REKAP ENGINEERING ESTIMATE ( EE )

PROYEK PEMBANGUNAN GEDUNG PELAYANAN PERIJINAN DAN PENANAMAN MODAL


KABUPATEN TEMANGGUNG
PEKERJAAN MEKANIKAL & ELEKTRIKAL

JUMLAH HARGA
NO JENIS PEKERJAAN
(Rp)
I. PEKERJAAN ELEKTRIKAL
A. TOTAL PEKERJAAN INSTALASI PENERANGAN DAN KOTAK KONTAK 197,781,275.00
B. TOTAL PEKERJAAN PANEL DAN KABEL FEEDER 81,429,765.00
C. TOTAL PEKERJAAN TAMBAH DAYA LISTRIK DARI 7,7 kVA ke 23 kVA 34,425,000.00
D. TOTAL PEKERJAAN FIRE ALARM DAN APAR #N/A
E. TOTAL PEKERJAAN TELEPON #N/A
F. TOTAL PEKERJAAN DATA KOMPUTER 11,846,175.00
G. TOTAL PEKERJAAN CCTV 57,411,800.00
H. TOTAL PEKERJAAN GENSET 168,600,000.00
I. TOTAL PEKERJAAN PENYALUR PETIR 32,188,899.50
TOTAL PEKERJAAN ELEKTRIKAL #N/A

II. PEKERJAAN MEKANIKAL PLUMBING


A. TOTAL PEKERJAAN INSTALASI AIR KOTOR, BEKAS DAN VENT 55,216,830.50
B. TOTAL PEKERJAAN INSTALASI AIR BERSIH 28,698,193.60
C. TOTAL PEKERJAAN DRAINASE AIR HUJAN 77,796,059.50
D. TOTAL PEKERJAAN TATA UDARA 205,879,281.00
TOTAL PEKERJAAN MEKANIKAL 367,590,364.60

TOTAL PEKERJAAN ELEKTRIKAL & MEKANIKAL #N/A


PPN 10 % #N/A
JUMLAH TOTAL #N/A

DIBULATKAN #N/A
URAIAN ENGINEERING ESTIMATE MEKANIKAL ELEKTRIKAL

PROGRAM : PROYEK PEMBANGUNAN GEDUNG PELAYANAN PERIJINAN DAN PENANAMAN MODAL


LOKASI : KABUPATEN TEMANGGUNG

No. Jenis Pekerjaan Vol Sat Harga Satuan Jumlah Harga Total
I. PEKERJAAN ELEKTRIKAL
A. Instalasi Penerangan dan Kotak Kontak
1. Basement
Kabel NYM 3x2.5 mm Ex Supreme dalam High Impact conduit dia. 20 mm Ex. Clipsal
1 Memasang 1 titik instalasi Penerangan 19 titik Rp 235,250.00 Rp 4,469,750.00
2 Memasang 1 bh Lampu Downligh LED 6 W 2 bh Rp 229,200.00 Rp 458,400.00
3 Memasang 1 bh Lampu Downligh Outbow LED 9 W 8 bh Rp 338,500.00 Rp 2,708,000.00
4 Memasang 1 bh Lampu TL BALK T8 1 x 36 W 15 bh Rp 353,500.00 Rp 5,302,500.00
5 Memasang 1 bh Lampu Baret Circular LED 10 W 3 bh Rp 373,500.00 Rp 1,120,500.00
6 Memasang 1 bh Lampu Emergency Exit 8 W c/w NiCad Batery 1 bh Rp 1,378,500.00 Rp 1,378,500.00
7 Memasang 1 bh Saklar Seri/Ganda 5 bh Rp 58,375.00 Rp 291,875.00
8 Memasang 1 bh Saklar Tunggal 7 bh Rp 43,375.00 Rp 303,625.00
Kabel NYM 3x2.5 mm Ex Supreme dalam High Impact conduit dia. 20 mm Ex. Clipsal
9 Memasang 1 titik instalasi Stop Kontak 5 titik Rp 235,250.00 Rp 1,176,250.00
10 Memasang 1 bh Stop Kontak 5 bh Rp 43,375.00 Rp 216,875.00

2. Lantai 1
Kabel NYM 3x2.5 mm Ex Supreme dalam High Impact conduit dia. 20 mm Ex. Clipsal
1 Memasang 1 titik instalasi Penerangan 156 titik Rp 235,250.00 Rp 36,699,000.00
2 Memasang 1 bh Lampu Downligh LED 6 W 10 bh Rp 229,200.00 Rp 2,292,000.00
3 Memasang 1 bh Lampu Downligh LED 9 W 102 bh Rp 270,900.00 Rp 27,631,800.00
4 Memasang 1 bh Lampu Downligh Spot LED 10 W 12 bh Rp 453,500.00 Rp 5,442,000.00
5 Memasang 1 bh Lampu Baret Circular LED 10 W 4 bh Rp 373,500.00 Rp 1,494,000.00
6 Memasang 1 bh Lampu RM 2 x 18 W 24 bh Rp 535,500.00 Rp 12,852,000.00
7 Memasang 1 bh Lampu Emergency Exit 8 W c/w NiCad Batery 4 bh Rp 1,378,500.00 Rp 5,514,000.00
8 Memasang 1 bh Exhaust Fan 40 W 5 bh Rp 478,500.00 Rp 2,392,500.00
9 Memasang 1 bh Saklar Seri/Ganda 23 bh Rp 58,375.00 Rp 1,342,625.00
10 Memasang 1 bh Saklar Tunggal 6 bh Rp 43,375.00 Rp 260,250.00
11 Memasang 1 bh Saklar Grid 6 Gang 3 bh Rp 215,875.00 Rp 647,625.00
Kabel NYM 3x2.5 mm Ex Supreme dalam High Impact conduit dia. 20 mm Ex. Clipsal
12 Memasang 1 titik instalasi Stop Kontak 26 titik Rp 235,250.00 Rp 6,116,500.00
13 Memasang 1 bh Stop Kontak 22 bh Rp 43,375.00 Rp 954,250.00
14 Memasang 1 bh Stop Kontak Lantai 4 bh Rp 465,875.00 Rp 1,863,500.00

3. Lantai 2
Kabel NYM 3x2.5 mm Ex Supreme dalam High Impact conduit dia. 20 mm Ex. Clipsal
1 Memasang 1 titik instalasi Penerangan 95 titik Rp 235,250.00 Rp 22,348,750.00
2 Memasang 1 bh Lampu Downligh LED 6 W 7 bh Rp 229,200.00 Rp 1,604,400.00
3 Memasang 1 bh Lampu Downligh LED 9 W 47 bh Rp 270,900.00 Rp 12,732,300.00
4 Memasang 1 bh Lampu RM 2 x 18 W 38 bh Rp 535,500.00 Rp 20,349,000.00
5 Memasang 1 bh Lampu Emergency Exit 8 W c/w NiCad Batery 2 bh Rp 1,378,500.00 Rp 2,757,000.00
6 Memasang 1 m' Lampu Strip LED 6 W / meter 25 m' Rp 203,500.00 Rp 5,087,500.00
7 Memasang 1 bh Exhaust Fan 40 W 3 bh Rp 478,500.00 Rp 1,435,500.00
8 Memasang 1 bh Saklar Seri/Ganda 21 bh Rp 58,375.00 Rp 1,225,875.00
9 Memasang 1 bh Saklar Tunggal 8 bh Rp 43,375.00 Rp 347,000.00
Kabel NYM 3x2.5 mm Ex Supreme dalam High Impact conduit dia. 20 mm Ex. Clipsal
10 Memasang 1 titik instalasi Stop Kontak 25 titik Rp 235,250.00 Rp 5,881,250.00
11 Memasang 1 bh Stop Kontak 25 bh Rp 43,375.00 Rp 1,084,375.00

TOTAL PEKERJAAN INSTALASI PENERANGAN DAN KOTAK KONTAK Rp 197,781,275.0


B. Panel dan Kabel Feeder
GEDUNG A ( DEPAN )
1 Memasang 1 unit Panel MDP uk. 600 x 800 x 400 mm 1 set Rp 11,447,485.00 Rp 11,447,485.00
2 Memasang 1 unit Panel Penerangan Basement A ( LPBS.A ) uk. 400 x 500 x 200 mm 1 set Rp 2,165,735.00 Rp 2,165,735.00
3 Memasang 1 unit Panel Penerangan Lantai 1 A ( LP1.A ) uk. 400 x 500 x 200 mm 1 set Rp 2,584,735.00 Rp 2,584,735.00
4 Memasang 1 unit Panel Penerangan Lantai 2 A ( LP2.A ) uk. 400 x 500 x 200 mm 1 set Rp 2,584,735.00 Rp 2,584,735.00
5 Memasang 1 unit Power Panel AC Lantai 1 ( PPAC 1.A ) uk. 400 x 600 x 200 mm 1 set Rp 4,129,735.00 Rp 4,129,735.00
6 Memasang 1 unit Power Panel AC Lantai 2 ( PPAC 2.A ) uk. 400 x 600 x 200 mm 1 set Rp 3,314,735.00 Rp 3,314,735.00
7 Memasang 1 unit Panel ATS/AMF 1 set Rp 17,500,000.00 Rp 17,500,000.00
8 Memasang 1 meter kabel NYFGbY 4 x 25 mm dari Jaringan PLN ke MDP 45 m' Rp 186,360.00 Rp 8,386,200.00
9 Memasang 1 meter kabel NYFGbY 4 x 25 mm dari MDP ke Panel ATS/AMF 12 m' Rp 186,360.00 Rp 2,236,320.00
10 Memasang 1 meter kabel NYFGbY 4 x 25 mm dari Genset ke Panel ATS/AMF 30 m' Rp 186,360.00 Rp 5,590,800.00
11 Memasang 1 meter kabel NYY 4 x 4 mm dari MDP ke LPBS.A 4 m' Rp 40,585.00 Rp 162,340.00
12 Memasang 1 meter kabel NYY 4 x 4 mm dari MDP ke LP1.A 28 m' Rp 40,585.00 Rp 1,136,380.00
13 Memasang 1 meter kabel NYY 4 x 6 mm dari MDP ke PPAC 1.A 32 m' Rp 65,885.00 Rp 2,108,320.00
14 Memasang 1 meter kabel NYY 4 x 4 mm dari MDP ke LP2.A 32 m' Rp 40,585.00 Rp 1,298,720.00
15 Memasang 1 meter kabel NYY 4 x 6 mm dari MDP ke PPAC 2.A 36 m' Rp 65,885.00 Rp 2,371,860.00
16 Grounding sistem 1 ls Rp 3,250,000.00 Rp 3,250,000.00

