total
H. Harga Satuan Pekerjaan(Dibulatkan)
ANALISA HARGA SATUAN PEKERJAAN

Analisa : Tambahan II
Pekerjaan : Bronjong kawat galvanis pabrikasi
Satuan : M3

TYPE II : Ukuran 3 x 1 x 0,5 m, Ø 2,7 mm


NO. HARGA ( Rp. )
URAIAN PEKERJAAN SATUAN VOLUME
SATUAN

A. UPAH
1. Pekerja Org/Hari 2.250 65,000.00
2. Mandor Org/Hari 0.038 80,000.00

Sub Total A

B. BAHAN
1. Batu kali M3 1.100 349,226.00
2. Kawat bronjong pabrikasi Type II Unit 0.667 711,033.51
Sub Total B

C. PERALATAN

Sub Total C

D. Jumlah Sub Total


E. Keuntungan dan Overhead ( 15 % * D )
F. Perda No. 6 Tahun 2011
G. Total
H. Harga Satuan Pekerjaan(Dibulatkan)
ANALISA HARGA SATUAN PEKERJAAN

Analisa : Tambahan III


Pekerjaan : Bronjong kawat galvanis pabrikasi
Satuan : M3

TYPE III : Ukuran 3 x 1,5 x 0,5 m, Ø 2,7 mm


NO. HARGA ( Rp. )
URAIAN PEKERJAAN SATUAN VOLUME
SATUAN

A. UPAH
1. Pekerja Org/Hari 3.375 65,000.00
2. Mandor Org/Hari 0.056 80,000.00

Sub Total A

B. BAHAN
1. Batu kali M3 1.100 349,226.00
2. Kawat bronjong pabrikasi Type III Unit 0.444 973,188.34
Sub Total B

C. PERALATAN

Sub Total C

D. Jumlah Sub Total


E. Keuntungan dan Overhead ( 15 % * D )
F. Perda No. 6 Tahun 2011
G. Total
H. Harga Satuan Pekerjaan(Dibulatkan)
NALISA HARGA SATUAN PEKERJAAN

HARGA ( Rp. )
TOTAL

97,500.00
2,000.00

99,500.00

384,148.60
424,022.34
808,170.94

907,670.94
136,150.64
22,000.00
1,065,821.58
1,065,821.00
NALISA HARGA SATUAN PEKERJAAN

HARGA ( Rp. )
TOTAL

146,250.00
3,040.00

149,290.00

384,148.60
474,259.35
858,407.95

1,007,697.95
151,154.69
22,000.00
1,180,852.64
1,180,852.00
NALISA HARGA SATUAN PEKERJAAN

HARGA ( Rp. )
TOTAL

219,375.00
4,480.00

223,855.00

384,148.60
432,095.62
816,244.22

1,040,099.22
156,014.88
22,000.00
1,218,114.10
1,218,114.00
REKAPITULASI BIAYA
PROPINSI : SUMATERA UTARA
KABUPATEN : NIAS
DINAS : PEKERJAAN UMUM KABUPATEN NIAS
NAMA PROYEK : SUMATERA UTARA

JUMLAH BIAYA
NO URAIAN PEKERJAAN
(Rp.)

I. #REF! #REF!

II. #REF! #REF!

III. #REF! #REF!

IV. #REF! #REF!

V. #REF! #REF!

VI. #REF! #REF!

JUMLAH TOTAL ( 1 + 2 + 3 + 4 + 5 + 6 ) #REF!


P P N 10 % #REF!
IURAN JAMSOSTEK #REF!
JUMLAH KESELURUHAN #REF!

Terbilang Seratus Lima Puluh Lima Juta Lima Ratus Tujuh Puluh Enam Ribu Tujuh

0
0
0

### ###
### ###

### ###
### ###
### ###
### ###
###

### ###
### ###

#REF!
#REF!

#REF!
0
RENCANA ANGGARAN BIAYA
PROVINSI : SUMATERA UTARA
KABUPATEN / KOTA :
KECAMATAN :
DESA :
JENIS KEGIATAN :
VOLUME PENANGANAN :
SUMBER DANA :
BIAYA :
TAHUN ANGGARAN :

KODE
URAIAN H. SATUAN JLH. HARGA
NO ANALISA SAT. VOLUME
PEKERJAAN
PEKERJAAN Rp. Rp.
1 2 3 4 5 6 7

I. PEKERJAAN PERSIAPAN
1 Biaya Sewa Direksikeet Los Buruh Dan Gudang - Ls 1.00 2,500,000.00 2,500,000.00
2 Biaya Pengukuran Dan Pematokan - Ls 1.00 5,000,000.00 5,000,000.00
3 Pembersihan Semak Pada Damija K-210 m2 7,475.20 3,388.00 25,325,977.60
JLH. PEK. "I" 32,825,977.60

