SOP Proyek Konstruksi Terintegrasi
SOP Proyek Konstruksi Terintegrasi
PERENCANA KONTRAKTOR
QS CM OWNER REF
M/E ARS SIPIL SPESIALIS MAIN SPESIALIS
UNDANGAN
BERITA ACARA
RAPAT
RAPAT REVIEW
KOORDINASI
SUPERVISI &
PELAKSANAAN PEKERJAAN
KOORDINASI
BERITA ACARA
RAPAT
BERITA ACARA
RAPAT
LAPORAN
BULANAN
ASLI
(3 SET)
R.F.I.
KONSULTASI
PERENCANA
VARIATION
ORDER TIDAK
JAWABAN RFI
YA
NEGOSIASI & KLARIFIKASI
PENERBITAN SPP / VO
PELAKSANAAN
PEKERJAAN
PERENCANA KONTRAKTOR
QS CM OWNER REF
M/E ARS SIPIL SPESIALIS A B
EVALUASI :
SHOP DRAWING
MATERIAL
METODE PEKERJAAN
PERALATAN
TENAGA KERJA
PEK./KONTRAKTOR LAIN
QA & K3L
JADWAL PELAKSANAAN
TANDA TANGAN : FC
TIDAK
TIDAK DISETUJUI
YA
YA
PELAKSANAAN PEKERJAAN
PENGAJUAN MATERIAL
PERENCANAAN
QS MK OWNER KONTRAKTOR REF
M/E ARS SIPIL SPESIALIS
KONSULTASI
PERENCANA
SETUJU
YA
COPY ASLI
MONITORING
PERSETUJUAN
MATERIAL
Pengajuan Sub
Kontraktor
KONSULTASI
PERENCANA
SETUJU
PERUBAHAN PEKERJAAN
PERENCANA KONTRAKTOR
QS CM OWNER REF
M/E ARS SIPIL SPESIALIS
USULAN PERUBAHAN
ESTIMASI
RAPAT REVIEW
YA
INSTRUKSI
PERUBAHAN
SURAT
PERINTAH
PERUBAHAN
CEK BOQ
PENGAJUAN
HARGA
PEK. YG
MENDESAK
DIKERJAKAN MAX 14
KLARIFIKASI / NEGOSIASI
HARI
SURAT
PERSETUJUAN
PELAKSANAAN
PEKERJAAN
PERUBAHAN
PERENCANA KONTRAKTOR
QS CM OWNER REF
M/E ARS SIPIL SPESIALIS
IZIN PENGELUARAN
MATERIAL/ALAT
TANDA TANGAN : SM
EVALUASI :
MATERIAL
PERALATAN
METODE PEKERJAAN
PEK./KONTRAKTOR LAIN
JADWAL PELAKSANAAN
SECURITY PROYEK
TANDA TANGAN : FC
TIDAK DISETUJUI
YA
PEMERIKSAAN MATERIAL/ALAT
TIDAK
DISETUJUI
YA
PELAKSANAAN PEKERJAAN
PENGELUARAN MATERIAL/ALAT
PERENCANA
QS CM OWNER REF
M/E ARS SIPIL SPESIALIS KONTRAKTOR SUPPLIER
EVALUASI :
BILL OF QUANTITY
MATERIAL
METODE PEKERJAAN
PEK./KONTRAKTOR LAIN
JADWAL PELAKSANAAN
MONITOR DELIVERY
PENERIMAAN MATERIAL
(PER 2 MINGGU)
TIDAK YA
GUDANG
KEMBALI KE
SUPPLIER
SHOP DRAWING
PERENCANA KONTRAKTOR
QS CM OWNER REF
M/E ARS SIPIL SPESIALIS MAIN SPESIALIS
Uk. A1/A2/A3
EVALUASI TIDAK
MAX. 3 hari
kalender
YA
PERUBAHAN/
PENGARUH THD
DISAIN/SPEK.
Instruksi
perubahan
YA pekerjaan
PERSETUJUAN
1 hari
ARSIP
PERBANYAK
IZIN
PELAKSANAAN
PELAKSANAAN
METODE PELAKSANAAN
PERENCANA KONTRAKTOR
QS CM OWNER REF
M/E ARS SIPIL SPESIALIS MAIN SPESIALIS
Uk. A1/A2/A3
EVALUASI TIDAK
MAX. 3 hari
kalender
YA
PERUBAHAN/
PENGARUH THD
DISAIN/SPEK.
