AANWIJZING

KONSTRUKSI PLTS 3
KILANG

RU II Dumai, RU IV Cilacap,
RU VI Balongan

Jl. Soekarno-Hatta No.439, Kb. Lega, Kec. Bojongloa


Kidul, Kota Bandung, Jawa Barat 40235 suryaenergi.com (022) 7351 8273 info@suryaenergi.com
OUTLINE

1. Project Overview
2. Struktur Kepemilikan Proyek
3. Scope of Work
4. Working Item & Duration
5. Manpower Plan
6. Desain Engineering Doc.
7. Persyaratan Kerja (HSE)
8. Concern Items
9. HPS
10. Submit Dok. Penawaran
02
1 Project
02 Overview

Pekerjaan PLTS Ground Mounted RU II Dumai, RU IV Cilacap, RU VI Balongan

No Location Capacity
1 PSA-Dumai 1,00 MWp
RU II Dumai
2 Perumahan-Dumai 0,77 MWp
3 Tegal Kamulyan-Cilacap 0,567 MWp
RU IV Cilacap
4 Gn. Simping-Cilacap 0,432 MWp
5 Kandang Rusa-Balongan 1,00 MWp
RU VI Balongan
6 Pemadam Kebakaran-Balongan 0,51 MWp
Total 4,2 MWp
Working Area Dumai 1 - PSA 1 MWp
Working Area Dumai 2 – Perumahan 0.77 MWp
Working Area Cilacap 1 - Komperta Tegal Kamulyan 0.56 MWp
Working Area Cilacap 2 – Komperta Gn. Simping 0.43 MWp
Working Area Balongan
Layout PV Area Balongan (1 MWp)

Layout PV Area Balongan (0,5 MWp)


02
2 Struktur
02 Kepemilikan Proyek
3 Scope of Work
SCOPE OF WORK
GENERAL WORKS:
Site Clearing & Conditioning
Mob Demob
Work Permit
CIVIL WORKS:
Pemasangan Pagar, Pintu Pagar (incl. pondasi)
Akses Internal Sites & rabat jalan
Power House
Drainase & Bak Kontrol
Foundation Structure Trafo, MV SWGR Hanya Lokasi Dumai PSA & Dumai Perumahan
Foundation Structure PJU
Pembuatan Jalur Kabel Bawah Tanah
Water Cleaning System
Instalasi Screw Pile & PV Mounting Support
MECHANICAL ELECTRICAL WORKS:
Instalasi PV Module
Instalasi Inverter
Instalasi AC Combiner
Instalasi Transformator Hanya Lokasi Dumai PSA & Dumai Perumahan
Instalasi MV Switchgear Hanya Lokasi Dumai PSA & Dumai Perumahan
Instalasi Control & Monitoring System
Instalasi PJU
Instalasi Grounding dan Penangkal Petir
Instalasi Cable Tray
Instalasi Kabel PV, Inverter, AC Combiner
Instalasi Kabel Trafo, MV SWGR Hanya Lokasi Dumai PSA & Dumai Perumahan
Instalasi Kabel Grounding
Instalasi Kabel Control & Monitoring System
Individual Test PV System
Commissioning PLTS & Sync to Existing System
02
4 Working
02 Item & Duration

Durasi Pelaksanaan Konstruksi:

Cilacap = 28 Agustus 2023 sd. 27 November 2023


Dumai = 11 September 2023 sd. 10 Desember 2023 (est.)
Balongan = 18 September 2023 sd. 17 Desember 2023 (est.)

*Durasi Konstruksi kurang lebih 3 bulan per lokasi


*Tanggal Mulai Konstruksi mengikuti estimasi tanggal rilis AMDAL
Pemasangan Pile

02
Fencing Site

4 Working
02 Item & Duration Pemasangan Tiang
Pemasangan Pagar
Power House
Pekerjaan Pondasi Power House
Pekerjaan Dinding
Pekerjaan Atap