GEDUNG B ( BELAKANG )
No. Jenis Pekerjaan Vol Sat Harga Satuan Jumlah Harga Total
1 Memasang 1 unit Panel Penerangan Basement B ( LPBS.B ) - Box MCB 12 Gang 1 set Rp 1,618,245.00 Rp 1,618,245.00
2 Memasang 1 unit Panel Penerangan Lantai 1 B ( LP1.B ) - Box MCB 8 Gang 1 set Rp 933,245.00 Rp 933,245.00
3 Memasang 1 unit Panel Penerangan Lantai 2 B ( LP2.B ) - Box MCB 12 Gang 1 set Rp 1,173,245.00 Rp 1,173,245.00
4 Memasang 1 meter kabel NYY 3 x 4 mm dari LPBS.B ke KWH Meter 4400 VA 4 m' Rp 31,235.00 Rp 124,940.00
5 Memasang 1 meter kabel NYY 3 x 4 mm dari LPBS.B ke LP1.B 15 m' Rp 31,235.00 Rp 468,525.00
6 Memasang 1 meter kabel NYY 3 x 4 mm dari LPBS.B ke LP2.B 19 m' Rp 31,235.00 Rp 593,465.00
7 Pemasangan dan penyambungan ke jaringan Existing daya 4400 KVA 1 ls Rp 3,500,000.00 Rp 3,500,000.00
8 Grounding sistem 1 ls Rp 2,750,000.00 Rp 2,750,000.00

TOTAL PEKERJAAN PANEL DAN KABEL FEEDER Rp 81,429,765.0


C. Tambah Daya Listrik dari 7,7 kVA ke 23 kVA
1 Biaya Tambah Daya Listrik termasuk Administrasi 15300 VA Rp 2,250.00 Rp 34,425,000.00
TOTAL PEKERJAAN TAMBAH DAYA LISTRIK DARI 7,7 kVA ke 23 kVA Rp 34,425,000.0
D. Instalasi Fire Alarm dan APAR
1. Basement
1 Memasang 1 titik instalasi ROR Heat Detector 6 titik Rp 127,400.00 Rp 764,400.00
2 Memasang 1 bh ROR Heat Detector 6 bh Rp 204,775.00 Rp 1,228,650.00
3 Memasang 1 titik instalasi Manual Push Button 1 titik Rp 174,900.00 Rp 174,900.00
4 Memasang 1 titik instalasi Indicating Lamp 1 titik Rp 174,900.00 Rp 174,900.00
5 Memasang 1 titik instalasi Alarm Bell 1 titik Rp 174,900.00 Rp 174,900.00
6 Memasang 1 bh Manual Push Button 1 bh Rp 307,900.00 Rp 307,900.00
7 Memasang 1 bh Indicating Lamp 1 bh Rp 113,325.00 Rp 113,325.00
8 Memasang 1 bh Alarm Bell 1 bh Rp 278,475.00 Rp 278,475.00
9 Memasang 1 bh EOLR 1 bh Rp 38,325.00 Rp 38,325.00
10 Memasang 1 bh Juction Box Fire Alarm 1 unit #N/A #N/A
11 Memasang kabel feeder dari JBFA-1 ke MCFA 1 ls Rp 250,000.00 Rp 250,000.00
12 Memasang 1 bh Fire Extinguisher tipe ABC kap. 3,5 kg 2 unit Rp 1,250,000.00 Rp 2,500,000.00

2. Lantai 1
1 Memasang 1 titik instalasi ROR Heat Detector 14 titik Rp 127,400.00 Rp 1,783,600.00
2 Memasang 1 bh ROR Heat Detector 14 bh Rp 204,775.00 Rp 2,866,850.00
3 Memasang 1 titik instalasi Manual Push Button 1 titik Rp 174,900.00 Rp 174,900.00
4 Memasang 1 titik instalasi Indicating Lamp 1 titik Rp 174,900.00 Rp 174,900.00
5 Memasang 1 titik instalasi Alarm Bell 1 titik Rp 174,900.00 Rp 174,900.00
6 Memasang 1 bh Manual Push Button 1 bh Rp 307,900.00 Rp 307,900.00
7 Memasang 1 bh Indicating Lamp 1 bh Rp 113,325.00 Rp 113,325.00
8 Memasang 1 bh Alarm Bell 1 bh Rp 278,475.00 Rp 278,475.00
9 Memasang 1 bh EOLR 2 bh Rp 38,325.00 Rp 76,650.00
10 Memasang 1 bh Juction Box Fire Alarm 1 unit #N/A #N/A
11 Memasang kabel feeder dari JBFA-2 ke MCFA 1 ls Rp 550,000.00 Rp 550,000.00
12 Memasang 1 bh Fire Extinguisher tipe ABC kap. 3,5 kg 4 unit Rp 1,250,000.00 Rp 5,000,000.00
13 MCFA 5 Zone 1 unit Rp 8,750,000.00 Rp 8,750,000.00
14 Annuciator 5 Zone 1 unit Rp 3,500,000.00 Rp 3,500,000.00

3. Lantai 2
1 Memasang 1 titik instalasi ROR Heat Detector 14 titik Rp 127,400.00 Rp 1,783,600.00
2 Memasang 1 bh ROR Heat Detector 14 bh Rp 204,775.00 Rp 2,866,850.00
3 Memasang 1 titik instalasi Smoke Detector 2 titik Rp 127,400.00 Rp 254,800.00
4 Memasang 1 bh Smoke Detector 2 bh Rp 394,150.00 Rp 788,300.00
5 Memasang 1 titik instalasi Manual Push Button 1 titik Rp 174,900.00 Rp 174,900.00
6 Memasang 1 titik instalasi Indicating Lamp 1 titik Rp 174,900.00 Rp 174,900.00
7 Memasang 1 titik instalasi Alarm Bell 1 titik Rp 174,900.00 Rp 174,900.00
8 Memasang 1 bh Manual Push Button 1 bh Rp 307,900.00 Rp 307,900.00
9 Memasang 1 bh Indicating Lamp 1 bh Rp 113,325.00 Rp 113,325.00
10 Memasang 1 bh Alarm Bell 1 bh Rp 278,475.00 Rp 278,475.00
11 Memasang 1 bh EOLR 2 bh Rp 38,325.00 Rp 76,650.00
12 Memasang 1 bh Juction Box Fire Alarm 1 unit #N/A #N/A
13 Memasang kabel feeder dari JBFA-3 ke MCFA 1 ls Rp 750,000.00 Rp 750,000.00
14 Memasang 1 bh Fire Extinguisher tipe ABC kap. 3,5 kg 4 unit Rp 1,250,000.00 Rp 5,000,000.00

TOTAL PEKERJAAN FIRE ALARM DAN APAR #N/A


E. Instalasi Telepon
1. Lantai 1
1 Instalasi Telephone dg Kabel ITC 2x2x0.6 mm Ex. Supreme dlm Pipa EGA Conduit 20 mm 9 titik Rp 232,400.00 Rp 2,091,600.00
2 Memasang Direct Outlet Telephone 9 bh Rp 125,875.00 Rp 1,132,875.00
3 Memasang Handset single Telephone 9 bh Rp 350,000.00 Rp 3,150,000.00
4 Memasang 1 bh Telepon Terminal Box uk. 30x20x20 cm 1 unit #N/A #N/A
5 Instalasi Kabel Feeder ITC 10 pairs 3 m' Rp 28,485.00 Rp 85,455.00
6 Main Distrubution Fram Telepon (MDF-TP) 1 unit Rp 2,450,000.00 Rp 2,450,000.00
7 Private Automatic Branch eXchange (PABX),6 Co, 24 Extensions. 1 unit Rp 10,750,000.00 Rp 10,750,000.00

2. Lantai 2
1 Instalasi Telephone dg Kabel ITC 2x2x0.6 mm Ex. Supreme dlm Pipa EGA Conduit 20 mm 8 titik Rp 232,400.00 Rp 1,859,200.00
2 Memasang Direct Outlet Telephone 8 bh Rp 125,875.00 Rp 1,007,000.00
3 Memasang Handset single Telephone 8 bh Rp 350,000.00 Rp 2,800,000.00
4 Memasang 1 bh Telepon Terminal Box uk. 30x20x20 cm 1 unit #N/A #N/A
5 Instalasi Kabel Feeder ITC 10 pairs dari TTB-1 ke MDF-TP 20 m' Rp 28,485.00 Rp 569,700.00
No. Jenis Pekerjaan Vol Sat Harga Satuan Jumlah Harga Total

TOTAL PEKERJAAN TELEPON #N/A


F. Instalasi Data Komputer
1. Lantai 1
1 Instalasi Data komputer dg kabel UTP Cath 6 dlm pipa conduit PVC dia. 20 mm2 8 titik Rp 297,400.00 Rp 2,379,200.00
2 Memasang Outlet Data Komputer 8 bh Rp 110,875.00 Rp 887,000.00
3 Memasang Switch hub 12 port 1 unit Rp 1,350,000.00 Rp 1,350,000.00
4 Instalasi Kabel Feeder UTP Cath 6 dari Switch Hub 12 port Lantai 1 ke Switch Hub 12 port Lantai 2 50 m' Rp 16,110.00 Rp 805,500.00

2. Lantai 2
1 Instalasi Data komputer dg kabel UTP Cath 6 dlm pipa conduit PVC dia. 20 mm2 9 titik Rp 297,400.00 Rp 2,676,600.00
2 Memasang Outlet Data Komputer 9 bh Rp 110,875.00 Rp 997,875.00
3 Memasang Switch hub 12 port Managable 1 unit Rp 2,750,000.00 Rp 2,750,000.00

TOTAL PEKERJAAN DATA KOMPUTER Rp 11,846,175.0


G. Instalasi CCTV
1. Basement
1 Instalasi CCTV dg kabel RG 59 + kabel power dlm pipa conduit PVC dia. 20 mm2 2 titik Rp 662,400.00 Rp 1,324,800.00
2 Memasang In door Camera CCTV IR type Fixed 2 bh Rp 2,905,250.00 Rp 5,810,500.00

2. Lantai 1
1 Instalasi CCTV dg kabel RG 59 + kabel power dlm pipa conduit PVC dia. 20 mm2 6 titik Rp 662,400.00 Rp 3,974,400.00
2 Memasang Color Dome type camera 6 bh Rp 2,805,250.00 Rp 16,831,500.00

