Perhitungan Pondasi Telapak
Perhitungan Pondasi Telapak
1200 mm
B. Hasil Analisa Mu
Lebar pondasi (B) = 1100 mm
Tebal pondasi (d) = 0.3 mm 300 mm
Tulangan = dia16 - 250
Jumlah tul.per lebar pondasi = 5 bh
d=
0.3
C. Analisa
Data penyelidikan tanah
gelam
g (Wet density) = 1700 t/m3 f10-6m
f (angle of internal friction) = 45 o
c (cohesion) = 0 kg/cm2
t (timbunan tanah merah) = 0 cm B=1100
Analisa Terzaghi
qult = 1,3.c.Nc.+q.Nq+0,4.g.B.Ng
gelam
f10-6m
Tabel Tersaghi untuk nilai :f,Nc,Nq,Ng
f = 0 5
Nc = 5.7 7.3
Nq = 1 1.6
B=1100
b
Ng = 0 0.5
Untuk sudut geser (f) = 45 o
b
Nc = 20.1
Nq = 6.4
Ng = 4.5
qult = 1,3.c.Nc.+q.Nq+0,4.g.B.Ng = 336.600 kg/cm2 B=1100
SF ( safety factor) = 1.5
qa tanah = qult/SF = 224.400 kg/cm2
Daya dukung gelamf10-600 = 0 kg/cm2
Rencana jumlah gelam = 0 bh
Daya dukung gelam totalf10-600 = 0 kg/cm2
qa tanah + gelam = 224.400 kg/cm2 = 22.44 N/mm2
Pu/B^2 <s'lentur
B^2 ³ Pu/s'lentur, B^2 = 14594.4741533 mm2
Page 1 of 8
B = 121 mm
Page 2 of 8
1. One way action
diambil lebar pondasi = 1100 mm
qu= Pu/B^2 = 0.270661157 N/mm2
Vu < Vc
qu*B(0.5*B-0.5*b-d)£0.6*1/6(sqrt(f'c))*B*d
=
Tebal pondasi (d) ³ 390.7598193837 mm
diambil tebal pondasi = 400 mm
Page 3 of 8
Design Pile Cap (Tanpa tulangan geser)
A. Data teknis
Gaya aksial (b. mati+b. hidup) (Pu) = 2E+05 kg
Gaya aksial Perlu/horizontal (Ph) = 0 kg Pu
Momen perlu (M1) = 70 kgm
Mutu beton (K125 ,K175, K225) = 225 kg/cm2
fy = 320 Mpa Ph
Lebar kolom pondasi(b) = 60 cm
Lebar tiang pancang(b') = 35 cm
Mu
Lebar pile cap (B) = 220 cm
Tebal pile cap (ht) = 60 cm
Penutup beton (Pb) = 7.5 cm 1 2
d=
60
B. Analisa
a.Tebal pile cap dan penulangan
T.
Berat sendiri pile cap = 6970 kg Pancang
Beban pertiang (ada 4tiang) = 81742 kg 35x35
Cek Geser
b
potongan 2-2
b
D2-2= Ptiang - berat sendiri kepala tiang = 80323 kg
Amin=q*B*h*(2*0.5*mutu beton)/
t *au = 81.8 cm2
dicoba dia. Tul (d) = 14 mm
jarak = 9 cm
Luas tulan = 37.63 cm2 < 81.8 No Ok
Mydoc/titip/jal/design/pondasi.xls
A'=0.2*Amin = 16.359 cm2
dicoba dia. Tul (d) = 14 mm
jarak = 9 cm
Luas tulan = 37.63 cm2 > 16.4 Ok !!!
Mydoc/titip/jal/design/pondasi.xls
Mydoc/titip/jal/design/pondasi.xls
Design Pile Cap (Tanpa tulangan geser)
A. Data teknis
Gaya aksial (b. mati+b. hidup) (Pu) = 2028 kg
Momen perlu (M1) = 147 kgm Pu
Mutu beton (K125 ,K175, K225) = 175 kg/cm2
fy = 240 Mpa
Lebar kolom pondasi(b) = 20 cm Ph
Lebar tiang pancang(b') = 30 cm
d=
12
B. Analisa
a.Tebal pile cap dan penulangan
T.
Berat sendiri pile cap = 1152 kg Pancang
Beban pertiang (ada 4tiang) = 1302 kg 35x35
Geser Pons
b
8 cm
B=200
h=ht-Pb =
luas bidang geser =4(b+h)*h = 4(20+h)*h
tbpu =Pu/(4(b+h)*h) <= t*bpu = 3.3951 kg/cm2 < 13 Ok
Cek Geser
potongan 2-2 B=200
D2-2= Ptiang - berat sendiri kepala tiang = -328.5 kg
Mydoc/titip/jal/design/pondasi.xls
d = 0.2
q = 0.068
t*au = 2080 kg/cm2
Amin=q*B*h*(2*0.5*mutu beton)/
t *au = 9.087 cm2
dicoba dia. Tul (d) = 10 mm
jarak = 15 cm
Luas tulan = 10.47 cm2 > 9.09 Ok !!!
Mydoc/titip/jal/design/pondasi.xls