NAMA : AYU LINTANG CAHYANI

NIM : 2019710450051
MATKUL : MANAJEMEN INDUSTRI

JAWABAN POINT B
Varian
Pendahuluan t (Waktu yg Masing-
Kegiatan a m b
Langsung diharapkan) Masing
Proyek
A 1 2 3 - 2 0.1111111
B 2 3 4 - 3 0.1111111
C 4 5 6 A 5 0.1111111
D 8 9 10 B 9 0.1111111
E 2 5 8 C,D 5 1
F 4 5 6 D 5 0.1111111
G 1 2 3 E 2 0.1111111
Jumlah 1.6666667
Standar Deviasi 1.2909944

JML VARIANS PROYEK DI TITIK KRITIS = 1.333333333

DEV.STANDAR PROYEK = 1.154700538

INDEKS

ETi

AKTIFITAS KE
LTI

PENENTUAN TOTAL FLOAT

ETi ETj
ti,j

LTi LTj

RUMUS:

TF ij =LT(j)-Eti-tij

GARIS
ACTIVITY TOTAL FLOAT HASIL TF KRITIS GARS KRITIS
A TF(1,2) = 6-0-2 4 TIDAK MAKA GARIS KRITIS ADA DI AKTIVITAS
B TF (1,3) = 2-0-2 0 YA B 1-3
C TF (2,4) = 11-2-5 4 TIDAK D 3-4
D TF (3,4) =11-2-9 0 YA E 4-5
E TF (4,5) =16-11-5) 0 YA G 5-6
F TF (3,6) = 18-11-5 4 TIDAK
G TF (5,6) = 18-16-2 0 YA
JAWABAN POINT A

GARIS JARINGAN KERJA

2
A,2
C,5
E,5
1 4 5

B,2
3
6

GARIS JARINGAN KERJA DAN GARIS KRITIS

2
2
A,2
0 6
C,5
1 16
11
0
4 E,5
5
11 16
B,2 G,2
2 D,9
3
2 F,5

18
6
18