3. Lantai 2
1 Instalasi CCTV dg kabel RG 59 dlm pipa conduit PVC dia. 20 mm2 4 titik Rp 662,400.00 Rp 2,649,600.00
2 Memasang Color Dome type camera 4 bh Rp 2,805,250.00 Rp 11,221,000.00
3 DVR kap 16 chanel hardisc 1 T 1 unit Rp 5,750,000.00 Rp 5,750,000.00
4 Video Manager 1 unit Rp 2,350,000.00 Rp 2,350,000.00
5 Monitor LED 32" 2 unit Rp 3,750,000.00 Rp 7,500,000.00

TOTAL PEKERJAAN CCTV Rp 57,411,800.0


H. Pekerjaan GENSET
1 Genset 30 KVA. 380 V, 50 Hz, Silent type 1 unit Rp 155,000,000.00 Rp 155,000,000.00
2 Tangki bahan bakar harian (200 L) 1 unit Rp 1,750,000.00 Rp 1,750,000.00
3 Instalasi (gas buang, pipa bahan bakar, dll) 1 ls Rp 7,500,000.00 Rp 7,500,000.00
4 Pompa Bahan bakar 10 LPM 1 unit Rp 4,350,000.00 Rp 4,350,000.00
TOTAL PEKERJAAN GENSET Rp 168,600,000.0
I. Pekerjaan Penyalur Petir
1 Head terminal type Electrostatic R=67 m 1 bh Rp 15,950,000.00 Rp 15,950,000.00
2 Tiang penyangga penangkal petir 3 meter lengkap terpasang dg obstruction lamp 1 unit Rp 1,875,000.00 Rp 1,875,000.00
3 Kabel NYY 1x70 mm2 ex. Supreme 47 m' Rp 127,485.00 Rp 5,991,795.00
4 Kabel BC 1x50 mm2 25 m' Rp 62,610.00 Rp 1,565,250.00
5 Instalasi Pentanahan 1 unit Rp 3,500,000.00 Rp 3,500,000.00
6 Bak Kontrol Uk. 40x40 Cm 1 unit Rp 806,854.50 Rp 806,854.50
7 Fitting + Supporting 1 ls Rp 2,500,000.00 Rp 2,500,000.00
TOTAL PEKERJAAN PENYALUR PETIR Rp 32,188,899.5
TOTAL PEKERJAAN ELEKTRIKAL #N/A
URAIAN ENGINEERING ESTIMATE MEKANIKAL ELEKTRIKAL

PROGRAM : PROYEK PEMBANGUNAN GEDUNG PELAYANAN PERIJINAN DAN PENANAMAN MODAL


LOKASI : KABUPATEN TEMANGGUNG

No. Jenis Pekerjaan Vol Sat Harga Satuan Jumlah Harga Total
II. PEKERJAAN MEKANIKAL/PLUMBING
A. Pekerjaan Instalasi Air Kotor, Bekas dan Vent
Pipa PVC klas AW komplit dg bobokan dan galian
1. Basement
1 Memasang 1 m' pipa PVC type AW 4" 45 m' Rp 137,467.50 Rp 6,186,037.50
2 Memasang 1 m' pipa PVC type AW 3" 26 m' Rp 92,269.50 Rp 2,399,007.00
3 Memasang 1 m' pipa PVC type AW 2" 4 m' Rp 58,249.50 Rp 232,998.00
4 Memasang Septictank BF-04 1 unit Rp 8,500,000.00 Rp 8,500,000.00
5 Memasang Septictank BF-08 1 unit Rp 10,500,000.00 Rp 10,500,000.00
6 Memasang 1 bh Peresapan, dalam 3 m' 2 unit Rp 2,321,922.00 Rp 4,643,844.00
7 Fitting dan Supporting 1 ls Rp 1,250,000.00 Rp 1,250,000.00

2. Lantai 1
1 Memasang 1 m' pipa PVC type AW 4" 50 m' Rp 137,467.50 Rp 6,873,375.00
2 Memasang 1 m' pipa PVC type AW 3" 8 m' Rp 92,269.50 Rp 738,156.00
3 Memasang 1 m' pipa PVC type AW 2" 29 m' Rp 58,249.50 Rp 1,689,235.50
4 Memasang 1 m' pipa PVC type AW 1 1/4" 19 m' Rp 46,909.50 Rp 891,280.50
5 Memasang 1 m' pipa PVC type AW 1" 73 m' Rp 38,809.50 Rp 2,833,093.50
6 Fitting dan Supporting 1 ls Rp 1,250,000.00 Rp 1,250,000.00

3. Lantai 2
1 Memasang 1 m' pipa PVC type AW 4" 19 m' Rp 137,467.50 Rp 2,611,882.50
2 Memasang 1 m' pipa PVC type AW 3" 11 m' Rp 92,269.50 Rp 1,014,964.50
3 Memasang 1 m' pipa PVC type AW 2" 8 m' Rp 58,249.50 Rp 465,996.00
4 Memasang 1 m' pipa PVC type AW 1 1/4" 12 m' Rp 46,909.50 Rp 562,914.00
5 Memasang 1 m' pipa PVC type AW 1" 47 m' Rp 38,809.50 Rp 1,824,046.50
6 Fitting dan Supporting 1 ls Rp 750,000.00 Rp 750,000.00

TOTAL PEKERJAAN INSTALASI AIR KOTOR, BEKAS DAN VENT Rp 55,216,830.5


B. Pekerjaan Instalasi Air Bersih
Instalasi Pipa PPR PN 10 komplit dg Gantungan pipa, bobokan dan galian
1. Basement
1 Memasang 1 m' pipa PPR PN10 1 1/4" 4 m' Rp 100,913.40 Rp 403,653.60
2 Memasang 1 m' pipa PPR PN10 1" termasuk Suplay GWT 68 m' Rp 63,441.00 Rp 4,313,988.00
3 Memasang 1 m' pipa PPR PN10 3/4" 35 m' Rp 42,381.00 Rp 1,483,335.00
4 Memasang 1 buah Ball Valve 3/4" 1 bh Rp 106,870.00 Rp 106,870.00
5 Pompa transfer kap. 50 lpm lengkap dg WLC, kabel power dan aksesoris lainnya 1 unit Rp 4,500,000.00 Rp 4,500,000.00
6 Ground Water Tank kap. ( 2 x 1,5 x 1,5 ) m3 1 unit by Struktur
7 Fitting + asesories 1 ls Rp 1,000,000.00 Rp 1,000,000.00

2. Lantai 1
1 Memasang 1 m' pipa PPR PN10 1 1/4" 4 m' Rp 100,913.40 Rp 403,653.60
2 Memasang 1 m' pipa PPR PN10 1" 22 m' Rp 63,441.00 Rp 1,395,702.00
3 Memasang 1 m' pipa PPR PN10 3/4" 82 m' Rp 42,381.00 Rp 3,475,242.00
4 Memasang 1 buah Ball Valve 1" 1 bh Rp 156,870.00 Rp 156,870.00
5 Memasang 1 buah Ball Valve 3/4" 2 bh Rp 106,870.00 Rp 213,740.00
6 Fitting + asesories 1 ls Rp 1,250,000.00 Rp 1,250,000.00

3. Lantai 2
1 Memasang 1 m' pipa PPR PN10 1 1/4" 6 m' Rp 100,913.40 Rp 605,480.40
2 Memasang 1 m' pipa PPR PN10 1" 14 m' Rp 63,441.00 Rp 888,174.00
3 Memasang 1 m' pipa PPR PN10 3/4" 45 m' Rp 42,381.00 Rp 1,907,145.00
4 Memasang 1 buah Ball Valve 2" 1 bh Rp 236,870.00 Rp 236,870.00
5 Memasang 1 buah Ball Valve 1 1/4" 1 bh Rp 196,870.00 Rp 196,870.00
6 Memasang 1 buah Ball Valve 1" 2 bh Rp 156,870.00 Rp 313,740.00
7 Memasang 1 buah Ball Valve 3/4" 1 bh Rp 106,870.00 Rp 106,870.00
8 Memasang 1 m' pipa PVC klas AW 2" untuk kurasan Tandon Air 20 m' Rp 58,249.50 Rp 1,164,990.00
9 Tandon Air kap. 1 m3 2 unit Rp 1,850,000.00 Rp 3,700,000.00
10 Memasang 1 unit header 2" 1 unit Rp 875,000.00 Rp 875,000.00
11 Fitting + asesories 1 ls Rp 1,650,000.00 Rp 1,650,000.00
TOTAL PEKERJAAN INSTALASI AIR BERSIH Rp 28,698,193.6
C. Pekerjaan Drainase Air Hujan
1 Memasang 1 buah Roofdrain 3" 25 bh Rp 326,870.00 Rp 8,171,750.00
2 Memasang 1 m' pipa PVC type AW 3" 321 m' Rp 92,269.50 Rp 29,618,509.50
3 Memasang 1 m' pipa PVC type AW 4" 36 m' Rp 137,467.50 Rp 4,948,830.00
4 Memasang 1 bh bak kontrol pas. batu bata uk. 40 cm x 40 cm, tinggi 50 cm 16 unit Rp 806,854.50 Rp 12,909,672.00
5 Memasang 1 bh Peresapan, dalam 3 m' 9 unit Rp 2,321,922.00 Rp 20,897,298.00
6 Fitting dan Supporting 1 ls Rp 1,250,000.00 Rp 1,250,000.00
TOTAL PEKERJAAN DRAINASE AIR HUJAN Rp 77,796,059.5
D. Pekerjaan Tata Udara
No. Jenis Pekerjaan Vol Sat Harga Satuan Jumlah Harga Total
1 Lantai 1
Kabel NYM 3x2.5 mm Ex Supreme dalam High Impact conduit dia. 20 mm Ex. Clipsal
1 Memasang 1 titik instalasi AC 1 phase 3 titik Rp 425,250.00 Rp 1,275,750.00
2 AC Split Wall 0,75 PK lengkap terpasang dg pipa Refrigerant berisolasi Armaflex 1 unit Rp 4,250,000.00 Rp 4,250,000.00
3 AC Split Wall 1,5 PK lengkap terpasang dg pipa Refrigerant berisolasi Armaflex 2 bh Rp 5,150,000.00 Rp 10,300,000.00
4 Memasang 1 m' pipa PVC type AW 1" untuk drainase 17 m' Rp 38,809.50 Rp 659,761.50
Kabel NYM 3x2.5 mm Ex Supreme dalam High Impact conduit dia. 20 mm Ex. Clipsal
1 Memasang 1 titik instalasi AC 3 phase 2 titik Rp 695,250.00 Rp 1,390,500.00
2 AC Ceiling Cassete 5 PK lengkap terpasang dg pipa Refrigerant berisolasi Armaflex 2 unit Rp 48,500,000.00 Rp 97,000,000.00
3 Memasang 1 m' pipa PVC type AW 1" untuk drainase 21 m' Rp 38,809.50 Rp 814,999.50