IV. PEKERJAAN JALAN, SEP. 3737,60 M'


1 Leveling / Pasangan LPB dari telford K-516.A m3 159.68 517,461.00 82,628,172.48
2 Leveling / Pasangan LPA kelas B tebal 10 cm K-523 m3 329.34 868,248.00 285,948,796.32
3 Lapis aspal resap perekat ( Primecoat ) K-880 Ltr 27.99 13,951.00 390,542.90
4 Lapisan aspal pelekat ( tack coat ) K-881 Ltr 3,078.04 14,758.00 45,425,714.32
5 Lapis penetrasi macadam ( Lapen ) K-618 m2 11,590.00 121,535.00 1,408,590,650.00
6 Pekerjaan bahu jalan ( Tanah Setempat ) K-410 m3 261.63 137,323.00 35,928,091.14
JLH. PEK. "IV" 1,858,911,967.15

V. PEKERJAAN BANGUNAN PENDUKUNG


1 Pek. Tembok Penahan Tanah 20 tpt sep. 462 m'
P3+28 =28,00 m' kiri ; P5+31 = 13,00 m' kiri ;
P7+40 =26,00 m' kanan ; P7+96 = 65,00 m' kanan ;
P10+46 =8,00 m' kiri ; P10+67 = 4,00 m' kiri ;
P10+83 =13,00 m' kanan ; P10+98 = 14,00 m' kanan ;
P11+46 =20,00 m' kanan ; P14+25 = 30,00 m' kanan ;
P17+87 =10,00 m' kanan ; P19+80 = 10,00 m' kiri ;
P20+00 =35,00 m' kiri ; P22+62 = 17,00 m' kiri ;
P22+87 =38,00 m' kiri ; P24+11 = 14,00 m' kiri ;
P28+50 =56,00 m' kiri ; P28+50 = 43,00 m' kanan ;
P29+19 =3,00 m' kanan ; P48+25 = 15,00 m' kanan ;
3.1 Galian tanah K-224 m3 156.29 #REF! #REF!
3.2 Pasangan batu K-705 m3 389.01 #REF! #REF!
3.3 Plesteran permukaan yang nampak SNI m2 572.44 #REF! #REF!
3.4 Acian permukaan yang nampak SNI m2 572.44 #REF! #REF!
3.5 Timbunan Tanah ( Tanah Setempat ) K-225 m3 270.62 134,583.00 36,420,851.46
1 PEK. BRONJONG PENAHAN 1 TPT SEP. 18 M'
4.1 Galian Tanah K-224 m3 18.00 #REF! #REF!
4.2 Pasangan Bronjong Type I Tamb. I m3 8.00 1,065,821.00 8,526,568.00
4.3 Pasangan Bronjong Type II Tamb. II m3 46.50 1,180,852.00 54,909,618.00
4.4 Pasangan Bronjong Type III Tamb. III m3 13.50 1,218,114.00 16,444,539.00
4.5 Timbunan Tanah ( Tanah Setempat ) K-225 m3 15.56 134,583.00 2,094,111.48
JLH. PEK. "V" #REF!

VI. PEKERJAAN LAIN - LAIN


1 Biaya foto - foto proyek - - 1.00 903,603.04 903,603.04
2 Biaya papan pengenal proyek - Bh 1.00 500,000.00 500,000.00
3 Biaya mutasi peralatan P.P dan perb. ringan - - 1.00 30,000,000.00 30,000,000.00
JLH. PEK. "VI" 31,403,603.04

TOTAL FISIK ( I + II + III + IV + V + VI ) Rp. #REF!


P P N 10 % Rp. #REF!
IURAN JAMSOSTEK Rp. #REF!
JUMLAH KESELURUHAN Rp. #REF!

Terbilang : Empat Milyar Tujuh Puluh Tiga Juta Dua Ratus Empat Puluh Lima Ribu Rupiah

Gunungsitoli Selatan, Juni 2013


Direncanakan :
PT. TRANSIMA CITRA INDO CONSULTANT

Ir. KESUMA PERANGIN ANGIN Ir. MUHAMMAD MISRI


TEAM LEADER COST ESTIMATOR

Disetujui : Diperiksa :
KUASA PENGGUNA ANGGARAN (KPA) / DIREKSI LAPANGAN
PEJABAT PEMBUAT KOMITMEN (PPK) DINAS PEKERJAAN UMUM
DINAS PEKERJAAN UMUM PEMERINTAH KABUPATEN NIAS
PEMERINTAH KABUPATEN NIAS

ELIZARO LAOLI, BE YANUARI ZEBUA


NIP. 19630319 198703 1 003 NIP. 19670104 199003 1 005

Diketahui :
Plt KEPALA DINAS PEKERJAAN UMUM KABUPATEN NIAS

MAZDAN ALMAHDALI, BE
NIP 19600221 198503 1 018