Week Weeks Duration


Milesto ne Item Kerja Pekerjaan Pemasangan Inverter Station
Start Finish (day)
Pembuatan Jalur Kabel Bawah Tanah
Land Clearing Akses Internal Sites
Water Cleaning System Week Weeks Duration
Pengurusan Permit Milestone Item Kerja
Start Finish (day)
Mobilisasi Personil dan Tools Pemasangan Pipa
Penebangan Pohon Tapping Titik Air
Land Clearing
Instalasi Support Modul
Stripping Lahan
Mobilisasi buangan land clearing Pemasangan Support Modul
Mobilisasi Personil dan Tools
Portable Toilet/Direksi Kit Installation Pemasangan Support Railing
Penebangan
Instalasi Pohon
PV Modul
Mobilisasi Portable Toilet/Direksi Kit
Tapping Titik Air Pemasangan PV Modul
Mobilisasi buangan land clearing
Wiring/Stringing
Mounting Foundation Structure
Portable Toilet/Direksi
Instalasi Inverter Kit Installation
& Electrical Equipment
Marking
Co nstruction - PV Mobilisasi Portable Toilet/Direksi Kit
Pemasangan Pile Pemasangan Inverter
System
Fencing Site Pemasangan Panel Proteksi
Mounting
Wiring Foundation Structure
Pemasangan Tiang
Pemasangan Pagar Monitoring System
Pemasangan
Pemasangan Pile
Data Logger, sensor & CCTV
Power House
Fencing
WiringSite
Pekerjaan Pondasi Power House
Pemasangan Tiang
Grounding System
Pekerjaan Dinding
Pemasangan Pagar
Pekerjaan Atap Penangkal Petir
Power House
Individual Test PV System
Pekerjaan Finishing
Pekerjaan Pondasi &
I-V curve checking Power House Tahanan
Pengecekan
Pekerjaan Pemasangan Inverter Station
Pekerjaan
Individual ACDinding
Combiner & Monitoring System
Pembuatan Jalur Kabel Bawah Tanah
Pekerjaan Atap
Akses Internal Sites Commissioning Individual Test AC Combiner
Water Cleaning System Individual Monitoring System
Pekerjaan Pemasangan Inverter Station
Pemasangan Pipa Full Commissioning
Pembuatan JalurSystem
Sync to Existing Kabel Bawah Tanah
Tapping Titik Air
Akses Internal Sites
Instalasi Support Modul
Water Cleaning System
Pemasangan Support Modul
Pemasangan Pipa
Kontraktor agar membuat dan mengirimkan Tabel Rencana Jadwal Pekerjaan per lokasi (Cilacap, Dumai, Balongan)
Instalasi PV Modul
(Template tersedia
Pemasangan PV Modul di G Drive)
Instalasi Support Modul
Pemasangan Support Modul

Instalasi Inverter & Electrical Equipment


Instalasi PV Modul
Pemasangan Inverter
Pemasangan PV Modul
Pemasangan Panel Proteksi

Instalasi Inverter & Electrical Equipment


Monitoring System
Pemasangan Inverter
Pemasangan Data Logger, sensor & CCTV
Pemasangan Panel Proteksi

Grounding System
Monitoring System
Penangkal Petir
02
5 Manpower
02 Plan

No Minimum Personel Remarks

1 Site Leader Minimum 1 orang per lokasi

2 Civil Supervisor Minimum 1 orang per lokasi

3 Mechanical Electrical Supervisor Minimum 1 orang per lokasi

4 Civil Technician Jumlah orang menyesuaikan

5 Mechanical Electrical Technician Jumlah orang menyesuaikan

6 Civil Helper Prefer menggunakan tenaga lokal

7 Mechanical Electrical Helper Prefer menggunakan tenaga lokal

Kontraktor agar membuat dan mengirimkan Tabel Rencana Manpower per lokasi (Cilacap, Dumai, Balongan)
(Template tersedia di G Drive)
02
6 Design
02 Engineering Doc.

No Design Engineering Doc.

1 BOM

2 Datasheet Material

3 Drawing Layout

4 GA Drawing

5 SLD

6 Wiring Diagram

7 dll

Detail terkait DED dapat diakses di Folder G Drive


02
7 Work Permit (HSE)
02

Detail terkait Prosedur Permit dapat diakses di Folder G Drive


02
8 Concern
02 Items

1. Work Permit: Menggunakan resources manpower dengan persyaratan lengkap


2. Alur koordinasi tim pelaksana dengan SEI, PPI dan Kilang RU
3. Mobilisasi tim dan peralatan
4. Menggunakan tenaga lokal (disarankan yang sudah pernah mempunyai HSSE
passport di area kilang RU terkait)
02
9 HPS02

No Location Capacity HPS


1 PSA-Dumai 1,00 MWp
RU II Dumai Rp 1.090.504.000
2 Perumahan-Dumai 0,77 MWp

3 Tegal Kamulyan-Cilacap 0,567 MWp


RU IV Cilacap Rp 601.398.000
4 Gn. Simping-Cilacap 0,432 MWp

5 Kandang Rusa-Balongan 1,00 MWp


RU VI Balongan Rp 856.170.000
6 Pemadam Kebakaran-Balongan 0,51 MWp

Total 4,2 MWp Rp 2.548.072.000


02 Submit
11 02 Dokumen Penawaran

• Submit Jadwal Pelaksanaan menggunakan dokumen “Planning Pekerjaan, Manpower Planning & Productivity”
• Submit Rencana Manpower menggunakan dokumen “Planning Pekerjaan, Manpower Planning & Productivity”
• Submit Detail Penawaran Harga menggunakan dokumen “RAB KONSTRUKSI PLTS 3 KILANG”

• Template dokumen bisa diakses di G Drive:


https://drive.google.com/drive/folders/1_jKsWjQaEAQ3QMnJgzW7f6n-9gA34wDP?usp=sharing
HATUR NUHUN
TERIMA KASIH

suryaenergi.com | (022) 42830 750 | marketing@suryaenergi.com