T I M E S C H E D U L E

KEGIATAN : Sanimas Spald-s


DESA : Talagasari
KECAMATAN : Kadungora
KABUPATEN : Garut
PROVINSI : Jawa Barat

MINGGU KE
1 2 3 4 5 6 7 8 9 10 11 12 13
PERIODE HARI KALENDER

Bobot Pekerjaan 02/10/2023 09/10/2023 16/10/2023 23/10/2023 30/10/2023 06/11/2023 13/11/2023 20/11/2023 27/11/2023 04/12/2023 11/12/2023 18/12/2023 25/12/2023
NO JENIS PEKERJAAN Cost BOBOT (%)
(%)
s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d

08/10/2023 15/10/2023 22/10/2023 29/10/2023 05/11/2023 12/11/2023 19/11/2023 26/11/2023 03/12/2023 10/12/2023 17/12/2023 24/12/2023 30/12/2023

1 2 3 4 6 7

A BIAYA OPERASIONAL PEKERJAAN (BOP)


I ALAT TULIS KANTOR (ATK) TERMASUK MATERAI : 4,956,000.00 1.416 0.202 0.202 0.202 0.202 0.202 0.202 0.20
II PEMBUATAN DOKUMEN LPJ KMP (Cetak, Foto Copy, Jilid) 2,000,000.00 0.571 0.044 0.044 0.044 0.044 0.044 0.044 0.044 0.044 0.044 0.044 0.044 0.044 0.044
ALAT PELINDUNG DIRI DAN KESELAMATAN KERJA (APD K3)
III 6,125,000.00 1.750 0.437 0.437 0.437 0.437

IV KAMPANYE PHBS 1,400,000.00 0.400 0.200 0.200


V KEGIATAN REMBUK WARGA 1,000,000.00 0.286 0.036 0.036 0.036 0.036 0.036 0.036 0.036 0.036
VI MEDIA INFORMASI PELAKSANAAN KEGIATAN 640,000.00 0.183 0.091 0.091
VII TRANSPORT KMP 750,000.00 0.214 0.016 0.016 0.016 0.016 0.016 0.016 0.016 0.016 0.016 0.016 0.016 0.016 0.016

B PEKERJAAN BANGUNAN BILIK TOILET


I PEKERJAAN PONDASI DAN BETON 39,131,736.25 11.180 1.398 1.398 1.398 1.398 1.398 1.398 1.398 1.398
II PEKERJAAN PASANGAN DINDING 46,404,729.82 13.258 1.657 1.657 1.657 1.657 1.657 1.657 1.657 1.657
III PEKERJAAN ATAP, LISTRIK, LANTAI DAN PENGECATAN 32,800,499.97 9.372 1.339 1.339 1.339 1.339 1.339 2.678

C PEKERJAAN SEPTICTANK DAN RESAPAN


I PEKERJAAN PIPA DAN ACCESORIS 56,705,095.00 16.201 2.025 2.025 2.025 2.025 2.025 2.025 2.025 2.025
II PEKERJAAN SEPTICTANK TYPE 1 (1-5 Jiwa) 122,016,041.42 34.862 4.358 4.358 4.358 4.358 4.358 4.358 2.179 2.179 2.179 2.179
III PEKERJAAN RESAPAN 36,071,284.10 10.306 1.288 1.288 1.288 1.288 1.288 1.288 1.288 1.288

JUMLAH BOBOT 100.00

RENCANA BOBOT MINGGUAN 0.70 1.49 5.47 11.26 11.02 12.36 12.80 12.16 11.07 8.84 6.84 3.53 2.44

KUMULATIF RENCANA BOBOT MINGGUAN 0 0.70 2.19 7.66 18.92 29.95 42.31 55.11 67.27 78.35 87.19 94.03 97.56 100.00

REALISASI BOBOT MINGGUAN - - 6.99 12.16 5.34 0.44 11.63 15.53 0.30 14.11

KUMULATIF REALISASI BOBOT MINGGUAN 0 0 6.99 19.15 24.49 24.93 36.56 52.09 52.39 66.50

DEVIASI (+/-) % 6.29 16.96 16.83 6.01 6.61 9.78 (2.72) (0.77)

Rencana

Realisasi

Disetujui oleh, Di Verifikasi Oleh : Diperiksa Oleh : Dibuat Oleh :


Pejabat Pembuat Komitmen Sanitasi I Koordinator Fasilitator Fasilitator Teknik Ketua KMP Seksi Pelaksana
Satuan kerja Pelaksanaan Prasarana Permukiman SINERGI
Wilayah II Provinsi Jawa Barat

Friska Nur Afianti, S.T.,M.Eng Derry Swenlie Putra, S.T Astia Agustiani K, ST Ujang Ari Jaelani
NIP. 19870126 200912 2 003