2 Lantai 2
Kabel NYM 3x2.5 mm Ex Supreme dalam High Impact conduit dia. 20 mm Ex. Clipsal
1 Memasang 1 titik instalasi AC 1 phase 15 titik Rp 425,250.00 Rp 6,378,750.00
2 AC Split Wall 0,5 PK lengkap terpasang dg pipa Refrigerant berisolasi Armaflex 2 unit Rp 4,100,000.00 Rp 8,200,000.00
3 AC Split Wall 1 PK lengkap terpasang dg pipa Refrigerant berisolasi Armaflex 3 bh Rp 4,500,000.00 Rp 13,500,000.00
4 AC Split Wall 1,5 PK lengkap terpasang dg pipa Refrigerant berisolasi Armaflex 6 bh Rp 5,150,000.00 Rp 30,900,000.00
5 AC Split Wall 2 PK lengkap terpasang dg pipa Refrigerant berisolasi Armaflex 4 bh Rp 6,250,000.00 Rp 25,000,000.00
6 Memasang 1 m' pipa PVC type AW 1" untuk drainase 160 m' Rp 38,809.50 Rp 6,209,520.00
TOTAL PEKERJAAN TATA UDARA Rp 205,879,281.0
TOTAL PEKERJAAN MEKANIKAL PLUMBING Rp 367,590,364.6
HARGA SATUAN (Rp.)
KODE URAIAN PEKERJAAN
BAHAN UPAH
1 2 3 4
A. ANALISA BIAYA KONSTRUKSI PEKERJAAN PLUMBING

A.1 Memasang 1 m' pipa PVC type AW 1"


1.2000 m' Pipa PVC klas AW dia. 1" 9,500.00
35.0000 % Perlengkapan (dari harga pipa) 3,325.00
0.0810 Oh Buruh tak terlatih 57,000.00
0.1350 Oh Tukang ledeng/pipa 65,000.00
0.1350 Oh Kepala tukang 72,000.00
0.0041 Oh Mandor 75,000.00

A.2 Memasang 1 m' pipa PVC type AW 1 1/4"


1.2000 m' Pipa PVC klas AW dia. 1 1/4" 14,500.00
35.0000 % Perlengkapan (dari harga pipa) 5,075.00
0.0810 Oh Buruh tak terlatih 57,000.00
0.1350 Oh Tukang ledeng/pipa 65,000.00
0.1350 Oh Kepala tukang 72,000.00
0.0041 Oh Mandor 75,000.00

A.3 Memasang 1 m' pipa PVC type AW 2"


1.2000 m' Pipa PVC klas AW dia. 2" 21,500.00
35.0000 % Perlengkapan (dari harga pipa) 7,525.00
0.0810 Oh Buruh tak terlatih 57,000.00
0.1350 Oh Tukang ledeng/pipa 65,000.00
0.1350 Oh Kepala tukang 72,000.00
0.0041 Oh Mandor 75,000.00

A.4 Memasang 1 m' pipa PVC type AW 3"


1.2000 m' Pipa PVC klas AW dia. 3" 42,500.00
35.0000 % Perlengkapan (dari harga pipa) 14,875.00
0.0810 Oh Buruh tak terlatih 57,000.00
0.1350 Oh Tukang ledeng/pipa 65,000.00
0.1350 Oh Kepala tukang 72,000.00
0.0041 Oh Mandor 75,000.00

A.5 Memasang 1 m' pipa PVC type AW 4"


1.2000 m' Pipa PVC klas AW dia. 4" 70,400.00
35.0000 % Perlengkapan (dari harga pipa) 24,640.00
0.0810 Oh Buruh tak terlatih 57,000.00
0.1350 Oh Tukang ledeng/pipa 65,000.00
0.1350 Oh Kepala tukang 72,000.00
0.0041 Oh Mandor 75,000.00

A.6 Memasang 1 m' pipa PPR PN10 3/4"


1.2000 m' Pipa PPR PN10 dia. 3/4" 19,000.00
35.0000 % Perlengkapan (dari harga pipa) 6,650.00
0.0540 Oh Buruh tak terlatih 57,000.00
0.0900 Oh Tukang ledeng/pipa 65,000.00
0.0090 Oh Kepala tukang 72,000.00
0.0270 Oh Mandor 75,000.00

A.7 Memasang 1 m' pipa PPR PN10 1"


1.2000 m' Pipa PPR PN10 dia. 1" 32,000.00
35.0000 % Perlengkapan (dari harga pipa) 11,200.00
0.0540 Oh Buruh tak terlatih 57,000.00
0.0900 Oh Tukang ledeng/pipa 65,000.00
0.0090 Oh Kepala tukang 72,000.00
0.0270 Oh Mandor 75,000.00

A.8 Memasang 1 m' pipa PPR PN10 1 1/4"


1.2000 m' Pipa PPR PN10 dia. 1 1/4" 50,220.00
35.0000 % Perlengkapan (dari harga pipa) 17,577.00
0.1080 Oh Buruh tak terlatih 57,000.00
0.1800 Oh Tukang ledeng/pipa 65,000.00
0.0180 Oh Kepala tukang 72,000.00
0.0054 Oh Mandor 75,000.00

A.9 Memasang 1 buah Ball Valve 3/4"


1.0000 bh Ball Valve dia. 3/4" 95,000.00
0.0750 Oh Buruh tak terlatih 57,000.00
0.1000 Oh Tukang ledeng/pipa 65,000.00
0.0100 Oh Kepala tukang 72,000.00
0.0050 Oh Mandor 75,000.00

A.10 Memasang 1 buah Ball Valve 1"


1.0000 bh Ball Valve dia. 1" 145,000.00
0.0750 Oh Buruh tak terlatih 57,000.00
0.1000 Oh Tukang ledeng/pipa 65,000.00
0.0100 Oh Kepala tukang 72,000.00
0.0050 Oh Mandor 75,000.00

A.11 Memasang 1 buah Ball Valve 1 1/4"


1.0000 bh Ball Valve dia. 1 1/4" 185,000.00
0.0750 Oh Buruh tak terlatih 57,000.00
0.1000 Oh Tukang ledeng/pipa 65,000.00
0.0100 Oh Kepala tukang 72,000.00
0.0050 Oh Mandor 75,000.00

A.12 Memasang 1 buah Ball Valve 2"


1.0000 bh Ball Valve dia. 2" 225,000.00
0.0750 Oh Buruh tak terlatih 57,000.00
0.1000 Oh Tukang ledeng/pipa 65,000.00
0.0100 Oh Kepala tukang 72,000.00
0.0050 Oh Mandor 75,000.00

A.13 Memasang 1 buah Roofdrain 3"


1.0000 bh Roofdrain dia. 3" 315,000.00
0.0750 Oh Buruh tak terlatih 57,000.00
0.1000 Oh Tukang batu 65,000.00
0.0100 Oh Kepala tukang 72,000.00
0.0050 Oh Mandor 75,000.00

A.14 Memasang 1 bh bak kontrol pas. batu bata uk. 40 cm x 40 cm, tinggi 50 cm
88.0000 bh Batu bata merah (lokal) 1,100.00
59.0000 kg Semen PC @ 50 kg 1,600.00
0.9310 m Pasir ayak untuk beton ( kasar ) 195,000.00
0.9310 m Batu kerikil sungai 141,000.00
2.1280 kg Besi beton 15,000.00
0.0789 m Pasir ayak untuk beton ( halus ) 195,000.00
3.2000 Oh Buruh tak terlatih 57,000.00
1.1050 Oh Tukang batu 65,000.00
0.0015 Oh Kepala tukang 72,000.00
0.0160 Oh Mandor 75,000.00

A.15 Memasang 1 bh Peresapan, dalam 3 m'


3.0000 m Galian Tanah 35,000.00
33.33 % Urugan Kembali 11,665.50
3.0000 bh Pas.Buis Beton tak bertulang 80 cm 540,000.00
0.3840 m Pas. Plesteran dinding(dalam) pd pertemuan buis , ad. 1 : 2, tebal 15mm 45,500.00
0.6000 m' Pas. Pipa galvanis 1,5" 170,750.00
2.3000 Oh Buruh tak terlatih 57,000.00
3.2000 Oh Tukang batu 65,000.00
0.7000 Oh Kepala tukang 72,000.00
0.7000 Oh Mandor 75,000.00

B. ANALISA BIAYA KONSTRUKSI PEKERJAAN ELEKTRIKAL

B.1 Memasang 1 meter kabel NYY 1 x 70 mm


1.1000 m' Kabel NYY 1 x 70 mm 115,000.00
0.0050 Oh Buruh tak terlatih 57,000.00
0.0050 Oh Tukang Listrik 65,000.00
0.0050 Oh Mandor 75,000.00

B.2 Memasang 1 meter kabel NYY 3 x 4 mm


1.1000 m' Kabel NYY 3 x 4 mm 27,500.00
0.0050 Oh Buruh tak terlatih 57,000.00
0.0050 Oh Tukang Listrik 65,000.00
0.0050 Oh Mandor 75,000.00
B.3 Memasang 1 meter kabel NYY 4 x 4 mm
1.1000 m' Kabel NYY 4 x 4 mm 36,000.00
0.0050 Oh Buruh tak terlatih 57,000.00
0.0050 Oh Tukang Listrik 65,000.00
0.0050 Oh Mandor 75,000.00

B.4 Memasang 1 meter kabel NYY 4 x 6 mm


1.1000 m' Kabel NYY 4 x 6 mm 59,000.00
0.0050 Oh Buruh tak terlatih 57,000.00
0.0050 Oh Tukang Listrik 65,000.00
0.0050 Oh Mandor 75,000.00

B.5 Memasang 1 meter kabel NYFGbY 4 x 25 mm


1.1000 m' Kabel NYFGbY 4 x 25 mm 165,000.00
0.0550 Oh Buruh tak terlatih 57,000.00
0.0150 Oh Tukang Listrik 65,000.00
0.0100 Oh Mandor 75,000.00

