TUGAS

CPM (CRITICAL PATH


METHOD)
KELOMPOK 2 :
ABDUL HAFIDH
RENAL DELVIANDY.T
T. SANDI REVAN NARIA
DHAHRUL MULIANDA
FATHUL SAFA MAULA
BERDASARKAN TABEL DISAMPING :
• TENTUKAN DIAGRAM CPM.
Preceeding • TENTUKAN BERAPA L AMA DURASI
Aktivity Duration
Activity PROYEK SELESAI.
• TENTUKAN TOTAL FLOAT MASING
MASING PEKERJAAN.
A - 5 • TENTUKAN JALUR KRIT IS.

B A 3

C A 4

D B,C 2

E D 5
• ME NENTUKAN
DIAGRAM CPM

0 A 5 B 8 D 10 E 15
1 2 3 5 6
0 5 8 10 15
5 3 2 5
C
4

9
4

2 . DURASI PROYE K SE LE SAI ADALAH


1 5 MINGGU
3 . TABEL TOTAL
FLOAT

Aktivity Float

A Tf 1,2 = 5 - 0 - 5 = 0

B Tf 2,3 = 8 - 5 - 3 = 0

C Tf 2,4 = -

D Tf 3,5 = 10 - 8 - 2 = 0

E Tf 5,6 = 15 - 10 - 5 = 0
4. JALUR KRITIS : 1 - 2 - 3 -
5 - 6
0 A 5 B 8 D 10 E 15
1 2 3 5 6
0 5 8 10 15
5 3 2 5
C
4

9
4