Instruksi
perubahan
YA pekerjaan
PERSETUJUAN
1 hari
ARSIP
PERBANYAK
IZIN
PELAKSANAAN
PELAKSANAAN
PERENCANA KONTRAKTOR
QS CM OWNER REF
M/E ARS SIPIL SPESIALIS
LAPORAH HARIAN :
TENAGA KERJA
PERALATAN
PEKERJAAN
JAM KERJA
CUACA
LAPORAN MINGGUAN :
PEKERJAAN
VOLUME
PROGRESS :
REALISASI MINGGU INI
MINGGU LALU
DEVIASI
LAPORAN BULANAN :
ADMINISTRASI :
DATA PROYEK
PROGRESS
SCHEDULE & S CURVE
V.O. LIST
FOTO
CUACA
TEKNIS :
SHOP DRAWING LIST
ZONING PEKERJAAN
MATERIAL LIST
RENCANA KERJA BULAN YAD
REKAPITULASI LAP. HARIAN
PERALATAN
K3L (TERPISAH)
HASIL TEST MATERIAL
ASLI ASLI
MEMBERIKAN
REKOMENDASI
JIKA PERLU
LAPORAN BULANAN :
ADMINISTRASI :
DATA PROYEK
STATUS KONTRAK
PROGRESS
MASTER SCHEDULE
S - CURVE
MONITOR V.O.
MONITOR LABORS
FOTO
PERMASALAHAN & SOLUSI
CUACA
TEKNIS :
HASIL TEST MATERIAL
MONITOR SHOP DRAWING
MONITOR IZIN-IZIN
MONITOR ZONING PEK.
MONITOR MATERIAL :
APPROVAL
SBO
ASLI
(3 SET)
PERENCANA KONTRAKTOR
QS CM OWNER REF
M/E ARS SIPIL SPESIALIS MAIN SPESIALIS
PENGAJUAN PRESTASI
PEKERJAAN
UNDANGAN
PEMERIKSAAN
BERSAMA
REVISI PROGRESS
MAX 7 HARI
BERITA ACARA
PRESTASI
SERTIFIKAT
PEMBAYARAN
BERITA ACARA
PEMBAYARAN
ASLI
KELENGKAPAN DOKUMEN
TAGIHAN
VERIFIKASI
DOKUMEN TIDAK
TAGIHAN
YA
PEMBAYARAN
AS-BUILT DRAWING
PERENCANA KONTRAKTOR
QS CM OWNER REF
M/E ARS SIPIL SPESIALIS
PEKERJAAN
SUPERVISI & SELESAI
KOORDINASI 10O% /
PARSIAL
BUAT
AS BUILT
DRAWING
REVIEW (1
BULAN)
ATAU (MAX. 2
MINGGU UTK
PARSIAL)
1. PERIKSA
2. DISTRIBUSI
PERIKSA
PEKERJAAN
VO
SELESAI
100%
JILID
1. PERIKSA
2. DISTRIBUSI
PEKERJAAN
SELESAI 100%
ATAU PARSIAL
SCHEDULE
PROCEDURE
METODE PELAKSANAAN
FORM TEST. & COMM.
PRESENTASI
TESTING &
COMMISSIONING
PEMERIKSAAN BERSAMA
DEFECT YA
TIDAK
ASLI + LAMPIRAN
COPY COPY COPY
BA ST 1
PERENCANA KONTRAKTOR
QS MK/CM OWNER REF
M/E ARS SIPIL SPESIALIS
PEKERJAAN
SELESAI 100%
YA TIDAK
TIDAK
UNDANGAN
PERBAIKAN
PEMERIKSAAN
PEMERIKSAAN BERSAMA
BERITA ACARA PEMERIKSAAN
DEFECT LIST
YA
BERITA ACARA
SERAH TERIMA
PERTAMA
PEMERIKSAAN KELENGKAPAN
DOKUMEN
SERTIFIKAT
PEMBAYARAN
& RENTENSI 5%
PROSES
TAGIHAN
PERENCANA KONTRAKTOR
QS CM OWNER REF
M/E ARS SIPIL SPESIALIS
PERBAIKAN
SUPERVISI &
CACAT
KOORDINASI
PEKERJAAN
SELESAI &
PERMOHONAN
PEMERIKSAAN
TIDAK
MENYIAPKAN
UNDANGAN
PEMERIKSAAN
PEMERIKSAAN BERSAMA
YA
BERITA ACARA
PENYERAHAN SYARAT LAIN
KEDUA
PERIKSA
SERTIFIKAT
PEMBAYARAN
RENTENSI 5%
PROSES
TAGIHAN
v Disetujui oleh,
PT. Wijaya Karya Bangunan Gedung, Tbk. PT. Ciputra Development, Tbk.