B.6 Memasang 1 meter kabel BC 1 x 50 mm


1.1000 m' Kabel BC 50 mm 52,500.00
0.0550 Oh Buruh tak terlatih 57,000.00
0.0150 Oh Tukang Listrik 65,000.00
0.0100 Oh Mandor 75,000.00

B.7 Memasang 1 unit Panel Penerangan Basement A ( LPBS.A ) uk. 400 x 500 x 200 mm
1.0000 Unit Box Panel 400 x 500 x 200 mm 675,000.00
3.0000 bh MCB 4 A / 4,5 kA 65,000.00
2.0000 bh MCB 6 A / 4,5 kA 65,000.00
1.0000 bh MCB C60N 6 A / 6 kA / 3 ph 431,000.00
0.3000 m' Rel MCB 52,450.00
1.0000 btg Ground Rod (Galvanist) 45,000.00
6.0000 m' Kabel BC 6 mm 12,000.00
3.0000 bh Pilot Lamp 20,000.00
1.0000 ls Kabel Pengawatan Panel 250,000.00
1.0000 bh Terminal Nol Besar 45,000.00
3.0000 bh Sekering kecil 12,500.00
1.0000 Oh Buruh tak terlatih 57,000.00
0.7500 Oh Tukang Listrik 65,000.00
0.2500 Oh Mandor 75,000.00
1.0000 set Alat Bantu Pasang/Bongkar - Panel Box 85,000.00

B.8 Memasang 1 unit Panel Penerangan Lantai 1 A ( LP1.A ) uk. 400 x 500 x 200 mm
1.0000 Unit Box Panel 400 x 500 x 200 mm 675,000.00
8.0000 bh MCB 6 A / 4,5 kA 65,000.00
1.0000 bh MCCB EZC100B 15 A/ 7,5 Ka 655,000.00
0.3000 m' Rel MCB 52,450.00
1.0000 btg Ground Rod (Galvanist) 45,000.00
6.0000 m' Kabel BC 6 mm 12,000.00
3.0000 bh Pilot Lamp 20,000.00
1.0000 ls Kabel Pengawatan Panel 250,000.00
1.0000 bh Terminal Nol Besar 45,000.00
3.0000 bh Sekering kecil 12,500.00
1.0000 Oh Buruh tak terlatih 57,000.00
0.7500 Oh Tukang Listrik 65,000.00
0.2500 Oh Mandor 75,000.00
1.0000 set Alat Bantu Pasang/Bongkar - Panel Box 85,000.00

B.9 Memasang 1 unit Panel Penerangan Lantai 2 A ( LP2.A ) uk. 400 x 500 x 200 mm
1.0000 Unit Box Panel 400 x 500 x 200 mm 675,000.00
8.0000 bh MCB 6 A / 4,5 kA 65,000.00
1.0000 bh MCCB EZC100B 15 A/ 7,5 Ka 655,000.00
0.3000 m' Rel MCB 52,450.00
1.0000 btg Ground Rod (Galvanist) 45,000.00
6.0000 m' Kabel BC 6 mm 12,000.00
3.0000 bh Pilot Lamp 20,000.00
1.0000 ls Kabel Pengawatan Panel 250,000.00
1.0000 bh Terminal Nol Besar 45,000.00
3.0000 bh Sekering kecil 12,500.00
1.0000 Oh Buruh tak terlatih 57,000.00
0.7500 Oh Tukang Listrik 65,000.00
0.2500 Oh Mandor 75,000.00
1.0000 set Alat Bantu Pasang/Bongkar - Panel Box 85,000.00

B.10 Memasang 1 unit Power Panel AC Lantai 1 ( PPAC 1.A ) uk. 400 x 600 x 200 mm
1.0000 Unit Box Panel 400 x 600 x 200 mm 950,000.00
4.0000 bh MCB 6 A / 4,5 kA 65,000.00
3.0000 bh MCB C60N 16 A / 6 kA / 3 ph 510,000.00
1.0000 bh MCCB EZC100B 30 A/ 7,5 Ka 655,000.00
0.3000 m' Rel MCB 52,450.00
1.0000 btg Ground Rod (Galvanist) 45,000.00
6.0000 m' Kabel BC 6 mm 12,000.00
3.0000 bh Pilot Lamp 20,000.00
1.0000 ls Kabel Pengawatan Panel 250,000.00
1.0000 bh Terminal Nol Besar 45,000.00
3.0000 bh Sekering kecil 12,500.00
1.0000 Oh Buruh tak terlatih 57,000.00
0.7500 Oh Tukang Listrik 65,000.00
0.2500 Oh Mandor 75,000.00
1.0000 set Alat Bantu Pasang/Bongkar - Panel Box 85,000.00

B.11 Memasang 1 unit Power Panel AC Lantai 2 ( PPAC 2.A ) uk. 400 x 600 x 200 mm
1.0000 Unit Box Panel 400 x 600 x 200 mm 950,000.00
6.0000 bh MCB 6 A / 4,5 kA 65,000.00
9.0000 bh MCB 16 A / 4,5 kA 65,000.00
1.0000 bh MCCB EZC100B 40 A/ 7,5 Ka 655,000.00
0.3000 m' Rel MCB 52,450.00
1.0000 btg Ground Rod (Galvanist) 45,000.00
6.0000 m' Kabel BC 6 mm 12,000.00
3.0000 bh Pilot Lamp 20,000.00
1.0000 ls Kabel Pengawatan Panel 250,000.00
1.0000 bh Terminal Nol Besar 45,000.00
3.0000 bh Sekering kecil 12,500.00
1.0000 Oh Buruh tak terlatih 57,000.00
0.7500 Oh Tukang Listrik 65,000.00
0.2500 Oh Mandor 75,000.00
1.0000 set Alat Bantu Pasang/Bongkar - Panel Box 85,000.00

B.12 Memasang 1 unit Panel MDP uk. 600 x 800 x 400 mm


1.0000 Unit Box Panel 600 x 800 x 400 mm 1,750,000.00
1.0000 bh MCB C60N 6 A / 6 kA / 3 ph 431,000.00
3.0000 bh MCCB EZC100B 15 A/ 7,5 Ka 655,000.00
2.0000 bh MCCB EZC100B 30 A/ 7,5 Ka 655,000.00
1.0000 bh MCCB EZC100B 40 A/ 7,5 Ka 655,000.00
1.0000 bh MCCB EZC250F 100 A/ 18 Ka 1,750,000.00
1.0000 bh Selector Switch , 7 posisi 550,000.00
3.0000 bh Ampere Meter 325,000.00
1.0000 bh Volt Meter AC 220/380 V 435,000.00
1.0000 bh CT 100/5 475,000.00
0.3000 m' Rel MCB 52,450.00
1.0000 btg Ground Rod (Galvanist) 45,000.00
6.0000 m' Kabel BC 16 mm 22,500.00
3.0000 bh Pilot Lamp 20,000.00
1.0000 ls Kabel Pengawatan Panel 450,000.00
1.0000 bh Terminal Nol Besar 45,000.00
3.0000 bh Sekering kecil 12,500.00
2.0000 Oh Buruh tak terlatih 57,000.00
1.0000 Oh Operator Terlatih 73,000.00
1.0000 Oh Tukang Listrik 65,000.00
0.3500 Oh Mandor 75,000.00
1.0000 set Alat Bantu Pasang/Bongkar - Panel Box 85,000.00

B.13 Memasang 1 unit Panel Penerangan Lantai 2 B ( LP2.B ) - Box MCB 12 Gang
1.0000 Unit Box MCB 12 Gang 225,000.00
4.0000 bh MCB 4 A / 4,5 kA 65,000.00
1.0000 bh MCB 6 A / 4,5 kA 65,000.00
2.0000 bh MCB 16 A / 4,5 kA 65,000.00
1.0000 bh MCB 20 A / 6 kA 210,000.00
0.1000 m' Rel MCB 52,450.00
0.5000 btg Ground Rod (Galvanist) 45,000.00
0.5000 bh Terminal Nol Besar 45,000.00
1.0000 ls grounding 75,000.00
0.7500 Oh Buruh tak terlatih 57,000.00
0.3500 Oh Tukang Listrik 65,000.00
0.1000 Oh Mandor 75,000.00
1.0000 set Alat Bantu Pasang/Bongkar - Panel Box 85,000.00

B.14 Memasang 1 unit Panel Penerangan Lantai 1 B ( LP1.B ) - Box MCB 8 Gang
1.0000 Unit Box MCB 8 Gang 150,000.00
3.0000 bh MCB 2 A / 4,5 kA 65,000.00
2.0000 bh MCB 4 A / 4,5 kA 65,000.00
1.0000 bh MCB 4 A / 6 kA 175,000.00
0.1000 m' Rel MCB 52,450.00
0.5000 btg Ground Rod (Galvanist) 45,000.00
0.5000 bh Terminal Nol Besar 45,000.00
1.0000 ls grounding 75,000.00
0.7500 Oh Buruh tak terlatih 57,000.00
0.3500 Oh Tukang Listrik 65,000.00
0.1000 Oh Mandor 75,000.00
1.0000 set Alat Bantu Pasang/Bongkar - Panel Box 85,000.00

B.15 Memasang 1 unit Panel Penerangan Basement B ( LPBS.B ) - Box MCB 12 Gang
1.0000 Unit Box MCB 12 Gang 225,000.00
2.0000 bh MCB 2 A / 4,5 kA 65,000.00
2.0000 bh MCB 4 A / 6 kA 175,000.00
3.0000 bh MCB 20 A / 6 kA 210,000.00
0.1000 m' Rel MCB 52,450.00
0.5000 btg Ground Rod (Galvanist) 45,000.00
0.5000 bh Terminal Nol Besar 45,000.00
1.0000 ls grounding 75,000.00
0.7500 Oh Buruh tak terlatih 57,000.00
0.3500 Oh Tukang Listrik 65,000.00
0.1000 Oh Mandor 75,000.00
1.0000 set Alat Bantu Pasang/Bongkar - Panel Box 85,000.00

B.16 Memasang 1 bh Lampu Downligh Outbow LED 9 W


1.0000 bh Armatur Downlight Outbow 235,000.00
1.0000 bh Lampu LED Bulb 9W "Philips" 75,000.00
1.0000 x Material bantu ringan 7,500.00
0.2500 Oh Buruh tak terlatih 57,000.00
0.0750 Oh Tukang Listrik 65,000.00
0.0250 Oh Mandor 75,000.00

B.17 Memasang 1 bh Lampu Downligh LED 9 W


1.0000 bh Armatur Downlight RD 150 167,400.00
1.0000 bh Lampu LED Bulb 9W "Philips" 75,000.00
1.0000 x Material bantu ringan 7,500.00
0.2500 Oh Buruh tak terlatih 57,000.00
0.0750 Oh Tukang Listrik 65,000.00
0.0250 Oh Mandor 75,000.00

B.18 Memasang 1 bh Lampu Downligh LED 6 W


1.0000 bh Armatur Downlight RD 125 155,700.00
1.0000 bh Lampu LED Bulb 6W "Philips" 45,000.00
1.0000 x Material bantu ringan 7,500.00
0.2500 Oh Buruh tak terlatih 57,000.00
0.0750 Oh Tukang Listrik 65,000.00
0.0250 Oh Mandor 75,000.00

B.19 Memasang 1 bh Lampu Downligh Spot LED 10 W


1.0000 bh Armatur Downlight Spot LED 10 W 425,000.00
1.0000 bh Lampu LED 10W "Philips" include
1.0000 x Material bantu ringan 7,500.00
0.2500 Oh Buruh tak terlatih 57,000.00
0.0750 Oh Tukang Listrik 65,000.00
0.0250 Oh Mandor 75,000.00

B.20 Memasang 1 bh Lampu Baret Circular LED 10 W


1.0000 bh Armatur Lampu Baret Circular LED 10 Watt 345,000.00
1.0000 bh Lampu LED 10W "Philips" include
1.0000 x Material bantu ringan 7,500.00
0.2500 Oh Buruh tak terlatih 57,000.00
0.0750 Oh Tukang Listrik 65,000.00
0.0250 Oh Mandor 75,000.00

B.21 Memasang 1 bh Lampu Emergency Exit 8 W c/w NiCad Batery


1.0000 bh Armatur Lampu Emergency Exit LED 8 W 1,350,000.00
1.0000 bh NiCad Batery include
1.0000 x Material bantu ringan 7,500.00
0.2500 Oh Buruh tak terlatih 57,000.00
0.0750 Oh Tukang Listrik 65,000.00
0.0250 Oh Mandor 75,000.00

B.22 Memasang 1 bh Lampu TL BALK T8 1 x 36 W


1.0000 unit Armatur Lampu TL BALK T8 1 x 36 W 225,000.00
1.0000 bh Lampu T8 36 Watt 35,000.00
1.0000 bh Balast 36W Ex PHILIPS 55,000.00
1.0000 bh Stater 10,000.00
1.0000 x Material bantu ringan 7,500.00
0.2500 Oh Buruh tak terlatih 57,000.00
0.0750 Oh Tukang Listrik 65,000.00
0.0250 Oh Mandor 75,000.00
B.23 Memasang 1 bh Lampu RM T8 2 x 18 W
1.0000 unit Armatur Lampu RM T8 2 x 18 W 367,000.00
2.0000 bh Lampu T8 18 Watt 25,000.00
2.0000 bh Balast 18W Ex PHILIPS 35,000.00
2.0000 bh Stater 10,000.00
1.0000 x Material bantu ringan 7,500.00
0.2500 Oh Buruh tak terlatih 57,000.00
0.0750 Oh Tukang Listrik 65,000.00
0.0250 Oh Mandor 75,000.00

B.24 Memasang 1 m' Lampu Strip LED 6 W / meter


1.0000 bh Lampu Strip LED 6 W/meter 175,000.00
0.2000 bh Power Suplay include
1.0000 x Material bantu ringan 7,500.00
0.2500 Oh Buruh tak terlatih 57,000.00
0.0750 Oh Tukang Listrik 65,000.00
0.0250 Oh Mandor 75,000.00

B.25 Memasang 1 bh Saklar Tunggal


1.0000 bh Sakelar Tunggal 27,500.00
1.0000 bh Inbow dos seng 10,000.00
0.0500 Oh Buruh tak terlatih 57,000.00
0.0350 Oh Tukang Listrik 65,000.00
0.0100 Oh Mandor 75,000.00

B.26 Memasang 1 bh Saklar Seri/Ganda


1.0000 bh Sakelar Seri 42,500.00
1.0000 bh Inbow dos seng 10,000.00
0.0500 Oh Buruh tak terlatih 57,000.00
0.0350 Oh Tukang Listrik 65,000.00
0.0100 Oh Mandor 75,000.00

B.27 Memasang 1 bh Saklar Grid 6 Gang


1.0000 bh Sakelar Grid 6 Gang 200,000.00
1.0000 bh Inbow dos seng 10,000.00
0.0500 Oh Buruh tak terlatih 57,000.00
0.0350 Oh Tukang Listrik 65,000.00
0.0100 Oh Mandor 75,000.00

B.28 Memasang 1 bh Stop Kontak


1.0000 bh Stop Kontak 27,500.00
1.0000 bh Inbow dos seng 10,000.00
0.0500 Oh Buruh tak terlatih 57,000.00
0.0350 Oh Tukang Listrik 65,000.00
0.0100 Oh Mandor 75,000.00

B.29 Memasang 1 bh Stop Kontak Lantai


1.0000 bh Stop Kontak Lantai 450,000.00
1.0000 bh Inbow dos seng 10,000.00
0.0500 Oh Buruh tak terlatih 57,000.00
0.0350 Oh Tukang Listrik 65,000.00
0.0100 Oh Mandor 75,000.00

B.30 Memasang 1 titik instalasi Penerangan


10.0000 m' Kabel NYM 3 x 2,5 mm 14,500.00
10.0000 m' Pipa Conduit 20mm 4,500.00
1.0000 x Material bantu T dos,klem,dll 17,500.00
0.2500 Oh Buruh tak terlatih 57,000.00
0.1500 Oh Tukang Listrik 65,000.00
0.0500 Oh Mandor 75,000.00

B.31 Memasang 1 titik instalasi Stop Kontak


10.0000 m' Kabel NYM 3 x 2,5 mm 14,500.00
10.0000 m' Pipa Conduit 20mm 4,500.00
1.0000 x Material bantu T dos,klem,dll 17,500.00
0.2500 Oh Buruh tak terlatih 57,000.00
0.1500 Oh Tukang Listrik 65,000.00
0.0500 Oh Mandor 75,000.00

B.32 Memasang 1 titik instalasi AC 1 Phase


20.0000 m' Kabel NYM 3 x 2,5 mm 14,500.00
20.0000 m' Pipa Conduit 20mm 4,500.00
1.0000 x Material bantu T dos,klem,dll 17,500.00
0.2500 Oh Buruh tak terlatih 57,000.00
0.1500 Oh Tukang Listrik 65,000.00
0.0500 Oh Mandor 75,000.00

B.33 Memasang 1 titik instalasi AC 3 Phase


20.0000 m' Kabel NYM 4 x 4 mm 28,000.00
20.0000 m' Pipa Conduit 20mm 4,500.00
1.0000 x Material bantu T dos,klem,dll 17,500.00
0.2500 Oh Buruh tak terlatih 57,000.00
0.1500 Oh Tukang Listrik 65,000.00
0.0500 Oh Mandor 75,000.00

B.34 Memasang 1 bh Exhaust Fan 40 W


1.0000 bh Exhaust Fan 40 W 450,000.00
1.0000 x Material bantu ringan 7,500.00
0.2500 Oh Buruh tak terlatih 57,000.00
0.0750 Oh Tukang Listrik 65,000.00
0.0250 Oh Mandor 75,000.00

FIRE ALARM

B.35 Memasang 1 titik instalasi Smoke Detector


20.0000 m' Kabel NYA 1,5 mm 2,500.00
10.0000 m' Pipa Conduit 20mm 4,500.00
1.0000 x Material bantu ringan 7,500.00
0.2000 Oh Buruh tak terlatih 57,000.00
0.1500 Oh Tukang listrik 65,000.00
0.0500 Oh Mandor 75,000.00

B.36 Memasang 1 bh Smoke Detector


1.0000 bh Smoke Detektor 375,000.00
1.0000 x Material bantu ringan 7,500.00
0.2000 Oh Buruh tak terlatih 57,000.00
0.0500 Oh Tukang listrik 65,000.00
0.0100 Oh Mandor 75,000.00

B.37 Memasang 1 titik instalasi ROR HEat Detector


20.0000 m' Kabel NYA 1,5 mm 2,500.00
10.0000 m' Pipa Conduit 20mm 4,500.00
1.0000 x Material bantu ringan 7,500.00
0.2000 Oh Buruh tak terlatih 57,000.00
0.1500 Oh Tukang listrik 65,000.00
0.0500 Oh Mandor 75,000.00

B.38 Memasang 1 bh ROR Heat Detector


1.0000 bh ROR Heat Detektor 187,500.00
1.0000 x Material bantu ringan 7,500.00
0.2000 Oh Buruh tak terlatih 57,000.00
0.0500 Oh Tukang listrik 65,000.00
0.0100 Oh Mandor 75,000.00

B.39 Memasang 1 titik instalasi Manual Push Button


30.0000 m' Kabel NYA 1,5 mm 2,500.00
15.0000 m' Pipa Conduit 20mm 4,500.00
1.0000 x Material bantu ringan 7,500.00
0.2000 Oh Buruh tak terlatih 57,000.00
0.1500 Oh Tukang listrik 65,000.00
0.0500 Oh Mandor 75,000.00

B.40 Memasang 1 bh Manual Push Button


1.0000 bh Manual Push Button 285,000.00
1.0000 x Material bantu ringan 7,500.00
0.2000 Oh Buruh tak terlatih 57,000.00
0.0500 Oh Tukang listrik 65,000.00
0.0100 Oh Mandor 75,000.00

B.41 Memasang 1 titik instalasi Indicating Lamp


30.0000 m' Kabel NYA 1,5 mm 2,500.00
15.0000 m' Pipa Conduit 20mm 4,500.00
1.0000 x Material bantu ringan 7,500.00
0.2000 Oh Buruh tak terlatih 57,000.00
0.1500 Oh Tukang listrik 65,000.00
0.0500 Oh Mandor 75,000.00

B.42 Memasang 1 bh Indicating Lamp


1.0000 bh Indicating Lamp 95,000.00
1.0000 x Material bantu ringan 7,500.00
0.1000 Oh Buruh tak terlatih 57,000.00
0.0500 Oh Tukang listrik 65,000.00
0.0250 Oh Mandor 75,000.00

B.43 Memasang 1 titik instalasi Alarm Bell


30.0000 m' Kabel NYA 1,5 mm 2,500.00
15.0000 m' Pipa Conduit 20mm 4,500.00
1.0000 x Material bantu ringan 7,500.00
0.2000 Oh Buruh tak terlatih 57,000.00
0.1500 Oh Tukang listrik 65,000.00
0.0500 Oh Mandor 75,000.00

B.44 Memasang 1 bh Alarm Bell


1.0000 bh Alarm Bell 265,000.00
1.0000 x Material bantu ringan 7,500.00
0.1000 Oh Buruh tak terlatih 57,000.00
0.0500 Oh Tukang listrik 65,000.00
0.0250 Oh Mandor 75,000.00

B.45 Memasang 1 bh EOLR


1.0000 bh EOLR 20,000.00
1.0000 x Material bantu ringan 7,500.00
0.1000 Oh Buruh tak terlatih 57,000.00
0.0500 Oh Tukang listrik 65,000.00
0.0250 Oh Mandor 75,000.00

B.46 Memasang 1 bh Juction Box Fire Alarm


1.0000 bh Box Panel 200 x 300 x 200 mm 325,000.00
1.0000 % Material bantu sedang 27,500.00
0.5000 Oh Buruh tak terlatih 57,000.00
0.3500 Oh Tukang listrik #N/A
0.1500 Oh Mandor #N/A

TELEPON

B.47 Instalasi Telephone dg Kabel ITC 2x2x0.6 mm dlm Pipa Conduit PVC dia 20 mm
20.0000 m' Kabel ITC 2x2x0.6 mm 5,500.00
20.0000 m' Pipa Conduit 20mm 4,500.00
1.0000 x Material bantu ringan 7,500.00
0.2000 Oh Buruh tak terlatih 57,000.00
0.1500 Oh Tukang listrik 65,000.00
0.0500 Oh Mandor 75,000.00

B.48 Memasang Direct Outlet Telephone


1.0000 bh Outlet Telepon 110,000.00
1.0000 bh Inbow dos seng 10,000.00
0.0500 Oh Buruh tak terlatih 57,000.00
0.0350 Oh Tukang Listrik 65,000.00
0.0100 Oh Mandor 75,000.00

B.49 Instalasi Kabel Feeder ITC 10 pairs


1.0000 m' Kabel ITC 10 pair 15,500.00
1.0000 m' Pipa Conduit 20mm 4,500.00
1.0000 x Material bantu ringan 7,500.00
0.0050 Oh Buruh tak terlatih 57,000.00
0.0050 Oh Tukang listrik 65,000.00
0.0050 Oh Mandor 75,000.00

B.50 Memasang 1 bh Juction Box Telepon


1.0000 bh Box Panel 200 x 300 x 200 mm 325,000.00
1.0000 % Material bantu sedang 27,500.00
0.5000 Oh Buruh tak terlatih 57,000.00
0.3500 Oh Tukang listrik #N/A
0.1500 Oh Mandor #N/A

DATA KOMPUTER

B.51 Instalasi Data komputer dg kabel UTP Cath 6 dlm pipa conduit PVC dia. 20 mm2
20.0000 m' Kabel UTP Cath 6 8,750.00
20.0000 m' Pipa Conduit 20mm 4,500.00
1.0000 x Material bantu ringan 7,500.00
0.2000 Oh Buruh tak terlatih 57,000.00
0.1500 Oh Tukang listrik 65,000.00
0.0500 Oh Mandor 75,000.00

B.52 Memasang Outlet Data Komputer


1.0000 bh Outlet Data Komputer 95,000.00
1.0000 bh Inbow dos seng 10,000.00
0.0500 Oh Buruh tak terlatih 57,000.00
0.0350 Oh Tukang Listrik 65,000.00
0.0100 Oh Mandor 75,000.00

B.53 Instalasi Kabel Feeder UTP Cath 6


1.0000 m' Kabel UTP Cath 6 8,750.00
1.0000 m' Pipa Conduit 20mm 4,500.00
0.2500 x Material bantu ringan 7,500.00
0.0050 Oh Buruh tak terlatih 57,000.00
0.0050 Oh Tukang listrik 65,000.00
0.0050 Oh Mandor 75,000.00

CCTV

B.54 Instalasi CCTV dg kabel RG 59 + power dlm pipa conduit PVC dia. 20 mm2
45.0000 m' Kabel RG 59 + power 9,500.00
45.0000 m' Pipa Conduit 20mm 4,500.00
1.0000 x Material bantu ringan 7,500.00
0.2000 Oh Buruh tak terlatih 57,000.00
0.1500 Oh Tukang listrik 65,000.00
0.0500 Oh Mandor 75,000.00

B.57 Memasang In door Camera CCTV IR type Fixed


1.0000 bh In door Camera CCTV IR type Fixed 2,850,000.00
1.0000 x Material bantu sedang 27,500.00
0.2500 Oh Buruh tak terlatih 57,000.00
0.1500 Oh Tukang Listrik 65,000.00
0.0500 Oh Mandor 75,000.00

B.58 Memasang Color Dome type camera


1.0000 bh Color Dome type camera 2,750,000.00
1.0000 x Material bantu sedang 27,500.00
0.2500 Oh Buruh tak terlatih 57,000.00
0.1500 Oh Tukang Listrik 65,000.00
0.0500 Oh Mandor 75,000.00
JUMLAH (Rp.)

11,400.00
3,990.00
4,617.00
8,775.00
9,720.00
307.50
38,809.50

17,400.00
6,090.00
4,617.00
8,775.00
9,720.00
307.50
46,909.50

25,800.00
9,030.00
4,617.00
8,775.00
9,720.00
307.50
58,249.50

51,000.00
17,850.00
4,617.00
8,775.00
9,720.00
307.50
92,269.50

84,480.00
29,568.00
4,617.00
8,775.00
9,720.00
307.50
137,467.50

22,800.00
7,980.00
3,078.00
5,850.00
648.00
2,025.00
42,381.00

38,400.00
13,440.00
3,078.00
5,850.00
648.00
2,025.00
63,441.00

60,264.00
21,092.40
6,156.00
11,700.00
1,296.00
405.00
100,913.40
95,000.00
4,275.00
6,500.00
720.00
375.00
106,870.00

145,000.00
4,275.00
6,500.00
720.00
375.00
156,870.00

185,000.00
4,275.00
6,500.00
720.00
375.00
196,870.00

225,000.00
4,275.00
6,500.00
720.00
375.00
236,870.00

315,000.00
4,275.00
6,500.00
720.00
375.00
326,870.00

96,800.00
94,400.00
181,545.00
131,271.00
31,920.00
15,385.50
182,400.00
71,825.00
108.00
1,200.00
806,854.50

105,000.00
35,000.00
1,620,000.00
17,472.00
102,450.00
131,100.00
208,000.00
50,400.00
52,500.00
2,321,922.00

126,500.00
285.00
325.00
375.00
127,485.00

30,250.00
285.00
325.00
375.00
31,235.00

39,600.00
285.00
325.00
375.00
40,585.00

64,900.00
285.00
325.00
375.00
65,885.00

181,500.00
3,135.00
975.00
750.00
186,360.00

57,750.00
3,135.00
975.00
750.00
62,610.00

675,000.00
195,000.00
130,000.00
431,000.00
15,735.00
45,000.00
72,000.00
60,000.00
250,000.00
45,000.00
37,500.00
57,000.00
48,750.00
18,750.00
85,000.00
2,165,735.00

675,000.00
520,000.00
655,000.00
15,735.00
45,000.00
72,000.00
60,000.00
250,000.00
45,000.00
37,500.00
57,000.00
48,750.00
18,750.00
85,000.00
2,584,735.00

675,000.00
520,000.00
655,000.00
15,735.00
45,000.00
72,000.00
60,000.00
250,000.00
45,000.00
37,500.00
57,000.00
48,750.00
18,750.00
85,000.00
2,584,735.00

950,000.00
260,000.00
1,530,000.00
655,000.00
15,735.00
45,000.00
72,000.00
60,000.00
250,000.00
45,000.00
37,500.00
57,000.00
48,750.00
18,750.00
85,000.00
4,129,735.00

950,000.00
390,000.00
585,000.00
655,000.00
15,735.00
45,000.00
72,000.00
60,000.00
250,000.00
45,000.00
37,500.00
57,000.00
48,750.00
18,750.00
85,000.00
3,314,735.00

1,750,000.00
431,000.00
1,965,000.00
1,310,000.00
655,000.00
1,750,000.00
550,000.00
975,000.00
435,000.00
475,000.00
15,735.00
45,000.00
135,000.00
60,000.00
450,000.00
45,000.00
37,500.00
114,000.00
73,000.00
65,000.00
26,250.00
85,000.00
11,447,485.00

225,000.00
260,000.00
65,000.00
130,000.00
210,000.00
5,245.00
22,500.00
22,500.00
75,000.00
42,750.00
22,750.00
7,500.00
85,000.00
1,173,245.00

150,000.00
195,000.00
130,000.00
175,000.00
5,245.00
22,500.00
22,500.00
75,000.00
42,750.00
22,750.00
7,500.00
85,000.00
933,245.00

225,000.00
130,000.00
350,000.00
630,000.00
5,245.00
22,500.00
22,500.00
75,000.00
42,750.00
22,750.00
7,500.00
85,000.00
1,618,245.00

235,000.00
75,000.00
7,500.00
14,250.00
4,875.00
1,875.00
338,500.00

167,400.00
75,000.00
7,500.00
14,250.00
4,875.00
1,875.00
270,900.00

155,700.00
45,000.00
7,500.00
14,250.00
4,875.00
1,875.00
229,200.00

425,000.00

7,500.00
14,250.00
4,875.00
1,875.00
453,500.00

345,000.00

7,500.00
14,250.00
4,875.00
1,875.00
373,500.00

1,350,000.00

7,500.00
14,250.00
4,875.00
1,875.00
1,378,500.00

225,000.00
35,000.00
55,000.00
10,000.00
7,500.00
14,250.00
4,875.00
1,875.00
353,500.00

367,000.00
50,000.00
70,000.00
20,000.00
7,500.00
14,250.00
4,875.00
1,875.00
535,500.00

175,000.00

7,500.00
14,250.00
4,875.00
1,875.00
203,500.00

27,500.00
10,000.00
2,850.00
2,275.00
750.00
43,375.00

42,500.00
10,000.00
2,850.00
2,275.00
750.00
58,375.00

200,000.00
10,000.00
2,850.00
2,275.00
750.00
215,875.00

27,500.00
10,000.00
2,850.00
2,275.00
750.00
43,375.00

450,000.00
10,000.00
2,850.00
2,275.00
750.00
465,875.00

145,000.00
45,000.00
17,500.00
14,250.00
9,750.00
3,750.00
235,250.00

145,000.00
45,000.00
17,500.00
14,250.00
9,750.00
3,750.00
235,250.00

290,000.00
90,000.00
17,500.00
14,250.00
9,750.00
3,750.00
425,250.00

560,000.00
90,000.00
17,500.00
14,250.00
9,750.00
3,750.00
695,250.00

450,000.00
7,500.00
14,250.00
4,875.00
1,875.00
478,500.00

50,000.00
45,000.00
7,500.00
11,400.00
9,750.00
3,750.00
127,400.00

375,000.00
3,750.00
11,400.00
3,250.00
750.00
394,150.00

50,000.00
45,000.00
7,500.00
11,400.00
9,750.00
3,750.00
127,400.00

187,500.00
1,875.00
11,400.00
3,250.00
750.00
204,775.00

75,000.00
67,500.00
7,500.00
11,400.00
9,750.00
3,750.00
174,900.00

285,000.00
7,500.00
11,400.00
3,250.00
750.00
307,900.00

75,000.00
67,500.00
7,500.00
11,400.00
9,750.00
3,750.00
174,900.00

95,000.00
7,500.00
5,700.00
3,250.00
1,875.00
113,325.00

75,000.00
67,500.00
7,500.00
11,400.00
9,750.00
3,750.00
174,900.00

265,000.00
2,650.00
5,700.00
3,250.00
1,875.00
278,475.00

20,000.00
7,500.00
5,700.00
3,250.00
1,875.00
38,325.00

325,000.00
3,250.00
28,500.00
#N/A
#N/A
#N/A

110,000.00
90,000.00
7,500.00
11,400.00
9,750.00
3,750.00
232,400.00

110,000.00
10,000.00
2,850.00
2,275.00
750.00
125,875.00

15,500.00
4,500.00
7,500.00
285.00
325.00
375.00
28,485.00

325,000.00
3,250.00
28,500.00
#N/A
#N/A
#N/A

175,000.00
90,000.00
7,500.00
11,400.00
9,750.00
3,750.00
297,400.00

95,000.00
10,000.00
2,850.00
2,275.00
750.00
110,875.00

8,750.00
4,500.00
1,875.00
285.00
325.00
375.00
16,110.00

427,500.00
202,500.00
7,500.00
11,400.00
9,750.00
3,750.00
662,400.00

2,850,000.00
27,500.00
14,250.00
9,750.00
3,750.00
2,905,250.00

2,750,000.00
27,500.00
14,250.00
9,750.00
3,750.00
2,805,250.00
DAFTAR HARGA SATUAN UPAH DAN BAHAN DI LINGKUNGAN PEMERINTAH KABUPATEN
TEMANGGUNG

No URAIAN BAHAN Satuan Harga

1 Tukang batu oh Rp 65,000.00


2 Tukang ledeng/pipa oh Rp 65,000.00
3 Tukang Gali sumur oh Rp 65,000.00
4 Tukang listrik oh Rp 65,000.00
5 Kepala tukang oh Rp 72,000.00
6 Mandor oh Rp 75,000.00
7 Operator Terlatih oh Rp 73,000.00
` 8 Buruh tak terlatih oh Rp 57,000.00

No URAIAN BAHAN Satuan Harga

1 Alarm Bell BH Rp 265,000.00


2 Alat Bantu Pasang/Bongkar - Panel Box set Rp 85,000.00
3 Ampere Meter bh Rp 325,000.00
4 Armatur Downlight RD 125 bh Rp 155,700.00
5 Armatur Downlight RD 150 bh Rp 167,400.00
5 Armatur Downlight Outbow bh Rp 235,000.00
5 Armatur Downlight Spot LED 10 W bh Rp 425,000.00
6 Armatur Lampu Baret Circular LED 10 Watt bh Rp 345,000.00
6 Armatur Lampu Emergency Exit LED 8 W bh Rp 1,350,000.00
8 Armatur Lampu TL BALK T8 1 x 36 W bh Rp 225,000.00
9 Armatur Lampu RM T8 2 x 18 W bh Rp 367,000.00
13 Balast 18W Ex PHILIPS bh Rp 35,000.00
15 Balast 36W Ex PHILIPS bh Rp 55,000.00
16 Batu bata merah (lokal) bh Rp 1,100.00
17 Batu kerikil sungai m Rp 141,000.00
18 Besi beton kg Rp 15,000.00
21 Box MCB 8 Gang bh Rp 150,000.00
21 Box MCB 12 Gang bh Rp 225,000.00
21 Box Panel 200 x 300 x 200 mm bh Rp 325,000.00
19 Box Panel 400 x 600 x 200 mm bh Rp 950,000.00
19 Box Panel 400 x 500 x 200 mm bh Rp 675,000.00
20 Box Panel 600 x 800 x 400 mm bh Rp 1,750,000.00
27 Color Dome type camera unit Rp 2,750,000.00
28 CT 100/5 bh Rp 475,000.00
29 Exhaust Fan 40 W bh Rp 450,000.00
29 EOLR bh Rp 20,000.00
31 Ball Valve dia. 3/4" bh Rp 95,000.00
32 Ball Valve dia. 1" bh Rp 145,000.00
33 Ball Valve dia. 1 1/4" bh Rp 185,000.00
35 Ball Valve dia. 2" bh Rp 225,000.00
36 Ground Rod (Galvanist) btg Rp 45,000.00
38 Inbow dos seng bh Rp 10,000.00
39 Indicating Lamp bh Rp 95,000.00
40 In door Camera CCTV IR type Fixed unit Rp 2,850,000.00
42 Kabel BC 6 mm m' Rp 12,000.00
43 Kabel BC 16 mm m' Rp 22,500.00
44 Kabel BC 50 mm m' Rp 52,500.00
45 Kabel ITC 2x2x0.6 mm m' Rp 5,500.00
46 Kabel ITC 10 pair m' Rp 15,500.00
48 Kabel NYA 1,5 mm m' Rp 2,500.00
49 Kabel NYM 3 x 2,5 mm m' Rp 14,500.00
49 Kabel NYM 4 x 4 mm m' Rp 28,000.00
50 Kabel NYMHY 2 x 1,5 mm m' Rp 9,000.00
51 Kabel NYMHY 3 x 1,5 mm m' Rp 12,500.00
52 Kabel NYY 1 x 70 mm m' Rp 115,000.00
52 Kabel NYY 3 x 4 mm m' Rp 27,500.00
53 Kabel NYY 4 x 4 mm m' Rp 36,000.00
54 Kabel NYY 4 x 6 mm m' Rp 59,000.00
56 Kabel NYFGbY 4 x 25 mm m' Rp 165,000.00
57 Kabel RG 59 + power m' Rp 9,500.00
58 Kabel UTP Cath 6 m' Rp 8,750.00
59 Kontaktor bh Rp 425,000.00
63 Lampu LED Bulb 6W "Philips" bh Rp 45,000.00
64 Lampu LED Bulb 9W "Philips" bh Rp 75,000.00
66 Lampu Strip LED 6 W/meter m' Rp 175,000.00
66 Lampu T8 18 Watt bh Rp 25,000.00
67 Lampu T8 36 Watt bh Rp 35,000.00
69 Manual Push Button bh Rp 285,000.00
70 Material bantu ringan set Rp 7,500.00
71 Material bantu sedang set Rp 27,500.00
72 Material bantu T dos,klem,dll set Rp 17,500.00
73 MCB 2 A / 4,5 kA bh Rp 65,000.00
73 MCB 4 A / 4,5 kA bh Rp 65,000.00
74 MCB 6 A / 4,5 kA bh Rp 65,000.00
75 MCB 16 A / 4,5 kA bh Rp 65,000.00
75 MCB 4 A / 6 kA bh Rp 175,000.00
75 MCB 20 A / 6 kA bh Rp 210,000.00
75 MCB C60N 6 A / 6 kA / 3 ph bh Rp 431,000.00
75 MCB C60N 16 A / 6 kA / 3 ph bh Rp 510,000.00
76 MCCB EZC100B 15 A/ 7,5 Ka bh Rp 655,000.00
78 MCCB EZC100B 30 A/ 7,5 Ka bh Rp 655,000.00
78 MCCB EZC100B 40 A/ 7,5 Ka bh Rp 655,000.00
79 MCCB EZC250F 100 A/ 18 Ka bh Rp 1,750,000.00
80 Outlet Data Komputer bh Rp 95,000.00
81 Outlet Telepon bh Rp 110,000.00
83 Pasir ayak untuk beton ( halus ) m Rp 195,000.00
84 Pasir ayak untuk beton ( kasar ) m Rp 195,000.00
85 Pilot Lamp bh Rp 20,000.00
86 Pipa PPR PN10 dia. 3/4" m' Rp 19,000.00
87 Pipa PPR PN10 dia. 1" m' Rp 32,000.00
88 Pipa PPR PN10 dia. 1 1/4" m' Rp 50,220.00
90 Pipa Conduit 20mm m' Rp 4,500.00
91 Pipa PVC klas AW dia. 1" m' Rp 9,500.00
91 Pipa PVC klas AW dia. 1 1/4" m' Rp 14,500.00
92 Pipa PVC klas AW dia. 2" m' Rp 21,500.00
93 Pipa PVC klas AW dia. 3" m' Rp 42,500.00
94 Pipa PVC klas AW dia. 4" m' Rp 70,400.00
95 Rel MCB m' Rp 52,450.00
96 Roofdrain dia. 3" bh Rp 315,000.00
97 ROR Heat Detektor bh Rp 187,500.00
98 Sakelar Grid 6 Gang bh Rp 200,000.00
100 Sakelar Seri bh Rp 42,500.00
101 Sakelar Tunggal bh Rp 27,500.00
103 Seal Tape bh Rp 4,000.00
104 Semen PC @ 50 kg kg Rp 1,600.00
105 Sekering kecil bh Rp 12,500.00
106 Selector Switch , 7 posisi bh Rp 550,000.00
107 Smoke Detektor bh Rp 375,000.00
108 Stater bh Rp 10,000.00
109 Stop Kontak bh Rp 27,500.00
110 Stop Kontak Lantai bh Rp 450,000.00
111 Terminal Nol Besar bh Rp 45,000.00
115 Volt Meter AC 220/380 V bh Rp 435,000.00